Sie sind auf Seite 1von 147

OPTIMISATION OF SEWAGE SLUDGE LOGISTICS

IN
WASTEWATER TREATMENT PLANTS

OYEDUN ADETOYESE OLAJIRE

25th September, 2009

Supervised by: Professor Nilay Shah

A thesis submitted to Imperial College London in partial fulfilment of the requirements for the degree
of Master of Science in Advanced Chemical Engineering with Process Systems Engineering and for
the Diploma of Imperial College

Department of Chemical Engineering and Chemical Technology


Imperial College London
London SW7 2AZ, UK

This piece of work is dedicated to the Almighty


God; the pillar that holds my life, the source of
my strength, the joy of my glory and the hope
of the future.
I also dedicate my thesis report to the memory
of my late Father Prince, Lawrence Ademola
Oyedun whose desire before his death had
always being for me to study abroad.

ii

ABSTRACT
In order to minimize the overall cost incurred in sludge management as well as environmental
impacts of transporting sewage sludge from the wastewater treatment plant to the final
disposal point, there is need for a dynamic multi-period optimisation model that considers the
adequate trade-offs between the treatment costs and transportation costs (distance) to
determine the cheapest final disposal route of sludge from each works.
This thesis presents a linear dynamic multi-period optimisation model that considers the
inventory management of sludge from wastewater treatment to disposal via a 3-echelon
network which includes an export, transfer and final treatment works. The feasibility of the
model was tested using three different scenarios of Yorkshire Water data statistics and the
results were analysed in the report.
Here, a multi-period mathematical model has been developed by discretising the planning
horizon into a number of time periods. The main objective function is to minimise the total
variable costs over all planning time periods consisting of treatment cost of sludge,
transportation cost and inventory costs subject to the capacity constraints, inventory
constraints, and conservation of sludge.
Overall, the multi-period planning problem has been formulated as a linear programming (LP)
model which can help in making strategic inventory management decisions. The cost of the
different optimised variables is given in monthly periods which make it appropriate for
effective sludge logistics planning.

iii

ACKNOWLEDGEMENT
First of all, I give all the glory to the Almighty God who brought me out of the miry clay and
set my feet upon the rock so as to sit among the princes of this world. He gave me the
courage even when my strength failed me, all honour to him.
I would like to express my sincere gratitude to my supervisor Professor Nilay Shah for all his
support and for the great enthusiasm he has always shown for my work. His careful reading
of this thesis has improved its quality considerably.
I would also like to thank Dr Lazaros Papageorgiou (Centre for Process Systems Engineering,
University College London) who assisted in the supervision of this thesis and who helped
with the collection of data for this work.
Special appreciation to the management of Yorkshire Waters for the provision of data for this
thesis. The availability of data had greatly helps in determining the feasibility of the model
proposed in this work and all the assistance rendered are sincerely acknowledged. Special
thanks to Shell Centenary Scholarship Fund and Imperial College Scholarship Board for the
funding of my MSc programme at Imperial College London.
I also want to thank the following PhD students; Songsong Liu (University College London)
and Alexander Dunnett (Imperial College London) for their guidance on the running of the
model for this report and for providing me with valuable comments on the model. In addition
to this, I would like to thank the rest of the staff and my fellow MSc students at the
Department of Chemical Engineering and Chemical Technology for providing the creative
and friendly atmosphere which makes studying a pleasure.
I am greatly indebted to my mother and all members of my immediate family for the love,
support and trust that they have always shown towards me to get to this height. I pray that
you will live long to eat the fruit of your labour. I would like to thank Adedoja Adisa and
Adewale Ige for proof-reading the thesis and providing me with valuable comments.
I would also like to thank my friends, the likes of Popoola Yinka, Raji Adewale, Akinbola
Gbenga, fellow Shell Scholars and PTDF Scholars in Imperial. Who at various stages
contributed towards the successful completion of my programme. All members of the Divine
Grace Baptist Church are also appreciated for at one time or the other adding some virtues to
my life. Special thanks to my fiance Adekiitan for her love and being there throughout my

iv

programme at Imperial College London. Your inspirational and courageous words are greatly
appreciated.
Finally, for everyone who has contributed to my success in one way or the other, I pray that
the labour of your love will never be in vain. (Amen).

TABLE OF CONTENTS

Page

ABSTRACT ............................................................................................................................. iii


ACKNOWLEDGEMENT ........................................................................................................ iv
CHAPTER ONE: INTRODUCTION .................................................................................... 1
1.0

Background .................................................................................................................... 1

1.1

Aim and Objectives ........................................................................................................ 2

CHAPTER TWO: WASTEWATER AND SEWAGE TREATMENT .............................. 4


2.0

Introduction ..................................................................................................................... 4

2.1

Wastewater Treatment Overview ................................................................................... 4

2.1.1

Preliminary Treatment ............................................................................................. 5

2.1.1.1 Screening.............................................................................................................. 5
2.1.1.2 Grit Removal ........................................................................................................ 5
2.1.2

Primary Treatment (Sedimentation) ........................................................................ 5

2.1.3

Secondary (Biological) Treatment........................................................................... 6

2.1.4

Final Settlement ....................................................................................................... 6

2.1.5

Tertiary Treatment ................................................................................................... 7

2.2

Sewage Sludge Treatment and Disposal Options ........................................................... 7

2.2.1 Sewage Sludge Treatment ............................................................................................. 8


2.2.1.1 Sewage Sludge Thickening .................................................................................... 8
2.2.1.2 Sewage Sludge Dewatering .................................................................................... 8
2.2.1.3 Sewage Sludge Drying. ...................................................................................... 10
2.2.1.4 Sludge Storage ................................................................................................... 13
2.2.3

Sewage Sludge Disposal Options .......................................................................... 13

2.2.3.1 Agricultural Use of Sewage Sludge ................................................................... 13


2.2.3.2 Land-Filling Method of Disposal....................................................................... 14
2.2.3.3 Dumping of Sewage Sludge into the Sea ........................................................... 14
2.2.3.4 Disposal of Sewage Sludge through Incineration .............................................. 15
2.3

Incineration .................................................................................................................. 16

CHAPTER THREE: LITERATURE REVIEW................................................................. 19


3.0

Overview of Logistics .................................................................................................. 19

3.1

Existing Models on Waste Management Logistics ...................................................... 19

vi

3.2

Existing Models on Sewage Sludge Logistics ............................................................. 22

CHAPTER FOUR: MODEL FORMULATION ................................................................ 26


4.0

Problem Statement ....................................................................................................... 26

4.1

Mathematical Formulation ........................................................................................... 27

CHAPTER FIVE: YORKSHIRE WATER CASE STUDIES ........................................... 39


5.0

Introduction .................................................................................................................. 39

5.1

Works at Yorkshire Water ........................................................................................... 40

5.2

Distances between Works ............................................................................................ 41

5.3

Monthly Variations in Production of Sludge at Export Works .................................... 42

5.4

Loss Fraction of Dry Solid Retained at Transfer Works.............................................. 43

5.5

Inventories of Sludge at Different Works .................................................................... 44

CHAPTER SIX: RESULTS AND DISCUSSION............................................................... 45


6.0

Introduction .................................................................................................................. 45

6.1

Scenario One: Transfer Check. .................................................................................... 45

6.1.1

Transfer Check 1 ................................................................................................... 45

6.1.2

Transfer Check 2 ................................................................................................... 49

6.2

Scenario Two: Model Test. .......................................................................................... 51

6.2.1

Model Test 1 .......................................................................................................... 51

6.2.2

Model Test 2 .......................................................................................................... 55

6.3
6.3.1
6.3

Scenario Three: Final Cost Check. .............................................................................. 59


Final Cost Check ................................................................................................... 59
Model Summary ........................................................................................................... 63

CHAPTER SEVEN: CONCLUSION AND RECOMMENDATIONS............................. 64


7.0

Conclusion ................................................................................................................... 64

7.1

Recommendations for Further Work ........................................................................... 65

REFERENCES....................................................................................................................... 66
APPENDICES ......................................................................................................................... 71

vii

LIST OF TABLES

Page

Table 2.0: Incineration Use in Some Advance Countries of the World ................................. 16
Table 5.0: Monthly variations of sludge production ................................................................ 43
Table 6.0: Results for Transfer Check 1 (Scenario one). ......................................................... 46
Table 6.1: Results for Transfer Check 2 (Scenario one). ......................................................... 49
Table 6.2: Results for Model Test 1 (Scenario two). ............................................................... 52
Table 6.3: Results for Model Test 2 (Scenario two). ............................................................... 55
Table 6.4: Results for Final Cost Check (Scenario three). ...................................................... 60
Table 6.5: Model Statistics for the Three Scenarios. ............................................................... 63

viii

LIST OF FIGURES

Page

Figure 2.0: Typical stages in the conventional treatment of sewage ......................................... 4


Figure 2.1: Schematic representation of sludge transformation from wastewater
to disposal. .............................................................................................................. 7
Figure 2.2: Incineration Plant with an Energy Recovery Unit................................................. 18
Figure 4.0: System Structure at Yorkshire Water .................................................................... 27
Figure 5.0: Yorkshire Water Region showing Operational boundaries for water
and sewerage services ........................................................................................... 39
Figure 5.1: Schematic representation of possible links between works .................................. 41
Figure 6.0: Monthly Total Variable Costs for Transfer Check 1 (Scenario one). ................... 47
Figure 6.1: Monthly Treatment Costs for Transfer Check 1 (Scenario one). .......................... 47
Figure 6.2: Monthly Transportation Costs for Transfer Check 1 (Scenario one). ................... 48
Figure 6.3: Monthly Inventory Costs for Transfer Check 1 (Scenario one). ........................... 48
Figure 6.4: Monthly Total Variable Costs for Transfer Check 2 (Scenario one). ................... 50
Figure 6.5: Monthly Treatment Costs for Transfer Check 2 (Scenario one). .......................... 50
Figure 6.6: Monthly Transportation Costs for Transfer Check 2 (Scenario one). ................... 50
Figure 6.7: Schematic representation of Optimised path for Transfer Check
(Scenario one). ...................................................................................................... 51
Figure 6.8: Monthly Total Variable Costs for Model Test 1 (Scenario two). ......................... 53
Figure 6.9: Monthly Treatment Costs for Model Test 1 (Scenario two). ................................ 53
Figure 6.10: Monthly Transportation Costs of Cake Sludge for Model Test 1
(Scenario two). ...................................................................................................... 54
Figure 6.11: Monthly Transportation Costs of Wet Sludge for Model Test 1
(Scenario two). ...................................................................................................... 54
ix

Figure 6.12: Monthly Inventory for Model Test 1 (Scenario two). ......................................... 55
Figure 6.13: Monthly Total Variable Costs for Model Test 2 (Scenario two). ....................... 56
Figure 6.14: Monthly Treatment Costs for Model Test 2 (Scenario two). .............................. 57
Figure 6.15: Monthly Transportation Costs of Cake Sludge for Model Test 2
(Scenario two). ...................................................................................................... 57
Figure 6.16: Monthly Transportation Costs of Wet Sludge for Model Test 1
(Scenario two). ...................................................................................................... 58
Figure 6.17: Monthly Inventory for Model Test 2 (Scenario two). ......................................... 58
Figure 6.18: Schematic representation of Optimised path for Model test (Scenario two).......59
Figure 6.19: Monthly Total Variable Costs for Final Cost Check (Scenario three). ............... 61
Figure 6.20: Monthly Treatment Costs for Model Final Cost Check (Scenario three). .......... 61
Figure 6.21: Monthly Transportation Costs of Cake Sludge for Final Cost Check
(Scenario three). .................................................................................................... 62
Figure 6.22: Monthly Transportation Costs of Wet Sludge for Final Cost Check
(Scenario three). .................................................................................................... 62
Figure 6.23: Monthly Inventory for Final Cost Check (Scenario three).................................. 63

CHAPTER ONE: INTRODUCTION


1.0

Background

Sludge is inevitably generated during both the water and sewage treatment processes. An
estimated 0.7 billion tonnes (wet) of sewage sludge is generated annually in sewage sludge
treatment plants worldwide. The sewage sludge is buried in landfills, incinerated, applied to
agricultural land, or dumped into the ocean (Takada H. et al, 1994).
In 2007/2008, 250,000 tonnes dry solids of sludge was produced by Thames Water as
presented on their website, 150,000 tonnes dry solids of sludge by Yorkshire Water and BBC
reported in 2005 that more than 110,000 tonnes of sewage sludge were produced by Scottish
Water each year. This shows a significant increase in the amount of sludge generated in the
UK and the need for proper and acceptable disposal option remains a challenge for most
wastewater treatment companies.
The handling of sewage sludge is one of the most significant challenges in wastewater
management. Sewage sludge generation and disposal is increasingly becoming a global issue
not only due to the rate of production of the sludge as a result of regulations for proper
treatment of effluents before discharge to water bodies but also due to the need for cost
effective and environmental friendly methods of disposal.
Many studies had been carried out on the different methods of sludge disposal. The methods
of sewage sludge disposal ranges from sea disposal, land filling, use in agriculture and
incineration among others. The incineration method which was highly criticised in the past
due to the cost and environmental impacts is now gaining recognition around the globe due to
the possibility of energy recovery from the process and the possibility of producing refined
flue gas from the process which is not harmful to the environment. Thames Water in
2007/2008 sent 37% of the sludge generated to the incineration plant and it was used to
generate 56GWh of renewable energy at their two incinerator plants in East London (Thames
report, 2008). Incineration is also been preferred as a favourite method of sludge disposal to
landfill and agricultural use due to limited land mass area and its effect on the crop
production due to uptake and also lead to the transfer of heavy metals to human beings
through plants and animals (Korentajer, 1991).

Introduction

Sewage sludge transportation from the wastewater treatment plant to the final disposal site is
a major economic issue for the wastewater company. Depending on the distance,
transportation costs can be the largest decisive cost factor for an alternative final route for
treated sludge. Issues of logistics involved in the transportation of sewage sludge can pose a
great problem for the company.
The choice of disposal route for treated sludge can be greatly influenced by three main
factors which are: distances between works, treatment costs at each works and the types of
sludge intake at each works. The distances between the works will subsequently determine
the transportation costs.
Logistics involved in sewage sludge transportation therefore includes consideration of the
sludge processing capacity at all treatment sites, the treatment cost involved for each type of
sludge at each sites, environmental impacts, inventories, vehicle capacity at each sites,
distances between sites, rate of production of the sludge, the percentage of dry solid of sludge
and so on.
In order to minimize the overall cost incurred in sludge management as well as environmental
impacts of transporting sewage sludge from the wastewater treatment plant to the final
disposal point, there is need for a dynamic optimisation model that considers the adequate
trade-offs between the treatment costs and transportation costs (distance) to determine the
cheapest final disposal route of sludge from each works.

1.1

Aim and Objectives

The aim of this project is to develop a robust dynamic optimisation model for sewage sludge
logistics that will dictate how well the transportation can be run while considering the
production profile, sludge drying, environmental impacts, storage capacity, planned
shutdown, system stability and the inventories.
The objectives of this project include;

Detailed study of the Yorkshire Water static model

Development of a linear dynamic optimisation multi-period model that will consider the
inventory management of sludge at export, transfer and final treatment works

Introduction

Application of the dynamic model to three example problems of Yorkshire Water to


explore the feasibility of the model and generate route that produces the least optimised
cost.

CHAPTER TWO: WASTEWATER AND SEWAGE TREATMENT


2.0

Introduction

Wastewater is not just sewage. From the standpoint of source of generation, wastewater may
be defined as a combination of liquid or water carried wastes removed from residences,
institutions, commercial and industrial establishment together with such groundwater, surface
water and storm water as may be present (Metcalf and Eddy Inc., 1991). Therefore all the
water used in the home or industries can be referred to as wastewater. Examples of these will
include water from showers, toilets, baths, washing machines and dishwashers.

2.1

Wastewater Treatment Overview

Raw sewage is treated in the wastewater treatment plant and the overview of the steps
involved is as treated below;
Raw Sewage

Screening
Large Solids for disposal

Preliminary
Grit Removal

Dense solids for disposal

Primary Sedimentation
Secondary

Sludge

Biological Oxidation

Treatment

Sludge
Secondary Sedimentation
Sludge
Tertiary Treatment

Liquid Effluents to discharge


To sludge Treatment
Figure 2.0: Typical stages in the conventional treatment of sewage. Source: Metcalf and
Eddy Inc. (1991)

Wastewater and Sewage Treatment

2.1.1 Preliminary Treatment


When sewage has been delivered, via the sewers, to the treatment plants, it is given
preliminary treatment to remove the larger floating and suspended solid matter, grit and also
much of oil and grease content if present in an appreciable amount.

2.1.1.1

Screening

It is important to remove the larger floating and suspended matter, which mainly consists of
large solids (plastics, rags, woody material, paper and faecal matter) in the early stages of
sewage treatment. If these materials are not removed, according to Bolton and Klein (1971)
they would cause damage to pumps and other mechanical equipment and might block pipes,
valves and channels. The method used in removing gross solids in sewage sludge is by
passing the sewage through screens.
In the past, screening was only used to remove large solid material so as to protect
downstream operations. Recently, much finer screens are commonly employed to remove
smaller inert solids. The retained material is usually washed to remove faecal matter and then
compressed for disposal to landfill or to an incinerator (EUWFD).

2.1.1.2

Grit Removal

Inorganic gritty matter, or detritus as it is often called, originating mainly from road runoff
must be removed from sewage in the early stages of treatment, as its abrasive action would
also cause damage to pumps and other mechanical equipment (Bolton and Klein, 1971).
These materials are removed by sedimentation in grits or detritus tanks. The retained solids
are therefore removed and then sent to landfill for disposal.

2.1.2 Primary Treatment (Sedimentation)


After gross solid matter, grit and excessive amounts of oil and grease have been removed
from the sewage, the next step is to eliminate as much as possible of the remaining suspended
solid matter, so as to reduce the strength of the sewage and to make it more amenable to
biological oxidation (Bolton and Klein, 1971).

Wastewater and Sewage Treatment

Sedimentation is the most practical and economical method of removing suspended solid
matter from the sewage and efficient removal of the suspended solid matter by sedimentation
is one of the cheapest means of reducing the strength of the sewage (Bolton and Klein, 1971).
The sewage passes into large sedimentation tanks and is allowed to settle for a period of
time. Most of the solids settle to the bottom of the tanks and form a watery sludge, known as
primary sludge, which is removed for separate treatment. The sewage remaining after
settlement has taken place is known as settled sewage (EUWFD).

2.1.3 Secondary (Biological) Treatment


Settled sewage from the primary treatment tank then flows to an aerobic biological treatment
stage where it comes into contact with micro-organisms which remove and oxidise most of
the remaining organic pollutants (EUWFD).
At smaller works, the biological stage often takes the form of a packed bed of graded mineral
media through which the sewage trickles and on the surfaces of which the micro-organisms
grow. At larger plants, the sewage is mixed for several hours with an aerated suspension of
flocs of micro-organisms (known as the activated sludge process) (Bolton and Klein, 1971).
As well as removing most of the polluting organic matter, modern biological treatment can,
where necessary, remove much of the nitrogen and phosphorus in the sewage, thus reducing
the nutrient load on the receiving waters.

2.1.4 Final Settlement


Following secondary (biological) treatment, the flow passes to final settlement tanks where
most of the biological solids are deposited as sludge (secondary sludge) while the clarified
effluent passes to the outfall pipe for discharge to a watercourse. In the case of the activated
sludge process, some of the secondary sludge is returned to the aeration tanks for further
contact with the sewage. The secondary sludge from biological treatment also requires
separate treatment and disposal and may be combined with the primary sludge for this
purpose (EUWFD).

Wastewater and Sewage Treatment

2.1.5 Tertiary Treatment


In circumstances where the highest quality of effluent is required, a third (tertiary) stage of
treatment can be used to remove most of the remaining suspended organic matter from the
effluent before it is discharged to a watercourse. Tertiary treatment is effected by sand filters,
mechanical filtration or by passing the effluent through a constructed wetland such as a reed
bed or grass plot (EUWFD).

Figure 2.1: Schematic representation of sludge transformation from wastewater to


disposal.

2.2

Sewage Sludge Treatment and Disposal Options

Sewage sludge can be referred to as any solid, semisolid, or liquid waste that settles to the
bottom of sedimentation tanks (in wastewater treatment plants or drinking water treatment
plants) or septic tanks. The treatment of wastewaters invariably produces a residual which
must be disposed of into the environment. Most often this residual is a semisolid, odoriferous,
unmanageable and dangerous material commonly termed sludge (Vesilind, 1979).
7

Wastewater and Sewage Treatment

Sewage sludge is a by-product of wastewater treatment, which contains around 3% of solids


and 97% water (Larson, 1988).
Approximately 5.4 million metric tonnes of dry sewage sludge are generated annually from
about 12750 public owned treatment works (POTW) in the US (Outwater, 1994), while the
average sludge production in the Europe is 0.090kg dry sludge per person per day in
European countries (Brestal et al, 1998).

2.2.1 Sewage Sludge Treatment


There are many methods for treating sewage sludge to reduce the overall volume, but nearly
all are devoted either to reducing the carbon content or the water content (or possibly both).
Since the water content of the produced sewage sludge from the wastewater treatment is very
high, the treatment of the sludge will be based majorly on reducing the water content and the
methods of sludge dewatering and sludge drying will be effective in doing that.

