Beruflich Dokumente
Kultur Dokumente
QS/14/37/08
ACKNOWLEDGEMENT
First and foremost I would like to gratefully acknowledge the enthusiastic Building
construction lecturer Mr.S.A.M.HILMY of British College of Applied Studies (BCAS) for
her valuable guidance and advice. She inspired us greatly to work in this project. Her
willingness to motivate us contributed tremendously to this assignment.
I would also like thank the authority of BCAS for providing us with a good environment and
facilities to complete this module. Also, I take this opportunity to thank the Programmed
Manager Mr. Haseeb for offering this subject, Tender Estimation. This gave me a clear
vision of what a Quantity Surveyor must do in future as his job.
Finally, my honorable mention of thanks goes to my family and friends for their
understandings and supports on me in completing this assignment.
Without helps of the particular that I have mentioned above, I would face many difficulties
while doing this assignment.
Thanking you
R.T.Zhahrhan Suzan
(QS/14/37/08)
QS/14/37/08
Introduction
The Building Construction Technology curriculum prepares students with skills to work in
many areas of the construction industries. The program is a unique blend of education and
hands-on training that will allow students to work for builders, general contractors and
subcontractors in residential, industrial and light commercial construction. Students develop
the skills, knowledge and attitudes necessary to function on the construction site with the
potential to advance into supervisory positions within the building industry.
The program provides students with realistic classroom and laboratory experiences
emphasizing, wood frame, steel frame, concrete construction, steel erection, and assembly of
pre-fabricated metal building systems, equipment operation, construction safety, interior
finishing, blueprint reading and job-site responsibilities.
QS/14/37/08
Contents
Column formwork
Slab form work
Reinforcement Task-3 (3.2)
Foundation slab
Column
Beam
Slab (floor)
Brick works .Task-3 (3.3)
Statement of construction of 1st floor concrete slab..... Task-3 (3.4)
Finishing.. Task-3 (3.5)
Water proofing Task-3 (3.6)
Timberworks... Task-3 (3.7)
QS/14/37/08
STRIP FOOTING
SHALLOW
FOUNDATION
SPREAD
FOOTING
FOUNDATION
PAD FOOTING
RAFT
FOUNDATION
COMBINED
FOOTING
FOUNDATION
PILE
FOUNDATION
DEEP
FOUNDATION
CAISSION
FOUNDATION
Shallow foundation
Shallow Foundations support structures at a shallow depth below the ground surface or at a
shallow depth below the deepest basement of a building. There are three main types of
shallow foundations:
Spread footing foundation
Raft or mat foundation
Spread footing foundation
Square or rectangular shaped blocks of reinforced concrete that typically support a single
column or wall of a building. The allowable bearing pressure on the soil determines the size
of the spread footing.
Under the Spread footing category there are 3 types of foundation:
Strip footing foundation
Pad footing foundation
Combined footing foundation
QS/14/37/08
Pad foundations are used to support individual or multiple columns, spreading the
load to the ground below.
They are generally square or rectangular in plan, with the plan area being
determined by the permissible bearing pressure of the soil.
The shape in plan will be dictated by the arrangement of the columns and the load to
be transferred into the soil.
The thickness of the slab must be sufficient to ensure distribution of the load.
The top of the pad may be sloping (i.e. the pad is thicker in the center than it is at the
edge). This is an economic solution, although there may be construction problems
involved with casting the slope.
In simple cases the pad may be constructed from mass concrete.
In general, some reinforcement (either welded steel fabric or reinforcing bars,
depending on the loads involved) will be required in both directions.
For design purposes, the pad is treated as if it were an inverted cantilever carrying the
soil pressure and supported by the column.
QS/14/37/08
A mat or raft foundation is a large slab supporting a number of columns and walls
under the entire structure or a large part of the structure. A mat is required when
the allowable soil pressure is low or where the columns and walls are so close that
individual footings would overlap or nearly touch each other.
Mat foundations are useful in reducing the differential settlements on nonhomogeneous soils or where there is a large variation in the loads on individual
columns.
QS/14/37/08
Raft foundation
Deep foundation
Deep Foundation is transmitting some or all the structural loads to deep soil or rock. Such
foundation often used with larger structures or when shallow soils are poor. Many kind of
deep foundations are available. Mainly two categories are here.
