Tunnel (CSST)
Contract No. ISD14-2036
Issued for Tender
Prepared for:
City of Ottawa
Prepared by:
Stantec Consulting Ltd.
CH2M HILL
Revision
0
Description
Revision Record
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
DIVISION 00
00010
00060
00100
00105
SECTION 00010
TABLE OF CONTENTS
PAGE 1 of 6
Pages
6
1
2
20
00200
00205
00400
00410
00450
00496
00496A
00803
00803A
DIVISION 01
01010
01015
01025
01050
01060
01080
01100
01117
01119
01120
01160
01200
01220
01310
01330
01353
01355
01420
01450
01510
01520
01560
01561
01635
01705
01710
01720
GENERAL REQUIREMENTS
Summary of Work
Contractors Use of Premises
Measurement and Payment
Coordination
Regulatory Requirements
Manufacturers Services
Special Project Procedures
Construction Sequences and Constraints
Preservation and Protection
Pre-construction and Post-construction Survey
Erosion and Sediment Control Plan
Alternatives
Project Meetings
Progress Schedules
Submittal Procedures
Special Procedures: Traffic Control
Waste Management and Disposal
References
Quality Control
Temporary Utilities
Construction Facilities
Temporary Barriers and Enclosures
Environmental Protection
Value Engineering Change Proposals
Contract Work Health and Safety Clauses
Tunnel and Shaft Safety
Preparation, Mobilization, Demobilization
Pages
8
9
00110
3
13
13
24
3
10
5
10
9
8
25
6
12
4
5
36
6
6
2
2
5
2
20
51
7
4
12
4
12
7
5
4
12
6
5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
01740
01750
01770
01780
01810
01820
Cleaning
Operations and Maintenance Manual
Closeout Procedures
Closeout Submittals
Commissioning
Demonstration and Training
DIVISION 02
02072
02140
02150
02200
02222
02226
02228
02231
02232
02260
02311
02315
02316
02362
02400
02405
02407
02410
02412
02415
02430
02437
02439
02440
02442
02444
02450
02455
SITE WORK
Geotextiles
Groundwater Control
Excavation Support System
Site Preparation
Demolition and Removal
Removal of Existing Asphalt Pavement
Blasting
Clearing and Grubbing
Tree Pruning
Mechanically Stabilized Earthen Slopes
Site Grading
Excavating, Trenching and Backfilling
Rock Removal
Dust Control
Shaft Construction
Steel Liner Plates
Shaft Secant Piles
Drilled Shaft
Shaft Backfill
Steel Sheet Piling
Tunnel Excavation by Tunnel Boring Machine (TBM)
Rock Reinforcement and Excavation
Pre-excavation Grouting from Surface
Pipe Jacking
Other Tunnel Excavation Methods
Tunnel and Shaft Ventilation and Utilities
Micropile Foundation
Contact Grouting
Geotechnical and Structural Instrumentation and
Monitoring
Vibration Monitoring
Water Mains
Sanitary Sewer and Odour Control Ducts
Storm Sewer
Maintenance Holes and Catch Basins
Aggregates: General
Aggregates: Landscaping
Granular Base
02480
02482
02511
02530
02630
02631
02701
02702
02721
SECTION 00010
TABLE OF CONTENTS
PAGE 2 of 6
3
5
2
6
23
5
Pages
3
13
7
2
6
3
9
5
5
7
3
13
4
2
14
3
12
8
7
4
30
10
15
8
7
9
17
12
26
13
4
13
10
4
3
4
4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00010
TABLE OF CONTENTS
PAGE 3 of 6
3
5
3
5
2
3
5
9
6
6
1
02723
02743
02770
02785
02821
02870
02901
02906
02911
02933
02980
Granular Sub-Base
Asphalt Concrete Paving
Concrete Walks and Curbs
Unit Paving
Chain Link Fences and Gates
Exterior Site Furnishings
Tree and Shrub Preservation
Trees, Shrubs and Ground Cover Planting
Topsoil Placement and Grading
Sodding
Restoration
DIVISION 03
CONCRETE
03100
03200
03202
03301
03345
03361
03362
03410
03420
03430
03700
Concrete Reinforcement
Steel Fibre Reinforcement for Concrete
Cast-in-Place Concrete (Shafts and Underground
Structures)
Cast-in-Place Concrete (Odour Control Structures)
Concrete Finishing and Curing
Shotcrete
Concrete Sealer
Precast Concrete Structures
Precast Concrete Tunnel Lining
Precast Modular Block Retaining Wall
Concrete Restoration
DIVISION 04
04051
04060
04080
04090
04220
04412
MASONRY
Common Work Results for Masonry
Masonry Mortar and Grout
Masonry Anchorage and Reinforcing
Masonry Accessories
Concrete Masonry Units
Granite Cladding
Pages
7
6
5
3
10
6
DIVISION 05
05121
05310
05500
05501
05502
METALS
Structural Steel for Buildings
Steel Deck
Metal Fabrications
Metal Fabrications - Architectural
Metal Fabrications - Landscaping
Pages
5
3
6
6
5
DIVISION 06
06100
06110
06600
Pages
2
3
9
03300
Pages
4
6
12
11
11
7
6
2
6
14
21
2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00010
TABLE OF CONTENTS
PAGE 4 of 6
DIVISION 07
07130
07210
07212
07272
07420
07465
07466
07550
07620
07710
07840
07900
Pages
DIVISION 08
08110
08331
08710
08711
Pages
7
3
2
2
DIVISION 09
09910
09930
FINISHES
Paints
Protective Coating
Pages
9
8
DIVISION 10
10441
10520
10990
FURNISHINGS
Exterior Signage
Portable Fire Extinguishers
Manufactured Specialties
Pages
3
2
2
DIVISION 11
11001
11120
11160
11201
11202
11230
EQUIPMENT
Engineered Fall Arrest System
Electric Motor Actuator
Process Valves and Piping
Stainless Steel Wedge-Style Slide Gates
Flap Gates
Stop Logs
Pages
2
13
6
8
9
9
DIVISION 13
13222
13251
13900
13910
13915
13930
13991
SPECIAL CONSTRUCTION
Grease and Mist Eliminator
Carbon Adsorption Odour Control
Instrumentation and Controls
Remote Processing Units
Alarm Autodialer / Security System
Structured Communications System
Control Panels and Junction Boxes
Pages
4
10
71
4
6
32
30
3
3
2
3
5
4
4
10
2
5
3
3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00010
TABLE OF CONTENTS
PAGE 5 of 6
DIVISION 14
14600
CONVEYING EQUIPMENT
Hoists and Cranes
Pages
3
DIVISION 15
15010
15053
15061
15072
15075
15081
15082
15101
15142
15151
15152
15187
15401
15411
15440
15480
15540
15615
15731
15766
15811
15820
15822
15824
15831
15851
15916
15950
MECHANICAL
Mechanical General Requirements
Motors, Drives and Guards for Mechanical Systems
Hangers, Bases and Supports
Vibration and Seismic Control for HVAC Equipment
Mechanical Identification
Thermal Insulation for Piping
Thermal Insulation for Ducting
Installation of Pipework
Domestic Water Piping
Drainage, Waste and Vent Piping: Cast Iron and Copper
Drainage Waste and Vent Piping - Plastic
Copper Tubing and Fittings Refrigerant
Plumbing Specialties and Accessories
Plumbing Fixtures and Trim
Plumbing Pump
Domestic Water Heaters
FRP Fans
Polyvinyl Chloride (PVC) Duct
Split Unit Air Conditioning
Unit Heaters - Electric
Ductwork Low Pressure to 500PA
Duct Accessories
Dampers Operating
Duct Heaters
HVAC Fans
Louvres, Intakes and Vents
Electric Heating and Cooling Controls
Testing, Adjusting and Balancing (TAB)
Pages
5
3
7
12
5
8
5
4
4
2
2
4
8
4
4
3
6
7
4
4
5
4
3
2
5
2
3
5
DIVISION 16
16010
16051
16052
16053
16054
16061
16062
16070
16071
16122
16131
ELECTRICAL
Electrical General Requirements
Installation of Cables in Trenches and in Ducts
Concrete Encased Ducts
Metering and Switchboard Instruments
Coordination, Short Circuit and Device Evaluation
Grounding Primary
Grounding Secondary
Electrical Demolition
Fastenings and Supports
Wires and Cables (0-1000V)
Splitters, Junction and Pull Boxes
Pages
7
2
2
4
8
2
2
2
2
5
3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
16132
16133
16141
16151
16153
16223
16261
16262
16275
16370
16412
16414
16441
16491
16505
16531
16536
SECTION 00010
TABLE OF CONTENTS
PAGE 6 of 6
2
4
3
1
1
15
4
10
2
11
1
3
3
2
5
2
3
Appendices:
1.
CCDC 4 Unit Price Contract 2011
2.
Geotechnical Data Report
3.
Geotechnical Baseline Report
4.
Phase II Environmental Site Assessment (ESA) Report
5.
Hydrogeological Report Assessment for a Permit to Take Water Application
6.
Ministry of Environment DRAFT Permit to Take Water (PTTW) - To be provided by Addendum
Ministry of Environment ECA
7.
8.
IOS As-Built Drawings
9.
RCI As-Built Drawings
10.
Real Property Sketches (Referenced in Section 01015 Attachment A).
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00060
PROJECT DIRECTORY
PAGE 1 of 1
OWNER:
City of Ottawa
110 Laurier Avenue
Ottawa, Ontario
K1P 1J1
Purchasing Officer:
Louise Amyotte-Baker
City of Ottawa
Supply Management Division
100 Constellation Cres., 4th Floor West
Ottawa, Ontario
K2G 6J8
Phone:
(613) 580-2424 Ext. 21750
Fax:
(613) 560-2126
E-mail:
Louise.Amyotte-Baker@ottawa.ca
Project Manager:
Randy Dempsey, P.Eng.
City of Ottawa
Infrastructure Services Department,
100 Constellation Cres., 6th Floor West
Ottawa, Ontario
K2G 6J8
Phone:
(613) 580-2424 Ext. 14102
Fax:
(613) 560-6064
E-mail:
Randy.Dempsey@ottawa.ca
CONSULTANTS
Prime Consultant: Stantec Consulting Ltd.
Project Manager: Adrien Comeau, P.Eng.
400-1331 Clyde Avenue
Ottawa, ON K2C 3G4
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Form of Contract
.1
SECTION 00100
AMENDMENTS TO THE CCDC4 2011 AGREEMENT
PAGE 1 of 2
The form of contract is the agreement as defined by the Canadian Construction Documents Committee,
CCDC 4 - Unit Price Contract 2011 (available from the CCDC at www.ccdc.org) and as amended by this
section and Section 00105.
The Agreement between the City and Contractor, including the definitions
Addenda, as issued
In paragraph A-5.3.1 (1), DELETE 2% per annum and REPLACE with 0% per annum.
.2
In paragraph A-5.3.1 (1), DELETE 4% per annum and REPLACE with 0% per annum.
.2
In paragraph A-5.3.2:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00100
AMENDMENTS TO THE CCDC4 2011 AGREEMENT
PAGE 2 of 2
In the first line, DELETE and in the manner prescribe by paragraph 5.3.1 of this article,
And REPLACE with of Prime plus 1%.
4
Definitions
.1
Paragraph 4, Consultant:
ADD after the last sentence The contract documents may refer to Consultant, Engineer, Owners
Agent and Contract Administrator. All these have the same meaning as Consultant as defined in
GC2.2.
.2
Paragraph 9, Contractor:
ADD after the last sentence The Contractor shall be the constructor as defined within the Occupational
Health and Safety Act, R.S.O. 1990, c.O.1, as amended, (the Act) subject to sub-clause GC 3.2.1
Construction by Owner or other Contract.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 1 of 20
.2
The Agreement between the City and Contractor, including the definitions
Addenda, as issued
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 2 of 20
The City shall provide the Contractor up to ten (10) copies of the Contract Documents to perform
the Work. Should the Contractor require additional sets, the contract documents will be made
available to the contractor at their own expense."
GC 1.4 Assignment
.1
No Change in Ownership of the Contractor, or of any person with any form of direct,
indirect, beneficial or other ownership interest in the Contractor, shall be permitted:
.1
.2
.2
Subject to Section 6.2.4.1 no Change in Control of the Contractor, or of any person with
any form of direct, indirect, beneficial or other ownership interest the Contractor, shall be
permitted without the prior written consent of the City not to be unreasonably withheld or
delayed.
.3
This Section shall not apply to a Change in Ownership or Change in Control of persons
whose Securities evidencing ownership or any other ownership interests are listed on a
recognized stock exchange.
.4
Whether or not the Contractor is required to obtain the Citys consent pursuant to this
Section, the Contractor shall provide notice to the City of any proposed Change in
Ownership or Change in Control of the Contractor, or of any person with any form of
direct, indirect, beneficial or other ownership interest in the Contractor, as the case may
be, within 5 Business Days after such Change in Ownership or Change in Control, and
such notification shall include a statement identifying, in respect of the relevant owners in
the ownership interests of the Contractor, or of any person with an ownership interest in
the Contractor, as the case may be, the holdings prior to and proposed holdings following
the Change in Ownership or Change in Control, respectively.
In paragraph 2.2.3, AMEND the second sentence by adding the following phrase to the end of the sentence:
"... upon the request of the Contractor.".
.2
At paragraphs 2.2.7; DELETE the words: "Except with respect to GC 5.1 - FINANCING INFORMATION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 3 of 20
At paragraphs 3.2.2 and 3.2.3; DELETE the words: "When separate contracts are awarded for other parts of
the Project, or and between the words performed by ADD on Site
.2
At paragraphs 3.2.2.2; ADD the words to the end of the sentence: "upon notifying the contractor in writing
accordingly.
.3
the Owner may assign the methods and manner (where applicable) of the performance of
the Work, the coordination and scheduling of the performance of the Work and the safety
training in respect of the performance of the Work to the Rideau Transit Group General
Partnership (in this section, RTG) pursuant to an agreement between the Owner and
RTG for the design, construction, financing and maintenance of the Confederation Line
light rail transit system in Ottawa (in this section, the OLRT Contract);
.2
the Contractor shall comply with the instructions of RTG relating to matters of health and
safety, methods and manner (where applicable) of the performance of the Work, and
coordination and scheduling of the performance of the Work with work undertaken by
RTG in respect of the OLRT Contract;
.3
if directed by the Owner, RTG shall have responsibilities as the constructor under the
Ontario Health and Safety Act (Ontario);
.4
if:
.1
the Contractor causes any damage to RTGs work under the OLRT Contract;
.2
RTG incurs any additional costs or there is any delay in the schedule or
performance of its works as a result of the Contractor not complying with the
coordination, scheduling and safety instructions of RTG; or
.3
RTG incurs any additional costs or there is any delay in the schedule or
performance of its work under the OLRT Contract as a result of the performance
of the Work,
then the Contractor shall be responsible for all impacts and consequences of such delay or
additional costs, including to indemnify and to hold harmless the Owner for any change
order issued under the OLRT Contract or amendment made to the OLRT Contract in
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 4 of 20
respect thereof, or for any rights or remedies enforced by RTG against the Owner under
the OLRT Contract in respect thereof.
.5
introduction and storage of equipment, tools and other materials on site by the
Contractor;
.2
.3
.4
ADD to end of 3.5.2 and the owner reserves the right to request more frequent schedule updates of the
project, when the project does not appear to be capable of being completed within the defined time frames of
the contract.
GC 3.6 Supervision
.1
.1
if directed by the Owner, the Contractor shall, in good faith and acting reasonably,
negotiate and enter into any agreements with the Owner and/or RTG that are necessary or
desirable to effect the foregoing requirements of this Section or which are otherwise in
respect of the subject matter hereof, including:
ADD to end of 3.6.1 and the owner shall be notified in writing for consideration by the Engineer prior to
changing the Supervisor.
The Contractor shall be required to produce and demonstrate to the Engineer on a monthly basis
that Contractor has kept the records of the adjustments of the work on a set of Record drawings
kept on site.
.2
The contractor shall on a monthly basis issue a certificate with their monthly progress payment
request that the Record drawings are complete and up to date as reflected in the work certified to
date.
.3
As part of the project breakdown, the Contractor will identify a schedule of values, as defined in
GC5.2.5, associated with the monthly Record drawing update with a value of a 0.5% of the project
and billed on a monthly basis.
.4
When the Contractor requests for substantial performance, the Contractor shall submit a legible
copy of the marked up Record drawings.
.5
The Contractor will submit operation and maintenance instruction manuals updated and revised to
show construction revisions upon submittal of the marked up record drawings.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
10
11
12
ADD 5.2.8 as follows: The Contractor shall include an updated work schedule with each progress billing
submission as required in Section 01310, Progress Schedules otherwise payment of progress billing shall be
held back until the updated schedule is submitted.
.2
ADD 5.2.9 as follows: The Contractor shall include an original signed Statutory Declaration and valid WSIB
Certificate of Clearance with all progress payments (note: a statutory declaration is not required on the 1st
Progress Draw).
.2
In paragraph 5.5.4; DELETE the first sentence in paragraph 5.5.4 and SUBSTITUTE the following:
" In a common law jurisdiction, the holdback amount authorized by the certificate for payment of the holdback
amount is due and payable ten (10) days following the expiration of the holdback period stipulated in the lien
legislation applicable to the Place of Work."
.3
DELETE the third and fourth lines in paragraph 5.6.1 and SUBSTITUTE the following:
"the City may pay the Contractor the holdback amount retained for such subcontract work, or the Products
supplied by such Supplier, ten (10) days following the expiration of the holdback period for such work"
.2
13
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 5 of 20
DELETE in the second line of paragraph 5.7.4 "5 days" and SUBSTITUTE "30 days".
All approved change orders must account for revisions to added or credited time to the Contract
Schedule. Change Orders approved without the indication of a Change in time period of Contract
cannot be contested at a later date. Additional or credit of time to contract must be represented
with financial credit/extra associated with extension/reduction of contract time or overtime hours
worked.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 6 of 20
6.2.6 This does not prevent the contractor from addressing a claim for cumulative time impact
associated with multiple changes.
.1 Should it be demonstrated that the cumulative impact of multiple individual Change Orders and
should the claim be supported with demonstrated documentation of the variation on the approved
schedule, then the Contractor is entitled to submit costs to the Consultant within 15 days of
notifying the Owner of the change to the schedule.
6.2.7 The adjustment in the Contract Price for a change carried out by way of a Change Order or a Change
Directive as provided in GC 6.2 CHANGE ORDER and GC 6.3 CHANGE DIRECTIVE, shall be in
accordance with the rates and conditions stipulated in this Supplementary Condition.
.1
All labour, equipment, rental of equipment or tools, materials, subcontracts and outside
services to be charged as a result of changes to the scope of the Work will be subject to prior
authorization by the City.
.2
For the determination of the costs associated with Change Orders and Change Directive, the
following provisions will apply:
2.1
The City will reimburse the contractor for "Field Labour Costs" as the actual direct
wages or salaries of the workers, up to and including working foremen, plus actual
payroll burdens, but not including additional cost for full time site superintendent unless
it is clearly demonstrated that additional time above and beyond the extent of the Time
for Completion of Contract / Work.
(i) Payroll Burden" means the payments in respect of workers compensation, vacation
pay, unemployment insurance, public liability, and property damage insurance,
sickness and accident insurance, pension fund and such other welfare and benefit
payments as form part of the Contractor's normal labour costs and will include any
applicable cost or expense which has been incurred by the Contractor for food,
lodging and similar items.
(ii) The Contractor will provide the City with the information required to calculate Field
labour rates within 14 days of the date of Contract Award.
(iii) Field Labour rates for premium portion overtime will be fixed and remain firm for
the duration of this Contract and will not be subject to escalation unless prior
written approval is obtained from the City, and such approval will not be
unreasonably withheld.
(iv) Only labour personnel up to and including working foremen will be chargeable on
additional work and then only to the extent such personnel are directly engaged on
the additional work. The City will not pay for supervision beyond the working
foreman level, nor will it pay for administration or management time spent on
additional work.
2.2
The City will pay the Contractor for the actual cost of materials installed or used directly
in connection with the Work (excepting materials supplied by the City). Payment will be
for the actual cost to the Contractor delivered at the site. Copies of invoices from
delivery companies or transporters' must accompany the Contractor's billing.
2.3
The City will pay for the cost of rentals for Contractor's owned equipment already on
site will be based on the actual time such equipment is used beyond the period the
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 7 of 20
equipment was expected to be on site, exclusive of operators time, and on the following
basis:
(i) At established hourly, daily, weekly or monthly rental rates.
(ii) The stipulated rental rates will apply when the number of hours the equipment is
operated does not exceed 175 hours in any one month, or does not exceed 40 hours
in any one week, or does not exceed 8 hours in any one day.
(iii) For rental rates quoted, no differentiation will be made between equipment owned
by Contractor or rented by Contractor from third parties.
(iv) For equipment not already on site, rental agreements and copies of invoices from
equipment Rental Company must accompany the Contractors billing.
.3
Where the Contractor arranged for Work to be carried out by a Subcontractor or its own forces
and has received prior approval from the City prior to the commencement of the Work, the
City will pay the Contractor the approved cost of the Subcontractor's work, plus a 10%
mark-up to the Contractor for all administration, supervision, bonding premiums, record
documentation, overheads and profits.
.4
The City will reimburse the Subcontractor via the contractor or the contractors own forces for
actual Field Labour, material and equipment costs of work performed plus a 15% mark-up to
cover the cost of small tools, expendables and consumables, field overhead, supervision above
working foreman level and all other indirect labour and materials costs not defined as
reimbursable. Expendables and consumables includes all items which are consumed in the
performance of the Work whether or not such materials are incorporated in the permanent
works.
.5
The City will provide for an additional 5% mark-up to the Subcontractor via the contractor for
the profit and overhead associated with Change Orders and Change Directives that are a result
of the Subcontractors necessity to subcontract out a portion of the work.
.6
Maximum mark-up permitted on any Change Order or Change Directive will not exceed an
aggregate total of 35%.
.7
When Change Orders or Change Directives are agreed by the owner to proceed on a time and
material basis or the contractor is preparing a claim against the work, the Contractor must:
.1
Provide daily work records prepared by the Contractor and reporting the labour and
equipment employed and the material used on any specific portion of the Work, to be
reconciled with and signed by the Engineer each day, whenever, in the opinion of the
Engineer, such records are required.
.2
Maintain and keep sufficiently complete and accurate books, payrolls, accounts and
records relating to the Work or any extensions or additions thereto or claims arising
there from to permit the verification and audit thereof and the Contractor will have no
claim for repayment of any nature and kind whatsoever therefore, unless such books,
payrolls, accounts and records have been so maintained and kept.
.3
Submit to the City, at the end of each Working Day a detailed report showing the
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 8 of 20
names, occupations and hours worked of all personnel employed that performed work
on a time and material basis, the material supplied and the description and hours of use
for equipment and tools employed.
.4
14
The City, its Engineer or their agents may inspect and audit the books, payrolls,
accounts and records of the Contractor at any time during the period of the Contract
and at any time thereafter as deemed necessary, and the Contractor will supply payrolls
and any other records required whenever requested by the City.
DELETE paragraphs 6.4.1 through 6.4.3 and REPLACE with new paragraphs 6.4.1 through 6.4.3:
6.4.1 The Contractor shall notify the Consultant in writing of the following conditions, known as
concealed or unknown conditions, but hereinafter called changed conditions or differing site
conditions, promptly upon their discovery and before they are disturbed, and in no case shall such
notification be made later than five (5) calendar days after such conditions are discovered:
a)
Subsurface or latent physical conditions in the Place of the Work differing materially
from those indicated in the Contract Documents; or
b)
Unknown physical conditions in the Place of the Work of an unusual nature differing
materially from those ordinarily encountered and generally recognized as inherent in
Work of the character provided for in the Contract Documents.
The Contractors notification shall provide sufficient description of the conditions as encountered
and how such conditions represent changed conditions so as to allow the Consultant to review and
investigate such conditions as provided in GC 6.4.3.
6.4.2 No claim by the Contractor related to shaft, tunnel, trench or other open-cut excavation shall be
allowed under the Concealed or Unknown Conditions provisions unless the Contractor submits
documentation that demonstrates that such alleged conditions are materially different from those
conditions identified in the Contract Documents and are more adverse than those conditions. The
Contractor shall submit such documentation within 30 calendar days after notification to the
Consultant that the Contractor believes a material difference exists. The Contractor may conduct
any investigations as are reasonably necessary for demonstrating that a material difference exists,
and any and all costs incurred by the Contractor to conduct such investigations shall be borne by
the Contractor unless the Consultant agrees that a material difference in conditions does exist and
that such conditions have a cost and/or time impact. If the Consultant agrees that there is a
material difference that impacts the Contractors cost and/or time of performing the Work,
payment for investigation(s), including necessary testing, to document the material difference will
be paid for by the Owner as part of the cost impact directly associated with the materially different
conditions. Payment will be made by the Owner for reasonable and customary prices for geologic /
geotechnical investigation(s) and testing. The Contractor is encouraged to review such planned
investigations and/or testing with the Consultant prior to execution of the same. The Consultant
will be sole judge of what is reasonable and customary.
In addition to the documentation to support the Contractors position that concealed or unknown
conditions exist, the Contractor shall also submit documentation, backup, justification, and
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 9 of 20
compensation, as is necessary, for the alleged impact to Contractors cost of and/or time required
for performance of the Work. Such documentation shall be submitted within the 30-day period
cited above.
The Owner and Consultant agree a priori that the full extent of the alleged concealed or unknown
conditions may not be known within the 30-day period cited above for submission of
documentation. If the full extent of the alleged concealed or unknown conditions is not known
within the 30-day period, the Contractor shall submit such documentation as may be available
within the required period. The Contractor shall submit all additional documentation as may be
required to support its position that materially different conditions exist and to document the cost
and/or time impact on the performance of the Work within 30 calendar days of the date on which
the full extent of such conditions is determined. The Contractor shall promptly notify the
Consultant when the full extent of the alleged changed conditions is known.
The Contractor expressly agrees to maintain Daily Work Records as required by GC 6.3.9 to
include detailed daily labor, material, production, and equipment logs defining hours and costs for
all periods of Contractor performance representing claimed concealed or unknown site conditions.
These logs shall fully separate bid Contract Work from Work associated with addressing and
overcoming claimed concealed and unknown conditions. These Daily Work Records shall
constitute documentation of performance, and the Contractor and Consultant agree to attempt to
reconcile their respective Daily Work Records on a daily basis. Such reconciliation of Daily Work
Records shall not be construed by the Contractor to indicate acceptance of the Contractors claim
of concealed or unknown site conditions or cost or time impact to the Contractors performance of
the Work. The failure of the Contractor to maintain Daily Work Records shall render the
Consultants Daily Work Records as definitive.
6.4.3
The Consultant shall, after Contractor notification of the existence of concealed or unknown
conditions, promptly review the conditions, and if the Consultant finds that such conditions do
constitute changed conditions as defined in GC 6.4.1 and cause an increase in or decrease in the
Contractors cost of, or the time required for, performance of any part of the Work defined in the
Contract Documents, an equitable adjustment shall be made, and the Contract Documents shall be
modified in writing in accordance with the provisions of General Conditions Part 5 Payment and
other applicable paragraphs within Part 6 Changes in the Work.
The Consultants review will overlap with the period of time during which the Contractor is
required to assemble and submit initial and final documentation regarding the claim. Within 30
calendar days of the receipt of the Contractors initial documentation, the Consultant will advise
the Contractor, in writing, of the Consultants initial opinion as to the existence of changed
conditions. The Contractor acknowledges that a final determination cannot be made until after the
Contractor submits its final documentation as required in GC 6.4.2. The Consultant will advise
the Contractor of the Consultants final determination, in writing, within 30 calendar days of
receipt of the Contractors full documentation of the nature of and cost and/or time impacts of the
alleged concealed or unknown conditions. Alternatively the Consultant may request able infraction
or enter negotiations with the Contractor over the cost with respect to time impacts,
If the Consultant determines that concealed or unknown conditions do not exist, and therefore,
there is no justification for an adjustment in Cost or Time of the Work, the Consultant will so
advise the Contractor in writing. Should the Contractor disagree with such determination, the
Contractor agrees to initially engage the Consultant in negotiations and then implement other
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 10 of 20
dispute resolution provisions of Part 8 Dispute Resolution of the General Conditions, as modified
by these Supplementary Conditions, to resolve the dispute regarding the Consultants
determination.
No claim by the Contractor for an equitable adjustment hereunder shall be allowed if asserted
after the date on which the Substantial Performance Certificate is issued by the Consultant.
6.4.3
15
GC 6.5 Delays
.1
.2
extended head office overhead and profit for the work at a reasonable rate demonstrated by
the Contractor.
Upon notice of Delay, the Contractor shall demonstrate the impact of the delay clearly identified
on each subsequent schedule update.
17
The costs which the Contractor may, from time to time, be entitled to pursuant to the provisions
of paragraphs 6.5.1, 6.5.2 or 6.5.3 shall not include loss of profits or consequential damages and
"reasonable costs" shall be specifically defined as documented, itemized costs directly
attributable to delay and categorized as follows:
16
For greater certainty, the Owner may avail itself of the dispute resolution provision under this
Contract in respect of any matters under this Section 6.4.
ADD to the first sentence after the first word claim other than covered by GC 6.5 Delays.
.2.
If, in the opinion of the City or Citys Agent, the Contractor fails to satisfactorily carry out the
obligations and duties of an employer and/or constructor as required under the Occupational
Health and Safety Act, the City reserves the right to immediately notify the Contractor in writing
of the alleged default.
.2
Upon issuance, the notice of alleged default shall be signed off by both the Contractor and the
City or Citys Agent.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
.3
18
19
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 11 of 20
In the case of an alleged default under GC 7.1.2.1, upon receipt of written notice, the Contractor
shall take action forthwith to correct the default to the satisfaction of the City or Citys Agent.
In the case of an alleged default under GC 7.1.2.1, and should the Contractor disagree with the
alleged default, the City or Citys Agent reserves the right to terminate all or part of the work and
immediately contact the Ontario Ministry of Labour to render a decision.
.2
In the case of an alleged default under GC 7.1.2.1, should it be determined by the Ontario
Ministry of Labour that a default did not occur, the City will reimburse all expenses to the
Contractor for the termination of all or part of the work.
.2
In paragraph 7.2.3.4 DELETE in the first and second lines the words "except for GC 5.1 - FINANCING
INFORMATION REQUIRED OF THE OWNER".
20
.2
ADD new paragraph 8.2.2 and RENUMBER current paragraphs 8.2.2 and 8.2.3 to be 8.2.3 and 8.2.4:
"8.2.2 This Contract shall include a Dispute Review Board. The specific details and requirements for engaging
the Dispute Review Board and for its operation during the period of the Contract are provided in Section
00803 Dispute Review Board."
.3
ADD new paragraph 8.2.5 and RENUMBER current paragraphs 8.2.4 through 8.2.8:
8.2.4 As provided and following the requirements and procedures stipulated in Specification Section 00803,
Dispute Review Board, prior to engaging in either mediation or arbitration to resolve disputes, either the
Contractor or Owner shall refer a dispute to the Dispute Review Board for action and resolution.
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 12 of 20
the Project Mediator to assist the parties to reach agreement on any unresolved dispute. The mediated
negotiations shall be conducted in accordance with the Rules for Mediation of Construction Disputes as
provided in CCDC 40 in effect at the time of bid closing.
.5
21
22
23
In RENUMBERED paragraphs 8.2.6 through 8.2.10, REVISE paragraph references to other paragraphs
within the current paragraphs of GC 8.2 to match the paragraph renumbering described above.
.2
.3
24
.4
.5
.6
25
The reporting requirements of this provision do not relieve the Contractor from its legal
responsibilities pursuant to any municipal, provincial or federal legislation."
ADD the following to the end of the first sentence in paragraph 10.2.3:
"which were in force at the date of bid closing, and those in force at the time of execution of works."
GC 11.1 Insurance
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 13 of 20
Contractor is insured for its blasting operations until the date of acceptance of the entire work by the City. If
the Contractor employs Subcontractors for blasting operations, the Contractor shall ensure that its subcontract
includes the requirements for blasting coverage as provided herein and the additional insureds required by this
Contract".
.2
The Contractor shall provide the City with an original Certificate of Insurance and shall ensure
that the City at all times is in receipt of a valid Certificate of Insurance for all the policies
required by GC 11.1. The Contractor shall ensure that the Certificate of Insurance states that
thirty (30) days prior written notice shall be given to all the named insureds in the event of any
changes, cancellation or termination of the policies. The City's receipt and acceptance of a
Certificate of Insurance is in no way an approval of the Contractor's policy or policies of
insurance, and does not affect the obligations to insure set out in this GC 11.1 -INSURANCE.
The City may withhold payment of any monies due to the Contractor under this or any other
contract until the Contractor has provided the City with a valid Certificate of Insurance as
required by this condition."
26
GC 12.1 Indemnification
.1
.2
any breach of a representation or warranty by the party from whom indemnification is sought; and
.3
.4
.5
the limits of indemnity set forth in paragraphs 12.1.2.1 and 12.1.2.2 shall not apply in cases of
willful misconduct or deliberate acts of wrongdoing.
arising out of the Contractor's performance of the Contract which are attributable to a lack of or
defect in title or an alleged lack of or defect in title to the Place of the Work, provided that no
indemnity is provided by the Owner, and no claim shall be asserted by the Contractor, in respect
of any matter which is set out as a restriction, encumbrance or other limitation on the Place of
Work in this Contract, including schedule constraints and use of the premises constraints outlined
in Section 01015 (Contractors Use of Premises) and Section 01117 (Construction Sequences and
Constraints).
Without limiting or impairing any indemnity by, or other obligation of, the Contractor in this
Contract:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 14 of 20
.1
The Contractor shall indemnify and save harmless the Owner from and against all
claims, demands, loss, costs, damages, suits and actions whatsoever, including any claim
for personal injury and any loss or for damage to property, which arise out of or in
connection with the entry onto and use of the Site 6 staging area and access through
PWGSC property north of Wellington Street, including any made by PWGSC against the
Owner. If PWGSC is made a party to any litigation commenced by or against the Owner
or the Contractor, the Contractor will promptly indemnify and hold harmless the Owner,
PWGSC and its agents and will pay to the Owner (whether for its own benefit of for
PWGSC) all costs and expenses incurred or paid by Owner in connection with such
litigation, including any costs and expenses claimed by PWGSC against the Owner.
.2
The Contractor hereby releases and discharges the Owner and PWGSC, and their
respective employees and anyone for whom it is responsible in law, from any claim,
demand or action whatsoever as a result of any loss, damage, injury or death suffered by
the Contractor or any of its contractors, employees and anyone for whom it is responsible
in law, howsoever caused, arising from use or occupancy of Site 6 staging area and access
through PWGSC property north of Wellington Street. This paragraph constitutes a full
waiver and release in favour of the Owner and PWGSC for any such claim.
.3
Neither the Owner nor PWGSC warrants safe access to, on or under the Site 6 staging
area and access through PWGSC property north of Wellington Street. Such access or the
presence of the Contractor, its employees, contractors, servants, licensees and agents on
Site 6 staging area and access through PWGSC property north of Wellington Street shall
be solely at the risk and peril of the Contractor and the Contractor assumes all risk of loss,
damage to property of, or injury to itself, its servants, contractors, agents, employees or
Contractor in connection or in any way related therewith. Neither the Owner nor
PWGSC shall have responsibility for any such loss, damage or injury, or for any safety
related issues. Neither the Owner nor PWGSC has made and does not make any
representation as to the present or future conditions of the Site 6 staging area and access
through PWGSC property north of Wellington Street. The Contractor covenants,
represents and warrants that any employee, contractor, servant, agent or licensee that will
access the real property will be adequately trained and at all times comply with all
applicable health and safety laws and requirements.
.4
For greater certainty, the indemnities and releases in this paragraph 12.1.7 are not
subject to the limitations in paragraph 12.1.3.
Without prejudice to the parties rights in respect of payments or liquidated damages provided for
herein, the indemnities under this Contract shall not apply and there shall be no right to claim
damages for breach of this Contract, in tort or on any other basis whatsoever, to the extent that
any loss claimed by either party is:
.1
.2
for loss of profits, loss of use, loss of production, loss of business or loss of business
opportunity sustained by either party and not by third parties; or
.3
is a claim for consequential loss or for indirect loss of any nature suffered or allegedly
suffered by either party.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.7
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 15 of 20
Subject to the indemnities provided herein, neither party shall be liable in tort to the
other party in respect of any negligent act or omission of any such person relating to or in
connection with this Contract and no such person shall bring such a claim.
.2
Notwithstanding any other provision of this Contract, and except to the extent
recovered under any of the insurances required pursuant to this Contract, neither Party
shall be entitled to recover compensation or make a claim under this Contract, or any
other agreement in relation to the Project, in respect of any loss that it has incurred (or
any failure of the other party) to the extent that the party has already been compensated in
respect of that loss or failure pursuant to this Contract, or otherwise.
.3
The Owner and the Contractor shall at all times take commercially reasonable steps to
minimize and mitigate any loss for which the relevant party is entitled to bring a claim
against the other party pursuant to this Contract.
27
28
29
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 16 of 20
c.R.31 as amended, it will obtain and provide the City with a duplicate copy of a valid certificate issued
by the Minister of Revenue indicating that the Contractor has fulfilled its obligation to deposit funds or a
guarantee bond with the Treasurer of Ontario to secure payment of the tax payable in respect of tangible
personal property consumed or used pursuant to or in the carrying out of the Contract.
15.2 The non-resident Contractor will provide the certificate within seven (7) Working Days of the date the
City requests it. If the non-resident Contractor fails to provide the appropriate certificate within the time
limit specified by this condition, the City may, in addition to any other remedies which it might have,
withhold from payment to the non-resident Contractor, an administration fee, to be determined by the
City, to cover costs incurred by the City to comply with the requirements of the Retail Sales Tax Act."
30
GC 16 Integrity Provisions
.1
31
(1)
no Restricted Person has or will have Direct or Indirect power or control over the Contractor in
relation to the decisions, management, actions or policies of the Contractor or in relation to the
operation, management and ownership of the Project;
(2)
no Restricted Person has or will have directly or indirectly, an Economic Interest in the
Contractor or the Project;
(3)
(4)
in respect of the Project, it and its subcontractors have not contracted with, and will not
contract with, any person that is a Restricted Person.
the Contractor shall provide and shall cause each subcontractor to provide to the Owner all
information, reports, documents, records and the like, in the possession of, or available to, the
Contractor as the Owner may reasonably require from time to time for any purpose in connection
with this Contract. The Contractor shall use commercially reasonable efforts to ensure that, for
such purpose, all such information, reports, documents, records and the like in the possession of,
or available to the subcontractors shall be available to the Contractor and the Contractor shall
include relevant terms in all subcontracts to this effect;
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 17 of 20
.2
all information, reports, documents and records in the possession of, or available to, the
Contractor which are required to be provided to or available to the Owner hereunder, shall be
subject and open to inspection and audit by the Owner at any time and from time to time, which
inspection and audit shall take place during normal business hours and at the Contractors normal
places of business unless the Owner and the Contractor otherwise agree. The Owner shall also
have the right to monitor and audit the performance of any and all the activities within the Work
wherever located, and the Contractor shall cooperate with, and shall require each subcontractor to
cooperate with, and provide access to the representatives of the Owner monitoring and auditing
the Work, including providing them with access and copies (at the Owners reasonable cost) of
all relevant information, reports, documents and records pertaining to the performance of the
activities within the Work. Except as otherwise provided herein, all of the Owners costs for the
inspections, audits and monitoring shall be borne by the Owner;
.3
in conducting an audit of the Contractor hereunder or as otherwise provided under this Contract,
the Owner shall have all rights necessary or incidental to conducting an audit, including the right
to have access to and inspect and take copies (at the Owners reasonable cost) of all books and
records of the Contractor required to be provided to or available to the Owner hereunder, upon
reasonable notice and at reasonable times. The Contractor shall fully cooperate with the Owner
and its auditors in the conduct of any audits, including by making available all such records and
accounts in existence at that time as they may require to perform a full and detailed audit, and the
Contractor further agrees to promptly review and settle with the Owner all matters arising from
such audits, including the refunding of monies to the Owner where applicable. At the reasonable
request of the Owners auditors, the Contractor shall provide such information, reports,
documents and records as the Owners auditors may reasonably require;
.4
the Owners rights pursuant to this section shall be in addition to, and shall not limit, any other
audit, information, inspection or similar rights under this Contract; and
.5
the Owners rights pursuant to this section shall not limit or restrict any governmental authoritys
(including its own) right of review, audit, information or inspection under applicable law. Upon
notice to the Contractor, the Owners right pursuant to this section may also be exercised by Her
Majesty the Queen in Right of Ontario, the Auditor General of Ontario, Her Majesty the Queen
in Right of Canada, the Auditor General of Canada and anyone acting on their behalf without the
requirement for further action on the part of the Owner.
17.2 Without altering, impairing or limiting any other obligations of the Contractor in the Contract
Documents, the Contractor acknowledges and agrees that throughout the term of the Contract, without
any prejudice to any access rights of any such person as a member of the general public or pursuant to
applicable law, the Owner and its agents and representatives shall have unrestricted access to the Place
of Work and any workshop where materials, or equipment are being manufactured, prepared or stored at
all reasonable times during normal working hours, including for the purposes of general inspection or
audit, or of attending any test or study being carried out in respect of the Work, or to fulfill any
statutory, public or other duties or functions. In exercising their access rights under this section the
Owner shall (i) provide reasonable prior notice appropriate to the circumstances (other than for any
offices or other facilities provided at the Place of Work for the use of the Owner or its agents and
representatives); and (ii) comply with all relevant safety procedures and any reasonable directions with
regard to site safety that may be issued by or on behalf of the Contractor from time to time. With the
prior authorization of the Owner, any of the Her Majesty the Queen in Right of Ontario, the Auditor
General of Ontario, Her Majesty the Queen in Right of Canada, the Auditor General of Canada and
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 18 of 20
anyone acting on their behalf shall also have access to the Place of Work and other sites.
17.3 Without altering, impairing or limiting any other obligations of the Contractor in the Contract
Documents, the Contractor acknowledges and agrees that it shall comply with all applicable laws in
undertaking the Work, including all applicable labour, environmental, and human rights legislation.
17.4 Subject to sections 17.4.1 and 17.4.2, but notwithstanding anything else in the Contract to the contrary,
the Contractor acknowledges and agrees that, in accordance with the transparency and accountability
principles of the Owner, the Owner has a right to disclose or publish (including on websites) this
Contract, any or all terms hereof, including any or all contractual submissions and other records kept in
accordance with the Contract, any information related to the performance of the Contractor or any
related persons or any information derived from the Contract or the information related to the
performance of the Contractor (or any related party or subcontractor) as the Owner, in its discretion,
may consider appropriate. In exercising its discretion, the Owner will be guided by the principles set
out in sections 17.4.1 and 17.4.2.
.1
the Owner will not disclose portions of the Contract or any terms hereof, including any
contractual submissions or other records kept in accordance with the Contract, any information
related to the performance of the Contractor (or any related party or subcontractor) or any
information derived from this Contract or the information related to the performance of the
Contractor (or any related party or subcontractor) which would be exempt from disclosure under
section 10(1) of the Municipal Freedom of Information and Protection of Privacy Act (Ontario);
and
.2
notwithstanding section 17.4.1, where a compelling public interest in the disclosure of the
information clearly outweighs the public interest in limiting the disclosure of the information
supplied by the Contractor (or any related party or subcontractor), the Owner may disclose such
information.
17.5 The Owner may disclose this Contract, any or all terms hereof, including any or all contractual
submissions and other records kept in accordance with this Contract, any information related to the
performance of the Contractor (or any related party or subcontractor) or any information derived from
this Contract or the information related to the performance of the Contractor (or any related party or
subcontractor) to any of the Her Majesty the Queen in Right of Ontario, the Auditor General of Ontario,
Her Majesty the Queen in Right of Canada, the Auditor General of Canada and anyone acting on their
behalf in connection with funding and/or contribution agreements made in respect of this Project. In the
event of such disclosure, the Contractor acknowledges and agrees that:
.1
such persons may be subject to the Freedom of Information and Protection of Privacy Act
(Ontario), Access to Information Act (Canada) or other applicable laws in respect of protection
and/or disclosure of such information;
.2
.3
subject to compliance with, as applicable, Freedom of Information and Protection of Privacy Act
(Ontario), Access to Information Act (Canada) or other applicable laws, such persons will be free
to use, disclose or publish (including on websites) any information on such terms and in such
manner as they see fit.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 19 of 20
17.6 The Contractor acknowledges and agrees during the term of this Contract that:
32
.1
.2
the Owner, together with Her Majesty the Queen in Right of Ontario and Her Majesty the Queen
in Right of Canada may have regular media events about the funding and status of the Project.
Key milestones may be marked by public events, news releases and/or other mechanisms. The
Contractor will use commercially reasonable efforts to accommodate such events, including at the
Place of Work, when requested by the Owner at no additional cost or expense to the Owner; and
.3
the Owner may request that the Contractor install signage on the Place of Work supplied by the
Owner identifying the Project and the Contractor will use commercially reasonable efforts to
accommodate such signage when requested by the Owner, all at no additional cost or expense to
the Owner.
Definitions
.1
Change in Ownership means, with respect to a person, any change in ownership, whether beneficial or otherwise,
of any of the securities of ownership of such person, or in the direct or indirect power to vote or transfer any of the
securities of ownership of such person.
Change in Control means, with respect to a person: (a) any Change in Ownership, where the effect of such change
is to result in control of the decisions made by or on behalf of such person subsequently being with a different entity
or entities than prior to such change; (b) any other change in respect of the power to elect a majority of the directors of
the person or otherwise control the decisions made on behalf of such person; or (c) any other change of direct or
indirect power to direct or cause the direction of the management, actions or policies of such person.
Direct or Indirect Power or Control means the direct or indirect power or control over the decisions,
management, actions or policies of a person, including through the direct or indirect power or control over the
decisions, management, actions or policies of any persons having direct or indirect power or control over the
decisions, management, actions or policies of any other person, whether through:
- ownership, beneficial or otherwise, of any of the shares, units or equity interest of a person;
- the direct or indirect power to vote any of the shares, units or equity interests of a person; or
- the direct or indirect power or authority to influence or direct the approval of a decision, the
management, actions or policies of a person or to prevent the approval of a decision, the management,
actions or policies of a person through any contractual right or other power or interest with or over a
person.
Economic Interest means any right to receive, directly or indirectly and whether in cash or in kind, a payment,
repayment, fee, interest, dividend, distribution, redemption or any other consideration of benefit or value to the
recipient of any nature whatsoever.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00105
SUPPLEMENTARY CONDITIONS
CCDC 4-2011 SPECIFICATIONS
PAGE 20 of 20
Restricted Person means any person who (or any member of a group of persons acting together, any one of
which):
- has, directly or indirectly, its principal or controlling office in a country that is subject to any economic
or political sanctions imposed by Canada for reasons other than its trade or economic policies;
- is or has been involved in the illegal manufacture, sale, distribution or promotion of narcotic substances
or arms, or is or has been involved in the promotion, support or carrying out of terrorism;
- in the case of an individual, he or she (or in the case of a legal entity, any of the members of the board
of directors or its senior executive managers) has been sentenced to imprisonment or otherwise given a
custodial sentence (other than a suspended sentence) for any criminal offence (other than minor traffic
offences or misdemeanours) less than 5 years prior to the date at which the determination of whether
the person falls within this definition is being made;
- has as its primary business the acquisition of distressed assets or investments in companies or
organizations which are or are believed to be insolvent or in a financial standstill situation or potentially
insolvent;
- is subject to any claim of the Owner, the Province of Ontario or the Government of Canada in any
proceedings (including regulatory proceedings) which have been concluded or are pending at the time
at which the determination of whether the person falls within this definition is being made and which
(in respect of any such pending claim, if it were to be successful) would, in the Owners view, in either
case, be reasonably likely to materially affect the ability of the Contractor to perform its obligations
under this Contract; or
- has been convicted of an offence under the Proceeds of Crime (Money Laundering) and Terrorist
Financing Act (Canada), has been convicted of an offence relating to anti-competitive behaviour under
the Competition Act (Canada), or has been convicted of the commission of a money laundering offence
or a terrorist activity financing offence under the Criminal Code (Canada).
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00110
AMENDMENTS TO THE CCDC41
2008 INSURANCE REQUIREMENTS
PAGE 1 of 3
.1
REPLACE paragraph 1 with the below text:
The City of Ottawa shall purchase and maintain in full force at all times, from the execution of the Contract through to
Construction Completion:
Wrap-up comprehensive liability insurance with a combined single limit of liability of not less than one
hundred million dollars ($100,000,000) per occurrence and in aggregate for bodily injury, personal injury and
property damage including loss of use thereof. The policy shall be primary over and above any other existing
policy. The insured parties under the policy shall include the successful Contractor, all sub-consultants and all
subcontractors. The deductible shall be not less than one hundred thousand dollars (100,000); the first fifty
thousand (50,000) shall be paid by the Contractor or Contractors responsible for the loss to the City of
Ottawa. If more than one Contractor is involved, the City of Ottawas Representative shall be the sole judge as
to how the deductible is apportioned.
Upon notification of a claim being made, the City of Ottawa shall, at its sole discretion, be entitled to retain the
amount of the deductible in whole or in part from payment to the Contractor. Such amount will be applied by
the City of Ottawa in satisfaction of that claim and excess amounts, if any, will be paid to the Contractor
in the event and at such time as the claim is settled, dismissed or withdrawn. Notwithstanding the foregoing,
the City of Ottawa may, at its sole discretion, issue an invoice to the Contractor for the actual amount
of the claim settlement up to the amount of the deductible, and if the invoice is not paid within thirty (30)
days, the City of Ottawa shall deduct such amount from a future payment due to the Contractor
Such insurance shall include but not be limited to:
Products and broad form completed operations liability; the completed operations liability coverage shall
remain in effect for a period of not less than twenty-four ( 24) months after Construction
Completion;
Premises, property and operations;
Occurrence property damage;
Medical payments;
Owners and contractors protective liability;
Blanket contractual liability
Contingent employer's liability;
Personal injury liability;
Non-owned automobile liability;
Cross liability with respect to additional insureds;
Severability of interest clause;
Employees as additional insureds;
Broad form property damage endorsement;
Operation of attached machinery; and
Sudden and accidental pollution,
Blasting, demolition, pile driving
Caisson work or tunnelling
.2
REPLACE paragraph 2 with the below text:
The City of Ottawa shall maintain for the term of the Project, Environmental Liability Insurance which will
cover the Contractor and Subcontractors on the Project. Such Environmental Liability Insurance shall provide
coverage for on site cleanup of new conditions, third party claims for on-site and off-site bodily injury and
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00110
AMENDMENTS TO THE CCDC41
2008 INSURANCE REQUIREMENTS
PAGE 2 of 3
property damage, and off-site clean up for a limit of not less than twenty five million dollars ( $25,000,000) per
occurrence and in the aggregate. If such insurance is issued on a claims made basis, such insurance shall contain a
24 month extended reporting period or be maintained for a period of two years subsequent to completion of the
project.
Claims under this insurance shall be subject to a deductible of one hundred thousand dollars ( $100,000)
per claim. The first fifty thousand dollars ($50,000) of the one hundred thousand dollars ( $100,000)
deductible shall be paid by the Contractor or Contractors responsible for the loss. If more than one contractor
is involved, the City of Ottawa Representative shall be the sole judge as to how the deductible is apportioned.
Upon notification of a claim being made, the City of Ottawa shall, at its sole discretion, be entitled to retain
the amount of the deductible in whole or in part from payment to the Contractor. Such amount may be
applied by the City in satisfaction of that claim and excess amounts, if any, will be paid to the
Contractor in the event and at such time as the claim is settled, dismissed or withdrawn. Notwithstanding the
foregoing, the City may, at its sole discretion, issue an invoice to the Contractor for the actual amount of the
claim settlement up to the amount of the deductible, and if the invoice is not paid within thirty (30) days, the
City shall deduct such amount from a future payment due to the Contractor.
-
.3
REPLACE paragraph 3 with the below text:
Throughout the term of the Contract including all warranty periods, the Contractor shall obtain and maintain at
their own expense the following insurance in relation to the CSST Project, any services required to be performed
by the Contractor under the Contract Documents, or otherwise, each such policy to be issued by an insurance
company licensed to carry on the business of issuing such policies in Ontario, and possessing a Best's Financial
Strength Rating of at least A- or better.
Comprehensive General Liability Insurance which shall include, but not limited to:
Bodily injury and property damage;
Personal injury;
Blanket contractual liability;
Premises, property and operations;
Products and broad form completed operations coverage;
Occurrence property damage;
Medical payments;
Contingent employer's liability coverage, for any claims that might be brought against the City of
Ottawa by any employee of the Contractor;
Owner's and Contractor's protective coverage for all subcontracted operations;
Sudden and accidental pollution coverage;
Broad form property damage;
Employees as additional insured;
Non-owned automobile; and
Cross liability and severability of interest clause.
Such insurance shall provide a combined single limit of not less than Twenty Five Million Dollars
($25,000,000) for any one occurrence or accident for all claims arising out of bodily injury (including
death) and damage to property of others. Such liability insurance shall contain no exclusions in
conflict with the character of the Work required to be performed under the Contract and shall include
the Commission as additional insured.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00110
AMENDMENTS TO THE CCDC41
2008 INSURANCE REQUIREMENTS
PAGE 3 of 3
The above noted insurance policies shall add the City of Ottawa, its elected officials, agents, officers and employees
as an additional insured with respect to the operations of the Contractor. Such insurance policies shall be noncontributing with and apply as primary and not as excess of any insurance available and shall contain a waiver of
subrogation in favor of the City of Ottawa.
.4
REPLACE paragraph 4 with the below text:
Contractor shall provide Automobile Liability insurance, for liability arising out of the use of leased and owned
automobiles in connection with the performance of the Work. Coverage will consist of a combined single limit of
liability of five million dollars ($5,000,000) per occurrence and annual aggregate and shall be in effect where the Work
is being performed.
.5
REPLACE paragraph 7 and its subsections with the below text:
Contractor shall maintain contractors equipment insurance covering the Contractor's plant, construction machinery,
tools, tackle and other equipment in a manner acceptable to the City.
ADD additional paragraph8 as follows
All the above insurance policies shall contain an endorsement to provide the City of Ottawa with 30 days advance
written notice of cancellation of the insurance coverage.
Prior to commencement of the project and at each policy renewal, the contractor shall provide the City of Ottawa
with an insurance certificate as evidence of the above noted insurance.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 1 of 13
TENDER CALL
.1
The City of Ottawa, hereinafter called the "City" or Owner invites Tenders for Contract
Number:
ISD14-2036 described as follows:
.1
In general, the Work under this contract consists of supply and installation of materials,
labour and equipment for the construction of the Combined Sewage Storage Tunnel
(CSST) as per the work described in Section 01010 Summary of Work.
.2
Name of work:
Construction of the Combined Sewage Storage Tunnel
Dates
Tenderers Briefing
February 1, 2016
April 5, 2016
Tenders shall be received until: 3:00 p.m. local time, Tuesday, April 5, 2016.
.2
Tenders received by the time and date specified above will be opened and read in public as
soon as possible after that time. Public reading of a Tender does not imply any decision by
the City as to whether a Tender is or is not irregular.
.3
The timing device at the point of receipt will determine the time the Tenders are received.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
5
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 2 of 13
Sole Proprietorship: Signature of sole proprietor in the presence of a witness who will also
sign. Insert the words "Sole Proprietor" under signature.
.2
Partnership: Signature of Minimum partners in the presence of a witness who will also
sign. Insert the word "Partner" against each signature.
.3
Limited Company:
.1
Signature of duly authorized signing officer in their normal signatures. Insert the
officer's capacity in which the signing officer acts against each signature. The
tender forms shall be affixed with the Corporates seals.
.2
If the tender is signed by officials other than the President and Secretary of the
Company or the President Secretary Treasurer of the company, a copy of the by
law resolution of the Board of Directors authorizing them to do so must also be
submitted with the tender in the tender envelope.
TENDER DEPOSIT
.1
At the time of tendering, the Tenderer shall submit, with its Tender, a deposit in the form of
a certified cheque or a bid bond signed and sealed by the Tenderer's surety in favour of the
City of Ottawa. The Tender deposit be an original and shall be equal to at least ten percent
(10%) of the total Tender price.
.2
.3
The City will retain the Tender deposit of the successful Tenderer until:
.4
7
.1
the successful Tenderer has executed the Agreement between City and Contractor
in accordance with the article Successful Tenderer- Execution of Form of
Agreement in this section and Section 00400, Form of Tender; and
.2
the successful Tenderer has provided all bonding in accordance with the article
Successful Tenderer- Bonds in this section and Section 00400, Form of Tender.
The City will return the deposit of unsuccessful Tenderers at a time determined by the City.
AGREEMENT TO BOND
.1
At the time of Tendering, the Tenderer shall submit, with its Tender, an Agreement to Bond
completed and executed by the Tenderer's surety. The Agreement to Bond must be an
original and the Tenderer's surety shall be to the satisfaction of the City.
ADDENDAS
.1
The Tenderer shall ensure that its name and address for receipt of addendas are included on
the City's list of firms to whom addendas to this Contract, if any, are to be sent. Inclusion
on the City's list does not absolve the Tenderer of its responsibilities set out in the article
"Contract Documents" of this Section.
.2
The Tenderer shall ensure that all addendas issued are acknowledged and listed under
Section 00400, Form of Tender.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
9
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 3 of 13
IRREGULAR TENDERS
.1
10
The City shall be the sole judge of whether or not a Tender is irregular.
UNBALANCED TENDERS
.1
.2
11
.1
.2
COLLUSION
.1
12
The Tenderer shall not engage in collusion of any sort and, in particular, shall:
.1
ensure that no person or other legal entity, other than the Tenderer, has any
undisclosed interest in the Tenderer's Tender; and
.2
prepare its Tender without any knowledge of, comparison of figures with or
arrangement with any other person or firm preparing a Tender for the same work.
.2
.3
13
Notwithstanding any other provision in this Contract, the City shall have the right to:
.1
.2
.3
Without limiting the generality of Item 11.1, the City shall have the right to:
.1
.2
.3
Acceptance of the Tender shall occur at the time the City awards the Tender and not
necessarily at the time the award is communicated to the successful Tenderer.
CONTRACT DOCUMENTS
.1
The Tenderer shall obtain and review all Contract Documents as listed in the Form of
Tender and all Addenda issued by the City pertaining to this Contract.
.2
Tender Documents are made available only for the purpose of obtaining offers for this
project. Their use does not confer licence or grant for other purposes.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
14
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 4 of 13
If the Tenderer finds any errors or omissions in or discrepancies among the Contract
Documents, it shall immediately notify the Purchasing Officer identified in Section 00060,
Project Directory.
.2
No oral explanation or interpretation by any person shall modify any of the Contract
Documents.
15
IRREVOCABILITY OF OFFER
.1
The Tenderer shall not revoke its offer until after the expiration of ninety (90) days after the
opening of Tenders by the City.
.2
If the Tenderer revokes its offer prior to the expiration of ninety (90) days after the Tender
opening, the Tenderer shall forfeit its Tender deposit but this shall not prohibit the City
from pursuing any other legal remedy which it may have.
.3
While the City will attempt to award the Contract as expeditiously as possible, the Tenderer
shall make allowance in the Construction Schedule for the full ninety (90) days
"Irrevocability of Offer" period noted above. Such allowance shall include all financial
obligations required to complete the project as specified.
16
SUBSTITUTIONS
.1
.2
Specific materials, products and systems are specified to provide a standard of acceptance.
Equivalent materials, products or systems by other manufacturers are acceptable as
substitutions when approved by an Addendum, provided that the properties and compliance
of the substitutions meet or exceed the properties and compliance of the specified materials,
products and systems in all respects and that items exposed to sight are of the same
appearance as the specified items.
.3
Substitutions, which do not satisfy the above requirements, may be rejected by the
Consultant. Materials, products and systems, which are so rejected, shall be replaced by the
specified items at no cost to the City.
.4
In the event that, prior to closing of tenders, the Tenderer wishes to offer a substitution or a
proposal of work materials or methods as an alternative to those described in the Contract
Documents, he/she shall submit a request in writing at least 21 calendar days prior to the
tender closing date.
.5
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 5 of 13
in the same sequence as specified herein or in the sequence listed in the specified
manufacturer's published literature, as applicable; and
.3
.4
If requested by the Director, a list of no less than five projects of comparable size
where the proposed substitution has been used in a similar application. Such
projects shall have been completed prior within the last five years and, where
applicable, shall have been subject to climatic conditions similar to those
experienced in Ottawa. The list shall include the name and current telephone
number of the Consultant and the Owner for each project.
.6
In the event that the Consultant deems the information provided with the request for
approval of a substitution to be inadequate, the request may be rejected.
.7
.8
The cost of additional work and/or modification to the design due to the use of alternative
materials, products or systems shall be borne by the Contractor.
.9
Where the terms "or equal", "or equivalent" or terms of similar meaning are used in the
specifications, this shall not be construed as acceptance of any alternative material, product
or system to those specified. The use of these terms does not relieve the Contractor from his
responsibility to follow the procedures for approval of substitutions specified herein (during
tender period) or the procedures described in Section 01200, Alternatives (after award of
Contract).
.10
No substitutions will be permitted after award of the Contract except in accordance with
General Conditions GC 6.1 "Changes" and the article "Alternative Products" in Section
01200 Alternatives. For procedures regarding substitutions after the award of the Contract,
refer to General Conditions GC 6.1 "Changes".
17
Each Tenderer, before submitting his Tender, shall carefully examine the drawings and
specifications to establish the extent of the work and shall visit and examine the site and
fully inform himself/herself of all the existing conditions, limitations and difficulties which
may arise and include in his/her Tender the cost of all labour, materials, equipment and
services required to complete the Work.
.2
Drawings and Specifications are complementary. Items shown or mentioned in one and not
in the other are deemed to be included as part of the contract.
.3
In the event of any discrepancy between the Drawings and the Specifications, the
Specifications shall apply.
.4
In the event of any discrepancy between one drawing and another, the larger scale drawing
shall apply.
.5
The sequence and numbering of the drawings and details and the organization of the
specifications into Divisions and Sections are established for convenient ordering of
information. It must not be assumed that such ordering of information is intended to define
or limit the scope of extent of the work of any particular subcontractor or supplier. The
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 6 of 13
drawings and specifications as a whole must be fully read, in detail, to determine the extent
of any portion of the Work. It is the responsibility of the Contractor to coordinate
subcontractors and suppliers prices such that the stipulated Tender Price is all inclusive as
specified herein.
.6
18
.1
19
Tenders submitted in accordance with these instructions are irrevocable. Requests for
withdrawals or revisions for whatever reason will be allowed only if unequivocal,
submitted in writing, and received by the Supply Management Division prior to Tender
closing date.
QUESTIONS
.1
Tenderers are required to submit their Tenders on the basis of the information contained in
the Tender Documents only. Should a Tenderer find any discrepancy, omission or
ambiguity in the Contract Documents, or should he/she be in any doubt as to their meaning,
he/she shall notify the Purchasing Officer identified in Section 00060 Project Directory in
writing by email or fax communications.
.2
All questions, regarding this Request for Tender, are to be referred to the Contracting
Authority no later than fourteen (14) working days before the Tender Closing Date.
.3
.4
No questions shall be submitted to any of the Consultants. If so, such questions shall be
disregarded, and shall not form part of any addendum.
20
.2
A labour and material payment bond signed and sealed by the Tenderer's surety;
Each in the amount of One Hundred percent (100%) of the total Tender price.
.2
21
The surety of the successful Tenderer and the bonds referred to above shall be to the
satisfaction of the City.
PARENT COMPANY GUARANTEE
.1
Depending on the Tenderers business structure and financial position, one or more
parent(s) or other affiliate(s) of the Tenderer may be added as a party for purposes of
providing a guarantee of obligations under this Contract.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
22
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 7 of 13
The successful Tenderer shall provide the City with a valid Workplace Safety & Insurance
Board Certificate of Clearance to the satisfaction of the City.
23
For the purposes of this Contract, the form of Agreement shall be the Agreement between
Owner and Contractor contained in Unit Price Contract CCDC4-2011.
.2
.3
The successful Tenderer shall execute, in triplicate, signed and sealed copies of the
Agreement between City and Contractor that forms part of the Contract Documents.
.4
The successful Tenderer shall forward the three copies of the executed Agreement to the
City.
24
25
.1
The successful Tenderer shall acknowledge that time is of the essence and shall complete
the Contract as quickly as possible from date of award of contract.
.2
The Contractor shall phase the construction such that the Work will be Substantially
Performed and turned over to the City for Occupancy within the noted timeframes.
.3
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 8 of 13
The Contractor acknowledges that he is aware that the awarding of this Contract, and/or
release of the Commence Work Order is at the Citys discretion. The Contractor shall not
make any claims for additional costs or expenses due to delays in the commencement of
work (or portions thereof). The Contractor acknowledges that it is aware that the awarding
of this Contract, and/or release of the Commence Work Order, are subject to City of Ottawa
obtaining the following:
.1
.2
.5
The Contractor shall not make any claims for additional costs or expenses due to delays in
the commencement of work (or portions thereof). The Contract Substantial Performance
and Project Completion dates will be adjusted to account for delays to release of the
Commence Work Order.
.6
Project Completion: The Contractor shall provide a Construction schedule that identifies
the final date of completion in the shortest time period possible and separately identifies
each element of the construction, the planned completion dates for each and the critical
path.
26
INCENTIVE / DISINCENTIVE
.1
Scope of Work
.1
The Contractor is advised that for the portion of the Work outlined below
Incentive/Disincentive will apply. This provision does not modify any completion
date or working day provisions as stated elsewhere in the Contract Documents.
.2
The Contractor shall complete all works at Site 3a indicated on the Contract
Drawings and within the Specifications, meeting the schedule constraints outlined in
Section 01117. Access to this site is permitted only between March 1, 2018 and
December 31, 2018. Final restoration, landscaping, and work within the chambers
may be completed between March 1, 2019 and May 31, 2019 (for diversion
chamber) and between March 1, 2019 and August 2019 (for odour control building).
.2
.3
If works at Site 3a, including demobilization from site and reinstatement to the
satisfaction of the Contract Administrator, (excluding final restoration), is completed
to the satisfaction of the Contract Administrator on or before 3:00 p.m. local time on
December 31, 2018 the Contractor will be paid an incentive of $315,000. In
addition, for each full calendar day prior to the above date that the above work is
completed, to the satisfaction of the Contract Administrator, the Contractor will be
paid $10,500 per calendar day, up to a maximum additional incentive payment of
$315,000. Therefore, the maximum grand total incentive available is ($315,000
+$315,000 =) $630,000.
Disincentive for late completion
.1
If the works at Site 3a, including demobilization from site and reinstatement to the
satisfaction of the Contract Administrator, (excluding final restoration) is not
completed to the satisfaction of the Contract Administrator on or before 3:00 p.m.
local time on December 31, 2018 the Owner will deduct a single lump sum amount
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 9 of 13
of $630,000 from amounts otherwise payable to the Contractor under the Contract.
In addition, the Owner will deduct an amount equal to a further $10,500 per day for
each additional full calendar day until the above work is completed, up to a
maximum additional deduction of $315,000. Therefore, the maximum grand total
disincentive that would be deducted is ($315,000 +$315,000 =) $630,000. In
addition, the Contractor will be solely responsible for all costs associated with fully
demobilizing by December 31, 2018 and remobilizing to site, when permitted as
identified in Section 01117, to complete the work. The Contractor will be required to
complete the work within the specified timeline in 2019. Any work needed to occur
outside of this time will require an access agreement with the NCC and will be solely
the Contractors responsibility and their expense and risk.
.2
.4
Basis of Payment
.1
27
Any and all compensation for the Contractor to schedule the operations in
accordance with these requirements, including, if required, utilizing extra crews,
shall be deemed to be included in the Contract bid price for the various tender items
and no additional payment shall be made except for the payments outlined above.
This Special Provision - The Contractor will be paid under the Contract Item
Incentive/Disincentive following successful completion of the above work to the
satisfaction of the Contract Administrator, or deducted from amounts otherwise
payable to the Contractor under the Contract.
The successful Tenderer shall submit the documentation as required by the article
"Successful Tenderer - Bonds", "Successful Tenderer Workplace Safety & Insurance Board
Certificate of Clearance", "Successful Tenderer Execution of Form of Agreement" and
"Successful Tenderer Insurance'" of this document, within seven (7) working days of the
day the City notifies the successful Tenderer that the documentation should be sent to the
City.
.2
If the successful Tenderer fails to comply with the above requirement, the City may, in its
sole discretion, withdraw its acceptance of the Tender and the Tenderer shall have no
recourse whatsoever against the City.
28
29
The successful Contractor shall pay liquidated damages in the amount of eleven thousand
five hundred eighty eight Dollars ($11,588.00) per calendar day as a result of the nondelivery of the completed work beyond the Contract dates.
SUCCESSFUL TENDERER COMMENCEMENT OF THE WORK
.1
The successful Tenderer shall not commence the Work until it has received a Commence
Work Order issued by the City. For the purpose of establishing a schedule for the Work, it
is assumed that the Commence Work Order will be issued 3 working days after the
Contract Award is complete.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
30
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 10 of 13
TENDERERS' BRIEFING
.1
All Tenderers are strongly recommended to attend the Tenderers Briefing due to the
complexity of some parts of the project. The Tenderers Briefing will take place at:
10:00 a.m. local time, Thursday January 14, 2016
.2
Meeting Location:
1331 Clyde Avenue, Suite 400, Ottawa ON K1K 4H7.
31
All Tenderers are notified that viewings will be held to view rock cores collected during the
geotechnical investigation, for informational purposes. No cores are permitted to be
removed from the viewing area.
.2
Viewing Procedures
.1
Due to the number of rock cores, there will be two viewings for each Tenderer. Each
Tenderer is permitted one (1) viewing of each set of cores with a maximum of four
(4) attendees.
.2
All requests for viewings by proponents of the core samples must be formally
submitted (electronic and / or hard copy) to the City of Ottawa Purchasing Officer.
Each Tenderer shall identify three (3) timeslots identified below for both viewing
that they prefer to attend. The purchasing officer will notify each Tenderer of their
actual timeslot once all Tenderers viewing timeslots have been requested. The
formal viewing request must include the following information:
.1
.2
.3
.3
The facility will at all times be supervised by the Consultant while the Tenderers are
present at the facility and the visits can only take place between the hours of 8:00 am
and 4:00 pm during the specified days. No technical information related to the
samples or the project will be shared with any of the visiting parties from the
proponents. Consultant staff will not provide any technical information about the
samples to the Tenderers who are to refer to the available documentation (i.e., GDR
and GBR).
.4
Each individual participating in the viewings will receive a brief health and safety
orientation at 8:00am or 1:00pm, depending on their selected timeslot, and will be
expected to sign a sheet confirming they received the orientation.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
.6
Available Times
8:00am 12:00pm
1:00pm 5:00pm
8:00am 12:00pm
1:00pm 5:00pm
8:00am 12:00pm
.3
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 11 of 13
Available Times
1:00pm 5:00pm
8:00am 12:00pm
1:00pm 5:00pm
8:00am 12:00pm
8:00am 12:00pm
.7
Each proponent will be assigned a timeslot based on the schedule above for viewing
each set of core samples. Only one proponent team will be admitted to the sample
storage warehouse at a time. The order of viewing will be decided by the Purchasing
Officer.
.8
All persons entering the sample storage warehouse will be required to wear CSA
approved steel toed safety shoes, safety eyewear and will be required to review and
comply with the storage warehouse health and safety plan. Samples may be visually
inspected and photographed by the proponents; however, no destructive testing of the
core may be carried out.
Viewing Location:
93 Hines Road Storage Facility Storage Bay 6, Ottawa, ON
32
FAIRNESS COMMISSIONER
.1
The City has retained a Fairness Commissioner to monitor, advise and provide expert
procurement guidance during the Tender process. The Fairness Commissioners role is to
actively monitor the Tender process from the release of the Tender to the selection of the
successful Tenderer to ensure that all processes are conducted in accordance with the
provisions of the Tender.
.2
The Fairness Commissioner will be present at all Commercially Confidential Meetings and
other discussions between the Owner, Consultant and a Tenderer to ensure compliance with
the Tender. The Fairness Commissioner may be contacted at any time by a Tenderer to
discuss fairness issues.
33
The Owner reserves the sole and absolute right to disqualify any Tenderer that, in the
Owners sole and absolute discretion, has a conflict of interest or an unfair advantage. If the
Owner determines that a conflict of interest or unfair advantage does exist, the Owner may
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 12 of 13
withhold consideration of the Tenderers submission until the conflict of interest or unfair
advantage is eliminated or mitigated to the satisfaction of the Owner. If the conflict of
interest or unfair advantage cannot be eliminated or mitigated to the satisfaction of the
Owner, the Tenderer will receive no further consideration in this Tender.
.2
Tenderers are required to complete Form Conflict of Interest and Unfair Advantage
Declaration, attached as Statement C as part of its submission.
.3
A non-exhaustive list of certain key persons that have worked on the design and
engineering assignment or other aspects of the project that render them ineligible to
respond to this Tender is: Stantec Consulting Ltd., CH2M Hill, Golder Associates, Jacobs
Engineering, Peregoy Construction Services Inc., and Borden Ladner Gervais LLP.
.4
By participating in this Tender process and providing a Tender Submission, a Tenderer: (a)
confirms that it has disclosed to the Owner all matters in which it has retained, directly or
indirectly (including through an insurer), any of the above-noted firms and shall forthwith
disclose any new retainer following the date of such disclosure; (b) if it has retained any of
the above-noted firms, acknowledges that either no conflicts of any nature whatsoever,
including legal or business conflicts, exist or will be created as a result of participation in
the Tender process to the above-noted firms having acted, and continuing to act, for and on
behalf of the Owner in respect of the Project; and (c) notwithstanding the foregoing,
acknowledges that it is waiving all conflicts of any nature whatsoever, including legal or
business conflicts, which may now or hereafter exist as a result of the above-noted firms
having acted, and continuing to act, for and on behalf of the Owner in respect of the
Project.
.5
.6
.1
A real conflict of interest arises where the business, professional, personal, financial
or other considerations of the Tenderer and/or a team member, or one of its
respective principals, shareholders, directors, officers, key employees or executives,
affect or compromise, or reasonably appears to affect or compromise the Tenderers
or a team members undertaking of its obligations under or in respect of its Tender
submission or the Tender process;
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00200
INSTRUCTIONS TO TENDERERS
PAGE 13 of 13
could compromise the integrity of the Tender process and/or does or could result in any
material unfairness to other Tenderers. Similar to a conflict of interest, an unfair advantage
may be real, potential or perceived in nature.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PART 1
GENERAL
1.1
PAGE 1 OF 13
.1
White Paper Submissions are requested by the Owner. While they are not mandatory,
Tenderers are strongly encouraged to submit White Paper Submissions.
.2
With the financial support of its CSST Project funding partners at Infrastructure Canada
and the Province of Ontario, the City of Ottawa has identified a pre-established budget of
$150M for the construction of the CSST Project. As part of the white paper and
commercially confidential meeting process (described under Part 3 of this Section
00205), the Owner wishes to solicit input and engage the Tenderers in discussions related
to the feasibility of delivering the project within this budgetary limit. For greater clarity,
the budget referred to in this paragraph is not a cap or limit on the Contract Price payable
by the Owner to the Contractor under the Contract, which will be determined in
accordance with the Contract.
.3
The purpose of the White Paper Submissions is thus to solicit and provide a forum for
Tenderers to provide further suggestions and explore the viability of their ideas for
improved cost-effectiveness in the delivery of the CSST project as they relate to project
design and construction, cost and schedule control, as well as risk management in view of
the Owners budgetary and schedule constraints for the project.
.4
There are three categories of White Paper Submissions requested. Tenderers are
encouraged to be creative in proposing White Paper Submissions within the categories
described below.
-
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 2 OF 13
The provisions contained in Section 00205 will apply to each of the three categories of
White Paper Submission to the extent indicated.
.5
As part of the review process, the contents of the White Paper Submissions will be
discussed within a commercially confidential setting as explained in Part 3 of this Section
00205. The Owners determination of the merits of each submission shall be in
accordance to the review process outlined in Part 4 and Part 5 of this Section 00205. Part
5 addresses the detailed development, submittal requirements and review process for
accepted Category 3 submissions.
.6
As specified in Section 00200, the Owner will retain the services of a Fairness
Commissioner to monitor, advise and provide expert procurement guidance during the
White Paper Submission Review Process as well as be present at all White Paper
Submission Meetings.
.7
The White Paper Submission must not substantially impair any essential form,
fit, function or characteristic of the Work, such as, but not limited to, safety,
service life, reliability, economy of operation, ease of maintenance, aesthetics
and necessary standard features at the sole discretion of the City; (particularly as
it either impacts its functionality, operation or negotiated land use agreements
with land owners); and
The White Paper Submission shall not materially increase the risk to project
implementation, system performance, cost or schedule of completion.
.2 The Tenderer must submit a separate White Paper Submission for each proposed
White Paper Submission proposal and the Tenderer will identify, for each
submission, the category of submission under which it falls. Each White Paper
Submission must be capable of being assessed for acceptability on its own merits.
Unless the Tenderer clearly indicates that certain White Paper Submissions are not
mutually exclusive of one another, individual White Paper Submissions must not be
dependent or contingent on the acceptance of another or other White Paper
Submission(s) in order to meet the parameters and requirements outlined in this
Section 00205. The Owner will be entitled, in their sole discretion, to accept some,
all, or none of the White Paper Submissions.
.3 Category 3 Commercially Confidential White Paper Submissions must each provide
an Instant Contract Saving of a minimum of $500,000.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.2
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 3 OF 13
At a minimum, and as applicable, the Contractor shall include, in each White Paper, the
information described below:
.1 A description of the difference between the existing Contract requirement and that
proposed in the White Paper Submission, the comparative advantages and
disadvantages of each, a justification when an item's function or characteristics are
being altered, and the effect of the change on the end item's performance.
.2 A list of the Contract requirements that must be changed if the White Paper
Submission is accepted, including a recommendation as to how the revisions must be
made and any suggested specification revisions.
.3 A description of the added value and material benefit resulting from the proposal,
including the associated differences in cost. The cost information shall include both
capital cost savings and life cycle cost savings. The cost reduction associated with the
White Paper Submission shall take into account the Contractor's implementation
costs.
.2
PART 2
.1
The Contractor will submit all White Paper Submissions as described in this Section
00205 and shall include completed Appendix 1 and 2 with the submission.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
PART 3
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 4 OF 13
Preferred White Paper Submissions must fall within the parameters described under Part
1 of this Section 00205.
.1
The purpose, procedures, submittal requirements, and evaluation process related to the
White Paper Submissions, including the White Paper Submission Meeting, will be
reviewed at the Tenderers Briefing. Refer to Section 00200 for details on the Tenderers
Briefing.
.2
The Owner will hold, with each Tenderer, one White Paper Submissions Meeting, which
will be considered commercially confidential.
.3
The purpose of the White Paper Submission Meeting is to facilitate an open dialogue
with the Owner and provide an opportunity for the Tenderer to present their White Paper
Submissions in the various categories defined in Part 1 of this Section 00205. The White
Paper Submission Meeting will provide the opportunity to discuss, with the Owner,
whether the Preferred White Paper Submissions and potential Contractor White Paper
Submissions are of interest to the Owner and the extent to which the potential White
Paper Submissions and Preferred White Paper Submissions may be acceptable to the
Owner.
.4
White Paper Submission Meetings will be scheduled at the mid-way point of the tender
period as outlined in the Tender schedule in Section 00200.
.5
The Contractor must provide the information requested in this Section 00205 no later
than 10 Business Days prior to a White Paper Submission Meeting. The Owner will not
provide any written commentary with respect to the White Paper Submissions either prior
to or during the White Paper Submission Meeting. Submissions will be reviewed and
evaluated as described in Part 4 of this Section 00205.
PART 4
.1.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 5 OF 13
.4. In determining the cost savings, the right is reserved to disregard the submission if, in
the judgment of the Owner and Consultant, such prices do not represent a fair
measure of the value of the work to be performed or to be deleted. The Owner retains
the right to have a cost consultant review the proposed cost savings identified by the
White Paper Submission.
.5. Following the submission of the White Papers, and at any point during their review
of any White Paper Submission, the Owner reserves the right to request, from the
Tenderer, additional information, more detailed descriptions and/or clarifications to
the extent that it feels is necessary to assess the merits of the subject White Paper
Submission.
.6. The decision of the Owner and Consultant regarding acceptability or unacceptability
of the White Paper Submission, as well as the savings and costs, shall be final. The
Owner and Consultant will not have any obligation or liability whatsoever in relation
to the consideration or rejection of any White Paper Submission.
.2.
.3.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 6 OF 13
PART 5
DETAILED DEVELOPMENT AND SUBMITTAL OF CATEGORY 3
(COMMERCIALLY CONFIDENTIAL) WHITE PAPERS
5.1
5.2
DEFINITIONS
.1
.2
Collateral Savings, as used herein, means those measurable net reductions resulting
from a Commercially Confidential White Paper Submission in the Owner's overall
projected collateral costs, exclusive of acquisition savings, whether or not the acquisition
cost changes.
.3
.4
Contractor's Development Costs, as used herein, mean those costs the Contractor incurs
that are specifically related to developing, testing, preparing and submitting the
Commercially Confidential White Paper Submission. Contractor's development costs will
not be recoverable. If the Commercially Confidential White Paper Submission is adopted,
the Contractor's share of the savings as hereinafter defined shall be considered full
compensation to the Contractor for the development and implementation of the
Commercially Confidential White Paper Submission.
.5
Implementation Costs, as used herein, means those costs the Contractor incurs to make
the contractual changes required by the Owner's acceptance of a Commercially
Confidential White Paper Submission. Such costs will be subject to Owner audit.
.6
Owner Costs, as used herein, means those costs the Owner incurs that result directly
from developing and implementing the Commercially Confidential White Paper
Submission, such as, but not limited to, any net increases in the cost of engineering,
testing, operations, maintenance and logistic support. The term also includes the
administrative costs of review and processing the Commercially Confidential White
Paper Submission.
.7
Instant Contract Savings, as used herein, means the reduction in Contractor cost of
performance (which includes overhead and profit attributable to the reduced or
eliminated work), resulting from acceptance of the Commercially Confidential White
Paper Submission, minus implementation costs and Owner costs.
Final Submittal Requirements for Category 3 White Papers (submitted as part of the final
RFT submission) are as follows:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 7 OF 13
.1 Once a Category 3 White Paper Submission is accepted by the Owner, Tenderers are
provided with the opportunity to develop a detailed proposal and separately submit each
one in an envelope clearly marked and sealed as Category 3 (Commercially
Confidential) White Paper Submissions.
.2 At a minimum, the Tenderer shall include in each Category 3 White Paper Submission
the technical information described below:
.1 A description of the difference between the existing Contract requirement
and that proposed in the White Paper Submission, the comparative
advantages and disadvantages of each, a justification when an item's function
or characteristics are being altered, and the effect of the change on the end
item's performance.
.2 An itemized list and analysis of the Contract requirements that must be
changed if the White Paper Submission is accepted, including a
recommendation as to how the revisions must be made and any suggested
specification revisions.
.3 All specifications, instructions, plans and drawings detailing the
implementation of the White Paper Submission. All drawings and
specifications must be prepared by and sealed by a Professional Engineer
registered in the Province of Ontario.
.4 A revised schedule for the affected portion(s) of the Work and the entire
contract work, if any.
.5 Potential impact on the environment and obtaining permits resulting from the
White Paper Submission.
.6 Any other information required in the judgment of the Owner to review
and/or implement the White Paper Submission. Such information shall be
provided by the Tenderer as soon as practicable after the Owner's request
thereof.
.3 .At a minimum, the Tenderer shall include in each Category 3 White Paper Submission
the financial information described below:
.1 A separate, detailed cost estimate for: (i) the affected portions of the existing
Contract requirement and (ii) the White Paper Submission. The cost estimate
shall include, without limitation, both capital cost savings, and life cycle cost
savings as well as an itemized breakdown including the items, quantities, unit
prices for both the affected portion in the original design and the proposed
changes in the White Paper Submission. The cost reduction associated with
the White Paper Submission shall take into account the Contractor's
implementation costs.
.2 A description and estimate of the Owner Costs in implementing the White
Paper Submission.
.3 A prediction of any effects the proposed change would have on Collateral
Costs. The financial offer associated with each Category 3 White Paper
Submission will thus include any associated design costs and any costs
associated with the review of the White Paper Submission by the Owner and
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 8 OF 13
Category 3 White Paper Submissions will be reviewed further to bid closing and only at
the negotiation stage with the successful Tenderer. Category 3 White Paper Submissions
will not be considered as part of the evaluation of Tenders or identification of the
Successful Tenderer. All Tenderers acknowledge and agree that the Contract Documents
may be materially modified or amended as a result of any Commercially Confidential
White Paper Submissions that are accepted by the Owner from the Successful Tenderer,
and each Tenderer waives any right to contest such modifications or amendments.
.2
.3
If it is determined there will be a cost decrease to the Owner, Instant Contract Savings
will be shared between the Contractor and the Owner as specified within this Section
00205.
.4
White Paper Submissions will be processed expeditiously, however, neither the Owner
nor Consultant will be liable for any delay in acting upon or for failure to act upon, any
White Paper Submissions submitted pursuant to this Section.
.5
The Owner and the Consultant will be the sole judge of the acceptability of a White Paper
Submissions and of the savings and costs from the adoption of all or any part of such
proposal. In determining the savings, the right is reserved to disregard the Contract bid
prices represented in the White Paper Submissions if, in the judgment of the Owner and
Consultant, such prices do not represent a fair measure of the value of the work to be
performed or to be deleted. The decision of the Owner and the Consultant regarding
acceptability or unacceptability of the White Paper Submissions, as well as the savings
and costs, shall be final.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
5.4
5.5
5.6
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 9 OF 13
The Owner and the Consultant may require the Tenderer to modify the White Paper
Submission to make it acceptable. If any modification increases or decreases the savings
resulting from the White Paper Submission(s), the Contractor's fair share will be
determined upon the basis of the White Paper Submission(s) as modified.
The Contractor and Owner shall each receive a 50 percent share in the Instant Contract
Savings. Upon acceptance of the White Paper Submission (s) by the Owner and
Consultant, the Instant Contract Savings will be incorporated into the contract price and
associated contract award documents. Any White Paper submissions that are not
immediately accepted by the Owner and Consultant will be retained for possible reconsideration further to contract award. If accepted at a later date, the associated savings
will be applied by means of a change order.
.2
The Contractor is not entitled to share the Collateral Savings and other future contract
savings resulting from the accepted White Paper Submission (s). Life cycle cost savings
in maintenance, operations etc. will remain with the Owner and will not be shared with
the Contractor.
WARRANTY
.1
The Contractor shall be, and shall remain, liable for the effectiveness of the design of the
change proposed.
.2
The Contractor warrants that such change: shall be free from defects in design, function,
configuration and purpose; shall fully perform the function as intended and required by
the Contract Documents; complies with all laws, rules, regulations and ordinances
governing such an item; and infringes no patent, copyright, trade secret or other third
party proprietary right or interest.
DATA
.1
To the extent permitted or allowed by law, neither the Owner nor Consultant will
disclose, use or duplicate any data provided by the Contractor pursuant to this Section,
while such Commercially Confidential White Paper Submission is being evaluated. This
restriction shall not apply to any information if it is, or has been obtained, or is otherwise
available, from the Contractor or from any other source, without limitation. Once the
White Paper Submission evaluation process has concluded, the Owner shall have the
right to duplicate, use and disclose any data in any manner, and for any purpose, and have
others do so, under this or any other Owner contract.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 10 OF 13
Appendix 1
Category 1: Preferred White Paper Submission
Re-scoping Description
1.0
2.0
3.0
4.0
5.0
Category
Price Adjustment
Requirements
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 11 OF 13
Appendix 1
Category 2: Non-Commercial White Paper Submission
Category
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 12 OF 13
Appendix 1
Category 3: Commercially Confidential White Paper Submission
Category
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00205
WHITE PAPER INSTRUCTIONS TO TENDERERS
PAGE 13 OF 13
APPENDIX 2
INFORMATION TO BE SUBMITTED BY TENDERERS RELATING TO POTENTIAL
WHITE PAPER SUBMISSIONS
CATEGORIZATION OF POTENTIAL WHITE PAPER SUBMISSION
(1)
Preferred
(2)
Non-Commercially Confidential
(3)
Commercially Confidential
Yes / No
Yes / No
Will the White Paper Submission postpone Substantial Performance? If yes, what is the
expected duration of the postponement?
Yes / No
Will the White Paper Submission require a variance or other changes to any required
approvals (e.g. Permits)? If yes, please specify.
Yes / No
2.
What are the specific provisions of the Contract Documents that relate to or may be affected by the
White Paper Submission?
3.
What are the specific benefits which the Tenderer is prepared to guarantee will accrue to the Owner?
4.
What are the assumptions or conditions, if any, which underlie the guarantee of specific benefits in item
3 above?
5.
What are the potential financial impacts of the proposed change? (should be broken down into capital,
lifecycle, maintenance, operations)
6.
What is the potential negative impact, if any, associated with the White Paper Submission?
7.
List and describe any other factors which the Tenderer wishes the Owner to consider in considering the
merits of the White Paper Submission.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00400
FORM OF TENDER
PAGE 1 of 24
00 40 00 FORM OF TENDER
Tender by:
Name of Tenderer
Address of Tenderer
Telephone Number
Fax Number
Email Address
CONTRACT DOCUMENTS
.1
TENDERER'S DECLARATIONS
.1
The Tenderer declares that it has obtained and read the Contract Documents.
.2
The Tenderer declares that it understands and agrees to be bound by the Contract Documents.
.3
Without limiting the generality of Item 2.2 of this Tender Form, the Tenderer declares that it has, at
the time of tendering, fulfilled all of those obligations under the Contract, which are required to be
fulfilled by the time of tendering.
.4
The Tenderer declares that all information, which it has provided or will provide to the City, is true.
.5
The Tenderer declares that this tender is made without knowledge, comparison of figures or
arrangement with any other company, firm or person submitting a Tender for the same Work.
.6
The Tenderer declares that no member of the City of Ottawa Council or any officer of the
Corporation of the City of Ottawa is, or will become, interested directly or indirectly as a contracting
party, partner, surety or otherwise or in the performance of the Contract, or in the supplies, Work or
business to which it relates or in any portion of profits thereof, or of any such supplies to be used
therein, or in any of the moneys to be derived therefrom.
The Tenderer agrees to provide, within 24 hours after notice by the City, a complete list of all
Subcontractors and manufacturers that will be retained for the duration of the Contract. This list will
be required prior to award.
.8
The Tenderer agrees that, June 1, 2016, assuming the issuance of an official commence work order
by the timelines outlined within the Contract, the Tenderer will commence the work, assembling all
necessary labour forces and equipment on the site and will continue the work with the utmost
diligence until completion.
.9
The Successful Tender shall complete the Work on or before the City's Date of Substantial
Performance and Completion as set out in the article Time for Completion of Contract / Work in
Document 00200 Instructions to Tenderers.
TENDERERS OFFER
.1
The Tenderer offers to do the Work in accordance with the Contract Documents.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
SECTION 00400
FORM OF TENDER
PAGE 2 of 24
The Tenderer offers to do the Work and to accept payment at the contract price specified in this Tender
Form, in accordance with the Contract Documents.
ADDENDA
.1
The Tenderer acknowledges that it has received, reviewed and provided in its Tender Price for all
work and costs associated with the following addenda:
Addendum No. 1 dated
Addendum No. 2 dated
Addendum No. 3 dated
Addendum No. 4 dated
Addendum No. 5 dated
Addendum No. 6 dated
Addendum No. 7 dated
Addendum No. 8 dated
Addendum No. 9 dated
Addendum No. 10 dated
CONTRACT PRICE
The Schedule of Prices forms the basis for determining the Total Contract Price. Quantities for Unit Price items in
the Schedule of Prices are estimated.
SUMMARY
AMOUNT
$ 975,000
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.1
SECTION 00400
FORM OF TENDER
PAGE 3 of 24
Canadian Dollars
This offer is made this
day of,
CONTRACTOR (TENDERER)
20
WITNESS
Signature
Signature
Signature
Signature
BASIS OF AWARD
The City intends to award a contract to the bidder who submits the lowest responsive bid (as defined
In the City of Ottawa Purchasing By-Law No. 50 of 2000, as amended) by Total Contract Price
(Excluding HST) described herein. Upon formal notification of award the bidder shall thereafter be
known as the Contractor.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00400
FORM OF TENDER
PAGE 4 of 24
Provisional Items
.1
Items of work that are likely to be required during the course of construction but the exact quantities
or requirements of which will depend on ground conditions or other uncertain factors encountered,
are shown in the Schedule of Items and Prices under the heading Provisional Items. The Tenderer
acknowledges that the work in Provisional Items may or may not be executed in the Contract.
.2
Work done under such items will not require an individual Contract Change Order, but will be
authorized in writing and will be measured for payment.
.3
At the discretion of the Owner, this work may or may not be included in the Contract and may or
may not be taken into account by the Owner in comparing tenders and awarding a contract.
.4
The unit prices inserted above for provisional quantities shall be applicable to extras or deductions
even if actual quantities are found to vary considerably from them.
.5
Unless approved by the Owner, the substantial performance of the project shall not be delayed even
if the actual quantities of the provisional items are found to vary considerably.
.6
Provisional items are not major items as defined in CCDC4-2011 and if not used, or are partially
used, partial payment for unused amounts shall not be made.
6.2
6.3
6.4
In addition to the Breakdown of Items and Prices Schedule, the Contractor shall provide a schedule
of values to facilitate payment for lump sum items as per CCDC4-2011, GC5.2.5.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00400
FORM OF TENDER
PAGE 5 of 24
Statement B: Subcontractors
The Contractor named in the form of Tender shall list all subcontractor (s) to be used for the project along with his or
her responsibilities in the space provided below.
Scope of Work
Division 1
Division 2
Division 3
Division 4
Division 5
Division 6
Division 7
Division 8
Division 9
Division 10
Division 11
Division 13
Division 14
Division 15
Division 16
Others (Specify)
Sub-Contractor
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00400
FORM OF TENDER
PAGE 6 of 24
Within twenty four (24) hours of Tender Close, Statement B shall be completed by the three (3) lowest Tenderers and
provided to the Supply Branch, the City of Ottawa.
Replacement, substitution or addition of any Key Team Member and named subcontractor subsequent to the Request
for Pre-Qualification Submission Due Date is not permitted without the prior written consent of the City, which
consent may be withheld by the City. The Key Team Members and named subcontractors shall remain constant after
the Request for Pre-Qualification Submission Due Date through Tendering and until the end of Construction.
If there is any change in the Key Team Members and named subcontractors, subsequent to the Request for PreQualification Submission Due Date, written notice must be provided to the City five (5) business days before such
change. The City, in their sole and absolute discretion, may withhold consent, should the change have a material
adverse impact on the Project. The substitute must meet or exceed the qualifications of the Key Team Member and/or
subcontractor they replace.
In addition, any change, replacement, substitution or addition of a Key Team Member and subcontractor subsequent to
the Request for Pre-Qualification Submission Due Date, without the prior written consent of the City, may be grounds
for disqualification.
Statement C: Conflicts and Unfair Advantage
Tenderers are required to complete Form Conflict of Interest and Unfair Advantage, attached as Statement C within
twenty four (24) hours of Tender Close. Refer to GC17 outlined in Section 00200 Instructions to Tenderers.
END OF SECTION
SUPPLEMENTAL INFORMATION
STATEMENT A: BREAKDOWN OF ITEMS AND PRICES
STATEMENT C: FORM CONFLICT OF INTEREST AND UNFAIR ADVANTAGE
QTY
UNIT
1
1
8,000
1,000
3000
150
500
1
LS
LS
t
hr
hr
hr
hr
LS
2,015
40
2,100
1,915
m
m
m
m
140
145
LS
LS
LS
LS
LS
LS
LS
LS
1
1
1
LS
LS
LS
LS
UNIT PRICE
AMOUNT
Mobilization/Demobilization
General
TBM
Contaminated Soil Disposal Offsite
Street Sweeping
Flusher (Operated)
Hydro Excavating/Vacuum Truck (Operated)
Police Assistance at Intersections
Incentive/Disincentive (Site 3a)
B2.1
B2.2
B3
B3.1
B1
B1.1
B1.1.1
B1.2
B1.3
B2
B3.1.1
B3.1.2
B3.2
B3.3
B3.4
B3.5
B3.6
B3.7
B3.8
B3.9
B3.10
Page 1 of 17
$
$
204.56 $
630,000.00 $
Subtotal Part A
102,280.00
630,000.00
QTY
UNIT
B3.11
LS
B3.11.1
LS
B3.12
LS
B4
21
ea
B4.2
ea
B4.3
54
ea
B4.4
17
ea
B4.5
40
ea
ea
26
ea
LS
172
ea
B4.1
B4.5.1
B4.6
B4.7.1
B4.7.2
B4.8
98
ea
B4.9
31
ea
B4.10
28
ea
15
ea
ea
ea
96
ea
B4.11
B4.11.1
B4.12
B4.13
Page 2 of 17
UNIT PRICE
AMOUNT
QTY
UNIT
B4.14
LS
B4.15
LS
LS
ea
LS
1
1
LS
LS
B4.16
B4.17
B4.18
B5
B6
UNIT PRICE
Subtotal Part B
C1
C1.1
C1.2
C1.2.1
C1.2.2
C1.2.3
C1.2.4
C1.2.5
C1.2.6
Subtotal
LS
t
t
t
t
t
t
C1.2.7
19
C1.2.8
72
C1.2.9
ea
C1.2.10
C1.2.11
C1.2.12
C1.2.13
Tree removal
Dust control
Hydraulic seeding and mulching
Topsoil, imported (100 mm thick)
10
1
1800
180
ea
LS
m2
m3
Page 3 of 17
AMOUNT
C1.2.32
C1.2.33
C1.2.34
C1.2.17
C1.2.18
C1.2.19
C1.2.20
C1.2.21
C1.2.22
C1.2.23
C1.2.24
C1.2.25
C1.2.26
C1.2.27
C1.2.28
C1.2.29
C1.2.30
C1.2.31
QTY
UNIT
30
ea
ea
22
63
90
ea
258
m2
10
m2
61
m2
58
m2
13
4
9
14
6
1
13
ea
ea
m
m2
m2
ea
ea
LS
1
1
LS
LS
LS
C1.3
C1.4
C1.5
C1.6
C1.7
C1.8
C1.9
C1.10
C1.11
Division 3: Concrete
Division 4: Masonry
Division 5: Metals
Division 6: Woods and Plastics
Division 7: Thermal and Moisture Protection
Division 8: Windows and Doors
Division 9: Finishes
Division 10: Furnishings
Division 11: Equipment
1
1
1
1
1
1
1
1
1
LS
LS
LS
LS
LS
LS
LS
LS
LS
C1.12
LS
1
1
1
LS
LS
LS
LS
LS
1000
m2
C1.13
C1.14
C1.15
C2
C2.1
C2.2
C2.2.1
C2.2.2
UNIT PRICE
Subtotal
Page 4 of 17
AMOUNT
QTY
UNIT
LS
200
370
t
t
325
m2
120
60
C2.2.9
17
C2.2.10
ea
C2.2.11
ea
11
LS
C2.2.12
C2.2.13
C2.2.14
C2.2.15
C2.2.16
C2.2.17
C2.2.18
C2.2.19
C2.2.20
C2.2.21
C2.2.22
C2.2.23
2
2
1
12
1
12
5
54
4
ea
ea
ea
ea
LS
ea
ea
m
m
C2.2.24
LS
11
12
1
1
1
1
1
1
1
1
m2
ea
LS
LS
LS
LS
LS
LS
LS
LS
C2.2.25
C2.2.26
C2.2.27
C2.2.28
C2.2.29
C2.2.30
C2.3
C2.4
C2.5
C2.6
Pea Gravel
Tree Grate and Guard
Landscape Plantings
Tree Plantings
Tree Pruning
All Other Sections in Division 2
Division 3: Concrete
Division 4: Masonry
Division 5: Metals
Division 6: Woods and Plastics
Page 5 of 17
UNIT PRICE
AMOUNT
QTY
UNIT
1
1
1
1
1
1
1
1
1
LS
LS
LS
LS
LS
LS
LS
LS
LS
UNIT PRICE
Subtotal
1
LS
LS
282
m2
407
m2
38
650
542
m
t
t
90
90
67
40
20
ea
188
m (P)
119
m (P)
LS
21
17
Page 6 of 17
AMOUNT
QTY
UNIT
40
m (P)
ea
ea (P)
C3.2.22
C3.2.23
C3.2.24
21
1
1250
ea
LS
m2
C3.2.25
C3.2.26
C3.2.27
C3.2.28
125
79
24
1
m3
m
m
ea
C3.2.29
20
C3.2.20
C3.2.21
C3.2.30
C3.2.31
C3.2.32
C3.2.33
C3.2.34
C3.2.35
C3.2.36
C3.2.37
C3.2.38
C3.2.39
C3.2.40
C3.2.41
C3.2.42
C3.2.43
C3.3
C3.4
C3.5
C3.6
C3.7
C3.8
C3.9
C3.10
C3.11
C3.12
C3.13
C3.14
2
2
4
9
2
3
1
8
1
7
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
ea
ea
m
m
ea
ea
ea
m
ea
ea
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
C3.15
LS
LS
LS
20
C4
C4.1
C5
C5.1
C5.2
C5.2.1
UNIT PRICE
Subtotal
Subtotal
Page 7 of 17
AMOUNT
QTY
UNIT
861
m2
971
380
750
51
1
1
4013
m2
t
t
ea
LS
LS
m2
401
5
m3
m
C5.2.10
C5.2.11
C5.2.12
LS
C5.2.13
LS
C5.2.14
LS
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
m2
LS
120
m2 (P)
100
C5.2.15
C5.2.15
C5.3
C5.4
C5.5
C5.6
C5.7
C5.8
C5.9
C5.10
C5.11
C5.12
C5.13
C5.14
C5.15
C6
C6.1
C6.2
C6.2.1
C6.2.2
C6.2.3
C6.2.4
C6.2.5
Tree Pruning
All Other Sections in Division 2
Division 3: Concrete
Division 4: Masonry
Division 5: Metals
Division 6: Woods and Plastics
Division 7: Thermal and Moisture Protection
Division 8: Windows and Doors
Division 9: Finishes
Division 10: Furnishings
Division 11: Equipment
Division 13: Special Construction
Division 14: Conveying Equipment
Division 15: Mechanical
Division 16: Electrical
Site 4: Surface Works
Division 1: General Requirements
Division 2 - Site Works
Full depth removal of asphalt, concrete
sidewalk, curb/gutter
Shave Asphalt Pavement - 40 mm (Dry
Grinding)
Excavation, capping, removal and backfill of
abandoned watermain, watermain, gas main,
sanitary sewer, storm sewer, other utilities
Concrete sidewalks, medians, boulevards and
islands
Granular 'A'
UNIT PRICE
Subtotal
Page 8 of 17
AMOUNT
QTY
UNIT
130
90
50
C6.2.9
38
m (P)
C6.2.10
525 mm PVC SDR35 pipe sanitary sewer including excavation, pipe supply,
installation, and backfilling
42
m (P)
14
m (P)
ea
ea
ea
1
30
6
LS
m
m
LS
1
1
LS
LS
24
ea
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
C6.2.11
C6.2.12
C6.2.13
C6.2.14
C6.2.15
C6.2.16
C6.2.17
C6.2.18
C6.2.19
C6.2.20
C6.2.21
C6.2.22
C6.2.23
C6.2.24
C6.3
C6.4
C6.5
C6.6
C6.7
C6.8
C6.9
C6.10
C6.11
C6.12
C6.13
C6.14
C6.15
C7
UNIT PRICE
Subtotal
Page 9 of 17
AMOUNT
QTY
UNIT
LS
20
1
9
700
1250
59
m2 (P)
LS
m (P)
t
t
m2
C7.2.7
450
m2
C7.2.8
C7.2.9
C7.2.10
200
1530
9
m2
m2
m
C7.2.11
58
C7.2.12
46
ea
18
36
1
1
10667
ea
ea
LS
LS
m2
1067
39
125
m3
m
m
LS
LS
C7.2.24
LS
C7.2.25
ea
C7.2.13
C7.2.14
C7.2.15
C7.2.16
C7.2.17
C7.2.18
C7.2.19
C7.2.20
C7.2.21
C7.2.22
C7.2.23
C7.2.26
C7.2.27
C7.2.28
C7.3
C7.4
C7.5
C7.6
C7.7
C7.8
C7.9
C7.10
5
1
1
1
1
1
1
1
1
1
1
m
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
C7.11
LS
C7.12
LS
Page 10 of 17
UNIT PRICE
AMOUNT
C8.2.6
C8.2.7
C8.2.8
C8.2.9
C8.2.10
C8.2.11
QTY
UNIT
1
1
LS
LS
LS
LS
160
m2
140
m2
76
2
m2
ea (P)
15
LS
76
m2
75
115
t
t
30
20
Subtotal
C8.2.12
16
C8.2.13
ea
C8.2.14
12
C8.2.15
16
ea
ea
1
1
39
8
1
1
1
ea
LS
m
m
LS
LS
LS
C8.2.16
C8.2.17
C8.2.18
C8.2.19
C8.2.20
C8.2.21
C8.2.22
C8.2.23
C8.2.24
C8.3
UNIT PRICE
Page 11 of 17
AMOUNT
QTY
UNIT
1
1
1
1
1
1
1
1
1
1
1
1
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
1
1
1
20
1
300
51
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
LS
LS
LS
m
LS
m
ea
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
ea
LS
39
m2
50
UNIT PRICE
Subtotal
Subtotal
Page 12 of 17
AMOUNT
QTY
UNIT
91
17
17
30
ea
ea
C10.2.12
C10.2.13
ea
ea
C10.2.14
C10.2.15
C10.2.16
ea
C10.2.17
C10.2.18
C10.2.19
C10.2.20
C10.2.21
Tree removal
Tree Plantings
Dust control
Saw-cutting of asphalt
Saw-cutting of concrete curb, sidewalk
2
1
1
35
4
ea
LS
LS
m
m
C10.2.22
LS
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
C10.2.23
C10.2.24
C10.3
C10.4
C10.5
C10.6
C10.7
C10.8
C10.9
C10.10
C10.11
C10.12
C10.13
C10.14
C10.15
C11
Tree Pruning
All Other Sections in Division 2
Division 3: Concrete
Division 4: Masonry
Division 5: Metals
Division 6: Woods and Plastics
Division 7: Thermal and Moisture Protection
Division 8: Windows and Doors
Division 9: Finishes
Division 10: Furnishings
Division 11: Equipment
Division 13: Special Construction
Division 14: Conveying Equipment
Division 15: Mechanical
Division 16: Electrical
Site 9: Odour Control Facility and Surface
Works
UNIT PRICE
Subtotal
Page 13 of 17
AMOUNT
QTY
UNIT
LS
LS
74
m2
132
201
t
t
14
14
12
15
C11.2.9
C11.2.10
C11.2.11
C11.2.12
35
Page 14 of 17
UNIT PRICE
AMOUNT
QTY
UNIT
ea
ea
29
29
ea
ea (P)
3
1
1
245
ea
LS
LS
m2
C11.2.23
C11.2.24
C11.2.25
25
34
4
m3
m
m
C11.2.26
LS
C11.2.27
C11.2.28
C11.3
C11.4
C11.5
C11.6
C11.7
C11.8
C11.9
C11.10
C11.11
Tree Pruning
All Other Sections in Division 2
Division 3: Concrete
Division 4: Masonry
Division 5: Metals
Division 6: Woods and Plastics
Division 7: Thermal and Moisture Protection
Division 8: Windows and Doors
Division 9: Finishes
Division 10: Furnishings
Division 11: Equipment
1
1
1
1
1
1
1
1
1
1
1
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
C11.12
LS
C11.13
C11.14
C11.15
1
1
1
LS
LS
LS
Page 15 of 17
UNIT PRICE
AMOUNT
QTY
UNIT
LS
70
7
12
m (P)
t
t
LS
C12.2.7
11
ea
10
1
10
128
m (P)
LS
m
m
LS
C12.2.9
C12.2.10
C12.2.11
C12.2.12
C12.2.13
AMOUNT
Subtotal
C12.2.6
C12.2.8
UNIT PRICE
C12.2.14
C12.2.15
C12.2.16
C12.2.17
C12.2.17
C12.3
C12.4
C12.5
C12.6
C12.7
C12.8
C12.9
C12.10
Landscape Plantings
Tree Plantings
Site Restoration
Tree Pruning
All Other Sections in Division 2
Division 3: Concrete
Division 4: Masonry
Division 5: Metals
Division 6: Woods and Plastics
Division 7: Thermal and Moisture Protection
Division 8: Windows and Doors
Division 9: Finishes
Division 10: Furnishings
1
1
1
1
1
1
1
1
1
1
1
1
1
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
C12.11
LS
C12.12
C12.13
C12.14
C12.15
1
1
1
1
LS
LS
LS
LS
Subtotal Part C
D1
D2
1
1
Page 16 of 17
Allowance $
Allowance $
100,000.00
75,000.00
$
$
100,000.00
75,000.00
E1
QTY
UNIT
1
1
1
1
1
1
Allowance
Allowance
Allowance
Allowance
Allowance
Allowance
250
Tonne
E2
ea
E2.1
1,000
m3
E2.2
1,000
m3
E3
200
500
m3
500
m3
500
m3
100
m2
100
50
15
2000
100
100
100
100
100
5
t
m2
m3
t
m3
t
m
m3
m3
t
E4
E5
E6
E7
E8
E9
E10
E11
E12
E13
E14
E15
E16
E17
E18
E19
E20
10
10
10
UNIT PRICE
$
$
$
$
$
$
100,000.00
25,000.00
25,000.00
50,000.00
500,000.00
100,000.00
Subtotal Part D
m3
m3
m2
Subtotal Part E
Page 17 of 17
AMOUNT
$
$
$
$
$
$
$
100,000.00
25,000.00
25,000.00
50,000.00
500,000.00
100,000.00
975,000.00
_____________________________
(Name of Tenderer)
Re: City of Ottawa Tender No. [Number] (the Tender)
Unless otherwise disclosed herein, we confirm that neither the Tenderer nor any of its team members has
(or will have) any conflict of interest (as defined below) or obtained an unfair advantage (as defined
below) in connection with making its Tender submission and participating in the Tender process,
including but not limited to:
having knowledge of or the ability to avail itself of information that is confidential to the
Owner in relation to the project, the Tender and the Tender process, other than information
which was disclosed by the Owner to all Tenderers in the normal course of the Tender
process;
in respect of the project, the Tender, its Tender submission and the Tender process, having a
material relationship with any current or former officials, employees or representatives of the
Owner;
as the Government of Canada and Government of Ontario are anticipated to provide funding
for the project, any elected or appointed official or senior employee, agent or representative
of the Government of Canada, Province of Ontario or the Owner having a material financial
interest in or deriving a material benefit from the Tenderer or a team members participation
in the Tender process; or
in respect of the Project, the Tender, its Tender submission and the Tender process, having a
material relationship with those persons listed in Section 32 of the Instructions to Tender, or
their respective officers, directors, employees, partners, shareholders or agents.
