Beruflich Dokumente
Kultur Dokumente
Tender Document
For
Fabrication of 19 x 123m span triangulated steel bridge girders for
new rail-cum-road bridge over river Ganga at Patna by setting up
of field workshop on the Pahlejaghat end (North end) of river
Ganga including leading of the structural steel from Fatua
stockyard, shop painting and trial assembly of one span of 123m
in the shop as a complete job. IRCON will supply structural steel
free of cost while the other materials shall have to be arranged by
the contractor at his own cost.
Package: II
Tender No. IRCON/CC/TN/GANGA BRIDGE-BIHAR/08/459
PACKET-I
TECHNICAL BID
AUGUST 2008
IRCON INTERNATIONAL LIMITED
(A Govt. of India Undertaking)
C-4, DISTRICT CENTRE, SAKET,
NEW DELHI-110017
PHONE:+91-11-29565666; FAX:+91-11-26522000,26854000
PACKAGE - 2
1. NAME OF THE WORK
2. TENDER ISSUED TO
_________________
_______________
3. S.No.
OF THE TENDER
: __________
ISSUED
4. OFFICER
ISSUING
THE
TENDER DOCUMENTS
Signature
Name
Designation
Date
TENDER DOCUMENTS
CONTENTS
S.
No.
1
2
3
4
5
6
7
8
9
SECTION
Section 1
Section 2
Section 3
Section 4
Section 5
Section 6
Section 7
Section 8
Section 9
DESCRIPTION
PAGES
FROM
TO
28
29
30
31
42
43
57
58
107
108
183
SECTION - 1
Date : 22.08.2008
2.0
Package
No.
Name of Work
Estimated
Cost
of Work
(Rs. in
Crores)
II
135.89
Earnest
Money
(Rs. in
Lacs)
Completion
Period
25.00
40 Months
ELIGIBILITY CRITERIA
Eligibility of the tenderers shall be assessed based on the Essential Qualifying
Criteria and Other Qualifying Criteria as given in Annexure-I.
3.0 Tender documents can be obtained from 10.30 hours to 16.00 hours on any
working days from 26.08.2008 to 12.09.2008 from the office of General
Manager (Bridges & Contracts), IRCON INTERNATIONAL LIMITED, C-4,
District Centre, Saket, New Delhi 110017 and from the office of General
Manager, IRCON INTERNATIONAL LIMITED, 1st Floor, Sone Bhawan, D. P.
1
5.0
The tender documents shall be submitted in two separate sealed packets viz.
Packet-I containing Technical Bid and Packet-II containing Financial Bid.
Detailed credentials as per the requirement of eligibility criteria and all tender
papers except Bill of Quantities are to be submitted in Technical Bid. Bill of
Quantities with rates duly filled in are to be submitted in Financial Bid.
6.0
It is a key date based works and penalty clause is there for missing the key
dates.
7.0
Completed tender documents in two packets viz. Packet-I and Packet-II shall
be sealed separately in envelopes superscribing as Packet-I (Technical Bid)
and Packet-II (Financial Bid) along with the name of the work. These two
sealed envelopes and the envelop (superscribing Earnest Money for the
work containing the Earnest Money) in the form as prescribed in the tender
documents shall further be sealed in a larger envelope super- scribing the
name of the work as stated above (alongwith date and time of opening of
tenders) and addressed to General Manager (Bridges & Contracts), IRCON
INTERNATIONAL LIMITED, C-4, District Centre, Saket, New Delhi-110017
and should be deposited in the tender box at IRCONs office, C-4, District
Centre, Saket, New Delhi-110017, before 15.00 hours of 15.09.2008. Tenders
shall be opened (Technical Bids only) at 15:30 hours on the same day in the
presence of the tenderers or their authorised representatives intending to
attend the opening. The Financial Bids shall be opened only after assessing
suitability as per the technical bids by IRCON. The technically qualified
agencies shall be informed to attend the opening of financial bids.Tenders
2
duly sealed in the prescribed manner above can also be sent through
Registered Post/Speed Post/Courier so as to reach in this office(General
Manager/Bridges & Contract, IRCON INTERNATIONAL LIMITED, C-4, District
Centre, Saket, New Delhi-110017) not later than the time and date of opening
of tenders. Any tender received later than the time and date of opening of
tenders shall be rejected and returned tothe tenderer unopened.
8.0
9.0
Any tender received without Earnest Money in the form as specified in tender
documents shall not be considered and shall be summarily rejected.
10.0
11.0
Tenderers may note that they are liable to be disqualified at any time during
tendering process in case any of the information furnished by them is not
found to be true. EMD of such tenderer shall be forfeited. The decision of
IRCON in this regard shall be final and binding.
12.0
The validity of the offer shall be 90 days after the date of opening
Bid) of the tender.
13.0
14.0
(Technical
ANNEXURE I
A. ESSENTIAL QUALIFYING CRITERIA
3
1. The tenderer should possess adequate experience and capacity to carry out the
fabrication of triangulated railway bridge girders and to show this he/they should
fulfill the following criteria:
i.
The average annual financial turnover during the last three years should be at
least 20% of the estimated cost.
Notes:
The financial turnover shall be judged from ITCC or audited Annual Reports
including Profit and Loss Account.
3.
The Contractor should have positive networth. This will be judged from the
audited Balance Sheet of the last financial year ending on a date not prior to
18 months from the date of submission of the tender.
4.
5.
SN
Description
Maximum
Marks
10
3
4
35
10
10
10
100
The contractors should pass in all items of Essential Qualifying Criteria and should
obtain minimum 60 marks out of the 100 of Other Qualifying Criteria to get short
listed/technical qualification.
Tenderer(s) may please note that their offers will be evaluated as per the
credentials/documents attached by the tenderer(s) along with the tender.
Tenderers shall furnish the requisite information in the formats enclosed
alongwith.
SECTION - 2
FORM
OF
BID
FORM OF BID
To
The General Manager (Bridges & Contracts)
IRCON International Limited, C-4, District Centre,
Saket, New Delhi 110017.
Dear Sir,
I/We, ____________________________ (Name and address of the tenderer)
have read the various terms and conditions of the tender documents attached
here with duly signed by me/us and agree to abide by the same. I/We also
agree to keep this tender open for acceptance for a period of 90 days from the
date fixed for opening the same and on default thereof our Earnest Money is
liable to be forfeited.
I/We hereby declare that we have visited the site of the work and have made
ourselves fully conversant of the conditions therein and including the
topography of area, soil strata at site of work, sources and availability of
construction materials, rates of construction materials, water, electricity, all
local taxes, royalties, octrois etc., availability of local labour (both skilled and
unskilled), relevant labour rates and labour laws, the existing road and
approaches to the site of work, requirements for further service roads /
approaches to be constructed by me / us,the availability and rates of private
land etc. that may be required by me / us for various purposes, climatic
conditions, law and order situation and availability of working days.
I/We have quoted our rates for various items in the Bill of Quantities taking
into account all the above factors and We offer to do the work
_____________________________________________ (Name of the
work) at the rates quoted in the attached Bill of Quantities and hereby bind
ourselves to complete the work in all respects within time schedule depicted in
tender documents from the date of issue of letter of acceptance of tender.
A sum of Rs.____________ (Rupees _________________)(amount of
Earnest money deposit) is herewith forwarded as Earnest Money. I/We
understand that the full value of the Earnest Money shall stand forfeited
without prejudice to any other rights and remedies available to IRCON
International Limited in case our tender is accepted and if:i) I/We do not execute the Contract Agreement within time period specified in
the tender documents.
ii) I/We do not commence the work as soon as is reasonably possible after
the receipt of the Letter of Acceptance or elsewhere stated in the Contract
documents.
7
SECTION - 3
INSTRUCTIONS TO TENDERES
INSTRUCTIONS TO TENDERERS
A
1
General
Ircon International Limited (A Govt. of India Undertaking) under the
Ministry of Railways having ISO 9001: 2000 have been awarded the
work of fabrication and erection of steel girders for Rail cum Road
bridge across river Ganga at Patna in Bihar by Ministry of Railways.
Here, tender is invited for fabrication of steel girders including painting.
Erection work will be taken up subsequently.
1.1
1.2
c.
d.
e.
f.
1.3
c) Contractor :
d) Consultant :
1.4
1.6
1.7
1.8
Cost of Bidding
2.1
The bidder shall bear all costs associated with the preparation and
submission of the bid and the Employer will in no case be
responsible or liable for these costs regardless of the conduct or the
outcome of the bidding process.
ii.
3.1
4.0
4.1
The bidder must obtain for itself on its own responsibility and its own
cost all the information including risks, contingencies & other
circumstances in execution of the work. It shall also carefully read
and understand all its obligations & liabilities given in tender
documents.
4.2
The bidder is advised to visit and examine the site where the work is
to be executed and its surroundings or other areas as deemed fit by
the bidder and obtain for itself on its own responsibility all information
that may be necessary for preparing the bid and execution of the
contract. The cost of visiting the site and collecting relevant data shall
be at the bidders own expenses. It is a condition of the tender that
the tenderer is deemed to have visited the site and satisfied himself
with all the conditions prevailing including any difficulties for
executing the work.
4.3
4.4
C.
5.0
Language of Bid
5.1
The bid prepared by the bidder and all documents related to the bid
shall be written in English.
6.0
6.1
6.2
6.3
The tenderer must fill and submit the prices as per instructions given
in Bill of Quantities. He shall not make any addition or alteration in
the tender documents. The requisite details should be filled in by
the tenderer wherever required in the documents. Incomplete tender
or tender not submitted as per instructions is liable to be rejected. If
a tenderer does not quote a price/rate for any BOQ item, his tender
shall be summarily rejected.
7.0
Deviations
7.1
The tenderer should clearly read and understand all the terms and
conditions, specifications, drawings, etc. mentioned in the original
tender documents. If the tenderer has any observations, the same
may be indicated in his forwarding letter along with the tender.
Tenderers are advised not to make any corrections, additions or
alterations in the original tender documents. If tenderer makes any
correction in his own entries the same shall be initialed and stamped
by him. If this condition is not complied with, tender is liable to be
rejected.
8.0
9.0
Earnest Money
12
9.1
b)
9.2.1
9.2.2
ii)
iii)
9.2.3
9.3
9.3.1
9.3.2
of retention money from the bills shall commence after adjusting this
EMD amount.
b)If the Earnest Money Deposit (EMD) is in the form of Demand
Draft/Pay Order, the same shall be retained towards retention money
and further deduction of retention money from the bills shall
commence after adjusting this EMD amount.
10.0
10.1
The tender shall remain valid for the period indicated in Appendix to
Tender after the date of the opening of the tender. If the Tenderer
gives validity period less than that fixed/prescribed by Employer, the
tender shall be liable to be rejected.
10.2
D.
Submission of Bids
11.0
11.1
11.2
11.3
11.4
Any tender received after opening of the tender shall be rejected and
returned unopened to the tenderer.
12.0
Withdrawal of tender
No tender can be withdrawn after submission and during tender
validity period.
13.0
14.0
14
14.1
14.2
The tenders shall be submitted on or before the due date and time
with all the relevant documents as mentioned in Para 3.1 and the
following:
a)
b)
c)
d)
E.
15.0
15.1
15.2
15.3
16.0
16.1
17.0
17.1
The Employer shall examine the bids to determine whether they are
complete, whether any computational errors have been made, whether
the documents have been properly signed and whether the bids are
generally in order.
15
17.2
17.3
ii)
iii)
17.4
17.5
18.0
18.1
18.2
offer is liable to be rejected and the original offer shall remain valid
and binding on him.
18.3
19.0
Canvassing
19.1
20.0
21
22.0
Award of Contract
22.1
22.2
23.0
17
ANNEXURE I
A. ESSENTIAL QUALIFYING CRITERIA
1. The tenderer should possess adequate experience and capacity to carry out
the fabrication of triangulated railway bridge girders and to show this he/they
should fulfill the following criteria:
i.
ii.
Iii.
The tenderer should fullfill all the three above mentioned criteria.
For assessing the monthly fabrication capacity, the tenderer shall submit the
inspection certificates of the inspecting agencies like RDSO, RITES or any other
independent agency, as the case may be, showing the tonnage of the inspected
and passed fabricated materials / components. Monthly production of 250 MT or
more in any two consecutive months in the past seven years will be taken as the
satisfying criterion for the purpose of fabrication capacity.
2.
The average annual financial turnover during the last three years should
be at least 20% of the estimated cost.
Notes:
The financial turnover shall be judged from ITCC or audited Annual Reports
including Profit and Loss Account.
3.
The Contractor should have positive networth. This will be judged from the
audited Balance Sheet of the last financial year ending on a date not prior
to 18 months from the date of submission of the tender.
18
4.
5.
Description
Registration of Company, Partnership Deed, Article of
Association, Registration under Labour Law,
registration under Sales Tax Act.
Maximum
Marks
10
3
4
35
10
10
10
100
The contractors should pass in all items of Essential Qualifying Criteria and
should obtain minimum 60 marks out of the 100 of Other Qualifying Criteria to
get short listed/technical qualification.
Tenderer(s) may please note that their offers will be evaluated as per the
credentials/documents attached by the tenderer(s) along with the tender.
Tenderers shall furnish the requisite information in the formats enclosed
alongwith.
19
ANNEXURE II
2.
Annual Turnover for the last three years with supporting documents.
3.
Registration of Company.
4.
5.
6.
7.A
7.B
8.A
8.B
8C.
9.
10.
11.
Bankers certificate.
12. Net worth statement for the last financial year ending on a date not prior
to 18 months from the due date of submission of the tender duly
supported by Audited Balance Sheet.
13.
14.
20
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
21
Date of
Value of Reasons Penalty , Any other
actual
completed
for
if any,
relevant
completion
work (In delays, if imposed information
lacs of Rs)
any
for delay
Note :
1 Please attach copies of the certificates issued by the Client.
2 Only those works shall be considered for evaluation for which copies of the certificates issued by the client are attached.
3 In case of Joint venture/ consortium/Consortium, the information is to be furnished by both the partners.
22
Remarks
S.
No.
YEAR
Remarks
1
2
3
Note :
1 Please attach certified/attested copies of the latest ITCC and/or Profit and Loss Account statement to support the information
furnished.
2 In case of joint venture/ consortium, the information is to be furnished by both the partners.
23
DETAILS OF SKILLED AND TRAINED MANPOWER INCLUDING ENGINEERS AND TECHNICAL STAFF PRESENTLY EMPLOYED
S.
No.
Name
Qualification
Designation
Total Experience
(in years)
Remarks
1
2
3
Note : In case of joint venture/ consortium, the information is to be furnished by both the partners.
PROGRAMME FOR DEPLOYMENT OF MAN POWER ALONGWITH COMPLETE ORGANISATION CHART AND BIO-DATA OF KEY
PERSONNELS.
S.
No.
Name
Qualification
Designation
1
2
3
24
Total Experience
(in years)
S.
No.
DETAILS OF TOOLS, PLANT AND MACHINERY (IN WORKING CONDITIONS) OWNED BY THE TENDERER
Description
Make
Model & Year
Capacity
Condition
Nos.
Any other
Remarks
of
available
relevant
manufacture
information
1
2
3
4
Note : In case of joint venture/ consortium, the information is to be furnished by both the partners.
S.
No.
1
2
3
4
25
DETAILS OF TESTING, MEASURING AND INSPECTION EQUIPMENT AND FACILITIES FOR CALIBERATION OWNED
S.
No.
Description
Make
Capacity (if
any)
Condition
Nos.
available
1
2
3
4
5
6
7
8
9
Note :
1.In case of joint venture/ consortium, the information is to be furnished by both the partners.
26
Any other
relevant
information
Remarks
S.
No.
Description
Make
Capacity (if
any)
Condition
Nos.
available
1
2
3
4
5
6
7
8
9
Note :
1. In case of joint venture/ consortium, the information is to be furnished by both the partners.
27
Any other
relevant
information
Remarks
Any other
relevant
information
Remarks
SECTION - 4
APPENDIX TO TENDER
29
FABRICATION OF STEEL GIRDERS FOR RAIL CUM ROAD BRIDGE ACROSS RIVER GANGA AT PATNA
APPENDIX TO TENDER
APPENDIX TO TENDER
DESCRIPTION
Reference Clause
Name of Work:
Fabrication of 19 x 123m span triangulated steel
bridge girders for new rail-cum-road bridge over
river Ganga at Patna by setting up of field
workshop on the Pahlejaaghat end (North end)
of river Ganga including leading of the structural
steel from Fatuha stockyard, shop painting and
trial assembly of one span of 123m in the shop
as a complete job. IRCON will supply structural
steel free of cost while the other materials shall
have to be arranged by the contractor at his own
cost.
1.1 of
Instructions to Tenderers
Place of Registration of
Joint venture/ consortium
applicable):
1.2 of
Instructions to Tenderers
Agreement (if
Anywhere in India.
Client:
East Central Railway under Ministry of Railways,
Government of India.
1.3(a) of
Instructions to Tenderers
Employer:
IRCON INTERNATIONAL LIMITED
C-4, District Centre,
Saket, New Delhi-110 017.
1.3(b) of
Instructions
to Tenderers
Scope of Work:
Fabrication including Shop painting of 19 Nos. of
123 m span span steel girders for rail cum road
bridge across river Ganga at Patna in Bihar. For
fabrication workshop has to be set up at the work
site by the contractor. Work includes trial
assembly of one span.
1.5 of
Instructions
to Tenderers
1.6 of
Instructions to Tenderers
9.1 of
Instructions
to Tenderers
10.1 of
Instructions to Tenderers
Period of Completion:
40 Months including monsoon and flood period.
1.0 of
Notice Inviting Tender
10.0 of
Special Conditions of Contracts
30
32
SECTION - 5
31
31
IRCON will release 10% of original contract value towards mobilisation advance in
following stages:
2.2 Stages of Payment:
Stage - I -
Stage - II -
SUPPLY OF MATERIALS
3.1 CONTRACTORS MATERIALS
(a)
(b)
If called upon, the Tenderer(s) shall state the actual source of supply of
material(s) to be supplied by him and shall submit test certificate &
samples for prior approval.
(c)
During the execution of work, all materials brought to site by the contractor
must be offered for inspection and passed by the engineer or his
representative before being used in the work and such approval shall be
recorded in a register maintained for that purpose. only passed material
shall be used by the contractor.
33
3
(d)
If the contractor fails to return excess material issued to him, the cost of such excess
materials shall be recovered at last purchase rate or current market rate plus 12.5 % for
supervision charges and 2% towards incidental charges on the quantity not returned.
3.3 PAINTS
(A)
(B)
These materials shall be brought in sealed drums and each drum shall be
opened in the presence of the Engineer-at-site before use.
(C)
3.4 Electrodes:
All Electrodes shall be kept under dry conditions. Any electrode with parts of its flux
coating broken away or otherwise damaged shall be rejected. Any electrode older than
six months from the date of manufacture or older than the date of expiry as specified by
manufacturer should not be used. Welding Electrodes to be used in the work should
conform to RDSO approved firm and quality only.
The Electrodes to be used should be No.8 SWG or 10 SWG of class B-1 & B-2 of mild
steel for arc welding or those approved by RDSO.
The Electrodes to be used in the work shall be of any of the following firms of repute :
I.M/s Advani Oerlikon Ltd., Mumbai.
II.M/s. Diffusion Engineering Ltd., Nagpur.
III.M/s. Valency Compound Service, Ahemed Nagar.
IV.M/s. Modi Arc Electrodes, Modi Nagar.
V.M/s. D&H Secheron , Indore.
VI.M/s. EWAC Alloys Ltd., Mumbai.
VII.M/s. Weld Craft Pvt., Ltd., Tunkur Road.
3.5 Rivets:
Since the components of the steel girders are comprising of mild steel as well as high
tensile steel both, rivets of only high tensile bar conforming to the relevant IS Code shall
be used.
4.0 Transportation of structural steel
35
3
Contractor shall transport the structural steel supplied free of cost by the IRCON at his
own cost. Transportation shall include loading, leading, unloading, stacking etc.
Contractor should quote his rate accordingly.
Security of materials including the fabricated material arrived at site shall be the
responsibility of the contractor till completion of the work to the satisfaction of the
Engineer. Contractor shall submit an indemnity bond for safe transportation and
custody of raw structural steel supplied by IRCON as well as of the fabricated materials
till completion of the work.
Pro-forma of indemnity bond is available at Annexure II of SECTION-5.
5.0
Contractor shall make his own arrangements at his cost for all Plant and Machinery
required for execution, completion and maintenance of all items of work included in his
scope of work to the complete satisfaction of the Engineer.
