Sie sind auf Seite 1von 52

TALPAC 8 TUTORIALS

Workshops
Metric
TALPAC 8 TUTORIAL

Table of Contents

INTRODUCTION ............................................................................................................................................1

BACKGROUND TO WORKED EXAMPLE ...............................................................................................3

1. TALPAC OVERVIEW..........................................................................................................................4

2. THE MATERIAL TYPE.....................................................................................................................11

3. THE SHIFT ROSTER........................................................................................................................13

4. SELECTING A LOADER ..................................................................................................................15

5. SELECTING A TRUCK ....................................................................................................................18

6. SETTING-UP A HAUL CYCLE ........................................................................................................22

7. PRODUCTION ANALYSIS ...............................................................................................................25

8. INCREMENTAL ANALYSIS AND RESULTS TABLES.....................................................................26

9. FLEET SIZE OPTIMISATION..........................................................................................................31

10.FLEET COMPARISON.....................................................................................................................33

11.THE EQUIPMENT DATABASE .......................................................................................................35

12.IMPORTING A HAUL CYCLE .........................................................................................................37

13.TALPAC OPTIONS...........................................................................................................................39

ANSWERS ......................................................................................................................................................41

TALPAC COMMANDS ................................................................................................................................49

Runge Pty Ltd Table of Contents ( i )


Revision Draft
TALPAC 8 TUTORIAL

Introduction
This tutorial has been written so that users learn how to use TALPAC. The intention is
that by following the series of workshops set out in this booklet, you will be able to use
TALPAC, and have an appreciation as to the functionality of the program.

Each of the workshops sets out a number of key TALPAC concepts, what actually needs
to be completed for each workshop and what the results should be at various points. As
well, there are questions that should be answered for each workshop. Some of these
questions are qualitative, so no numerical answer has been provided. The phrases listed as
concepts in each workshop can all be found in the on-line help.

In the answers chapter of this booklet there are some answers to specific questions, and
screen captures at certain points of the process which will enable you to check your
progress. Often these screen captures contain the numeric answer.

This tutorial does not cover every feature of TALPAC. However upon completion of this
tutorial the user will have the skills required to successfully use TALPAC, and to self-learn
the TALPAC facilities not covered here.

Firstly it is recommended that you read through an entire workshop before starting it.

TALPAC may be used to analyse the performance of existing fleets of equipment or to


investigate the application of new equipment fleets in earthmoving and mining operations.
In either case, the performance of a single fleet may be examined, or a comparison made of
two or more different fleets. Typical TALPAC applications are listed below.

Calculation of truck travel time to allow a comparative analysis of haul route


alternatives.

Estimation of fleet productivities for use in long and short term planning studies.

Estimation and comparison of productivities using various loading


methodologies to determine the optimum loading technique or loading unit bucket
size.

Sensitivity analysis in road design criteria to assess the relative importance of road
maintenance.

Runge Pty Ltd Page 1


March, 2002
TALPAC 8 TUTORIAL

Calculation of tyre TKPH or TMPH ratings for use in tyre selection.

Estimation of fuel usage.

Determination (using discounted cash flow methods) of haulage contract costs and
pricing.

Truck fleet size optimisation to quantify the effect of over and under trucking.

Incremental analyses, in which simulations can be automatically run for a range


of haulage segment lengths and the results used to generate productivity curves.

Equipment loading analysis to optimise loader bucket size, truck capacity and
number of passes.

Collation of results from calculations to examine the relationship between


variables in the calculation, eg. haul distance versus productivity, haul distance
versus truck fleet size.

Runge Pty Ltd Page 2


March, 2002
TALPAC 8 TUTORIAL

Background To Worked
Example
A contractor has been invited to submit a tender for the removal of waste from an open-
cut mine, at 2.5 million BCM per year. The contractor utilises the following equipment:

Caterpillar 992G Front End Loaders (13.68 tonne payload); and

Komatsu HD785-5 Rear Dump Trucks (99.0 tonne payload).

In bidding for the waste removal contract, the contractor must determine how many trucks
and loaders are required to meet the production target and the cost of production. The
contractor is also unsure whether to continue with the same equipment or upgrade to
larger equipment.

In the workshops of this tutorial we will configure the required TALPAC components so
that this analysis can be undertaken.

Runge Pty Ltd Page 3


March, 2002
TALPAC 8 TUTORIAL

1. TALPAC OVERVIEW

Key Concepts: Project, Haulage System, Template

Technical Description
This workshop is to generally discuss how TALPAC works and what the key areas of data input and
out put are.

The figure below shows how a Haulage System is made up of the unique combination of nominated
templates. The templates are where the data is held for the Material, Roster, Loader, Truck and Haul
Cycle. So, if you change data in one of the templates, then really you are simulating a different haulage
system. In this way many Haul Systems can be stored in the one project.

