Sie sind auf Seite 1von 1

GENERAL NOTES

Key Plan

G1 ALL STRUCTURAL DRAWINGS SHALL BE READ IN CONJUNCTION WITH ALL OTHER DRAWINGS,
DOCUMENTS, SPECIFICATIONS ETC. AS MAY BE ISSUED DURING THE COURSE OF THE CONTRACT.
S11 PROVIDE MINIMUM LENGTH BEARING OF 200mm FOR ALL STEEL BEAMS BEARING ON MASONRY C15 THE CONTRACTOR IS RESPONSIBLE FOR PROVISION OF, AND SCHEDULING OF CHAIRS, SPACERS
ETC. FOR THE SUPPORT OF REINFORCEMENT.
STANDARD NOTATION LEGEND
AND CONCRETE AND A MINIMUM OF 100mm ON STRUCTURAL STEEL, UNLESS OTHERWISE NOTED
ALL DISCREPANCIES SHALL BE REFERRED TO THE ENGINEER FOR DECISION BEFORE OR SHOWN. C16 SURFACE FINISHES:
PROCEEDING. S12 CENTRE BEARING PLATES UNDER BEAMS UNLESS OTHERWISE NOTED OR SHOWN. CONCRETE SURFACES TO - TAMPED SURFACE FINISH T12-250
G2 DIMENSIONS SHALL NOT BE OBTAINED BY SCALING DRAWINGS S13 BEARING PLATE DIMENSION GIVEN FIRST INDICATES SIDE PARALLEL TO BEAM WEB. RECEIVE FUTURE SCREED SPACING (mm)
N
G3 LEVELS SHOWN ARE IN METERS ABOVE NEW ABU DHABI DATUM LEVEL (NADD) S14 NO STRUCTURAL STEEL SHALL BE CUT IN THE FIELD UNLESS REVIEWED AND AGREED BY THE BLINDING CONCRETE - TROWEL FINISH BAR SIZE (mm)
ENGINEER. PLANT ROOMS - POWER FLOATED FINISH TYPE OF REINFORCEMENT
G4 THE CONTRACTOR SHALL SUBMIT RECORD DRAWINGS OF ALL "AS BUILT" WORKS FOR THE
ENGINEER REVIEW & AGREEMENT. S15 WHERE COLUMNS ARE STABILIZED BY WALLS PROVIDE COLUMN ANCHORS AT ABUTTING WALLS. WET AREAS, AMENITIES BLOCKS, KITCHENS - TROWEL FINISH 6T12

A
PROVIDE TEMPORARY BRACING UNTIL WALLS ARE BUILT TIGHTLY TO COLUMNS. TO RECEIVE WATER PROOF MEMBRANE

BL
G5 SETTING OUT DIMENSIONS AND LEVELS SHOWN ON THE DRAWINGS SHALL BE VERIFIED BY BAR SIZE (mm)

