Kovacs Szabolcs Project Duration: 231 days

Appendix B. Residential house summary


B+GF+A House, Garage, Pool and Fence
1 - 1 (1)
Code WBS Name Start Finish Calendaristic Duration, Unit of Volume 2017
Duration, Days Days Volume [Remaining
[Remaining] [Remaining ] Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
]
0 B+GF+A House, Garage, Pool and Fence 02.01.2017 28.07.2017 231 150.00 B+GF+A House, Garage, Pool and Fence
1 Key Milestones 02.01.2017 05.07.2017 231 Key Milestones
2 Project Management 02.01.2017 05.07.2017 231 133.00 Project Management
3 Project Preparation 02.01.2017 19.01.2017 20 14.00 Project Preparation
4 Procurement of Design 16.01.2017 27.01.2017 14 10.00 Procurement of Design
5 Design 30.01.2017 25.04.2017 95 62.00 Design
6 Procurement of General Contractor 26.04.2017 06.06.2017 88 30.00 Procurement of General Contractor
7 Procurement of Execution Consultant (En26.04.2017 09.05.2017 29 10.00 Procurement of Execution Consultant (Engineer)
8 Execution Supervision 15.06.2017 21.06.2017 6 5.00 Execution Supervision
9 Construction Works 02.01.2017 28.07.2017 202 123.00 Construction Works
9.1 Mobilization/Demobilization 07.06.2017 21.06.2017 14 11.00 Mobilization/Demobilization
9.2 B+GF+A House 02.01.2017 06.07.2017 217 107.00 B+GF+A House
9.2.1 Infrastructure 16.03.2017 30.06.2017 28 24.00 Infrastructure
9.2.1.1 Foundations 16.03.2017 30.06.2017 18 16.00 Foundations
9.2.1.2 +0.00 Elevation Slab 04.04.2017 13.04.2017 10 8.00 +0.00 Elevation Slab
9.2.2 Superstructure 16.03.2017 22.05.2017 53 41.00 Superstructure
9.2.2.1 Ground Floor 16.03.2017 02.05.2017 33 27.00 Ground Floor
9.2.2.2 Roof 27.04.2017 22.05.2017 20 18.00 Roof
9.2.3 Architecture 02.01.2017 06.07.2017 61 54.00 Architecture
9.2.3.1 Exterior Works 23.05.2017 09.06.2017 18 14.00 Exterior Works
9.2.3.2 Interior Works 02.01.2017 06.07.2017 49 45.00 Interior Works
9.2.4 Electrical and Lighting Protection 30.01.2017 02.06.2017 30 19.00 Electrical and Lighting Protection
9.2.4.1 Exterior 16.03.2017 23.05.2017 7 5.00 Exterior
9.2.4.2 Interior 30.01.2017 02.06.2017 23 15.00 Interior
9.2.5 Plumbing and Water Supply 02.01.2017 29.05.2017 21 8.00 Plumbing and Water Supply
9.2.5.1 Plumbing 02.01.2017 25.05.2017 13 6.00 Plumbing
9.2.5.2 Water Supply 23.05.2017 29.05.2017 8 5.00 Water Supply
9.2.6 Heating 30.01.2017 26.05.2017 9 6.00 Heating
9.2.7 Gas 23.05.2017 25.05.2017 3 3.00 Gas
9.3 Garage 16.03.2017 28.07.2017 69 46.00 Garage
9.4 Fence and Gates 12.06.2017 27.06.2017 14 12.00 Fence and Gates
9.5 Utilities 16.03.2017 28.03.2017 10 9.00 Utilities
9.5.1 Electrical 16.03.2017 28.03.2017 11 9.00 Electrical
9.5.2 Plumbing and Water Supply 16.03.2017 27.03.2017 9 8.00 Plumbing and Water Supply
9.5.2.1 Plumbing 16.03.2017 27.03.2017 9 8.00 Plumbing
9.5.2.2 Water Supply 16.03.2017 27.03.2017 9 8.00 Water Supply
9.5.3 Gas 16.03.2017 27.03.2017 9 8.00 Gas
9.6 Roads and Sidewalks 12.06.2017 16.06.2017 6 5.00 Roads and Sidewalks
9.7 Final Testing and Handing Over 15.06.2017 19.06.2017 3 3.00 Final Testing and Handing Over
10 Commissioning 22.06.2017 05.07.2017 13 10.00 Commissioning
Phase "B+GF+A House, Garage, Pool and Fence" (Code: Project Budget 21.83 3.15 49.55 15.95 24.08 35.32 18.12
B_GF_A_House_Garage_Pool_Fence) 49.55