Sie sind auf Seite 1von 60

Design of 2 MW Power Plant Using Renewable Energy for LUBELCO Lubang Island, Mindoro

By
Gaspar, Vandrix O.
A Design Project Submitted to Electrical Engineering Department
In Partial Fulfillment of the Required for the Course
Power System Analysis and Design (EEP533L1)

TECHNOLOGICAL INSTITUTE OF THE PHILIPPINES


2016

Acknowledgement
The design project serves as a partial fulfilment for Power Plant Engineering and Design course for
electrical engineering student of the technological Institute of the Philippines. A research-oriented task
that aims to enhance a students knowledge and understanding of the actual design process weve
achieved; we wouldnt be able to accomplish this without those people who helped us for the entire
process.
To Engr. Gerard Francesco DG. Apolinario, our Professor, for he had always time for the consultation
time and all the ideas he had shared with us.
To our family who give us strength and support to finish the project.
And lastly, to our Almighty GOD for the grace, mercy, and compassion.

Table of Contents

Title Page .................................................................................................................................................. i


ii

Aknkowledgement..................................................................................................................................... ii
Table of Contents .................................................................................................................................... iii
List of Figures........................................................................................................................................... iii
List of Tables ............................................................................................................................................v
Chapter 1 Project Background ................................................................................................................ 1
The Project .......................................................................................................................................... 1
Project Objectives ................................................................................................................................ 1
The Client ............................................................................................................................................ 1
Project Scope and Limitation......................................................................................................... 1
Significance of the Project ................................................................................................................... 1
Project Development ........................................................................................................................... 3
Chapter 2 Design Inputs (Technical Specifications) ................................................... 4
Summary ............................................................................................................................................. 4
Scope of the Project ............................................................................................................................ 4
Chapter 3 Project Design ........................................................................................................................ 8
Chapter 4 Design Constraints, Trade-Off and Standards ...................................................................... 25
Design Constraints ............................................................................................................................ 25
Trade-Offs .......................................................................................................................................... 25
Chapter 5 Final Design .......................................................................................................................... 32
Chapter 6 Design Simulation.................................................................................................................. 39
Chapter 7 Conclusion ............................................................................................................................ 48
Reference .............................................................................................................................................. 49
Appendix A ............................................................................................................................................ 50
List of Figures
Figure 1-1 Project Development ............................................................................................................. 3
Figure 2-1 Wave map of Lubang Island (from NREL) and Wave scale (from NREL) ................. 4
Figure 2-2 Distance of Looc Poblacion from the Lubang LPP................................................................. 5
Figure 2-3 Map of Lubang Island .........................................,,,................................................................ 6
Figure 2-4 Single Line Diagram .............................................................................................................. 7
Figure 3-1 Schematic Diagram of Additional Power Plant ...................................................................... 8
Figure 3-2 Single Line Diagram Biomass ............................................................................................. 12
Figure 3-3 Figure 3-3 Pelton Turbine..................................................................................................... 13
Figure 3-4 Figure 3-4 Kaplan Turbine........................................................................................ 18
Figure 3-5 Seagen Horizontal Axis Turbine........................................................................................... 22
Figure 3-6 Vertical Axis Turbine ......................................................................................... 23
Figure 4-1 Graphical Representaion for Efficiency ............................................................................... 27
Figure 4-2 Graphical Representation for Life Span .............................................................................. 28
Figure 4-3 Graphical Representation for Land Area ............................................................................ 29
Figure 4-4 Graphical Representation for Levelized Cost of Energy ......................................................30
Figure 5-1 Single Line Diagram with Additional Wind Power Plant ...................................................... 32
Figure 5-2 Pelton Turbine......................................................................................... 33
iii

Figure 6-1 Single Line diagram Simulation .....................................................................................39


Figure 6-2 Protective Device Coordination ........................................................................................... 47
List of Tables
Table 2-1 Load Forecasting .................................................................................................................... 5
Table 2-2 Forecast (Growth Rate %) ...................................................................................................... 6
Table 2-3 Power Capacity (2015) ........................................................................................................... 6
Table 2-4 Load Feeder (2015) ................................................................................................................ 6
Table 3.1 Power loss in transformer 10
Table 4-1 Efficiency. ............................................................................................................................. 26
Table 4-2 Life Span .............................................................................................................................. 27
Table 4-3 Land Area ............................................................................................................................. 28
Table 4-4 Levelized Cost of Energy ...................................................................................................... 29
Table 4-5 TRADE-OFFS RESULT ........................................................................................................ 30
Table 6-1 Current Loading Violations ................................................................................................... 40
Table 6-2 Bus Voltage Violations .......................................................................................................... 40
Table 6-3 Transformer Violations .......................................................................................................... 40
Table 6-4 Transformer & Line Voltage Regulator Data ......................................................................... 40
Table 6-5 Branch Current Flow Values ................................................................................................. 40
Table 6-6: Bus (A) 3P Fault- Classical Method at 0.5 Cycle .............................................................. 41
Table 6-7: Bus (A) 3P Fault- Classical Method at 1 Cycle ................................................................. 41
Table 6-8: Bus (A) 3P Fault- Classical Method at 3 Cycle ................................................................. 41
Table 6-9: Bus (A) 3P Fault- Classical Method at Std Cycle .............................................................. 42
Table 6-10: Bus (A) LL Fault- Classical Method at 0.5 Cycle ............................................................ 42
Table 6-11: Bus (A) LL Fault- Classical Method at 1 Cycle .............................................................. .42
Table 6-12: Bus (A) LL Fault- Classical Method at 3 Cycle ................................................................43
Table 6-13: Bus (A) LL Fault- Classical Method at Std Cycle ............................................................ 43
Table 6-14: Bus (A) LG Fault- Classical Method at 0.5 Cycle ............................................................ 44
Table 6-15: Bus (A) LG Fault- Classical Method at 1 Cycle ............................................................... 44
Table 6-16: Bus (A) LG Fault- Classical Method at 3 Cycle ............................................................... 44
Table 6-17: Bus (A) LG Fault- Classical Method at Std Cycle ........................................................... 45
Table 6-18: Bus (A) LLG Fault- Classical Method at 0.5 Cycle .......................................................... 45
Table 6-19: Bus (A) LLG Fault- Classical Method at 1 Cycle ............................................................. 45
Table 6-20: Bus (A) LLG Fault- Classical Method at 3 Cycle ............................................................. 46
Table 6-21: Bus (A) LLG Fault- Classical Method at Std Cycle ......................................................... 46

