Beruflich Dokumente
Kultur Dokumente
GENERAL ABSTRACT
Gen.ABS
ABSTRACT FOR CIVIL
Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddi
Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Quantity Description Rate Unit
No.
Earth work excavation for foundations and depositing on
bank for all lifts and with aninitial lead of 10m including all
operational, incidental, labour charges such as shoring
1 2593.722 96.95 1 Cum.
sheeting, planking, strutting, etc. complete for finished item
of work excluding dewatering charges etc. as per SS- 20 B
(APSS 308).
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
A FOR SLABS
a 107.400 For cellar floor 10293.55 1 cum.
b 57.377 GROUND FLOOR 10293.55 1 cum.
c 45.809 FOR FIRST FLOOR 10463.24 1 cum.
d 54.187 FOR SECOND FLOOR 10838.00 1 cum.
e 58.065 FOR THIRD FLOOR 11035.75 1 cum.
f 58.065 FOR FOURTH FLOOR 11219.75 1 cum.
g 11.232 FOR FIFTH FLOOR 11410.10 1 cum.
B FOR BEAMS
a 29.996 For cellar floor 11399.15 1 cum.
b 15.260 GROUND FLOOR 11399.15 1 cum.
c 15.019 FOR FIRST FLOOR 11626.60 1 cum.
d 15.770 FOR SECOND FLOOR 12057.55 1 cum.
e 15.770 FOR THIRD FLOOR 12302.50 1 cum.
f 15.770 FOR FOURTH FLOOR 12545.90 1 cum.
g 1.605 FOR FIFTH FLOOR 12790.85 1 cum.
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
c 6.998 FOR SECOND FLOOR 7349.55 1 cum.
d 6.998 FOR THIRD FLOOR 7661.10 1 cum.
e 6.998 FOR FOURTH FLOOR 7971.45 1 cum.
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
c 634.565 FOR FIRST FLOOR 428.45 1Sqm
d 1017.947 FOR SECOND FLOOR 433.75 1Sqm
e 661.295 FOR THIRD FLOOR 439.05 1Sqm
f 661.295 FOR FOURTH FLOOR 444.35 1Sqm
g 126.270 FOR FIFTH FLOOR 449.65 1Sqm
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
ABS-Civil
Sl.
Quantity Description Rate Unit
No.
e 1113.110 FOR THIRD FLOOR 193.40 1 Sq.mtr.
f 1113.110 FOR FOURTH FLOOR 193.40 1 Sq.mtr.
g 170.579 FOR FIFTH FLOOR 193.40 1 Sq.mtr.
Total:
Add for Unforcein items
Total:
ABS-Civil
ABSTRACT FOR CIVIL
mmercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
n the place of existing A & B staff quarters.
Amount
251,461.35
159,868.54
1,231,254.85
145,599.97
473,576.39
ABS-Civil
Amount
-
174,979.22
109,553.48
7,804.48
8,573.33
8,750.20
8,927.06
-
297,883.99
168,047.60
171,715.04
189,272.34
194,124.51
198,977.35
-
510.57
1,543.86
4,874.72
21,286.43
23,099.33
23,251.51
1,129.18
-
-
834,924.29
ABS-Civil
Amount
51,477.88
551,157.56
-
21,412.96
24,370.05
24,922.61
1,708.86
-
ABS-Civil
Amount
-
1,105,527.27
590,613.02
479,310.56
587,278.71
640,790.82
651,474.78
128,158.24
-
-
341,928.90
173,951.03
174,619.91
190,147.56
194,010.43
197,848.84
20,529.31
-
165,845.09
18,276.26
ABS-Civil
Amount
3,171,363.54
711,954.30
635,622.81
719,612.92
752,442.52
753,933.25
104,430.56
233,381.36
323,662.99
373,182.32
460,582.68
467,764.25
481,358.08
238,744.55
-
-
52,743.80
49,258.92
ABS-Civil
Amount
51,432.15
53,612.38
55,784.21
-
292,599.50
84,829.47
75,803.23
84,319.18
92,350.99
95,242.60
9,623.91
-
285,078.60
188,189.26
46,679.43
39,442.42
85,688.36
89,913.76
90,415.78
96,083.94
-
24,572.59
279,523.25
ABS-Civil
Amount
271,879.37
441,534.51
290,341.57
293,846.43
56,777.31
-
377,254.85
-
306,092.98
-
377,231.22
364,060.81
430,713.78
474,176.81
475,169.98
-
37,916.75
36,588.63
43,287.03
47,655.59
47,754.91
ABS-Civil
Amount
-
38,269.88
39,675.75
39,815.96
39,956.16
40,096.37
-
16,456.87
103,138.13
131,367.88
87,025.03
87,136.11
87,248.43
-
121,567.40
72,110.34
13,327.71
13,372.06
13,416.54
13,460.89
-
ABS-Civil
Amount
26,749.80
402,924.00
24,344.10
ABS-Civil
Amount
880,918.50
59,796.00
ABS-Civil
Amount
684,377.30
150,417.89
383,477.69
256,397.07
226,151.07
316,938.03
244,327.65
244,327.65
37,442.09
-
337,879.66
225,909.77
199,260.21
279,252.00
ABS-Civil
Amount
215,275.47
215,275.47
32,989.98
-
93,240.21
23,127.78
18,435.40
39,825.88
41,555.43
41,555.43
43,915.66
-
18,567.40
33,791,952.73
1,008,047.27
34,800,000.00
ABS-Civil
DETAILED ESTIMATE
Name of work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Madd
Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Description Nos. Length Breadth Depth
No.
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
A. Footings
FG-1 1 x 17 0.80 0.80 0.225
FG-2 1 x 16 1.05 1.05 0.325
FG-3 1 x 7 1.50 1.50 0.425
FG-4 1 x 6 2.15 2.15 0.600
FG-5 1 x 4 2.25 2.25 0.650
FG-6 1 x 6 2.50 2.50 0.750
FG-7 1 x 6 2.65 2.65 0.800
CF-1 1 x 2 2.50 1.80 0.550
CF-2 1 x 2 3.70 1.95 0.900
TOTAL Total :
B. Pedastal
For Coloums 1 x 33 0.45 0.45 0.450
For Coloums 1 x 29 0.75 0.75 0.600
CF-1 1 x 4 0.45 0.45 0.450
CF-2 1 x 4 0.60 0.60 0.600
TOTAL Total :
C Plinth Beam
For C55-C70, C45-C54, C33-C42. 1 x 3 39.48 0.23 0.300
For C43 1 x 1 4.78 0.23 0.300
For C44 1 x 1 3.73 0.23 0.300
For C27 1 x 1 3.00 0.23 0.300
For C28 1 x 1 3.73 0.23 0.300
For C16-C19 1 x 1 31.43 0.23 0.300
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
2nd Floor
Windows 1x 18 1.82 0.46 --
3rd Floor
Windows 1x 20 1.82 0.46 --
4th Floor
Windows 1x 20 1.82 0.46 --
5th Floor
Head room door and lift room door 1x 2 1.22 0.46
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
A FOR SLABS
Cellar floor
For slab 1x 1 39.48 18.77 0.15
Waist slab for stair case 1x 1 9.63 1.47 0.175
Deduction
Stair case rooms area -1 x 1 4.77 3.30 0.15
South side portion -1 x 1 4.77 2.06 0.15
South east corner -1 x 0.5 3.30 9.69 0.15
TOTAL Total :
Ground floor
For slab 1 x 1 31.43 10.97 0.15
Waist slab for stair case 1 x 1 9.63 1.47 0.175
Ramp to ground floor slab 1 x 2 8.05 3.93 0.15
Slab projection alround 1 x 1 79.06 0.30 0.15
Deduction : Stair case rooms area -1 x 1 4.77 3.30 0.15
Ramp portion -1 x 2 3.47 7.21 0.15
TOTAL Total :
First floor
For slab 1x 1 31.43 10.97 0.15
Waist slab for stair case 1x 1 9.63 1.47 0.175
Slab projection alround 1x 1 73.83 0.30 0.15
Deduction
Stair case rooms area -1 x 1 4.77 3.30 0.15
Span C-36 - C39 and C-48 - C51 -1 x 1 12.17 5.12 0.15
TOTAL Total :
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
2nd floor
For slab 1x 1 31.43 10.97 0.15
Waist slab for stair case 1x 1 9.63 1.47 0.175
Slab projection alround 1x 1 81.23 0.30 0.15
Deduction
Span C-37 - C38 and C-49 - C50 -1 x 1 4.77 5.12 0.15
TOTAL Total :
3rd floor
For slab 1x 1 31.43 10.97 0.15
Waist slab for stair case 1x 1 9.63 1.47 0.175
Slab projection alround 1x 1 86.00 0.30 0.15
TOTAL Total :
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
For Cellar
For Footing Qty as above 124.449 0.150 MT/Cum
Pedestals Qty as above 14.024 0.080 MT/Cum
Plinth Beams Qty as above 38.951 0.120 MT/Cum
Colunms Qty as above 24.042 0.150 MT/Cum
Lintals Qty as above 0.042 0.080 MT/Cum
R.C.C. Side walls Qty as above 56.389 0.080 MT/Cum
For Roof Slab Qty as above 107.400 0.120 MT/Cum
Roof Beams Qty as above 29.996 0.150 MT/Cum
TOTAL Total :
Ground floor
For Columns Qty as above 13.563 0.150 MT/Cum
Fro Lintals Qty as above 0.127 0.080 MT/Cum
For Roof Slab Qty as above 57.377 0.120 MT/Cum
For Roof Beams Qty as above 15.260 0.150 MT/Cum
TOTAL Total :
For 1 st Floor
For Columns Qty as above 13.563 0.150 MT/Cum
Fro Lintals Qty as above 0.401 0.080 MT/Cum
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Cellar Floor
Stair Case side walls 1 x 2 5.000 0.23 2.745
Lift Room 1 x 1 7.320 0.23 2.745
Alround the Building above ground 1 x 1 115.370 0.23 0.76
L shape wall 1 x 2 9.160 0.23 1.68
Total Total :
Ground floor
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
2nd Floor
Slab 1 x 1 31.43 10.97
Waist slab bottom 1 x 1 9.63 1.47
Slab projection 1 x 1 81.23 0.30
Beams 1 x 1 51.53 0.84
Columns 1 x 8 1.80 2.75
Deductions : Stair case room -1 x 1 4.77 3.30
Slab -1 x 1 4.77 5.12
Total Total :
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
3rd Floor
Slab 1 x 1 31.43 10.97
Waist slab bottom 1 x 1 9.63 1.47
Slab projection 1 x 1 86.00 0.30
Beams 1 x 1 51.53 0.84
Columns 1 x 8 1.80 2.75
Deductions : Stair case room -1 x 1 4.77 3.30
Total Total :
5th Foor
Stair case Head Room 1x 1 5.23 3.76 --
Waist slab bottom 1x 1 9.63 1.47
Lift room top and bottom slab 1x 2 2.29 2.29
Total Total :
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Deductions
Rolling shetter -1 x 2 3.96 -- 2.745
Rolling shetter -1 x 7 4.26 -- 2.745
Front ramp -1 x 1 12.09 -- 2.745
Ventilators -1 x 6 0.91 -- 0.45
Total Total :
1 st Floor
Alround the building 1x 1 84.8 -- 3.05
Deductions
Rolling shetter -1 x 7 4.26 -- 2.745
Rolling shetter -1 x 1 3.96 -- 2.745
Rolling shetter -1 x 1 2.74 -- 2.745
Rolling shetter -1 x 1 2.44 -- 2.745
Ventilators -1 x 6 0.91 -- 2.745
Front opening -1 x 1 15.13 -- 2.745
Total Total :
2nd Floor
Alround the building 1x 1 84.8 -- 3.05
Deductions
For windows -1 x 18 1.52 -- 1.37
Ventilators -1 x 6 0.91 -- 0.45
Front opening -1 x 1 4.77 -- 2.745
Total Total :
3rd Floor
Alround the building 1x 1 84.8 -- 3.05
Deductions
For windows -1 x 20 1.52 -- 1.37
Ventilators -1 x 6 0.91 -- 0.45
Total Total :
4th Floor Total :
5th Floor
Head room alround 1x 1 16.14 -- 3.05
Parapet wall alround 1x 1 85.46 -- 1.75
Lift room alround 1x 1 9.16 -- 3.05
Total Total :
Cellar Floor
Stair case in side Long walls 1x 2 5.17 - 2.745
Stair case in side Short walls 1x 1 4.77 - 2.745
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
5th Floor
Stair case in side Long walls 1 x 2 5.40 -- 3.05
Stair case in side Short walls 1 x 3 4.72 -- 3.05
Lift room inside 1 x 4 1.83 -- 3.05
Lift room outside 1 x 1 9.12 -- 3.05
Total Total :
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Cellar Floor
(46.32+
floorarea 1x 1 38.70)/2
20.11
deductions -1 x 1 4.72 2.59
Total Total :
Ground Floor
Floor area 1 x 1 30.97 10.51
Deduction for ramp portion -1 x 2 3.47 7.21
toilet rooms -1 x 2 5.82 3.30
stari case room -1 x 1 4.54 3.30
Total Total :
First floor
Floor area 1 x 1 30.97 10.51
Deduction for span C36-C39-C48-C51 -1 x 1 12.17 5.12
Toilet rooms -1 x 2 5.82 3.30
Staircaseroom -1 x 1 4.54 3.30
Total Total :
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Second floor
Floor area 1 x 1 30.97 10.51
Deduction for staircase room -1 x 1 4.54 3.30
Deduct for toilet portion -1 x 2 5.82 3.30
For span C37-C38-C49-50 -1 x 1 4.77 5.12
Total Total :
Third floor
Floor area 1x 1 30.97 10.51
Deduction for staircase room -1 x 1 4.54 3.30
Deduct for toilet portion -1 x 2 5.82 3.30
Total Total :
Toilets
Groundfloor 1 x 2 5.82 3.30
1st floor 1 x 2 5.82 3.30
2 nd Floor 1 x 2 5.82 3.30
3 rd Floor 1 x 2 5.82 3.30
4 th Floor 1 x 2 5.82 3.30
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Cellar floor
Stair case side long walls 1x 2 5.43 - 1.52
Stair case side short walls 1x 1 4.72 - 1.52
Total Total :
Ground floor
Stair case side long walls 1 x 2 5.43 -- 1.52
Stair case side short walls 1 x 1 4.72 1.52
Toilet horizontal walls 1 x 2 17.17 1.52
Toilet vertical walls 1 x 2 15.64 -- 1.52
Lift room 1 x 2 8.22 -- 1.52
Total Total :
1stfloor
Toilets quantity
Toilet horizontal walls 1 x 2 17.17 1.52
Toilet vertical walls 1 x 2 15.64 -- 1.52
Stair case side long walls 1 x 2 5.43 - 1.52
Stair case side short walls 1 x 1 4.72 - 1.52
Lift room 1 x 2 8.22 -- 1.52
for corridor 1 x 1 25.10 -- 1.52
Total Total :
2nd Floor
Toilet horizontal walls 1 x 2 17.17 1.52
Toilet vertical walls 1 x 2 15.64 -- 1.52
Stair case side long walls 1 x 2 5.43 - 1.52
Stair case side short walls 1 x 1 4.72 - 1.52
Total -- -- -- Total :
3rdfloor -- -- -- Total :
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Total Total :
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Door shutters 1x 6 -- -- --
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Cellar floor
Cellar Ceiling Qty. --
Cellar Plastering Qty
Total Total :
Groundfloor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
1st Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
2nd Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
3rd Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
4th Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
5th Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Cellar floor
Cellar Ceiling Qty. -- -- --
Cellar Plastering Qty
Total Total :
Groundfloor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
1st Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
2nd Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
3rd Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
4th Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
5th Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.
Cellar floor
External Plastering Qty. -- -- --
Ground floor
External Plastering Qty. -- -- --
1st Floor
External Plastering Qty. -- -- --
2nd Floor
External Plastering Qty. -- -- --
3rd Floor
External Plastering Qty. -- -- --
4th Floor
External Plastering Qty. -- -- --
5th Floor
External Plastering Qty. -- -- --
Det-Civil
ETAILED ESTIMATE
mmercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
n the place of existing A & B staff quarters.
QUANTITY Unit
2135.899
-42.557
107.168
-2.220
-2.398
2195.892
19.125
30.625
29.839
54.673
40.817
78.732
90.160
21.141
32.718
397.830
2593.722 Cum.
2.550
3.000
3.035
4.970
3.602
6.561
7.310
2.187
2.517
35.732 Cum.
Det-Civil
QUANTITY Unit
2.448
5.733
6.694
16.641
13.163
28.125
33.708
4.950
12.987
124.449 Cum.
3.007
9.788
0.365
0.864
14.024 Cum.
8.172
0.330
0.257
0.207
0.257
2.169
Det-Civil
QUANTITY Unit
2.541
1.006
1.161
0.361
11.656
0.391
0.424
0.627
0.828
1.238
7.326
38.951 Cum.
0.632
1.265
11.732
0.765
14.394 Cum.
0.632
Det-Civil
QUANTITY Unit
8.380
9.012 Cum.
0.632 Cum.
0.632 Cum.
0.632 Cum.
0.632 Cum.
1.252
10.870
2.594
2.223
7.103
24.042 Cum.
1.252
10.870
0.494
0.947
13.563 Cum.
13.563 cum.
13.563 cum.
13.563 cum.
13.563 cum.
0.042
0.042 Cum.
0.042
0.085
0.127 Cum.
0.042
0.106
0.253
0.401 Cum.
Det-Civil
QUANTITY Unit
0.042
0.106
1.130
0.253
0.084
1.615 Cum.
0.042
0.106
1.256
0.253
0.084
1.741 Cum.
1.741 cum.
0.084 Cum.
7.181
16.499
7.324
17.640
7.745
56.389 Cum.
397.830
-35.732
-124.449
-14.02
-38.951
184.674 Cum.
107.168
-2.220
Det-Civil
QUANTITY Unit
-2.398
0.000
2.129
10.458
5.126
1.778
7.401
129.442 Cum.
15.070 Sqm
16.744 Sqm
16.744 Sqm
1.122 Sqm
Det-Civil
QUANTITY Unit
111.156
2.477
-2.361
-1.474
-2.398
107.400 Cum.
51.718
2.477
9.491
3.558
-2.361
-7.506
57.377 Cum.
51.718
2.477
3.322
-2.361
-9.347
45.809 Cum.
Det-Civil
QUANTITY Unit
51.718
2.477
3.655
0.000
-3.663
54.187 Cum.
51.718
2.477
3.870
58.065 Cum.
58.065 Cum.
2.950
2.477
4.232
1.573
11.232 Cum.
5.539
0.606
0.688
0.194
2.584
1.023
1.181
0.637
0.842
4.133
0.459
2.249
1.209
1.995
0.445
2.029
2.293
1.224
0.666
29.996 Cum.
2.702
0.734
Det-Civil
QUANTITY Unit
0.335
1.200
0.487
0.126
2.205
6.027
0.752
0.284
0.408
15.260 Cum.
4.410
0.487
0.128
1.200
1.351
6.027
0.724
0.284
0.408
15.019 Cum.
15.019
0.751
15.770 Cum.
15.770 Cum.
15.770 Cum.
0.734
0.463
0.408
1.605 Cum.
741.040
-15.989
-9.826
Det-Civil
QUANTITY Unit
-344.787
370.438 Sqm
344.787
22.374
30.360
-15.670
37.064 Sqm
18.667
1.122
4.674
3.606
0.003
4.511
12.888
4.499
49.970 MT
2.034
0.010
6.885
2.289
11.218 MT
2.034
0.032
Det-Civil
QUANTITY Unit
5.497
2.253
9.816 MT
2.034
0.129
0.060
6.502
2.366
11.091 MT
2.034
0.139
0.067
6.968
2.366
11.574 MT
2.034
0.139
0.067
6.968
2.366
11.574 MT
0.007
0.004
1.348
0.241
1.600 MT
6.314
4.621
20.167
7.079
38.181 Cum
Det-Civil
QUANTITY Unit
9.180
4.621
19.843
12.160
26.618
4.356
-5.000
-18.827
52.951 Cum
4.621
19.843
10.480
8.165
6.276
26.618
6.389
-18.827
-2.500
-1.730
-1.540
57.795 Cum
4.621
19.843
8.165
17.046
2.980
26.618
-8.621
-0.565
-0.892
69.195 Cum
4.621
39.687
2.980
8.165
13.309
3.390
7.109
-9.579
-0.565
Det-Civil
QUANTITY Unit
-0.892
68.225 Cum
68.225 Cum
10.190
14.938
4.621
3.157
32.906 Cum
1.861
0.811
1.190
2.776
0.824
1.525
0.320
0.000
-1.295
8.012 Cum
1.861
0.811
1.190
2.086
0.824
1.525
0.320
-1.619
6.998 Cum
6.998 Cum
6.998 Cum
Det-Civil
QUANTITY Unit
6.998 Cum
741.040
14.156
118.584
218.778
634.479
-15.989
-9.826
-15.741
1685.481 Sqm
344.787
14.156
63.273
23.718
43.285
49.410
-15.741
-50.037
472.851 Sqm
344.787
14.156
22.149
43.285
49.410
-15.741
-62.310
395.736 Sqm
344.787
14.156
24.369
43.285
39.528
-15.741
-24.422
425.962 Sqm
Det-Civil
QUANTITY Unit
344.787
14.156
25.800
43.285
39.528
-15.741
451.815 Sqm
451.815 Sqm
19.665
14.156
10.488
44.309 Sqm
480.450
173.550
654.000 Sqm
28.383
13.094
22.619
316.691
100.577
481.364 Sqm
258.640
Det-Civil
QUANTITY Unit
-21.740
-81.856
-33.187
-2.457
119.400 Sqm
258.640
-81.856
-10.870
-7.521
-6.698
-14.988
-41.532
95.175 Sqm
258.640
-37.483
-2.457
-13.094
205.606 Sqm
258.640
-41.648
-2.457
214.535 Sqm
214.535 Sqm
49.227
149.555
27.938
226.720 Sqm
28.383
13.094
Det-Civil
QUANTITY Unit
20.093
61.570 Sqm
31.537
14.396
22.326
27.816
287.737
67.893
70.394
37.210
23.790
16.226
55.510
30.500
16.470
6.390
-12.950
695.245 Sqm
67.100
14.396
64.538
224.297
76.067
22.326
27.816
103.334
37.210
23.790
16.226
19.947
30.500
16.470
9.150
-24.156
-12.950
634.565 Sqm
67.100
28.792
65.514
5.582
55.632
Det-Civil
QUANTITY Unit
575.474
37.210
23.790
16.226
63.440
39.894
30.500
16.470
9.150
-3.877
-12.950
1017.947 Sqm
32.940
43.188
317.932
37.210
23.790
16.226
63.440
39.894
30.500
16.470
6.390
22.326
27.816
-12.950
-3.877
661.295 Sqm
661.295 Sqm
32.940
43.188
22.326
27.816
126.270 Sqm
Det-Civil
QUANTITY Unit
854.876
-12.225
842.651 Sqm
854.876
-12.225
842.651 Sqm
325.495
-50.037
-38.412
-14.982
222.064 Sqm
325.495
-62.310
-38.412
-14.982
209.791 Sqm
Det-Civil
QUANTITY Unit
325.495
-14.982
-38.412
-24.422
247.679 Sqm
325.495
-14.982
-38.412
272.101 Sqm
272.101 Sqm
22.206 Sqm.
20.979 Sqm.
24.768 Sqm.
27.210 Sqm.
27.210 Sqm.
38.412 Sqm.
38.412 Sqm.
38.412 Sqm.
38.412 Sqm.
38.412 Sqm.
Det-Civil
QUANTITY Unit
16.507
7.174
23.681 Sqm
16.507
7.174
52.197
47.546
24.989
148.413 Sqm
52.197
47.546
16.507
7.174
24.989
38.152
186.565 Sqm
52.197
47.546
16.507
7.174
123.424 Sqm
123.424 Sqm
123.424 Sqm
Det-Civil
QUANTITY Unit
12.152
24.304
78.214
114.670 Sqm
12.152
55.867
68.019 Sqm
12.152
12.152 Sqm
12.152 Sqm
12.152 Sqm
12.152 Sqm
Det-Civil
QUANTITY Unit
6.000 Nos.
48.000 Nos.
6.000 Nos.
Det-Civil
QUANTITY Unit
58.000 Nos.
30.000 Nos.
Det-Civil
QUANTITY Unit
163.712
7.521
6.698
32.611
210.542 Sqm
327.424
15.043
13.396
65.221
200.275
29.975
241.558
24.570
917.462 Sqm
Det-Civil
QUANTITY Unit
1685.481
61.570
1747.051 Sqm
472.851
695.245
1168.096 Sqm
395.736
634.565
1030.301 Sqm
425.962
1017.947
1443.909 Sqm
451.815
661.295
1113.110 Sqm
451.815
661.295
1113.110 Sqm
44.309
126.270
170.579 Sqm
Det-Civil
QUANTITY Unit
1685.481
61.570
1747.051 Sqm
472.851
695.245
1168.096 Sqm
395.736
634.565
1030.301 Sqm
425.962
1017.947
1443.909 Sqm
451.815
661.295
1113.110 Sqm
451.815
661.295
1113.110 Sqm
44.309
126.270
170.579 Sqm
Det-Civil
QUANTITY Unit
481.364 Sqm
119.400 Sqm
95.175 Sqm
205.606 Sqm
214.535 Sqm
214.535 Sqm
226.720 Sqm
68.000 Rmt
Det-Civil
CIVIL DATAS
As per Common SSR 2015-16
Name of Work :- Construction of Commercial Complex (Cellar+Gr
Maddilapalem, Visakhapatnam in the place of existing A & B S
Earth work excavation for foundations and depositing on bank for all lifts and with an init
operational, incidental, labour charges such as shoring incidental, sheeting, planking, struttin
1
item of work .in ordinary soils by manual means upto 3.00mt depth excluding dewatering c
(APSS 308)
Data-Civil
Earth work excavation for foundations and depositing on bank for all lifts and with an init
operational, incidental, labour charges such as shoring incidental, sheeting, planking, struttin
1A
item of work .in ordinary soils by Mechanical means upto 3.00mt depth excluding dewaterin
B (APSS 308)
Data-Civil
Laying PCC work of mix (1 : 4 : 8) prop. Using 40 mm gauge hard granite machine crush
2
conveyance of all materials, machine mixing, labour charges, tamping, curing, taxes etc., com
Data-Civil
Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 usi
minimum cement content of 380 Kg. per Cum with 12mm and 20mm size graded machine
(coarse aggregate) from approved quarry including cost and conveyance of all materials
( sand) coarse aggregate, water etc., to site and including, sales & other taxes on all mater
3 incidental and labour charges such as weigh batching, machine mixing, laying concrete, Vi
but excluding cost of steel and its fabrication charges for finished item of work (APSS
shuttering using adjastable Jack Screws, Props and Acro span beams including all pipe bra
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
cost of steel and its fabrication charges for finished item of work. FOUNDATIONS, PLINTH, P
Data-Civil
A) FOR FOOTINGS
Cost of M30 Grade Concreate Cum 1
Centring charges Cum 1
(Item No.1A P.No.66)
Add M.L 40% on labour charges 473.00 Cum 1
Total (Item No.IA, P.No.66). Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Sundries Rs.
