Beruflich Dokumente
Kultur Dokumente
The information provided in this report is not official U.S. Government information and does not
represent the views or positions of the U.S. Agency for International Development or the U.S.
Government.
I. Chavchavadze Avenue
II Blind Alley, 4-8, Apartment 6
Tbilisi
May 2011
Content
1
Summary .................................................................................................................................. 4
2 Introduction ............................................................................................................................. 5
2.1 Background ............................................................................................................................... 5
2.2 The Project Development Process ............................................................................................ 5
3 Project Organisation ................................................................................................................ 7
4 Standards and Regulation ......................................................................................................... 7
5 Building State Description ......................................................................................................... 8
5.1 General Conditions.................................................................................................................... 8
5.3 Hot Water Supply System ....................................................................................................... 10
5.4 Lighting System ....................................................................................................................... 11
5.5 Various ................................................................................................................................. 11
6.1. Measured Energy Consumption ............................................................................................ 12
6.2 Calculated and Baseline Energy Consumption .................................................................... 12
7
Environmental Benefits......................................................................................................... 20
Appendix 1 .................................................................................................................................. 20
1 Summary
The baseline for energy consumption of the Khashuri Hospital for its normal functioning is
approximately 469,094 kWh/year for space heating supplied by a local boiler 202,639
kWh/year for hot water supply as well as 84,206 kWh/year electricity for the lighting
system.
The Energy Audit identified a considerable energy efficiency improvement potential for the
hospital:
206202
23802
105336
4.4
kWh/year
GEL/year
GEL
Years
The energy savings potential for the identified energy efficiency and renovation measures is
summarized in the following table, with a ranking of measures and their profitability - Net
Present Value Quotient (NPVQ).
The real interest rate used in these economic calculations is taken as 3.5%. This number
derives from a 15.1% nominal interest rate and the 11.2% official inflation rate.1
For investment and savings assumption effectiveness, all measures should be implemented
within one project. The figures have an accuracy of 10-15%.
Khashuri Hospital
EE Measures
Investment
12,349 m
Net Savings
[GEL]
[kWh/yr]
[GEL/yr]
Payback
NPVQ
[year]
1.
Insulation of walls
35800
80410
8845
4.1
2.51
2.
Insulation of ceiling
14036
38846
4273
3.3
3.32
2500
19309
3244
0.8
2.63
53000
67637
7440
7.1
0.99
3.
4.
Helio-system
Profitable EE Measures
1.
Insulation of walls
35800
80410
8845
4.1
2.51
2.
Insulation of ceiling
14036
38846
4273
3.3
3.32
3.
2500
19309
3244
0.8
2.63
4.
Helio-system
53000
67637
7440
7.1
0.99
105336
206202
23802
4.4
Total
Annual inflation rate was taken as 3.2% according to the ENSI economic program
4
Introduction
2.1 Background
The energy audit of the Khashuri Hospital has been carried out by the Sustainable
Development and Policy (SDAP) Center within the scope of the work of the energy
management component of the NATELI project, led by Winrock International. The results of
the energy audit are included in this report.
The Khashuri Hospital building began operation in 1962 and since then has not been
repaired. The heating system has not functioned since 1990 year.
Currently, redesigning works of the whole building of the hospital are going on. After
reconstruction the building will be provided with a new heating system and with doubleglazed metal-plastic windows.
The goal of the project is to reduce energy costs, improve the indoor environment conditions
and improve building exploitation efficiency.