MATERIAL
TYPES

SHIFT
ROSTERS

HAULAGE
LOADER
SYSTEMS TEMPLATES

TRUCK
TEMPLATES

HAUL
CYCLES

TALPAC Data Structure

To set up a haulage system for the waste contract project, you will need to create a new haulage system,
in a new TALPAC project. Initially we need to learn how to work with the templates. In later
workshops we will begin entering data into these templates.

Runge Pty Ltd Page 4


March, 2002
TALPAC 8 TUTORIAL

Tasks

Start up TALPAC. Do this via Start|Programs|Runge Software|TALPAC8 or by double


clicking on the TALPAC icon on your desktop.

In the opening dialogue click on the Create a New Project radio button and then click on the
OK button.

In the Create a New Project screen choose to Create An Empty Project and OK.

Runge Pty Ltd Page 5


March, 2002
TALPAC 8 TUTORIAL

In the file name box type: Waste Haulage Tutorial and open the file in your working directory. Click
on Yes when asked to create a new project.

The Set Print Titles dialogue box will then be opened. It is important to enter report titles for
your TALPAC project. These titles are entered from the File|Set Print Header, and will appear
on all TALPAC output. Normally you would enter appropriate project titles, in this instance
please enter the following:

Runge Pty Ltd Page 6


March, 2002
TALPAC 8 TUTORIAL

In this way you will be able to see what titles are user definable in TALPAC, and which titles are
fixed format.

Identify the five components of the haulage system. In the following workshops you will learn
how to set up each of these components to represent a haulage situation.

Open the AllParameters sheet and it will show:


Technical, Stochastic and Costing information for the loader and truck;

Roster and Material information;

Cash flow options; and

Loading options and Bucket construction options.

Runge Pty Ltd Page 7


March, 2002
TALPAC 8 TUTORIAL

Open the Loading Analysis sheet and you will get information on material, truck and loader.

Runge Pty Ltd Page 8


March, 2002
TALPAC 8 TUTORIAL

From the Main screen the material, roster, loader and truck templates may be edited. First click
with the left mouse on one of the list boxes to get a selection list.

To edit one of the templates click on the relevant Edit button. After editing you can either click
on OK to save or Cancel to return to the Main screen.

Note: Make sure you understand the difference between adding a new template to a list, and
editing an existing template.

Click on the Edit Haul Cycle button to open the Haul Cycle window. First, left mouse click on
the Haul Cycle button to get a selection list of haul cycles in this project. Then click on any
segment of the haul cycle and use either the cursor keys or the mouse to move around the haul
cycle. Then right click and you can add, edit or delete segments from the haul cycle. Note the
automatic segments. Close the Haul Cycle window.

Click in the Haulage System drop down box so that Haulage System-1 is highlighted. Right click
with the mouse on the highlighted name and choose Edit. Rename the haulage system to Basic

Runge Pty Ltd Page 9


March, 2002
TALPAC 8 TUTORIAL

Waste Contract. Now click on the lower portion of the screen so that the haulage system name is
no longer highlighted, and then press the Save button on the toolbar.

Questions
1. What is in a TP7 file?

2. What are the 5 components of a haulage system?

3. What is a TALPAC project?

4. Why would you want to print out the ALL PARAMETERS sheet?

5. What are the options available on the right click of the mouse when a template name is highlighted?

6. What types of Haul Segments can be used?

7. What is the difference between adding to a template list, and editing a template?

Runge Pty Ltd Page 10


March, 2002
TALPAC 8 TUTORIAL

2. THE MATERIAL TYPE

Key Concepts: Density, Swell, Fill Factor, Production Measurement

Technical Description
In this workshop, the characteristics of the material being hauled by the contractor will be entered into
a template. The characteristics of the waste are described below.

The productivity results are to be reported by volume rather than weight. Since we are working in
metric units, this will mean that productivities are expressed as bcm/op.hour, bcm/shift and bcm/year.

The insitu bank density is the density of the material while it is in the ground. This parameter is used to
convert an insitu bank volume to its equivalent weight, and vice versa.

The material swell factors are used to convert bank volumes to loose volumes in the loader bucket and
the truck tray. Note that both swell factors are based on insitu volume.

The loader bucket fill factor is dependent on both the material type and the class of loader. It is the
ratio of the loose volume of the material in the loader bucket to the volumetric rated capacity of the
loader bucket. The volumetric rated capacity of the loader bucket may be expressed on either a struck
or heaped basis.

Similarly, the loader bucket fill factor may be expressed on a struck or a heaped basis. The fill factor is
selected from a scale in the material template.

Tasks

Create a new material template for the waste that the contractor is to haul. Click in the Material
Template drop down box and then either right mouse click and choose Add off the menu or click
on the Add button on the toolbar. Call the new template Tutorial Waste.

The waste has an insitu bank density of 2.2 tonnes/cu.metre.

