Beruflich Dokumente
Kultur Dokumente
Prepared by:
Leslie Esparza
Krisha Mehta
Sean Swearingen, Team Leader
Prepared by:
Leslie Esparza
Krisha Mehta
Sean Swearingen, Team Leader
ACKNOWLEDGMENTS
Over the course of semester we received much guidance and technical advice from both the
engineers at Chevron and the faculty at the University of Texas at Austin. We would like to
extend our thanks to those who helped make our project possible and call attention to their
contributions.
First, we would like to thank Wesley Brubaker, Chris Kurr, and Zachary Schneider at
Chevron for sponsoring our senior design project and giving us the key information and
counseling necessary to execute our project.
We would also like to think Dr. Crawford for heading the UT-SDP program which gives us
and our classmates the opportunity to work on real world projects with major companies, such as
Chevron.
Dr. Kiehne, our Mechanical Engineering faculty advisor, provided us with valuable feedback
on our project. Dr. Bommer, from UTs Petroleum Engineering department, was also kind
enough to review our vapor recovery unit design and give us insight into critical problems that
occur in the field during oil and gas production. Dr. Krueger, our graphics advisor, reviewed our
reports helped us to improve their professionalism.
John Montgomery, our teaching assistant, played a central role in our projects
development and provided us with advice and coaching throughout the semester.
TABLE OF CONTENTS
Acknowledgments................................................................................................................ i
Table of Contents ............................................................................................................... iii
List of Figures ......................................................................................................................v
List of Tables .................................................................................................................... vii
Executive Summary ........................................................................................................... ix
1 INTRODUCTION ..........................................................................................................1
2 BACKGROUND ............................................................................................................1
2.1 Chevron ................................................................................................................... 1
2.2 Project Overview .....................................................................................................2
2.3 Standard Vapor Recovery Unit ...............................................................................5
3 PROBLEM STATEMENT ..............................................................................................6
4 REQUIREMENTS AND CONSTRAINTS ....................................................................6
4.1 Requirements ...........................................................................................................6
4.2 Constraints ..............................................................................................................8
5 SUBFUNCTION DEFINITION ......................................................................................9
5.1 Function Structure and Morphological Matrix .......................................................9
5.2 Patent Search .........................................................................................................11
6 DESIGN EMBODIMENT AND ANALYSIS ............................................................. 12
6.1 VRU Design Overview ........................................................................................ 12
6.1.1 Determining Gas Compression Stages Required ................................... 13
6.1.1.1 Tank 1 Gas Compressions Feasibility Calculation ................... 14
6.1.1.2 Combined Gas Flow Compression Feasibility Calculation ...... 16
6.1.2 Interstage Cooling ................................................................................. 17
6.1.3 Water and Gas Phase Separation ............................................................ 17
6.1.4 Equipment Drivers ................................................................................. 18
6.1.5 Valve Systems ........................................................................................ 18
6.2 MATLAB Model ................................................................................................. 19
6.3 Individual Component Design ............................................................................. 20
6.3.1 Compressors ........................................................................................... 20
6.3.1.1 Compressor Selection Justification ........................................... 21
6.3.1.2 Design Calculations .................................................................. 24
6.3.2 Gas Coolers ............................................................................................ 24
6.3.2.1 Cooler Selection Justification ................................................... 25
6.3.2.2 Air-Cooled Heat Exchanger Design ......................................... 25
6.3.3 Gas-Liquid Separators ............................................................................ 28
6.3.3.1 Separator Selection Justification ............................................... 29
6.3.3.2 Vertical Separator Design ......................................................... 30
6.3.4 Water Disposal System .......................................................................... 31
6.3.5 Drivers .................................................................................................... 34
6.3.5.1 Compressor Drivers .................................................................. 34
6.3.5.2 Cooler Drivers ........................................................................... 34
6.4 MATLAB Results and Sensitivities..................................................................... 34
6.4.1 Separator and Cooler Results ................................................................. 36
6.4.2 Compressor Results and Sensitivities..................................................... 37
iii
iv
LIST OF FIGURES
Figure 1.
Figure 2.
Figure 3.
Figure 4.
Figure 5.
Figure 6.
Figure 7.
Figure 8.
Figure 9.
Figure 10.
Figure 11.
Figure 12.
Figure 13.
Figure 14.
Figure 15.
Figure 16.
Figure B.1.
Figure C.1.
Figure C.2.
Figure C.3.
Figure C.4.
Figure G.1.
LIST OF TABLES
Table 1.
Table 2.
Table 3.
Table 4.
Table 5.
Table 6.
Table 7.
Table 8.
Table 9.
Table 10.
Table 11.
Table 12.
Table 13.
vii
EXECUTIVE SUMMARY
The Vapor Recovery Unit project focuses on one of Chevrons oil and gas
production platforms in the Gulf of Mexico continental shelf. Our teams objective is to
configure a Vapor Recovery Unit (VRU) for this platform that will increase two lowpressure gas flows to a sufficient pressure and re-route the gas to enter the sales stream.
This system will compress gas coming from both an existing bulk surge tank on the
platform as well as a new tank that has not yet been installed. Chevron wants to maintain
compliance with applicable environmental laws and regulations to minimize gas losses
and increase profits. To reduce hazardous emissions on the platform, an efficient and
economical system is needed to capture hydrocarbon vapors which are currently being
flared or burnt off into the atmosphere. Further detail on our projects background and
design requirements can be seen in the Background, Problem Statement, and
Requirements and Constraints sections of the report.
Overall VRU and detailed individual component designs have been developed
through research and analysis. Our final VRU design recommendation incorporates the
following key components: gas compression and cooling, water and gas separation,
piping systems for condensate water removal, equipment drivers, and key valve systems.
Reciprocating compressors, powered by natural gas engines, are used for gas
compression. Hot gas at the compressor outlet is cooled using air-cooled heat exchangers,
which are powered by electric motors. Vertical liquid-vapor separators use gravity to
separate condensate water from dry gas after cooling, where the water is piped from the
scrubbers to a water collection point. The key valve systems include valves for the
compressor inlet and discharge, control valves for the scrubber, and a three way valve to
combine gas flows. Because of the significantly low gas pressures, multiple compression
stages are needed considering individual and combined gas streams. As a result, three
sets of compressors, coolers, and scrubbers are modeled in our overall VRU design.
Thermodynamic feasibility calculations and justifications are presented to support
our findings and component selections. A MATLAB computer model of our system
provides design simulation and verification using engineering analysis. Equipment sizing
and power specifications from the model, along with a compiled bill of materials, are
used to create a solid skid model of our design layout for visualization. A full discussion
of these topics concerning our overall VRU design and its key components can be seen in
the Design Embodiment and Analysis section of the report.