Pile foundation
Caisson foundation
Pile foundation
Piles are relatively long and slender members used to transmit foundation loads through soil
strata of low bearing capacity to deeper soil to rock strata having a high bearing capacity.
They are also used in normal ground conditions to resist heavy uplift forces or in poor soil
condition to resist horizontal loads piles are convenient methods of foundation construction
for works over water such as jetties or bridges piers.
QS/14/37/08
Load transmission
Friction piles
Displacement piles
Displacement piles comprise solid-section piles or hollow section piles with a closed end,
which are driven or forced into the ground and thus displace the soil.
QS/14/37/08
QS/14/37/08
Caisson foundation
Caissons are a deep foundation support that is constructed by placing fresh concrete and
reinforcing steel into a drilled shaft. These reinforced concrete piles are cast in holes of
predetermined diameters and depths drilled through soil and rock to the desired bearing
stratum.
10
QS/14/37/08
The load of the building is most important factor when we selecting foundation to
our constructions.
In our construction site we have to build 5 stories building it mostly less than 20ft,
in this case we need to select the Raft foundation.
The load is movable such as after finished our super market complex which have
lots of furnitures and things etc., etc. so all load comes under the foundation
thats why we need eligible foundation, its should be the raft foundation.
Raft foundation area is large and wider hence the load well distributes all wider
face.
Cost of the foundation:
When we select the foundation we should consider about the cost of the
foundation.
According to our site we have selected the raft foundation that is not much cost
than comparing any other such as pile.
Raft foundation cost less than compare with pile, if we did not selected the raft
foundation another choice which is pile. But pile is most constables than raft
foundation.
Duration:
We should have to complete our construction within very short period in this case
our foundation will be complete in this short and estimate period.
Always Raft foundation build very easier than any other foundation.
It take less duration when compare other types of foundation.
Also we have to complete our project very short period because season weather
will affect the construction so if we use the raft foundation it will reduce our
duration and we can complete our construction within estimate duration.
Distance from the adjacent building:
Near our site there are several buildings such as delmon hospital, bcas campus, etc
etc so if we use pile foundation for our construction neighboring buildings might
have been affected due to vibration.
We can selected the pile foundation, while doing this foundation work this method
using very larger a machinery, so when the time that machine vibrating it has
damaged neither building so we will give the lot of money for solving this
problem so, too we are select raft foundation
Sometimes, soil has been disturbed while our vibration and it may affected to
another building construction in future
But we have selected raft foundation though it may not affect neighboring
buildings and lands.
Also raft foundation havent vibration purposes, so raft foundation is the most
suitable one for our selected site
Water level:
In our site water level is high (4.8m) hence we dont consider about pile
foundation and any other one.
11
QS/14/37/08
If our site having less water level likewise dehiwala site (1.8m) we should have to
consider pile foundation
We dont need to consider about the water level and water will not affect our
excavation though we have selected raft foundation in our site.
Conclusion
If we select pile foundation we should have to do dewatering according to our bore hole
report it will cost more as well as it is very difficult thats the main reason to ignored pile
foundation. In my justification and if we consider all factors, I have select Raft foundation
for my selected site.
Soil strip
excavation
Reduce
level
excavation
Hole or pit
excavation
Excavation
Trench
excavation
Bulk
excavation
12
QS/14/37/08
13
QS/14/37/08
14
QS/14/37/08
Raking shores
Shoring
Horizontal or
flying shores
Vertical or dead
shores
Raking Shores
Raking Shores consist of one or more timbers sloping between the face of the structure to be
supported and the ground. The most effective support is given if the ranker meets the wall at
an angle of 60 to 70 degrees. A wall-plate is typically used to increase the area of support.
15
QS/14/37/08
16
QS/14/37/08
Dewatering
Excavation of foundation trenches in ground having high water table, or in water-logged area
pose great problem because of water oozing in the trench from sides, bringing with it the soil
from the sides. The timbering, if provide would become loose and collapse. Excavation can
be carried out by dewatering the sub-soil water.
Ditches and
sumps
Well point system
Shallow well
system
Dewatering
Vacuum method
Deep well system
Electro-osmosis
method
Conclusion
According to our site bore hole report water level is below than our design level
(4.8m)
In this case there is no need to do dewatering in our selected site regarding our bore
hole report
17
QS/14/37/08
TASK- 2.3
Describe the construction method of selected foundation type stating all the main steps.