QI
S16 ALL WELDS EXPOSED TO VIEW SHALL BE GROUND SMOOTH. ROOF AREAS AND CARPARK ROOF AREAS - POWER FLOATED FINISH
THE CONTRACTOR. THE ENGINEER SHALL BE NOTIFIED OF ANY DISCREPANCIES PRIOR TO TYPE OF REINFORCEMENT
CONSTRUCTION S17 WHERE MOMENT CONNECTIONS ARE CALLED FOR BUT FORCES ARE NOT INDICATED, DESIGN TO RECEIVE SLIP MEMBRANE Notes
CONNECTIONS FOR FULL MOMENT CAPACITY OF THE SMALLER MEMBER JOINED. NUMBER OF BARS
LOADING DOCK AREAS - POWER FLOATED FINISH
1. ALL DIMENSIONS ARE IN MILLIMETER U.N.O.
G6 ALL WORKMANSHIP AND MATERIALS SHALL BE IN ACCORDANCE WITH THE CURRENT BRITISH
STANDARDS UNLESS NOTED OTHERWISE (U.N.O) AND THE REQUIREMENTS OF MUNICIPALITY
S18 SPLICES SHALL BE DESIGNED TO DEVELOP THE FULL CAPACITY OF THE MEMBER AT THE POINT
OF THE SPLICE. MEMBERS SHALL NOT BE SPLICED AT POINTS OF MAXIMUM STRESS. NO SPLICES
C17 FORMED FINISHES:
EXTERNAL BURIED - FORMED FINISH
REINFORCEMENT 2. ALL THE LEVELS ARE IN METER.
3. REFER TO THE ARCHITECTURAL DRAWINGS FOR THE RELATION BETWEEN
SHALL BE MADE UNLESS SHOWN ON THE DRAWINGS OR REVIEWED AND AGREED BY THE ENGINEER
G7 ALL DIMENSIONS ARE IN MILLIMETRES AND ALL LEVELS ARE IN METERS UNLESS NOTED INTERNAL FACE OF BURIED STRUCTURES - NORMAL FAIR FACED FINISH THE BUILDING LEVELS AND THE PROJECT DATUM.
S19 PROVIDE WELDED STIFFENER PLATES ON BOTH SIDES OF THE WEB OF BEAMS AT POINTS OF 4. GENERAL NOTES, STANDARD DETAILS, WATERPROOFING AND MATERIAL
OTHERWISE CONCENTRATED LOAD INCLUDING BEAMS SUPPORTING COLUMNS OR RUNNING OVER TOPS OF SOFFITS/COLUMN /WALLS, UNO - NORMAL FAIR FACE FINISH PROPERTIES REFER TO DRAWINGS. " S001 - S005"
G8 DETAIL R.C. SHOP DRAWINGS AND BAR BENDING SCHEDULES SHALL BE PREPARED BY THE COLUMNS CIRCULAR COLUMNS - NORMAL FAIR FACE FINISH 5. THIS DRAWING SHOULD BE READ IN CONJUNCTION WITH THE RELATIVE
CONTRACTOR AND SUBMITTED TO THE ENGINEER FOR REVIEW. WORK SHALL NOT COMMENCE EXISTING BUILDING
S20 CONNECT ALL COLUMNS TO THE BASE PLATES FOR THE LARGER OF THE FOLLOWING FORCES IN C18 REFER ALSO TO THE SPECIFICATION AND ARCHITECTURAL DRAWINGS FOR TYPE OF CONCRETE ARCHITECTURAL, MEP AND CIVIL DRAWINGS. COORDINATE ALL
UNTIL REVIEWED AND ACCEPTED. REVIEW OF THESE DRAWINGS DOES NOT ALLEVIATE THE PENETRATIONS CONDUTES AND EQUIPMENT REQUIREMENTS.
ADDITION TO OTHER FORCES SHOWN: SURFACE FINISH REQUIRED
CONTRACTOR'S RESPONSIBILITIES.
A) AT BRACING FOR THE HORIZONTAL COMPONENTS FROM THE BRACING. COLUMN OR WALL UNDER
G9 FOR GROUND WATER TABLE REFER TO THE SOIL INVESTIGATION REPORT.
B) FOR 3% OF THE FACTORED VERTICAL COLUMN LOAD APPLIED HORIZONTALLY. C19 NON STRUCTURAL CONCRETE USED TO MAKE UP LEVELS & INFILL VOIDS AS SHOWN ON THE (INCLUDING HEADER BEAMS)
G10 WHERE DEWATERING IS TO BE CARRIED OUT THE SYSTEM IS TO BE SUBMITTED OF TO THE S21 SHAPE AND SIZE OF GUSSET PLATES TO CLEAR ARCHITECTURAL FINISHES AND MECHANICAL DRAWINGS SHALL BE A LIGHTWEIGHT CONCRETE WITH A MAXIMUM DENSITY OF 15kN/m AND
ENGINEER FOR REVIEW PRIOR TO INSTALLATION DUCTS, PIPES AND ELEVATOR SHAFTS. COMPRESSIVE STRENGTH 15N/mm , AS AGREED WITH THE ENGINEER.
S22 PROVIDE ALL ANCHOR BOLTS, CAST IN PLATES WITH ANCHORS AND ANCHORS REQUIRED TO COLUMN OR WALL UNDER

MASONRY S23
CONNECT STRUCTURAL STEEL TO CAST-IN-PLACE CONCRETE.
THE ENDS OF ALL TUBULAR MEMBERS ARE TO BE SEALED WITH 5mm THICK PLATES AND
PRECAST FLOOR AND PANEL AND OVER.

