Beruflich Dokumente
Kultur Dokumente
Philosophy
for
Piping Design
Onshore
Document Number
TO-HQ-02-037-00
00
Final Issue
JS
27/5/05
A2
Comments Incorporated
IB
28/4/05
A1
IB
Issue
Rev
Origin
By
Date
JEA
31/5/05
PZ
31/5/05
MF
3/6/05
Chk
d By
Date
Appd
By
Date
Appd
By
Date
Revision
Description of revision
A1
For Comment/Approval
A2
Comments Incorporated
00
Final Issue
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
2 of 41
Contents
1.0 PREFACE .......................................................................................................................6
2.0 DEFINITIONS .................................................................................................................6
3.0 ABBREVIATIONS...........................................................................................................6
4.0 INTRODUCTION.............................................................................................................7
5.0 APPLICABLE CODES, STANDARDS AND REGULATIONS........................................7
5.1
5.2
Design Requirements.............................................................................................................. 11
Material Selection .................................................................................................................... 12
Cathodic Protection and Coatings......................................................................................... 12
Fabrication ............................................................................................................................... 13
Inspection and Testing............................................................................................................ 13
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
3 of 41
13.1
13.2
13.3
13.4
Pipe Routing............................................................................................................................. 19
Clearance and Accessibility ................................................................................................... 20
Piperacks/Pipeways ................................................................................................................ 21
Grouping................................................................................................................................... 21
General ..................................................................................................................................... 23
Pumps....................................................................................................................................... 23
Compressors............................................................................................................................ 25
Turbines.................................................................................................................................... 26
Diesel Engines ......................................................................................................................... 26
Vessels and Towers ................................................................................................................ 27
Heat Exchanger Piping............................................................................................................ 28
Launchers and Receivers ....................................................................................................... 28
Air Piping.................................................................................................................................. 29
Steam Piping ............................................................................................................................ 29
Utility Piping............................................................................................................................. 30
Pressure Relief Piping............................................................................................................. 30
Underground Piping (in plant sites)....................................................................................... 31
Firewater/Deluge Piping.......................................................................................................... 32
Drainage and Sewerage Piping .............................................................................................. 33
Storage Tank Piping ................................................................................................................ 33
Wellhead Area Piping .............................................................................................................. 34
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
4 of 41
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
5 of 41
1.0
PREFACE
This Philosophy defines the OMV Exploration & Production GmbH
corporate policy on the design of piping for onshore hydrocarbon
production and processing facilities. The document specifies basic
requirements and criteria, defines the appropriate codes and standards,
and assists in the standardisation of facilities design across all onshore
operations.
The design process needs to consider project specific factors such as
the location, production composition, production rates and pressures,
the process selected and the size of the plant. This philosophy aims to
address a wide range of the above variables, however it is recognised
that not all circumstances can be covered. In situations where project
specific considerations may justify deviation from this philosophy, a
document supporting the request for deviation shall be submitted to
OMV E&P for approval.
Reference should be made to the parent of this philosophy, document
number TO-HQ-02-001 for information on deviation procedures and
Technical Authorities, general requirements and definitions and
abbreviations not specific to this document.
2.0
DEFINITIONS
There are no definitions with particular relevance to this document.
3.0
ABBREVIATIONS
The following abbreviations are significant to this document.
NPSH
MT
NPS
PT
Penetrent Testing
PWHT
RT
Radiographic Testing
UT
Ultrasounic Testing
WFMT
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
6 of 41
4.0
INTRODUCTION
Most of the risks to safety in the oil and gas industry are from the
production process by release of hydrocarbons. Hazards associated
with the uncontrolled release of hydrocarbons are as follows:
Over pressure
Leak
Liquid overflow
Gas blowby
Under pressure
Over temperature
5.0
Local Regulations
National standards
Design of the safety system shall comply with the standards listed within this
philosophy, however, for instances where local standards are more onerous
local standards shall apply.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
7 of 41
5.1
5.1.1
Process Piping
ASME B16.5
ASME B16.47
ASME VIII
Div 1
API RP 14E
API RP 14C
API RP 521
API 618
ISO 10474
(EN 10204)
ISO 15589-1
ISO 12944
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
8 of 41
5.2
6.0
NACE
MR-01-75
(ISO 15156)
API 6FA
API 607
BSEN ISO
10497
References
TO-HQ-02-001
TO-HQ-02-021
TO-HQ-02-022
TO-HQ-02-031
TO-HQ-02-034
TO-HQ-02-036
TO-HQ-02-038
TO-HQ-02-039
TO-HQ-02-040
SYSTEM GOAL
The emphasis on design and selection of piping systems is to eliminate
hazards completely. However, should it prove impossible to prevent
certain hazards every effort shall be taken to reduce the probability of
its occurrence.