2.2.1.1 Sewage Sludge Thickening


The solids content of primary, activated or mixed sludge varies considerably, depending on
the characteristics of the sludge, the sludge removal and pumping facilities, and the method
of operation (Metcalf and Eddy Inc., 1991). Sludge thickening produces a concentrated
product that retains the properties of a liquid. The product of sludge thickening often contains
5-6% solid material by weight.
Thickening is generally accomplished by physical means including gravity settling, floatation,
centrifugation and gravity belts.

2.2.1.2 Sewage Sludge Dewatering


The effect of moisture content on the sludge volume is enormous, and sludge handling
techniques are directed toward reducing the moisture content and hence the volume of the
sludge to be disposed. Dewatering as stated by Werther and Ogada (1999) is the prerequisite
for the further treatment of sludge, as well as handling, transporting and disposal. The higher
the dewaterability of the sludge, the larger the amount of water abstracted during mechanical
dewatering and a higher amount of dry solids (DS) will be achieved.

Dewatering of sludge is required for most methods of sewage sludge disposal. In composting,
it is required to improve airflow and texture, in incineration, it is required to reduce fuel
8

Wastewater and Sewage Treatment

demand and in landfills, it is required to reduce leachate production at the landfill site
(Turovskiy and Mathai, 2006).
Stavropoulos (2004) stated that as far as incineration of sludge is concerned, a high level of
sludge dewaterability provides two benefits. The first benefit is that with a higher dry solid
content after mechanical dewaterability, thermal drying will require less energy (heat input)
to reach the desired autothermic DS content in the sludge. The second benefit is that overall,
a higher amount of water can be extracted by both mechanical dewatering and thermal drying,
which means that less energy will be demanded by the incineration process to burn the dried
sludge.

The moisture associated with flocs of sewage sludge is: 70 75% free water, 20 25% floc
water and 1% each capillary and bound water. The free water can be removed by thickening.
The floc water is trapped in the interstices of floc particles and is separable only by
mechanical dewatering. The capillary moisture can be removed mechanically only after
chemical conditioning, whereas the bound moisture is separable only through cell destruction
McGhee (1991).

Prior to sludge dewatering, the digested sludge is usually conditioned to generate flocs that
are easy to filtrate. Chemical conditioning using polyelectrolytes; Fe(III), Fe(II), lime, or
Al(III), is the most common method (Guohua et al, 2002). The chemicals act as either
coagulant by reducing the zeta potential of the solid particles or flocculants through the
bridging effect to form proper-sized flocs. Chemical conditioning results in coagulation of the
solids and the release of the water (Metcalf et al., 1991). The quantity of chemicals required
for this is small (8-10 mg/kg d.m) as stated by Werther and Ogada (1999) and therefore does
not affect the quantity of sludge produced. Sludge incineration ash, fine sludge particles or
coal can also be used as additives for sludge conditioning.
Metcalf et al. (1991) state the main properties of the sludge that determine the amount and
type of chemical to be used, these are: sludge source, solids concentration, age, pH and
alkalinity. Sludge sources include primary sludge, waste activated sludge and digested sludge.
The pH and alkalinity may affect the performance of the conditioning agents, in particular the
inorganic conditioners. The method of dewatering also affects the selection of the
conditioning chemical because of the differences in the mixing equipment used. For example,
9

Wastewater and Sewage Treatment

polymers are used particularly in centrifuge and belt press dewatering systems and less
frequently in vacuum and pressure filters.
The most ideal case to determine the quantity and the type of conditioning agent to be used
prior to mechanical dewatering is to conduct laboratory or pilot scale tests, especially in cases
where the sludge is difficult to dewater (Metcalf et al., 1991).
There are many equipment and technologies used in the dewatering of sewage sludge. Some
of the equipment used include;

Vacuum Filters: These are the earliest mechanical devices employed for the sludge
dewatering. Their use has declined due to different improvements to alternative
mechanical dewatering equipment. The major disadvantages of this method of
dewatering as stated by Metcalf et al (2005) includes; system complexity, high operating
and maintenance costs.

Belt Filter Presses: These are continuous feed sludge dewatering devices that involve the
application of chemical conditioning, gravity drainage and mechanically applied pressure
to dewater sludge. These presses produced a continuous sludge cake at about 25 35%
DS (CIWEM, 1999). The belt filter press operates at a continuous mode and at low
pressures giving reasonable dewatering results.

Centrifugal Dewaterers: This operates at a continuous mode and use the centrifugal force
developed by spinning a bowl or basket to separate the sludge solids from the liquids.
There are three types of centrifugal devices: disc, basket and solid bowl centrifuges, with
the latter being the most common. As stated by Metcalf et al (1991) new designs of solid
bowl centrifuges can be used to achieve dry solid content of up to 35%. Solid bowl
centrifuges are also called decanter centrifuges and their main advantage to other
dewatering devices is that it requires a much smaller footprint and also it can be installed
in the open.

Other equipment includes: Plate and Frame filters presses and High pressure dewaterers

2.2.1.3

Sewage Sludge Drying.

After dewatering of sewage sludge, one may need to find out whether it is necessary to dry
the sludge since thermal drying of the sludge will add to the operating cost of the treatment
plant. The necessity of sludge drying is connected with the types of water in sludge.
According to Flaga (2005), water present in sludge may be of the following types:
10

Wastewater and Sewage Treatment

Water between pores (unbound) that is subordinate to gravity force and can be easily
removed from sludge by gravity settling (thickening);

Free capillary water, held in sludge by adhesion and cohesion forces, that is readily
removed from sludge by mechanical dewatering without using chemicals; e.g in
centrifuges where centrifugal force (inversely directed) opposes capillary force and
helps to get rid of capillary water;

Physically half-bound water, that is bound inside flakes of sludge;

Bound water
-

biological intracellular form, it is a part of the cells of living organisms present


in sludge, bound by molecular forces to the constant phase of sludge;

chemically intercellular form, it is a part of the crystals lattice of molecules of


the constant phase of sludge;

physically in colloids, bound by the surface tension present on the border of


phases.

The essence of stating the state of water present in sludge is to show that the only means of
removing biologically bound water from sludge is drying (thermal) (Flaga, 2005) and this
also confirms that dewatering processes are no longer sufficient to cope with the still growing
amounts of sludge or to reach the required standards.
Irrespective of the method of disposal or reuse of sewage sludge, the main goals of thermal
drying as stated by Flaga (2005) are:
-

to eliminate water from sludge and diminish volume of sludge (approx. 4-5
times) in order to make the transportation cost lower and the sludge storage
easier;

to increase sludge calorific value, so that sludge could easily be incinerated


without additional fuel;

to make sludge hygienic (without pathogenic organisms);

to stabilize sludge (which is achieved by drying sludge to the sludge dry mass
above 90% of dry solids).

Therefore, if the water content in sludge has to be diminished to minimum (approximately


90% of dry solids) or if there is a need to get moisture removal higher than is guaranteed by
mechanical dewatering, then thermal drying is necessary because thermal drying of sludge
removes water from sludge to significantly higher degree than the best dewatering processes.
11

Wastewater and Sewage Treatment

As stated by Flaga (2005), when taking into consideration a wide range of sludge thermal
utilization methods (e.g. incineration), sludge drying should be treated not only as a necessity
but also as an integral process.
The trend of drying dewatered sludge in sewage treatment plants is motivated by ascending
disposal cost and more stringent regulations. The product of the drying process generally
contains water content lower than 10% and with one-fourth of the original volume. This
significantly reduces the transportation cost to distant landfill and disposal fee. Besides, the
dried biosolids can be utilized as marketable fertilizer for soil conditioning or as alternative
fuel for co-generation (Viraj & Chan, 2005).

The different sludge drying process was explained extensively by Viraj De Silva and Chan,
Kwan Kin in their paper Overview of current sludge drying process (2005). They analysed
the three major types of sludge drying technology which include; thermal drying, solar
drying, and non-thermal drying.
Thermal dryer dries wet sludge by direct, indirect, or combined process. Direct thermal dryer
employs hot gas as the drying media. Hot gas is injected to the drying chamber and removes
moisture from sludge by convection. Indirect dryer dries sludge by conduction. The drying
media (e.g. hot gas or oil) is separated from sludge by heat conducting surfaces which dries
sludge through the agitation process. The combined type of thermal dryer utilized both
convection and conduction method. A thermal dryer is usually compact in size and it
provides consistent dried products. The high energy and maintenance cost are the major
disadvantages of thermal dryers (Viraj and Chan, 2005).
Solar dryer utilized solar energy as the exclusive energy provider in the drying process. A
greenhouse-like enclosure is used to contain the drying bed for odour reduction. An electric
mole is functioned as a tilling device to agitate the sludge layer to promote drying. The
environmental conditions including humidity and ventilation within the drying bed and the
motion of electric mole are controlled by microprocessors. The solar drying bed has the
advantages of low capital and operating cost. It has a limited amount of machinery and the
energy cost is insignificant compare to thermal dryers. However, the drying process is
heavily relied on the humidity difference between the environment and the sludge. The dried

12

Wastewater and Sewage Treatment

product quality may vary even with the optimization of microprocessor. This technology may
not be practical in the area with lots of precipitation (Viraj and Chan, 2005).
Non-thermal dryers are a relatively new technology which removes moisture by accelerating
the wet sludge and injected to a series of cyclones and conditioning chambers. This design
has the advantages of space saving and the product is independent of environmental
conditions (Viraj and Chan, 2005).

2.2.1.4

Sludge Storage

In any sewage sludge treatment plant, there should be the inclusion of the sludge storage
compartment where dried sludge can be stored. This is necessary especially if the end-use of
the sewage sludge is for incineration in which it will be transported in batches to the
incineration plant.
The storage compartment conditions must prevent the dried sludge from absorbing moisture
from the environment so as not to get damped. Flaga (2005) stated that they can be stored in
silos under the cover of gaseous nitrogen that prevents it from self-ignition.

2.2.3 Sewage Sludge Disposal Options


There are many disposal options for sewage sludge and all the different options will be
briefly discussed, even though some are being phased out.

2.2.3.1

Agricultural Use of Sewage Sludge

Sewage sludge can be applied to land to serve as a fertilizer and soil conditioner. Werther and
Ogada (1999) stated that communal sludge shows good fertilizer properties based on its
nitrogen and phosphorus content. They also stated further that sludge recycling as fertilizer
has several advantages which include the return of the organic materials into bio-cycle and it
also replaces the application of artificial fertilizers whose production requires a lot of energy
and CO2.
In the nineties (1990 -1994) as stated by Hall and Dalimier (1994) and McGhee (1991), the
application of sludge in agriculture used 60% of the sludge produced in France, 54% in
Denmark, 50% in Spain, 44% in UK and 26% in USA. This use of sewage sludge seems to
be the best method of disposal at first sight but a lot of setbacks had made it to be otherwise.
Analyses by Korentajer (1991) shows that the average content of heavy metals in municipal
13

Wastewater and Sewage Treatment

sludge is higher than the average for most farming soils which implies that uncontrolled
addition to the agricultural land may increase the concentration of heavy metals in the
farmland. This could have an effect on the crop production due to uptake and could also lead
to the transfer of heavy metals to human beings through plants and animals.
Due to the issue of heavy metals present in sludge and other environmental factors, the
European Commission stated the conditions in which sewage sludge must meet in order to be
used as fertilizers (agricultural use) as stated in the Directive 86/278/EEC and in a way
regulates the indiscriminate use so as to prevent or reduce its deleterious effects on the
biosphere. The directives prohibit the use of untreated sludge on agricultural land unless it is
injected or incorporated into the soil. Treated sludge is defined as having undergone
"biological, chemical or heat treatment, long-term storage or any other appropriate process so
as significantly to reduce its fermentability and the health hazards resulting from its use". To
provide protection against potential health risks from residual pathogens, sludge must not be
applied to soil in which fruit and vegetable crops are growing or grown, or less than ten
months before fruit and vegetable crops are to be harvested. Grazing animals must not be
allowed access to grassland or forage land less than three weeks after the application of
sludge (Europa). The Directive also requires that sludge should be used in such a way that
account is taken of the nutrient requirements of plants and that the quality of the soil and of
the surface and groundwater is not impaired.

2.2.3.2

Land-Filling Method of Disposal

Disposal of sewage sludge through land-filling still takes the bulk of sludge in the developed
countries. According to Hall and Dalimier (1994), about 40% of the sludge produced in the
European Union is disposed of through land filling. McGhee (1991) showed that the amount
of sludge taken to landfills in Greece, Luxembourg and Italy were 90%, 88% and 85%
respectively and this makes landfilling there main method of sludge disposal, while in the
USA, 48% of the sludge produced in 1990 was deposited through land filling.

2.2.3.3

Dumping of Sewage Sludge into the Sea

The dumping of sewage sludge into the sea has been phased out in most countries in Europe
but practise of which was noticed in Ireland, UK and Spain in the early Nineties where
marine dispersal was controlled with certain requirements, e.g. the Oslo Convention for the
14

Wastewater and Sewage Treatment

protection of the North Sea and the North East Atlantic, and in accordance to licences issued
under national legislation which take into account the quantity and quality of the sludge and
the nature of the receiving area. The dumping of sludge into the ocean was finally phased out
on 31 December 1998 when the North Sea Conference Agreement for the eradication of
dumping sludge into the Ocean came into force and sea disposal was banned (Werther and
Ogada, 1999).
In the USA ocean disposal by states having coastal lines has been practised but it was
phased out because of changes in water pollution regulations (McGhee, 1991).

2.2.3.4

Disposal of Sewage Sludge through Incineration

The limitation facing land filling, recycling and the ban on sea disposal leads to moves
towards incineration of sewage sludge and wastes in general. Though many have criticised
the method of incineration in disposing waste however, it was revisited due to some
advantages attached to it. The advantages as stated by Vesilind and Ramsey (1996) includes
among others: large reduction of sludge volume to a small stabilized ash, which accounts for
only 10% of the volume of mechanically dewatered sludge and thermal destruction of toxic
organic constituents. Likewise, Metcalf et al. (1991) stated the advantages and the
disadvantages of sludge incineration. The advantages include;
Maximum volume reduction, thus reducing the disposal of space and of transfer costs.
Destruction of pathogens and toxic compounds.
Energy recovery potential.
While the disadvantages include;

Higher capital and operational costs compared to landfill and use of sludge as soil
conditioner.

Highly skilled operating and maintenance staff is required.

The residuals produced (air emissions and ash) may have adverse environmental
effects.

Despite the disadvantages, Ronald J. et al (2008) stated that incineration of wastewater sludge
has become standard practice in large, densely populated areas of some technologically
advanced countries. Japan incinerates more than 70% of its wastewater sludge; in the
Netherlands and Germany, the rates are 58% and 34%, respectively. Slovenia dries much of
15

Wastewater and Sewage Treatment

its wastewater sludge and then sends 50% out of the country for disposal in incinerators. In
Canada, about one-third of the sludge is incinerated.

The table below as analysed by Hester and Harrison (1994) describe the use of incineration in
treating waste in some of the advanced countries in the world.

Table 2.0: Incineration Use in Some Advance Countries of the World (Hester and
Harrison, 1994)
Country

Number of

% incinerated

% sewage

Municipal

Incinerator

municipal waste

sludge

waste

plants

including energy

incinerated

incinerated

recovery

Canada

17

N/A

USA

16

168

N/A

N/A

Japan

75

1900

Mostly plant recovery

N/A

energy
Sweden

55

23

86

Denmark

65

38

Mostly plant recovery

19

energy

2.3

France

42

170

67

20

Netherlands

40

12

72

10

Germany

35

47

N/A

10

Italy

18

94

21

11

Spain

22

61

N/A

UK

30

33

Incineration

Incineration, according to Salvato (1992) is a controlled combustion process for burning solid,
liquid, or gaseous combustible waste to gases and a residue containing little or no
combustible material when properly carried out. It is a volume reduction and usually an
16

Wastewater and Sewage Treatment

energy recovery process suitable for about 70% of municipal solid wastes. Incineration of
sewage sludge is the firing of sludge at high temperature in an enclosed device called an
incinerator (furnace) (Turovskiy and Mathai, 2006).
Incineration plant according to the department of Environment, Foods and Rural affairs, UK
means any stationary or mobile technical unit and equipment dedicated to the thermal
treatment of waste with or without recovery of combustion heat generated. This includes the
incineration by oxidation of waste as well as other thermal treatment processes such as
pyrolysis, gasification or plasma processes in so far as the substances resulting from the
treatment are subsequently incinerated (Francois Audibert, 2006)
Incineration is still one of the best means of sewage sludge and waste disposal. For municipal
solid wastes (MSWs), incineration not only greatly reduces the pressure on landfills, but it
also provides energy, either thermal or electrical to local communities (Y. B Yang et al,
2004). Issues such as increasing competition for landfill space, higher taxes, more strict
environmental regulations set by authorities and the possibility of heavy metal soil
contamination have made sludge landfilling a non-sustainable disposal route. Currently
around 48% of the 949,000 tonnes of sewage sludge produced in the UK is applied to
agricultural land, 17% is incinerated mainly in single feed form and 11% is sent to landfill
(Diaper et al, 2001).
The most commonly used incinerators are multiple-hearth, fluidized-bed and electric infrared
furnaces. An incinerator system consists of an incinerator and one or more air pollution
control devices, which are used either to remove small particles and the adhering metals in
the exhaust gas from the incinerator or to further decompose organics (Turovskiy and Mathai,
2006).
Good performance by an incineration plant depends upon the provision of proper auxiliary
equipment and devices, which include receiving and storage systems, pre-treatment
equipment, feeding system, flue gas cleaning, heat recovery, ash handling, wastewater
disposal and process monitoring.
In their work, Zabaniotou and Theofilou (2008) stated the use of sewage sludge as a
conventional fuel substitute at cement kiln in Cyprus; the heat generated by the incineration
of sludge is recovered in a single pass vertical waste heat boiler and used for power
17

Wastewater and Sewage Treatment

generation, sludge drying, air preheating and flue gas reheating. Power is generated in a back
pressure turbine using high pressure steam produced in the boiler. Zabaniotou and Theofilou
(2008) were able to present new technology in the use of sewage sludge as fuel substitute and
it involves mixing of sewage sludge with pet coke and then incinerating the mixture at high
temperatures. The new sewage sludge-based fuel does not emit dioxins harmful to human
health because cement plants burn fuel at 1400oC (Zabaniotou A. and Theofilou C., 2008).
The ash residue from the incineration plant is usually disposed of in landfill but recently due
to the call for energy and material recovery, ash is increasingly being put to use as fill
material in construction projects or as an ingredient in cement (Ronald J. et al, 2008). In
Japan for example, 110,000m3 of improved soil are produced each year using 7,000m3 of
wastewater sludge ash as one of the ingredients and several tests have shown that the end
products have essentially the same characteristics as pit sand designated by road works
administrators as backfill material (Ronald J. et al, 2008).
The diagram below gives a schematic diagram of an incineration plant with the energy
recovered used in the generation of electricity.

Figure 2.2: Incineration Plant with an Energy Recovery Unit. Source: Huber
Technology (Sludge to Energy website).

18

CHAPTER THREE: LITERATURE REVIEW


3.0

Overview of Logistics

Logistics can be seen from many areas but based on the dictionary definition, logistics can be
defined as the branch of military science having to do with procuring, maintaining,
transporting material, personnel and facilities (Websters New Encyclopaedic Dictionary).
The council of Logistics Management (CLM) gave a broader definition of logistics as; The
process of planning, implementing, and controlling the efficient, cost-effective flow and
storage of raw materials, in-process inventory, finished goods and related information from
point of origin to point of consumption for the purpose of conforming to customer
requirement.
Ratliff & Nulty (1996) defines logistics as the collection of activities associated with
acquiring, moving, storing and delivering supply chain commodities i.e. products in all stages
of manufacture, services and information.
All the definitions above show that logistics encompasses the business functions of
transportation, distribution, warehousing, material handling, and inventory management, and
interfaces closely with manufacturing and marketing.

A logistical analysis implies the assessment of ensuring that the right goods are conveyed
safely to the correct place at the right time at the lowest possible cost (Diaper et al, 2001).

3.1

Existing Models on Waste Management Logistics

In the past, many researchers have attempted to solve the problem of logistics in relation to
waste management with the aid of different mathematical models. Although the focus of this
thesis is the optimisation of sewage sludge logistics in wastewater treatment, very scanty
literature is available on the relevant subject and hence, the need to cover literature pertaining
to optimisation of logistics in waste management as well as waste water treatment.
Zografos and Davis (1989) developed a multi-objective decision making model for the
formulation of hazardous waste routing problem via a goal programming approach to address
the risk imposed on special population categories, travel time and property damages.

19

Literature Review

Their proposed model includes the following objectives; minimization of travel time,
minimization of risk, minimization of risk of special population categories and minimization
of property damages. They used the goal programming formulation based on its advantages
which includes;

Considerable flexibility to the decision maker

Allows the examination of different planning scenarios

It does not require converting all objectives to a single monetary value for the evaluation
of alternative planning scenarios

It requires a limited amount of information from the decision maker and it is


subsequently very easy to understand.

