Method Statement

For
Well Submersible Pump

Client:

KAHRAMAA
Contractor:

Issued by:
Rev.No

Date

Description

Prepared

9-12-12

Issued for Tender

MV

KAHRAMAA-Well Submersible Pump

Checked Approved
AA

AA

Page 1

WELL SUBMERSIBLE
PUMP
TABLE OF CONTENTS

1.0

TITLE

2.0

SCOPE OF WORKS
2.1
General Description
2.2
Plant and Equipment
2.3
Materials
2.4
Site Planning & Preparation
2.5
Work Methodology

3.0

HEALTH & SAFETY


3.1
Protective & Safety Equipment
3.2
Contractual Requirements
3.3
Information to Personnel
3.4
Emergency Procedures

4.0

QUALITY ASSURANCE
4.1
Contractual Impact Requirement
4.2
Inspection & Testing
4.3
Follow up & Evaluation

KAHRAMAA-Well Submersible Pump

Page 2

TITLE

Method of Statement for Well Submersible Pump

SCOPE OF WORK
2.1.

General Description
This method of statement describes the procedures and sequences involved in
the installation of Well Submersible Pump Works. This procedure is to
established and to define the Well Pump Installation

2.2.

Plant and Equipment


The equipment employed by BUILDERS for the installation shall include the
following as required
Equipment

2.3.

Mechanical Tool Kit

Qty
Lot

Hydraulic Lifting Machine

Generator
Tower Lights
Pick-ups

1
1
1

Remarks

As required
As required

Materials
BUILDERS shall submit product data sheet and/or samples of materials as
requested by the Engineer including full details and technical literature with
names, sources and descriptions, for the following:
1. Submersible Pump
2. Pipes
3 Supports

2.4.

Site Planning & Preparation


2.4.1

Site Preparation

KAHRAMAA-Well Submersible Pump

Page 3

Approved drawings and relevant surveying information including well


station status shall be obtained.
Survey works shall establish benchmarks as needed to execute the
works, preserving all stakes, existing monuments and benchmarks.
Utilities shall be marked and shall be protected.
Necessary work permit shall be obtained.
Required safety material reflecting the risk assessment shall be delivered
to location.
2.4.2

Site Management Plan & Access Routes


Prior to start of the work, necessary site coordination meeting will be
conducted, assigning responsibilities to BUILDERS staff. If the job is
performed at an area that will obstruct other contractors or movement of
traffics, necessary coordination will be done for alternate routes.

2.4.3

Materials Delivery and Storage


All materials shall be stored in designated area, properly identified and
segregated, and protected against damage and deterioration
Safety provision materials such as safety cones, warning tapes, fixed and
solid barriers for edge protection, etc. shall be arranged for barricading
and protection of work site.

2.5.

Work Methodology
2.5.1

Survey, Layout and Preparation

Site survey and layout shall be completed in accordance with Drawings.


2.5.2

Submersible Pump Installation

Check the pump for shipment damage


Check for free rotation prior to installation, even though the pump has
been factory tested, by removing suction screen and rotating the pump
shaft coupling with fingers or a standard screw driver.
The complete pump should be submerge below the drawdown level of the
well, but the motor should be a minimum distance from top of the well
screen.
Use the specified pipe as per the project specification.

KAHRAMAA-Well Submersible Pump

Page 4

Install torque arrestor for well casing using rigid PVC or flexible plastic
piped due to the starting torque of the motor will rub against the inside
walls of the well casing.
Install cable guards to protect the submersible cable from abrasion against
side of the well.
Lay the pump 25mm to 50mm from the well, pointing outward(pump
discharge away from the well).
Lay out plastic pipes, safety ropes, hose clamps, bleeder orifice, piping,
assembly package, tape, submersible cable etc.
Assembly of all components that go into the well should be made
horizontally on the ground and then lowered into the well.
Install a pipe adapter in the pump discharge tapping using Teflon tape.
Do not use pipe wrench on any part of the pump except the cast discharge
of the pump.
Be sure that the working surface is smooth to avoid damage to the plastic
pipe and electric cable. Cut off sealed end of the plastic pipe with
hacksaw.
Slide torque arrestor on plastic pipe from pump end. Pull the motor lead
cable through one of the small outside hole of the torque arrestor.
Position two hose clamps over end of plastic pipe. Slide plastic pipe over
the pipe adapter all the way to the shoulder. Position the clamp tightening
screws opposite each other and away from the motor lead wires to prevent
insulation damage. Tighten the hose clamps and tape clamp tab ends to
pipe with plastic tape.
Slide torque arrestor down from the end of the plastic pipe, and clamp
sufficiently to prevent the torque arrestor from sliding up on the pipe while
lowering unit in well.
Splice the electric cable to the pump leads. Heat shrink tubing and Sta-kon
connectors are recommended. It is necessary that the splice be water tight.
Unroll the electric cable along side of the plastic pipe. Be sure not to
damage wire insulation, and that all kinks are straightened out.