M1 ALL MASONRY CONSTRUCTION SHALL CONFORM TO BS 6073, BS 5628 AND SPECIFICATIONS. CONTINUOUS FILLET WELDS UNLESS NOTED OTHERWISE. PROVIDE WEEP HOLES IN TUBULAR
MEMBERS USED IN AN EXTERIOR ENVIRONMENT. END PLATES SHALL MATCH TUBE SHAPE UNO.
DESIGN AND CONSTRUCTION CARRIED
COLUMN OR WALL OVER.
M2 ALL CONTROL JOINTS ARE TO BE FILLED WITH COMPRESSIBLE/ EXPANDABLE FILLER, TO MEET
S24 MAINTAIN TEMPORARY BRACING UNTIL COMPLETION OF THE ENTIRE STRUCTURE INCLUDING
A 2 HOUR FIRE RATING. CP1 PRECAST, PRESTRESSED CONCRETE ELEMENTS SHALL BE USED TO FORM THE DECKS WHERE
STEEL DECK AND GRATING OR OTHER ELEMENTS WHICH ARE PART OF THE LATERAL LOAD
M3 ALL WALL FINISHES MUST BE JOINTED AT THE WALL JOINTS TO PREVENT UNCONTROLLED SHOWN ON THE DRAWINGS. ALL GAPS BETWEEN UNITS SHALL BE FILLED WITH GROUT AND UPSTAND
RESISTING SYSTEM.
CRACKS IN THE WALL FINISHES. REINFORCED AS REQUIRED. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE DESIGN OF
S25 DETAILED STRUCTURAL STEEL SHOP DRAWINGS, CONNECTION DETAILS AND CALCULATIONS
M4 GREAT CARE MUST BE TAKEN TO ENSURE THAT MORTAR DROPPINGS AND OTHER HARD SHALL BE PREPARED BY THE CONTRACTOR IN ACCORDANCE WITH BS 449 AND SUBMITTED AS THE ELEMENTS AS A WHOLE. LAYOUT DRAWINGS AND DETAILS SHALL BE FORWARDED TO THE
MATERIALS DO NOT FALL OR REMAIN IN THE CONTROL JOINTS. POLYSTYRENE TO BE PLACED DEFINED IN THE CONTRACT. FABRICATION OR INSTALLATION SHALL NOT COMMENCE UNTIL ENGINEER FOR REVIEW & AGREEMENT PRIOR TO CASTING THE ELEMENTS.
IN ALL VERTICAL JOINTS DURING CONSTRUCTION IN MASONRY TO AVOID MORTAR DROPPINGS REVIEWED AND ACCEPTED. REVIEW OF THESE DRAWINGS DOES NOT ALLEVIATE THE CP2 REFER TO THE SPECIFICATION FOR REQUIREMENTS.
SECTION
FILLING THE JOINTS. CONTRACTOR'S RESPONSIBILITIES. COORDINATE THE INPUT OF ALL TRADES ON THE SHOP
M5 ALL JOINTS ARE TO BE REVIEWED AND AGREED BY THE ENGINEER OR HIS REPRESENTATIVE NUMBER
DRAWINGS.
PRIOR TO USE. SURFACE FINISH A
S26 REFER TO ARCHITECTS DRAWINGS FOR ARCHITECTURAL DETAILS/ REQUIREMENTS OF
M6 WHERE FILLER MATERIALS ARE NOT SPECIFIED BY A TRADE NAME, THE CONTRACTOR SHALL FIXINGS & CONNECTIONS. 004
SUBMIT THE NAME OF HIS PROPOSED FILLERS TO THE ENGINEER FOR REVIEW PRIOR TO USE. TOP - ROUGH(TO RECEIVE STRUCTURAL TOPPING)
CP3
M7 THE CONTRACTOR'S ATTENTION IS DRAWN TO THE MANUFACTURER'S REQUIREMENTS WITH MOVEMENT JOINTS BOTTOM - SMOOTH (OFF STEEL FORMS)
DRAWING REFERENCE
NUMBER
A ISSUED FOR TENDER RBU BM* AH* 08.03.15

