ENGG
PROJECT SPECIFICATION
REV NO.
DATE
JO/EWO
BASIS OF DESIGN
-ELECTRICAL SYSTEM
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
REVISION CERTIFICATION
DATE: __________
-----------------------------CONTROL NUMBER
BY: ____________
EDSD VERIFICATION
DATE _________
00
28/01/16
MXX
YL
CW
A00
28/09/14
ZSY
YL
CW
Rev
Date
Description
Prep
Chk
App
Proj
SAPMT
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
1
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
CERT
PMT
OPRNS
CERT
ENGG
TABLE OF CONTENTS
DESCRIPTION
1.2 Definitions...........................................................................................11
2
JO/EWO
DATE
REV NO.
3.SCOPE .............................................................................................................20
4 FACILITIES DESCRIPTION .............................................................................22
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
REVISION CERTIFICATION
DATE: __________
-----------------------------CONTROL NUMBER
BY: ____________
EDSD VERIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
2
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
ENGG
DESCRIPTION
JO/EWO
11 MOTORS ........................................................................................................39
DATE
REV NO.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
3
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
CERT
OPRNS
REV NO.
DATE
JO/EWO
DESCRIPTION
AC
DISCIPLINE
ENGINEER
_______________
Alternating Current
AFD
AGR
AOC
ASU
BEDD
BFW
BLD
Buildings
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CADD
CONSTRUCTION
AGENCY
_______________
DATE _________
CCB
CCR
CCW
CGT
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
4
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
ENGG
CERT
OPRNS
Communication Systems
ENGG
Current Transformer
DC
Direct Current
DCS
EAS
ESD
ETAP
FEED
GAC
GEC
GFU
Gasification Unit
GIS
HOC
REV NO.
DATE
JO/EWO
CT
DESCRIPTION
CERT
COM
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
HP
BASIS OF DESIGN
ELECTRICAL SYSTEM
High Pressure
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
5
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
ENGG
HRC
HVAC
HVN
IED
IPR
IRP
ISF
JZR
Jazan Refinery
KSM
LAN
REV NO.
DATE
JO/EWO
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
LP
_______________
Low Pressure
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
LRC
LSTK
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
6
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
CERT
HPU
DESCRIPTION
PMT
OPRNS
Low Voltage
ENGG
MBOD
MCC
MEC
MMS
MOV
REV NO.
DATE
JO/EWO
MBCD
DESCRIPTION
CERT
LV
DISCIPLINE
ENGINEER
_______________
DATE _________
MP
Medium Pressure
OA
Operating Area
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
OAS
OME
ONAF
ONAN
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
OOK
BASIS OF DESIGN
ELECTRICAL SYSTEM
Out of Kingdom
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
7
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
ENGG
OSE
On-Stream Efficiency
P&ID
PCC
PDI
PDS
REV NO.
DATE
JO/EWO
OPR
DESCRIPTION
CERT
OPGW
DISCIPLINE
ENGINEER
_______________
DATE _________
PEECC
PROJECT
ENGINEER
_______________
PF
DATE _________
Power Factor
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
PGB
PIB
ProcessInterfaceBuilding
PPE
PSA
RTU
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
8
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
ENGG
SAMSS
SCADA
SEC
SFC
REV NO.
DATE
JO/EWO
SAES
DESCRIPTION
CERT
SAEP
SS
DISCIPLINE
ENGINEER
_______________
DATE _________
Substation
SSD
STG
STM
SWA
SWA
TNK
Tank Form
UPS
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
9
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
ENGG
VSD
WAN
WTS
WWT
JO/EWO
DATE
REV NO.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
10
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
CERT
VLAN
DESCRIPTION
PMT
OPRNS
CERT
1.DOCUMENT PURPOSE
ENGG
This design basis describes the minimum requirements for the design,
drawings, fabrication, testing and installation of Electrical System.
1.1 Scope
DESCRIPTION
This document applies to the supply and installation of the electrical systems
and equipment used in the Sea Water Unit of the Integrated Gasification
Combined Cycle (IGCC) Project in Jazan, Saudi Arabia.
JO/EWO
1.2 Definitions
COMPANY
CONTRACTOR
SUBCONTRACTOR(S)
VENDOR
WORK
MUST
REV NO.
DATE
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
11
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
SHOULD
WILL
MAY
DESCRIPTION
JO/EWO
DATE
REV NO.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
12
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
SHALL
ENGG
CERT
PMT
OPRNS
CERT
ENGG
This project shall be designed and implemented in accordance with the latest
revision of applicable Saudi Aramco Standards.
DESCRIPTION
REV NO.
DATE
JO/EWO
DISCIPLINE
ENGINEER
_______________
DATE _________
A00-A-DOC-VE722623
A00-P-DOC-VE721940
A00-A-FPP-VA722020
A00-P-E1L-VA721950
A61-P-E1L-VA746200
A61-P-E1L-VA746199
14-SAMSS-531
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
13
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
14-SAMSS-536
15-SAMSS-502
16-SAMSS-502
16-SAMSS-503
16-SAMSS-504
16-SAMSS-506
16-SAMSS-507
16-SAMSS-512
16-SAMSS-513
REV NO.
DATE
JO/EWO
DESCRIPTION
ENGG
CERT
14-SAMSS-533
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
14
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
16-SAMSS-517
16-SAMSS-518
16-SAMSS-520
16-SAMSS-521
16-SAMSS-523
17-SAMSS-004
17-SAMSS-005
17-SAMSS-006
17-SAMSS-007
17-SAMSS-008
REV NO.
DATE
JO/EWO
DESCRIPTION
ENGG
CERT
16-SAMSS-514
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
15
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
17-SAMSS-502
17-SAMSS-503
17-SAMSS-511
17-SAMSS-514
17-SAMSS-515
17-SAMSS-516
17-SAMSS-518
17-SAMSS-520
SAES-O-207
SAES-O-204
SAES-P-100
REV NO.