The piping specified and supplied for the Project shall otherwise be in
accordance with the relevant codes, good industry practices and shall
meet agreed Project Specifications.
All mechanical equipment and facilities shall in addition be designed for:
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
9 of 41
7.0
SYSTEM BOUNDARIES
The boundary of the application of this philosophy is as shown in the figure
below:
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
10 of 41
8.0
8.1
Design Pressure
The design pressure shall be that determined by Document No TO-HQ02-031 - Philosophy for Process systems General Design Guidelines
Onshore, and in accordance with the requirements of ASME B31.3.
8.2
Design Temperature
The design temperature shall be that determined by Document No TOHQ-02-031 - Philosophy for Process systems General Design
Guidelines Onshore, and in accordance with the requirements of ASME
B31.3.
8.3
Design Load
Loadings to be considered in designing piping shall include internal and
external pressure, self weight including service fluid or hydrostatic test fluid
which ever is the heavier, loading from supports, temperature gradients
and differential temperature expansion. Effects from cyclic application of
the above loads shall be considered if applicable. The effects from
environmental loads such as snow, wind, ice and earthquake shall be
included as specified within the applicable project specification or data
sheet.
9.0
DESIGN CRITERIA
9.1
Design Requirements
The design of all piping systems shall be in accordance with the latest
edition of the codes and standards listed in Section 5.
Design conditions will be in accordance with ASME B31.3 for process
and utility piping, except where the requirements of this document are
more stringent.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
11 of 41
9.2
Material Selection
Materials of construction for each item will be selected to ensure that
the item will remain fit for purpose throughout its design life. When
determining the suitability of a material for a given application,
consideration will be given to likely degradation mechanisms,
internal/external environments, normal/abnormal operational conditions
and interactions with other items/materials/chemicals, as appropriate.
Where carbon steel is to be exposed to a corrosive environment, an
appropriate corrosion allowance will be provided, based on predicted
corrosion rates over the life of the asset. A minimum corrosion
allowance of 3.0mm is required for carbon steel items exposed to sour
hydrocarbon service, as defined by NACE MR0175/ISO 15156. All other
carbon steel items containing hazardous or hydrocarbon process fluids
will have a minimum corrosion allowance of 1.5mm.
Materials selection will be performed with the aim of minimising life
cycle costs over the life of the asset.
9.3
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
12 of 41
Fabrication
Preparation, preheating, welding, heat treatment and non destructive
examination of welds to pressure-containing parts shall be in
accordance with the requirements of the ASME B31.3.
Design shall also take into consideration the selection of weld
procedures.
9.5
9.5.1
9.5.2
7C
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
13 of 41
The chloride content of water shall not exceed 30 ppm for testing of
piping fabricated from any austenitic stainless steel.
OMV approval is required for a pneumatic or hydropneumatic test in lieu
of a hydrostatic test.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
14 of 41
9.5.3
Repairs
Defects shall be removed to sound metal and re-welded using qualified
welding procedures by qualified welders. Pre and post weld heat
treatment shall be as for the original weld.
Repair welds shall be re-examined by the original method to ensure
freedom from defects.
OMV approval prior to repair is required for the following:
10.0
PIPE SIZING
Pipe sizing shall be in accordance with Document No TO-HQ-02-031 Philosophy for Process Systems General Design Guidelines Onshore.
Pipe sizes of NPS 1 , 2 , 3 , 4 , 5, 7, 9 are not permitted
unless necessary for mating to equipment. Where prohibited pipe sizes
are required for mating to equipment this shall change to the largest
acceptable piping size immediately adjacent to the equipment.
Piping which crosses bridges shall be NPS 2 minimum.
The minimum size for process piping shall be NPS 1, or NPS 2 when
installed in pipe racks (unless flow velocity is critical). NPS 1 shall not
be run for long distances.
The minimum size for utility piping shall be NPS 2 when installed in
pipe racks.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
15 of 41
PIPING COMPONENTS
All piping and piping components shall be specified in the piping material
class datasheets, which shall be included in a Piping and Valve Material
Specification.
