Beruflich Dokumente
Kultur Dokumente
By
Gaspar, Vandrix O.
A Design Project Submitted to Electrical Engineering Department
In Partial Fulfillment of the Required for the Course
Power System Analysis and Design (EEP533L1)
Acknowledgement
The design project serves as a partial fulfilment for Power Plant Engineering and Design course for
electrical engineering student of the technological Institute of the Philippines. A research-oriented task
that aims to enhance a students knowledge and understanding of the actual design process weve
achieved; we wouldnt be able to accomplish this without those people who helped us for the entire
process.
To Engr. Gerard Francesco DG. Apolinario, our Professor, for he had always time for the consultation
time and all the ideas he had shared with us.
To our family who give us strength and support to finish the project.
And lastly, to our Almighty GOD for the grace, mercy, and compassion.
Table of Contents
Aknkowledgement..................................................................................................................................... ii
Table of Contents .................................................................................................................................... iii
List of Figures........................................................................................................................................... iii
List of Tables ............................................................................................................................................v
Chapter 1 Project Background ................................................................................................................ 1
The Project .......................................................................................................................................... 1
Project Objectives ................................................................................................................................ 1
The Client ............................................................................................................................................ 1
Project Scope and Limitation......................................................................................................... 1
Significance of the Project ................................................................................................................... 1
Project Development ........................................................................................................................... 3
Chapter 2 Design Inputs (Technical Specifications) ................................................... 4
Summary ............................................................................................................................................. 4
Scope of the Project ............................................................................................................................ 4
Chapter 3 Project Design ........................................................................................................................ 8
Chapter 4 Design Constraints, Trade-Off and Standards ...................................................................... 25
Design Constraints ............................................................................................................................ 25
Trade-Offs .......................................................................................................................................... 25
Chapter 5 Final Design .......................................................................................................................... 32
Chapter 6 Design Simulation.................................................................................................................. 39
Chapter 7 Conclusion ............................................................................................................................ 48
Reference .............................................................................................................................................. 49
Appendix A ............................................................................................................................................ 50
List of Figures
Figure 1-1 Project Development ............................................................................................................. 3
Figure 2-1 Wave map of Lubang Island (from NREL) and Wave scale (from NREL) ................. 4
Figure 2-2 Distance of Looc Poblacion from the Lubang LPP................................................................. 5
Figure 2-3 Map of Lubang Island .........................................,,,................................................................ 6
Figure 2-4 Single Line Diagram .............................................................................................................. 7
Figure 3-1 Schematic Diagram of Additional Power Plant ...................................................................... 8
Figure 3-2 Single Line Diagram Biomass ............................................................................................. 12
Figure 3-3 Figure 3-3 Pelton Turbine..................................................................................................... 13
Figure 3-4 Figure 3-4 Kaplan Turbine........................................................................................ 18
Figure 3-5 Seagen Horizontal Axis Turbine........................................................................................... 22
Figure 3-6 Vertical Axis Turbine ......................................................................................... 23
Figure 4-1 Graphical Representaion for Efficiency ............................................................................... 27
Figure 4-2 Graphical Representation for Life Span .............................................................................. 28
Figure 4-3 Graphical Representation for Land Area ............................................................................ 29
Figure 4-4 Graphical Representation for Levelized Cost of Energy ......................................................30
Figure 5-1 Single Line Diagram with Additional Wind Power Plant ...................................................... 32
Figure 5-2 Pelton Turbine......................................................................................... 33
iii
iv
Chapter 1
Project Background
The Project
Electricity has develop and very useful and has changed everyone life since the day it has discovered.
Electricity plays a huge part in peoples everyday lives. Even though power generation existed many
years ago, there are still places in the country that lacks electricity. It is because these places are
beyond the reach of the main grid. Most of these places are islands, just like the Lubang Group of
Island which lies to the northwest of the northern end of Mindoro.
The Lubang Electric Power Cooperative Inc. (LUBELCO), which can ensure relations with Occidental
Mindoro Electric Cooperative (OMECO), distribution supply and achieves power to customers in the
Lubang Isle in Mindoro. The National Power Corporation over Small Power Utility Group, is assigned to
supply power to isolated isles and detached island barangays that stay not linked to certain of the core
grids. The NPC diesel distribution plants are located contradictory to the main office of LUBELCO in
Barangay Bagubag, Vigo, Lubang. NPC consumes 2 arrangements of diesel generator: 500 kW and
650 kW.
