I have messed around with an evaluation version of Microstrategy software (9.2.1m). After some time
I have what I want, a nice project connected to a mysql database which shows reports on a mobile
device... I would now like to clean up and perform a clean install.
I have install the free Microstrategy mobile suite 9.2.1m on a brand new machine... how can I safely
transfer the entire project from the old machine to the new one? I have looked on the forum and
knowledge base, but could not find a low-level step-by-step guide.
Any help is welcome.
Stijn

Solved! Go to Solution.
Report Content
Message 1 of 3 (57 Views)
Everyone's Tags:
o

copy project

move project

transfer project
View All (3)
Reply
0 Likes
board-id/351/mes

forums/v2/forumm ForumTopicPage:

ggw pBP4agHi5sr

form_0

NEaFJNhcUWmKV

90242

Submit

Post

Cancel

Cancel

CH
Trusted Guru

Posts: 1,669
Registered: 08-28-2011

Re: Copy entire project from 1


machine to another
Options

Mark as New

Bookmark

Subscribe

Subscribe to RSS Feed

Highlight

Print

Email to a Friend

Report Content
08-12-2012 12:34 PM
Please follow the below steps.
1.Take a backup of the metadata --if its a acces database just copy it to another location.
2.Uninstall the MicroStrategy 9.2.1.
3. Delete all files related to MSTR from C:/Program Files/Common Files and C:/Program
Files/MicroStrategy
4. Restart your machine.
5. Do a fresh install again
6. Now create a 2 tier connection for the old metadata.
7. Use the 3 tier of the new metadata.
8. Duplicate the project from 2 tier to 3 tier.
Please vote if helpful. Please mark as right answer if it was your solution.
Report Content
Message 2 of 3 (57 Views)
Reply
0 Likes
board-id/351/mes

forums/v2/forumm ForumTopicPage:

NEaFJNhcUWmKV

Gk_GhFGpXW2s

form_1

90247

Submit

Post

Cancel

Cancel

Lev Ajar
Trusted Guru
Expert (Environment: Installation, Configuration, and Upgrades)

Posts: 2,376
Topics: 41
Likes: 666
Blog Posts: 1
Ideas: 7
Solutions: 145
Registered: 08-07-2012

Re: Copy entire project from 1


machine to another
Options
o

Mark as New

Bookmark

Subscribe

Subscribe to RSS Feed

Highlight

Print

Email to a Friend

Report Content
08-12-2012 11:45 PM
if its a version upgrade from 9.2.1 to 9.2.1m , then follow the configuration wizard to upgrade the
Metadata as well...
Always take metadata backup for recovery,
Then as poornima said follow the process...
Perform the clean installation, once its done,
Point the Metadata to Intelligence Server and configure it....
Goto the configuration wizard and update the Intelligence Server Components,Stats, HList if any...
Regards,
Rajavel S