Beruflich Dokumente
Kultur Dokumente
ECONOMIC EVALUATION
5.1
General
The economic evaluation methodology for the bridge construction project under
Phase II of the project is basically the same with that during the Phase I with some
additional assumptions applied on a case-to-case basis. Basically, the economic
evaluation is carried out by comparing the economic cost of the project with the
economic benefit which will be brought about by the bridge construction.
The following three indicators are considered to assess the project viability:
5.2
5.2.1
Implementation Schedule
As discussed in Chapter 8, the project is proposed to be implemented with
the following schedule:
Year 2008
2009-2010
2010-2011
2011-2012
2012-2015
:
:
:
:
:
Project Preparation
Procurement of Consultant
Detailed Engineering Design
Procurement of Contractors
Construction of bridges
Project Life
The economic life of the project is assumed to be 25 years (2014-2038),
although the physical life of the bridge is much longer. The economic
viability of the bridge construction/improvement shall be evaluated within
the period of 25 years.
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-1
5.3
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-2
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-3
Ford Crossing
Spillway
Timber/Bailey
Bridge
Permanent
Bridge with
Load Limit
Permanent
bridge
Note: () Only selected bridges are applicable.
5.5
(5)
(6)
(7)
(8)
(9)
(10)
()
()
()
()
()
()
Benefit Calculation
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-4
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-5
Benefit Calculation
1) VOC savings from replacement of permanent bridge with new bridge
Construction of new bridge will reduce the probability of bridge collapse and
entailing bridge un-serviceability which requires vehicles to take the longer
detour route. The differences in vehicle operating cost between the detour
road and the regular road is considered as benefit.
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-6
b. Bridge Age
Residual life of bridges differs by structure type, traffic volume, geography,
present structural conditions and other factors even calendar age is the same.
Since the bridges identified for reconstruction in this study are already in the
advanced stage of dilapidation, their physical lives are assumed to have
elapsed. Hence, the age of bridges proposed for reconstruction in this study
is set at 50 years.
The of probability densities for bridge at the age of 50 years and newly
constructed bridge in comparison with the original probability densities are
shown in Table 5.6-1
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-7
=
=
fw(x)
d
AADTxi
DLo
DLw
VOCoi
=
=
=
=
=
VOCwi
Benefit at year x
Probability of bridge un-serviceability in year x for
without project case
Probability of bridge un-serviceability in year x for with
project case
Number of days required for bridge reconstruction
Average Annual Daily Traffic of vehicle type i in year x
Length of detour route (km)
Length of regular route (km)
Vehicle operating cost of vehicle type i along detour route
(p/km)
Vehicle operating cost of vehicle type i along regular
route (p/km)
Bridge reconstruction cost
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-8
Load Limit 5t
Timber Bridge :
Load Limit 3t
The same traffic regulation is applied for permanent bridges with load limit.
The benefits are calculated as follows:
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-9
Bx
=
AADTxi =
DLo
DLw
VOCoi
=
=
=
VOCwi
Benefit at Year x
Average Annual Daily Traffic of vehicle type I (Truck, Bus) in
year x
Length of detour route (km)
Length of regular route (km)
Vehicle operating cost of vehicle type i along detour route
(p/km)
Vehicle operating cost of vehicle type i along regular route
(p/km)
7 years
5 years
The short physical life of temporary bridges is attributed not only to rapid
dilapidation of the bridge component but also due to the high risk of
bridge washout during rainy season. An annual probability of bridge unserviceability is assumed to be distributed uniformly over physical life
period.
b. Physical Age of Existing Bridges
It may be unusual that all existing temporary bridges are new ones, they
are rather constructed at a certain period of time before. With the absence
of reliable data, the average physical age of existing bridges is assumed as
follows:
Bailey Bridge :
Timber Bridge :
2 years
3 years
The probability density of timber and bailey bridge are shown in Table
5.6-2 together with the probability of newly constructed bridge.