They concluded that the imposition of capacity constraints on the links of the network
distributes the risk in an equal manner and the decision maker can use the proposed multiobjective model as a decision making tool for routing hazardous materials.
Giannikos (1998) formulated a multi-objective model for locating treatment facilities and
transportation routes for hazardous waste shipments through an underlying transportation
networks. A goal programming model was introduced and the four objectives considered
were; (1) Minimization of total operating cost, (2) minimization of total perceived risk, (3)
equitable distribution of the disutility caused by the operation of the treatment facilities, and
(4) equitable distribution of risk among population centres.
The goal programming approach was used to show how monotonically increasing penalty
functions can be used to obtain more satisfactory solutions.
Nema and Gupta (1999) presented a model based on a multi-objective integer programming
approach to suggest the optimal configuration of facilities for transportation, treatment and
disposal with minimum cost and risk to the environment. Their formulation addressed
important practical issues like selection of treatment and disposal facilities, allocation of
hazardous waste residues from generator to the treatment and disposal sites as well as the
selection of the transportation routes.

20

Literature Review

Tung and Pinnoi (2000) formulated a mixed integer program and proposed an heuristic
procedure to solve a vehicle routing and scheduling problem (VRSP) of waste collection in
Hanoi. The proposed heuristics consist of two phases; the construction and improvement
phases. The objective function minimizes the total operating costs which include vehicle
deployment travelling cost.
Their proposed heuristic model showed a good performance in terms of the selection quality
and the computational time. It also achieved improvement in both total cost and the number
of vehicles utilized.
Hu et al (2002) presented a cost minimization model for multi-time step, multiple-type
hazardous waste reverse logistics system. The model considered four critical activities which
include collection of waste, storage, treatment and distribution of waste. The objective was to
minimize the total reverse logistics cost for a given multi-time-step period.
The model addressed the classical hazardous waste treatment problem and can be used to
strategically determine the time varying waste collection amounts and treated amounts in
response to the variety of waste demand from multiple waste resources but its majorly
streamlined towards hazardous waste component.
Kumar Pati et al (2004) formulated a linear analytical model that minimizes the total reverse
logistics costs for multi variety Recycled Waste Reverse Logistics System (RWRLS). The
model was subjected to two major constraints which are internal and external factors. The
internal factors include initial inventories, inventory carrying costs, inventory capacities and
units manufacturing costs while the external factors include distance, demands and unit
travelling costs.
Their analytical model compared costs in different scenarios of demand and it helped in
deciding about the transaction of goods and material taking place in the long term. It can also
help in making strategic inventory management decisions.
Sahoo et al (2005) presented a GIS-based Multi-Objective mathematical programming model
called waste VRPTW model for the routing problem in waste management. The objective
of the model includes minimization of the number of vehicles travelled, minimization of the
travel time and minimization of visual attractiveness. They concluded that the GIS-based
route-management application reduces waste management operational costs by;
21

Literature Review
-

Organising routes to minimize overlap and thereby reduce the number of vehicles waste
management needed to serve its customers and

Sequencing stops along a route to make the best use of fuel, driver schedule and disposal
trips.

3.2

Existing Models on Sewage Sludge Logistics

Logistics is a collection of functional activities that are repeated many times throughout the
channel through which raw materials are converted to finished products and value is added in
the eyes of consumers.
Sewage sludge logistics can be likened to this in which sewage sludge is seen as raw
materials to be transported to the treatment plants where they are treated and subsequently
taken for disposal preferably in incineration plants where they are converted to energy and
ash residue which can be used in the generation of electricity and in the cement industries
respectively (products). Therefore logistics of sewage sludge is meant to serve many
purposes which includes; effective treatment of sludge, the storage of the processed sludge,
environmental impacts and effective transportation of sludge from the wastewater treatment
plant to the final disposal site as well as proper disposal of sewage sludge.
The cost of transportation is often a large proportion of processing costs and the rheological
properties of the sludge as well as the location of the plant are also important in selecting the
best equipment to be used for transport (Diaper et al, 2003). Sludge can be transported by
pipeline, barge, rail or truck and despite its highest environmental pollution load; the truck
option or rail option is often used due to the flexibility of the operation (Diaper et al, 2003). It
must be noted that for the rail option, the cost of construction of a rail network might exceed
the investment and operating cost of the plant and based on that, trucks usage might be
considered the best way of transporting the sludge from the treatment plant to the incineration
plant.
For the past two decades, many studies have focussed on the network flows, modelling
logistics and transportation problems; however as earlier stated there is little information on
models for sewage sludge logistics.
Larson Richard (1988) developed a model for the transportation of sludge to the 106-Mile
site for the New York department of Environmental Protection Agency (EPA). He
22

Literature Review

characterizes the plants as source nodes and the transhipment point as the destination or
sink node in a network paradigm. In the formulation, the source node is the inner-harbour
transhipment point while the destination node is the 106 mile site. The source node has
the usual attributes: mean and variance of daily sludge inflows and storage capacity. In
developing the model, they assumed that; there exists a fleet of identical inner-harbour vessel
whose sole purpose is to pick up sludge from each of the plants and to deliver it to a single
transhipment point and also that there exists a fleet of ongoing vessels whose sole purpose is
to pick up sludge from the transhipment point and to deliver it to the 106-mile site. In the
final modelling analysis, they included the effects of breakdowns of various system
components, abnormal weather conditions, draft restrictions and others.
The model developed by Larson Richard (1988) was highly useful for meeting the problem of
logistics for waste disposal in the 106-mile site in New York and the key decision outcome of
the model is least cost fleet sizing and fleet mix, using a simple periodic routing optimisation
model as a mechanism for integrating system components. Other outcomes are number and
location of transhipment points, appropriate technologies for product transfer and inventory
holding capacity.
In the model developed by Larson Richard (1988), the major concern was the disposal of the
sewage sludge in the ocean which is more or less not globally acceptable and has been phased
out in most developed countries, implying the need for more robust model for acceptable
method of disposal.
De mol et al (1997) used the simulation model Biologics and dynamic optimisation (DP) in
simulation and optimisation of the logistics of biomass fuel collection. They were able to use
the simulation model as well as the optimisation model to get insight into the logistics
involved in biomass fuel collection for an energy plant in Netherlands. The degrees of
freedom they considered include:
-

biomass types;

transport means: road, rail or water transport;

pre-treatment of biomass;

location of the energy plant.


23

Literature Review

De mol et al (1997) also developed a mixed integer linear programming (MIP) model that
gives the minimal costs of the annual flows of biomass. The MIP model was divided into
three sub-models each restricted to biomass types with certain pre-treatment options.
The first sub-model was a case where the biomass flows without pre-treatment for example
pruning or waste wood, the second sub-model looks into biomass flows with pre-treatment in
a separate pre-treatment site e.g. waste paper with pelletion in a pelleting factory as pretreatment and the last sub-model was the case where biomass flows with pre-treatment in
every node.
The binary variables were the decision variables that show whether or not a site for an energy
plant is chosen in the optimal solution. The objective function is built up from the costs of
biomass flows and fixed costs of pre-treatment.
They concluded that the costs of the biomass collections depends on the logistics which
includes the pre-treatments from source locations to the energy plant which can be modelled
by means of a network structure. In their network structure, nodes correspond with source
locations, collection sites, transhipment sites, pre-treatment sites or the energy plant and arcs
correspond with transport (De mol et al, 1997).
Hara K. and Mino T. (2008) evaluate the flow of treated sewage sludge in the treatment
processes starting from each wastewater treatment plant to the final destination in Tokyos 23
wards. The flow and amount of sludge originating from each treatment process at all the
sludge treatment plants were precisely analysed based on primary and actual data obtained
from individual treatment plants. The study is mostly environmentally and energy efficiency
driven and the environmental loads include total energy consumption and gas emissions
(green house and acidification gases).
The sludge flow analysis identified that the raw sewage sludge from the twelve wastewater
treatment plants located within Tokyos 23 wards was transported to and treated at five
wastewater treatment plants that were equipped with sludge treatment facilities such as
dewatering and incineration processes. The way in which the treated sludge was conveyed
from one plant to another varies considerably depending on the properties of the treated
sludge. The sludge transportation methods considered include; Trucking, underground piping
and Shipping.
24

Literature Review

Their work only considered improvements for the future prospects of sewage sludge
management in Tokyo and not much was said as regards optimising the transportation
between the plants and the associated costs involved in the running of the sludge flow.
It can be seen from the above reviews that there had been significant research work on waste
management, wastewater treatment, sludge management and disposal options as well as
literature on logistics in general but there is little information about dynamic models of
sludge transportation logistics.
The logistics involved in the sludge transportation can pose a big problem for the wastewater
treatment company considering the large inventories involved, vehicle capacity, storage
capacity at sludge treatment plant while reducing operational costs, environmental impacts
and maximizing the energy recovery of the whole process.
As discussed in the literature, the use of incineration as a method of sewage sludge disposal
might be expensive in terms of capital/investment cost but if the logistics involved is well
optimised and there is maximum energy recovery, the method can be an added advantage to
the wastewater treatment company and definitely dominate the other methods of sewage
disposal especially in areas where there is scarcity of land.
Yorkshire Water in 2008 in conjunction with ATKINS developed a static model for the
optimisation of sewage sludge transport. In the model, conservation of sludge at the export
works, capacities at both transfer and final works, conservation at transfer works and the
adhoc constraints were considered. The adhoc constraints specified the sludge type produced
restriction and the sludge destination restriction.
The model developed was a static model and lacks multi-periodicity since it only shows the
flow path of sewage sludge from one work to another for just one period. Also, the model did
not consider the possibility of having inventories at the end of each time period and
subsequently ignored the inventory cost at each works.
This project will look into solving the problem of the logistics involved in the transportation
of the sewage sludge in the wastewater treatment plant by developing a more robust linear
dynamic multi-period model that will look into the production profile, inventories, storage
capacities, treatment costs, transport costs and system stability.

25

CHAPTER FOUR: MODEL FORMULATION


4.0

Problem Statement

Yorkshire Water has a number of exports sites which produce sludge; this sludge may be
transported either to a final processing works or an intermediate works known as transfer site
as shown in Figure 4.0. One of the principal objectives of treatment is to reduce the moisture
content of sludge and the transfer sites serve this purpose. Sludge is taken from the transfer
sites to the final sites for final treatment and subsequent disposal (landfill, incineration, e.t.c).
Costs arise principally from running the works and transporting the sludge. The objective is
to minimise the cost of the whole system. Typically this consists of a large number of export
sites generating sludge and a relatively small number of both transfer and final works, all of
which are connected by a road network.
Transport between the sites is either by trucks (tanker) for wet sludges or by skip for cakes.
Costs associated with transport are based on mileage and tonnage for wet sludges and
numbers of loads for cakes.
Treatment costs are based on annual sludge throughput and fixed operating costs at each
works. The treatment cost also depends on the type of sludge being produced at each of the
treatment works (transfer and final) and the reason for the restrictions on the types of sludge
accepted by each works.
The cost function therefore consists of;
-

Fixed treatment costs

Variable treatment costs

Transport costs

Since the fixed costs are indeed fixed i.e. they are going to be incurred, they represent just a
single monetary sum that can be added into the cost structure of the model, therefore they are
not considered in the optimisation problem.

26

4.1

Model Formulation

Mathematical Formulation

Yijst

Export works
i

Xikst

Transfer
treatment works
j

Zjkst

Final treatment
works, k
(Disposal)
Figure 4.0: System Structure at Yorkshire Water
The following comprise the key variables and parameters in the model.
Indices
i

Export works

Transfer treatment works

Final treatment works (Incineration plants)

s, s`

sludge types

period of operation (months)

Sets
I

Export works

Transfer treatment works

Final treatment works (Incineration plants)

sludge types

period of operation (months)


27

Model Formulation

Produced sludge types and works


Is

Set of all export works i that produces sludge type s

Si

Set of sludge type s that can be produced by export works i

Jsout

Set of all transfer works j that can produce sludge of type s

Sjout

Set of sludge type s that can be produced by transfer works j

Entering sludge types and works


Jsin

Set of all transfer works j that can take-in (accept) sludge of type s

Sjin

Set of sludge type s that can be accepted by transfer works j

Ks

Set of all final treatment works k that can take-in (accept) sludge of type s

Sk

Set of sludge type s that can be accepted by final treatment works k

Sludge types produced


IW

Set of all export works i that produce wet sludge.

IC

Set of all export works i that produce cake sludge.

JW

Set of all transfer works j that produce wet sludge.

IC

Set of all transfer works j that produce cake sludge.

Possible links between works


IJ (i, j) possible links between works i and j.
IK (i, k) possible links between works i and k.
JK (j, k) possible links between works j and k.
28

Model Formulation

Parameters
Pis

The indigenous sludge production at export work i of type s in tds/annum

monthly variation (seasonality) of sludge production

Pist

The indigenous production of sludge of type s produced at export work i during

period t in tds
Pist =

Pis
t
12

i, s, t

Ci

Capacity of trucks based at export works i in m3

Cj

Capacity of trucks based at transfer treatment works j in m3

ej

cost () of processing one tonne of dry solids at transfer works j

Ek

cost () of processing one tonne of dry solids at final treatment works k

Hi

inventory cost () at export works per tonnes of dry solids

Hj

inventory cost () at transfer works per tonnes of dry solids

Hk

inventory cost () at final treatment works per tonnes of dry solids

Dij

The distance travelled between work i and work j in kilometres

Djk

The distance travelled between work j and work k in kilometres

Dik

The distance travelled between work i and work k in kilometres

Nj

Processing capacity at the transfer work j in tds/a (where this capacity is expressed in
terms of the incoming, not outgoing, flow of sludge)

Nk

Processing capacity for sludge at the final treatment work k in tds/a (where this
capacity is expressed in terms of the incoming, not outgoing, flow of sludge)

Aj

The monthly processing capacity for transfer works j at time t


Aj =

Nj
12

29

j, t


Ak

Model Formulation
The monthly processing capacity for final treatment works k at time t
Ak =

Nk
12

k,t

Qi

The monthly inventory capacity for export works i at time t

Qj

The monthly inventory capacity for transfer works j at time t

Qk

The monthly processing capacity for final treatment works k at time t

LFij

Loss fraction of dry solid retained for sludge of type s at transfer works j coming from
works i

Wi

Dry solid fraction for flow out of export works i

Wj

Dry solid fraction for flow out of transfer treatment works j

variation of inventory capacities

Variables
Xikst

Wet volume of sludge (m3) transported from i to k over period t.

Yijst

Wet volume of sludge (m3) transported from i to j over period t.

Zjkst

Wet volume of sludge (m3) transported from j to k over period t.

Bkst

Dry sludge of type s disposed off from final treatment works k over period t.

Iist

The inventory of sludge of type s at export works i at period t in tds.

Ijst

The inventory of sludge of type s at transfer treatment plant j at period t in tds.

Ikst

The inventory of sludge of type s at final treatment plant k at period t in tds.

30

Model Formulation

Equations
The main objective is to minimise the total variable costs over period t.
Min

TC (t) + FTC1 (t) + FTC2 (t) + IC (t) .. (4.1)

Subject to the following constraints:


Variable Treatment cost of sludge (TC)
The variable treatment costs are based on a cost per tonnes of dry solid treated at each of
transfer and final treatment works. Export works have zero treatment costs since they only
produce the sludge and do not treat it.
Hence let:
ej be the cost () of processing one tonnes of dry solids at transfer works j
Ek be the cost () of processing one tonnes of dry solids at final treatment works k
Strictly the dry solid fractions when used numerically gives an answer in m3 and for the
purpose of translating the wet volume into mass, a common density D is used, it can be
assumed that 1 cubic metre of dry solid weighs 1 tonne = 1000kg.
Therefore mass in dry solid tonnes is equal to the wet volume multiplied by the dry solids
fraction and the common density D.
The variable treatment cost at the transfer works j over time period t is;

j:( i , j )IJ sSi S in


j

e j Wi DYijst

The inner summation represents the incoming wet volume flow of sludge of all types from
export works i, the summation over all export works i and transfer works j gives the total dry
solids content being processed at transfer works j and over all possible links between i and j.
The term Wi D converts that into dry solid equivalent tonnes and the term ej converts them all
into a monetary value.

31

Model Formulation

In a similar way, the variable treatment cost at the final treatment works k over time period t
is;

k :( i , k )IK sSi Sk

Ek Wi D X ikst +

j k :( j , k )JK sS out
j Sk

Ek W j D Z jkst

Likewise, the inner summation terms represents the incoming wet volume flow of sludge of
all types from export works i and transfer works k respectively, the summation over all export
works i, transfer works j and final treatment works k gives the total dry solids content being
processed at final treatment works k and over all possible links between i and k as well as
links between j and k. The terms Wi D and Wj D converts those into dry solid equivalent
tonnes and the terms Ek converts them all into a monetary value.
Hence the total treatment cost over time period t is derived by taking the two expressions
above and adding them together over all transfer and treatment works respectively:

TC (t) =
i

j:(i , j )IJ

sSi Sinj

ej Wi DYijst +

i k:(i,k )IK sSi Sk

Ek Wi D Xikst +

j k:( j ,k )JK

t T

sSout
j Sk

Ek Wj DZ jkst

....................(4.2)

Transport costs of sludge


The transport costs depend greatly on the different types of sludge.
The cost coefficients given are;
r1 - Rate based on volume of wet sludge [/m3]
r2 - Rate based on distance travelled for each load [/MileLoad]
r3 - Rate based on journey time of vehicle travel based on distance divided by average speed
[ /Hour]
r4 - Cost of transporting one load [] for sludge types 3 and 5.

Transport Costs Cake Sludge (FTC1).


For sludge types IC (cakes) the cost incurred is simply a constant amount (r4) per load
transported, where the number of loads is:
32

Model Formulation
Number of loads = total volume to be transported/vehicle capacity.

The volume of sludge of types IC flowing from export works i at time period t is given by;

Pist

iIC sSi

Since this is the total volume of sludge of these types and this must flow away from export
works i, the transport cost here is

Pist r4
iIC sSi
i Ci

For transfer works j, the volume of sludge of types JC (cakes) flowing from it at time period t
is given by;

jJ C kJK sS out
j Sk

Z jkst

Where the summation terms add over all possible transfer works that produces sludge of
types JC as well as receiving final treatment works k. Hence the transport cost here is

jJ C kJK sS out
j Sk

r4 Z jkst
Cj

Therefore the total transport cost for sludge of types 3 and 5 at time period t is given by;

Pist r4
+
W
C
iIC sSi
i
i

FTC1(t) =

jJC kJK

sSout
j Sk

r4 Z jkst
Cj

t T

...........................(4.3)

Transport Costs Wet Sludge (FTC2).


The total transport cost for wet sludge (IC and JC) is a linear function (per load) of the wet
volume transported, the distance travelled and the time taken. The constant Gij, Gjk and Gik
are define to be a constant value for transport of wet sludge between works ij, jk and ik
respectively where:
Gij = Dij (r2 + r3)
Gjk = Djk (r2 + r3)
Gik = Dik (r2 + r3)
33

Model Formulation

The cost of transport for each load of wet sludge is:


r1 Vehicle capacity + G.
The assumption here is that all loads are full capacity loads.
The transport costs for wet sludge from export works i is calculated thus;
The wet volume of wet sludge of type 1, 2 and 4 flowing from export works i to final
treatment works k at time period t is given by;

iIW k :( i , k )IK sSi Sk

X ikst

The number of loads required is hence;

iIW k :( i , k )IK sSi Sk

X ikst
Ci

The cost involved is therefore the cost per load multiplied by the number of loads given by

iIW k :( i , k )IK sSi Sk

rC
1 i + Gik
X ikst
Ci

The wet volume of wet sludge flowing from export works i to transfer works j over time
period t is given by

iIW j:( i , j )IJ SSi S inj

Yijst

The number of loads required is

iIW j:( i , j )IJ SSi S inj

Yijst
Ci

The cost involved is therefore;

iIW j:( i , j )IJ SSi S in


j

r1Ci + Gij
Ci

Yijst

34

Model Formulation

Hence the total transport cost for export works i involved in transporting wet sludge over
time period t is:

r1Ci + Gik
X ikst +
Ci

iIW k :( i , k )IK sSi Sk

r1Ci + Gij

iIW j:( i , j )IJ SSi S inj

Ci

Yijst

The above equation can be simplified based on;

kIK

ikst

Y
jIJ

ijst

Pist
Wi

This therefore gives;

r1 Pist
+
Wi

r1 Pist
Wi

iIW sSi

Gik X ikst
+
Ci
iIW k :( i , k )IK sSi Sk
iIW

j:( i , j )IJ S Si S inj

Gij Yijst
Ci

Where the first term

iIW sSi

is simply a constant term (since it does not involve any of the variables) and so could be
neglected (including or excluding it would make no difference to the flow pattern decided).
The explanation for this is that there is a constant cost per load (equal to r1 multiplied by the
vehicle capacity) and there will be movement of a certain loads away from export works i
irrespective of the flow pattern involved and hence that has no effect on the flow pattern
adopted.
Likewise the transport costs for wet sludge from the transfer works k over time period t is
calculated thus;
The wet volume of wet sludge of types flowing from transfer works j to final treatment works
k over time period t is given by;

jJW k :( j , k )JK sS out


j Sk

Z jkst

35

Model Formulation

The number of loads required is hence

Z jkst

(r1C j + Gik ) Z jkst

Cj

jJW k :( j , k )JK sS out


j Sk

The cost involved is therefore:

Cj

jJW k :( j , k )JK sS out


j Sk

In conclusion, the total transport costs associated with transporting sludge of types 1, 2 and 4
at time period t is given by;

FTC2(t) =

G Y
Gik Xikst
+ ij ijst
Ci
Ci
iIW k:(i,k )IK sSi Sk
iIW j:(i, j )IJ SSi Sinj

r1 Pist

iIW sSi

(rC
1 j + Gik ) Z jkst

jJW k:( j ,k )JK sSout


j Sk

Cj

t T ..................................(4.4)

Inventory cost
The total inventory cost of dry sludge over each time period is the summation of the
inventory cost of tonnes of dry solids at each works.
i.e.