REGARD TO THE POSITION OF THE FLEXIBLE ANCHORS WHEN FIXED. THE MANUFACTURER'S No Revision
Job Project
Drawn Manager Director Date
WRITTEN RECOMMENDATIONS SHALL BE FOLLOWED STRICTLY. MJ1 THE CONTRACTOR SHALL NOT FILL ANY STRUCTURAL MOVEMENT JOINTS UNTIL THE
PERIMETER INNER LEAF WALLS HAVE BEEN CONSTRUCTED AND SEALED. CUTOUTS AND OPENINGS
M8 THE CONTRACTOR IS TO TAKE PARTICULAR CARE TO ENSURE THAT ALL PERPENDS AND BEDS
ARE PROPERLY FILLED WITH MORTAR. SECTION MARK Note: * indicates signatures on original issue of drawing or last revision of drawing

M9 REFER TO ARCHITECTURAL PLANS AND ELEVATIONS FOR LOCATIONS OF CONTROL JOINTS. REINFORCED CONCRETE CP4 ONLY LARGE OPENINGS ARE SHOWN ON THE STRUCTURAL DRAWINGS. THE CONTRACTOR SHALL
COORDINATE ALL BUILDERS WORK REQUIREMENTS FOR OTHER OPENINGS REQUIRED FOR
Conditions of Use. This document may only be used by GHD's client (and any other
person who GHD has agreed can use this document) for the purpose for which it was
M10 PROVIDE RESTRAINT TO ALL MASONRY AT SOFFIT OF SLAB OVER AS REQUIRED. VERTICAL SERVICES AND ENSURE THAT SUCH OPENINGS ARE PROPERLY ALLOWED FOR IN THE prepared and must not be used by any other person or for any other purpose.
DETAIL
C1 ALL WORKMANSHIP AND MATERIALS SHALL COMPLY WITH THE SPECIFICATION DESIGN AND FORMING OF THE PRECAST ELEMENTS. NUMBER
M11 WHERE STARTER BARS, ANCHOR BOLTS, ETC. ARE SHOWN PROJECTING INTO MASONRY,
C2 ALL CONCRETE SHALL BE PREMIXED BY A REVIEWED AND ACCEPTED SUPPLIER CP5 ELEMENTS ARE TO BE NOTCHED AROUND COLUMNS TO SUIT THE LAYOUT.
BUILD THESE TIGHTLY INTO MASONRY VOIDS WITH MASONRY GROUT.
C3 ALL REINFORCEMENT SHALL BE HIGH YIELD DEFORMED TYPE 2 CLASSIFICATION AND MEET THE
A
M12 PROVIDE LINTELS OVER ALL OPENINGS OR RECESSES IN MASONRY WALLS, INCLUDING THOSE CP6 ALL LIFTING AND HANDLING DEVICES SHALL BE DESIGNED TO CARRY MAXIMUM LOAD RESULTING
FOR MECHANICAL OR ELECTRICAL SERVICES OR EQUIPMENT. SEE TYPICAL DETAILS FOR
REQUIREMENTS OF THE SPECIFICATION FROM LIFTING, HANDLING AND ERECTION PLUS AN IMPACT ALLOWANCE OF ATLEAST 100 PERCENT. - Master Developper / Owner