For the 2007 the full demand on the organization was nearby 370kW then this would currently be
significantly higher. The rate of electricity in 2009 was P5.89 per kilowatt-hour for housing and P6.2378
kWh for profitable users. The problem is through the increase in charge for diesel fuel, and growing
demand for electricity, different sources of imminent electricity generation are actuality measured.
Project Objectives
The project aims to design a 2 MW generating plant using renewable energy for Lubang Island.
Specifically it address the following:
To cover the insufficient supply of electrical energy in year 2021.
To provide a less expensive electricity to the people of Lubang.
And to utilize the renewable energy that are available in the island.
The Client
The client of the project is Lubang Electric Cooperative, Inc. (LUBELCO).
Project Scope and Limitation
The project covers the generation of electrical power by means of renewable energy, specifically wave.
In wave power plant, the designer only design the generator that will be used in the wave turbine.
Significance of the Project
The electrical power deficiency in Lubang Island can be solved by applying the design project. With the
proper utilization of renewable energy, the nature will benefit as well with the residents of the island. By
using the renewable energy for electricity generation, it will provide substantial benefits to the health
and economy of the residents of Lubang Island. It will also provide clean environment for the residents
and the nature of the island. Using renewable energy will provide less expensive electricity to the
consumers. This is due to the abundant supply of renewable energy, like wave. Wave is well suited to
1
an island because of the availability and infinity of the source. Producing energy from renewable
electricity are practically than relic oils proposals important community health benefits. The greenhouse
gas produced by diesel power plants is linked to inhalation problems, neurological damage, heart
attacks and cancer.
The designers will also be benefitted by the project. As an engineering student, it is a good experience
to solve a real life problem. This will provide the designers a practice to apply all the gathered
knowledge from the very beginning of the electrical engineering program. With this project, the
designers will also be aware to the problems and trends in the world of electricity not only in the country
but the whole world.
Project Development
Start
Identify the
Problem
Data gathering / Technical
Study
Formulation
Design
Wave
NO
YES
Simulation
Final Design
End
Figure 1-1 Project Development
Chapter 2
Design Inputs (Technical Specifications)
Summary
Lubang, Island is a small group island located near at Occidental Mindoro due to its rich natural
resources and several tourist attractions which caused an imminent increase in demand for electricity.
The load growth is statistically forecasted that resulted to a substantial increase in the peak demand in
the province. The continuous increase of peak demand can provide power shortage in the years to
come. By designing of renewable power plant in the island are possibly the answer for the problem of
the island. If possible, this power plant can solve the problems and theres some benefits not only in
terms of money but in terms of health also.
Scope of the Project
The scope of the project is to design an additional 2 MW power plant, utilizing wind or biomass. To
obtain the approximate capacity of the additional power plant, the power losses from transmission line,
substation, generator feeder, and the generator. In each type of power plant, the designer will only
focus to the part of the power plant that will be used in the tradeoffs. And the winning design in the
tradeoffs will be used for the final design, where it will be simulated in paladin, and analyzed for
additional protection.
Figure 2-1 Wave map of Lubang Island (from NREL) and Wave scale (from NREL)
Figure 2-1 show behavior of wave within the whole Island of Lubang. It is obvious that the common
areas in the Province of Lubang Island experience same wave density.
-NPC
-Lubang Electric Cooperative, Inc. (LUBELCO)
-1.415
Reserved Capacity
3,218
Dependable Capacity
295.2
73.8
Reserve Capacity
1.4
1.4
The data inputs shown in the tables above correspond to the existing situation in the power system of
Lubang Island. In the year 2015, the reserve capacity is 1.4 MW. This capacity was calculated through
the dependable capacity and peak demand of the system. The producers dont function at their full
capability all the time; the outputs might differ according to circumstances at the power plant, fuel costs,
and/or as trained from the electric power grid operator.
Chapter 3
Project Design Methodology
Methodology
The design project provides solution to the power shortage of the franchise of LUBELCO by providing
additional Power Plant in the island. The researcher will gather data to create the load characteristics of
the system in order to formulate the needed power for the franchise.
