Beruflich Dokumente
Kultur Dokumente
TaskName
Duration
Start
Finish
F
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
MAINSCHEDULE
PREPARATIONWORK
HordingWorks
Demolitonworks
Floordemolition
Walldemolition
Ceilingdemolition
EXTERIORFITTING
EXTERIORFITTING
EXTERIORFITTING
STRUCTUREWORKS
Earthwork
exavationwork
Footingpoundation
Footingpoundation
Footingpoundation
Formwork
Steelwork
Concretepouring
Neckcolumn
Formwork
Steelwork
Concretepouring
TieBeam
TieBeam
TieBeam
Project:2016.10.09Timeschedul
Date:Sun10/9/16
98days?
9days
2days
7days
7days
7days
7days
49days?
0days?
0days?
49days?
3days
3days
10days?
0days?
0days?
3days
3days
3days
7days
3days
3days
3days
17days?
0days?
0days?
Sep11,'16
T
Sep25,'16
S
T
Mon9/19/16 Sun12/25/16
Mon9/19/16 Tue9/27/16
Mon9/19/16 Tue9/20/16
Wed9/21/16 Tue9/27/16
Wed9/21/16 Tue9/27/16
Wed9/21/16 Tue9/27/16
Wed9/21/16 Tue9/27/16
Wed9/28/16 Tue11/15/16
Wed9/28/16 Wed9/28/16
Tue11/15/16 Tue11/15/16
Wed9/28/16 Tue11/15/16
Wed9/28/16 Fri9/30/16
Wed9/28/16 Fri9/30/16
Wed9/28/16 Fri10/7/16
Wed9/28/16 Wed9/28/16
Fri10/7/16 Fri10/7/16
Sat10/1/16 Mon10/3/16
Mon10/3/16 Wed10/5/16
Wed10/5/16 Fri10/7/16
Fri10/7/16 Thu10/13/16
Fri10/7/16 Sun10/9/16
Sun10/9/16 Tue10/11/16
Tue10/11/16 Thu10/13/16
Mon10/10/1 Wed10/26/1
Wed10/12/16Wed10/12/16
Wed10/26/16Wed10/26/16
9/28
9/28
10
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page1
O
M
ID
TaskName
Duration
Start
Finish
F
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
Formwork
Steelwork
Concretepouring
Floorslab
Floorslab
Floorslab
Formwork
Steelwork
Concretepouring
Columm
Formwork
Steelwork
Concretepouring
SteelBeamandFirstfloorslab
SteelBeamandFirstfloorslab
SteelBeamandFirstfloorslab
Hbeam150
Floordeck0.7mm
Formwork
Steelwork
Concretepouring
INTERIORFITTING
INTERIORFITTING
INTERIORFITTING
Wallfinishing
Settingout
Project:2016.10.09Timeschedul
Date:Sun10/9/16
7days
7days
7days
17days?
0days?
0days?
7days
7days
7days
10days
5days
5days
5days
15days?
0days?
0days?
3days
5days
6days
6days
4days
69days?
0days?
0days?
65days
2days
Sep11,'16
T
Sep25,'16
S
T
Mon10/10/16Sun10/16/16
Fri10/14/16 Thu10/20/16
Tue10/18/16 Mon10/24/16
Wed10/12/1 Fri10/28/16
Wed10/12/16Wed10/12/16
Fri10/28/16 Fri10/28/16
Fri10/14/16 Thu10/20/16
Tue10/18/16 Mon10/24/16
Sat10/22/16 Fri10/28/16
Sat10/29/16 Mon11/7/16
Sat10/29/16 Wed11/2/16
Mon10/31/16Fri11/4/16
Thu11/3/16 Mon11/7/16
Tue11/1/16 Tue11/15/16
Tue11/1/16 Tue11/1/16
Tue11/15/16 Tue11/15/16
Sat11/5/16 Mon11/7/16
Thu11/3/16 Mon11/7/16
Sat11/5/16 Thu11/10/16
Tue11/8/16 Sun11/13/16
Sat11/12/16 Tue11/15/16
Wed9/28/16 Mon12/5/16
Wed9/28/16 Wed9/28/16
Mon12/5/16 Mon12/5/16
Wed9/28/16 Thu12/1/16
Wed9/28/16 Thu9/29/16
9/28
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page2
O
M
ID
TaskName
Duration
Start
Finish
F
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
Erectingwalls
Plasterworks
Smoothplaster
Finesanding
Primerecoating
Firstcoatingwhite
Defectrepair
Finalpainting
Tilingworks
Tilingworks
Tilingworks
Roomfloortiling
Toiletfloortiling
Toiletwalltiling
Roomceilingfinishing
Roomceilingfinishing
Roomceilingfinishing
Hollowframe
Gypsuminstallation
Compounding
Sanding
Firstcoatingwhite
Defectrepair
Finalpainting
Toiletceilingfinishing
Hollowframe
Project:2016.10.09Timeschedul
Date:Sun10/9/16
5days
10days
10days
12days
8days
10days
9days
10days
25days?
