37

600-FKM (FYP1-PS-Rev.02)

PROJECT PLANNING
(List the main activities of the project. Indicate the length of time needed for each activity.)

2016
LI
PROJECT ACTIVITIES

FINDING SUPERVISOR

TITLE REGISTERATION
LITERATURE REVIEW AND
DATA COLLECTION
CONCEPT GENERATION
AND SELECTION
CATIA SOFTWARE
EXPLORATION
EARLY PROTOTYPE
FABRICATING
TEST RIG FABRICATING
FINAL PROTOYPE

SEMESTER 7

AUG
1

2017

SEPT
4

OCT
7

NOV

SEMESTER BREAK
DEC

JAN

9 10 11 12 13 14 15 16 17 18 19 20 1

SEMESTER 8

FEB
2

MAC
7

APRIL

MAY

9 10 11 12 13 14 15 16 17 18

38
600-FKM (FYP1-PS-Rev.02)

FABRICATING
TESTING AND
EVALUATION
SOLVING PROBLEM

REPORT WRITING

FYP 2 PRESENTATION

SUBMISSION OF FYP

INDICATOR
PLANNING
ACTUAL