Sie sind auf Seite 1von 1

 !

" 

 *% #

  $

)  c  %


Check
After the
Check
Producethat
the
there
that
for
the
ainstallation
the
installation
pipework
location
alignment
valves
pipe
painting,
equipment
set
defects
all
check-valves
allisthe
the correct
of
of
apipework
flow
flanges
the
suitable
marked-up
bolts
are
list
of
direction
the
installation
of
materiel
of
tagging,
correctly
the
of
has
for
aand
are
the
insulation
all
and
does
valve
operate
access,
pipe
issue
been
pipe-supports
fasteners
mounted
pipe
drawings
of
valves
conforms
labeling
not
anchors.
check
lubricated
in
the
conforms
bonded
guides.
freely
both
the
and
invalves
are
any
square
that
are
Punch
in
the
and
to
to
before
as
undamaged.
accordance
way
operate
suitably
and
are
to
the
ittrace-heating
isper
colour
operates
specifications,
to
in
List.
load
specifications.
as
they
they
drawings
each
the
per
and
lubricated.
coding
and
have
correct
are
specifications
other.
with
freely.
Also
tostress
installed
as
the
maintain
and
of
the
sense/direction.
check
per
Also
drawings
pipework
correct
specifications.
installation.
the
specifications.
the
into
the
equipment
valves.
and
spindle
bolting
position.
and
ancillaries
and and it
TOTAL FINA
c  Produce
Check
Ensure
Produce
Check
Make
Seal
For
RemoveELF
Hydraulic
Pneumatic
Air
Emergency
Consolidate
Where
At
Produce
Check
Remove
Replace
Ensure
Verify
Produced
Pack
Produce
Check
Check
Check
the
Receiver.
Compressor.
Filter.
Drier.
floating
up
the
time
a
the
that
brake
for
that
all
out
visually
both
the
visualy
for
location,
that,
heater
that
the
for
both
out
that
the
with
applicable,
location,
that,
for
that
the
that
the
for
that
a
marked-up
the
dimentional
the
a
that
a(both
a
the
Circuit.
Tank.
a
painting
handchain
any
freedom
any
the
free
set
condition
pipework
compressor
holding
painting
filter
coupling
location,
refer
flue
free
defects
installation
general
a
any
the
lift
alignment
mechanical
correct
launcher
operation
vessel
structure
platforms
belt-sheave
blade-tip
fan
pump,
gearbox
coupling
painted
filter
accessibility
painting
equipment
set
unit
marked-up
defect
defects
free
Circuit.
package
crane
mounting
alignment
freedom
location,
set
the
after
there
preservation
earthing
painting
painted
filter
connecting
turbine
unit
operation
heater
valving
combustion
metering
each
when
all
defects
mounting
location,
lubrication
preservation
pump,
heat
there
the
with
of
set
maintenance
general
all
mounting
location
location,
pump,
any
Slewing
both
the
disconnected
there
each
when
all
preservation
roofs:
defects
the
lift
unit
all
there
when
the
with
both
after
pump,
internally
bolting,
all
there
any
preservation
the
set
preservation
both
on
availability
transport
fan
the
internal
linkage
there
all
the
compressor
(both
available
the
all
itand
the
all
location,
nameplate
the
removal
detailed
correct
free
of
refractory
the
installation
bolts
bolting
of
all
pump,
free
the
of
installation
painting,
for
refer
earthing
gas
the
nameplate
of
spool-piece,
unbolted
access
stack
bolting
suction
as
installation
painting
vacuum
channel
rotation
ladder
freon
insulation
reciprocating
earthing
supports,
coupling
equipment
fan
hydraulic
all
correct
name
for
of
crane
shafts
doors
S.W.L.
bearings
operational
hoist
operation
air
drive
louvres
discharge
strainer
head-tank
nameplate
"Tag
location
filter
holding
bolting
the
fuel
seal-gas
pre-filters
anti-vibration
access
package
load/radius
temporary
coupling
rotation
materiel
gantry
caisson
earthing
element,
utility
launcher
exchanger
of
vessel
seawater
equipment
for
the
crane
preservation
fan
drains
internal
air
installation,
supports
eathing
when
nozzles
manway
pipe
filter
chillers
water
ball-valve
turbine
acoustic
coupling
compressor
suction,
skid
items
temporary
two
bolting
nameplate
inlet
heater
observation
holding
gantry
stores
fixing
casing
large
the
earthing
motor
gearbox
trolley
equipment
stops
preservation
painting
HVAC.
hoist
of
piping
vessel
to
access
damage
plates
lift,
installation
inlet
unbolted
the
temporary
of
motorised
(stuffing
correct
pig
hypochIorite
positioners
is
maintenance
filter
unbolting
above
as
elevation,
disconnected
general
gantry
nozzles
heater
location
tracing
access
crane
stores
exchanger
bearings
air
marked-up
the
connecting
coupling
drive
(equipment
exchanger
rope
cooler
stuffing-box
ladder
Vendor
individual
is
lube
marked-up
the
plates
drains
coupling
of
pinion
nozzles
vessel
pulsation
has