Stage 3
Stage 2
Stage 1
97.197 A
Conductors are selected such that their ampacities are at least 125% of the continuous current through
the conductor.
As per PEC Part 1, Table
3.10.1.16: Allowable ampacities of
1.25*IL=121.4963A
insulated conductor rated 0
through 2000V.
The impedance of each line
The approximate distance of the power plant to the substation is 2 km. The total impedance of each line
will vary according to the length of the line. See at Appendix C. Note: 2 km = 6561.6798 ft.
0.5218
R=
3.4239 XL
0.8983
0.1369
XC
Z=R+j(XL-XC)=3.4239+j(0.8983-108950.8)=108.95<-89.9982 k
Where:
R = resistance
XL = inductive reactance
XC = capacitive reactance
Z = impedance
Plosses=3IL2RL=3(97.197)2(3.4239)=97.0394 kW
Where:
IL = line current (ampere)
RL = resistance per line (ohm)
Plosses = power loss in the transmission line (watt)
Stage 2: Substation System
Table 3.1 Power loss in transformer
3.12 MVA 690 V/13.2 kV Power Transformer (Y-)
Maximum permissible no load loss at rated
3.0 KW (Maximum)
voltage and rated frequency
Maximum permissible load loss at rated
17.0 KW (Maximum)
current,
According to E5-1-Power Transformer, the maximum power loss of the selected transformer will be 17
kW.
Efficiency of transformer
IEC 60076: Power transformer
measuring
technique
and
accuracy in loss measurement.
Pout
=
*100%
Pout+Plosses
2 MW+97.0394 kW
99.1959%
10
VS IP
1.38 kV
3
97.197 A
3
=
13.2 kV
IP
IP=929.71 A
Where:
V1 = voltage at primary side
V2 = voltage at secondary side
I1 = current at primary side
I2 = current at secondary side
Conductors are selected such that their ampacities are at least 125% of the continuous current through
the conductor.
As per PEC Part 1, Table 3.10:
Allowable ampacities of insulated
1.25*IP=1.1621 kA
conductor.
The impedance of each line
The approximate distance of the power plant to the substation is 30 m. The total impedance of each line
will vary according to the length of the line. See Appendix C Note: 30 m = 98.4252 ft.
0.0170
R=
0.1369
XL
XC
Z=R+j(XL-XC)=1.6732m+j(4.3799m-4.5822M)=4.5822<-90 M
Where:
R = resistance
XL = inductive reactance
XC = capacitive reactance
Z = impedance
Power loss in transmission line
The loss in transmission line is due to the
2
3 2
-3
Plosses=3IL RL=3(1.1621*10 ) (1.6732*10 )=6.7789 kW
11
Where:
IL = line current (ampere)
RL = resistance per line (ohm)
Plosses = power loss in the transmission line (watt)
The total losses from load up to the feeder
Total Losses=97.0394 kW+17 kW+6.7789 kW=120.8183 kW
Therefore the total capacity of the additional power plant must not
be less than 2 MW+120.8183 kW=2.1208 MW.
12
Hn = Hg- Htl
13
Where:
Hg = the gross head which is the vertical distance between water surface level at the intake and at the
turbine.
