Beruflich Dokumente
Kultur Dokumente
C
Activity ID
Page 1 of 7
Activity Name
340
15-Apr-14
13-Jun-15
411
15-Apr-14
30-May-15
30-May-15
399
15-Apr-14
18-May-15
18-May-15, U
325
15-Apr-14
05-Mar-15
15-Apr-14*
1020.KD.UP.71
Access Date for Track Installation + OHL 1st Fix (CH 10000 - 9370)
30-Jul-14*
1020.KD.UP.121
1020.KD.UP.201
1020.KD.UP.241
0
245
2015
April May June July
0
0 2 1 0
Start
1020.KD.UP.1
Approx.630m
2014
ril May June July
2 1
0 2 2
O.D
A
1
O
1
J
1
M
2 1
13-Jun-
Approx.6
29-Oct-14
01-Jan-15*
05-Mar-15
15-Apr-14
15-Dec-14
1020.KD.UP.11
15-Apr-14
1020.KD.UP.21
15-Apr-14
1020.KD.UP.51
1st Access Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C1064 pipe installation
1020.KD.UP.61
Completion Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C1064 pipe installation for 1st Access 0
1020.KD.UP.81
Access Date for Turnout and Rail Delivery (Short Rails - 18m) via HOM Zone B
30-Jul-14*
1020.KD.UP.91
2nd Access Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C1064 pipe installation
15-Aug-14*
1020.KD.UP.101
Completion Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C1064 pipe installation for 2nd Access 0
1020.KD.UP.111
Access Date for Track Installation + OHL 1st Fix (CH 8500 - 8300) Approx. 200m
31-Aug-14*
1020.KD.UP.151
Access Date for Turnout and Rail Delivery (Long Rails - 72m) via HOM Zone B
15-Dec-14*
1020.KD.UP.221
Access for OHL 2nd Fix Works using UNIMOG + WORKS TRAIN
15-Dec-14*
42
30-Nov-14
1st Access Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C1064 pipe install
15-Jun-14*
20-Jun-14
Completion Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C1064 pipe inst
Access Date for Turnout and Rail Delivery (Short Rails - 18m) via HOM Zone B
2nd Access Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C10
26-Aug-14
Completion Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C
Access Date for Track Installation + OHL 1st Fix (CH 8500 - 8300) App
10-Jan-15
1020.KD.UP.131
Access Date for Track Installation + OHL1st Fix (CH 8300 - 8050) Approx.250m
30-Nov-14*
1020.KD.UP.141
Access for OHL 2nd Fix Works using UNIMOG + WORKS TRAIN
15-Dec-14*
1020.KD.UP.161
Completion Date - Degree 1 (Trackwork + OHL 1st Fix ) (CH 8050 - 8530) Approx. 480m
16-Dec-14
1020.KD.UP.231
10-Jan-15*
351
15-Apr-14
31-Mar-15
Access for OHL 2nd Fix Works using WORKS TRAIN
1020.KD.UP.31
15-Apr-14
1020.KD.UP.171
Access Date for Track Installation + OHL1st Fix (CH 9370 - 8700) Approx.670m
15-Jan-15*
1020.KD.UP.261
Completion Date - Degree 1 (Trackwork + OHL 1st Fix ) (CH 9370 - 8700 ) Approx.670m
27-Mar-15
1020.KD.UP.41
Completion Date - Degree 2 (OHL 2nd Fix) CH 9370 - 8700) Approx . 670m
31-Mar-15
18-May-15
18-May-15, H
65
15-Mar-15
1020.KD.UP.181
Access Date for Track Installation + OHL 1st Fix (CH 8700 - 8500) Approx.200m
15-Mar-15*
1020.KD.UP.211
01-Apr-15*
1020.KD.UP.191
Completion Date - Degree 1 (Trackwork + OHL 1st Fix ) (CH 8700 - 8500) Approx.200m
15-Apr-15
1020.KD.UP.251
18-May-15
Completion D
411
15-Apr-14
30-May-15
30-May-15
311
30-Jun-14
06-May-15
06-May-15, YAU
30-Jun-14*
1020.KD.DN.61
Access Date for Track Installation + OHL 1st Fix (CH 10000 - 9370) Approx. 630m
1020.KD.DN.101
Summary
Completion Date - D
Access Date for Track Installation + OHL 1st Fix (CH 10000 - 9370) Approx. 630m
06-Oct-14
Date
28-May-12
15-Jun-12
26-Jun-12
04-Aug-14
Revision
Rev.0
Rev.A
Rev.B
Rev.C
Checked
TM
TM
TM
TM
Approved
PHH
PHH
PHH
PHH
1020.KD.DN.31
Page 2 of 7
Activity Name
O.D
0
246
1020.KD.DN.71
1020.KD.DN.81
1020.KD.DN.91