DATE
JO/EWO
DESCRIPTION
ENGG
CERT
Cathodic Protection
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
REVISION CERTIFICATION
DATE: __________
-----------------------------CONTROL NUMBER
BY: ____________
EDSD VERIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
16
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
SAES-P-101
SAES-P-103
SAES-P-104
SAES-P-107
SAES-P-111
SAES-P-113
SAES-P-114
SAES-P-116
SAES-P-119
SAES-P-121
SAES-P-123
SAES-P-126
REV NO.
DATE
JO/EWO
DESCRIPTION
ENGG
CERT
Criteria
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
17
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
SAES-X-500
SAES-X-600
SAES-J-902
SAES-B-014
REV NO.
DATE
JO/EWO
DESCRIPTION
ENGG
CERT
SAES-X-400
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
2.2 References
OPERATIONS
_______________
This document shall be read in conjunction with the following related project
documents:
REVISION CERTIFICATION
DATE: __________
-----------------------------CONTROL NUMBER
BY: ____________
EDSD VERIFICATION
DATE _________
A00-A-FPP-VA-722020
A00-A-DOC-VE-72223
A00-A-DOC-VE-722624
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
18
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
CERT
A95-A-DOC-VE-541008
A61-A-PID-VA-728820
DESCRIPTION
A61-B-FPS-VA-722745
A61-P-E1L-VA-383359
JO/EWO
A61-S-GAP-VA-745070
Also refer to other applicable P&IDs, line lists, and equipment lists.
DATE
2.3 Language
REV NO.
All documentation shall be in the English language and use the English
(International) dictionary. Language usage disputes shall be resolved by
reference to the Oxford English Dictionary.
DISCIPLINE
ENGINEER
_______________
Equipment warning labels and instruction labels shall be in the English and
Arabic languages.
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
19
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
A00-A-DOC-VE-745698
ENGG
OPRNS
CERT
3.SCOPE
DESCRIPTION
ENGG
The Electrical scope of work for the Sea Water Contract includes the detail
design of the electrical systems in support of the Lump Sum Turn Key (LSTK)
contract. All work shall be in accordance with Saudi Aramco Engineering
Standards and Procedures as identified in this document as well as all the
related documents issued as part of the ITB package.
JO/EWO
3.1 Substations SS-161, all power distribution system and control equipment
downstream of the 132kV incoming cables, including, but not limited to, stepdown power transformers, 13.8kV and 480V switchgears and motor control
centers, panel boards, neutral grounding resistors, power, control, and fiber
optic cables etc.
DATE
3.2 All power and control cabling required for electrical loads within the geographic
limits of the Sea Water Areas.
REV NO.
3.4 Adjustable Speed Drives (ASD) as required and specified by process if needed.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
3.8 Design of the Power System Automation will be as per Section 16 of this
document.
3.9 All interior and exterior lighting systems within the geographic boundary of the
contract including area, street, and roadway lighting.
3.10 Equipment & system grounding systems.
3.11 Power system studies and data.
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
3.12 Protection relay configuration and setting. Setting will be based on the system
study based on the purchased equipment and coordinated with Power System
Contractor (IGC-4).
3.13 Electric Heat Tracing Systems (where identified on the P&IDs)
3.14 Interface and co-ordination with other EPC Contractors during engineering as
per project interface procedures, diagrams and register. This shall include but
not be limited to:
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
20
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
CERT
ENGG
DESCRIPTION
3.15 The Sea Water contract package is comprised of the following major areas
which are identified as the Sea Water System (Unit A61) of the Jazan IGCC
facility. Refer to drawing A61-A-FPP-VA-722037
Cooling Water Inlet Canal
JO/EWO
DATE
REV NO.
Intake Channel
In-Plant Lagoon
Bypass Channel
DISCIPLINE
ENGINEER
_______________
Collection Basin
DATE _________
Discharge Channel
PROJECT
ENGINEER
_______________
Submarine Outfall
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
21
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
DESCRIPTION
The Cooling Water Inlet Canal is an excavated, sheet pile lined, open waterway
directing the gravity and tidal flow of seawater from the Red Sea to the Cooling
Water Inlet Structure. Other than area and roadway lighting and water condition
instrumentation there are no other electrical loads currently identified for the
Cooling Water Inlet Canal.
JO/EWO
DATE
The Cooling Water Inlet Structures are concrete intake structures housing the
inlet trash screens, drum screens, water quality measurement, chemical dosing
and associated maintenance equipment.
REV NO.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
The Intake Channel is a concrete lined, open waterway directing the gravity flow
of treated seawater from the Inlet Pumping Structure to the In-Plant Lagoon.
Other than area and roadway lighting and water condition instrumentation there
are no other electrical loads currently identified for the Intake Channel.
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
The In-Plant Lagoon is a concrete lined, open sea water reservoir which serves
as the source of cooling water for the IGCC facility.
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
The Bypass Channel is a concrete lined, open waterway directing the gravity
flow of excess seawater from the Inlet Pumping Structure directly to the
Discharge Channel. Other than area lighting there are no other electrical loads
currently identified for the Bypass Channel.
4.7 Collection Basin & Discharge Channel
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
22
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
ENGG
4 FACILITIES DESCRIPTION
CERT
OPRNS
ENGG
CERT
The Collection Basin & Discharge Channel are a concrete lined, open
waterways directing the gravity return flow of seawater from the IGCC facility to
the Outfall Pipes. Other than roadway and area lighting and water condition
instrumentation there are no other electrical loads currently identified for the
Collection Basin & Discharge Channel.
DESCRIPTION
REV NO.
DATE
JO/EWO
The Outfall Pipes returning seawater into Submarine pipes for discharge into
the Red Sea.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
23
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
DESCRIPTION
5.2 Normal electric power for the Inlet Areas shall be received at Substation SS-161
via two redundant 132kV underground cables from the Main IGCC Distribution
Substation SS-229.
JO/EWO
5.3 Essential power to Substation SS-161 shall be supplied from IGCC substation
SS-329 at 13.8kV via underground cable to the substation essential transformer
A61-329-XFR(T)-301.
REV NO.
DATE
5.4 Supply, Installation, termination, testing, and commissioning of the normal and
essential power, control, and fiber optic signalling cables shall be by the IGCC
lead power distribution contractor (IGC-4). The design and construction of cable
trench within project boundary of IGC-006 will be done by the Seawater LSTK
contractor (IGC-6).