The Piping and Valve Material Specification shall include as the minimum:
Valve datasheets
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
16 of 41
VALVES
All valves shall be designed and constructed in accordance with ASME or
API standards.
All valves which require operation under normal operating or emergency
conditions shall be accessible from grade/floor or platform. Generally
valves shall not be located above roads or walkways.
Isolation valves shall preferably be accessible from grade/floor or
platform. Where this is not possible valves shall be positioned such that
they are accessible from temporary access facilities. Chain wheel
operated valves shall not be allowed for isolation purposes.
Firewater valves shall always be accessible from grade/floor or permanent
platform.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
17 of 41
When required fire testing in accordance with API 6FA, API 607 or BSEN
ISO 10497 shall be performed as applicable and an independent authority
shall provide test certification.
Pressure relief devices shall be accessible from grade/floor or permanent
platform. Relief valves shall be installed with their stem vertical.
Actuated valves shall be accessible from grade/floor or permanent
platform.
Where the installation of check valves in vertical piping is required the flow
must be upward. A drain on the downstream side shall be provided.
Installation of valves in fouling services shall be with the stem horizontal
(for butterfly and gate).
Bypass valves and their associated piping shall be of the same
pressure rating as the higher pressure main piping to which they are
connected.
12.1
Control Valves
Control valves shall be located as near to the associated equipment as
possible.
Control valves to be operated by a local controller shall be within visual
range to permit observation.
Where there is a requirement for increased size of the downstream piping
the control valve shall be located as close to the reducer as possible.
Where control valves are less than the piping line size, the required
reducers shall be installed adjacent to the valve.
Where a high pressure drop occurs across a control valve sonic
harmonics and high noise levels are likely to occur. The downstream
piping shall be designed to prevent transmission of excessive vibration
and noise.
For critical operations and services bypass valves should be capable of
throttling the flow.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
18 of 41
13.0
PIPING LAYOUT
13.1
Pipe Routing
All piping shall be routed such that a simple, neat and ergonomic layout
is provided, allowing for easy supporting and flexibility.
Piping shall be routed overhead, except where process, safety or layout
requirements do not permit this.
Potential sources of hazard, such as flanged joints, shall be located
within hazardous areas as defined in the Hazardous Area Classification
specification or drawings.
Piping containing pressurised flammable or toxic fluids shall be of fully
welded construction when passing through non hazardous areas.
Pipe flanges in piping transporting corrosive fluids shall not be installed
above equipment, vessels or escape routes.
Piping transporting corrosive fluids shall not be installed above other
piping or cables.
The use of flanges in piping transporting corrosive fluids in pipe racks
shall be avoided wherever possible.
The use of flanges in overhead piping transporting hydrocarbon fluids in
pipe racks shall be avoided wherever possible.
Piping containing liquids shall not be routed above electrical
installations or equipment.
Cable trays at crossings shall be run above piping where ever possible.
Where the above cannot be avoided all potential leak sources shall be
eliminated.
Piping shall be protected from falling object hazards where applicable.
With the exception of fire fighting piping systems piping shall not be
located
within
instrument,
electrical
or
telecommunication
control/switchgear rooms.
Un-insulated cold piping, where ice build up is possible shall not be
routed above walkways.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
19 of 41
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
20 of 41
Piperacks/Pipeways
Pipe racks shall be routed parallel or perpendicular to roads. The
minimum distance between the road shoulder and outside of pipe rack
columns shall be 1.0m.
The minimum distance between two pipe rack levels shall be 1.2m and
shall take into account pipe sizes and insulation thickness.
Pipe racks running perpendicular to each other shall be at different
elevations.
Pipe spacing shall take into account insulation thicknesses and
movement due to thermal contraction/expansion.
Piping should be arranged on horizontal racks at specific elevations.
When a change in direction of piping is required, with the exception of
expansion loops, the piping should change elevation. Care shall be
taken to avoid pockets.
Bridge piping shall be designed with expansion loops capable of
handling relative movement under design conditions.
Condensate piping shall be located on the lowest pipe rack level where
applicable.
13.4
Grouping
The grouping of hot and cold piping together shall be avoided. Hot,
un-insulated piping should be at a higher elevation that cold piping.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
21 of 41
ISOLATIONS
The requirements of this section should be reviewed in conjunction with
the requirements of Document No TO-HQ-02-034 - Philosophy for
Isolation of Process Systems Onshore.