Access Date for Turnout & Track Installation + OHL 1st Fix (CH 8500 - 8300) Approx. 200m
1020.KD.DN.121
Finish
06-May-15
15-Apr-14
2014
ril May June July
2 1
0 2 2
A
1
O
1
2015
April May June July
0
0 2 1 0
M
2 1
Completion Dat
14-Aug-14*
Access Date for Turnout & Track Installation + OHL 1st Fix (CH 8500 -
31-Aug-14*
16-Dec-14
15-Nov-14
01-Aug-14*
81
J
1
16-Dec-14
15-Apr-14
03-Feb-15
1020.KD.DN.111
Access Date for Track Installation + OHL1st Fix (CH 8300 - 7890) Approx.410m
15-Nov-14*
1020.KD.DN.141
15-Dec-14*
1020.KD.DN.151
16-Dec-14
1020.KD.DN.211
03-Feb-15
06-May-15
06-May-15, WY
158
30-Nov-14
1020.KD.DN.131
Access Date Track Installation + OHL1st Fix (CH 9370 - 8900) Approx. 470m
30-Nov-14*
1020.KD.DN.161
Access Date Track Installation + OHL1st Fix (CH 8900 - 8700) Approx. 200m
15-Jan-15*
1020.KD.DN.221
Completion Date - Degree 1 (Trackwork + OHL 1st Fix ) (CH 9370 - 8700 ) Approx . 670m
26-Feb-15
1020.KD.DN.41
06-May-15
Completion Dat
46
15-Mar-15
15-Mar-15*
1020.KD.DN.181
Access Date for Track Installation + OHL 1st Fix (CH 8700 - 8500) Approx.200m
1020.KD.DN.1
Completion Date - Degree 1 (Trackwork + OHL 1st Fix ) (CH 8700 - 8500) Approx.200m
WHAMPOA STATION
STATIO (WHA) (CH 7890 - 7400) Approx.490m
29-Apr-15, HO M
29-Apr-15
29-Apr-15
126
25-Jan-15
30-May-15
30-May-15
1020.KD.DN.171
Access Date for Track Installation + OHL1st Fix (CH 7400 - 7555) Approx.155m
25-Jan-15*
1020.KD.DN.11
Access Date for Track Installation + OHL1st Fix (CH 7835 - 7890) Approx.55m
15-Mar-15*
1020.KD.DN.191
Access Date for Track Installation + OHL1st Fix (CH 7555 - 7690) Approx.135m
22-Mar-15*
1020.KD.DN.201
Access Date for Track Installation + OHL1st Fix (CH 7690 - 7835) Approx.145m
15-Apr-15*
1020.KD.DN.231
20-May-15
Completion D
1020.KD.DN.51
30-May-15
Completion
402
15-Apr-14
22-May-15
22-May-15, S
258
15-Apr-14
29-Dec-14
15-Apr-14
1020.SA.1
Possession Date
1020.SA.41
Vacation Date
GASCOIGNE ROAD
ROA TRACTION SUBSTATION (GAR) (STAGING & ACCESS AREA)
15-Apr-14
15-Apr-14
Posssesion Date
1020.SA.61
Vacation Date
31-Aug-14
31-Aug-14*
Posssesion Date
1020.SA.31
Vacation Date
Posssesion Date
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
22-May-15, G
22-May-15
Posssesion Date
Vacation Da
22-May-15*
108
1020.SA.21
Vacation Date
29-Dec-14*
402
1020.SA.11
Possession Date
16-Dec-14
Posssesion Date
Vacation Date
16-Dec-14
110
25-Jan-15
25-Jan-15*
14-May-15, FI
14-May-15
Posssesion Date
Date
28-May-12
15-Jun-12
26-Jun-12
04-Aug-14
Revision
Rev.0
Rev.A
Rev.B
Rev.C
Checked
TM
TM
TM
TM
Approved
PHH
PHH
PHH
PHH
1020.SA.71
Page 3 of 7
Activity Name
O.D
Vacation Date
Finish
14-May-15
A
1
O
1
J
1
M
2 1
2015
April May June July
0
0 2 1 0
Vacation Date
20-May-15, T
320
15-Apr-14
20-May-15
282
15-Apr-14
31-Mar-15
31-Mar-15, UP TRACK
198
30-Jul-14
31-Mar-15
31-Mar-15, RESOURCE
1020.TW.UP.21
YMT - WAB
76
30-Jul-14
29-Oct-14
1020.TW.UP.101
14
01-Dec-14
16-Dec-14
1020.TW.UP.141
44
15-Jan-15
13-Mar-15
1020.TW.UP.221
HOM
14
16-Mar-15
31-Mar-15
160
15-Apr-14
29-Oct-14
2014
ril May June July
2 1
0 2 2
YMT - WAB
HOM XVR - END OF TRACK
WAB - HOM Tunnels
HOM
29-Oct-14, YMT - WAB (CH 10000 - 9370) Approx.630
Rail Delivery and Stoarge thru Kowloon Bay Depot
1020.TW.UP.1
100
15-Apr-14
16-Aug-14
1020.TW.UP.11
40
30-Jul-14
15-Sep-14
1020.TW.UP.31
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 10000 - 9895) Approx.105m
16-Sep-14
22-Sep-14
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works
1020.TW.UP.41
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9895 - 9790) Approx.105m
23-Sep-14
