Beruflich Dokumente
Kultur Dokumente
discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/274704636
CITATIONS READS
4 170
3 AUTHORS, INCLUDING:
All in-text references underlined in blue are linked to publications on ResearchGate, Available from: Xianbo Zhao
letting you access and read them immediately. Retrieved on: 26 March 2016
The current issue and full text archive of this journal is available on Emerald Insight at:
www.emeraldinsight.com/0969-9988.htm
Abstract
Purpose The purposes of this paper are to: investigate schedule performance of new and retrofitting
green building projects; identify the critical factors that influence the schedule performance of new and
retrofitting green building projects; and provide solutions to improve schedule performance of
new and retrofitting green building projects.
Design/methodology/approach A questionnaire survey were conducted and responses were
received from 34 firms experienced in green building projects in Singapore. After the data from the
survey had been analyzed, face-to-face interviews were conducted with two senior project managers to
solicit comments on the survey results.
Findings This study identified the degree of project delay in 98 new green building projects and
51 retrofitting green building projects in Singapore. The result indicated that 22 percent of the
Singaporean green building projects were plagued with delay and retrofitting projects had a
significantly higher likelihood of delay and significantly longer extension than new projects. In
addition, consultant cooperation to solve problems was the most influential to schedule performance
of both new and retrofitting green building projects, and the two project groups agreed on the overall
ranking of the factors affecting schedule performance.
Research limitations/implications There may be geographical limitation on the conclusions
drawn from the findings. Also, the sample size was still small, despite a relatively high response rate. In
addition, the majority of the respondents were contractors as other project players were reluctant to
respond to the survey.
Practical implications This study provides a clear understanding of the schedule performance of
green building projects as well as the critical factors that should be highlighted when constructing
green building projects. Also, strategies to overcome the negative impact of these factors allow
practitioners to better deal with the potential causes of delay and to attain the schedule performance.
Originality/value Although construction delays have been widely investigated in previous studies
relating to construction management, few have attempted to analyze the schedule performance of new
and retrofitting green buildings. Thus, this study adds significantly to the existing research on both
green building and construction delay.
Keywords Singapore, Buildings, Green building, Retrofitting, Delay, Schedule
Paper type Research paper
that require major retrofitting work. The Singapore Green Building Council (SGBC)
estimated that at least 6,500 buildings would need to be retrofitted over the next
20 years to enable Singapore to reach the goal of having 80 percent of all buildings
certified by the Green Mark by 2,030 (BCA, 2009). A recent study by the BCA showed
that the retrofitted existing buildings can achieve an average of 20 percent in energy
savings (BCA, 2014a).
To achieve the goal, it is important to diminish delays in green building projects and
to ensure the projects are completed on time. Also, assurance of project schedule is an
important indicator of project success, and factors associated with project schedule
have been recognized to be critical to project success (Hwang et al., 2013; Ling et al.,
2009). If a project can be completed on time or even earlier than the completion date, the
overhead costs, labor costs, and interest costs will be reduced. Simultaneously, early
completion enables clients to make more profits as revenue can be earned earlier.
Construction delays have been widely investigated in previous studies relating to
construction management (such as Assaf and Al-Hejji, 2006; Long et al., 2008a; Sweis
et al., 2008). However, few studies have attempted to analyze the schedule performance
of new and retrofitting green buildings. The specific objectives of this study are to:
investigate schedule performance of new and retrofitting green building projects;
identify the critical factors that influence the schedule performance of new and
retrofitting green building projects; and provide solutions to improve schedule
performance of new and retrofitting green building projects.
As an increasing number of countries have initiated programs to embrace green
buildings to deal with the climate change (He and Kua, 2013; Kua and Wong, 2012) and
schedule performance is an indicator of project performance and critical to project
success (Ling et al., 2009), this study provides a clear understanding of the schedule
performance of green building projects as well as the critical factors that should be
highlighted when constructing green building projects. Also, strategies to overcome the
negative impact of these factors allow practitioners to better deal with the potential
causes of delay and to attain the schedule performance.