An important aspect of the proposed design solution is our financial analysis,
addressing annual sales loss, investment costs, payback, ROI, and net present value. The
Financial Analysis section in the report provides further detail on these topics. Based on
average values, considering the short payback period of 4 months, high return on
investment of 243%, and positive annual revenue of $4 million, our analysis shows
implementing our final design solution is financially sound and would be a favorable
investment for Chevron.
ix
INTRODUCTION
The Vapor Recovery Unit project focuses on one of Chevrons oil and gas
production platforms in the Gulf of Mexico continental shelf. Our teams objective is to
configure a Vapor Recovery Unit (VRU) for this platform that will increase two lowpressure gas flows to a sufficient pressure to enter the sales gas stream. In addition to
conveying our understanding of the project background and problem, we will describe
and justify our decisions made when generating ideas for design. Our primary focus will
be on outlining the design analysis, embodiment, and results for our final design model
and individual component designs. Our team will discuss the financial analysis associated
with our project solution, as well as provide recommendations for further solution
improvements and future studies for the project. Also included in this report is a project
Gantt Chart outlining our project time schedule, and a specification sheet detailing the
project-specific design requirements and constraints for implementing a VRU system.
BACKGROUND
2.1
Chevron
Our sponsor, Chevron, is a major oil and gas company that has over 62,000
companies that are involved in all aspects of upstream and downstream activities,
including the exploration, production, refining, distributing, and marketing of
hydrocarbons as finished oil and gas products. In addition to producing oil and gas,
Chevron is also involved with power production and is the worlds leader in producing
geothermal energy. Chevron also has mining and chemical production divisions and
invests in researching renewable fuels. Outside of oil and gas production, Chevron is
well known for its fuel additive Techron, which acts as a detergent and prevents engine
build-up [1].
Chevron is one of the largest producers of oil and natural gas on the Gulf of
Mexico shelf. In addition to being the largest lease holder on the outer continental shelf,
Chevron owns 313 major structures in the Gulf of Mexico and in 2008 maintained an
average daily net production of 76,000 barrels of crude oil, 439 million cubic feet of
natural gas and 10,000 barrels of natural gas liquids. Working with engineers in Houston,
TX and Covington, LA, our team will be focusing on one of Chevrons oil and gas
production platforms in the Gulf of Mexico continental shelf [2].
2.2
Project Overview
Our project involves increasing the reliability and efficiency of gas production,
presenting a unique set of cost drivers and environmental concerns due to its offshore
location. Offshore equipment reliability is a high priority because loss of production and
equipment replacement present financial liabilities for Chevron. Environmental factors
are also of concern and Chevron wants to reduce its carbon emissions on this platform by
recovering excess low pressure gas and adding it to the sales gas stream rather than
burning it off, also known as flaring. Gas flaring and venting are highly regulated in the
Gulf of Mexico by the Minerals Management Service (MMS).
Our team will focus on one of Chevrons offshore production platforms in the
Gulf of Mexico, where oil and gas are produced and processed from underground
deposits. A general flow diagram of this platform, as seen in Figure 1 on the following
page, gives a basic overview of how oil, water, and gas are separated from the well
streams. The gas and liquids flow from the well head through high, medium, and low
pressure separators. The liquids, consisting of oil and water, eventually exit the low
pressure separator and enter the oil dehydration unit. At this stage the water is sent for
treatment to be dumped back into the ocean, while the dry oil is pumped to shore. The
excess gas needs to be compressed to be sent to shore and must go through the inlet of the
sales compressor. The high and medium pressure gas flows are at sufficient pressures to
enter the second and first stages of the sales gas compressor, respectively. Currently, the
excess low pressure gas must flow from the low pressure separator to a bulk surge tank,
where the gas is then flared to the atmosphere rather than going through a Vapor
Recovery Unit (VRU). This VRU would allow for excess low pressure gas to achieve a
sufficient pressure to enter the first stage of the sales compressor, recovering some of the
gas.
Liquid Flows
Gas Flows
Alternate LP Gas Flow
Sales
Compressor
1st
stg
High
Pressure
Separator
1000 psig
Medium
Pressure
Separator
Low
Pressure
Separator
200 psig
Well Stream
Clean H2O
Dry Oil
35 psig
Oil
Dehydration
2nd
stg
Bulk
Surge
Tank
VRU
Flare to
Atmosphere
incorporating it into the sales stream will recover vapors and boost sales while
maintaining compliance with applicable laws and regulations.
2.3
compressor, and a liquid transfer pump (with its associated drivers). Figure 2 below
depicts a standard single stage VRU attached to a crude oil storage tank. Initially,
hydrocarbon vapors are drawn out of the storage tank under low pressure and sent to a
suction scrubber which separates excess water from the gas. The condensed water is then
sent back to the storage tank via the liquid transfer pump while the gas in the suction
scrubber flows through a compressor. From the compressor, the vapors are metered and
transported to either the sales gas line or back to the production facility to drive other
equipment. The control pilot that separates the stock tank from the suction scrubber
prevents the formation of a vacuum in the top of the stock tank by shutting off the
compressor and allowing back flow into the tank [3].
PROBLEM STATEMENT
Our team will research various Vapor Recovery Unit (VRU) equipment to develop
design recommendations and select the optimal configuration for incorporating a VRU
system on the platform while meeting key design criteria. This VRU will need to
compress excess low pressure gas coming from both an existing bulk surge tank as well
as a new tank that has not yet been installed. This gas must be brought up to a sufficient
pressure in order to enter the inlet of the sales gas compressor.
4.1
Requirements
The first page of the specification sheet shown in Table 1 outlines the functional
This
environmental factor, which is one of the key drivers for installing the VRU, will be
achieved by taking low pressure gas that that would normally be burned off or flared
and increasing its pressure so that it can be added to the sales gas stream and sold or
rerouted back to the platform for use on-site.
Another significant requirement for this project is to bring the low pressure gas
from the new bulk surge tank and add it to the gas from the existing bulk surge tank.
This is done to recover the low pressure gas from a damaged facility by integrating it
with a functional facility.
6
Other key requirements for the VRU include making it easy to install and
minimizing its size and weight due to the limited space available on the platform. It is
also important to ensure that the design operates within safe temperature and pressure
limits. This will ultimately prevent the need for costly repairs and extend the useful life
of the gas processing equipment that makes up the VRU. The VRU design must also be
judged on its financial merits and should provide a cost-benefit to Chevron in addition to
complying with environmental regulations.
4.2
Constraints
The second page of the specification sheet, Table 2, details the five categories of
constraints associated with our VRU design: pressures, temperatures, flow rates,
equipment sizes, and gas properties. The specifications for some pressures, temperatures,
and flow rates were determined by first locating where the VRU would be integrated with
the existing equipment, and then looking up the relevant information from our facilitys
process and instrumentation diagrams (P&ID). The rest of the pressures, temperatures,
and flow rates were found by asking our sponsor what could generally be expected from
the additional low pressure gas that would be brought in from the damaged facility. The
limitations on equipment size and placement can be found by looking at the equipment
location diagrams for our platform. The gas properties found in the specification sheet
were determined by reviewing the results of a gas sample analysis test and will be
assumed constant for all further models and analysis.