Any repair, maintenance, POL, manpower required in operation of such plants &
machineries shall also be the liability of the contractor at his own cost.
6.0 LABORATORY
6.1
This list is indicative only and not exhaustive. If required by the engineer, other
equipments shall be procured by the contractor at his own cost.
6.2
TESTING CHARGES
No payment shall be made to the Contractor for setting up laboratory or getting any tests
in-house (in the workshop premises) or from the outside laboratory approved by the
36
3
Engineer. Contractor shall quote their rate accordingly keeping in view that no any extra
payment shall be made over and above the rate quoted by the Contractor.
7.0
7.1 The Contractor shall get registered with the concerned Sales tax/VAT Department of
the relevant state(s) of the project and submit a copy of the same to the
Employer/Engineer. He shall be responsible for filing sales tax/VAT returns and
assessments, as necessary as per prevalent Laws, Rules and Regulations and
shall also furnish necessary certificates to Employer/Engineer from time to time.
The rate quoted by the bidder shall be full and final including all taxes. Additional
taxes / duties if levied any by statutory body shall be compensated as below:
7.1.1 Excise Duty :
Excise Duty shall be reimbursed as per actual on production of the proof, if
levied. However, to claim excise duty the contractor has to raise the excise
invoice.
7.1.2 Value Added Tax : The contractor has to pay Value added Tax on his purchase
(consumables like electrodes, paint, POL, spares, etc.) and VAT on free supply of
materials will be paid by IRCON.
7.1.3 Works Contract Tax : Fabrication job does not attract works contract tax.
However for transfer of goods any tax liability arises then contractor has to bear the tax
and nothing will be paid extra.
7.1.4 Entry Tax : Entry Tax is applicable and it should be included in rates. For free
supply of material, IRCON will be responsible for Entry Tax.
7.1.5 Construction Worker's Welfare Cess : A Cess of 1% of value of work will be
deducted from the bill.
7.1.6 Service Tax : Not applicable.
8.0 PRICE ADJUSTMENT
Ref.: GCC clause 57.0
Price Variation Clause shall be applicable as given in Additional Special Conditions of
Contract.
9.0
COMPLETION PERIOD
Completion period of the work is 40 months from the date of issue of Letter of
Acceptance. However, Contractor shall note that the present work is fixed key date
based work. Various activities are required to be finished within the assigned key dates,
otherwise provisions of penalty is there as specified in Additional Special Conditions of
the Contract.
The work has to be executed in co-ordination with other agencies working on or near
the project.
In case of any delay in the completion period, the extension of the same shall be dealt
as per the clause 49.0 of General Conditions of the contract.
37
3
10.0
The Contractor shall maintain, rectify and make good at his own cost any
defect/deficiencies, which may develop in the work or as notified by the Engineer during
Defect Liability Period as specified in the Appendix to Tender i.e. 12 months from the
date of completion of the work. However, maintenance during Defect Liability Period
shall not include day-to-day upkeep, cleaning, custody and security of the work.
11.0
INSURANCE
Before commencement of work, contractor shall follow the provisions of the GCC
Clause 9.0 for the Insurances at their own cost.
12.0 PROVIDING ADEQUATE SITE FACILITIES BY THE CONTRACTOR:
Contractor shall provide following office/site facilities at the bridge site/ other location for
ensuring smooth and efficient communication and work execution. Cost of these
facilities is deemed to be included in the quoted rates and nothing extra shall be paid
for this items.
i- Contractor shall provide round the clock electricity in site offices of IRCON /
Railways located at end of bridge during the entire contract work. Contractor
shall maintain the electric fittings/ wirings/ plants of offices in good condition.
ii- Contractor shall provide six computers of approved configuration ( Four desktop
and two laptop ) with at least two colour laser printer cum fax machines capable
of printing A/3 size for IRCON offices. These computers shall always be
equipped with latest, valid and authorized softwares like MS office, AUTOCAD,
PRIMAVERA and MS project etc. Contractor shall also provide three competent
and qualified operators. Contractor shall furnish the computer room/ technical
library in IRCON office at DIGHAGHAT / PAHLEJAGHAT whatsoever, may be
applicable to him, with such codes, manuals, books of reference. The cartridge,
stationary for above shall be arranged by the contractor.
iii- Railway has already installed Walkie-Talkie arrangements (about 15 sets) at site.
Contractor shall always maintain the same in good working conditions.
ivContractor shall provide at least one vehicle ( Tata Sumo or similar ) for
facilitating inspection by IRCON/Railways. All expenditure incidental to running
of these vehicles shall be borne by the contractor.
vContractor shall provide one cook, one gardener and one safaiwala for
maintenance and up keep of IRCON/Raiwlays office.
viThe contractor shall provide two rooms, with toilet facility, of size not less than
12' x 15' with suitable furniture.
vii- Contractor shall establish at his cost, the inter office communication between
IRCON and Railways offices, fabrication workshops and contractor's offices at
site. All charges for running these shall be borne by the contractor.
viii- Contractor shall provide and run and maintain a motor boat of minimum 12 seat
capacity, not older than 3 years for entire contract period.
ix- Contractor will keep deployed two survey teams and TOTAL STATION SURVEY
INSTRUMENT of approved configuration with all accessories for exact and
precise setting out of all the works. Contractor shall also have to make / maintain
adequate numbers of secondary reference survey pillars/ points/ towers of
suitable dimensions.
xContractor shall depute safety officer for supervising safety aspects of all works/
processes including enabling arrangements for execution and inspection of work.
xi.
In case of Bridge site workshop, the contractor shall, at his own cost construct the
38
3
39
3
ANNEXURE-I
BANK GUARANTEE FOR ADVANCE PAYMENT
To
IRCON INTERNATIONAL LIMITED,
Name & Address of Project.
[Acting through ______________________(Project Incharge) & Address of the Project]
Fabrication of 19 x 123m span triangulated steel bridge girders for new rail-cumroad bridge over river Ganga at Patna by setting up of field workshop on the
Pahlejaaghat end (North end) of river Ganga including leading of the structural
steel from Fatuha stockyard, shop painting and trial assembly of one span of
123m in the shop as a complete job. IRCON will supply structural steel free of
cost while the other materials shall have to be arranged by the contractor at his
own cost. Package-2 [name of Contract]
Gentlemen:
In accordance with the provisions of the Conditions of contract, Sub-Clause ____
(Advance
Payment)
of
the
above-mentioned
contract,
____________________________________________________ [name and address
of the Contractor] (hereinafter called the Contractor) shall deposit with
____________________ [name of Employer] a bank guarantee to guarantee his proper
and faithful performance under the said Clause of the Contract in an amount of
____________ [amount of Guarantee], ________________________ [amount in
words].
We, the ____________________ [name of bank], as instructed by the Contractor, agree
unconditionally and irrevocably to guarantee as primary obligator and not as Surety
merely, the payment to IRCON INTERNATIONAL LIMITED on their first demand without
whatsoever right of objection on our part and without his first claim to the Contractor, in
the
amount
not
exceeding
______________
[amount
of
Guarantee],
______________________________ [amount in words].
We further agree that no change or addition to or other modification of the terms of the
Contract or of Works to be performed there under or of any of the Contract documents
which may be made between IRCON INTERNATIONAL LIMITED and the Contractor,
shall in any way release us from any liability under this guarantee, and we hereby
waive notice of any such change, addition, or modification.
This guarantee shall remain valid and in full effect from the date of the advance
payment under the Contract upto ______ (until IRCON INTERNATIONAL LIMITED
receives/recovers full repayment of advance along with interest accrued thereon from
the Contractor).
Yours truly,
SIGNATURE AND SEAL OF THE GUARANTOR
Name of Bank:
Address:
Date:
40
4
Annexure-II
PROFORMA OF IDEMNITY BOND
Indemnity for Safe Custody of Structural Steel as per Special Conditions of Contract
Agreement No.:................dated:..........for Fabrication of 19 x 123m span triangulated
steel bridge girders for new rail-cum-road bridge over river Ganga at Patna by setting
up of field workshop on the Pahlejaaghat end (North end) of river Ganga including
leading of the structural steel from Fatuha stockyard, shop painting and trial assembly of
one span of 123m in the shop as a complete job. IRCON will supply structural steel free
of cost while the other materials shall have to be arranged by the contractor at his own
cost. Package-2
1.
We
(Name
of
Contractor)
.hereby
undertake that we shall hold at our Workshop at Patna bridge site, for and behalf of the
IRCON/Railways and in trust for him the stores / articles (mentioned in annexure, details
to be given for quantity for each section and grade) which may be
and/or which
has been made over to us, in connection with fabrication of girders against the
contract agreement No.. dated.
2.
We shall be and remain absolutely responsible for the safe custody and
protection of the said stores and articles against all risks, whatsoever, till those and
assembled in the bridge to be fabricated against the above mentioned contract and duly
delivered to IRCON/Railway or to his representative as he may direct and as such do
hereby indemnify IRCON/Railways against any loss and/or damage to the said stores
and articles while in our possession/custody. The said stores and articles shall be,
however, he at all times, open to the inspection by officers who may be authored on that
behalf by IRCON/ Railway or its nominee.
3.
Should however, at any time any loss or damage to as aforesaid, occurs or a
refund become otherwise due to IRCON/Railways, he or his representative shall be
entitled to recover from us compensation for, and in respect of such loss or damage, if
any, or the amount to be so refunded without prejudice to any other remedies which
may be otherwise available to the said IRCON/Railways by way of deduction from any
sum due to/or any sum which at any time hereafter may become due to us under this or
any other contract.
In the event of any loss or damage as aforesaid, the assessment of such loss or
damage and the assessment of the compensation therefore would be made by
IRCON/Railways or his authorized nominee and the said assessment would be final
and binding upon us.
For.
41
4
ANNEXURE-III
BANK GUARANTEE FOR EARNEST MONEY
To
General Manger (Bridges & Contracts),
IRCON INTERNATIONAL LIMITED,
C-4, District Centre, Saket,
New Delhi 11 00 17.
Fabrication of 19 x 123m span triangulated steel bridge girders for new rail-cum-road
bridge over river Ganga at Patna by setting up of field workshop on the Pahlejaaghat
end (North end) of river Ganga including leading of the structural steel from Fatuha
stockyard, shop painting and trial assembly of one span of 123m in the shop as a
complete job. IRCON will supply structural steel free of cost while the other materials
shall have to be arranged by the contractor at his own cost. Package-2 [name of
Contract]
Gentlemen:
In accordance with the provisions of the Conditions of contract, Sub-Clause 9.1 of
Instructions to Tenderers and Corrigendum No.: 1 (Earnest Money) of the abovementioned contract, ____________________________________________________
[name and address of the Contractor] (hereinafter called the Contractor) shall deposit
with ____________________ [name of Employer] a bank guarantee to guarantee his
proper and faithful participation under the said Sub-Clause of the Contract in an amount
of Rs. 25.00 Lacs [amount of Guarantee],Rupees Twenty Five Lacs Only [amount in
words].
We, the ____________________ [name of bank], as instructed by the Contractor, agree
unconditionally and irrevocably to guarantee as primary obligator and not as Surety
merely, the payment to IRCON INTERNATIONAL LIMITED on their first demand without
whatsoever right of objection on our part and without his first claim to the Contractor, in
the amount not exceeding Rs. 25.00 Lacs [amount of Guarantee], Rupees Twenty Five
Lacs Only [amount in words].
We further agree that no change or addition to or other modification of the terms of the
Contract or of Works to be performed there under or of any of the Contract documents
which may be made between IRCON INTERNATIONAL LIMITED and the Contractor,
shall in any way release us from any liability under this guarantee, and we hereby
waive notice of any such change, addition, or modification.
This guarantee shall remain valid and in full effect from the date of the submission of
the tender under the Contract upto 180-days from the date of opening of the tender.
Yours truly,
SIGNATURE AND SEAL OF THE GUARANTOR
Name of Bank:
Address:
Date:
42
SECTION - 6
ADDITIONAL
SPECIAL CONDITIONS OF CONTRACT
43
4
PARTICULARS
Length of the bridge
Span Arrangement
Type of superstructure
BRIEF DETAILS
4556 m
1 x 64 m+ 36 x 123 + 1x 64 m
Through warren type steel truss with
subdivided panels.
Superstructure with provision for double track
at bottom level and road deck at intermediate
level.
Double-D (18 m x 9.50 m)
Double-D (18 m x 6.00 m)
Outer dia-5.50 m, Inner dia-3.90 m (Twin piers)
10.75 m
18.50 m
52.50 m RL
43.50 m RL
43.50 m RL
61.80 m RL
64.393 m RL
4.
Configuration
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Note: Scope of the work shown in the above Table is for Package-I and Package-II
both. Fabrication work has been divided into two Packages of equal quantity ie.
comprising of approximately 37,000 metric tons each in each Package.
2.1 The bridge falls in seismic Zone-IV as per classification of IS: 1893. The
superstructure consists of steel trusses of 123m (c/c of pier) span and 64 m (c/c of pier)
span, for double track on bottom level and road deck at intermediate level. The warren
type truss of 123m (c/c of pier) span consists of 16 panels of 7.475 m each with centreto-centre distance of bearings as 119.6 m. The members shall consist of welded plates
of either I or Box-sections.
The Box-section shall have punched/drilled holes in plates perpendicular to plane of
truss. No butt-welding has been envisaged and splices have been provided at all joints
of the members. All site and splice connections shall have high strength rivets. The
44
Railway deck shall consist of cross girders at a spacing of 7.475 m at the bottom chord
joints of truss. The stringers and cross girders are of welded type with riveted
connections for lateral and cross bracing members. The roadway deck consists of
composite stringers and cross girders. The roadway cross girders are at the same
spacing of 7.475 m as the Rail cross girders. There are 6 stringers in each panel at a
spacing of 1700 mm. Two spans of 64 m, one each at shores shall be required to be
fabricated and launched alongwith 36 spans of 123 m each.
2.2 Briefs of the design details given above are only tentative and same may undergo
modifications at the detailed design stage.
The design and drawings of the
superstructure is being prepared by RITES who have been engaged by Railway as
design consultant.
2.3 Bridge girder drawings are under finalization. In case any delay is taking place in
arranging some of the drawings, no claim is admissible on account of delayed supply of
the drawings.
3.0 COMPENSATION TO THE CONTRACTOR REGARDING THE ADDITIONAL
TAXES/DUTIES:
The contractor should note that the rate offered by him is complete in all respect and
fixed till completion of the work. However, compensation as per Price Variation clause
shall be admissible.
If any additional taxes / duties are being imposed after issue of the LOA by either
Central or State Govt., the same shall be fully compensated as per actual on production
of the proof. Similarly in case of reduction of taxes/duties by either Central or State
Govt., rate shall accordingly be reduced in the same way.
While preferring on account/ final bills, the contractor shall have to submit a certificate
that there has not been any decrease/ abolition of any statutory taxes/ duties in respect
of those applicable on date of tender opening/ date of negotiation.
4.0 RELIEF TO THE CONTRACTOR REGARDING THE RECOVERED RETENTION
MONEY:
Retention Money shall be recovered as per the conditions laid down in GCC. However,
to ensure better liquidity of the contractors money, whatsoever retention money will be
deducted from the running bills during the last six month period, the same shall be
returned to the contractor on submission of equal amount of Bank Guarantee of the
period upto three month beyond Defect Liability Period/Maintenance period. In similar
way, on six monthly basis, recovered retention money shall be returned on submission
of Bank Guarantee of the equal amount valid beyond three months of the Defect
Liability Period / Maintenance period.
5.0 SUBMISSION OF CVs OF THE ENGINEERS AND ARTISAN STAFFS:
The contractor shall also submit CVs of the Engineers and artisan staff to be engaged to
carry out the work. The contractor shall also submit organizational chart along with the
key- position of the Engineers and artisans which shall be commensurate with the work.
6.0
BRIEFS OF THE WORK:
Scope of the work is mainly fabrication of the bridge girders. Before start of the
fabrication work, workshop fully equipped with the fabrication tools and plants including
the relevant machineries required in that connection has to be set up by the contractor
at his own cost.
45
4
The bridge girder components are having appreciable percentage of high tensile steel
as well in addition to mild steel. Fabrication shall have to be done as per drawing.
After fabrication, primer and first coat painting as per specification of the fabricated
bridge girder will be done before the dispatch. Regarding this, contractor may refer to
the technical specifications and BOQ.
For fabrication work, steel will be supplied from the stockyard of the reputed structural
steel producers. Most probably, major structural steel portion will be arranged from the
Fatua Stockyard of SAIL near Patna. Contractor shall have to load, lead, unload and
properly stack the structural steel from the stockyard to the fabrication workshop at his
own cost. If full quantity of steel is not available at the Fatua Stockyard, balance quantity
shall be arranged from somewhere else, for which additional leading charges as per
actual shall be paid to the contractor.
For brief idea of the contractor, some of the works involved are given herewith.
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
Notes:
(i)
This list is only indicative and the work is to be done in accordance with
detailed tender/contract conditions, approved drawings and as per direction of
Engineer etc as stipulated in these documents.
(ii)
Allied/secondary works not reflected in describing the BOQ item, but,
required in connection with the main work will not be paid. Those have been
mentioned just for the information/guidance of the contractor.
(iii)
Payment shall be made as per BOQ items. Nothing extra is payable beyond
the BOQ items. Contractor shall quote his rate accordingly that nothing extra
shall be paid beyond the BOQ item.
7.0 INSPECTING AGENCY:
On day-to-day basis, inspection of the fabrication work shall be done by the Engineer.
However, final inspection and passing of the bridge girders shall be done by RDSO.
Decision of the RDSO shall be final and binding
46
4
Before start of the fabrication work, many preparatory works shall be done by the
contractor and get approval of RDSO. Details of the same are given in Indian Railways
Standard Specifications for Fabrication and Erection of Steel Girder Bridges and
Locomotive Turn-Tables [Fabrication Specification (B12001)], Indian Railway
Standard Code of Practice for Metal Arc Welding in Structural Steel Bridges Carrying
Rail, Rail-cum-Road or Pedestrian Traffic (Welded Bridge Code), Birdge manual, etc.
Contractor shall follow each and every provisions contained in the Codes and Manuals
as well as instructions given by the engineers and representatives of RDSO.
8.0 SETTING UP OF THE WORKSHOP INCLUDING SITE OFFICE:
The contractor shall submit schematic plan and flow diagram of the proposed
field workshop along with his offer.
For setting up of the workshop, IRCON will provide adequate area, i.e. fully developed
and leveled land free of cost. Necessary work regarding connecting the earmarked
area for setting up of the workshop and site office with proper road and all related
works shall be done by the contractor at his own cost. Complete setting up of the
workshop and site office along with the required machineries; tools and plants including
setting up of the laboratory shall be done by the contractor at his own cost. Nothing
extra for that shall be paid. Responsibility of IRCON shall be just to provide the
adequate developed and leveled land free of cost.
This shall be ensured that levelled land is handed over to the successful bidders for
setting up of the workshop. But, for the land required by the contractor for his own
purpose like, his office, hutments, etc. , he will make his own arramgement for land.
Following minimum Machines & Plants will essentially be required to be arranged in the
workshop, which will be handed over to IRCON on completion of work in working
condition alongwith the shed, free of cost:
i.
Hydra Crane 12 MT : 06 Nos.
ii.
Tata 320 Crane 12 MT : 02 Nos.
iii.
Gantry Crane with Hoist: 03 Nos.
iv.
Generator 320 KVA 03 Nos.
v.
SAW (Submerged Arc Welding Machine) : 08 Nos.
vi.
MIG (Manual Inert Gas Welding Machine) : 05 Nos.
vii. Welding Rectifier : 05 Nos.
viii. Radial Drilling Machine : 10 Nos.
ix. Compressor 450 Cfm : 03 Nos.
x.
Step down transformer : 02 Nos.
xi. End Milling Machine : 02 Nos.
xii. Magnetic drill : 15 Nos.
xiii. PUG Machine : 04 Nos.
xiv. Gas Cutters : 04 Nos.
xv. Hydraulic Press for Straightening : 03 Nos.
Other machines whatsoever required for fabrication need not be handed over to IRCON
on completion of the work.
To test the raw material and girders to conform to relevant specification, testing facilities
for the following shall be made available either in house or through outsourcing.
i)
47
4
ii)
The above list is only indicative. Number of each and every equipment required in
connection with fabrication of Bridge girders shall be finalized by the contractor keeping
in view achieving the key date progress.
Rough assesment reveals that workshop should have the capacity to produce
1200 to 1500 MT of bridge girder per month. As such, tenderer alongwith its offer
shall submit the details of such machines required to be procured/installed in the
field workshop to achieve a monthly production of aforesaid tonnage per month.