is
Vendor
internals
location
marked-
for
suction
caisson
gearbox
the
elevation,
individual
pump,
disconnected
gantry
marked-up
nameplate
refer
inspection
input
is
the
chlorination
centering
of
coupling
list
installation
internally
freedom
the
pipe
painting
required.
in
lubrication
(holding
refer
rack
nozzlels
internal
bearings
coupling
is
platforming
ladders
warning
pipe-supports
check
for
hose
recommended
painting
outlet
marked
functioning
cleanliness.
down
marked-up
hoist
C-HX-09
/the
commissioning
is
nozzles
list
C-HX-01
earthing
platforming
rotation
movement
driver,
and
cleanliness.
marked-up
the
painted
surfaces
accessibility
rising-main
arrangement
hose
list.
list
coupling
is
nameplate
cleanliness
accessability
shaft
bearings
operation
and
commissioning
visually
the
is
sampling
adequate
check
surfaces
or
of
list
equipment
nameplate
visually
visualy
required.
and
refer
centering
inlet
no
not
possible
adequate
sytems
alignment.
the
for
elevation,
insulation
visually
have
and
pre-filters
suction
rack
for
sufficient
adequate
flanges
drawings
preservation
to
nozzles
launcher
cleanliness
transporter
internally
clearances
connections
external
gearbox,
throughout
list
is
motor,
of
adequate
for
elevation,
pipework
piping-supports
System.
the
and
strainers
auxillary
elevation
elevation,
supports
cleanliness.
access
elevation,
is
transport/shipping
coupling
elevetion
adequate
belts
and
internals
holding
conforms
of
charge
pump,
elevation,
gaskets
bearings,
preservation
auxillary
utility
into
internally
arrangements
strainer
for
to
adequate
platforming
Number"
piping-supports
between
and
the
correct
check
ropes
plate
items
is
bolting
of
been
cleanliness.
arrangement
platforming
including
location
piping
can
adequate
movement.
expansion
identification
insulation
has
location
installation
are
cleanliness
for
arrangement
of
and
coupling
belt
shaft
rising
is
to
for
crane
of
are
bolts
clips
internally
nozzles
C-CX-01
contain
piping
has
is
pipework
pipe
ladders
installation
for
to
of
the
and
supports
ductwork
welding
movement
operation
internally
are
strainers
is
cleanliness.
installed
doors
for
list
arrangements
arrangments
arrarngements
down
alignment.
and
is
its
driver,
temporary
holding
nozzles
motor
of
any
are
elevation,
to
the
with
ductwork
material
of
visually
down
line,
indicators
is
and
cover
has
be
tubes-support
contain
in
arrangement,
supports
couplings
insulation
components
belt
to
elevation
is
tightened
installed
are
and
door
the
discharge
element
number
guard
in
guards
plate
drawings
can
has
flanges
is
and
wheels
bonding
elevation,
inclusion
issue
system
arrangements.
door
box
suitably
work
has
the
are
and
is
pads
enclosure
elevation,
covers
to
lubricator
in
suitably
the
be
internally
system
incurred
piping
and
is
internals
are
of
has
bonded
clearly
correctly
the
components
coupling,
and
location
ladders;
suitably
be
clevis
displayed
issue
accessibility
reeved
is
on
its
been
cleanliness.
zone
discharge
C-DX-01
of
that
flanges
access
issue
incusion
inclusion
has
damage.
head
coupling
the
is
and
that
inaccordance
operates
free
gearbox
C-KX-06
damage.
has
inclusion
be
issue
installed
sound
the
auxillaries
details
and
pipework
of
bolting
are
installed.
been
has
correctly
strainer
damage
commissioning
damage.
cleanliness.
up
is
details
data
internally
of
handrail
guards
location,
fine
alignment
painting
wire
and
for
alignment
level.
externally
be
pipe
damper
installed
orientation
has
is
been
control
included
of
that
details
"Tag
nameplate
both
pipe-supports
sufficiently
reassembled
up
element
down
pipe
and
for
surfaces
not
diagram
the
undamaged
zone
can
spacer
no
pit-prop.
loading
correctly
fine
C-GX-07
for
the
are
filter
damper
for
actuators
and
installation
supports
in
of
sign,
"Tag
which
rotates
for
its
from
car
suitably
)the
been
internal
issued
included
doors,
visualy
is
satisfied
drawings
motor
holding
orientation
trolley
guards
installed
bonding
are
the
door
bag.
burners
connected
level
issued
of
is
correctly
visualy
rings
drawings
pressure
main
for
and
the
been
finish
bonding
interior
fluids
output
compressor
which
preserved
pipework
satisfied
been
insulation
the
is
mountings
installation.
points
ladders
bonding
drawings
fan
pump,
of
packing
is
the
be
preserved
bonded
withdrawn
output
arrangements
suitably
arragement
and
been
are
bonding
blanked-off
fluids
space
bolting
water
the
rotation.
for
piping
pipework
alignment
items
to
details