29-Sep-14
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Wor
1020.TW.UP.51
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9790 - 9685) Approx.105m
30-Sep-14
08-Oct-14
1020.TW.UP.61
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9685 - 9580) Approx.105m
09-Oct-14
15-Oct-14
1020.TW.UP.71
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9580 - 9475) Approx.105m
16-Oct-14
22-Oct-14
1020.TW.UP.81
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9475 - 9370) Approx.105m
23-Oct-14
29-Oct-14
14
01-Dec-14
16-Dec-14
1020.TW.UP.91
01-Dec-14
02-Dec-14
1020.TW.UP.111
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8050 - CH 8175) Approx.125m
03-Dec-14
09-Dec-14
1020.TW.UP.121
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8175 - CH 8300) Approx.125m
10-Dec-14
16-Dec-14
44
15-Jan-15
13-Mar-15
1020.TW.UP.131
15-Jan-15
23-Jan-15
1020.TW.UP.151
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8700 - 8810) Approx.110m
24-Jan-15
30-Jan-15
1020.TW.UP.161
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8810 - 8920) Approx.110m
31-Jan-15
06-Feb-15
1020.TW.UP.171
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8920 - 9030) Approx.110m
07-Feb-15
13-Feb-15
1020.TW.UP.181
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9030 - 9140) Approx.110m
14-Feb-15
27-Feb-15
1020.TW.UP.191
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9140 - 9250) Approx.110m
28-Feb-15
06-Mar-15
1020.TW.UP.201
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9250 - 9370) Approx.120m
07-Mar-15
13-Mar-15
14
16-Mar-15
31-Mar-15
16-Mar-15
19-Mar-15
Site Set-Up,Survey,Materia
1020.TW.UP.231
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8700 - 8600) Approx.100m
20-Mar-15
25-Mar-15
1020.TW.UP.241
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8600 - 8500) Approx.100m
26-Mar-15
31-Mar-15
261
30-Jun-14
20-May-15
20-May-15, D
261
30-Jun-14
20-May-15
20-May-15, R
YMT - WAB
61
30-Jun-14
10-Sep-14
1020.TW.DN.101
27
15-Nov-14
16-Dec-14
1020.TW.DN.211
02-Feb-15
02-Feb-15
1020.TW.DN.241
HOM
18
16-Mar-15
09-Apr-15
Summary
YMT - WAB
HOM XVR - WHA
WAB - HOM Tunnels
HOM
Date
28-May-12
15-Jun-12
26-Jun-12
04-Aug-14
Revision
Rev.0
Rev.A
Rev.B
Rev.C
Checked
TM
TM
TM
TM
Approved
PHH
PHH
PHH
PHH
1020.TW.DN.291
Page 4 of 7
Activity Name
WHA
O.D
Start
Finish
30
15-Apr-15
20-May-15
71
30-Jun-14
22-Sep-14
2014
ril May June July
2 1
0 2 2
A
1
O
1
J
1
M
2 1
2015
April May June July
0
0 2 1 0
WHA
1020.TW.DN.1
25
30-Jun-14
29-Jul-14
1020.TW.DN.21
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 10000 - 9895) Approx.105m
30-Jul-14
05-Aug-14
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 100
1020.TW.DN.31
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9895 - 9790) Approx.105m
06-Aug-14
12-Aug-14
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 98
1020.TW.DN.41
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9790 - 9685) Approx.105m
13-Aug-14
19-Aug-14
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH
1020.TW.DN.51
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9685 - 9580) Approx.105m
20-Aug-14
26-Aug-14
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH
1020.TW.DN.61
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9580 - 9475) Approx.105m
27-Aug-14
02-Sep-14
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (C
1020.TW.DN.71
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9475 - 9370) Approx.105m
03-Sep-14
10-Sep-14
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works)
1020.TW.DN.81
