Sie sind auf Seite 1von 656

THE GRID CODE

ISSUE 5
REVISION 19

30 September 2016

2013 Copyright owned by National Grid Electricity Transmission plc, all rights reserved.

No part of this publication may be reproduced in any material form (including photocopying and restoring in any
medium or electronic means and whether or not transiently or incidentally) without the written permission of
National Grid Electricity Transmission plc, except:

1. to the extent that any party who is required to comply (or is exempt from complying) with the provisions
under the Electricity Act 1989 reasonably needs to reproduce this publication to undertake its licence or
statutory duties within Great Britain (or any agent appointed so to act on that partys behalf); and

2. in accordance with the provisions of the Copyright, Designs and Patents Act 1988.
THE GRID CODE
CONTENTS
CONTENTS* (C)

PREFACE* (P)

GLOSSARY AND DEFINITIONS (GD)

PLANNING CODE (PC)

CONNECTION CONDITIONS (CC)

COMPLIANCE PROCESSES (CP)

OPERATING CODES (OC)

OC1 Demand Forecasts


OC2 Operational Planning and Data Provision
OC3 Not Used
OC4 Not Used
OC5 Testing and Monitoring
OC6 Demand Control
OC7 Operational Liaison
OC8 Safety Co-ordination
OC9 Contingency Planning
OC10 Event Information Supply
OC11 Numbering and Nomenclature of HV Apparatus at Certain Sites
OC12 System Tests

BALANCING CODES (BC)

BC1 Pre Gate Closure Process


BC2 Post Gate Closure Process
BC3 Frequency Control Process

DATA REGISTRATION CODE (DRC)

GENERAL CONDITIONS (GC)

REVISIONS* (R)
*does not constitute part of the Grid Code

Issue 5 Revision 0 C 17 August 2012


i
PREFACE
(P)

(This section does not form part of the Grid Code)

P.1. The Grid Code sets out the operating procedures and principles governing the relationship
between NGET and all Users of the National Electricity Transmission System, be they
Generators, DC Converter owners, Suppliers or Non-Embedded Customers. The Grid
Code specifies day-to-day procedures for both planning and operational purposes and covers
both normal and exceptional circumstances.

P.2 The Grid Code is designed to:


(i) permit the development, maintenance and operation of an efficient, coordinated and
economical system for the transmission of electricity;
(ii) facilitate competition in the generation and supply of electricity (and without limiting the
foregoing, to facilitate the national electricity transmission system being made available
to persons authorised to supply or generate electricity on terms which neither prevent
nor restrict competition in the supply or generation of electricity);
(iii) promote the security and efficiency of the electricity generation, transmission and
distribution systems in the national electricity transmission system operator area taken
as a whole; and
(iv) efficiently discharge the obligations imposed upon the licensee by this license and to
comply with the Electricity Regulation and any relevant legally binding decisions of the
European Commission and/or the Agency.
and is conceived as a statement of what is optimal (particularly from a technical point of view)
for all Users and NGET itself in relation to the planning, operation and use of the National
Electricity Transmission System. It seeks to avoid any undue discrimination between
Users and categories of Users.

P.3 The Grid Code is divided into the following sections:


(a) a Planning Code which provides generally for the supply of certain information by
Users in order for NGET to undertake the planning and development of the National
Electricity Transmission System;
(b) the Connection Conditions which specify minimum technical, design and operational
criteria which must be complied with by NGET at Connection Sites and by Users
connected to or seeking connection with the National Electricity Transmission
System or by Generators (other than in respect of Small Power Stations) or DC
Converter owners, connected to or seeking connection to a User's System;
(c) the Compliance Processes which specify the process that must be followed by NGET
and any Generator or DC Converter Station owner to demonstrate its compliance with
the Grid Code in relation to its Plant and Apparatus.

Issue 5 Revision 0 P 17 August 2012


1 of 2
(d) an Operating Code, which is split into a number of sections and deals with Demand
forecasting (OC1); the co-ordination of the outage planning process in respect of Large
Power Stations, the National Electricity Transmission System and User Systems
for construction, repair and maintenance, and the provision of certain types of
Operating Margin data (OC2); testing and monitoring of Users (OC5); different forms
of reducing Demand (OC6); the reporting of scheduled and planned actions, and
unexpected occurrences such as faults (OC7); the co-ordination, establishment and
maintenance of Isolation and Earthing in order that work and/or testing can be carried
out safely (OC8); certain aspects of contingency planning (OC9); the provision of written
reports on occurrences such as faults in certain circumstances (OC10); the procedures
for numbering and nomenclature of HV Apparatus at certain sites (OC11); and the
procedures for the establishment of System Tests (OC12);
(e) a Balancing Code, which is split into three sections and deals with the submission of
BM Unit Data from BM Participants, and of certain other information, for the following
day and ahead of Gate Closure (BC1); the post Gate Closure process (BC2); and the
procedures and requirements in relation to System Frequency control (BC3);
(f) a Data Registration Code, which sets out a unified listing of all data required by NGET
from Users, and by Users from NGET, under the Grid Code;
(g) General Conditions, which are intended to ensure, so far as possible, that the various
sections of the Grid Code work together and work in practice and include provisions
relating to the establishment of a Grid Code Review Panel and other provisions of a
general nature.
P.4 This Preface is provided to Users and to prospective Users for information only and does not
constitute part of the Grid Code.

< END OF PREFACE >

Issue 5 Revision 0 P 17 August 2012


2 of 2
GLOSSARY & DEFINITIONS
(GD)

GD.1 In the Grid Code the following words and expressions shall, unless the subject matter or
context otherwise requires or is inconsistent therewith, bear the following meanings:

Access Group A group of Connection Points within which a User declares under the
Planning Code
(a) An interconnection and/or
(b) A need to redistribute Demand between those Connection Points
either pre-fault or post-fault
Where a single Connection Point does not form part of an Access
Group in accordance with the above, that single Connection Point shall
be considered to be an Access Group in its own right.

Access Period A period of time in respect of which each Transmission Interface


Circuit is to be assessed as whether or not it is capable of being
maintained as derived in accordance with PC.A.4.1.4. The period shall
commence and end on specified calendar weeks.

Act The Electricity Act 1989 (as amended by the Utilities Act 2000 and the
Energy Act 2004).

Active Energy The electrical energy produced, flowing or supplied by an electric circuit
during a time interval, being the integral with respect to time of the
instantaneous power, measured in units of watt-hours or standard
multiples thereof, ie:
1000 Wh = 1 kWh
1000 kWh = 1 MWh
1000 MWh = 1 GWh
1000 GWh = 1 TWh

Active Power The product of voltage and the in-phase component of alternating current
measured in units of watts and standard multiples thereof, ie:
1000 Watts = 1 kW
1000 kW = 1 MW
1000 MW = 1 GW
1000 GW = 1 TW

Affiliate In relation to any person, any holding company or subsidiary of such


person or any subsidiary of a holding company of such person, in each
case within the meaning of Section 736, 736A and 736B of the
Companies Act 1985 as substituted by section 144 of the Companies Act
1989 and, if that latter section is not in force at the Transfer Date, as if
such section were in force at such date.

AF Rules Has the meaning given to allocation framework in section 13(2) of the
Energy Act 2013.

Issue 5 Revision 19 GD 30 September 2016


1 of 49
Ancillary Service A System Ancillary Service and/or a Commercial Ancillary Service,
as the case may be.

Ancillary Services An agreement between a User and NGET for the payment by NGET to
Agreement that User in respect of the provision by such User of Ancillary Services.

Annual Average Cold A particular combination of weather elements which gives rise to a level
Spell Conditions or ACS of peak Demand within a Financial Year which has a 50% chance of
Conditions being exceeded as a result of weather variation alone.

Apparent Power The product of voltage and of alternating current measured in units of
voltamperes and standard multiples thereof, ie:
1000 VA = 1 kVA
1000 kVA = 1 MVA

Apparatus Other than in OC8, means all equipment in which electrical conductors
are used, supported or of which they may form a part. In OC8 it means
High Voltage electrical circuits forming part of a System on which
Safety Precautions may be applied to allow work and/or testing to be
carried out on a System.

Authorised Electricity Any person (other than NGET in its capacity as operator of the National
Operator Electricity Transmission System) who is authorised under the Act to
generate, participate in the transmission of, distribute or supply electricity.

Automatic Voltage The continuously acting automatic equipment controlling the terminal
Regulator or AVR voltage of a Synchronous Generating Unit by comparing the actual
terminal voltage with a reference value and controlling by appropriate
means the output of an Exciter, depending on the deviations.

Authority for Access An authority which grants the holder the right to unaccompanied access
to sites containing exposed HV conductors.

Authority, The The Authority established by section 1 (1) of the Utilities Act 2000.

Auxiliaries Any item of Plant and/or Apparatus not directly a part of the boiler plant
or Generating Unit or DC Converter or Power Park Module, but
required for the boiler plant's or Generating Unit's or DC Converters or
Power Park Modules functional operation.

Auxiliary Diesel Engine A diesel engine driving a Generating Unit which can supply a Unit
Board or Station Board, which can start without an electrical power
supply from outside the Power Station within which it is situated.

Auxiliary Gas Turbine A Gas Turbine Unit, which can supply a Unit Board or Station Board,
which can start without an electrical power supply from outside the
Power Station within which it is situated.

Average Conditions That combination of weather elements within a period of time which is the
average of the observed values of those weather elements during
equivalent periods over many years (sometimes referred to as normal
weather).

Back-Up Protection A Protection system which will operate when a system fault is not
cleared by other Protection.

Issue 5 Revision 19 GD 30 September 2016


2 of 49
Balancing and The code of that title as from time to time amended.
Settlement Code or BSC

Balancing Code or BC That portion of the Grid Code which specifies the Balancing Mechanism
process.

Balancing Mechanism Has the meaning set out in NGETs Transmission Licence

Balancing Mechanism Has the meaning set out in the BSC.


Reporting Agent or
BMRA

Balancing Mechanism Has the meaning set out in the BSC.


Reporting Service or
BMRS

Balancing Principles A statement prepared by NGET in accordance with Condition C16 of


Statement NGETs Transmission Licence.

Baseline Forecast Has the meaning given to the term baseline forecase in Section G of the
BSC.

Bid-Offer Acceptance (a) A communication issued by NGET in accordance with BC2.7; or


(b) an Emergency Instruction to the extent provided for in BC2.9.2.3.

Bid-Offer Data Has the meaning set out in the BSC.

Bilateral Agreement Has the meaning set out in the CUSC

Black Start The procedure necessary for a recovery from a Total Shutdown or
Partial Shutdown.

Black Start Capability An ability in respect of a Black Start Station, for at least one of its
Gensets to Start-Up from Shutdown and to energise a part of the
System and be Synchronised to the System upon instruction from
NGET, within two hours, without an external electrical power supply.

Black Start Stations Power Stations which are registered, pursuant to the Bilateral
Agreement with a User, as having a Black Start Capability.

Black Start Test A Black Start Test carried out by a Generator with a Black Start
Station, on the instructions of NGET, in order to demonstrate that a
Black Start Station has a Black Start Capability.

Block Load Capability The incremental Active Power steps, from no load to Rated MW, which
a generator can instantaneously supply without causing it to trip or go
outside the Frequency range of 47.5 52Hz (or an otherwise agreed
Frequency range). The time between each incremental step shall also
be provided.

BM Participant A person who is responsible for and controls one or more BM Units or
where a Bilateral Agreement specifies that a User is required to be
treated as a BM Participant for the purposes of the Grid Code. For the
avoidance of doubt, it does not imply that they must be active in the
Balancing Mechanism.

BM Unit Has the meaning set out in the BSC, except that for the purposes of the
Grid Code the reference to Party in the BSC shall be a reference to
User.

Issue 5 Revision 19 GD 30 September 2016


3 of 49
BM Unit Data The collection of parameters associated with each BM Unit, as described
in Appendix 1 of BC1.

Boiler Time Constant Determined at Registered Capacity, the boiler time constant will be
construed in accordance with the principles of the IEEE Committee
Report "Dynamic Models for Steam and Hydro Turbines in Power System
Studies" published in 1973 which apply to such phrase.

British Standards or BS Those standards and specifications approved by the British Standards
Institution.

BSCCo Has the meaning set out in the BSC.

BSC Panel Has meaning set out for Panel in the BSC.

BS Station Test A Black Start Test carried out by a Generator with a Black Start
Station while the Black Start Station is disconnected from all external
alternating current electrical supplies.

BS Unit Test A Black Start Test carried out on a Generating Unit or a CCGT Unit, as
the case may be, at a Black Start Station while the Black Start Station
remains connected to an external alternating current electrical supply.

Business Day Any week day (other than a Saturday) on which banks are open for
domestic business in the City of London.

Cancellation of National The notification given to Users when a National Electricity


Electricity Transmission Transmission System Warning is cancelled.
System Warning

Capacity Market The Capacity Market Rules, The Electricity Capacity Regulations 2014
Documents and any other Regulations made under Chapter 3 of Part 2 of the Energy
Act 2013 which are in force from time to time.

Capacity Market Rules The rules made under section 34 of the Energy Act 2013 as modified
from time to time in accordance with that section and The Electricity
Capacity Regulations 2014.

Cascade Hydro Scheme Two or more hydro-electric Generating Units, owned or controlled by the
same Generator, which are located in the same water catchment area
and are at different ordnance datums and which depend upon a common
source of water for their operation, known as:
(a) Moriston
(b) Killin
I Garry
(d) Conon
(e) Clunie
(f) Beauly
which will comprise more than one Power Station.

Cascade Hydro Scheme The matrix described in Appendix 1 to BC1 under the heading Cascade
Matrix Hydro Scheme Matrix.

Caution Notice A notice conveying a warning against interference.

Issue 5 Revision 19 GD 30 September 2016


4 of 49
Category 1 Intertripping A System to Generator Operational Intertripping Scheme arising from
Scheme a Variation to Connection Design following a request from the relevant
User which is consistent with the criteria specified in the Security and
Quality of Supply Standard.

Category 2 Intertripping A System to Generator Operational Intertripping Scheme which is:-


Scheme
(i) required to alleviate an overload on a circuit which connects the
Group containing the Users Connection Site to the National
Electricity Transmission System; and
(ii) installed in accordance with the requirements of the planning
criteria of the Security and Quality of Supply Standard in order
that measures can be taken to permit maintenance access for
each transmission circuit and for such measures to be
economically justified,
and the operation of which results in a reduction in Active Power on the
overloaded circuits which connect the Users Connection Site to the
rest of the National Electricity Transmission System which is equal to
the reduction in Active Power from the Connection Site (once any
system losses or third party system effects are discounted).

Category 3 Intertripping A System to Generator Operational Intertripping Scheme which,


Scheme where agreed by NGET and the User, is installed to alleviate an overload
on, and as an alternative to, the reinforcement of a third party system,
such as the Distribution System of a Public Distribution System
Operator.

Category 4 Intertripping A System to Generator Operational Intertripping Scheme installed to


Scheme enable the disconnection of the Connection Site from the National
Electricity Transmission System in a controlled and efficient manner in
order to facilitate the timely restoration of the National Electricity
Transmission System.

CENELEC European Committee for Electrotechnical Standardisation.

CfD Counterparty A person designated as a CfD counterparty under section 7(1) of the
Energy Act 2013.

CfD Documents The AF Rules, The Contracts for Difference (Allocation) Regulations
2014, The Contracts for Difference (Definition of Eligible Generator)
Regulations 2014 and The Contracts for Difference (Electricity Supplier
Obligations) Regulations 2014 and any other regulations made under
Chapter 2 of Part 2 of the Energy Act 2013 which are in force from time
to time.

CfD Settlement Services means any person:


Provider
(i) appointed for the time being and from time to time by a CfD
Counterparty; or
(ii) who is designated by virtue of Section C1.2.1B of the
Balancing and Settlement Code,

in either case to carry out any of the CFD settlement activities (or any
successor entity performing CFD settlement activities).

CCGT Module Matrix The matrix described in Appendix 1 to BC1 under the heading CCGT
Module Matrix.

Issue 5 Revision 19 GD 30 September 2016


5 of 49
CCGT Module Planning A matrix in the form set out in Appendix 3 of OC2 showing the
Matrix combination of CCGT Units within a CCGT Module which would be
running in relation to any given MW output.

CM Administrative The Secretary of State, the CM Settlement Body, and any CM


Parties Settlement Services Provider.

CM Settlement Body the Electricity Settlements Company Ltd or such other person as may
from time to time be appointed as Settlement Body under regulation 80 of
the Electricity Capacity Regulations 2014.

CM Settlement Services any person with whom the CM Settlement Body has entered into a
Provider contract to provide services to it in relation to the performance of its
functions under the Capacity Market Documents.

Code Administration Means the code of practice approved by the Authority and:
Code of Practice
(a) developed and maintained by the code administrators in existence
from time to time; and
(b) amended subject to the Authoritys approval from time to time;
and
(c) re-published from time to time;

Means NGET carrying out the role of Code Administrator in accordance


Code Administrator with the General Conditions.

Combined Cycle Gas A collection of Generating Units (registered as a CCGT Module under
Turbine Module or the PC) comprising one or more Gas Turbine Units (or other gas based
CCGT Module engine units) and one or more Steam Units where, in normal operation,
the waste heat from the Gas Turbines is passed to the water/steam
system of the associated Steam Unit or Steam Units and where the
component units within the CCGT Module are directly connected by
steam or hot gas lines which enable those units to contribute to the
efficiency of the combined cycle operation of the CCGT Module.

Combined Cycle Gas A Generating Unit within a CCGT Module.


Turbine Unit or CCGT
Unit

Commercial Ancillary Ancillary Services, other than System Ancillary Services, utilised by
Services NGET in operating the Total System if a User (or other person) has
agreed to provide them under an Ancillary Services Agreement or
under a Bilateral Agreement with payment being dealt with under an
Ancillary Services Agreement or in the case of Externally
Interconnected System Operators or Interconnector Users, under
any other agreement (and in the case of Externally Interconnected
System Operators and Interconnector Users includes ancillary
services equivalent to or similar to System Ancillary Services).

Commercial Boundary Has the meaning set out in the CUSC

Committed Project Data relating to a User Development once the offer for a CUSC
Planning Data Contract is accepted.

Common Collection A busbar within a Power Park Module to which the higher voltage side
Busbar of two or more Power Park Unit generator transformers are connected.

Issue 5 Revision 19 GD 30 September 2016


6 of 49
Completion Date Has the meaning set out in the Bilateral Agreement with each User to
that term or in the absence of that term to such other term reflecting the
date when a User is expected to connect to or start using the National
Electricity Transmission System. In the case of an Embedded
Medium Power Station or Embedded DC Converter Station having a
similar meaning in relation to the Network Operators System as set out
in the Embedded Development Agreement.

Complex A Connection Site together with the associated Power Station and/or
Network Operator substation and/or associated Plant and/or
Apparatus, as appropriate.

Compliance Processes That portion of the Grid Code which is identified as the Compliance
or CP Processes.

Compliance Statement A statement completed by the relevant User confirming compliance with
each of the relevant Grid Code provisions, and the supporting evidence
in respect of such compliance, of its:
Generating Unit(s); or,
CCGT Module(s); or,
Power Park Module(s); or,
DC Converter(s)
in the form provided by NGET to the relevant User or another format as
agreed between the User and NGET.

Connection Conditions That portion of the Grid Code which is identified as the Connection
or CC Conditions.

Connection Entry Has the meaning set out in the CUSC


Capacity

Connected Planning Data which replaces data containing estimated values assumed for
Data planning purposes by validated actual values and updated estimates for
the future and by updated forecasts for Forecast Data items such as
Demand.

Connection Point A Grid Supply Point or Grid Entry Point, as the case may be.

Connection Site A Transmission Site or User Site, as the case may be.

Construction Has the meaning set out in the CUSC


Agreement

Contingency Reserve The margin of generation over forecast Demand which is required in the
period from 24 hours ahead down to real time to cover against
uncertainties in Large Power Station availability and against both
weather forecast and Demand forecast errors.

Control Calls A telephone call whose destination and/or origin is a key on the control
desk telephone keyboard at a Transmission Control Centre and which,
for the purpose of Control Telephony, has the right to exercise priority
over (ie. disconnect) a call of a lower status.

Control Centre A location used for the purpose of control and operation of the National
Electricity Transmission System or DC Converter Station owner's
System or a User System other than a Generator's System or an
External System.
Issue 5 Revision 19 GD 30 September 2016
7 of 49
Control Engineer A person nominated by the relevant party for the control of its Plant and
Apparatus.

Control Person The term used as an alternative to "Safety Co-ordinator" on the Site
Responsibility Schedule only.

Control Phase The Control Phase follows on from the Programming Phase and
covers the period down to real time.

Control Point The point from which:-


(a) A Non-Embedded Customer's Plant and Apparatus is
controlled; or
(b) A BM Unit at a Large Power Station or at a Medium Power
Station or representing a Cascade Hydro Scheme or with a
Demand Capacity with a magnitude of:
(i) 50MW or more in NGETs Transmission Area; or
(ii) 30MW or more in SPTs Transmission Area; or
(iii) 10MW or more in SHETLs Transmission Area,
(iv) 10MW or more which is connected to an Offshore
Transmission System
is physically controlled by a BM Participant; or
(c) In the case of any other BM Unit or Generating Unit, data
submission is co-ordinated for a BM Participant and instructions
are received from NGET,
as the case may be. For a Generator this will normally be at a Power
Station but may be at an alternative location agreed with NGET. In the
case of a DC Converter Station, the Control Point will be at a location
agreed with NGET. In the case of a BM Unit of an Interconnector User,
the Control Point will be the Control Centre of the relevant Externally
Interconnected System Operator.

Control Telephony The principal method by which a User's Responsible


Engineer/Operator and NGET Control Engineer(s) speak to one
another for the purposes of control of the Total System in both normal
and emergency operating conditions.

CUSC Has the meaning set out in NGETs Transmission Licence

CUSC Contract One or more of the following agreements as envisaged in Standard


Condition C1 of NGETs Transmission Licence:
(a) the CUSC Framework Agreement;
(b) a Bilateral Agreement;
(c) a Construction Agreement
or a variation to an existing Bilateral Agreement and/or Construction
Agreement;

CUSC Framework Has the meaning set out in NGETs Transmission Licence
Agreement

Customer A person to whom electrical power is provided (whether or not he is the


same person as the person who provides the electrical power).

Issue 5 Revision 19 GD 30 September 2016


8 of 49
Customer Demand Reducing the supply of electricity to a Customer or disconnecting a
Management Customer in a manner agreed for commercial purposes between a
Supplier and its Customer.

Customer Demand The level above which a Supplier has to notify NGET of its proposed or
Management achieved use of Customer Demand Management which is 12 MW in
Notification Level England and Wales and 5 MW in Scotland.

Customer Generating A Power Station or Generating Unit of a Customer to the extent that it
Plant operates the same exclusively to supply all or part of its own electricity
requirements, and does not export electrical power to any part of the
Total System.

Data Registration Code That portion of the Grid Code which is identified as the Data
or DRC Registration Code.

Data Validation, The rules relating to validity and consistency of data, and default data to
Consistency and be applied, in relation to data submitted under the Balancing Codes, to
Defaulting Rules be applied by NGET under the Grid Code as set out in the document
th
Data Validation, Consistency and Defaulting Rules - Issue 8, dated 25
January 2012. The document is available on the National Grid website or
upon request from NGET.

DC Converter Any Onshore DC Converter or Offshore DC Converter.

DC Converter Station An installation comprising one or more Onshore DC Converters


connecting a direct current interconnector:
to the NGET Transmission System; or,
(if the installation has a rating of 50MW or more) to a User System,
and it shall form part of the External Interconnection to which it relates.

DC Network All items of Plant and Apparatus connected together on the direct
current side of a DC Converter.

DCUSA The Distribution Connection and Use of System Agreement approved by


the Authority and required to be maintained in force by each Electricity
Distribution Licence holder.

De-Load The condition in which a Genset has reduced or is not delivering


electrical power to the System to which it is Synchronised.

Demand The demand of MW and Mvar of electricity (i.e. both Active and
Reactive Power), unless otherwise stated.

Demand Capacity Has the meaning as set out in the BSC.

Demand Control Any or all of the following methods of achieving a Demand reduction:
(a) Customer voltage reduction initiated by Network Operators
(other than following an instruction from NGET);
(b) Customer Demand reduction by Disconnection initiated by
Network Operators (other than following an instruction from
NGET);
(c) Demand reduction instructed by NGET;
(d) automatic low Frequency Demand Disconnection;
(e) emergency manual Demand Disconnection.

Issue 5 Revision 19 GD 30 September 2016


9 of 49
Demand Control The level above which a Network Operator has to notify NGET of its
Notification Level proposed or achieved use of Demand Control which is 12 MW in
England and Wales and 5 MW in Scotland.

Designed Minimum The output (in whole MW) below which a Genset or a DC Converter at a
Operating Level DC Converter Station (in any of its operating configurations) has no
High Frequency Response capability.

De-Synchronise (a) The act of taking a Generating Unit, Power Park Module or DC
Converter off a System to which it has been Synchronised, by
opening any connecting circuit breaker; or
(b) The act of ceasing to consume electricity at an importing BM Unit;
and the term "De-Synchronising" shall be construed accordingly.

De-synchronised Has the meaning set out in OC9.5.1(a)


Island(s)

Detailed Planning Data Detailed additional data which NGET requires under the PC in support of
Standard Planning Data, comprising DPD I and DPD II

Detailed Planning Data The Detailed Planning Data categorised as such in the DRC, and
Category I or DPD I submitted in accordance with PC.4.4.2 or PC.4.4.4 as applicable.

Detailed Planning Data The Detailed Planning Data categorised as such in the DRC, and
Category II or DPD II submitted in accordance with PC.4.4.2 or PC.4.4.4 as applicable.

Discrimination The quality where a relay or protective system is enabled to pick out and
cause to be disconnected only the faulty Apparatus.

Disconnection The physical separation of Users (or Customers) from the National
Electricity Transmission System or a User System as the case may
be.

Disputes Resolution The procedure described in the CUSC relating to disputes resolution.
Procedure

Distribution Code The distribution code required to be drawn up by each Electricity


Distribution Licence holder and approved by the Authority, as from
time to time revised with the approval of the Authority.

Droop The ratio of the per unit steady state change in speed, or in Frequency
to the per unit steady state change in power output.

Dynamic Parameters Those parameters listed in Appendix 1 to BC1 under the heading BM
Unit Data Dynamic Parameters.

E&W Offshore An Offshore Transmission System with an Interface Point in England


Transmission System and Wales.

E&W Offshore A person who owns or operates an E&W Offshore Transmission


Transmission Licensee System pursuant to a Transmission Licence.

E&W Transmission Collectively NGETs Transmission System and any E&W Offshore
System Transmission Systems.

Issue 5 Revision 19 GD 30 September 2016


10 of 49
E&W User A User in England and Wales or any Offshore User who owns or
operates Plant and/or Apparatus connected (or which will at the OTSUA
Transfer Time be connected) to an E&W Offshore Transmission
System.

Earth Fault Factor At a selected location of a three-phase System (generally the point of
installation of equipment) and for a given System configuration, the ratio
of the highest root mean square phase-to-earth power Frequency
voltage on a sound phase during a fault to earth (affecting one or more
phases at any point) to the root mean square phase-to-earth power
Frequency voltage which would be obtained at the selected location
without the fault.

Earthing A way of providing a connection between conductors and earth by an


Earthing Device which is either:
(a) Immobilised and Locked in the earthing position. Where the
Earthing Device is Locked with a Safety Key, the Safety Key
must be secured in a Key Safe and the Key Safe Key must be,
where reasonably practicable, given to the authorised site
representative of the Requesting Safety Co-ordinator and is to
be retained in safe custody. Where not reasonably practicable the
Key Safe Key must be retained by the authorised site
representative of the Implementing Safety Co-ordinator in safe
custody; or
(b) maintained and/or secured in position by such other method which
must be in accordance with the Local Safety Instructions of
NGET or the Safety Rules of the Relevant Transmission
Licensee or that User, as the case may be.

Earthing Device A means of providing a connection between a conductor and earth being
of adequate strength and capability.

Electrical Standard A standard listed in the Annex to the General Conditions.

Electricity Council That body set up under the Electricity Act, 1957.

Electricity Distribution The licence granted pursuant to Section 6(1) (c) of the Act.
Licence

Electricity Supply The unincorporated members' club of that name formed inter alia to
Industry Arbitration promote the efficient and economic operation of the procedure for the
Association resolution of disputes within the electricity supply industry by means of
arbitration or otherwise in accordance with its arbitration rules.

Electricity Supply The licence granted pursuant to Section 6(1) (d) of the Act.
Licence

Electromagnetic Has the meaning set out in Engineering Recommendation G5/4.


Compatibility Level

Embedded Having a direct connection to a User System or the System of any other
User to which Customers and/or Power Stations are connected, such
connection being either a direct connection or a connection via a busbar
of another User or of a Transmission Licensee (but with no other
connection to the National Electricity Transmission System).

Embedded Development Has the meaning set out in PC.4.4.3(a)

Issue 5 Revision 19 GD 30 September 2016


11 of 49
Embedded Development An agreement entered into between a Network Operator and an
Agreement Embedded Person, identifying the relevant site of connection to the
Network Operators System and setting out other site specific details in
relation to that use of the Network Operators System.

Embedded Person The party responsible for a Medium Power Station not subject to a
Bilateral Agreement or DC Converter Station not subject to a Bilateral
Agreement connected to or proposed to be connected to a Network
Operators System.

Emergency an Emergency Instruction issued by NGET to De-Synchronise a


Deenergisation Generating Unit, Power Park Module or DC Converter in
Instruction circumstances specified in the CUSC.

Emergency Instruction An instruction issued by NGET in emergency circumstances, pursuant to


BC2.9, to the Control Point of a User. In the case of such instructions
applicable to a BM Unit, it may require an action or response which is
outside the Dynamic Parameters, QPN or Other Relevant Data, and
may include an instruction to trip a Genset.

EMR Administrative Has the meaning given to administrative parties in The Electricity
Parties Capacity Regulations 2014 and each CfD Counterparty and CfD
Settlement Services Provider.

EMR Documents The Energy Act 2013, The Electricity Capacity Regulations 2014, the
Capacity Market Rules, The Contracts for Difference (Allocation)
Regulations 2014, The Contracts for Difference (Definition of Eligible
Generator) Regulations 2014, The Contracts for Difference (Electricity
Supplier Obligations) Regulations 2014, The Electricity Market Reform
(General) Regulations 2014, the AF Rules and any other regulations or
instruments made under Chapter 2 (contracts for difference), Chapter 3
(capacity market) or Chapter 4 (investment contracts) of Part 2 of the
Energy Act 2013 which are in force from time to time.

EMR Functions Has the meaning given to EMR functions in Chapter 5 of Part 2 of the
Energy Act 2013.

Engineering The documents referred to as such and issued by the Energy Networks
Recommendations Association or the former Electricity Council.

Energisation A notification (in respect of Plant and Apparatus (including OTSUA)


Operational Notification which is directly connected to the National Electricity Transmission
or EON System) from NGET to a User confirming that the User can in
accordance with the Bilateral Agreement and/or Construction
Agreement, energise such Users Plant and Apparatus (including
OTSUA) specified in such notification.

Estimated Registered Those items of Standard Planning Data and Detailed Planning Data
Data which either upon connection will become Registered Data, or which for
the purposes of the Plant and/or Apparatus concerned as at the date of
submission are Registered Data, but in each case which for the seven
succeeding Financial Years will be an estimate of what is expected.

EU Transparency Such data as Customers and Generators are required to provide under
Availability Data Articles 7.1(a) and 7.1(b) and Articles 15.1(a), 15.1(b), 15.1(c), 15.1(d) of
European Commission Regulation (EU) No. 543/2013 respectively
(known as the Transparency Regulation), and which also forms part of
DRC Schedule 6 (Users Outage Data).

Issue 5 Revision 19 GD 30 September 2016


12 of 49
European Specification A common technical specification, a British Standard implementing a
European standard or a European technical approval. The terms
"common technical specification", "European standard" and "European
technical approval" shall have the meanings respectively ascribed to
them in the Regulations.

Event An unscheduled or unplanned (although it may be anticipated)


occurrence on, or relating to, a System (including Embedded Power
Stations) including, without limiting that general description, faults,
incidents and breakdowns and adverse weather conditions being
experienced.

Exciter The source of the electrical power providing the field current of a
synchronous machine.

Excitation System The equipment providing the field current of a machine, including all
regulating and control elements, as well as field discharge or suppression
equipment and protective devices.

Excitation System No- The minimum value of direct voltage that the Excitation System is able
Load Negative Ceiling to provide from its terminals when it is not loaded, which may be zero or
Voltage a negative value.

Excitation System Shall have the meaning ascribed to that term in IEC 34-16-1:1991
Nominal Response [equivalent to British Standard BS4999 Section 116.1 : 1992]. The time
interval applicable is the first half-second of excitation system voltage
response.

Excitation System On- Shall have the meaning ascribed to the term 'Excitation system on load
Load Positive Ceiling ceiling voltage' in IEC 34-16-1:1991[equivalent to British Standard
Voltage BS4999 Section 116.1 : 1992].

Excitation System No- Shall have the meaning ascribed to the term 'Excitation system no load
Load Positive Ceiling ceiling voltage' in IEC 34-16-1:1991[equivalent to British Standard
Voltage BS4999 Section 116.1 : 1992].

Exemptable Has the meaning set out in the CUSC.

Existing AGR Plant The following nuclear advanced gas cooled reactor plant (which was
commissioned and connected to the Total System at the Transfer
Date):-
(a) Dungeness B
(b) Hinkley Point B
(c) Heysham 1
(d) Heysham 2
(e) Hartlepool
(f) Hunterston B
(g) Torness

Issue 5 Revision 19 GD 30 September 2016


13 of 49
Existing AGR Plant In respect of each Genset within each Existing AGR Plant which has a
Flexibility Limit safety case enabling it to so operate, 8 (or such lower number which
when added to the number of instances of reduction of output as
instructed by NGET in relation to operation in Frequency Sensitive
Mode totals 8) instances of flexibility in any calendar year (or such lower
or greater number as may be agreed by the Nuclear Installations
Inspectorate and notified to NGET) for the purpose of assisting in the
period of low System NRAPM and/or low Localised NRAPM provided
that in relation to each Generating Unit each change in output shall not
be required to be to a level where the output of the reactor is less than
80% of the reactor thermal power limit (as notified to NGET and which
corresponds to the limit of reactor thermal power as contained in the
"Operating Rules" or "Identified Operating Instructions" forming part of
the safety case agreed with the Nuclear Installations Inspectorate).

Existing Gas Cooled Both Existing Magnox Reactor Plant and Existing AGR Plant.
Reactor Plant

Existing Magnox The following nuclear gas cooled reactor plant (which was commissioned
Reactor Plant and connected to the Total System at the Transfer Date):-
(a) Calder Hall
(b) Chapelcross
(c) Dungeness A
(d) Hinkley Point A
(e) Oldbury-on-Severn
(f) Bradwell
(g) Sizewell A
(h) Wylfa

Export and Import Those parameters listed in Appendix 1 to BC1 under the heading BM
Limits Unit Data Export and Import Limits.

External Apparatus for the transmission of electricity to or from the National


Interconnection Electricity Transmission System or a User System into or out of an
External System. For the avoidance of doubt, a single External
Interconnection may comprise several circuits operating in parallel.

External Plant or Apparatus which comprises a circuit and which operates in


Interconnection Circuit parallel with another circuit and which forms part of the External
Interconnection.

Externally A person who operates an External System which is connected to the


Interconnected System National Electricity Transmission System or a User System by an
Operator or EISO External Interconnection.

External System In relation to an Externally Interconnected System Operator means


the transmission or distribution system which it owns or operates which is
located outside the National Electricity Transmission System
Operator Area any Apparatus or Plant which connects that system to
the External Interconnection and which is owned or operated by such
Externally Interconnected System Operator.

Fault Current The time interval from fault inception until the end of the break time of the
Interruption Time circuit breaker (as declared by the manufacturers).

Issue 5 Revision 19 GD 30 September 2016


14 of 49
Fast Start A start by a Genset with a Fast Start Capability.

Fast Start Capability The ability of a Genset to be Synchronised and Loaded up to full Load
within 5 minutes.

Final Generation Outage An outage programme as agreed by NGET with each Generator and
Programme each Interconnector Owner at various stages through the Operational
Planning Phase and Programming Phase which does not commit the
parties to abide by it, but which at various stages will be used as the
basis on which National Electricity Transmission System outages will
be planned.

Final Operational A notification from NGET to a Generator or DC Converter Station


Notification or FON owner confirming that the User has demonstrated compliance:
(a) with the Grid Code, (or where they apply, that relevant derogations
have been granted), and
(b) where applicable, with Appendices F1 to F5 of the Bilateral
Agreement,
in each case in respect of the Plant and Apparatus specified in such
notification.

Final Physical Has the meaning set out in the BSC.


Notification Data

Final Report A report prepared by the Test Proposer at the conclusion of a System
Test for submission to NGET (if it did not propose the System Test) and
other members of the Test Panel.

Financial Year Bears the meaning given in Condition A1 (Definitions and Interpretation)
of NGETs Transmission Licence.

Flicker Severity A value derived from 12 successive measurements of Flicker Severity


(Long Term) (Short Term) (over a two hour period) and a calculation of the cube root
of the mean sum of the cubes of 12 individual measurements, as further
set out in Engineering Recommendation P28 as current at the
Transfer Date.

Flicker Severity A measure of the visual severity of flicker derived from the time series
(Short Term) output of a flickermeter over a 10 minute period and as such provides an
indication of the risk of Customer complaints.

Forecast Data Those items of Standard Planning Data and Detailed Planning Data
which will always be forecast.

Frequency The number of alternating current cycles per second (expressed in Hertz)
at which a System is running.

Frequency Sensitive Each Generating Unit in an Existing AGR Plant for which the
AGR Unit Generator has notified NGET that it has a safety case agreed with the
Nuclear Installations Inspectorate enabling it to operate in Frequency
Sensitive Mode, to the extent that such unit is within its Frequency
Sensitive AGR Unit Limit. Each such Generating Unit shall be treated
as if it were operating in accordance with BC3.5.1 provided that it is
complying with its Frequency Sensitive AGR Unit Limit.

Issue 5 Revision 19 GD 30 September 2016


15 of 49
Frequency Sensitive In respect of each Frequency Sensitive AGR Unit, 8 (or such lower
AGR Unit Limit number which when added to the number of instances of flexibility for the
purposes of assisting in a period of low System or Localised NRAPM
totals 8) instances of reduction of output in any calendar year as
instructed by NGET in relation to operation in Frequency Sensitive
Mode (or such greater number as may be agreed between NGET and
the Generator), for the purpose of assisting with Frequency control,
provided the level of operation of each Frequency Sensitive AGR Unit
in Frequency Sensitive Mode shall not be outside that agreed by the
Nuclear Installations Inspectorate in the relevant safety case.

Frequency Sensitive A Genset operating mode which will result in Active Power output
Mode changing, in response to a change in System Frequency, in a direction
which assists in the recovery to Target Frequency, by operating so as to
provide Primary Response and/or Secondary Response and/or High
Frequency Response.

Fuel Security Code The document of that title designated as such by the Secretary of State,
as from time to time amended.

Gas Turbine Unit A Generating Unit driven by a gas turbine (for instance by an aero-
engine).

Gas Zone Diagram A single line diagram showing boundaries of, and interfaces between,
gas-insulated HV Apparatus modules which comprise part, or the whole,
of a substation at a Connection Site (or in the case of OTSDUW Plant
and Apparatus, Transmission Interface Site), together with the
associated stop valves and gas monitors required for the safe operation
of the National Electricity Transmission System or the User System,
as the case may be.

Gate Closure Has the meaning set out in the BSC.

GC Modification A proposal to modify the Grid Code which is not rejected pursuant to the
Proposal terms of the Grid Code and has not yet been implemented.

General Conditions or That portion of the Grid Code which is identified as the General
GC Conditions.

Generating Plant The difference between Output Usable and forecast Demand.
Demand Margin

Generating Unit An Onshore Generating Unit and/or an Offshore Generating Unit.

Generating Unit Data The Physical Notification, Export and Import Limits and Other
Relevant Data only in respect of each Generating Unit:
(a) which forms part of the BM Unit which represents that Cascade
Hydro Scheme;
(b) at an Embedded Exemptable Large Power Station, where the
relevant Bilateral Agreement specifies that compliance with BC1
and/or BC2 is required:
(i) to each Generating Unit, or
(ii) to each Power Park Module where the Power Station
comprises Power Park Modules

Generation Capacity Has the meaning set out in the BSC.

Issue 5 Revision 19 GD 30 September 2016


16 of 49
Generation Planning Those parameters listed in Appendix 2 of OC2.
Parameters

Generator A person who generates electricity under licence or exemption under the
Act acting in its capacity as a generator in Great Britain or Offshore.

Generator Performance A diagram which shows the MW and Mvar capability limits within which a
Chart Generating Unit will be expected to operate under steady state
conditions.

Genset A Generating Unit, Power Park Module or CCGT Module at a Large


Power Station or any Generating Unit, Power Park Module or CCGT
Module which is directly connected to the National Electricity
Transmission System.

Good Industry Practice The exercise of that degree of skill, diligence, prudence and foresight
which would reasonably and ordinarily be expected from a skilled and
experienced operator engaged in the same type of undertaking under the
same or similar circumstances.

Governor Deadband The total magnitude of the change in steady state speed (expressed as a
range of Hz ( x Hz) where "x" is a numerical value) within which there is
no resultant change in the position of the governing valves of the
speed/load Governing System.

Great Britain or GB The landmass of England and Wales and Scotland, including internal
waters.

Grid Code Review Panel The panel with the functions set out in GC.4.
or Panel

Grid Entry Point An Onshore Grid Entry Point or an Offshore Grid Entry Point.

Grid Supply Point A point of supply from the National Electricity Transmission System to
Network Operators or Non-Embedded Customers.

Group Those National Electricity Transmission System sub-stations bounded


solely by the faulted circuit(s) and the overloaded circuit(s) excluding any
third party connections between the Group and the rest of the National
Electricity Transmission System, the faulted circuit(s) being a Secured
Event.

Headroom The Power Available (in MW) less the actual Active Power exported
from the Power Park Module (in MW).

High Frequency An automatic reduction in Active Power output in response to an


Response increase in System Frequency above the Target Frequency (or such
other level of Frequency as may have been agreed in an Ancillary
Services Agreement). This reduction in Active Power output must be in
accordance with the provisions of the relevant Ancillary Services
Agreement which will provide that it will be released increasingly with
time over the period 0 to 10 seconds from the time of the Frequency
increase on the basis set out in the Ancillary Services Agreement and
fully achieved within 10 seconds of the time of the start of the Frequency
increase and it must be sustained at no lesser reduction thereafter. The
interpretation of the High Frequency Response to a + 0.5 Hz frequency
change is shown diagrammatically in Figure CC.A.3.3.

Issue 5 Revision 19 GD 30 September 2016


17 of 49
High Voltage or HV For E&W Transmission Systems, a voltage exceeding 650 volts. For
Scottish Transmission Systems, a voltage exceeding 1000 volts.

HV Connections Apparatus connected at the same voltage as that of the National


Electricity Transmission System, including Users' circuits, the higher
voltage windings of Users' transformers and associated connection
Apparatus.

HP Turbine Power Ratio of steady state mechanical power delivered by the HP turbine to
Fraction the total steady state mechanical power delivered by the total steam
turbine at Registered Capacity.

IEC International Electrotechnical Commission.

IEC Standard A standard approved by the International Electrotechnical Commission.

Implementing Safety The Safety Co-ordinator implementing Safety Precautions.


Co-ordinator

Import Usable That portion of Registered Import Capacity which is expected to be


available and which is not unavailable due to a Planned Outage.

Incident Centre A centre established by NGET or a User as the focal point in NGET or in
that User, as the case may be, for the communication and dissemination
of information between the senior management representatives of NGET,
or of that User, as the case may be, and the relevant other parties during
a Joint System Incident in order to avoid overloading NGET's, or that
User's, as the case may be, existing operational/control arrangements.

Independent Back-Up A Back-Up Protection system which utilises a discrete relay, different
Protection current transformers and an alternate operating principle to the Main
Protection systems(s) such that it can operate autonomously in the
event of a failure of the Main Protection.

Independent Main A Main Protection system which utilises a physically discrete relay and
Protection different current transformers to any other Main Protection.

Indicated Constraint The difference between a constraint boundary transfer limit and the
Boundary Margin difference between the sum of BM Unit Maximum Export Limits and the
forecast of local Demand within the constraint boundary.

Indicated Imbalance The difference between the sum of Physical Notifications for BM Units
comprising Generating Units or CCGT Modules and the forecast of
Demand for the whole or any part of the System.

Indicated Margin The difference between the sum of BM Unit Maximum Export Limits
submitted and the forecast of Demand for the whole or any part of the
System

Instructor Facilities A device or system which gives certain Transmission Control Centre
instructions with an audible or visible alarm, and incorporates the means
to return message acknowledgements to the Transmission Control
Centre

Integral Equipment Test A test on equipment, associated with Plant and/or Apparatus, which
or IET takes place when that Plant and/or Apparatus forms part of a
Synchronised System and which, in the reasonable judgement of the
person wishing to perform the test, may cause an Operational Effect.

Issue 5 Revision 19 GD 30 September 2016


18 of 49
Interconnection An agreement made between NGET and an Externally Interconnected
Agreement System Operator and/or an Interconnector User and/or other relevant
persons for the External Interconnection relating to an External
Interconnection and/or an agreement under which an Interconnector
User can use an External Interconnection.

Interconnector Export In relation to an External Interconnection means the (daily or weekly)


Capacity forecast value (in MW) at the time of the (daily or weekly) peak demand,
of the maximum level at which the External Interconnection can export
to the Grid Entry Point.

Interconnector Import In relation to an External Interconnection means the (daily or weekly)


Capacity forecast value (in MW) at the time of the (daily or weekly) peak demand
of the maximum level at which the External Interconnection can import
from the Grid Entry Point.

Interconnector Owner Has the meaning given to the term in the Connection and Use of
System Code.

Interconnector User Has the meaning set out in the BSC.

Interface Agreement Has the meaning set out in the CUSC.

Interface Point As the context admits or requires either;


(a) the electrical point of connection between an Offshore
Transmission System and an Onshore Transmission System,
or
(b) the electrical point of connection between an Offshore
Transmission System and a Network Operators User System.

Interface Point Capacity The maximum amount of Active Power transferable at the Interface
Point as declared by a User under the OTSDUW Arrangements
expressed in whole MW.

Interface Point Target The nominal target voltage/power factor at an Interface Point which a
Voltage/Power factor Network Operator requires NGET to achieve by operation of the
relevant Offshore Transmission System.

Interim Operational A notification from NGET to a Generator or DC Converter Station


Notification or ION owner acknowledging that the User has demonstrated compliance,
except for the Unresolved Issues;
(a) with the Grid Code, and
(b) where applicable, with Appendices F1 to F5 of the Bilateral
Agreement,
in each case in respect of the Plant and Apparatus (including OTSUA)
specified in such notification and provided that in the case of the
OTSDUW Arrangements such notification shall be provided to a
Generator in two parts dealing with the OTSUA and Generators Plant
and Apparatus (called respectively Interim Operational Notification
Part A or ION A and Interim Operational Notification Part B or
ION B) as provided for in the CP.

Intermittent Power The primary source of power for a Generating Unit that can not be
Source considered as controllable, e.g. wind, wave or solar.

Issue 5 Revision 19 GD 30 September 2016


19 of 49
Intertripping (a) The tripping of circuit-breaker(s) by commands initiated from
Protection at a remote location independent of the state of the
local Protection; or
(b) Operational Intertripping.

Intertrip Apparatus Apparatus which performs Intertripping.

IP Turbine Power Ratio of steady state mechanical power delivered by the IP turbine to the
Fraction total steady state mechanical power delivered by the total steam turbine
at Registered Capacity.

Isolating Device A device for achieving Isolation.

Isolation The disconnection of HV Apparatus (as defined in OC8A.1.6.2 and


OC8B.1.7.2) from the remainder of the System in which that HV
Apparatus is situated by either of the following:
(a) an Isolating Device maintained in an isolating position. The
isolating position must either be:
(i) maintained by immobilising and Locking the Isolating
Device in the isolating position and affixing a Caution
Notice to it. Where the Isolating Device is Locked with a
Safety Key, the Safety Key must be secured in a Key Safe
and the Key Safe Key must be, where reasonably
practicable, given to the authorised site representative of the
Requesting Safety Co-Ordinator and is to be retained in
safe custody. Where not reasonably practicable the Key
Safe Key must be retained by the authorised site
representative of the Implementing Safety Co-ordinator in
safe custody; or
(ii) maintained and/or secured by such other method which
must be in accordance with the Local Safety Instructions
of NGET or the Safety Rules of the Relevant
Transmission Licensee or that User, as the case may be;
or
(b) an adequate physical separation which must be in accordance with
and maintained by the method set out in the Local Safety
Instructions of NGET or the Safety Rules of the Relevant
Transmission Licensee or that User, as the case may be.

Joint BM Unit Data Has the meaning set out in the BSC.

Joint System Incident An Event wherever occurring (other than on an Embedded Medium
Power Station or an Embedded Small Power Station) which, in the
opinion of NGET or a User, has or may have a serious and/or
widespread effect, in the case of an Event on a User(s) System(s)
(other than on an Embedded Medium Power Station or Embedded
Small Power Station), on the National Electricity Transmission
System, and in the case of an Event on the National Electricity
Transmission System, on a User(s) System(s) (other than on an
Embedded Medium Power Station or Embedded Small Power
Station).

Key Safe A device for the secure retention of keys.

Key Safe Key A key unique at a Location capable of operating a lock, other than a
control lock, on a Key Safe.

Issue 5 Revision 19 GD 30 September 2016


20 of 49
Large Power Station A Power Station which is
(a) directly connected to:
(i) NGETs Transmission System where such Power Station
has a Registered Capacity of 100MW or more; or
(ii) SPTs Transmission System where such Power Station
has a Registered Capacity of 30MW or more; or
(iii) SHETLs Transmission System where such Power
Station has a Registered Capacity of 10MW or more; or
(iv) an Offshore Transmission System where such Power
Station has a Registered Capacity of 10MW or more;
or,
(b) Embedded within a User System (or part thereof) where such
User System (or part thereof) is connected under normal
operating conditions to:
(i) NGETs Transmission System and such Power Station
has a Registered Capacity of 100MW or more; or
(ii) SPTs Transmission System and such Power Station has
a Registered Capacity of 30MW or more; or
(iii) SHETLs Transmission System and such Power Station
has a Registered Capacity of 10MW or more;
or,
(c) Embedded within a User System (or part thereof) where the User
System (or part thereof) is not connected to the National
Electricity Transmission System, although such Power Station
is in:
(i) NGETs Transmission Area where such Power Station
has a Registered Capacity of 100MW or more; or
(ii) SPTs Transmission Area where such Power Station has
a Registered Capacity of 30MW or more; or
(iii) SHETLs Transmission Area where such Power Station
has a Registered Capacity of 10MW or more;

Licence Any licence granted to NGET or a Relevant Transmission Licensee or


a User, under Section 6 of the Act.

Licence Standards Those standards set out or referred to in Condition C17 of NGETs
Transmission Licence and/or Condition D3 and/or Condition E16 of a
Relevant Transmission Licensees Transmission Licence.

Limited Frequency A mode whereby the operation of the Genset (or DC Converter at a DC
Sensitive Mode Converter Station exporting Active Power to the Total System) is
Frequency insensitive except when the System Frequency exceeds
50.4Hz, from which point Limited High Frequency Response must be
provided.

Limited High Frequency A response of a Genset (or DC Converter at a DC Converter Station


Response exporting Active Power to the Total System) to an increase in System
Frequency above 50.4Hz leading to a reduction in Active Power in
accordance with the provisions of BC3.7.2.

Issue 5 Revision 19 GD 30 September 2016


21 of 49
Limited Operational A notification from NGET to a Generator or DC Converter Station
Notification or LON owner stating that the Users Plant and/or Apparatus specified in such
notification may be, or is, unable to comply:
(a) with the provisions of the Grid Code specified in the notice, and
(b) where applicable, with Appendices F1 to F5 of the Bilateral
Agreement ,
and specifying the Unresolved Issues.

Load The Active, Reactive or Apparent Power, as the context requires,


generated, transmitted or distributed.

Loaded Supplying electrical power to the System.

Load Factor The ratio of the actual output of a Generating Unit to the possible
maximum output of that Generating Unit.

Load Management A block of Demand controlled by a Supplier or other party through the
Block means of radio teleswitching or by some other means.

Local Joint Restoration A plan produced under OC9.4.7.12 detailing the agreed method and
Plan procedure by which a Genset at a Black Start Station (possibly with
other Gensets at that Black Start Station) will energise part of the Total
System and meet complementary blocks of local Demand so as to form
a Power Island.
In Scotland, the plan may also: cover more than one Black Start
Station; include Gensets other than those at a Black Start Station and
cover the creation of one or more Power Islands.

Local Safety For safety co-ordination in England and Wales, instructions on each User
Instructions Site and Transmission Site, approved by the relevant NGET or User's
manager, setting down the methods of achieving the objectives of
NGET's or the User's Safety Rules, as the case may be, to ensure the
safety of personnel carrying out work or testing on Plant and/or
Apparatus on which his Safety Rules apply and, in the case of a User,
any other document(s) on a User Site which contains rules with regard to
maintaining or securing the isolating position of an Isolating Device, or
maintaining a physical separation or maintaining or securing the position
of an Earthing Device.

Local Switching A procedure produced under OC7.6 detailing the agreed arrangements in
Procedure respect of carrying out of Operational Switching at Connection Sites
and parts of the National Electricity Transmission System adjacent to
those Connection Sites.

Localised Negative That margin of Active Power sufficient to allow transfers to and from a
Reserve Active Power System Constraint Group (as the case may be) to be contained within
Margin or Localised such reasonable limit as NGET may determine.
NRAPM

Location Any place at which Safety Precautions are to be applied.

Locked A condition of HV Apparatus that cannot be altered without the operation


of a locking device.

Locking The application of a locking device which enables HV Apparatus to be


Locked.

Issue 5 Revision 19 GD 30 September 2016


22 of 49
Low Frequency Relay Has the same meaning as Under Frequency Relay.

Low Voltage or LV For E&W Transmission Systems a voltage not exceeding 250 volts. For
Scottish Transmission Systems, a voltage exceeding 50 volts but not
exceeding 1000 volts.

LV Side of the Offshore Unless otherwise specified in the Bilateral Agreement, the busbar on
Platform the Offshore Platform (typically 33kV) at which the relevant Offshore
Grid Entry Point is located.

Main Protection A Protection system which has priority above other Protection in
initiating either a fault clearance or an action to terminate an abnormal
condition in a power system.

Manufacturers Data & A report submitted by a manufacturer to NGET relating to a specific


Performance Report version of a Power Park Unit demonstrating the performance
characteristics of such Power Park Unit in respect of which NGET has
evaluated its relevance for the purposes of the Compliance Processes.

Market Operation Data A computer system operated by NGET and made available for use by
Interface System Customers connected to or using the National Electricity
(MODIS) Transmission System for the purpose of submitting EU Transparency
Availability Data to NGET.

Market Suspension Has the meaning given to the term Market Suspension Threshold in
Threshold Section G of the BSC.

Material Effect An effect causing NGET or a Relevant Transmission Licensee to effect


any works or to alter the manner of operation of Transmission Plant
and/or Transmission Apparatus at the Connection Site (which term
shall, in this definition and in the definition of Modification only, have
the meaning ascribed thereto in the CUSC) or the site of connection or a
User to effect any works or to alter the manner of operation of its Plant
and/or Apparatus at the Connection Site or the site of connection which
in either case involves that party in expenditure of more than 10,000.

Maximum Export The maximum continuous Apparent Power expressed in MVA and
Capacity maximum continuous Active Power expressed in MW which can flow
from an Offshore Transmission System connected to a Network
Operator's User System, to that User System.

Maximum Generation A service utilised by NGET in accordance with the CUSC and the
Service or MGS Balancing Principles Statement in operating the Total System.

Maximum Generation An agreement between a User and NGET for the payment by NGET to
Service Agreement that User in respect of the provision by such User of a Maximum
Generation Service.

Maximum Import The maximum continuous Apparent Power expressed in MVA and
Capacity maximum continuous Active Power expressed in MW which can flow to
an Offshore Transmission System connected to a Network
Operator's User System, from that User System.

Issue 5 Revision 19 GD 30 September 2016


23 of 49
Medium Power Station A Power Station which is
(a) directly connected to NGETs Transmission System where such
Power Station has a Registered Capacity of 50MW or more but
less than 100MW;
or,
(b) Embedded within a User System (or part thereof) where such
User System (or part thereof) is connected under normal
operating conditions to NGETs Transmission System and such
Power Station has a Registered Capacity of 50MW or more but
less than 100MW;
or,
(c) Embedded within a User System (or part thereof) where the User
System (or part thereof) is not connected to the National
Electricity Transmission System, although such Power Station
is in NGETs Transmission Area and such Power Station has a
Registered Capacity of 50MW or more but less than 100MW.

Medium Voltage or MV For E&W Transmission Systems a voltage exceeding 250 volts but not
exceeding 650 volts.

Mills Milling plant which supplies pulverised fuel to the boiler of a coal fired
Power Station.

Minimum Generation The minimum output (in whole MW) which a Genset can generate or DC
Converter at a DC Converter Station can import or export to the Total
System under stable operating conditions, as registered with NGET
under the PC (and amended pursuant to the PC). For the avoidance of
doubt, the output may go below this level as a result of operation in
accordance with BC3.7.

Minimum Import The minimum input (in whole MW) into a DC Converter at a DC
Capacity Converter Station (in any of its operating configurations) at the Onshore
Grid Entry Point (or in the case of an Embedded DC Converter at the
User System Entry Point) at which a DC Converter can operate in a
stable manner, as registered with NGET under the PC (and amended
pursuant to the PC).

Modification Any actual or proposed replacement, renovation, modification, alteration


or construction by or on behalf of a User or NGET to either that Users
Plant or Apparatus or Transmission Plant or Apparatus, as the case
may be, or the manner of its operation which has or may have a Material
Effect on NGET or a User, as the case may be, at a particular
Connection Site.

Mothballed DC A DC Converter at a DC Converter Station that has previously imported


Converter at a DC or exported power which the DC Converter Station owner plans not to
Converter Station use to import or export power for the remainder of the current Financial
Year but which could be returned to service.

Mothballed Generating A Generating Unit that has previously generated which the Generator
Unit plans not to use to generate for the remainder of the current NGET
Financial Year but which could be returned to service.

Mothballed Power Park A Power Park Module that has previously generated which the
Module Generator plans not to use to generate for the remainder of the current
Financial Year but which could be returned to service.

Issue 5 Revision 19 GD 30 September 2016


24 of 49
Multiple Point of A double (or more) Point of Connection, being two (or more) Points of
Connection Connection interconnected to each other through the Users System.

National Demand The amount of electricity supplied from the Grid Supply Points plus:-
that supplied by Embedded Large Power Stations, and
National Electricity Transmission System Losses,
minus:-
the Demand taken by Station Transformers and Pumped
Storage Units
and, for the purposes of this definition, does not include:-
any exports from the National Electricity Transmission System
across External Interconnections.

National Electricity The Onshore Transmission System and, where owned by Offshore
Transmission System Transmission Licensees, Offshore Transmission Systems.

National Electricity The amount of electricity supplied from the Grid Supply Points plus:-
Transmission System
Demand that supplied by Embedded Large Power Stations, and
exports from the National Electricity Transmission System
across External Interconnections, and
National Electricity Transmission System Losses,
and, for the purposes of this definition, includes:-
the Demand taken by Station Transformers and Pumped
Storage Units.

National Electricity The losses of electricity incurred on the National Electricity


Transmission System Transmission System.
Losses

National Electricity Has the meaning set out in Schedule 1 of NGET's Transmission
Transmission System Licence.
Operator Area

National Electricity A computer file produced by NGET which in NGETs view provides an
Transmission System appropriate representation of the National Electricity Transmission
Study Network Data File System for a specific point in time. The computer file will contain
information and data on Demand on the National Electricity
Transmission System and on Large Power Stations including Genset
power output consistent with Output Usable and NGETs view of
prevailing system conditions.

National Electricity A warning issued by NGET to Users (or to certain Users only) in
Transmission System accordance with OC7.4.8.2, which provides information relating to
Warning System conditions or Events and is intended to :
(a) alert Users to possible or actual Plant shortage, System problems
and/or Demand reductions;
(b) inform of the applicable period;
(c) indicate intended consequences for Users; and
(d) enable specified Users to be in a state of readiness to receive
instructions from NGET.

Issue 5 Revision 19 GD 30 September 2016


25 of 49
National Electricity A warning issued by NGET, in accordance with OC7.4.8.7, which is
Transmission System intended to provide short term notice, where possible, to those Users
Warning - Demand who are likely to receive Demand reduction instructions from NGET
Control Imminent within 30 minutes.

National Electricity A warning issued by NGET, in accordance with OC7.4.8.6, which is


Transmission System intended to alert recipients that there is a high risk of Demand reduction
Warning - High Risk of being implemented and which may normally result from an Electricity
Demand Reduction Margin Notice.

National Electricity A warning issued by NGET, in accordance with OC7.4.8.5, which is


Transmission System intended to invite a response from and to alert recipients to a decreased
Warning - Electricity System Margin.
Margin Notice

National Electricity A warning issued by NGET, in accordance with OC7.4.8.8, which is


Transmission System intended to alert Users of the risk of widespread and serious System
Warning - Risk of disturbance which may affect Users.
System Disturbance

Network Data The data to be provided by NGET to Users in accordance with the PC,
as listed in Part 3 of the Appendix to the PC.

Network Operator A person with a User System directly connected to the National
Electricity Transmission System to which Customers and/or Power
Stations (not forming part of the User System) are connected, acting in
its capacity as an operator of the User System, but shall not include a
person acting in the capacity of an Externally Interconnected System
Operator or a Generator in respect of OTSUA.

NGET National Grid Electricity Transmission plc (NO: 2366977) whose


registered office is at 1-3 Strand, London, WC2N 5EH.

NGET Control Engineer The nominated person employed by NGET to direct the operation of the
National Electricity Transmission System or such person as
nominated by NGET.

NGET Operational NGET's operational procedures which form the guidelines for operation
Strategy of the National Electricity Transmission System.

No-Load Field Voltage Shall have the meaning ascribed to that term in IEC 34-16-1:1991
[equivalent to British Standard BS4999 Section 116.1 : 1992].

No System Connection As defined in OC8A.1.6.2 and OC8B.1.7.2

Notification of Users A notification from a Generator or DC Converter Station owner to


Intention to NGET informing NGET of the date upon which any OTSUA, a
Synchronise Generating Unit(s), CCGT Module(s), Power Park Module(s) or DC
Converter(s) will be ready to be Synchronised to the Total System.

Non-Embedded A Customer in Great Britain, except for a Network Operator acting in


Customer its capacity as such, receiving electricity direct from the Onshore
Transmission System irrespective of from whom it is supplied.

Non-Synchronous An Onshore Non-Synchronous Generating Unit or Offshore Non-


Generating Unit Synchronous Generating Unit.

Normal CCGT Module A CCGT Module other than a Range CCGT Module.

Novel Unit A tidal, wave, wind, geothermal, or any similar, Generating Unit.
Issue 5 Revision 19 GD 30 September 2016
26 of 49
OC9 De-synchronised Has the meaning set out in OC9.5.4.
Island Procedure

Offshore Means wholly or partly in Offshore Waters, and when used in


conjunction with another term and not defined means that the associated
term is to be read accordingly.

Offshore DC Converter Any User Apparatus located Offshore used to convert alternating
current electricity to direct current electricity, or vice versa. An Offshore
DC Converter is a standalone operative configuration at a single site
comprising one or more converter bridges, together with one or more
converter transformers, converter control equipment, essential protective
and switching devices and auxiliaries, if any, used for conversion.

Offshore Development A statement prepared by NGET in accordance with Special Condition C4


Information Statement of NGETs Transmission Licence.

Offshore Generating Unless otherwise provided in the Grid Code, any Apparatus located
Unit Offshore which produces electricity, including, an Offshore
Synchronous Generating Unit and Offshore Non-Synchronous
Generating Unit.

Offshore Grid Entry In the case of:-


Point
(a) an Offshore Generating Unit or an Offshore DC Converter, as
the case may be, which is directly connected to an Offshore
Transmission System, the point at which it connects to that
Offshore Transmission System, or;
(b) an Offshore Power Park Module which is directly connected to
an Offshore Transmission System, the point where one Power
Park String (registered by itself as a Power Park Module) or the
collection of points where a number of Offshore Power Park
Strings (registered as a single Power Park Module) connects to
that Offshore Transmission System, or;
(c) an External Interconnection which is directly connected to an
Offshore Transmission System, the point at which it connects to
that Offshore Transmission System.

Offshore Non- An Offshore Generating Unit that is not an Offshore Synchronous


Synchronous Generating Unit including for the avoidance of doubt a Power Park Unit
Generating Unit located Offshore.

Offshore Platform A single structure comprising of Plant and Apparatus located Offshore
which includes one or more Offshore Grid Entry Points.

Offshore Power Park A collection of one or more Offshore Power Park Strings (registered as
Module a Power Park Module under the PC). There is no limit to the number of
Power Park Strings within the Power Park Module, so long as they
either:
(a) connect to the same busbar which cannot be electrically split; or
(b) connect to a collection of directly electrically connected busbars of
the same nominal voltage and are configured in accordance with
the operating arrangements set out in the relevant Bilateral
Agreement.

Issue 5 Revision 19 GD 30 September 2016


27 of 49
Offshore Power Park A collection of Offshore Generating Units that are powered by an
String Intermittent Power Source, joined together by cables forming part of a
User System with a single point of connection to an Offshore
Transmission System. The connection to an Offshore Transmission
System may include a DC Converter.

Offshore Synchronous An Offshore Generating Unit in which, under all steady state conditions,
Generating Unit the rotor rotates at a mechanical speed equal to the electrical frequency
of the National Electricity Transmission System divided by the number
of pole pairs of the Generating Unit.

Offshore Tender The process followed by the Authority to make, in prescribed cases, a
Process determination on a competitive basis of the person to whom an offshore
transmission licence is to be granted.

Offshore Transmission An agreement entered into by NGET and a Network Operator in respect
Distribution Connection of the connection to and use of a Network Operators User System by
Agreement an Offshore Transmission System.

Offshore Transmission Such person in relation to whose Transmission Licence the standard
Licensee conditions in Section E (offshore transmission owner standard conditions)
of such Transmission Licence have been given effect, or any person in
that prospective role who has acceded to the STC.

Offshore Transmission A system consisting (wholly or mainly) of high voltage electric lines and
System used for the transmission of electricity from one Power Station to a sub-
station or to another Power Station or between sub-stations, and
includes any Plant and Apparatus (including OTSUA) and meters in
connection with the transmission of electricity but does not include any
Remote Transmission Assets. An Offshore Transmission System
extends from the Interface Point, or the Offshore Grid Entry Point(s)
and may include Plant and Apparatus located Onshore and Offshore
and, where the context permits, references to the Offshore
Transmission System includes OTSUA.

Offshore Waters Has the meaning given to offshore waters in Section 90(9) of the
Energy Act 2004.

Offshore Works In relation to a particular User means those assumptions set out in
Assumptions Appendix P of the relevant Construction Agreement as amended from
time to time.

Onshore Means within Great Britain, and when used in conjunction with another
term and not defined means that the associated term is to be read
accordingly.
st
Onshore DC Converter Any User Apparatus located Onshore with a Completion Date after 1
April 2005 used to convert alternating current electricity to direct current
electricity, or vice versa. An Onshore DC Converter is a standalone
operative configuration at a single site comprising one or more converter
bridges, together with one or more converter transformers, converter
control equipment, essential protective and switching devices and
auxiliaries, if any, used for conversion. In a bipolar arrangement, an
Onshore DC Converter represents the bipolar configuration.

Onshore Generating Unless otherwise provided in the Grid Code, any Apparatus located
Unit Onshore which produces electricity, including, an Onshore
Synchronous Generating Unit and Onshore Non-Synchronous
Generating Unit.
Issue 5 Revision 19 GD 30 September 2016
28 of 49
Onshore Grid Entry A point at which a Onshore Generating Unit or a CCGT Module or a
Point CCGT Unit or a Onshore DC Converter or a Onshore Power Park
Module or an External Interconnection, as the case may be, which is
directly connected to the Onshore Transmission System connects to
the Onshore Transmission System.

Onshore Non- A Generating Unit located Onshore that is not a Synchronous


Synchronous Generating Unit including for the avoidance of doubt a Power Park Unit
Generating Unit located Onshore.

Onshore Power Park A collection of Non-Sychronous Generating Units (registered as a


Module Power Park Module under the PC) that are powered by an Intermittent
Power Source, joined together by a System with a single electrical point
of connection directly to the Onshore Transmission System (or User
System if Embedded) with no intermediate Offshore Transmission
System connections. The connection to the Onshore Transmission
System (or User System if Embedded) may include a DC Converter.

Onshore Synchronous An Onshore Generating Unit including, for the avoidance of doubt, a
Generating Unit CCGT Unit in which, under all steady state conditions, the rotor rotates at
a mechanical speed equal to the electrical frequency of the National
Electricity Transmission System divided by the number of pole pairs of
the Generating Unit.

Onshore Transmission NGET, SPT, or SHETL.


Licensee

Onshore Transmission The system consisting (wholly or mainly) of high voltage electric lines
System owned or operated by Onshore Transmission Licensees and used for
the transmission of electricity from one Power Station to a substation or
to another Power Station or between substations or to or from Offshore
Transmission Systems or to or from any External Interconnection,
and includes any Plant and Apparatus and meters owned or operated
by any Onshore Transmission Licensee in connection with the
transmission of electricity but does not include any Remote
Transmission Assets.

On-Site Generator Site A site which is determined by the BSC Panel to be a Trading Unit under
the BSC by reason of having fulfilled the Class 1 or Class 2 requirements
as such terms are used in the BSC.

Operating Code or OC That portion of the Grid Code which is identified as the Operating Code.

Operating Margin Contingency Reserve plus Operating Reserve.

Operating Reserve The additional output from Large Power Stations or the reduction in
Demand, which must be realisable in real-time operation to respond in
order to contribute to containing and correcting any System Frequency
fall to an acceptable level in the event of a loss of generation or a loss of
import from an External Interconnection or mismatch between
generation and Demand.

Operation A scheduled or planned action relating to the operation of a System


(including an Embedded Power Station).

Operational Data Data required under the Operating Codes and/or Balancing Codes.

Operational Day The period from 0500 hours on one day to 0500 on the following day.

Issue 5 Revision 19 GD 30 September 2016


29 of 49
Operation Diagrams Diagrams which are a schematic representation of the HV Apparatus
and the connections to all external circuits at a Connection Site (and in
the case of OTSDUW, Transmission Interface Site), incorporating its
numbering, nomenclature and labelling.

Operational Effect Any effect on the operation of the relevant other System which causes
the National Electricity Transmission System or the System of the
other User or Users, as the case may be, to operate (or be at a
materially increased risk of operating) differently to the way in which they
would or may have operated in the absence of that effect.

Operational The automatic tripping of circuit-breakers to prevent abnormal system


Intertripping conditions occurring, such as over voltage, overload, System instability,
etc. after the tripping of other circuit-breakers following power System
fault(s) which includes System to Generating Unit, System to CCGT
Module, System to Power Park Module, System to DC Converter and
System to Demand intertripping schemes.

Operational Any Energisation Operational Notification, Interim Operational


Notifications Notification, Final Operational Notification or Limited Operational
Notification issued from NGET to a User.

Operational Planning Planning through various timescales the matching of generation output
with forecast National Electricity Transmission System Demand
together with a reserve of generation to provide a margin, taking into
account outages of certain Generating Units, of parts of the National
Electricity Transmission System and of parts of User Systems to
which Power Stations and/or Customers are connected, carried out to
achieve, so far as possible, the standards of security set out in NGETs
Transmission Licence, each Relevant Transmission Licensees
Transmission Licence or Electricity Distribution Licence, as the case
may be.

Operational Planning An operational planning margin set by NGET.


Margin
th
Operational Planning The period from 8 weeks to the end of the 5 year ahead of real time
Phase operation.

Operational Procedures Management instructions and procedures, both in support of the Safety
Rules and for the local and remote operation of Plant and Apparatus,
issued in connection with the actual operation of Plant and/or Apparatus
at or from a Connection Site.

Operational Switching Operation of Plant and/or Apparatus to the instruction of the relevant
Control Engineer. For the avoidance of doubt, the operation of
Transmission Plant and/or Apparatus forming part of the National
Electricity Transmission System in England and Wales, will be to the
instruction of NGET and in Scotland and Offshore will be to the
instruction of the Relevant Transmission Licensee.

Other Relevant Data The data listed in BC1.4.2(f) under the heading Other Relevant Data.

Offshore Transmission In relation to a particular User where the OTSDUW Arrangements


System Development apply, means those activities and/or works for the design, planning,
User Works or OTSDUW consenting and/or construction and installation of the Offshore
Transmission System to be undertaken by the User as identified in Part
2 of Appendix I of the relevant Construction Agreement.

Issue 5 Revision 19 GD 30 September 2016


30 of 49
OTSDUW Arrangements The arrangements whereby certain aspects of the design, consenting,
construction, installation and/or commissioning of transmission assets
are capable of being undertaken by a User prior to the transfer of those
assets to a Relevant Transmission Licensee under an Offshore
Tender Process.

OTSDUW Data and The data and information to be provided by Users undertaking
Information OTSDUW, to NGET in accordance with Appendix F of the Planning
Code.

OTSDUW DC Converter A Transmission DC Converter designed and/or constructed and/or


installed by a User under the OTSDUW Arrangements and/or operated
by the User until the OTSUA Transfer Time.

OTSDUW Development The timetable for both the delivery of OTSDUW Data and Information
and Data Timetable and OTSDUW Network Data and Information as referred to in
Appendix F of the Planning Code and the development of the scope of
the OTSDUW.

OTSDUW Network Data The data and information to be provided by NGET to Users undertaking
and Information OTSDUW in accordance with Appendix F of the Planning Code.

OTSDUW Plant and Plant and Apparatus, including any OTSDUW DC Converter, designed
Apparatus by the User under the OTSDUW Arrangements.

Offshore Transmission OTSDUW Plant and Apparatus constructed and/or installed by a User
System User Assets or under the OTSDUW Arrangements which form an Offshore
OTSUA Transmission System that once transferred to a Relevant
Transmission Licensee under an Offshore Tender Process will
become part of the National Electricity Transmission System.

OTSUA Transfer Time The time and date at which the OTSUA are transferred to a Relevant
Transmission Licensee.

Out of Synchronism The condition where a System or Generating Unit cannot meet the
requirements to enable it to be Synchronised.

Output Usable or OU The (daily or weekly) forecast value (in MW), at the time of the (daily or
weekly) peak demand, of the maximum level at which the Genset can
export to the Grid Entry Point, or in the case of Embedded Power
Stations, to the User System Entry Point. In addition, for a Genset
powered by an Intermittent Power Source the forecast value is based
upon the Intermittent Power Source being at a level which would
enable the Genset to generate at Registered Capacity.
For the purpose of OC2 only, the term Output Usable shall include the
terms Interconnector Export Capacity and Interconnector Import
Capacity where the term Output Usable is being applied to an External
Interconnection.

Over-excitation Limiter Shall have the meaning ascribed to that term in IEC 34-16-1:1991
[equivalent to British Standard BS4999 Section 116.1 : 1992].

Part 1 System Ancillary Ancillary Services which are required for System reasons and which
Services must be provided by Users in accordance with the Connection
Conditions. An exhaustive list of Part 1 System Ancillary Services is
included in that part of CC.8.1 headed Part 1.

Issue 5 Revision 19 GD 30 September 2016


31 of 49
Part 2 System Ancillary Ancillary Services which are required for System reasons and which
Services must be provided by a User if the User has agreed to provide them
under a Bilateral Agreement. A non-exhaustive list of Part 2 System
Ancillary Services is included in that part of CC.8.1 headed Part 2.

Part Load The condition of a Genset, or Cascade Hydro Scheme which is Loaded
but is not running at its Maximum Export Limit.

Permit for Work for In respect of E&W Transmission Systems, a document issued by the
proximity work Relevant E&W Transmission Licensee or an E&W User in accordance
with its respective Safety Rules to enable work to be carried out in
accordance with OC8A.8 and which provides for Safety Precautions to
be applied and maintained. An example format of a Relevant E&W
Transmission Licensees permit for work is attached as Appendix E to
OC8A.
In respect of Scottish Transmission Systems, a document issued by a
Relevant Scottish Transmission Licensee or a Scottish User in
accordance with its respective Safety Rules to enable work to be carried
out in accordance with OC8B.8 and which provides for Safety
Precautions to be applied and maintained. Example formats of Relevant
Scottish Transmission Licensees permits for work are attached as
Appendix E to OC8B.

Partial Shutdown The same as a Total Shutdown except that all generation has ceased in
a separate part of the Total System and there is no electricity supply
from External Interconnections or other parts of the Total System to
that part of the Total System and, therefore, that part of the Total
System is shutdown, with the result that it is not possible for that part of
the Total System to begin to function again without NGETs directions
relating to a Black Start.

Phase (Voltage) The ratio (in percent) between the rms values of the negative sequence
Unbalance component and the positive sequence component of the voltage.

Physical Notification Data that describes the BM Participants best estimate of the expected
input or output of Active Power of a BM Unit and/or (where relevant)
Generating Unit, the accuracy of the Physical Notification being
commensurate with Good Industry Practice.

Planning Code or PC That portion of the Grid Code which is identified as the Planning Code.

Planned Maintenance An outage of NGET electronic data communication facilities as provided


Outage for in CC.6.5.8 and NGETs associated computer facilities of which
normally at least 5 days notice is given, but in any event of which at least
twelve hours notice has been given by NGET to the User and which is
anticipated to last no longer than 2 hours. The length of such an outage
may in exceptional circumstances be extended where at least 24 hours
notice has been given by NGET to the User. It is anticipated that
normally any planned outage would only last around one hour.

Planned Outage An outage of a Large Power Station or of part of the National


Electricity Transmission System, or of part of a User System, co-
ordinated by NGET under OC2.

Plant Fixed and movable items used in the generation and/or supply and/or
transmission of electricity, other than Apparatus.

Issue 5 Revision 19 GD 30 September 2016


32 of 49
Point of Common That point on the National Electricity Transmission System electrically
Coupling nearest to the User installation at which either Demands or Loads are,
or may be, connected.

Point of Connection An electrical point of connection between the National Electricity


Transmission System and a Users System.

Point of Isolation The point on Apparatus (as defined in OC8A.1.6.2 and OC8B.1.7.2) at
which Isolation is achieved.

Post-Control Phase The period following real time operation.

Power Available A signal prepared in accordance with good industry practice,


representing the instantaneous sum of the potential Active Power
available from each individual Power Park Unit within the Power Park
Module calculated using any applicable combination of meteorological
(including wind speed), electrical or mechanical data measured at each
Power Park Unit at a specified time. Power Available shall be a value
between 0MW and Registered Capacity which is the sum of the
potential Active Power available of each Power Park Unit within the
Power Park Module. A turbine that is not generating will be considered
as not available. For the avoidance of doubt, the Power Available signal
would be the Active Power output that a Power Park Module could
reasonably be expected to export at the Grid Entry Point or User
System Entry Point taking all the above criteria into account including
Power Park Unit constraints such as optimisation modes but would
exclude a reduction in the Active Power export of the Power Park
Module instructed by NGET (for example) for the purposes selecting a
Power Park Module to operate in Frequency Sensitive Mode or when
an Emergency Instruction has been issued.

Power Factor The ratio of Active Power to Apparent Power.

Power Island Gensets at an isolated Power Station, together with complementary


local Demand. In Scotland a Power Island may include more than one
Power Station.

Power Park Module Any Onshore Power Park Module or Offshore Power Park Module.

Power Park Module The matrix described in Appendix 1 to BC1 under the heading Power
Availability Matrix Park Module Availability Matrix.

Power Park Module A matrix in the form set out in Appendix 4 of OC2 showing the
Planning Matrix combination of Power Park Units within a Power Park Module which
would be expected to be running under normal conditions.

Power Park Unit A Generating Unit within a Power Park Module.

Power Station An installation comprising one or more Generating Units or Power Park
Modules (even where sited separately) owned and/or controlled by the
same Generator, which may reasonably be considered as being
managed as one Power Station.

Power System Stabiliser Equipment controlling the Exciter output via the voltage regulator in such
or PSS a way that power oscillations of the synchronous machines are
dampened. Input variables may be speed, frequency or power (or a
combination of these).

Issue 5 Revision 19 GD 30 September 2016


33 of 49
Preface The preface to the Grid Code (which does not form part of the Grid Code
and therefore is not binding).

Preliminary Notice A notice in writing, sent by NGET both to all Users identified by it under
OC12.4.2.1 and to the Test Proposer, notifying them of a proposed
System Test.

Preliminary Project Data relating to a proposed User Development at the time the User
Planning Data applies for a CUSC Contract but before an offer is made and accepted.

Primary Response The automatic increase in Active Power output of a Genset or, as the
case may be, the decrease in Active Power Demand in response to a
System Frequency fall. This increase in Active Power output or, as the
case may be, the decrease in Active Power Demand must be in
accordance with the provisions of the relevant Ancillary Services
Agreement which will provide that it will be released increasingly with
time over the period 0 to 10 seconds from the time of the start of the
Frequency fall on the basis set out in the Ancillary Services
Agreement and fully available by the latter, and sustainable for at least a
further 20 seconds. The interpretation of the Primary Response to a
0.5 Hz frequency change is shown diagrammatically in Figure CC.A.3.2.

Programming Phase The period between Operational Planning Phase and the Control
Phase. It starts at the 8 weeks ahead stage and finishes at 17:00 on the
day ahead of real time.

Proposal Notice A notice submitted to NGET by a User which would like to undertake a
System Test.

Proposal Report A report submitted by the Test Panel which contains:


(a) proposals for carrying out a System Test (including the manner in
which the System Test is to be monitored);
(b) an allocation of costs (including un-anticipated costs) between the
affected parties (the general principle being that the Test
Proposer will bear the costs); and
(c) such other matters as the Test Panel considers appropriate.
The report may include requirements for indemnities to be given in
respect of claims and losses arising from a System Test.

Protection The provisions for detecting abnormal conditions on a System and


initiating fault clearance or actuating signals or indications.

Protection Apparatus A group of one or more Protection relays and/or logic elements
designated to perform a specified Protection function.

Pumped Storage A Generator which owns and/or operates any Pumped Storage Plant.
Generator

Pumped Storage Plant The Dinorwig, Ffestiniog, Cruachan and Foyers Power Stations.

Pumped Storage Unit A Generating Unit within a Pumped Storage Plant.

Quiescent Physical Data that describes the MW levels to be deducted from the Physical
Notification or QPN Notification of a BM Unit to determine a resultant operating level to
which the Dynamic Parameters associated with that BM Unit apply, and
the associated times for such MW levels. The MW level of the QPN must
always be set to zero.

Issue 5 Revision 19 GD 30 September 2016


34 of 49
Range CCGT Module A CCGT Module where there is a physical connection by way of a steam
or hot gas main between that CCGT Module and another CCGT Module
or other CCGT Modules, which connection contributes (if open) to
efficient modular operation, and which physical connection can be varied
by the operator.

Rated Field Voltage Shall have the meaning ascribed to that term in IEC 34-16-1:1991
[equivalent to British Standard BS4999 Section 116.1 : 1992].

Rated MW The rating-plate MW output of a Generating Unit, Power Park Module


or DC Converter, being:
(a) that output up to which the Generating Unit was designed to
operate (Calculated as specified in British Standard BS EN
60034 1: 1995); or
(b) the nominal rating for the MW output of a Power Park Module
being the maximum continuous electric output power which the
Power Park Module was designed to achieve under normal
operating conditions; or
(c) the nominal rating for the MW import capacity and export capacity
(if at a DC Converter Station) of a DC Converter.

Reactive Despatch Has the meaning set out in the CUSC.


Instruction

Reactive Despatch A restriction placed upon an Embedded Generating Unit, Embedded


Network Restriction Power Park Module or DC Converter at an Embedded DC Converter
Station by the Network Operator that prevents the Generator or DC
Converter Station owner in question (as applicable) from complying with
any Reactive Despatch Instruction with respect to that Generating
Unit, Power Park Module or DC Converter at a DC Converter Station,
whether to provide Mvars over the range referred to in CC 6.3.2 or
otherwise.

Reactive Energy The integral with respect to time of the Reactive Power.

Reactive Power The product of voltage and current and the sine of the phase angle
between them measured in units of voltamperes reactive and standard
multiples thereof, ie:
1000 VAr = 1 kVAr
1000 kVAr = 1 Mvar

Record of Inter-System A written record of inter-system Safety Precautions to be compiled in


Safety Precautions or accordance with the provisions of OC8.
RISSP

Issue 5 Revision 19 GD 30 September 2016


35 of 49
Registered Capacity (a) In the case of a Generating Unit other than that forming part of a
CCGT Module or Power Park Module, the normal full load
capacity of a Generating Unit as declared by the Generator, less
the MW consumed by the Generating Unit through the
Generating Units Unit Transformer when producing the same
(the resultant figure being expressed in whole MW, or in MW to
one decimal place).
(b) In the case of a CCGT Module or Power Park Module, the normal
full load capacity of the CCGT Module or Power Park Module (as
the case may be) as declared by the Generator, being the Active
Power declared by the Generator as being deliverable by the
CCGT Module or Power Park Module at the Grid Entry Point (or
in the case of an Embedded CCGT Module or Power Park
Module, at the User System Entry Point), expressed in whole
MW, or in MW to one decimal place.
(c) In the case of a Power Station, the maximum amount of Active
Power deliverable by the Power Station at the Grid Entry Point
(or in the case of an Embedded Power Station at the User
System Entry Point), as declared by the Generator, expressed in
whole MW, or in MW to one decimal place. The maximum Active
Power deliverable is the maximum amount deliverable
simultaneously by the Generating Units and/or CCGT Modules
and/or Power Park Modules less the MW consumed by the
Generating Units and/or CCGT Modules in producing that Active
Power.
(d) In the case of a DC Converter at a DC Converter Station, the
normal full load amount of Active Power transferable from a DC
Converter at the Onshore Grid Entry Point (or in the case of an
Embedded DC Converter Station at the User System Entry
Point), as declared by the DC Converter Station owner,
expressed in whole MW, or in MW to one decimal place.
(e) In the case of a DC Converter Station, the maximum amount of
Active Power transferable from a DC Converter Station at the
Onshore Grid Entry Point (or in the case of an Embedded DC
Converter Station at the User System Entry Point), as declared
by the DC Converter Station owner, expressed in whole MW, or
in MW to one decimal place.

Registered Data Those items of Standard Planning Data and Detailed Planning Data
which upon connection become fixed (subject to any subsequent
changes).

Registered Import In the case of a DC Converter Station containing DC Converters


Capability connected to an External System, the maximum amount of Active
Power transferable into a DC Converter Station at the Onshore Grid
Entry Point (or in the case of an Embedded DC Converter Station at
the User System Entry Point), as declared by the DC Converter
Station owner, expressed in whole MW.
In the case of a DC Converter connected to an External System and in
a DC Converter Station, the normal full load amount of Active Power
transferable into a DC Converter at the Onshore Grid Entry Point (or in
the case of an Embedded DC Converter Station at the User System
Entry Point), as declared by the DC Converter owner, expressed in
whole MW.

Regulations The Utilities Contracts Regulations 1996, as amended from time to time.

Issue 5 Revision 19 GD 30 September 2016


36 of 49
Reheater Time Constant Determined at Registered Capacity, the reheater time constant will be
construed in accordance with the principles of the IEEE Committee
Report "Dynamic Models for Steam and Hydro Turbines in Power System
Studies" published in 1973 which apply to such phrase.

Relevant E&W As the context requires NGET and/or an E&W Offshore Transmission
Transmission Licensee Licensee.

Relevant Scottish As the context requires SPT and/or SHETL and/or a Scottish Offshore
Transmission Licensee Transmission Licensee.

Relevant Transmission Means SP Transmission Ltd (SPT) in its Transmission Area or Scottish
Licensee Hydro-Electric Transmission Ltd (SHETL) in its Transmission Area or
any Offshore Transmission Licensee in its Transmission Area.

Relevant Unit As defined in the STC, Schedule 3.

Remote Transmission Any Plant and Apparatus or meters owned by NGET which:
Assets
(a) are Embedded in a User System and which are not directly
connected by Plant and/or Apparatus owned by NGET to a sub-
station owned by NGET; and
(b) are by agreement between NGET and such User operated under
the direction and control of such User.

Requesting Safety Co- The Safety Co-ordinator requesting Safety Precautions.


ordinator

Responsible Engineer/ A person nominated by a User to be responsible for System control.


Operator

Responsible Manager A manager who has been duly authorised by a User or NGET to sign
Site Responsibility Schedules on behalf of that User or NGET, as the
case may be.
For Connection Sites in Scotland and Offshore a manager who has
been duly authorised by the Relevant Transmission Licensee to sign
Site Responsibility Schedules on behalf of that Relevant
Transmission Licensee.

Re-synchronisation The bringing of parts of the System which have become Out of
Synchronism with any other System back into Synchronism, and like
terms shall be construed accordingly.

Safety Co-ordinator A person or persons nominated by a Relevant E&W Transmission


Licensee and each E&W User in relation to Connection Points (or in
the case of OTSUA operational prior to the OTSUA Transfer Time,
Transmission Interface Points) on an E&W Transmission System
and/or by the Relevant Scottish Transmission Licensee and each
Scottish User in relation to Connection Points (or in the case of
OTSUA operational prior to the OTSUA Transfer Time, Transmission
Interface Points) on a Scottish Transmission System to be
responsible for the co-ordination of Safety Precautions at each
Connection Point (or in the case of OTSUA operational prior to the
OTSUA Transfer Time, Transmission Interface Points) when work
(which includes testing) is to be carried out on a System which
necessitates the provision of Safety Precautions on HV Apparatus (as
defined in OC8A.1.6.2 and OC8B.1.7.2), pursuant to OC8.

Issue 5 Revision 19 GD 30 September 2016


37 of 49
Safety From The System That condition which safeguards persons when work is to be carried out
on or near a System from the dangers which are inherent in the System.

Safety Key A key unique at the Location capable of operating a lock which will
cause an Isolating Device and/or Earthing Device to be Locked.

Safety Log A chronological record of messages relating to safety co-ordination sent


and received by each Safety Co-ordinator under OC8.

Safety Precautions Isolation and/or Earthing.

Safety Rules The rules of NGET (in England and Wales) and the Relevant
Transmission Licensee (in Scotland or Offshore) or a User that seek to
ensure that persons working on Plant and/or Apparatus to which the
rules apply are safeguarded from hazards arising from the System.

Scottish Offshore An Offshore Transmission System with an Interface Point in Scotland.


Transmission System

Scottish Offshore A person who owns or operates a Scottish Offshore Transmission


Transmission Licensee System pursuant to a Transmission Licence.

Scottish Transmission Collectively SPTs Transmission System and SHETLs Transmission


System System and any Scottish Offshore Transmission Systems.

Scottish User A User in Scotland or any Offshore User who owns or operates Plant
and/or Apparatus connected (or which will at the OTSUA Transfer Time
be connected) to a Scottish Offshore Transmission System

Secondary Response The automatic increase in Active Power output of a Genset or, as the
case may be, the decrease in Active Power Demand in response to a
System Frequency fall. This increase in Active Power output or, as the
case may be, the decrease in Active Power Demand must be in
accordance with the provisions of the relevant Ancillary Services
Agreement which will provide that it will be fully available by 30 seconds
from the time of the start of the Frequency fall and be sustainable for at
least a further 30 minutes. The interpretation of the Secondary
Response to a -0.5 Hz frequency change is shown diagrammatically in
Figure CC.A.3.2.

Secretary of State Has the same meaning as in the Act.

Secured Event Has the meaning set out in the Security and Quality of Supply
Standard.

Security and Quality of The version of the document entitled Security and Quality of Supply
Supply Standard Standard established pursuant to the Transmission Licence in force at
the time of entering into the relevant Bilateral Agreement.

Setpoint Voltage The value of voltage at the Grid Entry Point, or User System Entry
Point if Embedded, on the automatic control system steady state
operating characteristic, as a percentage of the nominal voltage, at which
the transfer of Reactive Power between a Power Park Module, DC
Converter or Non-Synchronous Generating Unit and the
Transmission System, or Network Operators system if Embedded, is
zero.

Settlement Period A period of 30 minutes ending on the hour and half-hour in each hour
during a day.

Issue 5 Revision 19 GD 30 September 2016


38 of 49
Seven Year Statement A statement, prepared by NGET in accordance with the terms of NGETs
Transmission Licence, showing for each of the seven succeeding
Financial Years, the opportunities available for connecting to and using
the National Electricity Transmission System and indicating those
parts of the National Electricity Transmission System most suited to
new connections and transport of further quantities of electricity.

SF6 Gas Zone A segregated zone surrounding electrical conductors within a casing
containing SF6 gas.

SHETL Scottish Hydro-Electric Transmission Limited

Shutdown The condition of a Generating Unit where the generator rotor is at rest or
on barring.

Significant Code Review Means a review of one or more matters which the Authority considers is
likely to:
(a) relate to the Grid Code (either on its own or in conjunction with
any other industry codes); and
(b) be of particular significance in relation to its principal objective
and/or general duties (under section 3A of the Act), statutory
functions and/or relevant obligations arising under EU law, and
concerning which the Authority has issued a notice to NGET
(among others, as appropriate) stating:
(i) that the review will constitute a Significant Code Review;
(ii) the start date of the Significant Code Review; and
(iii) the matters that will fall within the scope of the review;

Significant Code Review Means the period commencing on the start date of a Significant Code
Phase Review as stated in the notice issued by the Authority, and ending
either:
(a) on the date on which the Authority issues a statement that no
directions will be issued in relation to the Grid Code; or
(b) if no statement is made under (a), and the Authority has directed
NGET to raise GC Modification Proposal associated with the
Significant Code Review, on the date on which NGET has raise
such a GC Modification Proposal; or
(c) immediately, if neither a statement nor directions are issued by the
Authority within (and including) twenty eight (28) days from the
Authoritys publication of its Significant Code Review
conclusions.

Significant Incident An Event which either:


(a) was notified by a User to NGET under OC7, and which NGET
considers has had or may have had a significant effect on the
National Electricity Transmission System, and NGET requires
the User to report that Event in writing in accordance with OC10
and notifies the User accordingly; or
(b) was notified by NGET to a User under OC7, and which that User
considers has had or may have had a significant effect on that
Users System, and that User requires NGET to report that Event
in writing in accordance with the provisions of OC10 and notifies
NGET accordingly.

Issue 5 Revision 19 GD 30 September 2016


39 of 49
Simultaneous Tap A tap change implemented on the generator step-up transformers of
Change Synchronised Gensets, effected by Generators in response to an
instruction from NGET issued simultaneously to the relevant Power
Stations. The instruction, preceded by advance notice, must be effected
as soon as possible, and in any event within one minute of receipt from
NGET of the instruction.

Single Line Diagram A schematic representation of a three-phase network in which the three
phases are represented by single lines. The diagram shall include (but
not necessarily be limited to) busbars, overhead lines, underground
cables, power transformers and reactive compensation equipment. It
shall also show where Large Power Stations are connected, and the
points at which Demand is supplied.

Single Point of A single Point of Connection, with no interconnection through the


Connection Users System to another Point of Connection.

Site Common Drawings Drawings prepared for each Connection Site (and in the case of
OTSDUW, Transmission Interface Site) which incorporate Connection
Site (and in the case of OTSDUW, Transmission Interface Site) layout
drawings, electrical layout drawings, common protection/ control
drawings and common services drawings.

Site Responsibility A schedule containing the information and prepared on the basis of the
Schedule provisions set out in Appendix 1 of the CC.

Slope The ratio of the steady state change in voltage, as a percentage of the
nominal voltage, to the steady state change in Reactive Power output, in
per unit of Reactive Power capability. For the avoidance of doubt, the
value indicates the percentage voltage reduction that will result in a 1 per
unit increase in Reactive Power generation.

Issue 5 Revision 19 GD 30 September 2016


40 of 49
Small Power Station A Power Station which is
(a) directly connected to:
(i) NGETs Transmission System where such Power Station
has a Registered Capacity of less than 50MW; or
(ii) SPTs Transmission System where such Power Station
has a Registered Capacity of less than 30MW; or
(iii) SHETLs Transmission System where such a Power
Station has a Registered Capacity of less than 10 MW; or
(iv) an Offshore Transmission System where such Power
Station has a Registered Capacity of less than 10MW;
or,
(b) Embedded within a User System (or part thereof) where such
User System (or part thereof) is connected under normal
operating conditions to:
(i) NGETs Transmission System and such Power Station
has a Registered Capacity of less than 50MW; or
(ii) SPTs Transmission System and such Power Station has
a Registered Capacity of less than 30MW; or
(iii) SHETLs Transmission System and such Power Station
has a Registered Capacity of less than 10MW;
or,
(c) Embedded within a User System (or part thereof) where the User
System (or part thereof) is not connected to the National
Electricity Transmission System, although such Power Station
is in:
(i) NGETs Transmission Area and such Power Station has
a Registered Capacity of less than 50MW; or
(ii) SPTs Transmission Area and such Power Station has a
Registered Capacity of less than 30MW; or
(iii) SHETLs Transmission Area and such Power Station has
a Registered Capacity of less than 10MW;

Speeder Motor Setting The minimum and maximum no-load speeds (expressed as a percentage
Range of rated speed) to which the turbine is capable of being controlled, by the
speeder motor or equivalent, when the Generating Unit terminals are on
open circuit.

SPT SP Transmission Limited

Standard Planning Data The general data required by NGET under the PC. It is generally also the
data which NGET requires from a new User in an application for a CUSC
Contract, as reflected in the PC.

Start Time The time named as such in an instruction issued by NGET pursuant to
the BC.

Start-Up The action of bringing a Generating Unit from Shutdown to


Synchronous Speed.

Statement of Readiness Has the meaning set out in the Bilateral Agreement and/or
Construction Agreement.

Issue 5 Revision 19 GD 30 September 2016


41 of 49
Station Board A switchboard through which electrical power is supplied to the
Auxiliaries of a Power Station, and which is supplied by a Station
Transformer. It may be interconnected with a Unit Board.

Station Transformer A transformer supplying electrical power to the Auxiliaries of


(a) a Power Station, which is not directly connected to the
Generating Unit terminals (typical voltage ratios being 132/11kV
or 275/11kV),or
(b) a DC Converter Station.

STC Committee The committee established under the STC.

Steam Unit A Generating Unit whose prime mover converts the heat-energy in
steam to mechanical energy.

Subtransmission The part of a Users System which operates at a single transformation


System below the voltage of the relevant Transmission System.

Supergrid Voltage Any voltage greater than 200kV.

Supplier (a) A person supplying electricity under an Electricity Supply


Licence; or
(b) A person supplying electricity under exemption under the Act;
in each case acting in its capacity as a supplier of electricity to
Customers in Great Britain.

Surplus A MW figure relating to a System Zone equal to the total Output Usable
in the System Zone:
(a) minus the forecast of Active Power Demand in the System Zone,
and
(b) minus the export limit in the case of an export limited System
Zone,
or
plus the import limit in the case of an import limited System Zone,
and
(c) (only in the case of a System Zone comprising the National
Electricity Transmission System) minus the Operational
Planning Margin.
For the avoidance of doubt, a Surplus of more than zero in an export
limited System Zone indicates an excess of generation in that System
Zone; and a Surplus of less than zero in an import limited System Zone
indicates insufficient generation in that System Zone.

Synchronised (a) The condition where an incoming Generating Unit or Power Park
Module or DC Converter or System is connected to the busbars
of another System so that the Frequencies and phase
relationships of that Generating Unit, Power Park Module, DC
Converter or System, as the case may be, and the System to
which it is connected are identical, like terms shall be construed
accordingly e.g. Synchronism.
(b) The condition where an importing BM Unit is consuming electricity.

Issue 5 Revision 19 GD 30 September 2016


42 of 49
Synchronising The amount of MW (in whole MW) produced at the moment of
Generation synchronising.

Synchronising Group A group of two or more Gensets) which require a minimum time interval
between their Synchronising or De-Synchronising times.

Synchronous The operation of rotating synchronous Apparatus for the specific


Compensation purpose of either the generation or absorption of Reactive Power.

Synchronous Any Onshore Synchronous Generating Unit or Offshore


Generating Unit Synchronous Generating Unit.

Synchronous Speed That speed required by a Generating Unit to enable it to be


Synchronised to a System.

System Any User System and/or the National Electricity Transmission


System, as the case may be.

System Ancillary Collectively Part 1 System Ancillary Services and Part 2 System
Services Ancillary Services.

System Constraint A limitation on the use of a System due to lack of transmission capacity
or other System conditions.

System Constrained That portion of Registered Capacity or Registered Import Capacity not
Capacity available due to a System Constraint.

System Constraint A part of the National Electricity Transmission System which, because
Group of System Constraints, is subject to limits of Active Power which can
flow into or out of (as the case may be) that part.

System Fault A measure of the ability of Protection to initiate successful tripping of


Dependability Index or circuit-breakers which are associated with a faulty item of Apparatus. It
Dp is calculated using the formula:
Dp = 1 F1/A
Where:
A = Total number of System faults
F1 = Number of System faults where there was a failure to trip a
circuit-breaker.

System Margin The margin in any period between


(a) the sum of Maximum Export Limits and
(b) forecast Demand and the Operating Margin,
for that period.

System Negative That margin of Active Power sufficient to allow the largest loss of Load
Reserve Active Power at any time.
Margin or System
NRAPM

System Operator - Has the meaning set out in NGETs Transmission Licence
Transmission Owner
Code or STC

Issue 5 Revision 19 GD 30 September 2016


43 of 49
System Telephony An alternative method by which a Users Responsible
Engineer/Operator and NGET Control Engineer(s) speak to one and
another for the purposes of control of the Total System in both normal
operating conditions and where practicable, emergency operating
conditions.

System Tests Tests which involve simulating conditions, or the controlled application of
irregular, unusual or extreme conditions, on the Total System, or any
part of the Total System, but which do not include commissioning or
recommissioning tests or any other tests of a minor nature.

System to Demand An intertrip scheme which disconnects Demand when a System fault
Intertrip Scheme has arisen to prevent abnormal conditions occurring on the System.

System to Generator A Balancing Service involving the initiation by a System to Generator


Operational Operational Intertripping Scheme of automatic tripping of the Users
Intertripping circuit breaker(s), or Relevant Transmission Licensees circuit
breaker(s) where agreed by NGET, the User and the Relevant
Transmission Licensee, resulting in the tripping of BM Unit(s) or
(where relevant) Generating Unit(s) comprised in a BM Unit to prevent
abnormal system conditions occurring, such as over voltage, overload,
System instability, etc, after the tripping of other circuit-breakers
following power System fault(s).

System to Generator A System to Generating Unit or System to CCGT Module or System to


Operational Power Park Module Intertripping Scheme forming a condition of
Intertripping Scheme connection and specified in Appendix F3 of the relevant Bilateral
Agreement, being either a Category 1 Intertripping Scheme, Category 2
Intertripping Scheme, Category 3 Intertripping Scheme or Category 4
Intertripping Scheme.

System Zone A region of the National Electricity Transmission System within a


described boundary or the whole of the National Electricity
Transmission System, as further provided for in OC2.2.4, and the term
"Zonal" will be construed accordingly.

Target Frequency That Frequency determined by NGET, in its reasonable opinion, as the
desired operating Frequency of the Total System. This will normally be
50.00Hz plus or minus 0.05Hz, except in exceptional circumstances as
determined by NGET, in its reasonable opinion when this may be 49.90
or 50.10Hz. An example of exceptional circumstances may be difficulties
caused in operating the System during disputes affecting fuel supplies.

Technical Specification In relation to Plant and/or Apparatus,


(a) the relevant European Specification; or
(b) if there is no relevant European Specification, other relevant
standards which are in common use in the European Community.

Test Co-ordinator A person who co-ordinates System Tests.

Test Panel A panel, whose composition is detailed in OC12, which is responsible,


inter alia, for considering a proposed System Test, and submitting a
Proposal Report and a Test Programme.

Issue 5 Revision 19 GD 30 September 2016


44 of 49
Test Programme A programme submitted by the Test Panel to NGET, the Test Proposer,
and each User identified by NGET under OC12.4.2.1, which states the
switching sequence and proposed timings of the switching sequence, a
list of those staff involved in carrying out the System Test (including
those responsible for the site safety) and such other matters as the Test
Panel deems appropriate.

Test Proposer The person who submits a Proposal Notice.

Total Shutdown The situation existing when all generation has ceased and there is no
electricity supply from External Interconnections and, therefore, the
Total System has shutdown with the result that it is not possible for the
Total System to begin to function again without NGETs directions
relating to a Black Start.

Total System The National Electricity Transmission System and all User Systems
in the National Electricity Transmission System Operator Area.

Trading Point A commercial and, where so specified in the Grid Code, an operational
interface between a User and NGET, which a User has notified to NGET.

Transfer Date Such date as may be appointed by the Secretary of State by order
under section 65 of the Act.

Transmission Means, when used in conjunction with another term relating to equipment
or a site, whether defined or not, that the associated term is to be read as
being part of or directly associated with the National Electricity
Transmission System, and not of or with the User System.

Transmission Area Has the meaning set out in the Transmission Licence of a
Transmission Licensee.

Transmission DC Any Transmission Licensee Apparatus (or OTSUA that will become
Converter Transmission Licensee Apparatus at the OTSUA Transfer Time) used
to convert alternating current electricity to direct current electricity, or vice
versa. A Transmission Network DC Converter is a standalone
operative configuration at a single site comprising one or more converter
bridges, together with one or more converter transformers, converter
control equipment, essential protective and switching devices and
auxiliaries, if any, used for conversion.

Transmission Entry Has the meaning set out in the CUSC.


Capacity

Transmission Interface In NGETs Transmission Area, a Transmission circuit which connects


Circuit a System operating at a voltage above 132kV to a System operating at
a voltage of 132kV or below
In SHETLs Transmission Area and SPTs Transmission Area, a
Transmission circuit which connects a System operating at a voltage of
132kV or above to a System operating at a voltage below 132kV.

Transmission Interface means the electrical point of connection between the Offshore
Point Transmission System and an Onshore Transmission System.

Transmission Interface the site at which the Transmission Interface Point is located.
Site

Transmission Licence A licence granted under Section 6(1)(b) of the Act.

Issue 5 Revision 19 GD 30 September 2016


45 of 49
Transmission Licensee Any Onshore Transmission Licensee or Offshore Transmission
Licensee

Transmission Site In England and Wales, means a site owned (or occupied pursuant to a
lease, licence or other agreement) by NGET in which there is a
Connection Point. For the avoidance of doubt, a site owned by a User
but occupied by NGET as aforesaid, is a Transmission Site.
In Scotland and Offshore, means a site owned (or occupied pursuant to
a lease, licence or other agreement) by a Relevant Transmission
Licensee in which there is a Connection Point. For the avoidance of
doubt, a site owned by a User but occupied by the Relevant
Transmission Licensee as aforesaid, is a Transmission Site.

Transmission System Has the same meaning as the term "licensee's transmission system" in
the Transmission Licence of a Transmission Licensee.

Turbine Time Constant Determined at Registered Capacity, the turbine time constant will be
construed in accordance with the principles of the IEEE Committee
Report "Dynamic Models for Steam and Hydro Turbines in Power System
Studies" published in 1973 which apply to such phrase.

Unbalanced Load The situation where the Load on each phase is not equal.

Under-excitation Limiter Shall have the meaning ascribed to that term in IEC 34-16-1:1991
[equivalent to British Standard BS4999 Section 116.1 : 1992].

Under Frequency Relay An electrical measuring relay intended to operate when its characteristic
quantity (Frequency) reaches the relay settings by decrease in
Frequency.

Unit Board A switchboard through which electrical power is supplied to the


Auxiliaries of a Generating Unit and which is supplied by a Unit
Transformer. It may be interconnected with a Station Board.

Unit Transformer A transformer directly connected to a Generating Units terminals, and


which supplies power to the Auxiliaries of a Generating Unit. Typical
voltage ratios are 23/11kV and 15/6.6Kv.

Unit Load Controller The time constant, expressed in units of seconds, of the power output
Response Time increase which occurs in the Secondary Response timescale in
Constant response to a step change in System Frequency.

Unresolved Issues Any relevant Grid Code provisions or Bilateral Agreement requirements
identified by NGET with which the relevant User has not demonstrated
compliance to NGETs reasonable satisfaction at the date of issue of the
Interim Operational Notification and/or Limited Operational
Notification and which are detailed in such Interim Operational
Notification and/or Limited Operational Notification.

User A term utilised in various sections of the Grid Code to refer to the persons
using the National Electricity Transmission System, as more
particularly identified in each section of the Grid Code concerned. In the
Preface and the General Conditions the term means any person to
whom the Grid Code applies.

Issue 5 Revision 19 GD 30 September 2016


46 of 49
User Data File Structure The file structure given at DRC 18 which will be specified by NGET which
a Generator or DC Converter Station owner must use for the purposes
of CP to submit DRC data Schedules and information demonstrating
compliance with the Grid Code and, where applicable, with the CUSC
Contract(s), unless otherwise agreed by NGET.

User Development In the PC means either User's Plant and/or Apparatus to be connected
to the National Electricity Transmission System, or a Modification
relating to a User's Plant and/or Apparatus already connected to the
National Electricity Transmission System, or a proposed new
connection or Modification to the connection within the User System.

User Self Certification of A certificate, in the form attached at CP.A.2.(1) completed by a Generator
Compliance or DC Converter Station owner to which the Compliance Statement is
attached which confirms that such Plant and Apparatus complies with the
relevant Grid Code provisions and where appropriate, with the CUSC
Contract(s), as identified in the Compliance Statement and, if
appropriate, identifies any Unresolved Issues and/or any exceptions to
such compliance and details the derogation(s) granted in respect of such
exceptions.

User Site In England and Wales, a site owned (or occupied pursuant to a lease,
licence or other agreement) by a User in which there is a Connection
Point. For the avoidance of doubt, a site owned by NGET but occupied
by a User as aforesaid, is a User Site.
In Scotland and Offshore, a site owned (or occupied pursuant to a lease,
licence or other agreement) by a User in which there is a Connection
Point. For the avoidance of doubt, a site owned by a Relevant
Transmission Licensee but occupied by a User as aforesaid, is a User
Site.

User System Any system owned or operated by a User comprising:-


(a) Generating Units; and/or
(b) Systems consisting (wholly or mainly) of electric lines used for the
distribution of electricity from Grid Supply Points or Generating
Units or other entry points to the point of delivery to Customers,
or other Users;
and Plant and/or Apparatus Apparatus (including prior to the OTSUA
Transfer Time, any OTSUA) connecting:-
(c) The system as described above; or
(d) Non-Embedded Customers equipment;
to the National Electricity Transmission System or to the relevant
other User System, as the case may be.
The User System includes any Remote Transmission Assets operated
by such User or other person and any Plant and/or Apparatus and
meters owned or operated by the User or other person in connection with
the distribution of electricity but does not include any part of the National
Electricity Transmission System.

User System Entry Point A point at which a Generating Unit, a CCGT Module or a CCGT Unit or
a Power Park Module or a DC Converter, as the case may be, which is
Embedded connects to the User System.

Water Time Constant Bears the meaning ascribed to the term "Water inertia time" in IEC308.

Issue 5 Revision 19 GD 30 September 2016


47 of 49
Weekly ACS Conditions Means that particular combination of weather elements that gives rise to
a level of peak Demand within a week, taken to commence on a Monday
and end on a Sunday, which has a particular chance of being exceeded
as a result of weather variation alone. This particular chance is
determined such that the combined probabilities of Demand in all weeks
of the year exceeding the annual peak Demand under Annual ACS
Conditions is 50%, and in the week of maximum risk the weekly peak
Demand under Weekly ACS Conditions is equal to the annual peak
Demand under Annual ACS Conditions.

Zonal System Security That generation required, within the boundary circuits defining the
Requirements System Zone, which when added to the secured transfer capability of
the boundary circuits exactly matches the Demand within the System
Zone.

A number of the terms listed above are defined in other documents, such as the Balancing and Settlement
Code and the Transmission Licence. Appendix 1 sets out the current definitions from the other documents
of those terms so used in the Grid Code and defined in other documents for ease of reference, but does not
form part of the Grid Code.

Issue 5 Revision 19 GD 30 September 2016


48 of 49
GD.2 Construction of References
GD.2.1 In the Grid Code:
(i) a table of contents, a Preface, a Revision section, headings, and the Appendix to this
Glossary and Definitions are inserted for convenience only and shall be ignored in
construing the Grid Code;
(ii) unless the context otherwise requires, all references to a particular paragraph, sub-
paragraph, Appendix or Schedule shall be a reference to that paragraph, sub-paragraph
Appendix or Schedule in or to that part of the Grid Code in which the reference is made;
(iii) unless the context otherwise requires, the singular shall include the plural and vice
versa, references to any gender shall include all other genders and references to
persons shall include any individual, body corporate, corporation, joint venture, trust,
unincorporated association, organisation, firm or partnership and any other entity, in
each case whether or not having a separate legal personality;
(iv) references to the words "include" or "including" are to be construed without limitation to
the generality of the preceding words;
(v) unless there is something in the subject matter or the context which is inconsistent
therewith, any reference to an Act of Parliament or any Section of or Schedule to, or
other provision of an Act of Parliament shall be construed at the particular time, as
including a reference to any modification, extension or re-enactment thereof then in
force and to all instruments, orders and regulations then in force and made under or
deriving validity from the relevant Act of Parliament;
(vi) where the Glossary and Definitions refers to any word or term which is more
particularly defined in a part of the Grid Code, the definition in that part of the Grid Code
will prevail (unless otherwise stated) over the definition in the Glossary & Definitions in
the event of any inconsistency;
(vii) a cross-reference to another document or part of the Grid Code shall not of itself impose
any additional or further or co-existent obligation or confer any additional or further or
co-existent right in the part of the text where such cross-reference is contained;
(viii) nothing in the Grid Code is intended to or shall derogate from NGET's statutory or
licence obligations;
(ix) a "holding company" means, in relation to any person, a holding company of such
person within the meaning of section 736, 736A and 736B of the Companies Act 1985
as substituted by section 144 of the Companies Act 1989 and, if that latter section is not
in force at the Transfer Date, as if such latter section were in force at such date;
(x) a "subsidiary" means, in relation to any person, a subsidiary of such person within the
meaning of section 736, 736A and 736B of the Companies Act 1985 as substituted by
section 144 of the Companies Act 1989 and, if that latter section is not in force at the
Transfer Date, as if such latter section were in force at such date;
(xi) references to time are to London time; and
(xii) (a) Save where (b) below applies, where there is a reference to an item of data being
expressed in a whole number of MW, fractions of a MW below 0.5 shall be rounded
down to the nearest whole MW and fractions of a MW of 0.5 and above shall be
rounded up to the nearest whole MW;
(b) In the case of the definition of Registered Capacity, fractions of a MW below 0.05
shall be rounded down to one decimal place and fractions of a MW of 0.05 and above
shall be rounded up to one decimal place.

< END OF GLOSSARY & DEFINITIONS >

Issue 5 Revision 19 GD 30 September 2016


49 of 49
PLANNING CODE
(PC)

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


PC.1 INTRODUCTION.................................................................................................................................. 2
PC.2 OBJECTIVE......................................................................................................................................... 3
PC.3 SCOPE ................................................................................................................................................ 3
PC.4 PLANNING PROCEDURES ................................................................................................................. 6
PC.5 PLANNING DATA .............................................................................................................................. 10
PC.6 PLANNING STANDARDS .................................................................................................................. 13
PC.7 PLANNING LIAISON .......................................................................................................................... 14
PC.8 OTSDUW PLANNING LIAISION ........................................................................................................ 15
APPENDIX A - PLANNING DATA REQUIREMENTS .................................................................................... 16
PART 1 - STANDARD PLANNING DATA................................................................................................. 20
PC.A.2 USERS SYSTEM (AND OTSUA) DATA................................................................................. 20
PC.A.3 GENERATING UNIT AND DC CONVERTER DATA ............................................................... 28
PC.A.4 DEMAND AND ACTIVE ENERGY DATA ................................................................................ 34
PART 2 - DETAILED PLANNING DATA ................................................................................................... 40
PC.A.5 GENERATING UNIT, POWER PARK MODULE, DC CONVERTER AND OTSDUW PLANT
AND APPARATUS DATA ..................................................................................................................... 40
PC.A.6 USERS SYSTEM DATA ........................................................................................................ 55
PC.A.7 ADDITIONAL DATA FOR NEW TYPES OF POWER STATIONS, DC CONVERTER
STATIONS, OTSUA AND CONFIGURATIONS..................................................................................... 59
PART 3 DETAILED PLANNING DATA .................................................................................................. 60
APPENDIX B - SINGLE LINE DIAGRAMS .................................................................................................... 62
APPENDIX C - TECHNICAL AND DESIGN CRITERIA .................................................................................. 65
PART 1 SHETLs TECHNICAL AND DESIGN CRITERIA ...................................................................... 65
PART 2 - SPT's TECHNICAL AND DESIGN CRITERIA ........................................................................... 67
APPENDIX D - DATA NOT DISCLOSED TO A RELEVANT TRANSMISSION LICENSEE ............................. 68
APPENDIX E - OFFSHORE TRANSMISSION SYSTEM AND OTSDUW PLANT AND
APPARATUS TECHNICAL AND DESIGN CRITERIA .................................................................................... 70
APPENDIX F - OTSDUW DATA AND INFORMATION AND OTSDUW NETWORK DATA AND
INFORMATION............................................................................................................................................. 71

Issue 5 Revision 15 PC 03 February 2015


i
PC.1 INTRODUCTION
PC.1.1 The Planning Code ("PC") specifies the technical and design criteria and procedures to be
applied by NGET in the planning and development of the National Electricity Transmission
System and to be taken into account by Users in the planning and development of their own
Systems. In the case of OTSUA, the PC also specifies the technical and design criteria and
procedures to be applied by the User in the planning and development of the OTSUA. It details
information to be supplied by Users to NGET, and certain information to be supplied by NGET to
Users. In Scotland and Offshore, NGET has obligations under the STC to inform Relevant
Transmission Licensees of data required for the planning of the National Electricity
Transmission System. In respect of PC data, NGET may pass on User data to a Relevant
Transmission Licensee, as detailed in PC.3.4 and PC.3.5.
PC.1.1A Provisions of the PC which apply in relation to OTSDUW and OTSUA shall apply up to the
OTSUA Transfer Time, whereupon such provisions shall (without prejudice to any prior non-
compliance) cease to apply, without prejudice to the continuing application of provisions of the
PC applying in relation to the relevant Offshore Transmission System and/or Connection Site.
PC.1.1B As used in the PC:
(a) National Electricity Transmission System excludes OTSDUW Plant and Apparatus (prior
to the OTSUA Transfer Time) unless the context otherwise requires;
(b) and User Development includes OTSDUW unless the context otherwise requires.
PC.1.2 The Users referred to above are defined, for the purpose of the PC, in PC.3.1.
PC.1.3 Development of the National Electricity Transmission System, involving its reinforcement or
extension, will arise for a number of reasons including, but not limited to:
(a) a development on a User System already connected to the National Electricity
Transmission System;
(b) the introduction of a new Connection Site or the Modification of an existing Connection
Site between a User System and the National Electricity Transmission System;
(c) the cumulative effect of a number of such developments referred to in (a) and (b) by one or
more Users.
PC.1.4 Accordingly, the reinforcement or extension of the National Electricity Transmission System
may involve work:
(a) at a substation at a Connection Site where User's Plant and/or Apparatus is connected to
the National Electricity Transmission System (or in the case of OTSDUW, at a substation
at an Interface Point);
(b) on transmission lines or other facilities which join that Connection Site (or in the case of
OTSDUW, Interface Point) to the remainder of the National Electricity Transmission
System;
(c) on transmission lines or other facilities at or between points remote from that Connection
Site (or in the case of OTSDUW, Interface Point).
PC.1.5 The time required for the planning and development of the National Electricity Transmission
System will depend on the type and extent of the necessary reinforcement and/or extension
work, the need or otherwise for statutory planning consent, the associated possibility of the need
for a public inquiry and the degree of complexity in undertaking the new work while maintaining
satisfactory security and quality of supply on the existing National Electricity Transmission
System.

Issue 5 Revision 15 PC 03 February 2016


2 of 72
PC.2 OBJECTIVE
PC.2.1 The objectives of the PC are:
(a) to promote NGET/User interaction in respect of any proposed development on the User
System which may impact on the performance of the National Electricity Transmission
System or the direct connection with the National Electricity Transmission System;
(b) to provide for the supply of information to NGET from Users in order that planning and
development of the National Electricity Transmission System can be undertaken in
accordance with the relevant Licence Standards, to facilitate existing and proposed
connections, and also to provide for the supply of certain information from NGET to Users in
relation to short circuit current contributions and OTSUA; and
(c) to specify the Licence Standards which will be used in the planning and development of the
National Electricity Transmission System; and
(d) to provide for the supply of information required by NGET from Users in respect of the
following to enable NGET to carry out its duties under the Act and the Transmission
Licence:
(i) Mothballed Generating Units; and
(ii) capability of gas-fired Generating Units to run using alternative fuels.
NGET will use the information provided under PC.2.1(d) in providing reports to the Authority
and the Secretary of State and, where directed by the Authority or the Secretary of Sate
to do so, NGET may publish the information. Where it is known by NGET that such
information is intended for wider publication the information provided under PC.2.1(d) shall
be aggregated such that individual data items should not be identifiable.
(e) in the case of OTSUA:
(i) to specify the minimum technical and design criteria and procedures to be applied by
Users in the planning and development of OTSUA; and thereby
(ii) to ensure that the OTSUA can from the OTSUA Transfer Time be operated as part of
the National Electricity Transmission System; and
(iii) to provide for the arrangements and supply of information and data between NGET and
a User to ensure that the User is able to undertake OTSDUW; and
(iv) to promote NGET/User interaction and co-ordination in respect of any proposed
development on the National Electricity Transmission System or the OTSUA, which
may impact on the OTSUA or (as the case may be) the National Electricity
Transmission System.

PC.3 SCOPE
PC.3.1 The PC applies to NGET and to Users, which in the PC means:
(a) Generators;
(b) Generators undertaking OTSDUW;
(c) Network Operators;
(d) Non-Embedded Customers; and
(e) DC Converter Station owners.
The above categories of User will become bound by the PC prior to them generating, operating,
or consuming or importing/exporting, as the case may be, and references to the various
categories (or to the general category) of User should, therefore, be taken as referring to them in
that prospective role as well as to Users actually connected.

Issue 5 Revision 15 PC 03 February 2016


3 of 72
PC.3.2 In the case of Embedded Power Stations and Embedded DC Converter Stations, unless
provided otherwise, the following provisions apply with regard to the provision of data under this
PC:
(a) each Generator shall provide the data direct to NGET in respect of (i) Embedded Large
Power Stations, (ii) Embedded Medium Power Stations subject to a Bilateral Agreement
and (iii) Embedded Small Power Stations which form part of a Cascade Hydro Scheme;
(b) each DC Converter owner shall provide the data direct to NGET in respect of Embedded
DC Converter Stations subject to a Bilateral Agreement;
(c) each Network Operator shall provide the data to NGET in respect of each Embedded
Medium Power Station not subject to a Bilateral Agreement or Embedded DC Converter
Station not subject to a Bilateral Agreement connected, or proposed to be connected
within such Network Operators System;
(d) although data is not normally required specifically on Embedded Small Power Stations or
on Embedded installations of direct current converters which do not form a DC Converter
Station under this PC, each Network Operator in whose System they are Embedded
should provide the data (contained in the Appendix) to NGET in respect of Embedded
Small Power Stations or Embedded installations of direct current converters which do not
form a DC Converter Station if:
(i) it falls to be supplied pursuant to the application for a CUSC Contract or in the
Statement of Readiness to be supplied in connection with a Bilateral Agreement
and/or Construction Agreement, by the Network Operator; or
(ii) it is specifically requested by NGET in the circumstances provided for under this PC.
PC.3.3 Certain data does not normally need to be provided in respect of certain Embedded Power
Stations or Embedded DC Converter Stations, as provided in PC.A.1.12.
In summary, Network Operators are required to supply the following data in respect of
Embedded Medium Power Stations not subject to a Bilateral Agreement or Embedded DC
Converter Stations not subject to a Bilateral Agreement connected, or is proposed to be
connected, within such Network Operators System:
PC.A.2.1.1
PC.A.2.2.2
PC.A.2.5.5.2
PC.A.2.5.5.7
PC.A.2.5.6
PC.A.3.1.5
PC.A.3.2.2
PC.A.3.3.1
PC.A.3.4.1
PC.A.3.4.2
PC.A.5.2.2
PC.A.5.3.2
PC.A.5.4
PC.A.5.5.1
PC.A.5.6

Issue 5 Revision 15 PC 03 February 2016


4 of 72
For the avoidance of doubt Network Operators are required to supply the above data in respect
of Embedded Medium Power Stations not subject to a Bilateral Agreement and Embedded
DC Converter Stations not subject to a Bilateral Agreement which are located Offshore and
which are connected or proposed to be connected within such Network Operators System.
This is because Embedded Medium Power Stations not subject to a Bilateral Agreement and
Embedded DC Converter Stations not subject to a Bilateral Agreement are treated as
Onshore Generators or Onshore DC Converter Station owners connected to an Onshore
User System Entry Point.
PC.3.4 NGET may provide to the Relevant Transmission Licensees any data which has been
submitted to NGET by any Users pursuant to the following paragraphs of the PC. For the
avoidance of doubt, NGET will not provide to the Relevant Transmission Licensees, the types
of data specified in Appendix D. The Relevant Transmission Licensees use of such data is
detailed in the STC.
PC.A.2.2
PC.A.2.5
PC.A.3.1
PC.A.3.2.1
PC.A.3.2.2
PC.A.3.3
PC.A.3.4
PC.A.4
PC.A.5.1
PC.A.5.2
PC.A.5.3.1
PC.A.5.3.2
PC.A.5.4.1
PC.A.5.4.2
PC.A.5.4.3.1
PC.A.5.4.3.2
PC.A.5.4.3.3
PC.A.5.4.3.4
PC.A.7
(and in addition in respect of the data submitted in respect of the OTSUA)
PC.A.2.2
PC.A.2.3
PC.A.2.4
PC.A.2.5
PC.A.3.2.2
PC.A.3.3.1(d)
PC.A.4
PC.A.5.4.3.1
PC.A.5.4.3.2
PC.A.6.2
PC.A.6.3
Issue 5 Revision 15 PC 03 February 2016
5 of 72
PC.A.6.4
PC.A.6.5
PC.A.6.6
PC.A.7
PC.3.5 In addition to the provisions of PC.3.4 NGET may provide to the Relevant Transmission
Licensees any data which has been submitted to NGET by any Users in respect of Relevant
Units pursuant to the following paragraphs of the PC.
PC.A.2.3
PC.A.2.4
PC.A.5.5
PC.A.5.7
PC.A.6.2
PC.A.6.3
PC.A.6.4
PC.A.6.5
PC.A.6.6
PC.3.6 In the case of Offshore Embedded Power Stations connected to an Offshore User System
which directly connects to an Offshore Transmission System, any additional data requirements
in respect of such Offshore Embedded Power Stations may be specified in the relevant
Bilateral Agreement with the Network Operator or in any Bilateral Agreement between NGET
and such Offshore Embedded Power Station.
PC.3.7 In the case of a Generator undertaking OTSDUW connecting to an Onshore Network
Operators System, any additional requirements in respect of such OTSDUW Plant and
Apparatus will be specified in the relevant Bilateral Agreement with the Generator. For the
avoidance of doubt, requirements applicable to Generators undertaking OTSDUW and
connecting to a Network Operators User System, shall be consistent with those applicable
requirements of Generators undertaking OTSDUW and connecting to a Transmission Interface
Point.

PC.4 PLANNING PROCEDURES


PC.4.1 Pursuant to Condition C11 of NGETs Transmission Licence, the means by which Users and
proposed Users of the National Electricity Transmission System are able to assess
opportunities for connecting to, and using, the National Electricity Transmission System
comprise two distinct parts, namely:
(a) a statement, prepared by NGET under its Transmission Licence, showing for each of the
seven succeeding Financial Years, the opportunities available for connecting to and using
the National Electricity Transmission System and indicating those parts of the National
Electricity Transmission System most suited to new connections and transport of further
quantities of electricity (the "Seven Year Statement"); and
(b) an offer, in accordance with its Transmission Licence, by NGET to enter into a CUSC
Contract. A Bilateral Agreement is to be entered into for every Connection Site (and for
certain Embedded Power Stations and Embedded DC Converter Stations) within the first
two of the following categories and the existing Bilateral Agreement may be required to be
varied in the case of the third category:
(i) existing Connection Sites (and for certain Embedded Power Stations) as at the
Transfer Date;
(ii) new Connection Sites (and for certain Embedded Power Stations and for Embedded
DC Converter Stations) with effect from the Transfer Date;

Issue 5 Revision 15 PC 03 February 2016


6 of 72
(iii) a Modification at a Connection Site (or in relation to the connection of certain
Embedded Power Stations and for Embedded DC Converter Stations whether or not
the subject of a Bilateral Agreement) (whether such Connection Site or connection
exists on the Transfer Date or is new thereafter) with effect from the Transfer Date.
In this PC, unless the context otherwise requires, "connection" means any of these 3
categories.
PC.4.2 Introduction to Data
User Data
PC.4.2.1 Under the PC, two types of data to be supplied by Users are called for:
(a) Standard Planning Data; and
(b) Detailed Planning Data,
as more particularly provided in PC.A.1.4.
PC.4.2.2 The PC recognises that these two types of data, namely Standard Planning Data and Detailed
Planning Data, are considered at three different levels:
(a) Preliminary Project Planning Data;
(b) Committed Project Planning Data; and
(c) Connected Planning Data,
as more particularly provided in PC.5
PC.4.2.3 Connected Planning Data is itself divided into:
(a) Forecast Data;
(b) Registered Data; and
(c) Estimated Registered Data,
as more particularly provided in PC.5.5
PC.4.2.4 Clearly, an existing User proposing a new Connection Site (or Embedded Power Station or
Embedded DC Converter Station in the circumstances outlined in PC.4.1) will need to supply
data both in an application for a Bilateral Agreement and under the PC in relation to that
proposed new Connection Site (or Embedded Power Station or Embedded DC Converter
Station in the circumstances outlined in PC.4.1) and that will be treated as Preliminary Project
Planning Data or Committed Project Planning Data (as the case may be), but the data it
supplies under the PC relating to its existing Connection Sites will be treated as Connected
Planning Data.
Network Data
PC.4.2.5 In addition, there is Network Data supplied by NGET in relation to short circuit current
contributions and in relation to OTSUA.

Issue 5 Revision 15 PC 03 February 2016


7 of 72
PC.4.3 Data Provision
PC.4.3.1 Seven Year Statement
To enable the Seven Year Statement to be prepared, each User is required to submit to NGET
(subject to the provisions relating to Embedded Power Stations and Embedded DC Converter
Stations in PC.3.2) both the Standard Planning Data and the Detailed Planning Data as listed
in parts l and 2 of the Appendix. This data should be submitted in calendar week 24 of each year
(although Network Operators may delay the submission of data (other than that to be submitted
pursuant to PC.3.2(c) and PC.3.2(d)) until calendar week 28) and should cover each of the seven
succeeding Financial Years (and in certain instances, the current year). Where, from the date of
one submission to another, there is no change in the data (or in some of the data) to be
submitted, instead of re-submitting the data, a User may submit a written statement that there
has been no change from the data (or in some of the data) submitted the previous time. In
addition, NGET will also use the Transmission Entry Capacity and Connection Entry Capacity
data from the CUSC Contract, and any data submitted by Network Operators in relation to an
Embedded Medium Power Station not subject to a Bilateral Agreement or Embedded DC
Converter Station not subject to a Bilateral Agreement, in the preparation of the Seven Year
Statement and to that extent the data will not be treated as confidential.
PC.4.3.2 Network Data
To enable Users to model the National Electricity Transmission System in relation to short
circuit current contributions, NGET is required to submit to Users the Network Data as listed in
Part 3 of the Appendix. The data will be submitted in week 42 of each year and will cover that
Financial Year.
PC.4.3.3 To enable Users to model the National Electricity Transmission System in relation to OTSUA,
NGET is required to submit to Users the Network Data as listed in Part 3 of Appendix A and
Appendix F. NGET shall provide the Network Data with the offer of a CUSC Contract in the case
of the data in PC F2.1 and otherwise in accordance with the OTSDUW Development and Data
Timetable.
PC.4.4 Offer of Terms for Connection
PC.4.4.1 CUSC Contract Data Requirements/Offer Timing
The completed application form for a CUSC Contract to be submitted by a User when making an
application for a CUSC Contract will include:
(a) a description of the Plant and/or Apparatus (excluding OTSDUW Plant and Apparatus) to
be connected to the National Electricity Transmission System or of the Modification
relating to the User's Plant and/or Apparatus (and prior to the OTSUA Transfer Time, any
OTSUA) already connected to the National Electricity Transmission System or, as the
case may be, of the proposed new connection or Modification to the connection within the
User System of the User, each of which shall be termed a "User Development" in the PC;
(b) the relevant Standard Planning Data as listed in Part 1 of the Appendix (except in respect
of any OTSUA); and
(c) the desired Completion Date of the proposed User Development.
(d) the desired Connection Entry Capacity and Transmission Entry Capacity.
The completed application form for a CUSC Contract will be sent to NGET as more particularly
provided in the application form.

Issue 5 Revision 15 PC 03 February 2016


8 of 72
PC.4.4.2 Any offer of a CUSC Contract will provide that it must be accepted by the applicant User within
the period stated in the offer, after which the offer automatically lapses. Except as provided in the
CUSC Contract, acceptance of the offer renders the National Electricity Transmission System
works relating to that User Development, reflected in the offer, committed and binds both parties
to the terms of the offer. The User shall then provide the Detailed Planning Data as listed in Part
2 of the Appendix (and in the case of OTSUA the Standard Planning Data as listed in Part 1 of
Appendix A within the timeline provided in PC.A.1.4). In respect of DPD I this shall generally be
provided within 28 days (or such shorter period as NGET may determine, or such longer period
as NGET may agree, in any particular case) of acceptance of the offer and in respect of DPD II
this shall generally be provided at least two years (or such longer period as NGET may
determine, or such shorter period as NGET may agree, in any particular case or in the case of
OTSUA such shorter period as NGET shall require) prior to the Completion Date of the User
Development.
PC.4.4.3 Embedded Development Agreement - Data Requirements
The Network Operator shall submit the following data in relation to an Embedded Medium
Power Station not subject to, or proposed to be subject to, a Bilateral Agreement or Embedded
DC Converter Station not subject to, or proposed to be subject to, a Bilateral Agreement as
soon as reasonably practicable after receipt of an application from an Embedded Person to
connect to its System:
(a) details of the proposed new connection or variation (having a similar effect on the Network
Operators System as a Modification would have on the National Electricity
Transmission System) to the connection within the Network Operators System, each of
which shall be termed an Embedded Development in the PC (where a User
Development has an impact on the Network Operators System details shall be supplied
in accordance with PC.4.4 and PC.4.5);
(b) the relevant Standard Planning Data as listed in Part 1 of the Appendix;
(c) the proposed completion date (having a similar meaning in relation to the Network
Operators System as Completion Date would have in relation to the National Electricity
Transmission System) of the Embedded Development; and
(d) upon the request of NGET, the relevant Detailed Planning Data as listed in Part 2 of the
Appendix.
PC.4.4.4 The Network Operator shall provide the Detailed Planning Data as listed in Part 2 of the
Appendix. In respect of DPD I this shall generally be provided within 28 days (or such shorter
period as NGET may determine, or such longer period as NGET may agree, in any particular
case) of entry into the Embedded Development Agreement and in respect to DPD II this shall
generally be provided at least two years (or such longer period as NGET may determine, or such
shorter period as NGET may agree, in any particular case) prior to the Completion Date of the
Embedded Development.
PC.4.5 Complex Connections
PC.4.5.1 The magnitude and complexity of any National Electricity Transmission System extension or
reinforcement will vary according to the nature, location and timing of the proposed User
Development which is the subject of the application and it may, in the event, be necessary for
NGET to carry out additional more extensive system studies to evaluate more fully the impact of
the proposed User Development on the National Electricity Transmission System. Where
NGET judges that such additional more detailed studies are necessary the offer may indicate the
areas that require more detailed analysis and before such additional studies are required, the
User shall indicate whether it wishes NGET to undertake the work necessary to proceed to make
a revised offer within the 3 month period normally allowed or, where relevant, the timescale
consented to by the Authority.
PC.4.5.2 To enable NGET to carry out any of the above mentioned necessary detailed system studies, the
User may, at the request of NGET, be required to provide some or all of the Detailed Planning
Data listed in part 2 of the Appendix in advance of the normal timescale referred in PC.4.4.2
provided that NGET can reasonably demonstrate that it is relevant and necessary.

Issue 5 Revision 15 PC 03 February 2016


9 of 72
PC.4.5.3 To enable NGET to carry out any necessary detailed system studies, the relevant Network
Operator may, at the request of NGET, be required to provide some or all of the Detailed
Planning Data listed in Part 2 of the Appendix in advance of the normal timescale referred in
PC.4.4.4 provided that NGET can reasonably demonstrate that it is relevant and necessary.

PC.5 PLANNING DATA


PC.5.1 As far as the PC is concerned, there are three relevant levels of data in relation to Users. These
levels, which relate to levels of confidentiality, commitment and validation, are described in the
following paragraphs.
Preliminary Project Planning Data
PC.5.2 At the time the User applies for a CUSC Contract but before an offer is made and accepted by
the applicant User, the data relating to the proposed User Development will be considered as
Preliminary Project Planning Data. Data relating to an Embedded Development provided by a
Network Operator in accordance with PC.4.4.3, and PC.4.4.4 if requested, will be considered as
Preliminary Project Planning Data. All such data will be treated as confidential within the scope
of the provisions relating to confidentiality in the CUSC.
PC.5.3 Preliminary Project Planning Data will normally only contain the Standard Planning Data
unless the Detailed Planning Data is required in advance of the normal timescale to enable
NGET to carry out additional detailed system studies as described in PC.4.5.
Committed Project Planning Data
PC.5.4 Once the offer for a CUSC Contract is accepted, the data relating to the User Development
already submitted as Preliminary Project Planning Data, and subsequent data required by
NGET under this PC, will become Committed Project Planning Data. Once an Embedded
Person has entered into an Embedded Development Agreement, as notified to NGET by the
Network Operator, the data relating to the Embedded Development already submitted as
Preliminary Project Planning Data, and subsequent data required by NGET under the PC, will
become Committed Project Planning Data. Such data, together with Connection Entry
Capacity and Transmission Entry Capacity data from the CUSC Contract and other data held
by NGET relating to the National Electricity Transmission System will form the background
against which new applications by any User will be considered and against which planning of the
National Electricity Transmission System will be undertaken. Accordingly, Committed Project
Planning Data, Connection Entry Capacity and Transmission Entry Capacity data will not be
treated as confidential to the extent that NGET:
(a) is obliged to use it in the preparation of the Seven Year Statement and in any further
information given pursuant to the Seven Year Statement;
(b) is obliged to use it when considering and/or advising on applications (or possible
applications) of other Users (including making use of it by giving data from it, both orally and
in writing, to other Users making an application (or considering or discussing a possible
application) which is, in NGET's view, relevant to that other application or possible
application);
(c) is obliged to use it for operational planning purposes;
(d) is obliged under the terms of an Interconnection Agreement to pass it on as part of system
information on the Total System;
(e) is obliged to disclose it under the STC;
(f) is obliged to use and disclose it in the preparation of the Offshore Development
Information Statement;
(g) is obliged to use it in order to carry out its EMR Functions or is obliged to disclose it under
an EMR Document.

Issue 5 Revision 15 PC 03 February 2016


10 of 72
To reflect different types of data, Preliminary Project Planning Data and Committed Project
Planning Data are themselves divided into:
(a) those items of Standard Planning Data and Detailed Planning Data which will always be
forecast, known as Forecast Data; and
(b) those items of Standard Planning Data and Detailed Planning Data which relate to Plant
and/or Apparatus which upon connection will become Registered Data, but which prior to
connection, for the seven succeeding Financial Years, will be an estimate of what is
expected, known as Estimated Registered Data.
Connected Planning Data
PC.5.5 The PC requires that, at the time that a Statement of Readiness is submitted under the Bilateral
Agreement and/or Construction Agreement, any estimated values assumed for planning
purposes are confirmed or, where practical, replaced by validated actual values and by updated
estimates for the future and by updated forecasts for forecast data items such as Demand. In
the case of an Embedded Development the relevant Network Operator will update any
estimated values assumed for planning purposes with validated actual values as soon as
reasonably practicable after energisation. This data is then termed Connected Planning Data.
To reflect the three types of data referred to above, Connected Planning Data is itself divided
into:
(a) those items of Standard Planning Data and Detailed Planning Data which will always be
forecast data, known as Forecast Data; and
(b) those items of Standard Planning Data and Detailed Planning Data which upon
connection become fixed (subject to any subsequent changes), known as Registered Data;
and
(c) those items of Standard Planning Data and Detailed Planning Data which for the purposes
of the Plant and/or Apparatus concerned as at the date of submission are Registered Data
but which for the seven succeeding Financial Years will be an estimate of what is expected,
known as Estimated Registered Data,
as more particularly provided in the Appendix.
PC.5.6 Connected Planning Data, together with Connection Entry Capacity and Transmission Entry
Capacity data from the CUSC Contract, and other data held by NGET relating to the National
Electricity Transmission System, will form the background against which new applications by
any User will be considered and against which planning of the National Electricity
Transmission System will be undertaken. Accordingly, Connected Planning Data, Connection
Entry Capacity and Transmission Entry Capacity data will not be treated as confidential to the
extent that NGET:
(a) is obliged to use it in the preparation of the Seven Year Statement and in any further
information given pursuant to the Seven Year Statement;
(b) is obliged to use it when considering and/or advising on applications (or possible
applications) of other Users (including making use of it by giving data from it, both orally and
in writing, to other Users making an application (or considering or discussing a possible
application) which is, in NGET's view, relevant to that other application or possible
application);
(c) is obliged to use it for operational planning purposes;
(d) is obliged under the terms of an Interconnection Agreement to pass it on as part of system
information on the Total System.
(e) is obliged to disclose it under the STC;
(f) is obliged to use it in order to carry out its EMR Functions or is obliged to disclose it under
an EMR Document.

Issue 5 Revision 15 PC 03 February 2016


11 of 72
PC.5.7 Committed Project Planning Data and Connected Planning Data will each contain both
Standard Planning Data and Detailed Planning Data.

Issue 5 Revision 15 PC 03 February 2016


12 of 72
PC.6 PLANNING STANDARDS
PC.6.1 NGET shall apply the Licence Standards relevant to planning and development, in the planning
and development of its Transmission System. NGET shall procure that each Relevant
Transmission Licensee shall apply the Licence Standards relevant to planning and
development, in the planning and development of the Transmission System of each Relevant
Transmission Licensee and that a User shall apply the Licence Standards relevant to planning
and development, in the planning and development of the OTSUA.
PC.6.2 In relation to Scotland, Appendix C lists the technical and design criteria applied in the planning
and development of each Relevant Transmission Licensee's Transmission System. The
criteria are subject to review in accordance with each Relevant Transmission Licensees
Transmission Licence conditions. Copies of these documents are available from NGET on
request. NGET will charge an amount sufficient to recover its reasonable costs incurred in
providing this service.
PC.6.3 In relation to Offshore, Appendix E lists the technical and design criteria applied in the planning
and development of each Offshore Transmission System. The criteria are subject to review in
accordance with each Offshore Transmission Licensees Transmission Licence conditions.
Copies of these documents are available from NGET on request. NGET will charge an amount
sufficient to recover its reasonable costs incurred in providing this service.
PC.6.4 In planning and developing the OTSUA, the User shall comply with (and shall ensure that (as at
the OTSUA Transfer Time) the OTSUA comply with):
(a) the Licence Standards; and
(b) the technical and design criteria in Appendix E.
PC.6.5 In addition the User shall, in the planning and development of the OTSUA, to the extent it is
reasonable and practicable to do so, take into account the reasonable requests of NGET (in the
context of its obligation to develop an efficient, co-ordinated and economical system) relating to
the planning and development of the National Electricity Transmission System.
PC.6.6 In planning and developing the OTSUA the User shall take into account the Network Data
provided to it by NGET under Part 3 of Appendix A and Appendix F, and act on the basis that the
Plant and Apparatus of other Users complies with:
(a) the minimum technical design and operational criteria and performance requirements set out
in CC.6.1, CC.6.2, CC.6.3 and CC.6.4; or
(b) such other criteria or requirements as NGET may from time to time notify the User are
applicable to specified Plant and Apparatus pursuant to PC.6.7.
PC.6.7 Where the OTSUA are likely to be materially affected by the design or operation of another
User's Plant and Apparatus and NGET:
(a) becomes aware that such other User has or is likely to apply for a derogation under the Grid
Code;
(b) is itself applying for a derogation under the Grid Code in relation to the Connection Site on
which such other User's Plant and Apparatus is located or to which it otherwise relates; or
(c) is otherwise notified by such other User that specified Plant or Apparatus is normally
capable of operating at levels better than those set out in CC.6.1, CC.6.2, CC.6.3 and
CC.6.4,
NGET shall notify the User.

Issue 5 Revision 15 PC 03 February 2016


13 of 72
PC.7 PLANNING LIAISON
PC.7.1 This PC.7 applies to NGET and Users, which in PC.7 means
(a) Network Operators
(b) Non-Embedded Customers
PC.7.2 As described in PC.2.1 (b) an objective of the PC is to provide for the supply of information to
NGET by Users in order that planning and development of the National Electricity
Transmission System can be undertaken in accordance with the relevant Licence Standards.
PC.7.3 Grid Code amendment B/07 (Amendment B/07) implemented changes to the Grid Code which
included amendments to the datasets provided by both NGET and Users to inform the planning
and development of the National Electricity Transmission System. The Authority has
determined that these changes are to have a phased implementation. Consequently the
provisions of Appendix A to the PC include specific years (ranging from 2009 to 2011) with effect
from which certain of the specific additional obligations brought about by Amendment B/07 on
NGET and Users are to take effect. Where specific provisions of paragraphs PC.A.4.1.4,
PC.A.4.2.2 and PC.A.4.3.1 make reference to a year, then the obligation on NGET and the Users
shall be required to be met by the relevant calendar week (as specified within such provision) in
such year.
In addition to the phased implementation of aspects of Amendment B/07, Users must discuss
and agree with NGET by no later than 31 March 2009 a more detailed implementation
programme to facilitate the implementation of Grid Code amendment B/07.
It shall also be noted by NGET and Users that the dates set out in PC.A.4 are intended to be
minimum requirements and are not intended to restrict a User and NGET from the earlier
fulfilment of the new requirements prior to the specified years. Where NGET and a User wish to
follow the new requirements from earlier dates than those specified, this will be set out in the
more detailed implementation programme agreed between NGET and the User.
The following provisions of PC.7 shall only apply with effect from 1 January 2011.
PC.7.4 Following the submission of data by a User in or after week 24 of each year NGET will provide
information to Users by calendar week 6 of the following year regarding the results of any
relevant assessment that has been made by NGET based upon such data submissions to verify
whether Connection Points are compliant with the relevant Licence Standards.
PC.7.5 Where the result of any assessment identifies possible future non-compliance with the relevant
Licence Standards NGET shall notify the relevant User(s) of this fact as soon as reasonably
practicable and shall agree with Users any opportunity to resubmit data to allow for a
reassessment in accordance with PC.7.6.
PC.7.6 Following any notification by NGET to a User pursuant to PC.7.5 and following any further
discussions held between the User and NGET:
(i) NGET and the User may agree revisions to the Access Periods for relevant Transmission
Interface Circuits, such revisions shall not however permit an Access Period to be less
than 4 continuous weeks in duration or to occur other than between calendar weeks 10 and
43 (inclusive); and/or,
(ii) The User shall as soon as reasonably practicable
(a) submit further relevant data to NGET that is to NGETs reasonable satisfaction; and/or,
(b) modify data previously submitted pursuant to this PC, such modified data to be to
NGETs reasonable satisfaction; and/or
(c) notify NGET that it is the intention of the User to leave the data as originally submitted
to NGET to stand as its submission.
PC.7.7 Where an Access Period is amended pursuant to PC.7.6 (i) NGET shall notify The Authority
that it has been necessary to do so.
PC.7.8 When it is agreed that any resubmission of data is unlikely to confirm future compliance with the
relevant Licence Standards the Modification process in the CUSC may apply.
Issue 5 Revision 15 PC 03 February 2016
14 of 72
PC.7.9 A User may at any time, in writing, request further specified National Electricity Transmission
System network data in order to provide NGET with viable User network data (as required under
this PC). Upon receipt of such request NGET shall consider, and where appropriate provide such
National Electricity Transmission System network data to the User as soon as reasonably
practicable following the request.

PC.8 OTSDUW PLANNING LIAISON


PC.8.1 This PC.8 applies to NGET and Users, which in PC.8 means Users undertaking OTSDUW
PC.8.2 As described in PC.2.1 (e) an objective of the PC is to provide for the supply of information
between NGET and a User undertaking OTSDUW in order that planning and development of the
National Electricity Transmission System can beco-ordinated.
PC.8.3 Where the OTSUA also require works to be undertaken by NGET and/or any Relevant
Transmission Licensee on its Transmission System NGET and the User shall throughout the
construction and commissioning of such works:
(a) co-operate and assist each other in the development of co-ordinated construction
programmes or any other planning or, in the case of NGET, analysis it undertakes in respect
of the works; and
(b) provide to each other all information relating to its own works (and in the case of NGET the
works on other Transmission Systems) reasonably necessary to assist each other in the
performance of that other's part of the works, and shall use all reasonable endeavours to co-
ordinate and integrate their respective part of the works; and
the User shall plan and develop the OTSUA, taking into account to the extent that it is
reasonable and practicable to do so the reasonable requests of NGET relating to the planning
and development of the National Electricity Transmission System.
PC.8.4 Where NGET becomes aware that changes made to the investment plans of NGET and any
Relevant Transmission Licensee may have a material effect on the OTSUA, NGET shall notify
the User and provide the User with the necessary information about the relevant Transmission
Systems sufficient for the User to assess the impact on the OTSUA.

Issue 5 Revision 15 PC 03 February 2016


15 of 72
APPENDIX A - PLANNING DATA REQUIREMENTS

PC.A.1 INTRODUCTION
PC.A.1.1 The Appendix specifies data requirements to be submitted to NGET by Users, and in certain
circumstances to Users by NGET.
PC.A.1.2 Submissions by Users
(a) Planning data submissions by Users shall be:
(i) with respect to each of the seven succeeding Financial Years (other than in the case
of Registered Data which will reflect the current position and data relating to Demand
forecasts which relates also to the current year);
(ii) provided by Users in connection with a CUSC Contract (PC.4.1, PC.4.4 and PC.4.5
refer);
(iii) provided by Users on a routine annual basis in calendar week 24 of each year to
maintain an up-to-date data bank (although Network Operators may delay the
submission of data (other than that to be submitted pursuant to PC.3.2(c) and
PC.3.2(d)) until calendar week 28). Where from the date of one annual submission to
another there is no change in the data (or in some of the data) to be submitted, instead
of re-submitting the data, a User may submit a written statement that there has been
no change from the data (or some of the data) submitted the previous time; and
(iv) provided by Network Operators in connection with Embedded Development (PC.4.4
refers).
(b) Where there is any change (or anticipated change) in Committed Project Planning Data or
a significant change in Connected Planning Data in the category of Forecast Data or any
change (or anticipated change) in Connected Planning Data in the categories of
Registered Data or Estimated Registered Data supplied to NGET under the PC,
notwithstanding that the change may subsequently be notified to NGET under the PC as
part of the routine annual update of data (or that the change may be a Modification under
the CUSC), the User shall, subject to PC.A.3.2.3 and PC.A.3.2.4, notify NGET in writing
without delay.
(c) The notification of the change will be in the form required under this PC in relation to the
supply of that data and will also contain the following information:
(i) the time and date at which the change became, or is expected to become, effective;
(ii) if the change is only temporary, an estimate of the time and date at which the data will
revert to the previous registered form.
(d) The routine annual update of data, referred to in (a)(iii) above, need not be submitted in
respect of Small Power Stations or Embedded installations of direct current converters
which do not form a DC Converter Station (except as provided in PC.3.2.(c)), or unless
specifically requested by NGET, or unless otherwise specifically provided.
PC.A.1.3 Submissions by NGET
Network Data release by NGET shall be:
(a) with respect to the current Financial Year;
(b) provided by NGET on a routine annual basis in calendar week 42 of each year. Where from
the date of one annual submission to another there is no change in the data (or in some of
the data) to be released, instead of repeating the data, NGET may release a written
statement that there has been no change from the data (or some of the data) released the
previous time.
The three parts of the Appendix
PC.A.1.4 The data requirements listed in this Appendix are subdivided into the following four parts:
(a) Standard Planning Data
Issue 5 Revision 15 PC 03 February 2016
16 of 72
This data (as listed in Part 1 of the Appendix) is first to be provided by a User at the time of
an application for a CUSC Contract or in accordance with PC.4.4.3. It comprises data
which is expected normally to be sufficient for NGET to investigate the impact on the
National Electricity Transmission System of any User Development or Embedded
Development associated with an application by the User for a CUSC Contract. Users
should note that the term Standard Planning Data also includes the information referred to
in PC.4.4.1.(a) and PC.4.4.3.(a). In the case of OTSUA, this data is first to be provided by a
User in accordance with the time line in Appendix F.
(b) Detailed Planning Data
This data (as listed in Part 2 of the Appendix) includes both DPD I and DPD II and is to be
provided in accordance with PC.4.4.2 and PC.4.4.4. It comprises additional, more detailed,
data not normally expected to be required by NGET to investigate the impact on the
National Electricity Transmission System of any User Development associated with an
application by the User for a CUSC Contract or Embedded Development Agreement.
Users and Network Operators in respect of Embedded Developments should note that
the term Detailed Planning Data also includes Operation Diagrams and Site Common
Drawings produced in accordance with the CC.
The User may, however, be required by NGET to provide the Detailed Planning Data in
advance of the normal timescale before NGET can make an offer for a CUSC Contract, as
explained in PC.4.5.
(c) Network Data
The data requirements for NGET in this Appendix are in Part 3.
(d) Offshore Transmission System (OTSDUW) Data
Generators who are undertaking OTSDUW are required to submit data in accordance with
Appendix A as summarised in Schedule 18 of the Data Registration Code.

Forecast Data, Registered Data and Estimated Registered Data


PC.A.1.5 As explained in PC.5.4 and PC.5.5, Planning Data is divided into:
(i) those items of Standard Planning Data and Detailed Planning Data known as Forecast
Data; and
(ii) those items of Standard Planning Data and Detailed Planning Data known as Registered
Data; and
(iii) those items of Standard Planning Data and Detailed Planning Data known as Estimated
Registered Data.
PC.A.1.6 The following paragraphs in this Appendix relate to Forecast Data:
3.2.2(b), (h), (i) and (j)
4.2.1
4.3.1
4.3.2
4.3.3
4.3.4
4.3.5
4.5
4.7.1
5.2.1
5.2.2
5.6.1
Issue 5 Revision 15 PC 03 February 2016
17 of 72
PC.A.1.7 The following paragraphs in this Appendix relate to Registered Data and Estimated Registered
Data:
2.2.1
2.2.4
2.2.5
2.2.6
2.3.1
2.4.1
2.4.2
3.2.2(a), (c), (d), (e), (f), (g), (i)(part) and (j)
3.4.1
3.4.2
4.2.3
4.5(a)(i), (a)(iii), (b)(i) and (b)(iii)
4.6
5.3.2
5.4
5.4.2
5.4.3
5.5
5.6.3
6.2
6.3
PC.A.1.8 The data supplied under PC.A.3.3.1, although in the nature of Registered Data, is only supplied
either upon application for a CUSC Contract, or in accordance with PC.4.4.3, and therefore does
not fall to be Registered Data, but is Estimated Registered Data.
PC.A.1.9 Forecast Data must contain the User's best forecast of the data being forecast, acting as a
reasonable and prudent User in all the circumstances.
PC.A.1.10 Registered Data must contain validated actual values, parameters or other information (as the
case may be) which replace the estimated values, parameters or other information (as the case
may be) which were given in relation to those data items when they were Preliminary Project
Planning Data and Committed Project Planning Data, or in the case of changes, which replace
earlier actual values, parameters or other information (as the case may be). Until amended
pursuant to the Grid Code, these actual values, parameters or other information (as the case
may be) will be the basis upon which the National Electricity Transmission System is planned,
designed, built and operated in accordance with, amongst other things, the Transmission
Licences, the STC and the Grid Code, and on which NGET therefore relies. In following the
processes set out in the BC, NGET will use the data which has been supplied to it under the BC
and the data supplied under OC2 in relation to Gensets, but the provision of such data will not
alter the data supplied by Users under the PC, which may only be amended as provided in the
PC.
PC.A.1.11 Estimated Registered Data must contain the User's best estimate of the values, parameters or
other information (as the case may be), acting as a reasonable and prudent User in all the
circumstances.

Issue 5 Revision 15 PC 03 February 2016


18 of 72
PC.A.1.12 Certain data does not need to be supplied in relation to Embedded Power Stations or
Embedded DC Converter Stations where these are connected at a voltage level below the
voltage level directly connected to the National Electricity Transmission System except in
connection with a CUSC Contract, or unless specifically requested by NGET.
PC.A.1.13 In the case of OTSUA, Schedule 18 of the Data Registration Code shall be construed in such a
manner as to achieve the intent of such provisions by reference to the OTSUA and the Interface
Point and all Connection Points.

Issue 5 Revision 15 PC 03 February 2016


19 of 72
PART 1 - STANDARD PLANNING DATA

PC.A.2 USER'S SYSTEM (AND OTSUA) DATA


PC.A.2.1 Introduction
PC.A.2.1.1 Each User, whether connected directly via an existing Connection Point to the National
Electricity Transmission System, or seeking such a direct connection, or providing terms for
connection of an Offshore Transmission System to its User System to NGET, shall provide
NGET with data on its User System (and any OTSUA) which relates to the Connection Site
(and in the case of OTSUA, the Interface Point) and/or which may have a system effect on the
performance of the National Electricity Transmission System. Such data, current and forecast,
is specified in PC.A.2.2 to PC.A.2.5. In addition each Generator in respect of its Embedded
Large Power Stations and its Embedded Medium Power Stations subject to a Bilateral
Agreement and each Network Operator in respect of Embedded Medium Power Stations
within its System not subject to a Bilateral Agreement connected to the Subtransmission
System, shall provide NGET with fault infeed data as specified in PC.A.2.5.5 and each DC
Converter owner with Embedded DC Converter Stations subject to a Bilateral Agreement, or
Network Operator in the case of Embedded DC Converter Stations not subject to a Bilateral
Agreement, connected to the Subtransmission System shall provide NGET with fault infeed
data as specified in PC.A.2.5.6.
PC.A.2.1.2 Each User must reflect the system effect at the Connection Site(s) of any third party Embedded
within its User System whether existing or proposed.
PC.A.2.1.3 Although not itemised here, each User with an existing or proposed Embedded Small Power
Station, Embedded Medium Power Station or Embedded DC Converter Station with a
Registered Capacity of less than 100MW or an Embedded installation of direct current
converters which does not form a DC Converter Station in its User System may, at NGET's
reasonable discretion, be required to provide additional details relating to the User's System
between the Connection Site and the existing or proposed Embedded Small Power Station,
Embedded Medium Power Station or Embedded DC Converter Station or Embedded
installation of direct current converters which does not form a DC Converter Station.
PC.A.2.1.4 At NGETs reasonable request, additional data on the Users System (or OTSUA) will need to be
supplied. Some of the possible reasons for such a request, and the data required, are given in
PC.A.6.2, PC.A.6.4, PC.A.6.5 and PC.A.6.6.
PC.A.2.2 User's System (and OTSUA) Layout
PC.A.2.2.1 Each User shall provide a Single Line Diagram, depicting both its existing and proposed
arrangement(s) of load current carrying Apparatus relating to both existing and proposed
Connection Points (including in the case of OTSUA, Interface Points).
PC.A.2.2.2 The Single Line Diagram (three examples are shown in Appendix B) must include all parts of the
User System operating at Supergrid Voltage throughout Great Britain and, in Scotland and
Offshore, also all parts of the User System operating at 132kV, and those parts of its
Subtransmission System at any Transmission Site. In the case of OTSDUW, the Single Line
Diagram must also include the OTSUA. In addition, the Single Line Diagram must include all
parts of the Users Subtransmission System (and any OTSUA) throughout Great Britain
operating at a voltage greater than 50kV, and, in Scotland and Offshore, also all parts of the
Users Subtransmission System (and any OTSUA) operating at a voltage greater than 30kV,
which, under either intact network or Planned Outage conditions:-
(a) normally interconnects separate Connection Points, or busbars at a Connection Point
which are normally run in separate sections; or
(b) connects Embedded Large Power Stations, or Embedded Medium Power Stations, or
Embedded DC Converter Stations or Offshore Transmission Systems connected to the
Users Subtransmission System, to a Connection Point or Interface Point.

Issue 5 Revision 15 PC 03 February 2016


20 of 72
At the Users discretion, the Single Line Diagram can also contain additional details of the
Users Subtransmission System (and any OTSUA) not already included above, and also
details of the transformers connecting the Users Subtransmission System to a lower
voltage. With NGETs agreement, the Single Line Diagram can also contain information
about the Users System (and any OTSUA) at a voltage below the voltage of the
Subtransmission System.
The Single Line Diagram for a Power Park Module must include all parts of the System
connecting generating equipment to the Grid Entry Point (or User System Entry Point if
Embedded). As an alternative the User may choose to submit a Single Line Diagram with
the equipment between the equivalent Power Park Unit and the Common Collection
Busbar reduced to an electrically equivalent network. The format for a Single Line
Diagram for a Power Park Module electrically equivalent system is shown in Appendix B.
The Single Line Diagram must include the points at which Demand data (provided under
PC.A.4.3.4 and PC.A.4.3.5, or in the case of Generators, PC.A.5.) and fault infeed data
(provided under PC.A.2.5) are supplied.
PC.A.2.2.3 The above mentioned Single Line Diagram shall include:
(a) electrical circuitry (ie. overhead lines, identifying which circuits are on the same towers,
underground cables, power transformers, reactive compensation equipment and similar
equipment); and
(b) substation names (in full or abbreviated form) with operating voltages.
In addition, for all load current carrying Apparatus operating at Supergrid Voltage throughout
Great Britain and, in Scotland and Offshore, also at 132kV, (and any OTSUA) the Single Line
Diagram shall include:-
(a) circuit breakers
(b) phasing arrangements.
PC.A.2.2.3.1 For the avoidance of doubt, the Single Line Diagram to be supplied is in addition to the
Operation Diagram supplied pursuant to CC.7.4.
PC.A.2.2.4 For each circuit shown on the Single Line Diagram provided under PC.A.2.2.1, each User shall
provide the following details relating to that part of its User System and OTSUA:
Circuit Parameters:
Rated voltage (kV)
Operating voltage (kV)
Positive phase sequence reactance
Positive phase sequence resistance
Positive phase sequence susceptance
Zero phase sequence reactance (both self and mutual)
Zero phase sequence resistance (both self and mutual)
Zero phase sequence susceptance (both self and mutual)
In the case of a Single Line Diagram for a Power Park Module electrically equivalent
system the data should be on a 100MVA base. Depending on the equivalent system
supplied an equivalent tap changer range may need to be supplied. Similarly mutual values,
rated voltage and operating voltage may be inappropriate. Additionally in the case of
OTSUA, seasonal maximum continuous ratings and circuit lengths are to be provided in
addition to the data required under PC.A.2.2.4.

PC.A.2.2.5 For each transformer shown on the Single Line Diagram provided under PC.A.2.2.1, each User
(including those undertaking OTSDUW) shall provide the following details:
Rated MVA

Issue 5 Revision 15 PC 03 February 2016


21 of 72
Voltage Ratio
Winding arrangement
Positive sequence reactance (max, min and nominal tap)
Positive sequence resistance (max, min and nominal tap)
Zero sequence reactance
PC.A.2.2.5.1. In addition, for all interconnecting transformers between the User's Supergrid Voltage System
and the User's Subtransmission System throughout Great Britain and, in Scotland and
Offshore, also for all interconnecting transformers between the Users 132kV System and the
Users Subtransmission System (and any OTSUA) the User shall supply the following
information:-
Tap changer range
Tap change step size
Tap changer type: on load or off circuit
Earthing method: Direct, resistance or reactance
Impedance (if not directly earthed )
PC.A.2.2.6 Each User shall supply the following information about the Users equipment installed at a
Transmission Site (or in the case of OTSUA, all OTSDUW Plant and Apparatus):-
(a) Switchgear. For all circuit breakers:-
Rated voltage (kV)
Operating voltage (kV)
Rated 3-phase rms short-circuit breaking current, (kA)
Rated 1-phase rms short-circuit breaking current, (kA)
Rated 3-phase peak short-circuit making current, (kA)
Rated 1-phase peak short-circuit making current, (kA)
Rated rms continuous current (A)
DC time constant applied at testing of asymmetrical breaking abilities (secs)
In the case of OTSDUW Plant and Apparatus operating times for circuit breaker,
Protection, trip relay and total operating time should be provided.
(b) Substation Infrastructure. For the substation infrastructure (including, but not limited to,
switch disconnectors, disconnectors, current transformers, line traps, busbars, through
bushings, etc):-
Rated 3-phase rms short-circuit withstand current (kA)
Rated 1-phase rms short-circuit withstand current (kA).
Rated 3-phase short-circuit peak withstand current (kA)
Rated 1- phase short-circuit peak withstand current (kA)
Rated duration of short circuit withstand (secs)
Rated rms continuous current (A)
A single value for the entire substation may be supplied, provided it represents the most
restrictive item of current carrying apparatus.
PC.A.2.2.7 In the case of OTSUA the following should also be provided
(a) Automatic switching scheme schedules including diagrams and an explanation of how the
System will operate and what plant will be affected by the schemes Operation.

