Beruflich Dokumente
Kultur Dokumente
The following table represents the authorities under the Contract that are delegated by the Engineer to the Assistant
Any issue or responsibility which is not specifically listed shall remain the responsibility of the Engineer.
S.No.
FIDIC Clause
3.3 Instructions of the Engineer Design related instructions (no cost or time)
3.3 Instructions of the Engineer Design related instructions (with cost and/or time
impact) PRIOR APPROVAL REQUIRED FROM EMPLOYER
3.3 Instructions of the Engineer Design related instructions (with cost and/or time
impact) PRIOR APPROVAL REQUIRED FROM EMPLOYER
3.3 Instructions of the Engineer construction related instructions (no cost or time)
3.3 Instructions of the Engineer construction related instructions (with cost and/or
time impact) PRIOR APPROVAL REQUIRED FROM EMPLOYER
3.3 Instructions of the Engineer construction related instructions (with cost and/or
time impact) PRIOR APPROVAL REQUIRED FROM EMPLOYER
10
11
12
13
14
15
16
17
18
19
20
21
22
6.5 Working Hours consent to working outside normal working hours. PRIOR
APPROVAL REQUIRED FROM EMPLOYER
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
9.4(b) Failure to Pass Tests on Completion issue Taking Over Certificate PRIOR
APPROVAL REQUIRED FROM EMPLOYER
40
10.0 Employers Taking Over issue Taking Over Certificate. PRIOR APPROVAL
REQUIRED FROM EMPLOYER
41
42
43
44
45
46
47
48
49
13.1 Right to Vary request for proposal. PRIOR APPROVAL REQUIRED FROM
EMPLOYER
50
51
52
53
54
55
56
57
58
14.5 Plant and Materials Intended for the Works determine and certify
59
60
61
62
63
64
65
20.1 Contractors Claims submission of detailed claim for scope change variations
66
67
Project
Director
Design
Managers
Design Manager
Commercial
Manager
Senior Construction
Manager
Deputies
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
PMs
MEP CM &
Lead Designer
Project Engineer
Construction
Supervision
X
X
X
X
X
X
X
Letter
RFI Response
RFIs with Cost and Time Impact
RFI Response
(Field RFI Response)
Engineers Instruction
Letter
Letter
Letter
Letter
Letter
Letter
Letter
Letter
Letter
Letter
Engineers Instruction
Letter
Letter
Letter
Letter
Letter
Letter
Aconex Workflow
Engineers Instruction
Engineers Instruction
Performance Certificate
Letter
Letter
Engineers Instruction
Letter
Engineers Instruction
Letter
Letter
Letter
Engineers Instruction
Engineers Instruction
Letter
Letter
Payment Certificate
Payment Certificate
Engineers Instruction
Letter
Letter
Letter
Letter
Letter
Letter
Letter