Sie sind auf Seite 1von 28

Bulk Separation The first stage of produced

water treatment
Produced Water Best Management Practices
Conference, Kuala Lumpur
20-21 November 2013

OPUS Maxim Limited 2013

Objectives of this Presentation

The Traditional Approach:


Our industry divides Bulk Separation and Produced Water
Treatment as two separate processes dealt with by different
departments and vendors

> Bulk Separation


The objective is to remove as much water and gas from
the oil for product quality
> Produced Water Treatment
The objective is to remove as much oil and solids as
possible to meet discharge consents and remove any
residual gas
The objective of this presentation is to demonstrate why we do
not segregate the two processes and consider the bulk separation
stage as the first stage of produced water treatment.

OPUS Maxim Limited 2013

About Opus

T EC H N O LO G Y

E N V I R O N M E N TA L

A UNIQUE BLEND OF

TECHNOLOGIES

MARINE & FRESH WATER

EXPERTISE & RESOURCES

DEVELOPED TO MEET THE

TOXICITY TESTING,

GROWING LEGISLATIVE

BIOACCUMULATION &

REQUIREMENTS OF THE

BIODEGRADATION

ENERGY SECTOR

ANALYSES

C O N S U LTA N C Y

OPUS Maxim Limited 2013

C O N S U LTANC Y

The challenges

Some common factors that contribute to PW quality challenges:


>

>

>

>

Increasing water rates


>

Aging wells

>

New tie-backs

>

EOR

Ageing process equipment


>

Hydrocyclones

>

IGF

>

Erosion of internals, control valves etc

Operational methods / changes


>

Recycles,

>

Fluids incompatibilities (inc EOR)

>

Chemical treatment e.g. corrosion inhibitor

Tightening regulations/targets

OPUS Maxim Limited 2013

C O N S U LTANC Y

Overview of the Separation Process

Oil Removed

Majority Free Oil

Some Dispersed
Oil

Majority Dispersed Oil

Some Dissolved Oil

Incoming Fluids
(Oil Content)

>10%

1,000 - 10,000ppm

100 - 500ppm

10 - 50ppm

Treated Fluids
(Oil Content)

1,000 - 10,000ppm

100 - 500ppm

10 - 50ppm

< 5ppm

Natural Mean Oil Droplet


Size (exit)

100 - 500 Microns

20 - 100 Microns

5 - 20 Microns

<5 Microns

Relative Separation
Difficulty

Easy

Medium

Difficult

Very Difficult
OPUS Maxim Limited 2013

C O N S U LTANC Y

Process Modelling

>

The objective is to identify non ideal


fluids behaviour and adapt a theoretical
design to achieve optimal hydraulic
efficiency

>

Physical Modelling and Computational


Fluid Dynamics (CFD) are
complementary tools

>

Results of modelling validate upgrade


design and support for investment
decisions

>

Apply the strengths of both techniques


to develop optimal solutions

OPUS Maxim Limited 2013

C O N S U LTANC Y

Physical Modelling of Separators

>

Physical modelling is a scaled modelling


technique that successfully illustrates the
fluids behaviour

>

Identifies excessive turbulence, gas carry


under and recirculation

>

Can replicate conditions such as slugging,


surging and sloshing

>

Provides a realistic, visual and dynamic


means of assessing fluids behaviour
within the vessel

OPUS Maxim Limited 2013

C O N S U LTANC Y

Computational Fluid Dynamics (CFD)

>

Mathematically simulates multiphase


flows in a process vessel of system at
full scale

>

Simulates actual process conditions e.g.


mass flow rate, temperature, pressure,
and other physical properties

>

Helps to verify results from process


evaluation and feed directly into detail
design, reducing time and costs

>

Used to verify and fine tune a design


alongside the results from physical
modelling, on a scale up basis

OPUS Maxim Limited 2013

C O N S U LTANC Y

Sloshing Analysis and Design


CFD and Physical Modelling
>

Physical modelling and CFD can be applied


independently, but the strength lies in
applying both simultaneously to verify results
from process evaluation