Issue 5 Revision 15 PC 03 February 2016


22 of 72
(b) Intertripping schemes both Generation and Demand. In each case a diagram of the
scheme and an explanation of how the System will operate and what Plant will be affected
by the schemes Operation.
PC.A.2.3 Lumped System Susceptance
PC.A.2.3.1 For all parts of the Users Subtransmission System (and any OTSUA) which are not included in
the Single Line Diagram provided under PC.A.2.2.1, each User shall provide the equivalent
lumped shunt susceptance at nominal Frequency.
PC.A.2.3.1.1 This should include shunt reactors connected to cables which are not normally in or out of service
independent of the cable (ie. they are regarded as part of the cable).
PC.A.2.3.1.2 This should not include:
(a) independently switched reactive compensation equipment connected to the User's System
specified under PC.A.2.4, or;
(b) any susceptance of the User's System inherent in the Demand (Reactive Power) data
specified under PC.A.4.3.1.
PC.A.2.4 Reactive Compensation Equipment
PC.A.2.4.1 For all independently switched reactive compensation equipment (including any OTSUA),
including that shown on the Single Line Diagram, not operated by NGET and connected to the
User's System at 132kV and above in England and Wales and 33kV and above in Scotland and
Offshore (including any OTSDUW Plant and Apparatus operating at High Voltage), other than
power factor correction equipment associated directly with Customers' Plant and Apparatus, the
following information is required:
(a) type of equipment (eg. fixed or variable);
(b) capacitive and/or inductive rating or its operating range in MVAr;
(c) details of any automatic control logic to enable operating characteristics to be determined;
(d) the point of connection to the User's System (including OTSUA) in terms of electrical
location and System voltage.
(e) In the case of OTSDUW Plant and Apparatus the User should also provide:-
(i) Connection node, voltage, rating, power loss, tap range and connection arrangement.
(ii) A mathematical representation in block diagram format to model the control of any
dynamic compensation plant. The model should be suitable for RMS dynamic stability
type studies where each time constant should be no less than 10ms.
(iii) For Static Var Compensation equipment the User should provide:
HV Node
LV Node
Control Node
Nominal Voltage (kV)
Target Voltage (kV)
Maximum MVAr at HV
Minimum MVAr at HV
Slope %
Voltage dependant Q Limit
Normal Running Mode
Postive and zero phase sequence resistance and reactance
Transformer winding type
Connection arrangements

Issue 5 Revision 15 PC 03 February 2016


23 of 72
PC.A.2.4.2 DC Converter Station owners (and a User where the OTSUA includes an OTSDUW DC
Converter) are also required to provide information about the reactive compensation and
harmonic filtering equipment required to ensure that their Plant and Apparatus (and the OTSUA)
complies with the criteria set out in CC.6.1.5.
PC.A.2.5 Short Circuit Contribution to National Electricity Transmission System
PC.A.2.5.1 General
(a) To allow NGET to calculate fault currents, each User is required to provide data, calculated
in accordance with Good Industry Practice, as set out in the following paragraphs of
PC.A.2.5.
(b) The data should be provided for the User's System with all Generating Units, Power Park
Units and DC Converters Synchronised to that User's System (and any OTSUA where
appropriate). The User must ensure that the pre-fault network conditions reflect a credible
System operating arrangement.
(c) The list of data items required, in whole or part, under the following provisions, is set out in
PC.A.2.5.6. Each of the relevant following provisions identifies which data items in the list
are required for the situation with which that provision deals.
The fault currents in sub-paragraphs (a) and (b) of the data list in PC.A.2.5.6 should be
based on an a.c. load flow that takes into account any pre-fault current flow across the Point
of Connection (and in the case of OTSUA, Interface Points and Connection Points) being
considered.
Measurements made under appropriate System conditions may be used by the User to
obtain the relevant data.
(d) NGET may at any time, in writing, specifically request for data to be provided for an
alternative System condition, for example minimum plant, and the User will, insofar as such
request is reasonable, provide the information as soon as reasonably practicable following
the request.
PC.A.2.5.2 Network Operators and Non-Embedded Customers are required to submit data in accordance
with PC.A.2.5.4. Generators, DC Converter Station owners and Network Operators, in
respect of Embedded Medium Power Stations not subject to a Bilateral Agreement and
Embedded DC Converter Stations not subject to a Bilateral Agreement within such Network
Operators Systems are required to submit data in accordance with PC.A.2.5.5.
PC.A.2.5.3 Where prospective short-circuit currents on equipment owned, operated or managed by NGET
are close to the equipment rating, and in NGETs reasonable opinion more accurate calculations
of the prospective short circuit currents are required, then NGET will request additional data as
outlined in PC.A.6.6 below.
PC.A.2.5.4 Data from Network Operators and Non-Embedded Customers
PC.A.2.5.4.1 Data is required to be provided at each node on the Single Line Diagram provided under
PC.A.2.2.1 at which motor loads and/or Embedded Small Power Stations and/or Embedded
Medium Power Stations and/or Embedded installations of direct current converters which do
not form a DC Converter Station are connected, assuming a fault at that location, as follows:-

The data items listed under the following parts of PC.A.2.5.6:-


(a) (i), (ii), (iii), (iv), (v) and (vi);
and the data items shall be provided in accordance with the detailed provisions of PC.A.2.5.6(c) -
(f).
PC.A.2.5.4.2 Network Operators shall provide the following data items in respect of each Interface Point
within their User System:
(a) Maximum Export Capacity;
(b) Maximum Import Capacity; and,
(c) Interface Point Target Voltage/Power Factor
Issue 5 Revision 15 PC 03 February 2016
24 of 72
Network Operators shall alongside these parameters include details of any manual or automatic
post fault actions to be taken by the owner / operator of the Offshore Transmission System
connected to such Interface Point that are required by the Network Operator.
PC.A.2.5.5 Data from Generators (including Generators undertaking OTSDUW), DC Converter Station
owners and from Network Operators in respect of Embedded Medium Power Stations not subject
to a Bilateral Agreement and Embedded DC Converter Stations not subject to a Bilateral
Agreement within such Network Operators Systems.
PC.A.2.5.5.1 For each Generating Unit with one or more associated Unit Transformers, the Generator, or
the Network Operator in respect of Embedded Medium Power Stations not subject to a
Bilateral Agreement and Embedded DC Converter Stations not subject to a Bilateral
Agreement within such Network Operators System is required to provide values for the
contribution of the Power Station Auxiliaries (including Auxiliary Gas Turbines or Auxiliary
Diesel Engines) to the fault current flowing through the Unit Transformer(s).
The data items listed under the following parts of PC.A.2.5.6(a) should be provided:-
(i), (ii) and (v);
(iii) if the associated Generating Unit step-up transformer can supply zero phase
sequence current from the Generating Unit side to the National Electricity
Transmission System;
(iv) if the value is not 1.0 p.u;
and the data items shall be provided in accordance with the detailed provisions of PC.A.2.5.6(c) -
(f), and with the following parts of this PC.A.2.5.5.
PC.A.2.5.5.2 Auxiliary motor short circuit current contribution and any Auxiliary Gas Turbine Unit contribution
through the Unit Transformers must be represented as a combined short circuit current
contribution at the Generating Unit's terminals, assuming a fault at that location.
PC.A.2.5.5.3 If the Power Station or DC Converter Station (or OTSDUW Plant and Apparatus which
provides a fault infeed) has separate Station Transformers, data should be provided for the fault
current contribution from each transformer at its high voltage terminals, assuming a fault at that
location, as follows:-
The data items listed under the following parts of PC.A.2.5.6
(a) (i), (ii), (iii), (iv), (v) and (vi);
and the data items shall be provided in accordance with the detailed provisions of PC.A.2.5.6(b) -
(f).
PC.A.2.5.5.4 Data for the fault infeeds through both Unit Transformers and Station Transformers shall be
provided for the normal running arrangement when the maximum number of Generating Units
are Synchronised to the System or when all the DC Converters at a DC Converter Station are
transferring Rated MW in either direction. Where there is an alternative running arrangement (or
transfer in the case of a DC Converter Station) which can give a higher fault infeed through the
Station Transformers, then a separate data submission representing this condition shall be
made.
PC.A.2.5.5.5 Unless the normal operating arrangement within the Power Station is to have the Station and
Unit Boards interconnected within the Power Station, no account should be taken of the
interconnection between the Station Board and the Unit Board.
PC.A.2.5.5.6 Auxiliary motor short circuit current contribution and any auxiliary DC Converter Station
contribution through the Station Transformers must be represented as a combined short circuit
current contribution through the Station Transformers.
PC.A.2.5.5.7 Where a Manufacturers Data & Performance Report exists in respect of the model of the
Power Park Unit, the User may opt to reference the Manufacturers Data & Performance
Report as an alternative to the provision of data in accordance with this PC.A.2.5.5.7. For the
avoidance of doubt, all other data provision pursuant to the Grid Code shall still be provided
including a Single Line Diagram and those data pertaining thereto.

Issue 5 Revision 15 PC 03 February 2016


25 of 72
For each Power Park Module and each type of Power Park Unit (eg. Doubly Fed Induction
Generator) (and any OTSDUW Plant and Apparatus which provides a fault infeed), including
any Auxiliaries, positive, negative and zero sequence root mean square current values are to be
provided of the contribution to the short circuit current flowing at:
(i) the Power Park Unit terminals, or the Common Collection Busbar if an equivalent Single
Line Diagram and associated data as described in PC.A.2.2.2 is provided, and
(ii) the Grid Entry Point (and in case of OTSUA, Transmission Interface Point), or User
System Entry Point if Embedded
for the following solid faults at the Grid Entry Point (and in case of OTSUA, Interface Point), or
User System Entry Point if Embedded:
(i) a symmetrical three phase short circuit
(ii) a single phase to earth short circuit
(iii) a phase to phase short circuit
(iv) a two phase to earth short circuit
For a Power Park Module in which one or more of the Power Park Units utilise a protective
control such as a crowbar circuit, the data should indicate whether the protective control will act
in each of the above cases and the effects of its action shall be included in the data. For any
case in which the protective control will act, the data for the fault shall also be submitted for the
limiting case in which the protective circuit will not act, which may involve the application of a
non-solid fault, and the positive, negative and zero sequence retained voltages at
(i) the Power Park Unit terminals, or the Common Collection Busbar if an equivalent Single
Line Diagram and associated data is provided and
(ii) the Grid Entry Point, or User System Entry Point if Embedded
in this limiting case shall be provided.
For each fault for which data is submitted, the data items listed under the following parts of
PC.A.2.5.6(a) shall be provided:-
(iv), (vii), (viii), (ix), (x);

In addition, if an equivalent Single Line Diagram has been provided the data items listed under
the following parts of PC.A.2.5.6(a) shall be provided:-
(xi), (xii), (xiii);

In addition, for a Power Park Module in which one or more of the Power Park Units utilise a
protective control such as a crowbar circuit:-
the data items listed under the following parts of PC.A.2.5.6(a) shall be provided:-
(xiv), (xv);
All of the above data items shall be provided in accordance with the detailed provisions of
PC.A.2.5.6(c), (d), (f).
Should actual data in respect of fault infeeds be unavailable at the time of the application for a
CUSC Contract or Embedded Development Agreement, a limited subset of the data,
representing the maximum fault infeed that may result from all of the plant types being
considered, shall be submitted. This data will, as a minimum, represent the root mean square of
the positive, negative and zero sequence components of the fault current for both single phase
and three phase solid faults at the Grid Entry Point (or User System Entry Point if Embedded)
at the time of fault application and 50ms following fault application. Actual data in respect of fault
infeeds shall be submitted to NGET as soon as it is available, in line with PC.A.1.2
PC.A.2.5.6 Data Items

Issue 5 Revision 15 PC 03 February 2016


26 of 72
(a) The following is the list of data utilised in this part of the PC. It also contains rules on the
data which generally apply:-
(i) Root mean square of the symmetrical three-phase short circuit current infeed at the
instant of fault, (I1");
(ii) Root mean square of the symmetrical three-phase short circuit current after the
subtransient fault current contribution has substantially decayed, (I1');
(iii) the zero sequence source resistance and reactance values of the User's System as
seen from the node on the Single Line Diagram provided under PC.A.2.2.1 (or Station
Transformer high voltage terminals or Generating Unit terminals or DC Converter
terminals, as appropriate) consistent with the infeed described in PC.A.2.5.1.(b);
(iv) root mean square of the pre-fault voltage at which the maximum fault currents were
calculated;
(v) the positive sequence X/R ratio at the instant of fault;
(vi) the negative sequence resistance and reactance values of the User's System seen
from the node on the Single Line Diagram provided under PC.A.2.2.1 (or Station
Transformer high voltage terminals, or Generating Unit terminals or DC Converter
terminals if appropriate) if substantially different from the values of positive sequence
resistance and reactance which would be derived from the data provided above;
(vii) A continuous trace and a table showing the root mean square of the positive, negative
and zero sequence components of the short circuit current between zero and 140ms at
10ms intervals;
(viii) The Active Power (or Interface Point Capacity being exported pre-fault by the
OTSDUW Plant and Apparatus) being generated pre-fault by the Power Park Module
and by each type of Power Park Unit;
(ix) The reactive compensation shown explicitly on the Single Line Diagram that is
switched in;
(x) The Power Factor of the Power Park Module and of each Power Park Unit type;
(xi) The positive sequence X/R ratio of the equivalent at the Common Collection Busbar
or Interface Point in the case of OTSUA;
(xii) The minimum zero sequence impedance of the equivalent seen from the Common
Collection Busbar or Interface Point in the case of OTSUA ;
(xiii) The number of Power Park Units represented in the equivalent Power Park Unit;
(xiv) The additional rotor resistance and reactance (if any) that is applied to the Power Park
Unit under a fault condition;
(xv) A continuous trace and a table showing the root mean square of the positive, negative
and zero sequence components of the retained voltage at the fault point and Power
Park Unit terminals, or the Common Collection Busbar if an equivalent Single Line
Diagram and associated data as described in PC.A.2.2.2 is provided or Interface
Point in the case of OTSUA, representing the limiting case, which may involve the
application of a non-solid fault, required to not cause operation of the protective control;
(b) In considering this data, unless the User notifies NGET accordingly at the time of data
submission, NGET will assume that the time constant of decay of the subtransient fault
current corresponding to the change from I1" to I1', (T") is not significantly different from
40ms. If that assumption is not correct in relation to an item of data, the User must inform
NGET at the time of submission of the data.
(c) The value for the X/R ratio must reflect the rate of decay of the d.c. component that may be
present in the fault current and hence that of the sources of the initial fault current. All shunt
elements and loads must therefore be deleted from any system model before the X/R ratio is
calculated.
(d) In producing the data, the User may use "time step analysis" or "fixed-point-in-time analysis"
with different impedances.
Issue 5 Revision 15 PC 03 February 2016
27 of 72
(e) If a fixed-point-in-time analysis with different impedances method is used, then in relation to
the data submitted under (a) (i) above, the data will be required for "time zero" to give I 1".
The figure of 120ms is consistent with a decay time constant T" of 40ms, and if that figure is
different, then the figure of 120ms must be changed accordingly.
(f) Where a "time step analysis" is carried out, the X/R ratio may be calculated directly from the
rate of decay of the d.c. component. The X/R ratio is not that given by the phase angle of
the fault current if this is based on a system calculation with shunt loads, but from the
Thvenin equivalent of the system impedance at the instant of fault with all non-source
shunts removed.

PC.A.3 GENERATING UNIT AND DC CONVERTER DATA


PC.A.3.1 Introduction
Directly Connected
PC.A.3.1.1 Each Generator and DC Converter Station owner (and a User where the OTSUA includes an
OTSDUW DC Converter) with an existing, or proposed, Power Station or DC Converter Station
directly connected, or to be directly connected, to the National Electricity Transmission System
(or in the case of OTSUA, the Interface Point), shall provide NGET with data relating to that
Power Station or DC Converter Station, both current and forecast, as specified in PC.A.3.2 to
PC.A.3.4.
Embedded
PC.A.3.1.2 (a) Each Generator and DC Converter Station owner in respect of its existing, and/or
proposed, Embedded Large Power Stations and/or Embedded DC Converter Stations
and/or its Embedded Medium Power Stations subject to a Bilateral Agreement and each
Network Operator in respect of its Embedded Medium Power Stations not subject to a
Bilateral Agreement and/or Embedded DC Converter Stations not subject to a Bilateral
Agreement within such Network Operators System in each case connected to the
Subtransmission System, shall provide NGET with data relating to that Power Station or
DC Converter Station, both current and forecast, as specified in PC.A.3.2 to PC.A.3.4.
(b) No data need be supplied in relation to any Small Power Station or any Medium Power
Station or installations of direct current converters which do not form a DC Converter
Station, connected at a voltage level below the voltage level of the Subtransmission
System except:-
(i) in connection with an application for, or under, a CUSC Contract, or
(ii) unless specifically requested by NGET under PC.A.3.1.4.
PC.A.3.1.3 (a) Each Network Operator shall provide NGET with the data specified in PC.A.3.2.2(c)(i)
and (ii) and PC.A.3.2.2(i).
(b) Network Operators need not submit planning data in respect of an Embedded Small
Power Station unless required to do so under PC.A.1.2(b) or unless specifically requested
under PC.A.3.1.4 below, in which case they will supply such data.
PC.A.3.1.4 (a) PC.A.4.2.4(b) and PC.A.4.3.2(a) explain that the forecast Demand submitted by each
Network Operator must be net of the output of all Small Power Stations and Medium
Power Stations and Customer Generating Plant and all installations of direct current
converters which do not form a DC Converter Station, Embedded within that Network
Operators System. The Network Operator must inform NGET of:
(i) the number of such Embedded Power Stations and such Embedded installations of
direct current converters (including the number of Generating Units or Power Park
Modules or DC Converters) together with their summated capacity; and
(ii) beginning from the 2015 Week 24 data submission, for each Embedded Small Power
Station of registered capacity (as defined in the Distribution Code) of 1MW or more:
1. A reference which is unique to each Network Operator;
2. The production type as follows:
Issue 5 Revision 15 PC 03 February 2016
28 of 72
a) In the case of an Embedded Small Power Station first connected on or
after 1 January 2015, the production type must be selected from the list
below derived from the Manual of Procedures for the ENTSO-E Central
Information Transparency Platform:
- Biomass;
- Fossil brown coal/lignite;
- Fossil coal-derived gas;
- Fossil gas;
- Fossil hard coal;
- Fossil oil;
- Fossil oil shale;
- Fossil peat;
- Geothermal;
- Hydro pumped storage;
- Hydro run-of-river and poundage;
- Hydro water reservoir;
- Marine;
- Nuclear;
- Other renewable;
- Solar;
- Waste;
- Wind offshore;
- Wind onshore; or
- Other;
together with a statement as to whether the generation forms part of a
CHP scheme;
b) In the case of an Embedded Small Power Station first connected to the
Users System before 1 January 2015, as an alternative to the
production type, the technology type(s) used, selected from the list set
out at paragraph 2.23 in Version 2 of the Regulatory Instructions and
Guidance relating to the distributed generation incentive, innovation
funding incentive and registered power zones, reference 83/07,
published by Ofgem in April 2007;
3. The registered capacity (as defined in the Distribution Code) in MW;
4. The lowest voltage level node that is specified on the most up-to-date Single Line
Diagram to which it connects or where it will export most of its power;
5. Where it generates electricity from wind or PV, the geographical location using
either latitude or longitude or grid reference coordinates of the primary or higher
voltage substation to which it connects;
6. The reactive power and voltage control mode, including the voltage set-point and
reactive range, where it operates in voltage control mode, or the target Power
Factor, where it operates in Power Factor mode;
7. Details of the types of loss of mains Protection in place and their relay settings
which in the case of Embedded Small Power Stations first connected to the
Users System before 1 January 2015 shall be provided on a reasonable
endeavours basis.

Issue 5 Revision 15 PC 03 February 2016


29 of 72
(b) On receipt of this data, the Network Operator or Generator (if the data relates to Power
Stations referred to in PC.A.3.1.2) may be further required, at NGET's reasonable
discretion, to provide details of Embedded Small Power Stations and Embedded Medium
Power Stations and Customer Generating Plant and Embedded installations of direct
current converters which do not form a DC Converter Station, both current and forecast, as
specified in PC.A.3.2 to PC.A.3.4. Such requirement would arise where NGET reasonably
considers that the collective effect of a number of such Embedded Power Stations and
Customer Generating Plants and Embedded installations of direct current converters may
have a significant system effect on the National Electricity Transmission System.
Busbar Arrangements
PC.A.3.1.5 Where Generating Units, which term includes CCGT Units and Power Park Modules, and DC
Converters, are connected to the National Electricity Transmission System via a busbar
arrangement which is or is expected to be operated in separate sections, the section of busbar to
which each Generating Unit, DC Converter or Power Park Module is connected is to be
identified in the submission.
PC.A.3.2 Output Data
PC.A.3.2.1 (a) Large Power Stations and Gensets
Data items PC.A.3.2.2 (a), (b), (c), (d), (e), (f) and (h) are required with respect to each
Large Power Station and each Generating Unit and Power Park Module of each Large
Power Station and for each Genset (although (a) is not required for CCGT Units and (b),
(d) and (e) are not normally required for CCGT Units and (a), (b), (c), (d), (e), (f) and (h) are
not normally required for Power Park Units).
(b) Embedded Small Power Stations and Embedded Medium Power Stations
Data item PC.A.3.2.2 (a) is required with respect to each Embedded Small Power Station
and Embedded Medium Power Station and each Generating Unit and Power Park
Module of each Embedded Small Power Station and Embedded Medium Power Station
(although (a) is not required for CCGT Units or Power Park Units).In addition, data item
PC.A.3.2.2(c)(ii) is required with respect to each Embedded Medium Power Station.
(c) CCGT Units/Modules
(i) Data item PC.A.3.2.2 (g) is required with respect to each CCGT Unit;
(ii) data item PC.A.3.2.2 (a) is required with respect to each CCGT Module; and
(iii) data items PC.A.3.2.2 (b), (c), (d) and (e) are required with respect to each CCGT
Module unless NGET informs the relevant User in advance of the submission that it
needs the data items with respect to each CCGT Unit for particular studies, in which
case it must be supplied on a CCGT Unit basis.
Where any definition utilised or referred to in relation to any of the data items does not
reflect CCGT Units, such definition shall be deemed to relate to CCGT Units for the
purposes of these data items. Any Schedule in the DRC which refers to these data items
shall be interpreted to incorporate the CCGT Unit basis where appropriate;
(d) Cascade Hydro Schemes
Data item PC.A.3.2.2(i) is required with respect to each Cascade Hydro Scheme.
(e) Power Park Units/Modules
Data items PC.A.3.2.2 (k) is required with respect to each Power Park Module.
(f) DC Converters
Data items PC.A.3.2.2 (a), (b), (c), (d) (e) (f) (h) and (i) are required with respect to each DC
Converter Station and each DC Converter in each DC Converter Station. For installations
of direct current converters which do not form a DC Converter Station only data item
PC.A.3.2.2.(a) is required.

Issue 5 Revision 15 PC 03 February 2016


30 of 72
PC.A.3.2.2 Items (a), (b), (d), (e), (f), (g), (h), (i), (j) and (k) are to be supplied by each Generator, DC
Converter Station owner or Network Operator (as the case may be) in accordance with
PC.A.3.1.1, PC.A.3.1.2, PC.A.3.1.3 and PC.A.3.1.4. Items (a), and (f)(iv) are to be supplied (as
applicable) by a User in the case of OTSUA which includes an OTSDUW DC Converter. Item (c)
is to be supplied by each Network Operator in all cases:-
(a) Registered Capacity (MW) or Interface Point Capacity in the case of OTSDUW;
(b) Output Usable (MW) on a monthly basis;
(c) (i) System Constrained Capacity (MW) ie. any constraint placed on the capacity of the
Embedded Generating Unit, Embedded Power Park Module, an Offshore
Transmission System at an Interface Point or DC Converter at an Embedded DC
Converter Station due to the Network Operators System in which it is Embedded.
Where Generating Units (which term includes CCGT Units), Power Park Modules,
Offshore Transmission Systems at an Interface Point or DC Converters are
connected to a Network Operators User System via a busbar arrangement which is
or is expected to be operated in separate sections, details of busbar running
arrangements and connected circuits at the substation to which the Embedded
Generating Unit, Embedded Power Park Module, Offshore Transmission System
at an Interface Point or Embedded DC Converter is connected sufficient for NGET to
determine where the MW generated by each Generating Unit, Power Park Module or
DC Converter at that Power Station or DC Converter Station or Offshore
Transmission System at an Interface Point would appear onto the National
Electricity Transmission System;
(ii) any Reactive Despatch Network Restrictions;
(d) Minimum Generation (MW);
(e) MW obtainable from Generating Units, Power Park Modules or DC Converters at a DC
Converter Station in excess of Registered Capacity;
(f) Generator Performance Chart:
(i) at the Onshore Synchronous Generating Unit stator terminals
(ii) at the electrical point of connection to the Offshore Transmission System for an
Offshore Synchronous Generating Unit.
(iii) at the electrical point of connection to the National Electricity Transmission System
(or User System if Embedded) for a Non Synchronous Generating Unit (excluding a
Power Park Unit), Power Park Module and DC Converter at a DC Converter
Station;
(iv) at the Interface Point for OTSDUW Plant and Apparatus
Where a Reactive Despatch Network Restriction applies, its existence and details should
be highlighted on the Generator Performance Chart, in sufficient detail for NGET to
determine the nature of the restriction.
(g) a list of the CCGT Units within a CCGT Module, identifying each CCGT Unit, and the
CCGT Module of which it forms part, unambiguously. In the case of a Range CCGT
Module, details of the possible configurations should also be submitted, together:-
(i) (in the case of a Range CCGT Module connected to the National Electricity
Transmission System) with details of the single Grid Entry Point (there can only be
one) at which power is provided from the Range CCGT Module;
(ii) (in the case of an Embedded Range CCGT Module) with details of the single User
System Entry Point (there can only be one) at which power is provided from the
Range CCGT Module;
Provided that, nothing in this sub-paragraph (g) shall prevent the busbar at the relevant point
being operated in separate sections;

Issue 5 Revision 15 PC 03 February 2016


31 of 72
(h) expected running regime(s) at each Power Station or DC Converter Station and type of
Generating Unit, eg. Steam Unit, Gas Turbine Unit, Combined Cycle Gas Turbine Unit,
Power Park Module, Novel Units (specify by type), etc;
(i) a list of Power Stations and Generating Units within a Cascade Hydro Scheme,
identifying each Generating Unit and Power Station and the Cascade Hydro Scheme
of which each form part unambiguously. In addition:
(i) details of the Grid Entry Point at which Active Power is provided, or if
Embedded the Grid Supply Point(s) within which the Generating Unit is
connected;
(ii) where the Active Power output of a Generating Unit is split between more than
one Grid Supply Points the percentage that would appear under normal and
outage conditions at each Grid Supply Point.
(j) The following additional items are only applicable to DC Converters at DC Converter
Stations.
Registered Import Capacity (MW);
Import Usable (MW) on a monthly basis;
Minimum Import Capacity (MW);
MW that may be absorbed by a DC Converter in excess of Registered Import
Capacity and the duration for which this is available;
(k) the number and types of the Power Park Units within a Power Park Module, identifying
each Power Park Unit, the Power Park Module of which it forms part and identifying the
BM Unit of which each Power Park Module forms part, unambiguously. In the case of a
Power Station directly connected to the National Electricity Transmission System with
multiple Power Park Modules where Power Park Units can be selected to run in different
Power Park Modules and/or Power Park Modules can be selected to run in different BM
Units, details of the possible configurations should also be submitted. In addition for
Offshore Power Park Modules, the number of Offshore Power Park Strings that are
aggregated into one Offshore Power Park Module should also be submitted.
PC.A.3.2.3 Notwithstanding any other provision of this PC, the CCGT Units within a CCGT Module, details
of which are required under paragraph (g) of PC.A.3.2.2, can only be amended in accordance
with the following provisions:-
(a) if the CCGT Module is a Normal CCGT Module, the CCGT Units within that CCGT Module
can only be amended such that the CCGT Module comprises different CCGT Units if NGET
gives its prior consent in writing. Notice of the wish to amend the CCGT Units within such a
CCGT Module must be given at least 6 months before it is wished for the amendment to
take effect;
(b) if the CCGT Module is a Range CCGT Module, the CCGT Units within that CCGT Module
and the Grid Entry Point at which the power is provided can only be amended as described
in BC1.A1.6.4.
PC.A.3.2.4 Notwithstanding any other provision of this PC, the Power Park Units within a Power Park
Module, and the Power Park Modules within a BM Unit, details of which are required under
paragraph (k) of PC.A.3.2.2, can only be amended in accordance with the following provisions:-
(a) if the Power Park Units within that Power Park Module can only be amended such that the
Power Park Module comprises different Power Park Units due to repair/replacement of
individual Power Park Units if NGET gives its prior consent in writing. Notice of the wish to
amend a Power Park Unit within such a Power Park Module must be given at least 4
weeks before it is wished for the amendment to take effect;

Issue 5 Revision 15 PC 03 February 2016


32 of 72
(b) if the Power Park Units within that Power Park Module and/or the Power Park Modules
within that BM Unit can be selected to run in different Power Park Modules and/or BM
Units as an alternative operational running arrangement the Power Park Units within the
Power Park Module, the BM Unit of which each Power Park Module forms part, and the
Grid Entry Point at which the power is provided can only be amended as described in
BC1.A.1.8.4.
PC.A.3.3. Rated Parameters Data
PC.A.3.3.1 The following information is required to facilitate an early assessment, by NGET, of the need for
more detailed studies;
(a) for all Generating Units (excluding Power Park Units) and Power Park Modules:
Rated MVA
Rated MW;
(b) for each Synchronous Generating Unit:
Short circuit ratio
Direct axis transient reactance;
Inertia constant (for whole machine), MWsecs/MVA;
(c) for each Synchronous Generating Unit step-up transformer:
Rated MVA
Positive sequence reactance (at max, min and nominal tap);
(d) for each DC Converter at a DC Converter Station or DC Converter connecting a Power
Park Module (including when forming part of OTSUA).
DC Converter type (e.g. current/voltage sourced)
Rated MW per pole for import and export
Number of poles and pole arrangement
Rated DC voltage/pole (kV)
Return path arrangement
Remote AC connection arrangement (excluding OTSDUW DC Converters)
(e) for each type of Power Park Unit in a Power Park Module not connected to the Total
System by a DC Converter:
Rated MVA
Rated MW
Rated terminal voltage
Inertia constant, (MWsec/MVA)
Additionally, for Power Park Units that are squirrel-cage or doubly-fed induction
generators driven by wind turbines:
Stator reactance.
Magnetising reactance.
Rotor resistance (at rated running)
Rotor reactance (at rated running)
The generator rotor speed range (minimum and maximum speeds in RPM) (for
doubly-fed induction generators only)
Converter MVA rating (for doubly-fed induction generators only)

Issue 5 Revision 15 PC 03 February 2016


33 of 72
For a Power Park Unit consisting of a synchronous machine in combination with a back-to-
back DC Converter, or for a Power Park Unit not driven by a wind turbine, the data to be
supplied shall be agreed with NGET in accordance with PC.A.7.
This information should only be given in the data supplied in accordance with PC.4.4 and PC.4.5.
PC.A.3.4 General Generating Unit Power Park Module and DC Converter Data
PC.A.3.4.1 The point of connection to the National Electricity Transmission System or the Total System,
if other than to the National Electricity Transmission System, in terms of geographical and
electrical location and system voltage is also required.
PC.A.3.4.2 (a) Type of Generating Unit (ie Synchronous Generating Unit, Non-Synchronous
Generating Unit, DC Converter or Power Park Module).
(b) In the case of a Synchronous Generating Unit details of the Exciter category, for example
whether it is a rotating Exciter or a static Exciter or in the case of a Non-Synchronous
Generating Unit the voltage control system.
(c) Whether a Power System Stabiliser is fitted.
PC.A.3.4.3 Each Generator shall supply NGET with the production type(s) used as the primary source of
power in respect of each Generating Unit, selected from the list set out below:
- Biomass
- Fossil brown coal/lignite
- Fossil coal-derived gas
- Fossil gas
- Fossil hard coal
- Fossil oil
- Fossil oil shale
- Fossil peat
- Geothermal
- Hydro pumped storage
- Hydro run-of-river and poundage
- Hydro water reservoir
- Marine
- Nuclear
- Other renewable
- Solar
- Waste
- Wind offshore
- Wind onshore
- Other

PC.A.4 DEMAND AND ACTIVE ENERGY DATA


PC.A.4.1 Introduction
PC.A.4.1.1 Each User directly connected to the National Electricity Transmission System with Demand
shall provide NGET with the Demand data, historic, current and forecast, as specified in
PC.A.4.2 and PC.A.4.3. Paragraphs PC.A.4.1.2 and PC.A.4.1.3 apply equally to Active Energy
requirements as to Demand unless the context otherwise requires.
PC.A.4.1.2 Data will need to be supplied by:
Issue 5 Revision 15 PC 03 February 2016
34 of 72
(a) each Network Operator, in relation to Demand and Active Energy requirements on its
User System;
(b) each Non-Embedded Customer (including Pumped Storage Generators with respect to
Pumping Demand) in relation to its Demand and Active Energy requirements.
(c) each DC Converter Station owner in relation to Demand and Active Energy transferred
(imported) to its DC Converter Station.
(d) each OTSDUW DC Converter in relation to the Demand at each Interface Point and
Connection Point.
Demand of Power Stations directly connected to the National Electricity Transmission
System is to be supplied by the Generator under PC.A.5.2.
PC.A.4.1.3 References in this PC to data being supplied on a half hourly basis refer to it being supplied for
each period of 30 minutes ending on the hour or half-hour in each hour.
PC.A.4.1.4 Access Periods and Access Groups
PC.A.4.1.4.1 Each Connection Point must belong to one, and only one, Access Group.
PC.A.4.1.4.2 Each Transmission Interface Circuit must have an Access Period.
PC.A.4.1.4.3 The Access Period shall
(a) normally be a minimum of 8 continuous weeks and can occur in any one of three
maintenance years during the period from calendar week 13 to calendar week 43 (inclusive)
in each year; or,
(b) exceptionally and provided that agreement is reached between NGET and the relevant
User(s), such agreement to be sought in accordance with PC.7, the Access Period may be
of a period not less than 4 continuous weeks and can occur in any one of three maintenance
years during the period from calendar week 10 to calendar week 43 (inclusive) in each year.
PC.A.4.1.4.4 NGET shall submit in writing no later than calendar week 6 in each year:
(a) the calendar weeks defining the proposed start and finish of each Access Period for each
Transmission Interface Circuit; and
(b) the Connection Points in each Access Group.
The submission by NGET under PC.A.4.1.4.4 (a) above shall commence in 2010 and shall then
continue each year thereafter. The submission by NGET under PC.A.4.1.4.4 (b) shall commence
in 2009 and then continue each year thereafter.
PC.A.4.1.4.5 It is permitted for Access Periods to overlap in the same Access Group and in the same
maintenance year. However, where possible Access Periods will be sought by NGET that do not
overlap with any other Access Period within that Access Group for each maintenance year.
Where it is not possible to avoid overlapping Access Periods, NGET will indicate to Users by
calendar week 6 its initial view of which Transmission Interface Circuits will need to be
considered out of service concurrently for the purpose of assessing compliance to Licence
Standards. The obligation on NGET to indicate which Transmission Interface Circuits will
need to be considered out of service concurrently for the purpose of assessing compliance to
Licence Standards shall commence in 2010 and shall continue each year thereafter.
PC.A.4.1.4.6 Following the submission(s) by NGET by week 6 in each year and where required by either party,
both NGET and the relevant User(s) shall use their reasonable endeavours to agree the
appropriate Access Group(s) and Access Period for each Transmission Interface Circuit prior
to week 17 in each year. The requirement on NGET and the relevant User(s) to agree, shall
commence in respect of Access Groups only in 2010. This paragraph PC.A.4.1.4.6 shall apply
in its entirety in 2011 and shall then continue each year thereafter.
PC.A.4.1.4.7 In exceptional circumstances, and with the agreement of all parties concerned, where a
Connection Point is specified for the purpose of the Planning Code as electrically independent
Subtransmission Systems, then data submissions can be on the basis of two (or more)
individual Connection Points.

Issue 5 Revision 15 PC 03 February 2016


35 of 72
PC.A.4.2 Users User System Demand (Active Power) and Active Energy Data
PC.A.4.2.1 Forecast daily Demand (Active Power) profiles, as specified in (a), (b) and (c) below, in respect
of each of the User's User Systems (each summated over all Grid Supply Points in each User
System) are required for:
(a) peak day on each of the User's User Systems (as determined by the User) giving the
numerical value of the maximum Demand (Active Power) that in the Users' opinion could
reasonably be imposed on the National Electricity Transmission System;
(b) day of peak National Electricity Transmission System Demand (Active Power) as
notified by NGET pursuant to PC.A.4.2.2;
(c) day of minimum National Electricity Transmission System Demand (Active Power) as
notified by NGET pursuant to PC.A.4.2.2.
In addition, the total Demand (Active Power) in respect of the time of peak National Electricity
Transmission System Demand in the preceding Financial Year in respect of each of the User's
User Systems (each summated over all Grid Supply Points in each User System) both outturn
and weather corrected shall be supplied.
PC.A.4.2.2 No later than calendar week 17 each year NGET shall notify each Network Operator and Non-
Embedded Customer in writing of the following, for the current Financial Year and for each of
the following seven Financial Years, which will, until replaced by the following years notification,
be regarded as the relevant specified days and times under PC.A.4.2.1:
(a)the date and time of the annual peak of the National Electricity Transmission System
Demand;
(b) the date and time of the annual minimum of the National Electricity Transmission System
Demand;
(c) the relevant Access Period for each Transmission Interface Circuit; and,
(d) Concurrent Access Periods of two or more Transmission Interface Circuits (if any) that
are situated in the same Access Group.
The submissions by NGET made under PC.A.4.2.1 (c) and PC.A.4.2.1 (d) above shall commence
in 2010 and shall then continue in respect of each year thereafter.
PC.A.4.2.3 The total Active Energy used on each of the Network Operators or Non-Embedded
Customers User Systems (each summated over all Grid Supply Points in each User System)
in the preceding Financial Year, both outturn and weather corrected, together with a prediction
for the current financial year, is required. Each Active Energy submission shall be subdivided
into the following categories of Customer tariff:
LV1
LV2
LV3
HV
EHV
Traction
Lighting
In addition, the total User System losses and the Active Energy provided by Embedded Small
Power Stations and Embedded Medium Power Stations shall be supplied.
PC.A.4.2.4 All forecast Demand (Active Power) and Active Energy specified in PC.A.4.2.1 and PC.A.4.2.3
shall:
(a) in the case of PC.A.4.2.1(a), (b) and (c), be such that the profiles comprise average Active
Power levels in 'MW' for each time marked half hour throughout the day;

Issue 5 Revision 15 PC 03 February 2016


36 of 72
(b) in the case of PC.A.4.2.1(a), (b) and (c), be that remaining after any deductions reasonably
considered appropriate by the User to take account of the output profile of all Embedded
Small Power Stations and Embedded Medium Power Stations and Customer
Generating Plant and imports across Embedded External Interconnections including
imports across Embedded installations of direct current converters which do not form a DC
Converter Station and Embedded DC Converter Stations with a Registered Capacity of
less than 100MW;
(c) be based upon Annual ACS Conditions for times that occur during week 44 through to
week 12 (inclusive) and based on Average Conditions for weeks 13 to 43 (inclusive).
PC.A.4.3 Connection Point Demand (Active and Reactive Power)
PC.A.4.3.1 Forecast Demand (Active Power) and Power Factor (values of the Power Factor at maximum
and minimum continuous excitation may be given instead where more than 95% of the total
Demand at a Connection Point is taken by synchronous motors) to be met at each Connection
Point within each Access Group is required for:
(a) the time of the maximum Demand (Active Power) at the Connection Point (as determined
by the User) that in the User's opinion could reasonably be imposed on the National
Electricity Transmission System;
(b) the time of peak National Electricity Transmission System Demand as provided by NGET
under PC.A.4.2.2;
(c) the time of minimum National Electricity Transmission System Demand as provided by
NGET under PC.A.4.2.2;
(d) the time of the maximum Demand (Apparent Power) at the Connection Point (as
determined by the User) during the Access Period of each Transmission Interface
Circuit;
(e) at a time specified by either NGET or a User insofar as such a request is reasonable.
Instead of such forecast Demand to be met at each Connection Point within each Access
Group the User may (subject to PC.A.4.3.4) submit such Demand at each node on the Single
Line Diagram.
In addition, the Demand in respect of each of the time periods referred to in PC.A.4.3.1 (a) to (e)
in the preceding Financial Year in respect of each Connection Point within each Access Group
both outturn and weather corrected shall be supplied. The weather correction shall normalise
outturn figures to Annual ACS Conditions for times that occur during calendar week 44 through
to calendar week 12 (inclusive) or Average Conditions for the period calendar weeks 13 to
calendar week 43 (inclusive) and shall be performed by the relevant User on a best endeavours
basis.
The submission by a User pursuant to PC.A.4.3.1 (d) shall commence in 2011 and shall then
continue each year thereafter.
PC.A.4.3.2 All forecast Demand specified in PC.A.4.3.1 shall:
(a) be that remaining after any deductions reasonably considered appropriate by the User to
take account of the output of all Embedded Small Power Stations and Embedded Medium
Power Stations and Customer Generating Plant and imports across Embedded External
Interconnections, including Embedded installations of direct current converters which do
not form a DC Converter Station and Embedded DC Converter Stations and such
deductions should be separately stated;
(b) include any User's System series reactive losses but exclude any reactive compensation
equipment specified in PC.A.2.4 and exclude any network susceptance specified in
PC.A.2.3;
(c) be based upon Annual ACS Conditions for times that occur during calendar week 44
through to calendar week 12 (inclusive) and based on Average Conditions for calendar
weeks 13 to calendar week 43 (inclusive), both corrections being made on a best
endeavours basis;

Issue 5 Revision 15 PC 03 February 2016


37 of 72
(d) reflect the Users opinion of what could reasonably be imposed on the National Electricity
Transmission System.
PC.A.4.3.3 The date and time of the forecast maximum Demand (Apparent Power) at the Connection
Point as specified in PC.A.4.3.1 (a) and (d) is required.
PC.A.4.3.4 Each Single Line Diagram provided under PC.A.2.2.2 shall include the Demand (Active Power)
and Power Factor (values of the Power Factor at maximum and minimum continuous excitation
may be given instead where more than 95% of the Demand is taken by synchronous motors) at
the time of the peak National Electricity Transmission System Demand (as provided under
PC.A.4.2.2) at each node on the Single Line Diagram. These Demands shall be consistent with
those provided under PC.A.4.3.1(b) above for the relevant year.
PC.A.4.3.5 The Single Line Diagram must represent the Users User System layout under the period
specified in PC.A.4.3.1(b) (at the time of peak National Electricity Transmission System
Demand). Should the Users User System layout during the other times specified in PC.A.4.3.1
be planned to be materially different from the Single Line Diagram submitted to NGET pursuant
to PC.A.2.2.1 the User shall in respect of such other times submit:
(i) an alternative Single Line Diagram that accurately reflects the revised layout and in such
case shall also include appropriate associated data representing the relevant changes, or;
(ii) submit an accurate and unambiguous description of the changes to the Single Line
Diagram previously submitted for the time of peak National Electricity Transmission
System Demand.
Where a User does not submit any changes, NGET will assume that the Single Line Diagram
(and associated circuit and node data) provided at the time of peak National Electricity
Transmission System Demand will be valid for all other times. In respect of such other times,
where the User does not submit such nodal demands at the times defined in PC.A.4.3.1(a), (c),
(d) and (e), the nodal demands will be pro-rata, to be consistent with the submitted Connection
Point Demands.
PC.A.4.4 NGET will assemble and derive in a reasonable manner, the forecast information supplied to it
under PC.A.4.2.1, PC.A.4.3.1, PC.A.4.3.4 and PC.A.4.3.5 above into a cohesive forecast and will
use this in preparing Forecast Demand information in the Seven Year Statement and for use in
NGET's Operational Planning. If any User believes that the cohesive forecast Demand
information in the Seven Year Statement does not reflect its assumptions on Demand, it should
contact NGET to explain its concerns and may require NGET, on reasonable request, to discuss
these forecasts. In the absence of such expressions, NGET will assume that Users concur with
NGET's cohesive forecast.
PC.A.4.5 Post Fault User System Layout
PC.A.4.5.1 Where for the purposes of NGET assessing against the Licence Standards an Access Group,
the User reasonably considers it appropriate that revised post fault User System layouts should
be taken into account by NGET, the following information is required to be submitted by the User:
(i) the specified Connection Point assessment period (PC.A.4.3.1,(a)-(e)) that is being
evaluated;
(ii) an accurate and unambiguous description of the Transmission Interface Circuits
considered to be switched out due to a fault;
(iii) appropriate revised Single Line Diagrams and/or associated revised nodal Demand and
circuit data detailing the revised User System(s) conditions;
(iv) where the Users planned post fault action consists of more than one component, each
component must be explicitly identified using the Single Line Diagram and associated nodal
Demand and circuit data;
(v) the arrangements for undertaking actions (eg the time taken, automatic or manual and any
other appropriate information);.

Issue 5 Revision 15 PC 03 February 2016


38 of 72
The User must not submit any action that it does not have the capability or the intention to
implement during the assessment period specified (subject to there being no further unplanned
outages on the Users User System).
PC.A.4.6 Control of Demand or Reduction of Pumping Load Offered as Reserve
Magnitude of Demand or pumping load which is tripped MW
System Frequency at which tripping is initiated Hz
Time duration of System Frequency below trip setting for tripping to s
be initiated
Time delay from trip initiation to tripping s

PC.A.4.7 General Demand Data


PC.A.4.7.1 The following information is infrequently required and should be supplied (wherever possible)
when requested by NGET:
(a) details of any individual loads which have characteristics significantly different from the
typical range of Domestic, Commercial or Industrial loads supplied;
(b) the sensitivity of the Demand (Active and Reactive Power) to variations in voltage and
Frequency on the National Electricity Transmission System at the time of the peak
Demand (Active Power). The sensitivity factors quoted for the Demand (Reactive Power)
should relate to that given under PC.A.4.3.1 and, therefore, include any User's System
series reactive losses but exclude any reactive compensation equipment specified in
PC.A.2.4 and exclude any network susceptance specified in PC.A.2.3;
(c) details of any traction loads, e.g. connection phase pairs and continuous load variation with
time;
(d) the average and maximum phase unbalance, in magnitude and phase angle, which the User
would expect its Demand to impose on the National Electricity Transmission System;
(e) the maximum harmonic content which the User would expect its Demand to impose on the
National Electricity Transmission System;
(f) details of all loads which may cause Demand fluctuations greater than those permitted
under Engineering Recommendation P28, Stage 1 at a Point of Common Coupling
including the Flicker Severity (Short Term) and the Flicker Severity (Long Term).

Issue 5 Revision 15 PC 03 February 2016


39 of 72
PART 2 - DETAILED PLANNING DATA

PC.A.5 GENERATING UNIT, POWER PARK MODULE, DC CONVERTER AND OTSDUW PLANT AND
APPARATUS DATA
PC.A.5.1 Introduction
Directly Connected
PC.A.5.1.1 Each Generator (including those undertaking OTSDUW), with existing or proposed Power
Stations directly connected, or to be directly connected, to the National Electricity
Transmission System, shall provide NGET with data relating to that Plant and Apparatus, both
current and forecast, as specified in PC.A.5.2, PC.A.5.3, PC.A.5.4 and PC.A.5.7 as applicable.
Each DC Converter Station owner, with existing or proposed DC Converter Stations (including
Generators undertaking OTSDUW which includes an OTSDUW DC Converter) directly
connected, or to be directly connected, to the National Electricity Transmission System, shall
provide NGET with data relating to that Plant and Apparatus, both current and forecast, as
specified in PC.A.5.2 and PC.A.5.4.
Embedded
PC.A.5.1.2 Each Generator, in respect of its existing, or proposed, Embedded Large Power Stations and
its Embedded Medium Power Stations subject to a Bilateral Agreement and each Network
Operator in respect of Embedded Medium Power Stations not subject to a Bilateral
Agreement within its System shall provide NGET with data relating to each of those Large
Power Stations and Medium Power Stations, both current and forecast, as specified in
PC.A.5.2, PC.A.5.3, PC.A.5.4 and PC.A.5.7 as applicable. Each DC Converter Station owner, or
Network Operator in the case of an Embedded DC Converter Station not subject to a Bilateral
Agreement within its System with existing or proposed DC Converter Stations shall provide
NGET with data relating to each of those DC Converter Stations, both current and forecast, as
specified in PC.A.5.2 and PC.A.5.4. However, no data need be supplied in relation to those
Embedded Medium Power Stations or Embedded DC Converter Stations if they are
connected at a voltage level below the voltage level of the Subtransmission System except in
connection with an application for, or under a, CUSC Contract or unless specifically requested by
NGET under PC.A.5.1.4.
PC.A.5.1.3 Each Network Operator need not submit Planning Data in respect of Embedded Small Power
Stations unless required to do so under PC.A.1.2(b), PC.A.3.1.4 or unless specifically requested
under PC.A.5.1.4 below, in which case they will supply such data.
PC.A.5.1.4 PC.A.4.2.4(b) and PC.A.4.3.2(a) explained that the forecast Demand submitted by each Network
Operator must be net of the output of all Medium Power Stations and Small Power Stations
and Customer Generating Plant Embedded within that User's System. In such cases, the
Network Operator must provide NGET with the relevant information specified under PC.A.3.1.4 .
On receipt of this data further details may be required at NGET's discretion as follows:
(i) in the case of details required from the Network Operator for Embedded Medium Power
Stations not subject to a Bilateral Agreement and Embedded DC Converter Stations not
subject to a Bilateral Agreement and Embedded Small Power Stations and Embedded
DC Converters in each case within such Network Operators System and Customer
Generating Plant; and
(ii) in the case of details required from the Generator of Embedded Large Power Stations and
Embedded Medium Power Stations subject to a Bilateral Agreement; and
(iii) in the case of details required from the DC Converter Station owner of an Embedded DC
Converter or DC Converter Station subject to a Bilateral Agreement.
both current and forecast, as specified in PC.A.5.2 and PC.A.5.3. Such requirement would arise
when NGET reasonably considers that the collective effect of a number of such Embedded
Small Power Stations, Embedded Medium Power Stations, Embedded DC Converter
Stations, DC Converters and Customer Generating Plants may have a significant system
effect on the National Electricity Transmission System.
PC.A.5.1.5 DPD I and DPD II
Issue 5 Revision 15 PC 03 February 2016
40 of 72
The Detailed Planning Data described in this Part 2 of the Appendix comprises both DPD I and
DPD II. The required data is listed and collated in the Data Registration Code. The Users need
to refer to the DRC to establish whether data referred to here is DPD I or DPD II.
PC.A.5.2 Demand
PC.A.5.2.1 For each Generating Unit which has an associated Unit Transformer, the value of the Demand
supplied through this Unit Transformer when the Generating Unit is at Rated MW output is to
be provided.
PC.A.5.2.2 Where the Power Station or DC Converter Station has associated Demand additional to the
unit-supplied Demand of PC.A.5.2.1 which is supplied from either the National Electricity
Transmission System or the Generator's User System the Generator, DC Converter Station
owner or the Network Operator (in the case of Embedded Medium Power Stations not subject
to a Bilateral Agreement within its System), as the case may be, shall supply forecasts for each
Power Station or DC Converter Station of:
(a) the maximum Demand that, in the User's opinion, could reasonably be imposed on the
National Electricity Transmission System or the Generator's User System as
appropriate;
(b) the Demand at the time of the peak National Electricity Transmission System Demand
(c) the Demand at the time of minimum National Electricity Transmission System Demand.
PC.A.5.2.3 No later than calendar week 17 each year NGET shall notify each Generator in respect of its
Large Power Stations and its Medium Power Stations and each DC Converter owner in
respect of its DC Converter Station subject to a Bilateral Agreement and each Network
Operator in respect of each Embedded Medium Power Station not subject to a Bilateral
Agreement and each Embedded DC Converter Station not subject to a Bilateral Agreement
within such Network Operators System in writing of the following, for the current Financial
Year and for each of the following seven Financial Years, which will be regarded as the relevant
specified days and times under PC.A.5.2.2:
(a) the date and time of the annual peak of the National Electricity Transmission System
Demand at Annual ACS Conditions;
(b) the date and time of the annual minimum of the National Electricity Transmission System
Demand at Average Conditions.
PC.A.5.2.4 At its discretion, NGET may also request further details of the Demand as specified in PC.A.4.6
PC.A.5.2.5 In the case of OTSDUW Plant and Apparatus the following data shall be supplied:
(a) The maximum Demand that could occur at the Interface Point and each Connection Point
(in MW and MVAr);
(b) Demand at specified time of annual peak half hour of National Electricity Transmission
System Demand at Annual ACS Conditions (in MW and MVAr); and
(c) Demand at specified time of annual minimum half-hour of National Electricity
Transmission System Demand (in MW and MVAr).

For the avoidance of doubt, Demand data associate(d with Generators undertaking OTSDUW
which utilise an OTSDUW DC Converter should supply data under PC.A.4.
PC.A.5.3 Synchronous Generating Unit and Associated Control System Data
PC.A.5.3.1 The data submitted below are not intended to constrain any Ancillary Services Agreement
PC.A.5.3.2 The following Synchronous Generating Unit and Power Station data should be supplied:
(a) Synchronous Generating Unit Parameters
Rated terminal volts (kV)
Maximum terminal voltage set point (kV)

Issue 5 Revision 15 PC 03 February 2016


41 of 72
Terminal voltage set point step resolution if not continuous (kV)
* Rated MVA
* Rated MW
* Minimum Generation MW
* Short circuit ratio
Direct axis synchronous reactance
* Direct axis transient reactance
Direct axis sub-transient reactance
Direct axis short-circuit transient time constant.
Direct axis short-circuit sub-transient time constant.
Quadrature axis synchronous reactance
Quadrature axis sub-transient reactance
Quadrature axis short-circuit sub-transient time constant.
Stator time constant
Stator leakage reactance
Armature winding direct-current resistance.
Note: The above data item relating to armature winding direct-current resistance
need only be supplied with respect to Generating Units commissioned after 1st
March 1996 and in cases where, for whatever reason, the Generator or the
Network Operator, as the case may be is aware of the value of the relevant
parameter.
* Turbogenerator inertia constant (MWsec/MVA)
Rated field current (amps) at Rated MW and MVAr output and at rated terminal
voltage.
Field current (amps) open circuit saturation curve for Generating Unit terminal
voltages ranging from 50% to 120% of rated value in 10% steps as derived from
appropriate manufacturers test certificates.
(b) Parameters for Generating Unit Step-up Transformers
* Rated MVA
Voltage ratio
* Positive sequence reactance (at max, min, & nominal tap)
Positive sequence resistance (at max, min, & nominal tap)
Zero phase sequence reactance
Tap changer range
Tap changer step size
Tap changer type: on load or off circuit
(c) Excitation Control System parameters

Issue 5 Revision 15 PC 03 February 2016


42 of 72
Note: The data items requested under Option 1 below may continue to be provided in
relation to Generating Units on the System at 09 January 1995 (in this paragraph, the
"relevant date") or the new data items set out under Option 2 may be provided. Generators
or Network Operators, as the case may be, must supply the data as set out under Option 2
(and not those under Option 1) for Generating Unit excitation control systems
commissioned after the relevant date, those Generating Unit excitation control systems
recommissioned for any reason such as refurbishment after the relevant date and
Generating Unit excitation control systems where, as a result of testing or other process,
the Generator or Network Operator, as the case may be, is aware of the data items listed
under Option 2 in relation to that Generating Unit.

Option 1
DC gain of Excitation Loop
Rated field voltage
Maximum field voltage
Minimum field voltage
Maximum rate of change of field voltage (rising)
Maximum rate of change of field voltage (falling)
Details of Excitation Loop described in block diagram form showing transfer functions
of individual elements.
Dynamic characteristics of Over-excitation Limiter.
Dynamic characteristics of Under-excitation Limiter

Option 2
Excitation System Nominal Response
Rated Field Voltage
No-Load Field Voltage
Excitation System On-Load Positive Ceiling Voltage
Excitation System No-Load Positive Ceiling Voltage
Excitation System No-Load Negative Ceiling Voltage
Details of Excitation System (including PSS if fitted) described in block diagram form
showing transfer functions of individual elements.
Details of Over-excitation Limiter described in block diagram form showing transfer
functions of individual elements.
Details of Under-excitation Limiter described in block diagram form showing transfer
functions of individual elements.
The block diagrams submitted after 1 January 2009 in respect of the Excitation
System (including the Over-excitation Limiter and the Under-excitation Limiter) for
Generating Units with a Completion date after 1 January 2009 or subject to a
Modification to the Excitation System after 1 January 2009, should have been
verified as far as reasonably practicable by simulation studies as representing the
expected behaviour of the system.
(d) Governor Parameters
Incremental Droop values (in %) are required for each Generating Unit at six MW loading
points (MLP1 to MLP6) as detailed in PC.A.5.5.1 (this data item needs only be provided for
Large Power Stations)

Issue 5 Revision 15 PC 03 February 2016


43 of 72
Note: The data items requested under Option 1 below may continue to be provided by
Generators in relation to Generating Units on the System at 09 January 1995 (in this
paragraph, the "relevant date") or they may provide the new data items set out under Option
2. Generators must supply the data as set out under Option 2 (and not those under Option
1) for Generating Unit governor control systems commissioned after the relevant date,
those Generating Unit governor control systems recommissioned for any reason such as
refurbishment after the relevant date and Generating Unit governor control systems where,
as a result of testing or other process, the Generator is aware of the data items listed under
Option 2 in relation to that Generating Unit.
Option 1
(i) Governor Parameters (for Reheat Steam Units)
HP governor average gain MW/Hz
Speeder motor setting range
HP governor valve time constant
HP governor valve opening limits
HP governor valve rate limits
Reheater time constant (Active Energy stored in reheater)

IP governor average gain MW/Hz


IP governor setting range
IP governor valve time constant
IP governor valve opening limits
IP governor valve rate limits

Details of acceleration sensitive elements in HP & IP governor loop.


A governor block diagram showing transfer functions of individual elements.

(ii) Governor Parameters (for Non-Reheat Steam Units and Gas Turbine Units)
Governor average gain
Speeder motor setting range
Time constant of steam or fuel governor valve
Governor valve opening limits
Governor valve rate limits
Time constant of turbine
Governor block diagram

The following data items need only be supplied for Large Power Stations:
(iii) Boiler & Steam Turbine Data
Boiler Time Constant (Stored Active Energy) s
HP turbine response ratio:
proportion of Primary Response arising from HP turbine %
HP turbine response ratio:
proportion of High Frequency Response arising from HP turbine %

Issue 5 Revision 15 PC 03 February 2016


44 of 72
[End of Option 1]

Option 2
(i) Governor and associated prime mover Parameters - All Generating Units
Governor Block Diagram showing transfer function of individual elements including
acceleration sensitive elements.
Governor Time Constant (in seconds)
Speeder Motor Setting Range (%)
Average Gain (MW/Hz)
Governor Deadband (this data item need only be provided for Large Power
Stations)

- Maximum Setting Hz

- Normal Setting Hz
- Minimum Setting Hz
Where the Generating Unit governor does not have a selectable deadband
facility, then the actual value of the deadband need only be provided.
The block diagrams submitted after 1 January 2009 in respect of the Governor
system for Generating Units with a Completion date after 1 January 2009 or
subject to a Modification to the governor system after 1 January 2009, should
have been verified as far as reasonably practicable by simulation studies as
representing the expected behaviour of the system.

(ii) Governor and associated prime mover Parameters - Steam Units


HP Valve Time Constant (in seconds)
HP Valve Opening Limits (%)
HP Valve Opening Rate Limits (%/second)
HP Valve Closing Rate Limits (%/second)
HP Turbine Time Constant (in seconds)

IP Valve Time Constant (in seconds)


IP Valve Opening Limits (%)
IP Valve Opening Rate Limits (%/second)
IP Valve Closing Rate Limits (%/second)
IP Turbine Time Constant (in seconds)

LP Valve Time Constant (in seconds)


LP Valve Opening Limits (%)
LP Valve Opening Rate Limits (%/second)
LP Valve Closing Rate Limits (%/second)
LP Turbine Time Constant (in seconds)
Reheater Time Constant (in seconds)
Boiler Time Constant (in seconds)
HP Power Fraction (%)
IP Power Fraction (%)
Issue 5 Revision 15 PC 03 February 2016
45 of 72
(iii) Governor and associated prime mover Parameters - Gas Turbine Units
Inlet Guide Vane Time Constant (in seconds)
Inlet Guide Vane Opening Limits (%)
Inlet Guide Vane Opening Rate Limits (%/second)
Inlet Guide Vane Closing Rate Limits (%/second)
Fuel Valve Constant (in seconds)
Fuel Valve Opening Limits (%)
Fuel Valve Opening Rate Limits (%/second)
Fuel Valve Closing Rate Limits (%/second)
Waste Heat Recovery Boiler Time Constant (in seconds)

(iv) Governor and associated prime mover Parameters - Hydro Generating Units
Guide Vane Actuator Time Constant (in seconds)
Guide Vane Opening Limits (%)
Guide Vane Opening Rate Limits (%/second)
Guide Vane Closing Rate Limits (%/second)
Water Time Constant (in seconds)
[End of Option 2]

(e) Unit Control Options


The following data items need only be supplied with respect to Large Power Stations:
Maximum Droop %
Normal Droop %
Minimum Droop %

Maximum Frequency deadband Hz

Normal Frequency deadband Hz

Minimum Frequency deadband Hz

Maximum output deadband MW

Normal output deadband MW

Minimum output deadband MW


Frequency settings between which Unit Load Controller Droop applies:
- Maximum Hz
- Normal Hz
- Minimum Hz
State if sustained response is normally selected.

(f) Plant Flexibility Performance


The following data items need only be supplied with respect to Large Power Stations, and
should be provided with respect to each Genset:
# Run-up rate to Registered Capacity,
# Run-down rate from Registered Capacity,
Issue 5 Revision 15 PC 03 February 2016
46 of 72
# Synchronising Generation,
Regulating range
Load rejection capability while still Synchronised and able to supply Load.

Data items marked with a hash (#) should be applicable to a Genset which has been
Shutdown for 48 hours.
* Data items marked with an asterisk are already requested under partx1, PC.A.3.3.1, to
facilitate an early assessment by NGET as to whether detailed stability studies will be
required before an offer of terms for a CUSC Contract can be made. Such data items have
been repeated here merely for completeness and need not, of course, be resubmitted
unless their values, known or estimated, have changed.

(g) Generating Unit Mechanical Parameters


It is occasionally necessary for NGET to assess the interaction between the Total System
and the mechanical components of Generating Units. For Generating Units with a
Completion Date on or after 01 April 2015, the following data items should be supplied:
The number of turbine generator masses.
Diagram showing the Inertia and parameters for each turbine generator mass (kgm 2)
and Stiffness constants and parameters between each turbine generator mass for the
complete drive train (Nm/rad).
Number of poles.
Relative power applied to different parts of the turbine (%).
Torsional mode frequencies (Hz).
Modal damping decrement factors for the different mechanical modes.

PC.A.5.4 Non-Synchronous Generating Unit and Associated Control System Data


PC.A.5.4.1 The data submitted below are not intended to constrain any Ancillary Services Agreement
PC.A.5.4.2 The following Power Park Unit, Power Park Module and Power Station data should be supplied
in the case of a Power Park Module not connected to the Total System by a DC Converter (and
in the case of PC.A.5.4.2(f) any OTSUA):
Where a Manufacturers Data & Performance Report exists in respect of the model of the
Power Park Unit, the User may subject to NGETs agreement, opt to reference the
Manufacturers Data & Performance Report as an alternative to the provision of data in
accordance with PC.A.5.4.2 except for:
(1) the section marked thus # at sub paragraph (b); and
(2) all of the harmonic and flicker parameters required under sub paragraph (h); and
(3) all of the site specific model parameters relating to the voltage or frequency control systems
required under sub paragraphs (d) and (e),
which must be provided by the User in addition to the Manufacturers Data & Performance
Report reference.
(a) Power Park Unit model
A mathematical model of each type of Power Park Unit capable of representing its transient
and dynamic behaviour under both small and large disturbance conditions. The model shall
include non-linear effects and represent all equipment relevant to the dynamic performance
of the Power Park Unit as agreed with NGET. The model shall be suitable for the study of
balanced, root mean square, positive phase sequence time-domain behaviour, excluding the
effects of electromagnetic transients, harmonic and sub-harmonic frequencies.

Issue 5 Revision 15 PC 03 February 2016


47 of 72
The model shall accurately represent the overall performance of the Power Park Unit over
its entire operating range including that which is inherent to the Power Park Unit and that
which is achieved by use of supplementary control systems providing either continuous or
stepwise control. Model resolution should be sufficient to accurately represent Power Park
Unit behaviour both in response to operation of Transmission System protection and in the
context of longer-term simulations.

The overall structure of the model shall include:


(i) any supplementary control signal modules not covered by (c), (d) and (e) below.
(ii) any blocking, deblocking and protective trip features that are part of the Power Park Unit
(e.g. crowbar).
(iii) any other information required to model the Power Park Unit behaviour to meet the model
functional requirement described above.
The model shall be submitted in the form of a transfer function block diagram and may be
accompanied by dynamic and algebraic equations.
This model shall display all the transfer functions and their parameter values, any non wind-up
logic, signal limits and non-linearities.
The submitted Power Park Unit model and the supplementary control signal module models
covered by (c), (d) and (e) below shall have been validated and this shall be confirmed by the
Generator. The validation shall be based on comparing the submitted model simulation results
against measured test results. Validation evidence shall also be submitted and this shall include
the simulation and measured test results. The latter shall include appropriate short-circuit tests.
In the case of an Embedded Medium Power Station not subject to a Bilateral Agreement the
Network Operator will provide NGET with the validation evidence if requested by NGET. The
validation of the supplementary control signal module models covered by (c), (d) and (e) below
applies only to a Power Park Module with a Completion Date after 1 January 2009.
(b) Power Park Unit parameters
* Rated MVA
* Rated MW
* Rated terminal voltage
* Average site air density (kg/m3), maximum site air density (kg/m3) and minimum site air
density (kg/m3) for the year
Year for which the air density is submitted
Number of pole pairs
Blade swept area (m2)
Gear box ratio
Mechanical drive train
For each Power Park Unit, details of the parameters of the drive train represented as
an equivalent two mass model should be provided. This model should accurately
represent the behaviour of the complete drive train for the purposes of power system
analysis studies and should include the following data items:-
Equivalent inertia constant (MWsec/MVA) of the first mass (e.g. wind turbine rotor
and blades) at minimum, synchronous and rated speeds
Equivalent inertia constant (MWsec/MVA) of the second mass (e.g. generator
rotor) at minimum, synchronous and rated speeds
Equivalent shaft stiffness between the two masses (Nm/electrical radian)
Additionally, for Power Park Units that are induction generators (e.g. squirrel cage,
doubly-fed) driven by wind turbines:
* Stator resistance
Issue 5 Revision 15 PC 03 February 2016
48 of 72
* Stator reactance
* Magnetising reactance.
* Rotor resistance.(at starting)
* Rotor resistance.(at rated running)
* Rotor reactance (at starting)
* Rotor reactance (at rated running)
Additionally for doubly-fed induction generators only:
The generator rotor speed range (minimum and maximum speeds in RPM)
The optimum generator rotor speed versus wind speed submitted in tabular format
Power converter rating (MVA)

The rotor power coefficient (Cp) versus tip speed ratio () curves for a range of blade
angles (where applicable) together with the corresponding values submitted in tabular
format. The tip speed ratio () is defined as R/U where is the angular velocity of
the rotor, R is the radius of the wind turbine rotor and U is the wind speed.
The electrical power output versus generator rotor speed for a range of wind speeds
over the entire operating range of the Power Park Unit, together with the
corresponding values submitted in tabular format.
The blade angle versus wind speed curve together with the corresponding values
submitted in tabular format.
The electrical power output versus wind speed over the entire operating range of the
Power Park Unit, together with the corresponding values submitted in tabular format.
Transfer function block diagram, including parameters and description of the operation
of the power electronic converter and fault ride through capability (where applicable).

For a Power Park Unit consisting of a synchronous machine in combination with a back to
back DC Converter, or for a Power Park Unit not driven by a wind turbine, the data to be
supplied shall be agreed with NGET in accordance with PC.A.7.

(c) Torque / speed and blade angle control systems and parameters
For the Power Park Unit, details of the torque / speed controller and blade angle controller
in the case of a wind turbine and power limitation functions (where applicable) described in
block diagram form showing transfer functions and parameters of individual elements.
(d) Voltage/Reactive Power/Power Factor control system parameters
For the Power Park Unit and Power Park Module details of voltage/Reactive
Power/Power Factor controller (and PSS if fitted) described in block diagram form showing
transfer functions and parameters of individual elements.
(e) Frequency control system parameters
For the Power Park Unit and Power Park Module details of the Frequency controller
described in block diagram form showing transfer functions and parameters of individual
elements.
(f) Protection
Details of settings for the following Protection relays (to include): Under Frequency, over
Frequency, under voltage, over voltage, rotor over current, stator over current, high wind
speed shut down level.

(g) Complete Power Park Unit model, parameters and controls

Issue 5 Revision 15 PC 03 February 2016


49 of 72
An alternative to PC.A.5.4.2 (a), (b), (c), (d), (e) and (f), is the submission of a single
complete model that consists of the full information required under PC.A.5.4.2 (a), (b), (c),
(d), (e) and (f) provided that all the information required under PC.A.5.4.2 (a), (b), (c), (d), (e)
and (f) individually is clearly identifiable.
(h) Harmonic and flicker parameters
When connecting a Power Park Module, it is necessary for NGET to evaluate the
production of flicker and harmonics on NGET and User's Systems. At NGET's reasonable
request, the User (a Network Operator in the case of an Embedded Power Park Module
not subject to a Bilateral Agreement) is required to submit the following data (as defined in
IEC 61400-21 (2001)) for each Power Park Unit:-
Flicker coefficient for continuous operation.
Flicker step factor.
Number of switching operations in a 10 minute window.
Number of switching operations in a 2 hour window.
Voltage change factor.
Current Injection at each harmonic for each Power Park Unit and for each Power Park
Module

* Data items marked with an asterisk are already requested under part 1, PC.A.3.3.1, to
facilitate an early assessment by NGET as to whether detailed stability studies will be
required before an offer of terms for a CUSC Contract can be made. Such data items have
been repeated here merely for completeness and need not, of course, be resubmitted
unless their values, known or estimated, have changed.

PC.A.5.4.3 DC Converter
PC.A.5.4.3.1 For a DC Converter at a DC Converter Station or a Power Park Module connected to the Total
System by a DC Converter (or in the case of OTSUA which includes an OTSDUW DC
Converter) the following information for each DC Converter and DC Network should be
supplied:
(a) DC Converter parameters
* Rated MW per pole for transfer in each direction;
* DC Converter type (i.e. current or voltage source);
* Number of poles and pole arrangement;
* Rated DC voltage/pole (kV);
* Return path arrangement;

(b) DC Converter transformer parameters


Rated MVA
Nominal primary voltage (kV);
Nominal secondary (converter-side) voltage(s) (kV);
Winding and earthing arrangement;
Positive phase sequence reactance at minimum, maximum and nominal tap;
Positive phase sequence resistance at minimum, maximum and nominal tap;
Zero phase sequence reactance;
Tap-changer range in %;
number of tap-changer steps;

Issue 5 Revision 15 PC 03 February 2016


50 of 72
(c) DC Network parameters
Rated DC voltage per pole;
Rated DC current per pole;
Single line diagram of the complete DC Network;
Details of the complete DC Network, including resistance, inductance and capacitance
of all DC cables and/or DC lines;
Details of any DC reactors (including DC reactor resistance), DC capacitors and/or DC-
side filters that form part of the DC Network;
(d) AC filter reactive compensation equipment parameters
Note: The data provided pursuant to this paragraph must not include any contribution from
reactive compensation plant owned or operated by NGET.
Total number of AC filter banks.
Type of equipment (e.g. fixed or variable)
Single line diagram of filter arrangement and connections;
Reactive Power rating for each AC filter bank, capacitor bank or operating range of
each item of reactive compensation equipment, at rated voltage;
Performance chart showing Reactive Power capability of the DC Converter, as a
function of MW transfer, with all filters and reactive compensation plant, belonging to
the DC Converter Station working correctly.

Note: Details in PC.A.5.4.3.1 are required for each DC Converter connected to the DC Network,
unless each is identical or where the data has already been submitted for an identical DC
Converter at another Connection Point.
Note: For a Power Park Module connected to the Grid Entry point or (User System Entry
Point if Embedded) by a DC Converter the equivalent inertia and fault infeed at the Power Park
Unit should be given.
DC Converter Control System Models
PC.A.5.4.3.2 The following data is required by NGET to represent DC Converters and associated DC
Networks (and including OTSUA which includes an OTSDUW DC Converter) in dynamic power
system simulations, in which the AC power system is typically represented by a positive
sequence equivalent. DC Converters are represented by simplified equations and are not
modelled to switching device level.
(i) Static VDC-IDC (DC voltage - DC current) characteristics, for both the rectifier and inverter
modes for a current source converter. Static VDC-PDC (DC voltage - DC power)
characteristics, for both the rectifier and inverter modes for a voltage source converter.
Transfer function block diagram including parameters representation of the control systems
of each DC Converter and of the DC Converter Station, for both the rectifier and inverter
modes. A suitable model would feature the DC Converter firing angle as the output variable.
(ii) Transfer function block diagram representation including parameters of the DC Converter
transformer tap changer control systems, including time delays
(iii) Transfer function block diagram representation including parameters of AC filter and
reactive compensation equipment control systems, including any time delays.
(iv) Transfer function block diagram representation including parameters of any Frequency
and/or load control systems.
(v) Transfer function block diagram representation including parameters of any small signal
modulation controls such as power oscillation damping controls or sub-synchronous
oscillation damping controls, that have not been submitted as part of the above control
system data.

Issue 5 Revision 15 PC 03 February 2016


51 of 72
(vi) Transfer block diagram representation of the Reactive Power control at converter ends for a
voltage source converter.

Issue 5 Revision 15 PC 03 February 2016


52 of 72
Plant Flexibility Performance
PC.A.5.4.3.3 The following information on plant flexibility and performance should be supplied (and also in
respect of OTSUA which includes an OTSDUW DC Converter):
(i) Nominal and maximum (emergency) loading rate with the DC Converter in rectifier mode.
(ii) Nominal and maximum (emergency) loading rate with the DC Converter in inverter mode.
(iii) Maximum recovery time, to 90% of pre-fault loading, following an AC system fault or severe
voltage depression.
(iv) Maximum recovery time, to 90% of pre-fault loading, following a transient DC Network fault.
Harmonic Assessment Information
PC.A.5.4.3.4 DC Converter owners shall provide such additional further information as required by NGET in
order that compliance with CC.6.1.5 can be demonstrated.

* Data items marked with an asterisk are already requested under part 1, PC.A.3.3.1, to facilitate
an early assessment by NGET as to whether detailed stability studies will be required before an
offer of terms for a CUSC Contract can be made. Such data items have been repeated here
merely for completeness and need not, of course, be resubmitted unless their values, known or
estimated, have changed.
PC.A.5.5 Response Data For Frequency Changes
The information detailed below is required to describe the actual frequency response capability
profile as illustrated in Figure CC.A.3.1 of the Connection Conditions, and need only be
provided for each:
(i) Genset at Large Power Stations; and
(ii) Generating Unit, Power Park Module or CCGT Module at a Medium Power Station or DC
Converter Station that has agreed to provide Frequency response in accordance with a
CUSC Contract.
In the case of (ii) above for the rest of this PC.A.5.5 where reference is made to Gensets, it
shall include such Generating Units, CCGT Modules, Power Park Modules and DC
Converters as appropriate, but excludes OTSDUW Plant and Apparatus utilising
OTSDUW DC Converters.
In this PC.A.5.5, for a CCGT Module with more than one Generating Unit, the phrase Minimum
Generation applies to the entire CCGT Module operating with all Generating Units
Synchronised to the System. Similarly for a Power Park Module with more than one Power
Park Unit, the phrase Minimum Generation applies to the entire Power Park Module operating
with all Power Park Units Synchronised to the System.
PC.A.5.5.1 MW Loading Points At Which Data Is Required
Response values are required at six MW loading points (MLP1 to MLP6) for each Genset.
Primary and Secondary Response values need not be provided for MW loading points which
are below Minimum Generation. MLP1 to MLP6 must be provided to the nearest MW.
Prior to the Genset being first Synchronised, the MW loading points must take the following
values :
MLP1 Designed Minimum Operating Level
MLP2 Minimum Generation
MLP3 70% of Registered Capacity
MLP4 80% of Registered Capacity
MLP5 95% of Registered Capacity
MLP6 Registered Capacity

Issue 5 Revision 15 PC 03 February 2016


53 of 72
When data is provided after the Genset is first Synchronised, the MW loading points may take
any value between Designed Minimum Operating Level and Registered Capacity but the value
of the Designed Minimum Operating Level must still be provided if it does not form one of the
MW loading points.

PC.A.5.5.2 Primary And Secondary Response To Frequency Fall


Primary and Secondary Response values for a -0.5Hz ramp are required at six MW loading
points (MLP1 to MLP6) as detailed above
PC.A.5.5.3 High Frequency Response To Frequency Rise
High Frequency Response values for a +0.5Hz ramp are required at six MW loading points
(MLP1 to MLP6) as detailed above.
PC.A.5.6 Mothballed Generating Unit Mothballed Power Park Module Or Mothballed DC Converter At A DC
Converter Station And Alternative Fuel Information
Data identified under this section PC.A.5.6 must be submitted as required under PC.A.1.2 and at
NGETs reasonable request.
In the case of Embedded Medium Power Stations not subject to a Bilateral Agreement and
Embedded DC Converter Stations not subject to a Bilateral Agreement, upon request from
NGET each Network Operator shall provide the information required in PC.A.5.6.1, PC.A.5.6.2,
PC.A.5.6.3 and PC.A.5.6.4 on respect of such Embedded Medium Power Stations and
Embedded DC Converters Stations with their System.
PC.A.5.6.1 Mothballed Generating Unit Information
Generators and DC Converter Station owners must supply with respect to each Mothballed
Generating Unit, Mothballed Power Park Module or Mothballed DC Converter at a DC
Converter Station the estimated MW output which could be returned to service within the
following time periods from the time that a decision to return was made:
< 1 month;
1-2 months;
2-3 months;
3-6 months;
6-12 months; and
>12 months.
The return to service time should be determined in accordance with Good Industry Practice
assuming normal working arrangements and normal plant procurement lead times. The MW
output values should be the incremental values made available in each time period as further
described in the DRC.

PC.A.5.6.2 Generators and DC Converter Station owners must also notify NGET of any significant factors
which may prevent the Mothballed Generating Unit, Mothballed Power Park Module or
Mothballed DC Converter at a DC Converter Station achieving the estimated values provided
under PC.A.5.6.1 above, excluding factors relating to Transmission Entry Capacity.
PC.A.5.6.3 Alternative Fuel Information
The following data items must be supplied with respect to each Generating Unit whose main fuel
is gas.
For each alternative fuel type (if facility installed):
(a) Alternative fuel type e.g. oil distillate, alternative gas supply
(b) For the changeover from main to alternative fuel:
- Time to carry out off-line and on-line fuel changeover (minutes).
- Maximum output following off-line and on-line changeover (MW).
Issue 5 Revision 15 PC 03 February 2016
54 of 72
- Maximum output during on-line fuel changeover (MW).
- Maximum operating time at full load assuming typical and maximum possible stock
levels (hours).
- Maximum rate of replacement of depleted stocks (MWh electrical/day) on the basis of
Good Industry Practice.
- Is changeover to alternative fuel used in normal operating arrangements?
- Number of successful changeovers carried out in the last NGET Financial Year
(choice of 0, 1-5, 6-10, 11-20, >20).
(c) For the changeover back to main fuel:
- Time to carry out off-line and on-line fuel changeover (minutes).
- Maximum output during on-line fuel changeover (MW).
PC.A.5.6.4 Generators must also notify NGET of any significant factors and their effects which may prevent
the use of alternative fuels achieving the estimated values provided under PC.A.5.6.3 above (e.g.
emissions limits, distilled water stocks etc.)
PC.A.5.7 Black Start Related Information
Data identified under this section PC.A.5.7 must be submitted as required under PC.A.1.2. This
information may also be requested by NGET during a Black Start and should be provided by
Generators where reasonably possible. Generators in this section PC.A.5.7 means Generators
only in respect of their Large Power Stations.
The following data items/text must be supplied, from each Generator to NGET, with respect to
each BM Unit at a Large Power Station (excluding the Generating Units that are contracted to
provide Black Start Capability, Power Park Modules or Generating Units with an Intermittent
Power Source);
(a) Expected time for each BM Unit to be Synchronised following a Total Shutdown or Partial
Shutdown. The assessment should include the Power Stations ability to re-synchronise
all BM Units, if all were running immediately prior to the Total Shutdown or Partial
Shutdown. Additionally this should highlight any specific issues (i.e. those that would
impact on the BM Units time to be Synchronised) that may arise, as time progresses
without external supplies being restored.
(b) Block Loading Capability. This should be provided in either graphical or tabular format
showing the estimated block loading capability from 0MW to Registered Capacity. Any
particular hold points should also be identified. The data of each BM Unit should be
provided for the condition of a hot unit that was Synchronised just prior to the Total
Shutdown or Partial Shutdown and also for the condition of a cold unit. The block loading
assessment should be done against a frequency variation of 49.5Hz 50.5Hz.

PC.A.6 USERS' SYSTEM DATA


PC.A.6.1 Introduction
PC.A.6.1.1 Each User, whether connected directly via an existing Connection Point to the National
Electricity Transmission System or seeking such a direct connection, or providing terms for
connection of an Offshore Transmission System to its User System to NGET or undertaking
OTSDUW, shall provide NGET with data on its User System or OTSDUW Plant and Apparatus
which relates to the Connection Site containing the Connection Point (or Interface Points or
Connection Points in the case of OTSUA) both current and forecast, as specified in PC.A.6.2 to
PC.A.6.6.
PC.A.6.1.2 Each User must reflect the system effect at the Connection Site(s) of any third party Embedded
within its User System whether existing or proposed.

Issue 5 Revision 15 PC 03 February 2016


55 of 72
PC.A.6.1.3 PC.A.6.2, and PC.A.6.4 to PC.A.6.6 consist of data which is only to be supplied to NGET at
NGETs reasonable request. In the event that NGET identifies a reason for requiring this data,
NGET shall write to the relevant User(s), requesting the data, and explaining the reasons for the
request. If the User(s) wishes, NGET shall also arrange a meeting at which the request for data
can be discussed, with the objective of identifying the best way in which NGETs requirements
can be met.
PC.A.6.2 Transient Overvoltage Assessment Data
PC.A.6.2.1 It is occasionally necessary for NGET to undertake transient overvoltage assessments (e.g.
capacitor switching transients, switchgear transient recovery voltages, etc). At NGETs
reasonable request, each User is required to provide the following data with respect to the
Connection Site (and in the case of OTSUA, Interface Points and Connection Points), current
and forecast, together with a Single Line Diagram where not already supplied under PC.A.2.2.1,
as follows:
(a) busbar layout plan(s), including dimensions and geometry showing positioning of any current
and voltage transformers, through bushings, support insulators, disconnectors, circuit
breakers, surge arresters, etc. Electrical parameters of any associated current and voltage
transformers, stray capacitances of wall bushings and support insulators, and grading
capacitances of circuit breakers;
(b) Electrical parameters and physical construction details of lines and cables connected at that
busbar. Electrical parameters of all plant e.g., transformers (including neutral earthing
impedance or zig-zag transformers, if any), series reactors and shunt compensation
equipment connected at that busbar (or to the tertiary of a transformer) or by lines or cables
to that busbar;
(c) Basic insulation levels (BIL) of all Apparatus connected directly, by lines or by cables to the
busbar;
(d) characteristics of overvoltage Protection devices at the busbar and at the termination points
of all lines, and all cables connected to the busbar;
(e) fault levels at the lower voltage terminals of each transformer connected directly or indirectly
to the National Electricity Transmission System (including OTSUA at each Interface
Point and Connection Point) without intermediate transformation;
(f) the following data is required on all transformers operating at Supergrid Voltage throughout
Great Britain and, in Scotland and Offshore, also at 132kV (including OTSUA): three or five
limb cores or single phase units to be specified, and operating peak flux density at nominal
voltage;
(g) an indication of which items of equipment may be out of service simultaneously during
Planned Outage conditions.
PC.A.6.3 User's Protection Data
PC.A.6.3.1 Protection
The following information is required which relates only to Protection equipment which can trip or
inter-trip or close any Connection Point circuit-breaker or any Transmission circuit-breaker (or
in the case of OTSUA, any Interface Point or Connection Point circuit breaker). This
information need only be supplied once, in accordance with the timing requirements set out in
PC.A.1.4(b), and need not be supplied on a routine annual basis thereafter, although NGET
should be notified if any of the information changes
(a) a full description, including estimated settings, for all relays and Protection systems
installed or to be installed on the User's System;
(b) a full description of any auto-reclose facilities installed or to be installed on the User's
System, including type and time delays;
(c) a full description, including estimated settings, for all relays and Protection systems or to be
installed on the generator, generator transformer, Station Transformer and their associated
connections;

Issue 5 Revision 15 PC 03 February 2016


56 of 72
(d) for Generating Units (other than Power Park Units) or Power Park Modules or DC
Converters at a DC Converter Station or OTSDUW Plant and Apparatus having (or
intended to have) a circuit breaker at the generator terminal voltage, clearance times for
electrical faults within the Generating Unit (other than a Power Park Unit) or Power Park
Module zone, or within the OTSDUW Plant and Apparatus;
(e) the most probable fault clearance time for electrical faults on any part of the User's System
directly connected to the National Electricity Transmission System including OTSDUW
Plant and Apparatus; and
(f) in the case of OTSDUW Plant and Apparatus, synchronisation facilities and delayed auto
reclose sequence schedules (where applicable).
PC.A.6.4 Harmonic Studies
PC.A.6.4.1 It is occasionally necessary for NGET to evaluate the production/magnification of harmonic
distortion on NGET and Users Systems (and OTSUA), especially when NGET is connecting
equipment such as capacitor banks. At NGETs reasonable request, each User is required to
submit data with respect to the Connection Site (and in the case of OTSUA, each Interface
Point and Connection Point), current and forecast, and where not already supplied under
PC.A.2.2.4 and PC.A.2.2.5, as follows:
PC.A.6.4.2 Overhead lines and underground cable circuits of the User's Subtransmission System must be
differentiated and the following data provided separately for each type:
Positive phase sequence resistance;
Positive phase sequence reactance;
Positive phase sequence susceptance;
and for all transformers connecting the User's Subtransmission System and OTSDUW Plant
and Apparatus to a lower voltage:
Rated MVA;
Voltage Ratio;
Positive phase sequence resistance;
Positive phase sequence reactance;
and at the lower voltage points of those connecting transformers:
Equivalent positive phase sequence susceptance;
Connection voltage and MVAr rating of any capacitor bank and component design
parameters if configured as a filter;
Equivalent positive phase sequence interconnection impedance with other lower voltage
points;
The minimum and maximum Demand (both MW and MVAr) that could occur;
Harmonic current injection sources in Amps at the Connection voltage points. Where the
harmonic injection current comes from a diverse group of sources, the equivalent
contribution may be established from appropriate measurements;
Details of traction loads, eg connection phase pairs, continuous variation with time, etc;
An indication of which items of equipment may be out of service simultaneously during
Planned Outage conditions.
PC.A.6.5 Voltage Assessment Studies
It is occasionally necessary for NGET to undertake detailed voltage assessment studies (e.g., to
examine potential voltage instability, voltage control co-ordination or to calculate voltage step
changes). At NGETs reasonable request, each User is required to submit the following data
where not already supplied under PC.A.2.2.4 and PC.A.2.2.5:
For all circuits of the Users Subtransmission System (and any OTSUA):-

Issue 5 Revision 15 PC 03 February 2016


57 of 72
Positive Phase Sequence Reactance;
Positive Phase Sequence Resistance;
Positive Phase Sequence Susceptance;
MVAr rating of any reactive compensation equipment;
and for all transformers connecting the User's Subtransmission System to a lower voltage (and
any OTSUA):
Rated MVA;
Voltage Ratio;
Positive phase sequence resistance;
Positive Phase sequence reactance;
Tap-changer range;
Number of tap steps;
Tap-changer type: on-load or off-circuit;
AVC/tap-changer time delay to first tap movement;
AVC/tap-changer inter-tap time delay;
and at the lower voltage points of those connecting transformers (and any OTSUA):-
Equivalent positive phase sequence susceptance;
MVAr rating of any reactive compensation equipment;
Equivalent positive phase sequence interconnection impedance with other lower voltage
points;
The maximum Demand (both MW and MVAr) that could occur;
Estimate of voltage insensitive (constant power) load content in % of total load at both
winter peak and 75% off-peak load conditions.

PC.A.6.6 Short Circuit Analysis


PC.A.6.6.1 Where prospective short-circuit currents on equipment owned, operated or managed by NGET
are greater than 90% of the equipment rating, and in NGETs reasonable opinion more accurate
calculations of short-circuit currents are required, then at NGETs request each User is required
to submit data with respect to the Connection Site (and in the case of OTSUA, each Interface
Point and Connection Point), current and forecast, and where not already supplied under
PC.A.2.2.4 and PC.A.2.2.5, as follows:
PC.A.6.6.2 For all circuits of the Users Subtransmission System (and any OTSUA):
Positive phase sequence resistance;
Positive phase sequence reactance;
Positive phase sequence susceptance;
Zero phase sequence resistance (both self and mutuals);
Zero phase sequence reactance (both self and mutuals);
Zero phase sequence susceptance (both self and mutuals);
and for all transformers connecting the User's Subtransmission System to a lower voltage (and
any OTSUA):
Rated MVA;
Voltage Ratio;
Positive phase sequence resistance (at max, min and nominal tap);
Positive Phase sequence reactance (at max, min and nominal tap);
Issue 5 Revision 15 PC 03 February 2016
58 of 72
Zero phase sequence reactance (at nominal tap);
Tap changer range;
Earthing method: direct, resistance or reactance;
Impedance if not directly earthed;
and at the lower voltage points of those connecting transformers (and any OTSUA):
The maximum Demand (in MW and MVAr) that could occur;
Short-circuit infeed data in accordance with PC.A.2.5.6 unless the Users lower voltage
network runs in parallel with the Users Subtransmission System, when to prevent double
counting in each node infeed data, a equivalent comprising the data items of PC.A.2.5.6
for each node together with the positive phase sequence interconnection impedance
between the nodes shall be submitted.
PC.A.7 ADDITIONAL DATA FOR NEW TYPES OF POWER STATIONS, DC CONVERTER STATIONS,
OTSUA AND CONFIGURATIONS
Notwithstanding the Standard Planning Data and Detailed Planning Data set out in this
Appendix, as new types of configurations and operating arrangements of Power Stations, DC
Converter Stations and OTSUA emerge in future, NGET may reasonably require additional data
to represent correctly the performance of such Plant and Apparatus on the System, where the
present data submissions would prove insufficient for the purpose of producing meaningful
System studies for the relevant parties.

Issue 5 Revision 15 PC 03 February 2016


59 of 72
PART 3 - DETAILED PLANNING DATA

PC.A.8 To allow a User to model the National Electricity Transmission System, NGET will provide,
upon request, the following Network Data to Users, calculated in accordance with Good
Industry Practice:
To allow a User to assess undertaking OTSDUW and except where provided for in Appendix F,
NGET will provide upon request the following Network Data to Users, calculated in accordance
with Good Industry Practice:
PC.A.8.1 Single Point of Connection
For a Single Point of Connection to a User's System (and OTSUA), as an equivalent 400kV or
275kV source and also in Scotland and Offshore as an equivalent 132kV source, the data (as at
the HV side of the Point of Connection (and in the case of OTSUA, each Interface Point and
Connection Point) reflecting data given to NGET by Users) will be given to a User as follows:
The data items listed under the following parts of PC.A.8.3:
(a) (i), (ii), (iii), (iv), (v) and (vi)
and the data items shall be provided in accordance with the detailed provisions of PC.A.8.3 (b) -
(e).
PC.A.8.2 Multiple Point of Connection
For a Multiple Point of Connection to a User's System equivalents suitable for use in loadflow
and fault level analysis shall be provided. These equivalents will normally be in the form of a
model or extension with a source (or demand for a loadflow equivalent) at each node and a
linking impedance. The boundary nodes for the equivalent shall be either at the Connection
Point (and in the case of OTSDUW, each Interface Point and Connection Point) or (where
NGET agrees) at suitable nodes (the nodes to be agreed with the User) within the National
Electricity Transmission System. The data at the Connection Point (and in the case of
OTSDUW, each Interface Point and Connection Point) will be given to a User as follows:
The data items listed under the following parts of PC.A.8.3:-
(a) (i), (ii), (iv), (v), (vi), (vii), (viii), (ix), (x) and (xi)
and the data items shall be provided in accordance with the detailed provisions of PC.A.8.3 (b) -
(e).
When an equivalent of this form is not required NGET will not provide the data items listed under
the following parts of PC.A.8.3:-
(a) (vii), (viii), (ix), (x) and (xi)
PC.A.8.3 Data Items
(a) The following is a list of data utilised in this part of the PC. It also contains rules on the data
which generally apply.
(i) symmetrical three-phase short circuit current infeed at the instant of fault from the
National Electricity Transmission System, (I1");
(ii) symmetrical three-phase short circuit current from the National Electricity
Transmission System after the subtransient fault current contribution has substantially
decayed, (I1');
(iii) the zero sequence source resistance and reactance values at the Point of Connection
(and in case of OTSUA, each Interface Point and Connection Point), consistent with
the maximum infeed below;
(iv) the pre-fault voltage magnitude at which the maximum fault currents were calculated;
(v) the positive sequence X/R ratio at the instant of fault;
(vi) the negative sequence resistance and reactance values of the National Electricity
Transmission System seen from the (Point of Connection and in case of OTSUA,
each Interface Point and Connection Point), if substantially different from the values
Issue 5 Revision 15 PC 03 February 2016
60 of 72
of positive sequence resistance and reactance which would be derived from the data
provided above;
(vii) the initial positive sequence resistance and reactance values of the two (or more)
sources and the linking impedance(s) derived from a fault study constituting the ()
equivalent and evaluated without the User network and load and where appropriate
without elements of the National Electricity Transmission System between the User
network and agreed boundary nodes (and in case of OTSUA, each Interface Point and
Connection Point);
(viii) the positive sequence resistance and reactance values of the two (or more) sources
and the linking impendence(s) derived from a fault study, considering the short circuit
current contributions after the subtransient fault current contribution has substantially
decayed, constituting the () equivalent and evaluated without the User network and
load, and where appropriate without elements of the National Electricity
Transmission System between the User network and agreed boundary nodes (and in
case of OTSUA, each Interface Point and Connection Point);
(ix) the corresponding zero sequence impedance values of the () equivalent produced for
use in fault level analysis;
(x) the Demand and voltage at the boundary nodes and the positive sequence resistance
and reactance values of the linking impedance(s) derived from a loadflow study
considering National Electricity Transmission System peak Demand constituting the
() loadflow equivalent; and,
(xi) where the agreed boundary nodes are not at a Connection Point (and in case of
OTSUA, Interface Point or Connection Point), the positive sequence and zero
sequence impedances of all elements of the National Electricity Transmission
System between the User network and agreed boundary nodes that are not included in
the equivalent (and in case of OTSUA, each Interface Point and Connection Point).
(b) To enable the model to be constructed, NGET will provide data based on the following
conditions.
(c) The initial symmetrical three phase short circuit current and the transient period three phase
short circuit current will normally be derived from the fixed impedance studies. The latter
value should be taken as applying at times of 120ms and longer. Shorter values may be
interpolated using a value for the subtransient time constant of 40ms. These fault currents
will be obtained from a full System study based on load flow analysis that takes into account
any existing flow across the point of connection being considered.
(d) Since the equivalent will be produced for the 400kV or 275kV and also in Scotland and
Offshore132kV parts of the National Electricity Transmission System NGET will provide
the appropriate supergrid transformer data.
(e) The positive sequence X/R ratio and the zero sequence impedance value will correspond to
the NGET source network only, that is with the section of network if any with which the
equivalent is to be used excluded. These impedance values will be derived from the
condition when all Generating Units are Synchronised to the National Electricity
Transmission System or a User's System and will take account of active sources only
including any contribution from the load to the fault current. The passive component of the
load itself or other system shunt impedances should not be included.
(f) A User may at any time, in writing, specifically request for an equivalent to be prepared for
an alternative System condition, for example where the User's System peak does not
correspond to the National Electricity Transmission System peak, and NGET will, insofar
as such request is reasonable, provide the information as soon as reasonably practicable
following the request.

Issue 5 Revision 15 PC 03 February 2016


61 of 72
APPENDIX B - SINGLE LINE DIAGRAMS
PC.B.1 The diagrams below show three examples of single line diagrams, showing the detail that should
be incorporated in the diagram. The first example is for an Network Operator connection, the
second for a Generator connection, the third for a Power Park Module electrically equivalent
system.

Network Operator Single Line Diagram

Issue 5 Revision 15 PC 03 February 2016


62 of 72
Generator Single Line Diagram

Issue 5 Revision 15 PC 03 February 2016


63 of 72
Power Park Module Single Line Diagram

Notes:
(1) The electrically equivalent Power Park Unit consists of a number of actual Power Park
Units of the same type ie. any equipment external to the Power Park Unit terminals is
considered as part of the Equivalent Network. Power Park Units of different types shall be
included in separate electrically equivalent Power Park Units. The total number of
equivalent Power Park Units shall represent all of the actual Power Park Units in the
Power Park Module.
(2) Separate electrically equivalent networks are required for each different type of electrically
equivalent Power Park Unit. The electrically equivalent network shall include all equipment
between the Power Park Unit terminals and the Common Collection Busbar.
(3) All Plant and Apparatus including the circuit breakers, transformers, lines, cables and
reactive compensation plant between the Common Collection Busbar and Substation A
shall be shown.

Issue 5 Revision 15 PC 03 February 2016


64 of 72
APPENDIX C - TECHNICAL AND DESIGN CRITERIA
PC.C.1 Planning and design of the SPT and SHETL Transmission Systems is based generally, but not
totally, on criteria which evolved from joint consultation among various Transmission Licensees
responsible for design of the National Electricity Transmission System.
PC.C.2 The above criteria are set down within the standards, memoranda, recommendations and reports
and are provided as a guide to system planning. It should be noted that each scheme for
reinforcement or modification of the Transmission System is individually designed in the light of
economic and technical factors associated with the particular system limitations under
consideration.
PC.C.3 The tables below identify the literature referred to above, together with the main topics
considered within each document.

PART 1 SHETL's TECHNICAL AND DESIGN CRITERIA

ITEM No. DOCUMENT REFERENCE No.


1 National Electricity Transmission System Security and Quality Version [ ]
of Supply Standard
2 System Phasing TPS 13/4
3 Not used
4 Planning Limits for Voltage Fluctuations Caused by Industrial, ER P28
Commercial and Domestic Equipment in the United Kingdom
5 EHV or HV Supplies to Induction Furnaces ER P16
(Supported by
Voltage unbalance limits. ACE Report
Harmonic current limits. No.48)
6 Planning Levels for Harmonic Voltage Distortion and the ER G5/4
Connection of Non-Linear Loads to Transmission Systems (Supported by
and Public Electricity Supply Systems in the United Kingdom ACE Report
No.73)
Harmonic distortion (waveform).
Harmonic voltage distortion.
Harmonic current distortion.
Stage 1 limits.
Stage 2 limits.
Stage 3 Limits
Addition of Harmonics
Short Duration Harmonics
Site Measurements
7 AC Traction Supplies to British Rail ER P24

Type of supply point to railway system.


Estimation of traction loads.
Nature of traction current.
System disturbance estimation.
Earthing arrangements.

Issue 5 Revision 15 PC 03 February 2016


65 of 72
ITEM No. DOCUMENT REFERENCE No.
8 Operational Memoranda (SOM)

Main System operating procedure. SOM 1

Operational standards of security. SOM 3

Voltage and reactive control on main system. SOM 4

System warnings and procedures for instructed load SOM 7


reduction.

Continuous tape recording of system control telephone SOM 10


messages and instructions.

Emergency action in the event of an exceptionally SOM 15


serious breakdown of the main system.
9 Planning Limits for Voltage Unbalance in the United Kingdom. ER P29

Issue 5 Revision 15 PC 03 February 2016


66 of 72
PART 2 - SPT's TECHNICAL AND DESIGN CRITERIA

ITEM No. DOCUMENT REFERENCE No.


1 National Electricity Transmission System Security and Version [ ]
Quality of Supply Standard
2 System Phasing TDM 13/10,002
Issue 4
3 Not used
4 Planning Limits for Voltage Fluctuations Caused by ER P28
Industrial, Commercial and Domestic Equipment in the
United Kingdom
5 EHV or HV Supplies to Induction Furnaces ER P16
(Supported by
Voltage Unbalance limits. ACE Report
Harmonic current limits. No.48)
6 Planning Levels for Harmonic Voltage Distortion and the ER G5/4
Connection of Non-Linear Loads to Transmission Systems (Supported by
and Public Electricity Supply Systems in the United ACE Report
Kingdom No.73)

Harmonic distortion (waveform).


Harmonic voltage distortion.
Harmonic current distortion.
Stage 1 limits.
Stage 2 limits.
Stage 3 Limits
Addition of Harmonics
Short Duration Harmonics
Site Measurements
7 AC Traction Supplies to British Rail ER P24

Type of supply point to railway system.


Estimation of traction loads.
Nature of traction current.
System disturbance estimation.
Earthing arrangements.

Issue 5 Revision 15 PC 03 February 2016


67 of 72
APPENDIX D - DATA NOT DISCLOSED TO A RELEVANT
TRANSMISSION LICENSEE
PC.D.1 Pursuant to PC.3.4, NGET will not disclose to a Relevant Transmission Licensee data items
specified in the below extract:

PC DATA
DATA DESCRIPTION UNITS
REFERENCE CATEGORY

PC.A.3.2.2 (f) (i) Performance Chart at Generating Unit stator terminals SPD

PC.A.3.2.2 (b) Output Usable (on a monthly basis) MW SPD

PC.A.5.3.2 (d) GOVERNOR AND ASSOCIATED PRIME MOVER


Option 1 (iii) PARAMETERS

Option 1

BOILER & STEAM TURBINE DATA

Boiler time constant (Stored Active Energy) S DPD II

HP turbine response ratio: (Proportion of Primary % DPD II


Response arising from HP turbine)

HP turbine response ratio: (Proportion of High Frequency % DPD II


Response arising from HP turbine)

Part of Option 2
PC.A.5.3.2 (d)
Option 2 (i) All Generating Units

Governor Deadband

- Maximum Setting Hz DPD II

- Normal Setting Hz DPD II

- Minimum Setting Hz DPD II

Part of Steam Units


PC.A.5.3.2 (d)
Option 2 (ii)

Reheater Time Constant sec DPD II

Boiler Time Constant sec DPD II

HP Power Fraction % DPD II

IP Power Fraction % DPD II

Part of Gas Turbine Units


PC.A.5.3.2 (d)
Option 2 (iii) Waste Heat Recovery Boiler Time Constant

Part of UNIT CONTROL OPTIONS


PC.A.5.3.2 (e)
Maximum droop % DPD II

Minimum droop % DPD II

Maximum frequency deadband Hz DPD II

Issue 5 Revision 15 PC 03 February 2016


68 of 72
PC DATA
DATA DESCRIPTION UNITS
REFERENCE CATEGORY

Normal frequency deadband Hz DPD II

Minimum frequency deadband Hz DPD II

Maximum Output deadband MW DPD II

Normal Output deadband MW DPD II

Minimum Output deadband MW DPD II

Frequency settings between which Unit Load Controller


droop applies:
Maximum Hz DPD II

Normal Hz DPD II

Minimum Hz DPD II

Sustained response normally selected Yes/No DPD II

PC.A.3.2.2 (f) (ii) Performance Chart of a Power Park Modules at the SPD
connection point

PC.A.3.2.2 (b) Output Usable (on a monthly basis) MW SPD

PC.A.3.2.2 (e) DC CONVERTER STATION DATA


and (j)
ACTIVE POWER TRANSFER CAPABILITY (PC.A.3.2.2)

Import MW available in excess of Registered Import MW SPD


Capacity.

Time duration for which MW in excess of Registered Min SPD


Import Capacity is available

Export MW available in excess of Registered Capacity. MW SPD

Time duration for which MW in excess of Registered Min SPD


Capacity is available

Part of LOADING PARAMETERS


PC.A.5.4.3.3

MW Export

Nominal loading rate MW/s DPD I

Maximum (emergency) loading rate MW/s DPD I

MW Import

Nominal loading rate MW/s DPD I

Maximum (emergency) loading rate MW/s DPD I

Issue 5 Revision 15 PC 03 February 2016


69 of 72
APPENDIX E - OFFSHORE TRANSMISSION SYSTEM AND OTSDUW
PLANT AND APPARATUS TECHNICAL AND DESIGN CRITERIA
PC.E.1 In the absence of any relevant Electrical Standards, Offshore Transmission Licensees and
Generators undertaking OTSDUW are required to ensure that all equipment used in the
construction of their network is:
(i) Fully compliant and suitably designed to any relevant Technical Specification;
(ii) Suitable for use and operation in an Offshore environment, where such parts of the
Offshore Transmission System and OTSDUW Plant and Apparatus are located in
Offshore Waters and are not installed in an area that is protected from that Offshore
environment, and
(iii) Compatible with any relevant Electrical Standards or Technical Specifications at the
Offshore Grid Entry Point and Interface Point.
PC.E.2 The table below identifies the technical and design criteria that will be used in the design and
development of an Offshore Transmission System and OTSDUW Plant and Apparatus.

ITEM No. DOCUMENT REFERENCE No.


1 National Electricity Transmission System Security and Quality of Version [ ]
Supply Standard
2* Planning Limits for Voltage Fluctuations Caused by Industrial, ER P28
Commercial and Domestic Equipment in the United Kingdom
3* Planning Levels for Harmonic Voltage Distortion and the Connection ER G5/4
of Non-Linear Loads to Transmission Systems and Public Electricity
Supply Systems in the United Kingdom
4* Planning Limits for Voltage Unbalance in the United Kingdom ER P29

* Note:- Items 2, 3 and 4 above shall only apply at the Interface Point.

Issue 5 Revision 15 PC 03 February 2016


70 of 72
APPENDIX F - OTSDUW DATA AND INFORMATION AND OTSDUW
NETWORK DATA AND INFORMATION
PC.F.1 Introduction
PC.F.1.1 Appendix F specifies data requirements to be submitted to NGET by Users and Users by NGET
in respect of OTSDUW.
PC.F.1.2 Such User submissions shall be in accordance with the OTSDUW Development and Data
Timetable in a Construction Agreement.
PC.F.1.3 Such NGET submissions shall be issued with the offer of a CUSC Contract in the case of the
data in Part 1 and otherwise in accordance with the OTSDUW Development and Data
Timetable in a Construction Agreement.
PC.F.2. OTSDUW Network Data and Information
PC.F.2.1 With the offer of a CUSC Contract under the OTSDUW Arrangements NGET shall provide:
(a) the site specific technical design and operational criteria for the Connection Site;
(b) the site specific technical design and operational criteria for the Interface Point, and
(c) details of NGETs preliminary identification and consideration of the options available for the
Interface Point in the context of the Users application for connection or modification, the
preliminary costs used by NGET in assessing such options and the Offshore Works
Assumptions including the assumed Interface Point identified during these preliminary
considerations.
PC.F.2.2 In accordance with the OTSDUW Development and Data Timetable in a Construction
Agreement NGET shall provide the following information and data to a User:
(a) equivalent of the fault infeed or fault level ratings at the Interface Point (as identified in the
Offshore Works Assumptions)
(b) notification of numbering and nomenclature of the HV Apparatus comprised in the
OTSDUW;
(i) past or present physical properties, including both actual and designed physical
properties, of Plant and Apparatus forming part of the National Electricity
Transmission System at the Interface Point at which the OTSUA will be connected to
the extent it is required for the design and construction of the OTSDUW, including but
not limited to:
(ii) the voltage of any part of such Plant and Apparatus;
(iii) the electrical current flowing in or over such Plant and Apparatus;
(iv) the configuration of any part of such Plant and Apparatus
(v) the temperature of any part of such Plant and Apparatus;
(vi) the pressure of any fluid forming part of such Plant and Apparatus
(vii) the electromagnetic properties of such Plant and Apparatus; and
(viii) the technical specifications, settings or operation of any Protection Systems forming
part of such Plant and Apparatus.
(c) information necessary to enable the User to harmonise the OTSDUW with construction
works elsewhere on the National Electricity Transmission System that could affect the
OTSDUW
(d) information related to the current or future configuration of any circuits of the Onshore
Transmission System with which the OTSUA are to connect;

Issue 5 Revision 15 PC 03 February 2016


71 of 72
(e) any changes which are planned on the National Electricity Transmission System in the
current or following six Financial Years and which will materially affect the planning or
development of the OTSDUW.
PC.F.2.3 At the User's reasonable request additional information and data in respect of the National
Electricity Transmission System shall be provided.
PC.F.2.4 OTSDUW Data And Information
PC.F.2.4.1 In accordance with the OTSDUW Development and Data Timetable in a Construction
Agreement the User shall provide to NGET the following information and data relating to the
OTSDUW Plant and Apparatus in accordance with Appendix A of the Planning Code.

< END OF PLANNING CODE >

Issue 5 Revision 15 PC 03 February 2016


72 of 72
CONNECTION CONDITIONS
(CC)

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


CC.1 INTRODUCTION .......................................................................................................................................2
CC.2 OBJECTIVE ..............................................................................................................................................2
CC.3 SCOPE ......................................................................................................................................................2
CC.4 PROCEDURE ...........................................................................................................................................4
CC.5 CONNECTION ..........................................................................................................................................4
CC.6 TECHNICAL, DESIGN AND OPERATIONAL CRITERIA .........................................................................6
CC.7 SITE RELATED CONDITIONS ...............................................................................................................44
CC.8 ANCILLARY SERVICES .........................................................................................................................51
APPENDIX 1 - SITE RESPONSIBILITY SCHEDULES .....................................................................................53
PROFORMA FOR SITE RESPONSIBILITY SCHEDULE ..........................................................................56
APPENDIX 2 - OPERATION DIAGRAMS..........................................................................................................60
PART 1A - PROCEDURES RELATING TO OPERATION DIAGRAMS ....................................................60
PART 1B - PROCEDURES RELATING TO GAS ZONE DIAGRAMS .......................................................63
PART 2 - NON-EXHAUSTIVE LIST OF APPARATUS TO BE INCLUDED ON OPERATION
DIAGRAMS .................................................................................................................................................64
APPENDIX 3 - MINIMUM FREQUENCY RESPONSE REQUIREMENT PROFILE AND OPERATING
RANGE FOR NEW POWER STATIONS AND DC CONVERTER STATIONS .................................................66
APPENDIX 4 - FAULT RIDE THROUGH REQUIREMENTS .............................................................................71
APPENDIX 4A ............................................................................................................................................71
APPENDIX 4B ............................................................................................................................................77
APPENDIX 5 - TECHNICAL REQUIREMENTS LOW FREQUENCY RELAYS FOR THE AUTOMATIC
DISCONNECTION OF SUPPLIES AT LOW FREQUENCY ..............................................................................83
APPENDIX 6 - PERFORMANCE REQUIREMENTS FOR CONTINUOUSLY ACTING AUTOMATIC
EXCITATION CONTROL SYSTEMS FOR ONSHORE SYNCHRONOUS GENERATING UNITS ...................85
APPENDIX 7 - PERFORMANCE REQUIREMENTS FOR CONTINUOUSLY ACTING AUTOMATIC
VOLTAGE CONTROL SYSTEMS FOR ONSHORE NON-SYNCHRONOUS GENERATING UNITS,
ONSHORE DC CONVERTERS, ONSHORE POWER PARK MODULES AND OTSDUW PLANT AND
APPARATUS AT THE INTERFACE POINT ......................................................................................................89

Issue 5 Revision 17 CC 29 June 2016


i
CC.1 INTRODUCTION
CC.1.1 The Connection Conditions ("CC") specify both:
(a) the minimum technical, design and operational criteria which must be complied with by:
(i) any User connected to or seeking connection with the National Electricity
Transmission System, or
(ii) Generators (other than in respect of Small Power Stations) or DC Converter
Station owners connected to or seeking connection to a User's System which is
located in Great Britain or Offshore, and
(b) the minimum technical, design and operational criteria with which NGET will comply in
relation to the part of the National Electricity Transmission System at the
Connection Site with Users. In the case of any OTSDUW Plant and Apparatus, the
CC also specify the minimum technical, design and operational criteria which must be
complied with by the User when undertaking OTSDUW.

CC.2 OBJECTIVE
CC.2.1 The objective of the CC is to ensure that by specifying minimum technical, design and
operational criteria the basic rules for connection to the National Electricity Transmission
System and (for certain Users) to a User's System are similar for all Users of an equivalent
category and will enable NGET to comply with its statutory and Transmission Licence
obligations.
CC.2.2 In the case of any OTSDUW the objective of the CC is to ensure that by specifying the
minimum technical, design and operational criteria the basic rules relating to an Offshore
Transmission System designed and constructed by an Offshore Transmission Licensee
and designed and/or constructed by a User under the OTSDUW Arrangements are
equivalent.
CC.2.3 Provisions of the CC which apply in relation to OTSDUW and OTSUA, and/or a
Transmission Interface Site, shall (in any particular case) apply up to the OTSUA Transfer
Time, whereupon such provisions shall (without prejudice to any prior non-compliance)
cease to apply, without prejudice to the continuing application of provisions of the CC
applying in relation to the relevant Offshore Transmission System and/or Connection
Site. It is the case therefore that in cases where the OTSUA become operational prior to the
OTSUA Transfer Time that a Generator is required to comply with this CC both as it
applies to its Plant and Apparatus at a Connection Site\Connection Point and the
OTSUA at the Transmission Interface Site/Transmission Interface Point until the
OTSUA Transfer Time and this CC shall be construed accordingly.
CC.2.4 In relation to OTSDUW, provisions otherwise to be contained in a Bilateral Agreement may
be contained in the Construction Agreement, and accordingly a reference in the CC to a
relevant Bilateral Agreement includes the relevant Construction Agreement.

CC.3 SCOPE
CC.3.1 The CC applies to NGET and to Users, which in the CC means:
(a) Generators (other than those which only have Embedded Small Power Stations),
including those undertaking OTSDUW;
(b) Network Operators;
(c) Non-Embedded Customers;
(d) DC Converter Station owners; and
(e) BM Participants and Externally Interconnected System Operators in respect of
CC.6.5 only.

Issue 5 Revision 17 CC 29 June 2016


2 of 95
CC.3.2 The above categories of User will become bound by the CC prior to them generating,
distributing, supplying or consuming, as the case may be, and references to the various
categories should, therefore, be taken as referring to them in that prospective role as well as
to Users actually connected.

CC.3.3 Embedded Medium Power Stations not subject to a Bilateral Agreement and Embedded
DC Converter Stations not subject to a Bilateral Agreement Provisions.
The following provisions apply in respect of Embedded Medium Power Stations not
subject to a Bilateral Agreement and Embedded DC Converter Stations not subject to a
Bilateral Agreement.
CC.3.3.1 The obligations within the CC that are expressed to be applicable to Generators in respect
of Embedded Medium Power Stations not subject to a Bilateral Agreement and DC
Converter Station Owners in respect of Embedded DC Converter Stations not subject to
a Bilateral Agreement (where the obligations are in each case listed in CC.3.3.2) shall be
read and construed as obligations that the Network Operator within whose System any
such Medium Power Station or DC Converter Station is Embedded must ensure are
performed and discharged by the Generator or the DC Converter Station owner.
Embedded Medium Power Stations not subject to a Bilateral Agreement and Embedded
DC Converter Stations not subject to a Bilateral Agreement which are located Offshore
and which are connected to an Onshore User System will be required to meet the
applicable requirements of the Grid Code as though they are an Onshore Generator or
Onshore DC Converter Station Owner connected to an Onshore User System Entry
Point.
CC.3.3.2 The Network Operator within whose System a Medium Power Station not subject to a
Bilateral Agreement is Embedded or a DC Converter Station not subject to a Bilateral
Agreement is Embedded must ensure that the following obligations in the CC are
performed and discharged by the Generator in respect of each such Embedded Medium
Power Station or the DC Converter Station owner in the case of an Embedded DC
Converter Station:
CC.5.1
CC.5.2.2
CC.5.3
CC.6.1.3
CC.6.1.5 (b)
CC.6.3.2, CC.6.3.3, CC.6.3.4, CC.6.3.6, CC.6.3.7, CC.6.3.8, CC.6.3.9, CC.6.3.10,
CC.6.3.12, CC.6.3.13, CC.6.3.15, CC.6.3.16
CC.6.4.4
CC.6.5.6 (where required by CC.6.4.4)

In respect of CC.6.2.2.2, CC.6.2.2.3, CC.6.2.2.5, CC.6.1.5(a), CC.6.1.5(b) and


CC.6.3.11 equivalent provisions as co-ordinated and agreed with the Network
Operator and Generator or DC Converter Station owner may be required. Details of
any such requirements will be notified to the Network Operator in accordance with
CC.3.5.
CC.3.3.3 In the case of Embedded Medium Power Stations not subject to a Bilateral Agreement
and Embedded DC Converter Stations not subject to a Bilateral Agreement the
requirements in:
CC.6.1.6
CC.6.3.8
CC.6.3.12
Issue 5 Revision 17 CC 29 June 2016
3 of 95
CC.6.3.15
CC.6.3.16

that would otherwise have been specified in a Bilateral Agreement will be notified to the
relevant Network Operator in writing in accordance with the provisions of the CUSC and the
Network Operator must ensure such requirements are performed and discharged by the
Generator or the DC Converter Station owner.
CC.3.4 In the case of Offshore Embedded Power Stations connected to an Offshore Users
System which directly connects to an Offshore Transmission System, any additional
requirements in respect of such Offshore Embedded Power Stations may be specified in
the relevant Bilateral Agreement with the Network Operator or in any Bilateral
Agreement between NGET and such Offshore Embedded Power Station.
CC.3.5 In the case of a Generator undertaking OTSDUW connecting to an Onshore Network
Operators System, any additional requirements in respect of such OTSDUW Plant and
Apparatus will be specified in the relevant Bilateral Agreement with the Generator. For the
avoidance of doubt, requirements applicable to Generators undertaking OTSDUW and
connecting to a Network Operators User System, shall be consistent with those applicable
requirements of Generators undertaking OTSDUW and connecting to a Transmission
Interface Point.

CC.4 PROCEDURE
CC.4.1 The CUSC contains certain provisions relating to the procedure for connection to the
National Electricity Transmission System or, in the case of Embedded Power Stations
or Embedded DC Converter Stations, becoming operational and includes provisions
relating to certain conditions to be complied with by Users prior to and during the course of
NGET notifying the User that it has the right to become operational. The procedure for a
User to become connected is set out in the Compliance Processes.

CC.5 CONNECTION
CC.5.1 The provisions relating to connecting to the National Electricity Transmission System (or
to a User's System in the case of a connection of an Embedded Large Power Station or
Embedded Medium Power Station or Embedded DC Converter Station) are contained in:
(a) the CUSC and/or CUSC Contract (or in the relevant application form or offer for a
CUSC Contract);
(b) or, in the case of an Embedded Development, the relevant Distribution Code and/or
the Embedded Development Agreement for the connection (or in the relevant
application form or offer for an Embedded Development Agreement),
and include provisions relating to both the submission of information and reports relating to
compliance with the relevant Connection Conditions for that User, Safety Rules,
commissioning programmes, Operation Diagrams and approval to connect (and their
equivalents in the case of Embedded Medium Power Stations not subject to a Bilateral
Agreement or Embedded DC Converter Stations not subject to a Bilateral Agreement).
References in the CC to the "Bilateral Agreement and/or Construction Agreement"
and/or Embedded Development Agreement shall be deemed to include references to the
application form or offer therefor.
CC.5.2 Items For Submission
CC.5.2.1 Prior to the Completion Date (or, where the Generator is undertaking OTSDUW, any later
date specified) under the Bilateral Agreement and/or Construction Agreement, the
following is submitted pursuant to the terms of the Bilateral Agreement and/or
Construction Agreement:

Issue 5 Revision 17 CC 29 June 2016


4 of 95
(a) updated Planning Code data (both Standard Planning Data and Detailed Planning
Data), with any estimated values assumed for planning purposes confirmed or, where
practical, replaced by validated actual values and by updated estimates for the future
and by updated forecasts for Forecast Data items such as Demand, pursuant to the
requirements of the Planning Code;

(b) details of the Protection arrangements and settings referred to in CC.6;


(c) copies of all Safety Rules and Local Safety Instructions applicable at Users' Sites
which will be used at the NGET/User interface (which, for the purpose of OC8, must be
to NGETs satisfaction regarding the procedures for Isolation and Earthing. For User
Sites in Scotland and Offshore NGET will consult the Relevant Transmission
Licensee when determining whether the procedures for Isolation and Earthing are
satisfactory);
(d) information to enable NGET to prepare Site Responsibility Schedules on the basis of
the provisions set out in Appendix 1;
(e) an Operation Diagram for all HV Apparatus on the User side of the Connection
Point as described in CC.7;
(f) the proposed name of the User Site (which shall not be the same as, or confusingly
similar to, the name of any Transmission Site or of any other User Site);
(g) written confirmation that Safety Co-ordinators acting on behalf of the User are
authorised and competent pursuant to the requirements of OC8;
(h) RISSP prefixes pursuant to the requirements of OC8. NGET is required to circulate
prefixes utilising a proforma in accordance with OC8;
(i) a list of the telephone numbers for Joint System Incidents at which senior
management representatives nominated for the purpose can be contacted and
confirmation that they are fully authorised to make binding decisions on behalf of the
User, pursuant to OC9;
(j) a list of managers who have been duly authorised to sign Site Responsibility
Schedules on behalf of the User;
(k) information to enable NGET to prepare Site Common Drawings as described in CC.7;
(l) a list of the telephone numbers for the Users facsimile machines referred to in
CC.6.5.9; and
(m) for Sites in Scotland and Offshore a list of persons appointed by the User to undertake
operational duties on the Users System (including any OTSDUW prior to the OTSUA
Transfer Time) and to issue and receive operational messages and instructions in
relation to the Users System (including any OTSDUW prior to the OTSUA Transfer
Time); and an appointed person or persons responsible for the maintenance and testing
of Users Plant and Apparatus.
CC.5.2.2 Prior to the Completion Date the following must be submitted to NGET by the Network
Operator in respect of an Embedded Development:
(a) updated Planning Code data (both Standard Planning Data and Detailed Planning
Data), with any estimated values assumed for planning purposes confirmed or, where
practical, replaced by validated actual values and by updated estimates for the future
and by updated forecasts for Forecast Data items such as Demand, pursuant to the
requirements of the Planning Code;
(b) details of the Protection arrangements and settings referred to in CC.6;
(c) the proposed name of the Embedded Medium Power Station or Embedded DC
Converter Station Site (which shall be agreed with NGET unless it is the same as, or
confusingly similar to, the name of other Transmission Site or User Site);

Issue 5 Revision 17 CC 29 June 2016


5 of 95
CC.5.2.3 Prior to the Completion Date contained within an Offshore Transmission Distribution
Connection Agreement the following must be submitted to NGET by the Network
Operator in respect of a proposed new Interface Point within its User System:
(a) updated Planning Code data (both Standard Planning Data and Detailed Planning
Data), with any estimated values assumed for planning purposes confirmed or, where
practical, replaced by validated actual values and by updated estimates for the future
and by updated forecasts for Forecast Data items such as Demand, pursuant to the
requirements of the Planning Code;
(b) details of the Protection arrangements and settings referred to in CC.6;
(c) the proposed name of the Interface Point (which shall not be the same as, or
confusingly similar to, the name of any Transmission Site or of any other User Site);
CC.5.2.4 In the case of OTSDUW Plant and Apparatus (in addition to items under CC.5.2.1 in
respect of the Connection Site), prior to the Completion Date (or any later date specified)
under the Construction Agreement the following must be submitted to NGET by the User
in respect of the proposed new Connection Point and Interface Point:
(a) updated Planning Code data (Standard Planning Data, Detailed Planning Data and
OTSDUW Data and Information), with any estimated values assumed for planning
purposes confirmed or, where practical, replaced by validated actual values and by
updated estimates for the future and by updated forecasts for Forecast Data items
such as Demand, pursuant to the requirements of the Planning Code;
(b) details of the Protection arrangements and settings referred to in CC.6;
(c) information to enable preparation of the Site Responsibility Schedules at the
Transmission Interface Site on the basis of the provisions set out in Appendix 1.
(d) the proposed name of the Interface Point (which shall not be the same as, or
confusingly similar to, the name of any Transmission Site or of any other User Site);
CC.5.3 (a) Of the items CC.5.2.1 (c), (e), (g), (h), (k) and (m) need not be supplied in respect of
Embedded Power Stations or Embedded DC Converter Stations,
(b) item CC.5.2.1(i) need not be supplied in respect of Embedded Small Power Stations
and Embedded Medium Power Stations or Embedded DC Converter Stations with
a Registered Capacity of less than 100MW, and
(c) items CC.5.2.1(d) and (j) are only needed in the case where the Embedded Power
Station or the Embedded DC Converter Station is within a Connection Site with
another User.
CC.5.4 In addition, at the time the information is given under CC.5.2(g), NGET will provide written
confirmation to the User that the Safety Co-ordinators acting on behalf of NGET are
authorised and competent pursuant to the requirements of OC8.

CC.6 TECHNICAL, DESIGN AND OPERATIONAL CRITERIA


CC.6.1 National Electricity Transmission System Performance Characteristics
CC.6.1.1 NGET shall ensure that, subject as provided in the Grid Code, the National Electricity
Transmission System complies with the following technical, design and operational criteria
in relation to the part of the National Electricity Transmission System at the Connection
Site with a User and in the case of OTSDUW Plant and Apparatus, a Transmission
Interface Point (unless otherwise specified in CC.6) although in relation to operational
criteria NGET may be unable (and will not be required) to comply with this obligation to the
extent that there are insufficient Power Stations or User Systems are not available or
Users do not comply with NGET's instructions or otherwise do not comply with the Grid
Code and each User shall ensure that its Plant and Apparatus complies with the criteria set
out in CC.6.1.5.

Issue 5 Revision 17 CC 29 June 2016


6 of 95
Grid Frequency Variations
CC.6.1.2 The Frequency of the National Electricity Transmission System shall be nominally 50Hz
and shall be controlled within the limits of 49.5 - 50.5Hz unless exceptional circumstances
prevail.
CC.6.1.3 The System Frequency could rise to 52Hz or fall to 47Hz in exceptional circumstances.
Design of User's Plant and Apparatus and OTSDUW Plant and Apparatus must enable
operation of that Plant and Apparatus within that range in accordance with the following:
Frequency Range Requirement
51.5Hz - 52Hz Operation for a period of at least 15 minutes is required
each time the Frequency is above 51.5Hz.
51Hz - 51.5Hz Operation for a period of at least 90 minutes is required
each time the Frequency is above 51Hz.
49.0Hz - 51Hz Continuous operation is required
47.5Hz - 49.0Hz Operation for a period of at least 90 minutes is required
each time the Frequency is below 49.0Hz.
47Hz - 47.5Hz Operation for a period of at least 20 seconds is required
each time the Frequency is below 47.5Hz.

For the avoidance of doubt, disconnection, by frequency or speed based relays is not
permitted within the frequency range 47.5Hz to 51.5Hz, unless agreed with NGET in
accordance with CC.6.3.12.
Grid Voltage Variations
CC.6.1.4 Subject as provided below, the voltage on the 400kV part of the National Electricity
Transmission System at each Connection Site with a User (and in the case of OTSDUW
Plant and Apparatus, a Transmission Interface Point) will normally remain within 5% of
the nominal value unless abnormal conditions prevail. The minimum voltage is -10% and the
maximum voltage is +10% unless abnormal conditions prevail, but voltages between +5%
and +10% will not last longer than 15 minutes unless abnormal conditions prevail. Voltages
on the 275kV and 132kV parts of the National Electricity Transmission System at each
Connection Site with a User (and in the case of OTSDUW Plant and Apparatus, a
Transmission Interface Point) will normally remain within the limits 10% of the nominal
value unless abnormal conditions prevail. At nominal System voltages below 132kV the
voltage of the National Electricity Transmission System at each Connection Site with a
User (and in the case of OTSDUW Plant and Apparatus, a Transmission Interface Point)
will normally remain within the limits 6% of the nominal value unless abnormal conditions
prevail. Under fault conditions, voltage may collapse transiently to zero at the point of fault
until the fault is cleared. The normal operating ranges of the National Electricity
Transmission System are summarised below:

National Electricity Transmission System Normal Operating Range


Nominal Voltage
400kV 400kV 5%
275kV 275kV 10%
132kV 132kV 10%

NGET and a User may agree greater or lesser variations in voltage to those set out above in
relation to a particular Connection Site, and insofar as a greater or lesser variation is
agreed, the relevant figure set out above shall, in relation to that User at the particular
Connection Site, be replaced by the figure agreed.

Issue 5 Revision 17 CC 29 June 2016


7 of 95
Voltage Waveform Quality
CC.6.1.5 All Plant and Apparatus connected to the National Electricity Transmission System, and
that part of the National Electricity Transmission System at each Connection Site or, in
the case of OTSDUW Plant and Apparatus, at each Interface Point, should be capable of
withstanding the following distortions of the voltage waveform in respect of harmonic content
and phase unbalance:
(a) Harmonic Content
The Electromagnetic Compatibility Levels for harmonic distortion on the Onshore
Transmission System from all sources under both Planned Outage and fault outage
conditions, (unless abnormal conditions prevail) shall comply with the levels shown in
the tables of Appendix A of Engineering Recommendation G5/4. The
Electromagnetic Compatibility Levels for harmonic distortion on an Offshore
Transmission System will be defined in relevant Bilateral Agreements.
Engineering Recommendation G5/4 contains planning criteria which NGET will apply
to the connection of non-linear Load to the National Electricity Transmission
System, which may result in harmonic emission limits being specified for these Loads
in the relevant Bilateral Agreement. The application of the planning criteria will take
into account the position of existing and prospective Users Plant and Apparatus (and
OTSDUW Plant and Apparatus) in relation to harmonic emissions. Users must
ensure that connection of distorting loads to their User Systems do not cause any
harmonic emission limits specified in the Bilateral Agreement, or where no such limits
are specified, the relevant planning levels specified in Engineering Recommendation
G5/4 to be exceeded.
(b) Phase Unbalance
Under Planned Outage conditions, the weekly 95 percentile of Phase (Voltage)
Unbalance, calculated in accordance with IEC 61000-4-30 and IEC 61000-3-13, on the
National Electricity Transmission System for voltages above 150kV should remain,
in England and Wales, below 1.5%, and in Scotland, below 2%, and for voltages of
150kV and below, across GB below 2%, unless abnormal conditions prevail and
Offshore (or in the case of OTSDUW, OTSDUW Plant and Apparatus) will be defined
in relevant Bilateral Agreements.
The Phase Unbalance is calculated from the ratio of root mean square (rms) of negative
phase sequence voltage to rms of positive phase sequence voltage, based on 10-
minute average values, in accordance with IEC 61000-4-30.
CC.6.1.6 Across GB, under the Planned Outage conditions stated in CC.6.1.5(b) infrequent short
duration peaks with a maximum value of 2% are permitted for Phase (Voltage) Unbalance,
for voltages above 150kV, subject to the prior agreement of NGET under the Bilateral
Agreement and in relation to OTSDUW, the Construction Agreement. NGET will only
agree following a specific assessment of the impact of these levels on Transmission
Apparatus and other Users Apparatus with which it is satisfied.
Voltage Fluctuations
CC.6.1.7 Voltage changes at a Point of Common Coupling on the Onshore Transmission System
shall not exceed:
(a) The limits specified in Table CC.6.1.7 with the stated frequency of occurrence, where:

(i) Vsteadystate
%Vsteadystate = 100 x
V0

and

Vmax
%Vmax =100 x ;
V0

Issue 5 Revision 17 CC 29 June 2016


8 of 95
(ii) V0 is the initial steady state system voltage;

(iii) Vsteadystate is the system voltage reached when the rate of change of system
voltage over time is less than or equal to 0.5% over 1 second and Vsteadystate is
the absolute value of the difference between Vsteadystate and V0;
(iv) Vmax is the absolute value of the maximum change in the system voltage relative
to the initial steady state system voltage of V0;
(v) All voltages are the root mean square of the voltage measured over one cycle
refreshed every half a cycle as per IEC 61000-4-30;
(vi) The voltage changes specified are the absolute maximum allowed, applied to
phase to ground or phase to phase voltages whichever is the highest change;
(vii) Voltage changes in category 3 do not exceed the limits depicted in the time
dependant characteristic shown in Figure CC.6.1.7;
(viii) Voltage changes in category 3 only occur infrequently, typically not planned more
than once per year on average over the lifetime of a connection, and in
circumstances notified to NGET, such as for example commissioning in
accordance with a commissioning programme, implementation of a planned
outage notified in accordance with OC2 or an Operation or Event notified in
accordance with OC7; and
st
(ix) For connections with a Completion Date after 1 September 2015 and where
voltage changes would constitute a risk to the National Electricity
Transmission System or, in NGETs view, the System of any User, Bilateral
Agreements may include provision for NGET to reasonably limit the number of
voltage changes in category 2 or 3 to a lower number than specified in Table
CC.6.1.7 to ensure that the total number of voltage changes at the Point of
Common Coupling across multiple Users remains within the limits of Table
CC.6.1.7.

Maximum number of
Category %Vmax & %Vsteadystate
Occurrences

%Vmax 1% &
1 No Limit
%Vsteadystate 1%

3600
0.304
2.5 %Vmax 1% < %Vmax 3% &
2
%Vsteadystate 3%
occurrences per hour with
events evenly distributed
For decreases in voltage:
1
%Vmax 12% &
%Vsteadystate 3%
No more than 4 per day for
3 Commissioning, Maintenance For increases in voltage:
and Fault Restoration
2
%Vmax 5% &
%Vsteadystate 3%

(see Figure CC6.1.7)

Table CC.6.1.7 - Limits for Rapid Voltage Changes

Issue 5 Revision 17 CC 29 June 2016


9 of 95
1
A decrease in voltage of up to 12% is permissible for up to 80ms, as highlighted in the
shaded area in Figure CC.6.1.7, reducing to up to 10% after 80ms and to up to 3% after 2
seconds.
2
An increase in voltage of up to 5% is permissible if it is reduced to up to 3% after 0.5
seconds.

Voltage
Non-compliant zone
V0+5%
V0+3%
V0
V03%
Compliant zone Vsteadystate is reached when
V010% dv/dt 0.5% over 1s

V012%

Non-compliant zone

80ms 0.5 s 2s Time

Figure CC.6.1.7 -
Time and magnitude limits for a category 3 Rapid Voltage Change

(b) For voltages above 132kV, Flicker Severity (Short Term) of 0.8 Unit and a Flicker
Severity (Long Term) of 0.6 Unit, for voltages 132kV and below, Flicker Severity
(Short Term) of 1.0 Unit and a Flicker Severity (Long Term) of 0.8 Unit, as set out in
Engineering Recommendation P28 as current at the Transfer Date.
CC.6.1.8 Voltage fluctuations at a Point of Common Coupling with a fluctuating Load directly
connected to an Offshore Transmission System (or in the case of OTSDUW, OTSDUW
Plant and Apparatus) shall not exceed the limits set out in the Bilateral Agreement.

Issue 5 Revision 17 CC 29 June 2016


10 of 95
CC.6.2 Plant and Apparatus relating to Connection Site and Interface Point
The following requirements apply to Plant and Apparatus relating to the Connection Point,
and OTSDUW Plant and Apparatus relating to the Interface Point (until the OTSUA
Transfer Time) and Connection Point which (except as otherwise provided in the relevant
paragraph) each User must ensure are complied with in relation to its Plant and Apparatus
and which in the case of CC.6.2.2.2.2, CC.6.2.3.1.1 and CC.6.2.1.1(b) only, NGET must
ensure are complied with in relation to Transmission Plant and Apparatus, as provided in
those paragraphs.
CC.6.2.1 General Requirements
CC.6.2.1.1 (a) The design of connections between the National Electricity Transmission System
and:
(i) any Generating Unit (other than a CCGT Unit or Power Park Unit) DC
Converter, Power Park Module or CCGT Module, or
(ii) any Network Operators User System, or
(iii) Non-Embedded Customers equipment;
will be consistent with the Licence Standards.
In the case of OTSDUW, the design of the OTSUAs connections at the Interface Point
and Connection Point will be consistent with Licence Standards.
(b) The National Electricity Transmission System (and any OTSDUW Plant and
Apparatus) at nominal System voltages of 132kV and above is/shall be designed to be
earthed with an Earth Fault Factor of, in England and Wales or Offshore, below 1.4
and in Scotland, below 1.5. Under fault conditions the rated Frequency component of
voltage could fall transiently to zero on one or more phases or, in England and Wales,
rise to 140% phase-to-earth voltage, or in Scotland, rise to 150% phase-to-earth
voltage. The voltage rise would last only for the time that the fault conditions exist. The
fault conditions referred to here are those existing when the type of fault is single or two
phase-to-earth.
(c) For connections to the National Electricity Transmission System at nominal System
voltages of below 132kV the earthing requirements and voltage rise conditions will be
advised by NGET as soon as practicable prior to connection and in the case of
OTSDUW Plant and Apparatus shall be advised to NGET by the User.

CC.6.2.1.2 Substation Plant and Apparatus


(a) The following provisions shall apply to all Plant and Apparatus which is connected at
the voltage of the Connection Point (and OTSDUW Plant and Apparatus at the
Interface Point) and which is contained in equipment bays that are within the
Transmission busbar Protection zone at the Connection Point. This includes circuit
breakers, switch disconnectors, disconnectors, Earthing Devices, power transformers,
voltage transformers, reactors, current transformers, surge arresters, bushings, neutral
equipment, capacitors, line traps, coupling devices, external insulation and insulation
co-ordination devices. Where necessary, this is as more precisely defined in the
Bilateral Agreement.
(i) Plant and/or Apparatus prior to 1st January 1999
Each item of such Plant and/or Apparatus which at 1st January 1999 is either :
installed; or
owned (but is either in storage, maintenance or awaiting installation); or
ordered;
and is the subject of a Bilateral Agreement with regard to the purpose for which it
is in use or intended to be in use, shall comply with the relevant

Issue 5 Revision 17 CC 29 June 2016


11 of 95
standards/specifications applicable at the time that the Plant and/or Apparatus
was designed (rather than commissioned) and any further requirements as
specified in the Bilateral Agreement.
(ii) Plant and/or Apparatus post 1st January 1999 for a new Connection Point
(including OTSDUW Plant and Apparatus at the Interface Point)
Each item of such Plant and/or Apparatus installed in relation to a new
Connection Point (or OTSDUW Plant and Apparatus at the Interface Point)
after 1st January 1999 shall comply with the relevant Technical Specifications
and any further requirements identified by NGET, acting reasonably, to reflect the
options to be followed within the Technical Specifications and/or to complement
if necessary the Technical Specifications so as to enable NGET to comply with
its obligations in relation to the National Electricity Transmission System or, in
Scotland or Offshore, the Relevant Transmission Licensee to comply with its
obligations in relation to its Transmission System. This information, including the
application dates of the relevant Technical Specifications, will be as specified in
the Bilateral Agreement.
(iii) New Plant and/or Apparatus post 1st January 1999 for an existing Connection
Point (including OTSDUW Plant and Apparatus at the Interface Point)
Each new additional and/or replacement item of such Plant and/or Apparatus
installed in relation to a change to an existing Connection Point (or OTSDUW
Plant and Apparatus at the Interface Point and Connection Point) after 1st
January 1999 shall comply with the standards/specifications applicable when the
change was designed, or such other standards/specifications as necessary to
ensure that the item of Plant and/or Apparatus is reasonably fit for its intended
purpose having due regard to the obligations of NGET, the relevant User and, in
Scotland, or Offshore, also the Relevant Transmission Licensee under their
respective Licences. Where appropriate this information, including the application
dates of the relevant standards/specifications, will be as specified in the varied
Bilateral Agreement.
(iv) Used Plant and/or Apparatus being moved, re-used or modified
If, after its installation, any such item of Plant and/or Apparatus is subsequently:
moved to a new location; or
used for a different purpose; or
otherwise modified;
then the standards/specifications as described in (i), (ii), or (iii) above as applicable
will apply as appropriate to such Plant and/or Apparatus, which must be
reasonably fit for its intended purpose having due regard to the obligations of
NGET, the relevant User and, in Scotland or Offshore, also the Relevant
Transmission Licensee under their respective Licences.
(b) NGET shall at all times maintain a list of those Technical Specifications and additional
requirements which might be applicable under this CC.6.2.1.2 and which may be
referenced by NGET in the Bilateral Agreement. NGET shall provide a copy of the list
upon request to any User. NGET shall also provide a copy of the list to any new User
upon receipt of an application form for a Bilateral Agreement for a new Connection
Point.
(c) Where the User provides NGET with information and/or test reports in respect of Plant
and/or Apparatus which the User reasonably believes demonstrate the compliance of
such items with the provisions of a Technical Specification then NGET shall promptly
and without unreasonable delay give due and proper consideration to such information.

Issue 5 Revision 17 CC 29 June 2016


12 of 95
(d) Plant and Apparatus shall be designed, manufactured and tested in premises with an
accredited certificate in accordance with the quality assurance requirements of the
relevant standard in the BS EN ISO 9000 series (or equivalent as reasonably approved
by NGET) or in respect of test premises which do not include a manufacturing facility
premises with an accredited certificate in accordance with BS EN 45001.
(e) Each connection between a User and the National Electricity Transmission System
must be controlled by a circuit-breaker (or circuit breakers) capable of interrupting the
maximum short circuit current at the point of connection. The Seven Year Statement
gives values of short circuit current and the rating of Transmission circuit breakers at
existing and committed Connection Points for future years.
(f) Each connection between a Generator undertaking OTSDUW or an Onshore
Transmission Licensee, must be controlled by a circuit breaker (or circuit breakers)
capable of interrupting the maximum short circuit current at the Transmission Interface
Point. The Seven Year Statement gives values of short circuit current and the rating
of Transmission circuit breakers at existing and committed Transmission Interface
Points for future years.
CC.6.2.2 Requirements at Connection Points or, in the case of OTSDUW at Interface Points that
relate to Generators or OTSDUW Plant and Apparatus or DC Converter Station owners
CC.6.2.2.1 Not Used.
CC.6.2.2.2 Generating Unit, OTSDUW Plant and Apparatus and Power Station Protection
Arrangements
CC.6.2.2.2.1 Minimum Requirements
Protection of Generating Units (other than Power Park Units), DC Converters, OTSDUW
Plant and Apparatus or Power Park Modules and their connections to the National
Electricity Transmission System shall meet the requirements given below. These are
necessary to reduce the impact on the National Electricity Transmission System of faults
on OTSDUW Plant and Apparatus circuits or circuits owned by Generators or DC
Converter Station owners.
CC.6.2.2.2.2 Fault Clearance Times
(a) The required fault clearance time for faults on the Generator's or DC Converter Station
owners equipment directly connected to the National Electricity Transmission
System or OTSDUW Plant and Apparatus and for faults on the National Electricity
Transmission System directly connected to the Generator or DC Converter Station
owner's equipment or OTSDUW Plant and Apparatus, from fault inception to the circuit
breaker arc extinction, shall be set out in the Bilateral Agreement. The fault clearance
time specified in the Bilateral Agreement shall not be shorter than the durations
specified below:
(i) 80ms at 400kV
(ii) 100ms at 275kV
(iii) 120ms at 132kV and below
but this shall not prevent the User or NGET or the Generator (including in respect of
OTSDUW Plant and Apparatus) from selecting a shorter fault clearance time on their
own Plant and Apparatus provided Discrimination is achieved..
A longer fault clearance time may be specified in the Bilateral Agreement for faults on
the National Electricity Transmission System. A longer fault clearance time for faults
on the Generator or DC Converter Station owner's equipment or OTSDUW Plant and
Apparatus may be agreed with NGET in accordance with the terms of the Bilateral
Agreement but only if System requirements, in NGET's view, permit. The probability
that the fault clearance time stated in the Bilateral Agreement will be exceeded by any
given fault, must be less than 2%.

Issue 5 Revision 17 CC 29 June 2016


13 of 95
(b) In the event that the required fault clearance time is not met as a result of failure to
operate on the Main Protection System(s) provided, the Generators or DC Converter
Station owners or Generators in the case of OTSDUW Plant and Apparatus shall,
except as specified below provide Independent Back-Up Protection. NGET will also
provide Back-Up Protection and NGET and the Users Back-Up Protections will be
co-ordinated so as to provide Discrimination.
On a Generating Unit (other than a Power Park Unit), DC Converter or Power Park
Module or OTSDUW Plant and Apparatus in respect of which the Completion Date is
after 20 January 2016 and connected to the National Electricity Transmission
System at 400kV or 275kV and where two Independent Main Protections are
provided to clear faults on the HV Connections within the required fault clearance time,
the Back-Up Protection provided by the Generators (including in respect of OTSDUW
Plant and Apparatus) and DC Converter Station owner shall operate to give a fault
clearance time of no longer than 300ms at the minimum infeed for normal operation for
faults on the HV Connections. Where two Independent Main Protections are
installed the Back-Up Protection may be integrated into one (or both) of the
Independent Main Protection relays.
On a Generating Unit (other than a Power Park Unit), DC Converter or Power Park
Module or OTSDUW Plant and Apparatus in respect of which the Completion Date is
after 20 January 2016 and connected to the National Electricity Transmission
System at 132 kV and where only one Main Protection is provided to clear faults on
the HV Connections within the required fault clearance time, the Independent Back-
Up Protection provided by the Generator (including in respect of OTSDUW Plant and
Apparatus) and the DC Converter Station owner shall operate to give a fault
clearance time of no longer than 300ms at the minimum infeed for normal operation for
faults on the HV Connections.
On a Generating Unit (other than a Power Park Unit), DC Converter or Power Park
Module or OTSDUW Plant and Apparatus connected to the National Electricity
Transmission System and on Generating Units (other than a Power Park Unit), DC
Converters or Power Park Modules or OTSDUW Plant and Apparatus connected to
the National Electricity Transmission System at 400 kV or 275 kV or 132 kV, in
respect of which the Completion Date is before the 20 January 2016, the Back-Up
Protection or Independent Back-Up Protection shall operate to give a fault clearance
time of no longer than 800ms in England and Wales or 300ms in Scotland at the
minimum infeed for normal operation for faults on the HV Connections.
A Generating Unit (other than a Power Park Unit), DC Converter or Power Park
Module or OTSDUW Plant and Apparatus) with Back-Up Protection or Independent
Back-Up Protection will also be required to withstand, without tripping, the loading
incurred during the clearance of a fault on the National Electricity Transmission
System by breaker fail Protection at 400kV or 275kV or of a fault cleared by Back-Up
Protection where the Generator (including in the case of OTSDUW Plant and
Apparatus) or DC Converter is connected at 132kV and below. This will permit
Discrimination between Generator in respect of OTSDUW Plant and Apparatus or
DC Converter Station owners Back-Up Protection or Independent Back-Up
Protection and the Back-Up Protection provided on the National Electricity
Transmission System and other Users' Systems.

Issue 5 Revision 17 CC 29 June 2016


14 of 95
(c) When the Generating Unit (other than Power Park Units), or the DC Converter or
Power Park Module or OTSDUW Plant and Apparatus is connected to the National
Electricity Transmission System at 400kV or 275kV, and in Scotland and Offshore
also at 132kV, and a circuit breaker is provided by the Generator (including in respect
of OTSDUW Plant and Apparatus) or the DC Converter Station owner, or NGET, as
the case may be, to interrupt fault current interchange with the National Electricity
Transmission System, or Generator's System, or DC Converter Station owners
System, as the case may be, circuit breaker fail Protection shall be provided by the
Generator (including in respect of OTSDUW Plant and Apparatus) or DC Converter
Station owner, or NGET, as the case may be, on this circuit breaker. In the event,
following operation of a Protection system, of a failure to interrupt fault current by these
circuit-breakers within the Fault Current Interruption Time, the circuit breaker fail
Protection is required to initiate tripping of all the necessary electrically adjacent circuit-
breakers so as to interrupt the fault current within the next 200ms.
(d) The target performance for the System Fault Dependability Index shall be not less
than 99%. This is a measure of the ability of Protection to initiate successful tripping of
circuit breakers which are associated with the faulty item of Apparatus.
CC.6.2.2.3 Equipment to be provided
CC.6.2.2.3.1 Protection of Interconnecting Connections
The requirements for the provision of Protection equipment for interconnecting connections
will be specified in the Bilateral Agreement. In this CC the term "interconnecting
connections" means the primary conductors from the current transformer accommodation on
the circuit side of the circuit breaker to the Connection Point or the primary conductors from
the current transformer accommodation on the circuit side of the OTSDUW Plant and
Apparatus of the circuit breaker to the Transmission Interface Point.
CC.6.2.2.3.2 Circuit-breaker fail Protection
The Generator or DC Converter Station owner will install circuit breaker fail Protection
equipment in accordance with the requirements of the Bilateral Agreement. The
Generator or DC Converter Station owner will also provide a back-trip signal in the event of
loss of air from its pressurised head circuit breakers, during the Generating Unit (other than
a CCGT Unit or Power Park Unit) or CCGT Module or DC Converter or Power Park
Module run-up sequence, where these circuit breakers are installed.
CC.6.2.2.3.3 Loss of Excitation
The Generator must provide Protection to detect loss of excitation on a Generating Unit
and initiate a Generating Unit trip.
CC.6.2.2.3.4 Pole-Slipping Protection
Where, in NGET's reasonable opinion, System requirements dictate, NGET will specify in
the Bilateral Agreement a requirement for Generators to fit pole-slipping Protection on
their Generating Units.
CC.6.2.2.3.5 Signals for Tariff Metering
Generators and DC Converter Station owners will install current and voltage transformers
supplying all tariff meters at a voltage to be specified in, and in accordance with, the
Bilateral Agreement.
CC.6.2.2.4 Work on Protection Equipment
No busbar Protection, mesh corner Protection, circuit-breaker fail Protection relays, AC or
DC wiring (other than power supplies or DC tripping associated with the Generating Unit,
DC Converter or Power Park Module itself) may be worked upon or altered by the
Generator or DC Converter Station owner personnel in the absence of a representative of
NGET or in Scotland or Offshore, a representative of NGET, or written authority from NGET
to perform such work or alterations in the absence of a representative of NGET.

Issue 5 Revision 17 CC 29 June 2016


15 of 95
CC.6.2.2.5 Relay Settings
Protection and relay settings will be co-ordinated (both on connection and subsequently)
across the Connection Point in accordance with the Bilateral Agreement and in relation to
OTSDUW Plant and Apparatus, across the Interface Point in accordance with the
Bilateral Agreement to ensure effective disconnection of faulty Apparatus.
CC.6.2.3 Requirements at Connection Points relating to Network Operators and Non-Embedded
Customers
CC.6.2.3.1 Protection Arrangements for Network Operators and Non-Embedded Customers
CC.6.2.3.1.1 Protection of Network Operator and Non-Embedded Customers User Systems directly
connected to the National Electricity Transmission System, shall meet the requirements
given below:
Fault Clearance Times
(a) The required fault clearance time for faults on Network Operator and Non-Embedded
Customer equipment directly connected to the National Electricity Transmission
System, and for faults on the National Electricity Transmission System directly
connected to the Network Operators or Non-Embedded Customer's equipment,
from fault inception to the circuit breaker arc extinction, shall be set out in each Bilateral
Agreement. The fault clearance time specified in the Bilateral Agreement shall not be
shorter than the durations specified below:
(i) 80ms at 400kV
(ii) 100ms at 275kV
(iii) 120ms at 132kV and below
but this shall not prevent the User or NGET from selecting a shorter fault clearance time
on its own Plant and Apparatus provided Discrimination is achieved.
For the purpose of establishing the Protection requirements in accordance with
CC.6.2.3.1.1 only, the point of connection of the Network Operator or Non-
Embedded Customer equipment to the National Electricity Transmission System
shall be deemed to be the low voltage busbars at a Grid Supply Point, irrespective of
the ownership of the equipment at the Grid Supply Point.
A longer fault clearance time may be specified in the Bilateral Agreement for faults on
the National Electricity Transmission System. A longer fault clearance time for faults
on the Network Operator and Non-Embedded Customers equipment may be agreed
with NGET in accordance with the terms of the Bilateral Agreement but only if System
requirements in NGET's view permit. The probability that the fault clearance time stated
in the Bilateral Agreement will be exceeded by any given fault must be less than 2%.
(b) (i) For the event of failure of the Protection systems provided to meet the above fault
clearance time requirements, Back-Up Protection shall be provided by the
Network Operator or Non-Embedded Customer as the case may be.
(ii) NGET will also provide Back-Up Protection, which will result in a fault clearance
time longer than that specified for the Network Operator or Non-Embedded
Customer Back-Up Protection so as to provide Discrimination.
(iii) For connections with the National Electricity Transmission System at 132kV
and below, it is normally required that the Back-Up Protection on the National
Electricity Transmission System shall discriminate with the Network Operator
or Non-Embedded Customer's Back-Up Protection.
(iv) For connections with the National Electricity Transmission System at 400kV or
275kV, the Back-Up Protection will be provided by the Network Operator or
Non-Embedded Customer, as the case may be, with a fault clearance time not
longer than 300ms for faults on the Network Operators or Non-Embedded
Customer's Apparatus.

Issue 5 Revision 17 CC 29 June 2016


16 of 95
(v) Such Protection will also be required to withstand, without tripping, the loading
incurred during the clearance of a fault on the National Electricity Transmission
System by breaker fail Protection at 400kV or 275kV. This will permit
Discrimination between Network Operators Back-Up Protection or Non-
Embedded Customers Back-Up Protection, as the case may be, and Back-Up
Protection provided on the National Electricity Transmission System and other
User Systems. The requirement for and level of Discrimination required will be
specified in the Bilateral Agreement.
(c) (i) Where the Network Operator or Non-Embedded Customer is connected to the
National Electricity Transmission System at 400kV or 275kV, and in Scotland
also at 132kV, and a circuit breaker is provided by the Network Operator or Non-
Embedded Customer, or NGET, as the case may be, to interrupt the interchange
of fault current with the National Electricity Transmission System or the System
of the Network Operator or Non-Embedded Customer, as the case may be,
circuit breaker fail Protection will be provided by the Network Operator or Non-
Embedded Customer, or NGET, as the case may be, on this circuit breaker.
(ii) In the event, following operation of a Protection system, of a failure to interrupt
fault current by these circuit-breakers within the Fault Current Interruption Time,
the circuit breaker fail Protection is required to initiate tripping of all the necessary
electrically adjacent circuit-breakers so as to interrupt the fault current within the
next 200ms.
(d) The target performance for the System Fault Dependability Index shall be not less
than 99%. This is a measure of the ability of Protection to initiate successful tripping of
circuit breakers which are associated with the faulty items of Apparatus.

Issue 5 Revision 17 CC 29 June 2016


17 of 95
CC.6.2.3.2 Fault Disconnection Facilities
(a) Where no Transmission circuit breaker is provided at the User's connection voltage,
the User must provide NGET with the means of tripping all the User's circuit breakers
necessary to isolate faults or System abnormalities on the National Electricity
Transmission System. In these circumstances, for faults on the User's System, the
User's Protection should also trip higher voltage Transmission circuit breakers.
These tripping facilities shall be in accordance with the requirements specified in the
Bilateral Agreement.
(b) NGET may require the installation of a System to Generator Operational
Intertripping Scheme in order to enable the timely restoration of circuits following
power System fault(s). These requirements shall be set out in the relevant Bilateral
Agreement.
CC.6.2.3.3 Automatic Switching Equipment
Where automatic reclosure of Transmission circuit breakers is required following faults on
the User's System, automatic switching equipment shall be provided in accordance with the
requirements specified in the Bilateral Agreement.
CC.6.2.3.4 Relay Settings
Protection and relay settings will be co-ordinated (both on connection and subsequently)
across the Connection Point in accordance with the Bilateral Agreement to ensure
effective disconnection of faulty Apparatus.
CC.6.2.3.5 Work on Protection equipment
Where a Transmission Licensee owns the busbar at the Connection Point, no busbar
Protection, mesh corner Protection relays, AC or DC wiring (other than power supplies or
DC tripping associated with the Network Operator or Non-Embedded Customers
Apparatus itself) may be worked upon or altered by the Network Operator or Non-
Embedded Customer personnel in the absence of a representative of NGET or in Scotland,
a representative of NGET, or written authority from NGET to perform such work or
alterations in the absence of a representative of NGET.
CC.6.2.3.6 Equipment to be provided
CC.6.2.3.6.1 Protection of Interconnecting Connections
The requirements for the provision of Protection equipment for interconnecting connections
will be specified in the Bilateral Agreement.

CC.6.3 GENERAL GENERATING UNIT (AND OTSDUW) REQUIREMENTS


CC.6.3.1 This section sets out the technical and design criteria and performance requirements for
Generating Units, DC Converters and Power Park Modules (whether directly connected
to the National Electricity Transmission System or Embedded) and (where provided in
this section) OTSDUW Plant and Apparatus which each Generator or DC Converter
Station owner must ensure are complied with in relation to its Generating Units, DC
Converters and Power Park Modules and OTSDUW Plant and Apparatus but does not
apply to Small Power Stations or individually to Power Park Units. References to
Generating Units, DC Converters and Power Park Modules in this CC.6.3 should be read
accordingly. The performance requirements that OTSDUW Plant and Apparatus must be
capable of providing at the Interface Point under this section may be provided using a
combination of Generator Plant and Apparatus and/or OTSDUW Plant and Apparatus.
Plant Performance Requirements

Issue 5 Revision 17 CC 29 June 2016


18 of 95
CC.6.3.2 (a) When supplying Rated MW all Onshore Synchronous Generating Units must be
capable of continuous operation at any point between the limits 0.85 Power Factor
lagging and 0.95 Power Factor leading at the Onshore Synchronous Generating
Unit terminals. At Active Power output levels other than Rated MW, all Onshore
Synchronous Generating Units must be capable of continuous operation at any point
between the Reactive Power capability limits identified on the Generator
Performance Chart.
In addition to the above paragraph, where Onshore Synchronous Generating Unit(s):
(i) have a Connection Entry Capacity which has been increased above Rated MW
(or the Connection Entry Capacity of the CCGT module has increased above
the sum of the Rated MW of the Generating Units compromising the CCGT
st
module), and such increase takes effect after 1 May 2009, the minimum lagging
Reactive Power capability at the terminals of the Onshore Synchronous
Generating Unit(s) must be 0.9 Power Factor at all Active Power output levels in
excess of Rated MW. Further, the User shall comply with the provisions of and
any instructions given pursuant to BC1.8 and the relevant Bilateral Agreement; or
(ii) have a Connection Entry Capacity in excess of Rated MW (or the Connection
Entry Capacity of the CCGT module exceeds the sum of Rated MW of the
Generating Units comprising the CCGT module) and a Completion Date before
st
1 May 2009, alternative provisions relating to Reactive Power capability may be
specified in the Bilateral Agreement and where this is the case such provisions
must be complied with.
The short circuit ratio of Onshore Synchronous Generating Units with an Apparent
Power rating of less than 1600MVA shall be not less than 0.5. The short circuit ratio of
Onshore Synchronous Generating Units with a rated Apparent Power of 1600MVA
or above shall be not less than 0.4.
(b) Subject to paragraph (c) below, all Onshore Non-Synchronous Generating Units,
Onshore DC Converters and Onshore Power Park Modules must be capable of
maintaining zero transfer of Reactive Power at the Onshore Grid Entry Point (or User
System Entry Point if Embedded) at all Active Power output levels under steady
state voltage conditions. For Onshore Non-Synchronous Generating Units and
Onshore Power Park Modules the steady state tolerance on Reactive Power transfer
to and from the National Electricity Transmission System expressed in MVAr shall
be no greater than 5% of the Rated MW. For Onshore DC Converters the steady
state tolerance on Reactive Power transfer to and from the National Electricity
Transmission System shall be specified in the Bilateral Agreement.

Issue 5 Revision 17 CC 29 June 2016


19 of 95
(c) Subject to the provisions of CC.6.3.2(d) below, all Onshore Non-Synchronous
Generating Units, Onshore DC Converters (excluding current source technology) and
Onshore Power Park Modules (excluding those connected to the Total System by a
current source Onshore DC Converter) and OTSDUW Plant and Apparatus at the
Interface Point with a Completion Date on or after 1 January 2006 must be capable of
supplying Rated MW output or Interface Point Capacity in the case of OTSDUW Plant
and Apparatus at any point between the limits 0.95 Power Factor lagging and 0.95
Power Factor leading at the Onshore Grid Entry Point in England and Wales or
Interface Point in the case of OTSDUW Plant and Apparatus or at the HV side of the
33/132kV or 33/275kV or 33/400kV transformer for Generators directly connected to
the Onshore Transmission System in Scotland (or User System Entry Point if
Embedded). With all Plant in service, the Reactive Power limits defined at Rated MW
or Interface Point Capacity in the case of OTSDUW Plant and Apparatus at Lagging
Power Factor will apply at all Active Power output levels above 20% of the Rated MW
or Interface Point Capacity in the case of OTSDUW Plant and Apparatus output as
defined in Figure 1. With all Plant in service, the Reactive Power limits defined at
Rated MW at Leading Power Factor will apply at all Active Power output levels above
50% of the Rated MW output or Interface Point Capacity in the case of OTSDUW
Plant and Apparatus as defined in Figure 1. With all Plant in service, the Reactive
Power limits will reduce linearly below 50% Active Power output as shown in Figure 1
unless the requirement to maintain the Reactive Power limits defined at Rated MW or
Interface Point Capacity in the case of OTSDUW Plant and Apparatus at Leading
Power Factor down to 20% Active Power output is specified in the Bilateral
Agreement. These Reactive Power limits will be reduced pro rata to the amount of
Plant in service.

Figure 1

Point A is equivalent 0.95 leading Power Factor at Rated MW output or Interface Point
(in MVAr) to Capacity in the case of OTSDUW Plant and Apparatus

Point B is equivalent 0.95 lagging Power Factor at Rated MW output or Interface Point
(in MVAr) to: Capacity in the case of OTSDUW Plant and Apparatus

Point C is equivalent -5% of Rated MW output or Interface Point Capacity in the case
(in MVAr) to: of OTSDUW Plant and Apparatus

Issue 5 Revision 17 CC 29 June 2016


20 of 95
Point D is equivalent +5% of Rated MW output or Interface Point Capacity in the case
(in MVAr) to: of OTSDUW Plant and Apparatus

Point E is equivalent -12% of Rated MW output or Interface Point Capacity in the case
(in MVAr) to: of OTSDUW Plant and Apparatus

(d) All Onshore Non-Synchronous Generating Units and Onshore Power Park
Modules in Scotland with a Completion Date after 1 April 2005 and before 1 January
2006 must be capable of supplying Rated MW at the range of power factors either:
(i) from 0.95 lead to 0.95 lag as illustrated in Figure 1 at the User System Entry
Point for Embedded Generators or at the HV side of the 33/132kV or 33/275kV or
33/400kV transformer for Generators directly connected to the Onshore
Transmission System. With all Plant in service, the Reactive Power limits
defined at Rated MW will apply at all Active Power output levels above 20% of the
Rated MW output as defined in Figure 1. These Reactive Power limits will be
reduced pro rata to the amount of Plant in service, or
(ii) from 0.95 lead to 0.90 lag at the Onshore Non-Synchronous Generating Unit
(including Power Park Unit) terminals. For the avoidance of doubt Generators
complying with this option (ii) are not required to comply with CC.6.3.2(b).
(e) The short circuit ratio of Offshore Synchronous Generating Units at a Large Power
Station shall be not less than 0.5. At a Large Power Station all Offshore Synchronous
Generating Units, Offshore Non-Synchronous Generating Units, Offshore DC
Converters and Offshore Power Park Modules must be capable of maintaining:
(i) zero transfer of Reactive Power at the Offshore Grid Entry Point for all
Generators with an Offshore Grid Entry Point at the LV Side of the Offshore
Platform at all Active Power output levels under steady state voltage conditions.
The steady state tolerance on Reactive Power transfer to and from an Offshore
Transmission System expressed in MVAr shall be no greater than 5% of the
Rated MW, or
(ii) a transfer of Reactive Power at the Offshore Grid Entry Point at a value
specified in the Bilateral Agreement that will be equivalent to zero at the LV Side
of the Offshore Platform. In addition, the steady state tolerance on Reactive
Power transfer to and from an Offshore Transmission System expressed in
MVAr at the LV Side of the Offshore Platform shall be no greater than 5% of the
Rated MW, or
(iii) the Reactive Power capability (within associated steady state tolerance) specified
in the Bilateral Agreement if any alternative has been agreed with the Generator,
Offshore Transmission Licensee and NGET.
(f) In addition, a Genset shall meet the operational requirements as specified in BC2.A.2.6.
CC.6.3.3 Each Generating Unit, DC Converter (including an OTSDUW DC Converter), Power Park
Module and/or CCGT Module must be capable of:
(a) continuously maintaining constant Active Power output for System Frequency
changes within the range 50.5 to 49.5 Hz; and

Issue 5 Revision 17 CC 29 June 2016


21 of 95
(b) (subject to the provisions of CC.6.1.3) maintaining its Active Power output at a level not
lower than the figure determined by the linear relationship shown in Figure 2 for System
Frequency changes within the range 49.5 to 47 Hz, such that if the System Frequency
drops to 47 Hz the Active Power output does not decrease by more than 5%. In the
case of a CCGT Module, the above requirement shall be retained down to the Low
Frequency Relay trip setting of 48.8 Hz, which reflects the first stage of the Automatic
Low Frequency Demand Disconnection scheme notified to Network Operators
under OC6.6.2. For System Frequency below that setting, the existing requirement
shall be retained for a minimum period of 5 minutes while System Frequency remains
below that setting, and special measure(s) that may be required to meet this
requirement shall be kept in service during this period. After that 5 minutes period, if
System Frequency remains below that setting, the special measure(s) must be
discontinued if there is a materially increased risk of the Gas Turbine tripping. The
need for special measure(s) is linked to the inherent Gas Turbine Active Power output
reduction caused by reduced shaft speed due to falling System Frequency.

Figure 2

(c) For the avoidance of doubt in the case of a Generating Unit or Power Park Module (or
OTSDUW DC Converters at the Interface Point) using an Intermittent Power Source
where the mechanical power input will not be constant over time, the requirement is that
the Active Power output shall be independent of System Frequency under (a) above
and should not drop with System Frequency by greater than the amount specified in
(b) above.
(d) A DC Converter Station must be capable of maintaining its Active Power input (i.e.
when operating in a mode analogous to Demand) from the National Electricity
Transmission System (or User System in the case of an Embedded DC Converter
Station) at a level not greater than the figure determined by the linear relationship
shown in Figure 3 for System Frequency changes within the range 49.5 to 47 Hz, such
that if the System Frequency drops to 47.8 Hz the Active Power input decreases by
more than 60%.

Issue 5 Revision 17 CC 29 June 2016


22 of 95
47 47.8 Frequency (Hz) 49.5 52.0

100% of Active
Power Input

40% of Active
Power Input
Figure 3

(e) At a Large Power Station, in the case of an Offshore Generating Unit, Offshore
Power Park Module, Offshore DC Converter and OTSDUW DC Converter, the
Generator shall comply with the requirements of CC.6.3.3. Generators should be
aware that Section K of the STC places requirements on Offshore Transmission
Licensees which utilise a Transmission DC Converter as part of their Offshore
Transmission System to make appropriate provisions to enable Generators to fulfil
their obligations.
(f) In the case of an OTSDUW DC Converter the OTSDUW Plant and Apparatus shall
provide a continuous signal indicating the real time frequency measured at the
Interface Point to the Offshore Grid Entry Point.
CC.6.3.4 At the Grid Entry Point, the Active Power output under steady state conditions of any
Generating Unit, DC Converter or Power Park Module directly connected to the National
Electricity Transmission System or in the case of OTSDUW, the Active Power transfer at
the Interface Point, under steady state conditions of any OTSDUW Plant and Apparatus
should not be affected by voltage changes in the normal operating range specified in
paragraph CC.6.1.4 by more than the change in Active Power losses at reduced or
increased voltage. In addition:
(a) For any Onshore Generating Unit, Onshore DC Converter and Onshore Power
Park Module or OTSDUW the Reactive Power output under steady state conditions
should be fully available within the voltage range 5% at 400kV, 275kV and 132kV and
lower voltages, except for an Onshore Power Park Module or Onshore Non-
Synchronous Generating Unit if Embedded at 33kV and below (or directly connected
to the Onshore Transmission System at 33kV and below) where the requirement
shown in Figure 4 applies.
(b) At a Large Power Station, in the case of an Offshore Generating Unit, Offshore DC
Converter and Offshore Power Park Module where an alternative reactive capability
has been agreed with the Generator, as specified in CC.6.3.2(e) (iii), the voltage /
Reactive Power requirement shall be specified in the Bilateral Agreement. The
Reactive Power output under steady state conditions shall be fully available within the
voltage range 5% at 400kV, 275kV and 132kV and lower voltages.