Material Delivery and Storage (Sleepers, FST, Baseplates) for WAB - Ho Man Tin Section (Up & Dn Track) ... 10
11-Sep-14
22-Sep-14
27
15-Nov-14
16-Dec-14
15-Nov-14
18-Nov-14
1020.TW.DN.111
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 7890 - 7990) Approx.100m
19-Nov-14
25-Nov-14
1020.TW.DN.121
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 7990 - 8090) Approx.100m
26-Nov-14
02-Dec-14
1020.TW.DN.131
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8090 - 8190) Approx.100m
03-Dec-14
09-Dec-14
1020.TW.DN.141
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8190 - 8300) Approx.110m
10-Dec-14
16-Dec-14
53
17-Dec-14
26-Feb-15
17-Dec-14
24-Dec-14
1020.TW.DN.161
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9370 - 9250 ) Approx.120m
12
27-Dec-14
10-Jan-15
1020.TW.DN.171
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9250- 9140 ) Approx.110m
12-Jan-15
17-Jan-15
1020.TW.DN.181
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9140 - 9030 ) Approx.110m
19-Jan-15
24-Jan-15
1020.TW.DN.191
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 9030 - 8920 ) Approx.110m
26-Jan-15
31-Jan-15
1020.TW.DN.201
02-Feb-15
05-Feb-15
1020.TW.DN.221
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8920 - 8810 ) Approx.110m
06-Feb-15
12-Feb-15
1020.TW.DN.231
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8810 - 8700 ) Approx.110m
13-Feb-15
26-Feb-15
18
16-Mar-15
09-Apr-15
16-Mar-15
21-Mar-15
Site Set-Up,Survey,Materi
1020.TW.DN.261
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8500 - 8600) Approx.100m
23-Mar-15
28-Mar-15
1020.TW.DN.271
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8600 - 8700) Approx.100m
30-Mar-15
09-Apr-15
30
15-Apr-15
20-May-15
20-May-15, W
1020.TW.DN.281
Site Set-Up,Survey,Material Delivery for UP & DN Track (CH 7890 - CH 7400 ) Approx. 490m
15-Apr-15
21-Apr-15
Site Set-Up,Survey
1020.TW.DN.301
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 7890 - 7775) Approx.115m
22-Apr-15
28-Apr-15
Track Installation
1020.TW.DN.311
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 7775 - 7650) Approx.125m
29-Apr-15
06-May-15
Track Installatio
1020.TW.DN.321
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 7650 - 7525) Approx.125m
07-May-15
13-May-15
Track Installat
1020.TW.DN.331
Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) ( CH 7525 - 7400) Approx.125m
14-May-15
20-May-15
115
01-Aug-14
16-Dec-14
85
05-Sep-14
16-Dec-14
16-Dec-14, RESOURCES
Turnout 1 - T 82 - DN Track
16
05-Sep-14
24-Sep-14
1020.T/O.81
Turnout 2 - T 83 - UP Track
20
25-Sep-14
20-Oct-14
Summary
Track Installa
Turnout 1 - T 82 - DN Track
Turnout 2 - T 83 - UP Track
Date
28-May-12
15-Jun-12
26-Jun-12
04-Aug-14
Revision
Rev.0
Rev.A
Rev.B
Rev.C
Checked
TM
TM
TM
TM
Approved
PHH
PHH
PHH
PHH
Page 5 of 7
Activity Name
O.D
Start
Finish
1020.T/O.121
Diamond Crossing
20
21-Oct-14
12-Nov-14
1020.T/O.151
Turnout 3 - T 84 - DN Track
15
15-Nov-14
02-Dec-14
1020.T/O.181
Turnout 4 - T 81 - UP Track
14
01-Dec-14
16-Dec-14
46
01-Aug-14
24-Sep-14
2014
ril May June July
2 1
0 2 2
A
1
O
1
J
1
Diamond Crossing
M
2 1
2015
April May June July
0
0 2 1 0
Turnout 3 - T 84 - DN Track
Turnout 4 - T 81 - UP Track
24-Sep-14, FST Trackform & Turnout no .1 - (T82 ) - DN Track T2
Rail, Material and Turnout Delivery via HOM by 1001 Hoisting Facility
1020.T/O.1
Rail, Material and Turnout Delivery via HOM by 1001 Hoisting Facility
01-Aug-14
05-Aug-14
1020.T/O.31
FST Type -2 Trackform Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8450 - 8480) A...
