Sie sind auf Seite 1von 39

GE Renewable Energy Original

Technical Documentation
Wind Turbine Generator Systems
1&2MW Platform

Bus Bar to Cable Installation


Check List (BBCICL)
Applicable for Wind Turbine Generators from 1.5 MW to 2.4 MW

Project:
Turbine ID:

imagination at work
2016 General Electric Company. All rights reserved.
GE Renewable Energy
Original

www.gepower.com

Visit us at
www.renewables.gepower.com

All technical data is subject to change in line with ongoing technical development!

Copyright and patent rights

This document is to be treated confidentially. It may only be made accessible to authorized persons. It may
only be made available to third parties with the expressed written consent of General Electric Company.

All documents are copyrighted within the meaning of the Copyright Act. The transmission and reproduction of
the documents, also in extracts, as well as the exploitation and communication of the contents are not allowed
without express written consent. Contraventions are liable to prosecution and compensation for damage. We
reserve all rights for the exercise of commercial patent rights.

2016 General Electric Company. All rights reserved.

GE and are trademarks and service marks of General Electric Company.

Other company or product names mentioned in this document may be trademarks or registered trademarks of
their respective companies.

imagination at work
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Table of Contents
1 Purpose .............................................................................................................................................................................................................. 5
1.1 Disclaimer ............................................................................................................................................................................................... 5
1.2 Inspection Criteria............................................................................................................................................................................... 6
1.3 Definition of Abbreviations ............................................................................................................................................................. 6
2 Safety Information ........................................................................................................................................................................................ 6
3 Tooling ................................................................................................................................................................................................................ 8
4 Names of the Employees........................................................................................................................................................................... 8
5 Turbine Information ..................................................................................................................................................................................... 9
6 Torque Tooling Information...................................................................................................................................................................... 9
7 Hub Cables Inspection/Anemometer Wind Mast ....................................................................................................................... 13
8 Cable Installation Nacelle-to-Bus Bar at Saddle / Bus Bar Transition .............................................................................. 14
9 Insulated Bus Bar at Saddle / Bus Bar Transition ....................................................................................................................... 16
10 Insulated Bus Bars Tower Flange Top-to-Mid __ ................................................................................................................... 17
11 Communication and Power Cables Tower Flange Top-to-Mid __ ................................................................................ 19
12 Insulated Bus Bars Tower Flange Mid __ to Mid __ .......................................................................................................... 20
13 Communication and Power Cables Tower Flange Mid __ to Mid __ ........................................................................ 22
14 Insulated Bus Bars Tower Flange Mid __ - to Mid __ ....................................................................................................... 23
15 Communication and Power Cables Tower Flange Mid __ to - Mid __ ......................................................................... 25
16 Insulated Bus Bars Tower Flange Mid __ to Mid __ .......................................................................................................... 26
17 Communication and Power Cables Tower Flange Mid __ to Mid __ ....................................................................... 28
18 Insulated Bus Bars Tower Flange Mid __ to Base .............................................................................................................. 29
19 Communication and Power Cables Tower Flange Mid __ to Base ........................................................................ 31
20 Insulated Bus Bars at Tower / DTA Transition ......................................................................................................................... 32
21 Down Tower Assembly ....................................................................................................................................................................... 33
22 Foundation Inspection....................................................................................................................................................................... 38
23 Verification Sheet .................................................................................................................................................................................. 39

3
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

1 Purpose
The purpose of this installation check list is to verify the quality and integrity of complete turbine installation.

This document applies to all current and future WTG unit configurations that are based off of the 1&2MW
Platform design, e.g.:

1.x-70.5 / 77 / 82.5 / 87 / 100 / 103


2.x-107 / 116.

NOTE
Prior to final tightening of the lugs on Generator or DTA/PDC perform an
INSULATION INTEGRITY TEST according to GE procedure 104W2311. Log results
and attach to BBCICL (Request procedure from Requisition Engineering).

NOTE
For Details related to Insulated Bus Bar system refer to latest revision of GE
Canada Manual:
1.x: Manual #443(Busbar rev.1) #624(Busbar rev.2)
2.x: Manual #672(Busbar rev.3)

NOTE
For details related to Down Tower Assembly, Stator/Rotor, power and
communication Cables, refer to GE Installation Manuals:
Installation_Manual_1.x-xxHz_1-2MW_EN
Installation_Manual_2.0-2.4-xxHz_1-2MW_EN

1.1 Disclaimer
GE Energy does not accept liability for activities/work/conditions resulting in any non-conforming items or
conditions where (a) customer subcontractor(s) signed this check list. These items include but are not limited to
loose foundation bolts, loose tower flange bolts, cable termination, and exterior cleanliness or any
unacceptable condition.
All line items are to be checked for data, signed, initialed or not applicable (N/A) must be checked. Use of
whiteout is not permitted. Any item not checked off complete, signed or marked as not applicable must be
entered as a punch list item with the party responsible for completion of the item identified.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 5/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

1.2 Inspection Criteria


Inspect each line item listed in this check list, for Complete items enter initial and date in the space provided,
for Not Applicable items place a check mark in the box.

If using a printed version use blue ink for all signatures and to complete all fields. Only original documents are
to be inserted in to Job Site Books.

For digital copies refer to the Verification Sheet (signature page).

Use `Not Applicable' if equipment configuration does not apply.

For all fields requiring SSO - Identification Code GE employees shall use their SSO numbers and
customers/contractors shall use their agreed upon company identification e.g. initials or employee ID number.

1.3 Definition of Abbreviations


Term Definition
CB-Q1 Main Circuit Breaker CB1, CB2, CB3 for 575 V or Q1 for 690 V.
DTA or Down Tower Equipment
DTA DTA- 690 V single console (ESS configuration)
PPM- Pre Assemble Power Module could be 575 V or 690 V
ESS Electrical System Simplification
PDC Power Distribution Cabinet
CFC Converter Filter Cabinet
MCC Main Control Cabinet
CBC Converter Bridge Cabinet

2 Safety Information

ATTENTION
Please read all these instructions completely and clarify any unclear points
prior to commencing work!
Please also read and observe the Safety Chapter included in the Operating
Instructions Manual of the Wind Turbine Generator System!