Issue 5 Revision 17 CC 29 June 2016


23 of 95
Voltage at an Onshore Grid Entry Point or User System Entry Point if Embedded
(% of Nominal) at 33 kV and below

105%

100%

95%

Power Factor 0.95 Lead at Rated 1.0 Power Factor 0.95 lag at Rated MW
MW output or Onshore Grid output or Onshore Grid Entry Point
Entry Point equivalent Power equivalent Power Factor if connected
Factor if connected to the to the Onshore Transmission
Onshore Transmission System System in Scotland or optionally in
in Scotland Scotland for Plant with a Completion
Date before 1 January 2006 Power
Factor 0.9 lag at an Onshore Non-
synchronous Generating Unit or
Onshore Power Park Unit Terminals

Figure 4

CC.6.3.5 It is an essential requirement that the National Electricity Transmission System must
incorporate a Black Start Capability. This will be achieved by agreeing a Black Start
Capability at a number of strategically located Power Stations. For each Power Station
NGET will state in the Bilateral Agreement whether or not a Black Start Capability is
required.
Control Arrangements
CC.6.3.6 (a) Each:
(i) Offshore Generating Unit in a Large Power Station or Onshore Generating
Unit; or,
(ii) Onshore DC Converter with a Completion Date on or after 1 April 2005 or
Offshore DC Converter at a Large Power Station; or,
(iii) Onshore Power Park Module in England and Wales with a Completion Date on
or after 1 January 2006; or,
(iv) Onshore Power Park Module in operation in Scotland on or after 1 January 2006
(with a Completion Date after 1 July 2004 and in a Power Station with a
Registered Capacity of 50MW or more); or,
(v) Offshore Power Park Module in a Large Power Station with a Registered
Capacity of 50MW or more;
must be capable of contributing to Frequency control by continuous modulation of
Active Power supplied to the National Electricity Transmission System or the User
System in which it is Embedded. For the avoidance of doubt each OTSDUW DC
Converter shall provide each User in respect of its Offshore Power Stations
connected to and/or using an Offshore Transmission System a continuous signal
indicating the real time Frequency measured at the Transmission Interface Point.
(b) Each:
(i) Onshore Generating Unit; or,
(ii) Onshore DC Converter (with a Completion Date on or after 1 April 2005
excluding current source technologies); or
(iii) Onshore Power Park Module in England and Wales with a Completion Date on
Issue 5 Revision 17 CC 29 June 2016
24 of 95
or after 1 January 2006; or,
(iv) Onshore Power Park Module in Scotland irrespective of Completion Date; or,
(v) Offshore Generating Unit at a Large Power Station, Offshore DC Converter at
a Large Power Station or Offshore Power Park Module at a Large Power
Station which provides a reactive range beyond the minimum requirements
specified in CC.6.3.2(e) (iii); or,
(vi) OTSDUW Plant and Apparatus at a Transmission Interface Point
must be capable of contributing to voltage control by continuous changes to the
Reactive Power supplied to the National Electricity Transmission System or the
User System in which it is Embedded.

CC.6.3.7 (a) Each Generating Unit, DC Converter or Power Park Module (excluding Onshore
Power Park Modules in Scotland with a Completion Date before 1 July 2004 or
Onshore Power Park Modules in a Power Station in Scotland with a Registered
Capacity less than 50MW or Offshore Power Park Modules in a Large Power
Station located Offshore with a Registered Capacity less than 50MW) must be fitted
with a fast acting proportional Frequency control device (or turbine speed governor)
and unit load controller or equivalent control device to provide Frequency response
under normal operational conditions in accordance with Balancing Code 3 (BC3). In
the case of a Power Park Module the Frequency or speed control device(s) may be on
the Power Park Module or on each individual Power Park Unit or be a combination of
both. The Frequency control device(s) (or speed governor(s)) must be designed and
operated to the appropriate:
(i) European Specification; or
(ii) in the absence of a relevant European Specification, such other standard which
is in common use within the European Community (which may include a
manufacturer specification);
as at the time when the installation of which it forms part was designed or (in the case of
modification or alteration to the Frequency control device (or turbine speed governor))
when the modification or alteration was designed.
The European Specification or other standard utilised in accordance with sub-
paragraph CC.6.3.7 (a) (ii) will be notified to NGET by the Generator or DC Converter
Station owner or, in the case of an Embedded Medium Power Station not subject to a
Bilateral Agreement or Embedded DC Converter Station not subject to a Bilateral
Agreement, the relevant Network Operator:
(i) as part of the application for a Bilateral Agreement; or
(ii) as part of the application for a varied Bilateral Agreement; or
(iii) in the case of an Embedded Development, within 28 days of entry into the
Embedded Development Agreement (or such later time as agreed with NGET);
or
(iv) as soon as possible prior to any modification or alteration to the Frequency control
device (or governor); and
(b) The Frequency control device (or speed governor) in co-ordination with other control
devices must control the Generating Unit, DC Converter or Power Park Module
Active Power Output with stability over the entire operating range of the Generating
Unit, DC Converter or Power Park Module; and
(c) The Frequency control device (or speed governor) must meet the following minimum
requirements:
(i) Where a Generating Unit, DC Converter or Power Park Module becomes
isolated from the rest of the Total System but is still supplying Customers, the

Issue 5 Revision 17 CC 29 June 2016


25 of 95
Frequency control device (or speed governor) must also be able to control
System Frequency below 52Hz unless this causes the Generating Unit, DC
Converter or Power Park Module to operate below its Designed Minimum
Operating Level when it is possible that it may, as detailed in BC 3.7.3, trip after a
time. For the avoidance of doubt the Generating Unit, DC Converter or Power
Park Module is only required to operate within the System Frequency range 47 -
52 Hz as defined in CC.6.1.3;
(ii) the Frequency control device (or speed governor) must be capable of being set so
that it operates with an overall speed Droop of between 3% and 5%. For the
avoidance of doubt, in the case of a Power Park Module the speed Droop should
be equivalent of a fixed setting between 3% and 5% applied to each Power Park
Unit in service;
(iii) in the case of all Generating Units, DC Converter or Power Park Module other
than the Steam Unit within a CCGT Module the Frequency control device (or
speed governor) deadband should be no greater than 0.03Hz (for the avoidance of
doubt, 0.015Hz). In the case of the Steam Unit within a CCGT Module, the
speed Governor Deadband should be set to an appropriate value consistent with
the requirements of CC.6.3.7(c)(i) and the requirements of BC3.7.2 for the
provision of Limited High Frequency Response;
For the avoidance of doubt, the minimum requirements in (ii) and (iii) for the provision of
System Ancillary Services do not restrict the negotiation of Commercial Ancillary
Services between NGET and the User using other parameters; and
(d) A facility to modify, so as to fulfil the requirements of the Balancing Codes, the Target
Frequency setting either continuously or in a maximum of 0.05 Hz steps over at least
the range 50 0.1 Hz should be provided in the unit load controller or equivalent device.
(e) (i) Each Onshore Generating Unit and/or CCGT Module which has a Completion
Date after 1 January 2001 in England and Wales, and after 1 April 2005 in
Scotland, must be capable of meeting the minimum Frequency response
requirement profile subject to and in accordance with the provisions of Appendix 3.
(ii) Each DC Converter at a DC Converter Station which has a Completion Date on
or after 1 April 2005 and each Offshore DC Converter at a Large Power Station
must be capable of meeting the minimum Frequency response requirement profile
subject to and in accordance with the provisions of Appendix 3.
(iii) Each Onshore Power Park Module in operation in England and Wales with a
Completion Date on or after 1 January 2006 must be capable of meeting the
minimum Frequency response requirement profile subject to and in accordance
with the provisions of Appendix 3.
(iv) Each Onshore Power Park Module in operation on or after 1 January 2006 in
Scotland (with a Completion Date on or after 1 April 2005 and a Registered
Capacity of 50MW or more) must be capable of meeting the minimum Frequency
response requirement profile subject to and in accordance with the provisions of
Appendix 3.
(v) Each Offshore Generating Unit in a Large Power Station must be capable of
meeting the minimum Frequency response requirement profile subject to and in
accordance with the provisions of Appendix 3.
(vi) Each Offshore Power Park Module in a Large Power Station with a Registered
Capacity of 50 MW or greater, must be capable of meeting the minimum
Frequency response requirement profile subject to and in accordance with the
provisions of Appendix 3.
(vii) Subject to the requirements of CC.6.3.7(e), Offshore Generating Units at a Large
Power Station, Offshore Power Park Modules at a Large Power Station and
Offshore DC Converters in a Large Power Station shall comply with the
requirements of CC.6.3.7. Generators should be aware that Section K of the STC
Issue 5 Revision 17 CC 29 June 2016
26 of 95
places requirements on Offshore Transmission Licensees which utilise a
Transmission DC Converter as part of their Offshore Transmission System to
make appropriate provisions to enable Generators to fulfil their obligations.
(viii) Each OTSDUW DC Converter must be capable of providing a continuous signal
indicating the real time frequency measured at the Interface Point to the Offshore
Grid Entry Point.
(f) For the avoidance of doubt, the requirements of Appendix 3 do not apply to:
(i) Generating Units and/or CCGT Modules which have a Completion Date before
1 January 2001 in England and Wales, and before 1 April 2005 in Scotland, for
whom the remaining requirements of this clause CC.6.3.7 shall continue to apply
unchanged: or
(ii) DC Converters at a DC Converter Station which have a Completion Date before
1 April 2005; or
(iii) Onshore Power Park Modules in England and Wales with a Completion Date
before 1 January 2006 for whom only the requirements of Limited Frequency
Sensitive Mode (BC3.5.2) operation shall apply; or
(iv) Onshore Power Park Modules in operation in Scotland before 1 January 2006 for
whom only the requirements of Limited Frequency Sensitive Mode (BC3.5.2)
operation shall apply; or
(v) Onshore Power Park Modules in operation after 1 January 2006 in Scotland
which have a Completion Date before 1 April 2005 for whom the remaining
requirements of this clause CC.6.3.7 shall continue to apply unchanged; or
(vi) Offshore Power Park Modules which are in a Large Power Station with a
Registered Capacity less than 50MW for whom only the requirements of Limited
Frequency Sensitive Mode (BC3.5.2) operation shall apply; or
Excitation and Voltage Control Performance Requirements
CC.6.3.8 (a) Excitation and voltage control performance requirements applicable to Onshore
Generating Units, Onshore Power Park Modules, Onshore DC Converters and
OTSDUW Plant and Apparatus.
(i) A continuously-acting automatic excitation control system is required to provide
constant terminal voltage control of the Onshore Synchronous Generating Unit
without instability over the entire operating range of the Onshore Generating Unit.
(ii) In respect of Onshore Synchronous Generating Units with a Completion Date
before 1 January 2009, the requirements for excitation control facilities, including
Power System Stabilisers, where in NGET's view these are necessary for system
reasons, will be specified in the Bilateral Agreement. If any Modification to the
excitation control facilities of such Onshore Synchronous Generating Units is
made on or after 1 January 2009 the requirements that shall apply may be
specified in the Bilateral Agreement as varied. To the extent that the Bilateral
Agreement does not specify, the requirements given or referred to in CC.A.6 shall
apply. The performance requirements for a continuously acting automatic
excitation control system that shall be complied with by the User in respect of such
Onshore Synchronous Generating Units with a Completion Date on or after 1
January 2009 are given or referred to in CC.A.6. Reference is made to on-load
commissioning witnessed by NGET in BC2.11.2.
(iii) In the case of an Onshore Non-Synchronous Generating Unit, Onshore DC
Converter, Onshore Power Park Module or OTSDUW Plant and Apparatus at
the Interface Point a continuously-acting automatic control system is required to
provide control of the voltage (or zero transfer of Reactive Power as applicable to
CC.6.3.2) at the Onshore Grid Entry Point or User System Entry Point or in the
case of OTSDUW Plant and Apparatus at the Interface Point without instability
over the entire operating range of the Onshore Non-Synchronous Generating
Issue 5 Revision 17 CC 29 June 2016
27 of 95
Unit, Onshore DC Converter, Onshore Power Park Module or OTSDUW Plant
and Apparatus. Any Plant or Apparatus used in the provisions of such voltage
control within an Onshore Power Park Module may be located at the Power Park
Unit terminals, an appropriate intermediate busbar or the Connection Point.
OTSDUW Plant and Apparatus used in the provision of such voltage control may
be located at the Offshore Grid Entry Point, an appropriate intermediate busbar
or at the Interface Point. In the case of an Onshore Power Park Module in
Scotland with a Completion Date before 1 January 2009, voltage control may be
at the Power Park Unit terminals, an appropriate intermediate busbar or the
Connection Point as specified in the Bilateral Agreement. When operating below
20% Rated MW the automatic control system may continue to provide voltage
control utilising any available reactive capability. If voltage control is not being
provided the automatic control system shall be designed to ensure a smooth
transition between the shaded area bound by CD and the non shaded area bound
by AB in Figure 1 of CC.6.3.2 (c).
(iv) The performance requirements for a continuously acting automatic voltage control
system in respect of Onshore Power Park Modules, Onshore Non-
Synchronous Generating Units and Onshore DC Converters with a
Completion Date before 1 January 2009 will be specified in the Bilateral
Agreement. If any Modification to the continuously acting automatic voltage
control system of such Onshore Power Park Modules, Onshore Non-
Synchronous Generating Units and Onshore DC Converters is made on or
after 1 January 2009 the requirements that shall apply may be specified in the
Bilateral Agreement as varied. To the extent that the Bilateral Agreement does
not specify, the requirements given or referred to in CC.A.7 shall apply. The
performance requirements for a continuously acting automatic voltage control
system that shall be complied with by the User in respect of Onshore Power Park
Modules, Onshore Non-Synchronous Generating Units and Onshore DC
Converters or OTSDUW Plant and Apparatus at the Interface Point with a
Completion Date on or after 1 January 2009 are given or referred to in CC.A.7.
(v) Unless otherwise required for testing in accordance with OC5.A.2, the automatic
excitation control system of an Onshore Synchronous Generating Unit shall
always be operated such that it controls the Onshore Synchronous Generating
Unit terminal voltage to a value that is
- equal to its rated value; or
- only where provisions have been made in the Bilateral Agreement, greater than
its rated value.

(vi) In particular, other control facilities, including constant Reactive Power output
control modes and constant Power Factor control modes (but excluding VAR
limiters) are not required. However, if present in the excitation or voltage control
system they will be disabled unless the Bilateral Agreement records otherwise.
Operation of such control facilities will be in accordance with the provisions
contained in BC2.
(b) Excitation and voltage control performance requirements applicable to Offshore
Generating Units at a Large Power Station, Offshore Power Park Modules at a
Large Power Station and Offshore DC Converters at a Large Power Station.
A continuously acting automatic control system is required to provide either:
(i) control of Reactive Power (as specified in CC.6.3.2(e) (i) (ii)) at the Offshore Grid
Entry Point without instability over the entire operating range of the Offshore
Generating Unit, Offshore DC Converter or Offshore Power Park Module. The
performance requirements for this automatic control system will be specified in the
Bilateral Agreement or;
(ii) where an alternative reactive capability has been specified in the Bilateral
Agreement, in accordance with CC.6.3.2 (e) (iii), the Offshore Generating Unit,
Issue 5 Revision 17 CC 29 June 2016
28 of 95
Offshore Power Park Module or Offshore DC Converter will be required to
control voltage and / or Reactive Power without instability over the entire operating
range of the Offshore Generating Unit, Offshore Power Park Module or
Offshore DC Converter. The performance requirements of the control system will
be specified in the Bilateral Agreement.
In addition to CC.6.3.8(b) (i) and (ii) the requirements for excitation control facilities,
including Power System Stabilisers, where in NGETs view these are necessary for
system reasons, will be specified in the Bilateral Agreement. Reference is made to on-
load commissioning witnessed by NGET in BC2.11.2.
Steady state Load Inaccuracies
CC.6.3.9 The standard deviation of Load error at steady state Load over a 30 minute period must not
exceed 2.5 per cent of a Gensets Registered Capacity. Where a Genset is instructed to
Frequency sensitive operation, allowance will be made in determining whether there has
been an error according to the governor droop characteristic registered under the PC.
For the avoidance of doubt in the case of a Power Park Module allowance will be made for
the full variation of mechanical power output.
Negative Phase Sequence Loadings
CC.6.3.10 In addition to meeting the conditions specified in CC.6.1.5(b), each Synchronous
Generating Unit will be required to withstand, without tripping, the negative phase sequence
loading incurred by clearance of a close-up phase-to-phase fault, by System Back-Up
Protection on the National Electricity Transmission System or User System located
Onshore in which it is Embedded.
Neutral Earthing
CC.6.3.11 At nominal System voltages of 132kV and above the higher voltage windings of a
transformer of a Generating Unit, DC Converter, Power Park Module or transformer
resulting from OTSDUW must be star connected with the star point suitable for connection to
earth. The earthing and lower voltage winding arrangement shall be such as to ensure that
the Earth Fault Factor requirement of paragraph CC.6.2.1.1 (b) will be met on the National
Electricity Transmission System at nominal System voltages of 132kV and above.
Frequency Sensitive Relays
CC.6.3.12 As stated in CC.6.1.3, the System Frequency could rise to 52Hz or fall to 47Hz. Each
Generating Unit, DC Converter, OTSDUW Plant and Apparatus, Power Park Module or
any constituent element must continue to operate within this Frequency range for at least
the periods of time given in CC.6.1.3 unless NGET has agreed to any Frequency-level
relays and/or rate-of-change-of-Frequency relays which will trip such Generating Unit, DC
Converter, OTSDUW Plant and Apparatus, Power Park Module and any constituent
element within this Frequency range, under the Bilateral Agreement.
CC.6.3.13 Generators (including in respect of OTSDUW Plant and Apparatus) and DC Converter
Station owners will be responsible for protecting all their Generating Units (and OTSDUW
Plant and Apparatus), DC Converters or Power Park Modules against damage should
Frequency excursions outside the range 52Hz to 47Hz ever occur. Should such excursions
occur, it is up to the Generator or DC Converter Station owner to decide whether to
disconnect his Apparatus for reasons of safety of Apparatus, Plant and/or personnel.
CC.6.3.14 It may be agreed in the Bilateral Agreement that a Genset shall have a Fast-Start
Capability. Such Gensets may be used for Operating Reserve and their Start-Up may be
initiated by Frequency-level relays with settings in the range 49Hz to 50Hz as specified
pursuant to OC2.

Issue 5 Revision 17 CC 29 June 2016


29 of 95
CC.6.3.15 Fault Ride Through
This section sets out the fault ride through requirements on Generating Units, Power Park
Modules, DC Converters and OTSDUW Plant and Apparatus. Onshore Generating
Units, Onshore Power Park Modules, Onshore DC Converters (including Embedded
Medium Power Stations and Embedded DC Converter Stations not subject to a Bilateral
Agreement and with an Onshore User System Entry Point (irrespective of whether they
are located Onshore or Offshore)) and OTSDUW Plant and Apparatus are required to
operate through System faults and disturbances as defined in CC.6.3.15.1 (a), CC.6.3.15.1
(b) and CC.6.3.15.3. Offshore Generating Units at a Large Power Station, Offshore
Power Park Modules at a Large Power Station and Offshore DC Converters at a Large
Power Station shall have the option of meeting either:
(i) CC.6.3.15.1 (a), CC.6.3.15.1 (b) and CC.6.3.15.3, or:
(ii) CC.6.3.15.2 (a), CC.6.3.15.2 (b) and CC.6.3.15.3
Offshore Generators and Offshore DC Converter owners, should notify NGET which
option they wish to select within 28 days (or such longer period as NGET may agree, in any
event this being no later than 3 months before the Completion Date of the offer for a final
CUSC Contract which would be made following the appointment of the Offshore
Transmission Licensee).
CC.6.3.15.1 Fault Ride through applicable to Generating Units, Power Park Modules and DC Converters
and OTSDUW Plant and Apparatus
(a) Short circuit faults on the Onshore Transmission System (which may include an
Interface Point) at Supergrid Voltage up to 140ms in duration.
(i) Each Generating Unit, DC Converter, or Power Park Module and any
constituent Power Park Unit thereof and OTSDUW Plant and Apparatus shall
remain transiently stable and connected to the System without tripping of any
Generating Unit, DC Converter or Power Park Module and / or any constituent
Power Park Unit, OTSDUW Plant and Apparatus, and for Plant and Apparatus
installed on or after 1 December 2017, reactive compensation equipment, for a
close-up solid three-phase short circuit fault or any unbalanced short circuit fault on
the Onshore Transmission System (including in respect of OTSDUW Plant and
Apparatus, the Interface Point) operating at Supergrid Voltages for a total fault
clearance time of up to 140 ms. A solid three-phase or unbalanced earthed fault
results in zero voltage on the faulted phase(s) at the point of fault. The duration of
zero voltage is dependent on local Protection and circuit breaker operating times.
This duration and the fault clearance times will be specified in the Bilateral
Agreement. Following fault clearance, recovery of the Supergrid Voltage on the
Onshore Transmission System to 90% may take longer than 140ms as
illustrated in Appendix 4A Figures CC.A.4A.1 (a) and (b). It should be noted that in
the case of an Offshore Generating Unit, Offshore DC Converter or Offshore
Power Park Module (including any Offshore Power Park Unit thereof) which is
connected to an Offshore Transmission System which includes a Transmission
DC Converter as part of that Offshore Transmission System, the Offshore Grid
Entry Point voltage may not indicate the presence of a fault on the Onshore
Transmission System. The fault will affect the level of Active Power that can be
transferred to the Onshore Transmission System and therefore subject the
Offshore Generating Unit, Offshore DC Converter or Offshore Power Park
Module (including any Offshore Power Park Unit thereof) to a load rejection.
(ii) Each Generating Unit, Power Park Module and OTSDUW Plant and Apparatus,
shall be designed such that upon both clearance of the fault on the Onshore
Transmission System as detailed in CC.6.3.15.1 (a) (i) and within 0.5 seconds of
the restoration of the voltage at the Onshore Grid Entry Point (for Onshore
Generating Units or Onshore Power Park Modules) or Interface Point (for
Offshore Generating Units, Offshore Power Park Modules or OTSDUW Plant
and Apparatus) to the minimum levels specified in CC.6.1.4 (or within 0.5
Issue 5 Revision 17 CC 29 June 2016
30 of 95
seconds of restoration of the voltage at the User System Entry Point to 90% of
nominal or greater if Embedded), Active Power output or in the case of OTSDUW
Plant and Apparatus, Active Power transfer capability, shall be restored to at
least 90% of the level available immediately before the fault. Once the Active
Power output, or in the case of OTSDUW Plant and Apparatus, Active Power
transfer capability, has been restored to the required level, Active Power
oscillations shall be acceptable provided that:
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped
During the period of the fault as detailed in CC.6.3.15.1 (a) (i) for which the voltage
at the Grid Entry Point (or Interface Point in the case of OTSDUW Plant and
Apparatus) is outside the limits specified in CC.6.1.4, each Generating Unit or
Power Park Module or OTSDUW Plant and Apparatus shall generate maximum
reactive current without exceeding the transient rating limit of the Generating Unit,
OTSDUW Plant and Apparatus or Power Park Module and / or any constituent
Power Park Unit or reactive compensation equipment. For Plant and Apparatus
installed on or after 1 December 2017, switched reactive compensation equipment
(such as mechanically switched capacitors and reactors) shall be controlled such
that it is not switched in or out of service during the fault but may act to assist in
post fault voltage recovery.
(iii) Each DC Converter shall be designed to meet the Active Power recovery
characteristics (and OTSDUW DC Converter shall be designed to meet the Active
Power transfer capability at the Interface Point) as specified in the Bilateral
Agreement upon clearance of the fault on the Onshore Transmission System as
detailed in CC.6.3.15.1 (a) (i).
(b) Supergrid Voltage dips on the Onshore Transmission System greater than 140ms in
duration
(1b) Requirements applicable to Synchronous Generating Units subject to Supergrid
Voltage dips on the Onshore Transmission System greater than 140ms in duration.

In addition to the requirements of CC.6.3.15.1 (a) each Synchronous Generating Unit,


each with a Completion Date on or after 1 April 2005 shall:
(i) remain transiently stable and connected to the System without tripping of any
Synchronous Generating Unit for balanced Supergrid Voltage dips and
associated durations on the Onshore Transmission System (which could be at
the Interface Point) anywhere on or above the heavy black line shown in Figure
5a. Appendix 4A and Figures CC.A.4A.3.2 (a), (b) and (c) provide an explanation
and illustrations of Figure 5a; and,

Issue 5 Revision 17 CC 29 June 2016


31 of 95
Figure 5a
(ii) provide Active Power output at the Grid Entry Point, during Supergrid Voltage
dips on the Onshore Transmission System as described in Figure 5a, at least in
proportion to the retained balanced voltage at the Onshore Grid Entry Point (for
Onshore Synchronous Generating Units) or Interface Point (for Offshore
Synchronous Generating Units) (or the retained balanced voltage at the User
System Entry Point if Embedded) and shall generate maximum reactive current
(where the voltage at the Grid Entry Point is outside the limits specified in
CC.6.1.4) without exceeding the transient rating limits of the Synchronous
Generating Unit and,
(iii) restore Active Power output following Supergrid Voltage dips on the Onshore
Transmission System as described in Figure 5a, within 1 second of restoration of
the voltage to 1.0p.u of the nominal voltage at the:
Onshore Grid Entry Point for directly connected Onshore Synchronous
Generating Units or,
Interface Point for Offshore Synchronous Generating Units or,
User System Entry Point for Embedded Onshore Synchronous
Generating Units or,
User System Entry Point for Embedded Medium Power Stations not
subject to a Bilateral Agreement which comprise Synchronous Generating
Units and with an Onshore User System Entry Point (irrespective of
whether they are located Onshore or Offshore)
to at least 90% of the level available immediately before the occurrence of the dip.
Once the Active Power output has been restored to the required level, Active
Power oscillations shall be acceptable provided that:
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped.
For the avoidance of doubt a balanced Onshore Transmission System Supergrid
Voltage meets the requirements of CC.6.1.5 (b) and CC.6.1.6.
(2b) Requirements applicable to OTSDUW Plant and Apparatus and Power Park Modules
subject to Supergrid Voltage dips on the Onshore Transmission System greater
than 140ms in duration

Issue 5 Revision 17 CC 29 June 2016


32 of 95
In addition to the requirements of CC.6.3.15.1 (a) each OTSDUW Plant and Apparatus
or each Power Park Module and / or any constituent Power Park Unit, each with a
Completion Date on or after the 1 April 2005 shall:
(i) remain transiently stable and connected to the System without tripping of any
OTSDUW Plant and Apparatus, or Power Park Module and / or any constituent
Power Park Unit, for balanced Supergrid Voltage dips and associated durations
on the Onshore Transmission System (which could be at the Interface Point)
anywhere on or above the heavy black line shown in Figure 5b. Appendix 4A and
Figures CC.A.4A.3.4 (a), (b) and (c) provide an explanation and illustrations of
Figure 5b; and,
Supergrid Voltage Level
(% of Nominal)
90
85
80

15

0.14s 1.2s 2.5s 3 minutes

Supergrid Voltage Duration

Figure 5b

(ii) provide Active Power output at the Grid Entry Point or in the case of an
OTSDUW, Active Power transfer capability at the Transmission Interface Point,
during Supergrid Voltage dips on the Onshore Transmission System as
described in Figure 5b, at least in proportion to the retained balanced voltage at the
Onshore Grid Entry Point (for Onshore Power Park Modules) or Interface
Point (for OTSDUW Plant and Apparatus and Offshore Power Park Modules)
(or the retained balanced voltage at the User System Entry Point if Embedded)
except in the case of a Non-Synchronous Generating Unit or OTSDUW Plant
and Apparatus or Power Park Module where there has been a reduction in the
Intermittent Power Source or in the case of OTSDUW Active Power transfer
capability in the time range in Figure 5b that restricts the Active Power output or in
the case of an OTSDUW Active Power transfer capability below this level and
shall generate maximum reactive current (where the voltage at the Grid Entry
Point, or in the case of an OTSDUW Plant and Apparatus, the Interface Point
voltage, is outside the limits specified in CC.6.1.4) without exceeding the transient
rating limits of the OTSDUW Plant and Apparatus or Power Park Module and
any constituent Power Park Unit; and,

(iii) restore Active Power output (or, in the case of OTSDUW, Active Power transfer
capability), following Supergrid Voltage dips on the Onshore Transmission
System as described in Figure 5b, within 1 second of restoration of the voltage at
the:
Onshore Grid Entry Point for directly connected Onshore Power Park
Modules or,

Issue 5 Revision 17 CC 29 June 2016


33 of 95
Interface Point for OTSDUW Plant and Apparatus and Offshore Power
Park Modules or,
User System Entry Point for Embedded Onshore Power Park Modules or,
User System Entry Point for Embedded Medium Power Stations which
comprise Power Park Modules not subject to a Bilateral Agreement and
with an Onshore User System Entry Point (irrespective of whether they are
located Onshore or Offshore)
to the minimum levels specified in CC.6.1.4 to at least 90% of the level available
immediately before the occurrence of the dip except in the case of a Non-
Synchronous Generating Unit, OTSDUW Plant and Apparatus or Power Park
Module where there has been a reduction in the Intermittent Power Source in
the time range in Figure 5b that restricts the Active Power output or, in the case of
OTSDUW, Active Power transfer capability below this level. Once the Active
Power output or, in the case of OTSDUW, Active Power transfer capability has
been restored to the required level, Active Power oscillations shall be acceptable
provided that:
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped.
For the avoidance of doubt a balanced Onshore Transmission System Supergrid
Voltage meets the requirements of CC.6.1.5 (b) and CC.6.1.6.
CC.6.3.15.2 Fault Ride Through applicable to Offshore Generating Units at a Large Power Station,
Offshore Power Park Modules at a Large Power Station and Offshore DC Converters at
a Large Power Station who choose to meet the fault ride through requirements at the LV
side of the Offshore Platform
(a) Requirements on Offshore Generating Units, Offshore Power Park Modules and
Offshore DC Converters to withstand voltage dips on the LV Side of the Offshore
Platform for up to 140ms in duration as a result of faults and / or voltage dips on the
Onshore Transmission System operating at Supergrid Voltage
(i) Each Offshore Generating Unit, Offshore DC Converter, or Offshore Power
Park Module and any constituent Power Park Unit thereof shall remain transiently
stable and connected to the System without tripping of any Offshore Generating
Unit, or Offshore DC Converter or Offshore Power Park Module and / or any
constituent Power Park Unit or, in the case of Plant and Apparatus installed on
or after 1 December 2017, reactive compensation equipment, for any balanced or
unbalanced voltage dips on the LV Side of the Offshore Platform whose profile is
anywhere on or above the heavy black line shown in Figure 6. For the avoidance of
doubt, the profile beyond 140ms in Figure 6 shows the minimum recovery in
voltage that will be seen by the generator following clearance of the fault at 140ms.
Appendix 4B and Figures CC.A.4B.2 (a) and (b) provide further illustration of the
voltage recovery profile that may be seen. It should be noted that in the case of an
Offshore Generating Unit, Offshore DC Converter or Offshore Power Park
Module (including any Offshore Power Park Unit thereof) which is connected to
an Offshore Transmission System which includes a Transmission DC
Converter as part of that Offshore Transmission System, the Offshore Grid
Entry Point voltage may not indicate the presence of a fault on the Onshore
Transmission System. The voltage dip will affect the level of Active Power that
can be transferred to the Onshore Transmission System and therefore subject
the Offshore Generating Unit, Offshore DC Converter or Offshore Power Park
Module (including any Offshore Power Park Unit thereof) to a load rejection.

Issue 5 Revision 17 CC 29 June 2016


34 of 95
V/VN(%)

100%

94%

60%

15%

0 140ms 500ms Time

Figure 6

V/VN is the ratio of the actual voltage on one or more phases at the LV Side of the
Offshore Platform to the nominal voltage of the LV Side of the Offshore
Platform.
(ii) Each Offshore Generating Unit, or Offshore Power Park Module and any
constituent Power Park Unit thereof shall provide Active Power output, during
voltage dips on the LV Side of the Offshore Platform as described in Figure 6, at
least in proportion to the retained voltage at the LV Side of the Offshore Platform
except in the case of an Offshore Non-Synchronous Generating Unit or
Offshore Power Park Module where there has been a reduction in the
Intermittent Power Source in the time range in Figure 6 that restricts the Active
Power output below this level and shall generate maximum reactive current
without exceeding the transient rating limits of the Offshore Generating Unit or
Offshore Power Park Module and any constituent Power Park Unit or, in the
case of Plant and Apparatus installed on or after 1 December 2017, reactive
compensation equipment. Once the Active Power output has been restored to the
required level, Active Power oscillations shall be acceptable provided that:
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped
and;
(iii) Each Offshore DC Converter shall be designed to meet the Active Power
recovery characteristics as specified in the Bilateral Agreement upon restoration
of the voltage at the LV Side of the Offshore Platform.

(b) Requirements of Offshore Generating Units, Offshore Power Park Modules, to


withstand voltage dips on the LV Side of the Offshore Platform greater than 140ms in
duration.
(1b) Requirements applicable to Offshore Synchronous Generating Units to withstand
voltage dips on the LV Side of the Offshore Platform greater than 140ms in duration.
In addition to the requirements of CC.6.3.15.2. (a) each Offshore Synchronous
Generating Unit shall:

Issue 5 Revision 17 CC 29 June 2016


35 of 95
(i) remain transiently stable and connected to the System without tripping of any
Offshore Synchronous Generating Unit for any balanced voltage dips on the LV
side of the Offshore Platform and associated durations anywhere on or above
the heavy black line shown in Figure 7a. Appendix 4B and Figures CC.A.4B.3.2
(a), (b) and (c) provide an explanation and illustrations of Figure 7a. It should be
noted that in the case of an Offshore Synchronous Generating Unit which is
connected to an Offshore Transmission System which includes a Transmission
DC Converter as part of that Offshore Transmission System, the Offshore Grid
Entry Point voltage may not indicate the presence of a voltage dip on the
Onshore Transmission System. The voltage dip will affect the level of Active
Power that can be transferred to the Onshore Transmission System and
therefore subject the Offshore Generating Unit, to a load rejection.

(ii) provide Active Power output, during voltage dips on the LV Side of the Offshore
Platform as described in Figure 7a, at least in proportion to the retained balanced
or unbalanced voltage at the LV Side of the Offshore Platform and shall
generate maximum reactive current (where the voltage at the Offshore Grid Entry
Point is outside the limits specified in CC.6.1.4) without exceeding the transient
rating limits of the Offshore Synchronous Generating Unit and,
(iii) within 1 second of restoration of the voltage to 1.0p.u of the nominal voltage at the
LV Side of the Offshore Platform, restore Active Power to at least 90% of the
Offshore Synchronous Generating Unit's immediate pre-disturbed value, unless
there has been a reduction in the Intermittent Power Source in the time range in
Figure 7a that restricts the Active Power output below this level. Once the Active
Power output has been restored to the required level, Active Power oscillations
shall be acceptable provided that:
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped

(2b) Requirements applicable to Offshore Power Park Modules to withstand voltage dips
on the LV Side of the Offshore Platform greater than 140ms in duration.

Issue 5 Revision 17 CC 29 June 2016


36 of 95
In addition to the requirements of CC.6.3.15.2. (a) each Offshore Power Park Module
and / or any constituent Power Park Unit, shall:
(i) remain transiently stable and connected to the System without tripping of any
Offshore Power Park Module and / or any constituent Power Park Unit, for any
balanced voltage dips on the LV side of the Offshore Platform and associated
durations anywhere on or above the heavy black line shown in Figure 7b. Appendix
4B and Figures CC.A.4B.5. (a), (b) and (c) provide an explanation and illustrations
of Figure 7b. It should be noted that in the case of an Offshore Power Park
Module (including any Offshore Power Park Unit thereof) which is connected to
an Offshore Transmission System which includes a Transmission DC
Converter as part of that Offshore Transmission System, the Offshore Grid
Entry Point voltage may not indicate the presence of a voltage dip on the
Onshore Transmission System. The voltage dip will affect the level of Active
Power that can be transferred to the Onshore Transmission System and
therefore subject the Offshore Power Park Module (including any Offshore
Power Park Unit thereof) to a load rejection.
Voltage at LV Side of Offshore Platform
(% of Nominal)
90
85
80

15

0.14s 1.2s 2.5s 3 minutes


Offshore Platform LV Voltage Duration

Figure 7b

(ii) provide Active Power output, during voltage dips on the LV Side of the Offshore
Platform as described in Figure 7b, at least in proportion to the retained balanced
or unbalanced voltage at the LV Side of the Offshore Platform except in the case
of an Offshore Non-Synchronous Generating Unit or Offshore Power Park
Module where there has been a reduction in the Intermittent Power Source in
the time range in Figure 7b that restricts the Active Power output below this level
and shall generate maximum reactive current (where the voltage at the Offshore
Grid Entry Point is outside the limits specified in CC.6.1.4) without exceeding the
transient rating limits of the Offshore Power Park Module and any constituent
Power Park Unit or reactive compensation equipment. For Plant and Apparatus
installed on or after 1 December 2017, switched reactive compensation equipment
(such as mechanically switched capacitors and reactors) shall be controlled such
that it is not switched in or out of service during the fault but may act to assist in
post fault voltage recovery; and,
(iii) within 1 second of the restoration of the voltage at the LV Side of the Offshore
Platform (to the minimum levels specified in CC.6.1.4) restore Active Power to at
least 90% of the Offshore Power Park Module's immediate pre-disturbed value,
unless there has been a reduction in the Intermittent Power Source in the time
range in Figure 7b that restricts the Active Power output below this level. Once the
Active Power output has been restored to the required level, Active Power
oscillations shall be acceptable provided that:
Issue 5 Revision 17 CC 29 June 2016
37 of 95
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped
CC.6.3.15.3 Other Requirements
(i) In the case of a Power Park Module (comprising of wind-turbine generator units), the
requirements in CC.6.3.15.1 and CC.6.3.15.2 do not apply when the Power Park
Module is operating at less than 5% of its Rated MW or during very high wind speed
conditions when more than 50% of the wind turbine generator units in a Power Park
Module have been shut down or disconnected under an emergency shutdown
sequence to protect Users Plant and Apparatus.
(ii) In addition to meeting the conditions specified in CC.6.1.5(b) and CC.6.1.6, each Non-
Synchronous Generating Unit, OTSDUW Plant and Apparatus or Power Park
Module with a Completion Date after 1 April 2005 and any constituent Power Park
Unit thereof will be required to withstand, without tripping, the negative phase sequence
loading incurred by clearance of a close-up phase-to-phase fault, by System Back-Up
Protection on the Onshore Transmission System operating at Supergrid Voltage.
(iii) In the case of an Onshore Power Park Module in Scotland with a Completion Date
before 1 January 2004 and a Registered Capacity less than 30MW the requirements in
CC.6.3.15.1 (a) do not apply. In the case of an Onshore Power Park Module in
Scotland with a Completion Date on or after 1 January 2004 and before 1 July 2005
and a Registered Capacity less than 30MW the requirements in CC.6.3.15.1 (a) are
relaxed from the minimum Onshore Transmission System Supergrid Voltage of zero
to a minimum Onshore Transmission System Supergrid Voltage of 15% of nominal.
In the case of an Onshore Power Park Module in Scotland with a Completion Date
before 1 January 2004 and a Registered Capacity of 30MW and above the
requirements in CC.6.3.15.1 (a) are relaxed from the minimum Onshore Transmission
System Supergrid Voltage of zero to a minimum Onshore Transmission System
Supergrid Voltage of 15% of nominal.
(iv) To avoid unwanted island operation, Non-Synchronous Generating Units in Scotland
(and those directly connected to a Scottish Offshore Transmission System), Power
Park Modules in Scotland (and those directly connected to a Scottish Offshore
Transmission System) , or OTSDUW Plant and Apparatus with an Interface Point in
Scotland shall be tripped for the following conditions:
(1) Frequency above 52Hz for more than 2 seconds
(2) Frequency below 47Hz for more than 2 seconds
(3) Voltage as measured at the Onshore Connection Point or Onshore User
System Entry Point or Offshore Grid Entry Point or Interface Point in the case
of OTSDUW Plant and Apparatus is below 80% for more than 2.5 seconds
(4) Voltage as measured at the Onshore Connection Point or Onshore User
System Entry Point or Offshore Grid Entry Point or Interface Point in the case
of OTSDUW Plant and Apparatus is above 120% (115% for 275kV) for more than
1 second.
The times in sections (1) and (2) are maximum trip times. Shorter times may be used to
protect the Non-Synchronous Generating Units, or OTSDUW Plant and Apparatus
or Power Park Modules.

Issue 5 Revision 17 CC 29 June 2016


38 of 95
Additional Damping Control Facilities for DC Converters
CC.6.3.16 (a) DC Converter owners, or Generators in respect of OTSDUW DC Converters or
Network Operators in the case of an Embedded DC Converter Station not subject to
a Bilateral Agreement must ensure that any of their Onshore DC Converters or
OTSDUW DC Converters will not cause a sub-synchronous resonance problem on the
Total System. Each DC Converter or OTSDUW DC Converter is required to be
provided with sub-synchronous resonance damping control facilities.
(b) Where specified in the Bilateral Agreement, each DC Converter or OTSDUW DC
Converter is required to be provided with power oscillation damping or any other
identified additional control facilities.
System to Generator Operational Intertripping Scheme
CC.6.3.17 NGET may require that a System to Generator Operational Intertripping Scheme be
installed as part of a condition of the connection of the Generator. Scheme specific details
shall be included in the relevant Bilateral Agreement and shall, in respect of Bilateral
th
Agreements entered into on or after 16 March 2009 include the following information:
(1) the relevant category(ies) of the scheme (referred to as Category 1 Intertripping
Scheme, Category 2 Intertripping Scheme, Category 3 Intertripping Scheme and
Category 4 Intertripping Scheme);
(2) the Generating Unit(s) or CCGT Module(s) or Power Park Module(s) to be either
permanently armed or that can be instructed to be armed in accordance with BC2.8;
(3) the time within which the Generating Unit(s) or CCGT Module(s) or Power Park
Module(s) circuit breaker(s) are to be automatically tripped;
(4) the location to which the trip signal will be provided by NGET. Such location will be
provided by NGET prior to the commissioning of the Generating Unit(s) or CCGT
Module(s) or Power Park Module(s).
Where applicable, the Bilateral Agreement shall include the conditions on the National
Electricity Transmission System during which NGET may instruct the System to
Generator Operational Intertripping Scheme to be armed and the conditions that would
initiate a trip signal.
CC.6.3.18 The time within which the Generating Unit(s) or CCGT Module or Power Park Module
circuit breaker(s) need to be automatically tripped is determined by the specific conditions
local to the Generator. This time to trip (defined as time from provision of the trip signal by
NGET to the specified location, to circuit breaker main contact opening) can typically range
from 100ms to 10sec. A longer time to trip may allow the initiation of an automatic reduction
in the Generating Unit(s) or CCGT Module(s) or Power Park Module(s) output prior to the
automatic tripping of the Generating Unit(s) or CCGT Module(s) or Power Park Module(s)
circuit breaker. Where applicable NGET may provide separate trip signals to allow for either
a longer or shorter time to trip to be initiated.
CC.6.4 General Network Operator And Non-Embedded Customer Requirements
CC.6.4.1 This part of the Grid Code describes the technical and design criteria and performance
requirements for Network Operators and Non-Embedded Customers.

Issue 5 Revision 17 CC 29 June 2016


39 of 95
Neutral Earthing
CC.6.4.2 At nominal System voltages of 132kV and above the higher voltage windings of three phase
transformers and transformer banks connected to the National Electricity Transmission
System must be star connected with the star point suitable for connection to earth. The
earthing and lower voltage winding arrangement shall be such as to ensure that the Earth
Fault Factor requirement of paragraph CC.6.2.1.1 (b) will be met on the National
Electricity Transmission System at nominal System voltages of 132kV and above.
Frequency Sensitive Relays
CC.6.4.3 As explained under OC6, each Network Operator, will make arrangements that will facilitate
automatic low Frequency Disconnection of Demand (based on Annual ACS Conditions).
CC.A.5.5. of Appendix 5 includes specifications of the local percentage Demand that shall
be disconnected at specific frequencies. The manner in which Demand subject to low
Frequency disconnection will be split into discrete MW blocks is specified in OC6.6.
Technical requirements relating to Low Frequency Relays are also listed in Appendix 5.
Operational Metering
CC.6.4.4 Where NGET can reasonably demonstrate that an Embedded Medium Power Station or
Embedded DC Converter Station has a significant effect on the National Electricity
Transmission System, it may require the Network Operator within whose System the
Embedded Medium Power Station or Embedded DC Converter Station is situated to
ensure that the operational metering equipment described in CC.6.5.6 is installed such that
NGET can receive the data referred to in CC.6.5.6. In the case of an Embedded Medium
Power Station subject to, or proposed to be subject to a Bilateral Agreement NGET shall
notify such Network Operator of the details of such installation in writing within 3 months of
being notified of the application to connect under CUSC and in the case of an Embedded
Medium Power Station not subject to, or not proposed to be subject to a Bilateral
Agreement in writing as a Site Specific Requirement in accordance with the timescales in
CUSC 6.5.5. In either case the Network Operator shall ensure that the data referred to in
CC.6.5.6 is provided to NGET.
CC.6.5 Communications Plant
CC.6.5.1 In order to ensure control of the National Electricity Transmission System,
telecommunications between Users and NGET must (including in respect of any OTSDUW
Plant and Apparatus at the OTSUA Transfer Time), if required by NGET, be established in
accordance with the requirements set down below.
CC.6.5.2 Control Telephony and System Telephony
CC.6.5.2.1 Control Telephony is the principle method by which a User's Responsible
Engineer/Operator and NGET Control Engineers speak to one another for the purposes of
control of the Total System in both normal and emergency operating conditions. Control
Telephony provides secure point to point telephony for routine Control Calls, priority
Control Calls and emergency Control Calls.
CC.6.5.2.2 System Telephony is an alternate method by which a User's Responsible
Engineer/Operator and NGET Control Engineers speak to one another for the purposes of
control of the Total System in both normal operating conditions and where practicable,
emergency operating conditions. System Telephony uses the Public Switched Telephony
Network to provide telephony for Control Calls, inclusive of emergency Control Calls.
CC.6.5.2.3 Calls made and received over Control Telephony and System Telephony may be
recorded and subsequently replayed for commercial and operational reasons.
CC.6.5.3 Supervisory Tones
CC.6.5.3.1 Control Telephony supervisory tones indicate to the calling and receiving parties dial,
engaged, ringing, secondary engaged (signifying that priority may be exercised) and priority
disconnect tones.

Issue 5 Revision 17 CC 29 June 2016


40 of 95
CC.6.5.3.2 System Telephony supervisory tones indicate to the calling and receiving parties dial,
engaged and ringing tones.
CC.6.5.4 Obligations in respect of Control Telephony and System Telephony
CC.6.5.4.1 Where NGET requires Control Telephony, Users are required to use the Control
Telephony with NGET in respect of all Connection Points with the National Electricity
Transmission System and in respect of all Embedded Large Power Stations and
Embedded DC Converter Stations. NGET will install Control Telephony at the Users
Control Point where the Users telephony equipment is not capable of providing the
required facilities or is otherwise incompatible with the Transmission Control Telephony.
Details of and relating to the Control Telephony required are contained in the Bilateral
Agreement.
CC.6.5.4.2 Where in NGETs sole opinion the installation of Control Telephony is not practicable at a
Users Control Point(s), NGET shall specify in the Bilateral Agreement whether System
Telephony is required. Where System Telephony is required by NGET, the User shall
ensure that System Telephony is installed.
CC.6.5.4.3 Where System Telephony is installed, Users are required to use the System Telephony
with NGET in respect of those Control Point(s) for which it has been installed. Details of
and relating to the System Telephony required are contained in the Bilateral Agreement.
CC.6.5.4.4 Where Control Telephony or System Telephony is installed, routine testing of such
facilities may be required by NGET (not normally more than once in any calendar month).
The User and NGET shall use reasonable endeavours to agree a test programme and
where NGET requests the assistance of the User in performing the agreed test programme
the User shall provide such assistance.
CC.6.5.4.5 Control Telephony and System Telephony shall only be used for the purposes of
operational voice communication between NGET and the relevant User.
CC.6.5.4.6 Control Telephony contains emergency calling functionality to be used for urgent
operational communication only. Such functionality enables NGET and Users to utilise a
priority call in the event of an emergency. NGET and Users shall only use such priority call
functionality for urgent operational communications.
CC.6.5.5 Technical Requirements for Control Telephony and System Telephony
CC.6.5.5.1 Detailed information on the technical interfaces and support requirements for Control
Telephony applicable in NGETs Transmission Area is provided in the Control Telephony
Electrical Standard identified in the Annex to the General Conditions. Where additional
information, or information in relation to Control Telephony applicable in Scotland, is
requested by Users, this will be provided, where possible, by NGET.
CC.6.5.5.2 System Telephony shall consist of a dedicated Public Switched Telephone Network
telephone line that shall be installed and configured by the relevant User. NGET shall
provide a dedicated free phone number (UK only), for the purposes of receiving incoming
calls to NGET, which Users shall utilise for System Telephony. System Telephony shall
only be utilised by the NGET Control Engineer and the Users Responsible
Engineer/Operator for the purposes of operational communications.
Operational Metering
CC.6.5.6 (a) NGET shall provide system control and data acquisition (SCADA) outstation interface
equipment. The User shall provide such voltage, current, Frequency, Active Power
and Reactive Power measurement outputs and plant status indications and alarms to
the Transmission SCADA outstation interface equipment as required by NGET in
accordance with the terms of the Bilateral Agreement. In the case of OTSDUW, the
User shall provide such SCADA outstation interface equipment and voltage, current,
Frequency, Active Power and Reactive Power measurement outputs and plant status
indications and alarms to the SCADA outstation interface equipment as required by
NGET in accordance with the terms of the Bilateral Agreement.

Issue 5 Revision 17 CC 29 June 2016


41 of 95
(b) For the avoidance of doubt, for Active Power and Reactive Power measurements,
circuit breaker and disconnector status indications from:
(i) CCGT Modules at Large Power Stations, the outputs and status indications must
each be provided to NGET on an individual CCGT Unit basis. In addition, where
identified in the Bilateral Agreement, Active Power and Reactive Power
measurements from Unit Transformers and/or Station Transformers must be
provided.
(ii) DC Converters at DC Converter Stations and OTSDUW DC Converters, the
outputs and status indications must each be provided to NGET on an individual DC
Converter basis. In addition, where identified in the Bilateral Agreement, Active
Power and Reactive Power measurements from converter and/or station
transformers must be provided.
(iii) Power Park Modules at Embedded Large Power Stations and at directly
connected Power Stations, the outputs and status indications must each be
provided to NGET on an individual Power Park Module basis. In addition, where
identified in the Bilateral Agreement, Active Power and Reactive Power
measurements from station transformers must be provided.
(iv) In respect of OTSDUW Plant and Apparatus, the outputs and status indications
must be provided to NGET for each piece of electrical equipment. In addition,
where identified in the Bilateral Agreement, Active Power and Reactive Power
measurements at the Interface Point must be provided.
(c) For the avoidance of doubt, the requirements of CC.6.5.6(a) in the case of a Cascade
Hydro Scheme will be provided for each Generating Unit forming part of that Cascade
Hydro Scheme. In the case of Embedded Generating Units forming part of a
Cascade Hydro Scheme the data may be provided by means other than a NGET
SCADA outstation located at the Power Station, such as, with the agreement of the
Network Operator in whose system such Embedded Generating Unit is located, from
the Network Operators SCADA system to NGET. Details of such arrangements will
be contained in the relevant Bilateral Agreements between NGET and the Generator
and the Network Operator.
(d) In the case of a Power Park Module, additional energy input signals (e.g. wind speed,
and wind direction) may be specified in the Bilateral Agreement. For Power Park
Modules with a Completion Date on or after 1st April 2016 a Power Available signal
will also be specified in the Bilateral Agreement. The signals would be used to
establish the potential level of energy input from the Intermittent Power Source for
monitoring pursuant to CC.6.6.1 and Ancillary Services and will, in the case of a wind
farm, be used to provide NGET with advanced warning of excess wind speed shutdown
and to determine the level of Headroom available from Power Park Modules for the
purposes of calculating response and reserve. For the avoidance of doubt, the Power
Available signal would be automatically provided to NGET and represent the sum of
the potential output of all available and operational Power Park Units within the Power
Park Module. The refresh rate of the Power Available signal shall be specified in the
Bilateral Agreement.
Instructor Facilities
CC.6.5.7 The User shall accommodate Instructor Facilities provided by NGET for the receipt of
operational messages relating to System conditions.
Electronic Data Communication Facilities
CC.6.5.8 (a) All BM Participants must ensure that appropriate electronic data communication
facilities are in place to permit the submission of data, as required by the Grid Code, to
NGET.
(b) In addition,
(1) any User that wishes to participate in the Balancing Mechanism;
Issue 5 Revision 17 CC 29 June 2016
42 of 95
or
(2) any BM Participant in respect of its BM Units at a Power Station where the
Construction Agreement and/or a Bilateral Agreement has a Completion Date
on or after 1 January 2013 and the BM Participant is required to provide all Part 1
System Ancillary Services in accordance with CC.8.1 (unless NGET has
otherwise agreed)
must ensure that appropriate automatic logging devices are installed at the Control
Points of its BM Units to submit data to and to receive instructions from NGET, as
required by the Grid Code. For the avoidance of doubt, in the case of an
Interconnector User the Control Point will be at the Control Centre of the
appropriate Externally Interconnected System Operator.

(c) Detailed specifications of these required electronic facilities will be provided by NGET
on request and they are listed as Electrical Standards in the Annex to the General
Conditions.
Facsimile Machines
CC.6.5.9 Each User and NGET shall provide a facsimile machine or machines:
(a) in the case of Generators, at the Control Point of each Power Station and at its
Trading Point;
(b) in the case of NGET and Network Operators, at the Control Centre(s); and
(c) in the case of Non-Embedded Customers and DC Converter Station owners at the
Control Point.
Each User shall notify, prior to connection to the System of the User's Plant and
Apparatus, NGET of its or their telephone number or numbers, and will notify NGET of any
changes. Prior to connection to the System of the User's Plant and Apparatus NGET shall
notify each User of the telephone number or numbers of its facsimile machine or machines
and will notify any changes.
CC.6.5.10 Busbar Voltage
NGET shall, subject as provided below, provide each Generator or DC Converter Station
owner at each Grid Entry Point where one of its Power Stations or DC Converter
Stations is connected with appropriate voltage signals to enable the Generator or DC
Converter Station owner to obtain the necessary information to permit its Gensets or DC
Converters to be Synchronised to the National Electricity Transmission System. The
term "voltage signal" shall mean in this context, a point of connection on (or wire or wires
from) a relevant part of Transmission Plant and/or Apparatus at the Grid Entry Point, to
which the Generator or DC Converter Station owner, with NGET's agreement (not to be
unreasonably withheld) in relation to the Plant and/or Apparatus to be attached, will be able
to attach its Plant and/or Apparatus (normally a wire or wires) in order to obtain
measurement outputs in relation to the busbar.
CC.6.5.11 Bilingual Message Facilities
(a) A Bilingual Message Facility is the method by which the Users Responsible
Engineer/Operator, the Externally Interconnected System Operator and NGET
Control Engineers communicate clear and unambiguous information in two languages
for the purposes of control of the Total System in both normal and emergency
operating conditions.
(b) A Bilingual Message Facility, where required, will provide up to two hundred pre-defined
messages with up to five hundred and sixty characters each. A maximum of one minute
is allowed for the transmission to, and display of, the selected message at any
destination. The standard messages must be capable of being displayed at any
combination of locations and can originate from any of these locations. Messages
displayed in the UK will be displayed in the English language.
Issue 5 Revision 17 CC 29 June 2016
43 of 95
(c) Detailed information on a Bilingual Message Facility and suitable equipment required for
individual User applications will be provided by NGET upon request.
CC.6.6 System Monitoring
CC.6.6.1 Monitoring equipment is provided on the National Electricity Transmission System to
enable NGET to monitor its power system dynamic performance conditions. Where this
monitoring equipment requires voltage and current signals on the Generating Unit (other
than Power Park Unit), DC Converter or Power Park Module circuit from the User or from
OTSDUW Plant and Apparatus, NGET will inform the User and they will be provided by the
User with both the timing of the installation of the equipment for receiving such signals and
its exact position being agreed (the User's agreement not to be unreasonably withheld) and
the costs being dealt with, pursuant to the terms of the Bilateral Agreement.
CC.6.6.2 For all on site monitoring by NGET of witnessed tests pursuant to the CP or OC5 the User
shall provide suitable test signals as outlined in OC5.A.1.
CC.6.6.2.1 The signals which shall be provided by the User to NGET for onsite monitoring shall be of
the following resolution, unless otherwise agreed by NGET:
(i) 1 Hz for reactive range tests
(ii) 10 Hz for frequency control tests
(iii) 100 Hz for voltage control tests
CC.6.6.2.2 The User will provide all relevant signals for this purpose in the form of d.c. voltages within
the range -10V to +10V. In exceptional circumstances some signals may be accepted as d.c.
voltages within the range -60V to +60V with prior agreement between the User and NGET.
All signals shall:
(i) in the case of an Onshore Power Park Module, DC Convertor Station or
Synchronous Generating Unit, be suitably terminated in a single accessible location
at the Generator or DC Converter Station owners site.
(ii) in the case of an Offshore Power Park Module and OTSDUW Plant and Apparatus,
be transmitted onshore without attenuation, delay or filtering which would result in the
inability to fully demonstrate the objectives of the test, or identify any potential safety or
plant instability issues, and be suitably terminated in a single robust location normally
located at or near the onshore Interface Point of the Offshore Transmission System
to which it is connected.
CC.6.6.2.3 All signals shall be suitably scaled across the range. The following scaling would (unless
NGET notify the User otherwise) be acceptable to NGET:
(a) 0MW to Registered Capacity or Interface Point Capacity 0-8V dc
(b) Maximum leading Reactive Power to maximum lagging Reactive Power -8 to 8V dc
(c) 48 52Hz as -8 to 8V dc
(d) Nominal terminal or connection point voltage -10% to +10% as -8 to 8V dc
CC.6.6.2.4 The User shall provide to NGET a 230V power supply adjacent to the signal terminal
location.

CC.7 SITE RELATED CONDITIONS


CC.7.1 Not used.
CC.7.2 Responsibilities For Safety
CC.7.2.1 In England and Wales, any User entering and working on its Plant and/or Apparatus
(including, until the OTSUA Transfer Time, any OTSUA) on a Transmission Site will work
to the Safety Rules of NGET.

Issue 5 Revision 17 CC 29 June 2016


44 of 95
In Scotland or Offshore, any User entering and working on its Plant and/or Apparatus
(including, until the OTSUA Transfer Time, any OTSUA) on a Transmission Site will work
to the Safety Rules of the Relevant Transmission Licensee, as advised by NGET.
CC.7.2.2 NGET entering and working on Transmission Plant and/or Apparatus on a User Site will
work to the User's Safety Rules. For User Sites in Scotland or Offshore, NGET shall
procure that the Relevant Transmission Licensee entering and working on Transmission
Plant and/or Apparatus on a User Site will work to the Users Safety Rules.
CC.7.2.3 A User may, with a minimum of six weeks notice, apply to NGET for permission to work
according to that Users own Safety Rules when working on its Plant and/or Apparatus on
a Transmission Site rather than those set out in CC.7.2.1. If NGET is of the opinion that
the User's Safety Rules provide for a level of safety commensurate with those set out in
CC.7.2.1, NGET will notify the User, in writing, that, with effect from the date requested by
the User, the User may use its own Safety Rules when working on its Plant and/or
Apparatus on the Transmission Site. For a Transmission Site in Scotland or Offshore,
in forming its opinion, NGET will seek the opinion of the Relevant Transmission Licensee.
Until receipt of such written approval from NGET, the User will continue to use the Safety
Rules as set out in CC.7.2.1.
CC.7.2.4 In the case of a User Site in England and Wales, NGET may, with a minimum of six weeks
notice, apply to a User for permission to work according to NGETs Safety Rules when
working on Transmission Plant and/or Apparatus on that User Site, rather than the Users
Safety Rules. If the User is of the opinion that NGETs Safety Rules provide for a level of
safety commensurate with that of that Users Safety Rules, it will notify NGET, in writing,
that, with the effect from the date requested by NGET, NGET may use its own Safety Rules
when working on its Transmission Plant and/or Apparatus on that User Site. Until receipt
of such written approval from the User, NGET shall continue to use the Users Safety
Rules.
In the case of a User Site in Scotland or Offshore, NGET may, with a minimum of six weeks
notice, apply to a User for permission for the Relevant Transmission Licensee to work
according to the Relevant Transmission Licensees Safety Rules when working on
Transmission Plant and/or Apparatus on that User Site, rather than the Users Safety
Rules. If the User is of the opinion that the Relevant Transmission Licensees Safety
Rules, provide for a level of safety commensurate with that of that Users Safety Rules, it
will notify NGET, in writing, that, with effect from the date requested by NGET, that the
Relevant Transmission Licensee may use its own Safety Rules when working on its
Transmission Plant and/or Apparatus on that Users Site. Until receipt of such written
approval from the User, NGET shall procure that the Relevant Transmission Licensee
shall continue to use the Users Safety Rules.
CC.7.2.5 For a Transmission Site in England and Wales, if NGET gives its approval for the Users
Safety Rules to apply to the User when working on its Plant and/or Apparatus, that does
not imply that the Users Safety Rules will apply to entering the Transmission Site and
access to the Users Plant and/or Apparatus on that Transmission Site. Bearing in mind
NGETs responsibility for the whole Transmission Site, entry and access will always be in
accordance with NGETs site access procedures. For a User Site in England and Wales, if
the User gives its approval for NGETs Safety Rules to apply to NGET when working on its
Plant and Apparatus, that does not imply that NGETs Safety Rules will apply to entering
the User Site, and access to the Transmission Plant and Apparatus on that User Site.
Bearing in mind the Users responsibility for the whole User Site, entry and access will
always be in accordance with the Users site access procedures.

Issue 5 Revision 17 CC 29 June 2016


45 of 95
For a Transmission Site in Scotland or Offshore, if NGET gives its approval for the Users
Safety Rules to apply to the User when working on its Plant and/or Apparatus, that does
not imply that the Users Safety Rules will apply to entering the Transmission Site and
access to the Users Plant and/or Apparatus on that Transmission Site. Bearing in mind
the Relevant Transmission Licensees responsibility for the whole Transmission Site,
entry and access will always be in accordance with the Relevant Transmission Licensees
site access procedures. For a User Site in Scotland or Offshore, if the User gives its
approval for Relevant Transmission Licensee Safety Rules to apply to the Relevant
Transmission Licensee when working on its Plant and Apparatus, that does not imply that
the Relevant Transmission Licensees Safety Rules will apply to entering the User Site,
and access to the Transmission Plant and Apparatus on that User Site. Bearing in mind
the Users responsibility for the whole User Site, entry and access will always be in
accordance with the Users site access procedures.
CC.7.2.6 For User Sites in England and Wales, Users shall notify NGET of any Safety Rules that
apply to NGETs staff working on User Sites. For Transmission Sites in England and
Wales, NGET shall notify Users of any Safety Rules that apply to the Users staff working
on the Transmission Site.
For User Sites in Scotland or Offshore, Users shall notify NGET of any Safety Rules that
apply to the Relevant Transmission Licensees staff working on User Sites. For
Transmission Sites in Scotland or Offshore NGET shall procure that the Relevant
Transmission Licensee shall notify Users of any Safety Rules that apply to the Users
staff working on the Transmission Site.
CC.7.2.7 Each Site Responsibility Schedule must have recorded on it the Safety Rules which apply
to each item of Plant and/or Apparatus.
CC.7.2.8 In the case of OTSUA a User Site or Transmission Site shall, for the purposes of this
CC.7.2, include a site at which there is an Interface Point until the OTSUA Transfer Time
when it becomes part of the National Electricity Transmission System.
CC.7.3 Site Responsibility Schedules
CC.7.3.1 In order to inform site operational staff and NGET Control Engineers of agreed
responsibilities for Plant and/or Apparatus at the operational interface, a Site
Responsibility Schedule shall be produced for Connection Sites (and in the case of
OTSUA, until the OTSUA Transfer Time, Interface Sites) in England and Wales for NGET
and Users with whom they interface, and for Connection Sites (and in the case of OTSUA,
until the OTSUA Transfer Time, Interface Sites) in Scotland or Offshore for NGET, the
Relevant Transmission Licensee and Users with whom they interface.
CC.7.3.2 The format, principles and basic procedure to be used in the preparation of Site
Responsibility Schedules are set down in Appendix 1.
CC.7.4 Operation And Gas Zone Diagrams
Operation Diagrams
CC.7.4.1 An Operation Diagram shall be prepared for each Connection Site at which a Connection
Point exists (and in the case of OTSDUW Plant and Apparatus, by Users for each
Interface Point) using, where appropriate, the graphical symbols shown in Part 1A of
Appendix 2. Users should also note that the provisions of OC11 apply in certain
circumstances.

Issue 5 Revision 17 CC 29 June 2016


46 of 95
CC.7.4.2 The Operation Diagram shall include all HV Apparatus and the connections to all external
circuits and incorporate numbering, nomenclature and labelling, as set out in OC11. At those
Connection Sites (or in the case of OTSDUW Plant and Apparatus, Interface Points)
where gas-insulated metal enclosed switchgear and/or other gas-insulated HV Apparatus is
installed, those items must be depicted within an area delineated by a chain dotted line
which intersects gas-zone boundaries. The nomenclature used shall conform with that used
on the relevant Connection Site and circuit (and in the case of OTSDUW Plant and
Apparatus, Interface Point and circuit). The Operation Diagram (and the list of technical
details) is intended to provide an accurate record of the layout and circuit interconnections,
ratings and numbering and nomenclature of HV Apparatus and related Plant.
CC.7.4.3 A non-exhaustive guide to the types of HV Apparatus to be shown in the Operation
Diagram is shown in Part 2 of Appendix 2, together with certain basic principles to be
followed unless equivalent principles are approved by NGET.
Gas Zone Diagrams
CC.7.4.4 A Gas Zone Diagram shall be prepared for each Connection Site at which a Connection
Point (and in the case of OTSDUW Plant and Apparatus, by Users for an Interface Point)
exists where gas-insulated switchgear and/or other gas-insulated HV Apparatus is utilised.
They shall use, where appropriate, the graphical symbols shown in Part 1B of Appendix 2.
CC.7.4.5 The nomenclature used shall conform with that used in the relevant Connection Site and
circuit (and in the case of OTSDUW Plant and Apparatus, relevant Interface Point and
circuit).
CC.7.4.6 The basic principles set out in Part 2 of Appendix 2 shall be followed in the preparation of
Gas Zone Diagrams unless equivalent principles are approved by NGET.
Preparation of Operation and Gas Zone Diagrams for Users' Sites and Transmission
Interface Sites
CC.7.4.7 In the case of a User Site, the User shall prepare and submit to NGET, an Operation
Diagram for all HV Apparatus on the User side of the Connection Point (and in the case
of OTSDUW Plant and Apparatus, on what will be the Offshore Transmission side of the
Connection Point and the Interface Point) and NGET shall provide the User with an
Operation Diagram for all HV Apparatus on the Transmission side of the Connection
Point (and in the case of OTSDUW Plant and Apparatus on what will be the Onshore
Transmission side of the Interface Point, in accordance with the timing requirements of the
Bilateral Agreement and/or Construction Agreement prior to the Completion Date under
the Bilateral Agreement and/or Construction Agreement.
CC.7.4.8 The User will then prepare, produce and distribute, using the information submitted on the
User's Operation Diagram and NGET Operation Diagram, a composite Operation
Diagram for the complete Connection Site (and in the case of OTSDUW Plant and
Apparatus, Interface Point), also in accordance with the timing requirements of the
Bilateral Agreement and/or Construction Agreement .
CC.7.4.9 The provisions of CC.7.4.7 and CC.7.4.8 shall apply in relation to Gas Zone Diagrams
where gas-insulated switchgear and/or other gas-insulated HV Apparatus is utilised.
Preparation of Operation and Gas Zone Diagrams for Transmission Sites
CC.7.4.10 In the case of an Transmission Site, the User shall prepare and submit to NGET an
Operation Diagram for all HV Apparatus on the User side of the Connection Point, in
accordance with the timing requirements of the Bilateral Agreement and/or Construction
Agreement.
CC.7.4.11 NGET will then prepare, produce and distribute, using the information submitted on the
User's Operation Diagram, a composite Operation Diagram for the complete Connection
Site, also in accordance with the timing requirements of the Bilateral Agreement and/or
Construction Agreement .
CC.7.4.12 The provisions of CC.7.4.10 and CC.7.4.11 shall apply in relation to Gas Zone Diagrams
where gas-insulated switchgear and/or other gas-insulated HV Apparatus is utilised.
Issue 5 Revision 17 CC 29 June 2016
47 of 95
CC.7.4.13 Changes to Operation and Gas Zone Diagrams
CC.7.4.13.1 When NGET has decided that it wishes to install new HV Apparatus or it wishes to change
the existing numbering or nomenclature of Transmission HV Apparatus at a Transmission
Site, NGET will (unless it gives rise to a Modification under the CUSC, in which case the
provisions of the CUSC as to the timing apply) one month prior to the installation or change,
send to each such User a revised Operation Diagram of that Transmission Site,
incorporating the new Transmission HV Apparatus to be installed and its numbering and
nomenclature or the changes, as the case may be. OC11 is also relevant to certain
Apparatus.
CC.7.4.13.2 When a User has decided that it wishes to install new HV Apparatus, or it wishes to change
the existing numbering or nomenclature of its HV Apparatus at its User Site, the User will
(unless it gives rise to a Modification under the CUSC, in which case the provisions of the
CUSC as to the timing apply) one month prior to the installation or change, send to NGET a
revised Operation Diagram of that User Site incorporating the new User HV Apparatus to
be installed and its numbering and nomenclature or the changes as the case may be. OC11
is also relevant to certain Apparatus.
CC.7.4.13.3 The provisions of CC.7.4.13.1 and CC.7.4.13.2 shall apply in relation to Gas Zone
Diagrams where gas-insulated switchgear and/or other gas-insulated HV Apparatus is
installed.
Validity
CC.7.4.14 (a) The composite Operation Diagram prepared by NGET or the User, as the case may
be, will be the definitive Operation Diagram for all operational and planning activities
associated with the Connection Site. If a dispute arises as to the accuracy of the
composite Operation Diagram, a meeting shall be held at the Connection Site, as
soon as reasonably practicable, between NGET and the User, to endeavour to resolve
the matters in dispute.
(b) The composite Operation Diagram prepared by NGET or the User, as the case may
be, will be the definitive Operation Diagram for all operational and planning activities
associated with the Interface Point until the OTSUA Transfer Time. If a dispute arises
as to the accuracy of the composite Operation Diagram prior to the OTSUA Transfer
Time, a meeting shall be held at the Interface Point, as soon as reasonably
practicable, between NGET and the User, to endeavour to resolve the matters in
dispute.
(c) An equivalent rule shall apply for Gas Zone Diagrams where they exist for a
Connection Site.
CC.7.4.15 In the case of OTSUA, a User Site and Transmission Site shall, for the purposes of this
CC.7.4, include a site at which there is an Interface Point until the OTSUA Transfer Time
when it becomes part of the National Electricity Transmission System and references to
HV Apparatus in this CC.7.4 shall include references to HV OTSUA.
CC.7.5 Site Common Drawings
CC.7.5.1 Site Common Drawings will be prepared for each Connection Site (and in the case of
OTSDUW, each Interface Point) and will include Connection Site (and in the case of
OTSDUW, Interface Point) layout drawings, electrical layout drawings, common
Protection/control drawings and common services drawings.
Preparation of Site Common Drawings for a User Site and Transmission Interface Site
CC.7.5.2 In the case of a User Site, NGET shall prepare and submit to the User, Site Common
Drawings for the Transmission side of the Connection Point (and in the case of OTSDUW
Plant and Apparatus, on what will be the Onshore Transmission side of the Interface
Point,) and the User shall prepare and submit to NGET, Site Common Drawings for the
User side of the Connection Point (and in the case of OTSDUW, on what will be the
Offshore Transmission side of the Interface Point) in accordance with the timing
requirements of the Bilateral Agreement and/or Construction Agreement.
Issue 5 Revision 17 CC 29 June 2016
48 of 95
CC.7.5.3 The User will then prepare, produce and distribute, using the information submitted on the
Transmission Site Common Drawings, Site Common Drawings for the complete
Connection Site (and in the case of OTSDUW, Interface Point) in accordance with the
timing requirements of the Bilateral Agreement and/or Construction Agreement .
Preparation of Site Common Drawings for a Transmission Site
CC.7.5.4 In the case of a Transmission Site, the User will prepare and submit to NGET Site
Common Drawings for the User side of the Connection Point in accordance with the
timing requirements of the Bilateral Agreement and/or Construction Agreement.
CC.7.5.5 NGET will then prepare, produce and distribute, using the information submitted in the
User's Site Common Drawings, Site Common Drawings for the complete Connection
Site in accordance with the timing requirements of the Bilateral Agreement and/or
Construction Agreement.
CC.7.5.6 When a User becomes aware that it is necessary to change any aspect of the Site
Common Drawings at a Connection Site (and in the case of OTSDUW, Interface Point) it
will:
(a) if it is a User Site, as soon as reasonably practicable, prepare, produce and distribute
revised Site Common Drawings for the complete Connection Site (and in the case of
OTSDUW, Interface Point); and
(b) if it is a Transmission Site, as soon as reasonably practicable, prepare and submit to
NGET revised Site Common Drawings for the User side of the Connection Point
(and in the case of OTSDUW, Interface Point) and NGET will then, as soon as
reasonably practicable, prepare, produce and distribute, using the information submitted
in the User's Site Common Drawings, revised Site Common Drawings for the
complete Connection Site (and in the case of OTSDUW, Interface Point).
In either case, if in the User's reasonable opinion the change can be dealt with by it notifying
NGET in writing of the change and for each party to amend its copy of the Site Common
Drawings (or where there is only one set, for the party holding that set to amend it), then it
shall so notify and each party shall so amend. If the change gives rise to a Modification
under the CUSC, the provisions of the CUSC as to timing will apply.
CC.7.5.7 When NGET becomes aware that it is necessary to change any aspect of the Site Common
Drawings at a Connection Site(and in the case of OTSDUW, Interface Point) it will:
(a) if it is a Transmission Site, as soon as reasonably practicable, prepare, produce and
distribute revised Site Common Drawings for the complete Connection Site (and in
the case of OTSDUW, Interface Point); and
(b) if it is a User Site, as soon as reasonably practicable, prepare and submit to the User
revised Site Common Drawings for the Transmission side of the Connection Point
(in the case of OTSDUW, Interface Point) and the User will then, as soon as
reasonably practicable, prepare, produce and distribute, using the information submitted
in the Transmission Site Common Drawings, revised Site Common Drawings for
the complete Connection Site (and in the case of OTSDUW, Interface Point).
In either case, if in NGET's reasonable opinion the change can be dealt with by it notifying
the User in writing of the change and for each party to amend its copy of the Site Common
Drawings (or where there is only one set, for the party holding that set to amend it), then it
shall so notify and each party shall so amend. If the change gives rise to a Modification
under the CUSC, the provisions of the CUSC as to timing will apply.
Validity
CC.7.5.8 (a) The Site Common Drawings for the complete Connection Site prepared by the User
or NGET, as the case may be, will be the definitive Site Common Drawings for all
operational and planning activities associated with the Connection Site. If a dispute
arises as to the accuracy of the Site Common Drawings, a meeting shall be held at the
Site, as soon as reasonably practicable, between NGET and the User, to endeavour to
resolve the matters in dispute.
Issue 5 Revision 17 CC 29 June 2016
49 of 95
(b) The Site Common Drawing prepared by NGET or the User, as the case may be, will
be the definitive Site Common Drawing for all operational and planning activities
associated with the Interface Point until the OTSUA Transfer Time. If a dispute arises
as to the accuracy of the composite Operation Diagram prior to the OTSUA Transfer
Time, a meeting shall be held at the Interface Point, as soon as reasonably
practicable, between NGET and the User, to endeavour to resolve the matters in
dispute.
CC.7.5.9 In the case of OTSUA, a User Site and Transmission Site shall, for the purposes of this
CC.7.5, include a site at which there is an Interface Point until the OTSUA Transfer Time
when it becomes part of the National Electricity Transmission System.
CC.7.6 Access
CC.7.6.1 The provisions relating to access to Transmission Sites by Users, and to Users' Sites by
Transmission Licensees, are set out in each Interface Agreement (or in the case of
Interfaces Sites prior to the OTSUA Transfer Time agreements in similar form) with, for
Transmission Sites in England and Wales, NGET and each User, and for Transmission
Sites in Scotland and Offshore, the Relevant Transmission Licensee and each User.
CC.7.6.2 In addition to those provisions, where a Transmission Site in England and Wales contains
exposed HV conductors, unaccompanied access will only be granted to individuals holding
an Authority for Access issued by NGET and where a Transmission Site in Scotland or
Offshore contains exposed HV conductors, unaccompanied access will only be granted to
individuals holding an Authority for Access issued by the Relevant Transmission
Licensee.
CC.7.6.3 The procedure for applying for an Authority for Access is contained in the Interface
Agreement.
CC.7.7 Maintenance Standards
CC.7.7.1 It is the User's responsibility to ensure that all its Plant and Apparatus (including, until the
OTSUA Transfer Time, any OTSUA) on a Transmission Site is tested and maintained
adequately for the purpose for which it is intended, and to ensure that it does not pose a
threat to the safety of any Transmission Plant, Apparatus or personnel on the
Transmission Site. NGET will have the right to inspect the test results and maintenance
records relating to such Plant and Apparatus at any time
CC.7.7.2 For User Sites in England and Wales, NGET has a responsibility to ensure that all
Transmission Plant and Apparatus on a User Site is tested and maintained adequately for
the purposes for which it is intended and to ensure that it does not pose a threat to the safety
of any User's Plant, Apparatus or personnel on the User Site.
For User Sites in Scotland and Offshore, NGET shall procure that the Relevant
Transmission Licensee has a responsibility to ensure that all Transmission Plant and
Apparatus on a User Site is tested and maintained adequately for the purposes for which it
is intended and to ensure that it does not pose a threat to the safety of any Users Plant,
Apparatus or personnel on the User Site.
The User will have the right to inspect the test results and maintenance records relating to
such Plant and Apparatus on its User Site at any time.
CC.7.8 Site Operational Procedures
CC.7.8.1 NGET and Users with an interface with NGET, must make available staff to take necessary
Safety Precautions and carry out operational duties as may be required to enable
work/testing to be carried out and for the operation of Plant and Apparatus (including, prior
to the OTSUA Transfer Time, any OTSUA) connected to the Total System.

Issue 5 Revision 17 CC 29 June 2016


50 of 95
CC.7.9 Generators and DC Converter Station owners shall provide a Control Point in respect of
each Power Station directly connected to the National Electricity Transmission System
and Embedded Large Power Station or DC Converter Station to receive an act upon
instructions pursuant to OC7 and BC2 at all times that Generating Units or Power Park
Modules at the Power Station are generating or available to generate or DC Converters at
the DC Converter Station are importing or exporting or available to do so. The Control
Point shall be continuously manned except where the Bilateral Agreement in respect of
such Embedded Power Station specifies that compliance with BC2 is not required, where
the Control Point shall be manned between the hours of 0800 and 1800 each day.

CC.8 ANCILLARY SERVICES


CC.8.1 System Ancillary Services
The CC contain requirements for the capability for certain Ancillary Services, which are
needed for System reasons ("System Ancillary Services"). There follows a list of these
System Ancillary Services, together with the paragraph number of the CC (or other part of
the Grid Code) in which the minimum capability is required or referred to. The list is divided
into two categories: Part 1 lists the System Ancillary Services which
(a) Generators in respect of Large Power Stations are obliged to provide (except
Generators in respect of Large Power Stations which have a Registered Capacity of
less than 50MW and comprise Power Park Modules); and,
(b) Generators in respect of Large Power Stations with a Registered Capacity of less
than 50MW and comprise Power Park Modules are obliged to provide in respect of
Reactive Power only; and,
(c) DC Converter Station owners are obliged to have the capability to supply; and

(d) Generators in respect of Medium Power Stations (except Embedded Medium Power
Stations) are obliged to provide in respect of Reactive Power only:
and Part 2 lists the System Ancillary Services which Generators will provide only if
agreement to provide them is reached with NGET:
Part 1
(a) Reactive Power supplied (in accordance with CC.6.3.2) otherwise than by means of
synchronous or static compensators (except in the case of a Power Park Module
where synchronous or static compensators within the Power Park Module may be
used to provide Reactive Power)
(b) Frequency Control by means of Frequency sensitive generation - CC.6.3.7 and
BC3.5.1
Part 2
(c) Frequency Control by means of Fast Start - CC.6.3.14
(d) Black Start Capability - CC.6.3.5
(e) System to Generator Operational Intertripping

Issue 5 Revision 17 CC 29 June 2016


51 of 95
CC.8.2 Commercial Ancillary Services
Other Ancillary Services are also utilised by NGET in operating the Total System if these
have been agreed to be provided by a User (or other person) under an Ancillary Services
Agreement or under a Bilateral Agreement, with payment being dealt with under an
Ancillary Services Agreement or in the case of Externally Interconnected System
Operators or Interconnector Users, under any other agreement (and in the case of
Externally Interconnected System Operators and Interconnector Users includes
ancillary services equivalent to or similar to System Ancillary Services) ("Commercial
Ancillary Services"). The capability for these Commercial Ancillary Services is set out in
the relevant Ancillary Services Agreement or Bilateral Agreement (as the case may be).

Issue 5 Revision 17 CC 29 June 2016


52 of 95
APPENDIX 1 - SITE RESPONSIBILITY SCHEDULES
FORMAT, PRINCIPLES AND BASIC PROCEDURE TO BE USED IN THE PREPARATION
OF SITE RESPONSIBILITY SCHEDULES

CC.A.1.1 Principles
Types of Schedules
CC.A.1.1.1 At all Complexes (which in the context of this CC shall include, Interface Sites until the
OTSUA Transfer Time) the following Site Responsibility Schedules shall be drawn up
using the relevant proforma attached or with such variations as may be agreed between
NGET and Users, but in the absence of agreement the relevant proforma attached will be
used. In addition, in the case of OTSDUW Plant and Apparatus, and in readiness for the
OTSUA Transfer Time, the User shall provide NGET with the necessary information such
that Site Responsibility Schedules in this form can be prepared by the Relevant
Transmission Licensees for the Transmission Interface Site:
(a) Schedule of HV Apparatus
(b) Schedule of Plant, LV/MV Apparatus, services and supplies;
(c) Schedule of telecommunications and measurements Apparatus.
Other than at Generating Unit, DC Converter, Power Park Module and Power Station
locations, the schedules referred to in (b) and (c) may be combined.
New Connection Sites
CC.A.1.1.2 In the case of a new Connection Site each Site Responsibility Schedule for a
Connection Site shall be prepared by NGET in consultation with relevant Users at least 2
weeks prior to the Completion Date (or, where the OTSUA is to become Operational prior
to the OTSUA Transfer Time, an alternative date) under the Bilateral Agreement and/or
Construction Agreement for that Connection Site (which may form part of a Complex).
In the case of a new Interface Site where the OTSUA is to become Operational prior to the
OTSUA Transfer Time each Site Responsibility Schedule for an Interface Site shall be
prepared by NGET in consultation with relevant Users at least 2 weeks prior to the
Completion Date under the Bilateral Agreement and/or Construction Agreement for that
Interface Site (which may form part of a Complex) (and references to and requirements
placed on Connection Site in this CC shall also be read as Interface Site where the
context requires and until the OTSUA Transfer Time). Each User shall, in accordance with
the timing requirements of the Bilateral Agreement and/or Construction Agreement ,
provide information to NGET to enable it to prepare the Site Responsibility Schedule.
Sub-division
CC.A.1.1.3 Each Site Responsibility Schedule will be subdivided to take account of any separate
Connection Sites on that Complex.
Scope
CC.A.1.1.4 Each Site Responsibility Schedule shall detail for each item of Plant and Apparatus:
(a) Plant/Apparatus ownership;
(b) Site Manager (Controller) (except in the case of Plant/Apparatus located in SPTs
Transmission Area);
(c) Safety issues comprising applicable Safety Rules and Control Person or other
responsible person (Safety Co-ordinator), or such other person who is responsible for
safety;
(d) Operations issues comprising applicable Operational Procedures and control
engineer;
(e) Responsibility to undertake statutory inspections, fault investigation and maintenance.
Issue 5 Revision 17 CC 29 June 2016
53 of 95
Each Connection Point shall be precisely shown.
Detail
CC.A.1.1.5 (a) In the case of Site Responsibility Schedules referred to in CC.A.1.1.1(b) and (c), with
the exception of Protection Apparatus and Intertrip Apparatus operation, it will be
sufficient to indicate the responsible User or Transmission Licensee, as the case may
be.
(b) In the case of the Site Responsibility Schedule referred to in CC.A.1.1.1(a) and for
Protection Apparatus and Intertrip Apparatus, the responsible management unit
must be shown in addition to the User or Transmission Licensee, as the case may be.
CC.A.1.1.6 The HV Apparatus Site Responsibility Schedule for each Connection Site must include
1
lines and cables emanating from or traversing the Connection Site.
Issue Details
CC.A.1.1.7 Every page of each Site Responsibility Schedule shall bear the date of issue and the issue
number.
Accuracy Confirmation
CC.A.1.1.8 When a Site Responsibility Schedule is prepared it shall be sent by NGET to the Users
involved for confirmation of its accuracy.
CC.A.1.1.9 The Site Responsibility Schedule shall then be signed on behalf of NGET by its
Responsible Manager (see CC.A.1.1.16) and on behalf of each User involved by its
Responsible Manager (see CC.A.1.1.16), by way of written confirmation of its accuracy.
For Connection Sites in Scotland or Offshore, the Site Responsibility Schedule will also
be signed on behalf of the Relevant Transmission Licensee by its Responsible Manager.
Distribution and Availability
CC.A.1.1.10 Once signed, two copies will be distributed by NGET, not less than two weeks prior to its
implementation date, to each User which is a party on the Site Responsibility Schedule,
accompanied by a note indicating the issue number and the date of implementation.
CC.A.1.1.11 NGET and Users must make the Site Responsibility Schedules readily available to
operational staff at the Complex and at the other relevant control points.
Alterations to Existing Site Responsibility Schedules
CC.A 1.1.12 Without prejudice to the provisions of CC.A.1.1.15 which deals with urgent changes, when a
User identified on a Site Responsibility Schedule becomes aware that an alteration is
necessary, it must inform NGET immediately and in any event 8 weeks prior to any change
taking effect (or as soon as possible after becoming aware of it, if less than 8 weeks remain
when the User becomes aware of the change). This will cover the commissioning of new
Plant and/or Apparatus at the Connection Site, whether requiring a revised Bilateral
Agreement or not, de-commissioning of Plant and/or Apparatus, and other changes which
affect the accuracy of the Site Responsibility Schedule.
CC.A 1.1.13 Where NGET has been informed of a change by a User, or itself proposes a change, it will
prepare a revised Site Responsibility Schedule by not less than six weeks prior to the
change taking effect (subject to it having been informed or knowing of the change eight
weeks prior to that time) and the procedure set out in CC.A.1.1.8 shall be followed with
regard to the revised Site Responsibility Schedule.
CC.A 1.1.14 The revised Site Responsibility Schedule shall then be signed in accordance with the
procedure set out in CC.A.1.1.9 and distributed in accordance with the procedure set out in
CC.A.1.1.10, accompanied by a note indicating where the alteration(s) has/have been made,
the new issue number and the date of implementation.

1
Details of circuits traversing the Connection Site are only needed from the date which is the earlier of the date when the Site
Responsibility Schedule is first updated and 15th October 2004. In Scotland or Offshore, from a date to be agreed between NGET
and the Relevant Transmission Licensee.
Issue 5 Revision 17 CC 29 June 2016
54 of 95
Urgent Changes
CC.A.1.1.15 When a User identified on a Site Responsibility Schedule, or NGET, as the case may be,
becomes aware that an alteration to the Site Responsibility Schedule is necessary
urgently to reflect, for example, an emergency situation which has arisen outside its control,
the User shall notify NGET, or NGET shall notify the User, as the case may be, immediately
and will discuss:
(a) what change is necessary to the Site Responsibility Schedule;
(b) whether the Site Responsibility Schedule is to be modified temporarily or
permanently;
(c) the distribution of the revised Site Responsibility Schedule.
NGET will prepare a revised Site Responsibility Schedule as soon as possible, and in any
event within seven days of it being informed of or knowing the necessary alteration. The
Site Responsibility Schedule will be confirmed by Users and signed on behalf of NGET
and Users (by the persons referred to in CC.A.1.1.9) as soon as possible after it has been
prepared and sent to Users for confirmation.
Responsible Managers
CC.A.1.1.16 Each User shall, prior to the Completion Date under each Bilateral Agreement and/or
Construction Agreement, supply to NGET a list of Managers who have been duly
authorised to sign Site Responsibility Schedules on behalf of the User and NGET shall,
prior to the Completion Date under each Bilateral Agreement and/or Construction
Agreement, supply to that User the name of its Responsible Manager and for Connection
Sites in Scotland or Offshore, the name of the Relevant Transmission Licensees
Responsible Manager and each shall supply to the other any changes to such list six
weeks before the change takes effect where the change is anticipated, and as soon as
possible after the change, where the change was not anticipated.
De-commissioning of Connection Sites
CC.A.1.1.17 Where a Connection Site is to be de-commissioned, whichever of NGET or the User who is
initiating the de-commissioning must contact the other to arrange for the Site Responsibility
Schedule to be amended at the relevant time.

Issue 5 Revision 17 CC 29 June 2016


55 of 95
PROFORMA FOR SITE RESPONSIBILITY SCHEDULE

AREA

COMPLEX: SCHEDULE:

CONNECTION SITE:

SAFETY OPERATIONS PARTY


RESPONSIBLE
FOR
UNDERTAKING
CONTROL OR STATUTORY
OTHER CONTROL OR INSPECTIONS,
RESPONSIBLE OTHER FAULT
ITEM OF PLANT PERSON RESPONSIBLE INVESTIGATION
PLANT/ APPARATUS SITE SAFETY (SAFETY CO- OPERATIONAL ENGINEER & REMARKS
APPARATUS OWNER MANAGER RULES ORDINATOR PROCEDURES MAINTENANCE

PAGE: ISSUE NO: DATE:

Issue 5 Revision 17 CC 29 June 2016


56 of 95
PROFORMA FOR SITE RESPONSIBILITY SCHEDULE

AREA

COMPLEX: SCHEDULE:

CONNECTION SITE:

SAFETY OPERATIONS PARTY


RESPONSIBLE
FOR
UNDERTAKING
CONTROL OR STATUTORY
OTHER CONTROL OR INSPECTIONS,
RESPONSIBLE OTHER FAULT
ITEM OF PLANT PERSON RESPONSIBLE INVESTIGATION
PLANT/ APPARATUS SITE SAFETY (SAFETY CO- OPERATIONAL ENGINEER & REMARKS
APPARATUS OWNER MANAGER RULES ORDINATOR PROCEDURES MAINTENANCE

NOTES:

SIGNED: NAME: COMPANY: DATE:

SIGNED: NAME: COMPANY: DATE:

SIGNED: NAME: COMPANY: DATE:

SIGNED: NAME: COMPANY: DATE:

PAGE: ISSUE NO: DATE:

Issue 5 Revision 17 CC 29 June 2016


57 of 95
Issue 5 Revision 17 CC 29 June 2016
58 of 95
Issue 5 Revision 17 CC 29 June 2016
59 of 95
APPENDIX 2 - OPERATION DIAGRAMS

PART 1A - PROCEDURES RELATING TO OPERATION DIAGRAMS

Issue 5 Revision 17 CC 29 June 2016


60 of 95
Issue 5 Revision 17 CC 29 June 2016
61 of 95
Issue 5 Revision 17 CC 29 June 2016
62 of 95
PART 1B - PROCEDURES RELATING TO GAS ZONE DIAGRAMS

Issue 5 Revision 17 CC 29 June 2016


63 of 95
PART 2 - NON-EXHAUSTIVE LIST OF APPARATUS
TO BE INCLUDED ON OPERATION DIAGRAMS

Basic Principles
(1) Where practicable, all the HV Apparatus on any Connection Site shall be shown on one
Operation Diagram. Provided the clarity of the diagram is not impaired, the layout shall
represent as closely as possible the geographical arrangement on the Connection Site.
(2) Where more than one Operation Diagram is unavoidable, duplication of identical
information on more than one Operation Diagram must be avoided.
(3) The Operation Diagram must show accurately the current status of the Apparatus e.g.
whether commissioned or decommissioned. Where decommissioned, the associated
switchbay will be labelled "spare bay".
(4) Provision will be made on the Operation Diagram for signifying approvals, together with
provision for details of revisions and dates.
(5) Operation Diagrams will be prepared in A4 format or such other format as may be agreed
with NGET.
(6) The Operation Diagram should normally be drawn single line. However, where appropriate,
detail which applies to individual phases shall be shown. For example, some HV Apparatus
is numbered individually per phase.

Apparatus To Be Shown On Operation Diagram


(1) Busbars
(2) Circuit Breakers
(3) Disconnector (Isolator) and Switch Disconnecters (Switching Isolators)
(4) Disconnectors (Isolators) - Automatic Facilities
(5) Bypass Facilities
(6) Earthing Switches
(7) Maintenance Earths
(8) Overhead Line Entries
(9) Overhead Line Traps
(10) Cable and Cable Sealing Ends
(11) Generating Unit
(12) Generator Transformers
(13) Generating Unit Transformers, Station Transformers, including the lower voltage circuit-
breakers.
(14) Synchronous Compensators
(15) Static Variable Compensators
(16) Capacitors (including Harmonic Filters)
(17) Series or Shunt Reactors (Referred to as "Inductors" at nuclear power station sites)
(18) Supergrid and Grid Transformers
(19) Tertiary Windings
(20) Earthing and Auxiliary Transformers
(21) Three Phase VT's

Issue 5 Revision 17 CC 29 June 2016


64 of 95
(22) Single Phase VT & Phase Identity
(23) High Accuracy VT and Phase Identity
(24) Surge Arrestors/Diverters
(25) Neutral Earthing Arrangements on HV Plant
(26) Fault Throwing Devices
(27) Quadrature Boosters
(28) Arc Suppression Coils
(29) Single Phase Transformers (BR) Neutral and Phase Connections
(30) Current Transformers (where separate plant items)
(31) Wall Bushings
(32) Combined VT/CT Units
(33) Shorting and Discharge Switches
(34) Thyristor
(35) Resistor with Inherent Non-Linear Variability, Voltage Dependent
(36) Gas Zone

Issue 5 Revision 17 CC 29 June 2016


65 of 95
APPENDIX 3 - MINIMUM FREQUENCY RESPONSE REQUIREMENT
PROFILE AND OPERATING RANGE FOR NEW POWER STATIONS AND
DC CONVERTER STATIONS
CC.A.3.1 Scope
The frequency response capability is defined in terms of Primary Response, Secondary
Response and High Frequency Response. This appendix defines the minimum frequency
response requirement profile for:
(a) each Onshore Generating Unit and/or CCGT Module which has a Completion Date
after 1 January 2001 in England and Wales and 1 April 2005 in Scotland and Offshore
Generating Unit in a Large Power Station,
(b) each DC Converter at a DC Converter Station which has a Completion Date on or
after 1 April 2005 or each Offshore DC Converter which is part of a Large Power
Station.
(c) each Onshore Power Park Module in England and Wales with a Completion Date on
or after 1 January 2006.
(d) each Onshore Power Park Module in operation in Scotland after 1 January 2006 with
a Completion Date after 1 April 2005 and in Power Stations with a Registered
Capacity of 50MW or more.
(e) each Offshore Power Park Module in a Large Power Station with a Registered
Capacity of 50MW or more.
For the avoidance of doubt, this appendix does not apply to:
(i) Generating Units and/or CCGT Modules which have a Completion Date before 1
January 2001 in England and Wales and before 1 April 2005 in Scotland,
(ii) DC Converters at a DC Converter Station which have a Completion Date before 1
April 2005.
(iii) Power Park Modules in England and Wales with a Completion Date before 1 January
2006.
(iv) Power Park Modules in operation in Scotland before 1 January 2006.
(v) Power Park Modules in Scotland with a Completion Date before 1 April 2005.
(vi) Power Park Modules in Power Stations with a Registered Capacity less than 50MW.
(vii) Small Power Stations or individually to Power Park Units; or.
(viii) an OTSDUW DC Converter where the Interface Point Capacity is less than 50MW.
OTSDUW Plant and Apparatus should facilitate the delivery of frequency response
services provided by Offshore Generating Units and Offshore Power Park Modules at
the Interface Point.
The functional definition provides appropriate performance criteria relating to the provision of
Frequency control by means of Frequency sensitive generation in addition to the other
requirements identified in CC.6.3.7.
In this Appendix 3 to the CC, for a CCGT Module or a Power Park Module with more than
one Generating Unit, the phrase Minimum Generation applies to the entire CCGT Module
or Power Park Module operating with all Generating Units Synchronised to the System.
The minimum Frequency response requirement profile is shown diagrammatically in Figure
CC.A.3.1. The capability profile specifies the minimum required levels of Primary
Response, Secondary Response and High Frequency Response throughout the normal
plant operating range. The definitions of these Frequency response capabilities are
illustrated diagrammatically in Figures CC.A.3.2 & CC.A.3.3.

Issue 5 Revision 17 CC 29 June 2016


66 of 95
CC.A.3.2 Plant Operating Range
The upper limit of the operating range is the Registered Capacity of the Generating Unit or
CCGT Module or DC Converter or Power Park Module.
The Minimum Generation level may be less than, but must not be more than, 65% of the
Registered Capacity. Each Generating Unit and/or CCGT Module and/or Power Park
Module and/or DC Converter must be capable of operating satisfactorily down to the
Designed Minimum Operating Level as dictated by System operating conditions, although
it will not be instructed to below its Minimum Generation level. If a Generating Unit or
CCGT Module or Power Park Module or DC Converter is operating below Minimum
Generation because of high System Frequency, it should recover adequately to its
Minimum Generation level as the System Frequency returns to Target Frequency so that
it can provide Primary and Secondary Response from Minimum Generation if the
System Frequency continues to fall. For the avoidance of doubt, under normal operating
conditions steady state operation below Minimum Generation is not expected. The
Designed Minimum Operating Level must not be more than 55% of Registered Capacity.
In the event of a Generating Unit or CCGT Module or Power Park Module or DC
Converter load rejecting down to no less than its Designed Minimum Operating Level it
should not trip as a result of automatic action as detailed in BC3.7. If the load rejection is to
a level less than the Designed Minimum Operating Level then it is accepted that the
condition might be so severe as to cause it to be disconnected from the System.
CC.A.3.3 Minimum Frequency Response Requirement Profile
Figure CC.A.3.1 shows the minimum Frequency response requirement profile
diagrammatically for a 0.5 Hz change in Frequency. The percentage response capabilities
and loading levels are defined on the basis of the Registered Capacity of the Generating
Unit or CCGT Module or Power Park Module or DC Converter. Each Generating Unit
and/or CCGT Module and/or Power Park Module and/or DC Converter must be capable of
operating in a manner to provide Frequency response at least to the solid boundaries
shown in the figure. If the Frequency response capability falls within the solid boundaries,
the Generating Unit or CCGT Module or Power Park Module or DC Converter is
providing response below the minimum requirement which is not acceptable. Nothing in this
appendix is intended to prevent a Generating Unit or CCGT Module or Power Park
Module or DC Converter from being designed to deliver a Frequency response in excess
of the identified minimum requirement.
The Frequency response delivered for Frequency deviations of less than 0.5 Hz should be
no less than a figure which is directly proportional to the minimum Frequency response
requirement for a Frequency deviation of 0.5 Hz. For example, if the Frequency deviation
is 0.2 Hz, the corresponding minimum Frequency response requirement is 40% of the level
shown in Figure CC.A.3.1. The Frequency response delivered for Frequency deviations of
more than 0.5 Hz should be no less than the response delivered for a Frequency deviation
of 0.5 Hz.
Each Generating Unit and/or CCGT Module and/or Power Park Module and/or DC
Converter must be capable of providing some response, in keeping with its specific
operational characteristics, when operating between 95% to 100% of Registered Capacity
as illustrated by the dotted lines in Figure CC.A.3.1.
At the Minimum Generation level, each Generating Unit and/or CCGT Module and/or
Power Park Module and/or DC Converter is required to provide high and low frequency
response depending on the System Frequency conditions. Where the Frequency is high,
the Active Power output is therefore expected to fall below the Minimum Generation level.
The Designed Minimum Operating Level is the output at which a Generating Unit and/or
CCGT Module and/or Power Park Module and/or DC Converter has no High Frequency
Response capability. It may be less than, but must not be more than, 55% of the
Registered Capacity. This implies that a Generating Unit or CCGT Module or Power
Park Module or DC Converter is not obliged to reduce its output to below this level unless
the Frequency is at or above 50.5 Hz (cf BC3.7).
Issue 5 Revision 17 CC 29 June 2016
67 of 95
CC.A.3.4 Testing Of Frequency Response Capability
The response capabilities shown diagrammatically in Figure CC.A.3.1 are measured by
taking the responses as obtained from some of the dynamic response tests specified by
NGET and carried out by Generators and DC Converter Station owners for compliance
purposes and to validate the content of Ancillary Services Agreements using an injection
of a Frequency change to the plant control system (i.e. governor and load controller). The
injected signal is a linear ramp from zero to 0.5 Hz Frequency change over a ten second
period, and is sustained at 0.5 Hz Frequency change thereafter, as illustrated
diagrammatically in figures CC.A.3.2 and CC.A.3.3. In the case of an Embedded Medium
Power Station not subject to a Bilateral Agreement or Embedded DC Converter Station
not subject to a Bilateral Agreement, NGET may require the Network Operator within
whose System the Embedded Medium Power Station or Embedded DC Converter
Station is situated, to ensure that the Embedded Person performs the dynamic response
tests reasonably required by NGET in order to demonstrate compliance within the relevant
requirements in the CC.
The Primary Response capability (P) of a Generating Unit or a CCGT Module or Power
Park Module or DC Converter is the minimum increase in Active Power output between 10
and 30 seconds after the start of the ramp injection as illustrated diagrammatically in Figure
CC.A.3.2. This increase in Active Power output should be released increasingly with time
over the period 0 to 10 seconds from the time of the start of the Frequency fall as illustrated
by the response from Figure CC.A.3.2.
The Secondary Response capability (S) of a Generating Unit or a CCGT Module or
Power Park Module or DC Converter is the minimum increase in Active Power output
between 30 seconds and 30 minutes after the start of the ramp injection as illustrated
diagrammatically in Figure CC.A.3.2.
The High Frequency Response capability (H) of a Generating Unit or a CCGT Module or
Power Park Module or DC Converter is the decrease in Active Power output provided 10
seconds after the start of the ramp injection and sustained thereafter as illustrated
diagrammatically in Figure CC.A.3.3. This reduction in Active Power output should be
released increasingly with time over the period 0 to 10 seconds from the time of the start of
the Frequency rise as illustrated by the response in Figure CC.A.3.2.
CC.A.3.5 Repeatability Of Response
When a Generating Unit or CCGT Module or Power Park Module or DC Converter has
responded to a significant Frequency disturbance, its response capability must be fully
restored as soon as technically possible. Full response capability should be restored no
later than 20 minutes after the initial change of System Frequency arising from the
Frequency disturbance.

Issue 5 Revision 17 CC 29 June 2016


68 of 95
Figure CC.A.3.1 - Minimum Frequency Response Requirement Profile for a 0.5 Hz frequency change from
Target Frequency

Issue 5 Revision 17 CC 29 June 2016


69 of 95
Figure CC.A.3.2 - Interpretation of Primary and Secondary Response Values

Figure CC.A.3.3 - Interpretation of High Frequency Response Values

Issue 5 Revision 17 CC 29 June 2016


70 of 95
APPENDIX 4 - FAULT RIDE THROUGH REQUIREMENTS

APPENDIX 4A - FAULT RIDE THROUGH REQUIREMENTS FOR ONSHORE


SYNCHRONOUS GENERATING UNITS, ONSHORE POWER PARK MODULES,
ONSHORE DC CONVERTERS OTSDUW PLANT AND APPARATUS AT THE
INTERFACE POINT, OFFSHORE SYNCHRONOUS GENERATING UNITS IN A LARGE
POWER STATION, OFFSHORE POWER PARK MODULES IN A LARGE POWER
STATION AND OFFSHORE DC CONVERTERS IN A LARGE POWER STATION WHICH
SELECT TO MEET THE FAULT RIDE THROUGH REQUIREMENTS AT THE
INTERFACE POINT

CC.A.4A.1 Scope
The fault ride through requirement is defined in CC.6.3.15.1 (a), (b) and CC.6.3.15.3. This
Appendix provides illustrations by way of examples only of CC.6.3.15.1 (a) (i) and further
background and illustrations to CC.6.3.15.1 (1b) (i) and CC.6.3.15.1 (2b) (i) and is not
intended to show all possible permutations.

CC.A.4A.2 Short Circuit Faults At Supergrid Voltage On The Onshore Transmission System Up To
140ms In Duration
For short circuit faults at Supergrid Voltage on the Onshore Transmission System (which
could be at an Interface Point) up to 140ms in duration, the fault ride through requirement is
defined in CC.6.3.15.1 (a) (i). Figures CC.A.4A.1 (a) and (b) illustrate two typical examples of
voltage recovery for short-circuit faults cleared within 140ms by two circuit breakers (a) and
three circuit breakers (b) respectively.

Figure CC.A.4A.1 (a)

Issue 5 Revision 17 CC 29 June 2016


71 of 95
Figure CC.A.4A.1 (b)

CC.A.4A.3 Supergrid Voltage Dips On The Onshore Transmission System Greater Than 140ms In
Duration
CC.A.4A3.1 Requirements applicable to Synchronous Generating Units subject to Supergrid Voltage
dips on the Onshore Transmission System greater than 140ms in duration.
For balanced Supergrid Voltage dips on the Onshore Transmission System having
durations greater than 140ms and up to 3 minutes, the fault ride through requirement is
defined in CC.6.3.15.1 (1b) and Figure 5a which is reproduced in this Appendix as Figure
CC.A.4A3.1 and termed the voltageduration profile.
This profile is not a voltage-time response curve that would be obtained by plotting the
transient voltage response at a point on the Onshore Transmission System (or User
System if located Onshore) to a disturbance. Rather, each point on the profile (i.e. the
heavy black line) represents a voltage level and an associated time duration which
connected Synchronous Generating Units must withstand or ride through.
Figures CC.A.4A3.2 (a), (b) and (c) illustrate the meaning of the voltage-duration profile for
voltage dips having durations greater than 140ms.

Issue 5 Revision 17 CC 29 June 2016


72 of 95
Figure CC.A.4A3.1

Figure CC.A.4A3.2 (a)

Issue 5 Revision 17 CC 29 June 2016


73 of 95
Figure CC.A.4A3.2 (b)

Figure CC.A.4A3.2 (c)

CC.A.4A3.2 Requirements applicable to Power Park Modules or OTSDUW Plant and Apparatus
subject to Supergrid Voltage dips on the Onshore Transmission System greater than
140ms in duration
For balanced Supergrid Voltage dips on the Onshore Transmission System (which could
be at an Interface Point) having durations greater than 140ms and up to 3 minutes the fault
ride through requirement is defined in CC.6.3.15.1 (2b) and Figure 5b which is reproduced in
this Appendix as Figure CC.A.4A3.3 and termed the voltageduration profile.

Issue 5 Revision 17 CC 29 June 2016


74 of 95
This profile is not a voltage-time response curve that would be obtained by plotting the
transient voltage response at a point on the Onshore Transmission System (or User
System if located Onshore) to a disturbance. Rather, each point on the profile (i.e. the
heavy black line) represents a voltage level and an associated time duration which
connected Power Park Modules or OTSDUW Plant and Apparatus must withstand or ride
through.
Figures CC.A.4A.4 (a), (b) and (c) illustrate the meaning of the voltage-duration profile for
voltage dips having durations greater than 140ms.

Figure CC.A.4A3.3

Figure CC.A.4A3.4 (a)

Issue 5 Revision 17 CC 29 June 2016


75 of 95
Figure CC.A.4A3.4 (b)

Figure CC.A.4A3.4 (c)

Issue 5 Revision 17 CC 29 June 2016


76 of 95
APPENDIX 4B - FAULT RIDE THROUGH REQUIREMENTS FOR OFFSHORE
GENERATING UNITS IN A LARGE POWER STATION, OFFSHORE POWER PARK
MODULES IN A LARGE POWER STATION AND OFFSHORE DC CONVERTERS IN A
LARGE POWER STATION WHICH SELECT TO MEET THE FAULT RIDE THROUGH
REQUIREMENTS AT THE LV SIDE OF THE OFFSHORE PLATFORM AS SPECIFIED
IN CC.6.3.15.2

CC.A.4B.1 Scope
The fault ride through requirement is defined in CC.6.3.15.2 (a), (b) and CC.6.3.15.3. This
Appendix provides illustrations by way of examples only of CC.6.3.15.2 (a) (i) and further
background and illustrations to CC.6.3.15.2 (1b) and CC.6.3.15.2 (2b) and is not intended to
show all possible permutations.
CC.A.4B.2 Voltage Dips On The LV Side Of The Offshore Platform Up To 140ms In Duration
For voltage dips on the LV Side of the Offshore Platform which last up to 140ms in
duration, the fault ride through requirement is defined in CC.6.3.15.2 (a) (i). This includes
Figure 6 which is reproduced here in Figure CC.A.4B.1. The purpose of this requirement is
to translate the conditions caused by a balanced or unbalanced fault which occurs on the
Onshore Transmission System (which may include the Interface Point) at the LV Side of
the Offshore Platform.

V/VN is the ratio of the voltage at the LV side of the Offshore Platform to the nominal
voltage of the LV side of the Offshore Platform.
Figure CC.A.4B.1

Figures CC.A.4B.2 (a) and CC.A.4B.2 (b) illustrate two typical examples of the voltage
recovery seen at the LV Side of the Offshore Platform for a short circuit fault cleared within
140ms by (a) two circuit breakers and (b) three circuit breakers on the Onshore
Transmission System.

Issue 5 Revision 17 CC 29 June 2016


77 of 95
Figure CC.A.4B.2 (a)

Figure CC.A.4B.2 (b)

CCA.4B.3 Voltage Dips Which Occur On The LV Side Of The Offshore Platform Greater Than 140ms
In Duration
CC.A.4B.3.1 Requirements applicable to Offshore Synchronous Generating Units subject to voltage
dips which occur on the LV Side of the Offshore Platform greater than 140ms in duration.
In addition to CC.A.4B.2 the fault ride through requirements applicable to Offshore
Synchronous Generating Units during balanced voltage dips which occur at the LV Side
of the Offshore Platform and having durations greater than 140ms and up to 3 minutes are
defined in CC.6.3.15.2 (1b) and Figure 7a which is reproduced in this Appendix as Figure
CC.A.4B3.1 and termed the voltageduration profile.
This profile is not a voltage-time response curve that would be obtained by plotting the
transient voltage response at the LV Side of the Offshore Platform to a disturbance.
Rather, each point on the profile (i.e. the heavy black line) represents a voltage level and an
associated time duration which connected Offshore Synchronous Generating Units must
withstand or ride through.

Issue 5 Revision 17 CC 29 June 2016


78 of 95
Figures CC.A.4B3.2 (a), (b) and (c) illustrate the meaning of the voltage-duration profile for
voltage dips having durations greater than 140ms.

Figure CC.A.4B3.1

Figure CC.A.4B3.2 (a)

Issue 5 Revision 17 CC 29 June 2016


79 of 95
Figure CC.A.4B3.2 (b)

Figure CC.A.4B3.2 (c)

CC.A.4B.3.2 Requirements applicable to Offshore Power Park Modules subject to Voltage Dips Which
Occur On The LV Side Of The Offshore Platform Greater Than 140ms in Duration.
In addition to CCA.4B.2 the fault ride through requirements applicable for Offshore Power
Park Modules during balanced voltage dips which occur at the LV Side of the Offshore
Platform and have durations greater than 140ms and up to 3 minutes are defined in
CC.6.3.15.2 (2b) (i) and Figure 7b which is reproduced in this Appendix as Figure CC.A.4B.4
and termed the voltageduration profile.

Issue 5 Revision 17 CC 29 June 2016


80 of 95
This profile is not a voltage-time response curve that would be obtained by plotting the
transient voltage response at the LV Side of the Offshore Platform to a disturbance.
Rather, each point on the profile (i.e. the heavy black line) represents a voltage level and an
associated time duration which connected Offshore Power Park Modules must withstand
or ride through.
Figures CC.A.4B.5 (a), (b) and (c) illustrate the meaning of the voltage-duration profile for
voltage dips having durations greater than 140ms.

Figure CC.A.4B.4

Figure CC.A.4B.5 (a)

Issue 5 Revision 17 CC 29 June 2016


81 of 95
Figure CC.A.4B.5(b)

Figure CC.A.4B.5(c)

Issue 5 Revision 17 CC 29 June 2016


82 of 95
APPENDIX 5 - TECHNICAL REQUIREMENTS
LOW FREQUENCY RELAYS FOR THE AUTOMATIC
DISCONNECTION OF SUPPLIES AT LOW FREQUENCY
CC.A.5.1 Low Frequency Relays
CC.A.5.1.1 The Low Frequency Relays to be used shall have a setting range of 47.0 to 50Hz and be
suitable for operation from a nominal AC input of 63.5, 110 or 240V. The following general
parameters specify the requirements of approved Low Frequency Relays for automatic
st
installations installed and commissioned after 1 April 2007 and provide an indication,
without prejudice to the provisions that may be included in a Bilateral Agreement, for those
st
installed and commissioned before 1 April 2007:

(a) Frequency settings: 47-50Hz in steps of 0.05Hz or better, preferably 0.01Hz;

(b) Operating time: Relay operating time shall not be more than 150 ms;

(c) Voltage lock-out: Selectable within a range of 55 to 90% of nominal voltage;

(d) Facility stages: One or two stages of Frequency operation;

(e) Output contacts: Two output contacts per stage to be capable of repetitively
making and breaking for 1000 operations:

(f) Accuracy: 0.01 Hz maximum error under reference environmental and


system voltage conditions.
0.05 Hz maximum error at 8% of total harmonic distortion
Electromagnetic Compatibility Level.

CC.A.5.2 Low Frequency Relay Voltage Supplies


CC.A.5.2.1 It is essential that the voltage supply to the Low Frequency Relays shall be derived from
the primary System at the supply point concerned so that the Frequency of the Low
Frequency Relays input voltage is the same as that of the primary System. This requires
either:
(a) the use of a secure supply obtained from voltage transformers directly associated with
the grid transformer(s) concerned, the supply being obtained where necessary via a
suitable automatic voltage selection scheme; or
(b) the use of the substation 240V phase-to-neutral selected auxiliary supply, provided that
this supply is always derived at the supply point concerned and is never derived from a
standby supply Generating Unit or from another part of the User System.
CC.A.5.3 Scheme Requirements
CC.A.5.3.1 The tripping facility should be engineered in accordance with the following reliability
considerations:
(a) Dependability
Failure to trip at any one particular Demand shedding point would not harm the overall
operation of the scheme. However, many failures would have the effect of reducing the
amount of Demand under low Frequency control. An overall reasonable minimum
requirement for the dependability of the Demand shedding scheme is 96%, i.e. the
average probability of failure of each Demand shedding point should be less than 4%.
Thus the Demand under low Frequency control will not be reduced by more than 4%
due to relay failure.
(b) Outages
Low Frequency Demand shedding schemes will be engineered such that the amount
of Demand under control is as specified in Table CC.A.5.5.1a and is not reduced
unacceptably during equipment outage or maintenance conditions.
Issue 5 Revision 17 CC 29 June 2016
83 of 95
CC.A.5.3.2 The total operating time of the scheme, including circuit breakers operating time, shall where
reasonably practicable, be less than 200 ms. For the avoidance of doubt, the replacement of
plant installed prior to October 2009 will not be required in order to achieve lower total
scheme operating times.
CC.A.5.4 Low Frequency Relay Testing
st
CC.A.5.4.1 Low Frequency Relays installed and commissioned after 1 January 2007 shall be type
tested in accordance with and comply with the functional test requirements for Frequency
Protection contained in Energy Networks Association Technical Specification 48-6-5 Issue 1
dated 2005 ENA Protection Assessment Functional Test Requirements Voltage and
Frequency Protection.
st
For the avoidance of doubt, Low Frequency Relays installed and commissioned before 1
January 2007 shall comply with the version of CC.A.5.1.1 applicable at the time such Low
Frequency Relays were commissioned.
CC.A.5.5 Scheme Settings
CC.A.5.5.1 Table CC.A.5.5.1a shows, for each Transmission Area, the percentage of Demand (based
on Annual ACS Conditions) at the time of forecast National Electricity Transmission
System peak Demand that each Network Operator whose System is connected to the
Onshore Transmission System within such Transmission Area shall disconnect by Low
Frequency Relays at a range of frequencies. Where a Network Operators System is
connected to the National Electricity Transmission System in more than one
Transmission Area, the settings for the Transmission Area in which the majority of the
Demand is connected shall apply.

Frequency Hz % Demand disconnection for each Network Operator in


Transmission Area

NGET SPT SHETL

48.8 5

48.75 5

48.7 10

48.6 7.5 10

48.5 7.5 10

48.4 7.5 10 10

48.2 7.5 10 10

48.0 5 10 10

47.8 5

Total % Demand 60 40 40
Table CC.A.5.5.1a

Note the percentages in table CC.A.5.5.1a are cumulative such that, for example, should
the frequency fall to 48.6 Hz in the NGET Transmission Area, 27.5% of the total Demand
connected to the National Electricity Transmission System in the NGET Transmission
Area shall be disconnected by the action of Low Frequency Relays.
The percentage Demand at each stage shall be allocated as far as reasonably practicable.
The cumulative total percentage Demand is a minimum.

Issue 5 Revision 17 CC 29 June 2016


84 of 95
APPENDIX 6 - PERFORMANCE REQUIREMENTS FOR CONTINUOUSLY
ACTING AUTOMATIC EXCITATION CONTROL SYSTEMS FOR
ONSHORE SYNCHRONOUS GENERATING UNITS
CC.A.6.1 Scope
CC.A.6.1.1 This Appendix sets out the performance requirements of continuously acting automatic
excitation control systems for Onshore Synchronous Generating Units that must be
complied with by the User. This Appendix does not limit any site specific requirements that
may be included in a Bilateral Agreement where in NGET's reasonable opinion these
facilities are necessary for system reasons.
CC.A.6.1.2 Where the requirements may vary the likely range of variation is given in this Appendix. It
may be necessary to specify values outside this range where NGET identifies a system
need, and notwithstanding anything to the contrary NGET may specify in the Bilateral
Agreement values outside of the ranges provided in this Appendix 6. The most common
variations are in the on-load excitation ceiling voltage requirements and the response time
required of the Exciter. Actual values will be included in the Bilateral Agreement.
CC.A.6.1.3 Should a Generator anticipate making a change to the excitation control system it shall
notify NGET under the Planning Code (PC.A.1.2(b) and (c)) as soon as the Generator
anticipates making the change. The change may require a revision to the Bilateral
Agreement.
CC.A.6.2 Requirements
CC.A.6.2.1 The Excitation System of an Onshore Synchronous Generating Unit shall include an
excitation source (Exciter), a Power System Stabiliser and a continuously acting
Automatic Voltage Regulator (AVR) and shall meet the following functional specification.
CC.A.6.2.2 In respect of Onshore Synchronous Generating Units with a Completion Date on or after
1 January 2009, and Onshore Synchronous Generating Units with a Completion Date
before 1 January 2009 subject to a Modification to the excitation control facilities where the
Bilateral Agreement does not specify otherwise, the continuously acting automatic
excitation control system shall include a Power System Stabiliser (PSS) as a means of
supplementary control. The functional specification of the Power System Stabiliser is
included in CC.A.6.2.5.
CC.A.6.2.3 Steady State Voltage Control
CC.A.6.2.3.1 An accurate steady state control of the Onshore Generating Unit pre-set terminal voltage is
required. As a measure of the accuracy of the steady-state voltage control, the Automatic
Voltage Regulator shall have static zero frequency gain, sufficient to limit the change in
terminal voltage to a drop not exceeding 0.5% of rated terminal voltage, when the Onshore
Generating Unit output is gradually changed from zero to rated MVA output at rated
voltage, Active Power and Frequency.
CC.A.6.2.4 Transient Voltage Control
CC.A.6.2.4.1 For a step change from 90% to 100% of the nominal Onshore Generating Unit terminal
voltage, with the Onshore Generating Unit on open circuit, the Excitation System
response shall have a damped oscillatory characteristic. For this characteristic, the time for
the Onshore Generating Unit terminal voltage to first reach 100% shall be less than 0.6
seconds. Also, the time to settle within 5% of the voltage change shall be less than 3
seconds.

Issue 5 Revision 17 CC 29 June 2016


85 of 95
CC.A.6.2.4.2 To ensure that adequate synchronising power is maintained, when the Onshore Generating
Unit is subjected to a large voltage disturbance, the Exciter whose output is varied by the
Automatic Voltage Regulator shall be capable of providing its achievable upper and lower
limit ceiling voltages to the Onshore Generating Unit field in a time not exceeding that
specified in the Bilateral Agreement. This will normally be not less than 50 ms and not
greater than 300 ms. The achievable upper and lower limit ceiling voltages may be
dependent on the voltage disturbance.
CC.A.6.2.4.3 The Exciter shall be capable of attaining an Excitation System On Load Positive Ceiling
Voltage of not less than a value specified in the Bilateral Agreement that will be:
not less than 2 per unit (pu)
normally not greater than 3 pu
exceptionally up to 4 pu
of Rated Field Voltage when responding to a sudden drop in voltage of 10 percent or more
at the Onshore Generating Unit terminals. NGET may specify a value outside the above
limits where NGET identifies a system need.
CC.A.6.2.4.4 If a static type Exciter is employed:
(i) the field voltage should be capable of attaining a negative ceiling level specified in the
Bilateral Agreement after the removal of the step disturbance of CC.A.6.2.4.3. The
specified value will be 80% of the value specified in CC.A.6.2.4.3. NGET may specify a
value outside the above limits where NGET identifies a system need.
(ii) the Exciter must be capable of maintaining free firing when the Onshore Generating
Unit terminal voltage is depressed to a level which may be between 20% to 30% of
rated terminal voltage
(iii) the Exciter shall be capable of attaining a positive ceiling voltage not less than 80% of
the Excitation System On Load Positive Ceiling Voltage upon recovery of the
Onshore Generating Unit terminal voltage to 80% of rated terminal voltage following
fault clearance. NGET may specify a value outside the above limits where NGET
identifies a system need.
(iv) The requirement to provide a separate power source for the Exciter will be specified in
the Bilateral Agreement if NGET identifies a Transmission System need.
CC.A.6.2.5 Power Oscillations Damping Control
CC.A.6.2.5.1 To allow the Onshore Generating Unit to maintain second and subsequent swing stability
and also to ensure an adequate level of low frequency electrical damping power, the
Automatic Voltage Regulator shall include a Power System Stabiliser as a means of
supplementary control.
CC.A.6.2.5.2 Whatever supplementary control signal is employed, it shall be of the type which operates
into the Automatic Voltage Regulator to cause the field voltage to act in a manner which
results in the damping power being improved while maintaining adequate synchronising
power.
CC.A.6.2.5.3 The arrangements for the supplementary control signal shall ensure that the Power System
Stabiliser output signal relates only to changes in the supplementary control signal and not
the steady state level of the signal. For example, if generator electrical power output is
chosen as a supplementary control signal then the Power System Stabiliser output
should relate only to changes in generator electrical power output and not the steady state
level of power output. Additionally the Power System Stabiliser should not react to
mechanical power changes in isolation for example during rapid changes in steady state
load or when providing frequency response.
CC.A.6.2.5.4 The output signal from the Power System Stabiliser shall be limited to not more than 10%
of the Onshore Generating Unit terminal voltage signal at the Automatic Voltage
Regulator input. The gain of the Power System Stabiliser shall be such that an increase in
the gain by a factor of 3 shall not cause instability.
Issue 5 Revision 17 CC 29 June 2016
86 of 95
CC.A.6.2.5.5 The Power System Stabiliser shall include elements that limit the bandwidth of the output
signal. The bandwidth limiting must ensure that the highest frequency of response cannot
excite torsional oscillations on other plant connected to the network. A bandwidth of 0-5Hz
would be judged to be acceptable for this application.
CC.A.6.2.5.6 The Generator will agree Power System Stabiliser settings with NGET prior to the on-load
commissioning detailed in BC2.11.2(d). To allow assessment of the performance before on-
load commissioning the Generator will provide to NGET a report covering the areas
specified in CP.A.3.2.1.
CC.A.6.2.5.7 The Power System Stabiliser must be active within the Excitation System at all times
when Synchronised including when the Under Excitation Limiter or Over Excitation
Limiter are active. When operating at low load when Synchronising or De-Synchronising
an Onshore Generating Unit, the Power System Stabiliser may be out of service.
CC.A.6.2.5.8 Where a Power System Stabiliser is fitted to a Pumped Storage Unit it must function
when the Pumped Storage Unit is in both generating and pumping modes.
CC.A.6.2.6 Overall Excitation System Control Characteristics
CC.A.6.2.6.1 The overall Excitation System shall include elements that limit the bandwidth of the output
signal. The bandwidth limiting must be consistent with the speed of response requirements
and ensure that the highest frequency of response cannot excite torsional oscillations on
other plant connected to the network. A bandwidth of 0-5 Hz will be judged to be acceptable
for this application.
CC.A.6.2.6.2 The response of the Automatic Voltage Regulator combined with the Power System
Stabiliser shall be demonstrated by injecting similar step signal disturbances into the
Automatic Voltage Regulator reference as detailed in OC5A.2.2 and OC5.A.2.4. The
Automatic Voltage Regulator shall include a facility to allow step injections into the
Automatic Voltage Regulator voltage reference, with the Onshore Generating Unit
operating at points specified by NGET (up to rated MVA output). The damping shall be
judged to be adequate if the corresponding Active Power response to the disturbances
decays within two cycles of oscillation.
CC.A.6.2.6.3 A facility to inject a band limited random noise signal into the Automatic Voltage Regulator
voltage reference shall be provided for demonstrating the frequency domain response of the
Power System Stabiliser. The tuning of the Power System Stabiliser shall be judged to be
adequate if the corresponding Active Power response shows improved damping with the
Power System Stabiliser in combination with the Automatic Voltage Regulator compared
with the Automatic Voltage Regulator alone over the frequency range 0.3Hz 2Hz.
CC.A.6.2.7 Under-Excitation Limiters
CC.A.6.2.7.1 The security of the power system shall also be safeguarded by means of MVAr Under
Excitation Limiters fitted to the generator Excitation System. The Under Excitation
Limiter shall prevent the Automatic Voltage Regulator reducing the generator excitation to
a level which would endanger synchronous stability. The Under Excitation Limiter shall
operate when the excitation system is providing automatic control. The Under Excitation
Limiter shall respond to changes in the Active Power (MW) and the Reactive Power
(MVAr), and to the square of the generator voltage in such a direction that an increase in
voltage will permit an increase in leading MVAr. The characteristic of the Under Excitation
Limiter shall be substantially linear from no-load to the maximum Active Power output of
the Onshore Generating Unit at any setting and shall be readily adjustable.

Issue 5 Revision 17 CC 29 June 2016


87 of 95
CC.A.6.2.7.2 The performance of the Under Excitation Limiter shall be independent of the rate of
change of the Onshore Generating Unit load and shall be demonstrated by testing as
detailed in OC5.A.2.5. The resulting maximum overshoot in response to a step injection
which operates the Under Excitation Limiter shall not exceed 4% of the Onshore
Generating Unit rated MVA. The operating point of the Onshore Generating Unit shall be
returned to a steady state value at the limit line and the final settling time shall not be greater
than 5 seconds. When the step change in Automatic Voltage Regulator reference voltage
is reversed, the field voltage should begin to respond without any delay and should not be
held down by the Under Excitation Limiter. Operation into or out of the preset limit levels
shall ensure that any resultant oscillations are damped so that the disturbance is within 0.5%
of the Onshore Generating Unit MVA rating within a period of 5 seconds.
CC.A.6.2.7.3 The Generator shall also make provision to prevent the reduction of the Onshore
Generating Unit excitation to a level which would endanger synchronous stability when the
Excitation System is under manual control.
CC.A.6.2.8 Over-Excitation Limiters
CC.A.6.2.8.1 The settings of the Over-Excitation Limiter, where it exists, shall ensure that the generator
excitation is not limited to less than the maximum value that can be achieved whilst ensuring
the Onshore Generating Unit is operating within its design limits. If the generator excitation
is reduced following a period of operation at a high level, the rate of reduction shall not
exceed that required to remain within any time dependent operating characteristics of the
Onshore Generating Unit.
CC.A.6.2.8.2 The performance of the Over-Excitation Limiter, where it exists, shall be demonstrated by
testing as described in OC5.A.2.6. Any operation beyond the Over-Excitation Limit shall be
controlled by the Over-Excitation Limiter without the operation of any Protection that could
trip the Onshore Generating Unit.

CC.A.6.2.8.3 The Generator shall also make provision to prevent any over-excitation restriction of the
generator when the Excitation System is under manual control, other than that necessary
to ensure the Onshore Generating Unit is operating within its design limits.

Issue 5 Revision 17 CC 29 June 2016


88 of 95
APPENDIX 7 - PERFORMANCE REQUIREMENTS FOR CONTINUOUSLY
ACTING AUTOMATIC VOLTAGE CONTROL SYSTEMS FOR ONSHORE
NON-SYNCHRONOUS GENERATING UNITS, ONSHORE DC
CONVERTERS, ONSHORE POWER PARK MODULES AND OTSDUW
PLANT AND APPARATUS AT THE INTERFACE POINT

CC.A.7.1 Scope
CC.A.7.1.1 This Appendix sets out the performance requirements of continuously acting automatic
voltage control systems for Onshore Non-Synchronous Generating Units, Onshore DC
Converters, Onshore Power Park Modules and OTSDUW Plant and Apparatus at the
Interface Point that must be complied with by the User. This Appendix does not limit any
site specific requirements that may be included in a Bilateral Agreement where in NGET's
reasonable opinion these facilities are necessary for system reasons.
CC.A.7.1.2 Proposals by Generators to make a change to the voltage control systems are required to
be notified to NGET under the Planning Code (PC.A.1.2(b) and (c)) as soon as the
Generator anticipates making the change. The change may require a revision to the
Bilateral Agreement.
CC.A.7.2 Requirements
CC.A.7.2.1 NGET requires that the continuously acting automatic voltage control system for the
Onshore Non-Synchronous Generating Unit, Onshore DC Converter or Onshore Power
Park Module or OTSDUW Plant and Apparatus shall meet the following functional
performance specification. If a Network Operator has confirmed to NGET that its network to
which an Embedded Onshore Non-Synchronous Generating Unit, Onshore DC
Converter, Onshore Power Park Module or OTSDUW Plant and Apparatus is connected
is restricted such that the full reactive range under the steady state voltage control
requirements (CC.A.7.2.2) cannot be utilised, NGET may specify in the Bilateral Agreement
alternative limits to the steady state voltage control range that reflect these restrictions.
Where the Network Operator subsequently notifies NGET that such restriction has been
removed, NGET may propose a Modification to the Bilateral Agreement (in accordance
with the CUSC contract) to remove the alternative limits such that the continuously acting
automatic voltage control system meets the following functional performance specification.
All other requirements of the voltage control system will remain as in this Appendix.
CC.A.7.2.2 Steady State Voltage Control
CC.A.7.2.2.1 The Onshore Non-Synchronous Generating Unit, Onshore DC Converter, Onshore
Power Park Module or OTSDUW Plant and Apparatus shall provide continuous steady
state control of the voltage at the Onshore Grid Entry Point (or Onshore User System
Entry Point if Embedded) (or the Interface Point in the case of OTSDUW Plant and
Apparatus) with a Setpoint Voltage and Slope characteristic as illustrated in Figure
CC.A.7.2.2a. It should be noted that where the Reactive Power capability requirement of a
directly connected Onshore Non-Synchronous Generating Unit, Onshore DC Converter,
Onshore Power Park Module in Scotland, or OTSDUW Plant and Apparatus in Scotland
as specified in CC.6.3.2 (c), is not at the Onshore Grid Entry Point or Interface Point, the
values of Qmin and Qmax shown in this figure will be as modified by the 33/132kV or
33/275kV or 33/400kV transformer.

Issue 5 Revision 17 CC 29 June 2016


89 of 95
Figure CC.A.7.2.2a

CC.A.7.2.2.2 The continuously acting automatic control system shall be capable of operating to a
Setpoint Voltage between 95% and 105% with a resolution of 0.25% of the nominal voltage.
For the avoidance of doubt values of 95%, 95.25%, 95.5% may be specified, but not
intermediate values. The initial Setpoint Voltage will be 100%. The tolerance within which
this Setpoint Voltage shall be achieved is specified in BC2.A.2.6. For the avoidance of
doubt, with a tolerance of 0.25% and a Setpoint Voltage of 100%, the achieved value shall
be between 99.75% and 100.25%. NGET may request the Generator to implement an
alternative Setpoint Voltage within the range of 95% to 105%. For Embedded Generators
the Setpoint Voltage will be discussed between NGET and the relevant Network Operator
and will be specified to ensure consistency with CC.6.3.4.
CC.A.7.2.2.3 The Slope characteristic of the continuously acting automatic control system shall be
adjustable over the range 2% to 7% (with a resolution of 0.5%). For the avoidance of doubt
values of 2%, 2.5%, 3% may be specified, but not intermediate values. The initial Slope
setting will be 4%. The tolerance within which this Slope shall be achieved is specified in
BC2.A.2.6. For the avoidance of doubt, with a tolerance of 0.5% and a Slope setting of 4%,
the achieved value shall be between 3.5% and 4.5%. NGET may request the Generator to
implement an alternative slope setting within the range of 2% to 7%. For Embedded
Generators the Slope setting will be discussed between NGET and the relevant Network
Operator and will be specified to ensure consistency with CC.6.3.4.

Issue 5 Revision 17 CC 29 June 2016


90 of 95
Figure CC.A.7.2.2b

Figure CC.A.7.2.2c

Issue 5 Revision 17 CC 29 June 2016


91 of 95
CC.A.7.2.2.4 Figure CC.A.7.2.2b shows the required envelope of operation for Onshore Non-
Synchronous Generating Units, Onshore DC Converters, OTSDUW Plant and
Apparatus and Onshore Power Park Modules except for those Embedded at 33kV and
below or directly connected to the National Electricity Transmission System at 33kV and
below. Figure CC.A.7.2.2c shows the required envelope of operation for Onshore Non-
Synchronous Generating Units, Onshore DC Converters and Onshore Power Park
Modules Embedded at 33kV and below or directly connected to the National Electricity
Transmission System at 33kV and below. Where the Reactive Power capability
requirement of a directly connected Onshore Non-Synchronous Generating Unit,
Onshore DC Converter, OTSDUW Plant and Apparatus or Onshore Power Park Module
in Scotland, as specified in CC.6.3.2 (c), is not at the Onshore Grid Entry Point or
Interface Point in the case of OTSDUW Plant and Apparatus, the values of Qmin and
Qmax shown in this figure will be as modified by the 33/132kV or 33/275kV or 33/400kV
transformer. The enclosed area within points ABCDEFGH is the required capability range
within which the Slope and Setpoint Voltage can be changed.
CC.A.7.2.2.5 Should the operating point of the Onshore Non-Synchronous Generating Unit, Onshore
DC Converter, OTSDUW Plant and Apparatus or Onshore Power Park Module deviate
so that it is no longer a point on the operating characteristic (figure CC.A.7.2.2a) defined by
the target Setpoint Voltage and Slope, the continuously acting automatic voltage control
system shall act progressively to return the value to a point on the required characteristic
within 5 seconds.
CC.A.7.2.2.6 Should the Reactive Power output of the Onshore Non-Synchronous Generating Unit,
Onshore DC Converter, OTSDUW Plant and Apparatus or Onshore Power Park Module
reach its maximum lagging limit at a Onshore Grid Entry Point voltage (or Onshore User
System Entry Point voltage if Embedded or Interface Point in the case of OTSDUW Plant
and Apparatus) above 95%, the Onshore Non-Synchronous Generating Unit, Onshore
DC Converter, OTSDUW Plant and Apparatus or Onshore Power Park Module shall
maintain maximum lagging Reactive Power output for voltage reductions down to 95%. This
requirement is indicated by the line EF in figures CC.A.7.2.2b and CC.A.7.2.2c. Should the
Reactive Power output of the Onshore Non-Synchronous Generating Unit, Onshore DC
Converter, OTSDUW Plant and Apparatus or Onshore Power Park Module reach its
maximum leading limit at a Onshore Grid Entry Point voltage (or Onshore User System
Entry Point voltage if Embedded or Interface Point in the case of OTSDUW Plant and
Apparatus) below 105%, the Onshore Non-Synchronous Generating Unit, Onshore DC
Converter, OTSDUW Plant and Apparatus or Onshore Power Park Module shall
maintain maximum leading Reactive Power output for voltage increases up to 105%. This
requirement is indicated by the line AB in figures CC.A.7.2.2b and CC.A.7.2.2c.

Issue 5 Revision 17 CC 29 June 2016


92 of 95
CC.A.7.2.2.7 For Onshore Grid Entry Point voltages (or Onshore User System Entry Point voltages if
Embedded or Interface Point voltages) below 95%, the lagging Reactive Power capability
of the Onshore Non-Synchronous Generating Unit, Onshore DC Converter, OTSDUW
Plant and Apparatus or Onshore Power Park Module should be that which results from
the supply of maximum lagging reactive current whilst ensuring the current remains within
design operating limits. An example of the capability is shown by the line DE in figures
CC.A.7.2.2b and CC.A.7.2.2c. For Onshore Grid Entry Point voltages (or User System
Entry Point voltages if Embedded or Interface Point voltages) above 105%, the leading
Reactive Power capability of the Onshore Non-Synchronous Generating Unit, Onshore
DC Converter, OTSDUW Plant and Apparatus or Onshore Power Park Module should
be that which results from the supply of maximum leading reactive current whilst ensuring
the current remains within design operating limits. An example of the capability is shown by
the line AH in figures CC.A.7.2.2b and CC.A.7.2.2c. Should the Reactive Power output of
the Onshore Non-Synchronous Generating Unit, Onshore DC Converter, OTSDUW
Plant and Apparatus or Onshore Power Park Module reach its maximum lagging limit at
an Onshore Grid Entry Point voltage (or Onshore User System Entry Point voltage if
Embedded or Interface Point in the case of OTSDUW Plant and Apparatus) below 95%,
the Onshore Non-Synchronous Generating Unit, Onshore DC Converter or Onshore
Power Park Module shall maintain maximum lagging reactive current output for further
voltage decreases. Should the Reactive Power output of the Onshore Non-Synchronous
Generating Unit, Onshore DC Converter, OTSDUW Plant and Apparatus or Onshore
Power Park Module reach its maximum leading limit at a Onshore Grid Entry Point
voltage (or User System Entry Point voltage if Embedded or Interface Point voltage in
the case of an OTSDUW Plant and Apparatus) above 105%, the Onshore Non-
Synchronous Generating Unit, Onshore DC Converter, OTSDUW Plant and Apparatus
or Onshore Power Park Module shall maintain maximum leading reactive current output for
further voltage increases.
CC.A.7.2.2.8 All OTSDUW Plant and Apparatus must be capable of enabling Users undertaking
OTSDUW to comply with an instruction received from NGET relating to a variation of the
Setpoint Voltage at the Interface Point within 2 minutes of such instruction being received.
CC.A.7.2.2.9 For OTSDUW Plant and Apparatus connected to a Network Operators System where
the Network Operator has confirmed to NGET that its System is restricted in accordance
with CC.A.7.2.1, clause CC.A.7.2.2.8 will not apply unless NGET can reasonably
demonstrate that the magnitude of the available change in Reactive Power has a significant
effect on voltage levels on the Onshore National Electricity Transmission System.
CC.A.7.2.3 Transient Voltage Control
CC.A.7.2.3.1 For an on-load step change in Onshore Grid Entry Point or Onshore User System Entry
Point voltage, or in the case of OTSDUW Plant and Apparatus an on-load step change in
Transmission Interface Point voltage, the continuously acting automatic control system
shall respond according to the following minimum criteria:
(i) the Reactive Power output response of the Onshore Non-Synchronous Generating
Unit, Onshore DC Converter, OTSDUW Plant and Apparatus or Onshore Power
Park Module shall commence within 0.2 seconds of the application of the step. It shall
progress linearly although variations from a linear characteristic shall be acceptable
provided that the MVAr seconds delivered at any time up to 1 second are at least those
that would result from the response shown in figure CC.A.7.2.3.1a.
(ii) the response shall be such that 90% of the change in the Reactive Power output of the
Onshore Non-Synchronous Generating Unit, Onshore DC Converter, OTSDUW
Plant and Apparatus or Onshore Power Park Module, will be achieved within
1 second, where the step is sufficiently large to require a change in the steady
state Reactive Power output from zero to its maximum leading value or
maximum lagging value, as required by CC.6.3.2 (or, if appropriate,
CC.A.7.2.2.6 or CC.A.7.2.2.7); and

Issue 5 Revision 17 CC 29 June 2016


93 of 95
2 seconds, for Plant and Apparatus installed on or after 1 December 2017,
where the step is sufficiently large to require a change in the steady state
Reactive Power output from its maximum leading value to its maximum lagging
value or vice versa.

(iii) the magnitude of the Reactive Power output response produced within 1 second shall
vary linearly in proportion to the magnitude of the step change.
(iv) within 2 seconds from achieving 90% of the response as defined in CC.A.7.2.3.1 (ii), the
peak to peak magnitude of any oscillations shall be less than 5% of the change in
steady state Reactive Power.
(v) following the transient response, the conditions of CC.A.7.2.2 apply.

MVArs

Required response at 1
second

0.2 1 Seconds
Figure CC.A.7.2.3.1a

CC.A.7.2.3.2 An Onshore Non-Synchronous Generating Unit, Onshore DC Converter, OTSDUW


Plant and Apparatus or Onshore Power Park Module installed on or after 1 December
2017 shall be capable of

(a) changing its Reactive Power output from its maximum lagging value to its maximum
leading value, or vice versa, then reverting back to the initial level of Reactive Power
output once every 15 seconds for at least 5 times within any 5 minute period; and

(b) changing its Reactive Power output from zero to its maximum leading value then
reverting back to zero Reactive Power output at least 25 times within any 24 hour
period and from zero to its maximum lagging value then reverting back to zero
Reactive Power output at least 25 times within any 24 hour period. Any subsequent
restriction on reactive capability shall be notified to NGET in accordance with
BC2.5.3.2, and BC2.6.1.

In all cases, the response shall be in accordance to CC.A.7.2.3.1 where the change in
Reactive Power output is in response to an on-load step change in Onshore Grid Entry
Point or Onshore User System Entry Point voltage, or in the case of OTSDUW Plant and
Apparatus an on-load step change in Transmission Interface Point voltage.

CC.A.7.2.4 Power Oscillation Damping

Issue 5 Revision 17 CC 29 June 2016


94 of 95
CC.A.7.2.4.1 The requirement for the continuously acting voltage control system to be fitted with a Power
System Stabiliser (PSS) shall be specified in the Bilateral Agreement if, in NGETs view,
this is required for system reasons. However if a Power System Stabiliser is included in
the voltage control system its settings and performance shall be agreed with NGET and
commissioned in accordance with BC2.11.2. To allow assessment of the performance
before on-load commissioning the Generator will provide to NGET a report covering the
areas specified in CP.A.3.2.2.
CC.A.7.2.5 Overall Voltage Control System Characteristics
CC.A.7.2.5.1 The continuously acting automatic voltage control system is required to respond to minor
variations, steps, gradual changes or major variations in Onshore Grid Entry Point voltage
(or Onshore User System Entry Point voltage if Embedded or Interface Point voltage in
the case of OTSDUW Plant and Apparatus).
CC.A.7.2.5.2 The overall voltage control system shall include elements that limit the bandwidth of the
output signal. The bandwidth limiting must be consistent with the speed of response
requirements and ensure that the highest frequency of response cannot excite torsional
oscillations on other plant connected to the network. A bandwidth of 0-5Hz would be judged
to be acceptable for this application. All other control systems employed within the Onshore
Non-Synchronous Generating Unit, Onshore DC Converter, OTSDUW Plant and
Apparatus or Onshore Power Park Module should also meet this requirement
CC.A.7.2.5.3 The response of the voltage control system (including the Power System Stabiliser if
employed) shall be demonstrated by testing in accordance with OC5A.A.3.

< END OF CONNECTION CONDITIONS >

Issue 5 Revision 17 CC 29 June 2016


95 of 95
COMPLIANCE PROCESSES
(CP)

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


CP.1 INTRODUCTION ................................................................................................................................... 2
CP.2 OBJECTIVE .......................................................................................................................................... 2
CP.3 SCOPE ................................................................................................................................................. 2
CP.4 CONNECTION PROCESS .................................................................................................................... 3
CP.5 ENERGISATION OPERATIONAL NOTIFICATION ............................................................................... 3
CP.6 INTERIM OPERATIONAL NOTIFICATION ........................................................................................... 4
CP.7 FINAL OPERATIONAL NOTIFICATION ................................................................................................ 7
CP.8 LIMITED OPERATIONAL NOTIFICATION ............................................................................................ 9
CP.9 PROCESSES RELATING TO DEROGATIONS .................................................................................. 12
CP.10 MANUFACTURERS DATA & PERFORMANCE REPORT ............................................................... 12
APPENDIX 1 - ILLUSTRATIVE PROCESS DIAGRAMS ................................................................................ 15
APPENDIX 2 - USER SELF CERTIFICATION OF COMPLIANCE ................................................................. 20
APPENDIX 3 - SIMULATION STUDIES ......................................................................................................... 21

Issue 5 Revision 15 CP 03 February 2016


i
CP.1 INTRODUCTION
CP.1.1 The Compliance Processes ("CP") specifies:
the process (leading to an Energisation Operational Notification) which must be followed
by NGET and any User to demonstrate its compliance with the Grid Code in relation to its
Plant and Apparatus (including OTSUA) prior to the relevant Plant and Apparatus
(including any OTSUA) being energised.
the process (leading to an Interim Operational Notification and Final Operational
Notification) which must be followed by NGET and any Generator or DC Converter
Station owner to demonstrate its compliance with the Grid Code in relation to its Plant and
Apparatus (including any dynamically controlled OTSUA). This process shall be followed
prior to and during the course of the relevant Plant and Apparatus (including OTSUA) being
energised and Synchronised.
the process (leading to a Limited Operational Notification) which must be followed by
NGET and each Generator and DC Converter Station owner where any of its Plant and/or
Apparatus (including any OTSUA) becomes unable to comply with relevant provisions of
the Grid Code, and where applicable with Appendices F1 to F5 (and in the case of OTSUA,
Appendices OF1 to OF5 of the Bilateral Agreement). This process also includes when
changes or Modifications are made to Plant and/or Apparatus (including OTSUA). This
process applies to such Plant and/or Apparatus after the Plant and/or Apparatus has
become Operational and until Disconnected from the Total System, (or until, in the case
of OTSUA, the OTSUA Transfer Time), when changes or Modifications are made.
CP.1.2 As used in this CP references to OTSUA means OTSUA to be connected or connected to
the National Electricity Transmission System prior to the OTSUA Transfer Time.
CP1.3 Where the Generator or DC Convertor Station Owner and/or NGET are required to apply
for a derogation from the Authority, this is not in respect of the OTSUA

CP.2 OBJECTIVE
CP.2.1 The objective of the CP is to ensure that there is a clear and consistent process for
demonstration of compliance by Users with the Connection Conditions and Bilateral
Agreement which are similar for all Users of an equivalent category and will enable NGET
to comply with its statutory and Transmission Licence obligations.
CP.2.2 Provisions of the CP which apply in relation to OTSDUW and OTSUA shall (in any particular
case) apply up to the OTSUA Transfer Time, whereupon such provisions shall (without
prejudice to any prior non-compliance) cease to apply.
CP.2.3 In relation to OTSDUW, provisions otherwise to be contained in a Bilateral Agreement may
be contained in the Construction Agreement, and accordingly a reference in the CP to a
relevant Bilateral Agreement includes the relevant Construction Agreement.

CP.3 SCOPE
CP.3.1 The CP applies to NGET and to Users, which in the CP means:
(a) Generators (other than in relation to Embedded Small Power Stations or Embedded
Medium Power Stations not subject to a Bilateral Agreement) including those
undertaking OTSDUW.
(b) Network Operators;
(c) Non-Embedded Customers;
(d) DC Converter Station owners (other than those which only have Embedded DC
Converter Stations not subject to a Bilateral Agreement).

Issue 5 Revision 15 CP 03 February 2016


2 of 28
CP.3.2 The above categories of User will become bound by the CP prior to them generating,
distributing, supplying or consuming, or in the case of OTSUA, transmitting, as the case may
be, and references to the various categories should, therefore, be taken as referring to them
in that prospective role as well as to Users actually connected.
CP.4 CONNECTION PROCESS
CP.4.1 The CUSC Contract(s) contain certain provisions relating to the procedure for connection to
the National Electricity Transmission System or, in the case of Embedded Power
Stations or Embedded DC Converter Stations, becoming operational and include
provisions to be complied with by Users prior to and during the course of NGET notifying the
User that it has the right to become operational. In addition to such provisions this CP sets
out in further detail the processes to be followed to demonstrate compliance. Whilst this CP
does not expressly address the processes to be followed in the case of OTSUA connecting
to a Network Operators User System prior to the OTSUA Transfer Time, the processes
to be followed by NGET and the Generator in respect of OTSUA in such circumstances
shall be consistent with those set out below by reference OTSUA directly connected to the
National Electricity Transmission System.
CP.4.2 The provisions contained in CP.5 to CP.7 detail the process to be followed in order for the
Users Plant and Apparatus (including OTSUA) to become operational. This process
includes EON (energisation) ION (interim synchronising) and FON (final).
CP.4.2.1 The provisions contained in CP.5 relate to the connection and energisation of Users Plant
and Apparatus (including OTSUA) to the National Electricity Transmission System or
where Embedded, to a Users System and is shown diagrammatically at CP.A.1.1.
CP.4.2.2 The provisions contained in CP.6 and CP.7 provide the process for Generators and DC
Converter Station owners to demonstrate compliance with the Grid Code and with, where
applicable, the CUSC Contract(s) prior to and during the course of such Generators or DC
Converter Station owners Plant and Apparatus (including OTSUA up to the OTSUA
Transfer Time) becoming operational and is shown diagrammatically at CP.A.1.2 and
CP.A.1.3.
CP.4.2.3 The provisions contained in CP.8 detail the process to be followed when:
(a) a Generator or DC Converter Station owners Plant and/or Apparatus (including the
OTSUA) is unable to comply with any provisions of the Grid Code and Bilateral
Agreement; or,
(b) following any notification by a Generator or a DC Converter Station owner under the
PC of any change to its Plant and Apparatus (including any OTSUA); or,
(c) a Modification to a Generator or a DC Converter Station owners Plant and/or
Apparatus.
The process is shown diagrammatically at Appendix CP.A.1.4 for condition (a) and Appendix
CP.A.1.5 for conditions (b) and (c)
CP.4.3 Embedded Medium Power Stations not subject to a Bilateral Agreement and Embedded DC
Converter Stations not subject to a Bilateral Agreement
CP.4.3.1 For the avoidance of doubt the process in this CP does not apply to Embedded Medium
Power Stations not subject to a Bilateral Agreement and Embedded DC Converter
Stations not subject to a Bilateral Agreement.

CP.5 ENERGISATION OPERATIONAL NOTIFICATION


CP.5.1 The following provisions apply in relation to the issue of an Energisation Operational
Notification.

Issue 5 Revision 15 CP 03 February 2016


3 of 28
CP.5.1.1 Certain provisions relating to the connection and energisation of the Users Plant and
Apparatus at the Connection Site and OTSUA at the Transmission Interface Point and
in certain cases of Embedded Plant and Apparatus are specified in the CUSC and/or
CUSC Contract(s). For other Embedded Plant and Apparatus the Distribution Code, the
DCUSA and the Embedded Development Agreement for the connection specify equivalent
provisions. Further detail on this is set out in CP.5 below.
CP.5.2 The items for submission prior to the issue of an Energisation Operational Notification are
set out in CC.5.2
CP.5.3 In the case of a Generator or DC Converter Station owner the items referred to in CC.5.2
shall be submitted using the User Data File Structure.
CP.5.4 Not less than 28 days, or such shorter period as may be acceptable in NGETs reasonable
opinion, prior to the User wishing to energise its Plant and Apparatus (including passive
OTSUA) for the first time the User will submit to NGET a Certificate of Readiness to
Energise High Voltage Equipment which specifies the items of Plant and Apparatus
(including OTSUA) ready to be energised in a form acceptable to NGET.
CP.5.5 If the relevant obligations under the provisions of the CUSC and/or CUSC Contract(s) and
the conditions of CP.5 have been completed to NGETs reasonable satisfaction then NGET
shall issue an Energisation Operational Notification. Any dynamically controlled reactive
compensation OTSUA (including Statcoms or Static Var Compensators) shall not be
Energised until the appropriate Interim Operational Notification has been issued in
accordance with CP.6.

CP.6 INTERIM OPERATIONAL NOTIFICATION


CP.6.1 The following provisions apply in relation to the issue of an Interim Operational
Notification.
CP.6.2 Not less than 28 days, or such shorter period as may be acceptable in NGETs reasonable
opinion, prior to the Generator or DC Converter Station owner wishing to Synchronise its
Plant and Apparatus or dynamically controlled OTSUA for the first time the Generator or
DC Converter Station owner will:
(i) submit to NGET a Notification of Users Intention to Synchronise; and
(iI) submit to NGET the items referred to at CP.6.3.
CP.6.3 Items for submission prior to issue of the Interim Operational Notification.
CP.6.3.1 Prior to the issue of an Interim Operational Notification in respect of the Users Plant and
Apparatus or dynamically controlled OTSUA.
the Generator or DC Converter Station owner must submit to NGET to NGETs
satisfaction:
(a) updated Planning Code data (both Standard Planning Data and Detailed Planning
Data), with any estimated values assumed for planning purposes confirmed or, where
practical, replaced by validated actual values and by updated estimates for the future
and by updated forecasts for Forecast Data items such as Demand;
(b) details of any special Power Station, Generating Unit(s), Power Park Module(s) or
DC Converter Station(s) protection as applicable. This may include Pole Slipping
protection and islanding protection schemes;
(c) any items required by CP.5.2, updated by the User as necessary;
(d) simulation study provisions of Appendix CP.A.3 and the results demonstrating
compliance with Grid Code requirements of:
PC.A.5.4.2
PC.A.5.4.3.2,

Issue 5 Revision 15 CP 03 February 2016


4 of 28
CC.6.3.4,
CC.6.3.7(c)(i),
CC.6.3.15,
CC.A.6.2.5.6,
CC.A.7.2.3.1,
as applicable to the Power Station, Generating Unit(s), Power Park Module(s) or DC
Converter(s) or dynamically controlled OTSUA unless agreed otherwise by NGET;
(e) a detailed schedule of the tests and the procedures for the tests required to be carried
out by the Generator or DC Converter Station owner under CP.7.2 to demonstrate
compliance with relevant Grid Code requirements. Such schedule to be consistent with
Appendix OC5.A.2 (in the case of Generating Units other than Power Park Modules)
or Appendix OC5.A.3 (in the case of Generating Units comprising Power Park
Modules) and OTSUA as applicable); and
(f) an interim Compliance Statement and a User Self Certification of Compliance
completed by the User (including any Unresolved Issues) against the relevant Grid
Code requirements including details of any requirements that the Generator or DC
Converter Station owner has identified that will not or may not be met or
demonstrated.
CP.6.3.2 The items referred to in CP.6.3 shall be submitted by the Generator or DC Converter
Station owner using the User Data File Structure.
CP.6.4 No Generating Unit, CCGT Module, Power Park Module or DC Converter or dynamically
controlled OTSUA shall be Synchronised to the Total System (and for the avoidance of
doubt, dynamically controlled OTSUA will not be able to transmit), until the later of:
(a) the date specified by NGET in the Interim Operational Notification issued in respect
of the Generating Unit(s), CCGT Module(s), Power Park Module(s) or DC
Converter(s) or dynamically controlled OTSUA; and,
(b) if Embedded, the date of receipt of a confirmation from the Network Operator in
whose System the Plant and Apparatus is connected that it is acceptable to the
Network Operator that the Plant and Apparatus be connected and Synchronised;
and,
(c) in the case of Synchronous Generating Unit(s) only after the date of receipt by
Generator of written confirmation from NGET that the Generating Unit or CCGT
Module as applicable has completed the following tests to demonstrate compliance with
the relevant provisions of the Connection Conditions to NGETs satisfaction:
(i) those tests required to establish the open and short circuit saturation
characteristics of the Generating Unit (as detailed in Appendix OC5.A.2.3) to
enable assessment of the short circuit ratio in accordance with CC.6.3.2. Such
tests may be carried out at a location other than the Power Station site; and
(ii) open circuit step response tests (as detailed in Appendix OC5.A.2.2) to
demonstrate compliance with CC.A.6.2.4.1.
CP.6.5 NGET shall assess the schedule of tests submitted by the Generator or DC Converter
Station owner with the Notification of Users Intention to Synchronise under CP.6.1 and
shall determine whether such schedule has been completed to NGETs satisfaction.
CP.6.6 When the requirements of CP.6.2 to CP.6.5 have been met, NGET will notify the Generator
or DC Converter Station owner that the:
Generating Unit,
CCGT Module,
Power Park Module,

Issue 5 Revision 15 CP 03 February 2016


5 of 28
Dynamically controlled OTSUA or
DC Converter,
as applicable may (subject to the Generator or DC Converter Station owner having fulfilled
the requirements of CP.6.3 where that applies) be Synchronised to the Total System
through the issue of an Interim Operational Notification. Where the Generator is
undertaking OTSDUW then the Interim Operational Notification will be in two parts, with
the Interim Operational Notification Part A applicable to the OTSUA and the Interim
Operational Notification Part B applicable to the Users Plant and Apparatus. For the
avoidance of doubt, the Interim Operational Notification Part A and the Interim
Operational Notification Part B can be issued together or at different times. In respect of
an Embedded Power Station or Embedded DC Converter Station (other than a
Embedded Medium Power Stations not subject to a Bilateral Agreement and Embedded
DC Converter Stations not subject to a Bilateral Agreement), NGET will notify the
Network Operator that an Interim Operational Notification has been issued.
CP.6.6.1 The Interim Operational Notification will be time limited, the expiration date being specified
at the time of issue. The Interim Operational Notification may be renewed by NGET.
CP.6.6.2 The Generator or DC Converter Station owner must operate the Generating Unit, CCGT
Module, Power Park Module, OTSUA or DC Converter in accordance with the terms,
arising from the Unresolved Issues, of the Interim Operational Notification. Where
practicable, NGET will discuss such terms with the Generator or DC Converter Station
owner prior to including them in the Interim Operational Notification.
CP.6.6.3 The Interim Operational Notification will include the following limitations:
(a) In the case of OTSUA, the Interim Operational Notification Part A permits
Synchronisation of the dynamically controlled OTSUA to the Total System only for
the purposes of active control of voltage and reactive power and not for the purpose of
exporting Active Power.
(b) In the case of a Power Park Module the Interim Operational Notification (and where
OTSDUW Arrangements apply, this reference will be to the Interim Operational
Notification Part B) will limit the proportion of the Power Park Module which can be
simultaneously Synchronised to the Total System such that neither of the following
figures is exceeded:
(i) 20% of the Registered Capacity of the Power Park Module (or the output of a
single Power Park Unit where this exceeds 20% of the Power Stations
Registered Capacity); nor
(ii) 50MW
until the Generator has completed the voltage control tests (detailed in OC5.A.3.2)
(including in respect of any dynamically controlled OTSUA) to NGETs reasonable
satisfaction. Following successful completion of this test each additional Power Park
Unit should be included in the voltage control scheme as soon as is technically possible
(unless NGET agrees otherwise).
(b) In the case of a Power Park Module with a Registered Capacity greater or equal to
100MW, the Interim Operational Notification (and where OTSDUW Arrangements
apply, this reference will be to the Interim Operational Notification Part B) will limit
the proportion of the Power Park Module which can be simultaneously Synchronised
to the Total System to 70% of Registered Capacity until the Generator has
completed the Limited Frequency Sensitive Mode control tests with at least 50% of
the Registered Capacity of the Power Park Module in service (detailed in OC5.A.3.3)
to NGETs reasonable satisfaction.

Issue 5 Revision 15 CP 03 February 2016


6 of 28
(c) In the case of a Synchronous Generating Unit employing a static Excitation System
the Interim Operational Notification (and where OTSDUW Arrangements apply, this
reference will be to the Interim Operational Notification Part B) may if applicable limit
the maximum Active Power output and reactive power output of the Synchronous
Generating Unit or CCGT module prior to the successful commissioning of the Power
System Stabiliser to NGETs satisfaction.
CP.6.6.4 When a User and NGET are acting/operating in accordance with the provisions of a Interim
Operational Notification, whilst it is in force, the relevant provisions of the Grid Code to
which that Interim Operational Notification relates will not apply to the User or NGET to
the extent and for the period set out in the Interim Operational Notification.
CP.6.7 Other than Unresolved Issues that are subject to tests required under CP.7.2 to be
witnessed by NGET, the Generator or DC Converter Station owner must resolve any
Unresolved Issues prior to the commencement of the tests, unless NGET agrees to a later
resolution. The Generator or DC Converter Station owner must liaise with NGET in
respect of such resolution. The tests that may be witnessed by NGET are specified in
CP.7.2.
CP.6.8 Not less than 28 days, or such shorter period as may be acceptable in NGETs reasonable
opinion, prior to the Generator or DC Converter Station owner wishing to commence tests
required under CP.7 to be witnessed by NGET, the Generator or DC Converter Station
owner will notify NGET that the Generating Unit(s), CCGT Module(s), Power Park
Module(s) or DC Converter(s) as applicable is ready to commence such tests.
CP.6.9 The items referred to at CP.7.3 shall be submitted by the Generator or the DC Converter
Station owner after successful completion of the tests required under CP.7.2.

CP.7. FINAL OPERATIONAL NOTIFICATION


CP.7.1 The following provisions apply in relation to the issue of a Final Operational Notification.
CP.7.2 Tests to be carried out prior to issue of the Final Operational Notification
CP.7.2.1 Prior to the issue of a Final Operational Notification the Generator or DC Converter
Station owner must have completed the tests specified in this CP.7.2.2 to NGETs
satisfaction to demonstrate compliance with the relevant Grid Code provisions.
CP.7.2.2 In the case of any Generating Unit, CCGT Module, Power Park Module, OTSUA (if
applicable) and DC Converter these tests will comprise one or more of the following:
(a) reactive capability tests to demonstrate that the Generating Unit, CCGT Module,
Power Park Module, OTSUA (if applicable) and DC Converter can meet the
requirements of CC.6.3.2. These may be witnessed by NGET on site if there is no
metering to the NGET Control Centre.
(b) voltage control system tests to demonstrate that the Generating Unit, CCGT Module,
Power Park Module, OTSUA (if applicable) and DC Converter can meet the
requirements of CC.6.3.6, CC.6.3.8 and, in the case of Power Park Module, OTSUA (if
applicable) and DC Converter, the requirements of CC.A.7 and, in the case of
Generating Unit and CCGT Module, the requirements of CC.A.6, and any terms
specified in the Bilateral Agreement as applicable. These tests may also be used to
validate the Excitation System model (PC.A.5.3) or voltage control system model
(PC.A.5.4) as applicable. These tests may be witnessed by NGET.
(c) governor or frequency control system tests to demonstrate that the Generating Unit,
CCGT Module, OTSUA (if applicable) and Power Park Module can meet the
requirements of CC.6.3.6, CC.6.3.7, where applicable CC.A.3, and BC.3.7. The results
will also validate the Mandatory Service Agreement required by CC.8.1. These tests
may also be used to validate the Governor model (PC.A.5.3) or frequency control
system model (PC.A.5.4) as applicable. These tests may be witnessed by NGET.

Issue 5 Revision 15 CP 03 February 2016


7 of 28
(d) fault ride through tests in respect of a Power Station with a Registered Capacity of
100MW or greater, comprised of one or more Power Park Modules, to demonstrate
compliance with CC.6.3.15 (a), (b) and (c), CC.A.4.1, CC.A.4.2 and CC.A.4.3. Where
test results from a Manufacturers Data & Performance Report as defined in CP.10
have been accepted this test will not be required.
(e) any further tests reasonably required by NGET and agreed with the User to
demonstrate any aspects of compliance with the Grid Code and the CUSC Contracts.
CP.7.2.3 NGETs preferred range of tests to demonstrate compliance with the CC are specified in
Appendix OC5.A.2 (in the case of Generating Units other than Power Park Modules) or
Appendix OC5.A.3 (in the case of Generating Units comprising Power Park Modules or
OTSUA if applicable) or Appendix OC5.A.4 (in the case of DC Converters) and are to be
carried out by the User with the results of each test provided to NGET. The User may carry
out an alternative range of tests if this is agreed with NGET. NGET may agree a reduced set
of tests where there is a relevant Manufacturers Data & Performance Report as detailed
in CP.10.
CP.7.2.4 In the case of Offshore Power Park Modules which do not contribute to Offshore
Transmission Licensee Reactive Power capability as described in CC.6.3.2(e)(i) or
CC.6.3.2(e)(ii) or Voltage Control as described in CC.6.3.8(b)(i) the tests outlined in CP.7.2.2
(a) and CP.7.2.2 (b) are not required. However, the offshore reactive power transfer tests
outlined in OC5.A.2.8 shall be completed in their place.
CP.7.2.5 Following completion of each of the tests specified in this CP.7.2, NGET will notify the
Generator or DC Converter Station owner whether, in the opinion of NGET, the results
demonstrate compliance with the relevant Grid Code conditions.
CP.7.2.6 The Generator or DC Converter Station owner is responsible for carrying out the tests and
retains the responsibility for safety and personnel during the test.
CP.7.3 Items for submission prior to issue of the Final Operational Notification
CP.7.3.1 Prior to the issue of a Final Operational Notification the Generator or DC Converter
Station owner must submit to NGET to NGETs satisfaction:
(a) updated Planning Code data (both Standard Planning Data and Detailed Planning
Data), with validated actual values and updated estimates for the future including
Forecast Data items such as Demand;
(b) any items required by CP.5.2 and CP.6.3, updated by the User as necessary;
(c) evidence to NGETs satisfaction that demonstrates that the controller models and/or
parameters (as required under PC.A.5.3.2(c) option 2, PC.A.5.3.2(d) option 2,
PC.A.5.4.2, and/or PC.A.5.4.3.2) supplied to NGET provide a reasonable representation
of the behaviour of the Users Plant and Apparatus and OTSUA if applicable;
(d) results from the tests required in accordance with CP.7.2 carried out by the Generator
to demonstrate compliance with relevant Grid Code requirements including the tests
witnessed by NGET; and
(e) the final Compliance Statement and a User Self Certification of Compliance signed
by the User and a statement of any requirements that the Generator or DC Converter
Station owner has identified that have not been met together with a copy of the
derogation in respect of the same from the Authority.
CP.7.3.2 The items in CP.7.3 should be submitted by the Generator (including in respect of any
OTSUA if applicable) or DC Converter Station owner using the User Data File Structure.

