Beruflich Dokumente
Kultur Dokumente
House Project
Project Crashing
Crashing
This
Thismodel
modelillustrates
illustrateshow
howRISKOptimizer
RISKOptimizercan
canbe
beused
usedwith
with@RISK
@RISKProject.
Project.The
Theproject
projectconsists
consistsof
o
Tasks
sheet.
Resources
have
been
assigned
to
the
tasks
in
Project,
as
indicated
in
the
Resources
Tasks sheet. Resources have been assigned to the tasks in Project, as indicated in the Resources
modeled
modeledwith
withPert
Pertdistributions,
distributions,using
usingthe
theparameters
parametersin
inthe
theModel
Modelsheet.
sheet.IfIfthe
thedecreases
decreasesin
incolu
col
they
are
now,
the
project
is
completed
in
the
"normal"
way.
If
you
run
the
simulation
with
these
they are now, the project is completed in the "normal" way. If you run the simulation with thesev
project
projectduration
durationisisabout
about133
133days
daysand
andthe
themean
meancost
costisisabout
about$58,000.
$58,000.However,
However,the
theproject
projectdur
du
because
of
the
uncertainty.
For
example,
there
is
about
a
40%
that
the
duration
will
exceed
135
because of the uncertainty. For example, there is about a 40% that the duration will exceed 135
The
Thecontractor
contractorisisunder
underpressure
pressureto
tocomplete
completethe
thehouse
housequicker.
quicker.To
Todo
dothis,
this,he
hecan
can"crash"
"crash"any
anyof
o
column
F
of
the
Model
sheet,
up
to
the
maximum
in
column
H.
In
this
case,
each
of
the
Pert
column F of the Model sheet, up to the maximum in column H. In this case, each of the Pertpara
para
explained
explainedin
inthe
thecell
cellcomment
commentin
incell
cellJ3
J3of
ofthe
theModel
Modelsheet,
sheet,this
thisresults
resultsin
inaapenalty
penaltycost
costfor
forexpe
expe
costs,
there
are
bonuses
for
the
contractor
if
he
finishes
stage
1
of
the
project,
and
both
stages
costs, there are bonuses for the contractor if he finishes stage 1 of the project, and both stageso
rows
rows17
17and
and18
18of
ofthe
theModel
Modelsheet.
sheet.Finally,
Finally,the
thecontractor
contractorwants
wantsaa95%
95%chance
chanceof
ofcompleting
completingthe
th
RISKOptimizer
has
been
set
up
to
minimize
the
mean
net
extra
cost
to
the
contractor
RISKOptimizer has been set up to minimize the mean net extra cost to the contractor(penalty
(penaltyco
c
deadline
deadlineconstraint.
constraint.
Two
Twoassumptions
assumptionsof
ofthis
thismodel
modelare
arethat
that(1)
(1)the
theadjustable
adjustablecells,
cells,the
thedecreases,
decreases,are
areallowed
allowedto
tobe
be
penalty
costs
are
linear
functions
of
the
adjustable
cells.
Both
of
these
assumptions
could
be
penalty costs are linear functions of the adjustable cells. Both of these assumptions could berela
rel
of
ofthe
themodel.
model.
Note:
Note: The
TheIndustrial
Industrialedition
editionisisrequired
requiredto
touse
usethe
theRISKOptimizer
RISKOptimizerand
andProject
Projectfeatures
featuresof
of@RISK.
@RISK
t. The
ct.
Theproject
projectconsists
consistsof
ofbuilding
buildingaahouse,
house,as
asindicated
indicatedin
inthe
the
dicated
in
the
Resources
sheet.
The
task
durations
are
all
dicated in the Resources sheet. The task durations are all
t. IfIfthe
et.
thedecreases
decreasesin
incolumn
columnFFof
ofthe
theModel
Modelsheet
sheetare
are0,
0,as
as
e
simulation
with
these
values,
you
should
find
that
the
he simulation with these values, you should find that themean
mean
However,
However,the
theproject
projectduration
durationcan
canbe
besignificantly
significantlylonger
longer
duration
will
exceed
135
days.
duration will exceed 135 days.
is, he
his,
hecan
can"crash"
"crash"any
anyof
ofthe
thetasks
tasksby
bythe
thenumber
numberof
ofweeks
weeksin
in
se,
each
of
the
Pert
parameters
decreases
by
this
amount.
ase, each of the Pert parameters decreases by this amount.As
As
nnaapenalty
penaltycost
costfor
forexpediting.