SUBFUNCTION DEFINITION
5.1
also learned that the process of transferring condensed water and compressing gas
pressure may require a driver. Due to the flow process, if one of the components fail, the
entire process will need to be shut down until the component is repaired.
10
5.2
Patent Search
Throughout the design process our team has performed a patent search to generate
ideas for selection and design of VRU components and alternative vapor recovery
systems. The following section is a description of two patents that we found to be the
most relevant for the systems we considered in our project design.
The first patent, Air Cooled Exchanger, describes an improved air-cooled heat
exchanger with shields attached to each tube bank to deflect wind entering the exchanger
without affecting cooling air flow on the tube exterior [5]. This proposed system seen in
Figure 4, which has shields comprised of a wind deflecting front wall and triangular side
walls, would be advantageous for improving control of exchanger operations in difficult
weather with high wind velocities. This invention is significant for the project because
certain design aspects were adopted for modeling the inter-stage gas coolers in our VRU
system. It also provided insight into reflecting adverse atmospheric conditions in our
design sensitivity analysis, which is especially relevant considering our projects offshore
location.
The second patent, Eductor System and Method for Vapor Recovery, outlines a
system for recovering discharged vapors from hydrocarbon processing systems to prevent
or minimize harmful emissions [6]. This design uses venturi eductor technology to
combine a high-pressure motive fluid with low-pressure vapors to discharge gas at an
intermediate pressure and inject it into existing process equipment. Considering our
projects objective of economically capturing hydrocarbon emissions, while maintaining
Chevrons compliance with environmental regulations, this non-mechanical alternative
vapor recovery system is relevant for our projects gas production and processing
application. However, due to the lack of a high-pressure gas source on the offshore
facility, we have only utilized this idea for future project recommendations.
6.1
input from our sponsor we created the VRU layout shown in Figure 5.
The
thermodynamic properties associated with states 1-9 can be found in Table 3. The
following sections will outline the process that led us to this design.
12
ratio for each stage of compression less than 4. This prevents the gas from reaching
critical temperatures in excess of 300 oF which will damage compressors [7]. To create
our design we performed design feasibility calculations for both the 5-45 psig gas
compression from stock tank 1 and the 45-90 psig gas compression for the combined
3MMSCFD flow stream.
6.1.1.1 Tank 1 Gas Compression Feasibility Calculation
Figure 6 details the thermodynamic constraints associated with gas compression
from tank 1.
Assuming negligible changes in potential and kinetic energy and adiabatic compression,
the first law of thermodynamics reduces to [7]:
If we assume constant specific heat for the gas, the isentropic outlet temperature can be
found by the relation [7]:
14
Where (P2/P1) is the compression ratio, K is the gas heat capacity ratio, and T2s is the
isentropic compressor outlet temperature.
compressor outlet has been determined the actual outlet temperature can be found from
the relation [7]:
Where c is the isentropic compressor efficiency which we have assumed to be 83% for a
reciprocating compressor [8]. As expected, the outlet temperature for the compressor
was in excess of 300oF. With this in mind we decided to add a second compression stage
and an interstage cooler to the design as seen in Figure 7.
15
From the Handbook of Natural Gas Transmission, we found a rule of thumb relation that
said that interstage air cooling could result in output cooler temperatures of 25oF above
ambient temperature. Assuming Steady State Steady Flow isentropic compression and
negligible pressure drop across the cooler, we followed a similar procedure to the single
stage compression and determined the intermediate temperature T3 as well as T5. This
procedure resulted in compressor operating temperatures safely below the critical
temperature of 300oF.
16
Minimizing
scrubbers in our design it is necessary to transport the excess water to a holding tank to
be cleaned and disposed of. On the bottom deck of the production facility where the VRU
will be installed, there is a holding vessel called a sump tank where excess water
produced at the facility can be stored. Since the VRU will be installed on the top deck of
the facility, condensate water will be piped from the scrubbers to the sump tank using
17
gravity and internal scrubber pressure as a driving force. It is important to note that we
have assumed that changes in pressure, temperature and volumetric gas flow rates across
the scrubbers will be negligible.
6.1.4 Equipment Drivers
Compressors and coolers are the only two pieces of equipment in the VRU that
require an outside power source. As a requirement from our sponsors, the compressors in
the VRU will be powered with natural gas drivers. These natural gas drivers typically
come in the form of internal combustion engines and will provide power to all three of
our compressors. The cooling systems typically have a low horsepower requirement and
will be powered electrically from the production facility.
6.1.5 Valve Systems
To set limits on the scope of our design we have decided not to design the valves
in the VRU in detail but to simply show the placement of key valve systems in a detailed
VRU design flow diagram found in Appendix B. There are three key valve systems
found on the VRU design in Appendix B including compressor valves, scrubber valves
and a three way valve. In order to control fluctuating gas flows and prevent damage, each
compressor in the VRU is equipped with an inlet valve and discharge valve, labeled CIV
and CDV respectively. In addition to controlling gas flows through the use of a pressure
control valve (PCV), scrubbers must also be able to control the condensate liquid flow to
the sump tank. This will be achieved through the use of a liquid control valve or LCV.
A three way valve between state 7 and 8 on the VRU flow process diagram will be used
18
to combine the gas flows from stock tank 1 and 2 so that they may enter the final
compression stage.
6.2
MATLAB Model
A critical aspect of our engineering analysis for the project was to apply
principles of thermodynamics, heat transfer, fluid mechanics, and gas separation to verify
our proposed VRU configuration. As a result, we have created a computer model to
simulate our developed VRU design using MATLAB. From this model, we automated
our final design and obtained significant outputs by running simulations with varying key
parameters. It also allowed us to examine and evaluate each individual component design
in greater detail and adjust assumptions made as necessary. This feature facilitated the
troubleshooting process for our design since each key component is modeled as a
separate entity that can be modified individually.
These computer simulations provided us with a collection of valuable data for our
design: temperatures at all key states including compressor outlet temperatures;
compressor and cooler brake horsepower to determine overall power required to drive the
system; scrubber and cooler sizing specifications; and effects of deviating ambient
temperatures, and flow rates. Some of this data, particularly the power requirements and
dimensions, were important factors in sizing our VRU system for the platform and
determining capital expenditure cost estimates for our financial analysis.
