Electrical (Project Engineering and Commissioning, O&M) Areas- ,AHU , Process Plant Utilities,
CHILLER , BMS, POWER PLANT , BOILER,CHP,AHS , RMHS, ESP ,DSS, DES, COKE OVEN,BFP ,
THERMOPAC , L.P.BOILER, E.T.P.

C.M.V.P. Certified Measurement And Verification Professional

Asst. Mgr. Electrical 7years ( Projects 6+, O&M 2+ yrs)

Industry- Steel, Power,RMHS

Major Concentration : KAIZEN , TQM, JIT

Professional Highlights

Present Employer

BOMBAY RAYON FASHIONS LIMITED. , Mumbai , Tarapur 2014 to till date

Projects
Erection & Commissioning of 10 MVA,8MW generator (make - TDPS),
Erection & Commissioning of 4 Nos. of transformer (11kv/440) 2.5MVA x3 , 3MVA x 1
11kv switch gears (8 nos HT breaker, make Siemens), LT PCC & AUXULLARY panels of CPP, all motors,
ACC, ESP, COAL handling plant.
Responsible for the upcoming 360kl RO plant Erection and commissioning.(CAPEX)
Responsible for the upcoming 15TPH ,6TPH boiler E&I Erection and commissioning.(CAPEX)

O&M
O&M of power plant 8MW co generation type complete electrical and instrumentation (Generator make TOYO
DENKI Power SYSTEM.10MVA.
O&M , installation of UPS 4000VA Dilligent power system
O&M of transformer 2500KVA power distribution transformer , generator
O&M OF INSTRUMENTAION OF POWERPLANT , THERMOPAC , L.P. BOILER 22T, AIR HANDLING UNIT,
CHILLER SYSTEM UTILITIES
O&M of 33/11kv switch yard of MSEDCL And BOMBAY RAYON FASHIONS Ltd
O&M of 1500x4 cfm Atlas Copco SCREW compressors.
O&M of SF6 IOCG Breaker.
O&M of switchgears for MCC ,PCC , VCB, APFC 350kVAR x 3 panel, 415v,6.6Kv
O&M of DM Plant , RAW WATER SOFT WATER SUPPLY
O&M of turbine control panel , excitation control panel, generator control panel
O&M of all lighting and air conditioning panels
O&M of control and power panels.
O&M of 1500KVA DG Powerica Make.
Purchase and Materials requisition through internal enterprise software NOW

Previous Employer

ENVIIRO BULKK HANDLING SYSTEM Pvt,Ltd., PUNE, 2012 to 2014

Designation : Sr Engineer
Role : Projects
Preparation of concept design, Working out Preliminary budget estimation and Project
timescale. Finalizing consultant for the projects and able to feed basic requirement to consultant.
Review, Comment/Rectify and approval of Design Basis Report , Detail Design Engineering, Drawings and
tender packages.
Assisting Contract team in vendor selection. Preparation of Work Order
Preparation of Offer Letter for filling quotation.
Co-ordinate with consultant and vendor for Shop drawing preparation
Assist execution team in design related issues for successful completion and handing over Commissioning of
16 VCB feeders 77 ACB feeders 165 DOL/RDOL/Star Delta feeders.
Commissioning of all the feeders through s7-400 SIEMENS PLC.
Commissioning of ESP for 4x135MW BOILER
Proper planning, execution and coordinating with client and contractor. MODIFICATION IN PROGRAM OF
BWSR (platform SIEMENS S7-400)
Commissioning of 2400Tph BUCKET WHEEL Stacker cum Reclaimer SDA make China. Commissioning of
10x5.5kw through Schneider Altivar 71 VVF Drive.
Commissioning of GE AF 650GP 22kw drive 10 nos. for Mobile SCREEN. Commissioning of Sinamics
(siemens) drive 15kw 10 nos. for vibro feeders. Commissioning of Hagglund Hydraulic Power Unit pec
En326, 55kw & 22k

ACCOMPLISHMENTS:

Lead Engineer for Detail Engineering of CHP 2x650 Tph


Lead Engineer for commissioning of Bucket wheel stacker reclaimer 650 Tph CHINA SDA make at JSPL
4x135MW
COMAPNY BENEFIT- PROJECT COSTING LOWERED by Prompt Technical Action.

Appreciation From Client JSPL 4x135MW for commissioning of CHP2x650 Tph


Appreciation From SDA China for commissioning of BSWR
Support The package through PLC S7-400 Siemens and cary out necessary modification

Previous Employer

SESA GOA LTD, PANAJI,GOA 2010 to 2011

Designation : Engineer
Role : Projects
Detail Engineering(electrical &instrumentation )of the total coke oven plant project
0.28MTPA Preparation of BOM, TRAY ROUTING,EARTHING LAYOUT,CABLE SCHEDULE
Preparation of technical Drawing as per co-ordinates Technical Negotiation with competent Bidders Execution
of electrical package
Installation and commissioning of 3MVA Transformer 11kv/415v
Installation and commissioning of PCC ,MCC Panels of CHP,CSP,OVEN AREA,STAMPING STATION,
COKE&COAL CARS

ACCOMPLISHMENTS:
EFFICIENT TEAM WORK BY INSTATLLATION AND COMMISSIONING OF TRANSFORMER and PCC
IN24HOURS THEREBY SAVING A LOT TO THE COMPANY.

CERTIFICATION

CMVP (Certified Measurement & Verification Professional)


Auto Cad Drafting & Modeling 2D,3D
Certified Automation Engineer

DECLARATION

I do hereby declare that the information furnished above is true to the best of my knowledge.

Date :
Place:
Ajit Kumar Sahoo

Das könnte Ihnen auch gefallen