iv

Chapter 1
Project Background
The Project
Electricity has develop and very useful and has changed everyone life since the day it has discovered.
Electricity plays a huge part in peoples everyday lives. Even though power generation existed many
years ago, there are still places in the country that lacks electricity. It is because these places are
beyond the reach of the main grid. Most of these places are islands, just like the Lubang Group of
Island which lies to the northwest of the northern end of Mindoro.
The Lubang Electric Power Cooperative Inc. (LUBELCO), which can ensure relations with Occidental
Mindoro Electric Cooperative (OMECO), distribution supply and achieves power to customers in the
Lubang Isle in Mindoro. The National Power Corporation over Small Power Utility Group, is assigned to
supply power to isolated isles and detached island barangays that stay not linked to certain of the core
grids. The NPC diesel distribution plants are located contradictory to the main office of LUBELCO in
Barangay Bagubag, Vigo, Lubang. NPC consumes 2 arrangements of diesel generator: 500 kW and
650 kW.
For the 2007 the full demand on the organization was nearby 370kW then this would currently be
significantly higher. The rate of electricity in 2009 was P5.89 per kilowatt-hour for housing and P6.2378
kWh for profitable users. The problem is through the increase in charge for diesel fuel, and growing
demand for electricity, different sources of imminent electricity generation are actuality measured.
Project Objectives
The project aims to design a 2 MW generating plant using renewable energy for Lubang Island.
Specifically it address the following:
To cover the insufficient supply of electrical energy in year 2021.
To provide a less expensive electricity to the people of Lubang.
And to utilize the renewable energy that are available in the island.
The Client
The client of the project is Lubang Electric Cooperative, Inc. (LUBELCO).
Project Scope and Limitation
The project covers the generation of electrical power by means of renewable energy, specifically wave.
In wave power plant, the designer only design the generator that will be used in the wave turbine.
Significance of the Project
The electrical power deficiency in Lubang Island can be solved by applying the design project. With the
proper utilization of renewable energy, the nature will benefit as well with the residents of the island. By
using the renewable energy for electricity generation, it will provide substantial benefits to the health
and economy of the residents of Lubang Island. It will also provide clean environment for the residents
and the nature of the island. Using renewable energy will provide less expensive electricity to the
consumers. This is due to the abundant supply of renewable energy, like wave. Wave is well suited to
1

an island because of the availability and infinity of the source. Producing energy from renewable
electricity are practically than relic oils proposals important community health benefits. The greenhouse
gas produced by diesel power plants is linked to inhalation problems, neurological damage, heart
attacks and cancer.
The designers will also be benefitted by the project. As an engineering student, it is a good experience
to solve a real life problem. This will provide the designers a practice to apply all the gathered
knowledge from the very beginning of the electrical engineering program. With this project, the
designers will also be aware to the problems and trends in the world of electricity not only in the country
but the whole world.

Project Development
Start
Identify the
Problem
Data gathering / Technical
Study
Formulation
Design

Wave

Does the design meet


the requirement?

NO

YES
Simulation
Final Design
End
Figure 1-1 Project Development

Chapter 2
Design Inputs (Technical Specifications)
Summary
Lubang, Island is a small group island located near at Occidental Mindoro due to its rich natural
resources and several tourist attractions which caused an imminent increase in demand for electricity.
The load growth is statistically forecasted that resulted to a substantial increase in the peak demand in
the province. The continuous increase of peak demand can provide power shortage in the years to
come. By designing of renewable power plant in the island are possibly the answer for the problem of
the island. If possible, this power plant can solve the problems and theres some benefits not only in
terms of money but in terms of health also.
Scope of the Project
The scope of the project is to design an additional 2 MW power plant, utilizing wind or biomass. To
obtain the approximate capacity of the additional power plant, the power losses from transmission line,
substation, generator feeder, and the generator. In each type of power plant, the designer will only
focus to the part of the power plant that will be used in the tradeoffs. And the winning design in the
tradeoffs will be used for the final design, where it will be simulated in paladin, and analyzed for
additional protection.

Figure 2-1 Wave map of Lubang Island (from NREL) and Wave scale (from NREL)

Figure 2-1 show behavior of wave within the whole Island of Lubang. It is obvious that the common
areas in the Province of Lubang Island experience same wave density.

Figure 2-2 Distance of Looc Poblacion from the Lubang LPP


Figure 2-2 shows the distance of Lubang power plant from the load. The distance is estimated as 40
kilometers.
Power Profile
Main Stakeholders Supplier
Electric Cooperative

-NPC
-Lubang Electric Cooperative, Inc. (LUBELCO)

Table 2-1 Load Forecasting


Year
2015
2016
2017
2018
2019
2020
2021
Forecasted load after 6 years.

Peak Load (MW)


2.304
2.4323
2.5678
2.7108
2.861
3.0212
3.189

Reserve Capacity (MW)


1.4

-1.415

Load Projection in 6 years


Where,
Pm=Peak demand in mth year Po=Peak
demand in the year 2015 g=0.0557
Pm= Po(1+g)m
P6= 2.304 MW*(1+0.0557)6
P6= 2.815 MW

Reserve Capacity in 10 years


P= 1.4 MW-2.815 MW
P6=-1.415 MW
Note: Negative sign indicates insufficient supply
Table 2-2 Forecast (Growth Rate %)
Name of Plant
Lubang Dpp

Peak Demand (KW)


809

Energy Sales (MWH)


3,218

Table 2-3 Power Capacity


(2015)
Name of Plant
Lubang Dpp

Dependable Capacity (MW)


809

Reserved Capacity
3,218

Table 2-4 Load Feeder (2015)


Name of Plant
Vigo
Sorville

Dependable Capacity
295.2
73.8

Reserve Capacity
1.4
1.4

The data inputs shown in the tables above correspond to the existing situation in the power system of
Lubang Island. In the year 2015, the reserve capacity is 1.4 MW. This capacity was calculated through
the dependable capacity and peak demand of the system. The producers dont function at their full
capability all the time; the outputs might differ according to circumstances at the power plant, fuel costs,
and/or as trained from the electric power grid operator.

Figure 2-3 Map of Lubang Island


Figure 2-3 shows the geographical map of Lubang Island.
Lubang DPP, Lubang Island 0.5 MW
24hr of operation - 0.5MW
6

From 12MN-12MN 0.704MW


Lubelco - 0.6MW
Lubang Land Area (in hectares) - 11,310

Figure 2-4 Single Line Diagram


Figure 2-4 shows detailed single line diagram of the whole province of Lubang Island. This was the
basis in studying the whole power system of Lubang Island.

Chapter 3
Project Design Methodology
Methodology
The design project provides solution to the power shortage of the franchise of LUBELCO by providing
additional Power Plant in the island. The researcher will gather data to create the load characteristics of
the system in order to formulate the needed power for the franchise.