IC(t) =Iist Hi +
i sSi

I
j

sout
j

jst

Hj +Ikst Hk

t T ..................(4.5)

k sSk

Capacity constraints
At the further treatment works, the processing capacity of the works must not be exceeded.
The capacity constraints of both the transfer and final works are expressed in terms of the dry
solids, therefore the need to convert the wet volume to solid in both constraints.

i:(i , j )IJ sSi S inj

Wi Yijst Aj

j J , t T ...........................(4.6)
36

Model Formulation

At the final treatment works, the storage capacity of sludge must not be exceeded.

WX

i:(i,k )IK sSi Sk

ikst

j:( j ,k )JK

sSout
j Sk

Wj Z jkst Ak

k K, t T ...........................(4.7)

Inventories at the export works


The inventory of dry sludge of type s at the export works at the beginning of each time
interval is equal to the value from the last time period plus dry sludge produced at the
beginning of the time interval minus total amount of dry sludge discharge from it at the
beginning of that time interval.

I ist = I is , t 1 + Pist Wi
X ikst +
k :( i ,k )IK K s
I ist Qi

Yijst
j:( i , j )IJ J s

for any i , s, t

i I , s Si , t T ...........................( 4.8)
...........................( 4.9)

Inventories at the transfer works


The inventory of dry sludge at the transfer works at the beginning of each time interval is
equal to the value from the last time period plus any sludge charged to it at the beginning of
the time interval minus any sludge discharge from it at the beginning of that time interval.
The inventory at the transfer works also takes into account possible conversion of sludge at
the transfer works i.e. whatever the incoming mix of sludge, a transfer works j produces only
one type of outgoing sludge Jsout.
In general, the total dry solids content remains unchanged after transfer works processing.
The only exception is that at a transfer works where the incoming sludge is not digested but
outgoing is, then the total solids exiting is some percentage of that entering due to a loss
factor during the digestion.

37

Model Formulation

Therefore, the inventory of sludge of type s at time period t for transfer work j is given as;

I jst = I js , t 1 +

i:( i , j )IJ s 'I s J sin

Wi Yijs 't LFij

I jst Q j

k :( j , k )JK K s

W j Z jkst

for any j , s, t

j J , s S j , t T ......................(4.10)
.......................(4.11)

Inventories at the final works

The inventory of dry sludge at the final treatment works (incineration plant) at the beginning
of each time interval is equal to the value from the last time period plus total amount of dry
sludge charged to it at the beginning of the time interval minus any sludge used for
incineration at the time interval.

I kst = I k , s , t 1 + Wi

i:( i , k )IK I s

I kst Qk

X ikst + W j

Z jskt Bkst

k K , s Sk , t T .......................(4.12)

j:( j , k )JK J sout

for any k , s, t

38

.......................(4.13)

CHAPTER FIVE: YORKSHIRE WATER CASE STUDIES


5.0

Introduction

Yorkshire Water manages the collection, treatment and distribution of water in the Yorkshire
region. They supply around 1.3 billion litres of drinking water each day and subsequently
collect, treat and return about 1 billion litres of wastewater safely back into the environment.
The Figure below shows the Yorkshire Water region.

Figure 5.0: Yorkshire Water Region showing Operational boundaries for water and
sewerage services

39

Yorkshire Water Case Studies

In order to ensure adequate treatment of wastewater and meeting demanding environmental


standards, Yorkshire Water collects wastewater via 30,300km of sewers and are treated in
over 631 wastewater treatment works referred to as export works.
In this write up, three different scenarios or case studies of Yorkshire Water will be
considered to evaluate the feasibility of the optimisation model and the cost associated with
each scenario.

5.1

Works at Yorkshire Water

There are three different types of works at Yorkshire Water. They are:
9 Export works sludge producers
9 Transfer works these works reduce moisture contest and export the treated sludge to
final works
9 Final works these works process sludge further for disposal.
As earlier noted, export works are generally small and numerous compared to transfer and
final works. There are six different types of sludges produced at both export and transfer
works and they fall into two groups, wet sludges and cakes.
Wet sludges include raw, thickened, digested and contaminated sludge while cake sludges are
undigested and digested cakes. The sludge produced by the final treatment works is for
disposal and therefore not considered in the optimisation process. In general, only one type of
sludge is produced at an export or transfer work and a transfer or final treatment works can
actually receive and process a limited range of sludge types.
All works are connected by road network and therefore there are many possibilities of
movement between the works. The potentially very large number of connections is limited by
the types of sludge that are produced by export and transfer sites and the types of sludge that
can be processed by both transfer and final works. The optimisation process gives the lowest
possible cost after examining all the possible paths as well as the constraints and sludge
restrictions.
Figure 5.1 shows a representation of the possible connections between works where there are
seven export works, two transfer and three final treatment works.
40

Yorkshire Water Case Studies

Figure 5.1: Schematic representation of possible links between works

5.2

Distances between Works

In the data from Yorkshire Water, the OSGB coordinates (Northings and Eastings) were
given for all works and this can be used to generate the distances between the works in the
optimisation model.
The distance between the works is very important since the transport cost is a function of
distance travelled between the works where there are possible links.
There are four ways of developing the distance data between the works.
Straight Line: Based on the straight line distance between works given their positions in
OSGB coordinates. The distances can be factored. It has been found for example that a factor
of 1.5 times the straight line distance gives a reasonably good initial estimate of the actual
distance between two points along the road network.
Dijkstra: This algorithm is based on a network [graph in computer science parlance] which
for SPLAT is based on the road network.

41

Yorkshire Water Case Studies

Modified Dijkstra: As the normal Dijkstra algorithm is not based on any georeferenced data
SPLAT provides an improved version of the algorithm which makes use of the
georeferencing. This is known as the alpha algorithm and is the preferred algorithm to be
used when generating a distance table from road network data.
User Defined: Real data from, for example, GPS tracking of sludge transport vehicles can be
used if available. This is almost certain to be more accurate than any of the other three
sources of distance data. The user defined table can be based on any of other data as the user
is able to edit individual links, cut and paste and import and export data.
The straight line method is used for the purpose of the optimisation process since the other
three methods were not available. Also the distances were given in miles and for consistency
purpose; the distances were multiplied by a factor of 1.60934 to convert to kilometres.

5.3

Monthly Variations in Production of Sludge at Export Works

In the data provided there is no monthly production therefore arbitrary values were used to
suggest variation of monthly production.
There are some months of the year that the production of sludge is expected to be high
especially during the autumn and winter seasons when the population of the Yorkshire region
is on the high side while the other seasons like spring and summer when most of the
population travels for summer holidays, the production is expected to be on the low side.
Table 5.0 shows the arbitrary monthly variations for the production of sludge at the Yorkshire
Water based on the explanations above.

42

Yorkshire Water Case Studies

Table 5.0: Monthly variations of sludge production

5.4

Months

Fractional variations

January

1.2

February

0.9

March

1.1

April

0.95

May

1.0

June

0.9

July

0.9

August

0.8

September

0.9

October

1.0

November

1.15

December

1.2

Loss Fraction of Dry Solid Retained at Transfer Works

The moisture removed by transfer works j must be accounted for and whatever the incoming
mix of sludge, a transfer works can only produces only one type of outgoing sludge.
In general the total dry solids content remains unchanged after transfer works processing. The
exception is that at a transfer works where incoming sludge is not digested but outgoing
sludge is, then the total dry solid leaving is some percentage of that entering, due to a loss to
gas during the digestion process. The exact value of the fraction of dry solids depends upon
the works being considered.
In general, the loss fraction retained is only other than unity for works where the incoming
sludge is not digested but the outgoing sludge is digested. For the purpose of this
optimisation, the loss to digestion of 30% is used and therefore the loss fraction retained is
0.7 (70%) for all works where the outgoing sludge is digested.
43

5.5

Yorkshire Water Case Studies

Inventories of Sludge at Different Works

The inventories of sludge at the different works are considered at the end of each time period
(monthly in this case). The data for the inventory cost is not given in Yorkshire water data but
arbitrary values were set for the inventory costs at the export, transfer and the final treatment
works. The reason for consideration of the inventories at different works is based on many
issues ranging from ensuring constant supply of sludge and also based on the capacity
constraints in both transfer and final treatment works. If the inventory cost at a transfer works
A is low and the nearest final treatment works B is full due to capacity constraint then A
can hold back some of the sludge till the next time period rather than transporting the sludge
to a final treatment works C which is very far to A. Therefore due to the introduction of
the inventory costs, the optimisation model then trade-offs between the transportation costs,
treatment costs and the inventory costs of sludge.
For the purpose of this optimisation model, to avoid backlog of sludge at the export works, it
is assumed that there is enough vehicle to transport sludge from the export works. Therefore,
the inventory of sludge at the export works at time period t is less than or equal to zero.

44

CHAPTER SIX: RESULTS AND DISCUSSION


6.0

Introduction

Three different case studies of Yorkshire Water were considered to check the feasibility of
the proposed model. The data were supplied by Yorkshire Water and the necessary
modifications were applied to the data to suit the model. The General Algebraic Modelling
System (GAMS) was used coupled with the Simplex linear programming algorithm (CPLEX
solver) to find the optimised costs for each of the scenario considered and as earlier explained,
since no inventory cost was available in the data provided by Yorkshire Water, arbitrary
values were used for the inventory cost of sludge per dry tonnes at export, transfer and final
treatment works and these costs were varied to evaluate the effect on the flow of sludge and
also on optimised costs of running the system. The planning horizon of interest is 1 year split
into 12 monthly time periods.

6.1

Scenario One: Transfer Check.

The first scenario considered is termed TRANSFER CHECK. It consists of seven export
works, three transfer works and two final treatment works. The data for the TRANSFER
CHECK is shown in APPENDIX 1A.
In order for the model to be feasible, some of the parameters were modified as follows:Vehicle Capacity for A/STW and B/STW are zero, these were corrected by allocating a
vehicle capacity of 14.51m3 to both works.
The logistics problem was solved as a multiperiod linear programming problem (LP) using
General Algebraic Modelling System (GAMS) and the result is as discussed below.

6.1.1 Transfer Check 1


The result of the first scenario (Transfer Check 1) when the inventory cost at export works,
transfer works and final works were 1.15, 2.50 and 1.50 per tonnes of dry solids
respectively is as shown in Table 6.0.

45

Results and Discussion

Table 6.0: Results for Transfer Check 1 (Scenario one).


Optimised Variables

Optimised Costs ()

Final Total variable cost

964,532

Total Treatment cost

281,297

Total Final transport costs for cake sludge

97,289

Total Final transport costs for wet sludge

583,962

Total Inventory cost

1,983

The detailed result for this case is given in APPENDIX 1B which shows the flow pattern of
sludge from the different export works to both the transfer works and final treatment works.
The results produced thirteen optimised flows in all as represented in Figure 6.7. The flows
includes three flows from export works to final treatment works (Xikst), seven flows from
export works to transfer treatment works (Yijst) and three flows from transfer works to final
treatment works (Zjkst).
The flows though as expected are between works with shortest distance but there were some
exceptions. D/STW which is an export works is closer to transfer works T1/STF (22.870
miles) and T2/STF (22.123miles) but the result shows a connection between T3/STF (70.207
miles) which is more than three times farther than the distance between the two other transfer
works. This can be attributed to the capacity constraints at both T1/STF and T2/STF.
The results also shows that there was flow of sludge between G/STW and two different
transfer works - T1/STF and T2/STF. This was also due to the capacity constraints at the
transfer works and the level of production at G/STW is more than what can be received by
just one transfer or final treatment works.
Figures 6.0, 6.1, and 6.2 below shows the monthly total variable cost, monthly treatment cost
and monthly transportation cost respectively for this case.
The result shows that the monthly total variable costs, monthly treatment cost and monthly
transport costs follows the production monthly variations with peak of the graph at January
when the sludge production is expected to be at the peak based on the explanation in the
preceding chapter.

46

Results and Discussion

Figure 6.0: Monthly Total Variable Costs for Transfer Check 1 (Scenario one).

Figure 6.1: Monthly Treatment Costs for Transfer Check 1 (Scenario one).
The monthly transportation cost for cake sludge was low when compared with the monthly
transportation cost for the wet sludge as shown in figure 6.2 below. This can be attributed to
the large volume of wet sludge being produced at the export works.

47

Results and Discussion

Figure 6.2: Monthly Transportation Costs for Transfer Check 1 (Scenario one).
Figure 6.3 below shows the inventory costs. There were increasing amount of inventories of
sludge for some transfer works from August to December; this is due to the trade-offs
between the inventory cost and the transportation cost in this months, though there is
adequate capacity for flow of sludge from this works. There are no inventories of sludge from
January to July at the transfer works and no inventories of sludge at all at final treatment
works and this can be attributed to adequate capacity of sludge and adequate capacity for
disposal respectively.

Figure 6.3: Monthly Inventory Costs for Transfer Check 1 (Scenario one).
In real life situations, there will be possibilities of inventories of sludge at every month
though the volume can be very small and therefore can be ignored.
48

Results and Discussion

6.1.2 Transfer Check 2


The result of the first scenario (Transfer Check) when the inventory costs at export works,
transfer works and final works were 100, 200 and 150 per tonnes of dry solids
respectively is as shown in the table below.
Table 6.1: Results for Transfer Check 2 (Scenario one).
Optimised Variables
Final Total variable cost

Optimised Costs ()
1,011,730

Total Treatment cost

307,776

Total Final transport costs for cake sludge

101,406

Total Final transport costs for wet sludge

602,548

Total Inventory cost

The detailed result for this case is given in APPENDIX 1C which shows the flow pattern of
sludge from the different export works to both the transfer works and final treatment works.
The same thirteen optimised flows were produced as is the case for Transfer Check 1 as
represented in Fig 6.6. The flows includes three flows from export works to final treatment
works (Xikst), seven flows from export works to transfer treatment works (Yijst) and three
flows from transfer works to final treatment works (Zjkst).
There was slight difference between the results obtained for the Transfer Check 1 and
Transfer Check 2. There was an increase in the final total variable cost from 964,532 to
1,011,730 and therefore affected the treatment costs and transportation costs. There was no
inventories of sludge at all at any works due to the increase in inventory costs per tonnes of
dry solid. This shows that there was a trade-off between the transportation costs and the
inventory costs of sludge.
The trade-offs between the transportation costs and the inventory costs also result in an
increase in volume of sludge transported from transfer works to final treatment works though
the pattern of flow remains the same as in the previous example.
The monthly total variable costs, treatment costs and transportation costs are shown in
Figures 6.4, 6.5 and 6.6 respectively.

49

Results and Discussion

Figure 6.4: Monthly Total Variable Costs for Transfer Check 2 (Scenario one).

Figure 6.5: Monthly Treatment Costs for Transfer Check 2 (Scenario one).

Figure 6.6: Monthly Transportation Costs for Transfer Check 2 (Scenario one).
50

Results and Discussion

The optimised flow of sludge for the two cases of scenario one (Transfer Check 1 and
Transfer Check 2) are shown in figure 6.7 below.

Figure 6.7: Schematic representation of Optimised path for Transfer Check (Scenario
one).

6.2

Scenario Two: Model Test.

The second scenario considered is termed MODEL TEST. It consists of twenty export works,
seven transfer works and seven final treatment works. The data for the MODEL TEST is
shown in APPENDIX 2A.
Some of the parameters were modified for the optimisation model to be feasible. These are
analysed below:Vehicle Capacity at export works E_C, E_D, E_E, E_K, E_L, E_O, E_P, E_R and E_S are
zero, these were corrected by allocating a vehicle capacity of 14.51m3.
The optimisation problem was solved as an linear programming problem (LP) using the
General Algebraic Modelling System (GAMS) and the results are discuss below.

6.2.1 Model Test 1


The result of the second scenario (Model Test 1) when the inventory costs at export works,
transfer works and final works were 1.15, 2.50 and 1.50 per tonnes of dry solids
respectively is as shown in the Table 6.3.
51

Results and Discussion

Table 6.2: Results for Model Test 1 (Scenario two).


Optimised Variables

Optimised Costs ()

Final Total variable cost

7,411,842

Total Treatment cost

1,844,096

Total Final transport costs for cake sludge


Total Final transport costs for wet sludge
Total Inventory cost

51,032
5,513,373
3,341

The detailed result for this case is shown in APPENDIX 2B which shows the flow pattern of
sludge from the different export works to both the transfer works and final treatment works.
There were twenty-eight (28) different flows in the optimised network which include thirteen
(13) flows from export works to final treatment works (Xikst), eight (8) flows from export
works to transfer works (Yijst) and seven (7) flows from transfer works to final treatment
works (Zjkst) as shown in figure 6.18.
In the result obtained for this case, export works E_G transfers sludge to both transfer works
T_G and final treatment works F_B. This can be attributed to sludge capacity at both the
transfer work (T_G) and final treatment work (F_B). Also, T_E being a transfer works
transfer sludge to F_F, a final treatment works which is farther to it (103 miles). This is due
to the trade-off between the treatment costs and the transportation costs from T_E. All the
final treatment works closer to T_E have a higher treatment cost per dry tonnes of solid and
the only one that is lower than F_F is F_G which has a lower sludge capacity and therefore
the need to transfer sludge to a further distance from the transfer works so as to optimise the
running cost.
Figures 6.8, 6.9, 6.10 and 6.11 shows the monthly total variable costs, monthly treatment
costs, monthly transportation costs for cake sludge and monthly transportation costs for wet
sludge respectively.

52

Results and Discussion

Figure 6.8: Monthly Total Variable Costs for Model Test 1 (Scenario two).

Figure 6.9: Monthly Treatment Costs for Model Test 1 (Scenario two).

53

Results and Discussion

Figure 6.10: Monthly Transportation Costs of Cake Sludge for Model Test 1
(Scenario two).

Figure 6.11: Monthly Transportation Costs of Wet Sludge for Model Test 1
(Scenario two).
Figure 6.12 shows the inventory costs for this case. There were fluctuations in the inventory
costs as shown in the figure and this can be due to the trade-offs between the inventory cost
and the transportation cost in the affected months, though there is adequate capacity for flow
of sludge from this works. There are no inventories of sludge in February, July and August at
54

Results and Discussion

both the transfer works and the final treatment works and this can as well be attributed to
adequate capacity of sludge and adequate capacity for disposal respectively.

Figure 6.12: Monthly Inventory for Model Test 1 (Scenario two).


All the seven transfer works have inventories of sludge while just three of the final treatment
works have inventories of sludge at each time period.

6.2.2 Model Test 2


The result of the first scenario (Transfer Check) when the inventory costs at export works,
transfer works and final works were 100, 200 and 150 per tonnes of dry solids
respectively is as shown in the table below.
Table 6.3: Results for Model Test 2 (Scenario two).
Optimised Variables

Optimised Costs ()

Final Total variable cost

7,578,914

Total Treatment cost

1,860,349

Total Final transport costs for cake sludge


Total Final transport costs for wet sludge
Total Inventory cost

58,520
5,560,771
99,273

55

Results and Discussion

The detailed result for this case is given in APPENDIX 2C which shows the flow pattern of
sludge from the different export works to both the transfer works and final treatment works.
The same twenty-eight (28) different flows were obtained in the optimised network which
include thirteen (13) flows from export works to final treatment works (Xikst), eight (8) flows
from export works to transfer works (Yijst) and seven (7) flows from transfer works to final
treatment works (Zjkst) as shown in figure 6.18.
There was slight difference between the results obtained for the Model Test 1 and Model Test
2. There was an increase in the final total variable cost from 7,411,842 to 7,578,914 and
therefore affected the treatment costs and transportation costs as well as the inventory costs.
Only one of the final treatment works have inventories of sludge compared to three in the
first case and just four of the transfer works too have inventories of sludge at the end of the
time period. This shows that there was a trade-offs between the transportation costs,
treatments costs and the inventory costs of sludge.
The trade-off between the transportation costs and the inventory costs also result in an
increase in volume of sludge transported from transfer works to final treatment works though
the pattern of flow remains the same as earlier stated.
The monthly total variable costs, monthly treatment costs, monthly transportation costs for
cake sludge and monthly transportation costs for wet sludge types are shown in figures 6.13,
6.14, 6.15 and 6.16 respectively.

Figure 6.13: Monthly Total Variable Costs for Model Test 2 (Scenario two).

56

Results and Discussion

Figure 6.14: Monthly Treatment Costs for Model Test 2 (Scenario two).

Figure 6.15: Monthly Transportation Costs of Cake Sludge for Model Test 2
(Scenario two).