The Tenderer and/or its team member(s) hereby disclose the following conflict(s) of interest or unfair
advantage(s):
______________________________________________________________________________
______________________________________________________________________________
Instruction: Fully describe any conflict of interest or unfair advantage. If none exist, please mark Nil.
Where the Tenderer and/or a team member shall disclose a conflict of interest or unfair advantage, the
Owner reserves the right to review such conflict of interest or unfair advantage (including with reference
to any conditions of funding made by the Government of Canada and/or Government of Ontario) and to
exercise all or any rights available to it, including as set out in the Tender.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SECTION 00410
CASH ALLOWANCES
PAGE 1 OF 3
.1
The total Cash Allowance shall be $ 975,000.00 (Nine Hundred Seventy Five Thousand
dollars) as identified in Section 00400 Form of Tender.
.2
The contractor shall carry in Section 00400 - Form of Tender the total cash allowances
identified in Part D for this section and shall include in the Total Contract Price.
.3
The Cash Allowance shall be available for the following noted items. For all items noted
below, no work is to proceed unless directed by the Contract Administrator. Following
direction from the Contract Administrator, the Contractor shall submit a formal plan for
each item for the Contract Administrators review a minimum of fourteen (14) days prior
to implementation.
.1
Dispute Review Board (DRB): This item shall be used for the DRB services as
outlined in Section 00803.
.2
As-Built Drawings: This item shall be used to pay for preparation of as-built
drawings by the Contractor as per the requirements outlined within the
specifications.
.3
Commissioning: This item shall be used to pay for all services relating to the
requirements of Section 01810.
.4
Operation and Maintenance Manuals: This item shall be used to pay for all
services relating to the requirements of Section 01750.
.5
Demonstration and Training: This item shall be used to pay for all services
relating to the requirements of Section 01820.
.6
Warranty Maintenance: This item shall be used to pay for maintenance services
during the one (1) year warranty period beginning at issuance of Substantial
Completion.
.7
NST Pull Back Sewer Interference: Payment against the allowance amount
included on the Form of Tender shall be made for man-made obstructions
encountered during tunneling that stop forward progress of the TBM. Allowance
will cover TBM delay operating cost and repair costs and any associated costs
with removing the obstruction and associated labor. This includes obstructions
related to the Pull-back sewer along the NST including reinforced concrete pipe,
rock bolts and other items that stop forward progress of the TBM and other
potential obstructions along the alignment such as tiebacks. The Contractor is to
provide a plan for dealing with the obstruction for the Contract Administrators
review a minimum of 30 working days prior to TBM arrival at this location.
.8
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00410
CASH ALLOWANCES
PAGE 2 OF 3
CASH ALLOWANCES
.1
Consult with the Contract Administrator in the selection of products or services, obtain
proposals from suppliers and installers, and offer recommendations.
.2
Submit, with application for payment, labour and material invoices, invoices showing
date of purchase, from whom the purchase was made, the date of delivery of the product
or service, and the price, including delivery to the site and applicable taxes.
.3
Cash Allowance payments will only be made with the written authorization of the
Contract Administrator. The Contractor shall have no claim on the unused portion of any
cash allowance.
.4
.5
Cash allowances, unless otherwise specified, cover net cost to the Vendor, subVendor,
products, construction machinery and equipment, freight, handling, unloading, storage,
installation, other authorized expenses and applicable taxes (excluding HST) incurred in
performing the work stipulated under cash allowance item.
.6
Include progress payments on accounts of work authorized under cash allowances in the
Contract Administrator's monthly certificate for payment.
.7
Prepare schedule jointly with the Contract Administrator to show when items called for
under cash allowances must be authorized by the Contract Administrator for ordering
purposes so that progress of Work will not be delayed.
.8
Amounts of each allowance, for work specified in respective specification sections, are
shown in the Form of Tender.
.9
.10
.2
.2
.3
Delivery to site
In addition to amount of allowances include in the Total Contract Price costs for:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.3
SECTION 00410
CASH ALLOWANCES
PAGE 3 OF 3
.2
.3
.4
.5
CONTRACTORS RESPONSIBILITY
.1
1.4
Contractors Duties:
.1
Assist the Contract Administrator and the City in determining qualified suppliers.
.2
.3
.4
.2
.5
.6
Arrange for and process shop drawings, product data and samples.
.7
.8
.9
The Contractor is solely responsible for rectifying and paying for any costs
resulting from transportation damage.
.10
ADJUSTMENT OF COST
.1
Should the net cost be more or less than the allowance, the Contract Amount will be
adjusted by Change Order.
.2
The City reserves the right to use the Cash Allowances identified for other construction
items. The Contractor shall carry this out as directed by the Contract Administrator.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
SECTION 00450
STANDARD DRAWINGS &
STANDARD SPECIFICATIONS
Page 1 of 10
The Contractor acknowledges that certain standard detail drawings, which are provisions
of this Contract, have not been reproduced for inclusion in the Contract Documents.
These standard drawings are listed in subsections SS-1.3 and SS-1.4. Some of the
standard detail drawings may be shown on the Contract Drawings.
1.2
The Contractor acknowledges that the standard drawings referred to in subsections SS1.3 are the Ontario Provincial Standard Drawings (OPSD) as produced and amended by
the government of the Province of Ontario.
Only the municipal and provincial common standards on OPS Volumes 1 to 4 and the
municipal-oriented specifications in OPS volumes 7 and 8 apply to this Contract, unless
specified otherwise in the Contract Documents.
The Contractor also acknowledges that the standard detail drawings referred to in
subsections SS-1.4 are the Standard Detail Drawings as produced and amended by the
City of Ottawa.
The Contractor shall obtain its own copy of the standard detail drawings from the
Standard Tender Documents Vol. #2: Material Specifications and Standard Detail
Drawings dated March 31, 2015.
These documents are available from the City of Ottawa, Infrastructure Services Branch,
and it is the responsibility of the Contractor to ensure that it has the correct document.
Contact information for standards is as follows: standardssection@ottawa.ca.
1.3
The Ontario Provincial Standard Drawings (OPSD) which are provisions of this Contract
are:
OPSD
NO.
Revision
Date
219.---
Nov-2006
403.010
Nov-2013
405.020
Nov-2013
406.010
Nov-2013
Aluminum Ladder
701.010
Nov-2014
701.011
Nov-2014
701.012
Nov-2014
701.013
Nov-2014
701.014
Nov-2014
701.015
Nov-2014
Description
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00450
STANDARD DRAWINGS &
STANDARD SPECIFICATIONS
Page 2 of 10
OPSD
NO.
Revision
Date
705.010
Nov-2014
705.030
Nov. 2014
802.010
Nov-2014
802.013
Nov-2014
802.030
Nov-2010
802.031
Nov-2010
802.032
Nov-2010
802.033
Nov-2010
810.020
Nov. 2013
912.130
Nov. 2008
922.530
Nov. 2010
972.130
Nov. 2012
Description
Guide Rail System, Steel Beam, Steel Post with Offset Block
Assembly Installation Single Rail
Energy Attenuator, End Treatment, Steel Beam Energy Attenuating
Terminal, Extruder Terminal System with Wooden Posts, Installation
Fence, Chain-Link, Installation Roadway
NOTE: OPSD references noted above and in the Specification Sections for Specifications in the
OPSS Volume 3 and Volume 4, shall be the latest revision as of Apr. 2015 unless otherwise
specified.
1.4
The City of Ottawa Standard Detail Drawings which are provisions of this Contract are:
City of Ottawa
Standard Detail Drawings
Date
Sewer
S1 Installation of Catch Basin with Curb and Gutter
Mar. 2009
S2 Installation of Catch Basin with Monolithic Sidewalk and Curb, Barrier and
Depressed Curb
Mar. 2009
Mar. 2009
Mar. 2013
Mar. 2013
Mar. 2006
May 2001
Mar. 2006
Mar. 2005
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00450
STANDARD DRAWINGS &
STANDARD SPECIFICATIONS
Page 3 of 10
S19 Heavy Duty Fish Type Round Catch Basin Cover (Modified OPSD
400.07)
Mar. 2008
Mar. 2008
May 2001
Mar. 2015
Mar. 2015
Mar. 2008
Road
R1 Subdrain Installation Detail
Mar. 2009
May 2001
Fence
F4 200mm Diameter Steel Bollard Installation for Road Closure
Jan. 2015
Feb. 2014
Mar. 2014
Mar. 2014
July 2014
Mar. 2014
Mar. 2014
Feb. 2014
Water
W1 Pipe Joints at Chambers
May 2001
Mar. 2007
Mar. 2007
Mar. 2007
May 2001
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00450
STANDARD DRAWINGS &
STANDARD SPECIFICATIONS
Page 4 of 10
May 2001
May 2001
May 2001
W9 Adjustment Section
May 2001
May 2001
Mar.2008
Mar. 2002
Mar. 2008
Mar. 2013
Mar. 2013
Mar. 2013
Feb. 2004
Mar. 2007
Mar. 2013
May 2001
Mar. 2013
W25.3 Concrete Thrust Blocks for PVC and DI Pipe 400mm and Under
May 2001
W25.4 Thrust Block Dimension Tables for PVC and DI Pipe 400mm and
Under
Mar. 2011
W25.5 Restraining and Retaining Rings for PVC and DI Pipe 400mm and
Under
May 2001
W25.6 Table of Restrained Lengths for PVC and DI Pipe 400mm and Under
Mar. 2011
Mar. 2013
May 2001
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00450
STANDARD DRAWINGS &
STANDARD SPECIFICATIONS
Page 5 of 10
May 2001
Mar. 2005
Mar. 2013
Mar. 2013
Mar. 2014
May 2001
Mar. 2013
Mar. 2013
Mar. 2013
Mar. 2014
Mar. 2011
Mar. 2013
Mar. 2013
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00450
STANDARD DRAWINGS &
STANDARD SPECIFICATIONS
Page 6 of 10
The Contractor acknowledges that certain standard specifications, which are provisions
of this Contract, have not been reproduced for inclusion in the Contract Documents.
These standard specifications are listed in subsections SS-2.3 and SS-2.4, and in the
Schedule of Prices. All references to measurement for payment within these
standard specifications shall not apply.
2.2
2.3
The Ontario Provincial Standard Specifications (OPSS) which are provisions of this
Contract are:
OPSS
No.
102
120
Revision Date
October 1992
November 2014
127
Current
128
180
310
Current
November 2011
November 2012
Description
Weighing of Materials
Use of Explosives
Schedule of Rental Rates for Construction Equipment
including Model and Specification Reference
The Supply of Materials from Designated Sources
Management of Excess Material
Hot Mix Asphalt
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00450
STANDARD DRAWINGS &
STANDARD SPECIFICATIONS
Page 7 of 10
OPSS
No.
Revision Date
311
November 2009
351
353
401
November 2010
November 2010
November 2013
403
November 2010
404
405
November 2010
November 2008
407
November 2014
408
November 2014
409
410
415
416
November 2013
November 2013
November 2013
November 2013
490
November 2010
501
November 2014
504
November 2010
517
November 2010
518
772
803
1150
1541
120.M
UNI
206.M
UNI
212.M
UNI
510.M
UNI
1820.
MUNI
November 2011
November 2012
November 2010
November 2010
November 2012
November 2014
Explosives
November 2013
Grading
November 2013
Borrow
November 2014
Removal
November 2014
Description
NOTE: OPSS references noted above and in the Specification Sections for Specifications in the
OPSS Volume 1 and Volume 2, shall be the latest revision as of Apr. 2015 unless otherwise
specified.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.4
SECTION 00450
STANDARD DRAWINGS &
STANDARD SPECIFICATIONS
Page 8 of 10
The City of Ottawa Standard Special Provisions which are provisions of this Contract
are:
Clause
No.
S.P. No: F-1005
S.P. No: F-1010
SP No: F-1011
SP No: F-1012
SP No: F-1013
S.P. No: F-1014
S.P. No.: F-2060
S.P. No.: F-2120
S.P.No.: F-3130
S.P. No: F-3147
Revision Date
Watermain Pipe
Hydrants
Temporary Services
Water Services
March 2015
March 2008
March 2013
March 2015
March 2015
March 2006
March 2008
March 2005
Mar. 2015
March 2014
March 2015
Description
March 2008
March 2011
March 2009
March 2015
March 2015
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00450
STANDARD DRAWINGS &
STANDARD SPECIFICATIONS
Page 9 of 10
Clause
Revision Date
No.
S.P. No.: F-4491 March 2015
Commissioning of Watermains
Precision Milling
March 2011
March 2013
March 2013
March 2015
March 2008
April 2015
March 2004
March 2004
March 2011
March 2013
March 2014
Description
The City of Ottawa Material Specifications which are provisions of this Contract are:
Clause
No.
M.S. No: MS-13.1
Revision
Date
March 2013
March 2011
Sewer Pipe
March 2011
Sewers-General
March 2014
March 2013
March 2014
Watermain Pipe
March 2015
General Specification
Description
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00450
STANDARD DRAWINGS &
STANDARD SPECIFICATIONS
Page 10 of 10
March 2007
Tracing Wire
March 2013
March 2015
Fire Hydrants
March 2013
Valves
March 2015
Water Meters
March 2013
March 2015
Services
March 2011
Cathodic Protection
March 2015
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE
.1
SECTION 00496
ESCROW BID DOCUMENTS
PAGE 1 OF 5
The three low tenderers shall submit, within three (3) Working Days after opening of the
tenders, one copy of all documentary information generated in preparation of tender
prices for this Project. This material is hereinafter referred to as Escrow Bid Documents
(EBDs). The EBDs of the successful bidder will be held in escrow for the duration of the
Contract and Warranty Period. Escrow Bid Documents of the other bidders will be
returned to the bidders following award and execution of the respective contract.
.2
The successful tenderer agrees, as a condition of award of the Contract, that the Escrow
Bid Documents constitute all the information used in preparation of its tender and that no
other tender preparation information shall be considered in resolving disputes or claims,
or in negotiation of change orders to the Contract.
.3
Nothing in the Escrow Bid Documents shall change or modify the terms or conditions of
the Contract.
1.2
OWNERSHIP
.1
The EBDs are and shall always remain the property of the Contractor subject only to
joint review by the Contract Administrator and the Contractor, except as provided for
herein.
.2
The City acknowledges the information contained in the EBDs is not known outside the
Contractors business, is known only to a limited extent and only by a limited number of
employees of the Contractor, is safeguarded while in Contractors possession, is
extremely valuable to the Contractor, and could be extremely valuable to the
Contractors competitors by virtue of it reflecting the Contractors contemplated
techniques of construction.
.3
The City further acknowledges that the EBDs and the information contained therein are
made available to the City only because such action is an express prerequisite to award
of the Contract. The City acknowledges that the EBDs include a compilation of
information used in the Contractors business to obtain an advantage over competitors
who do not know of or use the contents of the documentation. The City agrees to
safeguard the EBDs and all information contained therein against disclosure, to the
fullest extent permitted by law.
1.3
PURPOSE
.1
EBDs will be used to assist in the negotiation of price adjustments and change orders and
in the settlement of disputes and claims. They will not be used for pre-award evaluation
of the Contractor's anticipated methods of construction or to assess the Contractor's
qualifications for performing the Work.
.2
If Contractor wishes to subcontract any portion of the Work after award that was not
identified in the Tender Documents, City retains the right to require Contractor to submit
Escrow Bid Documents from Subcontractor before subcontract is approved.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.4
SECTION 00496
ESCROW BID DOCUMENTS
PAGE 2 OF 5
Tenderers may submit EBDs in their usual cost estimating format. It is not intended that
extra work is required in preparing the tender; however, the format and contents of the
EBDs must be sufficient to ensure that the EBDs will be adequate to enable complete
and proper understanding and proper interpretation for their intended use. The EBDs
shall be in the English language only.
.2
The EBDs shall clearly itemize, organize and identify the estimated costs of performing
the work of each item contained in the Tender Schedule. Items should be separated into
sub-items as required to present a complete and detailed cost estimate and allow a
detailed cost review. For ease of reference and completeness, each cost item and subitem shall be preceded with a summary sheet, with appropriate references, to its various
cost components. Where alternative construction methods are used in the estimate, the
EBDs shall describe the methods used and pertinent information related to the cost of
such methods. The EBDs shall include all quantity take-offs, crews, equipment,
calculations of rates of production and progress, copies of quotations from subcontractors and suppliers, and memoranda, narratives, consultants reports, add/deduct
sheets and all other information used by the Contractor to arrive at the prices contained
in the tender. Estimated costs shall be broken down into the Contractor's usual estimate
categories, such as direct labor, repair labor, equipment operation, equipment ownership,
expendable materials, permanent materials and subcontract costs as appropriate. Plant
and equipment and indirect costs should be detailed in the Contractor's usual format. The
Contractor's allocation of plant and equipment, indirect costs, contingencies, mark-up
and other items to each tender item shall be clearly indicated.
.3
With regard to the Contractors estimate of TBM work, the EBDs shall specifically
include at least the following: assumed TBM penetration rates for the various rock
conditions; assumed rock support for the various reaches (confirmation of the Contract
requirement to use precast concrete segments); estimated TBM down-time (all
categories) and utilization; assessment of geotechnical, hydrogeological, TBM and
construction variables that affect performance parameters; cutter cost and anticipated
cutter changes, and maintenance or replacements for rings, hubs, bearings, mounting
brackets, etc.; and a detailed TBM manufacturers proposal for equipment and
performance with at least the details as required in the Specifications. Distinguish all of
the foregoing items between tunnel sections for which full pressure-mode is required,
tunnel sections for which full pressure-mode is anticipated by the Contractor, and tunnel
sections for which semi-pressure-mode or no face pressure are required or anticipated.
Consistent with the requirements of this subparagraph, the Contractor, in addition, shall
enclose with the EBDs, the completed Attachment 3, which is included in Section
0496A.
.4
The EBDs shall clearly show in calculations, text, or both, the relationship between
baseline indications presented in the Contract Documents and assumptions that form the
basis for the Contractor's means, methods, equipment selection, rates of production, and
costs.
.5
All costs shall be identified. For bid items for which the extended amount is less than
$10,000, estimated unit costs are acceptable without a detailed cost estimate, provided
that labor, equipment, materials and subcontracts, as applicable, are included and
provided that indirect costs, contingencies, and mark-up, as applicable, are allocated.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
1.5
SECTION 00496
ESCROW BID DOCUMENTS
PAGE 3 OF 5
Bid Documents provided by City should not be included in the EBDs unless needed to
comply with the above requirements.
SUBMITTAL
.1
The EBDs shall be submitted to the Escrow Agent, by each of the three lowest bidders in
a sealed container within three days after the date of the Bid Opening, excluding
Saturdays, Sundays, and legal holidays. The container shall be clearly marked on the
outside with the Bidder's name, date of submittal, project name, Contract No., and the
words Escrow Bid Documents.
.2
.3
Prior to award of the Contract, the EBDs of the apparent successful bidder will be
examined, organized and inventoried by representatives of the Contract Administrator,
together with members of the Contractor's staff who are knowledgeable in how the bid
was prepared. This examination is to ensure that the EBDs are authentic, legible, and
complete. It will not include review of and will not constitute approval of proposed
construction methods, estimating assumptions, or interpretations of the Contract
Documents. Examination will not alter any condition(s) or term(s) of the Contract.
.4
If all documentation required in the Format and Contents has not been included in the
original submittal, additional documentation shall be submitted, at the City's discretion,
prior to award of the Contract. The detailed breakdown of estimated costs shall be
reconciled and revised, if appropriate, by agreement between the Contractor and City,
prior to award of Contract.
.5
If the Contract is not awarded to the apparent successful Tenderer, the EBDs of the next
Tenderer to be considered for award shall be processed, as described above.
.6
.7
If the Tenderer's proposal is based on subcontracting any part of the Work, each
subcontractor whose total subcontract price exceeds five percent of the total contract
price proposed by the Tenderer, shall provide separate EBDs to be included with those of
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00496
ESCROW BID DOCUMENTS
PAGE 4 OF 5
the Tenderer. These documents will be opened and examined in the same manner and at
the same time as the examination described above for the apparent successful Tenderer.
.8
.9
If the Contractor wishes to subcontract any portion of the Work after award, City retains
the right to require the Contractor to submit EBDs from the subcontractor before the
subcontract is approved.
1.6
STORAGE
.1
1.7
The EBDs shall be placed in escrow for the life of the Contract, in the institution
specified herein. The cost of storage will be borne by the City. Should the Contractor
contest the specific storage institution selected by the City, the City may, at its
discretion, negotiate with the Contractor to determine a mutually agreeable institution,
but is under no obligation to do so.
EXAMINATION
.1
The EBDs shall be examined by both City and Contractor, at any time deemed necessary
by either City or Contractor, to assist in the negotiation of price adjustments and change
orders, or the settlement of disputes.
.2
City stipulates and expressly acknowledges that the EBDs constitute trade secrets
and are proprietary and confidential as described herein.
.2
City and Contractor shall each designate, in writing to the other party a minimum
of ten days prior to examination, representatives who are authorized to examine
the EBDs. In addition, with notification to both the City and the Contractor,
members of the Dispute Review Board (DRB) may examine the Escrow Bid
Documents if the DRB determines such examination is necessary for the DRB to
exercise its responsibility to assist in the settlement of a dispute.
.3
Access to the EBDs will take place only in the presence of duly designated
representatives of both City and Contractor; except that:
.4
1.8
.1
.2
Review of EBDs by DRB members shall take place without the City or
Contractor or any of their representatives being present, such review being
agreed by the City and Contractor to constitute private deliberations of the
DRB.
No other person shall have access to the EBDs other than as described in this
Section, unless agreed in writing between the City and the Contractor.
FINAL DISPOSITION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.1
1.9
SECTION 00496
ESCROW BID DOCUMENTS
PAGE 5 OF 5
The EBDs will be returned to the Contractor at such time as the Contract has been
completed and final payment has been made, provided that no claims are either pending
or forthcoming. EBDs will only be returned subsequent to the latter of final resolution of
any outstanding, pending or forthcoming claims or the warranty period.
EXECUTION OF ESCROW AGREEMENT
.1
The three low tenderers, as a condition of award of the Contract, shall execute the
Escrow Agreement included in Section 00496A, and submit the EBDs within the
specified timeframe after bid opening.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00496A
ESCROW BID DOCUMENTS
AGREEMENT AND ATTACHMENTS
PAGE 1 OF 10
ESCROW AGREEMENT
This Agreement made and entered into as of the
day of
, 201 by and
between the [
] (the Owner or City), [ ] as Escrow Agent (Escrow
Agent) and (the Tenderer), Witnesseth That:
WHEREAS the City of Ottawa is a public entity in Ontario Province, which is presently engaged
in a competitive tendering process governed by law to award a construction contract to the lowest
responsible and eligible Bidder for a construction project entitled Combined Sewage Storage
Tunnel; and
WHEREAS the Tenderer has submitted a Tender on this Contract and is one of the apparent
three low Tenderers for this Contract; and Section 00496 of the Specifications of the Contract
Documents requires the apparent three low Tenderers to submit, within three days after the date
of the Tender Opening, excluding Saturdays, Sundays, and legal holidays, one copy of all
documentary information generated in preparation of Tender prices for this Project, as described
in Format and Contents of Section 00496, this material hereinafter referred to as Escrow Bid
Documents or EBDs, to the Escrow Agent together with a certification in the form provided as
Attachment 1 of this Section; and
WHEREAS, the Escrow Agent, for stated consideration, is willing to assume the obligations of
Escrow Agent as agreed herein;
NOW THEREFORE, for consideration mutually acknowledged, the City and the Tenderer each
hereby agree, in respect of itself as appropriate:
.1
The Tenderer shall comply with the provisions of Section 00496 of the
Specifications of the Contract Documents by delivering a copy of the Escrow Bid
Documents to the Escrow Agent within the required time limits together with the
required Certification. The Tenderer shall receive from the Escrow Agent an
Acknowledgement of Delivery of Tender Documentation in the form attached
hereto as Attachment 2, at the time the Tenderer delivers the Escrow Bid
Documents to the Escrow Agent. The Tenderer shall deliver the original Escrow
Agent Acknowledgement and a copy of the Escrow Bid Document Certification,
in the form attached hereto as Attachment 1, to the City within the required time
limits.
.2
The City will comply with the provisions of Section 00496 of the Specifications
of the Contract Documents regarding use of the Escrow Bid Documents and will
safeguard the Escrow Bid Documents and all information contained therein
against disclosure to the fullest extent permitted by law.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
.5
SECTION 00496A
ESCROW BID DOCUMENTS
AGREEMENT AND ATTACHMENTS
PAGE 2 OF 10
The Escrow Agent is hereby expressly authorized to return the Escrow Bid
Documents to the Tenderer if the Tenderer is unsuccessful and not awarded the
Contract with the City. Otherwise, the Escrow Agent is expressly authorized to
only release the Escrow Bid Documents under the following circumstances:
.1
.2
For return to the Tenderer at such time as the Contract has been completed
and final payment has been made provided no claims are outstanding,
pending or forthcoming; or
.3
.4
Should access be requested by the DRB, the EBD would also be released to
the DRB for viewing.
The City and the Tenderer further acknowledge and agree as follows:
.1
That the Escrow Agent: (i) will not be responsible for any of the agreements
referred to herein but will be obligated only for the performance of such
duties as are specifically set forth in the Escrow Agreement; (ii) will not be
obligated to take any legal or other action hereunder which might in its
judgment involve any expense or liability unless it will have been furnished
with acceptable indemnification; (iii) may rely on and will be protected in
acting or refraining from acting upon any written notice, instruction,
instrument, statement, request or document furnished to it hereunder and
believed by it to be genuine and to have signed or presented by the proper
person, and will have no responsibility for determining the accuracy thereof;
and (iv) may consult counsel satisfactory to it, including house counsel, and
the opinion of such counsel shall be full and complete authorization and
protection in respect of any action taken, suffered or omitted by it hereunder
in good faith and in accordance with the opinion of such counsel.
.2
Neither the Escrow Agent nor any of its directors, officers or employees will
be liable to anyone for any action taken or omitted to be taken by it or any of
its directors, officers or employees hereunder except in the case of gross
negligence or willful misconduct to the fullest extent permitted by law. The
City and the Tenderer covenant and agree to indemnify the Escrow Agent
and hold it harmless without limitation to the extent permitted by law from
and against any loss, liability or expense of any nature incurred by the
Escrow Agent arising out of or in connection with this Agreement or with
the administration of its duties hereunder, including, but not limited to, legal
fees and other costs and expenses of defending or preparing to defend
against any claim or liability in the premises, unless such loss, liability or
expense shall be caused by the Escrow Agent's willful misconduct or gross
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00496A
ESCROW BID DOCUMENTS
AGREEMENT AND ATTACHMENTS
PAGE 3 OF 10
negligence. In no event will the Escrow Agent be liable for indirect, special
or consequential damages.
.3
In the event the Escrow Agent's obligations would involve the handling of
Escrow Funds, which is not presently contemplated, the City and the
Tenderer, to the extent permitted by law, agree to assume any and all
obligations imposed now or hereafter by any applicable tax law with respect
to the payment of Escrow Funds under this Agreement, and to indemnify
and hold the Escrow Agent harmless from and against any taxes, additions
for late payment, interest, penalties and other expenses, that may be
assessed against the Escrow Agent on any such payment or other activities
under this Agreement. The City and the Tenderer undertake to instruct the
Escrow Agent in writing with respect to the Escrow Agent's responsibility
for withholding and other taxes, assessments or other governmental charges,
certifications and governmental reporting in connection with its acting as
Escrow Agent under this Agreement. To the fullest extent permitted by law,
the City and the Tenderer agree to indemnify and hold Escrow Agent
harmless from any liability on account of taxes, assessments or other
governmental charges, including, without limitation, the withholding or
deduction or the failure to withhold or deduct same, and any liability for
failure to obtain proper certification or to properly report to governmental
authorities, to which the Escrow Agent may be or become subject in
connection with or which arises out of this Agreement, including costs and
expenses (including reasonable legal fees), interest and penalties.
.4
.5
That the City pay or reimburse the Escrow Agent for any costs and legal
fees incurred in connection with the preparation of this Agreement and to
pay the Escrow Agent's reasonable compensation for its normal services
hereunder as agreed in advance between the Escrow Agent and the City.
The Escrow Agent shall be entitled to reimbursement on demand for all
expenses incurred in connection with the administration of the escrow
created hereby which are in excess of its compensation for normal services
hereunder, including without limitation, payment for any legal fees incurred
by the Escrow Agent in connection with resolution of any claim by any
party hereunder.
.6
The Escrow Agent may at any time resign as Escrow Agent hereunder by
giving thirty days prior written notice of resignation to the City and the
Tenderer. Prior to the effective date of the resignation as specified in such
notice, the City will issue to the Escrow Agent a written instruction
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00496A
ESCROW BID DOCUMENTS
AGREEMENT AND ATTACHMENTS
PAGE 4 OF 10
authorizing redelivery of the Escrow Bid Documents and any Escrow Funds
to a bank or trust company that it selects subject to the reasonable consent of
the Tenderer. Such bank or trust company shall have capital, surplus and
undivided profits in excess of $50,000,000. If, however, the City fails to
name such a successor escrow agent within twenty days after the notice of
resignation from the Escrow Agent, the Tenderer shall be entitled to name
such escrow agent. If no successor escrow agent is named by the City or the
Tenderer, the Escrow Agent may apply to a court of competent jurisdiction
for appointment of a successor escrow agent. The provisions of paragraphs
5.2 and 5.3 shall survive the termination of this Agreement.
.6
Dispute Resolution: It is understood and agreed that should any dispute arise with
respect to the delivery, ownership, right of possession, and/or disposition of the
Escrow Bid Documents and/or any Escrow Funds, or should any claim be made
upon such Fund by a third party, the Escrow Agent, upon receipt of written notice
of such dispute or claim by the parties hereto or by a third party, is authorized and
directed to retain in its possession without liability to anyone, all or any of said
Escrow Bid Documents and/or Fund until such dispute shall have been settled
either by the mutual agreement of the parties involved or by a final order, decree
or judgment of a Court in the Province of Ontario, the time for perfection of any
appeal of such order, decree or judgment having expired. The Escrow Agent may,
but shall be under no duty whatsoever to, institute or defend any legal proceedings
that relate to the Escrow Bid Documents and/or any Escrow Fund.
.7
Consent to Jurisdiction and Service: The City and the Tenderer hereby absolutely
and irrevocably consent and submit to the jurisdiction of the courts of the
Province of Ontario and of any federal court located in said Province in
connection with any actions or proceedings brought against the City and the
Tenderer by the Escrow Agent arising out of or relating to this Escrow
Agreement.
.8
Force Majeure: Neither the City, the Tenderer nor Escrow Agent shall be
responsible for delays or failure in performance resulting from acts beyond their
control. Such acts shall include, but not be limited to, acts of God, strikes,
lockouts, riots, acts of war, epidemics, governmental regulations superimposed
after the fact, fire, communication line failures, power failures, earthquakes or
other disasters.
.9
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
If to the City:
Attn:
If to the Bidder:
Attn:
Attn:
SECTION 00496A
ESCROW BID DOCUMENTS
AGREEMENT AND ATTACHMENTS
PAGE 5 OF 10
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00496A
ESCROW BID DOCUMENTS
AGREEMENT AND ATTACHMENTS
PAGE 6 OF 10
.10
Binding Effect: This Agreement shall be binding upon the respective parties
hereto and their heirs, executors, successors and assigns.
.11
.12
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00496A
ESCROW BID DOCUMENTS
AGREEMENT AND ATTACHMENTS
PAGE 7 OF 10
______________________________
CITY
ESCROW AGENT
By:
Signature
By:
______________________________
Signature
Typed Name
______________________________
Typed Name
Title
______________________________
Title
Date
______________________________
Date
Attest:
By:
Clerk
CONTRACTOR
By:
Signature
Typed Name
Title
Date
Attest:
By:
Secretary
AFFIX SEAL
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00496A
ESCROW BID DOCUMENTS
AGREEMENT AND ATTACHMENTS
PAGE 8 OF 10
ATTACHMENT 1
ESCROW BID DOCUMENT CERTIFICATION
THE UNDERSIGNED HEREBY CERTIFIES THAT THE TENDER DOCUMENTATION
CONTAINED HEREIN CONSTITUTES ALL THE INFORMATION USED IN
PREPARATION OF THE TENDER AND THAT I HAVE PERSONALLY EXAMINED
THESE CONTENTS AND HAVE FOUND THAT THIS TENDER DOCUMENTATION IS
COMPLETE.
SIGNATURE:
NAME:
(Print)
TITLE:
FIRM:
DATE:
ATTEST BY:
(Secretary)
AFFIX SEAL
Bid Date:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00496A
ESCROW BID DOCUMENTS
AGREEMENT AND ATTACHMENTS
PAGE 9 OF 10
ATTACHMENT 2
ACKNOWLEDGMENT OF DELIVERY OF TENDER DOCUMENTATION
,
AS ESCROW AGENT, IDENTIFIED IN CONTRACT DOCUMENTS
FOR THE COMBINED SEWAGE STORAGE TUNNEL PROJECT
HEREBY CERTIFIES THAT
(Name of Contractor)
AS IDENTIFIED BY
(Representative of Contractor)
HAS DELIVERED TO ESCROW AGENTS OFFICE FOR STORAGE, A SEALED CONTAINER,
WHICH TENDERER REPRESENTS TO BE ALL DOCUMENTATION USED IN THE PREPARATION
OF TENDERERS TENDER, OTHERWISE KNOWN AS THE ESCROW BID DOCUMENTS, AS
TENDERER REPRESENTS IT IS REQUIRED TO DO IN ACCORDANCE WITH THE CONTRACT
DOCUMENTS OF THE ABOVE REFERENCED CONTRACT, THIS
DAY OF
, 2015.
BY:
DATE:
ATTEST BY:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
SECTION 00496A
ESCROW BID DOCUMENTS
AGREEMENT AND ATTACHMENTS
PAGE 10 OF 10
ATTACHMENT 3
1.
Did the Contractor rely on either the GDR, GBR or both in preparing its Tender?
2.
If the Contractor did not rely on the GDR, GBR or both in preparing its Tender, attach a narrative
describing the following:
The specific portion(s) of the above-referenced upon which the Contractor did not rely.
What information the Contractor specifically used instead of the portion(s) of the above-reference
reports.
The impact on the Tender price of not using the identified portion(s) of the above-referenced reports.
3.
Complete the following table as a summary of the information required in Section 00496, Article 1.4,
Paragraph 3.
Reach
(TBM
Sections)
4.
Reach
Length
(m)
Cutter
Life
(cm/ring)
Cutter
Changes
(number)
Cutter
Cost
($/cutter)
Instantaneous
Penetration
Rate
(mm/rev)
Average
Penetration
Rate (m/hr)
TBM Down
Time (hrs)
The Escrow Bid Documents shall include, and Tenderer shall confirm the inclusion of such
information:
Any geotechnical reports prepared for and/or commissioned by the Contractor
Tunnel Boring Machine manufacturer's report to the Contractor
END OF SECTION
TBM
Utilization
(%)
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
GENERAL
1.1
SCOPE
SECTION 00803
DISPUTE REVIEW BOARD
PAGE 1 OF 8
.1
A Dispute Review Board (DRB), with highly experienced members, shall be established to
assist in the resolution of disputes, claims and other controversies in connection with, or
arising out of performance of the Work of this Contract. The DRB will assist the
Contractor and the City in resolution of disputes in a timely manner by providing nonbinding, confidential recommendations to the City and the Contractor in accordance with
this section of the specifications, solely based on factual matters presented, and its physical
observations of the project.
.2
The following provisions describe the purpose, procedure, function and key features of
the DRB. A Three-Party Agreement formalizing the creation of the DRB is provided in
Section 00803A. In the event of conflict, the provisions of the Three-Party Agreement
take precedence over the provisions herein.
.3
The DRB will assist in and facilitate the timely and equitable resolution of disputes
between City and Contractor in an effort to avoid construction delay and implementation
of Mediation or Arbitration methods of dispute resolution as provided in General
Conditions Part 8.
.4
It is not intended for City or the Contractor to default on their normal responsibility to
amicably and fairly settle their differences by indiscriminately referring them to the
DRB. It is intended that the DRB encourage the City and Contractor to resolve potential
disputes without resorting to this review procedure.
.5
Either the City or the Contractor may refer a dispute to the DRB. Referral to the DRB
should be initiated as soon as it is apparent that the dispute resolution efforts indicated in
the General Conditions are not succeeding, and prior to initiating Mediation or
Arbitration methods of dispute resolution procedures by either party as required by
General Conditions Part 8.
.6
The DRB shall impartially and promptly consider disputes referred to it, and shall
provide written recommendations to the City and Contractor, to assist in the resolution of
these disputes.
.7
.8
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.2
SECTION 00803
DISPUTE REVIEW BOARD
PAGE 2 OF 8
1.3
At all times during the course of the dispute resolution process, the Contractor shall
diligently continue with the Work as directed, without delay, conforming to the Citys
decision or order, and all applicable provisions of the Contract.
MEMBERSHIP
.1
General: The DRB will consist of three members selected jointly by the City and the
Contractor. The three members will meet to select the member that will act as the
chairman.
.2
Experience: All DRB members shall be experienced with work of the type to be
performed under the Contract, interpretation of Contract Documents, and resolution of
construction disputes.
.3
Neutral and Impartial: DRB members shall be neutral, act impartially, and not have any
conflict of interest, meaning ownership interest, financial interest or contractual
relationships with the City, Contract Administrator or Contractor at any tier as further
described in Article 1.3.4 of this Section.
.4
Criteria for Membership: For purposes of this Section, the term member also includes
the member's current primary or full-time employer, and involved means having a
contractual relationship with the City, Contract Administrator or Contractor at any tier.
The criteria and limitations for membership are:
.1
.2
No member shall have been previously employed by, or have had financial ties to,
any party involved in the Contract within a period of five years prior to award of
the Contract other than for services on a previous DRB.
.3
No member shall have had prior involvement in the Project, of a nature that could
compromise that members ability to participate impartially in the DRB's
activities.
.4
During his or her tenure on the DRB, no member shall be employed, including feebased consulting services, by any party involved in the Contract, except with the
express approval of both parties.
.5
During his or her tenure on the DRB, no member shall engage in a discussion or
make an agreement with any party involved in the Contract regarding employment
after the Contract is completed.
.6
All members shall be fluent in English and shall prepare their recommendations in
English.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.7
SECTION 00803
DISPUTE REVIEW BOARD
PAGE 3 OF 8
.5
.6
Disclosure Statement: Before their appointments are final, all three prospective
members shall submit complete disclosure statements for the approval of both the City
and Contractor. Each statement shall include a resume of experience, together with a
declaration describing all past, present and anticipated or planned future relationships,
including indirect relationships through the prospective member's primary or full-time
employer, to this Project and with all parties involved in the Contract. Disclosure of
close professional or personal relationships with all key members of all parties to the
Contract shall be included. Relationships with any party indirectly involved shall also be
disclosed, including relationships with the Contract Administrator, designers, architects,
engineers, or other professional service firms or consultants, joint-venture partners,
subcontractors of any tier, and suppliers on this project.
.7
Nomination and Approval of the Three Members: The City and Contractor shall each
prepare a list of 10 proposed DRB members and convey the names and reference
information to the other party within 20 Working Days after Award of the Contract. The
City and the Contractor shall meet within 10 Working Days of receipt of both lists to
jointly select and nominate three members to serve as the DRB. The Contract
Administrator, will solicit from each nominee the resume and disclosure statement
described in Paragraph 1.3.6 of this Section. Nominees shall be requested to provide
requested information within two weeks of receipt of notice. Within two weeks of
receipt of resumes and disclosure statements, the City and Contractor shall meet and
shall either approve all three nominees or reject one or more nominees. In the event of
rejection, the City and Contractor shall reconsider the remaining individuals from the
original list of 10 prospective members. One or more names shall be selected as required,
and the process for soliciting resume(s) and disclosure statement(s) shall be repeated
until three members are approved to serve on the Board.
.8
.9
.1
Immediately after the selection of the three DRB members, the Contract
Administrator will notify the selected members of their approval, and request the
three members to confer and select among themselves one member to act as the
chairman. The process of electing the chairman will be completed within three
weeks of the notification of the three DRB members.
.2
In the event of an impasse in selection of the member to act as the chairman, the
chairman shall be selected by mutual agreement of the City and Contractor.
Execution of Three-Party Agreement: The City, Contractor, and all three members of
the DRB shall execute the Three-Party Agreement provided in Section 00803A within
four weeks after the selection and approval of the three members.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.4
SECTION 00803
DISPUTE REVIEW BOARD
PAGE 4 OF 8
OPERATION
.1
General
.1
The DRB shall formulate its own operating procedures, which shall be in
accordance with the provisions of these specifications. The procedures adopted by
the DRB will be in writing and provided to the City and the Contractor for their
approval. The procedures shall be kept flexible to adapt to changing situations.
The DRB shall initiate, with the City's and Contractor's concurrence, new
procedures or modifications to old ones, whenever this is deemed appropriate.
.2
Neither party shall solicit any DRB member's advice or consultation on matters
concerning the conduct of the Work outside of a DRB meeting where all parties
are present and aware of such requests.
.2
Reports to DRB: The members will be kept informed of construction activities and other
developments by means of regular weekly progress reports, minutes of progress
meetings, and other relevant information prepared by the City, Contract Administrator
and Contractor.
.3
Regular Visits by DRB: The DRB shall visit the Project site and meet with
representatives of the City, Contract Administrator and Contractor at regular intervals,
with a minimum frequency of at least once every three months, and more frequently at
times of critical construction events. The frequency and scheduling of these visits shall
be as agreed among the City, Contractor and the DRB, depending on the progress of the
Work. In case of failure to agree, the DRB shall schedule the visits.
.4
Regular Meetings with DRB: The regular meetings shall be held at the job site. Each
meeting shall consist of an informal round table discussion followed by field observation
of the Work. The round table discussion shall be attended by selected personnel from the
City, Contract Administrator and Contractor. The regular meeting agenda shall generally
include the following:
.1
.2
.3
.4
.1
.2
.3
.4
.5
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
SECTION 00803
DISPUTE REVIEW BOARD
PAGE 5 OF 8
.5
Such other items as the parties may wish to discuss with the DRB.
.6
.7
.5
The Contract Administrator shall prepare the minutes of regular meetings and circulate
them for comments, revisions and/or approval of all concerned.
.6
The field observations shall cover all active segments of the work. The DRB members
shall be accompanied by the representatives of the City, Contract Administrator and
Contractor.
1.5
.2
By written request for review, either the Contract Administrator or Contractor may
request that the DRB review any disputes, claims and other controversies in connection
with, or arising out of performance of the Work, which the parties have considered, but
have been unable to resolve.
.3
Simultaneous with submittal to the DRB Chair, a copy of the request for review shall be
provided to the other Board members and the other party. The request for review shall
state clearly and concisely the specific issues of the dispute to be considered by the DRB.
.4
When a dispute is submitted to the DRB it may be heard at the next regular meeting or at
a special meeting, as agreed by both parties. For an urgent matter, the DRB shall meet
within two weeks of notification.
.5
During the hearing the Contractor and City shall each have ample opportunity to be
heard and to offer evidence. Detailed procedures are given in Article 1.6 of this Section.
The DRB's recommendations for resolution of the dispute will be given in writing, to
both the City and Contractor within two weeks of completion of the hearings. In
difficult or complex cases, and in consideration of the DRB's schedule, this time may be
extended by mutual agreement of all parties.
.6
.7
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00803
DISPUTE REVIEW BOARD
PAGE 6 OF 8
either acceptance or rejection of the DRB's recommendations. The failure of either party
to respond within the specified period shall be deemed an acceptance of the DRB's
recommendations. If, with the aid of the DRB's recommendations, the City and
Contractor are able to resolve their dispute, the Contract Administrator will promptly
process any required Contract Change Orders consistent with the requirements of
General Conditions Part 6, CHANGES IN THE WORK and any revisions stated in the
Amendments or Supplemental Conditions. Acceptance by the City of a report on
entitlement only, or on entitlement with guidelines for quantum, does not obligate the
City to any particular quantum amount.
.8
Should the dispute remain unresolved, either party may appeal or request that the DRB
clarify its recommendation or, if new evidence has become available, reconsider its
recommendation.
.9
Although both the City and Contractor should place great weight on the DRB's
recommendations, they are not binding. If the DRB's recommendations do not resolve the
dispute, the written recommendations, including any minority report, will be admissible
as evidence in any subsequent dispute resolution proceeding including but not limited to
mediation.
1.6
CONDUCT OF HEARING
.1
Prehearing Submittals:
.1
Written position statements shall be submitted to each DRB member before the
hearing begins. Position statements shall include such backup information and
data as is referenced in the position statement, and shall be tabbed, indexed, and
the pages consecutively numbered. The DRB may also request a presentation of
factual documentation, prepared jointly by the parties.
.2
Position statements shall include the basis and justification for the partys
position, with reference to contract language and other supporting documents for
each element of the dispute. In order to minimize duplication and repetitiveness,
the parties may identify a common set of documents that will be referred to by
both parties and submit them in a separate package.
.3
When the scope of the hearing includes quantum, the referring party shall include
a schedule impact analysis and full cost details, calculated in accordance with
methods set forth in the Contract. This requirement does not apply if the scope of
the hearing and any submitted position statements are to be made for entitlement
alone or for entitlement with guidelines for quantum.
.4
The number of copies, distribution requirements, and time for submittal will be
established by the DRB and communicated to the parties by the Chair.
.2
Location: Normally the hearing will be conducted at the job site. However, any location
in the greater Ottawa area that would be more convenient and still provide all required
facilities and access to necessary documentation is satisfactory. Private meetings of the
DRB may be held at any convenient location.
.3
Proceedings:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
.5
.6
SECTION 00803
DISPUTE REVIEW BOARD
PAGE 7 OF 8
.1
The Chairman of the DRB will act as Chairman of the hearing, or he may appoint
one of the other members. A formal transcript will not be prepared. In special
cases, when requested by either party, the DRB may allow preparation of a
transcript by a court reporter. Audio or video recordings will not be permitted.
.2
The party requesting DRB review will first present its position, followed by the
other party. If so requested by the City, the Contract Administrator may present
the Citys position on behalf of the City and otherwise participate in the hearing
along with or on behalf of the City. Each party will then be allowed successive
rebuttals until all aspects are fully covered. The DRB members may ask questions,
request clarification, or ask for additional data. In difficult or complex cases,
additional hearings may be necessary in order to consider and fully understand all
the evidence presented by both parties. Both the City and Contractor shall be
provided full and adequate opportunity to present all of their evidence,
documentation and testimony regarding all issues before the DRB.
.3
.4
During the hearing, no DRB member shall express any opinion concerning the
merit of any facet of the case.
Participants:
.1
The City, Contract Administrator and Contractor shall have representatives at all
hearings.
.2
Attorneys may attend hearings and provide consultation to their clients, but they
shall not be allowed to address the DRB.
A party intending to offer an outside experts analysis at the hearing shall disclose
such intention in writing to the other party and to the DRB no less than 30 days
prior to the due date for delivering the pre-hearing submission. The experts name
and a general statement of the area of the dispute that will be covered by his or her
testimony shall be included in the disclosure.
.2
Upon receipt of the above disclosure, the other party shall have the opportunity to
secure the services of an outside expert to address or respond to those issues that
may be raised by the other partys outside expert. The disclosure requirements
shall be the same as that specified above, except the time requirement is 10 days.
.3
The cost for securing outside expert services shall be borne entirely by the party
securing such services.
DRB Deliberations:
.1
After the hearing is concluded, the DRB shall meet to formulate its
recommendations. All DRB deliberations shall be conducted in private, with all
individual views kept strictly confidential. The DRB's recommendations, together
with explanations of its reasoning, shall be submitted as a written report to both
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00803
DISPUTE REVIEW BOARD
PAGE 8 OF 8
.7
1.7
Part 2
2.1
Part 3
3.1
.2
The DRB shall be permitted to consult with outside experts, including independent
legal counsel. Prior to arranging for outside experts, the DRB shall obtain prior
approval from the City and the Contractor by providing a statement explaining the
need for such expert assistance and an estimate of the cost. Such outside experts
shall provide disclosure statements as per Article 1.3.6 of this Section and agree to
maintain confidentiality regarding the engagement, as is the case for the DRB
members.
.3
When deliberating and drafting its decision, the DRB may request position
statements or legal briefs from each side.
.4
The DRB shall make every effort to reach a unanimous recommendation. If this
proves impossible, the dissenting member shall prepare a minority report.
All information presented to the DRB and all deliberations and recommendations, shall,
except as provided herein, be kept strictly confidential. The DRB members shall not,
during their tenures as members, and at any time thereafter, reveal any information
presented to the DRB or obtained in their capacity as DRB member, or disclose any
recommendation, to any third party.
COMPENSATION AND LOGISTIC SUPPORT
.1
Fees and expenses of all three members of the DRB shall be shared equally by the City
and Contractor. The City, will mail progress reports, will provide administrative services,
such as conference facilities and secretarial services, and will bear the cost of these
services. If the DRB desires special services, such as preparation of transcripts by a
Court Reporter or similar party, legal or other consultation, accounting, data research,
and the like, both parties must agree, and the costs will be shared by them as mutually
agreed.
.2
The Contractor shall pay the invoices of all DRB members after approval by both parties.
The Contractor will then bill the Owner for 50 percent of such invoices via its normal
monthly progress invoices.
Products
NOT USED
Execution
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
SECTION 00803A
DISPUTE REVIEW BOARD
THREE PARTY AGREEMENT
PAGE 1 OF 8
THIS THREE PARTY AGREEMENT (Agreement) made and entered into this
, 2016 , between:
day of
,and
WITNESSETH, that
WHEREAS, the OWNER is now engaged in the construction of the COMBINED SEWAGE STORAGE
TUNNEL; and
WHEREAS, the COMBINED SEWAGE STORAGE TUNNEL Contract (CONTRACT) provides for the
establishment and operation of a BOARD to assist in resolving disputes, claims and other controversies; and
WHEREAS, the BOARD is composed of three members, jointly selected and approved by the OWNER and
by the CONTRACTOR;
NOW THEREFORE, in consideration of the terms, conditions, covenants and agreements contained herein,
or attached and incorporated and made a part hereof, the parties hereto agree as follows:
1.1
DESCRIPTION OF WORK
.1
In order to assist in the resolution of disputes, claims and other controversies between the
OWNER and CONTRACTOR arising from or related to the Construction Contract, the
OWNER has provided, in the Contract, for the establishment of a Dispute Review Board.
The intent is for the BOARD to fairly and impartially consider the disputes referred to it,
and to provide written recommendations to the OWNER and CONTRACTOR for
resolution of these disputes.
.2
The members of this BOARD shall perform the services necessary to participate on this
BOARD in accordance with the Scope of Work.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.2
SECTION 00803A
DISPUTE REVIEW BOARD
THREE PARTY AGREEMENT
PAGE 2 OF 8
SCOPE OF WORK
The Scope of Work of the BOARD includes, but is not limited to, the following:
.1
.2
General
.1
.2
The BOARD members shall become familiar with the Contract Documents,
review periodic reports, and maintain a current file.
.3
The BOARD members shall visit the Project site to keep abreast of construction
activities and to become familiar with the Work in progress. The frequency, time,
and duration of these visits shall be mutually agreed upon among the BOARD, the
OWNER and the CONTRACTOR. In case of failure to agree, the BOARD shall
schedule the visits at intervals not to exceed three months.
.4
Establish Procedures
.1
.3
During its first meeting at the Project site, the BOARD shall, with the agreement
of all parties, establish procedures for the conduct of its routine site visits and its
hearings of disputes. The conduct of its business shall comply with the provisions
of Section 00803 and requirements of this Agreement.
Upon receipt by the BOARD of a written Request for Review of a dispute, either
from the OWNER or the CONTRACTOR, the BOARD shall convene a hearing to
review and consider the dispute. Both the OWNER and CONTRACTOR shall be
given the opportunity to present their evidence at these hearings. Both the
OWNER and the CONTRACTOR are encouraged to provide exhibits,
calculations, and any other pertinent material to the BOARD for review prior to
the hearing. All such material shall be given in the same form and content to all
parties to this agreement at the same time.
.2
It is expressly understood that all BOARD members are to act impartially and
independently in the consideration of facts and conditions surrounding any
dispute, and that the recommendations concerning any such dispute are advisory
and not binding, unless agreed otherwise by the OWNER and the
CONTRACTOR.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
Member Replacement
.1
1.3
SECTION 00803A
DISPUTE REVIEW BOARD
THREE PARTY AGREEMENT
PAGE 3 OF 8
Should the need arise to appoint a replacement BOARD member, the replacement
member shall be appointed in the same manner as the original member was
appointed. The selection of a replacement BOARD member shall begin promptly
upon notification of the necessity for a replacement and shall be completed within
four weeks. This Agreement will be amended to indicate changes in BOARD
membership.
BOARD RESPONSIBILITIES
.1
Maintain impartiality and avoid conflicts of interest by continuing to meet the specified
requirements for nominees for Board members. Promptly advise all parties upon
becoming aware of any development that could be perceived as a conflict of interest.
.2
.3
Do not express an individual or collective opinion of merit, in whole or in part, for any
potential or other dispute at any time prior to the issuance of a report, except in the case
of an advisory opinion.
.4
Except as required when performing the duties of the Chair or conducting a hearing that
the OWNER or CONTRACTOR refuses to attend, do not meet or communicate with
either the OWNER or CONTRACTOR in the absence of the other.
.5
Consider the facts and conditions forming the basis for a referred dispute impartially and
independently, and evaluate the merits based on careful consideration of all contract
requirements, applicable law and regulations, and the facts and circumstances of the
dispute. Do not:
.1
Ignore or undermine the clear intent of the Contract, or disregard or alter any
requirements of the Contract or allocation of risk specified therein.
.2
Supplant or otherwise interfere with the respective rights, authority, duties, and
obligations of either the OWNER or CONTRACTOR as set forth in the Contract
Documents.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00803A
DISPUTE REVIEW BOARD
THREE PARTY AGREEMENT
PAGE 4 OF 8
.6
.7
Prior to receiving any request for review, the BOARD will encourage the resolution of
differences at the job level, consistent with the requirements of General Conditions, Part
8 Dispute Resolution.
.8
Except for providing the services required in the Agreement, the BOARD and its
individual members shall refrain from giving any advice to either party concerning
conduct of the Work or the resolution of problems, which might compromise the
BOARD's integrity.
1.4
CONTRACTOR RESPONSIBILITIES
.1
Except for its participation in the BOARD's activities as provided in the Contract
Documents and in this Agreement, the CONTRACTOR shall not solicit advice or
consultation from the BOARD or its members on matters dealing with the conduct of the
Work or resolution of problems, which might compromise the BOARD's integrity.
.2
The CONTRACTOR shall furnish to each BOARD member one copy of all documents it
has, other than those furnished by the OWNER, which are pertinent to the performance
of the BOARD, with copies to the OWNER.
.3
The CONTRACTOR shall cooperate with the OWNER and BOARD to facilitate
presentation of disputes and the timely and impartial resolution of disputes that are
referred to the BOARD.
1.5
OWNER RESPONSIBILITIES
.1
Except for its participation in the BOARD's activities as provided in the Contract
Documents and in this Agreement, the OWNER shall not solicit advice or consultation
from the BOARD or its members on matters dealing with the conduct of the Work or
resolution of problems, which might compromise the BOARD's integrity.
.2
The OWNER shall furnish each BOARD member one copy of the conformed Contract
Documents, including but not limited to, the Specifications, Drawings, Geotechnical
Baseline Report, Geotechnical Data Report, addenda, progress schedule and updates,
weekly progress reports, minutes of progress meetings, change orders, and other
documents pertinent to the performance of the Contract, and necessary to the BOARD's
work.
.3
The OWNER will, in cooperation with the CONTRACTOR, coordinate the operations of
the BOARD.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00803A
DISPUTE REVIEW BOARD
THREE PARTY AGREEMENT
PAGE 5 OF 8
.4
The OWNER will arrange for or provide conference facilities at or near the site, and
provide secretarial and copying services.
.5
The OWNER will cooperate with the CONTRACTOR and BOARD to facilitate
presentation of disputes and the timely and impartial resolution of disputes that are
referred to the BOARD.
1.6
The BOARD shall be active throughout the duration of the Contract. It shall begin
operation upon written authorization of the OWNER following execution of this
Agreement, and shall terminate its activities on completion or termination of the
Contract.
.2
The BOARD members shall not begin any work under the terms of this Agreement until
authorized in writing by the OWNER.
1.7
PAYMENT
.1
Invoices of the BOARD members shall be paid by the CONTRACTOR. Payments shall
constitute full compensation for work performed and services rendered, and for all
materials, supplies and incidentals necessary to serve on the BOARD.
.1
.2
Payment for services rendered by the three members of the BOARD will
be made at the rate agreed to between the OWNER, the
CONTRACTOR, and the members. Changes in the billing rate are
subject to agreement between the OWNER, the CONTRACTOR and the
members.
.2
Payments
.1
Each BOARD member may submit invoices for payment for work
completed not more than once per month during the progress of the
Work. Such invoices shall be in a format approved by the OWNER and
CONTRACTOR, and accompanied by a general description of activities
performed during that period. The value of the work accomplished for
payment shall be established from the billing rate and hours expended by
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 00803A
DISPUTE REVIEW BOARD
THREE PARTY AGREEMENT
PAGE 6 OF 8
.3
1.8
The cost records and accounts pertaining to this Agreement shall be kept
available for inspection by representatives of the OWNER or
CONTRACTOR for three years after final payment.
ASSIGNMENT
.1
1.9
BOARD members shall not assign any of the Work of this Agreement.
TERMINATION OF AGREEMENT
.1
This Agreement may be terminated by mutual agreement of the OWNER and the
CONTRACTOR at any time upon not less than four weeks written notice to the other
parties.
.2
BOARD members may withdraw from the BOARD by providing four weeks written
notice. BOARD members may be terminated for or without cause. The OWNER and
CONTRACTOR must agree to terminate a member.
1.10
LEGAL RELATIONS
.1
The parties hereto mutually understand and agree that each BOARD member, in the
performance of his duties on the BOARD, is acting in the capacity of an independent
agent and not as an employee of either the OWNER or the CONTRACTOR.
.2
The OWNER and CONTRACTOR expressly acknowledge that each BOARD member is
acting in a capacity intended to facilitate resolution of disputes. Accordingly, it is agreed
and acknowledged that, to the fullest extent permitted by law, each BOARD member
shall be accorded quasi-judicial immunity for any actions or decisions associated with
the consideration, hearing, and recommendation of resolution for disputes rightfully
referred to the BOARD.
.3
Each BOARD member shall be held harmless for any personal or professional liability
arising from or related to BOARD activities. To the fullest extent permitted by law, the
OWNER and CONTRACTOR shall indemnify all BOARD members for claims, losses,
demands, costs and damages (including reasonable attorney fees) for bodily injury,
property damage, or economic loss arising out of or related to BOARD decisions. The
foregoing indemnity is a joint and several obligation.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.11
SECTION 00803A
DISPUTE REVIEW BOARD
THREE PARTY AGREEMENT
PAGE 7 OF 8
Any dispute among the parties hereto, arising out of the Work or other items of this
Agreement, which cannot be resolved by negotiation and mutual concurrence between
the parties, shall be referred to either mediation or arbitration according to procedures as
stated in CCDC4-2011 GC 8.0.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
SECTION 00803A
DISPUTE REVIEW BOARD
THREE PARTY AGREEMENT
PAGE 8 OF 8
IN WITNESS WHEREOF, the parties hereto have executed this Agreement as of the day and year first
above written.
BOARD MEMBER
BOARD MEMBER
Signature
Signature
Typed Name
Typed Name
Date
Date
BOARD MEMBER
Signature
Typed Name
Date
CONTRACTOR
OWNER
By:
By:
Signature
Signature
Typed Name
Typed Name
Title
Title
Date
Date
Attest:
By:
Attest:
By:
Clerk
Secretary
AFFIX SEAL
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DEFINITIONS
SECTION 01010
SUMMARY OF WORK
PAGE 1 OF 8
.1
The City of Ottawa is hereinafter and elsewhere in the Contract Documents referred to as
the Owner. The contract documents may refer to the Owner, the City of Ottawa,
the City and City. All these have the same meaning as the Owner.
.2
The contract documents may refer to Consultant, Engineer, Owners Agent and
Contract Administrator. All these have the same meaning as Consultant.
.3
Where the word provide is used in any Specification Section, it shall mean furnishing
and incorporating a specified item, product, or material into the Works, including all
necessary labour, materials, and equipment to perform the Work required, ready for use
by the Engineer.
.4
Where the words demolish and demolition are used in any Specification Section,
they shall mean remove and dispose of as specified in Section 02222 Demolition and
Removal.
.5
.6
1.2
GENERAL SUMMARY
.1
This section outlines in general the work to be done under the Contract in accordance
with the contract drawings and specified herein.
.2
The Contractor shall supervise, organize, coordinate and direct all construction
operations described in the contract documents, regardless of the division in which the
works are specified. The Contractor shall resolve conflicts arising between trades, subcontractors, suppliers and/or other contractors working in the adjacent area.
.3
Construct and test foundations, structures, pipelines, sewers and tunnels, shafts,
buildings, tanks, equipment and other facilities shown on the contract drawings and
specified herein.
.4
.5
In addition to constructing the works shown on the drawings, design, construct, and
maintain, unless otherwise specified or shown on the drawings, all temporary works and
facilities required for the construction of the works. Remove temporary works and
facilities when construction is completed. Temporary works and facilities include, but
are not limited to, the following:
.1
.2
Shoring and bracing systems for excavations whether part or all is left in place or
not, shall be designed, approved and stamped by a Professional Engineer Licensed
in Ontario.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.3
SECTION 01010
SUMMARY OF WORK
PAGE 2 OF 8
.3
.4
.5
.6
Falsework and bracing for formwork or for other parts of the works while under
construction.
.7
Bracing and shoring for partially completed steelwork, precast concrete, existing
structures and pipelines, or other assembly.
.8
Scaffolding.
.9
.10
.11
Silt fencing and other erosion and sediment control measures such as tire washing
stations.
.12
Protection and support for existing structures and facilities as necessary for the
construction to proceed.
.13
.14
.15
.16
.17
.18
DESCRIPTION OF WORK
.1
The description of the Work is not, nor is it intended to be, complete and all inclusive.
.2
In general, the Work under this contract consists of supply and installation of materials,
labour and equipment for the construction of the Combined Sewage Storage Tunnel
(CSST) inclduing, but not limited to, the following. The list below is provided for
general reference and is not considered exhaistive and does not relieve the Contractor of
their responsibility to comply with all requirements of the Contract Documents:
.1
West End Shaft (Site 1): New EWT Access Chamber, miscellaneous works
at the existing Diversion Chambers, electrical and instrumentation and
control modifications at the existing Real Time Control regulator control
vault, and a new Odour Control Building and supporting facilities. This site
will serve as the TBM extraction point for the EWT.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
SECTION 01010
SUMMARY OF WORK
PAGE 3 OF 8
.2
.3
.4
Rideau Canal Regulator (Site 3b): Modifications to the existing Real Time
Control regulator including electrical and instrumentation and control
removals, gate and actuator abandonment/decommissioning and
miscellaenous concrete works.
.5
Nicholas Street Shaft (Site 3c): EWT Access Structure, miscellaneous site
works, and mid-point launch and/or extraction shaft for EWT construction
and associated air vent chamber including temporary electrical power for
TBM operations and miscellaneous construction requirements.
.6
Cumberland Street Shaft (Site 4): Access structure on the EWT and
associated air vent chamber.
.7
EWT Outlet (Site 5): The site will be the primary staging area for EWT
construction and include the tunnel launch or extraction shaft. Outlet
chamber to control diversion of flows from the Rideau River Collector
(RRC) to the EWT, and EWT flows to the existing Interceptor Outfall
Sewer (IOS), including temporary electrical power for TBM operations and
miscellaneous construction requirements. New control building within the
existing Keefer Biofilter grounds to house the electrical, control and
communications equipment.
.8
RRC Diversion (Site 5c): New diversion sewer and RRC overflow sump
chamber to convey RRC flow to the outlet chamber.
NST Overflow (Site 6): Emergency overflow for EWT/NST to Kent Street
storm tunnel outfall chamber north of the Supreme Court within the
escarpment. New chamber for connection of NST to outfall chamber,
equipped with overflow weir and associated level monitoring and
communication equipment. Replacement of the existing Kent Storm Sewer
outlet and new connection chamber with surface outfall to the Ottawa
River. This site will serve as the TBM extraction point for the NST.
.2
McLeod Street Drop (Site 8): Vortex drop chamber for future sewer with
de-aeration chamber, connection to the NST, and associated air vent
chamber.
.3
Catherine Street Drop (Site 9): NST access and drop structure to direct
flows from the existing combined sewer in a new structure to the NST
access/drop structure. Odour Control Building complete with air duct
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01010
SUMMARY OF WORK
PAGE 4 OF 8
Chamberlain Shaft (Site 10): This site will be the primary staging area for
NST construction including a launch shaft. New domestic flush water shaft
to house isolation gates and associated level monitoring equipment for
flushing of the NST, and associated air vent chamber, including temporary
electrical power for TBM operations and miscellaneous construction
requirements.
.3
Supply, installation, testing and commissioning of flap gates, isolation style slide
gates and motorized actuators including stem, stem supports and associated
mounting assembly at locations indicated on the Contract Drawings.
.4
.5
Supply, install, calibrate, test and commission all mechanical, process, electrical,
communication and instrumentation equipment, control systems, cables, wires,
ductbanks, lighting and associated appurtenances shown on the drawings and
specified herein to meet functional and operational requirements.
.6
.7
.8
Connection and tie-in of the new equipment systems and utility services to the
existing systems.
.9
.10
.11
.12
.13
.14
Coordinate with the City of Ottawa staff for the system programming and SCADA
Site Acceptance Tests.
.15
Support the SCADA Site Acceptance Test that will be led by City staff.
.16
.17
.18
Ensuring that City has access to operating infrastructure at all times, in or near the
construction sites.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.4
SECTION 01010
SUMMARY OF WORK
PAGE 5 OF 8
.19
Clean and tidy access and egress routes for all personnel and equipment traffic.
.20
.21
.22
Successful continuous operation of the entire CSST system over the warranty
period. The City of Ottawa will operate the CSST system over this period.
.23
.24
Warranty service, inspection and support including cleaning and confined space
entry support as needed.
CONTRACT METHOD
.1
.2
The Contract Work within all sites in the Combined Sewage Storage Tunnel
Construction Limit will be paid at the unit prices as specified in the Schedule of Items
and Prices following the requirements of CCDC4-2011, Section 00100 Amendments to
the CCDC4 2011 Agreement and Section 00105 Supplementary Conditions CCDC42011 Specifications.
1.5
CONSTRUCTION CONSTRAINTS
.1
1.6
Refer to Section 01117 Construction Sequences and Constraints for other details.
CODES AND PERFORMANCE REQUIREMENTS
.1
.2
1.7
.1
Contract documents
.2
Specifications
.3
Addenda
.4
.5
.6
.7
.8
.9
CONTRACT DRAWINGS
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01010
SUMMARY OF WORK
PAGE 6 OF 8
.2
.3
Read the Drawings as a whole, as details applicable to one Section may appear on the
Drawings of another Section or Sections.
.4
.5
Contract Drawings give general location of piping routes and equipment. Except where
specific dimensions are indicated, locate equipment and piping to limit interference with
pedestrian access, crane routes, equipment operation, equipment maintenance and
required headroom.
.6
Refer to Structural and Architectural Drawings for dimensions and details which are not
indicated on Instrumentation, Mechanical or Electrical Drawings.
1.8
CONTRACT SPECIFICATIONS
.1
For easy reference, the contract specifications are divided into divisions. The
specifications shall be read as a whole as details applicable to one division may appear in
another division or divisions. The Contractor shall coordinate all work performed by
subcontractors.
.2
In the event of any conflicts within and/or between the specification sections, the more
stringent requirement(s) shall apply.
1.9
WORK COMPLIANCE
.1
Provide all work during its progress and at its completion to the lines, levels and grades
shown.
.2
Build all work in a thoroughly substantial and workmanlike manner, in accordance with
the Contract Drawings and Specifications, subject to such modifications and additions as
may be deemed necessary during its execution. In no case will any work in excess of the
requirements of the Drawings and Specifications be paid for, unless approved in writing
by the Engineer.
.3
The Contractor acknowledges that it is aware that the awarding of this Contract, and/or
release of the Commence Work Order, are subject to obtaining the following approvals.
Copies of these approvals and application information are provided to the Contractor as
Reference Documents:
.4
.1
.2
The Contractor shall not make any claims for additional costs or expenses due to delays
in the commencement of work (or portions thereof). The Contract Substantial
Performance and Completion dates will be adjusted to account for delays to release of
the Commence Work Order.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.10
SECTION 01010
SUMMARY OF WORK
PAGE 7 OF 8
ENGINEER DESIGN
.1
1.11
.1
Execute cutting, fitting, and patching including excavation and fill, to complete Work.
.2
.3
.4
.5
.6
Execute Work by methods to avoid damage to other Work, and which will provide
proper surfaces to receive patching and finishing.
.7
Employ original installer to perform cutting and patching for weather-exposed and
moisture-resistant elements, and sight-exposed surfaces.
.8
Cut rigid materials using masonry saw or core drill. Pneumatic or impact tools not
allowed on masonry work without prior approval.
.9
.10
Fit Work airtight to pipes, sleeves, ducts, conduit, and other penetrations through
surfaces.
.11
Refinish surfaces to match adjacent finishes: For continuous surfaces refinish to nearest
intersection; for an assembly, refinish entire unit.
.12
Conceal pipes, ducts and wiring in floor, wall and ceiling construction of finished areas
except where indicated otherwise.
.13
Coordinate with the City staff or the Owner of the facility in advance if the cutting or
alternation affects or may affect the operation of the existing facilities.
1.12
PAYMENT
.1
General
.1
1.13
SUBSTANTIAL PERFORMANCE
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01010
SUMMARY OF WORK
PAGE 8 OF 8
.1
.2
.3
Demonstration and Training of the Citys staff operating the facilities as specified
in Section 01820 Demonstration and Training.
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
SECTION 01015
CONTRACTOR'S USE OF PREMISES
PAGE 1 OF 9
.1
This Section specifies requirements for Contractor's use of project site during the
construction.
.2
This Section also specifies the easements being obtained by the City.
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
1.3
GENERAL
.1
The Contractors staging area for each of the project sites is defined on the Contract
Drawings.
.2
The Contractor shall confine its operations within the maximum working easements and
staging areas shown on the drawings for construction, storage and access. At no time will
the Contractor be permitted to operate outside of these defined maximum staging areas.
Electronic CADD files of the staging areas can be provided to the Contractor if
requested.
.3
The Contractor shall not enter NCC, PWGSC or MTO property at any time that is not
outlined in the Contract Documents.
.4
The Contractor is informed that the City is currently undertaking real estate easement
and property purchase negotiations for the properties shown in Attachment A and listed
in the Attachment A table with anticipated commencement dates and real estate type.
This information may be modified prior to and during construction and will be provided
to the Contractor when available.
.5
Refer to Section 01560 - Temporary Barriers and Enclosures for details on the fencing
required at each site.
.6
The Contractor shall not enter upon or occupy with workers, equipment, tools or
materials, any lands other than public streets, roadways, right-of-ways or easements
shown on the Contract Drawings except after written consent has been received from the
private property owner and the City.
.7
The Contractor shall maintain the site in good order and shall not unnecessarily
encumber the site with materials or equipment.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01015
CONTRACTOR'S USE OF PREMISES
PAGE 2 OF 9
.8
The construction of the Work shall be carried out in such a manner that minimizes any
inconvenience caused to the owners and occupants of properties adjacent to the Site.
.9
All materials shall be stored separately on the Site at locations agreed upon with the
Consultant and shall be suitably protected to prevent their deterioration or damage. Any
material which, in the opinion of the Consultant, has deteriorated or been damaged shall
be removed immediately from the Site at the Contractor's expense.
.10
The flow in existing drains and ditches shall be maintained by the Contractor at all times
at no extra cost to the City. During the construction of the facilities, the Contractor shall
coordinate with the Consultant to schedule the Work in order to ensure continual flow.
.11
The Contractor shall obtain the prior written approval of the Consultant for all tie-in or
shut down work to the existing facilities. The City's staff will operate any valve, switch,
or other control on existing facilities. The application for the tie-in or shutdown work
shall be submitted to the City for approval at least 10 working days in advance of the
Work. Refer to Section 01117 - Construction Sequences and Constraints for further
details related to tie-ins and shutdowns.
.12
The Contractor shall maintain access to the City for operating infrastructure in the work
areas at all times.
.13
1.4
STAGING AREA
.1
The staging area for the construction is shown on the contract drawing for each site.
.2
The Contractor shall base their bid price on the maximum staging areas indicated on the
Contract Drawings. At no time will the Contractor be allowed to stage works outside
these areas.
.3
Locate construction trailers, laydown areas, and temporary buildings under the direction
of the Contract Administrator.
.4
Develop a Staging Plan showing the staging area and any modifications to this area for
work on or near NCC/PWGSC land (Site 1, 3a, 3c, 5, 6) and within 30m of Parks Canada
land (Site 3a, 3b), along with equipment storage, fueling areas, and access/egress
locations. Coordinate with the Erosion and Sediment Control Plan (Section 01160).
Provide this plan to the Contract Administrator, NCC, PWGSC, and Parks Canada at
least 60 working days prior to start of work and modify based on comments. Ensure
plans comply with the Parks Canada Permit (Section 01060). Do not commence any
work at these sites until the plan has been approved by the NCC, Parks Canada and the
Contract Administrator.
1.5
WORK AREA
.1
Contractor shall clearly delineate the entire perimeter of his working area with fencing as
specified in Section - 01560 Temporary Barriers and Enclosures and as shown on the
contract drawings, with sufficient access gates, c/w signage identifying company name,
site contact telephone number, and emergency contact information prior to
commencement of any work.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01015
CONTRACTOR'S USE OF PREMISES
PAGE 3 OF 9
.2
All points of entry into the Contractor's working area shall be similarly controlled by
sturdy barriers and signage.
.3
.4
Install, secure and maintain fencing along working and storage areas, access routes and
both sides of easements.
1.6
STORAGE
.1
.2
Contractor shall obtain permission from the site Engineer before storing any materials in
any new building areas under construction.
.3
Excess materials resulting from any or all excavations are the property of the Owner. Its
disposal by the Contractor as part of his contract shall be as directed by the Owner unless
the Owner waives this requirement. Under this circumstance, the Contractor shall be
responsible for the disposal of any or all of the excess materials.
1.7
1.8
Contractor to maintain the grounds within his working limits and around any equipment
or storage areas. This includes removal of waste material, cutting of grass, and snow
removal.
CONTRACTOR PARKING
.1
The Contractor is made aware that the Owner will not provide designated parking for the
Contractors staff outside of the designated staging area. It is the Contractors
responsibility to obtain and pay for offsite parking and transportation of staff to the work
sites, should adequate space not be available within the staging area. Any parking tickets
issued to the Contractors employees shall be the responsibility of the Contractor.
.2
Only commercial vehicles subject to the requirements of PWGSC as outlined within the
Contract Documents are permitted to access Site 6. No personal vehicles are permitted to
access Site 6. Parking is not permitted for Contractor staff on NCC, PWGSC, Supreme
Court, Parliamentary Precinct or Government of Canada lands in the vicinity of Site 6
north of Wellington Street.
1.9
The Contractor shall take over the existing roadway protection and shoring system for
the Highway 417 installed as part of the 2015 Kent Street Bridge Replacement project at
Site 10, and shall assume full responsibility for this system for the duration of the works.
Details of the existing roadway protection and shoring system are indicated in the
Contract Drawings. Monitoring of vertical and horizontal displacement has been ongoing
since installation, which will be provided to the Contractor upon Contract Award.
Monitoring of the existing roadway protection and shoring system will be required on a
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01015
CONTRACTOR'S USE OF PREMISES
PAGE 4 OF 9
bi-weekly basis upon Contract Award and is required to be removed upon completion of
the works shall follow the requirements of Section 02150 Excavation Support System.
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
ATTACHMENTS
Attachment A: Real Property Schedule. Refer to Appendix 10 for Real Property Sketches.
END OF SECTION
Introduction
This Real Property Schedule describes real property interests which the City is in the process of acquiring for purposes of the CSST
Project. The boundaries and limits of the said real property interests, including commencement dates and durations of Temporary
Easements, are more particularly described in the tables below (the Property Tables) together with the Property Request Plans
referred to in the Property Tables.
Additional limitations on Real Property Interests included in this Real Property Schedule are denoted by a reference number included
in the Notes column of the Property Tables which reference number corresponds to the number listed in Section 3 Special
Limitations to this Real Property Schedule. The list of limitations described in Section 3 Special Limitations to this Real Property
Schedule is not exhaustive and is in addition to other constraints on the use of real property including but not limited to constraints
described in Contract No. ISD14-2036 and/or limitations arising from title encumbrances.
No
Project Sector
Parcel
Type of Interest
Construction Access
Date
Available Duration
(Months)
001
16478site01-02c
Parcel 1
01-Aug-18
n/a
002
16478site01b
Parcel 1
01-Aug-18
n/a
003
16478site03-01d
Parcel 1
1-Mar-18
n/a
004
Site 3a
16478site03-01d
Parcel 2
Permanent Easement
1-Mar-18
n/a
005
Site 3a
16478site03-01d
Parcel 3
1-Mar-18
15
006
Site 3a
16478site03-01d
Parcel 4
Permanent Easement
1-Mar-18
n/a
007
Site 3a
16478site03-01d
Parcel 5
Permanent Easement
1-Mar-18
n/a
008
16478site03-02d
Parcel 1
1-Mar-18
n/a
009
Site 3a
16478site03-02d
Parcel 2
Permanent Easement
1-Mar-18
n/a
010
Site 3a
16478site03-02d
Parcel 3
Permanent Easement
1-Mar-18
n/a
011
Site 3a
16478site03-02d
Parcel 4
1-Mar-18
15
012
Site 3a
16478site03-02d
Parcel 5
Permanent Easement
1-Mar-18
n/a
013
Site 3a
16478site03-02d
Parcel 6
Permanent Easement
1-Mar-18
n/a
Notes
Project Sector
Parcel
Type of Interest
Construction Access
Date
Available Duration
(Months)
014
16478site03-03
Parcel 1
1-Mar-18
n/a
015
Site 3a
16478site03-04d
Parcel 1
Permanent Easement
1-Mar-18
n/a
016
Site 3a
16478site03-04d
Parcel 2
1-Mar-18
20
017
Site 3a
16478site03-04d
Parcel 3
1-Mar-18
20
018
Site 3a
16478site03-04d
Parcel 4
Temporary Easement
1-Mar-18
20
019
16478site03c-01c-1&2
Parcel 1
31-July-17
n/a
020
16478site03c-01c-1&2
Parcel 2
31-July-17
24
021
16478site03c-01c-1&2
Parcel 3
31-July-17
n/a
022
16478site03c-01c-1&2
Parcel 4
Permanent Easement
31-July-17
n/a
023
Site 3c
16478site03c-01c1&2
Parcel 5
31-July-17
24
024
EWT Tunnel
16478site03c-02c
Parcel 1
01-May-17
n/a
025
EWT Tunnel
16478site05-01b
Parcel 1
01-May-17
n/a
026
EWT Tunnel
16478site05-01b
Parcel 2
01-May-17
n/a
027
EWT Tunnel
16478site05-02b
Parcel 1
01-May-17
n/a
028
EWT Tunnel
16478site05-03b
Parcel 1
01-May-17
n/a
029
Site 5
16478site05-04b
Parcel 1
01-May-17
30
030
Site 5
16478site05-04b
Parcel 2
01-May-17
n/a
031
Site 5
16478site05-04b
Parcel 3
01-May-17
30
032
Site 5
16478site05-04b
Parcel 4
01-May-17
n/a
033
Site 5
16478site05-04b
Parcel 5
Permanent Easement
01-May-17
n/a
034
Site 5
16478site05-06d
Parcel 1
01-May-17
30
035
Site 5
16478site05-06d
Parcel 2
01-May-17
n/a
036
Site 5
16478site05-06d
Parcel 3
Permanent Easement
01-May-17
n/a
037
Site 5
16478site05-06d
Parcel 4
01-May-17
30
038
Site 5
16478site05-07d
Parcel 1
01-May-17
n/a
039
Site 5
16478site05-07d
Parcel 2
01-May-17
n/a
040
Site 5
16478site05-07d
Parcel 3
01-May-17
30
041
Site 5
16478site05-07d
Parcel 4
01-May-17
30
Notes
Project Sector
Parcel
Type of Interest
Construction Access
Date
Available Duration
(Months)
042
Site 5
16478site05-07d
Parcel 5
01-May-17
30
043
Site 5
16478site05-07d
Parcel 6
Permanent Easement
01-May-17
n/a
044
Site 5
16478site05-07d
Parcel 7
01-May-17
30
045
Site 5
16478site05-07d
Parcel 8
01-May-17
30
046
Site 5
16478site05-09
Parcel 1
01-May-17
30
047
EWT Tunnel
16478site05w-01
Parcel 1
01-May-17
n/a
048
EWT Tunnel
16478site05w-02
Parcel 1
01-May-17
n/a
049
EWT Tunnel
16478site05w-03
Parcel 1
01-May-17
n/a
050
EWT Tunnel
16478site05w-04
Parcel 1
01-May-17
n/a
051
EWT Tunnel
16478site05w-05
Parcel 1
01-May-17
n/a
052
EWT Tunnel
16478site05w-06
Parcel 1
01-May-17
n/a
053
EWT Tunnel
16478site05w-07
Parcel 1
01-May-17
n/a
054
EWT Tunnel
16478site05w-08
Parcel 1
01-May-17
n/a
055
EWT Tunnel
16478site05w-09
Parcel 1
01-May-17
n/a
056
EWT Tunnel
16478site05w-10
Parcel 1
01-May-17
n/a
057
EWT Tunnel
16478site05w-11
Parcel 1
01-May-17
n/a
058
EWT Tunnel
16478site05w-12
Parcel 1
01-May-17
n/a
059
EWT Tunnel
16478site05w-13
Parcel 1
01-May-17
n/a
060
EWT Tunnel
16478site05w-14
Parcel 1
01-May-17
n/a
061
EWT Tunnel
16478site05w-15
Parcel 1
01-May-17
n/a
062
EWT Tunnel
16478site05w-16
Parcel 1
01-May-17
n/a
063
EWT Tunnel
16478site05w-17
Parcel 1
01-May-17
n/a
064
EWT Tunnel
16478site05w-18
Parcel 1
01-May-17
n/a
065
Site 6
16478site06-01b
Parcel 1
Permanent Easement
01-May-16
n/a
066
Site 6
16478site06-01b
Parcel 2
01-April-17
14
067
Site 6
16478site06-01b
Parcel 3
01-April-17
14
068
Site 6
16478site06-01b
Parcel 4
01-April-17
14
069
16478site06-02b
Parcel 1
01-May-16
n/a
Notes
2.
No
Project Sector
Parcel
Type of Interest
Construction Access
Date
Available Duration
(Months)
070
16478site06-02b
Parcel 2
01-April-17
14
071
16478site06-02b
Parcel 3
01-April-17
14
072
16478site06-02b
Parcel 4
01-April-17
14
073
16478site06-02b
Parcel 5
Permanent Easement
01-April-17
n/a
074
16478site06-02b
Parcel 6
Permanent Easement
01-April-17
n/a
075
16478site09-04c
Parcel 1
01-May-16
31
076
16478site09-04c
Parcel 2
Permanent Easement
01-May-16
n/a
077
16478site09-04c
Parcel 3
01-May-16
31
078
16478site09-04c
Parcel 4
01-May-16
n/a
079
16478site09-04c
Parcel 5
Fee Simple
01-May-16
n/a
080
16478site09-04c
Parcel 6
Fee Simple
01-May-16
n/a
081
16478site09-04c
Parcel 7
Fee Simple
01-May-16
n/a
082
16478site09-04c
Parcel 8
01-May-16
31
083
16478site09-04c
Parcel 9
Permanent Easement
01-May-16
n/a
084
16478site09-04c
Parcel 10
01-May-16
31
085
Site 9 OCF
16478site09-05c
Parcel 1
Fee Simple
01-May-16
n/a
086
Site 9 OCF
16478site09-05c
Parcel 2
01-May-16
31
087
NST Tunnel
16478site09-06c
Parcel 1
01-May-16
n/a
088
NST Tunnel
16478site09-07b
Parcel 1
01-May-16
20
089
NST Staging
16478site10-03
Parcel 1
01-May-16
32
Definitions
In the above table, the following definitions apply in respect of the terms used in the Type of Interest column:
Fee Simple means all rights of ownership of real property.
Notes
Permanent Easement means the rights to use real property for a specific purpose, including for purposes of constructing
and maintaining a utility. The underlying interest in the real property remains with the original owner and the use of real
property pursuant to the easement is subject to certain conditions.
Stratified means the property rights are to specify vertical limits as shown on the applicable Property Request Plan. For
example, a permanent easement, a fee simple interest or a temporary interest may be Stratified, in which case such property
interest only commences below certain vertical limits as shown on the relevant Property Request Plan.
Temporary Easement means the rights to use real property for a specific purpose, such as construction staging and/or
construction. Temporary Easements will have a limited duration and may, but will not necessarily, provide exclusive access to
the relevant real property. Prior to expiry of the term of a Temporary Easement, the real property must be reinstated and, on
expiry, possession of real property is returned to original owner.
3.
Special Limitations
The following notes correspond to the numbers shown in the Notes column of the Property Tables:
[NOTE TO TENDERERS This Attachment A, including the real property constraints described in this Section 3 and
referenced in the Notes column of the Property Table, will be the subject of a future Addendum].
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.
GENERAL
1.1
Related Sections
.1
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 1 of 25
1.2
.1
Submit with initially accepted Detailed Pricing Breakdown as per CCDC 4, GC 5.2.5.
.2
.2
.3
1.3
.1
1.4
.1
Provisional Items
1.5
.1
Purpose of the provisional items in Form of Tender is to cover the cost of specific
extra work items that are addressed by the Specifications, provided that implementation of
such work is approved by t h e City. The provisional items include unit price items and
allowances. Some, none, or all of each provisional unit price item and allowance may be
used at sole discretion of the City. The Contractor shall have no claim on any unused
portion of the provisional items or allowances.
.2
Payment for the provisional items shall be based on the actual quantities and the unit prices
entered for provisional quantities shall be applicable to extras or deductions even if actual
quantities are found to vary considerably from them.
Schedule of Estimated Progress Payments
1.6
.1
Show estimated payment requests throughout the Contract beginning within 30 calendar
days of the commencement of the Work and monthly thereafter.
.2
Base estimated progress payments on initially accepted progress schedule and cash flow,
substantiated by a fully itemized statement showing the estimated value of the permanent
work executed through the end of the monthly payment period. Adjust to reflect
subsequent adjustments in the progress schedule and Contract Price as reflected by any
modifications to the Contract Documents.
.3
No progress payment will be made until such time that the Estimated Progress Payment
Schedule (Cash Flow) has been submitted and reviewed by the Contract Administrator.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 2 of 25
1.7
.1
Transmittal Summary Form: Attach one Summary Form with each detailed Payment
Certificate and include a Request for Payment of Materials and Equipment on Hand as
applicable. Applications for Payment and all related documentation shall be executed by
an authorized officer of the Contractor.
.2
.3
Payment for bonds and insurance shall be included in the first monthly Payment
Certificate after the City has received the required bonds and proof of insurance in a form
satisfactory to the City and confirming that the Citys bonding and insurance requirements
have been met.
.4
Preparation:
.5
.1
.2
List each Change Order and Written Amendment executed prior to date of
submission as separate line item. Totals are to equal those shown on the
Payment Certificate for each major item of the Work as applicable.
.3
Payment Certificate must show, for each item of the schedule of values, as defined in
GC5.2.5, of the Contract Price and of each Division 1 to 16 inclusive with the following:
.1
.2
.3
.4
.5
.6
Submit Payment Certificate to Contract Administrator before last day of each payment period.
.7
To assist the Contractor with preparation of the Payment Certificate, the Contract
Administrator will meet with the Contractor at the site office on an agreed date during
each payment period, on or prior to last day of payment period, to review the progress of the
Work.
.8
The Contractor and the Contract Administrator shall agree on the quantity of the work
performed and due for payment. Once the quantity has been agreed upon, the Contractor shall
submit the Payment Certificate to the City. The certificate shall be signed and dated by the
Contractors representative.
.9
Starting from the second Application for Payment and onwards, a current copy
of a valid Workplace Safety and Insurance Board (WSIB) Certificate of
Clearance and an executed Statutory Declaration certifying that payment has
been made in full to all sub Vendors, suppliers, workmen, and others for labour,
materials, and services required by the Contract through, and including, the
latest progress payment.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 3 of 25
.2
Include copies of all bills of lading for equipment, material, and other items
delivered to site for which payment is requested with each Application for
Payment.
.3
.4
The City shall not release monies for Payment Certificates until the Contractor has
provided all of the supporting documentation, as specified herein.
MeasurementGeneral
1.8
.1
Measurement will be made for lump sum items in the Form of Tender for interim
payments that will be used to substantiate the percentage of the Work completed as agreed
to by the Contract Administrator.
.2
Measurement may also be made for items used in the provisional items in the Form of
Tender for interim payments that will be used to substantiate the percentage of the Work
completed as agreed to by the Contract Administrator.
.3
Weighing, measuring, and metering devices used to measure the quantities of materials
for the Work shall be suitable for the purpose intended and conform to the tolerances and
specifications as specified in Government of Canada Weights and Measures Act and
Regulations.
.4
Whenever pay quantities of material are determined by weight, the material shall be weighed
on scales furnished by the Contractor and certified accurate by the federal or provincial
agency responsible. A weight or load slip shall be obtained from the weigher and delivered
to the Citys representative at the point of delivery of the material. When the established
weight includes the weight of a vehicle or container, vehicle or container weight shall be
established as stated herein and used to determine the net weight of material on which
payment will be made.
.5
If the material is shipped by rail, car weights will be accepted provided that the actual
weight of the material only will be paid for and not the minimum car weight used for
assessing freight tariff, and provided further that the car weights will not be acceptable for
material that is to be passed through mixing plants.
.6
Vehicles used to haul material being paid for by weight shall be weighed empty daily and
at such additional times as required by the Contract Administrator. Each vehicle shall
bear a plainly legible identification mark.
.7
Materials that are specified for measurement by the cubic metre measured in the vehicle
shall be hauled in vehicles of such type and size that the actual contents may be readily
and accurately determined. Unless all vehicles are of uniform capacity, each vehicle
must bear a plainly legible identification mark indicating its water level capacity.
Vehicles shall be loaded to at least their water level capacity. Loads hauled in vehicles
not meeting the above requirements or loads of a quantity less than the capacity of the
vehicle, measured after being leveled off as above provided, will be subject to rejection,
and no compensation will be allowed for such material.
.8
Where measurement of quantities depends on the elevation of the existing ground, the
elevations obtained during construction will be compared with those shown on the
Contract Drawings. Variations of 300 mm or less will be ignored, and the profiles shown
on the Contract Drawings will be used for determining quantities.
.9
Units of measure shown on the Form of Tender and methods of measurement shall be
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 4 of 25
METHOD OF MEASUREMENT
EachField count by Contract Administrator
HourField measure by Contract Administrator
HectareField measure by Contract Administrator
KilogramWeight measure by scale
LitreField measure by Contract Administrator
Lump SumUnit is one; no measurement will be made
Linear MetreField measure by Contract Administrator
Square MetreField measure by Contract Administrator
Cubic MetreField measure by Contract Administrator within limits
specified or shown
m3-VM
Payment
1.9
.1
.2
General:
.1
.2
The date for the Contractors submission of the monthly Application for
Payment shall be established at the project preconstruction meeting.
Payment for all the Work shown or specified in Contract Documents is included in the
Contract Price.
Non-Payment for Rejected or Unused Products
1.10
.1
.2
.3
Rejected loads of material, including material rejected after it has been placed,
by reason of the failure of the Contractor to conform to provisions of the
Contract Documents.
.4
.5
.6
1.11
.1
Partial Payment: No partial payments will be made for materials and equipment delivered to
the Site but not yet incorporated into the permanent work, with the exception of items that
apply to Section 1.12 and 1.13 below.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 5 of 25
Final Payment: Will be made only for products incorporated in the Work. The remaining
products, for which partial payments have been made, shall remain the property of the
Contractor unless otherwise agreed by the City, and partial payments made for those items
will be deducted from final payment.
Partial Payment for Undelivered, Project-Specific Manufactured or Fabricated Equipment
1.12
.1
.2
Notwithstanding the above provisions, partial payments for undelivered (not yet delivered to
site or not stored in the vicinity of site) products specifically manufactured for the Project,
excluding off-the-shelf or catalog items, will be made for products listed below when all of
the following conditions exist:
.1
.2
.3
Each equipment item is clearly marked and segregated from other items to
permit inventory and accountability.
.4
Authorization has been provided for access to the storage site for the Contract
Administrator and City.
.5
Applicable Items:
.1
.3
The following items may be applicable for partial payment. Validity for other
items may be requested by the Contractor at the discretion of the Contract
Administrator.
.1
.2
Mechanical equipment
.3
Electrical equipment
.4
Instrumentation
Failure of the Contractor to continue in compliance with above requirements shall give
cause for the City to withhold payments to be made for such equipment from future partial
payments.
Advance Payments for Material
1.13
.1
The Owner may make advance payments for Material, except for aggregates, intended for
incorporation in the Work upon the written request of the Contractor and according to the
following terms and conditions:
.1
.2
Payment for all other materials, unless otherwise specified elsewhere in the
Contract, shall be based on the invoice price, and the Contractor shall submit
proof of payment (i.e. Invoice Receipt etc.) to the Contract Administrator before
payment can be made by the Owner.
.3
The payment for all Materials shall be prorated against the appropriate tender
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 6 of 25
item by paying for sufficient units of the item to cover the value of the material.
Such payment shall not exceed 80% of the Contract price for the item.
.4
No partial payments will be made for materials and equipment delivered or stored
unless shop drawings and preliminary operation and maintenance manuals are
acceptable to the Contract Administrator.
.1
1.14
.1
No extra payment will be made to the Contractor should frozen ground be encountered to
any depth.
.2
Frozen ground shall not be opened further in advance of construction for more than one
days installation. Frozen native material shall not be placed into any trench as backfill, but
shall be removed from the site and replaced with approved unfrozen or granular material.
2.
3.
EXECUTION
3.1
Contract Items
.1
Payment for each item will be made at the unit or lump sum price indicated in the Schedule
of Prices in the Form of Tender for the provision of all necessary materials, equipment,
tools, incidentals, labour and supervision to complete the Work as specified in the Contract
Documents, including all Specifications, and as shown on the Contract Drawings.
.2
In the case of any work item and any requirements set out in the General Conditions,
Supplementary Conditions, Specifications, or on the Contract Drawings for which a
separate payment item is not provided in the Schedule of Prices to pay specifically for that
work item, that item or requirement shall be treated as incidental, and all costs associated
with that item shall be apportioned to or included as part of an applicable unit or lump
sum payment item in the Schedule of Prices. The Contractor shall review the Contract
Documents in full and satisfy itself fully of all the requirements of the Contract prior to the
Contractor Submission.
.3
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 7 of 25
.3
.2
.2
.3
The bid price for this item will be limited to a maximum of 2% of the
total contract price. The price for general mobilization shall not exceed
70% of the total price entered for this item, and the price for general
demobilization shall not exceed 30% of the total price entered for this
item.
.4
.5
Payment for Mobilization - TBM will be made at the lump sum price
as stated in the Schedule of Prices. Only one lump sum amount will be
paid, regardless of the number of TBMs the Contractor utilizes to
complete the Work. The lump sum price shall constitute full
compensation for all labour, material, equipment and incidentals
including, but not limited to:
.1
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 8 of 25
.3
.4
The bid price for this item shall be limited to a maximum of 10% of the
Part B works associated with tunneling. A maximum of 75% of the cost
entered against this item will be for mobilization. Of the price for
mobilization, 30% will be paid on the first contract payment and the
remainder shall be paid in equal payments thereafter over the first year
commencing when the TBM is proven to be fully functional and has
completed a minimum of 100m of NST or EWT tunnel. The remaining
25% of the total contract price for this item will be for demobilization.
Payment for Contaminated Soil Disposal Offsite will be made at the unit
price per tonne as stated in the Schedule of Prices. The unit price per
tonne shall constitute full compensation for all labour, material,
equipment and incidentals including, but not limited to:
.1
.2
.3
.5
.6
Payment for Street Sweeping will be made at the unit price per
truck hour as stated in the Schedule of Prices. The unit price shall
constitute full compensation for all labour, supervision, material,
equipment and incidentals for street sweeping trucks performing
sweeping in accordance with the requirements of Section 01740 Cleaning. Measurement will be made to the nearest quarter-hour.
Payment for Flushing will be made at the unit price per truck
hour as stated in the Schedule of Prices. The unit price shall
constitute full compensation for all labour, supervision, material,
equipment and incidentals for flushing trucks performing
flushing in accordance with the requirements of Section 01740 Cleaning. Measurement will be made to the nearest quarter-hour.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.1
.7
.4
Payment for Hydro Excavating will be made at the unit price per
truck hour as stated in the Schedule of Prices. The unit price shall
constitute full compensation for all labour, material, equipment
and incidentals for hydro excavating and supervision as
requested by the Contract Administrator. Measurement will be
made to the nearest quarter-hour.
.8
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 9 of 25
Tunneling and Precast Lining Installation Item B1.1: EWT East (Site
5a to Site 3c), Item B1.2: EWT West (Site 3c to Site 1) and Item B1.3:
NST (Site 10 to Site 6)
.1
.2
.3
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 10 of 25
.3
.4
.5
.6
.7
.8
.2
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
.2
.3
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 11 of 25
Clean up of the finished pipeline.
.2
.2
.3
.4
.5
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 12 of 25
.2
.3
.4
.5
.6
.7
.8
.9
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.4
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 13 of 25
.5
.6
.7
.8
.9
Item B3.4: Site 4 EWT Access Chamber and Shaft with Tunnel
Connection
.10
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 14 of 25
.11
.12
.13
.14
.2
.15
.16
.17
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 15 of 25
.2
.3
.2
.3
.19
.20
.21
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 16 of 25
.22
.23
.24
.25
.26
.27
.28
.29
.30
.31
.32
.33
.34
.35
.36
.37
.38
.39
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 17 of 25
abandonment/removal
.40
.1
.41
.1
.5
Items under C1.1, C2.1, C3.1, C5.1, C6.1, C7.1, C8.1, C9.1, C10.1, C11.1, and
C12.1: Division 1 General Requirements
.1
.2
.3
Items under C1.2, C2.2, C3.2, C5.2, C6.2, C7.2, C8.2, C9.2, C10.2 C11.2, C12.2:
Division 2 Site Works
.1
Payment for all items listed under Division 2 Site Works will be made
per unit, or lump sum, as stated in the Schedule of Prices for each site or
identified structure location.