Work described in this Installation Check List may only be carried out by trained technical personnel who
have been authorized by GE Company.
Comply with the general accident prevention regulations for all work.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
6/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

DANGER
Electrical hazard!
Turbine de-energized state:
WTG with the external unit transformer (PMT):
De-energized state means the turbine is isolated from any potential energy
source by one of the following means in order of preference:
1. Unit transformer (PMT) high or low side is not terminated and
terminations controlled with LOTO. Temporary generator is not
connected to the DTA and stored energy devices (UPS, capacitors etc.) are
isolated/discharged/verified zero voltage.

2. Unit transformer (PMT) oil switch/vacuum circuit breaker is open, verified,


lock applied to prevent oil switch/vacuum circuit breaker closure and
safety grounds attached. Temporary generator is not connected to the
DTA and stored energy devices (UPS, capacitors etc.) are
isolated/discharged/verified zero voltage.

For units with external PMT & MVSG apply LOTO and temporary
safety grounds in accordance with site specific MVSG LOTO.
3. Other location for isolation, (junction box, air switch, switchgear etc.)
requires approval from regional EHS before proceeding.

WTG with the internal unit transformer (PMT):


De-energized state means the turbine is isolated from any potential energy
source by one of the following means in order of preference:
1. High voltage cables are not routed into the WTG. Temporary generator is
not connected to the DTA and stored energy devices (UPS, capacitors etc.)
are isolated/discharged/verified zero voltage.

2. Other location for isolation, (junction box, air switch, switchgear etc.)
requires approval from regional EHS before proceeding.

Definitions:
Temporary Safety Grounds: Grounding cables shall be large enough to
withstand conductor fault current until up stream protective equipment operates.
Grid: The distribution system between points of consumption and production of
energy.
Grid Capable: Utility power can be distributed from or to the Wind Turbine
Generator System. WTGS can be energized using electricity from the power
company or temporary power for commissioning activities or to produce
electricity.
Note 1: Reference the latest procedure for connecting portable generator to
turbine.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 7/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Note 2: Review IIP pre condition documentation to ensure no critical punch list
items are identified.
For more detailed information, refer to the Energization Process Flow Chart.

WARNING
Electrical hazard!
Stored energy may be present within electrical cabinets.
Consult with GE engineering to identify the voltages that could be present.
Verify site-specific LOTO has been applied.
Refer to the latest Energization Flow Chart.

3 Tooling
Refer to installation manual for tool list.

4 Names of the Employees


Name SSO / Identification Code

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
8/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

5 Turbine Information
Turbine Type
1.x 70.5 1.x-77 1.x82.5 1.x87 1.x-100 1.x-103

2.x 107 2.x 116 Other:


Tower Type
2 Sections 3 Sections 4 Sections 5 Sections 6 Sections
Base and Top Base, Mid 1, Top Base, Mid 1, 2, Top Base, Mid 1, 2, 3, Top Base, Mid 1, 2, 3, 4, Top

6 Torque Tooling Information

NOTE
Tooling calibration dates are 3rd party calibration dates.

PMT to PDC
Crimping Die Information
Mechanical Hydraulic Hydraulic Crimping
Torque Wrench Pump/Gauge Heads Connection
Connection Grounds
Stator/Rotor
Serial No.: Serial No.: Serial No.: Die No.: Die No.:

Manufacturer: Manufacturer: Manufacturer: Manufacturer: Manufacturer:

Calibration Date: Calibration Date:

Rotor/Stator/Ground DTA/ESS
Crimping Die Information
Mechanical Hydraulic Hydraulic Crimping
Torque Wrench Pump/Gauge Heads Connection
Connection Grounds
Stator/Rotor
Serial No.: Serial No.: Serial No.: Die No.: Die No.:

Manufacturer: Manufacturer: Manufacturer: Manufacturer: Manufacturer:

Calibration Date: Calibration Date:

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 9/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Transition Bus Bar to cable Base / DTA Initial Torque


Crimping Die Information
Mechanical Hydraulic Hydraulic Crimping
Torque Wrench Pump/Gauge Heads Connection
Connection Grounds
Stator/Rotor
Serial No.: Serial No.: Serial No.: Die No.: Die No.:

Manufacturer: Manufacturer: Manufacturer: Manufacturer: Manufacturer:

Calibration Date: Calibration Date:

Transition Bus Bar to Cable Base / DTA 2-hour torque check


Mechanical
Torque Wrench
Serial No.:

Manufacturer:

Calibration Date:

Base to Mid 1 (or Top for 2 Section Tower )

Initial Torque 2-hour torque check


Mechanical Mechanical
Torque Wrench Torque Wrench
Serial No.: Serial No.:

Manufacturer: Manufacturer:

Calibration Date: Calibration Date:

Mid 1 to Mid __ N/A

Initial Torque 2-hour torque check


Mechanical Mechanical
Torque Wrench Torque Wrench
Serial No.: Serial No.:

Manufacturer: Manufacturer:

Calibration Date: Calibration Date:

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
10/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Mid __ to Mid __ N/A

Initial Torque 2-hour torque check


Mechanical Mechanical
Torque Wrench Torque Wrench
Serial No.: Serial No.:

Manufacturer: Manufacturer:

Calibration Date: Calibration Date:

Mid __ to Mid __ N/A


Initial Torque 2-hour torque check
Mechanical Mechanical
Torque Wrench Torque Wrench
Serial No.: Serial No.:

Manufacturer: Manufacturer:

Calibration Date: Calibration Date:

Mid __ to Top

Initial Torque 2-hour torque check


Mechanical Mechanical
Torque Wrench Torque Wrench
Serial No.: Serial No.:

Manufacturer: Manufacturer:

Calibration Date: Calibration Date:

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 11/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Transition Bus Bar to Cable - Saddle Initial Torque


Crimping Die Information
Mechanical Hydraulic Hydraulic Crimping
Torque Wrench Pump/Gauge Heads Connection
Connection Grounds
Stator/Rotor
Serial No.: Serial No.: Serial No.: Die No.: Die No.:

Manufacturer: Manufacturer: Manufacturer: Manufacturer: Manufacturer:

Calibration Date: Calibration Date:

Transition Bus Bar to Cable - Saddle 2-hour torque check


Mechanical
Torque Wrench
Serial No.:

Manufacturer:

Calibration Date:

Generator
Crimping Die Information
Mechanical Hydraulic Hydraulic Crimping
Torque Wrench Pump/Gauge Heads Connection
Connection Grounds
Stator/Rotor
Serial No.: Serial No.: Serial No.: Die No.: Die No.:

Manufacturer: Manufacturer: Manufacturer: Manufacturer: Manufacturer:

Calibration Date: Calibration Date:

Electrical Validation
Insulation Resistance
Serial No.: Manufacturer: UL or CE mark present Calibration Date:
Testing
Yes No
High Potential Testing Serial No.: Manufacturer: UL or CE mark present Calibration Date:
Yes No

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
12/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

7 Hub Cables Inspection/Anemometer Wind Mast


Hub Cables Inspection/Anemometer Wind Mast
Item Description Initials Date N/A

7.1 Verify hub cables are inspected for damage.

Verify cables are routed and secured to support through flex tubing
7.2 and conduit connector into hub control cabinet or axis 1 with lock
ring installed.
Remove jumper wires on Salem pitch and ESS Salem main control
7.3
box.