Stage 3

Stage 2

Stage 1

Figure 3-1 Schematic Diagram of Additional Power Plant


Figure 3-1 shows the detailed schematic diagram of the additional power plant. The generation part is
connected to a transformer, then to the transmission line with a length of 2 km.

Stage 1: Transmission System


The line current at the secondary side of the transformer
To attain the line current that ill flow on the transmission line from substation to load, this formula will be
used:
P
IL =
3*Vr*pf
Where:
IL = line current (ampere) VR=
receiving voltage at the grid
pf = power factor
P = additional power needed in Lubang Island
2 MW
IL

NEC Section 240-3: General


Requirements for branch circuit,
feeder and other conductors

97.197 A

Conductors are selected such that their ampacities are at least 125% of the continuous current through
the conductor.
As per PEC Part 1, Table
3.10.1.16: Allowable ampacities of
1.25*IL=121.4963A
insulated conductor rated 0
through 2000V.
The impedance of each line
The approximate distance of the power plant to the substation is 2 km. The total impedance of each line
will vary according to the length of the line. See at Appendix C. Note: 2 km = 6561.6798 ft.
0.5218
R=

3.4239 XL

0.8983

0.1369
XC
Z=R+j(XL-XC)=3.4239+j(0.8983-108950.8)=108.95<-89.9982 k
Where:
R = resistance
XL = inductive reactance
XC = capacitive reactance
Z = impedance

Power loss in transmission line


The loss in transmission line is due to the

IEC 60287, Series for calculating


losses for electric cables

Plosses=3IL2RL=3(97.197)2(3.4239)=97.0394 kW
Where:
IL = line current (ampere)
RL = resistance per line (ohm)
Plosses = power loss in the transmission line (watt)
Stage 2: Substation System
Table 3.1 Power loss in transformer
3.12 MVA 690 V/13.2 kV Power Transformer (Y-)
Maximum permissible no load loss at rated
3.0 KW (Maximum)
voltage and rated frequency
Maximum permissible load loss at rated
17.0 KW (Maximum)
current,
According to E5-1-Power Transformer, the maximum power loss of the selected transformer will be 17
kW.
Efficiency of transformer
IEC 60076: Power transformer
measuring
technique
and
accuracy in loss measurement.

Pout
=

*100%
Pout+Plosses
2 MW+97.0394 kW
99.1959%

Line current at the primary side of the transformer


Since it is a step-up transformer, the current at the primary side is high. To obtain the current at the
primary side, turns ration will be used.
VP IS
=

10

VS IP
1.38 kV
3

97.197 A
3
=

As per PEC Part 1, Table


3.10.1.16: Allowable ampacities
of insulated conductor rated 0
through 2000V.

13.2 kV
IP
IP=929.71 A
Where:
V1 = voltage at primary side
V2 = voltage at secondary side
I1 = current at primary side
I2 = current at secondary side
Conductors are selected such that their ampacities are at least 125% of the continuous current through
the conductor.
As per PEC Part 1, Table 3.10:
Allowable ampacities of insulated
1.25*IP=1.1621 kA
conductor.
The impedance of each line
The approximate distance of the power plant to the substation is 30 m. The total impedance of each line
will vary according to the length of the line. See Appendix C Note: 30 m = 98.4252 ft.
0.0170
R=
0.1369
XL
XC
Z=R+j(XL-XC)=1.6732m+j(4.3799m-4.5822M)=4.5822<-90 M
Where:
R = resistance
XL = inductive reactance
XC = capacitive reactance
Z = impedance
Power loss in transmission line
The loss in transmission line is due to the
2
3 2
-3
Plosses=3IL RL=3(1.1621*10 ) (1.6732*10 )=6.7789 kW

IEC 60287, Series for calculating


losses for electric cables

11

Where:
IL = line current (ampere)
RL = resistance per line (ohm)
Plosses = power loss in the transmission line (watt)
The total losses from load up to the feeder
Total Losses=97.0394 kW+17 kW+6.7789 kW=120.8183 kW
Therefore the total capacity of the additional power plant must not
be less than 2 MW+120.8183 kW=2.1208 MW.

IEC 60287, Series for calculating


losses for electric cables

Stage 3: Generation System


Design : Wave Power Plant

Figure 3-2 Single Line Diagram


Figure 3-2 shows the detailed schematic diagram of the wind power plant. The generation part is
connected to a transformer, then to the transmission line with a length of 2 km.

12

Option 1: Point absorber

Figure 3-3 Pelton Turbine


Figure 3-3 shows the construction of the pelton turbine.
Pelton Turbine.
Calculation of turbine input power (Pi)
Pi = r * g * Cn2 *Hn * Qt
Where:
Pi = input power, in watts
r = density, in kg/m3 (r water =1025kg/m3)
g = gravitational constant, 9.81 m/s2
Cn = nozzle discharge coefficient, ~0.98
Hn = net head, in meters
Qt = water flow capacity of each nozzles, in m3/s

Hn = Hg- Htl
13

Where:
Hg = the gross head which is the vertical distance between water surface level at the intake and at the
turbine.
Htl = total head losses due to the open channel, trash rack, intake, penstock and gate or valve.These
losses approximately equal to 6% of gross head
Calculation:
Net head,
Hg=43m
Htl= 2.58m

Water flow capacity of each nozzles,


Ar= 0.03m2
Vr= 18.84m/s

IEC:41-1991 filed acceptance


tests to determine the hydraulic
performance of hydraulic
turbines, storage pumps and
pump-turbines.

Input power,

Calculation of Turbine speed (N)

Where:

14

N = turbine speed, in rpm


Ns = specific speed, in rpm
Hn = net head, in meters
Nj = number of turbine nozzles (jet), as:

Where:
Qt = water flow capacity of each nozzles, in m3/s
Qn = water flow rate, m3/s

IEC:41-1991 filed acceptance tests


to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

specific speed, in rpm

N = turbine speed,
(

pm
number of turbine nozzles (jet),

For Water jet Velocity (Vj):

Where:

15

= Water jet velocity, in m/s


IEC:41-1991 filed acceptance tests
to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

For water jet,

Calculation of nozzle dimensions


Water Flow rate through each nozzles (Qn)
,in m3/s
Where:
The nozzle area (Aj) can be computed as
, in m2
water flow rate :

The nozzle area:

Calculation of maximum turbine efficiency


The output power developed (Po) by the turbine can be computed as:
(

,in watts
16

Then the hydraulic efficiency (hth) can be computed as:


(

= 180

IEC:41-1991 filed acceptance tests


to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

Where:
=bucket roughness coefficient, ~0.98
= deflection angle between bucket and jet, (160 - 170)
Output power,
= 180
=