LINTEL SIZES FOR NON-LOAD BEARING MASONRY WALLS. C4 LAPS AND SPLICES SHALL BE MADE ONLY WHERE SHOWN OR NOTED. BARS SHOWN LONGER
THAN STOCK LENGTHS SHALL BE LAPPED IN ACCORDANCE WITH THE NOTES HEREIN. MAXIMUM CP7 WHERE SHOWN ON THE DRAWINGS, THE CONTRACTOR IS REQUIRED TO DESIGN & ERECT Abu Dhabi Airports Company PJSC
M13 BLOCKS ARE TO BE LAID IN STRETCHER BOND PATTERN OVER FULL HEIGHT, INCLUDING AT STOCK LENGTHS SHALL BE USED WHERE POSSIBLE AND LAPS IN ADJACENT BARS SHALL BE SECONDARY STEEL MEMBERS SUPPORTING THE PRECAST PANELS. DRAWING Planning & Development
TOP OF WALL. STAGGERED. REFERENCE PO Box 94449, Abu Dhabi, U.A.E
C5 ALL STARTER BARS TO BE PROTECTED FROM DUST AND CORROSION BY COVERING WITH NUMBER T: +971 (0) 2 505 5000

WATER TESTING AND CHECKING


F: +971 (0) 2 575 8300
REVIEWED AND ACCEPTED PROTECTION MATERIAL UNTIL COMMENCEMENT OF NEXT PHASE OF
GROUND SLAB & FOUNDATION CONCRETE WORKS. STARTER BARS TO BE UN BENT, MARKED FOR SAFETY REASONS AND DETAIL MARK
PROTECTED FROM CONSTRUCTION TRAFFIC.
W1 THE FOLLOWING IS ENTIRELY SEPARATE TO THE REQUIREMENTS FOR HYDROSTATIC TESTING
F1 THE ENGINEER IS TO BE ADVISED IMMEDIATELY UPON DISCOVERY OF ANY SOFT SPOTS OR C6 CONCRETE QUALITY: REFER TO THE SPECIFICATION FOR TESTING REQUIREMENTS. OF ANY LIQUID FILLED TANKS, ALTHOUGH THE TWO OPERATIONS MAY BE COMBINED.
SERVICES IN THE GROUND C7 CONCRETE STRENGTH AND COVER W2 FILLING SHALL BE DONE UNDER CONTROLLED CONDITIONS TO ENSURE THAT FAILURE DOES NOT
OCCUR DURING FILLING. Lead Consultant
F2 POSITION OF ALL CONSTRUCTION JOINTS TO BE REVIEWED BY THE ENGINEER WHERE THESE
DIFFER FROM THOSE PROPOSED. W3 EACH TANK TO BE FILLED GRADUALLY WITH WATER AT CONSTANT RATE OVER 3 MONTHS.
F3 ON NO ACCOUNT SHOULD ANY HOLES, OPENINGS OR REINFORCEMENT BE CUT WITHOUT GRADE STRENGTH, CEMENT TARGET MINIMUM LEVELS AROUND THE TANK TO BE CHECKED WEEKLY DURING FILLING. LEVELS INSIDE THE TANK ABBREVIATIONS
PRIOR REVIEW OF THE ENGINEER. ELEMENT Fcu U.N.O. (Mpa) TYPE COVER (mm) CAN THEN BE CHECKED.
CTS CENTRES
F4 RETAINING WALLS AND WALLS OF BURIED STRUCTURES HAVE BEEN DESIGNED AS PROPPED W4 IN CARRYING OUT SUCH TEST PROCEDURE ADEQUATE ARRANGEMENTS SHOULD BE MADE