Htl = total head losses due to the open channel, trash rack, intake, penstock and gate or valve.These
losses approximately equal to 6% of gross head
Calculation:
Net head,
Hg=43m
Htl= 2.58m
Input power,
Where:
14
Where:
Qt = water flow capacity of each nozzles, in m3/s
Qn = water flow rate, m3/s
N = turbine speed,
(
pm
number of turbine nozzles (jet),
Where:
15
,in watts
16
= 180
Where:
=bucket roughness coefficient, ~0.98
= deflection angle between bucket and jet, (160 - 170)
Output power,
= 180
=
17
Option 2: Overtopping/Terminator
g H Qt
Where:
Pi = input power, in watts
r = density, in kg/m3 (r water =1025kg/m3)
g = gravitational constant, 9.81 m/s2
H = 25m
Input power,
18
Where:
N = turbine speed, in rpm
Ns = specific speed, in rpm
Hn = net head, in meters
Nj = number of turbine nozzles (jet), as:
Where:
Qt = water flow capacity of each nozzles, in m3/s
Qn = water flow rate, m3/s
specific speed, in rpm
N = turbine speed,
pm
number of turbine nozzles (jet),
19
Where:
= Water jet velocity, in m/s
m3/s
Where:
The nozzle area (Aj) can be computed as:
, in m2
The nozzle area:
,in watts
20
= 180
Where:
=bucket roughness coefficient, ~0.98
= deflection angle between bucket and jet, (160 - 170)
Output power,
= 180
=
21
eceiving Power
Turbine Losses Transmission line and transformer
eceiving Power
Where:
Pin - Power input of the turbine
Pa - Density of water (kg/m3)
A - Area of the wind passing through rotor diameter of the (m2)
v - Velocity of water (m/s)
Cp - Power coefficient (Betz Limit)
- Efficiency
22
1
10 2
Pin = 1023 ) ( ) 0.34 3 0.55 = 8 8.43k
2
2
Efficiencygenerator = 0.84 0.97)x100 = 85.09
Efficiency at the generation part= 0.8509 0.92 100 = 78.28
Pout =0.7828 3.47
) 9.8k
2000 k
umber of tidal turbines=
= 2.94 3
679.8
Efficiency of the Turbine
Pin Losses
Efficiency=
Pin
78.28 =
868.43k Losses
868.43k
Losses=193.3k
Total Losses=Losses x no. of turbines
Total Losses=193.3k x 3
Total Losses=773.279k
23
Pout =
1
2
v3
p b g
eceiving Power
Turbine Losses Transmission line and transformer
eceiving Power
Where:
Pin = power input of the turbine
Pa = density of water (kg/m3)
A = area of the wind passing through rotor diameter of the (m2)
v = velocity of water (m/s)
Cp = power coefficient Betz Limit)
IEC/TS 62600-200 ed 1:
Power
performance
measurements of electricity
producing tidal turbines
6 2
Pin = 2 1023
(2) 0.5 3 0.55 = 994.284 k
Efficiencygenerator = 0.84 0.97)x100 = 85.09
Efficiency at the generation part= 0.8509 0.92 100 = 78.28
Pout =0.7828 994.2846 k )= 8.32 k
2000 k
umber of tidal turbines=
= 2.56 3
778.326 k
Efficiency of the Turbine
Pin Losses
Efficiency=
Pin
78.28 =
994.2846 k Losses
994.2846 k
Losses=215.9586 k
Total Losses=Losses x no. of turbines
Total Losses=215.9586k x 3
Total Losses=647.87k
24
Chapter 4
Design Constraints, Trade-offs and Standards
Design Constraints
The design constraints were acquired during the selection of design in order to land with the best
possible proposal without compromising other aspects.
Levelized Cost of Energy
Levelized cost of energy is the main metrics for the charge of energy developed by a generator. Since
generation was the main concern of the project, LCOE was prized meant for evaluation of numerous
generation selections. It is computed by auditing all of a structures estimated lifespan costs, which are
separated by the structures lifetime estimated generated power production (kWh). The investment
capability and demands of the client was took in consideration without having disadvantages to the
design so that in long term, the advantages of the best design will come into realization in terms of cost
saving and profit against initial investments.
Efficiency
The design should attain satisfying efficiency when commissioned as a whole system. The design
should incorporate the least possible losses that a system could possibly achieve. In comparison of
different generation options, the individual efficiency of the designs were taken into consideration so
that there can be a proper selection that can obtain the said objective without compromising much the
other factors considered.
Area
The design should be in suitable size which will compliment with respect to the target location of the
project. The area of the best design must be at the minimum with respect to other criterions.
Life Span
The design should provide a quality service by having acceptable power output. The design should also
be able to withstand long term operations and different environmental conditions with respect to the
area of installation. The degradation of the design must be at the minimum to maximize the usage to
the extent of the economic life of the converting technology.
Trade-Offs
The following table shows the trade-off for each type includes in the design project. Kirkwood and Sarin
quantitative method was used for the trade-off for final design of the project. The following equation will
be used in determining the criterion rank of each design based on the criteria. Equation 4.1 will be used
in determining the lowest importance while Equation 4.2 is for highest importance.
25
(4.1)
Exponential Scoring
-(low-v)
1-e P
Ranking Scoring=
(4.2)
-(low-high)
1-e
Where:
High: the high value
Low: the lowest value
v: the input value
P: the base value
Table 4-1 Efficiency.
