ConstructionLaw:EoTRejection,conditionsofcontract,timelynotice

ConstructionLaw/ EoTRejection
Expert:JonathanL.Peralta8/29/2012

Question
DoestheEngineerhavetherighttorejecttheEoTclaimoftheContractorbysayingthattheContractorsMaster
Scheduleisnotapprovedoracceptedyet?
CanyourpleaseprovidemeotherreasonsthattheEngineermaybasehisrejectionofEoTclaim.
PleaseanswerbasedonFIDIC1999
Answer
DearPat,
UnlesssomethingiswrittenintheContract,theEngineerhas21daysfromthereceiptofContractor's
ProgrammetogivenoticetotheContractorifprogrammedoesnotcomplywiththeContractpursuantto
subclause8.3.
TheEngineershallrejecttheContractor'sEoTClaimifContractorfailedtosubmitatimelynoticeinaccordancewithsub
clause20.1
TheEngineershallrejectEoTClaimifprovisionsforEoTisdeletedunderGeneralConditions.
TheEngineermayrejectEoTClaimifit'sbaselessanddoesnotcomplywiththeConditionsofContract.
Hopetheabovehelps.Thanks.

http://en.allexperts.com/q/ConstructionLaw914/2012/8/eotrejection.htm