01-Sep-14
04-Sep-14
1020.T/O.41
05-Sep-14
15-Sep-14
1020.T/O.61
Final Survey , Adjustments , Levelling , Conrceting with Misc Works for Turnout Trackform
16-Sep-14
24-Sep-14
62
06-Aug-14
20-Oct-14
Rail, Material and Turnout Delivery via HOM by 1001 Hoisting Facility
06-Aug-14
09-Aug-14
1020.T/O.71
FST Type - Track Installation (Fmk Fix, Adjust, Level, Concreting & Misc Works) (CH 8460 - 8590) Approx... 4
25-Sep-14
29-Sep-14
1020.T/O.91
30-Sep-14
10-Oct-14
1020.T/O.101
Final Survey , Adjustments , Levelling , Conrceting with Misc Works for Turnout Trackform
11-Oct-14
20-Oct-14
78
11-Aug-14
12-Nov-14
Rail, Material and Turnout Delivery via HOM by 1001 Hoisting Facility
11-Aug-14
14-Aug-14
1020.T/O.111
10
21-Oct-14
31-Oct-14
1020.T/O.131
Final Survey , Adjustments , Levelling , Conrceting with Misc Works for Turnout Trackform
10
01-Nov-14
12-Nov-14
15
15-Nov-14
02-Dec-14
Rail, Material and Turnout Delivery via HOM by 1001 Hoisting Facility
FST Type - Track Installation (Fmk Fix, Adjust, Level, Concreting
Survey , Assembly,Positioning for Turnout Trackform
Final Survey , Adjustments , Levelling , Conrceting with Misc
12-Nov-14, Diamond Crossing (DIAMX) T2
Rail, Material and Turnout Delivery via HOM by 1001 Hoisting Facility
Survey , Assembly,Positioning for DIAM Trackform
Final Survey , Adjustments , Levelling , Conrceting with
02-Dec-14, Turnout no .3 - (T84 ) - DN Track T2
1020.T/O.141
15-Nov-14
18-Nov-14
1020.T/O.161
Final Survey , Adjustments , Levelling , Conrceting with Misc Works for Turnout Trackform
12
19-Nov-14
02-Dec-14
14
01-Dec-14
16-Dec-14
01-Dec-14
02-Dec-14
1020.T/O.191
Final Survey , Adjustments , Levelling , Conrceting with Misc Works for Turnout Trackform
12
03-Dec-14
16-Dec-14
293
16-Jun-14
13-Jun-15
13-Jun-
244
16-Jun-14
15-Apr-15
207
30-Jul-14
15-Apr-15
OVERHEAD LINE
LIN (OHL) INSTALLATION WORKS [OVERHEAD RIGID CONDUCTOR RIGID (O...