All equipments shall be of standard make so that chances of their failure may be
minimum. This is essential to ensure by the contractor since, in missing the key dates
progress, penalty clause is there.
9.0 ARRANGEMENT OF ELECTRICITY AND WATER:
Contractor shall make his own arrangement for electricity and water. IRCON will just
confirm to the concerned authority about award of the work to that particular contractor.
Contractor should note that keeping in view the tight target of the work based on fixed
key dates as well as electricity deficient position of the State of Bihar, standby power
arrangement will have to be made, otherwise meeting with the target will not be
possible.
10.0 PREPARATORY ARRANGEMENTS BEFORE START OF THE WORK:
Fabrication of the bridge girders is highly specialized work. It requires lot of technical
inputs. Some of the inputs required in this connection are listed herewith. Contractor
should know that the list is only indicative and not exhaustive/complete. Some more
preparatory measures/ arrangements as per the requirement, if arises anytime during
the work in progress, shall be done by the contractor. Indicative list of the
arrangements is as under:
i)
ii)
iii)
Recruitment of the welders and preparation of the test samples for testing
and passing of the same. Only qualified welders duly approved by RDSO
shall be allowed to do the welding works.
Recruitment of rivetiers for doing the rivetting works required in connection
with fabrication of the bridge girders. Only qualified rivetiers will be allowed
to do the work.
Preparation of jigs and fixtures for fabrication of the bridge girders. Jigs
and fixtures shall be offered to RDSO for their inspection and passing.
Preparation of Quality Assurance Programme (QAP) and getting approval of
the same from the RDSO. QAP shall be prepared well in time and be got
approved from RDSO.
All preparatory works, some of which have been mentioned above for guidance of the
contractor, shall be completed well in time and as per the programme submitted by the
contractor.
Contractor shall give fortnightly progress about the preparatory works. Non-starting of
the preparatory work/inordinate delay in that may be one of the grounds for annulment
of the contract.
14.0 PROCUREMENT OF STEEL:
14.1 GENERAL:
49
4
the fixed key date related fabrication targets. Contractor shall arrange the necessary
T&Ps including manpower accordingly.
To meet with the target, contractor shall start physical fabrication work from D +
145 days, where D is the day of issue of LOA. He shall be able to arrange trial
assembly of the fabricated girders in his workshop premises by D + 225 days.
Fabrication work shall be completed in all respects in 3 years time from the issue of
letter of acceptance.
To ensure smooth progress of work, within 15 days of the issue of LOA, contractor shall
submit the Bar Chart showing the main activities along with its start and finish time.
Initial activities shall be regarding setting up of the workshop, offices, laboratories,
procurement of machineries, approval of artisan staff from the inspecting agencies,
finalization of the other preparatory works, etc.
After setting up of the workshop and starting of fabrication works, activities has to be
modified mainly related to fabrication plans, offering of the fabricated components for
inspection, testing of the materials, etc.
For better planning, by 25th of every month, contractor shall submit detailed programme
of the following month. If any shortfall had taken place, the contractor shall enhance the
average monthly progress target accordingly so as to meet with the shortfall.
17.0 SUBMISSION OF BAR CHART REGARDING COMMISSIONING OF THE
WORKSHOP:
Within 15 days of the issue of LOA, contractor shall submit the Bar Chart regarding
commissioning of the fully equipped workshop along with required sheds, offices along
with equipment, Lab along with equipments/apparatus and installation of the required
machineries including T&Ps. This Bar Chart be strictly adhered to so that workshop
may be functional in all respects by D + 140 days.
2.
D + 140 Days
3.
D + 210 Days
Successful
123m span
trial
assembly
4.
D + 270 Days
5.
D + 330 Days
Completing total fabrication
of 4 Nos. of 123 m span.
6.
D + 504 Days
7.
D + 678 Days
8.
D + 852 Days
9.
D + 1026 Days
10.
D + 1200 Days
NOTE: For each missing key date, a penalty of Rs.1 Lakh per day shall be imposed.
However, this penalty can be reimbursed, if the contractor makes up the progress and
completes the work as per target of next key dates i.e. meeting with the cumulative
target of next key date.
19.0 ACTION FOR EFFICIENT / SLOW PROGRESSING CONTRACTOR:
Work being of national importance having tight target, it shall be ensured to complete
the same as per the key dates. To achieve the same, provisions for rewarding the
efficient contractor and imposing suitable penalty to the slow contractor shall be made
and be implemented as under:
(i)
(ii)
In case of failure to achieve the first key date, a penalty of Rs.1 lakh per day
shall be imposed. If the Contractor is catching up and making good the
progress as per schedule by the next key date, imposed penalty shall be
refunded through the running bill.
In case Contractor fails in achieving the target as scheduled by the next key
date as well, in addition to imposition of penalty, part quantity in terms of span
units may be withdrawn and be handed over to other contractor if he is
progressing well.
52
5
(iii)
If the contractor who is progressing well is meeting with his own target and is
in a position to complete the additional assigned work within the next two key
dates, he shall be given incentive of Rs.1000/MT for the additional quantities.
This incentive shall be in addition to his quoted rate. In case the other
(another package) contractor is not able to meet the target by the next two key
dates, after assigning the additional quantity, incentive of Rs.1000/MT shall
not be given.
Total quantity variation in this work will be to the extent of 50% of the original assigned
quantity. It is clarified here that this quantity variation clause will prevail and not the
quantity variation clause given in GCC of IRCON.
20.0 PRICE VARIATION CLAUSE:
20.1 GENERAL:
i)
ii)
iii)
iv)
The rates for each item quoted by the contractor in his tender and
accepted by IRCON shall hold good till the completion of the work.
Fluctuations in market rates/conditions, taxes additional levies or any
other changes in the cost of an item as a whole or in the cost of a
component of expenditure constituting that item shall be taken into
account and payments to contractor shall be adjusted i.e. increased/
decreased, in accordance with the provisions of this clause. No other
claims on account of these disputes shall be admissible.
The total amount payable to the contractor for the payments made
through on account/final bills for the work done in a particular quarter
shall be adjusted i.e. increase/decrease, based on the overall market
situation as reflected by increase/decrease in various Price Indices
published by the Reserve Bank of India from time to time.
The amount of adjustment i.e. increase/decrease in the payments to the
contractor shall be calculated in accordance with the method detailed
herewith.
Price variation is not applicable for any new NS item, if any, that may be
included subsequent to finalization of contract.
ii)
Material supplied free by IRCON to the contractor will fall outside the
purview of Price Variation Clause.
53
5
(a)
R x (l- l0)
I0
(b)
(c)
M
U
100
R x (W- W0 )
W0
R (F- F0)
F0
X
X
Q
100
Z
100
Where:
L =
M =
U =
R
L0
I0
Wo =
W
Fo =
F
P
Q
Z
=
=
=
The percentages P, Q, Z of various components i.e. labour, materials, fuel etc for items
other than supply of steel and cement in this contract shall be as follows: Labour components (P)
35%
Material components(Q)
15%
Fuel components (Z)
30%
Fixed components
20%
The amount on which the adjustment is to be calculated, shall be the amount payable to
the contractor for the item or items of various types of works given in the reference
quarter, Refer Making adjustment for price variation below for procedure of calculation
of adjustment.
The calculations for adjustments in the amount payable to the contractor shall be made
on the value of the work done in each quarter by the contractor. Quarterly periods shall
be counted commencing from the month following the month in which tender have been
opened. However, in case the tender is finalized after the negotiation, quarterly periods
shall be counted commencing from the month following the month in which the last
negotiation was held leading to the award of contract. Refer Making adjustment for
price variation below also.
The calculations for adjustments should be based on the average price Index of the
three months of the quarter.
The demand for escalation of the cost may be allowed on the basis of provisional
indices made available by the Reserve Bank of India. Any adjustment need to be done
based on the finally published indices shall be made as and when they become
available.
20.6 MAKING ADJUSTMENTS FOR PRICE VARIATION:
i)
The adjustment for variation in prices i.e. extra payment in case of increase
and recovery in case of decrease, as required, shall be made once in every
quarter in the on accounts payments. If more than one on account payment
is made to the contractor in a quarter, the adjustment, if required, shall be
made as and when they become available.
ii)
It shall be contractors responsibility to submit the value of various price
Indices for appropriate points of time along with proof / authenticity thereof,
to enable the IRCON to calculate the price variations.
20.7 METHOD OF OPERATION OF THIS CLAUSE:
i)
Since the adjustment of payments are based on the amount of work done
by contractor in each quarter, measurements of actual work done must be
taken and recorded in the measurements books and signed by the
contractor at the end of each quarter, if not frequently.
ii)
Since the various Indices are published by RBI / Ministry of Labour a few
months later than the months to which they pertain, the normal on account
bills based on quarterly measurements will be prepared as per current
procedure on the adopted rates without considering the Price Variation
clause.
iii)
The adjustments in Price variations shall be done subsequently through
separate series of on account bills, called Escalation on account bill no 1,2
etc. the adjustment bills and the normal on account bills will be kept
independent of each other for facility of operations.
55
5
After completion of the work, contractor shall hand over the complete workshop i.e.
fixed structure along with machineries as was there during the fabrication time, to Ircon
International Limited for further use of the same. It means that just after completion of
the work, the complete workshop along with all its assets shall be property of IRCON.
However, proper handing over of the assets as mentioned in Clause 8.0 above Setting
up of the workshop including site office, mentioning each and every item along with its
particulars and conditions shall be handed over by the contractor to the Engineer of
IRCON. In case of removal of any assets which was there during the fabrication time but
removed during the handing over time by the contractor, necessary recovery shall be
made from the dues of the contractor.
56
5
However, Sand blaster, spray painting machine, office computers may be carried
away by the contractor after completion of the work.
Tenderer shall workout their rate accordingly and quote while bidding. Nothing
extra shall be paid to the Contractor in taking over of the workshop along with its
complete assets including machineries, T&Ps, Lab equipments etc.
25.0 SITE CLEARANCE:
After completion of the work, site has to be cleared including removal of all debris and
be handed over to IRCON/Railways. Nothing extra for dismantling of the workshop,
removal of debris and clearing of the site, etc. shall be paid.
26.0
57
5
SECTION - 7
58
DESCRIPTION
CLAUSE
No.
1.0
DEFINITIONS
2.0
3.0
4.0
5.0
6.0
7.0
CONTRACTOR'S UNDERSTANDING
8.0
9.0
INSURANCE
10.0
COMMUNICATION
CONTRACTOR
11.0
12.0
13.0
SUBCONTRACTING
14.0
15.0
PROGRAMME OF WORK
16.0
COMMENCEMENT OF WORK
17.0
18.0
SETTING OUT
19.0
TEMPORARY WORKS
20.0
21.0
22.0
BETWEEN
59
EMPLOYER/ENGINEER
AND
23.0
24.0
25.0
PROTECTION OF ENVIRONMENT
26.0
CARE OF WORKS
27.0
USE OF EXPLOSIVES
28.0
29.0
EXCAVATED MATERIALS
30.0
31.0
32.0
33.0
34.0
ENGINEERS MATERIALS
35.0
36.0
37.0
38.0
39.0
ENGAGEMENT OF LABOUR
60
40.0
WAGES OF LABOUR
41.0
42.0
43.0
REPAIR TO DAMAGES
44.0
45.0
46.0
47.0
48.0
49.0
50.0
51.0
52.0
13.0.1.1.DEATH OF CONTRACTOR/PARTNER
53.0
EMPLOYMENT OF RETIRED
EMPLOYER/ENGINEER
54.0
MODIFICATION TO CONTRACT
55.0
MODIFICATIONS TO WORK
56.0
61
OFFICERS/
ENGINEER
OF
57.0
58.0
59.0
60.0
61.0
62.0
ON ACCOUNT PAYMENT
63.0
64.0
65.0
COMPLETION CERTIFICATE
66.0
67.0
68.0
69.0
70.0
PRODUCTION OF VOUCHERS
71.0
FORCE MAJEURE
72.0
SETTLEMENT OF DISPUTES
ANN-I
FORMAT OF AGREEMENT
ANN-II
ANN-III
BANK GUARANTEE
RETENTION MONEY
FORMAT
62
FOR
RELEASE
OF
50%
DEFINITIONS
In the Contract, as herein after defined, the following word expressions shall
have the meanings hereby assigned to them, except where the context requires
otherwise.
a)"Client or Principal Employer or Owner" means the Department,
Organisation, individual, firm, company, J.V. or Consortium who awarded the
work to IRCON International Limited for execution of the project of which the
works is a part, and shall include its heirs, executors, legal representatives etc.
b)"Employer" means the IRCON INTERNATIONAL LIMITED, A Govt. of India
Undertaking (IRCON in abbreviation) acting through its Managing Director or any
other authorised officer and shall include their legal successors in title and
permitted assignees.
c)"Engineer or Engineer in Charge" means the Project Head of IRCON
INTERNATIONAL Ltd.(Employer) or any other officer authorised by the Employer
to act on his behalf and for the purpose of operating the contract.
d)"Engineer's Representative" means any official nominated from time to time
by the Engineer to act on his behalf.
e)"Contractor" means the individual, firm, Company, Corporation, Joint venture/
consortium, or Consortium whether incorporated or not, who enters into the
Contract with the Employer/Engineer, and shall include its heirs, executors,
administrators, successors, legal representatives, as the case may be.
f)"Contractors Representative" shall mean the person responsible for
execution of the contract who shall be so declared by the Contractor and who
shall be authorised under a duly executed power of attorney to comply the
instructions and to use, receive materials issued by the Engineer to the
Contractor for works. He shall be capable of taking responsibility for proper
execution of works.
g)"Sub-Contractor" means the individual, firm, Company, Corporation, Joint
venture/ consortium or Consortium, having direct Contract with the Contractor
and to whom any part of the work has been sublet by the Contractor and shall
include his heirs, his executors, administrators, successors, legal
representatives, as the case may be.
h)"Other Contractors" means the individual, firm, Company, Corporation, Joint
venture/ consortium or Consortium employed by or having a Contract directly or
indirectly with the Client/Employer/Engineer other than the Contractor.
i)"Tenderer or Bidder" means the individual, firm, Company, Corporation, Joint
venture/ consortium or Consortium submitting a bid/tender.
j)"Scheduled Bank" means a bank included in the second schedule to the
Reserve Bank of India Act, 1934, or modification thereto.
63
k)"Contract" shall mean and include the Agreement or Letter of Acceptance, the
accepted Bill of Quantities and Rates, the General Conditions of Contract,
Special Conditions of Contract, Appendix to Tender, Form of Bid, Instructions to
the Tenderers, Drawings, Specifications and other Tender Documents.
l)"Tender or Bid" means the offer (Technical and/or Financial) made by
individual, firm, Company, corporation, Joint venture/ consortium or Consortium
for the execution of the works.
m)"Specifications" means the specifications referred to in the Contract and any
modification thereof or addition thereto, or as may from time to time be furnished
or approved in writing by the Engineer.
n)"Drawings" means the Drawings annexed to the Contract or referred in it and
shall include any modifications of such Drawings and further Drawings as may
be issued or approved by the Engineer.
o)"Bill of Quantities (BOQ)" means list of items of work, their quantities and
rates.
p)Original Contract Value" means the sum stated in the letter of
Acceptance/Contract Agreement.
q)Contract Value" means the original contract value subject to the adjustments
in accordance with the provisions of the Contract.
r)"Temporary Works" means all enabling works of every kind required for the
execution of the works.
s)"Permanent Work(s)/ Work(s)" means the works (other than temporary
works) to be executed in accordance with the Contract or part/s thereof as the
case may be and shall include extra or additional, altered or substituted items of
work as required for performance of the Contract.
t)"Construction Plant" means all machinery, appliances or things of whatsoever
nature required for the execution, completion and maintenance of the works, but
does not include material or other things intended to form or forming part of the
permanent works.
u)"Site" means the land and/or other places on, under, in or through which the
works are to be carried out, and any other lands or places provided by the
Client/Employer/Engineer for the purpose of the Contract.
v)"Material/s" means all equipment, components, fittings and other materials
including raw materials, which form part of the permanent works.
w)"Test" means such tests as prescribed in the Contract or by the Engineer or
Engineer's Representatives, whether performed by the Contractor or by the
Engineer or his Representative, or any agency approved by the Engineer.
64
3.0
4.0
5.0
65
7.0
CONTRACTOR'S UNDERSTANDING
The Contractor shall be deemed to have satisfied himself, before tendering, as to
the correctness and sufficiency of his tender for the works and of the rates and
prices stated in the Bill of Quantities, all of which shall except in so far as it is
otherwise provided in the Contract, cover all his obligations under the Contract
and all matters and things necessary for the proper execution, completion and
maintenance of works.
8.0
8.1
8.2
i.
ii.
iii.
8.3
be
Performance Security for Contracts valuing more than Rs. 1.00 Crore
Within 28 days of issue of the Letter of Acceptance from the Employer/Engineer,
the successful tenderer shall furnish to Employer/Engineer a Performance
Security in the form of bank guarantee on the proforma annexed as annexure-II
from any Scheduled Bank for an amount of 2% (Two percent) of the original
Contract value.
Alternatively, the performance security can be furnished by the Contractor in the
form of Fixed Deposit Receipt (FDR) from a scheduled bank endorsed in
favour
of the Employer.
The Bank Guarantee/FDR shall be operative till the same is approved for
discharge by the Employer/Engineer on satisfactory completion of work.
No payment under the contract shall be made to the Contractor before receipt of
performance security.
Failure of the successful tenderer to furnish the required performance security
shall be a ground for the annulment of the award of the Contract and forfeiture of
the Earnest Money Deposit.
Retention Money:
66
i.
ii.
Retention money for all contracts shall be recovered from on account/ final bills
of the Contractor @ 10% of gross value of each bill after adjusting EMD amount
till the amount so recovered including EMD amount adds upto 5% of the contract
value of the work.
No interest shall be payable to the Contractor on the amount retained in cash
towards retention money.
8.5
i.
(iii)
67
INSURANCE
9.1 Depending on the nature of work, Contractors All Risk (CAR) shall be obtained by
Employer/Engineer at his own cost as per the requirement. Employer/Engineer may
take necessary add on covers and voluntary excess specified elsewhere in the
contract, which shall be binding on the Contractor. At the time of taking policy,
possible time over-run, if any, may be taken into account in deciding the
period/validity of the policy. The above insurance shall cover the risks normally
covered under the CAR policy. Any item not covered under the above policy shall be
the responsibility of the Contractor.
9.2 Contractors claims, if any, shall be entertained within the scope of Insurance policy
taken by Employer/Engineer. This will be subject to:9
The Policies of the Contractor shall remain in force through out the period
of execution of the works and till the expiry of the defect liability period
except for any specific insurance covers necessary for shorter period.
If the Contractor fails to effect or keep in force or provide adequate cover
as acceptable to the Engineer in the insurance policies mentioned above,
then in such cases, the Engineer may effect and keep in force any such
insurance or further insurance on behalf of the Contractor. The recovery
shall be made at the rate of 1.5 times the premium/premiums paid by the
Engineer in this regard from the payment due to the Contractor or from
the Contractors Performance Security. However, the Contractor shall not
be absolved from his responsibility and/or liability in this regard.
10 COMMUNICATION BETWEEN EMPLOYER/ENGINEER AND CONTRACTOR
10.1 Instructions in writing
Instructions given by the Engineer shall be in writing, provided that if for any reason the
Engineer considers it necessary to give any instructions orally, the Contractor shall
comply with such instructions. Confirmation in writing of such oral instruction given by
the Engineer, whether before or after carrying out of the instructions, shall be deemed
to be instructions within the meaning of this sub-clause.
The Contractor shall also be bound to carry out any instructions issued by Client as
confirmed in writing by the Engineer.
10.2 All certificates, notices, written orders or letters, to be given by the Employer or the
Engineer to the Contractor, shall be deemed to have been served, if the same are
delivered to the Contractor or his authorised representative, or delivered or left at or
posted to the given address of the Contractor or Contractors registered office or
principal place of business. Such documents shall be deemed to have been received
on the day they are left or delivered, or in the case of postal transmission, on the day
they would ordinarily have reached but not exceeding 7 days from the date of posting
inclusive of day of posting, in any case.
69
11
12
70
SUBCONTRACTING
13.1 Subcontracting
The Contractor shall not subcontract the whole of the works. Except
where otherwise provided in the Contract, the Contractor shall not
subcontract any part of the works without the prior consent of the Engineer
in writing. Any such consent shall not relieve the Contractor from any of
his liability or obligation under the Contract and he shall be responsible
for the acts, defaults and neglects of any subcontractor, his representative,
servants or workmen as fully as if they were the acts, defaults or neglects
of the Contractor.
i.