.2
These items do not include site works specific to the Tunneling and
associated works or otherwise specified in Parts A and B, above.
.3
The payment quantity for items listed per linear metre shall be the
actual number of linear metres, as measured by the Contract
Administrator. Measurement will be made to the nearest 0.1 metre.
.2
The payment quantity for items listed per square metre shall be the
actual number of square metres, as measured by the Contract
Administrator. Measurement will be made to the nearest 0.1
square metre.
.3
The payment quantity for items listed per cubic metre shall be the
actual number of cubic metres, as measured by the Contract
Administrator. Measurement will be made to the nearest 0.1 cubic
metre.
.4
The payment quantity for items listed per tonne shall be the actual
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 18 of 25
.4
.5
The payment quantity for items listed per unit each shall be the
number of units counted by the Contract Administrator and
specified in the Contract Documents, unless otherwise agreed
upon by the Contract Administrator.
.6
The payment quantity for items listed as Lump Sum shall be one,
as per the price listed in the Schedule of Prices. Only one lump
sum amount will be paid, regardless of the extent of the work
completed.
For all items, the unit price or lump sum price per site or location shall
constitute full compensation for all labour, material, equipment and
incidentals necessary to complete the work as described in specification
sections under Division 2, excluding tunneling and associated works
outlined in Part A and B, for the completion of the odour control facilities
and surface works, including but not limited to the following:
.1
.2
.3
.4
.4
.5
.6
.7
all other works required for the construction of the odour control
facilities and other miscellaneous surface works at each site
included in specification sections under Division 2.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
Items under C1.3, C2.3, C3.3, C5.3, C6.3, C7.3, C8.3, C9.3, C10.3, C11.3, and
C12.3: Division 3- Concrete
.1
Payment for all items listed as Division 3: Concrete will be made at the
lump sum price as stated in the Schedule of Prices for each site or
identified structure location.
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
.1
.5
Items under C1.4, C2.4, C3.4, C5.4, C6.4, C7.4, C8.4, C9.4, C10.4, C11.4, and
C12.4: Division 4- Masonry
.1
Payment for all items listed as Division 4: Masonry will be made at the
lump sum price as stated in the Schedule of Prices for each site or
identified structure location.
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
.1
.6
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 19 of 25
Items under C1.5, C2.5, C3.5, C5.5, C6.5, C7.5, C8.5, C9.5, C10.5, C11.5, and
C12.5: Division 5- Metals
.1
Payment for all items listed as Division 5: Metals will be made at the lump
sum price as stated in the Schedule of Prices for each site or identified
structure location.
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.1
.7
.1
Payment for all items listed as Division 6: Woods and Plastics will be
made at the lump sum price as stated in the Schedule of Prices for each site
or identified structure location.
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
supply and installation of all wood and plastics including framing,
sheathing and carpentry work required for the construction of the
odour control facilities, air vent chambers, control buildings and
other surface works as indicated on the Contract Drawings. Refer
to Division 6 specification sections for details;
Items under C1.7, C2.7, C3.7, C5.7, C6.7, C7.7, C8.7, C9.7, C10.7, C11.7, and
C12.7: Division 7- Thermal and Moisture Protection
.1
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
.1
.9
Items under C1.6, C2.6, C3.6, C5.6, C6.6, C7.6, C8.6, C9.6, C10.6, C11.6, and
C12.6: Division 6- Woods and Plastics
.1
.8
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 20 of 25
Items under C1.8, C2.8, C3.8, C5.8, C6.8, C7.8, C8.8, C9.8, C10.8, C11.8, and
C12.8: Division 8- Windows and Doors
.1
Payment for all items listed as Division 8: Windows and Doors will be
made at the lump sum price as stated in the Schedule of Prices for each site
or identified structure location.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 21 of 25
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
.1
.10
Items under C1.9, C2.9, C3.9, C5.9, C6.9, C7.9, C8.9, C9.9, C10.9, C11.9, and
C12.9: Division 9- Finishes
.1
Payment for all items listed as Division 9: Finishes will be made at the
lump sum price as stated in the Schedule of Prices for each site or
identified structure location.
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
.1
.11
Items under C1.10, C2.10, C3.10, C5.10, C6.10, C7.10, C8.10, C9.10, C10.10,
C11.10, and C12.10: Division 10- Furnishings
.1
Payment for all items listed as Division 10: Furnishings will be made at the
lump sum price as stated in the Schedule of Prices for each site or
identified structure location.
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
.1
.12
Items under C1.11, C2.11, C3.11, C5.11, C6.11, C7.11, C8.11, C9.11, C10.11,
C11.11, and C12.11: Division 11 - Equipment
.1
Payment for all items listed as Division 11: Equipment will be made at the
lump sum price as stated in the Schedule of Prices for each site or
identified structure location.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
.1
.13
.1
Payment for all items listed as Division 13: Special Construction will be
made at the lump sum price as stated in the Schedule of Prices for each site
or identified structure location.
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
supply and installation of all instrumentation, communications and
odour control equipment, including carbon filters, grease/mist
eliminators, control panels, junction boxes, computing units, and
security systems as indicated on the Contract Drawings. Refer to
Division 13 specification sections for details;
Items under C1.13, C2.13, C3.13, C5.13, C6.13, C7.13, C8.13, C9.13, C10.13,
C11.13, and C12.13: Division 14 - Conveying Equipment
.1
Payment for all items listed as Division 14: Conveying Equipment will be
made at the lump sum price as stated in the Schedule of Prices for each site
or identified structure location.
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
.1
.15
supply and installation of all slide gates, flap gates, process valves,
stoplogs, motors/actuators and other process equipment as
indicated on the Contract Drawings. Refer to Division 11
specification sections for details;
Items under C1.12, C2.12, C3.12, C5.12, C6.12, C7.12, C8.12, C9.12, C10.12,
C11.12, and C12.12: Division 13 Special Construction
.1
.14
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 22 of 25
Items under C1.14, C2.14, C3.14, C5.14, C6.14, C7.14, C8.14, C9.14, C10.14,
C11.14, and C12.14: Division 15 - Mechanical
.1
Payment for all items listed as Division 15: Mechanical will be made at the
lump sum price as stated in the Schedule of Prices for each site or
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 23 of 25
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
.1
.16
Items under C1.15, C2.15, C3.15, C5.15, C6.15, C7.15, C8.15, C9.15, C10.15,
C11.15, and C12.15: Division 16 - Electrical
.1
Payment for all items listed as Division 16 - Electrical will be made at the
lump sum price as stated in the Schedule of Prices for each site or
identified structure location.
.2
.3
The lump sum price per site or location shall constitute full compensation
for all labour, material, equipment and incidentals necessary for the
completion of the odour control facilities and surface works, including but
not limited to the following:
.1
.6
.7
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 24 of 25
.3
.2
.2
Measurement will be made to the nearest 0.005 cubic meter for each flow
meter, and the readings for each meter will be aggregated for payment
purposes.
Payment for Disposal of Contaminated Water Offsite will be made at the
unit price per cubic metre of treated water as stated in the Schedule of
Prices. Refer to Section 02140 Groundwater Control and Section
01355 Waste Management and Disposal for details. The unit price
shall constitute full compensation for all labour, material, equipment
and incidentals for storage and disposal of contaminated water offsite.
As per Section 02901 Tree and Shrub Protection.
As per Section 02315 Excavation, Trenching and Backfill.
Item E6: Replacement of Unsuitable Native Backfill Material with SSM Type III
.1
.8
.7
.4
.6
.5
.3
.4
.4
.2
Item E7: Remove and Replace Asphalt for Temporary Reinstatement (40mm HL3,
40mm HL8)
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.9
.10
.21
.20
.19
.18
.17
.16
.15
.14
.13
.12
.11
SECTION 01025
MEASUREMENT AND PAYMENT
PAGE 25 of 25
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01050
COORDINATION
PAGE 1 OF 6
.1
.2
.3
.4
1.3
REFERENCE
.1
.2
1.4
.2
.3
.4
.5
.6
1.5
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01050
COORDINATION
PAGE 2 OF 6
needed. Cut and make good, or excavate and backfill, as required and in a timely manner
so that the work proceeds expeditiously.
.3
.4
The various divisions of these specifications have not necessarily been segregated into
sub-trades or sub-contracts. It shall be the responsibility of the Contractor to define the
scope of work required of each sub-trade or subcontract.
.5
1.6
Other contracts may be awarded to construct adjacent work to which this contract work
connects.
.2
At the interface with other contracts, jointly plan and coordinate with other contractors
the work so that the project:
.1
.2
.3
.4
Will not cause the City to be designated as the Constructor as set out in the
Occupational Health and Safety Act.
.3
.4
Where other work is in progress within or adjacent to the limits of this Contract, cooperate and co-ordinate with other Contractor(s), Utility Companies, and the City of
Ottawa and allow reasonable, free access to their work at all times.
.1
Note that OLRT operations including tunnel and station construction and testing
operations along with bus rerouting is expected to take place during much of this
Contract duration near some of the project sites. The Contractor shall coordinate
with OLRT Constructors to ensure OLRT operations are not impacted by Contract
works.
.5
Co-operate and make suitable working arrangements with other Contractor(s) (i.e. third
party Contractors).
.6
Notify the Engineer and the City in advance and obtain approval in writing from the
Engineer and the City for all arrangements made with other Contractor(s) (i.e. third party
Contractors).
.7
Engineer shall determine co-ordination and execution of work in event that Contractor(s)
(i.e. third party Contractors and the Contractor) are unable to reach satisfactory working
agreements.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
1.7
SECTION 01050
COORDINATION
PAGE 3 OF 6
The Contractor is made aware of the following proposed works by others within the
vicinity of the Contract limits. The following list is not exhaustive and may be subject to
change, including dates and extents:
.1
Road Resurfacing Waller St (southbound lanes and ramps) from 60m north of
Stewart St to Nicholas St southbound, 2015
.2
Road, Sewer and Water Works Nicholas St from Laurier Ave to Main St, 2015
.3
.4
Transit Priority Works Bus turn around, King Edward Ave at Union St, 2015
.5
Cycling Route Works Laurier Ave E from Nicholas St to Waller St, 2018
.6
.7
.8
.9
Road Resurfacing Chamberlain Ave from Kent St to 60m West of Bank St, 2015,
2016
.10
.11
Rideau Street Reconstruction - between Dalhousie and Sussex Drive, 2016, 2017.
.12
Reconstruction of Rideau Street between Dalhousie and Sussex Drive (2016 and
2017).
Coordinate start up and commissioning activities with the Citys staff responsible for
PLC and HMI programming for Contractor provided systems in a timely manner so that
the Work proceeds expeditiously.
.2
Deliver any purchased components of the SCADA system to the City for any required
programming in a manner such that the overall schedule is not adversely affected.
1.8
Coordinate the Work with various utilities (power, gas, telephone, water, cable etc.)
within Project limits. The Contractor shall notify applicable utilities prior to
commencing the Work and make necessary accommodations if the utility requires an
inspector during the work. The Contractor shall also notify the applicable utilities if any
damage occurs, or if conflicts or emergencies arise during the execution of the Work.
.2
Coordinate the utility companies for the tie-in, shutdown, disconnection and relocation
of the existing services prior to commencing the work. Provide the utilities at least 15
working days advance notification before commencing work that affects utilities. If
utility modifications require a utility design generated by the utility, provide an
additional 15 working day period to generate the design. Allow additional time as
required by the utility at no additional cost to the Contract.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01050
COORDINATION
PAGE 4 OF 6
.3
Provide assistance to the utilities as requested to allow for utility relocations where
required.
.4
Coordinate with all utilities to ensure their availability on Site to suit the Contractor's
schedule. The Contractor shall adjust its schedule, at no additional cost to the Contract,
to suit the availability of the utility companies.
.5
Should any piping, sewers, ductbanks, cables or similar services be encountered during
performance of the Work that are not known from the City or other utility companies
records, the Contractor shall notify the Engineer and the appropriate utility agency and
shall not proceed with their removal or cutting until direction has been provided.
.6
1.9
.1
NCC utilities
.2
Enbridge
.3
Rogers
.4
Bell
.5
Hydro Ottawa
.6
Hydro One
.7
.8
.9
PWGSC utilities
The Contractor shall perform all new street lighting works as per F-6011, removals as
per F-6101, underpass lighting as per F-6111, pole erection as per F-6151, roadway
luminaires as per F-6171, and high mast pole construction as per F-6301.
.2
The Contractor shall coordinate with City of Ottawa Street Lighting to obtain design
works, construction support, and approval for all street lighting related works.
.3
Street lighting works for removal and installation is to be paid under the relevant unit
price item in Division 2.
1.10
The Contractor shall ensure cooperation and coordination with the National Capital
Commission (NCC) at Site 3a, 3b, 3c, 5 and shall follow the requirements of the Noise
and Vibration Monitoring Plan and communication process in Section 02482 Noise
and Vibration Monitoring. Works at Site 6 shall follow the requirements of Section
01117 Construction Sequences and Constraints.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.11
SECTION 01050
COORDINATION
PAGE 5 OF 6
.2
.3
1.12
1.13
The Contractor shall ensure cooperation and coordination with the Ministry of
Transportation (MTO) at Site 9 and 10.
EXISTING ROADS
.1
Provide all signage necessary to properly direct construction traffic to the Contractors
site trailer and worker parking area at each site, where worker parking at the site is
permitted. All signage shall be to the satisfaction of the Engineer. Refer to Section 01353
- Special Procedures: Traffic Control for additional signage requirements.
.2
Existing roads on the site may not be used for construction purposes except as shown on
the contract drawings and unless agreed to by the Owner. Repair all road damage and
reinstate to existing or better condition after the completion of construction work. All
reinstatement shall be in accordance with requirements of Section 02980 - Restoration.
1.14
EXISTING DIMENSIONS
.1
1.15
Dimensions shown are based on existing drawings and are approximate. Verify field
dimensions and details before commencing work. Report discrepancies to the Engineer.
FEES AND CHARGES
.1
1.16
Pay fees and charges imposed for disposal of waste materials, engineering fees for
substitutions, permit fees and similar items to complete the work.
CEILING AND WALL OPENINGS
.1
1.17
Locate wall and ceiling openings to suit the pattern of concrete, masonry and ceiling tile
work. Make necessary adjustments in systems to allow openings to coincide with wall
and ceiling patterns.
STANDARD AND CUSTOM COLOURS
.1
Colour to be selected by Owner; the Engineer can select standard or custom colours
without increase to the contract price.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
SECTION 01050
COORDINATION
PAGE 6 OF 6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01060
REGULATORY REQUIREMENTS
PAGE 1 OF 12
.1
.2
.3
.4
1.3
SUBMITTALS
.1
Quality Control Submittals: Submit certificates from inspecting authorities for electrical
work and pressure piping etc.
.2
.3
Submit the information required under Part 1 of Ontario Regulation 213 to the Ministry
of Labour prior to commencing work.
1.4
APPLICABLE CODES
.1
Comply with the latest edition of the following statutes, regulations, and codes and all
amendments thereto:
.1
.2
.3
Occupational Health and Safety Act and Regulations for Construction Projects,
covering safety, hazardous materials, and Workplace Hazardous Material
Information.
.4
.5
.6
.7
.8
Ontario Regulation made pursuant to the Power Corporation Act regarding the
Electrical Safety Code.
.9
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
1.5
SECTION 01060
REGULATORY REQUIREMENTS
PAGE 2 OF 12
.10
.11
.12
.13
.14
.15
.16
.17
AODA Regulations
.18
The Contractor shall conform to and enforce strict compliance with the Occupational
Health and Safety Act (OHSA). For purposes of the Occupational Health and Safety Act,
the Contractor will be designated the Constructor and assumes the responsibility of the
Constructor as set out in the Act and its regulations.
PERMITS, APPROVALS, AND LICENCES
.1
Apply for, obtain, and pay for all permits, approvals, and licenses required for the
project, including but not limited to:
.1
Plumbing permit
.2
.3
.4
Operating engineers
.5
.6
.7
Electrical supply and inspection authorities including Hydro Ottawa and the
Ontario Electrical Safety Authority (ESA). Contractor shall submit and pay for
ESA Plans Approval review and associated electrical permits for all electrical
installations.
.8
Rideau Valley Conservation Authority (RVCA) permit O.Reg 174/06 for works in
floodplain/near shoreline. This permit is attached; the Contractor shall review and
comply with all terms in this permit throughout construction when working
adjacent to the Rideau River and Ottawa River
.9
.10
Sanitary and Storm Sewer Use Bylaws from the City of Ottawa, including all
associated testing of groundwater required to obtain a Sewer Use Discharge
Agreement. The NCC and PWGSC is to be sent a copy of this permit at least 10
working days prior to commencement of work for work on NCC and PWGSC
property.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01060
REGULATORY REQUIREMENTS
PAGE 3 OF 12
.11
Permit to Perform Work in the Waters and along the Shorelines of the Rideau
River. The Contractor is made aware that work is allowed within the waters of the
Rideau River, however the Contractor must secure this permit as some work
extends beneath the canal and along the shoreline. The NCC is to be sent a copy of
this permit at least 10 working days prior to commencement of work.
.12
.13
Other permits required for the work from governing federal, provincial and
municipal authorities having the jurisdictions, including Parks Canada for works
within 30m of the Rideau Canal, PWGSC, and NCC. A copy of the Parks Canada
permit is to be provided to the NCC at least 10 working days prior to
commencement of work.
.14
.15
.16
.17
Authorization for Building Access for any employees requiring access to PWGSC
facilities (requires Secret clearance as specified in 01117 Construction
Sequences and Constraints).
.2
The Contractor shall notify the Ministry of Labour of the commencement of the
construction by mailing a Notice of Project, in accordance with the latest version of
the Occupational Health and Safety Act and Regulations.
.3
.4
The Owner will be responsible for obtaining a Permit for Building Construction for
Odour Control Facilities. Building permit required for this project will be provided by
the City at no cost to the Contractor.
.5
Draft Permit to Take Water (PTTW) will be applied for by the City of Ottawa,
Contractor to request transfer to their name. Refer to the City of Ottawa General
Special Provision No. D-030 (attached) and Section 02140 Groundwater Control
for details.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01060
REGULATORY REQUIREMENTS
PAGE 4 OF 12
.6
Where electrical enclosures and panels do not have CSA labels, arrange and pay for each
such electrical enclosure or panel to be inspected by the provincial electrical safety
inspector.
.7
.2
.3
.4
.8
Arrange for all other regular inspections and final inspections required.
.9
The Contractor shall be solely responsible, without limitations, for any delays arising
from the Contractor's failure to plan for the required inspections and to ascertain the
availability of the Permit/Approval/Licensing Inspectors to complete the required
inspections for the Works under this Contract. The related costs and expenses incurred
by the Contractor shall be borne by the Contractor, with no change in the Contract Price
and/or Contract Time.
.10
The Contractor shall meet all applicable equipment standards and regulations regarding
noise emissions. Ensure all vehicles are in good condition and use effective muffling
devices.
.11
Comply with City of Ottawa Noise By-law No. 2004-253 (unless provided an approved
exemption as 1.5.1.12 above) with the summary as below. Exemptions must be applied
for at least 5 working days prior to work.
.1
No person shall, between 22:00 hours of one day and 07:00 hours of the next day
operate or cause to be operated, any construction vehicle or construction
equipment in connection with the construction of any building or structure,
highway, motor car, steam boiler or other engine or machine.
.2
.3
the use of construction equipment shall not create noise likely to cause a nuisance
or disturb the inhabitants or exceed 90 dBA when measured at the point of
reception,
.4
the use of the construction equipment shall not continue for more than eight (8)
hours on any one day,
.5
the duration of any noise exemption requested shall not exceed thirty(30) calendar
days in length, unless specifically requested by the Contractor and
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
SECTION 01060
REGULATORY REQUIREMENTS
PAGE 5 OF 12
ATTACHMENTS
PWGSC AUTHORIZATION FOR VEHICULAR ACCESS
PWGSC CONSENT TO CRIMINAL RECORD VERIFICATION
PWGSC PARLIAMENTARY PRECINCT COMMUNIQUES
PWGSC AUTHORIZATION FOR BUILDING ACCESS (To Be Provided by Addendum)
RVCA SHORELINE WORKS PERMIT (To Be Provided by Addendum)
END OF SECTION
SECTION 01060
COMBINED SEWAGE STORAGE TUNNEL
SECTION 01060
COMBINED SEWAGE STORAGE TUNNEL
SECTION 01060
COMBINED SEWAGE STORAGE TUNNEL
SECTION 01060
COMBINED SEWAGE STORAGE TUNNEL
SECTION 01060
COMBINED SEWAGE STORAGE TUNNEL
SECTION 01060
COMBINED SEWAGE STORAGE TUNNEL
SECTION 01060
COMBINED SEWAGE STORAGE TUNNEL
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01080
MANUFACTURERS' SERVICES
PAGE 1 OF 4
This section includes instructions regarding manufacturer support during and following
installation.
DEFINITIONS
.1
1.3
Person-Day: One person for 10 hours within regular Contractor working hours.
SUBMITTALS
.1
Training Schedule to the Owners operating staff: Submit schedule of time and date to
Owners staff not less than 15 working days prior to designated training dates and revise
as necessary for acceptance.
.2
Lesson Plan: Submit proposed lesson plan or instruction material to Owners staff not
less than 15 working days prior to scheduled training and revise as necessary for
acceptance.
.3
1.4
.2
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
.2
The time necessary to complete all manufacturers services, to ensure a fully operational
and satisfactory installation, shall be included under the Total Lump Sum Tender Price
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01080
MANUFACTURERS' SERVICES
PAGE 2 OF 4
Where time is necessary in excess of that stated in the individual specification section for
manufacturers services, or a minimum time is not specified, the time required to
perform specified service is considered incidental.
.4
Schedule manufacturers services to avoid conflict with other onsite testing or other
manufacturers onsite services.
.5
Determine, before scheduling services, that all conditions necessary to allow successful
testing have been met.
.6
Only those days of service approved by the Contract Administrator will be credited to
fulfill the specified minimum services.
.7
3.2
.1
.2
.3
.4
Revisiting the site as required to correct problems until installation and operation
are acceptable to Contract Administrator.
.5
.6
Assistance during factory acceptance testing (FAT), site acceptance testing (SAT),
functional and performance testing, facility start-up, commissioning and
evaluation.
.7
.8
.2
The Contract Administrator may permit use of certain materials or assemblies prior to
sampling and testing if accompanied by acceptable certification of compliance.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01080
MANUFACTURERS' SERVICES
PAGE 3 OF 4
.3
.4
3.3
Before commencing installation of equipment, the Contractor shall arrange for the
attendance of the Manufacturers Representative to provide instructions in the methods,
techniques, precautions, and other information relevant to the successful installation of
the equipment.
.2
When the Manufacturers Representative is satisfied that the Contractor is aware of all
installation requirements, he shall so certify by completing Form 101 attached to Section
01810 - Commissioning.
.3
3.4
.2
Such form shall certify that the signing party is a duly authorized representative of the
manufacturer, is empowered by the manufacturer to inspect, approve and operate their
equipment and is authorized to make recommendations required to assure that the
equipment is complete and operational.
.3
3.5
General:
.1
.2
.3
.4
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.3
SECTION 01080
MANUFACTURERS' SERVICES
PAGE 4 OF 4
Pre-Commissioning Training:
.1
.2
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
SECTION 01100
SPECIAL PROJECT PROCEDURES
PAGE 1 OF 5
RELATED SECTIONS
.1
.2
.3
.4
.5
1.3
REFERENCES
.1
1.4
.1
.2
.3
.4
1.5
.2
.3
All areas to be cleaned to the condition of the area prior to the work being done.
.4
.5
Coordinate with the City and Utility Companies in advance about any modification to the
existing facilities. Refer to Section 01050 - Coordination for details.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.6
SECTION 01100
SPECIAL PROJECT PROCEDURES
PAGE 2 OF 5
LIMITS OF CONSTRUCTION
.1
The Contractor shall note that all work is to be contained within the limits of
construction as marked on the Contract Drawings. Trespassing outside these limits is not
allowed. This requirement will be strictly enforced.
.2
The Contractor shall coordinate the use of premises for staging, construction, storage and
access area under the direction of the Owner and the Contract Administrator.
1.7
1.8
The Contractor shall provide access to existing City infrastructure in operation on or near
work sites to City personnel at all times to meet its operational needs.
RELICS, ANTIQUITIES AND ARCHAEOLOGICAL FINDS
.1
The Contractor is made aware that the Owner will have archaeological staff present
during all excavation works at all sites. Allow access to Work for monitoring during
excavation. If part of Work is in preparation at locations other than Place of Work, allow
access to such Work whenever it is in progress.
.2
The Contractor shall develop an Archaeological Risk Management Plan and submit it to
the City at least 30 calendar days prior to mobilization. The Plan shall be developed in
consultation with the Algonquins of Ontario and the Quebec Algonquins (Kitigan Zibi
Anishinabeg), and as a minimum, shall include the following:
.1
.2
.3
A process to ensure that the Contractor complies with all applicable laws for the
management of archaeological sites, including the Ontario Heritage Act.
.4
.3
During the Work, the Contractor shall protect relics, antiquities, items of historical or
scientific interest such as cornerstones and monuments, commemorative plaques,
inscribed tablets, and similar objects found during course of work.
.4
If the Contractor's operations expose any items that may indicate an archaeological find,
such as building remains, hardware, accumulations of bones, pottery, or arrowheads, the
Contractor shall immediately notify the Contract Administrator and suspend operations
within the area identified by the Contract Administrator. Notification may be verbal
provided that such notice is confirmed in writing within 2 calendar days.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01100
SPECIAL PROJECT PROCEDURES
PAGE 3 OF 5
.5
Work shall remain suspended within that area until otherwise directed by the Contract
Administrator in writing, in accordance with the General Conditions and Supplementary
General Conditions.
.6
The Contractor shall provide access to the NCC archeologist to observe any
archeological find.
.7
Any delay in the completion of the Contract that is caused by such a suspension of Work
shall be considered in accordance with General Conditions and Supplementary General
Conditions.
.8
The Contractor shall take all reasonable action to minimize additional costs that may
accrue as a result of any work stoppage.
1.9
REPLACEMENT PARKING
.1
1.10
The Contractor is made aware that the Owner will compensate PWGSC for parking
spaces eliminated as part of the construction works at Site 6 that are identified on the
Contract Drawings. The Contractor is not permitted to freely occupy PWGSC parking
spaces unless specifically identified on the Contract Drawings. Locations of alternate
parking will be determined by PWGSC. Refer to Section 01117 for additional details on
parking restrictions at Site 6.
STORAGE AND PROTECTION OF MATERIALS AND EQUIPMENT
.1
Protect materials and equipment after unloading, from weather, dust, dirt and moisture,
both before and after erection and placing. Observe manufacturer's written instructions
for temporary storage.
.2
Provide manufacturer's written instructions for the storing of equipment during the
construction period, well in advance of equipment delivery.
.3
.4
Store materials subject to water absorption off the ground. Protect materials from other
damage due to environmental conditions using waterproof covers.
.5
As work proceeds and upon completion, promptly clean up and remove from site surplus
materials resulting from foregoing work.
.6
Storage of materials and equipment is not allowed within operational sewers. Material
and tools left within operational sewers shall be moved to the designated storage location
at the end of the working day.
.7
The electrical, communication, instrumentation and control products and equipment with
the bearings shall be stored at minimum 15 degree C.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.11
SECTION 01100
SPECIAL PROJECT PROCEDURES
PAGE 4 OF 5
The Contractor will be held fully responsible by the City for any damage to utilities,
properties, buildings, homes or structures adjacent to or in the general area of the work,
through settlement of ground, vibration or shock resulting from any cause relating to the
work carried out under this Contract. Make good and repair such damage at own
expense.
.2
1.12
1.13
If at any time, in the opinion of the Contract Administrator, damage is being or is likely
to be done to any road, highway, improvements or property therein, other than such
portions as are part of the work, by the Contractor's vehicles or other equipment whether
licensed or unlicensed, the Contractor shall, on the direction of the Contract
Administrator and at the Contractor's own expense, make changes in or substitutions for
such vehicles or other equipment or shall alter loadings or shall in some manner remove
the cause.
PROPERTY OWNERS LETTER OF RELEASE
.1
.2
This letter of release will only be required where damage has been caused to private
property or where work takes place on private property or easements.
1.14
1.15
.1
Make adequate protection and take all necessary precautions at times of inclement
weather. Refer to Section 01117 Construction Sequences for flow management and
other construction constraints.
.2
Inclement weather or extra work caused by such weather will not be accepted as reason
for additional payment or an extension to the time of completion.
1.16
SNOW REMOVAL
.1
The Contractor shall be responsible for snow and ice removal in the designated
construction area and related access roads as well as Contractors staging and storage
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01100
SPECIAL PROJECT PROCEDURES
PAGE 5 OF 5
areas at its own cost. The Contractor will not be permitted to dump or store snow outside
of the designated staging area. No storage or dumping of snow is permitted in staging
area at Site 6.
.2
Snow plowing shall be under the direction of the Contract Administrator and shall not
block the access road or public roadway.
.3
Where the Contractors work affects or impedes local snow clearing, the Contractor shall
be responsible for clearing and removal or making necessary accommodations to allow
City or private snow clearing and removal.
.4
Snow clearing of Pit Road and Confederation Pit parking lot at Site 6 to be performed by
PWGSC.
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
GENERAL
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 1 OF 36
.1
The Work is to be completed in the time stated in Section 00400 - Form of Tender and
Section 00200 instructions to Tenderers. In this regard, the Contractor is responsible
for scheduling the sequence of work.
.2
.3
The conceptual construction sequences referred to herein are general in nature and
illustrate the design intent with respect to execution of the Work. The Contractor shall
prepare and submit a proposed sequence of construction for review by the City and
Engineer. This review will serve to satisfy the City and Engineer that all mandatory
construction constraints have been properly addressed by the Contractor in the proposed
sequence of construction but shall in no way relieve the Contractor of complete
responsibility for execution of the Work in accordance with the requirements of the
Contract Documents. The descriptions of construction activities as outlined in this
Section and in the Contract Drawings are not intended to be comprehensive or allinclusive. Many other construction activities and work components, although not
specifically noted in this Section or in the Contract Drawings, are integral parts of the
Work and shall be scheduled and completed by Contractor in accordance with the
Contract Documents.
.4
The Contractor shall plan to perform the work activities in such a sequence that does not
interrupt the continuous operation of the existing sewers and other facilities at any time
during the construction period.
.5
Unless noted otherwise, the City and Engineer reserve the right to review and revise the
Contractors schedule and the sequence of construction to comply with the operational
constraints defined in this section without additional cost to the Contract. Refer to
Section 01015 Attachment A for additional information on specific property parcels
being acquired by the City for this project.
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 2 OF 36
.6
.7
.8
.9
.10
1.3
SUBMITTALS
.1
Submit within two (2) weeks of contract award a detailed sequence of work that meets
the requirements of Section 01330 Submittal Procedures.
.2
Flow management constraints for managing live wastewater flow during dry and wet
weather events are described in this Section. Conceptual flow control methods outlined
in the Contract Drawings are suggested only and were developed to minimize the bypass
pumping requirements given the flows that can be anticipated. The Contractor may
present other options based on their own experience.
.3
Following award of the contract, the Contractor shall develop a conceptual design of its
Flow Management Plan for each site in coordination with the requirements of the Citys
Environmental Services Division (ESD), Wastewater Collection group. After the
conceptual design is verified by ESD, the Contractor shall submit its own method of flow
diversion and control in a Flow Management Plan, and the related shop drawings subject
to performance criteria for the Engineers review and acceptance a minimum of three (3)
weeks prior to commencing the Work. The Contractor is ultimately responsible for
developing their own Flow Management Plans and shall not rely on the conceptual flow
control methods illustrated in the Contract Drawings as the basis for their bid or flow
management plan.
1.
The flow management plan at each site shall include the following as a
minimum:
.1
.2
.3
.4
.5
Drawings to show the locations of the plug and/or dams to block the
flow and locations of the pumping and piping
.6
List of the major equipment including the size of the pumps and piping
.7
2.
The Flow Management Plan shall also include alternative flow management
methods for each site in the event that the primary method fails.
3.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.4
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 3 OF 36
4.
5.
6.
Meetings will be required for the Contractor to review the bypass flow
management plans (for each site) and sequence of construction with the
Engineer, City Project Manager and Environmental Services Department (ESD)
staff prior to implementation. Resubmittal of the plans shall be completed within
seven (7) working days following the meeting. The number of meetings required
will depend on the Contractors proposed flow management plan and on a site by
site basis. Bypass of flow and associated construction activities may not
commence until approval is received from the City.
7.
The Contractor shall complete and submit a Flow Management Plan Form F1007 to ESD. Ongoing flow management work plan updates must be submitted
on a regular basis as detailed in this Section.
COORDINATION
.1
It is noted that the proposed Works must be performed so as not to interfere with or
cause any un-scheduled interruption of operation of the existing components of the sewer
and regulator operation at all sites, and must not cause overflows to the Ottawa River
that would classify as spills, except as described herein.
.2
Coordinate the requirements of this Section with the other requirements of the Contract
Documents.
.3
Coordinate with the Ottawa Light Rail Transit (OLRT) through the City of Ottawas Rail
Implementation office and the Contract Administrator to ensure no impact of this
contract work on OLRTs construction operations.
.4
.5
The existing sewer network facility operates 24 hours per day, 7 days per week. In the
event of conflict between construction operations and routine regulator/sewer operations,
all regulator/sewer operations have priority. Take every precaution to avoid interfering
with routine regulator/sewer operation and maintenance. Reschedule construction
activities, if required, without change to the contract price. Access to all existing
infrastructure by City forces shall be maintained at all times.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 4 OF 36
.6
.7
Do not block or modify sewer lines, open or close valves, or take other action which
would affect the operation of existing systems (i.e. flow management), except as
specifically required by the Contract Documents and only after the prior authorization of
ESD and the Engineer has been obtained.
.8
The Owner will limit the duration of shutdowns of important or critical systems.
Stated durations are the total time period between when the system is made
available to the Contractor and when it is ready for return to service. If the
Contractor cannot complete the Work within the allowed time, the Contractor
shall immediately request an extension from the Owner. If the Owner does not
approve the requested extension, the Contractor shall complete the Work or return
the system to operable condition. The Owner will complete the Work if the
Contractor does not return the system to operable condition as directed. The
Contractor is responsible for extra costs or damages incurred by the Contractor or
the Owner to meet these requirements.
2.
The Contractor acknowledges that any operation impacting the flow of the
existing sewers, regulators or wastewater flow in any way, referred to hereinafter
as a shutdown, shall require observation, approval or monitoring by the City of
Ottawa ESD Operations Staff as outlined in the Ontario Water Resources Act and
associated regulations. The Contractor shall provide the Contract Administrator a
minimum 72 hour notification for requiring ESD staff onsite.
3.
When the Contractor requires a part of the sewer/regulator system shutdown for
execution of construction activities (i.e. changes to flow directions in sewers,
sewer isolation, slide gate movement, regulator control/power/communication
interruption, etc.), a formal shutdown request must be made in writing to the
Contract Administrator at least 72 hours (excluding Saturday, Sunday, and legal
holidays) in advance of the requested shutdown date. The shutdown request shall
describe in detail the proposed method, and the procedures proposed to
accomplish each portion of the Work that requires an interruption to the
operation of the existing facility. The Contractor shall not begin any such work
until it has received written acceptance of the methodology and approach from
the Engineer. The Contractor shall include in its plan the specific number of
days to complete each facility interruption.
4.
With each formal shutdown request and within the Flow Management Plan, the
Contractor shall include the following:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 5 OF 36
List the labour, equipment, materials, tools, utilities and incidental items
to be used.
.3
.4
.5
.6
.7
.8
.9
.10
5.
The Contractor participating in the planning and execution of the shutdown shall
coordinate with ESD on the planning of the shutdown activity. The Contractor and
ESD shall work together to establish a shutdown specific energy and equipment
lockout strategy that is required for each shutdown of existing facilities and/or all
work that includes the Contractors work to connect new facilities to the existing
plant facilities. The City is not obliged to provide the shutdown within the 72 hour
period if the effectiveness of the regulator/sewer operations could be
compromised. The City will not unreasonably delay or refuse to make the
regulator/sewer processes or systems available for the Contractors construction
activities. A delay or refusal shall be based on the Citys opinion that the
performance of the regulator/sewer will be compromised or until resources are
available.
6.
At each location where tie-in is required, the Contractor shall provide a complete
system of temporary works including bulkheads, pumps, power, equipment,
watertight separations and labour as necessary to maintain regulator/sewer
flow/operations as identified in 1.5and to allow for construction of the new
structures.
7.
8.
The City reserves the right to cancel any scheduled shutdown if regulator/sewer or
weather conditions dictate, at no additional cost to the City. The Contractor will be
provided with written notification of any such cancellation.
9.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.9
.10
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 6 OF 36
During the construction, the Contractor shall provide and maintain all necessary
labour, material and equipment required for flow management at each site
including pumping, piping, valves , generator, power, diversion, bulkheads and
fuel etc. that ensure the flow does not interfere with the construction operations,
system operations, no overflows to the Ottawa River that would classify as a spill,
no flow backup leading to surcharge to the existing gravity pipes and no damage
to the existing facilities and grounds.
2.
In case of bypass pump failure, the backup pump shall be provided within one
hour of the pump failure, and be of the same or greater capacity.
3.
The Contractor shall also provide the required temporary construction, drainage,
grading, sedimentation and erosion control measures for the construction area.
4.
Any and all costs related to cleanup or damage resulting from not maintaining the
flow management constraints and causing spills or flow backup will be the
Contractors responsibility.
2.
ESD will be required to be onsite during all major shutdowns to observe and
monitor the Contractors works.
.11
In the event any existing facility asset is damaged, the mode of operation is changed, or
there is a risk of actual regulator/sewer upset due to the Contractors work activity, the
Contractor shall stop work immediately, contact the City ESD representative, report the
incident to the Engineer, and make the Contractors on-site resources available at the
request and direction of the Engineer at no extra cost to the project to mitigate any
damage.
.12
If during the execution of the Contractors work ESD or the Engineer observes
conditions that will result in imminent danger to any worker, ESD or the Engineer may
exercise their right to shut down the Contractors work activity until it is determined to
be safe to resume work and the observed risks are under control.
.13
Contractor shall supply and maintain all appropriate and necessary equipment for
confined space entry operations in accordance with applicable regulations.
.14
The Contractor shall coordinate confined space entry operations where multiple parties
are involved in accordance with O.Reg. 632/05.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.5
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 7 OF 36
For the Works, the incoming combined wastewater flow must be bypassed or managed to
complete the Work at several sites. Constraints for flow management are outlined herein.
The Contractor is responsible for submitting detailed flow management plans for each
site at least three (3) weeks prior to commencement of the Work.
.2
.3
The Contractor shall make reasonable effort to schedule as much of the Work as possible
during dry weather conditions.
.4
.5
1.
2.
3.
4.
5.
General: No flow at any point shall be diverted into the EWT or NST unless all
chambers, sewers, tunnels or other works are fully constructed, instrumentation and
controls are commissioned and operational, and capable of accepting and releasing such
flow as intended without issue.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 8 OF 36
.6
The Contractor shall not allow any chunks of concrete or other debris from falling into
the sewer lines during construction. The Contractor is responsible for any damage caused
downstream to City facilities and cleaning of all debris.
.7
The Contractor shall not divert any combined wastewater flow towards the Ottawa River
under any circumstances. Refer to the Contract Drawings and coordinate with the
Engineer to identify which sewers bypass the sites and may lead to the Ottawa River.
.8
.9
Site 1a:
.10
1.
2.
The Booth Street Overflow sewer receives combined sewage during wet weather
events from the upstream Booth and Booth-Wellington Regulators. The
proposed works involve removal of concrete within the sump in the EWT Inlet
Chamber and pipe from the Booth Street Regulator Chamber to the EWT Inlet
Chamber to provide a flow path to the new EWT.
.2
The Work may only be completed during dry periods. When rainfall is
forecast and at the end of each working day, all tools, equipment and
loose materials are to be removed from the work area and the flow path
is to be maintained.
.3
Coordinate with ESD to ensure gates GV01 and GV02 in the Booth
Street Regulator Chamber are open during the Works; if these gates
close, flow is likely to enter the work zone and all construction material
must be removed immediately. GV01 and GV02 must be locked
out/tagged out prior to the Contractor entering the work zone.
The Contractor shall not divert any flow into the CSST at this site.
Site 2:
1.
.12
This Work shall not be completed until the EWT has been fully
commissioned and placed into service.
Site 1b:
1.
.11
.1
The Contractor shall not divert any flow into the CSST at this site.
Site 3a:
1.
Rideau Canal Interceptor (RCI) Flow at Site 3a/b: Dry Weather Flow (DWF) =
up to 390L/s; WWF = up to 15,000L/s; 6.0m maximum head.
2.
3.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.13
4.
Coordinate with City ESD to ensure the existing isolation gate at the Rideau
Canal Regulator is set and locked to the 100% open position while the RCI is
exposed at Site 3a for the duration of construction.
5.
Complete all removal, wall construction and associated chamber works around
the RCI in Site 3a and 3b without impeding sewer flows, and maintain existing
flows at all times.
6.
The Contractor shall maintain the existing sewer flow path, free of debris,
obstructions, sharp bends and interferences at all times.
7.
The Contractor shall ensure that when rainfall is forecast and at the end of each
working day, all tools, equipment and loose materials within flow are removed
from the work area and the flow path is maintained.
8.
The Contractor shall not divert any flow from the RCI or other local sewers into
the CSST at this site.
Site 3b:
1.
Rideau Canal Interceptor (RCI) Flow at Site 3a/b: DWF = up to 390L/s; WWF =
up to 15,000L/s
2.
The Works at this site are limited to construction of a concrete wall and removal
of the two (2) modulation gate actuators and associated electrical and
communication equipment within the existing Rideau Canal Regulator chamber.
The two (2) modulation gates shall also be permanently fixed in the open
position. Complete all work during low flow conditions.
The Contractor shall maintain the existing sewer flow path, free of debris,
obstructions, sharp bends and interferences at all times.
3.
.14
Site 3c:
1.
.15
The Contractor shall not divert any flow into the CSST at this site.
Site 4:
1.
2.
3.
.16
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 9 OF 36
The Contractor shall reroute 1200 mm dia storm sewer and 525 mm dia sanitary
sewer prior to commencing Work on the tunnel shaft.
Storm sewer theoretical capacity = 3,000 L/s; sanitary sewer theoretical capacity
= 318 L/s.
The Contractor shall not divert any flow into the CSST at this site.
Site 5:
1.
.2
.3
The new IOS connection chamber is intended to connect the new EWT
from the new EWT Outlet Chamber to the IOS. Flows to this junction
structure will ultimately be controlled by a dual gate system within the
EWT Outlet Chamber upon CSST completion. Complete all construction
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 10 OF 36
2.
.4
The Contractor shall not divert flow from the IOS or other local sewers
into the CSST at this site. The contractor shall plan the implementation
of the flow management measure with the Citys operation group to
assess whether it may be possible to partially control/mitigate flows at
the chamber site through real time control along the system to facilitate
the installation.
.5
Monitor upstream IOS water levels closely through City ESD and
connect to IOS during low flow conditions only. Do not connect to the
IOS when rainfall is predicted. The above noted DWF depth is the
minimum anticipated at all times, so the Contractor shall manage flows
entering the work zone to avoid sewage spills. Ensure removed pipe
sections or debris from pipe sections do not enter the flow channel.
.6
At the end of each working day, all tools, equipment and loose materials
are to be removed from the work area and the flow path is to be
maintained.
.7
The Contractor shall minimize the time that sewage is exposed to the
atmosphere when connecting to the IOS.
.2
.3
.4
.5
.6
.7
The Contractor shall ensure that when rainfall is forecast and at the end
of each working day, all tools, equipment and loose materials are
removed from the work area and the flow path is maintained.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.
.8
The contractor shall plan the Work at this site with the Citys operation
group to assess whether it may be possible to partially control/mitigate
overflows at the chamber site through real time control along the system.
.9
The Contractor shall not divert any flow from the RRC Overflow Sewer
or other local sewers into the CSST at this site.
.2
.17
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 11 OF 36
.2
.3
.4
.5
Site 6:
1.
Kent Street Storm Sewer Theoretical Capacity = 13,600 L/s and may
flow at full capacity, being a storm sewer outfall. Very low flow during
dry weather flow conditions, but constant low flow to be expected.
.2
.3
The new storm outfall chamber at Site 6 will combine flows from the
NST overflow sewer and the 2400 mm Kent Street Storm Sewer.
.4
Contractor shall manage flows entering the work zone with the use of
diversions and/or bypass pumping. It is expected that management of
flows will only be appropriate during dry weather flow and other low
flow conditions.
.5
.6
.7
The Contractor shall not divert any flow into the CSST at this site.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
2.
.18
The Contractor shall ensure that when rainfall is forecast and at the end
of each working day, all tools, equipment and loose materials are
removed from the work area and the flow path is maintained.
.2
.3
The existing 275 mm diameter drop pipe is to be abandoned and the 300
mm diameter pull-back sanitary sewer is to be decommissioned.
Regulator chamber is to be rebenched afterward. Complete the work
without impeding overflows within this sewer.
.4
.5
The Contractor shall not divert any flow into the CSST at this site.
.6
The Contractor shall ensure that when rainfall is forecast and at the end
of each working day, all tools, equipment and loose materials are
removed from the work area and the flow path is maintained.
.7
Site 8:
1.
.19
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 12 OF 36
The Contractor shall not divert any flow into the CSST at this site.
Site 9:
1.
2.
3.
4.
Complete all removal, wall construction and associated chamber works around
the Catherine Street Sewer without impeding sewer flows, and maintain existing
flows at all times.
5.
The Contractor shall not divert flow from the Catherine Street Sewer or other
local sewers into the CSST at this site.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.20
6.
The Contractor shall maintain the existing sewer flow path, free of debris,
obstructions, sharp bends and interferences at all times.
7.
The Contractor shall ensure that when rainfall is forecast and at the end of each
working day, all tools, equipment and loose materials within flow are removed
from the work area and the flow path is maintained.
Site 10:
1.
1.6
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 13 OF 36
The Contractor shall not divert any flow into the CSST at this site.
The air duct for the odour control facility at Site 1b is to pass above the OLRT near the
tunnel portal. Under no circumstances will the Contractor be permitted to modify or
disturb or interrupt construction or operations of the OLRT tunnel during construction of
the duct.
1.
The Contractor shall ensure the OLRT crossing is constructed as shown in the
Contract Drawings.
2.
The Contractor shall include all associated costs with maintaining OLRT
operations for the duration of construction in their Tender Price.
3.
.2
.3
The Contractor shall coordinate the relocation of the existing Rogers/Allstream plant at
Site 2 with Rogers (contact Graeme Juhasz 613-898-5684) and Allstream (contact Al
Robidoux 613-799-8397 or John Steele 613-790-1974).
1.
2.
3.
.4
The Contractor shall schedule a meeting with Rogers and Allstream prior to
construction or any work in the vicinity.
The Contractor shall excavate and expose the existing plant and coordinate
relocation by a Rogers and Allstream approved Contractor.
All costs associated with coordinating and completing the relocation is included
in the Tender Price and there shall be no claim for any delays associated with
scheduling or coordinating the work.
Protect the Hydro Ottawa duct at Site 2 for the duration of construction.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
1.
2.
The Contractor shall adhere to the Electrical Safety Authority Guideline for
Excavation in the Vicinity of Utility Lines.
3.
When working in the vicinity of Hydro Ottawa ducts and structures, the
Contractor shall employ a Hydro Ottawa approved heavy civil contractor, and
protect and support the plant per Hydro Ottawa procedures, specifications and
details, including UDS0011, UDS0013 and UDS0022 available at
www.hydroottawa.com.
4.
The Contractor shall include all associated costs with maintaining and protecting
the plant for the duration of construction in their Tender Price.
5.
Should the ductbank be compromised, the Contractor shall notify the Engineer,
City, and Hydro Ottawa immediately. The Contractor will be responsible for all
costs associated with immediate repair.
Protect and/or coordinate the relocation of the existing utility poles and overhead utilities
at Site 5c with Hydro Ottawa.
1.
There are existing overhead Hydro, Bell and Rogers in the vicinity of Site 5C:
.1
Existing 4kV overhead wires on the North side of River Lane as well as
on the West side of Queen Victoria Ave North of River Lane.
.2
2.
3.
The Contractor shall contact Hydro Ottawa prior to commencing work when
proposing to work within 3.0m of Hydro Ottawa distribution lines. No such
work shall commence without approval of Hydro Ottawa.
4.
If relocation the poles or raising the wires is required, the Contractor must
contact Hydro Ottawa well in advance of when the relocation is required.
To accommodate construction on the west side of River Lane (Site 5c), the Bell
and Rogers overhead utilities can be raised approximately 2 feet at the center of
the road. The Contractor shall coordinate this work with Rogers (contact Graeme
Juhasz 613-898-5684) and Bell (contact Richard Miceli 613-299-6554).
The Contractor shall include all associated costs with maintaining, protecting
and relocating existing utilities in their Tender Price and there shall be no claim
for any delays associated with scheduling or coordinating the work.
5.
6.
.6
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 14 OF 36
The Contractor shall coordinate the relocation of the existing gas main at Site 2 and Site
9 with Enbridge.
1.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.7
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 15 OF 36
2.
The Contractor shall provide Enbridge with a minimum notice of 5 business days
prior to relocation. Relocation of the gas main to be completed by Enbridge and
its contractor Aecon.
3.
The Contractor shall include all costs associated with coordinating the relocation
in their Tender Price and shall not claim for any delays associated with
scheduling the work or allowing Enbridge and its contractor access to the sites.
Protect the Hydro One duct at Site 3A adjacent to the odour control facility for the
duration of construction. Under no circumstances will the Contractor be permitted to
modify or disturb this ductbank during construction.
1.
The Contractor shall support the ductbank when crossing it as per the typical
utility support detail shown in the Contract Drawings.
2.
The Contractor shall design the shoring system and plan the excavation methods
for the new works to accommodate this ductbank at all times. The shoring design
shall be submitted to the Engineer for review as per Section 02150 Excavation
Support System. This may include but not be limited to the installation of
engineered shoring parallel to the ductbank to allow for odour control facility
construction.
3.
The Contractor shall include all associated costs with maintaining this ductbank
in operation for the duration of construction in their Tender Price.
4.
Should the ductbank be compromised, the Contractor shall notify the Engineer,
City, and Hydro One immediately. The Contractor will be responsible for all
costs associated with immediate repair, re-wiring of duct.
.8
At Site 5, the Contractor shall maintain an access road through the construction staging
area, as identified on the Contract Drawings, and allow access for City of Ottawa
Operations staff and vehicles to access the Rideau River to facilitate ice management
works. Contractor shall coordinate access with City Operations staff regarding site
specific health and safety requirements, designated access routes and communication
protocols.
.9
Work in Hazardous Areas and Confined Space: refer to Section 01705 - Contract Work
Health and Safety Clauses. Coordinate confined space entry operations where multiple
parties are involved according to O.Reg. 632/05.
.10
The Contractor shall locate the IOS at Site 5, as per the requirements outlined in Section
01720, prior to commencement of NST tunneling works.
.11
Trucking route to Site 5 must be via Sussex Drive and trucks must leave Site 5 via St.
Patrick Street. Vanier Parkway is not a permitted trucking route.
1.7
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.3
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 16 OF 36
1.
The contractor shall carefully co-ordinate the work of this contract with the work
of the control system programmer, to complete construction while meeting the
construction timing restrictions detailed herein.
2.
The contractor will allow for thirty (30) working days (non-consecutive, at each
individual work site), within their project schedule and provide support to the
Owners during this duration for their programming activities. This time does not
include the contractors requirements for the completion of their own testing and
commissioning activities as outlined within this specification.
Construction must proceed while existing sites remains online and operational at all
times.
1.
Any control system shutdowns shall be in strict accordance with the Contractors
schedule and shall be carefully coordinated with the Engineer and Operating
personnel to avoid placing the Owner in a position of increased Risk of
Overflow.
2.
The Contractor shall so arrange the timing of, and the method by which he
carries out the Works so as not to affect the operation of the existing facility.
The work will be carried out to accommodate the Owners continued access for
operating and maintenance of the facility during installation.
The Contractor is advised that there will be more than one occasion in the construction
sequence where control program modifications by the Owner will be required to
continue to the next step in the sequence.
1.
2.
The Contractor shall provide at least fifteen (15) working days notice, in writing,
to the Engineer and Owner when control programming modifications required to
complete construction are required. The Contractor shall identify the proposed
date and time, and specific control programming step required in the written
notification.
.4
The Contractor shall schedule his work and conform with the intent of the following
requirements, and ample allowance shall be made in the schedule to comply therewith.
The following is not intended to imply the Contractor must carry out the work in the
exact manner indicated but is intended to indicate the restrictions that shall be imposed
on construction work sequence. Circumstances may arise during construction that will
change this suggested sequence. The Contractor is also referred to the contract drawings
for further information on construction sequencing.
.5
2.
Obtain an approved schedule and shop drawings and purchase all materials
required to complete the project.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 17 OF 36
3.
4.
5.
6.
7.
.1
.2
Install, test and commission telephone, Rogers fibre and private Ethernet
communications systems.
.3
.4
.5
.6
.7
.8
Confirm operation.
.2
.3
.4
Install, terminate and test all existing monitoring and control points to
new ControlLogix based RPU via existing field terminals.
.5
Install, terminate and test all new monitoring and control points to new
ControlLogix based RPU via new field terminals.
.6
.7
.8
Owner will load new control programs into new ControlLogix based
RPU.
.9
.10
Confirm operation.
.11
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 18 OF 36
the first day. Complete steps 4-7 within the second day. City
programmers/staff will have a minimum of three days to steps 8 to 10.
8.
1.8
Continuous Operational Trial (7-day) on the new control programs at all sites
(existing and new).
General:
1.
All work at Site 6 will be in accordance with the Plans listed in all specifications
submitted by the Contractor for review by PWGSC, which include but are not
limited to those summarized in the master submittal list provided in Section
01330. All plans are to be submitted at least twenty (20) working days prior to
the start of implementation of these plans. The Contract Administrator must
approve all of the Plans prior to their review by PWGSC. No activities at Site 6
shall commence prior to approval by PWGSC of the related Plans. All approved
Plans will be strictly enforced.
2.
3.
4.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
5.
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 19 OF 36
The road network (such as Kent Street, Vittoria Street, Bank Street and Pit
Road) and the Confederation Pit parking lot were not designed nor constructed
for heavy vehicles, equipment, oversized vehicles and loads and commercial
vehicles. The Contractor shall determine the suitability of the road network and
parking lot in regard to load bearing capacity.
.1
6.
Any damage to road network (Kent Street, Vittoria Street, Bank Street),
are to be repaired immediately to an operable standard and to
satisfaction of PWGSC. Prior to conducting works Contractor through
the Contract Administrator is to submit plans and obtain approval from
PWGSC.
.2
Any damage to parking lots (Pit Road and Confederation Pit), are to be
repaired immediately to full pavement structure and subgrade depth and
to satisfaction of PWGSC. Prior to conducting works Contractor
through the Contract Administrator is to submit plans and obtain
approval from PWGSC.
The construction site is to remain accessible at all times to the Royal Canadian
Mounted Police (RCMP), Ottawa Fire Services and PWGSC health and safety
staff.
7.
Parking north of Wellington Street is used twenty four (24) hours a day and
seven (7) days a week, including holidays. Contractor parking is limited to the
construction staging area. Parking of vehicles elsewhere north of Wellington
Street is not permitted.
8.
Construction traffic is to minimize the impacts upon parking and the road and
pedestrian networks. Further, oversized vehicle and other traffic that cannot be
accommodated within the driving lanes and cannot turn within the construction
staging area must be coordinated with PWGSC through the Communiqu
process (see item #28) prior to any disturbance.
9.
10.
11.
12.
Before the start of site activities, a start-up meeting will be held with the
PWGSC manager assigned to the project, and the Contract Administrator, which
shall be attended by the Contractor and the Contractors site representative.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 20 OF 36
Biweekly meetings will be held with these personnel throughout the works at
this site as in 01330 Project Meetings.
.2
The 2015 schedule (appended to this specification section) for site users
illustrates the blocks of time when sittings were scheduled to occur
throughout the calendar year. This shall be used for the basis of bidding
and construction sequencing. 2016 and 2017 schedules will be provided
by PWGSC when available. During sitting sessions construction activity
is to be limited so as to minimize impacts upon building occupants and
site operations. Further, when sitting sessions are not scheduled it is
noted for these blocks of time that buildings remain occupied and site
operations continue; and, as result the Contractor is to be cognizant of
level of construction activity proposed and to minimize impacts upon
respective users buildings and operations.
.2
.3
2.
3.
RCMP may instruct the Contractor directly or PWGSC may instruct the Contract
Administrator (who in turn will notify the Contractor) to curtail activities, stop
work and/or vacate the work site due to planned, unforeseen or other events such
as Very Important Persons (VIP) visitors, demonstrations, late sittings, and
security or perceived disturbances to building occupants and site users. This
direction to act may occur with no advance notice.
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 21 OF 36
materials are not permitted. Also, site construction lighting must be shut
down, booms lowered to horizontal position; and audible equipment
must be shut off such as compressors, generators, excavation or hoisting
equipment, and other noise producing equipment. Note: Dates and times
shown below are subject to change.
.1
Remembrance Day: November 11, from 7:00 AM to 12:00 PM
hours.
.2
Canada Day: July 1, 06:00 AM hours to July 2, 01:00 AM hours.
.3
2017 Canada Day Celebrations: June 29 to July 3, 2017
.4
Police Memorial Service: last Sunday of September from 08:30
AM to 12:30 PM hours.
.5
Fire-fighter Memorial Service: second Sunday of September
from 08:30 AM to 12:30 PM hours.
.3
Monitoring
1.
2.
3.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 22 OF 36
2.
3.
4.
.2
.3
.4
.5
.6
.7
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
.9
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 23 OF 36
.5
.6
.7
1.
The Contractor through the Contract Administrator shall provide PWGSC with a
copy of any and all data and/or results of site investigations, including but not
limited to any reports created or generated from the investigations.
2.
Any additional investigative works on the site during construction, including but
not limited to boreholes, die testing, sewer tracing, sewer cleaning and CCTV,
etc. are to be reported to PWGSC through the Communiqu process. The results
(such as reports, logs, etc.) of these works are to be provided to the PWGSC
through the Contract Administrator.
The Contractor is required to comply with the PWGSC Parliamentary Precinct Branch:
Traffic Operation Safe Operating Guidelines as attached in Section 01353 Special
Procedures: Traffic Control
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 24 OF 36
.8
No vehicular movements are permitted to cross the Ottawa River Pathway while the
pathway remains open between the hours of 7:00AM -9:00AM, 11:30AM-1:30PM, and
3:00PM-6:00PM.
.9
In the event of emergency at Site 6, refer to Section 01705 Contract Work Health and
Safety Clauses.
.10
There will be no compensation in the event of an emergency on site that halts work.
1.9
SCHEDULE CONSTRAINTS
.1
.2
This section lists the specific schedule constraints for when construction is permitted or
not permitted at each site. These constraints may be modified by the Engineer or the City
as construction proceeds. Refer to Section 01015 for additional constraints and details on
property parcels being acquired by the City for this project. See the below table for
specific site schedule constraints.
Site No.
1
(West End
Shaft)
2
(EWT/NST
Intersection)
3a
(Diversion
Chamber)
3a
(Odour
Control
Building)
Schedule Restriction
Access to the site permitted August 1,
2018.
Comment
Restriction applies to all work at Site 1a and
Site 1b.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Site No.
3b
(Rideau
Canal
Regulator)
3c
(Nicholas St.
Shaft)
4 (Patrick St.
Shaft)
5 (EWT
Outlet and
RRC
Diversion)
6 (NST
Overflow)
8 (McLeod
St. Drop)
9 (Catherine
St. Drop)
10
(Chamberlain
Shaft)
10 (Percy
Staging
Area)
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 25 OF 36
Schedule Restriction
Access to the site is permitted
November 1 to April 30 (2016 or 2018).
Access to the site is not permitted
between January 1, 2017 and December
31, 2017.
Access to the site is permitted for a 2
year contiguous timeframe selected by
the Contractor after July 31, 2017.
Comment
Restriction is required to prevent work
during tourist season at the site.
.3
For Sites 4, 5, 6: No work may take place at these sites June 29 through July 3, 2017
inclusive to accommodate Canadas 150th anniversary celebrations scheduled around
July 1st 2017. No work shall occur on any site, with the exception of tunneling works, on
July 1, 2017.
.4
No work shall occur on the project from 10:00am to 12:00pm on November 11 of any
year. Work at Site 3a, 3b and 3c shall comply with the requirements for Site 6 identified
in article 1.8.
.5
Access to Site 3a is permitted only between March 1, 2018 and December 31, 2018. The
Contractor shall demobilize fully from this site by December 31, 2018. Final restoration,
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 26 OF 36
landscaping, and work within the chambers and EWT may be completed between March
1, 2019 and May 31, 2019 (for diversion chamber) and between March 1, 2019 and
August 2019 (for odour control building).
1.
1.10
The type of work permitted between March 1, 2019 and May 31, 2019 (for
diversion chamber) and between March 1, 2019 and August 2019 (for odour
control building) at this site is limited to surface reinstatement, landscaping,
hardscaping, and structural, electrical, mechanical, process and instrumentation
works within the diversion chamber and within the tunnel and de-aeration
chamber. During this period the Contractor shall erect temporary fencing, as
required to delineate and secure their work site. The temporary fencing or
hoarding will be subject to review and approval by the Contract Administrator
and NCC.
FIRE PROTECTION
.1
Provide adequate supplementary fire protection facilities including but not limited to
ample hand-operated 15 to 20 pound multipurpose dry chemical extinguishers at each
work site/facility. Provide temporary hose lines in areas where construction is in
progress until the permanent fire protection is placed into service. Do not block hydrant
hose connections and other firefighting equipment by construction equipment and make
readily accessible at all times.
.2
Dispose of all combustible rubbish promptly and safely. Prompt disposal is particularly
needed for material subject to spontaneous ignition such as oily waste and paint rags.
.3
Monitor and control probable ignition sources as necessary to prevent the threat of fire.
.4
Minimize hot work including but not limited to operations involving open flames, heat,
or sparks such as brazing, cutting, welding, grinding, soldering, and torching. If there is a
practical and safer way to do the Work without hot work, the alternative method shall be
used.
.5
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01117
CONSTRUCTION SEQUENCES
AND CONSTRAINTS
PAGE 27 OF 36
ATTACHMENTS
TEMPORARY AND PERMANENT SUPPORT OF HYDRO DUCTS
2015 SUPREME COURT OF CANADA SITTING SCHEDULE
2015 HOUSE OF COMMENTS SITTING SCHEDULE
2015 SENATE SITTING SCHEDULE
2015 FEDERAL COURT OF CANADA SITTING SCHEDULE
END OF SECTION
SECTION 01117
COMBINED SEWAGE STORAGE TUNNEL CONSTRUCTION SEQUENCES
AND CONSTRAINTS
ATTACHMENTS
SECTION 01117
COMBINED SEWAGE STORAGE TUNNEL CONSTRUCTION SEQUENCES
AND CONSTRAINTS
ATTACHMENTS
SECTION 01117
COMBINED SEWAGE STORAGE TUNNEL CONSTRUCTION SEQUENCES
AND CONSTRAINTS
ATTACHMENTS
SECTION 01117
COMBINED SEWAGE STORAGE TUNNEL CONSTRUCTION SEQUENCES
AND CONSTRAINTS
ATTACHMENTS
SECTION 01117
COMBINED SEWAGE STORAGE TUNNEL CONSTRUCTION SEQUENCES
AND CONSTRAINTS
ATTACHMENTS
SECTION 01117
COMBINED SEWAGE STORAGE TUNNEL CONSTRUCTION SEQUENCES
AND CONSTRAINTS
ATTACHMENTS
2015
HOUSE OF COMMONS
CALENDAR
CALENDRIER
January Janvier
February Fvrier
March Mars
SD ML TM WM TJ FV SS
SD ML TM WM TJ FV SS
SD ML TM WM TJ FV SS
1
8
15
22
1
8
15
22
29
4
11
18
25
5
12
19
26
6
13
20
27
7
14
21
28
1
8
15
22
29
2
9
16
23
30
3
10
17
24
31
2
9
16
23
3
10
17
24
4
11
18
25
5
12
19
26
6
13
20
27
7
14
21
28
2
9
16
23
30
3
10
17
24
31
4
11
18
25
5
12
19
26
6
13
20
27
7
14
21
28
April Avril
May Mai
June Juin
SD ML TM WM TJ FV SS
SD ML TM WM TJ FV SS
SD ML TM WM TJ FV SS
5
12
19
26
6
13
20
27
7
14
21
28
1
8
15
22
29
2
9
16
23
30
3
10
17
24
4
11
18
25
3
10
17
24
31
4
11
18
25
5
12
19
26
6
13
20
27
7
14
21
28
1
8
15
22
29
2
9
16
23
30
7
14
21
28
1 2 3 4 5
8 9 10* 11* 12*
15* 16* 17* 18* 19*
22* 23* 24 25 26
29 30
6
13
20
27
July Juillet
August Aot
September Septembre
SD ML TM WM TJ FV SS
SD ML TM WM TJ FV SS
SD ML TM WM TJ FV SS
5
12
19
26
6
13
20
27
7
14
21
28
1
8
15
22
29
2
9
16
23
30
3
10
17
24
31
4
11
18
25
2
9
16
23
30
3
10
17
24
31
4
11
18
25
5
12
19
26
6
13
20
27
7
14
21
28
1
8
15
22
29
6
13
20
27
7
14
21
28
1
8
15
22
29
2
9
16
23
30
3
10
17
24
4
11
18
25
5
12
19
26
October Octobre
November Novembre
December Dcembre
SD ML TM WM TJ FV SS
SD ML TM WM TJ FV SS
SD ML TM WM TJ FV SS
4
11
18
25
5
12
19
26
6
13
20
27
7
14
21
28
1
8
15
22
29
2
9
16
23
30
3
10
17
24
31
1
8
15
22
29
2
9
16
23
30
3
10
17
24
4
11
18
25
5
12
19
26
6
13
20
27
7
14
21
28
6
13
20
27
7
14
21
28
1
8
15
22
29
2
9
16
23
30
3
10
17
24
31
4
11
18
25
5
12
19
26
SECTION 01117
COMBINED SEWAGE STORAGE TUNNEL CONSTRUCTION SEQUENCES
AND CONSTRAINTS
ATTACHMENTS
&
'
JANV.
"
"
"
"
"
>
"
"
"
"
<
<
"
"
"
JUIN
JUNE
"
SEPT.
SEPT.
"
"
"
"
"
"
NOV.
"
DEC.
"
"
"
DC.
MARS
"
&
AOT
"
NOV.
"
"
"
OCT.
"
MAI
AUG.
OCT.
'
"
JUIL.
MAY
JULY
&
MARCH
"
"
AVRIL
"
"
FV.
APRIL
FEB.
2015
JAN.
"
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01119
PRESERVATION AND PROTECTION
PAGE 1 OF 6
This Section specifies requirements for preservation and protection of existing and new
utilities, services, buildings, structures, and property.
GENERAL
.1
1.3
Comply with all requirements and regulations of the City of Ottawa and Utility
Companies, especially those pertaining to protective work, inspection and safety.
MAINTENANCE AND PROTECTION OF EXISTING UTILITIES, SERVICE,
STRUCTURES AND PROPERTIES
.1
The Contractor will be held fully responsible by the Owner for any damage to utilities,
services, properties, buildings, or structures adjacent to or in the general area of the
work, through settlement of ground, vibration or shock resulting from any cause relating
to the work carried out under this Contract. Make good and repair all such damage at
own expense.
.2
The Contractor shall supply and install the shoring, bracing and support system at his
own judgment and at his own cost to protect the existing utilities, services, buildings and
structures from damage for the duration of the construction. The cost for this item shall
be included in the tender price and the Contractor shall not make any claim against the
Owner for extra work on this item.
.3
Perform Work within right of way and easements in a systematic manner that minimizes
inconvenience to property owners and the public.
.4
During emergencies, no residence or business shall be cut off from vehicular traffic for a
period exceeding four hours, unless special arrangements have been made.
.5
Keep fire hydrants and water control valves free from obstruction and available for use at
all times.
.6
Notify property owners and utility offices that may be affected by construction operation
at least five calendar days in advance, and as per the PWGSC communique process for
works at Site 6 as in Section 01117 Construction Sequences and Constraints.
.7
.8
Request owners of all underground services to locate, stake and clearly mark in the field
all services which are located on or near the line of the proposed work. For works at Site
6 the Contractor is to locate the site utilities themselves. Refer to Section 01117
Construction Sequences and Constraints for details.
.9
Obtain certificates from all utility companies having facilities in the area of the proposed
works certifying that facilities have been marked to confirm the utility location.
.10
Utilize non-mechanical means such as hydrovac excavation to determine the location and
depth of utilities when not known.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01119
PRESERVATION AND PROTECTION
PAGE 2 OF 6
.11
Sustain in their places and protect from direct or indirect injury, all water and gas mains,
sewers and drains, conduits, cables, service pipes, poles, sidewalks, curbs, embankments,
structures, equipment and other property in the vicinity of the work.
.12
Sustain and support structures that are uncovered, weakened, endangered or threatened.
.13
Use flowable concrete fill if required or upon request by Contract Administrator or the
utility to provide additional support during reinstatement.
.14
Notify the Contract Administrator immediately (and follow up in writing) if and when
any damage to such facilities occur during the planned execution of work. Provide all
necessary written documentation such as incident reports, accident reports, investigative
reports and preventative measures to be implemented within 48 hours of any incident
taking place, in a format that clearly identifies details such as the report author, his/her
role in the project, the company the author represents, date, signature, etc., all on
Contractors Company letterhead.
.15
Repair immediately all items that are damaged during construction, at no cost to the
Owner.
.16
Immediately report all damages occurred on the City's or any other land owners
property, existing services and structure during construction to the Contract
Administrator.
.17
Protect from damage the existing SCADA pole located adjacent to the existing biofilter
odour control facility at Site 5. Survey the pole and alignment on a weekly basis to
monitor ground movement. Immediately report any movement or damage to the City and
Engineer and provide a plan to repair the damage.
.18
Prevent dust and dirt from entering existing buildings or areas where equipment is stored
or is operating. Refer to Section 02362 - Dust Control for further detail regarding control
of dust and application of dust suppressants.
.19
Prevent dust, water or other deleterious substances from entering areas with existing
electrical, heating, ventilating, pumping and other equipment. The Contractor will be
held responsible for any damage caused by work carried out under this Contract.
.20
Where existing wall sections are removed or where pipes are installed through existing
walls or where any dust-generating operation is necessary, provide a suitable temporary
wall or enclosure suitably reinforced and sealed to prevent dust or water entering the
area. When work is completed, remove temporary dust control device and thoroughly
clean all areas affected by the work.
.21
.22
Control groundwater level to prevent damage to any pipe or structure due to water
pressure during and after construction and until the completed works are accepted.
.23
Protect or cut and cap existing irrigation lines to ensure continued functioning of
irrigation system. Reinstall affected irrigation system lines during final reinstatement
works.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.24
Control of Vibrations
.1
Control vibration levels as per Section 02482 Noise and Vibration Monitoring.
.2
1.4
SECTION 01119
PRESERVATION AND PROTECTION
PAGE 3 OF 6
(Hours)
P.P.V. (mm/s)
Less than 4
50
4 to 60
10
Over 60
50
.3
Schedule and execute placing of concrete so that, for concrete 4 to 24 hours old, a
minimum distance of 40 m between the source of vibration and the concrete is
maintained.
.4
The Engineer reserves the right to require additional restrictive limits for vibration
control if recommended by the inspection agency.
The Contractor shall comply with the following requirements when excavating within 2
metres of any underground high voltage (115kV-230kV) Hydro One cables:
.1
Follow all Infrastructure Health and Safety Association (IHSA) applicable safety
regulations, and any other requirements determined by Hydro One in its
discretion;
.2
Do not perform any excavation within one metre of Hydro Ones underground
cables except in the presence of a Hydro One representative. The third party must
contact Hydro One at 1-888-977-8665 #1, at least 72 hours before excavation
work, to schedule the attendance of the Hydro One representative;
.3
Prior to the commencement of any excavation, inform Hydro One of the proposed
scope of work around the cables and cable trench;
.4
Do not commence any excavation before requesting and obtaining from the Hydro
One representative the approximate cable depth at the work site, unless the third
party determines the exact cable depth by either hand-digging or using hydrovac
equipment, whichever of those two methods has been approved by the Hydro One
representative after considering the type of buried cables;
.5
Ensure that step and touch potentials are controlled by the use of an equipotential
work zone prior to operating hydrovac equipment within one metre of the cable.
The third party must protect the public and all workers from these potential
hazards;
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.5
SECTION 01119
PRESERVATION AND PROTECTION
PAGE 4 OF 6
.6
.7
Where the Hydro One representative identifies the need to support exposed cables,
deliver to Hydro One a temporary support design bearing the stamp of a
professional Engineer to be presented to Hydro Ones Engineering Department;
.8
Ensure that no personnel make direct contact with pipe-type cable without wearing
appropriately-rated personal protective equipment (PPE), because the cable pipe
may become energized during a power system fault. Accidental contact with the
exposed cable shall be avoided;
.9
Do not replace backfill until after the Hydro One representative on site has
inspected all sections of exposed cable following backfill removal and has found
the said cable to be satisfactory;
.10
Use only backfill that satisfies Hydro One specifications, which specifications the
third party shall obtain from the Hydro One representative or from the Hydro One
employee providing the locate.
The Contractor shall comply with the following requirements when excavating within 2
metres of any underground Hydro Ottawa ducts or structures:
.1
.2
.3
Before any work is to be done on an existing Hydro Ottawa duct bank, the extent
of works and proposed method of construction are to be verified and approved by
the Hydro Ottawa inspector.
.4
The Contractor shall be responsible for testing, handling, and disposal of any
environmental contamination associated with the site as per legislative
requirements before the installation of Hydro Ottawas Work.
.5
The Electrical System shall be terminated and disconnected with the completion of
the underground tunnel work by the Contractor and/or prior to the permanent
CSST site services being energized. Hydro Ottawa shall remove its electrical
equipment. The Contractor shall remove the remaining temporary electrical
service equipment and re-instate the site to the property owners standards.
.6
The Contractor shall not vary the design of the System subsequent to the
commencement of construction of the System, without first submitting such
variation in writing to Hydro Ottawa for approval. The Contractor shall not
implement any such variation unless approval in writing has been received from
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01119
PRESERVATION AND PROTECTION
PAGE 5 OF 6
Hydro Ottawa.
.7
1.6
The Contractor shall be responsible for repairing any damages caused to any other
service or utility by any activities arising directly, or indirectly, which are
undertaken by the Contractor. Hydro Ottawa shall be responsible for repairing any
damages caused to any other service or utility by any activities arising directly, or
indirectly, which are undertaken by Hydro Ottawa. The obligation of the
Contractor herein shall continue until a Certificate of Acceptance has been issued
by Hydro Ottawa for the Contractors Work.
Protect all newly constructed work from damage. Prevent heavy loading of newly
constructed work and repair all damage. Construct all works watertight and correct all
imperfect work.
.2
If, in the final inspection, any deficiencies are found, repair or replace the defective
work. Be responsible for satisfactory maintenance and repair of all work undertaken for
the specified guaranteed maintenance period. Protect and store all equipment supplied
under this Contract.
1.7
Furnish all necessary equipment and fuel for heating buildings and structures during
construction. Maintain a minimum temperature of 15 degree C in interior areas for
mechanical, electrical, painting and other work susceptible to frost damage.
.2
Drain pipelines in trench that may be left exposed in winter. Drain pipelines below
concrete slabs or in areas too large to heat practically.
.3
1.8
1.9
Control groundwater level to prevent damage to any pipe or structure due to water
pressure during and after construction and until the completed works are accepted.
SURVEY MONUMENTS
.1
Maintain survey monuments, iron bars, round iron pipes and stakes for marking property
boundaries and locations.
.2
Where monuments, pipes or stakes are located on the line of the trench or within the
limits of the work, the Contractor shall report to the Owner.
.3
Do not remove survey monuments without receiving prior approval. Pay for or replace
monuments which were removed without approval.
1.10
PRECONSTRUCTION SURVEY
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.11
SECTION 01119
PRESERVATION AND PROTECTION
PAGE 6 OF 6
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate general lump sum items for each site included in Section 01025,
Measurement and Payment for all work required in this section as specified herein and
no separate payment shall be made.
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
PART 1
1.01
1.02
1.03
SECTION 01120
PRECONSTRUCTION AND
POST-CONSTRUCTION SURVEY
PAGE 1 OF 6
GENERAL
DESCRIPTION
.1
This section includes the requirements to perform pre-construction and postconstruction inspections for interior and exterior of structures, houses, buildings
and other facilities as described herein. An independent consultant, acceptable to
the Engineer, specializing in preconstruction surveys, shall be retained to conduct
the inspections.
.2
Inspections shall be repeated when monitoring results in Section 02480 Geotechnical and Structural Instrumentation and Monitoring show that movement
has occurred or, in the opinion of the Engineer, to verify the adequacy of
construction methods compared to settlement thresholds.
.3
.4
REFERENCES
.1
.2
SUBMITTALS
1.
2.
3.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01120
PRECONSTRUCTION AND
POST-CONSTRUCTION SURVEY
PAGE 2 OF 6
.1
A letter of introduction shall be provided to the property owner, after it has been
reviewed and approved by the Engineer.
.2
Carry out a precondition survey of all buildings, structures, pavement, utilities and
other items that are likely to be affected by all construction activities, including
trenchless and trenched excavation, shaft excavation, building construction, or
other work within 75m of the tunnel centreline and 75m from the centre of each
shaft, and within 30m of all work staging areas, whichever is larger. In addition
each building or structure proposed to have a tiltmeter installed shall be included
in this survey even if the structure is outside of the 75m limits. The preconstruction inspection shall be carried out in the presence of the affected property
owners. The Contractor acknowledges that property owners are not required by
the City to grant access to their property, and that access is at the discretion of the
individual property owner.
1.
.2
.3
.3
.4
Engineer may be in attendance for the precondition survey with a 48-hour prior
notice and shall have the right to select subject matter and vantage point from which
photos and videos are to be taken.
.5
Surveys in the vicinity of Site 6 and north of Queen Street shall be undertaken in
compliance with the communique process detailed in Section 01117
Construction Sequences and Constraints.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
SECTION 01120
PRECONSTRUCTION AND
POST-CONSTRUCTION SURVEY
PAGE 3 OF 6
General:
1.
2.
The Contractor or firm shall propose the methods, format and standards to
be employed in the survey in a written description and submitted for
approval by the Engineer. No work shall commence until this has been
approved by the Engineer. Minimum requirements include the following:
.1
.2
.3
Recordings shall begin with the date and time of recording, project
name, sheet numbers or engineering stationing as shown on the
Drawings, the name of the street, easement, or building being
recorded, the direction of travel and the viewing side.
.4
.5
.6
3.
4.
5.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
6.
.7
SECTION 01120
PRECONSTRUCTION AND
POST-CONSTRUCTION SURVEY
PAGE 4 OF 6
Area to be Surveyed:
1.
2.
3.
The Contractor shall survey all premises outside the limits defined herein
that in his or the Engineers opinion are likely to be affected by the Work.
4.
5.
Easement areas shall be recorded by video for the full width of the
permanent (or temporary) easements and all other adjacent areas lying
within the zone of influence of construction as directed by the Engineer.
6.
Buildings interiors and exteriors: Record video of all interior and exterior
surfaces of buildings within the zone of influence. Interior coverage shall
include all rooms, hallways, and basements including items sensitive to
settlement as a minimum. Exterior building coverage shall include but not
be limited to, walls visible foundations, chimney, porches and trim.
Particular detailed coverage shall be made at historical and heritage
structures if observed on site, including the conditions of historical repairs
such as grouting, repointing, and building tie-backs.
.8
Recording shall be done during times of good visibility. Do not record during
periods of precipitation or when the ground is covered by snow, leaves, or debris
unless authorized by Engineer.
.9
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.05
.10
Any portion of the recordings deemed unacceptable by the Engineer must be rerecorded at no additional cost to the Owner.
.11
.12
.13
2.
3.
The post-construction survey shall be carried out by the same firm that
performed the precondition survey using the same methods and equipment
previously accepted by the Engineer. The Contractor shall employ
additional survey techniques or measures instructed by the Engineer in
carrying out the post-construction survey.
QUALITY CONTROL
.1
1.06
SECTION 01120
PRECONSTRUCTION AND
POST-CONSTRUCTION SURVEY
PAGE 5 OF 6
.1
All photographs, videos, and recordings produced will become the permanent
property of the City.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
PART 2
2.01
SECTION 01120
PRECONSTRUCTION AND
POST-CONSTRUCTION SURVEY
PAGE 6 OF 6
PRODUCTS
EQUIPMENT REQUIREMENTS
.1
.2
Video must be recorded in colour MPEG2 format compatible with standard video
players. Videos in DVD format from a proprietary DVD recorder are not
acceptable. Audio encoding: uncompressed stereo or stereo Dolby Digital (256
kilobit or better). Aspect ratio 4 by 3 (720 by 480). Video encoding highest
available bit rate (6-9 Megabit), 60 fields per second interlaced.
.3
Audio description shall be made simultaneously with and shall support video
coverage.
.4
.5
PART 3
EXECUTION
3.01
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01160
EROSION AND SEDIMENT CONTROL PLAN
PAGE 1 OF 2
.1
1.3
.1
1.4
City of Ottawa Special Provision S.P. No: F-1005 Erosion and Sediment Control Plan
APPLICATION
.1
The Contractor shall provide an Erosion and Sediment Control Plan for each site,
which shall be signed and sealed by a Professional Engineer registered in the
Province of Ontario.
.2
The NCC and PWGSC is to be provided a copy of the E&S plan at least 15
working days prior to commencement of work, and the Contractor is to revise
according to NCC and PWGSC comments prior to commencing work.
.3
The Contractor shall utilize a tire and vehicle washing station at each site for the
duration of the work at each site.
.4
Consider existing overland flow routes to direct flows through E&S measures.
.5
Consider the location of all E&S measures in relation to existing watercourses and
environmentally sensitive areas (as detailed in Section 01561 Environmental
Protection) and incorporate contingency measures for additional E&S devices and
more frequent replacement and monitoring as required.
.6
Silt fencing is to be installed to prevent species at risk reptiles from accessing the
construction site (as per Section 01561 Environmental Protection). Show location
of this fencing in the E&S plan.
.7
Measurement for Payment section and Basis of Payment section of S.P. No: F-1005
is deleted in its entirety.
.8
The Contractor shall bear all expenses in connection with the erosion and sediment
control plans as part of this item.
.9
Maintain the erosion and sediment control measures in place until the construction
is fully completed.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE
CONTRACT NO. ISD14-2036
1.5
Part 2
2.1
Part 3
3.1
SECTION 01160
EROSION AND SEDIMENT CONTROL PLAN
PAGE 2 OF 2
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate general lump sum items for each site included in Section 01025,
Measurement and Payment for all work required in this section as specified herein and no
separate payment shall be made.
Products
NOT USED
Execution
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
SECTION 01200
ALTERNATIVES
PAGE 1 OF 2
Part 2
Products
2.1
ALTERNATIVE PRODUCTS
.1
Contract documents stipulate pertinent requirements for products and methods to achieve
the Work.
.2
Where products are specified with a manufacturers name and/or model number and
which do not include the words or approved equal, the Contractor shall supply the
specified product. Alternative products will not be acceptable.
.3
Where products are specified with two or more manufacturers names and/or model
numbers and which do not include the words or approved equal, the Contractor shall
supply one of the specified products. Alternative products will not be acceptable.
.4
In the event that, prior to closing of tenders, the Tenderer wishes to offer a substitution
(terms or equal, or equivalent) or a proposal of work, materials or methods as an
alternative to those described in the Contract Documents, he/she shall submit a request in
writing at least thirty (30) days prior to the time for receiving tenders specified herein.
.5
.2
.3
If requested by the City, a list of no less than five (5) projects of comparable size
where the proposed substitution has been used in a similar application, subject to
climatic conditions similar to those experienced in Ottawa. The list shall include
the name, current telephone number, and e-mail address of the Design
Consultant for each project.
.4
In the event, that the City deems the information provided with the request for
approval of a substitution, to be inadequate, the request may be rejected.
.5
.6
Cost of additional work and/or modification to the design due to the use of
alternative materials, products or systems shall be borne by the Contractor.
.7
Where the terms or equal, or equivalent or terms of similar meaning are used
in the specifications, this shall not be construed as acceptance of any alternative
material, product or system to those specified. The use of these terms does not
CITY OF OTTAWA
COMBINED SEWAGE STORAGE
CONTRACT NO. ISD14-2036
SECTION 01200
ALTERNATIVES
PAGE 2 OF 2
relieve the Contractor from his responsibility to follow procedures for approval
of substitutions specified herein (during tender period) or in accordance with the
General Conditions.
.6
The proposed alternative product will be reviewed by the City and the Contract
Administrator. No changes to the specified product shall be authorized without the
official approval in writing by the City and the Contract Administrator. The final
selection of an equipment manufacturer by the City and the Contract Administrator shall
not prevent the selected Contractor from meeting the specified completion date.
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01220
PROJECT MEETINGS
PAGE 1 OF 5
.1
The Contract Administrator will schedule the project meetings throughout progress of
the Work.
.2
The Contract Administrator will prepare meeting agenda with regular participant input
and distribute the written notice of each meeting, preside at meetings, record minutes to
include significant proceedings and decisions, and reproduce and distribute copies of
minutes within 5 working days after each meeting to participants and parties affected by
meeting decisions.
.3
Unless noted otherwise, the project meetings will be held at the Contractors primary site
office. The Contractor shall provide physical space and make arrangements for meetings
at the site in the primary Site trailer as requested by the Contract Administrator.
.4
1.3
PRECONSTRUCTION MEETING
.1
After award of Contract, the Contract Administrator will request a meeting of parties in
contract to discuss and resolve administrative, health and safety procedures and
responsibilities.
.2
.2
.3
.4
.5
Status of bonds and insurance, although these are provided in advance of Contract
Award.
.6
.7
.8
.9
.10
Use of site, access, office and storage areas, security and temporary facilities.
.11
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
1.4
SECTION 01220
PROJECT MEETINGS
PAGE 2 OF 5
.12
.13
Owner-provided equipment.
.14
Record drawings.
.15
Maintenance manuals.
.16
.17
.18
Site security.
.19
.20
.21
Citys representatives.
.2
.3
.4
.5
.6
.7
.8
Others as appropriate.
Prior to start of work at Site 6, the Contractor is to attend a preconstruction meeting with
PWGSC representatives.
PROGRESS MEETINGS
.1
Contract Administrator will schedule regular progress meetings at site, conducted weekly
at minimum to review the Work progress, progress schedule, Shop Drawing and Sample
submissions schedule, Application for Payment, contract modifications, and other
matters needing discussion and resolution. Progress meetings may be held on a more
regular basis depending on current site activities.
.2
Project progress review meeting agenda may include the following, as a minimum:
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
1.5
SECTION 01220
PROJECT MEETINGS
PAGE 3 OF 5
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
.15
.16
Citys representatives.
.2
.3
.4
.5
Others as appropriate.
During works at Site 6, PWGSC and other area stakeholders will be invited to the
progress meetings.
PRE-COMMISSIONING TESTING, FACILITY COMMISSIONING AND
PERFORMANCE EVALUATION MEETINGS
.1
Schedule and attend a minimum of four meetings for Equipment field Testing, Facility
Commissioning, and System Commissioning. The first of such meetings shall be held
prior to submitting respective Testing and Commissioning Plans, as specified in
Section 01810 - Commissioning, and shall include preliminary discussions and
coordination regarding such plans.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01220
PROJECT MEETINGS
PAGE 4 OF 5
.2
.3
Within five (5) working days after the first of testing and commissioning meetings,
submit electronic copies of draft testing and commissioning plans for review and
comment. Draft plans to include a detailed schedule of activities and timing for each
activity. Submit updated testing and commissioning plans for review as required to
obtain Contract Administrator and City acceptance.
.4
Agenda items shall include, but not be limited to, content of Testing and Facility
Commissioning Plans, coordination needed between various parties in attendance, and
potential problems associated with the work.
.5
1.6
.1
Contractor.
.2
.3
.4
.5
Citys representatives.
.6
.7
OTHER MEETINGS
.1
In accordance with Contract Documents and as may be required by City and Contract
Administrator.
.2
Flow Management Plan meeting, for each site, as outlined in Section 01117
Construction Sequences and Constraints.
.3
.4
Concrete pre-pour meetings prior to commencing concrete pours for each project site.
.5
Brief meetings attended by the Contractors key personnel, the Contract Administrator
and as required, the Citys representative every week to review the 14-day detailed work
plan submitted to the Contract Administrator by the Contractor, in accordance with
Section 01117 Construction Sequences and Constraints.
.6
The Contractor shall accommodate site tours of the project sites and tunnels by City
staff, politicians and Consultant staff,
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.1
.2
.3
SECTION 01220
PROJECT MEETINGS
PAGE 5 OF 5
The Contractor shall provide Health and Safety orientation and site orientation to
all attendees.
The Contract Administrator will provide the Contractor a minimum of one (1)
weeks notice prior to a site tour.
The Contractor shall accommodate a maximum of six (6) tunnel and site tours in
each calendar year that the project is underway.
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01310
PROGRESS SCHEDULES
PAGE 1 OF 2
.1
.2
City of Ottawa General Special Provision No. D-010-A Work Schedule and Cash Flow
Forecast
1.3
CONTRACTOR'S RESPONSIBILITIES
.1
.2
.3
Submission of Shop Drawings, product data, material lists and samples. All
required submittals shall be included within the project schedule.
.4
.5
.6
.7
Substantial performance and completion dates within time period required by the
Contract Documents.
.8
.9
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01310
PROGRESS SCHEDULES
PAGE 2 OF 2
.2
Schedule and cash flow forecast shall conform to City of Ottawa General Special
Provision - General No. D-010A Work Schedule and Cash Flow Forecast except as
amended herein.
.3
.4
The contractor shall submit the schedule of material testing within fourteen (14) working
days after the award of the Contract.
.5
Use extra forces and equipment, or revise method of operation when progress of work is
not sufficient to meet Project Schedule.
.6
.7
Construction schedule shall be updated monthly with the payment schedule for the
duration of the Contract. No payment will be made to the Contractor until such time as
an updated project schedule is submitted to, and reviewed by, the Contract Administrator.
.8
Add detail to the schedule as major work components draw closer in time, breaking
down major work components (such as mechanical, electrical, tunneling, shaft works,
etc.) into smaller more specific tasks.
.9
Include Communique Process and associated lead time in the project schedule as
identified in Section 01117.
1.4
CONSTRUCTION CONSTRAINTS
.1
Refer to Section 01117 Construction Sequences and Constraints for other requirements
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SUMMARY
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 1 OF 20
.1
This section defines the submittals to the Owner, or his designate, necessary before,
during and after construction, which include, as a minimum, the items identified in the
submittal list provided as supplemental information to this Section. The Contractor is
made aware that the list of submittals is not comprehensive, is provided for Contractor
reference and that the submittal requirements outlined in each specification Section shall
govern over the list. The Contractor shall not rely on the list and shall prepare their own
submittals list based on the specifications as a whole as per the requirements outlined
herein.
.2
.3
Do not proceed with work until the Engineer reviews relevant submissions.
.4
.5
The Contractor is to produce and submit separate submittals for each site.. This includes
submittals related to works to take place at Site 6. Submittals that are general for all sites
may be provided as a single package for all sites, if permitted by the Contract
Administrator, except where the work at any site requires submittal to and approval by an
external party to the project (NCC, PWGSC, Parks Canada).
1.2
.2
.3
.4
.5
.6
.7
.8
.9
City of Ottawa Special Provision No. General NO. D-018 Requirements for Concrete,
Hot Mix Asphalt and Granular Materials
.10
City of Ottawa Special Provision No. General NO. D-010-A Work Schedule and Cash
Flow Forecast
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.3
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 2 OF 20
ADMINISTRATIVE
.1
Submit to the Engineer a list of submittals for review within twenty (20) working days of
the Award of the Contract and receipt of Order to Commence Work. Submit with
reasonable promptness and in orderly sequence so as not to cause delay in Work. Failure
to submit in ample time is not considered sufficient reason for an extension of Contract
Time and no claim for extension by reason of such default will be allowed.
.2
.3
.4
Where items or information is not produced in SI Metric units, converted values are
acceptable.
.5
Review submittals prior to submission to Engineer. This review represents that necessary
requirements have been determined and verified, or will be, and that each submittal has
been checked and co-ordinated with requirements of Work and Contract Documents.
Submittals not stamped, signed, dated as reviewed by the Contractor and identified as to
specific project will be returned without being examined and shall be considered
rejected.
.6
.7
Verify that field measurements and affected adjacent Work are coordinated.
.8
.9
.10
Keep one reviewed copy of each submission on site for reference during the
construction.
.11
Refer to other individual sections for specific requirements on shop drawing submission.
1.4
PROCEDURES
.1
.2
Unless indicated otherwise, submit one (1) electronic copy and upon request by the
Engineer four (4) paper copies of all submittals.
.3
Electronic Submittals:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
.5
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 3 OF 20
.2
Electronic submittal that contains more than 10 pages in PDF format shall contain
internal book marking from an index page to major sections of the document.
.3
All shop drawings shall be discrete (individual files for each piece of equipment)
native PDF files.
.4
Each shop drawing shall be searchable (i.e. native PDF file, not photocopy or
otherwise).
.5
.6
.7
.8
.9
List of Submittals:
.1
Within twenty (20) working days of receiving the Order to Commence Work,
submit a complete list of submittals.
.2
For each Specification Division, the Contractor shall provide a table listing all the
submittals anticipated for that Specification Division. The table shall include the
following information as a minimum:
.1
.2
.3
.4
.5
Transmittal of Submittal:
.1
.2
Date of Submittal
.3
.4
.2
.5
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
.7
.8
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 4 OF 20
.7
.8
Contractors stamp, signature and statement to certify that the submittal has
been reviewed, checked, and approved for compliance with Contract
Documents
.9
.10
Processing Time:
1.
2.
The Engineer will act upon the Contractor's submittal and transmit response
to Contractor not later than 15 working days after receipt, unless otherwise
specified
3.
4.
5.
Resubmittals:
.1
Clearly identify each correction or change made and include revision date.
.2
.3
.4
The Contractor is noted that the first two submissions of each submittal (original
submittal and subsequent resubmittal) will be reviewed at no charge to the
Contractor. Any cost for processing/reviewing submittals which have been
reviewed two times will be deducted from the contract amount owed to the
Contractor.
Incomplete Submittals:
.1
The Engineer will return entire submittal for the Contractor's revision if
preliminary review deems it incomplete.
.2
When any of the following are missing, submittal will be deemed incomplete:
.1
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.5
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 5 OF 20
A construction and payment schedule for the work is to be submitted by the Contractor
within 14 calendar days after the award of the Contract.
.2
The initial construction schedule will show clearly, in weekly stages, the proposed
progress on the main items, structures and sub-trades of the contract, and shall indicate
where applicable the labour construction crews, plant and equipment to be employed.
.3
Provide the revised construction schedule every 14 calendar days after the first
submission, providing additional detail as major work components draw closer in time.
.4
The payment schedule will provide proposed monthly payments in relation to the
construction schedule to assist the Engineer in project financing and payment
certificates.
.5
1.6
.2
.3
.4
Allow fifteen (15) working days for Consultant's review of each submission.
.5
Adjustments made on shop drawings by Consultant are not intended to change Contract
Price. If adjustments affect value of Work, state such in writing to Consultant prior to
proceeding with Work.
.6
Make changes in shop drawings as Consultant may require, consistent with Contract
Documents. When resubmitting, notify Consultant in writing of any revisions other than
those requested.
.7
Date
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 6 OF 20
.4
Identification and quantity of each shop drawing, product data and sample
.5
.2
.3
Subcontractor
.2
Supplier
.3
Manufacturer
.4
.5
Fabrication
.2
.3
.4
Capacities
.5
Performance characteristics
.6
Standards
.7
Operating weight
.8
Wiring diagrams
.9
.10
.9
.10
All shop drawings shall be discreet (individual files for each piece of equipment)
native PDF files.
.2
Each shop drawing shall be searchable (i.e. native PDF file, not photocopy or
otherwise).
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.11
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 7 OF 20
Submit electronic copies of product data sheets or brochures for requirements requested
in specification Sections and as requested by Consultant where shop drawings will not be
prepared due to standardized manufacture of product. Electronic copies shall conform to
the following requirements:
.1
All files shall be discreet native PDF files (individual files for each piece of
equipment).
.2
Each file shall be searchable (i.e. native PDF file, not photocopy or otherwise).
.12
.13
.14
.15
The review of shop drawings by the Consultant is for sole purpose of ascertaining
conformance with general concept. This review shall not mean that Consultant approves
detail design inherent in shop drawings, responsibility for which shall remain with
Contractor submitting same, and such review shall not relieve Contractor of
responsibility for errors or omissions in shop drawings or of responsibility for meeting
all requirements of construction and Contract Documents. Without restricting generality
of foregoing, Contractor is responsible for dimensions to be confirmed and correlated at
job site, for information that pertains solely to fabrication processes or to techniques of
construction and installation and for co-ordination of Work of all sub-trades.
.16
Material and equipment delivered to the construction site will not be paid until the
pertinent drawings and product data have been reviewed and accepted.
.17
Keep one copy of the reviewed drawing at the site of the work for reference during the
construction.
1.7
SAMPLES
.1
.2
Do not use material in the work which is in any way inferior to the samples submitted
and reviewed. Match accepted samples.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 8 OF 20
.4
Identify samples by project name and number, date, name of Contractor and all other
pertinent information.
.5
.6
.7
.8
Make changes in samples which Engineer may require, consistent with Contract
Documents.
.9
Reviewed and accepted samples will become standard of workmanship and material
against which installed Work will be verified.
1.8
Refer to individual specification sections and the below general details. Also refer to
Section 01750 Operation and Maintenance Manual.
.2
Insofar as practical, test materials and equipment on site. Where shop test is necessary,
give two (2) weeks prior notice in writing of shop test date. The Owner reserves the
right to be present at the testing and/or the Engineer to be present.
.3
Complete an equipment report prior to site testing each item. During testing complete the
remainder of the equipment report. Submit the reports for inclusion in the Installation,
Operation and Maintenance manual.
.4
.5
.6
Inspection includes:
.1
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 9 OF 20
.7
Operate, test and adjust equipment to prove that it is correctly installed to operate under
the intended conditions.
.8
.9
.10
.11
1.9
1.10
Reference Section 01750 - Operations and Maintenance Manual for details related to this
item
EQUIPMENT TESTING AND FACILITY COMMISSIONING PLANS
.1
1.11
.1
.2
Submit two (2) hard copies and one (1) electronic copy of the Interference Drawings to
the Engineer for information.
.3
Show on Drawings locations and relationship of all trades in odour control rooms,
electrical equipment rooms, pipe spaces, and underground structures. Show on Drawings
electrical conduits and pipes to be cast into structural slabs, shafts, tunnel wall, walls and
columns.
.4
.5
After discussion with Owner and Engineer make necessary relocations due to
interference of trades, as a result of incomplete drawings, at no additional cost.
.6
After discussion with Owner or his designated representative make necessary relocations
due to interference of trades, as a result of incomplete drawings, at no additional cost.
1.12
PENETRATION DRAWINGS
.1
Provide drawings detailing all penetrations through walls, floors and ceilings for
mechanical and electrical installations. Identify items that are cast-in-place, sleeved etc.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 10 OF 20
1.14
.1
.2
Impose loads on parts of the works which are still under construction or on
existing structures.
.2
Submit shop drawings for review. Payment will not be made for work started or
completed without the required drawing review. Submit shop drawings well in advance
of the time when they are required for construction. Coordinate shop drawings prepared
by different trades so that information is available to prevent conflict or errors where the
work of one trade affects the work of another.
.3
Shop drawings will be reviewed for conformity with the required arrangement and
dimensions of the permanent structures and for general conformity with the
specifications.
.4
If resubmittal is requested, discuss the comments made and resolve all issues raised by
them, then resubmit the shop drawings amended accordingly.
.5
Do not begin construction of temporary works until after the completion of review of the
shop drawings.
.6
Review of the Contractor's drawings does not relieve the Contractor of the responsibility
for the results arising from errors or omissions of design or from the use or abuse of the
temporary works.
.7
Keep one copy of each stamped, reviewed drawing at the site of the work for reference
during the time the construction work is in progress.
.8
.9
.10
The shop drawings for the temporary work shall be designed and stamped by a
Professional Engineer licensed in the Province of Ontario.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.15
SECTION 01330
SUBMITTAL PROCEDURES
PAGE 11 OF 20
1.16
.1
The Contractor is to develop and provide a Health and Safety Management Plan that is to
be utilized for the duration of this project. Contractor shall review plan on a monthly
basis to ensure that it is up to date. The Owner/Engineer will be the sole authority on
whether the plan is considered complete.
.2
Detailed health and safety plan for this contract shall clearly identify compliance with
the latest revisions and editions of the Occupational Health and Safety Act and
regulations for construction projects.
.3
Refer to Section 01705 Contract Work Health and Safety Clauses for detailed
requirements.