OHL 1st FIX - UP
U TRACK
RESOURCES
1020.OHL1.UP.31
YMT - WAB
16
30-Jul-14
16-Aug-14
1020.OHL1.UP.61
HOM XVR
12
03-Dec-14
16-Dec-14
1020.OHL1.UP.81
12
14-Mar-15
27-Mar-15
1020.OHL1.UP.121
HOM
12
28-Mar-15
15-Apr-15
16
30-Jul-14
16-Aug-14
1020.OHL1.UP.21
1st Fix - Survey, Setting out , Drilling, Pull-out tests, Template Check
30-Jul-14
05-Aug-14
1020.OHL1.UP.41
10
06-Aug-14
16-Aug-14
154
16-Jun-14
16-Dec-14
1020.OHL1.UP.1
1st Access Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C1064 pipe installation
16-Jun-14*
20-Jun-14
1st Access Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C1064 pipe instal
1020.OHL1.UP.11
2nd Access Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C1064 pipe installation
10
15-Aug-14
26-Aug-14
2nd Access Date for OHL 1st Fix (Preliminary Works) in HOM XVR for C
1020.OHL1.UP.51
1st Fix - Survey, Setting out , Drilling, Pull-out tests, Template Check
03-Dec-14
09-Dec-14
1020.OHL1.UP.71
10-Dec-14
16-Dec-14
12
14-Mar-15
27-Mar-15
Summary
Date
28-May-12
15-Jun-12
26-Jun-12
04-Aug-14
Revision
Rev.0
Rev.A
Rev.B
Rev.C
Checked
TM
TM
TM
TM
Approved
PHH
PHH
PHH
PHH
Page 6 of 7
Activity Name
O.D
Start
Finish
2014
ril May June July
2 1
0 2 2
A
1
O
1
J
1
M
2 1
2015
April May June July
0
0 2 1 0
1020.OHL1.UP.91
1st Fix - Survey, Setting out , Drilling, Pull-out tests, Template Check (CH 8900 - 8700) Approx 200m
14-Mar-15
20-Mar-15
1020.OHL1.UP.101
1st Fix - Drop Tube Support Installation (CH 8900 - 8700) Approx 200m
21-Mar-15
27-Mar-15
12
28-Mar-15
15-Apr-15
15-Apr-15, HOM (C
1020.OHL1.UP.111
28-Mar-15
08-Apr-15
1020.OHL1.UP.131
1st Fix - Survey, Setting out , Drilling, Pull-out tests, Template Check
09-Apr-15
15-Apr-15
195
11-Sep-14
14-May-15
14-May-15, O
195
11-Sep-14
14-May-15
14-May-15, RE
YMT - WAB
1020.OHL1.DN.11
YMT - WAB
20
11-Sep-14
06-Oct-14
1020.OHL1.DN.41
12
03-Dec-14
16-Dec-14
1020.OHL1.DN.71
12
15-Jan-15
28-Jan-15
1020.OHL1.DN.101
HOM
12
16-Apr-15
29-Apr-15
1020.OHL1.DN.131
WHA
12
30-Apr-15
14-May-15
20
11-Sep-14
06-Oct-14
HOM
WHA
1020.OHL1.DN.1
1st Fix - Survey, Setting out , Drilling, Pull-out tests, Template Check
10
11-Sep-14
22-Sep-14
1020.OHL1.DN.21
10
23-Sep-14
06-Oct-14
12
03-Dec-14
16-Dec-14
1020.OHL1.DN.31
1st Fix - Survey, Setting out , Drilling, Pull-out tests, Template Check
03-Dec-14
09-Dec-14
1020.OHL1.DN.51
10-Dec-14
16-Dec-14
12
15-Jan-15
28-Jan-15
1020.OHL1.DN.61
1st Fix - Survey, Setting out , Drilling, Pull-out tests, Template Check
15-Jan-15
21-Jan-15
1020.OHL1.DN.81
22-Jan-15
28-Jan-15
12
16-Apr-15
29-Apr-15
29-Apr-15, HOM
1st Fix - Survey, Setting out , Drilling, Pull-out tests, Template Check
16-Apr-15
22-Apr-15
1020.OHL1.DN.111
23-Apr-15
29-Apr-15
12
30-Apr-15
14-May-15
14-May-15, W