Efficiency
Rank Score
Point
absorber
Overtopping/Terminator
Seagen
Horizontal
Axis Turbine
Vertical Axis
Turbine
98.3%
92.27%
78.28%
78.28%
0.6775
Tabulation of the efficiency and rank score of the efficiency of each design.
26
1.2
1
98.3
93.27
%
78.28
%
0.8
78.28
%
0.6
0.4
0.2
0
Point Absorber
Terminator/Overtoppin
g
Vertical
Axis
Turbine
Seagen
Horizontal
Axis
Turbine
Ranking Score =
-
- low-v
P
- low-high
P
This formula was used to analyze the Efficiency and the Life Span of all designs since the higher value
is being considered in the designs.
Table 4-2 Life Span
Life Span
Rank Score
Point
absorber
Overtopping/Terminator
Seagen
Horizontal
Axis Turbine
Vertical Axis
Turbine
50yrs
50yrs
20yrs
15yrs
0.1223
Tabulation of the life span and rank score of the efficiency of each design.
27
60
50
1
50
50
04
30
20
20
15
10
0
Point Absorber
Terminator/Overtoppin
g
Vertical
Axis
Turbine
Seagen
Horizontal
Axis
Turbine
Ranking Score =
-
- low-v
P
- low-high
P
This formula was used to analyze the Efficiency and the Life Span of all designs since the higher value
is being considered in the designs.
Table 4-3 Land Area
Land Area
Rank Score
Overtopping/Terminator
Seagen
Horizontal
Axis Turbine
Vertical Axis
Turbine
150m2
185m2
270m2
210m2
0.8194
0.646
Point
absorber
Tabulation of the land area and rank score of the efficiency of each design.
28
270m
300m
210m
250m
200m
185m
150m
150m
100m
50m
1
0m
1
Point Absorber
Terminator/Overtoppin
g
Vertical
Axis
Turbine
Seagen
Horizontal
Axis
Turbine
Ranking Score =
-
- high-v
P
- -high-low
P
This formula was used to analyze the levelized cost of energy and the land area of all designs since the
lowest value is being considered in the designs.
Table 4-4 Levelized Cost of Energy
Point
absorber
LCoE
Rank Score
7.23 wh
0.8804
Overtopping/Terminator
2.2/Kwh
1
Seagen
Horizontal Axis
Turbine
Vertical Axis
Turbine
38.069 wh
11.486 wh
0.7745
Tabulation of levelized cost and rank score of the efficiency of each design
29
38.06
9
40/Kwh
11.04
6
20/Kwr
10/Kwh
8/Kwh
7.23
4/Kw
h
2.2
2/Kw
h
0
Point Absorber
Terminator/Overtoppin
g
Vertical
Axis
Turbine
Seagen
Horizontal
Axis
Turbine
Ranking Score =
-
- high-v
P
- -high-low
P
This formula was used to analyze the levelized cost of energy and the land area of all designs since the
lowest value is being considered in the designs.
Table 4-5 TRADE-OFFS RESULT
Rank
Criterion
Efficiency
LCoE
Area
Life Span
Rank Score
5
3
2
1
Overtopping/Terminator
Seagen
Horizontal Axis
Turbine
Vertical Axis
Turbine
1
0.8804
1
1
0.6775
1
0.8194
1
0
0
0
0.1223
0
0.7745
0.646
0
10.6412
9.0263
0.1223
3.6155
Point
absorber
30
Table 4.5 shows the ability to satisfy the criterion (Efficiency, LCOE, Area, Manufacturability and Life
Span) that has a scale from 0 to 1. Using the standard analysis of Kirkwood and Sarin, Therefore, the
Point Absorber Option 1) is the final design of the project.
31
Chapter 5
Final Design
Figure 5-1 Single Line Diagram with Additional Wave Power Plant
32
Point absorber
Hn = Hg- Htl
33
Where:
Hg = the gross head which is the vertical distance between water surface level at the intake and at the
turbine.
