IKPP Perawang PPM# 7 installation feeding system

40076
Make a floor and construct
Provide water, air, power 220 V and 380 V
Equipment arrive IKPP Perawang and cutom clearance
Start Installation
Water Trial for equipment
Ready equipment

Gantt chart created 12/29/2016

40083

40090

40097

40104

40111

40118

IKPP Perawang PPM# 7 installation feeding system


Gantt Chart Maker
Name
Buckman : Joni /Hanes
IKPP Perawang PPM# 7
Buckman : Joni /Hanes
Buckman : Joni /Hanes
Buckman : Joni /Hanes
Buckman : Joni /Hanes

Task description
Make a floor and construct
Provide water, air, power 220 V and 380 V
Equipment arrive IKPP Perawang and cutom clearance
Start Installation
Water Trial for equipment
Ready equipment

Start date # of days


9/20/2009
7
9/20/2009
14
10/8/2009
6
10/14/2009
10
10/24/2009
4
10/28/2009
2

End date
9/27/2009
10/4/2009
10/14/2009
10/24/2009
10/28/2009
10/30/2009

How to create a Gantt chart


1. Enter task descriptions.
2. Enter task start dates.
3. Enter number of days to complete each
task. The program assumes weekends
are work days, so you may need to allow
for that.
4. Enter the name of the person
responsible for each task, if desired. This
will not show on the Gantt chart.
5. If you need to insert one or more tasks
into the middle of the task list, click the
Insert task(s) button.
6. If you need to remove one or more
tasks from the list, click the
Remove task(s) button.
7. Type a title for the chart in cell C3.
8. When you are ready to create the
charts, click the Make Gantt chart button.
Notes:
- There is 2 task minimum and 500 task
maximum.
- You may make additional charts
whenever you like.
- You may delete existing charts whenever
you like.
- See cell comments for additional tips.