Where the total shutdown, isolation and depressurisation and draining
of piping is not practical the piping design shall incorporate facilities to
ensure isolation of a complete system, train or item of individual piece
of equipment.
The isolations shall be provided at the boundaries of the unit, or item of
equipment.
In addition to main inlet and outlet piping, isolation shall also include
drains, vents and other interfaces.
Isolation shall include a means of positive isolation, which shall be
achieved by fitting a blind, insertion of a spade or the rotation of a
spectacle blind.
Piping shall be designed to allow adequate flexibility to spring the piping
for removal/insertion. For ring type joints this flexibility shall allow for
removal of the ring.
For piping where liquids can be shut in and there is a source of heat
(including environmental heating) a thermal RV shall be installed.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
22 of 41
15.0
15.1
General
Piping connected to equipment shall be designed such that any forces or
moments due to thermal expansion, dead weight and operating loads do
not exceed those specified by the equipment vendor or code allowable
limits.
Piping configurations at equipment shall be designed and supported so
that equipment can be dismantled or removed without the addition of
temporary supports or dismantling valves and piping other than removing
spool pieces or reducers adjacent to the equipment. Clearance shall be
provided for the installation of blind flanges or reversible spades on block
valves on hazardous fluids or high pressure piping. Breakout spools shall
be as short as possible.
Supports and anchors shall be provided to ensure that excessive weight
and thermal stresses are not imposed on the casing of rotating equipment.
Piping for rotating equipment shall be designed for sufficient flexibility
without the use of flexible couplings and expansion bellows. Cold
springing shall not be permitted.
Where deck level supports for piping are required they shall be supported
on integral extensions of the equipment support structure and not the
equipment base plate. This shall apply to both resilient and fixed supports.
Provision shall be made for the isolation of equipment with blinds or the
removal of spool pieces for maintenance and pressure testing.
Piping shall be balanced through the use of suitable supports to minimise
the load which can be exerted on compressor gas nozzles and the
nozzles of large centrifugal pumps.
Piping to equipment operating in parallel shall be symmetrical wherever
possible.
15.2
Pumps
The requirements of this section should be reviewed in conjunction with
the requirements of Document No TO-HQ-02-039 - Philosophy for
Rotating and Reciprocating Equipment Onshore.
In the absence of vendor allowable loading criteria the applicable API
specifications shall be used.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
23 of 41
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
24 of 41
Compressors
The requirements of this section should be reviewed in conjunction with
the requirements of Document No TO-HQ-02-039 - Philosophy for
Rotating and Reciprocating Equipment Onshore.
In the absence of vendor allowable loading criteria, API specifications shall
be used.
Top and bottom entry compressors should be evaluated on the basis of
neat piping layout.
All suction piping between the knock out (scrubber) vessel and
compressor shall be arranged to prevent the trapping or collection of
liquid.
Piping shall continuously slope downwards from the suction cooler to the
knockout (scrubber) vessel. Piping shall be routed so that any condensate
drains back from the compressor suction to the knockout (scrubber)
vessel.
All compressors shall be provided with a temporary strainer in the suction
piping unless a permanent strainer is specified. Strainers shall be located
as close a possible to the compressor suction.
A check valve shall be installed in the compressor discharge piping, and
be as close as possible to the discharge nozzle.
Recycle lines shall be optimised with respect to recycle volumes as much
as possible.
Where reciprocating compressors are utilised, an acoustical and
mechanical analysis to API 618 shall be performed to avoid acoustic
resonances which can produce excessive vibration and stress in the
piping system.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
25 of 41
Turbines
The requirements of this section should be reviewed in conjunction with
the requirements of Document No TO-HQ-02-039 - Philosophy for
Rotating and Reciprocating Equipment Onshore.
In non hazardous areas all connections shall be buttweld except valves
and turbine connections which can be flanged within the turbine enclosure.
Fuel controls and fuel filters shall be easily accessible.
All inlet and exhaust piping/ducting shall be supported in accordance with
vendor requirements.
Exhausts shall be routed to a non hazardous area and shall not prove
hazardous to personnel or foul the air inlet.
15.5
Diesel Engines
The requirements of this section should be reviewed in conjunction with
the requirements of Document No TO-HQ-02-039 - Philosophy for
Rotating and Reciprocating Equipment Onshore.
Fuel piping shall not run directly over the engines, their exhaust or any
other area where leakage can impinge on a hot surface.