Background
Green building
Sustainable development has turned out to be a global issue as global climate changes
have gradually become a serious concern for the future. Thus, the major goal of
sustainable construction is to create a healthy built environment based on efficient use
of resources and smart ecological design. The building sector is experiencing a green Green
revolution (Gou et al., 2013). There have been various definitions of the term green building
building. For example, green building is defined as a building that the required
building performance criteria while minimizing the disturbance to and improving the
projects
ecosystems in the local, regional and global context throughout its life cycle (Glavinich,
2008). In Singapore, a building is deemed green if it has met the requirements under the
Green Mark Scheme, which adopts the assessment criteria covering energy efficiency, 329
water efficiency, environmental protection, indoor environmental quality, and other
green features and innovation (Hwang and Tan, 2012).
sustainable buildings in 2005 and formed the backbone of Singapores first Green
Building Masterplan focussed on new buildings and those under major retrofitting.
With the success on the first Masterplan, the BCA announced their second Green
Building Masterplan focussed on converting the existing buildings to green buildings
(BCA, 2009). To accelerate the process of going green, the BCA has launched the third
Green Building Masterplan, which highlights building capability in the industry,
engaging the tenants and occupants for closer partnership between the people, private
and public sectors, driving consumption behavioral adjustments, as well as developing
an environment that addresses the well-being of the people (BCA, 2014a).
In addition, the BCA introduced a Green Mark Incentives Scheme for New Buildings
(GMIS-NB). The scheme offers S$20 million incentives to developers, building owners,
project architects and M&E engineers who make efforts to achieve at least a Green
Mark Gold rating in the design and construction of new buildings (BCA, 2013b). Also,
the BCA launched a Green Mark Incentive Scheme for Existing Buildings (GMIS-EB)
with the financial incentives of S$100 million in order to boost the retrofitting of
existing buildings in the private sector, recognizing that owners are discouraged from
upgrading the energy performance of their buildings due to the financial expenditure
involved (BCA, 2013a). Because of the incentive schemes mentioned above, till July
2016, there have been 2,155 Green Mark certified buildings in Singapore (BCA, 2014a).
The last section was aimed to collect the respondents opinions on potential strategies
to enhance schedule performance of green building projects. A list of recommendations
was presented that could be used to solve the delay problems faced by project players
Downloaded by Central Queensland University At 03:19 22 May 2015 (PT)
References
Category Code Factor 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
(continued )
Factors affecting
projects
performance
project schedule
building
Green
Table I.
331
Downloaded by Central Queensland University At 03:19 22 May 2015 (PT)
22,3
332
Table I.
ECAM
References
Category Code Factor 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Labor-related LR1 Shortage of labor * * * *
factors LR2 Low labor productivity *
LR3 Low labor skills *
External factors EX1 Bad weather conditions * * * *
EX2 Unfavorable site conditions * * * * *
EX3 Delays in obtaining permit from municipality * * *
EX4 Accident during construction * * *
EX5 Discrepancy between design specification and building code * *
EX6 Delay in performing final inspection and certification by a third party * *
Notes: 1, Long et al. (2008b); 2, Abd El-Razek et al. (2008); 3, Akinsola et al. (1997); 4, Assaf and Al-Hejji (2006); 5, Belassi and Tukel (1996); 6, Belout (1998);
7, Chan and Kumaraswamy (1997); 8, Chua et al. (1999); 9, Al-Momani (2000); 10, Sweis et al. (2008); 11, Lowe et al. (2006); 12, Manavazhi and Adhikari (2002);
13, Hwang et al. (2013); 14, Odeyinka and Yusif (1997); 15, Ahmed et al. (2003); 16, Sambasivan and Soon (2007); 17, Songer and Molenaar (1997);
18, Dissanayaka and Kumaraswamy (1999); 19, Frimpong et al. (2003). *Indicates the inclusion of the specific factor in the reference
in new and retrofitting green building projects. The respondents were asked whether Green
they agree or disagree on these strategies. building
The population was all the professionals with experience in green building. A total
of 113 questionnaires were randomly sent out to the building contractors registered
projects
with the BCA, as well as the consultants, architects, and developers in the directory of
the Association of Consulting Engineers Singapore and the Real Estate Developers
Association of Singapore. The possible problem of low response rate could be settled 333
through telephone reminders. As a result, a total of 34 responses were received,
representing a response rate of 30 percent, which was consistent with the norm of 20-30
percent in most surveys in the construction industry (Akintoye, 2000). Despite the small
sample size, statistical analysis could still be performed as the central limit theorem
holds true with a sample size not smaller than 30 (Ott and Longnecker, 2008).