71
14
15
PROGRAMME OF WORK
The Contractor shall submit the programme for completion of work to the
Engineer for his approval within 15 days from the date of receipt of letter of
acceptance. Unless otherwise directed, the programme shall be in the form of
Bar-Chart showing proposed execution of quantities of principal items of work.
The programme shall be related to the capability of equipment proposed to be
deployed and site conditions. The Contractor shall also provide in writing
methodology for execution of major items of work as desired by the Engineer.
The submission and approval of such programme shall not relieve the
Contractor of any of his duties or responsibilities or obligations under the
contract. The Engineer shall have full power and authority during the progress
of work, to issue such instructions as may be necessary for the proper and
adequate execution of the work.
16
COMMENCEMENT OF WORK
72
The Contractor shall commence the works within the time limit as specified in the
Letter of Acceptance.
17
18
SETTING OUT
The Contractor shall be responsible for the true and proper setting out of the
works using his own survey instruments, appliances and labour. If at any time
during the progress of works, any error appears or arises in any part of the
work, the Contractor on being required to do so by the Engineer, shall at once
rectify such error, to the satisfaction of the Engineer. The Contractor shall also
provide all necessary assistance in the form of labour and materials to Engineer
or his representatives for checking the set out with his own instruments. The
checking of any setting out, or of any line or level by the Engineers
representative shall not any way relieve the Contractor of his responsibility for
the correctness thereof. The Contractor shall carefully protect and preserve all
bench marks, reference pillars, pegs, and other things used in setting out the
works.
19
i.
ii.
20
TEMPORARY WORKS
All temporary works necessary for the proper execution of the works shall be
provided and maintained by the Contractor at his own cost. All detailed working
drawings, design, design calculations and fabrication drawings for important
temporary works as decided by the Engineer, shall be prepared by the
Contractor at his own cost and forwarded to the Engineer at least 30 days in
advance of actual constructional requirements for his approval. Such approval
shall not, however, relieve the Contractor of any of his responsibility in
connection with the temporary works.
When the temporary works are no longer required, the Contractor shall remove
the same at his own cost. In the event of failure on the part of the Contractor to
remove the temporary works, the Engineer will cause them to be removed and
cost incurred for removal, supervision, and other incidental charges shall be
recovered from the Contractor.
SPECIFICATIONS AND DRAWINGS
73
20.1
The Contractor shall keep at site in good condition one copy of latest approved
Specifications and Drawings and also such other Contract documents as may be
necessary and make them available to the Client/Employer/Engineer or his
Representative at all reasonable times. Any specification & drawing shall not be
used on any other work or communicated to a third party by the Contractor.
20.2
20.3
21
21.2
pay all royalties, taxes, rent and other payments or compensation, if any,
for getting the materials required for the works and due fulfillment of the
contract and indemnify Client/Employer/Engineer against any claims in
this regard.
22
Existing road or water courses or any other utility shall not be blocked,
cut through, altered, diverted or obstructed in any way by the Contractor,
except with the permission of the Engineer. All compensation claimed by
any Department/Organisation for any unauthorized closure, cutting
through, alteration, diversion or obstruction to such roads or water
courses by the Contractor or his staff shall be recovered from any moneys
due to the Contractor.
ii)
iii)
iv)
24.0
24.1
75
24.4
25.0
PROTECTION OF ENVIRONMENT
During execution of works, the Contractor and his sub-contractors, petty
contractors shall abide at all times by all existing enactments on environmental
protections and rules made there under, regulations, notifications and bye-laws
of the State or Central Government or local authorities and any other law, byelaw, regulation that may be issued in this respect in future by the State or Central
Government or local authority. Salient features of some of the laws that are
applicable are given below:i)
The Water (Prevention and Control of Pollution) Act, 1974. This provides
for the prevention and control of water pollution and maintaining and
restoring of wholesomeness of water. Pollution means such
contamination of water or such alteration of the physical, chemical or
biological properties of water or such discharge of any sewage or trade
effluent or of any other liquid, gaseous or solid substance into water
(whether directly or indirectly) as may, or is likely to, create a nuisance or
render such water harmful or injurious to public health or safety, or to
domestic, commercial, industrial, agricultural or other legitimate uses, or
to the life and health of animals or plants or of aquatic organisms.
ii-
The Air (Prevention and Control of Pollution) Act, 1981. This provides for
prevention, control and abatement of air pollution. Air Pollution means
the presence in the atmosphere of any air pollutant, which means any
solid, liquid or gaseous substance (including noise) present in the
atmosphere in such concentration as may be or tend to be injurious to
human beings or other living creatures or plants or property or
environment.
76
iii-
The Environment (Protection) Act, 1986. This provides for the protection
and improvement of environment and for matters connected therewith,
and the prevention of hazards to human beings, other living creatures,
plants and property. Environment includes water, air and land and the
inter-relationship, which exists among and between water, air and land,
other living creatures, plants, microorganism and property.
The Public Liability Insurance Act, 1991. This provides for public liability
insurance for the purpose of providing immediate relief to the persons
affected by accident occurring while handling hazardous substances and
for matters connected herewith or incidental thereto. Hazardous
substance means any substance or preparation which is defined as
hazardous substance under the Environment (Protection) Act, 1986, and
exceeding such quantity as may be specified by notification by the Central
Government.
26.0
CARE OF WORKS
From the commencement of the work until completion, acceptance and final take
over of the works by the Engineer, the Contractor shall take full responsibility for
the care of all works including temporary works. In case any damage, loss or
injury happens to the work or to any temporary works from any cause
whatsoever, the Contractor shall at his own cost repair and make good the same
so that on completion and at the time of final take over, the work shall be in good
condition and in conformity in every respect with the requirements of the contract
and the Engineers instructions.
the property of the Client. The Contractor may be permitted by the Engineer to use the
same for the purpose of works on mutually agreed payment terms.
30.0 RELICS AND TREASURES
All gold, silver, coins, oil and other minerals of any description, and precious stones of
all kinds, treasures, antiques, fossils and other similar things, which shall be found in or
at site, shall be the property of the Client and the Contractor shall duly preserve the
same to the satisfaction of the Engineer, and from time to time deliver the same to such
person or persons, as the Client/Engineer may appoint to receive the same.
31.0 CO-OPERATION WITH OTHER CONTRACTORS
The Contractor shall in accordance with the requirements of the Engineer, cooperate
with and afford all reasonable opportunities for carrying out the work by other
Contractors engaged by the Client/Employer/Engineer or any other Authority.
32.0 WORK DURING NIGHT
Unless specifically provided elsewhere in the Contract, the Contractor shall not carry
out any work between sunset and sunrise without the prior permission of the Engineer.
In case of any grave emergency or in order to avoid risk to property and life or to
prevent damage to utilities or to restore them, work may be done at night also without
the prior permission of the Engineer, but intimation to this effect should be sent to him
immediately. No increase in rates or extra payment shall be admissible for the night
work. The Contractor shall make adequate lighting and safety arrangements for night
working. He shall also be responsible for any claim on account of any injury to or loss
of life, of any one, arising out of inadequate lighting, safety arrangements or due to any
other failure of the Contractor.
33.0SHEDS, STORES, YARDS
The Contractor shall at his own expense provide and maintain sheds, store-houses and
yards at such locations and in such numbers as in the opinion of the Engineer are
necessary for carrying out the works. The Engineer and the Engineers representatives
shall have free access to the said sheds, storehouses and yards at any time for the
purpose of inspecting the stock of materials and plant so kept in hand. Any materials or
plant which the Engineer may object to shall not be brought upon or used in the works
and shall forthwith be removed from the sheds, storehouses or yards by the Contractor.
34.0ENGINEERS MATERIALS
34.1 Materials to be supplied by the Engineer.
After the acceptance of tender, the Contractor shall make request in writing to the
Engineer for the materials to be supplied by the Engineer, if any, in accordance with the
approved programme for execution of works.
34.2 Cost to be borne by Contractor
78
The materials shall be issued to the Contractor at the Engineers depots or near the
project site. The Contractor shall bear the cost of loading, transporting to site,
unloading, storing safely under cover, as required.
34.3 Return of surplus materials.
All surplus materials issued to the Contractor by the Engineer for use, incorporation or
fixing in the works (including preparatory works, if any) shall, on completion of or
before closure of works, be returned by the Contractor at his expense. However, the
materials considered unserviceable by the Engineer shall not be taken back.
34.4 Credit for returned materials.
Surplus materials returned by the Contractor in acceptable condition to the Engineer
shall be credited to the Contractor by the Engineer.
34.5 Accountal of the materials issued by the Engineer including recovery etc. shall be
in accordance with the Special Conditions of Contract.
35.0TOOLS, PLANT AND EQUIPMENT
Except for any specific item mentioned in the contract, the Contractor shall have to
make his own arrangements, at his own cost, Plant, Machinery and Equipment required
for execution and completion of all works to the entire satisfaction of the Engineer. This
shall also include all other associated equipment, tools/tackles, spare parts, POL,
consumables, stores, manpower as required for the execution of works.
38.2
38.3
38.4
38.5
Use of Intoxicants
No sale of alcoholic drinks and/or intoxicating drinks or drugs shall be
permitted by the Contractor at or near the site. The Contractor shall also
80
ENGAGEMENT OF LABOUR
The Contractor shall make his own arrangements for the engagement of all
labour, except as provided otherwise in the contract.
The Contractor shall not employ any labour below the age prescribed in any
labour legislation, directly or through petty Contractors or sub-Contractors, for
execution of the work.
81
REPAIR TO DAMAGES
resources as may be considered necessary and the cost of such remedial works shall
be recovered from the Contractors dues. The decision of the Engineer regarding
reasons of the damage shall be final and binding.
44.0 IMPLEMENTATION OF QUALITY MANAGEMENT SYSTEM
44.1 The Contractor shall follow and implement Quality Management System as
per IS/ISO-9001-2000.
44.2 The Contractor shall execute the work following the safety policy of IRCON
which shall include providing safety equipment, safety shoes, helmets to all
workers, erecting of safety barricades and displaying safety posters and
instructions about awareness for safety.
44.3 The Contractor shall arrange timely calibration of all his measuring and
testing equipment at his own cost from reputed laboratory and supply of
calibration certificates to the Engineer.
44.4 The Contractor shall ensure maintenance and overhauling of all his plant
and machinery to satisfy the requirements of IS/ISO-9001-2000.
44.5 The Contractor shall arrange to provide test certificates issued by
manufacturers for materials supplied by him or arrange to test the materials at
his own cost in a reputed laboratory and supply test certificates to the Engineer.
The Contractor shall implement full process control by issue of work instructions
and check lists and maintaining latest drawings, specifications and codes.
45.0
ii.
83
The Engineer shall have the authority to order in writing from time to time:
a.The removal from site within specified time, of any material, which in the
opinion of the Engineer, is not in accordance with the Specifications and
Conditions of the Contract.
b.The substitution of defective material by approved quality material; and
c.The removal and proper re-execution, notwithstanding any previous
decision or interim payment thereof, of any work which in respect of
materials or workmanship is not, in the opinion of the Engineer, in
accordance with the contract.
ii.
In case of default on the part of the Contractor in carrying out such order,
the Engineer shall be entitled to get the same done by engaging another agency
or by deploying labour, materials and other resources. All such cost shall be
recovered from the Contractors dues.
47.0 EXAMINATION OF WORK BEFORE COVERING UP
No work or part of work shall be covered up or put out of view, without the prior
approval of the Engineer or the Engineers representative. If any work shall be
covered up or put beyond the reach of inspection/measurement without the prior
approval of the Engineer or Engineers representative, the same shall be
uncovered by the Contractor at his own cost.
48.0 SUSPENSION OF WORKS ORDERED BY THE ENGINEER
The Contractor shall, on the order of the Engineer, suspend the works or any
part thereof, for such time, and in such manner, as the Engineer may consider
necessary, and shall during such suspension, properly protect and secure the
works so far as it is necessary in the opinion of the Engineer.
The Contractor shall not be entitled to extra cost, if any, incurred by him during
such suspension if such suspension is on account of weather conditions or
requirement for execution of works or provided for in the Contract or for less
than 30 days at a time for any other reason. The Contractor shall, however, be
entitled for extension of time for completion of work as the Engineer may
consider proper having regard to the period of suspension. However, if the
suspension is ordered by the Engineer due to any default of the Contractor such
as defective materials, workmanship etc., the Contractor shall not be entitled to
any extension or extra cost incurred.
49.0
84
49.1 The time allowed for execution and completion of the works or part of the
works as specified in the contract, shall be essence of the contract on the part of
the Contractor.
49.2 As soon as it becomes apparent to the Contractor, that the work and / or
portions thereof (required to be completed earlier), cannot be completed within
the period(s) stipulated in the contract, or the extended periods granted, he shall
forthwith inform the Engineer and advise him of the reasons for the delay, as
also the extra time required to complete the works and / or portions of work,
together with justification therefore. In all such cases, whether the delay is
attributable to the Contractor or not, the Contractor shall be bound to apply for
extension well within the period of completion/extended period of completion of
the whole works and / or portions thereof.
49.3 Extension due to modifications
If any modifications are ordered by the Engineer or site conditions actually
encountered are such, that in the opinion of the Engineer the magnitude
of the work has increased materially, then such extension of the stipulated
date of completion may be granted, as shall appear to the Engineer to be
reasonable.
49.4 Delays not due to Employer/Contractor.
If the completion of the whole works (or part thereof which as per the
contract is required to be completed earlier), is likely to be delayed on
account of:
a) Any force majeure event referred to in Clause 71.0 or
b) Delay on the part of other Contractors engaged directly by the
Client/Employer, on whose Progress the performance of the
Contractor necessarily depends or
c) Any relevant order of court or
d) Any other event or occurrence which, according to the Engineer is
not due to the Contractors failure or fault, and is beyond his
control;
The Engineer may grant such extensions of the completion period as in
his opinion is reasonable.
49.5 Delays due to Employer/Engineer.
In the event of any failure or delay by the Employer/Engineer in fulfilling
his obligations under the contract, then such failure or delay, shall in no
way affect or vitiate the contract or alter the character thereof; or entitle the
Contractor to damages or compensation thereof but in any such case, the
Engineer shall grant such extension or extensions of time to complete the
work, as in his opinion is / are reasonable.
49.6 Delays due to Contractor and Liquidated Damages:
If the delay in the completion of the whole works or a part of the works,
beyond stipulated completion period, is due to the Contractors failure or
85
fault, and the Engineer feels that the remaining works or the portion of
works can be completed by the Contractor in a reasonable and
acceptable short time, then, the Engineer may allow the Contractor
extension or further extension of time, for completion, as he may decide,
subject to the following:
a. Without prejudice to any other right or remedy available to the
Engineer, recover by way of liquidated damages and not as penalty, a
sum equivalent to quarter of one percent (0.25%) of the contract value of
the works, for each week or part of a week the Contractor is in default.
b. If the delay relates only to a portion of the works with a separate and
earlier completion period, the contract value shall be restricted to the cost
of that portion of the works only.
c. The recovery on account of compensation for delay shall be limited to
5% of the contract value of the works, or the portion of the works, as the
case may be.
The recovery of such damages shall not relieve the Contractor from his
obligation to complete the work or from any other obligation and liability
under the contract.
49.7
49.8
If the Contractor
86
b)
Measure up whole or part of the work from which the Contractor has
been removed, and get it completed by another Contractor. The
manner and method in which such work is to be completed, shall be
87
Carry out the whole or part of the work from which the Contractor has
been removed, by the employment of the required labour, materials,
plants and equipment and other resources.
OF
CONTRACT
ON
EMPLOYER/ENGINEERS
Contractor. The amount to be recovered from the Contractor shall be decided by the
Engineer whose decision in this regard shall be final and binding. The Contractor shall
have to pay back unrecovered portion of advances made to him, together with accrued
interest thereon. In case, the Contractor defaults, the Engineer shall recover the
amounts from any payment due to the Contractor, or from the Performance Security or
by encashing the Bank Guarantees given by the Contractor for securing the advances
or for any other purpose. This is without prejudice to other remedies available to the
Employer/Engineer.
52.0 DEATH OF CONTRACTOR/ PARTNER
If the Contractor is an individual or a sole proprietary concern, and the individual or a
sole proprietor dies, or if the Contractor is a partnership concern and one of the
partners dies, in that case, unless the Employer/Engineer is satisfied that the legal
representative of the individual Contractor or of the sole proprietor, as the case may be,
or in the case of partnership firm, all surviving partners are capable of carrying out and
completing the contract, the Employer/Engineer shall be entitled to rescind the contract
as to its incomplete part. In that event, the Employer/Engineer shall not be liable to pay
any compensation to the legal heirs of the deceased Contractor and / or to the surviving
partners of the Contractors firm, on account of such cancellation of contract. The
Engineers decision as to whether the legal representatives of the deceased Contractor
or surviving partners of the Contractor are capable of carrying on and completing the
contract shall be final and binding on the parties. Provided further that the legal
representatives of the deceased Contractor or the surviving partners shall also not be
liable to pay any damages, alleged or actually suffered by the Employer/Engineer, in
respect of incomplete part of the contract. Any liability incurred by the deceased
Contractor, or by the deceased partner of the contracting firm, before his death, shall be
recovered from the legal representatives of the deceased Contractor or from the
surviving partners of the said contracting firm as the case may be.
53.0 EMPLOYMENT
OF
EMPLOYER/ENGINEER.
RETIRED
OFFICERS/ENGINEER
OF
89
The rates entered in the accepted Bill of Quantities of the Contract, shall be allinclusive and provide for works duly and properly completed in accordance with
terms and conditions of the Contract and processes as mentioned in
specifications and drawings (including revised drawings), relevant codes
whether mentioned or not in the nomenclature of the item in Bill of Quantities. All
rates quoted in the tender shall also deemed to include except specifically
provided otherwise in the Contract:
All materials, labour, tools and plant, stores, centering, shuttering, etc.
All watching, lighting, pumping and draining unless otherwise provided for.
All barriers and arrangements for safety of the property, utilities, public or
employees/workers during the execution of works.
The setting out of all works of construction, repair and up-keep of all centre
lines, benchmarks, reference pillars etc.
(ii)
(iii)
The Contractor shall bear the cost of all royalties, fees and other
payments in respect of patents, patents right and license(s) which may be
payable to patentee, licensee or other person or corporation and shall
obtain all necessary licenses/ permissions. In case of any breach
(whether willfully or inadvertently) by the Contractor of this provision, the
Contractor shall indemnify Employer, Engineer and their employees
against all claims, proceedings, damages, costs, charges, loss and
liability which they or any of them may sustain, incur or be put to by
reason or in consequence directly or indirectly of such breach and against
payment of any royalties, damages or other money which the
Employer/Engineer may have to make to any persons or pay in total to the
patent rights in respect of the users of any machine, instruments, process,
articles matter or thing constructed, manufactured, supplied or delivered
by the Contractor under this contract.
91
effected for payment to the contractor beyond (+)25% variation and upto
(+)50% variation.
ii.
In other works where it is generally possible to work out fairly accurate
estimate before award of the contract,2 % reduction in the accepted will be
effected beyond
(+)25% variation and upto (+)50% variation.
iii.
In case the variations in individual items is more than (+) 50%, the rate for
the increased quantity beyond (+)50% shall be negotiated between the
Engineer and the Contractor. Provided further that for the quantities
exceeding (=) 50% of each item of Bill of Quantities, the Engineer shall
have a right to get these executed from any other agency or by his own
labour, material and resources.
iv.
Decrease in quantity of individual items up to (-)50% due to site conditions
shall not form ground for revision of rates or claim on this account.
Beyond (-) 50% variation, rate shall be negotiated between the Engineer
and the Contractor.
c- The above limit of variation shall not be applicable for small value items and no
negotiations for rates for such items shall be done. Small value items shall be
those items whose sum, starting from the lowest value item, is upto 2% of the
original contract value and shall be decided between the Engineer and the
Contractor.
59.0
If any item of work not provided for in the accepted Bill of quantities and
required to be executed for completion of work, the Contractor on receipt
of instructions from the Engineer, shall be bound to carry out such items
of work at the rates to be decided as per sub-clause 59.2 and 59.3.
59.2
The rate for such extra items shall be derived from rate for similar items
available in the accepted Bill of Quantities.
59.3
In case rates can not be derived from the accepted Bill of Quantities, the
rate may be worked out on the following basis:
a.Cost of materials and consumables at current market rates, as actually
utilized in the final finished permanent work, including a reasonable
percentage for wastage and cost of loading, unloading and transportation.
b.Cost of labour required for the work.
c.Hire charges for plant and machinery, scaffolding, shuttering, forms, etc.
required to be used at the site of the work.
d.An amount of 10% of items (a), (b) and (c) above to allow for
Contractors overheads, profits and other contingencies.