0days?
0days?
20days
8days
18days
50days?
0days?
0days?
8days
8days
10days
10days
8days
9days
8days
32days
5days
Sep11,'16
T
Sep25,'16
S
T
Wed9/28/16 Sun10/2/16
Fri9/30/16 Sun10/9/16
Fri10/7/16 Sun10/16/16
Fri10/14/16 Tue10/25/16
Wed10/26/16Wed11/2/16
Thu11/3/16 Sat11/12/16
Sun11/13/16 Mon11/21/16
Tue11/22/16 Thu12/1/16
Mon10/10/1 Thu11/3/16
Mon10/10/16Mon10/10/16
Thu11/3/16 Thu11/3/16
Mon10/10/16Sat10/29/16
Mon10/10/16Mon10/17/16
Mon10/17/16Thu11/3/16
Mon10/17/1 Mon12/5/16
Mon10/17/16Mon10/17/16
Mon12/5/16 Mon12/5/16
Mon10/17/16Mon10/24/16
Sat10/22/16 Sat10/29/16
Thu10/27/16Sat11/5/16
Thu11/3/16 Sat11/12/16
Wed11/9/16 Wed11/16/16
Thu11/17/16Fri11/25/16
Thu11/24/16Thu12/1/16
Fri11/4/16 Mon12/5/16
Fri11/4/16 Tue11/8/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page3
O
M
ID
TaskName
Duration
Start
Finish
F
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
Calsiboardinstallation
Compounding
Sanding
Firstcoatingwhite
Defectrepair
Finalpainting
Door&windowsworks
Frameinstallationbathroomdoor
Ceilingtrackinstallationtoiletdoor
Paintremovedentrance&connectingdoor
Sandingentrance&connectingdoor
Primereaplicationentrance&connectingdoor
Ducopaintingentrance&connectingdoor
Installationbathroom/toiletdoor
Finishingbathroom/toiletdoor
Showerdoor
AluminiumSlidingdoor
OTHERWORKS
Roofmodification
Knockdownexisting
Roofstructurework
Erectingwallto1stfloorterrace
Ironwoodshinglesinstallation
Finishingwallto1stfloorterrace
BalineseRedBrickcolumncover
Balineseredbrickinstallation
Project:2016.10.09Timeschedul
Date:Sun10/9/16
5days
5days
10days
5days
5days
9days
67days
6days
3days
13days
11days
11days
12days
10days
10days
10days
10days
69days
65days
4days
6days
8days
4days
8days
12days
6days
Sep11,'16
T
Sep25,'16
S
T
Mon11/7/16 Fri11/11/16
Thu11/10/16Mon11/14/16
Sun11/13/16 Tue11/22/16
Mon11/21/16Fri11/25/16
Thu11/24/16Mon11/28/16
Sun11/27/16 Mon12/5/16
Wed9/28/16 Sat12/3/16
Mon10/17/16Sat10/22/16
Mon10/17/16Wed10/19/16
Wed9/28/16 Mon10/10/16
Tue10/11/16 Fri10/21/16
Sat10/22/16 Tue11/1/16
Wed11/2/16 Sun11/13/16
Fri11/4/16 Sun11/13/16
Mon11/14/16Wed11/23/16
Thu11/24/16Sat12/3/16
Thu11/24/16Sat12/3/16
Wed9/28/16 Mon12/5/16
Wed9/28/16 Thu12/1/16
Wed9/28/16 Sat10/1/16
Wed11/16/16Mon11/21/16
Wed11/16/16Wed11/23/16
Tue11/22/16 Fri11/25/16
Thu11/24/16Thu12/1/16
Wed11/16/1 Sun11/27/16
Wed11/16/16Mon11/21/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page4
O
M
ID
TaskName
Duration
Start
Finish
F
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
Stonepolish
4days
Coating
2days
Floorfinishing2Floor
19days
Waterproofing
5days
Whitewashterrazo
11days
Coating
5days
Woodenrailing2Floor
6days
Woodenrailinginstallation
5days
Woodenrailingfinishing
3days
NewTerrace&stairgarden
9days
Whitewashterrazo
8days
Coating
3days
Bamboopartion2Floor
4days
Bamboopartitioninstallation
4days
Bamboopartitionfinishing
2days
Canopysupport
20days
Wall&concretefasciabracket
4days
Floorbracket
8days
Pole
3days
MEWORK(DM)
73days
