Sie sind auf Seite 1von 1

GE

Energy

MS7001EA Gas Turbine


Proven Performance for 60 Hz Applications fact sheet
High Reliability and Availability MS7001EA Combined Cycle Performance Ratings (60 Hz)
With over thirty million hours of service and more than 1100 Heat Rate
units in operation, the MS7001 fleet is well recognized for its high Net Plant Net Plant GT Number
Output (MW) (Btu/kWh) (KJ/kWh) Efficiency and Type
reliability and availability.
S107EA 130.2 6,800 7,173 50.2% 1 x MS7001EA
GEs MS7001EA 85 MW gas turbine provides strong efficiency S207EA 263.6 6.700 7,067 50.9% 2 x MS7001EA
performance in simple and combined-cycle applicationsand is
used in a wide variety of power generation, industrial, mechanical
drive, and cogeneration applications. Uncomplicated and versatile, MS7001EA Simple Cycle Performance Ratings (60 Hz)
its medium-size design lends itself to flexibility in plant layout and 60 Hz Power Generation Mechanical Drive
fast, low-cost additions of incremental power. For customers Output (MW) 85.1 (hp) 116,230
needing additional performance, GE Energy offers an optional Heat Rate (Btu/kWh) 10,430 (Btu/shp-hr) 7,720
Performance Improvement Pack which can provide up to 5.1+% (kJ/KWh) 11,002

incremental output and as much as a 2.7% reduction in heat rate Pressure Ratio 12.7:1 12.6:1
in simply cycle applications. Mass Flow (lb/sec) 660 (lb/sec) 666
(kg/sec) 299 (kg/sec) 301
Full Range of Fuel Capabilities Turbine Speed (rpm) 3,600 (rpm) 3,600
The 7EA unit can accommodate a full range of fuels with its world-
Exhaust (F) 999 (F) 995
class fuel handling equipment, advanced bucket cooling, thermal Temperature
(C) 537 (C) 535
barrier coatings, and multiple-fuel combustion system. Designed
Model PG7121EA M7121EA
for dual fuel operation, it is able to switch from one fuel to another Designation
while the turbine is running under load or during shutdown. 7E/EA
units have accumulated millions of hours of operation using crude
and residual oils.
An MS7001EA is shown on half
shell during assembly.
Operating Flexibility
The 7EA is well suited for peak, cyclic or base load operation. Its
Fast-Start-Fast-Load capability enables the 7EA to deliver 85% load
in less than ten minutes. 60% turndown with DLN1 also contributes
to the 7Es proven operating flexibility.

GEs DLN1 combustion system achieves less than 9 ppm NO x .


DLN 1+, which is a certified ecomagination product, is available as
a retrofit, and allows the Frame 7EA to produce less than 5 ppm
NO x when fired with natural gas, making it an industry leader in
reducing emissions.

For more information, contact your GE representative


or visit ge.com/energy.

2008 General Electric Company. All rights reserved.

Printed on recycled paper. GEA-16017 (02/08)