Issue 5 Revision 15 CP 03 February 2016


8 of 28
CP.7.4 If the requirements of CP.7.2 and CP.7.3 have been successfully met, NGET will notify the
Generator or DC Converter Station owner that compliance with the relevant Grid Code
provisions has been demonstrated for the Generating Unit(s), CCGT Module(s), Power
Park Module(s), OTSUA, if applicable or DC Converter(s) as applicable through the issue
of a Final Operational Notification. In respect of a Embedded Power Station or
Embedded DC Converter Station other than a Embedded Medium Power Stations not
subject to a Bilateral Agreement and Embedded DC Converter Stations not subject to a
Bilateral Agreement, NGET will notify the Network Operator that a Final Operational
Notification has been issued.
CP.7.5 If a Final Operational Notification can not be issued because the requirements of CP.7.2
and CP.7.3 have not been successfully met prior to the expiry of an Interim Operational
Notification then the Generator or DC Converter Station owner (where licensed in respect
of its activities) and/or NGET shall apply to the Authority for a derogation. The provisions of
CP.9 shall then apply.

CP.8 LIMITED OPERATIONAL NOTIFICATION


CP.8.1 Following the issue of a Final Operational Notification if:
(i) the Generator or DC Converter Station owner becomes aware, that its Plant and/or
Apparatus (including OTSUA if applicable) capability to meet any provisions of the
Grid Code, or where applicable the Bilateral Agreement is not fully available then the
Generator or DC Converter Station owner shall follow the process in CP.8.2 to
CP.8.11; or,
(ii) a Network Operator becomes aware, that the capability of Plant and/or Apparatus
belonging to a Embedded Power Station or Embedded DC Converter Station (other
than a Embedded Medium Power Stations not subject to a Bilateral Agreement and
Embedded DC Converter Stations not subject to a Bilateral Agreement) is failing to
meet any provisions of the Grid Code, or where applicable the Bilateral Agreement
then the Network Operator shall inform NGET and NGET shall inform the Generator
or DC Converter Station owner and then follow the process in CP.8.2 to CP.8.11; or,
(iii) NGET becomes aware through monitoring as described in OC5.4, that a Generator or
DC Converter Station owner Plant and/or Apparatus (including OTSUA if applicable)
capability to meet any provisions of the Grid Code, or where applicable the Bilateral
Agreement is not fully available then NGET shall inform the other party. Where NGET
and the Generator or DC Converter Station owner cannot agree from the monitoring
as described in OC5.4 whether the Plant and/or Apparatus (including OTSUA if
applicable) is fully available and/or is compliant with the requirements of the Grid Code
and where applicable the Bilateral Agreement, the parties shall first apply the process
in OC5.5.1, before applying the process defined in CP.8 (LON) if applicable. Where the
testing instructed in accordance with OC.5.5.1 indicates that the Plant and/or
Apparatus (including OTSUA if applicable) is not fully available and/or is not compliant
with the requirements of the Grid Code and/or the Bilateral Agreement, or if the parties
so agree, the process in CP.8.2 to CP.8.11 shall be followed.
CP.8.2 Immediately upon a Generator or DC Converter Station owner becoming aware that its
Generating Unit, CCGT Module, Power Park Module, OTSUA (if applicable) or DC
Converter Station as applicable may be unable to comply with certain provisions of the Grid
Code or (where applicable) the Bilateral Agreement, the Generator or DC Converter
Station owner shall notify NGET in writing. Additional details of any operating restrictions or
changes in applicable data arising from the potential non-compliance and an indication of the
date from when the restrictions will be removed and full compliance demonstrated shall be
provided as soon as reasonably practical.

Issue 5 Revision 15 CP 03 February 2016


9 of 28
CP.8.3 If the nature of any unavailability and/or potential non-compliance described in CP.8.1
causes or can reasonably be expected to cause a material adverse effect on the business or
condition of NGET or other Users or the National Electricity Transmission System or any
User Systems then NGET may, notwithstanding the provisions of this CP.8 follow the
provisions of Paragraph 5.4 of the CUSC.
CP.8.4 Except where the provisions of CP.8.3 apply, where the restriction notified in CP.8.2 is not
resolved in 28 days then the Generator or DC Converter Station owner with input from and
discussion of conclusions with NGET, and the Network Operator where the Generating
Unit, CCGT Module, Power Park Module or Power Station as applicable is Embedded,
shall undertake an investigation to attempt to determine the causes of and solution to the
non-compliance. Such investigation shall continue for no longer than 56 days. During such
investigation the Generator or DC Converter Station owner shall provide to NGET the
relevant data which has changed due to the restriction in respect of CP.7.3.1 as notified to
the Generator or DC Converter Station owner by NGET as being required to be provided.
CP.8.5 Issue and Effect of LON
CP.8.5.1 Following the issue of a Final Operational Notification, NGET will issue to the Generator
or DC Converter Station owner a Limited Operational Notification if:
(a) by the end of the 56 day period referred to at CP.8.4, the investigation has not resolved
the non-compliance to NGETs satisfaction; or
(b) NGET is notified by a Generator or DC Converter Station owner of a Modification to
its Plant and Apparatus (including OTSUA if applicable); or
(c) NGET receives a submission of data, or a statement from a Generator or DC
Converter Station owner indicating a change in Plant or Apparatus (including OTSUA
if applicable) or settings (including but not limited to governor and excitation control
systems) that may in NGETs reasonable opinion, acting in accordance with Good
Industry Practice be expected to result in a material change of performance.
In the case of an Embedded Generator or Embedded DC Converter Station owner,
NGET will issue a copy of the Limited Operational Notification to the Network Operator.
CP.8.5.2 The Limited Operational Notification will be time limited to expire no later than 12 months
from the start of the non-compliance or restriction or from reconnection following a change.
NGET may agree a longer duration in the case of a Limited Operational Notification
following a Modification or whilst the Authority is considering the application for a
derogation in accordance with CP.9.1.
CP.8.5.3 The Limited Operational Notification will notify the Generator or DC Converter Station
owner of any restrictions on the operation of the Generating Unit(s), CCGT Module(s),
Power Park Module(s), OTSUA (if applicable) or DC Converter(s) and will specify the
Unresolved Issues. The Generator or DC Converter Station owner must operate in
accordance with any notified restrictions and must resolve the Unresolved Issues.
CP.8.5.4 When a User and NGET are acting/operating in accordance with the provisions of a Limited
Operational Notification, whilst it is in force, the relevant provisions of the Grid Code to
which that Limited Operational Notification relates will not apply to the User or NGET to
the extent and for the period set out in the Limited Operational Notification.
CP.8.5.5 The Unresolved Issues included in a Limited Operational Notification will show the
extent that the provisions of CP.7.2 (testing) and CP.7.3 (final data submission) shall apply.
In respect of selecting the extent of any tests which may in NGETs view reasonably be
needed to demonstrate the restored capability and in agreeing the time period in which the
tests will be scheduled, NGET shall, where reasonably practicable, take account of the
Generator or DC Converter Station owners input to contain its costs associated with the
testing.

Issue 5 Revision 15 CP 03 February 2016


10 of 28
CP.8.5.6 In the case of a change or Modification the Limited Operational Notification may specify
that the affected Plant and/or Apparatus (including OTSUA if applicable) or associated
Generating Unit(s) or Power Park Unit(s) must not be Synchronised until all of the
following items, that in NGETs reasonable opinion are relevant, have been submitted to
NGET to NGETs satisfaction:
(a) updated Planning Code data (both Standard Planning Data and Detailed Planning
Data);
(b) details of any relevant special Power Station, Generating Unit(s), Power Park
Module(s), OTSUA (if applicable) or DC Converter Station(s) protection as applicable.
This may include Pole Slipping protection and islanding protection schemes; and
(c) simulation study provisions of Appendix CP.A.3 and the results demonstrating
compliance with Grid Code requirements relevant to the change or Modification as
agreed by NGET; and
(d) a detailed schedule of the tests and the procedures for the tests required to be carried
out by the Generator or DC Converter Station to demonstrate compliance with
relevant Grid Code requirements as agreed by NGET. The schedule of tests shall be
consistent with Appendix OC5.A.2 or Appendix OC5.A.3 as appropriate; and
(e) an interim Compliance Statement and a User Self Certification of Compliance
completed by the User (including any Unresolved Issues) against the relevant Grid
Code requirements including details of any requirements that the Generator or DC
Converter Station owner has identified that will not or may not be met or
demonstrated; and
(f) any other items specified in the LON.
CP.8.5.7 The items referred to in CP.8.5.6 shall be submitted by the Generator (including in respect
of any OTSUA if applicable) or DC Converter Station owner using the User Data File
Structure.
CP.8.5.8 In the case of Synchronous Generating Unit(s) only, the Unresolved Issues of the LON
may require that the Generator must complete the following tests to NGETs satisfaction to
demonstrate compliance with the relevant provisions of the CCs prior to the Generating Unit
being Synchronised to the Total System:
(a) those tests required to establish the open and short circuit saturation characteristics of
the Generating Unit (as detailed in Appendix OC5.A.2.3) to enable assessment of the
short circuit ratio in accordance with CC.6.3.2. Such tests may be carried out at a
location other than the Power Station site; and
(b) open circuit step response tests (as detailed in Appendix OC5.A.2.2) to demonstrate
compliance with CC.A.6.2.4.1.
CP.8.6 In the case of a change or Modification, not less than 28 days, or such shorter period as
may be acceptable in NGETs reasonable opinion, prior to the Generator or DC Converter
Station owner wishing to Synchronise its Plant and Apparatus (including OTSUA if
applicable) for the first time following the change or Modification, the Generator or DC
Converter Station owner will:
(i) submit a Notification of Users Intention to Synchronise; and
(ii) submit to NGET the items referred to at CP.8.5.6.
CP.8.7 Other than Unresolved Issues that are subject to tests to be witnessed by NGET, the
Generator or DC Converter Station owner must resolve any Unresolved Issues prior to
the commencement of the tests, unless NGET agrees to a later resolution. The Generator
or DC Converter Station owner must liaise with NGET in respect of such resolution. The
tests that may be witnessed by NGET are specified in CP.7.2.2.

Issue 5 Revision 15 CP 03 February 2016


11 of 28
CP.8.8 Not less than 28 days, or such shorter period as may be acceptable in NGETs reasonable
opinion, prior to the Generator or DC Converter Station owner wishing to commence tests
listed as Unresolved Issues to be witnessed by NGET, the Generator or DC Converter
Station owner will notify NGET that the Generating Unit(s), CCGT Module(s), Power Park
Module(s), OTSUA (if applicable) or DC Converter(s) as applicable is ready to commence
such tests.
CP.8.9 The items referred to at CP.7.3 and listed as Unresolved Issues shall be submitted by the
Generator or the DC Converter Station owner after successful completion of the tests.
CP.8.10 Where the Unresolved Issues have been resolved a Final Operational Notification will be
issued to the User.
CP.8.11 If a Final Operational Notification has not been issued by NGET within the 12 month
period referred to at CP.8.5.2 (or where agreed following a Modification by the expiry time
of the LON) then the Generator or DC Converter Station owner (where licensed in respect
of its activities) and NGET shall apply to the Authority for a derogation.

CP.9 PROCESSES RELATING TO DEROGATIONS


CP.9.1 Whilst the Authority is considering the application for a derogation, the Interim Operational
Notification or Limited Operational Notification will be extended to remain in force until
the Authority has notified NGET and the Generator or DC Converter Station owner of its
decision. Where the Generator or DC Converter Station owner is not licensed NGET may
propose any necessary changes to the Bilateral Agreement with such unlicensed
Generator or DC Converter Station owner.
CP.9.2 If the Authority:
(a) grants a derogation in respect of the Plant and/or Apparatus, then NGET shall issue
Final Operational Notification once all other Unresolved Issues are resolved; or
(b) decides a derogation is not required in respect of the Plant and/or Apparatus then
NGET will reconsider the relevant Unresolved Issues and may issue a Final
Operational Notification once all other Unresolved Issues are resolved; or
(c) decides not to grant any derogation in respect of the Plant and/or Apparatus, then
there will be no Operational Notification in place and NGET and the User shall
consider its rights pursuant to the CUSC.
CP.9.3 Where an Interim Operational Notification or Limited Operational Notification is so
conditional upon a derogation and such derogation includes any conditions (including any
time limit to such derogation) the Generator or DC Converter Station owner will progress
the resolution of any Unresolved Issues and / or progress and / or comply with any
conditions upon such derogation and the provisions of CP.6.9 to CP.7.4 shall apply and shall
be followed.

CP.10 MANUFACTURERS DATA & PERFORMANCE REPORT


CP.10.1.1 Data and performance characteristics in respect of certain Grid Code requirements may be
registered with NGET by Power Park Unit manufacturers in respect of specific models of
Power Park Units by submitting information in the form of a Manufacturers Data and
Performance Report to NGET.

Issue 5 Revision 15 CP 03 February 2016


12 of 28
CP.10.1.2 A Generator planning to construct a new Power Station containing the appropriate version
of Power Park Units in respect of which a Manufacturers Data & Performance Report
has been submitted to NGET may reference the Manufacturers Data & Performance
Report in its submissions to NGET. Any Generator considering referring to a
Manufacturers Data & Performance Report for any aspect of its Plant and Apparatus
may contact NGET to discuss the suitability of the relevant Manufacturers Data &
Performance Report to its project to determine if, and to what extent, the data included in
the Manufacturers Data & Performance Report contributes towards demonstrating
compliance with those aspects of the Grid Code applicable to the Generator. NGET will
inform the Generator if the reference to the Manufacturers Data & Performance Report is
not appropriate or not sufficient for its project.
CP.10.1.3 The process to be followed by Power Park Unit manufacturers submitting a Manufacturers
Data & Performance Report is agreed by NGET. CP.10.2 indicates the specific Grid Code
requirement areas in respect of which a Manufacturers Data & Performance Report may
be submitted.
CP.10.1.4 NGET will maintain and publish a register of those Manufacturers Data & Performance
Reports which NGET has received and accepted as being an accurate representation of the
performance of the relevant Plant and / or Apparatus. Such register will identify the
manufacturer, the model(s) of Power Park Unit(s) to which the report applies and the
provisions of the Grid Code in respect of which the report contributes towards the
demonstration of compliance. The inclusion of any report in the register does not in any way
confirm that any Power Park Modules which utilise any Power Park Unit(s) covered by a
report is or will be compliant with the Grid Code.
CP.10.2 A Manufacturers Data & Performance Report in respect of Power Park Units may cover
one (or part of one) or more of the following provisions of the Grid Code:
(a) Fault Ride Through capability CC.6.3.15
(b) Power Park Module mathematical model PC.A.5.4.2
CP.10.3 Reference to a Manufacturers Data & Performance Report in a Users submissions does
not by itself constitute compliance with the Grid Code.
CP.10.4 A Generator referencing a Manufacturers Data & Performance Report should insert the
relevant Manufacturers Data & Performance Report reference in the appropriate place in
the DRC data submission and / or in the User Data File Structure. NGET will consider the
suitability of a Manufacturers Data & Performance Report:
(a) in place of DRC data submissions a mathematical model suitable for representation of
the entire Power Park Module as per CP.A.3.4.4. For the avoidance of doubt only the
relevant sections as specified in PC.A.2.5.5.7 apply. Site specific parameters will still
need to be submitted by the Generator.
(b) in place of Fault simulation studies as follows;
NGET will not require Fault Ride Through simulation studies to be conducted as per
CP.A.3.5.1 and qualified in CP.A.3.5.2 provided that;
(i) Adequate and relevant Power Park Unit data is included in respect of Fault Ride
Through testing covered in CP.A.14.7.1 in the relevant Manufacturers Data &
Performance Report , and
(ii) For each type and duration of fault as detailed in CP.A.3.5.1, the expected
minimum retained voltage is greater than the corresponding minimum voltage
achieved and successfully ridden through in the fault ride through tests covered by
the Manufacturers Data & Performance Report.
(c) to reduce the scope of compliance site tests as follows;
(i) Where there is a Manufacturers Data & Performance Report in respect of a
Power Park Unit which covers Fault Ride Through, NGET may agree that no Fault
Ride Through testing is required.
Issue 5 Revision 15 CP 03 February 2016
13 of 28
CP.10.5 It is the responsibility of the User to ensure that the correct reference for the Manufacturers
Data & Performance Report is used and the User by using that reference accepts
responsibility for the accuracy of the information. The User shall ensure that the
manufacturer has kept NGET informed of any relevant variations in plant specification since
the submission of the relevant Manufacturers Data & Performance Report which could
impact on the validity of the information.
CP.10.6 NGET may contact the Power Park Unit manufacturer directly to verify the relevance of the
use of such Manufacturers Data & Performance Report. If NGET believe the use some
or all of such Manufacturers Data & Performance Report information is incorrect or the
referenced data is inappropriate then the reference to the Manufacturers Data &
Performance Report may be declared invalid by NGET. Where, and to the extent possible,
the data included in the Manufacturers Data & Performance Report is appropriate, the
compliance assessment process will be continued using the data included in the
Manufacturers Data & Performance Report.

Issue 5 Revision 15 CP 03 February 2016


14 of 28
APPENDIX 1 - ILLUSTRATIVE PROCESS DIAGRAMS
CP.A.1.1 Illustrative Compliance Process for Energisation of a User

The process illustrated in CP.A.1.1 applies to all Users energising passive network Plant and Apparatus
including Distribution Network Operators, Non-embedded Customers, Generators and DC Converter
Station owners. This process is a subset of the full process for Generators and DC Converter Station
owners shown in CP.A.1.2. This diagram illustrates the process in the CP and includes references in
brackets to specific Grid Code clauses.

Issue 5 Revision 15 CP 03 February 2016


15 of 28
CP.A.1.2 Illustrative Compliance Process for New Power Stations/DC Converter Stations

This diagram illustrates the process in the CP and includes references in brackets to specific Grid Code
clauses. For the avoidance of doubt this process does not apply to Embedded Medium Power Stations not
subject to a Bilateral Agreement and Embedded DC Converter Stations not subject to a Bilateral
Agreement.

Issue 5 Revision 15 CP 03 February 2016


16 of 28
CP.A.1.3 Illustrative Compliance Process for New Offshore Power Stations and OTSUA

This diagram illustrates the process in the CP and includes references in brackets to specific Grid Code
clauses.
Issue 5 Revision 15 CP 03 February 2016
17 of 28
CP.A.1.4 Illustrative Compliance Process for Ongoing Compliance

This diagram illustrates the process in the CP and includes references in brackets to specific Grid Code
clauses. For the avoidance of doubt this process does not apply to Embedded Medium Power Stations not
subject to a Bilateral Agreement and Embedded DC Converter Stations not subject to a Bilateral
Agreement.

Issue 5 Revision 15 CP 03 February 2016


18 of 28
CP.A.1.5 Illustrative Compliance Process for Modification or change

This diagram illustrates the process in the CP and includes references in brackets to specific Grid Code
clauses. For the avoidance of doubt this process does not apply to Embedded Medium Power Stations not
subject to a Bilateral Agreement and Embedded DC Converter Stations not subject to a Bilateral
Agreement.

Issue 5 Revision 15 CP 03 February 2016


19 of 28
APPENDIX 2 - USER SELF CERTIFICATION OF COMPLIANCE

USER SELF CERTIFICATION OF COMPLIANCE (Interim/Final)


Power Station/ DC
[Name of Connection Site/site of connection]
Converter Station:
OTSUA [Name of Interface Site]

User: [Full User name]


Registered Capacity
(MW) of Plant:

This User Self Certification of Compliance records the compliance by the User in respect of [NAME]
Power Station/DC Converter Station [and, in the case of OTSDUW Arrangements, OTSUA] with the Grid
Code and the requirements of the Bilateral Agreement and Construction Agreement dated [ ] with
reference number [ ]. It is completed by the Power Station/DC Converter Station owner in the case of
Plant and/or Apparatus (including OTSUA) connected to the National Electricity Transmission System
and for Embedded Plant.
We have recorded our compliance against each requirement of the Grid Code which applies to the Power
Station/DC Converter Station/OTSUA, together with references to supporting evidence and a commentary
where this is appropriate, and have provided this to NGET. A copy of the Compliance Statement is
attached.
Supporting evidence, in the form of simulation results, test results, manufacturers data and other
documentation, is attached in the User Data File Structure.
The User hereby certifies that, to the best of its knowledge and acting in accordance with Good Industry
Practice, [the Power Station is compliant with the Grid Code and the Bilateral Agreement] [the OTSUA is
compliant with the Grid Code and the Construction Agreement] in all aspects [with the following
Unresolved Issues*] [with the following derogation(s)**]:
Connection
Requirement Ref: Issue
Condition

Compliance Name: Title:


certified by: [PERSON] [PERSON DESIGNATION]
Signature: Of
[PERSON] [USER DETAILS]
Date:

* Include for Interim User Self Certification of Compliance ahead of Interim Operational Notification.

** Include for final User Self Certification of Compliance ahead of Final Operational Notification where derogation(s) have been granted.
If no derogation(s) required delete wording and Table.

Issue 5 Revision 15 CP 03 February 2016


20 of 28
APPENDIX 3 - SIMULATION STUDIES
CP.A.3.1.1 This Appendix sets out the simulation studies required to be submitted to NGET to
demonstrate compliance with the Connection Conditions unless otherwise agreed with
NGET. This Appendix should be read in conjunction with CP.6 with regard to the submission
of the reports to NGET. Where there is any inconsistency in the technical requirements in
respect of which compliance is being demonstrated by simulation in this Appendix and
CC.6.3 and the Bilateral Agreement, the provisions of the Bilateral Agreement and CC.6.3
prevail. The studies specified in this Appendix will normally be sufficient to demonstrate
compliance. However NGET may agree an alternative set of studies proposed by the
Generator or DC Converter Station owner provided NGET deem the alternative set of
studies sufficient to demonstrate compliance with the Grid Code and the Bilateral
Agreement.
CP.A.3.1.2 The Generator or DC Converter Station owner shall submit simulation studies in the form
of a report to demonstrate compliance. In all cases the simulation studies must utilise models
applicable to the Generating Unit, DC Converter or Power Park Module with proposed or
actual parameter settings. Reports should be submitted in English with all diagrams and
graphs plotted clearly with legible axes and scaling provided to ensure any variations in
plotted values is clear.
CP.A.3.1.3 In the case of an Offshore Power Station where OTSDUW Arrangements apply simulation
studies by the Generator should include the action of any relevant OTSUA where applicable
to demonstrate compliance with the Grid Code and the Bilateral Agreement at the
Interface Point.
CP.A.3.2 Power System Stabiliser Tuning
CP.A.3.2.1 In the case of a Synchronous Generating Unit the Power System Stabiliser tuning
simulation study report required by CC.A.6.2.5.6 or required by the Bilateral Agreement
shall contain:
(i) the Excitation System model including the Power System Stabiliser with settings as
required under the Planning Code (PC.A.5.3.2(c))
(ii) on load time series dynamic simulation studies of the response of the Excitation
System with and without the Power System Stabiliser to 2% and 10% steps in the
reference voltage and a three phase short circuit fault applied to the higher voltage side
of the Generating Unit transformer for 100ms. The simulation studies should be carried
out with the Generating Unit operating at full Active Power and maximum leading
Reactive Power import with the fault level at the Supergrid HV connection point at
minimum or as otherwise agreed with NGET. The results should show Generating Unit
field voltage, Generating Unit terminal voltage, Power System Stabiliser output,
Generating Unit Active Power and Generating Unit Reactive Power output.
(iii) gain and phase Bode diagrams for the open loop frequency domain response of the
Generating Unit Excitation System with and without the Power System Stabiliser.
These should be in a suitable format to allow assessment of the phase contribution of
the Power System Stabiliser and the gain and phase margin of the Excitation
System with and without the Power System Stabiliser in service.
(iv) an eigenvalue plot to demonstrate that all modes remain stable when the Power
System Stabiliser gain is increased by at least a factor of 3 from the designed
operating value.
(v) gain Bode diagram for the closed loop on load frequency domain response of the
Generating Unit Excitation System with and without the Power System Stabiliser.
The Generating Unit operating at full load and at unity power factor. These diagrams
should be in a suitable format to allow comparison of the Active Power damping across
the frequency range specified in CC.A.6.2.6.3 with and without the Power System
Stabiliser in service.

Issue 5 Revision 15 CP 03 February 2016


21 of 28
CP.A.3.2.2 In the case of Onshore Non-Synchronous Generating Units, Onshore DC Converters
and Onshore Power Park Modules and OTSDUW Plant and Apparatus at the Interface
Point the Power System Stabiliser tuning simulation study report required by CC.A.7.2.4.1
or required by the Bilateral Agreement shall contain:
(i) the Voltage Control System model including the Power System Stabiliser with
settings as required under the Planning Code (PC.A.5.4) and Bilateral Agreement.
(ii) on load time series dynamic simulation studies of the response of the Voltage Control
System with and without the Power System Stabiliser to 2% and 10% steps in the
reference voltage and a three phase short circuit fault applied to the Grid Entry Point
or the Interface Point in the case of OTSDUW Plant and Apparatus for 100ms. The
simulation studies should be carried out operating at full Active Power and maximum
leading Reactive Power import condition with the fault level at the Supergrid HV
connection point at minimum or as otherwise agreed with NGET. The results should
show appropriate signals to demonstrate the expected damping performance of the
Power System Stabiliser.
(iii) any other simulation as specified in the Bilateral Agreement or agreed between the
Generator or DC Converter Owner or Offshore Transmission Licensee and NGET.
CP.A.3.3 Reactive Capability across the Voltage Range
CP.A.3.3.1 The Generator or DC Converter station owner shall supply simulation studies to
demonstrate the capability to meet CC.6.3.4 by submission of a report containing:
(i) a load flow simulation study result to demonstrate the maximum lagging Reactive
Power capability of the Synchronous Generating Unit, DC Converter, OTSUA or
Power Park Module at Rated MW when the Grid Entry Point or User System Entry
Point if Embedded or Interface Point (in case of OTSUA) voltage is at 105% of
nominal.
(ii) a load flow simulation study result to demonstrate the maximum leading Reactive
Power capability of the Synchronous Generating Unit, DC Converter, OTSUA or
Power Park Module at Rated MW when the Grid Entry Point or User System Entry
Point if Embedded or Interface Point (in case of OTSUA) voltage is at 95% of
nominal.
CP.A.3.3.2 In the case of a Synchronous Generating Unit the terminal voltage in the simulation should
be the nominal voltage for the machine. Where necessary to demonstrate compliance with
CC.6.3.4 and subject to compliance with CC.6.3.8 (a) (v), the Generator shall repeat the two
simulation studies with the terminal voltage being greater than the nominal voltage and less
than or equal to the maximum terminal voltage. The two additional simulations do not need
to have the same terminal voltage.
CP.A.3.3.3 In the case of a Synchronous Generating Unit the Generator shall supply two sets of
simulation studies to demonstrate the capability to meet the operational requirements of
BC2.A.2.6 and CC.6.1.7 at the minimum and maximum short circuit levels when changing
tap position. Each set of simulation studies shall be at the same system conditions. None of
the simulation studies shall include the Synchronous Generating Unit operating at the
limits of its Reactive Power output.
The simulation results shall include the Reactive Power output of the Synchronous
Generating Unit and the voltage at the Grid Entry Point or, if Embedded, the User
System Entry Point with the Generating Unit transformer at two adjacent tap positions with
the greatest interval between them and the terminal voltage of the Synchronous
Generating Unit equal to
- its nominal value; and
- subject to compliance with CC.6.3.8 (a) (v), its maximum value.

Issue 5 Revision 15 CP 03 February 2016


22 of 28
CP.A.3.3.4 In the case of a Power Park Module where the load flow simulation studies show that the
individual Power Park Units deviate from nominal voltage to meet the Reactive Power
requirements then evidence must be provided from factory (e.g. in a Manufacturers Data &
Performance Report) or site testing that the Power Park Unit is capable of operating
continuously at the operating points determined in the load flow simulation studies.
CP.A.3.4 Voltage Control and Reactive Power Stability
CP.A.3.4.1 In the case of a power station containing Power Park Modules and/or OTSUA the
Generator shall provide a report to demonstrate the dynamic capability and control stability
of the Power Park Module. The report shall contain:
(i) a dynamic time series simulation study result of a sufficiently large negative step in
System voltage to cause a change in Reactive Power from zero to the maximum
lagging value at Rated MW.
(ii) a dynamic time series simulation study result of a sufficiently large positive step in
System voltage to cause a change in Reactive Power from zero to the maximum
leading value at Rated MW.
(iii) a dynamic time series simulation study result to demonstrate control stability at the
lagging Reactive Power limit by application of a -2% voltage step while operating within
5% of the lagging Reactive Power limit.
(iv) a dynamic time series simulation study result to demonstrate control stability at the
leading Reactive Power limit by application of a +2% voltage step while operating
within 5% of the leading Reactive Power limit.
CP.A.3.4.2 All the above studies should be completed with a nominal network voltage for zero Reactive
Power transfer at the Grid Entry Point or User System Entry Point if Embedded or, in the
case of OTSUA, Interface Point unless stated otherwise and the fault level at the HV
connection point at minimum as agreed with NGET.
CP.A.3.4.3 NGET may permit relaxation from the requirements of CP.A.3.4.1(i) and (ii) for voltage
control if the Power Park Modules are comprised of Power Park Units in respect of which
the User has in its submissions to NGET referenced an appropriate Manufacturers Data &
Performance Report which is acceptable to NGET for voltage control.
CP.A.3.4.4 In addition NGET may permit a further relaxation from the requirements of CP.A.3.4.1(iii) and
(iv) if the User has in its submissions to NGET referenced an appropriate Manufacturers
Data & Performance Report for a Power Park Module mathematical model for voltage
control acceptable to NGET.
CP.A.3.5 Fault Ride Through
CP.A.3.5.1 The Generator, (including where undertaking OTSDUW) or DC Converter Station owner
shall supply time series simulation study results to demonstrate the capability of Non-
Synchronous Generating Units, DC Converters, Power Park Modules and OTSUA to
meet CC.6.3.15 by submission of a report containing:
(i) a time series simulation study of a 140ms solid three phase short circuit fault applied on
the nearest point of the National Electricity Transmission System operating at
Supergrid voltage to the Non-Synchronous Generating Unit, DC Converter, Power
Park Module or OTSUA.
(ii) time series simulation study of 140ms unbalanced short circuit faults applied on the
nearest point of the National Electricity Transmission System operating at
Supergrid voltage to the Non-Synchronous Generating Unit, DC Converter, Power
Park Module or OTSUA. The unbalanced faults to be simulated are:
1. a phase to phase fault
2. a two phase to earth fault
3. a single phase to earth fault.

Issue 5 Revision 15 CP 03 February 2016


23 of 28
For a Non-Synchronous Generating Unit, DC Converter, Power Park Module or OTSUA
the simulation study should be completed with the Non-Synchronous Generating Unit, DC
Converter, Power Park Module or OTSUA operating at full Active Power and maximum
leading Reactive Power import and the fault level at the Supergrid HV connection point at
minimum or as otherwise agreed with NGET.
(iii) time series simulation studies of balanced Supergrid voltage dips applied on the
nearest point of the National Electricity Transmission System operating at
Supergrid voltage to the Non-Synchronous Generating Unit, DC Converter, Power
Park Module or OTSUA. The simulation studies should include:
1. 30% retained voltage lasting 0.384 seconds
2. 50% retained voltage lasting 0.71 seconds
3. 80% retained voltage lasting 2.5 seconds
4. 85% retained voltage lasting 180 seconds.
For a Non-Synchronous Generating Unit, DC Converter, Power Park Module or OTSUA
the simulation study should be completed with the Non-Synchronous Generating Unit, DC
Converter, Power Park Module or OTSUA operating at full Active Power and zero
Reactive Power output and the fault level at the Supergrid HV connection point at minimum
or as otherwise agreed with NGET. Where the Non-Synchronous Generating Unit, DC
Converter or Power Park Module is Embedded the minimum Network Operators
System impedance to the Supergrid HV connection point shall be used which may be
calculated from the maximum fault level at the User System Entry Point.
For DC Converters the simulations should include the duration of each voltage dip 1 to 4
above for which the DC Converter will remain connected.
CP.A.3.5.2 In the case of Power Park Modules comprised of Power Park Units in respect of which the
Users reference to a Manufacturers Data & Performance Report has been accepted by
NGET for Fault Ride Through, CP.A.3.5.1 will not apply provided:
(i) the Generator or DC Converter Station owner demonstrates by load flow simulation
study result that the faults and voltage dips at either side of the Power Park Unit
transformer corresponding to the required faults and voltage dips in CP.A.3.5.1 applied
at the nearest point of the National Electricity Transmission System operating at
Supergrid voltage are less than those included in the Manufacturers Data &
Performance Report,
or;
(ii) the same or greater percentage faults and voltage dips in CP.A.3.5.1 have been applied
at either side of the Power Park Unit transformer in the Manufacturers Data &
Performance Report.
CP.A.3.5.3 In the case of an Offshore Power Park Module or Offshore DC Converter the studies may
instead be completed at the LV Side of the Offshore Platform. For fault simulation studies
described in CCA.8.5.1(i) and CCA.8.5.1(ii) a retained voltage of 15% or lower may be
applied at the LV Side of the Offshore Platform on the faulted phases. For voltage dip
simulation studies described in CP.A.3.5.1(iii) the same voltage levels and durations as
normally applied at the National Electricity Transmission System operating at Supergrid
Voltage will be applied at the LV Side of the Offshore Platform.
CP.A.3.6 Load Rejection
CP.A.3.6.1 In respect of Generating Units or DC Converters or Power Park Modules with a
Completion Date on or after 1 January 2012, the Generator or DC Converter Station
owner shall demonstrate the speed control performance of the plant under a part load
rejection condition as required by CC.6.3.7(c)(i), through simulation study. In respect of
Generating Units or DC Converters or Power Park Modules, including those with a
Completion Date before 1 January 2013, the load rejection capability while still supplying
load must be stated in accordance with PC.A.5.3.2(f).
Issue 5 Revision 15 CP 03 February 2016
24 of 28
CP.A.3.6.2 For Power Park Modules comprised of Power Park Units having a corresponding
generically verified and validated model included in the Manufacturers Data &
Performance Report this study is not required if the correct Manufacturers Data &
Performance Report reference has been submitted in the appropriate location in the Data
Registration Code.
CP.A.3.6.3 The simulation study should comprise of a Generating Unit, DC Converter or Power Park
Module connected to the total System with a local load shown as X in figure CP.A.3.6.1.
The load X is in addition to any auxiliary load of the Power Station connected directly to
the Generating Unit, DC Converter or Power Park Module and represents a small portion
of the System to which the Generating Unit, DC Converter or Power Park Module is
attached. The value of X should be the minimum for which the Generating Unit, DC
Converter or Power Park Module can control the power island frequency to less than 52Hz.
Where transient excursions above 52Hz occur the Generator or DC Converter Owner
should ensure that the duration above 52Hz is less than any high frequency protection
system applied to the Generating Unit, DC Converter or Power Park Module.
CP.A.3.6.4 At the start of the simulation study the Generating Unit, DC Converter or Power Park
Module will be operating maximum Active Power output. The Generating Unit, DC
Converter or Power Park Module will then be islanded from the Total System but still
supplying load X by the opening of a breaker, which is not the Generating Unit, DC
Converter or Power Park Module connection circuit breaker (the governor should therefore,
not receive any signals that the breaker has opened other than the reduction in load and
subsequent increase in speed). A schematic arrangement of the simulation study is
illustrated by Figure CP.A.3.6.1.

Figure CP.A.3.6.1 Diagram of Load Rejection Study

CP.A.3.6.5 Simulation study shall be performed for both control modes, Frequency Sensitive Mode
(FSM) and Limited Frequency Sensitive Mode (LFSM). The simulation study results
should indicate Active Power and Frequency in the island system that includes the
Generating Unit, DC Converter or Power Park Module.

Issue 5 Revision 15 CP 03 February 2016


25 of 28
CP.A.3.6.6 To allow validation of the model used to simulate load rejection in accordance with
CC.6.3.7(c)(i) as described a further simulation study is required to represent the largest
positive Frequency injection step or fast ramp (BC1 and BC3 of Figure 2) that will be applied
as a test as described in OC5.A.2.8 and OC5.A.3.6.
CP.A.3.7 Voltage and Frequency Controller Model Verification and Validation
CP.A.3.7.1 For Generating Units, DC Converters or Power Park Modules with a Completion Date
after 1 January 2012 or subject to a Modification to a Excitation System, voltage control
system, governor control system or Frequency control system after 1 January 2012 the
Generator or DC Converter Station owner shall provide simulation studies to verify that the
proposed controller models supplied to NGET under the Planning Code are fit for purpose.
These simulation study results shall be provided in the timescales stated in the Planning
Code. For Power Park Modules comprised of Power Park Units having a corresponding
generically verified and validated model in a Manufacturers Data & Performance Report
NGET may permit the simulation studies detailed in CP.A.3.7.2, CP.A.3.7.4 and CP.A.3.7.5
to be replaced by submission of the correct Manufacturers Data & Performance Report
reference in the appropriate location in the Data Registration Code.
CP.A.3.7.2 To demonstrate the Frequency control or governor/load controller/plant model the
Generator or DC Converter Station owner shall submit a simulation study representing the
response of the Synchronous Generating Unit, DC Converter or Power Park Module
operating at 80% of Registered Capacity. The simulation study event shall be equivalent to:
(i) a ramped reduction in the measured System Frequency of 0.5Hz in 10 seconds
followed by
(ii) 20 seconds of steady state with the measured System Frequency depressed by 0.5Hz
followed by
(iii) a ramped increase in measured System Frequency of 0.3Hz over 30 seconds followed
by
(iv) 60 seconds of steady state with the measured System Frequency depressed by 0.2Hz
as illustrated in Figure CP.A.3.7.2 below.

Figure CP.A.3.7.2

The simulation study shall show Active Power output (MW) and the equivalent of
Frequency injected.
CP.A.3.7.3 To demonstrate the Excitation System model the Generator shall submit simulation studies
representing the response of the Synchronous Generating Unit as follows:
(i) operating open circuit at rated terminal voltage and subjected to a 2% step increase in
terminal voltage reference.

Issue 5 Revision 15 CP 03 February 2016


26 of 28
(ii) operating at Rated MW, nominal terminal voltage and unity power factor subjected to a
2% step increase in the voltage reference. Where a Power System Stabiliser is
included within the Excitation System this shall be in service.
The simulation study shall show the terminal voltage, field voltage of the Generating Unit,
Active Power, Reactive Power and Power System Stabiliser output signal as appropriate.
CP.A.3.7.4 To demonstrate the Voltage Controller model the Generator or DC Converter Station
owner shall submit a simulation study representing the response of the Non-Synchronous
Generating Unit, DC Converter or Power Park Module operating at Rated MW and unity
power factor at the connection point to a 2% step increase in the voltage reference. The
simulation study shall show the terminal voltage, Active Power, Reactive Power and
Power System Stabiliser output signal as appropriate.
CP.A.3.7.5 To validate that the excitation and voltage control models submitted under the Planning
Code are a reasonable representation of the dynamic behaviour of the Synchronous
Generating Unit, DC Converter Station or Power Park Module as built, the Generator or
DC Converter Station owner shall repeat the simulation studies outlined above but using
the operating conditions of the equivalent tests. The simulation study results shall be
displayed overlaid on the actual test results.
CP.A.3.7.7 For Generating Units or DC Converters with a Completion Date after 1 January 2012 or
subject to a Modification to the governor system or Frequency control system after 1
January 2013 to validate that the governor/load controller/plant or Frequency control models
submitted under the Planning Code is a reasonable representation of the dynamic
behaviour of the Synchronous Generating Unit or DC Converter Station as built, the
Generator or DC Converter Station owner shall repeat the simulation studies outlined
above but using the operating conditions of the equivalent tests. The simulation study results
shall be displayed overlaid on the actual test results.

Issue 5 Revision 15 CP 03 February 2016


27 of 28
CP.A.3.8 Sub-synchronous Resonance Control and Power Oscillation Damping Control for DC
Converters
CP.A.3.8.1 To demonstrate the compliance of the sub-synchronous control function with CC.6.3.16(a)
and the terms of the Bilateral Agreement, the DC Converter Station owner or Generator
undertaking OTSDUW shall submit a simulation study report.
CP.A.3.8.2 Where power oscillation damping control function is specified on a DC Converter the DC
Converter Station owner or Generator undertaking OTSDUW shall submit a simulation
study report to demonstrate the compliance with CC.6.3.16(b) and the terms of the Bilateral
Agreement.
CP.A.3.8.3 The simulation studies should utilise the DC Converter control system models including the
settings as required under the Planning Code (PC.A.5.3.2). The network conditions for the
above simulation studies should be discussed with NGET prior to commencing any
simulation studies.

< END OF COMPLIANCE PROCESSES >

Issue 5 Revision 15 CP 03 February 2016


28 of 28
OPERATING CODE NO. 1
(OC1)

DEMAND FORECASTS

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC1.1 INTRODUCTION...................................................................................................................................2
OC1.2 OBJECTIVE ..........................................................................................................................................2
OC1.3 SCOPE..................................................................................................................................................2
OC1.4 DATA REQUIRED BY NGET IN THE OPERATIONAL PLANNING PHASE .......................................2
OC1.5 DATA REQUIRED BY NGET IN THE PROGRAMMING PHASE, CONTROL PHASE AND
POST-CONTROL PHASE..................................................................................................................................3
OC1.6 NGET FORECASTS .............................................................................................................................5

Issue 5 Revision 0 OC1 17 August 2012


i
OC1.1 INTRODUCTION
OC1.1.1 Operating Code No.1 ("OC1") is concerned with Demand forecasting for operational
purposes. In order to match generation output with Demand for electricity it is necessary to
undertake Demand forecasting. It is also necessary to undertake Demand forecasting of
Reactive Power.
OC1.1.2 In the Operational Planning Phase, Demand forecasting shall be conducted by NGET
taking account of Demand forecasts furnished by Network Operators, who shall provide
NGET with information in the form set out in this OC1. The data supplied under the PC is
also taken into account.
OC1.1.3 In the Programming Phase and Control Phase, NGET will conduct its own Demand
forecasting taking into account information to be furnished by Suppliers and Network
Operators and the other factors referred to in OC1.6.1.
OC1.1.4 In this OC1, the point of connection of the External Interconnection to the National
Electricity Transmission System shall be considered as a Grid Supply Point. Reactive
Power Demand includes the series Reactive losses of the User's System but excludes any
network susceptance and any Reactive compensation on the User's System. NGET will
obtain the lumped network susceptance and details of Reactive compensation from the
requirements to submit data under the PC.
OC1.1.5 Data relating to Demand Control should include details relating to MW.
OC1.1.6 OC1 deals with the provision of data on Demand Control in the Operational Planning
Phase, the Programming Phase and the Post-Control Phase, whereas OC6 (amongst
other things) deals with the provision of data on Demand Control following the
Programming Phase and in the Control Phase.
OC1.1.7 In this OC1, Year 0 means the current Financial Year at any time, Year 1 means the next
Financial Year at any time, Year 2 means the Financial Year after Year 1, etc.
OC1.1.8 References in OC1 to data being supplied on a half hourly basis refer to it being supplied for
each period of 30 minutes ending on the hour and half-hour in each hour.

OC1.2 OBJECTIVE
The objectives of OC1 are to:
OC1.2.1 enable the provision of data to NGET by Users in the Programming Phase, Control Phase
and Post-Control Phase; and
OC1.2.2 provide for the factors to be taken into account by NGET when Demand forecasting in the
Programming Phase and Control Phase.

OC1.3 SCOPE
OC1 applies to NGET and to Users which in this OC1 means:
(a) Network Operators, and
(b) Suppliers.

OC1.4 DATA REQUIRED BY NGET IN THE OPERATIONAL PLANNING PHASE


OC1.4.1 (a) Each User, as specified in (b) below, shall provide NGET with the data requested in
OC1.4.2 below.
(b) The data will need to be supplied by each Network Operator directly connected to the
National Electricity Transmission System in relation to Demand Control and in
relation each Generator with respect to the output of Embedded Medium Power
Stations within its System.
OC1.4.2 (a) Data

Issue 5 Revision 0 OC1 17 August 2012


2 of 5
By calendar week 28 each year each Network Operator will provide to NGET in writing
the forecast information listed in (c) below for the current Financial Year and each of
the succeeding five Financial Years.
(b) Data Providers
In circumstances when the busbar arrangement at a Grid Supply Point is expected to
be operated in separate sections, separate sets of forecast information for each section
will be provided to NGET.
(c) Embedded Medium Power Station Output and Demand Control
For the specified time of the annual peak half hour National Electricity Transmission
System Demand, as specified by NGET under PC.A.5.2.2, the output of Embedded
Medium Power Stations and forecasts of Demand to be relieved by Demand Control
on a Grid Supply Point basis giving details of the amount and duration of the Demand
Control.

OC1.5 DATA REQUIRED BY NGET IN THE PROGRAMMING PHASE, CONTROL PHASE AND
POST-CONTROL PHASE
OC1.5.1 Programming Phase
For the period of 2 to 8 weeks ahead the following will be supplied to NGET in writing by
1000 hours each Monday:
(a) Demand Control
Each Network Operator will supply MW profiles of the amount and duration of their
proposed use of Demand Control which may result in a Demand change equal to or
greater than the Demand Control Notification Level (averaged over any half hour on
any Grid Supply Point) on a half hourly and Grid Supply Point basis;
(b) Medium Power Station Operation
Each Network Operator will, if reasonably required by NGET, supply MW schedules for
the operation of Embedded Medium Power Stations within its System on a half hourly
and Grid Supply Point basis.
OC1.5.2 For the period 2 to 12 days ahead the following will be supplied to NGET in writing by 1200
hours each Wednesday:
(a) Demand Control
Each Network Operator will supply MW profiles of the amount and duration of their
proposed use of Demand Control which may result in a Demand change equal to or
greater than the Demand Control Notification Level (averaged over any half hour on
any Grid Supply Point) on a half hourly and Grid Supply Point basis;
(b) Medium Power Station Operation
Each Network Operator will, if reasonably required by NGET, supply MW schedules for
the operation of Embedded Medium Power Stations within its System on a half hourly
and Grid Supply Point basis.
OC1.5.3 Medium Power Station Output
Each Network Operator will, if reasonably required by NGET, supply NGET with MW
schedules for the operation of Embedded Medium Power Stations within its System on a
half hourly and Grid Supply Point basis in writing by 1000 hours each day (or such other
time specified by NGET from time to time) for the next day (except that it will be for the next
3 days on Fridays and 2 days on Saturdays and may be longer (as specified by NGET at
least one week in advance) to cover holiday periods);
OC1.5.4 Other Codes

Issue 5 Revision 0 OC1 17 August 2012


3 of 5
Under OC6 each Network Operator will notify NGET of their proposed use of Demand
Control (which may result in a Demand change equal to or greater than the Demand
Control Notification Level), and under BC1, each Supplier will notify NGET of their
proposed use of Customer Demand Management (which may result in a Demand change
equal to or greater than the Customer Demand Management Notification Level) in this
timescale.
OC1.5.5 Control Phase
OC1.5.5.1 Demand Control
Under OC6, each Network Operator will notify NGET of any Demand Control proposed by
itself which may result in a Demand change equal to or greater than the Demand Control
Notification Level averaged over any half hour on any Grid Supply Point which is planned
after 1000 hours, and of any changes to the planned Demand Control notified to NGET
prior to 1000 hours as soon as possible after the formulation of the new plans;
OC1.5.5.2 Customer Demand Management
(a) Each Supplier will notify NGET of any Customer Demand Management proposed by
itself which may result in a Demand change equal to or greater than the Customer
Demand Management Notification Level averaged over any half hour on any Grid
Supply Point which is planned to occur at any time in the Control Phase and of any
changes to the planned Customer Demand Management already notified to NGET as
soon as possible after the formulation of the new plans.
(b) The following information is required on a Grid Supply Point and half-hourly basis:
(i) the proposed date, time and duration of implementation of Customer Demand
Management; and
(ii) the proposed reduction in Demand by use of Customer Demand Management.
OC1.5.5.3 Load Management Blocks
In Scotland, by 11:00 each day, each Supplier who controls a Load Management Block of
Demand with a capacity of 5MW or more shall submit to NGET a schedule of its proposed
switching times and profiles in respect of each block for the next day.
OC1.5.6 Post-Control Phase
The following will be supplied to NGET in writing by 0600 hours each day in respect of
Active Power data and by 1000 hours each day in respect of Reactive Power data:
(a) Demand Control
Each Network Operator will supply MW profiles for the previous calendar day of the
amount and duration of Demand reduction achieved by itself from the use of Demand
Control equal to or greater than the Demand Control Notification Level (averaged
over any half hour on any Grid Supply Point), on a half hourly and Grid Supply Point
basis.
(b) Customer Demand Management
Each Supplier will supply MW profiles of the amount and duration of Demand reduction
achieved by itself from the use of Customer Demand Management equal to or greater
than the Customer Demand Management Notification Level (averaged over any half
hour on any Grid Supply Point) on a half hourly and Grid Supply Point basis during
the previous calendar day.

Issue 5 Revision 0 OC1 17 August 2012


4 of 5
OC1.6 NGET FORECASTS
OC1.6.1 The following factors will be taken into account by NGET when conducting National
Electricity Transmission System Demand forecasting in the Programming Phase and
Control Phase:
(a) Historic Demand data (this includes National Electricity Transmission System
Losses).
(b) Weather forecasts and the current and historic weather conditions.
(c) The incidence of major events or activities which are known to NGET in advance.
(d) Anticipated interconnection flows across External Interconnections.
(e) Demand Control equal to or greater than the Demand Control Notification Level
(averaged over any half hour at any Grid Supply Point) proposed to be exercised by
Network Operators and of which NGET has been informed.
(f) Customer Demand Management equal to or greater than the Customer Demand
Management Notification Level (averaged over any half hour at any Grid Supply
point) proposed to be exercised by Suppliers and of which NGET has been informed.
(g) Other information supplied by Users.
(h) Anticipated Pumped Storage Unit demand.
(i) the sensitivity of Demand to anticipated market prices for electricity.
(j) BM Unit Data submitted by BM Participants to NGET in accordance with the
provisions of BC1 and BC2.
(k) Demand taken by Station Transformers
OC1.6.2 Taking into account the factors specified in OC1.6.1 NGET uses Demand forecast
methodology to produce forecasts of National Electricity Transmission System Demand.
A written record of the use of the methodology must be kept by NGET for a period of at least
12 months.
OC1.6.3 The methodology will be based upon factors (a), (b) and (c) above to produce, by statistical
means, unbiased forecasts of National Demand. National Electricity Transmission
System Demand will be calculated from these forecasts but will also take into account
factors (d), (e), (f), (g), (h), (i) and (j) above. No other factors are taken into account by
NGET, and it will base its National Electricity Transmission System Demand forecasts on
those factors only.

< END OF OPERATING CODE NO. 1 >

Issue 5 Revision 0 OC1 17 August 2012


5 of 5
OPERATING CODE NO. 2
(OC2)

OPERATIONAL PLANNING AND DATA PROVISION

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC2.1 INTRODUCTION................................................................................................................................... 1
OC2.2 OBJECTIVE .......................................................................................................................................... 2
OC2.3 SCOPE .................................................................................................................................................. 2
OC2.4 PROCEDURE ....................................................................................................................................... 3
OC2.4.1 Co-ordination of outages ............................................................................................................ 3
OC2.4.2 Data Requirements .................................................................................................................. 17
OC2.4.3 Negative Reserve Active Power Margins ................................................................................. 19
OC2.4.4 Frequency Sensitive Operation ................................................................................................ 22
OC2.4.6 Operating Margin Data Requirements ..................................................................................... 22
APPENDIX 1 - PERFORMANCE CHARTS ..................................................................................................... 25
APPENDIX 2 - GENERATION PLANNING PARAMETERS ............................................................................ 27
APPENDIX 3 - CCGT MODULE PLANNING MATRIX .................................................................................... 29
APPENDIX 4 - POWER PARK MODULE PLANNING MATRIX ...................................................................... 30

Issue 5 Revision 18 OC2 11 August 2016


i
OC2.1 INTRODUCTION
OC2.1.1 Operating Code No. 2 ("OC2") is concerned with:
(a) the co-ordination of the release of Synchronous Generating Units and Power Park
Modules, External Interconnections, the National Electricity Transmission System
and Network Operators' Systems for construction, repair and maintenance;
(b) provision by NGET of the Surpluses both for the National Electricity Transmission
System and System Zones;
(c) the provision by Generators of Generation Planning Parameters for Gensets,
including CCGT Module Planning Matrices and Power Park Module Planning
Matrices, to NGET for planning purposes only; and
(d) the agreement for release of Existing Gas Cooled Reactor Plant for outages in certain
circumstances.
OC2.1.2 (a) Operational Planning involves planning, through various timescales, the matching of
generation output with forecast National Electricity Transmission System Demand
together with a reserve of generation to provide a margin, taking into account outages of
certain Generating Units, Power Park Modules, External Interconnections, and DC
Converters, and of parts of the National Electricity Transmission System and of
parts of Network Operators' Systems which is carried out to achieve, so far as
possible, the standards of security set out in NGETs Transmission Licence, each
Relevant Transmission Licensees Transmission Licence or Electricity
Distribution Licence as the case may be.
(b) In general terms there is an "envelope of opportunity" for the release of Synchronous
Generating Units, Power Park Modules and External Interconnections, and for the
release of parts of the National Electricity Transmission System and parts of the
Network Operators User Systems for outages. The envelope is defined by the
difference between the total generation output expected from Large Power Stations,
Medium Power Stations and Demand, the operational planning margin and taking into
account External Interconnections.
OC2.1.3 In this OC2 for the purpose of Generator and Interconnector Owner outage co-ordination
Year 0 means the current calendar year at any time, Year 1 means the next calendar year at
any time, Year 2 means the calendar year after Year 1, etc. For the purpose of
Transmission outage planning Year 0 means the current Financial Year at any time, Year
1 means the next Financial Year at any time, Year 2 means the Financial Year after Year
1, etc. References to weeks in OC2 are to calendar weeks as defined in ISO 8601.
OC2.1.4 References in OC2 to a Generator's and Interconnector Owners "best estimate" shall be
that Generator's or Interconnector Owners best estimate acting as a reasonable and
prudent Generator or Interconnector Owner in all the circumstances.
OC2.1.5 References to NGET planning the National Electricity Transmission System outage
programme on the basis of the Final Generation Outage Programme, are to NGET
planning against the Final Generation Outage Programme current at the time it so plans.
OC2.1.6 Where in OC2 data is required to be submitted or information is to be given on a particular
day, that data does not need to be submitted and that information does not need to be given
on that day if it is not a Business Day or it falls within a holiday period (the occurrence and
length of which shall be determined by NGET, in its reasonable discretion, and notified to
Users). Instead, that data shall be submitted and/or that information shall be given on such
other Business Day as NGET shall, in its reasonable discretion, determine. However,
NGET may determine that that data and/or information need not be submitted or given at all,
in which case it shall notify each User as appropriate.
OC2.1.7 In Scotland, it may be possible with the agreement of NGET to reduce the administrative
burden for Users in producing planning information where either the output or demand is
small.

Issue 5 Revision 18 OC2 11 August 2016


1 of 30
OC2.2 OBJECTIVE
OC2.2.1 (a) The objective of OC2 is to seek to enable NGET to harmonise outages of
Synchronous Generating Units, Power Park Modules and External
Interconnections in order that such outages are co-ordinated (taking account of
Embedded Medium Power Stations) between Generators and Network Operators,
and that such outages are co-ordinated taking into account National Electricity
Transmission System outages and other System outages, so far as possible to
minimise the number and effect of constraints on the National Electricity
Transmission System or any other System.
(b) In the case of Network Operator User Systems directly connected to the National
Electricity Transmission System this means in particular that there will also need to
be harmonisation of outages of Embedded Synchronous Generating Units and
Embedded Power Park Modules, and National Electricity Transmission System
outages, with Network Operators in respect of their outages on those Systems.
OC2.2.2 The objective of OC2 is also to enable the provision by NGET of the Surpluses both for the
National Electricity Transmission System and System Zones.
OC2.2.3 A further objective of OC2 is to provide for the agreement for outages for Existing Gas
Cooled Reactor Plant in certain circumstances and to enable a process to be followed in
order to provide for that.
OC2.2.4 The boundaries of the System Zones will be determined by NGET from time to time taking
into account the disposition of Generators' Power Stations and Interconnector Owners
External Interconnections within the System Zones. The location of the boundaries will be
made available to all Users. Any User may request that NGET reviews any of the System
Zonal boundaries if that User considers that the current boundaries are not appropriate,
giving the reasons for their concerns. On receipt of such a request NGET will review the
boundaries if, in NGET's reasonable opinion, such a review is justified.
OC2.3 SCOPE
OC2.3.1 OC2 applies to NGET and to Users which in OC2 means:
(a) Generators, only in respect of their Large Power Stations or their Power Stations
which are directly connected to National Electricity Transmission System (and the
term Generator in this OC2 shall be construed accordingly);
(b) Network Operators; and
(c) Non-Embedded Customers; and
(d) DC Converter Station owners; and
(e) Interconnector Owners in respect of their External Interconnections.
OC2.3.2 NGET may provide to the Relevant Transmission Licensees any data which has been
submitted to NGET by any Users in respect of Relevant Units pursuant to the following
paragraphs of the OC2.
OC2.4.1.2.1 (a)
OC2.4.1.2.1 (e)
OC2.4.1.2.1 (j)
OC2.4.1.2.2 (a)
OC2.4.1.2.2 (i)
OC2.4.1.3.2 (a)
OC2.4.1.3.2 (b)
OC2.4.1.3.3
OC2.4.2.1 (a)

Issue 5 Revision 18 OC2 11 August 2016


2 of 30
OC2.3.3 For the purpose of OC2 only, the term Output Usable shall include the terms
Interconnector Export Capacity and Interconnector Import Capacity where the term
Output Usable is being applied to an External Interconnection.
OC2.4 PROCEDURE
OC2.4.1 Co-ordination of Outages
OC2.4.1.1 Under OC2 the interaction between NGET and Users will be as follows:

(a) Each Generator, and each In respect of outages of Synchronous Generating


Interconnector Owner and Units, Power Park Modules and External
NGET Interconnection Circuits and in respect of outages
of other Plant and/or Apparatus directly connected
to the National Electricity Transmission System;

(b) NGET and each Generator in respect of National Electricity Transmission


and each Inteconnector System outages relevant to each Generator (other
Owner than in respect of Embedded Small Power
Stations or Embedded Medium Power Stations)
and Interconnector Owner;

(c) NGET and each Network in respect of outages of all Embedded Large Power
Operator Stations and in respect of outages of other Plant
and/or Apparatus relating to such Embedded
Large Power Stations;

(d) NGET and each Network in respect of National Electricity Transmission


Operator and each Non- System outages relevant to the particular Network
Embedded Customer Operator or Non-Embedded Customers;

(e) Each Network Operator and in respect of User System outages relevant to
each Non-Embedded NGET; and
Customer and NGET in respect of Network Operators only, outages of
the Network Operators User System that may
impact upon an Offshore Transmission System
connected to that Network Operators User
System.

OC2.4.1.2 Planning Of Synchronous Generating Unit And External Interconnection And Power Park
Module Outages
OC2.4.1.2.1 Operational Planning Phase - Planning for Calendar Years 3 to 5 inclusive Weekly
Resolution
In each calendar year:
(a) By the end of week 2
Each Generator and each Interconnector Owner will provide NGET in writing with:
(i) a provisional Synchronous Generating Unit and Power Park Module outage
programme (covering all non-Embedded Power Stations and Embedded Large
Power Stations) for Year 3 to Year 5 (inclusive) specifying the Synchronous
Generating Unit and/or Power Park Module and External Interconnection
Circuits and MW concerned, duration of proposed outages, the preferred date for
each outage and where there is a possibility of flexibility, the earliest start date and
latest finishing date; and
(ii) a best estimate weekly Output Usable forecast of all its Gensets and External
Interconnections for Year 3 to Year 5.

(b) Between the end of week 2 and the end of week 12

Issue 5 Revision 18 OC2 11 August 2016


3 of 30
NGET will be:
(i) calculating total winter peak generating capacity assumed to be available to the
Total System;
(ii) calculating the total winter peak generating capacity expected from Large Power
Stations, taking into account Demand forecasts and details of proposed use of
Demand Control received under OC1, and an operational planning margin set by
NGET (the "Operational Planning Margin");
(iii) calculating the weekly peak generating capacity expected from Large Power
Stations taking into account demand forecasts and details of proposed use of
Demand Control received under OC1, and the Operational Planning Margin and
Zonal System Security Requirements. The total weekly peak MW needed to be
available is the "weekly total MW required".
The calculation under (iii) will effectively define the envelope of opportunity for outages
of Synchronous Generating Units and Power Park Modules.
During this period, NGET may, as appropriate, contact each Generator and each
Interconnector Owner who has supplied information to seek clarification on points.
(c) By the end of week 12
NGET will:
(i) having taken into account the information notified to it by Generators and
Interconnector Owners and taking into account:
(1) National Electricity Transmission System constraints and outages,
(2) Network Operator System constraints and outages, known to NGET, and
(3) the Output Usable required, in its view, to meet weekly total MW
requirements,
provide each Generator and each Interconnector Owner in writing with any
suggested amendments to the provisional outage programme supplied by the
Generator and Interconnector Owner which NGET believes necessary, and will
advise Generators with Large Power Stations of the Surpluses both for the
National Electricity Transmission System and System Zones and potential
export limitations, on a weekly basis, which would occur without such
amendments;
(ii) provide each Network Operator in writing with potential outages of Synchronous
Generating Units, External Interconnection Circuits and/or Power Park
Modules which may, in the reasonable opinion of NGET and the Network
Operator, affect the integrity of that Network Operators User System provided
that, in such circumstances NGET has notified the Generator concerned at least
48 hours beforehand of its intention to do so (including identifying the
Synchronous Generating Unit and/or Power Park Module concerned).
(d) By the end of week 14
(i) Where a Generator or Interconnector Owner or a Network Operator is unhappy
with the suggested amendments to its provisional outage programme (in the case
of a Generator or Interconnector Owner) or such potential outages (in the case
of a Network Operator) it may contact NGET to explain its concerns and NGET
and that Generator or an Interconnector Owner or Network Operator will then
discuss the problem and seek to resolve it.
(ii) The possible resolution of the problem may require NGET or a User to contact
other Generators and Network Operators, and joint meetings of all parties may, if
any User feels it would be helpful, be convened by NGET. The need for further
discussions, be they on the telephone or at meetings, can only be determined at
the time.
(e) By the end of week 25
Issue 5 Revision 18 OC2 11 August 2016
4 of 30
Each Generator will provide NGET in writing with an updated provisional Synchronous
Generating Unit and Power Park Module outage programme covering both
Embedded and non-Embedded Large Power Stations together with the best estimate
weekly Output Usable forecasts for each Genset, in all cases for Year 3 to Year 5
(inclusive). The updated provisional Synchronous Generating Unit and Power Park
Module outage programme will contain the MW concerned, duration of proposed
outages, the preferred date for each outage and, where applicable, earliest start date
and latest finishing date, together with an update of the Output Usable estimate
supplied under (a)(ii) above.
Each Interconnector Owner will provide NGET in writing with an updated provisional
External Interconnection Circuit outage programme together with best estimate
weekly Output Usable forecast for each External Interconnection, in all cases for
Year 3 to Year 5 (inclusive). The updated provisional External Interconnection Circuit
outage programme will contain the MW concerned, duration of proposed outages, the
preferred date for each outage and, where applicable, earliest start date and latest
finishing date, together with an update of the Output Usable estimate supplied under
(a)(ii) above.
(f) Between the end of week 25 and the end of week 28
NGET will be considering the updated provisional Synchronous Generating Unit,
Power Park Module and External Interconnection Circuit outage programmes,
together with the best estimate weekly Output Usable forecasts supplied to it by
Generators and Interconnector Owners under (e) and their Registered Capacity and
will be analysing Operational Planning Margins for the period.
(g) By the end of week 28
NGET will:
(i) provide each Generator and each Interconnector Owner in writing with details of
any suggested revisions considered by NGET as being necessary to the updated
provisional Synchronous Generating Unit, Power Park Module and External
Interconnection Circuit outage programmes supplied to NGET under (e) and will
advise Generators with Large Power Stations and Inteconnector Owners of the
Surpluses for the National Electricity Transmission System and System
Zones and potential export limitations on a weekly basis which would occur without
such revisions; and
(ii) provide each Network Operator in writing with the update of potential outages of
Synchronous Generating Units, External Interconnection Circuits and/or
Power Park Modules which, in the reasonable opinion of NGET and the Network
Operator, affect the integrity of that Network Operators User System.
(h) By the end of week 31
Where a Generator, Interconnector Owner or a Network Operator is unhappy with
the revisions suggested to the updated provisional Synchronous Generating Unit,
Power Park Module and External Interconnector Circuit outage programme (in the
case of a Generator) or such update of potential outages (in the case of an
Interconnector Owner or Network Operator) under (g) it may contact NGET to
explain its concerns and the provisions set out in (d) above will apply to that process.

Issue 5 Revision 18 OC2 11 August 2016


5 of 30
(i) By the end of week 42
NGET will:
(1) provide each Generator and each Interconnector Owner in writing with details of
suggested revisions considered by NGET as being necessary to the updated
provisional Synchronous Generating Unit, Power Park Module and External
Inteconnection Circuit outage programmes supplied to NGET and will advise
Generators with Large Power Stations and Interconnector Owners of the
Surpluses for the National Electricity Transmission System and System
Zones and potential export limitations, on a weekly basis which would occur
without such revisions;
(2) provide each Network Operator in writing with the update of potential outages of
Synchronous Generating Units and/or Power Park Modules which may, in the
reasonable opinion of NGET and the Network Operator, affect the integrity of that
Network Operators User System provided that, in such circumstances NGET
has notified the Generator or, as appropriate, the Interconnector Owner
concerned at least 48 hours beforehand of its intention to do so (including
identifying the Synchronous Generating Units and/or Power Park Modules
concerned).
(j) By the end of week 45
NGET will seek to agree a Final Generation Outage Programme for Year 3 to Year 5.
If agreement cannot be reached on all aspects, NGET and each Generator and each
Interconnector Owner will record their agreement on as many aspects as have been
agreed and NGET will advise each Generator with Large Power Stations,
Interconnector Owner and each Network Operator, of the Surpluses for the
National Electricity Transmission System and System Zones on a weekly basis
which would occur in relation to those aspects not agreed. It is accepted that
agreement of the Final Generation Outage Programme is not a commitment on
Generators, Interconnector Owners or NGET to abide by it, but NGET will be
planning the National Electricity Transmission System outage programme on the
basis of the Final Generation Outage Programme and if in the event the Generator's
or the Interconnector Owners outages differ from those contained in the Final
Generation Outage Programme, or in any way conflict with the National Electricity
Transmission System outage programme, NGET need not alter the National
Electricity Transmission System outage programme.
OC2.4.1.2.2 Operational Planning Phase - Planning for Calendar Year 1 and Calendar Year 2 Weekly
Resolution
The basis for Operational Planning for Year 1 and Year 2 will be the Final Generation
Outage Programmes agreed for Years 2 and 3:
In each calendar year:
(a) By the end of week 10
Each Generator and each Interconnector Owner will provide NGET in writing with its
previously agreed Final Generation Outage Programme updated and best estimate
weekly Output Usable forecasts for each Genset and for each External
Interconnection Circuit for weeks 1-52 of Years 1 and 2.

Issue 5 Revision 18 OC2 11 August 2016


6 of 30
(b) Between the end of week 10 and the end of week 12
NGET will be considering the updated proposed Synchronous Generating Unit,
Power Park Module and External Interconnection Circuit outage programme
together with the estimate of Output Usable supplied by Generators and
Interconnector Owners under (a) and will be analysing Operational Planning
Margins for the period. Taking these into account together with National Electricity
Transmission System constraints and outages and Network Operator User System
constraints and outages known to NGET, NGET will assess whether the estimates of
Output Usable supplied by Generators and Interconnector Owners are sufficient to
meet forecast National Electricity Transmission System Demand plus the
Operational Planning Margin.
(c) By the end of week 12
NGET will:
(i) notify each Generator and each Interconnector Owner in writing whether the
Output Usable estimates are adequate for weeks 1-52 of Years 1 and 2, together
with suggested changes to its Final Generation Outage Programme where
necessary and will advise each Generator with Large Power Stations and each
Interconnector Owner of the Surpluses both for the National Electricity
Transmission System and System Zones and potential export limitations, on a
weekly resolution which would occur without such changes;
(ii) provide each Network Operator in writing with weekly Output Usable estimates of
Generators and Interconnector Owners for weeks 1-52 of Years 1 and 2, and
updated details of potential outages of Synchronous Generating Units, Power
Park Modules and/or External Interconnection Circuits which may, in the
reasonable opinion of NGET and the Network Operator, affect the integrity of that
Network Operators User System provided that, in such circumstances, NGET
has notified the Generator or, as appropriate, the Interconnector Owner
concerned at least 48 hours beforehand of its intention to do so (including
identifying the affected Gensets or Synchronous Generating Units or Power
Park Modules and/or External Interconnection Circuits, as appropriate).
(d) By the end of week 14
Where a Generator, Interconnector Owner or a Network Operator is unhappy with
any suggested changes to its Final Generation Outage Programme (in the case of a
Generator) or such update of potential outages (in the case of an Interconnector
Owner or Network Operator), equivalent provisions to those set out in OC2.4.1.2.1(d)
will apply.
(e) By the end of week 34
Each Generator and each Interconnector Owner will provide NGET in writing with
revised best estimate weekly Output Usable forecasts for each Genset or External
Interconnection, as appropriate, for weeks 1-52 of Years 1 and 2.
(f) Between the end of week 34 and the end of week 39
NGET will be analysing the revised estimates of Output Usable supplied by
Generators and Interconnector Owners under (e) and will be analysing Operational
Planning Margins for the period. Taking these into account together with National
Electricity Transmission System constraints and outages and Network Operator
User System constraints and outages known to NGET, NGET will assess whether the
estimates of Output Usable supplied by Generators and Interconnector Owners are
sufficient to meet forecast National Electricity Transmission System Demand plus
the Operational Planning Margin.

Issue 5 Revision 18 OC2 11 August 2016


7 of 30
(g) By the end of week 39
NGET will:
(i) notify each Generator and each Interconnector Owner in writing whether it
accepts the Output Usable estimates for weeks 1-52 of Years 1 and 2, and of any
suggested changes to its Final Generation Outage Programme where necessary
and will advise Generators with Large Power Stations and Interconnector
Owners of the Surpluses both for the National Electricity Transmission System
and System Zones and potential export limitations on a weekly basis which would
occur without such changes;
(ii) provide each Network Operator in writing with Output Usable estimates of
Generators and Interconnector Owners for weeks 1-52 of Years 1 and 2, and
updated details of potential outages of Synchronous Generating Units, Power
Park Modules and/or External Interconnection Circuits which may, in the
reasonable opinion of NGET and the Network Operator, affect the integrity of that
Network Operators User System provided that, in such circumstances, NGET
has notified the Generator or, as appropriate, Interconnector Owner concerned
at least 48 hours beforehand of its intention to do so (including identifying the
affected Gensets or Synchronous Generating Units or Power Park Modules
and/or External Interconnection as appropriate).
(h) By the end of week 46
Where a Generator, an Interconnector Owner or a Network Operator, is unhappy
with any suggested changes to its Final Generation Outage Programme (in the case
of a Generator) or such update of potential outages (in the case of an Interconnector
Owner or Network Operator), equivalent provisions to those set out in OC2.4.1.2.1(d)
will apply.
(i) By the end of week 48
NGET will seek to agree the revised Final Generation Outage Programme for Year 1
and Year 2. If agreement cannot be reached on all aspects, NGET and each
Interconnector Owner and each Generator will record their agreement on as many
aspects as have been agreed and NGET will advise each Generator with Large Power
Stations, Interconnector Owner and each Network Operator, of Generating Plant
Demand Margins for national and zonal groups, on a weekly basis, which would occur
in relation to those aspects not agreed. It is accepted that agreement of the Final
Generation Outage Programme is not a commitment on Generators, Interconnector
Owners or NGET to abide by it, but NGET will be planning the National Electricity
Transmission System outage programme on the basis of the Final Generation
Outage Programme and if, in the event, a Generator's and/or Interconnector
Owners outages differ from those contained in the Final Generation Outage
Programme, or in any way conflict with the National Electricity Transmission
System outage programme, NGET need not alter the National Electricity
Transmission System outage programme.
OC2.4.1.2.3 Planning for Calendar Year 0 Weekly Resolution
The basis for Operational Planning for Year 0 will be the revised Final Generation Outage
Programme agreed for Year 1:
In each week:
(a) By 1600 hours each Wednesday Weekly Resolution
Each Generator and each Interconnector Owner will provide NGET in writing with an
update of the Final Generation Outage Programme and a best estimate weekly
Output Usable forecast for each of its Gensets or its External Interconnection
Circuits, as appropriate, from the 2nd week ahead to the 52nd week ahead.

Issue 5 Revision 18 OC2 11 August 2016


8 of 30
(b) Between 1600 hours Wednesday and 1600 hours Friday
NGET will be analysing the revised estimates of Output Usable supplied by
Generators and Interconnector Owners under (a) and will be analysing Operational
Planning Margins for the period. Taking into account National Electricity
Transmission System constraints and outages and Network Operator User System
constraints and outages known to NGET, NGET will assess whether the estimates of
Output Usable supplied by Generators and Interconnector Owners are sufficient to
meet forecast National Electricity Transmission System Demand plus the
Operational Planning Margin.
(c) By 1600 hours each Friday
NGET will:
(i) notify each Generator with Large Power Stations, Interconnector Owner and
Network Operator, in writing if it considers the Output Usable forecasts will give
Surpluses and potential export limitations both for the National Electricity
nd
Transmission System and System Zones from the 2 week ahead to the 52nd
week ahead;
(ii) provide each Network Operator, in writing with weekly Output Usable estimates
of Gensets and External Interconnection from the 2nd week ahead to the 52nd
week ahead and updated outages of Synchronous Generating Units, Power
Park Modules and/or External Interconnection Circuits which may, in the
reasonable opinion of NGET and the Network Operator, affect the integrity of that
Network Operators User System and in such circumstances, NGET shall notify
the Generator and Interconnector Owner concerned within 48 hours of so
providing (including identifying the affected Gensets or Synchronous Generating
Units and/or Power Park Modules and/or External Interconnection Circuits, as
appropriate), from the 2nd week ahead to the 52nd week ahead.
OC2.4.1.2.4 Programming Phase 2-49 Days Ahead Daily Resolution
(a) By 1200 hours each Friday
NGET will notify in writing each Generator with Large Power Stations, Interconnector
Owner and Network Operator if it considers the Output Usable forecasts will give MW
shortfalls both nationally and for constrained groups for the period 2-7 weeks ahead.
(b) By 1100 hours each Business Day
Each Generator and each Interconnector Owner shall provide NGET in writing with
the best estimate of daily Output Usable for each Genset or each External
Interconnection Circuit as appropriate for the period from and including day 2 ahead
to day 14 ahead, including the forecast return to service date for any such Generating
Unit, Power Park Module or External Interconnection subject to Planned Outage or
breakdown.
(c) By 1100 hours each Wednesday
For the period 2 to 49 days ahead, every Wednesday by 11:00 hours, each Generator
and each Interconnector Owner shall provide NGET in writing best estimate daily
Output Usable forecasts for each Genset or External Interconnection, and changes
(start and finish dates) to Planned Outage or to the return to service times of each
Synchronous Generating Unit, Power Park Module and/or External
Interconnection Circuit which is subject to breakdown.

Issue 5 Revision 18 OC2 11 August 2016


9 of 30
(d) Between 1100 hours and 1600 hours each Business Day
NGET will be analysing the revised estimates of Output Usable supplied by
Generators and Interconnector Owners under (b) and will be analysing Operational
Planning Margins for the period 2-14 days ahead. Taking into account National
Electricity Transmission System constraints and outages and Network Operator
User System constraints and outages known to NGET, NGET will assess whether the
estimates of Output Usable are sufficient to meet forecast National Electricity
Transmission System Demand plus the Operational Planning Margin.
(e) By 1600 hours each Business Day
(i) NGET will notify in writing each Generator with Large Power Stations, each
Interconnector Owner and each Network Operator, of the Surpluses both for
the National Electricity Transmission System and System Zones and potential
export limitations, for the period from and including day 2 ahead to day 14 ahead
which it considers the Output Usable forecasts will give. The time of 1600 hours
can only be met in respect of any Generator, Interconnector Owner or Network
Operator if all the information from all Generators and Interconnector Owners
was made available to NGET by 1100 hours and if a suitable electronic data
transmission facility is in place between NGET and the Generator, or the
Interconnector Owner or the Network Operator, as the case may be, and if it is
fully operational. In the event that any of these conditions is not met, or if it is
necessary to revert to a manual system for analysing the information supplied and
otherwise to be considered, NGET reserve the right to extend the timescale for
issue of the information required under this sub-paragraph to each, or the relevant,
Generator, Interconnector Owner and/or Network Operator (as the case may
be) provided that such information will in any event be issued by 1800 hours.
(ii) NGET will provide each Network Operator, where it has an effect on that User, in
writing with Output Usable estimates of Gensets and External Interconnections
from and including day 2 ahead to day 14 ahead and updated outages of
Synchronous Generating Units, Power Park Modules and/or External
Interconnection Circuits which are either in its User System or which may, in the
reasonable opinion of NGET and the Network Operator, affect the integrity of that
Network Operators User System and in such circumstances, NGET shall notify
the Generator and Interconnector Owner concerned within 48 hours of so
providing (including identifying the affected Gensets or Synchronous Generating
Units or Power Park Modules and/or External Interconnection Circuits, as
appropriate), for the period from and including day 2 ahead to day 14 ahead.
OC2.4.1.3 Planning of National Electricity Transmission System Outages
OC2.4.1.3.1 Operational Planning Phase - Planning for Financial Years 2 to 5 inclusive ahead
NGET shall plan National Electricity Transmission System outages required in Years 2 to
5 inclusive required as a result of construction or refurbishment works. This contrasts with
the planning of National Electricity Transmission System outages required in Years 0 and
1 ahead, when NGET also takes into account National Electricity Transmission System
outages required as a result of maintenance.
Users should bear in mind that NGET will be planning the National Electricity
Transmission System outage programme on the basis of the previous year's Final
Generation Outage Programme and if in the event a Generator's, an Interconnector
Owners or Network Operator's outages differ from those contained in the Final
Generation Outage Programme, or in the case of Network Operators, those known to
NGET, or in any way conflict with the National Electricity Transmission System outage
programme, NGET need not alter the National Electricity Transmission System outage
programme.

Issue 5 Revision 18 OC2 11 August 2016


10 of 30
OC2.4.1.3.2 In each calendar year:
(a) By the end of week 8
Each Network Operator will notify NGET in writing of details of proposed outages in
Years 2-5 ahead in its User System which may affect the performance of the Total
System (which includes but is not limited to outages of User System Apparatus at
Grid Supply Points and outages which constrain the output of Synchronous
Generating Units and/or Power Park Modules Embedded within that User System).
Each Network Operator will notify NGET in writing of details of proposed outages in
Years 2-5 ahead in its User System which may affect the declared values of Maximum
Export Capacity and/or Maximum Import Capacity for each Interface Point within its
User System together with the Network Operators revised best estimate of the
Maximum Export Capacity and/or Maximum Import Capacity during such outages.
Network Operators will also notify NGET of any automatic and/or manual post fault
actions that it intends to utilise or plans to utilise during such outages.
(b) By the end of week 13
Each Generator will inform NGET in writing of proposed outages in Years 2 - 5 ahead
of Generator owned Apparatus (eg. busbar selectors) other than Synchronous
Generating Units, and/or Power Park Modules, at each Grid Entry Point.
NGET will provide to each Network Operator and to each Generator and each
Interconnector Owner a copy of the information given to NGET under paragraph (a)
above (other than the information given by that Network Operator). In relation to a
Network Operator, the data must only be used by that User in planning and operating
that Network Operators User System and must not be used for any other purpose or
passed on to, or used by, any other business of that User or to, or by, any person within
any other such business or elsewhere.
(c) By the end of week 28
NGET will provide each Network Operator in writing with details of proposed outages
in Years 2-5 ahead which may, in NGET's reasonable judgement, affect the
performance of that Network Operators User System.
(d) By the end of week 30
Where NGET or a Network Operator is unhappy with the proposed outages notified to
it under (a), (b) or (c) above, as the case may be, equivalent provisions to those set out
in OC2.4.1.2.1 (d) will apply.
(e) By the end of week 34
NGET will draw up a draft National Electricity Transmission System outage plan
covering the period Years 2 to 5 ahead and NGET will notify each Generator,
Interconnector Owner and Network Operator in writing of those aspects of the plan
which may operationally affect such Generator (other than those aspects which may
operationally affect Embedded Small Power Stations or Embedded Medium Power
Stations), Interconnector Owner or Network Operator. NGET will also indicate where
a need may exist to issue other operational instructions or notifications (including but
not limited to the requirement for the arming of an Operational Intertripping scheme)
or Emergency Instructions to Users in accordance with BC2 to allow the security of
the National Electricity Transmission System to be maintained within the Licence
Standards.
OC2.4.1.3.3 Operational Planning Phase - Planning for Financial Year 1 ahead
Each calendar year NGET shall update the draft National Electricity Transmission
System outage plan prepared under OC2.4.1.3.2 above and shall in addition take into
account outages required as a result of maintenance work.
In each calendar year:
(a) By the end of week 13

Issue 5 Revision 18 OC2 11 August 2016


11 of 30
Generators and Non-Embedded Customers will inform NGET in writing of proposed
outages for Year 1 of Generator owned Apparatus at each Grid Entry Point (e.g.
busbar selectors) other than Synchronous Generating Units and/or Power Park
Modules or Non-Embedded Customer owned Apparatus, as the case may be, at
each Grid Supply Point.
(b) By the end of week 28
NGET will provide each Network Operator and each Non-Embedded Customer in
writing with details of proposed outages in Year 1 ahead which may, in NGET's
reasonable judgement, affect the performance of its User System or the Non-
Embedded Customer Apparatus at the Grid Supply Point.
(c) By the end of week 32
Each Network Operator will notify NGET in writing with details of proposed outages in
Year 1 in its User System which may affect the performance of the Total System
(which includes but is not limited to outages of User System Apparatus at Grid
Supply Points and outages which constrain the output of Synchronous Generating
Units and/or Power Park Modules Embedded within that User System).
Each Network Operator will notify NGET in writing of details of proposed outages in
Year 1 in its User System which may affect the declared values of Maximum Export
Capacity and/or Maximum Import Capacity for each Interface Point within its User
System together with the Network Operators revised best estimate of the Maximum
Export Capacity and/or Maximum Import Capacity during such outages. Network
Operators will also notify NGET of any automatic and/or manual post fault actions that
it intends to utilise or plans to utilise during such outages.
Each Network Operator will also notify NGET in writing of any revisions to Interface
Point Target Voltage/Power Factor data submitted pursuant to PC.A.2.5.4.2.
(d) Between the end of week 32 and the end of week 34
NGET will draw up a revised National Electricity Transmission System outage plan
(which for the avoidance of doubt includes Transmission Apparatus at the
Connection Points).
(e) By the end of week 34
NGET will notify each Generator, Interconnector Owner, and Network Operator, in
writing, of those aspects of the National Electricity Transmission System outage
programme which may, in NGETs reasonable opinion, operationally affect that
Generator (other than those aspects which may operationally affect Embedded Small
Power Stations or Embedded Medium Power Stations), Interconnector Owner, or
Network Operator including in particular proposed start dates and end dates of
relevant National Electricity Transmission System outages.
NGET will provide to each Network Operator and to each Generator and each
Interconnector Owner a copy of the information given to NGET under paragraph (c)
above (other than the information given by that Network Operator). In relation to a
Network Operator, the data must only be used by that User in planning and operating
that Network Operators User System and must not be used for any other purpose or
passed on to, or used by, any other business of that User or to, or by, any person within
any other such business or elsewhere.
(f) By the end of week 36
Where a Generator, Interconnector Owner or Network Operator is unhappy with the
proposed aspects notified to it under (e) above, equivalent provisions to those set out in
OC2.4.1.2.1 (d) will apply.

Issue 5 Revision 18 OC2 11 August 2016


12 of 30
(g) Between the end of week 34 and 49
NGET will draw up a final National Electricity Transmission System outage plan
covering Year 1.
(h) By the end of week 49
(i) NGET will complete the final National Electricity Transmission System outage
plan for Year 1. The plan for Year 1 becomes the final plan for Year 0 when by
expiry of time Year 1 becomes Year 0.
(ii) NGET will notify each Generator, each Interconnector Owner and each Network
Operator in writing of those aspects of the plan which may operationally affect
such Generator (other than those aspects which may operationally affect
Embedded Small Power Stations or Embedded Medium Power Stations),
Interconnector Owner or Network Operator including in particular proposed start
dates and end dates of relevant National Electricity Transmission System
outages. NGET will also indicate where a need may exist to issue other operational
instructions or notifications (including but not limited to the requirement for the
arming of an Operational Intertripping scheme) or Emergency Instructions to
Users in accordance with BC2 to allow the security of the National Electricity
Transmission System to be maintained within the Licence Standards. NGET will
also inform each relevant Non-Embedded Customer of the aspects of the plan
which may affect it.
(iii) In addition, in relation to the final National Electricity Transmission System
outage plan for Year 1, NGET will provide to each Generator and each
Interconnector Owner a copy of the final National Electricity Transmission
System outage plan for that year. OC2.4.1.3.4 contains provisions whereby
updates of the final National Electricity Transmission System outage plan are
provided. The plan and the updates will be provided in writing. It should be noted
that the final National Electricity Transmission System outage plan for Year 1
and the updates will not give a complete understanding of how the National
Electricity Transmission System will operate in real time, where the National
Electricity Transmission System operation may be affected by other factors
which may not be known at the time of the plan and the updates. Therefore, Users
should place no reliance on the plan or the updates showing a set of conditions
which will actually arise in real time.
(i) Information Release Or Exchange
This paragraph (i) contains alternative requirements on NGET, paragraph (z) being an
alternative to a combination of paragraphs (x) and (y). Paragraph (z) will only apply in
relation to a particular User if NGET and that User agree that it should apply, in which
case paragraphs (x) and (y) will not apply. In the absence of any relevant agreement
between NGET and the User, NGET will only be required to comply with paragraphs (x)
and (y).
Information Release To Each Network Operator And Non-Embedded Customer
Between the end of Week 34 and 49 NGET will upon written request:
(x) for radial systems, provide each Network Operator and Non Embedded
Customer with data to allow the calculation by the Network Operator, and each
Non Embedded Customer, of symmetrical and asymmetrical fault levels; and
(y) for interconnected Systems, provide to each Network Operator an equivalent
network, sufficient to allow the identification of symmetrical and asymmetrical fault
levels, and power flows across interconnecting User Systems directly connected
to the National Electricity Transmission System; or
System Data Exchange
(z) as part of a process to facilitate understanding of the operation of the Total
System,

Issue 5 Revision 18 OC2 11 August 2016


13 of 30
(1) NGET will make available to each Network Operator, the National
Electricity Transmission System Study Network Data Files covering Year
1 which are of relevance to that User's System;
(2) where NGET and a User have agreed to the use of data links between them,
the making available will be by way of allowing the User access to take a copy
of the National Electricity Transmission System Study Network Data Files
once during that period. The User may, having taken that copy, refer to the
copy as often as it wishes. Such access will be in a manner agreed by NGET
and may be subject to separate agreements governing the manner of access.
In the absence of agreement, the copy of the National Electricity
Transmission System Study Network Data Files will be given to the User
on a disc, or in hard copy, as determined by NGET;
(3) the data contained in the National Electricity Transmission System Study
Network Data Files represents NGET's view of operating conditions although
the actual conditions may be different;
(4) NGET will notify each Network Operator, as soon as reasonably practicable
after it has updated the National Electricity Transmission System Study
Network Data Files covering Year 1 that it has done so, when this update
falls before the next annual update under this OC2.4.1.3.3(i). NGET will then
make available to each Network Operator who has received an earlier
version (and in respect of whom the agreement still exists), the updated
National Electricity Transmission System Study Network Files covering
the balance of Years 1 and 2 which remain given the passage of time, and
which are of relevance to that User's System. The provisions of paragraphs
(2) and (3) above shall apply to the making available of these updates;
(5) the data from the National Electricity Transmission System Study
Network Data Files received by each Network Operator must only be used
by that User in planning and operating that Network Operators User
System and must not be used for any other purpose or passed on to, or used
by, any other business of that User or to, or by, any person within any other
such business or elsewhere.
OC2.4.1.3.4 Operational Planning Phase - Planning In Financial Year 0 Down To The Programming
Phase (And In The Case Of Load Transfer Capability, Also During The Programming Phase)
(a) The National Electricity Transmission System outage plan for Year 1 issued under
OC2.4.1.3.3 shall become the plan for Year 0 when by expiry of time Year 1 becomes
Year 0.
(b) Each Generator or Interconnector Owner or Network Operator or Non-Embedded
Customer may at any time during Year 0 request NGET in writing for changes to the
outages requested by them under OC2.4.1.3.3. In relation to that part of Year 0,
excluding the period 1-7 weeks from the date of request, NGET shall determine whether
the changes are possible and shall notify the Generator, Interconnector Owner,
Network Operator or Non-Embedded Customer in question whether this is the case
as soon as possible, and in any event within 14 days of the date of receipt by NGET of
the written request in question.
Where NGET determines that any change so requested is possible and notifies the
relevant User accordingly, NGET will provide to each Network Operator, each
Interconnector Owner, and each Generator a copy of the request to which NGET has
agreed which relates to outages on Systems of Network Operators (other than any
request made by that Network Operator). The information must only be used by that
Network Operator in planning and operating that Network Operators User System
and must not be used for any other purpose or passed on to, or used by, any other
business of that User or to, or by, any person within any other such business or
elsewhere.

Issue 5 Revision 18 OC2 11 August 2016


14 of 30
(c) During Year 0 (including the Programming Phase) each Network Operator shall at
NGET's request make available to NGET such details of automatic and manual load
transfer capability of:
(i) 12MW or more (averaged over any half hour) for England and Wales
(ii) 10MW or more (averaged over any half hour) for Scotland
between Grid Supply Points.
During Year 0 (including the Programming Phase) each Network Operator shall notify
NGET of any revisions to the information provided pursuant to OC2.4.1.3.3 (c) for
Interface Points as soon as reasonably practicable after the Network Operator
becomes aware of the need to make such revisions.
(d) When necessary during Year 0, NGET will notify each Generator, each Interconnector
Owner and Network Operator and each Non-Embedded Customer, in writing of
those aspects of the National Electricity Transmission System outage programme in
the period from the 8th week ahead to the 52nd week ahead, which may, in NGET's
reasonable opinion, operationally affect that Generator (other than those aspects which
may operationally affect Embedded Small Power Stations or Embedded Medium
Power Stations) Interconnector Owner or Network Operator or Non-Embedded
Customer including in particular proposed start dates and end dates of relevant
National Electricity Transmission System outages.
NGET will also notify changes to information supplied by NGET pursuant to
OC2.4.1.3.3(i)(x) and (y) except where in relation to a User information was supplied
pursuant to OC2.4.1.3.3(i)(z). In that case:-
(i) NGET will, by way of update of the information supplied by it pursuant to
OC2.4.1.3.3(i)(z), make available at the first time in Year 0 that it updates the
National Electricity Transmission System Study Network Data Files in respect
of Year 0 (such update being an update on what was shown in respect of Year 1
which has then become Year 0) to each Network Operator who has received an
earlier version under OC2.4.1.3.3(i)(z) (and in respect of whom the agreement still
exists), the National Electricity Transmission System Study Network Data
Files covering Year 0 which are of relevance to that User's System.
(ii) NGET will notify each relevant Network Operator, as soon as reasonably
practicable after it has updated the National Electricity Transmission System
Study Network Data Files covering Year 0, that it has done so. NGET will then
make available to each such Network Operator, the updated National Electricity
Transmission System Study Network Data Files covering the balance of Year 0
which remains given the passage of time, and which are of relevance to that
User's System.
(iii) The provisions of OC2.4.1.3.3(i)(z)(2), (3) and (5) shall apply to the provision of
data under this part of OC2.4.1.3.4(d) as if set out in full.
NGET will also indicate where a need may exist to issue other operational instructions
or notifications (including but not limited to the requirement for the arming of an
Operational Intertripping scheme) or Emergency Instructions to Users in
accordance with BC2 to allow the security of the National Electricity Transmission
System to be maintained within the Licence Standards.
(e) In addition, by the end of each month during Year 0, NGET will provide to each
Generator and each Interconnector Owner a notice containing any revisions to the
final National Electricity Transmission System outage plan for Year 1, provided to
the Generator or the Interconnector Owner under OC2.4.1.3.3 or previously under
this provision, whichever is the more recent.

Issue 5 Revision 18 OC2 11 August 2016


15 of 30
OC2.4.1.3.5 Programming Phase
(a) By 1600 hours each Thursday
(i) NGET shall continue to update a preliminary National Electricity Transmission
System outage programme for the eighth week ahead, a provisional National
Electricity Transmission System outage programme for the next week ahead
and a final day ahead National Electricity Transmission System outage
programme for the following day.
(ii) NGET will notify each Generator, Interconnector Owner and Network Operator
and each Non-Embedded Customer, in writing of those aspects of the preliminary
National Electricity Transmission System outage programme which may
operationally affect each Generator (other than those aspects which may
operationally affect Embedded Small Power Stations or Embedded Medium
Power Stations) or Interconnector Owner or Network Operator and each Non-
Embedded Customer including in particular proposed start dates and end dates
of relevant National Electricity Transmission System outages.
NGET will also notify changes to information supplied by NGET pursuant to
OC2.4.1.3.3(i)(x) and (y) except where in relation to a User information was
supplied pursuant to OC2.4.1.3.3(i)(z). In that case:
(1) NGET will, by way of update of the information supplied by it pursuant to
OC2.4.1.3.3(i)(z), make available the National Electricity Transmission
System Study Network Data Files for the next week ahead and
(2) NGET will notify each relevant Network Operator, as soon as reasonably
practicable after it has updated the National Electricity Transmission
System Study Network Data Files covering the next week ahead that it has
done so, and
(3) The provisions of OC2.4.1.3.3(i)(z)(2), (3) and (5) shall apply to the provision
of data under this part of OC2.4.1.3.5(a)(ii) as if set out in full.
NGET may make available the National Electricity Transmission System Study
Network Data Files for the next week ahead where NGET and a particular User
agree, and in such case the provisions of OC2.4.1.1.3.3(i)(x) and (y) and the
provisions of OC2.4.1.3.4(d) and OC2.4.1.3.5(a) which relate to OC2.4.1.1.3.3(i)(x)
and (y) shall not apply. In such case the provisions of this OC2.4.1.3.5(a)(ii)2 and 3
shall apply to the provision of the data under this part of OC2.4.1.3.5(a)(ii) as if set
out in full.
NGET will also indicate where a need may exist to arm an Operational
Intertripping scheme, emergency switching, emergency Demand management or
other measures including the issuing of other operational instructions or
notifications or Emergency Instructions to Users in accordance with BC2 to allow
the security of the National Electricity Transmission System to be maintained
within the Licence Standards.
(b) By 1000 hours each Friday
Generators, Interconnector Owners and Network Operators will discuss with NGET
and confirm in writing to NGET, acceptance or otherwise of the requirements detailed
under OC2.4.1.3.5.
Network Operators shall confirm for the following week:
(i) the details of any outages of its User System that will restrict the Maximum
Export Capacity and/or Maximum Import Capacity at any Interface Points
within its User System for the following week; and
(ii) any changes to the previously declared values of the Interface Point Target
Voltage/Power Factor.

Issue 5 Revision 18 OC2 11 August 2016


16 of 30
(c) By 1600 hours each Friday
(i) NGET shall finalise the preliminary National Electricity Transmission System
outage programme up to the seventh week ahead. NGET will endeavour to give
as much notice as possible to a Generator with nuclear Large Power Stations
which may be operationally affected by an outage which is to be included in such
programme.
(ii) NGET shall finalise the provisional National Electricity Transmission System
outage programme for the next week ahead.
(iii) NGET shall finalise the National Electricity Transmission System outage
programme for the weekend through to the next normal working day.
(iv) In each case NGET will indicate the factors set out in (a)(ii) above (other than
those aspects which may operationally affect Embedded Small Power Stations
or Embedded Medium Power Stations) to the relevant Generators and Network
Operators and Non-Embedded Customers.
(v) Where a Generator with nuclear Large Power Stations which may be
operationally affected by the preliminary National Electricity Transmission
System outage programme referred to in (i) above (acting as a reasonable
operator) is concerned on grounds relating to safety about the effect which an
outage within such outage programme might have on one or more of its nuclear
Large Power Stations, it may contact NGET to explain its concerns and discuss
whether there is an alternative way of taking that outage (having regard to
technical feasibility). If there is such an alternative way, but NGET refuses to adopt
that alternative way in taking that outage, that Generator may involve the
Disputes Resolution Procedure to decide on the way the outage should be
taken. If there is no such alternative way, then NGET may take the outage despite
that Generator's concerns.
(d) By 1600 hours each Monday, Tuesday, Wednesday and Thursday
(i) NGET shall prepare a final National Electricity Transmission System outage
programme for the following day.
(ii) NGET shall notify each Generator and Network Operator and Non-Embedded
Customer in writing of the factors set out in (a)(ii) above (other than those aspects
which may operationally affect Embedded Small Power Stations or Embedded
Medium Power Stations).

OC2.4.2 DATA REQUIREMENTS


OC2.4.2.1 When a Statement of Readiness under the Bilateral Agreement and/or Construction
Agreement is submitted, and thereafter in calendar week 24 in each calendar year,
(a) each Generator shall (subject to OC2.4.2.1(k)) in respect of each of its:-
(i) Gensets (in the case of the Generation Planning Parameters); and
(ii) CCGT Units within each of its CCGT Modules at a Large Power Station (in the
case of the Generator Performance Chart)
submit to NGET in writing the Generation Planning Parameters and the Generator
Performance Chart.
(b) Each shall meet the requirements of CC.6.3.2 and shall reasonably reflect the true
operating characteristics of the Genset.
(c) They shall be applied (unless revised under this OC2 or (in the case of the Generator
Performance Chart only) BC1 in relation to Other Relevant Data) from the
Completion Date, in the case of the ones submitted with the Statement of Readiness,
and in the case of the ones submitted in calendar week 24, from the beginning of week
25 onwards.

Issue 5 Revision 18 OC2 11 August 2016


17 of 30
(d) They shall be in the format indicated in Appendix 1 for these charts and as set out in
Appendix 2 for the Generation Planning Parameters.
(e) Any changes to the Generator Performance Chart or Generation Planning
Parameters should be notified to NGET promptly.
(f) Generators should note that amendments to the composition of the CCGT Module or
Power Park Module at Large Power Stations may only be made in accordance with
the principles set out in PC.A.3.2.3 or PC.A.3.2.4 respectively. If in accordance with
PC.A.3.2.3 or PC.A.3.2.4 an amendment is made, any consequential changes to the
Generation Planning Parameters should be notified to NGET promptly.
(g) The Generator Performance Chart must be as described below and demonstrate the
limitation on reactive capability of the System voltage at 3% above nominal. It must
also include any limitations on output due to the prime mover (both maximum and
minimum), Generating Unit step up transformer or User System.
(i) For a Synchronous Generating Unit on a Generating Unit specific basis at the
Generating Unit Stator Terminals. It must include details of the Generating Unit
transformer parameters.
(ii) For a Non-Synchronous Generating Unit (excluding a Power Park Unit) on a
Generating Unit specific basis at the Grid Entry Point (or User System Entry
Point if Embedded).
(iii) For a Power Park Module, on a Power Park Module specific basis at the Grid
Entry Point (or User System Entry Point if Embedded).
(iv) For a DC Converter on a DC Converter specific basis at the Grid Entry Point (or
User System Entry Point if Embedded).
(h) For each CCGT Unit, and any other Generating Unit or Power Park Module whose
performance varies significantly with ambient temperature, the Generator Performance
Chart shall show curves for at least two values of ambient temperature so that NGET
can assess the variation in performance over all likely ambient temperatures by a
process of linear interpolation or extrapolation. One of these curves shall be for the
ambient temperature at which the Generating Unit's output, or CCGT Module at a
Large Power Station output or Power Park Modules output, as appropriate, equals
its Registered Capacity.
(i) The Generation Planning Parameters supplied under OC2.4.2.1 shall be used by
NGET for operational planning purposes only and not in connection with the operation
of the Balancing Mechanism (subject as otherwise permitted in the BC).
(j) Each Generator shall in respect of each of its CCGT Modules at Large Power
Stations submit to NGET in writing a CCGT Module Planning Matrix. It shall be
prepared on a best estimate basis relating to how it is anticipated the CCGT Module will
be running and which shall reasonably reflect the true operating characteristics of the
CCGT Module. It will be applied (unless revised under this OC2) from the Completion
Date, in the case of the one submitted with the Statement of Readiness, and in the
case of the one submitted in calendar week 24, from the beginning of week 31 onwards.
It must show the combination of CCGT Units which would be running in relation to any
given MW output, in the format indicated in Appendix 3.
Any changes must be notified to NGET promptly. Generators should note that
amendments to the composition of the CCGT Module at Large Power Stations may
only be made in accordance with the principles set out in PC.A.3.2.3. If in accordance
with PC.A.3.2.3 an amendment is made, an updated CCGT Module Planning Matrix
must be immediately submitted to NGET in accordance with this OC2.4.2.1(b).
The CCGT Module Planning Matrix will be used by NGET for operational planning
purposes only and not in connection with the operation of the Balancing Mechanism.

Issue 5 Revision 18 OC2 11 August 2016


18 of 30
(k) Each Generator shall in respect of each of its Cascade Hydro Schemes also submit
the Generation Planning Parameters detailed at OC2.A.2.6 to OC2.A.2.10 for each
Cascade Hydro Scheme. Such parameters need not also be submitted for the
individual Gensets within such Cascade Hydro Scheme.
(l) Each Generator shall in respect of each of its Power Park Modules at Large Power
Stations submit to NGET in writing a Power Park Module Planning Matrix. It shall be
prepared on a best estimate basis relating to how it is anticipated the Power Park
Module will be running and which shall reasonably reflect the operating characteristics
of the Power Park Module and the BM Unit of which it forms part. It will be applied
(unless revised under this OC2) from the Completion Date, in the case of the one
submitted with the Statement of Readiness, and in the case of the one submitted in
calendar week 24, from the beginning of week 31 onwards. It must show the number of
each type of Power Park Unit in the Power Park Module typically expected to be
available to generate and the BM Unit of which it forms part, in the format indicated in
Appendix 4. The Power Park Module Planning Matrix shall be accompanied by a
graph showing the variation in MW output with Intermittent Power Source (e.g. MW vs
wind speed) for the Power Park Module. The graph shall indicate the typical value of
the Intermittent Power Source for the Power Park Module.
Any changes must be notified to NGET promptly. Generators should note that
amendments to the composition of the Power Park Module at Large Power Stations
may only be made in accordance with the principles set out in PC.A.3.2.4. If in
accordance with PC.A.3.2.4 an amendment is made, an updated Power Park Module
Planning Matrix must be immediately submitted to NGET in accordance with this
OC2.4.2.1(a).
The Power Park Module Planning Matrix will be used by NGET for operational
planning purposes only and not in connection with the operation of the Balancing
Mechanism.
(m) For each Synchronous Generating Unit where the Generator intends to adjust the
Generating Unit terminal voltage in response to a MVAr Output Instruction or a Target
Voltage Level instruction in accordance with BC2.A.2.6 the Generator Performance
Chart shall show curves corresponding to the Generating Unit terminal voltage being
controlled to its rated value and to its maximum value.
OC2.4.2.2 Each Network Operator shall by 1000 hrs on the day falling seven days before each
Operational Day inform NGET in writing of any changes to the circuit details called for in
PC.A.2.2.1 which it is anticipated will apply on that Operational Day (under BC1 revisions
can be made to this data).
OC2.4.2.3 Under European Commission Regulation No. 543/2013, Users are required to submit certain
data for publication on the Central European Transparency Platform managed by the
European Network of Transmission System Operators for Electricity (ENTSO-E). NGET is
required to facilitate the collection, verification and processing of data from Users for onward
transmission to the Central European Transparency Platform.
Each Generator and each Non-Embedded Customer connected to or using the National
Electricity Transmission System shall provide NGET with such information as required by
and set out in DRC Schedule 6 (Users Outage Data EU Transparency Availability Data) in
the timescales detailed therein.

OC2.4.3 NEGATIVE RESERVE ACTIVE POWER MARGINS


OC2.4.3.1 In each calendar year, by the end of week 39 NGET will, taking into account the Final
Generation Outage Programme and forecast of Output Usable supplied by each
Generator and by each Interconnector Owner, issue a notice in writing to:-
(a) all Generators with Large Power Stations and to all Interconnector Owners listing
any period in which there is likely to be an unsatisfactory System NRAPM; and

Issue 5 Revision 18 OC2 11 August 2016


19 of 30
(b) all Generators with Large Power Stations and to all Interconnector Owners which
may, in NGET's reasonable opinion be affected, listing any period in which there is
likely to be an unsatisfactory Localised NRAPM, together with the identity of the
relevant System Constraint Group or Groups,
within the next calendar year, together with the margin. NGET and each Generator and
each Interconnector Owner will take these into account in seeking to co-ordinate outages
for that period.
OC2.4.3.2 (a) By 0900 hours each Business Day
Each Generator shall provide NGET in writing with a best estimate of Genset
inflexibility on a daily basis for the period 2 to 14 days ahead (inclusive).
(b) By 1600 hours each Wednesday
Each Generator shall provide NGET in writing with a best estimate of Genset
inflexibility on a weekly basis for the period 2 to 7 weeks ahead (inclusive).
(c) Between 1600 hours each Wednesday and 1200 hours each Friday
(i) If NGET, taking into account the estimates supplied by Generators under (b)
above, and forecast Demand for the period, foresees that:
(1) the level of the System NRAPM for any period within the period 2 to 7 weeks
ahead (inclusive) is too low, it will issue a notice in writing to all Generators,
Interconnector Owners, and Network Operators listing any periods and
levels of System NRAPM within that period; and/or
(2) having also taken into account the appropriate limit on transfers to and from a
System Constraint Group, the level of Localised NRAPM for any period
within the period 2 to 7 weeks ahead (inclusive) is too low for a particular
System Constraint Group, it will issue a notice in writing to all Generators,
Interconnector Owners, and Network Operators which may, in NGET's
reasonable opinion be affected by that Localised NRAPM, listing any periods
and levels of Localised NRAPM within that period. A separate notice will be
given in respect of each affected System Constraint Group.
Outages Adjustments
(ii) NGET will then contact Generators in respect of their Large Power Stations and
Interconnector Owners to discuss outages as set out in the following paragraphs
of this OC2.4.3.2.
(iii) NGET will contact all Generators and Interconnector Owners in the case of low
System NRAPM and will contact Generators in relation to relevant Large Power
Stations and Interconnector Owners in the case of low Localised NRAPM.
NGET will raise with each Generator and Interconnector Owner the problems it
is anticipating due to the low System NRAPM or Localised NRAPM and will
discuss:
(1) whether any change is possible to the estimate of Genset inflexibility given
under (b) above; and
(2) whether Genset or External Interconnection outages can be taken to
coincide with the periods of low System NRAPM or Localised NRAPM (as
the case may be).
In relation to Generators with nuclear Large Power Stations the discussions on
outages can include the issue of whether outages can be taken for re-fuelling
purposes to coincide with the relevant low System NRAPM and/or Localised
NRAPM periods.

Issue 5 Revision 18 OC2 11 August 2016


20 of 30
(iv) If agreement is reached with a Generator or an Interconnector Owner (which
unlike the remainder of OC2 will constitute a binding agreement), then such
Generator or Interconnector Owner will take such outage, as agreed with NGET,
and NGET will issue a revised notice in writing to the Generators, Interconnector
Owners, and Network Operators to which it sent notices under (i) above,
reflecting the changes brought about to the periods and levels of System NRAPM
and/or Localised NRAPM by the agreements with Generators or Interconnector
Owners.
(d) By 1600 hours each day
(i) If NGET, taking into account the estimates supplied under (a) above, and forecast
Demand for the period, foresees that:
(1) the level of System NRAPM for any period within the period of 2 to 14 days
ahead (inclusive) is too low, it will issue a notice in writing to all Generators,
Interconnector Owners, and Network Operators listing the periods and
levels of System NRAPM within those periods; and/or
(2) having also taken into account the appropriate limit on transfers to and from a
System Constraint Group, the level of Localised NRAPM for any period
within the period of 2 to 14 days ahead (inclusive) is too low for a particular
System Constraint Group, it will issue a notice in writing to all Generators,
Interconnector Owners, and Network Operators which may, in NGET's
reasonable opinion be affected by that Localised NRAPM, listing any periods
and levels of Localised NRAPM within that period. A separate notice will be
given in respect of each affected System Constraint Group.
(ii) NGET will contact all Generators in respect of their Large Power Stations (or in
the case of Localised NRAPM, all Generators which may, in NGET's reasonable
opinion be affected, in respect of their relevant Large Power Stations) to discuss
whether any change is possible to the estimate of Genset inflexibility given under
(a) above and to consider Large Power Station outages to coincide with the
periods of low System NRAPM and/or Localised NRAPM (as the case may be).
In the case of External Interconnections, NGET may contact Interconnector
Owners to discuss outages during the periods of low System NRAPM and/or
Localised NRAPM (as the case may be).
(e) If on the day prior to a Operational Day, it is apparent from the BM Unit Data
submitted by Users under BC1 that System NRAPM and/or Localised NRAPM (as the
case may be) is, in NGET's reasonable opinion, too low, then in accordance with the
procedures and requirements set out in BC1.5.5 NGET may contact Users to discuss
whether changes to Physical Notifications are possible, and if they are, will reflect
those in the operational plans for the next following Operational Day or will, in
accordance with BC2.9.4 instruct Generators to De-Synchronise a specified Genset
for such period. In determining which Genset to so instruct, BC2 provides that NGET
will not (other than as referred to below) consider in such determination (and
accordingly shall not instruct to De-Synchronise) any Genset within an Existing Gas
Cooled Reactor Plant. BC2 further provides that:-
(i) NGET is permitted to instruct to De-Synchronise any Gensets within an Existing
AGR Plant if those Gensets within an Existing AGR Plant have failed to offer to
be flexible for the relevant instance at the request of NGET provided the request is
within the Existing AGR Plant Flexibility Limit.

Issue 5 Revision 18 OC2 11 August 2016


21 of 30
(ii) NGET will only instruct to De-Synchronise any Gensets within an Existing
Magnox Reactor Plant or within an Existing AGR Plant (other than under (i)
above) if the level of System NRAPM (taken together with System constraints)
and/or Localised NRAPM is such that it is not possible to avoid De-
Synchronising such Generating Unit, and provided the power flow across each
External Interconnection is either at zero or results in an export of power from the
Total System. This proviso applies in all cases in the case of System NRAPM
and in the case of Localised NRAPM, only when the power flow would have a
relevant effect.

OC2.4.4 FREQUENCY SENSITIVE OPERATION


By 1600 hours each Wednesday
OC2.4.4.1 Using such information as NGET shall consider relevant including, if appropriate, forecast
Demand, any estimates provided by Generators of Genset inflexibility and anticipated plant
mix relating to operation in Frequency Sensitive Mode, NGET shall determine for the
period 2 to 7 weeks ahead (inclusive) whether it is possible that there will be insufficient
Gensets (other than those Gensets within Existing Gas Cooled Reactor Plant which are
permitted to operate in Limited Frequency Sensitive Mode at all times under BC3.5.3) to
operate in Frequency Sensitive Mode for all or any part of that period.
OC2.4.4.2 BC3.5.3 explains that NGET permits Existing Gas Cooled Reactor Plant other than
Frequency Sensitive AGR Units to operate in a Limited Frequency Sensitive Mode at all
times.
OC2.4.4.3 If NGET foresees that there will be an insufficiency in Gensets operating in a Frequency
Sensitive Mode, it will contact Generators in order to seek to agree (as soon as reasonably
practicable) that all or some of the Gensets (the MW amount being determined by NGET but
the Gensets involved being determined by the Generator) will take outages to coincide with
such period as NGET shall specify to enable replacement by other Gensets which can
operate in a Frequency Sensitive Mode. If agreement is reached (which unlike the
remainder of OC2 will constitute a binding agreement) then such Generator will take such
outage as agreed with NGET. If agreement is not reached, then the provisions of BC2.9.5
may apply.
OC2.4.5 If in NGET's reasonable opinion it is necessary for both the procedure set out in OC2.4.3
(relating to System NRAPM and Localised NRAPM) and in OC2.4.4 (relating to operation
in Frequency Sensitive Mode) to be followed in any given situation, the procedure set out
in OC2.4.3 will be followed first, and then the procedure set out in OC2.4.4. For the
avoidance of doubt, nothing in this paragraph shall prevent either procedure from being
followed separately and independently of the other.
OC2.4.6 OPERATING MARGIN DATA REQUIREMENTS
OC2.4.6.1 Modifications to relay settings
Relay settings in this OC2.4.6.1 refers to the settings of Low Frequency Relays in respect
of Gensets that are available for start from standby by Low Frequency Relay initiation with
Fast Start Capability agreed pursuant to the Bilateral Agreement.
By 1600 hours each Wednesday
A change in relay settings will be sent by NGET no later than 1600 hours on a
Wednesday to apply from 1000 hours on the Monday following. The settings allocated
to particular Large Power Stations may be interchanged between 49.70Hz and
49.60Hz (or such other System Frequencies as NGET may have specified) provided
the overall capacity at each setting and System requirements can, in NGET's view, be
met.
Issue 5 Revision 18 OC2 11 August 2016
22 of 30
Between 1600 hours each Wednesday and 1200 hours each Friday
If a Generator wishes to discuss or interchange settings it should contact NGET by
1200 hours on the Friday prior to the Monday on which it would like to institute the
changes to seek NGET's agreement. If NGET agrees, NGET will then send
confirmation of the agreed new settings.
By 1500 hours each Friday
If any alterations to relay settings have been agreed, then the updated version of the
current relay settings will be sent to affected Users by 1500 hours on the Friday prior to
the Monday on which the changes will take effect. Once accepted, each Generator (if
that Large Power Station is not subject to forced outage or Planned Outage) will
abide by the terms of its latest relay settings.
In addition, NGET will take account of any Large Power Station unavailability (as
notified under OC2.4.1.2 submissions) in its total Operating Reserve policy.
NGET may from time to time, for confirmation purposes only, issue the latest version of
the current relay settings to each affected Generator
OC2.4.6.2 Operating Margins
By 1600 hours each Wednesday
No later than 1600 hours on a Wednesday, NGET will provide an indication of the level of
Operating Reserve to be utilised by NGET in connection with the operation of the
Balancing Mechanism in the week beginning with the Operational Day commencing
during the subsequent Monday, which level shall be purely indicative.
This Operating Margin indication will also note the possible level of Operating Reserve (if
any) which may be provided by Interconnector Users in the week beginning with the
Operational Day commencing during the subsequent Monday.
This Operating Margin indication will also note the possible level of High Frequency
Response to be utilised by NGET in connection with the operation of the Balancing
Mechanism in the week beginning with the Operational Day commencing during the
subsequent Monday, which level shall be purely indicative.

OC2.4.7 In the event that:


a) a Non-Embedded Customer experiences the planned unavailability of its Apparatus
resulting in the reduction of Demand of 100MW or more, or a change to the planned
unavailability of its Apparatus resulting in a change in Demand of 100MW or more, for
one Settlement Period or longer; or
b) a Non-Embedded Customer experiences a change in the actual availability of its
Apparatus resulting in a change in Demand of 100MW or greater; or
c) a Generator experiences a planned unavailability of a Generating Unit resulting in a
change of 100MW or more in the Output Usable of that Generating Unit below its
previously notified availability, which is expected to last one Settlement Period or
longer and up to three years ahead; or
d) a Generator experiences a change of 100Mw or more in the Maximum Export Limit of
a Generating Unit which is expected to last one Settlement Period or longer; or
e) a Generator experiences a planned unavailability resulting in a change of 100MW or
more in its aggregated Output Usable below its previously notified availability for a
Power Station with a Registered Capacity of 200MW or more and which is expected
to last one Settlement Period or longer and up to three years ahead, save where
data has been provided pursuant to OC.2.4.7(c) above; or

Issue 5 Revision 18 OC2 11 August 2016


23 of 30
f) a Generator experiences a change of 100MW or more in the aggregated Maximum
Export Limit of a Power Station with a Registered Capacity of 200MW or more,
which is expected to last one Settlement Period or longer, save where data has been
provided pursuant to OC.2.4.7(d) above;
such Non-Embedded Customer or Generator shall provide NGET with the EU
Transparency Availability Data in accordance with DRC Schedule 6 (Users Outage Data)
using MODIS and, with reference to points OC2.4.7(a) to (f), EU Transparency Regulation
articles 7.1(a), 7.1(b), 15.1(a), 15.1(b), 15.1(c) and 15.1(d) respectively.

Issue 5 Revision 18 OC2 11 August 2016


24 of 30
Issue 5 Revision 18
E) User System

(E)

OC2
25 of 30
APPENDIX 1 - PERFORMANCE CHARTS

Where a Reactive Despatch Network Restriction is in place which requires


following of local voltage conditions, alternatively to (E), please check this box.

11 August 2016
POWER PARK MODULE PERFORMANCE CHART AT THE CONNECTION POINT OR USERS SYSTEM
ENTRY POINT

MW
Rated MW F G
Output
100%

50%

20%

MVAr
A E C D B

LEADING LAGGING

Point A is equivalent (in MVAr) to: 0.95 leading Power Factor at Rated MW output

Point B is equivalent (in MVAr) to: 0.95 lagging Power Factor at Rated MW output

Point C is equivalent (in MVAr) to: -5% of Rated MW output

Point D is equivalent (in MVAr) to: +5% of Rated MW output

Point E is equivalent (in MVAr) to: -12% of Rated MW output

Line F is equivalent (in MVAr) to: Leading Power Factor Reactive Despatch Network Restriction

Line G is equivalent (in MVAr) to: Lagging Power Factor Reactive Despatch Network Restriction

Where a Reactive Despatch Network Restriction is in place which requires


following of local voltage conditions, alternatively to Line F and G, please check
this box.

Issue 5 Revision 18 OC2 11 August 2016


26 of 30
APPENDIX 2 - GENERATION PLANNING PARAMETERS
OC2.A.2 Generation Planning Parameters
The following parameters are required in respect of each Genset.

OC2.A.2.1 Regime Unavailability


Where applicable the following information must be recorded for each Genset.
- Earliest synchronising time:
Monday
Tuesday to Friday
Saturday to Sunday
- Latest de-synchronising time:
Monday to Thursday
Friday
Saturday to Sunday

OC2.A.2.2 Synchronising Intervals


(a) The Synchronising interval between Gensets in a Synchronising Group assuming all
Gensets have been Shutdown for 48 hours;
(b) The Synchronising Group within the Power Station to which each Genset should be
allocated.

OC2.A.2.3 De-Synchronising Interval


A fixed value De-Synchronising interval between Gensets within a Synchronising Group.

OC2.A.2.4 Synchronising Generation


The amount of MW produced at the moment of Synchronising assuming the Genset has
been Shutdown for 48 hours.

OC2.A.2.5 Minimum Non-zero time (MNZT)


The minimum period on-load between Synchronising and De-Synchronising assuming the
Genset has been Shutdown for 48 hours.

OC2.A.2.6 Run-Up rates


A run-up characteristic consisting of up to three stages from Synchronising Generation to
Output Usable with up to two intervening break points assuming the Genset has been
Shutdown for 48 hours.

OC2.A.2.7 Run-down rates


A run down characteristic consisting of up to three stages from Output Usable to De-
Synchronising with breakpoints at up to two intermediate load levels.

Issue 5 Revision 18 OC2 11 August 2016


27 of 30
OC2.A.2.8 Notice to Deviate from Zero (NDZ)
The period of time normally required to Synchronise a Genset following instruction from
NGET assuming the Genset has been Shutdown for 48 hours.

OC2.A.2.9 Minimum Zero time (MZT)


The minimum interval between De-Synchronising and Synchronising a Genset.

OC2.A.2.10 Not used.

OC2.A.2.11 Gas Turbine Units loading parameters


- Loading rate for fast starting
- Loading rate for slow starting

Issue 5 Revision 18 OC2 11 August 2016


28 of 30
APPENDIX 3 - CCGT MODULE PLANNING MATRIX
CCGT Module Planning Matrix Example Form

CCGT MODULE CCGT GENERATING UNITS AVAILABLE

1st 2nd 3rd 4th 5th 6th 1st 2nd 3rd


GT GT GT GT GT GT ST ST ST
OUTPUT USABLE
OUTPUT USABLE

150 150 150 100


MW

0MW to 150MW
/

151MW to 250MW
/ /

251MW to 300MW
/ /

301MW to 400MW
/ / /

401MW to 450MW
/ / /

451MW to 550MW
/ / / /

Issue 5 Revision 18 OC2 11 August 2016


29 of 30
APPENDIX 4 - POWER PARK MODULE PLANNING MATRIX
Power Park Module Planning Matrix Example Form
BM Unit Name
Power Park Module [unique identifier]
POWER PARK POWER PARK UNITS
UNIT AVAILABILITY Type A Type B Type C Type D
Description
(Make/Model)

Number of units
Power Park Module [unique identifier]
POWER PARK POWER PARK UNITS
UNIT AVAILABILITY
Type A Type B Type C Type D
Description
(Make/Model)
Number of units

The Power Park Module Planning Matrix may have as many columns as are required to provide
information on the different make and model for each type of Power Park Unit in a Power Park Module and
as many rows as are required to provide information on the Power Park Modules within each BM Unit. The
description is required to assist identification of the Power Park Units within the Power Park Module and
correlation with data provided under the Planning Code.

< END OF OPERATING CODE NO. 2 >

Issue 5 Revision 18 OC2 11 August 2016


30 of 30
OPERATING CODE NO. 3
(OC3)

NOT USED

< END OF OPERATING CODE NO. 3 >

Issue 5 Revision 0 OC3 17 August 2012


i
OPERATING CODE NO. 4
(OC4)

NOT USED

< END OF OPERATING CODE NO. 4 >

Issue 5 Revision 0 OC4 17 August 2012


i
OPERATING CODE NO. 5
(OC5)

TESTING AND MONITORING

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC5.1 INTRODUCTION ................................................................................................................................ 2
OC5.2 OBJECTIVE ........................................................................................................................................ 3
OC5.3 SCOPE ............................................................................................................................................... 3
OC5.4 MONITORING .................................................................................................................................... 3
OC5.4.1 Parameters To Be Monitored .................................................................................................... 3
OC5.4.2 Procedure For Monitoring ......................................................................................................... 3
OC5.5 PROCEDURE FOR TESTING ............................................................................................................ 4
OC5.5.1 NGET Instruction For Testing ................................................................................................... 4
OC5.5.2 User Request For Testing ......................................................................................................... 5
OC5.5.3 Conduct Of Test ....................................................................................................................... 5
OC5.5.4 Test And Monitoring Assessment ............................................................................................. 5
OC5.5.5 Test Failure / Re-test ................................................................................................................ 8
OC5.5.6 Dispute Following Re-test ......................................................................................................... 9
OC5.6 DISPUTE RESOLUTION .................................................................................................................... 9
OC5.7 BLACK START TESTING ................................................................................................................... 9
OC5.7.1 General .................................................................................................................................... 9
OC5.7.2 Procedure For A Black Start Test ........................................................................................... 10
OC5.8 PROCEDURES APPLYING TO EMBEDDED MEDIUM POWER STATION NOT SUBJECT
TO A BILATERAL AGREEMENT AND EMBEDDED DC CONVERTER STATIONS NOT SUBJECT
TO A BILATERAL AGREEMENT ................................................................................................................... 11
APPENDIX 1 - ONSITE SIGNAL PROVISION FOR WITNESSING TESTS ................................................... 13
APPENDIX 2 - COMPLIANCE TESTING OF SYNCHRONOUS PLANT ........................................................ 16
APPENDIX 3 - COMPLIANCE TESTING OF POWER PARK MODULES ...................................................... 26
APPENDIX 4 - COMPLIANCE TESTING FOR DC CONVERTERS AT A DC CONVERTER STATION ......... 36

Issue 5 Revision 15 OC5 3 February 2016


i
OC5.1 INTRODUCTION
Operating Code No. 5 ("OC5") specifies the procedures to be followed by NGET in carrying
out:
(a) monitoring
(i) of BM Units against their expected input or output;
(ii) of compliance by Users with the CC and in the case of response to Frequency,
BC3; and
(iii) of the provision by Users of Ancillary Services which they are required or have
agreed to provide; and
(b) the following tests (which are subject to System conditions prevailing on the day):
(i) tests on Gensets, CCGT Modules, Power Park Modules, DC Converters,
OTSUA (prior to the OTSUA Transfer Time) and Generating Units (excluding
Power Park Units) to test that they have the capability to comply with the CC and,
in the case of response to Frequency, BC3 and to provide the Ancillary Services
that they are either required or have agreed to provide;
(ii) tests on BM Units, to ensure that the BM Units are available in accordance with
their submitted Export and Import Limits, QPNs, Joint BM Unit Data and
Dynamic Parameters.
The OC5 tests include the Black Start Test procedure.
OC5 also specifies in OC5.8 the procedures which apply to the monitoring and testing of
Embedded Medium Power Stations not subject to a Bilateral Agreement and Embedded
DC Converter Stations not subject to a Bilateral Agreement.
In respect of a Cascade Hydro Scheme the provisions of OC5 shall be applied as follows:
(a) in respect of the BM Unit for the Cascade Hydro Scheme the parameters referred to at
OC5.4.1 (a) and (c) in respect of Commercial Ancillary Services will be monitored and
tested;
(b) in respect of each Genset forming part of the Cascade Hydro Scheme the parameters
referred to at OC5.4.1 (a), (b) and (c) will be tested and monitored. In respect of
OC5.4.1 (a) the performance of the Gensets will be tested and monitored against their
expected input or output derived from the data submitted under BC1.4.2(a)(2). Where
necessary to give effect to the requirements for Cascade Hydro Schemes in the
following provisions of OC5 the term Genset will be read and construed in the place of
BM Unit.
In respect of Embedded Exemptable Large Power Stations the provisions of OC5 shall be
applied as follows:
(a) where there is a BM Unit registered in the BSC in respect of Generating Units the
provisions of OC5 shall apply as written;
(b) in all other cases, in respect of each Generating Unit the parameters referred to at
OC5.4.1(a), (b) and (c) will be tested and monitored. In respect of OC5.4.1(a) the
performance of the Generating Unit will be tested and monitored against their expected
input or output derived from the data submitted under BC1.4.2(a)(2). Where necessary
to give effect to the requirements for such Embedded Exemptable Large Power
Stations in the provisions of OC5 the term Generating Unit will be read and construed
in place of BM Unit.

Issue 5 Revision 15 OC5 03 February 2016


2 of 42
OC5.2 OBJECTIVE
The objectives of OC5 are to establish:
(a) that Users comply with the CC (including in the case of OTSUA prior to the OTSUA
Transfer Time);
(b) whether BM Units operate in accordance with their expected input or output derived
from their Final Physical Notification Data and agreed Bid-Offer Acceptances issued
under BC2;
(c) whether each BM Unit is available as declared in accordance with its submitted Export
and Import Limits, QPN, Joint BM Unit Data and Dynamic Parameters; and
(d) whether Generators, DC Converter Station owners and Suppliers can provide those
Ancillary Services which they are either required or have agreed to provide.
In certain limited circumstances as specified in this OC5 the output of CCGT Units may be
verified, namely the monitoring of the provision of Ancillary Services and the testing of
Reactive Power and automatic Frequency Sensitive Operation.

OC5.3 SCOPE
OC5 applies to NGET and to Users, which in OC5 means:
(a) Generators (including those undertaking OTSDUW);
(b) Network Operators;
(c) Non-Embedded Customers;
(d) Suppliers; and
(e) DC Converter Station owners.

OC5.4 MONITORING
OC5.4.1 Parameters To Be monitored
NGET will monitor the performance of:
(a) BM Units against their expected input or output derived from their Final Physical
Notification Data and agreed Bid-Offer Acceptances issued under BC2;
(b) compliance by Users with the CC; and
(c) the provision by Users of Ancillary Services which they are required or have agreed to
provide.
OC5.4.2 Procedure For Monitoring
OC5.4.2.1 In the event that a BM Unit fails persistently, in NGET's reasonable view, to follow, in any
material respect, its expected input or output or a User fails persistently to comply with the
CC and in the case of response to Frequency, BC3 or to provide the Ancillary Services it
is required, or has agreed, to provide, NGET shall notify the relevant User giving details of
the failure and of the monitoring that NGET has carried out.
OC5.4.2.2 The relevant User will, as soon as possible, provide NGET with an explanation of the
reasons for the failure and details of the action that it proposes to take to:
(a) enable the BM Unit to meet its expected input or output or to provide the Ancillary
Services it is required or has agreed to provide, within a reasonable period, or
(b) in the case of a Generating Unit (excluding a Power Park Unit), CCGT Module,
Power Park Module, OTSUA (prior to the OTSUA Transfer Time) or DC Converter to
comply with the CC and in the case of response to Frequency, BC3 or to provide the
Ancillary Services it is required or has agreed to provide, within a reasonable period.
OC5.4.2.3 NGET and the User will then discuss the action the User proposes to take and will
endeavour to reach agreement as to:

Issue 5 Revision 15 OC5 03 February 2016


3 of 42
(a) any short term operational measures necessary to protect other Users; and
(b) the parameters which are to be submitted for the BM Unit and the effective date(s) for
the application of the agreed parameters.
OC5.4.2.4 In the event that agreement cannot be reached within 10 days of notification of the failure by
NGET to the User, NGET or the User shall be entitled to require a test, as set out in OC5.5
and OC5.6, to be carried out.
OC5.5 PROCEDURE FOR TESTING
OC5.5.1 NGET Instruction For Testing
OC5.5.1.1 NGET may at any time (although not normally more than twice in any calendar year in
respect of any particular BM Unit) issue an instruction requiring a User to carry out a test,
provided NGET has reasonable grounds of justification based upon:
(a) a failure to agree arising from the process in CP.8.1; or
(b) monitoring carried out in accordance with OC5.4.2.
OC5.5.1.2 The test, referred to in OC5.5.1.1 and carried out at a time no sooner than 48 hours from the
time that the instruction was issued, on any one or more of the Users BM Units should only
be to demonstrate that the relevant BM Unit:
(a) if active in the Balancing Mechanism, meets the ability to operate in accordance with
its submitted Export and Import Limits, QPN, Joint BM Unit Data and Dynamic
Parameters and achieve its expected input or output which has been monitored under
OC5.4; and
(b) meets the requirements of the paragraphs in the CC which are applicable to such BM
Units; and
in the case of a BM Unit comprising a Generating Unit, a CCGT Module, a Power Park
Module or a DC Converter meets,
(c) the requirements for operation in Frequency Sensitive Mode and compliance with the
requirements for operation in Limited Frequency Sensitive Mode in accordance with
CC.6.3.3, BC3.5.2 and BC3.7.2; or
(d) the terms of the applicable Supplemental Agreement agreed with the Generator to
have a Fast Start Capability; or
(e) the Reactive Power capability registered with NGET under OC2 which shall meet the
requirements set out in CC.6.3.2. In the case of a test on a Generating Unit within a
CCGT Module the instruction need not identify the particular CCGT Unit within the
CCGT Module which is to be tested, but instead may specify that a test is to be carried
out on one of the CCGT Units within the CCGT Module.
OC5.5.1.3 (a) The instruction referred to in OC5.5.1.1 may only be issued if the relevant User has
submitted Export and Import Limits which notify that the relevant BM Unit is available
in respect of the Operational Day current at the time at which the instruction is issued.
The relevant User shall then be obliged to submit Export and Import Limits with a
magnitude greater than zero for that BM Unit in respect of the time and the duration
that the test is instructed to be carried out, unless that BM Unit would not then be
available by reason of forced outage or Planned Outage expected prior to this
instruction.
(b) In the case of a CCGT Module the Export and Import Limits data must relate to the
same CCGT Units which were included in respect of the Operational Day current at
the time at which the instruction referred to in OC5.5.1.1 is issued and must include, in
relation to each of the CCGT Units within the CCGT Module, details of the various data
set out in BC1.A.1.3 and BC1.A.1.5, which parameters NGET will utilise in instructing in
accordance with this OC5 in issuing Bid-Offer Acceptances. The parameters shall
reasonably reflect the true operating characteristics of each CCGT Unit.

Issue 5 Revision 15 OC5 03 February 2016


4 of 42
(c) The test referred to in OC5.5.1.1 will be initiated by the issue of instructions, which may
be accompanied by a Bid-Offer Acceptance, under BC2 (in accordance with the
Export and Import Limits, QPN, Joint BM Unit Data and Dynamic Parameters which
have been submitted for the day on which the test was called, or in the case of a CCGT
Unit, in accordance with the parameters submitted under OC5.5.1.3(b)). The
instructions in respect of a CCGT Unit within a CCGT Module will be in respect of the
CCGT Unit, as provided in BC2.
OC5.5.2 User Request For Testing
OC5.5.2.1 Where a User undertakes a test to demonstrate compliance with the Grid Code and
Bilateral Agreement in accordance with CP.6 or CP.7 or CP.8 (other than a failure between
NGET and a User to agree in CP.8.1 where OC5.5.1.1 applies) the User shall request
permission to test using the process laid out in OC7.5.
OC5.5.3 Conduct Of Test
OC5.5.3.1 The performance of the BM Unit will be recorded at Transmission Control Centres notified
by NGET with monitoring at site when necessary, from voltage and current signals provided
by the User for each BM Unit under CC.6.6.1.
OC5.5.3.2 If monitoring at site is undertaken, the performance of the BM Unit will be recorded on a
suitable recorder (with measurements, in the case of a Synchronous Generating Unit,
taken on the Generating Unit Stator Terminals / on the LV side of the generator
transformer) or in the case of a Non-Synchronous Generating Unit (excluding Power Park
Units), Power Park Module or DC Converter at the point of connection (including where
the OTSUA is operational prior to the OTSUA Transfer Time, the Transmission Interface
Point) in the relevant Users Control Room, in the presence of a reasonable number of
representatives appointed and authorised by NGET. If NGET or the User requests,
monitoring at site will include measurement of the parameters set out in OC5.A.1 or OC5.A.2
as appropriate.
OC5.5.3.3 The User is responsible for carrying out the test and retains the responsibility for the safety
of personnel and plant during the test.
OC5.5.4 Test And Monitoring Assessment
The criteria must be read in conjunction with the full text under the Grid Code reference. The
BM Unit, CCGT Module, Power Park Module or Generating Unit (excluding Power Park
Units) and OTSUA will pass the test the criteria below are met:

Issue 5 Revision 15 OC5 03 February 2016


5 of 42
Criteria against which the test results will be assessed
Parameter to be Tested
by NGET.

Harmonic Content CC.6.1.5(a) Measured harmonic emissions do not


exceed the limits specified in the Bilateral Agreement
or where no such limits are specified, the relevant
planning level specified in G5/4.

Phase Unbalance CC.6.1.5(b), The measured maximum Phase (Voltage)


Unbalance on the National Electricity Transmission
System should remain, in England and Wales, below
1% and, in Scotland, below 2% and Offshore will be
defined in relevant Bilateral Agreement.
CC.6.1.6 In England and Wales, measured infrequent
short duration peaks in Phase (Voltage) Unbalance
should not exceed the maximum value stated in the
Bilateral Agreement.

Voltage Fluctuation CC.6.1.7(a) In England and Wales, measured voltage


Voltage Quality

fluctuations at the Point of Common Coupling shall


not exceed 1% of the voltage level for step changes.
Measured voltage excursions other than step changes
may be allowed up to a level of 3%. In Scotland,
measured voltage fluctuations at a Point of Common
Coupling shall not exceed the limits set out in
Engineering Recommendation P28.

Flicker CC.6.1.7(b) Measured voltage fluctuations at a Point of


Common Coupling shall not exceed, for voltages
above 132kV, Flicker Severity (Short Term) of 0.8
Unit and Flicker Severity (Long Term) of 0.6 Unit,
and, for voltages at 132kV and below, shall not exceed
Flicker Severity (Short Term) of 1.0 Unit and Flicker
Severity (Long Term) of 0.8 Unit, as set out in
Engineering Recommendation P28 as current at the
Transfer Date.

Voltage Fluctuation CC.6.1.8 Offshore, measured voltage fluctuations at


the Point of Common Coupling shall not exceed the
limits set out in the Bilateral Agreement.

Fault Clearance Times CC.6.2.2.2.2(a), CC.6.2.3.1.1(a), Bilateral Agreement


Fault Clearance

Back Up Protection CC.6.2.2.2.2(b), CC.6.2.3.1.1(b) , Bilateral Agreement

Circuit Breaker Fail CC.6.2.2.2.2(c), CC.6.2.3.1.1(c)


Protection

Issue 5 Revision 15 OC5 03 February 2016


6 of 42
Criteria against which the test results will be assessed
Parameter to be Tested
by NGET.

Reactive Capability CC.6.3.2 (and in the case of CC.6.3.2(e)(iii), the


Bilateral Agreement), CC.6.3.4, Ancillary Services
Agreement.
For a test initiated under OC.5.5.1.1 the Generating
Unit, DC Converter or Power Park Module or (prior to
the OTSUA Transfer Time) OTSUA will pass the test if
it is within 5% of the reactive capability registered with
NGET under OC2. the duration of the test will be for a
period of upto 60 minutes during which period the
system voltage at the Grid Entry Point for the relevant
Generating Unit, DC Converter or Power Park
Module or Interface Point in the case of OTSUA will
be maintained by the Generator or DC Converter
Station owner at the voltage specified pursuant to
BC2.8 by adjustment of Reactive Power on the
remaining Generating Unit, DC Converter or Power
Park Modules or OTSUA, if necessary. Any test
performed in respect of an Embedded Medium Power
Station not subject to a Bilateral Agreement or, an
Embedded DC Converter Station not subject to a
Bilateral Agreement shall be as confirmed pursuant to
OC5.8.3.
Measurements of the Reactive Power output under
steady state conditions should be consistent with Grid
Code requirements i.e. fully available within the voltage
range 5% at 400kV, 275kV and 132kV and lower
voltages.

Primary Secondary and Ancillary Services Agreement, CC.6.3.7 and where


High Frequency applicable CC.A.3
Response
For a test initiated under OC.5.5.1.1 the measured
response in MW/Hz is within 5% of the level of
response specified in the Ancillary Services
Governor / Frequency Control

Agreement for that Genset.

Stability with Voltage CC.6.3.4

Governor / Load / CC.6.3.6(a), CC.6.3.7, CC.6.3.9, CC8.1, where


Frequency Controller applicable CC.A.3, BC3.5, BC3.6, BC3.7
System Compliance

Output at Reduced CC.6.3.3 - For variations in System Frequency


System Frequency exceeding 0.1Hz within a period of less than 10
seconds, the Active Power output is within 0.2% of
the requirements of CC.6.3.3 when monitored at
prevailing external air temperatures of up to 25C.,
BC3.5.1

Fast Start Ancillary Services Agreement requirements

Black Start OC5.7

Issue 5 Revision 15 OC5 03 February 2016


7 of 42
Criteria against which the test results will be assessed
Parameter to be Tested
by NGET.

Excitation/Voltage Control CC.6.3.6(b), CC.6.3.8, CC.A.6 or CC.A.7 as applicable,


System BC2.11.2, Bilateral Agreement

Fault Ride Through CC.6.3.15, CC.A.4.A or CC.A.4.B as applicable

Export and Import BC2


Limits, QPN, Joint BM
The Export and Import Limits, QPN, Joint BM Unit
Unit Data and Dynamic
Data and Dynamic Parameters under test are within
Parameters
2% of the declared value being tested.

Synchronisation time BC2.5.2.3


Synchronisation takes place within 5 minutes of the
time it should have achieved Synchronisation.
Dynamic Parameters

Run-up rates BC2


Achieves the instructed output and, where applicable,
the first and/or second intermediate breakpoints, each
within 3 minutes of the time it should have reached
such output and breakpoints from Synchronisation (or
break point, as the case may be), calculated from the
run-up rates in its Dynamic Parameters.

Run-down rates BC2


Achieves the instructed output and, where applicable,
the first and/or second intermediate breakpoints, each
within 5 minutes of the time it should have reached
such output and breakpoints from Synchronisation (or
break point, as the case may be), calculated from the
run-up rates in its Dynamic Parameters.

OC5.5.4.1 The duration of the Dynamic Parameter tests in the above table will be consistent with and
sufficient to measure the relevant expected input or output derived from the Final Physical
Notification Data and Bid-Offer Acceptances issued under BC2 which are still in dispute
following the procedure in OC5.4.2.
OC5.5.4.2 Due account will be taken of any conditions on the System which may affect the results of
the test. The relevant User must, if requested, demonstrate, to NGET's reasonable
satisfaction, the reliability of the suitable recorders, disclosing calibration records to the
extent appropriate.
OC5.5.5 Test Failure / Re-test
OC5.5.5.1 If the BM Unit, CCGT Modules, Power Park Module, OTSUA, or Generating Unit
(excluding Power Park Units) concerned fails to pass the test instructed by NGET under
OC5.5.1.1 the User must provide NGET with a written report specifying in reasonable detail
the reasons for any failure of the test so far as they are then known to the User after due and
careful enquiry. This must be provided within five Business Days of the test.

Issue 5 Revision 15 OC5 03 February 2016


8 of 42
OC5.5.5.2 If in NGETs reasonable opinion the failure to pass the test relates to compliance with the CC
then NGET may invoke the process detailed in CP.8.2 to CP.11.
OC5.5.5.3 If a dispute arises relating to the failure, NGET and the relevant User shall seek to resolve
the dispute by discussion, and, if they fail to reach agreement, the User may by notice
require NGET to carry out a re-test on 48 hours' notice which shall be carried out following
the procedure set out in OC5.5.3 and OC5.5.4 and subject as provided in OC5.5.1.3, as if
NGET had issued an instruction at the time of notice from the User.
OC5.5.6 Dispute Following Re-Test
If the BM Unit, CCGT Module, Power Park Module, OTSUA, or Generating Unit
(excluding Power Park Units) in NGET's view fails to pass the re-test and a dispute arises
on that re-test, either party may use the Disputes Resolution Procedure for a ruling in
relation to the dispute, which ruling shall be binding.

OC5.6 DISPUTE RESOLUTION


OC5.6.1 If following the procedure set out in OC5.5 it is accepted that the BM Unit, CCGT Module,
Power Park Module, OTSUA (prior to the OTSUA Transfer Time) or Generating Unit
(excluding Power Park Units) has failed the test or re-test (as applicable), the User shall
within 14 days, or such longer period as NGET may reasonably agree, following such failure,
submit in writing to NGET for approval the date and time by which the User shall have
brought the BM Unit concerned to a condition where it complies with the relevant
requirement. NGET will not unreasonably withhold or delay its approval of the Users
proposed date and time submitted. Should NGET not approve the Users proposed date or
time (or any revised proposal), the User should amend such proposal having regard to any
comments NGET may have made and re-submit it for approval.
OC5.6.2 If a BM Unit fails the test, the User shall submit revised Export and Import Limits, QPN,
Joint BM Unit Data and/or Dynamic Parameters, or in the case of a BM Unit comprising a
Generating Unit, CCGT Module, DC Converter, OTSUA (prior to the OTSUA Transfer
Time) or Power Park Module, the User may amend, with NGET's approval, the relevant
registered parameters of that Generating Unit, CCGT Module, DC Converter, OTSUA
(prior to the OTSUA Transfer Time) or Power Park Module, as the case may be, relating to
the criteria, for the period of time until the BM Unit can achieve the parameters previously
registered, as demonstrated in a re-test.
OC5.6.3 Once the User has indicated to NGET the date and time that the BM Unit, CCGT Module,
Power Park Module, Generating Unit (excluding Power Park Units) or OTSUA (prior to
the OTSUA Transfer Time) can achieve the parameters previously registered or submitted,
NGET shall either accept this information or require the User to demonstrate the restoration
of the capability by means of a repetition of the test referred to in OC5.5.3 by an instruction
requiring the User on 48 hours notice to carry out such a test. The provisions of this OC5.6
will apply to such further test.
OC5.7 BLACK START TESTING
OC5.7.1 General
(a) NGET may require a Generator with a Black Start Station to carry out a test (a "Black
Start Test") on a Genset in a Black Start Station either while the Black Start Station
remains connected to an external alternating current electrical supply (a "BS Unit Test")
or while the Black Start Station is disconnected from all external alternating current
electrical supplies (a "BS Station Test"), in order to demonstrate that a Black Start
Station has a Black Start Capability.
(b) Where NGET requires a Generator with a Black Start Station to carry out a BS Unit
Test, NGET shall not require the Black Start Test to be carried out on more than one
Genset at that Black Start Station at the same time, and would not, in the absence of
exceptional circumstances, expect any of the other Genset at the Black Start Station
to be directly affected by the BS Unit Test.

Issue 5 Revision 15 OC5 03 February 2016


9 of 42
(c) NGET may require a Generator with a Black Start Station to carry out a BS Unit Test
at any time (but will not require a BS Unit Test to be carried out more than once in each
calendar year in respect of any particular Genset unless it can justify on reasonable
grounds the necessity for further tests or unless the further test is a re-test, and will not
require a BS Station Test to be carried out more than once in every two calendar years
in respect of any particular Genset unless it can justify on reasonable grounds the
necessity for further tests or unless the further test is a re-test).
(d) When NGET wishes a Generator with a Black Start Station to carry out a Black Start
Test, it shall notify the relevant Generator at least 7 days prior to the time of the Black
Start Test with details of the proposed Black Start Test.
OC5.7.2 Procedure For A Black Start Test
The following procedure will, so far as practicable, be carried out in the following sequence
for Black Start Tests:
OC5.7.2.1 BS Unit Tests
(a) The relevant Generating Unit shall be Synchronised and Loaded;
(b) All the Auxiliary Gas Turbines and/or Auxiliary Diesel Engines in the Black Start
Station in which that Generating Unit is situated, shall be Shutdown.
(c) The Generating Unit shall be De-Loaded and De-Synchronised and all alternating
current electrical supplies to its Auxiliaries shall be disconnected.
(d) The Auxiliary Gas Turbine(s) or Auxiliary Diesel Engine(s) to the relevant
Generating Unit shall be started, and shall re-energise the Unit Board of the relevant
Generating Unit.
(e) The Auxiliaries of the relevant Generating Unit shall be fed by the Auxiliary Gas
Turbine(s) or Auxiliary Diesel Engine(s), via the Unit Board, to enable the relevant
Generating Unit to return to Synchronous Speed.
(f) The relevant Generating Unit shall be Synchronised to the System but not Loaded,
unless the appropriate instruction has been given by NGET under BC2.
OC5.7.2.2 BS Station Test
(a) All Generating Units at the Black Start Station, other than the Generating Unit on
which the Black Start Test is to be carried out, and all the Auxiliary Gas Turbines
and/or Auxiliary Diesel Engines at the Black Start Station, shall be Shutdown.
(b) The relevant Generating Unit shall be Synchronised and Loaded.
(c) The relevant Generating Unit shall be De-Loaded and De-Synchronised.
(d) All external alternating current electrical supplies to the Unit Board of the relevant
Generating Unit, and to the Station Board of the relevant Black Start Station, shall
be disconnected.
(e) An Auxiliary Gas Turbine or Auxiliary Diesel Engine at the Black Start Station shall
be started, and shall re-energise either directly, or via the Station Board, the Unit
Board of the relevant Generating Unit.
(f) The provisions of OC5.7.2.1 (e) and (f) shall thereafter be followed.
OC5.7.2.3 All Black Start Tests shall be carried out at the time specified by NGET in the notice given
under OC5.7.1(d) and shall be undertaken in the presence of a reasonable number of
representatives appointed and authorised by NGET, who shall be given access to all
information relevant to the Black Start Test.
OC5.7.2.4 Failure of a Black Start Test
A Black Start Station shall fail a Black Start Test if the Black Start Test shows that it does
not have a Black Start Capability (ie. if the relevant Generating Unit fails to be
Synchronised to the System within two hours of the Auxiliary Gas Turbine(s) or Auxiliary
Diesel Engine(s) being required to start).

Issue 5 Revision 15 OC5 03 February 2016


10 of 42
OC5.7.2.5 If a Black Start Station fails to pass a Black Start Test the Generator must provide NGET
with a written report specifying in reasonable detail the reasons for any failure of the test so
far as they are then known to the Generator after due and careful enquiry. This must be
provided within five Business Days of the test. If a dispute arises relating to the failure,
NGET and the relevant Generator shall seek to resolve the dispute by discussion, and if
they fail to reach agreement, the Generator may require NGET to carry out a further Black
Start Test on 48 hours notice which shall be carried out following the procedure set out in
OC5.7.2.1 or OC5.7.2.2 as the case may be, as if NGET had issued an instruction at the
time of notice from the Generator.
OC5.7.2.6 If the Black Start Station concerned fails to pass the re-test and a dispute arises on that re-
test, either party may use the Disputes Resolution Procedure for a ruling in relation to the
dispute, which ruling shall be binding.
OC5.7.2.7 If following the procedure in OC5.7.2.5 and OC5.7.2.6 it is accepted that the Black Start
Station has failed the Black Start Test (or a re-test carried out under OC5.7.2.5), within 14
days, or such longer period as NGET may reasonably agree, following such failure, the
relevant Generator shall submit to NGET in writing for approval, the date and time by which
that Generator shall have brought that Black Start Station to a condition where it has a
Black Start Capability and would pass the Black Start Test, and NGET will not
unreasonably withhold or delay its approval of the Generator's proposed date and time
submitted. Should NGET not approve the Generator's proposed date and time (or any
revised proposal) the Generator shall revise such proposal having regard to any comments
NGET may have made and resubmit it for approval.
OC5.7.2.8 Once the Generator has indicated to NGET that the Generating Station has a Black Start
Capability, NGET shall either accept this information or require the Generator to
demonstrate that the relevant Black Start Station has its Black Start Capability restored,
by means of a repetition of the Black Start Test referred to in OC5.7.1(d) following the same
procedure as for the initial Black Start Test. The provisions of this OC5.7.2 will apply to
such test.
OC5.8 PROCEDURES APPLYING TO EMBEDDED MEDIUM POWER STATION NOT SUBJECT
TO A BILATERAL AGREEMENT AND EMBEDDED DC CONVERTER STATIONS NOT
SUBJECT TO A BILATERAL AGREEMENT
OC5.8.1 Compliance Statement
Each Network Operator shall ensure that each Embedded Person provides to the
Network Operator upon NGET's request:
(a) written confirmation that each such Generating Unit, Power Park Module or DC
Converter complies with the requirements of the CC; and
(b) evidence, where requested, reasonably satisfactory to NGET, of such compliance.
Such a request shall not normally be made by NGET more than twice in any calendar
year in respect of any Generators Generating Unit or Power Park Module or DC
Converter owner's DC Converter.
The Network Operator shall provide the evidence or written confirmation required under
OC5.8.1 (a) and (b) forthwith upon receipt to NGET.
OC5.8.2 Network Operators Obligations To Facilitate Tests
If:
(a) the Network Operator fails to procure the confirmation referred to at OC5.8.1(a); or
(b) the evidence of compliance is not to NGETs reasonable satisfaction,
then, NGET shall be entitled to require the Network Operator to procure access upon terms
reasonably satisfactory to NGET to enable NGET to witness the Embedded Person
carrying out the tests referred to in OC5.8.3 in respect of the relevant Embedded Medium
Power Station or Embedded DC Converter Station.
OC5.8.3 Testing Of Embedded Medium Power Stations Not Subject To A Bilateral Agreement Or
Embedded DC Converter Stations Not Subject To A Bilateral Agreement
Issue 5 Revision 15 OC5 03 February 2016
11 of 42
NGET may, in accordance with the provisions of OC5.8.2, at any time (although not normally
more than twice in any calendar year in respect of any particular Embedded Medium Power
Station not subject to a Bilateral Agreement or Embedded DC Converter Station not
subject to a Bilateral Agreement) issue an instruction requiring the Network Operator
within whose System the relevant Medium Power Station not subject to a Bilateral
Agreement or DC Converter Station not subject to a Bilateral Agreement is Embedded,
to require the Embedded Person to carry out a test.
Such test shall be carried out at a time no sooner than 48 hours from the time that the
instruction was issued, on any one or more of the Generating Units, Power Park Module or
DC Converter comprising part of the relevant Embedded Medium Power Station or
Embedded DC Converter Station and should only be to demonstrate that:
(a) the relevant Generating Unit, Power Park Module or DC Converter meets the
requirements of the paragraphs in the CC which are applicable to such Generating
Units, Power Park Module or DC Converter;
(b) the Reactive Power capability registered with NGET under OC2 meets the
requirements set out in CC.6.3.2.
The instruction may only be issued where, following consultation with the relevant Network
Operator, NGET has:
(a) confirmed to the relevant Network Operator the manner in which the test will be
conducted, which shall be consistent with the principles established in OC5.5.3; and
(b) received confirmation from the relevant Network Operator that the relevant
Generating Unit, Power Park Module or DC Converter would not then be unavailable
by reason of forced outage or Planned Outage expected prior to the instruction.
The relevant Network Operator is responsible for ensuring the performance of any test so
required by NGET and the Network Operator shall ensure that the Embedded Person
retains the responsibility for ensuring the safety of personnel and plant during the test.
OC5.8.4 Test Failures/Re-Tests And Disputes
The relevant Network Operator shall:
(a) ensure that provisions equivalent to OC5.5.5, OC5.5.6 and OC5.6 apply to Embedded
Medium Power Stations not the subject of a Bilateral Agreement or Embedded DC
Converter Stations not the subject of a Bilateral Agreement within its System in
respect of test failures, re-tests and disputes as to test failures and re-tests;
(b) ensure that the provisions equivalent to OC5.5.5, OC5.5.6 and OC5.6 referred to in
OC5.8.4(a) are effective so that NGET may require, if it so wishes, the provision to it of
any reports or other information equivalent to those or that to which NGET would be
entitled in relation to test failures, re-tests and disputes as to test failures and re-tests
under the provisions of OC5.5.5, OC5.5.6 and OC5.6; and
(c) the provisions equivalent to OC5.5.5, OC5.5.6 and OC5.6 referred to in OC5.8.4(a) are
effective to permit NGET to conduct itself and take decisions in such a manner in
relation to test failures, re-tests and disputes as to test failures and re-tests in respect of
Embedded Medium Power Stations not the subject of a Bilateral Agreement or
Embedded DC Converter Stations not the subject of a Bilateral Agreement as it is
able to conduct itself and take decisions in relation to test failures, re-tests and disputes
as to test failures and re-tests under OC5.5.5, OC5.5.6 and OC5.6.

Issue 5 Revision 15 OC5 03 February 2016


12 of 42
APPENDIX 1 - ONSITE SIGNAL PROVISION FOR WITNESSING TESTS
OC5.A.1.1 During any tests witnessed on-site by NGET, the following signals shall be provided to
NGET by the Generator, Generator undertaking OTSDUW or DC Converter Station owner
in accordance with CC.6.6.2:
OC5.A.1.2 Synchronous Generating Units

(a) All Tests MW - Active Power at Generating Unit terminals

(b) Reactive & MVAr - Reactive Power at Generating Unit terminals


Excitation System
Vt - Generating Unit terminal voltage
Efd- Generating Unit field voltage and/or main exciter field
voltage
Ifd Generating Unit field current (where possible)
Power System Stabiliser output, where applicable.
Noise Injected noise signal (where applicable and
possible)

(c) Governor System & Fsys - System Frequency


Frequency Response
Finj - Injected Speed Reference
Logic - Stop / Start Logic Signal

For Gas Turbines:


GT Fuel Demand
GT Fuel Valve Position
GT Inlet Guide Vane Position
GT Exhaust Gas Temperature

For Steam Turbines at >= 1Hz:


Pressure before Turbine Governor Valves
Turbine Governor Valve Positions
Governor Oil Pressure*
Boiler Pressure Set Point *
Superheater Outlet Pressure *
Pressure after Turbine Governor Valves*
Boiler Firing Demand*
*Where applicable (typically not in CCGT module)

For Hydro Plant:


Speed Governor Demand Signal
Actuator Output Signal
Guide Vane / Needle Valve Position

(d) Compliance with Fsys - System Frequency

Issue 5 Revision 15 OC5 03 February 2016


13 of 42
CC.6.3.3 Finj - Injected Speed Reference
Appropriate control system parameters as agreed with
NGET (See OC5.A.2.9)

OC5.A.1.3 Power Park Modules, OTSUA and DC Converters

Each Power Park Module and DC Converters at Grid Entry


Point or User System Entry Point
(a) Real Time on Total Active Power (MW)
site.
Total Reactive Power (MVAr)
Line-line Voltage (kV)
System Frequency (Hz)
(b) Real Time on site Injected frequency signal (Hz) or test logic signal (Boolean)
or Downloadable when appropriate
Injected voltage signal (per unit voltage) or test logic signal
(Boolean) when appropriate
In the case of an Onshore Power Park Module the
Onshore Power Park Module site voltage (MV) (kV)
Power System Stabiliser output, where appropriate
In the case of a Power Park Module or DC Converter
where the Reactive Power is provided by from more than
one Reactive Power source, the individual Reactive Power
contributions from each source, as agreed with NGET.
In the case of DC Converters appropriate control system
parameters as agreed with NGET (See OC5.A.4)
In the case of an Offshore Power Park Module the Total
Active Power (MW) and the Total Reactive Power (MVAr)
at the Offshore Grid Entry Point
(c) Real Time on site Available power for Power Park Module (MW)
or Downloadable
Power source speed for Power Park Module (e.g. wind
speed) (m/s) when appropriate
Power source direction for Power Park Module (degrees)
when appropriate
See OC5.A.1.3.1

OC5.A.1.3.1 NGET accept that the signals specified in OC5.A.1.3(c) may have lower effective sample
rates than those required in CC.6.6.2 although any signals supplied for connection to
NGETs recording equipment which do not meet at least the sample rates detailed in
CC.6.6.2 should have the actual sample rates indicated to NGET before testing commences.
OC5.A.1.3.2 For all NGET witnessed testing either;
(i) the Generator or DC Converter Station owner shall provide to NGET all signals
outlined in OC5.A.1.3 direct from the Power Park Module control system without any
attenuation, delay or filtering which would result in the inability to fully demonstrate the
objectives of the test, or identify any potential safety or plant instability issues, and with
a signal update rate corresponding to CC.6.6.2.1; or
(ii) in the case of Onshore Power Park Modules the Generator or DC Converter Station
owner shall provide signals OC5.A.1.3(a) direct from one or more transducer(s)
connected to current and voltage transformers for monitoring in real time on site; or,
Issue 5 Revision 15 OC5 03 February 2016
14 of 42
(iii) In the case of Offshore Power Park Modules and OTSUA signals OC5.A.1.3(a) will be
provided at the Interface Point by the Offshore Transmission Licensee pursuant to
the STC or by the Generator when OTSDUW Arrangements apply.
OC5.A.1.3.3 Options OC5.A.1.3.2 (ii) and (iii) will only be available on condition that;
(a) all signals outlined in OC5.A.1.3 are recorded and made available to NGET by the
Generator or DC Converter Station owner from the Power Park Module or OTSUA or
DC Converter control systems as a download once the testing has been completed;
and
(b) the full test results are provided by the Generator or DC Converter Station owner
within 2 working days of the test date to NGET unless NGET agrees otherwise; and
(c) all data is provided with a sample rate in accordance with CC.6.6.2.2 unless NGET
agrees otherwise; and
(d) in NGETs reasonable opinion the solution does not unreasonably add a significant
delay between tests or impede the volume of testing which can take place on the day.
OC5.A.1.3.4 In the case of where transducers connected to current and voltage transformers are installed
(OC5.A.1.3.3 (ii) and (iii)), the transducers shall meet the following specification
(a) The transducer(s) shall be permanently installed to easily allow safe testing at any point
in the future, and to avoid a requirement for recalibration of the current transformers and
voltage transformers.
(b) The transducer(s) should be directly connected to the metering quality current
transformers and voltage transformers or similar.
(c) The transducers shall either have a response time no greater than 50ms to reach 90%
of output, or no greater than 300ms to reach 99.5%.

Issue 5 Revision 15 OC5 03 February 2016


15 of 42
APPENDIX 2 - COMPLIANCE TESTING OF SYNCHRONOUS PLANT
OC5.A.2.1 Scope
OC5.A.2.1.1 This Appendix sets out the tests contained therein to demonstrate compliance with the
relevant clauses of the Connection Conditions of the Grid Code. This Appendix shall be
read in conjunction with the CP with regard to the submission of the reports to NGET.
OC5.A.2.1.2 The tests specified in this Appendix will normally be sufficient to demonstrate compliance
however NGET may:
(i) agree an alternative set of tests provided NGET deem the alternative set of tests
sufficient to demonstrate compliance with the Grid Code and Bilateral Agreement;
and/or
(ii) require additional or alternative tests if information supplied to NGET during the
compliance process suggests that the tests in this Appendix will not fully demonstrate
compliance with the relevant section of the Grid Code or Bilateral Agreement.
(iii) Agree a reduced set of tests for subsequent Generating Units following successful
completion of the first Generating Unit tests in the case of a Power Station comprised
of two or more Generating Units which NGET reasonably considers to be identical.
If:
(a) the tests performed pursuant to OC5.A.2.1.2(iii) in respect of subsequent Generating
Units do not replicate the full tests for the first Generating Unit, or
(b) any of the tests performed pursuant to OC5.A.2.1.2(iii) do not fully demonstrate
compliance with the relevant aspects of the Grid Code, Ancillary Services Agreement
and / or Bilateral Agreement,
then notwithstanding the provisions above, the full testing requirements set out in this
Appendix will be applied.
OC5.A.2.1.3 The Generator is responsible for carrying out the tests set out in and in accordance with this
Appendix and the Generator retains the responsibility for the safety of personnel and plant
during the test. NGET will witness all of the tests outlined or agreed in relation to this
Appendix unless NGET decides and notifies the Generator otherwise. Reactive Capability
tests may be witnessed by NGET remotely from the NGET control centre. For all on site
NGET witnessed tests the Generator should ensure suitable representatives from the
Generator and manufacturer (if appropriate) are available on site for the entire testing
period. In all cases the Generator shall provide suitable monitoring equipment to record all
relevant test signals as outlined below in OC5.A.3.1.5.
OC5.A.2.1.6 The Generator shall submit a schedule of tests to NGET in accordance with CP.4.3.1
OC5.A.2.1.7 Prior to the testing of a Generating Unit the Generator shall complete the Integral
Equipment Test procedure in accordance with OC.7.5
OC5.A.2.1.8 Full Generating Unit testing as required by CP.7.2 is to be completed as defined in
OC5.A.2.2 through to OC5.A.2.9
OC5.A.2.2 Excitation System Open Circuit Step Response Tests
OC5.A.2.2.1 The open circuit step response of the Excitation System will be tested by applying a voltage
step change from 90% to 100% of the nominal Generating Unit terminal voltage, with the
Generating Unit on open circuit and at rated speed.

Issue 5 Revision 15 OC5 03 February 2016


16 of 42
OC5.A.2.2.1 The test shall be carried out prior to synchronisation in accordance with CP.6.4. This is not
witnessed by NGET unless specifically requested by NGET. Where NGET is not witnessing
the tests, the Generator shall supply the recordings of the following signals to NGET in an
electronic spreadsheet format:
Vt - Generating Unit terminal voltage
Efd - Generating Unit field voltage or main exciter field voltage
Ifd- Generating Unit field current (where possible)
Step injection signal
OC5.A.2.2.3 Results shall be legible, identifiable by labelling, and shall have appropriate scaling.
OC5.A.2.3 Open & Short Circuit Saturation Characteristics
OC5.A.2.3.1 The test shall normally be carried out prior to synchronisation in accordance with CP.6.4.
Manufacturer factory test results may be used where appropriate or manufacturers factory
type test results may be used if agreed by NGET.
OC5.A.2.3.2 This is not witnessed by NGET. Graphical and tabular representations of the results in an
electronic spreadsheet format showing per unit open circuit terminal voltage and short circuit
current versus per unit field current shall be submitted to NGET.
OC5.A.2.3.3 Results shall be legible, identifiable by labelling, and shall have appropriate scaling.
OC5.A.2.4 Excitation System On-Load Tests
OC5.A.2.4.1 The time domain performance of the Excitation System shall be tested by application of
voltage step changes corresponding to 1% and 2% of the nominal terminal voltage.
OC5.A.2.4.2 Where a Power System Stabiliser is present:
(i) The PSS must only be commissioned in accordance with BC2.11.2. When a PSS is
switched on for the first time as part of on-load commissioning or if parameters have
been adjusted the Generator should consider reducing the PSS output gain by at least
50% and should consider reducing the limits on PSS output by at least a factor of 5 to
prevent unexpected PSS action affecting the stability of the Generating Unit or the
National Electricity Transmission System.
(ii) The time domain performance of the Excitation System shall be tested by application
of voltage step changes corresponding to 1% and 2% of the nominal terminal voltage,
repeating with and without the PSS in service.
(iii) The frequency domain tuning of the PSS shall also be demonstrated by injecting a
0.2Hz-3Hz band limited random noise signal into the Automatic Voltage Regulator
reference with the Generating Unit operating at points specified by NGET (up to rated
MVA output).
(iv) The PSS gain margin shall be tested by increasing the PSS gain gradually to threefold
and observing the Generating Unit steady state Active Power output.
(v) The interaction of the PSS with changes in Active Power shall be tested by application
of a +0.5Hz frequency injection to the governor while the Generating Unit is selected to
Frequency Sensitive Mode.
(vi) If the Generating Unit is of the pump storage type then the step tests shall be carried
out, with and without the PSS, in the pumping mode in addition to the generating mode.
(vii) Where the Bilateral Agreement requires that the PSS is in service at a specified
loading level additional testing witnessed by NGET will be required during the
commissioning process before the Generating Unit or CCGT Module may exceed this
output level.
(viii) Where the Excitation System includes a PSS, the Generator shall provide a suitable
noise source to facilitate noise injection testing.

Issue 5 Revision 15 OC5 03 February 2016


17 of 42
OC5.A.2.4.3 The following typical procedure is provided to assist Generators in drawing up their own site
specific procedures for the NGET witnessed PSS Tests.