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
5.5 The essential power in SS-161 will feed an essential MCC via a step down
transformer or a power panel via MCC, a secondary circuit breaker and an
automatic transfer switch.
5.7 The normal position of the automatic transfer switch will be on essential power.
The position can be changed manually to "B" (backup) for maintenance of the
step down transformer or change to back up automatically in case of loss of
power from essential bus and DG's not starting.
5.8 Depending on the start-up time of the diesel generators and availability of power
(to be determined later by IGCC lead power distribution contractor, IGC-4), a
time delay will be incorporated in the automatic operation of the Automatic
Transfer Switch. The change-over time of diesel generator shall be immediately
after max 15 Sec to be loaded at 50% of its rated name plat capacity.
5.9 The essential bus in SS-329 will be powered from the normal power in addition
to power from the 4 diesel generators, 5 MW each. The switchgear will operate
under normal power during the routine operating conditions and will
automatically switch over to generator power during power outage or distress
conditions.
5.10.The back-up power to the essential MCC in substation SS-161 will be provided
by the normal power 480 V switchgear; in case of loss of essential power (DG
failure) or failure of the essential power step down transformer, the power will
automatically switch to back-up power. Refer to the one line diagrams for details.
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
24
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
5.1 For details of the JIGCC electrical system refer to Overall One Line Diagram
A00-P-E1L-VA-721950. For the electrical distribution for the Sea Water System
refer to A61-P-E1L-VA-746200.
ENGG
CERT
OPRNS
ENGG
5.12 A list of all the essential loads will be included in the electrical load list.
DESCRIPTION
5.13 Only secondary selective switchgear shall be used to feed critical loads. The
process loads and especially process critical loads shall be connected to
different MCCs or power sources. There shall be no single point of failure in
the power distribution design.
REV NO.
DATE
JO/EWO
5.14 All Interrupting devices shall be fully rated for the short circuit duty. Low voltage
AC distribution equipment shall be protected by circuit breakers; fuses are not
allowed. Molded case circuit breakers with integral current limiting fuses are
permitted and fuses are permitted for protection of circuits fed from UPS
systems.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
5.15 During motor starting, allowable voltage variation at motor terminal is -15% of
motor nominal voltage. Higher voltage variation (-20% or more) during starting
of large medium voltage motors may be allowed on an individual case basis
with specific approval from ARAMCO. Refer to section 6 of SAES-P-100 for
voltage range. Due consideration shall be given to individual load
characteristics and overall system voltage profile during such approvals.
5.16 The voltage variation is 5% as design basis for normal operation. However,
under exceptional circumstances the maximum over-voltage limit of + 10%
voltage shall not be exceeded for more than 30 minutes.
5.17 All cables, substations and equipment numbering system shall follow Aramco
standard SAES-A-202 and document A00-A-DOC-VE-722624 Revision D2.
Electrical equipment installation in the substation yards shall comply with the
requirements of Section 7 of SAES-P-119.
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
25
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
OPRNS
PMT
5.11 The essential power is part of the black start power for starting the CTGs in the
first power block and it is not intended to provide essential power to any process
loads.
CERT
CERT
5.18.The equipment shall be designed for operation at the voltages listed below:
ENGG
Equipment /
Service
Nominal
Voltage
DESCRIPTION
Nameplate
Voltage
and 230 V, 1- Ph
JO/EWO
Essential lighting
DATE
REV NO.
Instrument and
telecommunication users
120 V, 1-Ph
230 V, 1-Ph
230 V, 1-Ph
DISCIPLINE
ENGINEER
_______________
DATE _________
400 V,
3-Ph/1-Ph
PROJECT
ENGINEER
_______________
DATE _________
480 V, 3-Ph
HVAC
480 V , 3-Ph
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
AC UPS Input:
DATE _________
OPERATIONS
_______________
REVISION CERTIFICATION
AC UPS Output:
DATE: __________
-----------------------------CONTROL NUMBER
BY: ____________
EDSD VERIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
26
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
-----------------------------CONTROL NUMBER
BY: ____________
REV NO.
DATE
JO/EWO
DESCRIPTION
ENGG
CERT
PMT
HZ
BASIS OF DESIGN
ELECTRICAL SYSTEM
JAZAN
125 VDC
DWG. TYPE
DOC
SAUDI ARABIA
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
_______________
CERTIFIED
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
_______________
OPERATIONS
DATE _________
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
27
of
51
00
OPRNS
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
Nominal
System
Voe
Motor
Nameplate
Voltage
Ph
KW (hp)
Type
Notes
120
115
UP TO
0.25 (0.34)
208
200
UP TO
0.25 (0.34)
240
230
UP TO
0.25 (0.34)
208
200
0.18 (0.25)
to 3.7 (5)
Induction
1,2
240
230
0.18 (0.25)
to 7.5 (10)
Induction
480
460
0.18 (0.25)
to 185
(250)
Induction
4,160
4,000
185 (250)
to 3000
(4000)
Induction
4,160
4,000
370 (500)
to 3000
(4000)
Synchronous
3,4
6,900
6,600
750 (1000)
to 6000
Induction,
REV NO.
DATE
JO/EWO
DESCRIPTION
ENGG
CERT
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
28
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
Synchronous
13,200
750 (1000)
to 10500
(14000)
Induction,
Synchronous
13,800
13,200
above
10500
(14000)
Synchronous
REV NO.
DATE
5.20 Cathodic protection will be provided for all underground metal piping, and tank
bases, vessels and equipment in accordance with SAES-X-400, SAES-X-500
and SAES-X-600.
5.21 Heat Tracing shall be provided where required for process purposes.
DISCIPLINE
ENGINEER
_______________
5.22 Ground mat as per SAES-P-111 standard will be provided for substation SS161.
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
29
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
DESCRIPTION
JO/EWO
(8000)
13,800
ENGG
CERT
PMT
OPRNS
DESCRIPTION
6.2 Substation buildings shall have separate rooms for switchgears, batteries, and
HVAC equipment.
