Extension of Time Assessment Flow Chart PAM 2006 Form of Building Contract

YES

Contractor gives Notice of his Has Contractor Architect to determine any


used best Extension of Time Entitlement
intention to claim for Extension of
endeavours (SC within six weeks of Claim and
Time (Sub-Clause 23.1(a) NO
23.6) supporting particulars

Are Works
Was Notice
Delayed beyond
Issued within Date for
NO Time Limits? YES NO
Completion

Does Delay occur


YES as a result of Sub- YES
Clause 23.5(b) NO

Contractor submits claim for Architect to Issue Certificate of


Extension of Time with supporting Extension of Time SC 23.4
particulars (Sub-Clause 23.1(b)

YES

Architect Issues Certificate of


Is Delay a Result Practical Completion
Was Claim
of one of the
Submitted within
NO Relevant Events NO
Time Limits ? in 23.8

YES Within twelve weeks of CPC the


Architect May review and amend
any EOT SC 23.10

Architect Rejects Claim giving


Notice to Contractor