Date of Issue: March 2013

Version: V2
Internal Correspondence
Page: Page 1 of 2

Ref. No.: DC/F7/V1

Date : 22nd May 2013

Ref : MEP/13052210

To : Mr. Hassan Najim; Site Project Manager

Cc : Mr. Youssef Hayek; Head of Supervision Dept.

From : Mr. Ghassan Traboulsi; Lead Mechanical Engineer

Project : Villaggio Mall

Subject : Material Submittal Technical Submittal for FM200 System

Reference to Material Submittal No. MTS-056/13 dated 19th May 2013, please find below review
result;
1. Proposed model is not provided QCDD Approvals, provide the following:
A. Bell SSM24-6
B. Strobe 20 - 091- SA
C. CRM4 10-2204
2. Model # of SHP PRO Fire Extinguishing Panel is not specified in the QCDD Approval.
3. Capacity of FM200 cylinders should be as actual site condition and shop drawings, calculations
and schematic diagram should be submitted.
4. Provide QCDD certificate and UL, FM Approvals for the followings:
a. Impulse valve operator kit
b. Nozzles
c. Pipe fittings
5. Pipe fittings should be glass 300
6. FM 200 System and control panels UL listing certificate as per UL 864 9th edition should be
provided.
7. Pipes should be scheduled 80 Grade B.

The Contractor to resubmit and comply with all comments.

Remarks: Revise and resubmit