Beruflich Dokumente
Kultur Dokumente
BOILER ERECTION/INSTALLATION
Address : Ruko Golden Madrid II Blok I No 25, Jln. Letnan Sutopo, BSD - Tangerang Selatan 15323
Phone : +62-21 53164920, Fax : +62-21 53164921, Email : project.admin@nusareka.com, Website :
www.nusareka.com
Address : Ruko Golden Madrid II Blok I No 25, Jln. Letnan Sutopo, BSD - Tangerang Selatan 15323
Phone : +62-21 53164920, Fax : +62-21 53164921, Email : project.admin@nusareka.com, Website :
www.nusareka.com
MAIN-GIRDER ERECTION
Main girder erection is one of many rigging problems of the structural steel erection process.
The most accepted method of lifting the heavier girders is as follows: Once the girder is raised
above the column tops, bring the girder parallel to the front of the boiler. The girder can then
be connected to the upper ends of the columns. Once the girder is in place, intermediate
steel can be installed to tie all of the upper steel together. Coordinated radio communication,
highly experienced operating engineers and rigging supervisors, and first-class equipment are
imperative for successful girder erection.
STEAM-DRUM INSTALLATION
The steam drum can be raised into position at the top of the boiler once the main girder steel, vertical and horizontal bracing, have been
erected and completely bolted. The drum is hung just below the main girder steel by means of huge U bolts that encircle the drum
Ensure the direction of steam drum is correct since loading on the port
Prepare all rigging tools to be used.
Ensure that ground condition stability is enough to support transporter to
transfer the steam drum to lifting area.
The drum is hung from the main structure by two U type strap hangers. To
easier lifting operation and facilities the erection of hangers, the U road
hangers shall be assembled at ground level or the drum in order to be lifted
simultaneously.
The hanger threads are clean, to check nuts onto rods and Joints of U
roads- attention of the threads
Before steam drum lifting, drum should be hanging 1 meter from ground
floor and check by measuring tools the position of drum, hold for one hour to
see there are decline or not of the stem drum, this is to ensure that the lifting
tools is good condition
Lift up the steam drum around three(3) meters height then and tie in with wire
sling.
Stop the crane no 2 and lift up the crane no 1 to decline steam drum position
until 30 degree, until steam drum free from any obstruction.
After steam drum lifted to the final elevation, lock jack 1 and lift up jack 2 to
straight steam drum in horizontal position
The drum lift and positioned at the elevation appropriate and the operations of
hydraulic jack shall be locked.
The drum are moved towards to front boiler direction by slide steam drum in
temporary rail until final position.
While the steam drum is being erected, the pressure parts support steel can be installed. This
steel, located at the top of the unit, supports the weight of the boiler. Unlike conventional
structures that are built from the ground up, most modern boilers are built from the top down,
with the furnace suspended by constant load springs (locked) and the backpass suspended by
rigid hanger rods all from the main girders. This permits the furnace to expand upward and the
backpass to expand downward during the start up of the plant. The correct setting of the
pressure parts support steel is very important because every part of the boiler is located with
respect to this steel. It controls all elevations and is continually used as a reference to align the
different components as they are erected.
HANGER RODS
HANGER RODS
INSTALLATION
The downcomers from the steam drum to the lower water wall and
FBHE evaporator inlet headers are raised into place after the
above-mentioned work is completed. Each downcomer requires about 3
sections. Rigging must be located underneath the steam drum itself,
because the downcomers are welded directly to the drum nozzles. Clips
are welded on the ends so that threaded rods can be inserted to raise or
lower the downcomer a few inches for proper positioning for welding.
As soon as the downcomers are in place, welders can begin the fit up
and welding procedures that will ultimately join the downcomers to the
drum. Large, welded joints must be ground smooth for stress relieving
and radiography.