Cleanwaterplumbing
48days
Pipeinstallation
25days
MainEquipment(washbasin,showerandaccess8days
Hotwaterplumbing
48days
Pipeinstallation
25days
MainEquipment
8days
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Sep11,'16
T
Sep25,'16
S
T
Tue11/22/16 Fri11/25/16
Sat11/26/16 Sun11/27/16
Wed11/16/1 Sun12/4/16
Wed11/16/16Sun11/20/16
Sat11/19/16 Tue11/29/16
Wed11/30/16Sun12/4/16
Wed11/30/1 Mon12/5/16
Wed11/30/16Sun12/4/16
Sat12/3/16 Mon12/5/16
Sun11/27/16Mon12/5/16
Sun11/27/16 Sun12/4/16
Sat12/3/16 Mon12/5/16
Fri12/2/16 Mon12/5/16
Fri12/2/16 Mon12/5/16
Sun12/4/16 Mon12/5/16
Wed11/16/1 Mon12/5/16
Wed11/16/16Sat11/19/16
Wed11/16/16Wed11/23/16
Sat12/3/16 Mon12/5/16
Wed9/28/16 Fri12/9/16
Wed9/28/16 Mon11/14/1
Wed9/28/16 Sat10/22/16
Mon11/7/16 Mon11/14/16
Wed9/28/16 Mon11/14/1
Wed9/28/16 Sat10/22/16
Mon11/7/16 Mon11/14/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page5
O
M
ID
TaskName
Duration
Start
Finish
F
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
Sawage,WasteandRainwaterplumbing
Pipeinstallation
MainEquipment(WCandaccessories)
AC
Chilledpipeinstallation
Condensatedrainpipe
Ductinginstallation
FCU
MainEquipment
Exhaustfan
Exhaustductinstallation
MainEquipment
TelephoneandData
Telephoneanddatainstallation
Telephoneanddatasocket
FireAlarm
Firealarminstallation
Equipment
Electricalwork
Electricalinstallation
Lightingfixture
Keytags
TestingCommisioning
INTERIORWORK(GP)
BuiltinCabinetry
DELD02Luggage/DressingArc
Project:2016.10.09Timeschedul
Date:Sun10/9/16
48days
25days
8days
63days
25days
20days
10days
15days
15days
48days
12days
3days
38days
15days
3days
38days
15days
3days
73days
50days
15days
15days
2days
71days
49days
14days
Sep11,'16
T
Sep25,'16
S
T
Wed9/28/16 Mon11/14/1
Wed9/28/16 Sat10/22/16
Mon11/7/16 Mon11/14/16
Wed9/28/16 Tue11/29/16
Wed9/28/16 Sat10/22/16
Wed10/19/16Mon11/7/16
Sat11/5/16 Mon11/14/16
Sun10/23/16 Sun11/6/16
Tue11/15/16 Tue11/29/16
Wed9/28/16 Mon11/14/1
Wed9/28/16 Sun10/9/16
Sat11/12/16 Mon11/14/16
Wed9/28/16 Fri11/4/16
Wed9/28/16 Wed10/12/16
Wed11/2/16 Fri11/4/16
Wed9/28/16 Fri11/4/16
Wed9/28/16 Wed10/12/16
Wed11/2/16 Fri11/4/16
Wed9/28/16 Fri12/9/16
Wed9/28/16 Wed11/16/16
Sat11/19/16 Sat12/3/16
Fri11/25/16 Fri12/9/16
Sun12/4/16 Mon12/5/16
Wed9/21/16 Wed11/30/1
Wed9/21/16 Tue11/8/16
Wed10/26/16Tue11/8/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page6
O
M
ID
TaskName
Duration
Start
Finish
F
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
DELD03Panel/DressingArc
DELD05Vanity
DELD06VanityMirror
DELD12,D13,D14,HeadbedArc
LooseFurniture
DELD52Bedanddrawer
DELD51Sofa/Bed
DELD59SmallSofa
Defectlist
Cleaning
SUPERIORROOMWORK
TOPFLOOR
Protection
NewPelmetboxup
Sandingandtouchupofwallandceiling
Wallpainting
Ceilingpainting
Pelmetpainting
Dropceilingpainting
Repairmanhole
Newbedheadandextendsocketandswitch
cable
TVcabinetmodificationandtouchup
FCU
ExtendandrelocatesocketandTVSocket
Newshowerinstallation
Project:2016.10.09Timeschedul
Date:Sun10/9/16
