Sie sind auf Seite 1von 4

What temperature

drop is required and


how much concrete
must be cooled?

B y Wa r d R . M a l i s c h

ts summertime in Atlanta

I and job documents specify a


maximum delivered con-
crete temperature. Whats
the most economical way to
produce concrete at that temperature?
To answer that question, you first
need to ask a few other questions.
Whats the specified temperature?
You have many more options in
Using coarse aggregate thats been doused with cold water can lower concrete temperature by 10
delivering concrete at 70 to 75F
degrees. A solid stream instead of a spray minimizes cold waters contact with warm air.
than you do if 60F is the target
temperature.
Whats the difference between the Available cooling options Batching bagged or block ice. This
temperatures of the concreting ma- Once youve answered these ques- is one of the simplest and most eco-
terials and specified concrete tem- tions, you can evaluate your options. nomical methods for cooling concrete
perature? Some require little or no capital in- on pours less than 500 cubic yards, or
Are there any natural sources of cold vestment, while the capital cost for in areas where the cooling season is
water near your plant, such as others is significant. short. If you buy the ice in preweighed
mountain streams or deep wells? Cooling aggregate by evaporation. bags, use it to replace an equal weight
How long is the cooling season in Because coarse aggregate makes up the of mixing water.
your area? If its only one or two largest portion of concrete, reducing Heres a sequence that has worked for
months, you cant afford to put much aggregate temperature causes the one producer. Put the ice in the truck
money into systems requiring high greatest reduction in concrete temper- first, followed by two tons of coarse ag-
capital costs unless youre supplying ature. Simply wetting stockpiles cools gregate to help grind up the ice. Add
concrete for a large-volume project. them by evaporation, but theres a some of the remaining mixing water,
What volume of concrete requires limit to the amount of cooling that oc- but hold out about one-fourth of the
cooling? Again, producing small vol- curs. Wet aggregates wont cool as required amount. Next add cement,
umes of cooled concrete, say 500 cu- much in humid climates because less sand, the rest of the coarse aggregate,
bic yards or less, doesnt justify high evaporation takes place. However, and the last of the mixing water.
capital costs. even at a wet-bulb temperature of 80F Another alternative is buying block
Do plant site conditions permit you and air temperature in the mid-90s, ice and a crusher thats also equipped
to use all of the cooling options? evaporation can still cool aggregate with a conveyor for discharging the ice
Chiller systems supply cold water for piles to around 84F. Thats enough to into concrete trucks.
mixing water and possibly cooling lower the concrete temperature by Ice cools concrete by cooling mixing
aggregates. But cooling aggregates about 4 degrees. A 6-degree concrete water and by taking out heat as it melts.
might require high site-preparation temperature reduction is probably Each pound of ice takes 144 Btu out of
expenses, especially if in-ground stor- about the best you can expect from the concrete as it melts. Using ice to re-
age of the cooled water isnt feasible. evaporative cooling of aggregate alone. place half of the water batched at air
temperature can drop concrete temper- ate a compressor and controls. Be- directly on a coarse aggregate stockpile
ature as much as 12 to 20 degrees. cause they use electricity, chiller oper- quickly brings aggregate temperature to
There are limitations to this method, ational costs vary with electrical rates. about 5 to 10 degrees above the cold
however. It can be used only for dry- In some areas, local utility companies water temperature. Using 700 gallons of
batched transit-mixed concrete, and offer special incentive rates if chilling water per minute, a 500-ton pile of
the amount of ice that can be used is systems run only during off-peak coarse aggregate can be cooled by more
limited by the water content of the hours. The desired water-temperature than 25 degrees in less than 40 minutes.
concrete. Thus, there may be condi- drop also affects cost. Electrical cost Thats enough cooling to lower the
tions under which the target tempera- for reducing water temperature from concrete temperature about 10 degrees.
ture isnt reached by replacing all of 60 to 40F is about half that for re- Theres little capital expense if the wa-
the mixing water with ice. You also ducing it from 80 to 40F. Operating ter is naturally occurringcool well wa-
need a place to store the ice at the costs for electricity alone normally ter or snow-melt creek water. Then you
plant, and adding it is labor intensive. range from 4 to 12 per cubic yard of need only a water pump and piping to