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-10
New Bridge
(With Project)
0.0270%
0.0323%
0.0384%
0.0455%
0.0538%
0.0633%
0.0743%
0.0868%
0.1011%
0.1173%
0.1356%
0.1563%
0.1794%
0.2052%
0.2339%
0.2657%
0.3007%
0.3391%
0.3810%
0.4265%
0.4758%
0.5289%
0.5858%
0.6465%
0.7110%
6.2113%
Timber Bridge
(Without Project)
33.3333%
33.3333%
33.3333%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
20.0000%
539.9999%
Bailey Bridge
(Without Project)
25.0000%
25.0000%
25.0000%
25.0000%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
14.2857%
399.9997%
Period of Restoration
(days)
30
40
60
77
90
100
108
115
120
125
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-11
In the previous feasibility study for the Phase I of the project in 2001, the
cost of restoration is roughly estimated at P50,000 per meter. However,
since the construction materials used for restoration of temporary bridges
are mainly locally sourced and considering that the US dollar value has
already gone down by about 75% while the local price has increase by
about 5%, the present restoration cost per meter is estimated at P48,000.
d. Calculation of Benefit
The VOC savings from replacement of temporary bridge are calculated
from the following equation:
Bx = [(fo(x)- fw(x))*d*AADTxi*(DLo*VOCoi-DLw*VOCwi) +
(fo(x)- fw(x))]*C
Where:
Bx
fo(x)
=
=
fw(x)
AADTxi
DLo
DLw
VOCoi
=
=
=
=
VOCwi
Benefit at year x
Probability of bridge un-serviceability in year x for
without project case
Probability of bridge un-serviceability in year x for with
project case
Number of days required for reconstruction of temporary
bridge
Average Annual Daily Traffic of vehicle type i in year x
Length of detour route (km)
Length of regular route (km)
Vehicle operating cost of vehicle type i along detour route
(P/km)
Vehicle operating cost of vehicle type i along regular
route (P/km)
Bridge restoration cost
Buses and trucks are excluded among the traffic for timber bridges while
trucks are excluded among the traffic for bailey bridges, since these
vehicles are not allowed to pass the temporary bridges.
4) VOC Savings from Construction of New Bridge where There is No Way to
Cross the River
In cases where the river has high water depth or is located along a deep ravine
that prevents all types of vehicle from crossing the river even by ford crossing,
vehicles have to take detour route all year round.
The VOC savings from this situation to that with the new bridge is calculated
as follows:
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-12
Bx = [AADTxi*(DLo*VOCoi-DLw*VOCwi)]*365
Where:
Bx
AADTxi
DLo
DLw
VOCoi
=
=
=
=
=
VOCwi
Benefit at year x
Average Annual Daily Traffic of vehicle type i in year x
Length of detour route (km)
Length of regular route (km)
Vehicle operating cost of vehicle type i along detour route
(P/km)
Vehicle operating cost of vehicle type i along regular
route (P/km)
=
=
=
VOCwi
Benefit at year x
Average Annual Daily Traffic of vehicle type i in year x
Average number of days impassable along the regular
route due to flooding
Length of detour route (km)
Length of regular route (km)
Vehicle operating cost of vehicle type i along detour route
(P/km)
Vehicle operating cost of vehicle type i along regular
route (P/km)
The average number of days impassable along the regular route due to
flooding is estimated based on the interview with the residents near the
concerned bridge.
6) VOC Savings from Bridge Widening (from single lane to 2 lanes)
Vehicle encounters at a single lane bridge cause slowing or stopping of
vehicles in either one or both directions.
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-13
The total incremental traffic costs, composed of running, fixed and time costs,
are calculated on the basis of the basic traffic costs and the unit penalties in
the form of dl-values and deceleration, acceleration, crossing time and waiting
time.
The equation shown below are the formulae used, based on the DPWH
Highway Planning Manual, for the calculation of incremental traffic costs on
an annual basis in P1,000.
Incremental Running and Fixed Costs:
RF =
=
=
=
=
=
=
=
=
=
=
=
=
The values for the variables in the given equations are taken/derived from the
Tables given in Chapter 5 of the Guidelines on Economic Evaluation of
Design Standards of Pavement and Bridges (Highway Planning Manual,
Volume 7), October 1982.
7) VOC Savings from Bridge Widening (from 2-lanes to 4-lanes)
Travel speed of vehicles on a bridge will be remarkably reduced when the
traffic volume reaches the capacity of the carriageway. The increase in travel
time in crossing the bridge due to reduction of travel speed will entail
additional traffic cost. This incremental cost derived from bridge widening
that is considered as savings will be accounted as benefit.