1. Project Identification
Project
Identification
Scanning
2. Scanning
Improvement
Potential
3. Energy Audit
Simplified
Auditing
Detailed Auditing
with guarantee
4. Business Plan
Business Planning
5. Implementation
Implementation
6. Operation
Operation
3 Project Organisation
Name of Project/Building/Site:
Address:
Contact Person:
Phone:
Building Owner:
The work is carried out by:
Contact Person for the Energy
Audit:
Address:
Phone:
Fax:
Role in the Project:
Expert:
Phone:
Role in the Project:
Consultant:
Phone:
Role in the Project:
Consultant:
Phone:
Role in the Project:
Khashuri Hospital
Rustaveli St
Archil Akhalkatsi
897 00 19 10 (mobile)
Sustainable Development and Policy (SDAP) Center
Karina Melikidze
#34 Al. Kazbegi Ave. Plot # 3, Office 104, Tbilisi
(99532) 20 67 73
(99532) 42 00 60
Director of the SDAP Center
Karina Melikidze
893 14 62 54
In charge of conducting energy audit by the Key Number
software program and writing report
N. Kevkhishvili GTU Professor
Energy Auditor, in charge of site inspection and carrying
out energy audit
P. Gagnidze Energy Audit Expert
851 340 477
Energy audit team member, in charge of site inspection and
carrying out energy audit
Khashuri Hospital
Year of Construction
1962
In regular operation
Working days
Saturday
Sunday
Maintenance
24
24
24
Heating Schedule
24
24
24
(hours/
day)
(hours/
day)
30
persons
Number of Beds
31
unit
3845
12423
1103
m
m
m
External Walls
General evaluation of the condition of the
medium thermal capacity
walls
U
value
Total area of external
1392
m
(averag
walls
e)
N
E
S
Orientation
914
914
3
1.22
m
m
W/mK
Total
Coefficient of the thermal conductivity for walls: concrete is =0.8 w/m*K,
thickness = 0.51 m, exterior cement sandy plaster - =0.02 m,
=0.93w/m*K and from the inside an insulation layer with a thickness
=0.05 m, =0.055 w/m*K is proposed.
Material Type
Required thermal resistance value in case of insulation was calculated as:
m1
R0=1/8.7+0.51/0.8+0.02/0.93+0.05/0.05+0.01/0.8+1/23 =1.83 m2* K/W
Heat transfer value: U= 1/1.83=0.54 W/m2 K
Windows
General evaluation of the condition of windows
268
Type
2
2G
2G
NE
Total
Material 1
Type 2
Material1
2G
2G
Size A x B
Area
Q-ty
m2
1.42x1.2
1.42x1.89
2.02x1.89
2.02x1.2
1.2x0.8
1.704
5.3676
80.173
8
36.36
9.6
1
2
21
15
10
1.42 x1.2
1.42 x1.89
1.704
10.73.
52
1
4
42x1.2
1.42x1.89
2.02.42x1.8
9
15.336
75.146
4
7.6356
9
28
2
1.42x1.2
1.42x1.89
2.44x2.02
2.02x1.89
1.704
10.735
2
4.9288
7.6356
268.8
1
4
1
2
Joints
U value
W/m2K
0.62
0.62
0,62
0.62
101
Doors
General evaluation of the condition of doors Metal plastic
Type of doors
No. of doors
Roof
General evaluation of the condition of the roof
914
Total Roof Area
Roof type
Roof with garret
Total
Material Type m1
Insulation Type i1
Material
type
Insulation type
m1
Glass wool
26
U-value
(average)
2.91
10 mm plywood
The heat transfer U value (average) is evaluated as 1.2 W/m2 K. Based on information about
the roof material as well as the results of the site inspection.
Floor (with heat losses to outdoor air, through ground or unheated cold, basement)
General evaluation of the condition of the
Not Acceptable
floor
1103
U value
1.1
Total Floor Area
m
W/mK
(average)
Type of Floor
Under the floor is a basement
Floor
Construction
Concrete covered with laminated plastic and ceramic floor tiles
Materials
5.2 Heating System
The heating system of the Khashuri Hospital hasnt functioned since 1990. Currently,
renovation works are taking place for a whole building reconstruction and afterwards it is
planned to equip the building with a new heating system.
