Beruflich Dokumente
Kultur Dokumente
proceedings
Many large-diameter brick sewers were built in central Calcutta (now Kolkata), India during the 1870s. However,
over the past century they have deteriorated due to age, changed land-use patterns, lack of adequate maintenance
and failure of limited past measures to upgrade them. In 2007, the Kolkata Municipal Corporation embarked on a
major project of refurbishing the most critical stretches of these man-entry brick sewers with an estimated initial
cost of 70 million. The first phase of this work is due for completion in 2014. A costbenefit analysis shows an
economic internal rate of return of over 15%, amply justifying the investment towards sustainable renewal of an
indispensable infrastructure component.
1. Historical background
The birth of Kolkata (formerly Calcutta) as a commercial centre
was initiated by Job Charnock (16301692) of the English East
India Company in 1690. It became a crowning glory of British rule
and served as the administrative capital of continental India from
1757 to 1911. Planning and development of sanitation and drainage
infrastructure for Kolkata dates back to 1803 when governor-general
Lord Wellesley (17971805) stressed the need for public drains and
watercourses for a city receiving over 1600 mm annual rainfall,
mostly spread over a defined monsoon period (June to September).
However, despite several important instructions issued by the
governor-general, the work of providing a drainage system had been
limited to construction of Beliaghata Canal (1810) and a survey of the
town undertaken by John Schalch (17931825) (Smith, 1869). In 1821,
Schalch suggested providing major brick masonry sewers from the River
Hooghly to the proposed circular canal for conveying both sewage and
storm water run-off ultimately to salt-water lakes in the eastern part of the
city (present-day Salt Lake City). By 1835, several drainage proposals
were formulated by a number of prominent individuals (Goode, 1916).
1.1 The town scheme
Finally, a scheme proposal by William Clark, MICE (18211880)
was submitted to the municipal commissioners in November 1855 and
forwarded to the local government for approval. In 1858, it was decided
by the government that the scheme proposals be reviewed by Alexander
74
Downloaded by [] on [02/11/16]. Copyright ICE Publishing, all rights reserved.
2. Rehabilitation project
To formulate a workable and balanced refurbishment plan for the
brick sewers, it was important to recognise and identify the problems
with the existing sanitation system. Kolkata Municipal Corporation
(KMC) had conducted several studies to assess the ground condition
of its ailing sanitation infrastructure; the most important of these
being the ones funded by the Asian Development Bank (19992000)
and the World Bank (20002001).
These reports revealed the extremely dilapidated condition of the
century-old brick sewers and the high level of siltation that could be
r
we
se
d
oa
yR
Ro
C
AP
Nimtola
Ghat St.
sewer
Beadon
St. sewer
n
w ll
To tfa
u
O
Moulali
crossing
Civil Engineering
Volume 166 Issue CE2 May 2013
er
sew
oad
se R
o
B
AJC
Legend
Major brick sewer
Civil Engineering
Volume 166 Issue CE2 May 2013
Figure 3. Utilities cutting across brick sewer soffits have caused many of
the structural failures, with almost five collapses a week occuring in 2006
Name of
system
Town
Suburban
Total
Basin
area:
km2
Brick sewer
alignments
along road a
191
257
Length: m
Maximum dimension: mb
Total
Duration
Reported
collapses
of traffic
siltation: %
(19802006) blockage: h
(19802006)
Quantity
of silt
removed:
m3
Vert.
Hor.
4986
278
213
619
3433
5070
12 069
4631
279
215
627
3769
7085
12 288
Nimtola Ghat
Street
1785
239
186
215
1678
7075
4165
Beadon Street
747
242
189
114
787
70
1801
Canning Street
557
242
189
133
777
30
522
Kolutola Street
2000
242
189
258
1743
85
5749
Lenin Sarani
2787
239
188
333
1931
7075
6668
Hazra Road
(circular)
4044
Diameter 164217
457
3249
7580
8892 c
Rashbehari Avenue
(horseshoe)
4813
305
571
4242
70
362
3327
21 609
213
26 350
Sewers are named after their alignment along these prominent roads. Sewers are oval-shaped unless indicated.
b
Maximum clear vertical and horizontal dimensions of sewers are indicated and it varies along sewer length.
c
Work is ongoing in these sewers.
a
Table 1. Major man-entry brick sewers in Kolkata (Basu and Dey, 2012)
76
Downloaded by [] on [02/11/16]. Copyright ICE Publishing, all rights reserved.
52 516
Terminal
pumping
station
Palmer
Bridge
Ballygange
Civil Engineering
Volume 166 Issue CE2 May 2013
3. Trenchless technology
.8
1760 mm
2386 mm
2284 mm
36
Grouting
Rehabilitated with GRP 1760 x 2284 mm
77
Civil Engineering
Volume 166 Issue CE2 May 2013
4. Logistical challenges
Figure 6. Liner sections being delivered at night, when most work was
carried out due to reduced sewage flows
78
Downloaded by [] on [02/11/16]. Copyright ICE Publishing, all rights reserved.