Htl = total head losses due to the open channel, trash rack, intake, penstock and gate or valve.These
losses approximately equal to 6% of gross head
Calculation:
Net head,
Hg=43m
Htl= 2.58m
Input power,
Where:
34
Where:
Qt = water flow capacity of each nozzles, in m3/s
Qn = water flow rate, m3/s
N = turbine speed,
(
pm
number of turbine nozzles (jet),
Where:
35
,in watts
36
= 180
Where:
=bucket roughness coefficient, ~0.98
= deflection angle between bucket and jet, (160 - 170)
Output power,
= 180
XT1=j18.1026 x
2MVA
37
XT1=j20.3654 pu
108.95<-89.9982 k
XTL=
13.2kV
2.25MVA
XTL=1.4069<-89.9982 pu
Short Circuit Current @ Each Generator
Xeq
2.25MVA
x
= 129.9994A
Isc j14.4821x3 x 690V
Use 0.13KAIC breaker
=
Design Simulation
39
Load Flow
Table 6-1 Current Loading Violations
Branch
Name
Type
Over
Lim
(%)
Under
Lim
Violation
(%)
Lower Lim
(%)
Over
(%)
Violation
(%)
Under Viol.
(%)
X (%)
F Tap (pu)
T Tap (pu)
5.6900
5.6900
5.6900
1.0000
1.0000
1.0000
1.0000
1.0000
1.0000
Current
(kA)
0.016
0.016
0.016
0.007
0.133
0.439
0.023
Angle (deg)
14.6
14.6
14.6
190.4
160.6
-16.8
13.3
Ampacity
(kA)
0.025
0.019
0.025
0.010
1.140
0.450
0.025
Loading
(%)
65
84
65
69
95
98
93
0.311
-15.4
0.320
97
0.311
-15.4
97
40
18
29
38
2-W xfmr
2-W xfmr
2-W xfmr
1000-3-L
1000-3-L
1000-3-D
0.311
0.007
0.023
-15.4
190.4
24.6
28
Pre-Flt
(V)
13200
Bus Bar
690
220762
19.17
84305 101199
131714
Generator to Poblacion
690
61218
26.91
22881
28792
36777
Looc
690
10059
6.047
4420
3718
5775
19.68
85523 103106
Bus Name
NPC LUBANG D
690
224388
Power Plant
Table 6-7: Bus (A) 3P Fault- Classical Method at 1 Cycle
0.5C
Sym
456
0.5C
DC
357
Bus Name
28
Pre-Flt
( V )
13200
1C
X/R
5.315
1C
Sym
456
Bus Bar
690
220762
19.17
84305
Generator to Poblacion
Looc
690
690
61218
10059
26.91
6.047
22881
4420
8589
9
2562
0
2211
85523
8789
6
NPC LUBANG D
Power Plant
690
224388
19.68
1C
DC
198
0.5C
Asym
579
133959
1C
Asym
497
120358
34350
4942
122637
Pre-Flt
( V )
3C X/R
3C
Sym
3C DC
3C
Asym
28
13200
1014
5.315
456
19
456
Bus Bar
690
220762
19.17
84305
44590
95371
Generator to Poblacion
690
61218
26.91
22881
16060
27954
Looc
690
10059
6.047
4420
277
4428
NPC LUBANG D
Power Plant
690
224388
19.68
85523
46420
97309
41
Pre-Flt
( V )
Std
X/R
Std
Sym
Std
DC
Std
Asym
28
13200
1014
5.315
381
381
Bus Bar
690
220762
19.17
83436
83436
Generator to Poblacion
690
61218
26.91
3866
3866
Looc
690
10059
6.047
4016
4016
NPC LUBANG D
Power Plant
690
224388
19.68
84655
84655
0.5C
Sym
395
0.5C
DC
309
0.5C
Asym
502
690
191186
19.17
73010
87641
114068
Generator to Poblacion
690
53016
26.91
19815
24935
31850
Looc
690
8712
6.047
3828
3220
5002
NPC LUBANG D
Power Plant
690
194326
19.68
74065
89292
116012
5.315
1C
Sym
395
1C X/R
171
1C
Asym
431
1C DC
Bus Bar
690
191186
19.17
73010
74391
104233
Generator to Poblacion
690
53016
26.91
19815
22187
29748
42
Looc
690
NPC LUBANG D
Power Plant
690
Table 6-12
8712
6.047
3828
1915
4280
194326
19.68
74065
76120
106207
Bus Name
Pre-Flt
( V )
3C
X/R
3C
Sym
3C DC
3C
Asym
28
13200
878
5.315
395
16
395
Bus Bar
690
191186
19.17
73010
38616
82593
Generator to Poblacion
690
53016
26.91
19815
13908
24209
Looc
690
8712
6.047
3828
240
3835
NPC LUBANG D
Power Plant
690
194326
19.68
74065