10
Installed
Capacity
kW
16
Average
Power
W/m2
4.2
16
4.2
Type of Control/Comments
Lighting
Average Power Demand
5.0
W/m2
Operation Period
70
h/week
Operation Period
52
weeks/year
8.8
W/m
5.5
Various
Quantity
Various Exploitable
pcs
Computers
X-ray Machine
Ultra Sound Machine
Centrifugal Machine
Urine Testing Machine
Blood Testing Equipment
Other Medical Equipment
1
1
1
1
1
Installed
Capacity
kW
0.2
63
0.25
0.15
6.5
Average
Power
W/m2
0.3
4
0.1
0.1
0.1
0.2
50
120
1.0
2.5
8.1
Total
Comments
Various Exploitable
Average Power Demand
4.0
W/m2
Operation Period
70
h/week
Operation Period
52
weeks/year
5.0
W/m
11
Energy Consumption
Unit
Comment
kj/m3
The baseline energy consumption of the Khashuri Hospital necessary to ensure normal
operating conditions is 469094 kWh/year for space heating, 202639 kWh/year for hot water
supply and 84206 kWh/year for electricity lighting system purposes.
The building is characterized as one with a medium thermal capacity.
The decision to undertake an energy audit was made because a building renovation is
currently being carried out, thus the aim of this energy audit is to estimate the energy
consumption and ENCON potential in the building and to develop further recommendations.
Energy Budget
The calculated and measured energy consumption before and after the implementation of
the energy efficiency and renovation measures is summarized in the following Energy
Budget Table.
12
Heating
Ventilation
DHW
Pumps
Lighting
Various
Cooling
Total
Budget Item
Heating
Ventilation
DHW
Before EE
Calculated
Before EE
Measured
Before EE
Baseline
After EE and
Renovation
[kWh/myear]
[kWh/myear]
[kWh/myear]
[kWh/myear]
122.0
122.0
122.0
0
0
0
52.7
52.7
52.7
10.8
10.8
10.8
21.9
21.9
21.9
14.7
14.7
14.7
0
0
0
222.1
222.1
222.1
ENERGY BUDGET - ENERGY AUDIT
81.1
0
52.7
10.8
9.1
14.7
0
168.4
Before EE
Calculated
Before EE
Measured
Before EE
Baseline
After EE and
Renovation
[kWh/year]
469094
0
202639
[kWh/year]
469094
0
202639
[kWh/year]
469094
0
202639
[kWh/year]
312012
0
202639
41353
41353
41353
41353
Pumps
84206
84206
84206
35086
Lighting
56538
56538
56538
56538
Various
0
0
0
0
Cooling
853830
853830
853830
647628
Total
Figure 1. Annual energy consumption calculated by the ENSI Key Numbers Software
Program
13
206202
kWh/year
GEL/year
GEL
years
23802
105336
4.4
The energy savings potential for the identification of energy efficiency and renovation
measures is summarized in the following table:
Khashuri Hospital
EE Measures
Investment
3845 m
Net Savings
Payback NPVQ
[GEL]
[kWh/yr]
[GEL/yr]
[year]
1. Insulation of walls
35800
80410
8845
4.1
2.51
2. Insulation of ceiling
14036
38846
4273
3.3
3.32
2500
19309
3244
0.8
2.63
4. Helios System
53000
67637
7440
7.1
0.99
1. Insulation of walls
35800
80410
8845
4.1
2.51
2. Insulation of ceiling
14036
38846
4273
3.3
3.32
2500
19309
3244
0.8
2.63
4. Helios System
53000
67637
7440
7.1
0.99
105336
Total
* Based on a 10.47% real interest rate
206202
23802
4.4
Profitable EE Measures
It is important to pay attention to the first set of measures shown in the upper part of the
14
table and summarized as EE Measures. There are some measures that may be
comparatively expensive, but are still justified taking into account the functions that a
hospital performs.
The reduction of CO2 emissions achieved by implementing all measures identified through
the energy audit is estimated as 51.41 tons/year. These numbers result from the last table
(see the section on environmental benefits). The savings divided by the energy carrier are
multiplied by the CO2 emission coefficients. Then they are summarized and multiplied by the
total building area (3845 m2).
12.8 x 0.399=5.107 (kg/m2a)
40.9 x 0.202= 8.26 (kg/m2a)
5.107 +8.26=13.37 (kg/m2a)
13.37 x 3845=51.41 (t/a)
2.
3.
4.
8.2 Measures
A description of all measures that have been evaluated is given below.
Measure
Current Situation
1.