DOWNCOMER PIPE
PREPARATION HEADERS
INSTALLATION
COMBUSTOR
COMBUSTOR
COMBUSTOR
COMBUSTOR
COMBUSTOR
COMBUSTOR
COMBUSTOR
COMBUSTOR
COMBUSTOR
COMBUSTOR
COILS ERECTION
FINISH SUPERHEATER INSTALLATION
COILS ERECTION
ECONOMIZER INSTALLATION
The economizer, located just above the air preheater, can be erected.
This is a heat recovery device designed to transfer heat from the exiting
flue gases to the incoming, boiler feedwater. The economizer consists
of an interconnected horizontal bare tube array. The upper ends of
each economizer assembly connect to the outlet header, which is
already in place above the roof tubes.
Economizer assemblies are raised into place from the around with a
tugger rigged in the area of the outlet headers. Banks of economizer
elements can be pre assembled in groups. Pins and rods usually
support the assemblies directly to lugs welded to the bottom of the
intermediate headers. Because the economizer tubes are often
fabricated in a staggered pitch to increase heat transfer and minimize
space requirements, fitting the last few elements sometimes presents a
rigging problem. It is difficult to pass hoisting falls through the
staggered tubes. This often means that the already installed elements
must be spread apart and the side walls must be moved out.
BOTTOM HEADERS
BUCKSTAY ERECTION
Backpass buckstays
Combustor buckstays
BUCKSTAY ERECTION
The buck stay which has storage on the boiler steel structure can be Fitted up start from bottom panels to
the top for the safety as well as accessibility. These are some more importants notes :
Setting work should be performed after aligning panels. Panels located in the place where buckstays are to be
installed should be seal welded.
Fix Buckstays by inserting the guide pins to tie bar lugs which are welded to the panels.
Erection sequence of buckstay installation :
1. Set the position of buckstays which tie bar assembled on the furnace / boiler wall then tie bar are
positioned between two raws of guide bar. Temporary insert undersized pins through the guide bars to hold
the bulk stay assembly in place. Then check the buck stay level based on
furnace wall to confirm .
After that install the guide pin supplied from the manufacture across the furnace wall and make sure not to
bend any of the supplied pin .
2. Weld tie bar at the corner of the buck stay assembly and check the furnace cavity for square and angle
3. Next fit up the corner connection plate and the tack weld them into
position . Clamp the stand off bar to the web of I Beam (buck stay
beam ) and verify the preset dimension to be accurate.
Then stand off bars can be welded to the web . Finish corner
connection plate welding above and below and then attach the
linkage bar with the pin provided (according to drawing ) . Inserting
pins shall not using hammer.
Support : Attach the clips to the lugs provided on the convention pass rear wall for this purpose with the
support rod attached to the angle on the back side of the economizer support bar with a lock washer and nuts
. Weld the angle to the economizer support bar and tack weld the nut to the support rod after nut tightened .
FUEL SILO
FUEL FEEDERS
DUCTWORK ERECTION
Ductwork erection can be completely integrated with boiler erection to avoid problems in fitting
ductwork sections into the structural steel framework.
The boiler ductwork consists of two main systems; the air supply system, which includes the primary
and secondary air and the flue gas system, which includes the backpass ash hopper and ductwork to
the air preheater, precipitators, induced draft fans, and stack.
The primary and secondary hot air ductwork from the airheaters to the furnace contains some of
the biggest pieces of equipment on the boiler. Because of the sizes involved, ductwork is generally
assembled on the ground with sections installed simultaneously with the structural steel. Hanger
rods and expansion joints in the ductwork allow for thermal expansion. Hangers and ductwork
supports should be installed prior to erecting ductwork.
DUCTWORK ERECTION
The gas system ductwork extends from the bottom of the economizer to the
exit side of the tubular airheaters. It also includes the ductwork from the
airheater to the precipitator, to the induced draft fans, and to the stack. Most
of this ductwork is installed after the airheater is in place.
Economizer outlet
Air Heater
To Baghouse
Address : Ruko Golden Madrid II Blok I No 25, Jln. Letnan Sutopo, BSD - Tangerang Selatan 15323
Phone : +62-21 53164920, Fax : +62-21 53164921, Email : project.admin@nusareka.com, Website :
www.nusareka.com