Test Injection Notes

Synchronous Generator running rated MW, unity


pf, PSS Switched Off

1 Record steady state for 10 seconds


Inject +1% step to AVR Voltage Reference and
hold for at least 10 seconds until stabilised
Remove step returning AVR Voltage Reference
to nominal and hold for at least 10 seconds

2 Record steady state for 10 seconds


Inject +2% step to AVR Voltage Reference and
hold for at least 10 seconds until stabilised
Remove step returning AVR Voltage Reference
to nominal and hold for at least 10 seconds

3 Inject band limited (0.2-3Hz) random noise


signal into voltage reference and measure
frequency spectrum of Real Power.
Remove noise injection.

Switch On Power System Stabiliser

4 Record steady state for 10 seconds


Inject +1% step to AVR Voltage Reference and
hold for at least 10 seconds until stabilised
Remove step returning AVR Voltage Reference
to nominal and hold for at least 10 seconds

5 Record steady state for 10 seconds


Inject +2% step to AVR Voltage Reference and
hold for at least 10 seconds until stabilised
Remove step returning AVR Voltage Reference
to nominal and hold for at least 10 seconds

6 Increase PSS gain at 30 second intervals. i.e.


x1 x1.5 x2 x2.5 x3
Return PSS gain to initial setting

7 Inject band limited (0.2-3Hz) random noise


signal into voltage reference and measure
frequency spectrum of Real Power.
Remove noise injection.

Issue 5 Revision 15 OC5 03 February 2016


18 of 42
8 Select the governor to FSM
Inject +0.5 Hz step into governor.
Hold until generator MW output is stabilised
Remove step

OC5.A.2.5 Under-excitation Limiter Performance Test


OC5.A.2.5.1 Initially the performance of the Under-excitation Limiter should be checked by moving the
limit line close to the operating point of the Generating Unit when operating close to unity
power factor. The operating point of the Generating Unit is then stepped into the limit by
applying a 2% decrease in Automatic Voltage Regulator reference voltage.
OC5.A.2.5.2 The final performance of the Under-excitation Limiter shall be demonstrated by testing its
response to a step change corresponding to a 2% decrease in Automatic Voltage
Regulator reference voltage when the Generating Unit is operating just off the limit line, at
the designed setting as indicated on the Performance Chart submitted to NGET under
OC2.
OC5.A.2.5.3 Where possible the Under-excitation Limiter should also be tested by operating the tap-
changer when the Generating Unit is operating just off the limit line, as set up.
OC5.A.2.5.4 The Under-excitation Limiter will normally be tested at low Active Power output and at
maximum Active Power output (Registered Capacity).
OC5.A.2.5.5 The following typical procedure is provided to assist Generators in drawing up their own site
specific procedures for the NGET witnessed Under-excitation Limiter Tests.

Test Injection Notes

Synchronous generator running rated MW at


unity power factor. Under-excitation limit
temporarily moved close to the operating point
of the generator.
1 PSS on.
Inject -2% voltage step into AVR voltage
reference and hold at least for 10 seconds
until stabilised
Remove step returning AVR Voltage
Reference to nominal and hold for at least 10
seconds
Under-excitation limit moved to normal position.
Synchronous generator running at rated MW
and at leading MVArs close to Under-excitation
limit.
2 PSS on.
Inject -2% voltage step into AVR voltage
reference and hold at least for 10 seconds
until stabilised
Remove step returning AVR Voltage
Reference to nominal and hold for at least 10
seconds

Issue 5 Revision 15 OC5 03 February 2016


19 of 42
OC5.A.2.6 Over-excitation Limiter Performance Test
Description & Purpose of Test
OC5.A.2.6.1 The performance of the Over-excitation Limiter, where it exists, shall be demonstrated by
testing its response to a step increase in the Automatic Voltage Regulator reference
voltage that results in operation of the Over-excitation Limiter. Prior to application of the
step the Generating Unit shall be generating Rated Active Power and operating within its
continuous Reactive Power capability. The size of the step will be determined by the
minimum value necessary to operate the Over-excitation Limiter and will be agreed by
NGET and the Generator. The resulting operation beyond the Over-excitation Limit shall
be controlled by the Over-excitation Limiter without the operation of any protection that
could trip the Generating Unit. The step shall be removed immediately on completion of the
test.
OC5.A.2.6.2 If the Over-excitation Limiter has multiple levels to account for heating effects, an
explanation of this functionality will be necessary and if appropriate, a description of how this
can be tested.
OC5.A.2.6.3 The following typical procedure is provided to assist Generators in drawing up their own site
specific procedures for the NGET witnessed Under-excitation Limiter Tests.

Test Injection Notes

Synchronous Generator running rated MW and


maximum lagging MVAr.
Over-excitation Limit temporarily set close to this
operating point. PSS on.
1 Inject positive voltage step into AVR voltage
reference and hold
Wait till Over-excitation Limiter operates after
sufficient time delay to bring back the
excitation back to the limit.
Remove step returning AVR Voltage
Reference to nominal.
Over-excitation Limit restored to its normal
operating value. PSS on.

OC5.A.2.7 Reactive Capability


OC5.A.2.7.1 The leading and lagging Reactive Power capability on each Generating Unit will normally
be demonstrated by operation of the Generating Unit at 0.85 power factor lagging for 1 hour
and 0.95 power factor leading for 1 hour.
OC5.A.2.7.2 In the case of an Embedded Generating Unit where distribution network considerations
restrict the Generating Unit Reactive Power Output then the maximum leading and lagging
capability will be demonstrated without breaching the host network operators limits.
OC5.A.2.7.3 The test procedure, time and date will be agreed with NGET and will be to the instruction of
NGET control centre and shall be monitored and recorded at both the NGET control centre
and by the Generator.
OC5.A.2.7.4 Where the Generator is recording the voltage and Reactive Power at the Generating Unit
terminals the results shall be supplied in an electronic spreadsheet format.
OC5.A.2.7.5 The ability of the Generating Unit to comply with the operational requirements specified in
BC2.A.2.6 and CC.6.1.7 will normally be demonstrated by changing the tap position and,
where agreed in the Bilateral Agreement, the Generating Unit terminal voltage.

Issue 5 Revision 15 OC5 03 February 2016


20 of 42
OC5.A.2.8 Governor and Load Controller Response Performance
OC5.A.2.8.1 The governor and load controller response performance will be tested by injecting simulated
frequency deviations into the governor and load controller systems. Such simulated
frequency deviation signals must be injected simultaneously at both speed governor and
load controller references. For CCGT modules, simultaneous injection into all gas turbines,
steam turbine governors and module controllers is required.
OC5.A.2.8.2 Prior to witnessing the governor tests set out in OC5.A.2.8.6, NGET requires the Generator
to conduct the preliminary tests detailed in OC5.A.2.8.4 and send the results to NGET for
assessment unless agreed otherwise by NGET. The results should be supplied in an
electronic spreadsheet format. These tests shall be completed at least two weeks prior to the
witnessed governor response tests.
OC5.A.2.8.3 Where CCGT module or Generating Unit is capable of operating on alternative fuels, tests
will be required to demonstrate performance when operating on each fuel. NGET may agree
a reduction from the tests listed in OC5.A.2.8.6 for demonstrating performance on the
alternative fuel. This includes the case where a main fuel is supplemented by bio-fuel.
Preliminary Governor Frequency Response Testing
OC5.A.2.8.4 Prior to conducting the full set of tests as per OC5.A.2.8.6, Generators are required to
conduct a preliminary set of tests below to confirm the frequency injection method is correct
and the plant control performance is within expectation. The test numbers refer to Figure 1
below. With the plant running at 80% of full load, the following frequency injections shall be
applied.

Test No Frequency Injection Notes


(Figure 1)
8 Inject - 0.5Hz frequency fall over 10 sec
Hold until conditions stabilise
Remove the injected signal
14 Inject +0.5Hz frequency rise over 10 sec
Hold until conditions stabilise
Remove the injected signal
13 Inject -0.5Hz frequency fall over 10 sec
Hold for a further 20 sec
At 30 sec from the start of the test, Inject
a +0.3Hz frequency rise over 30 sec.
Hold until conditions stabilise
Remove the injected signal

OC5.A.2.8.5 The recorded results (e.g. Finj, MW and control signals) should be sampled at a minimum
rate of 1 Hz to allow NGET to assess the plant performance from the initial transients
(seconds) to the final steady state conditions (5-15 minutes depending on the plant design).
This is not witnessed by NGET. The Generator shall supply the recordings including data to
NGET in an electronic spreadsheet format. Results shall be legible, identifiable by labelling,
and shall have appropriate scaling.

Issue 5 Revision 15 OC5 03 February 2016


21 of 42
Full Frequency Response Testing Schedule Witnessed by NGET
OC5.A.2.8.6 The tests are to be conducted at a number of different Module Load Points (MLP). The load
points are conducted as shown below unless agreed otherwise by NGET.

Module Load Point 6


100% MEL
(Maximum Export Limit)

Module Load Point 5 95% MEL

Module Load Point 4


80% MEL
(Mid point of Operating Range)

Module Load Point 3 70% MEL

Module Load Point 2


MG
(Minimum Generation)

Module Load Point 1


DMOL
(Design Minimum Operating Level)

OC5.A.2.8.7 The tests are divided into the following two types;
(i) Frequency response volume tests as per OC5.A.2.8. Figure 1. These tests consist of
Frequency profile and ramp tests.
(ii) System islanding and step response tests as shown by OC5.A.2.8. Figure 2.
OC5.A.2.8.8 There should be sufficient time allowed between tests for control systems to reach steady
state. Where the diagram states HOLD the current injection should be maintained until the
Active Power (MW) output of the Generating Unit or CCGT Module has stabilised. The
frequency response capability test (see Figure 1) injection signal shall be returned to zero at
the same rate at which it was applied. NGET may require repeat tests should the tests give
unexpected results.

Issue 5 Revision 15 OC5 03 February 2016


22 of 42
0.6
HOLD

0.4

Frequency (Hz)
HOLD
0.2
HOLD
0 10s 30s 60s 10s 10s 10s 0 10s 30s 60s
0
10s 10s 10s
HOLD
-0.2
HOLD

HOLD
-0.4
HOLD

HOLD
-0.6

-0.8
Response (MW)

+
Typical

HF Ramp
HF Ramp

HF Ramp
LF Ramp
LF Ramp

LF Ramp
LF Event

LF Event
Profile 1

Profile 2
+0.5Hz
+0.1Hz

+0.2Hz
-0.2Hz
-0.1Hz

-0.5Hz
Load
Point

MLP6 * * 1 2 3 * 4 *
MLP5 5 * * 6 * * 7 *
MLP4 8 9 10 11 12 13 14 *
MLP3 15 * * * * * 16 17
MLP2 18 * * 19 20 21 * 22
MLP1 23 * * 24 25 * * 26

Figure 1: Frequency Response Capability Tests

Issue 5 Revision 15 OC5 03 February 2016


23 of 42
0.8 HOLD
*
HOLD
0.6 HOLD

0.4
Frequency (Hz)

HOLD
HOLD
0.2
0 1s (G) 31s
0 2s (A,J) 32s
0
0 1s 0 30s

HOLD
-0.2 HOLD

-0.4
HOLD HOLD
-0.6
-0.5Hz (K)
-2Hz (A,J)
-0.8
Response (MW)

+
Typical

Load Point +2.0* +0.02 -0.2 +0.2 -0.5 +0.5 +0.6 -0.5 -2.0 + 0**
MLP6 BC1 BC2 L
MLP6 LFSM BC3 BC4
MLP5 A
MLP4 D/E F G H I J M
*
MLP4 LFSM N
MLP3
MLP2
MLP1 K

Figure 2: System islanding and step response tests

* This will generally be +2.0Hz unless an injection of this size causes a reduction in plant
output that takes the operating point below Designed Minimum Operating Level in which
case an appropriate injection should be calculated in accordance with the following:
For example 0.9Hz is needed to take an initial output 65% to a final output of 20%. If the
initial output was not 65% and the Designed Minimum Operating Level is not 20% then the
injected step should be adjusted accordingly as shown in the example given below

Initial Output 65%


Designed Minimum Operating Level 20%

Frequency Controller Droop 4%


Frequency to be injected = (0.65 - 0.20) x 0.04 x 50 = 0.9Hz

** Tests L and M in Figure 2 shall be conducted if in this range of tests the system frequency
feedback signal is replaced by the injection signal rather than the injection signal being
added to the system frequency signal. The tests will consist of monitoring the Generating
Unit and CCGT Module in Frequency Sensitive Mode during normal system frequency
variations without applying any injection. Test N in figure 2 shall be conducted in all cases.
All three tests should be conducted for a period of at least 10 minutes.

Issue 5 Revision 15 OC5 03 February 2016


24 of 42
OC5.A.2.9 Compliance with CC.6.3.3 Functionality Test
OC5.A.2.9.1 Where the plant design includes active control function or functions to deliver CC.6.3.3
compliance, the Generator will propose and agree a test procedure with NGET, which will
demonstrate how the Generating Unit Active Power output responds to changes in
System Frequency and ambient conditions (e.g. by Frequency and temperature injection
methods).
OC5.A.2.9.2 The Generator shall inform NGET if any load limiter control is additionally employed.
OC5.A.2.9.3 With reference to the signals specified in OC5.A.1, NGET will agree with the Generator
which additional control system parameters shall be monitored to demonstrate the
functionality of CC.6.3.3 compliance systems. Where NGET recording equipment is not used
results shall be supplied to NGET in an electronic spreadsheet format.

Issue 5 Revision 15 OC5 03 February 2016


25 of 42
APPENDIX 3 - COMPLIANCE TESTING OF POWER PARK MODULES
(AND OTSUA)

OC5.A.3.1 Scope
OC5.A.3.1.1 This Appendix outlines the general testing requirements for Power Park Modules and
OTSUA to demonstrate compliance with the relevant aspects of the Grid Code, Ancillary
Services Agreement and Bilateral Agreement. The tests specified in this Appendix will
normally be sufficient to demonstrate compliance however NGET may:
(i) agree an alternative set of tests provided NGET deem the alternative set of tests
sufficient to demonstrate compliance with the Grid Code, Ancillary Services
Agreement and Bilateral Agreement; and/or
(ii) require additional or alternative tests if information supplied to NGET during the
compliance process suggests that the tests in this Appendix will not fully demonstrate
compliance with the relevant section of the Grid Code, Ancillary Services Agreement
or Bilateral Agreement; and/or
(ii) require additional tests if a Power System Stabiliser is fitted; and/or
(iv) agree a reduced set of tests if a relevant Manufacturer's Data & Performance Report
has been submitted to and deemed to be appropriate by NGET; and/or
(v) agree a reduced set of tests for subsequent Power Park Modules or OTSUA following
successful completion of the first Power Park Module or OTSUA tests in the case of a
Power Station comprised of two or more Power Park Modules or OTSUA which
NGET reasonably considers to be identical.
If:
(a) the tests performed pursuant to OC5.A.3.1.1(iv) do not replicate the results contained in
the Manufacturers Data & Performance Report or
(b) the tests performed pursuant to OC5.A.3.1.1(v) in respect of subsequent Power Park
Modules or OTSUA do not replicate the full tests for the first Power Park Module or
OTSUA, or
(c) any of the tests performed pursuant to OC5.A.3.1.1(iv) or OC5.A.3.1.1(v) do not fully
demonstrate compliance with the relevant aspects of the Grid Code, Ancillary
Services Agreement and / or Bilateral Agreement,
then notwithstanding the provisions above, the full testing requirements set out in this
Appendix will be applied.
OC5.A.3.1.2 The Generator is responsible for carrying out the tests set out in and in accordance with this
Appendix and the Generator retains the responsibility for the safety of personnel and plant
during the test. NGET will witness all of the tests outlined or agreed in relation to this
Appendix unless NGET decides and notifies the Generator owner otherwise. Reactive
Capability tests may be witnessed by NGET remotely from the NGET control centre. For all
on site NGET witnessed tests the Generator must ensure suitable representatives from the
Generator and / or Power Park Module manufacturer (if appropriate) and/or OTSUA
manufacturer (if appropriate) are available on site for the entire testing period. In all cases
and in addition to any recording of signals conducted by NGET the Generator shall record
all relevant test signals as outlined in OC5.A.1.
OC5.A.3.1.3 In addition to the dynamic signals supplied in OC5.A.1 the Generator shall inform NGET of
the following information prior to the commencement of the tests and any changes to the
following, if any values change during the tests:
(i) All relevant transformer tap numbers; and
(ii) Number of Power Park Units in operation
OC5.A.3.1.4 The Generator shall submit a detailed schedule of tests to NGET in accordance with
CP.6.3.1, and this Appendix.
Issue 5 Revision 15 OC5 03 February 2016
26 of 42
OC5.A.3.1.5 Prior to the testing of a Power Park Module or OTSUA the Generator shall complete the
Integral Equipment Tests procedure in accordance with OC.7.5.
OC5.A.3.1.6 Partial Power Park Module or OTSUA testing as defined in OC5.A.3.2 and OC5.A.3.3 is to
be completed at the appropriate stage in accordance with CP.6.
OC5.A.3.1.7 Full Power Park Module or OTSUA testing as required by CP.7.2 is to be completed as
defined in OC5.A.3.4 through to OC5.A.3.7.
OC5.A.3.1.8 Where OTSDUW Arrangements apply and prior to the OTSUA Transfer Time any relevant
OTSDUW Plant and Apparatus shall be considered within the scope of testing described in
this Appendix. Performance shall be assessed against the relevant Grid Code requirements
for OTSDUW Plant and Apparatus at the Interface Point and other Generator Plant and
Apparatus at the Offshore Grid Entry Point. This Appendix should be read accordingly.
OC5.A.3.2 Pre 20% (or <50MW) Synchronised Power Park Module Basic Voltage Control Tests
OC5.A.3.2.1 Before 20% of the Power Park Module (or 50MW if less) has commissioned, either voltage
control test OC5.A.3.5.6(i) or (ii) must be completed in accordance with CP.6.
OC5.A.3.2.2 In the case of an Offshore Power Park Module which provides all or a portion of the
Reactive Power capability as described in CC.6.3.2(e)(iii) and / or voltage control
requirements as described in CC.6.3.8(b)(ii) to enable an Offshore Transmission Licensee
to meet the requirements of STC Section K, the Generator is required to cooperate with the
Offshore Transmission Licensee to conduct the 20% voltage control test. The results in
relation to the Offshore Power Park Module will be assessed against the requirements in
the Bilateral Agreement. In the case of OTSUA prior to the OTSUA Transfer Time, the
Generator shall conduct the testing by reference to the entire control system responding to
changes at the Interface Point.
OC5.A.3.3 For Power Park Modules with Registered Capacity 100MW Pre 70% Power Park
Module Tests
OC5.A.3.3.1 Before 70% but with at least 50% of the Power Park Module commissioned the following
Limited Frequency Sensitive tests as detailed in OC5.A.3.6.2 must be completed.
(a) BC3
(b) BC4
OC5.A.3.4 Reactive Capability Test
OC5.A.3.4.1 This section details the procedure for demonstrating the reactive capability of an Onshore
Power Park Module or an Offshore Power Park Module or OTSUA which provides all or a
portion of the Reactive Power capability as described in CC.6.3.2(e)(iii) (for the avoidance
of doubt, an Offshore Power Park Module which does not provide part of the Offshore
Transmission Licensee Reactive Power capability as described in CC6.3.2(e)(i) and
CC6.3.2(e)(ii) should complete the reactive power transfer / voltage control tests as per
section OC5.A.3.8). These tests should be scheduled at a time where there are at least 95%
of the Power Park Units within the Power Park Module in service. There should be
sufficient MW resource forecasted in order to generate at least 85% of Registered Capacity
of the Power Park Module.
OC5.A.3.4.2 The tests shall be performed by modifying the voltage set-point of the voltage control
scheme of the Power Park Module or OTSUA by the amount necessary to demonstrate the
required reactive range. This is to be conducted for the operating points and durations
specified in OC5.A.3.4.5.
OC5.A.3.4.3 Embedded Generator should liaise with the relevant Network Operator to ensure the
following tests will not have an adverse impact upon the Network Operators System as
per OC.7.5. In situations where the tests have an adverse impact upon the Network
Operators System NGET will only require demonstration within the acceptable limits of the
Network Operator. For the avoidance of doubt, these tests do not negate the requirement to
produce a complete Power Park Module performance chart as specified in OC2.4.2.1

Issue 5 Revision 15 OC5 03 February 2016


27 of 42
OC5.A.3.4.4 In the case where the Reactive Power metering point is not at the same location as the
Reactive Power capability requirement, then an equivalent Reactive Power capability for
the metering point shall be agreed between the Generator and NGET.
OC5.A.3.4.5 The following tests shall be completed:
(i) Operation in excess of 50% Rated MW and maximum continuous lagging Reactive
Power for 60 minutes.
(ii) Operation in excess of 50% Rated MW and maximum continuous leading Reactive
Power for 60 minutes.
(iii) Operation at 50% Rated MW and maximum continuous leading Reactive Power for 5
minutes.
(iv) Operation at 20% Rated MW and maximum continuous leading Reactive Power for 5
minutes.
(v) Operation at 20% Rated MW and maximum continuous lagging Reactive Power for 5
minutes.
(vi) Operation at less than 20% Rated MW and unity Power Factor for 5 minutes. This test
only applies to systems which do not offer voltage control below 20% of Rated MW.
(vii) Operation at 0% Rated MW and maximum continuous leading Reactive Power for 5
minutes. This test only applies to systems which offer voltage control below 20% and
hence establishes actual capability rather than required capability.
(viii) Operation at 0% Rated MW and maximum continuous lagging Reactive Power for 5
minutes. This test only applies to systems which offer voltage control below 20% and
hence establishes actual capability rather than required capability.
OC5.A.3.4.6 Within this OC lagging Reactive Power is the export of Reactive Power from the Power
Park Module to the Total System and leading Reactive Power is the import of Reactive
Power from the Total System to the Power Park Module or OTSUA.
OC5.A.3.4.7 Where the Generator provides a report from a Power Park Unit manufacturer validating the
full Reactive Power capability envelope of the Power Park Unit by test results acceptable
to NGET, NGET may agree a reduction from the set of tests detailed in OC5.A.3.4.5. The
validation testing detailed in the report must fully demonstrate the Reactive Power capability
across both the Active Power range and the range of unit terminal voltages.
OC5.A.3.5 Voltage Control Tests
OC5.A.3.5.1 This section details the procedure for conducting voltage control tests on Onshore Power
Park Modules or OTSUA or an Offshore Power Park Module which provides all or a
portion of the voltage control capability as described in CC.6.3.8(b)(ii) (for the avoidance of
doubt, Offshore Power Park Modules which do not provide part of the Offshore
Transmission Licensee voltage control capability as described in CC6.3.8(b)(i) should
complete the reactive power transfer / voltage control tests as per section OC5.A.3.8). These
tests should be scheduled at a time when there are at least 95% of the Power Park Units
within the Power Park Module in service. There should be sufficient MW resource
forecasted in order to generate at least 65% of Registered Capacity of the Onshore Power
Park Module. An Embedded Generator should also liaise with the relevant Network
Operator to ensure all requirements covered in this section will not have a detrimental effect
on the Network Operators System.
OC5.A.3.5.2 The voltage control system shall be perturbed with a series of step injections to the Power
Park Module voltage reference, and where possible, multiple up-stream transformer taps. In
the case of an Offshore Power Park Module providing part of the Offshore Transmission
Licensee voltage control capability this may require a series of step injections to the voltage
reference of the Offshore Transmission Licensee control system.
OC5.A.3.5.3 For steps initiated using network tap changers the Generator will need to coordinate with
NGET or the relevant Network Operator as appropriate. The time between transformer
taps shall be at least 10 seconds as per OC5.A.3.5 Figure 1.

Issue 5 Revision 15 OC5 03 February 2016


28 of 42
OC5.A.3.5.4 For step injection into the Power Park Module or OTSUA voltage reference, steps of 1%
and 2% shall be applied to the voltage control system reference summing junction. The
injection shall be maintained for 10 seconds as per OC5.A.3.5 Figure 2.
OC5.A.3.5.5 Where the voltage control system comprises of discretely switched plant and apparatus
additional tests will be required to demonstrate that its performance is in accordance with
Grid Code and Bilateral Agreement requirements.
OC5.A.3.5.6 Tests to be completed:
(i)

Voltage

Time
1 tap

10s
minimum

OC5.A.3.5 Figure 1 Transformer tap sequence for voltage control tests

(ii)

Applied
Voltage
2%
Step

1% Time

10s
OC5.A.3.5 Figure 2 Step injection sequence for voltage control tests

OC.A.3.5.7 In the case of OTSUA where the Bilateral Agreement specifies additional damping
facilities, additional testing to demonstrate these damping facilities may be required.

OC5.A.3.6 Frequency Response Tests


OC5.A.3.6.1 This section describes the procedure for performing frequency response testing on an
Power Park Module. These tests should be scheduled at a time where there are at least
95% of the Power Park Units within the Power Park Module in service. There should be
sufficient MW resource forecasted in order to generate at least 65% of Registered Capacity
of the Power Park Module.
OC5.A.3.6.2 The frequency controller shall be in Frequency Sensitive Mode or Limited Frequency
Sensitive Mode as appropriate for each test. Simulated frequency deviation signals shall be
injected into the frequency controller reference/feedback summing junction. If the injected
frequency signal replaces rather than sums with the real system frequency signal then the
additional tests outlined in OC5.A.3.6.6 shall be performed with the Power Park Module or
Power Park Unit in normal Frequency Sensitive Mode monitoring actual system
frequency, over a period of at least 10 minutes. The aim of this additional test is to verify that
the control system correctly measures the real system frequency for normal variations over a
period of time.

Issue 5 Revision 15 OC5 03 February 2016


29 of 42
OC5.A.3.6.3 In addition to the frequency response requirements it is necessary to demonstrate the Power
Park Module ability to deliver a requested steady state power output which is not impacted
by power source variation as per CC.6.3.9. This test shall be conducted in Limited
Frequency Sensitive Mode at a part-loaded output for a period of 10 minutes as per
OC5.A.3.6.6.

Issue 5 Revision 15 OC5 03 February 2016


30 of 42
Preliminary Frequency Response Testing
OC5.A.3.6.4 Prior to conducting the full set of tests as per OC5.A.3.6.6, Generators are required to
conduct the preliminary set of tests below to confirm the frequency injection method is
correct and the plant control performance is within expectation. The test numbers refer to
Figure 1 below. The test should be conducted when sufficient MW resource is forecasted in
order to generate at least 65% of Registered Capacity of the Power Park Module. The
following frequency injections shall be applied when operating at module load point 4.

Test No Frequency Injection Notes


(Figure 1)
8 Inject - 0.5Hz frequency fall over 10 sec
Hold until conditions stabilise
Remove the injected signal
14 Inject +0.5Hz frequency rise over 10 sec
Hold until conditions stabilise
Remove the injected signal
13 Inject -0.5Hz frequency fall over 10 sec
Hold for a further 20 sec
At 30 sec from the start of the test, Inject
a +0.3Hz frequency rise over 30 sec.
Hold until conditions stabilise
Remove the injected signal

OC5.A.3.6.5 The recorded results (e.g. Finj, MW and control signals) should be sampled at a minimum
rate of 1 Hz to allow NGET to assess the plant performance from the initial transients
(seconds) to the final steady state conditions (5-15 minutes depending on the plant design).
This is not witnessed by NGET. The Generator shall supply the recordings including data to
NGET in an electronic spreadsheet format. Results shall be legible, identifiable by labelling,
and shall have appropriate scaling.
Full Frequency Response Testing Schedule Witnessed by NGET
OC5.A.3.6.6 The tests are to be conducted at a number of different Module Load Points (MLP). In the
case of a Power Park Module the module load points are conducted as shown below unless
agreed otherwise by NGET.

Module Load Point 6


100% MEL
(Maximum Export Limit)

Module Load Point 5 90% MEL

Module Load Point 4


80% MEL
(Mid point of Operating Range)

Module Load Point 3 DMOL + 20%

Module Load Point 2 DMOL + 10%

Module Load Point 1


DMOL
(Design Minimum Operating Level)

OC5.A.3.6.7 The tests are divided into the following two types;
Issue 5 Revision 15 OC5 03 February 2016
31 of 42
(i) Frequency response volume tests as per OC5.A.3.6. Figure 1. These tests consist of
frequency profile and ramp tests.
(ii) System islanding and step response tests as shown by OC5.A.3.6 Figure 2
OC5.A.3.6.8 There should be sufficient time allowed between tests for control systems to reach steady
state (depending on available power resource). Where the diagram states HOLD the
current injection should be maintained until the Active Power (MW) output of the Power
Park Module has stabilised. All frequency response tests should be removed over the same
timescale for which they were applied. NGET may require repeat tests should the response
volume be affected by the available power, or if tests give unexpected results.
0.6
HOLD

0.4
Frequency (Hz)

HOLD
0.2
HOLD
0 10s 30s 60s 10s 10s 10s 0 10s 30s 60s
0
10s 10s 10s
HOLD
-0.2
HOLD
HOLD

-0.4
HOLD

HOLD
-0.6

-0.8
Response (MW)

+
Typical

HF Ramp
HF Ramp

HF Ramp
LF Ramp
LF Ramp

LF Ramp
LF Event

LF Event
Profile 1

Profile 2
+0.5Hz
+0.1Hz

+0.2Hz
-0.2Hz
-0.1Hz

-0.5Hz

Load
Point

MLP6 * * 1 2 3 * 4 *
MLP5 5 * * 6 * * 7 *
MLP4 8 9 10 11 12 13 14 *
MLP3 15 * * * * * 16 17
MLP2 18 * * 19 20 21 * 22
MLP1 23 * * 24 25 * * 26

OC5.A.3.6. Figure 1 Frequency response volume tests

Issue 5 Revision 15 OC5 03 February 2016


32 of 42
0.8 HOLD
*
HOLD
0.6 HOLD

Frequency (Hz) 0.4

HOLD
HOLD
0.2
0 1s (G) 31s
0 2s (A,J) 32s
0
0 1s 0 30s

HOLD
-0.2 HOLD

-0.4
HOLD HOLD
-0.6
-0.5Hz (K)
-2Hz (A,J)
-0.8
Response (MW)

+
Typical

Load Point +2.0* +0.02 -0.2 +0.2 -0.5 +0.5 +0.6 -0.5 -2.0 + 0**
MLP6 BC1 BC2 L
MLP6 LFSM BC3 BC4
MLP5 A
MLP4 D/E F G H I J M
*
MLP4 LFSM N
MLP3
MLP2
MLP1 K

OC5.A.3.6. Figure 2 System islanding and step response tests

* This will generally be +2.0Hz unless an injection of this size causes a reduction in plant
output that takes the operating point below Designed Minimum Operating Level in which
case an appropriate injection should be calculated in accordance with the following:
For example 0.9Hz is needed to take an initial output 65% to a final output of 20%. If the
initial output was not 65% and the Designed Minimum Operating Level is not 20% then the
injected step should be adjusted accordingly as shown in the example given below

Initial Output 65%


Designed Minimum Operating Level 20%
Frequency Controller Droop 4%

Frequency to be injected = (0.65 - 0.20) x 0.04 x 50 = 0.9Hz

** Tests L and M in Figure 2 shall be conducted if in this range of tests the system frequency
feedback signal is replaced by the injection signal rather than the injection signal being
added to the system frequency signal. The tests will consist of monitoring the Power Park
Module in Frequency Sensitive Mode during normal system frequency variations without
applying any injection. Test N in Figure 2 shall be conducted in all cases. All three tests
should be conducted for a period of at least 10 minutes.
OC5.A.3.7 Fault Ride Through Testing
OC5.A.3.7.1 This section describes the procedure for conducting fault ride through tests on a single
Power Park Unit.
Issue 5 Revision 15 OC5 03 February 2016
33 of 42
OC5.A.3.7.2 The test circuit will utilise the full Power Park Unit with no exclusions (e.g. in the case of a
wind turbine it would include the full wind turbine structure) and shall be conducted with
sufficient resource available to produce at least 95% of the Registered Capacity of the
Power Park Unit. The test will comprise of a number of controlled short circuits applied to a
test network to which the Power Park Unit is connected, typically comprising of the Power
Park Unit transformer and a test impedance to shield the connected network from voltage
dips at the Power Park Unit terminals.
OC5.A.3.7.3 In each case the tests should demonstrate the minimum voltage at the Power Park Unit
terminals or High Voltage side of the Power Park Unit transformer which the Power Park
Unit can withstand for the length of time specified in OC5.A.3.7.5. Any test results provided
to NGET should contain sufficient data pre and post fault in order to determine steady state
values of all signals, and the power recovery timescales.
OC5.A.3.7.4 In addition to the signals outlined in OC5.A.1.2. the following signals from either the Power
Park Unit terminals or High Voltage side of the Power Park Unit transformer should be
provided for this test only:
(i) Phase voltages
(ii) Positive phase sequence and negative phase sequence voltages
(iii) Phase currents
(iv) Positive phase sequence and negative phase sequence currents
(v) Estimate of Power Park Unit negative phase sequence impedance
(vi) MW Active Power at the generating unit.
(vii) MVAr Reactive Power at the generating unit.
(viii) Mechanical Rotor Speed
(ix) Real / reactive, current / power reference as appropriate
(x) Fault ride through protection operation (e.g. a crowbar in the case of a doubly fed
induction generator)
(xi) Any other signals relevant to the control action of the fault ride through control deemed
applicable for model validation.
At a suitable frequency rate for fault ride through tests as agreed with NGET.
OC5.A.3.7.5 The tests should be conducted for the times and fault types indicated in OC5.A.3.7 Table 1.
3 Phase Phase to Phase 2 Phase to 1 Phase to Grid Code Ref
Earth Earth
0.14s 0.14s 0.14s 0.14s CC.6.3.15a
0.384s CC.6.3.15b
0.710s
2.5s
180.0s

OC5.A.3.7 Table 1 Types of fault for fault ride through testing

Issue 5 Revision 15 OC5 03 February 2016


34 of 42
OC5.A.3.8 Reactive Power Transfer / Voltage Control Tests for Offshore Power Park Modules
OC5.A.3.8.1 In the case of an Offshore Power Park Module which provides all or a portion of the
Reactive Power capability as described in CC.6.3.2(e)(iii) and / or voltage control
requirements as described in CC.6.3.8(b)(ii) to enable an Offshore Transmission Licensee
to meet the requirements of STC Section K, the testing, will comprise of the entire control
system responding to changes at the onshore Interface Point. Therefore the tests in this
section OC5.A.3.8 will not apply. The Generator shall cooperate with the relevant Offshore
Transmission Licensee to facilitate these tests as required by NGET. The testing may be
combined with testing of the corresponding Offshore Transmission Licensee requirements
under the STC. The results in relation to the Offshore Power Park Module will be assessed
against the requirements in the Bilateral Agreement.
OC5.A.3.8.2 In the case of an Offshore Power Park Module which does not provide part of the Offshore
Transmission Licensee Reactive Power capability the following procedure for conducting
reactive power transfer control tests on Offshore Power Park Modules and / or voltage
control system as per CC6.3.2(e)(i) and CC6.3.2(e)(ii) apply. These tests should be carried
out prior to 20% of the Power Park Units within the Offshore Power Park Module being
synchronised, and again when at least 95% of the Power Park Units within the Offshore
Power Park Module in service. There should be sufficient power resource forecast to
generate at least 85% of the Registered Capacity of the Offshore Power Park Module.
OC5.A.3.8.3 The Reactive Power control system shall be perturbed by a series of system voltage
changes and changes to the Active Power output of the Offshore Power Park Module.
OC5.A.3.8.4 System voltage changes should be created by a series of multiple upstream transformer
taps. The Generator should coordinate with NGET or the relevant Network Operator in
order to conduct the required tests. The time between transformer taps should be at least 10
seconds as per OC5.A.3.8 Figure 1.
OC5.A.3.8.5 The active power output of the Offshore Power Park Module should be varied by applying
a sufficiently large step to the frequency controller reference/feedback summing junction to
cause a 10% change in output of the Registered Capacity of the Offshore Power Park
Module in a time not exceeding 10 seconds. This test does not need to be conducted
provided that the frequency response tests as outlined in OC5.A.3.6 are completed.
OC5.A.3.8.6 The following diagrams illustrate the tests to be completed:

Voltage

Time
1 tap
>10s
OC5.A.3.8 Figure 1 Transformer tap sequence for reactive transfer tests

<=10s

Time
Active
Power
10% of
Change
Registered Capacity

OC5.A.3.8 Figure 2 Active Power ramp for reactive transfer tests

Issue 5 Revision 15 OC5 03 February 2016


35 of 42
APPENDIX 4 - COMPLIANCE TESTING FOR DC CONVERTERS AT A DC
CONVERTER STATION
OC5.A.4.1 Scope
OC5.A.4.1.1 This Appendix outlines the general testing requirements for DC Converter Station owners
to demonstrate compliance with the relevant aspects of the Grid Code, Ancillary Services
Agreement and Bilateral Agreement. The tests specified in this Appendix will normally be
sufficient to demonstrate compliance however NGET may:
(i) agree an alternative set of tests provided NGET deem the alternative set of tests
sufficient to demonstrate compliance with the Grid Code, Ancillary Services
Agreement and Bilateral Agreement; and/or
(ii) require additional or alternative tests if information supplied to NGET during the
compliance process suggests that the tests in this Appendix will not fully demonstrate
compliance with the relevant section of the Grid Code, Ancillary Services Agreement
or Bilateral Agreement; and/or
(iii) require additional tests if control functions to improve damping of power system
oscillations and/or subsynchronous resonance torsional oscillations required by the
Bilateral Agreement or included in the control scheme and active; and/or
(iv) agree a reduced set of tests for subsequent DC Converters following successful
completion of the first DC Converter tests in the case of a Power Station comprised of
two or more DC Converters which NGET reasonably considers to be identical.
If:
(a) the tests performed pursuant to OC5.A.4.1.1(iv) in respect of subsequent DC
Converters do not replicate the full tests for the first DC Converter, or
(b) any of the tests performed pursuant to OC5.A.4.1.1(iv) do not fully demonstrate
compliance with the relevant aspects of the Grid Code, Ancillary Services Agreement
and / or Bilateral Agreement,
then notwithstanding the provisions above, the full testing requirements set out in this
Appendix will be applied.
OC5.A.4.1.2 The DC Converter Station owner is responsible for carrying out the tests set out in and in
accordance with this Appendix and the DC Converter Station owner retains the
responsibility for the safety of personnel and plant during the test. The DC Converter
Station owner is responsible for ensuring that suitable arrangements are in place with the
Externally Interconnected System Operator to facilitate testing. NGET will witness all of
the tests outlined or agreed in relation to this Appendix unless NGET decides and notifies
the DC Converter Station owner otherwise. Reactive Capability tests if required, may be
witnessed by NGET remotely from the NGET control centre. For all on site NGET witnessed
tests the DC Converter Station owner must ensure suitable representatives from the DC
Converter Station owner and / or DC Converter manufacturer (if appropriate) are available
on site for the entire testing period. In all cases and in addition to any recording of signals
conducted by NGET the DC Converter Station owner shall record all relevant test signals
as outlined in OC5.A.1.
OC5.A.4.1.3 In addition to the dynamic signals supplied in OC5.A.1 the DC Converter Station owner
shall inform NGET of the following information prior to the commencement of the tests and
any changes to the following, if any values change during the tests:
(i) All relevant transformer tap numbers.
OC5.A.4.1.4 The DC Converter Station owner shall submit a detailed schedule of tests to NGET in
accordance with CP.6.3.1, and this Appendix.
OC5.A.4.1.5 Prior to the testing of a DC Converter the DC Converter Station owner shall complete the
Integral Equipment Tests procedure in accordance with OC.7.5

Issue 5 Revision 15 OC5 03 February 2016


36 of 42
OC5.A.4.1.6 Full DC Converter testing as required by CP.7.2 is to be completed as defined in OC5.A.4.2
through to OC5.A.4.5
OC5.A.4.2 Reactive Capability Test
OC5.A.4.2.1 This section details the procedure for demonstrating the reactive capability of an Onshore
DC Converter. These tests should be scheduled at a time where there are sufficient MW
resource forecasted in order to import and export full Registered Capacity of the DC
Converter.
OC5.A.4.2.2 The tests shall be performed by modifying the voltage set-point of the voltage control
scheme of the DC Converter by the amount necessary to demonstrate the required reactive
range. This is to be conducted for the operating points and durations specified in
OC5.A.4.2.5.
OC5.A.4.2.3 Embedded DC Converter Station owner should liaise with the relevant Network Operator
to ensure the following tests will not have an adverse impact upon the Network Operators
System as per OC.7.5. In situations where the tests have an adverse impact upon the
Network Operators System NGET will only require demonstration within the acceptable
limits of the Network Operator. For the avoidance of doubt, these tests do not negate the
requirement to produce a complete DC Converter performance chart as specified in
OC2.4.2.1.
OC5.A.4.2.4 In the case where the Reactive Power metering point is not at the same location as the
Reactive Power capability requirement, then an equivalent Reactive Power capability for
the metering point shall be agreed between the DC Converter Station owner and NGET.
OC5.A.4.2.5 The following tests shall be completed for both importing and exporting of Active Power for a
DC Converter (excluding current source technology):
(i) Operation at Rated MW and maximum continuous lagging Reactive Power for 60
minutes.
(ii) Operation at Rated MW and maximum continuous leading Reactive Power for 60
minutes.
(iii) Operation at 50% Rated MW and maximum continuous leading Reactive Power for 5
minutes.
(iv) Operation at 20% Rated MW and maximum continuous leading Reactive Power for 5
minutes.
(v) Operation at 20% Rated MW and maximum continuous lagging Reactive Power for 5
minutes.
(vi) Operation at less than 20% Rated MW and unity Power Factor for 5 minutes. This test
only applies to systems which do not offer voltage control below 20% of Rated MW.
(vii) Operation at 0% Rated MW and maximum continuous leading Reactive Power for 5
minutes. This test only applies to systems which offer voltage control below 20% and
hence establishes actual capability rather than required capability.
(viii) Operation at 0% Rated MW and maximum continuous lagging Reactive Power for 5
minutes. This test only applies to systems which offer voltage control below 20% and
hence establishes actual capability rather than required capability.
OC5.A.4.2.6 For the avoidance of doubt, lagging Reactive Power is the export of Reactive Power from
the DC Converter to the Total System and leading Reactive Power is the import of
Reactive Power from the Total System to the DC Converter.

Issue 5 Revision 15 OC5 03 February 2016


37 of 42
OC5.A.4.3 Reactive Control Testing For DC Converters (Current Source Technology)
OC5.A.4.3.1 The Reactive control testing for DC Converters employing current source technology shall
be for both importing and exporting of Active Power and shall demonstrate that the reactive
power transfer limits specified in the Bilateral Agreement are not exceeded. The Reactive
Power control system shall be perturbed by a series of system voltage changes to the
Active Power output of the DC Converter and changes of system voltage where possible.
The DC Converter Station owner is responsible for ensuring that suitable arrangements are
in place with the Externally Interconnected System Operator to facilitate the active power
changes required by these tests
OC5.A.4.3.2 The active power output of the DC Converter should be varied by applying a sufficiently
large step to the frequency controller reference/feedback summing junction to cause at least
a 10% change in output of the Registered Capacity of the DC Converter in a time not
exceeding 10 seconds. This test does not need to be conducted provided that the frequency
response tests as outlined in OC5.A.4.3 are completed.
OC5.A.4.3.3 Where possible system voltage changes should be created by a series of multiple upstream
transformer taps. The DC Converter station owner should coordinate with NGET or the
relevant Network Operator in order to conduct the required tests. The time between
transformer taps should be at least 10 seconds as per OC5.A.4.3 Figure 1.
OC5.A.4.3.4 The following diagrams illustrate the tests to be completed:

Voltage

Time
1 tap
>10s
OC5.A.4.3 Figure 1 Transformer tap sequence for reactive transfer tests

<=10s

Time
Active
Power
10% of
Change
Registered Capacity

OC5.A.4.3 Figure 2 Active Power ramp for reactive transfer tests

OC5.A.4.4 Voltage Control Tests


OC5.A.4.4.1 This section details the procedure for conducting voltage control tests on DC Converters
(excluding current source technology). These tests should be scheduled at a time where
there are sufficient MW resource in order to import and export full Registered Capacity of
the DC Converter. An Embedded DC Converter Station owner should also liaise with the
relevant Network Operator to ensure all requirements covered in this section will not have a
detrimental effect on the Network Operators System.
OC5.A.4.4.2 The voltage control system shall be perturbed with a series of step injections to the DC
Converter voltage reference, and where possible, multiple up-stream transformer taps.
OC5.A.4.4.3 For steps initiated using network tap changers the DC Converter Station owner will need to
coordinate with NGET or the relevant Network Operator as appropriate. The time between
transformer taps shall be at least 10 seconds as per OC5.A.4.4 Figure 1.
Issue 5 Revision 15 OC5 03 February 2016
38 of 42
OC5.A.4.4.4 For step injection into the DC Converter voltage reference, steps of 1% and 2% shall be
applied to the voltage control system reference summing junction. The injection shall be
maintained for 10 seconds as per OC5.A.4.4 Figure 2.
OC5.A.4.4.5 Where the voltage control system comprises of discretely switched plant and apparatus
additional tests will be required to demonstrate that its performance is in accordance with
Grid Code and Bilateral Agreement requirements.
OC5.A.4.4.6 Tests to be completed:
(i)

Voltage

Time
1 tap

10s
minimum

OC5.A.4.4 Figure 1 Transformer tap sequence for voltage control tests

(ii)

Applied
Voltage
2%
Step

1% Time

10s
OC5.A.4.4 Figure 2 Step injection sequence for voltage control tests

OC5.A.4.5 Frequency Response Tests


OC5.A.4.5.1 This section describes the procedure for performing frequency response testing on a DC
Converter. These tests should be scheduled at a time where there are sufficient MW
resource in order to import and export full Registered Capacity of the DC Converter. The
DC Converter Station owner is responsible for ensuring that suitable arrangements are in
place with the Externally Interconnected System Operator to facilitate the active power
changes required by these tests
OC5.A.4.5.2 The frequency controller shall be in Frequency Sensitive Mode or Limited Frequency
Sensitive Mode as appropriate for each test. Simulated frequency deviation signals shall be
injected into the frequency controller reference/feedback summing junction. If the injected
frequency signal replaces rather than sums with the real system frequency signal then the
additional tests outlined in OC5.A.4.5.6 shall be performed with the DC Converter in normal
Frequency Sensitive Mode monitoring actual system frequency, over a period of at least 10
minutes. The aim of this additional test is to verify that the control system correctly measures
the real system frequency for normal variations over a period of time.
OC5.A.4.5.3 In addition to the frequency response requirements it is necessary to demonstrate the DC
Converter ability to deliver a requested steady state power output which is not impacted by
power source variation as per CC.6.3.9. This test shall be conducted in Limited Frequency
Sensitive Mode at a part-loaded output for a period of 10 minutes as per OC5.A.4.5.6.

Issue 5 Revision 15 OC5 03 February 2016


39 of 42
Preliminary Frequency Response Testing
OC5.A.4.5.4 Prior to conducting the full set of tests as per OC5.A.4.5.6, DC Converter Station owners
are required to conduct a preliminary set of tests below to confirm the frequency injection
method is correct and the plant control performance is within expectation. The test numbers
refer to Figure 1 below. These tests should be scheduled at a time where there are sufficient
MW resource in order to export full Registered Capacity from the DC Converter. The
following frequency injections shall be applied when operating at module load point 4.

Test No Frequency Injection Notes


(Figure 1)
8 Inject - 0.5Hz frequency fall over 10 sec
Hold until conditions stabilise
Remove the injected signal
14 Inject +0.5Hz frequency rise over 10 sec
Hold until conditions stabilise
Remove the injected signal
13 Inject -0.5Hz frequency fall over 10 sec
Hold for a further 20 sec
At 30 sec from the start of the test, Inject
a +0.3Hz frequency rise over 30 sec.
Hold until conditions stabilise
Remove the injected signal

OC5.A.4.5.5 The recorded results (e.g. Finj, MW and control signals) should be sampled at a minimum
rate of 1 Hz to allow NGET to assess the plant performance from the initial transients
(seconds) to the final steady state conditions (5-15 minutes depending on the plant design).
This is not witnessed by NGET. The DC Converter Station owner shall supply the
recordings including data to NGET in an electronic spreadsheet format. Results shall be
legible, identifiable by labelling, and shall have appropriate scaling.
Full Frequency Response Testing Schedule Witnessed by NGET
OC5.A.4.5.6 The tests are to be conducted at a number of different Module Load Points (MLP). In the
case of a DC Converter the module load points are conducted as shown below unless
agreed otherwise by NGET.

Module Load Point 6


100% MEL
(Maximum Export Limit)

Module Load Point 5 90% MEL

Module Load Point 4


80% MEL
(Mid point of Operating Range)

Module Load Point 3 DMOL + 20%

Module Load Point 2 DMOL + 10%

Module Load Point 1


DMOL
(Design Minimum Operating Level)

Issue 5 Revision 15 OC5 03 February 2016


40 of 42
OC5.A.4.5.7 The tests are divided into the following two types;
(i) Frequency response volume tests as per OC5.A.4.5. Figure 1. These tests consist of
frequency profile and ramp tests.
(ii) System islanding and step response tests as shown by OC5.A.4.5 Figure 2
OC5.A.4.5.8 There should be sufficient time allowed between tests for control systems to reach steady
state (depending on available power resource). Where the diagram states HOLD the
current injection should be maintained until the Active Power (MW) output of the DC
Converter has stabilised. All frequency response tests should be removed over the same
timescale for which they were applied. NGET may require repeat tests should the response
volume be affected by the available power, or if tests give unexpected results.

0.6
HOLD

0.4
Frequency (Hz)

HOLD
0.2
HOLD
0 10s 30s 60s 10s 10s 10s 0 10s 30s 60s
0
10s 10s 10s
HOLD
-0.2
HOLD
HOLD

-0.4
HOLD

HOLD
-0.6

-0.8
Response (MW)

+
Typical

_
HF Ramp
HF Ramp

HF Ramp
LF Ramp
LF Ramp

LF Ramp
LF Event

LF Event
Profile 1

Profile 2
+0.5Hz
+0.1Hz

+0.2Hz
-0.2Hz
-0.1Hz

-0.5Hz

Load
Point

MLP6 * * 1 2 3 * 4 *
MLP5 5 * * 6 * * 7 *
MLP4 8 9 10 11 12 13 14 *
MLP3 15 * * * * * 16 17
MLP2 18 * * 19 20 21 * 22
MLP1 23 * * 24 25 * * 26

OC5.A.4.5. Figure 1 Frequency response volume tests

Issue 5 Revision 15 OC5 03 February 2016


41 of 42
0.8 HOLD
*
HOLD
0.6 HOLD

0.4
Frequency (Hz)

HOLD
HOLD
0.2
0 1s (G) 31s
0 2s (A,J) 32s
0
0 1s 0 30s

HOLD
-0.2 HOLD

-0.4
HOLD HOLD
-0.6
-0.5Hz (K)
-2Hz (A,J)
-0.8
Response (MW)

+
Typical

Load Point +2.0* +0.02 -0.2 +0.2 -0.5 +0.5 +0.6 -0.5 -2.0 + 0**
MLP6 BC1 BC2 L
MLP6 LFSM BC3 BC4
MLP5 A
MLP4 D/E F G H I J M
*
MLP4 LFSM N
MLP3
MLP2
MLP1 K

OC5.A.4.5. Figure 2 System islanding and step response tests

* This will generally be +2.0Hz unless an injection of this size causes a reduction in plant
output that takes the operating point below Designed Minimum Operating Level in which
case an appropriate injection should be calculated in accordance with the following:
For example 0.9Hz is needed to take an initial output 65% to a final output of 20%. If the
initial output was not 65% and the Designed Minimum Operating Level is not 20% then the
injected step should be adjusted accordingly as shown in the example given below

Initial Output 65%


Designed Minimum Operating Level 20%
Frequency Controller Droop 4%
Frequency to be injected = (0.65 - 0.20) x 0.04 x 50 = 0.9Hz

** Tests L and M in Figure 2 shall be conducted if in this range of tests the system frequency
feedback signal is replaced by the injection signal rather than the injection signal being
added to the system frequency signal. The tests will consist of monitoring the DC Converter
in Frequency Sensitive Mode during normal system frequency variations without applying
any injection. Test N in Figure 2 shall be conducted in all cases. All three tests should be
conducted for a period of at least 10 minutes.

< END OF OPERATING CODE NO. 5 >

Issue 5 Revision 15 OC5 03 February 2016


42 of 42
OPERATING CODE NO. 6
(OC6)

DEMAND CONTROL

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC6.1 INTRODUCTION................................................................................................................................... 2
OC6.2 OBJECTIVE .......................................................................................................................................... 3
OC6.3 SCOPE .................................................................................................................................................. 3
OC6.4 PROCEDURE FOR THE NOTIFICATION OF DEMAND CONTROL INITIATED BY
NETWORK OPERATORS ................................................................................................................................. 4
OC6.5 PROCEDURE FOR THE IMPLEMENTATION OF DEMAND CONTROL ON THE
INSTRUCTIONS OF NGET................................................................................................................................ 5
OC6.6 AUTOMATIC LOW FREQUENCY DEMAND DISCONNECTION ........................................................ 8
OC6.7 EMERGENCY MANUAL DISCONNECTION ........................................................................................ 9
OC6.8 OPERATION OF THE BALANCING MECHANISM DURING DEMAND CONTROL ......................... 10
APPENDIX 1 - EMERGENCY MANUAL DEMAND REDUCTION/DISCONNECTION SUMMARY
SHEET .............................................................................................................................................................. 11

Issue 5 Revision 12 OC6 01 November 2014


i
OC6.1 INTRODUCTION
OC6.1.1 Operating Code No.6 ("OC6") is concerned with the provisions to be made by Network
Operators, and in relation to Non-Embedded Customers by NGET, to permit the reduction of
Demand in the event of insufficient Active Power generation being available to meet Demand,
or in the event of breakdown or operating problems (such as in respect of System Frequency,
System voltage levels or System thermal overloads) on any part of the National Electricity
Transmission System.
OC6.1.2 OC6 deals with the following:
(a) Customer voltage reduction initiated by Network Operators (other than following the
instruction of NGET);
(b) Customer Demand reduction by Disconnection initiated by Network Operators (other
than following the instruction of NGET);
(c) Demand reduction instructed by NGET;
(d) automatic low frequency Demand Disconnection; and
(e) emergency manual Demand Disconnection.
The term "Demand Control" is used to describe any or all of these methods of achieving a
Demand reduction.
OC6.1.3 The procedure set out in OC6 includes a system of warnings to give advance notice of Demand
Control that may be required by NGET under this OC6.
OC6.1.4 Data relating to Demand Control should include details relating to MW
OC6.1.5 The Electricity Supply Emergency Code as reviewed and published from time to time by the
appropriate government department for energy emergencies provides that in certain
circumstances consumers are given a certain degree of "protection" when rota disconnections
are implemented pursuant to a direction under the Energy Act 1976. No such protection can be
given in relation to Demand Control under the Grid Code.
To invoke the Electricity Supply Emergency Code the Secretary of State will issue direction(s) to
all Network Operators affected, exercising emergency powers under the Electricity Act 1989 or
by virtue of an Order in Council under the Energy Act 1976. Following the issuance of such
direction, NGET will act to coordinate the implementation of an agreed schedule of rota
disconnections across all affected Network Operators licence area(s) and to disseminate any
information as necessary throughout the period of the emergency in accordance with the
instructions NGET receives from the Secretary of State or those authorised on his behalf for this
purpose.

OC6.1.6 Connections between Large Power Stations and the National Electricity Transmission
System and between such Power Stations and a User System will not, as far as possible, be
disconnected by NGET pursuant to the provisions of OC6 insofar as that would interrupt supplies
(a) for the purposes of operation of the Power Station (including Start-Up and shutting down);
(b) for the purposes of keeping the Power Station in a state such that it could be Started-up
when it is off-Load for ordinary operational reasons; or
(c) for the purposes of compliance with the requirements of a Nuclear Site Licence.
Demand Control pursuant to this OC6 therefore applies subject to this exception.

Issue 5 Revision 12 0C6 01 November 2014


2 of 11
OC6.2 OBJECTIVE
OC6.2.1 The overall objective of OC6 is to require the provision of facilities to enable NGET to achieve
reduction in Demand that will either avoid or relieve operating problems on the National
Electricity Transmission System, in whole or in part, and thereby to enable NGET to instruct
Demand Control in a manner that does not unduly discriminate against, or unduly prefer, any
one or any group of Suppliers or Network Operators or Non-Embedded Customers. It is also
to ensure that NGET is notified of any Demand Control utilised by Users other than following an
instruction from NGET.
OC6.2.2 For certain Grid Supply Points in Scotland it is recognised that it may not be possible to meet
the requirements in OC6.4.5(b), OC6.5.3(b) (in respect of Demand Disconnection only),
OC6.5.6 (ii), OC6.6.2 (c) and OC6.7.2 (b). In these circumstances NGET and the relevant
Network Operator(s) will agree equivalent requirements covering a number of Grid Supply
Points. If NGET and the relevant Network Operator fail to agree equivalent requirements
covering a number of Grid Supply Points, then the relevant Network Operator will apply the
provisions of OC6.4.5(b), OC6.5.3(b) (in respect of Demand Disconnection only), OC6.5.6(ii),
OC6.6.2(c) and OC6.7.2(b) as evenly as reasonably practicable over the relevant Network
Operators entire System.

OC6.3 SCOPE
OC6.3.1 OC6 applies to NGET and to Users which in OC6 means:
(a) Generators; and
(b) Network Operators.
It also applies to NGET in relation to Non-Embedded Customers.
OC6.3.2 Explanation
OC6.3.2.1 (a) Although OC6 does not apply to Suppliers, the implementation of Demand Control may
affect their Customers.
(b) In all situations envisaged in OC6, Demand Control is exercisable:
(i) by reference to a Network Operator's System; or
(ii) by NGET in relation to Non-Embedded Customers.
(c) Demand Control in all situations relates to the physical organisation of the Total System,
and not to any contractual arrangements that may exist.
OC6.3.2.2 (a) Accordingly, Demand Control will be exercisable with reference to, for example, five per
cent (or such other figure as may be utilised under OC6.5) tranches of Demand by a
Network Operator.
(b) For a Supplier, whose Customers may be spread throughout a number of User Systems
(and the National Electricity Transmission System), to split its Customers into five per
cent (or such other figure as may be utilised under OC6.5) tranches of Demand would not
result in Demand Control being implemented effectively on the Total System.
(c) Where Demand Control is needed in a particular area, NGET would not know which
Supplier to contact and (even if it were to) the resulting Demand Control implemented,
because of the diversity of contracts, may well not produce the required result.
OC6.3.2.3 (a) Suppliers should note, however, that, although implementation of Demand Control in
respect of their Customers is not exercisable by them, their Customers may be affected by
Demand Control.
(b) This will be implemented by Network Operators where the Customers are within User
Systems directly connected to the National Electricity Transmission System and by
NGET where they are Non-Embedded Customers.

Issue 5 Revision 12 0C6 01 November 2014


3 of 11
(c) The contractual arrangements relating to Customers being supplied by Suppliers will,
accordingly, need to reflect this.
(d) The existence of a commercial arrangement for the provision of Customer Demand
Management or Commercial Ancillary Services does not relieve a Network Operator
from the Demand Control provisions of OC6.5, OC6.6 and OC6.7, which may be exercised
from time to time.

OC6.4 PROCEDURE FOR THE NOTIFICATION OF DEMAND CONTROL INITIATED BY NETWORK


OPERATORS (OTHER THAN FOLLOWING THE INSTRUCTION OF NGET)
OC6.4.1 Pursuant to the provisions of OC1, in respect of the time periods prior to 1100 hours each day,
each Network Operator will notify NGET of all Customer voltage reductions and/or restorations
and Demand Disconnection or reconnection, on a Grid Supply Point and half-hourly basis,
which will or may, either alone or when aggregated with any other Demand Control planned by
that Network Operator, result in a Demand change equal to or greater than the Demand
Control Notification Level averaged over any half hour on any Grid Supply Point, which is
planned to be instructed by the Network Operator other than following an instruction from
NGET relating to Demand reduction.
OC6.4.2 Under OC6, each Network Operator will notify NGET in writing by 1100 hours each day (or such
other time specified by NGET from time to time) for the next day (except that it will be for the
next 3 days on Fridays and 2 days on Saturdays and may be longer (as specified by NGET at
least one week in advance) to cover holiday periods) of Customer voltage reduction or Demand
Disconnection which will or may result in a Demand change equal to or greater than the
Demand Control Notification Level averaged over any half hour on any Grid Supply Point, (or
which when aggregated with any other Demand Control planned by that Network Operator is
equal to or greater than the Demand Control Notification Level), planned to take place during
the next Operational Day.
OC6.4.3 When the Customer voltage reduction or Demand Disconnection which may result in a
Demand change equal to or greater than the Demand Control Notification Level averaged
over any half hour on any Grid Supply Point (or which when aggregated with any other
Demand Control planned or implemented by that Network Operator is equal to or greater than
the Demand Control Notification Level) is planned after 1100 hours, each Network Operator
must notify NGET as soon as possible after the decision to implement has been made. If the
Customer voltage reduction or Demand Disconnection is implemented immediately after the
decision to implement is made, each Network Operator must notify NGET within five minutes of
implementation.
OC6.4.4 Where, after NGET has been notified, whether pursuant to OC1, OC6.4.2 or OC6.4.3, the
planned Customer voltage reduction or Demand Disconnection is changed, the Network
Operator will notify NGET as soon as possible of the new plans, or if the Customer voltage
reduction or Demand Disconnection implemented is different to that notified, the Network
Operator will notify NGET of what took place within five minutes of implementation.
OC6.4.5 Any notification under OC6.4.2, OC6.4.3 or OC6.4.4 will contain the following information on a
Grid Supply Point and half hourly basis:
(a) the proposed (in the case of prior notification) and actual (in the case of subsequent
notification) date, time and duration of implementation of the Customer voltage reduction or
Demand Disconnection; and
(b) the proposed reduction in Demand by use of the Customer voltage reduction or Demand
Disconnection.
OC6.4.6 Pursuant to the provisions of OC1.5.6, each Network Operator will supply to NGET details of
the amount of Demand reduction actually achieved by use of the Customer voltage reduction or
Demand Disconnection.

Issue 5 Revision 12 0C6 01 November 2014


4 of 11
OC6.5 PROCEDURE FOR THE IMPLEMENTATION OF DEMAND CONTROL ON THE
INSTRUCTIONS OF NGET
OC6.5.1 A National Electricity Transmission System Warning - High Risk of Demand Reduction
will, where possible, be issued by NGET, as more particularly set out in OC6.5.4, OC7.4.8 and
BC1.5.4 when NGET anticipates that it will or may instruct a Network Operator to implement
Demand reduction. It will, as provided in OC6.5.10 and OC7.4.8.2, also be issued to Non-
Embedded Customers.
OC6.5.2 Where NGET expects to instruct Demand reduction within the following 30 minutes, NGET will
where possible, issue a National Electricity Transmission System Warning - Demand
Control Imminent in accordance with OC7.4.8.2(c) and OC7.4.8.6.
OC6.5.3 (a) Whether a National Electricity Transmission System Warning - High Risk of Demand
Reduction or National Electricity Transmission System Warning - Demand Control
Imminent has been issued or not:
(i) provided the instruction relates to not more than 20 per cent of its total Demand
(measured at the time the Demand reduction is required); and
(ii) if the instruction relates to less than 20 per cent of its total Demand, is in
two voltage reduction stages of between 2 and 4 percent, each of which can be
expected to deliver around 1.5 percent Demand reduction; and

up to three Demand Disconnection stages, each of which can reasonably be


expected to deliver between four and six percent Demand reduction,

each Network Operator will abide by the instructions of NGET, which should
specify whether a voltage reduction or Demand Disconnection stage is required;
or
(iii) if the instruction relates to less than 20 per cent of its total Demand, is in four
Demand Disconnection stages each of which can reasonably be expected to
deliver between four and six per cent Demand reduction,
each Network Operator will abide by the instructions of NGET with regard to Demand
reduction under OC6.5 without delay.
(b) The Demand reduction must be achieved within the Network Operator's System as far as
possible uniformly across all Grid Supply Points (unless otherwise specified in the
National Electricity Transmission System Warning - High Risk of Demand Reduction)
either by Customer voltage reduction or by Demand Disconnection.
(c) Demand Control initiated by voltage reduction shall be initiated as soon as possible but in
any event no longer than two minutes from the instruction being received from NGET, and
completed within 10 minutes of the instruction being received from NGET.

(d) Demand Control initiated by Demand Disconnection shall be initiated as soon as possible
but in any event no longer than two minutes from the instruction being received from NGET,
and completed within five minutes of the instruction being received from NGET.

(e) Each Network Operator must notify NGET in writing by calendar week 24 each year, for
the succeeding Financial Year onwards, whether Demand Control is to be implemented
either:

i) by a combination of voltage reduction and Demand Disconnection; or

ii) Demand Disconnection alone;

together with the magnitude of the voltage reduction stages (where applicable) and for
Demand Disconnection stages, the demand reduction anticipated. Thereafter, any
changes must be notified in writing to NGET at least 10 Business Days prior to the change
coming into effect.
Issue 5 Revision 12 0C6 01 November 2014
5 of 11
OC6.5.4 (a) Where NGET wishes to instruct a Demand reduction of more than 20 per cent of a
Network Operator's Demand (measured at the time the Demand reduction is required), it
shall, if it is able, issue a National Electricity Transmission System Warning - High Risk
of Demand Reduction to the Network Operator by 1600 hours on the previous day. The
warning will state the percentage level of Demand reduction that NGET may want to
instruct (measured at the time the Demand reduction is required).
(b) The National Electricity Transmission System Warning - High Risk of Demand
Reduction will specify the percentage of Demand reduction that NGET may require in
integral multiples of the percentage levels notified by Users under OC6.5.3(c) up to (and
including) 20 per cent and of five per cent above 20 per cent and will not relate to more than
40 per cent of Demand (measured at the time the Demand reduction is required) of the
Demand on the User System of a Network Operator.
(c) If NGET has issued the National Electricity Transmission System Warning - High Risk
of Demand Reduction by 1600 hours on the previous day, on receipt of it the relevant
Network Operator shall make available the percentage reduction in Demand specified for
use within the period of the National Electricity Transmission System Warning.
(d) If NGET has not issued the National Electricity Transmission System Warning - High
Risk of Demand Reduction by 1600 hours the previous day, but after that time, the
Network Operator shall make available as much of the required Demand reduction as it is
able, for use within the period of the National Electricity Transmission System Warning.

OC6.5.5 (a) If NGET has given a National Electricity Transmission System Warning - High Risk of
Demand Reduction to a Network Operator, and has issued it by 1600 hours on the
previous day, it can instruct the Network Operator to reduce its Demand by the
percentage specified in the National Electricity Transmission System Warning.
(b) NGET accepts that if it has not issued the National Electricity Transmission System
Warning - High Risk of Demand Reduction by 1600 hours on the previous day or if it has
issued it by 1600 hours on the previous day, but it requires a further percentage of Demand
reduction (which may be in excess of 40 per cent of the total Demand on the User System
of the Network Operator (measured at the time the Demand reduction is required) from
that set out in the National Electricity Transmission System Warning, it can only receive
an amount that can be made available at that time by the Network Operator.
(c) Other than with regard to the proviso, the provisions of OC6.5.3 shall apply to those
instructions.
OC6.5.6 Once a Demand reduction has been applied by a Network Operator at the instruction of NGET,
the Network Operator may interchange the Customers to whom the Demand reduction has
been applied provided that,
(i) the percentage of Demand reduction at all times within the Network Operator's System
does not change; and
(ii) at all times it is achieved within the Network Operator's System as far as possible
uniformly across all Grid Supply Points (unless otherwise specified in the National
Electricity Transmission System Warning - High Risk of Demand Reduction if one has
been issued),
until NGET instructs that Network Operator in accordance with OC6.
OC6.5.7 Each Network Operator will abide by the instructions of NGET with regard to the restoration of
Demand under OC6.5 without delay. It shall not restore Demand until it has received such
instruction. The restoration of Demand must be achieved as soon as possible and the process
of restoration must begin within 2 minutes of the instruction being given by NGET.

Issue 5 Revision 12 0C6 01 November 2014


6 of 11
OC6.5.8 In circumstances of protracted shortage of generation or where a statutory instruction has been
given (eg. a fuel security period) and when a reduction in Demand is envisaged by NGET to be
prolonged, NGET will notify the Network Operator of the expected duration.
OC6.5.9 The Network Operator will notify NGET in writing that it has complied with NGET's instruction
under OC6.5, within five minutes of so doing, together with an estimation of the Demand
reduction or restoration achieved, as the case may be.
OC6.5.10 NGET may itself implement Demand reduction and subsequent restoration on Non-Embedded
Customers as part of a Demand Control requirement and it will organise the National
Electricity Transmission System so that it will be able to reduce Demand by Disconnection
of, or Customer voltage reduction to, all or any Non-Embedded Customers. Equivalent
provisions to those in OC6.5.4 shall apply to issuing a National Electricity Transmission
System Warning - High Risk of Demand Reduction to Non-Embedded Customers, as
envisaged in OC7.4.8.
OC6.5.11 Pursuant to the provisions of OC1.5.6, the Network Operator will supply to NGET details of the
amount of Demand reduction or restoration actually achieved.

Issue 5 Revision 12 0C6 01 November 2014


7 of 11
OC6.6 AUTOMATIC LOW FREQUENCY DEMAND DISCONNECTION
OC6.6.1 Each Network Operator will make arrangements that will enable automatic low Frequency
Disconnection of at least:
(i) 60 per cent of its total Demand (based on Annual ACS Conditions) at the time of forecast
National Electricity Transmission System peak Demand where such Network
Operators System is connected to the National Electricity Transmission System in
NGETs Transmission Area
(ii) 40 per cent of its total Demand (based on Annual ACS Conditions) at the time of forecast
National Electricity Transmission System peak where such Network Operators
System is connected to the National Electricity Transmission System in either SPTs or
SHETLs Transmission Area
in order to seek to limit the consequences of a major loss of generation or an Event on the Total
System which leaves part of the Total System with a generation deficit. Where a Network
Operators System is connected to the National Electricity Transmission System in more
than one Transmission Area, the figure above for the Transmission Area in which the majority
of the Network Operators Demand is connected shall apply.
OC6.6.2 (a) The Demand of each Network Operator which is subject to automatic low Frequency
Disconnection will be split into discrete MW blocks.
(b) The number, size (% Demand) and the associated low Frequency settings of these blocks,
will be as specified in Table CC.A.5.5.1a. NGET will keep the settings under review.
(c) The distribution of the blocks will be such as to give a reasonably uniform Disconnection
within the Network Operator's System, as the case may be, across all Grid Supply
Points.
(d) Each Network Operator will notify NGET in writing by calendar week 24 each year of the
details of the automatic low Frequency Disconnection on its User System. The
information provided should identify, for each Grid Supply Point at the date and time of the
annual peak of the National Electricity Transmission System Demand at Annual ACS
Conditions (as notified pursuant to OC1.4.2), the frequency settings at which Demand
Disconnection will be initiated and amount of Demand disconnected at each such setting.
OC6.6.3 Where conditions are such that, following automatic low Frequency Demand Disconnection,
and the subsequent Frequency recovery, it is not possible to restore a large proportion of the
total Demand so disconnected within a reasonable period of time, NGET may instruct a
Network Operator to implement additional Demand Disconnection manually, and restore an
equivalent amount of the Demand that had been disconnected automatically. The purpose of
such action is to ensure that a subsequent fall in Frequency will again be contained by the
operation of automatic low Frequency Demand Disconnection.
OC6.6.4 Once an automatic low Frequency Demand Disconnection has taken place, the Network
Operator on whose User System it has occurred, will not reconnect until NGET instructs that
Network Operator to do so in accordance with OC6.
OC6.6.5 Once the Frequency has recovered, each Network Operator will abide by the instructions of
NGET with regard to reconnection under OC6.6 without delay. Reconnection must be achieved
as soon as possible and the process of reconnection must begin within 2 minutes of the
instruction being given by NGET.
OC6.6.6 (a) Non-Embedded Customers (including a Pumped Storage Generator) must provide
automatic low Frequency disconnection, which will be split into discrete blocks.
(b) The number and size of blocks and the associated low Frequency settings will be as
specified by NGET by week 24 each calendar year following discussion with the Non-
Embedded Customers (including a Pumped Storage Generator) in accordance with the
relevant Bilateral Agreement.

Issue 5 Revision 12 0C6 01 November 2014


8 of 11
OC6.6.7 (a) In addition, Generators may wish to disconnect Generating Units from the System, either
manually or automatically, should they be subject to Frequency levels which could result in
Generating Unit damage.
(b) This Disconnection facility on such Generating Unit directly connected to the National
Electricity Transmission System, will be agreed with NGET in accordance with the
Bilateral Agreement.
(c) Any Embedded Power Stations will need to agree this Disconnection facility with the
relevant User to whose System that Power Station is connected, which will then need to
notify NGET of this.
OC6.6.8 The Network Operator or Non-Embedded Customer, as the case may be, will notify NGET
with an estimation of the Demand reduction which has occurred under automatic low Frequency
Demand Disconnection and similarly notify the restoration, as the case may be, in each case
within five minutes of the Disconnection or restoration.
OC6.6.9 Pursuant to the provisions of OC1.5.6 the Network Operator and Non-Embedded Customer
will supply to NGET details of the amount of Demand reduction or restoration actually achieved.
OC6.6.10 (a) In the case of a User, it is not necessary for it to provide automatic low Frequency
disconnection under OC6.6 only to the extent that it is providing, at the time it would be so
needed, low Frequency disconnection at a higher level of Frequency as an Ancillary
Service, namely if the amount provided as an Ancillary Service is less than that required
under OC6.6 then the User must provide the balance required under OC6.6 at the time it is
so needed.
(b) The provisions of OC7.4.8 relating to the use of Demand Control should be borne in mind
by Users.

OC6.7 EMERGENCY MANUAL DISCONNECTION


OC6.7.1 Each Network Operator will make arrangements that will enable it, following an instruction from
NGET, to disconnect Customers on its User System under emergency conditions irrespective
of Frequency within 30 minutes. It must be possible to apply the Demand Disconnections to
individual or specific groups of Grid Supply Points, as determined by NGET.
OC6.7.2 (a) Each Network Operator shall provide NGET in writing by week 24 in each calendar year, in
respect of the next following year beginning week 24, on a Grid Supply Point basis, with
the following information (which is set out in a tabular format in the Appendix):
(i) its total peak Demand (based on Annual ACS Conditions); and
(ii) the percentage value of the total peak Demand that can be disconnected (and
must include that which can also be reduced by voltage reduction, where
applicable) within timescales of 5/10/15/20/25/30 minutes.
(b) The information should include, in relation to the first 5 minutes, as a minimum, the 20% of
Demand that must be reduced on instruction under OC6.5.
OC6.7.3 Each Network Operator will abide by the instructions of NGET with regard to Disconnection
under OC6.7 without delay, and the Disconnection must be achieved as soon as possible after
the instruction being given by NGET, and in any case, within the timescale registered in OC6.7.
The instruction may relate to an individual Grid Supply Point and/or groups of Grid Supply
Points.
OC6.7.4 NGET will notify a Network Operator who has been instructed under OC6.7, of what has
happened on the National Electricity Transmission System to necessitate the instruction, in
accordance with the provisions of OC7 and, if relevant, OC10.
OC6.7.5 Once a Disconnection has been applied by a Network Operator at the instruction of NGET,
that Network Operator will not reconnect until NGET instructs it to do so in accordance with
OC6.

Issue 5 Revision 12 0C6 01 November 2014


9 of 11
OC6.7.6 Each Network Operator will abide by the instructions of NGET with regard to reconnection
under OC6.7 without delay, and shall not reconnect until it has received such instruction and
reconnection must be achieved as soon as possible and the process of reconnection must begin
within 2 minutes of the instruction being given by NGET.
OC6.7.7 NGET may itself disconnect manually and reconnect Non-Embedded Customers as part of a
Demand Control requirement under emergency conditions.
OC6.7.8 If NGET determines that emergency manual Disconnection referred to in OC6.7 is inadequate,
NGET may disconnect Network Operators and/or Non-Embedded Customers at Grid Supply
Points, to preserve the security of the National Electricity Transmission System.
OC6.7.9 Pursuant to the provisions of OC1.5.6 the Network Operator will supply to NGET details of the
amount of Demand reduction or restoration actually achieved.

OC6.8 OPERATION OF THE BALANCING MECHANISM DURING DEMAND CONTROL


Demand Control will constitute an Emergency Instruction in accordance with BC2.9 and it
may be necessary to depart from normal Balancing Mechanism operation in accordance with
BC2 in issuing Bid-Offer Acceptances. NGET will inform affected BM Participants in
accordance with the provisions of OC7.

Issue 5 Revision 12 0C6 01 November 2014


10 of 11
APPENDIX 1 - EMERGENCY MANUAL DEMAND
REDUCTION/DISCONNECTION SUMMARY SHEET
(As set out in OC6.7)
NETWORK OPERATOR: [YEAR] PEAK:

% OF GROUP DEMAND DISCONNECTION


GRID (AND/OR REDUCTION IN THE CASE OF
SUPPLY THE FIRST 5 MINUTES)
POINT PEAK (CUMULATIVE) REMARKS
MW
TIME (MINS)
(Name)
5 10 15 20 25 30

Notes:
1. Data to be provided annually by week 24 to cover the following year.

< END OF OPERATING CODE NO. 6 >

Issue 5 Revision 12 0C6 01 November 2014


11 of 11
OPERATING CODE NO. 7
(OC7)

OPERATIONAL LIAISON

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC7.1 INTRODUCTION...................................................................................................................................2
OC7.2 OBJECTIVE ..........................................................................................................................................2
OC7.3 SCOPE..................................................................................................................................................3
OC7.4 PROCEDURE .......................................................................................................................................3
OC7.4.5 Requirement To Notify Operations .............................................................................................3
OC7.4.6 Requirements To Notify Events..................................................................................................6
OC7.4.7 Significant Incidents....................................................................................................................9
Oc7.4.8 National Electricity Transmission System Warnings ...................................................................9
OC7.5 PROCEDURE IN RELATION TO INTEGRAL EQUIPMENT TESTS .................................................12
OC7.6 PROCEDURE IN RESPECT OF OPERATIONAL SWITCHING IN SCOTLAND AND
OFFSHORE......................................................................................................................................................14
APPENDIX 1 - NATIONAL ELECTRICITY TRANSMISSION SYSTEM WARNINGS TABLE .........................17

Issue 5 Revision 8 OC7 10 June 2014


i
OC7.1 INTRODUCTION
OC7.1.1 Operating Code No. 7 ("OC7") sets out the requirements for the exchange of information in
relation to Operations and/or Events on the Total System which have had (or may have had)
or will have (or may have) an Operational Effect:
(a) on the National Electricity Transmission System in the case of an Operation and/or
Event occurring on the System of a User or Users; and
(b) on the System of a User or Users in the case of an Operation and/or Event occurring on
the National Electricity Transmission System.
It also describes the types of National Electricity Transmission System Warning which may
be issued by NGET.
OC7.1.2 The requirement to notify in OC7 relates generally to notifying of what is expected to happen or
what has happened and not the reasons why. However, as OC7 provides, when an Event or
Operation has occurred on the National Electricity Transmission System which itself has
been caused by (or exacerbated by) an Operation or Event on a User's System, NGET in
reporting the Event or Operation on the National Electricity Transmission System to another
User can pass on what it has been told by the first User in relation to the Operation or Event on
the first User's System.
OC7.1.3 Where an Event or Operation on the National Electricity Transmission System falls to be
reported by NGET to an Externally Interconnected System Operator under an
Interconnection Agreement, OC7 provides that in the situation where that Event or Operation
has been caused by (or exacerbated by) an Operation or Event on a User's System, NGET
can pass on what it has been told by the User in relation to the Operation or Event on that
User's System.
OC7.1.4 OC7 also deals with Integral Equipment Tests.
OC7.1.5 To reconfigure the National Electricity Transmission System, NGET may reasonably require
the assistance of a User to reconfigure parts of the User System. To reconfigure its User
System a User may reasonably require the reasonable assistance of NGET to direct the
reconfiguration of parts of the National Electricity Transmission System.
OC7.1.6 OC7.6 sets down the arrangements for the exchange of information required when configuring
Connection Sites (or in the case of OTSUA operational prior to the OTSUA Transfer Time,
Transmission Interface Sites) and parts of the National Electricity Transmission System
adjacent to those Connection Sites (or Transmission Interface Sites) in Scotland and
Offshore. It also covers the setting up of a Local Switching Procedure. NGET shall procure
that Relevant Transmission Licensees shall comply with section OC7.6 and any relevant
Local Switching Procedure where and to the extent that such matters apply to them.

OC7.2 OBJECTIVE
The objectives of OC7 are:
OC7.2.1 To provide for the exchange of information so that the implications of an Operation and/or
Event can be considered, possible risks arising from it can be assessed and appropriate action
taken by the relevant party in order to maintain the integrity of the Total System. OC7 does not
seek to deal with any actions arising from the exchange of information, but merely with that
exchange.
OC7.2.2 To provide for types of National Electricity Transmission System Warnings which may be
issued by NGET.
OC7.2.3 To provide the framework for the information flow and discussion between NGET and certain
Users in relation to Integral Equipment Tests.
OC7.2.4 To provide the procedure to be followed in respect of Operational Switching in Scotland and
Offshore.

Issue 5 Revision 19 OC7 30 September 2016


2 of 18
OC7.3 SCOPE
OC7.3.1 OC7 applies to NGET and to Users, which in OC7 means:
(a) Generators (other than those which only have Embedded Small Power Stations or
Embedded Medium Power Stations) and including Generators undertaking OTSDUW;
(b) Network Operators;
(c) Non-Embedded Customers;
(d) Suppliers (for the purposes of National Electricity Transmission System Warnings);
(e) Externally Interconnected System Operators (for the purposes of National Electricity
Transmission System Warnings); and
(f) DC Converter Station owners.
The procedure for operational liaison by NGET with Externally Interconnected System
Operators is set out in the Interconnection Agreement with each Externally Interconnected
System Operator.
In Scotland and Offshore OC7.6 also applies to Relevant Transmission Licensees.

OC7.4 PROCEDURE
OC7.4.1 The term "Operation" means a scheduled or planned action relating to the operation of a
System (including an Embedded Power Station).
OC7.4.2 The term "Event" means an unscheduled or unplanned (although it may be anticipated)
occurrence on, or relating to, a System (including an Embedded Power Station) including,
without limiting that general description, faults, incidents and breakdowns and adverse weather
conditions being experienced.
OC7.4.3 The term "Operational Effect" means any effect on the operation of the relevant other System
which causes the National Electricity Transmission System or the Systems of the other User
or Users, as the case may be, to operate (or be at a materially increased risk of operating)
differently to the way in which they would or may have normally operated in the absence of that
effect.
OC7.4.4 References in this OC7 to a System of a User or User's System shall not include Embedded
Small Power Stations or Embedded Medium Power Stations, unless otherwise stated.
OC7.4.5 Requirement To Notify Operations
OC7.4.5.1 Operation On The National Electricity Transmission System
In the case of an Operation on the National Electricity Transmission System, which will have
(or may have) an Operational Effect on the System(s) of a User or Users, NGET will notify the
User or Users whose System(s) will, or may, in the reasonable opinion of NGET, be affected, in
accordance with OC7.
OC7.4.5.2 Operation On A User's System
In the case of an Operation on the System of a User which will have (or may have) an
Operational Effect on the National Electricity Transmission System (including an equivalent
to an Operation on the equivalent of a System of a User or other person connected to that
User's System which, via that User System, will or may have an Operational Effect on the
National Electricity Transmission System), the User will notify NGET in accordance with OC7.
Following notification by the User, NGET will notify any other User or Users on whose
System(s) the Operation will have, or may have, in the reasonable opinion of NGET, an
Operational Effect, in accordance with OC7 and will notify any Externally Interconnected
System Operator on whose System the Operation will have, or may have, in the reasonable
opinion of NGET, an Operational Effect, if it is required to do so by the relevant
Interconnection Agreement.

Issue 5 Revision 19 OC7 30 September 2016


3 of 18
OC7.4.5.3 Examples Of Situations Where Notification By NGET Or A User May Be Required
Whilst in no way limiting the general requirement to notify in advance set out in OC7.4.5.1 and
OC7.4.5.2, the following are examples of situations where notification in accordance with
OC7.4.5 will be required if they will, or may, have an Operational Effect:
(a) the implementation of a planned outage of Plant and/or Apparatus which has been
arranged pursuant to OC2;
(b) the operation (other than, in the case of a User, at the instruction of NGET) of any circuit
breaker or isolator/disconnector or any sequence or combination of the two; or
(c) voltage control.
OC7.4.5.4 Operations Caused By Another Operation Or By An Event
An Operation may be caused by another Operation or an Event on another's System
(including an Embedded Power Station) (or by the equivalent of an Event or Operation on the
System of an Externally Interconnected System Operator or Interconnector User) and in
that situation the information to be notified is different to that where the Operation arose
independently of any other Operation or Event, as more particularly provided in OC7.4.5.6.
OC7.4.5.5 Form
A notification and any response to any questions asked under OC7.4.5, of an Operation which
has arisen independently of any other Operation or of an Event, shall be of sufficient detail to
describe the Operation (although it need not state the cause) and to enable the recipient of the
notification reasonably to consider and assess the implications and risks arising (provided that, in
the case of an Operation on a User's System which NGET is notifying to other Users under
OC7.4.5.2, NGET will only pass on what it has been told by the User which has notified it) and
will include the name of the individual reporting the Operation on behalf of NGET or the User, as
the case may be. The recipient may ask questions to clarify the notification and the giver of the
notification will, insofar as it is able, answer any questions raised, provided that, in the case of an
Operation on a User's System which NGET is notifying to other Users under OC7.4.5.2, in
answering any question, NGET will not pass on anything further than that which it has been told
by the User which has notified it. NGET may pass on the information contained in the notification
as provided in OC7.4.5.6.

OC7.4.5.6 (a) A notification by NGET of an Operation under OC7.4.5.1 which has been caused by
another Operation (the "first Operation") or by an Event on a User's System, will describe
the Operation and will contain the information which NGET has been given in relation to the
first Operation or that Event by the User. The notification and any response to any
questions asked (other than in relation to the information which NGET is merely passing on
from a User) will be of sufficient detail to enable the recipient of the notification reasonably
to consider and assess the implications and risks arising from the Operation on the
National Electricity Transmission System and will include the name of the individual
reporting the Operation on behalf of NGET. The recipient may ask questions to clarify the
notification and NGET will, insofar as it is able, answer any questions raised, provided that
in relation to the information which NGET is merely passing on from a User, in answering
any question NGET will not pass on anything further than that which it has been told by the
User which has notified it.
(b) Where a User is reporting an Operation or an Event which itself has been caused by an
incident or scheduled or planned action affecting (but not on) its System, the notification to
NGET will contain the information which the User has been given by the person connected
to its System in relation to that incident or scheduled or planned action (which the User
must require, contractually or otherwise, the person connected to its System to give to it)
and NGET may pass on the information contained in the notification as provided in this
OC7.4.5.6.

Issue 5 Revision 19 OC7 30 September 2016


4 of 18
OC7.4.5.7 Where an Operation on the National Electricity Transmission System falls to be reported by
NGET under an Interconnection Agreement and the Operation has been caused by another
Operation (the "first Operation") or by an Event on a User's System, NGET will include in that
report the information which NGET has been given in relation to the first Operation or that Event
by the User (including any information relating to an incident or scheduled or planned action, as
provided in OC7.4.5.6).
OC7.4.5.8 (a) A notification to a User by NGET of an Operation under OC7.4.5.1 which has been caused
by the equivalent of an Operation or of an Event on the equivalent of a System of an
Externally Interconnected System Operator or Interconnector User, will describe the
Operation on the National Electricity Transmission System and will contain the
information which NGET has been given, in relation to the equivalent of an Operation or of
an Event on the equivalent of a System of an Externally Interconnected System
Operator or Interconnector User, by that Externally Interconnected System Operator
or Interconnector User.
(b) The notification and any response to any question asked (other than in relation to the
information which NGET is merely passing on from that Externally Interconnected
System Operator or Interconnector User) will be of sufficient detail to enable the recipient
of the notification reasonably to consider and assess the implications and risks arising from
the Operation on the National Electricity Transmission System and will include the
name of the individual reporting the Operation on behalf of NGET. The recipient may ask
questions to clarify the notification and NGET will, insofar as it is able, answer any questions
raised, provided that, in relation to the information which NGET is merely passing on from
an Externally Interconnected System Operator or Interconnector User, in answering
any question NGET will not pass on anything further than that which it has been told by the
Externally Interconnected System Operator or Interconnector User which has notified
it.
OC7.4.5.9 (a) A Network Operator may pass on the information contained in a notification to it from
NGET under OC7.4.5.1, to a Generator with a Generating Unit or a Power Park Module
connected to its System, or to a DC Converter Station owner with a DC Converter
connected to its System, or to the operator of another User System connected to its
System (which, for the avoidance of doubt, could be another Network Operator), in
connection with reporting the equivalent of an Operation under the Distribution Code (or
the contract pursuant to which that Generating Unit or Power Park Module or other User
System, or to a DC Converter Station is connected to the System of that Network
Operator) (if the Operation on the National Electricity Transmission System caused it).
(b) A Generator may pass on the information contained in a notification to it from NGET under
OC7.4.5.1, to another Generator with a Generating Unit or a Power Park Module
connected to its System, or to the operator of a User System connected to its System
(which, for the avoidance of doubt, could be a Network Operator), if it is required (by a
contract pursuant to which that Generating Unit or that Power Park Module or that User
System is connected to its System) to do so in connection with the equivalent of an
Operation on its System (if the Operation on the National Electricity Transmission
System caused it).
OC7.4.5.10 (a) Other than as provided in OC7.4.5.9, a Network Operator or a Generator may not pass on
any information contained in a notification to it from NGET under OC7.4.5.1 (and an
operator of a User System or Generator receiving information which was contained in a
notification to a Generator or a Network Operator, as the case may be, from NGET under
OC7.4.5.1, as envisaged in OC7.4.5.9 may not pass on this information) to any other
person, but may inform persons connected to its System (or in the case of a Generator
which is also a Supplier, inform persons to which it supplies electricity which may be
affected) that there has been an incident on the Total System, the general nature of the
incident (but not the cause of the incident) and (if known and if power supplies have been
affected) an estimated time of return to service.

Issue 5 Revision 19 OC7 30 September 2016


5 of 18
(b) In the case of a Generator which has an Affiliate which is a Supplier, the Generator may
inform it that there has been an incident on the Total System, the general nature of the
incident (but not the cause of the incident) and (if known and if power supplies have been
affected in a particular area) an estimated time of return to service in that area, and that
Supplier may pass this on to persons to which it supplies electricity which may be affected).
(c) Each Network Operator and Generator shall use its reasonable endeavours to procure
that any Generator or operator of a User System receiving information which was
contained in a notification to a Generator or Network Operator, as the case may be, from
NGET under OC7.4.5.1, which is not bound by the Grid Code, does not pass on any
information other than as provided above.
OC7.4.5.11 The notification will, if either party requests, be recorded by the sender and dictated to the
recipient, who shall record and repeat each phrase as it is received and on completion of the
dictation shall repeat back the notification in full to the sender who shall confirm that it has been
accurately recorded.
OC7.4.5.12 Timing
A notification under OC7.4.5 will be given as far in advance as possible and in any event shall be
given in sufficient time as will reasonably allow the recipient to consider and assess the
implications and risks arising.
OC7.4.6 Requirements To Notify Events
OC7.4.6.1 Events On The National Electricity Transmission System
In the case of an Event on the National Electricity Transmission System which has had (or
may have had) an Operational Effect on the System(s) of a User or Users, NGET will notify
the User or Users whose System(s) have been, or may have been, in the reasonable opinion of
NGET, affected, in accordance with OC7.
OC7.4.6.2 Events On A User's System
In the case of an Event on the System of a User which has had (or may have had) an
Operational Effect on the National Electricity Transmission System, the User will notify
NGET in accordance with OC7.
OC7.4.6.3 Events Caused By Another Event Or By An Operation
An Event may be caused (or exacerbated by) another Event or by an Operation on another's
System (including on an Embedded Power Station) (or by the equivalent of an Event or
Operation on the equivalent of a System of an Externally Interconnected System Operator or
Interconnector User) and in that situation the information to be notified is different to that where
the Event arose independently of any other Event or Operation, as more particularly provided in
OC7.4.6.7.
OC7.4.6.4 NGET or a User, as the case may be, may enquire of the other whether an Event has occurred
on the other's System. If it has, and the party on whose System the Event has occurred is of the
opinion that it may have had an Operational Effect on the System of the party making the
enquiry, it shall notify the enquirer in accordance with OC7.
OC7.4.6.5 Examples Of Situations Where Notification By NGET Or A User May Be Required
Whilst in no way limiting the general requirement to notify set out in OC7.4.6.1, OC7.4.6.2 and
OC7.4.6.3, the following are examples of situations where notification in accordance with
OC7.4.6 will be required if they have an Operational Effect:
(a) where Plant and/or Apparatus is being operated in excess of its capability or may present
a hazard to personnel;
(b) the activation of any alarm or indication of any abnormal operating condition;
(c) adverse weather conditions being experienced;
(d) breakdown of, or faults on, or temporary changes in the capabilities of, Plant and/or
Apparatus;

Issue 5 Revision 19 OC7 30 September 2016


6 of 18
(e) breakdown of, or faults on, control, communication and metering equipment; or
(f) increased risk of inadvertent protection operation.
Form
OC7.4.6.6 A notification and any response to any questions asked under OC7.4.6.1 and OC7.4.6.2 of an
Event which has arisen independently of any other Event or of an Operation, will describe the
Event, although it need not state the cause of the Event, and, subject to that, will be of sufficient
detail to enable the recipient of the notification reasonably to consider and assess the
implications and risks arising and will include the name of the individual reporting the Event on
behalf of NGET or the User, as the case may be. The recipient may ask questions to clarify the
notification and the giver of the notification will, insofar as it is able (although it need not state the
cause of the Event) answer any questions raised. NGET may pass on the information contained
in the notification as provided in OC7.4.6.7.
OC7.4.6.7 (a) A notification (and any response to any questions asked under OC7.4.6.1) by NGET of (or
relating to) an Event under OC7.4.6.1 which has been caused by (or exacerbated by)
another Event (the "first Event") or by an Operation on a User's System will describe the
Event and will contain the information which NGET has been given in relation to the first
Event or that Operation by the User (but otherwise need not state the cause of the Event).
The notification and any response to any questions asked (other than in relation to the
information which NGET is merely passing on from a User) will be of sufficient detail to
enable the recipient of the notification reasonably to consider and assess the implications
and risks arising from the Event on the National Electricity Transmission System and
will include the name of the individual reporting the Event on behalf of NGET. The recipient
may ask questions to clarify the notification and NGET will, insofar as it is able, answer any
questions raised, provided that in relation to the information which NGET is merely passing
on from a User, in answering any question NGET will not pass on anything further than that
which it has been told by the User which has notified it.
(b) Where a User is reporting an Event or an Operation which itself has been caused by (or
exacerbated by) an incident or scheduled or planned action affecting (but not on) its
System the notification to NGET will contain the information which the User has been given
by the person connected to its System in relation to that incident or scheduled or planned
action (which the User must require, contractually or otherwise, the person connected to its
System to give to it) and NGET may pass on the information contained in the notification as
provided in this OC7.4.6.7.
OC7.4.6.8 Where an Event on the National Electricity Transmission System falls to be reported by
NGET under an Interconnection Agreement and the Event has been caused by (or
exacerbated by) another Event (the "first Event") or by an Operation on a User's System,
NGET will include in that report the information which NGET has been given in relation to the first
Event or that Operation by the User (including any information relating to an incident or
scheduled or planned action on that User's System, as provided in OC7.4.6.7).
OC7.4.6.9 (a) A notification to a User (and any response to any questions asked under OC7.4.6.1) by
NGET of (or relating to) an Event under OC7.4.6.1 which has been caused by (or
exacerbated by) the equivalent of an Event or of an Operation on the equivalent of a
System of an Externally Interconnected System Operator or Interconnector User, will
describe the Event on the National Electricity Transmission System and will contain the
information which NGET has been given, in relation to the equivalent of an Event or of an
Operation on the equivalent of a System of an Externally Interconnected System
Operator or Interconnector User, by that Externally Interconnected System Operator
or Interconnector User (but otherwise need not state the cause of the Event).

Issue 5 Revision 19 OC7 30 September 2016


7 of 18
(b) The notification and any response to any questions asked (other than in relation to the
information which NGET is merely passing on from that Externally Interconnected
System Operator or Interconnector User) will be of sufficient detail to enable the recipient
of the notification reasonably to consider and assess the implications and risks arising from
the Event on the National Electricity Transmission System and will include the name of
the individual reporting the Event on behalf of NGET. The recipient may ask questions to
clarify the notification and NGET will, insofar as it is able (although it need not state the
cause of the Event) answer any questions raised, provided that, in relation to the
information which NGET is merely passing on from an Externally Interconnected System
Operator or Interconnector User, in answering any question NGET will not pass on
anything further than that which it has been told by the Externally Interconnected System
Operator or Interconnector User which has notified it.
OC7.4.6.10 (a) A Network Operator may pass on the information contained in a notification to it from
NGET under OC7.4.6.1, to a Generator with a Generating Unit or a Power Park Module
connected to its System or to a DC Converter Station owner with a DC Converter
connected to its System or to the operator of another User System connected to its
System (which, for the avoidance of doubt, could be a Network Operator), in connection
with reporting the equivalent of an Event under the Distribution Code (or the contract
pursuant to which that Generating Unit or Power Park Module or DC Converter or other
User System is connected to the System of that Network Operator) (if the Event on the
National Electricity Transmission System caused or exacerbated it).
(b) A Generator may pass on the information contained in a notification to it from NGET under
OC7.4.6.1, to another Generator with a Generating Unit or a Power Park Module
connected to its System or to the operator of a User System connected to its System
(which, for the avoidance of doubt, could be a Network Operator), if it is required (by a
contract pursuant to which that Generating Unit or that Power Park Module or that User
System is connected to its System) to do so in connection with the equivalent of an Event
on its System (if the Event on the National Electricity Transmission System caused or
exacerbated it).
OC7.4.6.11 (a) Other than as provided in OC7.4.6.10, a Network Operator or a Generator, may not pass
on any information contained in a notification to it from NGET under OC7.4.6.1 (and an
operator of a User System or Generator receiving information which was contained in a
notification to a Generator or a Network Operator, as the case may be, from NGET under
OC7.4.6.1, as envisaged in OC7.4.6.10 may not pass on this information) to any other
person, but may inform persons connected to its System (or in the case of a Generator
which is also a Supplier, inform persons to which it supplies electricity which may be
affected) that there has been an incident on the Total System, the general nature of the
incident (but not the cause of the incident) and (if known and if power supplies have been
affected) an estimated time of return to service.
(b) In the case of a Generator which has an Affiliate which is a Supplier, the Generator may
inform it that there has been an incident on the Total System, the general nature of the
incident (but not the cause of the incident) and (if known and if power supplies have been
affected in a particular area) an estimated time of return to service in that area, and that
Supplier may pass this on to persons to which it supplies electricity which may be affected).
(c) Each Network Operator and Generator shall use its reasonable endeavours to procure
that any Generator or operator of a User System receiving information which was
contained in a notification to a Generator or Network Operator, as the case may be, from
NGET under OC7.4.6.1, which is not bound by the Grid Code, does not pass on any
information other than as provided above.

Issue 5 Revision 19 OC7 30 September 2016


8 of 18
OC7.4.6.12 When an Event relating to a Generating Unit, a Power Park Module or a DC Converter (or
OTSUA operational prior to the OTSUA Transfer Time), has been reported to NGET by a
Generator or DC Converter Station owner under OC7.4.6 and it is necessary in order for the
Generator or DC Converter Station owner to assess the implications of the Event on its
System more accurately, the Generator or DC Converter Station owner may ask NGET for
details of the fault levels from the National Electricity Transmission System to that
Generating Unit, Power Park Module or DC Converter (or OTSUA operational prior to the
OTSUA Transfer Time) at the time of the Event, and NGET will, as soon as reasonably
practicable, give the Generator or DC Converter Station owner that information provided that
NGET has that information.
OC7.4.6.13 Except in an emergency situation the notification of an Event will, if either party requests, be
recorded by the sender and dictated to the recipient, who shall record and repeat each phrase as
it is received and on completion of the dictation shall repeat the notification in full to the sender
who shall confirm that it has been accurately recorded.
Timing
OC7.4.6.14 A notification under OC7.4.6 shall be given as soon as possible after the occurrence of the
Event, or time that the Event is known of or anticipated by the giver of the notification under
OC7, and in any event within 15 minutes of such time.
OC7.4.7 Significant Incidents
OC7.4.7.1 Where a User notifies NGET of an Event under OC7 which NGET considers has had or may
have had a significant effect on the National Electricity Transmission System, NGET will
require the User to report that Event in writing in accordance with the provisions of OC10 and
will notify that User accordingly.
OC7.4.7.2 Where NGET notifies a User of an Event under OC7 which the User considers has had or may
have had a significant effect on that User's System, that User will require NGET to report that
Event in writing in accordance with the provisions of OC10 and will notify NGET accordingly.
OC7.4.7.3 Events which NGET requires a User to report in writing pursuant to OC7.4.7.1, and Events
which a User requires NGET to report in writing pursuant to OC7.4.7.2, are known as
"Significant Incidents".
OC7.4.7.4 Without limiting the general description set out in OC7.4.7.1 and OC7.4.7.2, a Significant
Incident will include Events having an Operational Effect which result in, or may result in, the
following:
(a) operation of Plant and/or Apparatus either manually or automatically;
(b) voltage outside statutory limits;
(c) Frequency outside statutory limits; or
(d) System instability.

OC 7.4.8 National Electricity Transmission System Warnings


OC7.4.8.1 Role Of National Electricity Transmission System Warnings
National Electricity Transmission System Warnings as described below provide information
relating to System conditions or Events and are intended to:
(i) alert Users to possible or actual Plant shortage, System problems and/or Demand
reductions;
(ii) inform of the applicable period;
(iii) indicate intended consequences for Users; and
(iv) enable specified Users to be in a state of readiness to react properly to instructions
received from NGET.

Issue 5 Revision 19 OC7 30 September 2016


9 of 18
A table of National Electricity Transmission System Warnings, set out in the Appendix to
OC7, summarises the warnings and their usage. In the case of a conflict between the table and
the provisions of the written text of OC7, the written text will prevail.
OC7.4.8.2 Recipients Of National Electricity Transmission System Warnings
(a) Where National Electricity Transmission System Warnings,(except those relating to
Demand Control Imminent), are applicable to System conditions or Events which have
widespread effect, NGET will notify all Users under OC7.
(b) Where in NGETs judgement System conditions or Events may only have a limited effect,
the National Electricity Transmission System Warning will only be issued to those
Users who are or may in NGETs judgement be affected.
(c) Where a National Electricity Transmission System Warning - Demand Control
Imminent is issued it will only be sent to those Users who are likely to receive Demand
Control instructions from NGET.
OC7.4.8.3 Preparatory Action
(a) Where possible, and if required, recipients of the warnings should take such preparatory
action as they deem necessary taking into account the information contained in the
National Electricity Transmission System Warning. All warnings will be of a form
determined by NGET and will remain in force from the stated time of commencement until
the cancellation, amendment or re-issue, as the case may be, is notified by NGET.
(b) Where a National Electricity Transmission System Warning has been issued to a
Network Operator and is current, Demand Control should not (subject as provided below)
be employed unless instructed by NGET. If Demand Control is, however, necessary to
preserve the integrity of the Network Operator's System, then the impact upon the
integrity of the Total System should be considered by the Network Operator and where
practicable discussed with NGET prior to its implementation.
Where a National Electricity Transmission System Warning has been issued to a
Supplier, further Customer Demand Management (in addition to that previously notified
under OC1 - Demand Forecasts) must only be implemented following notification to NGET.
(c) National Electricity Transmission System Warnings will be issued by such data
transmission facilities as have been agreed between NGET and Users. In the case of
Generators with Gensets this will normally be at their Trading Points (if they have notified
NGET that they have a Trading Point).
(d) Users may at times be informed by telephone of National Electricity Transmission
System Warnings and in these circumstances confirmation will be sent to those Users so
notified by such data transmission facilities as have been agreed between NGET and
Users, as soon as possible.
OC7.4.8.4 Types Of National Electricity Transmission System Warnings
National Electricity Transmission System Warnings consist of the following types:-
(i) National Electricity Transmission System Warning - Electricity Margin Notice
(ii) National Electricity Transmission System Warning - High Risk of Demand Reduction
(iii) National Electricity Transmission System Warning - Demand Control Imminent
(iv) National Electricity Transmission System Warning - Risk of System Disturbance
OC7.4.8.5 National Electricity Transmission System Warning - Electricity Margin Notice
A National Electricity Transmission System Warning - Electricity Margin Notice may be
issued to Users in accordance with OC7.4.8.2, at times when there is a reduced System
Margin, as determined under BC1.5.4. It will contain the following information:
(i) the period for which the warning is applicable; and
(ii) the availability shortfall in MW; and
Issue 5 Revision 19 OC7 30 September 2016
10 of 18
(iii) intended consequences for Users, including notification that Maximum Generation
Service may be instructed.
OC 7.4.8.6 National Electricity Transmission System Warning - High Risk of Demand Reduction
(a) A National Electricity Transmission System Warning - High Risk of Demand
Reduction may be issued to Users in accordance with OC7.4.8.2 at times when there is a
reduced System Margin, as determined under BC1.5.4 and in NGETs judgement there is
increased risk of Demand reduction being implemented under OC6.5.1. It will contain the
following information in addition to the required information in a National Electricity
Transmission System Warning - Electricity Margin Notice:
(i) the possible percentage level of Demand reduction required; and
(ii) Specify those Network Operators and Non Embedded Customers who may
subsequently receive instructions under OC6.5.1.
(b) A National Electricity Transmission System Warning - High Risk of Demand
Reduction may also be issued by NGET to those Network Operators and Non
Embedded Customers who may subsequently receive instructions under OC6.5.1 relating
to a Demand reduction in circumstances not related to System Margin (for example
Demand reduction required to manage System overloading).
The National Electricity Transmission System Warning - High Risk of Demand
Reduction will specify the period during which Demand reduction may be required and the
part of the Total System to which it applies and any other matters specified in OC6.5.
OC7.4.8.6.1 Protracted Periods Of Generation Shortage
(a) Whenever NGET anticipates that a protracted period of generation shortage may exist a
National Electricity Transmission System Warning - Electricity Margin Notice or High
Risk of Demand Reduction may be issued, to give as much notice as possible to those
Network Operators and Non Embedded Customers who may subsequently receive
instructions under OC6.5.
(b) A National Electricity Transmission System Warning - High Risk of Demand
Reduction will in these instances include an estimate of the percentage of Demand
reduction that may be required and the anticipated duration of the Demand reduction. It
may also include information relating to estimates of any further percentage of Demand
reduction that may be required.
(c) The issue of the National Electricity Transmission System Warning - Electricity Margin
Notice or High Risk of Demand Reduction is intended to enable recipients to plan ahead
on the various aspects of Demand reduction.
OC7.4.8.7 National Electricity Transmission System Warning - Demand Control Imminent
(a) A National Electricity Transmission System Warning - Demand Control Imminent,
relating to a Demand reduction under OC6.5, will be issued by NGET to Users in
accordance with OC7.4.8.2. It will specify those Network Operators who may subsequently
receive instructions under OC6.5.
(b) A National Electricity Transmission System Warning - Demand Control Imminent,
need not be preceded by any other National Electricity Transmission System Warning
and will be issued when a Demand reduction is expected within the following 30 minutes,
but will not cease to have effect after 30 minutes from its issue. However, NGET will either
reissue the National Electricity Transmission System Warning - Demand Control
Imminent or cancel the National Electricity Transmission System Warning - Demand
Control Imminent no later than 2 hours from first issue, or from re-issue, as the case may
be.

Issue 5 Revision 19 OC7 30 September 2016


11 of 18
OC7.4.8.8 National Electricity Transmission System Warning - Risk of System Disturbance
(a) A National Electricity Transmission System Warning - Risk of System Disturbance will
be issued by NGET to Users who may be affected when NGET knows there is a risk of
widespread and serious disturbance to the whole or part of, the National Electricity
Transmission System;
(b) The National Electricity Transmission System Warning - Risk of System Disturbance
will contain such information as NGET deems appropriate;
(c) for the duration of the National Electricity Transmission System Warning - Risk of
System Disturbance, each User in receipt of the National Electricity Transmission
System Warning - Risk of System Disturbance shall take the necessary steps to warn its
operational staff and to maintain its Plant and/or Apparatus in the condition in which it is
best able to withstand the anticipated disturbance;
(d) During the period that the National Electricity Transmission System Warning - Risk of
System Disturbance is in effect, NGET may issue Emergency Instructions in
accordance with BC2 and it may be necessary to depart from normal Balancing
Mechanism operation in accordance with BC2 in issuing Bid-Offer Acceptances.
OC7.4.8.9 Cancellation of National Electricity Transmission System Warning
(a) NGET will give notification of a Cancellation of National Electricity Transmission
System Warning to all Users issued with the National Electricity Transmission System
Warning when in NGETs judgement System conditions have returned to normal.
(b) A Cancellation of National Electricity Transmission System Warning will identify the
type of National Electricity Transmission System Warning being cancelled and the
period for which it was issued. The Cancellation of National Electricity Transmission
System Warning will also identify any National Electricity Transmission System
Warnings that are still in force.
OC7.4.8.10 General Management Of National Electricity Transmission System Warnings
(a) National Electricity Transmission System Warnings remain in force for the period
specified unless superseded or cancelled by NGET.
(b) A National Electricity Transmission System Warning issued for a particular period may
be superseded by further related warnings. This will include National Electricity
Transmission System Warning - Electricity Margin Notice being superseded by
National Electricity Transmission System Warning - High Risk of Demand Reduction
and vice-versa.
(c) In circumstances where it is necessary for the period of a National Electricity
Transmission System Warning to be changed:
(i) the period applicable may be extended by the issue of a National Electricity
Transmission System Warning with a period which follows on from the original
period, or
(ii) revised or updated National Electricity Transmission System Warnings will be
issued where there is an overlap with the period specified in an existing National
Electricity Transmission System Warning, but only if the revised period also
includes the full period of the existing National Electricity Transmission System
Warning.
In any other case the existing National Electricity Transmission System Warning will be
cancelled and a new one issued.
(d) A National Electricity Transmission System Warning is no longer applicable once the
period has passed and to confirm this NGET will issue a Cancellation of National
Electricity Transmission System Warning.

OC7.5 PROCEDURE IN RELATION TO INTEGRAL EQUIPMENT TESTS


Issue 5 Revision 19 OC7 30 September 2016
12 of 18
OC7.5.1 This section of the Grid Code deals with Integral Equipment Tests. It is designed to provide a
framework for the exchange of relevant information and for discussion between NGET and
certain Users in relation to Integral Equipment Tests.
OC7.5.2 An Integral Equipment Test :
(a) is carried out in accordance with the provisions of this OC7.5 at:
(i) a User Site,
(ii) a Transmission Site,
(iii) an Embedded Large Power Station, or,
(iv) an Embedded DC Converter Station;
(b) will normally be undertaken during commissioning or re-commissioning of Plant and/or
Apparatus;
(c) may, in the reasonable judgement of the person wishing to perform the test, cause, or have
the potential to cause, an Operational Effect on a part or parts of the Total System but
which with prior notice is unlikely to have a materially adverse effect on any part of the Total
System; and
(d) may form part of an agreed programme of work.
In the case of OTSUA operational prior to the OTSUA Transfer Time, a Users Site or
Transmission Site shall, for the purposes of this OC7, include a site at which there is an
Interface Point until the OTSUA Transfer Time and the provisions of this OC7.5 and references
to OTSUA shall be construed and applied accordingly until the OTSUA Transfer Time.
OC7.5.3 A set of guidance notes is available from NGET on request, which provide further details on
suggested procedures, information flows and responsibilities.
Notification Of An IET
OC7.5.4 In order to undertake an Integral Equipment Test (and subject to OC7.5.8 below), the User or
NGET, as the case may be, (the proposer) must notify the other (the recipient) of a proposed
IET. Reasonable advance notification must be given, taking into account the nature of the test
and the circumstances which make the test necessary. This will allow recipients time to
adequately assess the impact of the IET on their System.
OC7.5.5 The notification of the IET must normally include the following information:-
(a) the proposed date and time of the IET;
(b) the name of the individual and the organisation proposing the IET;
(c) a proposed programme of testing; and
(d) such further detail as the proposer reasonably believes the recipient needs in order to
assess the effect the IET may have on relevant Plant and/or Apparatus.
OC7.5.6 In the case of an IET in connection with commissioning or re-commissioning, the test should be
incorporated as part of any overall commissioning programme agreed between NGET and the
User.
Response To Notification Of An IET
OC7.5.7 The recipient of notification of an IET must respond within a reasonable timescale prior to the
start time of the IET and will not unreasonably withhold or delay acceptance of the IET proposal.
OC7.5.8 (a) Where NGET receives notification of a proposed IET from a User, NGET will consult those
other Users whom it reasonably believes may be affected by the proposed IET to seek their
views. Information relating to the proposed IET may be passed on by NGET with the prior
agreement of the proposer. However it is not necessary for NGET to obtain the agreement
of any such User as IETs should not involve the application of irregular, unusual or extreme
conditions. NGET may however consider any comments received when deciding whether or
not to agree to an IET.
Issue 5 Revision 19 OC7 30 September 2016
13 of 18
(b) In the case of an Embedded Large Power Station or Embedded DC Converter Station,
the Generator or DC Converter Station owner as the case may be must liaise with both
NGET and the relevant Network Operator. NGET will not agree to an IET relating to such
Plant until the Generator or DC Converter Station owner has shown that it has the
agreement of the relevant Network Operator.
(c) A Network Operator will liaise with NGET as necessary in those instances where it is
aware of an Embedded Small Power Station or an Embedded Medium Power Station
which intends to perform tests which in the reasonable judgement of the Network Operator
may cause an Operational Effect on the National Electricity Transmission System.
OC7.5.9 The response from the recipient, following notification of an IET must be one of the following:
(a) to accept the IET proposal;
(b) to accept the IET proposal conditionally subject to minor modifications such as date and
time;
(c) not to agree the IET, but to suggest alterations to the detail and timing of the IET that are
necessary to make the IET acceptable.
Final Confirmation Of An IET
OC7.5.10 The date and time of an IET will be confirmed between NGET and the User, together with any
limitations and restrictions on operation of Plant and/or Apparatus.
OC7.5.11 The IET may subsequently be amended following discussion and agreement between NGET and
the User.
Carrying Out An IET
OC7.5.12 IETs may only take place when agreement has been reached and must be carried out in
accordance with the agreed programme of testing.
OC7.5.13 The implementation of an IET will be notified in accordance with OC7.4.5.
OC7.5.14 Where elements of the programme of testing change during the IET, there must be discussion
between the appropriate parties to identify whether the IET should continue.

OC7.6 PROCEDURE IN RESPECT OF OPERATIONAL SWITCHING IN SCOTLAND AND


OFFSHORE
OC7.6.1 This section OC7.6 of the Grid Code sets out the procedure to be followed for Operational
Switching in Scotland and Offshore. Its provisions are supplementary to the provisions of the
rest of this OC7.
It is designed to set down the arrangements for NGET, Users and the Relevant Transmission
Licensees in respect of the Operational Switching of Plant and Apparatus at a Connection
Site and parts of the National Electricity Transmission System adjacent to that Connection
Site.
OC7.6.2 In general:
(i) NGET is responsible for directing the configuration of the National Electricity
Transmission System
(ii) Each Relevant Transmission Licensee is responsible for the instruction and operation of
its Plant and Apparatus on its Transmission System
(iii) Each User is responsible for the configuration, instruction and operation of its Plant and
Apparatus.
Definitive schedules of these responsibilities for each Connection Site are contained in the
relevant Site Responsibility Schedules.

Issue 5 Revision 19 OC7 30 September 2016


14 of 18
For the avoidance of doubt, where a User operates Transmission Plant and Apparatus on
behalf of a Relevant Transmission Licensee, NGET cannot instruct the User to operate that
Plant and Apparatus.
Planned Operational Switching
OC7.6.3 Following the notification of an Operation under OC7.4.5, NGET and the User shall discuss the
Operational Switching required. NGET will then discuss and agree the details of the
Operational Switching with the Relevant Transmission Licensee. The Relevant
Transmission Licensee shall then make contact with the User to initiate the Operational
Switching. For the avoidance of doubt, from the time that the Relevant Transmission
Licensee makes contact with the User, the Relevant Transmission Licensee shall then
become the primary point of operational contact with the User in relation to OC7 for matters
which would or could affect, or would or could be affected by the Operational Switching.
OC7.6.4 The User shall be advised by the Relevant Transmission Licensee on the completion of the
Operational Switching, that NGET shall again become the primary point of operational contact
for the User in relation to OC7.
OC7.6.5 During Operational Switching, either the Relevant Transmission Licensee or the User may
need to unexpectedly terminate the Operational Switching. NGET may also need to terminate
the Operational Switching during the Operational Switching. In the event of unexpected
termination of the Operational Switching, NGET shall become the primary point of operational
contact for the User in relation to OC7. Following the termination of the Operational Switching,
it will not be permitted to restart that Operational Switching without the parties again following
the process described in OC7.6.3.
Emergencies
OC7.6.6 For Operations and/or Events that present an immediate hazard to the safety of personnel,
Plant or Apparatus, the Relevant Transmission Licensee may:
(i) as permitted by the STC, carry out Operational Switching of Plant and Apparatus on its
Transmission System without reference to NGET and the User, and
(ii) request a User to carry out Operational Switching without the User first receiving
notification from NGET.
In such emergency circumstances, communication between the Relevant Transmission
Licensee and the User shall normally be by telephone and will include an exchange of names.
The User shall use all reasonable endeavours to carry out Operational Switching on its Plant
and Apparatus without delay. Following completion of the requested Operational Switching,
the Relevant Transmission Licensee shall notify NGET of the Operational Switching which
has taken place. In such emergency circumstances, the User may only refuse to carry out
Operational Switching on safety grounds (relating to personnel or plant) and this must be
notified to the Relevant Transmission Licensee immediately by telephone.
OC7.6.7 For Operations and/or Events that present an immediate hazard to the safety of personnel,
Plant or Apparatus, and which require Operational Switching of Plant or Apparatus on a
Transmission System in order to remove the hazard, the User should contact the Relevant
Transmission Licensee directly to request Operational Switching of Plant or Apparatus on
its Transmission System.
In such emergency circumstances, communication between the Relevant Transmission
Licensee and the User shall normally be by telephone and will include an exchange of names.
The Relevant Transmission Licensee shall use all reasonable endeavours to carry out
Operational Switching on its Plant and Apparatus without delay. Following completion of the
requested Operational Switching, the User shall notify NGET of the Operational Switching
which has taken place. In such emergency circumstances, the Relevant Transmission
Licensee may only refuse to carry out Operational Switching on safety grounds (relating to
personnel or plant) and this must be notified to the User immediately by telephone.

Issue 5 Revision 19 OC7 30 September 2016


15 of 18
OC7.6.8 Establishment Of A Local Switching Procedure
(a) NGET, a User or a Relevant Transmission Licensee may reasonably require a Local
Switching Procedure to be established.
(b) Where the need for a Local Switching Procedure arises the following provisions shall
apply:
(i) NGET, User(s) and the Relevant Transmission Licensee will discuss and agree
the detail of the Local Switching Procedure as soon as the requirement for a
Local Switching Procedure is identified. NGET will notify the Relevant
Transmission Licensee and the affected User(s) and will initiate these
discussions.
(ii) Each Local Switching Procedure shall be in relation to either one or more
Connection Sites (or in the case of OTSUA operational prior to the OTSUA
Transfer Time, Transmission Interface Sites) and parts of the National
Electricity Transmission System adjacent to the Connection Site(s) (or in the
case of OTSUA operational prior to the OTSUA Transfer Time, Transmission
Interface Sites)
(iii) A draft Local Switching Procedure shall be prepared by the Relevant
Transmission Licensee to reflect the agreement reached and shall be sent to
NGET.
(iv) When a Local Switching Procedure has been prepared, it shall be sent by NGET
to the Relevant Transmission Licensee and User(s) for confirmation of its
accuracy.
(v) The Local Switching Procedure shall then be signed on behalf of NGET and on
behalf of each User and Relevant Transmission Licensee by way of written
confirmation of its accuracy.
(vi) Once agreed under this OC7.6.8, the procedure will become a Local Switching
Procedure under the Grid Code, and (subject to any change pursuant to this OC7)
will apply between NGET, Relevant Transmission Licensee and the relevant
User(s) as if it were part of the Grid Code.
(vii) Once signed, NGET will send a copy of the Local Switching Procedure to the
Relevant Transmission Licensee and the User(s).
(viii) An agreed Local Switching Procedure should be referenced by relevant Site
Responsibility Schedules.
(ix) NGET, the User(s) and the Relevant Transmission Licensee must make the
Local Switching Procedure readily available to the relevant operational staff.
(x) If the Relevant Transmission Licensee or the User(s) become aware that a
change is needed to a Local Switching Procedure, they must inform NGET
immediately. Where NGET has been informed of a need for a change, or NGET
proposes a change, NGET shall notify both the affected User and the Relevant
Transmission Licensee and will initiate discussions to agree a change to the
Local Switching Procedure. The principles applying to the establishment of a new
Local Switching Procedure shall then apply to the discussion and agreement of
any changes.

Issue 5 Revision 19 OC7 30 September 2016


16 of 18
WARNING TYPE GRID FORMAT TO: FOR ACTION TO: FOR TIMESCALE WARNING OF/OR RESPONSE FROM RECIPIENTS
CODE INFORMATION CONSEQUENCE

NATIONAL ELECTRICITY OC7.4.8.5 Fax or Generators, Network All timescales when Insufficient generation Offers of increased availability from
TRANSMISSION other Suppliers, Operators, Non- at the time there is available to meet forecast Generators or DC Converter Station
WARNING electronic Externally Interconected Embedded not a high risk of Demand plus Operating owners and Interconnector Users.
ELECTRICITY MARGIN means System Operators, DC Customers Demand reduction. Margin.

Issue 5 Revision 19
NOTICE Converter Station owners Suppliers notify NGET of any
Primarily 1200 hours Notification that if not additional Customer Demand
onwards for a future improved Demand Management that they will initiate.
period. reduction may be
instructed.

(Normal initial warning of


insufficient System Margin

NATIONAL ELECTRICITY OC7.4.8.6 Fax or Generators, All timescales where Insufficient generation Offers of increased availability from
TRANSMISSION other Suppliers, there is a high risk of available to meet forecast Generators or DC Converter Station
SYSTEM WARNING electronic Network Operators, Demand Reduction. Demand plus Operating owners and Interconnector Users.
High risk of Demand means Non-Embedded Margin and/or a high risk of
Reduction Customers, Primarily 1200 hours Demand Reduction being Suppliers notify NGET of any
Externally Interconnected onwards for a future instructed. additional Customer Demand
System Operators, DC period Management that they will initiate.
Converter Station Owners (May be issued locally as
demand reduction risk only Specified Network Operators and
for circuit overloads) Non-Embedded Customers to
prepare their Demand Reduction

OC7
17 of 18
arrangements and take actions as
necessary to enable compliance with
NGET instructions that may follow.

(Percentages of Demand Reduction


above 20% may not be achieved if
WARNINGS TABLE

NGET has not issued the warning by


16:00 hours the previous day.)

< END OF OPERATING CODE NO. 7 >


NATIONAL ELECTRICITY OC7.4.8.7 Fax/Teleph Specified Users only: (to None Within 30 minutes of Possibility of Demand Network Operators specified to
TRANSMISSION one or whom an instruction is to anticipated Reduction within 30 prepare to take action as necessary
SYSTEM WARNING other be given) instruction minutes to enable them to comply with any
Demand Control electronic Network Operators, Non- subsequent NGET instruction for
Imminent means Embedded Customers Demand reduction.

NATIONAL ELECTRICITY OC7.4.8.8 Fax/Teleph Generators, DC Converter Suppliers Control room time Risk of, widespread system Recipients take steps to warn
TRANSMISSION one or Station owners scales disturbance to whole or part operational staff and maintain plant or
SYSTEM WARNING other Network Operators, Non- of the National Electricity apparatus such that they are best
Risk of System electronic Embedded Customers, Transmission System able to withstand the disturbance.
Disturbance means Externally Interconnected
System Operators who
APPENDIX 1 - NATIONAL ELECTRICITY TRANSMISSION SYSTEM

may be affected.

30 September 2016
Issue 5 Revision 19 OC7 30 September 2016
18 of 18
OPERATING CODE NO. 8
(OC8)

SAFETY CO-ORDINATION

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC8.1 INTRODUCTION.................................................................................................................................. 2
OC8.2 OBJECTIVE ......................................................................................................................................... 2
OC8.3 SCOPE................................................................................................................................................. 2
OC8.4 PROCEDURE ...................................................................................................................................... 2
OC8.4.1 Safety Co-Ordination In Respect Of The E&W Transmission Systems Or The Systems
Of E&W Users............................................................................................................................................ 2
OC8.4.2 Safety Co-Ordination In Respect Of The Scottish Transmission Systems Or The
Systems Of Scottish Users ........................................................................................................................ 3

Issue 5 Revision 8 OC8 10 June 2014


i
OC8.1 INTRODUCTION
OC8.1.1 OC8 specifies the standard procedures to be used for the co-ordination, establishment and
maintenance of necessary Safety Precautions when work is to be carried out on or near the
National Electricity Transmission System or the System of a User and when there is a
need for Safety Precautions on HV Apparatus on the other System for this work to be
carried out safely. OC8 Appendix 1 applies when work is to be carried out on or near to E&W
Transmission Systems or the Systems of E&W Users and OC8 Appendix 2 applies when
work is to be carried out on or near to Scottish Transmission Systems or the Systems of
Scottish Users.
OC8.1.2 OC8 also covers the co-ordination, establishment and maintenance of necessary safety
precautions on the Implementing Safety Co-ordinators System when work is to be
carried out at a Users Site or a Transmission Site (as the case may be) on equipment of
the User or a Transmission Licensee as the case may be where the work or equipment is
near to HV Apparatus on the Implementing Safety Co-ordinators System.

OC8.2 OBJECTIVE
OC8.2.1 The objective of OC8 is to achieve:
(i) Safety From The System when work on or near a System necessitates the provision
of Safety Precautions on another System on HV Apparatus up to a Connection
Point; and
(ii) Safety From The System when work is to be carried out at a Users Site or a
Transmission Site (as the case may be) on equipment of the User or a Transmission
Licensee (as the case may be) where the work or equipment is near to HV Apparatus
on the Implementing Safety Co-ordinators System.

OC8.3 SCOPE
OC8.3.1 OC8 applies to NGET and to Users, which in OC8 means:
(a) Generators (including where undertaking OTSDUW);
(b) Network Operators; and
(c) Non-Embedded Customers.
In Scotland and Offshore OC8 also applies to Relevant Transmission Licensees.
The procedures for the establishment of safety co-ordination by NGET in relation to External
Interconnections are set out in Interconnection Agreements with relevant persons for the
External Interconnections.

OC8.4 PROCEDURE
OC8.4.1 Safety Co-Ordination In Respect Of The E&W Transmission Systems Or The Systems Of
E&W Users
OC8.4.1.1 OC8 Appendix 1, OC8A, applies when work is to be carried out on or near to the E&W
Transmission System or the Systems of E&W Users or when Safety Precautions are
required to be established on the E&W Transmission System or the Systems of E&W
Users when work is to be carried out on or near to the Scottish Transmission System or
the Systems of Scottish Users.

Issue 5 Revision 8 OC8 10 June 2014


2 of 3
OC8.4.2 Safety Co-Ordination In Respect Of The Scottish Transmission Systems Or The Systems Of
Scottish Users
OC8.4.2.1 OC8 Appendix 2, OC8B, applies when work is to be carried out on or near to the Scottish
Transmission System or the Systems of Scottish Users or when Safety Precautions are
required to be established on the Scottish Transmission System or the Systems of
Scottish Users when work is to be carried out on or near to the E&W Transmission
System or the Systems of E&W Users.
OC8.4.3 Safety Co-ordination Offshore
OC8.4.3.1 For the purposes of OC8 Appendix 1, OC8A, OC8 Appendix 2 and OC8B, when work is to
be carried out on or near to Offshore Transmission Systems Safety Precautions shall be
established by the Offshore Transmission Licensee and the Offshore User.

< END OF OPERATING CODE NO. 8 >

Issue 5 Revision 8 OC8 10 June 2014


3 of 3
OPERATING CODE NO. 8 APPENDIX 1
(OC8A)

SAFETY CO-ORDINATION IN RESPECT OF THE E&W TRANSMISSION SYSTEMS OR


THE SYSTEMS OF E&W USERS

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC8A.1 INTRODUCTION ............................................................................................................................... 2
OC8A.2 OBJECTIVE....................................................................................................................................... 3
OC8A.3 SCOPE .............................................................................................................................................. 4
OC8A.4 PROCEDURE.................................................................................................................................... 4
OC8A.4.1 Approval Of Local Safety Instructions..................................................................................... 4
OC8A.4.2 Safety Co-ordinators ............................................................................................................... 5
OC8A.4.3 RISSP ..................................................................................................................................... 5
OC8A.5 SAFETY PRECAUTIONS ON HV APPARATUS .............................................................................. 6
OC8A.5.1 Agreement Of Safety Precautions .......................................................................................... 6
OC8A.5.2 Implementation Of Isolation .................................................................................................... 6
OC8A.5.3 Implementation Of Earthing .................................................................................................... 7
OC8A.5.4 RISSP Issue Procedure .......................................................................................................... 8
OC8A.5.5 RISSP Cancellation Procedure............................................................................................. 10
OC8A.5.6 RISSP Change Control ......................................................................................................... 10
OC8A.6 TESTING AFFECTING ANOTHER SAFETY CO-ORDINATORS SYSTEM ................................. 10
OC8A.7 EMERGENCY SITUATIONS........................................................................................................... 11
OC8A.8 SAFETY PRECAUTIONS RELATING TO WORKING ON EQUIPMENT NEAR TO THE HV
SYSTEM .......................................................................................................................................................... 12
OC8A.8.1 Agreement of Safety Precautions ......................................................................................... 12
OC8A.8.2 Implementation of Isolation and Earthing ............................................................................. 12
OC8A.8.3 Permit For Work For Proximity Work Issue Procedure......................................................... 13
OC8A.8.4 Permit For Work For Proximity Work Cancellation Procedure ............................................. 13
OC8A.9 LOSS OF INTEGRITY OF SAFETY PRECAUTIONS..................................................................... 13
OC8A.10 SAFETY LOG ................................................................................................................................ 13
APPENDIX A - RISSP-R ................................................................................................................................. 14
APPENDIX B - RISSP-I................................................................................................................................... 16
APPENDIX C- FLOWCHARTS ....................................................................................................................... 18
APPENDIX C1 - RISSP ISSUE PROCESS ............................................................................................ 18
APPENDIX C2 - TESTING PROCESS ................................................................................................... 19
APPENDIX C3 - RISSP CANCELLATION PROCESS............................................................................ 20
APPENDIX C4 - PROCESS FOR WORKING NEAR TO SYSTEM EQUIPMENT ................................. 21
APPENDIX D - NATIONAL GRID SAFETY CIRCULAR................................................................................. 22
APPENDIX E - FORM OF NGET PERMIT TO WORK ................................................................................... 23

Issue 5 Revision 8 OC8A 10 June 2014


i
OC8A.1 INTRODUCTION
OC8A.1.1 OC8A specifies the standard procedures to be used by the Relevant E&W Transmission
Licensee, NGET (where NGET is not the Relevant E&W Transmission Licensee) and
Users for the co-ordination, establishment and maintenance of necessary Safety
Precautions when work is to be carried out on or near the E&W Transmission System or
the System of an E&W User and when there is a need for Safety Precautions on HV
Apparatus on the other's System for this work to be carried out safely. OC8A applies to
Relevant E&W Transmission Licensees and E&W Users only. Where work is to be
carried out on or near equipment on the Scottish Transmission System or Systems of
Scottish Users, but such work requires Safety Precautions to be established on the E&W
Transmission System or the Systems of E&W Users, OC8A should be followed by the
Relevant E&W Transmission Licensee and E&W Users to establish the required Safety
Precautions.
OC8B specifies the procedures to be used by the Relevant Scottish Transmission
Licensees and Scottish Users.
In this OC8A the term work includes testing, other than System Tests which are covered
by OC12.
OC8A.1.2 OC8A also covers the co-ordination, establishment and maintenance of necessary safety
precautions on the Implementing Safety Co-ordinators System when work is to be
carried out at an E&W Users Site or a Transmission Site (as the case may be) on
equipment of the E&W User or the Relevant E&W Transmission Licensee as the case
may be where the work or equipment is near to HV Apparatus on the Implementing Safety
Co-ordinators System. In the case of OTSUA, an E&W Users Site or Transmission
Site shall, for the purposes of this OC8A, include a site at which there is a Transmission
Interface Point until the OTSUA Transfer Time and the provisions of this OC8A and
references to OTSUA shall be construed and applied accordingly until the OTSUA Transfer
Time at which time arrangements in respect of the Transmission Interface Site will have
been put in place between the Relevant E&W Transmission Licensee and the Offshore
Transmission Licensee.
OC8A.1.3 OC8A does not apply to the situation where Safety Precautions need to be agreed solely
between E&W Users. OC8A does not apply to the situation where Safety Precautions
need to be agreed solely between Transmission Licensees.
OC8A.1.4 OC8A does not seek to impose a particular set of Safety Rules on the Relevant E&W
Transmission Licensee and E&W Users; the Safety Rules to be adopted and used by the
Relevant E&W Transmission Licensee and each E&W User shall be those chosen by
each.
OC8A.1.5 Site Responsibility Schedules document the control responsibility for each item of Plant
and Apparatus for each site.
OC8A.1.6 Defined Terms
OC8A.1.6.1 E&W Users should bear in mind that in OC8 only, in order that OC8 reads more easily with
the terminology used in certain Safety Rules, the term "HV Apparatus" is defined more
restrictively and is used accordingly in OC8A. E&W Users should, therefore, exercise
caution in relation to this term when reading and using OC8A.
OC8A.1.6.2 In OC8A only the following terms shall have the following meanings:
(1) "HV Apparatus" means High Voltage electrical circuits forming part of a System, on
which Safety From The System may be required or on which Safety Precautions may
be applied to allow work to be carried out on a System.
(2) "Isolation" means the disconnection of Apparatus from the remainder of the System in
which that Apparatus is situated by either of the following:
(a) an Isolating Device maintained in an isolating position. The isolating position must
either be:

Issue 5 Revision 8 OC8A 10 June 2014


2 of 24
(i) maintained by immobilising and Locking the Isolating Device in the isolating
position and affixing a Caution Notice to it. Where the Isolating Device is
Locked with a Safety Key, the Safety Key must be secured in a Key Safe
and the Key Safe Key must be, where reasonably practicable, given to the
authorised site representative of the Requesting Safety Co-ordinator and is
to be retained in safe custody. Where not reasonably practicable the Key
Safe Key must be retained by the authorised site representative of the
Implementing Safety Co-ordinator in safe custody; or
(ii) maintained and/or secured by such other method which must be in
accordance with the Local Safety Instructions of the Relevant E&W
Transmission Licensee or that E&W User, as the case may be; or
(b) an adequate physical separation which must be in accordance with, and
maintained by, the method set out in the Local Safety Instructions of the
Relevant E&W Transmission Licensee or that E&W User, as the case may be,
and, if it is a part of that method, a Caution Notice must be placed at the point of
separation;
or
(c) in the case where the relevant HV Apparatus of the Implementing Safety Co-
ordinator is being either constructed or modified, an adequate physical separation
as a result of a No System Connection.
(3) No System Connection means an adequate physical separation (which must be in
accordance with, and maintained by, the method set out in the Local Safety
Instructions of the Implementing Safety Co-ordinator) of the Implementing Safety
Co-ordinators HV Apparatus from the rest of the Implementing Safety Co-
ordinators System where such HV Apparatus has no installed means of being
connected to, and will not for the duration of the Safety Precaution be connected to, a
source of electrical energy or to any other part of the Implementing Safety Co-
ordinators System.
(4) "Earthing" means a way of providing a connection between conductors and earth by an
Earthing Device which is either:
(i) immobilised and Locked in the earthing position. Where the Earthing Device is
Locked with a Safety Key, the Safety Key must be secured in a Key Safe and the
Key Safe Key must be, where reasonably practicable, given to the authorised site
representative of the Requesting Safety Co-ordinator and is to be retained in safe
custody. Where not reasonably practicable the Key Safe Key must be retained by
the authorised site representative of the Implementing Safety Co-ordinator in safe
custody; or
(ii) maintained and/or secured in position by such other method which must be in
accordance with the Local Safety Instructions of the Relevant E&W
Transmission Licensee or that E&W User as the case may be.
OC8A.1.6.3 For the purpose of the co-ordination of safety relating to HV Apparatus the term Safety
Precautions means Isolation and/or Earthing.

OC8A.2 OBJECTIVE
OC8A.2.1 The objective of OC8A is to achieve:-
(i) Safety From The System when work on or near a System necessitates the provision
of Safety Precautions on another System on HV Apparatus up to a Connection
Point (or, in the case of OTSUA, Transmission Interface Point); and
(ii) Safety From The System when work is to be carried out at an E&W Users Site or a
Transmission Site (as the case may be) on equipment of the User or the Relevant
E&W Transmission Licensee (as the case may be) where the work or equipment is
near to HV Apparatus on the Implementing Safety Co-ordinators System.

Issue 5 Revision 8 OC8A 10 June 2014


3 of 24
OC8A.2.2 A flow chart, set out in OC8A Appendix C, illustrates the process utilised in OC8A to
achieve the objective set out in OC8A.2.1. In the case of a conflict between the flow chart
and the provisions of the written text of OC8A, the written text will prevail.
OC8A.3 SCOPE
OC8A.3.1 OC8A applies to the Relevant E&W Transmission Licensee and to E&W Users, which in
OC8A means:
(a) Generators (including where undertaking OTSDUW);
(b) Network Operators; and
(c) Non-Embedded Customers.
The procedures for the establishment of safety co-ordination by the Relevant E&W
Transmission Licensee in relation to External Interconnections are set out in
Interconnection Agreements with relevant persons for the External Interconnections.

OC8A.4 PROCEDURE
OC8A.4.1 Approval Of Local Safety Instructions
OC8A.4.1.1 (a) In accordance with the timing requirements of its Bilateral Agreement, each E&W
User will supply to the Relevant E&W Transmission Licensee a copy of its Local
Safety Instructions relating to its side of the Connection Point at each Connection
Site, or in the case of OTSUA a copy of its Local Safety Instructions relating to its
side of the Transmission Interface Point at each Transmission Interface Site.
(b) In accordance with the timing requirements of each Bilateral Agreement, the Relevant
E&W Transmission Licensee will supply to each E&W User a copy of its Local Safety
Instructions relating to the Transmission side of the Connection Point at each
Connection Site, or in the case of OTSUA a copy of its Local Safety Instructions
relating to the Transmission side of the Transmission Interface Point at each
Transmission Interface Site.
(c) Prior to connection the Relevant E&W Transmission Licensee and the E&W User
must have approved each other's relevant Local Safety Instructions in relation to
Isolation and Earthing.
OC8A.4.1.2 Either party may require that the Isolation and/or Earthing provisions in the other partys
Local Safety Instructions affecting the Connection Site (or, in the case of OTSUA,
Transmission Interface Site) should be made more stringent in order that approval of the
other partys Local Safety Instructions can be given. Provided these requirements are not
unreasonable, the other party will make such changes as soon as reasonably practicable.
These changes may need to cover the application of Isolation and/or Earthing at a place
remote from the Connection Site (or, in the case of OTSUA, Transmission Interface Site),
depending upon the System layout. Approval may not be withheld because the party
required to approve reasonably believes the provisions relating to Isolation and/or Earthing
are too stringent.
OC8A.4.1.3 If, following approval, a party wishes to change the provisions in its Local Safety
Instructions relating to Isolation and/or Earthing, it must inform the other party. If the
change is to make the provisions more stringent, then the other party merely has to note the
changes. If the change is to make the provisions less stringent, then the other party needs to
approve the new provisions and the procedures referred to in OC8A.4.1.2 apply.

Issue 5 Revision 8 OC8A 10 June 2014


4 of 24
OC8A.4.2 Safety Co-ordinators
OC8A.4.2.1 For each Connection Point, (or, in the case of OTSUA, Transmission Interface Point),
the Relevant E&W Transmission Licensee and each E&W User will at all times have
nominated and available a person or persons (Safety Co-ordinator(s)) to be responsible
for the co-ordination of Safety Precautions when work is to be carried out on a System
which necessitates the provision of Safety Precautions on HV Apparatus pursuant to
OC8A. A Safety Co-ordinator may be responsible for the co-ordination of safety on HV
Apparatus at more than one Connection Point (or, in the case of OTSUA, Transmission
Interface Point).
OC8A.4.2.2 Each Safety Co-ordinator shall be authorised by the Relevant E&W Transmission
Licensee or an E&W User, as the case may be, as competent to carry out the functions set
out in OC8A to achieve Safety From The System. Confirmation from the Relevant E&W
Transmission Licensee or an E&W User, as the case may be, that its Safety Co-
ordinator(s) as a group are so authorised is dealt with in CC.5.2. Only persons with such
authorisation will carry out the provisions of OC8A.
OC8A.4.2.3 Contact between Safety Co-ordinators will be made via normal operational channels, and
accordingly separate telephone numbers for Safety Co-ordinators need not be provided. At
the time of making contact, each party will confirm that they are authorised to act as a Safety
Co-ordinator, pursuant to OC8A.
OC8A.4.2.4 If work is to be carried out on a System, or on equipment of the Relevant E&W
Transmission Licensee or an E&W User near to a System, as provided in this OC8A,
which necessitates the provision of Safety Precautions on HV Apparatus in accordance
with the provisions of OC8A, the Requesting Safety Co-ordinator who requires the Safety
Precautions to be provided shall contact the relevant Implementing Safety Co-ordinator
to co-ordinate the establishment of the Safety Precautions.
OC8A.4.3 RISSP
OC8A.4.3.1 OC8A sets out the procedures for utilising the RISSP, which will be used except where
dealing with equipment in proximity to the others System as provided in OC8A.8. Sections
OC8A.4 to OC8A.7 inclusive should be read accordingly.
OC8A.4.3.2 The Relevant E&W Transmission Licensee will use the format of the RISSP forms set out
in Appendix A and Appendix B to OC8A. That set out in OC8A Appendix A and designated
as "RISSP-R", shall be used when the Relevant E&W Transmission Licensee is the
Requesting Safety Co-ordinator, and that in OC8A Appendix B and designated as
"RISSP-I", shall be used when the Relevant E&W Transmission Licensee is the
Implementing Safety Co-ordinator. Proformas of RISSP-R and RISSP-I will be provided
for use by the Relevant E&W Transmission Licensee staff.
OC8A.4.3.3 (a) E&W Users may either adopt the format referred to in OC8A.4.3.2, or use an equivalent
format, provided that it includes sections requiring insertion of the same information and
has the same numbering of sections as RISSP-R and RISSP-I as set out in Appendices
A and B respectively.
(b) Whether E&W Users adopt the format referred to in OC8A.4.3.2, or use the equivalent
format as above, the format may be produced and held in, and retrieved from an
electronic form by the E&W User.
(c) Whichever method E&W Users choose, each must provide proformas (whether in
tangible or electronic form) for use by its staff.
OC8A.4.3.4 All references to RISSP-R and RISSP-I shall be taken as referring to the corresponding parts
of the alternative forms or other tangible written or electronic records used by each E&W
User.
OC8A.4.3.5 RISSP-R will have an identifying number written or printed on it, comprising a prefix which
identifies the location at which it is issued, and a unique (for each E&W User or the
Relevant E&W Transmission Licensee, as the case may be) serial number which both
together uses up to eight characters (including letters and numbers) and the suffix "R".

Issue 5 Revision 8 OC8A 10 June 2014


5 of 24
OC8A.4.3.6 (a) In accordance with the timing requirements set out in CC.5.2 each E&W User shall
apply in writing to the Relevant E&W Transmission Licensee for the Relevant E&W
Transmission Licensees approval of its proposed prefix.
(b) The Relevant E&W Transmission Licensee shall consider the proposed prefix to see
if it is the same as (or confusingly similar to) a prefix used by the Relevant E&W
Transmission Licensee or another User and shall, as soon as possible (and in any
event within ten days), respond in writing to the E&W User with its approval or
disapproval.
(c) If the Relevant E&W Transmission Licensee disapproves, it shall explain in its
response why it has disapproved and will suggest an alternative prefix.
(d) If the Relevant E&W Transmission Licensee has disapproved, then the E&W User
shall either notify the Relevant E&W Transmission Licensee in writing of its
acceptance of the suggested alternative prefix or it shall apply in writing to the Relevant
E&W Transmission Licensee with revised proposals and the above procedure shall
apply to that application.
OC8A.4.3.7 The prefix allocation will be periodically circulated by NGET to all E&W Users, for
information purposes, using a National Grid Safety Circular in the form set out in OC8A
Appendix D.

OC8A.5 SAFETY PRECAUTIONS ON HV APPARATUS


OC8A.5.1 Agreement Of Safety Precautions
OC8A.5.1.1 The Requesting Safety Co-ordinator who requires Safety Precautions on another
System(s) will contact the relevant Implementing Safety Co-ordinator(s) to agree the
Location of the Safety Precautions to be established. This agreement will be recorded in
the respective Safety Logs.
OC8A.5.1.2 It is the responsibility of the Implementing Safety Co-ordinator to ensure that adequate
Safety Precautions are established and maintained, on his and/or another System
connected to his System, to enable Safety From The System to be achieved on the HV
Apparatus, specified by the Requesting Safety Co-ordinator which is to be identified in
Part 1.1 of the RISSP. Reference to another System in this OC8A.5.1.2 shall not include
the Requesting Safety Co-ordinators System which is dealt with in OC8A.5.1.3.
OC8A.5.1.3 When the Implementing Safety Co-ordinator is of the reasonable opinion that it is
necessary for Safety Precautions on the System of the Requesting Safety Co-ordinator,
other than on the HV Apparatus specified by the Requesting Safety Co-ordinator, which
is to be identified in Part 1.1 of the RISSP, he shall contact the Requesting Safety Co-
ordinator and the details shall be recorded in part 1.1 of the RISSP forms. In these
circumstances it is the responsibility of the Requesting Safety Co-ordinator to establish
and maintain such Safety Precautions.
OC8A.5.1.4 In The Event Of Disagreement
In any case where the Requesting Safety Co-ordinator and the Implementing Safety Co-
ordinator are unable to agree the Location of the Isolation and (if requested) Earthing,
both shall be at the closest available points on the infeeds to the HV Apparatus on which
Safety From The System is to be achieved as indicated on the Operation Diagram.
OC8A.5.2 Implementation Of Isolation
OC8A.5.2.1 Following the agreement of the Safety Precautions in accordance with OC8A.5.1 the
Implementing Safety Co-ordinator shall then establish the agreed Isolation.

Issue 5 Revision 8 OC8A 10 June 2014


6 of 24
OC8A.5.2.2 The Implementing Safety Co-ordinator shall confirm to the Requesting Safety Co-
ordinator that the agreed Isolation has been established, and identify the Requesting
Safety Co-ordinator's HV Apparatus up to the Connection Point (or, in the case of
OTSUA, Transmission Interface Point), for which the Isolation has been provided. The
confirmation shall specify:
(a) for each Location, the identity (by means of HV Apparatus name, nomenclature and
numbering or position, as applicable) of each point of Isolation;
(b) whether Isolation has been achieved by an Isolating Device in the isolating position,
by an adequate physical separation or as a result of a No System Connection;
(c) where an Isolating Device has been used whether the isolating position is either:
(i) maintained by immobilising and Locking the Isolating Device in the isolating
position and affixing a Caution Notice to it. Where the Isolating Device has been
Locked with a Safety Key, the confirmation shall specify that the Safety Key has
been secured in a Key Safe and the Key Safe Key has been given to the
authorised site representative of the Requesting Safety Co-ordinator where
reasonably practicable and is to be retained in safe custody. Where not
reasonably practicable (including where Earthing has been requested in
OC8A.5.1), the confirmation shall specify that the Key Safe Key will be retained by
the authorised site representative of the Implementing Safety Co-ordinator in
safe custody; or
(ii) maintained and/or secured by such other method which must be in accordance
with the Local Safety Instructions of the Relevant E&W Transmission Licensee
or that E&W User, as the case may be; and
(d) where an adequate physical separation has been used that it will be in accordance with,
and maintained by, the method set out in the Local Safety Instructions of the
Relevant E&W Transmission Licensee or that E&W User, as the case may be, and, if
it is a part of that method, that a Caution Notice has been placed at the point of
separation;
(e) where a No System Connection has been used the physical position of the No
System Connection shall be defined and shall not be varied for the duration of Safety
Precaution and the Implementing Safety Co-ordinators relevant HV Apparatus will
not, for the duration of the Safety Precaution be connected to a source of electrical
energy or to any other part of the Implementing Safety Co-ordinators System.
The confirmation of Isolation shall be recorded in the respective Safety Logs.
OC8A.5.2.3 Following the confirmation of Isolation being established by the Implementing Safety Co-
ordinator and the necessary establishment of relevant Isolation on the Requesting Safety
Co-ordinators System, the Requesting Safety Co-ordinator will then request the
implementation of Earthing by the Implementing Safety Co-ordinator, if agreed in section
OC8A.5.1. If the implementation of Earthing has been agreed, then the authorised site
representative of the Implementing Safety Co-ordinator shall retain any Key Safe Key in
safe custody until any Safety Key used for Earthing has been secured in the Key Safe.
OC8A.5.3 Implementation Of Earthing
OC8A.5.3.1 The Implementing Safety Co-ordinator shall then establish the agreed Earthing.
OC8A.5.3.2 The Implementing Safety Co-ordinator shall confirm to the Requesting Safety Co-
ordinator that the agreed Earthing has been established, and identify the Requesting
Safety Co-ordinators HV Apparatus up to the Connection Point (or, in the case of
OTSUA, Transmission Interface Point), for which the Earthing has been provided. The
confirmation shall specify:
(a) for each Location, the identity (by means of HV Apparatus name, nomenclature and
numbering or position, as is applicable) of each point of Earthing; and
(b) in respect of the Earthing Device used, whether it is:
(i) immobilised and Locked in the earthing position. Where the Earthing Device has
Issue 5 Revision 8 OC8A 10 June 2014
7 of 24
been Locked with a Safety Key, that the Safety Key has been secured in a Key
Safe and the Key Safe Key has been given to the authorised site representative of
the Requesting Safety Co-ordinator where reasonably practicable and is to be
retained in safe custody. Where not reasonably practicable, that the Key Safe Key
will be retained by the authorised site representative of the Implementing Safety
Co-ordinator in safe custody; or
(ii) maintained and/or secured in position by such other method which is in
accordance with the Local Safety Instructions of the Relevant E&W
Transmission Licensee or the Relevant Transmission Licensee or that E&W
User, as the case may be.
The confirmation of Earthing shall be recorded in the respective Safety Logs.
OC8A.5.3.3. The Implementing Safety Co-ordinator shall ensure that the established Safety
Precautions are maintained until requested to be removed by the relevant Requesting
Safety Co-ordinator.
OC8A.5.3.4 Certain designs of gas insulated switchgear three position isolator and earth switches
specifically provide a combined Isolation and Earthing function within a single mechanism
contained within a single integral unit. Where Safety Precautions are required across
control boundaries and subject to the requirements of OC8A.5.1, it is permissible to earth
before Points of Isolation have been established provided that all interconnected circuits
are fully disconnected from live HV Apparatus.

OC8A.5.4 RISSP Issue Procedure


OC8A.5.4.1 Where Safety Precautions on another System(s) are being provided to enable work on the
Requesting Safety Co-ordinators System, before any work commences they must be
recorded by a RISSP being issued. The RISSP is applicable to HV Apparatus up to the
Connection Point (or, in the case of OTSUA, Transmission Interface Point) identified in
section 1.1 of the RISSP-R and RISSP-I forms.
OC8A.5.4.2 Where Safety Precautions are being provided to enable work to be carried out on both
sides of the Connection Point (or, in the case of OTSUA, Transmission Interface Point) a
RISSP will need to be issued for each side of the Connection Point (or, in the case of
OTSUA, Transmission Interface Point) with the Relevant E&W Transmission Licensee
and the respective User each enacting the role of Requesting Safety Co-ordinator. This
will result in a RISSP-R and a RISSP-I form being completed by each of the Relevant E&W
Transmission Licensee and the E&W User, with each Requesting Safety Co-ordinator
issuing a separate RISSP number.
OC8A.5.4.3 Once the Safety Precautions have been established (in accordance with OC8A.5.2 and
OC8A.5.3), the Implementing Safety Co-ordinator shall complete parts 1.1 and 1.2 of a
RISSP-I form recording the details specified in OC8A.5.1.3, OC8A.5.2.2 and OC8A.5.3.2.
Where Earthing has not been requested, Part 1.2(b) will be completed with the words not
applicable or N/A. He shall then contact the Requesting Safety Co-ordinator to pass on
these details.
OC8A.5.4.4 The Requesting Safety Co-ordinator shall complete Parts 1.1 and 1.2 of the RISSP-R,
making a precise copy of the details received. On completion, the Requesting Safety Co-
ordinator shall read the entries made back to the sender and check that an accurate copy
has been made.
OC8A.5.4.5 The Requesting Safety Co-ordinator shall then issue the number of the RISSP, taken from
the RISSP-R, to the Implementing Safety Co-ordinator who will ensure that the number,
including the prefix and suffix, is accurately recorded in the designated space on the RISSP-I
form.
OC8A.5.4.6 The Requesting Safety Co-ordinator and the Implementing Safety Co-ordinator shall
complete and sign Part 1.3 of the RISSP-R and RISSP-I respectively and then enter the time
and date. When signed no alteration to the RISSP is permitted; the RISSP may only be
cancelled.

Issue 5 Revision 8 OC8A 10 June 2014


8 of 24
OC8A.5.4.7 The Requesting Safety Co-ordinator is then free to authorise work (including a test that
does not affect the Implementing Safety Co-ordinator's System) in accordance with the
requirements of the relevant internal safety procedures which apply to the Requesting
Safety Co-ordinators System. This is likely to involve the issue of safety documents or
other relevant internal authorisations. Where testing is to be carried out which affects the
Implementing Safety Co-ordinator's System, the procedure set out below in OC8A.6 shall
be implemented.

Issue 5 Revision 8 OC8A 10 June 2014


9 of 24
OC8A.5.5 RISSP Cancellation Procedure
OC8A.5.5.1 When the Requesting Safety Co-ordinator decides that Safety Precautions are no longer
required, he will contact the relevant Implementing Safety Co-ordinator to effect
cancellation of the associated RISSP.
OC8A.5.5.2 The Requesting Safety Co-ordinator will inform the relevant Implementing Safety Co-
ordinator of the RISSP identifying number (including the prefix and suffix), and agree it is
the RISSP to be cancelled.
OC8A.5.5.3 The Requesting Safety Co-ordinator and the relevant Implementing Safety Co-ordinator
shall then respectively complete Part 2.1 of their respective RISSP-R and RISSP-I forms and
shall then exchange details. The details being exchanged shall include their respective
names and time and date. On completion of the exchange of details the respective RISSP is
cancelled. The removal of Safety Precautions is as set out in OC8A.5.5.4 and OC8A.5.5.5.
OC8A.5.5.4 Neither Safety Co-ordinator shall instruct the removal of any Isolation forming part of the
Safety Precautions as part of the returning of the HV Apparatus to service until it is
confirmed to each by each other that every earth on each side of the Connection Point (or,
in the case of OTSUA, Transmission Interface Point), within the points of isolation
identified on the RISSP, has been removed or disconnected by the provision of additional
Points of Isolation.
OC8A.5.5.5 Subject to the provisions in OC8A.5.5.4, the Implementing Safety Co-ordinator is then free
to arrange the removal of the Safety Precautions, the procedure to achieve that being
entirely an internal matter for the party the Implementing Safety Co-ordinator is
representing. Where a Key Safe Key has been given to the authorised site representative of
the Requesting Safety Co-ordinator, the Key Safe Key must be returned to the authorised
site representative of the Implementing Safety Co-ordinator. The only situation in which
any Safety Precautions may be removed without first cancelling the RISSP in accordance
with OC8A.5.5 or OC8A.5.6 is when Earthing is removed in the situation envisaged in
OC8A.6.2(b).
OC8A.5.6 RISSP Change Control
Nothing in this OC8A prevents the Relevant E&W Transmission Licensee and E&W
Users agreeing to a simultaneous cancellation and issue of a new RISSP, if both agree. It
should be noted, however, that the effect of that under the relevant Safety Rules is not a
matter with which the Grid Code deals.

OC8A.6 TESTING AFFECTING ANOTHER SAFETY CO-ORDINATOR'S SYSTEM


OC8A.6.1 The carrying out of the test may affect Safety Precautions on RISSPs or work being carried
out which does not require a RISSP. Testing can, for example, include the application of an
independent test voltage. Accordingly, where the Requesting Safety Co-ordinator wishes
to authorise the carrying out of such a test to which the procedures in OC8A.6 apply he may
not do so and the test will not take place unless and until the steps in (a)-(c) below have
been followed and confirmation of completion has been recorded in the respective Safety
Logs:
(a) confirmation must be obtained from the Implementing Safety Co-ordinator that:
(i) no person is working on, or testing, or has been authorised to work on, or test, any
part of its System or another System(s) (other than the System of the
Requesting Safety Co-ordinator) within the points of Isolation identified on the
RISSP form relating to the test which is proposed to be undertaken, and
(ii) no person will be so authorised until the proposed test has been completed (or
cancelled) and the Requesting Safety Co-ordinator has notified the
Implementing Safety Co-ordinator of its completion (or cancellation);
(b) any other current RISSPs which relate to the parts of the System in which the testing is
to take place must have been cancelled in accordance with procedures set out in
OC8A.5.5;
Issue 5 Revision 8 OC8A 10 June 2014
10 of 24
(c) the Implementing Safety Co-ordinator must agree with the Requesting Safety Co-
ordinator to permit the testing on that part of the System between the points of
Isolation identified in the RISSP associated with the test and the points of Isolation on
the Requesting Safety Co-ordinator's System.
OC8A.6.2 (a) The Requesting Safety Co-ordinator will inform the Implementing Safety Co-
ordinator as soon as the test has been completed or cancelled and the confirmation
shall be recorded in the respective Safety Logs.
(b) When the test gives rise to the removal of Earthing which it is not intended to re-apply,
the relevant RISSP associated with the test shall be cancelled at the completion or
cancellation of the test in accordance with the procedure set out in either OC8A.5.5 or
OC8A.5.6. Where the Earthing is re-applied following the completion or cancellation of
the test, there is no requirement to cancel the relevant RISSP associated with the test
pursuant to this OC8A.6.2.
OC8A.7 EMERGENCY SITUATIONS
OC8A.7.1 There may be circumstances where Safety Precautions need to be established in relation
to an unintended electrical connection or situations where there is an unintended risk of
electrical connection between the National Electricity Transmission System and an E&W
Users System, for example resulting from an incident where one line becomes attached or
unacceptably close to another.
OC8A.7.2 In those circumstances, if both the Relevant E&W Transmission Licensee and the
respective E&W User agree, the relevant provisions of OC8A.5 will apply as if the electrical
connections or potential connections were, solely for the purposes of this OC8A, a
Connection Point (or, in the case of OTSUA, Transmission Interface Point).
OC8A.7.3 (a) The relevant Safety Co-ordinator shall be that for the electrically closest existing
Connection Point (or, in the case of OTSUA, Transmission Interface Point) to that
E&W User's System or such other local Connection Point (or, in the case of OTSUA,
Transmission Interface Point) as may be agreed between the Relevant E&W
Transmission Licensee and the E&W User, with discussions taking place between the
relevant local Safety Co-ordinators. The Connection Point (or, in the case of OTSUA,
Transmission Interface Point) to be used shall be known in this OC8A.7.3 as the
"relevant Connection Point" (or, in the case of OTSUA, relevant Transmission
Interface Point).
(b) The Local Safety Instructions shall be those which apply to the relevant Connection
Point (or, in the case of OTSUA, Transmission Interface Point).
(c) The prefix for the RISSP will be that which applies for the relevant Connection Point
(or, in the case of OTSUA, Transmission Interface Point).

Issue 5 Revision 8 OC8A 10 June 2014


11 of 24
OC8A.8 SAFETY PRECAUTIONS RELATING TO WORKING ON EQUIPMENT NEAR TO THE HV
SYSTEM
OC8A.8 applies to the situation where work is to be carried out at an E&W Users Site or a
Transmission Site (as the case may be) on equipment of the User or the Relevant E&W
Transmission Licensee as the case may be, where the work or equipment is near to HV
Apparatus on the Implementing Safety Co-ordinators System. It does not apply to other
situations to which OC8A applies. In this part of OC8A, a Permit for Work for proximity
work is to be used, rather then the usual RISSP procedure, given the nature and effect of
the work, all as further provided in the OC8A.8.
OC8A.8.1 Agreement Of Safety Precautions
OC8A.8.1.1 The Requesting Safety Co-ordinator who requires Safety Precautions on another
System(s) when work is to be carried out at an E&W Users Site or a Transmission Site
(as the case may be) on equipment of the User or the Relevant E&W Transmission
Licensee, as the case may be, where the work or equipment is near to HV Apparatus on
the Implementing Safety Co-ordinators System will contact the relevant Implementing
Safety Co-ordinator(s) to agree the Location of the Safety Precautions to be established,
having as part of this process informed the Implementing Safety Co-ordinator of the
equipment and the work to be undertaken. The respective Safety Co-ordinators will ensure
that they discuss the request with their authorised site representative and that the respective
authorised site representatives discuss the request at the Connection Site (or, in the case
of OTSUA, Transmission Interface Site). This agreement will be recorded in the
respective Safety Logs.
OC8A.8.1.2 It is the responsibility of the Implementing Safety Co-ordinator, working with his authorised
site representative as appropriate, to ensure that adequate Safety Precautions are
established and maintained, on his and/or another System connected to his System, to
enable Safety From The System to be achieved for work to be carried out at an E&W
Users Site or a Transmission Site (as the case may be) on equipment and in relation to
work which is to be identified in the relevant part of the Permit for Work for proximity work
where the work or equipment is near to HV Apparatus of the Implementing Safety Co-
ordinators System specified by the Requesting Safety Co-ordinator. Reference to
another System in this OC8A.8.1.2 shall not include the Requesting Safety Co-ordinators
System.
OC8A.8.1.3 In The Event Of Disagreement
In any case where the Requesting Safety Co-ordinator and the Implementing Safety Co-
ordinator are unable to agree the Location of the Isolation and (if requested) Earthing,
both shall be at the closest available points on the infeeds to the HV Apparatus near to
which the work is to be carried out as indicated on the Operation Diagram.
OC8A.8.2 Implementation Of Isolation And Earthing
OC8A.8.2.1 Following the agreement of the Safety Precautions in accordance with OC8A.8.1 the
Implementing Safety Co-ordinator shall then establish the agreed Isolation and (if
required) Earthing.
OC8A.8.2.2 The Implementing Safety Co-ordinator shall confirm to the Requesting Safety Co-
ordinator that the agreed Isolation and (if required) Earthing has been established.
OC8A.8.2.3 The Implementing Safety Co-ordinator shall ensure that the established Safety
Precautions are maintained until requested to be removed by the relevant Requesting
Safety Co-ordinator.

Issue 5 Revision 8 OC8A 10 June 2014


12 of 24
OC8A.8.3 Permit For Work For Proximity Work Issue Procedure
OC8A.8.3.1 Where Safety Precautions on another System(s) are being provided to enable work to be
carried out at an E&W Users Site or Transmission Site (as the case may be) on
equipment where the work or equipment is in proximity to HV Apparatus of the
Implementing Safety Co-ordinator, before any work commences they must be recorded by
a Permit for Work for proximity work being issued. The Permit for Work for proximity
work shall identify the Implementing Safety Co-ordinators HV Apparatus in proximity to
the required work.
OC8A.8.3.2 Once the Safety Precautions have been established (in accordance with OC8A.8.2), the
Implementing Safety Co-ordinator shall agree to the issue of the Permit for Work for
proximity work with the appropriately authorised site representative of the Requesting
Safety Co-ordinators Site. The Implementing Safety Co-ordinator will inform the
Requesting Safety Co-ordinator of the Permit for Work for proximity work identifying
number.
OC8A.8.3.3 The appropriately authorised site representative of the Implementing Safety Co-ordinator
shall then issue the Permit for Work for proximity work to the appropriately authorised site
representative of the Requesting Safety Co-ordinator. The Permit for Work for proximity
work will in the section dealing with the work to be carried out, be completed to identify that
the work is near the Implementing Safety Co-ordinators HV Apparatus. No further
details of the Requesting Safety Co-ordinators work will be recorded, as that is a matter
for the Requesting Safety Co-ordinator in relation to his work.
OC8A.8.3.4 The Requesting Safety Co-ordinator is then free to authorise work in accordance with the
requirements of the relevant internal safety procedures which apply to the Requesting
Safety Co-ordinators Site. This is likely to involve the issue of safety documents or other
relevant internal authorisations.
OC8A.8.4 Permit For Work For Proximity Work Cancellation Procedure
OC8A.8.4.1 When the Requesting Safety Co-ordinator decides that Safety Precautions are no longer
required, he will contact the relevant Implementing Safety Co-ordinator to effect
cancellation of the associated Permit for Work for proximity work.
OC8A.8.4.2 The Requesting Safety Co-ordinator will inform the relevant Implementing Safety Co-
ordinator of the Permit for Work for proximity work identifying number, and agree that the
Permit for Work for proximity work can be cancelled. The cancellation is then effected by
the appropriately authorised site representative of the Requesting Safety Co-ordinator
returning the Permit for Work for proximity work to the appropriately authorised site
representative of the Implementing Safety Co-ordinator.
OC8A.8.4.3 The Implementing Safety Co-ordinator is then free to arrange the removal of the Safety
Precautions, the procedure to achieve that being entirely an internal matter for the party the
Implementing Safety Co-ordinator is representing.
OC8A.9 LOSS OF INTEGRITY OF SAFETY PRECAUTIONS
OC8A.9.1 In any instance when any Safety Precautions may be ineffective for any reason the relevant
Safety Co-ordinator shall inform the other Safety Co-ordinator(s) without delay of that
being the case and, if requested, of the reasons why.
OC8A.10 SAFETY LOG
OC8A.10.1 The Relevant E&W Transmission Licensee and E&W Users shall maintain Safety Logs
which shall be a chronological record of all messages relating to safety co-ordination under
OC8A sent and received by the Safety Co-ordinator(s). The Safety Logs must be retained
for a period of not less than one year.