59.4
In all cases where extra items of work are involved, for which there are no
rates in the accepted Bill of quantities, the Contractor shall give a notice
to the Engineer, of at least 7 days before the need for their execution
arises.
92
Such a notice shall not however be necessary if the Engineer has already
instructed in writing to take up such an item of work. To decide the rate,
the Contractor shall furnish detailed analysis of the rates on the lines
mentioned in sub-clause 59.2 and 59.3 above and attend a meeting with
Engineer to settle the rate as and when called for. The Contractor shall
be bound to furnish the requisite details and to attend the meeting.
59.5
59.6
The decision of the Engineer under this clause shall be final and binding.
Measurements
The Contractor shall be paid for the works at rates in the accepted Bill of
Quantities of the contract and extra items of work at rates determined
under clause 59.0 of these conditions. The measurement shall be taken
by the Engineer or his representative in the presence of the Contractor or
his authorised representative.
61.2
93
94
62.2 For materials brought to site by the Contractor, the Engineer may allow
(interest free) payment @ 75% cost of major materials brought to site for use in
the works as secured advance which will normally be paid along with next on
account payment. The payment of secured advance shall be made without any
bank guarantee but on written request of the Contractor alongwith indemnity
bond indemnifying Employer/Engineer against any loss and/or damages to the
materials for which secured advance is sought by the Contractor. The indemnity
bond shall be submitted on a non-judicial stamp paper of minimum value of Rs.
10/- duly notarized as per the format approved by the Engineer. The Contractor
should supply necessary vouchers etc. as evidence that payment has been made
by the Contractor for all the materials brought to site for which secured advance
is sought by the Contractor. Secured advance shall be paid at the rates derived
from the accepted rate of the item(s) for which the materials are to be consumed
and procurement rates, whichever is lower. The Engineers decision as to the
Quality, Quantity and value of the materials for which such secured advance is
payable will be final and binding on the Contractor. The recovery of secured
advance so made will be made from the subsequent on account bills to the
extent the materials are consumed in the work.
62.3 The Engineer may on specific request and authorization by the Contractor
in writing release payments directly to the Suppliers, sub-contractors or petty
contractors of the Contractor from the amount(s) certified, passed and due for
payment to the contractor.
62.4 In cases of default by the Contractor, the Engineer may without any notice
to the Contractor, release payments directly to the suppliers/sub-contractors
and/or petty contractors of the Contractor. All such payments shall be recovered
with interest @ 1.25% (including administrative charges) per month from the
payments due to the Contractor.
62.5 In exceptional circumstances, if the Contractor is not able to make prompt
payments to his suppliers affecting supplies of materials and progress of work,
the Engineer may (but shall not be obliged to) give assurance to the suppliers for
payments against supply of materials/consumables to the Contractor. In this
case, the Contractor shall give to the Engineer an undertaking in writing that cost
of such materials if not paid by him may be directly paid to his suppliers and
recovered from his dues. Such payments shall only be made after receipt of
materials at site and verification of the payments by the Contractor. The recovery
of such payments shall be made with interest @ 1.25% (including administrative
charges) per month from the next payment due to the Contractor. Total payments
so made on behalf of the contractor shall not exceed 05% of the Contract value
during the entire contract period.
62.6 The decision of the Engineer regarding exceptional circumstances and
payments to be made to the suppliers, sub-contractors and petty contractors
under the clause Nos. 62.3, 62.4 and 62.5 shall be final and binding on the
Contractor. Such payments shall also not relieve the Contractor from any of his
liabilities or obligations under the Contract.
62.7 No payment under the contract shall be made to the Contractor before
receipt of performance security. The Engineer shall also be entitled to withhold
payments under the above sub-clauses in case the Contractor fails to get himself
95
registered under sales tax/labour laws or fails to fulfill his obligation under the
contract.
63.0 FINAL MEASUREMENTS AND PAYMENTS
As soon as possible after completion of work, the Contractor shall submit the
final bill alongwith detailed measurements of work done, accountal of the
materials, plant and machinery issued by the Engineer and all other statements,
supporting documents required for finalisation of the bill. The final bill,
measurements and documents submitted by the Contractor shall be scrutinized
by the Engineer or his representative and in case the same are found not in
order, the Engineer shall direct the Contractor to re-submit the final bill alongwith
all details. On receipt of all requisite details and final bill from the Contractor, the
Engineer shall have the final measurements taken, recorded and signed jointly.
An accountal of any plant, equipment and materials issued by the Engineer to
the Contractor, shall also be prepared and signed jointly. Based on the final
measurements and materials and plant and equipment accountal statements, the
Engineer shall prepare the final bill.
The Contractor shall sign the Engineers copy of the Final Bill Account in token of
acceptance of the full and final value of the works performed under the contract,
and submit a No Claim Certificate on the prescribed proforma alongwith a list of
unsettled claims, if any. The Engineer shall then arrange to make payment
against the final bill. The Contractor shall not be entitled to make any claim
whatsoever against Engineer under or arising out of this contract, nor shall
Engineer entertain or consider any such claim, if made by the Contractor after he
shall have signed a No Claim certificate in favour of the Engineer. In case, the
Contractor submits a list of unsettled claims alongwith the No Claim Certificate,
he shall not be entitled to submit any additional claims other than those
submitted alongwith No Claim Certificate.
64.0 MODE OF PAYMENT AND TAX DEDUCTION AT SOURCE
64.1
MODE OF PAYMENT:
64.1.1
64.1.2
Income tax and Works tax shall be deducted from the payments
credited/released by Employer/Engineer to the Contractor against
execution of work as per law of the land. The deductions shall be made
as per prescribed rates prevalent from time to time unless a tax exemption
certificate is produced by the Contractor. Amount of tax deduction shall be
deposited with the concerned authorities and tax deduction certificate shall
be issued by Employer/Engineer. The Employer/Engineer shall deduct at
source taxes/duties under any other law/statute as may be applicable at
the time of making payments. The Contractor shall furnish to the Engineer
registration No. under works tax and PAN (for TDS), as applicable.
from any money due to the Contractor under the contract including the
Performance Security amount or from any money payable to the Contractor by
the Employer/Engineer, under any other contract.
66.0 CLEARANCE OF SITE ON COMPLETION
On completion of works, the Contractor shall clear and remove from site all
constructional plant, surplus materials, rubbish and temporary works of every
kind, and leave the whole of the site of work clean, tidy and in a workman like
condition to the satisfaction of the Engineer. This will be one of the pre-conditions
for making the final payment to the Contractor. Such clearance may be made by
the Engineer through any other agency at the expense of the Contractor in the
event of the Contractor's failure to comply with this provision within 7 days after
receiving notice to that effect from the Engineer.
67.0 POST PAYMENT AUDIT
It is an agreed term of the contract, that the Employer reserves to himself the
right to carry out a post payment audit or technical examination of the works, and
the final bill including all supporting vouchers, abstracts, etc. If as a result of such
examination, any over payment to the Contractor is discovered to have been
made in respect of any work done, the Contractor will be bound to refund the
same to the Engineer or may be adjusted against any dues of the Contractor. If
any under payment is discovered, the same shall be paid by the Engineer to the
Contractor. Such payments or recoveries, however, shall not carry any interest.
68.0 DEFECT LIABILITY CERTIFICATE
68.1
In the contract, the expression Defect Liability Period shall mean the
period of defect liability prescribed elsewhere in the contract, commencing
from the date of completion of the works, as certified by the Engineer.
The Contractor shall maintain, rectify and make good at his own cost any
defects/deficiencies, which may develop in the work or as notified by the
Engineer during Defect Liability Period. However, maintenance during
Defect Liability Period shall not include day to day upkeep, cleaning,
custody and security of the work.
68.2 The contract shall not be considered as completed, until a Defect Liability
Certificate has been issued by the Engineer stating that the works have
been completed and maintained to his satisfaction. Defect Liability
certificate shall be issued by the Engineer, upon expiry of Defect Liability
period or as soon thereafter as any works ordered during such period,
have been completed to the satisfaction of the Engineer.
68.3
98
Notwithstanding the issue of Defect Liability Certificate, the Contractor and the
Engineer shall remain liable for the fulfillment of any unfulfilled obligations under
the provision of the contract, prior to the issue of the Defect Liability Certificate,
and for the purpose of determination of the nature and extent of any such
obligation, the contract shall be deemed to remain in force between the parties
thereto.
70.0 PRODUCTION OF VOUCHERS
70.1
If, at any time during the currency of the contract, the performance of any
obligation (in whole or in part) by the Employer or the Contractor shall be
prevented or delayed by reason of any war, hostilities, invasion, acts of
public or foreign enemies, rebellion, revolution, insurrection, civil
commotion, sabotage, large scale arson, floods, earthquake or any other
act of God, large scale epidemics, nuclear accidents, any other
catastrophic unforeseeable circumstances, quarantine restrictions, any
statutory, rules, regulations, orders or
requisitions issued by a
Government department or competent authority(hereinafter referred to as
"event) then, provided notice of the happening of such an event is given
by either party to the other within 21 days of the occurrence thereof.
a.
b.
c.
d.
99
e.
Works that have already been measured shall be paid for by the Engineer
even if the same is subsequently destroyed or damaged as a result of the
event. The cost of rebuilding or replacing any work that has been
measured shall be borne by the Employer/Engineer.
f.
If the contract is fore-closed under this clause, the Contractor shall be paid
fully for the work done under the contract, but not for any defective work
or work done which has been destroyed or damaged before its
measurement. The Engineer shall have the option to take over any plant
and material lying at site, at rates provided for in the contract, failing that,
as per rates, which are determined to be fair and reasonable by the
Engineer.
71.2
Mutual Settlement
All such disputes or differences shall in the first place be referred by the
Contractor to the Employer in writing for resolving the same through mutual
discussions, negotiations, deliberation etc. associating representatives from both
the sides and concerted efforts shall be made for reaching amicable settlement
of disputes or differences.
72.2
Conciliation/Arbitration
72.1.1It is a term of this contract that Conciliation/Arbitration of disputes shall not
be commenced unless an attempt has first been made by the parties to settle
such disputes through mutual settlement.
72.1.2If the Contractor is not satisfied with the settlement by the Employer on any
matter in question, disputes or differences, the Contractor may refer to the
Managing Director of the Employer in writing to settle such disputes or
differences through Conciliation or Arbitration provided that the demand for
Conciliation or Arbitration shall specify the matters, which are in question or
subject of the disputes or differences as also the amount of claim, item wise.
Only such dispute(s) or difference(s) in respect of which the demand has been
made, together with counter claims of the Employer shall be referred to
Conciliator or Arbitrator as the case may be and other matters shall not be
included in the reference.
72.1.3Managing Director of the Employer may himself act as Sole
Conciliator/Sole Arbitrator or may at his option appoint another person as Sole
100
Conciliator or Sole Arbitrator, as the case may be. In case, Managing Director of
the Employer decides to appoint a Sole Conciliator/Sole Arbitrator, then a panel
of at least three names will be sent to the Contractor. Such persons may be
working/retired employees of the Employer who had not been connected with the
work. The Contractor shall suggest minimum two names out of this panel for
appointment of Sole Conciliator/ Sole Arbitrator. Managing Director of the
Employer will appoint Sole Conciliator/Sole Arbitrator out of the names agreed
by the Contractor.
72.1.4 In case, the Contractor opts for settlement of disputes through Conciliation
at first stage and if the efforts to resolve all or any of the disputes thorough
Conciliation fails, the Contractor may refer to the Managing Director of the
Employer for settlement of such disputes or differences through Arbitration. The
appointment of Sole Arbitrator shall be done by the Managing Director of the
Employer as per the procedure described above. No disputes or differences
shall be referred to Arbitration after expiry of 60 days from the date of notification
of failure of Conciliation.
72.1.5 The Conciliation and/or Arbitration proceedings shall be governed by the
provisions of the Indian Arbitration and Conciliation Act 1996 or any statutory
modification or re-enactment thereof and the rules made there under and for the
time being in force shall apply to the conciliation and arbitration proceedings
under this clause.
72.1.6 The language of proceedings, documents or communications shall be in
English and the award shall be made in English in writing.
72.1.7 The conciliation/arbitration proceedings shall be held at a place decided
by Conciliator/Arbitrator.
72.1.8 The fees and other charges of the Conciliator/Arbitrator shall be as per
the scales fixed by the Employer from time to time and shall be shared equally
between the Employer and the Contractor.
72.1.9 The minimum qualifications of Conciliator/ Arbitrator shall be graduate in
Engineering. He may be working or retired officer with a minimum of 20 years
service in Group-A of any Engineering Service of Central Govt. or an equivalent
service in a Central PSU. He should be clear from the vigilance angle and
should be a person with reputation of high technical ability and integrity. Also, he
should not have associated with the contract to which the dispute pertains.
72.2
72.3
No suspension of work
The Obligations of the Employer, the Engineer and the Contractor shall
not be altered by reasons of conciliation/arbitration being conducted
101
72.6
Exception:
For settlement of disputes with central PSUs, the procedure as per
existing orders of Permanent Machinery for Arbitration (PMA), Bureau of
Public Enterprises, Govt. of India shall be followed.
72.7
JURISDICTION OF COURTS:
Jurisdiction of courts for dispute resolution shall be New Delhi.
102
ANNEXURE-I
FORM OF AGREEMENT
(To be executed on requisite value of stamp Papers)
AGREEMENT
THIS AGREEMENT made on ____________ day of ________ (Month/year) between
Ircon International Limited, C-4, District Centre, Saket, New Delhi-110017, acting
through (Project Head and name/address of the Project)(hereinafter called the
Employer/Engineer)
of
the
one
part
and
__________________________________________________ (name and address of
the Contractor) (hereinafter called the Contractor) of the other part.
WHEREAS the Employer is desirous that certain works should be executed by the
Contractor
viz.
Contract
No.____________
___________________________________________ (hereinafter called the Works,
and has accepted a Bid by the Contractor for the execution and completion of such
Works and the remedying of any defects therein.
NOW THIS AGREEMENT WITNESSETH as follows:
1.In this Agreement, words and expressions shall have the same meaning as are
respectively assigned to them in the Conditions of Contract hereinafter referred to.
2.The following documents shall be deemed to form and be read and construed as part
of this Agreement:
a)Letter of Acceptance of Tender
b)Notice Inviting Tender
c)Instructions to the Tenderers
d)Appendix to Tender
e)Form of Bid
f)Special Conditions of the Contract
g)General Conditions of Contract
h)Additional Special Conditions of Contract
i)Technical Specifications
j)Relevant codes and Standards
k)Drawings
l)Bill of Quantities
103
Witness:
Witness:
1.
1.
2.
2.
104
ANNEXURE-II
PERFORMANCE BANK GURANTEE (UNCONDITIONAL)
To
IRCON International Limited,
Name & Address of Project.
[Acting through ______________________(Project Incharge) & Address of the Project]
WHEREAS __________________[name and address of contractor] (hereinafter called
the Contractor) has undertaken, in pursuance of Contract No.____________________
dated
__________
to
execute
____________________________________________________ [name of Contract
and brief description of Works] (hereinafter called the Contract.);
AND WHEREAS it has been stipulated by you in the said Contract that the contractor
shall furnish you with a Bank Guarantee by a scheduled bank for the sum specified
therein as security for compliance with his obligations in accordance with the Contract;
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee;
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you,
on behalf of the Contractor, up to a total of ______________________ [amount of
Guarantee], ____________________________________________ [amount in words],
such sum being payable in the types and proportions of currencies in which the Contract
Price is payable, and we undertake to pay you, upon your first written demand and
without cavil or argument, any sum or sums within the limits of _______________
[amount of Guarantee] as aforesaid without your needing to prove or to show grounds
or reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor
before presenting us with the demand.
We further agree that no change or addition to or other modification of the terms of the
Contract or of the Works to be performed there under or of any of the Contract
documents which may be made between you and the Contractor shall in any way
release us from any liability under this guarantee, and we hereby waive notice of any
such change, addition or modification.
This guarantee shall be valid upto _______ (a date 28 days from the date of completion
of the work).
SIGNATURE AND SEAL OF THE GUARANTOR
Name of Bank:
Address:
Date:
105
ANNEXURE-III
BANK GURANTEE FOR RELEASE OF 50% OF RETENTION MONEY
To
IRCON International Limited,
Name & Address of Project.
[Acting through ______________________(Project Incharge) & Address of the Project]
WHEREAS __________________[name and address of contractor*] (hereinafter called
the
Contractor)
has
undertaken,
in
pursuance
of
Contract
No.____________________________________ dated __________ to execute
________________________________________________________
[name
of
Contract and brief description of Works] (hereinafter called the Contract.);
AND WHEREAS it has been agreed by you in the said Contract that the Contractor has
option to get release 50% of the Retention Money against un-conditional Bank
Guarantee from a Scheduled Bank acceptable to you as security for compliance with
Contractors obligation in accordance with the contract (Sub clause _________).
AND WHEREAS the Contractor has opted to get released the 50% of the retention
money against an unconditional Bank Guarantee;
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you,
on behalf of the Contractor, up to a total of _______________ [amount of Guarantee],
___________________________ [amount in words], such sum being payable in the
types and proportions of currencies in which the Contract Price is payable, and we
undertake to pay you, upon your first written demand and without cavil or argument, any
sum or sums within the limits of __________ [amount of Guarantee] as aforesaid
without your needing to prove or to show grounds or reasons for your demand for the
sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor
before presenting us with the demand.
We further agree that no change or addition to or other modification of the terms of the
Contract or of the Works to be performed there under or of any of the Contract
documents which may be made between you and the Contractor shall in any way
release us from any liability under this guarantee, and we hereby waive notice of any
such change, addition or modification.
This guarantee shall be valid upto _______ (till the IRCON International Limited certifies
repayment of retention money in accordance with Sub-clause 8.5 of General Conditions
of Contract).
SIGNATURE AND SEAL OF THE GUARANTOR
Name of Bank:
Address:
106
SECTION - 8
TECHNICAL SPECIFICATION
107
IRS Rules Specifying the Loads for Design of Super-Structure and Sub-Structure
for Bridges (Bridge Rules)
RS Code of Practice for the Design of Sub-Structures and Foundations of
Bridges (Bridge Sub-Structures & Foundation Code) IRS Manual on the Design
and Construction of Well and Pile Foundations (Well and Pile Foundation Code)
Indian Railways Standard Code of Practice for the Design of Steel or Wrought
Iron Bridges Carrying Rail, Road or Pedestrian Traffic (Steel Bridge Code)
IRS Code of Practice for Metal Arc Welding in Structural Steel Bridges Carrying
Rail, Rail-cum-Road or Pedestrian Traffic (Welded Bridge Code)
IRS Specification for Fabrication and Erection of Steel Girder Bridges and
Locomotive Turn-Tables: Fabrication Specification (B1)
IRS Code of Practice for Plain, Reinforced & Prestressed Concrete for General
Bridge Construction (Concrete Bridge Code)
IRS Code of Practice for Fabrication and Erection of Steel Work of Microwave
Towers (Self Supporting Type)
IRS Code of Practice for the Structural Design of Microwave Towers of SelfSupporting Type (Self Supporting Microwave Tower Code)
Indian Railways Schedule of dimensions for Broad Gauge. -2005
Indian Railways Bridge Manual, 1998.
Indian Railways P. Way Manual. 2004
Indian Railways Works Manual. 2000
M-3: Class I, II, III and IV steel forgings, blooms for forging and billets for
rerolling
M-28: Classification, Testing and approval of metal-arc welding electrodes for
use on Indian Railways.
M-39: Classification, testing and approval of submerged arc welding wire flux
combination
M-41: Corrosion resistance steel
M-42: High strength low alloy structural steel with enhanced corrosion resistance
M-43: High strength low alloy structural steel rivet bars with enhance corrosion
resistance.
P-31: Zinc chromate red oxide primer
M&C/PCN/102/96: Epoxy zinc phosphate primer
M&C/PCN/103/86: Epoxy micaceous iron oxide
M&C/PCN/109/88: Polyurethane red oxide
M&C/PCN/110/88: Polyurethane aluminium
M&C/PCN/111/88: High build epoxy paint
RDSO/M&C/Specification: Classification, testing and approval of CO2 welding
filler wires for use on Indian Railways
108
IRC-5: Standard specifications and Code of practice for Road Bridges Section
I General features of design
IRC-6: Standard specifications and Code of practice for Road Bridges Section
II- Loads & stresses.