KAHRAMAA-Well Submersible Pump

Page 5

Cut the plastic pipe to proper length.

2.5.3

TESTING AND INSPECTION

Check the pipe connections for any clogged and leaks.


Measure the flow and or pressure at different rates. This can be used to
determine to the overall performance of the pump. Static Water Level and
Pumping Water measurements are also taken
Visual inspection of the Starter Panel, Electric Motor, Pump, and related
pump system components. Running tests include Amp/Voltage readings
and system pressure checks. This basic inspection can be your first line of
defense in preventing major problems before they occur.
The Pump Efficiency Test is performed by installing a Flow Meter on the
discharge of the pump and measuring the volume of flow, draws down in
the well, amp load of the motor, and system pressure. This information is
documented and entered into a computer to calculate Overall Pumping
Plant Efficiency. This test will determine how efficiently water is being
produced by the power input to the pump.
The Well Test consists of installing one Test Pumps to test the
performance of the existing well.
Measure well production at different rates of flow.
Measure sand production to determine if the proper size a pump is
installed on the well and also if sand filtration is needed.
2.5.4

RESPONSIBILITIES

Site Engineer is responsible to coordinate and explain the work to be


carried out to the supervisor or foreman.
Site Engineer is to assure that the installation is as per approved shop
drawing, specifications and recommendations.
Quality representative is responsible for the quality of work as per the

KAHRAMAA-Well Submersible Pump

Page 6

standard practice.
Site Engineer is the responsible person to ensure that the materials use are
as per approved material submittal.
Storekeeper will verify all the documents forwarded are as per the
requirement of purchased order.
Site engineer will inspect the equipment as per the manufacturer
recommendation prior to installation.
Storekeeper will inspect for any damage during shipping, handling and
storage.
Storekeeper will review the documents and verify the items with the
packing list.
Storekeeper is the responsible person for proper storage of the equipment
as per Manufacturers recommendation.
Construction Manager will ensure appropriate measures to avoid any
unexpected events.

2.6.

Organization & Supervision


The general staffing for concrete work shall be as follows, the number of persons
depend on the quantum of work being performed:
- Site Engineer/ Construction Manager
- Quality Control Engineer/Inspector
- Mechanical Foreman
- Pump Mechanic
- Pipe Fitter
- Plumber
- Electrician
- Unskilled Labours

2.7.

Work Force
There will be an average of 10 - 15 personnel executing the work at each Well
Station work locations.

3.

SAFETY AND HEALTH

KAHRAMAA-Well Submersible Pump

Page 7

3.1 Protective and Safety Equipment


Members of the construction team will be issued with the following personal
protective equipment ( PPE):
- Hard Hat
- Safety Glasses
- Gloves
- Safety Shoes
- High Visibility vest
3.2 Information to Personnel
Communication to personnel shall be made through:
-

Safety Induction
Pre-Task Hazard Identification Briefing
Supervisors
Notices and Memos
Method Statement

STARRT talks shall be conducted prior to start of every new activity and for each
new location.
Weekly safety toolbox meeting will be conducted by the assigned supervisors
and/or HSE Officers prior daily work activities. In addition to the basic HSE
instruction the following will be discussed:
3.3 Emergency Procedures

BUILDERS will provide first aid kits on site for light injuries.
In the event of an emergency, all workers will be asked to evacuate and
assemble at the designated assembly area and wait for further instruction from
the supervisors.

4.

QUALITY ASSURANCE
4.1

Contractual Requirements
A full time Quality Control Engineer shall be appointed to ensure that the pump
installation is properly executed, placed, and protected as per the specification
requirements. The QC Engineer shall prepare a quality control program for the
inspection and testing of well submersible pump. The QC Engineer shall have full
authority for postpone, reject or stop installation work.

KAHRAMAA-Well Submersible Pump

Page 8

4.2

Inspection & Testing


Inspection and Test Plan shall be prepared.

4.3

Follow up & Evaluation


The following documents shall be used to assess and evaluate the progress of
the works:
- Material checklist.
The Quality Control Engineer shall prepare and compile all quality data for the
pump.Supervisors shall prepare Daily reports and weekly reports. The
Construction/Site Manager shall evaluate and follow up on the progress of the
work based on the construction schedule.

KAHRAMAA-Well Submersible Pump

Page 9