Total
Data-Civil
B) PEDESTALS
Cost of M30 Grade Concreate Cum 1
Centring charges Cum 1
(Item No.1C P.No.66)
Add M.L 40% on labour charges 753.00 Cum 1
Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Sundries Rs.
Total
Data-Civil
C) PLINTH BEAMS
Cost of M30 Grade Concreate Cum 1
Centring charges Cum 1
(Item No.1D P.No.66)
Add M.L 40% on labour charges 1141.00 Cum 1
Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Sundries Rs.
Total
Data-Civil
Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 usi
minimum cement content of 380 Kg. per Cum with 12mm and 20mm size graded machine
(coarse aggregate) from approved quarry including cost and conveyance of all materials
(sand) coarse aggregate, water etc., to site and including, sales & other taxes on all mater
incidental and labour charges such as weigh batching, machine mixing, laying concrete, vi
4
but excluding cost of steel and its fabrication charges for finished item of work (APSS
shuttering using adjastable Jack Screws, Props and Acro span beams including all pipe bra
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
cost of steel and its fabrication charges for finished item of work. COLUMNS, LINTELS, WAT
BUILDINGS.
Data-Civil
A II. PCC M30 for Steps
Data-Civil
B) For COLOUMNS centering with steel scaffolding pipes, jack props, steel centering plat
Data-Civil
C) FOR LINTELS centering with steel scaffolding pipes, jack props, steel centering plates
Data-Civil
D R.C.C.Side walls
1.00 Cum cost of VRCC M30 grade rate as per data Rs.
1.00 Cum centering charges as per Sl. No.315, P.No.267 of PH SOR.
at Rs.1115/0.23 Rs.
Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
SUNDRIES
TOTAL
Data-Civil
Filling with useful available excavated earth (excluding rock) in trenches, sides of foundati
lead in layers not exceeding 15 cm thick,consolidating each deposited layer by watering and
5
conveyance of water to work site and all operational, incidental, labour charges, hire charge
finisheditem of work. (APSS NO. 309 & 310) OUT PU
Data-Civil
Laying PCC work of mix (1 : 5 : 10) prop. Using 40 mm gauge hard granite machine crus
6 conveyance of all materials, machine mixing, labour charges, tamping, cruing charge
foundations.
A.P.Standard Data No.24 P.No.21 (BLD-CSTN-3.7).
A. MATERIALS:
Cement MT 0.1296
Coarse aggregate 40 mm (HBG Metal) -
Cum. 0.90
( as per chart)
Fine aggregate (Sand) Cum 0.45
Water (including for curing) Urban KL. 1.2
(P.No.223, Item No.189.a)
B. MACHINERY
Concrete Mixer 10/7 cft (0.2/0.8 Cum. Capacity)
Hour 1
300/200 Diesel (Pg.No.230,Item.16)
Add. 40% on Crew charges of 206.70 Hour 1
(P.No.289, Item No.18)
C. LABOUR:
Mason 1st class (including area allowance) Day 0.10
Man Mazdoor (including area allowance) Day 1.39
Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Sundries Rs.
Total
Data-Civil
Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 usin
Cum (6.00cum / Hr) using minimum cement content of 380 Kg. per Cum with 12mm and
crushed hard granite metal (coarse aggregate) from approved quarry including cost and con
cement, fine aggregate (sand) coarse aggregate, water etc., to site and including, sales &
7 including all operational, incidental and labour charges such as weigh batching, machine m
etc.,complete but excluding cost of steel and its fabrication charges for finished item of wo
centering shuttering using adjastable Jack Screws, Props and Acro span beams includin
couplings pre fabricated steel H-frames, cross members etc., Complete, laying concre
excluding cost of steel and its fabrication charges for finished item of work. CHAJJAS.
Data-Civil
Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using WEIG
cement content of 380 Kg. per Cum with 12mm and 20mm size graded machine crushed
aggregate) from approved quarry including cost and conveyance of all materials like ce
coarse aggregate, water etc., to site and including, sales & other taxes on all materials includ
8 and labour charges such as weigh batching, machine mixing, laying concrete, vibrate, curing
cost of steel and its fabrication charges for finished item of work (APSS No.402)includin
adjastable Jack Screws, Props and Acro span beams including all pipe bracings, clamps c
H-frames, cross members etc., Complete, laying concrete, vibrating, curing etc. complete bu
its fabrication charges for finished item of work. RCC SLABS, BEAMS.
Data-Civil
A) For Roof Slab centering with steel scaffolding pipes, jack props, steel centering plates
Data-Civil
B) For Roof Beam centering with steel scaffolding pipes, jack props, steel centering plate
Data-Civil
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm th
compound per bag of cement laid over roof when it is green including cost of all materials,, in
9
of materials and including all operational, incidental and labour charges for mixing mortar, l
thread lining, curing, rounding off junctions of wall and slab etc,, complete for finished item of
Data-Civil
Providing High Yield Strength Deformed Steel bars (Fe 415 Grade as per IS : 1786 an
different diameters including labour charges for cutting bending to required size shapes, p
blocks of approved materials and size and tying firmly with M.S. Binding wire of 20 SWG fo
work as per approved designs and drawings including cost and conveyance of deformed ste
10
such as overlaps, welded joints, chairs spacer bars including cost and conveyance of bind
incidental, opeartional labour charges including sales and other taxes on all materials etc., c
work in all floors (APSS No.126) (Payment will be made on the basis of weight of fabrication
rolled steel shall be allowed) complete for (8 mm to 40 mm).
Lift Add
Charges 13.615%
vide towards
Sl. Initial M.L. @
Floor P.No.131 Total contractor
No. Rate 40%
of 's profit &
A.P.Stand O.H.
ard data Charges
Data-Civil
Masonry work in CM (1:6) prop with Flyash Cement solid blocks of size 290 x 225 x 140 mm
solid blocks using flyash of 80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and stone dust inclu
11
all materials, labour charges, scaffolding and curing etc., complete with a compressive stren
for walls for Superstructure Walls. For Super Structure.
Data-Civil
Masonry work in CM (1:4) prop with Flyash Cement solid blocks of size 230 x 100 x 140 mm
solid blocks using flyash of 80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and stone dust inclu
12
all materials, labour charges,, scaffolding and curing etc., complete with a compressive stren
for walls for Superstructure Walls. For Partion walls.
Data-Civil
Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened sand with sponge
13
coneyance of all meterials hacking surface, scaffolding, leads, lifts and labour charges etc., c
A) MATERIALS:
Cement Mortar (1:4) as per mortar chart 0.15 3972.53
B) LABOUR:
Mason 1st class Day 0.60
Man Mazdoor (including area allowance) Day 0.96
Add: M.L. 40% ( 559.20 ) Day
Data-Civil
Providing plastering in CM(1:3), 20mm thick laid over Granolithic flooring bed when it
materials, seigniorage charges, including conveyance charges of materials and including a
14
labour charges for mixing mortar, laying, rendering smooth and thread lining, curing, round
floor etc,, complete for finished item of work FOR ORNAMENTAL PLASTERING.
Data-Civil
Plastering with CM 2 coats, 12 mm thick, base coat in CM (1:5), 8mm thick and top coa
sponze finishing to suit application of Altek finish including cost and conveyance of all mat
15
and all operational incidental labour charges such as mixing mortar, lift charges, curing etc.
work as per SS No. 901, 904 for Exterior Walls.
A) MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement MT 0.0317
Fine aggregate (Sand) Cum 0.11
Top Coat in CM(1:3), 4 mm thick
Cement MT 0.0192
Fine aggregate (Sand) Cum 0.04
B) LABOUR:
Mason 1st class Day 0.63
Mason 2nd class Day 1.47
Mazdoor (unskiled) Day 3.9
Add M.L 40% on labour charges 2063.85 X 40% Rs.
Total Rate per 10 Sqm. Rs.
Rate per 1 Sqm. Rs.
Data-Civil
Plastering with CM in 2 coats of 12 mm thick, base coat in CM (1:5) of 8mm thick, top c
with sponze finishing to suit application of Altek finish including cost and conveyance of all
16
site and all operational incidental labour charges such as mixing mortar, lift charges, curing e
of work as per SS No. 901, 904 for Interior Walls.
Data-Civil
Plastering with CM (1:3), 20 mm thickin single coat with Screened sand with sponge
17 coneyance of all meterials hancking surface, scaffolding, leads lifts and labour charges etc., c
FLOORING.
MATERIALS:
Cement Mortal 1:3 prop. Cum 0.21
Water proof compound 2.00 Kg. x Rs.52.00 (SOR-2014-15) Kg 2
LABOUR
Mason 1st class Day 0.66
Mason 2nd class Day 1.54
Mazdoor (unskiled) Day 3.70
Add M.L 40% on labour charges 2038.70 X 40%
Total Rate per 10 Sqm. Rs.
Add 13.615% contractor's Profit & Over Head charges Rs.
Total Rs.
Total Rate per 1 Sqm. Rs.
sundries Rs.
Total Rate per 1 Sqm.
Data-Civil
Granolithic concrete flooring 20 mm thick with (1:1:2) using 6mm to 12 mm size hard gra
18 already laid or RCC Roof slab in alternate panels of size not exceeding 1.5Mt x 1.5Mt. and
required slopes including cost of all materials like cement, metal, sand and water etc., comple
Data-Civil
Flooring with vitrified tiles of size not less than 598 mm x 598 mm, 8 to 10 mm thick g
normal colour 1st quality set over base coat of cement mortar (1:8), 12mm thick over CC b
19 slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & join
paste to full depth mixed with pigment of matching shade, Pointing with CM (1:3) includ
cement, sand water and tiles etc., complete, for finished item of work.
Data-Civil
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length
over base coat of CM (1:5) 12 mm thick with cement slurry of honey like consistency sprea
20
sqm and jointed with white cement paste mixed with pigment of matching shade to full
materials like tiles, cement, sand and water etc., complete for finished item of work.
Data-Civil
Flooring with ceramic tiles of 7.3mm thick of 1st quality of all shades set over base coa
mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of hone
21
3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment
cost of all materials like cement, sand water and tiles etc., complete, for finished item of work
Data-Civil
Dadoing walls with 1st quality of glazed plain coloured tiles of 5 to 7 mm thick of any size ce
and neat cement slurry of honey like consistency at the rate of 3.30 Kgs. cement per S
22 matching shade of tiles including charges, curing etc., complete as directed by the dep
inclusive of all taxes for
BATH ROOMS.
A.P.Standard Data No.116, Page No.57.
A. MATERIALS:
Ceramic Glazed tiles of 1st quality of size (5 to 7mm thick)
(P.No.17, S.No.44) (SOR-2014-15) Sqm 10.5
Cement for CM (1:8) proportion for base coat MT 0.0576
Cement for slurry 0.033
Sand for CM (1:8) 0.12
White cement for jointing & pointing (Sl.No.1154 Page No.64). Kg 6.00
LABOUR
Mason 1st class Day 0.77
Mazdoor (unskiled) Day 0.80
Add M.L 40% on labour charges 579.40 X 40%
Total Rs.
add: for water @ 1% on 6055.89
Total Rate per 10 Sqm. Rs.
Rate per 1 Sqm. Rs.
Data-Civil
Supply and fixing of High strength cement concrete designer tiles of 30mm thicknes of M40
shall be for color pigmentation with imported colour and white cement to get required refle
taxes. and over a bse coat of C.M.(1:8) Prop. 20 mm thick including neat cement slurry of h
23
at the rate of 3.30 Kg. per Sq,/ and filling the joints with white cement at 2.00 Kg. per S
matching shade including cost and conveyance of all materials, labour charges, laying of til
by the Department for Stair case and Portco.
Data-Civil
Providing and fixing door frame fabricated from section made of galvanized steel powder c
513,galvanized as per IS 217 with zinc of 120 grams/square meter). The factory made sect
coating of pure polyester powder of 50-60 microns thick with total coated thickness of 1
section should be of 105 x 60 mm with a rebate of 38mm to accommodate 30 mm thick door
24 gasket in the frame section, frame section to be filled with polyurethane foam. the frame se
and joined by way be way of welding. Each frame should be provided with : 2mm thick MS
100 mm long -3 Nos. for single shutter, 6Nos. double shutter. CRCA Electroplates stiffeners
for double shrtter and 40mm x 200 mm x 1.2 mm hold fasts screwed to stiffeners - 6Nos. wi
Receiver -1No. for single shutter frame. Tie Rod 1 No. DOOR FRAME FOR WITH OUT SILL
Unit- Each
Door size 0.91 x 2.13 m with out sill
Data-Civil
Supplying and fixing of PVC Door frames made from extruded sections in over all dimention
thickness of 1.55 mm. wiht usual porcess veriation of +/- 0.3mm complete and Sintex door
Hot Press Moulded SMC (Sheet moulding coumpound sheets, Polyurethene core and PVC
shall be made from SMC comforming to IS 13410 sheet shall have an average thickness o
sides. Core of the door shutter shall be filled with high density polyurethane foam , injecte
injection method shutter frame to be made of PVC extruded section confirming to IS:10151 :1
25 with a wall thickness of 1.4 mm +0.3mm on both sides corresponding to sintex code DWUF
shall be reinforced with special polymeric reinforcement wooden blocks of suitable size. The
shall be reinforced with Polymeric 'L' shaped angle of size 105 mm x 230 mm correspondi
lock rail shall be made from PVC extruded sections having overall dimensions of 26 mm x
both sides, with usual process variation corresponding to Sintex code 305 combining two n
inserted on the periphery. Suitable MS Tube reinforcement shall be provided on vertical sid
inclusive of all taxes and finished item work Color: White & Grey. SINTEX ENDURA DOOR S
Unit - Each
Cost of door frame vide P.No.51, Item No.717
@ Rs.244/Rmt.
For each door frame 0.76 + 1.98 +1.98 Rmt
4.72Rmt. (SOR-2014-15)
Door Shutter Size 0.76 x 2.13 = 1.6188 Sqm
cost of Shutter with frame (SOR-2014-15) Sqm
(As per item No.723 page No.52)
Cost of fixtures
1 No. 264 mm. long Aluminim Aldrop (IS2681 20mm long) Nos
(item No.262 page No. 12)
1 No. Cost of tower bolt (P.No.11 Item No.231) Nos
10 mm. bolt (IS204) 200 mm long.
2 Nos. 125 mm. long Alluminum Door handle (IS208) Nos
( As per P.No.12, Item No.255 )
3 Nos. But hinges (As per P.No.12, Item No.246) Nos
(IS 205)100 mm long.
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total
Data-Civil
Supply and fixing of Flush door single leaf flushdoor shutter of solid bond wood black board
to IS2202 commercial ply on both faces including cost of fixtures of M.S.Powder coated 1 No
26 of 200 mm long aldrop, 1 No. of 200 mm tower blot, 1 No. 125 mm long handle including
materials and labour charges etc., complete as per drawing and as directed by the departme
X 2.13 Mts.
Cost of fixtures
1No.250mm long 10mm dia MS powder coated Aldrop Nos
(item No.266 page NO.12)
1 No 200 mm long 12 mm dia MS powder coat Aldrop Nos
(item No.265 page No.12)
1 No 200 mm long 10 mm dia tower bolt powder coated Nos
( item No.238, page No.12)
1 No. 125 mm long MS. Power coated handle Nos
(item No.257 page NO.12)
Labour charges
1.785 Sqm labour charges Sqm
SSR item No.1058 page 59
Add: M.L. 40% on labour charges
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total
Data-Civil
Providing and fixing ofdouble Openable / Casement Windows with fly proof mesh made of
as per IS 513 of 0.80 mm. thick galvanized as per IS-277 with Zinc of 120 GSM), finish pain
60-65 microns thick and section for outer frame fo 100 x 45 mm., centre mullion of 100x60 m
25 mm x 0.6 mm thick, section for fly-shutter of 52 x 25 m x 0.6 mm thick and fitted with stain
of 304 grade with 144 holes per Sq.inch and mullions to have double rebate for glazed s
provision for guard bars/grills and the sections cut to length metre joined with corner brack
27
mullion cap, 1 No.of High grade nylon latch handle, window stopper, 2 Nos. of with MS pow
butt Hinges provided per shutter and windows fitted with 4 mm thick plain float glass with ru
the frames in concrete/ masonry wall by means of self expanding screws, including 10 mm
(152.4mm) pitch etc., complete for finished item of work. Windows of size 5'-0"x4'-0" (15
section of size 80x45mm, shutterframe section size of 52x25mm, vertical mullion section
section size of 9x12mm to be provided for glass holding.
Data-Civil
Providing and fixing of top hung Ventilators made of pre-painted steel (Base steel as
galvanized as per IS 277 with Zinc of 120 GSM), finish painted with a polyester paint of 60-
for outer frame of 80 x 45mm, centre mullion of 80 x 60mm, section for shutter of 52 x 25mm
and mullions to have rebate for glazed shutter with a provision for guard bars/ grills and the
joined with corner bracket, centre mullion fixed with mullion cap, 1No. of High grade nylon lat
28
Nos. of with MS powder coated / SS ball bearing but hinges provided per shutter and window
float glass with rubber gaskets including fixing the frames in concrete / masonry wall by mea
including 10mm square guard bars with 6" (152.4mm) pitch etc., complete for finished item
ventilator size of 2'-0" x 2'-0" (609.6 x 609.6 mm) outer frame box section size of 80 x 45mm
6" . Outer frame section size 72 x 0mm shutter frame section size of 47 x 20mm 0.91 x 0.46
Data-Civil
Supply and fixing of rolling shutter made of 80 x 1.25 mm. machine rolled CRCA laths, inter
entire length and jointed together at the ends by end locks, mounted on specially design
nominal bore MS. B class pipe wiht brackets, plates, guide channels, stoppers, bottom lock
29
for inside & outside locking with push-pull operations inlcuding cost of hood cover and spring
coat of approved steel primer, locks, ball bearings, all accessories etc., complete for finished
spn : 1108.
Data-Civil
PAINTING to new WOOD work / Iron work in two coats with synthetic enamel paint of appr
30 primary coat including cost and conveyance of all materials, incidental charges such as sand
cost of brushes and putty etc., complete. (Three coats).
Data-Civil
Providing and applying of wall putty of white cement or polymer or cement based of avera
plastered surface to prepare the surface even and smooth after throughly brushing the su
remains of loose powdered materials, applying emery paper ,sand the surface ,clean & w
31
knifing paste filler putty knife/muslin pad ,air dry for 2-3 hrs sand with 180 and 320no,e
preparation including cost and conveyance of all matrials to work site and all operational
complete for finished item of work for internal walls.
Data-Civil
Painting to new walls with 2 coats of water proof cement paint interior grade-I of approved b
coat of approved cement primer grade I making 3 coats in all to give an even shade after th
32
to remove all dirt and remains of loose ppowdered materials to work site and all operationa
etc., complete for finished item of work as per SS 912 for internal walls.
Data-Civil
Painting to new walls with 2 coats of water based cement primer of exteriorgrade -II paint o
over a base coat of approved cement primer grade-2 making 3 coats in all to give an even sh
33
the surface to remove all dirt and remains of loose ppowdered materials to work site and all o
charges etc., complete for finished item of work as per SS 912 for exterior walls.
Data-Civil
Supply and fixing 110 mm dia 4.00 Kg./Sq.Cm. pressure P.V.C.Pipe of Prince / Sudhakar ma
34 level including plain bend clips and shoe as per ISI. Standard fixed to wall with pipe clips in
complete for RAIN WATER PIPE.
Data-Civil
CIVIL DATAS
er Common SSR 2015-16
of Commercial Complex (Cellar+Ground+4Floors) at
am in the place of existing A & B Staff quarters.
depositing on bank for all lifts and with an initial lead of 10m including all
as shoring incidental, sheeting, planking, strutting, etc. complete for finished
means upto 3.00mt depth excluding dewatering charges etc. as per SS- 20 B
320.00 1164.80
873.60
2038.40
277.53
2315.93
231.59
0.01
231.60
Data-Civil
depositing on bank for all lifts and with an initial lead of 10m including all
as shoring incidental, sheeting, planking, strutting, etc. complete for finished
al means upto 3.00mt depth excluding dewatering charges etc. as per SS- 20
448.00 3727.36
2791.00 16746.00
20473.36
2787.45
23260.81
96.92
0.03
96.95
Data-Civil
Using 40 mm gauge hard granite machine crushed metal including cost and
, labour charges, tamping, curing, taxes etc., complete for foundations.
Unit = 1 cum
5873.00 951.43
1146.98 1032.28
1617.43 727.84
103.00 123.60
338.60 338.60
82.68 82.68
588.00 58.80
448.00 622.72
3937.95
536.15
0.00
4474.10
Data-Civil
crete of grade M30 corresponding to IS 456 using WEIGH BATCHER using
um with 12mm and 20mm size graded machine crushed hard granite metal
including cost and conveyance of all materials like cement, fine aggregate
e and including, sales & other taxes on all materials including all operational,
gh batching, machine mixing, laying concrete, Vibrating, curing etc.,complete
ation charges for finished item of work (APSS No.402 including centering
rops and Acro span beams including all pipe bracings, clamps couplings pre
etc., Complete, laying concrete, vibrating, curing etc. complete but excluding
nished item of work. FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth).