7.4 Verify cables are neatly secured with cable ties inside hub cabinet.

Verify hub control cables are terminated according to latest Point


7.5
to Point.
After each wire is terminated, perform a pull test to ensure the
7.6
connection is not loose.

7.7 Verify all hub cabinet doors are closed and secured.

7.8 On 1.x only, verify straps are installed on hub cabinets.

7.9 Verify hub is clean and free of tools, materials, and trash.

Verify hub access cover is installed with all hardware and retaining
7.10
pins installed, tightened and secured.
Verify all hub hatches are closed properly, ensuring pins are not
7.11
damaged.
Install the anemometer and wind vane to the mast. Wind vane (V)
and anemometer (A) as labeled This Side Toward the Rotor,
7.12 grounds attached to mast.
NOTE: Non applicable if ultrasonic anemometer/wind vane is
installed.
Verify the wind vane and anemometer mast is bolted correctly in
7.13 the upright position, undamaged and shipping materials removed,
and marked as torqued.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 13/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

8 Cable Installation Nacelle-to-Bus Bar at Saddle / Bus Bar Transition


Cable Installation Nacelle-to-Bus Bar at Saddle / Bus Bar Transition
Item Description Initials Date N/A

8.1 Secure Rotor, Stator and GND cables to tray under generator.

2.x only: Terminate wires in generator junction box per latest PTP
8.2
(point to point).
Verify stator cables and stator ground coming from the nacelle are
8.3 marked according to local electrical code (to ensure proper
phasing).
Verify rotor cables and rotor ground coming from the nacelle are
8.4 marked according to local electrical code (to ensure proper
phasing).
Route all cables down through the platform A and cable collector
8.5
ring/s.
Verify cable sets are routed and secured to saddle with cable ties in
8.6
3 locations.

Dress the rotor, stator and ground cables through the transition
cable tray top rungs and install neoprene and steel cable ties. Use
RT2HT cable tie gun with correct tension setting (refer to installation
8.7 manual for tension values). Verify neoprene and steel ties are
secured to rungs with two nylon cable ties. Fasten the cable
bundles to the lower cable tray rungs using two zip ties in an X
pattern or double wrap a single zip tie.

If applicable verify high temperature (HT) tape is applied to the


8.8
cable trefoils.
If applicable, verify fiber reinforced tape (3M tape) is installed on the
vertical section of all cable trefoils and communication cablese very
8.9
500mm including spacers from dual saddle at yaw deck down to
the drip loop at the saddle.
Verify that the correct amount of spacers are installed and located
in accordance with the latest engineering drawing for 1.x or 2.x
configuration respectively.
8.10 Attach 3-phase cable bundles as well as control, fiber optic and
auxiliary supply. Cables arranged neatly around the spacers and
secured with cables ties per drawing.
Cable ties are to be oriented outwards to avoid damages to the
other cables.
2.x only: Ensure thermal probe is installed in accordance with the
8.11
Installation Manual.
Verify tower hoist power cable is connected and routed to the
8.12
bottom of the tower secured to cable tray
Verify tower lighting and receptacle power cords are connected
8.13
and routed to the bottom of the tower secured to cable tray
Verify the inside of the nacelle and top deck is clean and free of
8.14
debris

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
14/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Cable Installation Nacelle-to-Bus Bar at Saddle / Bus Bar Transition


Item Description Initials Date N/A

For 1.x: Verify steel cable with steel weight is routed through twist
8.15 switch eye, in PVC pipe and anchored to closest trefoil. Verify 67
inches from twist switch eye to top of activation ball.

For 1.x: Verify twist control cable is routed and terminated to twist
8.17 switch. After each wire is terminated, perform a pull test to ensure
the connection is not loose.
For 1x only: Adhesive permeated fiberglass is applied to the cable
8.18 bundle where it passes through the platform A and cable collector
rings.
Verify all cables clear hoist, ladder, and safety cable anchor or rail
8.19
system.
Verify Stator/Rotor cables are phased correctly at splice location
8.20 and route cables through appropriate cable glands (strain reliefs)
located on the top of the bus bar tray cable entry
Before cables are cut, ensure all cables are measured with an
8.21
approximate 1070 mm drip loop at saddle
Verify Ground, communication and power cables are routed and
8.22 secured to cable tray next to the bus bar system with cable ties at
every hole all the way to the bottom of the next tower section.
Verify that the 2 ground cables are lugged and connected to the
8.23
cable-tray end.
After the wire connector (lugs) is crimped and prior to electrical
8.24 insulation is applied, perform a pull test to ensure connectors are
not loose.
If required by local code, there is an option to separate the 690 V
8.25 cables from the communication cables in tower cable-tray. Two (2)
pairs of holes are available for that purpose.
Ensure the fiber optic cable is secured from pinching / crushing and
8.26 does not exceed the minimum bend radius through the full length
of tower.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 15/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

9 Insulated Bus Bar at Saddle / Bus Bar Transition


Insulated Bus Bar at Saddle / Bus Bar Transition
Item Description Initials Date N/A

Verify stator, rotor, and ground cables are properly splice-crimped


9.1 (die stamp imprinted legibly) at saddle (ensure no cut strands and
no strands outside the barrel).
After the wire connector (lugs) is crimped and prior to electrical
9.2 insulation is applied, perform a pull test to ensure connectors are
not loose.
All bus bar to lug contact surfaces at saddle transition are
9.3
thoroughly cleaned as per Bus Bar Installation.
Verify Mobile 28 grease is applied to the inner contact surfaces of
9.4
the bus bar (Do not apply grease to BNW hardware).