IEC:41-1991 filed acceptance tests


to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

17

Option 2: Overtopping/Terminator

Figure 3-4 Kaplan Turbine


Figure 3-4 shows the construction of the Kaplan Turbine
Kaplan Turbine
Calculation of turbine input power (Pi)
Pi = r

g H Qt

Where:
Pi = input power, in watts
r = density, in kg/m3 (r water =1025kg/m3)
g = gravitational constant, 9.81 m/s2

H = 25m
Input power,

Calculation of Turbine speed (N)

IEC:41-1991 filed acceptance tests


to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

18

Where:
N = turbine speed, in rpm
Ns = specific speed, in rpm
Hn = net head, in meters
Nj = number of turbine nozzles (jet), as:

Where:
Qt = water flow capacity of each nozzles, in m3/s
Qn = water flow rate, m3/s
specific speed, in rpm

IEC:41-1991 filed acceptance tests


to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

N = turbine speed,

pm
number of turbine nozzles (jet),

For Water jet Velocity (Vj):

19


Where:
= Water jet velocity, in m/s

For water jet,

Calculation of nozzle dimensions


Water Flow rate through each nozzles (Qn)
,in

IEC:41-1991 filed acceptance tests


to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

m3/s

Where:
The nozzle area (Aj) can be computed as:
, in m2
The nozzle area:

water flow rate :

Calculation of maximum turbine efficiency


The output power developed (Po) by the turbine can be computed as:
(

,in watts

20

Then the hydraulic efficiency (hth) can be computed as:


(

= 180
Where:
=bucket roughness coefficient, ~0.98
= deflection angle between bucket and jet, (160 - 170)
Output power,

IEC:41-1991 filed acceptance tests


to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

= 180
=

21

Option 3: Seagen Horizontal Axis Turbine

Figure 3.5 Seagen Horizontal Axis Turbine


Power Input Formula:
1
Pin = a v3 p
2
Power Output Formula:
1
Pout = a v3 p b g in terms of watt electrical power)
2

IEC/TS 62600-200, Section


9.1.2 : Water Density of 1023
kg/m3

Efficiency of the Turbine


Pin Losses
Efficiency=
Pin
Total Efficiency of the System

eceiving Power
Turbine Losses Transmission line and transformer

eceiving Power

Where:
Pin - Power input of the turbine
Pa - Density of water (kg/m3)
A - Area of the wind passing through rotor diameter of the (m2)
v - Velocity of water (m/s)
Cp - Power coefficient (Betz Limit)
- Efficiency

IEC/TS 62600-200 ed 1: Power


performance measurements of
electricity
producing
tidal
turbines
`

Considering one turbine in computing for the efficiency of the system,

22

1
10 2
Pin = 1023 ) ( ) 0.34 3 0.55 = 8 8.43k
2
2
Efficiencygenerator = 0.84 0.97)x100 = 85.09
Efficiency at the generation part= 0.8509 0.92 100 = 78.28
Pout =0.7828 3.47
) 9.8k
2000 k
umber of tidal turbines=
= 2.94 3
679.8
Efficiency of the Turbine
Pin Losses
Efficiency=
Pin
78.28 =

868.43k Losses
868.43k

Losses=193.3k
Total Losses=Losses x no. of turbines
Total Losses=193.3k x 3
Total Losses=773.279k

Option 4: Vertical Axis Turbine

Figure 3.6 Vertical Axis Turbine


Power Input Formula:
1
Pin = 2 a v3 p
Power Output Formula:

IEC/TS 62600-200, Section


9.1.2 : Water Density of
1023 kg/m3

23

Pout =

1
2

v3

p b g

in terms of watt electrical power)

Efficiency of the Turbine


Pin Losses
Efficiency=
Pin
Total Efficiency of the System

eceiving Power
Turbine Losses Transmission line and transformer

eceiving Power

Where:
Pin = power input of the turbine
Pa = density of water (kg/m3)
A = area of the wind passing through rotor diameter of the (m2)
v = velocity of water (m/s)
Cp = power coefficient Betz Limit)

IEC/TS 62600-200 ed 1:
Power
performance
measurements of electricity
producing tidal turbines

Considering one turbine in computing for the efficiency of the system,


1

6 2

Pin = 2 1023
(2) 0.5 3 0.55 = 994.284 k
Efficiencygenerator = 0.84 0.97)x100 = 85.09
Efficiency at the generation part= 0.8509 0.92 100 = 78.28
Pout =0.7828 994.2846 k )= 8.32 k
2000 k
umber of tidal turbines=
= 2.56 3
778.326 k
Efficiency of the Turbine
Pin Losses
Efficiency=
Pin
78.28 =

994.2846 k Losses
994.2846 k

Losses=215.9586 k
Total Losses=Losses x no. of turbines
Total Losses=215.9586k x 3
Total Losses=647.87k

24

Chapter 4
Design Constraints, Trade-offs and Standards
Design Constraints
The design constraints were acquired during the selection of design in order to land with the best
possible proposal without compromising other aspects.
Levelized Cost of Energy
Levelized cost of energy is the main metrics for the charge of energy developed by a generator. Since
generation was the main concern of the project, LCOE was prized meant for evaluation of numerous
generation selections. It is computed by auditing all of a structures estimated lifespan costs, which are
separated by the structures lifetime estimated generated power production (kWh). The investment
capability and demands of the client was took in consideration without having disadvantages to the
design so that in long term, the advantages of the best design will come into realization in terms of cost
saving and profit against initial investments.
Efficiency
The design should attain satisfying efficiency when commissioned as a whole system. The design
should incorporate the least possible losses that a system could possibly achieve. In comparison of
different generation options, the individual efficiency of the designs were taken into consideration so
that there can be a proper selection that can obtain the said objective without compromising much the
other factors considered.
Area
The design should be in suitable size which will compliment with respect to the target location of the
project. The area of the best design must be at the minimum with respect to other criterions.
Life Span
The design should provide a quality service by having acceptable power output. The design should also
be able to withstand long term operations and different environmental conditions with respect to the
area of installation. The degradation of the design must be at the minimum to maximize the usage to
the extent of the economic life of the converting technology.
Trade-Offs
The following table shows the trade-off for each type includes in the design project. Kirkwood and Sarin
quantitative method was used for the trade-off for final design of the project. The following equation will
be used in determining the criterion rank of each design based on the criteria. Equation 4.1 will be used
in determining the lowest importance while Equation 4.2 is for highest importance.

25

Reverse exponential Scoring


-(high-v)
1-e P
Ranking Scoring=
-(high-l0w)
1-e P

(4.1)

Exponential Scoring
-(low-v)
1-e P
Ranking Scoring=

(4.2)

-(low-high)

1-e

Where:
High: the high value
Low: the lowest value
v: the input value
P: the base value
Table 4-1 Efficiency.

