For
Well Submersible Pump
Client:
KAHRAMAA
Contractor:
Issued by:
Rev.No
Date
Description
Prepared
9-12-12
MV
Checked Approved
AA
AA
Page 1
WELL SUBMERSIBLE
PUMP
TABLE OF CONTENTS
1.0
TITLE
2.0
SCOPE OF WORKS
2.1
General Description
2.2
Plant and Equipment
2.3
Materials
2.4
Site Planning & Preparation
2.5
Work Methodology
3.0
4.0
QUALITY ASSURANCE
4.1
Contractual Impact Requirement
4.2
Inspection & Testing
4.3
Follow up & Evaluation
Page 2
TITLE
SCOPE OF WORK
2.1.
General Description
This method of statement describes the procedures and sequences involved in
the installation of Well Submersible Pump Works. This procedure is to
established and to define the Well Pump Installation
2.2.
2.3.
Qty
Lot
Generator
Tower Lights
Pick-ups
1
1
1
Remarks
As required
As required
Materials
BUILDERS shall submit product data sheet and/or samples of materials as
requested by the Engineer including full details and technical literature with
names, sources and descriptions, for the following:
1. Submersible Pump
2. Pipes
3 Supports
2.4.
Site Preparation
Page 3
2.4.3
2.5.
Work Methodology
2.5.1
Page 4
Install torque arrestor for well casing using rigid PVC or flexible plastic
piped due to the starting torque of the motor will rub against the inside
walls of the well casing.
Install cable guards to protect the submersible cable from abrasion against
side of the well.
Lay the pump 25mm to 50mm from the well, pointing outward(pump
discharge away from the well).
Lay out plastic pipes, safety ropes, hose clamps, bleeder orifice, piping,
assembly package, tape, submersible cable etc.
Assembly of all components that go into the well should be made
horizontally on the ground and then lowered into the well.
Install a pipe adapter in the pump discharge tapping using Teflon tape.
Do not use pipe wrench on any part of the pump except the cast discharge
of the pump.
Be sure that the working surface is smooth to avoid damage to the plastic
pipe and electric cable. Cut off sealed end of the plastic pipe with
hacksaw.
Slide torque arrestor on plastic pipe from pump end. Pull the motor lead
cable through one of the small outside hole of the torque arrestor.
Position two hose clamps over end of plastic pipe. Slide plastic pipe over
the pipe adapter all the way to the shoulder. Position the clamp tightening
screws opposite each other and away from the motor lead wires to prevent
insulation damage. Tighten the hose clamps and tape clamp tab ends to
pipe with plastic tape.
Slide torque arrestor down from the end of the plastic pipe, and clamp
sufficiently to prevent the torque arrestor from sliding up on the pipe while
lowering unit in well.
Splice the electric cable to the pump leads. Heat shrink tubing and Sta-kon
connectors are recommended. It is necessary that the splice be water tight.
Unroll the electric cable along side of the plastic pipe. Be sure not to
damage wire insulation, and that all kinks are straightened out.
Page 5
2.5.3
RESPONSIBILITIES
Page 6
standard practice.
Site Engineer is the responsible person to ensure that the materials use are
as per approved material submittal.
Storekeeper will verify all the documents forwarded are as per the
requirement of purchased order.
Site engineer will inspect the equipment as per the manufacturer
recommendation prior to installation.
Storekeeper will inspect for any damage during shipping, handling and
storage.
Storekeeper will review the documents and verify the items with the
packing list.
Storekeeper is the responsible person for proper storage of the equipment
as per Manufacturers recommendation.
Construction Manager will ensure appropriate measures to avoid any
unexpected events.
2.6.
2.7.
Work Force
There will be an average of 10 - 15 personnel executing the work at each Well
Station work locations.
3.
Page 7
Safety Induction
Pre-Task Hazard Identification Briefing
Supervisors
Notices and Memos
Method Statement
STARRT talks shall be conducted prior to start of every new activity and for each
new location.
Weekly safety toolbox meeting will be conducted by the assigned supervisors
and/or HSE Officers prior daily work activities. In addition to the basic HSE
instruction the following will be discussed:
3.3 Emergency Procedures
BUILDERS will provide first aid kits on site for light injuries.
In the event of an emergency, all workers will be asked to evacuate and
assemble at the designated assembly area and wait for further instruction from
the supervisors.
4.
QUALITY ASSURANCE
4.1
Contractual Requirements
A full time Quality Control Engineer shall be appointed to ensure that the pump
installation is properly executed, placed, and protected as per the specification
requirements. The QC Engineer shall prepare a quality control program for the
inspection and testing of well submersible pump. The QC Engineer shall have full
authority for postpone, reject or stop installation work.
Page 8
4.2
4.3
Page 9