The inter-stage coolers and vertical separators in our VRU configuration are
modeled as separate sub-functions that are called in from the main MATLAB function,
where the overall VRU program incorporates the isentropic compression analysis of the
three compressors to reflect different compression stages in our design. The MATLAB
19
flow chart for the main function can be seen in Appendix C.1, while the separator and
cooler flow charts are in Appendices C.2 and C.3, respectively. Another function was
created to calculate the specific heat capacity of the gas at variable temperatures, using
both the specific heat polynomial expression and, assuming the gas is treated as an ideal
gas mixture, mass composition for the individual gas components. This function, whose
MATLAB flow chart can be seen in Appendix C.4, proved to be extremely beneficial in
easing the automation process of our model algorithms. The MATLAB code for these
four functions can be seen in Appendices D.1-D.4.
The key input variables for our program included the temperatures, pressures, and
flow rates of the gas streams from both stock tanks, as well as the specific gravity and
molecular weight of the gas. To verify the feasibility and output values of our model, we
produced sample calculations for the compressors, coolers, and scrubbers, and provided
justifications for assumptions made in our analysis; these calculations can be seen in
Appendix A and Appendices E-F. Each of these components will be discussed in further
detail in the next section of this report.
6.3
6.3.1 Compressors
Compression is the central element in VRU design and successful compressor
selection is vital to a VRUs operation. Figure 9 divides natural gas compressors into
three distinct groups: positive displacement, dynamic, and thermal type compressors.
Though ejectors have been used in onshore gas pressure boosting, they require a high
20
pressure motive gas flow that is not available at our offshore site and will not be
considered in our compressor selection.
21
and power costs than centrifugal compressors while maintaining higher adiabatic
efficiencies [8].
increase the pressure of a gas stream, require less maintenance than reciprocating
compressors (due to having fewer moving parts) and have lower installation costs [8].
The benefits of each compressor type are summarized in Table 5 below. Since adiabatic
efficiency and maintenance are both key concerns in compressor selection, there is no
clear choice based on the aforementioned criteria. After running our MATLAB model
for each type of compressor we found that the brake horse power (horse power adjusted
for mechanical losses) requirements for the compressors were similar (within 5%), which
also prevented us from using power requirements as a deciding criteria. Our final
decision to use reciprocating compressors came after finding that using centrifugal
compressors led to higher interstage temperatures, resulting from their lower adiabatic
efficiencies. Since larger coolers are needed to offset the damaging high interstage
temperatures and production floor space is limited, we found reciprocating compressors
to be the preferred choice.
Table 5. Compressor Selection Decision Matrix.
23
Where Zavg is the average compressibility factor; QG,SC is the standard volumetric
flow rate of gas (MMSCFD). T is the compressor suction temperature (R). P2 and P1 are
the discharge and suction temperatures (Psia).
reciprocating: 0.72-0.82, for centrifugal: 0.99), and is the compression efficiency (1 for
reciprocating, 0.8-0.87 for centrifugal units) [7].
6.3.2 Gas Coolers
Gas coolers are typically used as intercoolers for multiple compression stages or
for compressor suction and discharge [9]. Gas cooling is a significant aspect of our VRU
design by helping prevent equipment damage and lower compressor power requirements.
These coolers cause minor pressure losses of the gas depending on the design [7].
However, for our design this pressure drop is considered negligible and gas cooling is
assumed to be done at constant pressure. Based on our research, calculations, and
selected cooler size, this critical assumption can safely be made and has been approved
by our Chevron sponsors and faculty advisor, Dr. Thomas Kiehne.
24
components: tube bundle, axial fan, fan drive assembly, and supporting structure [8]. Hot
gas flows through tubes in the tube bundle, the heat-transfer device for the cooler, where
fins are applied to increase heat-transfer effectiveness by providing an extended surface
on the air side [12]. We used the most typical fan configuration for our design, known as
forced-draft, where the fan below forces air up across the tube exterior; a basic layout of
this configuration can be seen in Figure 11.
26
underlying ACHE thermal design involve basic heat transfer analysis, where heat and
material balances are performed for the air and gas sides of the exchanger.
The heat dissipated by the gas (Qgas), absorbed by the air (Qair), and transferred from gas
to air (Q) are all equal [9]:
Qgas = Qair = Q
which can also be expressed as [9]:
mgas Cpgas Tgas = mair Cpair Tair = U A F (LMTD)
where m is the mass flow rate, Cp is the specific heat capacity, T is the temperature
change, U is the overall heat-transfer coefficient, A is the heat transfer area, F is the
LMTD correction factor, and LMTD is the log mean temperature difference that acts as
the driving force of heat transfer.
Using the relationship above, we calculated the total extended surface heat
transfer area and converted this value to a bundle face area depending on the tube
geometry and bundle layout. These parameters also allowed us to calculate the air mass
flow rate and velocity. The minimum fan area and fan diameter were calculated using the
bundle face area and fan coverage ratio. To determine the total pressure loss across the
fan, we summed the calculated dynamic fan and air static pressure drops. Finally, the fan
driver brake horsepower was estimated using average fan and speed reducer efficiencies,
total fan pressure drop, and the actual volumetric flow rate of air at the fan inlet [8].
Sample calculations and key assumptions detailing this cooler design methodology are
outlined in Appendix E.
27
6.3.3
Gas-Liquid Separators
Liquid-vapor separators are one of the most common types of process equipment.
As discussed in the VRU design section of the paper, water vapor extraction is crucial for
prolonging compressor life and preventing equipment damage. Though there are three
main types of gravity phase separators (horizontal, vertical and spherical) we will be
limiting our discussion to horizontal and vertical scrubbers because spherical separators
are only used for high pressure service which does not apply to our project constraints
[8]. For both horizontal and vertical scrubbers, gas-liquid separation is accomplished in
three stages. Primary separation, section A in Figure 12, occurs when incoming gas hits
the inlet diverter plate causing large water droplets to coalesce and fall into section D
from gravitational forces.
causes the smaller water droplets in the gas flow to fall through the disengagement area
into section D. Finally, the smallest droplets of water are collected by the mist extractor
in section C before the gas exits the separator [13].
28
Figure 12. Vertical and Horizontal Two Phase Separator Schematic [8].
29
where QV is the volumetric flow rate of gas in ft3/sec and UV is the vertical terminal vapor
velocity of a single water droplet falling through the disengagement area of the separator
in ft/sec. Once the vessel inner diameter has been found, the seam to seam height of the
separator HT in Figure 13 must be determined, where HT is simply the sum of the heights
HD, HLIN, HS, HH, HLLL and 1.5 ft. The lower liquid level height (HLLL), distance between
inlet nozzle and liquid level (HLIN ), and distance between inlet nozzle and mist extractor
HD are easily determined from pressure dependent sizing charts given in the paper by
Svrcek. Other heights that deal with the liquid level in the separator such as HS and HH,
require more detailed calculations and are outlined in Appendix F.
30
6.3.4
the VRU system, we found the most viable and economical choice for our project would
be to model a piping system that disposes the water into a sump tank, which is a mass
tank vessel at atmospheric pressure that contains collected water from other equipment on
the facility.