40201
84272
Pre-Flt
( V )
28
13200
Bus Bar
690
Generator to Poblacion
690
Looc
NPC LUBANG D
Power Plant
690
690
Std
X/R
Std
Sym
Std
DC
Std
Asym
5.315
359
359
191186
19.17
72632
72632
53016
26.91
5730
5730
8712
6.047
3644
3644
194326
19.68
73687
73687
43
0.5C
0.5C Sym
X/R
5.315
454
355
0.5C
Asym
576
0.5C DC
Bus Bar
690
219123
19.17
83679
100448
130736
Generator to Poblacion
690
59351
26.91
22183
27914
35655
Looc
690
12102
6.047
5317
4473
6948
NPC LUBANG D
Power Plant
690
222747
19.68
84898
102352
132979
1C
X/R
5.315
1C
Sym
454
1C
DC
197
1C
Asym
494
Bus Bar
690
219123
19.17
83679
85262
119464
Generator to Poblacion
690
59351
26.91
22183
24838
33302
Looc
690
12102
6.047
5317
2661
5946
19.68
84898
87253
121740
Bus Name
Pre-Flt
( V )
3C
X/R
3C
Sym
3C DC
3C
Asym
28
13200
1008
5.315
454
18
454
Bus Bar
690
219123
19.17
83679
44259
94663
Generator to Poblacion
690
59351
26.91
22183
15570
27102
Looc
690
12102
6.047
5317
333
5328
44
19.68
84898
46080
96597
Bus Name
Pre-Flt
( V )
Std
X/R
Std
Sym
Std
DC
Std
Asym
28
13200
1008
5.315
426
426
Bus Bar
690
219123
19.17
83391
83391
Generator to Poblacion
690
59351
26.91
8570
8570
Looc
690
12102
6.047
5111
5111
84611
84611
0.5C
Sym
476
0.5C
DC
373
0.5C
Asym
604
Bus Bar
690
220126
19.17
84062
100908
131334
Generator to Poblacion
690
60559
26.91
22634
28482
36381
Looc
690
11623
6.047
5107
4296
6673
690
223753
19.68
85281
102814
133580
690
690
1C
X/R
5.315
1C
Sym
476
206
1C
Asym
519
220126
19.17
84062
85652
120011
60559
26.91
22634
25344
33980
1C DC
45
Looc
690
690
11623
6.047
5107
2555
5710
223753
19.68
85281
87647
122290
Pre-Flt
( V )
3C
X/R
3C
Sym
3C DC
3C
Asym
28
13200
1057
5.315
476
19
476
Bus Bar
690
220126
19.17
84062
44462
95096
Generator to Poblacion
690
60559
26.91
22634
15887
27653
Looc
690
11623
6.047
5107
320
5117
690
223753
19.68
85281
46288
97033
Table 6-21
Bus Name
Pre-Flt
( V )
Std
X/R
Std
Sym
Std
DC
Std
Asym
28
13200
1057
5.315
420
420
Bus Bar
690
220126
19.17
83484
83484
Generator to Poblacion
690
60559
26.91
5351
5351
Looc
690
11623
6.047
4748
4748
690
223753
19.68
84704
84704
46
47
Chapter 7
Conclusion
After the formulation different designs in wave power plant, engineering constraint were used to
determine the best possible design that will sustain the deficit power in Lubang Island in the next
following years. The constraint are based upon the availability of the resources of renewable energy
and desired characteristics of the client.
After the step by step process, point absorber has won the tradeoff. Also, the project obejectives were
attained by winning the design. First, point absorber can compensate the insufficient supply of electrical
energy in year of 2021. Second, it can provide a less expensive to the people of Lubang Island. Lastly,
it will utilize the renewable energy that is available in the island which is the wind.
Using the paladin software, the system parameters were obtained by checking the full report after
conducting load flow analysis. With the power generation, the 2 MW deficit power in Lubang will be
covered. Satisfying and overcoming the all the problems that will be faced for the following years, this
design project is considered as a success.