The swell factors for the waste the contractor is to move are as follows:

Swell Factor - Bank to Loader Bucket 1.20


Swell Factor - Bank to Truck Tray 1.25

For the contractor's loader mining waste, set the loader bucket fill factor to average. This should
equate to a factor of 0.72 on a heaped basis (0.88 on a struck basis) for a Front End Loader.

Runge Pty Ltd Page 11


March, 2002
TALPAC 8 TUTORIAL

Questions
1. What is the Loose Density in the loader bucket?

2. How would you use your own site specific fill factors?

3. What else will affect the filling of the bucket

Runge Pty Ltd Page 12


March, 2002
TALPAC 8 TUTORIAL

3. THE SHIFT ROSTER

Key Concepts: Roster, Delay, Scheduled, Unscheduled, Operating, Non-Operating

Technical Description
Working and operating hours for the loader and trucks are defined in the shift roster. The weekly shift
pattern is specified, and then lost shifts per year and delays within each shift are allocated. These lost
shifts and delays are divided into the following categories.

Scheduled lost shifts;


Unscheduled lost shifts;
Non-operating shift delays; and
Operating shift delays;

The choice of category for a delay depends on mine site work practices. By definition, scheduled delays
are those that may be fixed in time, eg. the public holiday on 25th December. Unscheduled delays are
delays that you expect, but don't know exactly when they will occur, for example clean-up around the
loader area and delays due to wet weather. Operating delays are those delays when the equipment's
engine is running. Conversely, non-operating delays are those delays when the equipment's engine is
not running.

Tasks

Set-up a roster template for the shift roster described below. Call it Tutorial Roster.

The contractor operates on two shifts per day, from Monday to Friday. In addition, there is one
over-time shift on Saturdays.

The only rostered days of the year that are not worked are Christmas Day and Good Friday.

The contractor annually allows for ten shifts lost due to industrial action and ten shifts lost as a
result of wet weather.

Each shift is ten hours long. The following delays occur within each shift:
Crib (meal) break 30 minutes operating
Delays either side of crib 2 x 5 minutes operating
Delay at start of shift 5 minutes non-operating
Delay at end of shift 5 minutes operating
Delays for blasting 5 minutes non-operating
Clean-up around loader 15 minutes operating

Refuelling is carried out outside normal production hours.

Runge Pty Ltd Page 13


March, 2002
TALPAC 8 TUTORIAL

Questions
1. What are the total annual working hours for the loader?

2. What are the total fleet operating shifts for the year?

Runge Pty Ltd Page 14


March, 2002
TALPAC 8 TUTORIAL

4. SELECTING A LOADER

Key Concepts: Loader database, Distribution, Loader methodology

Technical Description
The contractor wants to use Caterpillar 992G front end loaders. The characteristics of the loader have
been determined from historical data. We need to use this data to correctly define how the loader is to
be simulated.

Tasks

Right click on the list of loaders and choose Add. You will now be looking at the loaders section
of the equipment database.

Choose Caterpillar from the Manufacturer drop down list. Scroll down through the list of loaders
until you find the 992G. Click on the Select button.

You will now be back in the loader template. Call this template Contract Cat 992G.

The contractor's 992 loaders have an expected mechanical availability of 90% and each loader pass
takes 35 seconds. Change the loader pass time in seconds and the minutes will calculate
automatically and vice versa.

Runge Pty Ltd Page 15


March, 2002
TALPAC 8 TUTORIAL

Click on the Bucket Selection button. The buckets available for the 992 are shown in the drop
down list. Examine all the options available, click on the Auto Select button and see what effect
it has. When you have finished click on the Restore Defaults button and then click on OK.

Click on the Costing Data tab. The capital cost to the contractor of a 992G loader is $1,200,000.

The contractor bases its cash flow on a 10% salvage value at the end of the loader life of 25,000
hours or 5 years (whichever occurs first).

The loaders are depreciated at a rate of 15% on a straight line basis.

The operating cost consists of the following components:


Operating Labour $54.76/op.hr
Maintenance Labour $19.52/op.hr
Lube $3.79/op.hr
Tyre Replacement $11.01/op.hr
Wear Items $6.00/op.hr
Repair Parts $45.00/op.hr

Runge Pty Ltd Page 16


March, 2002
TALPAC 8 TUTORIAL

Major Overhaul $18.00/op.hr


Liquid Fuels $25.26/op.hr

Click on the Distribution Data tab, examine the options available but do not change anything.
Click on OK when you are finished.

Questions
1. What is the total operating cost per hour?

2. Why can the template name be different to the database equipment name?

3. What does the default bucket payload represent?

Runge Pty Ltd Page 17


March, 2002
TALPAC 8 TUTORIAL

5. SELECTING A TRUCK

Key Concepts: Truck database, Local Characteristics

Technical Description
Characteristics of the haul trucks in the fleet are stored in the truck template, which is structured in a
similar way to the loader template. Our example contractor uses Komatsu HD785-5 rear dump trucks.
The characteristics of the trucks are described below.