The profile of the respondents and their companies and projects is presented in
Downloaded by Central Queensland University At 03:19 22 May 2015 (PT)
Table II. As shown in Table II, 65 percent of the respondents were from contractors,
while the remaining were from consulting firms (18 percent), developers (9 percent), and
architecture firms (9 percent).
Although the questionnaire has been considered as the most cost-effective and most
popular way to collect data relating to attitudes, opinions, and behaviors (Gravetter and
Forzano, 2012), survey responses could be subjective and thus validation and caution
for generalization are necessary (Hwang and Yang, 2014). As a result, after the data
from the survey had been analyzed, face-to-face interviews were conducted with two
senior project managers who had 15 and 18 years of experience in the construction
industry, respectively. As they were not included in the survey respondents, they could
fairly comment on the survey results.
Characteristics n %
where d is the difference between ranks assigned to each factor, and n is the number of
pairs of rank.
New Retrofitting
Project type n total n with delay % n total n with delay %
Commercial 36 14 39 18 9 50
Table III. Residential 23 0 0 12 0 0
Project delay: new Educational 28 6 21 13 4 31
vs retrofitting green Industrial 11 2 18 8 3 38
building projects Total 98 22 22 51 16 31
retrofitting (50 percent) projects. This was possibly because commercial projects are Green
relatively unique in nature and vary extensively in terms of its usage, design, and building
specification. Compared to other building types in which the building forms and
designs are relatively similar, commercial buildings are more difficult to replicate. Also,
projects
the retrofitting commercial buildings experienced more delay than the new buildings.
This may be attributed to the fact that commercial buildings are usually retrofitted
when they are still in operation, which is likely to bring constraints and restrictions to 335
retrofitting works.
The respondents were also requested to rate the likelihood and extension of project
delay based on their experience. As shown in Table IV, 65 percent of the respondents
believed that new green buildings were seldom plagued with delay, with the likelihood
lower than 30 percent. In contrast, only 41 percent considered that the delay in
retrofitting projects occurred at the likelihood below 30 percent and 53 percent of the
Downloaded by Central Queensland University At 03:19 22 May 2015 (PT)
respondents rated the likelihood between 31 and 60 percent for retrofitting projects.
In addition, retrofitting projects had a higher mean likelihood (31 percent) of delay than
new projects (23 percent). The paired t-test was carried out to test whether there was
significant difference in the likelihood of schedule delay between new and retrofitting
green building projects. The p-value was 0.040, suggesting that the null hypothesis was
rejected and that the difference was statistically significant.
As for the extension of project schedule delay, 53 percent of the respondents
considered that the actual schedule of new green building projects was 1-5 percent
longer than the planned schedule while 50 percent reported that retrofitting projects
usually experienced 6-9 percent schedule delay. However, none indicated building
projects had the schedule over 10 percent than the planned schedule. Additionally, new
green projects had a lower extension of delay than retrofitting projects, and the paired
t-test result implied that this difference was statistically significant (p-value 0.010).