9.5 Ensure that all bolting hardware are free of Mobil 28 grease.

Verify lugs are attached to bus bar with hardware. Verify the
correct torque value is applied to the lug/bus bar connections per
9.6 torque table for each bolted arrangement.
Record torque value: ______
Perform the torque checking procedure (after a waiting time of 2
hours) as specified in the manual. Write the torque value, date and
9.7 sign your name on the solid cover using a permanent marker.
Record torque value: ______
Verify excess grease is removed and Insulated shrink sleeves are
9.8
installed at connections per assembly drawing.
Verify cable glands (strain reliefs) are secured and tightened on all
9.9
cables.
All bus bar insulation is checked for damage and thoroughly
9.10
cleaned.
Verify protective cover on top of the assembly is in place (refer to
9.11
assembly drawing).
Perform a visual inspection for the complete bus bar length down
9.12 to the next tower section to ensure no damage and proper
installation is achieved.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
16/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

10 Insulated Bus Bars Tower Flange Top-to-Mid __


Insulated Bus Bars Tower Flange Top-to-Mid __
Item Description Initials Date N/A

Verify that the distance between two (2) tower sections bus bars is
10.1
approximately 1338mm 10 mm.
Verify all flexible braids and bus bar contact surfaces are
10.2
thoroughly cleaned (using a non abrasive pad).
Verify the insulating boots (sleeves) are installed on the stator and
10.3 rotor conductors.
2.x only: Verify heat shrink is installed as per Bus Bar Manual
Verify Mobile 28 grease is applied to the inner contact surfaces of
10.4 the bus bar and on the contact surfaces between the Z connector
and the cable trays. (Do not apply grease to BNW hardware).

10.5 Verify that all bolting hardware are free of Mobile 28 grease.

Verify bus bar splice section is installed with a solid connection to


10.6
the bottom and flexible connection at top.
Flexible braids are connected to existing bus bar and bolted
together:
1.x Rotor Bus Bar: 1 small flexible connection per phase.
10.7
1.x Stator Bus Bar: 1 large flexible connection per phase.

2.x Rotor & Stator: 2 large flexible connection per phase.


Verify that you have a gap of at least 3 mm between the
10.8
conductors.
Verify that you have a gap greater than 25 mm between the back
10.9
of the bus bars and the tower flange.
Verify the correct torque value was applied to the upper and lower
connections per torque table for each bolted arrangement and
10.10 verify paint pen torque mark is present.
Record torque value: ______
Perform the torque checking procedure (after a waiting time of 2
hours) as specified in the manual. Write the torque values, date and
10.11 sign your name on the solid cover using a permanent marker.
Record torque value: ______
Verify excess grease is removed and Insulated boots (sleeves) and
retaining hardware (if needed) are installed at connections over
10.12 flexible braids and bolts per assembly drawing.
2.x only: Verify heat shrink is installed as per Bus Bar Manual.
Verify solid and flexible ground connection plates are attached and
10.13 bolts torqued, verify paint pen mark is present.
Record torque value: ______
Verify all flexible braids and bus bar insulation is checked for
10.14
damage and thoroughly cleaned (remove tools).

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 17/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Insulated Bus Bars Tower Flange Top-to-Mid __


Item Description Initials Date N/A

Verify protective cover on top of the assembly is in place (refer to


10.15
assembly drawing).

10.16 Verify safety sign is attached to the protective cover.

Verify communication and power cable tray (with an offset) is


attached using the appropriate hardware and torque value.
10.17
Be sure that EPDM plate and Braided connector have been installed
and torqued properly at cable tray bridge section.
Perform a visual inspection for the complete bus bar length down
10.18 to the next tower section to ensure proper installation was
achieved.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
18/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

11 Communication and Power Cables Tower Flange Top-to-Mid __


Communication and Power Cables Tower Flange Top-to- Mid __
Item Description Initials Date N/A

Verify communication and power cables are routed and secured to


cable tray with cable ties through each pair of holes.
11.1 NOTE: If required by local code, there is an option to separate the
690 V cables from the communication cables in tower cable tray.
Two (2) pairs of holes are available for that purpose.
Verify tower lighting and receptacle power cords are connected
11.2 and secured and are in good working condition, protected from
sharp edges.
After each wire is terminated, perform a pull test to ensure the
11.3
connection is not loose.
Verify saddle and Top-to-Mid platforms are clean and free of
11.4
debris.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 19/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

12 Insulated Bus Bars Tower Flange Mid __ to Mid __


N/A

Insulated Bus Bars Tower Flange Mid __- to Mid __


Item Description Initials Date N/A

Verify that the distance between two (2) tower sections bus bars is
12.1
approximately 1338 mm 10 mm.
Verify all flexible braids and bus bar contact surfaces are
12.2
thoroughly cleaned (using a non abrasive pad).
Verify the insulating boots (sleeves) are installed on the stator and
12.3 rotor conductors.
2.x only: Verify heat shrink is installed as per Bus Bar Manual..
Verify Mobile 28 grease is applied to the inner contact surfaces of
12.4 the bus bar and on the contact surfaces between the Z connector
and the cable trays. (Do not apply grease to BNW hardware).

12.5 Verify that all bolting hardware are free of Mobile 28 grease.

Verify bus bar splice section is installed with a solid connection to


12.6 the bottom and flexible connection at top.
(Bus bar rev.3 uses 2 solid connectors and 2 flexibles per phase).
Flexible braids are connected to existing bus bar and bolted
together:
1.x Rotor Bus Bar: 1 small flexible connection per phase.
12.7
1.x Stator Bus Bar: 1 large flexible connection per phase.

2.x Rotor & Stator: 2 large flexible connection per phase.


Verify that you have a gap of at least 3 mm between the
12.8
conductors.
Verify that you have a gap greater than 25 mm between the back
12.9
of the bus bars and the tower flange.
Verify the correct torque value was applied to the upper and lower
connections per torque table for each bolted arrangement and
12.10 verify paint pen torque mark is present.
Record torque value: ______
Perform the torque checking procedure (after a waiting time of 2
hours) as specified in the manual. Write the torque values, date and
12.11 sign your name on the solid cover using a permanent marker.
Record torque value: ______
Verify excess grease is removed and Insulated boots (sleeves) and
retaining hardware (if needed) are installed at connections over
12.12 flexible braids and bolts per assembly drawing.
2.x only: Verify heat shrink is installed as per Bus Bar Manual.
Verify solid and flexible ground connection plates are attached and
12.13 bolts torqued, verify paint pen mark is present.
Record torque value: ______

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
20/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Insulated Bus Bars Tower Flange Mid __- to Mid __


Item Description Initials Date N/A

Verify all flexible braids and bus bar insulation is checked for
12.14
damage and thoroughly cleaned (remove tools).
Verify protective cover on top of the assembly is in place (refer to
12.15
assembly drawing).