position
access
is
drawings
adjacent
fan
drum.
arrangement
arrangements
space
installed
packing
tower
elevation
in
shaft.
and
have
final
can
for
the
unit
pump
shaft
of
been
are
included
pipework
/is
items
space
and
adjacent
can
orientation
ladders
the
correctly
are
access
damage.
any
been
shaft
drawings
installation
coupling
in
to
pipework
he
the
and
space
seawater
drains
damage.
has
installation
down
orientation
all
platfoming
been
sections
in
pipwork
installed
pipework
brackets
are
is
mesh
that
to
of
cleanliness.
discharge
clean.
any
space
orientation
insulation
re-tightened
the
incuding
internals
been
suitably
discharge
down
tower
bonded
auxillaries
in
internal
baseplate
of
are
complete.
ropes.
sequence
suction
correctly
is
orientation
details
its
in
pins.
supports
and
of
space
for
operate
the
stores
orientation
station
damage.
mesh
are
details
flanges
on
space
and
finer-mesh
coupling
centered
in
installed
)bolts.
not
the
can
pipework
be
accordance
for
bonding
is
clean.
correctly
displayed
to
of
power
Number"
have
space
securely
vessel
filters
the
set
motor
of
suitably
installed
has
are
is
for
coupling
the
tank
drive
withdrawn
lubricated.
stores
and
to
coupling
rotate
correct.
of
damage
withdraw
the
correctly
has
cleanliness.
use
lubricated.
clear.
shaft.
where
according
installed.
all
quality
are
of
and
motor
the
at
rotor,
tower
on
commissioning
opens
is
has
lubricated.
the
and
correctly
Punch
insalled
are
during
orientation
both
correct
complete
arrangement
the
Number"
in
(where
and
damage.
suitably
crane
is
bonding
are
to
"Do
be
the
spares,
for
and
coupling
coating
suction,
of
connects
carried
rack,
Number"
pump,
two
is
aligned
its
undamaged.
ladders
sections
has
be
fine
damage.
piping
in
orientation
the
pump,
and
filters
rotates
complete.
are
have
of
internals
level
guards
installed
on
and
been
)filled
clear.
spares,
each
the
any
carried
cleanliness.
situated
in
lubricants
is
linkage
of
for
not
hatch.
and
orientation
at
installation
are
the
damage
)disconnected
coupling
correctly.
been
freely
of
tower
damage.
orientation
in
have
line.
overpressure
at
baseplate
the
on
carried
plates
elevation,
are
for
is
and
in
unit
securely
installed
correctly
to
withdrawn
elbow
the
cleanliness.
of
coupling
available
in
for
lining
down
have
trap
shaft
are
the
shaft.
of
commissioning
rotating
isolated
flanges
orientation
in
air
available
be
has
correctly
around
are
insulated
coupling
is
(where
to
clean
Punch
the
check
for
available
&((! carried
installed
satisfied
bellows
its
bonded
the
)shaft
can
for
strainer
are
carried
and
of
in
correctly
is
project
hoist
unit.
to
arrangements
correct
complete
removed.
around
are
without
undamaged.
has
correct.
and
in
Punch
been
the
coupling
installed
maintenance.
commissioning
correct.
all
correct
carried
that
each
lubricated.
ladders
Punch
are
complete
available
is
withdrawn
stub-pedestal
in
been
the
correctly
isolated
doors,
unit.
at
of
correct
compatible.
are
orientation
and
bolting.
available
clearly
accordance
Punch
the
is
in
long
filter
strainer
roof
internal
that
their
belt
or
damage.
the
anchored
after-
arrangements,
inlet,
undamaged
is
are
available
in
been
both
which
combustible
each
of
the
unit.
correct
is
complete
gangway
ladders
can
damage.
any
available
utility
withdraw
to
orientation
which
turbine,
for
guards.
doors.
not
use
baseplate
coolant
and
skid
in
ladders
available
Not
to
linings
crane
gantry
of
are
any
installed.
mesh
brackets
flanges,
lining
the
lubricated.
damage.
correctly.
outlet
is
removed
baseplate
in
also
are
to
motor
flanges
inlet
perform
accordance
gaskets
remove
and
have
in
cab
correctly.
correctly
conformity,
not
freely.
is
which
are
applicable.
when
internally
issued
grease
cleanliness.
the
and
flanges
has
accordance
lift
are
damage.
installed
freely
in
been
undamaged
correct.
suction
with
between
discharge
correct
can
the
after
filter
installed.
accordance
lubricated.
of
in
List
Punch
flangers
been
handlebar
are
pipe,
flanges
in
installed.
been
accordance
for
platforms
issued
Punch
are
has
constructed
and
undamaged
gearbox,
have
in
suitably
mounted
be
platforming
piping
applicable).
lubricated.
correctly
ifis
are
adequately
Punch
accordance
installed
been
guard
damage.
correct.
gearbox,
top
in
overflows
the
Where
out
inaccordance
have
are
and
against
pipe
for
been
place
visually
accordance
lift
within
runway
the
out
correct
and
Punch
arrangements
couplings
has
freely.
of
connecting
lining