0% 7 21 5 15 0 7 21 5 15
1-30% 15 44 9 26 1-5 18 53 12 35
31-60% 12 35 18 53 6-9 9 26 17 50
61-99% 0 0 2 6 10 0 0 0 0 Table IV.
Total 34 100 34 100 Total 34 100 34 100 Likelihood and
Mean 23 31 Mean 3.5 4.8 extension of project
p-value 0.040* p-value 0.010* delay: new vs
Note: *Paired t-test result is significant at the 0.05 level (two-tailed) retrofitting
ECAM New Retrofitting
22,3 Rank Rank Rank Rank
Category Code Factors Mean I II Mean I II
Notes: Rank I Intra-category rank; Rank II Inter-category rank. The Spearman rank correlation
coefficient was 0.971 (p-value o0.001) Table V.
were ranked second and third, respectively, with mean scores of 3.91 and 3.88. As for
retrofitting green building projects, the most critical factor was PR1 with a mean score
of 4.09, followed by factors PR1 and PR3. Thus, the result implied that project
complexity was the most crucial delay factor among the other factors for both new and
retrofitting building projects.
Client-related factors. As shown in Table V, factor CR4 was ranked first with mean
scores of 4.35 and 4.41 in new and retrofitting green building projects, respectively.
It implied that client-initiated changes should be carefully considered for the potential
impact on schedule performance of both new and retrofitting building projects. These
changes would result in client-related rework, thus threatening project schedule
performance (Hwang et al., 2014a). Factor CR3 was ranked second in project groups.
It was found that projects tended to achieve better performance than desired when
payments to the contractor were released promptly (Iyer and Jha, 2006). In both groups
of building projects, all the client-related factors had mean scores over 4.00, indicating
that client had significant impact on the project schedule performance and should not
be overlooked.
Design team-related factors. Referring to Table V, misinterpretation of clients
requests (DR3) was deemed to be the most critical delay factor in both groups of
projects, confirming that the effectiveness of communication between designers and
client was crucial for project schedule performance (Lowe et al., 2006). Factor DR2
occupied the second position in both types of building projects with relatively high
mean scores of 4.24 and 4.32, respectively. This implied that mistakes/delays in
producing design documents have high influence in delaying the project schedule, and
thus it is essential for design team to produce the design documents promptly with
minimum mistakes to avoid project delays. Also, all the design team-related factors
gained mean scores above 4.00, suggesting that these factors exerted significant impact
on the project schedule performance and merited attention.
Consultant-related factors. With reference to Table V, CS3 consultant cooperation to
solve problem was considered as the most influential factor leading to project schedule
delay in both new and retrofitting projects. The mean score of factor CS3 was 4.44 in
new green building projects and 4.59 in the retrofitting group. In addition, factor CS2
ECAM was ranked second in both new and retrofitting green building projects with mean
22,3 scores of 4.35 and 4.56, respectively. The results implied that without consultants
commitment cooperation to solve problem and consultants involvement in monitoring
the project progress, it would be difficult to make projects meet their schedule.
Following, factors CS1 and CS4 are ranked third and fourth in new and retrofitting
green building projects. For both types of building projects, all the consultant-related
338 factors gained mean scores above 4.00, showing that consultant-related factor exerted
significant influence on the project schedule performance.
Contractor-related factors. As shown in Table V, in new green building projects,
factor CO2 yielded the highest mean score. It can be inferred that the respondents
considered the cash flow of the contractor as topmost important factor affecting the
project schedule. This result was consistent with the previous studies that recognized
cash flow problems of contractors as a cause of project delay (Al-Khalil and Al-Ghafly,
Downloaded by Central Queensland University At 03:19 22 May 2015 (PT)
1999; Arditi et al., 1985; Iyer and Jha, 2006). In retrofitting projects, factor CO1 was
ranked first, indicating that planning of site activities merited more attention because
these site activities would be conducted with the on-going operations of the building.
