Beruflich Dokumente
Kultur Dokumente
Environmental Risks
External Risks
Design Risks
Construction Risks
Organizational Risks
Design incomplete
Unexpected geotechnical or
groundwater issues
Resolving objections to Right of Way Change requests due to differing site Project scope, schedule, objectives,
appraisal takes more time and/or
conditions
cost, and deliverables are not clearly
money
defined or understood
Piles driven into fish habitat may require special Right of Way datasheet incomplete
noise attenuation to protect marine species
or underestimated
Changes to
materials/geotechnical/foundation
Lack of coordination/communication
Controversy on environmental
grounds expected
Pressure to deliver project on an
accelerated schedule
Long lead time for utilities caused by Priorities change on existing program
design and manufacture of special
components (steel towers or special
pipe)
Project may encroach into a floodplain or Construction or pile driving noise and
a regulatory floodway
vibration impacting adjacent
businesses or residents
1/3
May 5, 2007
8000
1500
55
42
20
22
12
2
13
7
11
184
65
3.67
29360
6000
3
4
5
6
7
8
9
10
11
12
23,360
24,360
24,360
24,360
24,360
24,360
24,360
24,360
24,360
24,360
162
20
3
2.6
12
20
57.6
6500
0.875
46
42
20
10
20
138
195.6
24
520000
413,733
431,444
431,444
431,444
431,444
431,444
431,444
431,444
431,444
431,444
17.71117
7500
487500
4,296,730
1.5