Since water flow from our three scrubber designs is substantially low, we
eliminated the need for liquid transfer pumps and their associated drivers in our system,
simplifying our overall VRU design. Instead, this piping system uses the pressure
difference from gravity to push the liquids out of the scrubbers and into the sump tank,
31
which is currently located on the bottom deck level of the platform. According to
Chevron, our VRU system will be installed above the tank, allowing us to utilize this
height difference and use gravity as the key driving force of this piping system.
Our analysis for determining the required pipe sizing for each scrubbers water
flow in our design was based on applying Bernoullis principle, assuming an
incompressible and non-viscous water flow. Standard pipe sizes vary from to 2 in
diameter with increments, as per Chevron. We have also accounted for pressure losses
in the pipe due to friction, which depends on the average water velocity, pipe length and
diameter, and a friction factor obtained from the Moody diagram. The friction factor is
based on pipe roughness and the Reynolds number for determining turbulent or laminar
flow [9]. To account for losses from expected bends and valves in the piping, Chevron
has provided us with an equivalent pipe length of 300 ft from each scrubber to the sump
tank for our calculations.
Using Bernoullis equation to combine the fluid energy in terms of elevation (h),
velocity (v), and pressure (P) between the scrubber and sump tank, the total energy can
be expressed as [9]:
P1 + v1 + gh1 = P2 + v2 + gh2 + Ploss
The pressure loss, using the DArcy-Weisbach Equation, is expressed as [9]:
Ploss = (f Leq /D)( vavg)
where f is the friction factor, Leq is the equivalent pipe length, D is the pipe diameter, and
vavg is the average water velocity in the pipe. For the height difference between the
32
scrubbers and sump tank, we assumed the VRU would be installed two deck levels above
the tank based on our systems skid dimensions and the equipment location diagram of
the platform. Provided that the pipe inlet at the sump tank is located 6 from the bottom
as per Chevron, and using the known height of 18 per deck level, we calculated the
elevation difference to be 355. Using these equations and assumptions, along with the
pressures and calculated water velocities for each scrubber, we created an Excel
spreadsheet to determine the average water velocity in the pipe for each scrubber design
at different standard pipe diameters. These results are summarized in Table 6.
Table 6. Condensate Water Piping Results.
The feasibility analysis of our piping system was based on ensuring that the water
velocity in the pipes remained between 5 to 15 ft/s to avoid pipe damage. According to
Chevron, high water flows cause pipe erosion, while low velocities cause pipe corrosion.
Using our data in Table 6, we were able to select the feasible pipe diameter for each
scrubber depending on which average pipe velocity fell within this velocity range. As a
result, both scrubbers 1 and 2 require diameter piping, while scrubber 3 requires a 1
pipe diameter for water condensate removal.
33
6.3.5
Drivers
In order to power our compressors and air coolers, we need to look at what types
key parameters to determine power and sizing requirements for each of the compressors,
34
scrubbers, and coolers in our VRU design. To run the overall MATLAB VRU program at
average conditions, we used the pressures, temperatures, and flow rates listed earlier in
the report in Table 3. These base conditions consist of an ambient air temperature of 80oF
at average gas flow rates.
From a practical standpoint, certain aspects associated with our design change on
a daily basis. To simulate these variations, we used our MATLAB program to run
multiple cases with varying parameters to reflect realistic conditions and analyze the
effects on key model outputs. Performing this sensitivity analysis allowed us to refine our
model and adjust assumptions made based on our designs feasibility in extreme
conditions. Two key fluctuations are modeled in our VRU design: ambient air
temperatures and gas flow rates. A summary of these sensitivity cases can be seen in
Table 7, and these cases will discussed in further detail in the compressor results section
of the report. We have considered sensitivity effects solely on the three compressors in
our model because altering these conditions only had a significant impact on the
compressor output values. The results presented for the scrubber and cooler designs were
obtained at average conditions using the values for case 2, or the base case, as seen in
Table 7.
Table 7. Sensitivity Cases.
35
6.4.1
containing the inner separator diameters (Dvd) and seam to seam lengths (Lss) in feet.
These values can be seen in Table 8. Since vendors only make separators with diameters
and lengths in 6-inch increments, the dimensions were converted to inches and then
rounded up to the next multiple of six inches. The slenderness ratio (Lss / Dvd) for each
separator was then calculated based on the rounded dimensions; these values can also be
seen in Table 8. Typical slenderness ratios for two-phase separators fall in the range of 3
to 5, and all three of our separators meet these criteria [8].
Table 8. Separator Design Outputs.
We obtained the necessary outputs from the model to determine the horsepower
and size requirements for our three cooler designs, providing data for the cost analysis
and skid model. These values, as seen in Table 10, include the fan driver brake
horsepower, total extended surface heat-transfer area of tubes (Ax), tube bundle face area
(Fa) which represents the heat-transfer surface available to airflow, and fan blade
diameter (Dfan) rounded up to the next available fan size. The total power required to
36
drive our entire VRU system was determined using the cooler and compressor brake
horsepower values.
Table 9. Cooler Design Outputs.
6.4.2
air temperature to model three cases: minimum (cold), average, and maximum (hot)
temperatures. After simulating these cases, also referred to as cases 1-3 in Table 7, our
results showed that both the outlet temperature and brake horsepower for compressors 2
and 3 increased with ambient temperature, as seen in the compressor outputs for cases 13 of Table 10. When compared to our base case conditions, the outlet temperature and
brake horsepower changed by an average 11% and 4%, respectively. The outlet
temperature is a critical aspect of our design as it determines compression feasibility. For
the hot conditions (case 3), we observed that the outlet temperature for compressor 2 was
slightly above the critical temperature of 300oF, illustrating that our design may not be
feasible for extremely hot weather without making key changes. To minimize these
compressor outlet temperatures for extreme conditions, many future modifications can be
made to our design: add more air cooling, use or add water cooling, increase number of
37
compression stages, change compressor type, increase compressor efficiency, and/or resize the existing compressors.
Surging effects were also considered, as the gas flow rates coming from both
stock tanks are constantly fluctuating, especially with the presence of excess liquids or
pipeline pressure changes. To model these deviations in flow, the given gas flow rates
were used as averages, while 30% of these values provided the maximum and minimum
flow rates; these conditions are indicated as cases 2, 4, and 5 in Table 7. According to our
design results, the brake horsepower for all three compressors significantly increased
with gas throughput, as seen in Table 10. Compressor power changed by an average 30%
when compared to our base case values, which stresses the importance of accounting for
extreme conditions in our design. Compressor brake horsepower is a key design output
because it not only determines minimum sizing and power requirements for the
compressor designs, but also affects compressor selection, equipment cost analysis, VRU
skid layout for the platform, and the total power required to run our system.
38
6.5
Bill of Materials
Before creating a skid layout of our proposed design, we had to list all
components with their dimensions in a Bill of Materials (BOM) as shown in Table 11.