Unit = 1 cum
1666.98 883.50
1399.48 377.86
1617.43 646.97
5873.00 2231.74
103.00 123.60
588.00 78.20
525.00 140.18
448.00 2060.80
556.80 742.21
128.00 170.62
175.40 233.81
59.52 79.34
0.01
Rs. 7768.85
Data-Civil
7768.85 7768.85
750.00 750.00
189.20 189.20
8708.05
1185.60
Rs. 9893.65
Data-Civil
7768.85 7768.85
1068.00 1068.00
301.20 301.20
9138.05
1244.15
Rs. 10382.20
Data-Civil
7768.85 7768.85
2476.00 2476.00
456.40 456.40
10701.25
1456.98
0.03
Rs. 12158.26
Data-Civil
crete of grade M30 corresponding to IS 456 using WEIGH BATCHER using
um with 12mm and 20mm size graded machine crushed hard granite metal
including cost and conveyance of all materials like cement, fine aggregate
and including, sales & other taxes on all materials including all operational,
gh batching, machine mixing, laying concrete, vibrating, curing etc.,complete
ation charges for finished item of work (APSS No.402) including centering
rops and Acro span beams including all pipe bracings, clamps couplings pre
etc., Complete, laying concrete, vibrating, curing etc. complete but excluding
inished item of work. COLUMNS, LINTELS, WATER TANKS, RCC, WALLS IN
Unit 1 Cum
1666.98 883.50
1399.48 377.86
1617.43 646.97
5873.00 2231.74
103.00 123.60
588.00 98.20
525.00 87.68
448.00 2508.80
556.80 742.21
128.00 170.62
175.40 233.81
59.52 79.34
0.02
Rs. 8184.35
Data-Civil
7871.21
13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
1456.75 0.04 12156.40
1456.75 0.04 12156.40
1479.82 0.03 12348.86
1625.60 0.02 13565.40
1659.14 0.03 13845.26
1692.67 0.03 14125.10
1726.40 0.04 14406.55
Data-Civil
ffolding pipes, jack props, steel centering plates etc.,.
8184.35
13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
1484.76 0.04 12390.15
1484.76 0.04 12390.15
1517.17 0.03 12660.55
1672.29 0.04 13955.05
1715.17 0.00 14312.80
1758.04 0.02 14670.60
1800.92 0.03 15028.40
Data-Civil
lding pipes, jack props, steel centering plates etc.,.
7871.21
13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
1456.75 0.04 12156.40
1456.75 0.04 12156.40
1456.75 0.04 12156.40
1579.47 0.00 13180.45
1589.94 0.02 13267.85
1600.42 0.04 13355.26
1610.89 0.00 13442.60
Data-Civil
8184.35
4847.83
13032.18
1774.33
Rs. 14806.51
Data-Civil
rth (excluding rock) in trenches, sides of foundations and basement with initial
nsolidating each deposited layer by watering and ramming including cost and
erational, incidental, labour charges, hire charges of T & P etc., complete for
) OUT PUT : 6 CUM.
Unit = 1 cum
448.00 1397.76
103.00 74.16
1471.92
200.40
Rs. 1672.32
Rs. 278.72
0.03
Rs. 278.75
Data-Civil
. Using 40 mm gauge hard granite machine crushed metal including cost and
xing, labour charges, tamping, cruing charges, taxes etc., complete for
Unit - 1 Cum
5873.00 761.14
1146.98 1032.28
1617.43 727.84
103.00 123.60
338.60 338.60
82.68 82.68
588.00 58.80
448.00 622.72
3747.67
510.24
0.04
Rs. 4257.95
Data-Civil
crete of grade M30 corresponding to IS 456 using WEIGH BATCHER of 0.50
nt content of 380 Kg. per Cum with 12mm and 20mm size graded machine
ate) from approved quarry including cost and conveyance of all materials like
egate, water etc., to site and including, sales & other taxes on all materials
our charges such as weigh batching, machine mixing, laying concrete, curing
nd its fabrication charges for finished item of work (APSS No.402) including
Screws, Props and Acro span beams including all pipe bracings, clamps
cross members etc., Complete, laying concrete, curing etc. complete but
arges for finished item of work. CHAJJAS.
Unit -1 Sqm.
393.56
13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
157.08 0.00 1310.80
157.08 0.00 1310.80
160.70 0.03 1341.05
170.27 0.04 1420.90
174.41 0.00 1455.45
178.37 0.00 1488.45
182.51 0.01 1523.05
Data-Civil
ete of M 30 corresponding to IS 456 using WEIGH BATCHER using minimum
12mm and 20mm size graded machine crushed hard granite metal (coarse
g cost and conveyance of all materials like cement, fine aggregate (sand)
luding, sales & other taxes on all materials including all operational, incidental
, machine mixing, laying concrete, vibrate, curing etc.,complete but excluding
or finished item of work (APSS No.402)including centering shuttering using
pan beams including all pipe bracings, clamps couplings pre fabricated steel
aying concrete, vibrating, curing etc. complete but excluding cost of steel and
ork. RCC SLABS, BEAMS.
Unit 1 Cum
1666.98 883.50
1399.48 377.86
1617.43 646.97
5873.00 2231.74
103.00 123.60
588.00 39.40
525.00 69.83
448.00 1378.50
556.80 171.49
128.00 39.42
175.40 54.02
59.52 18.33
0.04
Rs. 6034.70
Data-Civil
olding pipes, jack props, steel centering plates etc.,.
6034.70
13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
1233.52 0.00 10293.55
1233.52 0.00 10293.55
1253.85 0.04 10463.24
1298.76 0.02 10838.00
1322.46 0.00 11035.75
1344.51 0.01 11219.75
1367.32 0.00 11410.10
Data-Civil
olding pipes, jack props, steel centering plates etc.,.
Rs. 6034.70
13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
1366.01 0.04 11399.15
1366.01 0.04 11399.15
1393.26 0.04 11626.60
1444.91 0.01 12057.55
1474.26 0.00 12302.50
1503.43 0.03 12545.90
1532.78 0.02 12790.85
Data-Civil
RCC roof slab surface with CM(1:3), 20mm thick with 1kg of water proof
when it is green including cost of all materials,, including conveyance charges
ncidental and labour charges for mixing mortar, laying, rendering smooth and
of wall and slab etc,, complete for finished item of work.
Unit = 1 Sqm
4677.29 982.23
52.00 104.00
420.00 277.20
375.00 577.50
320.00 1184.00
815.48
3940.41
394.04
Add
13.615%
towards
Sund -
contractor' Amount
ries
s profit &
O.H.
Charges
53.65 0.01 447.70
53.65 0.01 447.70
57.54 0.03 480.15
57.92 0.03 483.40
58.31 0.01 486.60
58.70 0.01 489.85
59.09 0.02 493.10
59.48 0.02 496.35
Data-Civil
Steel bars (Fe 415 Grade as per IS : 1786 and as amended upto date) of
s for cutting bending to required size shapes, placing in position with cover
tying firmly with M.S. Binding wire of 20 SWG forming grills for reinforcement
s including cost and conveyance of deformed steel bars, including all wastage
cer bars including cost and conveyance of binding wire cover blocks and all
ding sales and other taxes on all materials etc., complete for finished item of
will be made on the basis of weight of fabrication deformed bars only) (No re-
8 mm to 40 mm).
Unit -1MT
Sundries Amount
0.01 63465.35
0.01 63465.35
0.02 64753.75
0.03 64882.60
0.04 65011.45
0.00 65140.25
0.01 65269.10
Data-Civil
Cement solid blocks of size 290 x 225 x 140 mm for manufacturing of flyash
of 15 kgs.Gypsum of 5 kgs. and stone dust including cost and conveyance of
d curing etc., complete with a compressive strength not lessthan 50 kg/sqcm
r Structure.
Unit = 1 cum
24.00 2,640.00
-
3267.77 326.78
-
420.00 176.40
375.00 345.00
320.00 224.00
320.00 672.00
566.96
4,951.14
13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
732.49 0.02 6112.50
732.49 0.02 6112.50
773.77 0.04 6457.00
797.65 0.00 6656.30
821.61 0.00 6856.20
845.48 0.04 7055.45
869.44 0.04 7255.35
Data-Civil
Cement solid blocks of size 230 x 100 x 140 mm for manufacturing of flyash
of 15 kgs.Gypsum of 5 kgs. and stone dust including cost and conveyance of
nd curing etc., complete with a compressive strength not lessthan 50 kg/sqcm
on walls.
Unit = 1 cum
11.00 2,695.00
3972.53 397.25
-
420.00 176.40
375.00 345.00
320.00 224.00
320.00 672.00
566.96
5,076.61
towards
contractor' Sundires Amount
s profit &
788.88 0.01 6583.10
788.88 0.01 6583.10
843.51 0.04 7039.00
880.73 0.00 7349.55
918.06 0.04 7661.10
955.25 0.03 7971.45
992.58 0.02 8282.95
1029.77 0.01 8593.30
Data-Civil
singlecoat with. Screened sand with sponge finishing including cost and
scaffolding, leads, lifts and labour charges etc., complete for CEILING.
Rs. 595.88
420.00 252.00
320.00 307.20
223.68
Rs. 1378.76
towards
contractor' Sundires Amount
s profit &
20.80 0.00 173.60
21.50 0.01 179.40
22.95 0.03 191.55
23.72 0.01 197.95
24.49 0.04 204.40
25.26 0.02 210.80
26.03 0.01 217.20
Data-Civil
thick laid over Granolithic flooring bed when it is green including cost of all
onveyance charges of materials and including all operational, incidental and
endering smooth and thread lining, curing, rounding off junctions of wall and
FOR ORNAMENTAL PLASTERING.
Unit = 1 sqm
4677.29 982.23
420.00 277.20
375.00 577.50
320.00 1184.00
815.48
3836.41
522.33
4358.74
435.87
0.03
Rs. 435.90
Data-Civil
base coat in CM (1:5), 8mm thick and top coat in CM (1:3), 4mm thick with
finish including cost and conveyance of all materials and water to work site
s such as mixing mortar, lift charges, curing etc.complete for finished item of
Walls.
Unit -1Sqm.
5873.00 186.17
1684.43 185.29
5873.00 112.76
1684.43 67.38
420.00 264.60
375.00 551.25
320.00 1248.00
825.54
3440.99
344.10
13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
46.85 0.00 390.95
46.85 0.00 390.95
49.66 0.02 414.42
49.94 0.02 416.76
50.22 0.02 419.11
50.50 0.02 421.45
50.78 0.02 423.80
Data-Civil
hick, base coat in CM (1:5) of 8mm thick, top coat in CM (1:3) of 4mm thick
Altek finish including cost and conveyance of all material and water to work
arges such as mixing mortar, lift charges, curing etc.complete for finished item
Walls.
Unit = 1 Sqm
5873.00 186.17
1684.43 185.29
5873.00 112.76
1684.43 67.38
420.00 264.60
375.00 551.25
320.00 1248.00
825.54
3440.99
344.10
towards
contractor' Sundires Amount
s profit &
47.83 0.00 399.10
48.18 0.00 402.05
51.34 0.01 428.45
51.98 0.01 433.75
52.61 0.02 439.05
53.25 0.02 444.35
53.88 0.04 449.65
Data-Civil
single coat with Screened sand with sponge finishing including cost and
, scaffolding, leads lifts and labour charges etc., complete PLASTERING FOR
Unit = 1 sqm
4677.29 982.23
52.00 104.00
420.00 277.20
375.00 577.50
320.00 1184.00
815.48
3940.41
536.49
4476.90
447.69
0.01
Rs. 447.70
Data-Civil
with (1:1:2) using 6mm to 12 mm size hard granite metal laid over CC bed
panels of size not exceeding 1.5Mt x 1.5Mt. and finishing the top surface to
s like cement, metal, sand and water etc., complete for finished item of work.
1218.23 207.10
1684.43 143.18
5873.00 704.76
420.00 525.00
375.00 22.50
320.00 960.00
603.00
3165.54
430.99
3596.52
359.65
3.60
Rs. 363.25
Data-Civil
ss than 598 mm x 598 mm, 8 to 10 mm thick glossy finish premium colour
at of cement mortar (1:8), 12mm thick over CC bed already laid or RCC roof
like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement
matching shade, Pointing with CM (1:3) including cost of all materials like
for finished item of work.
Unit = 1 Sqm
1048.00 11004.00
5873.00 126.86
5873.00 193.81
1684.43 202.13
29.00 58.00
420.00 403.20
375.00 840.00
320.00 1056.00
919.68
14803.68
148.04
14951.71
1495.17
Sund -
Amount
ries
--
0.01 1698.75
0.04 1735.35
0.03 1739.00
0.03 1742.65
0.02 1746.30
0.01 1749.95
Data-Civil
m height/risers of steps with vitrified tiles length equal to flooring stones, set
th cement slurry of honey like consistency spread at the rate of 3.30 kgs per
mixed with pigment of matching shade to full depth, including cost of all
etc., complete for finished item of work.
Unit = 1 Sqm
1048.00 11004.00
5873.00 202.97
5873.00 193.81
1684.43 202.13
29.00 58.00
0.00
420.00 403.20
375.00 840.00
320.00 1056.00
919.68
14879.79
148.80
15028.59
1502.86
Sund -
Amount
ries
--
0.03 1707.50
0.01 1744.06
0.00 1747.70
0.04 1751.40
0.03 1755.05
0.03 1758.70
Data-Civil
ck of 1st quality of all shades set over base coat of cement mortar (1:8), 12
C roof slab, including neat cement slurry of honey like consistency spread @
cement paste to full depth mixed with pigment of matching shade, including
and tiles etc., complete, for finished item of work.
Unit = 1 sqm
465.00 4882.50
5873.00 126.86
5873.00 193.81
1684.43 202.13
29.00 58.00
420.00 403.20
375.00 840.00
320.00 1056.00
919.68
8682.18
86.82
8769.00
876.90
Sund -
Amount
ries
--
0.01 996.30
0.04 1032.90
0.03 1036.55
0.02 1040.20
0.02 1043.85
0.01 1047.50
Data-Civil
in coloured tiles of 5 to 7 mm thick of any size cement base in C.M.(1:3) Prop.
sistency at the rate of 3.30 Kgs. cement per Sq.mt. mixed with pigment of
, curing etc., complete as directed by the department for finished of work
Unit = 1 sqm
413.00 4336.50
5873.00 338.28
5873.00 193.81
1684.43 202.13
29.00 174.00
0.00
420.00 323.40
320.00 256.00
231.76
6055.89
60.56
6116.44
611.64
Sund -
Amount
ries
0.03 694.94
0.03 694.94
0.01 704.14
0.04 705.09
0.02 705.99
0.00 706.90
0.03 707.85
Data-Civil
oncrete designer tiles of 30mm thicknes of M40 Grade which top 12mm thick
ed colour and white cement to get required reflective glazing inclisive of all
p. 20 mm thick including neat cement slurry of honey like consistency spread
the joints with white cement at 2.00 Kg. per Sq.m. mixed with pigment of
ance of all materials, labour charges, laying of tiles etc., complete as directed
o.
Unit = 1 sqm
518.00 5439.00
5873.00 126.86
5873.00 193.81
1684.43 202.13
29.00 58.00
420.00 403.20
375.00 840.00
320.00 1056.00
919.68
9238.68
92.39
9331.06
933.11
Sund -
Amount
ries
0.00 1060.15
0.00 1060.15
0.03 1096.75
0.02 1100.40
0.02 1104.06
0.01 1107.71
0.00 1111.35
Data-Civil
from section made of galvanized steel powder coated (base steel as per IS
120 grams/square meter). The factory made section should be with a powder
microns thick with total coated thickness of 1.25 mm. Size of door frame
bate of 38mm to accommodate 30 mm thick door shutter with groove to insert
o be filled with polyurethane foam. the frame section should be cut to length
frame should be provided with : 2mm thick MS powder coated butt hinges of
os. double shutter. CRCA Electroplates stiffeners of 6 Nos. -3 in each vertical
2 mm hold fasts screwed to stiffeners - 6Nos. with split end tail. Nylon Aldrop
Rod 1 No. DOOR FRAME FOR WITH OUT SILL OF SIZE 0.91X2.13 M.
759.00 3924.03
3924.03
534.26
0.01
4458.30
Data-Civil
made from extruded sections in over all dimentions of 40 x 48mm having wall
eriation of +/- 0.3mm complete and Sintex door shutter made from specially
coumpound sheets, Polyurethene core and PVC Frame Section SMS sheets
13410 sheet shall have an average thickness of 1.4 mm +0.35 mm on both
ed with high density polyurethane foam , injected wiht the help of hydraulic
of PVC extruded section confirming to IS:10151 :1982 of size 26 mm x 46 mm
both sides corresponding to sintex code DWUF 305. The hardware locations
einforcement wooden blocks of suitable size. The corners of the shutter frame
ed angle of size 105 mm x 230 mm corresponding to Sintex code PR-02 the
sections having overall dimensions of 26 mm x 46 mm 1.5 mm +0.3mm on
responding to Sintex code 305 combining two numbers. Wooden pieces are
e reinforcement shall be provided on vertical sides of shutter frame the rate
Color: White & Grey. SINTEX ENDURA DOOR SHUTTER (26MM THICK).
Unit - Each
Rs. 7388.33
Rs. 1005.92
Rs. 8394.25
Data-Civil
lushdoor shutter of solid bond wood black board type 30mmthick conforming
uding cost of fixtures of M.S.Powder coated 1 No. 250 mm long aldrop, 1 No.
tower blot, 1 No. 125 mm long handle including cost and conveyance of all
e as per drawing and as directed by the department for DOOR OF SIZE: 0.91
Unit :: Each
Rs. 248.47
Rs. 3571.14
Rs. 486.21
Rs. 4057.35
Data-Civil
asement Windows with fly proof mesh made of pre-painted steel (Base steel
as per IS-277 with Zinc of 120 GSM), finish painted with a polyester paint of
ame fo 100 x 45 mm., centre mullion of 100x60 mm, section for shutter of 52 x
r of 52 x 25 m x 0.6 mm thick and fitted with stainless steel 32 gauge fly mesh
and mullions to have double rebate for glazed shutter and fly-shutter with a
ons cut to length metre joined with corner bracket, centre mullion fixed with
h handle, window stopper, 2 Nos. of with MS powder coated/ SS ball bearing
ws fitted with 4 mm thick plain float glass with rubber gaskets including fixing
eans of self expanding screws, including 10 mm square guard bars with 6"
d item of work. Windows of size 5'-0"x4'-0" (1524x1219.20mm) outerframe
ction size of 52x25mm, vertical mullion section of size 100x60mm beeding
ass holding.
Unit : Each
Rs. 1820.075
15188.23
0.02
Rs. 15188.25
Data-Civil
ors made of pre-painted steel (Base steel as per IS 513of 0.80mm thick
GSM), finish painted with a polyester paint of 60-65 microns thick and section
n of 80 x 60mm, section for shutter of 52 x 25mm x 0.6mm thick, outer frame
ter with a provision for guard bars/ grills and the sections cut to length metre
ed with mullion cap, 1No. of High grade nylon latch handle, window stopper, 2
aring but hinges provided per shutter and windows fitted with 4 mm thick plain
ng the frames in concrete / masonry wall by means of self expanding screws,
(152.4mm) pitch etc., complete for finished item of work. Single fixed louvers
mm) outer frame box section size of 80 x 45mm.Ventilator window 2'-6" x 1'-
ter frame section size of 47 x 20mm 0.91 x 0.46 mm. Ventilator window.
Unit : Each
Rs. 238.85
0.01
Rs. 1993.20
Data-Civil
80 x 1.25 mm. machine rolled CRCA laths, interiocked together through their
nds by end locks, mounted on specially designed pipe shaft of 50 mm. dia
ts, plates, guide channels, stoppers, bottom locking plates and arrangements
perations inlcuding cost of hood cover and springs complete, painted wiht one
earings, all accessories etc., complete for finished item of work as per special
Unit - 1 Sqm.
1.00 2861.00 2861.00
Rs. 389.53
0.02
Rs. 3250.55
Data-Civil
k in two coats with synthetic enamel paint of approved colour, over one coat of
of all materials, incidental charges such as sand paper, cleaning the surface,
hree coats).
Unit : 1 Sqm.
Data-Civil
e cement or polymer or cement based of average 1 to 2mm thickness over
ven and smooth after throughly brushing the surface to remove all dirt and
lying emery paper ,sand the surface ,clean & wipe off loose dust ,applying
air dry for 2-3 hrs sand with 180 and 320no,emery paper for the surface
of all matrials to work site and all operational ,incidental,labour chages etc
al walls.
Unit = 1 Sqm
43.75 1006.25
480.00 131.04
375.00 238.88
320.00 291.20
264.45
Rs. 1931.81
Rs. 263.02
Rs. 2194.83
Rs. 219.48
Rs. 0.02
Rs. 219.50
Data-Civil
proof cement paint interior grade-I of approved brand and shade over a base
king 3 coats in all to give an even shade after throughly brushing the surface
owdered materials to work site and all operational, incidental, labour charges
er SS 912 for internal walls.
Unit : 1 Sqm.
165.00 165.00
480.00 100.80
375.00 183.75
113.82
52.00 182.00
480.00 72.00
375.00 131.25
320.00 480.00
273.30
Rs. 1701.92
Rs. 231.72
Rs. 1933.64
Rs. 193.36
Rs. 0.04
Rs. 193.40
Data-Civil
based cement primer of exteriorgrade -II paint of approved brand and shade
r grade-2 making 3 coats in all to give an even shade after throughly brushing
f loose ppowdered materials to work site and all operational, incidental, labour
ork as per SS 912 for exterior walls.
Unit : 1 Sqm.
210.00 210.00
480.00 100.80
375.00 183.75
113.82
40.00 140.00
480.00 72.00
375.00 131.25
320.00 480.00
273.30
Rs. 1704.92
Rs. 232.12
Rs. 1937.04
Rs. 193.70
Rs. 193.70
Data-Civil
Cm. pressure P.V.C.Pipe of Prince / Sudhakar make from roof up to basement
s per ISI. Standard fixed to wall with pipe clips including labour charges etc.,
Unit - 1Rmt
161.33 161.33
9.00 9.00
70.00 70.00
Rs. 240.33
Rs. 32.72
Rs. 273.05
Data-Civil
ABSTRACT FOR INTERNAL WATER SUPPLY AND SANITARY
Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddi
Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Quantity Description of item Rate Unit
No.
SANITARY FITTINGS
ABS-Int.WS
Sl.
Quantity Description of item Rate Unit
No.
Supply & Fixing White glazed flat back half stall Urinals 1
St guailty conforming to I S 2556-1995 with standard C P
Spreader of over all size 95 x 95 x 57 mm conforming to I S
9 20.000 3477.75 EACH
2556-part 6, sec.6-1974 fixed with screws complete Indian
make ( H S W / Parry /Neycer ) 410 x 265 x305 mm and
12.70 mmdia N P push cock.
Supplying & Fixing Indian make Flat Back Wash Hand Basin
(HSW/Parryware/Neycer) 1st quality with single C.P.Pillar
cock, conforming to IS:2556-Part-4-1972 with waste fittings
like 38.10mm waste coupling, rubber plug, chain, 32 mm
nominal size C.P fitting with parallel pipe thread conforming
to IS/:2963-1979 and fitted with 12.70mm dia. Chromium
Plated Pillar tap of 1st quality Indian make 400 grams
10 20.000 Seiko / Esso or equivalent etc., complete with standard CI 1761.05 EACH
brackets including wooden block, 31.75 mm PVC flexible
waste pipe of 914.4mm long, 15mm inlet PVC connection
with unions complete, including cutting and making good the
walls where ever required for the following sizes etc.,
complete for different floors, including cost, all taxes and
conveyance of all materials and all labour charges etc.,
complete for finished item of work.
ABS-Int.WS
Sl.
Quantity Description of item Rate Unit
No.
Supplying and fixing 75 mm (3") dia., PVC Pipe of Prince
/Sudhakar make of 4 Kg/Sq.Cm. and jointing and making
14 240.000 holes and redoing the same in good condition including cost 207.95 1 RMT
and conveyance of material, Labour charges Fixing etc.,
complete.