When we are to start construction work there are some main steps to do for every
construction. Its should have be done in every kind of construction though in our project also
we should have to following those works for proper construction. Those are:
Site preparation:
After we decided to build a building, we should have to cleaning our site area.
Sometimes construction area have un wanted extra over items such as Grass,
small trees, hills, hillock and bushes etc were removed inside of the land.
In our selected site there are several trees, bushes, and some other kinds of
grasses grown up, so we have to remove all the stuffs before starting
foundation excavation.
Also we need to check the Underground electric or telephone cables as
drainage or water supply lines were through our site area.
Soil investigation:
We have carried out a soil investigation and found out the soil type according
to the borehole test (I have explained clearly in above following task)
18
QS/14/37/08
Bulk Excavating:
After select the Raft foundation we have to excavate the bulk excavation.
Excavate with the machine power such as excavator, JCB, bulldozer etc etc.
19
QS/14/37/08
20
QS/14/37/08
Reinforcement arrangement:
There are so many methods for arranging reinforcement, if we arranged
properly then very easy to do the concreting.
The reinforced steel bars will then be placed into the formwork following the
bending schedule.
The structural engineer has provided all the sketches as a drawing with
arrangements.
Lay the concrete:
After this reinforcement work done the concrete which is mixed to a given
ratio is then poured in and spread all over to cover the reinforcement.
Curing:
After finished our leveling the concrete work we have to curing the concrete
with water.
Curing concrete prevents the concrete from drying too quickly. This is done
by pouring water over the concrete for two weeks.
This process stops the concrete from cracking or becoming too weak when it
dries too fast.
21
QS/14/37/08
Site
preparation
Site
investigation
Select a
suitable type of
foundation
Setting out
Bulk
excavating
Temporary
support for
excavated area
Compacting
bottom of
excavation
Disposal of
excavated
material
Reinforcement
arrangement
Lay the
concrete
Leveling and
vibrating
Curing
Conclusion:
Every works has some standard steps to do the works, also constructing the building
also has some main steps.
If we not maintain and concentrate all the main steps we cannot make our
construction very properly.
There are some procedures to do the raft foundation works, if we did not follow the
all steps exactly we cannot build our foundation works properly.
Thats the main thing we have to follow all the steps of build the foundation of our
super market complex, otherwise all works will collapse due to non-accessibility of
the woks.
There for we must following the methods or steps in the construct of the raft foundation
as well as building.
Suzan Rtz (BCAS Campus)
22
QS/14/37/08
23
QS/14/37/08
24
QS/14/37/08
Plywood Formwork:
Use of plywood instead of timber planks is getting popular these days.
In this case resin bonded plywood sheets are attached to timber frames to make up
panels of required sizes.
The panels thus formed can be easily assembled by bolding in the form of shuttering
This type of shuttering ensures quality surface finish and is specially recommended in
works where large exposed areas of concrete are to be constructed such as floor slab,
faces of retaining walls etc
25
QS/14/37/08
26
QS/14/37/08
Stull
Waler
Post
Thrust-boards
Concrete bottom
Tie wire
Wall Formwork
Wall formwork consists of vertically arranged upright timbers (formwork bearers) to
which sheeting boards are nailed at the concrete side.
The upright timbers are diagonally braced by means of boards at both sides.
On cleats situated at every third upright timber, there are horizontally arranged walers.
The opposite walers are tied at specified distances.
Prefabricated sheeting panels may also be used instead of sheeting boards.
Cleaning holes are to be provided at the foot of the formwork
27
QS/14/37/08
Beam Formwork
In a typical reinforced concrete building frame, the slabs are the primary load carrying
element. They transfer their load to Secondary elements such as walls or beams.
Beams can be grouped in two categories. When located in the interior of the structure
they are usually TEE Beams and when
on the perimeter are L Beams
28
QS/14/37/08
Column Formwork
Similar to beam formworks, the sheeting of column formworks is prefabricated
according to the column dimensions from sheeting boards connected by cover straps.
The sheeting panels are placed in a foot rim which is anchored in the soil by steel
bolts.
The foot rim consists of double-nailed boards.