12.16 Verify safety sign is attached to the protective cover.

Verify communication and power cable tray (with an offset) is


attached using the appropriate hardware and torque value.
12.17
Be sure that EPDM plate and Braided connector have been installed
and torqued properly at cable tray bridge section.
Perform a visual inspection for the complete bus bar length down
12.18 to the next tower section to ensure proper installation was
achieved.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 21/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

13 Communication and Power Cables Tower Flange Mid __ to Mid __


N/A

Communication and Power Cables Tower Flange Mid __ - to Mid __


Item Description Initials Date N/A

Verify communication and power cables are routed and secured to


cable tray with cable ties through each pair of holes.
13.1 NOTE: If required by local code, there is an option to separate the
690 V cables from the communication cables in tower cable tray.
Two (2) pairs of holes are available for that purpose.
Verify tower lighting and receptacle power cords are connected
13.2 and secured and are in good working condition, protected from
sharp edges.
After each wire is terminated, perform a pull test to ensure the
13.3
connection is not loose.

13.4 Verify Mid-to-Mid platform is clean and free of debris.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
22/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

14 Insulated Bus Bars Tower Flange Mid __ - to Mid __


N/A

Insulated Bus Bars Tower Flange Mid __- to Mid __


Item Description Initials Date N/A

Verify that the distance between two (2) tower sections bus bars is
14.1
approximately 1338 mm 10 mm.
Verify all flexible braids and bus bar contact surfaces are
14.2
thoroughly cleaned (using a non abrasive pad).
Verify the insulating boots (sleeves) are installed on the stator and
14.3 rotor conductors.
2.x only: Verify heat shrink is installed as per Bus Bar Manual.
Verify Mobile 28 grease is applied to the inner contact surfaces of
14.4 the bus bar and on the contact surfaces between the Z connector
and the cable trays. (Do not apply grease to BNW hardware).

14.5 Verify that all bolting hardware are free of Mobile 28 grease

Verify bus bar splice section is installed with a solid connection to


14.6 the bottom and flexible connection at top.
(Bus bar rev.3 uses 2 solid connectors and 2 flexibles per phase).
Flexible braids are connected to existing bus bar and bolted
together:
1.x Rotor Bus Bar: 1 small flexible connection per phase.
14.7
1.x Stator Bus Bar: 1 large flexible connection per phase.

2.x Rotor & Stator: 2 large flexible connection per phase.


Verify that you have a gap of at least 3 mm between the
14.8
conductors.
Verify that you have a gap greater than 25 mm between the back
14.9
of the bus bars and the tower flange.
Verify the correct torque value was applied to the upper and lower
connections per torque table for each bolted arrangement and
14.10 verify paint pen torque mark is present.
Record torque value: _______
Perform the torque checking procedure (after a waiting time of 2
hours) as specified in the manual. Write the torque values, date and
14.11 sign your name on the solid cover using a permanent marker.
Record torque value: _______
Verify excess grease is removed and Insulated boots (sleeves) and
retaining hardware (if needed) are installed at connections over
14.12 flexible braids and bolts per assembly drawing.
2.x only: Verify heat shrink is installed as per Bus Bar Manual.
Verify solid and flexible ground connection plates are attached and
14.13 bolts torqued, verify paint pen mark is present.
Record torque value: _______

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 23/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Insulated Bus Bars Tower Flange Mid __- to Mid __


Item Description Initials Date N/A

Verify all flexible braids and bus bar insulation is checked for
14.14
damage and thoroughly cleaned (remove tools)
Verify protective cover on top of the assembly is in place (refer to
14.15
assembly drawing).

14.16 Verify safety sign is attached to the protective cover.

Verify communication and power cable tray (with an offset) is


attached using the appropriate hardware and torque value.
14.17
Be sure that EPDM plate and Braided connector have been
installed and torqued properly at cable tray bridge section.
Perform a visual inspection for the complete bus bar length down
14.18 to the next tower section to ensure proper installation was
achieved.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
24/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

15 Communication and Power Cables Tower Flange Mid __ to Mid __


N/A

Communication and Power Cables Tower Flange Mid __ - to Mid __


Item Description Initials Date N/A

Verify communication and power cables are routed and secured to


cable tray with cable ties through each pair of holes.
15.1 NOTE: If required by local code, there is an option to separate the
690 V cables from the communication cables in tower cable tray.
Two (2) pairs of holes are available for that purpose.
Verify tower lighting and receptacle power cords are connected
15.2 and secured and are in good working condition, protected from
sharp edges.
After each wire is terminated, perform a pull test to ensure the
15.3
connection is not loose.

15.4 Verify Mid-to-Mid platform is clean and free of debris.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 25/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

16 Insulated Bus Bars Tower Flange Mid __ to Mid __


N/A

Insulated Bus Bars Tower Flange Mid __- to Mid __


Item Description Initials Date N/A

Verify that the distance between two (2) tower sections bus bars is
16.1
approximately 1338 mm 10 mm.
Verify all flexible braids and bus bar contact surfaces are
16.2
thoroughly cleaned (using a non abrasive pad)
Verify the insulating boots (sleeves) are installed on the stator and
16.3 rotor conductors.
2.x only: Verify heat shrink is installed as per Bus Bar Manual.
Verify Mobile 28 grease is applied to the inner contact surfaces of
16.4 the bus bar and on the contact surfaces between the Z connector
and the cable trays. (Do not apply grease to BNW hardware).

16.5 Verify that all bolting hardware are free of Mobile 28 grease

Verify bus bar splice section is installed with a solid connection to


16.6 the bottom and flexible connection at top.
(Bus bar rev.3 uses 2 solid connectors and 2 flexibles per phase).
Flexible braids are connected to existing bus bar and bolted
together:
1.x Rotor Bus Bar: 1 small flexible connection per phase.
16.7
1.x Stator Bus Bar: 1 large flexible connection per phase.

2.x Rotor & Stator: 2 large flexible connection per phase.