Supplying and fixing 150 mm x 100 mm SWG GULLY TRAP
of ISI make conforming to ISI 651 & 4127 with C.I Grating
15 4.000 288.60 EACH
including Cost and Conveyance of all materials etc.,
complete.
Constructing brick masonry inspection chamber of size
457.2 mm x 457.2 mm (1'6"x1'6") in CM 1:6 prop. upto
914.4 mm (3'0") and fitted with light weight 457.2 mm x
16 4.000 3109.69 EACH
457.2 mm (1'6"x1'6") C.I frame and cover of 20 Kg.
including cost all taxes and conveyance of all materials etc.,
complete for finished item of work.
Supplying and fixing 110mm dia., PVC Vent Cowl of
Prince/Sudhakar make suitable for Vent pipe with air tight
17 8.000 21.60 EACH
joint including cost and of all material, Labour charges Fixing
etc., complete.
ABS-Int.WS
Sl.
Quantity Description of item Rate Unit
No.
Supplying and fixing of 76.20 mm dia P.V.C. Door Bends
Prince/Sudhakar are equivalent make suitable for bath room
21 4.000 conneciton including cost and conveyance of all materials 76.15 EACH
jointing labour chareges for fixing etc. complete as directed
by the Department.
Supplying and fixing of 75 mm dia P.V.C. Door Tee
Prince/Sudhakar are equivalent make suitable for bath room
22 32.000 conneciton including cost and conveyance of all materials 82.95 EACH
jointing labour chareges for fixing etc. complete as directed
by the Department.
Constructing Brick masonry chamber over the gully trap or
peet valve and fitted with 304.8 x 228.6 m size CI frame and
23 4.000 538.55 EACH
hinged cover including plastering and finishing etc.,
complete.
Supplying and fixing 50.8 Cm dia C.I. Man hole frame &
25 2.000 cover for chamber (Medium weight) as per IS:1726-40Kgs. 3048.30 EACH
For Water Tanks.
TOTAL
Add L.S for unforceen items
Say. TOTAL:
ABS-Int.WS
R INTERNAL WATER SUPPLY AND SANITARY
mmercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
n the place of existing A & B staff quarters.
Amount
170,599.00
125,268.00
5,863.00
14,475.00
25,297.50
28,018.00
10,771.00
5,386.00
ABS-Int.WS
Amount
220,164.00
69,555.00
35,221.00
3,477.00
104,348.79
10,722.00
ABS-Int.WS
Amount
49,908.00
1,154.40
12,438.78
172.80
17,762.60
2,074.60
2,954.00
ABS-Int.WS
Amount
304.60
2,654.40
2,154.20
3,727.00
6,096.60
930,567.27
3,899.71
934,466.98
ABS-Int.WS
DETAILED ESTIMATE For W/S And S/F
A 54 mm dia OD pipe
Tank to Roof Slab 1 x 1 72.00 -- --
From ground sump to over head tank inlet 1 x 1 75.00 -- --
From Top Floor to 1st Floor 1 x 8 15.00 -- --
From 1st Floor to Cellar 1 x 1 19.00 -- --
Total :
B 28.60 mm dia OD pipe
From Top Floor to 1st Floor 1 x 4 x 16 5.00 -- --
From 5th Floor, G.F. and Cellar Floor 1x 2x 4 5.00 -- --
For Tap connection 1 x 40 x 4.00 -- --
Total :
2 Supplying and Fixing of 12.70mm NP Bib tap indian
make heavy duty, Seiko or equivalent fancy type
deluxe with necessary fittings etc., complete
including cost and conveyance of all materials, all
taxes and all labour charges for finished item.
1
Det-Int.WS
Sl.
No. Description of Item Nos. L B D
Angle valves 4x 5 -- -- --
7 Supply and fixing of 38.1 mm C.P. waste coupling
Half or Full Thead 1st Quality Indian make
Parryware of equivalent.
For coupling with pipe 4x 5 -- -- --
FOR SANITARY
8 Supply, Installation and commissioning approved
make floor mounted EWC (suit), White coloured
CASCADE model 'P' of 'S' trap with dual flush
porcelain cistern fixed on EWC with all internal parts
of dual flush cistern, ultra solid seat cover of
approved make with rubber buffer and cap 15 mm
angle stop cock 450 mm long PVC inter connection
pipe wall flanges all of approved make etc.
completeincluding cost, all taxes and all labour
charges etc., complete including cutting and making
good the walls and floors wherever required as
directed by Engineer-in-charge.
CASCADE 4x 5 -- -- --
9
Supply & Fixing White glazed flat back half stall
Urinals 1 St guailty conforming to I S 2556-1995 with
standard C P Spreader of over all size 95 x 95 x 57
mm conforming to I S 2556-part 6, sec.6-1974 fixed
with screws complete Indian make ( H S W /
Parry /Neycer ) 410 x 265 x305 mm and 12.70
mmdia N P push cock.
White glazed flat back stall Urinals 4x 5 -- -- --
1
Det-Int.WS
Sl.
No. Description of Item Nos. L B D
12
Supplying and fixing 110 mm (4") dia., PVC Vent
pipe of Prince /Sudhakar make and jointing and
making holes and redoing the same in good
condition including cost and conveyance of material,
Labour charges Fixing etc., complete.
W.C. Connections G.F. to 4th Floor 5 x 4 2.44 -- --
Connections Cellar 1 x 4 2.44 -- --
Vertical vent pipe 1 x 4 22.00 -- --
IC to IC connection 2 x 4 12.20 -- --
Chamber to chamber connection 1 x 2 54.00 -- --
septic tank to out side
drain connection 1x 1 30.00 -- --
Total: Total :
13 Supplying and fixing 160 mm (6") dia., PVC pipe of
Prince /Sudhakar make of 4 Kg/ Sq.Cm. and jointing
and making holes and redoing the same in good
condition including cost and conveyance of material,
Labour charges Fixing etc., complete.
1
Det-Int.WS
Sl.
No. Description of Item Nos. L B D
Inspection Chamber 1x 4 -- --
17 Supplying and fixing 110mm dia., PVC Vent Cowl of
Prince/Sudhakar make suitable for Vent pipe with air
tight joint including cost and of all material, Labour
charges Fixing etc., complete.
2x 4 -- --
18 Constructing 904.0 mm (30) dia brick masonry
inspection chamber as per IS - 4111: Part-1:1986 with
cement mortar (1:6) prop using 2nd Class Clay Bricks of
225 mm thick from approved source having a minimum
crushing strength of 5 N/sq.mm including plastering with
cement mortar 1:3 prop; thick both inside and outside
fitted with 20 dia RCC manhole covers and frames
including excavating pits up to a depth of 904 mm (3'-0")
in all sorts of soils (exculding rock) and laying cement
conrete (1:4:8) 150 mm thick using 40 mm HBG Metal
and P.C.C. 1:2:4 benching and channel 100 mm thick as
per Standard specification and including cost and
conveyance of all materials like cement, sand, bricks,
water etc., to site, cost of seigniorage charges on all
materials and all incidental and operational, labour
charges like mixing cement mortar, constructing masonry,
lift charges, curing etc., complete for finished item of work
as per Standard specification.
1
Det-Int.WS
Sl.
No. Description of Item Nos. L B D
Door bends 4x 5 -- --
. Connections Cellar 5th Floor 1x 2 -- --
Total :
20 Supplying and fixing of 110 mm dia P.V.C. Door
Single Tee Prince/ Sudhakar are equivalent make
suitable for bath room conneciton including cost and
conveyance of all materials jointing labour chareges
for fixing etc. complete as directed by the
Department.
Door Tee 4x 5 -- --
21 Supplying and fixing of 76.20 mm dia P.V.C. Door
Bends Prince/Sudhakar are equivalent make
suitable for bath room conneciton including cost and
conveyance of all materials jointing labour chareges
for fixing etc. complete as directed by the
Department.
Top floor 1x 4 -- --
22 Supplying and fixing of 75 mm dia P.V.C. Door Tee
Prince/Sudhakar are equivalent make suitable for
bath room conneciton including cost and
conveyance of all materials jointing labour chareges
for fixing etc. complete as directed by the
Department.
1
Det-Int.WS
LED ESTIMATE For W/S And S/F
72.000
75.000
120.000
19.000
286.000 Rmt
320.000
40.000
160.000
520.000 Rmt
20.000 Nos.
20.000 Nos.
1
Det-Int.WS
Quantity
6.000 Nos.
20.000 Nos.
20.000 Nos.
20.000 Nos.
20.000 Nos.
20.000 Nos.
1
Det-Int.WS
Quantity
20.000 Nos.
30.000 Nos.
48.800
9.760
88.000
97.600
108.000
30.000
382.160 Rmt
20.000 Rmt
1
Det-Int.WS
Quantity
160.000
80.000
240.000 Rmt
4.000 Nos
4.000 Nos
8.000 Nos
2.000 Nos
1
Det-Int.WS
Quantity
20.000
2.000
22.000 Nos
20.000 Nos
4.000 Nos
32.000 Nos
4.000 Nos
20.000 Nos
2.000 Nos
1
Det-Int.WS
L EAD C HAR T
6 MM Hard
1 granite metal Rapaka 29 1 Cum 735.00 386.40 46.30 340.10
10 mm hard
2 granite metal Rapaka 29 1 Cum 935.00 386.40 46.30 340.10
12.5 mm
hard granite
3 metal Rapaka 29 1 Cum 1097.50 386.40 46.30 340.10
20 mm hard
4 granite metal Rapaka 29 1 Cum 1365.00 386.40 46.30 340.10
40 mm hard
5 granite metal Rapaka 29 1 Cum 845.00 386.40 46.30 340.10
Sand for
Concrete
( Un Bonthala
6 sreened) Koduru 14 1 Cum 95.00 197.40 23.66 173.74
Sand for Bonthala
7 mortar Koduru 14 1 Cum 165.00 197.40 23.66 173.74
Steel (HYSD
12 Bars) Local 1 MT. 34500.00 --
13 Cement Local 1 MT. 6600.00 --
14 Bitumen Vizag HPCL 119 1 MT. 28435.93 837.40 100.35 737.05
Flyash Lime
Solid Bricks
size: 29 x Each 24.00 0.00
22.5 x 14
Cm.
50 Kgs./1
15 Sq.Cm. Local
Flyash Lime
Solid Bricks Each 20.00 0.00
size: 29 x 15
x 14 Cm.
50 Kgs./1
16 Sq.Cm. Local
Flyash Lime
Solid Bricks
Size 29 x 10 Each 11.00 0.00
x 14 Cm.
50 Kgs./1
17 Sq.Cm. Local
9.5 to 11.20
mm HBG
18 metal Rapaka 29 1 cum 656.00 386.40 46.30 340.10
5 to 7 mm
HBG metal
19 IRC Rapaka 29 1 Cum. 504.00 386.40 46.30 340.10
65 mm HBG
20 metal IRC Rapaka 29 1 Cum. 379.00 386.40 46.30 340.10
19 to 22mm
HBG metal
21 IRC Rapaka 29 1 Cum. 984.00 386.40 46.30 340.10
2.36 to 5 mm
HBG metal
22 IRC Rapaka 29 1 Cum. 308.00 386.40 46.30 340.10
40 to 45 mm
HBG metal
23 IRC Rapaka 29 1 Cum. 588.00 386.40 46.30 340.10
Name of Work :- PATRUNIVALASA,SRIKAKULAM.
Cement Mortor Chart
QtY Unit Rate Amount
Cement ( 1 ; 1 ) Prop
Cement 1440.00 Kgs 1 Cum 6.60 9504.00
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
9943.68
Cement ( 1 ; 3 ) Prop
Cement 480.00 1 Cum 6.60 3168.00
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
3607.68
Cement ( 1 ; 4 ) Prop
Cement 360.00 1 Cum 6.60 2376.00
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
2815.68
Cement ( 1 ; 5 ) Prop
Cement 288.00 1 Cum 6.60 1900.80
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
2340.48
Cement ( 1 ; 6 ) Prop
Cement 240.00 1 Cum 6.60 1584.00
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
2023.68
Cement ( 1 ; 8 ) Prop
Cement 180.00 1 Cum 6.60 1188.00
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
1627.68
Seignorage GRAND
Reference
charges TOTAL
Item No.50,
0.00 P.No.27 1075.10
Item No.51,
0.00 P.No.27 1275.10
Item No.52,
0.00 P.No.27 1437.60
Item No.53,
0.00 P.No.27 1705.10
Item No.55,
0.00 P.No.28 1185.10
Item No.27,A
0.00 P.No.308 268.74
Item No.27,A
0.00 P.No.309 338.74
Item No.27,B
0.00 P.No.309 268.74
Item No.8,
0.00 P.No.25 332.20
Item No.22
0.00 A, P.No.15 520.10
27.73
34500.00
6600.00
29172.98
Item No.10,
P.No.13 24.00
Item No.12,
P.No.13 20.00
Item No.13,
P.No.13 11.00
Item No.41,
P.No.27 996.10
Item No.4,
P.No.18 844.10
Item No.54,
P.No.18 719.10
Item No.49,
P.No.18 1324.10
Item No.45,
P.No.18 648.10
Item No.51,
P.No.18 928.10
STATEMENT SHOWING THE LABOUR RATES INCLUDING
ALLOWANCES 20%
Rate/D 20%
Sl No Description ay allowence Total Amt
1 MM 350 70 420
Remarks
Page No 8,Sl No 3
Page No 6,Sl No 11
Page No 8,Sl No 35
Page No 7,Sl No 35
Page No 8,Sl No 37
Page No 6,Sl No 11
Page No 6,Sl No 2
Page No 6,Sl No 4
Page No 7,Sl No 4
Page No 6,Sl No 5
CIVIL DATA
As per Common SSR
Name of Work :- PATRUNIVALAS
Earth work excavation for foundations and depositing on bank for all lif
1 labour charges such as shoring incidental, sheeting, planking, strutting
means upto 3.00mt depth excluding dewatering charges etc. as per SS
Rate of 1 Cum
Add Sundreis
Sundries
Laying PCC work of mix (1 : 4 : 8) prop. Using 40 mm gauge hard g
4
materials, machine mixing, labour charges, tamping, curing, taxes etc.,
Supply and placing of the Design Mix Concrete of grade M30 correspo
using minimum cement content of 380 Kg. per Cum with 12mm and
aggregate) from approved quarry including cost and conveyance of all
etc., to site and including, sales & other taxes on all materials inclu
13
batching, machine mixing, laying concrete, curing etc.,complete but e
work (APSS No.402) including centering shuttering using adjastable Ja
clamps couplings pre fabricated steel H-frames, cross members etc., C
steel and its fabrication charges for finished item of work. CHAJJAS, L
Lift Charges =
0.05 Cum Cost of M30 GradePlastring
Concreate @ Rs.6204.03
in Centering Charges vide Item
C.M (1:4) P.No.66 & 68 of SSR
Sl.
Floor InitialRate vide data Material
No.
No.13 for 2
1 G.F 307.94 Sqm.
251.70 224.00
2 FF 307.94 251.70 224.00
3 2nd Floor 307.94 251.70 224.00
4 3rd Floor 307.94 251.70 224.00
5 4th Floor 322.96 251.70 224.00
6 5th Floor 322.96 251.70 224.00
7 6th Floor 322.96 251.70 224.00
8 7th Floor 322.96 251.70 224.00
9 8th Floor 322.96 251.70 224.00
Supply and placing of the Design Mix Concrete of M 30 corresponding
of 380 Kg. per Cum with 12mm and 20mm size graded machine cr
including cost and conveyance of all materials like cement, fine aggreg
& other taxes on all materials including all operational, incidental an
14
concrete, vibrate, curing etc.,complete but excluding cost of stee
No.402)including centering shuttering using adjastable Jack Screws,
couplings pre fabricated steel H-frames, cross members etc., Complet
of steel and its fabrication charges for finished item of work. RCC BEAM
1 GF 4993.01 2002.00
2 FF 4993.01 2002.00
3 2nd Floor 4993.01 2002.00
4 3rd Floor 4993.01 2002.00
5 4th Floor 4993.01 2002.00
6 5th Floor 4993.01 2002.00
7 6th Floor 4993.01 2002.00
8 7th Floor 4993.01 2002.00
9 8th Floor 4993.01 2002.00
15 For roof Slab.
Centering Charges vide Item
Sl. Initial P.No.131of SSR
Floor
No. Rate
Material
1 GF 4993.01 227.00
2 FF 4993.01 227.00
3 2nd Floor 4993.01 227.00
4 3rd Floor 4993.01 227.00
5 4th Floor 4993.01 227.00
6 5th Floor 4993.01 227.00
7 6th Floor 4993.01 227.00
8 7th Floor 4993.01 227.00
9 8th Floor 4993.01 227.00
Initial 10 %
Sl. No. Floor
Rate labour
charges
Rs.1600.
25 / 10
Sqms.
1 GF 278.19
2 FF 278.19 16.00
3 2nd Floor 278.19 17.60
4 3rd Floor 278.19 19.20
5 4th Floor 278.19 20.80
6 5th Floor 278.19 22.40
7 6th Floor 278.19 24.00
8 7th Floor 278.19 25.60
9 8th Floor 278.19 27.20
Providing High Yield Strength Deformed Steel bars (Fe 415 Grade
including labour charges for cutting bending to required size shapes,
and tying firmly with M.S. Binding wire of 20 SWG forming grills for r
17 cost and conveyance of deformed steel bars, including all wastage su
conveyance of binding wire cover blocks and all incidental, opeartiona
complete for finished item of work in all floors (APSS No.126) (Payme
only) (No re-rolled steel shall be allowed) complete for (8 mm to 40 mm
Lift
Charges
vide
P.No.131
Initial
Sl. No. Floor of
Rate
A.P.Stand
ard data
9050*10
%
1 GF 47445.00 -
2 FF 47445.00 905.00
3 2nd Floor 47445.00 995.50
4 3rd Floor 47445.00 1086.00
5 4th Floor 47445.00 1176.50
6 5th Floor 47445.00 1267.00
7 6th Floor 47445.00 1357.50
8 7th Floor 47445.00 1448.00
9 8th Floor 47445.00 1538.50
Masonry work in CM (1:6) prop with Flyash Cement solid blocks of siz
flyash of 80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and stone du
18
scaffolding and curing etc., complete with a compressive strength not
Structure.
A.P.Standard Data No.55 P.No.35 (BLD-CSTN-5-17).
A. MATERIALS:
No of blocks required for one cum of Masonry (As per chart)
110 Nos. x Rs. 20.00 / 1 No.
Cost of Cement Mortar (1:6) 0.10 Cum x Rs.2012.03 Cum
B. LABOUR
Mason 1st class
Mason 2nd class
Man Mazdoor
Woman Mazdoor
Add M.L 20% on labour charges
Total
Scaffolding charges vide P.No.133 of SSR - Rs.71.76/1Sqm.
Scaffolding charges material Rs.9.93/1Sqm./0.150 = Rs. 66.20/Cum
Scaffolding labour charges Rs.61.83/1Sqm./0.150 = Rs412.20/Cum
1 GF 4818.45 99.30
2 FF 4818.45 99.30
3 2nd Floor 4818.45 99.30
4 3rd Floor 4818.45 99.30
5 4th Floor 4818.45 99.30
6 5th Floor 4818.45 99.30
7 6th Floor 4818.45 99.30
8 7th Floor 4818.45 99.30
9 8th Floor 4818.45 99.30
Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened san
20
hacking surface, scaffolding, leads, lifts and labour charges etc., compl
A) MATERIALS:
Cement Mortar (1:4) as per mortar chart
B) LABOUR:
Mason 1st class
Mason 2nd class
Man Mazdoor
Add: M.L. 20% 1600.25
A) MATERIALS:
Cement Mortar (1:3) as per mortar chart
B) LABOUR:
Mason 1st class
Mason 2nd class
Man Mazdoor
Add: M.L. 20% 1600.25
A) MATERIALS:
Cement Mortar (1:5) as per mortar chart
B) LABOUR:
Mason 1st class
Mason 2nd class
Man Mazdoor
Add: M.L. 20% 1600.25 )
A) MATERIALS:
Cement Mortar (1:5) as per mortar chart
B) LABOUR:
Mason 1st class
Mason 2nd class
Man Mazdoor
Add: M.L. 20% ( 1600.25 )
vide
Initial
Sl. No. Floor P.No.131
Rate
of
1 G.F 1333.50 0.00
2 FF 1333.50 22.99
3 2nd Floor 1333.50 25.28
4 3rd Floor 1333.50 27.57
5 4th Floor 1333.50 29.86
6 5th Floor 1333.50 32.15
7 6th Floor 1333.50 34.44
8 7th Floor 1333.50 36.73
9 8th Floor 1333.50 39.02
Initial
Sl. No. Floor
Rate
10 %
Initial labour
Sl. No. Floor charges
Rate
Rs.2478.
20 for
10Sqm.
1 G.F 1352.23 --
2 FF 1352.23 24.78
3 2nd Floor 1352.23 27.25
4 3rd Floor 1352.23 29.72
5 4th Floor 1352.23 32.19
6 5th Floor 1352.23 34.66
7 6th Floor 1352.23 37.13
8 7th Floor 1352.23 39.60
9 8th Floor 1352.23 42.07
Flooring with NON-SKID ceramic tiles of 7.3mm thick of 1st quality
over CC bed already laid or RCC roof slab, including neat cement sl
25
neatly with white cement paste to full depth mixed with pigment of ma
and tiles etc., complete, for finished item of work.
A.P.Standard Data No.104 P.No.51 & 52.
A. MATERIALS:
Ceramic tiles of 1st quality of size ( 7.30mm thick)
(P.No.16, S.No.38) (SOR-2014-15)
Cement for CM (1:8) proportion for base coat
Cement for slurry
Cost of Sand
White cement for jointing & pointing (Sl.No.1154 Page No.64).
LABOUR
Providing and fixing door frame fabricated from section made of galva
per IS 217 with zinc of 120 grams/square meter). The factory made sec
60 microns thick with total coated thickness of 1.25 mm. Size of door
accommodate 30 mm thick door shutter with groove to insert gasket in
28
the frame section should be cut to length and joined by way be way
powder coated butt hinges of 100 mm long -3 Nos. for single shutter,
each vertical for double shrtter and 40mm x 200 mm x 1.2 mm hold
Receiver -1No. for single shutter frame. Tie Rod 1 No. DOOR FRAME
Door size 0.91 x 1.98 m with sill
Providing and fixing door frame fabricated from section made of galva
per IS 217 with zinc of 120 grams/square meter). The factory made sec
60 microns thick with total coated thickness of 1.25 mm. Size of door
accommodate 30 mm thick door shutter with groove to insert gasket in
29
the frame section should be cut to length and joined by way be way
powder coated butt hinges of 100 mm long -3 Nos. for single shutter,
each vertical for double shrtter and 40mm x 200 mm x 1.2 mm hold
Receiver -1No. for single shutter frame. Tie Rod 1 No. DOOR FRAME
Total
30 Supply and fixing of Flush door single leaf shutter of 30 mm thick with
thick on both faces including cost of fixtures of M.S.Powder coated ma
of 200 mm tower blot, 1 No. 125 mm long handle including cost and c
drawing and as directed by the department for DOOR OF SIZE: 0.91 X
b) Cost of fixtures
1No.250mm long 10mm dia MS powder coated Aldrop
(item No. 275page NO.23)
1 No 200 mm long 12 mm dia MS powder coat Aldrop
(item No.274 page No.22)
1 No 200 mm long 10 mm dia tower bolt powder coated
( item No.247, page No.21)
1 No. 125 mm long MS. Power coated handle
c) (item No.266 page NO.22)
Labour charges
1.65 Sqm labour charges
SSR item No.1107 page 120
Add: M.L. 20% on labour charges
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total
Supply and fixing of Flush door single leaf flushdoor shutter of so
commercial ply on both faces including cost of fixtures of M.S.Powder
31
No. of 200 mm tower blot, 1 No. 125 mm long handle including cost a
per drawing and as directed by the department for DOOR OF SIZE: 0.7
Cost of fixtures
1No.250mm long 10mm dia MS powder coated Aldrop
(item No.276 page NO.23)
1 No 200 mm long 12 mm dia MS powder coat Aldrop
(item No.274 page No.22)
1 No 200 mm long 10 mm dia tower bolt powder coated
( item No.247, page No.21)
1 No. 125 mm long MS. Power coated handle
(item No.257 page NO.12)
Labour charges
1.365 Sqm labour charges
SoR item No.1107page 120
Add: M.L. 20% on labour charges
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total
Supply and fixing of Flush door single leaf flushdoor shutter of solid
conforming to IS2202 commercial ply on both faces including cost of
32
200 mm long aldrop, 1 No. of 200 mm tower blot, 1 No. 125 mm lon
charges etc., complete as per drawing and as directed by the departme
Size Shutter 0.85 x 1.95 = 1.36 Sqm 1.657
cost of flush door shutter @ Rs.2188.00/1Sqm
(As per item No.817, Page No.65)
Cost of fixtures
1No.250mm long 10mm dia MS powder coated Aldrop
(item No.276 page NO.23)
1 No 200 mm long 12 mm dia MS powder coat Aldrop
(item No.274 page No.22)
1 No 200 mm long 10 mm dia tower bolt powder coated
( item No.247, page No.21)
1 No. 125 mm long MS. Power coated handle
(item No.257 page NO.12)
Labour charges
1.365 Sqm labour charges
SSR item No.1107page 120
Add: M.L. 20% on labour charges
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total
Supplying and fixing of PVC Door frames made from extruded section
mm. wiht usual porcess veriation of +/- 0.3mm complete and Sintex
moulding coumpound sheets, Polyurethene core and PVC Frame Se
sheet shall have an average thickness of 1.4 mm +0.35 mm on bo
polyurethane foam , injected wiht the help of hydraulic injection meth
IS:10151 :1982 of size 26 mm x 46 mm with a wall thickness of 1.4 m
33
The hardware locations shall be reinforced with special polymeric rein
frame shall be reinforced with Polymeric 'L' shaped angle of size 105 m
be made from PVC extruded sections having overall dimensions of 2
variation corresponding to Sintex code 305 combining two numbers
reinforcement shall be provided on vertical sides of shutter frame the r
SINTEX ENDURA DOOR SHUTTER (26MM THICK).