JO/EWO
6.3 Substations shall not be located in hazardous areas and will be located away
from the security fence per Saudi Aramco engineering standards.
6.4 No substation doors shall exit into the transformer yard.
REV NO.
DATE
6.5 When the cable bus or cable enters the substation through walls, the entry shall
be with the use of cable transit rated for the application in compliance with
NFPA 251 and classified per UL 1479.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
6.6 Substation fence shall comply with SAES-M-006 and the signs on the fence
shall be as per standard drawing AB-036319 mounted on fence at intervals not
to exceed six (6) meters.
6.7 Battery rooms will be provided with redundant ventilation fans in accordance
with SAES-B-014. Audible and visual alarms will be installed outside the battery
room entrance to annunciate a failure in ventilation for immediate action in
accordance with SAES-P-103.
6.8 Each battery room shall have a storage cabinet equipped with safety equipment
required per SAES-P-103 paragraph 6.9 and accessories as required by
paragraph 15 of 17-SAMSS-511.
6.9 Battery disconnect switches shall be installed in the battery room (see paragraph
6.3.4 of SAES-P-103). Battery disconnect switches shall not be located directly
above the batteries and shall have a minimum horizontal separation of 1.5
meters from the nearest cell.
_______________
REVISION CERTIFICATION
DATE: __________
-----------------------------CONTROL NUMBER
BY: ____________
EDSD VERIFICATION
DATE _________
6.10 Battery rooms shall be provided with enclosed and gasketed (vapor tight)
corrosion resistant lighting fixtures.Lighting fixtures in the battery rooms shall be
installed at least 300 mm below the finished ceiling.
6.11 Fire detection and alarm systems will be designed and installed in accordance
with SAES-B-014.
6.12 Each substation building shall be provided with Annunciation/Monitoring panel
that complies with the requirements of 34-SAMSS-815 and section 5.5 of
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
30
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
6.1 The substation and the substation buildings shall comply with ARAMCO
Standards SAES-P-119 and SAES-M-100. Requirements of Standards SAESM-100, SAES-B-055, and SAES-B-014 shall also be considered in the
substation building design.
ENGG
6 SUBSTATION BUILDINGS
CERT
OPRNS
CERT
SAES-P-119, and installed in the substation. The panel shall be located as near
the main entrance door as practicable.
ENGG
6.13 The annunciator circuits shall be designed to fail safe. As a minimum the status
conditions to be displayed shall follow section 5.5.3 of SAES-P-119.
DESCRIPTION
6.14 Interiors of floor mounted UPS and battery chargers and other digital cabinets
containing power supplies shall be monitored by an addressable high sensitivity
air sampling or point type smoke detection as per the requirements of SAES-B014 section 7.6.
JO/EWO
6.15 Fire detection and alarm system for In-Plant buildings and substations shall
include a listed interior and external local audible alarm and listed external
visual beacon. The visual beacons shall be visible from the patrolling road side.
REV NO.
DATE
6.16 HVAC for substation buildings will be provided in accordance with SAES-K001,SAES-K-002, and SAES-K-100. Substation HVAC shall provide a sufficient
positive pressure to prevent the ingress of dust and sand. Buildings or HVAC air
intake shall not be taken from electrically classified areas. Redundant and
independent HVAC units shall be provided for each substation.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
6.17 The HVAC control panel shall be located in the HVAC mechanical room.
6.18 Each HVAC outdoor condensing unit shall have a disconnect switch installed
within sight of the equipment.
6.19 The following general maintenance considerations shall be applicable for
design of the electrical substations and systems for operation and start up.
Supplier for each piece of equipment shall provide details of specific
maintenance requirements for each supplied item and this shall form an
essential part of the Supplier's Scope of Supply. The equipment shall be
located with sufficient spacing to permit access to all components for normal
maintenance work and complete removal if required. The layout of the facilities
shall permit adequate maintenance access to all mechanical and control
components of the unit.
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
6.20 Each substation shall have remote racking units for each MV/HV switchgear
assembly as required by 16-SAMSS-504 paragraph 20.4.
6.21 Each substation shall have a cabinet for storage of operating and special tools.
Two fire blankets and a basket type splint stretcher shall be located in the same
cabinet.
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
31
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
DESCRIPTION
JO/EWO
DATE
7.1.3 Normal operation will be with both incomers closed and the bus tie circuit
breaker open per section 6.4 of Aramco Standard SAES-P-116. Pad locking
facilities shall be provided per Section 14 of 16-SAMSS-504.
REV NO.
DISCIPLINE
ENGINEER
_______________
DATE _________
7.1.5 The rating of the switchgear shall not be dependent on the forced air system.
The main switchgear bus bar and the switchgear ground bus bar shall have
the same ampacity rating throughout its length. The main switchgear bus bar
shall be insulated for full phase to phase voltage rating. Mating surfaces within
the main circuit shall be silver plated.
PROJECT
ENGINEER
_______________
7.1.6 The spare and space requirement shall be as per Aramco specification.
DATE _________
7.1.7 Space heaters shall not be installed within the switchgear enclosure.
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
7.1.8 Incoming breakers and bus tie breaker shall have individual vertical section.
For the incoming breakers the upper section can be used to house VTs.
7.1.9 A secondary selective transfer scheme will be included in the switchgear
design for the incomers and bus section circuit breakers.
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
7.1.12 Control voltage for all tripping and closing circuits, protective relaying and
metering shall be 125 VDC.
7.2 480V Switchgear
7.2.1 Low Voltage (480 V) switchgears will be in accordance with the requirements
detailed in specifications 16-SAMSS-502.
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
32
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
ENGG
7 ELECTRICAL EQUIPMENT
CERT
OPRNS
ENGG
CERT
7.2.2 The switchgear shall comprise of air insulated, metal enclosed design with
main transformer incomers, bus tie and feeder circuit-breakers. The
switchgear shall interface with Power System Automation and Power
Management System.
DESCRIPTION
7.2.3 A secondary selective transfer scheme will be included in the switchgear for
incomers and tie breaker.
