Beruflich Dokumente
Kultur Dokumente
BATCH PROCESSES
ADVANTAGE
DISADVANTAGE
Uninterrupted operation requires two or more
contact towers, so that at least one tower is on
stream when another is being recharged.
The pressure of liquids-poor upstream separation or
condensation in the tower due to temperature
changes ruins iron sponge chips and makes liquid
sweeteners foam.
Hydrate formation can occur at higher pressures
and lower temperatures.
Process Descriptions
Iron Sponge
Iron sponge is the oldest and still the most widely used batch process
(Duckworth and Geddes, 1965; Anerousis and Whitman, 1985; and
Zapffe, 1963). Because the bed consists of solid particles, the
superficial gas velocity is higher and the tower diameter smaller than
for slurries.
Iron sponge consists of wood chips or savings impregnated with
hydrated ferric oxide, Fe2O3, and sodium carbonate to control the pH
major suppliers are Connelly-GPM and Physichem Technologies.
The chips are dumped into the vertical contact tower (Figure 2)
through the manway at the top.
The sweetened reactions: ferric sulfide, Fe2S3, ferric mercaptide
Fe2O3 + 3 H2S = Fe2S3 + 3 H2O
Fe2O3 + 6 RSH = 2 Fe(RS)3 + 3 H2O
Regeneration: 2Fe2S3 + 3O2 = 2Fe2O3 + 6S
Calculation Procedure:
Gas actual flow rate, Qa at T&P
19.63(Q)(T 460)( Z )
Qa =
( P 14.7)
acfm
Superficial Velocity
ft/min
10.0
6.5
8.0
8.0
Cross Sectional
Area sq ft
0.10 Qa
0.16 Qa
0.11 Qa
0.13 Qa
ID = [A/0.7854]0.5 ft
Select a vessel OD that provides at least this internal diameter after
considering wall thickness. Calculate the actual ID (ft) and use this valve.
Example 1
Select & size sweetening process for gas stream 100 Mscfd, 100
ppm H2S, 1% CO2, 200 psig, 80 oF, SG=0.7, elevation =1000 ft.
First estimate sulfur content :
lb S scf lb mole gas mol H 2 S lb S 100,000 1
100 32
=
= 0.85
mol gas mol H S =
day day scf
1
379.5 1,000,000 1
Operation
The keys to trouble-free operating are proper installation of
the tower and preparation of the reactant. Be sure to :
Iron Sponge :
1. For medium and large vessels, coarse packing can be
placed below the bed support to prevent collapse of the
support structure and possible damage to the vessel shell.
2. Make sure there is a strainer in the exit gas line to remove
entrained particles of iron sponge.
Slurries
1. Check the water supply.
2. Check the pH of the batch.
3. Perform a foam test before starting the unit.
4. Make sure that the sour gas is saturated with water. If
not, add water periofically to restore the slurry level.
5. Include a downstream separator with a sight glass.
Trouble-shooting
The major problems are: premature H2S breakthrough;
rapid buildup of the pressure drop across iron sponge
beds; and foaming with bath carryover in slurries.
Iron Sponge :
1. Check the inlet gas temperature.
2. Check for channeling which usually occurs at very low gas
superficial velocities, i.e., below 2 ft/min.
3. Check for hydrate formation and condensation.
4. Check the alkalinity of the water in the bottom of the tower.
5. Check the pressure drop across the tower.
6. Find the cause of the liquids.
7. As a last resort back flow the bed to lift and repack the chips.
Slurries:
1. Check the sour gas velocity in the contactor.
2. Check the inlet gas temperature.
3. Check the bath level.
4. Check the outlet H2S cocentration.
5. Check the pH of the slurry.
6. Check for hydrocarbon condensation.
7. Check for settling of the slurry.
8. Check the inlet gas for RSH, RSSR, and COS.
9. Check the distributor plate or sparger.
Chemical Reaction
The reactions between amines and acid gases have been
examined extensively (Dankwerts, 1970; Deshmukh and Mather,
1981; Kent and Eisenberg, 1976; Moshfeghian et al., 1977).
Peotonation of the amine. RNH2, RRNH, and RRRN denote
primary, secondary, and tertiary amines, respectively and the
subtitution of one, two, and all three of the hydrogen atoms of the
parent ammonia molecule, NH3, with alkanol groups, for example,
with a primary amine: RNH2 + H+ = RNH3+
Reaction with H2S (RRNH). The addition compound between the
protonated amine and bisulfide ion can be formed by two parallel
mechanisms:
RRNH2+ + HS+ = RRNH2.SH
RRNH + H2S = RRNH2.SH
Chemical Reaction
The first reaction is fast, and together they limit the
formation of the sulfide addition compound:
2 RRNH2+ + S-- = (RRNH2).S
The rich solution is flashed at an intermediate pressure and
again at low pressure where it is also stripped with the
overhead vapors from the regenerator.