Lastly, standards play a vital role in governing the system and processes, such as IEC, IEEE, ANSI, ISO,
etc., and must always incorporate into the design to ensure that the design is safe, efficient and reliable.
48
Reference
From Books:
Kiameh, Philip (2012). Power Generation Handbook. McGraw-Hill Companies, United States of
America Wayne, H. W. (2007). Standard Handbook for Electrical Engineers. McGraw-Hill Incorporated,
United States of America.
Gasch, Robert. Wind Power Plants Fundamentals, Design, Construction and Operation Second Edition.
Gonen, Turan (2008). Electric Power Distribution System Engineering. Taylor and Francis Group LLC,
Florida
Online Sources:
Publications/freepublications/publication/essentials3.pdf
https://www.iea.org/
http://www.nrel.gov/docs/fy11osti/52688.pdf
AmandaCuellar_Thesis_June2012.pdf
https://sequestration.mit.edu/pdf/
Energy Content in Common Energy Sources. (n.d.). Retrieved February 03, 2016, from
http://www.engineeringtoolbox.com/energy-content-d_868.html
Transformer rating, Losses, and Short-circuit Impedance Specifications. (2016, January). Retrieved from
http://www.alibaba.com/product-detail/10-Mva-Amorphous-alloy
oilimmersed_60333898712.html?spm=a2700.7724838.30.1.0kEHfr&s=
49
Appendix A
Calculation of Trade-Offs
Efficiency
Point absorber
Terminator/Overtopping
868.43k Losses
868.43k
Losses=193.3k
Total Losses=Losses x no. of turbines
Total Losses=193.3k x 3
Total Losses=773.279k
Efficiency of the Turbine
Pin Losses
Efficiency=
Pin
78.28 =
994.2846 k Losses
994.2846 k
Losses=215.9586 k
Total Losses=Losses x no. of turbines
Total Losses=215.9586k x 3
50
Total Losses=647.87k
LCOE
Point Absorber
Equipment
Generator
Tidal Turbine
Total
Price
125,213,400
361, 727,600
No. of Pieces
1
1
Total Price
361, 727,600
125,213,400
486,941,000
No. of Pieces
3
3
Total Price
521,257,400
2,044,000,000
2,565,257,400
51
Price
62,000,000
196,000,000
No. of Pieces
3
3
Total Price
186,000,000
588,000,000
774,000,000
Terminator/Overtopping
Equipment
Generator
Tidal Turbine
Total
Price
33,00,000
117,000,000
No. of Pieces
1
1
Total Price
33,00,000
117,000,000
150,000,000
52
Life Span
Design
Vertical Axis Turbine
Seagen horizontal Axis Turbine
Point Absorber
Terminator/Overtopping
(Yrs)
15
20
50
50
Point Absorber:
Ranking Score =
- 78.28-98.3
100
- 78.28-98.3
100
Ranking Score = 1
Terminator/Overtopping:
Ranking Score =
- 78.28-92.27
100
- 78.28-98.3
100
53
- 78.28-78.28
100
- 78.28-98.3
100
- 78.28-78.28
100
- 78.28-98.3
100
LCOE:
Formula used for setting the high and low values:
High=38.069
Low=2.2
P=preferred value of the client
Ranking Score =
Point Absorber:
Ranking Score =
- 38.069-7.23)
100
- 38.069-2.2
100
- 38.069-2.2)
100
- 38.069-2.2
100
- 38.069-11.486)
100
- 38.069-2.2
100
54
Ranking Score =
- 38.069-38.069)
100
- 38.069-2.2
100
Ranking Score =0
Life Span
Formula used for setting the high and low values:
High=50
Low=15
P=preferred value of the client
Point Absorber:
Ranking Score =
Ranking Score =1
- 15-50
100
- 15-50
100
Terminator/Overtopping:
Ranking Score =
Ranking Score =1
- 15-50
100
- 15-50
100
- 15-15
100
- 15-50
100
- 15-20
100
- 15-50
100
Area
Since there is huge discrepancy between the areas of each design, low and high values are
set.
High=270
low=150
P=preferred value of the client
55
Point Absorber:
Ranking Score =
Ranking Score =1
- 270-150
100
- 270-150
100
Terminator/Overtopping:
Ranking Score =
- 270-185
100
- 270-150
100
- 150-210
100
- 270-150
100
- 150-270
100
- 270-150
100
56