57

Results and Discussion

Figure 6.16: Monthly Transportation Costs of Wet Sludge for Model Test 1
(Scenario two).
In addition to the differences noted above between the two cases, the inventory cost of sludge
in December was high compared to the remaining months but there was increase in inventory
costs though the tonnes of dry solid of sludge at the different works is lower than the first
case.

Figure 6.17: Monthly Inventory for Model Test 2 (Scenario two).


Figure 6.18 gives the schematic representation of the optimised path for the scenario. This
shows the possible connections between the different works.

58

Results and Discussion

Figure 6.18: Schematic representation of Optimised path for Model test (Scenario two).

6.3

Scenario Three: Final Cost Check.

The third scenario considered is termed FINAL COST CHECK. It consists of ninety three
(93) export works, fourteen (14) transfer works and twenty four (24) final treatment works.
The data for the FINAL COST CHECK is shown in APPENDIX 3A.
In order for the model to be feasible, some of the parameters were modified as follows:All export and transfer works with vehicle capacity of zero were modified and given a value
of 14.51m3 for the model to be feasible.
Only one case of inventory cost was considered for this scenario due to the large number of
works involved in this scenario.
The logistics problem was solved as a multiperiod linear programming problem (LP) using
General Algebraic Modelling System (GAMS) and the result is as discussed below.

6.3.1 Final Cost Check


The result of the third scenario (Final Cost Check) when the inventory costs at export works,
transfer works and final works were 1.15, 2.50 and 1.50 per tonnes of dry solids
respectively is as shown in table 6.5.
59

Results and Discussion

Table 6.4: Results for Final Cost Check (Scenario three).


Optimised Variables
Final Total variable cost

Optimised Costs ()
13,123,819

Total Treatment cost

5,574,344

Total Final transport costs for cake sludge


Total Final transport costs for wet sludge
Total Inventory cost

208,420
7,330,166
10,888

The detailed result for this case is shown in APPENDIX 3B which shows the flow pattern of
sludge from the different export works to both the transfer works and final treatment works.
There were one hundred and fourteen (114) different flows in the optimised network which
include eighty three (83) flows from export works to final treatment works (Xikst), seveenteen
(17) flows from export works to transfer works (Yijst) and fourteen (14) flows from transfer
works to final treatment works (Zjkst).
In the result obtained for this case, export works E22/STW transfers sludge to both F10/STF
and F16/STF which are the closest in distance to it but the transfer to F10/STF is only in
March and December and this can be due to the capacity constraints at works F16/STF in
those two months.
Export work E55/STW also transfers sludge to both F3/STF and F1/STF but despite the fact
that F1/STF is the closest in distance to E55/STW (5.199 miles) when compared to F3/STF
(10.52 miles), there was only transfer of sludge to F1/STF in November only and there was
transfer to F3/STF throughout the time period. This can be due to the trade-offs between the
treatment costs and the transportation costs to these works. The treatment costs at F3/STF is
low (48.27) compared to that of F1/STF (56.45). This shows the treatment costs can also
determine to a greater extent which pattern the flow of sludge will follow at every time period.
Figure 6.19, 6.20, 6.21 and 6.22 shows the monthly total variable costs, monthly treatment
costs, monthly transportation costs for cake sludge and monthly transportation costs for wet
sludge respectively.

60

Results and Discussion

Figure 6.19: Monthly Total Variable Costs for Final Cost Check (Scenario three).

Figure 6.20: Monthly Treatment Costs for Model Final Cost Check (Scenario three).

61

Results and Discussion

Figure 6.21: Monthly Transportation Costs of Cake Sludge for Final Cost Check
(Scenario three).

Figure 6.22: Monthly Transportation Costs of Wet Sludge for Final Cost Check
(Scenario three).
Figure 6.23 shows the monthly inventory costs for this case. There were fluctuations in the
inventory costs as shown in the figure and this can be due to the trade-offs between the
inventory cost and the transportation cost in the affected months, though there is adequate
capacity for flow of sludge from this works. There no inventories of sludge in February at
both the transfer works and the final treatment works and this can as well be attributed to
adequate capacity of sludge and adequate capacity for disposal respectively.
62

Results and Discussion

Figure 6.23: Monthly Inventory for Final Cost Check (Scenario three).

6.3

Model Summary

The three scenarios considered above express the ability of the model to easily solve the
logistics problem involved in sewage sludge treatment. Table 6.6 below shows the model
statistics for the three scenarios.
Table 6.5: Model Statistics for the Three Scenarios.
Scenario Name

Number of

Number of

Generation

Execution

RAM

Variables

Single Equations

Time

Time

Size

Transfer Check 1

817

577

0.450s

0.452s

3.7Mb

Transfer Check 2

817

577

0.428s

0.430s

3.7Mb

Model Test 1

2,869

1,357

0.254s

0.257s

4.2Mb

Model Test 2

2,869

1,357

0.521s

0.524s

4.2Mb

Final Cost Check

27,469

4,597

1.632s

1.652s

9.5Mb

63

CHAPTER SEVEN: CONCLUSION AND RECOMMENDATIONS


7.0

Conclusion

The multi-period dynamic optimisation model had been developed with the main objective to
investigate the inventory management of sludge at the transfer and final treatment works.
This can greatly help in making strategic inventory management decisions and logistics
planning. The model was developed as three echelons comprising the exports, transfer and
the final treatment works.
Three different scenarios of the Yorkshire Water case study have been considered in this
thesis and the results have shown that the model is feasible for all the scenarios. Each works
produce just one type of sludge as proposed and the cost of the different optimised variables
(Treatment costs, transportation costs and inventory costs) are given in monthly periods
which make it appropriate for effective sludge logistics planning.
The volume of sludge flowing from one work to the other is also given in monthly periods as
shown in the flow pattern of sludge in the Appendix 1B, 1C, 2B, 2C and 3B. For the first two
scenarios i.e. TRANSFER CHECK and MODEL TEST, two separate cases were considered
to explore the response of the model to different inventory costs of sludge. The results
showed that the pattern of flow remains the same irrespective of the inventory cost but the
volume of sludge transported from one work to the other increased while the inventories of
sludge at both transfer and final treatment works decreased.
The availability of data had greatly helps in determining the feasibility of the model and it
can be concluded that the major parameters that determine the value of the objective function
includes the distance between each works, the treatment cost of sludge at each works and the
inventory cost of sludge. The capacity constraints also play a major role in determining the
pattern of flow of sludge from one work to another.
The schematic representations of the optimised path for the first two scenarios were also
presented in this report to visualise the movement between each works. This was sketched
using the OSGB codes and a Google map of the Yorkshire region.

64

Conclusion and Recommendations

7.1

Recommendations for Further Work

The model was developed under time constraints and additional research work is required in
the following areas discussed below.

Disposal of Sludge: The model should be extended further from the final treatment work
to the logistics involved in the disposal of the sludge via the adequate disposal options
such as incineration, agricultural use and landfill.

Truck Types: In the model presented, each export and transfer work has just one type of
truck for the movement of sludge from one work to the other. The model can be made
more flexible by proposing the option of more than one type of trucks at each work.

Inventory of Sludge: The inventories of sludge at the transfer and final treatment works
at the end of the time period (December) were slightly high and necessary constraints are
needed to force the inventories to a bare minimum or probably to zero. Necessary
modifications are also needed on the bounds of the inventories that each works can
accommodate at every time period.

65

REFERENCES

1.

Bolton R. L. and Klein L. (1971); Sewage Treatment: Basic Principles and Trends.
London, Butterworth & co Publishers Limited.

2.

Brester, A.R.; Coulomb, I.; Deak, B.; Matter, B.; Saabye, A.; Spinosa, L.; Utvik,
A.O. (1998); Sludge Treatment and Disposal, Management Approaches and Experiences.
Environmental Issues Series, No. 7. European Environmental Agency, 1998.

3.

Chen, Guohua, Yue, Po Lock and Mujumdar, Arun S. (2002); Sludge Dewatering
and Drying. [online] 20 (4 &5), 883 916 Available from DOI: 10.1081/DRT120003768 [Accessed on 24th January, 2009].

4.

CIWEM, (1999); Sewage Sludge: Conditioning, Dewatering, Thermal Drying and


Incineration. Handbooks of UK Wastewater Practice, CIWEM, London.

5.

Dang Tung Vu and Pinnoi Anulark (2000); Vehicle Routing Scheduling for Waste
Collection in Hanoi. European Journal of Operational Research 125: 449 468.

6.

De Mol R. M., Jogems M.A.H., Van Beek P., and Gigler J. K., (1997); Simulation and
Optimisation of the logistics of Biomass Fuel Collection. Netherlands Journal of
Agricultural Science 45: 219 228. Available from:
http://library.wur.nl/ojs/index.php/njas/article/view/535/249 [Accessed
on 24th January, 2009]

7.

De Silva, Viraj and Chan, Kwan Kin (2005): An Overview of Current Sludge Drying
Practices. In; Proceedings of the Water Environment Federation Technology pp 740-749
Published

by

Water

Environment

Federation.

Available

from

DOI:10.2175/193864705783977790 [Accessed on 16th January, 2009]


8.

Diaper C., Cartmell E., Judd S. J., Kilgallon P. and Oakey J. (2001): Sewage Sludge
Disposal: A Logistical Analysis. In Ravindra K. Dhir, Mukesh E. Limbachiya, and
Michael J. McCarthy (eds): Recycling and Reuse of Sewage Sludge: Proceedings of the

66

References
International Symphosium organised by the Concrete Technology Unit and Held at the
University of Dundee, Scotland, UK on March 19 20, 2001. Thomas Telford
Publishers.

9.

Flaga A. (2005): Sludge drying; In Plaza E. and Levlin E. (eds): Integration and
optimisation of urban sanitation systems. Proceedings of Polish-Swedish seminars,
Cracow March 17-18, 2005.

10. Francois Audibert (2006): Waste Engine Oils; Rerefininng and Energy Recovery.
Elsevier Publishers.

11. Giannikos Ioannis (1998) A Multi-Objective Model for Locating Treatment Sites and
Routing Hazardous Wastes. European Journal of Operational Research 1998 104 page
333 342.

Available from doi:10.1016/S0377-2217(97)00188-4 [Accessed 19th

August, 2009]

12. Hall J.E. and Dalimier F. (1994): Waste managementsewage sludge: survey of
sludge production, treatment, quality and disposal in the EC. EC Reference No: B43040/014156/92, Report No: 3646, 1994.

13. Hara K. and Mino T. (2008) Environmental Assessment of Sewage Sludge Recycling
Options and Treatment Processes in Tokyo. Waste Management 2008 28 (12) page 2645
2652. Available from doi:10.1016/j.wasman.2008.02.020 [Accessed 19th August,
2009]

14. Hester R. E. and Harrison R. M. (1994): Waste incineration and the Environment.
Issues in Environmental Science and Technology. Royal Society of Chemistry.

15.

http://ec.europa.eu/environment/waste/sludge/index.htm

16.

http://news.bbc.co.uk/2/hi/uk_news/scotland/4564432.stm

67


17.

References
http://.thameswater.co.uk/cps/rde/xchg/SID-B8EFD863A3EB7AED/corp/hs.xsl/6881.htm

18.

http://www.euwfd.com/html/sewage_treatment.html - European Union


Water Framework Directives. (EUFWD)

19. http://www.sludge2energy.de/docs/sludge2energy_decentralised_sewage_
sludge_utilisation.pdf
20.

Hu Tang-Lai, Sheu Jiuh-Biing and Huang Kuan-Hsiung (2002) A Reverse


Logistics Cost Minimization Model for the Treatment of Hazardous Waste.
Transportation Research Part E 38 (2002) 457 473.

21.

Korentajer J. (1991): A review of the agricultural use of sewage sludge, benefits and
potential hazards. Water SA 1991; 17(3):189196.

22. Kumar Pati Rupesh, Prem Vrat and Kumar Pradeep (2004) Cost optimisation
model in recycled waste reverse logistics system. Journal of Business Performance
Management Vol 6 (3-4) page 245261.
23.

Larson Richard C. (1988); Transporting Sludge to the 106 Mile Site: An


Inventory/Routing Model for Fleet Sizing and Logistics System Design. [online] 22 (3)
186-198. Available from DOI: 10.1287/trsc.22.3.186 [Accessed on 4th February,
2009].

24.

McGhee T. J. (1991); Water supply and sewerage. New York: McGraw-Hill


Publishers.

25.

Metcalf and Eddy Inc (1991): Wastewater Engineering: Treatment, disposal and reuse. McGraw Hill Inc. International, New York

26.

Nema Arvind K. and Gupta S.K. (1999) Optimization of Regional Hazardous Waste
Management Systems: an Improved Formulation. Waste Management 1999 Vol 19 (7-8)
page 441451. Available from doi:10.1016/S0956-053X(99)00241-X [Accessed 19th
August, 2009]

68

References

27. Outwater, A.B. (1994): Reuse of Sludge and Minor Wastewater Residuals. Boca Raton:
Lewis Publishers.
28. Ratliff H. D. and Nulty W. G. (1996): Logistics Composite Modelling. In Technical
White paper series. The Logistics Institute at Georgia Technology.
29. Ronald J. Leblanc, Peter Matthews and Ronald P. Richard (2008); Global Atlas of
Excreta, Wastewater Sludge and Biosolids Management: Moving Forward the
Sustainable and Welcome Uses of a Global Resource. United Nations Human
Settlements Programme (UN HABITAT)
30. Sahoo S, Kim S, Kim B-I, Krass B and Popov Jr. A. (2005): Routing Optimisation
for Waste Management. Interfaces 2005 [online] 35 (1), 24 36. Available from doi
10.1287/inte.1040.0109 [Accessed 19th August, 2009].
31. Salvato Joseph A. (1992); Environmental Engineering and Sanitation. 4th Edition. New
York, John Wiley & Sons. Inc
32. Stravropoulos P. (2004) Energy Recovery and Sustainability of sewage sludge
incineration. MSc Thesis; Imperial College London.
33. Takada Hldeshige, John W. Farrington, Michael H. Bothner, Carl G. Johnson and
Bruce W. Tripp (1994): Transport of Sludge-Derived Organic Pollutants to Deep-sea
Sediments at Deep Water Dump Site 106. Environmental Science Technology 1994
Available from http://pubs.acs.org doi:10.102/es00055a015 [Accessed 19th
August, 2009]
34. Turovskiy I. S. and Mathai P. K. (2006): Wastewater Sludge Processing, New Jersey,
U.S.A. John Wiley & Sons.
35. Vesilind P. A. and Ramsey T. B. (1996): Effect of drying temperature on the fuel
value of wastewater sludge. Wastewater Management and Research 1996; 14:189196.
36. Werther J. and Ogada T. (1999): Sewage Sludge Combustion. Progress in Energy
and Combustion Science. [online] 25 (1), 55 116. Available from doi:10.1016/S03601285(98)00020-3 [Accessed 28th January, 2009]

69

References

37.

www.yorkshirewater.com/our-environment/carbon-management/reducing-waste.aspx

38.

Zabaniotou A, and Theofilou C. (2006); Green energy at cement kiln in Cyprus Use
of sewage sludge as a conventional fuel substitute. Renewable and Sustainable Energy
Reviews.

[online]

12

(2008)

531

541.

Available

from

doi:10.1016/j.rser.2006.07.017 [Accessed 2nd February, 2009]


39.

Zografus Konstantinos G. and Davis Christian F. (1989); Multi-Objective


Programming Approach for Routing Hazardous Materials. Journal of Transportation
Engineering.

[online]

15

(6)

661

673.

Available

from

http://dx.doi.org/10.1061/(ASCE)0733-947X(1989)115:6(661). [Accessed 28 August,


2009]

70

APPENDIX 1A: Data for Transfer Check (Scenario One)


Sludge Intake

Q Ind
[tds/annum]

Q Cap
[tds/an
num]

Dry Solids
[%age]

Works
Name

Site
Type

Destination

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Tanker
Size [m3]

A/STW

Export

F_1/STF

500

B/STW

Export

F_2/STF

250

C/STW

Export

T1/STF

500

D/STW

Export

T3/STF

300

E/STW

Export

T2/STF

500

T1/STF

Transfer

Any Final

F_1/STF

Final

F_2/STF

Sludge
Produced

Raw

Th

UC

DC

Raw

No

No

No

No

No

No

Raw

No

No

No

No

No

No

20

Thickened

No

No

No

No

No

No

15

Raw

No

No

No

No

No

No

15

Undigested
Cake

No

No

No

No

No

No

1600

20

30

50000

12.63

Digested
Cake

Yes

Yes

Yes

No

No

No

Disposal

8100

56.45

220311.39

Disposal

Yes

Yes

Yes

Yes

Yes

No

Final

Disposal

7800

76.35

99163.05

Disposal

Yes

Yes

Yes

Yes

Yes

No

T2/STF

Transfer

Any Final

2000

20

50000

12.64

Digested

Yes

Yes

Yes

No

No

No

T3/STF

Transfer

Any Final

1500

25

50000

12

Thickened

Yes

Yes

Yes

No

No

No

F/STW

Export

Any Non
Export

500

10

Raw

No

No

No

No

No

No

G/STW

Export

Any Non
Export

500

10

Raw

No

No

No

No

No

No

H/STW

Export

Any Non
Export

500

10

Raw

No

No

No

No

No

No

I/STW

Export

Any Non
Export

500

10

Raw

No

No

No

No

No

No

71

72

APPENDIX 1B
SCENARIO ONE: TRANSFER CHECK RESULT 1
Total Variable Costs for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

101,173.023

75,879.767

92,741.937

80,095.310

84,310.852

75,879.767

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

75,879.767

65,540.193

73,636.455

75,613.167

85,580.082

78,201.346

Treatment Costs for each time period (monthly)


Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

30,777.600

23,083.200

28,212.800

24,365.600

25,648.000

23,083.200

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

23,083.200

19,086.837

21,365.325

21,295.435

23,891.969

17,404.083

Transportation Costs for sludge type 3 and 5 for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

10,140.618

7,605.463

9,295.566

8,027.989

8,450.515

7,605.463

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

7,605.463

6,760.412

7,605.463

8,450.515

9,718.092

6,023.436

Transportation Costs for sludge type 1, 2 and 4 for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

60,254.805

45,191.104

55,233.571

47,701.721

50,212.338

45,191.104

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

45,191.104

39,646.069

44,562.542

45,593.363

51,473.355

53,711.327

Inventory Costs of sludge for each time period


Month

Aug

Sep

Oct

Nov

Dec

Cost ()

46.875

103.125

273.854

496.667

1,062.500

72

THE FLOW PATTERN OF SLUDGE.


Xikst Wet volume of sludge transported from export works i to final treatment works k
over period t.

1. A/STW to F_1/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

5000.000

3750.000

4583.333

3958.333

4166.667

3750.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

3750.000

3333.333

3750.000

4166.667

4791.667

5000.000

2. B/STW to F_2/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1250.000

937.500

1145.833

989.583

1041.667

937.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

937.500

833.333

937.500

1041.667

1197.917

1250.000

3. F/STW to F_2/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2500.000

1875.000

2291.667

1979.167

2083.333

1875.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1875.000

1666.667

1875.000

2083.333

2395.833

2500.000

Yijst Wet volume of sludge transported from export works i to transfer treatment
works j over period t.
1. C/STW to T_1/STF (Thickened Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1666.667

1250.000

1527.778

1319.444

1388.889

1250.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1250.000

1111.111

1250.000

1388.889

1597.222

1666.667

73

2. D/STW to T_3/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

750.000

562.500

687.500

593.750

625.000

562.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

562.500

500.000

562.500

625.000

718.750

750.000

3. E/STW to T_2/STF (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m )

1000.000

750.000

916.667

791.667

833.333

750.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

750.000

666.667

750.000

833.333

958.333

1000.000

4. G/STW to T_1/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

500.000

375.000

458.333

395.833

416.667

375.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

375.000

333.333

375.000

416.667

479.167

500.000

5. G/STW to T_2/STF (Raw Sludge))


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2000.000

1500.000

1833.333

1583.333

1666.667

1500.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1500.000

1333.333

1500.000

1666.667

1916.667

2000.000

6. H/STW to T_1/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2500.000

1875.000

2291.667

1979.167

2083.333

1875.000

74

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1875.000

1666.667

1875.000

2083.333

2395.833

2500.000

7. I/STW to T_1/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2500.000

1875.000

2291.667

1979.167

2083.333

1875.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1875.000

1666.667

1875.000

2083.333

2395.833

2500.000

Zjkst Wet volume of sludge transported from transfer treatment works j to final
treatment works k over period t.
1. T_1/STF to F_1/STF (Digested Cake Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

800.000

600.000

733.333

633.333

666.667

600.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

600.000

533.333

600.000

666.667

766.667

133.333

2. T_2/STF to F_1/STF (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1050.000

787.500

962.500

831.250

875.000

787.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

787.500

700.000

787.500

153.472

3. T_3/STF to F_2/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

375.000

281.250

343.750

296.875

312.250

281.250

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

281.250

15.625

75

THE INVENTORIES OF SLUDGE.