Efficiency
Rank Score

Point
absorber

Overtopping/Terminator

Seagen
Horizontal
Axis Turbine

Vertical Axis
Turbine

98.3%

92.27%

78.28%

78.28%

0.6775

Tabulation of the efficiency and rank score of the efficiency of each design.

26

1.2
1

98.3

93.27
%
78.28
%

0.8

78.28
%

0.6
0.4
0.2

0
Point Absorber

Terminator/Overtoppin
g

Vertical
Axis
Turbine

Seagen
Horizontal
Axis
Turbine

Figure 4-1 Graphical Representaion for Efficiency


The two methods of Kirkwood and Sarin were used to analyze the data above. The following formula
were:
-

Ranking Score =
-

- low-v
P
- low-high
P

This formula was used to analyze the Efficiency and the Life Span of all designs since the higher value
is being considered in the designs.
Table 4-2 Life Span

Life Span
Rank Score

Point
absorber

Overtopping/Terminator

Seagen
Horizontal
Axis Turbine

Vertical Axis
Turbine

50yrs

50yrs

20yrs

15yrs

0.1223

Tabulation of the life span and rank score of the efficiency of each design.

27

60
50
1

50

50

04
30
20
20

15

10

0
Point Absorber

Terminator/Overtoppin
g

Vertical
Axis
Turbine

Seagen
Horizontal
Axis
Turbine

Figure 4-2 Graphical Representation for Life Span


The two methods of Kirkwood and Sarin were used to analyze the data above. The following formula
were:
-

Ranking Score =
-

- low-v
P
- low-high
P

This formula was used to analyze the Efficiency and the Life Span of all designs since the higher value
is being considered in the designs.
Table 4-3 Land Area

Land Area
Rank Score

Overtopping/Terminator

Seagen
Horizontal
Axis Turbine

Vertical Axis
Turbine

150m2

185m2

270m2

210m2

0.8194

0.646

Point
absorber

Tabulation of the land area and rank score of the efficiency of each design.

28

270m

300m

210m

250m
200m

185m

150m

150m

100m

50m
1

0m
1

Point Absorber

Terminator/Overtoppin
g

Vertical
Axis
Turbine

Seagen
Horizontal
Axis
Turbine

Figure 4-3 Graphical Representation for Land Area


The two methods of Kirkwood and Sarin were used to analyze the data above. The following formula
were:
-

Ranking Score =
-

- high-v
P
- -high-low
P

This formula was used to analyze the levelized cost of energy and the land area of all designs since the
lowest value is being considered in the designs.
Table 4-4 Levelized Cost of Energy
Point
absorber
LCoE
Rank Score

7.23 wh
0.8804

Overtopping/Terminator

2.2/Kwh
1

Seagen
Horizontal Axis
Turbine

Vertical Axis
Turbine

38.069 wh

11.486 wh

0.7745

Tabulation of levelized cost and rank score of the efficiency of each design

29

38.06
9

40/Kwh

11.04
6

20/Kwr
10/Kwh
8/Kwh

7.23

4/Kw
h

2.2

2/Kw
h
0
Point Absorber

Terminator/Overtoppin
g

Vertical
Axis
Turbine

Seagen
Horizontal
Axis
Turbine

Figure 4-4 Graphical Representation for Levelized Cost of Energy


The two methods of Kirkwood and Sarin were used to analyze the data above. The following formula
were:
-

Ranking Score =
-

- high-v
P
- -high-low
P

This formula was used to analyze the levelized cost of energy and the land area of all designs since the
lowest value is being considered in the designs.
Table 4-5 TRADE-OFFS RESULT

Rank
Criterion
Efficiency
LCoE
Area
Life Span
Rank Score

5
3
2
1

Overtopping/Terminator

Seagen
Horizontal Axis
Turbine

Vertical Axis
Turbine

1
0.8804
1
1

0.6775
1
0.8194
1

0
0
0
0.1223

0
0.7745
0.646
0

10.6412

9.0263

0.1223

3.6155

Point
absorber

30

Table 4.5 shows the ability to satisfy the criterion (Efficiency, LCOE, Area, Manufacturability and Life
Span) that has a scale from 0 to 1. Using the standard analysis of Kirkwood and Sarin, Therefore, the
Point Absorber Option 1) is the final design of the project.

31

Chapter 5
Final Design

Figure 5-1 Single Line Diagram with Additional Wave Power Plant

32

Point absorber

Figure 5-2 Pelton Turbine


Figure 3-3 shows the construction of the pelton turbine.
Pelton Turbine.
Calculation of turbine input power (Pi)
Pi = r * g * Cn2 *Hn * Qt
Where:
Pi = input power, in watts
r = density, in kg/m3 (r water =1025kg/m3)
g = gravitational constant, 9.81 m/s2
Cn = nozzle discharge coefficient, ~0.98
Hn = net head, in meters
Qt = water flow capacity of each nozzles, in m3/s

Hn = Hg- Htl
33

Where:
Hg = the gross head which is the vertical distance between water surface level at the intake and at the
turbine.
Htl = total head losses due to the open channel, trash rack, intake, penstock and gate or valve.These
losses approximately equal to 6% of gross head
Calculation:
Net head,
Hg=43m
Htl= 2.58m

Water flow capacity of each nozzles,


Ar= 0.03m2
Vr= 18.84m/s

IEC:41-1991 filed acceptance


tests to determine the hydraulic
performance of hydraulic
turbines, storage pumps and
pump-turbines.

Input power,

Calculation of Turbine speed (N)

Where:

34

N = turbine speed, in rpm


Ns = specific speed, in rpm
Hn = net head, in meters
Nj = number of turbine nozzles (jet), as:

Where:
Qt = water flow capacity of each nozzles, in m3/s
Qn = water flow rate, m3/s

IEC:41-1991 filed acceptance tests


to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

specific speed, in rpm

N = turbine speed,
(

pm
number of turbine nozzles (jet),

For Water jet Velocity (Vj):

Where:

35

= Water jet velocity, in m/s


IEC:41-1991 filed acceptance tests
to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

For water jet,

Calculation of nozzle dimensions


Water Flow rate through each nozzles (Qn)
,in m3/s
Where:
The nozzle area (Aj) can be computed as
, in m2
water flow rate :

The nozzle area:

IEC:41-1991 filed acceptance tests


to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

Calculation of maximum turbine efficiency


The output power developed (Po) by the turbine can be computed as:
(

,in watts
36

Then the hydraulic efficiency (hth) can be computed as:


(

= 180
Where:
=bucket roughness coefficient, ~0.98
= deflection angle between bucket and jet, (160 - 170)
Output power,
= 180

IEC:41-1991 filed acceptance tests


to determine the hydraulic
performance of hydraulic turbines,
storage pumps and pump-turbines.