7.2.4 Normal operation will be with both incomer circuit breakers closed and the bus
tie circuit breaker open per section 6.4 of Aramco Standard SAES-P-116.
JO/EWO
7.2.5 Bus tie breaker shall be in a separate vertical section (one high arrangement).
7.2.6 The 480 V switchgears shall feed separate Motor Control Centers.
DATE
7.2.7 The spare and space requirement shall be as per Aramco specification.
REV NO.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
7.3.4 All switching assemblies in 480 V MCC shall be withdrawable except switching
assemblies containing a main circuit breaker rated greater than 225 A can be
fixed mounted.
7.3.5 The main circuit bus systems of Motor Control Center and switchgear shall not
be connected together.
7.3.6 Motor starters shall have isolation and start/stop facilities at the starter. They
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
33
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
shall also have start/stop facilities and indicating lights local to the motor.
ENGG
CERT
7.3.7 Starters associated with process loads shall have stop / start / permissive
facilities from the DCS. These signals will be hard wired between the DCS
interposing panel and the relevant starter. The motor starters shall be
conventional type.
DESCRIPTION
7.3.8 Motors will be streamed so that two motors of the same duty, one running and
one standby will be fed from different buses or MCC.
JO/EWO
7.3.9 Load diversification will be maintained to ensure that removal of a MCC from
service does not adversely affect the operation of the plant.
7.3.10 Control voltage will be 120VAC.
DATE
REV NO.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
DATE _________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
7.5 Transformers
7.5.1 Oil filled transformers shall be in accordance with Material System
Specification 14-SAMSS-531.
7.5.2 If specified, high voltage winding taps for de-energized operation shall be
provided with 2.5% and 5.0% above and 2.5% and 5.0% below the rated
voltage.
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
34
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
ENGG
CERT
7.5.3 When transformers are specified to be furnished with load tap changers (LTC),
it will be on the high voltage winding and provide approximately +/- 10%
automatic adjustment of the low voltage winding voltage, in approximately
5/8% steps with 16 steps above and below the rated voltage.
DESCRIPTION
7.5.4 Transformer will be sized to allow the largest motor to start without the voltage
limits on switchgear, motor terminals and other consumers being exceeded as
per SAES-P-100.
7.5.5 The impedances for transformers shall follow the guidelines of Material
System Specification 14-SAMSS-531, Tables 1 and 2.
JO/EWO
REV NO.
DATE
7.5.7 Transformer Neutral Resistors will be in accordance with IEEE 32, freestanding, sheet steel enclosed of the stainless-steel grid type, short time rated
for 10 seconds.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
7.5.8 No oil containment is required for transformers containing 2500 liters of oil or
less. For all others the oil containment is required and it shall follow the
requirements of section 7.3 of SAES-P-119.
7.5.9 Transformer clearances and fire barriers shall follow the requirements of
section 7.2 of SAES-P-119.
7.5.10 Cables feeding the primary side of transformers at all primary voltages of
13.8 kV will be routed underground in transformer pit area. However, 132 kV
cables, shall run direct underground in their entire length. Conduits will be
installed through the transformer oil containment bund and transformer
foundation in such a manner that the oil containment does not leak.
7.5.11 The conduits shall have sufficient bending radius to accommodate the
bending radius of the transformer primary cables. These conduits shall line up
with the transformer primary connections to allow for straight cable line up with
the primary terminals. The size of the conduit and use of long radius 90
degrees elbows shall facilitate installation and pulling of the cables.
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
7.5.12 Each transformer will be equipped with valve and standard adaptor flange to
interface with future condition monitoring system by others.
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
35
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
DESCRIPTION
8.2 Relay coordination must cover both relay settings and relay configuration,
including Automatic Transfer Schemes and Emergency Transfer Schemes.
JO/EWO
8.5 Remote backup protection will be provided to protect against relay or breaker
failures. Upstream backup protection shall coordinate with downstream
protection over the range of minimum to maximum fault currents.
REV NO.
8.4 Protection zones shall overlap, where feasible, to ensure complete protection at
the zone boundaries.
DATE
DISCIPLINE
ENGINEER
_______________
DATE _________
8.6 The protection schemes for each voltage level shall follow the schemes given in
the project protection and metering drawings. Interlocking and Inter-tripping will
be shown on the Project Protection and Metering drawings.
8.7 All micro processor based protective relays shall comply with IEC 61850.
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
36
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
ENGG
CERT
OPRNS
DESCRIPTION
9.2 Four sets of AC Uninterruptible Power Supply (UPS) system will be installed in
substation SS-161 to serve the critical loads, the four UPS(s) are listed as follows:
JO/EWO
a) A dual standalone UPS system (refer to attached drawing: A61-P-SCM-VA746229_001), 120/208V, 3 phases, 4 wires, 40kVA, 0.5 hours, with vented
(flooded) lead acid (Lead-Calcium) type batteries installed in battery room, and
two separate power distribution panels, mainly supplying the PCS system.
REV NO.
DATE
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
9.4 Each battery bank will be sized for 50% of the total back up time at 100% load.
The UPS voltages shall follow the voltage requirements of Section 5.
9.5 Smoke detection systems shall be installed for UPS and Battery Chargers in
accordance with SAES-B-014.
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
9.6 Per section 6.3.2.a of SAES-P-103, an interlock between the air handling unit
and high rate charging switch shall be provided, such that failure of the air
handling unit shall cause the high rate charging of batteries to stop.
9.7 Per section 6.3.2.b of SAES-P-103, the ventilation system shall be 100%
redundant. Only direct drive exhaust fans shall be used. An interlock with the
ventilation system shall be provided to stop the high-rate battery charging if the
exhaust fan stops.
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
37
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
9.1 The AC UPS systems shall be provided in accordance with SAES-P-103, 17SAMSS-516 and 17-SAMSS-511.
ENGG
9 AC&UPS SYSTEM
CERT
OPRNS
DESCRIPTION
10.2 Direct Current (DC) secure supply systems will be provided for the 13.8 kV
and 480 V Switchgear protective relay power, tripping and closing circuits. If
required, each substations Fire & Gas and PSA systems will also be fed from
substation DC UPS 125 VDC system.