Verify that you have a gap of at least 3 mm between the
16.8
conductors
Verify that you have a gap greater than 25 mm between the back
16.9
of the bus bars and the tower flange
Verify the correct torque value was applied to the upper and lower
connections per torque table for each bolted arrangement and
16.10 verify paint pen torque mark is present.
Record torque value: ______
Perform the torque checking procedure (after a waiting time of 2
hours) as specified in the manual. Write the torque values, date and
16.11 sign your name on the solid cover using a permanent marker.
Record torque value: ______
Verify excess grease is removed and Insulated boots (sleeves) and
retaining hardware (if needed) are installed at connections over
16.12 flexible braids and bolts per assembly drawing.
2.x only: Verify heat shrink is installed as per Bus Bar Manual.
Verify solid and flexible ground connection plates are attached and
16.13 bolts torqued, verify paint pen mark is present.
Record torque value: ______

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
26/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Insulated Bus Bars Tower Flange Mid __- to Mid __


Item Description Initials Date N/A

Verify all flexible braids and bus bar insulation is checked for
16.14
damage and thoroughly cleaned (remove tools).
Verify protective cover on top of the assembly is in place (refer to
16.15
assembly drawing).

16.16 Verify safety sign is attached to the protective cover.

Verify communication and power cable tray (with an offset) is


attached using the appropriate hardware and torque value.
16.17
Be sure that EPDM plate and Braided connector have been installed
and torqued properly at cable tray bridge section.
Perform a visual inspection for the complete bus bar length down
16.18 to the next tower section to ensure proper installation was
achieved.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 27/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

17 Communication and Power Cables Tower Flange Mid __ to Mid __


N/A

Communication and Power Cables Tower Flange Mid __- to Mid __


Item Description Initials Date N/A

Verify communication and power cables are routed and secured to


cable tray with cable ties through each pair of holes.
17.1 NOTE: If required by local code, there is an option to separate the
690 V cables from the communication cables in tower cable tray.
Two (2) pairs of holes are available for that purpose.
Verify tower lighting and receptacle power cords are connected
17.2 and secured and are in good working condition, protected from
sharp edges.
After each wire is terminated, perform a pull test to ensure the
17.3
connection is not loose.

17.4 Verify saddle and Top-to-Mid platforms are clean and free of debris.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
28/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

18 Insulated Bus Bars Tower Flange Mid __ to Base


Insulated Bus Bars Tower Flange Mid __ to Base
Item Description Initials Date N/A

Verify that the distance between two (2) tower sections bus bars is
18.1
approximately 1338 mm 10 mm.
Verify all flexible braids and bus bar contact surfaces are
18.2
thoroughly cleaned (using a non abrasive pad).
Verify the insulating boots (sleeves) are installed on the stator and
18.3 rotor conductors.
2.x only: Verify heat shrink is installed as per Bus Bar Manual.
Verify Mobile 28 grease is applied to the inner contact surfaces of
18.4 the bus bar and on the contact surfaces between the Z connector
and the cable trays. (Do not apply grease to BNW hardware).

18.5 Verify that all bolting hardware are free of Mobile 28 grease

Verify bus bar splice section is installed with a solid connection to


18.6 the bottom and flexible connection at top.
Refer to Bus Bar Manual.
Flexible braids are connected to existing bus bar and bolted
together:
1.x Rotor Bus Bar: 1 small flexible connection per phase.
18.7
1.x Stator Bus Bar: 1 large flexible connection per phase.

2.x Rotor & Stator: 2 large flexible connection per phase.


Verify that you have a gap of at least 3 mm between the
18.8
conductors.
Verify that you have a gap greater than 25 mm between the back
18.9
of the bus bars and the tower flange
Verify the correct torque value was applied to the upper and lower
connections per torque table for each bolted arrangement, verify
18.10 paint pen torque mark is present.
Record torque value: ______
Perform the torque checking procedure (after a waiting time of 2
hours) as specified in the manual. Write the torque values, date and
18.11 sign your name on the solid cover using a permanent marker.
Record Torque Value : ______
Verify excess grease is removed and Insulated boots (sleeves) and
retaining hardware (if needed) are installed at connections over
18.12 flexible braids and bolts per assembly drawing.
2.x only: Verify heat shrink is installed as per Bus Bar Manual.
Verify solid and flexible ground connection plates are attached and
18.13 bolts torqued, verify paint pen mark is present.
Record Torque Value : ______

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 29/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

Insulated Bus Bars Tower Flange Mid __ to Base


Item Description Initials Date N/A

Verify all flexible braids and bus bar insulation are checked for
18.14
damage and thoroughly cleaned (remove tools)
Verify protective cover on top of the assembly is in place (refer to
18.15
assembly drawing)

18.16 Verify safety sign is attached to the protective cover

Verify communication and power cable tray (with an offset) is


attached using the appropriate hardware and torque value.
18.17
Be sure that EPDM plate and Braided connector have been installed
and torqued properly at cable tray bridge section.
Perform a visual inspection for the complete bus bar length down
18.18 to the next tower section to ensure proper installation was
achieved.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
30/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

19 Communication and Power Cables Tower Flange Mid __ to Base


Communication and Power Cables Tower Flange Mid __ to Base
Item Description Initials Date N/A

Verify communication and power cables are routed and secured to


cable tray with cable ties through each pair of holes.
19.1 NOTE: If required by local code, there is an option to separate the
690 V cables from the communication cables in tower cable tray.
Two (2) pairs of holes are available for that purpose.
Verify tower lighting and receptacle power cords are connected
19.2 and secured and are in good working condition, protected from
sharp edges.
After each wire is terminated, perform a pull test to ensure the
19.3
connection is not loose.

19.4 Verify saddle and Top-to-Mid platforms are clean and free of debris.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 31/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

20 Insulated Bus Bars at Tower / DTA Transition


Insulated Bus Bars at Tower / DTA Transition
Item Description Initials Date N/A

Identify stator cable and stator ground coming from the DTA to
20.1
ensure proper phasing and mark according to local electrical code.
Identify rotor cables and rotor ground coming from the DTA to
20.2
ensure proper phasing and mark according to local electrical code.
Verify that the 2 ground cables are lugged and connected to the
20.3
cable-tray end.
Verify the cables coming from DTA are routed through platform on
20.4
cable tray with cable ties supporting the weight of the cables.
Verify stator and rotor cables are phased correctly at splice location
20.5 and cables routed through appropriate cable glands (strain reliefs)
located on the top of the bus bar tray.
Before cables are cut, ensure all cables are measured ensuring
20.6 proper length provided for termination and appropriate service drip
loop if applicable.
Verify each stator, rotor, and ground cables are properly splice-
20.7 crimped (die stamp imprinted legibly, ensure no cut strands and no
strands outside the barrel).
After the wire connector (lug) is crimped and prior to electrical
20.8 insulation is applied, perform a pull test to ensure connectors are
not loose.
Verify all bus bar-to-lug contact surfaces at transition are
20.9
thoroughly cleaned.
Verify Mobile 28 grease is applied to the inner contact surfaces of
20.10
the bus bar (Do not apply grease to BNW hardware).