be
accordance
that
pipe-supports
damage.
for
protected.
on
piping
and
correct.
is
eliminator
are
the
out
sealed
correct
discharge
guards,
in
accordance
and
bolted.
pontoons.
installed
connecting
accordance
spares,the
mounted.
carried
cooler
of
out
that
bolting,
to
individual
Punch
damage.
is
couplings
and
guards
accordance
using
fan
the
piping
stations.
installed.
tightened.
on
damage.
and
List.
their
to
discharge
accordance
have
correct
disconnected,
after
of
the
compliance
are
issued
discharge
installed
have
outlet
motor
applicable)
is
correct.
accordance
the
be
and
in
skid
impeller.
with
of
are
stack-damper.
serviceable.
installed.
Lift
element.
filters
installation.
the
List.
damage.
rotary
is
in
drawings.
strainer,
been
vented.
to
used
against
with
correct.
out
withdrawn
List.
pipe-supports
installed.
guards
correctly
the
be
and
conformity.
in
correctly.
issue.
leading
vessel
both
tightened.
out
(is
on
damage.
the
and
are
in
has
List.
that
cleanliness.
displayed
use
both
for
and
the
specifications
been
installed.
correct
are
to
in
cleanliness.
filter
preserved.
valve.
not
inspection.
correctly
the
out
that
and
of
allow
complete.
correct
plumb.
package
in
its
used
to
orientation
guard
and
filter
using
removed
plus
lubricants,
as
the
that
correct.
interlocks.
accordance
to
in
cooler
for
runway
bolts
if
and
are
installed
been
on
unit
that
of
guard
installed.
to
and
installed
the
correct.
heater
is
supplied
unit
engaged
in
chain.
that
and
the
accordance
hypochlorite
use
removed
installed;
blades.
within
are
enable
Punch
with
including
supplied
accordance
the
for
correct
supply
been
supports
front
and
installed
carried
that
nipples
Also
combustion
are
correct.
List.
lift
correctly
both
unit
accordance
carried
to
that
and
replaced
withdrawn
remove
are
for
have
maintenance.
applicable).
correct.
installed.
been
regulator
of
that
List
List.
the
condition
accordance
tube-bundle
Punch
have
withdraw
shaft.
the
provide
damage.
to
List
and
accordance
pump
with
be
List.
commissioning
is
the
in
platforming
and
baseplate
beam
using
to
gearboxes,
piping
spares
connected
applicable
unit
installation
List
per
in
complete.
are
installed.
the
gantry.
accordance
openings.
correctly
that
cartridge
filter
been
from
suitable
complete
runway
enable
complete.
have
in
tightened
damage.
sealed.
the
damaged
gantry
lined
and
are
the
complete
specifications.
baseplate
been
flanges
provision
up
for
beam
in
holding
and
that
are
the
List
bottom
in
direction.
carried
and
with
combustion
bearings,
is
that
coupling
skid
out
elevation
installed.
the
and
maintenance
complete.
have
verify
withdraw
coupling
exchanger
the
pump,
have
installed
being
and
in
correct
gearbox
is
alignment
the
gaskets
are
damage.
any
coupling
accordance
fuel.
and
correct.
undamaged.
withdraw
pipe
correct
the
level
accordance
are
that
is
suitably
able
for
correct.
adequately
they
remove
accordance
the
cooler.
with
suitable
removed.
and
spares,
units
limits
to
installed
piping
unit.
complete.
issue.
secure.
there
with
the
discharge
inspection.
"downshop
accordance
have
installed
Also
correct.
and
the
with
to
installed
accordance
correct.
corrrect.
direction.
and
install-
correct
have
spares,
item
heater
are
issue.
and
check
damage.
plates
also
package
with
pump
to
the
has
in
(cooling
both
supported
the
been
unit
correct
baseplate
duct-work
pipes,
in
bolted
correctly
suitably
with
and
has
the
ready
List.
beams.
vessel
approved
in
and
pipes
issue.
turbine
heater
skid
Load
utility
Note
ita
with
that
withdraw
and
skid
duct-work
Also
with
vessel
is
their
also
the
and
installed.
been
correctly
with
that
are
there
they
oil-filters
boltings,
crane
in
and
List.
installed
that
the
with
for
conform
gearbox
has
that
correct.
with
and
piped
out
has
that
suitably
with
be
auxiliary
also,
the
shaft
filter
been
and
platage
special
drum
includes
over
relative
are
safe
with
the
for
that
easy
and
out
over
design.
correct
filter
nozzle
to
on
align
flanges
use
bolting
and
the
rear
suitable
are
nozzle
(where
a
at
easily
use
utility
unit
beams
the
all
that
the
Punch
motor
of
check
out
been
the
or
that
has
down
when
lifting
limits
is
been
using
filters
align
is
are
(The
the
easily
both
their
vent
is
safe
filter
able
also
itrails
for
with
is
an
the
both
and
air
that
in
it
to
all
with
Also
the
and
are
pipe
itis
not
the
with
tha
and
job
that
are
pig
tab-
and
the
via
is
for
are
the
no
is
all
its
is
of
(if
to
its
in
is
in
ifitin
is in   

