Beruflich Dokumente
Kultur Dokumente
CHAPTER 10
PROJECT PLANNING
10.1 Introduction
A project is something, which has start date and finish date with some task to
be performed with allotted resources and with financial implications.
Guidelines and suggestions are given here which outline the organization and
execution of an engineering project as it relates to instrumentation, ft lists
documents which are necessary for communication between owner and builder,
communication within the contractor organization during the engineering phase
and the necessary information for construction. Coordination requirements with
other groups are discussed, planning hints are given, and a checklist for project
control is suggested to ensure the successful completion of the project. The
principles outlined apply to projects whose capital investments range from a few
hundred thousand dollars to the largest of projects.
The viewpoint presented is most applicable to the person responsible for the
application, selection, purchasing and installation of instruments arid control
systems. The documentation necessary for a complete record of a project is
outlined. Even though the viewpoint is slanted toward the responsible project
instrument engineer, other owner and contractor personnel project managers,
process people and leaders of other disciplineswill profit by an understanding
of how the job is organized, developed and executed.
Many jobs appear complex until they are organized and broken down into
components or units easily understood and accomplished. This is certainly true
of instrument work.
Specific documents are required for the workfor installation and later for
maintenance Scheduling, purchasing, installation and calibration must be done.
The following paragraphs discuss what these functions are and how they are
carried out.
Piping
Piping
Piping
The factors are so interrelated that they need not be listed in a definite order
of importance. Fabrication cost is always important, but other factors such as
installation schedule, startup time, etc., can minimize initial fabrication cost.
Timing and cost, then, must be considered together.
If the timing or schedule is critical, panel fabrication may be started before
engineering is complete with a gain of several weeks in panel delivery. The
added cost of such an action may be small compared to the advantage of earlier
on-stream commitments or other factors.
Capability and availability of manpower are also closely related. In most
cases the buyer knows the panel fabricator well enough to judge his engineering
capabilities. The buyer also knows his own department's workload and
capabilities. From these factors, he then must determine the amount of
engineering to be done by each. In some cases the panel fabricator will do little
or none of it; in other cases, he may do all of it.
Having decided which route to take, the engineer must schedule the work
accordingly. If the detailed engineering is left to the panel fabricator, the contract
must be let at an earlier date to allow time for engineering by the fabricator. The
quality of the written panel specifications must be better for this option than for
one on which detailed engineering is complete, because the written
specifications must convey in word description what detailed drawings normal.
Show pictorially.
Piping
Piping
should
include
the
following
information
in
some
This list is not intended to be complete, but it indicates the necessity for job
organization to assure quick and efficient flow of information. It assures orderly
progress and prevents costly mistakes due to lack of information. Primarily, it
saves the valuable time of many people. It includes the flow lines of
communication among the contractor, owner, vendors and subcontractors, as
well as within the contracting organization.
Piping
One good approach in scheduling a job is to work from the completion date
backwards to determine logical dates for the completion of various stages of the
job. Allow plenty of time for custom fabricated items, delivery of equipment after
shipment and communication delays that normally affect a job.
After the instrument schedule is temporarily worked out, review the items
again, checking with equipment vendors to verify their probable delivery
commitments.
Piping
Piping
10
Piping
11
Piping
12