Crack on wall

Dampness
Dampness & Fungus

corrosion

Damage to Brick work/major crack on wall

Deterioration/damage to plaster/ plaster


crack
plaster crack all over the wall

Detoriation of Mortar between brick

Reinforcement is protruding
member is bent

Welding
End connections truss
Detoriation of concrete

Vegetation

Cracks shall be sealed with crack sealant &


kept under observation.
Cause Of Dampness shall be found. It shall
be stopped and then repair work shall be
initiated under technical supervision.
Cause Of Dampness shall be found. It shall
be stopped and then repair work shall be
initiated under technical supervision.
Remove fungus periodically & kept surface
clean & dry.
Corrosion/scaling shall be rubbed with sand
paper/wire brush & primer coat shall be
applied with two coat of Asian make
synthetic enamel shall be applied.
Remove damaged brick work & rework of
brick work shall be initiated under expert
Technical supervision.
Remove affected plaster &replaster work
shall be initiated under technical supervision.
Remove affected plaster &replaster work
shall be initiated by applying chicken mesh
on
affected
portion
under
technical
supervision.
i) Brake the loose plaster pockets.
ii) Apply jet of water & clean the open loose
plaster surface.
iii) Hack the joints & fill it with cement mortar
& curing is done for brick masonry.
iv) Apply one coat of cement slurry for old
brick masonry
iv) Apply two coats (12mm+8mm) water
proof plastering in CM 1:4 for external
surface of wall.
If reinforcement used for future expansion
then shall be embedded in lean concrete
otherwise shall be cut.
Another additional equivalent member shall
be welding overlapping 1m on either side of
the affected area or the bent member shall
be replaced.
Welding Work shall be done properly under
expert technical supervision.
End Connection shall not be embedded in
wall; It shall be open for inspection.
i) Erect temporary steel props in required
position prior to R.C.C restoration to releave
partial loading on the structure.
ii) Carefully exposed the damage concrete
by concrete breaker or by hammer or by
chisel.
iii) After hacking of old concrete & applying
bonding agent NITO BOND, apply micro
concrete-SIKA Grout under technical
supervision.
Vegetation shall be removed & structural
shall be released from over loading.

Reinforcement exposed

Tile

Deterioration plaster

i) Erect temporary steel props in required


position prior to R.C.C restoration to releave
partial loading on the structure.
ii) Concrete Core extraction & determination
of compressive strength shall be done.
iii) Rectification measures shall be suggested
after obtaining NDT results (Core Cutting).
i) Break the old concrete completely in the
affected portion.
ii)Add new reinforcement along the old
reinforcement.
iii) Erect steel props & shuttering in required
position.
iv) Cast new slab in affected area in M20
grade concrete under expert technical
supervision.
i) Erect temporary steel props in required
position prior to R.C.C restoration to releave
partial loading on the structure.
ii) Carefully exposed the damage plaster by
plaster breaker or by hammer or by chisel.
iii) Expose the damage R.C.C member. Clean
the rusted reinforcement with light taping &
wire brushing.
iv) Pasivating the cleaned reinforcement
with rust passivator using rusticide.
v) Apply protective coating to the rust
passivated reinforcement with Polyalk F.P
with 1 part of polyalk F.P mixed to one part f
cement.
vi) Applying bonding coat to the entire
surface with 1 part of Polyalk E.P mixed to
1.5 part of cement. Care should be taken to
apply next coat within 10 minutes.
vii) Applying polymer modified cementations
mortar to the damage R.C.C mortar with
10mm cover to the reinforcement in
proportion of 1:5:15 i.ePolyalk E.P:
cement: quartz sand by weight.
i) Erect temporary steel props in required
position prior to R.C.C restoration to releave
partial loading on the structure.
ii) Carefully exposed the damage concrete
by concrete breaker or by hammer or by
chisel.
iii) After hacking of old concrete & applying
bonding agent NITO BOND, apply one coat
plaster under technical supervision.
After Repair works, Glaze tiles may be
provided to keep the surface clean & free
from algae.
Structural Drawing shall be furnished for
further comment.
Further remedial action can be suggested
after the results of NDT.
i)Break the loose plaster pockets.
ii) Apply jet of water & clean the open
loose plaster surface.
iii) Hack the joints &fill it with cement

Shed extended
Damage AC sheet
Honeycomb on slab,beam,column
Hairline crack
Wind bracing are missing
Expansion joint not properly maintained

Bick work open

mortar & curing is done for brick


masonry.
iv) Apply one coat of cement slurry for
old brick masonry.
iv) Apply two coats (12mm-8mm) water
proof plastering in CM 1:4 for external
surface of wall.
Drawings Shall Be Furnished For Further
Comments.
Remove and replace the AC sheets
Apply rich cement mortar paste (1:2)to fill
the gap of concrete.
After that plaster the surface with (1:4)CM
Cracks shall be sealed with crack sealant :
kept under observation.
It shall be provided according to drawings
Expansion/construction joint is not seen
distinct, joint shall be filled with
thermcol/shalitex board
and sealed externally as per Annexure A.
Provide plaster under expert technical
supervision

Brick work exposed


Deterioration of plaster

Loss not bolt

i) Brake the loose plaster pockets.


ii) Apply jet of water & clean the open loose
plaster surface.
iii) Hack the joints & fill it with cement mortar
& curing is done for brick masonry.
iv) Apply one coat of cement slurry for old
brick masonry
v) Apply two coats (12mm+8mm) water
proof plastering in CM 1:4 for external
surface of wall.
Bolt shall be tighten with proper torque.

Member covered with dust particle

Remove or clean the dust particles.