JO/EWO
10.5 The batteries will be vented lead acid type, and to be located in the substation
battery room. The battery will be sized to give a life expectancy of 20 years.
The batteries shall support the connected load for a period of two hours in
substations SS-161.
REV NO.
10.4 The system shall comprise of two 100% chargers and two 50% batteries (per
Clause 5.3.7 of SAEP-P-103) and one common distribution panel.
DATE
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
10.6 Working space of at least 1 meter shall be provided in front of each battery rack
or enclosure.
10.7 Per section 6.3.2.a of SAES-P-103, an interlock between the air handling unit
and high rate charging switch shall be provided, such that failure of the air
handling unit shall cause the high rate charging of batteries to stop.
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
10.8 Per section 6.3.2.b of SAES-P-103, the ventilation system shall be 100%
redundant. Only direct drive exhaust fans shall be used. An interlock with the
ventillation system shall be provided to stop the high-rate battery charging if
the exhaust fan stops.
10.9 The power supply to both chargers will be from essential source in SS-161.
DATE _________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
38
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
10.1 The 125V DC system shall conform to the requirements of SAES-P-103, 17SAMSS-511 and 17-SAMSS-514.
ENGG
10 DC SYSTEM
CERT
OPRNS
CERT
11.1 Motors will be in accordance with SAES-P-113 and 16-SAMSS-502 / 503 / 520.
ENGG
11.2 All motors except AFD system motors designated on electrical load lists will be
suitable for direct on line starting.
11.3 It will be verified that any power cables which have been oversized due to
ampacity or voltage drop issues can be terminated at both ends without the
need for splice boxes either at the field end or the MCC. Splice boxes shall not
be specified without ARAMCO approval.
REV NO.
DATE
JO/EWO
11.4 All motors rated 75kW (100HP) and above shall be equipped with space
heaters. Motor space heaters shall be powered from contactors installed in a
free standing space heater cabinet. The control for each space heater
contactor shall be from a 24VAC source originating from the space heater
cabinet through an auxiliary contact of the motor starter.
11.5 Motor starting studies shall be performed as per the requirements of section
7.5.3 of SAES-P-100.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
11.10 Controls shall include, but not be limited to, motor start, stop, status, fault and
motor in manual selection (available to run) to the DCS control system. For
individual control and indication requirements P&ID drawings will be referred
to. Motors which do not have the local control station adjacent to the motor
shall, in addition, have a hard wired emergency stop button provided
adjacent to the drive, connected directly to the motor control circuit.
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
39
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
11 MOTORS
DESCRIPTION
OPRNS
12.2 All cable and wire conductor sizes will be metric (mm2).
DESCRIPTION
12.3 All threaded cable fittings, including terminators (glands) for metric size cables,
shall have tapered (NPT) threads in accordance with ANSI/ASME B1.20.1.
JO/EWO
12.4 The selection and sizing of cables will be in accordance with ARAMCO
standards. Where a cable is installed by more than one method e.g.
underground and above ground, the cable will be rated for the worst case
condition for any portion of installation greater than 3 meters.
REV NO.
DATE
12.5 All power and control cables in non hazardous and Zone 2 hazardous process
and utilities areas installed on metal tray will be unarmored.
12.6 All power and control cables in Zone 1 hazardous classified areas, where
required, will be armored.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
12.7 All power and control cables installed underground will be armored per
paragraph 5.13 of SAES-P-104. Un-armored cable will be used for cable tray
and conduit systems installations. However, as per exception clause of
paragraph 5.13 of SAES-P-104, if the cable run has transition from direct
burial to cable tray, then the cable will be armored for the entire length.
DATE _________
CERTIFIED
_______________
12.8 All cables will be of consistent construction for the entire length of the cable.
Transition joints are not allowed except for extremely long runs where the
joints cannot be avoided, in agreement with Company.
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
12.9 Cable armoring for single core cables, where required, will be aluminum wire.
The armor will be adequately terminated using proprietary glands and will be
grounded at both ends. The cable will be rated to accommodate circulating
currents.
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
12.10 Non-magnetic gland plates will be used for the termination of single core
cables.
12.11 The inter-tripping, protection, and signaling for the main cable runs will be by
fiber optic cables and installed with the main power cable runs by the main
power distribution contractor.
12.12 Underground cable burial depth shall be according to table 2 of SAES-P-104.
12.13 Where any portion of an underground cable is located in areas where liquid
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
40
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
12.1 All cables will be sized, manufactured and tested in accordance with SAES-P104 and 15-SAMSS-502.
ENGG
CERT
OPRNS
CERT
hydrocarbons or liquid solvents are handled, the cable will be provided with a
lead sheath and single galvanized steel wire armor for multi-core cables and
aluminum wire armor for single core cables.
DESCRIPTION
ENGG
12.14 In general, cables will be installed aboveground in ladder type cable tray
covered with ventilated covers. Flanged type covers shall be secured with
heavy duty wrap around stainless steel band. Cable trays that run vertically in
outdoor areas shall have covers on both sides. The bands shall be installed
every meter and minimum of 6 per cover.
JO/EWO
12.15 Underground routing will be minimized. Where required, cables shall run in
duct bank for road crossings. Duct bank design shall be per section 10.4 of
SAES-P-104.
REV NO.
DATE
12.16 In general, cable entrances into all electrical gear will be by top entry. Cable
entry into instrumentation cabinets will be bottom entry through raised floor.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
12.17 In general cable entrances into buildings shall utilize factory made cable
transits. Cable entrances into substations will be distributed using entries
along the whole length of the substation wall to minimize layering and long
internal runs of cable tray. They shall, as far as practicable, be adjacent to
their associated equipment in the substations.
12.18 When cables or cable buses enter the substations through walls, the entry
shall be with the use of factory made transit systems rated for the application
in compliance with NFPA 251 and classified per UL-1479. Cable trays will be
constructed and cables installed on the trays in compliance with the
installation and safety requirements of NEMA VE1 Cable Tray System and
NEMA VE2 Cable Tray Installation Guidelines or according to manufacturers
recommendations.