The piping should not be supported by hanger type supports.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
26 of 41
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
27 of 41
15.7
15.8
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
28 of 41
The junction between the production piping and the inlet/outlet to the
launcher/receiver shall be designed to prevent pigs from entering the
production piping. This normally consists of a barred Tee.
A minimum of 2m straight run should be arranged between the barred tee
and the pipeline ESD valve in order to accommodate the installation of an
inflatable welding pig, allowing double isolation against the pipeline if
repair to the isolation valves to the launcher/receiver or process system
should be required.
The layout and alignment of receivers/launchers within the site shall be
such that buildings or other facilities are not sited immediately behind the
door opening.
16.0
16.1
Air Piping
Air system piping shall have a self draining facility provided at all low
points for the collection of condensate.
Air traps shall have isolation valves, balance lines and drains to local
collection points.
Instrument air headers and manifolds shall not be dead ended but
supplied with blind flanges for cleaning and maintenance.
All branches and take offs shall be from the top of headers.
Discharge piping from air compressors shall enter into headers from
above in order to prevent filling of the standby compressor with
condensate.
16.2
Steam Piping
Steam piping shall be run to prevent pockets.
Condensate shall be collected at low points utilising a standard steam
trapping system.
Drain points shall be from the bottom of a header and steam take off from
the top.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
29 of 41
16.3
Utility Piping
Utility stations shall be provided as required for air, water, steam/hot water
and/or nitrogen. Each station shall be numbered and located in general
working areas at ground or platform level.
Water, nitrogen and plant air systems shall be equipped with hose reels so
that all areas can be reached with a 15m length of hose.
Nitrogen stations shall not be located within buildings or enclosed areas.
Utility stations shall be piped up so that they remain in operation during a
shutdown of any of the process unit systems.
Hose connections shall be such that flexible hoses can only be used for
their intended service.
Different coupling types shall be employed for air and nitrogen.
Contamination of potable water from connecting piping systems shall be
prevented by the installation of isolation valves, check valves, break tank
with syphon or other back flow pressure prevention equipment.
Utility connections to process systems should be avoided, however, where
essential a double block and bleed valve with spectacle blind shall be
provided. All utility system piping to be hooked up to pressurised process
piping or equipment shall be equipped with a check valve to prevent
process fluid entering the utility piping.
Branch connections in utility piping shall be valved. These valves shall be
located in horizontal sections of piping as close to the header as possible
unless they can be grouped together at the edge of a pipe rack and are
accessible from ground level or a platform.
16.4
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
30 of 41
16.5
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
31 of 41
Firewater/Deluge Piping
The requirements of this section should be reviewed in conjunction with
the requirements of Document No TO-HQ-02-072 - Philosophy for Active
Fire Protection Systems Onshore.
Firewater distribution piping layout shall be designed taking hydraulic
pressure drop into consideration.
Branch offtakes for deluge nozzles shall avoid location at the bottom of the
header to avoid plugging of the nozzles.
The location of the nozzles shall be specified by the Technical Safety
discipline.
Dead end headers shall be avoided.
Slam type check valves are not permitted.
Deluge isolation valves shall be installed behind the safe area firewall.
Fire monitors and upstands shall be protected from vehicle impact, by pipe
frames.
Fire water distribution piping shall be routed to minimise exposure to
impingement by fire.
Piping and fittings shall be supported and braced for water hammer from
the fire pumps.
Fire water deluge system piping shall be sloped to drain. Low point drains
shall be provided and drainage shall be to the open drain system.
The layout shall be in a ring system which allows provision of fire water
to each area from two sides.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
32 of 41
16.7
16.8
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
33 of 41
17.0
18.0
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
34 of 41
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
35 of 41
19.0
SAMPLING CONNECTIONS
Sample connections shall be located such that they are accessible from
grade, floor or permanent platform.
Sample connections shall not be placed in locations subject to vibration.
Sample connections shall not be located in piping system dead legs.
Sample connections shall be as short as practical, and braced to mitigate
against mechanical damage.
The sample points shall have two valves. One valve at the take off point
from the process piping, with another at the sampling point. The valve at
the take off point shall be sized as a standard drain valve. The valve at the
sampling point shall be NPS maximum with good throttling properties.
Gas sample points shall have their take off located at the top of horizontal
piping.
Sample outlets for self igniting or toxic fluids shall have a self closing
downstream valve.