Tasks

Right click on the list of Truck Type 1 and choose Add. You will now be looking at the trucks
section of the equipment database.

Choose Komatsu from the Manufacturer drop down list. Scroll down through the list of trucks
until you find the HD785-5. Click on the Select button.

You will now be back at the truck template. Call this template Contract 785-5.

The contractor's trucks are equipped with standard motors and are designed to carry the
manufacturer's rated payload. The Komatsu HD785-5 trucks have an availability of 85%.

Runge Pty Ltd Page 18


March, 2002
TALPAC 8 TUTORIAL

Operational studies show a spot time at the loader is 24 seconds, dump spot time is 20 seconds
and a dump time of 30 seconds.
Note: changing the seconds will mean the minutes are updated automatically and vice versa.

Click on the Costing Data tab. The truck capital cost is $850,000. A 10% salvage value at the
end of the truck life of 30,000 hours or 6 years is assumed. The trucks depreciate at 25% on a
straight-line basis.

The operating cost consists of the following components:


Operating Labour $46.37/op.hr
Maintenance Labour $18.24/op.hr
Lube $2.59/op.hr
Tyre Replacement $10.91/op.hr
Wear Items $4.30/op.hr

Runge Pty Ltd Page 19


March, 2002
TALPAC 8 TUTORIAL

Repair Parts $24.08/op.hr


Major Overhaul $10.75/op.hr
Liquid Fuels $17.24/op.hr

Click on the Distribution Data tab, examine the options available but do not change anything.
Click on OK when you are finished.

Set the number of trucks to Auto, so that TALPAC estimates the number of trucks required to
keep the loader busy as follows:
Estimated Truck Cycle Time for Nominal Payload
=
Fleet Size Nominal Truck Truck Spot Time
+
Loading Time at Loader

Runge Pty Ltd Page 20


March, 2002
TALPAC 8 TUTORIAL

Questions
1. What is the total operating cost per hour for the truck?

2. When would you use the different truck types in the same simulation?

Runge Pty Ltd Page 21


March, 2002
TALPAC 8 TUTORIAL

6. SETTING-UP A HAUL CYCLE

Key Concepts: Segment, Rolling Resistance, Speed Restrictions, Forward and Reverse
Segments

Technical Description
To perform a simulation, TALPAC needs data regarding the haul route. This workshop describes how
this data can be converted into to a format required.

The loading segments are automatically included at the start of each new haul cycle.

Task

Click on the Edit Haul Cycle button to open the Haul Cycle window.

The drawing at the end of the workshop shows a typical haul profile on which the waste contract
is based. Conditions to be expected in the mine are listed below:
within 50 metres of the shovel and dump point, the truck speed is restricted to 30 km/hr;

around corners, trucks should not exceed 30 km/hr; and

when travelling down ramps, trucks must not exceed 40 km/hr.

Change the name of Haul Cycle 1 to Base Haul Route.

Add a new haul segment by clicking row 4 of the haul cycle and then either click on the Add
button on the toolbar or by using the right mouse menu.

Call the new haul segment Around Loader, the distance will be 50.0 metres, the maximum speed is
30 km/h and all of the other factors will use the default values.

The haul profile should be divided into the appropriate number of segments. The segments may
be of any length, but should have a constant grade, rolling resistance and load. Don't forget to
include loading, dumping and fixed time segments in the haul cycle and take into account the
speed restrictions.

Rolling resistance is expressed as a percentage of the component of the gross vehicle weight that is
normal to the ground surface. For guidance on rolling resistance values to use, access the table
from the rolling resistance column, right mouse click on one of the cells in the Rolling Resistance
column and choose Select. We will be using the average conditions for this tutorial, so click in the
average column of the row in the table that best describes the current haul segment.

Runge Pty Ltd Page 22


March, 2002
TALPAC 8 TUTORIAL

When you have added all of the haul segments needed, add the dumping segments.

As the haul route for the return journey is the same it is possible to use the Reverse all segments
option. Reverse all of the segments

Questions
1. When is a new segment required?

2. How many segments are required?

3. What other methods are available for constructing a haul route in TALPAC?

4. What is the benefit of using real names for segment titles?

5. What is the relationship between final and maximum speeds for segments?

Runge Pty Ltd Page 23


March, 2002
TALPAC 8 TUTORIAL

200m Corner

Top of Pit Ramp


= 300 Rl

300m @0%
@10
Top of Benc h Pit Floor

400m
= 270 Rl = 260 Rl
15

Base of Dump Ramp


0m

= 300 Rl

200m @10%
100m Corner

5 0m
50
m

Dump
= 320 Rl
m

= > Haul Route


50

Haul Cycle

Runge Pty Ltd Page 24


March, 2002
TALPAC 8 TUTORIAL

7. PRODUCTION ANALYSIS

Key Concepts: Calculation Type, Full Simulation, Stochastic, Excavation Target

Technical Description
Once the haulage system has been defined it is ready to be analysed. In assessing the productive
capacity of the system you have the choice of using the quick estimate or the full simulation. The other
types of calculations will be discussed later. Quick estimate assumes there is no variability in the truck
and loader parameters, and a deterministic analysis is performed.