Chilling mixing water. You can chill concrete. move the water to aggregate piles, a sys-
mix water with chillers that supply on- Whenever you use chilled water, be tem for directing streams of water onto
ly cool water, or with chillers that also sure that the water tank, piping, and the piles, and a means for draining ex-
serve as reverse-cycle heat pumps. The weigh batcher are well insulated. Oth- cess water from the piles. Any such sys-
latter units have another advantage: erwise, heat from the plant will in- tem would also need to meet local
They can be used to heat mixing water crease water temperature and drive up process water discharge regulations.
for cold-weather conditions. operating costs. When natural water temperature is-
Chillers that cool are designed to A chilled-water system designed to nt low enough, water chilling equip-
eject heat either to the air or to a water take 55F well water down to 35F may ment is needed. Equipment require-
source. Air systems are installed out- be able to drop the mix temperature 5 ments include:
doors, allowing heat to be easily eject- degrees. But if chilled mix water and Adequate water storage capacity
ed into ambient air. Water systems evaporative aggregate cooling dont normally about one days total
commonly use well water for the heat help you reach the target temperature, chilled water demand
sink, but can also use cooling towers. other steps are needed. Fire-hose-type nozzles for wetting
All chillers require a refrigerant Cooling aggregates with cold water. down aggregate piles
typically R22and electricity to oper- Applying a solid stream of cold water High-volume pumps for moving
chilled water to the aggregate piles
A chilled-water system that consis-
tently produces 40F or colder water
A water distribution and drainage
system that complies with local
process-water discharge regulations.
Aggregate cooling requires large vol-
umes of chilled water, so adequate stor-
age capacity is needed. Producing 800
cubic yards of concrete cooled 12F dai-
ly might require 60,000 gallons of stor-
age capacity. Insulated, above-ground
steel tanks of that capacity could cost
twice as much as an insulated pit for
ground storage. But ground storage is-
nt feasible if the water table is too high
or bedrock is too near the surface.
In arid climates, cooling towers are
sometimes used to pre-cool water, but
because mechanical water chillers are
usually needed as an adjunct cooling
system, most producers opt for chillers
without cooling towers. And in cli-
mates that arent as dry, the mechani-
In plants with ice makers, some cal chillers supply all of the cooling
insulated day tanks can deliver needs. Unit sizes are dictated by the
more than 2,000 pounds of ice amount of cooling water needed. Us-
per minute to the weigh hopper. ing a combination of aggregate cooled
with chilled water and chilled mixing
water will reduce concrete tempera-
ture by 10 to 22 degrees.
How a water-source heat pump works
Coarse aggregate cooling with
chilled air. You can cool coarse aggre- Vented storage tank
gate by blowing mechanically chilled
air up through specially designed bins. 2" spray foam
Capital costs are typically more than insulation with sealer
those for stockpile cooling, but the
Thermostat indicator
benefits include improved aggregate
temperature control, lower electrical
operating costs, and cooling to a much Batching pump
lower temperature than that achieved
in stockpiles. For example, this method
can cool 34-inch aggregate to 35F and
112-inch aggregate to below freezing.
The chilled air can be produced by
exchanging the air with chilled water
or chilled glycol. Alternatively, a direct Freshwater in Discharge water out
exchanger uses the refrigerant directly
in the air exchanger. A central chiller is
normally used to produce chilled mix This heat-pump system includes several parallel-connected modules that can be removed or added
water while also cooling the chilled air. quickly to adjust cooling capacity or to replace a failed module.
Specially selected blowers achieve the
proper volume and pressure for the Cooling with ice makers. Large-vol- cause of this, long-term storage isnt
chilled air thats blown through the ume cooling needs can often be met feasible and the ice must be used more
bins. The same air exchanger-blower most economically by making ice at quickly after its produced. In these
combinations can heat aggregates in the concrete plant and adding it at the plants, there are two different ways of
the winter when coupled with a water mixer drum. Use it as a direct substi- adding ice to the mixer. Rakes or con-
heater heat source. tute for batched water on a pound-for- veyors automatically move it from the
Chilled-air coarse aggregate cooling pound basis. Most ice makers for con- storage bin to a pneumatic- or screw-
is an economical option when large crete cooling produce flake ice (about conveyor system that takes it to a day
