INSPECTION IS REQUIRED IN STEEL MAKING OR NOT. we propose to supply pipes with Metallic Bevel End Protector and covered with Polythene sheet. Please confirm. Considering time bound delivery requirement and highly volatile steel market we propose validity of 30-45 days from bid due date. SINCE MAINTAINANCE OF DS IS NOT IN BIDDER SCOPE THUS WE PROPOSE THAT 100 PERCENT PAYMENT IN CASE OF COATED PIPE INSTEAD OF BARE AND COATING SHALL BE RELEASED ON RECEIPT OF PIPE AT SITE AS PIPE WILL BE SUPPLIED AFTER DS SEVELOPEMENT ONLY. The delivery period of 10 Weeks for Bare Line Pipe is grossly inadequate. This is because of the Steel manufacturers are quoting a delivery of 9 to 10 weeks on FOB basis considering the 4 weeks for voyage time custom clearance etc. the finished Steel will arrive at our facilities only in about 14 week time. Thereafter we require minimum 3 Week time for Bare pipe manufacturing inspection and dispatch. In view f above you are requested to please allow delivery for Bare Line Pipe as 17 weeks The delivery period of 14 Weeks Coated Pipe is grossly inadequate.As Steel manufacturers are quoting a delivery of 9to10 weeks on FOB basis considering the 4 weeks for voyage time custom clearance etc. the finished Steel will arrive at our facilities only in about 14 week time. Thereafter we require 4 weeks for Curing and minimum 4 Week time for Bare pipe manufacturing Coating inspection and dispatch. please allow delivery for Coated Line Pipe as 22 weeks. We understand for clause Doc No.161080137 Rev. B CL. No. K.6.4is applicable at pipe ends up to a length of 300 mm. However cracks shall not be accepted at the entire weld.
RESPONSE
As per Doc No.161080137 Rev. B CL J.3.2
Steel Making We understand that above underlined requirement shall not be applicable for steel since weld repair is not allowed in steel. However for pipe welding chemical composition we confirm requirement of ASME Sec. 2C. clause plate after trimming of the edges we understand that after trimming of Mill Edges of Steel Plate or coil. However at pipe mill process restriction Plate UT shall be carried out before final bevel profile with extra coverage of client requirement. At least 40mm shall be covered from each side of plate edges instead of requirement i.e. 25mm only. As per Doc No.161080137 Rev. B CL J.5.6 a Imperfections We understand that it should be less than equal to 0.05t but not exceeding 0.7mm Kindly confirm if Manufacturing Procedure Qualification Test shall be applicable for such small quantity requirement i.e. 1476 meter only Please note that we cut out samples from the pipes by using flame cutting keeping a machining allowance of around 5 to10 mm for final machining grinding for sample preparation. Please confirm.