Full simulation takes the variability of truck and loader parameters into account using a stochastic
analysis. Parameters that may be varied in the full simulation include loader bucket cycle time, loader
bucket payload, truck travel time, truck dumping time and truck availability.

The Excavation Target feature allows the user to specify a production target. When an excavation
target is specified the Production Summary Report lists how many days/years that it would take to
move the specified excavation target. The value for the target is independent on the measurement basis
chosen in the material template.

Tasks

Clicking on the Type of Calculation list box may access Quick Estimate. Select Quick Estimate
and either press the <F10> key or click on the Calculate button.

Similarly, selecting Full Simulation from the Type of Calculation list box and by using the <F10>
key or to click on the Calculate Results button to access Full Simulation.

View the simulation results for each option and compare the differences.

View the haul cycle details, the tyres and fuel consumption, and the cash flow screens. View the
defined travel time graphs to identify the key segments of the haul cycle.

Enter a production target of 2,500,000 bcm, run a Full Simulation and then view the results at
the bottom of the Production Summary Report.

Questions
1. Why is it useful to have different calculation types?

2. What is the vertical height difference that the load is being elevated through?

3. Why can you get different results for successive runs?

4. How long does it take to reach the production target?

Runge Pty Ltd Page 25


March, 2002
TALPAC 8 TUTORIAL

8. INCREMENTAL ANALYSIS AND RESULTS


TABLES

Key Concepts: Incremental Analysis, Results Table

Technical Description
The haul profile used so far is representative of haul routes at the mid-life of the waste contract. In the
early years the pit is shallower and in the later years it is deeper. The change in RL and the length of
the ramp out of the pit vary as follows:

Year Length of Pit Ramp

1 200 metres

2 300 metres

3 400 metres

4 500 metres

5 600 metres

The distance and elevation from the surface to the top of the waste dump do not change. In planning
we need to understand how the productivity requirements change for the life of the contract.

Also we are interested in seeing the results tabulated in a different format to the standard results.

Tasks

Based on this information, determine the productivity of the fleet for each year of the contract.
Choose the Incremental Analysis button.

In the Incremental Analysis window choose the Add button.

In the Incremental Item Selection window choose Haul Segment Distance from the Item dropdown
list. Choose Pit Ramp segment from the 4: Forward Segment dropdown list. Choose 15: Pit Ramp
(rev.) from the Reverse Segment dropdown list.

Set the First Value to 200 metres, the Last Value to 600 metres and the Step Value to 100 metres.
Click on OK.

Runge Pty Ltd Page 26


March, 2002
TALPAC 8 TUTORIAL

If the Incremental Analysis window looks like this, then click on Calculate.

Examine the information displayed in the Results Table.


Note: That the column headed Row 7: Distance: TT1 represents the Pit Ramp length.

Runge Pty Ltd Page 27


March, 2002
TALPAC 8 TUTORIAL

Try creating your own report by clicking on the Report button and then choosing fields from the
left-hand pane.

Produce a graph of the ramp length versus the fleet productivity. Highlight the rows in the
Results Table relating to the current run and then chose the Graph menu option.

From the X dropdown list choose Row 7: Distance: TT1 and choose Fleet Production Per Operating Hr
from the Y dropdown list.

Runge Pty Ltd Page 28


March, 2002
TALPAC 8 TUTORIAL

Try choosing Fleet Production Per Operating Hr from the Z dropdown list. What happens if you tick
the Group by checkbox?

Right mouse click on the graph and choose Chart Designer from the menu.

Try changing the chart type to a bar graph. Examine the options available and see what effect it
has on your graph.

Runge Pty Ltd Page 29


March, 2002
TALPAC 8 TUTORIAL

Questions
1. What is the key information?

2. How many variables are available for inclusion in the results table?

3. When should you consider purchasing another truck?

Runge Pty Ltd Page 30


March, 2002
TALPAC 8 TUTORIAL

9. FLEET SIZE OPTIMISATION

Key TALPAC Concepts: Optimisation Analysis, Marginal Economics

Technical Description
The optimum number of trucks in a fleet is a balance between productivity and cost. The fleet size
optimisation carries out a series of production analyses for a range of truck fleet sizes. The results are
summarised in a table displaying the fleet size, the fleet production and the discounted average cost.