Issue 5 Revision 8 OC8A 10 June 2014


13 of 24
APPENDIX A - RISSP-R
[the Relevant E&W Transmission Licensee] [__________________ CONTROL CENTRE/SITE]

RECORD OF INTER-SYSTEM SAFETY PRECAUTIONS (RISSP-R)


(Requesting Safety Co-ordinator's Record)

RISSP NUMBER
PART 1

1.1 HV APPARATUS IDENTIFICATION

Safety Precautions have been established by the Implementing Safety Co-ordinator (or by another User on that User's
System connected to the Implementing Safety Co-ordinator's System) to achieve (in so far as it is possible from that side of
the Connection Point/Transmission Interface Point) Safety From The System on the following HV Apparatus on the
Requesting Safety Co-ordinator's System: [State identity - name(s) and, where applicable, identification of the HV circuit(s)
up to the Connection Point/Transmission Interface Point]:

______________________________________________________________________________________________

______________________________________________________________________________________________
Further Safety precautions required on the Requesting Safety Co-ordinators System as notified by the Implementing
Safety Co-ordinator.

______________________________________________________________________________________________

1.2 SAFETY PRECAUTIONS ESTABLISHED

(a) ISOLATION

[State the Location(s) at which Isolation has been established (whether on the Implementing Safety Co-ordinator's System
or on the System of another User connected to the Implementing Safety Co-ordinator's System). For each Location,
identify each point of Isolation. For each point of Isolation, state the means by which the Isolation has been achieved, and
whether, immobilised and Locked, Caution Notice affixed, other safety procedures applied, as appropriate.]

______________________________________________________________________________________________

______________________________________________________________________________________________

______________________________________________________________________________________________

(b) EARTHING

[State the Location(s) at which Earthing has been established (whether on the Implementing Safety Co-ordinator's System
or on the System of another User connected to the Implementing Safety Co-ordinator's System). For each Location,
identify each point of Earthing. For each point of Earthing, state the means by which Earthing has been achieved, and
whether, immobilised and Locked, other safety procedures applied, as appropriate].

______________________________________________________________________________________________

______________________________________________________________________________________________

______________________________________________________________________________________________

1.3 ISSUE

I have received confirmation from _________________________________________ (name of Implementing Safety Co-


ordinator) at _________________________________________ (location) that the Safety Precautions identified in paragraph
1.2 have been established and that instructions will not be issued at his location for their removal until this RISSP is cancelled.

Signed ................................................................(Requesting Safety Co-ordinator)

at .......................................(time) on .................................................. (Date)

Issue 5 Revision 8 OC8A 10 June 2014


14 of 24
PART 2

2.1 CANCELLATION

l have confirmed to _________________________________________ (name of the Implementing Safety Co-ordinator) at


________________________________________ (location) that the Safety Precautions set out in paragraph 1.2 are no longer
required and accordingly the RISSP is cancelled.

Signed ................................................................(Requesting Safety Co-ordinator)

at ........................................(time) on ................................................. (Date)

Issue 5 Revision 8 OC8A 10 June 2014


15 of 24
APPENDIX B - RISSP-I
[the Relevant E&W Transmission Licensee] [_________________ CONTROL CENTRE/SITE]

RECORD OF INTER-SYSTEM SAFETY PRECAUTIONS (RISSP-I)


(Implementing Safety Co-ordinator's Record)

PART 1 RISSP NUMBER

1.1 HV APPARATUS IDENTIFICATION

Safety Precautions have been established by the Implementing Safety Co-ordinator (or by another User on that User's
System connected to the Implementing Safety Co-ordinator's System) to achieve (in so far as it is possible from that side of
the Connection Point/Transmission Interface Point) Safety From The System on the following HV Apparatus on the
Requesting Safety Co-ordinator's System: [State identity - name(s) and, where applicable, identification of the HV circuit(s)
up to the Connection Point/Transmission Interface Point]:
______________________________________________________________________________________________

______________________________________________________________________________________________

Recording of notification given to the Requesting Safety Co-ordinator concerning further Safety Precautions required on the
Requesting Safety Co-ordinators System.

1.2 SAFETY PRECAUTIONS ESTABLISHED

(a) ISOLATION

[State the Location(s) at which Isolation has been established (whether on the Implementing Safety Co-ordinator's System
or on the System of another User connected to the Implementing Safety Co-ordinator's System). For each Location,
identify each point of Isolation. For each point of Isolation, state the means by which the Isolation has been achieved, and
whether, immobilised and Locked, Caution Notice affixed, other safety procedures applied, as appropriate.]

______________________________________________________________________________________________

______________________________________________________________________________________________

______________________________________________________________________________________________

(b) EARTHING

[State the Location(s) at which Earthing has been established (whether on the Implementing Safety Co-ordinator's System
or on the System of another User connected to the Implementing Safety Co-ordinator's System). For each Location,
identify each point of Earthing. For each point of Earthing, state the means by which Earthing has been achieved, and
whether, immobilised and Locked, other safety procedures applied, as appropriate].

______________________________________________________________________________________________

______________________________________________________________________________________________

______________________________________________________________________________________________

1.3 ISSUE

I have confirmed to ________________________________________ (name of Requesting Safety Co-ordinator) at


__________________________________________ (location) that the Safety Precautions identified in paragraph 1.2 have
been established and that instructions will not be issued at my location for their removal until this RISSP is cancelled.

Signed ...............................................................(Implementing Safety Co-ordinator)

at ...............................................(time) on ...................................................... (Date)

Issue 5 Revision 8 OC8A 10 June 2014


16 of 24
PART 2

2.1 CANCELLATION

l have received confirmation from _________________________________________ (name of the Requesting Safety Co-
ordinator) at ________________________________________ (location) that the Safety Precautions set out in paragraph 1.2
are no longer required and accordingly the RISSP is cancelled.

Signed ................................................................(Implementing Safety Co-ordinator)

at ................................................(time) on ........................................................ (Date)

(Note: This form to be of a different colour from RISSP-R)

Issue 5 Revision 8 OC8A 10 June 2014


17 of 24
APPENDIX C - FLOWCHARTS

APPENDIX C1 - RISSP ISSUE PROCESS

Issue 5 Revision 8 OC8A 10 June 2014


18 of 24
APPENDIX C2 - TESTING PROCESS

Issue 5 Revision 8 OC8A 10 June 2014


19 of 24
APPENDIX C3 - RISSP CANCELLATION PROCESS

Issue 5 Revision 8 OC8A 10 June 2014


20 of 24
APPENDIX C4 - PROCESS FOR WORKING NEAR TO SYSTEM EQUIPMENT

Issue 5 Revision 8 OC8A 10 June 2014


21 of 24
APPENDIX D - NATIONAL GRID SAFETY CIRCULAR

NGSC Number:
National Grid Safety Circular ..........................

(NGSC)
Date:
RISSP prefixes - Issue x Issued By:

Example

Pursuant to the objectives of The Grid Code, Operating Code 8A1 - Safety Co-ordination, this circular will be
used in relation to all cross boundary safety management issues with the Relevant E&W Transmission
Licensee customers. Of particular note will be the agreed prefixes for the Record of Inter System Safety
Precautions (RISSP) documents.

Issue 5 Revision 8 OC8A 10 June 2014


22 of 24
APPENDIX E - FORM OF NGET PERMIT TO WORK

[Form of the Relevant E&W Transmission Licensee Permit for Work]


No.
PERMIT FOR WORK
1. Location..

Equipment Identification.

Work to be done

2. Precautions taken to achieve Safety from the System


Points of Isolation

Primary Earths

Actions taken to avoid Danger by draining, venting, purging and containment or dissipation of stored energy*

Further precautions to be taken during the course of the work to avoid System derived hazards*

3. Precautions that may be varied*


4. Preparation Key Safe number*


Control Person(s) (Safety) giving Consent

State whether this Permit for Work must be personally retained yes no

Signed Time Date


Senior Authorised Person

Issue 5 Revision 8 OC8A 10 June 2014


23 of 24
5. Issue & Receipt
Key Safe Number* Safety Keys (No. off)*

Earthing Schedule Number* Portable Drain earths (No. off)*

Recommendations for General Approved (ROMP)#/Card Safe#/


Safety Report Number* Procedure Number*

Circuit Identification Colours/ Flags (No. off)* Wristlets (No. off)*


Symbols*

Issued (Signed)

Senior Authorised Person

Received (Signed) Time Date

Competent Person

Name (Block letters) Company

# delete as appropriate *write N/A if not applicable February 1995

< END OF OPERATING CODE NO. 8 APPENDIX 1>

Issue 5 Revision 8 OC8A 10 June 2014


24 of 24
OPERATING CODE NO. 8 APPENDIX 2
(OC8B)

SAFETY CO-ORDINATION IN RESPECT OF THE SCOTTISH TRANSMISSION


SYSTEMS OR THE SYSTEMS OF SCOTTISH USERS

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC8B.1 INTRODUCTION ................................................................................................................................3
OC8B.2 OBJECTIVE ........................................................................................................................................6
OC8B.3 SCOPE ...............................................................................................................................................6
OC8B.4 PROCEDURE .....................................................................................................................................6
OC8B.4.1 Approval Of Safety Rules .........................................................................................................6
OC8B.4.2 Safety Co-ordinators ................................................................................................................7
OC8B.4.3 RISSP.......................................................................................................................................7
OC8B.5 SAFETY PRECAUTIONS ON HV APPARATUS................................................................................8
OC8B.5.1 Agreement Of Safety Precautions............................................................................................8
OC8B.5.2 Implementation Of Isolation .....................................................................................................9
OC8B.5.3 Implementation of Earthing ....................................................................................................10
OC8B.5.4 RISSP Issue Procedure .........................................................................................................10
OC8B.5.5 RISSP Cancellation Procedure ..............................................................................................11
OC8B.5.6 RISSP Change Control ..........................................................................................................13
OC8B.6 TESTING ..........................................................................................................................................13
OC8B.7 EMERGENCY SITUATIONS ............................................................................................................13
OC8B.8 SAFETY PRECAUTIONS RELATING TO WORKING ON EQUIPMENT NEAR TO THE HV
SYSTEM ...........................................................................................................................................................14
OC8B.8.1 Agreement Of Safety Precautions..........................................................................................14
OC8B.8.2 Implementation Of Isolation And Earthing..............................................................................15
OC8B.8.3 Permit For Work For Proximity Work Issue Procedure .........................................................15
OC8B.8.4 Permit For Work For Proximity Work.....................................................................................15
OC8B.9 LOSS OF INTEGRITY OF SAFETY PRECAUTIONS ......................................................................16
OC8B.10 SAFETY LOG .................................................................................................................................16
APPENDIX A - RISSP-R ..................................................................................................................................17
APPENDIX B - RISSP-I ....................................................................................................................................19
APPENDIX C- FLOWCHARTS ........................................................................................................................21
APPENDIX C1 - RISSP ISSUE PROCESS ..............................................................................................21
APPENDIX C2 - TESTING PROCESS.....................................................................................................22
APPENDIX C3 - RISSP CANCELLATION PROCESS .............................................................................23
APPENDIX C4 - PROCESS FOR WORKING NEAR TO SYSTEM EQUIPMENT...................................24

Issue 5 Revision 8 OC8B 10 June 2014


i
APPENDIX D - NOT USED ..............................................................................................................................25
APPENDIX E - FORM OF PERMIT TO WORK ...............................................................................................26

Issue 5 Revision 8 OC8B 10 June 2014


ii
OC8B.1 INTRODUCTION
OC8B.1.1 OC8B specifies the standard procedures to be used by NGET, the Relevant Scottish
Transmission Licensees and Scottish Users for the co-ordination, establishment and
maintenance of necessary Safety Precautions when work is to be carried out on or near the
Scottish Transmission System or the System of a Scottish User and when there is a
need for Safety Precautions on HV Apparatus on the other's System for this work to be
carried out safely. OC8B applies to Relevant Scottish Transmission Licensees and
Scottish Users. Where work is to be carried out on or near equipment on an E&W
Transmission System or the Systems of E&W Users, but such work requires Safety
Precautions to be established on a Scottish Transmission System or the Systems of
Scottish Users, OC8B should be followed by the Relevant Scottish Transmission
Licensee and Scottish Users to establish the required Safety Precautions.
OC8A specifies the procedures to be used by the Relevant E&W Transmission Licensee
and E&W Users.
NGET shall procure that Relevant Scottish Transmission Licensees shall comply with
OC8B where and to the extent that such section applies to them.
In this OC8B the term work includes testing, other than System Tests which are covered
by OC12.
OC8B.1.2 OC8B also covers the co-ordination, establishment and maintenance of necessary safety
precautions on the Implementing Safety Co-ordinators System when work is to be carried
out at a Scottish Users Site or a Transmission Site (as the case may be) on equipment of
the Scottish User or the Relevant Scottish Transmission Licensee as the case may be
where the work or equipment is near to HV Apparatus on the Implementing Safety Co-
ordinators System. In the case of OTSUA, a Scottish Users Site or Transmission Site
shall, for the purposes of this OC8B, include a site at which there is a Transmission
Interface Point until the OTSUA Transfer Time and the provisions of this OC8B and
references to OTSUA shall be construed and applied accordingly until the OTSUA Transfer
Time at which time arrangements in respect of the Transmission Interface Site will have
been put in place between the Relevant Scottish Transmission Licensee and the
Offshore Transmission Licensee.
OC8B.1.3 OC8B does not apply to the situation where Safety Precautions need to be agreed solely
between Scottish Users. OC8B does not apply to the situation where Safety Precautions
need to be agreed solely between Transmission Licensees.
OC8B.1.4 OC8B does not seek to impose a particular set of Safety Rules on Relevant Scottish
Transmission Licensees and Scottish Users. The Safety Rules to be adopted and used
by the Relevant Scottish Transmission Licensee and each Scottish User shall be those
chosen by each.
OC8B.1.5 Site Responsibility Schedules document the control responsibility for each item of Plant
and Apparatus for each site.
OC8B.1.6 (a) The Relevant Scottish Transmission Licensee may agree alternative site-specific
operational procedures with Scottish Users for the co-ordination, establishment and
maintenance of Safety Precautions instead of the Record of Inter-System Safety
Precautions (RISSP) procedure detailed in this OC8B. Such operational procedures
shall satisfy the requirements of paragraphs OC8B.1.7, OC8B.2.1, OC8B.4.1,
OC8B.4.2, OC8B.9, OC8B.10. These alternative site-specific operational procedures for
the co-ordination, establishment and maintenance of Safety Precautions will be
referenced in the relevant Site Responsibility Schedule.

Issue 5 Revision 8 OC8B 10 June 2014


3 of 28
(b) The Relevant Scottish Transmission Licensee may agree with Scottish Users site-
specific procedures for the application of Safety Precautions across the interface
between Relevant Scottish Transmission Licensee and Scottish User in addition to
and consistent with either the RISSP procedure or the alternative site-specific
operational procedures described in OC8B.1.6 (a). These site-specific procedures will
be referenced in the relevant Site Responsibility Schedule.
(c) The Relevant Scottish Transmission Licensee and the Scottish User shall comply
with the procedures agreed pursuant to OC8B.1.6 (a) and OC8B.1.6 (b).

Issue 5 Revision 8 OC8B 10 June 2014


4 of 28
OC8B.1.7 Defined Terms
OC8B.1.7.1 Scottish Users should bear in mind that in OC8 only, in order that OC8 reads more easily
with the terminology used in certain Safety Rules, the term "HV Apparatus" is defined more
restrictively and is used accordingly in OC8B. Scottish Users should, therefore, exercise
caution in relation to this term when reading and using OC8B.
OC8B.1.7.2 In OC8 only the following terms shall have the following meanings:
(1) "HV Apparatus" means High Voltage electrical circuits forming part of a System, on
which Safety From The System may be required or on which Safety Precautions may
be applied to allow work to be carried out on a System.
(2) "Isolation" means the disconnection of Apparatus from the remainder of the System in
which that Apparatus is situated by either of the following:
(a) an Isolating Device maintained in an isolating position. The isolating position must
either be:
(i) maintained by immobilising and Locking the Isolating Device in the isolating
position and affixing a Caution Notice to it. Where the Isolating Device is
Locked with a Safety Key, the Safety Key must be secured in a Key Safe
and the Key Safe Key must be given to the authorised site representative of
the Requesting Safety Co-ordinator where reasonably practicable and is to
be retained in safe custody. Where not reasonably practicable the Key Safe
Key must be retained by the authorised site representative of the
Implementing Safety Co-ordinator in safe custody; or
(ii) maintained and/or secured by such other method which must be in
accordance with the Safety Rules of the Relevant Scottish Transmission
Licensee or that Scottish User, as the case may be; or
(b) an adequate physical separation which must be in accordance with, and maintained
by, the method set out in the Safety Rules of the Relevant Scottish
Transmission Licensee or that Scottish User, as the case may be, and, if it is a
part of that method, a Caution Notice must be placed at the point of separation; or
(c) in the case where the relevant HV Apparatus of the Implementing Safety Co-
ordinator is being either constructed or modified, an adequate physical separation
as a result of a No System Connection.
(3) No System Connection means an adequate physical separation (which must be in
accordance with, and maintained by, the method set out in the Safety Rules of the
Implementing Safety Co-ordinator) of the Implementing Safety Co-ordinators HV
Apparatus from the rest of the Implementing Safety Co-ordinators System where
such HV Apparatus has no installed means of being connected to, and will not for the
duration of the Safety Precaution be connected to, a source of electrical energy or to
any other part of the Implementing Safety Co-ordinators System.
(4) "Earthing" means a way of providing a connection between conductors and earth by an
Earthing Device which is either:
(i) immobilised and Locked in the earthing position. Where the Earthing Device is
Locked with a Safety Key, the Safety Key must be secured in a Key Safe and the
Key Safe Key must be given to the authorised site representative of the
Requesting Safety Co-ordinator where reasonably practicable and is to be
retained in safe custody. Where not reasonably practicable the Key Safe Key must
be retained by the authorised site representative of the Implementing Safety Co-
ordinator in safe custody; or
(ii) maintained and/or secured in position by such other method which must be in
accordance with the Safety Rules of the Relevant Scottish Transmission
Licensee or that Scottish User as the case may be.
Issue 5 Revision 8 OC8B 10 June 2014
5 of 28
OC8B.1.7.3 For the purpose of the co-ordination of safety relating to HV Apparatus the term Safety
Precautions means Isolation and/or Earthing.

OC8B.2 OBJECTIVE
OC8B.2.1 The objective of OC8B is to achieve:-
(i) Safety From The System when work on or near a System necessitates the provision of
Safety Precautions on another System on HV Apparatus up to a Connection Point
(or, in the case of OTSUA, Transmission Interface Point); and
(ii) Safety From The System when work is to be carried out at a Scottish Users Site or a
Transmission Site (as the case may be) on equipment of the Scottish User or the
Relevant Scottish Transmission Licensee (as the case may be) where the work or
equipment is near to HV Apparatus on the Implementing Safety Co-ordinators
System.
OC8B.2.2 A flow chart, set out in OC8B Appendix C, illustrates the process utilised in OC8B to achieve
the objective set out in OC8B.2.1. In the case of a conflict between the flow chart and the
provisions of the written text of OC8B, the written text will prevail.

OC8B.3 SCOPE
OC8B.3.1 OC8B applies to NGET, Relevant Scottish Transmission Licensees and to Scottish
Users, which in OC8 means:-
(a) Generators (including where undertaking OTSDUW);
(b) Network Operators; and
(c) Non-Embedded Customers.
The procedures for the establishment of safety co-ordination by NGET in relation to External
Interconnections are set out in Interconnection Agreements with relevant persons for the
External Interconnections.

OC8B.4 PROCEDURE
OC8B.4.1 Approval Of Safety Rules
OC8B.4.1.1 (a) In accordance with the timing requirements of its Bilateral Agreement, each Scottish
User will supply to the Relevant Scottish Transmission Licensee a copy of its Safety
Rules relating to its side of the Connection Point at each Connection Site or in the
case of OTSUA a copy of its Local Safety Instructions relating to its side of the
Transmission Interface Point at each Transmission Interface Site.
(b) In accordance with the timing requirements of each Bilateral Agreement the Relevant
Scottish Transmission Licensee will supply to each Scottish User a copy of its
Safety Rules relating to the Transmission side of the Connection Point at each
Connection Site or in the case of OTSUA a copy of its Local Safety Instructions
relating to the Transmission side of the Transmission Interface Point at each
Transmission Interface Site.
(c) Prior to connection the Relevant Scottish Transmission Licensee and the Scottish
User must have approved each others relevant Safety Rules in relation to Isolation
and Earthing.

Issue 5 Revision 8 OC8B 10 June 2014


6 of 28
OC8B.4.1.2 Either party may require that the Isolation and/or Earthing provisions in the other partys
Safety Rules affecting the Connection Site (or, in the case of OTSUA, Transmission
Interface Site) should be made more stringent in order that approval of the other partys
Safety Rules can be given. Provided these requirements are not unreasonable, the other
party will make such changes as soon as reasonably practicable. These changes may need
to cover the application of Isolation and/or Earthing at a place remote from the Connection
Site (or, in the case of OTSUA, Transmission Interface Site), depending upon the System
layout. Approval may not be withheld because the party required to approve reasonably
believes the provisions relating to Isolation and/or Earthing are too stringent.
OC8B.4.1.3 If, following approval, a party wishes to change the provisions in its Safety Rules relating to
Isolation and/or Earthing, it must inform the other party. If the change is to make the
provisions more stringent, then the other party merely has to note the changes. If the change
is to make the provisions less stringent, then the other party needs to approve the new
provisions and the procedures referred to in OC8B.4.1.2 apply.
OC8B.4.2 Safety Co-ordinators
OC8B.4.2.1 For each Connection Point (or, in the case of OTSUA, Transmission Interface Point), the
Relevant Scottish Transmission Licensee and each Scottish User will have nominated to
be available, to a timescale agreed in the Bilateral Agreement, a person or persons (Safety
Co-ordinator(s)) to be responsible for the co-ordination of Safety Precautions when work
is to be carried out on a System which necessitates the provision of Safety Precautions on
HV Apparatus pursuant to OC8B. A Safety Co-ordinator may be responsible for the co-
ordination of safety on HV Apparatus at more than one Connection Point (or, in the case of
OTSUA, Transmission Interface Point).
OC8B.4.2.2 Each Safety Co-ordinator shall be authorised by the Relevant Scottish Transmission
Licensee or a Scottish User, as the case may be, as competent to carry out the functions
set out in OC8B to achieve Safety From The System. Confirmation from the Relevant
Scottish Transmission Licensee or a Scottish User, as the case may be, that its Safety
Co-ordinator(s) as a group are so authorised is dealt with, for Scottish Users, in CC.5.2
and for Relevant Scottish Transmission Licensees in the STC. Only persons with such
authorisation will carry out the provisions of OC8B. Each User shall, prior to being connected
to the National Electricity Transmission System, give notice in writing to the Relevant
Scottish Transmission Licensee of its Safety Co-ordinator(s) and will update the written
notice yearly and whenever there is a change to the identity of its Safety Co-ordinators or to
the Connection Points (or, in the case of OTSUA, Transmission Interface Points). The
Relevant Scottish Transmission Licensee will, at the time of a Scottish User being
connected to the National Electricity Transmission System give notice in writing to that
Scottish User of the identity of its Safety Co-ordinator(s) and will update the written notice
whenever there is a change to the Connection Points (or, in the case of OTSUA,
Transmission Interface Points) or Safety Co-ordinators.
OC8B.4.2.3 Contact between Safety Co-ordinators will be made via normal operational channels, and
accordingly separate telephone numbers for Safety Co-ordinators need not be provided.
OC8B.4.2.4 If work is to be carried out on a System, or on equipment of the Relevant Scottish
Transmission Licensee or a Scottish User near to a System, as provided in this OC8B,
which necessitates the provision of Safety Precautions on HV Apparatus in accordance
with the provisions of OC8B, the Requesting Safety Co-ordinator who requires the Safety
Precautions to be provided shall contact the relevant Implementing Safety Co-ordinator to
co-ordinate the establishment of the Safety Precautions.
OC8B.4.3 RISSP
OC8B.4.3.1 OC8B sets out the procedures for utilising the RISSP, which will be used except where
dealing with equipment in proximity to the others System as provided in OC8B.8. Sections
OC8B.4 to OC8B.7 inclusive should be read accordingly.

Issue 5 Revision 8 OC8B 10 June 2014


7 of 28
OC8B.4.3.2 The Relevant Transmission Licensee will use the format of the RISSP forms set out in
Appendix A and Appendix B to OC8B, or any other format which may be agreed between the
Relevant Scottish Transmission Licensee and each User. That set out in OC8B Appendix
A and designated as "RISSP-R", shall be used when the Relevant Scottish Transmission
Licensee is the Requesting Safety Co-ordinator, and that in OC8B Appendix B and
designated as "RISSP-I", shall be used when the Relevant Transmission Licensee is the
Implementing Safety Co-ordinator. Proformas of RISSP-R and RISSP-I will be provided for
use by Relevant Scottish Transmission Licensees staff.
OC8B.4.3.3 Scottish Users may either adopt the format referred to in OC8B.4.3.2 or any other format
which may be agreed between the Relevant Scottish Transmission Licensee and the
Scottish User from time to time.
OC8B.4.3.4 All references to RISSP-R and RISSP-I shall be taken as referring to the corresponding parts
of the alternative forms or other tangible written or electronic records used by each Scottish
User or Relevant Scottish Transmission Licensee.
OC8B.4.3.5 RISSP-R will have an identifying number written or printed on it, comprising a prefix which
identifies the location at which it is issued, and a unique (for each Scottish User or Relevant
Scottish Transmission Licensee, as the case may be) serial number which both together
uses up to eight characters (including letters and numbers) and the suffix "R".
OC8B.4.3.6 (a) In accordance with the timing requirements set out in the Bilateral Agreement each
Scottish User shall apply in writing to Relevant Scottish Transmission Licensee for
Relevant Scottish Transmission Licensees approval of its proposed prefix.
(b) Relevant Scottish Transmission Licensee shall consider the proposed prefix to see if
it is the same as (or confusingly similar to) a prefix used by Relevant Scottish
Transmission Licensee or another User and shall, as soon as possible (and in any
event within ten days), respond in writing to the Scottish User with its approval or
disapproval.
(c) If Relevant Scottish Transmission Licensee disapproves, it shall explain in its
response why it has disapproved and will suggest an alternative prefix.
(d) If Relevant Scottish Transmission Licensee has disapproved, then the Scottish User
shall either notify Relevant Scottish Transmission Licensee in writing of its
acceptance of the suggested alternative prefix or it shall apply in writing to Relevant
Scottish Transmission Licensee with revised proposals and the above procedure
shall apply to that application.

OC8B.5 SAFETY PRECAUTIONS ON HV APPARATUS


OC8B.5.1 Agreement Of Safety Precautions
OC8B.5.1.1 The Requesting Safety Co-ordinator who requires Safety Precautions on another
System(s) will contact the relevant Implementing Safety Co-ordinator(s) to agree the
Location of the Safety Precautions to be established. This agreement will be recorded in
the respective Safety Logs.
OC8B.5.1.2 It is the responsibility of the Implementing Safety Co-ordinator to ensure that adequate
Safety Precautions are established and maintained, on his and/or another System
connected to his System, to enable Safety From The System to be achieved on the HV
Apparatus, specified by the Requesting Safety Co-ordinator which is to be identified in
Part 1.1 of the RISSP. Reference to another System in this OC8B.5.1.2 shall not include the
Requesting Safety Co-ordinators System which is dealt with in OC8B.5.1.3.

Issue 5 Revision 8 OC8B 10 June 2014


8 of 28
OC8B.5.1.3 When the Implementing Safety Co-ordinator is of the reasonable opinion that it is
necessary for Safety Precautions on the System of the Requesting Safety Co-ordinator,
other than on the HV Apparatus specified by the Requesting Safety Co-ordinator, which is
to be identified in Part 1.1 of the RISSP, he shall contact the Requesting Safety Co-
ordinator and the details shall be recorded in part 1.1 of the RISSP forms. In these
circumstances it is the responsibility of the Requesting Safety Co-ordinator to establish
and maintain such Safety Precautions.
OC8B.5.1.4 The location of the Safety Precautions should be indicated on each Scottish Users
operational diagram and labelled as per the local instructions of each Scottish User.
OC8B.5.1.5 In The Event Of Disagreement
In any case where the Requesting Safety Co-ordinator and the Implementing Safety Co-
ordinator are unable to agree the Location of the Isolation and (if requested) Earthing,
both shall be at the closest available points on the infeeds to the HV Apparatus on which
Safety From The System is to be achieved as indicated on the Operation Diagram.
OC8B.5.2 Implementation Of Isolation
OC8B.5.2.1 Following the agreement of the Safety Precautions in accordance with OC8B.5.1 the
Implementing Safety Co-ordinator shall then establish the agreed Isolation.
OC8B.5.2.2 The Implementing Safety Co-ordinator shall confirm to the Requesting Safety Co-
ordinator that the agreed Isolation has been established, and identify the Requesting
Safety Co-ordinator's HV Apparatus up to the Connection Point (or, in the case of
OTSUA, Transmission Interface Point), for which the Isolation has been provided. The
confirmation shall specify:
(a) for each Location, the identity (by means of HV Apparatus name, nomenclature and
numbering or position, as applicable) of each point of Isolation;
(b) whether Isolation has been achieved by an Isolating Device in the isolating position, by
an adequate physical separation or as a result of a No System Connection;
(c) where an Isolating Device has been used whether the isolating position is either :
(i) maintained by immobilising and Locking the Isolating Device in the isolating
position and affixing a Caution Notice to it. Where the Isolating Device has been
Locked with a Safety Key, the confirmation shall specify that the Safety Key has
been secured in a Key Safe and the Key Safe Key has been given to the
authorised site representative of the Requesting Safety Co-ordinator where
reasonably practicable and is to be retained in safe custody. Where not reasonably
practicable (including where Earthing has been requested in OC8B.5.1), the
confirmation shall specify that the Key Safe Key will be retained by the authorised
site representative of the Implementing Safety Co-ordinator in safe custody; or
(ii) maintained and/or secured by such other method which must be in accordance with
the Safety Rules of the Relevant Scottish Transmission Licensee or that
Scottish User, as the case may be; and
(d) where an adequate physical separation has been used that it will be in accordance with,
and maintained by, the method set out in the Safety Rules of the Relevant Scottish
Transmission Licensee or that Scottish User, as the case may be, and, if it is a part of
that method, that a Caution Notice has been placed at the point of separation;
(e) where a No System Connection has been used the physical position of the No System
Connection shall be defined and shall not be varied for the duration of the Safety
Precaution and the Implementing Safety Co-ordinators relevant HV Apparatus will
not, for the duration of the Safety Precaution be connected to a source of electrical
energy or to any other part of the Implementing Safety Co-ordinators System.
The confirmation of Isolation shall be recorded in the respective Safety Logs.

Issue 5 Revision 8 OC8B 10 June 2014


9 of 28
OC8B.5.2.3 Following the confirmation of Isolation being established by the Implementing Safety Co-
ordinator and the necessary establishment of relevant Isolation on the Requesting Safety
Co-ordinators System, the Requesting Safety Co-ordinator will then request the
implementation of Earthing by the Implementing Safety Co-ordinator, if agreed in section
OC8B.5.1. If the implementation of Earthing has been agreed, then the authorised site
representative of the Implementing Safety Co-ordinator shall retain any Key Safe Key in
safe custody until any Safety Key used for Earthing has been secured in the Key Safe.
OC8B.5.3 Implementation Of Earthing
OC8B.5.3.1 The Implementing Safety Co-ordinator shall then establish the agreed Earthing.
OC8B.5.3.2 The Implementing Safety Co-ordinator shall confirm to the Requesting Safety Co-
ordinator that the agreed Earthing has been established, and identify the Requesting
Safety Co-ordinators HV Apparatus up to the Connection Point (or, in the case of
OTSUA, Transmission Interface Point), for which the Earthing has been provided. The
confirmation shall specify:
(a) for each Location, the identity (by means of HV Apparatus name, nomenclature and
numbering or position, as is applicable) of each point of Earthing; and
(b) in respect of the Earthing Device used, whether it is:
(i) immobilised and Locked in the earthing position. Where the Earthing Device has
been Locked with a Safety Key, that the Safety Key has been secured in a Key
Safe and the Key Safe Key has been given to the authorised site representative of
the Requesting Safety Co-ordinator where reasonably practicable and is to be
retained in safe custody. Where not reasonably practicable, that the Key Safe Key
will be retained by the authorised site representative of the Implementing Safety
Co-ordinator in safe custody; or
(ii) maintained and/or secured in position by such other method which is in accordance
with the Safety Rules of the Relevant Scottish Transmission Licensee or that
Scottish User, as the case may be.
The confirmation of Earthing shall be recorded in the respective Safety Logs.
OC8B.5.3.3 The Implementing Safety Co-ordinator shall ensure that the established Safety
Precautions are maintained until requested to be removed by the relevant Requesting
Safety Co-ordinator.
OC8B.5.3.4 Certain designs of gas insulated switchgear three position isolator and earth switches
specifically provide a combined Isolation and Earthing function within a single mechanism
contained within a single integral unit. Where Safety Precautions are required across
control boundaries and subject to the requirements of OC8B.5.1, it is permissible to earth
before Points of Isolation have been established provided that all interconnected circuits
are fully disconnected from live HV Apparatus.
OC8B.5.4 RISSP Issue Procedure
OC8B.5.4.1 Where Safety Precautions on another System(s) are being provided to enable work on the
Requesting Safety Co-ordinators System, before any work commences they must be
recorded by a RISSP being issued. The RISSP is applicable to HV Apparatus up to the
Connection Point (or, in the case of OTSUA, Transmission Interface Point) identified in
section 1.1 of the RISSP-R and RISSP-I forms.

Issue 5 Revision 8 OC8B 10 June 2014


10 of 28
OC8B.5.4.2 Where Safety Precautions are being provided to enable work to be carried out on both
sides of the Connection Point (or, in the case of OTSUA, Transmission Interface Point) a
RISSP will need to be issued for each side of the Connection Point (or, in the case of
OTSUA, Transmission Interface Point) with Relevant Scottish Transmission Licensee
and the respective User each enacting the role of Requesting Safety Co-ordinator. This
will result in a RISSP-R and a RISSP-I form being completed by each of the Relevant
Scottish Transmission Licensee and the Scottish User, with each Requesting Safety
Co-ordinator issuing a separate RISSP number.
OC8B.5.4.3 Once the Safety Precautions have been established (in accordance with OC8B.5.2 and
OC8B.5.3), the Implementing Safety Co-ordinator shall complete parts 1.1 and 1.2 of a
RISSP-I form recording the details specified in OC8B.5.1.3, OC8B.5.2.2 and OC8B.5.3.2.
Where Earthing has not been requested, Part 1.2(b) will be completed with the words not
applicable or N/A. He shall then contact the Requesting Safety Co-ordinator to pass on
these details.
OC8B.5.4.4 The Requesting Safety Co-ordinator shall complete Parts 1.1 and 1.2 of the RISSP-R,
making a precise copy of the details received. On completion, the Requesting Safety Co-
ordinator shall read the entries made back to the sender and check that an accurate copy
has been made.
OC8B.5.4.5 The Requesting Safety Co-ordinator shall then issue the number of the RISSP, taken from
the RISSP-R, to the Implementing Safety Co-ordinator who will ensure that the number,
including the prefix and suffix (where applicable), is accurately recorded in the designated
space on the RISSP-I form.
OC8B.5.4.6 The Requesting Safety Co-ordinator and the Implementing Safety Co-ordinator shall
complete and sign Part 1.3 of the RISSP-R and RISSP-I respectively and then enter the time
and date. When signed no alteration to the RISSP is permitted; the RISSP may only be
cancelled.
OC8B.5.4.7 The Requesting Safety Co-ordinator is then free to authorise work, but not testing, in
accordance with the requirements of the relevant internal safety procedures which apply to
the Requesting Safety Co-ordinators System. This is likely to involve the issue of safety
documents or other relevant internal authorisations. Where testing is to be carried out, the
procedure set out below in OC8B.6 shall be implemented.
OC8B.5.5 RISSP Cancellation Procedure
OC8B.5.5.1 When the Requesting Safety Co-ordinator decides that Safety Precautions are no longer
required, he will contact the relevant Implementing Safety Co-ordinator to effect
cancellation of the associated RISSP.
OC8B.5.5.2 The Requesting Safety Co-ordinator will inform the relevant Implementing Safety Co-
ordinator of the RISSP identifying number, including the prefix and suffix (where applicable),
and agree it is the RISSP to be cancelled.
OC8B.5.5.3 The Requesting Safety Co-ordinator and the relevant Implementing Safety Co-ordinator
shall then respectively complete Part 2.1 of their respective RISSP-R and RISSP-I forms and
shall then exchange details. The details being exchanged shall include their respective
names and time and date. On completion of the exchange of details the respective RISSP is
cancelled. The removal of Safety Precautions is as set out in OC8B.5.5.4 and OC8B.5.5.5.
OC8B.5.5.4 Neither Safety Co-ordinator shall instruct the removal of any Isolation forming part of the
Safety Precautions as part of the returning of the HV Apparatus to service until it is
confirmed to each by each other that every earth on each side of the Connection Point (or,
in the case of OTSUA, Transmission Interface Point), within the points of isolation
identified on the RISSP, has been removed or disconnected by the provision of additional
Points of Isolation.

Issue 5 Revision 8 OC8B 10 June 2014


11 of 28
OC8B.5.5.5 Subject to the provisions in OC8B.5.5.4, the Implementing Safety Co-ordinator is then free
to arrange the removal of the Safety Precautions, the procedure to achieve that being
entirely an internal matter for the party the Implementing Safety Co-ordinator is
representing. Where a Key Safe Key has been given to the authorised site representative of
the Requesting Safety Co-ordinator, the Key Safe Key must be returned to the authorised
site representative of the Implementing Safety Co-ordinator. The only situation in which
any Safety Precautions may be removed without first cancelling the RISSP in accordance
with OC8B.5.5 or OC8B.5.6 is when Earthing is removed in the situation envisaged in
OC8B.6.2(b).

Issue 5 Revision 8 OC8B 10 June 2014


12 of 28
OC8B.5.6 RISSP Change Control
Nothing in this OC8B prevents Relevant Scottish Transmission Licensee and Scottish
Users agreeing to a simultaneous cancellation and issue of a new RISSP, if both agree. It
should be noted, however, that the effect of that under the relevant Safety Rules is not a
matter with which the Grid Code deals.
OC8B.6 TESTING
OC8B.6.1 The carrying out of the test may affect Safety Precautions on RISSPs or work being carried
out which does not require a RISSP. Testing can, for example, include the application of an
independent test voltage. Accordingly, where the Requesting Safety Co-ordinator wishes to
authorise the carrying out of such a test to which the procedures in OC8B.6 apply he may not
do so and the test will not take place unless and until the steps in (a)-(c) below have been
followed and confirmation of completion has been recorded in the respective Safety Logs:
(a) confirmation must be obtained from the Implementing Safety Co-ordinator that:
(i) no person is working on, or testing, or has been authorised to work on, or test, any
part of its System or another System(s) (other than the System of the Requesting
Safety Co-ordinator) within the points of Isolation identified on the RISSP form
relating to the test which is proposed to be undertaken, and
(ii) no person will be so authorised until the proposed test has been completed (or
cancelled) and the Requesting Safety Co-ordinator has notified the
Implementing Safety Co-ordinator of its completion (or cancellation);
(b) any other current RISSPs which relate to the parts of the System in which the testing is
to take place must have been cancelled in accordance with procedures set out in
OC8B.5.5;
(c) the Implementing Safety Co-ordinator must agree with the Requesting Safety Co-
ordinator to permit the testing on that part of the System between the points of
Isolation identified in the RISSP associated with the test and the points of Isolation on
the Requesting Safety Co-ordinator's System.
OC8B.6.2 (a) The Requesting Safety Co-ordinator will inform the Implementing Safety Co-
ordinator as soon as the test has been completed or cancelled and the confirmation
shall be recorded in the respective Safety Logs.
(b) When the test gives rise to the removal of Earthing which it is not intended to re-apply,
the relevant RISSP associated with the test shall be cancelled at the completion or
cancellation of the test in accordance with the procedure set out in either OC8B.5.5 or
OC8B.5.6. Where the Earthing is re-applied following the completion or cancellation of
the test, there is no requirement to cancel the relevant RISSP associated with the test
pursuant to this OC8B.6.2.

OC8B.7 EMERGENCY SITUATIONS


OC8B.7.1 There may be circumstances where Safety Precautions need to be established in relation to
an unintended electrical connection or situations where there is an unintended risk of
electrical connection between the National Electricity Transmission System and a
Scottish Users System, for example resulting from an incident where one line becomes
attached or unacceptably close to another.
OC8B.7.2 In those circumstances, if both the Relevant Scottish Transmission Licensee the Scottish
User agree, the relevant provisions of OC8B.5 will apply as if the electrical connections or
potential connections were, solely for the purposes of this OC8B, a Connection Point (or, in
the case of OTSUA, Transmission Interface Point).

Issue 5 Revision 8 OC8B 10 June 2014


13 of 28
OC8B.7.3 (a) The relevant Safety Co-ordinator shall be that for the electrically closest existing
Connection Point (or, in the case of OTSUA, Transmission Interface Point) to that
Scottish User's System or such other local Connection Point (or, in the case of
OTSUA, Transmission Interface Point) as may be agreed between the Relevant
Scottish Transmission Licensee and the Scottish User, with discussions taking place
between the relevant local Safety Co-ordinators. The Connection Point (or, in the
case of OTSUA, Transmission Interface Point) to be used shall be known in this
OC8B.7.3 as the "relevant Connection Point" (or, in the case of OTSUA, relevant
Transmission Interface Point).
(b) The Safety Rules shall be those which apply to the relevant Connection Point (or, in
the case of OTSUA, Transmission Interface Point).
(c) The prefix for the RISSP (where applicable) will be that which applies for the relevant
Connection Point (or, in the case of OTSUA, Transmission Interface Point).
OC8B.8 SAFETY PRECAUTIONS RELATING TO WORKING ON EQUIPMENT NEAR TO THE HV
SYSTEM
OC8B.8 applies to the situation where work is to be carried out at a Scottish Users Site or a
Transmission Site (as the case may be) on equipment of the Scottish User or a Relevant
Scottish Transmission Licensee as the case may be, where the work or equipment is near
to HV Apparatus on the Implementing Safety Co-ordinators System. It does not apply to
other situations to which OC8B applies. In this part of OC8B, a Permit for Work for
proximity work is to be used, rather then the usual RISSP procedure, given the nature and
effect of the work, all as further provided in the OC8B.8.
OC8B.8.1 Agreement Of Safety Precautions
OC8B.8.1.1 The Requesting Safety Co-ordinator who requires Safety Precautions on another
System(s) when work is to be carried out at a Scottish Users Site or a Transmission Site
(as the case may be) on equipment of the Scottish User or a Relevant Scottish
Transmission Licensee, as the case may be, where the work or equipment is near to HV
Apparatus on the Implementing Safety Co-ordinators System will contact the relevant
Implementing Safety Co-ordinator(s) to agree the Location of the Safety Precautions to
be established, having as part of this process informed the Implementing Safety Co-
ordinator of the equipment and the work to be undertaken. The respective Safety Co-
ordinators will ensure that they discuss the request with their authorised site representative
and that the respective authorised site representatives discuss the request at the
Connection Site (or, in the case of OTSUA, Transmission Interface Site). This agreement
will be recorded in the respective Safety Logs.
OC8B.8.1.2 It is the responsibility of the Implementing Safety Co-ordinator, working with his authorised
site representative as appropriate, to ensure that adequate Safety Precautions are
established and maintained, on his and/or another System connected to his System, to
enable Safety From The System to be achieved for work to be carried out at a Scottish
Users Site or a Transmission Site (as the case may be) on equipment and in relation to
work which is to be identified in the relevant part of the Permit for Work for proximity work
where the work or equipment is near to HV Apparatus of the Implementing Safety Co-
ordinators System specified by the Requesting Safety Co-ordinator. Reference to
another System in this OC8B.8.1.2 shall not include the Requesting Safety Co-ordinators
System.
OC8B.8.1.3 In The Event Of Disagreement
In any case where the Requesting Safety Co-ordinator and the Implementing Safety Co-
ordinator are unable to agree the Location of the Isolation and (if requested) Earthing,
both shall be at the closest available points on the infeeds to the HV Apparatus near to
which the work is to be carried out as indicated on the Operation Diagram.

Issue 5 Revision 8 OC8B 10 June 2014


14 of 28
OC8B.8.2 Implementation Of Isolation And Earthing
OC8B.8.2.1 Following the agreement of the Safety Precautions in accordance with OC8B.8.1 the
Implementing Safety Co-ordinator shall then establish the agreed Isolation and (if
required) Earthing.
OC8B.8.2.2 The Implementing Safety Co-ordinator shall confirm to the Requesting Safety Co-
ordinator that the agreed Isolation and (if required) Earthing has been established.
OC8B.8.2.3 The Implementing Safety Co-ordinator shall ensure that the established Safety
Precautions are maintained until requested to be removed by the relevant Requesting
Safety Co-ordinator.
OC8B.8.3 Permit For Work For Proximity Work Issue Procedure
OC8B.8.3.1 Where Safety Precautions on another System(s) are being provided to enable work to be
carried out at a Scottish Users Site or Transmission Site (as the case may be) on
equipment where the work or equipment is in proximity to HV Apparatus of the
Implementing Safety Co-ordinator, before any work commences they must be recorded by
a Permit for Work for proximity work being issued. The Permit for Work for proximity
work shall identify the Implementing Safety Co-ordinators HV Apparatus in proximity to
the required work
OC8B.8.3.2 Once the Safety Precautions have been established (in accordance with OC8B.8.2), the
Implementing Safety Co-ordinator shall agree to the issue of the Permit for Work for
proximity work with the appropriately authorised site representative of the Requesting
Safety Co-ordinators Site. The Implementing Safety Co-ordinator will inform the
Requesting Safety Co-ordinator of the Permit for Work for proximity work identifying
number.
OC8B.8.3.3 The appropriately authorised site representative of the Implementing Safety Co-ordinator
shall then issue the Permit for Work for proximity work to the appropriately authorised site
representative of the Requesting Safety Co-ordinator. The Permit for Work for proximity
work will in the section dealing with the work to be carried out, be completed to identify that
the work is near the Implementing Safety Co-ordinators HV Apparatus. No further
details of the Requesting Safety Co-ordinators work will be recorded, as that is a matter
for the Requesting Safety Co-ordinator in relation to his work.
OC8B.8.3.4 The Requesting Safety Co-ordinator is then free to authorise work in accordance with the
requirements of the relevant internal safety procedures which apply to the Requesting
Safety Co-ordinators Site. This is likely to involve the issue of safety documents or other
relevant internal authorisations.
OC8B.8.4 Permit For Work For Proximity Work Cancellation Procedure
OC8B.8.4.1 When the Requesting Safety Co-ordinator decides that Safety Precautions are no longer
required, he will contact the relevant Implementing Safety Co-ordinator to effect
cancellation of the associated Permit for Work for proximity work.
OC8B.8.4.2 The Requesting Safety Co-ordinator will inform the relevant Implementing Safety Co-
ordinator of the Permit for Work for proximity work identifying number, and agree that the
Permit for Work for proximity work can be cancelled. The cancellation is then effected by
the appropriately authorised site representative of the Requesting Safety Co-ordinator
returning the Permit for Work for proximity work to the appropriately authorised site
representative of the Implementing Safety Co-ordinator.
OC8B.8.4.3 The Implementing Safety Co-ordinator is then free to arrange the removal of the Safety
Precautions, the procedure to achieve that being entirely an internal matter for the party the
Implementing Safety Co-ordinator is representing.

Issue 5 Revision 8 OC8B 10 June 2014


15 of 28
OC8B.9 LOSS OF INTEGRITY OF SAFETY PRECAUTIONS
OC8B.9.1 In any instance when any Safety Precautions may be ineffective for any reason the relevant
Safety Co-ordinator shall inform the other Safety Co-ordinator(s) without delay of that
being the case and, if requested, of the reasons why.

OC8B.10 SAFETY LOG


OC8B.10.1 Relevant Scottish Transmission Licensees and Scottish Users shall maintain Safety
Logs which shall be a chronological record of all messages relating to safety co-ordination
under OC8 sent and received by the Safety Co-ordinator(s). The Safety Logs must be
retained for a period of not less than six years.

Issue 5 Revision 8 OC8B 10 June 2014


16 of 28
APPENDIX A - RISSP-R
RECORD OF INTER-SYSTEM SAFETY PRECAUTIONS (RISSP-R)
(Requesting Safety Co-ordinator's Record)

RISSP NUMBER __________

Part 1

1.1 CIRCUIT IDENTIFICATION

Safety Precautions have been established by the Implementing Safety Co-ordinator to


achieve Safety From The System on the following HV Apparatus:

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

1.2 SAFETY PRECAUTIONS ESTABLISHED

(a) ISOLATION

State the Locations(s) at which Isolation has been established on the Implementing
Safety Co-ordinator's System. For each Location, identify each point of Isolation. For
each point of Isolation state, the means by which the Isolation has been achieved, and
whether, immobilised and Locked, Caution Notice affixed, other Safety Precautions
applied, as appropriate.

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

Issue 5 Revision 8 OC8B 10 June 2014


17 of 28
(b) EARTHING

State the Locations(s) at which Earthing has been established on the Implementing
Safety Co-ordinator's System. For each Location, identify each point of Earthing. For
each point of Earthing state, the means by which the Earthing has been achieved, and
whether, immobilised and Locked, other Safety Precautions applied, as appropriate.

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

1.3 ISSUE

I have received confirmation from ____________________ (name of Implementing


Safety Co-ordinator) at ____________________ (Location) that the Safety
Precautions identified in paragraph 1.2 have been established and that instructions will
not be issued at his Location for their removal until this RISSP is cancelled.

Signed ................................................ (Requesting Safety Co-ordinator)

at ............................. (time) on ....................................... (date)

PART 2

2.1 CANCELLATION

I have confirmed to ____________________ (name of the Implementing Safety


Co-ordinator) at ____________________ (Location) that the Safety Precautions set
out in paragraph 1.2 are no longer required and accordingly the RISSP is cancelled.

Signed ................................................... (Requesting Safety Co-ordinator)

at ............................. (time) on .............................. (date).......................................

Issue 5 Revision 8 OC8B 10 June 2014


18 of 28
APPENDIX B - RISSP-I
RECORD OF INTER-SYSTEM SAFETY PRECAUTIONS (RISSP-I)
(Implementing Safety Co-ordinator's Record)

RISSP NUMBER __________

PART 1

1.1 CIRCUIT IDENTIFICATION

Safety Precautions have been established by the Implementing Safety Co-ordinator to


achieve Safety From The System on the following HV Apparatus:

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

1.2 SAFETY PRECAUTIONS ESTABLISHED

(a) ISOLATION

State the Location(s) at which isolation has been established on the Implementing
Safety Co-ordinator's System. For each Location, identify each point of Isolation. For
each point of Isolation state, the means by which the Isolation has been achieved, and
whether, immobilised and Locked, Caution Notice affixed, other Safety Precautions
applied, as appropriate.

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

Issue 5 Revision 8 OC8B 10 June 2014


19 of 28
(b) EARTHING

State the Location(s) at which Earthing has been established on the Implementing
Safety Co-ordinator's System. For each Location, identify each point of Earthing. For
each point of Earthing state, the means by which the Earthing has been achieved, and
whether, immobilised and Locked, other Safety Precautions applied, as appropriate.

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

________________________________________________________________

1.3 ISSUE

I confirmed to ____________________ (name of Requesting Safety Co-ordinator) at


____________________ (Location) that the Safety Precautions identified in paragraph
1.2 have been established and that instructions will not be issued at my Location for
their removal until this RISSP is cancelled.

Signed ......................................................... (Implementing Safety Co-ordinator)

at ............................. (time) on .............................. (date)

PART 2

2.1 CANCELLATION

I have received confirmation from ____________________ (name of the Requesting


Safety Co-ordinator) at ____________________ (Location) that the Safety
Precautions set out in paragraph 1.2 are no longer required and accordingly the
RISSP is cancelled.

Signed .................................................. (Implementing Safety Co-ordinator)

at ................................. (time) on ........................... (date)

(Note: This form to be of a different colour from RISSP-R.)

Issue 5 Revision 8 OC8B 10 June 2014


20 of 28
APPENDIX C - FLOWCHARTS

APPENDIX C1 - RISSP ISSUE PROCESS

Issue 5 Revision 8 OC8B 10 June 2014


21 of 28
APPENDIX C2 - TESTING PROCESS

Issue 5 Revision 8 OC8B 10 June 2014


22 of 28
APPENDIX C3 - RISSP CANCELLATION PROCESS

Issue 5 Revision 8 OC8B 10 June 2014


23 of 28
APPENDIX C4 - PROCESS FOR WORKING NEAR TO SYSTEM EQUIPMENT

Issue 5 Revision 8 OC8B 10 June 2014


24 of 28
APPENDIX D - NOT USED

Not Used

Issue 5 Revision 8 OC8B 10 June 2014


25 of 28
APPENDIX E - FORM OF PERMIT TO WORK

Scottish & Southern Energy plc


PERMIT-TO-WORK No. .
______________________________________________________________

1. ISSUE

To .....

The following High Voltage Apparatus has been made safe in accordance with the Operational Safety Rules for the work detailed on
this Permit-to-Work to proceed:

......

......

......

TREAT ALL OTHER APPARATUS AS LIVE

Circuit Main Earths are applied at: .......

......

......

......

Other precautions (see Operational Safety Rules 3.2.1(b), 4.6.2(c) and 5.5.3), and any special instructions:

......

......

......

The following work is to be carried out: .......

......

......

......

Circuit Identification Issued: Colour .... No. of wristlets ... No. of step bolts ..

Name: (print): ...... Signature: ...... Time: ... Date: ..

_____________________________________________________________________________________________

2. RECEIPT

I accept responsibility for carrying out the work on the Apparatus detailed on this Permit-to-Work, applying additional earths as
necessary. No attempt will be made by me, or by the persons under my charge, to work on any other Apparatus.

Name: (print): ...... Signature: ...... Time: ... Date: ..

Circuit Identification Equipment Checked as above (Initials):

_____________________________________________________________________________________________

3. CLEARANCE

All persons under my control have been withdrawn and warned that it is no longer safe to work on the Apparatus detailed on this
Permit-to Work.

All gear, tools and additional earths have/have not* been removed. The works is/is not* complete.

All circuit identification equipment issued as above has been returned

Name: (print): ...... Signature: ...... Time: ... Date: ..

* Delete where not applicable

_____________________________________________________________________________________________

4. CANCELLATION

This Permit-to-Work is cancelled.

Name: (print): ...... Signature: ...... Time: ... Date: ..


Issue 5 Revision 8 OC8B 10 June 2014
26 of 28
Scottish Power

PERMIT FOR WORK No.

KEY SAFE No.

1. (i) LOCATION ..

....

(ii) PLANT/APPARATUS IDENTIFICATION .

(iii) WORK TO BE DONE .

....

....

....

_____________________________________________________________________________________________

2. (i) PRECAUTIONS TAKEN TO ACHIEVE SAFETY FROM THE SYSTEM: State points at which Plant/Apparatus has been
Isolated and specify position(s) of Earthing Devices applied. State actions taken to avoid Danger by draining, venting,
purging and containment or dissipation of stored energy.

...

...

...

...

...

...

...

...

...

Caution Notices have been affixed to all points of isolation

(ii) FURTHER PRECAUTIONS TO BE TAKEN DURING THE COURSE OF WORK TO AVOID SYSTEM DERIVED HAZARDS

...

...

...

...

...

I have confirmed with the Control Person(s)* . that precautions


in Section 2(i) have been carried out and that the Control Person(s) will maintain these until this Permit for Work is cancelled. I
certify that the precautions in Section 2(i) together with the precautions in Section 2(ii) are adequate to provide Safety from the
System in respect of the work in Section 1.

This Permit for Work must only be transferred under the Personal Supervision of a Senior Authorised

Person* ..

Signed . being a Senior Authorised Person. Time: .. Date: .

____________________________________________________________________________________________

3. ISSUE

(i) Key Safe Key (No.)* .... (ii) Earthing Schedule* .... (iii) Portable Drain Earths (No. off)*

(iv) Selected Persons Report (No.)* .. (v) Circuit Identification Flags (No. off)*

(vi) Circuit Identification Wristlets (No. off)* and Colours/Symbols .

Signed .. being the Senior Authorised Person responsible

for the issue of this Permit for Work Time: Date:

Issue 5 Revision 8 OC8B 10 June 2014


27 of 28
_____________________________________________________________________________________________

4. RECEIPT

I understand and accept my responsibilities under the ScottishPower Safety Rules as recipient of this Permit for Work and
acknowledge receipt of the items in Section 3.

Signed .. Name (Block Letters) .

being a Competent Person in the employ of Firm/Dept Time . Date

_____________________________________________________________________________________________

TRANSFER RECORD

PART 1 PART 2 PART 3

Person Time Senior Person receiving reissued Senior Time


surrendering Authorised Document Authorised
Date Date
Document Person receiving Person
Signature Name (Block
suspended reissuing
Letters)
Document * document

Signature of Person receiving re-issued Document in accordance with conditions detailed in Section 4.

_____________________________________________________________________________________________

5. CLEARANCE: I certify that all persons working under this Permit for Work have been withdrawn from, and warned not to work
on, the Plant/Apparatus in Section 1. All gears, tools, Drain Earths and loose material have been removed and guards and
access doors have been replaced, except for:

..

..

..

Signed being the Competent Person responsible for

clearing this Permit for Work Time Date .

_____________________________________________________________________________________________

6. CANCELLATION: I certify that all items issued under Section 3 have been accounted for and the Control

Person(s)* . informed of the cancellation and of any restrictions on returning

the Plant/Apparatus to service.

Signed . being the Senior Authorised Person responsible for

cancelling this Permit for Work. Time . Date .

_____________________________________________________________________________________________

*N/A if Not Applicable

< END OF OPERATING CODE NO. 8 APPENDIX 2 >

Issue 5 Revision 8 OC8B 10 June 2014


28 of 28
OPERATING CODE NO. 9
(OC9)

CONTINGENCY PLANNING

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC9.1 INTRODUCTION.....................................................................................................................................2
OC9.2 OBJECTIVE ............................................................................................................................................2
OC9.3 SCOPE ....................................................................................................................................................3
OC9.4 BLACK START ........................................................................................................................................3
OC9.4.1 - OC9.4.4 Total Shutdown And Partial Shutdown.........................................................................3
OC9.4.5 Black Start Stations ......................................................................................................................3
OC9.4.6 Black Start Situation .....................................................................................................................4
OC9.4.7 Black Start ....................................................................................................................................4
OC9.5 RE-SYNCHRONISATION OF DE-SYNCHRONISED ISLANDS ..........................................................12
OC9.5.2 Options .......................................................................................................................................12
OC9.5.3 Choice Of Option ........................................................................................................................14
OC9.5.4 Agreeing Procedures ..................................................................................................................15
OC9.6 JOINT SYSTEM INCIDENT PROCEDURE ..........................................................................................17

Issue 5 Revision 16 OC9 24 May 2016


i
OC9.1 INTRODUCTION
Operating Code No.9 ("OC9") covers the following:
OC9.1.1 Black Starts
The implementation of recovery procedures following a Total Shutdown or Partial
Shutdown.
OC9.1.2 Re-Synchronisation Of Islands
The Re-Synchronisation of parts of the Total System which have become Out of
Synchronism with each other irrespective of whether or not a Total Shutdown or Partial
Shutdown has occurred.
OC9.1.3 Joint System Incident Procedure
The establishment of a communication route and arrangements between senior
management representatives of NGET and Users involved in, or who may be involved in, an
actual or potential serious or widespread disruption to the Total System or a part of the
Total System, which requires, or may require, urgent managerial response, day or night, but
which does not fall within the provisions of OC9.1.4.
OC9.1.4 It should be noted that under section 96 of the Act the Secretary of State may give
directions to NGET and/or any Generator and/or any Supplier, for the purpose of "mitigating
the effects of any civil emergency which may occur" (ie. for the purposes of planning for a
civil emergency); a civil emergency is defined in the Act as "any natural disaster or other
emergency which, in the opinion of the Secretary of State, is or may be likely to disrupt
electricity supplies". Under the Energy Act 1976, the Secretary of State has powers to make
orders and give directions controlling the production, supply, acquisition or use of electricity,
where an Order in Council under section 3 is in force declaring that there is an actual or
imminent emergency affecting electricity supplies. In the event that any such directions are
given, or orders made under the Energy Act 1976, the provisions of the Grid Code will be
suspended in so far as they are inconsistent with them.
OC9.1.5 NGET shall procure that Relevant Scottish Transmission Licensees shall comply with
OC9.4 and OC9.5 and any relevant Local Joint Restoration Plan or OC9 De-
Synchronised Island Procedure where and to the extent that such matters apply to them.

OC9.2 OBJECTIVE
The overall objectives of OC9 are:
OC9.2.1 To achieve, as far as possible, restoration of the Total System and associated Demand in
the shortest possible time, taking into account Power Station capabilities, including
Embedded Generating Units, External Interconnections and the operational constraints
of the Total System.
OC9.2.2 To achieve the Re-Synchronisation of parts of the Total System which have become Out
of Synchronism with each other.
OC9.2.3 To ensure that communication routes and arrangements are available to enable senior
management representatives of NGET and Users, who are authorised to make binding
decisions on behalf of NGET or the relevant User, as the case may be, to communicate with
each other in the situation described in OC9.1.3.
OC9.2.4 To describe the role that in respect of Scottish Transmission Systems, Relevant Scottish
Transmission Licensees may have in the restoration processes as detailed in the relevant
OC9 De-Synchronised Island Procedures and Local Joint Restoration Plans.
OC9.2.5 To identify and address as far as possible the events and processes necessary to enable the
restoration of the Total System, after a Total Shutdown or Partial Shutdown. This is likely
to require the following key processes to be implemented, typically, but not necessarily, in the
order given below:

Issue 5 Revision 16 OC9 24 May 2016


2 of 18
(i) Selectively implement Local Joint Restoration Plans
(ii) Expand Power Islands to supply Power Stations
(iii) Expand and merge Power Islands leading to Total System energisation
(iv) Selectively reconnect Demand
(v) Facilitate and co-ordinate returning the Total System back to normal operation
(vi) Resumption of the Balancing Mechanism if suspended in accordance with the
provisions of the BSC.

OC9.3 SCOPE
OC9.3.1 OC9 applies to NGET and to Users, which in OC9 means:-
(a) Generators;
(b) Network Operators; and
(c) Non-Embedded Customers.
OC9.3.2 The procedure for the establishment of emergency support/contingency planning between
NGET and Externally Interconnected System Operators is set out in the Interconnection
Agreement with each Externally Interconnected System Operator.
OC9.3.3 In respect of Scottish Transmission Systems, OC9.4 and OC9.5 also apply to Relevant
Scottish Transmission Licensees.

OC9.4 BLACK START


Total Shutdown And Partial Shutdown
OC9.4.1 A "Total Shutdown" is the situation existing when all generation has ceased and there is no
electricity supply from External Interconnections. Therefore, the Total System has
shutdown with the result that it is not possible for the Total System to begin to function again
without NGET's directions relating to a Black Start.
OC9.4.2 A "Partial Shutdown" is the same as a Total Shutdown except that all generation has
ceased in a separate part of the Total System and there is no
electricity supply from External Interconnections or other parts of the Total System to that
part of the Total System. Therefore, that part of the Total System is shutdown with the
result that it is not possible for that part of the Total System to begin to function again
without NGET's directions relating to a Black Start.
OC9.4.3 During a Total Shutdown or Partial Shutdown and during the subsequent recovery, the
Licence Standards may not apply and the Total System may be operated outside normal
voltage and Frequency standards.
OC9.4.4 In a Total Shutdown and in a Partial Shutdown and during the subsequent recovery, it is
likely to be necessary for NGET to issue Emergency Instructions in accordance with
BC2.9.
OC9.4.5 Black Start Stations
OC9.4.5.1 Certain Power Stations ("Black Start Stations") are registered, pursuant to the Bilateral
Agreement with a User, as having an ability for at least one of its Gensets to Start-Up from
Shutdown and to energise a part of the Total System, or be Synchronised to the System,
upon instruction from NGET within two hours, without an external electrical power supply
("Black Start Capability").

Issue 5 Revision 16 OC9 24 May 2016


3 of 18
OC9.4.5.2 For each Black Start Station, a Local Joint Restoration Plan will be produced jointly by
NGET, the relevant Generator and Network Operator in accordance with the provisions of
OC9.4.7.12. The Local Joint Restoration Plan will detail the agreed method and procedure
by which a Genset at a Black Start Station (possibly with other Gensets at that Black Start
Station) will energise part of the Total System and meet complementary local Demand so
as to form a Power Island.
OC9.4.5.3 In respect of Scottish Transmission Systems, a Local Joint Restoration Plan may cover
more than one Black Start Station and may be produced with and include obligations on
Relevant Scottish Transmission Licensees, Generators responsible for Gensets not at a
Black Start Station and other Users.
OC9.4.6 Black Start Situation
In the event of a Total Shutdown or Partial Shutdown, NGET will, as soon as reasonably
practical, inform Users (or, in the case of a Partial Shutdown, Users which in NGET's
opinion need to be informed) and the BSCCo that a Total Shutdown, or, as the case may
be, a Partial Shutdown, exists and that NGET intends to implement a Black Start. NGET
shall (as soon as is practicable) determine, in its reasonable opinion, the time and date with
effect from which the Total Shutdown or Partial Shutdown commenced and notify BSCCo
of that time and date.
In the event of a Total Shutdown and following such notification, in accordance with the
provisions of the BSC, the BSCCo will determine the Settlement Period with effect from
which the Balancing Mechanism is suspended.
In the event of a Partial Shutdown and following such notification, the Balancing
Mechanism will not be suspended until such time and date that the Market Suspension
Threshold has been met, or deemed to have been met, in accordance with the provisions of
the BSC. NGET shall carry out the monitoring activities required by paragraph G3.1 of the
BSC.

Following determination by NGET pursuant to its obligations under the BSC that the Market
Suspension Threshold has been met, or deemed to have been met, NGET shall (as soon
as practicable) inform the BSCCo of that time and date at which the Market Suspension
Threshold was met, or deemed to have been met, and the BSCCo will determine the
Settlement Period in accordance with the provisions of the BSC with effect from which the
Balancing Mechanism will be suspended.

Should NGET determine that the Total System is capable of returning to normal operation
without meeting the Market Suspension Threshold, NGET will follow the procedure given
in OC9.4.7.9.

The Black Start will conclude with effect from the time and date determined in accordance
with OC9.4.7.10.
In respect of Scottish Transmission Systems, in exceptional circumstances, as specified in
the Local Joint Restoration Plan, SPT or SHETL, may invoke such Local Joint
Restoration Plan for its own Transmission System and Scottish Offshore Transmission
Systems connected to it and operate within its provisions.
OC9.4.7 Black Start
OC9.4.7.1 The procedure necessary for a recovery from a Total Shutdown or Partial Shutdown is
known as a "Black Start". The procedure for a Partial Shutdown is the same as that for a
Total Shutdown except that it applies only to a part of the Total System. It should be
remembered that a Partial Shutdown may affect parts of the Total System which are not
themselves shutdown.

Issue 5 Revision 16 OC9 24 May 2016


4 of 18
OC9.4.7.2 The complexities and uncertainties of recovery from a Total Shutdown or Partial Shutdown
require that OC9 is sufficiently flexible in order to accommodate the full range of Genset and
Total System characteristics and operational possibilities, and this precludes the setting out
in the Grid Code itself of concise chronological sequences. The overall strategy will, in
general, include the overlapping phases of establishment of Genset(s) at an isolated Power
Station, together with complementary local Demand, termed "Power Islands", step by step
integration of these Power Islands into larger sub-systems which includes utilising the
procedures in OC9.5 (Re-Synchronisation of De-Synchronised Island) and eventually re-
establishment of the complete Total System.
NGET Instructions
OC9.4.7.3 The procedures for a Black Start will, therefore, be those specified by NGET at the time.
These will normally recognise any applicable Local Joint Restoration Plan. Users shall
abide by NGET's instructions during a Black Start situation, even if these conflict with the
general overall strategy outlined in OC9.4.7.2 or any applicable Local Joint Restoration
Plan. NGET's instructions may (although this list should not be regarded as exhaustive) be
to a Black Start Station relating to the commencement of generation, to a Network
Operator or Non-Embedded Customer relating to the restoration of Demand, and to a
Power Station relating to preparation for commencement of generation when an external
power supply is made available to it, and in each case may include the requirement to
undertake switching.
In respect of Scottish Transmission Systems SPT and SHETL will act on NGETs behalf in
accordance with its duties under the relevant Local Joint Restoration Plan. Scottish
Users shall abide by SPTs or SHETLs instructions given in accordance with the Local
Joint Restoration Plan during a Black Start situation.
OC9.4.7.4 (a) Black Start following a Total Shutdown or where the Balancing Mechanism has been
suspended following a Partial Shutdown
During a Black Start situation where the Balancing Mechanism has been suspended, all
instructions to Power Stations and to Network Operators will be deemed to be Emergency
Instructions under BC2.9.2.2 (iii). All such Emergency Instructions will recognise any
differing Black Start operational capabilities (however termed) set out in the relevant
Ancillary Services Agreement in preference to the declared operational capability as
registered pursuant to BC1 (or as amended from time to time in accordance with the BC).
For the purposes of these instructions the Black Start will be an emergency circumstance
under BC2.9.
In Scotland, Gensets that are not at Black Start Stations, but which are part of a Local
Joint Restoration Plan, may be instructed in accordance with the provisions of that Local
Joint Restoration Plan.

(b) Black Start following a Partial Shutdown where the Balancing Mechanism has not
been suspended

During a Black Start situation where the Balancing Mechanism has not been suspended,
instructions in relation to Black Start Stations and to Network Operators which are part of
an invoked Local Joint Restoration Plan will (unless NGET specifies otherwise) be deemed
to be Emergency Instructions under BC2.9.2.2 (iv) and will recognise any differing Black
Start operational capabilities (however termed) set out in the relevant Ancillary Services
Agreement in preference to the declared operational capability as registered pursuant to
BC1 (or as amended from time to time in accordance with the BC). For the purposes of
these instructions the Black Start will be an emergency circumstance under BC2.9.

Issue 5 Revision 16 OC9 24 May 2016


5 of 18
During a Black Start situation where the Balancing Mechanism has not been suspended,
NGET may issue instructions to Users other than Black Start Stations and Network
Operators which are part of an invoked Local Joint Restoration Plan. Such instructions
would be Emergency Instructions pursuant to BC2.9.1.2(e)(i) subject to the requirements of
BC2.9.2.2 being met.

In Scotland, Gensets that are not at Black Start Stations, but which are part of an invoked
Local Joint Restoration Plan, may be instructed in accordance with the provisions of that
Local Joint Restoration Plan.

(c) If during the Demand restoration process any Genset cannot, because of the Demand
being experienced, keep within its safe operating parameters, the Generator shall, unless a
Local Joint Restoration Plan is in operation, inform NGET. NGET will, where possible,
either instruct Demand to be altered or will re-configure the National Electricity
Transmission System or will instruct a User to re-configure its System in order to alleviate
the problem being experienced by the Generator. If a Local Joint Restoration Plan is in
operation, then the arrangements set out therein shall apply. However, NGET accepts that
any decision to keep a Genset operating, if outside its safe operating parameters, is one for
the Generator concerned alone and accepts that the Generator may change generation on
that Genset if it believes it is necessary for safety reasons (whether relating to personnel or
Plant and/or Apparatus). If such a change is made without prior notice, then the Generator
shall inform NGET as soon as reasonably practical (unless a Local Joint Restoration Plan
is in operation in which case the arrangements set out therein shall apply).

Embedded Power Stations


OC9.4.7.5 Without prejudice to the provisions of OC9.4.7.8, Network Operators with Embedded
Power Stations will comply with any directions of NGET to restore Demand to be met by the
Embedded Power Stations.

Issue 5 Revision 16 OC9 24 May 2016


6 of 18
Local Joint Restoration Plan operation
OC9.4.7.6 (a) The following provisions apply in relation to a Local Joint Restoration Plan. As set out
in OC9.4.7.3, NGET may issue instructions which conflict with a Local Joint
Restoration Plan. In such cases, these instructions will take precedence over the
requirements of the Local Joint Restoration Plan. When issuing such instructions,
NGET shall state whether or not it wishes the remainder of the Local Joint Restoration
Plan to apply. If, not withstanding that NGET has stated that it wishes the remainder of
the Local Joint Restoration Plan to apply, the Generator or the relevant Network
Operator consider that NGETs instructions mean that it is not possible to operate the
Local Joint Restoration Plan as modified by those instructions, any of them may give
notice to NGET and the other parties to the Local Joint Restoration Plan to this effect
and NGET shall immediately consult with all parties to the Local Joint Restoration
Plan. Unless all parties to the Local Joint Restoration Plan reach an agreement
forthwith as to how the Local Joint Restoration Plan shall operate in those
circumstances, operation in accordance with the Local Joint Restoration Plan will
terminate.
(b) Where NGET, as part of a Black Start, has given an instruction to a Black Start
Station to initiate Start-Up, the relevant Genset(s) at the Black Start Station will Start-
Up in accordance with the Local Joint Restoration Plan.
(c) NGET will advise the relevant Network Operator of the requirement to switch its User
System so as to segregate its Demand and to carry out such other actions as set out in
the Local Joint Restoration Plan. The relevant Network Operator will then operate in
accordance with the provisions of the Local Joint Restoration Plan.
(d) NGET will ensure that switching carried out on the National Electricity Transmission
System and other actions are as set out in the Local Joint Restoration Plan.
(e) Following notification from the Generator that the Black Start Station is ready to
accept load, NGET will instruct the Black Start Station to energise part of the Total
System. The Black Start Station and the relevant Network Operator will then, in
accordance with the requirements of the Local Joint Restoration Plan, establish
communication and agree the output of the relevant Genset(s) and the connection of
Demand so as to establish a Power Island. During this period, the Generator will be
required to regulate the output of the relevant Genset(s) at its Black Start Station to
the Demand prevailing in the Power Island in which it is situated, on the basis that it will
(where practicable) seek to maintain the Target Frequency. The Genset(s) at the
Black Start Station will (where practical) also seek to follow the requirements relating to
Reactive Power (which may include the requirement to maintain a target voltage) set
out in the Local Joint Restoration Plan.
(f) Operation in accordance with the Local Joint Restoration Plan will be terminated by
NGET (by notifying the relevant Users) prior to connecting the Power Island to other
Power Islands (other than, in Scotland, as allowed for in the Local Joint Restoration
Plan), or to the User System of another Network Operator, or to the synchronising of
Gensets at other Power Stations (other than, in Scotland, those forming part of the
Local Joint Restoration Plan). Operation in accordance with the Local Joint
Restoration Plan will also terminate in the circumstances provided for in OC9.4.7.6(a) if
an agreement is not reached or if NGET states that it does not wish the remainder of the
Local Joint Restoration Plan to apply. Users will then comply with the Bid-Offer
Acceptances or Emergency Instructions of NGET.
(g) In Scotland, Gensets included in a Local Joint Restoration Plan, but not at a Black
Start Station, will operate in accordance with the requirements of the Local Joint
Restoration Plan.

Issue 5 Revision 16 OC9 24 May 2016


7 of 18
Interconnection of Power Islands
OC9.4.7.7 NGET will instruct the relevant Users so as to interconnect Power Islands to achieve larger
sub-systems, and subsequently the interconnection of these sub-systems to form an
integrated system. This should eventually achieve the re-establishment of the Total System
or that part of the Total System subject to the Partial Shutdown, as the case may be. The
interconnection of Power Islands and sub-systems will utilise the provisions of all or part of
OC9.5 (Re-Synchronisation of De-synchronised Islands) and in such a situation such
provisions will be part of the Black Start.
OC9.4.7.8 As part of the Black Start strategy each Network Operator with either an Embedded Black
Start Station which has established a Power Island within its User System or with any
Embedded Power Stations within its User System which have become islanded, may in
liaison with NGET sustain and expand these islands in accordance with the relevant
provisions of OC9.5 which shall apply to this OC9.4 as if set out here. They will inform NGET
of their actions and will not Re-Synchronise to the National Electricity Transmission
System or any
User's System which is already Synchronised to the National Electricity Transmission
System without NGET's agreement.
Return the Total System Back to Normal Operation
OC9.4.7.9 NGET shall, as soon as reasonably practical, inform Users and the BSCCo when the Total
System could return to normal operation. Any such determination by NGET does not mean
that the provisions of Section G paragraph 3 (Black Start) of the BSC shall cease to apply.
In making the determination that the Total System could return to normal operation, NGET,
would consider, amongst other things, the following areas:
(a) the extent to which the National Electricity Transmission System is contiguous and
energised;
(b) the integrity and stability of the National Electricity Transmission System and its
ability to operate in accordance with the Licence Standards;
(c) the impact that returning to normal may have on transmission constraints and the
corresponding ability to maximise the Demand connected; and
(d) the volume of generation or Demand not connected to the National Electricity
Transmission System; and
(e) the functionality of normal communication systems (i.e. electronic data communication
facilities, Control Telephony, etc).
In the event that the Balancing Mechanism has been suspended, it will not resume until the
start of the Settlement Period determined by the BSC Panel in accordance with paragraph
G3.1.2(d)(i) of the BSC.

For the avoidance of doubt, until resumption of the Balancing Mechanism, NGET is likely to
continue to issue Emergency Instructions in accordance with BC2.9.
Users shall use reasonable endeavours to submit Physical notifications ten hours prior to
the start of the Settlement Period determined by the BSC Panel in accordance with
paragraph G3.1.2(d)(i) of the BSC and as notified by NGET to Users, in preparation for a
return to normal operations.
In the event that the Balancing Mechanism has not been suspended and NGET has
determined that the Total System has returned to normal operation, NGET shall inform
Users and the BSCCo as soon as possible of the time and date at which (in NGETs
determination) the Total System returned to normal operation.

Issue 5 Revision 16 OC9 24 May 2016


8 of 18
Conclusion of Black Start
OC9.4.7.10 The provisions of this OC9 shall cease to apply with effect from either:

(a) Where the Balancing Mechanism was suspended, the start of the Settlement Period
that the Balancing Mechanism resumed normal operation, as determined by the BSC
Panel and notified by the BSCCo in accordance with the provisions of the BSC; or

(b) Where the Balancing Mechanism was not suspended, the end of the Settlement
Period determined and notified by the BSCCo (in accordance with the provisions of the
BSC) and corresponding to the time and date that NGET determined that the Total System
had returned to normal operation.

Externally Interconnected System Operators


OC9.4.7.11 During a Black Start, NGET will, pursuant to the Interconnection Agreement with
Externally Interconnected System Operators, agree with Externally Interconnected
System Operators when their transmission systems can be Re-Synchronised to the Total
System, if they have become separated.

OC9.4.7.12 Local Joint Restoration Plan Establishment


(a) In England and Wales, in relation to each Black Start Station, NGET, the Network
Operator and the relevant Generator will discuss and agree a Local Joint Restoration
Plan. Where at the date of the first inclusion of this OC9.4.7.12 into the Grid Code a
local plan covering the procedures to be covered in a Local Joint Restoration Plan is
in existence and agreed, NGET will discuss this with the Network Operator and the
relevant Generator to agree whether it is consistent with the principles set out in this
OC9.4. If it is agreed to be so consistent, then it shall become a Local Joint
Restoration Plan under this OC9 and the relevant provisions of OC9.4.7.12(b) shall
apply. If it is not agreed to be so consistent, then the provisions of OC9.4.7.12(b) shall
apply as if there is no Local Joint Restoration Plan in place.
In respect of Scottish Transmission Systems where a requirement for a Local Joint
Restoration Plan is identified, NGET, the Relevant Scottish Transmission
Licensee(s), the Network Operator and Black Start Station(s) will discuss and agree
a Local Joint Restoration Plan. In addition other Users, including other Generators,
may be reasonably required by NGET to discuss and agree a Local Joint Restoration
Plan.
(b) In England and Wales, where the need for a Local Joint Restoration Plan arises when
there is none in place, the following provisions shall apply:
(i) NGET, the Network Operator and the relevant Generator will discuss and agree
the detail of the Local Joint Restoration Plan as soon as the requirement for a
Local Joint Restoration Plan is identified by NGET. NGET will notify all affected
Users, and will initiate these discussions.
(ii) Each Local Joint Restoration Plan will be in relation to a specific Black Start
Station.
(iii) The Local Joint Restoration Plan will record which Users and which User Sites
are covered by the Local Joint Restoration Plan and set out what is required from
NGET and each User should a Black Start situation arise.
(iv) Each Local Joint Restoration Plan shall be prepared by NGET to reflect the
above discussions and agreement.
(v) Each page of the Local Joint Restoration Plan shall bear a date of issue and the
issue number.

Issue 5 Revision 16 OC9 24 May 2016


9 of 18
(vi) When a Local Joint Restoration Plan has been prepared, it shall be sent by
NGET to the Users involved for confirmation of its accuracy.
(vii) The Local Joint Restoration Plan shall then (if its accuracy has been confirmed)
be signed on behalf of NGET and on behalf of each relevant User by way of written
confirmation of its accuracy.
(viii) Once agreed under this OC9.4.7.12, the procedure will become a Local Joint
Restoration Plan under the Grid Code and (subject to any change pursuant to this
OC9) will apply between NGET and the relevant Users as if it were part of the Grid
Code.
(ix) Once signed, a copy of the Local Joint Restoration Plan will be distributed by
NGET to each User which is a party to it accompanied by a note indicating the date
of implementation.
(x) NGET and Users must make the Local Joint Restoration Plan readily available to
the relevant operational staff.
(xi) If NGET, or any User which is a party to a Local Joint Restoration Plan, becomes
aware that a change is needed to that Local Joint Restoration Plan, it shall (in the
case of NGET) initiate a discussion between NGET and the relevant Users to seek
to agree the relevant change. If a User becomes so aware, it shall contact NGET
who will then initiate such discussions. The principles applying to establishing a new
Local Joint Restoration Plan under this OC9.4.7.12 shall apply to such
discussions and to any consequent changes.
(xii) NGET, the Network Operator and the relevant Generator will conduct regular joint
exercises of the Local Joint Restoration Plan to which they are parties. The
objectives of such exercises include:

To test the effectiveness of the Local Joint Restoration Plan;


To provide for joint training of the parties in respect of the Local Joint
Restoration Plan;
To maintain the parties awareness and familiarity of the Local Joint
Restoration Plan;
To promote understanding of each parties roles under a Local Joint
Restoration Plan;
To identify any improvement areas which should be incorporated in to the
Local Joint Restoration Plan.
The principles applying to the establishment of a new Local Joint
Restoration Plan under this OC9.4.7.12 shall apply to any changes to the
Local Joint Restoration Plan.
NGET will propose to the parties of a Local Joint Restoration Plan a date for the
exercise to take place, to be agreed with the other parties. All the Local Joint
Restoration Plan parties will jointly share the task of planning, preparing,
participating in and facilitating the exercises, which will normally be in desktop
format or as otherwise agreed. The precise timing of the exercise for each Local
Joint Restoration Plan will be agreed by all parties, but will not be less than one
every 8 years.
(c) In respect of Scottish Transmission Systems, where the need for a Local Joint
Restoration Plan arises, the following provisions shall apply:

Issue 5 Revision 16 OC9 24 May 2016


10 of 18
(i) NGET, the Relevant Scottish Transmission Licensee(s), the Network Operator
and the relevant Generator will discuss and agree the detail of the Local Joint
Restoration Plan as soon as the requirement for a Local Joint Restoration Plan
is identified by NGET. In addition other Scottish Users, including other
Generators, may be reasonably required by NGET to discuss and agree details of
the Local Joint Restoration Plan as soon as the requirement for a Local Joint
Restoration Plan is identified by NGET. NGET will notify the Relevant Scottish
Transmission Licensee(s) and all affected Scottish Users, and will initiate these
discussions.
(ii) Each Local Joint Restoration Plan may be in relation to either a specific Black
Start Station or a number of Black Start Stations, and may include Gensets at
Power Stations other than a Black Start Station.
(iii) The Local Joint Restoration Plan will record which Scottish Users and which
Scottish User Sites are covered by the Local Joint Restoration Plan and set out
what is required from NGET, the Relevant Scottish Transmission Licensee(s)
and each Scottish User should a Black Start situation arise.
(iv) Each Local Joint Restoration Plan shall be prepared by NGET to reflect the
above discussions and agreement.
(v) Each page of the Local Joint Restoration Plan shall bear a date of issue and the
issue number.
(vi) When a Local Joint Restoration Plan has been prepared, it shall be sent by
NGET to the Relevant Scottish Transmission Licensee(s) and Scottish Users
involved for confirmation of its accuracy.
(vii) The Local Joint Restoration Plan shall then (if its accuracy has been confirmed)
be signed on behalf of NGET and on behalf of each relevant Scottish User and
Relevant Scottish Transmission Licensee(s) by way of written confirmation of its
accuracy.
(viii) Once agreed under this OC9.4.7.12, the procedure will become a Local Joint
Restoration Plan under the Grid Code and (subject to any change pursuant to this
OC9) will apply between NGET, Relevant Scottish Transmission Licensee(s)
and the relevant Scottish Users as if it were part of the Grid Code.
(ix) Once signed, a copy of the Local Joint Restoration Plan will be distributed by
NGET to the Relevant Scottish Transmission Licensee(s) and each Scottish
User which is a party to it accompanied by a note indicating the date of
implementation.
(x) NGET, the Relevant Scottish Transmission Licensee(s) and Scottish Users
must make the Local Joint Restoration Plan readily available to the relevant
operational staff.
(xi) If NGET, the Relevant Scottish Transmission Licensee(s) or any Scottish User
which is a party to a Local Joint Restoration Plan, becomes aware that a change
is needed to that Local Joint Restoration Plan, it shall (in the case of NGET)
initiate a discussion between NGET, the Relevant Scottish Transmission
Licensee(s) and the relevant Scottish Users to seek to agree the relevant change.
If a Scottish User or a Relevant Scottish Transmission Licensee becomes so
aware, it shall contact NGET who will then initiate such discussions. The principles
applying to establishing a new Local Joint Restoration Plan under this
OC9.4.7.12 shall apply to such discussions and to any consequent changes.
(xii) NGET, the Relevant Scottish Transmission Licensee(s), the Network Operator
and the relevant Generator will conduct regular joint exercises of the Local Joint
Restoration Plan to which they are parties. The objectives of such exercises
include:

To test the effectiveness of the Local Joint Restoration Plan;


Issue 5 Revision 16 OC9 24 May 2016
11 of 18
To provide for joint training of the parties in respect of the Local Joint
Restoration Plan;
To maintain the parties awareness and familiarity of the Local Joint
Restoration Plan;
To promote understanding of each parties roles under a Local Joint
Restoration Plan;
To identify any improvement areas which should be incorporated in to the
Local Joint Restoration Plan.
The principles applying to the establishment of a new Local Joint
Restoration Plan under this OC9.4.7.12 shall apply to any changes to the
Local Joint Restoration Plan.
NGET will propose to the parties of a Local Joint Restoration Plan a date for the
exercise to take place, to be agreed with the other parties. All the Local Joint
Restoration Plan parties will jointly share the task of planning, preparing,
participating in and facilitating the exercises, which will normally be in desktop
format or as otherwise agreed. The precise timing of the exercise for each Local
Joint Restoration Plan will be agreed by all parties, but will not be less than one
every 8 years.

OC9.5 RE-SYNCHRONISATION OF DE-SYNCHRONISED ISLANDS


The provisions in this OC9.5 do not apply to the parts of the Total System that normally
operate Out of Synchronism with the rest of the National Electricity Transmission
System.
Further requirements, including the provision of information, applying to Re-synchronisation
of De-synchronised Islands following any Total Shutdown or Partial Shutdown are
detailed in OC9.5.6.
OC9.5.1 (a) Where parts of the Total System are Out of Synchronism with each other (each such
part being termed a "De-Synchronised Island"), but there is no Total Shutdown or
Partial Shutdown, NGET will instruct Users to regulate generation or Demand, as the
case may be, to enable the De-Synchronised Islands to be Re-Synchronised and
NGET will inform those Users when Re-Synchronisation has taken place.
(b) As part of that process, there may be a need to deal specifically with Embedded
generation in those De-Synchronised Islands. This OC9.5 provides for how such
Embedded generation should be dealt with. In Scotland, this OC9.5 also provides for
how Transmission connected generation in De-Synchronised Islands should be dealt
with.
(c) In accordance with the provisions of the BC, NGET may decide that, to enable Re-
Synchronisation, it will issue Emergency Instructions in accordance with BC2.9 and it
may be necessary to depart from normal Balancing Mechanism operation in
accordance with BC2 in issuing Bid-Offer Acceptances.
(d) The provisions of this OC9.5 shall also apply during a Black Start to the Re-
Synchronising of parts of the System following a Total or Partial Shutdown, as
indicated in OC9.4. In such cases, the provisions of the OC9.5 shall apply following
completion and/or termination of the relevant Local Joint Restoration Plan(s) process
as referred to in OC9.4.7.6(f).
OC9.5.2 Options
Generation in those De-Synchronised Islands may be dealt with in three different ways,
more than one of which may be utilised in relation to any particular incident:-
OC9.5.2.1 Indirect Data

Issue 5 Revision 16 OC9 24 May 2016


12 of 18
(a) NGET, each Generator with Synchronised (or connected and available to generate
although not Synchronised) Genset(s) in the De-Synchronised Island and the
Network Operator whose User System forms all or part of the De-Synchronised
Island shall exchange information as set out in this OC9.5.2.1 to enable NGET to issue
a Bid-Offer Acceptance or an Emergency Instruction to that Generator in relation to
its Genset(s) in the De-Synchronised Island until Re-Synchronisation takes place, on
the basis that it will (where practicable) seek to maintain the Target Frequency.
(b) The information to NGET from the Generator will cover its relevant operational
parameters as outlined in the BC and from NGET to the Generator will cover data on
Demand and changes in Demand in the De-Synchronised Island.
(c) The information from the Network Operator to NGET will comprise data on Demand in
the De-Synchronised Island, including data on any constraints within the De-
Synchronised Island.
(d) NGET will keep the Network Operator informed of the Bid-Offer Acceptances or
Emergency Instructions it is issuing to Embedded Genset(s) within the Network
Operators User System forming part of the De-Synchronised Island.

Issue 5 Revision 16 OC9 24 May 2016


13 of 18
OC9.5.2.2 Direct Data
(a) NGET will issue an Emergency Instruction and/or a Bid-Offer Acceptance, to the
Generator to "float" local Demand and maintain Frequency at Target Frequency.
Under this the Generator will be required to regulate the output of its Genset(s) at the
Power Station in question to the Demand prevailing in the De-Synchronised Island in
which it is situated, until Re-Synchronisation takes place, on the basis that it will
(where practicable) seek to maintain the Target Frequency.
(b) The Network Operator is required to be in contact with the Generator at the Power
Station to supply data on Demand changes within the De-Synchronised Island.
(c) If more than one Genset is Synchronised on the De-Synchronised Island, or is
connected to the De-Synchronised Island and available to generate although not
Synchronised, the Network Operator will need to liaise with NGET to agree which
Genset(s) will be utilised to accommodate changes in Demand in the De-
Synchronised Island. The Network Operator will then maintain contact with the
relevant Generator (or Generators) in relation to that Genset(s).
(d) The Generator at the Power Station must contact the Network Operator if the level of
Demand which it has been asked to meet as a result of the Emergency Instruction
and/or Bid-Offer Acceptance to "float" and the detail on Demand passed on by the
Network Operator, is likely to cause problems for safety reasons (whether relating to
personnel or Plant and/or Apparatus) in the operation of its Genset(s), in order that the
Network Operator can alter the level of Demand which that Generator needs to meet.
Any decision to operate outside any relevant parameters is one entirely for the
Generator.
OC9.5.2.3 Control Features
(a) A system may be established in relation to a part of the National Electricity
Transmission System and a Network Operators User System, if agreed between
NGET and the Network Operator and any relevant Generator(s), whereby upon a
defined fault(s) occurring, manual or automatic control features will operate to protect
the National Electricity Transmission System and relevant Network Operators User
System and Genset(s) and simplify the restoration of Demand in the De-
Synchronised Island.
(b) In agreeing the establishment of such a system of control features NGET will need to
consider its impact on the operation of the National Electricity Transmission System.
OC9.5.2.4 Absence of Control Features System
If a system of control features under OC9.5.2.3 has not been agreed as part of an OC9 De-
Synchronised Island Procedure under OC9.5.4 below, NGET may choose to utilise the
procedures set out in OC9.5.2.1 or OC9.5.2.2, or may instruct the Genset(s) (or some of
them) in the De-Synchronised Island to De-Synchronise.
OC9.5.3 Choice Of Option
In relation to each of the methods set out in OC9.5.2, where a De-Synchronised Island has
come into existence and where an OC9 De-Synchronised Island Procedure under OC9.5.4
has been agreed, NGET, the Network Operator and relevant Generator(s) will operate in
accordance with that OC9 De-Synchronised Islands Procedure unless NGET considers
that the nature of the De-Synchronised Island situation is such that either:-
(i) the OC9 De-Synchronised Island Procedure does not cover the situation; or
(ii) the provisions of the OC9 De-Synchronised Island Procedure are not appropriate,
in which case NGET will instruct the relevant Users and the Users will comply with NGET's
instructions (which in the case of Generators will relate to generation and in the case of
Network Operators will relate to Demand).

Issue 5 Revision 16 OC9 24 May 2016


14 of 18
OC9.5.4 Agreeing Procedures
In relation to each relevant part of the Total System, NGET, the Network Operator and the
relevant Generator will discuss and may agree a local procedure (an "OC9 De-
Synchronised Island Procedure").
OC9.5.4.1 Where there is no relevant local procedure in place at 12th May 1997, or in the case where
the need for an OC9 De-Synchronised Island Procedure arises for the first time, the
following provisions shall apply:
(a) NGET, the Network Operator(s) and the relevant Generator(s) will discuss the need
for, and the detail of, the OC9 De-Synchronised Island Procedure. As soon as the
need for an OC9 De-Synchronised Island Procedure is identified by NGET or a User,
and the party which identifies such a need will notify all affected Users (and NGET, if
that party is a User), and NGET will initiate these discussions.
(b) Each OC9 De-Synchronised Island Procedure will be in relation to a specific Grid
Supply Point, but if there is more than one Grid Supply Point between NGET and the
Network Operator then the OC9 De-Synchronised Island Procedure may cover all
relevant Grid Supply Points. In Scotland, the OC9 De-Synchronised Island
Procedure may also cover parts of the National Electricity Transmission System
connected to the Users System(s) and Power Stations directly connected to the
National Electricity Transmission System which are also likely to form part of the
Power Island.
(c) The OC9 De-Synchronised Island Procedure will:
(i) record which Users and which User Sites are covered by the OC9 De-
Synchronised Island Procedure;
(ii) record which of the three methods set out in OC9.5 (or combination of the three)
shall apply, with any conditions as to applicability being set out as well;
(iii) set out what is required from NGET and each User should a De-Synchronised
Island arise;
(iv) set out what action should be taken if the OC9 De-Synchronised Island
Procedure does not cover a particular set of circumstances and will reflect that in
the absence of any specified action, the provisions of OC9.5.3 will apply;
(v) in respect of Scottish Transmission Systems, the OC9 De-Synchronised Island
Procedure may be produced with and include obligations on the Relevant
Scottish Transmission Licensee(s) ; and
(vi) in respect of Scottish Transmission Systems, where the OC9 De-Synchronised
Island Procedure includes the establishment of a De-synchronised Island,
describe the route for establishment of the De-Synchronised Island.
(d) Each OC9 De-Synchronised Island Procedure shall be prepared by NGET to reflect
the above discussions.
(e) Each page of the OC9 De-Synchronised Island Procedure shall bear a date of issue
and the issue number.
(f) When an OC9 De-Synchronised Island Procedure is prepared, it shall be sent by
NGET to the Users involved for confirmation of its accuracy.
(g) The OC9 De-Synchronised Island Procedure shall then be signed on behalf of NGET
and on behalf of each relevant User by way of written confirmation of its accuracy.
(h) Once agreed under this OC9.5.4.1, the procedure will become an OC9 De-
Synchronised Island Procedure under the Grid Code and (subject to any change
pursuant to this OC9) will apply between NGET, Relevant Transmission Licensee and
the relevant Users as if it were part of the Grid Code.
(i) Once signed, a copy will be distributed by NGET to each User which is a party
accompanied by a note indicating the issue number and the date of implementation.
Issue 5 Revision 16 OC9 24 May 2016
15 of 18
(j) NGET and Users must make the OC9 De-Synchronised Island Procedure readily
available to the relevant operational staff.
(k) If a new User connects to the Total System and needs to be included with an existing
OC9 De-Synchronised Island Procedure, NGET will initiate a discussion with that
User and the Users which are parties to the relevant OC9 De-Synchronised Island
Procedure. The principles applying to a new OC9 De-Synchronised Island
Procedure under this OC9.5.4.1 shall apply to such discussions and to any consequent
changes.
(l) If NGET, or any User which is a party to an OC9 De-Synchronised Island Procedure,
becomes aware that a change is needed to that OC9 De-Synchronised Island
Procedure, it shall (in the case of NGET) initiate a discussion between NGET and the
relevant Users to seek to agree the relevant change. The principles applying to
establishing a new OC9 De-Synchronised Island Procedure under this OC9.5.4.1
shall apply to such discussions and to any consequent changes. If a User becomes so
aware, it shall contact NGET who will then initiate such discussions.
(m) If in relation to any discussions, agreement cannot be reached between NGET and the
relevant Users, NGET will operate the System on the basis that it will discuss which of
the three methods set out in OC9.5.2.1 to OC9.5.2.3 would be most appropriate at the
time, if practicable. The complexities and uncertainties of recovery from a De-
Synchronised Island means that NGET will decide, having discussed the situation with
the relevant Users and taking into account the fact that the three methods may not
cover the situation or be appropriate, the approach which is to be followed. NGET will
instruct the relevant Users and the Users will comply with NGET's instructions as
provided in OC9.5.3.
OC9.5.4.2 Where there is a relevant local procedure in place at 12th May 1997, the following provisions
shall apply:
(a) NGET and the Network Operator and the relevant Generator(s) will discuss the
existing procedure to see whether it is consistent with the principles set out in this
OC9.5.
(b) If it is, then it shall become an OC9 De-Synchronised Island Procedure under this
OC9, and the relevant provisions of OC9.5.4.1 shall apply.
(c) If it is not, then the parties will discuss what changes are needed to ensure that it is
consistent, and once agreed the procedure will become an OC9 De-Synchronised
Island Procedure under this OC9, and the relevant provisions of OC9.5.4.1 shall apply.
(d) If agreement cannot be reached between NGET and the relevant Users after a
reasonable period of time, the existing procedure will cease to apply and NGET will
operate the System on the basis that it will discuss which of the three methods set out in
OC9.5.2.1 to OC9.5.2.3 would be most appropriate at the time, if practicable. The
complexities and uncertainties of recovery from a De-Synchronised Island means that
NGET will decide, having discussed the situation with the relevant Users and taking into
account the fact that the three methods may not cover the situation or be appropriate,
the approach which is to be followed. NGET will instruct the relevant Users and the
Users will comply with NGET's instructions as provided in OC9.5.3.
OC9.5.5 Where the National Electricity Transmission System is Out of Synchronism with the
Transmission System of an Externally Interconnected System Operator, NGET will,
pursuant to the Interconnection Agreement with that Externally Interconnected System
Operator, agree with that Externally Interconnected System Operator when its
Transmission System can be Re-Synchronised to the National Electricity Transmission
System.

OC9.5.6 Further requirements regarding Re-synchronisation of De-synchronised Islands following


any Total Shutdown or Partial Shutdown

Issue 5 Revision 16 OC9 24 May 2016


16 of 18
Following any Total Shutdown or Partial Shutdown NGET expects that it will be necessary
to interconnect Power Islands utilising the provisions of OC9.5. The complexities and
uncertainties of recovery from a Total Shutdown or Partial Shutdown requires the
provisions of OC9.5 to be flexible, however, the strategies which NGET will, where
practicable, be seeking to follow when Re-synchronising De-synchronised Islands
following any Total Shutdown or Partial Shutdown, include the following:
(a) the provision of supplies to appropriate Power Stations to facilitate their synchronisation
as soon as practicable;
(b) energisation of a skeletal National Electricity Transmission System;
(c) the strategic restoration of Demand in co-ordination with relevant Network Operators.
As highlighted in OC9.4.3, during a Total Shutdown or Partial Shutdown and during the
subsequent recovery, which includes any period during which the procedures in this OC9.5
apply, the Licence Standards may not apply and the Total System may be operated
outside normal voltage and Frequency standards.
OC9.5.7 To manage effectively and co-ordination the restoration strategies of the Total System (any
Re-Synchronisation of De-Synchronised Islands) following any Total Shutdown or
Partial Shutdown, requires NGET and relevant Users to undertake certain planning
activities as set out below:
(a) NGET and Network Operators shall review on a regular basis the processes by which
each Power Island will be interconnected. This is likely to cover an exchange of
information regarding the typical size, location and timing requirements for Demand to
be reconnected and also include details (ability to change/disable) of the low frequency
trip relay settings of the Demand identified.
(b) Each Generator shall provide to NGET information to assist NGET in the formulation of
the restoration strategies of Power Island expansion. This information shall be
provided in accordance with PC.A.5.7.
OC9.6 JOINT SYSTEM INCIDENT PROCEDURE
OC9.6.1 A "Joint System Incident" is
(a) an Event, wherever occurring (other than on an Embedded Small Power Station or
Embedded Medium Power Station), which, in the opinion of NGET or a User, has or
may have a serious and/or widespread effect.
(b) In the case of an Event on a User(s) System(s) (other than on an Embedded Small
Power Station or Embedded Medium Power Station), the effect must be on the
National Electricity Transmission System, and in the case of an Event on the
National Electricity Transmission System, the effect must be on a User(s)
System(s) (other than on an Embedded Small Power Station or Embedded Medium
Power Station).
Where an Event on a User(s) System(s) has or may have no effect on the National
Electricity Transmission System, then such an Event does not fall within OC9 and
accordingly OC9 shall not apply to it.
OC9.6.2 (a) (i) Each User (other than Generators which only have Embedded Small Power
Stations and/or Embedded Medium Power Stations) will provide in writing to
NGET, and
(ii) NGET will provide in writing to each User (other than Generators which only have
Embedded Small Power Stations and/or Embedded Medium Power Stations),
a telephone number or numbers at which, or through which, senior management
representatives nominated for this purpose and who are fully authorised to make
binding decisions on behalf of NGET or the relevant User, as the case may be, can
be contacted day or night when there is a Joint System Incident.

Issue 5 Revision 16 OC9 24 May 2016


17 of 18
(b) The lists of telephone numbers will be provided in accordance with the timing
requirements of the Bilateral Agreement and/or Construction Agreement with that
User, prior to the time that a User connects to the National Electricity Transmission
System and must be up-dated (in writing) as often as the information contained in them
changes.
OC9.6.3 Following notification of an Event under OC7, NGET or a User, as the case may be, will, if it
considers necessary, telephone the User or NGET, as the case may be, on the telephone
number referred to in OC9.6.2, to obtain such additional information as it requires.
OC9.6.4 Following notification of an Event under OC7, and/or the receipt of any additional information
requested pursuant to OC9.6.3, NGET or a User, as the case may be, will determine whether
or not the Event is a Joint System Incident, and, if so, NGET and/or the User may set up
an Incident Centre in order to avoid overloading the existing NGET or that User's, as the
case may be, operational/control arrangements.
OC9.6.5 Where NGET has determined that an Event is a Joint System Incident, NGET shall, as
soon as possible, notify all relevant Users that a Joint System Incident has occurred and, if
appropriate, that it has established an Incident Centre and the telephone number(s) of its
Incident Centre if different from those already supplied pursuant to OC9.6.2.
OC9.6.6 If a User establishes an Incident Centre it shall, as soon as possible, notify NGET that it has
been established and the telephone number(s) of the Incident Centre if different from those
already supplied pursuant to OC9.6.2.
OC9.6.7 NGET's Incident Centre and/or the User's Incident Centre will not assume any
responsibility for the operation of the National Electricity Transmission System or User's
System, as the case may be, but will be the focal point in NGET or the User, as the case
may be, for:
(a) the communication and dissemination of information between NGET and the senior
management representatives of User(s); or
(b) between the User and the senior management representatives of NGET, as the case
may be,
relating to the Joint System Incident. The term "Incident Centre" does not imply a
specially built centre for dealing with Joint System Incidents, but is a communications focal
point. During a Joint System Incident, the normal communication channels, for
operational/control communication between NGET and Users will continue to be used.
OC9.6.8 All communications between the senior management representatives of the relevant parties
with regard to NGET's role in the Joint System Incident shall be made via NGET's Incident
Centre if it has been established.
OC9.6.9 All communications between the senior management representatives of NGET and a User
with regard to that User's role in the Joint System Incident shall be made via that User's
Incident Centre if it has been established.
OC9.6.10 NGET will decide when conditions no longer justify the need to use its Incident Centre and
will inform all relevant Users of this decision.
OC9.6.11 Each User which has established an Incident Centre will decide when conditions no longer
justify the need to use that Incident Centre and will inform NGET of this decision.

< END OF OPERATING CODE NO. 9 >

Issue 5 Revision 16 OC9 24 May 2016


18 of 18
OPERATING CODE NO. 10
(OC10)

EVENT INFORMATION SUPPLY

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC10.1 INTRODUCTION.................................................................................................................................2
OC10.2 OBJECTIVE ........................................................................................................................................2
OC10.3 SCOPE................................................................................................................................................2
OC10.4 PROCEDURE .....................................................................................................................................2
OC10.4.1 Reporting ..................................................................................................................................2
OC10.4.2 Joint Investigations ...................................................................................................................3
APPENDIX 1 - MATTERS TO BE INCLUDED IN A WRITTEN REPORT..........................................................5

Issue 5 Revision 0 OC10 17 August 2012


i
OC10.1 INTRODUCTION
OC10.1.1. Operating Code No.10 ("OC10") sets out:
OC10.1.1.1 the requirements for the reporting in writing and, where appropriate, more fully, those Significant
Incidents which were initially reported to NGET or a User orally under OC7; and
OC10.1.1.2 the mechanism for the joint investigation of a Significant Incident or a series of Significant
Incidents if NGET and the relevant Users agree.

OC10.2 OBJECTIVE
The objective of OC10 is to facilitate the provision of more detailed information, in writing, of
Significant Incidents which were initially orally reported under OC7 and to enable joint
investigations to take place if NGET and the relevant Users agree.

OC10.3 SCOPE
OC10.3.1 OC10 applies to NGET and to Users, which in OC10 means:-
(a) Generators (other than those which only have Embedded Small Power Stations and/or
Embedded Medium Power Stations);
(b) Network Operators;
(c) Non-Embedded Customers; and
(d) DC Converter Station owners.
The procedure for Event information supply between NGET and Externally Interconnected
System Operators is set out in the Interconnection Agreement with each Externally
Interconnected System Operator.

OC10.4 PROCEDURE
OC10.4.1 Reporting
OC10.4.1.1 Written Reporting Of Events By Users To NGET
In the case of an Event which was initially reported by a User to NGET orally and subsequently
determined by NGET to be a Significant Incident, and accordingly notified by NGET to a User
pursuant to OC7, the User will give a written report to NGET, in accordance with OC10. NGET
will not pass on this report to other affected Users but may use the information contained therein
in preparing a report under OC10 to another User (or in a report which NGET is required to
submit under an Interconnection Agreement) in relation to a Significant Incident (or its
equivalent under an Interconnection Agreement or STC) on the National Electricity
Transmission System which has been caused by (or exacerbated by) the Significant Incident
on the User's System.
OC10.4.1.2 Written Reporting Of Events By NGET To Users
In the case of an Event which was initially reported by NGET to a User orally and subsequently
determined by the User to be a Significant Incident, and accordingly notified by the User to
NGET pursuant to OC7, NGET will give a written report to the User, in accordance with OC10.
The User will not pass on the report to other affected Users but:

Issue 5 Revision 0 0C10 17 August 2012


2 of 5
(a) a Network Operator may use the information contained therein in preparing a written report
to a Generator with a Generating Unit or a Power Park Module connected to its System
or to a DC Converter Station owner with a DC Converter connected to its System or to
another operator of a User System connected to its System in connection with reporting
the equivalent of a Significant Incident under the Distribution Code (or other contract
pursuant to which that Generating Unit or that Power Park Module or that DC Converter
or User System is connected to its System) (if the Significant Incident on the National
Electricity Transmission System caused or exacerbated it); and
(b) a Generator may use the information contained therein in preparing a written report to
another Generator with a Generating Unit or a Power Park Module connected to its
System or to the operator of a User System connected to its System if it is required (by a
contract pursuant to which that Generating Unit or a Power Park Module or that is
connected to its System) to do so in connection with the equivalent of a Significant
Incident on its System (if the Significant Incident on the National Electricity
Transmission System caused or exacerbated it).
OC10.4.1.3 Form
A report under OC10.4.1 shall be sent to NGET or to a User, as the case may be, and will
contain a confirmation of the oral notification given under OC7 together with more details relating
to the Significant Incident although it (and any response to any question asked) need not state
the cause of the Event save to the extent permitted under OC7.4.6.7 and OC7.4.6.9, and such
further information which has become known relating to the Significant Incident since the oral
notification under OC7. The report should, as a minimum, contain those matters specified in the
Appendix to OC10. The Appendix is not intended to be exhaustive. NGET or the User, as the
case may be, may raise questions to clarify the notification and the giver of the notification will, in
so far as it is able, answer any questions raised.
OC10.4.1.4 Timing
A full written report under OC10.4.1 must, if possible, be received by NGET or the User, as the
case may be, within 2 hours of NGET or the User, as the case may be, receiving oral notification
under OC7. If this is not possible, the User or NGET, as the case may be, shall, within this
period, submit a preliminary report setting out, as a minimum, those matters specified in the
Appendix to OC10. As soon as reasonably practical thereafter, the User or NGET, as the case
may be, shall submit a full written report containing the information set out in OC10.4.1.3.
OC10.4.2 Joint Investigations
OC10.4.2.1 Where a Significant Incident (or series of Significant Incidents) has been declared and a
report (or reports) under OC10 submitted, NGET or a User which has either given or received a
written report under OC10 may request that a joint investigation of a Significant Incident should
take place.
OC10.4.2.2 Where there has been a series of Significant Incidents (that is to say, where a Significant
Incident has caused or exacerbated another Significant Incident) the party requesting a joint
investigation or the recipient of such a request, may request that the joint investigation should
include an investigation into that other Significant Incident (or Significant Incidents).
OC10.4.2.3 NGET or a User may also request that:
(i) an Externally Interconnected System Operator and/or
(ii) Interconnector User or
(iii) (in the case of a Network Operator) a Generator with a Generating Unit or a Power Park
Module or a DC Converter Station owner with DC Converter connected to its System or
another User System connected to its System or
(iv) (in the case of a Generator) another Generator with a Generating Unit or a Power Park
Module connected to its System or a User System connected to its System.
be included in the joint investigation.

Issue 5 Revision 0 0C10 17 August 2012


3 of 5
OC10.4.2.4 A joint investigation will only take place if NGET and the User or Users involved agree to it
(including agreement on the involvement of other parties referred to in OC10.4.2.3). The form
and rules of, the procedure for, and all matters (including, if thought appropriate, provisions for
costs and for a party to withdraw from the joint investigation once it has begun) relating to the
joint investigation will be agreed at the time of a joint investigation and in the absence of
agreement the joint investigation will not take place.
OC10.4.2.5 Requests relating to a proposed joint investigation will be in writing.
OC10.4.2.6 Any joint investigation under OC10 is separate to any investigation under the Disputes
Resolution Procedure.

Issue 5 Revision 0 0C10 17 August 2012


4 of 5
APPENDIX 1 - MATTERS TO BE INCLUDED IN A WRITTEN REPORT

MATTERS, IF APPLICABLE TO THE SIGNIFICANT INCIDENT AND TO THE RELEVANT USER (OR
NGET, AS THE CASE MAY BE) TO BE INCLUDED IN A WRITTEN REPORT GIVEN IN ACCORDANCE
WITH OC10.4.1 AND OC10.4.2

1. Time and date of Significant Incident.

2. Location.

3. Plant and/or Apparatus directly involved (and not merely affected by the Event).

4. Description of Significant Incident.

5. Demand (in MW) and/or generation (in MW) interrupted and duration of interruption.

6. Generating Unit, Power Park Module or DC Converter - Frequency response (MW


correction achieved subsequent to the Significant Incident).

7. Generating Unit, Power Park Module or DC Converter - MVAr performance (change in


output subsequent to the Significant Incident).

8. Estimated time and date of return to service.

< END OF OPERATING CODE NO. 10 >

Issue 5 Revision 0 0C10 17 August 2012


5 of 5
OPERATING CODE NO. 11
(OC11)

NUMBERING AND NOMENCLATURE OF


HIGH VOLTAGE APPARATUS AT CERTAIN SITES

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC11.1 INTRODUCTION.................................................................................................................................2
OC11.2 OBJECTIVE ........................................................................................................................................2
OC11.3 SCOPE................................................................................................................................................2
OC11.4 PROCEDURE .....................................................................................................................................2
OC11.4.2 Transmission HV Apparatus Or OTSDUW HV Apparatus On Users' Sites..............................3
OC11.4.3 User HV Apparatus Or OTSDUW HV Apparatus On Transmission Sites ................................3
OC11.4.4 Changes ...................................................................................................................................4

Issue 5 Revision 0 OC11 17 August 2012


i
OC11.1 INTRODUCTION
OC11.1.1 Operating Code No.11 ("OC11") sets out the requirement that:
(a) Transmission HV Apparatus on Users' Sites; and
(b) User HV Apparatus on Transmission Sites; and
(c) OTSDUW HV Apparatus on both Users Sites and the Transmission Sites;
shall have numbering and nomenclature in accordance with the system used from time to
time by NGET.
OC11.1.2 The numbering and nomenclature (if required under the system of numbering and
nomenclature used from time to time by NGET) of each item of HV Apparatus shall be
included in the Operation Diagram prepared for each Transmission Site or User Site, as
the case may be. Further provisions on Operation Diagrams are contained in the
Connection Conditions and in each Bilateral Agreement.
OC11.1.3 In OC11 the term "HV Apparatus" includes any SF6 Gas Zones associated with any HV
Apparatus.
OC11.1.4 In OC11 the term "OTSDUW HV Apparatus" applies to any HV Apparatus installed by a
User as OTSDUW until it is accepted on to the National Electricity Transmission System
at which time for the purposes of OC11 it will be termed Transmission HV Apparatus.

OC11.2 OBJECTIVE
OC11.2.1 The overall objective of OC11 is to ensure, so far as possible, the safe and effective
operation of the Total System and to reduce the risk of human error faults by requiring, in
certain circumstances, that the numbering and nomenclature of User's HV Apparatus and
OTSDUW HV Apparatus shall be in accordance with the system used from time to time by
NGET.

OC11.3 SCOPE
OC11.3.1 OC11 applies to NGET and to Users, which in OC11 means:-
(a) Generators;
(b) Generators undertaking OTSDUW;
(c) Network Operators;
(d) Non-Embedded Customers; and
(e) DC Converter Station owners.

OC11.4 PROCEDURE
OC11.4.1.1 The term "User Site" means a site owned (or occupied pursuant to a lease, licence or other
agreement) by a User in which there is a Connection Point (and in the case of OTSDUW,
where there is a Connection Point or an Interface Point). For the avoidance of doubt,
where a site is owned by NGET (in England and Wales) or a Relevant Transmission
Licensee (in Scotland or Offshore) but occupied by a User (as aforesaid), the site is a User
Site.
OC11.4.1.2 The term "Transmission Site" means a site owned (or occupied pursuant to a lease, licence
or other agreement) by NGET (in England and Wales) or by a Relevant Transmission
Licensee (in Scotland or Offshore) in which there is a Connection Point (or in the case of
OTSDUW, an Interface Point). For the avoidance of doubt, where a site is owned by a User
but occupied by NGET (in England and Wales) or a Relevant Transmission Licensee (in
Scotland or Offshore)(as aforesaid), the site is an Transmission Site.

Issue 5 Revision 0 OC11 17 August 2012


2 of 4
OC11.4.2 Transmission HV Apparatus Or OTSDUW HV Apparatus On Users' Sites
(a) Transmission HV Apparatus or OTSDUW HV Apparatus on Users' Sites shall have
numbering and nomenclature in accordance with the system used from time to time by
NGET;
(b) when NGET (for sites in England and Wales) or the Relevant Transmission Licensee
(for sites in Scotland or Offshore) is to install its HV Apparatus on a User's Site, NGET
shall (unless it gives rise to a Modification under the CUSC, in which case the
provisions of the CUSC as to the timing apply) notify the relevant User of the numbering
and nomenclature to be adopted for that HV Apparatus at least eight months prior to
proposed installation. When OTSDUW HV Apparatus is to be installed on a Users
Site NGET shall notify the relevant User of the numbering and nomenclature to be
adopted for that OTSDUW HV Apparatus at least eight months prior to proposed
installation;
(c) in the case of HV Apparatus, the notification will be made in writing to the relevant User
and will consist of both a proposed Operation Diagram incorporating the proposed new
Transmission HV Apparatus to be installed, its proposed numbering and
nomenclature, and the date of its proposed installation. In the case of OTSDUW HV
Apparatus, the notification will be provided as part of the OTSDUW Network Data and
Information;
(d) the relevant User will respond in writing to NGET within one month of the receipt of the
notification, confirming receipt and confirming either that any other HV Apparatus of the
relevant User on such User Site does not have numbering and/or nomenclature which
could be confused with that proposed by NGET, or, to the extent that it does, that the
relevant other numbering and/or nomenclature will be changed before installation of the
Transmission HV Apparatus or OTSDUW HV Apparatus;
(e) the relevant User will not install, or permit the installation of, any HV Apparatus,
including OTSDUW HV Apparatus on such User Site which has numbering and/or
nomenclature which could be confused with Transmission HV Apparatus which is
either already on that User Site or which NGET has notified that User will be installed
on that User Site.
OC11.4.3 User HV Apparatus Or OTSDUW HV Apparatus On Transmission Sites
(a) User HV Apparatus and any OTSDUW HV Apparatus on Transmission Sites shall
have numbering and nomenclature in accordance with the system used from time to time
by NGET;
(b) when a User is to install its HV Apparatus on an Transmission Site, or it wishes to
replace existing HV Apparatus on an Transmission Site and it wishes to adopt new
numbering and nomenclature for such HV Apparatus, the User shall (unless it gives rise
to a Modification under the CUSC in which case the provisions of the CUSC as to the
timing apply) notify NGET of the details of the HV Apparatus and the proposed
numbering and nomenclature to be adopted for that HV Apparatus, at least eight
months prior to proposed installation;
(c) the notification will be made in writing to NGET and shall consist of both a proposed
Operation Diagram incorporating the proposed new HV Apparatus of the User to be
installed, its proposed numbering and nomenclature, and the date of its proposed
installation;
(d) NGET will respond in writing to the User within one month of the receipt of the
notification stating whether or not NGET accepts the User's proposed numbering and
nomenclature and, if they are not acceptable, it shall give details of the numbering and
nomenclature which the User shall adopt for that HV Apparatus;

Issue 5 Revision 0 OC11 17 August 2012


3 of 4
(e) when a User is to install OTSDUW HV Apparatus on a Transmission Site, NGET
notify the relevant User of the numbering and nomenclature to be adopted for that HV
Apparatus at least eight months prior to proposed installation. This notification will be
provided as part of the OTSDUW Network Data and Information.
OC11.4.4 Changes
Where NGET in its reasonable opinion has decided that it needs to change the existing
numbering or nomenclature of Transmission HV Apparatus on a User's Site or of User's
HV Apparatus on an Transmission Site:
(a) the provisions of paragraph OC11.4.2 shall apply to such change of numbering or
nomenclature of Transmission HV Apparatus with any necessary amendments to
those provisions to reflect that only a change is being made; and
(b) in the case of a change in the numbering or nomenclature of User's HV Apparatus on
an Transmission Site, NGET will (unless it gives rise to a Modification under the
CUSC, in which case the provisions of the CUSC as to the timing apply) notify the User
of the numbering and/or nomenclature the User shall adopt for that HV Apparatus (the
notification to be in a form similar to that envisaged under OC11.4.2) at least eight
months prior to the change being needed and the User will respond in writing to NGET
within one month of the receipt of the notification, confirming receipt.
In either case the notification shall indicate the reason for the proposed change.
OC11.4.5 Users will be provided upon request with details of NGET's then current numbering and
nomenclature system in order to assist them in planning the numbering and nomenclature for
their HV Apparatus or OTSDUW HV Apparatus on Transmission Sites and OTSDUW HV
Apparatus on Users Sites.
OC11.4.6 When a User installs HV Apparatus or OTSDUW HV Apparatus which is the subject of
OC11, the User shall be responsible for the provision and erection of clear and unambiguous
labelling showing the numbering and nomenclature. Where a User is required by OC11 to
change the numbering and/or nomenclature of HV Apparatus which is the subject of OC11,
the User will be responsible for the provision and erection of clear and unambiguous labelling
by the required date.
When either NGET (for sites in England and Wales), or a Relevant Transmission Licensee
(for sites in Scotland or Offshore) installs HV Apparatus which is the subject of OC11,
NGET shall be responsible for the provision and erection of a clear and unambiguous
labelling showing the numbering and nomenclature. Where NGET changes the numbering
and /or nomenclature of HV Apparatus which is the subject of OC11, NGET will be
responsible for the provision and erection of clear and unambiguous labelling showing the
numbering and nomenclature by the required date.
OC11.4.7 For sites in England and Wales, NGET will not change its system of numbering and
nomenclature in use immediately prior to the Transfer Date (which is embodied in OM5
(Operation Memorandum No.5 - Numbering and Nomenclature of HV Apparatus on the
CEGB Grid System Issue 3 June 1987)), other than to reflect new or newly adopted
technology or HV Apparatus. For the avoidance of doubt, this OC11.4.7 refers to the system
of numbering and nomenclature, and does not preclude changes to the numbering and/or
nomenclature of HV Apparatus which are necessary to reflect newly installed HV
Apparatus, or re-configuration of HV Apparatus installed, and similar changes being made
in accordance with that system of numbering and nomenclature.

< END OF OPERATING CODE NO. 11 >

Issue 5 Revision 0 OC11 17 August 2012


4 of 4
OPERATING CODE NO. 12
(OC12)

SYSTEM TESTS

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


OC12.1 INTRODUCTION...................................................................................................................................2
OC12.2 OBJECTIVE ..........................................................................................................................................2
OC12.3 SCOPE..................................................................................................................................................2
OC12.4 PROCEDURE .......................................................................................................................................3
OC12.4.1 Proposal Notice ..........................................................................................................................3
OC12.4.2 Preliminary Notice And Establishment Of Test Panel.................................................................3
OC12.4.3 Test Panel...................................................................................................................................4
OC12.4.4 Proposal Report..........................................................................................................................5
OC12.4.5 Test Programme .........................................................................................................................6
OC12.4.6 Final Report ................................................................................................................................6
OC12.4.7 Timetable Reduction...................................................................................................................6

Issue 5 Revision 0 OC12 17 August 2012


i
OC12.1 INTRODUCTION
OC12.1.1 Operating Code No.12 ("OC12") relates to System Tests, which are tests which involve
simulating conditions or the controlled application of irregular, unusual or extreme conditions, on
the Total System or any part of the Total System, but which do not include commissioning or
recommissioning tests or any other tests of a minor nature.
OC12.1.2 OC12 deals with the responsibilities and procedures for arranging and carrying out System
Tests which have (or may have) an effect on the Systems of NGET and Users and/or on the
System of any Externally Interconnected System Operator. Where a System Test proposed
by a User will have no effect on the National Electricity Transmission System, then such a
System Test does not fall within OC12 and accordingly OC12 shall not apply to it. A System
Test proposed by NGET which will have an effect on the System of a User will always fall within
OC12.

OC12.2 OBJECTIVE
The overall objectives of OC12 are:
OC12.2.1 to ensure, so far as possible, that System Tests proposed to be carried out either by:
(a) a User (or certain persons in respect of Systems Embedded within a Network Operators
System) which may have an effect on the Total System or any part of the Total System (in
addition to that User's System) including the National Electricity Transmission System;
or
(b) by NGET which may have an effect on the Total System or any part of the Total System
(in addition to the National Electricity Transmission System)
do not threaten the safety of either their personnel or the general public, cause minimum threat to
the security of supplies and to the integrity of Plant and/or Apparatus, and cause minimum
detriment to NGET and Users;
OC12.2.2 to set out the procedures to be followed for establishing and reporting System Tests.

OC12.3 SCOPE
OC12 applies to NGET and to Users, which in OC12 means:-
(a) Generators other than in respect of Embedded Medium Power Stations and Embedded
Small Power Stations (and the term Generator in OC12 shall be constructed accordingly);
(b) Network Operators;
(c) Non-Embedded Customers; and
(d) DC Converter Station owners other than in respect of Embedded DC Converter
Stations.
The procedure for the establishment of System Tests on the National Electricity Transmission
System, with Externally Interconnected System Operators which do not affect any User, is
set out in the Interconnection Agreement with each Externally Interconnected System
Operator. The position of Externally Interconnected System Operators and Interconnector
Users is also referred to in OC12.4.2.
OC12.3.2 Each Network Operator will liaise within NGET as necessary in those instances where an
Embedded Person intends to perform a System Test which may have an effect on the Total
System or any part of the Total System (in addition to that Generators or other Users
System) including the National Electricity Transmission System. NGET is not required to deal
with such persons.
OC12.3.3 Each Network Operator shall be responsible for co-ordinating with the Embedded Person or such
other person and assessing the effect ofany System Tests upon:

Issue 5 Revision 0 OC12 17 August 2012


2 of 6
(a) any Embedded Medium Power Station, Embedded Small Power Stations or
Embedded DC Converter Station within the Network Operators System; or
(b) any other User connected to or within the Network Operators System.
NGET is not required to deal with such persons.

OC12.4 PROCEDURE
OC12.4.1 Proposal Notice
OC12.4.1.1 Where a User (or in the case of a Network Operator, a person in respect of Systems
Embedded within its System, as the case may be) has decided that it would like to undertake a
System Test it shall submit a notice (a "Proposal Notice) to NGET at least twelve months in
advance of the date it would like to undertake the proposed System Test.
OC12.4.1.2 The Proposal Notice shall be in writing and shall contain details of the nature and purpose of the
proposed System Test and shall indicate the extent and situation of the Plant and/or Apparatus
involved.
OC12.4.1.3 If NGET is of the view that the information set out in the Proposal Notice is insufficient, it will
contact the person who submitted the Proposal Notice (the "Test Proposer") as soon as
reasonably practicable, with a written request for further information. NGET will not be required
to do anything under OC12 until it is satisfied with the details supplied in the Proposal Notice or
pursuant to a request for further information.
OC12.4.1.4 If NGET wishes to undertake a System Test, NGET shall be deemed to have received a
Proposal Notice on that System Test
OC12.4.1.5 Where, under OC12, NGET is obliged to notify or contact the Test Proposer, NGET will not be
so obliged where it is NGET that has proposed the System Test. Users and the Test Panel,
where they are obliged under OC12 to notify, send reports to or otherwise contact both NGET
and the Test Proposer, need only do so once where NGET is the proposer of the System Test.
OC12.4.2 Preliminary Notice And Establishment Of Test Panel
OC12.4.2.1 Using the information supplied to it under OC12.4.1 NGET will determine, in its reasonable
estimation, which Users, other than the Test Proposer, may be affected by the proposed
System Test. If NGET determines, in its reasonable estimation, that an Externally
Interconnected System Operator and/or Interconnector User (or Externally Interconnected
System Operators and/or Interconnector Users) may be affected by the proposed System
Test, then (provided that the Externally Interconnected System Operator and/or
Interconnector User (or each Externally Interconnected System Operator and/or
Interconnector User where there is more than one affected) undertakes to all the parties to the
Grid Code to be bound by the provisions of the Grid Code for the purposes of the System Test)
for the purposes of the remaining provisions of this OC12, that Externally Interconnected
System Operator and/or Interconnector User (or each of those Externally Interconnected
System Operators and/or Interconnector Users) will be deemed to be a User and references
to the Total System or to the Plant and/or Apparatus of a User will be deemed to include a
reference to the Transmission or distribution System and Plant and/or Apparatus of that
Externally Interconnected System Operator and/or Interconnector User or (as the case may
be) those Externally Interconnected System Operators and/or Interconnector Users. In the
event that the Externally Interconnected System Operator and/or Interconnector User (or
any of the Externally Interconnected System Operators and/or Interconnector Users where
there is more than one affected) refuses to so undertake, then the System Test will not take
place.
OC12.4.2.2 NGET will appoint a person to co-ordinate the System Test (a "Test Co-ordinator") as soon as
reasonably practicable after it has, or is deemed to have, received a Proposal Notice and in any
event prior to the distribution of the Preliminary Notice referred to below. The Test Co-
ordinator shall act as Chairman of the Test Panel and shall be an ex-officio member of the Test
Panel.
Issue 5 Revision 0 OC12 17 August 2012
3 of 6
(a) Where NGET decides, in its reasonable opinion, that the National Electricity
Transmission System will or may be significantly affected by the proposed System Test,
then the Test Co-ordinator will be a suitably qualified person nominated by NGET after
consultation with the Test Proposer and the Users identified under OC12.4.2.1.
(b) Where NGET decides, in its reasonable opinion, that the National Electricity
Transmission System will not be significantly affected by the proposed System Test, then
the Test Co-ordinator will be a suitably qualified person nominated by the Test Proposer
after consultation with NGET.
(c) NGET will, as soon as reasonably practicable after it has received, or is deemed to have
received, a Proposal Notice, contact the Test Proposer where the Test Co-ordinator is to
be a person nominated by the Test Proposer and invite it to nominate a person as Test
Co-ordinator. If the Test Proposer is unable or unwilling to nominate a person within
seven days of being contacted by NGET then the proposed System Test will not take place.
OC12.4.2.3 NGET will notify all Users identified by it under OC12.4.2.1 of the proposed System Test by a
notice in writing (a "Preliminary Notice) and will send a Preliminary Notice to the Test
Proposer. The Preliminary Notice will contain:
(a) the details of the nature and purpose of the proposed System Test, the extent and situation
of the Plant and/or Apparatus involved and the identity of the Users identified by NGET
under OC12.4.2.1 and the identity of the Test Proposer;
(b) an invitation to nominate within one month a suitably qualified representative (or
representatives, if the Test Co-ordinator informs NGET that it is appropriate for a particular
User including the Test Proposer) to be a member of the Test Panel for the proposed
System Test;
(c) the name of the NGET representative (or representatives) on the Test Panel for the
proposed System Test; and
(d) the name of the Test Co-ordinator and whether he was nominated by the Test Proposer
or by NGET.
OC12.4.2.4 The Preliminary Notice will be sent within one month of the later of either the receipt by NGET
of the Proposal Notice, or of the receipt of any further information requested by NGET under
OC12.4.1.3. Where NGET is the proposer of the System Test, the Preliminary Notice will be
sent within one month of the proposed System Test being formulated.
OC12.4.2.5 Replies to the invitation in the Preliminary Notice to nominate a representative to be a member
of the Test Panel must be received by NGET within one month of the date on which the
Preliminary Notice was sent to the User by NGET. Any User which has not replied within that
period will not be entitled to be represented on the Test Panel. If the Test Proposer does not
reply within that period, the proposed System Test will not take place and NGET will notify all
Users identified by it under OC12.4.2.1 accordingly.
OC12.4.2.6 NGET will, as soon as possible after the expiry of that one month period, appoint the nominated
persons to the Test Panel and notify all Users identified by it under OC12.4.2.1 and the Test
Proposer, of the composition of the Test Panel.
OC12.4.3 Test Panel
OC12.4.3.1 A meeting of the Test Panel will take place as soon as possible after NGET has notified all
Users identified by it under OC12.4.2.1 and the Test Proposer of the composition of the Test
Panel, and in any event within one month of the appointment of the Test Panel.

OC12.4.3.2 The Test Panel shall consider:


(a) the details of the nature and purpose of the proposed System Test and other matters set
out in the Proposal Notice (together with any further information requested by NGET under
OC12.4.1.3);
(b) the economic, operational and risk implications of the proposed System Test;
Issue 5 Revision 0 OC12 17 August 2012
4 of 6
(c) the possibility of combining the proposed System Test with any other tests and with Plant
and/or Apparatus outages which arise pursuant to the Operational Planning requirements
of NGET and Users; and
(d) implications of the proposed System Test on the operation of the Balancing Mechanism,
in so far as it is able to do so.
OC12.4.3.3 Users identified by NGET under OC12.4.2.1, the Test Proposer and NGET (whether or not they
are represented on the Test Panel) shall be obliged to supply that Test Panel, upon written
request, with such details as the Test Panel reasonably requires in order to consider the
proposed System Test.
OC12.4.3.4 The Test Panel shall be convened by the Test Co-ordinator as often as he deems necessary to
conduct its business.
OC12.4.4 Proposal Report
OC12.4.4.1 Within two months of first meeting the Test Panel will submit a report (a "Proposal Report"),
which will contain:
(a) proposals for carrying out the System Test (including the manner in which the System Test
is to be monitored);
(b) an allocation of costs (including un-anticipated costs) between the affected parties (the
general principle being that the Test Proposer will bear the costs); and
(c) such other matters as the Test Panel considers appropriate.
The Proposal Report may include requirements for indemnities (including an indemnity from the
relevant Network Operator to NGET and other Users in relation to its Embedded Persons) to
be given in respect of claims and losses arising from the System Test. All System Test
procedures must comply with all applicable legislation.
OC12.4.4.2 If the Test Panel is unable to agree unanimously on any decision in preparing its Proposal
Report, the proposed System Test will not take place and the Test Panel will be dissolved.
OC12.4.4.3 The Proposal Report will be submitted to NGET, the Test Proposer and to each User identified
by NGET under OC12.4.2.1.
OC12.4.4.4 Each recipient will respond to the Test Co-ordinator with its approval of the Proposal Report or
its reason for non-approval within fourteen days of receipt of the Proposal Report. If any
recipient does not respond, the System Test will not take place and the Test Panel will be
dissolved.
OC12.4.4.5 In the event of non-approval by one or more recipients, the Test Panel will meet as soon as
practicable in order to determine whether the proposed System Test can be modified to meet
the objection or objections.
OC12.4.4.6 If the proposed System Test cannot be so modified, the System Test will not take place and the
Test Panel will be dissolved.
OC12.4.4.7 If the proposed System Test can be so modified, the Test Panel will, as soon as practicable,
and in any event within one month of meeting to discuss the responses to the Proposal Report,
submit a revised Proposal Report and the provisions of OC12.4.4.3 and OC12.4.4.4 will apply to
that submission.
OC12.4.4.8 In the event of non-approval of the revised Proposal Report by one or more recipients, the
System Test will not take place and the Test Panel will be dissolved.

Issue 5 Revision 0 OC12 17 August 2012


5 of 6
OC12.4.5 Test Programme
OC12.4.5.1 If the Proposal Report (or, as the case may be, the revised Proposal Report) is approved by all
recipients, the proposed System Test can proceed and at least one month prior to the date of
the proposed System Test, the Test Panel will submit to NGET, the Test Proposer and each
User identified by NGET under OC12.4.2.1, a programme (the "Test Programme") stating the
switching sequence and proposed timings of the switching sequence, a list of those staff involved
in carrying out the System Test (including those responsible for site safety) and such other
matters as the Test Panel deems appropriate.
OC12.4.5.2 The Test Programme will, subject to OC12.4.5.3, bind all recipients to act in accordance with the
provisions of the Test Programme in relation to the proposed System Test.
OC12.4.5.3 Any problems with the proposed System Test which arise or are anticipated after the issue of
the Test Programme and prior to the day of the proposed System Test, must be notified to the
Test Co-ordinator as soon as possible in writing. If the Test Co-ordinator decides that these
anticipated problems merit an amendment to, or postponement of, the System Test, he shall
notify the Test Proposer (if the Test Co-ordinator was not appointed by the Test Proposer),
NGET and each User identified by NGET under OC12.4.2.1 accordingly.
OC12.4.5.4 If on the day of the proposed System Test, operating conditions on the Total System are such
that any party involved in the proposed System Test wishes to delay or cancel the start or
continuance of the System Test, they shall immediately inform the Test Co-ordinator of this
decision and the reasons for it. The Test Co-ordinator shall then postpone or cancel, as the
case may be, the System Test and shall, if possible, agree with the Test Proposer (if the Test
Co-ordinator was not appointed by the Test Proposer), NGET and all Users identified by
NGET under OC12.4.2.1 another suitable time and date. If he cannot reach such agreement, the
Test Co-ordinator shall reconvene the Test Panel as soon as practicable, which will endeavour
to arrange another suitable time and date for the System Test, in which case the relevant
provisions of OC12 shall apply.
OC12.4.6 Final Report
OC12.4.6.1 At the conclusion of the System Test, the Test Proposer shall be responsible for preparing a
written report on the System Test (the "Final Report") for submission to NGET and other
members of the Test Panel. The Final Report shall be submitted within three months of the
conclusion of the System Test unless a different period has been agreed by the Test Panel prior
to the System Test taking place.
OC12.4.6.2 The Final Report shall not be submitted to any person who is not a member of the Test Panel
unless the Test Panel, having considered the confidentiality issues arising, shall have
unanimously approved such submission.
OC12.4.6.3 The Final Report shall include a description of the Plant and/or Apparatus tested and a
description of the System Test carried out, together with the results, conclusions and
recommendations.
OC12.4.6.4 When the Final Report has been prepared and submitted in accordance with OC12.4.6.1, the
Test Panel will be dissolved.
OC12.4.7 Timetable Reduction
OC12.4.7.1 In certain cases a System Test may be needed on giving less than twelve months notice. In that
case, after consultation with the Test Proposer and User(s) identified by NGET under
OC12.4.2.1, NGET shall draw up a timetable for the proposed System Test and the procedure
set out in OC12.4.2 to OC12.4.6 shall be followed in accordance with that timetable.

< END OF OPERATING CODE NO. 12 >

Issue 5 Revision 0 OC12 17 August 2012


6 of 6
BALANCING CODE NO. 1
(BC1)

PRE GATE CLOSURE PROCESS

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


BC1.1 INTRODUCTION ................................................................................................................................... 1
BC1.2 OBJECTIVE ........................................................................................................................................... 1
BC1.3 SCOPE .................................................................................................................................................. 1
BC1.4 SUBMISSION OF DATA ....................................................................................................................... 1
BC1.4.1 Communication With Users ........................................................................................................ 1
BC1.4.2 Day Ahead Submissions ............................................................................................................. 2
BC1.4.3 Data Revisions ............................................................................................................................ 5
BC1.4.4 Receipt Of BM Unit Data Prior To Gate Closure ........................................................................ 5
BC1.4.5 BM Unit Defaulting, Validity And Consistency Checking ............................................................ 5
BC1.4.6 Special Provisions Relating To Interconnector Users ................................................................ 6
BC1.5 INFORMATION PROVIDED BY NGET................................................................................................. 6
BC1.5.1 Demand Estimates ..................................................................................................................... 6
BC1.5.2 Indicated Margin And Indicated Imbalance ................................................................................ 7
BC1.5.3 Provision Of Updated Information .............................................................................................. 7
BC1.5.4 Reserve And System Margin ...................................................................................................... 7
BC1.5.5 System And Localised NRAPM (Negative Reserve Active Power Margin) ................................ 8
BC1.6 SPECIAL PROVISIONS RELATING TO NETWORK OPERATORS ................................................... 9
BC1.6.1 User System Data From Network Operators .............................................................................. 9
BC1.6.2 Notification Times To Network Operators ................................................................................. 10
BC1.7 SPECIAL ACTIONS ............................................................................................................................ 10
BC1.8 PROVISION OF REACTIVE POWER CAPABILITY ........................................................................... 10
APPENDIX 1 - BM UNIT DATA ........................................................................................................................ 12
BC1.A.1.1 Physical Notifications ............................................................................................................ 12
BC1.A.1.2 Quiescent Physical Notifications (QPN) ................................................................................ 13
BC1.A.1.3 Export And Import Limits ....................................................................................................... 13
BC1.A.1.4 Bid Offer Data ........................................................................................................................ 14
BC1.A.1.5 Dynamic Parameters ............................................................................................................. 15
BC1.A.1.6 CCGT Module Matrix ............................................................................................................. 15
BC1.A.1.7 Cascade Hydro Scheme Matrix ............................................................................................ 17
BC1.A.1.8 Power Park Module Availability Matrix .................................................................................. 17
APPENDIX 2 - DATA TO BE MADE AVAILABLE BY NGET ........................................................................... 19
BC1.A.2.1 Initial Day Ahead Demand Forecast ..................................................................................... 19
BC1.A.2.2 Initial Day Ahead Market Information .................................................................................... 19
Issue 5 Revision 13 BC1 22 January 2015
i
BC1.A.2.3 Current Day & Day Ahead Updated Market Information .......................................................19

Issue 5 Revision 13 BC1 22 January 2015


ii
BC1.1 INTRODUCTION
Balancing Code No1 (BC1) sets out the procedure for:
(a) the submission of BM Unit Data and/or Generating Unit Data by each BM Participant;
(b) the submission of certain System data by each Network Operator; and
(c) the provision of data by NGET,
in the period leading up to Gate Closure.

BC1.2 OBJECTIVE
The procedure for the submission of BM Unit Data and/or Generating Unit Data is intended
to enable NGET to assess which BM Units and Generating Units are expected to be
operating in order that NGET can ensure (so far as possible) the integrity of the National
Electricity Transmission System, and the security and quality of supply.
Where reference is made in this BC1 to Generating Units (unless otherwise stated) it only
applies:
(a) to each Generating Unit which forms part of the BM Unit of a Cascade Hydro
Scheme; and
(b) at an Embedded Exemptable Large Power Station where the relevant Bilateral
Agreement specifies that compliance with BC1 is required:
(i) to each Generating Unit, or
(ii) to each Power Park Module where the Power Station comprises Power Park
Modules.

BC1.3 SCOPE
BC1 applies to NGET and to Users, which in this BC1 means:-
(a) BM Participants;
(b) Externally Interconnected System Operators; and
(c) Network Operators.

BC1.4 SUBMISSION OF DATA


In the case of BM Units or Generating Units Embedded in a User System, any data
submitted by Users under this BC1 must represent the value of the data at the relevant Grid
Supply Point.
BC1.4.1 Communication With Users
(a) Submission of BM Unit Data and Generating Unit Data by Users to NGET specified in
BC1.4.2 to BC1.4.4 (with the exception of BC1.4.2(f)) is to be by use of electronic data
communications facilities, as provided for in CC.6.5.8. However, data specified in
BC1.4.2(c) and BC1.4.2(e) only, may be submitted by telephone or fax.
(b) In the event of a failure of the electronic data communication facilities, the data to apply
in relation to a pre-Gate Closure period will be determined in accordance with the Data
Validation, Consistency and Defaulting Rules, based on the most recent data
received and acknowledged by NGET.
(c) Planned Maintenance Outages will normally be arranged to take place during periods
of low data transfer activity.
(d) Upon any Planned Maintenance Outage, or following an unplanned outage described
in BC1.4.1(b) (where it is termed a "failure") in relation to a pre-Gate Closure period:
(i) BM Participants should continue to act in relation to any period of time in
Issue 5 Revision 19 BC1 30 September 2016
1 of 20
accordance with the Physical Notifications current at the time of the start of the
Planned Maintenance Outage or the computer system failure in relation to each
such period of time subject to the provisions of BC2.5.1. Depending on when in
relation to Gate Closure the planned or unplanned maintenance outage arises
such operation will either be operation in preparation for the relevant output in real
time, or will be operation in real time. No further submissions of BM Unit Data
and/or Generating Unit Data (other than data specified in BC1.4.2(c) and
BC1.4.2(e)) should be attempted. Plant failure or similar problems causing
significant deviation from Physical Notification should be notified to NGET by the
submission of a revision to Export and Import Limits in relation to the BM Unit
and /or Generating Unit so affected;
(ii) during the outage, revisions to the data specified in BC1.4.2(c) and BC1.4.2(e)
may be submitted. Communication between Users Control Points and NGET
during the outage will be conducted by telephone; and
(iii) no data will be transferred from NGET to the BMRA until the communication
facilities are re-established.
BC1.4.2 Day Ahead Submissions
Data for any Operational Day may be submitted to NGET up to several days in advance of
the day to which it applies, as provided in the Data Validation, Consistency and
Defaulting Rules. However, Interconnector Users must submit Physical Notifications,
and any associated data as necessary, each day by 11:00 hours in respect of the next
following Operational Day in order that the information used in relation to the capability of
the respective External Interconnection is expressly provided. NGET shall not by the
inclusion of this provision be prevented from utilising the provisions of BC1.4.5 if necessary.
The data may be modified by further data submissions at any time prior to Gate Closure, in
accordance with the other provisions of BC1. The data to be used by NGET for operational
planning will be determined from the most recent data that has been received by NGET by
11:00 hours on the day before the Operational Day to which the data applies, or from the
data that has been defaulted at 11:00 hours on that day in accordance with BC1.4.5. Any
subsequent revisions received by NGET under the Grid Code will also be utilised by NGET.
In the case of all data items listed below, with the exception of item (e), Dynamic
Parameters (Day Ahead), the latest submitted or defaulted data, as modified by any
subsequent revisions, will be carried forward into operational timescales. The individual data
items are listed below:
(a) Physical Notifications
Physical Notifications, being the data listed in BC1 Appendix 1 under that heading,
are required by NGET at 11:00 hours each day for each Settlement Period of the next
following Operational Day, in respect of;
(1) BM Units:
(i) with a Demand Capacity with a magnitude of 50MW or more in NGETs
Transmission Area or 10MW or more in SHETLs Transmission Area or
30MW or more in SPTs Transmission Area; or
(ii) comprising Generating Units (as defined in the Glossary and Definitions and
not limited by BC1.2) and/or CCGT Modules and/or Power Park Modules in
each case at Large Power Stations, Medium Power Stations and Small
Power Stations where such Small Power Stations are directly connected to
an Offshore Transmission System; or
(iii) where the BM Participant chooses to submit Bid-Offer Data in accordance
with BC1.4.2(d) for BM Units not falling within (i) or (ii) above,
and
(2) each Generating Unit where applicable under BC1.2.

Issue 5 Revision 19 BC1 30 September 2016


2 of 20
Physical Notifications may be submitted to NGET by BM Participants, for the BM
Units, and Generating Units, specified in this BC1.4.2(a) at an earlier time, or BM
Participants may rely upon the provisions of BC1.4.5 to create the Physical
Notifications by data defaulting pursuant to the Grid Code utilising the rules referred to
in that paragraph at 11:00 hours in any day.
Physical Notifications (which must comply with the limits on maximum rates of change
listed in BC1 Appendix 1) must, subject to the following operating limits, represent the
Users best estimate of expected input or output of Active Power and shall be
prepared in accordance with Good Industry Practice. Physical Notifications for any
BM Unit, and any Generating Units, should normally be consistent with the Dynamic
Parameters and Export and Import Limits and must not reflect any BM Unit or any
Generating Units, proposing to operate outside the limits of its Demand Capacity and
(and in the case of BM Units) Generation Capacity and, in the case of a BM Unit
comprising a Generating Unit (as defined in the Glossary and Definitions and not
limited by BC1.2) or CCGT Module or Power Park Module, its Registered Capacity.
These Physical Notifications provide, amongst other things, indicative Synchronising
and De-Synchronising times to NGET in respect of any BM Unit comprising a
Generating Unit (as defined in the Glossary and Definitions and not limited by BC1.2)
or CCGT Module or Power Park Module, and for any Generating Units, and provide
an indication of significant Demand changes in respect of other BM Units.
(b) Quiescent Physical Notifications
Each BM Participant may, in respect of each of its BM Units, submit to NGET for each
Settlement Period of the next following Operational Day the data listed in BC1
Appendix 1 under the heading of Quiescent Physical Notifications to amend the
data already held by NGET in relation to Quiescent Physical Notifications, which
would otherwise apply for those Settlement Periods.
(c) Export and Import Limits
Each BM Participant may, in respect of each of its BM Units and its Generating Units
submit to NGET for any part or for the whole of the next following Operational Day the
data listed in BC1 Appendix 1 under the heading of Export and Import Limits to
amend the data already held by NGET in relation to Export and Import Limits, which
would otherwise apply for those Settlement Periods.
Export and Import Limits respectively represent the maximum export to or import from
the National Electricity Transmission System for a BM Unit and a Generating Unit
and are the maximum levels that the BM Participant wishes to make available and
must be prepared in accordance with Good Industry Practice.
(d) Bid-Offer Data
Each BM Participant may, in respect of each of its BM Units, but must not in respect of
its Generating Units submit to NGET for any Settlement Period of the next following
Operational Day the data listed in BC1 Appendix 1 under the heading of Bid-Offer
Data to amend the data already held by NGET in relation to Bid-Offer Data, which
would otherwise apply to those Settlement Periods. The submitted Bid-Offer Data will
be utilised by NGET in the preparation and analysis of its operational plans for the next
following Operational Day. Bid-Offer Data may not be submitted unless an automatic
logging device has been installed at the Control Point for the BM Unit in accordance
with CC.6.5.8(b).

Issue 5 Revision 19 BC1 30 September 2016


3 of 20
(e) Dynamic Parameters (Day Ahead)
Each BM Participant may, in respect of each of its BM Units, but must not in respect of
its Generating Units submit to NGET for the next following Operational Day the data
listed in BC1 Appendix 1 under the heading of Dynamic Parameters to amend that
data already held by NGET.
These Dynamic Parameters shall reasonably reflect the expected true operating
characteristics of the BM Unit and shall be prepared in accordance with Good Industry
Practice. In any case where non-zero QPN data has been provided in accordance with
BC1.4.2(b), the Dynamic Parameters will apply to the element being offered for control
only, i.e. to the component of the Physical Notification between the QPN and the full
level of the Physical Notification.
The Dynamic Parameters applicable to the next following Operational Day will be
utilised by NGET in the preparation and analysis of its operational plans for the next
following Operational Day and may be used to instruct certain Ancillary Services. For
the avoidance of doubt, the Dynamic Parameters to be used in the current
Operational Day will be those submitted in accordance with BC2.5.3.1.
(f) Other Relevant Data
By 11:00 hours each day each BM Participant, in respect of each of its BM Units and
Generating Units for which Physical Notifications are being submitted, shall, if it has
not already done so, submit to NGET (save in respect of item (vi) and (vii) where the
item shall be submitted only when reasonably required by NGET), in respect of the next
following Operational Day the following:
(i) in the case of a CCGT Module, a CCGT Module Matrix as described in BC1
Appendix 1;
(ii) details of any special factors which in the reasonable opinion of the BM
Participant may have a material effect or present an enhanced risk of a material
effect on the likely output (or consumption) of such BM Unit(s). Such factors may
include risks, or potential interruptions, to BM Unit fuel supplies, or developing
plant problems, details of tripping tests, etc. This information will normally only be
used to assist in determining the appropriate level of Operating Margin that is
required under OC2.4.6;
(iii) in the case of Generators, any temporary changes, and their possible duration, to
the Registered Data of such BM Unit;
(iv) in the case of Suppliers, details of Customer Demand Management taken into
account in the preparation of its BM Unit Data;
(v) details of any other factors which NGET may take account of when issuing Bid-
Offer Acceptances for a BM Unit (e.g., Synchronising or De-Synchronising
Intervals);
(vi) in the case of a Cascade Hydro Scheme, the Cascade Hydro Scheme Matrix as
described in BC1 Appendix 1; and
(vii) in the case of a Power Park Module, a Power Park Module Availability Matrix
as described in BC1 Appendix 1.
(g) Joint BM Unit Data
BM Participants may submit Joint BM Unit Data in accordance with the provisions of
the BSC. For the purposes of the Grid Code, such data shall be treated as data
submitted under BC1.

Issue 5 Revision 19 BC1 30 September 2016


4 of 20
BC1.4.3 Data Revisions
The BM Unit Data, and Generating Unit Data, derived at 1100 hours each day under
BC1.4.2 above may need to be revised by the BM Participant for a number of reasons,
including for example, changes to expected output or input arising from revised contractual
positions, plant breakdowns, changes to expected Synchronising or De-Synchronising
times, etc, occurring before Gate Closure. BM Participants should use reasonable
endeavours to ensure that the data held by NGET in relation to its BM Units and
Generating Units, is accurate at all times. Revisions to BM Unit Data, and Generating Unit
Data for any period of time up to Gate Closure should be submitted to NGET as soon as
reasonably practicable after a change becomes apparent to the BM Participant. NGET will
use reasonable endeavours to utilise the most recent data received from Users, subject to
the application of the provisions of BC1.4.5, for its preparation and analysis of operational
plans.
BC1.4.4 Receipt Of BM Unit Data Prior To Gate Closure
BM Participants submitting Bid-Offer Data, in respect of any BM Unit for use in the
Balancing Mechanism for any particular Settlement Period in accordance with the BSC,
must ensure that Physical Notifications and Bid-Offer Data for such BM Units are
received in their entirety and logged into NGETs computer systems by the time of Gate
Closure for that Settlement Period. In all cases the data received will be subject to the
application under the Grid Code of the provisions of BC1.4.5.
For the avoidance of doubt, no changes to the Physical Notification, QPN data or Bid-
Offer Data for any Settlement Period may be submitted to NGET after Gate Closure for
that Settlement Period.
BC1.4.5 BM Unit Data Defaulting, Validity And Consistency Checking
In the event that no submission of any or all of the BM Unit Data and Generating Unit Data
in accordance with BC1.4.2 in respect of an Operational Day, is received by NGET by 11:00
hours on the day before that Operational Day, NGET will apply the Data Validation,
Consistency and Defaulting Rules, with the default rules applicable to Physical
Notifications, Quiescent Physical Notifications and Export and Import Limits data
selected as follows:
(a) for an Interconnector Users BM Unit, the defaulting rules will set some or all of the
data for that Operational Day to zero, unless the relevant Interconnector arrangements,
as agreed with NGET, state otherwise (in which case (b) applies); and
(b) for all other BM Units or Generating Units, the defaulting rules will set some or all of
the data for that Operational Day to the values prevailing in the current Operational
Day.
A subsequent submission by a User of a data item which has been so defaulted under the
Grid Code will operate as an amendment to that defaulted data and thereby replace it. Any
such subsequent submission is itself subject to the application under the Grid Code of the
Data Validation, Consistency and Defaulting Rules.

Issue 5 Revision 19 BC1 30 September 2016


5 of 20
BM Unit Data and Generating Unit Data submitted in accordance with the provisions of
BC1.4.2 to BC1.4.4 will be checked under the Grid Code for validity and consistency in
accordance with the Data Validation, Consistency and Defaulting Rules. If any BM Unit
Data and Generating Unit Data so submitted fails the data validity and consistency
checking, this will result in the rejection of all data submitted for that BM Unit or Generating
Unit included in the electronic data file containing that data item and that BM Units or
Generating Units data items will be defaulted under the Grid Code in accordance with the
Data Validation, Consistency and Defaulting Rules. Data for other BM Units and
Generating Units included in the same electronic data file will not be affected by such
rejection and will continue to be validated and checked for consistency prior to acceptance.
In the event that rejection of any BM Unit Data and Generating Unit Data occurs, details
will be made available to the relevant BM Participant via the electronic data communication
facilities. In the event of a difference between the BM Unit Data for the Cascade Hydro
Scheme and sum of the data submitted for the Generating Units forming part of such
Cascade Hydro Scheme, the BM Unit Data shall take precedence.
BC1.4.6 Special Provisions Relating To Interconnector Users
(a) The total of the relevant Physical Notifications submitted by Interconnector Users in
respect of any period of time should not exceed the capability (in MW) of the respective
External Interconnection for that period of time. In the event that it does, then NGET
shall advise the Externally Interconnected System Operator accordingly. In the
period between such advice and Gate Closure, one or more of the relevant
Interconnector Users would be expected to submit revised Physical Notifications to
NGET to eliminate any such over-provision.
(b) In any case where, as a result of a reduction in the capability (in MW) of the External
Interconnection in any period during an Operational Day which is agreed between
NGET and an Externally Interconnected System Operator after 0900 hours on the
day before the beginning of such Operational Day, the total of the Physical
Notifications in the relevant period using that External Interconnection, as stated in
the BM Unit Data exceeds the reduced capability (in MW) of the respective External
Interconnection in that period then NGET shall notify the Externally Interconnected
System Operator accordingly.

BC1.5 INFORMATION PROVIDED BY NGET


NGET shall provide data to the Balancing Mechanism Reporting Agent or BSCCo each
day in accordance with the requirements of the BSC in order that the data may be made
available to Users via the Balancing Mechanism Reporting Service (or by such other
means) in each case as provided in the BSC. Where NGET provides such information
associated with the secure operation of the System to the Balancing Mechanism
Reporting Agent, the provision of that information is additionally provided for in the following
sections of this BC1.5. NGET shall be taken to have fulfilled its obligations to provide data
under BC1.5.1, BC1.5.2, and BC1.5.3 by so providing such data to the Balancing
Mechanism Reporting Agent.
BC1.5.1 Demand Estimates
Normally by 0900 hours each day, NGET will make available to Users a forecast of National
Demand and the Demand for a number of pre-determined constraint groups (which may be
updated from time to time, as agreed between NGET and BSCCo) for each Settlement
Period of the next following Operational Day. Normally by 1200 hours each day, NGET will
make available to Users a forecast of National Electricity Transmission System Demand
for each Settlement Period of the next Operational Day. Further details are provided in
Appendix 2.

Issue 5 Revision 19 BC1 30 September 2016


6 of 20
BC1.5.2 Indicated Margin And Indicated Imbalance
Normally by 1200 hours each day, NGET will make available to Users an Indicated Margin
and an Indicated Imbalance for each Settlement Period of the next following Operational
Day. NGET will use reasonable endeavours to utilise the most recent data received from
Users in preparing for this release of data. Further details are provided in Appendix 2.
BC1.5.3 Provision Of Updated Information
NGET will provide updated information on Demand and other information at various times
throughout each day, as detailed in Appendix 2. NGET will use reasonable endeavours to
utilise the most recent data received from Users in preparing for this release of data.
BC1.5.4 Reserve And System Margin
Contingency Reserve
(a) The amount of Contingency Reserve required at the day ahead stage and in
subsequent timescales will be decided by NGET on the basis of historical trends in the
reduction in availability of Large Power Stations and increases in forecast Demand up
to real time operation. Where Contingency Reserve is to be allocated to thermal
Gensets, NGET will instruct through a combination of Ancillary Services instructions
and Bid-Offer Acceptances, the time at which such Gensets are required to
synchronise, such instructions to be consistent with Dynamic Parameters and other
contractual arrangements.
Operating Reserve
(b) The amount of Operating Reserve required at any time will be determined by NGET
having regard to the Demand levels, Large Power Station availability shortfalls and the
greater of the largest secured loss of generation (ie, the loss of generation against
which, as a requirement of the Licence Standards, the National Electricity
Transmission System must be secured) or loss of import from or sudden export to
External Interconnections. NGET will allocate Operating Reserve to the appropriate
BM Units and Generating Units so as to fulfil its requirements according to the
Ancillary Services available to it and as provided in the BC.
System Margin
(c) In the period following 1200 hours each day and in relation to the following Operational
Day, NGET will monitor the total of the Maximum Export Limit component of the Export
and Import Limits received against forecast National Electricity Transmission
System Demand and the Operating Margin and will take account of Dynamic
Parameters to see whether the anticipated level of the System Margin for any period is
insufficient.
(d) Where the level of the System Margin for any period is, in NGET's reasonable opinion,
anticipated to be insufficient, NGET will send (by such data transmission facilities as
have been agreed) a National Electricity Transmission System Warning -
Electricity Margin Notice in accordance with OC7.4.8 to each Generator, Supplier,
Externally Interconnected System Operator, Network Operator and Non-
Embedded Customer.
(e) Where, in NGETs judgement the System Margin at any time during the current
Operational Day is such that there is a high risk of Demand reduction being instructed,
a National Electricity Transmission System Warning - High Risk of Demand
Reduction will be issued, in accordance with OC7.4.8.
(f) The monitoring will be conducted on a regular basis and a revised National Electricity
Transmission System Warning - Electricity Margin Notice or High Risk of Demand
Reduction may be sent out from time to time, including within the post Gate Closure
phase. This will reflect any changes in Physical Notifications and Export and Import
Limits which have been notified to NGET, and will reflect any Demand Control which
has also been so notified. This will also reflect generally any changes in the forecast
Demand and the relevant Operating Margin.

Issue 5 Revision 19 BC1 30 September 2016


7 of 20
(g) To reflect changing conditions, a National Electricity Transmission System Warning
- Electricity Margin Notice may be superseded by a National Electricity
Transmission System Warning - High Risk of Demand Reduction and vice-versa.
(h) If the continuing monitoring identifies that the System Margin is anticipated, in NGET's
reasonable opinion, to be sufficient for the period for which previously a National
Electricity Transmission System Warning had been issued, NGET will send (by such
data transmission facilities as have been agreed) a Cancellation of National
Electricity Transmission System Warning to each User who had received a National
Electricity Transmission System Warning - Electricity Margin Notice or High Risk
of Demand Reduction for that period. The issue of a Cancellation of National
Electricity Transmission System Warning is not an assurance by NGET that in the
event the System Margin will be adequate, but reflects NGET's reasonable opinion
that the insufficiency is no longer anticipated.
(i) If continued monitoring indicates the System Margin becoming reduced NGET may
issue further National Electricity Transmission System Warnings - Electricity
Margin Notice or High Risk of Demand Reduction.
(j) NGET may issue a National Electricity Transmission System Warning - Electricity
Margin Notice or High Risk of Demand Reduction for any period, not necessarily
relating to the following Operational Day, where it has reason to believe there will be a
reduced System Margin over a period (for example in periods of protracted Plant
shortage, the provisions of OC7.4.8.6 apply).
BC1.5.5 System And Localised NRAPM (Negative Reserve Active Power Margin)
(a) (i) System Negative Reserve Active Power Margin
Synchronised Gensets must at all times be capable of reducing output such that
the total reduction in output of all Synchronised Gensets is sufficient to offset the
loss of the largest secured demand on the System and must be capable of
sustaining this response;
(ii) Localised Negative Reserve Active Power Margin
Synchronised Gensets must at all times be capable of reducing output to allow
transfers to and from the System Constraint Group (as the case may be) to be
contained within such reasonable limit as NGET may determine and must be
capable of sustaining this response.
(b) NGET will monitor the total of Physical Notifications of exporting BM Units and
Generating Units (where appropriate) received against forecast Demand and, where
relevant, the appropriate limit on transfers to and from a System Constraint Group and
will take account of Dynamic Parameters and Export and Import Limits received to
see whether the level of System NRAPM or Localised NRAPM for any period is likely
to be insufficient. In addition, NGET may increase the required margin of System
NRAPM or Localised NRAPM to allow for variations in forecast Demand. In the case
of System NRAPM, this may be by an amount (in NGET's reasonable discretion) not
exceeding five per cent of forecast Demand for the period in question. In the case of
Localised NRAPM, this may be by an amount (in NGET's reasonable discretion) not
exceeding ten per cent of the forecast Demand for the period in question;
(c) Where the level of System NRAPM or Localised NRAPM for any period is, in NGET 's
reasonable opinion, likely to be insufficient NGET may contact all Generators in the
case of low System NRAPM and may contact Generators in relation to relevant
Gensets in the case of low Localised NRAPM. NGET will raise with each Generator
the problems it is anticipating due to low System NRAPM or Localised NRAPM and
will discuss whether, in advance of Gate Closure:-
(i) any change is possible in the Physical Notification of a BM Unit which has been
notified to NGET; or

(ii) any change is possible to the Physical Notification of a BM Unit within an


Issue 5 Revision 19 BC1 30 September 2016
8 of 20
Existing AGR Plant within the Existing AGR Plant Flexibility Limit;
in relation to periods of low System NRAPM or (as the case may be) low
Localised NRAPM. NGET will also notify each Externally Interconnected
System Operator of the anticipated low System NRAPM or Localised NRAPM
and request assistance in obtaining changes to Physical Notifications from BM
Units in that External System.
(d) Following Gate Closure, the procedure of BC2.9.4 will apply.

BC1.6 SPECIAL PROVISIONS RELATING TO NETWORK OPERATORS


BC1.6.1 User System Data From Network Operators
(a) By 1000 hours each day each Network Operator will submit to NGET in writing,
confirmation or notification of the following in respect of the next Operational Day:
(i) constraints on its User System which NGET may need to take into account in
operating the National Electricity Transmission System. In this BC1.6.1 the term
"constraints" shall include restrictions on the operation of Embedded CCGT Units,
and/or Embedded Power Park Modules as a result of the User System to which
the CCGT Unit and/or Power Park Module is connected at the User System
Entry Point being operated or switched in a particular way, for example, splitting
the relevant busbar. It is a matter for the Network Operator and the Generator to
arrange the operation or switching, and to deal with any resulting consequences.
The Generator, after consultation with the Network Operator, is responsible for
ensuring that no BM Unit Data submitted to NGET can result in the violation of any
such constraint on the User System.
(ii) the requirements of voltage control and MVAr reserves which NGET may need to
take into account for System security reasons.
(iii) where applicable, updated best estimates of Maximum Export Capacity and
Maximum Import Capacity and Interface Point Target Voltage/Power Factor
for any Interface Point connected to its User System including any requirement
for post-fault actions to be implemented on the relevant Offshore Transmission
System by NGET.
(b) The form of the submission will be:
(i) that of a BM Unit output or consumption (for MW and for MVAr, in each case a
fixed value or an operating range, on the User System at the User System Entry
Point, namely in the case of a BM Unit comprising a Generating Unit (as defined
in the Glossary and Definitions and not limited by BC1.2) on the higher voltage side
of the generator step-up transformer, or in the case of a Power Park Module, at
the point of connection) required for particular BM Units (identified in the
submission) connected to that User System for each Settlement Period of the
next Operational Day;

Issue 5 Revision 19 BC1 30 September 2016


9 of 20
(ii) adjusted in each case for MW by the conversion factors applicable for those BM
Units to provide output or consumption at the relevant Grid Supply Points.
(c) At any time and from time to time, between 1000 hours each day and the expiry of the
next Operational Day, each Network Operator must submit to NGET in writing any
revisions to the information submitted under this BC1.6.1.
BC1.6.2 Notification Of Times To Network Operators
NGET will make available indicative Synchronising and De-Synchronising times to each
Network Operator, but only relating to BM Units comprising a Generating Unit (as defined
in the Glossary and Definitions and not limited by BC1.2) or a Power Park Module or a
CCGT Module Embedded within that Network Operators User System and those
Gensets directly connected to the National Electricity Transmission System which NGET
has identified under OC2 as being those which may, in the reasonable opinion of NGET,
affect the integrity of that User System. If in preparing for the operation of the Balancing
Mechanism, NGET becomes aware that a BM Unit directly connected to the National
Electricity Transmission System may, in its reasonable opinion, affect the integrity of that
other User System which, in the case of a BM Unit comprising a Generating Unit (as
defined in the Glossary and Definitions and not limited by BC1.2) or a CCGT Module or a
Power Park Module, it had not so identified under OC2, then NGET may make available
details of its indicative Synchronising and De-Synchronising times to that other User and
shall inform the relevant BM Participant that it has done so, identifying the BM Unit
concerned.
BC1.7 SPECIAL ACTIONS
BC1.7.1 NGET may need to identify special actions (either pre- or post-fault) that need to be taken by
specific Users in order to maintain the integrity of the National Electricity Transmission
System in accordance with the Licence Standards and NGET Operational Strategy.
(a) For a Generator special actions will generally involve a Load change or a change of
required Notice to Deviate from Zero NDZ, in a specific timescale on individual or
groups of Gensets.
(b) For Network Operators these special actions will generally involve Load transfers
between Grid Supply Points or arrangements for Demand reduction by manual or
automatic means.
(c) For Externally Interconnected System Operators (in their co-ordinating role for
Interconnector Users using their External System) these special actions will generally
involve an increase or decrease of net power flows across an External
Interconnection by either manual or automatic means.
BC1.7.2 These special actions will be discussed and agreed with the relevant User as appropriate.
The actual implementation of these special actions may be part of an emergency
circumstances procedure described under BC2. If not agreed, generation or Demand may
be restricted or may be at risk.
BC1.7.3 NGET will normally issue the list of special actions to the relevant Users by 1700 hours on
the day prior to the day to which they are to apply.
BC1.8 PROVISION OF REACTIVE POWER CAPABILITY
BC1.8.1 Under certain operating conditions NGET may identify through its Operational Planning
that an area of the National Electricity Transmission System may have insufficient
Reactive Power capability available to ensure that the operating voltage can be maintained
in accordance with NGETs Licence Standards.
In respect of Onshore Synchronous Generating Unit(s)
(i) that have a Connection Entry Capacity in excess of Rated MW (or the Connection
Entry Capacity of the CCGT Module exceeds the sum of Rated MW of the
Generating Units comprising the CCGT Module); and

Issue 5 Revision 19 BC1 30 September 2016


10 of 20
(ii) that are not capable of continuous operation at any point between the limits 0.85 Power
Factor lagging and 0.95 Power Factor leading at the Onshore Synchronous
Generating Unit terminals at Active Power output levels higher than Rated MW; and
st
(iii) that have either a Completion Date on or after 1 May 2009, or where its Connection
Entry Capcity has been increased above Rated MW (or the Connection Entry
Capacityof the CCGT Module has increased above the sum of Rated MW of the
Generating Units comprising the CCGT Module) such increase takes effect on or after
st
1 May 2009; and
(iv) that are in an area of potentially insufficient Reactive Power capability as described in
this clause BC1.8.1,
NGET may instruct the Onshore Synchronous Generating Unit(s) to limit its submitted
Physical Notifications to no higher than Rated MW (or the Active Power output at which it
can operate continuously between the limits 0.85 Power Factor lagging to 0.95 Power
Factor leading at its terminals if this is higher) for a period specified by NGET. Such an
instruction must be made at least 1 hour prior to Gate Closure, although NGET will
endeavour to give as much notice as possible. The instruction may require that a Physical
Notification is re-submitted. The period covered by the instruction will not exceed the
expected period for which the potential deficiency has been identified. Compliance with the
instruction will not incur costs to NGET in the Balancing Mechanism. The detailed
provisions relating to such instructions will normally be set out in the relevant Bilateral
Agreement.

