Beruflich Dokumente
Kultur Dokumente
Inspected
by
Consultant
Rejected
Revise/Resubmit
Approved
Inspected
by
Consultant
Rejected
Approved
Material can be
used at site
AFRA 03
Contractor Consultant
Relevance
Baseline Program-Updated
Monthly Report
Weekly Report
Daily Report
Communication Log
Drawing Log
PQP
Method Statement Log
Material Submittal Log
Material Inspection Log
Work Inspection Log
Technical Query Log
Variation Log
Change Log
Payment Certificates
KCC
High
High
Medium
Medium
HIgh
High
CVTEC
Client
Azizi
ProjectEmad
NA
NA
NA
NA
NA
NA
NA
High
Medium
High
High
High
Medium
High
High
High
High
HandOver Documents
High
NA
Contractor
AFRA 06
Consultant
SS Lootah
CVTEC
Client
Azizi
ProjectA. Masoud
MBCC
Barajeel
Client
Azizi
ProjectM. Mustafa
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
Received but of
different
company
NA
AFRA 22
Contractor Consultant
NA
NA
Interview with Mr. Emad, Project Manager for Aster AFRA 003
Question: Employer's Role
Answer: Reviewing Logs, Drawings, Random QA/QC check with consultant, Material Approval, Rand
Interview with Resident Engineer from CVTEC AFRA 003 & AFRA 006
Question: Consultant's Role
Answer: Inspections, Review of PC, NCR,
His replies where related to site history which he highlighted are late nomination of contractor, des
for lobby late, diff terms and condition between subcon, unreplied letters,
Interview with M. Mustafa, Project Manager for AFRA 022
Question: Employer's Role at closing stage
Answer: No handover done by consulant/ contractor, no handover between teams, lots of snags in
compnay, etc.
Dated: 22/12/2016
Dated: 25/12/2016
Dated: 25/12/2016
Observations
Project
Project manager
Project artifacts
ID
Attribute
1.1
1.2
1.3
1.4
2.0
2.1
2.2
3.0
3.1
3.2
3.3
Document
Control
System
3.4
3.5
4.0
4.1
4.2
Payment
Termination
of Contractor
HSE
Handover
1.0
2.0
3.0
4.0
No change register
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
13.0
No observation to Consultant
14.0
15.0
Project Impact
Action Plan/Resolution
Responsible
Project #
Sponsor
Updated
Date
Entered
Project Team
High
Project Team
High
Project Team
High
Project Team
High
Project Team
High
Project Team
Consultant
Project Team
Project Team
High
High
High
High
& 22
OPMENTS
Date to
Review
Date
Resolved