Civil Engineering
Volume 166 Issue CE2 May 2013
79
Civil Engineering
Volume 166 Issue CE2 May 2013
Brick sewer
Project schedule
Start
Finish
Contract cost
INR million
million
Rehabilitation
cost:
million/km
Contractor
October 2008
November 2011
930
1283
257
November 2007
September 2010
795
1097
237
November 2008
January 2011
383
528
296
Beadon Street
November 2011
May 2012
158
219
293
Canning Street
November 2011
May 2012
104
144
259
Kolutola Street
November 2007
January 2011
368
508
254
Lenin Sarani
April 2008
May 2010
603
850
299
Hazra Road
November 2011
May 2014
720
993
246
Rashbehari Avenue
November 2011
September 2013
1018
1405
292
5079
7027
Total
a
Adjusted for rate of inflation as indicated in the text and adopting midmarket rate in the middle of the calendar year 2011 for conversion of INR into
Table 2. Project cost and current status (Basu and Dey, 2012)
80
Downloaded by [] on [02/11/16]. Copyright ICE Publishing, all rights reserved.
Civil Engineering
Volume 166 Issue CE2 May 2013
6. Current status
The cost and current status of the various brick sewer rehabilitation
works in Kolkata are given in Table 2.
Works for the sewers in the town system have been completed
and the refurbished sewers have been re-commissioned (Figure 9).
Works on two remaining main sewers in the suburban system are
ongoing and scheduled for completion by 2014.
Significant benefits in terms of better sanitation and reduced
flooding are already being experienced in the areas around the
completed sewers.
The project team is now adequately experienced to continue with
future rehabilitation programmes on Kolkatas brick sewers.
Acknowledgements
The authors would like to thank Vernon Downes, in particular,
and Michel Head of WERM Wink JV India Pvt. Ltd for their
contribution to the project. Support received from the then mayor
and commissioner of Kolkata Corporation for initiating the project
is also gratefully acknowledged.
The Kolkata Municipal Corporation project team comprised chief
engineer Subrata Kumar Seal, deputy chief engineers Somnath
Boral, Biplab Paul, Pranab Kumar Das, executive engineers Sushil
Kumar Mondal, Sarbani Kundu, Sudipto Chattopadhyay and
Samiran Ghosh, and other support staff.
The project contractors were Angerlehner Hoch- und Tiefbau
Gesellschaft mbH, Pucking, Austria and Michel Bau GmbH & Co.
KG, Neumnster, Germany.
References
ADB (Asian Development Bank) (1997) Guidelines for the Economic Analysis of Projects. Economics and Development Resource Centre, Manila, Philippines.
ASTM (2011) D3262: Standard specification for fiberglass (glass-fiber-reinforced thermosetting-resin) sewer pipe. ASTM International, West Conshohocken, PA, USA.
Basu NB and Dey A (2012) New life for Kolkatas sewers. Civil Engineering, ASCE 82(7/8): 6875.
CMS (Church Missionary Society) (1862) The Church Missionary Atlas, 3rd edn. Shelley, Jackson and Halliday, London, UK. See
http://wiki.fibis.org/index.php?title=File:Calcutta_map_1862_.jpg (accessed 06/02/2013).
Downey D (2006) Trenchless technology: a modern solution for clean-flowing cities. Proceedings of the Institution of Civil Engineers Civil Engineering 159(5): 2630,
http:// dx.doi.org/10.1680/cien.2006.159.5.16.
Goode SW (1916) Municipal Calcutta: its Institutions in their Growth and Origin. T & A Constable, Edinburgh, UK, reprinted in 2005 by Kolkata Municipal Corporation
and MacMillan, New Delhi, India.
Inocencio A, Kikuchi M, Tonosaki M et al. (2007) Costs and Performance of Irrigation Projects: a Comparison of Sub-Saharan Africa and Other Developing Regions.
International Water Management Institute, Colombo, Sri Lanka, IWMI Research Report 109.
Mohanty D (2011) Changing Inflation Dynamics in India. Reserve Bank of India, Mumbai, India, speech delivered at the Motilal Nehru National Institute of Technology
(MNNIT), Allahabad, India. See http://www.rbi.org.in/scripts/BS_SpeechesView.aspx?id=591 (accessed 06/02/2013).
Murty MN, Dhavala KK, Ghosh M and Singh R (2006) Social CostBenefit Analysis of Delhi Metro. Institute of Economic Growth, Delhi University Enclave, Delhi, India,
Working Paper 273. See http://iegindia.org/workpap/wp273.pdf (accessed 06/02/2013).
Pennington RA, Gersley KA, Gagliostro A et al. (2008) Serving a citys sewers. Civil Engineering, ASCE 78(12): 6067.
Roy J, Kanjilal M, Maitra S, Ghosh M and Dutta S (2008) Study on Willingness to Pay and Other Related Issues to Water Service Charge. Global Change Programme,
Jadavpur University, Kolkata, India, final report submitted to KMC/KEIP.
SA (Standards Australia) (1989) AS 3571: Glass filament reinforced thermosetting plastics (GRP) pipes polyester based water supply, sewerage and drainage
applications. Standards Australia Limited, Sydney, NSW, Australia.
Smith DB (1869) Report on the Drainage and Conservancy of Calcutta. Bengal Secretariat press, Calcutta, India.
WRC (Water Research Centre) (1986) Specification for Glassfibre Reinforced Plastics (GRP) Sewer Linings. WRC, Swindon, UK, information and guidance note 4-34-02.
WRC (2004) Sewer Rehabilitation Manual, 4th edn. Water Research Centre, Swindon, UK.
81