Issue 5 Revision 19 BC1 30 September 2016


11 of 20
APPENDIX 1 - BM UNIT DATA
BC1.A.1 More detail about valid values required under the Grid Code for BM Unit Data and
Generating Unit Data may be identified by referring to the Data Validation, Consistency
and Defaulting Rules. In the case of Embedded BM Units and Generating Units the BM
Unit Data and the Generating Unit Data shall represent the value at the relevant Grid
Supply Point. Where data is submitted on a Generating Unit basis, the provisions of this
Appendix 1 shall in respect of such data submission apply as if references to BM Unit were
replaced with Generating Unit. Where NGET and the relevant User agree, submission on a
Generating Unit basis (in whole or in part) may be otherwise than in accordance with the
provisions of the Appendix 1.
BC1.A.1.1 Physical Notifications
For each BM Unit, the Physical Notification is a series of MW figures and associated
times, making up a profile of intended input or output of Active Power at the Grid Entry
Point or Grid Supply Point, as appropriate. For each Settlement Period, the first from
time should be at the start of the Settlement Period and the last to time should be at the
end of the Settlement Period.
The input or output reflected in the Physical Notification for a single BM Unit (or the
aggregate Physical Notifications for a collection of BM Units at a Grid Entry Point or Grid
Supply Point or to be transferred across an External Interconnection, owned or controlled
by a single BM Participant) must comply with the following limits regarding maximum rates
of change, either for a single change or a series of related changes :

for a change of up to 300MW no limit;

for a change greater than 300MW and less than 1000MW 50MW per minute;

for a change of 1000MW or more 40MW per minute,

unless prior arrangements have been discussed and agreed with NGET. This limitation is not
intended to limit the Run-Up or Run-Down Rates provided as Dynamic Parameters.
An example of the format of Physical Notification is shown below. The convention to be
applied is that where it is proposed that the BM Unit will be importing, the Physical
Notification is negative.

From To
Data Name BMU name Time From
level Time To Level
(MW) MW)
PN , TAGENT , BMUNIT01 , 2001-11-03 06:30 , 77 , 2001-11-03 07:00 , 100
PN , TAGENT , BMUNIT01 , 2001-11-03 07:00 , 100 , 2001-11-03 07:12 , 150
PN , TAGENT , BMUNIT01 , 2001-11-03 07:12 , 150 , 2001-11-03 07:30 , 175

A linear interpolation will be assumed between the Physical Notification From and To
levels specified for the BM Unit by the BM Participant.

Issue 5 Revision 19 BC1 30 September 2016


12 of 20
BC1.A.1.2 Quiescent Physical Notifications (QPN)

For each BM Unit A series of MW figures and associated times, which describe the MW
(optional) levels to be deducted from the Physical Notification of a BM Unit to
determine a resultant operating level to which the Dynamic
Parameters associated with that BM Unit apply.

An example of the format of data is shown below.

From To
Data Name BMU name Time From level Time To level
(MW) (MW)
QPN , TAGENT , BMUNIT04 , 2001-11-03 06:30 , -200 , 2001-11-03 07:00 , -220
QPN , TAGENT , BMUNIT04 , 2001-11-03 07:00 , -220 , 2001-11-03 07:18 , -245
QPN , TAGENT , BMUNIT04 , 2001-11-03 07:18 , -245 , 2001-11-03 07:30 , -300

A linear interpolation will be assumed between the QPN From and To levels specified for the
BM Unit by the BM Participant.

BC1.A.1.3 Export And Import Limits


BC1.A.1.3.1 Maximum Export Limit (MEL)
A series of MW figures and associated times, making up a profile of the maximum level at
which the BM Unit may be exporting (in MW) to the National Electricity Transmission
System at the Grid Entry Point or Grid Supply Point, as appropriate.
For a Power Park Module, the Maximum Export Limit should reflect the maximum possible
Active Power output from each Power Park Module consistent with the data submitted
within the Power Park Module Availability Matrix as defined under BC.1.A.1.8. For the
avoidance of doubt, in the case of a Power Park Module this would equate to the
Registered Capacity less the unavailable Power Park Units within the Power Park
Module and not include weather corrected MW output from each Power Park Unit.

BC1.A.1.3.2 Maximum Import Limit (MIL)


A series of MW figures and associated times, making up a profile of the maximum level at
which the BM Unit may be importing (in MW) from the National Electricity Transmission
System at the Grid Entry Point or Grid Supply Point, as appropriate.
An example format of data is shown below. MEL must be positive or zero, and MIL must be
negative or zero.

From To
Data Name BMU name Time From
level Time To level
(MW) (MW)
MEL , TAGENT , BMUNIT01 , 2001-11-03 05:00 , 410 , 2001-11-03 09:35 , 410
MEL , TAGENT , BMUNIT01 , 2001-11-03 09:35 , 450 , 2001-11-03 12:45 , 450

MIL , TAGENT , BMUNIT04 , 2001-11-03 06:30 , -200 , 2001-11-03 07:00 , -220

Issue 5 Revision 19 BC1 30 September 2016


13 of 20
BC1.A.1.4 Bid-Offer Data

For each BM Unit for each Up to 10 Bid-Offer Pairs as defined in the BSC.
Settlement Period:

An example of the format of data is shown below.

Pair From To Offer Bid


Data Name BMU name Time from Time to ID Level Level (/ (/
(MW) (MW) MWh) MWh)
BOD , TAGENT , BMUNIT01 , 2000-10-28 12:00 , 2000-10-28 13:30 , 4 , 30 , 30 , 40 , 35
BOD , TAGENT , BMUNIT01 , 2000-10-28 12:00 , 2000-10-28 13:30 , 3 , 20 , 20 , 35 , 30
BOD , TAGENT , BMUNIT01 , 2000-10-28 12:00 , 2000-10-28 13:30 , 2 , 40 , 40 , 32 , 27
BOD , TAGENT , BMUNIT01 , 2000-10-28 12:00 , 2000-10-28 13:30 , 1 , 50 , 50 , 30 , 25
BOD , TAGENT , BMUNIT01 , 2000-10-28 12:00 , 2000-10-28 13:30 , -1 , -40 , -40 , 25 , 20
BOD , TAGENT , BMUNIT01 , 2000-10-28 12:00 , 2000-10-28 13:30 , -2 , -30 , -30 , 23 , 17

This example of Bid-Offer data is illustrated graphically below:

Bid-Offer Pair No 4 30MW Offer 40 Bid 35


Bid-Offer Pair No 3 20MW Offer 35 Bid 30

Bid-Offer Pair No 2 40MW Offer 32 Bid 27

Bid-Offer Pair No 1 50MW Offer 30 Bid 25


Final Physical
Notification
Bid-Offer Pair No -1 -40MW Offer 25 Bid 20

Bid-Offer Pair No -2 -30MW Offer 23 Bid 17

Issue 5 Revision 19 BC1 30 September 2016


14 of 20
BC1.A.1.5 Dynamic Parameters
The Dynamic Parameters comprise:
Up to three Run-Up Rate(s) and up to three Run-Down Rate(s), expressed in
MW/minute and associated Run-Up Elbow(s) and Run-Down Elbow(s), expressed in
MW for output and the same for input. It should be noted that Run-Up Rate(s) are
applicable to a MW figure becoming more positive;
Notice to Deviate from Zero (NDZ) output or input, being the notification time required
for a BM Unit to start importing or exporting energy, from a zero Physical Notification
level as a result of a Bid-Offer Acceptance, expressed in minutes;
Notice to Deliver Offers (NTO) and Notice to Deliver Bids (NTB), expressed in minutes,
indicating the notification time required for a BM Unit to start delivering Offers and Bids
respectively from the time that the Bid-Offer Acceptance is issued. In the case of a BM
Unit comprising a Genset, NTO and NTB will be set to a maximum period of two
minutes;
Minimum Zero Time (MZT), being either the minimum time that a BM Unit which has
been exporting must operate at zero or be importing, before returning to exporting or the
minimum time that a BM Unit which has been importing must operate at zero or be
exporting before returning to importing, as a result of a Bid-Offer Acceptance,
expressed in minutes;
Minimum Non-Zero Time (MNZT), expressed in minutes, being the minimum time that a
BM Unit can operate at a non-zero level as a result of a Bid-Offer Acceptance;
Stable Export Limit (SEL) expressed in MW at the Grid Entry Point or Grid Supply
Point, as appropriate, being the minimum value at which the BM Unit can, under stable
conditions, export to the National Electricity Transmission System;
Stable Import Limit (SIL) expressed in MW at the Grid Entry Point or Grid Supply
Point, as appropriate, being the minimum value at which the BM Unit can, under stable
conditions, import from the National Electricity Transmission System;
Maximum Delivery Volume (MDV), expressed in MWh, being the maximum number of
MWh of Offer (or Bid if MDV is negative) that a particular BM Unit may deliver within the
associated Maximum Delivery Period (MDP), expressed in minutes, being the maximum
period over which the MDV applies.
Last Time to Cancel Synchronisation, expressed in minutes with an upper limit of 60
minutes, being he notification time required to cancel a BM Units transition from
operation at zero. This parameter is only applicable where the transition arises either
from a Physical Notification or, in the case where the Physical Notification is zero, a
Bid-Offer Acceptance. There can be up to three Last Time to Cancel
Synchronisation(s) each applicable for a range of values of Notice to Deviate from Zero.

BC1.A.1.6 CCGT Module Matrix


BC1.A.1.6.1 CCGT Module Matrix showing the combination of CCGT Units running in relation to any
given MW output, in the form of the diagram illustrated below. The CCGT Module Matrix is
designed to achieve certainty in knowing the number of CCGT Units synchronised to meet
the Physical Notification and to achieve a Bid-Offer Acceptance.
BC1.A.1.6.2 In the case of a Range CCGT Module, and if the Generator so wishes, a request for the
single Grid Entry Point at which power is provided from the Range CCGT Module to be
changed in accordance with the provisions of BC1.A.1.6.4 below:

Issue 5 Revision 19 BC1 30 September 2016


15 of 20
CCGT Module Matrix example form

CCGT MODULE CCGT GENERATING UNITS* AVAILABLE


ACTIVE POWER nd rd
1st 2 3 4th 5th 6th 1st 2nd 3rd
GT GT GT GT GT GT ST ST ST

ACTIVE POWER OUTPUT


MW
150 150 150 100

0MW to 150MW /

151MW to 250MW / /

251MW to 300MW / /

301MW to 400MW / / /

401MW to 450MW / / /

451MW to 550MW / / / /

* as defined in the Glossary and Definitions and not limited by BC1.2


BC1.A.1.6.3 In the absence of the correct submission of a CCGT Module Matrix the last submitted (or
deemed submitted) CCGT Module Matrix shall be taken to be the CCGT Module Matrix
submitted hereunder.
BC1.A.1.6.4 The data may also include in the case of a Range CCGT Module, a request for the Grid
Entry Point at which the power is provided from the Range CCGT Module to be changed
with effect from the beginning of the following Operational Day to another specified single
Grid Entry Point (there can be only one) to that being used for the current Operational
Day. NGET will respond to this request by 1600 hours on the day of receipt of the request. If
NGET agrees to the request (such agreement not to be unreasonably withheld), the
Generator will operate the Range CCGT Module in accordance with the request. If NGET
does not agree, the Generator will, if it produces power from that Range CCGT Module,
continue to provide power from the Range CCGT Module to the Grid Entry Point being
used at the time of the request. The request can only be made up to 1100 hours in respect of
the following Operational Day. No subsequent request to change can be made after 1100
hours in respect of the following Operational Day. Nothing in this paragraph shall prevent
the busbar at the Grid Entry Point being operated in separate sections.
BC1.A.1.6.5 The principles set out in PC.A.3.2.3 apply to the submission of a CCGT Module Matrix and
accordingly the CCGT Module Matrix can only be amended as follows:
(a) Normal CCGT Module
if the CCGT Module is a Normal CCGT Module, the CCGT Units within that CCGT
Module can only be amended such that the CCGT Module comprises different CCGT
Units if NGET gives its prior consent in writing. Notice of the wish to amend the CCGT
Units within such a CCGT Module must be given at least 6 months before it is wished
for the amendment to take effect;
(b) Range CCGT Module
if the CCGT Module is a Range CCGT Module, the CCGT Units within that CCGT
Module can only be amended such that the CCGT Module comprises different CCGT
Units for a particular Operational Day if the relevant notification is given by 1100 hours
on the day prior to the Operational Day in which the amendment is to take effect. No
subsequent amendment may be made to the CCGT Units comprising the CCGT
Module in respect of that particular Operational Day.

Issue 5 Revision 19 BC1 30 September 2016


16 of 20
BC1.A.1.6.6 In the case of a CCGT Module Matrix submitted (or deemed to be submitted) as part of the
other data for CCGT Modules, the output of the CCGT Module at any given instructed MW
output must reflect the details given in the CCGT Module Matrix. It is accepted that in cases
of change in MW in response to instructions issued by NGET there may be a transitional
variance to the conditions reflected in the CCGT Module Matrix. In achieving an instruction
the range of number of CCGT Units envisaged in moving from one MW output level to the
other must not be departed from. Each Generator shall notify NGET as soon as practicable
after the event of any such variance. It should be noted that there is a provision above for the
Generator to revise the CCGT Module Matrix, subject always to the other provisions of this
BC1;
BC1.A.1.6.7 Subject as provided above, NGET will rely on the CCGT Units specified in such CCGT
Module Matrix running as indicated in the CCGT Module Matrix when it issues an
instruction in respect of the CCGT Module;
BC1.A.1.6.8 Subject as provided in BC1.A.1.6.5 above, any changes to the CCGT Module Matrix must
be notified immediately to NGET in accordance with the relevant provisions of BC1.
BC1.A.1.7 Cascade Hydro Scheme Matrix
BC1.A.1.7.1 A Cascade Hydro Scheme Matrix showing the performance of individual Generating Units
forming part of a Cascade Hydro Scheme in response to Bid-Offer Acceptance. An
example table is shown below:

Cascade Hydro Scheme Matrix example form

Plant Synchronises when offer is greater


than..
Generating Unit 1 ......MW
Generating Unit 2 ......MW
Generating Unit 3 ......MW
Generating Unit 4 ......MW
Generating Unit 5 ......MW

BC1.A.1.8 Power Park Module Availability Matrix


BC1.A.1.8.1 Power Park Module Availability Matrix showing the number of each type of Power Park
Units expected to be available is illustrated in the example form below. The Power Park
Module Availability Matrix is designed to achieve certainty in knowing the number of
Power Park Units Synchronised to meet the Physical Notification and to achieve a Bid-
Offer Acceptance by specifying which BM Unit each Power Park Module forms part of.
The Power Park Module Availability Matrix may have as many columns as are required to
provide information on the different make and model for each type of Power Park Unit in a
Power Park Module and as many rows as are required to provide information on the Power
Park Modules within each BM Unit. The description is required to assist identification of the
Power Park Units within the Power Park Module and correlation with data provided under
the Planning Code.

Issue 5 Revision 19 BC1 30 September 2016


17 of 20
Power Park Module Availability Matrix example form

BM Unit Name
Power Park Module [unique identifier]
POWER PARK POWER PARK UNITS
UNIT AVAILABILITY Type A Type B Type C Type D
Description
(Make/Model)
Number of units
Power Park Module [unique identifier]
POWER PARK POWER PARK UNITS
UNIT AVAILABILITY Type A Type B Type C Type D
Description
(Make/Model)
Number of units

BC1.A.1.8.2 In the absence of the correct submission of a Power Park Module Availability Matrix the
last submitted (or deemed submitted) Power Park Module Availability Matrix shall be
taken to be the Power Park Module Availability Matrix submitted hereunder.
BC1.A.1.8.3 NGET will rely on the Power Park Units, Power Park Modules and BM Units specified in
such Power Park Module Availability Matrix running as indicated in the Power Park
Module Availability Matrix when it issues an instruction in respect of the BM Unit.
BC1.A.1.8.4 Subject as provided in PC.A.3.2.4 any changes to Power Park Module or BM Unit
configuration, or availability of Power Park Units which affects the information set out in the
Power Park Module Availability Matrix must be notified immediately to NGET in
accordance with the relevant provisions of BC1. Initial notification may be by telephone. In
some circumstances, such as a significant re-configuration of a Power Park Module due to
an unplanned outage, a revised Power Park Module Availability Matrix must be supplied
on NGET's request.

Issue 5 Revision 19 BC1 30 September 2016


18 of 20
APPENDIX 2 - DATA TO BE MADE AVAILABLE BY NGET

BC1.A.2.1 Initial Day Ahead Demand Forecast


Normally by 09:00 hours each day, values (in MW) for each Settlement Period of the next
following Operational Day of the following data items:-
(i) Initial forecast of National Demand;
(II) Initial forecast of Demand for a number of predetermined constraint groups.
BC1.A.2.2 Initial Day Ahead Market Information
Normally by 12:00 hours each day, values (in MW) for each Settlement Period of the next
following Operational Day of the following data items:-
(i) Initial National Indicated Margin
This is the difference between the sum of BM Unit MELs and the forecast of National
Electricity Transmission System Demand.
(ii) Initial National Indicated Imbalance
This is the difference between the sum of Physical Notifications for BM Units
comprising Generating Units (as defined in the Glossary and Definitions and not
limited by BC1.2) or CCGT Modules or Power Park Modules and the forecast of
National Electricity Transmission System Demand.
(iii) Forecast of National Electricity Transmission System Demand.

BC1.A.2.3 Current Day And Day Ahead Updated Market Information


Data will normally be made available by the times shown below for the associated periods of
time:

Target Data
Release Time Period Start Time Period End Time
02:00 02:00 D0 05:00 D+1
10:00 10:00 D0 05:00 D+1
16:00 05:00 D+1 05:00 D+2
16:30 16:30 D0 05:00 D+1
22:00 22:00 D0 05:00 D+2

In this table, D0 refers to the current day, D+1 refers to the next day and D+2 refers to the
day following D+1.
In all cases, data will be hourly average MW values calculated by NGET. Information to be
released includes:

National Information
(i) National Indicated Margin;
(ii) National Indicated Imbalance;
(iii) Updated forecast of National Electricity Transmission System Demand.

Issue 5 Revision 19 BC1 30 September 2016


19 of 20
Constraint Boundary Information (For Each Constraint Boundary)
(i) Indicated Constraint Boundary Margin;
This is the difference between the Constraint Boundary Transfer limit and the difference
between the sum of BM Unit MELs and the forecast of local Demand within the
constraint boundary.
(ii) Local Indicated Imbalance;
This is the difference between the sum of Physical Notifications for BM Units
comprising Generating Units (as defined in the Glossary and Definitions and not
limited by BC1.2) or CCGT Modules or Power Park Modules and the forecast of local
Demand within the constraint boundary.
(iii) Updated forecast of the local Demand within the constraint boundary.

< END OF BALANCING CODE NO. 1 >

Issue 5 Revision 19 BC1 30 September 2016


20 of 20
BALANCING CODE NO. 2
(BC2)

POST GATE CLOSURE PROCESS

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


BC2.1 INTRODUCTION .....................................................................................................................................3
BC2.2 OBJECTIVE .............................................................................................................................................3
BC2.3 SCOPE ....................................................................................................................................................3
BC2.4 INFORMATION USED .............................................................................................................................3
BC2.5 PHYSICAL OPERATION OF BM UNITS ................................................................................................4
BC2.5.1 Accuracy Of Physical Notifications ...............................................................................................4
BC2.5.2 Synchronising And De-Synchronising Times ...............................................................................5
BC2.5.3 Revisions To BM Unit Data...........................................................................................................6
BC2.5.4 Operation In The Absence Of Instructions From NGC .................................................................7
BC2.5.5 Commencement Or Termination Of Participation In The Balancing Mechanism .........................8
BC2.6 COMMUNICATIONS ...............................................................................................................................9
BC2.6.1 Normal Communications With Control Points ..............................................................................9
BC2.6.2 Communication With Control Points In Emergency Circumstances...........................................10
BC2.6.3 Communication With Network Operators In Emergency Circumstances ...................................10
BC2.6.4 Communication With Externally Interconnected System Operators In Emergency
Circumstances ............................................................................................................................................10
BC2.6.5 Communications During Planned Outages Of Electronic Data Communication Facilities .........10
BC2.7 BID-OFFER ACCEPTANCES ...............................................................................................................10
BC2.7.1 Acceptance Of Bids And Offers By NGC ....................................................................................10
BC2.7.2 Consistency With Export And Import Limits, Qpns And Dynamic Parameters ..........................11
BC2.7.3 Confirmation And Rejection Of Acceptances .............................................................................11
BC2.7.4 Action Required From BM Participants ......................................................................................12
BC2.7.5 Additional Action Required From Generators .............................................................................12
BC2.8 ANCILLARY SERVICES .......................................................................................................................12
BC2.8.1 Call-Off Of Ancillary Services By NGET .....................................................................................12
BC2.8.2 Consistency With Export And Import Limits, Qpns And Dynamic Parameters ..........................13
BC2.8.3 Rejection Of Ancillary Service Instructions .................................................................................13
BC2.8.4 Action Required From BM Units .................................................................................................13
BC2.8.5 Reactive Despatch Network Restrictions ...................................................................................13
BC2.9 EMERGENCY CIRCUMSTANCES .......................................................................................................14
BC2.9.1 Emergency Actions .....................................................................................................................14
BC2.9.2 Implementation Of Emergency Instructions................................................................................14
BC2.9.3 Examples of Emergency Instructions .........................................................................................15
Issue 5 Revision 15 BC2 03 February 2016
i
BC2.9.4 Maintaining Adequate System And Localised NRAPM (Negative Reserve Active Power
Margin) ....................................................................................................................................................... 16
BC2.9.5 Maintaining Adequate Frequency Sensitive Generating Units .................................................. 17
BC2.9.6 Emergency Assistance To And From External Systems ........................................................... 18
BC2.9.7 Unplanned Outages Of Electronic Communication And Computing Facilities .......................... 18
BC2.10 OTHER OPERATIONAL INSTRUCTIONS AND NOTIFICATIONS ................................................... 19
BC2.11 LIAISON WITH GENERATORS FIR RISK OF TRIP AND AVR TESTING ........................................ 19
BC2.12 LIAISON WITH EXTERNALLY INTERCONNECTED SYSTEM OPERATORS ................................ 20
APPENDIX 1 - FORM OF BID-OFFER ACCEPTANCES ................................................................................. 21
APPENDIX 2 - TYPE AND FORM OF ANCILLARY SERVICE INSTRUCTIONS ............................................ 23
APPENDIX 3 - SUBMISSION OF REVISED MVAr CAPABILITY ..................................................................... 28
APPENDIX 3 ANNEXURE 1 ...................................................................................................................... 29
APPENDIX 3 ANNEXURE 2 ...................................................................................................................... 30
APPENDIX 3 ANNEXURE 3 ...................................................................................................................... 31
APPENDIX 4 - SUBMISSION OF AVAILABILITY OF FREQUENCY SENSITIVE MODE ............................... 32
APPENDIX 4 ANNEXURE 1 ...................................................................................................................... 33

Issue 5 Revision 15 BC2 03 February 2016


ii
BC2.1 INTRODUCTION
Balancing Code No 2 (BC2) sets out the procedure for:
(a) the physical operation of BM Units and Generating Units in the absence of any
instructions from NGET;
(b) the acceptance by NGET of Balancing Mechanism Bids and Offers,
(c) the calling off by NGET of Ancillary Services;
(d) the issuing and implementation of Emergency Instructions; and
(e) the issuing by NGET of other operational instructions and notifications.
In addition, BC2 deals with any information exchange between NGET and BM Participants
or specific Users that takes place after Gate Closure.
In this BC2, consistent shall be construed as meaning to the nearest integer MW level.
In this BC2, references to a BM Unit returning to its Physical Notification shall take
account of any Bid-Offer Acceptances already issued to the BM Unit in accordance with
BC2.7 and any Emergency Instructions already issued to the BM Unit or Generating Unit
in accordance with BC2.9.

BC2.2 OBJECTIVE
The procedure covering the operation of the Balancing Mechanism and the issuing of
instructions to Users is intended to enable NGET as far as possible to maintain the integrity
of the National Electricity Transmission System together with the security and quality of
supply.
Where reference is made in this BC2 to Generating Units (unless otherwise stated) it only
applies:
(a) to each Generating Unit which forms part of the BM Unit of a Cascade Hydro
Scheme; and
(b) at an Embedded Exemptable Large Power Station where the relevant Bilateral
Agreement specifies that compliance with BC2 is required:
(i) to each Generating Unit, or
(ii) to each Power Park Module where the Power Station comprises Power Park
Modules.

BC2.3 SCOPE
BC2 applies to NGET and to Users, which in this BC2 means:-
(a) BM Participants;
(b) Externally Interconnected System Operators, and
(c) Network Operators.

BC2.4 INFORMATION USED


BC2.4.1 The information which NGET shall use, together with the other information available to it, in
assessing:
(a) which bids and offers to accept;
(b) which BM Units and/or Generating Units to instruct to provide Ancillary Services;
(c) the need for and formulation of Emergency Instructions; and
(d) other operational instructions and notifications which NGET may need to issue
Issue 5 Revision 19 BC2 30 September 2016
3 of 33
will be:
(a) the Physical Notification and Bid-Offer Data submitted under BC1;
(b) Export and Import Limits, QPNs, and Joint BM Unit Data in respect of that BM Unit
and/or Generating Unit supplied under BC1 (and any revisions under BC1 and BC2 to
the data); and
(c) Dynamic Parameters submitted or revised under this BC2.
BC2.4.2 As provided for in BC1.5.4, NGET will monitor the total of the Maximum Export Limit
component of the Export and Import Limits against forecast Demand and the Operating
Margin and will take account of Dynamic Parameters to see whether the anticipated level
of System Margin is insufficient. This will reflect any changes in Export and Import Limits
which have been notified to NGET, and will reflect any Demand Control which has also
been so notified. NGET may issue new or revised National Electricity Transmission
System Warnings Electricity Margin Notice or High Risk of Demand Reduction in
accordance with BC1.5.4.

BC2.5 PHYSICAL OPERATION OF BM UNITS


BC2.5.1 Accuracy Of Physical Notifications
As described in BC1.4.2(a), Physical Notifications must represent the BM Participants
best estimate of expected input or output of Active Power and shall be prepared in
accordance with Good Industry Practice.
Each BM Participant must, applying Good Industry Practice, ensure that each of its BM
Units follows the Physical Notification in respect of that BM Unit (and each of its
Generating Units follows the Physical Notification in the case of Physical Notifications
supplied under BC1.4.2(a)(2)) that is prevailing at Gate Closure (the data in which will be
utilised in producing the Final Physical Notification Data in accordance with the BSC)
subject to variations arising from:
(a) the issue of Bid-Offer Acceptances which have been confirmed by the BM
Participant; or
(b) instructions by NGET in relation to that BM Unit (or a Generating Unit) which require,
or compliance with which would result in, a variation in output or input of that BM Unit
(or a Generating Unit); or
(c) compliance with provisions of BC1, BC2 or BC3 which provide to the contrary.
Except where variations from the Physical Notification arise from matters referred to at
(a),(b or (c) above, in respect only of BM Units (or Generating Units) powered by an
Intermittent Power Source, where there is a change in the level of the Intermittent Power
Source from that forecast and used to derive the Physical Notification, variations from the
Physical Notification prevailing at Gate Closure may, subject to remaining within the
Registered Capacity, occur providing that the Physical Notification prevailing at Gate
Closure was prepared in accordance with Good Industry Practice.
If variations and/or instructions as described in (a),(b) or (c) apply in any instance to BM
Units (or Generating Units) powered by an Intermittent Power Source (e.g. a Bid Offer
Acceptance is issued in respect of such a BM Unit and confirmed by the BM Participant)
then such provisions will take priority over the third paragraph of BC2.5.1 above such that
the BM Participant must ensure that the Physical Notification as varied in accordance with
(a), (b) or (c) above applies and must be followed, subject to this not being prevented as a
result of an unavoidance event as described below.

Issue 5 Revision 19 BC2 30 September 2016


4 of 33
For the avoidance of doubt, this gives rise to an obligation on each BM Participant (applying
Good Industry Practice) to ensure that each of its BM Units (and Generating Units),
follows the Physical Notifications prevailing at Gate Closure as amended by such
variations and/or instructions unless in relation to any such obligation it is prevented from so
doing as a result of an unavoidable event (existing or anticipated) in relation to that BM Unit
(or a Generating Unit) which requires a variation in output or input of that BM Unit (or a
Generating Unit).
Examples (on a non-exhaustive basis) of such an unavoidable event are:
plant breakdowns;
events requiring a variation of input or output on safety grounds (relating to
personnel or plant);
events requiring a variation of input or output to maintain compliance with the
relevant Statutory Water Management obligations; and
uncontrollable variations in output of Active Power.
Any anticipated variations in input or output post Gate Closure from the Physical
Notification for a BM Unit (or a Generating Unit) prevailing at Gate Closure (except for
those arising from instructions as outlined in (a), (b) or (c) above) must be notified to NGET
without delay by the relevant BM Participant (or the relevant person on its behalf). For the
avoidance of doubt, where a change in the level of the Intermittent Power Source from that
forecast and used to derive the Physical Notification results in the Shutdown or
Shutdown of part of the BM Unit (or Generating Unit), the change must be notified to
NGET without delay by the relevant BM Participant (or the relevant person on its behalf).
Implementation of this notification should normally be achieved by the submission of
revisions to the Export and Import Limits in accordance with BC2.5.3 below.
BC2.5.2 Synchronising And De-Synchronising Times
BC2.5.2.1 The Final Physical Notification Data provides indicative Synchronising and De-
Synchronising times to NGET in respect of any BM Unit which is De-Synchronising or is
anticipated to be Synchronising post Gate Closure.
Any delay of greater than five minutes to the Synchronising or any advancement of greater
than five minutes to the De-Synchronising of a BM Unit must be notified to NGET without
delay by the submission of a revision of the Export and Import Limits.
BC2.5.2.2 Except in the circumstances provided for in BC2.5.2.3, BC2.5.2.4, BC2.5.5.1 or BC2.9, no
BM Unit (nor a Generating Unit) is to be Synchronised or De-Synchronised unless:-
(a) a Physical Notification had been submitted to NGET prior to Gate Closure indicating
that a Synchronisation or De-Synchronisation is to occur; or
(b) NGET has issued a Bid-Offer Acceptance requiring Synchronisation or De-
Synchronisation of that BM Unit (or a Generating Unit).
BC2.5.2.3 BM Participants must only Synchronise or De-Synchronise BM Units (or a Generating
Unit);
(a) at the times indicated to NGET, or
(b) at times consistent with variations in output or input arising from provisions described in
BC2.5.1,
(within a tolerance of +/- 5 minutes) or unless that occurs automatically as a result of
Operational Intertripping or Low Frequency Relay operations or an Ancillary Service
pursuant to an Ancillary Services Agreement

Issue 5 Revision 19 BC2 30 September 2016


5 of 33
BC2.5.2.4 De-Synchronisation may also take place without prior notification to NGET as a result of
plant breakdowns or if it is done purely on safety grounds (relating to personnel or plant). If
that happens NGET must be informed immediately that it has taken place and a revision to
Export and Import Limits must be submitted in accordance with BC2.5.3.3. Following any
De-Synchronisation occurring as a result of plant failure, no Synchronisation of that BM
Unit (or a Generating Unit) is to take place without NGETs agreement, such agreement
not to be unreasonably withheld.
In the case of Synchronisation following an unplanned De-Synchronisation within the
preceding 15 minutes, a minimum of 5 minutes notice of its intention to Synchronise should
normally be given to NGET (via a revision to Export and Import Limits). In the case of any
other unplanned De-Synchronisation where the User plans to Synchronise before the
expiry of the current Balancing Mechanism period, a minimum of 15 minutes notice of
Synchronisation should normally be given to NGET (via a revision to Export and Import
Limits). In addition, the rate at which the BM Unit is returned to its Physical Notification is
not to exceed the limits specified in BC1, Appendix 1 without NGETs agreement.
NGET will either agree to the Synchronisation or issue a Bid-Offer Acceptance in
accordance with BC2.7 to delay the Synchronisation. NGET may agree to an earlier
Synchronisation if System conditions allow.
BC2.5.2.5 Notification Of Times To Network Operators
NGET will make changes to the Synchronising and De-Synchronising times available to
each Network Operator, but only relating to BM Units Embedded within its User System
and those BM Units directly connected to the National Electricity Transmission System
which NGET has identified under OC2 and/or BC1 as being those which may, in the
reasonable opinion of NGET, affect the integrity of that User System and shall inform the
relevant BM Participant that it has done so, identifying the BM Unit concerned.
Each Network Operator must notify NGET of any changes to its User System Data as
soon as practicable in accordance with BC1.6.1(c).
BC2.5.3 Revisions To BM Unit Data
Following Gate Closure for any Settlement Period, no changes to the Physical
Notification, to the QPN data or to Bid-Offer Data for that Settlement Period may be
submitted to NGET.
BC2.5.3.1 At any time, any BM Participant (or the relevant person on its behalf) may, in respect of any
of its BM Units, submit to NGET the data listed in BC1, Appendix 1 under the heading of
Dynamic Parameters from the Control Point of its BM Unit to amend the data already held
by NGET (including that previously submitted under this BC2.5.3.1) for use in preparing for
and operating the Balancing Mechanism. The change will take effect from the time that it is
received by NGET. For the avoidance of doubt, the Dynamic Parameters submitted to
NGET under BC1.4.2(e) are not used within the current Operational Day. The Dynamic
Parameters submitted under this BC2.5.3.1 shall reasonably reflect the true current
operating characteristics of the BM Unit and shall be prepared in accordance with Good
Industry Practice.
Following the Operational Intertripping of a System to Generating Unit or a System to
CCGT Module, the BM Participant shall as soon as reasonably practicable re-declare its
MEL to reflect more accurately its output capability.
BC2.5.3.2 Revisions to Export and Import Limits or Other Relevant Data supplied (or revised) under
BC1 must be notified to NGET without delay as soon as any change becomes apparent to
the BM Participant (or the relevant person on its behalf) via the Control Point for the BM
Unit (or a Generating Unit) to ensure that an accurate assessment of BM Unit (or a
Generating Unit) capability is available to NGET at all times. These revisions should be
prepared in accordance with Good Industry Practice and may be submitted by use of
electronic data communication facilities or by telephone.

Issue 5 Revision 19 BC2 30 September 2016


6 of 33
BC2.5.3.3 Revisions to Export and Import Limits must be made by a BM Participant (or the relevant
person on its behalf) via the Control Point in the event of any De-Synchronisation of a BM
Unit (or a Generating Unit) in the circumstances described in BC2.5.2.4 if the BM Unit (or a
Generating Unit) is no longer available for any period of time. Revisions must also be
submitted in the event of plant failures causing a reduction in input or output of a BM Unit (or
a Generating Unit) even if that does not lead to De-Synchronisation. Following the
correction of a plant failure, the BM Participant (or the relevant person on its behalf) must
notify NGET via the Control Point of a revision to the Export and Import Limits, if
appropriate, of the BM Unit (or a Generating Unit), using reasonable endeavours to give a
minimum of 5 minutes notice of its intention to return to its Physical Notification. The rate at
which the BM Unit (or a Generating Unit) is returned to its Physical Notification is not to
exceed the limits specified in BC1, Appendix 1 without NGETs agreement.
BC2.5.4 Operation In The Absence Of Instructions From NGET
In the absence of any Bid-Offer Acceptances, Ancillary Service instructions issued
pursuant to BC2.8 or Emergency Instructions issued pursuant to BC2.9:
(a) as provided for in BC3, each Synchronised Genset producing Active Power must
operate at all times in Limited Frequency Sensitive Mode (unless instructed in
accordance with BC3.5.4 to operate in Frequency Sensitive Mode);
(b) (i) in the absence of any MVAr Ancillary Service instructions, the MVAr output of
each Synchronised Genset located Onshore should be 0 MVAr upon
Synchronisation at the circuit-breaker where the Genset is Synchronised. For
the avoidance of doubt, in the case of a Genset located Onshore comprising of
Non-Synchronous Generating Units, Power Park Modules or DC Converters
the steady state tolerance allowed in CC.6.3.2(b) may be applied
(ii) In the absence of any MVAr Ancillary Service instructions, the MVAr output of
each Synchronised Genset comprising Synchronous Generating Units located
Offshore should be 0MVAr at the Grid Entry Point upon Synchronisation. For
the avoidance of doubt, in the case of a Genset located Offshore comprising of
Non-Synchronous Generating Units, Power Park Modules or DC Converters
the steady state tolerance allowed in CC.6.3.2(e) may be applied;
(c) (i) subject to the provisions of 2.5.4(c) (ii) and 2.5.4 (c) (iii) below, the excitation
system or the voltage control system of a Genset located Offshore which has
agreed an alternative Reactive Power capability range under CC.6.3.2 (e) (iii) or a
Genset located Onshore, unless otherwise agreed with NGET, must be operated
only in its constant terminal voltage mode of operation with VAR limiters in service,
with any constant Reactive Power output control mode or constant Power Factor
output control mode always disabled, unless agreed otherwise with NGET. In the
event of any change in System voltage, a Generator must not take any action to
override automatic MVAr response which is produced as a result of constant
terminal voltage mode of operation of the automatic excitation control system
unless instructed otherwise by NGET or unless immediate action is necessary to
comply with Stability Limits or unless constrained by plant operational limits or
safety grounds (relating to personnel or plant);
(ii) In the case of all Gensets comprising Non-Synchronous Generating Units, DC
Converters and Power Park Modules that are located Offshore and which have
agreed an alternative Reactive Power capability range under CC.6.3.2 (e) (iii), or
that are located Onshore only when operating below 20 % of the Rated MW
output, the voltage control system shall maintain the reactive power transfer at the
Grid Entry Point (or User System Entry Point if Embedded) to 0 MVAr. For the
avoidance of doubt the relevant steady state tolerance allowed in CC.6.3.2(b) or
CC.6.3.2 (e) may be applied. In the case of any such Gensets comprising current
source DC Converter technology or comprising Power Park Modules connected
to the Total System by a current source DC Converter when operating at any
power output the voltage control system shall maintain the reactive power transfer

Issue 5 Revision 19 BC2 30 September 2016


7 of 33
at the Grid Entry Point (or User System Entry Point if Embedded) to 0 MVAr.
For the avoidance of doubt the relevant steady state tolerance allowed in
CC.6.3.2(b) or CC.6.3.2 (c) (i) may be applied.
(iii) In the case of all Gensets located Offshore which are not subject to the
requirements of BC2.5.4 (c) (i) or BC2.5.4 (c) (ii) the control system shall maintain
the Reactive Power transfer at the Offshore Grid Entry Point at 0MVAr. For the
avoidance of doubt the steady state tolerance allowed by CC.6.3.2 (e) may be
applied.
(d) In the absence of any MVAr Ancillary Service instructions,
(i) the MVAr output of each Genset located Onshore should be 0 MVAr immediately
prior to De-Synchronisation at the circuit-breaker where the Genset is
Synchronised, other than in the case of a rapid unplanned De-Synchronisation
or in the case of a Genset comprising of Non-Synchronous Generating Units,
Power Park Modules or DC Converters which is operating at less than 20% of its
Rated MW output where the requirements of BC2.5.4 (c) part (ii) apply, or;
(ii) the MVAr output of each Genset located Offshore should be 0MVAr immediately
prior to De-Synchronisation at the Offshore Grid Entry Point, other than in the
case of a rapid unplanned De-Synchronisation or in the case of a Genset
comprising of Non-Synchronous Generating Units, Power Park Modules or DC
Converters which is operating at less than 20% of its Rated MW output and which
has agreed an alternative Reactive Power capability range under CC.6.3.2 (e) (iii)
where the requirements of BC2.5.4 (c) (ii) apply.
(e) a Generator should at all times operate its CCGT Units in accordance with the
applicable CCGT Module Matrix;
(f) in the case of a Range CCGT Module, a Generator must operate that CCGT Module
so that power is provided at the single Grid Entry Point identified in the data given
pursuant to PC.A.3.2.1 or at the single Grid Entry Point to which NGET has agreed
pursuant to BC1.4.2(f);
(g) in the event of the System Frequency being above 50.3Hz or below 49.7Hz, BM
Participants must not commence any reasonably avoidable action to regulate the input
or output of any BM Unit in a manner that could cause the System Frequency to
deviate further from 50Hz without first using reasonable endeavours to discuss the
proposed actions with NGET. NGET shall either agree to these changes in input or
output or issue a Bid-Offer Acceptance in accordance with BC2.7 to delay the change.
(h) a Generator should at all times operate its Power Park Units in accordance with the
applicable Power Park Module Availability Matrix.
BC2.5.5 Commencement Or Termination Of Participation In The Balancing Mechanism
BC2.5.5.1 In the event that a BM Participant in respect of a BM Unit with a Demand Capacity with a
magnitude of less than 50MW in NGETs Transmission Area or less than 10MW in
SHETLs Transmission Area or less than 30MW in SPTs Transmission Area or
comprising Generating Units (as defined in the Glossary and Definitions and not limited by
BC2.2) and/or CCGT Modules and/or Power Park Modules at a Small Power Station
notifies NGET at least 30 days in advance that from a specified Operational Day it will:
(a) no longer submit Bid-Offer Data under BC1.4.2(d), then with effect from that
Operational Day that BM Participant no longer has to meet the requirements of
BC2.5.1 nor the requirements of CC.6.5.8(b) in relation to that BM Unit. Also, with effect
from that Operational Day, any defaulted Physical Notification and defaulted Bid-
Offer Data in relation to that BM Unit arising from the Data Validation, Consistency
and Defaulting Rules will be disregarded and the provisions of BC2.5.2 will not apply;
(b) submit Bid-Offer Data under BC1.4.2(d), then with effect from that Operational Day
that BM Participant will need to meet the requirements of BC2.5.1 and the
requirements of CC.6.5.8(b) in relation to that BM Unit.
Issue 5 Revision 19 BC2 30 September 2016
8 of 33
BC2.5.5.2 In the event that a BM Participant in respect of a BM Unit with a Demand Capacity with a
magnitude of 50MW or more in NGETs Transmission Area or 10MW or more in SHETLs
Transmission Area or 30MW or more in SPTs Transmission Area or comprising
Generating Units (as defined in the Glossary and Definitions and not limited by BC2.2)
and/or CCGT Modules and/or Power Park Modules at a Medium Power Station or Large
Power Station notifies NGET at least 30 days in advance that from a specified Operational
Day it will:
(a) no longer submit Bid-Offer Data under BC1.4.2(d), then with effect from that
Operational Day that BM Participant no longer has to meet the requirements of
CC.6.5.8(b) in relation to that BM Unit; Also, with effect from that Operational Day, any
defaulted Bid-Offer Data in relation to that BM Unit arising from the Data Validation,
Consistency and Defaulting Rules will be disregarded;
(b) submit Bid-Offer Data under BC1.4.2(d), then with effect from that Operational Day
that BM Participant will need to meet the requirements of CC.6.5.8(b) in relation to that
BM Unit.

BC2.6 COMMUNICATIONS
Electronic communications are always conducted in GMT. However, the input of data and
display of information to Users and NGET and all other communications are conducted in
London time.
BC2.6.1 Normal Communication With Control Points
(a) With the exception of BC2.6.1(c) below, Bid-Offer Acceptances and, unless otherwise
agreed with NGET, Ancillary Service instructions shall be given by automatic logging
device and will be given to the Control Point for the BM Unit. For all Planned
Maintenance Outages the provisions of BC2.6.5 will apply. For Generating Units
communications under BC2 shall be by telephone unless otherwise agreed by NGET
and the User.
(b) Bid-Offer Acceptances and Ancillary Service instructions must be formally
acknowledged immediately by the BM Participant (or the relevant person on its behalf)
via the Control Point for the BM Unit or Generating Unit in respect of that BM Unit or
that Generating Unit. The acknowledgement and subsequent confirmation or rejection,
within two minutes of receipt, is normally given electronically by automatic logging
device. If no confirmation or rejection is received by NGET within two minutes of the
issue of the Bid-Offer Acceptance, then NGET will contact the Control Point for the
BM Unit by telephone to determine the reason for the lack of confirmation or rejection.
Any rejection must be given in accordance with BC2.7.3 or BC2.8.3.
(c) In the event of a failure of the logging device or a NGET computer system outage, Bid-
Offer Acceptances and instructions will be given, acknowledged, and confirmed or
rejected by telephone. The provisions of BC2.9.7 are also applicable.
(d) In the event that in carrying out the Bid-Offer Acceptances or providing the Ancillary
Services, or when operating at the level of the Final Physical Notification Data as
provided in BC2.5.1, an unforeseen problem arises, caused on safety grounds (relating
to personnel or plant), NGET must be notified without delay by telephone.
(e) The provisions of BC2.5.3 are also relevant.
(f) Submissions of revised MVAr capability may be made by facsimile transmission, using
the format given in Appendix 3 to BC2.
(g) Communication will normally be by telephone for any purpose other than Bid-Offer
Acceptances, in relation to Ancillary Services or for revisions of MVAr Data.

Issue 5 Revision 19 BC2 30 September 2016


9 of 33
(h) Submissions of revised availability of Frequency Sensitive Mode may be made by
facsimile transmission, using the format given in Appendix 4 to BC2. This process
should only be used for technical restrictions to the availability of Frequency Sensitive
Mode.
BC2.6.2 Communication With Control Points In Emergency Circumstances
NGET will issue Emergency Instructions direct to the Control Point for each BM Unit [or
Generating Unit] in Great Britain. Emergency Instructions to a Control Point will
normally be given by telephone (and will include an exchange of operator names).
BC2.6.3 Communication With Network Operators In Emergency Circumstances
NGET will issue Emergency Instructions direct to the Network Operator at each Control
Centre in relation to special actions and Demand Control. Emergency Instructions to a
Network Operator will normally be given by telephone (and will include an exchange of
operator names). OC6 contains further provisions relating to Demand Control instructions.
BC2.6.4 Communication With Externally Interconnected System Operators In Emergency
Circumstances
NGET will issue Emergency Instructions directly to the Externally Interconnected
System Operator at each Control Centre. Emergency Instructions to an Externally
Interconnected System Operator will normally be given by telephone (and will include an
exchange of operator names).
BC2.6.5 Communications During Planned Outages Of Electronic Data Communication Facilities
Planned Maintenance Outages will normally be arranged to take place during periods of
low data transfer activity. Upon any such Planned Maintenance Outage in relation to a post
Gate Closure period:-
(a) BM Participants should operate in relation to any period of time in accordance with the
Physical Notification prevailing at Gate Closure current at the time of the start of the
Planned Maintenance Outage in relation to each such period of time. Such operation
shall be subject to the provisions of BC2.5.1, which will apply as if set out in this
BC2.6.5. No further submissions of BM Unit Data (other than data specified in
BC1.4.2(c) and BC1.4.2(e)) should be attempted or Generating Unit Data. Plant failure
or similar problems causing significant deviation from Physical Notification should be
notified to NGET by the submission of a revision to Export and Import Limits in
relation to the BM Unit or Generating Unit so affected;
(b) during the outage, revisions to the data specified in BC1.4.2(c) and BC1.4.2(e) may be
submitted. Communication between Users Control Points and NGET during the
outage will be conducted by telephone;
(c) NGET will issue Bid-Offer Acceptances by telephone; and
(d) no data will be transferred from NGET to the BMRA until the communication facilities
are re-established.
(e) The provisions of BC2.9.7 may also be relevant.

BC2.7 BID-OFFER ACCEPTANCES


BC2.7.1 Acceptance Of Bids And Offers By NGET
Bid-Offer Acceptances may be issued to the Control Point at any time following Gate
Closure. Any Bid-Offer Acceptance will be consistent with the Dynamic Parameters,
QPNs, Export and Import Limits, and Joint BM Unit Data of the BM Unit in so far as the
Balancing Mechanism timescales will allow (see BC2.7.2).
(a) NGET is entitled to assume that each BM Unit is available in accordance with the BM
Unit Data submitted unless and until it is informed of any changes.

Issue 5 Revision 19 BC2 30 September 2016


10 of 33
(b) Bid-Offer Acceptances sent to the Control Point will specify the data necessary to
define a MW profile to be provided (ramp rate break-points are not normally explicitly
sent to the Control Point) and to be achieved consistent with the respective BM Unit's
Export and Import Limits, QPNs and Joint BM Unit Data provided or modified under
BC1 or BC2, and Dynamic Parameters given under BC2.5.3 or, if agreed with the
relevant User, such rate within those Dynamic Parameters as is specified by NGET in
the Bid-Offer Acceptances.
(c) All Bid-Offer Acceptances will be deemed to be at the current "Target Frequency",
namely where a Genset is in Frequency Sensitive Mode they refer to target output at
Target Frequency.
(d) The form of and terms to be used by NGET in issuing Bid-Offer Acceptances together
with their meanings are set out in Appendix 1 in the form of a non-exhaustive list of
examples.
BC2.7.2 Consistency With Export And Import Limits, QPNs And Dynamic Parameters
(a) Bid-Offer Acceptances will be consistent with the Export and Import Limits, QPNs,
and Joint BM Unit Data provided or modified under BC1 or BC2 and the Dynamic
Parameters provided or modified under BC2. Bid-Offer Acceptances may also
recognise Other Relevant Data provided or modified under BC1 or BC2
(b) In the case of consistency with Dynamic Parameters this will be limited to the time until
the end of the Settlement Period for which Gate Closure has most recently occurred.
If NGET intends to issue a Bid-Offer Acceptance covering a period after the end of
the Settlement Period for which Gate Closure has most recently occurred, based
upon the then submitted Dynamic Parameters, QPNs, Export and Import Limits,
Bid-Offer Data and Joint BM Unit Data applicable to that period, NGET will indicate
this to the BM Participant at the Control Point for the BM Unit. The intention will then
be reflected in the issue of a Bid-Offer Acceptance to return the BM Unit to its
previously notified Physical Notification after the relevant Gate Closure provided the
submitted data used to formulate this intention has not changed and subject to System
conditions which may affect that intention. Subject to that, assumptions regarding Bid-
Offer Acceptances may be made by BM Participants for Settlement Periods for
which Gate Closure has not yet occurred when assessing consistency with Dynamic
Parameters in Settlement Periods for which Gate Closure has occurred. If no such
subsequent BidOffer Acceptance is issued, the original Bid-Offer Acceptance will
include an instantaneous return to Physical Notification at the end of the Balancing
Mechanism period.
BC2.7.3 Confirmation And Rejection Of Acceptances
Bid-Offer Acceptances may only be rejected by a BM Participant :
(a) on safety grounds (relating to personnel or plant) as soon as reasonably possible and in
any event within five minutes; or
(b) because they are not consistent with the Export and Import Limits, QPNs, Dynamic
Parameters or Joint BM Unit Data applicable at the time of issue of the Bid-Offer
Acceptance.
A reason must always be given for rejection by telephone.
Where a Bid-Offer Acceptance is not confirmed within two minutes or is rejected, NGET
will seek to contact the Control Point for the BM Unit. NGET must then, within 15 minutes
of issuing the Bid-Offer Acceptance, withdraw the Bid-Offer Acceptance or log the Bid-
Offer Acceptance as confirmed. NGET will only log a rejected Bid-Offer Acceptance as
confirmed following discussion and if the reason given is, in NGETs reasonable opinion, not
acceptable and NGET will inform the BM Participant accordingly.

Issue 5 Revision 19 BC2 30 September 2016


11 of 33
BC2.7.4 Action Required From BM Participants
(a) Each BM Participant in respect of its BM Units will comply in accordance with BC2.7.1
with all Bid-Offer Acceptances given by NGET with no more than the delay allowed for
by the Dynamic Parameters unless the BM Unit has given notice to NGET under the
provisions of BC2.7.3 regarding non-acceptance of a Bid-Offer Acceptance.
(b) Where a BM Units input or output changes in accordance with a Bid-Offer
Acceptance issued under BC2.7.1, such variation does not need to be notified to
NGET in accordance with BC2.5.1.
(c) In the event that while carrying out the Bid-Offer Acceptance an unforeseen problem
arises caused by safety reasons (relating to personnel or plant), NGET must be notified
immediately by telephone and this may lead to revision of BM Unit Data in accordance
with BC2.5.3
BC2.7.5 Additional Action Required From Generators
(a) When complying with Bid-Offer Acceptances for a CCGT Module a Generator will
operate its CCGT Units in accordance with the applicable CCGT Module Matrix.
(b) When complying with Bid-Offer Acceptances for a CCGT Module which is a Range
CCGT Module, a Generator must operate that CCGT Module so that power is
provided at the single Grid Entry Point identified in the data given pursuant to
PC.A.3.2.1 or at the single Grid Entry Point to which NGET has agreed pursuant to
BC1.4.2 (f).
(c) On receiving a new MW Bid-Offer Acceptance, no tap changing shall be carried out to
change the MVAr output unless there is a new MVAr Ancillary Service instruction
issued pursuant to BC2.8.
(d) When complying with Bid-Offer Acceptances for a Power Park Module a Generator
will operate its Power Park Units in accordance with the applicable Power Park
Module Availability Matrix.

BC2.8 ANCILLARY SERVICES


This section primarily covers the call-off of System Ancillary Services. The provisions
relating to Commercial Ancillary Services will normally be covered in the relevant
Ancillary Services Agreement.
BC2.8.1 Call-Off Of Ancillary Services By NGET
(a) Ancillary Service instructions may be issued at any time.
(b) NGET is entitled to assume that each BM Unit (or Generating Unit) is available in
accordance with the BM Unit Data (or the Generating Unit Data) and data contained in
the Ancillary Services Agreement unless and until it is informed of any changes.
(c) Frequency control instructions may be issued in conjunction with, or separate from, a
Bid-Offer Acceptance.
(d) The form of and terms to be used by NGET in issuing Ancillary Service instructions
together with their meanings are set out in Appendix 2 in the form of a non-exhaustive
list of examples including Reactive Power and associated instructions.
(e) In the case of Generating Units that do not form part of a BM Unit any change in
Active Power as a result of, or required to enable, the provision of an Ancillary
Service will be dealt with as part of that Ancillary Service Agreement and/or
provisions under the CUSC.
(f) A System to Generator Operational Intertripping Scheme will be armed in
accordance with BC2.10.2(a)

Issue 5 Revision 19 BC2 30 September 2016


12 of 33
BC2.8.2 Consistency With Export And Import Limits, QPNs And Dynamic Parameters
Ancillary Service instructions will be consistent with the Export and Import Limits, QPNs,
and Joint BM Unit Data provided or modified under BC1 or BC2 and the Dynamic
Parameters provided or modified under BC2. Ancillary Service instructions may also
recognise Other Relevant Data provided or modified under BC1 or BC2
BC2.8.3 Rejection Of Ancillary Service Instructions
(a) Ancillary Service instructions may only be rejected, by automatic logging device or by
telephone, on safety grounds (relating to personnel or plant) or because they are not
consistent with the applicable Export and Import Limits, QPNs, Dynamic
Parameters, Joint BM Unit Data, Other Relevant Data or data contained in the
Ancillary Services Agreement and a reason must be given immediately for non-
acceptance.
(b) The issue of Ancillary Service instructions for Reactive Power will be made with due
regard to any resulting change in Active Power output. The instruction may be rejected
if it conflicts with any Bid-Offer Acceptance issued in accordance with BC2.7 or with
the Physical Notification.
(c) Where Ancillary Service instructions relating to Active Power and Reactive Power
are given together, and to achieve the Reactive Power output would cause the BM
Unit to operate outside Dynamic Parameters as a result of the Active Power
instruction being met at the same time, then the timescale of implementation of the
Reactive Power instruction may be extended to be no longer than the timescale for
implementing the Active Power instruction but in any case to achieve the MVAr
Ancillary Service instruction as soon as possible.
BC2.8.4 Action Required From BM Units
(a) Each BM Unit (or Generating Unit) will comply in accordance with BC2.8.1 with all
Ancillary Service instructions relating to Reactive Power properly given by NGET
within 2 minutes or such longer period as NGET may instruct, and all other Ancillary
Service instructions without delay, unless the BM Unit or Generating Unit has given
notice to NGET under the provisions of BC2.8.3 regarding non-acceptance of Ancillary
Service instructions.
(b) Each BM Unit may deviate from the profile of its Final Physical Notification Data, as
modified by any Bid-Offer Acceptances issued in accordance with BC2.7.1, only as a
result of responding to Frequency deviations when operating in Frequency Sensitive
Mode in accordance with the Ancillary Services Agreement.
(c) Each Generating Unit that does not form part of a BM Unit may deviate from the
profile of its Final Physical Notification Data where agreed by NGET and the User,
including but not limited to, as a result of providing an Ancillary Service in accordance
with the Ancillary Service Agreement.
(d) In the event that while carrying out the Ancillary Service instructions an unforeseen
problem arises caused by safety reasons (relating to personnel or plant), NGET must be
notified immediately by telephone and this may lead to revision of BM Unit Data or
Generating Unit Data in accordance with BC2.5.3.
BC2.8.5 Reactive Despatch Network Restrictions
Where NGET has received notification pursuant to the Grid Code that a Reactive Despatch
to Zero MVAr Network Restriction is in place with respect to any Embedded Generating
Unit, Embedded Power Park Module or DC Converter at an Embedded DC Converter
Station, then NGET will not issue any Reactive Despatch Instruction with respect to that
Generating Unit, Power Park Module or DC Converter until such time as notification is
given to NGET pursuant to the Grid Code that such Reactive Despatch to Zero MVAr
Network Restriction is no longer affecting that Generating Unit, Power Park Module or
DC Converter.

Issue 5 Revision 19 BC2 30 September 2016


13 of 33
BC2.9 EMERGENCY CIRCUMSTANCES
BC2.9.1 Emergency Actions
BC2.9.1.1 In certain circumstances (as determined by NGET in its reasonable opinion) it will be
necessary, in order to preserve the integrity of the National Electricity Transmission
System and any synchronously connected External System, for NGET to issue
Emergency Instructions. In such circumstances, it may be necessary to depart from
normal Balancing Mechanism operation in accordance with BC2.7 in issuing Bid-Offer
Acceptances. BM Participants must also comply with the requirements of BC3.
BC2.9.1.2 Examples of circumstances that may require the issue of Emergency Instructions include:-
(a) Events on the National Electricity Transmission System or the System of another
User; or
(b) the need to maintain adequate System and Localised NRAPM in accordance with
BC2.9.4 below; or
(c) the need to maintain adequate frequency sensitive Gensets in accordance with
BC2.9.5 below; or
(d) the need to implement Demand Control in accordance with OC6; or
(e) (i) the need to invoke the Black Start process or the Re-Synchronisation of De-
Synchronised Island process in accordance with OC9; or
(ii) the need to request provision of a Maximum Generation Service; or
(iii) the need to issue an Emergency Deenergisation Instruction in circumstances
where the condition or manner of operation of any Transmission Plant and/or
Apparatus is such that it may cause damage or injury to any person or to the
National Electricity Transmission System.
BC2.9.1.3 In the case of BM Units and Generating Units in Great Britain, Emergency Instructions
will be issued by NGET direct to the User at the Control Point for the BM Unit or
Generating Unit and may require an action or response which is outside its Other Relevant
Data, QPNs, or Export and Import Limits submitted under BC1, or revised under BC1 or
BC2, or Dynamic Parameters submitted or revised under BC2.
BC2.9.1.4 In the case of a Network Operator or an Externally Interconnected System Operator,
Emergency Instructions will be issued to its Control Centre.
BC2.9.2 Implementation Of Emergency Instructions
BC2.9.2.1 Users will respond to Emergency Instructions issued by NGET without delay and using all
reasonable endeavours to so respond. Emergency Instructions may only be rejected by an
User on safety grounds (relating to personnel or plant) and this must be notified to NGET
immediately by telephone.
BC2.9.2.2 Emergency Instructions will always be prefixed with the words This is an Emergency
Instruction except in the case of:
(i) Maximum Generation Service instructed by electronic data communication facilities
where the instruction will be issued in accordance with the provisions of the Maximum
Generation Service Agreement; and
(ii) an Emergency Deenergisation Instruction, where the Emergency Deenergisation
Instruction will be pre-fixed with the words This is an Emergency Deenergisation
Instruction; and
(iii) during a Black Start situation where the Balancing Mechanism has been suspended,
any instruction given by NGET will (unless NGET specifies otherwise) be deemed to be
an Emergency Instruction and need not be pre-fixed with the words This is an
Emergency Instruction; and

Issue 5 Revision 19 BC2 30 September 2016


14 of 33
(iv) during a Black Start situation where the Balancing Mechanism has not been
suspended, any instruction in relation to Black Start Stations and to Network
Operators which are part of an invoked Local Joint Restoration Plan will (unless
NGET specifies otherwise) be deemed to be an Emergency Instruction and need not
be prefixed with the words This is an Emergency Instruction.
In Scotland, any instruction in relation to Gensets that are not at Black Start Stations,
but which are part of an invoked Local Joint Restoration Plan and are instructed in
accordance with the provisions of that Local Joint Restoration Plan, will be deemed to
be an Emergency Instruction and need not be prefixed with the words This is an
Emergency Instruction.

BC2.9.2.3 In all cases under this BC2.9 except BC2.9.1.2 (e) where NGET issues an Emergency
Instruction to a BM Participant which is not rejected under BC2.9.2.1, the Emergency
Instruction shall be treated as a Bid-Offer Acceptance. For the avoidance of doubt, any
Emergency Instruction issued to a Network Operator or to an Externally Interconnected
System Operator or in respect of a Generating Unit that does not form part of a BM Unit,
will not be treated as a Bid-Offer Acceptance.
BC2.9.2.4 In the case of BC2.9.1.2 (e) (ii) where NGET issues an Emergency Instruction pursuant to
a Maximum Generation Service Agreement payment will be dealt with in accordance with
the CUSC and the Maximum Generation Service Agreement.
BC2.9.2.5 In the case of BC2.9.1.2 (e) (iii) where NGET issues an Emergency Deenergisation
Instruction payment will be dealt with in accordance with the CUSC, Section 5.
BC2.9.2.6 In the of BC2.9.1.2 (e) (i) upon receipt of an Emergency Instruction by a Generator during
a Black Start the provisions of Section G of the BSC relating to compensation shall apply.
BC2.9.3 Examples Of Emergency Instructions
BC2.9.3.1 In the case of a BM Unit or a Generating Unit, Emergency Instructions may include an
instruction for the BM Unit or the Generating Unit to operate in a way that is not consistent
with the Dynamic Parameters, QPNs and/or Export and Import Limits.
BC2.9.3.2 In the case of a Generator, Emergency Instructions may include:
(a) an instruction to trip one or more Gensets (excluding Operational Intertripping); or
(b) an instruction to trip Mills or to Part Load a Generating Unit (as defined in the
Glossary and Definitions and not limited by BC2.2); or
(c) an instruction to Part Load a CCGT Module or Power Park Module; or
(d) an instruction for the operation of CCGT Units within a CCGT Module (on the basis of
the information contained within the CCGT Module Matrix) when emergency
circumstances prevail (as determined by NGET in NGET's reasonable opinion); or
(e) an instruction to generate outside normal parameters, as allowed for in 4.2 of the
CUSC; or
(f) an instruction for the operation of Generating Units within a Cascade Hydro Scheme
(on the basis of the additional information supplied in relation to individual Generating
Units) when emergency circumstances prevail (as determined by NGET in NGETs
reasonable opinion); or
(g) an instruction for the operation of a Power Park Module (on the basis of the information
contained within the Power Park Module Availability Matrix) when emergency
circumstances prevail (as determined by NGET in NGET's reasonable opinion).
BC2.9.3.3 Instructions to Network Operators relating to the Operational Day may include:
(a) a requirement for Demand reduction and disconnection or restoration pursuant to OC6;
(b) an instruction to effect a load transfer between Grid Supply Points;
(c) an instruction to switch in a System to Demand Intertrip Scheme;
Issue 5 Revision 19 BC2 30 September 2016
15 of 33
(d) an instruction to split a network;
(e) an instruction to disconnect an item of Plant or Apparatus from the System.

BC2.9.4 Maintaining Adequate System And Localised NRAPM (Negative Reserve Active Power
Margin)
BC2.9.4.1 Where NGET is unable to satisfy the required System NRAPM or Localised NRAPM by
following the process described in BC1.5.5, NGET will issue an Emergency Instruction to
exporting BM Units for De-Synchronising on the basis of Bid-Offer Data submitted to
NGET in accordance with BC1.4.2(d).
BC2.9.4.2 In the event that NGET is unable to differentiate between exporting BM Units according to
Bid-Offer Data, NGET will instruct a BM Participant to Shutdown a specified exporting BM
Unit for such period based upon the following factors:
(a) effect on power flows (resulting in the minimisation of transmission losses);
(b) reserve capability;
(c) Reactive Power worth;
(d) Dynamic Parameters;
(e) in the case of Localised NRAPM, effectiveness of output reduction in the management
of the System Constraint.
BC2.9.4.3 Where NGET is still unable to differentiate between exporting BM Units, having considered
all the foregoing, NGET will decide which exporting BM Unit to Shutdown by the application
of a quota for each BM Participant in the ratio of each BM Participants Physical
Notifications.
BC2.9.4.4 Other than as provided in BC2.9.4.5 and BC2.9.4.6 below, in determining which exporting
BM Units to De-Synchronise under this BC2.9.4, NGET shall not consider in such
determination (and accordingly shall not instruct to De-Synchronise) any Generating Unit
(as defined in the Glossary and Definitions and not limited by BC2.2) within an Existing Gas
Cooled Reactor Plant.
BC2.9.4.5 NGET shall be permitted to instruct a Generating Unit (as defined in the Glossary and
Definitions and not limited by BC2.2) within an Existing AGR Plant to De-Synchronise if
the relevant Generating Unit within the Existing AGR Plant has failed to offer to be flexible
for the relevant instance at the request of NGET within the Existing AGR Plant Flexibility
Limit.
BC2.9.4.6 Notwithstanding the provisions of BC2.9.4.5 above, if the level of System NRAPM (taken
together with System constraints) or Localised NRAPM is such that it is not possible to
avoid instructing a Generating Unit (as defined in the Glossary and Definitions and not
limited by BC2.2) within an Existing Magnox Reactor Plant and/or an Existing AGR Plant
whether or not it has met requests within the Existing AGR Flexibility Limit to De-
Synchronise NGET may, provided the power flow across each External Interconnection is
either at zero or results in an export of power from the Total System, so instruct a
Generating Unit (as defined in the Glossary and Definitions and not limited by BC2.2) within
an Existing Magnox Reactor Plant and/or an Existing AGR Plant to De-Synchronise in
the case of System NRAPM, in all cases and in the case of Localised NRAPM, when the
power flow would have a relevant effect.
BC2.9.4.7 When instructing exporting BM Units which form part of an On-Site Generator Site to
reduce generation under this BC2.9.4, NGET will not issue an instruction which would
reduce generation below the reasonably anticipated Demand of the On-Site Generator
Site. For the avoidance of doubt, it should be noted that the term On-Site Generator Site
only relates to Trading Units which have fulfilled the Class 1 or Class 2 requirements.

Issue 5 Revision 19 BC2 30 September 2016


16 of 33
BC2.9.5 Maintaining Adequate Frequency Sensitive Generation
BC2.9.5.1 If, post Gate Closure, NGET determines, in its reasonable opinion, from the information then
available to it (including information relating to Generating Unit (as defined in the Glossary
and Definitions and not limited by BC2.2) breakdown) that the number of and level of
Primary, Secondary and High Frequency Response available from Gensets (other than
those units within Existing Gas Cooled Reactor Plant, which are permitted to operate in
Limited Frequency Sensitive Mode at all times under BC3.5.3) available to operate in
Frequency Sensitive Mode is such that it is not possible to avoid De-Synchronising
Existing Gas Cooled Reactor Plant then provided that:
(a) there are (or, as the case may be, that NGET anticipates, in its reasonable opinion, that
at the time that the instruction is to take effect there will be) no other Gensets
generating and exporting on to the Total System which are not operating in Frequency
Sensitive Mode (or which are operating with only a nominal amount in terms of level
and duration) (unless, in NGET's reasonable opinion, necessary to assist the relief of
System constraints or necessary as a result of other System conditions); and
(b) the power flow across each External Interconnection is (or, as the case may be, is
anticipated to be at the time that the instruction is to take effect) either at zero or result
in an export of power from the Total System,
then NGET may instruct such of the Existing Gas Cooled Reactor Plant to De-
Synchronise as it is, in NGET's reasonable opinion, necessary to De-Synchronise and for
the period for which the De-Synchronising is, in NGET's reasonable opinion, necessary.
BC2.9.5.2 If in NGET's reasonable opinion it is necessary for both the procedure in BC2.9.4 and that
set out in BC2.9.5.1 to be followed in any given situation, the procedure in BC2.9.4 will be
followed first, and then the procedure set out in BC2.9.5.1. For the avoidance of doubt,
nothing in this sub-paragraph shall prevent either procedure from being followed separately
and independently of the other.

Issue 5 Revision 19 BC2 30 September 2016


17 of 33
BC2.9.6 Emergency Assistance To And From External Systems
(a) An Externally Interconnected System Operator (in its role as operator of the
External System) may request that NGET takes any available action to increase the
Active Energy transferred into its External System, or reduce the Active Energy
transferred into the National Electricity Transmission System by way of emergency
assistance if the alternative is to instruct a demand reduction on all or part of its
External System (or on the system of an Interconnector User using its External
System). Such request must be met by NGET providing this does not require a
reduction of Demand on the National Electricity Transmission System, or lead to a
reduction in security on the National Electricity Transmission System.
(b) NGET may request that an Externally Interconnected System Operator takes any
available action to increase the Active Energy transferred into the National Electricity
Transmission System, or reduce the Active Energy transferred into its External
System by way of emergency assistance if the alternative is to instruct a Demand
reduction on all or part of the National Electricity Transmission System. Such
request must be met by the Externally Interconnected System Operator providing
this does not require a reduction of Demand on its External System (or on the system
of Interconnector Users using its External System), or lead to a reduction in security
on such External System or system.
BC2.9.7 Unplanned Outages Of Electronic Communication And Computing Facilities
BC2.9.7.1 In the event of an unplanned outage of the electronic data communication facilities or of
NGETs associated computing facilities or in the event of a Planned Maintenance Outage
lasting longer than the planned duration, in relation to a post-Gate Closure period NGET
will, as soon as it is reasonably able to do so, issue a NGET Computing System Failure
notification by telephone or such other means agreed between Users and NGET indicating
the likely duration of the outage.
BC2.9.7.2 During the period of any such outage, the following provisions will apply:
(a) NGET will issue further NGET Computing System Failure notifications by telephone or
such other means agreed between Users and NGET to all BM Participants to provide
updates on the likely duration of the outage;
(b) BM Participants should operate in relation to any period of time in accordance with the
Physical Notification prevailing at Gate Closure current at the time of the computer
system failure in relation to each such period of time. Such operation shall be subject to
the provisions of BC2.5.1, which will apply as if set out in this BC2.9.7.2. No further
submissions of BM Unit Data or Generating Unit Data (other than data specified in
BC1.4.2(c) (Export and Import Limits) and BC1.4.2(e) (Dynamic Parameters) should
be attempted. Plant failure or similar problems causing significant deviation from
Physical Notification should be notified to NGET by telephone by the submission of a
revision to Export and Import Limits in relation to the BM Unit or Generating Unit
Data so affected;
(c) Revisions to Export and Import Limits and to Dynamic Parameters should be notified
to NGET by telephone and will be recorded for subsequent use;
(d) NGET will issue Bid-Offer Acceptances by telephone which will be recorded for
subsequent use;
(e) No data will be transferred from NGET to the BMRA until the communication facilities
are re-established.
BC2.9.7.3 NGET will advise BM Participants of the withdrawal of the NGET Computing System
Failure notification following the re-establishment of the communication facilities.

Issue 5 Revision 19 BC2 30 September 2016


18 of 33
BC2.10 OTHER OPERATIONAL INSTRUCTIONS AND NOTIFICATIONS
BC2.10.1 NGET may, from time to time, need to issue other instructions or notifications associated
with the operation of the National Electricity Transmission System.
BC2.10.2 Such instructions or notifications may include:
Intertrips
(a) an instruction to arm or disarm an Operational Intertripping scheme;
Tap Positions
(b) a request for a Genset step-up transformer tap position (for security assessment);
Tests
(c) an instruction to carry out tests as required under OC5, which may include the issue of
an instruction regarding the operation of CCGT Units within a CCGT Module at a
Large Power Station;
Future BM Unit Requirements
(d) a reference to any implications for future BM Unit requirements and the security of the
National Electricity Transmission System, including arrangements for change in
output to meet post fault security requirements;
Changes to Target Frequency
(e) a notification of a change in Target Frequency, which will normally only be 49.95,
50.00, or 50.05Hz but in exceptional circumstances as determined by NGET in its
reasonable opinion, may be 49.90 or 50.10Hz.
BC2.10.3 Where an instruction or notification under BC2.10.2 (c) or (d) results in a change to the input
or output level of the BM Unit then NGET shall issue a Bid-Offer Acceptance or
Emergency Instruction as appropriate.

BC2.11 LIAISON WITH GENERATORS FOR RISK OF TRIP AND AVR TESTING
BC2.11.1 A Generator at the Control Point for any of its Large Power Stations may request NGET's
agreement for one of the Gensets at that Power Station to be operated under a risk of trip.
NGET's agreement will be dependent on the risk to the National Electricity Transmission
System that a trip of the Genset would constitute.
BC2.11.2 (a) Each Generator at the Control Point for any of its Large Power Stations will operate its
Synchronised Gensets (excluding Power Park Modules) with:
(i) AVRs in constant terminal voltage mode with VAR limiters in service at all times.
AVR constant Reactive Power or Power Factor mode should, if installed, be
disabled; and
(ii) its generator step-up transformer tap changer selected to manual mode,
unless released from this obligation in respect of a particular Genset by NGET.
(b) Each Generator at the Control Point for any of its Large Power Stations will operate
st
its Power Park Modules with a Completion Date before 1 January 2006 at unity
power factor at the Grid Entry Point (or User System Entry Point if Embedded).
(c) Each Generator at the Control Point for any of its Large Power Stations will operate
st
its Power Park Modules with a Completion Date on or after 1 January 2006 in
voltage control mode at the Grid Entry Point (or User System Entry Point if
Embedded). Constant Reactive Power or Power Factor mode should, if installed, be
disabled.

Issue 5 Revision 19 BC2 30 September 2016


19 of 33
(d) Where a Power System Stabiliser is fitted as part of the excitation system or voltage
control system of a Genset, it requires on-load commissioning which must be witnessed
by NGET. Only when the performance of the Power System Stabiliser has been
approved by NGET shall it be switched into service by a Generator and then it will be
kept in service at all times unless otherwise agreed with NGET. Further reference is
made to this in CC.6.3.8.
BC2.11.3 A Generator at the Control Point for any of its Power Stations may request NGET's
agreement for one of its Gensets at that Power Station to be operated with the AVR in
manual mode, or Power System Stabiliser switched out, or VAR limiter switched out.
NGET's agreement will be dependent on the risk that would be imposed on the National
Electricity Transmission System and any User System. Provided that in any event a
Generator may take such action as is reasonably necessary on safety grounds (relating to
personnel or plant) .
BC2.11.4 Each Generator shall operate its dynamically controlled OTSDUW Plant and Apparatus to
ensure that the reactive capability and voltage control performance requirements as
specified in CC.6.3.2, CC.6.3.8, CC.A.7 and the Bilateral Agreement can be satisfied in
response to the Setpoint Voltage and Slope as instructed by NGET at the Transmission
Interface Point.

BC2.12 LIAISON WITH EXTERNALLY INTERCONNECTED SYSTEM OPERATORS


BC2.12.1 Co-Ordination Role Of Externally Interconnected System Operators
(a) The Externally Interconnected System Operator will act as the Control Point for
Bid-Offer Acceptances on behalf of Interconnector Users and will co-ordinate
instructions relating to Ancillary Services and Emergency Instructions on behalf of
Interconnector Users using its External System in respect of each Interconnector
Users BM Units.
(b) NGET will issue Bid-Offer Acceptances and instructions for Ancillary Services
relating to Interconnector Users BM Units to each Externally Interconnected
System Operator in respect of each Interconnector User using its External System.
(c) If, as a result of a reduction in the capability (in MW) of the External Interconnection,
the total of the Physical Notifications and Bid-Offer Acceptances issued for the
relevant period using that External Interconnection, as stated in the BM Unit Data
exceeds the reduced capability (in MW) of the respective External Interconnection in
that period then NGET shall notify the Externally Interconnected System Operator
accordingly. The Externally Interconnected System Operator should seek a revision
of Export and Import Limits from one or more of its Interconnector Users for the
remainder of the Balancing Mechanism period during which Physical Notifications
cannot be revised.

Issue 5 Revision 19 BC2 30 September 2016


20 of 33
APPENDIX 1 - FORM OF BID-OFFER ACCEPTANCES
BC2.A.1.1 This Appendix describes the forms of Bid-Offer Acceptances. As described in BC2.6.1 Bid-
Offer Acceptances are normally given by an automatic logging device, but in the event of
failure of the logging device, Bid-Offer Acceptances will be given by telephone.
BC2.A.1.2 For each BM Unit the Bid-Offer Acceptance will consist of a series of MW figures and
associated times.
BC2.A.1.3 The Bid-Offer Acceptances relating to CCGT Modules will assume that the CCGT Units
within the CCGT Module will operate in accordance with the CCGT Module Matrix, as
required by BC1. The Bid-Offer Acceptances relating to Cascade Hydro Schemes will
assume that the Generating Unit forming part of the Cascade Hydro Scheme will operate,
where submitted, in accordance with the Cascade Hydro Scheme Matrix submitted under
BC1.
BC2.A.1.4 Bid-Offer Acceptances Given By Automatic Logging Device
(a) The complete form of the Bid-Offer Acceptance is given in the EDL Message Interface
Specification which can be made available to Users on request.
(b) Bid-Offer Acceptances will normally follow the form:
(i) BM Unit Name
(ii) Instruction Reference Number
(iii) Time of instruction
(iv) Type of instruction
(v) BM Unit Bid-Offer Acceptance number
(vi) Number of MW/Time points making up instruction (minimum 2, maximum 5)
(vii) MW value and Time value for each point identified in (vi)
The times required in the instruction are input and displayed in London time, but
communicated electronically in GMT.
BC2.A.1.5 Bid-Offer Acceptances Given By Telephone
(a) All run-up/run-down rates will be assumed to be constant and consistent with Dynamic
Parameters. Each Bid-Offer Acceptance will, wherever possible, be kept simple,
drawing as necessary from the following forms and BC2.7
(b) Bid-Offer Acceptances given by telephone will normally follow the form:
(i) an exchange of operator names;
(ii) BM Unit Name;
(iii) Time of instruction;
(iv) Type of instruction;
(v) Number of MW/Time points making up instruction (minimum 2, maximum 5)
(vi) MW value and Time value for each point identified in (v)
The times required in the instruction are expressed in London time.

Issue 5 Revision 19 BC2 30 September 2016


21 of 33
For example, for a BM Unit ABCD-1 acceptance logged with a start time at 1400 hours and
with a FPN at 300MW:
BM Unit ABCD-1 Bid-Offer Acceptance timed at 1400 hours. Acceptance consists of 4
MW/Time points as follows:
300MW at 1400 hours
400MW at 1415 hours
400MW at 1450 hours
300MW at 1500 hours

BC2.A.1.6 Submission Of Bid-Offer Acceptance Data To The Bmra


The relevant information contained in Bid-Offer Acceptances issued by NGET will be
converted into from and to MW levels and times before they are submitted to the BMRA
by NGET.

Issue 5 Revision 19 BC2 30 September 2016


22 of 33
APPENDIX 2 - TYPE AND FORM OF ANCILLARY SERVICE
INSTRUCTIONS
BC2.A.2.1 This part of the Appendix consists of a non-exhaustive list of the forms and types of
instruction for a Genset to provide System Ancillary Services. There may be other types of
Commercial Ancillary Services and these will be covered in the relevant Ancillary
Services Agreement. In respect of the provision of Ancillary Services by Generating
Units the forms and types of instruction will be in the form of this Appendix 2 unless
amended in the Ancillary Services Agreement.
As described in CC.8, System Ancillary Services consist of Part 1 and Part 2 System
Ancillary Services.
Part 1 System Ancillary Services Comprise:
(a) Reactive Power supplied other than by means of synchronous or static compensators.
This is required to ensure that a satisfactory System voltage profile is maintained and
that sufficient Reactive Power reserves are maintained under normal and fault
conditions. Ancillary Service instructions in relation to Reactive Power may include:
(i) MVAr Output
(ii) Target Voltage Levels
(iii) Tap Changes
(iv) Maximum MVAr Output (maximum excitation)
(v) Maximum MVAr Absorption (minimum excitation)
(b) Frequency Control by means of Frequency sensitive generation. Gensets may be
required to move to or from Frequency Sensitive Mode in the combinations agreed in
the relevant Ancillary Services Agreement. They will be specifically requested to
operate so as to provide Primary Response and/or Secondary Response and/or High
Frequency Response.
Part 2 System Ancillary Services Comprise:
(c) Frequency Control by means of Fast Start.
(d) Black Start Capability
(e) System to Generator Operational Intertripping
BC2.A.2.2 As Ancillary Service instructions are not part of Bid-Offer Acceptances they do not need
to be closed instructions and can cover any period of time, not just limited to the period of the
Balancing Mechanism.
BC2.A.2.3 As described in BC2.6.1, unless otherwise agreed with NGET, Ancillary Service
instructions are normally given by automatic logging device, but in the absence of, or in the
event of failure of the logging device, instructions will be given by telephone.
BC2.A.2.4 Instructions Given By Automatic Logging Device
(a) The complete form of the Ancillary Service instruction is given in the EDL Message
Interface Specification which is available to Users on request from NGET.
(b) Ancillary Service instructions for Frequency Control will normally follow the form:
(i) BM Unit Name
(ii) Instruction Reference Number
(iii) Time of instruction
(iv) Type of instruction (REAS)
(v) Reason Code
(vi) Start Time
Issue 5 Revision 19 BC2 30 September 2016
23 of 33
(c) Ancillary Service instructions for Reactive Power will normally follow the form:
(i) BM Unit Name
(ii) Instruction Reference Number
(iii) Time of instruction
(iv) Type of instruction (MVAr, VOLT or TAPP)
(v) Target Value
(vi) Target Time
The times required in the instruction are input and displayed in London time, but
communicated electronically in GMT.
BC2.A.2.5 Instructions Given By Telephone
(a) Ancillary Service instructions for Frequency Control will normally follow the form:
(i) an exchange of operator names;
(ii) BM Unit Name;
(iii) Time of instruction;
(iv) Type of instruction;
(v) Start Time.
The times required in the instruction are expressed in London time.
For example, for BM Unit ABCD-1 instructed at 1400 hours to provide Primary and High
Frequency response starting at 1415 hours:
BM Unit ABCD-1 message timed at 1400 hours. Unit to Primary and High Frequency
Response at 1415 hours

(b) Ancillary Service instructions for Reactive Power will normally follow the form:
(a) an exchange of operator names;
(b) BM Unit Name;
(c) Time of instruction;
(d) Type of instruction (MVAr, VOLT, SETPOINT, SLOPE or TAPP)
(e) Target Value
(f) Target Time.
The times required in the instruction are expressed as London time.
For example, for BM Unit ABCD-1 instructed at 1400 hours to provide 100MVAr by 1415
hours:
BM Unit ABCD-1 message timed at 1400 hours. MVAr instruction. Unit to plus 100 MVAr
target time 1415 hours.

Issue 5 Revision 19 BC2 30 September 2016


24 of 33
BC2.A.2.6 Reactive Power
As described in BC2.A.2.4 and BC2.A.2.5 instructions for Ancillary Services relating to
Reactive Power may consist of any of several specific types of instruction. The following
table describes these instructions in more detail:

Instruction Type of
Description
Name Instruction

MVAr Output The individual MVAr output from the Genset onto the MVAr
National Electricity Transmission System at the Grid
Entry Point (or onto the User System at the User System
Entry Point in the case of Embedded Power Stations),
namely on the higher voltage side of the generator step-up
transformer. In relation to each Genset, where there is no
HV indication, NGET and the Generator will discuss and
agree equivalent MVAr levels for the corresponding LV
indication.

Where a Genset is instructed to a specific MVAr output,


the Generator must achieve that output within a tolerance
of +/-25 MVAr (for Gensets in England and Wales) or the
lesser of +/-5% of rated output or 25MVAr (for Gensets in
Scotland) (or such other figure as may be agreed with
NGET) by tap changing on the generator step-up
transformer, or adjusting the Genset terminal voltage,
subject to compliance with CC.6.3.8 (a) (v), to a value that
is equal to or higher than 1.0p.u. of the rated terminal
voltage, or a combination of both. Once this has been
achieved, the Generator will not tap again and will not
readjust the Genset terminal voltage without prior
consultation with and the agreement of NGET, on the basis
that MVAr output will be allowed to vary with System
conditions.

Issue 5 Revision 19 BC2 30 September 2016


25 of 33
Instruction Type of
Description
Name Instruction

Target Voltage Target voltage levels to be achieved by the Genset on VOLT


Levels the National Electricity Transmission System at the
Grid Entry Point (or on the User System at the User
System Entry Point in the case of Embedded Power
Stations, namely on the higher voltage side of the
generator step-up transformer. Where a Genset is
instructed to a specific target voltage, the Generator
must achieve that target within a tolerance of 1 kV (or
such other figure as may be agreed with NGET) by tap
changing on the generator step-up transformer, or
adjusting the Genset terminal voltage, subject to
compliance with CC.6.3.8 (a) (v), to a value that is equal
to or higher than 1.0p.u. of the rated terminal voltage, or
a combination of both. In relation to each Genset, where
there is no HV indication, NGET and the Generator will
discuss and agree equivalent voltage levels for the
corresponding LV indication.

Under normal operating conditions, once this target voltage


level has been achieved the Generator will not tap again
and will not readjust the Genset terminal voltage without
prior consultation with, and with the agreement of, NGET.

However, under certain circumstances the Generator may


be instructed to maintain a target voltage until otherwise
instructed and this will be achieved by tap changing on the
generator step-up transformer, or adjusting the Genset
terminal voltage, subject to compliance with CC.6.3.8 (a)
(v), to a value that is equal to or higher than 1.0p.u. of the
rated terminal voltage, or a combination of both without
reference to NGET.

Setpoint Where a Non-Synchronous Generating Unit, DC SETPOINT


Voltage Converter or Power Park Module is instructed to a
specific Setpoint Voltage, the Generator must achieve
that Setpoint Voltage within a tolerance of 0.25% (or
such other figure as may be agreed with NGET).

The Generator must maintain the specified Setpoint


Voltage target until an alternative target is received from
NGET.

Slope Where a Non-Synchronous Generating Unit, DC SLOPE


Converter or Power Park Module is instructed to a
specific Slope, the Generator must achieve that Slope
within a tolerance of 0.5% (or such other figure as may
be agreed with NGET).

The Generator must maintain the specified Slope target


until an alternative target is received from NGET.

The Generator will not be required to implement a new


Slope setting in a time of less than 1 week from the time
of the instruction.

Issue 5 Revision 19 BC2 30 September 2016


26 of 33
Instruction Type of
Description
Name Instruction

Tap Changes Details of the required generator step-up transformer tap TAPP
changes in relation to a Genset. The instruction for tap
changes may be a Simultaneous Tap Change
instruction, whereby the tap change must be effected by
the Generator in response to an instruction from NGET
issued simultaneously to relevant Power Stations. The
instruction, which is normally preceded by advance
notice, must be effected as soon as possible, and in any
event within one minute of receipt from NGET of the
instruction.
For a Simultaneous Tap Change, change Genset
generator step-up transformer tap position by one [two]
taps to raise or lower (as relevant) System voltage, to be
executed at time of instruction.

Maximum Under certain conditions, such as low System voltage, an


MVAr Output instruction to maximum MVAr output at instructed MW
(maximum output ("maximum excitation") may be given, and a
excitation) Generator should take appropriate actions to maximise
MVAr output unless constrained by plant operational limits
or safety grounds (relating to personnel or plant).

Maximum Under certain conditions, such as high System voltage, an


MVAr instruction to maximum MVAr absorption at instructed MW
Absorption output ("minimum excitation") may be given, and a
("minimum Generator should take appropriate actions to maximise
excitation") MVAr absorption unless constrained by plant operational
limits or safety grounds (relating to personnel or plant).

BC2.A.2.7 In addition, the following provisions will apply to Reactive Power instructions:
(a) In circumstances where NGET issues new instructions in relation to more than one BM
Unit at the same Power Station at the same time tapping will be carried out by the
Generator one tap at a time either alternately between (or in sequential order, if more
than two), or at the same time on, each BM Unit.
(b) Where the instructions require more than two taps per BM Unit and that means that the
instructions cannot be achieved within 2 minutes of the instruction time (or such longer
period at NGET may have instructed), the instructions must each be achieved with the
minimum of delay after the expiry of that period.
(c) It should be noted that should System conditions require, NGET may need to instruct
maximum MVAr output to be achieved as soon as possible, but (subject to the
provisions of paragraph (BC2.A.2.7(b) above) in any event no later than 2 minutes after
the instruction is issued.
(d) An Ancillary Service instruction relating to Reactive Power may be given in respect of
CCGT Units within a CCGT Module at a Power Station where running arrangements
and/or System conditions require, in both cases where exceptional circumstances apply
and connection arrangements permit.
(e) In relation to MVAr matters, MVAr generation/output is an export onto the System and
is referred to as "lagging MVAr", and MVAr absorption is an import from the System
and is referred to as "leading MVAr".
(f) It should be noted that the excitation control system constant Reactive Power output
control mode or constant power factor output control mode will always be disabled,
unless agreed otherwise with NGET.

Issue 5 Revision 19 BC2 30 September 2016


27 of 33
APPENDIX 3 - SUBMISSION OF REVISED MVAr CAPABILITY
BC2.A.3.1 For the purpose of submitting revised MVAr data the following terms shall apply:

Full Output In the case of a Synchronous Generating Unit (as defined in the
Glossary and Definitions and not limited by BC2.2) is the MW output
measured at the generator stator terminals representing the LV
equivalent of the Registered Capacity at the Grid Entry Point, and
in the case of a Non-Synchronous Generating Unit (excluding
Power Park Units), DC Converter or Power Park Module is the
Registered Capacity at the Grid Entry Point

Minimum Output In the case of a Synchronous Generating Unit (as defined in the
Glossary and Definitions and not limited by BC2.2 ) is the MW output
measured at the generator stator terminals representing the LV
equivalent of the Minimum Generation at the Grid Entry Point, and
in the case of a Non-Synchronous Generating Unit (excluding
Power Park Units), DC Converter or Power Park Module is the
Minimum Generation at the Grid Entry Point

BC2.A.3.2 The following provisions apply to faxed submission of revised MVAr data:
(a) The fax must be transmitted to NGET (to the relevant location in accordance with GC6)
and must contain all the sections from the relevant part of Annexure 1 and from either
Annexure 2 or 3 (as applicable) but with only the data changes set out. The "notification
time" must be completed to refer to the time of transmission, where the time is
expressed as London time.
(b) Upon receipt of the fax, NGET will acknowledge receipt by sending a fax back to the
User. The acknowledgement will either state that the fax has been received and is
legible or will state that it (or part of it) is not legible and will request re-transmission of
the whole (or part) of the fax.
(c) Upon receipt of the acknowledging fax the User will, if requested, re-transmit the whole
or the relevant part of the fax.
(d) The provisions of paragraphs (b) and (c) then apply to that re-transmitted fax.

Issue 5 Revision 19 BC2 30 September 2016


28 of 33
APPENDIX 3 - ANNEXURE 1

Optional
Logo

Company name REVISED REACTIVE POWER


CAPABILITY DATA

TO: National Electricity Transmission Fax telephone No.


System Control Centre

Number of pages inc. header:.............................

Sent By : ........................................................................................................

Return Acknowledgement Fax to ....................................................................

For Retransmission or Clarification ring..........................................................

Acknowledged by NGET: (Signature)

................................................................................

Acknowledgement time and date


....................................................................................

Legibility of FAX :

Acceptable

Unacceptable ( Resend FAX )


(List pages if appropriate)

Issue 5 Revision 19 BC2 30 September 2016


29 of 33
APPENDIX 3 - ANNEXURE 2

To: National Electricity Transmission System Control Centre

From : [Company Name & Location]

REVISED REACTIVE POWER CAPABILITY DATA GENERATING UNITS EXCLUDING POWER PARK
MODULES AND DC CONVERTERS

Notification Time (HH:MM): Notification Date (DD/MM/YY):

Start Time (HH:MM): Start Date (DD/MM/YY):

Generating Unit*

* For a CCGT Module or a Cascade Hydro Scheme, the redeclaration is for a Generating Unit within a CCGT
Module or Cascade Hydro Scheme. For BM Units quote the NGET BM Unit id, for other units quote the
Generating Unit id used for OC2.4.1.2 Outage Planning submissions. Generating Unit has the meaning
given in the Glossary and Definitions and is not limited by BC2.2.

REVISION TO THE REACTIVE POWER CAPABILITY AT THE GENERATING UNIT STATOR


TERMINALS (at rated terminal volts) AS STATED IN THE RELEVANT ANCILLARY SERVICES
AGREEMENT:

MW MINIMUM (MVAr +ve MAXIUM (MVAr +ve


for lag, -ve for lead) for lag, -ve for lead)

AT RATED MW

AT FULL OUTPUT (MW)

AT MINIMUM
OUTPUT (MW)

COMMENTS e.g. generator transformer tap restrictions, predicted end time if known

_________________________________________________________________________

_________________________________________________________________________

Redeclaration made by (Signature)

_________________________________________________

Issue 5 Revision 19 BC2 30 September 2016


30 of 33
APPENDIX 3 - ANNEXURE 3

To: National Electricity Transmission System Control Centre

From : [Company Name & Location]

REVISED REACTIVE POWER CAPABILITY DATA POWER PARK MODULES AND DC CONVERTERS

Notification Time (HH:MM): Notification Date (DD/MM/YY):

Start Time (HH:MM): Start Date (DD/MM/YY):

Power Park Module / DC Converter*

* For BM Units quote the NGET BM Unit id, for other units quote the id used for OC2.4.1.2 Outage Planning
submissions

Start Time/Date (if not effective immediately)

REVISION TO THE REACTIVE POWER CAPABILITY AT THE COMMERCIAL BOUNDARY AS STATED


IN THE RELEVANT ANCILLARY SERVICES AGREEMENT:

MINIMUM (MVAr +ve MAXIMUM (MVAr +ve for


for lag, -ve for lead) lag, -ve for lead)

AT RATED MW

AT 50% OF RATED
MW
AT 20% OF RATED MW

BELOW 20% OF RATED MW

AT 0% OF RATED
MW

COMMENTS e.g. generator transformer tap restrictions, predicted end time if known

_________________________________________________________________________

_________________________________________________________________________

Redeclaration made by (Signature)

_________________________________________________

Issue 5 Revision 19 BC2 30 September 2016


31 of 33
APPENDIX 4 - SUBMISSION OF AVAILABILITY OF FREQUENCY
SENSITIVE MODE
BC2.A.4.1 For the purpose of submitting availability of Frequency Sensitive Mode, this process only
relates to the provision of response under the Frequency Sensitive Mode and does not
cover the provision of response under the Limited Frequency Sensitive Mode.
BC2.A.4.2 The following provisions apply to the faxed submission of the Frequency Sensitive Mode
availability;
(a) The fax must be transmitted to NGET (to the relevant location in accordance with GC6)
and must contain all the sections relevant to Appendix 4 - Annexure1 but with only the
data changes set out. The notification time must be completed to refer to the time and
date of transmission, where the time is expressed in London time.
(b) Upon receipt of the fax, NGET will acknowledge receipt by sending a fax back to the
User. This acknowledging fax should be in the format of Appendix 4 Annexure 1. The
acknowledgement will either state that the fax has been received and is legible or will
state that it (or part of it) is not legible and will request re-transmission of the whole (or
part) of the fax.
(c) Upon receipt of the acknowledging fax the User will, if requested re-transmit the whole
or the relevant part of the fax.
(d) The provisions of paragraph (b) and (c) then apply to the re-transmitted fax.
BC2.A.4.3 The User shall ensure the availability of operating in the Frequency Sensitive Mode is
restored as soon as reasonably practicable and will notify NGET using the format of
Appendix 4 Annexure 1. In the event of a sustained unavailability of Frequency Sensitive
Mode NGET may seek to confirm compliance with the relevant requirements in the CC
through the process in OC5.

Issue 5 Revision 19 BC2 30 September 2016


32 of 33
APPENDIX 4 - ANNEXURE 1

To: National Electricity Transmission System Control Centre

From : [Company Name & Location]

Submission of availability of Frequency Sensitive Mode

Notification Time (HH:MM): Notification Date (DD/MM/YY):

Start Time (HH:MM): Start Date (DD/MM/YY):

Genset or DC Converter

The availability of the above unit to operate in Frequency Sensitive Mode is as follows:

All contract modes: Available / Unavailable [delete as applicable]; or

Change to the availability of individual contract modes:

Contract Mode e.g. A Availability for operation in Frequency Sensitive Mode


[Y/N]

COMMENTS e.g. reason for submission, predicted end time if known

_________________________________________________________________________

_________________________________________________________________________

Redeclaration made by (Signature)______________________________________________

Receipt Acknowledgement from NGET

Legible (tick box) Illegible (tick box)


Explanation:

Time:
Date:
Signature:

< END OF BALANCING CODE 2 >


Issue 5 Revision 19 BC2 30 September 2016
33 of 33
BALANCING CODE NO. 3
(BC3)

FREQUENCY CONTROL PROCESS

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


BC3.1 INTRODUCTION ...................................................................................................................................2
BC3.2 OBJECTIVE...........................................................................................................................................2
BC3.3 SCOPE ..................................................................................................................................................2
BC3.4 MANAGING SYSTEM FREQUENCY ...................................................................................................3
BC3.4.1 Statutory Requirements ..............................................................................................................3
BC3.4.2 Target Frequency .......................................................................................................................3
BC3.4.3 Electric Time ...............................................................................................................................3
BC3.5 RESPONSE FROM GENSETS.............................................................................................................3
BC3.5.1 Capability ....................................................................................................................................3
BC3.5.2 Limited Frequency Sensitive Mode ............................................................................................3
BC3.5.3 Existing Gas Cooled Reactor Plant /Power Park Modules before 1 January 2006....................3
BC3.5.4 Frequency Sensitive Mode .........................................................................................................4
BC3.5.5 System Frequency Induced Change ..........................................................................................4
BC3.6 RESPONSE TO LOW FREQUENCY....................................................................................................5
BC3.6.1 Low Frequency Relay Initiated Response From Gensets ..........................................................5
BC3.6.2 Low Frequency Relay Initiated Response From Demand..........................................................5
BC3.7 RESPONSE TO HIGH FREQUENCY REQUIRED FROM SYNCHRONISED. GENSETS .................6
BC3.7.1 Plant In Frequency Sensitive Mode Instructed To Provide High Frequency Response ............6
BC3.7.2 Plant In Limited Frequency Sensitive Mode ...............................................................................7
BC3.7.3 Plant Operation To Below Minimum Generation ........................................................................7
BC3.7.5 Information Update To NGC .......................................................................................................8
BC3.7.6 Existing Gas Cooled Reactor Plant /Power Park Modules Before 1 January 2006 ...................8
BC3.7.7 Externally Interconnected System Operators .............................................................................8

Issue 5 Revision 0 BC3 17 August 2012


i
BC3.1 INTRODUCTION
BC3.1.1 BC3 sets out the procedure for NGET to use in relation to Users to undertake System
Frequency control. System Frequency will be controlled by response from Gensets (and
DC Converters at DC Converter Stations) operating in Limited Frequency Sensitive
Mode or Frequency Sensitive Mode, by the issuing of instructions to Gensets (and DC
Converters at DC Converter Stations) and by control of Demand. The requirements for
Frequency control are determined by the consequences and effectiveness of the Balancing
Mechanism, and accordingly, BC3 is complementary to BC1 and BC2.
BC3.1.2 Inter-Relationship With Ancillary Services
The provision of response (other than by operation in Limited Frequency Sensitive Mode
or in accordance with BC3.7.1(c)) in order to contribute towards Frequency control, as
described in BC3, by Generators or DC Converter Station owners will be an Ancillary
Service. Ancillary Services are divided into three categories, System Ancillary Services
Parts 1 and 2 and Commercial Ancillary Services. System Ancillary Services, Parts 1
and 2, are those Ancillary Services listed in CC.8.1; those in Part 1 of CC.8.1 are those for
which the Connection Conditions require the capability as a condition of connection and
those in Part 2 are those which may be agreed to be provided by Users and which can only
be utilised by NGET if so agreed. Commercial Ancillary Services like those System
Ancillary Services set out in Part 2 of CC.8.1, may be agreed to be provided by Users and
which can only be utilised by NGET if so agreed.
BC3.1.3 The provision of Frequency control services, if any, from an External System via a DC
Converter Station will be provided for in the Ancillary Services Agreement and/or
Bilateral Agreement with the DC Converter Station owner and/or any other relevant
agreements with the relevant EISO.
BC3.1.4 The provision of Frequency control services, if any, from an Offshore Power Station
connected to an Offshore Transmission System that includes a Transmission DC
Converter will be facilitated (where necessary) through appropriate data signals provided to
the Offshore Power Station by the Relevant Transmission Licensee in accordance with
the STC.

BC3.2 OBJECTIVE
The procedure for NGET to direct System Frequency control is intended to enable (as far
as possible) NGET to meet the statutory requirements of System Frequency control.

BC3.3 SCOPE
BC3 applies to NGET and to Users, which in this BC3 means:
(a) Generators with regard to their Large Power Stations (except those Large Power
Stations with a Registered Capacity less than 50MW comprising of Power Park
Modules),
(b) Network Operators,
(c) DC Converter Station owners,
(d) other providers of Ancillary Services, and
(e) Externally Interconnected System Operators.

Issue 5 Revision 0 BC3 17 August 2012


2 of 8
BC3.4 MANAGING SYSTEM FREQUENCY
BC3.4.1 Statutory Requirements
When NGET determines it is necessary (by having monitored the System Frequency), it
will, as part of the procedure set out in BC2, issue instructions (including instructions for
Commercial Ancillary Services) in order to seek to regulate System Frequency to meet
the statutory requirements of Frequency control. Gensets (except those comprising of a
Power Park Module in a Power Station with a Registered Capacity less than 50MW and
those comprising of a Power Park Module in Scotland with a Completion Date before 1
July 2004) and DC Converters at DC Converter Stations when transferring Active Power
to the Total System, operating in Frequency Sensitive Mode will be instructed by NGET to
operate taking due account of the Target Frequency notified by NGET.
BC3.4.2 Target Frequency
NGET will give 15 minutes notice of variation in Target Frequency.
BC3.4.3 Electric Time
NGET will endeavour (in so far as it is able) to control electric clock time to within plus or
minus 10 seconds by specifying changes to Target Frequency, by accepting bids and offers
in the Balancing Mechanism. Errors greater than plus or minus 10 seconds may be
temporarily accepted at NGET's reasonable discretion.

BC3.5 RESPONSE FROM GENSETS (AND DC CONVERTERS AT DC CONVERTER STATIONS


WHEN TRANSFERRING ACTIVE POWER TO THE TOTAL SYSTEM)
BC3.5.1 Capability
Each Genset (except those comprising of Power Park Modules in a Power Station with a
Registered Capacity less than 50MW and those comprising of Power Park Modules in
Scotland with a Completion Date before 1 July 2004) and each DC Converter at a DC
Converter Station must at all times have the capability to operate automatically so as to
provide response to changes in Frequency in accordance with the requirements of CC.6.3.7
in order to contribute to containing and correcting the System Frequency within the
statutory requirements of Frequency control. . For DC Converters at DC Converter
Stations, BC3.1.3 also applies In addition each Genset (and each DC Converter at a DC
Converter Station) must at all times have the capability to operate in a Limited Frequency
Sensitive Mode by operating so as to provide Limited High Frequency Response.
BC3.5.2 Limited Frequency Sensitive Mode
Each Synchronised Genset producing Active Power (and each DC Converter at a DC
Converter Station) must operate at all times in a Limited Frequency Sensitive Mode
(unless instructed in accordance with BC3.5.4 below to operate in Frequency Sensitive
Mode). Operation in Limited Frequency Sensitive Mode must achieve the capability
requirement described in CC.6.3.3 for System Frequencies up to 50.4Hz and shall be
deemed not to be in contravention of CC.6.3.7.
BC3.5.3 (a) Existing Gas Cooled Reactor Plant
NGET will permit Existing Gas Cooled Reactor Plant other than Frequency
Sensitive AGR Units to operate in Limited Frequency Sensitive Mode at all times.

Issue 5 Revision 0 BC3 17 August 2012


3 of 8
(b) Power Park Modules In Operation Before 1 January 2006
NGET will permit Power Park Modules in operation before 1 January 2006 to operate
in Limited Frequency Sensitive Mode at all times. For the avoidance of doubt Power
Park Modules in England and Wales with a Completion Date on or after 1 January
2006 and Power Park Modules in operation in Scotland after 1 January 2006 with a
completion date after 1 July 2004 and in a Power Station with a Registered Capacity
of 50MW or more will be required to operate in both Limited Frequency Sensitive
Mode and Frequency Sensitive Mode of operation depending on System conditions.
BC3.5.4 Frequency Sensitive Mode
(a) NGET may issue an instruction to a Genset (or DC Converter at a DC Converter
Station if agreed as described in BC3.1.3) to operate so as to provide Primary
Response and/or Secondary Response and/or High Frequency Response (in the
combinations agreed in the relevant Ancillary Services Agreement). When so
instructed, the Genset or DC Converter at a DC Converter Station must operate in
accordance with the instruction and will no longer be operating in Limited Frequency
Sensitive Mode, but by being so instructed will be operating in Frequency Sensitive
Mode.
(b) Frequency Sensitive Mode is the generic description for a Genset (or DC Converter
at a DC Converter Station) operating in accordance with an instruction to operate so
as to provide Primary Response and/or Secondary Response and/or High
Frequency Response (in the combinations agreed in the relevant Ancillary Services
Agreement).
(c) The magnitude of the response in each of those categories instructed will be in
accordance with the relevant Ancillary Services Agreement with the Generator or DC
Converter Station owner.
(d) Such instruction will continue until countermanded by NGET or until;
(i) the Genset is De-Synchronised; or
(ii) the DC Converter ceases to transfer Active Power to or from the Total System
subject to the conditions of any relevant agreement relating to the operation of the
DC Converter Station,
whichever is the first to occur.
(e) NGET will not so instruct Generators in respect of Existing Gas Cooled Reactor
Plant other than Frequency Sensitive AGR Units.
(f) NGET will not so instruct Generators in respect of Power Park Modules:
(i) in Scotland in a Power Station with a Completion Date before 1 July 2004; or,
(ii) in a Power Station with a Registered Capacity of less than 50MW.
(iii) in England and Wales with a Completion Date before 1 January 2006.
BC3.5.5 System Frequency Induced Change
A System Frequency induced change in the Active Power output of a Genset (or DC
Converter at a DC Converter Station) which assists recovery to Target Frequency must
not be countermanded by a Generator or DC Converter Station owner except where it is
done purely on safety grounds (relating to either personnel or plant) or, where necessary, to
ensure the integrity of the Power Station or DC Converter Station.

Issue 5 Revision 0 BC3 17 August 2012


4 of 8
BC3.6 RESPONSE TO LOW FREQUENCY
BC3.6.1 Low Frequency Relay Initiated Response From Gensets And DC Converters At DC
Converter Stations
(a) NGET may utilise Gensets (and DC Converters at DC Converter Stations) with the
capability of Low Frequency Relay initiated response as:
(i) synchronisation and generation from standstill;
(ii) generation from zero generated output;
(iii) increase in generated output;
(iv) increase in DC Converter output to the Total System (if so agreed as described in
BC3.1.3);
(v) decrease in DC Converter input from the Total System (if so agreed as described
in BC3.1.3);
in establishing its requirements for Operating Reserve.

(b) (i) NGET will specify within the range agreed with Generators and/or EISOs and/or
DC Converter Station owners (if so agreed as described in BC3.1.3), Low
Frequency Relay settings to be applied to Gensets or DC Converters at DC
Converter Stations pursuant to BC3.6.1 (a) and instruct the Low Frequency
Relay initiated response placed in and out of service.
(ii) Generators and/or EISOs and/or DC Converter Station owners (if so agreed as
described in BC3.1.3) will comply with NGET instructions for Low Frequency
Relay settings and Low Frequency Relay initiated response to be placed in or out
of service. Generators or DC Converter Station owners or EISOs may not alter
such Low Frequency Relay settings or take Low Frequency Relay initiated
response out of service without NGET's agreement (such agreement not to be
unreasonably withheld or delayed), except for safety reasons.
BC3.6.2 Low Frequency Relay Initiated Response From Demand And Other Demand Modification
Arrangements (Which May Include A DC Converter Station When Importing Active Power
From The Total System)
(a) NGET may, pursuant to an Ancillary Services Agreement, utilise Demand with the
capability of Low Frequency Relay initiated Demand reduction in establishing its
requirements for Frequency Control.
(b) (i) NGET will specify within the range agreed the Low Frequency Relay settings to
be applied pursuant to BC3.6.2 (a), the amount of Demand reduction to be
available and will instruct the Low Frequency Relay initiated response to be
placed in or out of service.
(ii) Users will comply with NGET instructions for Low Frequency Relay settings and
Low Frequency Relay initiated Demand reduction to be placed in or out of
service. Users may not alter such Low Frequency Relay settings or take Low
Frequency Relay initiated response out of service without NGET's agreement,
except for safety reasons.
(iii) In the case of any such Demand which is Embedded, NGET will notify the
relevant Network Operator of the location of the Demand, the amount of Demand
reduction to be available, and the Low Frequency Relay settings.
(c) NGET may also utilise other Demand modification arrangements pursuant to an
agreement for Ancillary Services, in order to contribute towards Operating Reserve.

Issue 5 Revision 0 BC3 17 August 2012


5 of 8
BC3.7 RESPONSE TO HIGH FREQUENCY REQUIRED FROM SYNCHRONISED GENSETS
(AND DC CONVERTERS AT DC CONVERTER STATIONS WHEN TRANSFERRING
ACTIVE POWER TO THE TOTAL SYSTEM)
BC3.7.1 Plant In Frequency Sensitive Mode Instructed To Provide High Frequency Response
(a) Each Synchronised Genset (or each DC Converter at a DC Converter Station) in
respect of which the Generator or DC Converter Station owner and/or EISO has been
instructed to operate so as to provide High Frequency Response, which is producing
Active Power and which is operating above the Designed Minimum Operating Level,
is required to reduce Active Power output in response to an increase in System
Frequency above the Target Frequency (or such other level of Frequency as may
have been agreed in an Ancillary Services Agreement). The Target Frequency is
normally 50.00 Hz except where modified as specified under BC3.4.2.
(b) (i) The rate of change of Active Power output with respect to Frequency up to 50.5
Hz shall be in accordance with the provisions of the relevant Ancillary Services
Agreement with each Generator or DC Converter Station owner. If more than
one rate is provided for in the Ancillary Services Agreement NGET will instruct
the rate when the instruction to operate to provide High Frequency Response is
given.
(ii) The reduction in Active Power output by the amount provided for in the relevant
Ancillary Services Agreement must be fully achieved within 10 seconds of the
time of the Frequency increase and must be sustained at no lesser reduction
thereafter.
(iii) It is accepted that the reduction in Active Power output may not be to below the
Designed Minimum Operating Level.
(c) In addition to the High Frequency Response provided, the Genset (or DC Converter
at a DC Converter Station) must continue to reduce Active Power output in response
to an increase in System Frequency above 50.5 Hz at a minimum rate of 2 per cent of
output per 0.1 Hz deviation of System Frequency above that level, such reduction to
be achieved within five minutes of the rise to or above 50.5 Hz. For a Power Station
with a Completion Date after 1st January 2009 this reduction in Active Power should
be delivered in accordance with in (i) to (iv) below. For the avoidance of doubt, the
provision of this reduction in Active Power output is not an Ancillary Service.
(i) The reduction in Active Power output must be continuously and linearly
proportional as far as practical, to the excess of Frequency above 50.5 Hz and
must be provided increasingly with time over the period specified in (iii) below.
(ii) As much as possible of the proportional reduction in Active Power output must
result from the frequency control device (or speed governor) action and must be
achieved within 10 seconds of the time of the Frequency increase above 50.5 Hz.
(iii) The residue of the proportional reduction in Active Power output which results
from automatic action of the Genset (or DC Converter at a DC Converter
Station) output control devices other than the frequency control devices (or speed
governors) must be achieved within 3 minutes from the time of the Frequency
increase above 50.5 Hz.
(iv) Any further residue of the proportional reduction which results from non-automatic
action initiated by the Generator or DC Converter Station owner shall be initiated
within 2 minutes, and achieved within 5 minutes, of the time of the Frequency
increase above 50.5 Hz.

Issue 5 Revision 0 BC3 17 August 2012


6 of 8
BC3.7.2 Plant In Limited Frequency Sensitive Mode
(a) Each Synchronised Genset (or DC Converter at a DC Converter Station) operating
in a Limited Frequency Sensitive Mode which is producing Active Power is also
required to reduce Active Power output in response to System Frequency when this
rises above 50.4 Hz. In the case of DC Converters at DC Converter Stations, the
provisions of BC3.7.7are also applicable. For the avoidance of doubt, the provision of
this reduction in Active Power output is not an Ancillary Service. Such provision is
known as "Limited High Frequency Response".

(b) (i) The rate of change of Active Power output must be at a minimum rate of 2 per
cent of output per 0.1 Hz deviation of System Frequency above 50.4 Hz.
(ii) The reduction in Active Power output must be continuously and linearly
proportional, as far as is practicable, to the excess of Frequency above 50.4 Hz
and must be provided increasingly with time over the period specified in (iii) below.
(iii) As much as possible of the proportional reduction in Active Power output must
result from the frequency control device (or speed governor) action and must be
achieved within 10 seconds of the time of the Frequency increase above 50.4 Hz.
(iv) The residue of the proportional reduction in Active Power output which results
from automatic action of the Genset (or DC Converter at a DC Converter
Station) output control devices other than the frequency control devices (or speed
governors) must be achieved within 3 minutes from the time of the Frequency
increase above 50.4 Hz.
(v) Any further residue of the proportional reduction which results from non-automatic
action initiated by the Generator or DC Converter Station owner shall be initiated
within 2 minutes, and achieved within 5 minutes, of the time of the Frequency
increase above 50.4 Hz.
(c) Each Genset (or DC Converter at a DC Converter Station) which is providing Limited
High Frequency Response in accordance with this BC3.7.2 must continue to provide it
until the Frequency has returned to or below 50.4 Hz or until otherwise instructed by
NGET.

BC3.7.3 Plant Operation To Below Minimum Generation


(a) As stated in CC.A.3.2, steady state operation below Minimum Generation is not
expected but if System operating conditions cause operation below Minimum
Generation which give rise to operational difficulties for the Genset (or DC Converter
at a DC Converter Station) then NGET should not, upon request, unreasonably
withhold issuing a Bid-Offer Acceptance to return the Generating Unit or CCGT
Module or Power Park Module or DC Converter to an output not less than Minimum
Generation. In the case of a DC Converter not participating in the Balancing
Mechanism, then NGET will, upon request, attempt to return the DC Converter to an
output not less than Minimum Generation or to zero transfer or to reverse the transfer
of Active Power.
(b) It is possible that a Synchronised Genset (or a DC Converter at a DC Converter
Station) which responded as required under BC3.7.1 or BC3.7.2 to an excess of
System Frequency, as therein described, will (if the output reduction is large or if the
Genset (or a DC Converter at a DC Converter Station) output has reduced to below
the Designed Minimum Operating Level) trip after a time.
(c) All reasonable efforts should in the event be made by the Generator or DC Converter
Station owner to avoid such tripping, provided that the System Frequency is below
52Hz.

Issue 5 Revision 0 BC3 17 August 2012


7 of 8
(d) If the System Frequency is at or above 52Hz, the requirement to make all reasonable
efforts to avoid tripping does not apply and the Generator or DC Converter Station
owner is required to take action to protect the Generating Units, Power Park Modules
or DC Converters as specified in CC.6.3.13.
(e) In the event of the System Frequency becoming stable above 50.5Hz, after all Genset
and DC Converter action as specified in BC3.7.1 and BC3.7.2 has taken place, NGET
will issue appropriate Bid-Offer Acceptances and/or Ancillary Service instructions,
which may include Emergency Instructions under BC2 to trip Gensets (or, in the case
of DC Converters at DC Converter Stations, to stop or reverse the transfer of Active
Power) so that the Frequency returns to below 50.5Hz and ultimately to Target
Frequency.
(f) If the System Frequency has become stable above 52 Hz, after all Genset and DC
Converter action as specified in BC3.7.1 and BC3.7.2 has taken place, NGET will issue
Emergency Instructions under BC2 to trip appropriate Gensets (or in the case of DC
Converters at DC Converter Stations to stop or reverse the transfer of Active Power)
to bring the System Frequency to below 52Hz and follow this with appropriate Bid-
Offer Acceptances or Ancillary Service instructions or further Emergency
Instructions under BC2 to return the System Frequency to below 50.5 Hz and
ultimately to Target Frequency.
BC3.7.4 The Generator or DC Converter Station owner will not be in breach of any of the provisions
of BC2 by following the provisions of BC3.7.1, BC3.7.2 or BC3.7.3.
BC3.7.5 Information Update To NGET
In order that NGET can deal with the emergency conditions effectively, it needs as much up
to date information as possible and accordingly NGET must be informed of the action taken
in accordance with BC3.7.1(c) and BC3.7.2 as soon as possible and in any event within 7
minutes of the rise in System Frequency, directly by telephone from the Control Point for
the Power Station or DC Converter Station.

BC3.7.6 (a) Existing Gas Cooled Reactor Plant


For the avoidance of doubt, Generating Units within Existing Gas Cooled Reactor
Plant are required to comply with the applicable provisions of this BC3.7 (which, for the
avoidance of doubt, other than for Frequency Sensitive AGR Units, do not include
BC3.7.1).
(b) Power Park Modules In Operation Before 1 January 2006.
For the avoidance of doubt, Power Park Modules in operation (irrespective of their
Completion Dates) before 1 January 2006 are required to comply with the applicable
provisions of this BC3.7 (which, for the avoidance of doubt do not include BC3.7.1).

BC3.7.7 Externally Interconnected System Operators


NGET will use reasonable endeavours to ensure that, if System Frequency rises above
50.4Hz, and an Externally Interconnected System Operator (in its role as operator of the
External System) is transferring power into the National Electricity Transmission System
from its External System, the amount of power transferred in to the National Electricity
Transmission System from the System of that Externally Interconnected System
Operator is reduced at a rate equivalent to (or greater than) that which applies for
Synchronised Gensets operating in Limited Frequency Sensitive Mode which are
producing Active Power. This will be done either by utilising existing arrangements which
are designed to achieve this, or by issuing Emergency Instructions under BC2.

< END OF BALANCING CODE 3 >

Issue 5 Revision 0 BC3 17 August 2012


8 of 8
DATA REGISTRATION CODE
(DRC)

CONTENTS
(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


DRC.1 INTRODUCTION ................................................................................................................................ 4
DRC.2 OBJECTIVE ....................................................................................................................................... 4
DRC.3 SCOPE .............................................................................................................................................. 4
DRC.4 DATA CATEGORIES AND STAGES IN REGISTRATION ................................................................. 4
DRC.4.2 Standard Planning Data .......................................................................................................... 5
DRC.4.3 Detailed Planning Data ............................................................................................................ 5
DRC.4.4 Operational Data ..................................................................................................................... 5
DRC.5 PROCEDURES AND RESPONSIBILITIES ........................................................................................ 5
DRC.5.1 Responsibility For Submission And Updating Of Data ............................................................. 5
DRC.5.2 Methods Of Submitting Data .................................................................................................... 5
DRC.5.3 Changes To Users Data .......................................................................................................... 6
DRC.5.4 Data Not Supplied ................................................................................................................... 6
DRC.5.5 Substituted Data ...................................................................................................................... 6
DRC.6 DATA TO BE REGISTERED .............................................................................................................. 6
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE AND DC
CONVERTER TECHNICAL DATA ................................................................................................................. 10
SCHEDULE 2 - GENERATION PLANNING PARAMETERS ......................................................................... 31
SCHEDULE 3 - LARGE POWER STATION OUTAGE PROGRAMMES, OUTPUT USABLE AND
INFLEXIBILITY INFORMATION ..................................................................................................................... 34
SCHEDULE 4 - LARGE POWER STATION DROOP AND RESPONSE DATA ............................................ 37
SCHEDULE 5 - USERS SYSTEM DATA ....................................................................................................... 38
SCHEDULE 6 - USERS OUTAGE INFORMATION ....................................................................................... 48
SCHEDULE 7 - LOAD CHARACTERISTICS AT GRID SUPPLY POINTS ..................................................... 52
SCHEDULE 8 - DATA SUPPLIED BY BM PARTICIPANTS .......................................................................... 53
SCHEDULE 9 - DATA SUPPLIED BY NGET TO USERS ............................................................................. 54
SCHEDULE 10 - DEMAND PROFILES AND ACTIVE ENERGY DATA ......................................................... 56
SCHEDULE 11 - CONNECTION POINT DATA ............................................................................................. 59
SCHEDULE 12 - DEMAND CONTROL.......................................................................................................... 63
SCHEDULE 13 - FAULT INFEED DATA ....................................................................................................... 67
SCHEDULE 13 - FAULT INFEED DATA ....................................................................................................... 68
SCHEDULE 14 - FAULT INFEED DATA (GENERATORS INCLUDING UNIT TRANSFORMERS AND
STATION TRANSFORMERS) ....................................................................................................................... 69
SCHEDULE 15 - MOTHBALLED GENERATING UNIT, MOTHBALLED POWER PARK MODULE,
MOTHBALLED DC CONVERTERS AT A DC CONVERTER STATION AND ALTERNATIVE FUEL
DATA) ............................................................................................................................................................ 75
Issue 5 Revision 15 DRC 03 February 2016
i of 105
SCHEDULE 16 - BLACK START INFORMATION ......................................................................................... 78
SCHEDULE 17 - ACCESS PERIOD DATA ................................................................................................... 79
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA .................................................................. 80
SCHEDULE 19 - USER DATA FILE STRUCTURE...................................................................................... 104

Issue 5 Revision 15 DRC 03 February 2016


ii of 105
Issue 5 Revision 15 DRC 03 February 2016
3 of 105
DRC.1 INTRODUCTION
DRC.1.1 The Data Registration Code ("DRC") presents a unified listing of all data required by
NGET from Users and by Users from NGET, from time to time under the Grid Code. The
data which is specified in each section of the Grid Code is collated here in the DRC.
Where there is any inconsistency in the data requirements under any particular section of
the Grid Code and the Data Registration Code the provisions of the particular section of
the Grid Code shall prevail.
DRC.1.2 The DRC identifies the section of the Grid Code under which each item of data is required.
DRC.1.3 The Code under which any item of data is required specifies procedures and timings for the
supply of that data, for routine updating and for recording temporary or permanent changes
to that data. All timetables for the provision of data are repeated in the DRC.
DRC.1.4 Various sections of the Grid Code also specify information which the Users will receive
from NGET. This information is summarised in a single schedule in the DRC (Schedule 9).
DRC.1.5 The categorisation of data into DPD I and DPD II is indicated in the DRC below.

DRC.2 OBJECTIVE
The objective of the DRC is to:
DRC.2.1 List and collate all the data to be provided by each category of User to NGET under the
Grid Code.
DRC.2.2 List all the data to be provided by NGET to each category of User under the Grid Code.

DRC.3 SCOPE
DRC.3.1 The DRC applies to NGET and to Users, which in this DRC means:-
(a) Generators (including those undertaking OTSDUW);
(b) Network Operators;
(c) DC Converter Station owners;
(d) Suppliers;
(e) Non-Embedded Customers (including, for the avoidance of doubt, a Pumped
Storage Generator in that capacity);
(f) Externally Interconnected System Operators;
(g) Interconnector Users; and
(h) BM Participants.

DRC.4 DATA CATEGORIES AND STAGES IN REGISTRATION


DRC.4.1.1 Within the DRC each data item is allocated to one of the following three categories:
(a) Standard Planning Data (SPD)
(b) Detailed Planning Data (DPD)
(c) Operational Data

Issue 5 Revision 15 DRC 03 February 2016


4 of 105
DRC.4.2 Standard Planning Data (SPD)
DRC.4.2.1 The Standard Planning Data listed and collated in this DRC is that data listed in Part 1 of
the Appendix to the PC.
DRC.4.2.2 Standard Planning Data will be provided to NGET in accordance with PC.4.4 and
PC.A.1.2.
DRC.4.3 Detailed Planning Data (DPD)
DRC.4.3.1 The Detailed Planning Data listed and collated in this DRC is categorised as DPD I and
DPD II and is that data listed in Part 2 of the Appendix to the PC.
DRC.4.3.2 Detailed Planning Data will be provided to NGET in accordance with PC.4.4, PC.4.5 and
PC.A.1.2.
DRC.4.4 Operational Data
DRC.4.4.1 Operational Data is data which is required by the Operating Codes and the Balancing
Codes. Within the DRC, Operational Data is sub-categorised according to the Code under
which it is required, namely OC1, OC2, BC1 or BC2.
DRC.4.4.2 Operational Data is to be supplied in accordance with timetables set down in the relevant
Operating Codes and Balancing Codes and repeated in tabular form in the schedules to
the DRC.

DRC.5 PROCEDURES AND RESPONSIBILITIES


DRC.5.1 Responsibility For Submission And Updating Of Data
In accordance with the provisions of the various sections of the Grid Code, each User must
submit data as summarised in DRC.6 and listed and collated in the attached schedules.
DRC.5.2 Methods Of Submitting Data
DRC.5.2.1 Wherever possible the data schedules to the DRC are structured to serve as standard
formats for data submission and such format must be used for the written submission of
data to NGET.
DRC.5.2.2 Data must be submitted to the Transmission Control Centre notified by NGET or to such
other department or address as NGET may from time to time advise. The name of the
person at the User Site who is submitting each schedule of data must be included.
DRC.5.2.3 Where a computer data link exists between a User and NGET, data may be submitted via
this link. NGET will, in this situation, provide computer files for completion by the User
containing all the data in the corresponding DRC schedule.
Data submitted can be in an electronic format using a proforma to be supplied by NGET or
other format to be agreed annually in advance with NGET. In all cases the data must be
complete and relate to, and relate only to, what is required by the relevant section of the
Grid Code.
DRC.5.2.4 Other modes of data transfer, such as magnetic tape, may be utilised if NGET gives its
prior written consent.
DRC.5.2.5 Generators and DC Converter Station owners submitting data for a Generating Unit, DC
Converter, Power Park Module or CCGT Module before the issue of a Final Operational
Notification should submit the DRC data schedules and compliance information required
under the CP electronically using the User Data File Structure unless otherwise agreed
with NGET.

Issue 5 Revision 15 DRC 03 February 2016


5 of 105
DRC.5.3 Changes To Users' Data
DRC.5.3.1 Whenever a User becomes aware of a change to an item of data which is registered with
NGET the User must notify NGET in accordance with each section of the Grid Code. The
method and timing of the notification to NGET is set out in each section of the Grid Code.
DRC.5.4 Data Not Supplied
DRC.5.4.1 Users and NGET are obliged to supply data as set out in the individual sections of the Grid
Code and repeated in the DRC. If a User fails to supply data when required by any section
of the Grid Code, NGET will estimate such data if and when, in the NGET's view, it is
necessary to do so. If NGET fails to supply data when required by any section of the Grid
Code, the User to whom that data ought to have been supplied, will estimate such data if
and when, in that User's view, it is necessary to do so. Such estimates will, in each case,
be based upon data supplied previously for the same Plant or Apparatus or upon
corresponding data for similar Plant or Apparatus or upon such other information as NGET
or that User, as the case may be, deems appropriate.
DRC.5.4.2 NGET will advise a User in writing of any estimated data it intends to use pursuant to
DRC.5.4.1 relating directly to that User's Plant or Apparatus in the event of data not being
supplied.
DRC.5.4.3 A User will advise NGET in writing of any estimated data it intends to use pursuant to
DRC.5.4.1 in the event of data not being supplied.
DRC.5.5 Substituted Data
DRC.5.5.1 In the case of PC.A.4 only, if the data supplied by a User does not in NGETs reasonable
opinion reflect the equivalent data recorded by NGET, NGET may estimate such data if and
when, in the view of NGET, it is necessary to do so. Such estimates will, in each case, be
based upon data supplied previously for the same Plant or Apparatus or upon
corresponding data for similar Plant or Apparatus or upon such other information as NGET
deems appropriate.
DRC.5.5.2 NGET will advise a User in writing of any estimated data it intends to use pursuant to
DRC.5.5.1 relating directly to that User's Plant or Apparatus where it does not in NGETs
reasonable opinion reflect the equivalent data recorded by NGET. Such estimated data will
be used by NGET in place of the appropriate data submitted by the User pursuant to
PC.A.4 and as such shall be deemed to accurately represent the Users submission until
such time as the User provides data to NGETs reasonable satisfaction.

DRC.6 DATA TO BE REGISTERED


DRC.6.1 Schedules 1 to 19 attached cover the following data areas.
DRC.6.1.1 Schedule 1 - Generating Unit (Or CCGT Module), Power Park Module (Including Power
Park Unit) And DC Converter Technical Data.
Comprising Generating Unit (and CCGT Module), Power Park Module (including Power
Park Unit) and DC Converter fixed electrical parameters.
DRC.6.1.2 Schedule 2 - Generation Planning Parameters
Comprising the Genset parameters required for Operational Planning studies.
DRC.6.1.3 Schedule 3 - Large Power Station Outage Programmes, Output Usable And Inflexibility
Information.
Comprising generation outage planning, Output Usable and inflexibility information at
timescales down to the daily BM Unit Data submission.

Issue 5 Revision 15 DRC 03 February 2016


6 of 105
DRC.6.1.4 Schedule 4 - Large Power Station Droop And Response Data.
Comprising data on governor Droop settings and Primary, Secondary and High
Frequency Response data for Large Power Stations.
DRC.6.1.5 Schedule 5 - User's System Data.
Comprising electrical parameters relating to Plant and Apparatus connected to the
National Electricity Transmission System.
DRC.6.1.6 Schedule 6 - Users Outage Information.
Comprising the information required by NGET for outages on the Users System, including
outages at Power Stations other than outages of Gensets
DRC.6.1.7 Schedule 7 - Load Characteristics.
Comprising the estimated parameters of load groups in respect of, for example, harmonic
content and response to frequency.
DRC.6.1.8 Schedule 8 - BM Unit Data.
DRC.6.1.9 Schedule 9 - Data Supplied By NGET To Users.
DRC.6.1.10 Schedule 10 - Demand Profiles And Active Energy Data
Comprising information relating to the Network Operators and Non-Embedded
Customers total Demand and Active Energy taken from the National Electricity
Transmission System
DRC.6.1.11 Schedule 11 - Connection Point Data
Comprising information relating to Demand, demand transfer capability and the Small
Power Station, Medium Power Station and Customer generation connected to the
Connection Point
DRC.6.1.12 Schedule 12 - Demand Control Data
Comprising information related to Demand Control
DRC.6.1.13 Schedule 13 - Fault Infeed Data
Comprising information relating to the short circuit contribution to the National Electricity
Transmission System from Users other than Generators and DC Converter Station
owners.
DRC.6.1.14 Schedule 14 - Fault Infeed Data (Generators Including Unit And Station Transformers)
Comprising information relating to the Short Circuit contribution to the National Electricity
Transmission System from Generators and DC Converter Station owners.
DRC.6.1.15 Schedule 15 Mothballed Generating Unit, Mothballed Power Park Module, Mothballed DC
Converters At A DC Converter Station And Alternative Fuel Data
Comprising information relating to estimated return to service times for Mothballed
Generating Units, Mothballed Power Park Modules and Mothballed DC Converters at a
DC Converter Station and the capability of gas-fired Generating Units to operate using
alternative fuels.
DRC.6.1.16 Schedule 16 Black Start Information
Comprising information relating to Black Start.
DRC.6.1.17 Schedule 17 Access Period Schedule
Comprising Access Period information for Transmission Interface Circuits within an
Access Group.

Issue 5 Revision 15 DRC 03 February 2016


7 of 105
DRC.6.1.18 Schedule 18 Generators Undertaking OTSDUW Arrangements
Comprising electrical parameters relating to OTSDUW Plant and Apparatus between the
Offshore Grid Entry Point and Transmission Interface Point.
DRC.6.1.19 Schedule 19 User Data File Structure
Comprising information relating to the User Data File Structure.
DRC.6.2 The Schedules applicable to each class of User are as follows:

User Schedule

Generators with Large Power Stations 1, 2, 3, 4, 9, 14,


15, 16, 19

Generators with Medium Power Stations 1, 2 (part), 9,


(see notes 2, 3, 4) 14, 15, 19

Generators with Small Power Stations directly connected to 1, 6, 14, 15, 19


the National Electricity Transmission System

Generators undertaking OTSDUW 18, 19


(see note 5)

All Users connected directly to the National Electricity 5, 6, 9


Transmission System

All Users connected directly to the National Electricity 10,11,13,17


Transmission System other than Generators

All Users connected directly to the National Electricity 7, 9


Transmission System with Demand

A Pumped Storage Generator, Externally Interconnected 12


System Operator and Interconnector Users (as marked)

All Suppliers 12

All Network Operators 12

All BM Participants 8

All DC Converter Station owners 1, 4, 9, 14, 15, 19

Notes:
(1) Network Operators must provide data relating to Small Power Stations and/or
Customer Generating Plant Embedded in their Systems when such data is
requested by NGET pursuant to PC.A.3.1.4 or PC.A.5.1.4.
(2) The data in schedules 1, 14 and 15 need not be supplied in relation to Medium Power
Stations connected at a voltage level below the voltage level of the Subtransmission
System except in connection with a CUSC Contract or unless specifically requested
by NGET.
(3) Each Network Operator within whose System an Embedded Medium Power Station
not subject to a Bilateral Agreement or Embedded DC Converter Station not subject
to a Bilateral Agreement is situated shall provide the data to NGET in respect of each
such Embedded Medium Power Station or Embedded DC Converter Station.

Issue 5 Revision 15 DRC 03 February 2016


8 of 105
(4) In the case of Schedule 2, Generators, DC Converter Station owners or Network
Operators in the case of Embedded Medium Power Stations not subject to a
Bilateral Agreement or Embedded DC Converter Stations not subject to a Bilateral
Agreement, would only be expected to submit data in relation to Standard Planning
Data as required by the Planning Code.
(5) In the case of Generators undertaking OTSDUW, the Generator will need to supply
User data in accordance with the requirements of Large or Small Power Stations (as
defined in DRC.6.2) up to the Offshore Grid Entry Point. In addition, the User will
also need to submit Offshore Transmission System data in between the Interface
Point and its Connection Points in accordance with the requirements of Schedule 18.

Issue 5 Revision 15 DRC 03 February 2016


9 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 1 OF 19

ABBREVIATIONS:
SPD = Standard Planning Data DPD = Detailed Planning Data

% on MVA = % on Rated MVA RC = Registered Capacity

% on 100 = % on 100 MVA OC1, BC1, etc = Grid Code


for which data is required

CUSC Contract = User data which may be CUSC App. Form = User data which may
submitted to the be submitted to the
Relevant Transmission Relevant
Licensees by NGET, Transmission
following the acceptance Licensees by NGET,
by a User of a CUSC following an application
Contract. by a User for a CUSC
Contract.

Note:
All parameters, where applicable, are to be measured at nominal System Frequency
+ these SPD items should only be given in the data supplied with the application for a CUSC
Contract.
* Asterisk items are not required for Small Power Stations and Medium Power Stations
Information is to be given on a Unit basis, unless otherwise stated. Where references to CCGT
Modules are made, the columns "G1" etc should be amended to read "M1" etc, as appropriate
These data items may be submitted to the Relevant Transmission Licensees from NGET in
respect of the National Electricity Transmission System. The data may be submitted to the
Relevant Transmission Licensees in a summarised form e.g. network model; the data
transferred will have been originally derived from data submitted by Users to NGET.
these data items may be submitted to the Relevant Transmission Licensee from NGET in
respect to Relevant Units only. The data may be submitted to the Relevant Transmission
Licensee in a summarised form e.g. network model; the data transferred will have been
originally derived from data submitted by Users to NGET.

Issue 5 Revision 15 DRC 03 February 2016


10 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 2 OF 19

POWER STATION NAME: _________________________ DATE: _____________

DATA to DATA GENERATING UNIT OR STATION DATA


DATA DESCRIPTION UNITS RTL CAT.
CUSC CUSC F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr.
Cont App.
ract Form 0 1 2 3 4 5 6
GENERATING STATION DEMANDS:
Demand associated with the Power
Station supplied through the National
Electricity Transmission System or
the Generator's User System (PC.A.5.2)

- The maximum Demand that could MW DPD I


occur. MVAr DPD I
- Demand at specified time of annual MW DPD II
peak half hour of National Electricity MVAr DPD II
Transmission System Demand at
Annual ACS Conditions.

- Demand at specified time of annual MW DPD II


minimum half-hour of National MVAr DPD II
Electricity Transmission System
Demand.

(Additional Demand supplied through


the unit transformers to be provided
below)

INDIVIDUAL GENERATING UNIT (OR G1 G2 G3 G4 G5 G6 STN


AS THE CASE MAY BE, CCGT
MODULE) DATA

Point of connection to the National Text SPD


Electricity Transmission System (or
the Total System if embedded) of the
Generating Unit (other than a CCGT
Unit) or the CCGT Module, as the case
may be in terms of geographical and
electrical location and system voltage
(PC.A.3.4.1)

If the busbars at the Connection Point Section SPD


are normally run in separate sections Number
identify the section to which the
Generating Unit (other than a CCGT
Unit) or CCGT Module, as the case may
be is connected (PC.A.3.1.5)

Type of Unit (steam, Gas Turbine


Combined Cycle Gas Turbine Unit,
tidal, wind, etc.)
(PC.A.3.2.2 (h))

Issue 5 Revision 15 DRC 03 February 2016


11 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 3 OF 19

INDIVIDUAL GENERATING UNIT (OR G1 G2 G3 G4 G5 G6 STN


AS THE CASE MAY BE, CCGT
MODULE) DATA

A list of the CCGT Units within a CCGT SPD


Module, identifying each CCGT Unit,
and the CCGT Module of which it forms
part, unambiguously. In the case of a
Range CCGT Module, details of the
possible configurations should also be
submitted.
(PC.A.3.2.2 (g))

Issue 5 Revision 15 DRC 03 February 2016


12 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK
MODULE AND DC CONVERTER TECHNICAL DATA
PAGE 4 OF 19

DATA to DATA GENERATING UNIT (OR CCGT MODULE,


DATA DESCRIPTION UNITS RTL CAT. AS THE CASE MAY BE)
CUSC CUSC G1 G2 G3 G4 G5 G6 STN
Cont App.
ract Form
Rated MVA (PC.A.3.3.1) MVA SPD+
Rated MW (PC.A.3.3.1) MW SPD+
Rated terminal voltage (PC.A.5.3.2.(a) & kV DPD I
PC.A.5.4.2 (b))
*Performance Chart at Onshore SPD (see OC2 for specification)
Synchronous Generating Unit stator
terminals (PC.A.3.2.2(f)(i))
* Performance Chart of the Offshore
Synchronous Generating Unit at the
Offshore Grid Entry Point
(PC.A.3.2.2(f)(ii))
* Maximum terminal voltage set kV DPD I
point(PC.A.5.3.2.(a) & PC.A.5.4.2 (b))
* Terminal voltage set point step resolution kV DPD I
if not continuous (PC.A.5.3.2.(a) &
PC.A.5.4.2 (b))
*Output Usable (on a monthly basis) MW SPD (except in relation to CCGT Modules when required
(PC.A.3.2.2(b)) on a unit basis under the Grid Code, this data item
may be supplied under Schedule 3)
Turbo-Generator inertia constant (for MW secs SPD+
synchronous machines) (PC.A.5.3.2(a)) /MVA
Short circuit ratio (synchronous machines) SPD+
(PC.A.5.3.2(a))
Normal auxiliary load supplied by the MW DPD II
Generating Unit at rated MW output MVAr DPD II
(PC.A.5.2.1)
Rated field current at rated MW and MVAr A DPD II
output and at rated terminal voltage
(PC.A.5.3.2 (a))

Field current open circuit saturation curve


(as derived from appropriate
manufacturers' test certificates):
(PC.A.5.3.2 (a)) A DPD II
120% rated terminal volts A DPD II
110% rated terminal volts A DPD II
100% rated terminal volts A DPD II
90% rated terminal volts A DPD II
80% rated terminal volts A DPD II
70% rated terminal volts A
DPD II
60% rated terminal volts A
DPD II
50% rated terminal volts
IMPEDANCES:
(Unsaturated)
Direct axis synchronous reactance % on MVA DPD I
(PC.A.5.3.2(a))
Direct axis transient reactance % on MVA SPD+
(PC.A.3.3.1(a)& PC.A.5.3.2(a)
Direct axis sub-transient reactance % on MVA DPD I
(PC.A.5.3.2(a))
Quad axis synch reactance (PC.A.5.3.2(a)) % on MVA DPD I
Quad axis sub-transient reactance % on MVA DPD I
(PC.A.5.3.2(a))
Stator leakage reactance (PC.A.5.3.2(a)) % on MVA DPD I
Armature winding direct current % on MVA DPD I
resistance. (PC.A.5.3.2(a))
In Scotland, negative sequence resistance % on MVA DPD I
(PC.A.2.5.6 (a) (iv)

Issue 5 Revision 15 DRC 03 February 2016


13 of 105
Note:- the above data item relating to armature winding direct-current resistance need only be provided by Generators in relation to
Generating Units commissioned after 1st March 1996 and in cases where, for whatever reason, the Generator is aware of
the value of the data item.

Issue 5 Revision 15 DRC 03 February 2016


14 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 5 OF 19

DATA to DATA GENERATING UNIT OR STATION DATA


DATA DESCRIPTION UNITS RTL CAT.
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form

TIME CONSTANTS
(Short-circuit and Unsaturated)
Direct axis transient time constant S DPD I
(PC.A.5.3.2(a))
Direct axis sub-transient time constant S DPD I
(PC.A.5.3.2(a))
Quadrature axis sub-transient time constant S DPD I
(PC.A.5.3.2(a))
Stator time constant (PC.A.5.3.2(a)) S DPD I

MECHANICAL PARAMETERS
(PC.A.5.3.2(a))
The number of turbine generator masses DPD II
Diagram showing the Inertia and parameters Kgm2 DPD II
for each turbine generator mass for the DPD II
complete drive train
Diagram showing Stiffness constants and Nm/rad DPD II
parameters between each turbine generator DPD II
mass for the complete drive train
Number of poles DPD II
Relative power applied to different parts of % DPD II
the turbine
Torsional mode frequencies Hz DPD II
Modal damping decrement factors for the DPD II
different mechanical modes

GENERATING UNIT STEP-UP


TRANSFORMER

Rated MVA (PC.A.3.3.1 & PC.A.5.3.2) MVA SPD+


Voltage Ratio (PC.A.5.3.2) - DPD I
Positive sequence reactance: (PC.A.5.3.2)
Max tap % on MVA SPD+
Min tap % on MVA SPD+
Nominal tap % on MVA SPD+
Positive sequence resistance: (PC.A.5.3.2)
Max tap % on MVA DPD II
Min tap % on MVA DPD II
Nominal tap % on MVA DPD II
Zero phase sequence reactance % on MVA DPD II
(PC.A.5.3.2)
Tap change range (PC.A.5.3.2) +% / -% DPD II
Tap change step size (PC.A.5.3.2) % DPD II
Tap changer type: on-load or off-circuit On/Off DPD II
(PC.A.5.3.2)

Issue 5 Revision 15 DRC 03 February 2016


15 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 6 OF 19

DATA to DATA GENERATING UNIT OR STATION DATA


DATA DESCRIPTION UNITS RTL CAT.
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form
EXCITATION:

Note: The data items requested under Option 1 below may continue to be provided by Generators in relation to Generating
Units on the System at 9 January 1995 (in this paragraph, the "relevant date") or they may provide the new data items set
out under Option 2. Generators must supply the data as set out under Option 2 (and not those under Option 1) for
Generating Unit excitation control systems commissioned after the relevant date, those Generating Unit excitation control
systems recommissioned for any reason such as refurbishment after the relevant date and Generating Unit excitation
control systems where, as a result of testing or other process, the Generator is aware of the data items listed under Option
2 in relation to that Generating Unit.

Option 1

DC gain of Excitation Loop (PC.A.5.3.2(c)) DPD II


Max field voltage (PC.A.5.3.2(c)) V DPD II
Min field voltage (PC.A.5.3.2(c)) V DPD II
Rated field voltage (PC.A.5.3.2(c)) V DPD II
Max rate of change of field volts: (PC.A.5.3.2(c))
Rising V/Sec DPD II
Falling V/Sec DPD II

Details of Excitation Loop (PC.A.5.3.2(c)) Diagram DPD II (please attach)


Described in block diagram form showing
transfer functions of individual elements

Dynamic characteristics of over- excitation limiter DPD II


(PC.A.5.3.2(c))
Dynamic characteristics of under-excitation DPD II
limiter (PC.A.5.3.2(c))

Option 2

Exciter category, e.g. Rotating Exciter, or Text SPD


Static Exciter etc (PC.A.5.3.2(c))
Excitation System Nominal (PC.A.5.3.2(c))
Response VE Sec-1 DPD II
Rated Field Voltage (PC.A.5.3.2(c)) UfN V DPD II
No-load Field Voltage (PC.A.5.3.2(c)) UfO V DPD II
Excitation System On-Load (PC.A.5.3.2(c))
Positive Ceiling Voltage UpL+ V DPD II
Excitation System No-Load (PC.A.5.3.2(c))
Positive Ceiling Voltage UpO+ V DPD II
Excitation System No-Load (PC.A.5.3.2(c))
Negative Ceiling Voltage UpO- V DPD II
Power System Stabiliser (PSS) fitted
(PC.A.3.4.2) Yes/No SPD

Details of Excitation System (PC.A.5.3.2(c))


(including PSS if fitted) described in block Diagram DPD II
diagram form showing transfer functions of
individual elements.

Details of Over-excitation Limiter


(PC.A.5.3.2(c))

described in block diagram form showing Diagram DPD II
transfer functions of individual elements.

Details of Under-excitation Limiter


(PC.A.5.3.2(c))

described in block diagram form showing Diagram DPD II
transfer functions of individual elements.

Issue 5 Revision 15 DRC 03 February 2016


16 of 105
Issue 5 Revision 15 DRC 03 February 2016
17 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 7 OF 19

DATA DESCRIPTION UNITS DATA to DATA GENERATING UNIT OR STATION DATA


RTL CAT.
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form

GOVERNOR AND ASSOCIATED PRIME MOVER PARAMETERS

Note: The data items requested under Option 1 below may continue to be provided by Generators in relation to Generating Units
on the System at 9 January 1995 (in this paragraph, the "relevant date") or they may provide the new data items set out
under Option 2. Generators must supply the data as set out under Option 2 (and not those under Option 1) for Generating
Unit governor control systems commissioned after the relevant date, those Generating Unit governor control systems
recommissioned for any reason such as refurbishment after the relevant date and Generating Unit governor control systems
where, as a result of testing or other process, the Generator is aware of the data items listed under Option 2 in relation to
that Generating Unit.

Option 1

GOVERNOR PARAMETERS (REHEAT


UNITS) (PC.A.5.3.2(d) Option 1(i))

HP Governor average gain MW/Hz DPD II


Speeder motor setting range Hz DPD II
HP governor valve time constant S DPD II
HP governor valve opening limits DPD II
HP governor valve rate limits DPD II
Re-heat time constant (stored Active Energy S DPD II
in reheater)
IP governor average gain MW/Hz DPD II
IP governor setting range Hz DPD II
IP governor time constant S DPD II
IP governor valve opening limits DPD II
IP governor valve rate limits DPD II
Details of acceleration sensitive DPD II (please attach)
elements HP & IP in governor loop
Governor block diagram showing DPD II (please attach)
transfer functions of individual elements

GOVERNOR (Non-reheat steam and Gas


Turbines) (PC.A.5.3.2(d) Option 1(ii))

Governor average gain MW/Hz DPD II


Speeder motor setting range DPD II
Time constant of steam or fuel governor valve S DPD II
Governor valve opening limits DPD II
Governor valve rate limits DPD II
Time constant of turbine S DPD II
Governor block diagram DPD II (please attach)

Issue 5 Revision 15 DRC 03 February 2016


18 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 8 OF 19

DATA to DATA GENERATING UNIT OR STATION DATA


DATA DESCRIPTION UNITS RTL CAT.
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form

(PC.A.5.3.2(d) Option 1(iii))


BOILER & STEAM TURBINE DATA*
Boiler time constant (Stored Active Energy) S DPD II
HP turbine response ratio: % DPD II
(Proportion of Primary Response arising from
HP turbine)
HP turbine response ratio: % DPD II
(Proportion of High Frequency Response
arising from HP turbine)
End of Option 1
Option 2
All Generating Units

Governor Block Diagram showing DPD II


transfer function of individual elements
including acceleration sensitive elements
Governor Time Constant Sec DPD II
(PC.A.5.3.2(d) Option 2(i))
Governor Deadband
(PC.A.5.3.2(d) Option 2(i))

- Maximum Setting Hz DPD II


- Normal Setting Hz DPD II
- Minimum Setting Hz DPD II
Speeder Motor Setting Range % DPD II
(PC.A.5.3.2(d) Option 2(i))
Average Gain (PC.A.5.3.2(d) Option 2(i)) MW/Hz DPD II
Steam Units
(PC.A.5.3.2(d) Option 2(ii))
HP Valve Time Constant sec DPD II
HP Valve Opening Limits % DPD II
HP Valve Opening Rate Limits %/sec DPD II
HP Valve Closing Rate Limits %/sec DPD II
HP Turbine Time Constant sec DPD II
(PC.A.5.3.2(d) Option 2(ii))
IP Valve Time Constant sec DPD II
IP Valve Opening Limits % DPD II
IP Valve Opening Rate Limits %/sec DPD II
IP Valve Closing Rate Limits %/sec DPD II
IP Turbine Time Constant sec DPD II
(PC.A.5.3.2(d) Option 2(ii))
LP Valve Time Constant sec DPD II
LP Valve Opening Limits % DPD II
LP Valve Opening Rate Limits %/sec DPD II
LP Valve Closing Rate Limits %/sec DPD II
LP Turbine Time Constant sec DPD II
(PC.A.5.3.2(d) Option 2(ii))
Reheater Time Constant sec DPD II
Boiler Time Constant sec DPD II
HP Power Fraction % DPD II
IP Power Fraction % DPD II
# Where the generating unit governor does not have a selectable deadband facility, then the actual
value of the deadband need only be provided.

Issue 5 Revision 15 DRC 03 February 2016


19 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 9 OF 19

DATA to DATA GENERATING UNIT OR STATION DATA


DATA DESCRIPTION UNITS RTL CAT.
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form

Gas Turbine Units


(PC.A.5.3.2(d) Option 2(iii))
Inlet Guide Vane Time Constant sec DPD II
Inlet Guide Vane Opening Limits % DPD II
Inlet Guide Vane Opening Rate Limits %/sec DPD II
Inlet Guide Vane Closing Rate Limits %/sec DPD II
(PC.A.5.3.2(d) Option 2(iii))
Fuel Valve Time Constant sec DPD II
Fuel Valve Opening Limits % DPD II
Fuel Valve Opening Rate Limits %/sec DPD II
Fuel Valve Closing Rate Limits %/sec DPD II
(PC.A.5.3.2(d) Option 2(iii))
Waste Heat Recovery Boiler Time Constant

Hydro Generating Units


(PC.A.5.3.2(d) Option 2(iv))
Guide Vane Actuator Time Constant sec DPD II
Guide Vane Opening Limits % DPD II
Guide Vane Opening Rate Limits %/sec DPD II
Guide Vane Closing Rate Limits %/sec DPD II

Water Time Constant sec DPD II

End of Option 2

UNIT CONTROL OPTIONS*


(PC.A.5.3.2(e)
Maximum droop % DPD II
Normal droop % DPD II
Minimum droop % DPD II

Maximum frequency deadband Hz DPD II


Normal frequency deadband Hz DPD II
Minimum frequency deadband Hz DPD II

Maximum Output deadband MW DPD II


Normal Output deadband MW DPD II
Minimum Output deadband MW DPD II

Frequency settings between which


Unit Load Controller droop applies:

Maximum Hz DPD II
Normal Hz DPD II
Minimum Hz DPD II

Sustained response normally selected Yes/No DPD II

Issue 5 Revision 15 DRC 03 February 2016


20 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 10 OF 19

DATA to DATA POWER PARK UNIT (OR POWER PARK


DATA DESCRIPTION UNITS RTL CAT. MODULE, AS THE CASE MAY BE)
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form
Power Park Module Rated MVA MVA SPD+
(PC.A.3.3.1(a))
Power Park Module Rated MW MW SPD+
(PC.A.3.3.1(a))
*Performance Chart of a Power Park Module SPD (see OC2 for specification)
at the connection point (PC.A.3.2.2(f)(ii))

*Output Usable (on a monthly basis) MW SPD (except in relation to CCGT Modules when
(PC.A.3.2.2(b)) required on a unit basis under the Grid Code,
this data item may be supplied under Schedule
3)
Number & Type of Power Park Units within SPD
each Power Park Module (PC.A.3.2.2(k))
Number & Type of Offshore Power Park SPD
Units within each Offshore Power Park
String and the number of Offshore Power
Park Strings and connection point within
each Offshore Power Park Module
(PC.A.3.2.2.(k))
In the case where an appropriate Reference the SPD
Manufacturers Data & Performance Manufacturers
Report is registered with NGET then subject Data &
to NGETs agreement, the report reference Performance
may be given as an alternative to completion Report
of the following sections of this Schedule 1 to
the end of page 11 with the exception of the
sections marked thus # below.

Power Park Unit Model - A validated Transfer function DPD II


mathematical model in accordance with block diagram
PC.5.4.2 (a) and algebraic
equations,
simulation and
measured test
results

Issue 5 Revision 15 DRC 03 February 2016


21 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 11 OF 19

DATA to DATA POWER PARK UNIT (OR POWER PARK


DATA DESCRIPTION UNITS RTL CAT. MODULE, AS THE CASE MAY BE)
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form
Power Park Unit Data (where applicable)
Rated MVA (PC.A.3.3.1(e)) MVA SPD+
Rated MW (PC.A.3.3.1(e)) MW SPD+
Rated terminal voltage (PC.A.3.3.1(e)) V SPD+
Site minimum air density (PC.A.5.4.2(b)) kg/m3 DPD II
Site maximum air density kg/m3 DPD II
Site average air density kg/m3 DPD II
Year for which air density data is submitted DPD II
Number of pole pairs DPD II
Blade swept area m2 DPD II
Gear Box Ratio DPD II
Stator Resistance (PC.A.5.4.2(b)) % on MVA SPD+
Stator Reactance (PC.A.3.3.1(e)) % on MVA SPD+
Magnetising Reactance (PC.A.3.3.1(e)) % on MVA SPD+
Rotor Resistance (at starting). % on MVA DPD II
(PC.A.5.4.2(b))
Rotor Resistance (at rated running) % on MVA SPD+
(PC.A.3.3.1(e))
Rotor Reactance (at starting). % on MVA DPD II
(PC.A.5.4.2(b))
Rotor Reactance (at rated running) % on MVA SPD
(PC.A.3.3.1(e))
Equivalent inertia constant of the first mass MW secs SPD+
(e.g. wind turbine rotor and blades) at /MVA
minimum speed
(PC.A.5.4.2(b))
Equivalent inertia constant of the first mass MW secs SPD+
(e.g. wind turbine rotor and blades) at /MVA
synchronous speed (PC.A.5.4.2(b))
Equivalent inertia constant of the first mass MW secs SPD+
(e.g. wind turbine rotor and blades) at rated /MVA
speed
(PC.A.5.4.2(b))
Equivalent inertia constant of the second mass MW secs SPD+
(e.g. generator rotor) at minimum speed /MVA
(PC.A.5.4.2(b))
Equivalent inertia constant of the second mass MW secs SPD+
(e.g. generator rotor) at synchronous speed /MVA
(PC.A.5.4.2(b))
Equivalent inertia constant of the second mass MW secs SPD+
(e.g. generator rotor) at rated speed /MVA
(PC.A.5.4.2(b))
Equivalent shaft stiffness between the two Nm / electrical SPD+
masses (PC.A.5.4.2(b)) radian

Issue 5 Revision 15 DRC 03 February 2016


22 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 12 OF 19

DATA to DATA POWER PARK UNIT (OR POWER PARK


DATA DESCRIPTION UNITS RTL CAT. MODULE, AS THE CASE MAY BE)
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form

Minimum generator rotor speed (Doubly Fed RPM SPD+


Induction Generators) (PC.A.3.3.1(e))
Maximum generator rotor speed (Doubly Fed RPM SPD+
Induction Generators) (PC.A.3.3.1(e))

The optimum generator rotor speed versus wind tabular DPD II


speed (PC.A.5.4.2(b)) format

Power Converter Rating (Doubly Fed Induction MVA DPD II


Generators) (PC.A.5.4.2(b))

The rotor power coefficient (Cp) versus tip speed Diagram + DPD II
ratio () curves for a range of blade angles tabular
(where applicable) (PC.A.5.4.2(b)) format

# The electrical power output versus generator Diagram + DPD II


rotor speed for a range of wind speeds over the tabular
entire operating range of the Power Park Unit. format
(PC.A.5.4.2(b))

The blade angle versus wind speed curve Diagram + DPD II


(PC.A.5.4.2(b)) tabular
format

The electrical power output versus wind speed Diagram + DPD II


over the entire operating range of the Power tabular
Park Unit. format
(PC.A.5.4.2(b))

Transfer function block diagram, parameters Diagram DPD II


and description of the operation of the power
electronic converter including fault ride though
capability (where applicable). (PC.A.5.4.2(b))

For a Power Park Unit consisting of a


synchronous machine in combination with a
back to back DC Converter, or for a Power
Park Unit not driven by a wind turbine, the
data to be supplied shall be agreed with NGET
in accordance with PC.A.7. (PC.A.5.4.2(b))

Issue 5 Revision 15 DRC 03 February 2016


23 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 13 OF 19

DATA to DATA POWER PARK UNIT (OR POWER PARK


DATA DESCRIPTION UNITS RTL CAT. MODULE, AS THE CASE MAY BE)
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form

Torque / Speed and blade angle control systems and Diagram DPD II
parameters (PC.A.5.4.2(c))

For the Power Park Unit, details of the torque /


speed controller and blade angle controller in the
case of a wind turbine and power limitation functions
(where applicable) described in block diagram form
showing transfer functions and parameters of
individual elements

# Voltage/Reactive Power/Power Factor control Diagram DPD II


system parameters (PC.A.5.4.2(d))

# For the Power Park Unit and Power Park


Module details of Voltage/Reactive Power/Power
Factor controller (and PSS if fitted) described in
block diagram form including parameters showing
transfer functions of individual elements.

# Frequency control system parameters Diagram DPD II


(PC.A.5.4.2(e))
# For the Power Park Unit and Power Park
Module details of the Frequency controller
described in block diagram form showing transfer
functions and parameters of individual elements.

As an alternative to PC.A.5.4.2 (a), (b), (c), (d), (e) Diagram DPD II


and (f), is the submission of a single complete model
that consists of the full information required under
PC.A.5.4.2 (a), (b), (c), (d) (e) and (f) provided that all
the information required under PC.A.5.4.2 (a), b), (c),
(d), (e) and (f) individually is clearly identifiable.
(PC.A.5.4.2(g))

# Harmonic Assessment Information


(PC.A.5.4.2(h))
(as defined in IEC 61400-21 (2001)) for each Power
Park Unit:-
# Flicker coefficient for continuous operation DPD I
# Flicker step factor DPD I
# Number of switching operations in a 10 minute DPD I
window
# Number of switching operations in a 2 hour window DPD I
# Voltage change factor DPD I
# Current Injection at each harmonic for each Power Tabular DPD I
Park Unit and for each Power Park Module format

Issue 5 Revision 15 DRC 03 February 2016


24 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 14 OF 19

DC CONVERTER STATION TECHNICAL DATA

DC CONVERTER STATION NAME DATE:___________

Data Description Units DATA to Data DC Converter Station Data


RTL Category
CUSC CUSC
(PC.A.4) Contract App.
Form

DC CONVERTER STATION DEMANDS:

Demand supplied through Station


Transformers associated with the DC
Converter Station [PC.A.4.1]

- Demand with all DC Converters operating MW DPD II


at Rated MW import. MVAr DPD II


- Demand with all DC Converters operating MW DPD II

at Rated MW export. MVAr DPD II

Additional Demand associated with the DC


Converter Station supplied through the
National Electricity Transmission
System. [PC.A.4.1]


- The maximum Demand that could occur. MW DPD II

MVAr DPD II
- Demand at specified time of annual
peak half hour of NGET Demand at MW DPD II
Annual ACS Conditions. MVAr DPD II

- Demand at specified time of annual MW DPD II


minimum half-hour of NGET Demand. MVAr DPD II

DC CONVERTER STATION DATA

SPD+
Number of poles, i.e. number of DC Converters Text

Pole arrangement (e.g. monopole or bipole) SPD+



Text
Details of each viable operating configuration
SPD+
Configuration 1 Diagram
Configuration 2 Diagram
Configuration 3 Diagram
Configuration 4 Diagram

Configuration 5 Diagram

Configuration 6 Diagram
SPD

Remote ac connection arrangement Diagram

Issue 5 Revision 15 DRC 03 February 2016


25 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 15 OF 19

Data Description Units DATA to Data Operating Configuration


RTL Category
CUSC CUSC 1 2 3 4 5 6
Contrac App.
t Form

DC CONVERTER STATION DATA


(PC.A.3.3.1d)
Text SPD
DC Converter Type (e.g. current or Voltage
source) Text SPD

Point of connection to the NGET


Transmission System (or the Total System
ifEmbedded) of the DC Converter Station
configuration in terms of geographical and
electrical location and system voltage Section SPD
Number
If the busbars at the Connection Point are
normally run in separate sections identify the SPD+

section to which the DC Converter Station MW
configuration is connected SPD+
MW
Rated MW import per pole [PC.A.3.3.1]

Rated MW export per pole [PC.A.3.3.1]


ACTIVE POWER TRANSFER CAPABILITY
(PC.A.3.2.2)
MW SPD
Registered Capacity MW SPD
Registered Import Capacity

MW SPD

Minimum Generation MW SPD
Minimum Import Capacity

Import MW available in excess of Registered MW SPD


Import Capacity.
Time duration for which MW in excess of SPD
Registered Import Capacity is available Min
SPD
Export MW available in excess of Registered MW
Capacity. SPD
Time duration for which MW in excess of Min
Registered Capacity is available

Issue 5 Revision 15 DRC 03 February 2016


26 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 16 OF 19

Data Description Units DATA to Data Operating Configuration


RTL Category
CUSC CUSC 1 2 3 4 5 6
Contrac App.
t Form

DC CONVERTER TRANSFORMER
[PC.A.5.4.3.1 DPD II
MVA
Rated MVA DPD II

Winding arrangement kV DPD II

Nominal primary voltage kV
Nominal secondary (converter-side) voltage(s) DPD II
Positive sequence reactance % on DPD II
Maximum tap MVA DPD II
Nominal tap % on
Minimum tap MVA DPD II
Positive sequence resistance % on DPD II

Maximum tap MVA DPD II

Nominal tap DPD II
Minimum tap % on DPD II
Zero phase sequence reactance MVA DPD II
Tap change range % on
Number of steps MVA
% on
MVA
% on
MVA
+% / -%

Issue 5 Revision 15 DRC 03 February 2016


27 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK
MODULE AND DC CONVERTER TECHNICAL DATA
PAGE 17 OF 19

Data Description Units DATA to Data Operating configuration


RTL Category
CUSC CUSC 1 2 3 4 5 6
Contrac App.
t Form

DC NETWORK [PC.A.5.4.3.1 (c)]

Rated DC voltage per pole kV DPD II


Rated DC current per pole A DPD II

Details of the DC Network



described in diagram form including Diagram DPD II
resistance, inductance and capacitance of
all DC cables and/or DC lines. Details of
any line reactors (including line reactor
resistance), line capacitors, DC filters,
earthing electrodes and other conductors
that form part of the DC Network should
be shown.