The results can also be displayed on a graph. The optimum fleet size is that with the lowest unit cost of
production. The optimum fleet size will not necessarily have the highest production or provide the
required output.

Tasks

Create a copy of the Base Waste Contract haulage, hit the <F2> key and rename it Workshop 10 Fleet
Size.

Make a copy of the base haul cycle, and call it Workshop 10 Haul.

In Workshop 10 Haul, change the pit ramp distance to 2,000 m. Remember to change both the
forward and reverse segments of the pit ramp.

Configure the rest of this haul system to have the same loader, truck, material and roster
templates. Make sure you save this haul system after you have selected the appropriate items.

Do a Full Simulation and note the number of trucks.

Now determine the optimum number of trucks for the contractor's fleet. Choose the
Optimisation button.

Choose the Fleet Size radio button and then click on OK.

Runge Pty Ltd Page 31


March, 2002
TALPAC 8 TUTORIAL

Plot a graph of the Fleet size versus the marginal cost.

Compare the optimum with the truck match determined in the full simulation in the previously in
this workshop.

Export the Results Table by going to File|Export, click on the brows button and choose a
name and location for the file. Make sure the Excel 5File (.XLS) radio button is chosen and then
click on OK. Open up your results file in Excel and examine the data.

Questions
1. What is the marginal cost of assigning one more truck than the optimum?

2. Why are the marginal economics important, and not just the average cost?

3. What is the optimum fleet size?

Runge Pty Ltd Page 32


March, 2002
TALPAC 8 TUTORIAL

10. FLEET COMPARISON

Key Concepts: Haulage Systems

Technical Description
The contractor wishes to investigate the cost benefits of moving to larger equipment for the waste
removal contract. A new haulage system is going to be configured for the larger equipment. New
truck and loader templates will be created.

Tasks

Add a new Haulage System, called Workshop 11 Comparison. This will have the Tutorial roster, the
tutorial waste, and the Base Haul Route from the Basic Waste Contract haulage system.

Create a new template for both the truck and loader, the details of the larger equipment items in
which the contractor is interested are as follows:
Item Shovel Truck
Name Demag H 285 S Dresser 510E
Type Hydraulic Shovel Rear Dump Trucks
Capacity 16.0 cu.m heaped 136.14 tonne payload
Availability 90% 85%
Capital $2,000,000 $1,300,000
Salvage Value 10% 10%
Life in Years 8 8
Life in Hours 35000 35000
Depreciation type Straight line Straight line
Depreciation Rate 15% 25%
Total Operating Cost $222.73 $163.50
With this equipment each loader pass takes 30 seconds. Also for the trucks the spot time at the
loader is 30 seconds. The spot time at dump is 30 seconds and the dump time is 30 seconds.

Use the Total Operating Cost checkbox to enter the operating cost

Runge Pty Ltd Page 33


March, 2002
TALPAC 8 TUTORIAL

Compare the discounted average cost for the equipment fleet above with the equipment fleet used
in the workshop 10. In determining the discounted average cost, use the optimum truck fleet size
for each option.

Questions
1. Which equipment fleet would you recommend the contractor purchase?

2. What factors affect this decision?

Runge Pty Ltd Page 34


March, 2002
TALPAC 8 TUTORIAL

11. THE EQUIPMENT DATABASE

Key Concepts: User Defined Equipment

Technical Description
The equipment database contains a large range of trucks and loaders used in surface mining operations.
The data supplied in the equipment database represents standard equipment and has been verified by
the appropriate manufacturer. For equipment that is not in the database or that has been modified, the
user is able to set-up their own equipment items.

Tasks

Access the equipment database from either View|Equipment Database or the Equipment
Database button on the toolbar.

Use the Type, Manufacturer and Class drop down list to view a truck and a loader to see the
data that is stored in the database for each equipment type.

Create a user defined equipment item by copying a standard item of equipment to a new name. To
copy an item from the standard database to a user database go to Edit|Copy Equipment.
Rename your copy of the Komatsu HD785-5 to My Mines 785-5.

Runge Pty Ltd Page 35


March, 2002
TALPAC 8 TUTORIAL

Question
1. What role would User Defined equipment have at your operation?

Runge Pty Ltd Page 36


March, 2002
TALPAC 8 TUTORIAL

12. IMPORTING A HAUL CYCLE

Key Concepts: Importing a Haul Cycle From a Text File

Technical Description
In a previous workshop we have created a haul cycle by manually typing in the required details for each
segment. In TALPAC you can also import this data directly from a text file. In turn this text file can
be automatically generated in another system, such as a design package or a fleet monitoring / dispatch
system.

The text file import facility in TALPAC can be quite sophisticated, and in this workshop only a small
portion of the functionality will be used. For more advanced requirements please refer to the help
documentation, or contact Runge.