Painting to new walls with 2 coats of water proof cement paint interior
cement primer grade I making 3 coats in all to give an even shade a
40
loose ppowdered materials to work site and all operational, incidental, l
for internal walls.
A.P.Standared data no.172 p.no.81
44 Supplying and fixing of sink with polished Black Granite Stone of thick
and waste water pipe including cost and conveyance of all materials , l
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total
45
Providing & placing on terrace (at all floors levels) polyethylene water s
cover and suitable locking arrangement & making necessary holes for
supports for tanks.
PAINTING to new WOOD work / Iron work in two coats with synth
46 including cost and conveyance of all materials, incidental charges such
complete. (Three coats).
Ground
1 343.18
Floor
48 R.R.Masonary in C.M.(1:8) Prop. using hard stone other than granite in
etc., complete for FOUNDATION AND BASEMENT.
A) MATERIALS :
Cement
Rough Stone as per chart
Bond stone
Sand
B)
LABOUR
Mason 1st class
Man Mazdoor
Add M.L20% on labour
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries.
Total
CIVIL DATAS
As per Common SSR 2016-17
Work :- PATRUNIVALASA (v) SRIKAKULAM .
epositing on bank for all lifts and with an initial lead of 10m including all operational, inc
heeting, planking, strutting, etc. complete for finished item of work .in ordinary soils by m
ng charges etc. as per SS- 20 B (APSS 308)
Rs.
Total Rs.
fit & Over head charges Rs.
Total Rs.
Rs.
Total Rs.
Total Rs.
and conveyance of all materials and labour charges filling spreading sectioning,
ng etc complete as per SS Under Footings and Flooring
Unit 1 Cum.
Rs. 279.83
Rs. 108.5
Rs. 43.40
Rs. 431.73
Rs. 58.78
Rs. 0.04
Rs. 490.55
approved source to site for leveling the road portions as per standered specification inc
ur charges etc., complete.
Unit -1 CUM
Total Rs.
fit & Over head charges Rs.
Total Rs.
Total Rs.
sing 40 mm gauge hard granite machine crushed metal including cost and conveyanc
amping, curing, taxes etc., complete for foundations.
MT 0.162 6600.00
(
Cum. 0.90 1185.10
Cum 0.45 268.74
KL. 1.2 103.00
Unit = 1 cum
Rs.
Cum 1 5463.29
Cum 1 750.00
Cum 1 5463.29
Cum 1 1068.00
Cum 1 5463.29
Cum 1 2476.00
Rs.
6489.20
330.42
6158.78
Rs.
2344.00 (P.No.131, SI.No.1E)
1133.00
1211.00
0.30 =706.88 706.88
20%= 70.27
Charges = Rs. 777.15
Using 40 mm gauge hard granite machine crushed metal including cost and conveyanc
amping, cruing charges, taxes etc., complete for foundations.
TN-3.7).
MT 0.1296 6600.00
per chart) Cum. 0.90 1185.10
Cum 0.45 268.74
KL. 1.2 103.00
ty) 300/200 Diesel
Hour 1 352.50
te of grade M30 corresponding to IS 456 using WEIGH BATCHER of 0.50 Cum (6.00cu
per Cum with 12mm and 20mm size graded machine crushed hard granite metal
ost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate
xes on all materials including all operational, incidental and labour charges such as
uring etc.,complete but excluding cost of steel and its fabrication charges for finished
ttering using adjastable Jack Screws, Props and Acro span beams including all pipe br
es, cross members etc., Complete, laying concrete, curing etc. complete but excluding
em of work. CHAJJAS, Lofts & Racks.
6489.20
330.42
6158.78
0.30 =706.88 706.88 *0.05 35.34
CSTN-3.16)
Rs.
131, Sl.No.1H)
Lift Add
Centering Charges vide Item Charges 13.615%
No.1.h, P.No.131 of SSR vide towards
P.No.131 Total contractor
M.L of 's profit &
Labour A.P.Stand O.H.
@ 20%
ard data Charges
1426.00 285.20 -- 8706.21 1185.35
1426.00 285.20 -- 8706.21 1185.35
1569.00 313.80 777.15 9654.96 1314.52
1711.00 342.20 847.84 9896.05 1347.35
1854.00 370.80 918.53 10138.34 1380.33
1996.00 399.20 989.21 10379.42 1413.16
2139.00 427.80 1059.90 10621.71 1446.15
2282.00 456.40 1130.59 10864.00 1479.13
2424.00 484.80 1201.28 11105.09 1511.96
Lift Add
ntering Charges vide Item No.1.i, Charges 13.615%
P.No.131of SSR vide towards
P.No.131 Total contractor
M.L of 's profit &
Labour
@ 20% A.P.Stand O.H.
162.00 32.40 ard --data 5414.41 Charges
737.17
178.00 35.60 5433.61 739.79
194.00 38.80 777.15 6229.96 848.21
211.00 42.20 847.84 6321.05 860.61
227.00 45.40 918.53 6410.94 872.85
243.00 48.60 989.21 6500.82 885.09
259.00 51.80 1059.90 6590.71 897.33
275.00 55.00 1130.59 6680.60 909.56
292.00 58.40 1201.28 6771.69 921.97
C roof slab surface with CM(1:3), 20mm thick with 1kg of water proof compound per
luding cost of all materials,, including conveyance charges of materials and inclu
or mixing mortar, laying, rendering smooth and thread lining, curing, rounding off junc
of work.
TN-6-8).
0.45 445.00
1.05 400.00
2.80 350.00
1600.25 20%
Rs.
Rs.
Lift Charges vide P.No.131 of
A.P.Standard data Add
13.615%
towards
Total contractor
's profit &
M.L O.H.
Labour @ 20% Charges
- 278.19 37.88
3.20 297.39 40.49
3.52 299.31 40.75
3.84 301.23 41.01
4.16 303.15 41.27
4.48 305.07 41.54
4.80 306.99 41.80
5.12 308.91 42.06
5.44 310.83 42.32
Steel bars (Fe 415 Grade as per IS : 1786 and as amended upto date) of different dia
to required size shapes, placing in position with cover blocks of approved materials a
SWG forming grills for reinforcement work as per approved designs and drawings in
, including all wastage such as overlaps, welded joints, chairs spacer bars including c
d all incidental, opeartional labour charges including sales and other taxes on all materia
rs (APSS No.126) (Payment will be made on the basis of weight of fabrication deform
mplete for (8 mm to 40 mm).
TN-4-2).
MT. MT 1.050
Kg 6.000
Add
13.615%
towards
M.L. @
Total contractor' Sundries
20%
s profit &
O.H.
Charges
TN-5-17).
STN-5-17).
y (As per chart) Nos. 245 11.00
Cum 0.10 2815.68
TN-6-2).
m thick laid over Granolithic flooring bed when it is green including cost of all ma
charges of materials and including all operational, incidental and labour charges for
lining, curing, rounding off junctions of wall and floor etc,, complete for finished item
TN-6-1).
TN-8-2).
TN-8-2).
towards
M.L
TOTAL contractor' Total
@ 20%
s profit &
0 1333.50 181.56 1515.06
4.60 1361.09 185.31 1546.40
5.06 1363.84 185.69 1549.53
5.51 1366.59 186.06 1552.65
5.97 1369.34 186.44 1555.77
6.43 1372.08 186.81 1558.89
6.89 1374.83 187.18 1562.02
7.35 1377.58 187.56 1565.14
7.80 1380.33 187.93 1568.26
height/risers of steps with vitrified tiles length equal to flooring stones, set over base
honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white
to full depth, including cost of all materials like tiles, cement, sand and water etc., comp
plain coloured tiles of 5 to 7 mm thick of any size cement base in C.M.(1:3) Prop. an
e rate of 3.30 Kgs. cement per Sq.mt. mixed with pigment of matching shade of tiles in
the department for finished of work inclusive of all taxes for
o 7mm thick)
Sqm 10.5 691.00
MT 0.0576 6600.00
0.033 6600.00
0.12 338.74
Sl.No.1154 Page No.64). Kg 6.00 29.00
Unit- Each
Rs.
d charges Rs.
Rs.
Rs.
om section made of galvanized steel powder coated (base steel as per IS 513,galvan
ter). The factory made section should be with a powder coating of pure polyester powde
of 1.25 mm. Size of door frame section should be of 105 x 60 mm with a rebate of 38
groove to insert gasket in the frame section, frame section to be filled with polyurethan
nd joined by way be way of welding. Each frame should be provided with : 2mm th
-3 Nos. for single shutter, 6Nos. double shutter. CRCA Electroplates stiffeners of 6 No
x 200 mm x 1.2 mm hold fasts screwed to stiffeners - 6Nos. with split end tail. Nylon
od 1 No. DOOR FRAME FOR WITH SILL OF SIZE 0.91X1.98 M.
Unit- Each
Rmt 5.66 759.00
0.91 = 1.82
Rs.
d charges Rs.
Rs.
Rs.
om section made of galvanized steel powder coated (base steel as per IS 513,galvan
ter). The factory made section should be with a powder coating of pure polyester powde
of 1.25 mm. Size of door frame section should be of 105 x 60 mm with a rebate of 38
groove to insert gasket in the frame section, frame section to be filled with polyurethan
nd joined by way be way of welding. Each frame should be provided with : 2mm th
-3 Nos. for single shutter, 6Nos. double shutter. CRCA Electroplates stiffeners of 6 No
x 200 mm x 1.2 mm hold fasts screwed to stiffeners - 6Nos. with split end tail. Nylon
od 1 No. DOOR FRAME FOR WITH SILL OF SIZE 0.76X1.98 M.
Unit- Each
Rs.
d charges Rs.
Rs.
Rs.
hutter of 30 mm thick with solid bond wood black board type including commercial ply
of M.S.Powder coated make of 1 No. 250 mm long aldrop, 1 No. of 200 mm long aldrop
andle including cost and conveyance of all materials and labour charges etc., complete
r DOOR OF SIZE: 0.91 X 1.98 Mts.
Sqm 1.65
Nos 1.00
Sqm 1.650
d charges
flushdoor shutter of solid bond wood black board type 30mmthick conforming to
of fixtures of M.S.Powder coated 1 No. 250 mm long aldrop, 1 No. of 200 mm long a
g handle including cost and conveyance of all materials and labour charges etc., comp
nt for DOOR OF SIZE: 0.76 X 1.98 Mts.
Sqm 1.36
Nos 1.00
Sqm 1.365
d charges
ushdoor shutter of solid bond wood black board type with teak piy on both faces 35m
h faces including cost of fixtures of M.S.Powder coated 1 No. 250 mm long aldrop, 1
r blot, 1 No. 125 mm long handle including cost and conveyance of all materials and
s directed by the department for DOOR OF SIZE: 0.91 X 1.98 Mts.
Sqm 1.36
Nos 1.00
Sqm 1.365
d charges
ade from extruded sections in over all dimentions of 40 x 48mm having wall thickness
mm complete and Sintex door shutter made from specially Hot Press Moulded SMC
core and PVC Frame Section SMS sheets shall be made from SMC comforming to IS
1.4 mm +0.35 mm on both sides. Core of the door shutter shall be filled with high
f hydraulic injection method shutter frame to be made of PVC extruded section confir
a wall thickness of 1.4 mm +0.3mm on both sides corresponding to sintex code DWU
with special polymeric reinforcement wooden blocks of suitable size. The corners of the
haped angle of size 105 mm x 230 mm corresponding to Sintex code PR-02 the lock r
g overall dimensions of 26 mm x 46 mm 1.5 mm +0.3mm on both sides, with usual p
combining two numbers. Wooden pieces are inserted on the periphery. Suitable M
des of shutter frame the rate inclusive of all taxes and finished item work Color: White
THICK).
Unit - Each
Rmt 4.42
Sqm 1.39
Nos 3.00
d charges
Windows with fly mesh made of pre-painted steel (Base steel as per IS 513 of 0.80 mm
SM), finish painted with a polyester paint of 60-65 microns thick and section for outer fra
, section for shutter of 52 x 25 mm x 0.6 mm thick, section for flyshutter of 52 x 25 mm x
uge fly mesh of 304 grade with 144 holes per sq.inch and mullions to have double rebat
for guard bars/grills and the sections cut to length metre joined with corner bracket, cen
grade nylon latch handle, window stopper, 2 nos. of with MS Powder coated /SS ball bea
s fitted with 4 mm thick plain float glass with rubber gaskets including fixing the frames in
nding screws, Including 10 mm Square guard bars with 6 (152.4mm) pitch etc., comple
O.H.Charges
O.H.Charges
O.H.Charges
O.H.Charges
ade of pre-painted steel (Base steel as per IS 513 of 0.80 mm thick galvanized as per IS
olyester paint of 60-65 microns thick and section for outer frame of 80 x 45 mm, centre
mm x 0.6 mm thick, outer frame and mullions to have rebate for glazed shutter with a pr
ngth metre joined with corner bracket, centre mullion fixed with mullion cap, 1 No. of Hig
nos. of with MS Powder coated /SS ball bearing butt Hinges provided per shutter and wi
bber gaskets including fixing the frames in concrete/masonry wall by means of self expa
with 6 (152.4mm) pitch etc., complete for finished item of work., Single openable ventila
outer frame section size of 80 x 45mm, shutter for 0.76X0.61Mt size
O.H.Charges
Kg 23.00 43.75
roof cement paint interior grade-I of approved brand and shade over a base coat of ap
to give an even shade after throughly brushing the surface to remove all dirt and rem
all operational, incidental, labour charges etc., complete for finished item of work as per
Kg 1.00 165.00
day 0.21 510.00
day 0.49 400.00
303.10 X 20%
igh UV Resistant exterior paint
Kg 3.50 52.00
ate 1300/25 = 52.00/-) Kg
day 0.15 510.00
day 0.35 400.00
day 1.50 350.00
741.50 X 20%
Rs.
d charges Rs.
Rs.
te per 1 Sqm Rs.
Rs.
Rs.
ased cement primer of exteriorgrade -II paint of approved brand and shade over a base
coats in all to give an even shade after throughly brushing the surface to remove all d
k site and all operational, incidental, labour charges etc., complete for finished item of w
Rs.
Cm. pressure P.V.C.Pipe of Prince / Sudhakar make from roof up to basement level in
d fixed to wall with pipe clips including labour charges etc., complete for RAIN WATER P
19.53/1 Cum
O.H.Charges
ack Granite Stone of thick 16 to 18 mm sink thick of size 24" x 18" x 10" with a hole at
veyance of all materials , labour charges , curing etc complete.
s.2352.00
RM x 289.00/1RM
119 at Rs.15.00/1RM 2.44*15
O.H.Charges
evels) polyethylene water storage tank with double layer approved brand & manufacture
aking necessary holes for inlet & outlets and over flow pipes but without fittings & base
O.H.Charges
k in two coats with synthetic enamel paint of approved colour, over one coat of prima
s, incidental charges such as sand paper, cleaning the surface, cost of brushes and pu
Lit 0.70
Nos 0.70
00% on Rs.460.60
Lit 1.20
d charges
h (1:1:2) using 6mm to 12 mm size hard granite metal laid over CC bed already laid
ceeding 1.5Mt x 1.5Mt. and finishing the top surface to required slopes including cos
etc., complete for finished item of work.
d charges Rs.
Rs.
Rs.
Rs.
Rs.
MT 0.0594
Cum 0.94
Cum 0.16
Cum 0.33
Day 1.2
2
1234 X 20%
d charges
cluding all operational, incidental,
work .in ordinary soils by manual
1820.00
1365.00
3185.00
433.64
3618.64
361.86
0.04
361.90
eading sectioning,
tandered specification including
152.88
31.50
22.61
206.99
28.18
235.17
0.03
235.20
uding cost and conveyance of all
Unit = 1 cum
1069.20
1066.59
120.94
123.60
352.50
43.94
53.40
583.80
3413.96
464.81
0.02
3878.79
ATCHER using minimum cement
oarse aggregate) from approved
e, water etc., to site and including,
batching, machine mixing, laying
hed item of work (APSS No.402
e bracings, clamps couplings pre
but excluding cost of steel and its
Unit = 1 cum
954.85
345.02
107.50
2508.00
123.60
45.60
29.90
26.88
385.14
119.72
15.12
425.13
12.61
75.92
246.07
42.18
0.04
5463.29
5463.29
750.00
94.60
6307.89
858.82
0.03
7166.74
5463.29
1068.00
150.60
6681.89
909.74
0.01
7591.64
5463.29
2476.00
228.20
8167.49
1112.00
0.00
9279.49
ATCHER using minimum cement
oarse aggregate) from approved
, water etc., to site and including,
batching, machine mixing, laying
hed item of work (APSS No.402)
e bracings, clamps couplings pre
but excluding cost of steel and its
LDINGS.
Unit 1 Cum
954.85
345.02
107.50
2508.00
123.60
45.60
59.27
106.56
653.52
239.45
30.25
850.26
25.21
151.85
246.07
42.18
0.01
6489.20
6158.78
Sundires Amount
0.00 9935.61
0.00 9935.61
0.01 10983.55
0.03 11228.85
0.01 11474.11
0.04 11719.42
0.00 11966.02
0.03 12211.34
0.01 12456.60
6489.20
Sundires Amount
0.04 10077.92
0.04 10077.92
0.04 11192.65
0.00 11504.70
0.02 11816.80
0.03 12128.90
0.00 12440.96
0.01 12753.06
0.03 13065.16
6158.78
Sundires Amount
0.00 9935.61
0.00 9935.61
0.02 10983.56
0.04 11228.86
0.01 11474.11
0.02 11719.40
0.02 11966.04
0.00 12211.31
0.04 13449.30
Unit - 1 Cum
855.36
1066.59
120.94
123.60
352.50
43.94
53.40
583.80
3200.12
435.70
0.02
3635.84
Unit -1 Sqm.
per Sqm
307.94
Sundires Amount
0.04 1143.96
0.04 1143.96
0.00 1213.98
0.03 1242.56
0.04 1289.56
0.02 1318.09
0.02 1348.01
0.03 1377.94
0.00 1406.47
R using minimum cement content
aggregate) from approved quarry
r etc., to site and including, sales
batching, machine mixing, laying
finished item of work (APSS
cluding all pipe bracings, clamps
etc. complete but excluding cost
Unit 1 Cum
954.85
345.02
107.50
2508.00
123.60
45.60
17.62
32.16
181.86
71.73
9.06
254.70
7.55
45.49
246.07
42.18
0.03
4993.01
Rs. 4993.01
Sundires Amount
0.03 9891.59
0.03 9891.59
0.01 10969.49
0.00 11243.40
0.02 11518.69
0.02 11792.60
0.04 12067.90
0.01 12343.14
0.00 12617.05
Sundires Amount
0.01 6151.59
0.01 6173.41
0.04 7078.21
0.00 7181.66
0.02 7283.81
0.03 7385.94
0.03 7488.07
0.00 7590.16
0.01 7693.67
Unit = 1 Sqm
757.61
104.00
200.25
420.00
980.00
320.05
2781.91
278.19
Sund -
Amount
ries
- 316.07
0.04 337.92
- 340.06
0.02 342.26
0.04 344.46
0.01 346.62
0.03 348.82
- 350.97
0.02 353.17
upto date) of different diameters
s of approved materials and size
d designs and drawings including
s spacer bars including cost and
d other taxes on all materials etc.,
ght of fabrication deformed bars
Unit -1MT
34500.00 36225.00
60.00 360.00
555.00 5550.00
350.00 3500.00
Rs. 1810.00
Rs. 47445.00
Amount
53904.65
55138.50
55261.90
55385.30
55508.65
55632.05
55755.45
55878.85
56002.20
uring of flyash solid blocks using
of all materials, labour charges,
Superstructure Walls. For Super
Unit = 1 cum
2,200.00
-
202.37
-
186.90
368.00
245.00
735.00
306.98
4,244.25
Sundires Amount
0.01 5305.00
0.02 5459.32
0.03 5633.72
0.03 5887.01
0.01 6140.01
0.02 6393.77
0.03 6646.62
0.03 6900.36
0.04 7153.22
0.00 7406.92
turing of flyash solid blocks using
of all materials, labour charges,,
uperstructure Walls. For Partion
Unit = 1 cum
2,695.00
281.57
-
186.90
368.00
245.00
735.00
306.98
4,818.45
Sundires Amount
0.04 6570.82
0.00 6745.16
0.01 7175.37
0.00 7605.07
0.01 8036.07
0.01 8465.46
0.03 8896.47
0.03 9325.87
0.04 9756.86
st and coneyance of all meterials
422.35
200.25
420.00
980.00
320.05
2342.65
Sundires Amount
0.01 285.98
0.03 304.18
757.61
277.20
577.50
1184.00
407.74
3204.05
436.23
3640.29
364.03
0.04
364.07
0.02 312.92
0.02 321.68
0.01 330.43
0.00 339.18
0.04 347.97
0.00 356.68
0.04 365.48
st and coneyance of all meterials
541.15
200.25
420.00
980.00
320.05
2461.45
Sundires Amount
0.01 299.48
0.03 317.67
0.03 326.43
0.02 335.18
0.01 343.93
0.00 352.67
0.00 361.43
0.00 370.18
0.04 378.97
st and coneyance of all meterials
351.07
200.25
420.00
980.00
640.10
2591.42
Sundires Amount
0.04 304.01
0.02 322.17
0.00 327.51
0.00 332.86
0.04 338.27
0.04 343.61
0.03 348.97
0.03 354.32
0.02 359.67
st and coneyance of all meterials
351.07
200.25
420.00
980.00
320.05
2271.37
Sundires Amount
0.01 258.08
0.03 276.27
0.02 278.08
0.00 279.88
0.03 281.73
0.01 283.52
0.04 285.37
0.03 287.18
0.01 288.98
m colour normal colour 1st
ncluding neat cement slurry of
xed with pigment of matching
e, for finished item of work.
