This survey and analysis aims to obtain data about the electrical energy
March 13) and provide appropriate action plan to any energy-related problem found
during the survey. This includes the efficiency of the room with respect to the
The data will be gathered by collecting the power rating of each appliance in
each location (rooms, offices and corridors/hallways) and monitoring their time of
usage. Unfortunately, due to the teams tight schedule with other major course
subject, the team cannot monitor the specified area; the time of usage of some
appliances will be based on the rooms schedule while others will be based on
1
Tabulated Data
Archi/ICT Building 1ST FLOOR
2
Appliances/Load/O Total No. No. of Rating Usage Consumption
utlets of Units Working (Watts) (hours) (Watt-hour)
Units
CFL 1 1 20 20 400
Electric Fan 1 1 70 20 1400
Outlets 4
Analysis/Notes: Total 1800
3
Archi/ICT Building 2nd FLOOR
4
Wi-fi Router 1 1 7.65 160 1224
Wi-fi Router HUB 1 1 12.5 160 2000
Speaker MPQ 1 1 300 60 18000
Genius Speaker 1 1 41.8 40 1672
Outlet 12
Analysis/Notes: Total 611056
5
Supply Samsung
Computer Monitor AOC 11 11 330 60 217800
Computer Monitor AOC 1 1 330 60 19800
Flat
Computer Monitor 5 5 396 60 118800
MLite
Computer Monitor 4 4 330 60 79200
AlphaScan Sampo
Fluorescent 4 3 24 80 5760
CFL 3 3 20 80 4800
Aircon 1 1 1492 80 119360
Wi-Fi Router 1 1 1.44 80 115.2
Laptop 1 1 220 20 4400
Projector 1 1 550 20 11000
Outlet 18
Analysis/Notes: Total 1337035.2
6
Projector 1 1 550 20 11000
Outlet 26
Notes: Computer systems are too old to be used by the Total 113400
students, AC and lightings used only during quizzes
7
Outlet
Analysis/Notes: Total 1564276
Data Summary
Location: 1st Floor Consumption (kilowatt-hour)
AR 101 4.680
AR 102 7.020
AR 103 9.360
AR 104 14.040
AR 105 19.224
ROTC Office 1.800
Architecture Department Office 310.760
ICT Lecture Room 2.310
Comfort Room 134.280
Hallway 0
Total 503.474
8
ICT Lab 5 113.400
Cyber Center 1122.5912
Total 6287.77812
Data Analysis
Based on the tabulated data, it shows that most of the power consumption of
the building is from rooms in the second floor, where a lot of computer systems and
air conditioning systems are being used simultaneously throughout the day. This is
due to the fact that most computer-related subjects are being thought in these
facilities and air conditioning system is recommended for the maintaining the
One of the rooms in the second floor, specifically ICT Lab 5 contains obsolete
and old model of computer systems which are not being used anymore due to their
poor performance compared to the newer computer systems in the other rooms.
It is also found out that the rooms in first floor of the building lack lightings
and other appliance such as electric fans are not functional which could result in
discomfort of the students having class in these rooms. Considering that most if not
9
all of the students in these rooms are BS architecture students whose major
subjects are related to drawing, poor lightings has a big impact in their
performance.
The library also has some defective compact fluorescent lamps that may
affect the experience of the students and other personnel doing their work/reading
in the library.
Based on one of the faculty members in the building, the electrical circuit
10
The Action Plan
Implementation Evaluation
Progress Eviden
Objective Activities/ Action In charge Time Resources Expected Output
Indicator ce
Posters advising the
Appliances
To reduce turning-off of appliances
1 Reduced Energy are being
Energy Posting Advisory The Whole Team when leaving the room
week Consumption turned off
Consumption (with the approval of the
properly
department head)
Increase in energy
The Whole Team
To improve Replacement of Compact Fluorescent consumption in CFLs are
(with the 1
lightings in the broken fluorescent Lamps from university exchange for the being
guidance of an week
1st floor lamps budget comfort of the replaced
electrician)
students
Increase in energy
The Whole Team
To improve Replacement of consumption in Electric fans
(with the 1 Electric Fans from
ventilation in broken electric exchange for the are being
guidance of an week university budget
the 1st floor fans comfort of the replaced
electrician)
students
The Whole Team
ICT Lab 5s
(with the
To improve ICT Replacement of 1 Computer Systems from ICT Lab 5 can be Computers
guidance of the
Lab 5 the computers week university budget used efficiently are being
computer
replaced
engineers)
Increase in energy
The Whole Team
To improve Replacement of Compact Fluorescent consumption in CFLs are
(with the 1
lightings in the broken fluorescent Lamps from university exchange for the being
guidance of an week
library lamps budget comfort of the replaced
electrician)
students
Maintain Air Checking and The whole team Once brush Decreased power AC has better
Conditioning cleaning a consumption and output
11
system compressor and increase efficiency
month
efficiency filter of AC
Checking and
The Whole Team
Improve overall repairing of Full operation of all Everything
(with the 1
performance of electrical circuit Electrical Equipments electrical outlets, are working
guidance of an month
building wirings of the lights, etc. properly
electrician)
building
12
Conclusion/ Recommendation
13
Appendices