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
SUPPLEMENTAL INFORMATION
OVERALL SUBMITTALS LIST
END OF SECTION
SECTION 01330
COMBINED SEWAGE STORAGE TUNNEL SUBMITTAL PROCEDURES - ATTACHMENT
Description
When Submitted
01810 - Commissioning
01810 - Commissioning
01810 - Commissioning
01810 - Commissioning
01810 - Commissioning
01810 - Commissioning
01810 - Commissioning
01810 - Commissioning
01810 - Commissioning
01810 - Commissioning
01810 - Commissioning
Commissioning Report
Turnaround Time
Fifteen (15) working days after receipt
Upon approval by manufacturer for installation Fifteen (15) working days after receipt
Upon successful completion of field, functional,
performance tests
Prior to or in tandem with submission of
commissioning plan
Minimum of two (2) weeks prior to any
functional testing
At least two (2) weeks prior to entering into the
commissioning phase
At least two (2) weeks prior to entering into the
commissioning phase
At least two (2) weeks prior to entering into the
commissioning phase
At least two (2) weeks prior to entering into the
commissioning phase
At least two (2) weeks prior to entering into the
commissioning phase
At least two (2) weeks prior to entering into the
commissioning phase
Fifteen (15) days prior to Substantial
Performance
At least two (2) weeks prior to designated
training dates
SECTION 01330
COMBINED SEWAGE STORAGE TUNNEL SUBMITTAL PROCEDURES - ATTACHMENT
Section
01820 - Demonstration and Training
01820 - Demonstration and Training
02228 - Blasting
02228 - Blasting
02228 - Blasting
02228 - Blasting
02228 - Blasting
02228 - Blasting
02231 - Clearing and Grubbing
02231 - Clearing and Grubbing
02315 - Excavating, Trenching and
Backfilling
02315 - Excavating, Trenching and
Backfilling
02316 - Rock Removal
Description
When Submitted
Not Specified
At least 30 days prior to beginning any shaft
excavation
At least 30 days prior to beginning any shaft
excavation
Not Specified
Turnaround Time
Stockpiling Plan
Product Data
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
SECTION 01330
COMBINED SEWAGE STORAGE TUNNEL SUBMITTAL PROCEDURES - ATTACHMENT
Section
Description
Other Preconstruction submittals:
- details of the ventilation system
- details and procedures for tunnel safety provisions
- details of noise control measures
- survey methods and procedures proposed
- Details of proposed survey equipment, methods and
procedures
- TBM alignment input data
-Details of system for transport of materials, equipment and
personnel
-TBM cutting head maintenance
- Launching of TBM
- TBM hole-through and removal procedures
-Tunnel Surveying
-Annular grouting
- Handling of spoil
- Contingency Plans
Reports and records: shift reports
When Submitted
Turnaround Time
Not Specified
Product Data
Not Specified
Not Specified
Mix Designs
Not Specified
Not Specified
Logs for each shift for each type of probe/grout hole drilling
Not Specified
Grouting records
Not Specified
Not Specified
Not Specified
Not Specified
02444 - Tunnel and Shaft Ventilation Details and layout of all water flow monitoring equipment to be Not less than thirty (30) days prior to the start of
Fifteen (15) working days after receipt
installed
any tunnel, shaft or related structure excavation
and Utilities
02444 - Tunnel and Shaft Ventilation
Details of all air flow and pressure monitoring equipment
and Utilities
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Welding submittals
Not Specified
Not Specified
Not Specified
During installation
Product Data
Working drawings and Methods statements
Descriptions of proposed grouting equipment for each type of
grouting operation
Mix Designs
Not Specified
Not Specified
Not Specified
Not Specified
Product Data
Not Specified
Not Specified
SECTION 01330
COMBINED SEWAGE STORAGE TUNNEL SUBMITTAL PROCEDURES - ATTACHMENT
Section
02480 - Geotechnical and Structural
Instrumentation and Monitoring
02480 - Geotechnical and Structural
Instrumentation and Monitoring
02480 - Geotechnical and Structural
Instrumentation and Monitoring
02480 - Geotechnical and Structural
Instrumentation and Monitoring
02480 - Geotechnical and Structural
Instrumentation and Monitoring
02480 - Geotechnical and Structural
Instrumentation and Monitoring
02480 - Geotechnical and Structural
Instrumentation and Monitoring
Description
When Submitted
Turnaround Time
As-Built Data
Within one (1) working day following installation Fifteen (15) working days after receipt
Contingency Plan
Not Specified
Mix Designs
Not Specified
Drill Logs
Not Specified
Not Specified
Workforce Qualifications
Not Specified
Certifications
Acceptance Criteria
Not Specified
Not Specified
Shop Drawings
Not Specified
Shop Drawings
Not Specified
Not Specified
Shop Drawings
Manufacturer's test data and certification
Manufacturer's information and data sheets and instructions
CCTV inspection plan
Not Specified
At least two (2) weeks prior to beginning work
Not Specified
At least thirty (30) days prior to inspection
Shop Drawings
Not Specified
Samples
Samples
Price Adjustment Form
Mix and placement form
Product test data
Shop drawings
Layout, pattern, relationship of paving joints to fixtures, project
formed details
Samples, full size sample of each type of paving unit
Shop drawings
Product Data
Shop drawings
Dimensions, sizes, assembly, anchorage, installation details
Maintenace data for care and cleaning
Not Specified
Not Specified
Monthly basis during paving process
In advance of paving
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Product Data
Not Specified
WHMIS MSDS
Not Specified
Not Specified
Not Specified
Samples
Not Specified
Shop Drawings
Not Specified
Product Data
Shop Drawings
Working drawings and Methods statements
Not Specified
Not Specified
Not Specified
Forty (40) days prior to the commencement of
segment production
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
SECTION 01330
COMBINED SEWAGE STORAGE TUNNEL SUBMITTAL PROCEDURES - ATTACHMENT
Section
Description
When Submitted
Turnaround Time
Not Specified
Not Specified
Not Specified
03345 - Concrete Finishing and Curing Manufacturer's reps names and phone numbers
Not Specified
03345 - Concrete Finishing and Curing Manufacturer's certificate of compliance for products furnished Not Specified
Not Specified
03361 - Shotcrete
Materials submittals
03361 - Shotcrete
Methods submittals
03361 - Shotcrete
Test results
Shop drawings
Qualifications
Shop drawings
Mix Designs
Certifications
Not Specified
Not Specified
WHMIS MSDS
Not Specified
Samples
Not Specified
Shop drawings
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Product Data
Not Specified
Shop Drawings
Not Specified
Manufacturer's Instructions
Not Specified
Product Data
Shop Drawings
Quality Assurance Submittals
Manufacturer's Instructions
Test Reports
Product Certificates
Pre-Installation meetings
Shop Drawings
Samples
Product Data
Manufacturer's instructions
Shop Drawings
Samples
Shop Drawings
Erection Drawings
Fabrication Drawings
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Four (4) weeks prior to fabrication of structural
steel
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
SECTION 01330
COMBINED SEWAGE STORAGE TUNNEL SUBMITTAL PROCEDURES - ATTACHMENT
Section
Description
When Submitted
Turnaround Time
Product Data
Not Specified
Shop Drawings
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Samples
Not Specified
Shop Drawings
Not Specified
Not Specified
Shop Drawings
Not Specified
At completion of roofing
Maintenance Data
Not Specified
Not Specified
Product Data
Not Specified
Shop Drawings
Not Specified
07840 - Firestopping and Smoke Seals Accredited Listings with accredited data sheets
Not Specified
Shop Drawings
Door Hardware Data
Closeout Submittals
Samples of each hardware item as requested
Templates, as required
Closeout Submittals
Control Samples
Product Data
Shop Drawings
Samples
Closeout Submittals
Shop drawings and product data
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Closeout Submittals
Not Specified
Closeout Submittals
Not Specified
Product Data
Not Specified
Shop Drawings
Not Specified
Manufacturer's Instructions
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Product Data
Not Specified
Not Specified
Prior to shipment
Following testing
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Shop Drawings
Not Specified
Maintenance Data
Not Specified
Prior to shipment
Special Tools
Not Specified
Not Specified
Not Specified
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
SECTION 01330
COMBINED SEWAGE STORAGE TUNNEL SUBMITTAL PROCEDURES - ATTACHMENT
Section
Description
When Submitted
Turnaround Time
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
13900 - Instrumentation and Controls Instrument analyzer panel dimensioned layout drawings
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
13900 - Instrumentation and Controls Instrument and control panel wiring diagrams
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
13900 - Instrumentation and Controls Instrument and control panel power distribution diagrams
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
Not later than four (4) weeks after tender award Fifteen (15) working days after receipt
13900 - Instrumentation and Controls Final as-constructed control and instrument panel drawings
13900 - Instrumentation and Controls Final as-constructed Operations and Maintenance Manuals
13900 - Instrumentation and Controls Final as-constructed instrument and equipment data sheets
13900 - Instrumentation and Controls Final as-constructed tabulated RPU I/O rack layouts
13900 - Instrumentation and Controls Final as-constructed instrument loop check sheets
Shop Drawings
Not Specified
For all programmable equipment: software, communication
Not Specified
links and networks submit bill of materials
For RPU Equipment: Product description for each item,
equipment layout drawings, related field tag numbers and wire
Not Specified
numbers, location and identifier and pin assignment, switch
settings and addresses, and interconnection diagrams for RPU
equipment hardware
Shop Drawings
Not Specified
Not Specified
Not Specified
SECTION 01330
COMBINED SEWAGE STORAGE TUNNEL SUBMITTAL PROCEDURES - ATTACHMENT
Section
Description
When Submitted
Turnaround Time
Not Specified
Not Specified
Not Specified
Shop Drawings
Not Specified
Not Specified
Not Specified
Shop Drawings
Operation and maintenance data for hoist hardware
Not Specified
Not Specified
Equipment List
Not Specified
Not Specified
Operation data
Not Specified
Maintenance Data
Not Specified
Performance Data
Not Specified
Shop Drawings
Not Specified
Product Data
Not Specified
Site Records
As-built drawings
Not Specified
Shop Drawings
Not Specified
Maintenance data
Not Specified
Shop Drawings
Product Data
Maintenance data
Not Specified
Not Specified
Not Specified
Not Specified
Shop Drawings
Not Specified
Product data
Samples
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Shop drawings
Not Specified
Not Specified
Not Specified
Product Data
Maintenance Data
Not Specified
Not Specified
Shop Drawings
Not Specified
Product Data
Not Specified
Certificates
Not Specified
Not Specified
Not Specified
Product data
Not Specified
Maintenance data
Not Specified
Shop Drawings
Not Specified
Maintenance data
Shop Drawings
Product Data
Maintenance Data
Shop Drawings
Maintenance and engineering data
Shop Drawings
Certification
Operation and Maintenance Manuals
Special tools
Spare Parts list
Maintenance Instructions
Field Procedures
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Prior to start-up
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Shop Drawings
Not Specified
Product Data
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
SECTION 01330
COMBINED SEWAGE STORAGE TUNNEL SUBMITTAL PROCEDURES - ATTACHMENT
Section
Description
When Submitted
Turnaround Time
Shop Drawings
Not Specified
Shop Drawings
Shop drawings
Performance data
Electrical data
Approvals and certification
Maintenance Data
Product Data
Product data sheets
Product Data
Shop Drawings
Fan performance curves, sound rating data, certified power
levels by octave band
Indicate motors, sheaves, bearings and shaft details
Minimum performance achievable with variable speed
controllers
Certificates signed by manufacturer certifying that materials
comply with specified performance characteristics
Manufacturer's installation instructions
Operation and maintenance data
Product Data
Mock-up review showing proposed louvre configuration
Certified Data from independent laboratory
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Product Data
Not Specified
Shop Drawings
Not Specified
Product Data
Not Specified
Shop Drawings
Not Specified
Product Data
Not Specified
Shop Drawings
Product Data
Not Specified
Not Specified
Not Specified
Shop Drawings
Product Data
Operation and maintenance data for each type of starter
Detailed instruction to permit effective operation,
maintenance, and repair
Complete list of maintenance materials
List of spare parts
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Shop Drawings
Not Specified
Not Specified
Shop Drawings
Not Specified
Not Specified
Not Specified
Not Specified
Product Data
Not Specified
Not Specified
Product Data
Not Specified
Product Data
Not Specified
Shop Drawings
Shop Drawings
Product Data
Shop Drawings
Product Data
Not Specified
Not Specified
Not Specified
Not Specified
Not Specified
Product Data
Not Specified
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SUMMARY
.1
1.2
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
PAGE 1 OF 51
Appended City of Ottawa Special Provisions General No. D-005 (SPG D-005), forms
part of this section. Compliance with the requirements of this section shall be to the
satisfaction of the Contract Administrator and PWGSC for Site 6.
SECTION INCLUDES
.1
.2
.3
Operational Requirements
1.3
RELATED SECTIONS
.1
.2
.3
1.4
REFERENCES
.1
.2
Ontario Traffic Manual (OTM) most recent Version(s) including but not limited to
Book 1 Introduction to the Ontario Traffic Manuals
Book 5 Regulatory Signs
Book 6 Warning Signs
Book 7 Temporary Conditions
Book 11 Markings and Delineations
Book 12 Traffic Signals
1.5
Comply with requirements of Acts, Regulations and By-Laws in force for regulation of
traffic or use of roadways upon or over which it is necessary to carry out Work or haul
materials or equipment.
.2
Undertake all submissions, receive comments from appropriate agencies and make
necessary adjustments to obtain approvals for Traffic Control Plan(s), Construction Site
Pedestrian Control Plan(s), Traffic Protection Plan(s), and Traffic Management Plan(s)
which satisfy the requirements of:
.1
.2
.3
City of Ottawa Special Provisions General No. D-005, City of Ottawa Special
provisions
City of Ottawa S.P No F-1010 Traffic Control Plan
City of Ottawa S.P No F-1012: Police at Intersection
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
.5
.6
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
PAGE 2 OF 51
The above Special Provisions are appended to this section. All references to
Measurement for Payment and Basis of Payment shall not be recognized. Requirements
of the above special provisions shall be included in the lump sum payment for Combined
Sewage Storage Tunnel works.
.3
Works at Site 6 on Pit Road and Confederation pit parking lot is to be considered a local
road so traffic control is required at these locations as per MTO Book 7.
.4
Works at Site 6 including road or lane closures or reductions or large numbers of truck
deliveries causing disruption to the public shall be approved through the PWGSC
communique process as specified in 01117 Construction Sequences and Constraints.
.5
.2
.3
.6
Do not close any lanes of road without approval of the Contract Administrator. Before
re-routing traffic erect suitable signs and devices in accordance with instructions
contained in City of Ottawa SPG D-005.
.7
Provide a minimum 1.5m wide hard surface pedestrian path on at least one side of the
work corridor at all times in accordance with F-1013. Use temporary hot mix asphalt as
pedestrian path surface where feasible instead of granular surface when temporary path
is to be in place for an extended period of time (greater than 5 days). Cold patch is not
permitted.
.8
Keep travelled way graded, free of pot holes and of sufficient width for required number
of lanes of traffic.
.1
.9
.10
Place and compact granular sub-base in accordance with Section 02723 Granular Sub-Base.
.2
Place and compact granular base in accordance with Section 02721 - Granular
Base.
.3
Place and compact asphalt concrete pavement in accordance with Section 02743
- Asphalt Concrete Paving.
Refer to City of Ottawa SPG D-005 for more detailed and site specific requirements.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
PAGE 3 OF 51
.11
Undertake all traffic control works at Site 6 on PWGSC property in compliance with the
Parliamentary Precinct Branch Traffic Operation guidelines for long duration work.
Incorporate the document requirements in the requirements for the plans listed in 1.5.2.
.12
No vehicular movements are permitted to cross the Ottawa River Pathway while the
pathway remains open between the hours of 7:00AM -9:00AM, 11:30AM-1:30PM, and
3:00PM-6:00PM.
1.6
1.7
.1
1.8
.1
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
SUPPLEMENTAL INFORMATION
SPECIAL PROVISION GENERAL NO. D-005
TRAFFIC CONTROL PLAN S.P. NO: F-1010
POLICE ASSISTANCE AT INTERSECTION S.P. NO: F-1012
CONSTRUCTION SITE PEDESTRIAN CONTROL PLAN S.P. NO: F-1013
STEEL INTERLOCKING PEDESTRIAN BARRIERS S.P. NO: F-1014
PWGSC PARLIAMENTARY PRECINCT BRANCH: TRAFFIC OPERATION SAFE OPERATING
GUIDELINES
END OF SECTION
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 1 of 15
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 2 of 15
detour and, if required, the subsequent removal shall be performed at the Contractor's
expense. The detour shall be constructed and maintained to structural and geometric
standards approved by the Contract Administrator. Removal and site restoration shall be
performed as directed by the Contract Administrator.
10) Where, with the prior written approval of the Contract Administrator, the Highway is
closed and the traffic diverted entirely off the Highway to any other Highway, the
Contractor shall, at no extra cost to the Owner, supply, erect and maintain traffic control
devices in accordance with the OTM.
11) Compliance with the foregoing provisions shall in no way relieve the Contractor of
obligations for Protection of Work, Persons and Property, dealing with the Contractor's
responsibility for damage claims, except for claims arising on sections of Highway within
the Working Area that are being maintained by others.
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 3 of 15
Traffic Control Device(s) (TCD): A generic term used to describe any person,
sign, signal, marking or device placed upon, over or adjacent to a roadway by or
at the direction of a public authority or official having jurisdiction (such as the City
of Ottawa) or their designate, for the purpose of regulating, warning, guiding or
informing a vehicle operator or pedestrian of an existing condition or hazard.
TCD must conform to requirements of OTM Book 7 Temporary Conditions
Traffic Control Plan (TCP): A detailed plan for the control of traffic, including
vehicular, transit, cyclists and pedestrian movements, required to allow the
Contractor to fulfill all conditions of the contract, taking into account the
organized, systematic safe conduct of the project. This includes, as applicable,
detours, staging sequences, work zones, public and emergency vehicle access
and egress, public access and separation from hazardous areas, temporary
barriers, removal of old pavement markings, and the selection of appropriate
typical layouts and devices necessary for traffic control. The TCP is to be signed
by a Designated Person trained in the use of Book 7 and will be responsible for
implementation, maintenance and plan revisions as required for the execution of
the Work. A copy of the plan must be posted and maintained on site and
available at all times. Contractor must maintain document update, revising or
amending to reflect construction operations and staging.
Traffic Control Persons (TCPs): A person duly trained and authorized to direct
traffic at a work zone through the use of the Traffic Control Sign (STOP/SLOW
Paddle)
Traffic Protection Plan (TPP): A plan required by the Occupational Health and
Safety Act and its regulations for the protection of workers in a work zone. The
plan must contain a written description of the traffic hazards to which workers
may be exposed and measures used to protect them.
Traffic Management Plan (TMP): A requirement of the roadcut permit. TMP
means a standard outlining the particulars of proposed work on any highway
described on Schedule B of the Road Activity Bylaw that is submitted by or on
behalf of the Contractor to the City for approval. The traffic management plan
shall contain the information respecting how the applicant intends to comply with
this by-law including but not limited to the following:
a)
b)
c)
d)
e)
f)
g)
h)
i)
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 4 of 15
j)
Note: The TMP submitted should include a copy of D-005 and a statement
indicating that the TMP is in compliance with D-005. The TMP is to be copied to
both the Project Manager and Contract Administrator for review.
Traffic Operational Studies Officer: responsible for determining traffic
management requirements and strategies for construction/rehabilitation projects,
including road closures and detours on behalf of the Road Authority. Provides
comment on TCP submissions and revisions during construction phase.
Traffic Management Inspector: responsible for monitoring and enforcement of
City Road Activity Bylaw for safe and continuous passage of traffic, pedestrian,
transit and cyclist mobility on the Citys transportation network. Provides support
in the monitoring of construction activities for conformance to approved TCP and
Book 7 requirements on behalf of the Road Authority.
General Requirements
The Ontario Traffic Manual supersedes all reference in this contract document to
the Ministry of Transportation, Manual for Uniform Traffic Control Devices, or
MUTCD.
Prior to commencing any construction, on or adjacent to a City street, the supply
and placement of all necessary temporary traffic control devices shall be
performed under the sole direction of the Contractor and in accordance with the
Contractors submitted/reviewed Traffic Control Plan. The Traffic Control Plan
(herein the TCP) shall be developed in accordance with guidelines established
by the most recent version of the Ontario Traffic Manual, (herein the OTM) the
Occupational Health and Safety Act (herein the OHSA), and SP F-1010 which
details the required contents and submission of the TCP. Two (2) weeks prior to
commencing construction, the Contractor shall submit the Traffic Control Plan to
the Contract Administrator.
Vehicular and pedestrian traffic control shall remain the sole responsibility of the
Contractor as the City of Ottawa delegates this authority to the Contractor in
accordance with the submitted/reviewed Traffic Control Plan. Notwithstanding the
foregoing, the Contractor shall, at his own expense, remove any equipment or
material, which in the Contract Administrators opinion, constitute a hazard to
traffic or pedestrians, or an obstruction to City maintenance operations.
Contractor must address review comments provided by the City, to the
satisfaction of the City.
The Contractor shall be fully and solely responsible to ensure the development
and implementation of a submitted/reviewed TCP as required in SP F-1010. The
TCP and all required traffic control devices shall be designed/installed,
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 5 of 15
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 6 of 15
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 7 of 15
Transit Services
Access by buses and pedestrians to all existing Bus Stops in the work zone must
be maintained at all times, except where stated in the Contract. The Contractor
shall provide O.C. Transpo at least five (5) working days notice to coordinate
adjustments required to their facilities as a result of construction.
Should the Contractor require access to or impede access/egress of a
Transitway, application for access to the Transitway is required 72 hours before
access is required.
Current O.C. Transpo routes operating within the project limits are as follows:
Slater Street:
Nicholas Street:
Eastbound Transitway
Eastbound transitway vehicles will be utilizing
Nicholas Street (southbound)
Chamberlain Ave.: Route 101
Parking
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 8 of 15
The Traffic and Parking By-law allows for on-street parking at locations
throughout the contract limits, except where stated otherwise for residents.
The Contractor's employees must be advised that parking regulations on City
streets in the vicinity of the construction zone will be enforced and will be subject
to the Citys Parking By-Law. If the Contractor wishes its employees to park on
adjacent City roads, in contravention of the Traffic and Parking By-law,
application must be made to the City for an encroachment permit.
A designated safe parking area shall be specified in the Traffic Control Plan for
the Contract Administrator for the duration of the contract. This parking area
shall accommodate a minimum of 2 vehicles and reserved for City of Ottawa
contract administration staff.
The Contractor shall make no claim for the additional costs of obtaining an
encroachment permit or for any parking tickets issued to its employees.
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 9 of 15
All pavement markings are to be in compliance with all relevant OPS & City
standards.
The Contractor will be responsible for maintenance or to rectify any errors or
inconsistencies in the pavement markings to the satisfaction of the Contract
Administrator until final acceptance of the work.
This requirement will not be considered for separate payment unless the
applicable items are included in the schedule of prices. The inclusion of this item
is at the sole discretion of the Owner.
The Contractor shall not make any claim for extra compensation or delays to the
project for the impact this provision may have on the construction of the roadway
and related works.
Signalized Intersections
Notwithstanding other notification requirements contained in this specification,
where the Contract, or Contractor, is planning to modify an approach to a
signalized intersection beyond OTM Book 7 applications, a three (3) week
notification to the City of Ottawa Signal Operations is required. Signal
Operations will determine if a CADD drawing submission is required by the
Contractor.
Traffic Control Plans that include signalized intersections shall be submitted on
1:250 scale.
Location and Storage of Materials and Equipment Outside of the Work Zone,
only for roads with normal posted speed of 80 km/hr or greater
Materials and/or equipment shall not be stored outside of the work zone within
4.0 m of the traveled portion of any roadway except where a barrier curb is in
place in which case the minimum clearance required is 1.0 m.
Notwithstanding the foregoing, the Contractor shall, at the Contractor's expense,
remove any vehicle, equipment or material, which, in the opinion of the Contract
Administrator, constitutes a hazard to traffic or pedestrians, or an obstruction to
City maintenance operations.
Contract Specific Requirements
In determining the expected traffic and pedestrian operations for the site, the
Contractor is advised of the following requirements that shall apply to this
Contract:
Advanced Notification Assistance and City Contract Sign
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 10 of 15
Pursuant to this contract the Contractor will provide the following devices to be
factored into the Contractors TCP.
Portable Variable Message Signs (PVMS) will be used as an advance notification
device for one week prior to the construction start date and for the duration of the
construction. Eight PVMS signs suitable for an urban setting shall be made
available for use during the project.
PVMS signs shall be located (or at locations as otherwise directed by Contract
Administrator)at:
Slater and Kent
Intersection:
Adjacent to Slater Street on the north side boulevard
facing eastbound traffic.
Adjacent to Kent Street south of Slater Street.
Location to be determined.
RCI-CSST
Chamber:
Cumberland
Access:
Adjacent to Cumberland Street between St. Patrick
Street and Murray Street on east side boulevard
facing northbound traffic.
McLeod Street:
Westbound at Kent Street.
Catherine Street: Westbound east of Kent Street
Chamberlain Ave.: Eastbound east of Kent Street ramp
The Contractors TCP shall identify appropriate traffic control devices that will be
required to protect these signs from creating a hazardous condition.
Lane Closures:
Where construction pursuant to this Contract will require temporary lane
closures, the lane closures shall be carried out by the Contractor at the
Contractors expense. The Contractor shall give forty-eight (48) hours notice to
the Contract Administrator prior to the day on which the lane closures will be
required.
Construction Operations - Impact on Open Lanes
As traffic and mobility are a priority for the City, construction activities such as
loading and unloading of materials/construction equipment, flagging, etc., onto
and from the traveled portion of the roadway shall be undertaken or staged in
accordance with applicable provisions of the contract and outside peak period
\Section D\D-005 April 3, 2014
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 11 of 15
Minor interruption
Uninterrupted
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 12 of 15
peak period*
Lanes
(#)
per lane
With Transit
operations
Arterial
peak period*
per lane
$1000
minute
none
peak period*
per lane
$500
5 minutes
every 15
minutes
With Transit
Operations
Collector
peak period*
per lane
$500(x1.5) 5 minutes
peak period*
per lane
$500
every 15
minutes
every 30
minutes
With Transit
Operations
Transit Priority
4 Lane**
peak period*
per lane
$500(x1.5) 10 minutes
peak period*
per lane
$1000
Value
($)
$1000
Frequency
Escalation****
minute
none
10 minutes
minute
every 30
minutes
None
Notes
*Peak period - as identified in contract conditions
**Contractor may trade off a general lane and Transit lane with appropriate TM set up
and TM staff approval
***Classification as identified in the OP/TMP
**** Double the previous value applied
Slater Street = arterial with transit operations
Documentation
For each deviation, the Contract Administrator will provide the Contractor with a
written notice via a Site Communication Memo which will indicate the date and
time of infraction with the appropriate calculations. Depending on the frequency
and nature of the impacts, other actions may be considered if escalated by the
Contract Administrator.
Monetary penalties imposed by the Contract Administrator as determined to be
non-performance related will be deducted from the Traffic Control item.
Road Closures
Where construction pursuant to this Contract will require road closures, the road
closure shall be carried out by the Contractor at the Contractors expense. The
Contractor shall apply for a road closure permit from the City of Ottawa and
\Section D\D-005 April 3, 2014
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 13 of 15
comply with all requirements of the permit prior to closing the road. In addition,
the road closure must be identified in the TCP.
Traffic Flows
AADT traffic volumes (recent City of Ottawa counts) are identified for impacted
roadways below:
Slater Street:
8,000
Kent Street (at Slater):
10,000
Nicholas Street (southbound):
12,000
Cumberland Ave. (northbound): 4,500
Cumberland Ave. (southbound): 1,200
Stanley Ave.
800
Kent Street (at Catherine)
16,000
Catherine Street
9,500
Chamberlain Avenue
10,000
Additional Traffic Control measures accepted for this contract will include
The Contractor is advised of the following traffic control measures will apply to
this contract.
Slater Street: Lyon Street to Bank Street
AM (7:00am 9:30am), PM (3:30pm 6:00pm)
o Maintain one eastbound through lane.
o Maintain one dedicated eastbound Transit lane.
o Maintain one eastbound left turn lane at Kent St.
o Maintain one eastbound right turn lane Bank St.
Queen Elizabeth Drive and Lawrence Freiman Lane:
Maintain one lane in each direction during the weekday AM (7:00am
9:30am) and PM (3:30pm 6:00pm).
Cumberland Street: George Street to Clarence Street
Maintain a minimum of one lane in northbound during the weekday AM
(7:00am 9:30am) and PM (3:30pm 6:00pm) peak periods
Maintain a minimum of one lane northbound at all other times
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 14 of 15
Close Mcleod Street to west bound traffic from Kent Street. Provide
westbound detour of traffic via Kent St Gladstone Ave and Lyon St.
Convert Mcleod Street from Lyon Street to west of Kent Street to 2-way
traffic.
Open McLeod Street to One lane of traffic from Kent St. to Lyon Street
upon substantial completion of backfilling operations.
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
April 2015
Page: 15 of 15
The City shall be responsible during construction to remove, install or modify any
necessary regulatory signage due to the requirements of the Traffic Control Plan.
The Contractor shall notify the Contract Administrator ten (10) calendar days
prior to this requirement. Temporary regulatory signage shall be provided and
installed by the City, as necessary.
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
S. P. No: F-1010
Date: March 2008
Page: 1 of 3
TRAFFIC CONTROL PLAN
1.0 Scope
The Scope of the work addressed in this specification Traffic Control Plan shall
include the preparation and submission of a Traffic Control Plan (TCP) as outlined in this
specification and in Special Provision General D-005.
Where construction pursuant to this Contract is being carried out on or adjacent to a City
street, the supply, placement, monitoring, and disassembly of all traffic control devices
shall be performed under the direction of the Contractor in accordance with the Ontario
Traffic Manual latest edition.
The Contractor shall be responsible for construction means, methods, techniques,
sequences, and procedures and for coordinating the various parts of the traffic control.
The Contractor shall prepare and submit a Traffic Control Plan that details the specific
traffic control layout(s), necessary for the completion of the works. The Traffic Control
Plan shall be in the form of drawing(s) and written description(s) of how the Contractor
intends to control traffic through and around the work zone. The TCP shall include, and
not necessarily be limited to:
Monitoring and Repair (24 hour contact number if not acquired)
Reference to Applicable OTM Book 7 Typical Layouts
Traffic control signs (regulatory, warning and temporary);
Traffic control delineation;
Traffic Control vehicles and devices (TC-12, Crash Trucks, Temporary Lighting
etc.)
Contract-specific operational requirements;
Night time requirements
Traffic staging and scheduling;
Construction vehicle access/egress;
Public access/egress for all existing entrances and side roads
Pedestrian safety; barriers and barricades;
Emergency Vehicle access
Locations for removal of existing line painting and proposed temporary pavement
markings;
Parking for Contract Administrator
Any other traffic control measures.
The Contractor shall refer to D-005 and other Special Provision-General for general and
contract specific requirements of traffic operations, and definition of terms.
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
S. P. No: F-1010
Date: March 2008
Page: 2 of 3
TRAFFIC CONTROL PLAN
In addition to the Traffic Control Plan, the Contractor is advised that a Traffic
Management Plan is required for any construction project within a City of Ottawa rightof-way in order to obtain a road-cut permit. The Traffic Management Plan is not part of
the scope of this Special Provision.
2.0 Submissions, Monitoring, and Repair
Two (2) weeks prior to commencing construction, the Contractor shall submit the Traffic
Control Plan to the Contract Administrator. The Contractor acknowledges that revisions
to the Traffic Control Plan may be necessary, in consultation with the City, where it
concerns public safety and mobility. For signalized intersections the Plan shall be
submitted on a 1:250 scale.
The Contractor shall ensure that all workers, including sub-contractors, in the Working
Area are aware of the importance of the Traffic Control Plan measures.
The Contractor shall be required to review and modify the TCP for errors, omissions,
deficiencies, or because of any new hazards are identified and not previously addressed
within the document.
The condition of all traffic control devices shall be maintained for the duration of the
contract, in accordance with the OTM.
The Contractor shall immediately repair, replace or otherwise make good the practice
deemed unsafe or non-compliant when the owner (or his delegated authority) makes the
Contractor aware of any violation of the TCP (or applicable regulations). Should the
Contractor disagree, the Ministry of Labour will be consulted to provide clarification of
the observed deficiency.
It is the responsibility of the Contractor to ensure that all necessary training has been
provided prior to commencement of the work.
The City of Ottawa through the Project Manager will accept the submission of the TCP,
and review it to identify any errors, omissions, or improvements that the City staff is
aware of, as it relates to maintaining public safety and mobility.
The acceptance and review of the TCP by the City will make no representation and/or
warranty that the document is accurate, complete, or compliant with all applicable
legislation. Any errors, omissions or deficiencies within the TCP will remain the sole
responsibility of the Contractor. The contract shall not commence, until the City has
reviewed the TCP to the satisfaction of the Citys Contract Administrator, and the
Contractor has addressed all comments
Section F\General\F-1010 March 31, 2008
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
S. P. No: F-1010
Date: March 2008
Page: 3 of 3
TRAFFIC CONTROL PLAN
The Contract Administrator reserves the right to ask for revisions to the Traffic Control
Plan at submission time, or reject it if the Plan does not meet the Contract language. In
addition, the Contract Administrator reserves the right to instruct the Contractor to revise
it at any time during the Contractors execution of the plan, when the Contract
Administrator finds that the Contractor is not providing the commitments shown in the
original Traffic Control Plan submission, or the Contractors Traffic Control Plan proves
to be insufficient to address the field conditions.
3.0 Basis of Payment
Payment at the contract Lump Sum Price for the item Traffic Control Plan shall be full
compensation for the research, preparation and implementation of the TCP, and shall
include all labour, equipment and material to supply, and maintain all traffic control
measures detailed therein. This payment includes supply, installation, monitoring,
operation, maintenance and removal of all required traffic control devices.
Traffic Control Persons (TCPs) shall not be included for payment under this item. The
Contractor shall include any costs associated with TCPs in the applicable item where
TCPs are required.
This item shall not include the cost for removing existing pavement marking and
temporary line painting
Payment shall be based upon the following schedule:
a) 25% upon satisfactory submission of the TCP and installation of the control
measures; and,
b) 75% pro-rated into equal payments over the term of the contract.
This payment schedule may only be modified as agreed upon in writing between the
Contractor and the Contract Administrator.
WARRANTS: On all Contracts involving vehicular and/or pedestrian traffic.
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Scope
The Scope of the work addressed in this specification Construction Site Pedestrian
Control Plan shall include the preparation and submission of a Construction Site
Pedestrian Control Plan (CSPCP) as outlined in this specification and in Special
Provision General D-005, along with all labour, equipment, and material required to
implement the CSPCP.
The Construction Site Pedestrian Control Plan shall ensure the provision of a safe and
accessible path of travel for all pedestrians through and/or around the construction
site. The plan shall ensure that pedestrians with disabilities, as well as those with
increased mobility needs (parents with strollers and/or young children, elderly
pedestrians using canes, walkers, or wheelchairs, etc.), shall be accommodated either
through or around the construction site.The scope of the work addressed in CSPCP
will include temporary pedestrian signing; directional signing; maintenance of sidewalk;
relocation, maintenance, and removal of pedestrian barriers; and all necessary
delineation or any other measures to provide a safe environment for pedestrians.
Staging of the Work
The work shall be staged in a manner consistent with the staging of the Contract and
in accordance with the implementation of the traffic control measures as stipulated in
the Contractors Traffic Control Plan. When determining the staging of the Contract,
the Contractor shall maintain existing sidewalk facilities for as long as possible.
Removal of any existing sidewalk facilities, or portion thereof, shall not be permitted
until permission has been granted by the Contract Administrator.
Pedestrian Facilities
Regardless of whether or not there is an existing sidewalk within the right-of-way, a
minimum 1.5m wide pedestrian facility shall be provided along at least one side of the
corridor at all times. The facility shall include a free and unobstructed hard surfaced
pedestrian surface acceptable for use by all pedestrians, including those with
disabilities, and shall include pedestrian access to all buildings and street crossings.
The facility shall be maintained clean and in a good state of repair to the satisfaction of
the Contract Administrator, through or around the construction site at all times. The
1.5m width shall not be reduced by protruding objects. If overhead works are required
a 2.1m clear headroom shall be provided along the entire 1.5m width.
Any change of level which is over 13mm height must be provided with a smooth, nontripping transition.
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Basis of Payment
Payment at the contract Lump Sum Price for the item Construction Site Pedestrian
Control Plan shall be full compensation for the research, preparation and
implementation of the CSPCP, and shall include all labour, equipment and material to
supply, and maintain all pedestrian control measures detailed therein. This payment
includes supply, installation, monitoring, operation, maintenance and removal of all
required pedestrian control devices.
Payment shall be full compensation for all labour, equipment, and material required to
do the work.
If they are included in the schedule of prices, the following items shall be
considered for separate payment:
Pedestrian Barriers
Granular A or Stone Dust for temporary pedestrian facility
Temporary hot mix asphalt for temporary pedestrian facility
For each of these items, no area shall be measured for payment more than once per
each linear side of the construction site corridor. For example, if the Contractor stages
the work such that they use temporary hot mix asphalt to construct a temporary
pedestrian facility three (3) separate times along one side of the street, and not at all
along the opposite side of the street, the maximum payment shall be for the
construction of two (2) of the temporary facilities.
Note to designer: If it seems necessary, due to the anticipated staging required to
construction the work, to use any of the above three items, then insert into the
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
This procedure is to be followed by all parties on Parliament including, but not limited to; The
House of Commons of Canada, The Senate of Canada, National Capital Commission, The
Library of Parliament and any contractor engaged in work on Parliament Hill.
4.0 LIST OF ATTACHMENTS, ANNEXES AND/OR TABLES
Parliament Hill map of one way and two way streets
Pictograms of typical traffic control set ups
Examples of Traffic Control Operations
5.0 KEY DEFINITIONS
competent worker, in relation to specific work, means a worker who,
(a) is qualified because of knowledge, training and experience to perform the work,
(b) is familiar with the Occupational Health and Safety Act and with the provisions of
the regulations that apply to the work, and
(c) has knowledge of all potential or actual danger to health or safety in the work;
highway means a common and public highway, street, avenue, parkway, driveway,
square, place, bridge, viaduct or trestle, any part of which is intended for or used by the
general public for the passage of vehicles;
Page 1 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
public way means a highway or other street, avenue, parkway, driveway, square, place,
bridge, viaduct, or other open space to which the public has access, as of right or by
expressed or implied invitation;
roadway means the travelled portion of a highway;
vehicle means a vehicle propelled by mechanical power and includes a trailer, a traction
engine and a road-building machine;
Duration of work is a major factor in determining the number and type of signs and
devices to be used in temporary work zones. This is defined in (4) subcategories;
Mobile Operations (MO) is work done while moving continuously with periodic stops
related to the mobile activity. The warning devices, signs and traffic control persons moves
with the activity area. Examples include, but not limited to; line painting, road sweeping, snow
clearing, etc.;
Very Short Duration Work (VSD) occupies a fixed location for up to 30 minutes, including
setup and take down. The work area may be moved along the road and make frequent, short
stops. If a short stop must be made at a specific location, it is VSD work, not MO. Examples
include, but not limited to; Utility work, minor road maintenance, pothole patching, surveying,
deliveries and catch basin cleanout work;
Short Duration Work (SD) refers to stationary activities which require a separate
continuously occupied work space and are more than 30 minutes and less than one-24 hour
period in duration. SD work does not typically include work longer than 24 hours, such as long
duration work;
Long Duration Work (LD) work refers to stationary activities which require a separate work
space for longer than 24 hours;
Page 2 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
7.0 A. ENQUIRIES (FOR PUBLIC WORKS AND GOVERNMENT SERVICES CANADA ONLY)
Travis Ford, Construction Health and Safety Coordinator, 613-957-1169
Travis.Ford@tpsgc-pwgsc.gc.ca
Tim Beauregard, Construction Health and Safety Coordinator, (613) 957-8343
Tim.Beauregard@tpsgc-pwgsc.gc.ca
7.0 B. ENQUIRIES (FOR NATIONAL CAPITAL COMMISSION ONLY)
XXXXXXXXXXXXXXXXXXXXXXXXXXXXX
8.0 PROCEDURE
8.1 PWGSC Departmental Representative must complete a hazard assessment based on
the scope of work, prior to tender;
8.2 PWGSC Departmental Representative must ensure the contract documents include
any special provisions identified in the hazard assessment based on the scope of
work;
8.3 The contractor shall prepare a hazard assessment and site specific safety plan,
outlining the anticipated and known hazards, complete with the contractors
mitigating measures;
8.4 Where the contractors work involves working on any public way in Parliamentary
Precinct, the specific measures and procedures must be accurately reflected in the
contractors hazard assessment and site specific safety plan. Work must not
commence until this is complete;
8.5 All provincial contractors shall comply with the Occupational Health and Safety Act
in the province of Ontario, particularly Parliamentary Precinct;
8.6 Where PWGSC employees perform work on a public way in Parliamentary Precinct,
they shall comply with the Canada Labour Code Part 2 and the Occupational Health
and Safety Regulations, Treasury Board guidelines, PWGSC Departmental Directives
for Health and Safety, Occupational Health and Safety Act in the province of Ontario
and any municipal laws or statutes applicable to the work;
8.7 Where work must occur on a public way where traffic is present within Parliamentary
Precinct, all PWGSC and contractor employees shall wear high visibility traffic vests/
apparel/clothing;
Page 3 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
8.8 As a minimum, any short duration work and long duration work on a public way in
Parliamentary Precinct where there is 2-way vehicular traffic, at least (2) traffic
control persons shall be present to direct vehicular traffic and the public;
8.9 As a minimum, any short duration work and long duration work on a public way in
Parliamentary Precinct where there is 1-way vehicular traffic, at least (1) traffic
control person shall be present to direct vehicular traffic and the public;
8.10 For mobile operations and very short duration work, 360 degree flashing lights, 4way hazard markers, traffic cones and a combination of barriers, delineators and
caution tape must be considered as the minimum. The departmental representatives
hazard assessment, Occupational Health and Safety Act and Ontario Traffic Control
Manual Book 7 Temporary Conditions will dictate the required devices and signs as
per the scope of work;
8.11 Parked or stationary vehicles and equipment for performing work must be
enclosed by fencing. Where this is not reasonably practicable, a combination of traffic
cones, caution tape, barriers, delineators, flashing devices, signs and/or traffic control
persons must be put in place in accordance with the Occupational Health and Safety
Act and Regulations for Construction Projects, the Ontario Traffic Control Manual
Book 7 Temporary Conditions and the hazard assessment;
8.12 The following pictogram examples are basic examples of the requirements for 1way traffic and 2-way traffic on a public way. The map of Parliament Hill also shows
where the 1-way traffic and 2-way traffic are normally in place. The pictures of
various traffic control set ups are also provided to show examples of what is expected
and what is considered not acceptable;
Page 4 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Page 5 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Page 6 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Page 7 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Good Example # 1
Comments:
-Well defined layout
-Good distance from the traffic to the outriggers of the crane and operator to access the truck
Page 8 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Good Example # 2
Comments:
-Good layout
-Highlighted fence (flashing beacons) around the corner for turning vehicles
Page 9 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Good Example # 3
Comments:
-Total access is blocked during the hoisting
Page 10 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Good Example # 4
Comments:
-Short term work
-Adequate visual separation to keep public and buses away from the vehicle
-Work area on the wall (right side) is barricaded
Page 11 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Good Example # 5
Comments:
-Adequate for short duration work
-Fencing would be the best option, especially if the zone is breached by the public at any time
Page 12 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Good Example # 6
Comments:
-Adequate short duration work
-Public access signage (arrows pointing to the left) would assist in communicating the intended walking
route options
-Sidewalk is still open on the left side
Page 13 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Good Example # 7
Comments:
-Well defined layout
Page 14 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Good Example # 8
Comments:
-Total access is blocked during the hoisting
-Fencing placed at the pedestrian crosswalk to ensure safe passage
-Fence legs highlighted with traffic cones
Page 15 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Good Example # 9
Comments:
-Equipment completely enclosed from the public with barricades
Page 16 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Comments:
-Uneven walking surface
-Poorly defined construction area and pedestrian area
-No flag person(s)
Page 17 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Comments:
-Unauthorized parking
-Water truck not using traffic cones on the truck and set up at the narrowest part of the road
-No flag person(s)
-Two way traffic on a blind curve
-Plenty of public
Page 18 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Comments:
-Short traffic cone layout doesnt create sufficient taper zone
-Flag person on the wrong side of the equipment and no STOP/SLOW sign
-Pedestrians are forced to cross at the equipment rather than at cross walks
Page 19 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Comments:
-Good traffic cones and signs
-Poorly placed pedestrian sign as pedestrians are forced to cross at the equipment rather than at cross
walks
-Limited traffic cone distance for the truck operator to access equipment
-Vehicles within the traffic cones are the contractors own forces
Page 20 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
Comments:
-The activity would be best performed off hours
-No signs, cones or flashing devices for this Mobile Operation
-Blind spot over the Hill and at a cross walk for construction workers
Page 21 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
SECTION 01353
SPECIAL PROCEDURES: TRAFFIC CONTROL
ATTACHMENTS
9.0 APPROVAL
(Approved by the senior most person responsible for those to whom this procedure applies)
Title
Name
Date
YYYY/MM/DD
xx / xx / xxxx
Approved by:
Title
Name
Date
YYYY/MM/DD
Page 22 of 22
NCA-#1575447-v2-Traffic_Protection-Safe_Operating_Guideline-PPB
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01355
DISPOSAL OF EXCESS MATERIAL
PAGE 1 OF 7
This section includes procedures for re-use or dispose of excess material as a result of
excavation of the tunnels, shafts and chambers and construction of final structures for the
Project.
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
1.3
REFERENCES
.1
OPSS 180 General Specification for the Management and Disposal of Excess Material
.2
.3
Environmental Protection Act, R.S.O. 1990, c. E. 19, Ontario Regulation 153/04, Records
of Site Conditions - Part XV.I of the Act, as amended
.4
Management of Excess Soil A Guide for Best Management Practices, prepared by the
MOECC, dated January 2014.
.5
.6
.7
.8
1.4
Management and disposal of excess materials shall conform to the requirements of OPSS
180, except as may be amended and extended herein.
.2
These requirements do not relieve the Contractor of its obligations imposed by the
Contractors Certificate of Approval for a Waste Management System or any municipal,
provincial or federal legislation.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
1.5
SECTION 01355
DISPOSAL OF EXCESS MATERIAL
PAGE 2 OF 7
Measurement for Payment sections and Basis of Payment sections of OPSS references
are deleted in their entirety.
NOTIFICATION TO THE MINISTRY OF THE ENVIRONMENT
.1
.2
1.6
.1
Submit a Groundwater, Soil and Rock Management Plan and Waste Disposal Plan a
minimum of 30 days prior to start any excavation. This plan is separate from the plans
required as part of Section 02140 Groundwater Control. The plan is to be provided to
the NCC and PWGSC where work takes place on their property. The plan shall include as
a minimum the following:
.1
.2
.3
.4
Identify the testing frequency and parameters for excess soil materials. The
Contractor shall assume a minimum testing frequency of one sample for every
500m3 of materials excavated for tunnel muck and one sample for every 200 m3
of excavated soil;
.5
Identify areas where soil segregation is known to be required (i.e. upper fill to be
removed first);
.6
.7
Procedure for stockpiling and testing when suspected impacted materials are
identified;
.8
.9
.10
.11
Permission for disposal from the Owner of the fill and waste receiving site;
.12
.13
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.14
.15
1.7
SECTION 01355
DISPOSAL OF EXCESS MATERIAL
PAGE 3 OF 7
Material recycling plan including the location and details of the proposed
recycling facility planned to accept the material. The recycling facility is to be a
licensed Waste Management Facility and be approved by the Contract
Administrator.
Letter of Release from the Owner of the disposal site at the completion of the
project.
1.8
.1
Excavated soil that meets the geotechnical requirements and Standards in O. Regulation
153/04 as amended, can be considered suitable for reuse on site within the Project site
bounds. Material that meets Table 1 Standards can be reused within the Project site
bounds. Material that meets Table 2 Standards can only be reused on-site at locations
which generated the material and similarly, material that meets Table 3 Standards can
only be reused on-site at locations which generated the material. Permission for material
reuse must be provided by the Contract Administrator in advance.
.2
Sampling and testing of soil or crushed rock of a size considered to be a soil shall be
executed to determine if material meets the quality standards provided in Table 1 to 3 of
the Ontario Standards. Sampling and testing of water extracted from rock shall be as per
Section 02140 Groundwater Control. Testing of the material must be completed by a
laboratory with internationally recognized accreditations and the analytical procedures be
in accordance with O. Regulation 153/04.
.3
The Contractor shall retain a Qualified Person (QP) (in accordance with O. Regulation
153/04) and geotechnical/environmental consultant to complete material testing,
sampling and provide direction to the Contractor on soil and groundwater management
for the duration of the Contract.
.4
The Contractors QP shall complete visual inspection of material to be reused within the
Project site to confirm that the material is free of contaminant staining, free product,
olfactory evidence of environmental contamination, contaminant sheen, or deleterious
materials of anthropogenic origin (i.e. debris) on a daily basis.
.5
The reuse of rock material on-site shall be in such a manner as to prevent or eliminate the
potential for material to become a contaminant in the environment, cause or have the
potential to cause an adverse effect (as defined by Ontario Environmental Protection
Act).
.6
All material that cannot be reused within the Project site bounds shall be dispose off-site.
1.9
All materials designated to be removed from the site must be promptly removed.
Stockpiling of materials at any time on site shall be avoided except as allowed due to
haulage restrictions. Temporary stockpiles to manage in accordance with MOECC excess
soil handling best practices to eliminate or mitigate potential for release of muck to the
environment such that it causes or may cause an adverse effect as defined by the Ontario
Environmental Protection Act.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01355
DISPOSAL OF EXCESS MATERIAL
PAGE 4 OF 7
recycling centres to be used. Follow all applicable local and provincial waste reduction
guidelines.
.3
Remove unwanted material, as classified by the City or Contract Administrator, from the
site and dispose of same at acceptable sites outside of the worksite.
.4
.5
Off-site disposal of muck to a registered landfill must be in accordance with Reg. 347, as
amended. A copy of Waste Management System or Waste Disposal Site Environmental
Compliance Approvals (ECAs) shall be supplied to the Contract Administrator prior to
transporting excavated material.
.6
Offsite disposal of excess soil to sites other than a registered landfill sites must
be classified in accordance with O. Reg. 153/04. Disposal of soil at sites other than
registered landfill sites must be in accordance with the MOECCs Guide on Management
of Excess Soil (MOECC, 2014). The Contractor shall confirm that the receiving site is
operating under the MOECCs Guide and has in place a Fill Management Plan.
.7
1.10
Areas with anticipated contaminated soil and/or groundwater are identified in the GBR
and ESA Report.
.1
At sites identified in the GBR and ESA as having potential for contamination,
excavated material is to be tested and characterized to confirm whether it meets
or exceeds MOECC Tables 1, 2 and 3 Standards. Material exceeding MOECC
Table 3 standards on NCC and PWGSC property are to be hauled off site and
disposed of at an MOECC-approved landfill suitable for disposal of this material.
.2
Material shall be tested at a minimum for BTEX, PHCs, VOCs, PAHs, and
metals, and TCLP shall be performed as required by landfill.
.3
.2
.3
Water can also be removed from the site should rainfall events prevent
the ability to pump groundwater into the existing combined sewer system
or an alternate receiver if it does not exceed City of Ottawa sewer use
bylaws. It is anticipated that the sewer use agreement, to be obtained by
the Contractor from the City of Ottawa, will contain restrictions which
will preclude or limit the pumping of groundwater to existing sewers
during wet weather or during any other event which could result in
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01355
DISPOSAL OF EXCESS MATERIAL
PAGE 5 OF 7
.2
.3
The Contractor shall not be entitled to claim for delay to the Contract Work due to
meeting the requirements of this specification.
.4
In accordance with regulations under the Occupational Health and Safety Act, R.S.O.
1990, c.0.1, as amended, the City advises that:
.1
The designated substances silica, lead and arsenic are generally present
throughout the Working Area occurring naturally or as a result of vehicle
emissions;
.2
.3
.4
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.11
SECTION 01355
DISPOSAL OF EXCESS MATERIAL
PAGE 6 OF 7
All costs related to sampling, testing, handling, stockpiling, sorting, screening, onsite reuse, hauling, offsite disposal, and/or treatment/storage of contaminated soil are deemed to
be included in the total contract price of the contract or associated bid item based on the
information in the aforementioned reports and on the Contractors proposed methods of
construction for the works following the requirements of the Contract Documents.
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
APPLICATION
.1
Materials that are surplus and required to be removed from site for disposal or reuse must
be tested in accordance with O. Regulation 153/04, O. Regulation 347 as amended
(including guidance) or receiving site requirements under the MOECC Soil BMP to
determine management options. Generally, material less than 2mm in size or passing the
U.S. #10 sieve is classified as soil and is governed by the aforementioned regulations and
guideline. Rock is material 2mm or more in size not passing the U.S. #10 sieve.
Collection and sampling of soil shall follow the procedures referenced in O. Regulation
153/04. Contaminants of concern selection should consider full suites of analysis for
assessment against O. Regulation 153/04 and any additional analytical parameters as may
be necessary based on the Contractors QP assessment of the area. If material is to be
reused at an RSC Property (as defined in O. Regulation 153/04) then sampling frequency
shall be as defined in O. Regulation 153/04. If material is to be reused at a site governed
by Certificate of Property Use then procedures shall be as defined in the Certificate of
Property Use.
.2
All materials which are removed from the Project site as soil shall be managed in
accordance with the Management of Excess Soil - A Guide for Best Management
Practices, prepared by the MOECC, dated January 2014. The soil shall be characterized
by the Contractors QP, or a person under the supervision of the Contractors QP, to
determine the volume and chemical composition that is to be managed off-site. The soil
shall be transferred to the receiving site in accordance with the receiving site
requirements which may include documentation with appropriate and representative
analysis signed by the Contractor QP. Excess soil shall not be commingled with waste at
the source and shall be segregated and directly transported to the receiving site.
.3
All materials which are removed from the Project site as rock shall be managed in
accordance with O. Regulation 347. The reuse of rock material on-site shall be in such a
manner as to prevent or eliminate the potential for material to become a contaminant in
the environment, cause or have the potential to cause an adverse effect (as defined by
Ontario Environmental Protection Act)
.4
.5
Offsite disposal of excess soil to sites other than a registered landfill sites must
be classified in accordance with O. Reg. 153/04. Disposal of soil at sites other than
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01355
DISPOSAL OF EXCESS MATERIAL
PAGE 7 OF 7
registered landfill sites must be in accordance with the MOECCs Guide on Management
of Excess Soil (MOECC, 2014). The Contractor will confirm that the receiving site is
operating under the MOECCs Guide and has in place a Fill Management Plan.
.6
.7
The Contractor shall notify the Citys representatives and the MOECC immediately on
the discovery of any contaminated material encountered within the Project limits.
.8
Rubbish and waste material is not to be buried on site and must be disposed of at an
MOECC certified landfill as above.
.9
.10
Carry out additional chemical analysis of site materials and determine applicable
MOECC Regulations and Guidelines as may be required to determine the environmental
quality of materials encountered and to determine suitable means for transportation and
ultimate disposal. Notify the Contract Administrator of concerns and provide copy of test
results. Load shall be regarded as unclassified until tested.
.11
If required, the Contractor will coordinate with the Contract Administrator to obtain the
MOECC generator registration number through Hazardous Waste Information Network
and waste class number, and will coordinate with the Contract Administrator the required
documentation. If requested by the Contract Administrator, the Contractor will deactivate the generator registration number at the completion.
.12
Weigh bills, bills of lading, waste manifests, receiving site confirmation of receipt or
other material receipts, analytical results and other applicable documentation must be
provided to the Contract Administrator confirming that excess material site and
quantities are in accordance with requirements of the receiving site. For each site used,
submit an OPSF 180-2 at least two weeks prior to the usage of any disposal site. Submit
OPSF 180-3 immediately upon the completion of the Work or if that site is no longer
being used.
3.2
CLEANING
.1
Remove tools and waste materials on completion of Work, and leave work area in clean
and orderly condition.
.2
.3
.4
Take all materials that can be recycled to recycling facilities approved by Contract
Administrator and MOECC to accept these materials.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
ASSOCIATIONS
SECTION 01420
REFERENCES
PAGE 1 OF 3
.1
AA - Aluminum Association, 900 19th Street N.W., Washington, D.C., U.S.A. 20006
URL http://www.aluminum.org
.2
.3
AMCA - Air Movement and Control Association Inc., 30 West University Drive,
Arlington Heights, Illinois, U.S.A. 60004-1893 URL http://www.amca.org
.4
ANSI - American National Standards Institute, 25 West 43rd Street, 4th Floor, New
York, New York, U.S.A. 10036 URL http://www.ansi.org
.5
API - American Petroleum Institute, 1220 L St. Northwest, Washington, D.C., U.S.A.
20005-4070 URL http://www.api.org
.6
ARI - Air Conditioning and Refrigeration Institute, 4100 N Fairfax Drive, Suite 200,
Arlington, Virginia, U.S.A. 22203 URL http://www.ari.org
.7
.8
.9
ISAP - International Society for Asphalt Paving, 400 Selby Avenue, Suite 1, St. Paul,
MN 55102 U.S.A. URL http://www.asphalt.org
.10
ASTM - American Society for Testing and Materials, 100 Barr Harbor Drive West,
Conshohocken, Pennsylvania 19428-2959 URL http://www.astm.org
.11
AWPA - American Wire Producer's Association, 801 N Fairfax Street, Suite 211,
Alexandria, VA U.S.A. 22314-1757 URL http://www.awpa.org
.12
AWS - American Welding Society, 550 N.W. LeJeune Road, Miami, Florida U.S.A.
33126 URL http://www.amweld.org
.13
.14
CCA - Canadian Construction Association, 75 Albert St., Suite 400 Ottawa, Ontario,
K1P 5E7 URL http://www.cca-acc.com
.15
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01420
REFERENCES
PAGE 2 OF 3
.16
CISC - Canadian Institute of Steel Construction, 201 Consumers Road, Suite 300,
Willowdale, Ontario M2J 4G8 URL http://www.cisc-icca.ca
.17
CNLA - Canadian Nursery Landscape Association, RR #4, Stn. Main, 7856 Fifth Street,
Milton, Ontario. L9T 2X8 URL http://www.canadanursery.com
.18
.19
CSC - Construction Specifications Canada, 120 Carlton Street, Suite 312, Toronto,
Ontario M5A 4K2 URL http://www.csc-dcc.ca
.20
CSSBI - Canadian Sheet Steel Building Institute, 652 Bishop St. N., Unit 2A,
Cambridge, Ontario N3H 4V6 URL http://www.cssbi.ca
.21
CWC - Canadian Wood Council, 1400 Blair Place, Suite 210, Ottawa, Ontario K1J 9B8
URL http://www.cwc.ca
.22
EC - Environment Canada, Conservation and Protection, Inquiry Centre, 351 St. Joseph
Blvd, Hull, Qubec KIA 0H3 URL http://www.ec.gc.ca
.23
EFC - Electro Federation of Canada, 5800 Explorer Drive, Suite 200, Mississauga,
Ontario L4W 5K9 URL http://www.electrofed.com
.24
EIMA EIFS Industry Manufacturer's Association, 3000 Corporate Center Drive, Suite
270, Morrow, Georgia U.S.A. 30260 URL http://www.eima.com
.25
ESA Electrical Safety Authority, 155 Matheson Blvd West, Mississauga, ON L5R 3L5
http://www.esasafe.com/
.26
FCC - Fire Commissioner of Canada, Place du Portage, Phase II, 165 rue Hotel de Ville,
Hull, Quebec K1A 0J2 http://info.load-otea.hrdc-drhc.gc.ca/fireprevention/standards/commissioner.shtml
.27
IHSA Infrastructure Health & Safety Association, 5110 Creekbank Road, Suite 400,
Mississauga, Ontario L4W 0A1 Canada http://www.ihsa.ca/
.28
MPI - The Master Painters Institute, 4090 Graveley Street, Burnaby, BC V5C 3T6 URL
http://www.paintinfo.com
.29
MSS - Manufacturers Standardization Society of the Valve and Fittings Industry, 127
Park Street, N.E., Vienna, Virginia U.S.A. 22180-4602 URL http://www.mss-hq.com
.30
.31
NABA - National Air Barrier Association, PO Box 2747, Winnipeg, Manitoba R3C 4E7
URL http://www.naba.ca
.32
NEMA - National Electrical Manufacturers Association, 1300 N. 17th Street, Suite 1847,
Rosslyn, Virginia 22209 URL http://www.nema.org
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01420
REFERENCES
PAGE 3 OF 3
.33
.34
NFSA - National Fire Sprinkler Association, P.O. Box 1000, Patterson, New York,
U.S.A. 12563 URL http://www.nfsa.org
.35
.36
NLGA - National Lumber Grades Authority, 406-First Capital Place, 960 Quayside
Drive, New Westminster, B.C. V3M 6G2
.37
NRC - National Research Council, Building M-58, 1200 Montreal Road, Ottawa, Ontario
K1A 0R6 URL http://www.nrc.gc.ca
.38
.39
PCI - Prestressed Concrete Institute, 209 W. Jackson Blvd., Suite 500, Chicago, Illinois,
U.S.A. 60606-6938 URL http://www.pci.org
.40
QPL - Qualification Program List, c/o Canadian General Standards Board, Place du
Portage, Phase III, 6B1, 11 Laurier Street, Hull, Quebec K1A 1G6 URL
http://www.pwgsc.gc.ca/cgsb
.41
SCC - Standards Council of Canada, 270 Albert Street, Suite 2000, Ottawa, Ontario K1P
6N7 URL http://www.scc.ca
.42
SSPC - The Society for Protective Coatings, 40 24th Street, 6th Floor, Pittsburgh,
Pennsylvania 15222-4656 URL http://www.sspc.org
.43
.44
.45
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01450
QUALITY CONTROL
PAGE 1 OF 12
RELATED SECTIONS
.1
.2
1.3
DEFINITIONS
.1
1.4
REFERENCES
.1
.2
City of Ottawa
1.5
.1
Special Provision S.P.No.: D-018 Requirements for Concrete, Hot Mix Asphalt
and Granular Materials.
.2
.3
CONTRACTORS RESPONSIBILITY
.1
The Contractor is to implement their own field quality control system that will include,
but is not limited to, the following tests:
.1
.2
Concrete testing, aggregate testing and cement testing for both cast-in-place
concrete, and precast concrete items.
.3
.4
.5
.6
.7
.8
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.9
Waterproofing membrane.
.10
.11
Vibration monitoring.
.12
.13
SECTION 01450
QUALITY CONTROL
PAGE 2 OF 12
Testing Requirements
.1
.2
Compaction testing:
.1
Testing shall be performed each day by the contractor for all types of
compaction work (piping, foundation, wall and concrete structures
backfill etc.) to demonstrate that the requirements of the specifications
are met to the satisfaction of the Contract Administrator. Testing is
required for compaction at each structure, trench, etc..
.2
Concrete testing:
.1
.3
.4
.6
.5
At least one set of concrete cylinder tests shall be conducted for each
pour with a volume of no more than 50m3. Additional sets of tests shall
be conducted at the rate of 1 set per 50 m3 if the concrete pour exceeds
50m3.
Asphalt mix design shall be submitted as per Citys special provision D018.
Contractor shall establish and implement his own quality control system
throughout the work.
.2
.3
The Contractor shall provide labour and equipment to deliver the samples to the Citys
lab or other approved labs.
.4
The Contractor shall retain a Quality Control Verification Engineer (QVE) licenced in
the Province of Ontario to approve works and submit Certificates of Conformance
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01450
QUALITY CONTROL
PAGE 3 OF 12
INSPECTION
.1
.2
Allow Engineer access to Work. If part of Work is in preparation at locations other than
Place of Work, allow access to such Work whenever it is in progress.
.3
Give timely notice requesting inspection if Work is designated for special tests,
inspections or approvals by Engineer instructions, or law of Place of Work.
.4
If Contractor covers or permits to be covered Work that has been designated for special
tests, inspections or approvals before such is made, uncover such Work, have inspections
or tests satisfactorily completed and make good such Work.
.5
The Engineer may order any part of Work to be examined if Work is suspected to be not
in accordance with Contract Documents. If, upon examination such work is found not in
accordance with Contract Documents, correct such Work and pay cost of examination
and correction.
.6
The Contractor shall engage welding inspector (s) certified by Canadian Welding Bureau
(CWB) to conduct welding inspection whenever field welding is performed. The
inspector must be certified for the appropriate pressure and position of object to be
welded. All brazing and welding on refrigeration piping requires the Contractor to use a
welder that is certified by TSSA. Welder certificate of qualification, not older than 6
months, to be on file at work site.The welding inspection reports shall be prepared and
submitted to the Owner by the certified welding inspector (s) to verify that the field
welding complies with the specification, welding procedures and relevant codes and
regulations.
.7
The contractor shall submit the schedule of material testing in two (2) weeks after the
award of the Contract.
1.7
.2
.3
If defects are revealed during inspection and/or testing, appointed independent agency
will request additional inspection and/or testing to ascertain full degree of defect. Correct
defect and irregularities as advised by Engineer at no cost to the City. Pay costs for all
retesting and re-inspection.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.8
SECTION 01450
QUALITY CONTROL
PAGE 4 OF 12
.2
Mix designs, truck tests and preparation of representative granular material, concrete and
asphalt samples shall be conducted by the Contractor at worksite or at source of
materials in accordance with City of Ottawa Special Provision S.P.No.: D-18.
.3
.4
If defects are revealed during inspection and/or testing, Engineer may request additional
inspection and/or testing to ascertain full degree of defect. Correct defect and
irregularities as advised by Engineer at no cost to the City. Pay costs for retesting and
reinspection.
.5
.6
Any work required to repair or remove and replace damaged QC lots shall be at no extra
cost to the Owner.
.7
.8
1.9
ACCESS TO WORK
.1
Allow Engineer, City staff and inspection/testing agencies access to Work, off site
manufacturing and fabrication plants.
.2
1.10
PROCEDURES
.1
Notify Engineer 48 hours in advance of requirement for tests, in order that attendance
arrangements can be made.
.2
Submit samples and/or materials required for testing, as per City of Ottawa Special
Provision S.P. No. D-018 and D-029. Submit with reasonable promptness and in an
orderly sequence so as not to cause delay in Work.
.3
Provide labour and facilities to obtain and handle samples and materials on site. Provide
sufficient space to store and cure test samples.
1.11
REJECTED WORK
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01450
QUALITY CONTROL
PAGE 5 OF 12
.2
Remove defective Work, whether result of poor workmanship, use of defective products
or damage and whether incorporated in Work or not, which has been rejected by
Engineer as failing to conform to Contract Documents. Replace or re-execute in
accordance with Contract Documents.
.3
.4
If in the opinion of the Engineer it is not expedient to correct defective Work or Work
not performed in accordance with Contract Documents, City may deduct from Contract
Price difference in value between Work performed and that called for by Contract
Documents, amount of which shall be determined by Engineer.
1.12
REPORTS
.1
.2
.3
1.13
Furnish test results and mix designs as per City Special Provision D-018 and D-029.
.2
1.14
1.15
Submit adjustment and balancing reports for mechanical, electrical and building
equipment systems.
MEASUREMENT AND PAYMENT
.1
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate lump sum items included in Section 01025, Measurement and
Payment for all work required to perform quality control as specified herein and no
separate payment shall be made.
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
MATERIAL TESTING
.1
Mix designs, truck tests and preparation of representative granular material, concrete and
asphalt samples shall be conducted by the Contractor at worksite or at source of
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01450
QUALITY CONTROL
PAGE 6 OF 12
materials in accordance with OPSS 501 and City of Ottawa Special Provision S.P. No.:
D-018.
.2
3.2
The Contractor shall provide labour and equipment to deliver the samples to the Citys
lab or other approved labs.
COMPACTION TESTING
.1
SUPPLEMENTAL INFORMATION
CITY OF OTTAWA SP D-023-B: QUALITY VERIFICATION ENGINEERING SERVICES
END OF SECTION
SECTION 01450
COMBINED SEWAGE STORAGE TUNNEL QUALITY CONTROL - ATTACHMENT
SECTION 01450
COMBINED SEWAGE STORAGE TUNNEL QUALITY CONTROL - ATTACHMENT
The Certificate of Conformance shall include the time, date and components
inspected in all Interim Inspections.
Where a QVE is unavailable to complete all the Interim Inspections that are
specified, the QVE shall issue a Certificate of Conformance covering the Interim
Inspections completed to date. The second QVE shall issue a Certificate of
Conformance covering the subsequent Interim Inspections for which the second
QVE is responsible. In this event, the Contractor shall ensure that the Certificates
cover all required inspections and shall submit them at the same time.
The QVE shall not delegate any activity that the Contract Documents require the
QVE to witness. For all other activities, the QVE may delegate the function to
another person where it is consistent with prudent engineering practice to do so,
and the function is performed under the supervision of the QVE.
The process prescribed in this Special Provision for correcting components of the
Work not in General Conformance with the Contract Documents shall apply
unless other remedies are prescribed elsewhere in the contract documents.
Construction
The Contractor shall submit Certificates of Conformance, with reference to the
applicable Working Drawings and other Contract Documents, to the Contract
Administrator at the milestones identified in the Contract Documents and prior to
commencing subsequent stages of the work. The Certificate of Conformance
shall be submitted within 48 hours of completing the Work described in the
Certificate of Conformance unless a different period is specified elsewhere in the
Contract Documents. Where Interim Inspections are specified, the Contractor
shall not proceed until written permission is received from the QVE. A copy of the
written permission shall be made available to the Contract Administrator upon
request.
The QVE shall seal, sign and date Certificates of Conformance indicating that
construction of the Work is in General Conformance with the stamped Working
Drawings and the requirements of the Contract Documents. No conditions or
limitations shall form part of the Certificate of Conformance or the written
permission to proceed following an Interim Inspection. Any amendments to the
Contract Documents accepted by the Owner, and related to the Certificate of
Conformance, shall be appended.
Non-Conforming Work by the Contractor
If the QVE is prevented from issuing a written permission following an Interim
Inspection, or a Certificate of Conformance, because of lack of clarity of the
Contract Documents, the QVE shall seek clarification of the requirements from
the Contract Administrator.
If components of the Work have aspects that are not in General Conformance
with the Contract Documents, the Contractor may propose an amendment to the
SECTION 01450
COMBINED SEWAGE STORAGE TUNNEL QUALITY CONTROL - ATTACHMENT
Contract Documents. The Contractor shall, under the seal and signature of the
QVE, provide the Contract Administrator with an itemized, detailed description of
all aspects within the scope of the Certificate of Conformance that are not in
General Conformance with the Contract Documents. The Contractor shall also,
under the seal and signature of a professional engineer (who may or may not
also be the QVE), provide to the Contract Administrator recommendations for an
amendment to the Contract Documents that will deliver the functionality of the
original Contract Documents.
The proposal for an amendment to the Contract Documents differs from a
change proposal. A proposal for an amendment to the Contract Documents
occurs after the work has been carried out, and the Work does not conform to the
Contract Documents.
The Contract Administrator will:
i) reject the proposed amendment, and require the Contractor to take whatever
remedial measures necessary to achieve a Certificate of Conformance based on
the original Contract Documents.
or
ii) Accept the proposed amendment, but negotiate a credit from the Contractor
where the Owner deems that the amendment does not deliver the same quality
or performance as the Work specified in the Contract Documents, and require
the Contractor to submit a Certificate of Conformance for the work with the
accepted amendment attached.
or
iii) Accept the proposed amendment and require the Contractor to submit a
Certificate of Conformance for the work with the accepted amendment attached.
Contract Specific Requirements
SECTION 01450
COMBINED SEWAGE STORAGE TUNNEL QUALITY CONTROL - ATTACHMENT
SECTION 01450
COMBINED SEWAGE STORAGE TUNNEL QUALITY CONTROL - ATTACHMENT
SECTION 01450
COMBINED SEWAGE STORAGE TUNNEL QUALITY CONTROL - ATTACHMENT
CERTIFICATE OF CONFORMANCE
Contract Number:
Prime Contractor:
Structure (if applicable):
Specific Element(s) being certified:
I,
P. Eng. (print name), a professional engineer
licensed to practice professional engineering in the Province of Ontario, certify
that, in accordance with SP
dated,
[Insert specific wording from the applicable contract document]
Date
Yes
Not
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
SECTION 01510
TEMPORARY UTILITIES
PAGE 1 OF 4
This section includes details regarding temporary utilities required for the construction.
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
1.3
The Contractor shall provide temporary utilities controls in order to execute work
expeditiously.
.2
1.4
UNWATERING
.1
1.5
Provide temporary drainage and pumping facilities to keep excavations and site free from
standing water in accordance of Section 02140 Groundwater Control.
WATER SUPPLY
.1
Contractor to supply, installation, maintenance and removal of the potable water system
required for construction use at its own expense.
.2
Provide a means to prevent water from flowing back into source pipeline. The Contractor
shall provide certified backflow preventer and other items as may be required.
1.6
Provide temporary heating and ventilation required during construction period, including
attendance, maintenance and fuel at contractors own cost.
.2
Temporary heating and ventilation inside hazardous and confined spaces shall meet the
requirements of applicable regulations as in Section 01060 Regulatory Requirements
and, refer to Section 01705 - Contract Work Health and Safety Clauses, and Section
1710 Tunnel and Shaft Safety for details about working in hazardous and confined
space.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01510
TEMPORARY UTILITIES
PAGE 2 OF 4
.3
Construction heaters used inside building must be vented to outside or be flameless type.
Solid fuel salamanders are not permitted.
.4
.2
.3
.4
Provide ambient temperatures and humidity levels for storage, installation and
curing of materials.
.5
.6
Provide heating for the cast-in-place concrete for the duration of cold weather
construction period in accordance with Division 03 of these specifications.
.5
.6
Ventilating:
.1
.2
.3
Dispose of exhaust materials in manner that will not result in harmful exposure
to persons.
.4
.5
.6
Continue operation of ventilation and exhaust system for time after cessation of
work process to assure removal of harmful contaminants.
.7
.8
.9
.10
.11
.12
.13
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.7
1.7
SECTION 01510
TEMPORARY UTILITIES
PAGE 3 OF 4
The Contractor shall be responsible for damage to Work due to failure in providing
adequate heat and protection during construction.
TEMPORARY CONSTRUCTION POWER FOR TUNNEL BORING MACHINE
.1
1.8
.1
Arrange for connection with appropriate utility company at the Contractors own
expense. Pay all costs for installation, maintenance and removal. The contractor shall
obtain power from Hydro Ottawa and will not be permitted to obtain power from any
other existing buildings or facilities unless otherwise approved by Engineer and Owner.
Refer to Section 01520 - Construction Facilities for more details regarding power for the
tunneling equipment. Refer to Section 01520 - Construction Facilities for details on field
office requirements for power and lighting.
.2
The Contractor shall be responsible for supply, installation, tie-in, maintenance and
removal of power service connection at its own expense under the direction of the
Engineer and in accordance with applicable federal, provincial and municipal
regulations.
.3
.4
Temporary lighting inside the hazardous and confined space shall meet the requirements
of regulations. Refer to Section 01705 - Contract Work Health and Safety Clauses and
Section 1710 Tunnel and Shaft Safety for details about working in hazardous and
confined space.
.5
Generators are not allowed to be used in classified areas. If generators are used in the
unclassified areas, comply with regulatory requirements and Citys noise by-laws as
specified in Section 01060 Regulatory Requirements.
.6
Tunnel and shaft lighting to be as per Section 01710 Tunnel and Shaft Safety.
1.9
FIRE PROTECTION
.1
Provide and maintain temporary fire protection equipment during performance of Work
required by governing codes, regulations and bylaws in accordance with Section 01117
Construction Sequences and Constraints.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
SECTION 01510
TEMPORARY UTILITIES
PAGE 4 OF 4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 1 OF 12
Section includes:
.1
Construction aids
.2
.3
Parking
REFERENCES
.1
Comply with the latest edition of the following statutes codes and standards and all
amendments thereto.
.1
Occupational Health and Safety Act and Regulations for Construction Projects,
O. Reg. 213/91 and amendments.
.2
.2
1.3
.1
.2
.3
.4
.5
1.4
MOBILIZATION
.1
1.5
.1
1.6
Provide and maintain scaffolding, ramps, ladders, platforms and temporary stairs.
HOISTING
.1
Provide, operate and maintain hoists required for moving of workers, materials and
equipment. Make financial arrangements with Subcontractors for use thereof.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.7
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 2 OF 12
STAGING AREA
.1
1.8
The staging area (the Contractors laydown area) for each site are shown on the Contract
Documents.
SITE STORAGE/LOADING
.1
.2
Do not load or permit to load any part of Work with a weight or force that will endanger
the Work.
.3
Provide adequate weather tight sheds with raised floors, for storage of materials, tools
and equipment, which are subject to damage by weather.
1.9
CONSTRUCTION SIGNAGE
.1
The warning signs shall be provided on site in both French and English.
.2
.3
Signs and notices for safety and instruction shall be in both official languages. Graphic
symbols shall conform to CSA/CAN3-Z321.
.4
Maintain approved signs and notices in good condition for duration of project, and
dispose of off-site on completion of project or earlier if directed by Engineer.
1.10
1.11
Remove temporary construction facilities from site at the contractors expense when
directed by the Engineer. All temporary site construction facilities will be the property
of Contractor when the Contract is complete.
ACCESS TO SITE
.1
1.12
The Contractor will not be provided with keys for any existing facilities and will
organize access as required with the Engineer.
FIRST AID ROOM
.1
1.13
Provide and maintain on each TBM launching site in a clean orderly condition, a
completely equipped first aid room readily accessible at all times to everyone on the site
all in accordance with governing legislation.
PORTABLE VARIABLE MESSAGING SIGNS
.1
The Contractor shall be prepared to move all portable variable message signs (PVMS) up
to six times a year to any location within the Limits of Work. All locations shall be
approved by the Engineer in advance of any move. All messaging shall be provided by
the Engineer and approved by the City prior to implementation.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 3 OF 12
Refer to Section 01353, Special Procedures: Traffic Control for additional instructions
for the PVMS.
Part 2
Products
2.1
Provide four Engineers Field Offices to be located at the TBM launch/extraction sites
(Sites 3C, 5A, 1, 6) for the duration of work at each of these sites.
.2
Furnish equipment specified for exclusive use of the Engineer and its representatives.
.3
Ownership of equipment furnished under this article will remain, unless otherwise
specified, that of the Contractor.
.4
Equipment furnished shall be new or when approved by the City like new in appearance
and function.
.5
Equipment if any of the models listed within this section are no longer in production
and or available at the time of contract tender, the contractor shall obtain the next model
up or the listed models replacement at no extra cost to the contract.
.6
Locate where directed by the Engineer; level, block, tie down, skirt, and relocate when
necessary and approved. Construct on proper foundations, provide proper surface
drainage.
.7
Provide minimum 10 sq m of gravel or crushed rock base, minimum depth of 100 mm, at
each entrance.
.8
Raise grade under field office, as necessary, to elevation adequate to avoid flooding.
.9
.10
Provide field offices inspected and approved by the Ontario Electrical Safety Authority.
Obtain Building Permits as required by Ontario Building Code (OBC).
.11
.12
.2
.3
Self-contained electric heating and air conditioning unit (no baseboard heaters
will be acceptable), properly sized for project locale and conditions. Provide
ample electric power to operate installed systems. Size heating for internal
temperature of 21 degrees C, outside temperature of minus 25 degrees C, and
allowance of 100 per cent of calculated heat load for infiltration.
.4
.5
Weatherproof, insulated.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 4 OF 12
.6
Doors to be fitted with cylinder locks, with the Engineer in possession of all
keys.
.7
.8
Sanitary Facilities:
.1
.9
Separate male and female sanitary facilities to be flush type with hot and
cold water and drains, electric water heater, all required supplies and to
have a latch with a padlock on the doors.
Exterior Door(s):
.1
Number: Two.
.2
.3
.10
.11
.12
.13
Rooms: Two, with minimum private office floor space of 7.5 sq m, and
remainder configured for open meeting or storage space.
.13
.14
All metal frame; all metal exterior, sides, and roof; and insulated double walls, floor, and
roof.
.15
.16
Electric exhaust fan for lavatory, minimum 1.0 m3/min capacity, complete with
backdraft damper.
.17
Storage Room: One, 1.8 m by 2.4 m, with door with cylinder lock, keyed differently than
exterior door locks. Provide two sets of keys.
.18
.19
.20
Bottled Water Service: One, with cooler that can produce both hot water and
cold water.
.2
.3
Microwave: One.
.4
Coffeemaker: One.
.5
Kettle: One.
.6
.7
.8
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 5 OF 12
.9
Desk: Two steel, 750 mm by 1500 mm with desk surface located 740 mm from
floor.
.10
.2
Adjustable height.
.3
Swivels.
.4
Locking Back.
.5
.6
Adjustable arms.
.11
.12
.13
.14
.15
.16
Four Drawer Steel File Cabinet with Lock: One, legal width.
.17
.18
.19
.20
.21
.22
.23
.21
Sign on entrance door reading CSST ENGINEERS FIELD OFFICE, letter height 100
mm minimum. Sign shall be lit.
.22
Property and Contents Insurance The Engineers trailers shall be insured and all
contents shall be insured for replacement value. Details of the insurance to be provided
by the Contractor shall be approved by the City prior to provision of the field offices.
.23
The engineers office trailer, equipment and furniture shall be available for use by the
Engineer within the first month after the issuance of Order to Commence Work and
remain maintained and available until minimum sixty (60) days after Substantial
Performance of the Contract Work and until all deficiencies are corrected.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.24
2.2
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 6 OF 12
Janitorial services for the Engineers office trailer shall be provided on a weekly basis to
clean floors, table and chair tops and other `general cleaning needs. Provide garbage
disposal and replenishment of paper towel, bottled water, paper cups, hand soap, toilet
paper, first aid kit supplies and garbage bags at least two (2) times per week.
SAFTEY REQUIREMENTS
.1
Construction Fall Arrest Harness (To be sized appropriately for engineering site staff):
Six. Miller tongue buckle leg straps universal harnesses, product number: MLRR10CNTB/UGN.
Part 3
Execution
3.1
TEMPORARY UTILITIES
.1
Provide the following utilities where required and for the field office as required and
specified
.2
Power:
.3
.4
.1
Electric power is available at or near each site except at Site 6. Determine type
and amount available and make arrangements for obtaining temporary electric
power service, metering equipment, and pay all costs for the electric power used
during contract period.
.2
Cost of electric power used in performance of the work and during acceptance
testing will be borne by Contractor.
.3
The Contractor shall replace any blown fuses or damaged breakers and repair
any other damage caused. The Contractor shall provide extension cords as
required. The Contractor shall not overload circuits beyond their rated
capacities.
.4
The Contractor shall provide ground fault protection for all electrical equipment.
.5
The City will not be responsible, or entertain any claims, for the delay of work
resulting from power interruptions to the site or loss of utility supply.
Lighting:
.1
.2
The Contractor shall secure all temporary lighting and wiring from damage,
falling or tripping hazards.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
.6
.7
.2
.3
Pay all costs of installation, maintenance, operation, removal, and fuel consumed
to execute the Work.
.4
Provide portable unit heaters, complete with controls, oil or gas fired, and
suitably vented to outside as required for protection of health and property.
.5
If permanent natural gas piping is used for temporary heating units, do not
modify or reroute gas piping without approval of utility company. Provide
separate gas metering as required by utility.
.6
Water:
.1
Contractor shall be responsible for all costs associated with all associated costs
with taking water.
.2
For water taking during filling during commissioning, refer to Section 01810,
Commissioning.
.2
Security:
.1
.8
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 7 OF 12
Provide and maintain integrated and monitored security system for the
Engineers Project office.
Communication Services:
.1
Contractor: Pay for all installation and monthly billing charges including long
distance charges. Contractor shall reinstate service outages resulting from
construction activities within one business day. Contractor shall report all
service outages to service provider and arrange for service resumption within
one business day.
.2
Contractor to pay for costs and monthly bills for mobile phones including long
distance charges. Contractor to pay for replacement costs of damaged, lost or
non-fully functioning mobile.
.3
Field Office
.1
Internet
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.2
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 8 OF 12
.2
.3
In general, the Contractor shall be responsible to design, provide, install, test, and
energize the temporary construction power distribution equipment; to apply for and
obtain all associated approvals and permits; to pay for all power used in the performance
of the work and during acceptance testing; to de-energize and remove all contractor
supplied temporary construction power distribution equipment, and to re-instate the site
to property owners standards.
.2
The ownership demarcation point is at the 15kV switchgear load side 600A 10kV inserts.
The Contractor is responsible to provide all temporary construction power distribution
equipment, cabling, grounding, and transformation downstream of the demarcation point.
.3
The Contractor shall provide terminations for primary bus cables at the Hydro Ottawa
Switchgear: Cooper #600-12 for 600A, 15kV, Class T-OP II deadbreak connectors.
.4
The Contractor shall design, provide, install, test, and energize the temporary
construction power distribution in accordance with the Ontario Electrical Safety Code
26th Edition 2015 and Hydro Ottawa requirements. The Contractor shall obtain and pay
for all permits and approvals for these works.
.5
All Contractor supplied stepdown transformers shall be submitted to Hydro Ottawa for
review prior to installation and energization.
.6
All Contractor supplied trenching, concrete encased ductbanks, utility structures, and
surface re-instatement shall be performed by a Hydro Ottawa qualified heavy civil
contractor in accordance with Hydro Ottawa specifications GCS0005 and GQS0002.
.7
.8
Armoured cables/conductors are not allowed within the underground ducts and
equipment bases.
.9
The Contractor shall perform hipot testing on the underground 15kV primary cables.
.10
The Contractor shall remove all equipment and civil structures back to the Hydro Ottawa
supply point once temporary construction power is no longer required. The Contractor
shall reinstate the land to the property Owners standard.
.11
Hydro Ottawa shall remove the 15kV switchgear and primary metering. Coordinate with
Hydro Ottawa for removals.
.12
The City will coordinate, pay for, and obtain the required Hydro Ottawa Offer to
Connect for the TBM temporary construction power primary services at the following
sites:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.13
.14
3.3
.1
CSST Site 3c
.2
CSST Site 5
.3
CSST Site 10
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 9 OF 12
The Contractor shall contact Hydro Ottawa to schedule a site kick-off meeting with
Hydro Ottawa and the City prior to the temporary construction power primary service
design and installation.
.1
.2
The City will not be responsible, or entertain any claims, for the delay of work resulting
from power interruptions to the site or loss of utility supply.
PROJECT SIGNS
.1
Install and maintain ten, 2400 mm wide by 1200 mm high signs constructed of 19 mm
exterior high density overlaid plywood. The proposed supports for the signs shall be
approved by the Engineer in advance of the sign installation. Signs will be provided by
the City.
.2
Erect project signs at locations acceptable to the Engineer as soon as any Work
commences on the site and maintain in position until completion. Relocate project signs
when necessary or directed by the Engineer.
.3
Upon completion of the Work, the Contractor is responsible for the removal of the
signboards and the return of the signboards to the Citys Works Compound. No other
signs or notices other than those required for the purposes of warning or indicating
danger to the public in connection with their Work may be exhibited by the Contractor
on the site without the prior approval of the City.
.4
The Contractor shall submit for approval all of their proposed Contractor specific
signage and signage locations prior to installation.
3.4
SECURITY
.1
.2
Provide protection for materials, tools, and equipment being employed on the Project,
including the tools of workers. The City shall not be held to have incurred any liability
for loss of, and damage to, materials, tools, and equipment of the Contractor or of those
employed by them , by contract or otherwise.
.3
The Contractor shall employ such site security services as they may deem necessary to
protect and safeguard the work and the Engineers Project office. The City shall not in
any way be liable for the damage or loss to the work due to trespass or theft.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 10 OF 12
.4
The City may provide such site security services as they may deem necessary to protect
their interest during the progress of the work. Any protection provided by the City shall
not in any way relieve the Contractor of the responsibility for the safety of the work and
acceptance thereof.
.5
The Contractor shall provide temporary fencing to secure the areas of work, laydown,
and office areas. Refer to construction drawings and specifications for the scope of this
work.
.6
The security of Site 6 equipment and staging area is the responsibility of the Contractor
and not the RCMP or PWGSC.
3.5
PROTECTION
.1
.2
3.6
.2
.3
Brace and secure all parts of the work against storm and accident.
.4
.5
Secure and lock all access points to the site at the close of each day's work.
Provide and maintain in good condition all protective measures required to adequately
protect the public from hazards resulting from the work and to exclude unauthorized
persons from the work. When regulated by the Building Code or other authority, such
legal requirements for protection shall be considered as minimum requirements; be
responsible for the protection in excess of such minimum requirements as required.
CONTROL OF SITE
.1
The Contractor shall ensure that no alcohol, firearms, weapons, or controlled substances
enters, or is used, at the project site. The Contractor shall immediately and permanently
remove from the site any of the Contractors or sub-contractors employee found in
violation of this provision.
.2
The Contractor will be responsible for their employees to ensure that contraband is not
transmitted by their employees.
3.7
.2
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
3.8
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 11 OF 12
ACCESS ROADS
.1
Construct access roads as shown and within easements, rights-of-way, or project limits.
Alignments for new routes must be approved by the Engineer.
.2
Maintain drainage routes. Install and maintain culverts to allow water to flow beneath
access roads. Provide corrosion-resistant culvert pipe of adequate strength to resist
construction loads.
.3
Provide gravel, crushed rock, or other stabilization material to permit access by all motor
vehicles at all times.
.4
Maintain road grade and crown to eliminate potholes, rutting, and other irregularities that
restrict access.
.5
Coordinate with the Engineer all proposed detours and other operations affecting traffic
and access. Provide at least 72 hours notice to the Engineer of operations that will alter
access to the site.
.6
Where access roads cross existing fences, install and maintain gates. Gates and gate
posts shall conform to those as specified in Section 02821, Chain Link Fences and Gates.
Upon completion of construction, restore ground surfaces disturbed by access road
construction to original grade.
3.9
PARKING AREAS
.1
Control vehicular parking to preclude interference with public traffic or parking, access
by emergency vehicles, the Citys operations, or other construction operations.
.2
.3
No parking is permitted at Site 6 outside of the staging area. The Contractor may choose
to park commercial vehicles meeting requirements of Section 01117, within the staging
area, but are not permitted to park any vehicles outside of the staging area north of
Wellington Street.
3.10
In accordance with General Conditions, Section 01740, Cleaning, and as required herein.
.2
Provide approved containers for collection and disposal of waste materials, debris, and
rubbish. At least at weekly intervals, dispose of such waste materials, debris, and rubbish
off-site.
.3
At least weekly, and daily at Site 6, brush sweep all driveways and roadways, and all
other streets and walkways affected by the Work and where adjacent to the Work.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
END OF SECTION
SECTION 01520
CONSTRUCTION FACILITIES
PAGE 12 OF 12
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
Section includes:
.1
.2
.3
.4
1.2
SECTION 01560
TEMPORARY BARRIERS AND ENCLOSURES
PAGE 1 of 7
Barriers
Environmental Controls
Traffic Controls
Fire Routes
RELATED SECTIONS
.1
.2
.3
.4
.5
1.3
REFERENCES
.1
1.4
.1
.2
Maintain the temporary fencing in good condition and free of graffiti or use graffiti proof
fencing and remove bill posters for the duration of construction.
.3
1.5
TEMPORARY FENCING
.1
It is imperative that the Contractor construct secure temporary fencing around all sites to
prevent unauthorized entry to the worksite and protect the general public as per the
contract drawings. The Contractor shall note that the limits of work and temporary
fencing shown on the drawings is the absolute limit of work; the Contractor may not in
any situation move fencing outside these limits or use or occupy additional space outside
of these limits.
.2
Refer to contract drawings for the location and type of fencing required at each site.
Chain Link fencing to be as per Section 02821 Chain Link Fences and Gates. The
Contract Administrator may modify the extents or type of fencing at any point during the
project. The Contractor shall notify the Contract Administrator immediately if any
changes in fence type or extents are requested in order to complete the work. All fences
must be maintained in good repair. Install temporary fencing in accordance with staging
contract drawings. See the below table for a list of the types of fencing included in the
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01560
TEMPORARY BARRIERS AND ENCLOSURES
PAGE 2 of 7
contract and referenced in the Contract Drawings. Note that Confederation Hoarding
and NCC Wooden Hoarding have the same meaning and are interchangeable as terms.
Type of Fencing
NCC Wooden Hoarding (Confederation Hoarding) constructed and
treated as per Attachment A with access gates as required
NCC Wooden Hoarding with silt fencing constructed and treated as per
Attachment A with access gates as required and with adjacent silt
fencing incorporated as in Section 01160 Erosion and Sediment
Control
Temporary concrete barrier with NCC Wooden Hoarding on top
constructed and treated as per Attachment A with access gates as
required
Chain Link Fences and Gates as per Section 02821
Chain Link Fences and Gates as per Section 02821 covered with
screening mesh for a partial visual barrier. Screening mesh is to be
20% Opaque.
Temporary Fencing or modular construction fencing to be 1.8 m high
Modu-Loc-type or similar modular panel fencing and/or gates
Temporary Fencing or modular construction fencing to be 1.8 m high
Modu-Loc-type or similar modular panel fencing and/or gates
wrapped/woven with black cloth or screening mesh for a visual barrier
Temporary Fencing or modular construction fencing to be 1.8 m high
Modu-Loc-type or similar modular panel fencing and/or gates with
adjacent silt fencing incorporated as in Section 01160 Erosion and
Sediment Control
Temporary concrete barrier
Temporary concrete barrier with 1.8m high Chain Link fencing on top
2.4 m high wooden hoarding on both sides of walkway combined with
overhead lighting and wooden overhead protection.
1.8m high solid metal or wood hoarding
.3
1.6
Provide temporary barriers around trees and plants designated to remain as per Section
02200 Site Preparation.
GUARD RAILS AND BARRICADES
.1
Provide secure, rigid guardrails and barricades around deep excavations, open shafts,
open stairwells, open edges of floors and roofs.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
1.7
SECTION 01560
TEMPORARY BARRIERS AND ENCLOSURES
PAGE 3 of 7
.1
Submit shop drawings for all fencing types in accordance with Section 01330 - Submittal
Procedures.
.2
Shop drawings for the wooden hoarding on both sides of walkway combined with
overhead lighting and wooden overhead protection shall be designed, approved and
stamped by a Professional Engineer Licensed in Ontario.
.3
Shop drawings for wooden hoarding at Site 6 shall be designed, approved and stamped
by a Professional Engineer Licensed in Ontario and include consideration for wind
loading from the Ottawa River.
1.8
ACCESS TO SITE
.1
Provide and maintain access roads, sidewalk crossings, ramps and construction runways
as required for access to Work as shown on contract drawings.
.2
1.9
Provide and maintain competent signal flag operators, traffic signals, barricades and
flares, lights, or lanterns as required to perform Work and protect the public.
.2
Refer to Section 01353 Special Procedures: Traffic Control for more details with
respect to the vehicular and traffic management and staging plans at all construction
sites.
1.10
FIRE ROUTES
.1
1.11
.1
Protect surrounding private and public property and the general public from damage
during performance of Work in accordance with Section 01119 Preservation and
Protection. Utilize the barriers specified in Article 1.5 above, or additional barriers as
required or requested by the City, Engineer, or NCC and PWGSC.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
SECTION 01560
TEMPORARY BARRIERS AND ENCLOSURES
PAGE 4 of 7
ATTACHMENT A
NCC FENCING STANDARD DRAWINGS
END OF SECTION
SECTION 01560
COMBINED SEWAGE STORAGE TUNNEL TEMPORARY BARRIERS AND ENCLOSURES - ATTACHMENTS
FROM:
Richard Daigneault
Project Manager
Design & Construction Division
SUBJECT:
New Color Codes & Reference Samples for Confed. Blvd Colors
Please note that we have recently developed new color codes and reference samples for
the Confederation Boulevard colors with the Sherwin Williams Chemical Coatings
Company. These new codes and reference samples have been produced specifically for
liquid paint coatings to match the original Confed. Blvd colors (from 1987) and to ensure
color uniformity with the powder coat finish samples developed with Lumec & Sherwin
Williams in 2003/04.
Note that the powder coat color codes (different codes than the liquid finish) are still
available from the Landscape Architecture Section if required.
Sherwin Williams was responsible for preparing reference samples and color codes for
the Powder Coating system used by Lumec for the new CB light fixtures. These colors
are now matched with the following new liquid paint codes:
NCC Dark grey:
NCC Cool Grey:
NCC Green:
* Cardboard color chits are available from the Landscape Architecture Section
The METALLIC BRONZE color for the lighting poles has recently been developed by
SICO paints (local source) to match the metallic bronze color used by Valmont (paint
supplier: Tnemec) for the poles purchased in 2004.
NCC metallic Bronze:
* Sico has been asked to change the above code to NCC 12478 40.
Richard Daigneault
c.c.
G. Lajeunesse
SECTION 01560
COMBINED SEWAGE STORAGE TUNNEL TEMPORARY BARRIERS AND ENCLOSURES - ATTACHMENTS
SECTION 01560
COMBINED SEWAGE STORAGE TUNNEL TEMPORARY BARRIERS AND ENCLOSURES - ATTACHMENTS
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
REFERENCE
SECTION 01561
ENVIRONMENTAL PROTECTION
PAGE 1 OF 5
.1
City of Ottawa Special Provision S.P. No.: D-014 Construction Activities around Trees
.2
City of Ottawa Special Provision S.P. No.: D-032B Protection of Species at Risk and
Wildlife Protocol (as attached)
.3
.4
City of Ottawa Special Provision S.P. No.: F-1005 Erosion and Sediment Control Plan
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
1.3
SUBMITTALS
.1
Submit an Environmental Protection Plan / Spill Response Plan for the approval of the
Contract Administrator and the Consultant for all sites. Submit for approval through the
Contract Administrator to the NCC and PWGSC for Site 3a, 3b, 3c, 5, and 6. The Plan
shall indicate actions and mitigation measures in the event of a spill, pump failure,
temporary dam failure, poor pipe condition and release of flow, or sediment release or
release of hazardous or contaminated material or fluid and personnel tasked with the
reporting and cleanup including but limited to the below procedure.
.1
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
SECTION 01561
ENVIRONMENTAL PROTECTION
PAGE 2 OF 5
.2
Review RVCA flood forecasting and incorporate a response plan to place equipment,
materials outside of the 100-year floodplain if required.
.3
For works on NCC and PWGSC property (Site 3a, 3b, 3c, 5, and 6) , provide a Tree
Management Plan to be reviewed by the NCC and PWGSC at least 15 working days prior
to start of work on the property including where and how the tree protection measures
will be implemented and confirm which trees are to be removed.
1.4
FIRES
.1
1.5
.1
.2
.3
Do not dispose of waste or volatile materials, such as mineral spirits, oil or paint thinner
into waterways, storm or sanitary sewers.
1.6
DRAINAGE
.1
Provide temporary drainage and pumping as necessary to keep excavations and site free
from water.
.2
Do not pump water containing suspended materials into waterways, sewer or drainage
systems.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01561
ENVIRONMENTAL PROTECTION
PAGE 3 OF 5
Sediment Control Plan, Section 01355 - Disposal of Excess Material and Section 02140
Groundwater Control.
.4
The Contractor shall be responsible for obtaining City of Ottawa Sanitary or Storm
Sewer Use Agreement to dispose of pumped water to the sewer.
.5
To prevent adverse effects on aquatic species listed at risk known to inhabit the
environmentally sensitive Rideau River (American eel, river redhorse and bridle shiner),
the Contractor will not discharge any untreated runoff or groundwater into the adjacent
watercourse during the entire duration of the works.
1.7
The Contractor shall refrain from clearing trees during the nesting season for migratory
birds (April 15-August 15) and following Environment Canada guidance on avoidance.
.2
In the event that clearing must occur, the Contractor must retain a Qualified Avian
Biologist to conduct a nesting surveying within 5 days prior to clearing. If active nests of
migratory birds are identified, a setback or buffer to the active nest will be established.
.3
Protect trees and plants on site and adjacent properties where indicated.
.4
For construction activities around trees, S.P. NO.: F-8011 and S.P. D-014 shall apply
except as may be amended and extended herein. Measurement for Payment Section and
Basis of Payment Section of S.P. NO.: F-8011 is deleted in their entirety.
.5
Wrap in burlap, trees and shrubs adjacent to construction work, storage areas and
trucking lanes, and encase with protective wood framework from grade level to height of
2 m.
.6
Protect roots of designated trees to dripline during excavation and site grading to prevent
disturbance or damage. Avoid unnecessary traffic, dumping and storage of materials over
root zones.
.7
For works on NCC and PWGSC property, provide a Tree Management and
Compensation Plan to be reviewed by the NCC and PWGSC at least 15 working days
prior to start of work on the property indicating the above planned information including
where and how the tree protection measures will be implemented and confirm which
trees are to be removed. Incorporate with plan for new trees as in Section 02906 Trees,
Shrubs, and Ground Cover Planting.
.8
Trees affected by Dutch Elm Disease or Emerald Ash Borer must be removed and
managed as per Canadian Food Inspection Agency (CFIA) regulations and standards.
.9
.10
1.8
WILDLIFE PROTECTION
.1
A screening of the Project site shall be completed by the Contractor prior to site
preparation to identify if species at risk are present. If endangered or threatened species
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01561
ENVIRONMENTAL PROTECTION
PAGE 4 OF 5
at risk are identified as occupying the site, a permit or authorization from Environment
Canada or the Ontario Ministry of Natural Resources and Forestry (MNRF) will be
obtained prior to removal.
.2
The Contractor shall train all staff to identify species at risk that could potentially occur
in the area.
.3
Daily visual inspections of the worksite are to be completed throughout the construction
period at Site 5 and 6 on NCC and PWGSC property respectively. In all locations on the
project, in the event that wildlife is incidentally encountered during construction, the
Contractor shall notify the Contract Administrator immediately. The Contractor shall
take all necessary measures to ensure that the animal is not harmed by waiting until the
animal leaves the site and protecting the animal/nest from harm until the young have left
the nest, or if the nest has been determined to be inactive or other mitigation measures
that result in a similar outcome have been implemented. If the animal does not or cannot
leave, the Contractor shall stop work at that location and contact the Canadian Wildlife
Service of Environment Canada (416-739-4214) and the MNRF Kemptville Office
(613-258-8418) for advice, and also notify the Contract Administrator. A permit or
authorization from Environment Canada must be obtained prior to relocation of the
animal.
.4
During the active season for turtles (April 1 to October 30) a daily visual survey for turtle
species at risk must be completed on NCC property at Site 5 within the construction area
by a qualified biologist retained by the Contractor. Turtle nesting may occur between late
May and early July; if nests are observed they are to be protected from harm until the
young have left or as determined by the biologist.
.5
Prior to work within the outfall drainage channel at Site 6, silt curtains or other measures
shall be installed to prevent access of fish to the work area. If required fish removal will
be completed by a qualified biologist to remove any fish trapped within the work area.
.6
All buildings shall be constructed and sealed as required to prevent entry by snakes.
.7
Silt fencing will be installed to prevent species at risk reptiles from accessing the
construction site.
.8
Other requirements for the protection of wildlife and species at risk are described in
D-032B.
1.9
POLLUTION CONTROL
.1
Maintain temporary erosion and pollution control features installed under this contract.
.2
Control emissions from equipment and plant to local authorities emission requirements.
.3
Prevent sandblasting and other extraneous materials from contaminating air beyond
application area, by providing temporary enclosures.
.4
Cover or wet down dry materials and rubbish to prevent blowing dust and debris. Provide
dust control for temporary roads.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.10
SECTION 01561
ENVIRONMENTAL PROTECTION
PAGE 5 OF 5
EQUIPMENT FUELLING
.1
Designate an area within the working limits to be used exclusively for fuelling
construction equipment. Equipment fueling shall be at least 30m away from the Rideau
River and Rideau Canal and at least 15m away from the Ottawa River.
.2
.3
The Contractor shall take all necessary measures to prevent fuel release into the
environment.
.4
Submit for review a plan as described in Article 1.3 above for the interception and rapid
clean-up of fuel spills should they occur. Maintain the apparatus for cleaning up fuel
spills on site.
1.11
NOISE CONTROL
.1
Refer to Section 02482 - Noise and Vibration Monitoring and Section 01060 Regulatory Requirements.
.2
1.12
DUST CONTROL
.1
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
SECTION 01635
COMBINED SEWAGE STORAGE TUNNEL VALUE ENGINEERING CHANGE PROPOSALS
CONTRACT NO. ISD14-2036
PAGE 1 OF 4
Part 1
General
1.1
The Contractor may submit Value Engineering Change Proposals (VECPs) for
changes that the Contractor believes will result in instant Contract savings of at
least $100,000.00. VECPs will only be considered if the proposed change:
.1
.2
will not impair any essential form, fit, function or characteristic of the
Work, such as, but not limited to, safety, service life, reliability, economy of
operation, ease of maintenance, aesthetics and necessary standard features
at the sole discretion of the City; and
.3
.2
.3
1.2
DEFINITIONS
.1
.2
.3
.4
Implementation Costs, as used herein, means those costs the Contractor incurs
to make the contractual changes required by the Owner's acceptance of a VECP.
Such costs will be subject to Owner audit.
.5
Owner Costs, as used herein, means those costs the Owner incurs that result
directly from developing and implementing the VECP, such as, but not limited to,
any net increases in the cost of engineering, testing, operations, maintenance and
logistic support. The term also includes the administrative costs of review and
processing the VECP.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
1.3
SECTION 01635
VALUE ENGINEERING CHANGE PROPOSALS
PAGE 2 OF 4
Instant Contract Savings, as used herein, means the reduction in Contractor cost
of performance (which includes overhead and profit attributable to the reduced or
eliminated work), resulting from acceptance of the VECP, minus implementation
costs and Owner costs.
VECP PREPARATION
.1
.2
.3
A separate, detailed cost estimate for: (i) the affected portions of the
existing Contract requirement and (ii) the VECP. The cost estimate shall
include, without limitation, both capital cost savings, and life cycle cost
savings as well as an itemized breakdown including the items, quantities,
unit prices for both the affected portion in the original design and the
proposed changes in the VECP. The cost reduction associated with the
VECP shall take into account the Contractor's implementation costs.
.4
.5
.6
A statement of the time by which a Change Order accepting the VECP must
be issued in order to achieve the maximum cost reduction, noting any effect
on the Contract Time, achievement of any milestones, or delivery schedule.
.7
.8
.9
.10
A revised schedule for the affected portion(s) of the Work and the entire
contract work if any.
.11
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.12
1.4
SECTION 01635
VALUE ENGINEERING CHANGE PROPOSALS
PAGE 3 OF 4
PROCESSING PROCEDURES
.1
Two copies of each VECP shall be submitted to the Consultant. VECPs will be
processed expeditiously, however, neither the Owner nor Consultant will be liable
for any delay in acting upon or for failure to act upon, any VECP submitted
pursuant to this Section. The Contractor may withdraw, in whole or in part, a
VECP not accepted by the Owner within the period specified in the VECP.
.2
The Owner and the Consultant will be the sole judge of the acceptability of a
VECP and of the savings and costs from the adoption of all or any part of such
proposal. In determining the savings, the right is reserved to disregard the
Contract bid prices if, in the judgment of the Consultant, such prices do not
represent a fair measure of the value of the work to be performed or to be deleted.
The decision of the Consultant regarding acceptability or unacceptability of the
VECP, as well as the savings and costs, shall be final.
.3
The Owner and the Consultant may require the Contractor to modify the VECP to
make it acceptable. If any modification increases or decreases the savings
resulting from the VECP, the Contractor's fair share will be determined upon the
basis of the VECP as modified.
.4
The Owner and Consultant may accept, in whole or in part, a VECP submitted
pursuant to this Section by issuing a Change Order. However, pending issuance
of a Change Order, the Contractor shall remain obligated to perform in
accordance with all requirements of the Contract Documents.
.5
The Owner and the Consultant will respond to the Contractor about the
acceptability of each VECP within 20 working days after the VECP is received.
1.5
SHARING ARRANGEMENTS
.1
The Contractor and Owner shall each receive a 50 percent share in the Instant
Contract Savings. Upon acceptance of a VECP, a Change Order will be issued
reducing the Contract Price by 50 percent of the Instant Contract Savings.
.2
The Contractor is not entitled to share the collateral savings and other future
contract savings resulting from the accepted VECP (s).