9870.00
142.56
217.80
40.65
58.00
403.20
840.00
1056.00
574.80
13203.01
132.03
13335.04
1333.50
Sund -
Amount
ries
0.02 1515.08
0.02 1546.42
0.00 1549.53
0.03 1552.68
0.01 1555.78
0.04 1558.93
0.01 1562.03
0.04 1565.18
0.02 1568.28
9870.00
228.10
217.80
40.65
58.00
427.20
896.00
1155.00
495.64
13388.39
133.88
13522.27
1352.23
Sund -
Amount
ries
Sund -
Amount
ries
0.04 1536.38
0.01 1570.13
0.04 1573.53
0.02 1576.88
0.00 1580.22
0.04 1583.63
0.02 1586.98
0.00 1590.33
0.03 1593.72
cement mortar (1:8), 12 mm thick
ad @ 3.3.kgs per sqm & jointed
materials like cement, sand water
Unit = 1 sqm
4882.50
142.56
217.80
40.65
58.00
427.20
896.00
1155.00
495.64
8315.35
83.15
8398.50
839.85
Sund -
Amount
ries
0.04 954.24
0 987.98
0.04 991.39
0.03 994.75
0.04 1042.55
0.04 1046.20
0.01 1049.80
0.00 1053.50
0.03 1057.10
Unit = 1 sqm
7255.50
380.16
217.80
40.65
174.00
342.65
280.00
124.53
8815.29
88.15
8903.44
890.34
Sund -
Amount
ries
0.02 1011.58
0.04 1020.08
0.04 1020.93
0 1021.73
0.00 1022.58
0.01 1023.43
0.01 1024.28
0.02 1025.13
0.02 1025.98
teel as per IS 513,galvanized as
g of pure polyester powder of 50-
60 mm with a rebate of 38mm to
be filled with polyurethane foam.
e provided with : 2mm thick MS
roplates stiffeners of 6 Nos. -3 in
. with split end tail. Nylon Aldrop
1X1.98 M.
3605.25
3605.25
490.85
0.00
4096.10
4295.94
584.89
0.02
4880.85
4113.78
4113.78
560.09
0.03
4673.90
including commercial ply of 3mm
No. of 200 mm long aldrop, 1 No.
our charges etc., complete as per
Unit :: Each
1314.00 2168.10
151.00 151.00
115.00 115.00
56.00 56.00
34.00 34.00
348 574.20
Rs. 114.84
Rs. 3213.14
Rs. 437.47
0.02
Rs. 3650.63
0mmthick conforming to IS2202
, 1 No. of 200 mm long aldrop, 1
labour charges etc., complete as
Unit :: Each
1314.00 1787.04
151.00 151.00
115.00 115.00
56.00 56.00
34.00 34.00
348 475.02
Rs. 95.00
Rs. 2713.06
Rs. 369.38
0.05
Rs. 3082.50
2188.00 3625.51
151.00 151.00
115.00 115.00
56.00 56.00
34.00 34.00
348 475.02
Rs. 95.00
Rs. 4551.53
Rs. 619.69
0.02
Rs. 5171.25
mm having wall thickness of 1.55
Hot Press Moulded SMC (Sheet
om SMC comforming to IS 13410
shall be filled with high density
C extruded section confirming to
nding to sintex code DWUF 305.
e size. The corners of the shutter
tex code PR-02 the lock rail shall
n both sides, with usual process
he periphery. Suitable MS Tube
d item work Color: White & Grey.
244.00 1078.48
3162.00 4395.18
329.00 329.00
141.00 141.00
126.00 252.00
132.00 396.00
Rs. 6591.66
Rs. 897.45
0.04
Rs. 7489.15
Rs. 10518.67
Rs. 10518.67
Rs. 1432.12
Rs. 0.06
Rs. 11950.85
RS 7846.59
Rs. 7846.59
Rs. 1068.31
0.00
Rs. 8914.90
RS 5020.51
Rs. 5020.51
Rs. 683.54
0.00
Rs. 5704.05
RS 3745.14
Rs. 3745.14
Rs. 509.90
0.01
Rs. 4255.05
m thick galvanized as per IS 277
me of 80 x 45 mm, centre mullion
or glazed shutter with a provision
h mullion cap, 1 No. of High
rovided per shutter and windows
wall by means of self expanding
k., Single openable ventilator
Mt size
RS 2830.28
Rs. 2830.28
Rs. 385.34
0.03
Rs. 3215.65
Unit = 1 Sqm
1006.25
139.23
254.80
318.50
142.51
1861.29
253.41
2114.70
211.47
0.03
211.50
Unit : 1 Sqm.
165.00
107.10
196.00
60.62
182.00
76.50
140.00
525.00
148.30
1600.52
217.91
1818.43
181.84
0.01
181.85
nd and shade over a base coat of
he surface to remove all dirt and
mplete for finished item of work as
Unit : 1 Sqm.
210.00
107.10
196.00
60.62
140.00
76.50
140.00
525.00
148.30
1603.52
218.32
1821.84
182.18
1.88
184.06
Unit - 1Rmt
161.33
9.00
70.00
240.33
32.72
273.05
y to full depth including cost and
orners suitable hole for gas pipe
Unit : 1 Sq.mt
Rs. 2469.60
Rs. 34.01
Rs. 21.78
Rs. 17.40
Rs. 544.20
Rs. 3086.99
Rs. 420.29
Rs. 0.97
Rs. 3508.25
Unit: Each
Rs. 2422.56
Rs. 705.16
36.60
Rs. 300.00
Rs. 3464.32
Rs. 471.66
Rs. 0.02
Rs. 3936.00
Unit 1 Each
Rs 4000.00
Rs. 544.60
Rs. 0.00
Rs. 4544.60
Unit : 1 Sqm.
158.00 110.60
400.00 280.00
Rs. 56.00
Rs. 4.60
276 331.20
400.00 480.00
96.00
Rs. 1358.40
Rs. 184.95
Rs. 1543.35
Rs. 154.33
0.02
Rs. 154.35
213.58
28.79
792.00
556.25
24.00
1050.00
326.05
2990.67
407.18
3397.85
339.79
3.40
0.00
343.18
0.02 389.92
materials, labour charges, curing
6600 392.04
520.10 488.89
520.10 83.22
268.74 88.69
445 534.00
350 700.00
246.80
2533.63
344.95
0.02
2878.60
ABSTRACT ESTIMATE
Name of the Work: Construction of G+3 houses for
No. of blocks
Unit cost for each flat =Rs
SNo. Qty Description of Item
Earth work excavation for foundations and depositing
on bank for all lifts and with an initial lead of 10m
including all operational, incidental, labour charges
such as shoring incidental, sheeting, planking,
1 454.61
strutting, etc. complete for finished item of work .in
ordinary soils by manual means upto 3.00mt depth
excluding dewatering charges etc. as per SS- 20 B
(APSS 308).
For Lofts
a 47.14 Ground Floor
b 47.14 First Floor
c 47.14 2nd Floor
d 47.14 3rd Floor
For Racks
a 70.06 Ground Floor
b 70.06 First Floor
c 70.06 2nd Floor
d 70.06 3rd Floor
Supply and placing of the Design Mix Concrete of M
30 corresponding to IS 456 using WEIGH BATCHER
using minimum cement content of 380 Kg. per Cum
with 12mm and 20mm size graded machine crushed
hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials
like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including, sales & other taxes
on all materials including all operational, incidental
and labour charges such as weigh batching, machine
14
mixing, laying concrete, vibrate, curing etc.,complete
but excluding cost of steel and its fabrication charges
for finished item of work (APSS No.402)including
centering shuttering using adjastable Jack Screws,
Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-
frames, cross members etc., Complete, laying
concrete, vibrating, curing etc. complete but
excluding cost of steel and its fabrication charges for
finished item of work. RCC ROOF BEAMS
59.96 Below PB
60.31 Ground Floor
60.31 First Floor
60.31 2nd Floor
60.31 3rd Floor
15.05 4 th Floor Stair Case Head room
53904.65 MT 718520.85
55138.50 MT 322049.99
55261.90 MT 322770.74
55385.30 MT 323491.49
55508.65 MT 35880.79
0.00
Sl.
Quantity Description of item Rate Unit
No.
ABS-Int.Elec.
Sl.
Quantity Description of item Rate Unit
No.
Supply and fixing of Modular (4 module box ) Type 16A/ 6A
one way combi socket modular socket with shutter of and
16A/10A module flush fuse with neon indicator duly on
8 100.000 349.95 Each
recessed in wall with suitable gang metalic flush box
including earth connection and all labour chargs
etc.,complete.
ABS-Int.Elec.
Sl.
Quantity Description of item Rate Unit
No.
Supplying and fixing of Electronic Regulators 400 w socket
type common switch board with earth continuity including
17 100.000 316.11 Each
wire leads, earth connections along with all labour charges
etc., complete.
Total Rs.
ABS-Int.Elec.
Sl.
Quantity Description of item Rate Unit
No.
Add L.S Rs.
Total Rs.
ABS-Int.Elec.
FOR INTERNAL ELECTRIFICATION
ommercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
in the place of existing A & B staff quarters.
Amount
310,431.00
71,145.00
50,592.00
248,462.50
65,618.00
35,585.00
15,800.00
ABS-Int.Elec.
Amount
34,995.00
17,360.20
4,685.56
5,990.00
4,234.00
5,966.40
5,802.00
120,567.20
336,802.00
ABS-Int.Elec.
Amount
31,611.00
93,907.50
78,672.80
10,277.00
29,692.00
1,578,196.16
ABS-Int.Elec.
Amount
23,333.40
1,601,529.56
ABS-Int.Elec.
DETAILED ESTIMATE (Internal Electrical)
Name of work : Construction of Commercial Complex (Cellar+Ground+4Floors) at
. Maddilapalem, Visakhapatnam in the place of existing A & B
quarters.
Sl.
Description of Item Nos. L B D
No.
Cellar floor 1 x 20
Ground,1St,2nd,3rd,4th floor
light point 14 x 10 -- -- --
Fan point 2 x 5 x 10
Tube point 5 x 10 -- -- --
3/2 pin point 8 x 10 -- -- --
T.V 4 x 5 -- -- --
Bath room 2 x 4x 5
Carridor, Mid landing 2 x 5 -- -- --
Total Total :
Det-Int.Elec.
Supply and fixing of 25mm dia 2.2 mm thick P.V.C
pipe (ISI MARK) concealed in Roof slabs with all
4
required accessories including masonary work and
labour charges etc. complete.
1St,2nd,3rd,4th floor 2x 5x 8 -- -- --
Cellar, Carridor & Stair case 2 x 10 -- -- --
Total Total :
Det-Int.Elec.
Supply and fixing of Modular (4 module box ) Type
16A/ 6A one way combi socket modular socket with
shutter of and 16A/10A module flush fuse with neon
8
indicator duly on recessed in wall with suitable gang
metalic flush box including earth connection and all
labour chargs etc.,complete.
1St,2nd,3rd,4th,5th floor 2x 5 x 10 -- -- --
For AC 16 A MCB 2x 5 -- -- --
For Flats 1x 2 -- -- --
Det-Int.Elec.
Supply and Fixing of Modular type conceiled type
Television socket & jack with White mounting plate
13 housed in a module metallic flush box including
cost and conveyance of all meterials and labour
charges etc., complete.
Television socket jack 2x 2x 5 -- -- --
Supply and laying of 2 pair Television wire of RG - 6
coaxil cable in the existing PVC conduct pipe with
14
labour charges etc., complete for finshing item of
work.
Television Wire internal 2x 5x 2 10.00 -- --
Electronic Regulator 5 x 10 x 2 -- -- --
Det-Int.Elec.
Supply, insallation, testing and commissioning of floor
mounting type meter panel board with alluminium bus
bars fabricated with 16 Duage CRCA sheet in standard
sections suitable for TNP bus bars with bus bars of equal
size in all phases and neutral equipped wiht bus bar
chambers and cable chambers. The painting of the
complete system shall be powder coated duly processing
the pabel in 7 tank process. The panel shall be suitable
for accomdating the following switch gear including
supply of all components, hard wares etc., including all
necessary civil works, adequate reinforcement foundation
19 bolts, suitable GI earth strip, suitable MS base channel,
door loop earthings, bus bars should be colour sleeved
wiht heat shrinkable sleeves for phase and neutral duly
supported at reqular intervels by SMC supports and bus
bar to switch inter connections shall have bimettalic
washers and all cables shall have proper cable entry,
danger board, feeder identification marks, rigid inter
connections, cadmium plated blots and nuts and shall be
installed and performed trench and consisting of the
following as required and as per IS standards for main
power control center.
1x 1 1 -- --
1x 1 860 -- --
Supply run of 1 of 36 / 0.30 mm (2.5 Sq.mm)
FRLS/HFFR PVC. Insulated1100v gradeflexible
21 copper cable in existing pipe for mains including all
labour charges etc. complete. For run of mains for
earthing.
1x 1 1040 -- --
Det-Int.Elec.
ESTIMATE (Internal Electrical)
rcial Complex (Cellar+Ground+4Floors) at
palem, Visakhapatnam in the place of existing A & B staff
Quantity
20.000
140.000
100.000
50.000
80.000
20.000
40.000
10.000
460.000 Rmt
600.000
300.000
900.000 Rmt
500.000
120.000
620.000 Rmt
Det-Int.Elec.
2650.000
600.000
3250.000 Rmt
660.000
200.000
860.000 Rmt
80.000
20.000
100.000 Nos
20.000
140.000
160.000 Nos
Det-Int.Elec.
100.000 Nos
10.000 Nos
2.000 Nos
20.000 Nos
200.000 Rmt
Det-Int.Elec.
20.000 Nos
200.000 Rmt
1040.000 Rmt
40.000 Nos
100.000 Nos
150.000 Rmt
Det-Int.Elec.
1.000 Nos
860.000 Rmt
1040.000 Rmt
Det-Int.Elec.
ABSTRACT FOR CIRCULAR SUMP
ABS-Cir.Sump
Sl. Qty. Description of item Rate Unit
No.
ABS-Cir.Sump
Sl. Qty. Description of item Rate Unit
No.
Supplying and fixing 50.8 Cm dia C.I. Man hole frame &
11 1.000 cover for chamber (Medium weight ) as per IS:1726-40Kgs. 3048.30 Each
For Circular Sump.
Total:
Add L.S for unforceen items
Cost of sump
ABS-Cir.Sump
STRACT FOR CIRCULAR SUMP
Amount
2,547.87
5,480.86
9,905.66
1,059.81
19,045.28
ABS-Cir.Sump
Amount
53,057.42
10,200.91
ABS-Cir.Sump
Amount
48,043.27
12,192.66
3,397.35
3,048.30
167,979.39
7,020.61
175,000.00
ABS-Cir.Sump
DETAILED ESTIMATE FOR SUMP
Name of work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddi
Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Description of item Nos. L B D
No.
Det-Cir.Sump
Sl.
Description of item Nos. L B D
No.
Det-Cir.Sump
Sl.
Description of item Nos. L B D
No.
Det-Cir.Sump
Sl.
Description of item Nos. L B D
No.
1x 1 -- --
Det-Cir.Sump
AILED ESTIMATE FOR SUMP
mmercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
the place of existing A & B staff quarters.
Qty
19.251 Cum.
2.984 Cum.
2.214 Cum.
3.802 Cum.
Det-Cir.Sump
Qty
1.925 Cum.
3.394 Cum.
Det-Cir.Sump
Qty
0.991 Cum.
0.231
0.407
0.119
0.757 MT
Det-Cir.Sump
Qty
15.715
4.911
6.608
27.234 Sqm
19.570 Sqm
1.000 Nos
Det-Cir.Sump
DATAS FOR CIRCULAR SUMP
1 Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead
of 10m including all operational, incidental, labour charges such as shoring incidental, sheeting,
planking, strutting, etc. complete for finished item of work .in ordinary soils by manual means
upto 3.00mt depth excluding dewatering charges etc. as per SS- 20 B (APSS 308)
Unit 1 Cum
Data-Cir.Sump
2 Filling sand cushion in the foundations below bed concrete as per standered specifications
including cost of sand and labour charges etc., complete.
Sand filling
A.P.Standard Data No.16 (Page No.18)
Unit = cum
A.Labour
Man Mazdoor Day 0.31 320.00 99.20
Add: M.L 40% on 99.20 39.68
B.Material
Sand Cum 1 1467.43 1467.43
Water 0.10 x 103 per 1KL Lit 0.1 103 10.30
Total Rs. 1616.61
C. Add 13.615 % contractor's Profit & Over Head charges 220.10
Sundries 0.04
Total Rs. 1836.75
Data-Cir.Sump
3 Laying PCC work of mix (1 : 4 : 8) proop. Using 40 mm gauge hard granite machine crushed
metal including cost and conveyance of all materials, machine mixing, labour charges, tamping,
curing, taxes etc., complete for foundations.
Unit 1 Cum
Data-Cir.Sump
4 Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not exceeding 15 cm thick,consolidating each deposited
layer by watering and ramming including cost and conveyance of water to work site and all
operational, incidental, labour charges, hire charges of T & P etc., complete for finisheditem of
work. (APSS NO. 309 & 310).
Unit 1 Cum
Data-Cir.Sump
5 Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 using
WEIGH BATCHER using minimum cement content of 380 Kg. per Cum with 12mm and 20mm
size graded machine crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate ( sand) coarse
aggregate, water etc., to site and including, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching, machine mixing, laying
concrete, Vibrating, curing etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work (APSS No.402 including centering shuttering using adjastable Jack
Screws, Props and Acro span beams including all pipe bracings, clamps couplings pre
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
etc. complete but excluding cost of steel and its fabrication charges for finished item of work for
Bottom Slab.
Unit 1 Cum
Data-Cir.Sump
6 Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 using
WEIGH BATCHER using minimum cement content of 380 Kg. per Cum with 12mm and 20mm
size graded machine crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching, machine mixing, laying
concrete, vibrating, curing etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work (APSS No.402) including centering shuttering using adjastable Jack
Screws, Props and Acro span beams including all pipe bracings, clamps couplings pre
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
etc. complete but excluding cost of steel and its fabrication charges for finished item of work
FOR CIRCULAR SUMP SIDE WALLS 200 mm. thick.
1 Cum M30 grade concrete vide Civil Data No.4 Cum 1.00 8184.35 8184.35
1.00 Cum centering charges as per Sl. No.31.5, Page
No.267. @ Rs.1115/0.2 Cum 1.00 5575 5575.00
Total Rs. 13759.35
Add 13.615 % contractor's Profit & Over Head charges 1873.34
Sundries 0.02
Total Rs. 15632.71
Data-Cir.Sump
7 Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380 Kg. per Cum with 12mm and 20mm size
graded machine crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching, machine mixing, laying
concrete, vibrate, curing etc.,complete but excluding cost of steel and its fabrication charges for
finished item of work (APSS No.402)including centering shuttering using adjastable Jack
Screws, Props and Acro span beams including all pipe bracings, clamps couplings pre
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
etc. complete but excluding cost of steel and its fabrication charges for finished item of work
FOR CIRCULAR SUMP COVER SLAB.
Unit 1 Cum
Data-Cir.Sump
8 Providing High Yield Strength Deformed Steel bars (Fe 415 Grade as per IS : 1786 and as
amended upto date) of different diameters including labour charges for cutting bending to
required size shapes, placing in position with cover blocks of approved materials and size and
tying firmly with M.S. Binding wire of 20 SWG forming grills for reinforcement work as per
approved designs and drawings including cost and conveyance of deformed steel bars,
including all wastage such as overlaps, welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all incidental, opeartional labour charges
including sales and other taxes on all materials etc., complete for finished item of work in all
floors (APSS No.126) (Payment will be made on the basis of weight of fabrication deformed
bars only) (No re-rolled steel shall be allowed) complete for (8 mm to 40 mm).
Unit 1 MT
Data-Cir.Sump
9 Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg
of water proof compound per bag of cement laid over roof when it is green including cost of all
materials,, including conveyance charges of materials and including all operational, incidental
and labour charges for mixing mortar, laying, rendering smooth and thread lining, curing,
rounding off junctions of wall and slab etc,, complete for finished item of work.
Unit 1 Sqm.
Data-Cir.Sump
10 Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened sand with sponge finishing
including cost and coneyance of all meterials hacking surface, scaffolding, leads, lifts and
labour charges etc., complete for CEILING.
Unit 1 Sqm.
Data-Cir.Sump
11 Supplying and fixing 50.8 Cm dia C.I. Man hole frame & cover for chamber (Medium weight ) as
per IS:1726-40Kgs. For Circular Sump.
Unit : Each
1 No. cost of 50.8 Cm. dia C.I Man hole frame &cover No. 1 2683 2683.00
vide P.No.87 of Item No.687
Add 13.615 % contractor's Profit & Over Head charges 365.29
Sundries 0.01
Total Rs. 3048.30
Data-Cir.Sump
ABSTRACT FOR COMPOUND WALL
Sl.
Quantity Description of item Rate Unit
No.
Earth work excavation for foundations and depositing on
bank for all lifts and with aninitial lead of 10m including all
operational, incidental, labour charges such as shoring
1 52.929 206.80 1 Cum.
sheeting, planking, strutting, etc. complete for finished item of
work excluding dewatering charges etc. as per SS- 20 B
(APSS 308).
ABS-Comp.wall
Sl.
Quantity Description of item Rate Unit
No.
ABS-Comp.wall
Sl.
Quantity Description of item Rate Unit
No.
Total:
Add Unforcein items
Say.
ABS-Comp.wall
RACT FOR COMPOUND WALL
Amount
10,945.72
31,722.70
7,070.97
ABS-Comp.wall
Amount
6,579.17
103,450.78
191,564.50
89,167.13
11,817.03
ABS-Comp.wall
Amount
3,446.02
43,800.00
10,696.87
510,260.89
4,122.95
514,383.84
ABS-Comp.wall
COMPOUND WALL (Detailed Estimate)
Det-Comp.wall
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
4
mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work.
COLUMNS.
Det-Comp.wall
Plastering with CM (1:4), 12 mm thick in singlecoat
with. Screened sand with sponge finishing including
cost and coneyance of all meterials hacking
7
surface, scaffolding, leads, lifts and labour charges
etc., complete for INTERIOR AND EXTERIOR
WALLS.
compound wall bothsides&top 1x 1 95.35 -- 3.27
Total: Total :
White washing two coats with approved quality of
white cement to give an even shade after
thoroughly brushing the surface to remove all dirt
and remains of loose powdered materials including
8
cost of all materials, labour charges and incidental
such as scaffolding, lift charges etc., complete for
finished item of work, but excluding conveyance
charges of materials
Qty. as per plastering qty. -- -- --
PAINTING to new WOOD work / Iron work in two
coats with synthetic enamel paint of approved
colour, over one coat of ( primary coat including
9 cost and conveyance of all materials, incidental
charges such as sand paper, cleaning the surface,
cost of brushes and putty etc., complete. (Three
coats).
For Gates 2x 2 3.05 -- 1.83
Total :
Det-Comp.wall
Providing High Yield Strength Deformed Steel bars
(Fe 415 Grade as per IS: 432 and as amended upto
date) of different diameters including labour charges
for cutting, bending to required size and shapes,
placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding
wire of 20 SWG forming grills for reinforcement
work as per approved designs and drawings
including cost and conveyance of deformed steel
bars, including all wastage such as overlaps,
11
welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all
incidental, opeartional, labour charges such as
cutting bending placing in position, tying etc.,
including sales and other taxes on all materials etc.,
complete for finished item of work in all floors
(APSS No.126) (Payment will be made on the basis
of weight of fabrication deformed bars only) (No re-
rolled steel shall be allowed) complete for (8 mm to
40 mm).
Ground floor
Footings (Qty as above) 0.762 0.150 MT/1Cum
Columns (Qty as above) 0.531 0.150 MT/1Cum
Total Total :
Det-Comp.wall
MPOUND WALL (Detailed Estimate)
Qty
52.929
52.929 Cum
8.725
8.725 Cum
0.762
0.762 Cum
Det-Comp.wall
0.531
0.531 Cum
19.308
16.305
35.613 Cum
33.334
33.334 Cum
Det-Comp.wall
311.795
311.795 Sqm
311.795 Sqm
22.326
22.326 Sqm
2.000
2.000 Nos
Det-Comp.wall
0.114
0.080
0.194 MT
Det-Comp.wall
ABSTRACT FOR SEPTIC TANK.
Sl.
QTY. Description of item RATE UNIT
No.
ABS-S.Tank
Sl.
QTY. Description of item RATE UNIT
No.
ABS-S.Tank
Sl.
QTY. Description of item RATE UNIT
No.
Total:
Add L.S
Say.
ABS-S.Tank
STRACT FOR SEPTIC TANK.