IRC-21: Standard specifications and Code of practice for Road Bridges- Sections
III- Cement concrete (Plain & reinforced)
IRC-24: Standard specifications and Code of Practice for Road Bridge Section
V- Steel Road Bridges.
IRC- 83: Bearings for bridges.
IRC-78: Road Bridges.
IRC-87: Design and erection of false work for road bridges.
109
33) IS: 875 (all 5 parts) design loads (other than earthquakes) for buildings and
structures.
34)IS: 2720 (all 41 parts)- Method of tests for soils.
35)IS: 800 General constructions in steel.
36)IS: 786- Conversion factors and conversion tables.
37)IS: 1024 Welding in bridges and structures subject to dynamic loading.
38)IS: 1261 - Seam welding in mild steel.
39)IS: 1367 (all 20 parts) - threaded steel fasteners.
40)IS: 6639- Hexagonal bolts for steel structures.
41)IS: 104 Ready mixed paint, brushing, zinc chrome, priming.
42)IS: 2074- Ready mixed paint, air drying, red oxide-zinc chrome, priming.
43)IS: 1852- Rolling and cutting tolerances for hot rolled steel products.
44)IS: 1270- Metric steel tape measure.
45)IS: 9595- Metal Arc Welding.
46)IS: 487- Brush, paint and varnish.
47)IS: 1030 Carbon steel castings for general engineering purposes.
48)IS: 3400 (all 22 parts) - Methods of tests for vulcanized rubbers.
49)IS: 1915- Steel bridge code
50)IS: 1893- Earthquake resistant design of structures.
51)IS: 3502- Steel Chequered plates.
52)IS: 3085- Method of test for permeability of cement mortar and concrete.
53)IS: 7320 Concrete slump test apparatus.
54)IS: 5515- Compaction factor apparatus.
55)IS: 6586- Metal spraying for protection of iron steel.
56)IS: 5666- Etch primer.
57)IS: 3955- Design and construction of well foundations.
58)SP 6, 7, 16, 21, 22, 23, 24, 34, 36, 52, 60.
59)IS: 2911- Design and construction of pile foundation.
60)IS; 7205- Safety code for erection of structural steel work.
61)IS: 8629- Protection of iron and steel structures form atmospheric corrosion.
62)IS: 5624- Foundation bolts.
63)IS: 7215- Tolerances for fabrication of steel structures.
64)IS: 8112- 43 Grade OPC.
65)IS: 4326- Earthquake resistant design and construction of buildings.
66)IS: 13920- Ductile detailing of reinforced concrete structures subjected to seismic
forces.
67)IS: 34 White lead for paints.
68)IS: 887 Animal tallow.
69)IS: 816- Metal arc welding for general construction in mild steel.
70)IS: 819- Resistance spot welding for light assemblies in mild steel
71)IS: 1024 Welding in bridges and structures subject to dynamic loading.
72)IS: 1261- Seam welding in mild steel.
73)IS: 1323- Oxy-acetylene welding for structural work in mild steel.
74)IS: 4081- Safety code for blasting and related drilling operations.
75)IS: 3764- Safety code for excavation work.
76)IS: 7293- Safety code for working with construction machinery.
77)IS: 817- Training and testing of metal arc welders.
78)IS: 1200 (all relevant parts)- Method of measurement of building and civil
engineering works.
79)IS: 2132- Thin walled tube sampling of soils
80)IS 2131- Standard penetration test for soils.
81)IS: 1892- subsurface investigations for foundations.
110
1.4 Miscellaneous:
i.
UIC-772R: Bearings of rail bridges.
ii.
BS-5400 (all parts)
iii.
BS-1449, 3484, 1134, 5296
iv.
ASTM/AASHTO
Note: The books of reference shall also include further references mentioned in
above-mentioned books of references. All the books, references and
codes shall be of latest edition with up to date correction slips.
2.0 DEFINITION:
Definition of the various terminology used herewith are the same as given in IRS
Fabrication Specification (B1) & IRS Welded Bridge Code
a)MATERIAL
2.1 Steel: IS: 2062 Grade "A" as rolled semi-killed or killed shall be used for foot-overbridges and other structures subjected to non-critical loading.IS: 2062 Grade "B" fully
killed and normalized/controlled-cooled, where service temperature does not fall below
00C, shall be used for welded/rivetted girders subjected to railway loading. Plates less
than 12 mm thick need not be normalized/controlled-cooled. IS: 2062 Grade C fully
killed and normalized/controlled-cooled, ensuring impact properties at (-) 200 C or (-) 400
C, shall be used for sub-zero temperature areas for welded/rivetted girders subjected to
railway loading. Plates less than 12mm thick need not be normalized/controlled-cooled.
High tensile steel shall comply in all respects with the requirement of IS: 2062, Fe: 540
or Fe: 570(both Copper bearing quality) according to the welded or rivetted work
respectively. (In the 2006 version of IS: 2062, provisions of IS: 1077 & IS: 8500 have
been included) For superior and enhanced corrosion resistance for sections, plates and
bars for welded, rivetted or bolted construction, the material shall comply with the
requirement of IRS: M-42, Grade-I or Grade-II for rivetted/bolted or welded work
respectively. Steel, which is to be cold pressed, shall comply with the requirements of
IS: 2002.Steel for bolts shall conform to property class 4.6 or 6.6 as specified in IS: 1367
accordingly, as the structural steel specification is for mild steel or high tensile steel.
Steel for drifts shall be in accordance with IS: 1875 for forged quality steel or IS: 7283
for hot rolled bars. Steel for rivets shall comply with the requirement of IS: 1148 for hot
rolled rivet bars for general structural purposes and IS: 1149 for high tensile steel rivet
bars for high strength structural purposes. For high strength low alloy structural steel
rivet bars with enhanced corrosion resistance for use in bridges, steel shall comply
with the requirement of IRS:M-43.
The dimensions of all rolled sections must agree with the contract drawings or as
agreed to between the Purchaser and the Contractor.
The rolling and cutting tolerances shall be in accordance with IS: 1852 or as agreed to
between the Purchaser/Engineer and the Contractor if closer tolerances are desired
they shall be shown in the drawing.
All the steel sections used in the fabrication must have mill test certificate clearly
indicating the specification to which the steel conforms and whether steel is killed and
normalized. All the cast mark numbers/ heat mark numbers shall be recorded alongwith the number of plates in a register as soon as the plates are received in the
111
workshop. Whenever the steel is received without any test certificate, a sample test
piece from plate of each cast mark number is to be cut and sent for testing. Only when it
is established that the plates are of required specification, these shall be processed for
cutting.
Use of steel of any quality other than those mentioned above would require the prior
approval of the Engineer.
NOTE: Rolled sections like angles, channels, I-sections etc., conforming to IS: 2062
Grade "A", may be used in structures till such time rolled sections conforming to IS:
2062 Grade B/C are not available in the market.
2.2 Steel castings:
Steel casting shall comply with IS: 1030 for normal temperature zone and to IS: 4899 for
use at low temperature zone.
2.3 Bronze plates:Bronze plates shall be of phosphor bronze complying with IS: 1458
Class I.
2.4 STACKING OF MATERIALS:On receipt of materials at the bridge yard, the same
shall be carefully unloaded, examined for defects, checked, sorted and stacked
securely on a level bed out of danger from flood or tide and out of contact with water or
ground moisture. All material shall be available for inspection by the Engineer or
Inspecting Officer. Materials shall be verified with the markings shown on the marking
plan of part list, which shall be supplied by the manufacturers or the Engineer.Any
material found damaged during transit or while unloading should be stacked separately
and damaged portions shall be indicated by paint with distinctive colour. All such
materials shall be dealt with under the orders of the Engineer without delay. If any
component after receipt at site, has in the opinion of the Engineer or Purchaser, been
damaged in transit, such component shall be replaced or repaired to the satisfaction of
the Engineer or Purchaser free of cost.All such damaged material shall be dealt with as
per the orders of the Engineer. Badly damaged portions may require replacement.
Slightly distorted parts may be straightened by gradual pressure without heat or
annealing. Badly distorted or broken parts must be dealt with as the case demands and
as directed by the Engineer.
Where the work has been passed in the manufacturers works as strictly
interchangeable, all members bearing the same marks can be stacked together without
reference to any particular span.
The Contractor shall unload the material promptly on delivery; otherwise he/she shall be
responsible for demurrage charges.
On receipt of rolled steel at workshop or fabrication yard they shall be carefully
unloaded and stacked properly to avoid bending, twisting, corrosion etc.
3.0 TESTING OF THE MATERIALS:
In addition to the test certificate obtained from the steel producers/suppliers/dealers, for
conformity sake, all materials/consumables, i.e. steel, rivets, welding electrodes, paints,
etc shall be got tested from the NABL approved labs/recognized labs. Proper record of
all such test results shall be maintained. A copy of the same be given to client/IRCON as
well. Test result of the supplier and that of the lab should match with each other. In case
of major difference, mater has to be investigated. Decision of the IRCON shall be final
in that regard.
112
Rolled steel shall also be ultrasonically tested by the reputed firm. Only ultrasonically
tested steel shall be used for fabrication work. Record of ultrasonically tested steel shall
be maintained separately.
All the testing work shall be done in accordance to the provisions of the relevant codes.
Regarding radiographic testing/x-ray testing of the welded joints, matter shall be
finalized in consultation with the inspecting authority, i.e. RDSO. Agreed to procedures
shall be followed. Necessary arrangement for that has to be got done by the tenderer at
their own cost.
All testing work shall be got done by the contractor at their own cost. Nothing extra shall
be paid. Tenderers should quote their rate accordingly.
4.0 MAINTENANCE OF RECORDS BY FABRICATORS
The records of fabrication shall be maintained in the registers as per the formats given
in the Appendix I of B-1 Specification. For ready reference, extract of the same has
been given in the end of this specification as well.
5.0 FABRICATION / MANUFACTURE
The whole work shall be representative of the highest class of workmanship. The
greatest accuracy shall be observed in the design, manufacture and erection of every
part of the work to ensure that all parts will fit accurately together on erection. For
manufacture of the components of all spans to be made strictly interchangeable as
specified in interchangeability criteria given in this specification on the subsequent
pages, approved set of same jigs and assembly fixtures shall be used. The tolerances
in manufacture shall be in accordance with as shown in Appendix III of IRS B-1-2001
Specification. For ready reference, the same are also produced in the end of this
technical specification (Quality control portion of this specification).
The Contractor shall state which of the following alternative methods of manufacture
he/she intends to adopt.
a). The whole of work to be erected complete and pieces marked to place.
b). All spans to be made strictly as per the interchangeable criteria described
subsequently of this technical specification
The Contractor shall maintain a master steel tape of approved make for which he/she
has obtained a certificate of accuracy from any National Test House or Government
recognized institutions, competent to do so.
6.0 TEMPLATES: The templates through out the work shall be of steel. The template
shall be used for marking of cutting material and as well as profile machining for
girders of railway loading. Templates shall be used for marking of drilling holes in
steel structures other than girder of railway loadings. In case where actual materials
from a bridge have been used as templates for drilling similar pieces the Inspecting
Officer will decide whether they are fit to be used as part of the finished structure.
6.1
ADDITIONAL DETAILS:
The contractor shall supply and provide templates at his own cost. No separate
payment shall be made for this and accepted rates shall be deemed to
113
include this aspect. The templates used for the work shall be of steel and of
tested quality.
6.2
(i)
(ii)
(iii)
(iv)
(v)
Template Shop:
Fully covered template shop consisting of uninterrupted steel or concrete floor as
approved having true and correct level covering adequate area shall be provided
by the contractor.
Camber layout shall be drawn to full scale from end of girder to half span. This
camber layout once approved shall be used for fabrication of master gusset profiles and end profile of each member. It shall be used for working out the actual
lengths of each member and checked to conform to the calculated length.
Master gussets at every panel joint of top chord, bottom chord and middle web
panel shall be marked accurately on camber layout drawn on template floor.
All precautions shall be taken while drawing camber layout for correct setting of
angle of intersection of chord and web member and great accuracy shall be ensured while transferring the same on master gusset. While marking centre point
of field rivet holes on master gusset, if there is symmetry of holes on vertical axis,
marking shall be made only on half the master gusset across vertical axis, and
holes drilled by inscribing each hole. Subsequently remaining half portion shall
be drilled through gusset using the same half portion master gusset. This will
help realize symmetry of holes in gusset and fairing of field rivet hole during girder assembly.
Camber layout and fabrication of Master gusset at every panel joint requires
highly skilled and trained staff experienced in accurate fabrication of large girders, drilling jigs and fixtures. At least one jig shall be required for each component. Each jig shall be numbered and a record kept in register for identification.
compression members the face shall be machined so that the faces are at right angle to
the axis of the members and the joint when made, will be in close contact throughout. At
the discretion of the Inspecting Officer, a tolerance of 0.4mm may be permitted at
isolated places on the butting line.
9.0 FLAME CUTTING
Flame cutting by mechanically controlled torch/torches shall be accepted both in the
case of mild steel and high tensile steelwork. Provided the edge as given by the torch is
reasonably clean and straight, plates may be cut to shape and beams and other
sections cut to length with a gas-cutting torch, preferably oxyacetylene gas should be
used. All flame cut edges shall be ground to obtain reasonably clean square and true
edges. Draglines produced by flame cut should be removed. Unless machining has
been specifically provided for, special care is to be taken to ensure that ends of all
plates and members are reasonably in close contact and the faces are at right angles to
the axis of the members and joints, when made, are also reasonably in close contact.
Use of multi-head flame cutting machine having multiple oxy acetylene torches is
desirable for higher productivity and reducing the distortion due to cutting operation.
Plasma-arc cutting method can also be employed. This process offers less heat input
causing less distortion.
10.0 DRILLING AND SUB-PUNCHING
All holes shall be drilled but the Contractor may, if he/she so prefers sub-punch them to
a diameter 6mm less than that of finished holes, e.g. a punched hole which is to be
drilled out to 25mm in diameter shall not exceed 19mm in diameter at the die end. When
the rivet holes are to be sub-punched, they shall be marked with a centre punch and
made with a nipple punch or preferably, shall be punched in a machine in which the
position of the hole is automatically regulated. The punching shall be so accurate that
when the work has been put together before drilling, a gauge 1.5mm less in diameter
than the size of the punched holes can be passed easily through all the holes. Holes for
countersunk heads of rivets, bolts or screws shall be drilled to the correct profile so as to
keep the heads flush with the surface Holes for countersunk heads of rivets, bolts or
screws shall be drilled to the correct profile so as to keep the heads flush with the
surface. No sub-punching shall be allowed in the main truss members of open-web
girders. Holes for turned bolts should be 1mm under drilled in shop and should be
reamed at site to suit the diameter of turned bolt.
Where the number of thicknesses to be rivetted exceeds three or the total thickness is
90mm or more, the rivet holes, unless they have been drilled through steel-bushed jigs,
shall be drilled out in place 3mm all round, after assembling. In such cases the work
shall be thoroughly bolted together.
The steel bushes shall be case hardened by an approved process and checked for
diameter after the heat-treatment. The bores of bushes shall initially have a tolerance of
-0mm, 0.1mm. The tolerance shall be checked from time to time and when the bores
exceed a tolerance of, -0mm, +0.4mm, the bushes shall be rejected. For this purpose,
go and no-go gauges are to be used. Tolerances for checking jigs from master plates
shall be +0mm -0.13mm.
The work shall be taken apart after drilling and all burrs left by the drill and the sharp
edges of all the rivet holes completely removed.
115
116
117
Riveting shall not be started until such time as the Engineer has personally satisfied
himself that the alignment of the girders is correct, the verticals plumb laterally, the
camber according to that shown on the camber diagram with camber jacks screwed
tight, all the joints and cover plates well up, service bolts tight and field rivet holes
coinciding. Special care should be taken that service bolts are frequently re-tightened
as the riveting proceeds.
All field rivets shall be tested as directed by the Engineer.
Where practicable all rivetting shall be done by pneumatic or hydraulic rivetting
machine. The working pressure to be employed when using pneumatic or hydraulic
tools shall be approved by the Engineer. Hand rivetting shall only be done when
sanctioned by the Engineer. In such cases, means shall be adopted to ensure the rivets
being used in their entire -only to give the correct form of head. When all the rivets of
joints have been finally passed, they shall be painted as under. One coat of ready
mixed zinc chrome primer to IS: 104 followed by one coat of ready mixed paint red
oxide zinc chrome primer to IS: 2074
Finishing coat as per painting schedule given under Oiling, Painting and Metallising of
this technical specification. For further details on the rivetting, Indian Railways Bridge
Manual can be referred to.
14.0 FIELD RIVETS, BOLTS, NUTS AND SERVICE ACCESSORIES
Fabricators shall arrange rivets, bolts, nuts, drifts and service accessories, etc. for all
those works required as a part of shop fabrication. For field erection and assembly
work, it shall be the responsibility of launching/ erection contractor to arrange such
type of fittings.
15.0 SMITHED WORK
All joggles shall be performed by pressure. Craned sections or knees can be formed by
forging or by gas cutting and welding by any approved electric arc process. Any
bending, forging, cutting or welding shall be carried out in such a manner as not to
impair the strength in the metal. Forging shall be annealed as indicated in the drawing.
If drop forging through dies is resorted to, excessive forging in one operation shall be
avoided. Where necessary, a series of intermediate stage dies shall be manufactured
and used.
16.0 WELDING
Welding of the bridge girders shall be done under strict supervision of the engineer.
Approved procedures shall be followed. A brief of the same are given herewith:
17.0 DRAWINGS AND PROCEDURE SHEETS
The symbols for welding used on the fabrication drawings and procedure sheets shall
be in accordance with IS: 813. If other symbols are used, a complete explanation of
their meaning shall be given.
The fabrication drawings and/or welding procedure sheets prepared for direction of the
welding organisation shall include the following information:
a) Specification of the parent metal, and electrodes and/or wire-flux combinations.
b) Locations, sizes, actual lengths and details, i.e. form of joint, angle between fusion
faces, gap between parts, etc., of all welds.
118
119
120
Thickness of thicker
part
6 mm up to
including 20 mm
Minimum
size
and
5 mm.
Over 20 mm up to and
including 32 mm
6 mm.
Over 32 mm up to and
including 50 mm
8 mm.
Minimum
size
3 mm
and
4 mm
6 mm
8 mm
10 mm
12 mm
Over 150 mm
16 mm
Notes:
i- When the minimum size of the first run of fillet weld and /or minimum size of
the fillet weld as given in Table-1 and Table-2 is greater than the thickness of
the thinner part, the minimum size of the weld shall be equal to the thickness
of the thinner part. The thicker part shall be adequately pre-heated to prevent
cracking of the weld.
ii- Where the thicker part is more than 50 mm in case of steel to IS: 2062
special precautions like pre-heating as per IS: 9595 shall be taken to ensure
weld soundness.
121
122
Where a fillet welds is applied to the rounded toe of a rolled section, the specified size
of the weld shall generally not exceed 3/4 of the thickness of the section at the toe (see
Fig. 14 of SKETCHES part of this specification).
Where a fillet weld equal in size to the thickness of the section at the toe of a rolled
section or at the square edge of a plate is required from design considerations and is
specially designated in the drawing, the toe or edge shall be specially built up with weld
metal in such a manner as to ensure full throat thickness, full fusion area and no injury
to the parent metal (see Fig. 15 & 16 of SKETCHES part of this specification).
24.6End fillets:
When end fillets are used alone, each fillet shall be returned as a side fillet for a
minimum length equal to twice the size of the weld, and this returned length shall be
disregarded in calculating the strength of the joint.
24.7 Fillet welds in slots or holes:
1.0 When welding inside a slot or a hole, in a plate or other part, in order to join the
same to an underlying part, fillet welding may be used along the wall or walls of the slot
or the hole, but the later shall not be filled with weld metal or partially filled in such a
manner as to form a direct weld metal connection between opposite wall.
The dimensions of the slot or hole shall comply with the following limits in terms of the
thickness of the steel part in which the slot or hole is formed.
2.0 The width or diameter to be not less than three times the thickness or 25 mm
whichever is greater.
3.0 Corners at the enclosed ends of slots to be rounded with a radius not less than 1.5
times the thickness or 12 mm whichever is greater.
4.0 The distance between the edge of the part and edge of the slot or hole or between
adjacent slots and/ or holes not to be less than twice the thickness when measured
along the direction of stress and five times the thickness when measured normal to the
direction of stress.26.8 End Returns:
Fillet welds terminating at the ends or sides of parts or members shall be returned
continuously around the corner for a distance of not less than twice the size of the weld.
This provision shall apply particularly to side and end fillet welds joining brackets, beam
seating and similar attachments at the tension side of such connections.