These two factors were followed by factors CO5 and CO3 in both types of projects. In
addition, factor CO4 received the bottom positions with mean scores of 3.38 and 3.29 in
new and retrofitting projects, respectively. This result suggested that the construction
method chosen by contractors was less important to schedule performance of green
building projects.
Equipment-/material-related factors. In this category, factor EM6 late delivery of
material was ranked top in both new and retrofitting building projects, with mean
scores of 4.38 and 4.47, respectively. It is not strange that delay in material delivery
causes negatively affects project schedule. This result substantiated the finding of
Enshassi et al. (2009) that delay of material delivery to site was one of the most
influential factor to schedule of construction projects. Factor EM5 shortage of
materials on site or market was ranked second in both project groups, which echoed
the findings of Enshassi et al. (2009) and Kaming et al. (1997). Thus, project delay could
be reduced if material is delivered promptly to prevent shortage of materials on site or
market. Additionally, the other five factors within this category did not obtain mean
scores above 4.00 in both groups of projects, suggesting that their influence on
schedule was less significant.
Labor-related factors. In this category of factors, factor LR1 was ranked top with
mean scores of 3.79 and 3.94 in new and retrofitting projects, respectively. This result
was consistent with the finding of Hwang et al. (2013) that availability of labor on site
was among the top three factors affecting schedule of Singaporean public housing
projects. In Singapore, most of the laborers working on construction site are foreigners.
Thus, the limit imposed by the government on the working visa would influence the
import of labor, thus possibly leading to shortage of labor. Also, it merits attention that
all the three factors in this category obtained mean scores below 4.00, indicating that
the influence of the labor issues on schedule was less significant. This was probably
attributed to the recent efforts made by the Singapores government to enhance the
construction productivity (BCA, 2014c).
External factors. Factor EX2 unfavorable site conditions received the top position
in both new and retrofitting green building projects, yielding mean scores of 4.35 and
4.44, respectively. This result substantiated the previous findings that site conditions,
especially unexpected foundation conditions, significantly contribute to project delay in
Saudi Arabia, Egypt and Australia (Abd El-Razek et al., 2008; Al-Khalil and Al-Ghafly, Green
1999; Walker, 1995). Factor EX2 was followed by EX4, which was ranked second in building
both project groups. The occurrence of accidents during construction usually requires
time spent on investigation and rescue. If the accidents occur in the critical path, they
projects
will result in project delay. Factor EX1 bad weather conditions was ranked third with
mean scores of 4.26 and 4.12 in new and retrofitting projects, respectively, indicating
that schedule performance of Singapores green projects was significantly impacted by 339
weather. This result was similar with the previous findings of Koushki et al. (2005) and
Semple et al. (1994). In Singapore, these external factors, which usually fall outside
a firms control, should be highlighted, as suggested by Low et al. (2009).
Cross-category ranking. According to their mean scores, the 36 factors were
ranked across categories in both new and retrofitting green building projects as well.
As Table V indicates, in the group of new green building projects, the top ten factors
Downloaded by Central Queensland University At 03:19 22 May 2015 (PT)
are CS3, EM6, CR1, CS2, EX2, DR3, CO2, CS1, CS4, and EX4. Additionally, in the
retrofitting group, the top-ten ranking consists of CS3, CS2, EM6, DR3, EX2, CR1, CO1,
CS4, CO2, and EM5.
Consultant cooperation to solve problem was ranked top in both project groups,
suggesting that the cooperation between consultant and other project players was the
most important to project schedule performance. This confirmed the finding of Ning
and Ling (2013) that the peaceful and harmonious affirmative cooperation can enhance
the schedule performance of public projects in Singapore. According to the
interviewees, it was important for consultants to give full cooperation to contractors
or client when their expertise advice or assistance is required. As green building
construction is considered relatively new in construction industry, consultant
proficiency and cooperation is crucial to prevent project schedule performance. Also,
late delivery of material was ranked second and third in new and retrofitting green
building projects, respectively. Materials are vital to keep the construction work going
on, so the execution time of the project may be extended due to delay in the delivery of
the material to the construction site. Ignoring the lead time for material delivery by the
vendors would result in material shortage, as the interviewees indicated. This result
echoed the previous findings of Enshassi et al. (2009) and Kadir et al. (2005).