1.6
WARRANTY
.1
The Contractor shall be, and shall remain, liable for the effectiveness of the
design of the change proposed.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
1.7
SECTION 01635
VALUE ENGINEERING CHANGE PROPOSALS
PAGE 4 OF 4
The Contractor warrants that such change: shall be free from defects in design,
function, configuration and purpose; shall fully perform the function as intended
and required by the Contract Documents; complies with all laws, rules,
regulations and ordinances governing such an item; and infringes no patent,
copyright, trade secret or other third party proprietary right or interest.
DATA
.1
To the extent permitted or allowed by law, neither the Owner nor Consultant will
disclose, use or duplicate any data provided by the Contractor pursuant to this
Section, while such VECP is being evaluated. This restriction shall not apply to
any information if it is, or has been obtained, or is otherwise available, from the
Contractor or from any other source, without limitation. Once the VECP
evaluation process has concluded, the Owner shall have the right to duplicate, use
and disclose any data in any manner, and for any purpose, and have others do so,
under this or any other Owner contract.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 1 OF 12
RELATED SECTIONS
.1
.2
.3
.4
.5
1.3
REFERENCES
.1
1.4
.1
The contractor shall register the project, as required by OHSA and regulations, with the
Ministry of Labour before commencing any work on any of the sites. A copy of the
registration must be provided to the Engineer before starting work on the site and a copy
must be posted in a visible location on the work site at all times.
.2
.3
Meet or exceed the latest revision of all Local, Federal, Provincial laws, regulations,
standards, and industry best practices relating to health and safety.
.4
Be solely responsible for safety of the Work under this Contract and for complying with
and ensuring that every person on the Site complies with the requirements contained
within the Contract Documents and regulatory requirements.
.5
Perform the Work, or ensure that it is performed, in a manner to avoid risk of injury,
security or damage to persons or property, adjacent property, or environment.
.6
Provide safe access, egress, and equipment in accordance with Occupational Health and
Safety Regulations for entry into all areas by the employees, subcontractors, City, and
Engineer. Where hazardous areas or confined space entry exists, implement procedures
defined by the latest revision of the applicable Occupational Health and Safety
Regulations or the Electrical Code.
.7
Refer to Section 01710 Tunnel and Shaft Safety for specific safety requirements
related to tunnel and shaft safety.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 2 OF 12
Prior to the commencement of the Work, review and become fully familiarized with all
Local, Provincial, and Federal regulatory requirements and the following documentation.
The Contractor shall be solely responsible for construction safety for this Contract and
for complying with and ensuring that every person on the Site complies with the
measures and requirements contained in:
.1
.2
.3
.4
.5
Contract Documents
.9
In event of a conflict between any provisions of the above authorities, the most stringent
provision shall govern.
.10
Provide and maintain first aid, hygiene, washrooms, potable water, and fire prevention
equipment, at the Site in accordance with the applicable regulatory requirements. The
Contractor shall designate trained employees to be in charge of first aid on the Site.
.11
Establish, maintain, and mark clear routes, paths and points for routine and emergency
exit to, from and within the Site for personnel and vehicles.
.12
The Contractor shall erect signs relating to safety on the Site, and signs or notices
required by the applicable provincial and local regulations or by the Contract
Documents.
.13
Erect signage and post notices acceptable to the City and required by the applicable
provincial and local regulations or by the Contract Documents at all entry points to the
Site to advise personnel, employees, Subcontractors and other individuals entering the
Site of the requirements respecting the use and wearing of personal protective equipment
and the below requirements:
.1
All personnel and employees on the Site are required to comply with safety
policies, procedures and instructions of the Contractor;
.2
That any personnel failing to adhere to the safety policies, procedures and
instructions of the Contractor may be removed from the Site and denied further
access.
The Contractor shall post warning signs at hazardous areas or where hazardous materials
are stored, and install protective barriers. The Contractor shall instruct personnel in
proper safety procedures.
.15
The Contractor shall identify all areas which are considered to be hazardous locations
and comply with all requirements of the Ministry of Labour.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 3 OF 12
.16
Smoking is not permitted in hazardous areas or other areas as designated by the City. The
Contractor shall post "No Smoking" signs as required.
.17
The Contractor shall inspect the physical condition of the workplace at least weekly, or
as often as required by provincial health and safety regulatory requirements, in order to
ensure that the Work is performed safely and that the Site is maintained in accordance
with the provincial regulatory requirements and the Contract Documents. The Contractor
shall prepare and maintain a documented record of each inspection describing the scope
of inspection and findings. Copies of all safety inspections shall be kept on Site and
available for review by the Engineer.
.18
Safety equipment such as gas detection equipment for explosive or toxic gases or oxygen
deficiency, fall protection devices etc., shall be made available by the Contractor to the
City's and the Engineer's staff for the access to the site when required. The Contractor
shall be responsible for the coordination of the multiple-party access to the hazardous
and confined spaces on the Site.
.19
Ensure adequate coordination and communication between all parties on site in regards
to safety.
.20
In addition to Occupational Health and Safety Act and applicable Regulations reporting
requirements, report all incidents, near misses, spills, environmental damage, and
property damage to the City and Engineer immediately. An incident investigation must
be conducted and a copy of the complete report provided to the City and Engineer within
24 hours.
.21
Ensure that all employees and subcontractors are competent, as prescribed by the
applicable legislation, in performing the Work and have been trained on the Contractor's
Site-specific Health and Safety Plan prior to starting Work on the Contract. The
Contractor shall make available all training records for the City and Engineer's review.
.22
The contractor shall ensure all workers that perform work be certified under the Trades
Qualifications and Apprenticeship Act for their specific work activity. No worker shall
perform a type of work unless he/she is certified to do so.
.23
.24
The supervisor shall supervise the work at all times either personally or by having an
identified assistant do so personally. The assistant must comply with all the same
requirements that the supervisor is held to.
.25
The supervisor shall inspect the work site and equipment associated with the project at
least once a week. A copy of the inspection report must be provided to the Engineer.
.26
The contractor shall remove waste material and debris from the work site(s) to a disposal
area at least once a day or more frequently if necessary to prevent the creation of a
hazardous condition.
.27
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.28
1.5
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 4 OF 12
The contractor shall ensure all vehicles, machinery, tools and equipment used on the
work site are operated and maintained in accordance with Section 93 to 116, O. Reg.
213/91.
SUBMITTALS
.1
The Contractor shall submit a Site-specific Health and Safety Management Plan within
ten (10) Working Days after the Award of the Contract to address the requirements of the
above referenced regulations and contract documents. The plan is to be provided to the
NCC and PWGSC at least 20 working days of when work takes place on their property.
The plan shall as a minimum include:
.1
.2
A Site Health and Management Plan, including introduction and roles and
responsibilities for:
.1
Site workers
.2
.3
.4
Task managers
.2
.3
.4
.5
.6
.7
.8
.9
.10
Housekeeping
.11
Tunnel and shaft related safety issues, including but not limited to air monitoring
and response plan in the event of atmospheric issues, evacuation procedures, fire
response plan, and other issues identified in related sections. Refer to Section
01710 Tunnel and Shaft Safety for more detailed requirements.
.2
Physical
.3
.4
.5
.6
.7
Biological
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
.5
1.6
.8
.9
Noise
.10
Personal Security
.11
.12
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 5 OF 12
.2
First aid
.2
Fire Protection
.3
Critical Injury
.4
Accident or Incident
The plan shall be posted in a visible location on the work site prior to the commencement
of any work.
CHEMICALS
.1
The Contractor must provide a list of all chemicals to be used on site and a copy of the
Material Safety Data Sheet (MSDS) for each chemical to the Engineer prior to being
brought onto the job site.
.2
The Contractor must ensure each chemical container brought on site is clearly labelled
with the identity of the chemical, information for the safe handling of the chemical and
the location of the MSDS.
.3
The Contractor must ensure adequate measures are taken to control the distribution,
within the application area or throughout the building, of fumes/vapours before applying
flammable, noxious or volatile materials.
.4
The Contractor may be required to schedule the application of hazardous materials which
might affect the well-being of any workers or disrupt work of other Contractors and
cannot be adequately controlled to prevent such occurrences to evening or weekend
periods.
.5
The Contractor must ensure workers wear the required personal protective equipment
(respiratory protection, protective clothing, hand protection, eye/face protection, etc.)
when working with chemicals.
.6
The Contractor must ensure the safe use and disposal of all chemicals that they are using
as in Section 01355 Disposal of Excess Material. No chemicals and/or chemical waste
product shall be disposed of on site without prior approval of Engineer.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.7
1.7
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 6 OF 12
The Contractor may not store chemicals and compressed gas cylinders on site without
approval of the Engineer. If approved, the Contractor must ensure incompatible
chemicals are stored separately.
DESIGNATED SUBSTANCES / HAZARDOUS WASTE
.1
The Contractor shall provide a work plan in Section 01355 Disposal of Excess
Materialfor the removal of designated substances, in accordance with all applicable
legislation, for review and approval to the Engineer.
.2
The Contractor shall provide evidence of competency with regards to the Environmental
Protection Act and its regulations, a copy of safe handling work plan prior to
commencing with work in the area.
.3
The Contractor shall register the project as a waste generator site, if not already
registered, for the waste that will be generated as a result of the work activities related to
the project.
.4
The Contractor shall ensure and provide evidence that all hazardous wastes removed
from the site is sent to a licensed waste disposal site by a licensed carrier and advise the
responsible individual when necessary testing is to be carried out.
.5
The Contractor shall retain copies of all hazardous waste manifests on file.
.6
The Contractor shall inspect the project daily to monitor compliance with designated
substances and hazardous waste regulations.
.7
The Contractor shall provide access to the responsible individual for review of all
inspection reports.
1.8
WORKING AT HEIGHTS
.1
1.9
The Contractor shall comply with the requirements of O.Reg 297/13 which requires all
workers complete working at heights training if they use fall protection systems.
FALL PROTECTION
.1
The Contractor shall comply with the requirements of Section 26, O. Reg. 213/91 and
Sections 85 and 86, O. Reg. 851.
.2
The Contractor shall provide, upon request, proof of worker training in the use of their
fall protection systems.
.3
The Contractor shall be responsible for supplying and maintaining (to City standards) all
equipment needed to perform this role.
1.10
LADDERS
.1
The Contractor shall comply with the requirements of Section 78 to 84, O. Reg. 213/91
and Sections 73, O. Reg. 851.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
1.11
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 7 OF 12
The Contractor shall be responsible for supplying and maintaining (to City standards) all
equipment needed to perform this role.
WELDING/CUTTING
.1
The Contractor shall comply with the requirements of Section 122 to 124, O. Reg.
213/91.
.2
The Contractor shall be responsible for supplying and maintaining all equipment needed
to perform this role.
.3
1.12
SCAFFOLDING
.1
The Contractor shall comply with the requirements of Section 125 to 142, O. Reg.
213/91.
.2
The Contractor shall design, erect, inspect, maintain and use scaffolding equipment,
materials, and components in accordance with CAN/CSA-S269.2-M87 (Access
Scaffolding for Construction Purposes).
.3
The Contractor shall be responsible for supplying and maintaining all equipment needed
to perform this role.
1.13
The Contractor shall comply with the requirements of Section 143 to 149, O. Reg.
213/91 and Sections 51 to 54, O. Reg. 851.
.2
The Contractor shall be responsible for supplying and maintaining all equipment needed
to perform this role.
1.14
The Contractor shall comply with the requirements of Section 150 to 156 and 168 to 180,
O. Reg. 213/91.
.2
The Contractor shall comply with the requirements of Section 187, O. Reg. 213/91 if a
crane or similar hoisting device is operated near an energized overhead electrical
conductor and if it is possible for a part of the equipment or its load to encroach upon the
minimum distance permitted under section 186, or when the hoisting device is positioned
closer than the length of its boom to an energized overhead electrical conductor.
.3
The Contractor shall provide, upon request, proof of worker training in the safe operation
of the crane or similar hoisting device.
.4
The Contractor shall make available all logbooks, inspection records and tests for cranes
or similar hoisting devices, upon request.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
1.15
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 8 OF 12
The Contractor shall be responsible for supplying and maintaining all equipment needed
to perform this role.
EXPLOSIVE ACTUATED FASTENING TOOL
.1
The Contractor shall comply with the requirements of Section 117 to 121, O. Reg.
213/91.
.2
The Contractor shall be responsible for supplying and maintaining all equipment needed
to perform this role.
1.16
The Contractor shall ensure no person enters an excavation unless another worker is
working above ground close to the excavation or to the means of access to it.
.2
The Contractor shall arrange the locating and marking of gas, electrical and other
services prior to commencing an excavation.
.3
The Contractor shall obtain approval from Engineer before arranging the shut off and
disconnection of a service that may pose a hazard.
.4
The Contractor shall comply with the requirements of Section 230 to 242, O. Reg.
213/91.
.5
The Contractor shall be responsible for supplying and maintaining all equipment needed
to perform this role.
1.17
1.18
The Contractor shall comply with the requirements of Section 64 to 66, O. Reg. 213/91.
TRAFFIC CONTROL
.1
1.19
.1
Before commencing the day's work and while working in areas that may contain an
explosive, toxic or oxygen deficient atmosphere, test for explosive, toxic gases, and
oxygen deficiency. If a hazardous condition is found, make the work area safe before
commencing or continuing work.
.1
Provide and maintain a suitable detection meter. Use this meter continuously.
Calibrate the meter to sound an alarm at a preset warning level.
.2
.2
Smoking is not permitted in the hazardous areas and other areas designated by the City.
The Contractor shall post No Smoking signs as required.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
.5
.6
Hazardous Locations
.1
Where not indicated on the Contract Drawings, the Contractor shall assess and
identify all hazardous locations and confined space locations.
.2
.3
.2
.7
When the potential for a hazardous atmosphere exists, have a competent worker
operate and read the portable meter continuously while construction activities
occur in the designated hazardous locations. This meter operator is not permitted
to assist in the construction activity in any way. Locate meter operator in the
immediate vicinity of construction activity. If work in two or more different
hazardous locations is required at the same time, provide the additional meter
operator and meter.
Training
.1
.9
Utilize a suitable portable gas detection meter to continuously monitor for toxic
gases, combustible gases, hydrogen sulfide and oxygen deficiency in the
surrounding atmosphere. Set meter to sound alarm at a preset warning level. The
Contractor shall demonstrate to the Engineer that the meter has recently been
calibrated by a certified technician and is adequately functional for the intended
purpose.
Meter Operator
.1
.8
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 9 OF 12
Arrange and pay for a meter manufacturer representative to supply site training to
designated meter operator(s). Conduct as many training sessions as required to
train the operator(s).
If the meter indicates 5% of the Lower Explosive Limit (LEL) or more for
methane or less than19.5% or more than 23% oxygen, discontinue construction
activity, evacuate area, and notify the Engineer.
.2
If meter detects H2S that exceed 1 ppmv the meter should alarm. If meter exceeds
2 ppmv, discontinue construction activity, evacuate area, and notify the Engineer.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.10
Log Book
.1
.2
.11
Date
.2
.3
.2
Firefighting Equipment
.1
1.20
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 10 OF 12
The identified Confined Space Locations are as defined by a O. Reg. 632/05, OHSA. All
work and entry into the identified Confined Spaces is to be done in accordance with the
Regulation (O. Reg. 632/05) and City of Ottawa Standard Special Provision D-009:
Work In Confined Spaces.
.2
Work in the confined spaces may involve workers from multiple employers. The
Contractor is deemed to be the lead constructor with respect to confined space entry
regulations. The Contractor is responsible for all duties to ensure the work performed in
the confined spaces is carried out in accordance with O. Reg. 632/05 and the Contractor
is responsible for all actions to ensure the duties imposed on employers by O. Reg.
632/05 are performed to protect the health and safety of all workers working in the
confined spaces. For all confined space entries, involving workers from any employer,
the Contractor is responsible for all coordination of work activities, confined space
assessment, development of entry plans, permitting, supply of equipment for
atmospheric testing and monitoring, ventilation, access and egress, entry, monitoring,
control, rescue planning, and the initiation and implementation of rescue procedures in
accordance with the Regulation.
.3
The Contractor shall maintain all appropriate documentation required under the
Regulation and provide daily copies to the Engineer.
.4
The Contractor shall supply all required safety, monitoring, control and personal
protective equipment required for confined space entry operation, including, but not
limited to entry and rescue equipment, atmosphere monitors and breathing
apparatus/respiratory protection.
.5
The Contractor shall ensure that all workers entering or interacting with the identified
confined spaces are appropriately trained and that proof of training is provided upon
request. The staff from the City, Engineer and third party workers hired by the City or
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 11 OF 12
the Engineer will have received training in confined space entry from their own
respective employer.
.6
1.21
The Contractor shall make provisions for the Contract Administrator, Engineer, third
party inspectors, and City staff to enter the identified confined spaces, if needed and as
required, under the Contractor's confined space entry permits and plans with one (1) day
notice (or less under emergency conditions).
EXPLOSION-PROOF CONSTRUCTION
.1
.2
In hazardous areas as defined above, provide intrinsically safe mechanical devices and
equipment such as non-sparking aluminum wheels for fans, pneumatic operators for
dampers and aluminum clappers for check valves on pipelines conveying gaseous fuels.
.3
Temporary structures such as fabrication shops, storage areas, and offices will not be
permitted within existing facility structures unless approved by the Engineer.
1.22
SAFETY EQUIPMENT
.1
1.23
Provide safety equipment such as ropes, fall arrest device, proximity belt,
combustible/hazardous gas and oxygen depletion meter for the use of the Engineers
resident inspection staff. Provide casual labour to resident inspection staff when entry is
required to manholes or other areas that may be hazardous. Resident services staff is not
allowed to enter such areas alone.
ASSISTANCE
.1
1.24
Give reasonable help to the Engineers resident services staff in checking the setting out
of the work. Arrange for ready access to work.
WORK AT SITE 6
.1
In the event of emergency at Site 6, call 911 and notify PWGSC and RCMP of the
incident (contact information and timeframe to be provided to Contractor when
available).
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
SECTION 01705
CONTRACT WORK HEALTH AND
SAFETY CLAUSES
PAGE 12 OF 12
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE OF WORK
.1
SECTION 01710
TUNNEL AND SHAFT SAFETY
PAGE 1 OF 6
This section complements Section 01705, Contract Work Health and Safety Clauses and
refers to additional safety requirements for the tunnel and shafts. The Contractor shall
be responsible for initiating, maintaining and supervising all safety precautions and
programs in connection with the Work. The Contractor shall take all reasonable
precautions for the safety of, and provide the appropriate protection to prevent damage,
injury or loss to:
.1
All employees contributing to the Work and other persons who may be affected
thereby.
.2
All the Work and all materials or equipment to be incorporated therein, whether
in storage on or off the site.
.2
The Contractor shall comply with all applicable laws, ordinances, rules, regulations and
orders of any public body having jurisdiction for the safety of persons or property or to
protect them from damage, injury or loss. Erect and maintain, as required by the
conditions and progress of the Work, all reasonable safeguards for its safety and
protection. Notify owners of adjacent utilities when prosecution of the Work may affect
them. All damage, injury or loss to any property caused directly or indirectly, in whole or
in part, by Contractor, any Sub-Contractor or anyone directly or indirectly employed by
any of them or anyone for whose acts any of them may be liable, shall be remedied by
Contractor, except damage or loss attributable to the fault of Contract Drawings or
Specifications or to the acts or omissions of City or Contract Administrator or anyone
employed by either of them or anyone for whose acts either of them may be liable, and
not attributable, directly or indirectly, in whole or in part, to the fault or negligence of
Contractor. Contractors duties and responsibilities for the safety and protection of the
Work shall continue until such time as all the Work is completed and Contract
Administrator has issued a notice to City and Contractor that Work is acceptable.
.3
All Work shall conform to the requirements of the Occupational Health and Safety Act,
O. Reg. 213/91 and O. Reg. 632/05.
.4
No separate payment will be made for the Work included herein, and all costs in
connection therewith shall be included in the cost of the structure or item to which it
pertains.
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01710
TUNNEL AND SHAFT SAFETY
PAGE 2 OF 6
.6
.7
.8
.9
1.3
REFERENCES
.1
.2
.3
.4
Ontario Health and Safety Act (OHSA) R.R.O. 1990, Reg. 854: Mines and Mining Plants
1.4
GENERAL REQUIREMENTS
.1
Comply with Section 01705, Contract Work Health and Safety Clauses and with Section
02444 Tunnel and Shaft Ventilation and Utilities.
.2
.3
The Contractor is advised that tunnel and shaft excavations in soil or rock are classified
as confine space as defined in O. Reg. 632/05 that may contain atmospheric hazards.
The term atmospheric hazard means (a) the accumulation of flammable, combustible
or explosive agents, (b) an oxygen content in the atmosphere that is less than 19.5 per
cent or more than 23 per cent by volume, or (c) the accumulation of atmospheric
contaminants, including gases, vapours, fumes, dusts or mists, that could. For this
project, historically there has been methane and hydrogen sulphide occurrences in the
geological formation in which the tunnel will be excavated Contractor shall comply with
requirements as stated in this Section.
1.5
SPECIFIC REQUIREMENTS
.1
Work in tunnel and shaft excavations shall be subject to provisions of certain mining
regulations promulgated under the Occupational Health and Safety Act. Specifically,
regulations for mines and mining plants stated in R.R.O. 1990, Reg. 854, Section 35
apply. These regulations address the occurrence of flammable gas in a mine, and this
specification section applies the referenced section of the regulation to the occurrence of
flammable or explosive gases in the tunnels and shafts to be excavated as part of the
Work.
.2
The tunnel and shaft excavations are classified as Class 1, Division 2 locations. At a
minimum, the tunnel ventilation system and tunnel construction water discharge pumps
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01710
TUNNEL AND SHAFT SAFETY
PAGE 3 OF 6
.4
The Contractor shall have a competent, Health and Safety Officer(s) on the job
with experience in tunnel and shafts construction, certified by OSHA Training
Institute, with an appropriate office on the job site to maintain and keep available
safety records and up-to-date copies of all pertinent safety rules and regulations.
.2
.2
.3
Post the name, address, and hours of the nearest medical doctor; names
and addresses of nearby clinics and hospitals; and the telephone numbers
of the fire and police departments.
.4
.5
.6
.7
.8
.9
Notify the City and the Contract Administrator of any accident claim
against the Contractor or any Sub Contractor immediately, followed up
by a detailed written report on the claim and its resolution.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.10
SECTION 01710
TUNNEL AND SHAFT SAFETY
PAGE 4 OF 6
.5
All personnel employed by the Contractor or its Sub Contractors, whenever entering the
job site, any shaft, or tunnel, shall be required to wear approved safety hats as well as
protective clothing, footwear and other equipment as required by OHSA or as necessary
for the safety of personnel. The Contractor shall maintain, on site, a sufficient number of
safety hats for the use of visitors.
.6
Should conditions change within the tunnel to the extent that Health and Safety
procedures must be modified, Contractors Health and Safety Officer shall immediately
provide new Health and Safety training for all personnel requiring access to the tunnel,
including Contract Administrator and City personnel.
.7
The Contractor is to ensure that a sufficient number of their staff have received rescue
training, per Section 265 of O.Reg. 213/91 Regulation for Construction Projects. The
Contractor is required to provide safe access to the tunnel at any location and any time to
the Owner, Contract Administrator, Inspectors, or Design Team when requested.
.8
Where Work is in progress in a tunnel or shafts, the Contractor shall also provide as a
minimum the following safety equipment:
.1
.2
.3
.4
.5
Portable combustible gas analyzer for the detection of explosive gases such as
methane, petroleum, and vapors;
.6
.7
.9
The Contractor shall provide lighting in accordance with applicable safety regulations
for the entire length of the tunnel. Light shall be adequate as determined by the Contract
Administrator, to permit proper inspection of all operations at all times. Minimum
lighting consisting of 60-Watt light bulb at 12-metre spacing will be maintained during
all Working hours. The intensity of the lighting required by applicable regulations for
tunnel excavating operations shall be increased as required by the Contract
Administrator for concrete placement and for final cleanup. Open flame lights shall not
be used. Flashlights and appropriate fixtures shall be explosion proof and designed to
function safely in a flammable or explosive gas atmosphere
.10
Ventilation: Comply with Section 02444, Tunnel and Shaft Ventilation and Utilities.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01710
TUNNEL AND SHAFT SAFETY
PAGE 5 OF 6
.11
The Contractor is cautioned that, upon excavation, the rock may deteriorate upon
exposure to air and water. The Contractor shall inspect all exposed rock surfaces and
installed support daily for signs of deterioration or distress. Qualified employees shall
perform inspection. Contractor shall report any remedial action deemed necessary
immediately after identified by inspection. Contractor shall support all rock surfaces and
protect all rock surfaces in tunnels and shafts from exposure to air and water as may be
necessary or as specified in the Contract Documents.
.12
All shafts shall be enclosed with a security fence in accordance with the Contract
Documents. The security fence shall be secure at any time the site is unattended by
Contractors personnel. All storage areas and Workshops shall be segregated so that
their use during times of site inactivity does not compromise the security of the shaft
area. The fence shall have all necessary gates and entrances. In addition, the Contractor
shall provide barricades at the top of shafts in accordance with applicable regulations,
and shaft covers as specified herein.
.13
Internal combustion engines other than mobile diesel powered equipment shall not be
used underground. All diesel powered mobile equipment used underground shall be as
prescribed in applicable safety regulations and operated in accordance with the same.
The Contractor, upon request, shall submit proof of certification to the Contract
Administrator.
.14
All haulage equipment such as hoists, cages, and elevators in operation in excavations
and shafts shall conform to all requirements described in applicable regulations.
.15
.16
Noise and Dust Control: Control noise and dust in accordance with applicable provincial,
and local laws, safety codes, regulations and ordinances.
.17
Muck Handling: Equip muck trains with acceptable braking systems and safety chains to
prevent runaway trains. Provide spill protection for muck conveyor systems.
.18
The Contractor shall maintain the stability of the excavation around the periphery of all
underground Work.
.19
The Contractor shall provide all requested access to Emergency Services personnel,
including, but not limited to police, fire, and EMS who may wish to visit the sites, to
acquaint themselves with the Contractors operations. The Contractor shall wholly
cooperate with the Emergency Services at all times and shall, as part of their health and
safety plan, incorporate training of select Emergency Services Personnel in the
Contractors Health and Safety Plan.
.20
The City and the Contract Administrator shall have the right to document all health and
safety concerns regarding the Contractors operations and to issue warnings and/or to
stop work for any violations of the OHSA, the Ontario Construction Regulations, or any
health and safety requirements of the Contract, including all City health and safety
policies, programs, rules, regulations, and/or if the Contractor creates a health or safety
hazard on, or in the vicinity of, the site.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.21
1.6
SECTION 01710
TUNNEL AND SHAFT SAFETY
PAGE 6 OF 6
The City reserves the right to have a health or safety hazard corrected at the Contractors
expense.
SUBMITTALS
.1
In addition to the Site-specific Health and Safety Management Plan described in Section
01705, Contract Work Health and Safety Clauses the Contractor shall submit Rescue
Procedure Plan for each shaft that address tunnel and shaft evacuation procedure in the
event of fire, flood, oxygen deficiency and presence of gas. Plan shall also address
eventuality of evacuation/rescue in the case of collapse, accident or other significant
events.
.2
In addition to requirements of the Health and Safety Officer stated in Subsection 1.5, the
Health and Safety Officer has to submit monthly incident reports indicating type of
incident, date and location, summary of events before the incident, description of the
incident, name of employee, type of injury if any, if hospitalization was required or not
and amount of leave days due to injuries if any. Also, the report has to describe the
rescue procedure if applicable, time of response and if any adjustments are required to
the Health and Safety Management Plan.
.3
Health and Safety Officer - Within 10 calendar days of the Notice to Proceed, submit a
resume showing the qualifications of the Health and Safety Officer, including a
description of the Safety Officer's experience, education, and special safety and first aid
courses completed, and safety conferences attended, and shall indicate that the individual
possesses safety experience in heavy construction and underground construction. If the
Health and Safety Officer is the same individual identified in Contractor's
prequalification submittal as the Safety/ Environmental Manager or the backup, then
Contractor's submittal shall clearly indicate which individual will serve as the Health and
Safety Officer, and resubmittal of qualifications is not required.
1.7
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to ensure safety to all personnel
entering the shafts and tunnels and no separate payment shall be made.
Part 2
Part 3
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01720
PREPARATION, MOBILIZATION,
DEMOBILIZATION
PAGE 1 OF 5
.2
.3
.4
.2
.3
1.3
QUALIFICATIONS OF SURVEYOR
.1
1.4
.1
Provide a minimum of three (3) consecutive reference points at a distance not exceeding
15 m (50 ft) at each Site.
.2
Locate, confirm and protect control points prior to starting site work. Preserve permanent
reference points during construction.
.3
.4
.5
Require surveyor to replace control points in accordance with original survey control.
.6
Do not commence construction unless all reference points and levels are in place along
section of work under construction.
.7
.8
The City or the Engineer will provide a Bench Mark close to each Site
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.5
SECTION 01720
PREPARATION, MOBILIZATION,
DEMOBILIZATION
PAGE 2 OF 5
SURVEY REQUIREMENTS
.1
Establish sufficient permanent bench marks at each Site, referenced to established bench
marks by survey control points. Record locations, with horizontal and vertical data in
Project Record Documents.
.2
.3
.4
.5
.6
.7
.8
.9
1.6
ELEVATIONS
.1
Unless otherwise stated, elevations given on the drawings or in the specifications refer to
the datum of the Geodetic Survey of Canada expressed in SI metric units.
.2
Verify elevations given and promptly report discrepancies to the Engineer in writing.
1.7
SURVEY MONUMENTS
.1
Maintain survey monuments, iron bars, round iron pipes and stakes for marking property
boundaries and locations.
.2
Where monuments, pipes or stakes are located on the line of the trench or within the
limits of the work, the Owner will replace them.
.3
Do not remove survey monuments without receiving prior written approval. Pay for or
replace monuments which were removed without approval.
.4
The Contractor shall confirm location of all monuments provided by the City and notify
the Contractor Administrator if any are missing.
1.8
EXISTING SERVICES
.1
Before commencing work, establish location and extent of service lines in area of Work
and notify Engineer of findings.
.2
Remove abandoned service lines within 2 m of structures. Cap or otherwise seal lines at
cut-off points as directed by Engineer.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.9
SECTION 01720
PREPARATION, MOBILIZATION,
DEMOBILIZATION
PAGE 3 OF 5
The Contractor shall locate the IOS in the field at Site 5, within 10m of the IOS
Connection Chamber as indicated on the Contract Drawings, by drilling pilot holes to
locate the elevation of the IOS invert and the exact horizontal location of the IOS. The
IOS shall be located to the satisfaction of the Contract Administrator prior to
commencement of NST tunneling.
.2
The Contractor is to carry the cost of a minimum six (6) 50mm pilot holes in Tender
bid price and all associated labour, materials, pedestrian control and all other works
required to locate the IOS. The pilot holes shall be decommissioned thereafter and filled
with non-shrink grout.
.3
The Contractor shall survey the location of the IOS upon successful locating, survey the
IOS invert elevation and provide down hole CCTV to demonstrate that the pilot hole(s)
are located in the sewers obvert.
.4
The method noted herein is conceptual only; the Contractor shall submit a plan for
locating the IOS via pilot holes, or alternative method as proposed by the Contractor,
including shop drawings and methodology, to the Contract Administrator for review a
minimum of 14 days prior to commencing work.
.5
If this work is completed outside of the timeframe when the Contractor has full access to
Site 5 as outlined in Section 01117, the Contractor shall pay for and obtain all necessary
permit(s) to complete the work. This may include, but is not limited to, an NCC Access
Permit and RVAC Floodplain Permit.
1.10
The Contractor shall locate the 1350mm diameter Storm Sewer on Slater in the field
prior to commencing excavation or installation of excavation protection system for the
3000mm diameter shaft at Site 2.
.2
The Contractor shall survey the location of the Storm Sewer upon successful locating,
including the invert elevation, obvert elevation and outside of pipe wall location and
location(s) of any shoring or bracing adjacent to the Storm Sewer.
.3
The Contractor shall submit a plan for locating the Storm Sewer, including shop
drawings and methodology, to the Contract Administrator for review a minimum of 14
days prior to commencing work.
1.11
Mobilization shall include, but not be limited to, the following items:
.1
.2
.3
Moving in the Contractor and Engineers field offices and equipment required
within the first month after issuance of the Commence Work Order.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.12
SECTION 01720
PREPARATION, MOBILIZATION,
DEMOBILIZATION
PAGE 4 OF 5
.4
.5
.6
.7
.8
.9
Arranging for and erection of Contractors work and storage yard including
temporary fencing.
.10
.11
.12
.13
Removing debris and trash, etc as needed for Contractor to gain access to do the
Work.
.14
Mobilization of the TBM(s), batch plant, tools and materials for the assembly
and commissioning of the TBM(s).
.15
.16
.17
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01720
PREPARATION, MOBILIZATION,
DEMOBILIZATION
PAGE 5 OF 5
.3
Inform Engineer of impending installation and obtain approval for actual location.
.4
Submit field drawings to indicate relative position of various services and equipment
when required by Engineer.
1.13
RECORDS
.1
.2
.3
1.14
SUBMITTALS
.1
Submit name and address of Surveyor to Engineer. The surveyor (s) shall be a licensed
Ontario Land Surveyor and the qualification of the surveyor shall be submitted.
.2
.3
Submit site survey certificate signed by surveyor certifying those elevations and
locations of completed Work that conform and do not conform to the Contract
Documents.
1.15
SUBSURFACE CONDITIONS
.1
.2
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01740
CLEANING
PAGE 1 OF 3
Progressive cleaning
.2
Final cleaning
RELATED SECTION
.1
.2
1.3
REFERENCES
.1
City of Ottawa
.1
1.4
PROJECT CLEANLINESS
.1
Maintain Work in tidy condition, free from accumulation of waste products, graffiti and
debris, other than that caused by City or other Contractors.
.2
Remove waste materials from site at regularly scheduled times or dispose of as directed
by Engineer. Do not burn waste materials on site.
.3
Make arrangements with and obtain permits from authorities having jurisdiction for
disposal of waste and debris.
.4
Provide on-site containers for collection of waste materials, recycling and debris.
.5
Provide and use clearly marked separate bins for recycling. Refer to Section 01355 Disposal of Excess Material.
.6
Remove waste material and debris from site at end of each working day.
.7
.8
Clean interior areas prior to start of finish work, and maintain areas free of dust and other
contaminants during finishing operations.
.9
Store volatile waste in covered metal containers, and remove from premises at end of
each working day.
.10
.11
.12
Schedule cleaning operations so that resulting dust, debris and other contaminants will
not fall on wet, newly painted surfaces nor contaminate equipment systems.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.13
1.5
SECTION 01740
CLEANING
PAGE 2 OF 3
Conduct street sweeping and flushing at the instruction and to the satisfaction of the
Consultant, as per S.P. No.: F-8028.
FINAL CLEANING
.1
.2
Remove waste products and debris other than that caused by others, and leave Work
clean and suitable for occupancy.
.3
Prior to final review, remove surplus products, tools, construction machinery and
equipment.
.4
Remove waste products and debris other than that caused by City or other Contractors.
.5
Remove waste materials from site at regularly scheduled times or dispose of as directed
by Consultant. Do not burn waste materials on site.
.6
Make arrangements with and obtain permits from authorities having jurisdiction for
disposal of waste and debris.
.7
Clean and polish all hardware, mechanical and electrical fixtures. Replace broken,
scratched or disfigured glass.
.8
Remove stains, spots, marks and dirt from electrical and mechanical fixtures, walls, and
floors.
.9
.10
.11
Inspect finishes, fitments and equipment and ensure specified workmanship and
operation.
.12
Broom clean and wash exterior walks, steps and surfaces; rake clean other surfaces of
grounds.
.13
.14
.15
.16
Remove debris and surplus materials from crawl areas and other accessible concealed
spaces.
.17
.18
Clean shafts, buildings and structures, and tunnel to a sufficient level to allow safe
access and proper operation.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
SECTION 01740
CLEANING
PAGE 3 OF 3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
SECTION 01750
OPERATIONS AND MAINTENANCE MANUAL
PAGE 1 OF 5
This section includes requirements for the Operations and Maintenance Manual
(O&MM) Volume 2: Equipment and Material Information, which includes an organized
compilation of operating and maintenance data including detailed technical information,
documents and records describing operation and maintenance of individual products or
systems as specified in specification Sections.
1.2
RESPONSIBILITIES
.1
1.3
.1
Submit five (5) hardcopies and one (1) electronic copy of the draft Operations and
Maintenance Manual Volume 2 to Engineer for approval four (4) weeks prior to the start
of equipment performance testing. Submission of individual data will not be accepted
unless so directed by Engineer.
.2
Make changes as required and re-submit as directed by Engineer to the satisfaction of the
Engineer.
.3
Do not submit draft Operations and Maintenance Manual until the shop drawings for
equipment, material and field verified control circuit loop diagrams have been reviewed
by the Engineer and finalized.
1.4
GENERAL
.1
Upon approval of draft submission, submit five (5) final hardcopies and one (1)
electronic copy as per formatting Article 1.5.
.2
Submit final operation and maintenance manuals to Engineer three (3) weeks prior to
start of commissioning.
1.5
STANDARD FORMAT
.1
FORMATTING
.1
All text shall be ARIAL font. Title Pages, Pocket Inserts, Cover pages shall have
a text size of 14 point. The facility name shall have a text size of 16 point and in
bold. Remaining document text, including Section headings to be size 11 point.
.2
Paragraphs shall be single spaced and fully justified. There shall be one (1) blank
line between paragraphs, and two (2) blank lines at the end of a section.
.3
Section headings shall be in CAPITALS, bold and underlined. The spacing after
a Section heading shall be 16 point.
.4
Sub-section headings shall be in CAPITALS, and bold. The spacing after a subSection heading shall be 16 point.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.3
.5
Pages shall be 8.5 by 11, with Top Margin = 0.8, Bottom Margin= 0.8, Left
and Right Margins = 1.
.6
Each page shall include a section number and page number, centered in the
footer on each page. The footer shall be located 0.5 from the bottom of the
page.
.7
.8
O&M manuals to be provided in digital (PDF) format which are searchable (i.e.
native PDFs) and indexed for major sections. Each shop drawing and equipment
information shall be provided in discreet native PDF files.
BINDERS
.1
To have three "D" type rings, with clear vinyl pockets on the front and on the
spine to allow for the insertion of labels. The pockets are to be the full size of the
front and spine.
.2
The Contractor is to use the appropriate size of binder for the amount of
information that it is to contain and is to be loaded to no more than 80% of its
capacity the maximum binder width is to be 3 inches.
.3
POCKET INSERTS
.1
.2
.4
SECTION 01750
OPERATIONS AND MAINTENANCE MANUAL
PAGE 2 OF 5
Both the spine and the front pockets are to contain light coloured or white inserts
showing the following information:
.1
.2
.3
City Operations
.4
.5
.6
System (CSST) and specific Facility name, to have the largest and
boldest print
.7
.8
Volume number
.9
.10
.11
Date of Issue
All lettering on the cover pages must be machine-produced lettering using black
ink. Hand-written or laser originals are unacceptable.
FRONT PAGES
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
.1
Title Page - Provide the contract number, contract name, the volume
number and the date.
.2
Master Table Of Contents Summarize and list contents for all volumes
and binders.
.3
QUANTITY
.1
1.6
SECTION 01750
OPERATIONS AND MAINTENANCE MANUAL
PAGE 3 OF 5
Five (5) sets (hardcopies) of the manuals are to be supplied to the Consultant. If
more than one binder is required due to the quantity of information, then the
binders shall be designated "Binder 1 of #", "Binder 2 of #", etc.
STANDARD CONTENT
.1
.2
ORGANIZATION
.1
The manuals are to be organized so that the Divisions and Sections of the manual
correspond to the Divisions and Sections found in the standard 16 Division
contract document.
.2
Each binder shall have a table of contents at the beginning that lists all of the
Divisions and Sections contained in the binder. The front cover shall indicate
which Divisions are covered in each binder. Effort should be made to ensure that
a Division is not split between binders however in some cases it may not be
feasible.
.3
Each Division shall have a cover page listing the applicable Sections that it
contains. For Sections with numerous pieces of equipment, provide a list of the
equipment within the Section on the cover page. Separate equipment with a
coloured sheet of plain paper.
.4
Divisions that are not required in the manual due to no applicable equipment or
materials being provided will be identified in the cover sheet and Table of
Contents with the text Not Required.
.5
Provide Tabs for each Volume and Division. Provide Tabs for Sections when
Divisions have more than 2 Sections. Do not provide Tabs for Divisions that are
Not Applicable.
Section contents:
.1
The following information shall be provided for each system and major
piece of equipment. The list is intended to be comprehensive and will
include requirements not associated with every piece of equipment or
product. The intended use of this volume is to provide the operations
group with all information that has been developed or produced for the
materials and equipment they have purchased.
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01750
OPERATIONS AND MAINTENANCE MANUAL
PAGE 4 OF 5
.2
Operating instructions.
.3
.4
Installation instructions.
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
.15
.16
.17
.18
.19
Shop Drawings.
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
SECTION 01750
OPERATIONS AND MAINTENANCE MANUAL
PAGE 5 OF 5
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01770
CLOSEOUT PROCEDURES
PAGE 1 OF 2
.1
.2
1.3
.2
.2
.3
Work has been completed and inspected for compliance with Contract
Documents.
.2
.3
Equipment and systems have been tested, adjusted and balanced and are fully
operational.
.4
.5
.6
.4
Final Inspection: when items noted above are completed, request final inspection of
Work by City, Engineer, and Contractor. If Work is deemed incomplete by City and
Engineer, complete outstanding items and request reinspection.
.5
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01770
CLOSEOUT PROCEDURES
PAGE 2 OF 2
period and commencement of lien period unless required otherwise by lien statute of
Place of Work.
.7
Final Payment: When City and Engineer consider final deficiencies and defects have
been corrected and it appears requirements of Contract have been totally performed,
make application for final payment. If Work is deemed incomplete by City and Engineer,
complete outstanding items and request reinspection.
.8
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
1.2
SECTION 01780
CLOSEOUT SUBMITTALS
PAGE 1 OF 6
.2
.3
.4
.5
.6
.7
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
1.3
SUBMISSION
.1
Prepare instructions and data using personnel experienced in maintenance and operation
of described products as per Section 01750 Operations and Maintenance Manual.
.2
.3
.4
Four (4) weeks prior to the start of commissioning, submit to the Engineer, five (5) final
copies of operations and maintenance manuals in English.
.5
Ensure spare parts, maintenance materials and special tools provided are new,
undamaged or defective, and of same quality and manufacture as products provided in
Work.
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01780
CLOSEOUT SUBMITTALS
PAGE 2 OF 6
.7
.8
1.4
FORMAT
.1
.2
Drawings: provide with reinforced punched binder tab. Bind in with text; fold larger
drawings to size of text pages.
.3
.4
1.5
In addition to requirements in General Conditions, maintain at the site for Engineer one
record copy of:
.1
Contract Drawings
.2
Specifications
.3
Addenda
.4
.5
.6
.7
.8
Inspection certificates
.9
Manufacturer's certificates
.2
Store record documents and samples in field office apart from documents used for
construction. Provide files, racks, and secure storage.
.3
Label record documents and file in accordance with Section number listings in List of
Contents of this Project Manual. Label each document "PROJECT RECORD" in neat,
large, printed letters.
.4
Maintain record documents in clean, dry and legible condition. Do not use record
documents for construction purposes.
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.6
SECTION 01780
CLOSEOUT SUBMITTALS
PAGE 3 OF 6
Record information on set of black line opaque drawings, and in copy of Project Manual,
provided by Engineer.
.2
Provide felt tip marking pens, maintaining separate colours for each major system, for
recording information.
.3
Record information concurrently with construction progress. Do not conceal Work until
required information is recorded.
.4
Contract Drawings and shop drawings: legibly mark each item to record actual
construction, including as a minimum:
.5
.6
1.7
.1
.2
.3
.4
Tunnel and shaft reports and surveyed data as detailed in division 2 tunnel and
shaft specifications.
.5
.6
.7
.8
.2
.1
1.8
Submit final site survey certificate in accordance with Section 01720 - Preparation,
Mobilization, Demobilization certifying that elevations and locations of completed Work
are in conformance, or non-conformance with Contract Documents.
EQUIPMENT AND SYSTEMS
.1
Each Item of Equipment and Each System: include description of unit or system, and
component parts. Give function, normal operation characteristics, and limiting
conditions. Include performance curves, with Consulting data and tests, and complete
nomenclature and commercial number of replaceable parts.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01780
CLOSEOUT SUBMITTALS
PAGE 4 OF 6
.2
Panel board circuit directories: provide electrical service characteristics, controls, and
communications.
.3
.4
.5
.6
.7
.8
.9
Provide original manufacturer's parts list, illustrations, assembly drawings, and diagrams
required for maintenance.
.10
.11
Provide Contractor's coordination drawings, with installed colour coded piping diagrams.
.12
Provide charts of valve tag numbers, with location and function of each valve, keyed to
flow and control diagrams.
.13
Provide list of original manufacturer's spare parts, current prices, and recommended
quantities to be maintained in storage.
.14
Include test and balancing reports as specified in Section 01450 - Quality Control and
Section 01810 - Commissioning.
.15
1.9
Building Products, Applied Materials, and Finishes: include product data, with catalogue
number, size, composition, and colour and texture designations. Provide information for
re-ordering custom manufactured products.
.2
Instructions for cleaning agents and methods, precautions against detrimental agents and
methods, and recommended schedule for cleaning and maintenance.
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.10
SECTION 01780
CLOSEOUT SUBMITTALS
PAGE 5 OF 6
SPARE PARTS
.1
.2
.3
.4
Receive and catalogue all items. Submit inventory listing to Engineer. Include approved
listings in Maintenance Manual.
.5
Obtain receipt for delivered products and submit prior to final payment.
1.11
MAINTENANCE MATERIALS
.1
.2
.3
.4
Receive and catalogue all items. Submit inventory listing to Engineer. Include approved
listings in Maintenance Manual.
.5
Obtain receipt for delivered products and submit prior to final payment.
1.12
SPECIAL TOOLS
.1
.2
Provide items with tags identifying their associated function and equipment.
.3
.4
Receive and catalogue all items. Submit inventory listing to Engineer. Include approved
listings in Maintenance Manual.
1.13
Store spare parts, maintenance materials, and special tools in manner to prevent damage
or deterioration.
.2
Store in original and undamaged condition with manufacturer's seal and labels intact.
.3
.4
.5
Remove and replace damaged products at own expense and to satisfaction of Engineer.
1.14
Separate each warranty or bond with index tab sheets keyed to Table of Contents listing.
.2
List subcontractor, supplier, and manufacturer, with name, address, and telephone
number of responsible principal.
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01780
CLOSEOUT SUBMITTALS
PAGE 6 OF 6
.5
Verify that documents are in proper form, contain full information, and are notarized.
.6
.7
.8
Extended Warranties:
.1
Unless noted otherwise, Extended Warranties shall commence upon the expiry
of the contract warranty period.
.2
Extended Warranty for the specified components and/or system will remain in
effect for the number of years as specified in the individual specification
sections.
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
NOT USED
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
.1
.2
1.2
SECTION 01810
COMMISSIONING
PAGE 1 OF 23
General requirements for testing and commissioning unit processes, subsystems, facilities and the overall CSST system.
.1
.2
.3
.4
.5
.6
.7
.8
Division 5 - Metals
.9
Division 11 - Equipment
.10
.11
Division 15 - Mechanical
.12
Division 16 - Electrical
1.3
DEFINITIONS
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 2 OF 23
.3
.4
.5
.6
.7
.8
.9
Functional Test: Test or tests conducted in the presence of the Engineer and
Owner to demonstrate a system or component of a system and its operational
effectiveness and suitability in meeting its specified performance criteria under
various operating conditions. Includes field tests repeated with the Engineer and
Owner as witness.
.10
Performance Test: Test or tests conducted to evaluate the system and all facilities
and sub-systems within, to meet the project-specific process performance
requirements. These tests involve operating equipment in conjunction with the
City-programmed PLC.
.11
.12
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 3 OF 23
.13
.14
Wet Test: A test performed in the presence of the Engineer and City to
demonstrate that the unit process, sub-system or equipment can operate
successfully in or when exposed to water in preparation for facility/system startup.
.15
1.4
.2
Pre-Commissioning Phase
.2
Commissioning Phase
Field Testing
.1
.2
Functional Testing
.1
.3
.3
Performance Testing
.1
.2
The final Commissioning phase shall begin following Performance Testing and
substantial completion of the Works and shall continue throughout the project
warranty period and until a minimum of three (3) rainfall events have occurred
causing activation of the tunnel filling and dewatering processes. If the warranty
period expires and less than three rainfall activation events have occurred, the
Commissioning Phase will continue until this requirement is satisfied.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.1
1.5
SECTION 01810
COMMISSIONING
PAGE 4 OF 23
GENERAL
.1
The Commissioning Plan for the Works shall be prepared by the Contractor and
submitted to the Engineer and the City for review eight (8) weeks prior to the
proposed start date of any testing or other pre-commissioning activities at any
particular site or facility. Contractor shall provide allow a minimum of four (4)
weeks for review by the Engineer and the City. Final Commissioning Plan shall be
submitted to the Engineer at least two (2) weeks prior to the planned start of the
pre-commissioning.
.2
The Contractor, Engineer, and the City shall jointly commission the works in
accordance with the reviewed commissioning plan. The Contractor shall provide
sufficient manpower and necessary tools for the duration of the commissioning
process, including both Pre-commissioning and final Commissioning Phases. This
will include manpower necessary to monitor and maintain the works in operation
outside normal working hours to ensure continuous operation of the works as per
intended design. The Contractor shall make necessary adjustments during the
commissioning process to put the works into continuous operation as per intended
design. Any special tools shall be turned over to the City following Precommissioning.
.3
.4
.5
Cooperate with Citys operating personnel and provide access to equipment and
systems. Notify the Engineer and Citys operating personnel at least 7 days prior
to time that any facility and all sub-systems and unit processes contained within
will be ready for testing, adjusting, and balancing.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 5 OF 23
.6
The Contractor shall accept the direction and co-ordination assistance of the
Engineer throughout the commissioning process.
.7
The Contractor shall provide its own personnel or sub-contractor to direct and
supervise the entire commissioning process, including pre-commissioning in
coordination with the Owner and Engineer. The Citys operating personnel cannot
be hired for the supervision of the commissioning but will have access for
optional surveillance of the commissioning.
.8
.9
Provide tools and personnel and operate unit processes, sub-systems, and
equipment at designated times, and under conditions required for proper testing,
adjusting, and balancing.
.10
The Contractor shall supply and install the utilities (potable water, electricity,
heating), chemicals/gases (i.e. for odour control units and gas alarms) and testing
equipment required during the commissioning process at his own expense.
.11
.12
.13
.14
All components and systems shall be operated and tested in the automatic/manual
and the remote/local modes as required to provide proper operation. The
Contractor shall coordinate with City operating personnel for testing of subsystems and facilities and inter-site operation requiring programmed logic.
.15
Where applicable, and under the supervision and direction of the Engineer and
City personnel, wastewater shall be connected and introduced to the system or
facility in a manner which precludes the damage to any equipment or structures.
Upon completion of the RCI Diversion Chamber and removal of the Contractors
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 6 OF 23
flow management system, raw sewage will be flowing through the structure at
Site 3a during dry weather conditions. All other sites containing equipment are
anticipated to be exposed to combined sewage flows under wet weather
conditions.
.16
Ensure that any and all temporary bypasses and backup provisions installed for the
commissioning process function to the satisfaction of the Engineer and the City
prior to implementation.
.17
All minor and major alarm conditions will be induced to ensure that the process
reacts as intended, and the applicable alarms are annunciated.
.18
.19
Should the field, functional, or performance tests reveal any defects, then these
defects shall be promptly rectified and the field, functional, and/or performance
tests shall be repeated to the satisfaction of the Engineer. Additional costs
incurred by Contractor, the Engineer, or the City, due to repeat field, functional,
and/or performance tests shall be the responsibility of the Contractor.
.20
Accurately record data for each step of the commissioning process to be included
in the commissioning report.
.21
.22
.23
The Contractor shall update the schedule of events throughout the commissioning
process.
.24
.25
The Contractor shall affix to the tested equipment a 100mm by 200mm yellow
card reading Operable Condition Do not Operate without Contractors
Permission stenciled on in large black letter.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.26
1.6
SECTION 01810
COMMISSIONING
PAGE 7 OF 23
Refer to individual Divisions and Sections for other detailed requirements about
the testing of specific unit process, sub-systems, or equipment.
QUALITY ASSURANCE
.1
.2
.3
1.7
REFERENCES
.1
1.8
.1
.2
Commissioning Plan:
.1
Within 5 working days after the first testing and commissioning meeting, as
specified in Section 01220 Project Meetings, submit five (5) hardcopies
and one (1) electronic copy of draft testing and commissioning plan
including all field testing, functional testing, performance testing, facility
startup, and System Startup. Plan shall be submitted to the Engineer and the
City for review at least eight (8) weeks before the planned start of any
testing or other pre-commissioning activities. Five (5) hardcopies and one
(1) electronic copy of the final commissioning plans shall be submitted to
the Engineer at least two (2) weeks prior to the planned start of the precommissioning. The Contractor shall prepare and submit pre start-up and
calibration reports for all equipment as required in their respective Sections
prior to, or in tandem with, submission of the final commissioning plan.
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 8 OF 23
.2
Provide a brief outline description of the unit process, subsystem or equipment and location within the facility involved.
.3
.4
.5
List and detail all temporary equipment (pump, valve, pipe, etc.)
and installations planned to allow field, functional, and
performance testing to take place.
.6
.7
.8
.9
.10
.11
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 9 OF 23
.12
.13
.14
.3
The Contractor shall prepare and submit pre start-up and calibration reports for all
equipment as required in their respective Sections prior to, or in tandem with,
submission of the commissioning plan.
.4
The Contractor will develop test documentation forms specific for each unit
process, sub-system, equipment and/or associated equipment items installed under
this Contract. Acceptable documentation forms for all unit process, sub-system,
equipment and/or associated equipment will be produced for review by the
Engineer a minimum of two (2) weeks prior to any functional testing. Once the
Engineer has reviewed and taken no exception to the forms proposed by the
Contractor, the Contractor will produce sufficient forms, at his expense, to
provide documentation of all testing work to be conducted as a part of this
contract. The following is a partial list of report documents to be included.
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
.15
Pressure/Hydrostatic Tests
.16
Leakage / Seal Test Reports (for gaseous and liquid containing systems)
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
SECTION 01810
COMMISSIONING
PAGE 10 OF 23
.17
.18
.19
.20
.21
.22
.23
The Contractor shall compile, maintain, make available for Engineers review and
submit the following documentation at least two (2) weeks prior to entering into
the commissioning phase at any particular site. The Contractor shall populate each
section with the prescribed documentation produced as a result of all activities
associated with pre-commissioning tasks that include, but are not limited to, the
following documents:
.1
.2
.3
.4
.5
.6
.6
.7
Commissioning Report
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 11 OF 23
.8
1.9
.1
.2
.3
.4
.5
.6
.7
.1
.2
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
3.2
SECTION 01810
COMMISSIONING
PAGE 12 OF 23
.1
.2
.3
General:
.1
.2
.3
.4
.5
.6
.7
.8
Test Report Form: Provide written test report form for each item of equipment to
be tested, to include the following minimum information:
.1
City/Project Name.
.2
.3
.4
.5
Test conditions.
.6
Test results.
.7
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.3
SECTION 01810
COMMISSIONING
PAGE 13 OF 23
.3
.4
.5
Open and close valves by hand and operate other devices to check for
binding, interference, or improper functioning.
.6
.7
.8
.9
.10
Piping, wiring and the conduit systems shall be finished and tested.
.11
.12
.13
.14
.15
.16
.17
.18
FIELD TEST
.1
The Contractor shall notify the Engineer of his readiness to start up and test the
equipment a minimum of two (2) weeks in advance. The Engineer, City
representative shall attend if deemed appropriate.
.2
The Contractor shall operate the unit process, sub-system, and/or equipment for at
least one (1) hour or as suggested by the manufacturers representative to
demonstrate to him the operation of the equipment and any required ancillary
services. Any remedial measures required to ensure satisfactory operation shall be
promptly undertaken.
.3
All control loop and/or I/O checks must be complete with no outstanding issues,
all control diagrams and wiring drawings must be marked-up to reflect actual
construction status, and draft O &M Manual completed and submitted to
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 14 OF 23
Engineer. The Engineer will confirm that these conditions are met before the
Contractor can proceed to functional testing.
.4
3.4
Functional tests shall not be scheduled concurrently or subsequent to the field test,
unless agreed to by the Engineer.
FUNCTIONAL TEST
.1
The Contractor shall notify the Engineer of his readiness to demonstrate the
operation of the unit process, sub-system, and/or equipment submitting to the
Engineer all required documentation a minimum of two (2) weeks in advance.
The Engineer and City representative shall attend all functional testing.
.2
Ready-to-test determination will be made by the Engineer based at least on but not
limited to the following:
.1
.2
Field Test Report including but not limited to documentation that all
equipment, controls and instrumentation has been installed, calibrated and
field tested.
.3
.4
.5
.6
.7
.8
.9
.3
.4
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 15 OF 23
the Engineer. Detailed equipment specifications may require longer durations than
one hour refer to individual specifications. Local and Remote-Manual control
shall be satisfactorily verified by cycling the equipment or sub-systems through
several start-stop operations, modulating its output, or some combination.
Operating parameters such as temperature, pressure, voltage, vibration, etc. will
be checked to ensure that they are within the specified Manufacturers
recommended limits, whichever is more stringent. Hardwired interlocks between
various equipment and/or unit processes shall be tested and verified.
.6
The Owner or Engineer may, at their own discretion, order additional or modified
tests to be conducted in field, even if not explicitly listed in the Functional Testing
Plan. Operating conditions for each test shall ultimately be determined by the
Owner and Engineer.
.7
3.5
PERFORMANCE TEST
.1
General
.1
The performance test shall consist of two (2) stages and completed in the
following order:
.1
.2
.2
.3
.4
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
SECTION 01810
COMMISSIONING
PAGE 16 OF 23
.3
.4
.5
As determined by Engineer.
.5
.6
New equipment will be started and run for three (3) days for each wet
testing stage, of which the last twenty-four hours shall be consecutive.
During the performance testing period, as practical, conditions will be
simulated which represent maximum or most severe, average, and minimum
or least severe conditions. These conditions will be mutually agreed by the
Contractor and Engineer on the basis of the information contained in the
technical specifications, as well as the methods utilized to create the
simulated conditions and the time periods allotted to each.
.7
.8
Performance testing shall not commence until equipment has been approved
by the Engineer as having satisfied functional test requirements specified.
.9
.10
Source and type of fluid, gas, or solid for testing shall be as specified.
.11
Unless otherwise indicated, furnish all labor, materials, and supplies for
conducting the wet tests and taking all samples and performance
measurements.
.12
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.1
.2
Wet Testing may include, but is not limited to, the following:
.3
.1
.2
.3
City Responsibilities:
.1
.4
.3
SECTION 01810
COMMISSIONING
PAGE 17 OF 23
Contractor Responsibilities:
.1
.2
.3
.4
.5
.6
Cooperate with the Engineer and Citys operating staff for the
duration of testing.
.7
Provide labor, equipment and tools as required for the duration of the
testing.
.2
SCADA SAT Testing may include, but is not limited to, testing of
equipment response to various site operating conditions and
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 18 OF 23
.4
.5
.6
City Responsibilities:
.1
.2
Contractor Responsibilities:
.1
Cooperate with the Engineer and Citys operating staff for the
duration of testing.
.2
Provide labor, equipment and tools as required for the duration of the
testing.
.3
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.6
SECTION 01810
COMMISSIONING
PAGE 19 OF 23
COMMISSIONING PHASE
.1
.2
Following successful of all facilities the City will place the new, refurbished and
reconstructed works into continuous operation. The Contractor shall, have
supervisory personnel, mechanics, electricians, instrument technicians, and other
workmen on call to attend to any adjustments and corrections required.
.3
.4
General
.1
.2
.2
.3
.4
.5
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 20 OF 23
warranty period, barring any significant interruptions, and the CSST system
has operated as intended and trouble-free throughout a minimum of three
(3) separate activation rainfall events in which the system is filled and
dewatered as designed, and all process, mechanical and electrical equipment
is free of vibration, overloading, or overheating, and is functioning in
accordance with specified rates, methods, and performance. In the event of a
failure of the identified components that are to be tested, the number of
successful activation events will be re-set to zero and retested for the full
duration.
3.7
.2
All analysis instruments, sensors and gauges used for performance testing will be
subject to recalibration to confirm accuracy after completion, but prior to
acceptance of each performance test. All analysis instruments, sensors and gauges
installed under this contract will be subject to recalibration as a condition
precedent to Commissioning under the provisions of this section.
END OF SECTION
SUPPLEMENTAL INFORMATION
CERTIFICATE OF READINESS TO INSTALL FORM 101
CERTIFICATE OF SATISFACTORY INSTALLATION FORM 102
CERTIFICATE OF EQUIPMENT SATISFACTORY PERFORMANCE FORM 103
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 21 OF 23
FORM 101
PROJECT:
OWNER:
EQPT/SYSTEM::
MANUFACTURER:
SPEC. SECTION:
I have familiarized the contractors installer (s) of the specific installation requirements related to the
equipment listed above and am satisfied that he (they) understands the required procedures.
____________________________________
_______________
MANUFACTURERS REPRESENTATIVE
DATE
___________________________________________
______________
DATE
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 22 OF 23
EQPT/SYSTEM::
MANUFACTURER:
SPEC. SECTION:
I have completed my check and inspections of the installation listed above and herby certify that the
above-referenced equipment has been:
(Check Applicable)
_____ Installed in accordance with Manufacturers recommendations
_____ Inspected, checked and adjusted
_____ Serviced with proper initial lubricants
_____ Electrical, mechanical and instrumentation connections meet quality and safety standards and
_____ All applicable safety equipment has been properly installed
I also confirm that the installation is satisfactory and that defects have been remedied to my satisfaction
except any as noted below.
COMMENTS:
____________________________________
_______________
MANUFACTURERS REPRESENTATIVE
DATE
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01810
COMMISSIONING
PAGE 23 OF 23
EQPT/SYSTEM::
MANUFACTURER:
SPEC. SECTION:
We certify that the equipment listed above has been operated for at least three days of which the last
twenty-four hours were consecutive and that the equipment operates satisfactorily and meets its specified
operating criteria. No defects in the equipment were found. The equipment is therefore classed as
conforming.
___________________________________
MANUFACTURERS REPRESENTATIVE
_____________
DATE
___________________________________________
______________
DATE
___________________________________
REPRESENTATIVE OF THE ENGINEER
(Print Name and Authorized Signature)
______________
DATE
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
SECTION 01820
DEMONSTRATION AND TRAINING
PAGE 1 OF 5
This section includes procedures for demonstration and instruction of equipment and
systems to City's personnel.
1.2
RELATED SECTIONS
.1
.2
.3
1.3
DESCRIPTION
.1
.2
City will provide list of personnel to receive instructions, and will coordinate their
attendance at agreed-upon times.
.3
The demonstration and training shall be provided at least two (2) weeks prior to the start
of commissioning. The contractor shall coordinate the schedule with the City and the
manufacturers representatives in advance for their attendance.
.4
Training should include both classroom discussion to present the materials and in-field
demonstration of each system as required to ensure that all City Operators clearly
understand the system after training.
.5
Contractor to arrange minimum two (2) separate training sessions with all major
manufacturers representatives present to demonstrate their equipment. The separate
training sessions will not be on consecutive days. Training is to be scheduled on
Tuesdays and/or Thursdays.
1.4
QUALITY CONTROL
.1
Qualified Trainer:
.1
The Contractor shall provide the specified on-the-job training of the Citys
operating and maintenance staff for the maintenance of equipment. The training
sessions shall be conducted by qualified and experienced (2 years minimum)
factory trained representatives from the various equipment manufacturers.
Training shall include instruction of operating personnel in equipment operation
and preventative maintenance and instruction of mechanics, electricians and
electronics technicians in normal maintenance up to major repair.
.2
At least two (2) weeks prior to the training, submit the qualifications and
experiences of the proposed trainers to the Engineer for approval.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
1.5
SECTION 01820
DEMONSTRATION AND TRAINING
PAGE 2 OF 5
Submit schedule of time and date for demonstration and training sessions at least two (2)
weeks prior to designated training dates for Engineer's approval.
.2
Submit fifteen (15) copies of the following training information to the Engineer. Due to
phased testing and commissioning activities, separate submittals can be prepared for
equipment items or systems. The material shall be reviewed and accepted by the
Engineer no later than two (2) weeks prior to the scheduled training sessions.
.1
.2
All training manuals, handouts, visual aids and other reference materials shall be
provided to attendees.
.3
Date, time, and subject of each training session with identity and qualifications
of individuals to be conducting the training.
.3
.4
.5
Submit reports within one (1) week after completion of demonstration, that
demonstration and instructions have been satisfactorily completed. Give time and date of
each demonstration with list of persons present.
.6
Submit electronic version of training documents in searchable PDF format to the City.
1.6
Equipment has been inspected, tested and put into operation in accordance with Section
01810 Commissioning.
.2
.3
Part 2
Products
2.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.2
.3
Instrumentation 4 hours
.4
Mechanical 4 hours
.5
Electrical 4 hours
.6
PLC 4 hours
SECTION 01820
DEMONSTRATION AND TRAINING
PAGE 3 OF 5
LESSON PLAN
.1
.2
.3
.4
.5
.6
Part 3
Execution
3.1
PREPARATION
.1
Verify that conditions for demonstration and instructions comply with requirements.
.2
3.2
.2
Instruct personnel in all phases of operation and maintenance using operation and
maintenance manuals as the basis of instruction.
.3
Review contents of manual in detail to explain all aspects of operation and maintenance.
.4
Prepare and insert additional data in operations and maintenance manuals when the need
for additional data becomes apparent during instructions.
3.3
TRAINING REQUIREMENTS
.1
The Contractor shall conduct training sessions for the Citys operating and maintenance
staff to instruct on the proper operation, care and maintenance of the equipment and
systems installed under this contract. Training shall take place at the site of the work and
under the conditions as specified.
.2
Field training session shall take place at the site of the equipment.
.3
Formal written lesson plans shall be prepared for each training session. Lesson plans
shall contain an outline of the material to be presented along with a description of visual
aids to be utilized during the session. Each plan shall contain a time allocation for each
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 01820
DEMONSTRATION AND TRAINING
PAGE 4 OF 5
subject. One complete set of the originals of the lesson plans; training manuals,
handouts, visual aids and reference material shall be the property of the City and shall be
properly bound and organized for easy reproduction of any section as required. The
Contractor shall furnish fifteen (15) copies of training manuals, handouts, visual aids and
reference materials at least two (2) weeks prior for each training session.
.4
.5
3.4
Each training session shall be comprised of time spent both in the classroom and training
session shall cover the following topics for each item of equipment or system:
.1
Familiarization
.2
Safety
.3
Operation
.4
Troubleshooting
.5
Preventive maintenance
.6
Corrective maintenance
.7
Parts
.8
Local representatives
.9
.1
As a minimum, the Contractor shall provide classroom equipment training for operating
and maintenance staff and shall include the following:
.1
Videos, slides and or drawings, for discussion of the specific equipment, its
location in the facility and an operation overview.
.2
.3
.4
.5
.6
.7
.8
.9
.10
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.11
3.5
SECTION 01820
DEMONSTRATION AND TRAINING
PAGE 5 OF 5
Locate and identify the equipment in the facility and review its function and
theory of operation.
.2
.3
.4
.2
.3
.5
.6
.7
.8
.9
.10
.11
.12
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02072
GEOTEXTILES
PAGE 1 OF 3
PART 1 - GENERAL
1.1
RELATED SECTIONS
.1
.2
1.2
REFERENCES
.1
.2
.2
.3
1.3
SUBMITTALS
.1
.2
1.4
1.5
During delivery and storage, protect geotextiles from direct sunlight, ultraviolet rays,
excessive heat, mud, dirt, dust, debris and rodents.
WASTE MANAGEMENT AND DISPOSAL
.1
Separate waste materials for reuse and recycling in accordance with Section 01355 Disposal of Excess Material.
PART 2 - PRODUCTS
2.1
MATERIAL
.1
.2
.3
.4
Physical properties:
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.5
.2
SECTION 02072
GEOTEXTILES
PAGE 2 OF 3
Hydraulic properties:
.1
.2
.6
.7
.8
.9
Thread for sewn seams: equal or better resistance to chemical and biological
degradation than geotextile.
Non-Woven Geotextile: AASHTO M288, Class 3..8 Turf Reinforcement Mat: North
American Green C350 (or approved equal) permanent turf reinforcement mat. Mat shall
consist of evenly distributed 100 percent coconut fiber matrix weighing 0.50 lbs per SY
(0.27 kg/sq m) encapsulated in a 3-D matting structure consisting of two, top and
bottom, heavyweight UV stabilized polypropylene nets, with a nominal weight of 8
lbs/1000 SF (0.04 kg/sq m) and a corrugated high strength center net with an nominal
weight of 24 lbs/1000 SF (0.12 kg/sq m). The three nets shall be stitched together on
1.50 inch (38 mm) centers with UV stabilized polypropylene thread to form a permanent
three-dimensional turf reinforcement mat with a minimum thickness of 0.5 inches (13
mm).
PART 3- EXECUTION
3.1
INSTALLATION
.1
Place geotextile material by unrolling onto graded surface in orientation, manner and
locations indicated and retain in position with gradient.
.2
Place geotextile material smooth and free of tension stress, folds, wrinkles and creases.
.3
Place geotextile material on sloping surfaces in one continuous length from toe of slope
to upper extent of geotextile.
.4
Overlap each successive strip of geotextile 600 mm over previously laid strip.
.5
Pin successive strips of geotextile with securing pins at 1220 mm interval at mid point of
lap.
.6
.7
.8
.9
Place and compact soil layers in accordance with Section 02315 Excavating, Trenching
and Backfilling.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.2
SECTION 02072
GEOTEXTILES
PAGE 3 OF 3
CLEANING
.1
3.3
Remove construction debris from Project site and dispose of debris in an environmentally
responsible and legal manner.
PROTECTION
.1
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
SECTION 02140
GROUNDWATER CONTROL
PAGE 1 OF 12
.1
.2
.3
.4
Active dewatering systems, such as those using methods that include, but are not limited
to, deep gravity wells, vacuum well points, vacuum lances, eductor wells, and any
combinations thereof, are not allowed at any shaft or structure site or at any location
along the tunnel alignment.
.5
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02140
GROUNDWATER CONTROL
PAGE 2 OF 12
and Sediment Control Plan. In the event of any conflict between the requirements stated
in this Section and those stated in Section 01160, Erosion and Sediment Control Plan, the
more stringent requirements shall take precedence.
.7
Dispose of removed water in a manner that conforms to all applicable laws and
regulations, and any required agreements or permits.
.8
Permits:
.9
1.2
.1
.2
All work and costs relating to obtaining the final PTTW; compliance with the PTTW,
including sampling, metering / measuring, reporting and treatment of construction water;
as well as all work and costs related to control of water for construction purposes,
including treating and discharging construction water, except as may be identified
elsewhere in the Contract Documents, are deemed to be incidental to the work and costs
associated with each respective bid item for those contract elements for which control of
water and compliance with the PTTW are required.
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
1.3
REFERENCE STANDARD
.1
.2
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.4
SECTION 02140
GROUNDWATER CONTROL
PAGE 3 OF 12
DEFINITIONS
.1
.2
Tunnel Construction Water: All water, whatever the source, pumped from shaft and
tunnel excavations.
.3
Control of Surface Drainage: The diversion of surface water away from excavations by
earth barriers, ditches or other means stated in Section 01160, Erosion and Sediment
Control Plan.
.4
Dewatering: Using active measures to lower the groundwater table and intercept seepage
that would otherwise emerge from excavation perimeters or bases, or into tunnels and
shafts. As stated in Paragraph 1.1.4 of this Specification, dewatering is not permitted on
this Contract.
.5
.6
Groundwater control: Includes unwatering activities, which are those activities that
exclude groundwater from infiltrating excavations, and those activities that involve
collecting and discharging groundwater that has infiltrated tunnels, shafts or other
excavations. Groundwater control also includes grouting or ground improvement
activities that are intended to reduce permeability of the subsurface materials around an
excavation to exclude or limit the rate of groundwater infiltration, or the use of
watertight excavation support systems.
.7
Sumping or Sump Pumping: The provision of sumps in excavations, along with all
necessary piping, ditches, pumps and other equipment necessary to collect and convey
construction water outside the excavation area according to the Construction Water
Discharge Plan prepared by the Contractor and accepted by the Engineer.
1.5
SUBMITTALS
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02140
GROUNDWATER CONTROL
PAGE 4 OF 12
.2
.2
.2
.3
Shop drawings of temporary tunnel and shaft sump locations, and pump
and discharge piping layouts.
.4
.5
.6
.7
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.3
1.6
SECTION 02140
GROUNDWATER CONTROL
PAGE 5 OF 12
.1
.2
Chemical grouts
.3
.4
.2
Testing method that will be used to demonstrate water has been treated
in accordance with this Specification, agreements or permits obtained by
the Contractor and applicable regulations prior to disposal
.3
.4
.5
.6
.1
The Contractor acknowledges that it is aware that the awarding of this Contract, and/or
release of the Commence Work Order, are subject to obtaining the following approvals:
.1
.2
.2
The Contractor shall not make any claims for additional costs or expenses due to delays
in the commencement of work (or portions thereof). The Contract Substantial
Performance and Project Completion dates will be adjusted to account for delays to
release of the Commence Work Order.
.3
The Contractor is made aware that the City has applied for an ECA for the construction
and operation of the system. A copy of the ECA will be provided to the NCC and
PWGSC at least 10 working days prior to commencement of work.
.4
The Contractor is made aware that the City has applied for a draft Permits to Take Water
(PTTW) for the works. The application for the draft PTTW was developed with
consideration for the baseline infiltration rates discussed in the GBR and requirements
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02140
GROUNDWATER CONTROL
PAGE 6 OF 12
.2
.3
.4
.5
Upon receipt and satisfaction with the information provided by the Contractor, the
PTTW Director will append the Contractor submissions to the PTTW application and
will issue the PTTW to the Contractor. If the Contractor significantly changes the
assumptions used as a basis for the draft PTTW, a new application will be required as
detailed below under Contractor's Responsibilities and Limitations.
.6
Upon receipt of the PTTW, the Contractor shall provide to the Engineer a copy of the
PTTW issued in its name.
.7
The PTTW is to be provided to the NCC and PWGSC at least 10 working days prior to
commencement of work. The PTTW will be provided to the NCC and the PWGSC by
the Contract Administrator.
.8
The Contractor shall submit to the MOECC, with a copy to the Engineer, any monitoring
results, including records of water takings, or other information as required by the PTTW
at the frequency specified by the PTTW.
.9
The PTTW Director will only issue a Permit to the Contractor to authorize water-taking
in accordance with the application submitted by the City to obtain the draft PTTW. Any
request for increased water taking or any change in the management of water taking and
return flows that cannot be reconciled against the PTTW Director's technical evaluation
of the City-submitted application submission will require a new application and shall be
the sole responsibility of the Contractor.
.10
The Contractor acknowledges and agrees that it will not seek additional compensation
for time delay or cost associated with preparing and submitting a new application to the
PTTW Director, inclusive of any resulting time delay to commencement of work.
1.7
PROTECTION
.1
Take all necessary precautions consistent with restrictions stated in this Section to
prevent uplift of any structure or pipeline prior to completion and backfilling of the
structure or pipeline.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
1.8
SECTION 02140
GROUNDWATER CONTROL
PAGE 7 OF 12
Protect all excavations against flooding and damage due to surface run-off.
PERFORMANCE REQUIREMENTS
.1
The Geotechnical Baseline Report (GBR) describes the groundwater conditions that the
Contractor should expect for tunnels and shafts during construction, and more
particularly states baseline groundwater infiltration rates that the Contractor should
anticipate. The volumes and infiltration rates discussed in the GBR do not include
service water introduced into the tunnel, shafts and other excavations as a result of the
Contractors activities nor any surface water or precipitation that may enter tunnel, shaft
or other excavations. The Contractor shall allow for all such water flows in sizing
pumps, piping and all other elements of systems to control construction water, and be
prepared to remove water and prevent water from entering shafts and tunnels.
.2
Develop tunnel construction water control systems as necessary to control all tunnel
construction water, including baselined infiltration rates for specifically identified
excavations, with consideration for limits set in the PTTW.
.3
Provide means to control drainage of seepage water, surface water and precipitation in
shafts and tunnels, as well as water from any other source entering the excavation to
prevent impact to construction operations due to water inflow. Excavation drainage may
include placement of drainage materials, such as crushed stone, together with sump
pumping.
.4
.5
.6
1.9
.1
.2
.3
.4
.5
.1
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to control groundwater as specified
herein and no separate payment shall be made.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.10
SECTION 02140
GROUNDWATER CONTROL
PAGE 8 OF 12
QUALITY ASSURANCE
.1
Qualifications
.1
Part 2
Products
2.1
Equipment, materials and facilities are at the option of the Contractor as necessary to
achieve desired and required results, unless specified otherwise in the Contract
Documents.
.2
.3
Arrange for standby equipment and materials where necessary or required in this
Specification.
.4
Generators and other equipment shall have effective muffling devices as required to keep
noise levels within limits specified in City regulations or as otherwise specified in the
Contract Documents.
.5
Flow meters:
.1
.2
.3
.6
Provide a totalizing flow meter on each tunnel construction water discharge line
and on each service water influent line.
Provide a totalizing flow meter on each shaft or excavation construction water
discharge line and on each service water influent line.
Flow meters shall be designed to measure water flows with an accuracy of 0.5
per cent across the full measuring range of the meter. Flow meters shall be
installed according to manufacturers instructions.
Part 3
Execution
3.1
GENERAL
.1
Adequacy of operations: Ensure that water control operations are adequate to protect the
integrity of the work in progress and the finished product, to protect adjacent structures
and facilities, and to satisfy discharge water quality required for the project.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02140
GROUNDWATER CONTROL
PAGE 9 OF 12
.2
Discontinue open pumping from sumps and ditches, if such pumping is resulting in boils,
loss of fines, softening of the ground, or instability of excavation perimeter walls or
excavation base. Modify the relevant control of water plan and submit to the Engineer at
no additional cost to the City.
.3
.2
.3
.4
.4
Maintenance
.1
.2
.3
.4
3.2
Install, maintain, monitor and take readings from flow meters or other flow
measuring devices set to measure the volumes of construction water pumped
from the tunnels, shafts and other project excavations. Provide separate
measurements for each tunnel drive, each shaft and each excavation. Tunnel
construction water may be aggregated for measurement purposes at the time that
shaft excavations are connected to tunnel excavations or that tunnel segments are
connected to each other via shaft or chamber excavations. However, the
Engineer reserves the right to subsequently require separate measurements if
necessary for permit compliance or as otherwise may be required by the MOECC
to demonstrate compliance with the PTTW. Contractor shall record readings for
each meter on a daily basis and submit records of daily readings to the Engineer
on a weekly basis.
Install, maintain, monitor and take readings from flow meters or other flow
measuring devices set to measure the volumes of service water introduced into
the tunnel and shaft excavations. Provide separate measurements for each tunnel
drive and each shaft. Contractor shall record readings for each meter on a daily
basis and submit records of daily readings to the Engineer on a weekly basis.
Records shall also be submitted to the MOECC as required by the PTTW.
Conform to requirements for monitoring groundwater and piezometric levels as
specified in Section 02480, Geotechnical and Structural Instrumentation and
Monitoring.
Conform to the requirements for settlement monitoring as specified in Section
02480, Geotechnical and Structural Instrumentation and Monitoring.
Conduct daily maintenance of the construction water and surface water control
systems.
Maintain groundwater and piezometric level monitoring devices as specified in
Section 02480, Geotechnical and Structural Instrumentation and Monitoring.
Replace inoperable or damaged system components as necessary to maintain
operation.
Conform to the requirements of Section 01355, Waste Management and
Disposal.
Install unwatering equipment and use equipment to control water to allow for installation
of works to the specified contract requirements.
.2
Insulate piping and fittings and provide shelter and heating as necessary to maintain
unwatering system in operation.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
.5
.6
3.3
SECTION 02140
GROUNDWATER CONTROL
PAGE 10 OF 12
Flotation of Structures:
.1
.2
.2
.3
.2
.3
.2
Provide 100 percent emergency power backup with automatic startup and
switchover in event of electrical power failure.
.2
The Contractor shall promptly and continuously control construction water associated
with tunnels, shafts and other project excavations and dispose of all water from any
source that may accumulate in the tunnel or any shaft or other project excavation. This
shall include all necessary sumping, pumping, bailing, draining, sedimentation and
Treatment prior to discharge.
.3
Sumps, ditches, settlement ponds and similar facilities shall be lined or otherwise
protected from degradation and shall be periodically inspected and maintained and
cleaned, where necessary, in order to maintain normal control of water operations.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.4
SECTION 02140
GROUNDWATER CONTROL
PAGE 11 OF 12
The Contractor is made aware that the Phase II ESA Report and Contaminated Materials
Management Strategy Report outline the anticipated groundwater quality conditions,
which may require the use of pre-treatment onsite in order to meet the sewer use bylaw
requirements. The Contractor shall form its base bid price based on the groundwater
conditions identified in the Contaminated Materials Management Strategy Report and
Geotechnical Baseline Report. Refer to Section 01355, Waste Management and
Disposal, for further information.
.2
Treat construction water as necessary to remove sediments, oil, grease, and other
contaminants prior to discharge to levels as established in permits issued by the City of
Ottawa and Ministry of Environment for specific discharge locations. Treated
construction water may be discharged to the nearest sanitary or storm sewer, as approved
by the City, after the Contractor has obtained necessary discharge permits, provided that
the Contractor demonstrates that the treated water is in conformance with the limits set
in any Discharge Permit issued by the City and the Permit to Take Water.
.3
No contaminated construction water shall be discharged into storm sewers unless treated
as required by the applicable permit for the receiving discharge location.
.4
Treatment facilities shall be designed, furnished, and operated to permit discharging into
storm sewers or sanitary sewers as shown on the Contract Drawings and in accordance
with all applicable federal, provincial and local codes, laws, regulations and ordinances,
permits and the following:
.5
3.5
.1
.2
.3
Test for discharge water quality and submit results to the Engineer as required
elsewhere in this Section. The City and Engineer reserve the right to sample and
test discharge water at any time.
Alternatively the Contractor may store and dispose of construction water using a licensed
Contractor and facility to accept the water in accordance with all applicable regulations
and the Control of Construction Water Plan.
DISPOSAL OF WATER
.1
Potential locations for disposal of construction water (i.e. sanitary sewer system, storm
sewer system, local water body, etc.) are shown on the Drawings. However, the
Contractor is responsible for determining specific disposal locations. The Contractor
shall be responsible for providing the necessary methodology, equipment, materials, and
labour needed to ensure that the water being discharged meets the applicable
requirements of the necessary agreements, permits and approvals of the discharge
receiver (City or Agency with authority) for the discharge location.
.2
Irrespective of the discharge receiver and any permit requirements, the Contractor shall
complete the necessary sampling at a minimum frequency of once per week for each
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02140
GROUNDWATER CONTROL
PAGE 12 OF 12
discharge location to demonstrate that before and during discharge the discharged
construction water meets the applicable requirements.
.3
.4
Groundwater encountered at all locations must be sampled and tested if and as required
by any agreements or permits required for the work and any applicable regulations.
.5
Overland discharge of treated and untreated construction water is not permitted on NCC
or PWGSC property.
.6
.7
.8
3.6
Remove sumps, pumps, piping and other equipment from tunnel, shafts and other
excavations. Sumps in the tunnels, shafts and other excavations shall be cleaned of
settled sediments and filled with backfill concrete in accordance with requirements
specified elsewhere in the Contract Documents for backfill concrete.
.2
Remove construction water treatment and discharge facilities when no longer required.
Restore construction sites and staging areas affected by such equipment as specified in
Section 02980, Restoration.
.3
.4
Remove all measures required to divert and control surface water drainage from entering
tunnel, shaft and other excavations upon completion of the work, as specified in Section
01160, Erosion and Sediment Control Plan.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE OF WORK
SECTION 02150
EXCAVATION SUPPORT SYSTEM
PAGE 1 OF 7
.1
The work specified in this Section consists of the design and construction of shoring
systems required for non-sealed and sealed shafts and protection of the existing and new
facilities to permit construction of permanent structures shown on the Contract Drawings
and specified in the Contract Documents.
.2
As identified in Section 01015 Contractors Use of Premises, the Contractor shall take
over the existing shoring at Site 10 and shall assume full responsibility for the shoring
for the duration of the works. Details of the existing shoring system are indicated in the
Contract Drawings.
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
1.3
REFERNCES
.1
.2
.3
.4
.5
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02150
EXCAVATION SUPPORT SYSTEM
PAGE 2 OF 7
.7
ASTM A29/A29M Specification for Steel Bars, Carbon and Alloy, Hot-Wrought and
Cold-Finished
.8
.9
.10
1.4
DEFINITIONS
.1
Sealed: Sealed, when used to define a type of shaft, shall mean a ground shoring system
designed to meet the design life of the Project, constructed and excavated without the use
of active dewatering and meeting the infiltration requirements specified herein, and
excluding the use of sheet piles, steel liner plates and gaskets or piles and lagging, but
may include secant piles, slurry walls or similar ground shoring system.
.2
Non-Sealed: Non-Sealed, when used to define a type of shaft, shall mean a ground
shoring system designed, constructed and excavated without the use of active dewatering
and may include the use of liner plates, piles and lagging or similar shoring system.
.3
1.5
SUBMITTALS
.1
Submit shop drawings of the excavation shoring and bracing systems for record purposes
at least 30 working days before commencement of shoring work.
.1
At least 30 days prior to starting any shaft construction, submit a narrative along
with shop and working drawings, signed and bearing the Professional
Engineering seal of Contractors excavation support system designer for review
by the Contract Administrator.
.2
The Contract Administrator will not review the submittal for adequacy of the
design of the excavation support system. Contract Administrators review will be
to determine conformance to requirements of the Contract Documents. Full
responsibility for the design, installation, and maintenance of the excavation
shoring and bracing systems rests with the Contractor. Comment or lack of
comment by the Contract Administrator regarding any aspect of the submittal
shall not be construed as approval or disapproval by the Contract Administrator
regarding any aspect of the excavation support system design.
.3
The submittal shall include, but not be limited to, detailed drawings, with all
pertinent descriptions, all materials including technical data, performance data,
and any calculations for:
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02150
EXCAVATION SUPPORT SYSTEM
PAGE 3 OF 7
.2
.3
.4
.5
.6
.7
.8
.9
.10
Calculations shall also show the thrust block design and an adequate
structural factor of safety for the thrust block-wall system when
subjected to the anticipated maximum jacking forces during TBM
advance, where applicable;
.11
Method and details to protect the existing and new utilities, structures
and facilities.
.12
.13
.2
.3
At least 40 working days before commencement of shoring work submit certificates of:
.4
.1
.2
Submit a copy of the written records of any deflections of the excavation shoring system,
sewer support and bracing systems to the Contract Administrator within 48 hours of
taken the measurements.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02150
EXCAVATION SUPPORT SYSTEM
PAGE 4 OF 7
.5
.6
Field Records: For each excavation support system member, maintain accurate records of
installation. Provide one copy of the field records, signed by Contractor's representative
within 48 hours. The following information, as a minimum, shall be included in the field
records:
1.6
.1
.2
.3
Sequence of installation
.4
Final tip and cut-off elevations of vertical excavation supports and plan location
.5
Other pertinent information such as time, date, and duration of installation and
interruptions, if any
.6
.7
.8
QUALIFICATIONS
.1
1.7
The Professional Engineer(s) responsible for the design of excavation shoring systems
and ground treatment to avoid Active Dewatering must have a minimum of ten years
experience in the design of similar shoring and ground treatment systems.
MEASUREMENT AND PAYMENT
.1
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to install the excavation support
systems as specified herein and no separate payment shall be made.
Part 2
Products
2.1
EQUIPMENT
.1
2.2
Select and design excavation support systems to meet the specified design criteria and
requirements on the Contract Documents, existing loads, and construction conditions,
and as set forth herein.
MATERIALS
.1
Provide and maintain minimum one-week supply of ground support materials at the
Work Site during excavation.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02150
EXCAVATION SUPPORT SYSTEM
PAGE 5 OF 7
.2
Provide and maintain an adequate supply of emergency ground support materials at the
Work Site, ready for immediate use.
.3
.4
All other support materials shall conform to their respective ASTM standards.
.5
Store all materials in accordance with the suppliers' specifications. Maintain materials in
a clean and undamaged condition. Replace damaged or destroyed materials.
Part 3
Execution
3.1
PREPARATION
.1
.2
Before excavation for excavation support system, check utility locations by field
investigations and confirm no conflict between them and proposed position of vertical
excavation support/walls.
.3
Review the site conditions and restrictions with respect to roadway width, existing
facilities and overhead power lines etc.
3.2
Design, supply and install any ground treatment required to permit shaft construction
without Active Dewatering.
.2
Design, supply and install excavation shoring systems to meet the following
requirements:
.1
.2
.3
Shoring for sealed shafts shall provide resistance to ground and water loads for
the duration of construction and permanent resistance to ground loads for the
design life of the Project.
Shoring for non-sealed shafts shall provide temporary resistance to ground and
water loads for the duration of construction.
Design shall consider all live and dead loads, load combinations including the
lateral pressure from the soil and ground water and surcharge loads resulting
from the traffic and construction operations.
.3
Prevent the disturbance, destabilization, or failure of the sides and the bottom of
excavations.
.4
Protect all structures, services, utilities, roads, and embankments from disturbance,
displacement, settlement, or damage during construction activities.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
.6
SECTION 02150
EXCAVATION SUPPORT SYSTEM
PAGE 6 OF 7
Shafts 3A, Shafts 3C, Shaft 8 drop and air vent, Shaft 9 and Shaft 10
.7
Pumps employed by the Contractor to remove water infiltrating through shaft shoring
shall be provided with flow meters to determine the volume and rate of water infiltration.
.8
Where excavation is near or adjacent to a building or other structure, the support shall be
started at such depth in relation to the foundation of each such structure as may be
necessary to prevent displacement of the soil that supports the structure.
.9
Ensure that any elements of excavation support system that are to remain in place upon
completion do not penetrate inside the limits of the permanent Work, or as indicated in
the Contract Documents. Protrusions inside the limits of the permanent Work shall be
removed by Contractor and supplemental measures shall be taken as necessary to ensure
safety of the excavation support system arising from such removal.
.10
All ground shall be fully supported during the last Work shift before weekends, holidays
not worked, and any shutdowns.
.11
Ensure that excavation support system is not disturbed or damaged during excavation
and construction.
.12
Coordinate the design of the excavation support system and groundwater control system
to meet the performance requirement as specified.
3.3
.2
Liner plates or piles and lagging shall not be used as shoring for sealed shafts.
.3
The amount of infiltration groundwater through the shoring system at each shaft shall not
exceed 3000 litres per Day as measured by totalizing flow meters installed on discharge
lines.
3.4
.2
Groundwater inflow through the shoring system at each shaft shall be controlled as per
Section 02140, Groundwater Control.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.5
SECTION 02150
EXCAVATION SUPPORT SYSTEM
PAGE 7 OF 7
.2
.3
.4
.5
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
DESCRIPTION
SECTION 02200
SITE PREPARATION
PAGE 1 OF 2
This section describes requirements related to preparation of the sites prior to start of
major excavation/site works.
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
GENERAL
.1
Implement traffic control and pedestrian protection measures prior to commencing any
work that will impact vehicular and pedestrian traffic in accordance with Section 01353
Special Procedures: Traffic Control.
.2
Implement erosion and sediment control measures prior to commencing any earthworks.
Inspect on a regular basis as per Section 01160 Erosion and Sediment Control Plan.
.3
Install tree protection measures as per Section 01561 Environmental Protection and
perform tree pruning as per Section 02232 Tree Pruning. Provide a Tree Management
Plan as per Section 01561.
.4
Install and maintain protection measures for existing structures and utilities as per
Section 01119 Preservation and Protection, and Section 02315 Excavating,
Trenching, and Backfilling.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
SECTION 02200
SITE PREPARATION
PAGE 2 OF 2
Remove obstructions, ice and snow, from surfaces to be excavated within limits
indicated with the below special requirements:
.1
.2
.6
Sawcut pavement neatly along limits of proposed excavation in order that surface may
break evenly and cleanly in accordance with Section 02226 Removal of Existing
Asphalt Pavement.
.7
Perform clearing and grubbing as per Section 02231 Clearing and Grubbing and topsoil
stripping as per Section 02315 Excavating, Trenching and Backfilling.
.8
Construct staging area and perform pre-construction surveying as per Section 01119
Preservation and Protection, and site mobilization as per Section 01720 Preparation,
Mobilization, Demobilization.
.9
Dispose of the debris in accordance with Section 01355 Disposal of Excess Material.
.10
.11
Relocate the RCMP CCTV camera within Site 6 as specified on the Site 6 contract
drawings.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
RELATED SECTIONS
SECTION 02222
DEMOLITION AND REMOVAL
PAGE 1 OF 6
.1
.2
.3
.4
.5
.6
.7
.8
.9
1.2
REFERENCES
.1
.2
1.3
.1
1.4
.1
.2
1.5
DEMOLITION DRAWINGS
.1
1.6
.1
Protect existing items designated to remain and items designated for salvage. In event of
damage to such, immediately replace or make good repair to the approval of the Engineer
and at no cost to the Owner.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.7
SECTION 02222
DEMOLITION AND REMOVAL
PAGE 2 OF 6
QUALITY ASSURANCE
.1
1.8
.1
1.9
Separate waste materials for reuse and recycling in accordance with Section 01355 Disposal of Excess Material.
ENVIRONMENTAL PROTECTION
.1
.2
.3
Cover or wet down dry materials and waste to prevent blowing dust and debris.
.4
Remove, protect and store salvaged items as directed by Engineer. Salvage items for
reuse as identified by the Engineer and noted on drawings. Deliver to the Engineer or
Owner as directed.
1.10
SCHEDULING
.1
Employ necessary means to meet project time lines without compromising specified
minimum rates of material diversion.
.1
Part 2
Products
2.1
EQUIPMENT
.1
Part 3
Execution
3.1
EXISTING CONDITIONS
.1
Take over existing structure, with selective demolition work based on existing condition
at time of examination prior to bidding. Carefully examine existing structure, equipment
and conditions.
.2
.3
Make good existing finishes disturbed or otherwise damaged during selective demolition,
by qualified tradesmen. Match existing materials and finishes.
.4
Make good existing materials and finishes disturbed or otherwise damaged by alterations
to mechanical and electrical equipment and piping. Match existing materials and finishes.
3.2
PROTECTION
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02222
DEMOLITION AND REMOVAL
PAGE 3 OF 6
.1
.2
.3
.4
Provide temporary dust screens, covers, railings, supports and other protection as
required.
.5
Prevent debris from collecting and blocking mechanical and electrical systems, which
will remain in operation.
.6
.7
Prevent dust from entering mechanical and electrical system. Maintain water and
electrical systems.
.8
Where openings are scheduled in existing masonry, remove sufficient existing masonry
units for toothing-in of new masonry units.
.9
Provide storage and protection for items which will be reclaimed and refinished for
installation.
.10
Protect interior of parts and items, which are not to be demolished, from exterior
elements at all times.
.11
3.3
.1
.2
.3
Turn over to the Owner, dismantled items, which are in good condition, and store at
location and as directed by the Engineer.
PREPARATION
.1
Disconnect electrical and mechanical systems in areas of selective demolition to rules and
regulations of authorities having jurisdiction.
.2
Post warning signs on equipment, which will remain in operation in areas of selective
demolition.
.3
.4
3.4
SAFETY CODE
.1
Do Work in accordance with Section 01705 Contract Work Health and Safety Clauses.
.2
3.5
Work of this Section is of selective nature. The work includes but not necessarily limited
to:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.3
Relocation
.4
Cleaning
.5
Disposal
SECTION 02222
DEMOLITION AND REMOVAL
PAGE 4 OF 6
.2
The general area in which the demolition work is to be performed shall be left clean and
free of debris at the end of each shift; access routes must always be kept clear. If
required, the general area shall be graded as required to provide a uniform appearance.
.3
All backfilling required in the demolition area shall conform to the governing
requirements of Section 02315 Excavating, Trenching and Backfilling.
.4
.5
.6
Do not throw or drop demolished materials from heights. Use chutes, conveyors or
hoisting equipment to lower materials.
.7
Demolish in a manner to minimize dusting. Keep dusty materials wetted but prevent
flooding or contaminated runoff.
.8
Demolish masonry and concrete elements in small sections. Carefully remove and lower
structural framing and other heavy and large objects.
.9
At all times leave work in safe condition, so that no part is in danger of uncontrolled
toppling or falling.
.10
.11
3.6
.2
Abandon maintenance holes and chambers indicated on Contract Drawings following the
requirements of City of Ottawa S.P F-4104.
3.7
.2
Existing concrete to be removed shall be cut into fragments and reduced in size as
required to facilitate removal and disposal.
.3
Disassembly and removal of all structural elements shall be carried out under the
supervision of a professional structural engineer licensed to practice in Ontario hired by
the Contractor.
3.8
CONCRETE MODIFICATIONS
.1
Remove existing concrete where such removal is indicated on the drawings or directed by
the Engineer.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02222
DEMOLITION AND REMOVAL
PAGE 5 OF 6
.2
Remove all dust, grease, curing compounds, impregnations, waxes, foreign particles, and
disintegrated material.
.3
.4
Remove all defective existing concrete down to sound concrete where indicated on the
drawings or as directed by the Engineer.
.5
Where existing concrete is to be removed, fill, repair, and finish the surfaces smooth and
flush with adjacent undisturbed surfaces.
.6
Unless otherwise indicated on the drawings or directed by the Engineer, clean and leave
in place existing reinforcing exposed during concrete removal operations.
.7
Where indicated on the drawings, extend existing reinforcing into the new construction
by mechanical connection to the existing reinforcement. Mechanical connections shall be
as specified in Division 15.
.8
Any reinforcement bars the Engineer allows to be cut shall be cut off not less than 25 mm
inside the finished and repaired surface. All anchor bolts, piping, and other hardware
projecting from concrete surfaces after piping and equipment have been removed shall be
cut 25 mm inside the finished or repaired surface. Reinforcement bars and other steel
construction to be removed may be flame-cut.
.9
Remove concrete bases of existing equipment that have been relocated or removed, down
to the reinforcing steel of the supporting slab. Initiate removal of curb base with a
concrete saw, cutting around the perimeter, taking care not to chip or spall the surface of
remaining structure. After existing materials have been removed, exposed reinforcing
steel and structural slab shall be cleaned and filled with new concrete, finished to match
the surrounding surface.
.10
Concrete materials and placement shall be in accordance with Section 03300 - Cast-inPlace Concrete (Shafts and Underground Structures) and Section 03301 Cast-in-Place
Concrete (Odour And Control Structures).
.11
Provide dust control by water systems or vacuum system and tarping to limit any dust
migration during any concrete demolition work
3.9
Be responsible for the removal of process equipment, pumps and associated motors,
piping and valves, and all other appurtenances associated with the item being removed.
.2
.3
Piping and equipment shall be disconnected, dismantled and removed as required and in
such a manner as to minimize disturbance or damage to adjacent construction.
.4
At any point or location where new work is to be connected or installed, the removal of
existing work shall be done so as to facilitate the new installation work to the maximum
possible extent.
3.10
The demolition of existing drives, curbs, walks, dikes, and similar items shall be
scheduled and performed so as to minimize inconvenience to the Owner.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02222
DEMOLITION AND REMOVAL
PAGE 6 OF 6
.2
The attention of the Contractor is called to Section 01010 - Summary of Work and
Section 01117 Construction Sequences and Constraints pertaining to the construction
sequence guidelines that are recommended to maintain system operations.
.3
The demolition of existing in-ground services including piping and chambers shall be
coordinated so as to ensure the continual unhindered operation of the system, allow for
efficient changeovers from existing to new in-ground services and to minimize
inconvenience to the Owner.
3.11
.2
The Contractor will be held responsible for any damage thereto because of his operations.
.3
.4
Holes and damage resulting from removal operations shall be filled, reconstructed,
repaired, and finished to match and conform to adjacent surfaces and construction as
determined by the Engineer.
3.12
3.13
.1
After selective demolition clean existing substrates to sound, clean surface free from
extraneous matter. Use only non-ionic surfactants.
.2
Where openings are scheduled in existing masonry, remove sufficient existing masonry
units for footing in of new masonry units.
.3
Test clean area designated by the Engineer. Use accepted, cleaned area as the standard
for the remainder of the cleaning work.
3.14
DISPOSAL OF WASTE
.1
.2
.3
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SECTION INCLUDES
.1
1.2
SECTION 02226
REMOVAL OF EXISTING ASPHALT
PAVEMENT
PAGE 1 OF 3
.1
.2
.3
.4
1.3
REFERENCES
.1
.2
City of Ottawa
1.4
.1
Special Provision S.P. No.: F-5103 Removal of Asphalt Pavement, Partial Depth.
.2
PAYMENT PROCEDURES
.1
1.5
Payment for all work completed in accordance with this Section will be paid as per
Section 01025, Measurement and Payment.
WASTE MANAGEMENT AND DISPOSAL
.1
Separate waste materials for reuse and recycling in accordance with Section 01355 Disposal of Excess Material.
.2
Divert unused asphalt materials from landfill to local recycling facility approved by
Contract Administrator.
Part 2
Products
2.1
EQUIPMENT
.1
Use cold milling, planning or grinding equipment with automatic grade controls capable
of operating from stringline, and capable of removing part of pavement surface to depths
or grades indicated.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 3
Execution
3.1
PREPARATION
.1
3.2
SECTION 02226
REMOVAL OF EXISTING ASPHALT
PAVEMENT
PAGE 2 OF 3
Prior to beginning removal operation, inspect and verify with Contract Administrator
areas, depths and lines of asphalt pavement to be removed and where milling will be
required.
PROTECTION
.1
3.3
Protect existing pavement not designated for removal, light units and structures from
damage. In event of damage, immediately replace or make repairs to approval of
Contract Administrator at no additional cost.
REMOVAL
.1
.2
Use equipment and methods of removal and hauling which do not damage or disturb
underlying pavement.
.3
.4
Provide for suppression of dust generated by removal process in accordance with Section
02362 - Dust Control.
SAW CUTTING AND PAVEMENT REMOVAL
3.4
.1
All excavations that will disturb asphalt or concrete pavement or structures shall be saw
cut. All saw cutting shall be completed wet. All sawcuts shall be made either parallel or
on angle to the direction of travel to prevent simultaneous contact between vehicle
wheels and the sawcut . Sawcuts shall be straight and vertical to the full depth of the
asphalt and concrete layers of pavement. The Contractor shall assume a minimum depth
of 300 mm for all saw cuts. Refer to the Geotechnical Data Report for the geotechnical
conditions.
.2
Saw cutting shall stop at, or just short of, corners to avoid overcutting. After saw cutting
the edges, removal of pavement materials shall be performed with care to avoid lifting or
breaking the road pavements beyond the sawcut borders.
.3
If during the course of the work additional asphalt or pavement has breakage beyond the
trench width, the Contractor shall saw cut completely around the breakage prior to
completing the restoration.
3.5
STOCKPILING OF MATERIAL
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
3.6
SECTION 02226
REMOVAL OF EXISTING ASPHALT
PAVEMENT
PAGE 3 OF 3
Removed asphalt pavement which is to be recycled in hot mix asphalt concrete under this
contract may be stockpiled at designated asphalt plant site.
SWEEPING
.1
Sweep remaining asphalt pavement surfaces clean of debris resulting from removal
operations using rotary power brooms and hand brooming as required.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
PART 1
GENERAL
1.1
SUMMARY
SECTION 02228
BLASTING
PAGE 1 OF 9
.1
.2
Related Sections:
.3
.4
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
Definitions:
.1
.2
.3
Peak Particle Velocity (PPV): the maximum speed in millimetres per second that
ground particles move as a result of energy released from explosive detonations.
Design Criteria:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.5
SECTION 02228
BLASTING
PAGE 2 OF 9
.3
Use controlled blasting methods for all pipeline, portal, and structure
excavations.
.4
.5
.6
Holes for blasting shall be 75 mm or less in diameter and shall not be sprung or
chambered.
.7
Control firing systems of general blast holes by the use of delay detonators.
Explosives used for a single period of delay shall be the minimum required.
.8
Performance Requirements:
.1
.2
.3
SUBMITTALS
1.2
.1
General: Make submittals in accordance with Section 01330. All blasting related
submittals for Site 6 and PWGSC property shall be subject to PWGSC and Royal
Canadian Mounted Police (RCMP) review and approval and is subject to the
Communique Process outlined in Section 01117.
.2
.3
.2
Submit a Blasting Safety Plan allowing time for approval in accordance with
Section 01330 and or use of explosives, blasting agents, primers, or initiators.
Include the following in the Blasting Safety Plan:
.1
.2
.3
Outline of safety and health training and inspection program for all
personnel.