DC CONVERTER STATION AC
HARMONIC FILTER AND REACTIVE
COMPENSATION EQUIPMENT
[PC.A.5.4.3.1 (d)]

For all switched reactive compensation Diagram DPD II


equipment
Text DPD II

Total number of AC filter banks Diagram DPD II

Diagram of filter connections Text
DPD II
Type of equipment (e.g. fixed or variable) MVAr DPD II
Capacitive rating; or MVAr DPD II
Inductive rating; or MVAr DPD II
Operating range
Table DPD II
Reactive Power capability as a function of
various MW transfer levels

Issue 5 Revision 15 DRC 03 February 2016


28 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 18 OF 19

Data Description Units DATA to Data Operating configuration


RTL Category
CUSC CUSC
Contract App. Form
1 2 3 4 5 6
CONTROL SYSTEMS [PC.A.5.4.3.2]

Static VDC PDC (DC voltage DC power) or


Static VDC IDC (DC voltage DC current)
characteristic (as appropriate) when operating DPD II
as Diagram DPD II
Rectifier Diagram
Inverter
DPD II
Diagram
Details of rectifier mode control system,
in block diagram form together with
parameters showing transfer functions of
individual elements.
Diagram DPD II
Details of inverter mode control system,
in block diagram form showing transfer
functions of individual elements including
parameters.
Diagram DPD II
Details of converter transformer tap changer
control system in block diagram form showing
transfer functions of individual elements
including parameters. (Only required for DC
Converters connected to the National
Electricity Transmission System.) Diagram
DPD II

Details of AC filter and reactive compensation


equipment control systems in block diagram
form showing transfer functions of individual
elements including parameters. (Only
Diagram DPD II
required for DC Converters connected to the
National Electricity Transmission System.)
Details of any frequency and/or load control
systems in block diagram form showing
transfer functions of individual elements Diagram DPD II
including parameters.

Details of any large or small signal modulating
controls, such as power oscillation damping Diagram DPD II
controls or sub-synchronous oscillation
damping controls, that have not been
submitted as part of the above control system
data.

Transfer block diagram representation of the


reactive power control at converter ends for a
voltage source converter.

Issue 5 Revision 15 DRC 03 February 2016


29 of 105
SCHEDULE 1 - GENERATING UNIT (OR CCGT MODULE), POWER PARK MODULE
AND DC CONVERTER TECHNICAL DATA
PAGE 19 OF 19

Data Description Units DATA to Data Operating configuration


RTL Category
CUSC CUSC
Contract App. Form
1 2 3 4 5 6

LOADING PARAMETERS [PC.A.5.4.3.3]

MW Export
Nominal loading rate MW/s DPD I
Maximum (emergency) loading rate MW/s DPD I

MW Import
DPD I
Nominal loading rate MW/s
DPD I
Maximum (emergency) loading rate MW/s

s DPD II
Maximum recovery time, to 90% of pre-fault
loading, following an AC system fault or
severe voltage depression.
DPD II
Maximum recovery time, to 90% of pre-fault
loading, following a transient DC Network s
fault.

NOTE: Users are referred to Schedules 5 & 14 which set down data required for all Users directly
connected to the National Electricity Transmission System, including Power Stations. Generators
undertaking OTSDUW Arrangements and are utilising an OTSDUW DC Converter are referered to
Schedule 18.

Issue 5 Revision 15 DRC 03 February 2016


30 of 105
SCHEDULE 2 - GENERATION PLANNING PARAMETERS
PAGE 1 OF 3

This schedule contains the Genset Generation Planning Parameters required by NGET to facilitate
studies in Operational Planning timescales.
For a Generating Unit (other than a Power Park Unit) at a Large Power Station the information is to be
submitted on a unit basis and for a CCGT Module or Power Park Module at a Large Power Station the
information is to be submitted on a module basis, unless otherwise stated.
Where references to CCGT Modules or Power Park Modules at a Large Power Station are made, the
columns "G1" etc should be amended to read "M1" etc, as appropriate.

Power Station: _________________________

Generation Planning Parameters


DATA to DATA GENSET OR STATION DATA
DATA DESCRIPTION UNITS RTL CAT.
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form

OUTPUT CAPABILITY
(PC.A.3.2.2)
Registered Capacity on a station and unit basis
(on a station and module basis in the case of a MW SPD

CCGT Module or Power Park Module at a
Large Power Station)
Minimum Generation (on a module
basis in the case of a CCGT Module or Power MW SPD
Park Module at a Large Power Station)

MW available from Generating Units or Power


Park Modules in excess of Registered MW SPD
Capacity

REGIME UNAVAILABILITY

These data blocks are provided to


allow fixed periods of unavailability to be
registered.
Expected Running Regime. Is Power Station
normally available for full output 24 hours per SPD
day, 7 days per week? If No please provide
details of unavailability below.
(PC.A.3.2.2.)
Earliest Synchronising time: OC2.4.2.1(a)
Monday hr/min OC2 -
Tuesday Friday hr/min OC2 -
Saturday Sunday hr/min OC2 -
Latest De-Synchronising time: OC2.4.2.1(a)
Monday Thursday hr/min OC2 -
Friday hr/min OC2 -
Saturday Sunday hr/min OC2 -

SYNCHRONISING PARAMETERS
OC2.4.2.1(a)
Notice to Deviate from Zero (NDZ) after 48 hour Mins OC2
Shutdown
Station Synchronising Intervals (SI) after Mins - - - - - -
48 hour Shutdown
Synchronising Group (if applicable) 1 to 4 OC2 -

Issue 5 Revision 15 DRC 03 February 2016


31 of 105
SCHEDULE 2 - GENERATION PLANNING PARAMETERS
PAGE 2 OF 3

DATA to DATA GENSET OR STATION DATA


DATA DESCRIPTION UNITS RTL CAT.
CUSC CUSC
Contract App.
G1 G2 G3 G4 G5 G6 STN
Form

Synchronising Generation (SYG) after MW DPD II -


48 hour Shutdown &
PC.A.5.3.2(f) & OC2.4.2.1(a) OC2

De-Synchronising Intervals (Single value) Mins OC2 - - - - - -


OC2.4.2.1(a)

RUNNING AND SHUTDOWN PERIOD


LIMITATIONS:

Minimum Non Zero time (MNZT) after 48 Mins OC2


hour Shutdown OC2.4.2.1(a)

Minimum Zero time (MZT) OC2.4.2.1(a) Mins OC2

Existing AGR Plant Flexibility Limit No. OC2


(Existing AGR Plant only)

80% Reactor Thermal Power (expressed as MW OC2


Gross-Net MW) (Existing AGR Plant only)

Frequency Sensitive AGR Unit Limit No. OC2


(Frequency Sensitive AGR Units
only)

RUN-UP PARAMETERS
PC.A.5.3.2(f) & OC2.4.2.1(a)
Run-up rates (RUR) after 48 hour (Note that for DPD only a single value of run-up rate from Synch Gen to Registered
Shutdown: Capacity is required)
(See note 2 page 3)
MW Level 1 (MWL1) MW OC2 -
MW Level 2 (MWL2) MW OC2 -

DPD II
&
RUR from Synch. Gen to MWL1 MW/Mins OC2
RUR from MWL1 to MWL2 MW/Mins OC2
RUR from MWL2 to RC MW/Mins OC2

Run-Down Rates (RDR): (Note that for DPD only a single value of run-down rate from Registered Capacity to de-
synch is required)

MWL2 MW OC2
RDR from RC to MWL2 MW/Min DPD II
OC2
MWL1 MW OC2
RDR from MWL2 to MWL1 MW/Min OC2
RDR from MWL1 to de-synch MW/Min OC2

Issue 5 Revision 15 DRC 03 February 2016


32 of 105
SCHEDULE 2 - GENERATION PLANNING PARAMETERS
PAGE 3 OF 3

DATA to DATA
DATA DESCRIPTION UNITS RTL CAT. GENSET OR STATION DATA
CUSC CUSC G1 G2 G3 G4 G5 G6 STN
Contrac App.
t Form
REGULATION PARAMETERS
OC2.4.2.1(a)
Regulating Range MW DPD II
Load rejection capability while still MW DPD II
Synchronised and able to supply Load.

GAS TURBINE LOADING PARAMETERS:


OC2.4.2.1(a)
Fast loading MW/Min OC2
Slow loading MW/Min OC2

CCGT MODULE PLANNING MATRIX OC2 (please attach)

POWER PARK MODULE PLANNING OC2 (please attach)


MATRIX

Power Park Module Active Power Output/ OC2 (please attach)


Intermittent Power Source Curve
(eg MW output / Wind speed)

NOTES:
(1) To allow for different groups of Gensets within a Power Station (eg. Gensets with the same
operator) each Genset may be allocated to one of up to four Synchronising Groups. Within
each such Synchronising Group the single synchronising interval will apply but between
Synchronising Groups a zero synchronising interval will be assumed.
(2) The run-up of a Genset from synchronising block load to Registered Capacity is represented
as a three stage characteristic in which the run-up rate changes at two intermediate loads,
MWL1 and MWL2. The values MWL1 & MWL2 can be different for each Genset.

Issue 5 Revision 15 DRC 03 February 2016


33 of 105
SCHEDULE 3 - LARGE POWER STATION OUTAGE PROGRAMMES, OUTPUT
USABLE AND INFLEXIBILITY INFORMATION
PAGE 1 OF 3

(Also outline information on contracts involving External Interconnections)


For a Generating Unit at a Large Power Station the information is to be submitted on a unit basis
and for a CCGT Module or Power Park Module at a Large Power Station the information is to be
submitted on a module basis, unless otherwise stated.

DATA DESCRIPTION UNITS TIME UPDATE DATA DATA to


COVERED TIME CAT. RTL
Power Station name:...........................
Generating Unit (or CCGT Module or Power Park Module at a
Large Power Station) number:...
Registered Capacity:..........................
Large Power Station OUTAGE Large Power Station
PROGRAMME OUTPUT USABLE

PLANNING FOR YEARS 3 - 7 AHEAD (OC2.4.1.2.1(a)(i), (e) & (j))


CUSC CUSC
Contract App.
Form
Monthly average OU MW F. yrs 5 - 7 Week 24 SPD

Provisional outage programme C. yrs 3 - 5 Week 2 OC2


comprising:
duration weeks " " "
preferred start date " " "
earliest start date " " "
latest finish date " " "

Weekly OU MW " " "

(NGET response as detailed in OC2 C. yrs 3 - 5 Week12)


(Users' response to NGET suggested changes or potential C. yrs 3 - 5 Week14)
outages)

Updated provisional outage C. yrs 3 - 5 Week 25 OC2


programme comprising:

duration weeks " " "


preferred start date " " "
earliest start date " " "
latest finish date " " "

Updated weekly OU MW " " "

(NGET response as detailed in OC2 for C. yrs 3 - 5 Week28)


(Users' response to NGET suggested changes or update of C. yrs 3 - 5 Week31)
potential outages)

(NGET further suggested revisions etc. (as detailed )


in OC2 for C. yrs 3 - 5 Week42)

Agreement of final C. yrs 3 - 5 Week 45 OC2


Generation Outage Programme

PLANNING FOR YEARS 1 - 2 AHEAD (OC2.4.1.2.2(a) & OC2.4.1.2.2(i))

Update of previously agreed Final C. yrs 1 - 2 Week 10 OC2


Generation Outage Programme

Weekly OU MW " " "

Issue 5 Revision 15 DRC 03 February 2016


34 of 105
SCHEDULE 3 - LARGE POWER STATION OUTAGE PROGRAMMES, OUTPUT
USABLE AND INFLEXIBILITY INFORMATION
PAGE 2 OF 3

DATA DESCRIPTION UNITS TIME UPDATE DATA DATA to


COVERED TIME CAT RTL
CUSC CUSC
Contract App. Form

(NGET response as detailed in OC2 for C. yrs 1 2 Week 12)


(Users' response to NGET suggested changes C. yrs 1 2 Week 14)
or update of potential outages)

Revised weekly OU C. yrs 1 2 Week 34 OC2

(NGET response as detailed in OC2 for C. yrs 1 2 Week 39)


(Users' response to NGET suggested changes C. yrs 1 2 Week 46)
or update of potential outages)

Agreement of final Generation C. yrs 1 2 Week 48 OC2


Outage Programme

PLANNING FOR YEAR 0

Updated Final Generation C. yr 0 Week 2 1600 OC2


Outage Programme ahead to year end Weds.

OU at weekly peak MW " " "

(NGET response as detailed in OC2 for C. yrs 0 1600 )


( Weeks 2 to 52 Friday )
( ahead )

(NGET response as detailed in OC2 for Weeks 2 - 7 1600 )


( ahead Thurs )

Forecast return to services date days 2 to 14 0900 OC2


(Planned Outage or breakdown) ahead daily

OU (all hours) MW " " OC2

(NGET response as detailed in OC2 for days 2 to 14 1600 )


( ahead daily )

INFLEXIBILITY

Genset inflexibility Min MW Weeks 2 - 8 1600 Tues OC2


(Weekly) ahead

(NGET response on Negative Reserve Active " 1200 )


(Power Margin Friday )

Genset inflexibility Min MW days 2 -14 ahead 0900 daily OC2


(daily)

(NGET response on Negative Reserve Active " 1600 )


(Power Margin daily )

Issue 5 Revision 15 DRC 03 February 2016


35 of 105
SCHEDULE 3 - LARGE POWER STATION OUTAGE PROGRAMMES, OUTPUT
USABLE AND INFLEXIBILITY INFORMATION
PAGE 3 OF 3

DATA DESCRIPTION UNITS TIME UPDATE DATA DATA to


COVERED TIME CAT RTL

OUTPUT PROFILES
CUSC CUSC
Contract App.
Form

In the case of Large Power Stations whose output MW F. yrs 1 - 7 Week 24 SPD
may be expected to vary in a random manner (eg.
wind power) or to some other pattern (eg. Tidal)
sufficient information is required to enable an
understanding of the possible profile

Notes: 1. The week numbers quoted in the Update Time column refer to standard weeks in the
current year.

Issue 5 Revision 15 DRC 03 February 2016


36 of 105
GOVERNOR DROOP AND RESPONSE (PC.A.5.5 CUSC Contract)
The Data in this Schedule 4 is to be supplied by Generators with respect to all Large Power Stations and by DC Converter Station
owners (where agreed), whether directly connected or Embedded

DROOP% RESPONSE CAPABILITY


DATA DATA
NORMAL VALUE MW
DESCRIPTION CAT
Unit 1 Unit 2 Unit 3 Primary Secondary High Frequency

Issue 5 Revision 15
MLP1 Designed Minimum Operating Level
(for a CCGT Module or Power Park
Module, on a modular basis assuming
all units are Synchronised)

MLP2 Minimum Generation (for a CCGT


Module or Power Park Module, on a
modular basis assuming all units are
Synchronised)

MLP3 70% of Registered Capacity

MLP4 80% of Registered Capacity

MLP5 95% of Registered Capacity

DRC
37 of 105
MLP6 Registered Capacity
PAGE 1 OF 1

Notes:
1. The data provided in this Schedule 4 is not intended to constrain any Ancillary Services Agreement.
2. Registered Capacity should be identical to that provided in Schedule 2.
3. The Governor Droop should be provided for each Generating Unit(excluding Power Park Units), Power Park Module or DC Converter. The Response Capability
should be provided for each Genset or DC Converter.
4. Primary, Secondary and High Frequency Response are defined in CC.A.3.2 and are based on a frequency ramp of 0.5Hz over 10 seconds. Primary Response
is the minimum value of response between 10s and 30s after the frequency ramp starts, Secondary Response between 30s and 30 minutes, and High Frequency
Response is the minimum value after 10s on an indefinite basis.
5. For plants which have not yet Synchronised, the data values of MLP1 to MLP6 should be as described above. For plants which have already Synchronised, the
values of MLP1 to MLP6 can take any value between Designed Operating Minimum Level and Registered Capacity. If MLP1 is not provided at the Designed
Minimum Operating Level, the value of the Designed Minimum Operating Level should be separately stated.
6. For the avoidance of doubt Transmission DC Converters and OTSDUW DC Converters must be capable of providing a continuous signal indicating the real time
frequency measured at the Transmission Interface Point to the Offshore Grid Entry Point (as detailed in CC.6.3.7(vii) and CC.6.3.7(viii) to enable Offshore
Generating Units, Offshore Power Park Modules and/or Offshore DC Converters to satisfy the frequency response requirements of CC.6.3.7.
SCHEDULE 4 - LARGE POWER STATION DROOP AND RESPONSE DATA

03 February 2016
SCHEDULE 5 - USERS SYSTEM DATA
PAGE 1 OF 10

The data in this Schedule 5 is required from Users who are connected to the National Electricity
Transmission System via a Connection Point (or who are seeking such a connection). Generators
undertaking OTSDUW should use DRC Schedule 18 although they should still supply data under Schedule
5 in relation to their Users System up to the Offshore Grid Entry Point.

DATA DESCRIPTION UNITS DATA to RTL DATA


CATEGORY
CUSC CUSC
Contract App.
Form
USERS SYSTEM LAYOUT (PC.A.2.2)

A Single Line Diagram showing all or part of the Users System is SPD
required. This diagram shall include:-

(a) all parts of the Users System, whether existing or


proposed, operating at Supergrid Voltage, and in Scotland
and Offshore, also all parts of the User System operating
at 132kV,
(b) all parts of the Users System operating at a voltage of
50kV, and in Scotland and Offshore greater than 30kV, or
higher which can interconnect Connection Points, or split
bus-bars at a single Connection Point,
(c) all parts of the Users System between Embedded
Medium Power Stations or Large Power Stations or
Offshore Transmission Systems connected to the
Users Subtransmission System and the relevant
Connection Point or Interface Point,
(d) all parts of the Users System at a Transmission Site.

The Single Line Diagram may also include additional details of the
Users Subtransmission System, and the transformers connecting
the Users Subtransmission System to a lower voltage. With
NGETs agreement, it may also include details of the Users
System at a voltage below the voltage of the Subtransmission
System.

This Single Line Diagram shall depict the arrangement(s) of all of


the existing and proposed load current carrying Apparatus relating
to both existing and proposed Connection Points, showing
electrical circuitry (ie. overhead lines, underground cables, power
transformers and similar equipment), operating voltages. In addition,
for equipment operating at a Supergrid Voltage, and in Scotland
and Offshore also at 132kV, circuit breakers and phasing
arrangements shall be shown.

Issue 5 Revision 15 DRC 03 February 2016


38 of 105
SCHEDULE 5 - USERS SYSTEM DATA
PAGE 2 OF 10

DATA DESCRIPTION UNITS DATA DATA


EXCH CATEGORY
CUSC CUSC
Contract App.
Form
REACTIVE COMPENSATION (PC.A.2.4)

For independently switched reactive compensation equipment


not owned by a Transmission Licensee connected to the
User's System at 132kV and above, and also in Scotland and
Offshore, connected at 33kV and above, other than power
factor correction equipment associated with a customers Plant
or Apparatus:

Type of equipment (eg. fixed or variable) Text SPD


Capacitive rating; or MVAr SPD
Inductive rating; or MVAr SPD
Operating range MVAr SPD

Details of automatic control logic to enable operating text and/or SPD


characteristics to be determined diagrams

Point of connection to User's System (electrical location and Text SPD


system voltage)

SUBSTATION INFRASTRUCTURE (PC.A.2.2.6(b))

For the infrastructure associated with any Users equipment at


a Substation owned by a Transmission Licensee or operated
or managed by NGET:-

Rated 3-phase rms short-circuit withstand current kA SPD


Rated 1-phase rms short-circuit withstand current kA SPD
Rated Duration of short-circuit withstand s SPD
Rated rms continuous current A SPD

Issue 5 Revision 15 DRC 03 February 2016


39 of 105
SCHEDULE 5 - USERS SYSTEM DATA
PAGE 3 OF 10

DATA DESCRIPTION UNITS DATA DATA


EXCH CATEGORY
CUSC CUSC
Contract App.
Form
LUMPED SUSCEPTANCES (PC.A.2.3)

Equivalent Lumped Susceptance required for all parts of the


Users Subtransmission System which are not included in the
Single Line Diagram.
This should not include:

(a) independently switched reactive compensation


equipment identified above.
(b) any susceptance of the Users System inherent in the
Demand (Reactive Power) data provided in Schedule
1 (Generator Data) or Schedule 11 (Connection Point
data).

Equivalent lumped shunt susceptance at nominal Frequency. % on 100 SPD


MVA

Issue 5 Revision 15 DRC 03 February 2016


40 of 105
USERS SYSTEM DATA

Circuit Parameters (PC.A.2.2.4) ( CUSC Contract & CUSC Application Form)

The data below is all Standard Planning Data. Details are to be given for all circuits shown on the Single Line Diagram

Issue 5 Revision 15
Years Node 1 Node 2 Rated Operating Positive Phase Sequence Zero Phase Sequence (self) Zero Phase Sequence
Valid Voltage Voltage % on 100 MVA % on 100 MVA (mutual)
kV kV % on 100 MVA

R X B R X B R X B

DRC
41 of 105
PAGE 4 OF 10
SCHEDULE 5 - USERS SYSTEM DATA

Notes

1. Data should be supplied for the current, and each of the seven succeeding Financial Years. This should be done by showing for
which years the data is valid in the first column of the Table.

03 February 2016
USERS SYSTEM DATA
Transformer Data (PC.A.2.2.5) ( CUSC Contract & CUSC Application Form)

The data below is all Standard Planning Data, and details should be shown below of all transformers shown on the Single Line Diagram. Details of
Winding Arrangement, Tap Changer and earthing details are only required for transformers connecting the Users higher voltage system with its
Primary Voltage System.

Issue 5 Revision 15
Years Name Trans- Rating Voltage Ratio Positive Phase Positive Phase Zero Winding Tap Changer Earthin
valid of former MVA Sequence Reactance Sequence Resistance Sequence Arr. g
Node % on Rating % on Rating React- Details
or ance (delete
Conn- % on as
HV LV Max. Min. Nom. Max. Min. Nom. range step size type
ection Rating app.) *
Tap Tap Tap Tap Tap Tap +% to -% % (delete
Point
as
ON/ Direct/
app.)
OFF Res/
Rea
ON/
OFF Direct/
Res/
ON/ Rea

DRC
OFF

42 of 105
Direct
PAGE 5 OF 10

ON/ /Res/
OFF Rea

ON/ Direct/
OFF Res/
Rea
SCHEDULE 5 - USERS SYSTEM DATA

ON/
OFF
Direct/
*If Resistance or Reactance please give impedance value Res/
Notes ON/OF Rea
F
1. Data should be supplied for the current, and each of the seven succeeding Financial Years. This should be done by showing fo r which Direct/R
years the data is valid in the first column of the Table es/Rea
2. For a transformer with two secondary windings, the positive and zero phase sequence leakage impedances between the HV and LV1,
HV and LV2, and LV1 and LV2 windings are required. Direct

03 February 2016
/Res/
Rea
USERS SYSTEM DATA
Switchgear Data (PC.A.2.2.6(a)) ( CUSC Contract & CUSC Application Form )
The data below is all Standard Planning Data, and should be provided for all switchgear (ie. circuit breakers, load disconnectors and
disconnectors) operating at a Supergrid Voltage, and also in Scotland and Offshore, operating at 132kV. In addition, data should be
provided for all circuit breakers irrespective of voltage located at a Connection Site which is owned by a Transmission Licensee or
operated or managed by NGET.

Issue 5 Revision 15
Years Connect-ion Switch Rated Operating Rated short-circuit Rated short-circuit peak Rated rms DC time
Valid Point No. Voltage kV Voltage breaking current making current continuous constant at
rms kV rms current testing of
(A) asymmetri
cal
3 Phase 1 Phase 3 Phase 1 Phase breaking
kA rms kA rms kA peak kA peak ability(s)

DRC
43 of 105
PAGE 6 OF 10
SCHEDULE 5 - USERS SYSTEM DATA

Notes

1. Rated Voltage should be as defined by IEC 694.

2. Data should be supplied for the current, and each of the seven succeeding Financial Years. This should be done by showing fo r which years
the data is valid in the first column of the Table

03 February 2016
SCHEDULE 5 - USERS SYSTEM DATA
PAGE 7 OF 10

DATA DESCRIPTION UNITS DATA to RTL DATA


CATEGORY
CUSC CUSC
PROTECTION SYSTEMS (PC.A.6.3) Contract App. Form

The following information relates only to Protection equipment


which can trip or inter-trip or close any Connection Point
circuit breaker or any Transmission circuit breaker. The
information need only be supplied once, in accordance with
the timing requirements set out in PC.A.1.4 (b) and need not
be supplied on a routine annual basis thereafter, although
NGET should be notified if any of the information changes.

(a) A full description, including estimated settings, for all DPD II


relays and Protection systems installed or to be installed
on the User's System;

(b) A full description of any auto-reclose facilities installed DPD II


or to be installed on the User's System, including type
and time delays;

(c) A full description, including estimated settings, for all DPD II


relays and Protection systems installed or to be
installed on the Power Park Module or Generating
Unit's generator transformer, unit transformer, station
transformer and their associated connections;

(d) For Generating Units (other than Power Park Units) DPD II
having a circuit breaker at the generator terminal voltage
clearance times for electrical faults within the
Generating Unit zone must be declared.

(e) Fault Clearance Times:


Most probable fault clearance time for electrical faults mSec DPD II
on any part of the Users System directly connected to
the National Electricity Transmission System.

DATA DESCRIPTION UNITS DATA to RTL DATA


CATEGORY
POWER PARK MODULE/UNIT PROTECTION SYSTEMS CUSC CUSC
Contract App. Form
Details of settings for the Power Park Module/Unit protection relays
(to include): (PC.A.5.4.2(f))
(a) Under frequency, DPD II
(b) Over Frequency, DPD II
(c) Under Voltage, Over Voltage, DPD II
(d) Rotor Over current DPD II
(e) Stator Over current,. DPD II
(f) High Wind Speed Shut Down Level DPD II
(g) Rotor Underspeed DPD II
(h) Rotor Overspeed DPD II

Issue 5 Revision 15 DRC 03 February 2016


44 of 105
SCHEDULE 5 - USERS SYSTEM DATA
PAGE 8 OF 10

Information for Transient Overvoltage Assessment (DPD I) (PC.A.6.2 CUSC Contract)


The information listed below may be requested by NGET from each User with respect to any Connection
Site between that User and the National Electricity Transmission System. The impact of any third party
Embedded within the Users System should be reflected.
(a) Busbar layout plan(s), including dimensions and geometry showing positioning of any current
and voltage transformers, through bushings, support insulators, disconnectors, circuit breakers,
surge arresters, etc. Electrical parameters of any associated current and voltage transformers,
stray capacitances of wall bushings and support insulators, and grading capacitances of circuit
breakers;
(b) Electrical parameters and physical construction details of lines and cables connected at that
busbar. Electrical parameters of all plant e.g., transformers (including neutral earthing
impedance or zig-zag transformers if any), series reactors and shunt compensation equipment
connected at that busbar (or to the tertiary of a transformer) or by lines or cables to that busbar;
(c) Basic insulation levels (BIL) of all Apparatus connected directly, by lines or by cables to the
busbar;
(d) Characteristics of overvoltage Protection devices at the busbar and at the termination points of
all lines, and all cables connected to the busbar;
(e) Fault levels at the lower voltage terminals of each transformer connected directly or indirectly to
the National Electricity Transmission System without intermediate transformation;
(f) The following data is required on all transformers operating at Supergrid Voltage throughout
Great Britain and, in Scotland and Offshore, also at 132kV: three or five limb cores or single
phase units to be specified, and operating peak flux density at nominal voltage.
(g) An indication of which items of equipment may be out of service simultaneously during Planned
Outage conditions.
Harmonic Studies (DPD I) (PC.A.6.4 CUSC Contract)
The information given below, both current and forecast, where not already supplied in this Schedule 5 may
be requested by NGET from each User if it is necessary for NGET to evaluate the production/magnification
of harmonic distortion on the National Electricity Transmission System and Users systems. The impact
of any third party Embedded within the Users System should be reflected:
(a) Overhead lines and underground cable circuits of the User's Subtransmission System must be
differentiated and the following data provided separately for each type:
Positive phase sequence resistance
Positive phase sequence reactance
Positive phase sequence susceptance
(b) for all transformers connecting the User's Subtransmission System to a lower voltage:
Rated MVA
Voltage Ratio
Positive phase sequence resistance
Positive phase sequence reactance

Issue 5 Revision 15 DRC 03 February 2016


45 of 105
SCHEDULE 5 - USERS SYSTEM DATA
PAGE 9 OF 10

(c) at the lower voltage points of those connecting transformers:


Equivalent positive phase sequence susceptance
Connection voltage and MVAr rating of any capacitor bank and component design
parameters if configured as a filter
Equivalent positive phase sequence interconnection impedance with other lower voltage
points
The minimum and maximum Demand (both MW and MVAr) that could occur
Harmonic current injection sources in Amps at the Connection voltage points
Details of traction loads, eg connection phase pairs, continuous variation with time, etc.

(d) an indication of which items of equipment may be out of service simultaneously during
Planned Outage conditions

Voltage Assessment Studies (DPD I) (PC.A.6.5 CUSC Contract)


The information listed below, where not already supplied in this Schedule 5, may be requested by NGET
from each User with respect to any Connection Site if it is necessary for NGET to undertake detailed
voltage assessment studies (eg to examine potential voltage instability, voltage control co-ordination or to
calculate voltage step changes). The impact of any third party Embedded within the Users System should
be reflected:
(a) For all circuits of the Users Subtransmission System:
Positive Phase Sequence Reactance
Positive Phase Sequence Resistance
Positive Phase Sequence Susceptance
MVAr rating of any reactive compensation equipment

(b) for all transformers connecting the User's Subtransmission System to a lower voltage:
Rated MVA
Voltage Ratio
Positive phase sequence resistance
Positive Phase sequence reactance
Tap-changer range
Number of tap steps
Tap-changer type: on-load or off-circuit
AVC/tap-changer time delay to first tap movement
AVC/tap-changer inter-tap time delay

Issue 5 Revision 15 DRC 03 February 2016


46 of 105
SCHEDULE 5 - USERS SYSTEM DATA
PAGE 10 OF 10

(c) at the lower voltage points of those connecting transformers:-


Equivalent positive phase sequence susceptance
MVAr rating of any reactive compensation equipment
Equivalent positive phase sequence interconnection impedance with other lower voltage
points
The maximum Demand (both MW and MVAr) that could occur
Estimate of voltage insensitive (constant power) load content in % of total load at both
winter peak and 75% off-peak load conditions

Short Circuit Analyses:(DPD I) (PC.A.6.6 CUSC Contract)


The information listed below, both current and forecast, and where not already supplied under this
Schedule 5, may be requested by NGET from each User with respect to any Connection Site
where prospective short-circuit currents on equipment owned by a Transmission Licensee or
operated or managed by NGET are close to the equipment rating. The impact of any third party
Embedded within the Users System should be reflected:-
(a) For all circuits of the Users Subtransmission System:
Positive phase sequence resistance
Positive phase sequence reactance
Positive phase sequence susceptance
Zero phase sequence resistance (both self and mutuals)
Zero phase sequence reactance (both self and mutuals)
Zero phase sequence susceptance (both self and mutuals)
(b) for all transformers connecting the User's Subtransmission System to a lower voltage:
Rated MVA
Voltage Ratio
Positive phase sequence resistance (at max, min and nominal tap)
Positive Phase sequence reactance (at max, min and nominal tap)
Zero phase sequence reactance (at nominal tap)
Tap changer range
Earthing method: direct, resistance or reactance
Impedance if not directly earthed
(c) at the lower voltage points of those connecting transformers:-
The maximum Demand (in MW and MVAr) that could occur
Short-circuit infeed data in accordance with PC.A.2.5.6(a) unless the Users lower voltage
network runs in parallel with the Subtransmission System, when to prevent double
counting in each node infeed data, a equivalent comprising the data items of
PC.A.2.5.6(a) for each node together with the positive phase sequence interconnection
impedance between the nodes shall be submitted.

Issue 5 Revision 15 DRC 03 February 2016


47 of 105
SCHEDULE 6 - USERS OUTAGE INFORMATION
PAGE 1 OF 2
DATA DESCRIPTION UNITS DATA to RTL TIMESCALE UPDATE DATA
COVERED TIME CAT.
CUSC CUSC
Contract App.
Form
Details are required from Network Operators of proposed Years 2-5 Week 8 OC2
outages in their User Systems and from Generators with (Network
respect to their outages, which may affect the performance of Operator etc)
the Total System (eg. at a Connection Point or constraining Week 13 OC2
Embedded Large Power Stations or constraints to the (Generators)
Maximum Import Capacity or Maximum Export Capacity
at an Interface Point) (OC2.4.1.3.2(a) & (b))

(NGET advises Network Operators of National Electricity Years 2-5 Week 28)
Transmission System outages affecting their Systems)

Network Operator informs NGET if unhappy with proposed " Week 30 OC2
outages)

(NGET draws up revised National Electricity " Week 34)


Transmission System
( outage plan advises Users of operational effects)

Generators and Non-Embedded Customers provide Year 1 Week 13 OC2


Details of Apparatus owned by them (other than Gensets) at
each Grid Supply Point (OC2.4.1.3.3)

(NGET advises Network Operators of outages affecting their Year 1 Week 28)
Systems) (OC2.4.1.3.3)

Network Operator details of relevant outages affecting the Year 1 Week 32 OC2
Total System (OC2.4.1.3.3)

Details of:- MVA / MW Year 1 Week 32 OC2


Maximum Import Capacity for each Interface Point MVA / MW
Maximum Export Capacity for each Interface Point V (unless
Changes to previously declared values of the Interface power factor
Point Target Voltage/Power Factor (OC2.4.1.3.3(c )). control

(NGET informs Users of aspects that may affect their Year 1 Week 34)
Systems) (OC2.4.1.3.3)

Users inform NGET if unhappy with aspects as notified Year 1 Week 36 OC2
(OC2.4.1.3.3)

(NGET issues final National Electricity Transmission Year 1 Week 49 OC2


System
( outage plan with advice of operational) (OC2.4.1.3.3)
( effects on Users System)

Generator, Network Operator and Non-Embedded Week 8 ahead As occurring OC2


Customers to inform NGET of changes to outages to year end
previously requested

Details of load transfer capability of 12MW or Within Yr 0 As NGET OC2


more between Grid Supply Points in England and Wales request
and 10MW or more between Grid Supply Points in
Scotland.
Details of:- MVA / MW Within Yr 0 As occurring OC2
Maximum Import Capacity for each Interface Point MVA / MW
Maximum Export Capacity for each Interface Point V (unless
Changes to previously declared values of the Interface power factor
Point Target Voltage/Power Factor control

Issue 5 Revision 15 DRC 03 February 2016


48 of 105
Note: Users should refer to OC2 for full details of the procedure summarised above and for the
information which NGET will provide on the Programming Phase.

SCHEDULE 6 - USERS OUTAGE INFORMATION


PAGE 2 OF 2

The data below is to be provided to NGET as required for compliance with the European Commission
Regulation No 543/2013 (OC2.4.2.3). Data provided under Article Numbers 7.1(a), 7.1(b), 15.1(a), 15.1(b),
and 15.1(c) and 15.1(d) is to be provided using MODIS.

ECR USERS
FREQUENCY OF
ARTICLE DATA DESCRIPTION PROVIDING
SUBMISSION
No. DATA

Planned unavailability of the Apparatus belonging to a Non-


Embedded Customer where OC2.4.7 (a) applies To be received by NGET
as soon as reasonably
- Energy Identification Code (EIC)* possible but in any case
- Unavailable demand capacity during the event (MW) to facilitate publication of
- Estimated start date and time (dd.mm.yy hh:mm) Non-Embedded data no later than 1 hour
7.1(a)
- Estimated end date and time (dd.mm.yy hh:mm) Customer after a decision has
- Reason for unavailability from the list below: been made by the Non-
. Maintenance Embedded Customer
. Failure regarding the planned
. Shutdown unavailability
. Other

Changes in actual availability of the Apparatus belonging to a


Non-Embedded Customer where OC2.4.7 (b) applies
To be received by NGET
- Energy Identification Code (EIC)*
as soon as reasonably
- Unavailable demand capacity during the event (MW)
possible but in any case
- Start date and time (dd.mm.yy hh:mm) Non-Embedded
7.1(b) to facilitate publication of
- Estimated end date and time (dd.mm.yy hh:mm) Customer
data no later than 1 hour
- Reason for unavailability from the list below :
after the change in actual
. Maintenance
availability
. Failure
. Shutdown
. Other

Year Ahead Forecast Margin information as provided in


accordance with OC2.4.1.2.2 In accordance with
8.1 Generator
OC2.4.1.2.2
- Output Usable

Registered Capacity for Generating Units with greater than 1


MW Registered Capacity provided in accordance with
PC.4.3.1 and PC.A.3.4.3 or PC.A.3.1.4
14.1(a) Generator Week 24
- Registered Capacity (MW)
- Production type (from that listed under PC.A.3.4.3)

Power Station Registered Capacity for units with equal or


greater than 100 MW Registered Capacity provided in
accordance with PC.4.3.1 and PC.A.3.4.3

14.1(b) - Power Station name Generator Week 24


- Location of Generating Unit
- Production type (from that listed under PC.A.3.4.3)
- Voltage connection levels
- Registered Capacity (MW)

Issue 5 Revision 15 DRC 03 February 2016


49 of 105
Estimated output of Active Power of a BM Unit or Generating
Unit for each per Settlement Period of the next Operational
In accordance with
14.1(c) Day provided in accordance with BC1.4.2 Generator
BC1.4.2
- Physical Notification

Planned unavailability of a Generating Unit where OC2.4.7(c)


applies
To be received by NGET
- Power Station name
as soon as reasonably
- Generating Unit name
possible possible but in
- Location of Generating Unit
any case to facilitate
- Generating Unit Registered Capacity (MW)
publication of data no
15.1(a) - Production type (from that listed under PC.A.3.4.3) Generator
later than 1 hour after a
- Output Usable (MW) during the event decision has been made
- Start date and time (dd.mm.yy hh:mm) by the Generator
- Estimated end date and time (dd.mm.yy hh:mm) regarding the planned
- Reason for unavailability from the list below: unavailability
. Maintenance
. Shutdown
. Other

Changes in availability of a Generating Unit where OC2.4.7


(d) applies

- Power Station name


- Generating Unit name To be received by NGET
- Location of Generating Unit as soon as reasonably
- Generating Unit Registered Capacity (MW) possible but in any case
15.1(b) - Production type(from that listed under PC.A.3.4.3) Generator to facilitate publication of
- Maximum Export Limit (MW) during the event data no later than 1 hour
- Start date and time (dd.mm.yy hh:mm) after the change in actual
- Estimated end date and time (dd.mm.yy hh:mm) availability
- Reason for unavailability from the list below:
. Maintenance
. Shutdown
. Other

Planned unavailability of a Power Station where OC2.4.7(e)


applies

- Power Station name To be received by NGET


- Location of Power Station as soon as reasonably
- Power Station Registered Capacity (MW) possible but in any case
- Production type (from that listed under PC.A.3.4.3) to facilitate publication of
15.1(c) - Power Station aggregated Output Usable (MW) during the Generator data no later than 1 hour
event after a decision has been
- Start date and time (dd.mm.yy hh:mm) made by the Generator
- Estimated end date and time (dd.mm.yy hh:mm) regarding the planned
- Reason for unavailability from the list below: unavailability
. Maintenance
. Shutdown
. Other

Changes in actual availability of a Power Station where


OC2.4.7 (f) applies

- Power Station name


To be received by NGET
- Location of Power Station
as soon as reasonably
- Power Station Registered Capacity (MW)
possible possible but in
- Production type (from that listed under PC.A.3.4.3)
any case to facilitate
15.1(d) - Power Station aggregated Maximum Export Limit (MW) Generator
publication of data no
during the event later than 1 hour after the
- Start date and time (dd.mm.yy hh:mm) change in actual
- Estimated end date and time (dd.mm.yy hh:mm) availability
- Reason for unavailability from the list below:
. Maintenance
. Shutdown
. Other

* Energy Identification Coding (EIC) is a coding scheme that is approved by ENTSO-E for standardised electronic data interchanges and
Issue 5 Revision 15 DRC 03 February 2016
50 of 105
is utilised for reporting to the Central European Transparency Platform. NGET will act as the Local Issuing Office for IEC in respect of
GB.

Issue 5 Revision 15 DRC 03 February 2016


51 of 105
SCHEDULE 7 - LOAD CHARACTERISTICS AT GRID SUPPLY POINTS
PAGE 1 OF 1

All data in this schedule 7 is categorised as Standard Planning Data (SPD) and is required for existing
and agreed future connections. This data is only required to be updated when requested by NGET.

DATA FOR FUTURE YEARS


DATA DESCRIPTION UNITS DATA to Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7
RTL
CUSC CUSC
Contrac App.
t Form
FOR ALL TYPES OF DEMAND FOR EACH GRID
SUPPLY POINT

The following information is required infrequently


and should only be supplied, wherever possible,
when requested by NGET (PC.A.4.7)

Details of individual loads which have (Please Attach)


Characteristics significantly different from the
typical range of domestic or commercial and
industrial load supplied: (PC.A.4.7(a))

Sensitivity of demand to fluctuations in voltage


And frequency on National Electricity
Transmission System at time of peak
Connection Point Demand (Active Power)
(PC.A.4.7(b))

Voltage Sensitivity (PC.A.4.7(b)) MW/kV


MVAr/kV

Frequency Sensitivity (PC.A.4.7(b)) MW/Hz


MVAr/Hz

Reactive Power sensitivity should relate to the


Power Factor information given in Schedule 11 (or
for Generators, Schedule 1) and note 6 on
Schedule 11 relating to Reactive Power therefore
applies: (PC.A.4.7(b))

Phase unbalance imposed on the National


Electricity Transmission System (PC.A.4.7(d))
- maximum %
- average %

Maximum Harmonic Content imposed on National %


Electricity Transmission System (PC.A.4.7(e))

Details of any loads which may cause Demand


Fluctuations greater than those permitted under
Engineering Recommendation P28, Stage 1 at
the Point of Common Coupling including
Flicker Severity (Short Term) and Flicker
Severity (Long Term) (PC.A.4.7(f))

Issue 5 Revision 15 DRC 03 February 2016


52 of 105
SCHEDULE 8 - DATA SUPPLIED BY BM PARTICIPANTS
PAGE 1 OF 1

CODE DESCRIPTION

BC1 Physical Notifications

BC1 Quiescent Physical Notifications

BC1 & BC2 Export and Import Limits

BC1 Bid-Offer Data

BC1 Dynamic Parameters (Day Ahead)

BC2 Dynamic Parameters (For use in Balancing Mechanism)

BC1 & BC2 Other Relevant Data

BC1 Joint BM Unit Data

- No information collated under this Schedule will be transferred to the Relevant Transmission Licensees

Issue 5 Revision 15 DRC 03 February 2016


53 of 105
SCHEDULE 9 - DATA SUPPLIED BY NGET TO USERS
PAGE 1 OF 1

(Example of data to be supplied)

CODE DESCRIPTION

CC Operation Diagram

CC Site Responsibility Schedules

PC Day of the peak National Electricity Transmission System Demand

Day of the minimum National Electricity Transmission System Demand

OC2 Surpluses and OU requirements for each Generator over varying timescales

Equivalent networks to Users for Outage Planning

Negative Reserve Active Power Margins (when necessary)

Operating Reserve information

BC1 Demand Estimates, Indicated Margin and Indicated Imbalance, indicative


Synchronising and Desynchronising times of Embedded Power Stations to
Network Operators, special actions.

BC2 Bid-Offer Acceptances, Ancillary Services instructions to relevant Users,


Emergency Instructions

BC3 Location, amount, and Low Frequency Relay settings of any Low Frequency
Relay initiated Demand reduction for Demand which is Embedded.

- No information collated under this Schedule will be transferred to the Relevant Transmission
Licensees

DATA TO BE SUPPLIED BY NGET TO USERS

PURSUANT TO THE TRANSMISSION LICENCE

1. The Transmission Licence requires NGET to publish annually the Seven Year Statement
which is designed to provide Users and potential Users with information to enable them to
identify opportunities for continued and further use of the National Electricity Transmission
System.

When a User is considering a development at a specific site, certain additional information


may be required in relation to that site which is of such a level of detail that it is inappropriate
to include it in the Seven Year Statement. In these circumstances the User may contact
NGET who will be pleased to arrange a discussion and the provision of such additional
information relevant to the site under consideration as the User may reasonably require.

2. The Transmission Licence also requires NGET to offer terms for an agreement for
connection to and use of the National Electricity Transmission System and further
information will be given by NGET to the potential User in the course of the discussions of the
Issue 5 Revision 15 DRC 03 February 2016
54 of 105
terms of such an agreement.

Issue 5 Revision 15 DRC 03 February 2016


55 of 105
SCHEDULE 10 - DEMAND PROFILES AND ACTIVE ENERGY DATA
PAGE 1 OF 2

The following information is required from each Network Operator and from each Non-Embedded Customer. The data
should be provided in calendar week 24 each year (although Network Operators may delay the submission until
calendar week 28).
DATA DESCRIPTION F. Yr. F. Yr. F. Yr. F. Yr. F. Yr. F. Yr. F. Yr. F. Yr. UPDATE DATA CAT
0 1 2 3 4 5 6 7 TIME

Demand Profiles (PC.A.4.2) ( CUSC Contract & CUSC Application Form)


Total User's Day of User's annual Maximum demand at Annual ACS Conditions (MW)
system profile (please Day of annual peak of National Electricity Transmission System Demand at Annual ACS
delete as applicable) Conditions (MW)
Day of annual minimum National Electricity Transmission System Demand at average conditions
(MW)

0000 : 0030 Wk.24 SPD


0030 : 0100 :
0100 : 0130 :
0130 : 0200 : :
0200 : 0230 : :
0230 : 0300 : :
0300 : 0330 : :
0330 : 0400 : :
0400 : 0430 : :
0430 : 0500 : :
0500 : 0530 : :
0530 : 0600 : :
0600 : 0630 : :
0630 : 0700 : :
0700 : 0730 : :
0730 : 0800 : :
0800 : 0830 : :
0830 : 0900 : :
0900 : 0930 : :
0930 : 1000 : :
1000 : 1030 : :
1030 : 1100 : :
1100 : 1130 : :
1130 : 1200 : :
1200 : 1230 : :
1230 : 1300 : :
1300 : 1330 : :
1330 : 1400 : :
1400 : 1430 : :
1430 : 1500 : :
1500 : 1530 : :
1530 : 1600 : :
1600 : 1630 : :
1630 : 1700 : :
1700 : 1730 : :
1730 : 1800 : :
1800 : 1830 : :
1830 : 1900 : :
1900 : 1930 : :
1930 : 2000 : :
2000 : 2030 : :
2030 : 2100 : :
2100 : 2130 : :
2130 : 2200 : :
2200 : 2230 : :
2230 : 2300 : :

Issue 5 Revision 15 DRC 03 February 2016


56 of 105
2300 : 2330 : :
2330 : 0000 : :

Issue 5 Revision 15 DRC 03 February 2016


57 of 105
SCHEDULE 10 - DEMAND PROFILES AND ACTIVE ENERGY DATA
PAGE 2 OF 2

DATA DESCRIPTION Out-turn F.Yr. Update Data Cat DATA to RTL


Actual Weather 0 Time
Corrected.
(PC.A.4.3) CUSC CUSC
Contract App.
Form
Active Energy Data Week 24 SPD

Total annual Active Energy


requirements under average
conditions of each Network
Operator and each Non-
Embedded Customer in the
following categories of Customer
Tariff:-

LV1
LV2
LV3
EHV
HV
Traction
Lighting
User System Losses

Active Energy from Embedded


Small Power Stations and
Embedded Medium Power
Stations

NOTES:

1. 'F. yr.' means 'Financial Year'

2. Demand and Active Energy Data (General)

Demand and Active Energy data should relate to the point of connection to the National
Electricity Transmission System and should be net of the output (as reasonably considered
appropriate by the User) of all Embedded Small Power Stations, Medium Power Stations and
Customer Generating Plant. Auxiliary demand of Embedded Power Stations should be included
in the demand data submitted by the User at the Connection Point. Users should refer to the PC
for a full definition of the Demand to be included.

3. Demand profiles and Active Energy data should be for the total System of the Network Operator,
including all Connection Points, and for each Non-Embedded Customer. Demand Profiles
should give the numerical maximum demand that in the User's opinion could reasonably be
imposed on the National Electricity Transmission System.

4. In addition the demand profile is to be supplied for such days as NGET may specify, but such a
request is not to be made more than once per calendar year.

Issue 5 Revision 15 DRC 03 February 2016


58 of 105
SCHEDULE 11 - CONNECTION POINT DATA
PAGE 1 OF 3

The following information is required from each Network Operator and from each Non-Embedded
Customer. The data should be provided in calendar week 24 each year (although Network Operators may
delay the submission until calendar week 28).
Connection Point:

Connection Point Demand at the time of - a) maximum Demand


(select each one in turn) b) peak National Electricity Transmission System Demand (specified by
(Provide data for each Access Period associated NGET)
with the Connection Point) c) minimum National Electricity Transmission System Demand
(specified by NGET)
d) maximum Demand during Access Period
e) specified by either NGET or a User
Name of Transmission Interface Circuit out of
PC.A.4.1.4.2
service during Access Period (if reqd).

DATA DESCRIPTION Outturn Outturn F.Yr F.Yr F.Yr. F.Yr. F.Yr. F.Yr F.Yr F.Yr DATA CAT
(CUSC Contract & CUSC Application Form ) Weather
1 2 3 4 5 6 7 8
Corrected
Date of a), b), c), d) or e) as denoted above. PC.A.4.3.3
Time of a), b), c), d) or e) as denoted above. PC.A.4.3.3
Connection Point Demand (MW) PC.A.4.3.1
Connection Point Demand (MVAr) PC.A.4.3.1
Deduction made at Connection Point for Small
Power Stations, Medium Power Stations and PC.A.4.3.2(a)
Customer Generating Plant (MW)
Reference to valid Single Line Diagram PC.A.4.3.5
Reference to node and branch data. PC.A.2.2

Note: The following data block can be repeated for each post fault network revision that may impact on the Transmission System.

Reference to post-fault revision of Single Line


PC.A.4.5
Diagram
Reference to post-fault revision of the node and
branch data associated with the Single Line PC.A.4.5
Diagram
Reference to the description of the actions and
timescales involved in effecting the post-fault
PC.A.4.5
actions (e.g. auto-switching, manual,
teleswitching, overload protection operation etc)

Access Group:
Note: The following data block to be repeated for each Connection Point with the Access Group.
Name of associated Connection Point within the
PC.A.4.3.1
same Access Group:
Demand at associated Connection Point (MW) PC.A.4.3.1
Demand at associated Connection Point
PC.A.4.3.1
(MVAr)

Deduction made at associated Connection


Point for Small Power Stations, Medium Power PC.A.4.3.2(a)
Stations and Customer Generating Plant (MW)

Issue 5 Revision 15 DRC 03 February 2016


59 of 105
SCHEDULE 11 - CONNECTION POINT DATA
PAGE 2 OF 3

Embedded Generation Data


Connection
Point:
DATA Outtur Outturn F.Yr F.Yr F.Yr. F.Yr. F.Yr. F.Yr F.Yr F.Yr DATA CAT
DESCRIPTION n
Weather
Correcte 1 2 3 4 5 6 7 8
d
Small Power For each Connection Point where there are Embedded Small Power Stations,
Station, Medium Medium Power Stations or Customer Generating Stations the following
Power Station information is required:
and Customer
Generation
Summary
No. of Small PC.A.3.1.4
Power Stations, (a)
Medium Power
Stations or
Customer Power
Stations
Number of PC.A.3.1.4
Generating Units (a)
within these
stations
Summated PC.A.3.1.4
Capacity of all (a)
these Generating
Units
Where the Network Operators System places a constraint on the capacity of an Embedded Large
Power Station
PC.A.3.2.2
Station Name
(c)
PC.A.3.2.2
Generating Unit
(c)
System PC.A.3.2.2
Constrained (c)(i)
Capacity
Reactive PC.A.3.2.2
Despatch (c)(ii)
Network
Restriction

Where the Network Operators System places a constraint on the capacity of an Offshore
Transmission System at an Interface Point
Offshore PC.A.3.2.2
Transmission (c)
System Name
Interface Point PC.A.3.2.2
Name (c)
Maximum Export PC.A.3.2.2
Capacity (c)
Maximum Import PC.A.3.2.2
Capacity (c)

Issue 5 Revision 15 DRC 03 February 2016


60 of 105
For each Embedded Small Power Station of 1MW and above, the following information is required, effective 2015 in line with the Week 24 data submissions.

DATA An Connection Generator Technology CHP Registered Lowest voltage Where it Control Control mode Loss of Loss of
DESCRIPTION Embedded Date unit Type (Y/N) capacity in node on the generates mode voltage target mains mains
Small (Financial Reference / Production MW (as most up-to-date electricity from and reactive protection protection
Power Year for type defined in the Single Line wind or PV, range or type settings
Station generator Distribution Diagram to the target pf (as

Issue 5 Revision 15
reference connecting Code) which it geographical appropriate)
unique to after week connects or location of the
each 24 2015) where it will primary or
Network export most of higher voltage
Operator its power substation to
which it
connects
DATA CAT PC.A.3.1.4 PC.A.3.1.4 PC.A.3.1.4 PC.A. PC.A.3.1.4 (a) PC.A.3.1.4 (a) PC.A.3.1.4 (a) PC.A.3.1.4 PC.A.3.1.4 PC.A.3.1.4 PC.A.3.1.4
(a) (a) (a) 3.1.4 (a) (a) (a) (a)
(a)

DRC
61 of 105
03 February 2016
SCHEDULE 11 - CONNECTION POINT DATA
PAGE 3 OF 3

NOTES:

1. 'F.Yr.' means 'Financial Year'. F.Yr. 1 refers to the current financial year.

2. All Demand data should be net of the output (as reasonably considered appropriate by the User) of all Embedded
Small Power Stations, Medium Power Stations and Customer Generating Plant. Generation and / or Auxiliary
demand of Embedded Large Power Stations should not be included in the demand data submitted by the User.
Users should refer to the PC for a full definition of the Demand to be included.

3. Peak Demand should relate to each Connection Point individually and should give the maximum demand that in
the User's opinion could reasonably be imposed on the National Electricity Transmission System. Users may
submit the Demand data at each node on the Single Line Diagram instead of at a Connection Point as long as
the User reasonably believes such data relates to the peak (or minimum) at the Connection Point.

In deriving Demand any deduction made by the User (as detailed in note 2 above) to allow for Embedded Small
Power Stations, Medium Power Stations and Customer Generating Plant is to be specifically stated as indicated
on the Schedule.

4. NGET may at its discretion require details of any Embedded Small Power Stations or Embedded Medium Power
Stations whose output can be expected to vary in a random manner (eg. wind power) or according to some other
pattern (eg. tidal power)

5. Where more than 95% of the total Demand at a Connection Point is taken by synchronous motors, values of the
Power Factor at maximum and minimum continuous excitation may be given instead. Power Factor data should
allow for series reactive losses on the User's System but exclude reactive compensation network susceptance
specified separately in Schedule 5.

6. Where a Reactive Despatch Network Restriction is in place which requires the generator to maintain a target
voltage set point this should be stated as an alternative to the size of the Reactive Despatch Network Restriction.

Issue 5 Revision 15 DRC 03 February 2016


62 of 105
SCHEDULE 12 - DEMAND CONTROL
PAGE 1 OF 2

The following information is required from each Network Operator and where indicated with
an asterisk from Externally Interconnected System Operators and/or Interconnector Users
and a Pumped Storage Generator. Where indicated with a double asterisk, the information
is only required from Suppliers.

DATA DESCRIPTION UNITS UPDATE TIME

Demand Control

Demand met or to be relieved by


Demand Control (averaging at the
Demand Control Notification Level
or more over a half hour) at each
Connection Point.

Demand Control at time of National


Electricity Transmission System
weekly peak demand
Amount MW )F.yrs 0 to 5 Week 24 OC1
Duration Min )

For each half hour MW Wks 2-8 ahead 1000 Mon OC1

For each half hour MW Days 2-12 ahead 1200 Wed OC1

For each half hour MW Previous calendar 0600 daily OC1


day

**Customer Demand Management


(at the Customer Demand
Management Notification Level or
more at the Connection Point)

For each half hour MW Any time in


Control Phase OC1

For each half hour MW Remainder of When


period changes OC1
occur to
previous plan

For each half hour MW Previous calendar 0600 daily OC1


day
**In Scotland, Load Management MW For the next day 11:00 OC1
Blocks
For each block of 5MW or more, for
each half hour

Issue 5 Revision 15 DRC 03 February 2016


63 of 105
SCHEDULE 12 - DEMAND CONTROL
PAGE 1 OF 2

DATA DESCRIPTION UNITS TIME COVERED UPDATE DATA


TIME CAT.
*Demand Control or Pump
Tripping Offered as Reserve

Magnitude of Demand or pumping MW Year ahead from Week 24 DPD I


load which is tripped week 24

System Frequency at which Hz " " "


tripping is initiated

Time duration of System Frequency S " " "


below trip setting for tripping to be
initiated

Time delay from trip initiation to S " " "


Tripping

Emergency Manual Load


Disconnection

Method of achieving load Text Year ahead from Annual in OC6


disconnection week 24 week 24

Annual ACS Peak Demand MW " " "


(Active Power) at Connection
Point (requested under Schedule
11 - repeated here for reference)

Cumulative percentage of
Connection Point Demand
(Active Power) which can be
disconnected by the following times
from an instruction from NGET

5 mins % " " "


10 mins % " " "
15 mins % " " "
20 mins % " " "
25 mins % " " "
30 mins % " " "

Notes:
1. Network Operators may delay the submission until calendar week 28.
2. No information collated under this Schedule will be transferred to the Relevant
Transmission Licensees (or Generators undertaking OTSDUW).

Issue 5 Revision 15 DRC 03 February 2016


64 of 105
Issue 5 Revision 15 DRC 03 February 2016
65 of 105
SCHEDULE 12A - AUTOMATIC LOW FREQUENCY DEMAND DISCONNECTION
PAGE 1 OF 1

Time Covered: Year ahead from week 24 Data Category: OC6


Update Time: Annual in week 24

GSP Low Frequency Demand Disconnection Blocks MW Residual


Demand 1 2 3 4 5 6 7 8 9 demand
48.8H 48.75H 48.7H 48.6H 48.5H 48.4H 48.2H 48.0H 47.8H
Grid Supply Point MW z z z z z z z z z MW
GSP1
GSP2
GSP3

Total demand disconnected


MW
per block %
Total demand disconnection MW ( % of aggregate demand of MW)

Note: All demand refers to that at the time of forecast National Electricity Transmission System
peak demand.
Network Operators may delay the submission until calendar week 28
No information collated under this schedule will be transferred to the Relevant
Transmission Licensees (or Generators undertaking OTSDUW).

Issue 5 Revision 15 DRC 03 February 2016


66 of 105
SCHEDULE 13 - FAULT INFEED DATA
PAGE 1 OF 2

The data in this Schedule 13 is all Standard Planning Data, and is required from all Users other than
Generators who are connected to the National Electricity Transmission System via a Connection Point
(or who are seeking such a connection). A data submission is to be made each year in Week 24 (although
Network Operators may delay the submission until Week 28). A separate submission is required for each
node included in the Single Line Diagram provided in Schedule 5.

DATA DESCRIPTION UNITS F.Yr F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to
0 1 2 3 4 5 6 7 RTL
SHORT CIRCUIT INFEED TO THE CUSC CUSC
Contrac App.
NATIONAL ELECTRICITY t Form
TRANSMISSION SYSTEM FROM
USERS SYSTEM AT A CONNECTION
POINT
(PC.A.2.5)

Name of node or Connection
Point

Symmetrical three phase


short-circuit current infeed

- at instant of fault kA

- after subtransient fault


current contribution has
substantially decayed Ka

Zero sequence source


impedances as seen from the
Point of Connection or node
on the Single Line
Diagram (as appropriate)
consistent with the maximum
infeed above:

- Resistance % on 100

- Reactance % on 100

Positive sequence X/R ratio


at instance of fault

Pre-Fault voltage magnitude


at which the maximum fault
currents were calculated p.u.

Issue 5 Revision 15 DRC 03 February 2016


67 of 105
SCHEDULE 13 - FAULT INFEED DATA
PAGE 2 OF 2

DATA DESCRIPTION UNITS F.Yr F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to
0 1 2 3 4 5 6 7 RTL
SHORT CIRCUIT INFEED TO THE CUSC CUSC
Contract App.
NATIONAL ELECTRICITY Form
TRANSMISSION SYSTEM FROM
USERS SYSTEM AT A CONNECTION
POINT
Negative sequence
impedances
of Users System as seen
from
the Point of Connection or
node on the Single Line
Diagram (as appropriate). If
no data is given, it will be
assumed that they are equal
to the positive sequence
values.

- Resistance % on
100
- Reactance % on
100

Issue 5 Revision 15 DRC 03 February 2016


68 of 105
SCHEDULE 14 - FAULT INFEED DATA (GENERATORS INCLUDING UNIT
TRANSFORMERS AND STATION TRANSFORMERS)
PAGE 1 OF 5

The data in this Schedule 14 is all Standard Planning Data, and is to be provided by Generators,
with respect to all directly connected Power Stations, all Embedded Large Power Stations and all
Embedded Medium Power Stations connected to the Subtransmission System. A data submission
is to be made each year in Week 24.
Fault infeeds via Unit Transformers
A submission should be made for each Generating Unit with an associated Unit Transformer.
Where there is more than one Unit Transformer associated with a Generating Unit, a value for the
total infeed through all Unit Transformers should be provided. The infeed through the Unit
Transformer(s) should include contributions from all motors normally connected to the Unit Board,
together with any generation (eg Auxiliary Gas Turbines) which would normally be connected to the
Unit Board, and should be expressed as a fault current at the Generating Unit terminals for a fault at
that location.

DATA DESCRIPTION UNITS F.Yr. F.Yr. F.Yr F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to
0 1 2 3 4 5 6 7 RTL
CUSC CUSC
(PC.A.2.5) Contract App.
Form

Name of Power Station

Number of Unit Transformer

Symmetrical three phase short-


circuit current infeed through the
Unit Transformers(s) for a fault
at the Generating Unit
terminals

- at instant of fault kA

- after subtransient fault


current contribution has
substantially decayed kA

Positive sequence X/R ratio


at instance of fault

Subtransient time constant (if ms


significantly different from 40ms)

Pre-fault voltage at fault point (if


different from 1.0 p.u.)

The following data items need only


be supplied if the Generating
Unit Step-up Transformer can
supply zero sequence current
from the Generating Unit side to
the National Electricity
Transmission System

Zero sequence source


impedances as seen from the
Generating Unit terminals
consistent with the maximum
infeed above:

- Resistance % on
100

Issue 5 Revision 15 DRC 03 February 2016


69 of 105
- Reactance % on
100

Issue 5 Revision 15 DRC 03 February 2016


70 of 105
SCHEDULE 14 - FAULT INFEED DATA (GENERATORS INCLUDING UNIT
TRANSFORMERS AND STATION TRANSFORMERS)
PAGE 2 OF 5

Fault infeeds via Station Transformers


A submission is required for each Station Transformer directly connected to the National Electricity
Transmission System. The submission should represent normal operating conditions when the maximum
number of Gensets are Synchronised to the System, and should include the fault current from all motors
normally connected to the Station Board, together with any Generation (eg Auxiliary Gas Turbines) which
would normally be connected to the Station Board. The fault infeed should be expressed as a fault current
at the hv terminals of the Station Transformer for a fault at that location.
If the submission for normal operating conditions does not represent the worst case, then a separate
submission representing the maximum fault infeed that could occur in practice should be made.

DATA DESCRIPTION UNITS F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to
0 1 2 3 4 5 6 7 RTL
CUSC CUSC
(PC.A.2.5) Contract App.
Form

Name of Power Station

Number of Station
Transformer

Symmetrical three phase


short-circuit current infeed for a
fault at the Connection Point

- at instant of fault kA

- after subtransient fault


current contribution
has substantially kA
decayed

Positive sequence X/R ratio


At instance of fault

Subtransient time constant (if


significantly different from mS
40ms)

Pre-fault voltage (if different


from 1.0 p.u.) at fault point (See
note 1)

Zero sequence source


Impedances as seen from
the Point of Connection
Consistent with the
maximum Infeed above:

- Resistance % on
100
- Reactance % on
100

Note 1. The pre-fault voltage provided above should represent the voltage within the range 0.95 to
1.05 that gives the highest fault current
Note 2. % on 100 is an abbreviation for % on 100 MVA
Issue 5 Revision 15 DRC 03 February 2016
71 of 105
SCHEDULE 14 - FAULT INFEED DATA (GENERATORS INCLUDING UNIT
TRANSFORMERS AND STATION TRANSFORMERS)
PAGE 3 OF 5

Fault infeeds from Power Park Modules


A submission is required for the whole Power Park Module and for each Power Park Unit type or
equivalent. The submission shall represent operating conditions that result in the maximum fault
infeed. The fault current from all motors normally connected to the Power Park Units electrical
system shall be included. The fault infeed shall be expressed as a fault current at the terminals of the
Power Park Unit, or the Common Collection Busbar if an equivalent Single Line Diagram and
associated data as described in PC.A.2.2.2 is provided, and the Grid Entry Point, or User System
Entry Point if Embedded, for a fault at the Grid Entry Point, or User System Entry Point if
Embedded.
Should actual data in respect of fault infeeds be unavailable at the time of the application for a CUSC
Contract or Embedded Development Agreement, a limited subset of the data, representing the
maximum fault infeed that may result from all of the plant types being considered, shall be submitted.
This data will, as a minimum, represent the root mean square of the positive, negative and zero
sequence components of the fault current for both single phase and three phase solid faults at the
Grid Entry Point (or User System Entry Point if Embedded) at the time of fault application and
50ms following fault application. Actual data in respect of fault infeeds shall be submitted to NGET
as soon as it is available, in line with PC.A.1.2

DATA DESCRIPTION UNITS F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to
0 1 2 3 4 5 6 7 RTL
CUSC CUSC
(PC.A.2.5) Contract App. Form

Name of Power Station

Name of Power Park Module

Power Park Unit type

A submission shall be provided for the


contribution of the entire Power Park
Module and each type of Power Park
Unit or equivalent to the positive,
negative and zero sequence
components of the short circuit current
at the Power Park Unit terminals, or
Common Collection Busbar, and
Grid Entry Point or User System
Entry Point if Embedded for
(i) a solid symmetrical three phase
short circuit

(ii) a solid single phase to earth short
circuit

(iii) a solid phase to phase short
circuit

(iv) a solid two phase to earth short
circuit
at the Grid Entry Point or User

System Entry Point if Embedded.

If protective controls are used and


active for the above conditions, a
submission shall be provided in the

limiting case where the protective
control is not active. This case may
require application of a non-solid fault,
resulting in a retained voltage at the
fault point.

Issue 5 Revision 15 DRC 03 February 2016


72 of 105
SCHEDULE 14 - FAULT INFEED DATA (GENERATORS INCLUDING UNIT
TRANSFORMERS AND STATION TRANSFORMERS)
PAGE 4 OF 5

DATA UNITS F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA DATA
DESCRIPTION 0 1 2 3 4 5 6 7 to DESCRIPTION
RTL
CUSC CUSC App. Form
Contract
- A continuous time Graphical
trace and table and
showing the root tabular
mean square of the
positive, negative and kA
zero sequence versus s
components of the
fault current from the
time of fault inception
to 140ms after fault
inception at 10ms
intervals

- A continuous time p.u.


trace and table versus s
showing the
positive, negative
and zero
sequence
components of
retained voltage at
the terminals or
Common
Collection
Busbar, if
appropriate

- A continuous time p.u.


trace and table versus s
showing the root
mean square of
the positive,
negative and zero
sequence
components of
retained voltage at
the fault point, if
appropriate

Issue 5 Revision 15 DRC 03 February 2016


73 of 105
SCHEDULE 14 - FAULT INFEED DATA (GENERATORS INCLUDING UNIT
TRANSFORMERS AND STATION TRANSFORMERS)
PAGE 5 OF 5

DATA UNITS F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA DATA
DESCRIPTION 0 1 2 3 4 5 6 7 to DESCRIPTION
RTL
CUSC CUSC App. Form
Contract

For Power Park


Units that utilise a
protective control,
such as a crowbar
circuit, % on
MVA
- additional rotor
resistance applied
to the Power Park % on
Unit under a fault MVA
situation

- additional rotor
reactance
applied to the
Power Park Unit
under a fault
situation.

Positive sequence X/R


ratio of the equivalent at
time of fault at the
Common Collection
Busbar

Minimum zero
sequence impedance
of the equivalent at a
Common Collection
Busbar

Active Power MW
generated pre-fault

Number of Power Park


Units in equivalent
generator

Power Factor (lead or


lag)

Pre-fault voltage (if p.u.


different from 1.0 p.u.)
at fault point (See note
1)

Items of reactive
compensation switched
in pre-fault

Note 1. The pre-fault voltage provided above should represent the voltage within the range 0.95 to 1.05
that gives the highest fault current

Issue 5 Revision 15 DRC 03 February 2016


74 of 105
MOTHBALLED GENERATING UNIT MOTHBALLED POWER PARK MODULE OR MOTHBALLED DC CONVERTER AT A DC CONVERTER
STATION AND ALTERNATIVE FUEL DATA

Issue 5 Revision 15
The following data items must be supplied with respect to each Mothballed Generating Unit Mothballed Power Park Module or Mothballed
DC Converter at a DC Converter station

Power Station_____________________________________ Generating Unit, Power Park Module or DC Converter Name (e.g. Unit 1)
_______________________________

DATA DESCRIPTION UNITS DATA GENERATING UNIT DATA


CAT
<1 1-2 2-3 3-6 6-12 >12 Total MW
month months months months months months being
returned

MW output that can MW DPD


be returned to II
service

DRC
75 of 105
Notes
PAGE 1 OF 3

1. The time periods identified in the above table represent the estimated time it would take to return the Mothballed Generating Unit,
Mothballed Power Park Module or Mothballed DC Converter at a DC Converter Station to service once a decision to return has been
made.
ALTERNATIVE FUEL DATA

2. Where a Mothballed Generating Unit, Mothballed Power Park Module or Mothballed DC Converter at a DC Converter Station can be
physically returned in stages covering more than one of the time periods identified in the above table then information should be provided for
each applicable time period.
3. The estimated notice to physically return MW output to service should be determined in accordance with Good Industry Practice assuming
normal working arrangements and normal plant procurement lead times.
4. The MW output values in each time period should be incremental MW values, e.g. if 150MW could be returned in 2 3 months and an
additional 50MW in 3 6 months then the values in the columns should be Nil, Nil, 150, 50, Nil, Nil, 200 respectively.
5. Significant factors which may prevent the Mothballed Generating Unit, Mothballed Power Park Module or Mothballed DC Converter at a
DC Converter Station achieving the estimated values provided in this table, excluding factors relating to Transmission Entry Capacity,
should be appended separately.
MODULE, MOTHBALLED DC CONVERTERS AT A DC CONVERTER STATION AND
SCHEDULE 15 - MOTHBALLED GENERATING UNIT, MOTHBALLED POWER PARK

03 February 2016
ALTERNATIVE FUEL INFORMATION

The following data items for alternative fuels need only be supplied with respect to each Generating Unit whose primary fuel is gas.

Issue 5 Revision 15
Power Station___________________________ Generating Unit Name (e.g. Unit 1) _____________________________

DATA DESCRIPTION UNITS DATA GENERATING UNIT DATA


CAT
1 2 3 4
Alternative Fuel Type
Text DPD II Oil distillate Other gas* Other* Other*
(*please specify)
CHANGEOVER TO ALTERNATIVE FUEL
For off-line changeover:
Time to carry out off-line fuel changeover Minutes DPD II
Maximum output following off-line changeover MW DPD II

DRC
For on-line changeover:

76 of 105
PAGE 2 OF 3

Time to carry out on-line fuel changeover Minutes DPD II


Maximum output during on-line fuel
MW DPD II
changeover
Maximum output following on-line changeover MW DPD II
ALTERNATIVE FUEL DATA

Maximum operating time at full load assuming:


Typical stock levels Hours DPD II
Maximum possible stock levels Hours DPD II
Maximum rate of replacement of depleted stocks
MWh(electrical)
of alternative fuels on the basis of Good DPD II
/day
Industry Practice
Is changeover to alternative fuel used in normal
Text DPD II
operating arrangements?
Number of successful changeovers carried out in 0 / 1-5 / 0 / 1-5 / 0 / 1-5 / 0 / 1-5 /
the last NGET Financial Year Text DPD II 6-10 / 11-20 6-10 / 11-20 6-10 / 11-20 6-10 / 11-20 /
(** delete as appropriate) / >20 ** / >20 ** / >20 ** >20 **
MODULE, MOTHBALLED DC CONVERTERS AT A DC CONVERTER STATION AND
SCHEDULE 15 - MOTHBALLED GENERATING UNIT, MOTHBALLED POWER PARK

03 February 2016
Issue 5 Revision 15
DATA DESCRIPTION UNITS DATA GENERATING UNIT DATA
CAT
1 2 3 4
CHANGEOVER BACK TO MAIN FUEL
For off-line changeover:
Time to carry out off-line fuel
Minutes
changeover
For on-line changeover:
Time to carry out on-line fuel
Minutes
changeover
Maximum output during on-line fuel
MW

DRC
changeover

77 of 105
PAGE 3 OF 3

Notes
1. Where a Generating Unit has the facilities installed to generate using more than one alternative fuel type details of each
ALTERNATIVE FUEL DATA

alternative fuel should be given.


2. Significant factors and their effects which may prevent the use of alternative fuels achieving the estimated values provided
in this table (e.g. emissions limits, distilled water stocks etc.) should be appended separately.

- No information collated under this Schedule will be transferred to the Relevant Transmission Licensees
MODULE, MOTHBALLED DC CONVERTERS AT A DC CONVERTER STATION AND
SCHEDULE 15 - MOTHBALLED GENERATING UNIT, MOTHBALLED POWER PARK

03 February 2016
Issue 5 Revision 15
BLACK START INFORMATION

The following data/text items are required from each Generator for each BM Unit at a Large Power Station as detailed in PC.A.5.7. Data is not
required for Generating Units that are contracted to provide Black Start Capability, Power Park Modules or Generating Units that have an
Intermittent Power Source. The data should be provided in accordance with PC.A.1.2 and also, where possible, upon request from NGET during a
Black Start.

Data Description Units Data


(PC.A.5.7) ( CUSC Contract) Category

Assuming all BM Units were running immediately prior to the Total Shutdown or Partial Shutdown and in the event
of loss of all external power supplies, provide the following information:

a) Expected time for the first and subsequent BM Units to be Synchronised, from the restoration of external power Tabular or DPD II
supplies, assuming external power supplies are not available for up to 24hrs Graphical

DRC
78 of 105
PAGE 1 OF 1

b) Describe any likely issues that would have a significant impact on a BM Units time to be Synchronised arising as Text DPD II
a direct consequence of the inherent design or operational practice of the Power Station and/or BM Unit, e.g. limited
barring facilities, time from a Total Shutdown or Partial Shutdown at which batteries would be discharged.

Block Loading Capability:

c) Provide estimated Block Loading Capability from 0MW to Registered Capacity of each BM Unit based on the Tabular or DPD II
SCHEDULE 16 - BLACK START INFORMATION

unit being hot (run prior to shutdown) and also cold (not run for 48hrs or more prior to the shutdown). The Block Graphical
Loading Capability should be valid for a frequency deviation of 49.5Hz 50.5Hz. The data should identify any
required hold points.

03 February 2016
SCHEDULE 17 - ACCESS PERIOD DATA
PAGE 1 OF 1

(PC.A.4 - CUSC Contract )

Submissions by Users using this Schedule 17 shall commence in 2011 and shall then continue in
each year thereafter

Access Group

Asset Start End Maintenance Potential Concurrent


Duration
Identifier Week Week Year (1, 2 or 3) Outage (Y/N)

Comments

Issue 5 Revision 15 DRC 03 February 2016


79 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 1 OF 24

The data in this Schedule 18 is required from Generators who are undertaking OTSDUW and
connecting to a Transmission Interface Point.

DATA DESCRIPTION UNITS DATA to DATA GENERATING UNIT OR STATION DATA


RTL CAT.
CUSC CUS F.Yr0 F.Yr1 F.Yr2 F.Yr3 F.Yr4 F.Yr5 F.Yr
Cont C
ract App. 6
Form
INDIVIDUAL OTSDUW DATA

Interface Point Capacity (PC.A.3.2.2 MW


(a)) MVAr



Performance Chart at the Transmission
Interface Point for OTSDUW Plant and
Apparatus (PC.A.3.2.2(f)(iv)

OTSDUW DEMANDS

Demand associated with the OTSDUW


Plant and Apparatus (excluding
OTSDUW DC Converters see Note 1))
supplied at each Interface Point. The
User should also provide the Demand
supplied to each Connection Point on
the OTSDUW Plant and Apparatus.
(PC.A.5.2.5)

- The maximum Demand that could MW DPD I


occur. MVAr DPD I
- Demand at specified time of annual MW DPD II
peak half hour of National Electricity MVAr DPD II
Transmission System Demand at
Annual ACS Conditions.

- Demand at specified time of annual MW DPD II


minimum half-hour of National MVAr DPD II
Electricity Transmission System
Demand.

(Note 1 Demand required from


OTSDUW DC Converters should be
supplied under page 2 of Schedule 18).

Issue 5 Revision 15 DRC 03 February 2016


80 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 2 OF 24

OTSDUW USERS SYSTEM DATA

DATA DESCRIPTION UNITS DATA to RTL DATA


CATEGORY
CUSC CUSC
Contract App.
Form
OFFSHORE TRANSMISSION SYSTEM LAYOUT
(PC.A.2.2.1, PC.A.2.2.2 and P.C.A.2.2.3)

A Single Line Diagram showing connectivity of all of the Offshore SPD


Transmission System including all Plant and Apparatus between the
Interface Point and all Connection Points is required.

This Single Line Diagram shall depict the arrangement(s) of all of the SPD
existing and proposed load current carrying Apparatus relating to both
existing and proposed Interface Points and Connection Points,
showing electrical circuitry (ie. overhead lines, underground cables
(including subsea cables), power transformers and similar equipment),
operating voltages, circuit breakers and phasing arrangements

Operational Diagrams of all substations within the OTSDUW Plant and SPD
Apparatus

SUBSTATION INFRASTRUCTURE (PC.A.2.2.6)

For the infrastructure associated with any OTSDUW Plant and


Apparatus

Rated 3-phase rms short-circuit withstand current kA SPD


Rated 1-phase rms short-circuit withstand current kA SPD
Rated Duration of short-circuit withstand s SPD
Rated rms continuous current A SPD

LUMPED SUSCEPTANCES (PC.A.2.3)

Equivalent Lumped Susceptance required for all parts of the Users


Subtransmission System (including OTSDUW Palnt and Apparatus)
which are not included in the Single Line Diagram.

This should not include:


(a) independently switched reactive compensation equipment
identified above.
(b) any susceptance of the OTSDUW Plant and Apparatus
inherent in the Demand (Reactive Power) data provided on
Page 1 and 2 of this Schedule 14.

Equivalent lumped shunt susceptance at nominal Frequency. % on 100


MVA

Issue 5 Revision 15 DRC 03 February 2016


81 of 105
OFFSHORE TRANSMISSION SYSTEM DATA
Branch Data (PC.A.2.2.4)

Issue 5 Revision 15
PPS PARAMETERS ZPS PARAMETERS Maximum Continuous
Ratings

Node Nod Rated Operating Circuit R1 X1 B1 R0 X0 B0 Winter Sprng Summer Length


1 e2 Voltage Voltage %100 %100 %100 %100 %100M %100M (MVA) Autumn (MVA) (km)
(kV) (kV) MVA MVA MVA MVA VA VA (MVA)

DRC
82 of 105
PAGE 3 OF 24

Notes

1. For information equivalent STC Reference: STCP12-1m Part 3 2.1 Branch Data
2. In the case where an overhead line exists within the OTSDUW Plant and Apparatus the Mutual inductances should also be provided.
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA

03 February 2016
OFFSHORE TRANSMISSION SYSTEM DATA

Issue 5 Revision 15
2 Winding Transfomer Data (PC.A.2.2.5)

The data below is Standard Planning Data, and details should be shown below of all transformers shown on the Single Line Diagram

HV Node HV LV LV Rating Positive Phase Positive Phase Tap Changer Winding Earthing Earthing
Trans-former
(kV) Node (kV) (MVA) Sequence Reactance Sequence Resistance Arr. Method Imped
% on 100MVA % on 100 MVA (Direct /Res Ance
/Reac) method
Max Min Nom Max Min Nom Range Step type
Tap Tap Tap Tap Tap Tap +% to -% size
%

DRC
83 of 105
PAGE 4 OF 24
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA

Notes

1 For information the corresponding STC Referecne is STCP12-1: Part 3 2.4 Transformers

03 February 2016
USERS SYSTEM DATA (OTSUA)

Auto Transformer Data 3-Winding (PC.A.2.2.5)

The data below is all Standard Planning Data, and details should be shown below of all transformers shown on the Single Line Diagram.

Issue 5 Revision 15
HV VH LV VL PSS/E Rating Transfo Positive Phase Positive Phase Taps Earthin EQUIVALENT T ZPS PARAMETERS (FLIP) NGT NGC
NODE (kV) NODE (kV) Circuit (MVA) rmer Sequence Sequence g Sheet Code
Reactance Risistance Impeda
% on 100MVA % on 100 MVA nce
Method
Max Min Nom Max Min Nom Range Step Type Windin ZOH ZOL ZOT
Tap Tap Tap Tap Tap Tap +% to -% size (onload g Dflt X/R =20
% Offload Arrange
R0H X0H R0L X0L R0T X0T
ment
% % % % % %
100 100 100 100 100 100
MVA MVA MVA MVA MVA MVA

DRC
84 of 105
PAGE 5 OF 24

Notes

1.For information STC Reference: STCP12-1: Part 3 - 2.4 Transformers


SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA

03 February 2016
OFFSHORE TRANSMISSION SYSTEM DATA

Issue 5 Revision 15
Circuit Breaker Data (PC.A.2.2.6(a))

The data below is all Standard Planning Data, and should be provided for all OTSUA switchgear (ie. circuit breakers, load
disconnectors and disconnectors)

Circuit Breaker Data Assumed Operating 3 Phase 1 Phase


Times

Location Name Rated Operatin Make Model Type Year Circuit Minimum Total Continuo Fault Rating Fault Break Fault Break Fault Make Fault Rating Fault Break Fault Break Fault Make DC time
Voltage g Voltage Commission Breaker Protection & Time us (RMS Rating (RMS Rating (Peak Rating (Peak (RMS Rating (RMS Rating (Peak Rating (Peak constant at

DRC
ed (mS) Trip Relay (mS) Rating Symmetrical) Symmetrical) Asymmetrical) Asymmetrical) Symmetrical) Symmetrical) Asymmetrical) Asymmetrical) testing of

85 of 105
(mS) (A) (3 phase) (3 phase) (kA) (3 phase) (kA) (3 phase) (kA) (1 phase) (1 phase) (kA) (1 phase) (kA) (1 phase) (kA) asymmetrical
(MVA) (MVA) breaking
PAGE 6 OF 24

ability (s)
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA

03 February 2016
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 7 OF 24

OFFSHORE TRANSMISSION SYSTEM DATA

REACTIVE COMPENSATION EQUIPMENT (PC.A.2.4(e))

Item Node kV Device No. Rating P Loss Tap range Connection


(MVAr) (kW) Arrangement

Notes:

1.For information STC Reference: STCP12-1: Part 3 - 2.5 Reactive Compensation Equipment

2. Data relating to continuously variable reactive compensation equipment (such as statcoms or SVCs)
should be entered on the SVC Modelling table.

3. For the avoidance of doubt this includes any AC Reactive Compensation equipment included within the
OTSDUW DC Converter other than harmonic filter data which is to be entered in the harmonic filter data
table.

PC.A.2.4.1(e A mathematical representation in block diagram format to model the control of any
) dynamic compensation plant. The model should be suitable for RMS dynamic
stability type studies in which the time constants used should not be less than 10ms.

Issue 5 Revision 15 DRC 03 February 2016


86 of 105
OFFSHORE TRANSMISSION SYSTEM DATA
REACTIVE COMPENSATION - SVC Modelling Data (PC.A.2.4.1(e)(iii))

Issue 5 Revision 15
HV LV Control Norminal Target Max Min Slope Voltage Normal R1 X1 R0 X0 Transf. Connection
Node Node Node Voltage Voltage MVAr MVAr % Dependant Running PPS_R PPS_X ZPS_R ZPS_X Winding (Direct/Tert
(kV) (kV) at HV at HV Q Limit Mode Type iary)

DRC
87 of 105
PAGE 8 OF 24

Notes:

1.For information the equivalent STC Ref,erence is: STCP12-1: Part 3 - 2.7 SVC Modelling Data
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA

03 February 2016
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 9 OF 24

OFFSHORE TRANSMISSION SYSTEM DATA


Harmonic Filter Data (including OTSDUW DC Converter harmonic Filter Data)
(PC.A.5.4.3.1(d) and PC.A.6.4.2)

Site Name SLD Reference Point of Filter Connection

Filter Description
Manufacturer Model Filter Type Filter connection Notes
type (Delta/Star,
Grounded/
Ungrounded)

Bus Voltage Rating Q factor Tuning Notes


Frequency

Component Parameters (as per SLD)

Parameter as applicable
Filter Capacitance Inductance (milli- Resistance Notes
Component (R, (micro-Farads) Henrys) (Ohms)
C or L)

Filter frequency characteristics (graphs) detailing for frequency range up to 10kHz and higher

1. Graph of impedance (ohm) against frequency (Hz)


2. Graph of angle (degree) against frequency (Hz)
3. Connection diagram of Filter & Elelments

Notes:
1. For information STC Reference: STCP12-1: Part 3 - 2.8 Harmonic Filter Data

Issue 5 Revision 15 DRC 03 February 2016


88 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 10 OF 24

Information for Transient Overvoltage Assessment (DPD I) (PC.A.6.2 CUSC Contract)

The information listed below may be requested by NGET from each User undertaking OTSDUW with
respect to any Interface Point or Connection Point to enable NGET to assess transient overvoltage on
the National Electricity Transmission System.

(a) Busbar layout plan(s), including dimensions and geometry showing positioning of any current and
voltage transformers, through bushings, support insulators, disconnectors, circuit breakers, surge
arresters, etc. Electrical parameters of any associated current and voltage transformers, stray
capacitances of wall bushings and support insulators, and grading capacitances of circuit breakers;

(b) Electrical parameters and physical construction details of lines and cables connected at that
busbar. Electrical parameters of all plant e.g., transformers (including neutral earthing impedance
or zig-zag transformers if any), series reactors and shunt compensation equipment connected at
that busbar (or to the tertiary of a transformer) or by lines or cables to that busbar;

(c) Basic insulation levels (BIL) of all Apparatus connected directly, by lines or by cables to the
busbar;

(d) Characteristics of overvoltage Protection devices at the busbar and at the termination points of all
lines, and all cables connected to the busbar;

(e) Fault levels at the lower voltage terminals of each transformer connected to each Interface Point
or Connection Point without intermediate transformation;

(f) The following data is required on all transformers within the OTSDUW Plant and Apparatus.

(g) An indication of which items of equipment may be out of service simultaneously during Planned
Outage conditions.

Harmonic Studies (DPD I) (PC.A.6.4 CUSC Contract)

The information given below, both current and forecast, where not already supplied in this Schedule 14
may be requested by NGET from each User if it is necessary for NGET to evaluate the
production/magnification of harmonic distortion on National Electricity Transmission System. The
impact of any third party Embedded within the Users System should be reflected:-

(a) Overhead lines and underground cable circuits (including subsea cables) of the User's OTSDUW
Plant and Apparatus must be differentiated and the following data provided separately for each
type:-

Positive phase sequence resistance


Positive phase sequence reactance
Positive phase sequence susceptance

(b) for all transformers connecting the OTSDUW Plant and Apparatus to a lower voltage:-

Rated MVA
Voltage Ratio
Positive phase sequence resistance
Positive phase sequence reactance

Issue 5 Revision 15 DRC 03 February 2016


89 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 11 OF 24

(c) at the lower voltage points of those connecting transformers:-

Equivalent positive phase sequence susceptance


Connection voltage and MVAr rating of any capacitor bank and component design parameters if configured
as a filter

Equivalent positive phase sequence interconnection impedance with other lower voltage points
The minimum and maximum Demand (both MW and MVAr) that could occur
Harmonic current injection sources in Amps at the Connection Points and Interface Points

(d) an indication of which items of equipment may be out of service simultaneously during Planned
Outage conditions

Voltage Assessment Studies (DPD I) (PC.A.6.5 CUSC Contract)

The information listed below, where not already supplied in this Schedule 14, may be requested by NGET
from each User undertaking OTSDUW with respect to any Connection Point or Interface Point if it is
necessary for NGET to undertake detailed voltage assessment studies (eg to examine potential voltage
instability, voltage control co-ordination or to calculate voltage step changes on the National Electricity
Transmission System).

(a) For all circuits of the Users OTSDUW Plant and Apparatus:-

Positive Phase Sequence Reactance


Positive Phase Sequence Resistance
Positive Phase Sequence Susceptance
MVAr rating of any reactive compensation equipment

(b) for all transformers connecting the User's OTSDUW Plant and Apparatus to a lower voltage:-

Rated MVA
Voltage Ratio
Positive phase sequence resistance
Positive Phase sequence reactance
Tap-changer range
Number of tap steps
Tap-changer type: on-load or off-circuit
AVC/tap-changer time delay to first tap movement
AVC/tap-changer inter-tap time delay

(c) at the lower voltage points of those connecting transformers

Equivalent positive phase sequence susceptance


MVAr rating of any reactive compensation equipment
Equivalent positive phase sequence interconnection impedance with other lower voltage points
The maximum Demand (both MW and MVAr) that could occur
Estimate of voltage insensitive (constant power) load content in % of total load at both winter peak
and 75% off-peak load conditions

Issue 5 Revision 15 DRC 03 February 2016


90 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 12 OF 24

Short Circuit Analyses:(DPD I) (PC.A.6.6 CUSC Contract)

The information listed below, both current and forecast, and where not already supplied under this
Schedule 14, may be requested by NGET from each User undertaking OTSDUW with respect to any
Connection Point or Interface Point where prospective short-circuit currents on equipment owned by a
Transmission Licensee or operated or managed by NGET are close to the equipment rating.

(a) For all circuits of the Users OTSDUW Plant and Apparatus:-
Positive phase sequence resistance
Positive phase sequence reactance
Positive phase sequence susceptance
Zero phase sequence resistance (both self and mutuals)
Zero phase sequence reactance (both self and mutuals)
Zero phase sequence susceptance (both self and mutuals)

(b) for all transformers connecting the User's OTSDUW Plant and Apparatus to a lower voltage:-

Rated MVA
Voltage Ratio
Positive phase sequence resistance (at max, min and nominal tap)
Positive Phase sequence reactance (at max, min and nominal tap)
Zero phase sequence reactance (at nominal tap)
Tap changer range
Earthing method: direct, resistance or reactance
Impedance if not directly earthed

(c) at the lower voltage points of those connecting transformers:-

The maximum Demand (in MW and MVAr) that could occur


Short-circuit infeed data in accordance with PC.A.2.5.6(a) unless the Users OTSDUW Plant and
Apparatus runs in parallel with the Subtransmission System, when to prevent double counting in
each node infeed data, a equivalent comprising the data items of PC.A.2.5.6(a) for each node
together with the positive phase sequence interconnection impedance between the nodes shall be
submitted

Issue 5 Revision 15 DRC 03 February 2016


91 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 13 OF 24

Fault infeed data to be submitted by OTSDUW Plant and Apparatus providing a fault infeed (including
OTSDUW DC Converters) (PC.A.2.5.5)

A submission is required for OTSDUW Plant and Apparatus (including OTSDUW DC Converters at each
Transmission Interface Point and Connection Point. The submission shall represent operating
conditions that result in the maximum fault infeed. The fault current from all auxilaries of the OTSDUW
Plant and Apparatus at the Transmission Interface Point and Connection Point shall be included. The
fault infeed shall be expressed as a fault current at the Transmission Interface Point and also at each
Connection Point.

Should actual data in respect of fault infeeds be unavailable at the time of the application for a CUSC
Contract or Embedded Development Agreement, a limited subset of the data, representing the maximum
fault infeed that may result from the OTSDUW Plant and Apparatus, shall be submitted. This data will, as
a minimum, represent the root mean square of the positive, negative and zero sequence components of
the fault current for both single phase and three phase solid faults at each Connection Point and Interface
Point at the time of fault application and 50ms following fault application. Actual data in respect of fault
infeeds shall be submitted to NGET as soon as it is available, in line with PC.A.1.2.

DATA DESCRIPTION UNITS F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to RTL
0 1 2 3 4 5 6 7
CUSC CUSC
(PC.A.2.5) Contract App.
Form

Name of OTSDUW Plant and


Apparatus

OTSDUW DC Converter type (ie


voltage or current source)

A submission shall be provided for


the contribution of each OTSDUW
Plant and Apparatus to the positive,
negative and zero sequence
components of the short circuit
current at the Interface Point and
each Connection Point for
(i) a solid symmetrical three phase
short circuit
(ii) a solid single phase to earth short
circuit
(iii) a solid phase to phase short
circuit
(iv) a solid two phase to earth short
circuit

If protective controls are used and


active for the above conditions, a
submission shall be provided in the
limiting case where the protective
control is not active. This case may
require application of a non-solid
fault, resulting in a retained voltage at
the fault point.

Issue 5 Revision 15 DRC 03 February 2016


92 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 14 OF 24

DATA DESCRIPTION UNITS F. F. F. F. F. F. F. F. DATA to


Yr. Yr. Yr. Yr. Yr. Yr. Yr. Yr. RTL
0 1 2 3 4 5 6 7
CUSC CUSC
Contract App.
Form

- A continuous time trace and Graphical


table showing the root mean and tabular
square of the positive, negative
and zero sequence components kA
of the fault current from the time versus s
of fault inception to 140ms after
fault inception at 10ms intervals

- A continuous time trace and p.u. versus


table showing the positive, s
negative and zero sequence
components of retained
voltage at the Interface Point
and each Connection Point,
if appropriate

- A continuous time trace and p.u. versus


table showing the root mean s
square of the positive,
negative and zero sequence
components of retained
voltage at the fault point, if
appropriate

Positive sequence X/R ratio of the


equivalent at time of fault at the
Interface Point and each
Connection Point

Minimum zero sequence


impedance of the equivalent at the
Interface Point and each
Connection Point

Active Power transfer at the MW


Interface Point and each
Connection Pointpre-fault

Power Factor (lead or lag)

Pre-fault voltage (if different from p.u.


1.0 p.u.) at fault point (See note 1)

Items of reactive compensation


switched in pre-fault

Note 1. The pre-fault voltage provided above should represent the voltage within the range 0.95 to 1.05
that gives the highest fault current

Issue 5 Revision 15 DRC 03 February 2016


93 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 15 OF 24

Thermal Ratings Data (PC.A.2.2.4)


CIRCUIT RATING SCHEDULE

Voltage Offshore TO Name Issue Date


132kV
CIRCUIT Name from Site A Site B

Winter Spring/Autumn Summer


OVERALL CCT RATINGS %Nom Limit Amps MVA %Nom Limit Amps MVA %Nom Limit Amps MVA
Pre-Fault Continuous 84% Line 485 111 84% Line 450 103 84% Line 390 89
Post-Fault Continuous 100% Line 580 132 100% Line 540 123 100% Line 465 106

Prefault load 6hr 95% Line 580 132 95% Line 540 123 95% Line 465 106
exceeds line 20m Line 580 132 Line 540 123 Line 465 106
prefault
10m mva Line 580 132 mva Line 540 123 mva Line 465 106
continuous rating
5m 125 Line 580 132 116 Line 540 123 100 Line 465 106
3m Line 580 132 Line 540 123 Line 465 106

6hr 90% Line 580 132 90% Line 540 123 90% Line 465 106
20m Line 580 132 Line 540 123 Line 465 106
Short Term 10m mva Line 580 132 mva Line 540 123 mva Line 465 106
Overloads 5m 118 Line 580 132 110 Line 540 123 95 Line 465 106
3m Line 580 132 Line 540 123 Line 465 106

Limiting Item 6hr 84% Line 580 132 84% Line 540 123 84% Line 465 106
and permitted 20m Line 590 135 Line 545 125 Line 470 108
overload 10m mva Line 630 144 mva Line 580 133 mva Line 495 113
values 5m 110 Line 710 163 103 Line 655 149 89 Line 555 126
for different 3m Line 810 185 Line 740 170 Line 625 143
times and
pre-fault loads 6hr 75% Line 580 132 75% Line 540 123 75% Line 465 106
20m Line 595 136 Line 555 126 Line 475 109
10m mva Line 650 149 mva Line 600 137 mva Line 510 116
5m 99 Line 760 173 92 Line 695 159 79 Line 585 134
3m Line 885 203 Line 810 185 Line 685 156

6hr 60% Line 580 132 60% Line 540 123 60% Line 465 106
20m Line 605 138 Line 560 128 Line 480 110
10m mva Line 675 155 mva Line 620 142 mva Line 530 121
5m 79 Line 820 187 73 Line 750 172 63 Line 635 145
3m Line 985 226 Line 900 206 Line 755 173

6hr 30% Line 580 132 30% Line 540 123 30% Line 465 106
20m Line 615 141 Line 570 130 Line 490 112
10m mva Line 710 163 mva Line 655 150 mva Line 555 127
5m 39 Line 895 205 36 Line 820 187 31 Line 690 158
3m Line 1110 255 Line 1010 230 Line 845 193

Issue 5 Revision 15 DRC 03 February 2016


94 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 16 OF 24

6hr
20m
10m
5m
3m

6hr
20m
10m
5m
3m

Notes or
Restrictions
Detailed
Notes: 1. For information the equivalent STC Reference: STCP12-1: Part 3 - 2.6 Thermal Ratings
2. The values shown in the above table is example data.

Issue 5 Revision 15 DRC 03 February 2016


95 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 17 OF 24

Protection Policy (PC.A.6.3)

To include details of the protection policy

Protection Schedules(PC.A.6.3)

Data schedules for the protection systems associated with each primary plant item including:
Protection, Intertrip Signalling & operating times
Intertripping and protection unstabilisation initiation
Synchronising facilities
Delayed Auto Reclose sequence schedules

Automatic Switching Scheme Schedules (PC.A.2.2.7)

A diagram of the scheme and an explanation of how the system will operate and what plant will be
affected by the schemes operation.

Issue 5 Revision 15 DRC 03 February 2016


96 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 18 OF 24

GENERATOR INTERTRIP SCHEMES (PC.A.2.2.7(b))

Substation: _______________________________

Details of Generator Intertrip Schemes:

A diagram of the scheme and an explanation of how the system will operate and what plant will be effected
by the schemes operation.

DEMAND INTERTRIP SCHEMES (PC.A.2.2.7(b))

Substation:________________________________

Details of Demand Intertrip Schemes:

A diagram of the scheme and an explanation of how the system will operate and what plant will be effected
by the schemes operation

Issue 5 Revision 15 DRC 03 February 2016


97 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 19 OF 24

Specific Operating Requirements (CC.5.2.1)

SUBSTATION OPERATIONAL GUIDE

Substation: __________________________

Location Details:

Postal Address: Telephone Nos. Map Ref.

National Grid Interface

Generator Interface

1. Substation Type:

2. Voltage Control: (short description of voltage control system. To include mention of modes ie
Voltage, manual etc. Plus control step increments ie 0.5%-0.33kV?)

3. Energisation Switching Information: (The standard energisation switching process from dead.)

4. Intertrip Systems:

5. Reactive Plant Outage: (A short explanation of any system re-configurations required to facilitate
the outage of any reactive plant which form part of the OTSDUW Plant and Apparatus equipment.
Also any generation restrictions required).

6. Harmonic Filter Outage: (An explanation as to any OTSDUW Plant and Apparatus
reconfigurations required to facilitate the outage and maintain the system within specified Harmonic
limits, also any generation restrictions required).

Issue 5 Revision 15 DRC 03 February 2016


98 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 20 OF 24

OTSDUW DC CONVERTER TECHNICAL DATA


OTSDUW DC CONVERTER NAME DATE:___________

Data Description Units DATA to Data DC Converter Station Data


RTL Category
CUSC CUSC
(PC.A.4 and PC.A.5.2.5) Contract App.
Form

OTSDUW DC CONVERTER (CONVERTER


DEMANDS):

Demand supplied through Station


Transformers associated with the
OTSDUW DC Converter at each Interface
Point and each Offshore Connection
Point Grid Entry Point [PC.A.4.1]

- Demand with all OTSDUW DC MW DPD II


Converters operating at Interface Point MVAr DPD II
Capacity .

- Demand with all OTSDUW DC MW
DPD II
Converters operating at maximum MVAr DPD II
Interface Point flow from the Interface
Point to each Offshore Grid Entry Point .

- The maximum Demand that could occur. MW DPD II


MVAr DPD II

- Demand at specified time of annual MW DPD II
peak half hour of NGET Demand at MVAr DPD II
Annual ACS Conditions.

- Demand at specified time of annual MW DPD II


minimum half-hour of NGET Demand. MVAr

OTSDUW DC CONVERTER DATA


SPD+
Number of poles, i.e. number of OTSDUW DC Text

Converters
SPD+
Pole arrangement (e.g. monopole or bipole) Text


Return path arrangement Diagram

Details of each viable operating configuration


SPD+

Configuration 1 Diagram

Configuration 2 Diagram

Configuration 3 Diagram


Configuration 4 Diagram

Configuration 5 Diagram
Configuration 6 Diagram

Issue 5 Revision 15 DRC 03 February 2016


99 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 21 OF 24

Data Description Units DATA to Data Operating Configuration


RTL Category
CUSC CUSC 1 2 3 4 5 6
Contrac App.
t Form

OTSDUW DC CONVERTER DATA


(PC.A.3.3.1(d))

OTSDUW DC Converter Type (e.g. current or Text SPD


Voltage source)


If the busbars at the Interface Point or Section SPD
Connection Point are normally run in separate Number
sections identify the section to which the
OTSDUW DC Converter configuration is SPD+
connected MW

Rated MW import per pole (PC.A.3.3.1) SPD+


MW
Rated MW export per pole (PC.A.3.3.1)
ACTIVE POWER TRANSFER CAPABILITY
(PC.A.3.2.2)
Interface Point Capacity
MW SPD
MVAr SPD

OTSDUW DC CONVERTER TRANSFORMER


(PC.A.5.4.3.1)

Rated MVA MVA DPD II


Winding arrangement

Nominal primary voltage kV DPD II

Nominal secondary (converter-side) voltage(s) kV DPD II
Positive sequence reactance
Maximum tap % on DPD II
Nominal tap MVA DPD II
Minimum tap % on DPD II
Positive sequence resistance MVA
Maximum tap % on DPD II

Nominal tap MVA DPD II

Minimum tap DPD II
Zero phase sequence reactance % on DPD II
Tap change range MVA DPD II
Number of steps % on DPD II
MVA
% on
MVA
% on
MVA
+% / -%

Issue 5 Revision 15 DRC 03 February 2016


100 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 22 OF 24

Data Description Units DATA to Data Operating configuration


RTL Category
CUSC CUSC 1 2 3 4 5 6
Contrac App.
t Form
OTSDUW DC CONVERTER NETWORK
DATA
(PC.A.5.4.3.1 (c))
kV DPD II
Rated DC voltage per pole A DPD II
Rated DC current per pole

Details of the OTSDUW DC Network Diagram DPD II
described in diagram form including
resistance, inductance and capacitance of
all DC cables and/or DC lines. Details of
any line reactors (including line reactor
resistance), line capacitors, DC filters,
earthing electrodes and other conductors
that form part of the OTSDUW DC
Network should be shown.

Issue 5 Revision 15 DRC 03 February 2016


101 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 23 OF 24

Data Description Units DATA to Data Operating configuration


RTL Category
CUSC CUSC
Contract App.
1 2 3 4 5 6
Form

OTSDUW DC CONVERTER CONTROL


SYSTEMS
(PC.A.5.4.3.2)

Static VDC PDC (DC voltage DC power) or Diagram


DPD II

Static VDC IDC (DC voltage DC current) Diagram
DPD II
characteristic (as appropriate) when
operating as Diagram DPD II
Rectifier
Inverter

Details of rectifier mode control system, DPD II


Diagram
in block diagram form together with
parameters showing transfer functions of
individual elements. Diagram DPD II

Details of inverter mode control system,


in block diagram form showing transfer
functions of individual elements including DPD II
Diagram
parameters (as applicable).

Details of OTSDUW DC Converter


transformer tap changer control system in DPD II
block diagram form showing transfer functions Diagram
of individual elements including parameters.

Details of AC filter control systems in block DPD II


Diagram
diagram form showing transfer functions of
individual elements including parameters

Details of any frequency and/or load control DPD II
systems in block diagram form showing Diagram
transfer functions of individual elements
including parameters.

Details of any large or small signal modulating DPD II
controls, such as power oscillation Diagram
damping controls or sub-synchronous
oscillation damping controls, that have not
been submitted as part of the above
control system data.

Transfer block diagram representation of the


reactive power control at converter ends for a
voltage source converter.

Issue 5 Revision 15 DRC 03 February 2016


102 of 105
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 24 OF 24

Data Description Units DATA to Data Operating configuration


RTL Category
CUSC CUSC
Contract App.
1 2 3 4 5 6
Form

LOADING PARAMETERS (PC.A.5.4.3.3)

MW Export from the Offshore Grid Entry


Point to the Transmission Interface Point DPD I
MW/s
Nominal loading rate MW/s
DPD I
Maximum (emergency) loading rate

Maximum recovery time, to 90% of pre-fault s DPD II
loading, following an AC system fault or
severe voltage depression.

Maximum recovery time, to 90% of pre-fault DPD II
s
loading, following a transient DC Network
fault.

Issue 5 Revision 15 DRC 03 February 2016


103 of 105
SCHEDULE 19 - USER DATA FILE STRUCTURE
PAGE 1 OF 2

The structure of the User Data File Structure is given below.

i.d. Folder name Description of contents


Part A: Commercial & Legal
A2 Commissioning Commissioning & Test Programmes
A3 Statements Statements of Readiness
A9 AS Monitoring Ancillary Services Monitoring
A10 Self Certification User Self Certification of Compliance
A11 Compliance statements Compliance Statement
Part 1: Safety & System Operation
1.1 Interface Agreements Interface Agreements
1.2 Safety Rules Safety Rules
1.3 Switching Procedures Local Switching Procedures
1.4 Earthing Earthing
1.5 SRS Site Responsibility Schedules
1.6 Diagrams Operational and Gas Zone Diagrams
1.7 Drawings Site Common Drawings
1.8 Telephony Control Telephony
1.9 Safety Procedures Local Safety Procedures
1.10 Co-ordinators Safety Co-ordinators
1.11 RISSP Record of Inter System Safety Precautions
1.12 Tel Numbers Telephone Numbers for Joint System
Incidents
1.13 Contact Details Contact Details (fax, tel, email)
1.14 Restoration Plan Local Joint Restoration Plan (incl. black start
if applicable)
1.15 Maintenance Maintenance Standards
Part 2: Connection Technical Data
2.1 DRC Schedule 5 DRC Schedule 5 Users System Data
2.2 Protection Report Protection Settings Reports
2.3 Special Automatic Special Automatic Facilities e.g. intertrip
Facilities
2.4 Operational Metering Operational Metering
2.5 Tariff Metering Tariff Metering
2.6 Operational Comms Operational Communications
2.7 Monitoring Performance Monitoring
2.8 Power Quality Power Quality Test Results (if required)

Issue 5 Revision 15 DRC 03 February 2016


104 of 105
SCHEDULE 19 - USER DATA FILE STRUCTURE
PAGE 2 OF 2

Part 3: Generator Technical Data


3.1 DRC Schedule 1 DRC Schedule 1 - Generating Unit
3.2 DRC Schedule 2 DRC Schedule 2 - Generation Planning Data
3.3 DRC Schedule 4 DRC Schedule 4 Frequency Droop &
Response
3.4 DRC Schedule 14 DRC Schedule 14 Fault Infeed Data
Generators
3.5 Special Generator Special Generator Protection eg Pole
Protection slipping; islanding
3.6 Compliance Tests Compliance Tests & Evidence
3.7 Compliance Studies Compliance Simulation Studies
3.8 Site Specific Bilateral Connections Agreement Technical
Data & Compliance
Part 4: General DRC Schedules
4.1 DRC Schedule 3 DRC Schedule 3 Large Power Station
Outage Information
4.2 DRC Schedule 6 DRC Schedule 6 Users Outage
Information
4.3 DRC Schedule 7 DRC Schedule 7 Load Characteristics
4.4 DRC Schedule 8 DRC Schedule 8 BM Unit Data (if
applicable)
4.5 DRC Schedule 10 DRC Schedule 10 Demand Profiles
4.6 DRC Schedule 11 DRC Schedule 11 Connection Point Data
Part 5: OTSDUW Data And Information
(if applicable and prior to OTSUA Transfer Time)
Diagrams
Circuits Plant and Apparatus
Circuit Parameters
Protection Operation and Autoswitching
Automatic Control Systems
Mathematical model of dynamic
compensation plant

< END OF DATA REGISTRATION CODE >

Issue 5 Revision 15 DRC 03 February 2016


105 of 105
GENERAL CONDITIONS
(GC)

CONTENTS

(This contents page does not form part of the Grid Code)

Paragraph No/Title Page Number


GC.1 INTRODUCTION.......................................................................................................................................2
GC.2 SCOPE ......................................................................................................................................................2
GC.3 UNFORESEEN CIRCUMSTANCES .........................................................................................................2
GC.4 GRID CODE REVIEW PANEL ..................................................................................................................2
GC.5 COMMUNICATION BETWEEN NGET AND USERS ...............................................................................4
GC.6 MISCELLANEOUS ....................................................................................................................................4
GC.7 OWNERSHIP OF PLANT AND/OR APPARATUS ...................................................................................5
GC.8 SYSTEM CONTROL .................................................................................................................................5
GC.9 EMERGENCY SITUATIONS ....................................................................................................................5
GC.10 MATTERS TO BE AGREED ...................................................................................................................5
GC.11 GOVERNANCE OF ELECTRICAL STANDARDS ..................................................................................5
GC.12 CONFIDENTIALITY ................................................................................................................................8
GC.13 RELEVANT TRANSMISSION LICENSEES ............................................................................................8
GC.14 BETTA TRANSITION ISSUES................................................................................................................8
GC.15 EMBEDDED EXEMPTABLE LARGE AND MEDIUM POWER STATIONS............................................8
GC.16 SIGNIFICANT CODE REVIEW ...............................................................................................................9
ANNEX TO THE GENERAL CONDITIONS .......................................................................................................10
APPENDIX TO THE GENERAL CONDITIONS .................................................................................................13

Issue 5 Revision 16 GC 24 May 2016


i
GC.1 INTRODUCTION
GC.1.1 The General Conditions contain provisions which are of general application to all provisions of
the Grid Code. Their objective is to ensure, to the extent possible, that the various sections of
the Grid Code work together and work in practice for the benefit of all Users.

GC.2 SCOPE
GC.2.1 The General Conditions apply to all Users (including, for the avoidance of doubt, NGET).

GC.3 UNFORESEEN CIRCUMSTANCES


GC.3.1 If circumstances arise which the provisions of the Grid Code have not foreseen, NGET shall, to
the extent reasonably practicable in the circumstances, consult promptly and in good faith all
affected Users in an effort to reach agreement as to what should be done. If agreement
between NGET and those Users as to what should be done cannot be reached in the time
available, NGET shall determine what is to be done. Wherever NGET makes a determination, it
shall do so having regard, wherever possible, to the views expressed by Users and, in any
event, to what is reasonable in all the circumstances. Each User shall comply with all instructions
given to it by NGET following such a determination provided that the instructions are consistent
with the then current technical parameters of the particular User's System registered under the
Grid Code. NGET shall promptly refer all such unforeseen circumstances and any such
determination to the Panel for consideration in accordance with GC.4.2(e).

GC.4 THE GRID CODE REVIEW PANEL


GC.4.1 NGET shall establish and maintain the Panel, which shall be a standing body to carry out the
functions referred to in paragraph GC.4.2.
GC.4.2 The Panel shall:
(a) keep the Grid Code and its working under review;
(b) review all suggestions for GC Modification Proposals which the Authority or any User or
any Relevant Transmission Licensee (in respect of PC.3.4, PC.3.5, PC.6.2, PC Appendix
A and C, CC.6.1, CC.6.2, CC.6.3, OC2.3.2, OC8 and GC.11, OC7.6, OC9.4 and OC9.5)
may wish to submit to NGET for consideration by the Panel from time to time;
(c) publish recommendations as to GC Modification Proposals that NGET or the Panel feels
are necessary or desirable and the reasons for the recommendations;
(d) issue guidance in relation to the Grid Code and its implementation, performance and
interpretation when asked to do so by any User; consider what changes are necessary to
the Grid Code arising out of any unforeseen circumstances referred to it by NGET under
GC.3;
(e) consider and identify changes to the Grid Code to remove any unnecessary differences in
the treatment of issues in Scotland from their treatment in England and Wales; and
(f) consider any changes to the Code Administration Code of Practice that the Code
Administrator considers appropriate to raise.
GC.4.3 The Panel shall consist of:
(a) a Chairman and up to 4 members appointed by NGET;
(b) a person appointed by the Authority; and
(c) the following members:
(i) 3 persons representing those Generators each having Large Power Stations with
a total Registered Capacity in excess of 3 GW;
(ii) a person representing those Generators each having Large Power Stations with
Issue 5 Revision 16 GC 24 May 2016
2 of 17
a total Registered Capacity of 3 GW or less;
(iii) 2 persons representing the Network Operators in England and Wales;
(iv) a person representing the Network Operators in Scotland;
(v) a person representing the Suppliers;
(vi) a person representing the Non Embedded Customers;
(vii) a person representing the Generators with Small Power Stations and/or Medium
Power Stations (other than Generators who also have Large Power Stations);
(viii) a person representing the BSC Panel;
(ix) a person representing the Externally Interconnected System Operators;
(x) a person representing Generators with Novel Units; and
(xi) 2 persons representing Relevant Transmission Licensees (in respect of PC.6.2,
PC.6.3, PC Appendix A C and E, CC.6.1, CC.6.2, CC.6.3, OC8 and GC.11, OC7.6,
OC9.4 and OC9.5).
each of whom shall be appointed pursuant to the rules issued pursuant to GC.4.4.
GC.4.4 The Panel shall establish and comply at all times with its own rules and procedures relating to
the conduct of its business, which shall be approved by the Authority.
GC.4.5 NGET shall consult in writing all Authorised Electricity Operators which are liable to be
materially affected in relation to all GC Modification Proposals and shall submit all GC
Modification Proposals to the Panel for discussion prior to such consultation. Each GC
Modification Proposals shall include an evaluation of whether the amendment would better
facilitate the achievement of the Grid Code objectives, as provided in NGET's Transmission
Licence. Where the impact on greenhouse gasses arising from any GC Modification Proposal
is likely to be material, this evaluation shall include an assessment of the quantifiable impact of
any GC Modification Proposal on greenhouse gas emissions, such assessment to be
conducted in accordance with any guidance (on the treatment of carbon costs and evaluation of
greenhouse gas emissions) as may be issued by the Authority from time to time.
GC.4.6 NGET shall establish (and, where appropriate, revise from time to time) joint working
arrangements with the STC Committee, the CM Administrative Parties and the Secretary of
State to facilitate the identification, co-ordination, making and implementation of change to the
STC, and the identification of potential inconsistencies between GC Modification Proposals
and Capacity Market Documents or the CfD Documents (as applicable) consequent on a GC
Modification Proposals in a full and timely manner. These working arrangements shall be
such as enable the consideration development and evaluation of GC Modification Proposals
to proceed in a full and timely manner and enable changes to the STC, and enable the
identification of inconsistencies between GC Modification Proposals and the Capacity Market
Documents and/or CfD Documents to be raised with the CM Administrative Parties and the
Secretary of State, consequent on a GC Modification Proposals to be made and given effect
wherever possible (subject to any necessary consent of the Authority) at the same time as such
approved amendment is made and given effect.
GC.4.7 NGET shall ensure that the Code Administrator undertakes its functions consistently with the
relevant provisions of the Code Administration Code of Practice.
GC.4.8 The procedures set out in the General Conditions, to the extent that they are dealt with in the
Code Administration Code of Practice, are consistent with the principles contained in the
Code Administration Code of Practice. Where inconsistencies or conflicts exist between the
Grid Code and the Code Administration Code of Practice, the Grid Code shall take
precedence.
GC.4.9 NGET is required by its Licence to provide a report to the Authority where NGET determines
that GC Modification Proposals are required. Following provision of such report to the
Authority, if the Authority determines that it is such that the Authority cannot properly form an
opinion on the GC Modification Proposal, it may issue a direction to the NGET:
Issue 5 Revision 16 GC 24 May 2016
3 of 17
(a) specifying the additional steps (including drafting or amending existing drafting associated
with the amendment), revisions (including revision to the timetable), analysis or information
that it requires in order to form such an opinion; and
(b) requiring the report to be revised and to be re-submitted.
GC.4.10 If a report is to be revised and re-submitted in accordance with a direction issued pursuant to
GC.4.9, it shall be re-submitted as soon after the Authoritys direction as is appropriate, taking
into account the complexity, importance and urgency of the GC Modification Proposal. NGET
shall decide on the level of analysis and consultation required in order to comply with the
Authoritys direction and shall agree an appropriate timetable for meeting its obligations.

GC.5 COMMUNICATION BETWEEN NGET AND USERS


GC.5.1 Unless otherwise specified in the Grid Code, all instructions given by NGET and
communications (other than relating to the submission of data and notices) between NGET and
Users (other than Generators, DC Converter Station owners or Suppliers) shall take place
between the NGET Control Engineer based at the Transmission Control Centre notified by
NGET to each User prior to connection, and the relevant User Responsible
Engineer/Operator, who, in the case of a Network Operator, will be based at the Control
Centre notified by the Network Operator to NGET prior to connection.
GC.5.2 Unless otherwise specified in the Grid Code all instructions given by NGET and communications
(other than relating to the submission of data and notices) between NGET and Generators
and/or DC Converter Station owners and/or Suppliers shall take place between the NGET
Control Engineer based at the Transmission Control Centre notified by NGET to each
Generator or DC Converter Station owner prior to connection, or to each Supplier prior to
submission of BM Unit Data, and either the relevant Generator's or DC Converter Station
owners or Suppliers Trading Point (if it has established one) notified to NGET or the Control
Point of the Supplier or the Generator's Power Station or DC Converter Station, as specified
in each relevant section of the Grid Code. In the absence of notification to the contrary, the
Control Point of a Generators Power Station will be deemed to be the Power Station at
which the Generating Units or Power Park Modules are situated.
GC.5.3 Unless otherwise specified in the Grid Code, all instructions given by NGET and
communications (other than relating to the submission of data and notices) between NGET and
Users will be given by means of the Control Telephony referred to in CC.6.5.2.
GC.5.4 If the Transmission Control Centre notified by NGET to each User prior to connection, or the
User Control Centre, notified in the case of a Network Operator to NGET prior to connection,
is moved to another location, whether due to an emergency or for any other reason, NGET shall
notify the relevant User or the User shall notify NGET, as the case may be, of the new location
and any changes to the Control Telephony or System Telephony necessitated by such move,
as soon as practicable following the move.
GC.5.5 If any Trading Point notified to NGET by a Generator or DC Converter Station owner prior to
connection, or by a Supplier prior to submission of BM Unit Data, is moved to another location
or is shut down, the Generator, DC Converter Station owner or Supplier shall immediately
notify NGET.
GC.5.6 The recording (by whatever means) of instructions or communications given by means of
Control Telephony or System Telephony will be accepted by NGET and Users as evidence of
those instructions or communications.

GC.6 MISCELLANEOUS
GC.6.1 Data and Notices

Issue 5 Revision 16 GC 24 May 2016


4 of 17
GC.6.1.1 Data and notices to be submitted either to NGET or to Users under the Grid Code (other than
data which is the subject of a specific requirement of the Grid Code as to the manner of its
delivery) shall be delivered in writing either by hand or sent by first-class pre-paid post, or by
facsimile transfer or by electronic mail to a specified address or addresses previously supplied by
NGET or the User (as the case may be) for the purposes of submitting that data or those
notices.
GC.6.1.2 References in the Grid Code to in writing or written include typewriting, printing, lithography,
and other modes of reproducing words in a legible and non-transitory form and in relation to
submission of data and notices includes electronic communications.
GC.6.1.3 Data delivered pursuant to paragraph GC.6.1.1, in the case of data being submitted to NGET,
shall be addressed to the Transmission Control Centre at the address notified by NGET to
each User prior to connection, or to such other Department within NGET or address, as NGET
may notify each User from time to time, and in the case of notices to be submitted to Users,
shall be addressed to the chief executive of the addressee (or such other person as may be
notified by the User in writing to NGET from time to time) at its address(es) notified by each User
to NGET in writing from time to time for the submission of data and service of notices under the
Grid Code (or failing which to the registered or principal office of the addressee).
GC.6.1.4 All data items, where applicable, will be referenced to nominal voltage and Frequency unless
otherwise stated.

GC.7 OWNERSHIP OF PLANT AND/OR APPARATUS


References in the Grid Code to Plant and/or Apparatus of a User include Plant and/or
Apparatus used by a User under any agreement with a third party.

GC.8 SYSTEM CONTROL


Where a User's System (or part thereof) is, by agreement, under the control of NGET, then for
the purposes of communication and co-ordination in operational timescales NGET can (for those
purposes only) treat that User's System (or part thereof) as part of the National Electricity
Transmission System, but, as between NGET and Users, it shall remain to be treated as the
User's System (or part thereof).

GC.9 EMERGENCY SITUATIONS


Users should note that the provisions of the Grid Code may be suspended, in whole or in part,
during a Security Period, as more particularly provided in the Fuel Security Code, or pursuant to
any directions given and/or orders made by the Secretary of State under section 96 of the Act
or under the Energy Act 1976.

GC.10 MATTERS TO BE AGREED


Save where expressly stated in the Grid Code to the contrary where any matter is left to NGET
and Users to agree and there is a failure so to agree the matter shall not without the consent of
both NGET and Users be referred to arbitration pursuant to the rules of the Electricity Supply
Industry Arbitration Association.

GC.11 GOVERNANCE OF ELECTRICAL STANDARDS


GC.11.1 In relation to the Electrical Standards the following provisions shall apply.
GC.11.2 (a) If a User, or in respect of (a) or (b) to the annex, NGET, or in respect of (c) or (d) to the
annex, the Relevant Transmission Licensee, wishes to:-
(i) raise a change to an Electrical Standard;

Issue 5 Revision 16 GC 24 May 2016


5 of 17
(ii) add a new standard to the list of Electrical Standards;
(iii) delete a standard from being an Electrical Standard,
it shall activate the Electrical Standards procedure.
(b) The Electrical Standards procedure is the notification to the secretary to the Panel of the
wish to so change, add or delete an Electrical Standard. That notification must contain
details of the proposal, including an explanation of why the proposal is being made.
GC.11.3 Ordinary Electrical Standards Procedure
(a) Unless it is identified as an urgent Electrical Standards proposal (in which case GC.11.4
applies) or unless the notifier requests that it be tabled at the next Panel meeting, as soon
as reasonably practicable following receipt of the notification, the Panel secretary shall
forward the proposal, with a covering paper, to Panel members.
(b) If no objections are raised within 20 Business Days of the date of the proposal, then it shall
be deemed approved pursuant to the Electrical Standards procedure, and NGET shall
make the change to the relevant Electrical Standard or the list of Electrical Standards
contained in the Annex to this GC.11.
(c) If there is an objection (or if the notifier had requested that it be tabled at the next Panel
meeting rather than being dealt with in writing), then the proposal will be included in the
agenda for the next following Panel meeting.
(d) If there is broad consensus at the Panel meeting in favour of the proposal, NGET will make
the change to the Electrical Standard or the list of Electrical Standards contained in the
Annex to this GC.11.
(e) If there is no such broad consensus, including where the Panel believes that further
consultation is needed, NGET will establish a Panel working group if this was thought
appropriate and in any event NGET shall undertake a consultation of Authorised
Electricity Operators liable to be materially affected by the proposal.
(f) Following such consultation, NGET will report back to Panel members, either in writing or at
a Panel meeting. If there was broad consensus in the consultation, then NGET will make
the change to the Electrical Standard or the list of Electrical Standards contained in the
Annex to this GC.11.
(g) Where following such consultation there is no broad consensus, the matter will be referred
to the Authority who will decide whether the proposal should be implemented and will notify
NGET of its decision. If the decision is to so implement the change, NGET will make the
change to the Electrical Standard or the list of Electrical Standards contained in the
Annex to this GC.11.
(h) In all cases where a change is made to the list of Electrical Standards, NGET will publish
and circulate a replacement page for the Annex to this GC covering that list and reflecting
the change.
GC.11.4 Urgent Electrical Standards Procedure
(a) If the notification is marked as an urgent Electrical Standards proposal, the Panel
secretary will contact Panel members in writing to see whether a majority who are
contactable agree that it is urgent and in that notification the secretary shall propose a
timetable and procedure which shall be followed.
(b) If such members do so agree, then the secretary will initiate the procedure accordingly,
having first obtained the approval of the Authority.
(c) If such members do not so agree, or if the Authority declines to approve the proposal
being treated as an urgent one, the proposal will follow the ordinary Electrical Standards
procedure as set out in GC.11.3 above.

Issue 5 Revision 16 GC 24 May 2016


6 of 17
(d) If a proposal is implemented using the urgent Electrical Standards procedure, NGET
will contact all Panel members after it is so implemented to check whether they wish to
discuss further the implemented proposal to see whether an additional proposal should be
considered to alter the implementation, such proposal following the ordinary Electrical
Standards procedure.

Issue 5 Revision 16 GC 24 May 2016


7 of 17
GC.12 CONFIDENTIALITY
GC.12.1 Users should note that although the Grid Code contains in certain sections specific provisions
which relate to confidentiality, the confidentiality provisions set out in the CUSC apply generally to
information and other data supplied as a requirement of or otherwise under the Grid Code. To
the extent required to facilitate the requirements of the EMR Documents, Users that are party to
the Grid Code but are not party to the CUSC Framework Agreement agree that the
confidentiality provisions of the CUSC are deemed to be imported into the Grid Code.
GC.12.2 NGET has obligations under the STC to inform Relevant Transmission Licensees of certain
data. NGET may pass on User data to a Relevant Transmission Licensee where:
(a) NGET is required to do so under a provision of Schedule 3 of the STC; and/or
(b) permitted in accordance with PC.3.4, PC.3.5 and OC2.3.2.

GC.12.3 NGET has obligations under the EMR Documents to inform EMR Administrative
Parties of certain data. NGET may pass on User data to an EMR Administrative Party
where NGET is required to do so under an EMR Document.

GC.12.4 NGET may use User data for the purpose of carrying out its EMR Functions.

GC.13 RELEVANT TRANSMISSION LICENSEES


GC.13.1 It is recognised that the Relevant Transmission Licensees are not parties to the Grid Code.
Accordingly, notwithstanding that Operating Code No. 8 Appendix 1 (OC8A) and Appendix 2
("OC8B"), OC7.6, OC9.4 and OC9.5 refer to obligations which will in practice be performed by
the Relevant Transmission Licensees in accordance with relevant obligations under the STC,
for the avoidance of doubt all contractual rights and obligations arising under OC8A, OC8B,
OC7.6, OC9.4 and OC9.5 shall exist between NGET and the relevant User and in relation to any
enforcement of those rights and obligations OC8A, OC8B, OC7.6, OC9.4 and OC9.5 shall be so
read and construed. The Relevant Transmission Licensees shall enjoy no enforceable rights
under OC8A, OC8B, OC7.6, OC9.4 and OC9.5 nor shall they be liable (other than pursuant to
the STC) for failing to discharge any obligations under OC8A, OC8B, OC7.6, OC9.4 and OC9.5.
GC.13.2 For the avoidance of doubt nothing in this Grid Code confers on any Relevant Transmission
Licensee any rights, powers or benefits for the purpose of the Contracts (Rights of Third Parties)
Act 1999.

GC.14 BETTA TRANSITION ISSUES


GC.14.1 The provisions of the Appendix to the General Conditions apply in relation to issues arising out
of the transition associated with the designation of GC Modification Proposals by the
Secretary of State in accordance with the provisions of the Energy Act 2004 for the purposes of
Condition C14 of NGETs Transmission Licence.

GC.15 EMBEDDED EXEMPTABLE LARGE AND MEDIUM POWER STATIONS


st
GC.15.1 This GC.15.1 shall have an effect until and including 31 March 2007.
(i) CC.6.3.2, CC.6.3.7, CC.8.1 and BC3.5.1; and
(ii) Planning Code obligations and other Connection Conditions; shall apply to a User who
owns or operates an Embedded Exemptable Large Power Station, or a Network
Operator in respect of an Embedded Exemptable Medium Power Station, except where
and to the extent that, in respect of that Embedded Exemptable Large Power Station or
Embedded Exemptable Medium Power Station, NGET agrees or where the relevant
User and NGET fail to agree, where and to the extent that the Authority consents.

Issue 5 Revision 16 GC 24 May 2016


8 of 17
GC.16 SIGNIFICANT CODE REVIEW
GC.16.1 A Significant Code Review is a code review process initiated and led by the Authority, on one
of a number of potential triggers. The Authority will launch a Significant Code Review on
publication of a notice setting out matters such as the scope of the review, reasons for it and
announcing the start date.
GC16.2 A Significant Code Review Phase begins on the start date set out in the Authoritys notice,
during which time any GC Modification Proposals that relate to the subject matter of the review
are restricted, to ensure the process is as efficient as possible. Once the Authority has
published its Significant Code Review conclusions, the Authority may direct NGET to raise a
GC Modification Proposal to put into effect the results of the Significant Code Review.
GC16.3 Where a GC Modification Proposal is raised during a Significant Code Review Phase unless
exempted by the Authority NGET in consultation with the Panel shall assess whether the GC
Modification Proposal falls within the scope of a Significant Code Review and shall notify the
Authority of its assessment, its reasons for that assessment and any representations received
in relation to it as soon as practicable.
GC.16.4 The GC Modification Proposal shall proceed during a Significant Code Review Phase unless
directed otherwise by the Authority in accordance with the paragraphs below.
GC.16.5 The Authority may at any time direct that a GC Modification Proposal made during a
Significant Code Review Phase falls within the scope of a Significant Code Review and must
not be made during the Significant Code Review Phase. If so directed the GC Modification
Proposal will not proceed and it shall be withdrawn or suspended until the end of the Significant
Code Review Phase.
GC.16.6 A GC Modification Proposal that falls within the scope of a Significant Code Review may be
made where:
(i) the Authority so determines, having taken into account (among other things) the urgency of
the subject matter of the GC Modification Proposal; or
(ii) NGET makes the GC Modification Proposal pursuant to a direction from the Authority in
accordance with the provisions below.
GC.16.7 Where a direction in accordance with GC.16.5 has not been issued, NGET, in consultation with
the Panel may proceed with the GC Modification Proposal.
GC.16.8 Within twenty-eight (28) days after the Authority has published its Significant Code Review
conclusions, the Authority may issue to NGET directions, including directions to NGET to make
GC Modification Proposal(s). NGET shall comply with those directions. Where NGET makes a
GC Modification Proposal in accordance with the Authoritys directions, it shall proceed as a
normal GC Modification Proposal. Such Authority conclusions and directions shall not fetter
the voting rights of the Panel or any recommendation NGET makes in relation to any GC
Modification Proposal.
GC.16.9 NGET may not, without the prior consent of the Authority, withdraw a GC Modification
Proposal made pursuant to a direction issued by the Authority pursuant to GC.16.8.

Issue 5 Revision 16 GC 24 May 2016


9 of 17
ANNEX TO THE GENERAL CONDITIONS

The Electrical Standards are as follows:


(a) Electrical Standards applicable in England and Wales

The Relevant Electrical Standards Reference Issue Date


Document (RES)

nd
Parts 1 to 3 2.0 22 Jan 2015
Part 4 Specific Requirements
nd
1 Back-Up Protection Grading PS(T)044(RES) 2.0 22 Jan 2015
across NGET's and other
Network Operator Interfaces
th
2 Ratings and General TS 1 (RES) 1.0 9 Jan 2006
Requirements for Plant, Draft
Equipment, Apparatus and
Services for the National Grid
System and Connections Points
to it.
th
3 Substations TS 2.01 (RES) 1.0 9 Jan 2006
Draft
nd
4 Switchgear TS 2.02 (RES) 2.0 22 Jan 2015
nd
5 Substation Auxiliary Supplies TS 2.12 (RES) 2.0 22 Jan 2015
nd
6 Ancillary Light Current TS 2.19 (RES) 2.0 22 Jan 2015
Equipment
th
7 Substation Interlocking TS 3.01.01 (RES) 1.0 9 Jan 2006
Schemes Draft
nd
8 Earthing Requirements TS 3.01.02 (RES) 2.0 22 Jan 2015
nd
9 Circuit Breakers TS 3.02.01 (RES) 2.0 22 Jan 2015
nd
10 Disconnectors and Earthing TS 3.02.02 (RES) 2.0 22 Jan 2015
Switches
nd
11 Current Transformers for TS 3.02.04 (RES) 2.0 22 Jan 2015
Protection and General Use on
the 132kV, 275kV and 400kV
Systems
th
12 Voltage Transformers TS 3.02.05 (RES) 1.0 9 Jan 2006
Draft
nd
13 Bushings TS 3.02.07 (RES) 2.0 22 Jan 2015
nd
14 Solid Core Post Insulators for TS 3.02.09 (RES) 2.0 22 Jan 2015
Substations
th
15 Voltage Dividers TS 3.02.12 (RES) 1.0 9 Jan 2006
Draft
nd
16 Gas Insulated Switchgear TS 3.02.14 (RES) 2.0 22 Jan 2015
nd
17 Environmental and Test TS 3.24.15 (RES) 2.0 22 Jan 2015
Requirements for Electronic
Equipment
nd
18 Busbar Protection TS 3.24.34 (RES) 2.0 22 Jan 2015
nd
19 Circuit Breaker Fail Protection TS 3.24.39 (RES) 2.0 22 Jan 2015
nd
20 System Monitor Dynamic TS 3.24.70 (RES) 2.0 22 Jan 2015
System Monitoring (DSM)
nd
21 Protection & Control for HVDC TS 3.24.90 (RES) 2.0 22 Jan 2015
Systems
nd
22 Ancillary Services Business TS 3.24.95 (RES) 2.0 22 Jan 2015
Monitoring
nd
23 Guidance for Conductor Jointing TGN(E)187 (RES) 2.0 22 Jan 2015

Issue 5 Revision 16 GC 24 May 2016


10 of 17
in Substations
Additional Requirements
th
Control Telephony Electrical Standard 1.0 17 Sept 2007

(b) Electronic data communications facilities.

th
Communications Standards for Electronic Data Issue 4 26 Aug 2015
Communication Facilities and Automatic Logging
Devices

th
EDT Interface Specification Issue 4 18 Dec 2000

st
EDT Submitter Guidance Note Issue 1 21 Dec 2001

th
EDL Message Interface Specification Issue 4 20 Jun 2000

rd
EDL Instruction Interface Valid Reason Codes Issue 2 23 Jul 2001

th
MODIS Interface Specification Version 4 26 May 2015

(c) Scottish Electrical Standards for SPT's Transmission System.

SPTTS 1 Requirements for the SP Transmission System Issue 1


and Connection Points to it.

SPTTS 2.1 Substations Issue 1

SPTTS 2.2 Switchgear Issue 1

SPTTS 2.3 Transformers and Reactors Issue 1

SPTTS 2.5 Cables Issue 1

SPTTS 2.6 Protection Issue 1

SPTTS 2.7 Substation Control Systems Issue 1

SPTTS 2.12 Substation Auxiliary Supplies Issue 1

Issue 5 Revision 16 GC 24 May 2016


11 of 17
(d) Scottish Electrical Standards for SHETL's Transmission System.

1. NGTS 1: Rating and General Requirements for


Plant, Equipment, Apparatus and Services
for the National Grid System and Direct
Connection to it. Issue 3 March 1999.
2. NGTS 2.1: Substations
Issue 2 May 1995
3. NGTS 3.1.1: Substation Interlocking Schemes.
Issue 1 October 1993.
4. NGTS 3.2.1: Circuit Breakers and Switches.
Issue 1 September 1992.
5. NGTS 3.2.2: Disconnectors and Earthing Switches.
Issue 1 March 1994.
6. NGTS 3.2.3: Metal-Oxide surge arresters for use on
132, 275 and 400kV systems.
Issue 2 May 1994.
7. NGTS 3.2.4: Current Transformers for protection and
General use on the 132, 275 and 400kV
systems.
Issue 1 September 1992.
8. NGTS 3.2.5: Voltage Transformers for use on the 132,
275 and 400 kV systems.
Issue 2 March 1994.
9. NGTS 3.2.6: Current and Voltage Measurement
Transformers for Settlement Metering of
33, 66, 132, 275 and 400kV systems.
Issue 1 September 1992.
10. NGTS 3.2.7: Bushings for the Grid Systems.
Issue 1 September 1992.
11. NGTS 3.2.9: Post Insulators for Substations.
Issue 1 May 1996.
12. NGTS 2.6: Protection
Issue 2 June 1994.
13. NGTS 3.11.1: Capacitors and Capacitor Banks.
Issued 1 March 1993.

Issue 5 Revision 16 GC 24 May 2016


12 of 17
APPENDIX TO THE GENERAL CONDITIONS
GC.A.1 Introduction
GC.A.1.1 This Appendix to the General Conditions deals with issues arising out of the transition
associated with the designation of amendments to the Grid Code by the Secretary of State in
accordance with the provisions of the Energy Act 2004 for the purposes of Condition C14 of
NGETs Transmission Licence. For the purposes of this Appendix to the General Conditions,
the version of the Grid Code as amended by the changes designated by the Secretary of State
and as further amended from time to time shall be referred to as the GB Grid Code.
GC.A.1.2 The provisions of this Appendix to the General Conditions shall only apply to Users (as defined
in GC.A.1.4) and NGET after Go-Live for so long as is necessary for the transition requirements
referred to in GC.A.1.1 and cut-over requirements (as further detailed in GC.A.3.1) to be
undertaken.
GC.A.1.3 In this Appendix to the General Conditions:
(a) Existing E&W Users and E&W Applicants are referred to as E&W Users;
(b) Users who as at 1 January 2005 have entered into an agreement or have accepted an offer
for connection to and/or use of the Transmission System of NGET are referred to as
Existing E&W Users;
(c) Users (or prospective Users) other than Existing E&W Users who apply during the
Transition Period for connection to and/or use of the Transmission System of NGET are
referred to as E&W Applicants;
(d) Existing Scottish Users and Scottish Applicants are referred to as Scottish Users;
(e) Users who as at 1 January 2005 have entered into an agreement or have accepted an offer
for connection to and/or use of the Transmission System of either Relevant
Transmission Licensee are referred to as Existing Scottish Users;
(f) Users (or prospective Users) other than Existing Scottish Users who apply during the
Transition Period for connection to and/or use of the Transmission System of either
Relevant Transmission Licensee are referred to as Scottish Applicants;
(g) the term Transition Period means the period from Go-Active to Go-Live (unless it is
provided to be different in relation to a particular provision), and is the period with which this
Appendix to the General Conditions deals;
(h) the term Interim GB SYS means the document of that name referred to in Condition C11
of NGETs Transmission Licence;
(i) the term Go-Active means the date on which the amendments designated by the
Secretary of State to the Grid Code in accordance with the Energy Act 2004 come into
effect; and
(j) the term Go-Live means the date which the Secretary of State indicates in a direction
shall be the BETTA go-live date.
GC.A.1.4 The provisions of GC.2.1 shall not apply in respect of this Appendix to the General Conditions,
and in this Appendix to the General Conditions the term Users means:
(a) Generators;
(b) Network Operators;
(c) Non-Embedded Customers;
(d) Suppliers;
(e) BM Participants; and
(f) Externally Interconnected System Operators,
(g) DC Converter Station owners
Issue 5 Revision 16 GC 24 May 2016
13 of 17
to the extent that the provisions of this Appendix to the General Conditions affect the rights and
obligations of such Users under the other provisions of the GB Grid Code.
GC.A.1.5 The GB Grid Code has been introduced with effect from Go-Active pursuant to the relevant
licence changes introduced into NGETs Transmission Licence. NGET is required to
implement and comply, and Users to comply, with the GB Grid Code subject as provided in this
Appendix to the General Conditions, which provides for the extent to which the GB Grid Code
is to apply to NGET and Users during the Transition Period.
GC.A.1.6 This Appendix to the General Conditions comprises:
(a) this Introduction;
(b) GB Grid Code transition issues; and
(c) Cut-over issues.
GC.A.1.7 Without prejudice to GC.A.1.8, the failure of any User or NGET to comply with this Appendix to
the General Conditions shall not invalidate or render ineffective any part of this Appendix to the
General Conditions or actions undertaken pursuant to this Appendix to the General
Conditions.
GC.A.1.8 A User or NGET shall not be in breach of any part of this Appendix to the General Conditions
to the extent that compliance with that part is beyond its power by reason of the fact that any
other User or NGET is in default of its obligations under this Appendix to the General
Conditions.
GC.A.1.9 Without prejudice to any specific provision under this Appendix to the General Conditions as to
the time within which or the manner in which a User or NGET should perform its obligations
under this Appendix to the General Conditions, where a User or NGET is required to take any
step or measure under this Appendix to the General Conditions, such requirement shall be
construed as including any obligation to:
(a) take such step or measure as quickly as reasonably practicable; and
(b) do such associated or ancillary things as may be necessary to complete such step or
measure as quickly as reasonably practicable.
GC.A.1.10 NGET shall use reasonable endeavours to identify any amendments it believes are needed to
the GB Grid Code in respect of the matters referred to for the purposes of Condition C14 of
NGETs Transmission Licence and in respect of the matters identified in GC.A.1.11, and,
having notified the Authority of its consultation plans in relation to such amendments, NGET
shall consult in accordance with the instructions of the Authority concerning such proposed
amendments.
GC.A.1.11 The following matters potentially require amendments to the GB Grid Code:
(a) The specific detail of the obligations needed to manage implementation in the period up to
and following (for a temporary period) Go-Live to achieve the change to operation under
the GB Grid Code (to be included in GC.A.3).
(b) Information (including data) and other requirements under the GB Grid Code applicable to
Scottish Users during the Transition Period (to be included in GC.A.2).
(c) The conclusions of Ofgem/DTI in relation to small and/or embedded generator issues under
BETTA and allocation of access rights on a GB basis.
(d) Any arrangements required to make provision for operational liaison, including Black Start
and islanding arrangements in Scotland.
(e) Any arrangements required to make provision for cascade hydro BM Units.
(f) Any consequential changes to the safety co-ordination arrangements resulting from STC
and STC procedure development.
(g) Any arrangements required to reflect the Electrical Standards for the Transmission
Systems of SPT and SHETL.

Issue 5 Revision 16 GC 24 May 2016


14 of 17
(h) The conclusions of Ofgem/DTI in relation to planning and operating standards.
GC.A.1.12 NGET shall notify the Authority of any amendments that NGET identifies as needed pursuant to
GC.A.1.10 and shall make such amendments as the Authority approves.
GC.A.2 GB Grid Code Transition
General Provisions
GC.A.2.1 The provisions of the GB Grid Code shall be varied or suspended (and the requirements of the
GB Grid Code shall be deemed to be satisfied) by or in accordance with, and for the period and
to the extent set out in this GC.A.2, and in accordance with the other applicable provisions in this
Appendix to the General Conditions.
GC.A.2.2 E&W Users:
In furtherance of the licence provisions referred to in GC.A.1.5, E&W Users shall comply with the
GB Grid Code during the Transition Period, but shall comply with and be subject to it subject to
this Appendix to the General Conditions, including on the basis that:
(a) during the Transition Period the Scottish Users are only complying with the GB Grid
Code in accordance with this Appendix to the General Conditions; and
(b) during the Transition Period the National Electricity Transmission System shall be
limited to the Transmission System of NGET, and all rights and obligations of E&W Users
in respect of the National Electricity Transmission System under the GB Grid Code
shall only apply in respect of the Transmission System of NGET, and all the provisions of
the GB Grid Code shall be construed accordingly.
GC.A.2.3 Scottish Users:
In furtherance of the licence provisions referred to in GC.A.1.5, Scottish Users shall comply with
the GB Grid Code and the GB Grid Code shall apply to or in relation to them during the
Transition Period only as provided in this Appendix to the General Conditions.
GC.A.2.4 NGET:
In furtherance of the licence provisions referred to in GC.A.1.5, NGET shall implement and
comply with the GB Grid Code during the Transition Period, but shall implement and comply
with and be subject to it subject to, and taking into account, all the provisions of this Appendix to
the General Conditions, including on the basis that:
(a) during the Transition Period NGETs rights and obligations in relation to E&W Users in
respect of the National Electricity Transmission System under the GB Grid Code shall
only apply in respect of the Transmission System of NGET, and all the provisions of the
GB Grid Code shall be construed accordingly; and
(b) during the Transition Period NGETs rights and obligations in relation to Scottish Users in
respect of the National Electricity Transmission System under the GB Grid Code shall
only be as provided in this Appendix to the General Conditions.
Specific Provisions
GC.A.2.5 Definitions:
The provisions of the GB Grid Code Glossary and Definitions shall apply to and for the
purposes of this Appendix to the General Conditions except where provided to the contrary in
this Appendix to the General Conditions.

GC.A.2.6 Identification of Documents:

Issue 5 Revision 16 GC 24 May 2016


15 of 17
In the period beginning at Go-Active, Scottish Users will work with NGET to identify and agree
with NGET any documents needed to be in place in accordance with the GB Grid Code, to apply
from Go-Live or as earlier provided for under this Appendix to the General Conditions,
including (without limitation) Site Responsibility Schedules, Gas Zone Diagrams and OC9
Desynchronised Island Procedures.
GC.A.2.7 Data:
Each Scottish User must provide, or enable a Relevant Transmission Licensee to provide,
NGET, as soon as reasonably practicable upon request, with all data which NGET needs in
order to implement, with effect from Go-Live, the GB Grid Code in relation to Scotland. This
data will include, without limitation, the data that a new User is required to submit to NGET under
CC.5.2. NGET is also entitled to receive data on Scottish Users over the Relevant
Transmission Licensees SCADA links to the extent that NGET needs it for use in testing and
in order to implement, with effect from Go-Live, the GB Grid Code in relation to Scotland. After
Go-Live such data shall, notwithstanding GC.A.1.2, be treated as though it had been provided to
NGET under the enduring provisions of the GB Grid Code.
GC.A.2.8 Verification of Data etc:
NGET shall be entitled to request from a Scottish User (which shall comply as soon as
reasonably practicable with such a request) confirmation and verification of any information
(including data) that has been received by a Relevant Transmission Licensee under an
existing grid code and passed on to NGET in respect of that Scottish User. After Go-Live such
information (including data) shall, notwithstanding GC.A.1.2, be treated as though provided to
NGET under the enduring provisions of the GB Grid Code.
GC.A.2.9 Grid Code Review Panel:
(a) The individuals whose names are notified to NGET by the Authority prior to Go-Active as Panel
members (and alternate members, if applicable) are agreed by Users (including Scottish
Users) and NGET to constitute the Panel members and alternate members of the Grid Code
Review Panel as at the first meeting of the Grid Code Review Panel after Go-Active as if they
had been appointed as Panel members (and alternate members) pursuant to the relevant
provisions of the Constitution and Rules of the Grid Code Review Panel incorporating
amendments equivalent to the amendments to GC.4.2 and GC.4.3 designated by the Secretary
of State in accordance with the provisions of the Energy Act 2004 for the purposes of Condition
C14 of NGETs Transmission Licence.
(b) The provisions of GC.4 of the GB Grid Code shall apply to, and in respect of, Scottish Users
from Go-Active.
GC.A.2.10 Interim GB SYS:
Where requirements are stated in, or in relation to, the GB Grid Code with reference to the
Seven Year Statement, they shall be read and construed as necessary as being with reference
to the Interim GB SYS.
GC.A.2.11 General Conditions:
The provisions of GC.4, GC.12 and GC.13.2 of the GB Grid Code shall apply to and be
complied with by Scottish Users in respect of this Appendix to the General Conditions.
GC.A.2.12 OC2 Data
(a) The following provisions of the GB Grid Code shall apply to and be complied with by
Scottish Users with effect from the relevant date indicated below:
(i) OC2.4.1.2.3 (a) from 19 January 2005 in respect of 2 to 52 week submissions,
(ii) OC2.4.1.2.4 (c) from 25 February 2005 in respect of 2 to 49 day submissions,
(iii) OC2.4.1.2.4 (b) from 22 March 2005 in respect of 2 to 14 day submissions,

The data to be submitted in respect of OC2.4.1.2.3 (a) and OC2.4.1.2.4 (b) and (c) need
only be in respect of dates on or after 1 April 2005.
Issue 5 Revision 16 GC 24 May 2016
16 of 17
GC.A.3 Cut-over
GC.A.3.1 It is anticipated that it will be appropriate for arrangements to be put in place for final transition to
BETTA in the period up to and following (for a temporary period) Go-Live, for the purposes of:
(a) managing the transition from operations under the Grid Code as in force immediately prior
to Go-Active to operations under the GB Grid Code and the BSC as in force on and after
Go-Active;
(b) managing the transition from operations under the existing grid code applicable to Scottish
Users as in force immediately prior to Go-Active to operations under the GB Grid Code as
in force on and after Go-Active;
(c) managing the transition of certain data from operations under the existing grid code
applicable to Scottish Users before and after Go-Active; and
(d) managing GB Grid Code systems, processes and procedures so that they operate
effectively at and from Go-Live.
GC.A.3.2 (a) The provisions of BC1 (excluding BC1.5.1, BC1.5.2 and BC1.5.3) shall apply to and be
complied with by Scottish Users and by NGET in respect of such Scottish Users with
effect from 11:00 hours on the day prior to Go-Live
(b) Notwithstanding (a) above, Scottish Users may submit data for Go-Live 3 days in advance
of Go-Live on the basis set out in the Data Validation, Consistency and Defaulting
Rules which shall apply to Scottish Users and NGET in respect of such Scottish Users
on that basis and for such purpose.
(c) The Operational Day for the purposes of any submissions by Scottish Users prior to Go-
Live under a) and b) above for the day of Go-Live shall be 00:00 hours on Go Live to
05:00 hours on the following day.
(d) The provisions of BC2 shall apply to and be complied with by Scottish Users and by NGET
in respect of such Scottish Users with effect from 23:00 hours on the day prior to Go-Live.
(e) The provisions of OC7.4.8 shall apply to and be complied with by Scottish Users and by
NGET in respect of such Scottish Users with effect from 11:00 hours on the day prior to
Go-Live.
(f) In order to facilitate cut-over, Scottish Users acknowledge and agree that NGET will
exchange data submitted by such Scottish Users under BC1 prior to Go-Live with the
Scottish system operators to the extent necessary to enable the cut-over.
(g) Except in the case of Reactive Power, Scottish Users should only provide Ancillary
Services from Go-Live where they have been instructed to do so by NGET. In the case of
Reactive Power, at Go-Live a Scottish Users MVAr output will be deemed to be the level
instructed by NGET under BC2, following this Scottish Users should operate in
accordance with BC2.A.2.6 on the basis that MVAr output will be allowed to vary with
system conditions.

< END OF GENERAL CONDITIONS >

Issue 5 Revision 16 GC 24 May 2016


17 of 17
REVISIONS
(R)

(This section does not form part of the Grid Code)

R.1 NGETs Transmission Licence sets out the way in which changes to the Grid Code are to be
made and reference is also made to NGET's obligations under the General Conditions.
R.2 All pages re-issued have the revision number on the lower left hand corner of the page and date
of the revision on the lower right hand corner of the page.
R.3 The Grid Code was introduced in March 1990 and the first issue was revised 31 times. In March
2001 the New Electricity Trading Arrangements were introduced and Issue 2 of the Grid Code
was introduced which was revised 16 times. At British Electricity Trading and Transmission
Arrangements (BETTA) Go-Active Issue 3 of the Grid Code was introduced and subsequently
revised 35 times. At Offshore Go-active Issue 4 of the Grid Code was introduced and has been
revised 13 times since its original publication. Issue 5 of the Grid Code was published to
accommodate the changes made by Grid Code Modification A/10 which has incorporated the
Generator compliance process into the Grid Code.
R.4 This Revisions section provides a summary of the sections of the Grid Code changed by each
revision to Issue 5.
R.5 All enquiries in relation to revisions to the Grid Code, including revisions to Issues 1, 2, 3, 4 and 5
should be addressed to the Grid Code development team at the following email address:
Grid.Code@nationalgrid.com

Issue 5 Revision 18 R 11 August 2016


1 of 12
Revision Section Related Effective Date
Modification

0 Glossary and Definitions A/10 and G/11 17 August 2012

0 Planning Code PC.2.1 G/11 17 August 2012

0 Planning Code PC.5.4 G/11 17 August 2012

0 Planning Code PC.8 G/11 17 August 2012

0 Planning Code PC.8.2 G/11 17 August 2012

0 Planning Code PC.A.1 G/11 17 August 2012

0 Planning Code PC.A.2 A/10 and G/11 17 August 2012

0 Planning Code PC.A.3 G/11 17 August 2012

0 Planning Code PC.A.5 A/10 and G/11 17 August 2012

0 Compliance Processes A/10 17 August 2012

0 Connection Conditions CC.1.1 A/10 17 August 2012

0 Connection Conditions CC.2.2 G/11 17 August 2012

0 Connection Conditions CC.3.3 A/10 17 August 2012

0 Connection Conditions CC.4.1 A/10 17 August 2012

0 Connection Conditions CC.5.2 G/11 17 August 2012

0 Connection Conditions CC.6.1 G/11 17 August 2012

0 Connection Conditions CC.6.3 G/11 17 August 2012

0 Connection Conditions CC.6.6 A/10 17 August 2012

0 Connection Conditions CC.7.2 G/11 17 August 2012

Issue 5 Revision 18 R 11 August 2016


2 of 12
Revision Section Related Effective Date
Modification

0 Connection Conditions CC.7.4 G/11 17 August 2012

0 Connection Conditions CC.A.1 G/11 17 August 2012

0 Connection Conditions CC.A.2 G/11 17 August 2012

0 Connection Conditions CC.A.3 G/11 17 August 2012

0 Connection Conditions CC.A.4 G/11 17 August 2012

0 Connection Conditions CC.A.6 A/10 17 August 2012

0 Connection Conditions CC.A.7 A/10 and G/11 17 August 2012

0 Connection Conditions Figure CC.A.3.1 G/11 17 August 2012

0 Operating Code No. 2 OC2.4 G/11 17 August 2012

0 Operating Code No. 2 OC2.A.1 G/11 17 August 2012

0 Operating Code No. 5 OC5.3 A/10 17 August 2012

0 Operating Code No. 5 OC5.5 A/10 and G/11 17 August 2012

0 Operating Code No. 5 OC5.7 G/11 17 August 2012

0 Operating Code No. 5 OC5.8 A/10 and G/11 17 August 2012

0 Operating Code No. 5 OC5.A.1 A/10 17 August 2012

0 Operating Code No. 5 OC5.A.2 A/10 17 August 2012

0 Operating Code No. 5 OC5.A.3 A/10 17 August 2012

0 Operating Code No. 5 OC5.A.4 A/10 17 August 2012

0 Operating Code No. 7 OC7.4 G/11 17 August 2012

0 Operating Code No. 8 OC8.2 G/11 17 August 2012

Issue 5 Revision 18 R 11 August 2016


3 of 12
Revision Section Related Effective Date
Modification

0 Operating Code No. 8 OC8A.1 G/11 17 August 2012

0 Operating Code No. 8 OC8A.5 G/11 17 August 2012

0 Operating Code No. 8 OC8B.1 G/11 17 August 2012

0 Operating Code No. 8 OC8B.4 G/11 17 August 2012

0 Operating Code No. 8 OC8B.5 G/11 17 August 2012

0 Operating Code No. 8 OC8B Appendix E G/11 17 August 2012

0 Operating Code No. 9 OC9.2 G/11 17 August 2012

0 Operating Code No. 9 OC9.4 G/11 17 August 2012

0 Operating Code No. 9 OC9.5 G/11 17 August 2012

0 Operating Code No. 12 OC12.3 G/11 17 August 2012

0 Operating Code No. 12 OC12.4 G/11 17 August 2012

0 Balancing Code No. 1 BC1.5 G/11 17 August 2012

0 Balancing Code No. 1 BC1.8 G/11 17 August 2012

0 Balancing Code No. 1 BC1.A.1 G/11 17 August 2012

0 Balancing Code No. 2 BC2.5 G/11 17 August 2012

0 Balancing Code No. 2 BC2.8 G/11 17 August 2012

0 Balancing Code No. 2 BC2.A.2 G/11 17 August 2012

0 Balancing Code No. 2 BC2.A.3 G/11 17 August 2012

0 Balancing Code No. 2 BC2.A.4 G/11 17 August 2012

0 Balancing Code No. 3 BC3.5 G/11 17 August 2012

Issue 5 Revision 18 R 11 August 2016


4 of 12
Revision Section Related Effective Date
Modification

0 Balancing Code No. 3 BC3.7 G/11 17 August 2012

0 Data Registration Code DRC.1.5 G/11 17 August 2012

0 Data Registration Code DRC.4.2 G/11 17 August 2012

0 Data Registration Code DRC.4.4 G/11 17 August 2012

0 Data Registration Code DRC.5.2 A/10 and G/11 17 August 2012

0 Data Registration Code DRC.5.5 G/11 17 August 2012

0 Data Registration Code DRC.6.1 A/10 and G/11 17 August 2012

0 Data Registration Code DRC.6.2 A/10 17 August 2012

0 Data Registration Code Schedule 1 A/10 and G/11 17 August 2012

0 Data Registration Code Schedule 2 G/11 17 August 2012

0 Data Registration Code Schedule 3 G/11 17 August 2012

0 Data Registration Code Schedule 4 G/11 17 August 2012

0 Data Registration Code Schedule 5 G/11 17 August 2012

0 Data Registration Code Schedule 10 G/11 17 August 2012

0 Data Registration Code Schedule 12A G/11 17 August 2012

0 Data Registration Code Schedule 14 A/10 and G/11 17 August 2012

0 Data Registration Code Schedule 15 G/11 17 August 2012

0 Data Registration Code Schedule 19 A/10 17 August 2012

0 General Conditions GC.4 G/11 17 August 2012

0 General Conditions GC.12 G/11 17 August 2012

Issue 5 Revision 18 R 11 August 2016


5 of 12
Revision Section Related Effective Date
Modification

0 General Conditions GC.15 G/11 17 August 2012

0 General Conditions GC.A1 G/11 17 August 2012

0 General Conditions GC.A2 G/11 17 August 2012

0 General Conditions GC.A3 G/11 17 August 2012

1 Operating Code No. 8 OC8A.5.3.4 C/12 6 November 2012

1 Operating Code No. 8 OC8B.5.3.4 C/12 6 November 2012

2 Balancing Code No. 1 BC1.2.1 B/12 31 January 2013

2 Balancing Code No. 1 BC1.4.2 B/12 31 January 2013

2 Balancing Code No. 1 BC1.A.1.5 B/12 31 January 2013

2 Connection Conditions CC.7.7 D/12 31 January 2013

3 Glossary and Definitions C/11 2 April 2013

3 Operating Code No. 8 OC8A.4.3.5 B/10 2 April 2013

3 Operating Code No. 8 OC8B.4.3.5 B/10 2 April 2013

3 Balancing Code No. 2 BC2.5 C/11 2 April 2013

4 Glossary and Definitions GC0060 (F/12) 19 August 2013

4 Planning Code PC.A.5 GC0040 (A/12) 19 August 2013

4 Operating Code No. 2 OC2.A.10 GC0060 (F/12) 19 August 2013

4 Data Registration Code Schedule 1 GC0040 (A/12) 19 August 2013

4 Data Registration Code Schedule 2 GC0060 (F/12) 19 August 2013

Issue 5 Revision 18 R 11 August 2016


6 of 12
Revision Section Related Effective Date
Modification

5 Glossary and Definitions GC0033, 71, 72 05 November 2013


and 73

5 General Conditions GC.4 GC0071, 72 and 05 November 2013


73

5 General Conditions GC.14 GC0071, 72 and 05 November 2013


73

5 General Conditions GC.16 GC0071, 72 and 05 November 2013


73

6 Connection Conditions CC.A.7 GC0065 13 December


2013

6 Planning Code PC.A.3 GC0037 13 December


2013

6 Operating Code No. 2 OC2.4.2 GC0037 13 December


2013

6 Operating Code No. 2 Appendix 4 GC0037 13 December


2013

6 Balancing Code No. 1 BC1.4.2 GC0037 13 December


2013

6 Balancing Code No. 1 BC1.A.1.8 GC0037 13 December


2013

7 Glossary and Definitions GC0044 31 March 2014

7 Operating Code No. 9 OC9.2.5 GC0044 31 March 2014

7 Operating Code No. 9 OC9.4.6 GC0044 31 March 2014

7 Operating Code No. 9 OC9.4.7.4 GC0044 31 March 2014

7 Operating Code No. 9 OC9.4.7.9 GC0044 31 March 2014

7 Operating Code No. 9 OC9.4.7.10 GC0044 31 March 2014

Issue 5 Revision 18 R 11 August 2016


7 of 12
Revision Section Related Effective Date
Modification

7 Balancing Code No. 2 BC2.9.2.2 GC0044 31 March 2014

8 Glossary and Definitions Secretary of State 10 June 2014


direction
Generator
Commissioning
Clause

Secretary of State
8 Planning Code 10 June 2014
direction
Generator
Commissioning
Clause

Secretary of State
8 Connection Conditions 10 June 2014
direction
Generator
Commissioning
Clause

Secretary of State
8 Compliance Processes 10 June 2014
direction
Generator
Commissioning
Clause

Secretary of State
8 Operating Code No. 5 10 June 2014
direction
Generator
Commissioning
Clause

Secretary of State
8 Operating Code No. 7 10 June 2014
direction
Generator
Commissioning
Clause

Secretary of State
8 Operating Code No. 8 10 June 2014
direction
Generator
Commissioning
Clause

Secretary of State
8 Operating Code No. 8A 10 June 2014
direction
Generator
Commissioning
Clause

Secretary of State
8 Operating Code No. 8B 10 June 2014
direction
Generator
Commissioning
Clause
Issue 5 Revision 18 R 11 August 2016
8 of 12
Revision Section Related Effective Date
Modification

Secretary of State
8 Balancing Code No. 2 10 June 2014
direction
Generator
Commissioning
Clause

9 Operating Code No. 6 OC6.5 GC0050 01 July 2014

9 Operating Code No. 6 OC6.7 GC0050 01 July 2014

9 Balancing Code No. 2 Appendix 3 GC0068 01 July 2014


Annexures

9 Balancing Code No. 2 Appendix 4 GC0068 01 July 2014


Annexure

10 Glossary and Definitions Secretary of State 01 August 2014


direction EMR

10 Planning Code PC.5.4 Secretary of State 01 August 2014


direction EMR

10 Planning Code PC.5.6 Secretary of State 01 August 2014


direction EMR

10 General Conditions GC.4.6 Secretary of State 01 August 2014


direction EMR

10 General Conditions GC.12 Secretary of State 01 August 2014


direction EMR

11 Planning Code PC.A.3.1.4 GC0042 21 August 2014

11 Planning Code PC.A.5 GC0042 21 August 2014

11 Data Registration Code DRC6.1.11 GC0042 21 August 2014

11 Data Registration Code Schedule 11 GC0042 21 August 2014

12 Glossary and Definitions GC0083 01 November 2014

12 Planning Code PC.A.3.4.3 GC0083 01 November 2014

Issue 5 Revision 18 R 11 August 2016


9 of 12
Revision Section Related Effective Date
Modification

12 Planning Code PC.D.1 GC0052 01 November 2014

12 Operating Code No. 2 OC2.4.2.3 GC0083 01 November 2014

12 Operating Code No. 2 OC2.4.7 GC0083 01 November 2014

12 Operating Code No. 6 OC6.1.5 GC0061 01 November 2014

12 Data Registration Code Schedule 1 GC0052 01 November 2014

12 Data Registration Code Schedule 2 GC0052 01 November 2014

12 Data Registration Code Schedule 6 GC0083 01 November 2014

13 Glossary and Definitions GC0063 22 January 2015

13 Connection Conditions CC.6.5.6 GC0063 22 January 2015

13 Balancing Code No. 1 BC1.A.1.3.1 GC0063 22 January 2015

13 General Conditions Annex to General GC0080 22 January 2015


Conditions

14 Connection Conditions - CC6.1.7 GC0076 26 August 2015

15 Glossary and Definitions GC0023 03 February 2016

15 Connection Conditions - CC6.2.2 GC0023 03 February 2016

15 Connection Conditions - CC6.2.3 GC0023 03 February 2016

15 Planning Code - PC.A.5.3.2 GC0028 03 February 2016

15 Connection Conditions - CC 6.3.2 GC0028 03 February 2016

15 Connection Conditions - CC 6.3.8 GC0028 03 February 2016

15 Compliance Processes CP.A.3.3.2 GC0028 03 February 2016

Issue 5 Revision 18 R 11 August 2016


10 of 12
Revision Section Related Effective Date
Modification

15 Compliance Processes CP.A.3.3.3 & 4 GC0028 03 February 2016

15 Operating Code No. 2 OC2.4.2.1 GC0028 03 February 2016

15 Operating Code No. 5 - OC5.A.2.7.5 GC0028 03 February 2016

15 Balancing Code No. 2 BC2.A.2.6 GC0028 03 February 2016

15 Data Registration Code Schedule 1 GC0028 03 February 2016

15 Connection Conditions - CC.6.1.5 GC0088 03 February 2016

15 Connection Conditions - CC.6.1.6 GC0088 03 February 2016

16 Connections Conditions - CC.6.3.15.1 GC0075 24 May 2016

16 Connections Conditions - CC.6.3.15.2 GC0075 24 May 2016

16 Connections Conditions - CC.A.7.2.3.1 GC0075 24 May 2016

16 Connections Conditions - CC.A.7.2.3.2 GC0075 24 May 2016

16 Operating Code No. 9 OC9.4.7.9 Communications/ 24 May 2016


Interface
Standards

16 General Condition - Annex to General Communications/ 24 May 2016


Conditions Interface
Standards

16 Glossary and Definitions Cluster removed Housekeeping 24 May 2016


change - error
resulting from
Issue 3 Revision
10

16 Glossary and Definitions Maximum Import Housekeeping 24 May 2016


Capacity amended change
duplicate definition

17 Connections Conditions - CC.6.3.15.1 GC0062 29 June 2016

Issue 5 Revision 18 R 11 August 2016


11 of 12
Revision Section Related Effective Date
Modification

17 Connections Conditions - CC.6.3.15.2 GC0062 29 June 2016

17 Connections Conditions Appendix 4 GC0062 29 June 2016

18 Operating Code No. 2 OC2.4.1.3 GC0092 11 August 2016

19 Glossary and Definitions Inadequate System GC0093 30 September


Margin amended 2016

19 Operating Conditions OC7.4.8.4 GC0093 30 September


2016

19 Operating Conditions OC7.4.8.5 GC0093 30 September


2016

19 Operating Conditions OC7.4.8.6 GC0093 30 September


2016

19 Operating Conditions OC7.4.8.6.1 GC0093 30 September


2016

19 Operating Conditions OC7.4.8.10 GC0093 30 September


2016

19 Operating Conditions Appendix 1 GC0093 30 September


2016

19 Balancing Conditions BC1.5.4 GC0093 30 September


2016

19 Balancing Conditions BC2.4.2 GC0093 30 September


2016

< END OF REVISIONS>

Issue 5 Revision 18 R 11 August 2016


12 of 12

Das könnte Ihnen auch gefallen