>

Results fed into detailed design - reducing


time, costs and improving process and
mechanical robustness of hardware

>

Correct interpretation of the results from


either technique is key to their success

>

Understanding the effects of geometry and


flow scaling on results obtained from physical
modelling is also important

>

Quality of CFD results are dependant on the


process understanding of the CFD Engineer

Correlation of Physical and Computational


modelling of sloshing

OPUS Maxim Limited 2013

T EC H N O LO GY

Good Practice for Separator Design

Objectives of Multi-phase Separator Optimisation:


>

>

>

Inlet/Transition Zones:
>

Preserve stratified fluids

>

Achieve early gas release

>

Achieve effective dissipation of energy

>

Minimise droplet shear

Liquid/Gas Interface and Liquid Level:


>

Optimise the fluid residence times

>

Identify and correct any undesirable fluid


behaviour

>

Channelling & Recirculation

>

Gas carry-under

Gas Outlet:
>

Remove Liquid Droplets


OPUS Maxim Limited 2013

T EC H N O LO GY

Good Practice for Separator Design

Inlet Zone
Challenges:
>
Flow bias due to upstream pipework leads
>

Leads to shortcutting and reduced residence


time

Solutions:
>
Pipe diameter changed to achieve plug flow
>

CFD Image of a Biased Inlet Pipe


Flow

Offset inlet vanes

OPUS Maxim Limited 2013

T EC H N O LO GY

Good Practice for Separator Design

Inlet Zone
Challenges:
>
Poor inlet device design leading to:
>
>
>
>
>
>
>

Droplet shear/shatter
Emulsion & Foam creation
Gas entrainment
Poor distribution
Clogging
Mechanical failure
Unsuitable for slugging

Physical modelling of
a bare vane inlet

Physical modelling of
an optimised vane inlet

Solutions:
>

Bespoke inlet device design

>

One size does not fit all


Physical modelling example of poor inlet zone leading to
shortcutting and reduced RT

OPUS Maxim Limited 2013

T EC H N O LO GY

Good Practice for Separator Design

Transitional & Quiescent Zone


Challenges:
>
Poor baffle design, leading to:
>

Poor distribution of fluids

>

Can lead to shortcutting and reduced RT

>

Increased velocity due to higher water rates

>

Droplet shear

>

Clogging/Scaling

Examples of blocked Perforated Plates

Fluid flow jets through small


orifices and penetrates further
downstream than is necessary

Solutions:
>
Bespoke baffle design considering:
>

Fluids chemistry

>

Solids/scale

>

Future rates

Recirculation behind
solid sections of plate
Shear layer between jetting
fluids increasing droplet shear
Pathlines coloured by velocity (m/s-1)
OPUS Maxim Limited 2013

T EC H N O LO GY

Good Practice for Separator Design

Outlet Zone
Challenges:
>
Poor water outlet design including:

>

>

Poorly positioned leading to reduced RT

>

Formation of vortices leading to oil pad


drawdown

>

High velocities due to undersized nozzles

Weir design
>

Poorly placed leading to reduced RT

>

Inappropriate bucket or V-notch designs


leading to poor skimming efficiency

Solutions:
>
Bespoke designs for individual applications
>

Optimised skimming

>

Future rates considered

Example of a Correctly
Designed Vortex Breaker

Example of a through-weir
nozzle cross-over

Original outlet location

Optimised outlet location


OPUS Maxim Limited 2013

RESOURCES

TECHNOLOGY CASE STUDIES

Case Study 1:

Mrsk Olie Og Gas A/S HP Separator on Gorm Platform

Case Study 2:

Talisman Malaysia Ltd Separator, Hydrocyclone and Degasser Debottlenecking

Case Study 3:

Hess Ltd HP Separator on Triton FPSO

Opus Maxim Limited 2013

RESOURCES

TECHNOLOGY CASE STUDIES


Mrsk Gorm HP Separator
Driver for the upgrade
>
>

Fluids study for end of pipe package


design information
High oil in water concentration, small
droplet emulsion

Original Design & Performance


>

>
>
Original internals arrangement
Opus Maxim Limited 2013

Vessel Internals Comprised of:> Basic deflector plates Inlet


> Perforated Plate Distribution Baffles
> Two Vane Packs
> Gas Outlet Droplet Separator
> Adjustable Weir
> Sand Jetting System
Oil in Water Performance ~1000 mg/l for
an inlet flowrate of 600 700 m3/hr
Small oil droplet emulsion

RESOURCES

TECHNOLOGY CASE STUDIES


Mrsk Gorm HP Separator
Review Phase
The requirement was to identify the operational
limitations of throughput through the HP Separator.

Physical modelling of Gorm Separator

Opus Maxim Limited 2013

Methods Adopted:> Theoretical Process Review


> Physical Modelling
> Finite Element Analysis of Existing Supports
Findings:> The inlet device created significant turbulence
> Flow is seen to exit the inlet zone over the first
distribution baffle
> Low open area baffle design is very restrictive
> The water outlet nozzle was found to be
undersized
> Sand system, Droplet Separator & Weir height
acceptable

RESOURCES

TECHNOLOGY CASE STUDIES


Mrsk Gorm HP Separator
Upgrade Modifications

Original internals arrangement

>

Removal of Existing Inlet, Perforated Baffles


and Vane Packs

>

Internals Supplied for Upgrade:-

Upgraded internals arrangement

Client confirmed results

Outlet
Pre-upgrade

Outlet Post
Upgrade

~1000ppm

<100ppm

Opus Maxim Limited 2013

>

>

Inlet Vane Device with Diffuser Baffle

>

Horizontal Gate Baffle with Top Gas


Baffle (Inlet Zone)

>

Horizontal Gate Baffle (Distribution


Baffle)

>

Vertical Gate Baffle (Calming Baffle)

>

Vortex Breaker (New Water Outlet)

The water outlet nozzle was replaced for a


larger nozzle

RESOURCES

TECHNOLOGY CASE STUDIES


Talisman Malaysia Ltd Bunga Raya
Debottlenecking
Driver for the upgrade
>

>

New wells require water handling increase


from 35MBD to 70, then 100MBD
Overboard discharge target <25ppm

Original Design & Performance


>
>
>

Opus Maxim Limited 2013

Process designed for 35 MBD


Consists of 2 stages of Bulk Separation,
Hydrocyclones and a Degasser
Overboard discharge: 40 80ppm

RESOURCES

TECHNOLOGY CASE STUDIES


Talisman Malaysia Ltd Bunga Raya
Debottlenecking
Review Phase
>
>
>
>

>

>
>

>

Opus Maxim Limited 2013

Full fluids characterisation and detailed process


review
Multi vendor Hydrocyclone trial
Small vessels
Separator internals consisted of:
> Rear Facing Vane Type Inlet Device
> 2 x Perforated Plate Baffles
> Weir & water outlet ~4m from Tan
Separator performing reasonably well at current
flows but small droplet size exiting vessel
Large diameter hydrocyclone liners giving ~15
40% oil removal
Degasser internals consisted of:
> Deflector inlet device
> Non-porous baffles
> Flow under weir bucket
> Spill over water weir
No oil removal from Degasser

RESOURCES

TECHNOLOGY CASE STUDIES


Talisman Malaysia Ltd Bunga Raya
Debottlenecking
Blowby CFD
>
>
>

>
>
>
>

Opus Maxim Limited 2013

Initially proposed internals


Liquid pool is pushed straight up into the gas
outlet
Substantial back pressure exceeding MAWP

Final proposed internals (as built)


Existing box is sealed and a new pipe
manifold fitted, which extends the gas outlet
A shroud is attached to the manifold nozzle
to deflect liquid away from the gas outlet
Dissipation baffle installed above the inlet
device to dissipate the momentum of the
blowby gas downstream

