1 3/5/2016 Make & installed the safe guard of motor sheet rolling machine.
Fire truck No.3 of Safety Section reverse allarm not bilt in , Garage team
2 10/5/2016
installed the reverse allram on Fire Truck.
Remove the sealing fan in Tool Room due to heing with "C" clamp it is danger,
3 23-05-2016
install a braket fan.
4 30-05-2016 Change the night light switch location due to easily approach at the time of use.
Modified & rectify the alternator of ambulance to make it working again till
5 21-06-2016
arrival of replacement part.
Identify water leakage & replacement need for the hose pipe of Fire Hydrant in
6 18-07-2016
Mech. Workshop
EMENT
NAME
M. Iqbal
Abdul Salam
Zafar Iqbal
Hamza Nouman
Abdul Salam
Hamza Nouman
SAFETY SUGGESTIONS FOR IMPROVEMENT
Related
SR.NO. DATE INITIATIVE NAME
Departments
1 10/5/2016 Roof crack of Mechanical Workshop work not done Civil Hamza Nouman
2 10/5/2016 Motor bike shied required for staff Admin Sajjad Ahmed