Iist - The inventory of sludge at export work i at period t.
(ALL

0.000)

Ijst - The inventory of sludge at transfer treatment works j at period t in tonnes of dry
solid.
Transfer Works j

Sludge type

Month
Aug

T_1/STF

Digested Cake

T_2/STF

Digested

T_3/STF

Thickened

Sep

Oct

Nov

133.333

18.750

41.250

43.292

103.667

166.667

66.250

95.000

125.000

Ikst - The inventory of sludge at final treatment works k at period t in tonnes of dry
solid.
(ALL

Dec

0.000)

76

APPENDIX 1C
SCENARIO ONE: TRANSFER CHECK RESULT 2
Total Variable Costs for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

101,173.023

75,879.767

92,741.937

80,095.310

84,310.852

75,879.767

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

75,879.767

67,448.682

75,879.767

84,310.852

96,957.480

101,173.023

Treatment Costs for each time period (monthly)


Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

30,777.600

23,083.200

28,212.800

24,365.600

25,648.000

23,083.200

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

23,083.200

20,518.400

23,083.200

25,648.000

29,495.200

30,777.600

Transportation Costs for sludge type 3 and 5 for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

10,140.618

7,605.463

9,295.566

8,027.989

8,450.515

7,605.463

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

7,605.463

6,760.412

7,605.463

8,450.515

9,718.092

10,140.618

Transportation Costs for sludge type 1, 2 and 4 for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

60,254.805

45,191.104

55,233.571

47,701.721

50,212.338

45,191.104

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

45,191.104

40,169.870

45,191.104

50,212.338

57,744.188

60,254.805

Inventory Costs of sludge for each time period


(ALL

0.000)

77

THE FLOW PATTERN OF SLUDGE.


Xikst Wet volume of sludge transported from export works i to final treatment works k
over period t.
1. A/STW to F_1/STF (Raw Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

5000.000

3750.000

4583.333

3958.333

4166.667

3750.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

3750.000

3333.333

3750.000

4166.667

4791.667

5000.000

2. B/STW to F_2/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1250.000

937.500

1145.833

989.583

1041.667

937.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

937.500

833.333

937.500

1041.667

1197.917

1250.000

3. F/STW to F_2/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2500.000

1875.000

2291.667

1979.167

2083.333

1875.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1875.000

1666.667

1875.000

2083.333

2395.833

2500.000

Yijst Wet volume of sludge transported from export works i to transfer treatment
works j over period t.
1. C/STW to T_1/STF (Thickened Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1666.667

1250.000

1527.778

1319.444

1388.889

1250.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1250.000

1111.111

1250.000

1388.889

1597.222

1666.667

78

2. D/STW to T_3/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

750.000

562.500

687.500

593.750

625.000

562.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

562.500

500.000

562.500

625.000

718.750

750.000

3. E/STW to T_2/STF (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1000.000

750.000

916.667

791.667

833.333

750.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

750.000

666.667

750.000

833.333

958.333

1000.000

4. G/STW to T_1/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

500.000

375.000

458.333

395.833

416.667

375.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

375.000

333.333

375.000

416.667

479.167

500.000

5. G/STW to T_2/STF (Raw Sludge))


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2000.000

1500.000

1833.333

1583.333

1666.667

1500.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1500.000

1333.333

1500.000

1666.667

1916.667

2000.000

6. H/STW to T_1/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2500.000

1875.000

2291.667

1979.167

2083.333

1875.000

79

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1875.000

1666.667

1875.000

2083.333

2395.833

2500.000

7. I/STW to T_1/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2500.000

1875.000

2291.667

1979.167

2083.333

1875.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1875.000

1666.667

1875.000

2083.333

2395.833

2500.000

Zjkst Wet volume of sludge transported from transfer treatment works j to final
treatment works k over period t.
1. T_1/STF to F_1/STF (Digested Cake Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

800.000

600.000

733.333

633.333

666.667

600.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

600.000

533.333

600.000

666.667

766.667

133.333

Volume (m )

2. T_2/STF to F_1/STF (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1050.000

787.500

962.500

831.250

875.000

787.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

787.500

700.000

787.500

875.000

1006.250

1050.000

3. T_3/STF to F_2/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

375.000

281.250

343.750

296.875

312.250

281.250

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

281.250

250.000

281.250

312.500

359.375

375.000

80

THE INVENTORIES OF SLUDGE.


Iist - The inventory of sludge at export work i at period t.
(ALL

0.000)

Ijst - The inventory of sludge at transfer treatment works j at period t in tonnes of dry
solid.
(ALL

0.000)

Ikst - The inventory of sludge at final treatment works k at period t in tonnes of dry
solid.
(ALL

0.000)

81

APPENDIX 2A: Data for Model Test (Scenario Two)


Works
Name

Site Type

E_A

Export

E_B

Export

Destination
Any Non
Export
Any Non
Export

E_C

Export

E_D

Q Ind
[tds/annum]

Q Cap
[tds/an
num]

Sludge Intake
Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Tanker
Size [m3]

Sludge
Produced

Raw

Th

UC

DC

11451.24

25

Raw

No

No

No

No

No

No

9815.46

25

Raw

No

No

No

No

No

No

F_G

7707.04

Thickened

No

No

No

No

No

No

Export

F_A

5148.78

Raw

No

No

No

No

No

No

E_E

Export

1925

Raw

No

No

No

No

No

No

E_F

Export

3465.07

14.51

Raw

No

No

No

No

No

No

E_G

Export

3317.75

12

Raw

No

No

No

No

No

No

E_H

Export

2582.04

14.51

Raw

No

No

No

No

No

No

E_I

Export

1886.31

25

Thickened

No

No

No

No

No

No

E_J

Export

F_D
Any Non
Export
Any Non
Export
Any Non
Export
Any Non
Export
Any Non
Export

1832.66

14.51

Raw

No

No

No

No

No

No

E_K

Export

T_G

1455.47

Raw

No

No

No

No

No

No

E_L

Export

726.85

3.35

Raw

No

No

No

No

No

No

E_M

Export

700.61

14.51

Raw

No

No

No

No

No

No

E_N

Export

T_A
Any Non
Export
Any Non
Export

544.24

5.94

25

Thickened

No

No

No

No

No

No

E_O

Export

T_E

536.76

17.17

Raw

No

No

No

No

No

No

E_P

Export

F_E

462.05

Raw

No

No

No

No

No

No

E_Q

Export

T_C

445.03

3.45

22

Raw

No

No

No

No

No

No

E_R

Export

T_F

382.6

Raw

No

No

No

No

No

No

E_S

Export

T_D

358.75

Raw

No

No

No

No

No

No

E_T

Export

T_B

220

6.84

27

Thickened

No

No

No

No

No

No

82

Q Cap
[tds/an
num]

Q Ind
[tds/annum]

Sludge Intake

Works
Name

Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Site Type

Destination

F_A

Final

Disposal

18000

20

1418747

F_B

Final

Disposal

1800

53.97

F_C

Final

Disposal

3996

F_D

Final

Disposal

1925

F_E

Final

Disposal

F_F

Final

Disposal

F_G

Final

T_A

Sludge
Produced

Raw

Th

UC

DC

Disposal

Yes

Yes

No

No

No

Yes

221179.62

Disposal

Yes

Yes

Yes

Yes

Yes

No

67.24

139039.17

Disposal

Yes

Yes

Yes

Yes

Yes

No

50.66

91992.97

Disposal

Yes

Yes

No

No

No

No

960

194.75

91315.34

Disposal

Yes

Yes

No

Yes

Yes

No

21864

33.11

1091016.21

Disposal

Yes

Yes

Yes

Yes

Yes

No

Disposal

26400

29.26

2932435.94

Yes

Yes

No

No

No

No

Transfer

F_C

1600

25.71

30

50000

12.63

Yes

Yes

No

No

No

No

T_B

Transfer

F_B

250

30

50000

12.63

Disposal
Undigested
Cake
Undigested
Cake

Yes

Yes

No

No

No

No

T_C

Transfer

Any Final

490

20

50000

27

Digested

Yes

Yes

No

No

No

No

T_D

Transfer

Any Final

996

2.56

73.1

72695.93

27

Yes

Yes

No

No

No

No

T_E

Transfer

Any Final

749

18

30

50000

12.63

Digested
Undigested
Cake

Yes

Yes

No

No

No

No

T_F

Transfer

Any Final

504

2.5

61.4

89123.89

14.51

Digested

Yes

Yes

No

No

No

No

T_G

Transfer

F_F

4500

4.88

10

501313.19

12.63

Digested

Yes

Yes

No

No

No

No

83

Tanker
Size [m3]

APPENDIX 2B
SCENARIO TWO: MODEL TEST RESULT 1
Total Variable Costs for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

693,206.713

567,131.032

756,267.835

598,708.156

630,215.435

567,154.314

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

567,131.032

504,116.473

564,279.840

625,550.413

667,478.612

670,602.060

Treatment Costs for each time period (monthly)


Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

171,889.638

140,636.977

187,515.969

148,450.142

156,263.307

140,636.977

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

140,636.977

125,010.646

140,210.047

155,570.412

167,696.594

169,578.415

Transportation Costs for sludge type 3 and 5 for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

5,364.355

4,389.018

5,852.024

4,632.852

4,876.686

4,389.018

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

4,389.018

3,901.349

4,389.018

4,876.686

3,851.471

120.084

Transportation Costs for sludge type 1, 2 and 4 for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

515,906.158

422,105.038

562,806.717

445,555.318

469,005.598

422,105.038

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

422,105.038

375,204.478

419,648.540

465,018.761

495,065.119

498,847.050

Inventory Costs of sludge for each time period


Month

Jan

Cost ()

46.562

Feb

Mar

Apr

May

Jun

93.125

69.844

69.844

23.281

84

Month

Jul

Aug

Cost ()

Sep

Oct

Nov

Dec

32.236

84.553

865.428

2,056.510

THE FLOW PATTERN OF SLUDGE.


Xikst Wet volume of sludge transported from export works i to final treatment works k
over period t.
1. E_A to F_G (Raw Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

34989.900

28628.100

38170.800

30218.550

31809.000

28628.100

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

28628.100

25447.200

28628.100

31809.000

36580.350

38170.800

2. E_B to F_F (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

29991.683

24538.650

32718.200

25901.908

27265.167

24538.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

24538.650

21812.133

24538.650

27265.167

31354.942

32718.200

3. E_C to F_G (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

14129.573

11560.560

15414.080

12202.813

12845.067

11560.560

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

11560.560

10276.053

11560.560

12845.067

14771.827

15414.080

4. E_D to F_A (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

15732.383

12871.950

17162.600

13587.058

14302.167

12871.950

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

12871.950

11441.733

12871.950

14302.167

16447.492

85

17162.600

5. E_E to F_D (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

5881.944

4812.500

6416.667

5079.861

5347.222

4812.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

4812.500

4277.778

4812.500

5347.222

6149.306

6416.667

6. E_F to F_A (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

10587.714

8662.675

11550.233

9143.935

9625.194

8662.675

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

8662.675

7700.156

8662.675

9625.194

11068.974

11550.233

7. E_G to F_B (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

4827.778

3950.000

5266.667

4169.444

4388.889

3950.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

3950.000

3511.111

3950.000

4388.889

5047.222

5961.111

8. E_H to F_F (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m )

7889.567

6455.100

8606.800

6813.717

7172.333

6455.100

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

6455.100

5737.867

6455.100

7172.333

8248.183

8606.800

9. E_I to F_A (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

3458.235

2829.465

3772.620

2986.657

3143.850

2829.465

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

2829.465

2515.080

2829.465

3143.850

3615.427

86

3772.620

10. E_J to F_F (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

5599.794

4581.650

6108.867

4836.186

5090.722

4581.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

4581.650

4072.578

4581.650

5090.722

5854.331

6108.867

11. E_M to F_G (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2140.753

1751.525

2335.367

1848.832

1946.139

1751.525

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1751.525

1556.911

1751.525

1946.139

2238.060

2335.367

12. E_N to F_G (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

839.877

687.172

916.229

725.348

763.524

687.172

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

687.172

610.819

687.172

763.524

878.053

916.229

13. E_P to F_E (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1411.819

1155.125

1540.167

1219.299

1283.472

1155.125

Month

Jul

Aug

Sep

Oct

Nov

Dec

1155.125

1026.778

1283.472

1475.993

Volume (m )

1155.125

1540.167

Yijst Wet volume of sludge transported from export works i to transfer treatment
works j over period t.
1. E_G to T_G (Raw Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

5309.792

4344.375

5792.500

4585.729

4827.083

4344.375

87

Month

Jul

Aug

Sep

Oct

Nov

Volume (m3)

4344.375

3861.667

4344.375

4827.083

5551.146

Dec
5098.056

2. E_K to T_G (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

4447.269

3638.675

4851.567

3840.824

4042.972

3638.675

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

3638.675

3234.378

3638.675

4042.972

4649.418

4851.567

3. E_L to T_A (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1988.893

1627.276

2169.701

1717.680

1808.085

1627.276

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1627.276

1446.468

1627.276

1808.085

2079.297

2169.701

4. E_O to T_E (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

286.564

234.461

312.615

247.487

260.513

234.461

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

234.461

208.410

234.461

260.513

299.589

312.615

5. E_Q to T_C (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1182.447

967.457

1289.942

1021.204

1074.952

967.457

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

967.457

859.961

967.457

1074.952

1236.194

88

1289.942

6. E_R to T_F (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1169.056

956.500

1275.333

1009.639

1062.778

956.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

956.500

850.222

956.500

1062.778

1222.194

1275.333

7. E_S to T_D (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1096.181

896.875

1195.833

946.701

996.528

896.875

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

896.875

797.222

896.875

996.528

1146.007

1195.833

8. E_T to T_B (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

294.834

241.228

321.637

254.630

268.031

241.228

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

241.228

214.425

241.228

268.031

308.236

321.637

Zjkst Wet volume of sludge transported from transfer treatment works j to final
treatment works k over period t.
1. T_A to F_C (Undigested Cake Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

259.152

212.033

282.711

223.813

235.593

212.033

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

212.033

188.474

212.033

235.593

35.037

2. T_B to F_B (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

336.111

275.000

366.667

290.278

305.556

275.000

89

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

275.000

244.444

275.000

305.556

351.389

19.444

3. T_C to F_F (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1427.805

1168.204

1557.605

1233.104

1298.004

1168.204

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1168.204

1038.403

1168.204

1298.004

1008.643

4. T_D to F_F (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

899.211

735.718

980.957

776.591

817.464

735.718

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

735.718

653.971

232.035

5. T_E to F_F (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

273.350

223.650

298.200

236.075

248.500

223.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

223.650

198.800

223.650

248.500

237.216

6. T_F to F_C (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

982.007

803.460

1071.280

848.097

892.733

803.460

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

803.460

714.187

803.460

892.733

417.923

90

7. T_G to F_F (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

4198.735

3435.329

4580.439

3626.180

3817.032

3435.329

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

3435.329

3053.626

3435.329

3817.032

986.760

THE INVENTORIES OF SLUDGE.


Iist - The inventory of sludge at export work i at period t.
(ALL

0.000)

Ijst - The inventory of sludge at transfer treatment works j at period t in tonnes of dry
solid.
Transfer Works j

Sludge type

Month
Sep

T_A

Undigested Cake

T_B

Undigested Cake

T_C

Digested

T_D

Digested

T_E

Oct

Nov

Dec

60.648

133.333
20.833

9.681

40.833

57.887

83.000

Undigested Cake

8.741

62.417

T_F

Digested

15.218

42.000

T_G

Digested

166.058

375.000

12.894

33.821

Ikst - The inventory of sludge at final treatment works k at period t in tonnes of dry
solid.
Final treatment

Sludge type

Month

Works k
Jan
F_B

Raw

F_B

Undigested Cake

15.000

F_D

Raw

16.042

Mar

Apr

May

Jun

Nov

Dec

30.000

22.500

22.500

7.500

22.500

52.500

32.083

24.062

24.062

8.021

24.062

56.146

91

APPENDIX 2C
SCENARIO TWO: MODEL TEST RESULT 2
Total Variable Costs for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

696,396.960

567,131.032

762,648.328

602,247.687

633,754.966

568,334.157

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

567,131.032

504,116.473

567,131.032

630,145.591

725,981.358

753,895.231

Treatment Costs for each time period (monthly)


Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

171,577.743

140,636.977

186,892.179

148,450.142

156,263.307

140,636.977

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

140,636.977

125,010.646

140,636.977

156,263.307

178,211.703

175,132.200

Transportation Costs for sludge type 3 and 5 for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

5,364.355

4,389.018

5,852.024

4,632.852

4,876.686

4,389.018

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

4,389.018

3,901.349

4,389.018

4,876.686

5,608.189

5,852.024

Transportation Costs for sludge type 1, 2 and 4 for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

517,048.612

422,105.038

565,091.625

445,555.318

469,005.598

422,105.038

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

422,105.038

375,204.478

422,105.038

469,005.598

535,508.491

495,931.132

92

Inventory Costs of sludge for each time period


Month

Jan

Cost ()

2,406.250

Month

Feb

Jul

Mar

Apr

May

4,812.500

3,609.375

3,609.375

Aug

Sep

Oct

Cost ()

Jun
1,203.125

Nov

Dec

6,652.975

76,979.875

THE FLOW PATTERN OF SLUDGE.


Xikst Wet volume of sludge transported from export works i to final treatment works k
over period t.
1. E_A to F_G (Raw Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

34989.900

28628.100

38170.800

30218.550

31809.000

28628.100

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

28628.100

25447.200

28628.100

31809.000

36580.350

38170.800

2. E_B to F_F (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

29991.683

24538.650

32718.200

25901.908

27265.167

24538.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

24538.650

21812.133

24538.650

27265.167

31354.942

32718.200

3. E_C to F_G (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

14129.573

11560.560

15414.080

12202.813

12845.067

11560.560

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

11560.560

10276.053

11560.560

12845.067

14771.827

15414.080

93

4. E_D to F_A (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

15732.383

12871.950

17162.600

13587.058

14302.167

12871.950

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

12871.950

11441.733

12871.950

14302.167

16447.492

17162.600

5. E_E to F_D (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

5881.944

4812.500

6416.667

5079.861

5347.222

4812.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

4812.500

4277.778

4812.500

5347.222

6149.306

6416.667

6. E_F to F_A (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

10587.714

8662.675

11550.233

9143.935

9625.194

8662.675

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

8662.675

7700.156

8662.675

9625.194

11068.974

11550.233

7. E_G to F_B (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

4327.778

3950.000

4266.667

4169.444

4388.889

3950.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

3950.000

3511.111

3950.000

4388.889

4297.222

4266.667

8. E_H to F_F (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

7889.567

6455.100

8606.800

6813.717

7172.333

6455.100

94

Month

Jul

Aug

Sep

Oct

Nov

Volume (m3)

6455.100

5737.867

6455.100

7172.333

8248.183

Dec
8606.800

9. E_I to F_A (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

3458.235

2829.465

3772.620

2986.657

3143.850

2829.465

Month

Jul

Aug

Sep

Oct

Nov

Dec

2829.465

2515.080

2829.465

3143.850

3615.427

Volume (m )

3772.620

10. E_J to F_F (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

5599.794

4581.650

6108.867

4836.186

5090.722

4581.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

4581.650

4072.578

4581.650

5090.722

5854.331

6108.867

11. E_M to F_G (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2140.753

1751.525

2335.367

1848.832

1946.139

1751.525

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1751.525

1556.911

1751.525

1946.139

2238.060

2335.367

12. E_N to F_G (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

839.877

687.172

916.229

725.348

763.524

687.172

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

687.172

610.819

687.172

763.524

878.053

95

916.229

13. E_P to F_E (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1411.819

1155.125

1540.167

1219.299

1283.472

1155.125

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1155.125

1026.778

1283.472

1475.993

1155.125

1540.167

Yijst Wet volume of sludge transported from export works i to transfer treatment
works j over period t.
1. E_G to T_G (Raw Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

5809.792

4344.375

6792.500

4585.729

4827.083

4344.375

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

4344.375

3861.667

4344.375

4827.083

6301.146

6792.500

2. E_K to T_G (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

4447.269

3638.675

4851.567

3840.824

4042.972

3638.675

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

3638.675

3234.378

3638.675

4042.972

4649.418

4851.567

3. E_L to T_A (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1988.893

1627.276

2169.701

1717.680

1808.085

1627.276

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1627.276

1446.468

1627.276

1808.085

2079.297

96

2169.701

4. E_O to T_E (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

286.564

234.461

312.615

247.487

260.513

234.461

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

234.461

208.410

234.461

260.513

299.589

312.615

5. E_Q to T_C (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1182.447

967.457

1289.942

1021.204

1074.952

967.457

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

967.457

859.961

967.457

1074.952

1236.194

1289.942

6. E_R to T_F (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1169.056

956.500

1275.333

1009.639

1062.778

956.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

956.500

850.222

956.500

1062.778

1222.194

1275.333

7. E_S to T_D (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1096.181

896.875

1195.833

946.701

996.528

896.875

Month

Jul

Aug

Sep

Oct

Nov

Dec

896.875

797.222

896.875

996.528

1146.007

Volume (m )

1195.833

8. E_T to T_B (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

294.834

241.228

321.637

254.630

268.031

241.228

97

Month

Jul

Aug

Sep

Oct

Nov

Volume (m3)

241.228

214.425

241.228

268.031

308.236

Dec
321.637

Zjkst Wet volume of sludge transported from transfer treatment works j to final
treatment works k over period t.
1. T_A to F_C (Undigested Cake Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

259.152

212.033

282.711

223.813

235.593

212.033

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

212.033

188.474

212.033

235.593

270.931

282.711

2. T_B to F_B (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

336.111

275.000

366.667

290.278

305.556

275.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

275.000

244.444

275.000

305.556

351.389

366.667

3. T_C to F_F (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1427.805

1168.204

1557.605

1233.104

1298.004

1168.204

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1168.204

1038.403

1168.204

1298.004

1492.705

4. T_D to F_F (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

899.211

735.718

980.957

776.591

817.464

735.718

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

735.718

653.971

735.718

817.464

940.084

98

5. T_E to F_F (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

273.350

223.650

298.200

236.075

248.500

223.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

223.650

198.800

223.650

248.500

285.775

298.200

6. T_F to F_C (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

982.007

803.460

1071.280

848.097

892.733

803.460

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

803.460

714.187

803.460

892.733

417.923

7. T_G to F_F (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

4413.899

3435.329

5010.766

3626.180

3817.032

3435.329

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

3435.329

3053.626

3435.329

3817.032

4712.333

THE INVENTORIES OF SLUDGE.