Tasks

In the Talpac8\Tutorials directory there is a flat text file called Test XYZ Space.txt. Open this
file with a text editor and inspect the layout. This file represents the co-ordinates of a haul route.
Close the file after inspection.

In TALPAC add a new Haul System called Workshop 13 Import.

Go to File|Import Haul Cycles From a Text File.

Click on the Add button and create a new template called Tutorial.

Click on the Browse button and find the file Test XYZ Space.txt.

Leave the First Import Line as 1, and also leave the Comment Character as ! Now click twice
on the Next Line button, so that line 3 of the file is shown in the viewer.

Set the Import Data Type radio button to X,Y,Z co-ordinates.

Enter appropriate field numbers for the entities. This is:


X coord 2

Y coord 3

Z coord 4.

All other fields should have a 0 value. This means that you will be accepting the defaults shown
for those fields.

Runge Pty Ltd Page 37


March, 2002
TALPAC 8 TUTORIAL

When complete, check the Reverse all segments setting load to Empty tick box , and then
click on OK.

Inspect the results in TALPAC. Check that two haul cycles Baso1 and Baso2 have been imported.

Questions
1. Why is the new haul cycle called Baso1?

2. How can this feature be used in your situation?

3. How else can the import facility be used?

Runge Pty Ltd Page 38


March, 2002
TALPAC 8 TUTORIAL

13. TALPAC OPTIONS

Key Concepts: Project Options, Customising TALPAC, Project Management, Feedback,


Project Properties

Technical Description
There are many variables and Options used in TALPAC that are not contained within any of the
templates that we have looked at so far. As well there are a number of ways of customising TALPAC
and other features of which you should be aware.

Tasks

Go to File|Project Properties. View the information available, click on the View Templates
List and Select a User Database buttons and examine the options available.

Using the Help pull down menu, select Feedback. If you click on the Email button an email to
Runges support desk is automatically generated with the feedback form included as an
attachment.

These following items are stored in the View pull-down menu. The main items are:
In Project Options there are the following: Truck Travel options; Loading options; Cash flow
options; Optimisation options; and, Bucket construction ratings;

In Customise TALPAC the items available are: General Options, Distribution Details and Set
Colours; and

In Project Management you can see all of the created Haulage systems in this project, create
new haulage systems, and run simulations on all of the haul systems.

Runge Pty Ltd Page 39


March, 2002
TALPAC 8 TUTORIAL

Questions
1. When should you change the options settings?

2. How can you tell the location of the current user database?

3. How can the project manager interact with mine planning?

Runge Pty Ltd Page 40


March, 2002
TALPAC 8 TUTORIAL

Answers
WORKSHOP 1: TALPAC Overview

1. What is in a TP7 file?


The TP7 file is the data file stored in your working directory that contains all of the data and
settings for the current project.

2. What are the 5 components of a haulage system?


Material, Roster, Loader, Truck and Haul Cycle.

3. What is a TALPAC project?


A TALPAC project is the collection of saved Haulage Systems that are in the same TP7 file.

4. Why would you want to print out the ALL PARAMETERS sheet?
For reference and auditing. For example it is useful to print this file to have as a backup of the
important TALPAC configuration settings. This is haulage system specific.

5. What are the options available on the right click of the mouse when a template name is highlighted?

6. What types of Haul Segments can be used?

Runge Pty Ltd Page 41


March, 2002
TALPAC 8 TUTORIAL

7. What is the difference between adding to a template list, and editing a template?
Editing a template overwrites the data that already existed in the template. Adding a new template
to the list means that a new template is created, and so all the original templates still remain.

WORKSHOP 2: THE MATERIAL TYPE

1. What is the Loose Density in the loader bucket?


1.83 t/m3 (See the figure below)

Runge Pty Ltd Page 42


March, 2002
TALPAC 8 TUTORIAL

2. How would you use your own site specific fill factors?
Change the Global variables table.

3. What else will affect the filling of the bucket?


Fragmentation, operator experience, weather conditions, visibility, bucket geometry.

WORKSHOP 3: THE SHIFT ROSTER

1. What are the total annual working hours for the loader?
4099 (See the figure below)

2. What are the total fleet operating shifts for the year?
464 (See the figure below)

Runge Pty Ltd Page 43


March, 2002
TALPAC 8 TUTORIAL

WORKSHOP 4: SELECTING A LOADER

1. What is the total Operating cost per hour?


The total operating cost for each loader is $183.34/operating hour.

2. Why can the template name be different to the database equipment name?
You may want to model variations of the same basic equipment.

3. What does the default bucket payload represent?


The amount of material that is actually in the bucket, not the bucket capacity.

Runge Pty Ltd Page 44


March, 2002
TALPAC 8 TUTORIAL

WORKSHOP 5: SELECTING A TRUCK


1. What is the total operating cost per hour for the truck?
The total operating cost for each truck is $134.48/operating hour.