In addition, to examine the agreement on the factor ranking between new and
retrofitting projects, the Spearmans rank correlation was performed and statistically
tested. In Table V, the correlation coefficient was computed based on the inter-category
ranks of new and retrofitting projects. The coefficient was 0.971 with a p-value <0.001,
implying that there was strong agreement on the factor ranking between new and
retrofitting projects.
As shown in Table VI, the mean scores of each factor category were computed by
taking average mean scores of all the factors under each category. Consultant-related
factors, design team-related factors, and client-related factors were ranked top three in
both new and retrofitting building construction projects. This implied that respondents
considered these three categories of factors had greatest impact on project schedule
performance. As the interviewees stated, both new and retrofitting green building
projects were intricate and required ample supports from the project design team and
construction professions. Additionally, during the design development stage, the
design team and consultants had to spend time in studying and analyzing the system
performance, following the green building design because the green technologies were
still new to the Singaporean construction industry. Furthermore, clients aptitude to
ECAM brief the projects objectives was also very important to avoid misinterpretations
22,3 during project progress and delay in project schedule. The Spearmans rank correlation
coefficient of 0.929 with a p-value of 0.001 indicated a strong agreement on the factor
category ranking between new and retrofitting building projects.
striving toward to reduce construction delay. The solutions for the top cause of delay
are discussed as follows.
The consultant cooperation to solve problem is the most critical to prevent poor
schedule performance in both building projects. Thus, consultant should give full
cooperation to contractor or client when their expertise is needed. Also, the consultant who
is involved in the construction projects should responsibly play his role in monitoring the
project progress and ensuring the project is completed according to the project plan.
In addition, materials are very important to ensure the construction works can move
on, thus the execution time of the project may be extended due to delay in the delivery
of the material to the construction site. Hence, it is highly recommended that material
supply should be recorded and monitored closely in order to have continuous and
sufficient supply to avoid unnecessary delays in construction projects.
Unfavorable site condition is identified as another key factor element to affect the
schedule performance for both new and retrofitting green building construction
projects. The conditions of a site would affect the performance of the construction work
to a large extent which might eventually delay the project schedule. Therefore, is it
important to for project players to work together to provide adequate measures and
provisions to counter the effects of unfavorable site conditions.
New Retrofit
Factor categories Mean Rank Mean Rank
important to reduce delays in green building projects and to ensure the projects are
completed on time. This study attempts to investigate schedule performance of new
and retrofitting green building projects, identify the critical factors affecting the
schedule performance, and provide solutions to improve schedule performance.
To achieve the research objectives, a questionnaire survey and follow-up interviews
were performed. The results indicated that an average of 22 percent of Singaporean
green building projects were plagued with delay and that commercial buildings were
more likely to experience delay than other types of buildings. Also, 65 percent of the
respondents indicated that new green buildings were seldom plagued with delay, while
53 percent rated the likelihood to experience delay between 31 and 60 percent for
ECAM retrofitting projects. In addition, the analysis results showed that retrofitting projects
22,3 had a significantly higher mean likelihood of delay and significantly longer extension
than new projects. As for the factors affecting schedule performance of green building
projects, the result indicated that the cooperation between consultant and other project
players was the most important to project schedule performance. Also, there was
strong agreement on the factor ranking between new and retrofitting green projects, as
342 the Spearmans rank correlation result showed. In terms of ranking of factor categories,
the factors related to consultant, design team, and clients were ranked top three in both
new and retrofitting projects. Finally, a list of solutions to delay problems was
proposed for practitioners.