The foot rim must be exactly measured-in because it is decisive for the exact location
of the column. It has the same functions as the thrust-board for foundation or beam
formwork
29
QS/14/37/08
30
QS/14/37/08
31
QS/14/37/08
For example: with a concrete beam or lintel compression occurs at the top and tension
at the bottom, so the reinforcement is placed about 25mm up from the bottom of the
beam and the ends are often hooked to provide a grip. The 25mm cover prevents
rusting of the reinforcement.
Reinforced concrete elements in a building and their reinforcement arrangements
Generally five major reinforced concrete members in a particular building:
1.
2.
3.
4.
5.
Foundation slab
Column
Beam
Slab (floor)
Stair
Tor steel
6 T 20 - 115
Bar diameter (mm)
Bar mark
Mild steel
Bar mark
- 460 N/sq.mm
250 N/sq.mm
32
QS/14/37/08
Foundation slab
33
QS/14/37/08
34
QS/14/37/08
35
QS/14/37/08
BEAM FB 3:
Reinforcement 30 x 36 4/R10-22-150 it means 4-shrubs, R-mild steel, 10diameter, 22-bar number, and 150-its distance.
BEAM FB 6:
Reinforcement 36 x 40 5/R10-46-250 it means 5-shrubs, R-mild steel, 10diameter, 46-bar number, and 250- its distance.
36
QS/14/37/08
Purchased the steels and other required materials for arrange the reinforcement. They
purchased tor, mild steel and tying wire.
Cover: for covering procedure they considered mainly these following considerations.
Durability of concrete.
To prevent corrosive agents reaching the reinforcement through cracks.
To protect the reinforcement from subsequent loss of strength during a fire.
In covering process, they embedded all the reinforcement bars a certain distance
from surface.
Tying reinforcement: In my site they used wire to tying rebar.
Lap and splices: lap splices are the predominant method of splicing and are the
preferred method for mechanical or welded splices.
A lap is when two pieces of rebar are overlapped to create a continuous line
of rebar. The length of the lap varies depending on the concrete strength, the
rebar grade, size and spacing.
When there is not enough space to do a lap splice, mechanical or welded
splices are often used.
In slab and beam they did the reinforcement on the surface. But for column,
first they arranged separately and embedded in the place.
For preventing the corrosion activity for column reinforcement they applied
cement liquid in the reinforcement.
37
QS/14/37/08
Brick walls
Generally brick are used for partition these can be classified in to two parts
1. Load bearing partition
2. Non-Load bearing partition
Load bearing partition
These are designed construct to require to received superimposed loads and transmit these to
a foundation generally load bearing partitions are constructed of brick or block to external
walls. Block wall partition have the following advantages to brick partition.
Light in weight
Chapter then brick
Quickly to build
Better thermal insulation
Direct fixing
Mud mortar.
lime mortar
cement mortar
lime-cement mortar
cement-lime mortar
38
QS/14/37/08
Bond
Arranging the bricks in courses individual units are together and the vertical joints are good
courses does not lie in same vertical line. Bricks used in masonry are all of uniform
Roles for bonding
39
QS/14/37/08
Ordinary
bricks
Wire cut
bricks
Fire bricks
Types of
bricks
Hollow
bricks
Perforated
bricks
Bricks are basically made out of clay and water. Clay is a plastic earth. Constituents of good
brick clay.
Sand
Silica
Alumina
Lime
Iron
Manganese dioxide
BONDS
English
bond
Flemish
bond
Stretcher
bond
Zigzag
bond
Header
bond
Facing
bond
Dutch
bond
American
bond
40
QS/14/37/08
41
QS/14/37/08
Size, shape
Uniform color
Edges and corners were sharp
Strength
Strength test
42
QS/14/37/08
Brick masonry
External wall thickness 6
Internal wall thickness 4.5
Used cement and sand mortar 1:5
Method of brick work at selected site
1. First of all they did the setting out procedure where should be build the brick work.
2. Bricks were soaked into the clear water before using it. It may be few minutes or
hours. This is one way to remove the dirt and dust.
3. Then bricks were laid in a full bed of mortar and it should be leveled horizontally and
vertically.
For this they used:
Plum bob: This is used to checking the vertical level of brick wall.
Spirit level: This is used for leveling the wall horizontally and
vertically.
