PROJECT BACKGROUND
The Project
The project is intended for the design of a distribution substation that will have a load of 50 MVA from
the existing 25 MVA. At present time, the area has been struggling to be provided and distributed with
an efficient supply of electric power with the complications that the Electric Cooperative is experiencing.
Certain problems are intended to be solved with this design project. The following are taken into
consideration in accomplishing the project:
1. System Reliability
2. System Stability
3. System Loss
Project Objectives
The project aims to design the distribution system of CANORECO. Specifically, it addresses the
following:
a. Design of distribution lines from the Lag-on Daet Substation and Calitaan Substations.
b. Design of distribution substation, specifically:
i. Protection
ii. Grounding
iii. Transformer Sizing
The Client
The client of the project is the Camarines Norte Electric Cooperative, Inc. situated in the Bicol Region
Area.
Start
Plotting of Distribution
Distribution Substation
Transformer
Short Circuit
Protection
Final
Design
End