FOUNDATION / FOR THE EMERGENCY DISPOSAL OF WATER IF OFF LOADING BECOMES NECESSARY. DISCHARGE BTM. BOTTOM
CANTILEVERS AND NO BACK FILLING TO THE RETAINING WALLS SHOULD TAKE PLACE UNTIL C40/20 CEM1 + GGBS 75
SLAB ON GRADE SHOULD BE CLEAR OF TANK TO AVOID EROSION. SHOULD ANY OF THE RESULTS BE
THE FLOOR SLABS ARE CONSTRUCTED, UNLESS OTHERWISE AGREED BY THE ENGINEER. GHD GLOBAL PTY LTD
BUILDING FRAME NSATISFACTORY, THE ENTIRE PROCEDURE IS TO BE REPEATED, AT THE DISCRETION OF THE NF NEAR FACE
F5 DO NOT USE COMPACTION METHODS THAT WILL CAUSE DAMAGE TO ADJACENT STRUCTURES 50 FOR EXTERNAL ENGINEER, UNTIL SATISFACTORY RESULTS ARE OBTAINED FOLLOWING REMEDIAL WORKS.
3rd Floor, Guardian Tower, Danet Community
IN CONTACT C40/20 CEM1 + GGBS FF FAR FACE PO Box 45921 Abu Dhabi United Arab Emirates
OR SERVICES.SELECTION OF METHODS SHALL BE THE CONTRACTORS RESPONSIBILITY.CARE FACE LEVELS OF ALL TANKS AT 4 REFERENCE POINTS PER TANK ARE TO BE CHECKED WEEKLY UNTIL
WITH GROUND T 971 2 6968700 F 971 2 4472915
SHALL BE TAKEN IN COMPACTION BEHIND RETAINING WALLS. THE FIRST MONTH OF SERVICE OF THE NEWEST TANK IS OVER, THENCEFORTH TO BE CHECKED EF EACH FACE E abumail@ghd.com W www.ghd.com
F6 SAND MATERIAL EXCAVATED FROM SITE MAY BE SUITABLE FOR BACKFILL PROVIDED IT IS FREE BUILDING FRAME C40/20 CEM1 40 MONTHLY FOR A FURTHER 2 MONTHS.
OF ALL DELETERIOUS MATTER AND COMPLIES WITH THE SPECIFICATION REQUIREMENT. EW EACH WAY
SUSPENDED Specialist Consultant
F7 THE CONTRACTOR SHALL BE ENTIRELY RESPONSIBLE FOR ENSURING THAT THE EXCAVATIONS C40/20 CEM1 35 STAG. STAGGERED BARS
ARE SUITABLE, SAFE AND STABLE. (i.e. TEMPORARY WORKS) ALTHOUGH SUCH PRECAUTIONS
SLAB
WATERTIGHT CONSTRUCTION
MAY HAVE ALREADY BEEN REVIEWED IN PRINCIPLE BY THE ENGINEER. ALT. ALTERNATING BARS
BLINDING C20/20 - -
F8 IT SHALL REMAIN THE CONTRACTOR'S OBLIGATION TO PROVIDE DRY WORKING CONDITIONS W5 THE FOLLOWING STRUCTURAL ELEMENTS ARE TO BE CONSTRUCTED IN ACCORDANCE WITH L.V. LENGTH VARIES
CONCRETE THE SPECIFICATION Fire Life Safety, Planning
BY ANY MEANS HE MIGHT SEE EFFECTIVE AND UTILIZING THE INSTALLED DEWATERING C60/20 CEM1 35