Short Circuit Analysis


VBase = 690 kV
SBase = 2.25 MVA
2.25MVA
XG=j72.4105 x
2.25MVA
XG=j72.4105 pu
2.25MVA

IEC Std 551-2006 , IEEE


Recommended Practice for
Calculating Short-Circuit Currents
in Industrial and Commercial
Power Systems

XT1=j18.1026 x
2MVA
37

XT1=j20.3654 pu
108.95<-89.9982 k
XTL=

13.2kV
2.25MVA
XTL=1.4069<-89.9982 pu
Short Circuit Current @ Each Generator

IEC Std 551-2006 , IEEE


Recommended Practice for
Calculating Short-Circuit Currents
in Industrial and Commercial
Power Systems

Xeq

2.25MVA
x
= 129.9994A
Isc j14.4821x3 x 690V
Use 0.13KAIC breaker
=

Short Circuit Current @ Step up Transformer, Primary Side


Xeq= j14.4821
1
2.25MVA
Isc= = = 129.9994A j14.4821 3 x 690V

Use 0.13KAIC breaker


Short Circuit Current @ Step up Transformer, Secondary Side
Xeq= j9.8421
1
2.25MVA
Isc= = = 9.9991A j9.8421
3 x 13.2kV

Use 0.01KAIC breaker


Short Circuit Current @ Transmission Line, Sending End
Xeq= j9.8421
1
2.25MVA
Isc= = = 9.9991A j9.8421
3 x 13.2kV

Use 0.01KAIC breaker


Short Circuit Current @ Transmission Line, Receiving End
Xeq= j9.8556
1
2.25MVA
Isc= = = 9.9854A j9.8556
3 x 13.2kV

Use 0.01KAIC breaker


Chapter 6
38

Design Simulation

Figure 6-1 Single Line diagram Simulation


Figure 6-1 shows the existing single line diagram of the LUBELCO and the additional power plant.

39

Load Flow
Table 6-1 Current Loading Violations
Branch
Name

Type

Over
Lim
(%)

Current Ampacity Loading


(kA)
(kA)
(%)

Under
Lim
Violation
(%)

No Current Violations Found!


Table 6-2 Bus Voltage Violations
Branch Name
Type
Bus
Voltage
Upper Lim
(kV)
(pu)
(%)
No Voltage Violations Found!

Lower Lim
(%)

Table 6-3 Transformer Violations


Library Code Capacity
Loading
Branch Name Library
Name
(MVA)
(MVA)
No Xfr Violations Found!

Over
(%)

Table 6-4 Transformer & Line Voltage Regulator Data


Branch
Library Code
Type
R (%)
Name
Name
18
2-W xfmr
1000-3-L
0.8000
29
2-W xfmr
1000-3-L
0.8000
38
2-W xfmr
1000-3-D
0.8000
Table 6-5 Branch Current Flow Values
Branch
Library
Type
Name
Code Name
19
Breaker
I4T - PH
22
Feeder
900
24
Breaker
MC 600A
30
Breaker
MC 600A
36
Breaker
MC 600A
39
Breaker
I4T - PH
41
Breaker
I4T - PH
HV Breaker
Breaker
MV I4TPH
from looc
Step up
Breaker
MV I4TPH
Trans

Violation
(%)

Under Viol.
(%)

X (%)

F Tap (pu)

T Tap (pu)

5.6900
5.6900
5.6900

1.0000
1.0000
1.0000

1.0000
1.0000
1.0000

Current
(kA)
0.016
0.016
0.016
0.007
0.133
0.439
0.023

Angle (deg)
14.6
14.6
14.6
190.4
160.6
-16.8
13.3

Ampacity
(kA)
0.025
0.019
0.025
0.010
1.140
0.450
0.025

Loading
(%)
65
84
65
69
95
98
93

0.311

-15.4

0.320

97

0.311

-15.4

97
40

18
29
38

2-W xfmr
2-W xfmr
2-W xfmr

1000-3-L
1000-3-L
1000-3-D

0.311
0.007
0.023

-15.4
190.4
24.6

Table 6-6: Bus (A) 3P Fault- Classical Method at 0.5 Cycle

28

Pre-Flt
(V)
13200

Bus Bar

690

220762

19.17

84305 101199

131714

Generator to Poblacion

690

61218

26.91

22881

28792

36777

Looc

690

10059

6.047

4420

3718

5775

19.68

85523 103106

Bus Name

Inst "=""Bus Name


"""
0.5C X/R
1014
5.315

NPC LUBANG D
690
224388
Power Plant
Table 6-7: Bus (A) 3P Fault- Classical Method at 1 Cycle

0.5C
Sym
456

0.5C
DC
357

Bus Name
28

Pre-Flt
( V )
13200

Inst "=""Bus Name


"""
1014

1C
X/R
5.315

1C
Sym
456

Bus Bar

690

220762

19.17

84305

Generator to Poblacion
Looc

690
690

61218
10059

26.91
6.047

22881
4420

8589
9
2562
0
2211

85523

8789
6

NPC LUBANG D
Power Plant

690

224388

19.68

1C
DC
198

0.5C
Asym
579

133959

1C
Asym
497
120358
34350
4942
122637

Table 6-8: Bus (A) 3P Fault- Classical Method at 3 Cycle


Bus Name

Pre-Flt
( V )

Inst "=""Bus Name


"""

3C X/R

3C
Sym

3C DC

3C
Asym

28

13200

1014

5.315

456

19

456

Bus Bar

690

220762

19.17

84305

44590

95371

Generator to Poblacion

690

61218

26.91

22881

16060

27954

Looc

690

10059

6.047

4420

277

4428

NPC LUBANG D
Power Plant

690

224388

19.68

85523

46420

97309

41

Table 6-9: Bus (A) 3P Fault- Classical Method at StdCycle


Bus Name

Pre-Flt
( V )

Inst "=""Bus Name


"""

Std
X/R

Std
Sym

Std
DC

Std
Asym

28

13200

1014

5.315

381

381

Bus Bar

690

220762

19.17

83436

83436

Generator to Poblacion

690

61218

26.91

3866

3866

Looc

690

10059

6.047

4016

4016

NPC LUBANG D
Power Plant

690

224388

19.68

84655

84655

0.5C
Sym
395

0.5C
DC
309

0.5C
Asym
502

Table 6-10: Bus (A) LL Fault- Classical Method at 0.5 Cycle


Pre-Flt
Inst "=""Bus Name
0.5C
Bus Name
( V )
"""
X/R
878
5.315
28
13200
Bus Bar

690

191186

19.17

73010

87641

114068

Generator to Poblacion

690

53016

26.91

19815

24935

31850

Looc

690

8712

6.047

3828

3220

5002

NPC LUBANG D
Power Plant

690

194326

19.68

74065

89292

116012

Table 6-11: Bus (A) LL Fault- Classical Method at 1 Cycle


Pre-Flt
Inst "=""Bus Name
Bus Name
( V )
"""
878
28
13200

5.315

1C
Sym
395

1C X/R

171

1C
Asym
431

1C DC

Bus Bar

690

191186

19.17

73010

74391

104233

Generator to Poblacion

690

53016

26.91

19815

22187

29748

42

Looc

690

NPC LUBANG D
Power Plant

690

Table 6-12

8712

6.047

3828

1915

4280

194326

19.68

74065

76120

106207

LL Fault- Classical Method at 3 Cycle

Bus Name

Pre-Flt
( V )