2. When would you use the different truck types in the same simulation?
If you were simulating a fleet that had more than one type of truck.

WORKSHOP 6: SETTING-UP A HAUL CYCLE

1. When is a new segment required?


Whenever there is a change to the conditions which control velocity. Thus gradient, rolling
resistance and Speed restrictions.

2. How many segments are required?


See the figure below.

3. What other methods are available for constructing a haul route in TALPAC?
Importing data from a text file.

4. What is the benefit of using real names for segment titles?


So the user can visualise, and hence validate, the haul cycle data.

5. What is the relationship between final and maximum speeds for segments?
If a certain segment has a maximum speed, then the preceding segment should have the same speed
set as the final speed for it. Otherwise the truck may enter the next segment at an excessive speed.

Runge Pty Ltd Page 45


March, 2002
TALPAC 8 TUTORIAL

WORKSHOP 7: PRODUCTION ANALYSIS


1. Why is it useful to have different calculation types?
Mine planning requires different scenarios and options to be investigated. This means that
different functionality is required. As well this is useful to calibrate the model in Quick estimate
(deterministic) mode first.

2. What is the vertical height difference that the load is being elevated through?
60m.

3. Why can you get different results in successive runs?


Due to the stochastic distributions used in simulation.

4. How long does it take to reach the production target?


approx. 1.06 Years

WORKSHOP 8: INCREMENTAL ANALYSIS AND RESULTS TABLE


1. What is the key information?
Key Information is what you need to see, and so depends on the purpose of the simulation. In this
instance, cost, time, productivity, fleet size and length of haul would be key.

Runge Pty Ltd Page 46


March, 2002
TALPAC 8 TUTORIAL

2. How many variables are available for inclusion in the results table?
250.

3. When should you consider purchasing another truck?


In year 3. But what else should be considered?

WORKSHOP 9: FLEET SIZE OPTIMIZATION

1. What is the marginal cost of assigning one more truck than the optimum?
$2.97 / bcm.

2. Why are the marginal economics important, and not just the average cost?
Average costs disguise the impact of individual truck assignment.

3. What is the optimum fleet size?


The run with the lowest fleet discount cost.

WORKSHOP 10: FLEET COMPARISON

1. Which equipment fleet would you recommend the contractor purchase?


The larger fleet is the pure cost choice, but is this correct?

2. What factors affect this decision?


Cost of capital, changes to working hours, flexibility of contract.

WORKSHOP 11: THE EQUIPMENT DATABASE

1. What role would User Defined equipment have at your operation?


You can set up the specifications for the Truck and Loader which exactly match your configuration,
rather than relying on the standard data.

WORKSHOP 12: IMPORTING A HAUL CYCLE

1. Why is the new haul cycle called Baso1?


Set by the variable on line 2 of the import file. Otherwise it will be imported and called the same as
the import file name.

Runge Pty Ltd Page 47


March, 2002
TALPAC 8 TUTORIAL

2. How can this feature be used in your situation?


Eg From the mine design package a string can be digitised which represents the haul route. This
string can then be exported to a text file as a series of X,Y, Z points. From there it can be
imported directly into TALPAC.

3. How else can the import facility be used?


To import complete Haul Systems.

WORKSHOP 13: TALPAC OPTIONS

1. When should you change the options settings?


Only after consideration of what they are doing. It is also suggested that if these are changed, then
make sure that changes are properly recorded. The ALL PARAMETRS print outs, and user
defined reports in the Results Tables are two good ways of doing this.

2. How can the project manager interact with mine planning?


Can make the analysis of multiple simulations easier and more straight forward.

3. How can you tell the location of the current user database?
Under View | Project Properties the location and name of the current user database is shown.

Runge Pty Ltd Page 48


March, 2002
TALPAC 8 TUTORIAL

Talpac Commands
Embedded Buttons

View All Parameters Optimisation Calculation

View Loading Analysis Incremental Analysis

Calculate Full Simulation


View Project Manager
or Quick Estimate

Edit Haulage System Edit Loader Template

Edit Material Template Edit Truck Template

Edit Roster Template Edit Haul Cycle

Runge Pty Ltd Page 49


March, 2002
TALPAC 8 TUTORIAL

Toolbars
Save Help

Print Insert haul segment

Print preview Delete haul segment

Equipment database Paste copied or cut segments in reverse

Edit haul system Reverse all haul segments

Edit material Undo last change

Edit roster Redo last change

Edit loading unit Export haul cycle

Edit truck Select rolling resistance

Edit haul cycle Set speed to maximum

View project manager Set curve data

Add template Set truck load to empty

Edit template Set truck load to full

Delete template Set load time spot time or truck numbers to


automatic
Copy template

Function Keys
F1 Help F9 Run Quick Estimate
F2 Edit F10 Run Full Simulation

Runge Pty Ltd Page 50


March, 2002

Das könnte Ihnen auch gefallen