Where the sampled fluid temperature is greater than 1700F sample
coolers shall be provided.
Sample connections shall be designed with the capability to flush through
test lines, drain, sump or containers.
Gas sample connections shall be connected to the flare system to
facilitate flushing.
20.0
INJECTION CONNECTIONS
Where the fluid to be injected is corrosive in nature it shall be injected into
the centre of the main pipe to avoid direct contact with the pipe wall and
shall not be immediately upstream of an elbow.
A check valve shall be installed at the injection point to hazardous process
fluid systems to prevent the process fluid entering the chemical system.
21.0
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
36 of 41
due to high fluid velocity and density, for flanged thermowell fittings.
Alternatively short thermowells can be used.
For temperature connections in piping less than NPS 4 the piping shall be
locally enlarged to NPS 4.
22.0
STRAINERS
The decision as to whether a strainer is to be specified as temporary or
permanent shall be addressed at the development of the P&IDs. The
P&IDs shall indicate whether a strainer is permanent or temporary.
Strainers are required to be installed to the suction piping of all pumps and
compressors, and shall be installed between the equipment and its
isolation valve.
Strainers shall be installed in all piping that convey fluids which may
contain solid particles, unless equipment is specifically designed to handle
these fluids, and at other locations where specified on P&IDs.
Where damage by harmful materials may be expected temporary strainers
should be provided.
Easy removal and cleaning of filters shall be facilitated.
Permanent strainers shall permit cleaning without the dismantling of the
housing or piping.
Temporary strainers shall be installed such that removal without alteration
to the piping, supports or equipment alignment is possible.
The allowable pressure drop and required particle filtration size shall be
specified by during FEED.
The strainer shall have a mesh size with minimum free area of 250% of
the cross sectional area of the pipe in which it is installed.
The strainer housing shall:
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
37 of 41
23.0
VALVE BYPASSES
Bypasses shall not be installed around relief devices or ESD valves.
Bypass valves and piping shall conform to the same piping classification
as the primary valve.
24.0
PIPE SUPPORTS
A pipe support philosophy and pipe support detail standard shall be
supplied by the Contractor for OMV to review.
Piping shall be adequately supported for its deadweight, including
contents, insulation, attached unsupported component weights and all
other external sustained loadings.
The minimum spacing for pipe supports shall be such that stress
developed in the piping shall be less that the allowable stress under
sustained loading in accordance with ASME B31.3
The spacing between pipe supports shall not exceed 6m. The maximum
deflection in the piping shall not exceed the distance between supports
divided by 360 (L/360).
The variation of pipe support types shall be kept to a minimum.
All insulated piping shall be supported on shoes.
The use of welded attachments shall be kept to a minimum, but where
required shall be of a material compatible with the piping material.
Piping in pipe racks shall have guides to provide lateral restraint.
Where the support material is different to that of the piping insulation
material shall be installed to mitigate against galvanic corrosion.
Galvanised pipe supports shall not be permitted for the supporting of
stainless steel piping.
Cold springing of piping is generally not permitted. The use of cold spring
shall be approved by OMV.
Piping shall be supported by resting type supports in preference to
hanging type supports. Hanging type supports shall only be installed when
it is not possible to install resting type supports.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
38 of 41
PIPING FLEXIBILITY
The requirements for the performance of piping flexibility analysis are
detailed in Document No TO-HQ-02-038 - Philosophy for Pipe Stress and
Flexibility Analysis Onshore.
Improvement of piping flexibility shall be achieved by the use of offsets
and changes in pipe routing direction.
Expansion bellows or other types of flexible coupling shall only be
considered when no other means of improving flexibility is possible.
Expansion bellow type joints shall meet the requirements of ASME B31.3,
Appendix X.
Sliding type joints are not permitted.
26.0
PIPING IDENTIFICATION
Piping shall be assigned a unique line number, made up of the following
components:
NPS
Sequential number
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
39 of 41
Each line shall be listed on a piping line list which shall as a minimum
contain the following information relevant to the line number:
P&ID number
Fluid
Fluid phase
Stress critical
Copy of NDE (RT, UT, MT, PT, WFMT, etc.) test results
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
40 of 41
28.0
29.0
CERTIFICATION
The appropriate certification confirming compliance with the specified
construction code shall be supplied by the fabricator for review by OMV
and endorsed by the certifying authority where applicable.
Document Number
Rev
Page
Onshore
TO-HQ-02-037
00
41 of 41