Inst "=""Bus Name


"""

3C
X/R

3C
Sym

3C DC

3C
Asym

28

13200

878

5.315

395

16

395

Bus Bar

690

191186

19.17

73010

38616

82593

Generator to Poblacion

690

53016

26.91

19815

13908

24209

Looc

690

8712

6.047

3828

240

3835

NPC LUBANG D
Power Plant

690

194326

19.68

74065

40201

84272

Table 6-13: Bus (A) LL Fault- Classical Method at Std Cycle


Bus Name

Pre-Flt
( V )

28

13200

Bus Bar

690

Generator to Poblacion

690

Looc
NPC LUBANG D
Power Plant

690
690

Inst "=""Bus Name


"""
878

Std
X/R

Std
Sym

Std
DC

Std
Asym

5.315

359

359

191186

19.17

72632

72632

53016

26.91

5730

5730

8712

6.047

3644

3644

194326

19.68

73687

73687

43

Table 6-14: Bus (A) LG Fault- Classical Method at 0.5


Cycle
Pre-Flt Inst "=""Bus Name
Bus Name
( V )
"""
1008
28
13200

0.5C
0.5C Sym
X/R
5.315
454

355

0.5C
Asym
576

0.5C DC

Bus Bar

690

219123

19.17

83679

100448

130736

Generator to Poblacion

690

59351

26.91

22183

27914

35655

Looc

690

12102

6.047

5317

4473

6948

NPC LUBANG D
Power Plant

690

222747

19.68

84898

102352

132979

Table 6: Bus (A) -15 LG Fault- Classical Method at 1 Cycle


Pre-Flt
Inst "=""Bus Name
Bus Name
( V )
"""
1008
28
13200

1C
X/R
5.315

1C
Sym
454

1C
DC
197

1C
Asym
494

Bus Bar

690

219123

19.17

83679

85262

119464

Generator to Poblacion

690

59351

26.91

22183

24838

33302

Looc

690

12102

6.047

5317

2661

5946

NPC LUBANG D Power


222747
690
Plant
Table 6-16: Bus (A) LG Fault- Classical Method at 3 Cycle

19.68

84898

87253

121740

Bus Name

Pre-Flt
( V )

Inst "=""Bus Name


"""

3C
X/R

3C
Sym

3C DC

3C
Asym

28

13200

1008

5.315

454

18

454

Bus Bar

690

219123

19.17

83679

44259

94663

Generator to Poblacion

690

59351

26.91

22183

15570

27102

Looc

690

12102

6.047

5317

333

5328

44

NPC LUBANG D Power


222747
690
Plant
Table 6-17: Bus (A) LG Fault- Classical Method at Std
Cycle

19.68

84898

46080

96597

Bus Name

Pre-Flt
( V )

Inst "=""Bus Name


"""

Std
X/R

Std
Sym

Std
DC

Std
Asym

28

13200

1008

5.315

426

426

Bus Bar

690

219123

19.17

83391

83391

Generator to Poblacion

690

59351

26.91

8570

8570

Looc

690

12102

6.047

5111

5111

NPC LUBANG D Power


222747
19.68
690
Plant
Table 6-18
LLG Fault- Classical Method at 0.5 Cycle
Pre-Flt
Inst "=""Bus Name
0.5C
Bus Name
( V )
"""
X/R
1057
5.315
28
13200

84611

84611

0.5C
Sym
476

0.5C
DC
373

0.5C
Asym
604

Bus Bar

690

220126

19.17

84062

100908

131334

Generator to Poblacion

690

60559

26.91

22634

28482

36381

Looc

690

11623

6.047

5107

4296

6673

NPC LUBANG D Power


Plant

690

223753

19.68

85281

102814

133580

Table 6-19: Bus (A) LLG Fault- Classical Method at 1 Cycle


Pre-Flt
Inst "=""Bus Name
Bus Name
( V )
"""
1057
28
13200
Bus Bar
Generator to Poblacion

690
690

1C
X/R
5.315

1C
Sym
476

206

1C
Asym
519

220126

19.17

84062

85652

120011

60559

26.91

22634

25344

33980

1C DC

45

Looc

690

NPC LUBANG D Power


Plant

690

11623

6.047

5107

2555

5710

223753

19.68

85281

87647

122290

Table 6-20: Bus (A) LLG Fault- Classical Method at 3 Cycle


Bus Name

Pre-Flt
( V )

Inst "=""Bus Name


"""

3C
X/R

3C
Sym

3C DC

3C
Asym

28

13200

1057

5.315

476

19

476

Bus Bar

690

220126

19.17

84062

44462

95096

Generator to Poblacion

690

60559

26.91

22634

15887

27653

Looc

690

11623

6.047

5107

320

5117

NPC LUBANG D Power


Plant

690

223753

19.68

85281

46288

97033

Table 6-21

LLG Fault- Classical Method at Std Cycle

Bus Name

Pre-Flt
( V )

Inst "=""Bus Name


"""

Std
X/R

Std
Sym

Std
DC

Std
Asym

28

13200

1057

5.315

420

420

Bus Bar

690

220126

19.17

83484

83484

Generator to Poblacion

690

60559

26.91

5351

5351

Looc

690

11623

6.047

4748

4748

NPC LUBANG D Power


Plant

690

223753

19.68

84704

84704

46

Figure 6-2 Protective Device Coordination


Figure 6-2 shows the protective device coordination (PDC) done in the system. Each device and equipment
was applied by the PDC so that the system will ensure its safety.

47

Chapter 7
Conclusion
After the formulation different designs in wave power plant, engineering constraint were used to
determine the best possible design that will sustain the deficit power in Lubang Island in the next
following years. The constraint are based upon the availability of the resources of renewable energy
and desired characteristics of the client.
After the step by step process, point absorber has won the tradeoff. Also, the project obejectives were
attained by winning the design. First, point absorber can compensate the insufficient supply of electrical
energy in year of 2021. Second, it can provide a less expensive to the people of Lubang Island. Lastly,
it will utilize the renewable energy that is available in the island which is the wind.
Using the paladin software, the system parameters were obtained by checking the full report after
conducting load flow analysis. With the power generation, the 2 MW deficit power in Lubang will be
covered. Satisfying and overcoming the all the problems that will be faced for the following years, this
design project is considered as a success.
Lastly, standards play a vital role in governing the system and processes, such as IEC, IEEE, ANSI, ISO,
etc., and must always incorporate into the design to ensure that the design is safe, efficient and reliable.

