1 Check that the pipework and equipment are drained as per procedure
Check that the pipework and equipment (re)installation conforms to the
2
specifications, drawings and to the P&ID's
Check that new gasket have been installed after pipework and equipment
3
reinstallation
Check that the pipework, valves, check valves are undamaged. Also check the
4
ancillaries and any other components.
8 Check that all the bolts and fasteners are suitably lubricated.
Check that after pre-commissioning is finished that the painting of piping systems
9
and of the equipment is "touched up" to conform to the specifications
Check for the correct tagging, labelling and colour coding of pipework and
10
equipment.