20.11 Verify that all bolting hardware are free of Mobile 28 grease.

Verify lugs are attached to bus bars with hardware. Verify the
correct torque value is applied to the lug/bus bar connections per
20.12 torque table for each bolted arrangement.
Record torque value: ______
Perform the torque checking procedure (after a waiting time of 2
hours) as specified in the manual. Write the torque values, date and
20.13 sign your name on the solid cover using a permanent marker.
Record torque value: ______
Verify excess grease is removed and apply insulated shrinks at
20.14
connections over lugs and bus bar per assembly drawing
Verify cable glands (strain reliefs) are secured and tightened on all
20.15
cables.
Verify all bus bar insulation is checked for damage and thoroughly
20.16
cleaned.
Verify protective cover on top of the assembly is in place (refer to
20.17
assembly drawing).

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
32/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

21 Down Tower Assembly


The following steps are CRITICAL TO QUALITY and CRITICAL TO SAFE OPERATION OF TURBINE and CRITICAL
FOR PERSONNEL SAFETY. Applicable to MCC, CFC and PDC cabinets.

DTA Cables Inspection


Item Description Initials Date N/A

If unistruts are not required, remove the unistruts to prevent cable


21.1
wear.

21.2 Verify the conduit is free of sharp edges.

Verify power and neutral cables are correctly routed through


21.3
conduit into PDC cabinet from pad mount transformer.
If applicable, required by local code, cables are properly secured to
21.4
unistruts.

21.5 Verify power and neutral cables are correctly lugged.

After the wire connector (lug) is crimped and prior to electrical


21.6 insulation is applied, perform a pull test to ensure connectors are
not loose.
Perform insulation resistance test to ensure cables were not
damaged when pulled through conduits.
Hi-Potential Test (if
required)
Insulation Resistance Test N/A
Applied Pass/ Applied Pass
Voltage Fail Voltage / Fail
21.7
A
Rotor B
C
A
Stator B
C

Verify power cables are correctly terminated to bottom of Q1 in


PDC cabinet.
21.8 Verify the correct hardware is installed in accordance with the site
specific Collector system drawing (Interface point PMT to PDC).
Record torque value: _______
Mark cable ends with electrical tape in accordance with applicable
21.9
electrical code.
Verify the torque value for power cable lugs to bus bar in PDC is
21.10
written on inside cabinet door.
Verify neutral cables are correctly terminated to:
21.11 1.x : ground bus bar PDC cabinet.
2.x: all grounds are connected to bar under DTA.
Verify the torque value for neutral cable lugs to ground bus bar is
21.12
written on inside cabinet door.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 33/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

DTA Cables Inspection


Item Description Initials Date N/A

Verify Scada fiber optic cables are correctly routed and terminated
21.13
in main controller cabinet, and conduit opening is sealed with foam.

Verify spray foam sealant is applied at conduit openings, and verify


21.14 foam insulation that seals the power cable entry is free of damage
in the PDC cabinet. Apply spray foam if needed.
Cables are laid in the floor-mounted trays and routed neatly into
21.15 the CFC Cabinet through rotor/stator cable entry and secured with
tie wraps. Verify no sharp edges are contacting the cables.
1.x: Stator ground is routed into CFC cabinet through cable glands.
21.16
2.x: All grounds are connected to bar under DTA.
Verify protective cover on top of the assembly is in place (refer to
21.17
assembly drawing)

After the wire connector (lug) is crimped and prior to electrical


21.18 insulation is applied, perform a pull test to ensure connectors are
not loose.
Verify stator lugs in stator j-box at generator are un-terminated and
21.19
perform ohm check

Verify stator cables are phased correctly and terminated to CFC Bus
21.20 bars and write date on inside door of cabinet.
Phasing Date: _________
Mark cable ends with electrical tape in accordance with applicable
electrical code
21.21
Note: Verify gearbox/generator configuration to ensure correct
rotation.
Perform an INSULATION INTEGRITY TEST according to GE procedure
104W2311. Log results on the following table:

Hi-Potential Test (if


required)
Insulation Resistance Test N/A
Applied Pass/ Applied Pass
Voltage Fail Voltage / Fail
21.22
A
Rotor B
C
A
Stator B
C

Verify stator lugs to bus bar are terminated to the DTA and marked
21.23 with a paint pen.
Record torque value: _________
Verify stator ground is terminated in DTA to ground bus bar and
21.24 torqued and mark with a paint pen.
Record torque value: _________

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
34/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

DTA Cables Inspection


Item Description Initials Date N/A

Verify stator lugs in j-box at generator are re-terminated and


torque to value listed on nameplate, mark with paint pen, and write
21.25 date on j-box exterior.
Record torque value: _________
Verify rotor cables and rotor ground are routed into converter with
21.26
a 150 mm clearance between cables and foundation.

1.x: Verify rotor cable and rotor ground between tower and DTA are
attached on the cable support trays and routed neatly into the DTA
cabinet through rotor/stator cable entry and secured with tie
21.27 wraps.
2.x: All tower grounds are connected to the SPG (Single Point
Grounding) bar under DTA.
Verify rotor lugs in rotor j-box at generator are un-terminated and
21.28
perform ohm check.

Verify rotor cables in converter/CFC are phased correctly and


terminated to rotor over voltage contactor and write date phase
verified on inside door of cabinet. Mark cable ends with electrical
21.29 tape in accordance with applicable electrical code.
Verify gearbox/generator configuration to ensure correct rotation.
Record torque value: _________
1.x: Verify rotor ground is terminated to ground bus bar in
Converter/CFC and torqued and mark with a paint pen.
21.30 2.x: Rotor grounds are connected to the SPG (Single Point
Grounding) bar under DTA.
Record torque value: _________
Verify rotor lugs in j-box at generator are re-terminated, torque to
value listed on nameplate, mark with paint pen, and write date on j-
21.31 box interior.
Record torque value: _________
Verify stator cable-sets are neatly formed and secured with cable
21.32
ties every 150 mm.