TOPPING - FOUNDATIONS UNO UNLESS NOTED OTHERWISE
SYSTEM. EXCAVATION SHALL BE AT ALL TIMES CARRIED OUT IN DRY CONDITIONS. GROUND and Regulatory Specialist
WATER SHALL BE MAINTAINED AT LEAST 500mm BELOW THE DEEPEST POINT IN THE - TANK WALLS U/S UNDERSIDE
EXCAVATION WHILE IT REMAINS OPEN. W6 REFER TO THE ARCHITECTURAL DRAWINGS AND SPECIFICATION FOR DETAILS OF
DEWATERING SHALL NOT BE DISCONTINUED WITHOUT THE WRITTEN AGREEMENT OF THE C8 REINFORCEMENT IS SHOWN DIAGRAMATICALLY ON THE DRAWINGS AND NOT NECESSARILY IN E.G.L. EXISTING GROUND LEVEL
TRUE POSITION. WATERPROOFING.
ENGINEER.
G.L. GROUND LEVEL
F9 FORMATION TO BASEMENT AND GROUND SLABS CAST ON THE GROUND TO BE COMPACTED C9 ALL REINFORCEMENT SHALL BE SECURELY SUPPORTED IN ITS CORRECT POSITION BY REVIEWED
IN ACCORDANCE WITH THE SPECIFICATION AND ADEQUATELY BLINDED WITH ROLLED-IN AND ACCEPTED MEANS BEFORE PLACING CONCRETE R.L. REDUCED LEVEL Specialist Consultant
CLEAN SAND. C10 WELDING AND/OR SITE CUTTING OF REINFORCING SHALL NOT BE PERMITTED UNLESS REVIEWED
AND ACCEPTED IN WRITING BY THE ENGINEER.
LOADING PARAMETER FFL FINISHED FLOOR LEVEL
F10 THE BACKFILLING MATERIAL SHALL BE SELECTED GRANULAR MATERIAL COMPACTED TO
AT LEAST 98% OF ITS MAXIMUM DRY DENSITY AND IN ACCORDANCE WITH THE C11 ALL PROPRIETARY FIXINGS SHALL BE INSTALLED IN ACCORDANCE WITH MANUFACTURER'S L1 THE STRUCTURAL HAS BEEN DESIGNED TO ALLOW FOR THE UNFACTORED LOADS GIVEN SSL STRUCTURAL SURFACE LEVEL
SPECIFICATIONS. INSTRUCTIONS. ON THE LOADING PLANS, IN ADDITION TO THE FLOOR SELF-WEIGHT Third Party
R.C. REINFORCED CONCRETE Operational Advisor
F11 FOR ALLOWABLE SOIL BEARING CAPACITY REFER TO GEOTHECHNICAL REPORT NO. ATGP-13-0327 C12 ALL CONCRETE SHALL BE COMPACTED USING A MECHANICAL VIBRATION PROCESS
L2 WIND LOADS TO ASCE/SCI 7-05
PREPARED BT MS. TERRASEARCH GULF. C13 CONCRETE SHALL BE CURED IN ACCORDANCE WITH THE SPECIFICATION M.C. MASS CONCRETE
C14 STANDARD REINFORCEMENT LAP LENGTHS (UNO) BASIN WIND SPEED = 40m/s
STRUCTURALSTEEL MESH - 1 PANEL +25mm DIRECTIONALITY FACTOR
OCCUPANCY CATEGORY
= 0.85 (TABLE 6.4-1)
= IV (TABLE 1)
T&B TOP & BOTTOM