The walls of the hospital building are constructed from bricks with a thickness of 0.51 m.
Description of Measure
In order to reduce heat loses it is recommended to insulate the inner surface of the walls with
insulation materials - 0.05m glass wool or basalt fiber and an external surface covered by a protective
material.
Calculation of Savings (by the ENSI Key Number Software or other tool)
The above measure requires the insulation of 1392 m2 of walls.
- Waterproofing Primary paint, an investment of 6 GEL/m2 x1392 = 8352 GEL
- Thermal Insulation, an investment of 2.70 GEL/m2 x 1392 = 3759 GEL
- Plastic net, an investment of 1 GEL/m2 x 1392 = 1392 GEL
15
35800
GEL
GEL/year
8845
GEL/year
20
Years
16
Measure.
Current Situation
A roof with garret is located directly above the heated space. The U-value (average) has been
calculated as 1.2 Wm2/K, based on the results of the site inspection and information about the roof
construction materials.
Description of Measure
After renovation it is planned to cover the roof with a 5 cm filling of basalt or glass wool insulation or
protective wood material. With this measure the U-value reduces to 0.7 Wm2/K
Calculation of Savings (by the ENSI Key Number Software or other tool)
The above measure calls for the insulation of the ceiling area: 914 m2.
- Gypsum board, an investment of 12 GEL/m2 x 914 = 10968 GEL
- Thermal insulation, an investment of 2.7 GEL/m2x 914 = 2468 GEL
Total Investment Constitutes 13436 GEL
The amount of saved energy calculated by the software program was defined as 38,846 kWh/y. In
monetary terms this will constitute: 38846 x 0.11 = 4273 GEL
Investment:
Design/Planning
300 GEL
Project Management
300 GEL
Insulation of the Roof
13436 GEL
GEL
As-built Documentation
Total Investment
14036
GEL
GEL/year
Net Savings
4273
GEL/year
Economic Lifetime
20
Years
17
Measure.
Current Situation
3.
200
300
2000
2500
GEL
GEL
GEL
GEL
GEL
GEL
GEL
GEL/year
3244
GEL/year
Years
18
Measure.
Current Situation
It is planned to install modern hot water supply system working on natural gas with 86% efficiency.
Description of Measure
Besides the above-mentioned measures the energy audit team has decided to substitute the current
system with Helio-systems. The saved thermal energy will constitute 2100 kWh/y.
Calculation of Savings (by the ENSI Key Number Software or other tool)
The mentioned measure demands the installation of 32 solar vacuum type collectors.
- Vacuum type collector, an investment of 32 x 1400 GEL/piece = 44800
- Pump, an investment of 200 GEL
- Accumulation tank 2000 GEL
- Installation, an investment of 5000 GEL
Total investment constitutes: 52000
The amount of saved energy calculated by the software program was defined as 67,637 kWh/y. In
monetary terms this will constitute: 67637 x 0.11= 7440 GEL
Investment:
Design/Planning
Project Management
Installing the Helios System
Control and Testing
As-built Documentation
Other Expenses
Total Investment
500
500
52000
53000
GEL
GEL
GEL
GEL
GEL
GEL
GEL
GEL/year
7440
GEL/year
20
years
19
9 Environmental Benefits
The calculated savings in delivered energy and related reductions in CO2 emissions for the
area F = 12349 m2 are identified as follows:
21.9
122.0
After EE and
(kWh/ma)
9.1
81.1.
Savings (kWh/ma)
12.8
40.9
Savings (kWh/a)
49120
157082
0,3999
0.202
5.107
13.37
51.41
Renovation
Measures
Other
Oil
Gas
Central
Heating
Electricity
Energy Carrier
The reduction of CO2 emissions achieved by implementing all the energy efficiency
measures identified through the energy audit is estimated as 51.41 tons/year
12.8 x 0.399 =5.107 (kg/m2a)
40.9 x 0.202 = 8.26 (kg/m2a)
5.107 + 8.26 =13.37 (kg/m2a)
13.37 x 3845 = 51.41 (t/a)
20
Appendix 1
Photos from the Khashuri Hospital
21