400 V power cables are routed from the tower cable tray and to the
floor mounted cable support trays and routed neatly into the ESS
21.33
TVSS cable entry. Torque terminations in accordance with the latest

revision of the Bolt Torque Specification.
Control cables are routed from the tower cable tray and to the floor
mounted cable support trays and routed neatly into the ESS MCC
21.34 cable entry If Comm cables are long enough, but that the insulation
jacket of the cable has been stripped too long from factory, the
wires should be cut and referuled.
Verify tower control cables have ferrules and are terminated to
21.35
main controller cabinet.

After each wire is terminated, perform a pull test to ensure the


21.36
connection is not loose.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 35/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

DTA Cables Inspection


Item Description Initials Date N/A

Verify encoder cable is routed through cable tray and secured with
cable ties into the MCC cabinet. Terminate the encoder wires to
21.37
MACC card TB1 terminals as per latest applicable PTP (point to

point).

21.38 Route and terminate ESS exhaust fan wire.

After each wire is terminated, perform a pull test to ensure the


21.39
connection is not loose.

Verify fiber optic cable is routed below deck and above cable tray to
main controller cabinet, and secured with cable ties to frame,
21.40 undamaged. Do not exceed min. bend radius.
Land fiber optic cable at I/O net Ntron Ethernet switch.
If applicable, verify aviation warning beacon controller is installed
and terminated at main controller cabinet or top box depending on
21.41 configuration.
After each wire is terminated, perform a pull test to ensure the
connection is not loose.
Route and terminate the tower light and receptacle cables into the
21.42
MCC cabinet.

If applicable, land at SCADA Ntron Ethernet switch Port 1. If not


21.43
used. Coil outside DTA in lower cable tray.

21.44 Install the UPS (Uninterruptible Power Supply) in the MCC door.

Attach serial cable to rear of UPS. Leave UPS by-passed by securing


21.45
the male plug to itself to prevent it from being plugged in.

Inspect inside the cabinet on top and around connectors (especially


around buss bars Q1). Remove any debris that can potentially
21.46
cause an arc. This will require the removal of panels as required use

of mirrors and flash light.
Verify no loose or misplaced tooling such as torque wrenches,
21.47
backup wrenches, and cable cutters, left attached to the bus bars.

21.48 Look for misplaced hardware, such as nuts washers bolts.

Using Mirror and Flashlight, verify debris, and materials such as


wire strands metal shavings are not left in DTA cabinets (especially
21.49
in gaps and around bus bars, Q1 and Transformer on the left hand

side cabinet).
If units have been in storage for long periods pay attention to
21.50
animal droppings/rodent nesting debris.

Vacuum and/or remove any debris, i.e. wire strands, metallic


21.51 shavings, tools, un-accounted for hardware and animal/rodent
debris.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
36/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

DTA Cables Inspection


Item Description Initials Date N/A

Reinstall all removable frames, close all doors and panels and
attach grounds
IF A TOOL OR HARDWARE IS DROPPED INSIDE OR AROUND Q1 OR
21.52
UNACCOUNTED FOR, DO NOT ENERGIZE TURBINE UNTIL MISSING

OR UNACCOUNTED PARTS OR TOOLS ARE FOUND.
"REPORT TO GE SITE MANAGER IMMEDIATELY IF UNABLE TO FIND".
Verify 2 insulated grounding cables connected from PDC grounding
bus bar to the console grounding bus bar are both marked as
21.53 torque on each side.
Record torque value: _________
Verify foundation and tower flange grounds connected to console
21.54 grounding bus (ESS) bolts marked as torque.
Record torque value: _________
ESS. Cable tray 1 each ground connected to console grounding bus
21.55
bar bolts marked as torqued.

Verify foundation below DTA is clean and free of tooling, hardware,


21.56
debris, and materials

21.57 Verify all debris and materials are removed from DTA walkways

If applicable, verify flood lighting is installed.


21.58 After each wire is terminated, perform a pull test to ensure the
connection is not loose.
Verify expanding foam is applied where applicable e.g., foundation
21.59
conduits and any other unused cable glands in ESS CFC cabinet.

ESS. Attach all cabinet panel covers with hardware and snug tight
21.60
the bolts (final torque to be done during final inspection IIP)

Verify door latches are working properly. Close all cabinet doors,
insert safety screws.
21.61 Torque panel hardware per manufacturers instruction.
BEFORE ENERGIZING DTA, If screws are missing contact GE
representative for instructions.
Any floor panels removed for this process must be reinstalled and
21.62
bolts torqued.

If applicable, install foundation ground lead to the metal tower door


21.63
entry step outside of tower.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 37/39
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

22 Foundation Inspection
Visual inspection of Foundation
Item Description Initials Date N/A

22.1 Power cables routed through conduit and cables free of defect.

22.2 Conduit is free of sharp edges.

Fiber optic cables routed through conduit and free of defects


22.3
comply with minimum bend radius.
All ground cables installed in foundation in accordance with
22.4
country-specific electrical code and free of defects.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
38/39 Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx
GE Renewable Energy
Original
Bus Bar to Cable Installation Check
List

23 Verification Sheet
Project Name:

Tower ID:

Select applicable installation instructions and insert revision Check 1 box Revision

Installation_Checklists_1-2MW-xxHz_CICL

Installation_Checklists_1-2MW-xxHz_ICL
Installation_Checklists_1-2MW-xxHz_IIP
Installation_Checklists_1-2MW-xxHz_Grid

Installation_Checklists_1-2MW-xxHz_BBCICL
Installation_Checklists_1-2MW-xxHz_BoltTorque

I hereby certify that this wind turbine was installed in accordance with the applicable installation instructions
noted above.

SSO / ID No. Print Name Signature Date

As Installation Lead I hereby certify that I have reviewed and accepted this document and that this installation
document applicable fields are 100 % complete and accurate.

SSO / ID No. Print Name Signature Date

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company.
UNCONTROLLED when printed or transmitted electronically.
2016 General Electric Company. All rights reserved.
Installation_Checklists_1-2MW-xxHz_BBCICL_EN_r01.docx 39/39

Das könnte Ihnen auch gefallen