1 Check that the pipework and equipment are drained as per procedure
Check that the pipework and equipment (re)installation conforms to the
2
specifications, drawings and to the P&ID's
Check that new gasket have been installed after pipework and equipment
3
reinstallation
Check that the pipework, valves, check valves are undamaged. Also check the
4
ancillaries and any other components.

5 After the (re)installation of a valve check that it operates freely.


Check that the flow direction of the valves and ckeck-valve is in the correct
6
sense/direction.
Check that the valves have been correctly lubricated and that they have the correct
7
spindle packing

8 Check that all the bolts and fasteners are suitably lubricated.
Check that after pre-commissioning is finished that the painting of piping systems
9
and of the equipment is "touched up" to conform to the specifications
Check for the correct tagging, labelling and colour coding of pipework and
10
equipment.

11 Produce a set of marked-up drawings in accordance with the installation.


All temporary supports are removed and permanent supports are in full contact with
12
pipes and the base, all clamp supports are installed, bolted and torqued.

13 All the required punch list items are closed. (Yes/No)


The vent and drain installed for hydro test shall be seal welded after hydro test and
14
required NDE performed.

15 Lay-up completed and required preservation applied.

16 Produce a defects list for issue in the Punch List.




 c

c)./(+,c- ((+,c - c( +(


c&'()

$(

Das könnte Ihnen auch gefallen