Dimensions were determined using product catalogs from vendors, MATLAB models,
and calculations described above [14,15]. The BOM was also needed to determine part of
the financial costs concerning capital expenses, where costs for the specific components
were obtained using values from 2003 [16]. We doubled the cost values to account for the
recent increase in raw materials and labor rate costs. The total equipment cost was
estimated to be approximately $750,000, which was also used for further financial
analysis. The BOM provides a layout of the type and quantity of individual components
needed for the VRU system as well as their estimated costs.
39
6.6
platform that will be able to withstand the weight of components placed on top. The VRU
components will be placed on a skid, transported, and finally be placed on the production
platform offshore. To fit on the production platform, we had to focus on reducing the skid
size as much as possible. From the BOM, we were able to lay out a two-dimensional
sketch of the VRU on the skid. Figure 14 shows the two-dimensional sketch from the top
view.
40
Key
Scrubbers
Coolers
29 ft.
Compressors
Cooler 2
Cooler 1
Cooler 3
12 ft.
S1
Com 1&2
S2
Com 3
S3
3 MMSCFD
2 MMSCFD
1 MMSCFD
5 psig
90 psig
45 psig
41
The final dimensions for the skid will be 29 ft. long and 12 ft. wide with a
maximum height of 10 ft due to scrubber 3s height. The components are spaced 2 ft.
apart from each other and 6 in. from the edges of the skid to allow access for piping and
maintenance.
Figure 15 is a three-dimensional model of our proposed design following the
same layout, from left to right, as the two-dimensional model in Figure 14. As seen in
Figure 15, the two stage reciprocating compressor on the left is much larger in
comparison to the single stage reciprocating compressor because it will have to
recompress two streams. The heat exchangers shown in the back are the largest pieces of
equipment in our final design while the vertical scrubbers are the tallest.
42
FINANCIAL ANALYSIS
7.1
focus to financial costs. Currently the gas stream of 45psi (1 MMSCFD) is being burnt
off into the atmosphere, so we calculated the value of the gas that was being lost. To do
this, we needed a cost estimate of how much the natural gas is worth in todays market,
also known as spot price. Since the spot price of natural gas changes every day, we chose
to look at the spot trends over the last year, published on online markets, as well as future
price predictions from natural gas price traders and the Energy Information
Administration. These prices per million British thermal units (MMBtu) for November
11th can be seen in Table 12.
Table 12. Past and Predicted Natural Gas Spot Prices [17,18,19].
To estimate the value of natural gas being lost in a given day, we took the Henry
Hub spot price on the day of November 11, 2009, since this is the closest value to
present day, which was $4.18 per million British thermal units [18]. To calculate the sales
amount that is lost due to flaring, we had to account for the natural gas heating value
which is 1,028 Btu/SCF. Using the equation below we are able to compute the value of
the original 1 MMSCFD stream being burnt off:
43
Annual Sales Loss = Flowrate (Q)* Heating Value (HV)* Spot Price* Days in a year
Annual Sales Loss = 1 MMSCF/day * 1,028 Btu/SCF* $4.18/MMBtu * 365 days/year
From our calculations, the annual sales loss from the 1 MMSCFD stream alone is
approximately $1,568,400 a year. Instead of earning this profit amount, Chevron is
currently burning off the 1 MMSCFD gas stream.
7.2
Investment Costs
Capital, installation, and operations and maintenance (O&M) costs are related to
the design flow capacity of the stream. We determined the costs for a VRU system for
the 3MMSCFD flow capacity leaving the VRU. Due to Chevrons request we were not
able to contact vendors for specific prices on equipment; therefore, we derived our
financial values from extrapolating capital, installation, and O&M costs available from
EPAs Natural Gas Star Program [20]. Capital costs were also compared to values of the
specific equipment costs [16]. Table 13 lists the capital, installation, and O&M costs
derived.
Table 13. VRU Costs [3].
44
Since the above values were obtained in 2004, we doubled the cost estimate to
take into account recent increases in labor rates, installation costs, deck differences, cost
of raw materials, and equipment costs. Therefore, the cost estimates we focused on for
our design were based on the 6000 MSCFD design capacity, rather than the 3000
MSCFD, to have a more conservative and accurate representation of todays prices.
Design capacity is the maximum fluid flow the VRU will experience while
running. As fluid capacity increases, the investment cost also increases. Capital costs
include the cost of the equipment: compressors, separators, and coolers. Installation costs
include the cost of a crew to install the system and any extra equipment needed to
transport the skid onto the platform. In the above example, installation cost is calculated
as 75% of the capital cost [20]. Operation and maintenance costs incorporate the cost of
the crew to maintain the VRU, as well as the operating cost to keep the VRU in working
order. The investment cost is the sum of the capital and installation cost. As seen in
Table 13, the investment cost for our project is approximately $1.3 million. Equipment
cost was the major factor in contributing to the investment cost and unavoidable since it
relies on the capacity flow.
7.3
payback period, and the return on investment after the installation of the VRU. The value
of recovered gas is the annual value that Chevron may potentially earn by selling off the
natural gas recovered by the VRU. The price range of the recovered gas was based on a
low and high range from past and future natural gas spot prices from Table 12. To
45
calculate the value of recovered gas, we used the same annual sales loss equation as
stated previously.
Figure 16 graphs the predicted value of recovered gas at 75% runtime versus the
natural gas spot price. A 75% runtime was chosen to take into account the annual
downtime from maintenance on the VRU equipment [21]. The value of recovered gas for
our range of $4.18/MMBtu to $6.50/MMBtu (highlighted in Figure 16) varied from $3.5
million to $5.5 million. In comparison to the initial investment cost of $1.3 million, the
profit exceeds the initial cost by double to triple the cost.
$25,000,000
Dollar Amount
$20,000,000
$15,000,000
Value of
Recovered
Gas at 75%
NPV 5yrs
$10,000,000
$5,000,000
$0
$0.00
$2.00
$4.00
$6.00
$8.00
$10.00
Figure 16. Value of Recovered Gas and Net Present Value vs. Natural Gas Spot Price.
Now that we know the investment cost and the value of recovered gas, we were
able to calculate payback and return on investment. The payback period tells us how
long it will take for incoming cash flow to equal the amount invested on implementing
46
the VRU system. The payback period was calculated by dividing the initial capital and
installation costs by the annual value of the recovered gas. For our low and high range
for natural gas spot prices, we calculated payback to be from about 3 months to less than
5 months. This is a considerably short payback and favors the installation of our VRU on
the platform.
The return on investment differs from the payback period because it determines
how much profit is gained in comparison to the initial investment.
The return on
even if implementing the VRU on the platform does not add much financial contributions
we chose a small discount rate (i) of 10%. The discount rate is the minimum percentage
price a company would like to be returned by an investment. By using the 10% discount
rate, we calculated the net present value (NPV) of the project for five years.