Iist - The inventory of sludge at export work i at period t.
(ALL

0.000)

Ijst - The inventory of sludge at transfer treatment works j at period t in tonnes of dry
solid.
Transfer Works j

Sludge type

Month
Nov

Dec

T_C

Digested

31.152

T_D

Digested

25.112

T_F

Digested

T_G

Digested

99

15.218

42.000
244.525

Ikst - The inventory of sludge at final treatment works k at period t in tonnes of dry
solid.
Final treatment

Sludge type

Month

Works k

F_D

Raw

Jan

Mar

Apr

May

Jun

Nov

Dec

16.042

32.083

24.062

24.062

8.021

24.062

56.146

100

APPENDIX 3A: Data for Final Cost Check (Scenario Three)


Sludge Intake
Works
Name

Site
Type

Destination

Q Ind
[tds/annum]

Q Cap
[tds/annum]

E1/STW

Export

E2/STW

Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Tanker
Size [m3]

F3/STF

11451.24

Export

F11/STF

9815.46

E3/STW

Export

F12/STF

7707.04

E4/STW

Export

F12/STF

7401.85

E5/STW

Export

F8/STF

5195.66

E6/STW

Export

F4/STF

E7/STW

Export

E8/STW

Sludge
Produced

Raw

Th

UC

DC

Raw

No

No

No

No

No

No

Raw

No

No

No

No

No

No

Thickened

No

No

No

No

No

No

Raw

No

No

No

No

No

No

14.51

Raw

No

No

No

No

No

No

5148.78

Raw

No

No

No

No

No

No

F9/STF

4459.36

Raw

No

No

No

No

No

No

Export

F5/STF

4384.75

Raw

No

No

No

No

No

No

E9/STW

Export

T13/STF

3845.65

Raw

No

No

No

No

No

No

E10/STW

Export

T5/STF

3465.07

14.51

Raw

No

No

No

No

No

No

E11/STW

Export

F22/STF

3317.75

Raw

No

No

No

No

No

No

E12/STW

Export

F15/STF

2731.36

Raw

No

No

No

No

No

No

E13/STW

Export

F7/STF

2642.83

Raw

No

No

No

No

No

No

E14/STW

Export

F1/STF

2582.04

Raw

No

No

No

No

No

No

E15/STW

Export

F16/STF

2257.09

Raw

No

No

No

No

No

No

101

Sludge Intake
Works
Name

Site
Type

Destination

Q Ind
[tds/annum]

Q Cap
[tds/annum]

E16/STW

Export

E17/STW

Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Tanker
Size [m3]

Any Non
Export

1927.63

25

Export

F14/STF

1832.66

E18/STW

Export

T11/STF

1455.47

E19/STW

Export

1142.08

E20/STW

Export

F6/STF
Any Non
Export

1137.06

E21/STW

Export

1127.44

E22/STW

Export

F20/STF
Any Non
Export

E23/STW

Export

Any Non
Export

E24/STW

Export

E25/STW

Sludge
Produced

Raw

Th

UC

DC

Thickened

No

No

No

No

No

No

Raw

No

No

No

No

No

No

Raw

No

No

No

No

No

No

Raw

No

No

No

No

No

No

5.14

25

Raw

No

No

No

No

No

No

Raw

No

No

No

No

No

No

979.52

4.45

25

Thickened

No

No

No

No

No

No

918.18

14.51

Raw

No

No

No

No

No

No

Any Non
Export

900.86

4.04

25

Raw

No

No

No

No

No

No

Export

Any Non
Export

869.04

5.4

25

Thickened

No

No

No

No

No

No

E26/STW

Export

F21/STF

860.47

Raw

No

No

No

No

No

No

E27/STW

Export

856.73

Raw

No

No

No

No

No

No

E28/STW

Export

F2/STF
Any Non
Export

855.21

3.19

25

Raw

No

No

No

No

No

No

E29/STW

Export

Any Non
Export

788.61

25

Raw

No

No

No

No

No

No

E30/STW

Export

Any Non
Export

785.67

5.17

25

Raw

No

No

No

No

No

No

102

Sludge Intake
Works
Name

Site
Type

Destination

Q Ind
[tds/annum]

Q Cap
[tds/annum]

E31/STW

Export

E32/STW

Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Tanker
Size [m3]

T1/STF

726.85

3.35

Export

T12/STF

700.61

E33/STW

Export

T9/STF

675.04

E34/STW

Export

635.6

E35/STW

Export

F19/STF
Any Non
Export

550.69

E36/STW

Export

Any Non
Export

E37/STW

Export

Any Non
Export

E38/STW

Export

E39/STW

Export

E40/STW

Export

E41/STW

Sludge
Produced

Raw

Th

UC

DC

Raw

No

No

No

No

No

No

Raw

No

No

No

No

No

No

Raw

No

No

No

No

No

No

Raw

No

No

No

No

No

No

3.55

27

Thickened

No

No

No

No

No

No

544.24

5.94

25

Thickened

No

No

No

No

No

No

537.09

2.75

27

Raw

No

No

No

No

No

No

T7/STF
Any Non
Export

536.76

17.17

Raw

No

No

No

No

No

No

530.22

5.24

25

Raw

No

No

No

No

No

No

519.46

Raw

No

No

No

No

No

No

Export

F17/STF
Any Non
Export

500.95

14.5

Thickened

No

No

No

No

No

No

E42/STW

Export

Any Non
Export

494.66

5.05

25

Raw

No

No

No

No

No

No

E43/STW

Export

Any Non
Export

483.05

2.54

14.5

Thickened

No

No

No

No

No

No

E44/STW

Export

T14/STF

478.26

Raw

No

No

No

No

No

No

Export

Any Non
Export

477.36

4.05

27

Raw

No

No

No

No

No

No

E45/STW

103

Sludge Intake
Works
Name

Site
Type

Destination

Q Ind
[tds/annum]

Q Cap
[tds/annum]

E46/STW

Export

E47/STW

Export

E48/STW

Export

E49/STW

Export

F10/STF
Any Non
Export

E50/STW

Export

E51/STW

Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Tanker
Size [m3]

Any Non
Export

471.94

2.55

Any Non
Export

469.61

6.61

462.05

455.62

Any Non
Export

448.62

Export

T10/STF

E52/STW

Export

E53/STW

Export

T6/STF
Any Non
Export

E54/STW

Export

Any Non
Export

E55/STW

Export

Any Non
Export

E56/STW

Export

E57/STW

Export

F18/STF
Any Non
Export

E58/STW

Export

E59/STW
E60/STW

Sludge
Produced

Raw

Th

UC

DC

22

Raw

No

No

No

No

No

No

27

Thickened

No

No

No

No

No

No

Raw

No

No

No

No

No

No

5.84

27

Raw

No

No

No

No

No

No

25

Raw

No

No

No

No

No

No

445.5

Raw

No

No

No

No

No

No

445.03

3.45

Raw

No

No

No

No

No

No

423.32

4.14

27

Thickened

No

No

No

No

No

No

408.16

5.36

18

Thickened

No

No

No

No

No

No

407.15

4.89

27

Thickened

No

No

No

No

No

No

400.88

Raw

No

No

No

No

No

No

398.2

3.44

25

Thickened

No

No

No

No

No

No

Any Non
Export

392.54

14.51

Thickened

No

No

No

No

No

No

Export

T8/STF

382.6

Raw

No

No

No

No

No

No

Export

F24/STF

358.75

Raw

No

No

No

No

No

No

104

Sludge Intake
Works
Name

Site
Type

Destination

Q Ind
[tds/annum]

Q Cap
[tds/annum]

E61/STW

Export

E62/STW

Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Tanker
Size [m3]

Any Non
Export

345.47

4.67

Export

Any Non
Export

342.67

2.33

E63/STW

Export

Any Non
Export

335.91

E64/STW

Export

Any Non
Export

330.36

E65/STW

Export

Any Non
Export

326.04

E66/STW

Export

Any Non
Export

E67/STW

Export

E68/STW

Sludge
Produced

Raw

Th

UC

DC

18

Thickened

No

No

No

No

No

No

25

Raw

No

No

No

No

No

No

18

Raw

No

No

No

No

No

No

3.85

27

Raw

No

No

No

No

No

No

25

Raw

No

No

No

No

No

No

307.41

25

Raw

No

No

No

No

No

No

Any Non
Export

296.46

14.51

Raw

No

No

No

No

No

No

Export

Any Non
Export

295.36

3.96

25

Raw

No

No

No

No

No

No

E69/STW

Export

Any Non
Export

275

18

Raw

No

No

No

No

No

No

E70/STW

Export

Any Non
Export

266.22

14.51

Thickened

No

No

No

No

No

No

E71/STW

Export

Any Non
Export

258.31

14.5

Raw

No

No

No

No

No

No

E73/STW

Export

E72/STW
E74/STW
E75/STW

254.57

6.84

27

Thickened

No

No

No

No

No

No

Export

T4/STF
Any Non
Export

245.34

18

Raw

No

No

No

No

No

No

Export

Any Non
Export

245.06

4.02

25

Raw

No

No

No

No

No

No

Export

Any Non
Export

240.13

3.05

14.5

Raw

No

No

No

No

No

No

105

Sludge Intake
Works
Name

Site
Type

Destination

Q Ind
[tds/annum]

Q Cap
[tds/annum]

E76/STW

Export

E77/STW

Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Tanker
Size [m3]

Any Non
Export

235.09

14.51

Export

Any Non
Export

230.24

3.73

E78/STW

Export

Any Non
Export

222.37

E79/STW

Export

221.59

E80/STW

Export

T2/STF
Any Non
Export

220.96

E81/STW

Export

Any Non
Export

220.11

E82/STW

Export

Any Non
Export

E83/STW

Export

E84/STW

Sludge
Produced

Raw

Th

UC

DC

Thickened

No

No

No

No

No

No

18

Raw

No

No

No

No

No

No

14.5

Raw

No

No

No

No

No

No

Raw

No

No

No

No

No

No

14.51

Raw

No

No

No

No

No

No

4.91

25

Raw

No

No

No

No

No

No

218.27

5.21

25

Raw

No

No

No

No

No

No

Any Non
Export

209.22

3.5

14.5

Raw

No

No

No

No

No

No

Export

Any Non
Export

207.41

5.94

18

Raw

No

No

No

No

No

No

E85/STW

Export

Any Non
Export

207

14.51

Thickened

No

No

No

No

No

No

E86/STW

Export

Any Non
Export

207

5.06

20

Raw

No

No

No

No

No

No

E87/STW

Export

Any Non
Export

200.59

2.83

27

Thickened

No

No

No

No

No

No

E88/STW

Export

Any Non
Export

194.19

4.44

25

Raw

No

No

No

No

No

No

E89/STW

Export

Any Non
Export

191.04

14.51

Raw

No

No

No

No

No

No

Export

Any Non
Export

190.29

18

Raw

No

No

No

No

No

No

E90/STW

106

Sludge Intake
Works
Name

Site
Type

Destination

Q Ind
[tds/annum]

Q Cap
[tds/annum]

E92/STW

Export

E93/STW

Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Tanker
Size [m3]

F13/STF

0.01

Export

F23/STF

0.01

F1/STF

Final

Disposal

7545

F2/STF

Final

Disposal

2268.24

F3/STF

Final

Disposal

F4/STF

Final

Disposal

F5/STF

Final

F6/STF

Sludge
Produced

Raw

Th

UC

DC

Digested Cake

No

No

No

No

No

No

Digested

No

No

No

No

No

No

56.45

220311.39

Disposal

Yes

Yes

No

Yes

Yes

No

65

99163.05

Disposal

Yes

Yes

Yes

Yes

Yes

No

14650

48.27

1619179.24

Disposal

Yes

Yes

No

No

No

Yes

15081.5

54.92

1418747.01

Disposal

Yes

Yes

No

No

No

Yes

Disposal

5400

63.59

246493.87

Disposal

Yes

Yes

Yes

No

No

No

Final

Disposal

2642.38

53.97

221179.62

Disposal

Yes

Yes

No

Yes

Yes

No

F7/STF

Final

Disposal

4242.45

65

139039.17

Disposal

Yes

Yes

No

Yes

Yes

No

F8/STF

Final

Disposal

18815.77

30.86

1785521.33

Disposal

Yes

Yes

Yes

No

No

No

F9/STF

Final

Disposal

9871.05

65

91992.97

Disposal

Yes

Yes

No

No

No

No

F10/STF

Final

Disposal

890

65

91315.34

Disposal

Yes

Yes

No

Yes

Yes

No

F11/STF

Final

Disposal

16008.38

33.11

1091016.21

Disposal

Yes

Yes

Yes

Yes

Yes

No

F12/STF

Final

Disposal

25853.66

29.26

2932435.94

Disposal

Yes

Yes

No

No

No

No

F13/STF

Final

Disposal

750

42.84

1614.96

Disposal

No

No

No

No

Yes

No

107

Sludge Intake
Works
Name

Site
Type

Destination

Q Ind
[tds/annum]

Q Cap
[tds/annum]

F14/STF

Final

F15/STF

Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Disposal

3932

65

278142.7

Final

Disposal

5140.45

65

F16/STF

Final

Disposal

4750

F17/STF

Final

Disposal

660

F18/STF

Final

Disposal

F19/STF

Final

Disposal

F20/STF

Final

F21/STF

Tanker
Size [m3]

Sludge
Produced

Raw

Th

UC

DC

Disposal

Yes

Yes

No

Yes

Yes

No

225496.63

Disposal

Yes

Yes

No

Yes

Yes

No

65

240881.44

Disposal

Yes

Yes

No

Yes

Yes

No

97.56

43054.27

Disposal

Yes

Yes

No

No

No

No

583.7

8.62

39961.67

Disposal

Yes

Yes

No

No

No

No

2300

50.94

140460.85

Disposal

Yes

Yes

No

Yes

Yes

No

Disposal

1545.28

65

140320.94

Disposal

Yes

Yes

No

No

Yes

No

Final

Disposal

3117.38

65

118342.59

Disposal

Yes

Yes

No

Yes

Yes

No

F22/STF

Final

Disposal

5037

54.14

212653.21

Disposal

Yes

Yes

No

Yes

Yes

No

F23/STF

Final

Disposal

5995.16

30

50000

Disposal

No

No

No

Yes

Yes

No

F24/STF

Final

Disposal

1455.12

65

72695.93

Yes

Yes

No

No

No

No

T1/STF

Transfer

Any Final

1596

25.71

30

50000

12.63

Disposal
Undigested
Cake

Yes

Yes

No

No

No

No

T2/STF

Transfer

Any Final

1404

75.81

246758.58

14.51

Digested

Yes

Yes

No

No

No

No

T3/STF

Transfer

F13/STF

1356

20

30

50000

Digested Cake

No

No

No

Yes

No

No

T4/STF

Transfer

F11/STF

260

30

50000

14.51

Thickened

Yes

Yes

No

No

No

No

108

Sludge Intake
Works
Name

Site
Type

Destination

Q Ind
[tds/annum]

Q Cap
[tds/annum]

T5/STF

Transfer

T6/STF

Dry Solids
[%age]

Treatment
Cost [/tds]

Fixed Cost
[/annum]

Tanker
Size [m3]

Any Final

6600

21.95

30

50000

12.63

Transfer

Any Final

490.01

30

50000

27

T7/STF

Transfer

Any Final

748.8

18

30

50000

T8/STF

Transfer

Any Final

504

2.5

61.4

T9/STF

Transfer

Any Final

1113.51

3.44

T10/STF

Transfer

Any Final

1482.2

T11/STF

Transfer

F11/STF

T12/STF

Transfer

Any Final

T13/STF

Transfer

T14/STF

Transfer

Sludge
Produced

Raw

Th

UC

DC

Undigested
Cake

Yes

Yes

No

No

No

No

Yes

Yes

No

No

No

No

12.63

Digested
Undigested
Cake

Yes

Yes

No

No

No

No

89123.89

14.51

Digested

Yes

Yes

No

No

No

No

163.88

89629.33

27

Yes

Yes

No

No

No

No

22.03

29.89

102693.34

12.63

Digested
Undigested
Cake

Yes

Yes

No

No

No

No

3000

20

111.09

501313.19

12.63

Undigested
Cake

Yes

Yes

No

No

No

No

1479.8

22.5

47.35

44814.61

12.63

Undigested
Cake

Yes

Yes

No

No

No

No

Any Final

7495.16

30

606673.56

14.51

Digested

Yes

Yes

No

No

No

No

Any Final

480

19.58

30

50000

12.63

Undigested
Cake

Yes

Yes

No

No

No

No

109

APPENDIX 3B
SCENARIO THREE: FINAL COST CHECK RESULT
Total Variable Costs for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

1,223,797.012

1,001,113.578

1,334,323.719

1,051,249.815

1,106,601.972

995,971.174

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

995,997.211

885,371.78

996,052.151

1,095,363.214

1,207,740.377

1,230,236.625

Treatment Costs for each time period (monthly)


Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

517,112.510

423,092.053

564,611.178

446,186.928

469,714.499

422,743.049

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

422,743.049

375,771.599

422,743.049

466,784.164

517,512.063

525,330.162

Transportation Costs for sludge type 3 and 5 for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

22,463.764

18,379.444

24,505.925

19,400.524

20,421.604

18,379.444

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

18,379.444

16,337.283

18,379.444

20,421.604

11,104.691

247.021

Transportation Costs for sludge type 1, 2 and 4 for each time period (monthly)
Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

684,006.982

559,642.076

744,477.130

585,612.584

616,383.773

554,745.396

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

554,745.396

493,107.019

554,745.396

607,696.674

676,541.013

698,462.691

Inventory Costs of sludge for each time period


Month

Jan

Feb

Mar

Apr

May

Jun

Cost ()

213.756

0.004

729.486

49.779

82.096

103.885

110

Month

Jul

Aug

Sep

Oct

Nov

Dec

Cost ()

129.323

155.177

184.262

460.774

2,582.610

6,196.751

THE FLOW PATTERN OF SLUDGE.