Water tube: This is used to determine the correct height of the wall.
43
QS/14/37/08
5. These surfaces were same and outside perpendicular to ground level for plastering
work.
6. The thickness was not exceeding 13 mm in any case.
7. Mortar was provided between two brick. It increases the strength of two bricks.
8. Finally brickwork was kept seven days.
They Used Tor steel for reinforcement and mild steel for links.
The reinforcement is arranged as reinforcement net by using
12mm Tor steel.
44
QS/14/37/08
Check whether the cover blocks are kept in all formworks properly:
Cover blocks are used to maintain a uniform cover thickness.
Main thing is the durability of concrete depends on cover
thickness. Also, cover helps to prevent those corrosive agents
reaching the reinforcement.
Check the formwork of beam and slab, staircase.
Here they checked the Level of slab, any possible to leakage,
thickness of every part and the supporting system.
Fixed the electrical pipes (for wiring purpose) between top and bottom of the
reinforcement.
Proportioning of materials for laying the concrete:
There are some nominal mixes. But, in my site they used grade
25 concrete for the slab.
Mixed the concrete:
Concrete is solid hard material, which consists of cement,
water, and fine aggregate and coarse aggregate. There are two
types of mixing the concrete.
1. Hand mixing
2. Machine mixing
But, they used machine mixing and ready mix concrete.
45
QS/14/37/08
46
QS/14/37/08
Tilling
Tiling is most common type of floor finishing. These tiles are available in different colors,
sizes and, thickness. When we consider about features of tiles, they are:
Strong
Long lasting
Not absorbing water
Easy to clean
Method of tilling
First of all required area will be cleaned. In this process dust and unwanted items will
be removed. Therefore a good & suitable surface can be obtained.
After that bedding mortar will be spread on the concrete bed and allowed to harden.
For bedding mortar, cement: sand will be 1:3 in ratio .Normally this bedding mortar
is spread at the thickness between 12mm-25mm and that will be leveled properly.
47
QS/14/37/08
At corners and edges tiles cannot be laid entirely. Therefore tiles will have to be cut
according to spaces. One kind of tile cutters will be used to cut tiles.
Then grout (cement slurry) will be spread over the mortar and at the back side of tiles
with the help of brushes.
After that tiles will be laid on that mortar. Normally 5mm gaps are left between each
tile according to ISO 9001standard.
When tiles are laid on this mortar and each tile will be lightly tapped to fix properly.
Then cement will come out through joints due to tapping. Therefore that cement will
be wiped and cleaned quickly.
After that tile grout will be placed between gaps of tiles after a day since tiles were
laid and tile grout is selected according to color of tiles.
Here more care is taken to get straight line in joints between tiles.
48
QS/14/37/08
Before laying tiles, they are soaked in clear water. Therefore it will prevent the
absorption of water by tiles from mortar & cement slurry.
Tiling work will be started outwards form center point of the floor. It is done center to
get good appearance. Otherwise parts of tiles may be at center, and then it will not
give good appearance.
Hall
Timber
This timber floor finishing is considered as economical and beautiful and an attractive
method.
This is commonly used in hall especially for dancing halls, carpentry halls,
auditoriums etc. In house also, it is used.
Here much care is taken about prevention of dampness and applied precaution and
skilled laborers are required for this work.
Here also a concrete base is required. In floor finishing, Moisture content anywhere in
a piece must generally be between 9-14% and Boards are generally manufactured to
about 10-12%.
Here Generally 19 mm deep board laid over joists or battens.
BED ROOM
Terrazzo
Terrazzo floor finishing is becoming popular nowadays that is commonly used in
offices, schools, hospitals, residential building, banks etc.
49
QS/14/37/08
But this floor finishing is much applied for bedrooms. For this floor finishing includes
terrazzo, cement mortar and metal strips are used.
This terrazzo is a mixture of cement and marble chips.
This mixture includes marble and cement in the ratio of 1:3. Terrazzo floor finishing
is generally constructed over a concrete base.
Here metal strips are used to control cracking.
OFFICE ROOM
Carpets
Carpets are frequently used as floor covering material.
It is used in residences, offices, and retail stores and generally most suitable for office
room. These carpets are available in much color, patterns and textures and gives
attractive appearance.
Here pads are used under the carpets to improve resilience.