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-14
V1
V2
V3
V1
V2
Q1
Q2 Q3
V3
Traffic Volume
Q1
Q2
Each travel speed is assumed as follows: Q3
=
=
=
=
=
=
V1
V2
V3
Bus/Truck
=
=
=
Car/Jeepney
All vehicles
All vehicles
= 60 km/h
= 30 km/h
= 10km/hr
free-flow speed
speed at capacity
minimum speed
10% of capacity
capacity
110% of capacity
= 50 km/hr
24,000 vehicles/day
68,000 vehicles/day
=
=
=
=
=
Benefit at year x
Running cost of without case in year x
Time and fixed cost of without case in year x
Running cost of with case in year x
Time and fixed cost of with case in year x
=
=
=
=
=
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-15
AADTxi =
L
=
0.1
0.1
0.01
0.035
=
=
=
=
=
b. Periodic Maintenance
The periodic replacement of timber and bailey bridges includes
replacement of abutments, piers, panels and decks, which are considered
as part of maintenance costs.
The periodic maintenance costs for concrete and steel bridges are almost
negligible since all abutments and piers are assumed to be concrete.
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-16
The estimated maintenance costs for each type of bridge are presented
below.
ESTIMATED ECONOMIC MAINTENANCE COST IN DECEMBER 2007 PRICES (P1,000)
Replacement
Bridge
Frequency
Elements
(Years)
30
1. Timber Bridge
Abutments 5, 10, 15, 20, 25
472.97
Piers
5, 10, 15, 20, 25
657.56
Deck
5, 10, 15, 20, 25
733.21
Total
5, 10, 15, 20, 25 1,863.74
2. Bailey Bridge
Abutments
15
602.28
Piers
10, 20
189.12
Deck
5, 10, 15, 20, 25 1,718.91
50
80
100
150
200
250
472.97
1,131.82
975.03
2,579.81
472.97
1,505.54
1,218.78
3,197.29
472.97
2,438.87
1,950.06
4,861.89
472.97
299.72
2,437.57
5,910.30
472.97
4,679.56
3,657.43
8,809.94
472.97
6,177.01
4,863.18
11,513.16
472.97
7,658.63
6,079.05
14,210.66
602.28
378.25
2,257.33
602.28
567.36
2,935.75
602.28
947.55
4,668.24
602.28
1,136.99
5,695.00
602.28
1,705.65
8,599.39
602.28
2,268.17
11,523.50
602.28
3,016.90
14,058.39
9) Savings in Transport Cost for Using Other Modes of Transport in Crossing the
River
a. Assumptions
River-crossings along the secondary national road which has no
connection to other road at its end and does not form part of the road
network has no detour route. Road users are obliged to cross the river
using boat or raft. The benefits derived from construction of new bridge
will be in the form of savings in transport cost from using water transport
to road transport.
Incremental traffic cost to cross a river using boat is roughly estimated
based on the result of hearing survey at the bridge site currently crossing
with boat/raft. The current fare in riding a boat is averaging P20 per
passenger, the fee for transporting light vehicles in a raft is estimated at
P1,000 per vehicle and the time value in estimating the savings in loss of
time is based on the time cost per minute (converted into per hour basis) as
established by DPWH. The duration of flooding is estimated on the
average to be 14 days.
However, based on actual experiences, not all the traffic choose to cross
the river under this situation, some portion of existing traffic, those with
not-so-urgent trip nature, prefer to wait until the flood subsides. A general
assumption considered is that about 60% of total traffic prefers to cross the
river and 40% prefer to wait.
Average occupancy rate of each vehicle type is estimated as follows:
Car/Van
3.3 persons
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-17
Jeepney
Bus
Truck
15.9 persons
41.2 persons
1 person
AADTx1 =
AADTx2 =
AADTx3 =
AADTx4 =
d
=
Fo(x)
=
Fw(x)
Benefit in year x
Traffic volume of car/van in year x
Traffic volume of jeepney in year x
Traffic volume of bus in year x
Traffic volume of truck in year x
Number of days required to restore the bridge
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-18
Fo(x)
Fw(x)
10)
Where:
Bx
VOCi
AADTxi
d
=
=
=
=
Fo(x)
Fw(x)
L * d*(Fo(x) -Fw(x))
1,000
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
5-19
5.7
II
ISABELA 1
ISABELA 3
N. VIZCAYA
N. VIZCAYA SUB
N. VIZCAYA SUB
AURORA
AURORA
AURORA
AURORA
AURORA
AURORA
AURORA
AURORA
AURORA
BATAAN 2
BULACAN 2
PAMPANGA 1
PAMPANGA 1
BATANGAS I
BATANGAS III
BATANGAS IV
LAGUNA SUB
CAMARINES S 4
ALBAY 3
CAMARINES S. 1
CAMARINES S. 2
SORSOGON 2
Bridge Name
Urdas
San Antonio I
Quinarayan
Villamil
Tulong
Cabagan-Sta.