Xikst Wet volume of sludge transported from export works i to final treatment works k
over period t.
1. E1/STW to F3/STF (Raw Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

34989.900

28628.100

38170.800

30218.550

31809.000

28628.100

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

28628.100

25447.200

28628.100

31809.000

36580.350

38170.800

2. E2/STW to F11/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

29991.683

24538.650

32718.200

25901.908

27265.167

24538.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

24538.650

21812.133

24538.650

27265.167

31354.942

32718.200

3. E3/STW to F12/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

14129.573

11560.560

15414.080

12202.813

12845.067

11560.560

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

11560.560

10276.053

11560.560

12845.067

14771.827

15414.080

4. E4/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

22616.764

18504.625

24672.833

19532.660

20560.694

18504.625

111

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

18504.625

16448.556

18504.625

20560.694

23644.799

24672.833

5. E5/STW to F8/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

15875.628

12989.150

17318.867

13710.769

14432.389

12989.150

Month

Jul

Aug

Sep

Oct

Nov

Dec

12989.150

11545.911

12989.150

14432.389

16597.247

17318.867

Volume (m )

6. E6/STW to F4/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

15732.383

12871.950

17162.600

13587.058

14302.167

12871.950

Month

Jul

Aug

Sep

Oct

Nov

Dec

12871.950

11441.733

12871.950

14302.167

13447.492

17162.600

Volume (m )

7. E7/STW to F9/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

13625.822

11148.400

14864.533

11767.756

12387.111

11148.400

Month

Jul

Aug

Sep

Oct

Nov

Dec

11148.400

9909.689

11148.400

12387.111

14245.178

14864.533

Volume (m )

8. E8/STW to F5/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

13397.847

10961.875

14615.833

11570.868

12179.861

10961.875

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

10961.875

9743.889

10961.875

12179.861

14006.840

14615.833

112

9. E11/STW to F22/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

10137.569

8294.375

11059.167

8755.174

9215.972

8294.375

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

8294.375

7372.778

8294.375

9215.972

10598.368

11059.167

10. E12/STW to F15/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

8345.822

6828.400

9104.533

7207.756

7587.111

6828.400

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

6828.400

6069.689

6828.400

7587.111

8725.178

9104.533

11. E13/STW to F7/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

8075.314

6607.075

8809.433

6974.135

7341.194

6607.075

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

6607.075

5872.956

6607.075

7341.194

8442.374

8809.433

12. E14/STW to F1/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

7889.567

6455.100

8606.800

6813.717

7172.333

6455.100

Month

Jul

Aug

Sep

Oct

Nov

Dec

6455.100

5737.867

6455.100

7172.333

8248.183

8606.800

Volume (m )

13. E15/STW to F16/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

6896.664

5642.725

7523.633

5956.210

6269.694

5642.725

113

Month

Jul

Aug

Volume (m3)

5642.725

5015.756

Sep
5642.725

Oct

Nov

Dec

6269.694

7210.149

7523.633

14. E16/STW to F8/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

3533.988

2891.445

3855.260

3052.081

3212.717

2819.445

Month

Jul

Aug

Sep

Oct

Nov

Dec

2819.445

2570.173

2891.445

3212.717

2694.624

3855.260

Volume (m )

15. E17/STW to F14/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

5599.794

4581.650

6108.867

4836.186

5090.722

4581.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

4581.650

4072.578

4581.650

5090.722

5854.331

6108.867

Volume (m )

16. E19/STW to F6/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

3489.689

2855.200

3806.933

3013.822

3172.444

2855.200

Month

Jul

Aug

Sep

Oct

Nov

Dec

2855.200

2537.956

2855.200

3172.444

3648.311

3806.933

Volume (m )

17. E20/STW to F8/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2027.831

1659.134

2212.179

1751.308

1843.482

1659.134

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1659.134

1474.786

1659.134

1843.482

2120.005

2212.179

114

18. E21/STW to F20/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

3444.956

2818.600

3758.133

2975.189

3131.778

2818.600

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

2818.600

2505.422

2818.600

3131.778

3601.544

3758.133

Apr

May

Jun

Oct

Nov

Dec

19. E22/STW to F10/STF (Thickened Sludge)


Month

Jan

Feb

Volume (m3)

Month

Mar
384.577

Jul

Aug

Sep

Volume (m3)

384.577

20. E22/STW to F16/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2017.738

1650.876

1816.592

1742.592

1834.307

1650.876

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1650.876

1467.446

1650.876

1834.307

2109.453

1816.592

21. E23/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2805.550

2295.450

3060.600

2422.975

2550.500

2295.450

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

2295.450

2040.400

2295.450

2550.500

2933.075

3060.600

22. E24/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2044.031

1672.389

2229.851

1765.299

1858.210

1672.389

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1672.389

1486.568

1672.389

1858.210

2136.941

2229.851

115

23. E25/STW to F12/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1475.222

1207.000

1609.333

1274.056

1341.111

1207.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1207.000

1072.889

1341.111

1542.278

1609.333

1207.000

24. E26/STW to F21/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2629.214

2151.175

2868.233

2270.685

2390.194

2151.175

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

2151.175

1912.156

2151.175

2390.194

2748.724

2868.233

25. E27/STW to F2/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2617.786

2141.825

2855.767

2260.815

2379.806

2141.825

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

2141.825

1903.844

2141.825

2379.806

2736.776

2855.767

26. E28/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2457.500

2010.682

2680.909

2122.386

2234.091

2010.682

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

2010.682

1787.273

2010.682

2234.091

2569.205

2680.909

27. E29/STW to F8/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2409.642

1971.525

2628.700

2081.054

2190.583

1971.525

Month

Jul

Aug

Sep

Oct

Nov

Dec

1971.525

1752.467

1971.525

2190.583

2519.171

2628.700

Volume (m )

116

28. E30/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1393.032

1139.753

1519.671

1203.073

1266.393

1139.753

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1139.753

1013.114

1139.753

1266.393

1456.352

1519.671

29. E34/STW to F19/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1942.111

1589.000

2118.667

1677.278

1765.556

1589.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1589.000

1412.444

1589.000

1765.556

2030.389

2118.667

30. E35/STW to F24/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1421.969

1163.430

1551.239

1228.065

1292.700

1163.430

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1163.430

1034.160

1163.430

1292.700

1486.604

1551.239

31. E36/STW to F12/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

839.877

687.172

916.229

725.348

763.524

687.172

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

687.172

610.819

687.172

763.524

878.053

916.229

32. E37/STW to F6/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1790.300

1464.791

1953.055

1546.168

1627.545

1464.791

117

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1464.791

1302.036

1464.791

1627.545

1871.677

1953.055

33. E39/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

927.548

758.903

1011.870

801.064

843.225

758.903

Month

Jul

Aug

Sep

Oct

Nov

Dec

758.903

674.580

758.903

843.225

969.709

1011.870

Volume (m )

34. E40/STW to F17/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1587.239

1298.650

1731.533

1370.797

1442.944

1298.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

1298.650

1154.356

1298.650

1442.944

1659.386

1731.533

Volume (m )

35. E41/STW to F19/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

918.408

751.425

1001.900

793.171

834.917

751.425

Month

Jul

Aug

Sep

Oct

Nov

Dec

751.425

667.933

751.425

834.917

960.154

1001.900

Volume (m )

36. E42/STW to F16/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m )

897.898

734.644

979.525

775.457

816.271

734.644

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

734.644

653.017

734.644

816.271

938.711

979.525

118

37. E43/STW to F14/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1743.291

1426.329

1901.772

1505.569

1584.810

1426.329

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1426.329

1267.848

1426.329

1584.810

1822.531

1901.772

38. E_J to F_F (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

5599.794

4581.650

6108.867

4836.186

5090.722

4581.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

4581.650

4072.578

4581.650

5090.722

5854.331

6108.867

39. E45/STW to F8/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1080.444

884.000

1178.667

933.111

982.222

884.000

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

884.000

785.778

884.000

982.222

1129.556

1178.667

40. E46/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1696.516

1388.059

1850.745

1465.173

1542.288

1388.059

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1388.059

1233.830

1388.059

1542.288

1773.631

1850.745

41. E47/STW to F12/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

651.249

532.840

710.454

562.443

592.045

532.840

119

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

532.840

473.636

532.840

592.045

680.852

710.454

42. E48/STW to F10/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1411.819

1155.125

1540.167

1219.299

1283.472

1155.125

Month

Jul

Aug

Sep

Oct

Nov

Dec

1155.125

1026.778

1155.125

1283.472

1475.993

1540.167

Volume (m )

43. E49/STW to F3/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

715.157

585.128

780.171

617.636

650.143

585.128

Month

Jul

Aug

Sep

Oct

Nov

Dec

585.128

520.114

585.128

650.143

747.664

780.171

Volume (m )

44. E50/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1028.087

841.162

1121.550

887.894

934.625

841.162

Month

Jul

Aug

Sep

Oct

Nov

Dec

841.162

747.700

841.162

934.625

1074.819

1121.550

Volume (m )

45. E53/STW to F3/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m )

937.303

766.884

1022.512

809.489

852.093

766.884

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

766.884

681.675

766.884

852.093

979.907

1022.512

120

46. E54/STW to F8/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

698.035

571.119

761.493

602.848

634.577

571.119

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

571.119

507.662

571.119

634.577

729.764

761.493

47. E55/STW to F1/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

Month
Volume (m3)

575.313

48. E55/STW to F3/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

763.233

624.463

832.618

659.156

693.848

624.463

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

624.463

555.078

624.463

693.848

222.612

832.618

49. E56/STW to F18/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1224.911

1002.200

1336.267

1057.878

1113.556

1002.200

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1002.200

890.844

1002.200

1113.556

1280.589

1336.267

50. E57/STW to F16/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1061.095

868.169

1157.558

916.400

964.632

868.169

Month

Jul

Aug

Sep

Oct

Nov

Dec

121

Volume (m3)

868.169

771.705

868.169

964.632

1109.327

1157.558

51. E58/STW to F11/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

719.657

588.510

785.080

621.522

654.233

588.810

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

588.810

523.387

588.810

654.233

752.368

785.080

52. E60/STW to F24/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1096.181

896.875

1195.833

946.701

996.528

896.875

Month

Jul

Aug

Sep

Oct

Nov

Dec

896.875

797.222

896.875

996.528

1146.007

1195.833

Volume (m )

53. E61/STW to F6/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

678.117

554.823

739.764

585.647

616.470

554.823

Month

Jul

Aug

Sep

Oct

Nov

Dec

554.823

493.176

554.823

616.470

708.941

739.764

Volume (m )

54. E62/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1348.129

1103.015

1470.687

1164.294

1225.572

1103.015

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1103.015

980.458

1103.015

1225.572

1409.408

1470.687

55. E63/STW to F8/STF (Raw Sludge)


Month
3

Volume (m )

Jan

Feb

Mar

Apr

May

Jun

1026.392

839.775

1119.700

886.429

933.083

839.775

122

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

839.775

746.467

839.775

933.083

1073.046

1119.700

Mar

Apr

May

Jun

715.065

643.558

56. E64/STW to F8/STF (Raw Sludge)


Month

Jan

Feb

Volume (m3)

786.571

643.558

Month

Jul

Aug

Sep

Oct

Nov

Dec

643.558

572.052

643.558

715.065

822.325

858.078

Mar

Apr

May

Jun

858.078

679.312

Sep

Oct

Nov

Dec

Mar

Apr

May

Jun

Oct

Nov

Dec

Volume (m )

57. E64/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Volume (m3)

Month

Jul

Aug

Volume (m3)
58. E65/STW to F10/STF (Raw Sludge)
Month

Jan

Feb

Volume (m3)

Month

76.267

Jul

Aug

Sep

Volume (m3)

76.267

59. E65/STW to F24/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

996.233

815.100

1010.533

860.383

905.667

815.100

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

815.100

724.533

815.100

905.667

1041.517

1010.533

60. E66/STW to F4/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

380.692

311.475

415.300

328.779

346.083

311.475

123

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

311.475

276.867

311.475

346.083

397.996

415.300

61. E66/STW to F18/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

558.617

457.050

609.400

482.442

507.833

457.050

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

457.050

406.297

457.050

507.833

584.008

609.400

62. E67/STW to F4/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

905.850

741.150

988.200

782.325

823.500

741.150

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

741.150

658.800

741.150

823.500

947.025

988.200

63. E68/STW to F3/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

683.704

559.394

745.859

590.471

621.549

559.394

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

559.394

497.239

621.549

714.781

745.859

559.394

64. E70/STW to F12/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

488.070

399.330

532.440

421.515

443.700

399.330

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

399.330

354.960

399.330

443.700

510.255

532.440

Mar

Apr

May

Jun

65. E71/STW to F1/STF (Raw Sludge)


Month

Jan

Feb

124

Volume (m3)

789.281

645.775

861.033

681.651

717.528

645.775

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

645.775

574.022

645.775

717.528

825.157

861.033

66. E74/STW to F8/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

558.802

457.201

609.602

482.602

508.002

457.201

Month

Jul

Aug

Sep

Oct

Nov

Dec

457.201

406.401

457.201

508.002

584.202

609.602

Volume (m )

67. E75/STW to F14/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

721.702

590.484

787.311

623.288

656.093

590.484

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

590.484

524.874

590.484

656.093

754.507

787.311

68. E76/STW to F11/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

718.331

587.725

783.633

620.376

653.028

587.725

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

587.825

522.422

587.725

653.028

750.982

783.633

69. E77/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

565.827

462.949

617.265

488.668

514.388

462.949

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

462.949

411.510

462.949

514.388

591.546

617.265

Mar

Apr

May

Jun

70. E78/STW to F19/STF (Raw Sludge)


Month

Jan

Feb

125

Volume (m3)

679.464

555.925

741.233

586.810

617.694

555.925

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

555.925

494.156

555.925

617.694

710.349

741.233

71. E80/STW to F8/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

675.156

552.400

736.533

583.089

613.778

552.400

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

552.400

491.022

552.400

613.778

705.844

736.533

72. E81/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

410.932

336.217

448.289

354.896

373.574

336.217

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

336.217

298.859

336.217

373.574

429.610

448.289

73. E82/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

384.032

314.208

418.944

331.664

349.120

314.208

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

314.208

279.296

314.208

349.120

401.488

418.944

74. E83/STW to F19/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

547.957

448.329

597.771

473.236

498.143

448.329

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

448.329

398.514

448.329

498.143

572.864

597.771

126

75. E84/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

320.077

261.881

349.175

276.430

290.979

261.881

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

261.881

232.783

261.881

290.979

334.626

349.175

76. E85/STW to F11/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

474.375

388.125

517.500

409.687

431.250

388.125

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

388.125

345.000

388.125

431.250

495.937

517.500

77. E86/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

375.000

306.818

164.653

323.864

340.909

306.818

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

306.818

272.727

306.818

340.909

Mar

Apr

May

Jun

Oct

Nov

Dec

409.091

78. E86/STW to F14/STF (Raw Sludge)


Month

Jan

Feb

Volume (m3)

Month

244.438

Jul

Aug

Sep

Volume (m3)

392.045

79. E87/STW to F21/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

649.732

531.599

708.799

561.132

590.665

531.599

127

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

531.599

472.532

531.599

590.665

679.265

708.799

80. E88/STW to F12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

400.918

328.024

437.365

364.247

364.471

328.024

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

328.024

291.577

328.024

364.471

419.141

437.365

81. E90/STW to F8/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

581.442

475.725

634.300

502.154

528.583

475.725

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

475.725

422.867

475.725

528.583

607.871

634.300

82. E92/STW to F13/STF (Digested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

0.031

0.025

0.033

0.026

0.028

0.025

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

0.025

0.022

0.025

0.028

0.032

0.033

83. E93/STW to F23/STF (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

0.031

0.025

0.033

0.026

0.028

0.025

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

0.025

0.022

0.025

0.028

0.032

0.033

128

Yijst Wet volume of sludge transported from export works i to transfer treatment
works j over period t.
1. E9/STW to T13/STF (Raw Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

11750.597

9614.125

12878.833

10148.243

10682.361

9614.125

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

9614.125

8545.889

9614.125

10682.361

12284.715

12818.833

2. E10/STW to T5/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

10587.714

8662.675

11550.233

9143.935

9625.194

8662.675

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

8662.675

770.156

8662.675

9625.194

11068.974

11550.233

3. E18/STW to T11/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

4447.269

3638.675

4851.567

3840.824

4042.972

3638.675

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

3638.675

3234.378

3638.675

4042.972

4649.418

4851.567

4. E31/STW to T1/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1988.893

1627.276

2169.701

1717.680

1808.085

1627.276

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1627.276

1446.468

1627.276

1808.085

2079.297

2169.701

5. E32/STW to T12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2140.753

1751.525

2335.367

1848.832

1946.139

1751.525

129

Month

Jul

Aug

Sep

Oct

Nov

Volume (m3)

1751.525

1556.911

1751.525

1946.139

2238.060

Dec
2335.367

6. E33/STW to T9/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

2062.622

1687.600

2250.133

1781.356

1875.111

1687.600

Month

Jul

Aug

Sep

Oct

Nov

Dec

1687.600

1500.089

1687.600

1875.111

2156.378

Volume (m )

2250.133

7. E38/STW to T7/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

286.564

234.461

312.615

247.487

260.513

234.461

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

234.461

208.410

234.461

260.513

299.589

312.615

8. E44/STW to T14/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1461.350

1195.650

1594.200

1262.075

1328.500

1195.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1195.650

1062.800

1195.650

1328.500

1527.775

1594.200

9. E51/STW to T10/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1361.250

1113.750

1485.000

1175.625

1237.500

1113.750

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1113.750

990.000

1113.750

1237.500

1423.125

1485.000

10. E52/STW to T6/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1182.447

967.457

1289.942

1021.204

1074.952

967.457

130

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

967.457

859.961

967.457

1074.952

1236.194

1289.942

11. E59/STW to T8/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1169.056

956.500

1275.333

1009.639

1062.778

956.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

956.500

850.222

956.500

1062.778

1222.194

1275.333

12. E69/STW to T10/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

840.278

687.500

916.667

725.694

763.889

687.500

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

687.500

611.111

687.500

763.889

878.472

916.667

13. E72/STW to T12/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

749.650

613.350

817.800

647.425

681.500

613.350

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

613.350

545.200

613.350

681.500

783.725

817.800

14. E73/STW to T4/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

341.163

279.134

372.178

294.641

310.149

279.134

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

279.134

248.119

279.134

310.149

356.671

372.178

Mar

Apr

May

Jun

15. E79/STW to T2/STF (Raw Sludge)


Month

Jan

Feb

131

Volume (m3)

677.081

553.975

738.633

584.751

615.528

553.975

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

553.975

492.422

553.975

615.528

707.857

738.633

16. E89/STW to T10/STF (Raw Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

583.733

477.600

636.800

504.133

530.667

477.600

Month

Jul

Aug

Sep

Oct

Nov

Dec

477.600

424.533

477.600

530.667

610.267

636.800

Volume (m )

17. E91/STW to T10/STF (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

0.031

0.025

0.033

0.026

0.028

0.025

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

0.025

0.022

0.025

0.028

0.032

0.033

Zjkst Wet volume of sludge transported from transfer treatment works j to final
treatment works k over period t.
1. T1/STF to F8/STF (Undigested Cake Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

259.152

212.033

282.711

223.813

235.593

212.033

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

212.033

188.474

212.033

235.593

36.334

Apr

May

Jun

Oct

Nov

Dec

2. T2/STF to F23/STF (Digested Sludge)


Month

Jan

Feb

Mar

Volume (m3)

710.935

581.674

613.042

Month

Jul

Aug

Sep

Volume (m3)

132

3. T4/STF to F11/STF (Thickened Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

388.926

318.212

424.283

335.891

353.569

318.212

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

318.212

282.586

318.212

353.569

406.605

63.172

4. T5/STF to F8/STF (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1447.068

1183.965

1180.218

1249.741

1315.516

1183.965

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1183.965

1052.413

1183.965

1315.516

585.769

Apr

May

Jun

Sep

Oct

Nov

Dec

5. T5/STF to F11/STF (Undigested Cake Sludge)


Month

Jan

Feb

Volume (m3)

Month

Mar
398.401

Jul

Aug

Volume (m3)
6. T6/STF to F23/STF (Digested Sludge)
Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1427.805

1168.204

1557.605

1233.104

1298.004

1168.204

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1168.204

1038.403

1168.204

1298.004

1008.601

7. T7/STF to F8/STF (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

273.350

223.650

298.200

236.075

248.500

223.650

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

223.650

198.800

223.650

248.500

237.308

133

8. T8/STF to F23/STF (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

982.007

803.460

1071.280

848.097

892.733

803.460

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

803.460

714.187

803.460

892.733

417.923

9. T9/STF to F23/STF (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

1259.159

1030.221

1373.628

1087.455

1144.690

1030.221

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

1030.221

915.752

1030.221

1137.255

10. T10/STF to F8/STF (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

481.377

393.854

525.138

415.735

437.615

393.854

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

393.854

350.092

393.854

437.615

467.721

11. T11/STF to F11/STF (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

667.090

545.801

727.735

576.124

606.446

545.801

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

545.801

485.157

545.801

606.446

175.148

12. T12/STF to F8/STF (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

285.434

233.537

311.382

246.511

259.485

233.537

134

Month

Jul

Aug

Sep

Oct

Nov

Volume (m3)

233.537

207.588

233.537

259.485

61.716

Dec

13. T13/STF to F23/STF (Digested Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

12338.127

10094.831

13459.775

10655.655

11216.479

10094.831

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

10094.831

8973.183

10094.831

6345.372

14. T14/STF to F8/STF (Undigested Cake Sludge)


Month

Jan

Feb

Mar

Apr

May

Jun

Volume (m3)

223.904

183.195

244.259

193.372

203.550

183.195

Month

Jul

Aug

Sep

Oct

Nov

Dec

Volume (m3)

183.195

162.840

183.195

203.550

234.082

39.969

THE INVENTORIES OF SLUDGE.


Iist - The inventory of sludge at export work i at period t.
(ALL

0.000)

Ijst - The inventory of sludge at transfer treatment works j at period t in tonnes of dry
solid.
Transfer

Sludge type

Month

Works j
Jan
T2/STF

Digested

T3/STF

Digested Cake

Transfer

Sludge type

0.00092

Feb

0.002

Mar

Apr

May

Jun

3.250

15.530

28.456

40.090

0.003

0.003

0.004

0.005

Month

Works j
Jul
T1/STF

Undigested Cake

T2/STF

Digested

51.723

Aug

62.064

135

Sep

73.698

Oct

86.624

Nov

Dec

60.315

133.000

101.489

117.000

T3/STF

Digested Cake

0.006

0.006

0.007

0.008

0.009

0.010

T4/STF

Thickened

T5/STF

Undigested Cake

203.493

550.000

T6/STF

Digested

9.682

40.834

T7/STF

Undigested Cake

8.724

62.400

T8/STF

Digested

15.218

42.000

T9/STF

Digested

45.540

92.792

T10/STF

Undigested Cake

7.829

123.517

T11/STF

Undigested Cake

104.453

250.000

T12/STF

Undigested Cake

53.256

123.317

T13/STF

Digested

355.401

624.597

T14/STF

Undigested Cake

21.667

0.256

97.422

40.000

Ikst - The inventory of sludge at final treatment works k at period t in tonnes of dry
solid.
Final

Sludge type

Month

treatment
Works k
Jan

Mar

F3/STF

Thickened

82.436

F8/STF

Raw

143.683

F8/STF

Thickened

111.489

F12/STF

Raw

26.149

F12/STF

Thickened

F18/STF

Raw

Apr

May

Jun

Nov

82.436

105.431
245.055

4.484

Dec

9.728

136

329.818
7.296

7.296

2.432

7.296

17.025

Das könnte Ihnen auch gefallen