CJ CONSTRUCTION JOINT
S1 ALL WORKMANSHIP AND MATERIALS SHALL BE IN ACCORDANCE WITH BS 5950 AND THE IMPORTANCE FACTOR = 1.15 (TABLE 6-1)
SPECIFICATION. REQUIRED LAP SPLICE LENGTH FOR DEFFERENT BAR SIZE IN (mm)
EXPOSURE CATEGORY = C (SECTION 6.4.2.2) MJ MOVEMENT JOINT Client
ADAC
TOPOGRAPHIC FACTOR (Kzt) = 1 (FIGURE 6.4-2)
S2 ALL DESIGN OF STEELWORK SHALL BE IN ACCORDANCE WITH THE STRUCTURAL STEEL TOB TOP OF BEAM
SPECIFICATION. STEEL SHALL BE GRADE S 275 UNLESS NOTED OTHERWISE. Fcu = 40Mpa fy = 460Mpa L3 SEISMIC LOAD ACCORDING TO ASCE/SEI 7-05
S3 ALL SECTIONS USED SHALL BE OF ROLLED STEEL SECTIONS FROM THE SOURCE REVIEWED AND NOTE:
Project
MIDFIELD TERMINAL FIRE
AGREED WITH THE ENGINEER. BUILT UP SECTIONS OR FABRICATED SECTIONS SHALL NOT BE BAR DIA. 12 16 20 25 32 40 OCCUPANCY CATEGORY = IV
USED UNLESS ADVISED BY THE ENGINEER. SEISMIC IMPORTANCE FACTOR = 1.5 (TABLE 11.5-1) WHEN A FINISH LEVEL IS THE SAME AS THE STRUCTURAL
LEVEL AND NO APPLIED FINISH IS PRESENT ONLY THE
STATION
S4 BOLTS AND NUTS SHALL HAVE ISO METRIC COARSE THREAD. 12 575 575 875 1100 1400 1750 SEISMIC GROUND MOTION VALUES:
SITE CLASS - D STRUCTURAL LEVEL WILL BE SHOWN Title
S5 MILD STEEL BOLTS AND NUTS SHALL COMPLY WITH THE REQUIREMENTS OF BS 5950 PART 1,
BS 4190 AND BS 4320 RESPECTIVELY. 16 750 875 1100 1400 1750 0.2 SEC SPECTRAL RESPONSE ACCELERATION
STRUCTURAL GENERAL
1 - SEC SPECTRAL RESPONSE ACCELERATION
S6 HIGH STRENGTH FRICTION GRIP BOLTS, NUTS AND WASHERS SHALL COMPLY WITH THE 20 1150 1150 1400 1750 SEISMIC DESIGN CATEGORY
REQUIREMENTS OF BS 4395 PART 1 AND BS 4604 PART 1. Fa = 1.14 (ASSUMING SITE CLASS C) NOTES & DETAILS SHEET 1
S7 WASHERS ARE TO BE PROVIDED UNDER ALL NUTS ON BEVELLED SURFACES. SQUARE TAPER 25 1425 1425 1750 Fv - 1.605 (ASSUMING SITE CLASS C)
WASHERS OF 5mm. MEAN THICKNESS SHALL BE UNDER NUT OR HEAD AS APPROPRIATE. SMS = FaSS = 1.14 x 0.65 = 0.741 Scale 1 : 100 DO NOT SCALE
S8 ALL WELDING SHALL BE TO BS-639 32 1825 1825 SM1 = FvS1 = 1.605 x 0.195 = 0.313
SDS = 2/3 SM1 = 0.494 Drawn R. BUDUAN Designer R. EDNALINO
ALL WELDS SHALL BE APPLIED WITH E48XX ELECTRODES AND CARRIED OUT BY A CERTIFIED
WELDER. STEELWORK SHALL BE CLEANED BACK TO WHITE METAL SURFACE AND FREE OF RUST , 40 2300 SD1 = 2/3 SM1 = 0.209
Drafting Design
SCALE ETC., PRIOR TO WELDING. SUPERVISION AND TESTING OF WELDS SHALL BE DONE IN SEISMIC DESIGN CATEGORY C Check Check
ACCORDANCE WITH BS-709 REFER TO SPECIFICATIONS FOR FURTHER DETAILS. Approved
NOTE: BASIC SEISMIC FORCE RESISTING SYSTEM
S9 UNLESS OTHERWISE SHOWN ALL GUSSET PLATES SHALL BE 10mm THICK AND ALL END PLATES BEARING WALL SYSTEMS, ORDINARY REINFORCED CONCRETE SHEAR WALLS: (Project Director)
SHALL BE 8mm THICK THE CONTRACTOR MAY REPLACE THE LAP LENGTH WITH AN APPROVED COUPLER IN Date
CONGESTED AREAS. RESPONSE MODIFICATION CO-EFIICIENT R = 6.0
S10 PROTECTIVE SURFACE TREATMENT SHALL BE AS STATED IN THE SPECIFICATIONS. SYSTEM OVER STRENGTH FACTOR = 0 = 2.5 This Drawing must not be used for Construction unless signed as Approved
DEFLECTION AMPLIFICATION FACTOR, Cd = 5.0
ACCIDENTAL TORSION, ecc = 5.0% Original Size
Drawing No:
Ss AND S1 Ss = 0.56 S1 = 0.23
A1
DETAIL DESIGN 76-10526- S001 Rev: A
Plot Date: 5/03/2015 10:39:21 PM Cad File No: C:\Users\rbuduan\Documents\76-10526_Midfield Fire Station-Central_rbuduan.rvt

Das könnte Ihnen auch gefallen