25.0 PREPARATION OF JOINT FACES
Preparation of joint faces shall be done as per IS: 9595.
25.1 Fusion faces:
The preparation of fusion faces, angle of preparation root radius and root face shall be
as specified in IS: 9595 and IS: 4353. Where the gap between the root faces of a butt
joint is excessive, the gap shall not be bridged since this procedure often leads to
cracking. The fusion faces of the joint shall be built-up with weld metal to give the
appropriate gap before the weld proper is commenced.
123
The preparation of fusion faces, angle of bevel, root radius and root face shall be such
that the limits of accuracy required by the appropriate application standard can be
achieved. When however, no appropriate application standard exists and this standard
is itself to be used, it is recommended that, for manual welding, the tolerances on limits
of gap and root face should be 1 mm on the specified dimensions for material up to
and including 12 mm thick and 2 mm for material over 12 mm thick. The tolerance on
the included angle between the fusion faces of a V preparation is recommended to be
5 degree and for U and J preparations + 10 degree. For an automatic process, closer
limits are necessary and particular requirements depend on the characteristics of the
process.
It shall be ensured, if necessary, by suitable non-destructive tests that the fusion faces
and adjacent surfaces shall be free from cracks, notches or other irregularities which
might be the cause of defects or would interfere with the deposition of the weld.
Fusion faces and the surrounding surfaces shall be free from heavy scale, moisture, oil,
paint or any other substance which might affect the quality of the weld or impede the
progress of welding. Certain proprietary protective coatings are specially formulated
with the intention that they should not interfere with welding. The use of such coatings is
not excluded by the requirements of this clause but shall be demonstrated by means of
specimen welds that the coating complies with the above requirements.
26.0 ASSEMBLY FOR WELDING:
Parts to be welded shall be assembled such that the joints are easily accessible and
visible to the operator.
Jigs and manipulators shall be used, where practicable, so that the welding can be
carried out in the most suitable position. Jigs shall maintain the alignment with the
minimum restraint so as to reduce the possibility of locked in-stress.
27.0 SEQUENCE OF WELDING AND WELD PASS FOR COMPOSITE GIRDERS,
SHEAR CONNECTORS ETC:
For fabrication of welded composite girders, channel shear connectors shall be welded
on top flange plate prior to assembly of I-section. This facilitates correction of any
distortion of flange plate developed during the welding of channel shear connectors.
In making a typical I-section four fillet welds are to be made. The welding sequence to
be followed is indicated by number 1 to 4 as shown in the Fig. No.-23.
Whenever a square butt weld in a 10 or 12mm thick plate is required to be made, the
sequence to be adopted is shown in Fig. No.-23.
28.0 WELDING IN SOLID WEB GIRDERS
Flange plates:
Each flange shall, as far as possible, particularly in dynamically loaded structures,
consist of a single section rather than of two or more sections super-imposed. The
single section may comprise a series of sections laid end to end and effectively welded
at their junctions.
If the use of curtailed flange plates can not be avoided the end of the plate shall be
tapered in plane to a rounded end and welded continuously round the end.
124
In dynamically loaded structures, flange plates laid end to end shall be joined by butt
welds, and welded cover plates shall not be used. Joints in flange plates shall be butt
welded and dressed flush before assembling.
Where the flange consists of more than one section, the butt joints shall be staggered.
Welded cover plates, where used in structures not subjected to dynamic loading, shall
have enough welds on either side to develop the load 5% more than that of the element
spliced.
The flange plate, welded directly to the web plate, shall not be more than 50 mm thick
when steel conforms to IS: 2062.
Web plates:
Splices in the webs of plate girders and rolled sections used, as beams shall be made
by butt welds dressed flush on all faces, in the case of dynamically loaded structures. In
the case of structures not subjected to dynamic loading, splice plates may be used
independently and not to reinforce a butt-welded splice.
Intermediate stiffeners:
Where intermediate stiffeners are connected to the web by intermittent fillet welds
placed in pairs, one weld on either side of the stiffeners, the effective length of each
weld shall be not less than four times the thickness of the stiffeners, subject to the
provisions of clause 6.7.
Where staggered intermittent fillet welds are used, the effective length of each weld
shall be not less than 10 times the thickness of the stiffener, subject to the provisions of
clause 6.7.
Fillet welds placed on one side only of the stiffener shall not be used.
Intermediate stiffeners carrying cross bracings or diaphragms shall not be connected to
the web by intermittent fillet welds.
Intermediate stiffeners shall be located away from web splices.
29.0 SAFETY PRECAUTIONS
Provisions of IS: 818, IS: 1179 and IS: 3016 shall generally apply for safety and health
requirements during welding operations.
30.0 APPROVAL AND TESTING OF WELDING PROCEDURES
Welding procedure test shall be carried out in accordance with IS: 7307(Part-I) to
demonstrate, by means of a specimen weld of adequate length on a steel
representative of that to be used, so as to confirm that satisfactory weld is achievable
with the welding procedure to be used for fabrication.
Provisions of IS: 9595 and IS: 4353, shall generally be followed, as applicable, for
welding procedure, details of workmanship, correction of weld faults, peening, painting,
etc. In case any of the provisions contained therein contravene the provisions made on
this code, the latter shall be followed.
125
In addition to the provisions of IS: 4353 the Inspector may, where deemed necessary,
require a sample joint having the same cross-section as the joint to be used in
construction and a length of at least 300 mm to be welded with the wire, flux current, arc
voltage and speed of travel that are proposed to be used and a macroetched cross
section of the welded joint prepared as a demonstration that the specified requirements
will be met, when the welding current, arc voltage and speed of travel are established
by a test made in accordance with requirements of this clause, they shall be kept within
the following limits of variations
Welding current
10%
Arc Voltage
7%
Speed of travel
15%
31.0 APPROVAL AND TESTING OF WELDERS:
The welders shall be trained in accordance with IS: 817. The welders shall be
subjected to appropriate qualifying tests specified in IS: 7310 (Pt-I).
32.0 WELDING PROCESSES AND PROCEDURES:
Welding work shall be given to a contractor who does produce satisfactory evidence of
his ability to handle the work in a competent manner. The contractor shall also prove
the ability of the operator/Welders employed by him to produce welds of the required
strength. The contractor shall employ a competent welding supervisor to ensure that
quality of materials and the standard of workmanship comply with the requirements laid
down in this code.
The sizes and length of welds shall not be less than those specified in the drawings nor
shall they be substantially in excess of the requirements without prior approval of the
Engineer. The location of welds shall not be changed without prior approval of the
Engineer. Welds shall preferably be made in flat position.
In case of welds in structures subjected to dynamic loading, adequate means of
identification, either by identification stamp or other records shall be provided to enable
each weld to be traced to the welding operator by whom it was made. During the entire
welding of cooling cycle, the joints shall not be subjected to any external forces or
shocks.
Freedom of movement of one member of a joint shall be allowed wherever possible.
No butt joint shall be welded without allowing one component, freedom of movement of
the order of 1.5 mm.In making welds under conditions of severe external shrinkage
restraint, the welding shall be carried out with electrodes having type 6 covering as per
IRS:M-28 Specification. In case of welding using direct current, earthing on the work
piece to be welded shall be connected carefully at more than one location with a view to
avoid Arc Blow during welding.
All welds should be done by submerged arc welding process either fully automatic or
semi-automatic. Carbon-dioxide (CO2) welding or manual metal arc welding may be
done only for welds of very short runs or of minor importance or where access of the
locations of weld does not permit automatic or semi-automatic welding.
Neither the depth of fusion nor the maximum width in the cross section of weld metal
deposited in each weld pass shall exceed the width of the face of the weld pass.
126
All welds should be done by submerged-arc welding process either fully automatic or
semi-automatic. Carbon di oxide welding or manual metal-arc welding may be done
only for welds of very short runs or of minor importance or where access of the
locations of weld do not permit automatic or semi-automatic welding.
Except for special types of edge preparation, such as single and double U single and
double J the fusion edges of all the plates which are to be joined by welding may be
prepared by using mechanically controlled automatic flame cutting equipment and then
ground to a smooth finish. Special edge preparation should be made by machining or
gouging.
The welding procedure shall be such as to avoid distortion and minimise residual
shrinkage stresses. Properly designed jigs should be used for assembly. The welding
techniques and sequence, quality, size of electrodes, voltage and current required shall
be as prescribed by manufacturers of the material and welding equipment. The
Contractor should submit full details of welding procedure in proforma given at
Appendix V of IRS B-1-2001 specification, copy of which is available in Maintenance of
Records of this specification.
Site welding should not be undertaken except in special circumstances with the
approval of the Engineer. Site welding should be confined to connections having low
stresses, secondary members, bracings etc.
Manual metal arc welding may be done taking adequate precautions as per IS: 9595
and under strict supervision.
33.0 SEQUENCE OF WELDING:
The sequence of welding shall be such that when possible the members, which offer
the greatest resistance to compression, are welded first.
The welding in the thinnest element of a section (usually the web in case of beams)
shall be done prior to the welding of the thicker elements (usually the flanges in case of
beams).
In making butt welded joints in rolled shapes, the sequence and procedure of welding
shall take into account unequal amount of expansion or contraction in elements being
welded.
Splices in each component part of a solid web girder or built-up member shall be made
before such component part is welded to other component part of the member.
34.0 POSITION OF WELDING:
For fabrication of steel bridge girders the following positions of welding shall be
adopted.
I)
Flat and horizontal position for Submerged Arc Welding (SAW) and
II)
127
All butt welds by the submerged arc process shall be made in the flat position. Fillet
welds may be made in either flat or horizontal-vertical position. The size of the single
pass fillet welds made in the horizontal-vertical position shall not exceed 8 mm.
35.0 TACK WELDS:
Tack welds shall be not less than the throat thickness or leg length of the root run to be
used in the joint. The length of the tack weld shall not be less than four times the
thickness of the thicker part or 50 mm whichever is the smaller
Where a tack weld is incorporated in a welded joint, the shape, size and quality shall
be suitable for incorporation in the finished weld and it shall be free from all cracks and
other welding defects. Tack welds, which are prone to cracking, shall be cut out and
rewelded.
Tack welds shall not be made at extreme ends of joints.
36.0 INTER-RUN CLEANING:
Each run of weld bead shall be thoroughly cleaned to remove particles of slag, spatters,
etc. before the subsequent bead is super-imposed during multi-pass welding. Similarly,
each layer of weld should be thoroughly cleaned of slag, spatters, etc, before depositing
subsequent layers of weld with particular reference to thorough cleaning of toes of the
welds. Visible defects, such as cracks, cavities and other deposition faults, if any, shall
be removed to sound metal before depositing subsequent run or layer of weld.
37.0 STRAY ARCING ON WORK:
Stray arcing shall be avoided as this can leave local hard spots or cracking which are to
be removed by mechanical means and be checked by inspection depending upon the
application.
38.0 INSPECTION AND TESTING OF WELDED JOINTS:
The inspection of bridge girders shall be done by RDSO. The Inspector designated by
the purchaser shall ascertain that fabrication by welding is performed in accordance
with the requirements of this code. Inspection of welds shall also be carried out in
accordance with this Code. For the provisions, which are not incorporated in this Code,
IS: 822 Code of procedure for inspection of welds shall be followed.
He shall be furnished with complete detailed drawings showing the size, length, type
and location of all welds, which are required to be made. He shall be notified in
advance of the start of any welding operations. He shall have free access to the work
being done at all reasonable times by the contractor and facilities shall be provided so
that during the course of welding he may be able to inspect any layer of weld metal. He
shall be at liberty to reject any material that does not conform to the provisions of this
code and to require any defective welds to be removed and re-welded.
39.0 INSPECTION PRIOR TO WELDING:
39.1 Parent metal:
All plates and sections shall be inspected in the contractors works before fabrication.
Verification of the quality of parent metal shall be carried out by reference to the
relevant test certificate. The Inspector may, at his discretion, ask for spot checks to be
made on the chemical composition and physical properties of the material. Freedom
from harmful defects such as cracks, surface flaws, laminations, and rough, jagged or
imperfect edges shall be verified by visual examination of the material prior to welding.
Dimensions of parts shall be checked by measurement.
128
129
IS: 1364.
Shank of bolt
(mm)
Hole(mm)
High
0.000
+0.125
Low
- 0.125
0.000
130
The shank of each turned bolt shall be of such a length that it is in full contact with the
work, throughout, the screwed portion being made at least 1.5mm less in diameter than
the shank or to suit the next smaller size of screw thread. The shank portion shall be
joined to the threaded portion by a 450 chamfer within the thickness of the washer.
Washers with perfectly flat faces should be provided with all turned bolts.
The washers under the nut shall have a hole of 1.5mm larger in diameter than the
shank of the bolt and shall have a thickness of not less than 6mm so that the nut, when
screwed up, shall not bear on the shoulder of the bolt.
45.0 CONNECTING PINS:
All connecting pins shall be finished accurately to gauge and parallel throughout,
straight and with smooth surface entirely free from flaws and of sufficient length to
ensure that all parts connected thereby shall have a full bearing on the pin. They shall
be turned to a smaller diameter at the end for the thread and driven to place with a pilot
nut, where necessary to preserve the thread.
46.0 PIN HOLES:
Pinholes shall be bored smooth straight and true to gauge and at right angles to the axis
of the member. Boring shall only be done after the member has been rivetted up and
the diameter of the pin shall not be less than that of the hole by more than 0.5mm.
47.0 BEARING AND EXPANSION GEAR:
All steel bed and bearing plates or plates over saddle castings, shall be made perfectly
level and all rivet heads on their bearing surfaces shall countersunk and dressed flush.
The saddles, knuckle-bearers and roller bed-plates shall be planed on all bearing
surfaces and elsewhere as indicated on the Contract Drawings and all bolt-holes shall
be drilled. The bottom edge of ribs should be machined and welded to the bottom slabs
after which the top edges of the ribs should be machined as a whole and the top plate
welded. Subsequently the top and bottom surfaces should be machined to the specified
tolerances as given in Appendix VI of B1 specification. Generally in connection with the
bearing gear all meeting surfaces including the sides of the roller frames, shall be
machined, all bolts except anchor bolts turned and fitted, all washers faced, the rollers
knuckles and pins polished to smooth surface and the whole finished in the style of first
class machined work.
Tolerances shall be as specified in Appendix VI of IRS B-1-2001 specification and shall
be shown on the drawings.
48.0 ERECTION IN CONTRACTORS WORKS:
The work shall be temporarily erected complete at the Contractors Works for inspection
by the Inspecting Officer, with the exception of such rivetting as has to be done at site,
so that accuracy of fit and perfection of workmanship may be assured. The work shall
be put together with sufficient numbers of parallel drifts or turned bolts or both to bring
the pieces into place. When so erected all holes left to be filled at site shall be so fair
that a parallel gauge turned to a diameter 0.8mm less than that of the hole, of a length
equal to the depth of the hole, can be passed through them without difficulty. No drift
shall be used anywhere in the work larger in any part than the hole in which it is to be
driven. Holes for turned bolts, which have been 1 mm-under drilled in shop, should be
reamed at site by the erecting agency.
49.0 INTERCHANGEABILITY:
131
51.0 TESTING:
The Inspecting Officer shall be empowered, at his/her discretion to make or have
made under the supervision, any of the tests specified in the specifications mentioned
herein in addition to such other tests as he/she may consider necessary, at any time
upto the completion of the contract and to such an extent as he/she may think necessary
to determine the quality of all materials used therein. In doing so, he/she shall be at
liberty under any reasonable procedure, he/she may think fit to select, identify, have cutoff and take possession of test pieces from the material either before, during or after its
being worked up into the finished product.
He shall also be empowered to call for a duly authenticated series of mechanical tests
to be obtained from the maker for this materials used in the work and to accept the
same in lieu of other tests to the extent he/she deems fit. The Contractor shall supply the
material required for the test pieces and shall also prepare the test pieces necessary.
The test shall be carried out by the Contractor, for which Contractor shall provide all
facilities including supply of labour and plant. Inspecting officer may at his/her
discretion direct the Contractor to dispatch such tests pieces as he/she may require to
the National Test House or elsewhere as he/she may think fit for such testing purposes.
52.0 CHECK ON TESTS MADE AT CONTRACTORS WORK:
The Inspecting Officer may at his/her discretion, check test results obtained at
Contractors work by independent tests at National Test House.The Inspecting Officer
shall at all times be empowered to examine and check the working of the Contractors
plant before and after using it. Should the Contractors plant be found, in the Inspecting
Officers opinion, unreliable, he/she is empowered to cancel any tests already carried
out in this contract and have these tests carried out at any National Test House or
elsewhere, as he/she may think fit.
53.0 ANALYSIS:
The Contractor shall supply authenticated copies of analysis of any materials used in
the contract when required to do so by the Inspecting Officer who shall be empowered
to accept them to the extent he/she thinks fit. In addition to the above samples may, at
the Inspecting Officers discretion be subjected to complete analysis at the National Test
House or elsewhere as the Inspecting Officer may determine, the cost of the same to be
borne by the Purchaser.
54.0 INSPECTION GENERAL
The Inspecting Officer shall have free access to the works of the Contractor at all
reasonable times and shall be at liberty to inspect the process of manufacture at any
such time and to reject in whole or part, any work or material that does not conform to
the provisions of this Specification and may order the same to be removed, replaced or
altered at the expense of the Contractor. All gauges and templates necessary to satisfy
the Inspecting Officer of the complete interchangeability of parts must be supplied by the
Contractor free of cost.
When so specified by the Purchaser, the whole of the work except machined surfaces
shall be given protective coating using one of the systems of painting or metallising
given herewith. Prior to the application of protective coating, the surface of work shall be
carefully prepared removing mill-scale, rust, etc. using wire brushes, sand or grit
blasting as stipulated and approved by the Purchaser.
Specifications for metallising and painting of bridge girders shall be as per
IRS:B1-2001.
55.1SURFACE PREPARATION ( FOR ALL TYPES OF PAINTING AND
METALLISING)
Surface of all components /members of the superstructure shall be prepared as
per following provisions before application of first coat of paint/primer or before
metallising
(i)
The surface should be clean, dry and free from contaminants and it should be
rough enough to ensure adhesion of the paint film. However it should not be so
rough that the film cannot cover the surface peaks.
(ii)
The cleaning of the surface shall be done initially with the use of emery paper,
wire brushes, scrapers etc. for spot cleaning to remove rust, scale etc. Subsequently, sand blasting of the surface shall be done to remove rust, mill scale
along with some of the base metal. This will be achieved by high velocity impact
of abrasive material against the surface in accordance with the provisions of IS:
6586, which will also create a base for good adhesion. The abrasive material
once used for cleaning heavily contaminated surface should not be reused even
though re-screened. Washed salt free angular silica sand of mesh size 12 to 30
with a minimum of 40% retained on a 20 mesh screen shall be used for blasting.
The material specifications and other requirements shall be as provided in Indian
Railways Bridge Manual, 1998.
(iii)
All site rivets, bolts, nuts and washers shall be thoroughly cleaned and dipped in
boiled linseed oil. All machined surfaces are to be well coated with a mixture of
white lead conforming to IS:34 and Mutton tallow conforming to IS:887 as per
specifications before dispatch to site. Nothing extra shall be payable to contractor
on this account.
55.2
(i)
(ii)
(iii)
134
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
(x)
55.3
55.4Miscellaneous
135
(i)
Final dry film thickness in case of metallising shall be average 150 microns and shall be measured before application of final finishing two
coats.
(ii)
Surface preparation shall not be done unless approved paints of sufficient
quantity (both primer and finishing) are available in stock.
(iii)
Special care should be taken in preparing corners, junctions of members,
head and nuts of bolts, rivets, holes, areas less accessible, hidden pockets etc. Surface preparation at such locations shall not be inferior to that
attained over the rest of the area.
(iv)
Surface preparation shall not be carried out in the following conditions:
- In rainy season from June to September and from December to January.
- In extremely windy/misty/dust blowing conditions.
- At night
- In winter before 8 A.M.
- In summer between 11 and 15 hrs, in areas, which are likely to be exposed to
direct sunlight.
Engineer reserves the right to change the above timings
56.0 MISCELLANEOUS:
Final dry film thickness in case of metallising as well epoxy painting shall be average
150 microns and shall be measured before application of final finishing coats.
Surface preparation shall not be done unless approved paints of sufficient quantity (both
primer and finishing) are available in stock.
Special care should be taken in preparing corners, junctions of members, head and
nuts of bolts, rivets, holes, areas less accessible, hidden pockets, etc. Surface
preparation at such locations shall not be inferior to that attained over the rest of the
area.
