1. Introduction
This method statement is developed for sewerage reticulation construction work which is
crossing underneath the existing flexible pavement (parking lot area)
2. Scope of Work
The scope of this method statement shall consist: Cutting the existing flexible pavement prior to shoring/trench excavation work for
225mm dia. VCP pipe.
Installation 225mm dia. VCP pipe and sewer manhole.
Backfilling and making good the Dewatering and re-route the drainage route
within the sewer work
3. Work Sequences
The work sequence shall as follow as list below: Preliminaries
Survey and setting out.
Excavation work including sheet pile installations which were deep shoring
excavation work exceeding 3m deep encountered.
Installation of sewer manhole and 225mm dia. VCP pipe
Backfilling and making good
4. Method Statement
4.1 Preliminaries
Prior to proceeding of work, contractor shall mobilize required resources to carry
out works in accordance to the project requirement. Contractor shall ensure that
materials mobilized at site shall as per approved by Consultant.
Upon arrival of materials, Contractor shall check and ensure that relevant
materials delivered are conforming to specification. Materials shall be stock piled
and stored properly as to safe-guard the quality and security.
4.2 Survey and Setting Out
Prior to commencement of site survey and setting out, RFI shall be submitted
accordingly as to comply a project requirement and specification.
Location of manhole and sewer route alignment shall be marking and set out by
using spray paint.
Reduced level for excavation work shall be set out by placing 25mm x 25mm
timber pegs, coloured in red and embedded 300mm into ground.
Revision: 0
Page No: 3
Pegging and verification of location and level shall be carried out by contractors
surveyor and shall be verified by Engineer.
Revision: 0
Page No: 4
Backfilling work shall be carried out after concrete encasement had cured up to
the existing flexible pavement level of sub-base layer by using appropriate
compactor machine.
Once backfilling work up to existing sub-base deem satisfactory, sub-grade layer
shall be laid and compacted accordingly.
A bituminous pavement course shall be laid and compacted accordingly to match
up to exiting pavement.
All the thickness of each pavement course layer shall follow accordingly to the
construction drawing issued by consultant.
Any others service and structure which were disturbed during the construction
work shall be rectified accordingly to match with existing.
4.7 Testing
All necessary testing including CCTV test, flushing and sterling shall be done by
the specialist once the sewerage reticulation system completed.
The testing shall meet the S.O and relevant Authority satisfaction and approval.
Any defect to reticulation system shall to make good and leave in perfect order.
5. Machinery/Equipment
Major machinery/equipment for this scope of work shall include: Road cutter
Excavator
Compactor
6. Man Power
The following labour resources shall be deployed to the site for the surveying, excavation
and installation work.
Site Engineer / Supervisor
Safety Representative
Surveyor
Operator
Plumber
General Worker
7. Materials
Material will include:-
Revision: 0
Page No: 5
ii-
iii-
Night Work
- For night work, the area of work shall be adequately lit the facilitate production
works and movements on site. Warning lights, directive signs, reflective aids and
barriers shall be placed at suitable location to forewarn all potential hazards.
In summation, in order to achieve safe, free risk and healthy working environment,
including loss prevention, every practicable step must be taken by each and everyone
engaged in this project site.