14days
5days
5days
17days
5days
3days
1day
1day
2days
2days
96days
33days
2days
4days
10days
5days
5days
3days
4days
7days
7days
8days
6days
5days
6days
Sep11,'16
T
Sep25,'16
S
T
Wed10/26/16Tue11/8/16
Fri11/4/16 Tue11/8/16
Fri11/4/16 Tue11/8/16
Wed9/21/16 Fri10/7/16
Sat11/26/16 Wed11/30/1
Sat11/26/16 Mon11/28/16
Tue11/29/16 Tue11/29/16
Wed11/30/16Wed11/30/16
Fri12/2/16 Sat12/3/16
Sun12/4/16 Mon12/5/16
Wed9/21/16 Sun12/25/16
Wed9/21/16 Sun10/23/16
Wed9/21/16 Thu9/22/16
Wed9/21/16 Sat9/24/16
Wed9/21/16 Fri9/30/16
Mon9/26/16 Fri9/30/16
Mon9/26/16 Fri9/30/16
Mon9/26/16 Wed9/28/16
Thu9/29/16 Sun10/2/16
Thu9/29/16 Wed10/5/16
Thu10/6/16 Wed
10/12/16
Fri9/23/16 Fri9/30/16
Sat10/1/16 Thu10/6/16
Sat10/1/16 Wed10/5/16
Sat10/1/16 Thu10/6/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page7
O
M
ID
TaskName
Duration
Start
Finish
F
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
Keytags
4days
Defectlist
5days
Cleansite
6days
SECONDFLOOR
44days
Protection
2days
Sandingandtouchupofwallandceiling
15days
Wallpainting
9days
Ceilingpainting
9days
Pelmetpainting
5days
Dropceilingpainting
8days
Repairmanhole
11days
Newbedheadandextendsocketandswitchcab11days
TVcabinetmodificationandtouchup
11days
FCU
8days
ExtendandrelocatesocketandTVSocket
11days
Newshowerinstallation
11days
Keytags
6days
Defectlist
11days
Cleansite
8days
FIRSTFLOOR
64days
Protection
3days
NewPelmetboxup
4days
Sandingandtouchupofwallandceiling
16days
Wallpainting
8days
Ceilingpainting
8days
Pelmetpainting
7days
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Sep11,'16
T
Sep25,'16
S
T
Sun10/9/16 Wed10/12/16
Thu10/13/16Mon10/17/16
Tue10/18/16 Sun10/23/16
Sat10/1/16 Sun11/13/16
Sat10/1/16 Sun10/2/16
Mon10/3/16 Mon10/17/16
Fri10/14/16 Sat10/22/16
Fri10/14/16 Sat10/22/16
Fri10/14/16 Tue10/18/16
Fri10/14/16 Fri10/21/16
Fri10/14/16 Mon10/24/16
Thu10/20/16Sun10/30/16
Mon10/3/16 Thu10/13/16
Sun10/23/16 Sun10/30/16
Fri10/14/16 Mon10/24/16
Fri10/14/16 Mon10/24/16
Wed11/2/16 Mon11/7/16
Fri10/28/16 Mon11/7/16
Sun11/6/16 Sun11/13/16
Sun10/23/16Sun12/25/16
Tue10/25/16 Thu10/27/16
Tue10/25/16 Fri10/28/16
Tue10/25/16 Wed11/9/16
Mon11/7/16 Mon11/14/16
Mon11/7/16 Mon11/14/16
Mon11/7/16 Sun11/13/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page8
O
M
ID
TaskName
Duration
Start
Finish
F
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
Dropceilingpainting
7days
Repairmanhole
12days
Newbedheadandextendsocketandswitchcab10days
FCU
10days
TVcabinetmodificationandtouchup
49days
ExtendandrelocatesocketandTVSocket
10days
Newshowerinstallation
10days
Keytags
8days
Defectlist
5days
Cleansite
6days
GROUNDFLOOR
40days
Protection
3days
NewPelmetboxup
4days
Sandingandtouchupofwallandceiling
8days
Wallpainting
12days
Ceilingpainting
9days
Pelmetpainting
5days
Dropceilingpainting
4days
Repairmanhole
4days
Newbedheadandextendsocketandswitchcab5days
FCU
5days
TVcabinetmodificationandtouchup
4days
ExtendandrelocatesocketandTVSocket
4days
Newshowerinstallation