RESOURCES

TECHNOLOGY CASE STUDIES


Talisman Malaysia Ltd Bunga Raya
Debottlenecking
Upgrade Modifications
>
>
>
>
>

Opus Maxim Limited 2013

Install Opus peripheral Diffuser Baffle around


the existing Vane type inlet
Replace perforated plate baffles plate/slotted
distribution baffles
New vortex breakers
Replace weir and relocate further downstream
Install internal piping to extend water outlet

>

Upgrade Hydrocyclones with high capacity high


efficiency liners

>
>

Remove all existing internals


Internals supplied for upgrade:> Opus inlet device
> Slotted baffles
> Notched spillover weir
> Crossover pipework for Oil & Water
outlets

RESOURCES

TECHNOLOGY CASE STUDIES


Talisman Malaysia Ltd Bunga Raya Debottlenecking
The Achievements

>
>
>
>
>

Offshore fluids characterisation and process optimisation identified specific areas for improvement
Detailed process review of the vessels identified where the best gains could be had
Opus supplied all vessel internals including 3rd party Hydrocyclones (single process guarantee)
Supervised installation with local contractors
Currently operating within discharge specification at design flow, with study underway to push
that to 100,000 BPD

>

Client confirmed performance:-

Opus Maxim Limited 2013

Original discharge
(35,000 BPD)

Current discharge
(70,000 BPD)

40-50ppm

<25ppm

RESOURCES

TECHNOLOGY CASE STUDIES


Hess Triton HP Separator
Original Design & Performance
>
>

>
>

Original internals arrangement

Opus Maxim Limited 2013

Split Flow Vessel Situated on FPSO


Vessel Internals Comprised of:> Inlet Diverter Assembly
> Perforated Plate Baffles
> Perforated Plate Over Weirs
Oil in Water Performance 300-1500ppm
Objective was to increase throughput by
~70% whilst maintaining performance

RESOURCES

TECHNOLOGY CASE STUDIES


Hess Triton HP Separator
Review Phase
>
>
>
>

Process review carried out


Physical Modelling undertaken with some CFD
Comparative analysis performed
Improved internals arrangement determined

Physical modelling of Triton Separator

Upgrade Modifications
>
>

CFD modelling of Triton Separator


Opus Maxim Limited 2013

Remove all existing internals


Internals supplied for upgrade:> Vane type inlet device with distribution baffle
> Slotted baffles
> Plate pack coalescer

RESOURCES

TECHNOLOGY CASE STUDIES


Hess Triton HP Separator
The Achievements

>
>
>

New internals fabricated and supplied on schedule


Opus supervised installation
Tie-in fluids added shortly after start-up

>

Client confirmed performance:-

Original Internals

Upgraded Internals
(with 70% additional flowrate)

300 - 1,500ppm

Opus Maxim Limited 2013

100 - 600ppm

Conclusions

>

Bulk separation and Produced Water Treatment processes are inextricably linked and
should be considered as a single process during design and optimisation projects

>

The quality of separation obtained in the first stage of bulk separation has a direct
impact on the performance of the downstream produced water treatment process

>

The root cause of a lot of Produced Water Treatment challenges is often the result of
poor 1st stage separator design

>

Oil in water levels entering the produced water treatment process can be improved
by orders of magnitude, leading to much less pressure on the rest of the process to
perform, leading to the following key benefits:
> Increased production through existing process vessels
> Optimised/Focussed CAPEX and OPEX

> More flexibility in the process with reduced impact from transient flows and
process upsets
> Better environmental performance

Opus Maxim Limited - 2013

Thank You

Opus
Flotta
Stromness

Brooklea
Compton

Orkney
United Kingdom
KW16 3NP

Guildford
United Kingdom
GU3 1HU

Glen McLellan
E-mail: glen.mclellan@opus-results.com
Web: www.opus-results.com
Telephone: +44 (0)1856 702000

Opus are a part of Aker Solutions


Opus Maxim Limited - 2013

Das könnte Ihnen auch gefallen