.4
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02228
BLASTING
PAGE 3 OF 9
.6
Provisions to ensure that flyrock does not result from the blasting
operation.
.7
.8
.9
.4
.2
Total weight of explosive in the blast and maximum weight per hole
and charge weight per delay period.
.3
.4
.4
Submit copies of all blast monitoring records to the City Representative within
6 hours of each blast.
.5
Contractor shall provide regular schedule updates such that City can notify
surrounding cities and residents of the blasting schedule.
Quality Control:
.1
.2
Qualifications:
.1
.2
Certifications:
.1
.3
Recordkeeping: Prepare and maintain on-site reports and records, which shall
be accessible to the City Representative during normal working hours,
including the following:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
1.3
.2
.3
SECTION 02228
BLASTING
PAGE 4 OF 9
QUALITY ASSURANCE
.1
Reference Standards:
.1
.2
.3
1.4
.2
.4
Qualifications:
.1
.2
.3
The Blasting Supervisors shall be persons over the age of 21 having a minimum of
5 years of relevant experience and trained in blast monitoring.
.4
The design and execution of the blasting program shall be performed under the
supervision of Blasting Supervisors.
.5
PRECONSTRUCTION MEETING
.1
Jointly with City Representative, Contractor shall convene a pre-blast meeting at least 5
days, but not more than 30 days prior to the first blast. The meeting shall discuss the
following
.1
Blasting procedures.
.2
Safety requirements.
.3
Monitoring criteria.
.4
Environmental considerations.
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.5
SECTION 02228
BLASTING
PAGE 5 OF 9
JOB CONDITIONS
.1
Blasting must satisfy all regulatory requirements, and the Performance Requirements
specified herein, and may then proceed under the Working Hour conditions prescribed
below.
.2
.3
Blasting may proceed only during the hours permitted by the City of Ottawa Noise
Bylaw unless special approval is granted in writing by the City Representative.
1.6
.2
Storage:
.3
.1
.2
Explosives shall not be stored underground or within 100 meters of the tunnel
portal.
.3
.4
PART 2
PRODUCTS
2.1
MATERIALS
.1
.2
Water-resistant.
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.3
2.2
SECTION 02228
BLASTING
PAGE 6 OF 9
Use explosives, blasting agents, and initiating devices that are less than one year old.
EQUIPMENT
.1
Equipment used for drilling of holes shall have positive means of dust control.
.2
The Contractor shall use seismographs with the following features to monitor each
blast, as specified in Section 02482, Vibration Monitoring.
PART 3
EXECUTION
3.1
GENERAL
.1
.2
Blasting will not be permitted when in the opinion of the City Representative it may
be detrimental to existing works, or result in unacceptable environmental impacts.
The City Representative's decision will be final.
.3
Due to the potential presence of Radio Frequency (RF) emitting devices in the vicinity,
only initiation systems that are not affected by stray current or RF energy shall be
utilized. Initiation systems consisting solely of cap and fuse shall not be used.
Procedures in the use of the initiation system selected shall conform to the system
manufacturer's recommendations. Regardless of other exclusions in this section, if
deemed safe by the Contractor, an electric detonator may be utilized to start the
initiation system. The electric cap or other starter shall not be brought onto the blast
site nor shall it be connected to the initiation system until the area has been cleared and
the blast is ready to be detonated.
.4
.5
Do not perform blasting closer than 5 m to existing water, gas, sewer, or other buried
utilities.
.6
.7
Control flyrock and debris to prevent injuries to persons or damage to structures. Use
blasting mats. Contain fly rock so that it shall not represent a hazard to people, vehicles,
existing improvements, nor vegetation.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02228
BLASTING
PAGE 7 OF 9
.8
Blasting within 100 m of the Ottawa River, Rideau River or Rideau Canal will not be
conducted during Ministry of Natural Resources (MNR) and Department of Fisheries
and Oceans (DFO) in-water timing windows.
.9
Blasting shall not be performed closer than 30 m of any fresh concrete within 72 hours
after completion of the concrete pour or when approved by the Contract Administrator
in writing, after a 24 hour period during which the ambient temperature is continuously
greater than 20C.
3.2
BLASTING SUPERVISORS
.1
.2
.2
.3
WARNING SYSTEMS
3.3
.1
Follow all warning requirements of local, Provincial, and federal agencies. Institute a
system of audible signals to warn of impending blasts.
.2
Erect signboards stating that blasting operations are taking place in the area. These
signs shall be clearly visible and legible from all points of access to the area, and shall
clearly describe the audible signal system for warning of impending blasts.
.3
3.4
POST-BLAST SAFETY
.1
After each blast, follow applicable safety regulations prior to returning to the blasting
area. Personnel may then enter the blasting area with appropriate respiratory equipment or
wait until air quality meets acceptable standards.
.2
After a blast has been fired, make a careful inspection to determine that all charges have
exploded before anyone is allowed to return to the operation. Misfires shall be
corrected in accordance with the applicable portions of federal, province, and local
safety and health codes for blasting. Before drilling blast holes for a new round; clean the
face and thoroughly examine it for missed holes and unexploded explosives.
.3
Remove all loose and shattered rock that may endanger the structure or the workers.
Make the excavation safe before proceeding with the work. Removal of loose or
shattered rock or other loose material may enlarge the excavation beyond the required
limits but shall not relieve the Contractor of the responsibility for removal of such
material.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.5
SECTION 02228
BLASTING
PAGE 8 OF 9
SUSPENSION OF BLASTING
.1
Blasting operations may be suspended by the City Representative for any of the
following:
.1
.2
.3
.4
.5
.6
.7
Skilled operators and/or the licensed Blasting Supervisor are not present.
.8
.2
Blasting operations shall not be resumed until modifications have been made to
correct the conditions that resulted in the suspension.
.3
Suspension of blasting operations resulting from any of the reasons stated above shall
in no way relieve the Contractor of its responsibilities under the terms of this
Contract. The Contractor shall not be entitled to any extension in time, or to any claim
of damage or excess costs, by reason of any blasting suspension order resulting
from any of the reasons stated above.
3.6
.2
The Contractor shall measure peak particle velocity, frequency, and airblast
overpressure for each blast with at least two seismographs. Placement is subject to
the approval of the City Representative.
.1
.3
3.7
Place one at structure subject to the highest ground vibration, and one at
the structure which will be subject to the highest airblast overpressure.
Access for monitoring at private residences shall be subject to property
owner approval. If access is not allowed, monitor at nearest property line.
.1
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.8
SECTION 02228
BLASTING
PAGE 9 OF 9
Damage to buildings, structures, facilities (above and below grade), and property
caused by blasting operations shall be repaired/replaced to the satisfaction of the
Owner, the property owner and property occupant at the Contractors sole and complete
expense.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
PART 1
1.1
1.3
GENERAL
RELATED SECTIONS
.1
.2
.3
.4
.4
.5
REFERENCES
.1
1.4
1.5
SECTION 02231
CLEARING AND GRUBBING
PAGE 1 OF 5
DEFINITIONS
.1
Clearing consists of cutting off trees and brush vegetative growth to not more than
specified height above ground and disposing of felled trees, previously uprooted trees and
stumps, and surface debris.
.2
Close-cut clearing consists of cutting off standing trees, brush, scrub, roots, stumps and
embedded logs, removing at, or close to, existing grade and disposing of fallen timber
and surface debris.
.3
Clearing isolated trees consists of cutting off to not more than specified height above
ground of designated trees, and disposing of felled trees and debris.
.4
Underbrush clearing consists of removal from treed areas of undergrowth, deadwood, and
trees smaller than 50 mm trunk diameter and disposing of fallen timber and surface
debris.
.5
Grubbing consists of excavation and disposal of stumps and roots boulders and rock
fragments of specified size 200mm to not less than specified depth below existing ground
surface.
SUBMITTALS
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
1.6
.1
.2
.1
Separate waste materials for reuse and recycling in accordance with Section 01335
Disposal of Excess Material.
.2
Consider felled timber from which saw logs, pulpwood, posts, poles, ties, or fuel wood
can be produced as saleable timber.
.1
Trim limbs and tops, and saw into saleable lengths of 1.2 m for saw logs.
.2
PRODUCTS
MATERIALS
.1
Bituminous based paint of standard manufacture specially formulated for tree wounds.
.2
PART 3
3.1
Prevent damage to fencing, trees, landscaping, natural features, bench marks, existing
buildings existing pavement, utility lines, site appurtenances, water courses, root systems
of trees which are to remain.
PART 2
2.1
1.8
QUALITY ASSURANCE
.1
1.7
SECTION 02231
CLEARING AND GRUBBING
PAGE 2 OF 5
.1
Excavated soil material: free of debris, roots, wood, scrap material, vegetable
matter, refuse, soft unsound particles, deleterious, or objectionable materials.
.2
EXECUTION
Provide temporary erosion and sedimentation control measures to prevent soil erosion
and discharge of soil-bearing water runoff or airborne dust to adjacent properties and
walkways, according to requirements of Section 01160 - Erosion and Sediment Control
Plan.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.2
3.3
.2
Inspect, repair, and maintain erosion and sedimentation control measures during
construction until permanent vegetation has been established.
.3
Remove erosion and sedimentation controls and restore and stabilize areas disturbed
during removal.
PREPARATION
.1
.2
Locate and protect utility lines: preserve in operating condition active utilities traversing
site.
3.5
.1
.2
.3
.4
APPLICATION
.1
3.4
SECTION 02231
CLEARING AND GRUBBING
PAGE 3 OF 5
CLEARING
.1
Clearing includes felling, trimming, and cutting of trees into sections and satisfactory
disposal of trees and other vegetation designated for removal, including downed timber,
snags, brush, and rubbish occurring within cleared areas.
.2
Clear as indicated or directed by Engineer, by cutting at height of not more than 300 mm
above ground. In areas to be subsequently grubbed, height of stumps left from clearing
operations to be not more than 1000 mm above ground surface.
.3
Cut off branches and cut down trees overhanging area cleared as directed by Engineer.
.4
.2
Cut off branches or down trees overhanging area cleared as directed by Engineer.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.6
3.7
ISOLATED TREES
.1
Cut off isolated trees as indicated Engineer at height of not more than 300 mm above
ground surface.
.2
.3
.4
Trim trees designated to be left standing within cleared areas of dead branches 4 cm or
more in diameter; and trim branches to heights as indicated.
.5
Cut limbs and branches to be trimmed close to bole of tree or main branches.
.6
Paint cuts more than 3 cm in diameter with approved tree wound paint.
UNDERBRUSH CLEARING
.1
3.8
3.9
SECTION 02231
CLEARING AND GRUBBING
PAGE 4 OF 5
GRUBBING
.1
Remove and dispose of roots larger than 7.5 cm in diameter, matted roots, and designated
stumps from indicated grubbing areas.
.2
Grub out stumps and roots to not less than 200 mm below ground surface.
.3
Grub out visible rock fragments and boulders, greater than 300 mm in greatest
dimension, but less than 0.25 m.
.4
Fill depressions made by grubbing with suitable material and to make new surface
conform with existing adjacent surface of ground.
Remove cleared and grubbed materials off site as indicated in Section 01355 Disposal of
Excess Material.
.2
Cut timber greater than 125 mm diameter to1200 mm lengths and stockpile as indicated
in Section 01355 Disposal of Excess Material.
.3
Chip or mulch and stockpile spread cleared and grubbed vegetative material on site as
indicated in Section 01355 Disposal of Excess Material.
.4
Remove diseased trees identified by Engineer and dispose of this material to approval of
Engineer.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.10
FINISHED SURFACE
1
3.11
SECTION 02231
CLEARING AND GRUBBING
PAGE 5 OF 5
Leave ground surface in condition suitable for immediate grading operations or stripping
of topsoil to approval of Engineer.
CLEANING
.1
.2
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
PART 1
1.1
GENERAL
RELATED SECTIONS
.1
1.3
REFERENCES
.1
ANSI A300 (Part 1)-2001, Tree Care Operations - Tree, Shrub and
Other Woody Plant Maintenance - Standard Practices (revision and redesignation of ANSI A300-1995) (includes supplements).
.2
ANSI A300 (Part 2)-1998, Tree Care Operations - Tree, Shrub, and
Other Woody Plant Maintenance - Standard Practices - Part 2 Fertilization.
.3
ANSI A300 (Part 3)-2000, Tree Care Operations - Tree, Shrub and Other
Woody Plant Maintenance: Standard Practices - Part 3 - Tree Support Systems
(a. Cabling, Bracing, and Guying) (supplement to ANSI A300-1995).
.2
.3
.4
1.4
SECTION 02232
TREE PRUNING
PAGE 1 OF 5
DEFINITIONS
.1
.2
.3
.4
.5
.6
Crown Restoration: improves structure, form and appearance of trees that have
been severely headed or vandalized.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.5
1.6
1.7
SECTION 02232
TREE PRUNING
PAGE 2 OF 5
QUALITY ASSURANCE
.1
.2
.3
.2
.4
.5
Separate waste materials for reuse and recycling in accordance with Section
01355 Disposal of Excess Material.
.3
.4
.5
TOOL MAINTENANCE
.1
Ensure that tools are clean and sharp throughout pruning operation: do not use
tools that crush or tear bark.
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
PART 2
2.1
PART 3
3.3
EXECUTION
APPLICATION
.1
3.2
PRODUCTS
DISINFECTANT
.1
3.1
SECTION 02232
TREE PRUNING
PAGE 3 OF 5
GENERAL
.1
.2
.3
Prune during plant dormant period or after leaves have matured. Avoid
pruning during leaf formation, at time of leaf fall, or when seasonal
temperature drops below minus 10 degrees C.
.4
.5
.6
Do not:
.1
.2
.3
.4
.5
PRUNING
.1
Remove dead, dying, diseased and weak growth from plant material to provide
crown cleaning, crown thinning, crown raising, crown reduction, vista pruning,
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02232
TREE PRUNING
PAGE 4 OF 5
.3
.2
.3
.4
Are broken.
.2
.3
.4
.4
.5
Remove vines.
.6
.7
.1
Locate branch bark ridge and make cuts smooth and flush with outer
edge of branch collar to ensure retention of branch collar. Cut target
area to bottom of branch collar at angle equal to that formed by line
opposite to branch bark ridge.
.2
Make cuts on dead branches smooth and flush with swollen callus
collar. Do not injure or remove callus collar.
.3
Make first cut on lower side of branch 300 mm from trunk, one third
diameter of branch.
.2
Make second cut on upper side of branch 500 mm from trunk until
branch falls off.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
Ensure that trunk bark and branch collar are not damaged or torn during limb
removal.
.1
.9
3.4
3.5
ROOT GIRDLING
.1
For girdling roots one-quarter size of trunk diameter or larger, V-cut girdling
root one-half way through at point where root is crossing.
.2
CARE OF WOUNDS
.1
3.6
SECTION 02232
TREE PRUNING
PAGE 5 OF 5
CLEAN-UP
.1
.2
.3
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02260
MECHANICALLY STABILIZED
EARTHEN SLOPES
PAGE 1 OF 7
PART 1 GENERAL
1.1
SECTION INCLUDES
.1
Mechanically stabilized earth (MSE) steep slope system with high-density polyethylene
and polypropylene reinforcing geogrids at Site 6.
.2
.3
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
1.3
REFERENCES
.1
.2
ASTM F 904 - Standard Test Method for Comparison of Bond Strength or Ply Adhesion
of Similar Laminates Made from Flexible Materials; 1991.
.3
ASTM D7737 - Standard Test Method for Individual Geogrid Junction Strength.
.4
1.4
SUBMITTALS
.1
.2
.3
.1
.2
.3
Installation methods.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02260
MECHANICALLY STABILIZED
EARTHEN SLOPES
PAGE 2 OF 7
.2
Manufacturer's certifications that the ultimate tensile strength and junction strength of
the geogrid are equal to or greater than those specified.
.4
.5
1.5
.2
.1
.2
Submit design and supporting data at least 2 weeks prior to commencing Work.
.3
Design and supporting data submitted to bear stamp and signature of qualified
professional engineer registered or licensed in the Province of Ontario.
.4
.5
1.6
.2
Prevent excessive mud, fluid concrete, epoxy, or other deleterious materials from coming
in contact with and affixing to materials.
.3
.4
.5
Do not place backfill during wet or freezing weather that prevents conformance with
specified compaction requirements.
1.7
Separate waste materials for reuse and recycling in accordance with Section 01355 Disposal of Excess Material.
PART 2 PRODUCTS
1.1
MANUFACTURERS
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.2
SECTION 02260
MECHANICALLY STABILIZED
EARTHEN SLOPES
PAGE 3 OF 7
MATERIALS
.1
.2
.3
Primary Geogrid - The primary geogrids long-term design strength shall be determined
in accordance with the following:
Where:
T ULT
Ta =
RF CR x RF ID x RF D
TULT - Ultimate Tensile Strength shall be the minimum average roll value ultimate tensile
strength as tested per ASTM D6637. This test shall be conducted without artificially
deforming test materials under load before measuring such resistance or employing an
artificial secant or offset tangent basis of measurement so as to overstate tensile
properties.
RFCR The Reduction Factor for Creep is the ratio of TULT divided by the creep rupture
strength determined in accordance with ASTM D5262-07. Long-term creep rupture of the
reinforcement shall be determined from controlled laboratory testing conducted for a range of
load levels and durations in accordance to ASTM D5262 adequate for extrapolation to the
design life. Elevated temperature can be used to accelerate creep rupture test for the purpose
of extrapolation. A minimum total of 12 rupture data points with a minimum of 4 data points
at each temperature and at least one test having a rupture time over 10,000 hours or more are
required to establish a rupture envelope. The requirement for the minimum creep test may be
waived for a new product if it can be demonstrated that is sufficiently similar to a proven
creep tested product of a similar nature. When these conditions are met, creep testing shall be
conducted for at least 1,000 hours before time shifting, with adequate elevated temperature
data to permit to 50,000 hours or more. The limited test results of the new product are
compared to the results of the previously conducted full testing program. The 1,000 hour
creep curves must pattern very closely to the 1,000 hour porting of the similar product to
demonstrate equivalency. Creep testing is required on representative samples of the finished
product and not a single component of the geogrid (e.g., fiber and/or yarn). The ultimate
strength used in this calculation shall be that of the roll used in the testing and not the MARV
for the product.
In no event shall the minimum value of RFCR be less than:
HDPE Uniaxial geogrid
2.56
PP biaxial geogrid
4.00
RFID The Reduction Factor for Installation Damage is the ratio of the virgin reinforcement
TULT divided by the TULT of a sample of the same material recovered from an installation
damage test. Tests shall be conducted using the actual backfill from the project in accordance
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02260
MECHANICALLY STABILIZED
EARTHEN SLOPES
PAGE 4 OF 7
with GRI-GG4. However, in lieu of such testing, the Manufacturer may supply test results
from other backfill soils if such soils can be shown to result in more severe construction
damage than the proposed backfill. TULT shall be determined in accordance with ASTM
D6637-01 and sample recovery shall be consistent with ASTM D5818-06.
In no event shall the minimum value of RFID be less than:
HDPE Uniaxial geogrid
1.05
PP Biaxial geogrid
1.05
RFD - Reduction Factor for Durability/Aging is the combined partial factor for potential
chemical and biological degradation. RFD shall be determined from polymer specific (HDPE
and PP as identified by their mechanical properties, and PET as identified by CEG number
and number average molecular weight, Mn) durability testing covering the range of expected
soil environments. Polyolefin geogrids can be used in a pH range from 3 to 12, and polyester
geogrids can be used within a pH range of greater than 3 and less than 9. The minimum
Reduction Factor for Durability/Aging for HDPE and PP shall be 1.0.
For soils of potential concern, as presented below (modified soil shall include lime stabilized
soil, cement stabilized soil, or concrete), only polymers listed as YES shall be used within
or adjacent to (3 feet shortest measurable distance) these soil environments (Reference: Table
8, FHWA NHI-00-044).
SOIL ENVIRONMENT
HDPE
PP
YES
NO
Organic Soils
YES
YES
YES
YES
Calcareous Soils
YES
YES
YES
YES
YES
YES
YES
YES
YES
NO
Ci - Soil Interaction Coefficient value shall be determined from long-term effective stress
pullout tests per ASTM D6706-01. The Ci value is determined as follows:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
SECTION 02260
MECHANICALLY STABILIZED
EARTHEN SLOPES
PAGE 5 OF 7
F
2 L N tan
Where:
Secondary and Slope Face Wrapping Geogrid: Tensar BX1120: Polymeric grid formed by
regular network of integrally connected tensile elements with apertures of sufficient size to
retain a 25-mm to 50-mm Stone Face Fill.
Aperture Size: 25 mm by 33 mm.
Carbon Black Content: 2.0 percent.
.4
Backfill outside of geogrid reinforced zone: Select Subgrade Material (as per Section
02315 Excavating, Trenching, and Backfilling)
.5
Soil within geogrid reinforced zone: OPSS Granular B Type I (as per Section 02315
Excavating, Trenching, and Backfilling) with the below modifications:
100% passing 50mm sieve
75% to 100% passing 19mm sieve
.6
Plantable Fill: as per Section 02702 Aggregates: Landscaping when not within
geogrid reinforced zone.
.7
Turf Reinforcement Mat: North American Green C350 (or approved equal) permanent
turf reinforcement mat. Mat shall consist of evenly distributed 100 percent coconut
fiber matrix weighing 0.27 kg/sq m encapsulated in a 3-D matting structure consisting
of two, top and bottom, heavyweight UV stabilized polypropylene nets, with a nominal
weight of 0.04 kg/sq m and a corrugated high strength center net with an nominal
weight of 0.12 kg/sq m. The three nets shall be stitched together on 38 mm centers
with UV stabilized polypropylene thread to form a permanent three-dimensional turf
reinforcement mat with a minimum thickness of 13 mm.
PART 3
EXECUTION
3.1
PREPARATION
.1
Notify Engineer of schedule and plan for works as per Section 01117 Construction Sequences
and Constraints.
.2
Do not begin reinforced slope construction until excavation to subgrade as approved by Engineer
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02260
MECHANICALLY STABILIZED
EARTHEN SLOPES
PAGE 6 OF 7
has been completed and the foundation for the reinforced fill has been properly prepared.
.3
Excavation:
.1
.2
Remove soils not meeting required strength and replace with approved materials as per
Section 02315 Excavating, Trenching, and Backfill and as specified in this section.
.3
3.2
CONSTRUCTION
.1
Construct slope system in accordance with approved shop drawings and manufacturer's
instructions.
.2
Geogrid placement:
Unroll the structural geogrid on the compacted backfill and cut to the length indicated on the
shop drawings.
Unroll and place uniaxial geogrids perpendicular to the slope face.
Cut uniaxial geogrids within 50mm from the thick transverse bar and place that end of the
strip at the slope face or to the position near the slope face shown on shop drawings.
Unroll and place biaxial geogrid parallel to the slope face unless otherwise shown on shop
drawings. Biaxial geogrids may be cut to the required width prior to unrolling.
Extend the geogrid and turf reinforcement mat beyond the slope face by the amount required
for the wrapped face and for anchorage at the top of the wrap.
Pull the geogrid taut to remove slack.
Stake or pin the geogrid near the ends as required to maintain alignment and tension during
filling.
Place a minimum of 75 mm of fill between any overlapping layers of geogrid where
overlapping occurs behind curves and corners of the slope.
Rubber tired vehicles may travel on the geogrid at low speeds, less than 10 km/hr. Turning of
vehicles should be avoided to prevent dislocation or damage to the geogrid.
Tracked vehicles shall not be operated directly on the geogrid. A minimum of 200 mm of fill
cover over the geogrid is required for operation of tracked construction vehicles in the
reinforced zone.
.3
Fill:
Place reinforced backfill material and compact to a maximum 225 mm deep lifts. Compact to
minimum of 95 percent Standard Proctor Dry Density in accordance with ASTM D 698 to
within 1 m of the slope face. Compact the near-face zone using a minimum of three passes.
Use only hand operated compaction equipment within 1 m of the slope face.
Do not perform soil density testing within 1 m of the slope face.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02260
MECHANICALLY STABILIZED
EARTHEN SLOPES
PAGE 7 OF 7
Place geotextile separator and stone or plantable face fill in the zone designated on the shop
drawings and compact with hand operated equipment.
Place and compact subsequent lifts of fill to the level of the next layer of geogrid
reinforcement. Smooth and level (or slope as shown on drawings) to ensure geogrid lays flat.
Shape the slope face above the lower level of geogrid reinforcement.
Pull any required slope wrapping geogrid and turf reinforcement mat up the slope and over the
compacted fill to the distance shown on the shop drawings and stake or anchor as required to
maintain alignment and tension.
Repeat geogrid and fill placement procedures to top of slope.
Place, stake and anchor turf reinforcement mat on slope face as shown on shop drawing.
Notify Engineer immediately if changes are required to the slope design or backfill material.
Notify Engineer immediately if excessive groundwater is noted which may require changes to
the installation method or backfill material.
.4
Landscaping:
Trim and cut geogrid to accommodate landscaping as per shop drawings and Section 02906
Trees and Shrub Planting. Do not exceed maximum trimming and cutting size necessary to
perform plantings or modify location and spacing of cutting of the geogrid without approval of
Engineer.
.5
.6
3.3
3.4
PROTECTION
A.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
1.2
SECTION 02311
SITE GRADING
PAGE 1 OF 3
REFERENCES
.1
.2
1.3
EXISTING CONDITIONS
.1
For existing geotechnical conditions, refer to the Geotechnical Baseline Report and
Geotechnical Data Report.
.2
Known underground and surface utility lines and buried objects are as indicated on
Contract Drawings based on information provided by utility companies and taken from
as-built documents and utility drawings. They are shown for scoping purposes as
reported but their exact location and depth must be confirmed by the contractor prior to
commencing any site excavation or grading work. Any discrepancy in findings must be
reported to the Contract Administrator.
.3
1.4
PROTECTION
.1
Protect and/or transplant existing fencing, trees, landscaping, natural features, bench
marks, buildings, posts, pavement, surface or underground utility lines which are to
remain as directed by Contract Administrator. If damaged, restore to original or better
condition unless directed otherwise.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 2
Products
2.1
MATERIALS
SECTION 02311
SITE GRADING
PAGE 2 OF 3
.1
Fill material: in accordance with Section 02315, Excavating, Trenching and Backfilling.
.2
Excavated or graded material existing on site may be suitable to use as fill for grading
work only if approved by Contract Administrator.
Part 3
Execution
3.1
STRIPPING OF TOPSOIL
.1
3.2
.1
Unless indicated otherwise by a grading plan, the contractor shall reinstate all sites to
pre-construction conditions and grades. The contractor shall conduct a comprehensive
photographic and topographic survey of each site in order to be able to reinstate as per
pre-construction conditions. Inadequacies in pre-construction grading discovered by the
contractor shall be reported to the Contract Administrator.
.2
Use Granular B Type II to rough grade the sites. Make up shortfall with imported fill
material or rock spoils excavated from the tunnels if it has been approved for use as
select subgrade material. Place a geotextile fabric underneath granular fill material in all
locations where preconstruction grading is to be reinstated. Place fill in lifts of 300 mm
compacted to 95% SPMDD.
.3
.4
.5
Slope rough grade away from building 1:50 minimum or as indicated on Contract
Drawings.
.6
Remove and dispose of stones or rock fragments larger than 75 mm nominal diameter
from the top of finished grade.
.7
Handle excavated material so that selected topsoil material is placed on top surface.
.8
3.3
3.4
Prior to commencing any work erosion and sediment control measures shall be in place
in accordance with Section 01160, Erosion and Sediment Control Plan.
TESTING
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
3.5
SECTION 02311
SITE GRADING
PAGE 3 OF 3
Submit testing procedure and frequency of tests to Contract Administrator for review, in
accordance with Section 01450, Quality Control.
SURPLUS MATERIAL
.1
Remove surplus material and material unsuitable for fill, grading or landscaping off site.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
RELATED SECTIONS
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 1 OF 13
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
.15
1.2
REFERENCES
.1
.2
ASTM C117-04, Standard Test Method for Material Finer Than 0.075 mm
(No.200) Sieve in Mineral Aggregates by Washing.
.2
ASTM C136-05, Standard Test Method for Sieve Analysis of Fine and Coarse
Aggregates.
.3
.4
ASTM D4318-00, Standard Test Methods for Liquid Limit, Plastic Limit, and
Plasticity Index of Soils.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.3
.5
1.3
.4
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 2 OF 13
.2
.3
City of Ottawa
.1
Special Provision S.P. No.: F-2120 Select Subgrade Material for Trench
Backfill
.2
.3
.4
.5
.6
.7
DEFINITIONS
.1
.2
.2
Topsoil: material capable of supporting good vegetative growth and suitable for use in
top dressing, landscaping and seeding.
.3
.4
Borrow material: material obtained from locations outside area to be graded, and
required for construction of fill areas or for other portions of Work.
.5
Unsuitable materials:
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 3 OF 13
.6
.7
Unshrinkable fill: very weak mixture of Portland cement, concrete aggregates and water
that resists settlement when placed in utility trenches, and capable of being readily
excavated.
1.4
SUBMITTALS
.1
.2
Samples:
.1
.2
.3
.4
Pre-Construction Inspection
.1
1.5
QUALITY ASSURANCE
.1
Where a third party Engineer is the employee of Contractor for the purpose of trenching
support design, submit proof that Work by this Engineer is included in Contractor's
insurance coverage.
.2
.3
Submit design and supporting data at least 2 weeks prior to commencing Work.
.4
Design and supporting data submitted to bear stamp and signature of qualified
professional engineer registered or licensed in the Province of Ontario.
.5
.6
1.6
Separate and recycle waste materials in accordance with Section 01355 - Disposal of
Excess Material.
.2
Collect and separate plastic, paper packaging and corrugated cardboard in accordance
with Waste Management Plan.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
1.7
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 4 OF 13
.1
.2
.3
.4
1.8
.1
Size, depth, and location of utilities and structures shown on the Contract
Drawings are approximate only and completeness and accuracy are not
guaranteed. Prior to commencing excavation work, the Contractor shall be
responsible to notify applicable Owner or authorities having jurisdiction,
establish location and state of use of buried utilities and structures using an
outside locating firm. The locating firm shall have Secret clearance if access
is required to PWGSC facilities and for PWGSC utility information to be
provided to the locating firm as specified in Section 01117.. The Contractor
shall co-ordinate his work with the Utility Company concerned should there be
any bracing, removal or relocation of utilities.
.2
.3
Maintain and protect from damage, water, sewer, gas, electric, telephone and
other utilities and structures encountered as indicated.
.4
.5
.6
.7
A Hydro One duct runs immediately north of the proposed odour control
facility at Site 3a. This duct must not be damaged due to the works and must be
protected and supported with the use of engineered shoring or other trench
support method during construction of the utility crossings and odour control
facility. Incorporate this shoring into shop drawings and design for shoring
required in other sections.
Conduct, with Engineer, condition survey of existing trees and other plants,
fencing, service poles, wires, pavement, survey bench marks and monuments
which may be affected by Work.
.2
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 5 OF 13
available; the Contract drawings show the conceptual protection system. The protection
system is Performance Level 2 as detailed in OPSS.PROV 539.
.2
The Contractor will be permitted to utilize the staging area at Site 10 adjacent to the
protection system within the timelines specified in Section 01117 Construction
Sequences and Constraints.
.3
The Contractor shall immediately report to the Contract Administrator any observed
movement or cracking/deformation of the protection system.
1.9
STABILITY OF EXCAVATION
.1
Employ such construction methods, plant, procedures and precautions to ensure that
excavations are stable, free from disturbance and, reasonably dry.
.2
Such construction methods could include, but are not limited to:
.1
Trench boxes, soldier pile and wood lagging, interlocking sheet piling, concrete
secant, or concrete diaphragm wall. Do not utilize trench boxes when
excavations are greater than 4 m in depth. Any engineered support system other
than a trench box must have a design drawing stamped and signed by a
qualified professional engineer registered or licensed in the Province of
Ontario.
.2
.3
Surface water or free water control systems employing ditches, stone drains,
pipes and/or pumps.
.4
.3
Employ such construction methods, plant and materials to ensure that migration of fine
soil material into pipe bedding or sub-bedding from adjacent ground shall not take place.
.4
Remove boulders larger than 0.3m in size from the walls of the excavations for work
safety.
.5
Do not use clear stone or other material with high approportion of voids for bedding or
sub-bedding unless specified or ordered in writing by Engineer for specific locations.
.6
Follow procedures for trimming of sheeting, staging of excavation and ground water
control to ensure the stability of excavation and existing structures.
.7
Part 2
Products
2.1
MATERIALS
.1
Type 1 and Type 2 fill: properties to the City of Ottawa S.P. No: F-3147, S.P. No. F2120and the following requirements:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 6 OF 13
.2
Gradations to be within limits specified when tested to ASTM C136 and ASTM
C117. Sieve sizes in accordance with LS-602.
.3
Sieve
Designation
Type 1
Type 2
Type 3
Granular B
Select Subgrade
Material
Granular A
Type I
Type II
150 mm
100
100
106 mm
100
37.5 mm
26.5 mm
100
50-100
50-100
50-100
19 mm
85-100
13.2 mm
65-90
9.5 mm
50-73
4.75 mm
35-55
20-100
20-55
20-100
1.18 mm
15-40
10-100
10-40
10-100
0.300 mm
10-22
2-65
5-22
5-95
0.150 mm
2-65
0.075 mm
2-8
0-8
0-10
0-25
Notes:
1. When RAP is blended with Granular B Type I, 100% of the RAP shall pass the 75 mm sieve.
Conditions in Note 1 supersede this requirement.
2. When the aggregate is obtained from an air-cooled blast furnace slag source.
3. When the aggregate is obtained from a quarry or an air-cooled blast furnace slag or nickel slag source.
.2
Type 3 fill: approved by Engineer for use intended, clean non-clay excavated soil
material, unfrozen, free from roots, weeds, soil, topsoil, tree or shrub material, foreign or
building debris, rocks larger than 75 mm, and having a moisture content not greater than
10% by weight.
.3
Type 4 fill: Clay fill intended for construction of berm core. Clay fill should meet the
classification of Fat Clay (CH) in accordance with the Unified Soil Classification
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 7 OF 13
System. Moisture content of Clay Fill should be within 5% of the optimum moisture
content.
Part 3
Type 5 fill: Clear stone for pipe subdrains where specified on drawings: 19mm
Type I or Type II Clear Stone as per OPSS 1004 and OPSS 405.Execution
3.1
SITE PREPARATION
.1
Remove obstructions, ice and snow, from surfaces to be excavated within limits
indicated.
.2
Sawcut pavement neatly along limits of proposed excavation in order that surface may
break evenly and cleanly in accordance with Section 02226 Removal of Existing
Asphalt Pavement.
.3
Rubbish and waste material shall not be buried on site and shall be disposed of at an
MOECC approved landfill as per Section 01355 Disposal of Excess Material.
3.2
STRIPPING OF TOPSOIL
.1
Do not handle topsoil while in wet or frozen condition or in any manner in which soil
structure is adversely affected as determined by Contract Administrator.
.2
Commence topsoil stripping of areas as indicated by Engineer after area has been cleared
of brush, weeds and grasses and removed from site.
.3
Strip topsoil to depths as indicated by Engineer. Do not mix topsoil with subsoil.
.4
.5
.6
3.3
STOCKPILING
.1
Stockpile fill materials within staging areas designated on drawings and in compliance
with the Staging Planfor each site. Stockpile granular materials in manner to prevent
segregation. If the Contractor does not have sufficient space in staging areas to stockpile
excavated material, the Contractor shall arrange for, and include in their Tender Price,
the cost for offsite stockpiling/hauling or disposal and subsequent importation of suitable
backfill material. Refer to Section 01355 - Disposal of Excess Material for waste
management, testing and disposal requirements.
.2
Do not stockpile excavation materials adjacent to the trenches and other excavations
unless the constructed excavation site slope and excavation support system are designed
by the Contractor for the stockpile loads.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 8 OF 13
.3
Only inert materials can be placed within 30m of the watercourse near Site 5 (Rideau
River) and Site 6 (Ottawa River). No stockpiling of soils/aggregate is permitted within
30m of the watercourse at Site 5 (Rideau River).
.4
.5
The height and grade of stockpiles must be controlled to safe levels to prevent collapse.
The height of the stockpile shall not exceed 3.5m.
.6
.7
Refer to Section 02150 for more requirements about the excavation support system.
3.4
3.5
Engineered shoring, bracing and underpinning if required to support excavations that are
not permanent shafts shall be signed and stamped by an engineer licenced in the Province
of Ontario.
UNWATERING AND HEAVE PREVENTION
.1
.2
.3
.4
Submit for Engineer's review details of proposed unwatering and heave prevention
methods.
.5
Protect open excavations against flooding and damage due to surface run-off.
3.6
.2
Adopt method of removal of frozen ground that will not cause excessive noise, ground
vibration, or damage to adjacent structures and utilities.
3.7
EXCAVATION
.1
Excavate to lines, grades, elevations and dimensions as indicated by Engineer and shown
on the contract drawings.
.2
Remove paving encountered during excavation in accordance with Section 02226 Removal of Existing Asphalt Pavement.
.3
In general, rock excavation defined in 1.3.1.1 shall be in accordance with Section 02316
Rock Removal.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 9 OF 13
.4
Do not disturb soil within branch spread of trees or shrubs that are to remain. If
excavating through roots, excavate by hand and cut roots with sharp axe or saw and
follow the related guidelines.
.5
.6
.7
.8
Keep excavated and stockpiled materials a safe distance away from edge of trench as
directed by Engineer.
.9
.10
Dispose of surplus and unsuitable excavated material off site at an appropriate location.
.11
.12
Do not use trenching box if soil conditions or method of use are such that disturbance of
soil, bedding or pipe occurs.
.13
Earth bottoms of excavations to be undisturbed soil, level, free from loose, soft or
organic matter.
.14
.15
.16
Remove unsuitable material from trench bottom to extent and depth as indicated by
Engineer.
.17
.2
Remove and replace weakened or disturbed soil with 15 MPa concrete where
excavated surface below or beside proposed structure is disturbed or weakened
by unsuitable construction methods or procedures which may include
inadequate control of ground water or free water or action of workmen at no
extra cost.
.3
Remove and replace weakened or disturbed soil with approved granular material
compacted to 98% maximum dry density in accordance with standard Proctor
maximum dry density (SPMDD) where excavated surface below or beside
proposed utility is disturbed or weakened by unsuitable construction methods or
procedures which may include inadequate control of ground water or free water or
action of workmen.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 10 OF 13
All other areas fill with Granular B Type II placed in maximum 300 mm thick
loose lifts and compacted to not less than 95% SPMDD.
.18
Hand trim, make firm and remove loose material and debris from excavations. Where
material at bottom of excavation is disturbed, compact foundation soil to density at least
equal to undisturbed soil. Clean out rock seams and fill with concrete mortar or grout to
approval of Engineer.
.19
Division 2 shall include required excavation, trenching and backfilling for all other
divisions.
3.8
.2
Use fill of types as indicated in 2.1 and specified below and granular materials shall be in
accordance with the City of Ottawa Special Provision No. F-3147. Compaction densities
are as per OPSS 501 and to be tested as per Section 01450 Quality Control.:
.1
.2
.3
.4
Trench backfill: existing inorganic fill or native inorganic soils (upon approval
by Engineer and not including silt, clay, or organic materials), or OPSS
Granular B Type I or Select Subgrade Material as per S.P. F-2120, placed in
300mm thick lifts and compacted to 95% SPMDD.
.5
.6
If Type 3 fill is used to build up subgrade level for areas to be paved, then it is
to be placed in thin lifts and compacted to 95% SPMDD.
.7
Defective Fills: If, during progress of work, tests indicate fills do not meet
specified requirements or compaction, remove defective fills, replace, compact
and retest at no extra cost. Contractor to pay cost of retest.
.8
Where the walls of chambers are constructed using formwork, the narrow
gallery between the shoring face and the outside of the walls shall be backfilled
with 6mm clear stone chip, placed by stone slinger or chute. The stone shall
not be placed in direct contact with adjacent soil or backfill material; clear
stone shall be covered with geotextile.
Backfill placed within the frost penetration depth (1.5m below finished grade) should be
compatible in nature to the soils in the exposed trench or excavation walls to minimize
differential frost heaving. Alternatively, free draining non-frost susceptible sand or sand
and gravel conforming to the requirements for OPSS Granular B Type I shall be used for
backfill in this area with 3H:1V frost tapers.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
3.9
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 11 OF 13
Any existing inorganic fill or native inorganic soils, not including any silt, clay, or
organic content material, may be suitable for use as backfill. These materials may be
reused as backfill provided testing indicates that it meets the OPSS requirements for
Granular B Type I or Select Subgrade Material. Additional imported OPSS Select
Subgrade Material (SSM) may be imported for backfill and compacted to a minimum of
95% SPMDD.
BEDDING AND SURROUND OF UNDERGROUND SERVICES
.1
Place and compact granular material for bedding and surround of underground services
as indicated and as specified in Section 02530 Sanitary Sewer and Odour Control
Ducts, Section 02511 Water Mains, Section 02630 Storm Sewer, and as per utility
requirements for all utility relocations.
.2
3.10
BACKFILLING
.1
Do not proceed with backfilling operations until Engineer has inspected and approved
installations.
.2
Areas to be backfilled to be free from debris, snow, ice, water and frozen ground.
.3
Do not use backfill material that is frozen or contains ice, snow or debris.
.4
.5
.2
.3
.4
.5
.6
.7
Imported soil for backfill of infrastructure on NCC land shall be subject to MOECC
Table 1 standards and Canadian Council of Ministers of Environment (CCME)
Guidelines for residential/parkland use.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.11
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 12 OF 13
SUPPORT AT STRUCTURES
.1
3.12
Where pipe is laid into a structure across an excavated area, provide one of the
following:
.1
Backfill excavation below pipe with controlled density fill or 15 MPa concrete
up to first pipe joint at undisturbed soil.
.2
.3
Provide a flexible pipe joint from outside face of structure unless indicated
otherwise on the drawings.
RESTORATION
.1
Upon completion of Work, remove waste materials and debris in accordance with
Section 01355 - Disposal of Excess Material, trim slopes, and correct defects as directed
by Engineer.
.2
.3
.4
3.13
3.14
Unless otherwise directed by the Contract Administrator, the protection system may be
left in place with the top removed at least 1.2m below finished grade or ground level as
per OPSS.PROV 539. When the site is no longer required by the Contractor, the
Contractor shall backfill the staging area as per Contract Drawings and shall disconnect
protection system tie backs and remove walers and lagging.
INSPECTION AND TESTING
.1
.2
.2
.3
Carry out the internal compaction tests to ensure that the required density is
achieved, and report the results of such tests in writing.
.4
The Contractor shall provide proper and sufficient samples, ample opportunity and
access at all times for the testing company to inspect materials, operations and completed
works carried out under this Section.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02315
EXCAVATING, TRENCHING AND
BACKFILLING
PAGE 13 OF 13
.3
.4
Other inspection and testing requirements shall be in accordance with Section 01450
Quality Control.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE OF WORK
.1
1.2
As per the Geotechnical Baseline Report (GBR) and Geotechnical Data Report (GDR),
the excavations will likely extend into bedrock. This section includes the requirements
for the rock excavation using mechanical means. The rock removal by blasting is
specified in Section 02228 Blasting.
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
.15
1.3
REFERENCES
.1
1.4
SECTION 02316
ROCK REMOVAL
PAGE 1 OF 4
DEFINITION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02316
ROCK REMOVAL
PAGE 2 OF 4
.1
Rock: any solid sedimentary material which is integral with its parent mass, and boulders
or rock fragments having an individual volume greater than 1.0 m3 and which cannot be
removed by means of mechanical excavating equipment. Frozen material is not classified
as rock.
.2
Rock removal by mechanical means: rock not removed by blasting; work consists of
drilling of holes 0.30 to 0.60 m apart horizontally (as required) and 0.10 m deeper than
the bottom of the trench, and breaking rock with a hammer.
1.5
SITE CONDITIONS
.1
As per the GBR and GDR, the excavations at several locations are expected to extend
into the bedrock. Some structures will be constructed directly over the existing sewers; at
these locations the bedrock should be removed using mechanical methods (i.e., hoeramming) which will likely be slow and tedious. Blasting is permitted for rock
excavation on this project in areas not within 5m of existing sewers and other utilities.
Refer to Section 02228 Blasting for requirements of blasting.
.2
For work within 5m of existing sewers and within bedrock, it should be planned to line
drill the bedrock along the perimeter of the excavation at a close spacing in advance hoeramming to provide a clean rock face and to reduce the potential for damage to existing
infrastructure. Line drilling shall include 75 millimetre diameter holes drilled at a
maximum spacing of 300 millimetres or closer as required by the rock conditions.
1.6
MEASUREMENT PROCEDURES
.1
The rock removal consists of rock excavation within the sewer, shafts, trenches, and
associated structures and disposal of excess materials off site. See 1.9 below for
additional disposal details.
.2
The payment under this section shall be included as a unit rate pricing as described in
Section 01025 Measurement and Payment.
.3
Measurement for Payment sections and Basis of Payment sections of OPSS references
are deleted in their entirety.
1.7
SUBMITTALS
.1
Submit to Engineer and local authorities having jurisdiction for approval, written
proposal of operations for removal of rock, as per Section 01330 - Submittal Procedures.
All submittals for rock removal at Site 6 shall be subject to review by PWGSC.
.1
.2
Indicate proposed method of carrying out work, hoe ramming and line drilling
equipment. Incorporate plan with blasting if blasting is proposed as per Section
02228 - Blasting.
.3
Submit rock removal records to Engineer at end of each shift. Maintain complete
and accurate record of rock removal.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.8
SECTION 02316
ROCK REMOVAL
PAGE 3 OF 4
QUALIFICATIONS
.1
1.9
Retain other qualified rock removal experts to design and implement rock removal
techniques and measures.
WASTE MANAGEMENT AND DISPOSAL
.1
Separate, dispose, or recycle waste materials off site in accordance with Section 01355 Disposal of Excess Material. Test materials as specified in Section 01355 Disposal of
Excess Material.
.2
Collect and separate plastic, paper packaging, and corrugated cardboard in accordance
with Waste Management Plan.
.3
.4
1.10
1.11
Refer to Section 02482 Noise and Vibration Monitoring and Section 02228 Blasting
for rock excavation survey and monitoring requirements.
ROCK EXCAVATION AND VIBRATION CONTROL
.1
Refer to Section 02482 Noise and Vibration Monitoring for noise and vibration control
requirements.
Part 2
Products
2.1
NOT USED
Part 3
Execution
3.1
PROTECTION
.1
3.2
Prevent damage to surroundings and injury to persons in accordance with Section 01560
- Temporary Barriers and Enclosures.
ROCK REMOVAL
.1
Coordinate this section with Section 01705 Contract Work Health and Safety Clauses.
.2
Perform all work according to OPSS 120 when blasting and as discussed below unless
otherwise noted.
.3
.4
Use rock removal procedures to produce uniform and stable excavation surfaces.
Minimize overbreak, and avoid damage to adjacent structures.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02316
ROCK REMOVAL
PAGE 4 OF 4
.5
Scale, pressure wash and broom clean rock surfaces, which are to bond to concrete.
.6
Excavate trenches to lines and grades to minimum of 300 mm below pipe invert
indicated. Provide recesses for bell and spigot pipe to ensure bearing will occur
uniformly along barrel of pipe.
.7
.8
.9
Use pre-shearing, or other smooth wall drilling and blasting techniques unless specified
otherwise or directed by Engineer.
.10
Remove boulders and fragments that may slide or roll into excavated areas.
.11
.12
Perform pre- and post rock removal survey to the approval of the Engineer to determine
rock removal quantities for payment.
3.3
ROCK DISPOSAL
.1
Dispose of surplus removed rock under the direction of Contract Administrator and in
accordance of Section 01355 Disposal of Excess Material.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
RELATED SECTIONS
.1
.2
1.2
SECTION 02362
DUST CONTROL
PAGE 1 OF 2
REFERENCES
.1
1.3
.2
.3
.4
.5
1.4
Separate and recycle waste materials in accordance with Section 01355 - Disposal of
Excess Material.
.2
.3
.4
Fold up metal banding, flatten and place in designated area for recycling.
Part 2
Products
2.1
MATERIALS
.1
.2
.3
Use of petroleum products for dust control is not allowed at any time.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 3
Execution
3.1
APPLICATION
SECTION 02362
DUST CONTROL
PAGE 2 OF 2
.1
Apply calcium chloride and/or water to City roads, recreational pathways, sidewalks and
Contractors access road(s) with equipment approved by Contract Administrator at least
3 times per week generally with a 4-hour minimum each time.
.2
Apply water and/or aqueous calcium chloride with distributors equipped with means of
shut-off and with spray system to ensure uniform application.
.3
Utilize vehicle wash stations at each site to minimize mud tracking for the duration of the
works. Use flushers if required and upon request by Contract Administrator to minimize
mud tracking.
.4
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE
SECTION 02400
SHAFT CONSTRUCTION
PAGE 1 OF 14
.1
.2
This Section delineates the requirements for shaft excavation in soil and rock and
includes:
1.2
.1
Design by the Contractor of the excavation support systems for shafts in soil
overburden, transition zones and bedrock.
.2
.3
.4
.5
.6
.7
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02400
SHAFT CONSTRUCTION
PAGE 2 OF 14
.10
.11
.12
.13
.14
.15
.16
.17
.18
.19
1.3
REFERENCES
.1
Perform all shaft work in accordance with all applicable provincial and local regulations,
codes, and standards.
.2
.3
.1
.2
CSA A3003 Chemical Test Methods for Cementitious Materials for Use in
Concrete and Masonry
.3
.4
.5
.6
.7
.8
.9
CSA W47.1-09 (Update No. 5 June 2012) Certification of Companies for Fusion
Welding of Steel Structures.
.10
.11
ASTM A29/A29M-12 Standard Specification for Steel Bars, Carbon and Alloy,
Hot-Wrought, General Requirement for.
.12
ASTM A322-07 Standard Specification for Steel Bars, Alloy, Standard Grades.
Ontario Provincial Standard Specifications (OPSS), including, but not limited to:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02400
SHAFT CONSTRUCTION
PAGE 3 OF 14
.1
OPSS 403 Rock Excavation for Pipelines, Utilities, and Associated Structures in
Open Cut
.2
.3
.4
.5
.4
.5
.6
Environmental Protection Act, R.S.O. 1990, c. E.19. R.R.O. Reg. 347: General - Waste
Management, as amended;
.7
.8
Management of Excess Soil A Guide for Best Management Practices, prepared by the
MOECC, dated January 2014.
1.4
RESPONSIBILITY
.1
As stated on the Contract Drawings, the Contractor is responsible for determining the
excavated diameter for each of the shafts consistent with its selected means and methods
of construction, required minimum diameters for construction of permanent structures,
and other requirements and tolerances as stated in the Specifications and shown on the
Contract Drawings. Any overexcavation or overbreak relative to Contractors established
excavation limits shall be supported and backfilled with shotcrete or concrete as
required. Any additional costs related to such overexcavation or overbreak shall be
considered to be incidental and Contractor shall be due no additional compensation. In
addition, if the Contractor employs a subcontractor to complete shaft excavation and
support, the Contractor shall coordinate with the subcontractor to confirm who is
responsible for any additional costs associated with the overexcavation or overbreak,
including additional volumes of shotcrete or concrete.
.2
The Contractor shall be responsible for design of excavation support systems for all
excavations required for the work, including associated excavations not specified herein
or shown on the Contract Drawings; and excavation support systems to accommodate
enlargements and other Contractor conveniences such as tail tunnel, switch locations,
and thrust blocks. Contractor designed elements shall be in accordance with the Contract
Documents, referring to all of the Contract Drawings, Specifications, and shop drawings
submitted to provide details of support systems, attachments, embedments, finishes and
other construction that affects the work covered under this Section.
.3
It is the responsibility of the Contractor and its excavation support system designer to
review the Contract Drawings, Specifications, and existing site conditions prior to
bidding to ascertain the extent of the work requiring excavation support systems.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02400
SHAFT CONSTRUCTION
PAGE 4 OF 14
.4
.5
Existing utilities will be either within or adjacent to some of the shafts. For utilities that
are shown on the Contract Drawings, the Contractor is responsible for the protection and
relocation of existing utilities, and the removal of abandoned utilities, as required for the
construction of the shafts as shown on the Contract Drawings or indicated in the
Contract Documents. If existing utilities shown on the Contract Drawings are damaged
as the result of the Contractors construction activities, the Contractor is responsible for
the cost of repairing damaged utilities. Unless otherwise shown, inside diameters of the
utilities are shown on the Contract Drawings. The Contractor should field verify all
utilities within 5 metres of the shafts prior to excavation. If the Contractor finds other
utilities not shown on the Contract Drawings, the Contractor shall notify the Contract
Administrator and will be compensated for reasonable time and materials required for
relocating these utilities by a Contract Modification.
1.5
DEFINITIONS
.1
Excavation Support (Shoring) System: the support system provided to maintain stability
of an excavation made for any purpose and to be occupied by Contractor, and
construction activity, until the permanent structure is complete in place or piping and
backfill is in place, the excavation is closed, and the structure is backfilled. Excavation
support may be installed prior to or concurrent with excavation, depending on ground
conditions and type of support. In the context of this Specification, excavation support
includes support for both soil and rock excavations.
.2
Shaft or Workshaft: The terms shaft or "workshaft" shall mean the temporary ground
excavation requiring an excavation support system until the shaft structure or permanent
facilities to be constructed within the excavation are complete and the excavation around
and over the structure is backfilled.
.3
.4
.5
.6
1.6
EXISTING CONDITIONS
.1
Contractor shall comply with all restrictions set as conditions under which easements,
agreements or permission (permits) were granted to the City or to the Contractor to
perform the work of this Contract.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02400
SHAFT CONSTRUCTION
PAGE 5 OF 14
.2
Contractor shall inspect the locations where the shafts are to be built to identify the
conditions under which the work will be performed and with all necessary detail as to the
orderly prosecution of the work.
.3
1.7
SUBMITTALS
.1
.2
At least 30 days prior to beginning any shaft excavation, Contractor shall submit
the name of its excavation support system designer. If the excavation support
system designer is a firm, Contractor shall identify the individual employee of
the identified firm who will prepare and assume professional responsibility for
the excavation support system designs. In accordance with the Ontario
Professional Engineers Act (R.S.O 1990, C. P.28), this individual must be a
Professional Engineer licensed in the Province of Ontario.
.2
At least 30 days prior to starting any shaft construction, submit a narrative along
with shop and working drawings, the Contractor proposes method of
construction and excavation intended in performing the work in this Section. The
submittal shall include, but not be limited to:
.1
.2
.3
.4
.5
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
SECTION 02400
SHAFT CONSTRUCTION
PAGE 6 OF 14
.7
.8
.9
Ventilation plan;
.10
.11
.12
.13
A site plan for each shaft indicating utilities, use of access roads, site
grading and site development details for the excavation and all work
areas, and the proposed limits of disturbance surrounding each
excavation;
.14
.15
.16
Flood contingency plans for shafts and methods for preventing ingress of
water inflow from surface.
.2
.3
.4
.5
No less than 30 days prior to start of any excavation for which rock bolts or rock dowels
are to be used, provide the submittal regarding rock dowels and rock bolts required under
Section 02437, Rock Reinforcement and Excavation. Contractor is not required to
provide a duplicate submittal under this Section.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02400
SHAFT CONSTRUCTION
PAGE 7 OF 14
.5
No less than 30 days prior to start of any excavation for which welded wire mesh, steel
straps, or rolled steel are to be used, provide the submittal regarding welded wire mesh,
steel straps, or rolled steel channels required under Section 02437, Rock Reinforcement
and Excavation. Contractor is not required to provide a duplicate submittal under this
Section.
.6
Conform to any additional applicable submittal requirements that are stated in Section
02150, Excavation Support System.
1.8
PERFORMANCE REQUIREMENTS
.1
Excavation support systems are not designed, and are shown only conceptually on the
Contract Drawings. It is the Contractors responsibility to select and design the
excavation support systems for shaft excavations through the soil overburden and rock
consistent with its means, methods and equipment for completing the work.
.2
Comply with Section 02439, Pre-excavation Grouting from Surface for sealed shafts.
.3
Based on expected soil overburden conditions as described in the GDR and any baseline
statements provided in the GBR, expected impacts on groundwater head in the rock and
soil, and resulting impacts on the Champlain Sea Clay that exists in the subsurface along
and adjacent to the tunnel alignment, the Contractor is required to use in overburden
sealed excavation support system as defined in Section 02150, Excavation Support
System, for the shafts identified in Section 02150.
.4
The excavation support systems for the rock portions of the shafts or other excavations
shall be designed based on ground conditions described in the GDR and shall consider
statements regarding anticipated ground behaviour in the GBR, as well as baseline
statements in the GBR. It shall be the responsibility of the Contractor in all instances to
assess ground conditions prior to start of excavation, and design excavation support
elements as Contractor determines to be necessary to adequately and safely carry any and
all loads that may be applied to the excavation support system. Contractors excavation
support system designer shall review rock mass conditions as shaft and other excavations
proceed and design any necessary modifications to the support system. The Contractor
shall design the excavation support system to be compatible with its choice of
construction means and methods. Any approvals or comments given by the Contract
Administrator to any procedure, operation, or construction method do not relieve the
Contractor from full responsibility for the adequacy and safety of the proposed
excavation method or the Contractors proposed design of excavation supports and
construction of the supports.
.5
Design of the excavation support systems for the rock portions of the shafts shall
consider the need to limit or prevent groundwater infiltration to minimize the potential
for impacts on the Champlain Sea Clay as defined in Section 02140, Groundwater
Control. Groundwater control methods, which could utilize methods such as preexcavation grouting or grouting from within the excavation or sprayed linings or
membranes, shall be used as necessary. Refer to Section 02480, Geotechnical and
Structural Instrumentation and Monitoring for limits on allowable groundwater level
drawdowns or ground movements in areas underlain by Champlain Sea Clay as described
in the GBR.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02400
SHAFT CONSTRUCTION
PAGE 8 OF 14
.6
The design shall provide groundwater control or isolation, bottom stability and system
stiffness sufficient to meet the Contract requirements for control of water and for
protection of adjacent work and property as specified herein. The design shall provide
for placement of excavation support systems and removal of excavation support systems
where required and feasible. The design shall provide for construction of the permanent
work, and all other construction operations and requirements.
.7
Design shaft excavation support systems and working slabs to withstand earth pressures,
groundwater pressures, frost loads, bottom heave, equipment loads, thrust block loads
from launching the TBM, loads from making a portal for tunneling, applicable traffic and
construction loads, buildings and other surcharge loads to allow the safe construction of
the tunnel without movement or settlement of the ground, and to prevent damage to or
movement of adjacent structures, streets, and utilities. Design excavation support
systems to be compatible with the geologic conditions described in the GDR and any
applicable baselines as stated in the GBR and in accordance with CISC and CSA code
provisions, as applicable.
.1
Design the support system to minimize horizontal and vertical movements, and
to protect adjacent utilities from damage. The type and stiffness of each ground
support system and the methods of ground support installation shall be designed
and constructed in order to meet the ground movement limits and adjacent
property protection requirements specified herein and in Section 02480,
Geotechnical and Structural Instrumentation and Monitoring.
.2
.3
.4
.5
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
1.9
SECTION 02400
SHAFT CONSTRUCTION
PAGE 9 OF 14
.2
.3
Final Precast Linings for Shafts and other Permanent Structures conform to tolerances specified in Section 03410, Precast Concrete
Structures.
.2
1.10
Store and protect all rock reinforcement materials, including steel elements, accessories,
resin grout, cement and any additives, in accordance with the manufacturer's
recommendations and in a manner that prevents damage or deterioration.
MEASUREMENT AND PAYMENT
.1
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to construct the shafts and associated
structure excavations and chambers as specified herein and no separate payment shall be
made.
Part 2
Products
2.1
MATERIALS
.1
.2
Resin used as grout for rock dowels, rock bolts, or spiles shall be the product of
an established manufacturer who has been regularly engaged in production of
these products for at least 5 years, capable of developing the minimum yield
strength of the dowel. Resin cartridges shall have diameter and length
compatible with the work. Cartridge casing shall be constructed of a saturated
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02400
SHAFT CONSTRUCTION
PAGE 10 OF 14
.3
.2
.3
Cement grout for encapsulating rock dowels and bolts shall be shrinkagecompensating grout specifically designed for encapsulation of rock dowels and
rock bolts, and the standard product of a recognized manufacturer of such grouts.
.2
.3
.4
.5
.6
Steel straps and rolled steel channels: Used to support the rock surface between
dowels or bolts. Conform to ASTM A36 and be compatible with dowels or bolts,
and with the intended function.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02400
SHAFT CONSTRUCTION
PAGE 11 OF 14
.3
Bearing plates: Conform to ASTM A36, and meet the load/deflection criteria of
ASTM F432. Bearing plates against rock shall be a minimum of 9.5-mm thick
and have a minimum bearing area of 0.0232 square metres. Holes in plate shall
be reamed and beveled on the rock side and shall be large enough to permit 30
degree rock dowel or rock bolt skew in all directions from normal centerline.
.4
Nuts: Shall be hex nuts of the heavy-duty type, shall be compatible with rock
bolts and rock dowels, and shall develop at least 125 percent of the minimum
yield strength of the element.
.5
Part 3
Execution
3.1
GENERAL
.1
All shafts shall be enclosed with a security fence as detailed in the Contract Drawings
and conforming to requirements stated in Section 01560, Temporary Barriers and
Enclosures, which shall be secure at any time the Site is unattended by Contractors
personnel. The fence shall have all necessary gates and entrances with keys furnished to
the Contract Administrator for all locking devices. In addition, the Contractor shall
provide barricades and covers at the top of shafts in accordance with these specifications.
.2
Provide lights, signage, and safety protection of shafts as per Section 01705 - Contract
Work Health and Safety Clauses, Section 01710 - Tunnel and Shaft Safety, and Section
01560 Temporary Barriers and Enclosures.
.3
.4
Perform shaft construction activities in conformance with vibration and noise limitations
and monitoring requirements as stated in Section 02482, Noise and Vibration
Monitoring.
3.2
EXCAVATION
.1
Provide necessary control and drainage of all construction water in accordance with
Section 02140, Groundwater Control and Section 01160, Erosion and Sediment Control
Plan.
.2
The methods of constructing the shafts are at the option of the Contractor, subject to
restrictions as stated in this and other Specification sections and subject to review by the
Contract Administrator. Excavations shall be made to the lines, grades, and dimensions
shown on the Contract Drawings or established by the Contractors design engineer.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02400
SHAFT CONSTRUCTION
PAGE 12 OF 14
.3
.4
Excavated soil that meets the geotechnical requirements and Standards in O. Regulation
153/04 as amended, can be considered suitable for reuse on site within the Project site
bounds. Material that meets Table 1 Standards can be reused within the Project site
bounds. Material that meets Table 2 Standards can only be reused on-site at locations
which generated the material and similarly, material that meets Table 3 Standards can
only be reused on-site at locations which generated the material. Permission for material
reuse must be provided by the Contract Administrator in advance.
.5
Excavation shall be confined to within the limits of the shaft and as required for the type
of construction to be used and in such manner as to minimize any settlement of the
ground near the shaft.
.6
.7
Shaft excavation shall be done in such manner as to provide adequate support at all times
to adjacent or nearby conduits, structures, or roads, including sidewalks, so as to offer no
hazard to pedestrians, train, truck or automobile operations. Excavation support shall be
substantial and safe, and all work shall be done in full conformity and subject to the
inspection of all affected parties. If and when required, and to the degree necessary, the
Contractor shall provide additional support as may be necessary.
.8
Monitor for explosive and toxic gasses and ventilate in accordance with requirements
stated in Section 01710, Tunnel and Shaft Safety and Section 02444, Tunnel and Shaft
Ventilation and Utilities.
.9
3.3
All material that will not be reused on site shall be removed from site immediately.
.2
All excess material resulted from shafts excavation that is to be removed from site shall
comply with Section 01355, Disposal Excess Material.
.3
Load all excavated material identified as contaminated or as waste into required haulage
trucks and dispose off-site at an approved disposal sites licensed to receive the waste.
Pay for all haulage and disposal fees for contaminated excavated material.
3.4
Excavation support systems for shaft and structure excavations in soil shall consist of
secant pile walls, slurry diaphragm walls or comparable systems that provide positive
ground support ahead of the excavation, and act as watertight excavation systems for the
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02400
SHAFT CONSTRUCTION
PAGE 13 OF 14
shafts designated as sealed, and otherwise satisfy the requirements of the Contract and
are compatible with ground and groundwater conditions as described in the GDR and are
consistent with applicable baselines as stated in the GBR.
.2
Support systems shall be installed to permit the safe execution of the work, and to ensure
that no ground loading or other loading will be placed on the new work prior to
completion and until design strength of the structure being constructed has been reached.
.3
.4
During periods of shutdown, fully support the shaft base to maintain bottom stability,
prevent lost ground and limit the potential for groundwater movement through the shaft
base.
.5
Install excavation support systems in a manner to limit vibrations on the ground adjacent
to the nearest structure to a peak particle velocity that conforms to limits stated in
Section 01119 Preservation and Protection and Section 02482, Noise and Vibration
Monitoring.
.6
During excavation, if more than 25 mm of void space develops outside of the support
system in soil, contact grouting shall be performed behind excavation support systems
specified herein. Contact grouting shall be performed to provide firm and uniform
contact between the support system and the ground, limit or prevent ground movement
into the excavation and to control groundwater infiltration. Grout holes shall be located
as necessary to fill all voids.
3.5
.2
Unless the Contractors design engineer design the shotcrete and rock dowels to
withstand groundwater load, groundwater infiltration shall be controlled by installing
drain pipes, or other means so that shotcrete will be unaffected by the action of the
water.
.3
Vary support systems as necessary to suit the rock conditions encountered in the
excavation.
.4
Install excavation support around tunnel eyes as determined to be necessary before the
excavation liner or any rock reinforcement at the penetration is cut or removed. Install
any special framing, or additional bracing or shoring determined necessary by Contractor
or Contractors excavation support system designer before the excavation liner or any
rock reinforcement at the penetration is cut or removed.
3.6
CONTACT GROUTING
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.7
SECTION 02400
SHAFT CONSTRUCTION
PAGE 14 OF 14
SHAFT BACKFILL
.1
3.8
.1
Remove excavation support systems that are left in place following shaft construction to
a depth of at least 2 metres below the finished ground surface. Leave in place deeper
shaft excavation support system elements that cannot be removed safely and without
causing settlement or damage to the work or adjacent property. The Contractors
excavation support system designer shall be responsible for determining if excavation
support systems can be safely removed. Excavation support system elements that are left
in place shall be at the Contractors expense.
.2
The Contractor shall be responsible for repairing any settlement or damage to the Work
or to adjacent property as a result of removing excavation support systems. Excavation
support systems that cannot be safely removed and without causing settlement or damage
to the Work or adjacent property shall be left in place, at no additional cost to the City.
Restoration of any damage and the cost of remediating disturbed backfill or adjacent
property damage caused by removal of ground support systems shall be at the
Contractors expense.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE OF WORK
.1
1.2
SECTION 02405
STEEL LINER PLATES
PAGE 1 OF 3
.1
.2
.3
.4
.5
.6
.7
.8
.9
1.3
REFERENCES
.1
All shaft work shall be performed in accordance with all applicable provincial and local
regulations, codes, and standards.
.2
.3
1.4
SUBMITTALS
.1
Conform to Section 02400, Shaft Construction and Section 02150, Excavation Support
System, as applicable.
.2
Submit calculations for the design of the Steel Liner Plate sealed and signed by a
Licensed Engineer in the Province of Ontario.
.3
Submit a detailed plan for grouting the void space on the exterior of the Steel Liner
Plate, including grout coupling location and spacing.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.5
SECTION 02405
STEEL LINER PLATES
PAGE 2 OF 3
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to providing and installing steel liner
plates as specified herein for excavation support of shafts where steel liner plates are
applicable and no separate payment shall be made.
Part 2
Products
2.1
General
.1
The Contractors excavation support system design engineer shall specify excavation
support system material requirements in accordance with the submitted designs. The
materials, however, shall meet the minimum requirements listed below.
Incorporation of used prefabricated elements into excavation support systems is
permitted, provided the strength and stability of used elements is verified prior to
incorporation, and allowances made for lost strengths, if any, due to existing damage or
deterioration.
2.2
Materials
.1
All structural steel used for the supporting systems, whether new or used, shall
be sound and free from defects that may impair their strength.
.2
Part 3
Execution
3.1
General
.1
General Procedures: Conform to Section 02400, Shaft Construction and Section 02430,
Tunnel Excavation by Tunnel Boring Machine (TBM) and Section 02150, Excavation
Support System, as applicable.
.2
3.2
Install liner plates for shaft installations in conformance with the plate manufacturer's
recommendations, and in a manner that will not deform or overstress the completed
rings. Prevent liner plate from deflecting more than 3 per cent of design diameter under
applied ground load.
.2
Install bolts and nuts specified in the liner plate design, and tighten in conformance with
manufacturer's recommendations. Flanges shall be clean and free from material that
could interfere with proper bearing. Stagger longitudinal joints in adjacent rings by onehalf plate or at least two bolt spaces.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02405
STEEL LINER PLATES
PAGE 3 OF 3
.3
Contractors excavation support system designer shall determine the need for internal
steel rib supports for the liner plate system. Place steel rib supports as determined
necessary. Use tie rods and braces to secure ribs against distortion. Block ribs against
liner plate with hardwood wedges or blocks, and nail wedges as necessary to prevent
loosening.
.4
Liner plate shall be assembled in a true circle and to the lines and grades presented on
the excavation support system plans. Contractor shall use hog rods or other restraint as it
determines to maintain liner plate in a true circle until their grouting operations are
completed.
.5
Contact grout annular space behind liner plate to ensure firm and uniformly distributed
contact between the liner plate and the excavated surface. Contact grout as frequently as
necessary, but at least once per shift. Maintain liner plate ring in a true circle until
contact grout is placed and set, using steel ribs, tie rods, or other restraint as necessary
.6
.7
Prior to allowing excavation to stand overnight, advance the liner plate to within one
liner plate width of the excavation base, and contact grout.
3.3
Shaft Backfill
.1
3.4
.1
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE OF WORK
.1
1.2
SECTION 02407
SHAFT SECANT PILES
PAGE 1 OF 12
The Work for this Section includes design and construction of secant pile shafts for
excavation support for shafts designated as sealed shafts or where elected by the
Contractor.
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
1.3
REFERENCES
.1
Except as otherwise indicated, the current editions of the following specifications and
standards apply to the Work of this Section.
.2
.3
.1
.2
RP 13B-1, Recommended Practice Standard Procedure for Field Testing WaterBased Drilling Fluids
ASTM
.1
.4
Other
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.4
SECTION 02407
SHAFT SECANT PILES
PAGE 2 OF 12
DEFINITIONS
.1
Secant Pile Walls: Concrete walls that are formed with overlapping concrete piles that
are reinforced with steel beams or cages of steel reinforcing bars. The concrete is placed
using the tremie method, below existing grade in fluid-filled and cased bored holes
stabilized with bentonite slurry. Secant piled walls are placed prior to excavation in a
complete perimeter around the workshaft.
.2
Defect/Defective Pile: The following will be considered defects and require satisfactory
repair or replacement of defective piles:
1.5
.1
.2
.3
.4
Voids/cavities
.5
.6
Honeycombing
.7
SUBMITTALS
.1
Provide design calculations and drawings for secant pile walls and groundwater cut-off
that are prepared, stamped, and signed by a registered Professional Engineer licensed in
the Province of Ontario.
.2
Name and experience resume of the drilling superintendent in charge of secant pile wall
construction operations.
.3
Provide engineering calculations and design assumptions for loads, stresses and
deformation of the secant pile wall during intermediate construction stages as well as the
final stage.
.4
For concrete and reinforcing steel that is part of the Work of this Section, submit mix
designs, and other submittals specified in the requirements stated in Section 03300, Castin-Place Concrete (Shafts and Underground Structures).
.5
.6
Show configuration and details of the completed secant pile walls, and proposed
equipment and method of construction, including the following:
.1
.2
.3
Details of plates, sleeves, pipes, and other embedded items, including freeze or
grout pipes, and requirements for instruments and utilities to be installed in or
through the wall.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.7
SECTION 02407
SHAFT SECANT PILES
PAGE 3 OF 12
.4
.5
.6
.7
Sequence of construction of the various secant piles forming the shaft walls.
.8
.9
.10
.11
Slurry mix composition, and methods of monitoring and testing to comply with
requirements specified herein.
.12
.13
.14
.15
.16
.17
.18
Measures and repair methods to protect the public and surrounding property
from hazards inherent in the operations, including leakage and spillage of slurry.
.19
Location of truck cleaning stations and methods of ensuring that haul trucks are
clean and that no spillage of excavated material from haul trucks occur on
existing streets.
.20
.21
Concrete mix design including strength at three days, seven days and 28 days.
Trial mix test results is to indicate strength at three days and slumps immediately
after mixing.
.22
.23
Two samples of proposed spacers (side and bottom) for maintaining reinforcing
steel in position.
.24
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
SECTION 02407
SHAFT SECANT PILES
PAGE 4 OF 12
.3
.4
Pile identification.
.2
Plan dimensions of the excavation and elevations of top and bottom of piles.
.3
Dates and times of pile borings, reinforcing steel placement and tremie concrete
placement. Indicate volume of excavation, and theoretical and actual volume of
concrete placed.
.4
.5
Reference to steel reinforcing shop drawings, cutouts, and other devices in the
temporary support system. Indicated approved variations from shop drawings, if
any.
.6
.7
.9
Provide results of quality control tests performed on the bentonite slurry to the Contract
Administrator promptly after the test results are completed. Submit copies of job test
records to the Contract Administrator each week.
.10
Groundwater Cut-off:
.11
1.6
.1
.2
Refer to Section 02150, Excavation Support Systems for the allowable inflows.
.3
Work Plan to address methods to be used to monitor and verify bottom stability
of shaft during all phases of construction until the completed structure can safely
resist hydrostatic uplift loads.
Shaft Excavation:
.1
.2
Contingency Plan setting forth steps that will be taken should deformation of the
shaft's secant pile wall exceed the values specified by the Contractor's excavation
support designer or cause movements of any monitored structures or
infrastructure that equal or exceed specified values. Include the remedial steps to
be utilized to arrest movement, and reinforce or improve the walls, such that
excavation may continue.
EXISTING CONDITIONS
.1
1.7
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.8
SECTION 02407
SHAFT SECANT PILES
PAGE 5 OF 12
DESIGN CRITERIA
.1
In accordance with minimum criteria and information for design of lateral loading
conditions indicated in the GBR. These criteria are intended to serve as guides in the
design of the secant pile wall walls and are the minimum acceptable. Account for the
varying field and subsurface conditions, as well as any surcharge load imposed by
equipment and material in the design.
.2
The secant pile support of excavation system shall be designed to prove sufficient
rigidity to prevent damage to adjacent structures from the ground movements and
distortions resulting from excavations. As a minimum, the support of excavation systems
shall be designed to limit ground movement at adjacent structures to the tolerances and
in accordance with the following requirements:
.1
Secant piles vertical shall be within a tolerance of 1:200, or 0.5% of total high.
.2
.3
.3
.4
Construct the inside face of the secant pile wall to be free from flaws and within the
tolerances indicated in this Section. Remove over poured concrete that encroaches within
the final lining if secant pile walls are used at workshaft locations where permanent
chambers will be constructed.
.5
Leakage: Completed secant piles shall be cleaned to bare concrete by pressure washing.
After cleaning, the exposed secant pile wall shall be free of all flowing water. Seal all
flowing leaks in the secant pile wall. Flowing leaks shall be defined as a leak from which
the water moves under the effects of wind or gravity. Moist patches that are not flowing
are acceptable.
.6
Minimum factor of safety for uplift resistance during construction is 1.1, using dead
weight only.
1.9
TOLERANCES
.1
.2
Construct the secant piles vertical, conforming to tolerances as stated in Section 02400,
Shaft Construction.
.3
Remove any protrusions, bulges, or cavities that compromise the wall design, interfere
with the means and methods or interfere with the final structure.
.4
Repair secant pile wall as necessary and prior to excavation advance below defective
location to ensure minimum contact between adjacent interlocking secant piles as per
designed by contractors design engineer and as not to exceed the leakage criteria
indicated in this Section.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02407
SHAFT SECANT PILES
PAGE 6 OF 12
.5
Formed Recesses: Position formed recesses and other devices necessary for the
temporary support system and other appurtenant structure indicated within 75 mm of the
indicated location.
.6
.7
1.10
.1
.2
.3
.4
Dowels: 75 mm from indicated position with respect to any slab, beam or other
pertinent structure.
.5
Top of steel and bottom of steel elevations: As stated for vertical tolerance,
except maintain minimum of 75 mm of cover.
Secant pile walls must not deflect laterally more than 25 mm during the excavation
process.
MEASUREMENT AND PAYMENT
.1
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 00400, Form of
Tender and Section 01025, Measurement and Payment for all work required to construct
shaft secant piles as shown on the Contract Drawings and excavate the EWT and NST
tunnels by TBM as specified herein and no separate payment shall be made.
Part 2
Products
2.1
EQUIPMENT
.1
Use equipment with capability to remove all material of whatever nature from the
excavation, so arranged as to permit the free vertical passage of slurry within the
excavation (when used) and to prevent development of suction or pressure, and such that
excavations do not exceed specified tolerances.
.2
Use boring equipment having adequate capacity including power, torque, and down
thrust to excavate a hole of both the maximum design diameter and to a depth minimum
of 5 m into bedrock.
.3
Slurry Mixing: Use equipment that produces a stable suspension of bentonite and water
along with necessary mechanical agitation. Transport slurry by means of a temporary
pipeline or other methods accepted by the Contract Administrator.
.4
Slurry Reclaiming: Use equipment that separates the bentonite from the excavated
material in a matter to clean the bentonite of soil particles before recirculation.
.5
Guidewalls: Use equipment that aids in the control of secant pile surface collaring,
positioning, and verticality during boring to meet the tolerances specified in this Section.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.2
SECTION 02407
SHAFT SECANT PILES
PAGE 7 OF 12
MATERIALS
.1
Bentonite Drilling Fluid Material: Selected from the substances described in API RP
13A as determined by the mud design engineer to produce slurry having the properties
and meeting the performance criteria specified below.
.2
Mix Design: Unless otherwise approved by the Contract Administrator, obtain slurry
(mud) design from a specialized drilling mud designer. Hydration time for bentonite
slurry is dependent on methods used for mixing, agitation, and storage, but a minimum of
six hours before use.
.3
Ingredients: Additives and chemicals may be added to the slurry, upon the approval of
the Contract Administrator, to maintain the necessary properties. Restrict the use of
polymers and additives, and their disposal to all applicable laws, rules, and regulations.
.4
Lost Circulation Material (LCM): As necessary to prevent loss of slurry through wall
and bottom of borings.
.5
Water: Clean, potable, and free of impurities detrimental to slurry, and compatible with
the slurry mix design.
.6
.7
Performance Criteria:
.1
Hydrostatic Head Produced: Sufficient to prevent water and soil inflow to the
excavation. Maintain maximum head in pile excavation at all times.
.2
.3
Stability and Flow: Ensure that the slurry will remain stable and fluid during
excavation and until concreting is completed and flows without gelling under
displacement by concrete.
.4
Slurry Properties:
.1
.2
.3
.4
.5
.6
.7
Storage time: six hours minimum hydration time prior to pile borehole
use.
.8
Sand Content: Maximum five per cent measured 305 mm from the
bottom of the pile, prior to concreting.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02407
SHAFT SECANT PILES
PAGE 8 OF 12
.8
Concrete for cast-in-place secant piles shall be in accordance with the requirements for
concrete as stated in Section 03300, Cast-in-Place Concrete (Shafts and Underground
Structures).
.9
Steel Reinforcing for secant piles shall be in accordance with the requirements stated in
Section 03200, Concrete Reinforcement.
.10
Grout shall be in accordance with the requirements for grout as stated in Section 02439,
Pre-Excavation Grouting from Surface.
Part 3
Execution
3.1
GENERAL
.1
Perform preparatory work to discover, protect, maintain, relocate and restore utility
service facilities. Conform to applicable requirements for site preparation, utility
identification and utility relocation as stated elsewhere in the Contract Documents.
.2
Perform construction that will allow a minimum elevation of slurry 0.6 m below ground
level.
.3
Conduct Work of this Section so as not to damage facilities or improvements that are to
remain in place.
.4
Employ construction methods that prevent the spillage of excavated materials, bentonite
slurry, or concrete into utilities, streets, sidewalks, or other facilities.
.5
Do not start secant pile wall excavation until geotechnical instrumentation for
monitoring shaft excavation other than that to be included with the secant piled wall is
installed. Instrumentation to be installed shall be in accordance with Section 02480,
Geotechnical and Structural Instrumentation and Monitoring.
3.2
DEMONSTRATION TESTING
.1
3.3
Demonstration testing shall be conducted on two piles that are separate from, and not
part of, the secant pile wall. Acoustic measuring devise measurements will need to be
performed on these piles. The slurry manufacturers technical representative shall be
onsite during the construction of the demonstration piles. Submit the results of the
acoustic measuring within a week of testing to the Owner for review.
BORINGS OF SECANT PILES
.1
Use excavation and boring equipment with the capacity specified in Part 2 in this
Section. The equipment shall further be able to meet the specified pile verticality
tolerances.
.2
Where caving occurs, install temporary casing as necessary to maintain the hole until
concrete is placed. Provide hole excavations with flat bottom. Remove temporary casing
while the concrete remains workable. Furnish at least 30 linear metres of ready-to-use
temporary casing at the project site.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02407
SHAFT SECANT PILES
PAGE 9 OF 12
.3
Use boring methods that will minimize over-excavation and loosening and caving of
material outside designed pile diameter. Anticipate that boulders and obstructions as
indicated by descriptions in the GDR and baseline statements in the GBR may be
encountered in excavating for piles and provide procedures and equipment for their
removal. Contain excavated spoil. Pump slurry to a central processing plant.
.4
Perform borings continuously from ground surface to the required depth. Excavate in a
manner that does not cause movement or loss of ground.
.5
Add slurry to the hole as necessary to prevent caving. Fill each boring and maintain with
a stable suspension of slurry. Advance hole through the slurry.
.6
Perform borings near existing structures and utilities that are to remain in place without
causing damage to, or movement of these facilities.
.7
.8
Do not advance borings until concrete in adjacent secant pile has cured for a minimum of
24 hours. Limit tip elevation differences between the bottoms of adjacent piles to
600 mm, unless otherwise approved by the Contract Administrator to accommodate field
conditions.
.9
Advance secant pile borings using guidewall systems as required to maintain horizontal
positioning and verticality tolerances specified in this Section.
3.4
.2
Prior to placing reinforcing steel and concrete in the pile borehole, clean the bottom of
the hole of all loose material, and inspect hole to determine that the required depth and
diameter had been achieved.
.3
Do not place reinforcing steel assemblies that are distorted. Accurately locate and secure
in place the reinforcing steel assemblies prior to and during the concrete placement. Use
suitable guides and spacers to maintain a minimum 125 mm cover between reinforcing
steel and the walls of the pile excavation as the reinforcing steel assembly is lowered into
the slurry-filled pile borehole. Protect and maintain the alignment of block out panels,
brace plates, and other specified connection during placement of the cage.
.4
Install outer casings for geotechnical instrumentation and grout pipes in secant pile as
required.
.5
Place concrete as soon as possible after completion of pile hole drilling, and reinforcing
steel components have been installed. Do not leave holes open longer than eight hours
after drilling is completed or overnight at any stage of excavation.
.6
Place concrete by tremie method, in such a manner that the concrete displaces the slurry
progressing from the bottom and rising uniformly level to the ground surface. The
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02407
SHAFT SECANT PILES
PAGE 10 OF 12
elapsed time from the beginning of concrete placement in the pile hole to the completion
of the placement is not to exceed two hours. Adjust admixtures in the concrete mix as
accepted by the Contract Administrator for the conditions encountered on the job so that
concrete remains in a workable plastic state throughout the two hour placement. Before
concrete placement, submit test results of both a trial mix and a slump loss test using
approved method to demonstrate the concrete meeting this two hour requirement.
Conduct the test using concrete and ambient temperatures appropriate for site conditions.
.7
3.5
Place reinforcing steel in accordance with the requirements as stated in Section 03200,
Concrete Reinforcement, and the following requirements specified in this Section:
.1
.2
If the bottom of the drilled pile hole elevation is lower than the design elevation,
extend all the longitudinal bars required in the upper portion of the hole to the
additional length. Continue spirals and stiffener bars for the extra depth. These
bars may be lap-spliced, or mechanically-spliced.
.3
Install temporary casing as necessary to maintain the hole open until concrete is placed.
Hole excavations shall have flat bottoms. Temporary casing shall be removed while the
concrete remains workable. At least 30 linear metres of ready to use temporary casing
shall be furnished at the project site.
.2
Conform to requirements of Article 3.3 of this Section for hole drilling and preparation,
placing of steel reinforcement and placing of concrete.
3.6
.2
Use inspection devices in the presence of the Contract Administrator before tremie
concreting, to demonstrate that the pile hole has been excavated to the specified
diameter, depth and verticality, the cleanliness of hole bottom; and to ensure that
overlapping of piles is maintained.
.3
After each pile is bored to required depth, verify exact X, Y, Z location of pile. Verify
using a Drilling Monitor, model DM-602, manufactured by Koden Electronics Company,
or equivalent. Correct piles exceeding the permissible tolerances by backfilling with lean
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02407
SHAFT SECANT PILES
PAGE 11 OF 12
concrete or cement stabilized sand, and re-excavate them to the required tolerance before
placement of reinforcement and final concreting proceeds.
.4
3.7
Bentonite Slurry in Pile Hole prior to Placing Concrete: Immediately prior to placing
concrete in any shaft wall pile borehole, take a sample of the slurry 300 mm from the
bottom of the hole, and test if for density and sand content. Modify or replace the slurry
in the hole if the density of the sample is found to exceed limit specified. Do not place
any concrete in the pile hole until the density of the slurry in the pile borehole is correct
and the sand content has been found to be five per cent or lower. Perform additional
tests, such as measurement of fluid loss, if requested by the Contract Administrator.
SHAFT EXCAVATION
.1
.2
Provide access, at all times to the Contract Administrator, for monitoring of secant pile
wall deformations during excavation using inclinometers in secant pile wall, if casings
are installed.
.3
If during excavation, readings on any geotechnical instrumentation within the shaft site
indicate that deformation have exceeded the values specified, immediately take remedial
steps to arrest movement in accordance with the requirements of Section 02480,
Geotechnical and Structural Instrumentation and Monitoring, this Section or as directed
by the Contract Administrator.
3.8
For those piles determined to be defective, the drilled hole shall be filled with Controlled
Density Fill in order to permit the secant pile to be redrilled.
.2
For those piles determined to be defective, submit a remedial action plan for review.
.3
Remedial work shall not begin until the information has been reviewed and the remedial
action plan accepted.
3.9
FINISHING
.1
.2
.3
Repair of Leaks:
.1
Ensure the walls are free of all seeping water and meet leakage criteria before
acceptance of secant piled wall construction, subject to tolerances as specified.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.10
SECTION 02407
SHAFT SECANT PILES
PAGE 12 OF 12
.2
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
1.1
1.2
1.3
SECTION 02410
DRILLED SHAFT
PAGE 1 OF 8
General
SCOPE OF WORK
.1
This work specify in this Section consist of the design of excavation and support of
drilled shafts in soil overburden and in rock as shown in the Contract Drawings for
access and vent shaft at Shaft 8. The work includes drilling a vertical shaft, handling the
spoils, installing and back grouting a casing in the drilled hole down to around 2 m above
top of de-aeration chamber, and supplying and operating all equipment, materials and
labour necessary to complete this part of the Work
.2
Assume responsibility for the safety of the work, the protection of personnel, and
damage to property
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
REFERENCES
.1
.2
.3
.4
.5
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.4
1.5
.7
.8
.2
.9
.10
DESIGN CRITERIA
.1
The diameters of the casing for the drilled shafts shall be designed by the Contractor
based on anticipated ground conditions described in the Geotechnical Baseline Report
(GBR), any surcharge loads due to materials and/or equipment, varying subsurface
conditions, vertical tolerance and layout of the finished structures at the surface. The
temporary steel casing is depicted in the Contract Drawings as concept only.
.2
Drill, install, and grout in place the casing for each shaft to 2 m above top of connection
chamber connecting the tunnel in advance of the tunnel excavation reaching the
designated intersection point.
.3
The design shall include complete calculations and shall be signed by a Professional
Engineer registered in Province of Ontario.
TOLERANCES
.1
1.6
.1
SECTION 02410
DRILLED SHAFT
PAGE 2 OF 8
Tolerances:
.1
.2
.3
Finished centerline shall not be greater than 20 mm offset from finished tunnel
centerline
.4
Minimum backfill thickness at any location shall be 200 mm, except where
otherwise indicated or specified.
SUBMITTALS
.1
Comply with Section 01330, Submittal Procedures. The Contractor shall submit a list of
at least three drilled shaft projects successfully completed of similar size, as the ones
being drilled for this project, in the past seven years. The contractor shall submit
descriptions of the drilled shaft construction projects to serve as evidence of capability to
construct drilled shafts and submit qualifications of key staff responsible for the shaft
installation.
.2
Integrate submittals specified herein with other submittals related to shafts, Section
02150, Excavation Support System, Section 02400, Shaft Construction, Section 02437,
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02410
DRILLED SHAFT
PAGE 3 OF 8
.4
Product Data:
.1
.2
Submit Material Safety Data Sheets for materials used in the work.
Shop Drawings:
.1
.5
Fully dimensioned fabrication drawings for the steel casing and welds. Include
calculations or certifications by the manufacturer for such items as allowable
loads and stresses.
Submit working drawings and Methods Statements including but not limited to:
.1
Fully dimensioned site development plan for shaft sites and work areas indicate
proposed layout, grading, and limits of sites identifying location and limits of
lay-down and storage areas, temporary structures and facilities, water and slurry
handling and treatment facilities, shaft services, shaft equipment and plant, and
fences and gates.
.2
Method of drilling a shaft from the ground surface and details of the temporary
shaft casing.
.3
Modifications of the initial tunnel supports to connect the drilled shaft with the
tunnel.
.4
Means and methods for ensuring vertical alignment and performing survey
control to demonstrate achieving specified alignment requirements for shaft
construction.
.5
.6
Slurry mix composition, and methods of monitoring and testing to comply with
requirements.
.6
Submit dimensional record drawings showing actual installed location of each drilled
shaft, size and offset dimension. Submit actual top of drilled shaft elevation.
.7
Mix Designs:
.1
.8
Mix design data, including all mix components and test results to meet
minimum requirements set forth in the design.
.2
Submit shop drawings of the excavation shoring and bracing systems for record purposes
at least 40 working days before commencement of shoring work.
.1
Shop drawings are to bear the seal and signature of a PEO licensed professional
engineer.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
1.7
SECTION 02410
DRILLED SHAFT
PAGE 4 OF 8
Excavation shoring and bracing system drawings will not be reviewed by the
Engineer for structural adequacy. Full responsibility for the design, installation,
and maintenance of the excavation shoring and bracing systems rests with the
Contractor.
QUALITY CONTROL
.1
.2
.3
.4
Plan: Identify how the quality of materials and installation will be controlled (e.g.
measurements, inspections, testing, etc.).
.1
Methods for minimizing ground loss and stabilizing the shaft walls.
.2
.3
.4
Sequence and method of monitoring the shaft excavation and support installed.
.2
Field Testing:
.1
.2
.3
Test Equipment and Methods: Provide test equipment and methods that conform
to the requirements of API RP 13B-1. Alternative equipment may be employed
subject to the City Representative's prior approval.
.4
Monitor placement and chart actual volume of backfill concrete placed versus
theoretical volume required.
Recordkeeping:
.1
Keep records of shaft drilling and prepare a Shift Report for each shift,
regardless of type of construction activities applied, and submit to the Engineer
no later than the beginning of the following working day. Include:
.1
Shaft bottom elevation at start of shift and end of shift. Crew size,
employee classification and employee work assignment.
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.8
1.9
.5
.6
.1
.2
.3
Size drilled shaft excavations to have the clear dimensions on the approved Working
Drawings, and to satisfy all minimum dimensional requirements for installation of the
final lining.
.4
The Contractor shall design and implement shape, size, and initial support of the
shaft/tunnel intersections to suit Contractor's needs for underground construction.
.5
Part 2
2.2
.4
JOB CONDITIONS
.1
2.1
SECTION 02410
DRILLED SHAFT
PAGE 5 OF 8
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01180, Price and
Payment Procedures for all work required to drill shafts installing steel casing as
specified herein and no separate payment shall be made.
Products
MATERIALS
.1
Corrugated Steel Casing: If used, provide corrugated steel casing in accordance with
CSA G401.
.2
.3
Structural Steel: Unless otherwise noted herein or on the Contract or approved Working
Drawings, all structural steel for use for rock support shall be minimum Grade 60 and
manufactured in accordance with CSA G40.
.4
Slurry: The Contractor is entirely responsible for developing any slurry used in drilled
shaft construction, including ingredients, mix design, mixing equipment, and handling,
treatment plant and disposal.
EQUIPMENT
.1
General:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.1
.2
Part 3
3.1
SECTION 02410
DRILLED SHAFT
PAGE 6 OF 8
.2
At the progress rates necessary to complete the work within the project
schedule.
.2
.3
The equipment shall be capable of removing all material of whatever nature from
the excavation, without exceeding the specified tolerances.
.2
Slurry Mixing: Use equipment that produces a stable suspension of bentonite and
water along with necessary mechanical agitation.
.3
Slurry Reclaiming: Use equipment that separates the bentonite from the
excavated material of soil particles before recirculation.
.4
Provide equipment for surveying the dimensions and alignment of each drilled
shaft.
Execution
GENERAL
.1
.2
.3
.4
.5
Monitor for gas occurrence on an ongoing basis, provide ventilation required to provide
safe working conditions at all times, install and maintain electrical equipment in
permissible condition, and conduct all work in a manner as to prevent any safety hazards
condition due to sudden occurrence of flammable and toxic gases.
.6
Grade shaft areas to divert rainfall/runoff away from the drilled shaft excavation.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.2
3.3
SECTION 02410
DRILLED SHAFT
PAGE 7 OF 8
.7
Install a concrete collar with a top surface at least 250 mm above ground to act as a curb
and to prevent water inflow from the ground into the open drilled shaft.
.8
Excavate the drilled shafts within indicated vertical tolerances and to the lines and grades
shown on the Contract Drawings. Ensure that the excavated dimensions of the shafts will
provide adequate clearances to allow construction of the final lining, where required.
.9
.10
Operations shall be conducted to minimize the impact of noise and dust in the vicinity of
the work. All surface equipment shall be equipped with noise suppressors, silencers, or
mufflers to accomplish this, storage bins, skips and muck buckets shall be lined with
materials that deaden noise. Dust shall be controlled by use of sprinklers, tank trucks and
temporary vegetative cover, as applicable.
Drill the shafts from the ground surface at the locations shown on the Contract
Drawings.
.2
Auger the shaft and maintain hole stability using a slurry where required and to limit the
groundwater inflow into the shaft.
.3
Place a corrugated steel or other approved temporary casing in the drilled shaft and
backfill the casing in place. Tremie the invert with low strength concrete if needed to
backfill casing.
.4
Pump out the slurry (if used) from inside the casing.
.5
The Contractor may use the drilled shaft for secondary purposes during tunnel
construction.
Products: Submit verification that the installed products are authentic (delivery receipts,
bill of lading, etc.).
.2
Execution: Submit verification that the work was installed correctly (inspection records,
as-built drawings, etc.).
.3
.1
Survey the drilled shaft to ensure verticality and location as shown on the
Drawings.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
SECTION 02410
DRILLED SHAFT
PAGE 8 OF 8
The Contractor shall provide access to the Engineer for additional inspection and
testing.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SUMMARY
.1
1.2
SECTION 02412
SHAFT BACKFILL
PAGE 1 OF 6
This Section specifies work to be completed to backfill the temporary shafts following
completion of the work in the tunnel performed from this location.
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
1.3
DESIGN CRITERIA
.1
1.4
The structural backfill material placed to fill and close the shaft shall be compacted to 95
percent relative compaction per ASTM D 1557 in layers not to exceed 200 mm in
thickness. Appropriate small compaction equipment shall be used along the shaft wall, as
required, to achieve this quality of compaction. Alternative backfill materials such as
unshrinkable fill (u-fill) or controlled low strength material (CLSM), soil cement
backfill, or cellular concrete may also be proposed by the Contractor and submitted for
review and approval by the Contract Administrator.
SUBMITTALS
.1
.2
Product Data:
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.5
SECTION 02412
SHAFT BACKFILL
PAGE 2 OF 6
.1
A complete set of lift drawings showing concrete and reinforcement for the
tunnel level encasement concrete shall be submitted and reviewed with
associated Methods Statements describing the construction work involved. The
drawings shall show forms, construction joints, keys and reinforcing splicing
proposed for the placement(s), and shall indicate sequence and schedule of
construction, and preparation of each construction joint.
.2
QUALITY CONTROL
.1
Plan: Identify how the quality of materials and installation will be controlled (e.g.
measurements, inspections, testing, etc.) in accordance with Section 01450, Quality
Control.
.1
.2
.2
Other Qualifications:
.1
Construction Superintendent
.2
Concrete tester
.3
.3
Concrete testing shall be performed by the Contractor per Section 03300, Cast-in-Place
Concrete (Shafts and Underground Structures).
.4
.5
Recordkeeping:
.6
.1
Copies of all compaction test reports and laboratory worksheets not later than the
next working day.
.2
Acceptance Criteria:
.1
Compaction:
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.7
1.6
SECTION 02412
SHAFT BACKFILL
PAGE 3 OF 6
Preconstruction Meeting:
.1
Hold a preconstruction meeting at least 5 days, but not more than 30 days, prior
to beginning fills which require compaction testing.
.2
.2
.3
Safety procedures
.4
.5
Reporting requirements
.6
QUALITY ASSURANCE
.1
Reference Standards:
.1
.2
1.7
.2
.3
.4
.5
ASTM Dl556M, Test Method for Density and Unit Weight of Soil In
Place by the Sand-Cone Method.
.2
.3
ASTM D2419, Sand Equivalent Value for Soils and Fine Aggregate.
.4
JOB CONDITIONS
.1
Verify all dimensions in the field and check all field conditions continuously
during construction.
.2
.3
Use equipment adequate in size, capacity, and numbers to accomplish the work
of this section in a timely manner.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
1.8
SECTION 02412
SHAFT BACKFILL
PAGE 4 OF 6
Acceptability of compacted fill will be based upon inspection and testing. The
Owner will advise Contractor immediately of any unsatisfactory conditions and
shall have the authority to measures are taken to comply with the Specifications,
or to direct the removal of unsuitable materials and their replacement with
suitable backfill. It shall be the Contractor's sole responsibility to achieve the
specified degree of compaction.
1.9
Allow the concrete structure to cure and reach 100% of the compressive strength as
shown on the drawings or approved by the Contract Administrator prior to beginning the
earth backfill operations on top of the structure.
PRODUCT DELIVERY, STORAGE, AND HANDLING
.1
1.10
During excavation of the shaft, spoil material for backfill of the shaft may be stockpiled
in the vicinity of the shaft as indicated on approved Working Drawings.
MEASUREMENT AND PAYMENT
.1
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to providing and installing backfill as
specified herein or as necessary to fill behind the final concrete structure and the
excavation support system and no separate payment shall be made.
Part 2
General
2.1
MATERIALS
.1
.2
Unshrinkable backfill: Per OPSS 1359, Material Specification for Unshrinkable Backfill
.3
Soil imported to the Site must be tested and confirmed suitable for use at the site
prior to transport in accordance with the MOECCs Soil BMP. Imported soil
must meet the Table 1 MOECC standards and be tested at a frequency no greater
than one sample per 200 m3 unless otherwise determined by the Contractors QP.
The Contractor must provide to the Contract Administrator the name of the
supplier and source of the imported soil, and including the analytical data a
minimum of 2 weeks prior to importing fill to the Site so that there is
preapproval by the Contract Administrator before importation begins. The
Contractors QP will develop a Fill Management Plan in accordance with the
MOECCs Soil BMP and follow the procedures therein for receipt, management
and documentation of the imported soil.
.2
Granular material from a commercial sand and gravel pit or quarry licensed by
the Ministry of Natural Resources pursuant to the Aggregate Resources Act,
R.S.O. 1990, c. A .8 can be imported to the site provided that the quarry license
number is documented and provided to the Contract Administrator within two
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02412
SHAFT BACKFILL
PAGE 5 OF 6
Part 3
Execution
3.1
.2
.3
3.2
Structural Backfill:
.1
Place structural backfill material to the lines and grades shown or specified, and
per Section 02315, Excavating, Trenching and Backfilling.
.2
Do not exceed loose lifts of 200 mm, or 100 mm if hand compaction equipment
is used.
.3
Compact each lift to 95% of maximum dry density compaction (OPSS 501),
unless otherwise shown in the Contract Drawings.
.4
.5
.6
Demolish the top of the secant piles or other structural shaft supports to a
minimum of 2.0 m below final grade of the site.
.7
.8
Moisture Control:
.1
.2
Maintain moisture content uniform throughout the lift. Add water to the material
at the site of excavation or material stockpile. Supplement by sprinkling the
backfill material.
.3
At the time of compaction, the water content of the material shall be between 1
and 3 percent above optimum water content. Aerate material containing
excessive moisture by scarifying, disking, or harrowing to hasten the drying
process.
If compaction fails to meet the specified requirements, remove and replace the backfill at
proper density or bring the density up to specified level by other means acceptable to the
Contract Administrator. If the compaction methods used fails to achieve the required
degree of compaction, revise the compaction method to achieve the required compaction.
MAINTENANCE AND REPAIR/RESTORATION
.1
Groundwater Control: The Contractor shall control the groundwater in accordance with
the requirements of Section 02140, Groundwater Control throughout the duration of
construction work at the shaft, including the time required to backfill the shaft; sump
pumping of water may be required.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02412
SHAFT BACKFILL
PAGE 6 OF 6
.2
On completion of backfilling of the shaft, all shaft initial support including secant walls,
shaft collar, fencing, and any other temporary feature installed to facilitate construction
at the site, shall be demolished and removed to a depth of 2.0 m below the surface of
final grading.
.3
3.3
It is the Contractor's sole responsibility to perform compliance testing for the compaction
requirements as described below and following the requirements of Section 01450,
Quality Control. If there are any discrepancies between this Section and Section 01450,
Quality Control, this Section shall govern with respect to Shaft Backfill. The Owner may
perform additional testing. Such testing does not relieve the Contractor from the duties
of complete quality control testing and record keeping of test results for all backfilling
operations.
.2
.3
.4
.5
.2
Location for compaction tests shall be designated by the Owner prior to testing.
.3
The minimum depth for the sand cone test hole shall be 300 mm. The minimum
size shall be 200 mm and a size 16/30 or 10/20 silica sand shall be used.
Perform two compaction tests meeting the compaction requirements for every
three lifts of loose fill.
.6
Compaction shall be deemed to comply with the specifications when no compaction test
falls below the specified relative compaction.
.7
If compaction fails to meet the specified requirements, the affected lifts shall be
reworked and re-compacted. Confirmation tests for remedial work shall be double the
number of tests specified for initial compaction density tests.
.8
Additional compaction tests may be taken by the Owner as described above to verify
compliance with these requirements. These tests shall not relieve the Contractor from its
testing requirements. Accommodate the Owner in conducting these tests and provide free
access as required by the Owner.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE OF WORK
.1
1.2
SECTION 02415
STEEL SHEET PILING
PAGE 1 OF 4
The Work for this Section includes design, furnishing and installation of steel sheet piles
as excavation support for shaft 4 should the Contractor elect to not install secant piles
due to space limitations.
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
.15
1.3
REFERENCES
.1
1.4
All open cut work shall be performed in accordance with all applicable provincial and
local regulations, codes, and standards.
DESIGN CRITERIA
.1
.2
Additional design criteria specific to sheet piles for shaft ground support:
.1
Interlocks shall be fully engaged to prevent soil migration into the excavation
and to limit or prevent groundwater infiltration.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
1.5
SECTION 02415
STEEL SHEET PILING
PAGE 2 OF 4
PERFORMANCE REQUIREMENTS
.1
1.6
.1
.2
.3
Submit information from the manufacturer that indicates the sheet piling meets or
exceeds the material requirements for the anticipated ground conditions described in the
GBR.
.4
Submit verification from the manufacturer that the hammer can deliver the required
energy to install the sheet piles efficiently.
.5
.6
Provide design calculations and drawings for steel sheet piles and groundwater cut-off
that are prepared, stamped, and signed by a registered Professional Engineer licensed in
the Province of Ontario.
1.7
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to construct excavation support with
steel sheet piles as shown on the Contract Drawings and specified herein and no separate
payment shall be made.
Part 2
Products
2.1
GENERAL
.1
The Contractors excavation support system design engineer shall specify the excavation
support system material requirements in accordance with the submitted designs. The
materials, however, shall meet the minimum requirements listed below.
