Beruflich Dokumente
Kultur Dokumente
Runoff problem encountered at the adjacent residential situated on lower ground is described
by the following photos.
Figure 1: Sediment laden runoff from a development site has caused inconvenience to
neighboring residents whenever rain falls
Instructions:
1.
2.
Project question:
A 37.07 acres of forested land is to be converted into commercial centre (Figure 1).
After land clearing (bare soil), rainfall events have caused sediment laden runoff to
intrude into lower ground, inundating depressions, and causing nuisance to neighboring
residents. Complaints by the residents have been filed at the local authority and
forwarded to the developer and contractor in-charge. Figure 1 shows the relationship of
rainfall intensity, duration, and frequency (IDF) developed from historical rainfall
record obtained from the rain station within the site. Considering rainfall duration of 30
minutes, propose a temporary drain to help the developer and contractor solve the
problem, focusing on the area marked as A in Figure 1. However, there is at least one
limitation. The width of the channel should not be greater than 1 m wide.
3.
4.
Additional information:
4.1
4.2
For the purpose of channel design, the rate of flow Q can be obtained from the
continuity equation, i.e.
(2)
Q = AV
where, V = mean velocity of flow (m/s), and A = area of flow (m2).
Also, the Manning flow resistance equation gives
2 1
1
(3)
Q = AR 3 S o2
n
where, n = Manning roughness coefficient (see Table 2), yo = uniform depth of
A
flow (m), R = hydraulic radius = (m), P = wetted perimeter (m), and So =
P
longitudinal channel bed slope. Table 3 shows the recommend limit for surface
flow velocity.
5.
5.2
5.3
Project presentation carried out either through presentation in class, videopresentation or interview-based, is subjected to the instructor requirement. During
submission/presentation of the report, all members of the group must be present
where questions will be posed to each member of the group (see assessment
rubric).
Note: Please refer to your instructor if any doubt arises during project implementation as the
assessment and grading will be carried out by the class instructor.
Table 2: Values of Manning roughness coefficent n for open channels (Chow, 1959; DID,
2012)
Drain/pipe
Manning roughness n
Grassed drain
Short grass cover (< 150 mm)
0.035
0.050
0.017
0.035
0.030
0.020
Pipe material
Vitrified clay
Spun precast concrete
Fibre reinforced cement
UPVC
0.012
0.013
0.013
0.011
0.015
0.018
Recommended limit
< 0.5 m2/s
2 to 2.5 m or a half-lane
Flow velocity
i. soft lined waterways and overland flow paths
ii. hard lined channels
Ponding depth
References:
Chow, V. T. (1959). Open-Channel Hydraulics. USA: McGraw-Hill Book Co., Inc.
DID (Department of Irrigation and Drainage Malaysia) (2012). Urban Stormwater
Management Manual for Malaysia. Kuala Lumpur: DID.
Criteria
Use of correct
variables and
equations
Report
Use appropriate
concept and
methodology to
interpret data
Justification on
methodology,
assumption &
limitation in study
Subcriteria
Application of suitable
equations
Analyses done through step
by step methodology
Analyses the direction of
flow for chosen alignment
Provide suitable sizing of
channel
Synthesizes all data in
sizing & aligning channel
Justify the use of all
variables
Level
Weight
C3
1.0
C4
1.0
C4
1.0
C4
1.0
C5
0.5
C6
0.5
Total (%)
Score
/25.0
CLO2: Discuss technically the given open channel hydraulics problem (P3, PLO2)
Assessment
Criteria
Technical
investigations on
study area
Report &
Presentation
Utilizing information
and equations in
sizing channel
Use/adapt appropriate
channel size for the
study area
Subcriteria
Level
Descriptions on study area
P1
based on provided data
Extracting data for use in
P2
calculation and analyses
Careful selection of equations
P3
based on instructions
Solutions are clearly
P3
described
Calculations carried out are
P4
ensured correct (validated)
Choice on complexity of
P5
design variables selection
Adapting appropriate
P6
channel size technically
Weight
Score
0.5
1.5
1.5
1.5
1.5
0.7
0.3
Total (%)
7.5
/37.5
CLO3: Respond in group effectively in solving uniform and non-uniform flows problems (A3, PLO5)
Assessment
Criteria
Convey information
in group
Report &
Presentation
Convey spoken ideas
in group
Subcriteria
Follows given format of
project report
Shows contribution from all
members
Demonstrate the utilization
of provided information
Demonstrate the importance
of documented information
Organisation of group work
and presentation
Support members in Q&A
session
Level
Weight
A1
1.5
A2
1.5
A3
1.5
A3
2.0
A4
0.7
A5
0.3
Score
Total (%)
7.5
/37.5
20
/100
1.
2.
2. Learning Activities
3. Instructor (s)
4. Group Members
5. Generic/Soft Skills
6. Overall/Others