Although the objectives of this study were achieved, there are some limitations to
conclusions drawn from the results. First, as the sample size in this study was
relatively small, one should be cautious when the analysis results are interpreted and
Downloaded by Central Queensland University At 03:19 22 May 2015 (PT)
generalized. Also, the majority of the respondents were contractors as other project
players were reluctant to respond to the survey. Lastly, the findings from this study are
well interpreted in the context of Singapore.
Nonetheless, an increasing number of countries have initiated programs to embrace
green buildings to deal with the climate change. As schedule performance is an
indicator of project performance and critical to project success (Ling et al., 2009), this
study provides a clear understanding of the schedule performance of green building
projects as well as the critical factors that should be highlighted when constructing
green building projects. Also, strategies to overcome the negative impact of these
factors allow practitioners to better deal with the potential causes of delay and to attain
the schedule performance.
Future study would attempt to set up a benchmarking system for green building
performance, thus allowing the practitioners to compare their performance with the
reference point and helping them learn from the leading organizations through the
adaptation of best practices. Additionally, the organizational issues of contractors or
owners involved in the trend of going green are worth investigation because in the
real-word circumstances it is these organizational issues (e.g. motivation, learning,
culture, and leadership) that influence their capability to go green.
References
Abd El-Razek, M.E., Bassioni, H. and Mobarak, A. (2008), Causes of delay in building
construction projects in Egypt, Journal of Construction Engineering and Management,
Vol. 134 No. 11, pp. 831-841.
Ahmed, S.M., Azhar, S., Kappagantula, P. and Gollapudi, D. (2003), Delays in construction:
a brief study of the Florida construction industry, in Berryman, C.W. (Ed.), Proceedings of
the 39th Annual Conference, Associated Schools of Construction, University of Nebraska
Lincoln, Lincoln, NE, pp. 257-266.
Akinsola, A., Potts, K., Ndekugri, I. and Harris, F. (1997), Identification and evaluation of factors
influencing variations on building projects, International Journal of Project Management,
Vol. 15 No. 4, pp. 263-267.
Akintoye, A. (2000), Analysis of factors influencing project cost estimating practice,
Construction Management and Economics, Vol. 18 No. 1, pp. 77-89.
Al-Khalil, M.I. and Al-Ghafly, M.A. (1999), Important causes of delay in public utility projects in
Saudi Arabia, Construction Management & Economics, Vol. 17 No. 5, pp. 647-655.
Al-Momani, A.H. (2000), Construction delay: a quantitative analysis, International Journal of Green
Project Management, Vol. 18 No. 1, pp. 51-59.
building
Arditi, D., Akan, G.T. and Gurdamar, S. (1985), Reasons for delays in public projects in Turkey, projects
Construction Management and Economics, Vol. 3 No. 2, pp. 171-181.
Assaf, S.A. and Al-Hejji, S. (2006), Causes of delay in large construction projects, International
Journal of Project Management, Vol. 24 No. 4, pp. 349-357.
BCA (2009), 2nd Green Building Masterplan, Building and Construction Authority, Singapore. 343
BCA (2013a), $100 Million Green Mark Incentive Scheme For Existing Buildings (GMIS-EB),
available at: www.bca.gov.sg/greenmark/gmiseb.html (accessed December 1, 2014).
BCA (2013b), Enhanced $20 Million Green Mark Incentive Scheme For New Buildings (GMIS-
NB), available at: www.bca.gov.sg/greenmark/gmis.html (accessed January 15, 2014).
BCA (2014a), 3rd Green Building Masterplan, Building and Construction Authority, Singapore.
Downloaded by Central Queensland University At 03:19 22 May 2015 (PT)
BCA (2014b), Construction demand for 2014 to remain strong, available at: www.bca.gov.sg/
Newsroom/pr09012014_BCA.html (accessed February 1, 2014).
BCA (2014c), Construction productivity and capability fund, available at: www.bca.gov.sg/cpcf/
cpcf.html (accessed April 2, 2014).