.2
2.2
MATERIALS
.1
Materials used in construction of the workshaft excavation support systems shall meet
these requirements:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02415
STEEL SHEET PILING
PAGE 3 OF 4
.1
.2
.3
Steel sheet piles and interlocks shall not have kinks, camber or twists that would
prevent the pile from reasonably free sliding to grade.
Part 3
Execution
3.1
GENERAL
.1
.2
3.2
All welding or gas cutting shall be in accordance with the current standards of the
American Welding Society.
.2
Driving of sheet piles will be allowed provided that the noise is within the permitted
range or if a noise exemption is received from the City.
.3
Sheet piles shall be installed in plumb position with each sheet pile interlocked with
adjoining piles for its entire length so as to form a continuous diaphragm throughout the
length of each run of wall, bearing tightly against original ground. Sheet piles shall be
installed to top of rock. Care shall be exercised in driving so that interlocking members
can be extracted without damaging adjacent structures or utilities. The methods of
driving, cutting, and splicing shall conform to the shop drawings prepared by the
Contractors design engineer.
.4
Sheet pile corners shall be installed with interlocks and bulbs properly engaged for full
depth of sheet piles. If interlocks and bulbs cannot be properly engaged for full depth,
Contractor shall take measures that may include continuous welding of corner
connections, to seal all cracks to avoid inflows of soils and minimize or prevent
groundwater infiltration.
.5
Internal supports, including walers, struts, and corner braces, shall be installed
sequentially as the shaft is excavated. At no time shall the unsupported excavation depth
exceed the design spacing plus 0.6 metre of horizontal support members as shown on
approved submittals. All internal supports shall be installed within plus or minus 75mm
of design locations shown on approved submittals.
.6
.7
A driving head shall be used and any piling which is damaged in driving or which has
broken interlocks between sections shall be pulled and replaced at Contractors expense.
3.3
BACKFILL
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.4
END OF SECTION
SECTION 02415
STEEL SHEET PILING
PAGE 4 OF 4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE OF WORK
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 1 OF 30
.1
The Work specified in this Section includes one-pass rock tunneling of the EWT and
NST by tunnel boring machine (TBM) capable to create and work in full pressurized
mode (pressurized face) that balance the groundwater pressure. The TBM can be an earth
pressure balance tunnel boring machine (EPBM) or slurry tunnel boring machine
(STBM) in accordance with the Contract Documents. The Contractor is responsible for
providing the design of the Work and the selection and complete design of the tunnel
boring machine and the tunnel construction systems.
.2
.2
.3
.4
.3
Drill and blast for excavation of the EWT and NST is not allowed.
.4
.5
Rock tunneling of the main tunnels shall include fabrication, transportation, testing,
installation and launch of the TBM; installation and use of all other tunnel excavation
equipment; the excavation, handling, removal, and disposal of all materials encountered
in the tunnel excavation; installation of the precast concrete tunnel lining (PCTL) for a
finished internal diameter of 3000 mm; installation of initial tunnel support different than
the PCTL as specified in Section 02437, Rock Reinforcement and Excavation when
required; groundwater control; temporary drainage, tunnel ventilation, lighting, and
wiring; tunnel safety; tunnel final lining; and all incidental work necessary to complete
the work in accordance with the Contract Documents.
.6
The main tunnel shall be excavated by either new or reconditioned tunnel boring
machines capable of working in a pressurized mode. All other tunnels related to the
EWT and NST, including starter tunnels, tail tunnels, junctions and connecting tunnels
are assumed to be excavated using hand mining or other mechanized means such as
hydraulic hammer or roadheader.
.7
The excavated size of the tunnels shall be determined by the Contractor based on
construction requirements for installing the final lining, subject to the limitations on
crown height and/or diameter shown on the Contract Drawings. Excavate the tunnel to
the selected size; to the shape, line, and grade shown on the Contract Drawings; and to
within the tolerances specified herein.
.8
Select and utilize methods and equipment compatible with the selected dimensions of the
tunnel and with the anticipated geologic conditions described in the Geotechnical
Baseline Report (GBR).
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 2 OF 30
.9
Patch all bolt pockets, shear pin sockets and surface imperfections on precast segmental
lining of the tunnels.
.10
Clean all tunnels including, but not limited to, the removal of all visible dust, dirt, oils
and other foreign matter and materials from all interior tunnel surfaces.
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
1.3
REFERENCES
.1
.2
.3
.4
.5
American Petroleum Institute: API 13A Oil Well Drilling Fluid Materials.
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 3 OF 30
.7
.8
Management of Excess Soil A Guide for Best Management Practices, prepared by the
MOECC, dated January 2014.
1.4
DEFINITIONS
.1
Abrasion: Detrimental wear of TBM and plant components from excavation and muck
handling processes.
.2
Cutter Head: Rotating tool or system of tools on common support excavating at face of
bore.
.3
.4
Earth Pressure Balance (EPB) TBM: A TBM with a pressure bulkhead located behind
the tunnel face that forms an excavation or mixing chamber under pressure. The sealed
system balances hydrostatic and earth pressures against the inflow of ground and water
during excavation. Conditioners are injected into the excavation chamber to be mixed
with material which is excavated by a rotary cutterhead. The spoil mix is extracted by
means of a sealed screw conveyor in an operation integrated with the TBM advance to
ensure continuous support of the tunnel face. EPBM that utilizes pressure relieving gates
are not acceptable.
.5
Excavated Profile: Shown on the Contract Drawings that defines the tunnel crosssection.
.6
Full Pressurized Mode: The tunnel face is continuously supported in closed mode at a
pressure no less than the groundwater pressure at the invert level plus the effective,
active ground pressure acting on the tunnel face.
.7
Muck: Excavated material consisting of a mixture of soil and/or rock cuttings and water,
removed from the tunnel. Muck may also include conditioner, bentonite, and polymer,
fragments of wood, cobbles, and boulders.
.8
Open Mode: The pressure in the TBM excavation chamber is equal to the atmosphere air
pressure in the lined tunnel. The excavation chamber may be full or partially full with
spoil.
.9
Overbreak: Excavation that occurs beyond the excavation limits shown on the Contract
Drawings.
.10
Precast Concrete Tunnel Lining (PCTL): Precast concrete segments that are bolted or
dowelled together inside the TBM tail shield to form contiguous gasketed, watertight
tunnel lining rings.
.11
Probe Hole: An exploratory hole drilled ahead of the excavation face to investigate
ground and/or groundwater and gas infiltration conditions.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 4 OF 30
.12
Pressurized Face Mode: Operation of the TBM with a filled pressure chamber with
active face support pressures that balances the pore pressure within the rock mass at all
times to minimize impact on sensitive clays.
.13
Rock Tunnel: A tunnel driven in dense, consolidated natural material, delineated on the
boring logs as Billings, Lindsay or Verulam Formations or other rock types as described
in the GBR.
.14
Rock Tunnel Excavation: Performing all operations for excavating and supporting the
excavated tunnel in rock, conforming to the geometry, criteria, and line and grade
indicated on the Contract Drawings.
.15
Slurry TBM (STBM): A TBM with a pressure bulkhead located behind the face to form
an excavation chamber under pressure. Bentonite slurry and/or other liquid medium is
introduced into the excavation chamber under controlled pressure that balances
hydrostatic and earth pressures that stabilize the face and to be mixed with material
excavated by the rotary cutterhead. The resultant slurry, with cuttings, is removed by
pumping in an operation integrated with TBM advance. The spoil mix is extracted by
means of a pumping system. The spoil is processed in a separation plant that removes the
Bentonite or other conditioning material for reuse.
.16
Starter and Tail Tunnels: Short sections of tunnel, excavated at the base of the
construction shafts for Contractor's convenience for the purpose of installing the TBM
and its trailing gear during start-up, storage, etc.
.17
Tunnel Boring Machine (TBM): In this project, a fully shielded (360-degree shield) with
a rotary wheel cutter head and cutters for excavation, ground control, steering, precast
concrete lining erector for ring assembly and advances using propulsion cylinders that
thrust against the precast concrete tunnel lining within the tail shield and is capable of
creating and maintaining a pressurized face during mining to balance earth and/or
groundwater pressure when required, including trailing gear and support equipment
required for performing tunnel excavation.
.18
Tunnel Construction Water: All water, whatever the source, pumped from shaft and
tunnel excavations.
.19
Tunnel Launch: Exit of the TBM from a portal or launching shaft through an "eye" that
is cut or formed within the wall of the portal or the launching shaft or excavation support
system.
.20
Tunnel Reception: Entry of the TBM into a portal through an "eye" that is cut or formed
within the wall of the portal or the receiving shaft or excavation support system.
1.5
SUBMITTALS
.1
The Contractor shall submit to the Contract Administrator for review, plans, details and
data including compliance with the requirements of the Contract Drawings. Such review
shall not be construed to relieve the Contractor in any way of responsibilities under the
Contract. Contractor shall not commence work on any items requiring a tunneling work
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 5 OF 30
plan or other submittals until the submittals have been reviewed and accepted by the
Contract Administrator.
.2
Tunnel Work Plan: Submit a detailed work plan of all proposed tunnel
construction operations and initial support provisions for all tunnel intersections
and any enlargements or additional excavations required for the Contractors
own convenience. Include details of proposed methods and procedures for
excavating the tunnel; hauling and disposal of tunnel muck; initial support
methods and installation procedures; face support; ventilation; illumination;
procedures for handling, control, treatment, and disposal of water; types of
equipment to be used; equipment specifications; and other pertinent data
requested by the Contract Administrator.
.2
Initial face pressure calculations shall be provided at least 60 days before tunnel
launch in a clear and understandable format with all assumptions and input
parameters documented.
.3
TBM face pressure tables shall be submitted for all ground, a minimum distance
of 300 m ahead of any active TBM face on a rolling, weekly basis. Calculations
shall be made every 10 m, or less. This shall include the sections whether no or
nominal face pressures are planned. Submit the tables to the Contract
Administrator for review.
.4
.5
.6
.7
.1
.2
.3
.4
.5
.6
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
.8
.9
.10
.11
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 6 OF 30
Shop Drawings: Submit detailed Shop Drawings and pertinent descriptions, data
and calculations for all items to be incorporated into the finished work. The Shop
Drawings and calculations shall show compliance to specified requirements and
applicable codes and shall bear the seal, signature and date of a professional
engineer registered in Province of Ontario. As a minimum, include the
following:
.1
.2
.2
.2
Submit materials and procedure to line the tail tunnel at Site 10 should
Contractors construction schedule expect the tail tunnel to be in
operation for more than 150 days. Total groundwater inflow into shaft
10 including tail tunnel shall not exceed 300 L/day.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.12
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 7 OF 30
Product Data. Submit Product Data for the Tunnel Boring Machine (TBM)
information including the TBM manufacturer, model number, and the following
information. Additional information to be provided in submittal shall include:
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
The year originally fabricated and released for operation and the
name of current Owner, with location, phone number, and
contact person.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.13
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 8 OF 30
Details of the ventilation system including type, size and location of all
fans, supply and exhaust ducts, scrubbers, noise attenuation devices and
other ventilation system components.
.2
.3
.4
.5
.6
.7
.8
.1
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.9
.10
.11
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 9 OF 30
.1
.2
.3
.4
.2
.3
.4
.5
.6
.2
.3
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.12
.13
.3
.3
.4
Testing procedures.
.5
Accelerator dosing.
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 10 OF 30
.2
.3
.4
.5
Machine entrapment.
.2
.3
.4
.5
.6
.7
.8
.14
.15
.16
Reports and Records: During tunneling, submit daily survey notes for line and grade
checks indicating any deviation from line and grade indicated by the laser control
system. Provide immediate notification to the resident Contract Administrator if position
monitoring or surveying indicates that line or grade limits have been exceeded. Also
provide immediate notification to the resident Contract Administrator if monitoring in
the tunnel or geotechnical instrumentation indicates any unexpected behaviour. Submit
tunnel shift reports with required tunneling data indicating for each lining segment
advance. Submit these reports to the Contract Administrator not later than the end of the
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 11 OF 30
next working day following the shift worked. The tunneling data submittals shall include
but not be limited to:
.1
.2
General Shift Report: Prepare a shift report of tunnel construction work for each
shift worked, and provide the Contract Administrator with one copy of the shift
report on the following work day. The following information shall be included in
these reports:
.1
Time and location of tunnel face(s) by station at start and end of each
work shift.
.2
.3
.4
.5
.6
TBM roll and cutterhead attitude for each TBM thrust cycle.
.7
.8
.9
.10
.11
TBM Shift Report: Prepare a TBM shift report for each shift in which the TBM
was operating, which shall further contain the following information:
.1
.2
.3
Number and location of TBM cutters changed and specific reasons for
the change. Each TBM cutter is to be uniquely identified to accurately
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 12 OF 30
.4
.5
.6
.5
.6
Bolt pocket and shear pin sockets patching work plan: Submit a detailed work plan for
patching all bolt pocket and shear pins 30 working days prior to commencing Work,
including, as a minimum, the following information:
.1
.2
Underground Cleaning Work Plan: Submit a detailed work plan for all tunnel cleaning
operations 30 working days prior to commencing Work, including, as a minimum, the
following information:
.1
.2
Disposal of solid and liquid waste materials generated during the tunnel
cleaning.
.3
.4
1.6
.4
Cleaning and Patching Shift Report. Prepare a report for each shift worked at
each heading, and provide the Contract Administrator with one copy of the
report on the following Day. Include in this report the start and end time,
location of the Work places and progress by station.
EXISTING CONDITIONS
.1
The Contractor shall be responsible for the protection of all utilities encountered during
the Work. The known utilities are shown on the Contract Drawings and the Contractor
shall take every precaution when working near the utilities to locate and protect these
utilities. All damage to, or resulting from, damage to the existing utilities shall be the
sole responsibility of the Contractor and the Contractor shall replace, repair, remedy, or
compensate for all damages at no additional cost to the Owner.
.2
The Contractor shall be responsible for the protection of all structures, roads and
railroads above or adjacent to the tunnel, within the framework and criteria set forth in
the Contract Documents.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.7
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 13 OF 30
SAFETY
.1
1.8
Conform to Section 01705, Contract Work Health and Safety Clauses, Section 02444,
Tunnel and Shaft Ventilation and Utilities and Section 01710, Tunnel and Shaft Safety.
QUALITY ASSURANCE
.1
.2
Qualifications:
.1
The actual work shall at all times be performed under the direct supervision of
an approved, experienced Project Superintendent with at least 10 years recent
on-the-job supervision experience on similar projects involving tunnels of
similar size constructed by similar methods and in similar ground conditions.
.2
.3
Each EPBM or STBM operator shall have constructed at least 1 tunnel greater
than 2,000 m in length of similar size and lining configuration with similar
equipment.
.4
All EPBM or STBM operators and tunneling superintendents shall read the
Geotechnical Baseline Report (GBR) and familiarize themselves with the
geotechnical conditions to develop their means and methods to suit the baseline
conditions.
.5
.6
.7
.8
Each surveyor responsible for tunnel surveying shall have had previous
experience with the TBM laser guidance system or have attended instructional
courses by the supplier of the system. Proof of training (i.e. certification from
manufacturer) shall be provided.
.9
Before machine start-up, the manufacturer shall train the EPBM or STBM
operators, mechanics, and the Contractors master mechanic(s). The machine
manufacturer shall certify in writing that the operators and master mechanic(s)
have completed this training on similar equipment and at manufacturers plant
for this projects equipment and are qualified and prepared for machine
operation.
The Contractor shall establish and maintain quality control for operations under this
section to assure compliance with the contract requirements and maintain records of
quality control for materials, equipment, and construction operations.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 14 OF 30
.3
The Contractor shall keep and maintain at the construction site a complete set of field
drawings for recording as-built conditions. It shall have marked or noted thereon all field
information, properly dated, recording as-built conditions. This set of field drawings
shall be kept up-to-date during the course of the project.
.4
.5
Surveying Related
.6
1.9
.1
.2
The Contract Administrator reserves the option to check any or all survey layout
data and measurements. Whether the Contract Administrator exercises this
option or not, the Contractors responsibility for accuracy will not be waived.
.3
Survey by the Contract Administrator: For the purposes of tunnel survey by the
Contract Administrator, provide stable survey instrument support brackets, level
benchmarks and access platforms, at 60 m spacing or 20 m in alignment curves.
Provide free access to the Contract Administrator as required.
The Contractor shall allow access to the Contract Administrator and shall furnish
necessary assistance and cooperation to aid the Contract Administrator in observations,
measurements, data, and sample collection, including, but not limited to the following:
.1
The Owner and/or Contract Administrator shall have full access to the operator
controls prior to, during, and following all tunneling operations. This shall
include, but not be limited to, providing visual access to real-time operator
control screens, gauges, and indicators.
.2
The Owner and/or Contract Administrator shall have full access to the launch
and retrieval shafts prior to, during, and following all tunneling operations. This
shall include, but not be limited to, visual inspection of installed liner system,
installed pipes, launch and retrieval seals, and verification of line and grade. The
Contractor and subcontractor shall provide safe access in accordance with all
safety regulations.
.3
The Owner and/or Contract Administrator shall have full access to the spoil
material. The Contract Administrator shall be allowed to collect rock samples
from the spoil removal system a minimum of once per installed segment of
tunnel liner, or every 3 meters, whichever is more often, and at any time when
changes in rock conditions or obstructions are apparent or suspected.
TOLERANCES
.1
The tolerances on tunnel alignment shall be such that the intrados surface shall be within
a 75 mm variation from the theoretical intrados surface in any direction. Misalignments
shall be corrected at a maximum rate of 5 mm per ring.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
1.10
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 15 OF 30
Steps in intrados between abutting segments shall not be greater than 10 mm.
MEASUREMENT AND PAYMENT
.1
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to construct the EWT and NST as
specified herein and no separate payment shall be made for completing this work.
.2
Measurement and payment for removing obstructions described in 3.3 Obstruction in this
Section is included as an allowance as described in Section 01025.
Part 2
Products
2.1
.2
General
.1
.2
.3
.2
Design and configure the cutterhead with wear protection to enable efficient
excavation of the ground indicated.
.1
.2
.3
Design the cutterhead to permit the use of disc cutters which can be
replaced from the excavation chamber (back loading).
.4
Provide wear indicators on tools located in the gauge position with status
indication at the TBM operator position.
.5
The cutterhead shall limit the size of rocks which can be admitted to the
screw conveyor on an EPB machine or the stone crusher on a slurry
TBM.
Provide and maintain one complete set of each type of (disc and scraper) of
cutting tools and associated mounts and seals available at all times.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
Adequate torque and power to the cutterhead so that the machine is not torque
limited while operating under any of the ground conditions indicated.
.2
.3
Certification from the main bearing manufacturer that the bearing is suitable for
the geotechnical conditions indicated and shall have a minimum bearing life of
two times the anticipated operational hours.
.4
Oil lubricated main bearing with pumping and filtration circuits equipped with
accessible sampling points.
.5
Main bearing shall be new and replaceable from within the tunnel
.2
.5
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 16 OF 30
Design the TBM to allow operator controlled application of active face support
at all times:
.1
.2
EPB TBM: Four earth pressure sensors within the excavation chamber:
two sensors each near the crown and tunnel spring line and replaceable
from the atmospheric side of the main bulkhead at any time.
.2
Slurry TBM: Four pressure sensors capable of measuring air and slurry
pressure at crown level.
.1
.2
.3
.4
Should the Contractor plan to operate the TBM in an open-face mode when
tunnelling through stable ground conditions with low permeability, provide
devices to quickly seal the excavation bulkhead if flowing water is encountered.
The sealing device shall be effective within 30 seconds.
Seals:
.1
The TBM design shall permit the replacement of seals from within the tunnel.
.2
.2
The two forward main bearing seals shall be replaceable from within the
working chamber without necessitating cutter head removal.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
.6
.7
.8
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 17 OF 30
.2
.2
Spring steel sealing plates designed to prevent the steering gap from
grout ingress.
.3
Two of the three wire brush seals replaceable from within the tunnel.
Provide sufficient thrust to advance the shield under the maximum anticipated
face pressure and shield friction.
.2
Provide a propulsion system that can advance the TBM under the combined
maximum loads of tool, earth and hydrostatic pressure, shield friction, and
trailing gear drag.
.3
.4
Ensure that maximum thrust contact pressure at any point and at any time on the
Initial Lining shall not exceed 50 percent of the maximum permissible jacking
load in the Initial Lining design.
.5
.6
Shield Articulation:
.1
Provide an active articulation joint fitted with hydraulic cylinders to permit the
TBM to follow the DTA.
.2
.3
Provide a passive articulation joint between the main shield and the tail shield
equipped with hydraulic cylinders.
.4
Provide extensometers at four positions on both the active and passive cylinders.
Erector system:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.9
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 18 OF 30
.1
.2
Erector system shall be compatible with the TBM and precast lining.
.1
The lifting and gripping mechanism shall be designed to handle all loads
with an adequate factor of safety in the axial, radial, and circumferential
directions, and in the three articulation angles corresponding to the six
degrees of freedom.
.2
.3
.4
The segment feeder shall supply the erector with segments at the correct
orientation and be capable of reverse operation for the removal of
damaged or incorrect segments.
Grouting System:
.1
.2
Tail void shall be grouted through lines integrated in the shield tail in accordance
with this Section.
.1
Four twinned (one primary and one spare) grout injection lines shall be
installed around the circumference of the shield and designed for
continuous grout flow that will maintain filling and pressure with the
maximum advance rate of the TBM.
.2
Each grout line utilized shall be equipped with a pressure sensor and
manual stop valve at the tail shield connection.
.3
Provide computer controlled double piston or hose pumps which shall provide
pressure and volume measurement for each of the lines continuously to the TBM
display and data logging system.
.10
Probing and Drilling Equipment: Provide drilling equipment and staging to enable
recovery of tail void grout samples and contact grouting at any position around the ring.
.11
.2
EPB TBM:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.12
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 19 OF 30
.2
Locate the screw conveyor inlet at the bottom of the excavation chamber
and equip the inlet with bulkhead doors designed to isolate the screw
conveyor from the excavation chamber. The screw conveyor shall be
fitted with wear-resistant plate and removable from the screw sleeve in
the tunnel.
.3
The screw outlet shall be fitted with a guillotine gate designed to operate
and seal maximum hydrostatic and earth pressure in all ground types
indicated.
.4
.5
.6
.7
.8
Provide accumulator with automatic valve which will close the screw
guillotine in the event of a power failure.
Slurry TBM:
.1
.2
.3
.4
Muck Control System: Provide equipment to measure the amount of excavated material
during advance for each segment ring. Muck Control System shall be designed to assist
the TBM operator by comparing the theoretical excavated material relative to propulsion
cylinder stroke to the actual excavated material at a given stroke length and display these
in real-time to the operators position
.1
EPB TBM:
.1
Include twin conveyor scales connected to the TBM PLC integrated with
propulsion cylinder stroke measuring units.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.3
.13
.14
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 20 OF 30
.2
.3
Slurry TBM:
.1
Include flow and density meters in the supply and discharge slurry lines
and TBM PLC propulsion cylinder stroke measuring units integrated
together to provide volumetric and unit weight measurements for each
segmental ring.
.2
Density meters in the return lines shall be located in the shaft and fitted
to the vertical pipes carrying the slurry up the shaft.
.3
.2
The system shall be capable of displaying the precise position and orientation of
the TBM on a continuous basis with numerical and graphical display of
horizontal and vertical deviation from the designed alignment direction with
respect to the designed alignment.
.3
.2
.3
Provide system for real-time data monitoring and acquisition, storage and display
system for:
.1
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.15
.16
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 21 OF 30
.5
Main bearing and main bearing sealing system oil pressure, temperature
and flow.
.6
.7
.8
Compressed air pressure and air flow for both working air and breathing
air.
.9
.10
GCS data including water, polymer and foam solution flows and
pressure, air flows and pressure, and injection ratios for each individual
line.
.11
.12
.13
.14
Pressures and volumes of shield tail grouting and tail seal grease.
Record data at maximum time intervals of ten seconds and display in real-time
at:
.1
.2
.3
Store and record data via an automated acquisition system in digital form for
later use and retrieval.
.4
Provide secure Internet-based access to real time data for use by the Project
Representative in the Project Representative office.
.5
Maintain hardware necessary for recording and real time viewing of data at the
project site. In the event of downtime due to hardware within the Contractors
control, notify the Project Representative of the issue, repair hardware, and
restore Internet-based access to real time data within 48 hours of hardware
failure. Maintain recording of data at all times.
Spare Parts:
.1
.2
Provide and maintain on site one spare screw conveyor assembly (screw, casing,
associated mounts and seals) that is available at all times.
.3
A spare main bearing and associated seals shall be available at the site within ten
days.
Communication Systems:
.1
Provide hard wired telephone communication system at all times,
including emergencies, from the TBM, along the tunnel alignment at
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 22 OF 30
.3
.4
.5
Electrical System:
.1
Comply with Section 01710, Tunnel and Shaft Safety.
.2
The primary power distribution system shall have means for eliminating
high-voltage fluctuations when starting up or shutting down the TBM.
.3
.4
The power interrupt that shall automatically shut down power to the
TBM and trailing equipment upon detection of an air quality event such
as explosive or toxic gas levels exceeding the regulation limits, while
maintaining power to ventilation, emergency lighting, de-watering
pumps, and safety support systems.
Lighting Systems:
.1
Provide a primary lighting system for the entire length of the tunnel.
.2
.3
.2
.3
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 23 OF 30
.3
.4
.2
.7
Ventilation System:
.1
.17
.2
.2
Provide fire suppression systems within TBM and along trailing gear for
all electro- hydraulic installations, heat sources, and the TBM
transformer.
.2
Provide a clear emergency escape way from the TBM along the trailing
gear.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
2.2
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 24 OF 30
Provide fire extinguishers at the TBM control panel, in the air locks, and
in every trailing car.
MATERIALS
.1
All materials other than bentonite used for muck conditioning and face control shall
conform to applicable regulations and be inert, biodegradable and meet soil standards in
Table 1, O. Regulation 153/04. Natural mineral bentonite or other inorganic conditioners
used in EPB tunneling shall be controlled on the Project site and not allowed to
contaminate land or water sources, and shall be disposed off-site in accordance with all
applicable regulations.
.2
Sikatop 123 Plus as supplied by Sika Canada Inc. or approved equivalent to be used to
patch the bolt pockets and shear pin sockets of precast concrete tunnel linings.
.3
Part 3
Execution
3.1
TUNNELING
.1
The Contractors selection of means and methods for excavation is integral to the
planning and execution of the work of the project as specified. The selection of means
and methods is the responsibility of the Contractor and the selected means and methods
shall be capable of coping with subsurface conditions encountered.
.2
Examination:
.3
.1
Verify existing conditions before starting work. Verify locations and sizes of
existing systems.
.2
Tunnel excavation shall not begin until the following conditions have been met:
.1
Required submittals have been made and the Contract Administrator has
reviewed submittals.
.2
.3
.4
Survey control has been established for the TBM and tunnel and has been
independently verified by Contract Administrator.
.5
.6
A start-up inspection of all mechanical and hydraulic systems associated with the
tunneling operations has been completed. The system shall be tested on the
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 25 OF 30
.4
.5
.6
Site safety representative has submitted the Health and Safety Management Plan
and Rescue Procedures Plan described in Section 01710. Hold safety meetings
and provide safety instruction for new employees as required.
Provide all installations in the portal for TBM launching, start-up and tunnel
operation, including installation of supplementary supports or bracing required
for structural support, thrust abutment, and launch cradle.
.2
Provide portal sealing structure for TBM launch which seals the gap between
portal and TBM and the gap between portal and initial support.
.3
.4
Complete the following before advancing the TBM cutterhead beyond the
ground improvement zone:
.1
Install at least one complete ring of segments and grout the tail void
between the segments and portal support wall to form a watertight seal.
.2
Fill excavation chamber with earth paste or slurry and apply required
support pressure.
Excavation:
.1
.2
As the TBM advances, continuously inject tail seal grease under pressure to
minimize risk of groundwater or backfill grout intrusion.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.7
.8
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 26 OF 30
.2
Grip and erect segments in a manner to accurately position and align segments
and gaskets within specified tolerances.
.3
.4
Clean all faces of each segment and gasket prior to fitting adjacent faces
together.
.5
.6
Maintain the ring erection area free of debris and accumulations of muck and
water prior to and during the ring building process.
.7
Annular grouting:
.1
Carried out such that complete filling and pressurization of the void is
simultaneous with TBM advance.
.2
Grout each ring of bolted lining concurrently with TBM advance. Maintain
sufficient grout to fill voids produced by advance including for wastage. Inject
the grout such that the annular space between the tunnel lining and the excavated
profile is kept completely filled as the TBM advances.
.3
The grout pressure at point of injection shall be not less than the pressure inside
the TBM pressure chamber and not more than this pressure plus 0.3 bar.
.4
Monitor grout volumes used for each ring and inform the Contract Administrator
if the volume varies by more than 10% of the theoretical volume.
.5
.6
As the TBM advances, continuously inject tail seal grease under pressure to
minimize risk of groundwater or backfill grout intrusion.
.7
Drill holes through the shear pin sockets nearest to the crown of the ring to
verify that the annular space has been completely filled. Length of hole to be
adequate to intersect voids. Punching through is not permitted. This will initially
be required on every fifth ring for the first 100 rings and continuing until such
time as confidence of annular filling is established. Thereafter, test every tenth
ring or as directed by the Contract Administrator. Revise grouting methods to
remedy insufficient filling of the annulus.
.8
.9
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.10
.9
.10
.1
Remove all accumulating water and groundwater inflow from the TBM and
tunnel using methods and equipment necessary to prevent damage to any portion
of the work.
.2
Ventilation System:
.2
Inspection Stop:
.1
Plan for locations of all inspection stops prior to commencing TBM drives.
Consider:
.1
Schedule of working hours and days of the week planned for tunnel
excavation.
.2
.2
Use any inspection method considered useful to the Contractor, but include at
least one visual method and direct measurement of cutter wear. Visual inspection
methods could include either personnel access or remote camera.
.3
Submit documentation report of all the items inspected and their condition
within 24 hours of the inspection stoppage. Include:
.4
.13
Comply with Section 02444, Tunnel and Shaft Ventilation and Utilities.
.12
Maintain contact surfaces above freezing for the minimum period called for in
CSA A23-1 or in accordance with the grout manufacturer's specifications.
Removal of Water:
.1
.11
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 27 OF 30
.1
.2
.3
TBM Maintenance:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 28 OF 30
.1
.2
Hydraulic oil, seal oil, and bearing lubricating oil and grease shall be tested at
least once per every 100 operating hours, monthly, or per manufacturer
recommendations, whichever is most frequent. Maintain records of these tests
and make available to the Project Representative upon request. Clearly indicate
the contaminate levels and overall condition including any changes since last
testing and maintenance action indicated.
.3
Optimize cutting tools for best TBM performance with consideration of:
production, cutter, and cutterhead wear.
.4
.5
.6
.14
Maintain clean working conditions at all times inside the tunnel and shafts. All muck,
slush, grout spills, ponded water, and any other material not required for tunneling shall
be removed from the excavations in a timely manner.
.15
The Contractor shall provide and maintain walking boards with non slippery surface in
the tunnel, outside of track.
.16
Prosecute tunneling Work in accordance with the approved working hours established
for the project. Notify the Contract Administrator at least 24 hours in advance of a
proposed change in working hours. When the work is interrupted for more than 24 hours,
or if required by the Contractor or the Contract Administrator based on ground
conditions, the face shall be supported in accordance with approved Shop Drawings.
.17
In case of emergency or work stoppages likely to endanger the stability of the excavation
or adjacent structures, maintain a full work force 24 hours per day, including weekends
and holidays, until emergency or hazardous conditions no longer jeopardize stability and
safety of the Work.
.18
Provide access for the Contract Administrator to inspect and observe the work at any
time without restriction, and to perform independent line and grade surveys, as deemed
necessary by the Contract Administrator.
.19
Survey the invert of the tunnel excavation at 10 m intervals to ensure the alignment is
within the tolerances specified.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 29 OF 30
.20
If unstable face conditions develop at the heading or high groundwater inflows into the
excavation chamber or through the spoil extraction are detected, immediately convert the
open-face mode into fully-pressurized EPB mode. Do not resume mining until
appropriate face stabilization measures have been satisfactorily implemented.
.21
The Contractor shall note that the TBM components as well as other excavation
equipment will be subject to abrasive ground conditions. Tunneling components subject
to high abrasive wear are, but not limited to, cutting tools, conveyors or other spoil
handling equipment, Earth Pressure Balance TBM screw conveyors, and sump pumps.
.22
Maintain station markers at all times during construction. Temporary tunnel station
markers shall be:
3.2
.1
Placed at approximate eye level near the spring line and away from utilities with
a minimum lettering of 200 mm in red colour.
.2
Located on the same side of the wall throughout the tunnel length and shall be
with respect to the centerline of the tunnel.
.3
The reuse of rock material on-site shall be in such a manner as to prevent or eliminate the
potential for material to become a contaminant in the environment, cause or have the
potential to cause an adverse effect (as defined by Ontario Environmental Protection
Act).
.2
All muck designated to be removed from the site must be promptly removed. Stockpiling
of materials at any time on site shall be avoided except as allowed due to haulage
restrictions. Temporary stockpiles to be managed in accordance with MOECC excess
soil handling best practices to eliminate or mitigate potential for release of muck to the
environment such that it causes or may cause an adverse effect as defined by the Ontario
Environmental Protection Act.
.3
All excess material resulted from tunnel excavation that is to be removed from site shall
comply with Section 01355, Disposal Excess Material.
3.3
Obstructions
.1
The Contract Drawings show schematic location of deep underground garages along the
tunnel alignment. According to information from Building Code Services, Planning and
Infrastructure, City of Ottawa, no rock anchors or any support systems from the buildings
were found to extend into the easement of the tunnels. However, the Contractor shall
confirm the presence of obstructions along the tunnel alignment prior to start tunnel
excavation and inform the Engineer immediately of any change.
.2
The contractor for the Ottawa Light Rail Transit installed rock anchors close to Site 1
that extend into the EWT. Those anchors will be removed by others, which has to be
confirmed by the Contractor prior to excavating the EWT from Site 3C to Site 1.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
3.4
SECTION 02430
TUNNEL EXCAVATION BY
TUNNEL BORING MACHINE (TBM)
PAGE 30 OF 30
An existing 300 mm sanitary sewer will be encounter between chainage 19+960 and
chainage 19+890 approximately. According to the As-Build drawings, it appears that for
the installation of the sewer a man-entry tunnel size was excavated by conventional drill
and blast method. No information is available with respect to the type of support that was
installed (if any).
Tunnel Cleaning and Patching
.1
Following completion of excavation of the TBM tunnels, dispose of all excess material
off Site in accordance with the Specifications.
.2
The entire interior of the tunnels within the Contract limits shall be thoroughly cleaned
using a high-pressure wash to remove all visible dust, dirt, and foreign material to the
satisfaction of the Contract Administrator.
.3
The Contractor shall remove the wash water after use from the tunnels within the
Contract limits and dispose of in accordance with the Specifications.
.4
Conduct bolt pocket, shear pin sockets, and surface imperfection patching application in
accordance with the segment manufacturers requirements and the requirements of the
manufacturer of the patching compound/materials.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE
SECTION 02437
ROCK REINFORCEMENT AND
EXCAVATION
PAGE 1 OF 9
.1
This section specifies requirements for the supply, installation and testing of rock
reinforcement and support for use in shaft, underground chamber and connecting tunnel
construction. In this context, the term underground chamber refers to deaeration
chambers at drop shaft locations, the chamber connection at the intersection of the EWT
and NST, and any diversion chamber or other structure excavation that extends into
bedrock.
.2
The requirements stated herein do not apply to the main tunnel sections for the EWT and
NST, because the specified method to be used for tunnel excavation and support, as
specified in Section 02430, Tunnel Excavation by Tunnel Boring Machine (TBM),
precludes the use of rock reinforcement as specified herein. However, in the event of any
enlargements for the Contractors convenience, as approved by the Engineer, or
construction of tail tunnels at launch shaft locations, these provisions will apply.
.3
Rock reinforcement and support elements addressed in this Section consist of the
following:
.1
.2
.3
.4
.5
Rock bolts
Rock dowels, including friction bolts
Steel straps or mine straps
Rolled steel channels
Welded wire mesh
.4
Steel rib supports are not specified. Should the Contractor or Contractors design
engineer determine a need for steel rib supports, the materials and installation procedures
are required to be detailed in a submittal to the Engineer.
.5
The identified rock reinforcement and excavation support elements shall be installed as
individual elements or in combinations as determined necessary by the Contractor or
Contractors design engineer to provide safe and stable shaft, underground chamber and
connecting tunnel excavations, as well as other enlargements or excavations made for the
Contractors convenience. This Section also details the methods to be used to select the
excavation support types for the excavations.
.6
Shotcrete may be used as an excavation support element in conjunction with the rock
reinforcement and excavation support specified in this Section. Shotcrete is specified in
Section 03361, Shotcrete.
.7
The Contractor is responsible to carry out the tests described here to verify that the rock
reinforcement comply with the Contract Documents, including sampling, curing,
transporting, testing and reporting,
.8
Additional requirements for support systems are specified in Section 02150, Excavation
Support System.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.2
SECTION 02437
ROCK REINFORCEMENT AND
EXCAVATION
PAGE 2 OF 9
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
1.3
REFERENCES STANDARDS
.1
.2
.3
.4
.5
ASTM D4435-13, Standard Test Method for Rock Bolt Anchor Pull Test
.6
ASTM F432-13 Standard Specification for Roof and Rock Bolts and Accessories
1.4
DEFINITIONS
.1
Rock Reinforcement: The use of rock bolts, rock dowels, steel straps, rolled steel
channels, welded wire mesh, spiles and shotcrete, with related support accessories, used
individually or in combination, to reinforce the in-situ rock mass and increase the
capacity of the rock mass to support itself. Rock reinforcement is intended to provide
tensile, shear, and frictional strength across rock discontinuities, to prevent progressive
failure of the rock mass along in situ or incipient planes of weakness. Rock
reinforcement is also referred to as initial support or excavation support. Related
accessories include, but are not limited to, steel washers, nuts, bearing plates, and
miscellaneous steel.
.2
Rock Bolt: A fully grouted initial support element consisting of deformed or threaded
steel bar installed in a hole drilled into the rock mass, fitted with standard end hardware
to allow the bolt to be tensioned. The bolt may have a mechanically set expansion anchor
that allows the bolt to be tensioned prior to grouting. Alternatively, if the bolt is grouted
using resin grout, then a fast-setting grout can be used in the anchor zone, with slower
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02437
ROCK REINFORCEMENT AND
EXCAVATION
PAGE 3 OF 9
setting grout used for the remainder of the bolt, allowing the bolt to be tensioned prior to
setting and curing of the slow set grout. Standard end hardware consists of a bearing
plate, one or more beveled washers, a flat steel washer and a hexagonal nut.
.3
.4
1.5
Grouted dowel: A deformed or threaded steel bar set in a hole drilled into the
rock mass and fully encapsulated in resin grout or cement grout; the bar is
installed without pretensioning and without end hardware, unless otherwise
specified. End hardware would be typically included to hold in place surface
elements such as welded wire mesh, steel straps or rolled steel channels.
Standard end hardware consists of a bearing plate, one or more beveled washers,
a flat steel washer, and a hexagonal nut.
.2
Friction bolt: An untensioned tube inserted into a drilled hole in a rock mass to
act as a reinforcing element. There are two basic types typically referred to as
Split Sets or Swellex bolts, although similar bolts are made by multiple
manufacturers. The former is a slotted steel tube with a tapered end that is
inserted into a drilled hole in the rock mass that is slightly smaller in diameter
than the bolt, and that is driven into the hole so that the exterior of the tube
makes full contact with the wall of the drilled hole along its full length and
circumference. The latter is a rock bolt made of a welded tube folded on itself
and sealed at one end that is inserted into a drilled hole in a rock mass and
expanded using a high pressure water flow provided by a special pump to
achieve full contact with the wall of the drilled hole along its full length and
circumference. Friction bolts shall not be installed to support the crown of the
NST and EWT connection chamber or the deaeration chambers.
Spile: A steel bar installed over the crown of a tunnel or chamber excavation and ahead
of the tunnel or chamber excavation face to provide temporary pre-reinforcement of
the crown during subsequent excavation. The bars are deformed or threaded steel bars,
and are fully grouted and installed in a percussion-drilled hole without pre-tensioning.
SUBMITTALS
.1
No less than 30 days prior to start of any excavation for which rock bolts or rock dowels
are to be used, submit shop drawings showing the following information for Rock Bolts
and Rock Dowels:
.1
Proposed layout for rock dowel/bolt installation together with type, size, length
and spacing of rock dowels, together with the type of accessories and surface
covering and the maximum time and distance from excavation at the face for
installation.
.2
.3
Applicable literature from both the steel bar and resin manufacturers including
manufacturer's recommended installation procedures for rock dowels on this
project.
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.5
Manufacturer's certified test results of gel time, working strength and shelf life
for each type of resin grout to be used. Manufacturers certified test results for
cement, grout mixes and working strength if cement grout is to be used.
.6
.7
.8
No less than 30 days prior to start of any excavation for which welded wire mesh, steel
straps, or rolled steel are to be used, submit shop drawings showing the following
information for each:
.1
.2
.3
1.6
SECTION 02437
ROCK REINFORCEMENT AND
EXCAVATION
PAGE 4 OF 9
Proposed layout for the welded wire mesh, steel straps, or rolled steel showing
sizes, details and arrangements of members, method of assembly, lists of
materials, and method of erection and blocking where required. Indicate the
maximum time and distance from excavation at the face for installation.
Provide certified mill reports for each of the surface reinforcement elements that
will be used.
Pull test equipment calibrations and pull test results. Submit results of all pull tests
within one day of performing the testing.
STORAGE AND PROTECTION
.1
1.7
Store and protect all rock reinforcement materials, including steel elements, accessories,
resin grout, cement and any additives, in accordance with the manufacturer's
recommendations and in a manner that prevents damage or deterioration.
MEASUREMENT AND PAYMENT
.1
1.8
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment, for all work required to reinforce rock excavated for shafts
and chambers as specified herein and no separate payment shall be made.
NOTED RESTRICTIONS
.1
Rock reinforcement is restricted by the sequence of excavation which requires that rock
reinforcement be installed, tested, tensioned (where applicable) and grouted (where
applicable) as the excavation is advanced.
.2
All necessary equipment and materials required to perform the Work are at the Work
Site, in sufficient quantity and in good working order.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 2
Products
2.1
MATERIALS
.1
.2
.3
SECTION 02437
ROCK REINFORCEMENT AND
EXCAVATION
PAGE 5 OF 9
Resin used as grout for rock dowels, rock bolts, or spiles shall be the product of
an established manufacturer who has been regularly engaged in production of
these products for at least 5 years, capable of developing the minimum yield
strength of the dowel. Resin cartridges shall have diameter and length
compatible with the work. Cartridge casing constructed of a saturated polyester
providing optimum resistance to moisture with a high frangibility for complete
mixing during installation. No resin shall be used after the expiration date stated
by the manufacturer.
.2
.3
.4
All resin cartridges shall be inspected prior to use. Cartridges, which have
hardened or have ruptured or are otherwise damaged, shall not be used.
Cement grout for encapsulating rock dowels and bolts shall be shrinkagecompensating grout specifically designed for encapsulation of rock dowels and
rock bolts, and the standard product of a recognized manufacturer of such grouts.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02437
ROCK REINFORCEMENT AND
EXCAVATION
PAGE 6 OF 9
.2
Grout shall achieve a minimum compressive strength of 6,000 psi at seven days
as determined by cube strength tests in conformance with ASTM C 109.
.3
.4
Design grout mix with flowability adequate for proper injection, consolidation,
and encapsulation. The cement grout shall completely encapsulate the rock
dowels and bolts without any air pockets. Admixtures that control bleed,
shrinkage, improve flowability. Reduce water content, and retard set may be
used subject to the approval of the Owner.
.5
Water for use in grout mixes shall be clean and free of deleterious substances.
.6
Centralizers shall ensure that the rock bolts/dowels are centered in the
hole and permit grout to move freely through the drilled hole.
.2
.4
.5
.6
Steel straps and rolled steel channels: Used to support the rock surface between
dowels or bolts. Conform to ASTM A36 and be compatible with dowels or bolts,
and with the intended function.
.2
.3
Bearing plates: Conform to ASTM A36, and meet the load/deflection criteria of
ASTM F432. Bearing plates against rock shall be a minimum of 9.5-mm thick
and have a minimum bearing area of 0.0232 square metres. Holes in plate shall
be reamed and beveled on the rock side and shall be large enough to permit 30
degree rock dowel or rock bolt skew in all directions from normal centerline.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.2
SECTION 02437
ROCK REINFORCEMENT AND
EXCAVATION
PAGE 7 OF 9
.4
Nuts: Shall be hex nuts of the heavy-duty type, shall be compatible with rock
bolts and rock dowels, and shall develop at least 125 percent of the minimum
yield strength of the element.
.5
EQUIPMENT
.1
Use drilling equipment for anticipated geologic conditions indicated in the GBR for
drilling holes to install rock dowels/bolts.
Part 3
Execution
3.1
GENERAL
.1
.2
Thoroughly scale freshly exposed rock surfaces prior to installing rock reinforcement.
The installation of rock reinforcement or surface treatment shall not be considered a
substitute for scaling.
.3
Following exposure of additional rock surface, examine the surface and confirm whether
or not the installed and planned rock reinforcement pattern will be adequate to provide
for the safety of personnel and stability of the excavation. Adjust the rock reinforcement
pattern, or install additional spot reinforcement in local areas of potential instability, as
necessary.
.4
Rock reinforcement bearing plates are to be set nearly flat against the rock face with the
bearing surface of the nut perpendicular to the Element as practicable.
.5
Maintain all temporary support throughout the length of the Contract. Periodically
inspect all exposed rock areas in the excavations and install additional temporary
support, as required.
.6
For all bolt types, upon completion of drilling, blow the hole clear with compressed air,
minimum 50 psi, introduced at the back of the hole. Holes drilled below horizontal shall
be blown clear immediately prior to bolt/dowel installation.
.7
During construction cement grout used for bolts/dowels installation shall be sampled and
tested for compressive strength for quality assurance. The frequency of the tests shall be
one test for every 50 bolts installed. The minimum compressive strength shall be 60 MPa
at 28 days as determined by cube strength tests in conformance with ASTM C 109. All
tests to be executed in the presence of the Engineer.
3.2
Insert individual resin cartridges carefully into the hole to avoid rupture, and position
with tamping rods. Use a shaped plastic cap after every third cartridge in holes rising at
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02437
ROCK REINFORCEMENT AND
EXCAVATION
PAGE 8 OF 9
more than 30 degrees above horizontal to maintain cartridges in position. Use the number
of cartridges per hole recommended by the resin cartridge manufacturer for the
combination of hole diameter and bar size being used to ensure complete encapsulation
of the dowel, bolt or spile.
.2
Insert the steel bar in the hole until it contacts the first cartridge. At this point rotate the
dowel at the rate recommended by the resin cartridge manufacturer, but not less than 100
rpm and insert it into the hole at a penetration rate of approximately 50 to 100 mm per
second, and continue rotation for at least 10 seconds after the dowel has been fully
inserted. Hold the bar until the resin has hardened sufficiently to keep the dowel in place.
.3
If the installation is for a rock bolt, ensure that the proper number of fast-setting resin
cartridges are used for the anchor zone of the bolt. Follow manufacturers
recommendations regarding resin set time. After the fast-setting resin gels and achieves
appropriate strength, but before the slower setting resin achieves its set, tension the bolt
as specified herein.
3.3
FRICTION BOLTS
.1
.2
3.4
Where welded wire mesh is used, welded wire mesh shall be fastened against excavated
rock surfaces by means of the installed rock dowels or bolts and shall follow rock
contours. Prior to installation of welded wire mesh, rock surfaces shall be scaled and
cleaned. The welded wire mesh shall be overlapped by an amount equal to 1-1/2 times
the mesh spacing at horizontal and vertical joints. Width of mesh shall be coordinated
with the anchor installation pattern. The mesh shall not be lapped at intermediate points.
Expansion bolts for supporting welded wire mesh from rock at intermediate points may
be used and shall be suitable commercially available steel bolts with resin anchors or
steel expansion shells. Expansion bolts shall be 19 mm in minimum diameter and of 305mm minimum length to extend approximately 305 mm into sound rock with sufficient
projection length from the rock for the proper attachment of the mesh with bearing
plates. Installed expansion bolts that become loose during or after attachment shall be retensioned or replaced.
.2
Where rolled steel channels are used, pin the channels with dowels or bolts. Ensure that
dowels or bolts are spaced appropriately to match anchor holes in the channels. Place
channels snug against rock surface and tighten bearing plate to the required working load
for rock dowels or bolts. Block rolled steel channels with hardwood wedges and/or
install additional rolled steel channels or steel straps along the length of the tunnel as
required to prevent fallout of rock.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
3.5
SECTION 02437
ROCK REINFORCEMENT AND
EXCAVATION
PAGE 9 OF 9
Where rolled steel channels and welded wire mesh are used together, welded wire mesh
shall be placed under the installed channels, where required, and drawn snug to the rock
surface by means of a bearing plate installed on the projecting end of each rock dowel or
bolt. Welded wire mesh shall be overlapped at the channel edges a minimum of two full
mesh widths.
STEEL STRAPS AND ROLLED STEEL CHANNELS
.1
Field bend steel straps as necessary to conform to the rock surface. Attach to the rock
using rock dowels or rock bolts.
.2
Place rolled steel channels against the rock surface to provide support to the rock surface
between rock dowels and rock bolts, as determined necessary by the Contractor or
Contractors design engineer.
.3
Block straps and channels where necessary with steel or wood wedges or shotcrete to
provide full contact between the rock and the strap.
3.6
.2
Maintain the equipment to be used for performing pull tests in good working condition.
.3
First five production rock bolts and the first five production friction and grouted steel
rock dowels of each type shall be tested. Thereafter rock bolts/dowels will be selected at
random by the Owner for testing. A minimum of three percent of each type installed
shall be tested. Perform tests not less than one or more than three days after installation.
.4
The bolt/dowel tested shall be considered to have failed and shall be replaced at no cost
to Owner if the total movement exceeds 13 mm or if movement occurs and continues to
occur below or at the indicated test load. Test up to three additional bolts/dowels
adjacent to a failed bolt/dowel. Replace the failed bolts/dowels at no additional cost to
Owner and retest the replacement bolts/dowels.
3.7
.2
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SUMMARY
.1
1.2
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 1 OF 15
This Section specifies the provisions, requirements, procedures and materials for shaft
and chambers grouting which shall be performed prior to the excavation of the shaft and
chambers designated as sealed. This Section also specifies grout materials, grout mixes,
grouting criteria, and performance requirements for each stage of the grouting program.
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
1.3
DEFINITIONS
.1
.2
.3
Closure Criteria: Criteria used to determine when an area undergoing grouting has been
sufficiently treated by evidence of reduction of the rock mass permeability. The measure
of the reduction of rock mass permeability will be determined by inflow measurement.
Criteria which are exceeded will determine whether it is necessary to drill additional
holes by the split-spacing approach and resume grouting.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 2 OF 15
.4
Ascending Stage Grouting: A procedure wherein a grout hole is drilled to the full
planned depth, or to such depth in response to subsurface conditions, then water tested
and grouted in packer isolated stages that are sequenced from the bottom to the top of the
hole.
.5
Grouting (Curtain Grouting): The injection of grout into grout holes arranged around the
shaft excavation and deaeration chambers as shown on the Contract Drawings. The grout
curtain is installed to reduce groundwater inflow into the shaft excavation.
.6
.7
Discrete Feature: A discrete joint or discontinuity in the rock mass as defined in the
GBR.
.8
.9
Hookup: The process of satisfactorily seating a packer at the top of a specified stage or
grout hole preparatory to performing a water pressure test or for grouting.
.10
Pre-excavation Grouting: The injection of grout into the ground or rock ahead of an
excavation through grout and probe holes drilled from within the excavation or ground
surface to control groundwater inflows or to improve ground conditions.
.11
Refusal: The point during grouting when little or no grout is accepted into the formation
under the maximum allowable pressure, which signals the completion of grouting in any
stage or hole.
.12
Staging: The breakdown of the grout or probe holes in intervals of stages. The basis of
staging a hole may be ground conditions encountered in the hole or for the purposes of
enhancing the effects of grouting. Staging may be performed in ascending or descending
methods where each stage is isolated by a packer for the purposes of water testing,
grouting and stabilizing and filling of the hole with grout and redrilled if conditions
require.
.13
Water Pressure Tests: Test consisting of measuring water take over a set time interval for
a particular stage or hole length at specified pressures. The purpose of water pressure
tests is to determine the ground/rock mass permeability and assist in selection of
appropriate grout mixes compatible with the measured permeability.
.14
Water to Cement Ratio: The ratio, as measured by weight, of water to cement in the
grout mix.
1.4
DESIGN CRITERIA
.1
The design criteria for curtain grouting shall be based upon specific closure criteria as
specified in 1.5 in this Section.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
1.5
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 3 OF 15
Pre-excavation grouting criteria, in all other areas, shall be determined by the Contractor,
subject to the limitations indicated below, and as accepted by the Engineer. Develop
efficient grouting/drainage means and methods to minimize impacts to the Champlain
Sea Clay.
PERFORMANCE REQUIREMENTS
.1
.2
Grouting:
.1
.2
.3
Closure criteria will be achieved when total seepage of water into a sealed shaft
or chamber through exposed rock does not exceed 2 liters per minute (3000
L/day) and at any time during excavation and upon completion of excavation as
measured by totalizing flow meters on the discharge lines.
Tolerances:
.1
Location and orientation for grout holes shall be as shown in the approved
working drawings and as described herein.
.2
SUBMITTALS
1.6
.1
.2
Integrate submittals specified herein with those specified for Section 02140,
Groundwater Control, Section 02450, Foundation and Load Bearing Elements (Rock
Anchors), and Section 02400, Shaft Construction.
.3
Product Data:
.1
.4
.2
.3
Equipment and procedures for conducting water pressure tests for each
method of grouting requiring such tests.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.5
.4
.5
.6
.2
.3
Mix Designs:
.1
.6
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 4 OF 15
Mix design data, including all mix components and test results to meet
minimum requirements specified herein.
.2
.3
.4
Initial and final set times for proposed mixes for the range of
water/cement ratios specified herein.
.5
Quality Control:
.1
Qualifications:
.1
.2
Certifications:
.1
.3
Recordkeeping:
.1
Logs for each shift for each type of probe/grout hole drilling including:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
1.7
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 5 OF 15
.2
.3
.4
.5
.6
.7
.8
.9
Grouting Records:
.1
.2
.3
.4
.5
.6
.7
QUALITY ASSURANCE
.1
Reference Standards:
.1
.2
ASTM Cl17, Test Method for Material Finer than 75-m (No. 200)
Sieve in Mineral Aggregates by Washing
.2
ASTM Cl36, Method for Sieve Analysis of Fine and Coarse Aggregates
.3
.4
.3
.2
Qualifications:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
Meetings:
.1
.2
1.8
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 6 OF 15
.2
Survey of hole layout for curtain grouting and hole layout for preexcavation grouting
.3
.4
.5
.2
.3
JOB CONDITIONS
.1
1.9
Anticipated subsurface conditions and unmitigated groundwater inflows are given in the
Geotechnical Baseline Report (GBR).
SEQUENCING AND SCHEDULING:
.1
1.10
.1
Transport, store, and handle materials in the manner prescribed by the manufacturers of
each product.
.2
.3
Cement:
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
1.11
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 7 OF 15
.3
Store cement such that each shipment can be identified and utilized separately.
.4
Cement shall be free from foreign matter and lumps. If cement is found to
contain lumps or foreign matter of a nature and in amounts deleterious to the
grouting operations, it shall not be used and shall be disposed of in a manner
satisfactory to the Owner.
.5
If bulk cement is used, accurate devices shall be used to measure the quantity of
cement delivered and utilized.
Chemical Grout:
.1
.2
Store and use the sodium silicate grout in the manner recommended by the
manufacturer.
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to execute pre-excavation grouting as
specified herein and no separate payment shall be made.
Part 2
Products
2.1
MATERIALS
.1
.2
General:
.1
.2
.3
All grouting materials used shall meet the requirements of Section 03300, Castin-Place Concrete (Shafts and Underground Structures) except as modified
herein.
Cement:
.1
.3
Admixtures:
.1
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
Water:
.1
.2
.5
.6
2.2
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 8 OF 15
Water used for all grout mixes shall meet the requirements of Section 03300,
Cast-in-Place Concrete (Shafts and Underground Structures).
The temperature of the water at the time of mixing shall be less than 25 degrees
Celsius.
Miscellaneous Materials:
.1
Caulking materials shall be kept available for use at all times during the
performance of grouting operations. These materials shall include oakum,
wooden wedges and burlap.
.2
Mixes:
.1
.2
Grout mixes shall be stable (less than 4% bleed) determined based on ASTM
C940 and shall have pressure filtration coefficients of 0.040 min- 112 or less,
determined based on API RP 13B-1.
.3
The Contractor shall design mixes with Marsh Cone values of less than 35
seconds, 40 to 50 seconds, and 60 to 75 seconds, determined based on API RP I
3B- I.
EQUIPMENT
.1
Drilling Equipment:
.1
Drilling equipment shall be selected to suit proposed methods, and for the
anticipated subsurface conditions as described in the Geotechnical Baseline
Report (GBR) to achieve the objectives of grouting specified herein.
.2
.3
Drilling equipment for grouting shall have capacity to drill to the depth and
alignment tolerances as shown on the Contract Drawings. Drilling equipment for
curtain grouting shall be selected to minimize the plugging of rock fractures or
damage to the rock mass.
.4
.5
Drill equipment and techniques shall be such as to minimize erosion and caving
in the hole.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.3
.5
.3
.4
Provide a means for increasing or decreasing the water/cement ratio at the mixer
as indicated by the field conditions.
.5
Provide a separate agitator serving as a holding tank between the mixer and the
pump that allows continuous pumping.
.6
Equip agitators with baffles to induce turbulence and rotating paddles that will
promote thorough mixing of the grout at all times prior to and during injection.
.4
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 9 OF 15
.2
.3
Provide a water connection on the grout pump to facilitate flushing the system
and injection of water into the grout holes.
.4
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
.6
.8
.9
.10
A sampling valve shall be placed beyond the point of mixing and the
baffling chamber, and shall be easily accessible for sampling mixed
grout.
Appurtenances:
.1
.7
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 10 OF 15
Packers:
.1
Packers shall be capable of tightly sealing the grout holes at the selected
locations and depths, such that grouting can be done at grout pressures
equal to the maximum pressure used in the hole without leakage. Packers
shall be designed prevent hydrostatic head build-up during placement
and seating of the packers. Packers shall be equipped with shutoff
valves.
.2
Grout pipe to and through the packer shall have a minimum inside
diameter of 38 mm.
Instrumentation:
.1
.2
Pressure Gauges:
.1
Gauges shall be accurate for the entire range of injection pressures, and
shall be provided with appropriate gauge savers.
.2
Pressure gauges shall be installed both at the collar of the hole and at the
pump.
.3
.4
Flowmeters:
.1
Furnish and install calibrated flowmeters for curtain grouting and pre
excavation grouting to monitor grout inflow for each hole.
.2
Piping:
.1
Locate a manifold consisting of a system of valves and pressure gauge in the line
at the collar of the hole to permit continuous circulation, accurate control and
monitoring of grouting pressure, bleeding, and regulation of flow.
.2
Size: Grout piping and hoses shall range in interior diameter between 25 mm and
38 mm.
Water pressure testing equipment shall include pressure gauges which are
appropriate for the intended pressure range and operation. Pressure gauges shall
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 11 OF 15
.11
.2
Headers used for water pressure testing shall include a "bleed-off ' valve to
facilitate adjustment of the test pressure.
.3
Pumps used for water pressure testing shall deliver a steady, non-fluctuating
flow within the desired range of test pressures.
.2
.3
Part 3
Execution
3.1
GENERAL
.1
Perform pre-excavation grouting for the purpose of reducing water inflows into the
shafts, chambers and their connections, the EWT or NST, or to stabilize ground
conditions in accordance with the approved working drawings and method statements.
.2
Do not perform grouting without the appropriate pressure gauges in place and in working
order, and appropriately checked with calibration gauges. Depending on magnitudes of
intervals of pressure needed for grouting, more than one range of gauges may be required
for any one heading.
.3
Discharge water from grouting operations shall be collected, treated and disposed of in
accordance with Section 01355, Waste Management and Disposal and Section 02140,
Groundwater Control.
.4
Appropriate calibration gauges shall continuously be available and used to calibrate field
gauges weekly, and as otherwise required.
.5
Any grout hole that becomes plugged or obstructed before water testing and grouting
shall be reopened, redrilled, downstaged or plugged with grout and abandoned.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
3.2
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 12 OF 15
Maintain equipment used for mixing and injection of grout in satisfactory operating
condition at all times. Keep equipment and lines clean by constant circulation of grout
and by periodic flushing.
PRE-EXCAVATION CURTAIN GROUTING
.1
.2
.3
General Requirements:
.1
The extent of drilling and grouting shall be adjusted as needed to achieve the
objectives based on conditions disclosed as excavation and grouting proceed.
.2
Grouting shall be carried out around the shaft or chamber primary support below
the secant pile in the rock excavated portion of the shafts or around chambers as
shown in the Contract Drawings. The purpose is to limit water infiltration into
the excavation through open fractures.
Drill grout holes to their full depth, clean, and grout in ascending stages from the
bottom of the hole.
.2
.3
Drill and grout holes such that a minimum distance of 8 m between holes to be
drilled and grouted is maintained until grout in holes within this distance has
completely set, or that no open grout hole exists within this distance of a hole to
be grouted.
.4
Monitor grout takes for each stage to determine the need for additional holes
split spaced between initial holes.
.5
Make successive reductions in the hole spacing until, in the judgment of the
Engineer, no further reductions in spacing are warranted by the conditions
encountered.
.6
Starting with the secondary holes, the drilling of any split-spaced curtain grout
hole shall not start until the grout in the two holes on each side of it has had time
to set.
.7
For all grouting holes, Contractor to determine the length of each stage.
.8
If the grout holes do not stay open during drilling, then a descending stage
grouting method shall be used.
.9
Each stage shall be water pressure tested and the stage shall be grouted to refusal
if the takes in the water pressure tests for that stage exceed the criteria specified
herein.
.10
After grouting each stage to refusal, failure to meet the preliminary closure
criteria in any stage shall mandate the drilling of additional holes midway
between existing adjacent holes (split-spacing).
Drilling Holes:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
.5
.1
Drill grout holes at the locations, orientation, inclinations, spacing and lengths
shown on approved working drawings.
.2
Diameter of all curtain grout holes shall have a nominal diameter of 50 mm.
.3
Use water as the exclusive circulation fluid for all drilling operations at a rate
sufficient to eject all drill cuttings and maintain a clean hole. Use of drilling mud
or polymers shall not be allowed.
.4
.5
Stop drilling the hole if there is evidence of caving or a total loss of circulation
water. If there is caving, descending stage grouting may be required.
.6
Perform water pressure test and inject grout into holes within 72 hours of initial
drilling.
Place grout agitators in the approximate center of the area being grouted at any
given time.
.2
Do not place the grout pump more than 15 m away from the hole being grouted.
Grouting of each stage shall be preceded by a water pressure test of each stage.
Water pressure tests shall consist of measuring water take over a 5-minute
interval at 2 bar above the height of the groundwater table or as approved by the
Engineer.
.2
.3
.6
.7
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 13 OF 15
.1
.2
All holes shall be grouted regardless of the results of water pressure testing.
Grout Mixing:
.1
.2
Add superplasticizers and other additives after partial mixing of the cementitious
materials, per approve work plans.
.3
Admixtures to increase flowability and stability of the grout mix shall be added
as required. Obtain flowability of grout using a dispersant, high-range water
reducers or superplasiticizer compatible with the cement being used.
Grout Injection:
.1
Injection pressures for curtain grouting shall not exceed 30 kPa per metre of
depth below the ground-rock interface for vertical depths up to 15 m and 45 kPa
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 14 OF 15
per metre of depth for > 15 m. Depths shall be measured to the center of the
interval being grouted.
.2
.8
Completion of Grouting:
.1
3.3
When the maximum allowable pressure has been reached, it shall be held and the
stage pumped to refusal in accordance with the refusal criteria.
Grout refusal for a specific stage in a grout hole has been achieved when the
following conditions are satisfied at the specified injection pressures:
.1
The rate of grout injection is less than or equal to 1.5 l/m for at least 5
minutes at the refusal pressure.
.2
.3
Inject no more than 100 sacks of cement into any single stage of a grout
hole, unless directed by the Engineer.
.2
Systematic curtain grouting shall be applied in primary and higher order grout
holes based on a pre-determined closure criterion.
.3
The addition of further holes beyond the mandatory primary holes shall be based
on reaching the designated inflow criterion.
SEALING INFLOWS
.1
Should there be any inflows observed into the excavation as excavation progresses the
Contractor shall grout additional curtain grouting holes or conduct grouting from within
the shafts or chambers to comply with the closure criteria.
.2
Other methods that can be used to comply with the closure criteria include sprayable
membranes in a sandwich configuration between two shotcrete layers in a way that meets
the leakage criteria. In this case the Contractor has to design the shotcrete to withstand
the external groundwater head.
.3
The Contractor shall propose methods to achieve the closure criteria as defined in this
Section.
3.4
Grouting Records:
.1
Data or notes taken by the Engineer during periodic inspections of grouting will
not relieve the Contractor's responsibility in documenting grouting operations.
.2
Provide survey equipment to ensure proper location and orientation of all curtain
grout holes.
.3
Execute at least one water pressure test for every 50m2 of rock that will be
exposed after excavation is finished to demonstrate that the grouted zones
comply with the performance requirements specified herein.
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.5
SECTION 02439
PRE-EXCAVATION GROUTING
FROM SURFACE
PAGE 15 OF 15
.2
.3
.4
.5
.6
.7
Refusal criterion has been satisfied for any stage of grouting within a
grout hole.
.8
CLEAN-UP
.1
.2
If leakage of grout, drill cuttings, or other foreign material occurs, remove and dispose of
such material by washing or other acceptable means.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE OF WORK
SECTION 02440
PIPE JACKING
PAGE 1 OF 8
.1
This section covers installation of the 1800mm internal diameter concrete pipe for the
Diversion Sewer by tunneling methods.
.2
The Contractor shall furnish all materials and equipment necessary for installation of a
concrete pipe as shown on the Contract Drawings and is responsible for selecting their
means and methods for completing the installation of the concrete pipe in compliance
with the Specifications.
.3
Rock tunneling shall include fabrication, transportation, testing, installation and launch
of the TBM; installation and use of all other tunnel excavation equipment; the
excavation, handling, removal, and disposal of all materials encountered in the tunnel
excavation; installation of concrete pipe where shown on the Contract Drawings or
specified in the Contract Documents; collecting and conveying all tunnel construction
water, including groundwater infiltration; provision of all temporary drainage, tunnel
ventilation, lighting, and wiring; tunnel safety; and all appurtenant work necessary to
complete the work in accordance with the Contract Documents.
.4
The excavated diameter of the tunnel shall be determined by the Contractor based on its
selected construction means, methods and equipment, subject to the limitations as shown
on the Contract Drawings or stated elsewhere in the Specifications. Excavate the tunnels
to the selected size; to the line and grade to allow the concrete pipe to be placed to the
line and grade shown on the Contract Drawings; and to within the tolerances specified
herein.
.5
Select and utilize methods and equipment compatible with the subsurface conditions
described in GBR.
.6
Tunnel Excavation by TBM for the EWT and NST is addressed in detail under Section
02430 - Tunnel Excavation by Tunnel Boring Machine (TBM).
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
.9
.10
1.3
SECTION 02440
PIPE JACKING
PAGE 2 OF 8
REFERNCES
.1
.2
CAN/CAS-A 257.3 - Joints for Circular Concrete Sewer and Culvert Pipe Using Rubber
Gaskets
1.4
DEFINITIONS
.1
Pipe Jacking: A system of directly installing pipes behind a shield tunnel boring machine
by hydraulic jacking from a drive shaft such that the pipes form a continuous string in
the ground. Tunnel muck is removed by muck cars, conveyor, slurry pipelines or augers.
.2
1.5
DESIGN CRITERIA
.1
Design shaft excavation support systems in accordance with Section 02150, Excavation
Support System.
.2
Jacking pipe shall be according to CAN/CSA A257.2 with a minimum class of 100-D.
.3
Jacking pipe shall contain two cages of circular reinforcement in the barrel of the pipe.
The outer cage shall extend into the bell of the pipe and the inner cage into the spigot of
the pipe. Elliptical reinforcement in the barrel of the pipe is not permitted for jacking
pipe.
.4
Design thrust block to withstand the maximum jacking force that the hydraulic jacking
system can produce without excessive deflection or displacement using a minimum
factor of safety of 1.5 for the maximum expected jacking force.
1.6
TOLERANCES
.1
Tunnel alignment shall not vary from the design alignment more than 100 mm
horizontally except at shafts or intersections where a 50 mm maximum variation applies.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.7
SECTION 02440
PIPE JACKING
PAGE 3 OF 8
SUBMITTALS
.1
Submit shaft excavation and support work plans per Section 02150, Excavation Support
System and Section 02400, Shaft Construction.
.2
Submit documentation showing that the Contractor and personnel meet the minimum
required qualifications. Include a list of a minimum of three projects similar in scope and
value to the project specified in the contract documents. Information must include, but
not be limited to date and duration of work, location, pipe information (i.e. length,
diameter, depth of installation, pipe material, etc.), project owner information (i.e. name,
address, telephone number, contact person), and the contents handled by the pipeline
(water, wastewater, etc.).
.3
Submit pipe jacking plan, complete with drawings, written descriptions, procedures, and
manufacturers information that details equipment, materials and construction
methodology. The plan shall include the following:
.1
Detailed tunnel boring machine dimensions and attributes including: shield and
gage cutter diameters, speed and torque ranges, face access for cutter changes,
capability for advance probing and grouting, flood door configuration,
.2
.3
.4
Description and capacity of the main jacking system including the details of the
thrust ring, thrust block, jacking controls, hydraulic pressure to jacking force
conversions and hydraulic jack calibration data.
.5
.6
.7
.8
Submit shop drawings detailing shaft layout plan and section views of shaft
support systems and detailing dimensions and sizes, and locations of all
equipment within available staffing areas at each shaft location required to
support pipe jacking operations. Equipment shall include but not be limited to
cranes, front-end loader, jacking pipe stockpiling, spoil transfer areas, spoil
hauling equipment, pumps, generators, lubrication plant, tool trailers, containers.
.9
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.10
1.8
SECTION 02440
PIPE JACKING
PAGE 4 OF 8
QUALITY ASSURANCE
.1
Supervision
.1
.2
Operators
.1
.3
Personnel experienced in pipe jacking with prior knowledge and ability in proper
operation of systems being employed with 5 years of previous experience.
Operation
.1
.2
.4
Run Test: Test full system on completion of set-up and before commencing drive.
.5
.6
1.9
Before commencement of any drive, demonstrate to Engineer that required setup procedures and system checks are complete and required materials are at hand
to commence drive.
.1
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to providing and installing reinforce
concrete pipe by pipe jacking as specified herein and no separate payment shall be made.
Part 2
Products
2.1
CONCRETE PIPE
.1
2.2
Reinforced concrete pipe for pipe jacking according to CSA- A257.2 - Reinforced
Concrete Culvert, Storm Drain and Sewer Pipe
GROUT
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.3
SECTION 02440
PIPE JACKING
PAGE 5 OF 8
Provide pipe-jacking system that has main jacks mounted in jacking frame located in
starting shaft.
.2
Has jacking frame that successively pushes string of connected pipes following TBM
towards receiving shaft.
.3
Has sufficient jacking capacity to push TBM and string of pipe through ground.
.4
Has at least 20% greater jacking load capacity than maximum calculated.
.5
Use jack thrust reaction blocks for pipe jacking that are adequate to support jacking
pressure developed by main jacking system. Special care shall be taken when setting pipe
guide rails in jacking shaft to ensure correctness of alignment, grade, and stability.
.6
Overall control system that enables remote control of all main operating functions of
system from one location, either at surface or underground.
.7
Main jacking system capable of exerting uniform load to casing pipe at speed
commensurate with speed of excavation advance.
.8
Ability to articulate and steer to correct vertical and horizontal deviation from alignment
datum by remote activation.
.9
Part 3
Execution
3.1
SHAFT INSTALLATION
.1
.2
3.2
PREPARATION
.1
Maintain clean working conditions inside jacking operation area and remove spoil,
debris, equipment, and other material not required for operations.
.2
Provide power generation equipment and other equipment operating on or with fuel or
lubrication oils with suitable barriers and safeguards to ensure no loss of oil to drains or
to contaminate ground.
3.3
TUNNEL EXCAVATION
.1
All materials encountered shall be regarded as unclassified. All excavated material must
be removed and disposed of in accordance with the Specifications. If the Contractor uses
or proposes to use tunneling methods which, in the opinion of the engineer, are not such
as to permit close adherence to line and grade, the Engineer may require the Contractor
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02440
PIPE JACKING
PAGE 6 OF 8
to revise his procedure to comply with methods which will give more satisfactory results.
Any changes required by the Contractor to comply with tunnel line and grade are at the
contractors cost and no additional payment or schedule extension will be granted to the
Contractor.
.2
Excavated material shall be handled in the underground opening and transported, hoisted
and loaded in accordance with applicable federal and provincial safety requirements and
Section 01710, Tunnel and Shaft Safety. Continuously remove muck from the mined
excavation as the tunnel is advanced.
.3
.4
The TBM shall be designed to permit critical and long-lead replacement parts to be
replaced from within the tunnel.
.5
The Contractor shall note that the TBM components as well as other excavation
equipment will be subject to abrasive ground conditions. Tunneling components subject
to high abrasive wear are, but not limited to, cutting tools, conveyors or other spoil
handling equipment, and sump pumps.
.6
The Contractor shall provide TBM spare parts that are considered critical and long-lead
items. Contractor shall maintain an inventory of spare parts as recommended by the
TBM manufacturer, to ensure continued operational availability of the TBM and
essential systems.
.7
Provide and maintains pipe lubrication system at all times to lower friction developed on
surface of pipe during jacking.
.8
The TBM shall be steer-able so as to maintain line and grade within the tolerances
specified.
3.4
The Contractor is solely responsible for evaluating the ground conditions and ensuring
the appropriate equipment and installation procedures are employed during the work.
.2
.3
Tunnel excavation shall not begin until a survey control has been established for the
TBM and tunnel.
.4
Tunnel excavation shall not begin until Contractors site safety representative has
reviewed and approved preparedness of Health and Safety Plan as per Contract
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02440
PIPE JACKING
PAGE 7 OF 8
Documents including emergency plan in accordance with OHSA and other applicable
requirements.
.5
The cutting tools shall be accessible for replacement during a drive without the use of a
rescue shaft.
.6
Develop uniform distribution of jacking forces on end of pipe by use of spreader rings
and packing measured by operating gauges.
.7
Maintain clean working conditions at all times inside the tunnel and shafts. All muck,
slush, grout spills, ponded water, and any other material not required for tunneling shall
be removed from the excavations in a timely manner.
.8
Provide sufficient overcut to minimize friction on the pipe. Overcut shall not exceed
25 mm on the radius without acceptance of the Engineer.
.9
The TBM shall be sealed to the leading pipe to prevent infiltration of soil, groundwater,
or lubricant into the tunnel.
3.1
3.2
All excess material resulted from pipe jacking operation that is be removed from site
shall comply with Section 01355, Disposal Excess Material.
SAFETY REQUIREMENTS
.1
Methods of construction for the tunnel shall be such as to ensure the safety of the work,
the Contractors employees, the public, and adjacent property, whether public or private.
All work shall conform to the requirements of Section 02444, Tunnel and Shaft
Ventilation and Utilities and Section 01710, Tunnel and Shaft Safety.
.2
Operations shall be conducted to minimize the impact of noise and dust to the residents
in the vicinity of the work. All surface equipment shall be equipped with noise
suppressors and enclosed in sound attenuation enclosures. All compressors shall be
enclosed in sound attenuation enclosures. All gasoline, diesel or air-powered equipment
shall be equipped with silencers or mufflers on exhaust lines. Storage bins and hoppers
shall be lined with materials that deaden sound.
3.3
Control the excavation of the tunnel and construction of the excavation support to allow
construction of the final lining elements in accordance with the specified tolerances.
.2
Survey the invert of the tunnel excavation at 20 m intervals to ensure the alignment is
within the tolerances specified. Conduct the survey using procedures submitted in
accordance with this Section.
.3
The Contractor shall demonstrate to the Contract Administrator that the surveyed
location of the heading at 20 m increments during excavation is within specified
tolerances.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02440
PIPE JACKING
PAGE 8 OF 8
.4
In the event that tolerances are exceeded, the additional excavation and associated work
necessary to bring the alignment of the tunnel within the stated tolerances shall be at no
additional cost to the Owner.
.5
Free access will be provided to the Owner for the Owners surveyors to conduct tunnel
line and grade surveys as requested by the Owner.
3.4
TEMPORARY VENTILATION
.1
Comply with the requirements of Section 01710, Tunnel and Shaft Safety and Section
02444, Tunnel and Shaft Ventilation and Utilities. Remove system(s) from the site when
work is completed.
.2
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE OF WORK
.1
1.2
SECTION 02442
OTHER TUNNEL EXCAVATION METHODS
PAGE 1 OF 7
.2
.3
.4
.5
.6
Design, supply and installation of the excavation support systems to permit the
excavation and installation of the permanent tunnel lining as per Section 02150,
Excavation Support Systems.
RELATED WORK
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
.13
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.3
SECTION 02442
OTHER TUNNEL EXCAVATION METHODS
PAGE 2 OF 7
REFERENCES
.1
.2
1.4
DEFINITIONS
.1
Tunnel line and grade: The designed alignment and the grade of the chambers and
tunnel.
.2
Ground Loss: Loss or removal of material in excess of that replaced by the shored
excavation.
.3
.4
.5
1.5
.1
1.6
.1
.2
Mucking.
.3
Overbreak: The amount of rock excavation outside the Contractors selected excavation
dimension due to geological factors and/or the Contractors means, methods, and
workmanship.
CLASSIFICATION OF EXCAVATION
Rock excavation involves excavation of a partial or full face tunnel or chamber of rock
material regardless of unconfined compressive strength or geologic rock type or
condition by one of the following methods:
.1
.2
.3
Hydraulic hammer
TOLERANCES
.1
The Contractor shall determine the tunnel excavated diameter based on final lining and
required excavation support, subject to minimum requirements and limitations shown on
the Contract Drawings. Final tunnel lining shall be constructed to within the following
tolerances:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Departure From:
established tunnel horizontal
alignment
established tunnel grade
Convergence points
.1
1.7
SECTION 02442
OTHER TUNNEL EXCAVATION METHODS
PAGE 3 OF 7
Not to Exceed:
A maximum of 50 mm
+ or - 25 mm
Refer to Section 02481
SUBMITTALS
.1
.2
.2
.3
Proposed work hours, number of shifts per day and number of days worked per
week, along with crew size and make-up.
.4
.5
.6
.7
.8
.9
Muck handling equipment and methods, including muck transfer from the
heading, surface retention, and disposal.
.10
.11
.12
.13
Provisions for controlling line and grade, and survey frequency with respect to
progress of excavation.
.14
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.15
1.8
SECTION 02442
OTHER TUNNEL EXCAVATION METHODS
PAGE 4 OF 7
1.9
Comply with Section 01710, Tunnel and Shaft Safety and Section 02444, Tunnel and
Shaft Ventilation and Utilities.
MEASUREMENT AND PAYMENT
.1
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to excavate including installation of
support systems for the deaeration chambers at Site 3A and Site 8 and the connection
tunnel to the IOS at Site 5, widening the EWT for the connection of shafts 2, 4 and the
EWT and NST intersection; and widening the NST for the connection of shaft 9, the
EWT and NST tunnels by TBM as specified herein and no separate payment shall be
made.
Part 2
Products
2.1
EQUIPMENT
.1
.2
Comply with Section 02444, Tunnel and Shaft Ventilation and Utilities.
Part 3
Execution
3.1
GENERAL REQUIREMENTS
.1
The Contractor is responsible for selecting methods of tunneling that are compatible with
the ground conditions as indicated in the GBR, with design, placement and performance
of initial ground support systems, with placement of final lining, with measures for
control of water, and with requirements for safety of personnel and protection of
adjacent property.
.2
Maintain continuous ground support during excavation, or open up only as much ground
as is safely self-supporting until initial support can be provided.
.3
Maintain tunnel/chamber excavation line and grade to provide for construction of final
lining within specified tolerances.
.4
.5
Monitor vertical and lateral ground movements outside excavations and inside
excavations, and monitor groundwater levels outside of excavations, as necessary to
ensure the stability of the excavation and the protection of adjacent work and property.
Maintain records of monitoring performed and provide copies to the Contract
Administrator each week, or more frequently if requested by the Contract Administrator.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02442
OTHER TUNNEL EXCAVATION METHODS
PAGE 5 OF 7
.6
In the event that excavation threatens to endanger personnel, the Work, or adjacent
property, cease excavation. Evaluate methods of construction and revise as necessary to
ensure the safe continuation of the work.
.7
.8
The Contractor is fully responsible for developing the ground stabilization, and initial
ground support system as specified in Section 02150, Excavation Support Systems or as
determine by the Contractors design engineer, and water control grouting program for
the chambers and tunnel as specify in Section 02439, Pre-excavation Grouting from
Surface and shown in the Contract Documents. The Contractor is fully responsible for
the design and success of the grouting operation when needed. If the grouting fails to
achieve the necessary results then the Contractor shall develop mitigation solutions for
review by the Contract Administrator.
.9
For the purpose of determining whether or not the baseline groundwater inflow defined
in the Contract Documents have been exceeded, the groundwater inflow measurements
shall be made in such a manner that inflows from the feature(s) can be clearly and
accurately differentiated from other adjacent features.
.10
The Contractor shall design, supply, install, operate, maintain and remove on completion
all groundwater control systems. The Contractor shall dispose of groundwater under
terms of all applicable permits.
.11
The deaeration chamber at Site 8 is not allowed to drain free for more than 150 days.
Final lining shall be installed as soon as possible to limit potential impacts on
groundwater table.
3.2
ROCK EXCAVATION
.1
Perform excavation and install initial support systems in a manner that minimizes
overbreak. The cost of handling overbreak and backfilling the resulting voids will be
considered incidental to the Work, and no additional payment will be made.
.2
Protect rock surfaces in shafts and tunnels with shotcrete, or other means as shown in the
Contract Drawings or designed by the support design engineer as necessary to prevent
deterioration resulting from exposure to air and water.
.3
At Sites 3A, 4, 8, 9 and 10 where shafts have been designated as sealed, the Contractor
may propose additional methods to pre-excavation grouting for Contract Administrators
review and acceptance to comply with maximum groundwater flow into the excavation
as defined in Section 02150, Excavation Support Systems.
3.3
The reuse of rock material on-site shall be in such a manner as to prevent or eliminate the
potential for material to become a contaminant in the environment, cause or have the
potential to cause an adverse effect (as defined by Ontario Environmental Protection
Act).
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02442
OTHER TUNNEL EXCAVATION METHODS
PAGE 6 OF 7
.2
Sampling and testing of muck shall be executed to determine if material meets the
standards provided in R.R.O. 1990, Reg. 347 (as amended) and can be reused within the
Project site bounds. Sampling and testing shall be at intervals no greater than 500 cubic
metres. Testing of the material must be completed by a laboratory with internationally
recognized accreditations and the analytical procedures be in accordance with O.
Regulation 153/04.
.3
3.4
3.5
Comply with Section 01710, Tunnel and Shaft Safety and Section 02444, Tunnel and
Shaft Ventilation and Utilities.
VENTILATION
.1
Comply with Section 02444, Tunnel and Shaft Ventilation and Utilities.
.2
Advance of the ventilation system shall be made a regular part of the normal excavation
cycle.
.3
Direct an airstream at the face to provide turbulent mixing and immediate dilution of
hazardous gas inflow with fresh air. Operate auxiliary fans and blowers to minimize
recirculation and provide ventilation air that effectively sweeps the face.
.4
Wash and filter exhausted air as necessary to remove excess dust particles, prior to
discharge to the atmosphere.
.5
Perform smoke tube tests in the chamber\tunnel heading to identify air recirculation and
areas of dead air. Modify or adjust the ventilation system as necessary to eliminate any
deficiencies. Maintain records of these observations, and provide copies to the Contract
Administrator, on a weekly basis, of measurements made the previous week.
3.6
.2
Position sensors at locations that provide for the most effective measurement of
combustible gases. Place sensors out of the fresh air stream.
.3
.4
Check all air monitoring equipment with a known mixture of gas, and calibrate if
necessary at least once every 30 days, and maintain in accordance with the
manufacturer's recommendations. Maintain calibration records and make available to the
Contract Administrator on request.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
3.7
SECTION 02442
OTHER TUNNEL EXCAVATION METHODS
PAGE 7 OF 7
.1
Prepare a plan for chamber/tunnel evacuation and a separate plan for tunnel re-entry, to
be implemented in the event that the air monitoring system alarms or automatic power
shutdown occurs. The plans shall outline the duties and responsibilities of all affected
personnel. The evacuation plan shall address elimination of ignition sources from battery
powered and diesel equipment.
.2
Post the evacuation and re-entry plans in a readily visible location at the entrance shaft.
Train workers in tunnel evacuation procedures.
.3
All unplanned tunnel evacuations shall be brought to the attention of the Contract
Administrator and the Contractor superintendent immediately, and prior to initiation of
tunnel re-entry procedures.
3.8
ILLUMINATION
.1
Comply with Section 01710, Tunnel and Shaft Safety to provide lighting for the entire
chamber/tunnel.
.2
Provide additional lighting in tunnel and shafts as appropriate to provide for inspections
of construction operations by the Contract Administrator, including but not limited to the
substantial completion inspection.
3.9
EMERGENCY MEASURES
.1
Provide emergency electric power supply that is independent of the primary electric
power supply, and which is capable of powering the tunnel lighting, ventilation and
unwatering systems. Perform an initial test and periodic tests thereafter in the presence
of the Owner.
.2
Whenever there is a condition which is likely to endanger the stability of the excavation
or adjacent work or structures, operate with a full crew for 24 hours per day including
weekends and holidays without interruption until those conditions are mitigated.
3.10
SURVEYING
.1
Survey each tunnel/chamber regularly to ensure line and grade are maintained as
designed. Within three working days of performing survey, provide a report to the
Contract Administrator showing actual line and grade with respect to design line and
grade.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE
.1
SECTION 02444
TUNNEL AND SHAFT VENTILATION
AND UTILITIES
PAGE 1 OF 8
The work specified in this Section includes the design, procurement, installation,
operation and removal of all temporary facilities required for the following:
.1
Ventilation, cooling, dust removal and maintenance of acceptable air quality and
environmental conditions, including the providing of sufficient ventilation flow
for dispersion, dilution and exhaust of toxic or explosive gases which may enter
the tunnel or other excavations in gaseous phase through soil or rock or via
groundwater flows and seepage. The ventilation system will also provide for
dispersion, dilution and exhaust of fumes from equipment operation and other
activities within the tunnels and shafts.
.2
Lighting along the length of tunnels, in shaft bottom areas, in shafts, and in the
vicinity of all equipment for safe operations.
.3
.4
Water and compressed air for construction, fire protection, and other use in
shafts and tunnels, with water available as stated in Section 01510, Temporary
Utilities.
.5
Discharge lines and intermediate sump pumps to remove and convey all
construction water, including groundwater inflows, from tunnels and shafts.
.6
.7
.8
Sanitary facilities at the tunnel headings and at the bottom of the construction
shafts.
.2
All work specified in this Section shall be the Contractors responsibility. All work shall
comply with all applicable federal, provincial and local codes, laws, regulations and
ordinances.
.3
The facilities to be provided include, but are not limited to, the following items: fans,
ventilation ducting, scrubbers, pumps, piping, water, compressed air, lighting,
components for hanging, fastening, and securing the facilities, power supplies, controls,
monitors, communication lines, heating facilities if required, and spot coolers as
required.
1.2
QUALITY CONTROL
.1
The facilities herein specified shall be designed by a firm or individual with a minimum
of five years of experience, all in the last seven years, designing ventilation and electrical
facilities for tunnel construction. The firm shall be operated and maintained by personnel
with a minimum of three years of experience within the last five years.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02444
TUNNEL AND SHAFT VENTILATION
AND UTILITIES
PAGE 2 OF 8
.2
All electrical systems, including electrical components of the ventilation system, shall
comply with applicable requirements of O. Reg 213/91 and R.R.O. 1990, Reg. 854.
Electrical systems shall comply with requirements for operation in Class I, Division 2
locations.
.3
Air Monitoring Program: The Contractor shall monitor air quality at the TBM and
elsewhere as appropriate in accordance with applicable regulations and requirements
stated further in this Section.
1.3
RELATED SECTIONS
.1
.2
.3
.4
1.4
REFERENCE STANDARDS
.1
.2
.3
Ontario Health and Safety Act (OHSA), R.R.O. 1990, Reg. 854, Mines and Mining
Plants.
.4
.5
.6
.7
All other federal, provincial and local requirements and regulations in effect at the time
of construction.
1.5
SUBMITTALS
.1
Not less than 30 days prior to the start of any tunnel, shaft or related structure
excavation, the following specific information shall be provided:
.1
Layout, details and specifications for all ventilation components, including but
not limited to: locations, sizes, manufacturers operating manuals, operating
configurations, ducting, methods of joining lengths of duct together, methods of
suspending the ducts, noise attenuation devices, fan noise performance data, fan
pressure / performance curves, control and operating systems, as well as backup
systems for electrical power and controls in event of loss of power or other
failure of the system to continuously provide the required minimum airflow in
the tunnels and shafts at all times.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.2
.3
.4
.5
Details of all air flow and pressure monitoring equipment together with a
schedule for proposed periodic air quality measurements at the face and at other
working areas away from the face. All air flow monitoring and ventilation
system performance data shall be submitted electronically, in a form acceptable
to the Engineer, on a weekly basis.
.6
Plan for emergency response in the event of a fire in the tunnel or any shaft, with
an assessment of the likely heat release rate and location of potential fires. The
Contractor shall demonstrate that safe egress is possible in the event of a fire in
the tunnel. Coordinate with and include details, as appropriate, in the Sitespecific Health and Safety Management Plans submittal required under Section
01705, Contract Work Health and Safety Clauses.
1.6
SECTION 02444
TUNNEL AND SHAFT VENTILATION
AND UTILITIES
PAGE 3 OF 8
Ventilation performance records and daily air quality measurements, which shall
be submitted on a weekly basis to the Engineer.
The Contractor shall install air quality monitoring equipment at all launch sites upon the
commencement of work at site.
.2
.3
.1
Carbon Monoxide
.2
Methane
.3
Hydrogen Sulphide
.4
Ozone
.5
.6
.7
Sulpher Dioxide
.8
Nitrogen Dioxide
The air monitoring equipment shall measure the air quality measures at least hourly and
shall produce an hourly Air Quality Index (AQI) in accordance with Air Quality Ontario
standards. The monitoring shall be continuous and occur 24 hours a day, seven days a
week, including non-working dates. AQI hourly readings shall be included on the
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02444
TUNNEL AND SHAFT VENTILATION
AND UTILITIES
PAGE 4 OF 8
Contractors daily reports. As not part of the AQI, the Contractor shall separately report
the Particulate Matter 10 results.
.4
Should the Contractors operations result in the AQI to poor quality when other air
monitoring stations nearby are reporting better air quality measures, the Contractor shall
immediately adjust its operations in order to improve the air quality.
.5
Should the Contractors operations result in the AQI to very poor quality when other
air monitoring stations nearby are reporting better air quality measures, the Contractor
shall immediately Stop Work until such time when emission reductions are in place.
.6
Submit all measured air quality monitoring monthly for all parameters listed.
.7
The Contractor shall arrange their work compounds as much as practicable to place
emission creating or ventilation stacks as far away from surrounding structures.
1.7
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
Measurement and Payment for all work required to providing and installing tunnel and
shaft ventilation and other utilities as specified herein or as necessary to provide a safe
working environment as specified herein and no separate payment shall be made.
Part 2
Products
2.1
Materials may be new or used, shall be adequate for purposes intended; and shall satisfy
requirements for codes and regulations pertaining to the system. Tunnel and shaft
support equipment and materials, including but not limited to utilities, shall be made of
such materials and maintained in such a manner so as not to impair production or expose
workers to safety hazards due to deterioration of the components or support equipment
resulting from exposure to gases or other contaminants identified in the contract
documents or that may be reasonably anticipated. Equipment and utilities within the
tunnel and shafts shall also be so designed, fabricated, maintained and operated in such a
manner to avoid accidents due to explosion or fire resultant from the equipment
operation in an explosive atmosphere.
.2
Select equipment and components that are sturdy, resistant to water damage and
deterioration under the conditions of the Project.
.3
.4
Select ventilation duct design for maximum airflow and minimum air leakage and
resistance to fire hazards. Duct sizes shall be determined by the Contractor. Total
leakage along the duct line shall not exceed one half of the air volume flow in the duct at
the inlet. All bends shall be formed of rigid duct materials.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
SECTION 02444
TUNNEL AND SHAFT VENTILATION
AND UTILITIES
PAGE 5 OF 8
Procurement of electrical power, potable water, sewer services, and sanitary facilities
shall be the Contractors responsibility.
Part 3
Execution
3.1
DESIGN
.1
Systems shall be installed in a neat and orderly manner, made structurally, mechanically
and electrically sound, maintained to provide safe, continuous service at required times
and to the minimum requirements outlined in these specifications, and modified and
extended as work progresses.
.2
Fresh air must be supplied to all underground work areas in sufficient amounts to prevent
any dangerous or harmful accumulation of dust, fumes, vapors, or gases in accordance
with requirements as stated in Section 01710, Tunnel and Shaft Safety and as required by
O. Reg. 213/91 and R.R.O. 1990, Reg. 854. In any event, sufficient ventilation shall be
provided at all times and locations to adequately disperse and dilute contaminants below
their acceptable levels. The additive effect of multiple contaminants shall be considered
when calculating the acceptable levels of airflow. In designing and operating the tunnel
and shaft ventilation system, Contractor shall also consider the equipment to be used in
prosecuting the work and the potential for encountering toxic or explosive gases as
excavation proceeds. The ventilation system shall be designed to operate in confined
spaces that may contain atmospheric hazards as required by Section 01710, Tunnel and
Shaft Safety. The design of the ventilation system shall consider at least the following:
.1
.2
.3
.4
.5
.6
Number and types of equipment in the tunnel, and their effects on air quality and
temperature.
.7
Methods of cooling TBM motors; water sprays for dust control; ventilation of
tunnel face; and removal of dust from the ventilation air.
.8
Friction losses, loss of air through duct leakage, minimum air velocity in the
tunnel.
.9
Phasing of the systems as the shaft and tunnel advances, and during retreat at
completion.
.10
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
3.2
SECTION 02444
TUNNEL AND SHAFT VENTILATION
AND UTILITIES
PAGE 6 OF 8
.11
.12
.13
.14
The Contractor shall design lighting and illumination system in the tunnels and any other
general underground work area during all operations in conformance with the
requirements of Section 01710, Tunnel and Shaft Safety
OPERATION
.1
Operate the tunnel main ventilation system continuously 24 hours per day, seven days
per week.
.2
In the event of primary ventilation system failure for any reason, withdraw all persons
from the tunnel. Permit limited access to those working to restore normal ventilation.
Following restoration of ventilation flow, verify the air quality and modify ventilation
system as required to meet OSHA requirements, prior to permitting re-entry of
personnel.
.3
Control of the ventilation systems shall be at ground surface; appropriate delays and
interlocks shall be provided for proper sequencing and operation of fans, including
reversal of fans.
.4
The exhaust/intake of the fans shall be kept clear of surface engine exhausts and at least
15 m from the edge of the shaft.
.5
Ground electrical equipment shall connect to an installation that extends throughout the
underground workings.
.6
Lighting and ventilation facilities shall be left in the tunnels and shafts until work has
progressed to the point at which such facilities must be removed to accomplish activities
such as constructing connections to dropshafts or cleaning. When appropriate, lighting
and ventilation facilities and all loose or projecting hangers and supports shall be
removed. Ventilation ducting may be removed on completion of excavation, providing
that positive through-tunnel ventilation is achieved by means of a bulkhead and
ventilation fans, or other arrangements such as a jet fan. In any event, sufficient
ventilation shall be provided at all times and locations to adequately disperse and dilute
contaminants below their acceptable levels.
.7
Provide and maintain communication systems in accordance with Article 3.3 below.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
3.3
SECTION 02444
TUNNEL AND SHAFT VENTILATION
AND UTILITIES
PAGE 7 OF 8
Monitor and provide airflow measurement data on a weekly basis and submit the results
to the Engineer, in a form and format approved by the Engineer, demonstrating that the
ventilation system is providing airflow in compliance with the minimum requirements
outlined in these specifications.
FIRE SAFETY
.1
.2
Conveyor Systems:
.3
.1
Vertical conveyors, if used, shall be outfitted with a deluge system, and the drive
motor stations of horizontal conveyors shall be protected either by water or dry
chemical protection. Booster drives, splicing stations, tail pulleys, and other
fixed pieces of equipment on vertical and horizontal conveyors and related
assemblies used underground shall be protected by fixed fire sprinklers or other
means. The deluge sprinkler system design shall include a Siamese connection
for an alternate water source. Provide means of testing all systems. Testing will
be required two times a year.
.2
Test samples of the actual conveyor belt materials shall be tested by a recognized
testing laboratory to determine the exact fire propagation index. The results of
the tests shall be used for emergency planning purposes.
.3
All belt conveyors used underground shall be equipped with pulley slippage
systems designed to shut down the belt if sliding friction develops between the
drive pulley(s) and the belt. The slippage system shall be inspected in
accordance with the manufacturer's recommendations.
.4
Any conveyor belt systems shall be equipped with interlock(s) compatible with
all conveyor system components, which shall shut down belt conveyors if any
conveyor in the system should stop or reduce its normal speed or upon activation
of a conveyor-related fire protection system.
.5
Fixed combustible materials such as lagging, posts, cribbing and roof supports
shall be either metal guarded from contact by conveyor belt(s) or located at least
half the width of the belt for an idler or pulley. Machinery guarding in the drive
area and at other points along the belt shall be of non-combustible material.
.6
Belt conveyors shall utilize structures that do not provide a deck between the
upper and lower strands of belt except at necessary transfer points and belt
splicing locations. Structures at transfer points and belt-splicing locations shall
not be constructed in a manner, which will cause hazardous accumulations of
material.
Communication Systems:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02444
TUNNEL AND SHAFT VENTILATION
AND UTILITIES
PAGE 8 OF 8
.2
Each field office of the Engineer shall be provided with one fixed-wire device
dedicated to maintaining communication with the underground work area at all
times. In addition, each field office of the Engineer shall be provided with four
radios and chargers of the same type and including all frequencies and channels
used by the Contractor.
.3
Fixed communications wiring and equipment shall be located away from fire
sources such as, but not limited to, transformer and conveyor systems.
.4
.5
.6
.4
.5
Drainage Systems: The drainage system in underground work areas of the tunnel shall be
designed and installed as to accommodate the maximum expected sprinkler or fire hose
discharge in addition to all other construction water as indicated in Section 02140,
Groundwater Control.
3.4
CLEANING
.1
Upon completion of the work, all temporary lighting, tunnel track system, ventilation
equipment and utility lines shall remain the property of the Contractor and shall be
removed from the site.
.2
All areas disturbed by the installation shall be restored to a condition satisfactory to the
Engineer, including patching of any anchorages in precast or cast-in-place concrete
linings.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.0
GENERAL
1.1
Scope of Work
1.2
SECTION 02450
MICROPILE FOUNDATION
PAGE 1 OF 17
.1
This work shall consist of constructing micropiles as shown on the contract plans and
approved working drawings and as specified herein. The micropile specialty Contractor is
responsible for furnishing of all design, materials, products, accessories, tools, equipment,
services, transportation, labour and supervision, and manufacturing techniques required
for design, installation and testing of micropiles and pile top attachments for this project.
.2
The selected micropile Contractor shall select the micropile type, size, pile top
attachment, installation means and methods, estimate the ground-grout bond value and
determine the required bond length and final micropile diameter. The micropile
Contractor shall design and install micropiles that will develop the load capacities
indicated on the contract plans. The micropile load capacities shall be verified by
verification and proof load testing as required and must meet the test acceptance criteria
specified herein.
DESCRIPTION
.1
1.3
.2
.3
The Contractor shall have previous micropile drilling and grouting experience in
soil/rock similar to this project conditions. The Contractor shall assign an Engineer to
supervise the work with experience on at least 3 projects of similar scope to this project,
completed over the past 5 years. The on-site foremen and drill rig operators shall also
have experience on at least 3 projects over the past 5 years installing micropiles of equal
or greater capacity than required in these plans and specifications.
Perform Micropile design and installation work in accordance with the following standards,
except where specified otherwise.
.1
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.4
1.5
.4
.5
.6
.7
.8
.9
.10
.11
.12
ASTM A252 Specifications for Welded and Seamless Steel Pipe Piles.
.13
ASTM D1143 Specifications for Method of Testing Piles Under Static Axial
Compressive Load
.14
ASTM D3689 Specifications for Method of Testing Individual Piles Under Static
Axial Tensile Load
.15
.16
REGULATIONS
.1
Abide by the current bylaws and regulations of the province and/or municipality in which
the work is located, and abide by the current laws and regulations with regard to public
safety.
.2
The codes and regulations of the Minister of Labour, Occupational Health and Safety
Act, the Workers Compensation Board and other applicable acts administered by the
authority having jurisdiction in the Province of Ontario apply to the work of this section.
SAFETY
.1
1.6
SECTION 02450
MICROPILE FOUNDATION
PAGE 2 OF 17
GEOTECHNICAL REPORT
.1
Refer to the geotechnical investigation report conducted for the present contract for
micropile design and installation recommendations.
.2
Ensure the requirements of the geotechnical report is read and understood prior to
commencing with work.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.7
1.8
SECTION 02450
MICROPILE FOUNDATION
PAGE 3 OF 17
Visit and examine the site and become thoroughly familiar with all features,
characteristics and existing conditions affecting the work.
.2
Examine the site and adjacent structures, services, process piping and utilities to be
protected and any area upon which the work of this section depends to determine the
conditions under which the work is to be done.
.3
Check all dimensions, elevations and locations of existing structures, services, process
piping and utilities at or adjacent to the site before commencing installation work, and
report all discrepancies to the Engineer.
.4
No allowances will be made by The Owner for any conditions not anticipated by the
Contractor or for any difficulties encountered due to any feature or peculiarities of the
site or of existing conditions which reasonably existed at the time of tender.
DESIGN REQUIREMENTS
.1
The micropiles shall be designed to meet the specified loading conditions, as shown on
the contract plans and approved working drawings. Design the micropiles and pile top to
footing connections using the procedures contained in the FHWA Micropile Design and
Construction, Report No. FHWA NHI-05-039.Contractor shall provide micropile design
including all materials, products, accessories, tools, equipment, services, transportation,
labour and supervision, manufacturing techniques required for design, installation and
testing of micropiles.
.2
Contractor shall select the micropile type, size, pile top attachment, installation means
and methods, estimate the ground-grout bond value and determine the required grout
bond length and final micropile diameter.
.3
The contractor shall design and install micropiles that will develop the load capacities
indicated on the plans. The micropile load capacities shall be confirmed by verification
and proof load testing as required and must meet the test acceptance criteria specified
herein.
.4
Material Specification:
.1
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02450
MICROPILE FOUNDATION
PAGE 4 OF 17
withstand the design service loadings shown on the plans and the proof/verification
tests loading described in this specification. The steel casing/pipe shall conform to
ASTM 252 or equivalent. Threaded casing joints shall develop at least the required
tensile, and/or bending strength used in the design of the micropile. The designer
will be responsible for indicating the applicable material specification(s) and any
welding or fabrication conditions that apply.
.5
.5
Structural steel plates: Structural steel plates for pile top attachments shall conform
to CAN3-G312.1 and CAN3-G312.2 or ASTM 572-Gr.50.
.6
Reinforcing bars: Reinforcing steel shall be deformed bars in accordance with CSA
G30.18. The grade, thickness and number of bars shall be indicated by the designer
and shall conform to any minimum and/or maximum properties shown on the
plans. Continuous spiral deformations (i.e. continuous thread bars) shall be used.
Bar tendon couplers, if required, shall develop the ultimate tensile strength of the
bars without evidence of any failure.
.7
Construction Method
.1
.2
The Contractor shall have previous micropile drilling and grouting experience in
soil/rock similar to project conditions. The Contractor shall submit construction
details, structural details and load test results for at least three previous successful
micropile load tests from different projects of similar scope to this project.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
SECTION 02450
MICROPILE FOUNDATION
PAGE 5 OF 17
.4
.5
At least 45 calendar days before the planned start of micropile construction, the
Contractor shall submit 5 copies of the completed project reference list and a
personnel list. The project reference list shall include a brief project description
with the owner's name and current phone number and load test reports. The
personnel list shall identify the supervising project engineer, drill rig operators,
and on-site foremen to be assigned to the project. The personnel list shall contain
a summary of each individual's experience and be complete enough for the
Engineer to determine whether each individual satisfies the required
qualifications.
