Updated on :

No

Area

Total Unit

Cement Mill - EE Room

25

Coal Mill

84

Main Substation

39

Raw Material Proportioning - EE Room

14

Raw Mill EE-Room

24

TOTAL CO2 Tanks

162

TOTAL CO2 Tanks (Full)

84

TOTAL CO2 Tanks (In Filling Process)

30

TOTAL CO2 Tanks (Empty)

78

9/9/2015
Status
Already Filled

In Filling
Process

Remaining

25

84

30

14

24

5
In

6
Out

In

Out

30

30

30

means Full CO2 tank arrived

means empty CO2 tank picke

Timeline
7
In
30

8
Out
24

In

9
Out

In

10
Out

In

11
Out

In

12
Out

In

25

25

Out

24
30

ns Full CO2 tank arrived at SJW

ns empty CO2 tank picked up by supplier for filling

30

9
14

21

21

13
In

14

Out