47
i = Discount rate
CC = Capital cost
O&MC = Operation and maintenance cost
The present value of an annuity was obtained from economic tables [22] and based on the
discount rate of 10% for a five year span.
Again, we took a range considering the changes in natural gas prices. Figure 16
also depicts the linear increase in net present value in relation to the natural gas price.
For our low/high range, net present value ranged from $11.3 million to $18.8 million.
Since net present value is greater than zero, this project can be deemed a good investment
because the company would not be losing any money; in fact, they can still make $11 to
$18 million dollars more than the 10% return desired.
Almost as important, is the annual revenue Chevron can expect to see after
installing the VRU system, also known as annuity. Taking the net present value, we
back-calculated to obtain the annual revenue. By knowing the interest rate and the
number of years, we determined the annuity of the present value using the conversion
factor (1/PVIFA). The equation used the equation:
Annuity = Net Present Value * (1/PVIFA).
After calculation, for the low and high gas spot prices, the annuity ranged from $3
million to $5 million. After incorporating the VRU system on the platform, Chevron can
expect positive annual revenue from the recovered natural gas.
48
Considering the short payback, high return on investment, and positive values of
net present value and annuity, the financial analysis proves to benefit Chevron financially
and would be a great investment if the VRU is implemented. If natural gas prices
continue to increase, Chevron will be able to obtain more revenue in the years to come.
COST ESTIMATE
No costs were associated with our project. A prototype was not required for our
project, eliminating material costs. The MATLAB and SolidWorks software we used
were available free of charge at the university. Due to resources through the universitys
libraries, we also did not need to buy technical papers.
For future purposes, implementing liquid transfer pumps after each scrubber may
be a critical addition to the proposed VRU system to account for surging and the presence
of excess liquids in the gas when restarting the VRU. This will help prevent damage to
the compressors and decrease downtime when gravity is not sufficient to drain all the
liquids to the sump tank. If there is access to a high pressure gas source on the platform,
an alternative for vapor recovery could be to use venturi jet ejector technology, which
takes a high pressure gas flow and combines it with the low pressure vapors to create an
intermediate pressure flow which can then enter the sales compressor or other processing
equipment. Currently, venturi jet ejectors have only been implemented onshore, but may
49
be used offshore in the future. In addition, venturi jet ejectors have no mechanical
moving parts resulting in significantly lower maintenance costs [23].
10
CONCLUSION
In conclusion, our team has developed overall VRU and detailed individual
component designs through research and utilization of applicable design tools, along with
supporting feasibility calculations and justifications for our selections. A critical
component of our engineering analysis included creating a MATLAB computer model to
simulate and verify our VRU design, applying principles of thermodynamics, heat
transfer, fluid mechanics, and gas separation. A three-dimensional solid model was also
created to provide detailed visualization of our VRU design components and overall
layout. This VRU system will recover hydrocarbon vapors and re-route the gas to sales
on one of Chevrons offshore production platform in the Gulf of Mexico, minimizing gas
losses and increasing profits while complying with environmental regulations.
Considering the short payback period, high return on investment, and annual revenue of
about $4 million associated with the proposed VRU design, our analysis shows this final
design solution is financially sound and would be a favorable investment for
implementing in the project. We have also provided Chevron with recommendations for
future work in terms of further improvement of the final solution and potential
investments in new and existing technologies.
50
REFERENCES
1.
2.
Chevron. (2009). Gulf of Mexico Business Unit Fact Sheet. Houston: Chevron
North American Exploration and Production.
3.
4.
5.
6.
Goodyear, M. A. (2002). U.S. Patent No. 6,418,957. Washington, DC: U.S. Patent
and Trademark Office.
7.
Mokhatab, S., Poe, W., & Speight, J. (2006). Handbook of Natural Gas
Transmission and Processing. Burlington: Gulf Publishing
8.
Gas Processors Suppliers Association. (1994). Engineering Data Bok. Tulsa: Gas
Processors Association.
9.
Mohitpour, M., Golshan, H., & Murray, A. (2003). Pipeline Design &
Construction: A Practical Approach. New York: American Society of Mechanical
Engineers.
10.
Hewitt, G. (1998). Heat Exchanger Design Handbook. New York: Begell House
Inc.
11.
12.
13.
Svrcek, W., & Monnery, W. (1993). Design Two-Phase Separators Within the
Right Limits. Chemical Engineering Progress , 53-60.
14.
Ariel Corporation. (n.d.). Ariel JGM, JGP, JGN, JCQ Compressors [Brochure].
Retrieved from http://www.arielcorp.com/uploadedFiles/Products/JGMPNQ.pdf
51
15.
16.
17.
Oilnergy. (n.d.). NYMEX Henry Hub Natural Gas Price. Retrieved November 19,
2009, from http://www.oilnergy.com/1gnymex.htm
18.
19.
CME Group. (2009, November 19). Natural Gas Henry Hub Futures. Retrieved
November 19, 2009, from http://www.cmegroup.com/trading/energy/naturalgas/natural-gas.html
20.
EPA's Natural Gas STAR Program, Shell, GCEAG, API, & Rice University.
(2004, June 8). Installing Vapor Recovery Units to Reduce Methane Losses
[PowerPoint slides].
21.
22.
23.
Goodyear, M. A., Graham, A. L., Stoner, J. B., Boyer, B. B., Zeringue, L. P., &
Society of Petroleum Engineers International. (2003, March). Vapor Recovery of
Natural Gas Using Non-Mechanical Technology (SPE No. 80599). Society of
Petroleum Engineers Inc.
24.
Schmidt, P., Baker, D., Ezekoye, O., & Howell, J. (2006). Thermodynamics: An
Integrated Learning System. Hoboken: Wiley.
25.
Kline, P. E., Fahlgren, C. E., & Kitchen, M. R. (1971). U.S. Patent No. 3,565,164.
Washington, DC: U.S. Patent and Trademark Office.
26.
27.
28.
Raseley, L. J., Collier, S. J., & McCarty, H. G. (1980). U.S. Patent No. 4,214,883.
Washington, DC: U.S. Patent and Trademark Office.
52
29.
Hewitt, P. J. (1991). U.S. Patent No. 5,006,138. Washington, DC: U.S. Patent and
Trademark Office.
30.
31.
