Beruflich Dokumente
Kultur Dokumente
Stephen R. Lambert, F
Power Technologies, Inc.
Abstract
Optimum reactor compensation configurations for
implementing single pole reclosing on EHV, double circuit lines
have been previously investigated'.
However, for some
applications, optimum schemes may not be practical due to
constraints such as reactor physical sue, operating constraints and
existing equipment.
The performance of non-optimum schemes is considered.
using an EGAT (Electricity Generating Authority of Thailand) 328
km. 500 kV. double circuit line as an example. Several
compensation schemes were considered, and their performance
examined with both circuits in service and with one circuit out for
maintenance. The analysis indicated that some schemes with
reactor values considerably off optimum still provided reasonable
performance.
Somkiet Phaloprakarn
Electricity Generating
Authority of Thailand
INTRODUCTION
Single pole reclosing is employed so that following the
occurrence of a phase to ground fault (the majority of faults on
most transmission l i e s ) only the faulted phase is cleared and then
reclosed. W i n g the dead time, the energized phases capacitively
and inductively couple energy into the faulted phase resulting in a
continuation of the arc current (called 4 here). If the phase is reenergized before the secondary arc current extinguishes, the full
phase to ground fault will redevelop. With relatively short
transmission lines, the secondary arc current may be so low that it
extinguishes quickly, and reclosing can be accomplishedafter only
a slight delay. With longer lines, some type of mitigating action
is usually needed to reduce the secondaxy arc current.
'
SECONDARYARCCURRENTREDUCTION
Secondary arc current is composed of a capacitive
component due to the intra- and intercircuit capacitances and an
inductive component driven by the voltage induced from the
currents in the other phases. Various methcds have been suggested
for reducing the secondary current - momentarily bypassing the
fault by mechanicallyconnecting the faulted phase to ground at one
or more points2,or connecting the faulted phase back to the source
voltage through a ~apacitor.~The method considered in this
analysis cancels the inter-phase capacitances with reactive
compensation.'^"
92 WM 261-8 PWRD A paper recommended and approved by
the IEEE Transmission and Distribution Committee of
the IEEE Power Engineering Society for presentation
at the IEEE/PES 1992 Winter Meeting, New York, New
York, January 26
30, 1992. ManUscriDt submitted
August 30, 1991; made available for printing
December 31, 1991.
652
Figure 2.
(1)
"
9
,
Experimental Data on Secondary Current Arc Extinction
xn =
-- 3 w , +BC,)
--3(BC, -BC,)
(3)
653
USSR. Reactive compensation with the usual neutral reactor was
used on both lines. although various reactor values were used
during the tests. Sh~erling'~
reported on tests on the same 765
kV line considered by Scherer and noted that the arc resistance has
a significant effect on the secondary arc current, with the secondary
current having a third harmonic component of about 40%.
700 R
Middle
14.5
3.1
Sag = 18.5
Volues in meters
-M-
Figure 4.
654
1.
2.
3.
Both Circuits
in Service
One Circuit with
other Grounded
Table 3.
Power
7.92.27
Values
Sag = in
14meters
5.39
1.76
1.05
.74
1.21
8.55
1.76
---
_--
---
MVA position
I 1 I I I I
Fault
PhaseFaulted
Location Cir 1
Cir2
4, A
kVhs
650
None
31.3
6.8
650
Existing
Middle
None
31.6
7.0
Existing
Middle
None
32.4
7.1
I Existing IMaeMohI
Complete Middle
I None I 31.1 I
None
16.0
6.8
3.4
655
10
z5
0
e
U
?i
-5
40'
' '
'
'
ldoo'
'
'
' l&"
' '
'
Xm, Ohms
-u- ExistingTrans. --e-- PerfectTrans.
4 and R
U-
I 4,
Figure 6.
Figure 8.
'
+- ExistingTrans.
Figure7.
PerfectTrans.
-8-
circuit. In this case the second circuit is out of service, but not
grounded, so the. first circuit C, and C, values would not change
significantly from those shown in the first row of Table 2. The
perfurmance with these values is shown in Figure 8. For any
reasonable X, value, this operation procedure should work and
keep one line in service.
-I/
,;*-;.\:,
-1500
0.40
0.60
0.80
1
1.
h, COMPENSATIONFRACTION
Xp --e- Xm -*-Xn
Figure 9.
X, is indicated,
656
0.
13
8 0
0.
Y
z
s?
8 0
c
Y
O.%.
- .
. . ..&....&.
- I
* Xn=600
Figure 10.
Xm, Ohms
Xn400
750
. . .Id00
Figure 12.
Xn=lOOO
. . .1
- -
.&
+- Xn=l000
.1 5 0 0
Xm, Ohms
Xn-1500
do0
Xn=2000
10
needed.
a
-10
s b o *
-m-
Figure 13.
I
ldoo
I
l&O
Xm, Ohm
Existing Trans.
Perfect Trans.
---
657
U
li
zf7
FH
I
sbo'
Id00
lh
'
'
Xm, Ohm
* ExistingTrans.
Perfect Trans.
---
* lf,A
Figure 14.
If and R
Figure 15.
Table 4.
(Power1 Trans-
Fault
I PhaseFaulted I
1-1
Location
1MV.1
position
650
Existing
ThaTako
b A (kV/rns
31.0
6.7
650
Existing
ThaTako
18.4
4.0
CONCLUSIONS
I Complete I ThaTako I
27.5
5.6
658
The few EMTP simulations that were presented indicated
that the dependence of 4 on the cment in other phases is not
easily predictable, probably because even a line that is completely
transposed will have unbalances near a fault.
7.
8.
9.
10.
11.
12.
13.
14.
APPENDIX
The existing EGAT double circuit is not perfectly
transposed between the circuits; there are 12 line transpositions of
the line at intervals of about 27 Inn. At each transposition point
the top two conductors of one circuit are exchanged, and the
bottom two phases are switched on the other circuit. At the next
transpositionpoint the bottom two phases of circuit 1 are switched,
etc. and this results in complete transposition within each circuit,
but not complete transposition between the circuits. The complete
transposition cases for the E M " simulations were done using a
line model with 9 sections.
Expressions for xh,
ch.
x,
Xp(Xp+3X, + 6X,)
X,
xi =
+uu,-xp+3x,
(xp+3X,
x#fl
+ 6X,)
(Xp +3X,)
X,
X, = Xp +3X, +6X,
(4)
(5)
(6)
REFERENCES
1.
Kimbark, W.E.. "Selective-PoleSwitchingof Long DoubleCircuit EHV Line," Paper F 75 511-6, IEEE PES Summer
Meeting, San Francisco, CA, July 20-25, 1975.
2.
3.
4.
5.
6.
659
Stephen R . Lambert
(M69,SM78,F91) received both a
BSEE and MS from the Universityof
Illinois (U)
in 1969. Afier teaching
at UI he joined Commonwealth
Associates, Inc. in 1970. He joined
Power Technologies, Inc. (FE)in
1973 and is presently a Senior
Consultant with I. Mr.Lambert is
a Registered Professional Engine-er
and a Senior Member of IEEE. He
is a past chairman of the IEEE
Switchgear Committee, the TRV
Working Group and High Voltage
Circuit Breaker Sub-Committee,and is presently Secretary of the
IEEE PES Technical Council. He is a member of IEC WG 28.1.