48

Reference
From Books:
Kiameh, Philip (2012). Power Generation Handbook. McGraw-Hill Companies, United States of
America Wayne, H. W. (2007). Standard Handbook for Electrical Engineers. McGraw-Hill Incorporated,
United States of America.
Gasch, Robert. Wind Power Plants Fundamentals, Design, Construction and Operation Second Edition.
Gonen, Turan (2008). Electric Power Distribution System Engineering. Taylor and Francis Group LLC,
Florida
Online Sources:
Publications/freepublications/publication/essentials3.pdf
https://www.iea.org/
http://www.nrel.gov/docs/fy11osti/52688.pdf
AmandaCuellar_Thesis_June2012.pdf
https://sequestration.mit.edu/pdf/
Energy Content in Common Energy Sources. (n.d.). Retrieved February 03, 2016, from
http://www.engineeringtoolbox.com/energy-content-d_868.html
Transformer rating, Losses, and Short-circuit Impedance Specifications. (2016, January). Retrieved from
http://www.alibaba.com/product-detail/10-Mva-Amorphous-alloy
oilimmersed_60333898712.html?spm=a2700.7724838.30.1.0kEHfr&s=

49

Appendix A
Calculation of Trade-Offs
Efficiency
Point absorber

Terminator/Overtopping

Efficiency of the Turbine


Pin Losses
Efficiency=
Pin
78.28 =

868.43k Losses
868.43k

Losses=193.3k
Total Losses=Losses x no. of turbines
Total Losses=193.3k x 3
Total Losses=773.279k
Efficiency of the Turbine
Pin Losses
Efficiency=
Pin
78.28 =

994.2846 k Losses
994.2846 k

Losses=215.9586 k
Total Losses=Losses x no. of turbines
Total Losses=215.9586k x 3

50

Total Losses=647.87k
LCOE
Point Absorber
Equipment
Generator
Tidal Turbine
Total

Price
125,213,400
361, 727,600

No. of Pieces
1
1

Total Price
361, 727,600
125,213,400
486,941,000

Operation and Maintenance = 0.3 x Investment Cost


Operation and Maintenance = 0.3 x 486,941,000
Operation and Maintenance = 146,082,300

Cost of Seagen horizontal Axis Turbine


Equipment
Price
Generator
173,752,447
Tidal Turbine
681,333,333
Total

No. of Pieces
3
3

Total Price
521,257,400
2,044,000,000
2,565,257,400

Operation and Maintenance = 0.3 x Investment Cost


Operation and Maintenance = 0.3 x 2,565,257,400
Operation and Maintenance = 769,577,220

51

Vertical Axis Turbine


Equipment
Generator
Tidal Turbine
Total

Price
62,000,000
196,000,000

No. of Pieces
3
3

Total Price
186,000,000
588,000,000
774,000,000

Operation and Maintenance = 0.3 x Investment Cost


Operation and Maintenance = 0.3 x 774,000,000
Operation and Maintenance = 232,200,000

Terminator/Overtopping
Equipment
Generator
Tidal Turbine
Total

Price
33,00,000
117,000,000

No. of Pieces
1
1

Total Price
33,00,000
117,000,000
150,000,000

Operation and Maintenance = 0.3 x Investment Cost


Operation and Maintenance = 0.3 x 150,000,000
Operation and Maintenance = 45,000,000

52

Life Span
Design
Vertical Axis Turbine
Seagen horizontal Axis Turbine
Point Absorber
Terminator/Overtopping

(Yrs)
15
20
50
50

Calculation of Rank Scores:


Ranking Score =
Formula if the high values are preferred.
Ranking Score =
Formula if the low values are preferred.
Efficiency
Formula used for setting the high and low values:
High=98.3%
Low=78.28%
P=preferred value of the client
Ranking Score =
Formula if the high values are preferred.

Point Absorber:
Ranking Score =

- 78.28-98.3
100

- 78.28-98.3
100

Ranking Score = 1
Terminator/Overtopping:
Ranking Score =

- 78.28-92.27
100

- 78.28-98.3
100

53

Ranking Score = 0.6775


Vertical Axis Turbine:
Ranking Score =
Ranking Score =0

- 78.28-78.28
100

- 78.28-98.3
100

Seagen Horizontal Axis Turbine:


Ranking Score =
Ranking Score =0

- 78.28-78.28
100

- 78.28-98.3
100

LCOE:
Formula used for setting the high and low values:
High=38.069
Low=2.2
P=preferred value of the client
Ranking Score =

Point Absorber:
Ranking Score =

- 38.069-7.23)
100

- 38.069-2.2
100

Ranking Score =0.8804


Terminator/Overtopping:
Ranking Score =
Ranking Score =1

- 38.069-2.2)
100

- 38.069-2.2
100

Vertical Axis Turbine:


Ranking Score =

- 38.069-11.486)
100

- 38.069-2.2
100

Ranking Score =0.7745


Seagen Horizontal Axis Turbine:

54

Ranking Score =

- 38.069-38.069)
100

- 38.069-2.2
100

Ranking Score =0

Life Span
Formula used for setting the high and low values:
High=50
Low=15
P=preferred value of the client
Point Absorber:
Ranking Score =
Ranking Score =1

- 15-50
100

- 15-50
100

Terminator/Overtopping:
Ranking Score =
Ranking Score =1

- 15-50
100

- 15-50
100

Vertical Axis Turbine:


Ranking Score =
Ranking Score =0

- 15-15
100

- 15-50
100

Seagen Horizontal Axis Turbine:


Ranking Score =

- 15-20
100

- 15-50
100

Ranking Score =0.1223

Area
Since there is huge discrepancy between the areas of each design, low and high values are
set.
High=270
low=150
P=preferred value of the client
55

Point Absorber:
Ranking Score =
Ranking Score =1

- 270-150
100

- 270-150
100

Terminator/Overtopping:
Ranking Score =

- 270-185
100

- 270-150
100

Ranking Score = 0.8194


Vertical Axis Turbine:
Ranking Score =

- 150-210
100

- 270-150
100

Ranking Score =0.646


Seagen Horizontal Axis Turbine:
Ranking Score =
Ranking Score =0

- 150-270
100

- 270-150
100

56

Das könnte Ihnen auch gefallen