DATE _________
CONSTRUCTION
AGENCY
_______________
12.19 Cables installed in vertical runs will be fixed using cable cleats such that the
weight of the cable is supported.
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
12.20 Power and Control cables will be segregated from instrument, signal and
communication cables in accordance with the relevant COMPANY standards.
Power and Control cables will be segregated from Instrument, signal and
communication cables in accordance with code requirements. In general cable
separation shall follow the guidelines of Section 14 of SAES-P-104.
12.21 Cabling associated with critical safety systems passing through fire hazardous
zones will be fire proofed in accordance with SAES-B-006. The fireproofing
shall meet UL1709 fire test procedure for twenty (20) minutes while
maintaining electrical continuity. Cable Trays and/or other supports for such
cables in fire hazardous zones will be made of stainless steel, or otherwise fire
proofed.
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
41
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
ENGG
CERT
12.22 Cable bus will be used for connection of the LV side of transformers to the
switchgear as shown on the single line diagrams and shall be in accordance
with 16-SAMSS-520. Cable bus entry through the walls of the substations
shall be by factory made transitions.
REV NO.
DATE
JO/EWO
DESCRIPTION
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
42
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
DESCRIPTION
JO/EWO
13.3 Building lighting design shall not rely solely on the technical specifications for
this project in order to achieve a suitable overall lighting scheme. Special
attention will be given to the architectural and ergonomic requirements for
lighting in certain special applications, as indicated below.
REV NO.
DATE
13.4 Detail lighting design and selection of light fixtures fittings will be carried out
and approved by Company prior to implementation. The following design
criteria will be carefully considered in the building lighting design:
DATE _________
PROJECT
ENGINEER
_______________
Daylight attributes
Maintenance
Contrast modifications
DISCIPLINE
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
13.5 Substation Building will be illuminated with trough type fluorescent fixtures
which shall have a wrap around type cover or egg crate type grille.
13.6 Battery rooms shall use enclosed and gasketed (vapor tight) lighting fixtures
suitable for the environment where they are installed as per paragraphs 4.2.6
and 4.2.7 of SAES-P-123.
13.7 Lighting circuits inside substation will be fed from different power source or
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
43
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
13.1 Lighting design, installation, fixture selection and illumination lux levels shall
comply with SAES-P-123. All fixtures will be suitably certified for the area in
which they are installed.
ENGG
CERT
OPRNS
ENGG
CERT
DESCRIPTION
13.8 Plant Area, task lighting and street lighting will be in accordance with SAES-P123.
JO/EWO
13.9 Control of the area lighting will be accomplished by photocell with Hand-OffAuto override switches. The area lighting will be operated on a 400/230V, 3
phase, 4 wire 60Hz electrical distribution system, supplied from panel boards
in the adjacent process area Substation.
REV NO.
DATE
13.10 Outdoors, general area lighting will be provided by high intensity, high
pressure sodium floodlights mounted on structures and / or poles.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
13.11 Task lighting will be provided for areas not illuminated sufficiently by the area
lighting. Sufficient plant area/task lighting connected to EDS (emergency
distribution system) will be provided at emergency and critical equipment /
areas for the safe plant shutdown in case of emergency.
13.12 All light fixtures in the process area shall be rated for classified area Class I
division 2, flame proof for consistency.
13.14 Buildings and areas that are to be used by personnel to follow planned
operating and shutdown procedures and to allow safe egress will be provided
by emergency distribution system after loss of the normal power source.
Substations and other buildings shall also be provided with reflective arrows to
show exit direction during lighting failure. Non-essential buildings will have
battery backed up luminaries to allow safe egress.
13.15 Minimum of 30% essential lighting will be provided in all Substation buildings
and PIBs. Emergency lighting will be provided along evacuation routes,
assembly areas and in the Process Plant areas. Normal and emergency task
lighting of at least 200 lux (20fc) will be provided in Plant areas to illuminate
equipment required for use in emergencies including, but not limited to,
emergency telephones, shutdown and emergency isolation stations, fire water
pump areas, central foam concentrate mixing areas, fire control panels and
stand-by generators.
13.16 Substation and other buildings shall be provided with battery back up exit
lights to indicate exit direction during lighting failure.
13.17 Power supply to all outdoor lighting system/fixtures will be switched on/off
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
44
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
CERT
ENGG
13.18 All outdoor lights will be connected to the central blackout switch located in
the CCR as per ARAMCO standard SAES-O-113 and SAES-P-123.
DESCRIPTION
13.19 Single phase 230 Volts, 20A receptacles will be located in plant areas so that
any point in the working area can be reached with a 25m (82 feet) extension
cord. The receptacles in the process areas will be of a construction suitable for
classified area class I division 2.
JO/EWO
13.20 Indoor type receptacles will be installed inside office and buildings in
accordance with ARAMCO guidelines.
REV NO.
DATE
13.21 Welding receptacles will be 480 Volt, 40 kW rated, three phase, 4 wire, 3 pole
plus ground. The receptacles will be of a construction suitable for the area
where it is to be installed. Receptacles will be located throughout the open
areas so that any part of the process areas can be reached with a 30m lead.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
45
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
DESCRIPTION
JO/EWO
14.3 Grid conductors and grounding electrode conductors used for substation grids
shall not be insulated. If conductors are larger than 35mm2 then they shall be
stranded according to SA standards.
REV NO.
DATE
14.4 The electrical grounding system for the entire installation will be based on an
underground earth grid system for each unit area. All equipment and
structures in each unit area will be connected to the area grid. Each area grid
will be connected to adjacent area grid via a test well to prevent any
equipotential difference in the grounding system across the site.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
14.5 The grounding grid conductor size, laying depth, length of each rod etc. will be
as shown on grounding drawing for the sea water project.
14.6 All grounding connections to ground grids, structures, electrical/mechanical
equipment, etc., will be performed as per installation detail drawings.
14.7 The 13.8 kV system will be low resistance grounded via neutral grounding
resistors connected to local dedicated ground electrodes and test wells which
have a solid connection to the plant main ground grid.