expediting.In
Inaddition
additionto
tothese
thesepenalty
penalty
roject,
and
both
stages
of
the
project,
by
the
times
indicated
project, and both stages of the project, by the times indicatedin
in
chance
chanceof
ofcompleting
completingthe
theproject
projectwithin
within135
135working
workingdays.
days.
he
hecontractor
contractor(penalty
(penaltycosts
costsminus
minusbonuses),
bonuses),subject
subjectto
tothe
the
eases, are
reases,
areallowed
allowedto
tobe
be any
anydecimal
decimalvalues,
values,and
and(2)
(2)the
the
ssumptions
could
be
relaxed
with
straightforward
modifications
assumptions could be relaxed with straightforward modifications
oject features
roject
featuresof
of@RISK.
@RISK.
ID
Task Name
Duration
Start
1 Build house
121 days
3/4/2013
89.9 days
3/4/2013
Stage 1
Build foundation
5 wks
3/4/2013
8 wks
4/3/2013
Build roof
6 wks
5/23/2013
Do electrical wiring
5 wks
5/23/2013
Do plumbing
4 wks
5/23/2013
62.3 days
5/23/2013
Install windows
3 wks
5/23/2013
10
Install drywall
3 wks
6/12/2013
11
Put on siding
4 wks
6/12/2013
12
Paint house
5 wks
7/11/2013
8
9
Stage 2
Finish
Predecessors
Resource Names
Cost
8/19/2013
$53,949.25
7/5/2013
$35,777.50
4/3/2013
Excavators
$6,885.00
5/23/2013
Builders
$7,150.00
7/5/2013
Roofers
$7,800.00
6/26/2013
Electricians
$7,702.50
6/21/2013
Plumbers
$6,240.00
8/19/2013
$18,171.75
6/12/2013
Window installers
$2,493.00
7/4/2013
Drywallers
$2,730.00
7/11/2013
Siding installers
$4,758.75
8/19/2013
11
Painters
$8,190.00
3/3/13
3/10/13
3/17/13
3/24/13
3/31/13
4/7/13
4/14/13
4/21/13
4/28/13
5/5/13
5/12/13
5/19/13
5/26/13
6/2/13
6/9/13
6/16/13
6/23/13
6/30/13
7/7/13
7/14/13
7/21/13
7/28/13
8/4/13
8/11/13
8/18/13
8/25/13
9/1/13
9/8/13
9/15/13
9/22/13
9/29/13
10/6/13
ID
Indicators
Resource Name
Type
Excavators
Work
Builders
Work
Roofers
Work
Electricians
Work
Plumbers
Work
Window installers
Work
Siding installers
Work
Drywallers
Work
Painters
Work
Material Label
Initials
Group
Max. Units
Std. Rate
100%
$300.00 /day
100%
$200.00 /day
100%
$250.00 /day
100%
$325.00 /day
100%
$300.00 /day
100%
$180.00 /day
100%
$225.00 /day
100%
$175.00 /day
100%
$300.00 /day
Ovt. Rate
Cost/Use
Accrue At
Base Calendar
$0.00 /hr
$0.00
Prorated
Standard
$0.00 /hr
$0.00
Prorated
Standard
$0.00 /hr
$0.00
Prorated
Standard
$0.00 /hr
$0.00
Prorated
Standard
$0.00 /hr
$0.00
Prorated
Standard
$0.00 /hr
$0.00
Prorated
Standard
$0.00 /hr
$0.00
Prorated
Standard
$0.00 /hr
$0.00
Prorated
Standard
$0.00 /hr
$0.00
Prorated
Standard
Code
Stage 1
90
$2,000
$2,000
$2,500
$0
-$4,500
$53,949
likely
Maximum Decrease
5.00
8.00
6.00
5.00
4.00
8.00
12.00
9.00
8.00
6.00
0.00
0.00
0.00
0.00
0.00
3.00
3.00
4.00
5.00
5.00
5.00
7.00
9.00
0.00
0.00
0.00
0.00
Stages 1, 2
130
$2,500
Deadline constraint
Duration Deadline
121
135
Max decrease
Resource cost
Penalty cost
<=
<=
<=
<=
<=
2
3
2
2
1
$1,500
$1,000
$1,250
$1,625
$1,500
$2,000
$1,500
$1,750
$2,250
$2,000
<=
<=
<=
<=
1
1
2
2
$900
$1,125
$875
$1,500
$1,250
$1,500
$1,300
$2,000
Summary statistics
P(bonus 1)
P(bonus 2)
P(meet deadline)
1.000
1.000
1.000
Percentile
95%