This pad is generally formed by rubber or plastic.
The additional advantage is provided by absorbing minor irregularities in the floor
surface.
Different types of materials are used for this carpet such as wool, acrylic and
polyester
50
QS/14/37/08
Cement plaster
Cement plaster is consists of an intimate mixture of cement and clean coarse sand
with required amount of water. Usual proportions of cement and sand is 1:3 or 1:4.
When cement and sand dries out shrinkage could occur and cracks may appear. The
cracking may appear depends on the strength of the surface and type of plaster.
The normal thickness of the plastering is 12mm-13mm.if the thickness is high, crack
may appear.
51
QS/14/37/08
Gypsum plaster
Gypsum is a chalk like a material and is available is both natural gypsum which is
mined in areas all over the world.
Advantage of this is that they expand very slightly on setting and drying.
Very good then lime and cement, but its not economical.
52
QS/14/37/08
They kept some hollows. Because, for plastering uppermost part of the
building we have to arrange some supporting system.
5) Leveling the wall surface
6) Prepare the mortar for the plastering.
The ratio of the mortar is 1:5
7) After finish these above steps , the wall should be thoroughly washed with water
The walls were thoroughly washed with water by using a bucket and kept
wet before plastering is started.
8) The two plastering equal points were marked
These points were marked by using plumb and long stick.
9) The plastering was done between the points.
This procedure was done from top to bottom.
10) Finally it was leveled.
Trowel and float are used to level this plastering surface.
11) It was left to get dry for 1-2 hours
Painting
Paint is a liquid which spread on a surface in a slim film dries in to a hard tough but
stretch skin.
This skin provides safety and decoration to many building materials. There by
enhancing their appearance made increasing their durability.
Paint provides protection and decoration to the surface. And increase the life time of
structure.
If paint spreads over the iron, it resists the corrosion. And also reduce the decay ness
in timber. Emulsion paint is used internal painting and weather guard is used for
external painting.
53
QS/14/37/08
First the wall surface was cleaned well and made smooth surface.
Then dust and small sand were removed.
If there any crack, it should be filled by using putty.
After water mixed filler was applied to the wall by using brush or spray.
Then it was left few days.
Paint was applied two times to get good appearance.
Finally it was left to get dryness 2-3 hours.
Inodoro
us paints
Graphite
paints
Enamel
paints
Oil
paints
Types of
paints
Aluminu
m paints
Plastic
paints
Silicate
paints
Syntheti
c rubber
paints
54
QS/14/37/08
Conclusion
The importance of plastering a wall, painting and its function is clearly understood.
In my point of view the people in the site could use some more application other than
the ones which they had used so it could be easy for them to handle the work.
So the suggestion for this is the building should be properly plastered and painted for
a long life and for good appearance. And therefore a suitable paint should be selected.
55
QS/14/37/08
56
QS/14/37/08
V. Betonies Waterproofing
It is a betonies clay below-grade foundation waterproofing product which consists of sodium
betonies clay sandwiched between 2 layers of woven and no-woven puncture resistant
polypropylene fabric.
Advantages:
It can absorb tremendous amount of water.
57
QS/14/37/08
And as it takes the water in the clay swells and pushes itself into cracks and voids
where it stays permanently as a barrier against the water.
Non-toxic, non-polluting, and no fumes. It can be applied in cold weather.
Disadvantages:
Because of the way the clay works the seal does not form until the foundation is
backfilled and the water reaches the betonies material, which means you, cannot
confirm the integrity of the seal.
Hot bitumen
Polythene sheets
Suzan Rtz (BCAS Campus)
Mastic asphalt
Metal sheets
Fiber net
58
QS/14/37/08
59
QS/14/37/08
Conclusion
Foundation is the base of a building and it must be laid with accurate measurements
and in accurate ratio.
First the area chosen for the building is excavated and using random rubbles the
foundation is laid.
Setting out is carried out in order to maintain it at horizontal level.
A building construction should include water proofing system so as to prevent the
leaking of water through walls.
Many types of water proofing system and the materials are available and they are used
according to the place where it is to be applied.
Water proofing has to be carried out accordingly in order to be an effective one.