Design:
Amine Flow Rate
1. Select the appropriate sweetening solution and the
concentrations of amine and physical solvent.
2. Calculate the partial pressure of H2S, CO2, RSH and other
organic sulfur gases using the tower pressure and the inlet
gas composition.
3. Estimate the temperature of the rich amine solution at the
bottom of the contact tower. This is usually 20 to 40 oF hotter
than the inlet gas.
4. Calculate the equilibrium loadings for H2S, CO2, RSH, etc., in
the rich amine solution.
5. Assume an approach to equilibrium and determine the
pickups for H2S, CO2, RSH, etc.
6. Calculate the amine circulation rate from the pickup and the
acid gas content of the sour gas.
Adsorption System
1. The high-pressure process gas system consists of an inlet
scrubber, contact tower, and outlet separator.
2. The inlet scrubber removes slugs and drops of condensed
hydrocarbons, produced water, corrosion inhibitors, and well
treating chemicals from the inlet sour gas stream.
3. Most adsorber towers use trays to contact the sour gas with the
amine solution.
4. The cross-sectional area of the contactor is sized for the gas and
amine flow rates. The maximum gas superficial velocity is obtained
from the Souders-Brown equation.
Vgas = 0.25 [(amine - gas)/gas]0.5 ft/sec.
Regeneration System
1. The regeneration system consists of a flash tank,
rich/lean amine heat exchanger, stripping still, reboiler
filters, and aerial cooler.
2. The lean/rich amine heat exchanger preheats the rich
amine solution and reduces the duty of the reboiler.
Reclaimer
1. Primary amines require additional regeneration, i.e.,
semi-continous distillation in areclaimer (Fig. 6).
2. The reclaimer temperature rises as the contaminants
accumulate and operation is stopped at a predetermined
temperature 300 oF for MEA to limit thermal
degradation of the amine.
Filters
Both mechanical filters for particulates and activated carbon
filters for heavy hydrocarbons and amine degradation
products are needed.
A mechanical filter in the rich amine line just after the flash
tank prevents plugging in the lean/rich heat exchanger and
still.
Including a carbon filter reduces the tendency to foam in
the still, but this adsorbs hydrocarbons that would otherwise
be removed in the still.
The mechanical filter should be full flow and remove 95% of
10 microns or large particles.
Pumps
1. The amine booster and reflux pumps are centrifugal,
preferably in-line or horizontal, with TEFC motors.
2. In sizing and rating pumps use a low positive suction
pressure of 310 psig. Motor sizes can be estimated
from the amine circulation rate (Jones and Perry, 1973).
Motor
Horsepower
Circulation Pump
Booster Pumps
gpm x 0.06
Reflux Pumps
gpm x 0.06
Aerial Cooler
gpm x 0.36
Construction Materials
1. Pearce and DuPart (1985) and Richert et al. (1989) reviewed the types
of corrosion that occur in amine plants: general, galvanic, crevice,
pitting, intergranular, selective leaching, erosion, and stress corrosion
cracking.
2. In considering the susceptibility of steel to stress corrosion cracking the
key property is hardness. In addition to H2S corrosion, the following
factors must be considered :
3. CO2 corrosion, especially when the rich amine temperature exceeds 150
oF.
4. Electrolytic corrosion due to the presence of unlike netals in aqueous
environments.
5. Oxidation corrosion due to free oxygen in the makeup water ad feed gas
streams.
Operation
Plant Check Out
1. Check that all materials have been received and order
replacements for damaged items.
2. Install blinds on the inlet gas line to prevent accidental and
premature pressurization of plant.
3. Check assembly of plant.
4. Check mechanical equipment for lubrication, alignment, rotation,
etc. Pack pumps and put filter elements into filters.
5. Check calibration of pressure, flow, and temperature and level
instrumen. Pressure test vessels, pipes, etc., using water or
clean gas. Repair leaks.
6. Check the alarm and safety devices.
7. Remove blinds and establish fuel gas, instrument air, and power
supply.
Troubleshooting
1.Gas is not Sweet
2.Amine solution not regenerated
3.Dirty, degraded amine
4.Excessive corrosion
5.Foaming of amine solution