1st Fix - Survey, Setting out , Drilling, Pull-out tests, Template Check
30-Apr-15
07-May-15
1020.OHL1.DN.141
08-May-15
14-May-15
140
16-Dec-14
13-Jun-15
118
16-Dec-14
18-May-15
13-Jun18-May-15, R
END OF TRACK - HOM XVR
1020.OHL2.UP.51
20
16-Dec-14
10-Jan-15
1020.OHL2.UP.61
YMT - WAB
20
04-Feb-15
05-Mar-15
1020.OHL2.UP.11
18-Mar-15
18-Mar-15
1020.OHL2.UP.81
HOM
10
07-May-15
18-May-15
20
16-Dec-14
10-Jan-15
2nd Fix - Rigid Rail Installation + Unwinding cables+ Equipment Installation using UNIMOG
10
16-Dec-14*
29-Dec-14
1020.OHL2.UP.91
10
30-Dec-14
10-Jan-15
20
04-Feb-15
05-Mar-15
2nd Fix - Rigid Rail Installation + Unwinding cables + Equipment Installation by WORKS TRAIN & UNIMOG
10
04-Feb-15*
14-Feb-15
1020.OHL2.UP.101
10
16-Feb-15
05-Mar-15
Summary
YMT - WAB
WAB - HOM TUNNELS
HOM
Date
28-May-12
15-Jun-12
26-Jun-12
04-Aug-14
Revision
Rev.0
Rev.A
Rev.B
Rev.C
Checked
TM
TM
TM
TM
Approved
PHH
PHH
PHH
PHH
Page 7 of 7
Activity Name
O.D
Start
Finish
22
06-Mar-15
31-Mar-15
2014
ril May June July
2 1
0 2 2
A
1
O
1
J
1
M
2 1
2015
April May June July
0
0 2 1 0
31-Mar-15, WAB - HO
1020.OHL2.UP.21
2nd Fix - Rigid Rail Installation + Unwinding cables + Equipment Installation by WORKS TRAIN & UNIMOG
10
06-Mar-15*
17-Mar-15
1020.OHL2.UP.1
12
18-Mar-15
31-Mar-15
10
07-May-15
18-May-15
18-May-15, H
2nd Fix - Rigid
2nd Fix - Rigid Rail Installation + Unwinding cables + Equipment Installation by WORKS TRAIN
07-May-15*
11-May-15
1020.OHL2.UP.111
12-May-15
18-May-15
08-Jun-15
13-Jun-15
13-Jun-
08-Jun-15
13-Jun-15
Comple
114
12-Jan-15
06-Jun-15
06-Jun-1
108
12-Jan-15
30-May-15
30-May-15
COMPLETE UP TRACK
TR
(CH 10000 - 8050 ) Total Length . 1950m
1020.OHL2.UP.100
20
12-Jan-15
03-Feb-15
1020.OHL2.DN.1
26
01-Apr-15
06-May-15
YMT - HOM XV
1020.OHL2.DN.41
WHA
10
19-May-15
30-May-15
WHA
20
12-Jan-15
03-Feb-15
CONTRACT LIMIT 1001/1002 - HOM XVR (CH 7890 - 8500) Approx . 610m
1020.OHL2.DN.61
2nd Fix - Rigid Rail Installation + Unwinding cables + Equipment Installation using UNIMOG
10
12-Jan-15
22-Jan-15
1020.OHL2.DN.81
10
23-Jan-15
03-Feb-15
26
01-Apr-15
06-May-15
06-May-15, YMT
2nd Fix - Rigid Rail
1020.OHL2.DN.11
2nd Fix - Rigid Rail Installation + Unwinding cables + Equipment Installation by WORKS TRAIN & UNIMOG
12
01-Apr-15
18-Apr-15
1020.OHL2.DN.21
14
20-Apr-15
06-May-15
10
19-May-15
30-May-15
30-May-15
2nd Fix - Rigid Rail Installation + Unwinding cables + Equipment Installation by WORKS TRAIN
19-May-15
22-May-15
1020.OHL2.DN.51
23-May-15
30-May-15
2nd FIx - F
01-Jun-15
06-Jun-15
06-Jun-1
01-Jun-15
06-Jun-15
Complete
COMPLETE DN TRACK
TR
(CH 10000 - 7400 ) Total Length . 2600m
1020.OHL2.DN.100
Summary
Date
28-May-12
15-Jun-12
26-Jun-12
04-Aug-14
Revision
Rev.0
Rev.A
Rev.B
Rev.C
Checked
TM
TM
TM
TM
Approved
PHH
PHH
PHH
PHH