AMOUNT
15,424.38
17,368.72
193,698.63
ABS-S.Tank
AMOUNT
13,308.40
9,012.20
32,973.21
433.94
ABS-S.Tank
AMOUNT
83,700.24
490.82
4,402.45
5,541.20
376,354.20
11,865.45
388,219.65
ABS-S.Tank
DETAILED ESTIMATE FOR SEPTIC TANK
Name of work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Ma
Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Description of item Nos. L B D
No.
1 Earth work excavation for foundations and
depositing on bank for all lifts and with an initial lead
of 10m including all operational, incidental, labour
charges such as shoring incidental, sheeting,
planking, strutting, etc. complete for finished item of
work .in ordinary soils by manual means upto
3.00mt depth excluding dewatering charges etc. as
per SS- 20 B (APSS 308)
Det-S.Tank
Sl.
Description of item Nos. L B D
No.
4 Supply and placing of the Design Mix Concrete of M
30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, vibrate, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402)including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete, vibrating,
curing etc. complete but excluding cost of steel and
its fabrication charges for finished item of work
PRECASTE SLABS FOR COVER OF SEPTIC
TANK.
Cover slab 1x 1 11.46 1.83 0.10
Det-S.Tank
Sl.
Description of item Nos. L B D
No.
7 Filling with useful available excavated earth
(excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not
exceeding 15 cm thick,consolidating each deposited
layer by watering and ramming including cost and
conveyance of water to work site and all
operational, incidental, labour charges, hire charges
of T & P etc., complete for finisheditem of work.
(APSS NO. 309 & 310).
Balance 1x 1 28.68 0.31 1.98
8 Providing High Yield Strength Deformed Steel bars
(Fe 415 Grade as per IS: 432 and as amended upto
date) of different diameters including labour charges
for cutting, bending to required size and shapes,
placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding
wire of 20 SWG forming grills for reinforcement
work as per approved designs and drawings
including cost and conveyance of deformed steel
bars, including all wastage such as overlaps,
welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all
incidental, opeartional, labour charges such as
cutting bending placing in position, tying etc.,
including sales and other taxes on all materials etc.,
complete for finished item of work in all floors
(APSS No.126) (Payment will be made on the basis
of weight of fabrication deformed bars only) (No re-
rolled steel shall be allowed) complete for (8 mm to
40 mm).
--
9
Supplying and fixing of 100 mm dia P.V.C. Plain Tee
of Prince / Sudhakar make in position with air tight
jointing materials including cost and conveyance of
all materials, labour charges, fixing etc., complete
as directed by the department.
Det-S.Tank
Sl.
Description of item Nos. L B D
No.
1x 2 1.83 0.10 1.83
11
Plastering with CM in 2 coats of 12 mm thick, base
coat in CM (1:4) of 8mm thick and top coat in CM
(1:2) of 4mm thick with sponze finishing to suit
including cost and conveyance of all materials and
water to work site and all operational incidental
labour charges such as mixing mortar, lift charges,
curring etc., complete for finished item of work as
per SS No. 901, 904 for Baffel walls.
1x 2 1.83 0.10 --
2x 2 1.83 1.83 --
Total Total :
Det-S.Tank
LED ESTIMATE FOR SEPTIC TANK
ommercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
in the place of existing A & B staff quarters.
Qty
74.586 Cum.
5.228 Cum.
11.281
1.801
13.082 Cum
Det-S.Tank
Qty
2.097 Cum.
20.130 Sqm
23.540
3.916
61.600
26.243
115.299 Sqm
Det-S.Tank
Qty
17.604 Cum
1.518 MT
4.000 Nos
Det-S.Tank
Qty
0.670 Cum
0.366 Sqm
13.396 Sqm
13.762 Sqm
Det-S.Tank
ABSTRACT FOR DISMANTLING
Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at
Maddilapalem, Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Quantity Description of item Rate Unit
No.
ABS-Dism
ABSTRACT FOR DISMANTLING
tion of Commercial Complex (Cellar+Ground+4Floors) at
hapatnam in the place of existing A & B staff quarters.
Amount
116,099.72
484,593.08
27,622.19
628,314.99
-73,200.00
4,885.01
560,000.00
ABS-Dism
DATAS FOR DISMANTLING
1 Demolition inlcuding stacking of serviceable materials and disposal of unserviceable materials with
100 meters lead.
RCC work Standard data No.298
Unit - 1 Cum.
Labour
Mazdoor (Unskilled) Day 4.32 320.00
Add: M.L 40% on labour charges 1382.40 X 40%
Total Rs.
Add 13.615 % contractor's Profit & Over Head charges
Sundries
Total Rs.
Data-Dism
2 Demolition inlcuding stacking of serviceable materials and disposal of unserviceable materials with
100 meters lead.
Data-Dism
3 Dismantling door windows and clear storey windows ventilators etc., (wood or steel) shutters includ
chowkhats architraves holdfast and other attachments etc., complete and stacking them with in 100
meters lead.
Data-Dism
4 Extra over item 14.2 ii for cutting steel bars in RCC of RB work (Sectional area of RCC or RB work
be measured) details of cost for 1 Sqm. of sectional area.
Data-Dism
DATAS FOR DISMANTLING
1382.40
552.96
1935.36
263.50
0.04
2198.90
Data-Dism
of serviceable materials and disposal of unserviceable materials with in
1308.80
523.52
1832.32
249.47
0.01
2081.80
Data-Dism
d clear storey windows ventilators etc., (wood or steel) shutters including
st and other attachments etc., complete and stacking them with in 100
37.50
18.75
64.00
48.10
168.35
22.92
0.03
191.30
Data-Dism
ing steel bars in RCC of RB work (Sectional area of RCC or RB work to
or 1 Sqm. of sectional area.
187.50
160.00
139.00
486.50
66.24
0.01
552.75
Data-Dism
LEAD CHART
Deduct
Net
Sl. Source of Lead in Conveyance 13.615%
Description of material Unit Initial cost Conveyance
No. supply K.M. charges contractor
charges
profit
1 2 3 4 5 6 7 8 9
1 6 MM Hard granite metal Aganampudi 27 1 Cum 735.00 343.10 -41.12 301.98
2 10 mm hard granite metal Aganampudi 27 1 Cum 935.00 343.10 -41.12 301.98
3 12.5 mm hard granite metal Aganampudi 27 1 Cum 1097.50 343.10 -41.12 301.98
4 20 mm hard granite metal Aganampudi 27 1 Cum 1365.00 343.10 -41.12 301.98
5 40 mm hard granite metal Aganampudi 27 1 Cum 845.00 343.10 -41.12 301.98
6 Sand for concrete(unscreened) Srikakulam 104 1 Cum 610.00 1144.60 -137.17 1007.43
7 Sand for filling Srikakulam 104 1 Cum 460.00 1144.60 -137.17 1007.43
8 Sand for mortar Srikakulam 104 1 Cum 677.00 1144.60 -137.17 1007.43
9 Gravel/quarryspot Yandada 8 1 Cum 103.00 107.50 -12.89 94.61
10 Rough stone (RR Masonary OTG) Yandada 8 1 Cum 180.00 107.50 -12.89 94.61
11 Filling earth Yandada 8 1 Cum 107.50 -12.89 94.61
12 Steel (HYSD Bars) Local 1 MT. 42000.00 GO RT No.419 June-2015 rate
13 Cement Local 1 MT. 5873.00
Flyash Lime Solid Bricks
14 size: 29 x 22.5 x 14 Cm. Parawada 33 Each 24.00
50 Kgs./1 Sq.Cm.
Flyash Lime Solid Bricks
15 Size 29 x 10 x 14 Cm. Parawada 33 Each 11.00
50 Kgs./1 Sq.Cm.
Certificate:
LEAD CHART
Certified that the lead charges are calculated as per guidelines at serial No.15 and 16 of Preamble of SOR 2015-16.Hence 1.00 km lead de
LEAD CHART
LEAD CHART
GRAND
Reference
TOTAL
10 11
Item No.33a, P.No.245 1036.98
Item No.33b, P.No.245 1236.98
Item No.33c, P.No.246 1399.48
Item No.33d, P.No.246 1666.98
Item No.33f, P.No.246 1146.98
Item No.36a, P.No.249 1617.43
Item No.36b, P.No.249 1467.43
Item No36c, P.No.249 1684.43
Item No.34, P.No.249 197.61
Item No.22a, P.No.244 274.61
94.61
GO RT No.419 June-2015 rate 42000.00
5873.00
LEAD CHART
serial No.15 and 16 of Preamble of SOR 2015-16.Hence 1.00 km lead deducted from total lead.
LEAD CHART
M O R TAR C HAR T
(As per Common S.S.R. 2015-16)
Name of work : Construction of Commercial Complex (Cellar+Ground+4Floors) at
. Maddilapalem, Visakhapatnam in the place of existing A & B
staff Rate of .cement :Rs.5873/-quarters.
Per M.T.
MORTAR
Index Sl. Quantity Rate Amount
MORTARS Unit
Code No.
1 2 3 4 5 6.000 7
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 3972.53
BLD-CSTN Cement mortar (1:5)
1-6 6 Unit : 1 Cum
A) MATERIALS
Cement Kg. 288.00 5.873 1691.42
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 3549.68
BLD-CSTN Cement mortar (1:6)
1-7 7 Unit : 1 Cum
A) MATERIALS
Cement Kg. 240.00 5.873 1409.52
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 3267.77
BLD-CSTN Cement mortar (1:8)
1-8 8 Unit : 1 Cum
A) MATERIALS
Cement Kg. 180.00 5.873 1057.14
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 2915.39
MORTAR
ABSTRACT FOR INTERNAL WATER SUPPLY AND SANITARY
Name of Work :- Construction of G+7 Flats Under Affordable Housing.Scheme in partnership at
Balaga(V) ,Srikakulam (M) ,Srikakulam (Dist).
Sl.
Quantity Description of item Rate Unit
No.
Supplying & Fixing Indian make Flat Back Wash Hand Basin
(HSW/Parryware/Neycer) 1st quality with single C.P.Pillar
cock, conforming to IS:2556-Part-4-1972 with waste fittings
like 38.10mm waste coupling, rubber plug, chain, 32 mm
nominal size C.P fitting with parallel pipe thread conforming
to IS/:2963-1979 and fitted with 12.70mm dia. Chromium
Plated Pillar tap of 1st quality Indian make 400 grams
8 64.000 Seiko / Esso or equivalent etc., complete with standard CI 1761.05 EACH
brackets including wooden block, 31.75 mm PVC flexible
waste pipe of 914.4mm long, 15mm inlet PVC connection
with unions complete, including cutting and making good the
walls where ever required for the following sizes etc.,
complete for different floors, including cost, all taxes and
conveyance of all materials and all labour charges etc.,
complete for finished item of work.
TOTAL
Add L.S for unforceen items
Say. TOTAL:
D SANITARY
eme in partnership at
Amount
256,256.40
179,615.04
18,761.60
138,960.00
269,840.00
103,401.60
34,470.40
260,928.04
112,707.20
25,961.60
94,813.88
34,540.92
87,779.85
13,852.80
24,877.56
172.80
26,643.90
6,035.20
9,452.80
14,620.80
15,926.20
25,850.40
5,382.40
8,515.20
1,769,366.59
633.41
1,770,000.00
DATAS INTERNAL WS & SF
1.00 RMT Cost of pipe as per SSR Item No.819 P.No.91 Rs.
Add 13.615 % contractor's Profit & Over Head charges
sundries
total Rs.
B For 28.60 mm dia OD pipe SDR 13.5
1.00 RMT Cost of pipe as per SSR Item No.816 , P.No.9 Rs.
Sundries
Total Rs.
Data-int.WS
C For 15.90 mm dia OD pipe SDR 13.5
1.00 RMT Cost of pipe as per SSR Item No.814 P.No.91 Rs.
Sundries
Total Rs.
Data-int.WS
d For 34.90 mm dia OD pipe SDR 13.5
1.00 RMT Cost of pipe as per SSR Item No.817 P.No.91 Rs.
Add 13.615 % contractor's Profit & Over Head charges
sundries
total Rs.
Supplying and Fixing of 12.70mm NP short bib tap indian make heavy duty, S
or equivalent fancy type deluxe with necessary fittings etc., complete inclu
2
cost and conveyance of all materials, all taxes and all labour charges for fin
item.
Unit: Each
Supplying and Fixing of 12.70mm NP long body Bib tap indian, fancy type d
3 with necessary fittings etc., complete including cost and conveyance o
materials, all taxes and all labour charges for finished item.
Unit: Each
1 No. cost of 12.7 mm NP. Long body Bib Tap
vide Item no.194, P.No.150 Rs.
Add 13.615 % contractor's Profit & Over Head charges
Sundries
Total Rs.
Supplying and fixing of50 mm dia G.M.Peet Valve as per I.S.778 1st Cla
4 approved make Zoloto including cost and conceyance of all materials, la
charges etc., complete.
Data-int.WS
Unit: Each
Data-int.WS
Supplying and Fixing of 12.70mm NP Angle stop cock indian make 400
Seiko or equivalent fancy type deluxe with necessary fittings etc., com
5
including cost and conveyance of all materials, all taxes and all labour charge
finished item of work in all floors.
Unit: Each
Sundries
Total Rs.
Data-int.WS
Supply and fixing of 38.1 mm C.P. waste coupling Half or Full Thead 1st Q
6
Indian make Parryware of equivalent.
Unit: Each
Supplying & Fixing Orissa Pan white glazed W.C 1st quality ISI ma
conforming to IS:2556-Part-3-1981 with "P" or "S" trap Hindware/ Parryw
Neycer - ISI Mark: 580 mm x 440 mm
7
1 No. cost of Orissa Pan White glazed W
C vide P.No.122 Item No.136 Rs.
Add M.L. 20%% on labour charges vide
item low
1 No. P.V.C. No.138
level at Rs 377.00
system flush tank 10 Rs.
Lt lt.capacity vide item No.342, P.No 132 Rs.
Supplying & Fixing Indian make Flat Back Wash Hand Basin of size 450x30
1st quality with single C.P.Pillar cock, conforming to IS:2556-Part-4-1972
waste fittings like 38.10mm waste coupling, rubber plug, chain, 32 mm no
size C.P fitting with parallel pipe thread conforming to IS/:2963-1979 and
with 12.70mm dia. Chromium Plated Pillar tap of 1st quality Indian make
8 grams Seiko / Esso or equivalent etc., complete with standard CI bra
including wooden block, 31.75 mm PVC flexible waste pipe of 914.4mm
15mm inlet PVC connection with unions complete, including cutting and m
good the walls where ever required for the following sizes etc., complet
different floors, including cost, all taxes and conveyance of all materials an
labour charges etc., complete for finished item of work.
Data-int.WS
DATAS INTERNAL WS & SF
VALASA,(v) SRIKAKULAM .
525.00
71.48
0.02
596.50
pipe SDR 13.5
212.00
28.86
0.04
240.90
Data-int.WS
pipe SDR 13.5
141.00
19.19
0.01
160.20
Data-int.WS
289.00
39.35
0.04
328.39
258.00
35.13
0.02
293.15
637.00
86.73
0.02
723.75
Data-int.WS
3,711.00
505.25
-
4,216.25
Data-int.WS
of 12.70mm NP Angle stop cock indian make 400gms,
ncy type deluxe with necessary fittings etc., complete
eyance of all materials, all taxes and all labour charges for
all floors.
474.00
64.54
0.01
538.55
Data-int.WS
.1 mm C.P. waste coupling Half or Full Thead 1st Quality
of equivalent.
237.00
32.27
0.03
269.30
1584.00
75.40
1455.00
474.00
3588.40
488.56
0.04
4077.00
Sl.
Quantity
No.
1 960.000
2 960.000
3 1782.760
4 1153.440
5 192.000
6 448.000
7 320.000
8 64.000
9 4.000
10 1500.640
11 112.000
12 120.000
13 2.000
14 4.000
15 64.000
16 1817.600
ABSTRACT FOR INTERNAL ELECTRIFICATION
of Work :- Construction of G+7 Flats Under Affordable Housing.Scheme in part
Balaga(V) ,Srikakulam (M) ,Srikakulam (Dist).
Total
Add L.S
Total
ON
.Scheme in partnership at
).
Unit Amount
Each 647,856.00
1RMT 75,888.00
1 RMT 145,473.22
1 RMT 88,180.49
Each 67,190.40
Each 44,240.00
Each 211,166.69
Each 111,104.00
Each 9,371.12
1 RMT 173,969.20
Each 34,558.72
1 RMT 74,232.00
Each 158,936.19
-
46,192.41
NO 466,169.60
1 RMT 21,720.32
Rs. 2,376,248.36
Rs. 23,751.64
Rs. 2,400,000.00
DATAS FOR ELECTRICAL
Data-Int.Elec.
sundries
Total
Supply and fixing of ISI 20mm outer medium dia (1.55 mm thick) grade w
4make Sudhakar / Modi / Atul P.V.C pipe concealed in wall with all requir
2
masonary work for light, fan and separate plug point with well seasoned
all labour charges etc. complete.
Data-Int.Elec.
Supply and fixing of 25mm dia 1.8 mm thick Surface P.V.C pipe (ISI MAR
3 fixing on chromium plated metallic base saddles including all labour char
mains.
A.P.Standard Data No.1.3.2, P.No.157
Taking Out put -100 M
Unit Qty
Material :-
25 mm dia 1.8mm thick PVC pipe 100 M 100.00
(P.No.103, item No.54)
Rawl Plugs 100 Nos. 2.00
(P.No.167,It.No.1340)
35 mm Screws(35/38mm) 100 Nos. 2.00
(P.No.104, It. No.134)
Chromium Plated saddles with base Each 200.00
(P.No.102, It.No.35) Rs.220.00/100No.=Rs.2.20
25 mm 1,2,3 & 4 way Junction boxes Each 12.00
(P.No.104, It.No.90)
25 mm PVC Bends Each 12.00
(P.No.104, It.No.95)
Cement MT 0.025
Labour charges :-
Skilled Electrician Day 2.00
Semi skilled Elecrician Day 2.00
Helpers Day 2.00
20% Labour compo 2630.00 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Total
Rate per 1 Rmt
sundries
Total
Supply and fixing of 25mm dia 2.2 mm thick P.V.C pipe (ISI MARK) con
4
required accessories including masonary work and labour charges etc. c
Data-Int.Elec.
Taking Out put -100 M
Unit Qty
Material :-
25 mm dia 2.2 mm thick PVC pipe 100 M 100.00
(P.No.103, item No.55)
25 mm dia 1,2,3, & 4 way deep junction
Each 12.00
box (P.No.104,It.No.90).
25 mm PVC Bends Each 12.00
(P.No.104, It.No.95)
Labour charges :-
Skilled Electrician Day 2.00
Semi skilled Elecrician Day 2.00
Helpers Day 2.00
20% Labour compo 2630.00 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Total
Rate per 1 Rmt
sundries
Total
Supply and fixing of 6A, 3/2 pin plate socket with 6 A Modular type switc
metalic flush box with 2 mts of 1 sqqmm PVC insulated copper conducto
5
on a common board with a run of 1.0 sqmm PVC insulated copper condu
wire for earth continuity along with labor charges etc.., complete
Unit - Each
A.P.Standard Data No.2.1.4 , P.No.165
Taking Out put -Each.
Unit Qty
Material :-
3/2 pin 6A Modular Socket Each 1.00
(P.No.182, item No.261)
6A 1 way Modular switch Each 1.00
Labour charges :-
Skilled Electrician Day 0.07
Helpers Day 0.07
Data-Int.Elec.
20% Labour compo 62.51 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
sundries
Total
Unit -Each
A.P.Standard Data No.2.1.7 , P.No.165
Taking Out put -Each.
Unit Qty
Material :-
PVC Batten holder (Anchor/ Gold medal) Each 1.00
(P.No.108, item No.215)
40 W Bulb Each 1.00
(P.No.132, item No.729)
Labour charges :-
Skilled Electrician Day 0.05
Helpers Day 0.05
20% Labour compo 45.75 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
sundries
Total
7 Supply and fixing of Modular (4 module box ) Type 16A/ 6A one way com
with shutter of and 16A/10A module flush fuse with neon indicator duly on
suitable gang metalic flush box including earth connection and all labou
Unit - Each
A.P.Standard Data No.2.1.6 , P.No.165
Taking Out put -Each
Data-Int.Elec.
Unit Qty
Material :-
4 way Modular type metal box concealed Each 1.00
(P.No.176, item No.102)
16 A & 6 A muilt socket - 3pin Modular type Each 1.00
(P.No.183, item No.270)
16 A Modulae type 3 pin/6A 3 pin plug socket (5 in 1) Each 1.00
(P.No.183, item No.265)
Labour charges :-
Skilled Electrician Day 0.10
Semi skilled Elecrician Day 0.10
Helpers ( Rs 400.00) Day 0.10
20% Labour component
131.5 x 20 %
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total
Rate per Each Point Rs.659.90
Supply and fixing Distribution board with 20 A single phase plug and
8 with 10/16/32A SP MCB including internal conneciton and labour charges
etc., complete. (Concailed in wall) for A.C. Point.
Data-Int.Elec.
Skilled Electrician Day 0.25
Semi skilled Elecrician Day 0.25
Helpers Day 0.25
20% Labour compo 328.75 X 20%
Sundries such as T.W.Plugs, Screws etc.,
Total
Add.13.615% towards Contractor Profit & O.H.Charges
sundries
Total
20% extra for narrow trench & pit back filling with
x 20%
sand, coke and salt etc.,. On Rs. 192.50
40mm dia G.I pipe (Medium) (P.No.80, Item 298 Rs.
Mtr. 2.50
355.00 - 67.00 (Labour charges ) = 288.00
Data-Int.Elec.
Hard Coke. (P.No.167, Item No.1347). Kg. 40.00
Salt. (P.No.167, Item No.1348). Kg. 20.00
Semi Skilled Electrician Day 0.50
Helpers 0.50
Add 20% Labour component
Total
Add.13.615% towards Contractor Profit & O.H.Charges
sundries
Total
Data-Int.Elec.
Supplying and fixing of Electronic Regulators 400 w socket type comm
11
continuity including wire leads, earth connections along with all labour ch
Labour charges :-
Skilled Electrician Day 0.067
Helpers Day 0.067
40% Labour compo 61.31 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Sundries
Total
Supplying and erecting the following PVC armoured cable 1100 V grade
alluminium in soil upto 0.9 M deep embedding the cable complete with sa
layer and bricks placed on top of the calbe with wise and sides all over th
12 excavated earth with outstones and hard materials and making the surfa
crown on the top duly providing route indicators including connections lik
complete.(makes polycab / KE1 / RPG/ finolex / havells / paragon/ Vguar
suncab).
Material
Cost of 95 Sq.mm 3.5 core XLPE insulated Unit Qty
1100 grade armoured arroured alluminium Rmt 1.000
cable
Labou(Page No.142, Item No :893)
r
Skilled Electrician Day 0.066
Helpers Day 0.066
20% Labour compo 60.39 X 20%
Total
Data-Int.Elec.
Add.13.615% towards Contractor Profit & O.H.Charges
Sundries
Total
13
Data-Int.Elec.
fuse box doors----------- ---- 8"x13"20= 2080
fuse box doors----------------------8"x19"x1= 152
Bus bar doors----------------------11"x16"x2= 352
SFU box door---------- -----------13"x19"x1= 247
Total--------18383.00sq inch or 11.859 sqmt each 11.86
b 200 amps TPN Switch disconnector fuse unit cubical
type without fuses of makes (Page No.=112, Item
No.=305).
each 1.00
c 200 amps HRC fuse links 3nos (Page
no.=115, Itemno.=349).
each 3.00
d supply and erection of analog LED
indicator lamps on the existing box /
pannel board (Page no=162, Item
no=1225)
each 3.00
e supply of 32A 240V porcelain rewirwble
fuse units (Page No.=114, Item
No.=353).
each 63.00
f supply of 32amps nutral links L.S P140
IT.325 (Page No.=114, Item No.=347).
each 21.00
g supply of 84/0.3mm (6.0 sqmm)
FR/FRLS PVC insulate copper cable
(Page No.=105, Item no.=141).
