Beruflich Dokumente
Kultur Dokumente
Sl No
3
4
5
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
LIQUIDATION OF COMMISSIONING PUNCH LIST OF
Job description
Shop floor layout diagram / Flowchart to be displayed on a board near the main entry to shop
floor.
Steps to be provided wherever there is more difference in height / running pipe lines for easy
and safe movement of people. Cooling tower railing ends are handing needs to be fixed on the
walls to prevent accidents.
DE & NDE dial type temperature gauges are showing different reading with RTD in HMI
System (variation 10-15 degrees). The same to be rectified.
Many air valves are not operating some are severely jammed (MOV60). They are not operating
in Manual / auto mode. All valves to be shown operating properly in both mode i.e. MOV60
Oil drain pipes of compressor #2 & #3 not fitted. Oil drain lines of all Compressors should be
fitted with ball valve at the outlet point.
No drain line from the air supply header, draining leads to spillage inside the shop.
Cooling Tower Fan#1 & #2 is not operable from control room. To be made operable from control
room.
The units shown in HMI are incorrect regarding the pressure and flow data. To be corrected.
The Air filter delta P is not correctly reflected in the HMI. To be rectified.
Three way valve of suction line to be made operational along with manometer to monitor the
delta P.
Alarm for Cooling water pump trip to be provided in the control room.
Shop floor Overhead lights are not properly installed. To be properly installed.
Ultrasonic Level Sensors for water Sump of cooling tower shall be replaced.
Faulty 2 nos. I/P Converters to be replaced.
Range of I/P Converters supplied along with Compressors is wrong with respect to actual
requirement so balance all should be changed.
Discharge flow meters for compressors as well as total discharge flow meters calibration are
wrong. As well as range in PLC has been wrongly programmed. Same shall be corrected.
Licensing of Software PLC / HMI has not been completed. Same shall be done.
Separate Cabinet for Engineering station shall be fabricated.
Isolator handle of MCC Panel (12 Nos.) are not available, feeder doors are not closing. To be
rectified.
FCMA soft starter commissioning to be done.
Hoist of suitable capacity for maintenance of EOT crane (3.01.09 of SOW, page 137).
In PDB room corner flooring fixture is improper and is not safe to work near the DBs place in
the vicinity. To be rectified.
Rain water ingress in the Sub-station room, PDB room and Control room to be arrested.
Water inflow in the Cable Tunnel to be arrested.
Dosing unit not Installed. The same to be installed.
Two nos. 30kw Cooling pump motor have burnt. These are to be replaced.
PDB 2 Incomer 1, MLDB Incomer 1 and MCC incomer have Latching problem. To be rectified.
In case of pump failure, individual feeders are not tripping. Instead, main incomer breaker of
MCC is tripping resulting in stopping of all the compressor. Problem to be rectified.
Short circuit current tripping setting of cooling pump and cooling tower MCCB is more than
setting of MCC incomer breaker. To be rectified.
Electronic overload of all the six panels of 30 KW drive are not working, these are to be
replaced.
Broken 12 Nos handles of MCCB of MCC panels need to be replaced.
Cooling water 3 panel (which is kept racked out) is not ready. Its main contactor and control
circuit plug in contacts are defective. These are to be replaced for making the panel ready.
Crane drawings, digital drive manual and exact parameter setting of digital drives to be
submitted in soft as well as hard copy.
Crane lighting stops glowing at three locations while L.T is operated. To be rectified.
Roof lighting - structure on which roof lights are installed are loosely fixed.
MOVs no. 17, 24, 25, 33, 40, 44, 45, 46, 48, 49, 50, 51, 52, 54, 56, 60, 64, 66 are not
operating electrically, to be rectified.
There should not be any interlock to prevent closing of an incomer if bus coupler in ON.
Incomer-1, Incomer-2 and bus coupler closing interlock circuit - TB numbers to be provided /
corrected.
TB numbers are not matching with the drawings at different pages. To be rectified.
Commissioning spares as per Contract to be provided by M/s BSL.
HART calibrator shall be handed over by M/s BSL.
Quality of instrument air is not as per requirement.
Discussion points
Completed
Completed
M/s BSL agreed to comply with the same.
M/s BSL agreed to comply with the same.
M/s BSL agreed to comply with the same by providing manpower only.
Light fittings will be supplied by DSP.
M/s BSL agreed to comply with the same. BSL will do the proper
scaling in HMI.
Completed
Completed
Completed
Completed
Completed
Already taken care off in point no. 12
M/s BSL will change the balance 2 nos. defective relay for rectification
of the said problem.
M/s BSL will change the balance 2 nos. defective relay for rectification
of the said problem.
M/s BSL already replaced 4 Nos relay. M/s. BSL will install the
balance 2 Nos relay.
Already taken care off in point No.35.
Completed
Completed
As advised by DSP PMD, we have made sump pit and installed pump
for dewatering of trench as and when required.
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Material in transit.
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Both the motor has sent to Pioneer Electric.
Completed
Please refer to our letter No.
BSL/DSP/NCAS/SM/16-17/347A, dated-
11.06.2017
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Will be done during PG test.