60
QS/14/37/08
Fire safety
Resistance to transfer of heat, sound
Security
Doors type
Panelled doors
Flushed doors
Glazed doors
Match boarded doors
Panelled door and flush door
61
QS/14/37/08
Casement
window
Sliding
folding
window
Compo
site
action
window
Roofs
This uses normally houses, school building etc.
In this case roof element developed by using timber triangular frame work. This easy
joint other parts and roof is some parts use timber these
Ridge piece
It is a timber piece which runs horizontally at the highest level
Common rafter
These are intermediate inclined wooden members laid over purlins from ridge to the
eaves
62
QS/14/37/08
Timber joins
Timber joints are important in fabrication of furniture and wooden or combined structures.
Type of joints
Lengthening joints
Widening joints
Bearing joints
Framing joints
Angle or corner joints
Oblique shouldered joints
Lengthening joints
These are used to lengthening members, there are main four types of lengthening types are
available.
Lapped joints
Fished joints
Scar fed or spliced joints
Tabled joints
Widening joints
There are many joints used to make a wide piece of wood out of small pieces. The commonly
used ones are as follow
Butt joint
63
QS/14/37/08
Rebated joint
Tongued and grooved joint
Dowelled joint
Bearing joints
These joints are used two members that meet at right angle. Commonly used joints under this
group are as follows:
Halved joints
Notched join
Cogged joints
Dovetailed joints
Mortise and tenon joints
Stub-tenon joints
QS/14/37/08
65
QS/14/37/08
Details of joining
When carrying out the joint work, we can use glue and also steel nail or wood pins.
For example, in a mortise tenon work, the contact surfaces are treated with glue
polyvinyl dispersions such as Fevicol) before we put the pieces together.
We also use pin (10mmdiometer of hardwood or bamboo pins) after gloving the
frames together.
The members are position by means of press.
Advantages
Dont need long members.
Stronger structure.
Fabricating any shape.
creating aesthetic and complicated
Dismantling easy to transport.
Disadvantages
66
QS/14/37/08
CONCLUSION
I have visited some sites. Mainly I visited on of wellawatta construction site. As far as my
concerned the site visiting is more important to performing the assignment work and gain the
knowledge and experience. When I find it difficult to remember the technical words, if I
think the duration of my site visiting, then I can remember and understand the technical
words and other difficult section also.
I have learned and understood these following details clearly by some practical procedure and
I have got much knowledge and experience about this subject.
The soil types have been identified and the important of the site investigation has been
understood.
The method of soil investigation has been demonstrated, the soil structure is
represented in a standard format and the borehole test results have been described.
Suitable type of foundation has been described for the building and the reinforcement
method for the selected foundation has been explained with sketches.
The function of the column has been recognized and the reinforcement method has
been explained with sketches.
Different type of slabs has been identified and the reinforcement method for a typical
floor slab has been explained with sketches.
Different brick work method has been identified and the methods of bonding used
have been described sketches.
The materials for the finishing work have been identified for the walls and the
method of finishing work for the wall has been described.
The type of excavation and the need for shoring has been appreciated and method of
excavation and shoring has been described.
The principal and the need of dewatering have been recognized and the method of
dewatering has been identified.
The method statement concrete slab construction has been written.
The waterproofing materials and method of application have been explained with
technical details.
Identified the timber work required for building construction and their associated
connections.
After performed this assignment I am feeling I can become a good quantity surveyor.
67
QS/14/37/08
My visited site
References
Grundy,J,T.(1984) Constructions Technology. Vol 3, 2nd ed., Edward Arnold (puplishers) pty Ltd.
Barry,R.(1980) The Constructions Buildings 1,4th ed., Nothumberland press Ltd.C
Ivor H.Selly (1995) Building constructions.5th ed., Macmillan press Ltd.
Gallwatte,B,S,L,K.(2009) [ no title] . Colombo; BCAS. 12-pages handout on the Importance of site
investigation, , in lecture 3 for module 22188X building construction technology.
Gallwatte,B,S,L,K.(2010) [ openings] . Colombo; BCAS. 12-pages handout on the Doors and Windows,
circulated 25th,feb,2010 in lecture for module 22188X building Construction Technology.
Dr. BC. Punima, ashok kumar jain, arun kumar jain. Reinforced concrete structures Volume
01, 7th edition.
Learning materials in Construction Technology, Department of Quantity Surveying,BCAS
68