4days
Keytags
4days
Defectlist
4days
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Sep11,'16
T
Sep25,'16
S
T
Mon11/7/16 Sun11/13/16
Mon11/7/16 Fri11/18/16
Sat11/19/16 Mon11/28/16
Sun10/23/16 Tue11/1/16
Fri10/28/16 Thu12/15/16
Fri12/16/16 Sun12/25/16
Fri12/16/16 Sun12/25/16
Fri11/25/16 Fri12/2/16
Sat11/19/16 Wed11/23/16
Thu11/24/16Tue11/29/16
Tue10/25/16Sat12/3/16
Tue10/25/16 Thu10/27/16
Tue10/25/16 Fri10/28/16
Tue10/25/16 Tue11/1/16
Mon10/31/16Fri11/11/16
Sat11/12/16 Sun11/20/16
Sat11/12/16 Wed11/16/16
Sat11/12/16 Tue11/15/16
Wed11/16/16Sat11/19/16
Sun11/20/16 Thu11/24/16
Mon11/21/16Fri11/25/16
Sun11/20/16 Wed11/23/16
Thu11/24/16Sun11/27/16
Thu11/24/16Sun11/27/16
Tue11/22/16 Fri11/25/16
Mon11/28/16Thu12/1/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page9
O
M
ID
TaskName
Duration
Start
Finish
F
234
Cleansite
Project:2016.10.09Timeschedul
Date:Sun10/9/16
4days
Sep11,'16
T
Sep25,'16
S
T
Wed11/30/16Sat12/3/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page10
O
M
Oct9,'16
T
Oct23,'16
S
T
Nov6,'16
T
Nov20,'16
S
T
Dec4,'16
T
Dec18,'16
S
T
11/15
10/7
10/12
10/26
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page11
Oct9,'16
T
Oct23,'16
S
T
Nov6,'16
T
Nov20,'16
S
T
Dec4,'16
T
Dec18,'16
S
T
10/12
10/28
11/1
11/15
12/5
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page12
Oct9,'16
T
Oct23,'16
S
T
Nov6,'16
T
Nov20,'16
S
T
Dec4,'16
T
Dec18,'16
S
T
10/10
11/3
10/17
12/5
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page13
Oct9,'16
T
Oct23,'16
S
T
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Nov6,'16
T
Nov20,'16
S
T
Dec4,'16
T
Dec18,'16
S
T
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page14
Oct9,'16
T
Oct23,'16
S
T
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Nov6,'16
T
Nov20,'16
S
T
Dec4,'16
T
Dec18,'16
S
T
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page15
Oct9,'16
T
Oct23,'16
S
T
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Nov6,'16
T
Nov20,'16
S
T
Dec4,'16
T
Dec18,'16
S
T
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page16
Oct9,'16
T
Oct23,'16
S
T
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Nov6,'16
T
Nov20,'16
S
T
Dec4,'16
T
Dec18,'16
S
T
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page17
Oct9,'16
T
Oct23,'16
S
T
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Nov6,'16
T
Nov20,'16
S
T
Dec4,'16
T
Dec18,'16
S
T
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page18
Oct9,'16
T
Oct23,'16
S
T
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Nov6,'16
T
Nov20,'16
S
T
Dec4,'16
T
Dec18,'16
S
T
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page19
Oct9,'16
T
Oct23,'16
S
T
Project:2016.10.09Timeschedul
Date:Sun10/9/16
Nov6,'16
T
Nov20,'16
S
T
Dec4,'16
T
Dec18,'16
S
T
Task
ExternalMilestone
ManualSummaryRollup
Split
InactiveTask
ManualSummary
Milestone
InactiveMilestone
Startonly
Summary
InactiveSummary
Finishonly
ProjectSummary
ManualTask
Deadline
ExternalTasks
Durationonly
Progress
Page20