Surface preparation shall not be carried out in the following conditions:
a.In rainy season from June to September and from December to January.
b.In extremely windy/misty/dust blowing conditions
c.At night
d.In winter before 8 A.M.
e.In summer between 11 and 15 hours, in areas, which are likely to be exposed to
direct sunlight.
57.0 INSPECTION:
Adhesion: The sprayed metal coating shall be subjected to an adhesion test using the
method described in IRS B1-2001if any part of the coating between the lines breaks
away from the base metal; it shall be deemed to have failed the test.
Articles that have been rejected, shall have the defective sections blasted clean off all
sprayed material prior to re=spraying. Where the rejection has been solely due to too
thin a coating, sprayed metal of the same quality may be added provided that the
surface has been kept dry and is free from visible contamination.
58.0 PAINTS: SOURCE & QUALITY:
136
Paint and other accessories including those for metallising for the work will be supplied
by the contractor. Paints manufactured by the following firms (or more) may be used
subject to their bearing in the approved list of RDSO and final approval by Engineer-incharge.
1.M/s. British/Burger paints
2.M/s. Johnson & Nicholson
3.M/s. Shalimar paints
4.M/s. I.C.I.
5.M/s. Nerolac.
The contractor shall furnish to IRCON, the date of manufacture of paint as certified by
the manufacturers with the necessary container marking and test certificate for paint
conforming to relevant IS code. In addition to this, he shall also submit the necessary
vouchers in respect of paint purchased by him.
IRCON reserves the right to get the paint tested at contractors expenses as considered
necessary by IRCON. If the test results do not conform to relevant IS specifications
fully, then the lot of paint shall be rejected and got removed from the contractor(s)
storage. If the paint has already been applied it shall be removed.
In addition to above, the following tests are required to be carried out in the field:
i.Weight per litre
ii.Consistency test
iii.Scratch test
iv.Flexibility and adhesive test
Note IRCON reserves the right to reject the lot of paint even on the basis of field
results.
59.0 PAINTING GENERAL INSTRUCTIONS:
Painting shall not be commenced till the surface preparation has been approved by the
Engineer or his representative or inspecting officer.
Sealed containers of paint of approved brand shall be used. The paint drums must be
rolled, turned upside down and shaken before opening. The paint must be stirred well
before use. Over stirring which results in invisible air bubbles etc., shall be avoided.
Where brush painting is accepted, the paint must be applied by means of flat brushes
not more than 75mm in width having soft flexible bristles conforming to IS: 384.
Round and oval brushes of approved quality conforming to IS: 487 may also be used as
per the instructions of the Engineer or his representative or inspecting officer.
All new bushes should be soaked in raw linseed oil conforming to IS: 77 for at least 24
hours before use.
A little blue paint shall be added, in the first coat of aluminium paint to distinguish it from
second coat. For paints of other colours for final and finishing two coats, suitable
137
pigment shall be used as per instruction of the Engineer, to distinguish the first coat
from the second coat.
The date of painting shall be marked with paint on the member.
60.0 CARE DURING PAINTING:
Paint should be mixed in small quantities sufficient to be consumed within one hour in
he case of red lead paint.
The applied coat of paint shall be uniform, and free from brush marks, sack marks,
blemishes, scratching, non-uniform thickness, holes, log marks, fuel staining, cracking,
scaling, and other defects.
Paint shall be applied only on dry and clean surface free from moisture or dust
(including scrapping dust).
Paint should be used within the prescribed shelf life from the date of manufacture.
Each coat of paint shall be left dry till it sufficiently hardens before the subsequent coat
is applied. Each coat of paint shall be inspected by the engineer or inspecting officer
and certified as satisfactory before applying subsequent coat.
The payment for complete painting of all components of girders including all
accessories, painting of contact surface etc. including all labour and material, is
included in the accepted rates for item in the schedule of items, rates and quantities and
nothing extra shall be paid.
61.0 SPECIFICATION FOR METALLISING WITH SPRAYED ALUMINIUM FOR
BRIDGE GIRDERS
61.1 Surface preparation:
The surface shall be thoroughly cleaned and roughened by compressed air blasting or
centrifugal blasting with a suitable abrasive material in accordance with Clause 3 of IS:
6586. Immediately, before spraying it shall be free from grease, scale, rust, moisture or
other foreign matter. It shall be comparable in roughness with a reference surface
produced in accordance with appendix A of IS: 5905 and shall provide an adequate key
for the subsequently sprayed metal coating
61.2 Metal spraying:
The metal spraying shall be carried out as soon as possible after surface preparation
but in any case within such period that the surface is still completely clean, dry and
without visible oxidation. If deterioration in the surface to be coated is observed by
comparison with a freshly prepared metal surface of similar quality which has
undergone the same preparation, the preparation treatment should be repeated on the
surface to be coated.
The wire method shall be used for the purpose of metallising the diameter of the wire
being 3mm or 5mm. Specified thickness of coating shall be applied in multiple layers
and in no case less than 2 passes of the metal spraying unit shall be made over every
part of the surface. At least one layer of the coating must be applied within 4 hours of
blasting and the surface must be completely coated to the specified thickness within 8
hours of blasting.
138
i- Purity of Aluminium:
The chemical composition of aluminium to be sprayed shall be 99.5% aluminium
conforming to IS: 2590.
ii- Appearance of the coating:
The surface of the sprayed coating shall be of uniform texture and free from lumps,
coarse areas and loosely adherent particles.
iii- Thickness of the coating:
The nominal thickness of the coating shall be 150 (microns).The minimum local
thickness, determined in accordance with procedure given in clause 3.1 below, shall be
not less than 110 (microns).
61.3 Shop painting:
Any oil, grease or other contamination should be removed by thorough washing with a
suitable thinner until no visible traces exist and the surfaces should be allowed to dry
thoroughly before application of paint. The coatings may be applied by brush or spray.
If sprayed, pressure type spray guns must be used. One coat of wash primer to IS: 5666
shall be applied first. After 4 to 6 hours of the application of the wash primer, one coat of
Zinc chrome primer to IS: 104 with the additional proviso that zinc chrome to be used in
the manufacture of primer shall conform to type 2 of IS: 51 shall be applied. After hard
drying of zinc chrome primer, one coat of Aluminium paint to IS: 2339 (brushing or
spraying as required) shall be applied.
62.0 Method for the determination of local thickness:
62.1 Equipment:
Any magnetic or electro-magnetic thickness meter that will measure local thickness of a
known standard with an accuracy of 10 percent.
62.2 Calibration of instrument:
Calibrate and check the meter on one of the following standards (as appropriate):
1) (Applicable to magnetic and electromagnetic meters other than the pull-off type)
A soft brass shim, free from burrs, in contact with the grit-blasted surface of the
base metal prior to its being sprayed. The thickness of the shim shall be
measured by micro meter and shall be approximately the same as the thickness
of the coating.
2) A sprayed metal coating of uniform known thickness approximately the same as
the thickness of the sprayed coating to be tested, applied to a base of similar
composition and thickness to the article being sprayed, grit-blasted in accordance
with Clause 1.
62.3 Procedure:
For each measurement of local thickness, make an appropriate number of
determinations, according to the type of instrument used.
With instrument measuring the average thickness over an area of not less than 0.645
cm2, the local thickness shall be the result of the one reading.
139
With instruments having one or more pointed or rounded probes, the local thickness
shall be the mean of three readings within a circle of 0.645 cm2 area.
With meters having two such probes, each reading shall be the average of two
determinations with the probes reversed position.
63.0 Method of test for adhesion:
Using a straight edge and hardened steel scriber which has been ground to a sharp
30 degree point, scribe two parallel lines at a distance apart equal to approximately
10 times the average coating thickness. In scribing the two lines, apply enough
pressure on each occasion to cut through the coating to the base metal in a single
stroke.
63.1 Inspection:
Determination of local thickness:
The minimum local thickness shall be determined by the method described above.
Adhesion:
The sprayed metal coating shall be subjected to an adhesion test using the method
described above. If any part of the coating between the lines breaks away from the base
metal, it shall be deemed to have failed the test
Articles, which have been rejected, shall have the defective sections blasted clean of all
sprayed metal prior to respraying. Where the rejection has been solely due to too thin a
coating, sprayed metal of the same quality may be added provided that the surface has
been kept dry and is free from visible contamination.
64.0 NAME PLATE:
A neat casting bearing the name of the Contractor, the place and year of manufacture,
drawing number, the contract number and the standard of loading to be specified by the
Purchaser shall be bolted conspicuously on each span. The drawing of the name plate
shall be approved by the Engineer.
65.0 ERECTION MARK:
Every portion of the work shall be distinctly stencilled with paint with letter size not less
than 10 mm for guidance in the erection in the field, and stamped with the letters
specified in the drawings. In the case of non-interchangeable work, the system of
marking shall be in accordance with the drawings prepared by the tenderer and
approved by the Purchaser.
66.0 PACKING:
All projecting plates or bars shall be kept in shape by timber or angle bars spiked or
bolted to them , and the ends of the chord lengths, end posts and plate girders at their
shipping joints shall be protected and stiffened so as to prevent damage or distortion in
transit as the Inspecting Officer may direct.
140
All threaded ends and machined surfaces are to be efficiently protected against damage
in transit. The parts shall be sent out in lengths convenient for transport. All straight bars
and plates except small pieces are to be sent out in convenient bundles temporarily
rivetted or bolted together or bound with wrought iron or suitable wire as the Inspecting
Officer may direct. All rivets, bolts, nuts, washers, plates under 300 mm square and
small articles generally are to be packed separately for each span in cases each
weighing, when full, not more than 350 kg, or in strong petroleum casks, or in barrels
approved by the Inspecting Officer. If not entirely filled by the contents the space left
shall be closely packed with wood shaving or other suitable material. Bolts and rivets of
different sizes shall be separately packed in bags, each bag having a label indicating its
contents. A list of the contents shall be placed in the top of each case or cask. In the
case of imported material all cases shall be made of 32mm boards with ends nailed
with 90mm wire nails strengthened by battens and 38mmx 1.6mm (No. 16 BG) hoop
-iron and made thoroughly secure for transit to India. All casks shall be in sound
condition, and if not entirely filled by the contents the space left shall be closely packed
with wood-wool or other suitable material. The heads shall be firmly secured by means
of hoops in the usual way, and in addition each head shall be further secured by a
strong wooden batten and not less than two strips of 1.6mm (No.16 BG) hoop-iron
passing over the head and nailed to the staves on both sides. The hop-iron shall be
long enough to pass over two hoops on each side of the cask and be nailed in such a
manner that the hoops cannot slack back. Bolts and rivets of different sizes shall be
packed in a separate canvas bags, each bag having a label in dictating its contents. End
field holes to be bolted in case of members having split in plate and channels.
67.0 DISPATCH OR SHIPPING MARKS:
Each package, case or bundle is to have clearly stencilled on it in good oil paint the
address as stated in the order of contract, gross and net weight description of contents
and such marks as may be required by the Purchaser must be shown against each item
in the invoice. The Contractor is to provide necessary stencil plates for marking. Every
piece of bundle shall be marked and in the case of material (shipped to India) all cases
or casks shall be clearly cut or branded, not merely painted, with their net and gross
weights and with such shipping marks and other particulars as the Inspecting Officer
may direct and each bundle shall also have a metal label securely attached with wire
stamped with similar marks. The marking shall be done with thick oil paint and in such a
manner that it cannot be washed off or obliterated.
141
68.0 LOADING:
All trucks or wagons are to be loaded to as near their full capacity as is consistent with
safe transport. While loading the material in wagon, truck or trailor, care should be
taken that heavier material is loaded first and lighter material is kept on top so that
lighter material is not damaged due to heavy weight. While transporting the material by
road, adequate safety precautions shall be taken as per extant instructions.
The Contractor shall apply all dunnage and lashing required to hold the material
securely in position free of charge.
While handling any girder or girder component it shall be ensured no damage to
material takes place in the form of dent/cut mark etc. Wooden blocks, rubber pads shall
be used to avoid direct contact between materials to be handled and handling
equipment.
69.0 WEIGHT OF STEEL WORK FOR PAYMENT:
Any steel work the weight of which differs by more than 2.5% from the calculated weight
determined from the nominal weight of the sections shall be liable to rejection.
Payment shall be made on the tendered weight to be calculated in accordance with the
nominal weight of the sections as specified on the contract drawings or as per actual
weight received from the supplier. An addition in weight will be allowed for welds and
rivet heads is as follows:
2% in case of rivetted or composite (rivetted and welded)work;
Should the actual weight fall short of the calculated weight by more than 2.5%, the
material if accepted, will be paid for the actual weight only. Should the actual weight
exceed the actual calculated weight, payment will be made for calculated weight only.
In the event of a dispute arising as to the weight of a portion of steelwork, a weighment
shall be made in the presence of the Inspecting Officer.
70.0 QUANTITIES:
In case where the estimated quantities are given with the schedule, it must be
understood that the Purchaser will not be responsible for their accuracy and if the
Contractor makes use of them in preparing his/her tender, he/she does so at his/her
own risk, as he/she will not be entitled to make any claim or demand nor to raise any
question whatsoever, on account of any error or miscalculations in or misunderstanding
of the said quantities, as these are given for the convenience of the Purchaser.
71.0 TRACINGS AND PRINTINGS:
Except in the case of standard spans fabricated without any modifications to the
standard drawings the Contractor shall supply free of charge, one set of neatly executed
tracing on linen. They shall be fully dimensioned and contain all erection marks,
notifications as to the colour the work has been printed, the name of the Contractor and
any alterations from the contract drawings, which may have been made in executing the
work. The drawings shall conform to standard sizes as given in IS: 962 and shall not
exceed AO size. The drawings shall not be folded but rolled outwards on a roller, in
addition to three sets of full size copies on strong paper made by an approved process.
72.0 RIVETS AND BOLTS LISTS:
The Contractor shall also supply, without charge, three complete lists of the rivets, bolts,
service bolts, washers and drifts required for erecting the work at site, showing the parts
of the work to which the various rivets and bolts belong and having each item marked
so as to indicate the particular case in which it will be found.
142
SKETCHES
In this portion, some sketches useful to the fabrication work have been given for the
benefit of the tenderer. In case further elaboration is required, tenderer will develop his
own sketch and get approval of the Engineer.
144
Fig
No.-1
145
146
147
Fig.
No.-4
148
Fig. No.-5
149
Fig No.-6
150
Fig. No.-7
151
152
Fig. No.-9:Butt Welded Joint With Run On & Run Off Plates
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
Fig. No.-23
168
169
MAINTENANCE
OF
RECORDS
170
MAINTENANCE OF RECORDS
At least, the following records be maintained by the contractor
for perusal of the engineer as well as RDSO authorities. If the
contractor wants to maintain some extra records/use different
proforma better than the suggested one, he may get approval of
the same from the engineer and do like that. But at least, the
details mentioned herein will have to be maintained by the
contractor, which is compulsory.
1. Jigs register:
This register shall be maintained for keeping record of details
of jigs, their approval and modification/rectification to the
jigs. One page should be allotted for each jig and details
mentioned in the following profarma:1.
2.
3.
4.
Description of jig:
Jig No.:
Shipping mark of the component for which jig is made:
Drawing No. for the component:
Date
of Observation/inspec
inspection
tion notes
2
Compliance
action
3
Initial
Supervisor
Incharge
4
of
1
In the beginning of Register, a statement of jigs shall also be
placed in the following profarma:
Jig
No.
1
Descrip Shipping
Drg. No. as per Inspecting
tion of mark of the which
jig
is officials
Jig.
component.
made/modified
approval
details
2
3
4
5
Date
of
rivet
ting
2
Rivet
ting
party
3
Number
and
nature
of
defective
rivets
4
171
Number
of Initial
of
defective
Supervisor
rivets
Incharge.
replaced
5
6
Girder
Weld
joint Name
of WPSS
component
description
welder/Tic followed
and
its
ket No.
Sl.No.
2
3
4
5
172
No.
Welding
consumable
used
Welding parameters
Elect
rode/
wire
Current
Flux
(amp.)
Arc
Voltage
(volt)
Travel
Speed
(m/min)
10
Weld
repair
details
Run
on/Run
off
tabs.
No. if
any
Radiogra
ph
no.
if any
Initial
of
Supervi
-sor
Incharg
e.
11
12
13
14
Date of
radiogr
aphic
inspect
ion.
Radi
ograp
h
No.
Obse
rvati
on
Resu Initia
lt
l
of
Superv
isor
Inchar
ge.
8
9
Type and
Size of
rolled
section
Materia
l Test
Certifi
cate
No.
Cas
t
No.
4
173
Steel
quantit
y as
per the
test
certifi
cate
5
Steel
Manufactu
rer/
Supplier
Initi
al of
Super
visor
Incha
rge.
7
Welding current:
Type:
Polarity:
8.
Welder qualification:
9
Welding parameters and technique:
Welding Parameters:
Weld
Pass
No.
1
9.1
10.
11.
12.
13
14
Electro
des/
wire
dia.
(mm)
2
Curre
nt
(amp)
3
Arc
Volta
ge
(volt
)
4
Wire
feed
speed
(m/min
))
5
Trave
l
speed
(m/mi
n)
6
Electr
ical
sticko
ut
(mm)
7
Gas
flow
rate
(litre/
min.)
8
15
16
17
18.
Electrod
e
wire
dia (mm)
Curren
t
(amp)
Arc
voltag
e
(volt)
4
Wire
feed
speed
(m/min.)
5
Travel
speed
(m/min.
)
6
Electric
al stick
out (mm)
7
Shielding
gas
flow
rate
(lit/min.)
8
Test
1
Non-destructive tests:
i)
Visual examination:
ii)
Dye penetrant test:
Specimen No.
2
175
Result.
3
iii)
iv)
Signature _______________________
Designation ___________________
Date _________________________
(for & on behalf of Fabricator).
176
QUALITY CONTROL
177
Table No.-1
APPENDIX - IV
( REF. TO CLAUSE - 23 )
SKETCH
TOLERANCE
1.
2.
3.
4.
NOT ALLOWED
NOT ALLOWED
5.
NOT ALLOWED
NOT ALLOWED
NOT ALLOWED
6.
7.
8.
9.
2 mm
b
b < 0.1d
b
a + b < 0.1d
a
a + b < 0.1d
d
b
a
c
a + b < 0.1d
c < 0.5d
NOT ALLOWED
NOT ALLOWED
a < 0.3 mm
DEVIATION UP TO
3% OF THICKNESS.
THICKNESS OF JOINT
ELEMENTS BUT NOT
MORE THAN 3mm.
178
179
Plate girders
Tolerances in mm
(plus)
(minus)
Notation in
the Figure
No.1
(a)
(b)
(c)
(d)
(e)
(f)
(g)
0.15
ii) locally
0.25
(h)
(i)
Concavity
(ii)Horizontal plane
2.
(b)
Distance
bearings
(c)
(d)
(e)
(f)
(g)
between
centre
to
centre
180
of
(h)
3.
throughout
0.15
(ii)
locally
0.25
.001 L
.001 L
0.5
0.5
0.5
0.5
0.8
(i)
Twist in members
(j)
Holes(a)
(b)
(c)
Edge distance
(d)
Tolerances in mm
1.
+2 to -1
2.
1/200 or 3 max
3.
4.
5.
+ 6 to -3
+ 3 to -1
+ 2 to -1
+ 1 to -1
10
+ 3 to -3
181
to +3
2)
Permitted, Maximum
Planar defects
a) Cracks and lamellar tears
not permitted
b) Root concavity
not permitted
not permitted
not permitted
not permitted
a) Isolated pores
3)
c) Linear porosity
l6 mm w1.5 mm
f) Crater pipes
l6 mm w1.5 mm
182
i)
18 mm
t/2 and 6 mm
1.5 mm
ii)
>18 mm and 75 mm
>75 mm
t/3
1.5 mm
iii
b) Linear group*
Copper inclusions
(Detected
by
visual
examination
or
by
radiography)
5)
25 mm
1.5 mm
Aggregate length should not exceed 8 percent
of length of group, which in turn should not
exceed 12t in length
Maximum dimension in any direction:
6
mm
Not permitted
Profile defects
a) Undercut
e) Overlap
f) Linear misalignment
g) Other profile defects
Symbols:
t
=
=
Diameter of defect
Individual inclusions within the group should not exceed the sizes in 3(a) above. A
linear group is defined as a number of inclusions in line and parallel to the weld axis
where the spacing between their adjacent ends does not exceed 6 times the length
of the longest inclusion within the group. With parallel groups, all inclusions count
towards the aggregate.
183
SECTION - 9
Drawings
184
1.0
Drawings enclosed with these documents are only for guidance and may change
during detailed design approved/ execution stage and the contractor shall not
have any claims whatsoever in case of such change.
185