.6
Work shall not start, nor materials ordered, until the Engineers written approval
of the Contractors experience qualification is given. The Engineer may suspend
work if the Contractor uses non-approved personnel. If work is suspended, the
Contractor shall be fully liable for all resulting cost and no adjustment in contract
time will result from the suspension.
.2
.3
Steel pipe used for micropile permanent casing shall incorporate an additional
1/16 thickness for sacrificial steel corrosion protection. Where required as
shown on the plans, corrosion protection of the internal steel reinforcing bars,
consisting of either encapsulation, epoxy coating, or grout, shall be provided in
accordance with the Material portion of this specification. Where the permanent
casing is used for a portion of the micropile, encapsulation shall extend at least
2m into the casing.
.4
The Contractor shall prepare and submit complete design calculations and
working drawings to the Engineer for review and approval. Submittal shall
include all information required for the design, plans, construction and quality
control of the piling. This information should include the following, but not
necessarily be limited to;
.1
Design Computations
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
SECTION 02450
MICROPILE FOUNDATION
PAGE 6 OF 17
.3
.4
.5
Safety factors/strength factors used in the design of the groundgrout bond values, surcharges, soil/rock and material unit weights,
steel, grout and concrete materials.
.6
.7
.8
.9
Plans
.1
.2
.3
.2
The offset from the construction center line or baseline to the face
of the micropile structure at all changes in horizontal alignment.
.3
.4
.5
.2
Existing and finish grade profiles both behind and in front of the
micropile structure.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02450
MICROPILE FOUNDATION
PAGE 7 OF 17
.4
.5
.6
.7
.3 Construction Procedures
.1
.2
Proposed start date and time schedule and micropile installation schedule
providing the following:
.1
Micropile number
.2
.3
.4
.5
.6
.3
.4
.5
Plan describing how surface water, drill flush, and excess waste grout
will be controlled and disposed.
.6
Certified mill test reports for the reinforcing steel and for permanent
casing. The ultimate strength, yield strength, elongation, and material
properties composition shall be included.
.7
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
SECTION 02450
MICROPILE FOUNDATION
PAGE 8 OF 17
.1
.2
.3
.4
.4
.5
Calibration reports and data for each test jack, pressure gauge
and master pressure gauge and electronic load cell to be used.
The calibration tests shall have been performed by an
independent testing laboratory, and tests shall have been
performed within 90 calendar days of the date submitted. Testing
shall not commence until the Engineer has reviewed and
accepted the jack, pressure gauge, master pressure gauge and
electronic load cell calibration data.
.6
Work shall not begin until the construction submittals have been
received, reviewed, and accepted in writing by the Engineer.
Any submittals that are found to be unacceptable by the engineer
shall be revised, resubmitted and accepted prior to commencing
work.
Pre-construction Meeting
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02450
MICROPILE FOUNDATION
PAGE 9 OF 17
.5
The Contractor shall control and properly dispose of drill flush and
construction related waste including spilled/excess grout in accordance
with related specifications within the contract documents and all
applicable codes and provincial regulations. Drill flush shall be conveyed
by pipe, hose or conduit a minimum 20ft away from the location where
the micropile is being drilled and away from any adjacent structure or
facility. Provide positive control and discharge of all surface water that
will affect construction of the micropile installation.
.2
.3
Excavation
.1
.6
.7
Coordinate the work and the excavation so the micropile structures are
safely constructed. Perform the micropile construction and related
excavation in accordance with the Plans and approved submittals.
.2
.3
.4
Micropile Installation
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02450
MICROPILE FOUNDATION
PAGE 10 OF 17
.1
The micropile Contractor shall select the drilling method, the grouting
procedure and the grouting pressure used for installation of the
micropiles. The micropile Contractor shall also determine the micropile
casing size, final drill hole diameter and bond length, and central tendon
reinforcement steel sizing necessary to develop the specified load
capacities and load testing requirements. The micropile Contractor is also
responsible for estimating the grout take. There will be no extra payment
for grout overruns.
.2
Should the plans require uncased drilling of the micropile into bedrock,
the permanent and/or temporary casing shall be drilled a minimum
200mm into ledge or to a depth within the ledge so as to prevent
subsidence of over burden into the uncased and/or bond zone portion of
the drill hole (i.e. the rock socket).
.3
The drilling equipment and methods shall be suitable for drilling through
the conditions to be encountered, without causing damage to the
overburden above rock head, any overlying or adjacent structures, buried
structures or utilities, or services. If called for in the drilling method
description, or by the nature of the stratum to be drilled through, the
micropile Contractor shall furnish an overburden casing of the type and
thickness, which can be installed without distortion. Casings that fail,
fracture, or otherwise distort during drilling or after drilling shall, unless
otherwise directed, be withdrawn or replaced at the micropile
Contractors expense. The drill hole must be open along its full length to
at least the design minimum drill hole diameter prior to placing grout and
reinforcement.
.4
.5
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02450
MICROPILE FOUNDATION
PAGE 11 OF 17
The micropile Contractor shall check pile top elevations and adjust all
installed micropiles to the planned elevations.
.8
.9
.10
Micropiles shall be grouted the same day the load transfer bond length is
drilled. The grouting equipment used shall be a colloidal grout plant, and
shall produce a grout free of lumps and undispersed cement. Paddle type
mixers are not acceptable. The micropile Contractor shall have means
and methods of measuring the grout quantity and pumping pressures
during the grouting operations. The grout pump shall be equipped with a
pressure gauge to monitor grout pressure. A second pressure gauge shall
be placed at the point of injection into the pile top. The pressure gauge
shall be capable of measuring pressures of at least 1000kPa or twice the
actual grout pressure used, whichever is greater. The grout shall be kept
in agitation prior to mixing. Grout shall be placed within one hour of
mixing.
.11
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
.12
Grout within the micropile verification and proof test piles shall attain
the minimum required 3-day compressive strength of 15 MPa prior to
load testing. During production, micropile grout shall be tested by the
Contractor for compressive strength at a frequency of not less than one
set of three 50mm grout cubes, or 75mm cylinders, per every 10 piles,
whichever occurs more frequently. The compressive strength shall be the
average of the 3 cubes tested.
.13
.14
.9
SECTION 02450
MICROPILE FOUNDATION
PAGE 12 OF 17
The micropile Contractor shall prepare and submit to the Engineer fulllength installation records for each micropile installed. The records shall
be submitted within one work shift after that pile installation is
completed. The data shall be recorded on a micropile installation log. A
separate log shall be provided for each micropile.
.2
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02450
MICROPILE FOUNDATION
PAGE 13 OF 17
.5
.6
.7
.8
.9
.10
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02450
MICROPILE FOUNDATION
PAGE 14 OF 17
and 60 minutes. The alignment load shall not exceed ten percent
of the DL load. Dial gauges shall be reset to zero after the initial
AL is applied.
Loading
Apply AL
Cycle 1
Cycle 2
Cycle 3
Cycle 4
.11
Applied Load
0.15 DL
0.30 DL
0.45 DL
AL
0.15 DL
0.45 DL
0.60 DL
0.75 DL
0.90DL
1.00DL
AL
0.15DL
1.00 DL
1.15 DL
1.30 DL
1.45 DL
AL
0.15DL
1.45 DL
1.60 DL
1.75 DL
1.90 DL
2.00 DL
1.50DL
1.00DL
0.50DL
AL
.2
At the end of the 1.30 DL creep test load increment, test piles
shall have a creep rate not exceeding 1.0 mm/log cycle time
(1 to 10 minutes) or 2.0 mm/log cycle time (6 to 60minutes or
the last log cycle if held longer). The creep rate shall be linear
or decreasing throughout the creep load hold period.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.12
.3
SECTION 02450
MICROPILE FOUNDATION
PAGE 15 OF 17
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
SECTION 02450
MICROPILE FOUNDATION
PAGE 16 OF 17
.2
.3
Step
1
2
Loading
Apply AL
Load Cycle
Unload cycle
.5
Applied Load
0.15 DL
0.30 DL
0.45 DL
0.60 DL
0.75 DL
0.90 DL
1.00 DL
1.15 DL
1.30 DL
1.45 DL
1.60 DL
1.30 DL
1.00 DL
0.75 DL
0.50 DL
0.25 DL
AL
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02450
MICROPILE FOUNDATION
PAGE 17 OF 17
.2
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SCOPE OF WORK
SECTION 02455
CONTACT GROUTING
PAGE 1 OF 12
.1
This Section specifies the provisions, requirements, procedures and materials for the
contact grouting which shall be performed to fill all voids behind the pipes installed by
pipe jacking and the excavated surface and behind the precast concrete segmental lining
when voids are found as described in Section 02430.
.2
This Section also specifies grout materials, grout mixes, grouting criteria, maximum
grout hole spacing and the water inflow criteria and performance.
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
1.3
DEFINITIONS
.1
.2
.3
Refusal for contact grouting: If less than 0.057 cubic meters of grout is injected in 2
minutes at maximum allowable pressure, the connection is considered grouted to refusal.
.4
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
1.4
SECTION 02455
CONTACT GROUTING
PAGE 2 OF 12
Water to Cement Ratio: The ratio, as measured by volume, of water to cement in the
grout mix.
DESIGN CRITERIA
.1
1.5
Contact Grouting:
.1
.2
Additional contact grouting will also be permed in specific areas where voids
may occur, protect fresh concrete from flow of water during placement of the
concrete lining.
.3
.4
PERFORMANCE REQUIREMENTS
.1
1.6
Contact grouting: Ensure continuous contact between the tunnel lining and the
surrounding ground. This includes contact grouting of overbreak areas, filling of
panning, drains and any embedded pipes within the tunnel or shafts.
SUBMITTALS
.1
.2
General:
.1
.2
Integrate submittals specified herein with those specified for Section 02430,
Tunnel Excavation by Tunnel Boring Machine (TBM), Section 02440, Pipe
Jacking, and Section 03420, Precast Concrete Tunnel Lining.
Product Data:
.1
Submit cement grout materials information as specified in Section 03300, Castin-Place Concrete (Shafts and Underground Structures) including required
information for cement, sand, water, and admixtures.
.2
Copies of the Material Safety Data Sheets (MSDS) for grout materials shall be
submitted to the CM for information.
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
1.7
SECTION 02455
CONTACT GROUTING
PAGE 3 OF 12
.2
Equipment, methods and means of accurately measuring grout pressure and rate
of grout injection.
.3
.4
.5
.6
Grouting sequence and criteria and threshold values for modifying mixes.
Mix design data, including all mix components and test results to meet minimum
requirements specified herein.
.2
Initial and final set times for proposed mixes for the range of water/cement ratios
specified herein.
QUALITY CONTROL
.1
Qualifications:
.1
.2
Certifications:
.1
.2
.3
.4
.5
.6
.3
.4
Recordkeeping:
.1
For contact grouting, submit records of strength test results on grout cylinders.
.2
Logs for each shift for each type of grout hole drilling including:
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
1.8
SECTION 02455
CONTACT GROUTING
PAGE 4 OF 12
.3
.4
.5
.6
.7
.8
.9
Grouting Record:
.1
.2
.3
.4
.5
.6
.7
.8
QUALITY ASSURANCE
.1
Reference Standards:
.1
.2
.1
.2
Qualifications:
.1
.2
.3
Preconstruction Meeting:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.9
SECTION 02455
CONTACT GROUTING
PAGE 5 OF 12
.2
.3
.4
.5
Grouting records.
Drill and perform contact grouting after the concrete has reached the specified 28-day
design compressive strength.
.2
.3
Carry out a sounding effort using a five pound hammer, as directed by the City
Representative, on the backfilled and contact grouted lining to check for localized voids
due to trapped air during placement of the lining backfill between the lining external
surface and the backfill. The sounding and skin grouting shall be carried out after contact
grouting of the lining is complete.
1.10
Transport, store, and handle grouting materials in the manner prescribed by the
manufacturers of each product.
.2
.3
Cement:
.4
1.11
.1
.2
.3
.4
Cement shall be free from foreign matter and lumps. If cement is found to
contain lumps or foreign matter of a nature and in amounts deleterious to the
grouting operations, it shall not be used and shall be disposed of in a manner
satisfactory to the City Representative.
.5
If bulk cement is used, accurate devices shall be used to measure the quantity of
cement delivered and utilized.
Post legible copies of MSDS and warnings as appropriate at all locations where
potentially hazardous grout materials are stored or handled. Copies of the MSDS shall be
submitted to the CM for information.
MEASUREMENT AND PAYMENT
.1
The Contractor shall include costs for all labour, equipment, materials and incidentals
within the appropriate unit price or lump sum items included in Section 01025,
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02455
CONTACT GROUTING
PAGE 6 OF 12
Measurement and Payment for all work required to execute contact grouting as specified
herein and no separate payment shall be made.
Part 2
PRODUCTS
2.1
MATERIALS
.1
.2
.3
.4
.5
General:
.1
.2
All materials used shall meet the requirements of Section 03300, Cast-in-Place
Concrete (Shafts and Underground Structures) except as modified herein.
.3
All grouting materials for contact grouting shall meet ANSI/NSF 61 potable
water standards requirements once they have fully cured and hardened.
Cement:
.1
.2
Contact, pressure, and skin grouting shall use Type III cement.
Admixtures:
.1
.2
.3
.4
Water:
.1
Water used for all grout mixes shall meet the requirements of Section 03300,
Cast-in-Place Concrete (Shafts and Underground Structures).
.2
The temperature of the water at the time of mixing shall be less than 25 degree
Celsius.
Miscellaneous Materials:
.1
Caulking materials shall be kept available for use at all times during the
performance of grouting operations. These materials shall include oakum,
wooden wedges and burlap.
.2
Non-shrink grout for plugging contact and pressure grout holes after the
completion of grout injection through concrete linings shall conform to the
requirements of Section 03300, Cast-in-Place Concrete (Shafts and Underground
Structures).
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.2
SECTION 02455
CONTACT GROUTING
PAGE 7 OF 12
EQUIPMENT
.1
Drilling Equipment:
.1
.2
.3
.4
.2
.3
.4
Provide a means for increasing or decreasing the water/cement ratio at the mixer
as indicated by the field conditions.
.5
Provide a separate agitator serving as a holding tank between the mixer and the
pump that allows continuous pumping.
.6
Equip agitators with baffles to induce turbulence and rotating paddles that will
promote thorough mixing of the grout at all times prior to and during injection.
Provide a water connection on the grout pump to facilitate flushing the system
and injection of water into the grout holes.
.2
Pumps used for contact grouting shall have a maximum pressure capacity of
1.5 MPa and consist of a helical screw rotor-type (Moyno pump) that produces
uniform flow without pulsation.
.3
Appurtenances:
.1
.2
.5
Drilling equipment for contact and pressure grouting shall be selected to suit
proposed methods, and the objectives of grouting specified herein.
Packers:
.1
Packers shall be capable of tightly sealing the grout holes at the selected
locations and depths, such that grouting can be done at grout pressures
equal to the maximum pressure used in the hole without leakage. Packers
shall be designed prevent hydrostatic head build up during placement
and seating of the packers. Packers shall be equipped with shutoff
valves.
.2
Grout pipe to and through the packer shall have a minimum inside
diameter of 38mm.
Instrumentation:
.1
Pressure Gauges:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.1
Pressure gauges shall be accurate within 5kPa for the entire range of
injection pressures, and shall be provided with appropriate gauge savers.
.2
Pressure gauges shall be installed both at the collar of the hole and at the
pump.
.3
.4
.3
2.3
Flowmeters:
.1
.6
SECTION 02455
CONTACT GROUTING
PAGE 8 OF 12
Piping:
.1
Locate a manifold consisting of a system of valves and pressure gauge in the line
at the collar of the hole to permit continuous circulation, accurate control and
monitoring of grouting pressure, bleeding, and regulation of flow.
.2
The arrangement of manifold, hoses and pipes used shall allow for reliable
recording of injected quantities of grout in each connection.
.3
Size:
.1
.2
.3
Embedded grout and vent pipes for contact grouting shall have a
minimum internal diameter of 25 mm.
MIXES
.1
Cementitious grout mixes shall be developed by the Contractor and shall be subject to
review and approval by the City Representative prior to commencement of grouting.
Part 3
EXECUTION
3.1
GENERAL
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02455
CONTACT GROUTING
PAGE 9 OF 12
.2
All grouting shall be performed with a pressure regulator and a grout return line to avoid
damage to the final lining.
.3
Do not perform any contact grouting until the cast-in-place concrete, reinforced concrete
pipe backfill, or precast concrete tunnel lining backfill has achieved the specified 28-day
strength and essentially completed shrinkage of the concrete material.
.4
All voids between the final lining and the rock surface shall be completely filled with
concrete, concrete backfill, or cement grout.
.5
Proceed from one end of the tunnel to the other end of the tunnel. Skipping
areas to return subsequently will not be allowed.
.2
Proceed from lower to higher holes, both in regard to location on the lining
circumference, and in regard to tunnel invert gradient.
.6
Discharge water from grouting operations shall be collected, treated and disposed of in
accordance with Section 01355, Waste Management and Disposal and Section 02140,
Groundwater Control.
.7
Do not perform grouting without the appropriate pressure gauges and flowmeters in
place and in working order.
.8
Any grout hole that becomes plugged or obstructed before grouting shall be reopened,
redrilled, downstaged, or plugged with grout and abandoned.
.9
Maintain equipment used for mixing and injection of grout in satisfactory operating
condition at all times. Keep equipment and lines clean by constant circulation of grout
and by periodic flushing.
.10
All grout holes through the cast-in-place concrete lining shall, on completion of contact
or pressure grouting, be filled by drypacking non-shrink grout into the holes.
.11
Promptly clean the tunnel of spills, deposits of grout and other debris. Do not permit
more than 2 calendar days' accumulation of trash, debris and deposits in the tunnel.
.12
All contact grouting penetrations/holes shall be provided with threaded pipe plugs, seal
welded, and ground flush with the steel lining internal surface prior to the field
application 'of the cement mortar lining.
3.2
PREPARATION
.1
.2
Drill or clean out each contact grout hole from the inside pipe face to the face of the rock
surface:
.1
Using a drill equipped with a bit of the same nominal diameter as that for holes
to be grouted.
.2
Affix a valve to each hole which has been cleaned and open all valves.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.3
SECTION 02455
CONTACT GROUTING
PAGE 10 OF 12
CONTACT GROUTING
.1
General:
.1
For the tunnel crown, perform contact grouting through the jacking pipes
systematically between the concrete lining and the surrounding ground.
.2
.3
Relieve air and groundwater through the valved, open, ungrouted holes adjacent
to the hole being grouted to the extent possible. Grout holes from lowest point in
tunnel to highest point.
.4
Do not close any valved, open, ungrouted hole until grout of the same
consistency as that being injected issues forth.
.5
Grout each hole until communication with adjacent holes is observed, or until
refusal is reached. Grout procedure consists of: hook up to each valve; begin
pumping; observe communication from adjacent holes; shut off valve when grout
of the same consistency issues forth; and move to the adjacent hole.
.6
.7
Remove grout valves and permanently install grout hole pipe plugs after the
grout has reached initial set.
.8
For all excavations and lined areas, panning and embedded drain materials and
pipes shall be contact grouted as shown on the Contract Drawings.
.9
Contact grout holes shall be located and staggered as shown on the Contract
Drawings. Place additional holes as necessary.
.10
.11
Provide grout pipes, packers, and drain pipes at locations as specified on the
Contract Drawings, approved working drawings, and as determined necessary by
the Engineer in the field in regard to contact grouting of panning and other
groundwater handling installations.
.12
.13
.14
All contact grouting shall proceed from connections beginning at the lowest
point in a continuous, up-gradient direction. Skip and leap operation along the
tunnel alignment will not be permitted. For each connection, anticipated vent
holes will be identified prior to commencement of grouting, and continuously
observed as grouting proceeds.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.3
.4
SECTION 02455
CONTACT GROUTING
PAGE 11 OF 12
Grout Holes:
.1
If grout holes are drilled, do not drill through cast-in-place lining until the
concrete has cured for at least 7 days or has reached a minimum compressive
strength of 20 MPa.
.2
Drill holes for contact grouting and venting, excluding those for panning and
invert drains, through the concrete lining and any localized voids a minimum of
50 mm into rock.
.3
Vent holes for contact grouting of overbreak areas shall be located in known
high points in the specific area to be grouted. Verify the escape of air/water and
grout from the vent holes during grouting.
.4
Contact grouting vent holes shall be drilled a minimum of 50 mm into rock and a
grout packer installed into each vent hole. The packer shall extend to within
25 mm of the end of the hole. Verify the escape of air and grout from the vent
holes. Once grout issues from the vent hole, the packer shall be closed off and
subsequently used as a grout hole as the grouting operation proceeds towards the
vent hole.
.5
Install grout holes and vent holes for grouting of the panning material and invert
drain as shown on the Contract Drawings. The spacing of the holes shall be
adequate to ensure that all voids are filled, including the invert drain pipe and
surrounding crushed rock, and that the final linings are in contact with rock
around its entire circumference. In areas of continuous panning, spacing of grout
and vent holes shall not exceed 3 m of tunnel length. The Contractor may modify
the hole spacing for contact grouting of panning upon approval of the Engineer.
.6
The diameter of each grout hole shall not be less than 38 mm and shall be
compatible with vent pipes specified in Part 2 - Products of this Section.
.7
Drill grout holes through concrete and rock, avoiding damage to permanent
lining components such as reinforcing steel and threaded fittings in steel lining,
where present.
.8
Remove temporary plugs in vent pipes and grout holes, and estimate the void gap
for each grout and vent hole.
Grouting:
.1
The maximum pressure at the point of injection shall not exceed 0.3MPa for
contact grouting unless otherwise approved by the Engineer.
.2
Leave adjacent grout holes open during grouting operations to facilitate the
escape of air and water from pockets in the space surrounding the tunnel lining.
Where grout is found to flow from adjacent grout connections in sufficient
quantity to seriously interfere with the grouting operations or to cause
appreciable loss of grout, valves on such connections may be temporarily closed,
and intermittently opened for bleeding and subsequent grout connection.
.3
Completion of Grouting:
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.4
SECTION 02455
CONTACT GROUTING
PAGE 12 OF 12
.1
Upon completion of grouting at each connection, close the shut-in valve and
leave it in place until the grout has set.
.2
Fill all open grout and vent holes with non-shrink grout at completion of the
grouting operations to within 150 mm of the tunnel lining surface and dry pack
the remainder of the hole with sand and cement to have a smooth finished
surface.
Data or notes taken by the City Representative during periodic inspections of grouting
will not relieve the Contractor's responsibility in documenting grouting operations.
.2
Contact Grouting - Test three cylinders for every 10 m3 of grout placed according to
Section 03300, Cast-in-Place Concrete (Shafts and Underground Structures). Minimum
cylinder diameter shall be 75 mm. Tests performed on grout cubes or prisms shall not be
accepted for verifying strength.
.3
.4
3.5
.1
.2
Ensure that grouting is performed from bottom upwards, and continuously in all
aspects.
.3
.4
.5
.6
.7
.8
Closure criteria and/or refusal criteria are satisfied prior to terminating grouting
of each hole.
Perform testing of all field gauges and meters no less often than weekly using
master gauges and meters.
.2
.3
Verify accuracy of master gauges and meters through the use of a test laboratory
no less frequently than every two months.
CLEAN-UP
.1
No buildup of wasted or leaked grout shall be allowed in the lined facilities at any time.
.2
If leakage of grout or other foreign material occurs, remove and dispose of such material
by washing or other suitable means.
.3
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
PART 1
GENERAL
1.1
SUMMARY
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 1 OF 26
.1
.2
.3
Related Sections:
.4
.1
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
.15
Definitions:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 2 OF 26
.3
.4
.5
.6
.7
Soil Deformation Monitoring Point: A capped steel pipe driven into the ground
that is used for monitoring vertical deformation (settlement or heave) of the soil at
or near the ground surface.
.8
Pavement Monitoring Point: A PK nail driven into a pavement surface that is used
for monitoring vertical deformation (settlement or heave) of the pavement at the
ground surface.
.9
.10
.11
.12
.13
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 3 OF 26
.14
Monitoring Bolts: Bolts installed into precast tunnel lining segments used to
measure deformations of the precast concrete tunnel lining, with measurements
made by optical survey methods.
.15
.16
.17
.18
Table 1- Threshold Value, Contractors Response Value, and Maximum Allowable Movement Levels
Type of Instrumentation
(movement direction)
Soil Deformation
Monitoring Points,
Pavement Monitoring
Points, (vertical)
Survey Reference Points,
Reflectorless Points,
Reflective Tape, Optical
Survey Targets (vertical)
Survey Reference Point,
Reflective Tape, Optical
Survey Targets(horizontal)
Multiple Point Borehole
Extensometer (vertical)
Threshold
Value
(Contractor
Action
Required)
12 mm
Contractor
Response
Value
Shutdown
Value
20 mm
25 mm
12 mm
20 mm
25 mm
12 mm
20 mm
25 mm
12 mm
20 mm
25 mm
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Type of Instrumentation
(movement direction)
Piezometers (groundwater
level drawdown below
lowest groundwater table
elevation shown in GBR
applies to piezometers with
tip elevations within 5
metres of bedrock surface)
Utility Monitoring Points
(vertical)
Tiltmeters (Inclination)
Inclinometer (horizontal)
Tape Extensometer
(convergence as a percent of
initial length)
Movement at Top of
Shoring
Tunnel Lining Movement at
Tunnel Eyes and Portals
.1
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 4 OF 26
Threshold
Value
(Contractor
Action
Required)
1m
Contractor
Response
Value
Shutdown
Value
1.6m
2m
12 mm
20 mm
25 mm
0.055 degrees
0.090 degrees
12 mm
0.1%
20 mm
0.16%
0.110
degrees
25 mm
0.2%
12 mm
20 mm
25 mm
12 mm
20 mm
25 mm
Tolerances:
.1
.2
.3
.4
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 5 OF 26
.2
When the Threshold Value is reached for any monitored instrument, the
Contractor shall meet with the Contract Administrator to discuss construction
means and methods to determine what changes, if any, shall be made to better
control ground movement or groundwater levels. When the threshold value is
reached, the frequency of readings for any affected instruments shall be double the
frequency stated in Table 2 or Table 3, whichever is applicable, or as otherwise
directed by the Contract Administrator. The increased frequency of reading shall
be maintained until readings made during five consecutive working days are
below the Threshold Value for the instrument(s) in question or reading values
have stabilized as determined by the Contract Administrator.
.3
.4
When the Shutdown Value is reached, the Contract Administrator may direct the
Contractor to stop all work immediately, and the Contractor must meet with the
Contract Administrator to develop a plan of action before work can be resumed.
Implementation of the approved Contingency Plan must commence immediately
and continue for as long as necessary as determined by the Contract
Administrator. No standby time will be paid if work is shut down because a
Shutdown Value is reached. Instrumentation reading frequency shall be
maintained at the increased frequency implemented as a result of readings
previously reaching either the Threshold and Response Values. The increased
frequency of reading shall be maintained until readings made during five
consecutive working days are below the Threshold Value for the instrument(s) in
question or reading values have stabilized as determined by the Contract
Administrator
.5
SUBMITTALS
1.2
.1
General:
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 6 OF 26
.2
.3
.4
.1
.2
.3
Develop and submit instrumentation plans for Taberet Hall and the areas designated on
north Cumberland Street, for the general areas as indicated on plans. Contractors plans
must meet the following requirements:
.1
Contractor must monitor each property under which the tunnel will pass
within the general areas as shown on the Drawings. Locations of required
structures to be monitored are identified by structure address in Appendix B of
this Section. See Section 02482 for additional vibration and noise monitoring
requirements to be included in the Contractor developed instrumentation
plans. Submittals for instrumentation in Contractor developed areas shall
include noise and vibration monitoring plans.
.2
.3
.5
If tilt meters are not used, monitoring points shall be placed in sufficient
quantities to estimate tilt on at least two walls on each of two stories of
the structure, in cases where structures are two stories or taller. At a
minimum, monitoring points shall be placed at intervals of no less than
10 m along each wall being monitored.
.4
.5
Negotiation Records:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
.7
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 7 OF 26
.2
.3
As-Built Data:
.1
.2
.3
.4
Contingency Plan
.1
.2
.8
Mix Designs: Materials, admixtures, other additives, and grout mix design required for
inclinometer installation. Provide manufacturers product descriptions for all admixtures
and additives.
.9
Drill Logs.
.1
.10
Detailed boring logs describing soils and rock encountered, depths of strata tops
and bottoms, drilling rates, recovery, and details of instrument installations.
Drilling activities shall be supervised and boring logs recorded by a qualified
geologist or soils engineer experienced with the specific types of earth materials to
be encountered. Drafted logs shall be prepared and submitted for approval. Field
logs shall not be an acceptable submittal.
A daily report including a summary of all monitoring data collected the previous day.
Provide the data electronically and with a hard copy in a format acceptable to the
Contract Administrator.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.11
.12
.13
.14
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 8 OF 26
Instrumentation Installation and Quality Plan: Describe how the quality of materials
required for installation of each instrument and the installation process will be
controlled (e.g. measurements, inspections, testing, etc.) in accordance with Section
01450 Quality Control. In addition, provide:
.1
.2
.3
Proposed format for presenting raw data readings. Include the date, time, and
name of personnel taking measurements or performing monitoring.
.4
.5
.2
.3
.4
Calibration certificates by manufacturer for each sensor, probe, readout device and
data logger.
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.3
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 9 OF 26
QUALITY CONTROL
.1
Testing: Calibrate all sensors and readout instruments at the manufacturers facility
prior to shipment.
.2
Notifications:
1.4
.1
.2
.3
.4
Immediately for any reading exceeding the Threshold Value Levels specified in
Table 1 when excavation is taking place within 150 m in plan of the designated
instrumentation location.
.5
REFERENCES
.1
Standards:
.1
1.5
ASTM A53, Standard Specification for Pipe. Steel, Black and Hot Dipped
Zinc-Coated (Galvanized), Welded and Seamless.
.2
.3
.4
.2
.3
JOB CONDITIONS
.1
The anticipated ground conditions are set forth in the Geotechnical Baseline Report
(GBR).
.2
Refer to the Geotechnical Data Report (GDR) for locations and details of piezometers
previously installed for this Contract.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.6
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 10 OF 26
1.7
.1
1.8
.1
.2
PART 2
PRODUCTS
2.1
GENERAL
.1
Ensure that all instrumentation components are on hand and approved by the Contract
Administrator before excavation begins.
.2
For each instrument type, provide all instruments and necessary components, including
readout devices, from the same manufacturer.
.3
.4
2.2
.1
.2
.3
Slope Indicator Co., 12123 Harbour Reach Drive, Suite 106, Mukilteo, WA
98275.
.4
.5
RST Instruments LTD., 200-2050 Hartley Av.enue, Coquitlam, BC, Canada V3K
6W5.
.6
Or approved equals.
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 11 OF 26
Inclinometer System, Geokon Inc. Model MP-20; Roctest Ltd. Model Accutilt; or
equal probes. Provide a carrying case for each probe.
.2
Cable: Combination signal and suspension cable. Cable with a steel or Kevlar core,
heavy-duty, waterproof jacket and external markings spaced at 300 mm intervals.
Cable 60 m long and furnished with one pulley assembly suitable for mounting on
the inclinometer casing. Use Slope Indicator Co. Digitilt Control Cable or equal.
.3
Portable Data Logger: Pocket PC-based logger with Bluetooth data link to cable
reel, powered by rechargeable internal batteries. Use Slope Indicator Co. Digitilt
Datamate Readout (Part No. 50310900); RST Inclinometer Pocket PC Logger,
Roctest Ltd. Model Accutilt-SA, or equal.
.4
Casing:
.1
.2
Casing sections: No less than 3m lengths, with no section having more than
one degree of spiral before installation.
.3
Couplings, locking devices and caps: Sizes and types recommended by the casing
manufacturer.
.4
Cement Grout: Use cement grout that conforms to the recommendations of the
inclinometer manufacturer.
.5
Casing Protectors: Provide a square steel stick-up cover where possible to improve
accessibility or a traffic-rated 305 mm ID flush cover with steel bolt down cover as
specified herein at each inclinometer installation.
.6
Twist survey apparatus: A groove alignment tool attached to orientation rods and a
protractor fitted to the assembly, to measure the angular rotation of the grooves with
depth.
.7
2.3
TILTMETERS
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.4
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 12 OF 26
.2
Provide rod type extensometers similar in design to one of the following models, or
approved equal.
.1
Model No. 517043, Slope Indicator Co for stainless steel rods and protective pipe.
Other components to be approved by Engineer.
.2
.3
.3
An extensometer with electrical sensors equipped with a remote monitoring system will
be allowed.
.4
Provide sufficient numbers of multiple point borehole extensometers and readout devices
to ensure the constant availability of functioning units on the site in case of loss or failure
of primary units. Working back up units shall be available on site at all times.
.5
.6
2.5
.1
The range of each anchor shall cover 50mm for heave measurements and 150 mm
for settlement measurements.
.2
Grout subsurface anchor points and the entire subsurface assembly with an
approved grout mix.
.3
.4
Provide a traffic rated bolt-down cover of size indicated, with a protective cap for the
extensometer reference head as recommended by the instrument manufacturer.
PAVEMENT MONITORING POINTS (PMP) AND MONITORING POINT
ARRAYS (MPA)
.1
PMPs will be used to monitor deformation at the ground surface or pavement surface.
All points shall be clearly identified with permanent easily readable letters and numbers.
.2
2.6
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.7
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 13 OF 26
Use black steel pipe and threaded couplings, ASTM A53, welded, standard weight,
for inner bench marks monitoring pipes and outer casing.
.2
Provide monitoring pipes and casing of lengths required for each monitoring
location as shown on the Drawings.
.3
.4
Use centering devices for placement between the inner benchmark and outer casing
that is suitable for use in deep settlement markers.
2.8
Provide vibrating wire components that are from the same manufacturer.
.2
Use a vibrating wire piezometer appropriate for pressures up to 690 kPa with a cable
length that will extend 1.5m above the ground surface after installation. Use Geokon
Model 4500-S, Slope Indicator Co. Part No. 52611034 or 52611035, RST
Instruments Model VW2100, or equal
.3
.4
2.9
REFLECTIVE TAPE
.1
Reflective tape to be compatible with the survey equipment used and capable of
providing measurements within the specified tolerances.
.2
Provide reflective tape similar in design to Leica Geosystems GZM30 Reflective Tape,
or equal.
2.10
Surveyors prisms or reflectors compatible with the survey equipment used and
capable of providing measurements within the specified tolerances.
.2
.3
Provide GHT112 Mounting Set for optical survey target, or approved equal. Mounting
set to be installed using manufacturers instructions.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.11
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 14 OF 26
Furnish monuments with access cover and install flush with the ground surface to
protect installed inclinometer casings, and piezometers. Use steel of sufficient
strength to withstand H-20 and HS-20 truck loadings. Provide a watertight access
cover. Use casings with diameters as shown on the Drawings.
.2
Set monuments in place with concrete with 150 mm annular thickness around the
monument.
.3
Inside each monument, install a hardened domed head nail embedded into concrete to
serve as a leveling point.
.4
2.12
.2
The Contractor shall choose suitable positions of the Automatic Total Stations as shown
on the Contract Drawings or as subject to the agreement of the Contract Administrator.
.3
Automatic total stations shall be robust and weather resistant, and be capable of
operating to the specified accuracy in all weather conditions. ATS shall be suitably
mounted on a secure foundation or purpose built bracket. The mounting shall be
birdproof and vandal and theft proof.
.4
The position of the reference prisms are to be selected by the Contractor. Where
reference points are within the zone of influence the data processing software shall
recalculate the position of these points based on survey by other ATS to allow correct
calculation of the position of all total stations using those reference points. The
Contractor shall propose the number and position of reference points outside the zone of
influence subject to the agreement of the Contract Administrator.
.5
During the monitoring period, one spare ATS shall be maintained on site for use as an
emergency replacement for damaged or malfunctioning equipment, and a second shall be
maintained as cover for machines removed for planned maintenance. The Contractor
shall allow for replacement setups, including calibration at no additional cost to the City.
.6
2.13
MONITORING BOLTS
.1
Monitoring Bolt with a fine threaded end (with cap for tread protection) for attachment
to a optical survey target or prism as approved by Contract Administrator.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.14
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 15 OF 26
Provide permanent convergence points made of stainless steel, compatible with the
tape extensometer manufacturers recommendations and suitable for the type of
initial support system installed. Use of one of the following models, or approved
equal.
.1
.2
.3
.2
Number of anchors (per location) as indicated on the Drawings and as directed by the
Contract Administrator.
.3
Use groutable eyebolt anchors for rigid attachment of convergence points to the
initial tunnel support, e.g. steel sets, or rock surfaces, as approved by Contract
Administrator. All convergence monitoring anchors shall be installed to be protected
from damage throughout the monitoring period.
.4
Provide a tape extensometer with minimum 20m survey tape from one of the
following models, or approved equal.
.1
.2
.3
PART 3
EXECUTION
3.1
GENERAL
.1
.2
3.2
PREPARATION
.1
Instrument locations in areas not otherwise prepared as part of the work at each site
shall be prepared, cleared, and stripped in accordance with Section 02200 Site
Preperation and Section 02231 Clearing and Grubbing.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.3
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 16 OF 26
INSTALLATION
.1
General:
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 17 OF 26
.2
.2
Furnish and install survey reference points as specified herein and as approved by
the Contract Administrator prior to installation of any instrumentation.
Tiltmeters
.1
.4
Inspect and log any drilled hole for instrument installation in accordance with
the associated ASTM standards. Confirm the ground conditions are compatible
with proposed installation.
.3
Negotiate and place tiltmeters on every property west of Elgin Street on the
EWT alignment and every property north of Slater on the North-South
tunnel alignment.
.2
Negotiate and place tiltmeters on every other property east of Elgin Street
on the East-West Tunnel alignment and every other property south of Slater
on the NST alignment.
.3
.2
For optional properties, confirm properties chosen for negotiation for placement
of instrumentation with Contract Administrator prior to beginning negotiations
with property owner. Tiltmeters shall be installed and initial readings shall be
taken prior to commencement of excavation. Tiltmeters shall be installed in
accordance with the manufacturers recommendations. Tiltmeters shall be nulled
in accordance with the manufacturers recommendations and using manufacturer
supplied nulling devices. Readings shall be made in accordance with
manufacturers instructions using the manufacturers recommended data loggers.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.5
Pavement Deformation Monitoring Point (PMP) and Monitoring Point Arrays (MPA)
.1
.6
.7
.8
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 18 OF 26
.2
.2
.3
Backfill with sand-cement grout using the tremie method to fill the hole from the
bottom.
.4
.2
.3
.9
Optical Survey Targets: Securely attach to the ends of steel bars or other steel members
by welding or bolting.
.10
For each building from Appendix A that is instrumented with a tiltmeter, install at
least two reflective tape targets.
.2
Install reflective tape targets on the structure wall facing the tunnel alignment.
Locations of reflective tape targets are to be approved by Contract Administrator
before installation.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.11
.12
.13
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 19 OF 26
The total station shall reference stable points (prisms) outside the zone of
influence and the system configured to self-correct for any movement of the total
station. It is the Contractors responsibility to select locations for stable points
and install these points in accordance with manufacturer recommendations.
Submit proposed locations to the Contract Administrator for review as a submittal
prior to installation.
Inclinometers
.1
.2
.3
.4
Assure sufficient anchoring of the bolts to avoid loosening of the bolts over the
entire construction period. Install bolts in predrilled holes bonded with epoxy
resin.
.2
Convergence Points:
.1
.2
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.4
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 20 OF 26
.5
.6
After installation, survey the location of each instrument or its marker point to a
horizontal accuracy of 3 mm and elevation accuracy of 3 mm. Submit location
information to the Contract Administrator.
.2
.3
Initial readings for each instrument shall be submitted within 1 working day of taking
readings.
3.5
MONITORING
.1
General: The Contractor shall monitor all instruments during construction. Upon
request, provide such cooperation, assistance, labour and equipment necessary to
allow the Contract Administrator to monitor instruments.
.1
.2
.2
.3
.3
.4
.5
Monitoring frequency:
.1
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 21 OF 26
.3
Monitor piezometers adjacent to shafts continuously during shaft draw down for
shafts excavated in the wet.
.4
.5
After tunnel face is greater than 90m from reflectorless point locations,
reflectoress point locations shall be replaced with a single MPA and shall be
monitored twice monthly until completion of construction.
.6
.7
.1
Daily during slope excavation and stabilization and for 30 days after slope
is stabilized.
.2
Weekly from 30 days after slope is stabilized until tunneling operations are
within 90m south of slope face.
.3
Daily while tunneling operations are within 90 m from slope face until
completion of all site 6 structures.
When the NST tunnel face reaches 90m south of Wellington Street, monitoring
frequency of all instruments north of Wellington Street shall be increased to every
6 hours. When the tunnel face reaches 30m south of Wellington Street, monitoring
frequency of all instruments north of Wellington Street shall be increased to every
3 hours until the excavated tunnel face reaches the portal at Site 6.
Table 2 - Monitoring Frequency of Equipment along Tunnel Alignments
d*
(m)
SDMP,
PMP,
Piezometers
Multiple Point
Borehole
Extensometers
Utility
Monitoring
Points
Inclinometers
Reflectorless
Points
daily
Tiltmeters
and
Reflective
Tape
daily
-30 to
0
daily
daily
daily
daily
continuously
0 to
30
daily
daily
daily
daily
daily
daily
continuously
30 to
90
twice
weekly
twice weekly
twice weekly
twice weekly
twice
weekly
twice weekly
continuously
>90
twice
monthl
twice
monthly
twice monthly
twice
monthly
twice
monthly
twice monthly
twice monthly
Note: d* is measured along longitudinal plan tunnel centerline. - 30 denotes 30 m ahead of the tunnel face. 90 denotes 90 m behind the
excavated tunnel face.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 22 OF 26
Daily
Weekly
Daily
Weekly
Inclinometers and
Piezometers
Daily
Weekly
Daily
Weekly
3.6
Protect and maintain instruments throughout the duration of monitoring. Drain water
or flush debris from under monument covers. Keep monument covers secured.
.2
.3
.4
.5
If any instruments are damaged that are deemed by the City to be critical, the
Contractor shall cease Work until the damaged instrument is replaced and readings
re-established. The Contractor will not be entitled to additional time or
compensation resulting from this delay or the cost of materials, labour or equipment
to install the replacement.
.6
For replacement instrumentation, take initial readings and correlate with previous
readings.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.7
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 23 OF 26
REMOVAL
.1
3.8
Removal:
.1
.2
.3
.4
Backfill grout holes with grout mix as required by applicable laws or regulations or as
approved by the applicable regulating agency and restore surfaces to conditions
existing before installation.
.5
Fill holes drilled in masonry or concrete surfaces with cement mortar to present an
appearance matching the surrounding surface.
.6
.2
Products: Submit verification that the installed products are authentic (delivery receipts,
bills of lading, etc.).
.3
Execution: Submit verification that the work was installed correctly (inspection records,
as-built drawings, etc.).
.4
.1
.2
The Contractor shall be responsible for the performance of all inspections and
testing.
.2
The Contractor shall provide free access to the Contract Administrator upon
request for additional inspection and testing.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 24 OF 26
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.
98.
99.
Site 6 to 10
100. 301 Wellington St (Supreme Court
of Canada Southeast Corner)
Instrumentation Required
101. Parliament Hill (Supreme Court of
Canada Parking Garage Northeast
Corner) - Instrumentation Required
102. Parliament Hill (Supreme Court of
Canada Parking Garage Southeast
Corner) Instrumentation Required
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
155.
156.
157.
158.
159.
160.
161.
162.
163.
164.
165.
166.
167.
168.
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 25 OF 26
169.
170.
171.
172.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02480
GEOTECHNICAL AND STRUCTURAL
INSTRUMENTATION AND MONITORING
PAGE 26 OF 26
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
PART 1
PART 1- GENERAL
1.1
SUMMARY
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 1 OF 13
.1
This section provides general noise and vibration control and monitoring requirements for
the project. It also specifies monitoring and protection requirements specific to the 1220mm
water main on Chamberlain Avenue.
.2
.3
.4
.5
.1
.2
.3
.4
.5
.6
.7
.8
Definitions
.1
Threshold Value: Value at which corrective actions are required, including procedural
modifications as established in the submitted plan that permit work to continue without
exceeding the specified Shutdown Value.
.2
Response Value: Value at which the Contractor shall actively control ground vibration
in accordance with the approved plan to prevent reaching the Shutdown Value.
.3
Shutdown Value: Value at which the Contractor shall stop all work immediately, and
must meet with the Contract Administrator to develop a plan of action before work can
be resumed.
.4
.5
Peak Particle Velocity (PPV): the maximum speed in millimetres per second that
ground particles move as a result of energy released from explosive detonations.
.6
dBL: Decibel.
Design Criteria:
.1
.2
Performance Requirements
.1
Noise levels during construction shall not exceed the thresholds specified herein.
.2
Vibration levels during construction shall not exceed the thresholds specified in this
Section.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.2
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 2 OF 13
SUBMITTALS
.1
.2
As soon as feasible after the Notice to Proceed, submit manufacturers product data
describing all specified vibration-monitoring instruments to the Contract Administrator at all
sites. The Contract Administrator will route information as required to PWGSC for review,
including requests for consideration of substitutions, if any, together with product data and
instruction manuals for requested substitutions.
.3
Within 3 weeks after the Notice to Proceed, submit to the Contract Administrator for review
the resumes of the Vibration Monitoring Specialist Engineer and any vibration monitoring
technical support personnel, sufficient to define details of relevant experience.
.4
Within 5 work days of receipt of each instrument at the site, submit to the Contract
Administrator a copy of the instruction manual and the laboratory calibration and test
equipment certification.
.5
Prior to the start of construction and prior to performing any vibration monitoring, the
Contractor shall submit to the Contract Administrator for review a written plan detailing the
procedures for vibration monitoring. Such details shall include:
.6
.1
The name of the Firm and Vibration Monitoring Specialist Engineer licensed in the
Province of Ontario and qualifications showing the necessary level of experience
providing the vibration monitoring services
.2
.3
.4
.5
Means and methods of providing warning when the Response Values, as specified in
Article 1.5.1, are reached.
.6
.7
Noise and Vibration Control Plan - Contractor shall prepare and submit to the Contract
Administrator for review and approval, as per Section 01330 Submittal Procedures at least
30 days prior to commencing construction, a Noise and Vibration Control Plan prepared by a
qualified noise and vibration specialist. Plan shall include identification of noise control
measures, monitoring protocol, notification procedures, and other information as necessary.
A qualified noise and vibration specialist is defined as a Board Certified Canadian Acoustical
Association member or other qualified consultant or engineer, subject to approval by the
Contract Administrator. The plan shall be submitted to the Contract Administrator at least 20
working days prior to the start of the works on their sites.
.1
The plan shall incorporate vibration monitoring of the 1220mm Chamberlain water
main, the Supreme Court Building, the Justice Building, and the daycare adjacent to
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 3 OF 13
the Justice Building. The existing vibration monitoring plan/shop drawings for the
MTO Kent Street bridge replacement works will be provided to the Contractor if and
when available.
.7
Quality Control
.1
1.3
QUALITY ASSURANCE
.1
Reference Standards:
.1
.2
Qualifications:
.1
The Contractors vibration monitoring personnel shall have the qualifications specified
herein. The personnel may be on the staff of the Contractor or may be on the staff of a
specialist subcontractor. However, they shall not be employed nor compensated by
subcontractors, or by persons or entities hired by subcontractors, who will provide
other services or material for the project.
.2
.3
1.4
.1
.2
RESPONSIBILITIES OF CONTRACTOR
.1
.2
Protect from damage and maintain instruments installed by the Contractor and repair or
replace damaged or inoperative instruments.
.3
.4
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 4 OF 13
.5
.6
Contractor shall monitor noise levels following approved monitoring protocols. Monitoring
shall occur, where allowed by adjacent property owners, at the nearest sensitive receptor.
If noise thresholds are exceeded, Contractor shall stop work and identify alternate methods
and equipment or place restrictions on construction operations to comply with noise
thresholds.
.7
Contractor shall not resume operations before correcting conditions that cause excessive
noise or vibration, subject to approval by the Contract Administrator. Contractor shall not
be entitled to additional compensation or extension of contract time for suspended
operations because of its failure to meet specified noise and vibration criteria.
.8
Contractor shall pay any and all fines and penalties that may be levied for violations
pertaining to noise and vibration thresholds specified herein, at no additional cost to the
City.
.9
Contractor shall implement effective noise and vibration control measures, as necessary,
whenever construction activities (including mobilization and demobilization) would
otherwise exceed the allowable thresholds. Contractor shall be responsible for ensuring
that all implemented noise and vibration control measures are installed and used correctly.
Control measures include but are not limited to the following:
.1
Best available controls techniques including mufflers, intake silencers, ducts, engine
enclosures and acoustically attenuating shields or shrouds for all construction-noise
equipment and trucks.
.2
.3
.4
Materials stockpiles as well as staging and parking areas shall be located as far as
feasible from sensitive receptors.
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 5 OF 13
shall not exceed the 70 dBA speech interference level criterion. The Contractor is
made aware of a daycare located adjacent to the Justice Building on PWGSC
property north of Wellington Street.
.6
Vibration monitoring is required when any work is within 100 metres of the
Chamberlain WM.
.1
.7
Design and construct temporary noise barriers at locations indicated on the Contract
Drawings and/or as required to meet specified noise criteria.
.8
Additional specific control measures at tunnel portal and shaft construction sites
include but are not limited to:
.9
1.5
.1
.2
.3
.4
.5
.6
.7
.8
.9
The Contractor shall not be entitled to additional compensation for delays resulting
from adjustments to the Contractors method/operation so that vibration limits are not
exceeded. All costs for delays resulting from adjustments to the Contractors
method/operation shall be at no expense to the owner.
For measurements at any receptor (activity based), unless otherwise noted below.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Source Type
Continuous / Intermittent
Source, any frequency
Transient Source, any
frequency
Blasting, any frequency
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 6 OF 13
Threshold Value,
mm/sec PPV
[Contractor Action
Required]
4
Contractor
Response Value,
mm/sec PPV
Shutdown Value,
mm/sec PPV
10
16
20
NOTE: Transient sources create an isolated vibration event such as drop of equipment. Continuous/intermittent sources
include, but not limited to, jackhammer, loaded trucks, pogo-stick compactors and impact excavators.
.2
Measurements at the 1220mm Chamberlain Water Main, resulting from any activity.
Frequency
(Hz)
Threshold Value,
mm/sec PPV
[Contractor Action
Required]
10
Any
.3
.2
Contractor Response
Value, mm/sec PPV
Shutdown Value,
mm/sec PPV
16
20
For vibration limits for work adjacent to recently placed concrete, refer to Section
01119 Preservation and Protection.
Noise thresholds
Day
Time
Mon-Fri
7 a.m. 7 p.m.
Mon-Fri
Mon-Fri
Sat-Sun
Sat-Sun
Sat-Sun
7 p.m. 10 p.m.
10 p.m. 7 a.m.
8 a.m. 5 p.m.
5 p.m. 10 p.m.
10 p.m. 8 a.m.
L max
(at any location)
130 dBA, unless otherwise limited
per Section 1.4, above
70 dBA
65 dBA
70 dBA
70 dBA
65 dBA
.3
In the event that any monitoring results indicate exceedance of noise or vibration thresholds,
the Contractor shall immediately notify the Contract Administrator of the exceedance,
identify the source and cause of the exceedance, implement corrective actions, and provide
documentation to the Contract Administrator that subsequent noise and vibration levels are
within acceptable limits.
.4
.5
If the Contractor receives any noise or vibration complaints directly, the Contractor shall
immediately notify the Contract Administrator.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 7 OF 13
.6
The Contract Administrator will require the Contractor to suspend operations when noise
or vibration complaints are received, damage or disturbance to adjoining property or
occupants has been reported, and noise or vibration exceeds specified limits. Contractor
shall restrict use of equipment causing noise or vibration disturbances so that specified
limits are not exceeded.
.7
Contractor shall monitor noise and vibration at the construction site and adjoining
buildings using acceptable equipment and methods. Monitoring shall be sufficient to
measure potential building damage and effects on occupants, property and sensitive
equipment.
.8
The response values for continuous/intermittent or transient sources shall be adhered to at all
times.
PART 2
PRODUCTS
2.1
EQUIPMENT
.1
The Contractor shall use seismographs with the following features to monitor noise and
vibration:
.1
Four channels comprising one airblast overpressure and three seismic channels.
.2
.3
.4
.5
Capable of measuring overpressures between 80 to 140 dBL overall peak sound level
(0.0003 to 0.2 kPa).
.6
Portable.
.7
.8
Water resistant.
.9
.10
Vibration monitoring on the Chamberlain Water Main shall be carried out with
Instantel Micromate digital seismographs or an approved equivalent, capable of
monitoring on a continuous basis and providing peak levels at regular intervals (no
greater than 5 minutes) as well as full waveform data. The vibration monitoring
equipment shall be capable of measuring vibration intensities up to 250 mm/s at a
frequency response of 2 to 250 Hz. The vibration monitors shall be equipped with a
real time warning system consisting of either a red flashing light or an air horn to alert
when a threshold value has been reached. The vibration monitor geophones shall be
capable of withstanding saturated conditions and require watertight connections.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 8 OF 13
.2
Any request from the Contractor for consideration of a substitution shall clearly state the
nature of the deviation from the product specified.
.3
The Contractor shall furnish all installation tools, materials and miscellaneous
instrumentation components for vibration monitoring.
PART 3
EXECUTION
3.1
INSTALLATION OF SEISMOGRAPHS
.1
The Contractor shall install seismographs at the near point of the buildings that are closest to
the project site, above the tunnel alignment, and at other locations specifically identified on
the Contract Drawings and Appendix B of Section 02480 - Geotechnical and Structural
Instrumentation and Monitoring, including the Supreme Court Building, the Justice
Building, the daycare adjacent to the Justice Building, and the Chamberlain Water Main.
.2
Seismographs shall be installed at all buildings or structures where the tunnel is crossing
directly beneath any portion of the building or structure.
.3
Seismographs shall be installed on all buildings or where indicated on the plans. These
include parcels for which tunnel easements have been obtained, whether or not the tunnel is
directly beneath a portion of the building or structure or not.
.4
Seismographs shall be installed at all buildings or structures within 100 m of any site at
which blasting is used.
.5
Unless easements have been obtained, the Contractor will be responsible for negotiating
placement of seismographs with Property Owners in accordance with Section 02480. In the
event a Property Owner refuses instrument installation, clearly document good faith efforts to
achieve agreement.
.6
The seismograph vibration sensors shall be located at points on the ground between 1 and 2
metres from the building facades.
.7
The seismograph vibration sensors shall be firmly mounted on the surface slab of concrete or
asphalt, or firmly set in undisturbed soil or affixed directly in the case of the Chamberlain
Water Main.
.8
The seismographs required north of Wellington along the NST alignment, as indicated on the
Contract Drawings, shall be in place for the duration of the work at Site 6 and at any time the
NST tunneling is between a location 100 m south of Wellington through the portal at Site 6.
.9
The seismographs shall be in place a minimum of five (5) days prior to the work commencing
in these areas to confirm observed background levels.
.10
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 9 OF 13
Contractor shall install new monitors as per the below procedure and shall not rely on the
existing monitors at the watermain at Chamberlain and Kent (Site 10) and at the watermain at
Chamberlain and Bronson (Site 10b staging area).
.1
.2
.11
3.2
At least four (4) seismographs shall be readily available for installation at other
structures/locations at the discretion of the Contract Administrator at all times during the
Project.
.2
All seismographs shall have been calibrated by the manufacturer or certified calibration
laboratory within one year of their use on site. A current certificate of calibration shall be
submitted to the Contract Administrator with the Contractors data. Calibration shall be
maintained in accordance with manufacturer recommendations throughout the project.
.3
.4
.5
3.3
A hole shall be advanced through existing ground to the top of the pipe with a
hydraulic-vacuum excavator. Control of groundwater inflow may be required. The
vibration monitor (seismograph) geophone shall then be lowered into place on top of
the WM, or the concrete encasement if applicable, adhered to the surface of the WM or
concrete, and the hole backfilled with native material to hold the geophone in place.
The Micromate should be placed in a secure, waterproof lockbox at the ground surface
or bolted to a hard surface in an accessible location. The ground must be hard and
compact. All installation shall be in accordance with manufactures recommendations
or the recommendations of the manufacturers designated dealer.
Vibration monitoring is required when any work occurs within 100 metres of the WM.
.1
.2
Stop all construction operations that are within 15 m of the existing monitor locations
which are subject to vibration monitoring requirements;
.3
Notify the Contractor Administrator when the sensor is put back into operation.
The Contractor shall ensure that the Vibration Monitoring Specialist Engineer is on site
monitoring readings for the full duration of all construction operations above and below the
WM.
DATA COLLECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 10 OF 13
.1
The Contractor shall collect seismograph data prior to any vibration-producing demolition or
construction activities to document background vibrations at each monitoring location. This
monitoring shall consist of a continuous recording of the maximum single-component peak
particle velocities for one-minute intervals, which shall be printed on a strip chart. The
background monitoring shall be performed for a minimum of five consecutive days,
continuously.
.2
The Contractor shall monitor vibration during demolition and other significant vibration
producing construction activities. This monitoring shall consist of a continuous recording of
the maximum single-component peak particle velocities for one-minute intervals, which shall
be printed on a strip chart. During the monitoring, the Contractor shall document all events
that are responsible for the measured vibration levels, and submit the documentation to the
Contract Administrator with the data as specified in Article 3.4.
.3
All vibration monitoring data shall be recorded contemporaneously and plotted continuously
on a graph by the data acquisition equipment or software. Each graph shall show timedomain wave traces (particle velocity versus time) for each transducer with the same vertical
and horizontal axes scale.
.4
The Contractor shall notify the Contract Administrator at least 24 hours prior to starting a
new vibration-producing construction task, and shall have the seismographs in place and
functioning properly prior to any such activity within 100 m of the monitoring locations. No
significant vibration-producing activity shall occur within this zone unless the monitoring
equipment is functioning properly and baseline data has been collected and submitted.
.5
The equipment shall be set up in a manner such that an immediate warning is given when the
peak particle velocity in any direction exceeds the Response Values specified in Article 1.5.1.
The warning emitted by the vibration-monitoring equipment shall be instantaneously
transmitted to the responsible person designated by the Contractor by means of warning
lights, audible sounds or electronic transmission. The Contractor shall immediately inform
the Contract Administrator of all such occurrences.
.6
The Contractor shall review seismograph readings a minimum of once per day when working
at Site 6, and shall record readings continuously at all identified structures and within 100 m
of the site.
.7
The Contractor shall obtain seismograph readings continuously within 100 m behind and 100
m ahead of the face of the tunnel during mining operations. This will require regular
movement of seismographs as the tunnel progresses. The Contractor shall maintain
additional seismographs such that monitoring proceeds continuously throughout construction
within the required distances from the tunnel face. The Contractor may negotiate for
permission to install the seismographs on private property along with the tiltmeters or install
the seismographs on public property subject to approval from the appropriate City or
Government Agencies.
3.4
Within 10 working days after the completion of the background vibration monitoring, and
prior to any vibration inducting activities, the Contractor shall submit to the Construction
Administrator a hard copy report documenting the results at each of the monitoring locations.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 11 OF 13
The report shall include all data collected in both hard copy and electronic format readable by
the Contract Administrator.
.2
Should specialized software be required to read any data files submitted, such software shall
be provided to the Contract Administrator at no additional cost to the City.
.3
During construction, the Contractor shall provide weekly, hard copy reports summarizing any
vibration monitoring data collected at the specified vibration-monitoring locations. The
reports for each week shall be submitted on or before the end of the following week.
.4
All reports shall be signed by the approved Vibration Monitoring Specialist Engineer, and
shall include the following:
.1
Project identification.
.2
.3
.4
Summary tables indicating the date, time and magnitude and frequency of maximum
single-component peak particle velocity measured during each one-hour interval of the
monitoring period.
.5
.6
Appendix graphs of the strip charts printed during the monitoring periods.
.5
In addition to the hard copy data specified herein, the Contractor shall provide electronic data
files with each report.
.6
For the Chamberlain WM, The Contractor shall notify the Contract Administrator in writing
that the vibrations measured at the WM has not exceeded the limits specified in the contract,
at the intervals below:
.1
3.5
DAMAGE TO INSTRUMENTATION
.1
The Contractor shall protect all instruments and appurtenant fixtures, leads, connections, and
other components of vibration-monitoring systems from damage due to construction
operations, weather, traffic, and vandalism.
.2
3.6
DISCLOSURE OF DATA
.1
The Contractor shall not disclose any instrumentation data to third parties and shall not
publish data without prior written consent of the City.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.7
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 12 OF 13
The Contractor shall interpret the data collected, including making correlations between
seismograph data and specific construction activities. The data shall be evaluated to
determine whether the measured vibrations can be reasonably attributed to construction
activities.
.2
.3
.1
.2
Meet with the Contract Administrator to discuss the need for response action(s).
.3
If directed by the Contract Administrator during the above meeting that a response
action is needed, submit within 24 hours a detailed specific plan of action based as
appropriate on the generalized plan of action submitted previously as part of the
vibration-monitoring plan specified in Article 1.05.
.4
Immediately notify the Contract Administrator and suspend activities in the affected
area, with the exception of those actions necessary to avoid exceeding the Shutdown
Value.
.2
Meet with the Contract Administrator to discuss the need for response action(s).
.3
If directed by the Contract Administrator during the above meeting that a response
action is needed, submit within 24 hours a detailed specific plan of action based as
appropriate on the generalized plan of action submitted previously as part of the
vibration-monitoring plan specified in Article 1.05.
.4
.5
If at any time the vibration limit is exceeded during execution of the WM monitoring
works, the Contractor shall immediately cease all operations and shall adjust the
method/operation until vibration limits are not exceeded.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.8
SECTION 02482
NOISE AND VIBRATION MONITORING
PAGE 13 OF 13
DISPOSTION OF INSTRUMENTS
.1
The Contractor shall remove all instruments at the conclusion of the Project and restore all
facilities. Prior to such removal, the Contractor shall obtain the approval of the Contract
Administrator to remove all instruments in writing.
.2
All salvaged instruments shall become the property of the Contractor. The Contract
Administrator can elect to maintain any instrumentation in place at the conclusion of the
project at no additional cost to the City. In such cases, instruments shall be the property of
the City.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SECTION INCLUDES
SECTION 02511
WATER MAINS
PAGE 1 OF 4
.1
Materials and installation for water mains, hydrants, valves, valve boxes, and valve
chambers, including service connections to lines, grades and dimensions indicated on the
Contract Drawings or as directed by the Contract Administrator.
.2
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
1.3
PAYMENT PROCEDURES
.1
1.4
Payment for all work completed in accordance with this Section will be paid as per
Section 01025, Measurement and Payment.
REFERENCE
.1
.2
.2
.3
Special Provision S.P. No.: F-2120 Select Subgrade Material for Trench Backfill
.2
.3
.4
.5
Special Provision S.P. No.: F-4413 Valves, Valve Boxes, Valve Chambers
.6
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
SECTION 02511
WATER MAINS
PAGE 2 OF 4
.7
.8
.9
.10
.11
.12
Special Provision S.P. No.: F-4492 Thrust Restraint of Watermain and Fittings
.13
Special Provision S.P. No.: F-4493 Tracing Wire for Watermain and Fittings
.14
Special Provision S.P. No.: F-4494 Cathodic Protection of New Watermain and
Fittings
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
.2
.3
.4
.5
.6
.7
Standard Drawing W7 Precast Top for Butterfly & Tapping Valve Chambers
.8
.9
.10
.11
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02511
WATER MAINS
PAGE 3 OF 4
.12
.13
Standard Drawing W16 Standard Frame for Valve Chambers (Modified OPSD
401.020)
.14
.15
.16
.17
.18
.19
.20
.21
.22
Standard Drawing W25.3 Concrete Thrust Blocks for PVC and DI Pipe 400mm
and Under
.23
Standard Drawing W25.4 Thrust Block Dimension Tables for PVC and DI Pipe
400mm and Under
.24
Standard Drawing W25.5 Restraining and Retaining Rings for PVC and DI Pipe
400mm and Under
.25
Standard Drawing W25.6 Tables of Restrained Lengths for PVC and DI Pipe
400mm and Under
.26
Standard Drawing W26 Typical Service Line 19 & 25mm (Nominal) Diameter
.27
.28
.29
.30
.31
.32
.33
.34
Standard Drawing W39 Cathodic Protection for Ductile Iron Watermain Systems
.35
.36
.37
.38
.39
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.40
1.5
SECTION 02511
WATER MAINS
PAGE 4 OF 4
Standard Drawing W50 Typical Private Service > 100mm Connection Procedure
SUBMITTALS
.1
1.6
.1
1.7
Provide data to produce as-built drawings, including directions for operating valves, list
of equipment required to operate valves, details of pipe material, location of air and
vacuum release valves, hydrant details, maintenance and operating instructions in
accordance with Section 01780 - Closeout Submittals.
WASTE MANAGEMENT AND DISPOSAL
.1
Separate waste materials for reuse and recycling in accordance with Section 01355 Waste Management and Disposal.
Part 2
Products
2.1
MATERIALS
.1
.2
Pipe bedding and surround materials: City of Ottawa Special Provision No. F-3147 and
as per the Contract Drawings.
.3
Water fountain valve box at Site 3a to be freeze resistant valve box designed for use in
the water fountain as shown in the contract drawings and in the climate encountered in
Ottawa.
Part 3
Execution
3.1
Excavate and backfill in accordance with Section 02315 Excavating, Trenching and
Backfilling.
.2
3.2
3.3
Prior to commencing any work erosion and sediment control measures shall be in place
in accordance with Section 01160, Erosion and Sediment Control Plan.
INSTALLATION AND COMMISSIONING
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SECTION INCLUDES
SECTION 02530
SANITARY SEWER AND
ODOUR CONTROL DUCTS
PAGE 1 OF 10
.1
.2
This section also includes pipe material for odour control ducts and air vent piping for
buried ducts. Indoor PVC ducts in the Odour Control Facilities are not covered in this
section.
.3
This section does not include work involved to construct the RRC Diversion Sewer
Tunnel or the EWT, NST and associated shafts. This section includes requirements for
CCTV of the RRC Diversion Sewer, EWT and NST.
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
1.3
PAYMENT PROCEDURES
.1
1.4
Payment for all work completed in accordance with this Section will be paid as per
Section 01025, Measurement and Payment.
REFERENCES
.1
.2
.3
ASTM D3034 RevA-14, Standard Specification for Type PSM Poly (Vinyl
Chloride) (PVC) Sewer Pipe and Fittings.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.2
.4
.5
1.5
SECTION 02530
SANITARY SEWER AND
ODOUR CONTROL DUCTS
PAGE 2 OF 10
OPSS 410, Nov. 2013, Construction Specification for Pipe Sewer Installation in
Open Cut
.2
OPSS.MUNI 1820, Nov. 2014, Material Specification for Circular and Elliptical
Concrete Pipe
.3
OPSD-802.030, Nov. 2010, Rigid Pipe Bedding, Cover, and Backfill, Type 1 or
2 Soil
City of Ottawa
.1
Special Provision S.P. No.: F-2120 Select Subgrade Material for Trench Backfill
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
Special Provision S.P. No.: F-4102 Expanded Polystyrene Insulation for Sewers
.13
.14
Special Provision S.P. No.: F-4105 Maintaining Flow in Sewers and Sewer
Services
DEFINITIONS
.1
1.6
Pipe section is defined as length of pipe between successive manholes and/or between
manhole and any other structure which is part of sewer system.
SUBMITTALS
.1
Submit shop drawings in accordance with Section 01330 - Submittal Procedures and as
specified in this section.
.2
Submit manufacturer's test data and certification at least 2 weeks prior to beginning
Work.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02530
SANITARY SEWER AND
ODOUR CONTROL DUCTS
PAGE 3 OF 10
.4
.5
Submit CCTV inspection plan for all existing and installed sewers at least 30 days prior
to inspection. The CCTV inspection plan shall include the following as a minimum:
1.1
.1
List of all existing and installed sewers to be inspected, including pipe diameters,
length, and access structures/maintenance holes to be utilized.
.2
.3
.4
For sewers greater than 1500mm diameter, the inspection plan shall also include:
.1
.2
1.2
Separate waste materials for reuse and recycling in accordance with Section 01355 Waste Management and Disposal.
DELIVERY, STORAGE AND HANDLING
.1
1.3
.1
.2
Submit schedule of expected interruptions for approval and adhere to approved schedule.
Part 2
Products
2.1
.2
OPSS 1820 shall apply for the concrete pipe and fittings for sewers and air ducts/vents
except where superseded by the following specifications.
.3
Minimum size for which concrete pipe will be permitted for this project: 300 mm. All
sewers larger than 675 mm shall be concrete pipe.
.4
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02530
SANITARY SEWER AND
ODOUR CONTROL DUCTS
PAGE 4 OF 10
.6
Pipe shall be supplied only by manufacturers pre-qualified by the Ontario Concrete Pipe
Association (OCPA). Lifting holes shall not be permitted on 900 mm diameter pipe and
smaller. Lift holes on larger pipe shall be made watertight.
.7
.8
.9
2.2
.1
.2
.3
Include a pipe stop as an integral part of the cored hole where gasketed inserts
are not used.
.2
.3
.4
Failure to produce a clear ringing sound when placed on end and dry-tapped with
a light hammer
.5
.1
.2
All Polyvinyl Chloride (PVC) gravity sanitary sewer, air ducts/vents and drain pipes
shall be: to CAN/CSA-B182.2 and ASTM D3034.
.1
2.3
.2
.2
Maximum size for which PVC pipe is permitted on this project: 675 mm
.3
.4
.5
Nominal lengths: 4 m.
.6
Sanitary sewer laterals are to have sweep bends; no angled bends are permitted.
INSULATION
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.4
SECTION 02530
SANITARY SEWER AND
ODOUR CONTROL DUCTS
PAGE 5 OF 10
GASKETS
.1
.2
All gaskets to be standard material, unless contaminated soil condition are encountered,
where they shall be constructed of nitrile.
2.5
WATERSTOPS
.1
.2
All pipe wall penetrations into maintenance holes to be sealed with appropriately sized,
as recommended by the manufacturer, Link-Seal modular seals with standard EPDM seal
elements and stainless steel hardware.
2.6
COUPLING
.1
Coupling for PVC pipe to be Robar 1506 or Fernco Flexible coupling with stainless steel
316 clamps and hardwares.
.2
Coupling for concrete pipe to be HOBAS Closure Coupling, Teekay AXIFLEX Coupling
(Type II) or approved equivalent with stainless steel 304 casing and stainless steel 316
fasteners.
.3
2.7
.2
Bedding:
.3
.4
.1
Granular A material with thickness no less than 150 mm for pipes on earth and
no less than 300 mm for pipes on rock, placed in lifts no greater than 300 mm
thick and compacted to 98% Standard Proctor.
.2
.3
.4
Cover Material:
.1
Cover to extend from spring line of pipe to at least 300 mm above obvert of pipe.
.2
Granular A material placed in thick lifts no greater than 225 mm and compacted
to 95% SPMDD.
.3
Sewer bedding and backfill requirements shall be as per OPSD 802 series as applicable,
depending on the ground conditions reported for specific sites and pipe material
stipulated.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.8
SECTION 02530
SANITARY SEWER AND
ODOUR CONTROL DUCTS
PAGE 6 OF 10
BACKFILL
.1
Trench backfill placed within the frost penetration depth (1.8m below finished grade)
shall match the soil exposed to the trench wall. It shall be free draining non-frost
susceptible sand or sand and gravel conforming to the requirements for OPSS Granular B
Type I and shall be configured with 3H:1V frost tapers.
.2
The existing inorganic fill or native inorganic soils may be suitable for use as backfill.
These materials may be reused as backfill provided testing indicates that it meets the
OPSS requirements for Granular B Type I or Select Subgrade Material.
.3
Trench backfill shall be placed in maximum 300mm thick loose lifts and compacted to a
minimum of 95% of the materials SPMDD.
.4
Part 3
Execution
3.1
PREPARATION
.1
.2
Ensure that pipes and fittings are new and undamaged. Carefully inspect materials and
replace defective material to the satisfaction of the Contract Administrator.
.3
3.2
3.3
Prior to commencing any work erosion and sediment control measures shall be in place
in accordance with Section 01160, Erosion and Sediment Control Plan.
TRENCHING
.1
.2
Do not allow contents of any sewer or sewer connection to flow into trench.
.3
Trench alignment and depth require approval of Contract Administrator prior to placing
bedding material and pipe.
3.4
GRANULAR BEDDING
.1
.2
Place granular bedding materials in uniform layers as indicated in Section 2.6, Pipe
Bedding and Surround Materials.
.3
Shape bed true to grade and to provide continuous, uniform bearing surface for pipe.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.1
SECTION 02530
SANITARY SEWER AND
ODOUR CONTROL DUCTS
PAGE 7 OF 10
.4
.5
3.5
INSTALLATION
.1
Lay and join pipes in accordance with manufacturer's recommendations and to approval
of the Contract Administrator. Sewer tolerance to adhere to City of Ottawa F-4100 (+/30mm).
.2
.3
Do not use chains or cables passed through rigid pipe bore so that weight of pipe
bears upon pipe ends.
Lay pipes on prepared bed, true to line and grade, with pipe invert smooth and free of
sags or high points.
.1
Ensure barrel of each pipe is in contact with shaped bed throughout its full
length.
.4
Begin laying at outlet and proceed in upstream direction with socket ends of pipe facing
upgrade.
.5
.6
Do not allow water to flow through pipe during construction, except as may be permitted
by the Contract Administrator.
.7
Whenever work is suspended, install removable watertight bulkhead at open end of last
pipe laid to prevent entry of foreign materials.
.8
.9
Pipe jointing:
.1
.2
Support pipes with hand slings or crane as required to minimize lateral pressure
on gasket and maintain concentricity until gasket is properly positioned.
.3
.4
Maintain pipe joints free from mud, silt, gravel and other foreign material.
.5
.6
.7
Minimize joint deflection after joint has been made to avoid joint damage.
.8
At rigid structures, install pipe joints not more than 1.2 m from side of structure.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02530
SANITARY SEWER AND
ODOUR CONTROL DUCTS
PAGE 8 OF 10
.9
.10
.10
When stoppage of Work occurs, block pipes as directed by the Contract Administrator to
prevent creep during down time.
.11
Cut pipes as required for special inserts, fittings or closure pieces as recommended by
pipe manufacturer, without damaging pipe or its coating and to leave smooth end at right
angles to axis of pipe.
.12
.13
3.6
Use shrinkage compensating grout when suitable gaskets are not available.
PIPE SURROUND
.1
.2
Upon completion of pipe laying, and after the Contract Administrator has inspected pipe
joints, surround and cover pipes as indicated.
.1
.3
Hand place surround material in uniform layers not exceeding 225 mm compacted
thickness as indicated.
.4
.5
Compact each layer from pipe invert to spring line of pipe to at least 98% SPMDD.
.6
Compact each layer from spring line of pipe to 300 mm above pipe to at least 95%
SPMDD.
.7
When field test results are acceptable to the Contract Administrator, place surround
material at pipe joints.
3.7
Refer to Section 02631 Maintenance Holes and Catch Basins for details on installation
of precast structures including manholes and catch basins.
.2
Confirm with the supplier of the precast concrete structures the weight of the individual
sections and proper handling and jointing procedures.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02530
SANITARY SEWER AND
ODOUR CONTROL DUCTS
PAGE 9 OF 10
.3
Install double seals, waterproofing membrane and protection board at each precast joint
and where indicated in accordance with the manufacturers instructions. The precast
structures to be watertight. Any visible leakage will have to be repaired.
.4
Protect the precast structures against buoyancy forces during construction until fully
backfilled.
.5
Backfill walls of the precast structures with 300 mm thick surrounding layer of Granular
A placed against the walls. Place the granular in 300 mm layers and compact to 95%
SPMDD.
.6
Install all ladders, platforms, covers, retrieval brackets and hatches as required and as
indicated on the Contract Drawings.
3.8
.2
.3
Cover to extend from spring line of pipe to at least 300 mm above obvert of pipe, placed
in thick lifts no greater than 300 mm and compacted to 95% SPMDD.
.4
Place backfill material, above cover in uniform layers not exceeding 300 mm compacted
thickness up to grades as indicated. Compact the backfill material to at least 95%
SPMDD.
3.9
FIELD TESTING
.1
The field testing shall be performed in the presence of a certified professional engineer
who shall submit a certified copy of the test results.
.2
.3
3.10
CCTV to be carried out as per City SP No. F-4090 Cleaning and Televising
Sewer.
.2
Carry out CCTV inspection of existing sewers within the construction limits and
the first length of existing sewer pipes outside of the contract limits including
cross streets pre and post construction. Major sewers (Rideau Canal Interceptor,
Rideau River Collector, and Interceptor Outfall Sewer) within the construction
limits shall be inspected pre and post construction.
.3
.4
Carry out CCTV inspection of the installed RRC Diversion Sewer, EWT and
NST.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.11
SECTION 02530
SANITARY SEWER AND
ODOUR CONTROL DUCTS
PAGE 10 OF 10
All new and existing sewer pipes to be cleaned and flushed prior to field testing and
CCTV inspection. Rideau Canal Interceptor, Rideau River Collector, and Interceptor
Outfall Sewer do not require cleaning and flushing prior to CCTV inspection.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SECTION INCLUDES
SECTION 02630
STORM SEWER
PAGE 1 OF 9
.1
This section includes materials and installation for storm sewers and pipe subdrains.
.2
This section does not include work involved to construct the RRC Diversion Sewer
Tunnel or CSST Tunnel and associated shafts. This section includes requirements for
CCTV of the storm sewers.
1.2
SECTION INCLUDES
.1
1.3
.1
.2
.3
.4
.5
.6
.7
.8
1.4
PAYMENT PROCEDURES
.1
1.5
Payment for all work completed in accordance with this Section will be paid as per
Section 01025, Measurement and Payment.
REFERENCES
.1
.2
.3
ASTM D3034 RevA-14, Standard Specification for Type PSM Poly (Vinyl
Chloride) (PVC) Sewer Pipe and Fittings.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.1
.2
.4
.5
1.6
SECTION 02630
STORM SEWER
PAGE 2 OF 9
OPSS 410, Nov. 2013, Construction Specification for Pipe Sewer Installation in
Open Cut
.2
OPSS.MUNI 1820, Nov. 2014, Material Specification for Circular and Elliptical
Concrete Pipe
.3
OPSD-802.030, Nov. 2010, Rigid Pipe Bedding, Cover, and Backfill, Type 1 or
2 Soil
City of Ottawa
.1
Special Provision S.P. No.: F-2120 Select Subgrade Material for Trench Backfill
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
.12
Special Provision S.P. No.: F-4102 Expanded Polystyrene Insulation for Sewers
.13
.14
Special Provision S.P. No.: F-4105 Maintaining Flow in Sewers and Sewer
Services
DEFINITIONS
.1
1.7
A pipe section is defined as length of pipe between successive catch basins and/or
manholes.
SUBMITTALS
.1
Submit shop drawings in accordance with Section 01330 - Submittal Procedures and as
specified in this section.
.2
Submit manufacturer's test data and certification at least 2 weeks prior to beginning
Work.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02630
STORM SEWER
PAGE 3 OF 9
.4
.5
Submit CCTV inspection plan of storm sewers with all other CCTV works planned as
specified in Section 02531 Sanitary Sewer and Odour Control Ducts.
1.8
1.9
Separate waste materials for reuse and recycling in accordance with Section 01355 Waste Management and Disposal.
DELIVERY, STORAGE AND HANDLING
.1
1.10
.1
.2
Submit schedule of expected interruptions for approval and adhere to approved schedule.
Part 2
Products
2.1
.2
OPSS 1820 shall apply for the concrete pipe and fittings except where superseded by the
following specifications.
.3
Minimum size for which concrete pipe will be permitted for this project: 300 mm. All
sewers larger than 675 mm shall be concrete pipe.
.4
.5
Pipe shall be supplied only by manufacturers pre-qualified by the Ontario Concrete Pipe
Association (OCPA). Lifting holes shall not be permitted on 900 mm diameter pipe and
smaller. Lift holes on larger pipe shall be made watertight.
.6
.7
.1
.2
.3
Include a pipe stop as an integral part of the cored hole where gasketed inserts
are not used.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.8
2.2
SECTION 02630
STORM SEWER
PAGE 4 OF 9
.3
.4
Failure to produce a clear ringing sound when placed on end and dry-tapped with
a light hammer
.5
.1
.2
All Polyvinyl Chloride (PVC) gravity sanitary sewer and drain pipes shall be: to
CAN/CSA-B182.2 and ASTM D3034.
.1
2.3
.2
.2
Maximum size for which PVC pipe is permitted on this project: 675 mm
.3
.4
.5
Nominal lengths: 4 m.
SUBDRAIN
.1
2.4
INSULATION
.1
2.5
.1
.2
All gaskets to be standard material, unless contaminated soil condition are encountered,
where they shall be constructed of nitrile.
2.6
WATERSTOPS
.1
.2
All pipe wall penetrations into maintenance holes to be sealed with appropriately sized,
as recommended by the manufacturer, Link-Seal modular seals with standard EPDM seal
elements and stainless steel hardware.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
2.7
SECTION 02630
STORM SEWER
PAGE 5 OF 9
COUPLING
.1
Coupling for PVC pipe to be Robar 1506 or Fernco Flexible coupling with stainless steel
316 clamps and hardwares.
.2
Coupling for concrete pipe to be HOBAS Closure Coupling, Teekay AXIFLEX Coupling
(Type II) or approved equivalent with stainless steel 304 casing and stainless steel 316
fasteners.
.3
2.8
.2
Bedding:
.3
.4
2.9
.1
Granular A material with thickness no less than 150 mm for pipes on earth and
no less than 300 mm for pipes on rock, placed in lifts no greater than 300 mm
thick and compacted to 98% Standard Proctor.
.2
.3
.4
Cover Material:
.1
Cover to extend from spring line of pipe to at least 300 mm above obvert of pipe.
.2
Granular A material placed in thick lifts no greater than 225 mm and compacted
to 95% Standard Proctor.
.3
Sewer bedding and backfill requirements shall be as per OPSD 802 series as applicable,
depending on the ground conditions reported for specific sites and pipe material
stipulated.
BACKFILL
.1
Trench backfill placed within the frost penetration depth (1.8m below finished grade)
shall match the soil exposed to the trench wall. It shall be free draining non-frost
susceptible sand or sand and gravel conforming to the requirements for OPSS Granular B
Type I and shall be configured with 3H:1V frost tapers.
.2
The existing inorganic fill or native inorganic soils may be suitable for use as backfill.
These materials may be reused as backfill provided testing indicates that it meets the
OPSS requirements for Granular B Type I or Select Subgrade Material.
.3
Trench backfill shall be placed in maximum 300mm thick loose lifts and compacted to a
minimum of 95% of the materials SPMDD.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02630
STORM SEWER
PAGE 6 OF 9
.4
Subdrain backfill with clear stone as per Section 02315 Excavating, Trenching and
Backfilling.
.5
Part 3
Execution
3.1
3.2
Prior to commencing any work erosion and sediment control measures shall be in place
in accordance with Section 01160, Erosion and Sediment Control Plan.
PREPARATION
.1
.2
Ensure that pipes and fittings are new and undamaged. Carefully inspect materials and
replace defective material to the satisfaction of the Contract Administrator.
.3
3.3
TRENCHING
.1
.2
.3
Trench alignment and depth require approval of Contract Administrator prior to placing
bedding material and pipe.
3.4
GRANULAR BEDDING
.1
.2
Place granular bedding materials in uniform layers as indicated in Section 2.6, Pipe
Bedding and Surround Materials.
.3
Shape bed true to grade and to provide continuous, uniform bearing surface for pipe. Do
not use blocks when bedding pipes.
.4
.5
Fill excavation below bottom of specified bedding adjacent to manholes or catch basins
with compacted bedding material.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.5
SECTION 02630
STORM SEWER
PAGE 7 OF 9
INSTALLATION
.1
Lay and join pipe in accordance with manufacturer's recommendations and to approval
of Contract Administrator. Sewer tolerance to adhere to City of Ottawa F-4100 (+/30mm).
.2
.3
Do not use chains or cables passed through rigid pipe bore so that weight of pipe
bears upon pipe ends.
Lay pipes on prepared bed, true to line and grade with pipe inverts smooth and free of
sags or high points.
.1
Ensure barrel of each pipe is in contact with shaped bed throughout its full
length.
.4
Begin laying at outlet and proceed in upstream direction with socket ends of pipe facing
upgrade.
.5
.6
Do not allow water to flow through pipes during construction except as may be permitted
by Contract Administrator.
.7
Whenever Work is suspended, install removable watertight bulkhead at open end of last
pipe laid to prevent entry of foreign materials.
.8
.9
Pipe jointing:
.10
.1
.2
Support pipes with hand slings or crane as required to minimize lateral pressure
on gasket and maintain concentricity until gasket is properly positioned.
.3
.4
Maintain pipe joints free from mud, silt, gravel and other foreign material.
.5
.6
.7
Minimize joint deflection after joint has been made to avoid joint damage.
.8
At rigid structures, install pipe joints not more than 1.2 m from side of structure.
.9
.10
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02630
STORM SEWER
PAGE 8 OF 9
.11
Cut pipes as required for special inserts, fittings or closure pieces, as recommended by
pipe manufacturer, without damaging pipe or its coating and to leave smooth end at right
angles to axis of pipe.
.12
.13
.14
3.6
Use shrinkage compensating grout when suitable gaskets are not available.
.1
.2
Upon completion of pipe laying, and after Contract Administrator has inspected pipe
joints, surround and cover pipes as indicated.
.1
.3
Hand place surround material in uniform layers not exceeding 225 mm compacted
thickness as indicated.
.4
.5
Compact each layer from pipe invert to spring line of pipe to at least 98% SPMDD.
.6
Compact each layer from spring line of pipe to 300 mm above pipe to at least 95%
SPMDD.
.7
When field test results are acceptable to Contract Administrator, place surround material
at pipe joints.
3.7
PRECAST CHAMBERS
.1
Refer to Section 02631 Maintenance Holes and Catch Basins for details on installation
of precast structures including manholes and catch basins.
.2
Confirm with the supplier of the precast concrete structures the weight of the individual
sections and proper handling and jointing procedures.
.3
Install double seals, waterproofing membrane and protection board at each precast joint
and where indicated in accordance with the manufacturers instructions. The precast
structures to be watertight. Any visible leakage will have to be repaired.
.4
Protect the precast structures against buoyancy forces during construction until fully
backfilled.
.5
Backfill walls of the precast structures with 300 mm layer of Granular A placed against
the walls. Place the granular in 300 mm layers and compact to 95% SPMDD.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.6
3.8
SECTION 02630
STORM SEWER
PAGE 9 OF 9
Install all ladders, platforms, covers, retrieval brackets and hatches as required and as
indicated on the Contract Drawings.
BACKFILL AND COVER
.1
.2
.3
Cover to extend from spring line of pipe to at least 300 mm above obvert of pipe, placed
in thick lifts no greater than 300 mm and compacted to 95% SPMDD.
.4
Place backfill material, above cover in uniform layers not exceeding 300 mm compacted
thickness up to grades as indicated. Compact the backfill material to at least 95 %
SPMDD.
3.9
FIELD TESTING
.1
The field testing shall be performed in the presence of a certified professional engineer
who shall submit a certified copy of the test results.
.2
.3
3.10
3.11
CCTV to be carried out as per City SP No. F-4090 Cleaning and Televising
Sewer.
.2
Carry out CCTV inspection of existing sewers within the construction limits and
the first length of existing sewer pipes outside of the contract limits including
cross streets pre and post construction.
.3
All new and existing sewer pipes to be cleaned and flushed prior to field testing and
CCTV inspection.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.1
SECTION 02631
MAINTENANCE HOLES AND CATCH BASINS
PAGE 1 OF 4
SECTION INCLUDES
.1
1.2
Materials and installation for constructing new precast manholes, chambers, catch basins
and ditch inlets which are included in standard City and OPS details, but does not
include cast-in-place structures. Further, it does not include precast structures that are not
typical City and OPS standards; these are described in Section 03410 Precast
Structures.
RELATED SECTIONS
.1
.2
.3
.4
.5
.6
.7
1.3
PAYMENT PROCEDURES
.1
1.4
Payment for all work completed in accordance with this Section will be paid as per
Section 01025, Measurement and Payment.
REFERENCES
.1
.2
.2
.3
.4
.2
City of Ottawa
.1
Special Provision S.P. No.: F-2120 Select Subgrade Material for Trench Backfill
.2
Special Provision S.P. No.: F-4070 Maintenance Holes, Catchbasins, Ditch Inlets
and Chambers.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
1.5
SECTION 02631
MAINTENANCE HOLES AND CATCH BASINS
PAGE 2 OF 4
.3
.4
Special Provision S.P. No.: F-4081 Self-Leveling Maintenance Hole Frame and
Cover
.5
.6
.7
.8
.9
.10
Standard Drawing S19 Heavy Duty "Fish" Type Round Catch Basin Cover
(Modified OPSD 400.07)
.11
Standard Drawing S22 Curb Inlet "Fish" Type Catch Basin Frame
.12
Standard Drawing S23 Curb Inlet "Fish" Type Catch Basin Cover
.13
.14
.15
SHOP DRAWINGS
.1
1.6
.1
Separate and recycle waste materials in accordance with Section 01355 - Waste
Management and Disposal.
Part 2
Products
2.1
.2
For granular material refer to Section 02315 - Excavating, Trenching and Backfilling.
.3
Precast concrete maintenance hole units shall be as per OPSD and as indicated on
Contract Drawings with flat cap where required to accommodate specified frame and
cover.
.4
Where specified on drawings covers shall be as per Standard Drawing S24 and S24.1.
.5
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02631
MAINTENANCE HOLES AND CATCH BASINS
PAGE 3 OF 4
.6
Where specified on drawings all 914mm covers shall be C-23B 35 cover with 37 5/8
ID frame, bolted or lockable and watertight, manufactured by Bibby Ste-Croix or
approved equal.
.7
Grates for air vent chambers shall be as per Section 05500 Metal Fabrications, or
OPSD 403.010 where specified on drawings.
2.2
.2
For granular material refer to Section 02315 - Excavating, Trenching and Backfilling.
.3
Precast concrete catch basin units shall be as per OPSD 705.010 and installed as per S1,
S2, or S3 as indicated on Contract Drawings.
.4
.5
.6
Precast Concrete ditch inlet shall be per OPSD 705.030 and grating shall be per OPSD
403.010.
Part 3
Execution
3.1
Excavate and backfill in accordance with Section 02315 Excavating, Trenching and
Backfilling and as indicated.
.2
Obtain approval of Consultant before installing maintenance holes and catch basins.
3.2
3.3
Prior to commencing any work erosion and sediment control measures shall be in place
in accordance with Section 01160, Erosion and Sediment Control Plan.
INSTALLATION
.1
Confirm with the supplier of the precast concrete structures the weight of the individual
sections and proper handling and jointing procedures.
.2
Install double seals, waterproofing membrane and protection board at each precast joint
and where indicated in accordance with the manufacturers instructions. The precast
structures are to be watertight. Any visible leakage will have to be repaired.
.3
Protect the precast structures against buoyancy forces during construction until fully
backfilled.
.4
Install all ladders, platforms, covers, retrieval brackets and hatches as required and as
indicated on the Contract Drawings.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02631
MAINTENANCE HOLES AND CATCH BASINS
PAGE 4 OF 4
.5
Backfill walls of the precast structures with 300 mm thick surrounding layer of Granular
A placed against the walls. Place the granular in 300 mm layers and compact to 95%
SPMDD.
.6
Installation of precast manhole, chamber, catch basin and ditch inlet structures as per
S.P. No.: F-4070.
.7
Adjust or rebuild manhole, chamber, catch basin and ditch inlet structures as per S.P.
No.: F-4080.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SECTION INCLUDES
.1
1.2
SECTION 02701
AGGREGATES: GENERAL
PAGE 1 OF 3
This section includes materials and requirements for aggregates only for road backfill and
reinstatement. Refer to Section 02315 Excavating, Trenching, and Backfilling for pipe
bedding and backfill requirements.
RELATED SECTIONS
.2
.3
.4
.5
.6
1.3
REFERENCES
.1
ASTM D4791-[99], Standard Test Method for Flat Particles, Elongated Particles, or Flat
and Elongated Particles in Coarse Aggregate.
Part 2
Products
2.1
MATERIALS
.1
Aggregate qualities: sound, hard, durable material free from soft, thin, elongated or
laminated particles, organic material, clay lumps or minerals, or other substances that
would act in deleterious manner for use intended.
.2
.3
.4
Natural sand.
.2
Manufactured sand.
.3
Crushed rock.
.2
Gradations to be within limits specified when tested to ASTM C136 and ASTM
C117. Sieve sizes to CAN/CGSB-8.1.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02701
AGGREGATES: GENERAL
PAGE 2 OF 3
GRADATION REQUIREMENTS
PERCENTAGE PASSING
MTO
SIEVE
DESIGNATION
100 mm
37.5 mm
26.5 mm
19 mm
13.2 mm
9.5 mm
4.75 mm
1.18 mm
300 m
150 m
75 m
GRANULAR A
GRANULAR B
TYPE II (note 1)
SELECT
SUBGRADE
MATERIAL
100
85 100
(87 100, note 2)
65 90
(75 95 note 2)
50 73
(60 83 note 2)
35 55
(40 60 note 2)
15 40
5 22
28
(2 10 note 3)
100
50 100
-
100
N/A
50 100
N/A
N/A
N/A
20 55
20 100
10 40
5 22
0 10
10 100
5 95
2.0 - 65.0
0 25.0
Notes:
1. When RAP is blended with Granular B Type I or Type III, 100% of the RAP shall pass the 75 mm sieve.
Conditions in Note 1 supersede this requirement.
2. When the aggregate is obtained from an air-cooled blast furnace slag source.
3. When the aggregate is obtained from a quarry or an air-cooled blast furnace slag or nickel slag source.
.5
2.2
Type 3 fill: selected material from excavation or other sources, approved by Contract
Administrator for use intended, unfrozen and free from rocks larger than 200 mm,
cinders, ashes, sods, refuse or other deleterious materials.
SOURCE QUALITY CONTROL
.1
Inform Contract Administrator of proposed source of aggregates and provide access for
sampling at least 2 weeks prior to commencing production.
.2
If, in opinion of Contract Administrator, materials from proposed source do not meet, or
cannot reasonably be processed to meet, specified requirements, locate an alternative
source or demonstrate that material from source in question can be processed to meet
specified requirements.
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.4
Acceptance of material at source does not preclude future rejection if it fails to conform
to requirements specified, lacks uniformity, or if its field performance is found to be
unsatisfactory.
Part 3
Execution
3.1
PREPARATION
.1
.2
.3
SECTION 02701
AGGREGATES: GENERAL
PAGE 3 OF 3
Processing
.1
.2
.3
.4
When operating in stratified deposits use excavation equipment and methods that
produce uniform, homogeneous aggregate.
Handling
.1
.2
.3
Stockpiling
.1
.2
.3
During winter operations, prevent ice and snow from becoming mixed into
stockpile or in material being removed from stockpile.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02702
AGGREGATES: LANDSCAPING
PAGE 1 OF 4
PART 1 - GENERAL
1.1
1.2
RELATED SECTIONS
.1
.2
.3
.4
.5
REFERENCES
.1
ASTM International(ASTM)
.1
1.3
1.4
ASTM D 4791-99, Standard Test Method for Flat Particles, Elongated Particles, or
Flat and Elongated Particles in Coarse Aggregate.
SAMPLES
.1
.2
.3
Provide Engineer with access to source and processed material for sampling.
.4
.5
Pay cost of sampling and testing of aggregates which fail to meet specified requirements.
.6
Provide water, electric power and propane to Engineer laboratory trailer at production site.
Divert unused granular materials from landfill to local quarry facility as approved by
Engineer.
PART 2 - PRODUCTS
2.1
MATERIALS
.1
Aggregate quality: sound, hard, durable material free from soft, thin, elongated or
laminated particles, organic material, clay lumps or minerals, or other substances that
would act in deleterious manner for use intended.
.2
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
2.2
SECTION 02702
AGGREGATES: LANDSCAPING
PAGE 2 OF 4
Natural sand.
.2
Manufactured sand.
.3
Crushed rock.
.2
.3
Inform Engineer of proposed source of aggregates and provide access for sampling at least
4 weeks prior to commencing production.
.2
If, in opinion of Engineer, materials from proposed source do not meet, or cannot
reasonably be processed to meet, specified requirements, locate an alternative source or
demonstrate that material from source in question can be processed to meet specified
requirements.
.3
.4
Acceptance of material at source does not preclude future rejection if it fails to conform to
requirements specified, lacks uniformity, or if its field performance is found to be
unsatisfactory.
PART 3 - EXECUTION
3.1
PREPARATION
.1
.2
Topsoil stripping
.1
Do not handle topsoil while in wet or frozen condition or in any manner in which
soil structure is adversely affected.
.2
Begin topsoil stripping of areas as indicated by Engineer after area has been cleared
of weeds and grasses and removed from site.
.3
.4
Prior to excavating materials for aggregate production, clear and grub area to be
worked, and strip unsuitable surface materials. Dispose of cleared, grubbed and
unsuitable materials as directed by Engineer.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
.3
.4
.2
Where clearing is required, leave screen of trees between cleared area and
roadways as directed.
.3
Clear, grub and strip area ahead of quarrying or excavating operation sufficient to
prevent contamination of aggregate by deleterious materials.
.4
.5
Trim off and dress slopes of waste material piles and leave site in neat condition.
Processing
.1
.2
.3
.4
When operating in stratified deposits use excavation equipment and methods that
produce uniform, homogeneous aggregate.
Handling
.1
.5
SECTION 02702
AGGREGATES: LANDSCAPING
PAGE 3 OF 4
Stockpiling
.1
.2
.3
Stockpiling sites to be level, well drained, and of adequate bearing capacity and
stability to support stockpiled materials and handling equipment.
.4
.5
.6
.7
.8
.1
.2
.3
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
3.2
SECTION 02702
AGGREGATES: LANDSCAPING
PAGE 4 OF 4
.9
.10
.11
During winter operations, prevent ice and snow from becoming mixed into
stockpile or in material being removed from stockpile.
CLEANING
.1
Leave aggregate stockpile site in tidy, well drained condition, free of standing surface
water.
.2
.3
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
RELATED SECTIONS
.1
.2
.3
.4
.5
1.2
SECTION 02721
GRANULAR BASE
PAGE 1 OF 4
REFERENCES
.1
.2
ASTM C117-04, Standard Test Methods for Material Finer Than 0.075 mm Sieve
in Mineral Aggregates by Washing.
.2
.3
ASTM C136-05, Standard Test Method for Sieve Analysis of Fine and Coarse
Aggregates.
.4
.5
ASTM D1883-99, Standard Test Method for CBR (California Bearing Ratio) of
Laboratory Compacted Soils.
.6
ASTM D4318-00, Standard Test Methods for Liquid Limit, Plastic Limit and
Plasticity Index of Soils.
.3
.4
1.3
.2
OPSS 1010 - Aggregates - Base, Subbase, Select Subgrade, and Backfill Material
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02721
GRANULAR BASE
PAGE 2 OF 4
.2
.3
Store cement in weathertight bins or silos that provide protection from dampness and easy
access for inspection and identification of each shipment.
Part 2
Products
2.1
MATERIALS
.1
Granular base shall be Granular A as per City of Ottawa Special Provision F-3147
Granular Materials.
.2
Part 3
Execution
3.1
3.2
Check grade of sub-base for conformity with elevations and sections before placing
granular base material.
PLACING
.1
Place granular base after sub-base surface is inspected and approved by Consultant.
.2
.3
.4
Place material only on clean unfrozen surface, free from snow and ice.
.5
Begin spreading base material on crown line or on high side of one-way slope.
.6
Place material using methods which do not lead to segregation or degradation of aggregate.
.7
For spreading and shaping material, use spreader boxes having adjustable templates or
screeds which will place material in uniform layers of required thickness.
.8
Shape each layer to smooth contour and compact to specified density before succeeding
layer is placed.
.9
Remove and replace that portion of layer in which material becomes segregated during
spreading.
3.3
Compact to density not less than 98% SPMDD in accordance with ASTM D698.
.2
Compaction and testing as per Section 01400 Quality Control, Section 02250
Compaction Control and Testing and OPSS 501.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02721
GRANULAR BASE
PAGE 3 OF 4
.3
Shape and roll alternately to obtain smooth, even and uniformly compacted base.
.4
.5
In areas not accessible to rolling equipment, compact to specified density with mechanical
tampers.
.6
Correct surface irregularities by loosening and adding or removing material until surface is
within specified tolerance.
.7
.8
3.4
SITE TOLERANCES
.1
Finished base surface to be within plus or minus 10 mm of established grade and cross
section but not uniformly high or low.
.2
Correct surface irregularities by loosening and adding or removing material until surface is
within specified tolerance.
3.2
PROOF ROLLING
.1
For proof rolling use standard roller of 45400 kg gross mass with four pneumatic tires each
carrying 11350 kg and inflated to 620 kPa. Four tires arranged abreast with centre to centre
spacing of 730 mm.
.2
Obtain approval from Contract Administrator to use non standard proof rolling equipment.
.3
Proof roll at level in granular base as indicated. If use of non standard proof rolling
equipment is approved, Contract Administrator to determine level of proof rolling.
.4
Make sufficient passes with proof roller to subject every point on surface to three separate
passes of loaded tire.
.5
Remove base, sub-base /and subgrade material to depth and extent as directed by
Contract Administrator.
.2
.3
.4
.6
Where proof rolling reveals defective base, remove defective materials to depth
and extent as directed by Contract Administrator and replace with new materials
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02721
GRANULAR BASE
PAGE 4 OF 4
PROTECTION
.1
Maintain finished base in condition conforming to this Section until succeeding material is
applied or until acceptance by Consultant.
END OF SECTION
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
Part 1
General
1.1
SECTION INCLUDES
.1
1.2
SECTION 02723
GRANULAR SUB-BASE
PAGE 1 OF 3
This section includes materials and requirements for granular sub-base only for road
backfill and reinstatement. Refer to Section 02315 Excavating, Trenching, and
Backfilling for pipe bedding and backfill requirements.
RELATED SECTIONS
.1
.2
1.3
REFERENCES
.1
ASTM C136-[96a], Standard Test Method for Sieve Analysis of Fine and Coarse
Aggregates.
.2
1.4
Separate and recycle waste materials in accordance with Section 01355 - Disposal of
Excess Material.
Part 2
Products
2.1
MATERIALS
.1
Granular sub-base material: in accordance with City of Ottawa Special Provision F-3147
Granular Materials.
.1
.2
Part 3
Execution
3.1
3.2
Check graded subgrade for conformity with elevations and sections before placing
granular subbase material.
PLACING
.1
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02723
GRANULAR SUB-BASE
PAGE 2 OF 3
.2
.3
.4
Place material only on clean unfrozen surface, free from snow or ice.
.5
Place granular sub-base materials using methods which do not lead to segregation or
degradation.
.6
Place material to full width in uniform layers not exceeding 150 mm compacted
thickness. Contract Administrator may authorize thicker lifts if specified compaction can
be achieved.
.7
Shape each layer to smooth contour and compact to specified density before succeeding
layer is placed.
.8
Remove and replace portion of layer in which material has become segregated during
spreading.
3.3
Compact to density not less than 98% SPMDD in accordance with ASTM D698.
.2
Compaction and testing as per Section 01400 Quality Control, Section 02250
Compaction Control and Testing and OPSS 501.
.3
.4
.5
Compact to density of not less than 98% corrected maximum dry density.
.6
Shape and roll alternately to obtain smooth, even and uniformly compacted sub-base.
.7
.8
.9
Correct surface irregularities by loosening and adding or removing material until surface
is within specified tolerance.
3.4
PROOF ROLLING
.1
For proof rolling use standard roller of 45400 kg gross mass with four pneumatic tires
each carrying 11350 kg and inflated to 620 kPa. Four tires arranged abreast with centre
to centre spacing of 730 mm maximum.
CITY OF OTTAWA
COMBINED SEWAGE STORAGE TUNNEL
CONTRACT NO. ISD14-2036
SECTION 02723
GRANULAR SUB-BASE
PAGE 3 OF 3
.2
.3
.4
Make sufficient passes with proof roller to subject every point on surface to three
separate passes of loaded tire.
.5
.6
3.5
.1
.2
.3
Where proof rolling reveals areas of defective sub-base, remove and replace in
accordance with this section at no extra cost.
SITE TOLERANCES
.1
3.6
.1
Maintain finished sub-base in condition conforming to this section until succeeding base
is constructed, or until granular sub-base is accepted by Contract Administrator.
END OF SECTION