Belassi, W. and Tukel, O.I. (1996), A new framework for determining critical success/failure
factors in projects, International Journal of Project Management, Vol. 14 No. 3, pp. 141-151.
Belout, A. (1998), Effects of human resource management on project effectiveness and success:
toward a new conceptual framework, International Journal of Project Management, Vol. 16
No. 1, pp. 21-26.
Chan, D.W. and Kumaraswamy, M.M. (1997), A comparative study of causes of time overruns in
Hong Kong construction projects, International Journal of Project Management, Vol. 15
No. 1, pp. 55-63.
Chua, D., Kog, Y. and Loh, P. (1999), Critical success factors for different project objectives,
Journal of Construction Engineering and Management, Vol. 125 No. 3, pp. 142-150.
Dascalaki, E. and Santamouris, M. (2002), On the potential of retrofitting scenarios for offices,
Building and Environment, Vol. 37 No. 6, pp. 557-567.
Dissanayaka, S.M. and Kumaraswamy, M.M. (1999), Evaluation of factors affecting time and
cost performance in Hong Kong building projects, Engineering, Construction and
Architectural Management, Vol. 6 No. 3, pp. 287-298.
Enshassi, A., Al-Najjar, J. and Kumaraswamy, M. (2009), Delays and cost overruns in the
construction projects in the Gaza Strip, Journal of Financial Management of Property and
Construction, Vol. 14 No. 2, pp. 126-151.
Frimpong, Y., Oluwoye, J. and Crawford, L. (2003), Causes of delay and cost overruns in
construction of groundwater projects in a developing countries: Ghana as a case study,
International Journal of project management, Vol. 21 No. 5, pp. 321-326.
Glavinich, T.E. (2008), Contractors Guide to Green Building Construction, John Wiley & Sons.,
Hoboken, NJ.
Gou, Z., Prasad, D. and Siu-Yu Lau, S. (2013), Are green buildings more satisfactory and
comfortable?, Habitat International, Vol. 39, pp. 156-161.
Gravetter, F. and Forzano, L.-A. (2012), Research Methods for the Behavioral Sciences, Cengage
Learning, Belmont, CA.
GreenBiz (2005), Green Building Technique: A Two-Minute Briefing on Key Business
Environmental Issues, GreenBiz Group Inc., Oakland, CA.
Hansen, S.J. (2006), Performance Contracting: Expanding Horizons, Fairmont Press, Lilburn, GA.
ECAM He, H.Z. and Kua, H.W. (2013), Lessons for integrated household energy conservation policy
from Singapores southwest eco-living program, Energy Policy, Vol. 55, pp. 105-116.
22,3
Hwang, B.G. and Leong, L.P. (2013), Comparison of schedule delay and causal factors between
traditional and green construction projects, Technological and Economic Development of
Economy, Vol. 19 No. 2, pp. 310-330.
Hwang, B.G. and Tan, J.S. (2012), Green building project management: obstacles and solutions
344 for sustainable development, Sustainable Development, Vol. 20 No. 5, pp. 335-349.
Hwang, B.G. and Yang, S. (2014), Rework and schedule performance: a profile of incidence,
impact, causes and solutions, Engineering, Construction and Architectural Management,
Vol. 21 No. 2, pp. 190-205.
Hwang, B.G., Zhao, X. and Goh, K.J. (2014a), Investigating the client-related rework in building
projects: the case of Singapore, International Journal of Project Management, Vol. 32
Downloaded by Central Queensland University At 03:19 22 May 2015 (PT)
Technology at the Central Queensland University, Australia. He holds the PhD Degree from the
National University of Singapore (NUS). His current research interests are in the areas of risk
management, sustainable construction, as well as rework and productivity. Dr Xianbo Zhao is the
corresponding author and can be contacted at: b.zhao@cqu.edu.au
Lene Lay Ghim Tan is a Customer Service Executive at the Pacific International Lines,
Singapore.
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com