Beruflich Dokumente
Kultur Dokumente
II.
Question 02
1. Should start with a good definition for value management and consequently
describe the followings.
A systematic process which is clearly defined
Key focus on the function
Not an individual work, but a multi disciplinary effort
2.
Costly projects
Complex projects
Repetitive projects
Projects with restricted budget
Q3.
I.
Superficial area method
II.
Estimate = Area of each of the floors*Cost per m2
Most Popular preliminary estimating method
Advantages
Quick method
Easy to employ as the rules for calculations are much more simple
Directly relates to accommodation
Allow comparison of different Designs
Meaningful in its concept of measurement(m2) to both client and architect
Allow comparison between buildings that differ in size and shape
Disadvantages
Fails to take account of any variation in plan and shape or storey height
* Try to highlight the advantages of this method by analysing the above mentioned
points.
III.
Hence for this shopping complex assume unit rate as 90000+100,000 = 95000.00
2
Hence, Estimate
IV.
= 8000sqm*95,000Rs/sqm
=760Mn
Since there is a checking system on the cost, there is possibility that less changes will be made to
the BQ. Discussions among designers can be made before the production of the final design. This
will definitely save time in making adjustment to any changes to the cost and design.
The effectiveness of cost and value for money can be achieved with cost planning process.
Cost consideration will be given more attention since the QS is involved in the early stage of the
design process.
The BQ can be prepared more easily since the QS is already familiar with or skilful in the project
and thus has clear understanding of what is to be achieved by a designer.
Cost planning provides basic information on cost comparison between different project
Disadvantages
1. It requires a lot of preparation at the early stage of the design process.
2. The designers may have some limitation in their work style.
3. The QS need to be equipped with past experience and knowledge pertaining to cost and factors
influencing the cost.
4. Both designer and QS are involved with a lot more work at the design stage as compared to when
no cost planning is used.
II.
It is a process whereby the estimated cost is being checked against cost target
set or elements of building and takes place during the design stage of
contract.
The cost checking process can be defined as being the assessment of the
probable cost of the Architects design, in step as it develops. The checks are
carried out by the Quantity Surveyor and the control exercise of the
Architect.
In another words, cost checking is the process of checking the estimated cost
of each section or element of the building as the detailed designs are
developed, against the cost target set against it in the cost plan.
Advantage of cost checking is that will help to keep the cost of detail design prepared
by the Architect does not exceed the cost target.
III.
Remedial action should be taken before any serious damage is done or work is so advanced that a great
deal of abortive work is the result. That is, before the decisions creating over-expenditure are irrevocably
incorporated into the project. The remedial action must be taken quickly and, ideally, as soon as the cost
overruns become known and the decisions communicated to everyone in the team. Remedial action thus
ensures that total project expenditure is contained within the cost limit.
Occasionally, suitable remedial action is impossible, and additional finances must be obtained to complete
the project. The client will generally be requested to supply the additional funds. This implies that the
initial estimate was incorrect and will certainly embarrass the design team. However, the presentation to
the client of a carefully completed and detailed revised budget is the most convincing argument to justify
the need for additional funds. The alternative does not bear consideration
Result
1. Cost Check Cost Target
Action
1.
Q5
I.
Explain: Elements. Prepare cost targets, BCIS data, previous experience and report, selecting
appropriate cost model, Adjustments
II.
Planning contingency
risk of not being able to design the spatial relationships and achieve the desired functional area and
travel/engineering allowances.
Design (risk) contingency
an allowance to cover the risk of the estimator/cost planner not adequately foreseeing the correct design
or the complexity of the design.The amount of the Design Contingency will depend on the amount of
detail available, and will be reduced to zero at Tender Document stage
Contract contingency
an allowance to cover the risk of variations and unforeseen items encountered during construction.
Project contingency.
to cover delays and/or inflation, major changes required by the client or authorities, fee negotiations and
similar.
The amount of each contingency should be decided before preparing the outline cost plan
III.
Location: Assessment of ease or difficulty of entry to and egress from the site, distance from
major highways, requirements for temporary roads.
Space available on site: Limited on-site storage and space for facilities (inner city sites) is likely
to require special measures leading to increased costs.
Security: Temporary fencing, hoardings and gantries required for public safety and to protect the
works from pilfering and vandalism are significant costs affected by the location and length of the
boundary of the site.
Contract period: Many items in preliminaries are related directly to the length of the construction
period supervision, cleaning, accommodation, hire, telephones and the like. Additionally, when
a client requires an early completion time the preliminaries section may be increased to account
for overtime payments, weekend working and penalty rates generally.
Plant: Many items of plant, particularly those provided by the subcontractor, are directly related
to the works in an element and are priced in that section. However, where the contractor provides
general items of plant for use by the whole site and across several subcontractors then these are
likely to be priced in the preliminaries element. Examples of these include scaffolding, hoists, site
cranes and a range of small tools.
Insurance: The requirement for insurance for public liability, adjoining owners and value of the
works is included in preliminaries and should be judged on the basis of risks influencing the
specific site.