53
3 = 1
3
1
1 + 1 = 849.40 = 390
3 1
+ 1 = 908.68 = 448.68
A-1
compression load
o Assumptions:
Steady State Steady Flow
No change in KE, PE
Adiabatic
Isentropic Compression
Constant K=1.27, evaluated at T1 using specific heat calculator
MATLAB function
Compressors are reciprocating with adiabatic efficiencies of
= .83
Pressure change across cooler is negligible
Tambient=80oF
3 = 1
3 =
3
1
1 + 1 = 707.33 = 247.33
3 1
+ 1 = 737.51 = 277.51
5 = 1
5 =
5
4
1 + 4 = 713.65 = 253.65
5 4
+ 4 = 744.10 = 284.10
o Since both T3 and T5 are safely below 300oF, 2 stage compression with
intercooling will boost the gas pressure without damaging the equipment
o Now we will check the feasibility of single stage compression for the
combined 45 psig gas flow stream
4590 psig: combined Gas flow Stream
8 = 7
8 =
8
7
1 + 7 = 648.91 = 188.91
8 7
+ 7 = 667.12 = 207.12
A-3
B-1
Calculate T3-T9
Calculate COM
BHPs
Calculate SCR
Dimensions
Outputs: T1-9,
BHPs: COM & CLR,
Dimensions: CLR
and SCR
C-1
Function
Inputs: P, T,
Qgas
Calculate SCR
inner vessel
diameter (Dvd)
Calculate SCR
Lss
Calculate SCR
Nozzle
Diameter (Dn)
Output array
with Dvd, Dn,
Lss
Figure C-2. Vertical Separator MATLAB Function Flowchart.
C-2
Calculate Total
Extended Surface
Area
Calculate Tube
Bundle Face Area
Outputs: Extended
Surface & Bundle
Face A's, Fan D, Fan
Driver BHP
Calculate Fan
Diameter
Send Outputs to
Main VRU Function
C-3
Inputs:
Temperature, Gas
Properties &
Composition
Calculate Overall
Gas Cp
Convert Molar
Fractions to Mass
Fractions
Send Cp to Main
VRU & Cooler
Functions
Figure C-4. Specific Heat Capacity Calculator MATLAB Function Flowchart.
C-4
T3R=((T3SR-T1R)/EffComp1)+T1R;
T3F=T3R-460;
%3-4: Cooler 1: Rule of thumb- discharge pressure @ cooler exit is ~25Deg F
%above ambient temp
T4F=25+Tinf;
T4R=T4F+460
%4-5: Compressor 2
T5SR=T4R*(((P5/P4)^((K-1)/K))-1)+T4R;
T5R=((T5SR-T4R)/EffComp2)+T4R;
T5F=T5R-460; %[Deg F]
%5-6: Cooler 2
T6F=25+Tinf;
T6R=T6F+460;
%6-7: Combine Gas Streams
cp6=CPcalc(T6F); %[Btu/lbm-degR]
cp2=CPcalc(T2F);
cp7=CPcalc((T6F+T2F)/2); %Evaluated at average of inlet temperatures
mdot6=(Q6*10^6*MW)/(379*24*3600);%Mass flowrate from stock tank 1 [lbm/sec]
mdot2=(Q2*10^6*MW)/(379*24*3600);%Mass flowrate from stock tank 2 [lbm/sec]
mdot7=(Q7*10^6*MW)/(379*24*3600);%Mass flowrate of combined gas streams
[lbm/sec]
T7R=((mdot6*cp6*T6R)+(mdot2*cp2*T2R))/(mdot7*cp7);
T7F=T7R-460; %[Deg F]
%7-8: Compressor 3
T8SR=T7R*(((P8/P7)^((K-1)/K))-1)+T7R;
T8R=((T8SR-T7R)/EffComp3)+T7R;
T8F=T8R-460; %[Deg F]
%8-9: Cooler 3
T9F=25+Tinf;
T9R=T9F+460;
%Outputs
T1F
T2F
T3F
T4F
T5F
T6F
T7F
D-2
T8F
T9F
% BHP for Compressors
KRatio=(K/(K-1));
BhpComp1=0.0854*((Q1*T1R)/(E*CompEff))*KRatio*(((P3/P1)^(1/KRatio))-1)
%[hp]
BhpComp2=0.0854*((Q4*T4R)/(E*CompEff))*KRatio*(((P5/P4)^(1/KRatio))-1)
%[hp]
BhpComp3=0.0854*((Q7*T7R)/(E*CompEff))*KRatio*(((P8/P7)^(1/KRatio))-1)
%[hp]
%Scrubber Designs
%Scrubber 1 Design
A1=VertSepFunction(T4F,P4,Q4)
%Scrubber 2 Design
A2=VertSepFunction(T6F,P6,Q6)
%Scrubber 3 Design
A3=VertSepFunction(T9F,P9,Q9)
%Cooler Designs
%Cooler 1 Design
B1=CoolerFunction(T3F,Tinf,P3,Q3)
%Cooler 2 Design
B2=CoolerFunction(T5F,Tinf,P5,Q5)
%Cooler 3 Design
B3=CoolerFunction(T8F,Tinf,P8,Q8)
D-3
D-5
D-6
D-7
D-8
Cpix=CPi.*xi;
SumCpix=sum(Cpix);
B=SumCpix;
D-10
P=15 psig
T1=280.33oF (Compressor 1 outlet temperature)
T2= T + 25 oF = 105oF (Rule of thumb for cooler outlet temperature)
T=80 oF
MWNatural Gas= 18.064
Cpair=0.24
Cpgas=0.5534
Qsc=2MMSCFD
F=LMTD Correction Factor=1
FCmin=Minimum Fan Coverage=0.40
1 +2
2
= 192.67
= 80.4
= 0.92
Assumptions
Procedure
E-1
50 15
100 50
=
1.6
1.9 1.6
= 1.39
+ 1
10
= 29.93 = ,
, = 106.93
1 , (2 )
ln 1 ,
2
= = 76.62
106
= 1.103
379 24 3600
= , 1 2
=
=
= 3627.57 2
= 45.12 2
E-2
Step 6: Calculate air mass flow rate & air face mass velocity
= ,
, =
=
= 1192.03 2
= 53784.21
2 = 18.05 2
4
= 4.79 5 ( )
= 0.094 2
,1
,
1
3
= 12212.25
( ) (,2 ) 60
E-3
=
2
4
2
2
=
,2
2
40052
4
,2
= 0.0236 2
40052
( 40052 = @ 70)
E-4
= 0.371
Givens
Rbar=10.73
L= water=62.4 3
Qsc=2MMSCFD
F-1
1
2
= 7.105
From GPSA:
100
= 0.342
100
= 0 .075 = 0.256
=
= 0.088 3
= .35 0.01
106
= 1.103
379 24 3600
3
=
= 12.534
3
=
= 0.018
4
= 1.731
For a mist eliminator add 3-6 to DVD to accommodate support ring and round
up to the next 6:
= + 6" = 2.23 ~ 2.5
3 60
3
= 0.018
= 1.08
F-2
=
= 1.383
2
Step 9: Calculate HS
=
= 0.830
2
= + = 12.552
=
= 0.001434
+
= + 1 = 0.177
= 9.55 "
60
F-3
Step 12: Allow 6in for mist eliminator and 1 ft between mist eliminator and top
seam
= 0.5 + 1 = 1.5
F-4
G-1