volumes of concrete must be cooled 1
1 6-inch thick), but ice makers that tank above the weigh hopper. Another
and stockpile cooling isnt practical. produce plate ice (about 18-inch thick) option is dispensing ice from storage
Its also cost effective when required have sometimes been used when to a separate scale, then blowing it di-
concrete temperatures are lower than longer concrete mixing times allow rectly into the mixing drum. Such sys-
can be achieved with stockpile cooling this thicker ice to completely melt. tems can deliver more than 1,000
using chilled water. Flake ice makers produce ice contin- pounds of ice per minute to the plant
Sand cooling with chilled air. Sand uously with individual capacities up to weigh hopper or mixer drum.
can now be effectively cooled as it 55 tons per day. The ice maker feeds a As with bagged ice, flake or plate ice
flows through a rotating drum along refrigerated, insulated storage bin that has a high cooling capacity because it
with cooled air. The rotary drum for is sized based on the amount of ice absorbs large amounts of heat by melt-
this patented process is similar to dri- used and the pour schedule. The bin ing. Concrete temperature reductions
ers used in asphalt plants, with special also contains an ice rake used in the up to 30 degrees are possible when all
flighting, retention time, and breach- discharge cycle. Storage capacities can of the batched mixing water is re-
ing for entering and exiting air. range from 12 tons to more than 250 placed by ice. The ice systems give
Sand can be cooled to 35F with this tons per bin-rake system. When ice is consistent cooling results starting with
system. Although sand coolers are needed, the rake automatically dis- the first mix of the day, and interrup-
more efficient and have a lower capital charges ice from the storage bin to a tions in concrete production dont
cost than ice production plants, they pneumatic- or screw-conveyor system pose a problem since the ice stays cold
always cost more than coarse aggregate that delivers it to a live-bottom, insu- and free flowing in an insulated bin.
cooling. Thus their use is generally lated day tank located above the batch- A significant capital investment is the
considered only after coarse aggregate plant weigh hopper. Day tanks can de- primary disadvantage of ice plants.
cooling is already in use. liver more than 2,000 pounds of ice However, at the end of a project, all of
By adding a burner to the drum, per minute to the weigh hopper. the equipment and most of the invest-
sand coolers can also be used as sand Plate ice plants usually include insu- ment can be recovered by moving it to
heaters during cold weather. lated but not refrigerated storage. Be- a new site. Buying and installing a flake
ice maker system with a nominal capac- several more minutes at remote truck- References
ity of 10 tons per day, a 12-ton storage cooling stations. Needed additional in- 1. Cooled Concrete Controls Cracking
bin, a 2-ton day tank, and the required jection time ranged from seven minutes for Base Mat Pour,Concrete Construc-
conveying systems will cost about during the heat of the day to a more tion, November 1988, pp. 1032-1033.
$300,000, depending on the length and typical two to three minutes. 2. Michael Lee, Economical Cooling
complexity of the external conveying Even for large-volume pours exceed- of Hot-Weather Concrete, Concrete
system. The cost per ton of production ing 10,000 cubic yards, costs for liquid C o n s t r u c t i o n , September 1989, pp.
drops dramatically for larger ice plants. nitrogen alone will be 30 to 55 to 791-796.
Liquid nitrogen cooling. Injection cool a cubic yard 1 degree. The nitro- 3. Anne Smith, Water-Source Heat
with liquid nitrogen can cool concrete gen tank, cooling stations, and labor Pump Economically Controls Concrete
to the very low temperatures some- can cost an additional $20,000 to Temperature, Concrete Construc-
times required for base mats and other $60,000 per cooling season. tion, February 1990, pp. 234-236.
mass-concrete pours. This cooling sys- Whatever your choice of cooling
tem will work for central-mixed con- method, remember to follow proper
crete, but for high-production plants, hot-weather concreting practices. Use
cooling capacity is usually limited to 3 admixtures and supplementary ce-
to 5F. Additional cooling is accom- menting materials when needed to
plished in truck mixers, using hydrauli- control setting time. Paint trucks a
cally operated arms to move a nitrogen light color to reduce heat gain from PUBLICATION #J970317
lance into the trucks charging hopper. solar radiation, and schedule trucks to Copyright 1997, The Aberdeen Group
On one project, 112 minutes of injection avoid long waits at the jobsite. All rights reserved
at the central mixer was followed by

Das könnte Ihnen auch gefallen