MTS 84.00
h 40x6mm aluminium bus bar
(1mtr=0.644kgs) 16x0.644 (Page
No=168, Item No=1376).
kg. 10.30
i Epoxy insulators l.S each 32.00
j 3mm thickhylam sheet size of
12"x15"( Page No.168, Item No
1385).0116*945=109.62
Sqmt 21.00
Total
Data-Int.Elec.
Add.13.615% towards Contractor Profit & O.H.Charges
Sundries
Total
Data-Int.Elec.
Total
Supplyong and fixing 4 way SPN, D.B. with IP-20 Protection suitable. F
15
insulator as in commer for 1 Phase ELCB/RCCB/FP isolator as incomme
Data-Int.Elec.
AS FOR ELECTRICAL
Unit - Each
Rate Amount
1051.00 1051.00
92.00 644.00
21.00 147.00
60.00 420.00
65.00 455.00
515.00 360.50
400.00 560.00
400.00 280.00
240.10
Rs. 4157.60
Rs. 566.06
Rs. 0.04
Rs 4723.70
Rs. 674.81
Data-Int.Elec.
Rs. 0.04
Rs. 674.85
Rate Amount
20.00 2000.00
44.00 88.00
22.00 264.00
4.00 48.00
6600.00 330.00
515.00 1030.00
400.00 800.00
400.00 800.00
445.00 890.00
704.00
Rs. 6954.00
Rs. 946.79
Rs 7900.79
Rs. 79.01
Rs. 0.04
Rs. 79.05
Data-Int.Elec.
hick Surface P.V.C pipe (ISI MARK ) with all accessories
saddles including all labour charges etc. complete for run of
Unit - 1 Rmt
Rate Amount
28.00 2800.00
28.00 56.00
96.00 192.00
2.20 440.00
25.00 300.00
6.00 72.00
6600.00 165.00
515.00 1030.00
400.00 800.00
400.00 800.00
526.00
Rs. 7181.00
Rs. 977.69
Rs 8158.69
Rs. 81.59
Rs. 0.01
Rs. 81.60
hick P.V.C pipe (ISI MARK) concealed in Roof slabs with all
y work and labour charges etc. complete.
Unit - 1 Rmt
Data-Int.Elec.
Rate Amount
32.00 3200.00
25.00 300.00
6.00 72.00
515.00 1030.00
400.00 800.00
400.00 800.00
526.00
Rs. 6728.00
Rs. 916.02
Rs 7644.02
Rs. 76.44
Rs. 0.01
Rs. 76.45
Rate Amount
141.00 141.00
92.00 92.00
515.00 34.51
400.00 28.00
Data-Int.Elec.
12.50
Rs. 308.01
Rs. 41.94
Rs. 0.00
Rs. 349.95
Rate Amount
20.00 20.00
12.00 12.00
515.00 25.75
400.00 20.00
9.15
Rs. 86.90
Rs. 11.83
Rs. 0.02
Rs. 98.75
Data-Int.Elec.
Rate Amount
101.00 101.00
196.00 196.00
126.00 126.00
515.00 51.50
400.00 40.00
400.00 40.00
26.30
580.80
Rs. 79.08
Rs. 0.02
Rs. 659.90
Unit Each
Rate Amount
901.00 901.00
121.00 121.00
6600.00 82.50
Data-Int.Elec.
515.00 128.75
400.00 100.00
400.00 100.00
65.75
28.96
Rs. 1527.96
Rs. 208.03
Rs. 0.01
Rs. 1736.00
Unit-Each
110.00 93.50
110.00 99.00
38.50
288.00 720.00
68.00 51.00
6.00 96.00
11.00 44.00
Data-Int.Elec.
9.00 360.00
4.00 80.00
400.00 200.00
400.00 200.00
80.00
Rs. 2062.00
Rs. 280.74
Rs. 0.04
Rs. 2342.78
Rate Amount
3833.00 7666.00
515.00 515.00
400.00 1200.00
400.00 400.00
423.00
Rs 10204.00
Rs. 1389.27
Rs. 0.03
Rs 11593.30
Rs. 115.93
Rs. 115.93
Data-Int.Elec.
ulators 400 w socket type common switch board with earth
nnections along with all labour charges etc., complete.
Rate Amount
198.00 198.00
515.00 34.51
400.00 26.80
12.26
Rs. 271.57
Rs. 36.97
0.02
Rs. 308.56
Rate Amount
472.00 472.00
515.00 33.99
400.00 26.40
12.08
Rs. 544.47
Data-Int.Elec.
Rs. 74.13
0.00
Rs. 618.60
Data-Int.Elec.
3565.00 42277.34
8215.00 8215.00
270.00 810.00
135.00 405.00
100.00 6300.00
50.00 1050.00
5828.00 4895.52
234.00 2410.20
40.00 1280.00
109.62 2302.02
69945.08
Data-Int.Elec.
9523.02
0.00
Rs 79468.10
Rate Amount
9821.00 9821.00
515 86.01
400 66.80
400 133.20
57.20
10164.21
1383.86
0.04
11548.10
Rate Amount
1051.00 1051.00
Rs. 143.09
Rs. 1194.09
Rs 11.94
0.01
Data-Int.Elec.
Rs. 11.95
2970.00 2970.00
201.00 2412.00
515.00 257.50
400.00 200.00
400.00 400.00
171.50
Rs 6411.00
Rs. 872.86
Rs. 0.04
Rs 7283.90
Data-Int.Elec.
DATAS FOR COMPOUND WALL
1 Earth work excavation for foundations and depositing on bank for all lifts and with aninitial lead
of 10m including all operational, incidental, labour charges such as shoring incidental, labour
charges such as shoring sheeting, planking, strutting, etc. complete for finished item of work
excluding dewatering charges etc. as per SS- 20 B (APSS 308).
Unit 1 Cum
Data-Comp.Wall
2 Laying PCC work of mix (1 : 5 : 10) prop. Using 40 mm gauge hard granite machine crushed
metal including cost and conveyance of all materials, machine mixing, labour charges, tamping,
cruing charges, taxes etc., complete for foundations.
Unit 1 Cum
Data-Comp.Wall
3 Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 using
WEIGH BATCHER using minimum cement content of 380 Kg. per Cum with 12mm and 20mm
size graded machine crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate ( sand) coarse
aggregate, water etc., to site and including, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching, machine mixing, laying
concrete, Vibrating, curing etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work (APSS No.402 including centering shuttering using adjastable Jack
Screws, Props and Acro span beams including all pipe bracings, clamps couplings pre
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
etc. complete but excluding cost of steel and its fabrication charges for finished item of work.
PLINTH BEAM
Unit 1 Cum
Data-Comp.Wall
4 R.R.Masonary in C.M.(1:8) Prop. using hard stone other than granite including cost and
conveyance of all materials, labour charges, curing etc., complete for FOUNDATION AND
BASEMENT.
MATERIALS :
Cement MT 0.0594 6600.00 392.04
Rough Stone as per chart Cum 0.94 520.10 488.89
Bond stone Cum 0.16 520.10 83.22
Sand Cum 0.33 338.74 111.79
LABOUR
Mason 1st class Day 1.2 445.00 534.00
Man Mazdoor 2 350.00 700.00
Add M.L 20% on labour 1234.00 X 20% 246.80
Total Rs. 2556.73
Add 13.615% contractor's Profit & Over Head charges Rs. 348.10
Sundries. Rs. 0.03
Total Rs. 2904.86
Data-Comp.Wall
5 Masonry work in CM (1:6) prop with Flyash Cement solid blocks of size 290 x 225 x 140 mm for
manufacturing of flyash solid blocks using flyash of 80 kgs, cement of 15 kgs.Gypsum of 5 kgs.
and stone dust including cost and conveyance of all materials, labour charges, , scaffolding and
curing etc., complete with a compressive strength not lessthan 50 kg/sqcm for walls for
Superstructure
Unit 1 Cum
Data-Comp.Wall
6 Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened sand with sponge finishing
including cost and coneyance of all meterials hacking surface, scaffolding, leads, lifts and
labour charges etc., complete for INTERIOR AND EXTERIOR WALLS.
Unit 1 Sq.mtr.
Data-Comp.Wall
7 White washing two coats with approved quality of white cement to give an even shade after
thoroughly brushing the surface to remove all dirt and remains of loose powdered materials
including cost of all materials, labour charges and incidental such as scaffolding, lift charges
etc., complete for finished item of work, but excluding conveyance charges of materials
Unit : 1 Sqm.
MATERIALS :
Whiting / White Cement (Page No.64, Sl.No.115 Kg 2.00 29.00 58.00
Gum, conjee water, or prickly pear juice
including necessary fire wood L.S LS 9.05
LABOUR
Brick Layers / Painter Day 0.21 510.00 107.10
Mazdoor (unskilled) 0.32 350.00 112.00
Add M.L 20% on labour charges 219.10 X 20% 43.82
Total Rs. 329.97
Sundries including brushes, ladders, etc., at 1% Rs. 3.30
Total Rs. 333.27
Add 13.615 % contractor's Profit & Over Head charges Rs. 45.37
Total Rs. 378.64
Rate for 1 Sqm Rs. 37.86
sundries Rs. 0.04
Total Rs. 37.90
Data-Comp.Wall
8 PAINTING to new WOOD work / Iron work in two coats with synthetic enamel paint of
approved colour, over one coat of ( primary coat including cost and conveyance of all materials,
incidental charges such as sand paper, cleaning the surface, cost of brushes and putty etc.,
complete. (Three coats).
Unit 1sqm
Data-Comp.Wall
9 Providing High Yield Strength Deformed Steel bars (Fe 415 Grade as per IS: 432 and as
amended upto date) of different diameters including labour charges for cutting, bending to
required size and shapes, placing in position with cover blocks of approved materials and size
and tying firmly with M.S. Binding wire of 20 SWG forming grills for reinforcement work as per
approved designs and drawings including cost and conveyance of deformed steel bars,
including all wastage such as overlaps, welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all incidental, opeartional, labour charges such as
cutting bending placing in position, tying etc., including sales and other taxes on all materials
etc., complete for finished item of work in all floors (APSS No.126) (Payment will be made on
the basis of weight of fabrication deformed bars only) (No re-rolled steel shall be allowed)
complete for (8 mm to 40 mm).
Unit 1 M.T
Data-Comp.Wall
ABSTRACT FOR SEPTIC TANK.
Sl.
QTY. Description of item RATE
No.
Total:
Add L.S
Say.
) Flats.
UNIT AMOUNT
1 Cum. 22,153.24
1 Cum. 43,053.04
Cum. 101,542.40
1 Cum. 84,328.65
1 Cum. 55,904.17
Cum. 10,685.93
`1Sqm 62,882.05
1 M.T. 123,629.24
Cum. 408.80
No 122.70
Cum. 2,027.84
506,738.05
3,261.95
510,000.00
DETAILED ESTIMATE FOR SEPTIC TANK
Name of work :- Construction of EWS (G+7) FLATS
Sl.
Description of item Nos. L B D
No.
1 Earth work excavation for foundations and
depositing on bank for all lifts and with an initial lead
of 10m including all operational, incidental, labour
charges such as shoring incidental, sheeting,
planking, strutting, etc. complete for finished item of
work .in ordinary soils by manual means upto
3.00mt depth excluding dewatering charges etc. as
per SS- 20 B (APSS 308)
Qty
107.124 Cum.
12.959 Cum.
16.000 cum
7.638
1.984
9.622 Cum
8.809 Cum.
1.178 Cum
1.178 Cum
60.000
37.200
9.920
7.200
67.760
38.192
10.912
231.18 Sqm
2.293 MT
76.887
-60.306
16.58 Sqm
1.000 Nos
0.320 Cum
DATAS FOR SEPTIC TANK
Earth work excavation for foundations and depositing on bank for all lifts and with an initial
lead of 10m including all operational, incidental, labour charges such as shoring incidental,
1 sheeting, planking, strutting, etc. complete for finished item of work .in ordinary soils by
manual means upto 3.00mt depth excluding dewatering charges etc. as per SS- 20 B (APSS
308)
Unit 1 Cum
Data-S.Tank
Laying PCC work of mix (1 : 5 : 10) prop. Using 40 mm gauge hard granite machine crushed
2 metal including cost and conveyance of all materials, machine mixing, labour charges,
tamping, cruing charges, taxes etc., complete for foundations.
Unit 1 Cum
Data-S.Tank
Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 using
WEIGH BATCHER using minimum cement content of 400 Kg. per Cum with 12mm and
20mm size graded machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including , sales & other taxes on all materials
including all operational, incidental and labour charges such as weigh batching, machine
mixing, laying concrete, Vibrating, curing etc.,complete but excluding cost of steel and its
3 fabrication charges for finished item of work (APSS No.402) including centering shuttering
using adjastable Jack Screws, Props and Acro span beams including all pipe bracings,
clamps couplings pre fabricated steel H-frames, cross members etc., Complete, laying
concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication charges
for finished item of work. BOTOM SLAB (Below Plinth).
Unit 1 Cum
6346.40
4 Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of all materials like cement,
fine aggregate sand) coarse aggregate, water etc., to site and including , sales & other taxes
on all materials including all operational, incidental and labour charges such as weigh
batching, machine mixing, laying concrete, vibrate, curing etc.,complete but excluding cost of
steel and its fabrication charges for finished item of work (APSS No.402)with minimum cement
content as per IS code from standard suppliers approved by the department including
centering shuttering using adjastable Jack Screws, Props and Acro span beams including all
pipe brancings, clamps couplings pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc. complete but excluding cost of steel and its
fabrication charges for finished item of work FOR SIde walls.
Data-S.Tank
Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site and including, sales & other taxes
on all materials including all operational, incidental and labour charges such as weigh
5 batching, machine mixing, laying concrete, vibrate, curing etc.,complete but excluding cost of
steel and its fabrication charges for finished item of work (APSS No.402)including centering
shuttering using adjastable Jack Screws, Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-frames, cross members etc., Complete,
laying concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication
charges for finished item of work PRECAST SLABS FOR COVER OF SEPTIC TANK.
Unit 1 Cum
Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site and including, sales & other taxes
on all materials including all operational, incidental and labour charges such as weigh
6 batching, machine mixing, laying concrete, vibrate, curing etc.,complete but excluding cost of
steel and its fabrication charges for finished item of work (APSS No.402)including centering
shuttering using adjastable Jack Screws, Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-frames, cross members etc., Complete,
laying concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication
charges for finished item of work. RCC BEAMS FOR SEPTCI TANK
Unit 1 Cum
Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened sand with sponge finishing
7 including cost and coneyance of all meterials hacking surface, scaffolding, leads, lifts and
labour charges etc., complete for OUT SIDE WALLS.
Data-S.Tank
Unit 1 Sq.mtr.
Providing High Yield Strength Deformed Steel bars (Fe 415 Grade as per IS: 432 and as
amended upto date) of different diameters including labour charges for cutting, bending to
required size and shapes, placing in position with cover blocks of approved materials and size
and tying firmly with M.S. Binding wire of 20 SWG forming grills for reinforcement work as per
approved designs and drawings including cost and conveyance of deformed steel bars,
8 including all wastage such as overlaps, welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all incidental, opeartional, labour charges such
as cutting bending placing in position, tying etc., including sales and other taxes on all
materials etc., complete for finished item of work in all floors (APSS No.126) (Payment will be
made on the basis of weight of fabrication deformed bars only) (No re-rolled steel shall be
allowed) complete for (8 mm to 40 mm).
Unit 1 M.T
Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not exceeding 15 cm thick,consolidating each
deposited layer by watering and ramming including cost and conveyance of water to work site
9
and all operational, incidental, labour charges, hire charges of T & P etc., complete for
finisheditem of work. (APSS NO. 309 & 310) OUT
PUT : 6 CUM.
Supplying and fixing of 100 mm dia P.V.C. Plain Tee of Prince / Sudhakar make in position
10 with air tight jointing materials including cost and conveyance of all materials, labour charges,
fixing etc., complete as directed by the department.
Unit : Each
110 mm dia plain Tee vide P.No.82 of item No.403. Rs. 108.00
Data-S.Tank
Add 13.615% contractor's Profit & Over Head charges 14.70
Sundries
Total Rs. 122.70
Masonry work in CM (1:4) prop with Flyash Cement solid blocks of size 230 x 100 x 140 mm
for manufacturing of flyash solid blocks using flyash of 80 kgs, cement of 15 kgs.Gypsum of 5
11 kgs. and stone dust including cost and conveyance of all materials, labour charges,,
scaffolding and curing etc., complete with a compressive strength not lessthan 50 kg/sqcm for
walls for Superstructure Walls for Baffle walls.
Unit : Cum.
Data-S.Tank
ABSTRACT FOR CIRCULAR SUMP
Name of Work :- Construction of G+7 Flats Under Affordable Housing.Schem
partnership at Balaga(V) ,Srikakulam (M) ,Srikakulam (Dist).
Sl. Qty. Description of item Rate
No.
Total:
Add L.S for unforceen items
Cost of sump
ble Housing.Scheme in
kulam (Dist).
Unit Amount
1 Cum. 4,573.87
1
7,738.65
Cum.
1 Cum. 164.67
1
12,205.71
Cum.
1
33,382.35
Cum.
1
6,284.70
Cum.
1 M.T. 35,577.07
1Sq.m
19,348.84
tr.
1 Sq.
5,696.71
mtr.
Each 3,129.20
128,101.77
1,898.23
130,000.00
DETAILED ESTIMATE FOR SUMP
Sl.
Description of item Nos. L
No.
c For Sump side wall concrete 1x 1 3.14/4 (2.90 X 2.90 - 2.60 X 2.60)
Supply and placing of the Design Mix Concrete of M
30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
6 mixing, laying concrete, vibrate, curing etc.,complete
but excluding cost of steel and its fabrication
charges for finished item of work (APSS
No.402)including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work FOR
CIRCULAR SUMP COVER SLAB.
1x 1 --
MP
B D Qty
-- 1.000 Nos
DATAS FOR SUMP
Earth work excavation for foundations and depositing on bank for all lifts and with an
initial lead of 10m including all operational, incidental, labour charges such as shoring
1 incidental, sheeting, planking, strutting, etc. complete for finished item of work .in
ordinary soils by manual means upto 3.00mt depth excluding dewatering charges etc.
as per SS- 20 B (APSS 308)
Unit 1 Cum
2 Laying PCC work of mix (1 : 4 : 8) proof. Using 40 mm gauge hard granite machine
crushed metal including cost and conveyance of all materials, machine mixing, labour
charges, tamping, cruing seinarge charges, taxes etc., complete.
Unit 1 Cum
3498.90
Filling with useful available excavated earth (excluding rock) in trenches, sides of
foundations and basement with initial lead in layers not exceeding 15 cm
3 thick,consolidating each deposited layer by watering and ramming including cost and
conveyance of water to work site and all operational, incidental, labour charges, hire
charges of T & P etc., complete for finisheditem of work. (APSS NO. 309 & 310).
Unit 1 Cum.
Rate Rs. 24.65 per 1 Cum
Unit 1 Cum
5 Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using
WEIGH BATCHER with 12mm and 20mm size graded machine crushed hard granite
metal (coarse aggregate) from approved quarry including cost and conveyance of all
materials like cement, fine aggregate sand) coarse aggregate, water etc., to site and
including , sales & other taxes on all materials including all operational, incidental and
labour charges such as weigh batching, machine mixing, laying concrete, vibrate,
curing etc.,complete but excluding cost of steel and its fabrication charges for finished
item of work (APSS No.402)with minimum cement content as per IS code from
standard suppliers approved by the department including centering shuttering using
adjastable Jack Screws, Props and Acro span beams including all pipe brancings,
clamps couplings pre fabricated steel H-frames, cross members etc., Complete, laying
concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication
charges for finished item of work FOR CIRCULAR SUMP SIDE WALLS
.
Unit : 1 Cum.
Providing High Yield Strength Deformed Steel bars (Fe 415 Grade as per IS: 432 and
as amended upto date) of different diameters including labour charges for cutting,
bending to required size and shapes, placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding wire of 20 SWG forming grills for
reinforcement work as per approved designs and drawings including cost and
conveyance of deformed steel bars, including all wastage such as overlaps, welded
7
joints, chairs spacer bars including cost and conveyance of binding wire cover blocks
and all incidental, opeartional, labour charges such as cutting bending placing in
position, tying etc., including sales and other taxes on all materials etc., complete for
finished item of work in all floors (APSS No.126) (Payment will be made on the basis
of weight of fabrication deformed bars only) (No re-rolled steel shall be allowed)
complete for (8 mm to 40 mm).
Unit 1 M.T
Unit 1 Sqm
Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened sand with sponge
9 finishing including cost and coneyance of all meterials hacking surface, scaffolding,
leads, lifts and labour charges etc., complete for OUT SIDE WALLS.
Unit 1 Sq.mtr.
Supplying and fixing 50.8 Cm dia C.I. Man hole frame & cover for chamber (Medium
weight ) as per IS:1726-40Kgs. For Circular Sump
10
Each
1 No. cost of 50.8 Cm. dia C.I Man hole frame &cover Rs. 2683.00
vide p.No166 of Item No.687
Add M.L.240% on labour charges at Rs.356.00
vide p.No.166 of Item No.688 Rs. 71.20
Total Rs. 2754.20
Add Over haeds & Contractors profit at 13.615% Rs. 374.98
Sundries 0.02
Total Rs. 3129.20
D A T A S 2016-2017
c) Material
Water kl
Cost of gravel as per lead chart cum
Cost for 10 cum
Rate per cum
Add 13.615 % towards overheads & Contractors profit
Sundries
Rate per 1 cum
2 Providing Modified penetration mecadam (MPM) Roads using 40 m
Cum/Sq.mtr and with required quantity of 12 mm size stone chips at 0.018
and 60/70 grade bitumen 2 Kg. per Sq.mts including removal of the loos
trimming the edges to provide firm vertical faces, cleaning, applying tack
duly ramping to fill voids and compacting with three wheel statick roller o
charges of Hydrallic self propelled chip spreader both for agreegates and
bitumen pressure distributer and power roller etc., complete for compacted
Say Rs 7.81
4 Providing laying of close graded premix surface materials mixed seal surf
by hot mix plant using hard blasted granite crushed aggregates of 13.2 mm
per table 500-26 of specification 512 of MoRTH & H (4th revision) pre mix
60/70 grade at 19 Kgs per 10 Sqm are including cost and transporting the
with mechanical paver finisher to the require grade, leavel and alignm
wheeled roller 8 to 10 tonnes as per MoRTH & H specifications 512 (4
finished item of work in all respects as directed by the Engineer-in-|Charge
Unit - 1Sq.Mtr
Taking out Put 500 Sq.mts.
A) Labour
Mazdoor (Unskilled) Day 21.00
Mazdoor (Skilled) Day 8.40
Total
Add M.L @ 20 % on labour charges Rs 9408.00
B) Machinary
Mix all hour 6.00
Oil fired bitumen boiler hour 6.00
P.No.28, Item No. 29
Three wheeler roller 8 to 10 T Hour 6.00
page No.43, item No.50 of S.S.R
Add: M.L. 20% on labour Rs 210.90 x 20 % = Rs 42.18
Bitumen @ 22Kg. Per 10 Sq,mtr. T 1.10
Stone chips 13.20 to 9.00 Cum 13.50
Add Over haeds & Contractors profit at 13.615%
Add sundries
Total
Rate for 1 Sq.mtr =
7 Earthen Embeankment with carrted earth from approved source to site for
as per standered specification including cost and conveyance of all materia
complete.
Unit - Sq.mtr.
350.00 Rs. 2800.00
350.00 Rs. 840.00
Rs. 728.00
Rs. 35.50
1122.10 Rs. 37870.88
Rs. 42.18
1650.00 Rs. 9900.00
Say Rs 164.99
Emulsion (medium setting ) (Bulk) using emulsion
Sq.mtr on the prepared bitumen by Granular surface
ed item of work as per morth and H specification 503
Unit - 1 Sq.mtr.
Unit - 1Sq.Mtr
Rs. 2058.00
Rs. 42.18
29172.98 Rs. 32090.28
693.40 Rs. 9360.90
Rs. 1274.49
Rs. 0.04
Rs. 64367.29
Rs. 128.73
m approved source to site for leveling the road portions
and conveyance of all material and labour charges etc.,
Unit 1 Cum
Rs. 31.50
Rs. 28.50
Rs. 60.00
Rs. 8.17
0.03
68.20