14.8 The 480 V and 400/230 Volts electrical system neutrals at each source of
supply will be solidly grounded by means of dedicated ground electrodes and
test well which have a solid connection to the plant main ground grid. Ground
loop impedances shall effect circuit disconnection in a time not exceeding 0.5
second under solid ground fault conditions.
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
14.9 For the grounding of electrical systems, equipment, and structures, each
installation or building shall have one common ground grid connected to at
least two groups of ground electrodes.
14.10 The ground resistance of made electrodes used for system grounding shall
not exceed five (5) ohms per paragraphs 8.2.1 and 8.3.1 of SAES-P-111
14.11 Static grounding and bonding of all electrical equipment and structures shall
ensure that no equipotential difference exists in the grounding system.
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
46
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
14.1 In general, substation and plant grounding shall comply with the requirements
of SAES-P-111.
ENGG
14 GROUNDING
CERT
OPRNS
DESCRIPTION
ENGG
REV NO.
DATE
JO/EWO
14.15 Special attention will be paid to the requirement for the instrument system
grounding for computers and control systems. Computer systems and
instrumentation should be grounded per supplier requirements and tied to
plant ground at one point as required per NEC and meet the requirement of
SAES-J-902
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
47
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
CERT
OPRNS
REV NO.
DATE
JO/EWO
DESCRIPTION
15.2 The following studies shall be performed during detail design phase:
Starting the largest in-plant motor during the normal and contingency
operation.
Grounding study
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
15.3 The design shall include confirmation of equipment sizes and ratings of all
electrical system components such as cable sizing, relay coordination, motor
starting, battery sizing, etc. by performing required system studies and
calculations.
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
15.4 The data for the sea water design shall be shared and coordinated with the
power distribution contractor.
15.5 The PSA network fiber optic cabling will be done by the communications
contractor and according to the drawings produced by the power system
automation contractor.
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
48
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
15.1 Power System studies will be performed during project detail design phase as
per SAES-P-100, using the ETAP software Version 11.1.1
ENGG
15 SYSTEM STUDIES
CERT
OPRNS
CERT
SCH-VE-744360 (7 Sheets), Power System Automation Scope of Work A00P-DOC-VE-721995, and Power System Automation I/O List A00-P-DOC-VE744363.
DESCRIPTION
ENGG
15.8 The PSA shall interface with electrical equipment and IEDs to provide
supervisory control, comprehensive acquisition of operational and nonoperational data, time synchronization and engineering access to the IEDs.
15.9 The PSA shall be designed with redundancy as per SAES-P-126 requirements.
No single failure of a PSA component shall result in loss of communication or
any function of PSA.
REV NO.
DATE
JO/EWO
15.10 The PSA local area network topology shall be parallel redundant or bus ring
or a combination of both topologies to provide a fault tolerant architecture. The
PSA LAN shall be stand alone and isolated from all other network traffic.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
49
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS
DESCRIPTION
REV NO.
DATE
JO/EWO
16.3 This Power System Automation (PSA), including Power Management System
(PMS) and SCADA sub-systems, shall provide the functionality as defined in
the Saudi Aramco standard, SAES-P-126, and as supplemented by Saudi
Aramco specification, 16-SAMSS-513, Power System Automation Philosophy
- A00-P-DOC-VE-721940, Power System Automation Block Diagram A00-PSCH-VE-744360 (7 Sheets), Power System Automation Scope of Work A00P-DOC-VE-721995, and Power System Automation I/O List A00-P-DOC-VE744363.
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
16.4 The PSA shall interface with electrical equipment and IEDs to provide
supervisory control, comprehensive acquisition of operational and nonoperational data, time synchronization and engineering access to the IEDs.
16.5 PSA shall be designed with redundancy as per SAES-P-126 requirements. No
single failure of a PSA component shall result in loss of communication or any
function of PSA.
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
16.6 The PSA local area network topology shall be parallel redundant or bus ring or
a combination of both topologies to provide a fault tolerant architecture. The
PSA LAN shall be stand alone and isolated from all other network traffic.
16.7 An Operator Automation System shall be provided in individual substations for
monitoring and control of the substation electrical equipment. Redundant,
centralized OAS shall be provided in the CCR for overall monitoring and
control of the entire electrical system network (by others). An Engineering
Automation System shall be provided in the CCR for system configuration,
network and security management and engineering access to the IEDs.
16.8 The PSA shall interface with the DCS for the exchange of electrical system
data as defined in project drawings and documents.
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
50
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
16.1 The PSA network fiber optic cabling will be done by the communications
contractor and according to the drawings produced by the power system
automation contractor.
ENGG
CERT
OPRNS
CERT
17 ELECTRICAL INTERFACES
ENGG
All electrical interface points between sea water unit and other EPC
contractors shall be identified in the Interface document.
DESCRIPTION
17.1 All cable tray, grounding, and trenching interface points shall be at the area
boundaries between different EPC contractors. EPC contractors are
responsible for coordination with the neighboring EPC contractor.
JO/EWO
17.2 The interface point for all main power distribution cables will be the cable
connection point at the primary of the main substation transformers. The main
power distribution cables are defined as cables connecting the 132 kV IGCC
GIS switchgear to the process area main substation transformer primaries, etc.
REV NO.
DATE
17.3 The interface point for all the control, signaling, and protection cables related to
the main power distribution shall be at the switchgears. These cables shall run
with the main power cables per the standards. The main power distribution
EPC contractor is responsible for coordinating this effort.
DISCIPLINE
ENGINEER
_______________
DATE _________
17.4 The main power distribution contractor is responsible for the purchase,
installation, termination, and testing of the main power and their associated
control, signaling, and protection cables. Cable raceway, trays, trenches,
supports, etc shall be by each area EPC contractor within their boundaries.
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
-----------------------------CONTROL NUMBER
BY: ____________
DATE: __________
EDSD VERIFICATION
REVISION CERTIFICATION
DATE _________
BASIS OF DESIGN
ELECTRICAL SYSTEM
DWG. TYPE
DOC
SAUDI ARABIA
PLANT
INDEX
DOC.
SHT.
REV.
A61
VE-383332
51
of
51
00
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
OPRNS