Maria
Ilot
Maddiangat
Siguem I
Biyoy
Amper
Dibutunan
Diarabasin
Borlongan
Diapalan
Dinadiawan A
Ditawini
Bungo
Gumaninang
Tuyo
Kay Tialo
Pampanga Delta
Cabetican
Cacauan
Pinagtulungan
Dona Alicia
Buenavista
Pagatpatan Coquit
Oas
Quitang
San Jose
Ariman
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
Length
(km)
81.0
75.0
30.0
112.0
455.0
EIRR (%)
w/o time
NPV
(P1,000)
97.6
19.7
24.0
44.6
33.0
507,552
16,374
20,986
180,025
399,093
600.0
17.3
136,970
35.0
216.0
60.0
160.0
224.0
672.0
180.0
84.0
63.0
84.0
84.0
252.0
63.0
36.0
96.0
240.0
150.0
30.0
40.0
60.0
30.0
75.0
36.0
25.0
60.0
54.0
30.5
31.2
46.9
26.2
23.8
25.2
25.3
25.1
25.7
25.7
25.7
22.5
76.1
30.3
42.3
41.8
20.6
89.4
52.3
68.4
65.8
44.6
23.6
25.0
30.8
21.6
33,262
173,142
121,249
77,514
94,320
266,981
87,132
48,206
41,934
49,835
49,835
84,791
422,865
86,041
396,551
224,416
36,322
142,993
77,548
143,856
76,772
110,218
17,842
12,983
37,763
11,981
5-20
III
NEGROS OCC 1
NEGROS OCC 1
NEGROS OCC 1
NEGROS OCC 1
NEGROS OCC 1
NEGROS OCC 5
CEBU 3
NEGROS OR. 1
NEGROS OR. 1
NEGROS OR. 1
ZAMBO CITY
ZAMBO CITY
IV
ZAMBO SBUGAY
ZAMBO SBUGAY
ZAMBO SBUGAY
ZAMBO SBUGAY
ZAMBO SBUGAY
DAVAO CITY 2
DAVAO CITY 2
DAVAO DS 1
DAVAO DS 2
DAVAO DS 2
DAVAO DS 2
DAVAO DS 2
DAVAO DS 2
DAVAO DS 2
AGUSAN DN 2
AGUSAN DN 2
AGUSAN DN 2
AGUSAN DS 1
SURIGAO DN 1
SURIGAO DN 1
SURIGAO DN 1
Himogaan
Da-an Lunsod
Patun-an
Talave
Madaboy
Hinigaran
Magsaysay
Malaga
Talaptap
La Libertad
Curuan I
Sinunuc II
(Maasin)
Guilinan
Tigbongabong
Madum
Siocon
Pisawak
Panglas
Panalum II
Digos I
Kipanan III
Lamidan
Manguile 1
Manguile 2
Caburan Small
Caburan Big
Buhang
Banza
Paypay Twin
Wawa'
Hinatigan I
Agona-Bangan
San Pedro
Implementation Program
Urgent Bridge Construction Project for Rural Development (UBCPRD), Phase II
140.0
50.0
96.0
34.0
34.0
155.0
120.0
50.0
60.0
150.0
30.0
35.0
20.9
17.5
19.2
28.9
31.4
50.3
18.7
21.6
18.5
41.07
170,427
16,188
10,779
9,536
31,746
128,223
325,892
24,769
46,252
22,761
47,153
46.0
35.48
58,274
68.0
36.0
45.0
140.0
180.0
30.0
30.0
42.0
60.0
60.0
75.0
45.0
30.0
30.0
100.0
90.0
90.0
231.0
32.0
32.0
46.0
26.28
22.46
112.02
117.60
58.33
50.82
53.75
68.19
64.77
32.62
100.53
124.84
128.27
50.82
28.97
107.61
117.21
134.37
41.07
35.48
26.28
38,497
14,995
311,546
302,549
112,078
100,287
102,410
164,989
106,837
34,842
116,582
795,507
722,112
154,594
82,911
136,639
135,445
190,503
47,153
58,274
38,497
5-21